MARCH 14, 2016 m enr.com BEST OF THE BEST ENR’S TOP PROJECTS OF 2015 EDITORS’ CHOICE Stanford Energy System Innovations Stanford University, Calif. Winners BEST OF THE BEST 2015 THIS YEAR’S JUDGES COSEMA “CONNIE” CRAWFORD Senior Vice President, Rail/Transit Global Practice Leader Louis Berger 2 ENR March 14, 2016 enr.com ROGER FRICKE Senior Vice President, Preconstruction MATT Construction ANDY FRY Chief Operating Officer Magnusson Klemencic Associates LAWRENCE A. HANSEN Consulting Geotechnical Engineer MARK HASSO Professor of Construction Management Wentworth Institute of Technology ERLEEN HATFIELD Principal Buro Happold CARL W. HEINLEIN Senior Safety Consultant American Contractors Insurance Group ENERGY/INDUSTRIAL l Submitted By ACCO Engineered Systems Stanford Energy System Innovations Stanford, Calif. REGION California PROJECT TEAM OWNER Stanford University LEAD DESIGN FIRM/MEP ENGINEER Affiliated Engineers Inc. CONTRACTOR Whiting-Turner STRUCTURAL ENGINEER Rutherford + Chekene CIVIL ENGINEER BKF Engineers ARCHITECT ZGF Architects MEP CONTRACTOR ACCO Engineered Systems CONTROL SYSTEM Johnson Controls Inc. To university engineers, the Stanford Energy System Innovations (SESI) project represents nothing less than a revolution in the way campuses in the U.S. should be heated and cooled. Stanford University eagerly uses SESI to demonstrate to corporate, municipal and other school officials that they, too, can save energy, reduce water use and drastically reduce greenhouse-gas emissions. The $485-million effort—in fact, four projects in one—replaces an aging 50-MW natural-gas-fired cogeneration plant with a new heatrecovery system to provide heating and cooling to the campus. A new 80-megavolt ampere electrical substation brings electricity from the grid and direct-sourced renewable-energy suppliers. Crews also converted 155 campus buildings from steam to hot-water distribution and installed a 22-mile-long network of new pipe. “You could take any one of those four projects and it would be a significant engineering challenge,” says Krista Murphy, principal with lead design firm Affiliated Engineers Inc. (AEI). “We were tackling all of those at the same time.” Since completion last April, facilities managers have flocked to study SESI. “We’ve had overwhelming demand—tours are booked months in advance,” says Joseph Stagner, executive director of sustainability and energy management at Stanford. Leaders from other universities, the President’s Council of Advisors on Science and Technology and even France’s ambassador have made the pilgrimage to SESI. Change of Heart To learn how Stanford cut campus energy use by 50% and dropped its greenhouse-gas emissions by 68% in just two and a half years, visitors start at SESI’s heart—the 125,614-sq-ft central energy facility (CEF), located on the west side of the campus. The CEF houses what Stanford calls the star of the show: three heat-recovery chillers—the largest in the U.S.—that strip waste heat from 155 campus buildings via a closed chilled-water loop and use it to preheat a separate closed hot-water loop that distributes heat to the same buildings. From dorms to hospitals to sports facilities, a variety of campus structures provides a huge heat-recovery potential. The system captures 57% of building waste heat, reusing it to meet 93% of campus heating needs. For most of the year, the system precludes the need for cooling towers to discharge excess heat, which reduces water consumption on campus by 15%. Each heat-recovery chiller (HRC) provides a 2,500-ton cooling CHUCK JABLON Senior Executive Vice President Skanska USA ALEISHA JAEGER Construction Director Gilbane Building Co. MICHAEL KAUFMAN BARRY L. LACY Partner Claims/Work Zone/ Audit Engineer Goettsch Partners Louisiana Dept. of Transportation & Development GATHERING SPACE Tour groups from all over the world congregate at the staircase in the main courtyard to learn about SESI. The stairs lead to a twostory administration building that wraps around a hot-water storage tank. capacity for chilled water and simultaneously can produce 40 million BTUs of heat per hour. The HRCs send out chilled water to the campus at 42°F, which returns at 56°F to 60°F. The heat removed from the chilled water as it is cooled back down to 42°F reheats spent hot water (which returns to the CEF from campus at 130°F) back up to 160°F to 170°F to supply heating. Additional efficiency results from the switch from steam heat to hot water. Line loss of up to 20% in the old steam system dropped to under 4% with hot-water piping. The switch also saves the school several million dollars a year in operations and maintenance. Further, the school’s previous cold storage existed in the form of ice. “Chillers take about 25% more energy to make ice than they do cold water,” he says. By using out-of-date systems that create steam and ice, “America has been hitting it with a sledgehammer because energy was so cheap, and ROBERT MATTHEW JOHN A. SPORIDIS NOBLETT Managing Principal Partner Vanderweil Behnisch Architekten Engineers DAVID WESSIN Vice President Safety and Loss Control PHOTO LEFT BY TODD QUAM, COURTESY JOHNSON CONTROLS; TOP RIGHT BY MATTHEW ANDERSON; BOTTOM RIGHT BY ROBERT CANFIELD Coastal Construction Group enr.com March 14, 2016 ENR 3 control-system subcontractor Johnson Controls to develop it into a viable commercial product. Dubbed the Central Energy Plant Optimization Model (CEPOM), the algorithm performs a 10-day look-ahead every 15 minutes, considering campus loads, weather patterns, price of electricity, available equipment and many other factors. It then computes the optimal dispatch plan, and it can even be used as an “autopilot” to run the plant. The program performs about 30% more efficiently than what a human can do, Stagner says. Led by contractor Whiting-Turner, construction began in 2012. While one crew assembled the complex plant, another worked its way through the active campus to install 22 miles of new pipe. Hot-water pipe can be installed more quickly and at less expense than steam pipe, which needs to be buried to a 15-ft depth—below all other utilities—to reduce the risk of heat damage from steam leaks. By contrast, the pre-insulated hot-water pipe system, sourced from Denmark, was buried 3 ft to 5 ft below the surface, without the need to construct concrete vaults or anchors. As a result, crews installed the system in two and a half years, instead of the 10 years it would have taken to replace the steam pipes. The old steam pipes remain abandoned in place. To convert each campus building from steam to hot water, the team designed a standardized heat-exchanger skid, with only the capacities varying by building. “This allowed the long-lead equipment to be ordered directly by Whiting-Turner before the mechanical subcontractors were hired. The prefabrication allowed building shutdowns to be much shorter, with less disruption to research and building occupants,” says Damon Ellis, Whiting-Turner vice president. Converting 155 buildings—while the CEF was still under construction and the cogen plant continued to provide steam heat—presented the team with a logistical puzzle. To solve this, AEI turned to regional heat exchangers—also skidmounted—which converted the cogen’s steam to hot water. Then, a mini hot-water loop transported the water to each pre-converted building. “Use of the regional heat exchangers ENERGY TRANSFER Three heat-exchange chillers (top) strip waste heat from the chilledgave us the single most important ability to execute this job,” water-loop return and use it to reheat partially the hot-water-loop return. The chillers work in says Michael Bove, principal with AEI. harmony with thermal storage tanks and other components (bottom). As part of the new substation, crews placed nearly 40 miles of copper wiring underground. Four miles of overlap between the that’s how things evolved.” wiring and piping allowed crews to work more efficiently and reduced The CEF’s thermal storage system contains two 5-million-gallon tanks campus disruption. to store cold water and a 2.3-million-gallon tank for hot water. The tanks While some may balk at the $485-million price tag, the project was double as reservoirs for power, allowing flexibility to operate the heat“completely driven by astute economics that allow this university to have recovery chillers and other equipment during times of lower energy pricing such a well-crafted and well-performing endowment,” Stagner says. “It’s or when outside air temperatures are optimal. For example, when it’s hot smart business.” during the day, excess heat can be converted and stored as hot water, Stanford carefully studied multiple options, including replacing the instead of being rejected out of evaporative cooling towers, and then used natural-gas cogen plant, and found that the heat exchange system would during the cooler nighttime hours. actually cost $459 million less over a 35-year life cycle while providing A two-story administration building surrounds a small plaza, which has environmental and efficiency benefits. the hot-water thermal storage tank at its center. The tank, painted Stanford “One of the things that we’ve talked to other universities about is to not be red and lit at night, evokes a beating heart at the center of a “system that too taken aback by the enormity of this project,” Bove says. “Any university pumps energy around the campus,” says architect Joseph Collins, partner could do bits and pieces that have happened here. Stanford just had the with ZGF Architects. vision and ability, both financially and scope-wise, to do it all at once.” Large expanses of glass provide transparency into the areas that house And the technology continues to improve. Stanford’s real estate the HRCs and other mechanical equipment. Vivid colors clearly demark the division retained AEI and architect ZGF to design a new, 1.5-million-sq-ft complex piping in a way that provides visual clarity to students and visitors. campus to house 2,300 Stanford employees in Redwood City. Due to For example, light-blue piping indicates the cold-water loop returning from efficiencies in the new buildings and their heat exchangers, the system campus, while dark blue pipe contains re-chilled water after the heat has can operate with water heated up to just 110°F, instead of the 160°F been removed. Similarly, hot-water pipes are painted orange and red. needed to heat the main campus. In fact, the team estimates the heat “We do many heat-recovery chillers, but I don’t think we have any that pumps at the new facility will operate at 0.7 KW per ton, instead of the 1.3 are showcased the way this is, with glass surrounds and strong colors,” KW per ton measured at SESI. Murphy says. “All of it tells a story, even at the equipment level.” “That’s the evolution of this,” Bove says. “As the temperature comes To control the complex system, Stagner spent months programming down, the heat-recovery equipment gets more efficient.” n a control “brain” that models, operates and verifies performance By Scott Blair efficiency at the facility. After patenting the system, Stanford tasked Excerpted from Engineering News-Record, March 14, 2016, copyright by BNP Media II, LLC. with all rights reserved. This reprint implies no endorsement, either tacit or expressed, of any company, product, service or investment opportunity. #C48684 Managed by The YGS Group, 800.290.5460. For more information visit www.theYGSgroup.com. PHOTO TOP BY MATTHEW ANDERSON; IMAGE BOTTOM BY AEI Winners BEST OF THE BEST