Review of the Impacts of Distributed Generation on Distribution Protection Robert F. Arritt Senior Member, IEEE Roger C. Dugan Fellow, IEEE 2015 IEEE Rural Electric Power Conference Asheville, NC April 20th-22nd, 2015 Background • This report focuses on the results of an industry survey EPRI has conducted on distribution protection practices to accommodate DG*. • The ultimate goal of this survey was to review existing protection practices and determine what lessons have been learned. • From this research, gaps/needs have been identified that will result in further EPRI research. *EPRI Survey on Distribution Protection: Emphasis on Distributed Generation Integration Practices. EPRI, Palo Alto, CA: 2013. 3002001277. 2 Overvoltage Concerns • 75% of participants selected overvoltages and islanding as biggest concern DTT Single-Line To Ground Fault 69/34.5 Substation DG 34.5/.66 + 69kV/_0 Sub_Gnd V_Source + + + DG_Gnd Va DG 1.73 pu Vc 1.73 pu Vb Events resulted in sustained overvoltages on the primary side of the substation transformer 3 660V 5 MW Interconnection Transformer • Inverter based system • Non-inverter based system Grounded-wye / Grounded-wye Grounded-wye / Grounded-wye No preference Grounded-wye / Delta (primary side grounded) Grounded-wye / Delta (primary side grounded) Delta / Grounded-wye (primary side delta) Delta / Grounded-wye (primary side delta) No preference Grounded-wye / Delta (With a reactively grounded primary side wye) Grounded-wye / Delta (Including reactively-grounded primary side neutral) Delta / Grounded-wye (With a reactively grounded wye on the DG side) No interconnection transformer required No interconnection transformer required 0% 0% 10% 20% 30% 40% 50% 4 10% 20% 30% 40% 50% Ground Fault Overvoltage Testing Delta / Wye • 2014 EPRI Report: – Product ID: 3002003233 “Protecting the Modern Distribution Grid: Preliminary Inverter Characterization for Overvoltages” Wye / Wye 5 Protection Supervision Concerns • Multiple events of inverters not turning on or cycling off due to overvoltages associated with high penetration. Voltage After DG ANSI Range A Upper Limit ANSI Range A Lower Limit Substation Before DG Distance End of Feeder • Reported problems of DG operators changing initial protection settings resulting in high voltages at PCC – Resulted in complaints from other customers of electronic equipment problems/failures 6 Impacts of System Overvotages • If you ever experienced any sustained primary overvoltages associated with DG interconnections, what was impacted, if anything? • Surge arrester failure would be one expected consequence, particularly on US systems that exploited reduced insulation levels to apply lower-cost, lowervoltage arresters. No Damage • Relay operation for overvoltages is also a common complaint, particularly for solar PV systems. Surge Arrester Failures Resulted in relaying activation due to overvoltages or… Load Failures Transformer Failure 0% 10% 20% 30% 40% 50% 60% 7 Anti-Islanding • Have communications technologies been added to your system to communicate between the feeder relaying and interconnected DG? • How is anti-islanding being addressed? Under/Over Voltage Fiber Optic Under/Over Frequency Radio Depend on inverter Controls Telephone Transfer Trip None added Reverse Power Protection as backup Spread Spectrum Communications Minimum to Maximum Generation Limits placed on DG penetration Power Line Carrier Rate of Change of Frequency (ROCOF) Two-Way Pagers 0% 20% 40% 60% 80% 100% Not applicable Note: No utilities that were interviewed actually use Rate of Change of Frequency (ROCOF) for islanding detection although 20% of respondents recognized it as an option for protection. 0% 8 10% 20% 30% 40% 50% 60% Additional Gaps Identified • Open-Phase protection – Some stated that it is the responsibility of the customer. – Some determined that it meets the requirements of IEEE Std 1547 the DG is able to protect against this event. – Two utilities identified open-phase concerns in commissioning tests. 9 Conclusions • The survey results found that DG interconnection protection practices vary significantly from utility to utility. • Despite different practices, the basic objectives: – operate reliably and safely, – operate without degrading electric service to nearby customers, – and operate without compromising utility system integrity. • By far, the protection issue of most concerns are islanding and overvoltages, in particular, overvoltages occurring following an islanding event. 10 2015 EPRI Work • Continue testing with additional islanding scenarios, e.g. fault current contribution, islanding, open conductor, etc. • Testing of additional inverter models to establish a representative sample • Continue to build on the inverter models with improved test data. • Provide model verification with this additional test data. Incorporate new modeling techniques to allow for additional inputs that impact inverter response. 2014 Tech update Lab Testing Incorporate test results into the model to predict system response. 2015 Technical Update 11 Together…Shaping the Future of Electricity