ASSAM POWER DISTRIBUTION COMPANY LIMITED BID DOCUMENT FOR Strengthening & Upgradation of Sub-transmission and Distribution works of project areas Nagaon, Morigaon, Dhing, Doboka, Jagiroad, Hojai & Lanka UNDER NAGAON ELECTRICAL CIRCLE, APDCL (CAZ) ON “TURNKEY” MODE VOLUME - II SCHEME: R-APDRP (Part-B) PACKAGE - II NIT No: APDCL /CGM (PP&D) /R-APDRP/Part-B/NGN EC MAY’2012 Technical Specification PART-Y STANDARD TECHNICAL SPECIFICATION SECTION -I GENERAL REQUIREMENTS The bidder shall comply with the following general requirements along with other specifications. 1.0 QUALITY ASSURANCE PLAN 1.1 The bidder shall invariably furnish the following information along with his offer failing which the offer shall be liable for rejection. Information shall be separately given for individual type of equipment offered. i) The structure of organization ii) The duties and responsibilities assigned to staff ensuring quality of work iii) The system of purchasing, taking delivery and verification of materials iv) The system for ensuring quality of workmanship v) The quality assurance arrangements shall confirm requirement of ISO 9001 on ISO 9002 as applicable. vi) Statement giving list of important raw materials, names of sub-supplies for the raw materials, list of standards according to which the raw material are tested, list of tests normally carried out on raw material in the presence of suppliers representative, copies of test certificates. to the relevant vii) Information and copies of test certificates as on (i) above in respect of bought out items viii) List of manufacturing facilities available ix) Level of automation achieved and list of areas where manual processing exists. x) List of areas in manufacturing process, where stage inspections are normally carried out for quality control and details of such test and inspection. xi) List of testing equipment available with the bidder for final testing of equipment specified and test plant limitation, if any vis-a-vis the type. Special acceptance and routine tests specified in the relevant standards. These limitations shall be very clearly brought out in "Schedule of Deviations" from the specified test requirement. 1.2 The contactor shall within 30 days of placement of order, submit the following information to the purchaser. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 1 Technical Specification i) List of the raw material as well as bought out accessories and the names of subsuppliers selected from those furnished along with the offer. ii) Type test certificates of the raw material and bought out accessories if required by the purchaser. iii) Quality Assurance Plant (QAP) with hold points for purchasers inspection. QAP and purchasers hold points shall be discussed between the purchaser and contractor before the QAP is finalized. The contractor shall submit the routine test certificates of bought out accessories and central excise asses for raw material at the time of routine testing if required by the purchaser and ensure that the quality assurance requirements of specification are followed by the sub-contractor. 1.3 The Quality Assurance Programme shall give a description of the Quality System and Quality Plans with the following details. i) Quality System The structure of the organization. The duties and responsibilities assigned to staff ensuring quality of work. The system of purchasing, taking delivery of verification of materials. The system of ensuring of quality workmanship. The system of control of documentation . The system of retention of records. The arrangement of contractor internal auditing. A list of administrator and work procedures required to achieve contractors quality requirements. These procedures shall be made readily available to the purchaser for inspection on request. ii) Quality Plans An outline of the proposed work and program sequence. The structure of contractor's organizations for the contract. The duties and responsibilities ensuring quality of work. Hold and notification points. Submission of engineering documents required by this pecification. The inspection of the materials and components on request. Reference to contractors work procedures appropriate to each activity. Inspection during fabrication/construction Final inspection and test. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 2 Technical Specification SECTION-2 TECHNICAL SPECIFICATIONS FOR 33/11kV POWER TRANSFORMER 1.0 SCOPE OF SPECIFICATION: 1.1. : This specification is intended to cover design, manufacture, assembly testing at manufacturer‟s works, supply and delivery of three phase 50HZ, 33/11 KV Delta/Star, Vector Group DY 11, two windings copper would outdoor type, oil immersed, naturally air cooled Power Transformer with off load tap changer for 10MVA , 5 and 2.5MVA transformer. 1.2. The transformer offered shall be complete with all parts and accessories which are necessary for their efficient and satisfactory operation The Transformer and all associated oil filled Equipment shall be supplied complete with insulating new oil required for first filling including 10% extra oil for future use during commissioning. The Transformer tank shall be dispatched completely filled with oil and the balance oil shall be supplied in non returnable sealed drums along with the Transformers. 1.3. Such parts and accessories shall be deemed to be within the scope of this specification whether specifically mentioned or not. Main tank body may be delivered in unpacked condition, but delicate parts like indicating meter, radiator, conservator, Pressure Relief Valve, equalizer pipe, buchholz relay etc. shall be packed to avoid damage due to transportation. 1.4. It may be noted that the Power Transformer must meet the following minimum criteria. Failure to comply with the requirements may results in rejection of the BID as non-responsive: 1.5. The Manufacturer must have designed, manufactured, type tested and supplied power transformers in at least two power utilities of similar rating which are in successful operation for at least 5 (Five) years as on the date of bid opening. Which should be substantiated by furnishing performance report by the official of the rank of minimum DGM/SE 1.6. The Manufacturer should have in-house Auto Clave facility 1.7. Impulse Test, Temperature Rise and Loss Measurement shall be carried out at CPRI / NABL accredited Laboratory. . 2.0 : ISOCERAUNIC CONDITION: 2.1. For the purpose of designing, the following condition shall be considered: 1. Maximum temperature of air in shade 40°C 2. Minimum temperature of air in shade 2°C 3. Maximum temperature of air in sun 45°C 4. Maximum humidity 100% 5. Average number of thunder storm days 45 Days per annum 6. Maximum rainfall per annum 3500 mm 7. Average rainfall per annum 2200 mm 8. Wind pressure 97.8 Kg/m2 9. Altitude above MSL 100 to 1000 M 3.0 APPLICABLE STANDARDS 3.1. Unless otherwise stated, transformer shall be designed, constructed and tested in accordance with provisions contained in latest revisions of following Indian standards and Rules. i) IS : 2026 ii) R.E.C. Manual 10/1976 iii) C.B. I.P. Manual on Transformer Technical Report 1: Section : A.D. (Revised: 1987) Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 3 Technical Specification iv) C.B.I.P. Technical Report No. 72 (June: 1989) v) Indian Electricity Rules, 1956 (Amended up to date) vi) IS : 2099 Bushing for alternating voltage above 1000 volt vii) IS : 6600 Guide for loading of oil immersed transformer viii) Specification for Transformer oil (IS-335 & IS-1866,1983) ix) Other applicable Indian Standards. 4.0 GUARANTEES 4.1. The bidder shall guarantee among other things the following: a) Quality and strength of the material used. b) Adequate factors of safety for all parts of equipment to withstand the mechanical and on electrical stresses developed therein. These will be stated in the tender. c) Suitability of the design and workmanship of the equipment for the conditions envisaged in the specification. d) Efficiencies, Temperature rise and other performance data on equipment which shall be furnished in the tender. 5.0 WARRANTEES 5.1. The bidder shall be responsible for replacing at site free of cost any part or parts of the equipment that may prove faulty or fail manufacturing defects on one or more of the reasons given in clause Error! Reference source not found. stated above within 5 (five) years commencing from the date of commissioning 5.2. In case of failure of the transformer, the supplier shall take back the faulty transformer from its plinth for repair at their own cost (or replace the transformer with a new transformer) and deliver, at their own cost, unload at the destination sub-station transformer plinth within 45 days, from the date of intimation of defects to the satisfaction of the owner, at free of cost. If the repair/replacement will not be completed within 45 days, then the supplier shall pay penalty @ 0.5% of the contract price for each calendar week of delay from the end of 45 days from the date of intimation of defects. Also, the Purchaser reserves the right for forfeiture of the total Composite Bank Guarantee and all the Securities, available with ASEB, in case the Supplier fails to pay the penalty by one month before the expiry of the guarantee period. Also, this will be taken as adverse in all future tenders. 5.3. The bidder shall furnish copies of test certificates of materials used for manufacture and also the test certificates of the tests conducted on the equipment after manufacture. The contractor shall also furnish the test certificate of bought out components for approval by the purchaser. 6.0 MISCELLANEOUS 6.1. Padlocks along with duplicate keys as asked for various valves, marshalling box etc. shall be supplied by the contractor, wherever applicable. 6.2. Foundation bolt for wheel locking devices of Transformer shall be supplied by the bidder. 7.0 DELIVERY SCHEDULE: 7.1. The equipment shall be delivered FOR Destination as per schedule specified in the BPS 8.0 CONFLICT IN CLAUSE: 8.1. In case of any conflict between the Specific Technical Requirements and General Technical Requirements the requirements indicated as Specific Technical Requirement shall prevail over the General Technical Requirements Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 4 Technical Specification 9.0 DEVIATION FROM SPECIFICATION 9.1. Normally the offer should be as per Technical Specification without any deviation. But any deviation felt necessary to improve utility, performance and efficiency of equipment or to secure overall economy shall be mentioned in the „Schedule of deviations” with full justification, supported by documentary evidence. Such deviations, suggested, may or may not be accepted. But deviations, not mentioned in the “Deviation Schedule” will not be considered. 10.0 DRAWINGS INCORPORATING THE FOLLOWING PARTICULARS SHALL BE SUBMITTED WITH THE BID: 10.1. The following drawings and details shall be furnished in triplicate along with the bid : 10.2. General Arrangement outline drawing with plan, elevation and end views showing various dimensions of transformer and its vital component including height of the bottom most portion of bushing from the bottom of base channel and also indicating thereon physical centre line and position of centre of gravity. 10.3. Details of various types of bushing. 10.4. Three copies of sketches for height of crane hook above ground for lifting and untanking core, shipping dimensions, complete lists of fittings and devices, net weights of core, winding, tank, radiator, oil, conservator and total weight, fixing arrangement of transformer in foundation. 10.5. Illustrative & descriptive literature of the Transformer. 10.6. Maintenance and operation Instructions. 10.7. Type test certificates of similar transformers. 11.0 RATING AND GENERAL PARTICULARS: Type: Core type, three phase, oil immersed, step down, two winding copper wound transformer for outdoor installation. 11.2. Standard Rating: 11.1. Continuous with off circuit taps as mentioned in the schedule of requirement. 11.3. Continuous Maximum Rating and Overloads: As regards maximum rating and temperature rise, all transformers shall comply with the appropriate requirement of Indian Standards For the purpose of consideration of maximum temperature rise of oil and winding, the following ambient temperatures are assumed. i) Cooling medium : Air ii) Maximum Ambient Air temperature: 50 °C. iii) Maximum daily average ambient Air temperature: 40 °C. iv) Maximum yearly weighted average temperature: 32 °C . The transformer may be operated without danger on any particular tapping at the rated KVA provided the voltage does not vary by more than +10% of the voltage at that tapping. 11.5. The transformer should be suitable for continuous operation with a frequency variation of +3% from normal 50Hz. Combined voltage and frequency variation should not exceed the rated V/f ratio by 10% 11.4. DUTY UNDER FAUALT CONDITION It is to be assumed that normal voltage will be maintained on one side of the Transformer when there is a short circuit between phases or to earth on the other side. 11.8. The transformer may be directly connected to an underground or overhead line and may be switched into and out of service together with or without its associated incoming/outgoing line. 11.9. The thermal ability to withstand short circuit shall be Two seconds (2 Sec.) without injury for 3 phase dead short circuit at the terminals. 11.6. 11.7. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 5 Technical Specification 12.0 GENERAL TECHNICAL PARAMETERS SN 9. 10. 11. 12. 13. Particulars Rating Number of Phases Vector group Type of installation Frequency Cooling Medium Type of Cooling Highest continuous system Voltage High Voltage Low Voltage Winding Connection Material High Voltage Winding Low Voltage Winding Method of System Earthing 14. Type of Tap Changer 15. Range of Tapping 16. 18. 19. Type of Insulation Insulation Level a) Type of insulation b) One minute power frequency withstand Voltage(kV rms) c) Lightning Impulse withstand voltage Terminal Details 33kV Termination 20. 11 KV Termination 1. 2. 3. 4. 5. 6. 7. 8. 17. 10MVA 5MVA Three Dyn-11 Outdoor 50HZ ( +/- )3% Insulating Oil ONAN 2.5 MVA :36kV :12kV Electrolytic Copper DELTA STAR Solidly grounded on LV side 10 MVA 5 MVA 2.5 MVA OFF OFF OFF Load Load Load (+) 3% to (-) 9% in steps of 3% on HV side and 33kV 11kV Uniform 70kV Uniform 28kV 170 75 (i) ACSR/AAAC Wolf conductor, Bus, (or IPs tube as applicable) for connecting to bushing terminals. Cable 300/630 mm2, 1-core Al. Armoured XLPE Cable 21. Maximum Temperature rise over ambient of 50° C a) Temperature rise of top oil 40° C (measured by Thermometer b) Temperature rise of 45° C winding resistance) C) Maximum Winding 105° C temperature in Deg. C d) Maximum Permissible 250° C value of Average temperature of winding after 3 sec Maximum Permissible short circuit: (measured Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. by 6 Technical Specification 12.1. Over load capacity 12.2. NOISE LEVEL AT RATED VOLTAGE & FREQUENCY: As per NEMA Pub TR-1. 13.0 : As per IS: 6600 GUARANTEED LOSSES 1. 2. 3. Impedance at rated MVA at 8.35% 75° C without (-) ve tolerance No Load Loss 6.0KW Load Loss at 75° C 44.0KW 7.15% 6.25% 4.0KW 24KW 2.1KW 14.0.0KW 13.1. Tolerance of losses shall be guided by the relevant clauses of relevant IS standard. The bidder shall state both no load loss and load loss at rated voltage and frequency and loss figures shall be firm and guaranteed. 14.0 Evaluation of Losses: For the purpose of comparison of bids, the capitalized cost of iron loss (KW) and load losses (KW) shall be added to the quoted price of transformer at the following rates. 14.1. Iron loss per KW – Rs. 287 834.00 Copper loss per KW – Rs. 86349.00 14.2. If any or all actual losses after test are found to exceed the guaranteed value, the penalty will be imposed on the excess loss over the corresponding guaranteed loss (any or all). The penalty shall be calculated for the excess of no load loss and for the excess of the load losses at rates specified above. For fraction of a KW the penalty shall be applied prorate basis. If the test figure of. losses are less than the guaranteed value, no bonus will be allowed. Any changes in the figure assigned for transformer losses will not be permitted after opening of bids and bid evaluation will be carried out on the basis of information made available at the time of bid opening. 15.0 SHORT CIRCUIT CALCULATIONS 15.1. Manufacturer shall submit theoretical calculations in support of the ability to withstand short circuit on consideration of highest value that may occur. 16.0 PERFORMANCE CERTIFICATES Copies of performance certificates of sImilar Equipment supplied to various utilities shall have to be furnished along with Tender 16.1. 17.0 LIST OF PAST SUPPLIES The bidder shall furnish documents in support of Supply, Delivery of similar Equipment indicating thereon names of the organization, quantity ordered, quantity supplied along with tender. 17.1. 18.0 DESIGN, STANDARDIZATION AND GENERAL CONSTRUCTION FEATURES 18.1. .All material used shall be best quality and of the class most suitable for working under the conditions specified and shall withstand the variations of temperature and atmospheric conditions without distortion or deterioration or the setting up of undue stresses which may impair suitability of the various parts for the work which they have to perform. 18.2. Large parts, particularly removable ones, shall be interchangeable. Pipes and pipe fittings, screws, studs, nuts and bolts used for external connections shall be as per the relevant standards. Steel bolts and nuts exposed to atmosphere shall be of hot deep galvanized Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 7 Technical Specification Nuts, bolts and pins used inside the transformers and tap changer compartments shall be provided with lock washers or locknuts. Exposed parts shall not have pockets where water can collect. 18.4. Internal design of transformer shall ensure that air is not trapped in any location. Material in contact with oil shall be such as not to contribute to the formation of acid in oil. Surface in contact with oil shall not be galvanized or cadmium plated. 18.5. Labels, indelibly marked shall be provided for all identifiable accessories like relays, switches, current transformers etc. All label plates shall be of in corrodible material. 18.6. All internal connections and fastening shall be capable of operating under overloads and over-excitation, allowed as per specified standard without injury. 18.7. Transformers and accessories shall be designed to facilitate proper operation, inspection, maintenance and repairs. No patching, plugging, shimming or other, such means of overcoming defects, discrepancies or errors will be accepted. 18.3. 19.0 CORES : 19.1. The Core shall preferably be boltless and step lap design and CRGO to be procured directly from CRGO supplier or from their accredited agent supported by necessary documentary evidence for. 19.2. Core shall have magnite coating as insulation. Successful bidder will offer the core for inspection and/or approval by the purchaser during manufacturing stage. 19.3. Manufacturer’s call notice for the purpose should be accompanied with the following documents as applicable as a proof towards use of prime core materials: i) ii) iii) iv) v) Invoice of the supplier Mill‘s Test Certificate Packing Lists Bill of landing Bill of entry Certificate to Customs Core materials shall be procured either from the core manufacturer or through their accredited marketing organisation of repute. Bidder should preferably have in-house Core cutting facility for proper monitoring and Control on quality. The materials used for insulation shall have high inter lamination resistance and rust inhibiting property. It shall not have any tendency to absorb moisture or to react with insulating oil. 19.4. The assembled core shall be securely clamped on the limbs and yoke with uniform pressure so as to minimise noise emission form it. 19.5. The top main core clamping structure shall be connected to the tank body by a copper strap. The bottom clamping structure shall be earthed by one or more of the following methods (i) (ii) (iii) by connection through vertical tie rods to the top structure by direct metal to metal contact with the tank base by the weight of the core and windings, by a connection to the top structure on the same side of core the main earth connection to the tank. 19.6. All parts of the cores shall be robust design capable of withstanding any shocks to which they may by subjected during lifting, transport, installation and service. 19.7. Adequate lifting lugs shall be provided to enable the core and winding to be lifted. 19.8. Adequate provision shall be made to prevent movement of the core and winding relative to the tank during transport and installation or while in service. 19.9. The supporting frame work of the cores shall be so designed as to avoid the presence of pockets which would prevent complete emptying of the tank through the drain valve or cause trapping of air during filling. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 8 Technical Specification 19.10. The insulation structure for the core to bolts and core to clamp plates shall be 20.0 such as to withstand a voltage of 2000 VAC at 50HZ for one minute . FLUX DENSITY OF CORE 20.1. The maximum flux density in any part of the core and yokes at principal (normal) tapping and at rated frequency shall not exceed 1.6 Tesla (16000 lines per sq.cm) at normal voltage and 1.9 Tesla (19000 lines per sq.cm) under overvoltage condition as specified in this specification. 20.2. Prior to inspection and testing of the Transformer the supplier shall submit on request following curves of the core manufacturer. i) Flux density vs Core loss. ii) Flux density vs Excitatioin 21.0 WINDING: 21.1. All windings shall be fully insulated. 12.02 Power transformer shall be designed to withstand the impulse and power frequency test voltages specified in clause no. 9.01. 21.2. The windings shall be designed to reduce to a minimum the out of balance forces in the transformer at all voltage ratios. 21.3. The insulation of Transformer winding and connections shall be free from insulating material liable to soften, ooze out shrink or collapse and shall be noncatalytic and chemically inactive to transformer oil during service. 21.4. The stacks of windings shall receive adequate shrinkage treatment before final assembly. Adjustable device shall be provided for taking up any possible shrinkage of coils in service. 21.5. All the insulating materials to be used in the transformer shall preferably be of class- A insulation as specified in Indian Standards. The test certificate of the raw materials shall be made available by the Transformer manufacturer on request during inspection and testing. 21.6. The coil clamping arrangement and the finished dimensions of any oil ducts shall be such that it will not impede the free circulation of oil through the ducts. 21.7. The windings and connection of transformer shall be braced to withstand shocks which may occur during transport or due to switching short circuit and other transient conditions during service. 21.8. Coil clamping rings, if provided shall be of steel or suitable insulating material. Axially laminated material other than bakelised paper shall not be used. 22.0 INTERNAL EARTHING ARRANGEMENTS: 22.1. General : All metal parts of the transformer with the exception of the individual core laminations, core bolts and associated individual clamping plates shall be maintained at fixed potential. 22.2. Earthing of coil clamping rings : Where coil clamping rings are of metal at earth potential, each ring shall be connected to the adjacent core clamping structure on the same side of transformer as the main earth connection. 23.0 TANKS: Construction : Conventional type tank shall be constructed. The Transformer tank and cover shall be fabricated from good commercial grade low Carbon steel suitable for welding and of adequate thickness. The tanks of all transformers shall be complete with all accessories and shall be designed so as to allow the complete transformer in the tank and filled with oil, to be lifted by crane or jacks, transported by rail, road without overstraining any joint and without causing subsequent leakage of oil. 23.2. The main tank body shall be capable of withstanding vaccum gauge pressure 68.0 KN per Sq, metres ( 500 mm. of HG). 23.1. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 9 Technical Specification The under carriage of the tank shall be made of channel of suitable size and design. The base of each tank shall be so designed that it shall be possible to move the complete transformer unit by skidding in any direction without injury when using plate or rails. 23.4. Where the base is of a channel construction, it shall be designed to prevent retention of water. Tank stiffeners shall be designed to prevent retention of water. 23.5. Wherever possible the Transformer tank and its accessories shall be designed without pockets wherein gas may accumulate. Where pockets cannot be avoided, pipes shall be provided to vent the gas into the main expansion pipe. 23.6. All joints other than those which may have to be broken shall be welded when required they shall be double welded. All bolted joints to the tank shall be fitted with suitable oil tight gaskets which shall give satisfactory service under the operating conditions and guaranteed temperature rise conditions. Special attention shall be given to the methods of making hot oil tight joints between the tank and the cover as also between the cover and bushing and all other outlets to ensure that the joints can be remade at site satisfactorily. 23.3. 24.0 TANK COVER 24.1. :Each tank cover shall be of adequate strength and shall not distort when lifted. Inspection openings shall be provided as necessary to give easy access to bushings or changing ratio or testing the earth connection. Each inspection opening shall be of ample size for the purpose for which it is provided. The tank cover and inspection cover shall be provided with suitable lifting arrangement. 24.2. The tank cover shall be fitted with pockets for thermometer and for the bulbs of Oil and Winding temperature indicators. The thermometer pocket shall be fitted with a captive screwed top to prevent the ingress of water. Protection shall be provided, where necessary, for each capillary tube. The pocket shall be located in the position of maximum oil temperature and it shall be possible to remove the instrument bulbs without lowering the oil in the tank. 24.3. Turrets should provided on tank cover to house the bushings. The turrets of both HV & LV bushings should be connected through pipes with main tank Buchholtz Relay pipe to drive out trapped air or should have air release plug to drive out trapped air as the case may be. 25.0 OFF LOAD TAP CHANGER. 25.1. The transformers shall be provided with voltage control equipment of the tap changing type on the HV side for HV variation of +3% to (-) 9% in equal 5 steps of 3.0% for varying its effective transformation ratio whilst the transformers are offload. The tap changing device shall be off-circuit type. The tap changing shall be carried out by means of an externally operated tapping switch capable of being located and locked in any required position. 25.2. The location of tap changing device shall be such that an operator can very easily change the tap, while standing on the ground without the aid of any climbing platform. A warning plate indicating that switch shall not be operated in “ON” position is to be provided. 25.3. The contact resistance between the contact points should be less than 20µΩ. The manufacturer should show the resistance to the inspector at the time of inspection. 26.0 CONSERVATOR VESSELS. Conservator vessels : The conservator should be air cell/ atmoseal type to prevent direct contact of Transformer oil with atmospheric air for retarding oxidation contamination of oil. The Air cell shall be made from suitable material with inner coating resistant to transformer oil & outer coating resistant to ozone & weathering. 26.2. The conservator shall be provided with necessary valves to drive out the air in the space between conservator wall & air cell during filling of oil, drain valves for complete draining of oil and cut off valves etc. 26.1. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 10 Technical Specification The conservator complete with necessary valves shall be provided in such a position as not to obstruct the electrical connections to the transformer from H.V & L.V SIDE. 26.4. The conservator shall be a capacity to meet the requirement of expansion of the total cold oil volume in the Transformer & cooling equipment. 26.5. The conservator shall be designed so that it can drain oil completely by means of the drain valve provided when mounted. One end of the conservator shall be bolted into position so that it can be removed for cleaning purpose. 26.6. The conservator shall be provided with different valves for filling of oil manually at site. 26.3. 27.0 OIL GAUGES 27.1. Normally one Magnetic type oil gage shall be provided. The oil level at 30 Deg. C. shall be marked on the guage. 27.2. CONNECTION : The oil connection from the transformer tank to the conservator vessel shall be arranged at a raising angle of 3 to 9 degrees to the horizontal up to the Buchholtz Relay and shall consist of pipe with inside diameter 50 mm./80 mm. as per capacity of the Transformer and as per IS:3639. 27.3. Two valves shall be provided between the conservator & Transformer main tank to cut off the oil supply to the transformer after providing a straight run of pipe for at least a length of five times the internal diameter of the pipe on the tank side ofthe Gas and Oil actuated Relay and at least three times the internal diameter of the pipe on the conservator side of the Gas and Oil actuated Relay. The valves should be fitted on both side of the Gas and Oil Actuated Relay. 28.0 BREATHER : Each conservator vessel shall be fitted with a glass container type breather in which silicagel is dehydrating agent and so designed that the passage of air through the silicagel the external atmosphere is not continuously in contact with the oil. 28.1. . 28.2. The moisture absorption indicated by a change in colour of the tinted crystals can be easily observed from the distance. 28.3. All breathers shall be mounted at approximately 1400 mm above ground level and shall be connected to the air cell of the conservator through pipe for the purpose of breathing during contraction or expansion of the air cell. 29.0 BUSHINGS 29.1. Bushings for 36 KV and below shall be of solid porcelain type. These bushings shall be suitable for bare ACSR conductor connections. 29.2. The bushing shall have sufficient insulation to avoid leakage to ground and shall be so located as to provide adequate electrical clearance between bushing or various voltages and between bushings and grounded parts. The insulation class of the high voltages neutral bushing shall be properly co-ordinated with the insulation class of the neutral of the high voltage winding. 29.3. Stresses due to expansion and contraction in any part of the bushing insulator shall not lead to the development of defects. Outdoor insulators and fittings shall be unaffected by atmospheric conditions due to weather, fuses, ozone, acids, dust and rapid changes of air temperature. Any stress shield shall be considered as integral part of the bushing assembly. 29.4. Porcelain shall not engage directly with hard metal and where necessary gaskets shall be interposed between the porcelain and the fittings. All porcelain clamping surface in contact with gasket shall be accurately grounded and free from glaze 29.5. Fixing material used shall be of suitable quality and properly applied and shall not enter into chemical action with the metal parts or cause fracture by contraction expansion in service. Cement thickness shall be as small and even as possible and proper care shall be taken to centre and locate individual parts Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 11 Technical Specification correctly during cementing. All porcelain insulators shall be designed to facilitate clearance. 29.6. Each porcelain bushing or insulator, and paper bushing shall have marked upon it the manufacturer‟s identification mark, and such other marks as may be required to assist in the representative selection of batches for the purpose of the sample tests. 29.7. Clamps and fittings shall be made of steel and galvanized. The bushing flanges shall not be re-entrant type (shape) which may trap air. 29.8. Each bushing shall be so coordinated with the transformer insulation, that the flashover will occur outside the tank. 29.9. All porcelain used in bushings shall be of wet process, homogeneous and free from cavities or other flaws. The glazing shall be uniform in colour (brown) and free from blisters, burns and other defects. Porcelain shall be thoroughly vitrified and shall be impervious to moisture. 29.10. All bushing shall have puncture strength greater than dry flashover value. 29.11. Creepage distance will be kept 27 mm/KV. Bushings may be provided with weather shield. 29.12. The bidder is requested to give the guarantee withstand voltage for the above and also furnish a calibration curve with different settings of the co-ordination gap to enable the purchaser to decide the actual gap settings. Tenderer‟s recommendations are also invited to this respect. During spark gap flashover, the arc shall remain away from the housing insulator. 29.13. Each terminal (including neutral) shall be distinctly marked and coloured for phase voltage and phase rotation on the primary secondary and tertiary sides in accordance with the diagram of connection supplied with the transformer, the system of marking shall conform IS 2026-1962 amended upto date. 29.14. Stress due to expansion and contraction in any part of the bushing shall not lead to deterioration. 29.15. Bushing shall be designed and tested to comply with the applicable standards. 29.16. Bushings rated for 400A and above shall have non-ferrous flanges and hardware. 29.17. Fittings made of steel or malleable iron shall be galvanized. 29.18. Bushing shall be so located on the transformer that full flashover strength will be utilized. Minimum clearances as required for the BIL shall be realized between live parts and live parts to earthed structures. 29.19. All applicable routine and type tests certificates of the bushings shall be furnished for approval. 29.20. Bushings shall be supplied with bimetallic/terminal connectors/ clamp suitable for fixing to bushing terminal and the PURCHASER‟S specified conductors. The connectors/clamp shall be rated to carry the bushing rated current without exceeding a temperature rise of 55° C over an ambient of 40° C. the connector/ clamp shall be designed to be corona free at the maximum rated line to ground voltage. 29.21. Bushing of identical voltage rating shall be interchangeable. 29.22. Each bushing shall be so coordinated with the transformer insulation that all flashover will occur outside tank. 30.0 FILTER AND DRAIN VALVES, SAMPLING DEVICES AND AIR RELEASE PLUGS : 30.1. Each Transformer shall be fitted with the following : 30.2. The filter and drain valves as specified. A drain valve as below shall be fitted to each conservator. For diameter upto 650 mm : Size of the valve 15 mm : for diameter above 650 mm : Size of the valve 25 mm. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 12 Technical Specification Suitable oil sampling device shall be provided at the top and bottom of the main tank. The sampling device shall not be fitted on the filter valves specified above. One 15mm air release plug on the main tank of the Transformer. 30.3. All other valves opening to atmosphere shall be fitted with blank flanges. Valves shall be of forged carbon steel upto 50 mm size and of gun metal or of cast iron bodies with gun metal fittings for sizes above 50 mm. They shall be of full way type with screwed ends and shall be opened by turning counter clock wise when facing the hand wheel. There shall be no oil leakage when the valves are in closed position. 30.4. Each valve shall be provided with an indicator to show the open and closed position and shall be provided with facility for padlocking in either open or closed position. All screwed valves shall be furnished with pipe plugs for protection. Padlocks with duplicate keys shall be supplied along with the valves. 30.5. All valves except screwed valves shall be provided with flanges having machined faces drilled to suit the applicable requirements. Oil tight blanking plates shall be provided for each connection for use when any radiator is detached and for all valves opening to atmosphere. If any special radiator valve tools are required, the Contractor shall supply the same. The main tank Valves shall be provided with suitable Iron cage Gaurd so that the valve doesnot get damage during transportation and not easily accesible to operate. 30.6. Each transformer shall be provided with following valves on the tank so located as to completely drain the tank. 30.7. 30.8. 31.0 Two filter valves on diagonally opposite corners, of 50 mm size. Oil sampling valves not less than 8 mm at top and bottom of main tank Valves between radiators and tank. Valve prior to and after the Buchholz Relay. COOLING PLANT 31.1. General :Radiators shall be so designed as to avoid pockets in which moisture may collect and shall withstand the pressure tests. 31.2. The radiator tubes / fins shall be seamless, made of mild steel having as minimum wall thickness of approx. 1.2mm and a clean bright internal surface free from dust and scale. They shall be suitably braced to protect them from mechanical shocks, normally met in transportation and to damp the modes of vibration transmitted by the active part of the transformer in service. 31.3. Each cooler unit shall have a lifting eye. 31.4. Radiator Valves: The butterfly or similar metal valves shall be provided for isolating detachable radiator assembly. 31.5. One cock each at the bottom of radiator stack shall be provided for draining oil from radiator stacks. 31.6. Air release plug each at the top of radiator stack shall be provided for release of air from radiator stack. 31.7. Removable blanking plates shall be provided to permit the blanking off the main oil Connection of each cooler. 31.8. Radiator fixing bands in top & bottom of radiators are to be provided to minimise the vibration of the same. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 13 Technical Specification 32.0 33.0 LIFTING AND HAULAGE FACILITY : 32.1. Each tank shall be provided with Lifting lugs suitable for lifting of transformer complete with oil. 32.2. A minimum of four jacking lugs, in accessible positions to enable the transformer complete with oil to be raised or lowered using hydraulic or screw jacks 32.3. The minimum height of the lugs above the base shall be as follows (a) for transformers up to and including 10 tones weight-300mm (b) for Transformers above 10 tones weight – 500 mm 32.4. Suitable haulage holes shall be provided. INSULATING OIL : 33.1. The Transformer and all associated oil filled Equipment shall be supplied complete with insulating new oil required for first filling including 10% extra oil for future use during commissioning. The Transformer tank shall be dispatched completely filled with oil and the balance oil shall be supplied in non returnable sealed drums along with the Transformers. 33.2. The Insulating oil shall conform to the requirement of IS:335. 34.0 PRESSURE RELIEF DEVICE : 34.1. Pressure relief device shall be provided of sufficient sizes for rapid release of pressure that may by generated within the tank, and which might result in damage to the equipment. The device shall operate at a static pressure of less than the hydraulic test pressure for transformer tank. Means shall be provided to prevent ingress of rain. 34.2. It shall be mounted on the cover of the main tank and shall be designed to prevent gas accumulation. 34.3. Spring loaded setting type Pressure Relief Valve having suitable opening Port hole according to the capacity of the transformers should be provided. 34.4. The pressure relief valve should have provision of visual indication for opening of the valve and also Contract/Micro Switch arrangement for alarm/Tripping Function. 35.0 AXLES AND WHEELS : 35.1. The Transformer shall be provided with flanged bi-directional wheels as mentioned below : Flanged wheel suitable for use on a 1435 mm / 1676 mm guage track. . The wheels shall be suitable for being turned through an angle of 90 Deg. and locked in that position when the tank is jacked up. 35.3. All wheels shall be detachable and shall be made of Cast Iron or Steel. Suitable locking arrangement shall be provided to prevent the accidental movement of the transformer. 35.2. 36.0 CLEANING & PAINTING 36.1. Before painting or filling with oil all galvanised parts shall be completely cleaned and free from rust, scale and grease and all external surface cavities on castings shall be filled by metal deposition. 36.2. The interior of all transformer tanks and other oil filled chambers and internal structural steel work shall be thoroughly cleaned of all scale and rust by sand blasting or other approved method. These surfaces shall be painted with hot oil resisting varnish or paint. Unexposed welds need not be painted. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 14 Technical Specification 36.3. Except for nuts, bolts and washers, which may have to be removed for maintenance purposes, all external surfaces shall receive a minimum of three coats of paint. 36.4. The primary coat shall be applied immediately after cleaning. The second coat shall be of oil paint of weather resisting nature and preferably of a shade or colour easily distinguishable from the primary and final coasts shall be applied after the primarycoats have been touched up where necessary. 36.5. The final coat shall be of glossy oil and weather resisting non fading paint of Dark Admiralty Grey shade no. 632 of IS:5. 36.6. Primer paint shall be ready made zinc chrome as per IS: 104: Intermediate and final costs of paint shall be as per IS: 2932. 36.7. All interior surfaces of mechanism chambers and kiosks except those which have received anti-corrosion treatment shall receive three coats of paint applied to the thoroughly cleaned metal surface as per procedure mentioned above. The final coat shall be of a light coloured anti-condensation mixture. 36.8. Any damage to paint work incurred during delivery shall be made good by the manufacturer by thoroughly cleaning the damage portion and applying the full number of coats of paint that had been applied before the damage was caused. 37.0 EARTHING TERMINAL 37.1. Two earthing terminals capable of carrying the full amount of lower voltage short circuit current of transformer continuously for a period of 5 Second Provision shall be made at positions close to each of the bottom two corners of the tank for bolting the earthing terminals to the tank structure to suit local condition. 38.0 TEMPERATURE INDICATING DEVICE: 38.1. Oil temperature indicator with two electrical contacts for alarm and trip purposes, shall be provided with anti vibration mounting. The oil temperature indicator shall be housed in the marshalling box. 38.2. The winding temperature indicator with two electrical contacts for alarm & trip purposes shall be provided with anti vibration mounting. The winding temperature indicator shall be housed in the marshalling Box. 38.3. The Oil and Winding temperature indicator should be of renowned make preferably of ―Perfect Control‖ or ―Precimeasure‖. The scale on the dial of the thermometer should be 0°C to 150°C. The angular displacement of thermometer should be 270 Deg. 38.4. The signaling contact of WTI & OTI shall be set to operate at the following temperature: OIL : Alarm-85 °C, Trip – 95 ° C WINDING : Alarm-100 °C, Trip – 110 °C The tripping contacts of indicator shall be adjustable to close the winding temperature indicator between 60 Deg.C and 120 Deg.C. The alarm contacts of indicator shall be adjustable to close between 50 deg.C & 100 Deg.C. 38.6. All contacts shall be adjustable on a scale and shall be accessible on removal of the cover. The Temperature indicators shall be so designed that it shall be possible to check the operation of contacts and associated Equipments. 38.7. For measuring winding temperature a heater coil fed from a C.T. has to be provided on the pocket for winding temperature indicator bulb. The connection from C.T. to heater should be through a link arrangement on the tank cover suitably housed in a weather proof box so that C.T. current and heater coil resistance can be checked. WTI C.T. secondary should be of 5 Amps, rating. 38.8. Accuracy class of both OTI and WTI shall be ±1% or better. 38.5. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 15 Technical Specification 39.0 MARSHALLING BOX 39.1. A sheet steel 3.15mm thick vermin proof, well ventilated and weather proof marshalling box of a suitable construction shall be provided for the transformer ancillary apparatus. The box shall have domed or sloping roofs and the interior & exterior painting shall be in accordance with painting clause specified. The degree of protection shall be IP-55. 39.2. The marshalling box shall accommodate. Winding and oil temperature indicator. Terminal Blocks and gland plates for incoming and outgoing Cables. One space heater operated by 220 V.A.C. Aux. Supply, Cubicle illuminating lamp with door switch. 39.3. All incoming cables shall enter the kiosk from the bottom and the gland plate shall not be less than 450 mm from the base of the box. The gland plate and associated compartment shall be sealed in suitable manner to prevent the ingress from the cable trench 39.4. All the above equipment shall be mounted on panels and back of panel wiring shall be used for Interconnection. The temperature indicators shall be so mounted that the dials are visible by standing at ground level. 39.5. Door of the compartment shall be provided with glass window of adequate size. Ventilation louvers shall be provided. 39.6. The schematic diagram of the circuitry inside the marshalling box be prepared and fixed inside the door 40.0 GAS AND OIL ACATUATED RELAYS 40.1. Each transformer shall be provided with gas and oil actuated Relay (Buchholtz Relay) equipment conforming of IS:3637 double float type with one set of alarm contacts, one set of trip contacts and a testing pet cock. The contacts shall be wired with a P.V.C. armoured cable. 40.2. A machined surface shall be provided on the top of Relay to facilitate the setting of Relay and to check the mounting angle in the pipe and cross level of the Relay. 40.3. The pipe work shall be so arranged that all gas arising from the Transformer shall pass into the gas and oil actuated Relay. The oil circuit through the Relay shall not form a delivery path in parallel with any circulating oil pipe. RATING DIAGRAM AND PROPERTY PLATES : 41.1. The following plates shall be fixed to the transformer tank at a suitable height so that the particulars could be read by standing at ground level. 41.2. A rating plate bearing the data specified in the relevant clauses of IS:2026 including figures of temperature rise of oil and winding and high voltage test values. that the equipment belongs to APDCL with reference of purchase order is also to be indicated. 41.3. A diagram plate showing the internal numbering of taps, tapping switch connection of windings and also the voltages vector relationship in accordance with IS:2026 and in addition a plan view of the transformer giving the correct physical relationship of the terminals. No load voltage shall be indicated for each tap. Details of C.T particulars w.r.o phase, Neutral &WTI CT. 41.0 42.0 CENTRE OF GRAVITY : 42.1. : The centre of gravity of the assembled transformer shall be low and as near the vertical centre line as possible. The transformer shall be stable with or without oil. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 16 Technical Specification 42.2. If the centre of gravity is eccentric relative to track either with or without oil, its location shall be shown on the outline drawing. . 43.0 44.0 FOUNDATION : 43.1. The tenderer shall furnish foundation plan of the transformer showing the fixing arrangement of the transformer so that the purchase may be able to finalise the foundation drawings. TEST AND INSPECTION : 44.1. Routine Tests : 44.2. All transformers shall be subjected to the following routine tests at the manufacturer‘s works. The tests shall be carried out in accordance with the details specified in IS:2026. i) Measurement of winding resistance. ii) Measurement of turns ratio for all sets wndings on each tap iii) Polarity and phase vector relationship. iv) Measurement of no load loss and no load current. v) Measurement of impedance voltage at normal , maximum and minmum tap vi) Measurement of insulation resistance between windings and between windings and earth vii) Measurement of load loss. viii) Induced over voltage withstand test. ix) Separate source voltage withstand test. x) Oil Leakage gas collection, oil surge and voltage test on gas and oil actuated relay for on load tap changer. xi) Magnetic balance test. xii) Testing of Phase & Neutral C.T., as applicable, in accordance with provisions in the relevant I.S. xiii) Oil leakage test of tnansformer tanks at a pressure equals to the normal pressure plus 35 KN/ sq.M measured at the base of tank. 44.3. Type Test 44.4. In addition to routine Tests mentioned above the transformer shall be subjected to all kinds of Type and Acceptance Test in accordance with Relevant I.S. (IS:2026) with latest amendment if any. 44.5. Bidder should submit Type Test report from NABL/Govt. approved Laboratories along with their offer having identical technical parameters as that of the tendered item failing which their offer may not be technically accepted. 44.6. However, if it is found that the bidder has submitted Type tests Report but those have not been conducted on identical Design of equipment/material as per specification of APDCL, the same may be accepted subject to the following conditions: APDCL at his discretion request the successful bidders to conduct Type Tests on identical design as per specification 44.7. . Such Type tests/special tests, if required to be carried out at NABL/Govt. approved Laboratories in presence of APDCL engineers for which no extra cost shall be charged to the APDCL. 44.8. However, the bidders who have not submitted such Type Test/Dynamic Short Circuit Test report but if their offer is considered technically acceptable by the purchasers on the basis of other credentials, they will have to carry out such tests at NABL/Govt. approved Laboratories in presence of APDCL engineers before effecting physical delivery against Purchase Order for which no extra cost shall be Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 17 Technical Specification charged to the APDCL. Routine Test have to be carried out in presence of APDCL engineers before carrying out type test. 45.0 46.0 47.0 INSPECTION AND TESTING 45.1. Inspection and testing as already mentioned the equipment shall be subjected to routine and other acceptance tests as per provisions in the relevant I.S. 45.2. The APDCL reserves the right to send its Engineers if so desires to witness manufacturing process and to reject either raw materials or finished products found to be not complying with the requirement of the specification and also shall have the right to select any/all equipment from the lot offered for tests. 45.3. The manufacturer shall give at least (21) twenty one days’ advance notice regarding readiness of such inspection and testing and shall submit six sets of the works test certificates of the materials/equipment offered for inspection and testing indicating probable date of inspection and testing. 45.4. The manufacturer shall arrange all possible facilities for such inspection and testing at any time during the course of manufacture free of cost. TEST CERTIFICATE 46.1. Five copies of the approved Test Certificates as mentioned above are to be furnished to the APDCL before dispatch of the equipment. DRAWINGS AND MANUALS TO BE SUBMITTED BY SUCCESSFUL BIDDER 47.1. The bidder shall furnish, within fifteen days after issuing of letters Award, six copies each of the following drawings/documents incorporating name of project and transformer rating for approval. i. Detailed overall general arrangement drawing showing front and side elevations and plan of the transformer and all accessories including radiators and external features with details of dimension, spacing of wheels in either direction of motion, net weights and shipping weights, crane lift for untanking, size of lugs and eyes, bushing lifting dimensions, clearances between HV and LV terminals and ground, quantity of insulating oil etc. ii. Foundation plan showing loading on each wheel and jacking points with respect to centre line of transformer. iii. GA drawing/details of bushing and terminal connectors. iv. Name plate drawing with terminal marking and connection diagrams. v. Wheel locking arrangement drawing. vi. Transportation dimension drawings. vii. Interconnection diagrams. viii. Over fluxing withstand time characteristics of transformer. ix. GA drawing of marshalling box. x. Control scheme/wiring diagram of marshalling box. xi. Technical leaflets of major components and fittings. xii. As built drawing of schematic, wiring diagrams etc. xiii. Setting of oil temperature indicator, winding temperature indicator. xiv. Completed technical data sheets. xv. HV/LV conductor bushing. xvi. Bushing assembly. xvii. Bi-metallic connector for connection to ―Wolf‖/PANTHER ACSR/AAAC conductor xviii. Radiator type assembly. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 18 Technical Specification 47.2. All drawings/documents, technical data sheets and test certificates/results/calculations shall be furnished. 47.3. Any approval given to the detailed drawings by the purchaser shall not relieve the contractor of the responsibility for correctness of the drawing and in the manufacture of the equipment. The approval given by the purchaser shall be general with overall responsibility with contractor. 47.4. Installation, operation and maintenance manual of transformer, associated equipment like buchholtz Relay, temperature indicators, oil level indicator etc. The manual shall clearly indicate the installation method, check-ups and tests to be carried out before and after commissioning of the transformer. 47.5. One copy of manual, set of approved drawings shall be submitted to the CGM(PPD)/APDCL before dispatch of the Transformer. 47.6. In addition one set of approved drawing, manual for transformer shall be send to the respective consignee officer in water proof folder at the time of delivery of the transformer. 48.0 GUARANTEED TECHNICAL PARTICULARS 48.1. Bidder shall furnish guaranteed technical particulars of equipment offered as per Schedule ‗B‘ To be provided along with final NIT specification), 49.0 ACCESSORIES 49.1. All accessories as specified in the schedule A are to be provided. Any other part necessary for smooth operation of the transformer if omitted it is the manufacturers responsibility to include the same. SPARE PARTS: 50.1. The Tenderer shall submit a recommended list of spare parts for five years of operation along with item wise price for each item of spares as stated in Schedule B 50.0 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 19 Technical Specification SCHEDULE – A FITTINGS & ACCESSORIES The following fittings and accessories shall be supplied with each Transformer : 1. Outdoor type bushing – 11KV-3 Nos. and LV-4 Nos. 2. Conservator with aircell and supporting bracket or structure as the case may be. 3. Isolating valve for conservator in between conservator and Buchholtz Relay and in between Buchholtz relay and main tank.. 4. Conservator valves for driving out air between air cell & wall of conservator & connection to breather. 5. Conservator drain valve. 6. Dial type oil level indicator complete with alarm contact. 7. Silica gel breather with oil seal and connecting pipe. The breather shall be accessible for inspection from ground. 8. Spring loaded setting type pressure relief Valve having suitable opening Port. Hole & provision of visual indication for opening of the valve & Alarm/Trip contact arrangement. 9. Access/inspection holes with bolted cover for access to inner ends of bushing. 10. Cover lifting eyes. 11. Lifting eyes for core frame with windings. 12. Tap changing arrangement with hand wheel for Off-Load tap13. Air release plugs on top of cover and pressure equalizer pipe for bushing turret. 14. Upper filter valve and bottom filter valve with cage valve guard.. 15. Drain valve with cage gaurd. 16. Top and bottom oil sampling devices. Provision for oil sample collection during process of filtration should be made. 17. Lifting lugs. 18. Jacking pads with handling holes at four corners. 19. Transport lugs. 20. Under carriage base channel. 21. Tank earthing terminals – 2 Nos. 22 Buchholtz relay double float type with one set of alarm contacts, one set of trip contacts and testing pet cock. The contacts should be wired with a PVC armoured cable. 23. Dial thermometer for winding temperature with alarm contacts and Trip contacts. 24. Dial thermometer for oil temperature with alarm contacts and Trip Contacts. 25. An additional pocket for inserting thermometer for oil temperature indication. 26. Weather proof control cabinet for marshalling terminal connections from protective and indicative devices. The cabinet shall be provided with incandescent filament lighting, heater and plugs etc. 28. Rating plate, as per I.S.S. 29. Diagram Plate : As per clause 28. 30. Property label. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 20 Technical Specification SCHEDULE – B SPARE PARTS: The mandatory spare parts shall include but not be limited to the following for each rating of transformer. (i) Bushings: a. High Voltage - 1 No. b. Low Voltage - 1 No. c. Neutral Bushing - 1 No. (ii) Complete set of gaskets for all - 1 Set openings on the tank requiring gasket. (iii) Magnetic oil level gauge with low oil - 1 No. level alarm contacts. (iv) Oil temperature indicator with alarm - 1 No. and trip contacts and maximum reading pointer. (v) Winding temperature indicator with alarm and trip - 1 No. contacts and maximum reading pointer (vi) Set of all types of valves comprising one in each type. - 1 Set (vii) Silicagel breather - 1 No. (viii) Buchholz Relay - 1 No. Note: The quantities indicated above are for each transformers. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 21 Technical Specification Section – 3 3.1 GENERAL TECHNICAL SPECIFICATIONS 1.0 Part A General: 1.1. It is not the intent to specify herein complete details of design and construction of the plant/equipment/material. The plant offered shall conform to the relevant standards and shall be of high quality, sturdy, robust and of good design and workmanship complete in all respects and capable to perform continuous and satisfactory operations in the actual service conditions at site and shall have sufficiently long life in service. The dimensional drawings attached with the technical Specification in Volume II are generally of illustrative nature. In actual practice, not withstanding any anomalies, discrepancies, omissions, incompleteness, etc. in these specifications and attached drawings, the design and constructional aspects, including materials and dimensions, will be subject to good engineering practice in conformity with the required quality of the product and to such tolerances, allowances and requirements for clearances etc. as are necessary by virtue of various stipulation in that respect in the relevant Indian Standards, IEC standards, I.E. Rules and other statutory provisions. 1.2. The plant/equipment/material offered shall be complete with all parts necessary for their effective and trouble free operation. Such parts will be deemed to be within the scope irrespective of whether they are specifically indicated in the Bid documents or not. 2.0 Quality Assurance Programme: 2.1. Bidder must establish that a proper quality assurance program is being followed by them for manufacture of plant/equipment. Quality Assurance Program must have a structure as detailed in following paragraphs. 2.2. Quality assurance and failure prevention starts with careful study and scrutiny of our technical specifications and requirements. Bidder/manufacturer shall carefully study all the technical parameters and other particulars and the Bidder/manufacturer shall categorically give his confirmation that these requirements shall be met in a satisfactory manner. 2.3. Bidder/manufacturer shall furnish the checks exercised in design calculations. The salient features of design shall be made available to the Employer. 2.4. Bidder/manufacturer shall indicate the various sources of the items being procured. Type of checks, quantum of checks and acceptance norms shall be intimated and random test and check results should be made available for inspection whenever so desired. 2.5. The Bidders shall invariably furnish following information. 1. Statement giving list of important raw materials, names if subBidder/manufacturers for the raw material, list of standards according to which the raw material is purchased and copies of test certificates thereof. 2. Information and copies of test certificates as in (i) above in respect of bought out items. 3. List of machines and manufacturing facilities available. 4. Levels of automation achieved and list of areas where manual processing exists. 5. List of areas in manufacturing process, where stage inspections are normally carried out for quality control and details of such tests and inspections. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 22 Technical Specification 6. List of testing equipment available with the Bidder for final testing of materials specified and test plant limitation, if any, vis-a-vis type, special, acceptance and routine tests specified in the relevant standards. These limitations shall be very clearly brought out in schedule of deviations from specified test equipments. 3.0 Pre Dispatch Inspection: 3.1. The Employer‘s representative may carry out stage inspection of the plant/equipment during manufacturing/ assembling stage. The Employer shall have absolute right to reject the raw material/ component/ sub assemblies or complete equipment not found to be conforming to the specification or being of poor quality/ workmanship. The stage inspection will particularly include tests specified for any particular plant or equipment in the technical specification, general routine tests and physical measurements to be conducted during manufacturing stages as per manufacturer‘s standard practice. 3.2. The Bidder/manufacturer shall give fifteen (15) days advance notice to enable the Employer to arrange for inspection. Inspection and testing shall be conducted at the place of manufacture. Inspection and testing of any material under this specification by the Employer shall not relieve the Bidder/manufacturer of his obligation to supply the plant/equipment in accordance with the specification and shall not prevent subsequent rejection if it is found to be defective. 3.3. The Bidder/manufacturer shall afford the Employer‘s representative all reasonable facilities, without charge, to satisfy him that the plant/ equipment is being manufactured in accordance with the specifications. The Bidders/manufacturer must have adequate set of instruments for conducting tests as per ISS specification. Instruments shall be duly calibrated and calibration certificate should not be older than one year on the date of inspection. Calibration shall be done by NABL accredited laboratories. A comprehensive list of testing equipment/ instruments indicating make, Sr.No., type, class of accuracy, calibrating agency, calibration date etc. should be furnished, as and when desired. Calibrated instruments shall be duly sealed by calibrating agency to avoid any tampering with calibration and the details thereof shall be clearly mentioned in the calibration certificate(s). 4.0 Defect Liability: 4.1. The defect liability period of plants/ equipments shall be as indicated in GCC of the bid document Vol. I. SPECIAL TECHNICAL SPECIFICATIONS FOR NEW SUBSTATION CIVIL WORKS & SWITCHGEAR 1.0 GENERAL The intent of specification covers the following: Design, engineering, and construction of all civil works at sub-station. All civil works shall also satisfy the general technical requirements specified in other Section of this Specification and as detailed below. They shall be designed to the required service conditions/loads as specified elsewhere in this Specification or implied as per National/International Standards. All civil works shall be carried out as per applicable Indian Laws, Standards and Codes. All materials shall be of best quality conforming to relevant Indian Standards and Codes. The Contractor shall furnish all design, drawings, labour, tools, equipment, materials, temporary works, constructional plant and machinery, fuel supply, transportation and all other incidental items not shown or specified but as may be required for complete performance of the Works in accordance with approved drawings, specifications and Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 23 Technical Specification direction of Employer. The work shall be carried out according to the design/drawings to be developed by the Contractor and approved by the owner based on Tender Drawings Supplied to the Contractor. by the Owner. For all buildings, structures, foundations, etc., necessary layout and details shall be developed by the Contractor keeping in view the functional requirement of the substation facilities and providing enough space and access for operation, use and maintenance based on the input provided by the Owner. Certain minimum requirements are indicated in this specification for guidance purposes only. However, the Contractor shall quote according to the complete requirements. 1.2 GEO-TECHNICAL INVESTIGATION 1.3 The Contractor shall perform a detailed soil investigation to arrive at sufficiently accurate, general as well as specific information about the soil profile and the necessary soil parameters of the Site in order that the foundation of the various structures can be designed and constructed safely and rationally. A report to the effect will be submitted by the contractor for Owner's specific approval giving details regarding data proposed to be utilized for civil structures design. 2.0 SCOPE OF WORK This specification covers all the work required for detailed soil investigation and preparation of a detailed report. The work shall include mobilization of necessary equipment, providing necessary engineering supervision and technical personnel, skilled and unskilled labour, etc., as required to carry out field investigation as well as, laboratory investigation, analysis and interpretation of data and results, preparation of detailed GeoTechnical report including specific recommendations for the type of foundations and the allowable safe bearing capacity for different sizes of foundations at different founding strata for the various structures of the substation. The Contractor shall make his own arrangement for locating the co-ordinates and various test positions in field as per the information supplied to him and also for determining the reduced level of these locations with respect to the benchmark indicated by the Owner. All the work shall be carried out as per latest edition of the corresponding Indian Standard Codes. 2.1 Bore Holes Drilling of bore holes of 150 mm dia, in accordance with the provisions of IS: 1982 at the rate of minimum two number of bore holes per bay to 15 m depth or to refusal which ever occur earlier. (By refusal it shall mean that a standard penetration blow count (N) of 100 is recorded for 30 cm penetration). However, in case deep pile foundations are envisaged the depths have to be regulated as per codel provisions. In cases where rock is encountered, coring in one borehole per bay shall be carried out to 3 M in bedrock and continuous core recovery is achieved. Performing Standard Penetration Tests at approximately 1.5 m interval in the borehole starting from 1.5 m below ground level onwards and at every change of stratum. The disturbed samples from the standard penetrometer shall also be collected for necessary tests. Collecting undistributed samples of 100/75 mm diameter 450 mm long from the boreholes at intervals of 2.5 m and every change of stratum starting from 1.0 m below ground level onwards in clayey strata. The depth of Water Table shall be recorded in each borehole. All samples, both disturbed and undisturbed, shall be identified properly with the borehole number and depth from which they have been taken. The sample shall be sealed at both ends of the sampling tubes with wax immediately after the sampling and shall be packed properly and transported to the Contractor's laboratory without any damage or loss. The logging of the boreholes shall be compiled immediately after the boring is completed and a copy of the bolero shall be handed over to the Engineer-in - Charge, Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 24 Technical Specification 2.2 Dynamic Cone Penetration Test Dynamic cone penetration tests of two numbers shall be carried out with the circulation of bentonite slurry at specified locations and a continuous record of penetration resistance (NG) upto 15.00 meter from natural ground level or the refusal shall be maintained by the Contractor IS: 4968 (Part-2) shall be followed for carrying out the test and reporting results. The location for tests shall be as directed by the Owner. On completion of the test, the results shall be presented as a continuous record as the numbers of blows required for every 300 mm penetration of the cone into the soil. 2.3 Trial Pits Trial pits shall be carried at specified one locations of per bay as directed by the Owner. The trial pits shall be 2m x 2m in size extending to 4 m depths, or as specified by the Owner. Undisturbed samples shall be taken from the trial pits as per the direction of the Owner. 2.4 Electrical Receptivity Test This test shall be conducted to determine the Electrical receptivity of soil required for designing safe grounding system for the entire station area. The specifications for the equipments and other accessories required for performing electrical receptivity test, the test procedure, and reporting of field observations shall confirm to IS: 3043. The test shall be conducted using Wagner's four electrode method as specified in IS: 1892, AppendixB2. Unless otherwise specified at each test location, the test shall be conduced along two perpendicular lines parallel to the co-ordinate axis. On each line a minimum of 8 to 10 readings shall be taken by changing the spacing of the electrodes from an initial small value of 0.5 m upto a distance of 10.0 m. 2.5 Plate Load Test Plate load test shall be conducted to determine the bearing capacity, modulus of subgrade reaction and load/settlement characteristics of soil at shallow depths by loading a plane and level steel plate kept at the desired depth and measuring the settlement under different loads, until a desired settlement takes place or failure occurs. The specification for the equipment and accessories required for conducting the test, the test procedure, field observations and reporting of results shall conform to IS: 1888. Modulus of sub-grade reaction shall be conducted as per IS: 9214. The location and depth of the test shall be as given below: 1) One at Control Building location at the proposed foundation depth below finished ground level for bearing capacity. 2) One test at Transformer foundation location at proposed foundation depth below FGL. Undisturbed tube samples shall be collected at 1.0 m and 2.5 m depths from natural ground level for carrying out laboratory tests. The size of the pit in plate load test shall not be less than five times the plate size and shall be taken upto the specified depth. All provisions regarding excavation and visual examination of pit shall apply here. Unless otherwise specified the reaction method of loading shall be adopted. Settlement shall be recorded from dial gauges placed at four diametrically opposite ends of the test plate. The load shall be increased in stages. Under each loading stage, record of time Vs. Settlement shall be kept as specified in IS: 1888. Backfilling of the pit shall be carried out as per the directions of the Owner. Unless otherwise specified the excavated soil shall be used for this purpose. In cases of gravelboulder or rocky strata, respective relevant codes shall be followed for tests. 2.6 Water Sample Representative samples of ground water shall be taken when ground water is first encountered before the addition of water to aid drilling of boreholes. The samples shall be of sufficient quantity for chemical analysis to be carried out and shall be stored in airtight containers. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 25 Technical Specification 2.7 Back Filling Bore Holes On completion of each hole, the Contractor shall backfill all boreholes as directed by the Owner. The backfill material can be the excavated material. 2.8 laboratory Test The laboratory tests shall be carried out progressively during the field work after sufficient number of samples have reached the laboratory in order that the test results of the initial boreholes can be made use of in planning the later stages of the field investigation and quantum of laboratory tests. All samples brought from field, whether disturbed or undisturbed shall be extracted/prepared and examined by competent technical personnel, and the test shall be carried out as per the procedures laid out in the relevant I.S.Codes. The following laboratory tests shall be carried out: i) Visual and Engineering Classification. ii) Liquid limit, plastic limit and shrinkage limit for CΦ soils. iii) Natural moisture content, bulk density and specific gravity. iv) Grain size distribution. v) Swell pressure and free swell index determination. vi) California bearing ratio. vii) Consolidated un-drained test with pore pressure measurement. viii) Chemical tests on soil and water to determine the carbonates, sulphates, nitrates, chlorides, Ph value, and organic matter and any other chemicals harms to the concrete foundation. ix) Rock quality designation (ROD), RMR in case of rock is encountered. 2.9 Test Results and Reports 1. The Contractor shall submit the detailed report in two (2) copies wherein information regarding the geological detail of the site, summarized observations and test data, bore logs, and conclusions and recommendations on the type of foundations with supporting calculations for the recommendations. Initially the report shall be submitted by the Contractor in draft form and after the draft report is approved, the final report in four (4) copies shall be submitted. The test data shall bear the signatures of the Investigation Agency, Vendor and also site representative of POWERGRID. 2. The report showing the locations of the exploration work i.e., bore holes, dynamic cone penetration tests, trial pits. Plate load test, etc. a) A plan showing the locations of the exploration work i.e., bore holes, dynamic cone penetration tests, trial pits. Plate load test, etc. b) Bore Logs: Bore logs of each bore holes clearly identifying the stratification and the type of soil stratum with depth. The values of Standard Penetration Test (SPT) at the depths where the tests were conducted on the samples collected at various depths shall be clearly shown against that particular stratum. Test results of field and laboratory tests shall be summarized strata wise as well in combined tabular form. All relevant graphs, charts tables, diagrams and photographs, if any, shall be submitted along with report. Sample illustrative reference calculations for settlement, bearing capacity, pile capacity shall be enclosed. 3.0 Recommendations The report should contain specific recommendations for the type of foundation for the various structures envisaged at site. The Contractor shall acquaint himself about the type of structures and their functions from the Owner. The observations and recommendations shall include but .not limited to the following: a) Geological formation of the area, past observations or historical data, if available, for the area and for the structures in the nearby area, fluctuations of water table, etc. slope stability characteristics and landslide history of the area shall be specifically highlighted. Remedial measures to be adopted shall also be given. b) Recommended type of foundations for various structures. If piles are recommended the type, size and capacity of pile and groups of piles shall be given after comparing different types and sizes of piles and pile groups. c) Allowable bearing pressure on the soil at various depths for different sizes of Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 26 Technical Specification the foundations based on shear strength and settlement characteristics of soil with supporting calculations. Minimum factor of safety for calculating net safe bearing capacity shall be taken as 3.0 (three). Recommendation of liquifaction characteristics of soil shall be provided. d) Recommendations regarding slope of excavations and dewatering schemes, if required. Required protection measures for slope stability for cut and fill slopes of switchyard and approach road with stone pitching/retaining walls shall be clearly spelt out. Calculation shall also be provided for stability adequacy. e) Comments on the Chemical nature of soil and ground water with due regard to deleterious effect of the same on concrete and steel and recommendations for protective measures. f) If expensive soil is met with, recommendation on removal or retainment of the same under the structure, road, drains, etc., shall be given. In the later case detailed specification of any special treatment required including specification or materials to be used, construction method, equipments to be deployed, etc., shall be furnished. Illustrative diagram of a symbolic foundation showing details shall be furnished. g) Recommendations for additional investigations beyond the scope of the present work, if considered such investigation as necessary. 4.0 SITE PREPARATION The Contractor shall be responsible for proper leveling of switchyard site as per layout and levels of switchyard finalized during detailed engineering stage. The Contractor at his own cost shall make the layout and levels of all structure, etc., from the general grids of the plot and benchmarks set by the Contractor and approved by the Owner. The Contractor shall give all help in instruments, materials and personal to the Owner for checking the detailed layout and shall be solely responsible for the correctness of the layout and levels. Site leveling shall be in the scope of the contractor. Bidder may decide the level of the sites. However, the level shall be such that it is 300 mm higher than the highest flood level (HFL) of the site. 5.0 SCOPE OF WORKS This clause covers the design and execution of the work for site preparation, such as clearing of the site, the supply and compaction of fill material, slope protection by stone pitching/retaining walls depending on the site location/ condition, excavation and compaction of backfill for foundation, road construction, drainage, trenches and final topping by stone (broken hard stone). 5.1 General 1) The Contractor shall develop the site area to meet the requirement of the intended purpose. The site preparation shall conform to the requirements of relevant sections of this specification or as per stipulations of standard specifications. Necessary protection of slope of switchyard area and approach road shall also be carried out by contractor. 2) If fill material is required, the fill material shall be suitable for the above requirement. The fill shall be such a material and the site so designed as to prevent the erosion by wind and water of material from its final compacted position or the in-site position of undisturbed soil. 3) When embankments are to be constructed on slopes of 15% or greater, benches or steps with horizontal and vertical faces shall be cut in the original slope prior to placement of embankment material. Vertical faces shall measure not more than 1 m in height. 4) Embankments adjacent to abutments, culverts, retaining walls and similar structures shall be constructed by compacting the material in successive uniform horizontal layers not exceeding 15 cm in thickness. (Of loose material before compaction). Each layer shall be compacted as required by means of mechanical tampers approved by the Owner. Rocks larger than 10 cm in any direction shall not be placed in embankment adjacent to Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 27 Technical Specification structures. 5) Earth embankments of roadways and site areas adjacent to buildings shall be placed in successive uniform horizontal layers not exceeding 20 cm in thickness in loose stage measurement and compacted to the full width specified. The upper surface of the .embankment shall be shaped so as to provide complete drainage of surface water at all times. 6) The pitching shall be designed and provided for slope protection as per approved drawings. The stone used shall be sound, hard, durable and fairly regular in shape. Stones subjected to marked deterioration by water or weather shall not be used. Suitable measures shall be provided to prevent erosion by seepage of water. Largest stone procurable shall be used as approved by owner for the work. Random rubble masonry (1:6) retaining walls shall be provided wherever required as per site condition. 5.2 Compaction 1. The density to which fill materials shall be compacted shall be as per relevant IS and as per direction of Owner. All compacted sand filling shall be confined as far as practicable. Backfilled earth shall be compacted to minimum 95% of the Standard Proctor's density at OMC. The sub-grade for the roads and embankment filling shall be compacted to 70% relative density (minimum). 2. At all times unfinished construction shall have adequate drainage. Upon completion of the road's surface course, adjacent shoulders shall be given a final shaping, true alignment and grade. 3. Each layer of earth embankment when compacted shall be as close to optimum moisture content as practicable. Embankment material, which does not contain sufficient moisture to obtain proper compaction, shall be wetted. If the material contains any excess moisture then it shall be allowed to dry before rolling. The rolling shall begin at the edges overlapping half the width of the roller each time and progress to the center of the road or towards the building as applicable. Rolling will also be required on rock fills. No compaction shall be carried out in rainy weather. 5.3 Requirement for fill material under foundation The thickness of fill material under the foundations shall be such that the maximum pressure from the footing, transferred through the fill material and distributed onto the original undisturbed soil will not exceed the allowable soil bearing pressure of the original undisturbed soil. For expansive soils the fill materials and other protections, etc., to be used under the foundation is to be got approved by the Owner. 6.0 6.1 ANTI-WEED TREATMENT AND STONE SPREADING Scope of Works The Contractor shall furnish all labour, equipment and materials required for complete performance of the work in accordance with the drawings specification and direction of the Owner. Stone spreading shall be done in the areas of the switchyard wherever equipments and or structures are to be provided under present scope of work. The stone spreading in future areas shall also be provided in case potential without stone layer is not well within safer limits. 7.0 GENERAL REQUIREMENT 7.1 The material required for site surfacing/stone filling shall be free from all types of organic materials and shall be of standard quality, and as approved by the Owner. The material to be used for stone filling/site surfacing shall be uncrushed/ crushed/broken stone of 20 mm nominal size (upgraded single size) conforming to Table 2 of IS:383-1970. Hardness, Flakiness shall be as required for wearing courses are given below: a) Sieve Analysis Limits (Gradation) (IS: 383 - Table 2) Sieve Size % passing by weight 40mm 100 20 mm 85 - 100 10 mm 0-20 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 28 Technical Specification 4.75 mm 0-5 b) Hardness Abrasion value (IS: 2386 Part-IV) - not more than 40% Impact value (IS: 2386 Part-IV) - not more than 30% and frequency shall be one test per 500 cum with a minimum of one test per source, c) Flakiness Index One test shall be conducted per 500 cum of aggregate as per IS: 2386 Part-I and maximum value is 25%, 7.2 After all the structures/equipments are erected and anti-weed treatment is complete, the surface of the switchyard area shall be maintained, rolled/ compacted to the lines and grades as decided by Engineer-in-Charge. Deweeding including removal of roots shall be done before rolling is commenced, Engineer-in-Charge shall decide final formation level so as to ensure that the site appears uniform devoid of undulations, The final formation level shall however be very close to the formation level indicated in the drawing using half ton roller with suitable water sprinkling arrangement to form a smooth and compact surface. 7.3 A base layer of uncrushed/crushed/broken stone of 20 mm nominal size (ungraded single size) shall be spread and rolled/compacted by using half ton roller with 4 to 5 passes and water sprinkling to form a minimum 50 mm layer on the finished ground level of the specified switchyard area excluding roads, drains, cable trench and tower and equipment foundations as indicated in the drawing. 7.4 Over the base layer of site surfacing material, a final surface course of minimum 50 mm thickness of 20 mm nominal size (single size ungraded) broken stone as specified above shall be spread and compacted by light roller using half tones steel roller (width 30" and 24" diameter) with water sprinkling as directed by he Engineer-in-Charge. The water shall be sprinkled in such a way that bulking does not take place. 7.5 In areas that are considered by the Engineer-in-Charge to be too congested with foundations and structures for proper rolling of the site surfacing material by normal rolling equipments, the material shall be compacted by hand, if necessary. Due care shall be exercised so as not to damage any foundation structures or equipment during rolling compaction. 7.6 Before taking up stone filling, anti-weed treatment shall be applied in the switchyard area wherever gravel filling is to be done, and the area shall be thoroughly de-weeded including removal of roots. The recommendation of local agriculture or horticulture department shall be sought wherever feasible while choosing the type of chemical to be used. Nevertheless the effectiveness of the chemical shall be demonstrated by the Contractor in a test area of 10M x 10M (approx.) and monitored over a period of two to three weeks by the Engineerin-Charge. The final approval shall be given by Engineer-in-Charge and final approval given based on the results. 7.7 The anti-weed chemical shall be procured from reputed manufacturers. The dosage and application of chemical shall be strictly followed as per manufacturer's recommendation. The contractor shall be required to maintain the area free of weeds for a period of 1 year from the date of application of 1st dose of anti-weed chemicals. 8.0 SITE DRAINAGE 1. Adequate site drainage system shall be provided by the Contractor. The Contractor shall obtain rainfall data and design the storm water drainage system, (culverts, ditches, drains, etc.) to accommodate run off due to the most intense rainfall that is likely to occur over the catchment area in one hour period on an average of once in tem years. The surface of the site shall be sloped to prevent the ponding of water. 2. The maximum velocity for pipe drains and open drains shall be limited to 2.4m/sec and 1.8m/sec respectively. However, minimum non-slitting velocity of 0.6 m/sec shall be ensured. Longitudinal bed slope not milder than 1 in 1000 shall be provided. 3. For design of RCC pipes for drains and culverts, 18:456 and 18:783 shall be followed. 4. The Contractor shall ensure that water drains are away from the site area and shall prevent damage to adjacent property by this water. Adequate protection shall be given to site surfaces, roads, ditches, culverts, etc., to prevent erosion of material by water. 5. The drainage system shall be adequate without the use of cable/pipe trenches. (Pipe drains shall be provided in areas of switchyard where movement of crane will be Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 29 Technical Specification necessary in operating phase of the substation). Open surface drains shall be provided with the Cement Concrete 1:2:4 of minimum thickness of 100 mm or more as per design condition. 7. Pipe drains shall be connected through manholes at an interval of max. 30m. Effluents shall be suitably treated by the Contractor to meet all the prevalent statutory requirements and local pollution control norms and treated effluents shall be conveyed to the storm water drainage system at a suitable location for its final disposal. 8. Invert of the drainage system shall be decided in such a way that the water can easily be discharged above the High Flood Level (HFL) outside substation boundary at suitable location upto a maximum 50M beyond boundary wall ot substation or actual whichever occurs earlier and approved by Owner. Pumps for drainage of water (it required) shall be provided by Contractor. 9. All internal site drainage system, including the final connection/disposal to owner acceptance points shall be pat of Supplier's scope including all required civil work, mechanical and electrical systems. The Contractor shall connect his drain(s) at one or more points to outfall points as feasible at site. 10. The drainage scheme and associated drawings shall be got approved. 6. 9.0 ROADS AND CULVERTS 1. The main approach road including modification of existing road to meet the site conditions, roads for access to equipment and building within substation are in the scope of bidder. Layout of the roads shall be based on General detail and Arrangement drawing for the substation. 2. All substation roads be constructed so as to permit transportation of all heavy equipment. The roads shall have min.3.75 black topping. Moorum shoulder shall be provided on either side of the road. The width of the shoulder shall be as per approved drawing depending upon the site conditions. 3. Road construction shall be as per IRC standards. 4. Adequate provision shall be made for road drainage. Protection of cut and embankment slopes of roads as per slope stability requirement shall be made. 5. All the culverts and its allied structure (required for road/rail, drain trench crossings, etc.) shall be designed for Class-AA loading as per IRC standards code and should be checked for loading. 6. All roads shall be designed for Class-'E' of traffic as per IRC-37 Guidelines for the design of flexible pavements. 10.0 TRANSFORMER FOUNDATION The Contractor shall provide a road system integrated with the transformer foundation to enable installation and the replacement of any failed unit by the spare unit located at the site. This system shall enable the removal of any failed unit from its foundation to the nearest road. If trench/drain crossings are required the suitable R.C.C. culverts shall be provided in accordance with I.R.C. Code & relevant IS. 11.0 FIRE PROTECTION WALLS 11.1 General Fire protection walls shall be provided in accordance with Tariff Advisory Committee (TAC) recommendations. 11.2 Application Criteria A firewall shall be erected between the transformer to protect each one from the effects of fire on another as per TAC guidelines. Also, if the free distance between the transformer and auxiliary services transformer is less. 11.3 Fire resistance The firewall shall have a minimum fire resistance of 3 hours. The partitions, which are made to reduce the noise level, shall have the same fire resistance where the partitions are also used as firewalls. The walls of the building, which are used as firewalls, shall also have a minimum fire resistance of 3 hours. The firewall shall be designed in order to protect against the effect of radiant heat and Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 30 Technical Specification flying debris from an adjacent fire. 11.4 Mechanical resistance The firewall shall have the mechanical resistance to withstand local atmospheric conditions. If this wall shall serve as a support for equipment such as insulators, etc., its mechanical rigidity must be increased. Connecting the walls by steel or other structures, which may produce a reversing torque if overheated, shall be avoided. 11.5 Dimensions The firewall shall extend at least 2 m on each side of the transformer and at least 1 m above the conservator tank or safety vent. These dimensions might be reduced in special cases, and if T AC permits so, where there is lack of space. A minimum of 2 meter clearance shall be provided between the equipments e.g., transformer and fire walls. The building walls, which act as firewalls, shall extend at least 1 m above the roof in order to protect it. 11.6 Materials The firewall may be made of reinforced concrete (M-20 grade), as per the system requirements. Materials used must conform to the standards of the National Fire Prevention Association and T AC norms. 12.0 CABLE AND PIPE TRENCHES 1. The cable trenches and precast removable RCC cover (with lifting arrangement) 2. The cable trench wall shall be designed for the following loads. i) Dead load of 155 Kg/m length of cable support + 75 Kg on one tier at the end. ii) Triangular earth pressure + uniform surcharge pressure of 2 T/m2. 3. Cable trench covers shall be designed for self-weight of top slab + UDL of 2000 Kg/ m2 + concentrated load of 200 Kg at centre of span on each panel. 4. Cable trench crossing the road/rails shall be designed for class AA. Loading of IRC/relevant IS Code and should be checked for transformer loading. 5. Trenches shall be drained. Necessary sumps be constructed and sump pumps if necessary shall be supplied. Cable trenches shall not be used as storm water drains. 6. The top of trenches shall be kept at least 100 mm above the finished ground level. The top of cable trench shall be such that the surface rainwater does not enter the trench. 7. All metal parts inside the trench shall be connected to the earthing system. 8. Cables from trench to equipments shall run in hard conduit pipes. 9. Trench wall shall not foul with the foundation. Suitable clear gap shall be provided. 10. The trench bed shall have a slope of 1/500 along the run and 1/250 perpendicular to the run. 11. All the construction joints of cable trenches i.e., between base slab to base slab and the junction of vertical wall to base slab as well as from vertical wall to wall and all the expansion joints shall be provided with approved quality PVC water stops of approx. 230 x 5 mm size for those sections where the ground water table is expected to rise above the junction of base slab and vertical wall of cable trenches. 12. Cable trenches shall be blocked at the ends if required with brick masonry in cement sand mortar 1:6 and plaster with 12 mm thick 1:6 cement sand mortar. 13. Cable trenches shall be provided with suitable hangers to support the running cables. 13.0 FOUNDATION I RCC CONSTRUCTION 13.1 General 1. Work covered under this Clause of the Specification comprises the design and construction of foundations and other RCC constructions for switchyard structures, equipment supports, trenches, drains, jacking pad, control cubicles, bus supports, transformer, marshalling kiosks, auxiliary equipments and systems, buildings, tanks, boundary wall or for any other equipment or service and any other foundation required to complete the work. This clause is as well applicable to the other ECC constructions. 2. Concrete shall conform to the requirements mentioned in IS: 456 and all the tests shall Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 31 Technical Specification be conducted as per relevant Indian Standard Codes as mentioned in Standard field quality plan appended with the specification. A minimum grade of M20 concrete (1:5:3 mix) shall be used for all structural/load bearing members as per latest IS 456. 3. If the site is sloppy, the foundation height will be adjusted to maintain the exact level of the top of structures to compensate such slopes. 4. The switchyard foundation's plinths and building plinths shall be minimum 300 mm and 500 mm above finished ground level respectively. 5. Minimum 75 mm thick lean concrete (1:4:8) shall be provided below all underground structures, foundations, trenches, etc., to provide a base for construction. 6. Concrete made with Portland slag cement shall be carefully cured and special importance shall be given during the placing of concrete and removal of shuttering. 7. The design and detailing of foundations shall be done based on the approved soil data and sub-soil conditions as well as for all possible critical loads and the combinations thereof. The Spread footings foundation or pile foundation as may be required based on soil/sub-soil conditions and superimposed loads shall be provided. 8. If pile foundations are adopted, the same shall be case-in-situ driven/bored or precast or under-reamed type as per relevant parts of IS Code 2911. Only RCC piles shall be provided. Suitability of the adopted pile foundations shall be justified by way of full design calculations. Detailed design calculations shall be submitted by the bidder showing complete details of piles/pile groups proposed to be used. Necessary initial load test shall also be carried out by the 'bidder at their cost to establish the piles design capacity. Only after the design capacity of piles has been established, the Contractor shall take up the job of piling. Routine tests fro the piles shall also be conducted. All the work (design & testing) shall be planned in such a way that these shall not cause any delay in project completion. 13.2 Design All foundation shall be of reinforced cement concrete. The design and construction of RCC structures shall be carried out as per IS: 456 and minimum grade of concrete shall be M20. Higher grade of concrete than specified above may be used at the discretion of Contractor without any additional financial implication to the Owner. Limit state method of design shall be adopted unless specified otherwise in the specification. For detailing of reinforcement IS: 2502 and SP: 34 shall be followed. Cold twisted deformed bars (Fe=415 N/mm2) conforming to IS: 1786 shall be used as reinforcement. However, in specific areas, mild steel (Grade-I) conforming to IS: 432 can also be used. Two layers of reinforcement (on inner and outer face) shall be provided for wall and slab sections having thickness of 150 mm and above. Clear cover to reinforcement towards the earth face shall be minimum 40 mm. RCC water retaining structures like storage tanks, etc., shall be designed as uncracked section in accordance with IS: 3370 (Part I to IV) by working stress method. However, water channels shall be designed as cracked section with limited steel stresses as per IS: 3370 (Part I to IV) by working stress method. The procedure used for the design of the foundations shall be the most critical loading combination of the steel structure and or equipment and or superstructure and other conditions, which produces the maximum stresses in the foundation or the foundation component and as per the relevant IS Codes of foundation design. Detailed design calculations shall be submitted by the bidder showing complete details of piles/pile groups proposed to be used. Design shall consider any sub-soil water pressure that may be encountered following relevant standard strictly. Necessary protection to the foundation work, if required shall be provided to take care of any special requirements for aggressive alkaline soil, black cotton soil or any other type of soil which is detrimental/harmful to the concrete foundations. RCC columns shall be provided with rigid connection at the base. All sub-structures shall be checked for sliding and overturning stability during both Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 32 Technical Specification construction and operating conditions for various combinations of loads. Factors of safety for these cases shall be taken as mentioned in relevant IS Codes or as stipulated elsewhere in the Specifications. For checking against overturning, weight of soil vertically above footing shall be taken and inverted frustum of pyramid of earth on the foundation should not be considered. E Earth pressure for all underground structures shall be calculated using coefficient of earth pressure at rest, co-efficient of active or passive earth pressure (whichever is applicable). However, for the design of substructures of any underground enclosures, earth pressure at rest shall be considered. ln addition to earth pressure and ground water pressure etc., a surcharge load of 2T/Sq.m shall also be considered for the design of all underground structures including channels, sumps, tanks, trenches, sub-structure of any underground hollow enclosure, etc., for the vehicular traffic in the vicinity of the structure. Following conditions shall be considered for the design of water tank in pumps house, channels, sumps, trenches and other underground structures: a) Full water pressure from inside and no earth pressure and ground water pressure and surcharge pressure from outside (application only to structures, which are liable to be filled up with water or any other liquid). b) Full earth pressure, surcharge pressure and ground water pressure from outside and no water pressure from inside. c) Design shall also be checked against buoyancy due to the ground water during construction and maintenance stages. Minimum factor of safety of 1.5 against buoyancy shall be ensured ignoring the superimposed loadings. The foundations shall be proportioned so that the estimated total and differential movements of the foundations are not greater than the movements that the structure or equipment is designed to accommodate. The foundations of transformer and circuit breaker shall be of block type foundation. Minimum reinforcement shall be governed by IS: 2974 and IS: 456. The tower and equipment foundations shall be checked for a factor of safety of 2.2 for normal condition and 1.65 for short circuit condition against sliding, overturning and pullout. The same factors shall be used as partial safety factor overloads in limit st 1te design also. 13.3 Admixtures & Additives Only approved admixtures shall be used in the concrete for the Works. When more than one admixture is to be used, each admixture shall be batched in its own, batch and added to the mixing water separately before discharging into the mixer. Admixtures shall be delivered in suitably labeled containers to enable identification. Admixtures in concrete shall conform to IS: 9103. The water proofing cement additives shall conform to IS: 2645. Owner shall approve concrete Admixtures/Additives. The Contractor may propose and the Owner may approve the use of a water-reducing setretarding admixture in some of the concrete. The use of such an admixture will not be approved to overcome problems associated with inadequate concrete plant capacity or improperly planned placing operations and shall only be approved as an aid to overcoming unusual circumstances and placing conditions. The water reducing set-retarding admixture shall be an approved brand of Lignosulphonate type admixture. The water proofing cement additives shall be used as required/advised by the owner. 14.0 GATES AND BOUNDARY WALL The Gate frame shall be made of medium duty MS pipe conforming to relevant IS with welded joints. The gates shall be fabricated with welded joints to achieve rigid connections. The gate frames shall be painted with one coat of approved steel primmer and two coats of synthetic enamel paint. Gates shall be fitted with approved quality iron hinges, latch and latch catch. Latch and latch catch shall be suitable for attachment and operation of pad lock from either side of gates. Hinges shall permit gates to swing through 180 degree back against fence. Gates shall be fitted with galvanized chain hook or gate hold back to hold gates open. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 33 Technical Specification Double gates shall be fitted with centre rest and drop bolt to secure gates in closed position. Gates shall be installed in locations shown on drawings. Next to the main gate, a men gate (1.25 m wide, single leaf) shall also be provided. Bottom of gates shall be set approximately 40 mm above ground surface and necessary guiding mechanism shall be fitted. The Contractor shall design and& construct boundary wall around substation area as per requirements. The boundary wall shall be of height 3.0M and shall be made of RCC frame construction with RCC column and plinth beam arrangement and panels filled with one brick thick wall in cement sand mortar 1 :6. The boundary wall shall be plastered on both external and internal faces with cement and sand plaster 1:6 of thickness18 mm and 12 mm respectively. An additional barbed Y -shaped arm of M8 angle 50x50x6 with 3-rows (6 nos) barbed wire A-4 18:278. Expansion joints shall be provided as per codal requirements. M8 grating shall be provided at required locations for drainage purposes. The boundary wall shall be painted with minimum two coats of color wash over a base coat of white wash with line. The front portion of boundary wall shall however be with a RC jail and 12 mm square MS bar top above brick work and pebble dash plaster finish with colour pigment. The steel work shall be given two coats of synthetic enamel paint of approved make over one coat of primer. A tentative drawing is enclosed for guidance purpose. A Security room shall be provided at the entrance of switchyard. The minimum dimension of the room shall be 3.0 m length and 3.0 m width. The roof shall be at RCC and aesthetically pleasing. 15.0 BUILDINGS - GENERAL REQUIREMENTS 15.1 General The scope include the design, engineering and construction including anti-termite treatment, plinth protection, DPC of Building including sanitary, water supply, electrification, false ceiling etc., of control room building, and DG set building. The buildings shall be of RCC framed structure of concrete of M20 grade (Min.) 15.2 Control Room Building Minimum floor area requirements shall be 120 Sq. Meter which may be increased at the time of detailed engineering to suit project requirements. The layout of the control room shall be finalized as per detailed engineering to suit project requirements. An open space of 1 m minimum shall be provided on the periphery of the rows of panel and equipment generally in order to allow easy operator movement and access as well as maintenance. Any future possibility of annexed building shall be taken care of while finalizing the layout of the control room building. Minimum head room of 3 M below soffit of beams/false ceiling shall be considered for rooms. The roof shall have four side sloping roof or flat roof as finalized during detailed engineering. 15.2.1 Design The buildings shall be designed: i. To the requirements of the National Building Code of India, and the standards quoted therein. ii. For the specified climatic and loading conditions iii. To adequately suit the requirements of the equipment and apparatus contained in the buildings and in all respects to be compatible with the intended use and occupancy iv. With a functional and economical space arrangement. v. For a life expectancy of structure, systems and components not less than that of the equipment, which is contained in the building, provided regular maintenance is carried out vi. Be aesthetically pleasing. Different buildings shall show a uniformity and consistency in architectural design. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 34 Technical Specification vii. To allow for easy access to equipment and maintenance of the equipment. viii. With, wherever required, fire retarding materials for walls, ceilings and doors, which would prevent supporting or spreading of fire. ix. With materials preventing dust accumulation. b) Suitable expansion joints shall be provided in the longitudinal direction wherever necessary with provision of twin columns. c) Individual members of the buildings frame shall be designed for the worst combination of forces such as bending moment, axial force, shear force, torsion, etc. d) Permissible stresses for different load combinations shall be taken as per relevant IS Codes. e) All cable vaults shall be located above ground levels i.e., cable vaults shall not be provided as basements in the buildings. f) The building lighting shall be designed in accordance with the requirements. g) One emergency exit shall be provided in control room building. 15.2.2 Design loads Building structures shall be designed for the most critical combinations of dead loads, super-imposed loads, equipment loads, crane load, wind loads, seismic loads, and temperature loads. Dead loads shall include the weight of structures complete with finishes, fixtures and partitions and should be taken as per IS: 1911. Super-imposed loads in different areas shall include live loads, minor equipment loads, cable trays, small pipe racks/hangers and erection, operation and maintenance loads. Equipment loads shall constitute, if applicable, all load of equipments to be supported on the building frame. For crane loads an impact factor of 30% and lateral crane surge of 10% (lifted weight + trolley) shall be considered in the analysis of frame according to provisions of IS: 875.the horizontal surge shall be 5% of the static wheel load. The wind loads shall be computed as per IS 875, Seismic Coefficient method shall be used for the seismic analysis as per IS 1893 with importance factor 1.5. For temperature loading, the total temperature variation shall be considered as 2/3 of the average maximum annual variation in temperature. The average maximum annual variation in temperature for the purpose shall be taken as the difference between the mean of the daily minimum temperature during the coldest month of the year and mean of daily maximum temperature during the hottest month of the year. The structure shall be designed to withstand stresses due to 50% of the total temperature variation. Wind and Seismic forces shall not be considered shall not be considered to act simultaneously. Floors/slabs shall be designed to carry loads imposed by equipment, cables piping travel of maintenance trucks and equipment and other loads associated with building. Floors shall be designed for live loads as per relevant IS. Cable and piping loads shall also be considered additionally for floors where these loads are expected. In addition, beams shall be designed for any incidental point loads to be applied at any point along the beams. The floor loads shall be subject to Owner's approval. For consideration of loads on structures, IS: 875, the following minimum superimposed live loads shall, however, be considered for the design. a) Roof 1.5 KN/M2 For accessible roofs 0.75 KN./M2 For in- accessible roofs b) RCC- Floor i) 5 KN/M2 For offices 2 ii) 10 KN/M For equipment floors or ( Minimum) actual requirement, if higher than 10 KN/M2, based on equipment component weight and layout plans c) Toiler Room 2 KN/M2 d) Chequered plate floor 4 KN/M2 e) Walkways 3 KN/M2 Any additional load coming in the structure shall be calculated as per IS: 875. 15.2.3 Submission Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 35 Technical Specification The following information shall be submitted for review and approval to the Owner: Design criteria shall comprise the codes and standards used, applicable climatic data including wind loads, earthquake factors maximum and minimum temperatures applicable to the building locations, assumptions of dead and live loads, including equipment loads, impact factors, safety factors and other relevant information. Structural design calculations and drawing (including constructions / fabrication) for all reinforced concrete and structural steel structures. Fully, dimensioned concept plan including floor plans, cross-sections, longitudinal sections, elevations and perspective view of each building. These drawings shall be drawn at a scale not smaller than 1 :50 and shall identify the major building components. Fully dimensioned drawings showing details and sections drawn to scales of sufficient size to clearly show sizes and configuration of the building components and the relationship between them. Product information of building components and materials, including walls partitions flooring ceiling, roofing, door and windows and building finishes. A detailed schedule of building finishes including colour schemes. A door and window schedule showing door types and locations, door lock sets and latch and other door hardware. Approval of the above information shall be obtained before ordering materials or starting fabrication or construction as applicable. 15.2.4 Finish Schedule The finishing schedule is given in subsequent clauses. 15.2.5 Flooring Flooring in various rooms of control room building shall be as for detailed schedules given in Table-1. High Voltage insulating mat conforming to IS 15652:2006 are to be provided in front of Indoor Switchgear Control panels inside the Control Room. 15.2.6 Walls Control room buildings shall be of framed superstructure. All walls shall be non-load bearing walls. Min. thickness of external walls shall be 230 mm (One brick) with 1:6 cement sand mortar. 15.2.7 Plastering All internal walls shall have minimum 15 mm thick 1:6 cement sand plaster. The ceiling shall have 6mm thick 1:4 cement sand plaster. 15.2.8 Finishing All external surfaces shall have 18 mm cement plaster in two coats, under layer 12 mm thick cement plaster 1:5 and finished with a top layer 6 mm thick cement plaster 1:6 (DSR (13.19) with water proofing compound. The paint shall be anti-fungal quality of reputed brand suitable for masonry surfaces for high rainfall zone. White cement primer shall be used as per manufacturer's recommendation. INTERNAL FINISH SCHEDULE IS GIVEN TABLE - 1 SI Location No. 1. Control Room & Relay room Flooring & Skirting 150 mm High Homogeneous PVC /Vetrified tiles 2 mm thick over 25 mm thick 1 :2:4 under bed neat cement Wall Internal Ceiling Plastic 7.3 mm False thick Ceiling ceramic tiles & (DSR Under deck 11.41 A.2.1) insulation Doors, Windows Ventilators Anodised aluminium Jindal or equivalent extruded sections as per IS 733 & 1285 Glazing Flat (DSR 97-11.64.2 drawn sheet & 11.4.1) glass (Min 5.5 mm Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 36 Technical Specification finished flooring 2. Sub-Station incharge, officers, corridor, staff, rooms 3. Battery room 4. Cable vault double sheet (if required) 5. Toilet 6. Other areas not specified Oil bound plastic paint washable distemper on smooth surface applied with POP putty Smooth surface (DSR-97) applied with (11.48.1) POP putty. DADO acid resistant title 2.1 M high Acid resistant paint above Acid Resistant 2.1 M Tiles high acid 25 mm thick resistant (DSR paint above 9711.36 C 12) 2.1 m upto ceiling (DSR 97.11.36 C 2.2) & 13.96.1) Oil bound IPS flooring distemper (DSR 97 White wash 11.4.3) (DSR 97 13.72.1) DADO glazed tile Non-solid/ 2.1 M high for vetrified toilet for pantry Terrazzo tiles above working with platform upto White cement 750 (DSR97,11.29 mm a.1) (DSR 97 11.36B) Vetrified Plastic/O.B. Terrazzo tiles distemper Dry with distemper white cement (DSR (DSR 97 29 97.13.75) A.1) Vetrified Terrazzo tiles with white cement (DSR97) (11.29 A.1) thick) double glazing with 12 mm gap hermetically sealed. (DSR097, 24.1, 24.3, 24.4 False ceiling & under deck insulation Teak wood frame flush doors shutter (DSR 97 9.1.3 & 9.4 A.2.2) Windows, Ventilators Aluminium as at 1. For entrance with glazing Steel door 45 mm thick double Acid sheet 18 G steel suitably resista reinforced and filled with nt mineral paint (DSR wool. Hot rolled steel 97 framed 1372.1) glazed window and ventilators. White wash Steel door double sheet as above. Ventilators as at 5. White wash Weather coat Teak wood frame flush door shutter with anodized Aluminium fixtures best quality (DSR 97 9.1.3 & 9.4 a 2) Windows, ventilators aluminium as at 1. White wash Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 37 Technical Specification Note : DSR item references to be read with CPWD specifications are only for material and workmanship guidance of the Contractor. 15.2.9 Roof Roof of the CR. Building shall consist of Cast-in-situ RCC slab treated with a water proofing system which shall be an integral cement based treatment conforming to CPWD specification (item NO.25.8 of DSR 1997) the water proofing treatment shall be of following operations. a) Applying and grouting a slurry coat of neat cement using 2.75 kg/m2 of cement admixed with proprietary water proofing compounds conforming to IS:2645 over the RCC slab including cleaning the surface before treatment. b) Laying cement concrete using broken bricks/bricks brick bats 25 mm to 100 mm size with 505 of cement mortar 1:5 (1 cement: 5 coarse sand) admixed with proprietary water proofing compound conforming to IS: 2645 over 20 mm thick layer of cement mortar of min 1:5 (Cement: 5 coarse sand) admixed with proprietary water proofing compound conforming to IS:2645 to required slope and treating similarly the adjoining walls upto 300 mm height including rounding of junctions of walls and slabs. c) After two days of proper curing applying a second coat of cement slurry admixed with proprietary water proofing compound conforming to IS:2645. d) Finishing the surface with 20 mm thick joint less cement mortar of mix 1:4 (1 cement: 4 course sand) admixed with proprietary water proofing compound conforming to IS:2645 and finally finishing the surface with trowel with neat cement slurry and making of 300 x 300 mm square. e) The whole terrace so finished shall be flooded with water for a minimum period of two weeks for curing and for final test. All above operations to be done in order and as directed and specified by the Engineering-in-charge. With average thickness of 120 mm and minimum thickness at khurra at 65 mm. 15.2.10 Glazing Minimum thickness of glazing shall be 5.5 mm as per IS:2835 sun film shall be provided for all window/doors of AC rooms. 15.2.11 Doors and Windows The details of doors and windows of the control room building shall be as per finish schedule Table-1 and tender drawing with the relevant IS, code. Rolling steel shutters and rolling steel grills shall be provided as per layout and requirement of buildings. Paints used in the work shall be of best quality specified in CPWD specification. 15.2.12 Plumbing & Sanitation i) All plumbing and sanitation shall be executed to comply with the requirements of the appropriate bye-laws, rules an regulations of the Local Authority having jurisdiction over such matters. The Contractor shall arrange for all necessary formalities to be met in regard to inspection, testing, obtaining approval and giving notices etc. ii) PVC syntax or equivalent make Roof water tank of adequate capacity depending on the number of users for 24 hours storage shall be provided. Minimum 2 Nos 500 litres capacity shall be provided. iii) Galvanized MS pipe of medium class conforming to IS: 1239 shall be used for internal & external piping work for potable water supply. iv) Sand CI pipes with lead joints conforming to IS:1729 shall be used for sanitary works above ground level. v) Each toilet shall have the following minimum fittings. a) WC (Western type) 390 mm high with toilet paper roll holder and all fittings or WC (Indian Type) Orissa Pattern (580 x 440 mill) with all fittings. (Both types of WCs shall be provided at alternate locations) b) Urinal (430 x 260 x 350 mm size) with all fittings. c) Wash basin (550 x 400 mm size) with all fittings. d) Bathroom mirror (600 x 450 x 6 mm thick) hard board backing. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 38 Technical Specification e) CP brass towel rail (600 x 20 mm) with CP brass brackets. f) Soap holder and liquid soap dispenser. vi) Water cooler for drinking water with adequate water storage facility shall be provided and located near control room instead of near toilet block. vii) An Eye & [ace fountain conforming to IS:1052 shall be provided for battery room viii) 1 No. stainless steel kitchen sink with Drain board (510 x 1040 x 178 mm bowl depth) for pantry shall be provided. ix) All fittings, fastener, grating shall be chromium plated. x) All sanitary fixtures and fittings shall be of approved quality and type manufactured by well known manufacturers. All items brought to site must bear identification marks of the type of the manufacturer. xi) Soil, waste and drain pipes, for underground works shall be stone ware for areas not subject to traffic load. Heavy-duty cast iron pipes shall be used otherwise. 16.0 SECURITY FENCING Security fencing shall be provided for 1.5 meter above the ground at the switchyard. Security fencing shall be provided with barbed wire mesh of 5 rows connected with the PSCC poles at 2 meters interval. 17.0 MISCELLANEOUS GENERAL REQUIREMENTS 17.1 Dense concrete with controlled water cement ratio as per IS-code shall be used for all underground concrete structures such as pump-house, tanks, water retaining structures, cable and pipe trenches etc. for achieving water tightness. 17.2 All joints including construction and expansion joints for the water retaining structures shall be made water tight by using PVC ribbed water stops with central bulb. However, kicker type (externally placed) PVC water stops shall be used for the base slab and in other areas where it is required to facilitate concreting. The minimum thickness of PVC water stops shall be 5 mm and minimum width shall be 230 mm. 17.3 All steel sections and fabricated structures which are required to be transported on sea shall be provided with anti corrosive paint to take care of sea worthiness. 17.4 All mild steel parts used in the water retaining structures shall be hot-double dip galvanized. The minimum coating of the zinc shall be 750 gm/sq. m for galvanized structures and shall comply with IS:2629 and IS:2633. Galvanizing shall be checked and tested in accordance with 18:2633.The galvanizing shall be followed by the application of an etching primer and dipping in black bitumen in accordance with B8:3416. 17.5 A screed concrete layer not less than 100 mm thick and of grade not weaker than M10 conforming to IS:456-1978 shall be provided below all water retaining structures. A sliding layer of bitumen paper or craft paper shall be provided over the screed layer to destroy the bond between the screed and the base slab concrete of the water retaining structures. 17.6 Bricks having minimum 75 kg/cm2 compressive strength can only be used for masonry work. Contractor shall ascertain himself at site regarding the availability of bricks of minimum 75 kg/cm2 compressive strength before submitting his offer. 17.7 Doors and windows on external walls of the building (other than areas provided, with insulated metal claddings) shall be provided with RCC sun-shade over the openings with 3000 mm projection on either side of the openings. Projection of sunshade from the wall shall be minimum 450 mm over window openings and 750 mm over door openings. 17.8 All stairs shall have maximum riser height of 150 mm and a minimum tread width of 300 mm. Minimum width of stairs shall be 1500 mm. Service ladder shall be provided for Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 39 Technical Specification access to all roofs. RCC fire escape staircase shall be provided in control buildings. 17.9 Angles 50 x 50 x 6 mm (minimum) with lugs shall be provided for edge protection all round cut outs/openings in floor slab, edges of drains supporting grating covers, edges of RCC cable/pipe trenches supporting covers, edges of manholes supporting covers, supporting edges of manhole precast cover and any other place where breakage of corners of concrete is expected. 17.10 Anti termite chemical treatment shall be given to column pits, wall trenches, foundations of buildings, filling below the floors etc. as per IS:6313 and other relevant Indian Standards. 17.11 Hand-railing minimum 900 mm high shall be provided around all floor/roof openings, projections/balconies, walk ways, platforms, steel stairs etc. All handrails and ladder pipes shall be 32 mm nominal bore MS pipes (medium class) and shall be galvanized (mediumclass as per IS:277). All rungs for ladder shall also be galvanized as per IS:277 medium classes. For RCC stairs, hand railing with 20 mm square MS bars, balustrades with suitable MS flats shall be provided with black PVC sheathing. 17.12 For all civil works covered under this specification, nominal mix by volume batching as per CPWD specification is intended. The relationship of grade of concrete and ratio of ingredients shall be as below: S.No. Mix Cement Sand Coarse Aggregate of 20 mm Down Grade as per IS 383 1. M 10 1 3 6 2. M 15 1 2 4 3. M 20 1 1.5 3 The material specification, workmanship and acceptance criteria shall be as per relevant clauses of CPWD specification and approved standard Field Quality Plan. 17.13 The details given in tender drawings shall be considered along with details available in this section of the specification while deciding various components of the building. 17.14 Items/components of buildings not explicitly covered in the specification but required for completion of the project shall be deemed to be included in the scope. 18.0 INTERFACING The proper coordination & execution of all interfacing civil works activities like fixing of conduits in roofs/walls/floors, fixing of foundation bolts, fixing of lighting fixtures, fixing of supports/embedment, provision of cutouts etc. shall be the sale responsibility of the Contractor. He shall plan all such activities in advance and execute in such a manner that interfacing activities do not become bottlenecks and dismantling, breakage etc. is reduced to minimum. 19.0 WATER SUPPLY i) Contractor shall make its own arrangement for construction water. ii) The contractor shall carry out all the plumbing/erection works required for supply of water in control room building. iii) The details of tanks, pipes, fittings, fixtures etc for water supply are given elsewhere in the specification under respective sections. iv) A scheme shall be prepared by the contractor indicating the layout and details of water supply which shall be got approved by the Owner before actual start of work including all other incidental items not shown or specified but as may be required for complete Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 40 Technical Specification performance of the works. v) Bore wells with Min 100mm dia casing pipe & 1HP submersible pump to get a discharge of at least 1000 Litre/Hr. with zealete make iron removed filter to get iron free water. Water purifier with UV mechanism is to be provided and pumps for water supply are in the scope of contractor meeting the day-to-day requirement of the water supply. 20.0 SEWERAGE SYSTEM i) Sewerage system shall be provided for control room building. ii) The contractor shall construct septic tank and soak pit suitable for 20 users. iii) The system shall be designed as per relevant IS Codes. 21.0 STATUTORY RULES 21.1 Contactor shall comply with all the applicable statutory rules pertaining to factories act (as applicable for the State). Fire Safety Rules of Tariff Advisory Committee. Water Act for pollution control etc. 21.2 Provisions for fire proof doors, no. of staircases, fire separation wall, plastering on structural members (in fire prone areas) etc. shall be made according to the recommendations of Tariff Advisory Committee. 21.3 Statutory clearance and norms of State Pollution Control Board shall be followed as per Water Act for effluent quality from plant. 21.4 Requirement of sulphate resistant cement (SRC) for sub-structural works shall be decided in accordance with the Indian Standards based on the findings of the detailed soil investigation to be carried by the bidder. 21.5 Foundation system adopted by the Bidder shall ensure that relative settlement and other criteria shall be as per provision in IS:1904 and other Indian Standard. 21.6 All water retaining structures designed as an un-cracked section shall also be tested for water tightness at full water level in accordance with clause No. 10 of IS:3370 (part-I) 21.7 Construction joints shall be as per IS:456 21.8 All underground concrete structures like basements, pumps houses, water retaining structures etc. shall have plasticizer cum water proofing cement additive conforming to IS:9103. in addition, limit on permeability as given in IS:2645 shall also be met with. The concrete surface of these structures in contact with earth shall also be provided with two coats of bituminous painting for water/damp proofing. In case of water leakage in the above structures, Injection Method shall be applied for requiring the leakage. 2.12 1.0 TECHNICAL SPECIFICATIONS FOR 36 KV VACUUM CIRCUIT BREAKER SCOPE 1.1 This section of specification covers the design, manufacture, assembly under stringent quality control at every stage of manufacturing, testing at manufacturer's works before dispatch, supply and delivery at destination store and supervision of erection, testing and commissioning of 36 KV outdoor type vacuum circuit breakers at various substations in SEB. 1.2 The scope of supply shall also include necessary special tools and plants required for erection, maintenance and necessary spares, required for normal operation and maintenance of the circuit breakers for a period of five years. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 41 Technical Specification 1.3 The circuit breakers should be complete in all respects with insulators, bimetallic connectors, interrupting chamber, operating mechanism control cabinet, interlocks, auxiliary switches indicating devices, supporting structures, accessories, etc., described herein and briefly listed in the schedule of requirements. The spares/attachments which are meant necessary for the smooth functioning of the equipment and specifically are not mentioned here shall be assumed to be included the scope of supply. 1.4 It may be noted that the Vacuum Circuit Breaker must meet the following minimum criteria. Failure to comply with the requirements may results in rejection of the BID as non-responsive: 1.4..1 The Manufacturer must have designed, manufactured, type tested and supplied vacuum circuit breaker in at least two power utilities of similar rating which are in successful operation for at least 5 (Five) years as on the date of bid opening which should be substantiated by furnishing performance report from the official of the rank not below DGM/SE 1.5 The manufacturer of the VCB must use their own make Vacuum Interrupters and must have in-house manufacturing facility for Vacuum Interrupter & Breaker (including mechanism) 1.6 Design and construction of Vacuum Circuit Breaker shall be such that there is no possibility for entry of moisture. There should not be any condensation or accumulation of moisture on the internal insulating surfaces and operating rod of the circuit breaker. For this purpose complete interrupter housing and support insulator should be filled either with SF6 gas or with Nitrogen or some other dielectric medium pressurized to avert condensation. For monitoring positive gas pressure monitoring device shall be provided by supplier for each pole. Bidder may please note that any other device like heater, fan etc. which requires operation monitoring on continuous basis are not acceptable to the purchaser. 2.0 STANDARDS 2.1 The circuit breaker shall conform in all respects to the requirements of latest issue of IS/IEC specifications except for modifications specified herein. The equipment manufactured according to any other authoritative standards which ensure an equal or better quality than the provision of IS/IEC specifications shall also be acceptable. The salient point of difference between the proposed standard and provision of these specifications shall be clearly brought out in the tender. A copy of English version of such specifications shall be enclosed with the tender. 2.2 The list of standards mentioned in this specification and to which the circuit conform is given below: 1. IEC-56 High Voltage A.C. Circuit Breakers 2 IEC-137 Bushing for alternating voltage above 1000 volts 3. IEC-71 Insulation Co-ordination Common clauses for high voltages switchgear and control 4. IEC-694 gear standards 5. IEC-815 Specification for Creepage distance Specifications for high voltage alternating current 6. IS-13118 circuit breakersporcelain bushings 7. IS-2099 High voltages 8. IS-4379 Identification of the contents of industrial gas cylinders 9. IS-3072 Installation and maintenance of switchgear Guide for testing of circuit breakers with respect to out 10. IEC-267 of phase switching Code of practice for use of structural steel in overhead 11. IS-802 transmission lines IEC-17A 12. Sealing of interrupters I breakers 5tudy Group 13. IS-1554 PVC insulated cables upto and including 1000 volts Dec.1981 14. IS-5 Colors for ready mixed paints and channels Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 42 Technical Specification 3.0 CLIMATIC CONDITONS The breakers and accessories to be supplied against this specification shall be suitable for satisfactory continuous operation under the tropical conditions specified in this bidding document. 4.0 AUXILIARY POWER SUPPLY 4.1 Auxiliary electrical equipment shall be suitable for operation on the following supply system. a. Power Devices (like drive motors) 415 V, 3 phase 4 wire 50 hz, neutral grounded AC supply b. DC Alarm, Control and Protective Devices 110 V DC, c. Lighting 240 V, single phase 50 Hz AC supply 4.2 5.0 5.1 5.2 Each of the foregoing supplies shall be made available by the Purchaser at the terminal point for each circuit breaker for operation of accessories and auxiliary equipment. Bidder's scope includes supply of interconnecting cables, terminal boxes, etc. The above supply voltage may vary as indicated below and all devices shall be suitable for continuous operation over the entire range of voltages 1) AC Supply 415V (+ 10% /-- 15%) 2) Frequency 50Hz (± 5%) 2) DC Supply 110V ( - 15% to + 10%) GENERAL REQUIREMENT OF 36 KV/OUTDOOR VACUUM CIRCUIT BREAKERS The vacuum type circuit breaker shall have vacuum interrupters, designed to provide a long contact life at all currents upto rated making and breaking current during switching operation: The vacuum interrupters sealed for life shall be encapsulated by porcelain insulators for out door installation requirement of the circuit breakers. The offered breakers shall be suitable for out door operation under climatic conditions specified without any protection from sun, rain and dust storm. The vacuum interrupters of each phase shall be housed in a separate porcelain insulator. The three identical poles shall be mounted on a' common base frame and the contact system of three poles should be mechanically linked to provide three pole gang opening/closing for all type of faults. i. The performance of breakers shall be adequately proven by type tests for the designed rating at internationally reputed independent testing station. ii. The offered equipment shall be practically maintenance free over a long period. iii. All mechanical parts and linkages shall be robust in construction and maintenance free, over at least 30,000 switching operations except for lubrication of pins/articulated joints at interval of 5 years or 5000 operations. iv) Similar parts shall be strictly interchangeable without special adjustment of individual fittings. Parts requiring maintenance shall be easily accessible, without requiring extensive dismantling of adjacent parts. v) The operating mechanism will be self maintained and of proper operation endurance not less than the mechanical life of circuit breaking unit. It shall be spring operated type described hereinafter. vi) The circuit breaker shall be supplied complete with all auxiliary equipment meant necessary for the safe operation, routine and periodic maintenance. All internal wiring including those of spare auxiliary contact. vii) viii) s shall be complete and wired upto terminal blocks situated near cable gland plate. ix) The breaker shall be totally restrike free under all duty conditions and shall be capable of performing the duties without opening resistor. The details of any device incorporated to limit or control the rate of rise of restriking voltage across the circuit breaker contacts shall be stated. x) The breaker shall be reasonably quiet in operation and the noise level shall not Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 43 Technical Specification exceed 140 decibels. xi) The breaker shall be suitable for three phase reclosing operation. xii) An operation counter, visible from the ground level even with the mechanism housing closed shall be provided. 6.0 VACUUM INTERRUPTER ASSEMBLY 6.1 Each pole of the circuit breaker shall be provided with vacuum interrupter, one for each phase, hermetically sealed for life and encapsulated by ceramic insulators. The interrupter shall be provided with steel chromium are chamber to prevent vaporized contact material being deposited on the insulating body. A further shield giving protection to the metal bellows shall also follow the travel of the moving contacts to seal the interrupter against the surroundings atmosphere. 6.2 It shall have high and consistent dielectric strength of vacuum unaffected by environment and switching operations. Bronzed joints should ensure retention of vacuum for life time. It shall have low and stable contact resistance due to absence of oxidation effects and shall ensure low power loss. The arcing voltage shall be low with minimum contact erosion. 6.3 The manufacturer of VCB should use their own Vacuum interrupter so that the drive mechanism is matched perfectly with that of the requirement of Vacuum Interrupter. 6.4 The vacuum bottles should be capable of withstanding minimum 100 full short circuit operations as per test duty 1 to 5 of IEC-56. The vacuum bottles, capable of withstanding less than 100 full short circuit faults, would not be considered and therefore should not be offered. 6.5 A manufacture‘s type test reports / literature for vacuum bottles, may, therefore be supplied along with tender in duplicate. 6.6 Vacuum Interrupters of China make should not be offered. 7.0 FIXED AND MOVING CONTACT 7.1 The fixed and moving contacts of the breaker have to ensure permanent full contact during closing without unusual maintenance. All making and breaking contacts shall be hermetically sealed and free from atmospheric effects. 7.2 The contacts metallurgy and geometry shall be such that there is minimum contact burning and wear. Main contact shall have ample area and contact pressure for carrying the rated current and rated short time current without excessive temperature rise which may cause pitting or welding of the contacts. 7.3 7.4 8.0 The main contacts should have low contact resistance. The contact should be self cleaning type, i.e., the layer of copper oxide should be cleaned during rubbing of contacts. The contact area should be well defined, spring used for contact shall be of gradually rising characteristic i.e., they should be soft. The contacts should not provide contact grip, ie., electro-magnetic forces should not grip the contacts and oppose the opening process. It would be desirable to have separate main contacts and arcing contacts in order to have longer life of the contacts. The contours of the energized metal parts of the breaker shall be such as to eliminate areas or points of high electrostatic flux concentration. Surfaces shall be smooth with no projection or irregularities which may cause visible corona. No corona shall be visible in complete darkness when the equipment is subjected to the specified test voltage. The circuit breaker units shall be suitable for installation on outdoor R.C.C. foundations. Ground clearance of the live parts of the breakers should be 3700 mm from foundation. The circuit breakers shall be spring operated. RECOVERY VOLTAGE AND POWER FACTOR 8.1 The circuit breaker shall be capable of interrupting rated power with recovery voltage equal to the rated maximum line to line service voltage at rated frequency and at a power factor equal to or exceeding 0.15. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 44 Technical Specification 9.0 RESTRIKING RECOVERY and LINE CHARGING INTERRUPTING CAPACITY 9.1 9.2 9.3 The complete data for the phase factor, amplitude factor, etc., for rate of rise of restriking voltage shall be furnished in the tender. The circuit breaker shall be designed so as to be capable of interrupting line charging currents without undue rise in the voltage on the supply side without restrike and without showing sign of undue strains. The maximum permissible switching over voltage shall not exceed 2.5 p.u. The guaranteed over voltage, which will not be exceeded while interrupting the rated line charging current for which the breaker is designed to interrupt shall also be stated. The results of the tests conducted along with the copies of the oscillographs to prove ability of the breakers to interrupt the rated as well as lower values of the line charging current shall be furnished with the tender. 10.0 TRANSFORMER CHARGING CURRENT BREAKING CAPACITY 10.1 The breaker shall be capable of interrupting inductive currents, such as those occurring while switching off unloaded transformers, without giving rise to undue over voltage and without restrikes. The maximum over voltage value, which will not be exceeded under such conditions, shall be stated in the tender. 11.0 BREAKING CAPACITY FOR SHORTLINE FAULTS 11.1 The interrupting capacity of the breaker for short line faults shall be stated in the tender. The details of the test conducted for proving the capability of the breaker under a short line fault occurring from one phase to earth conditions shall also be stated in the tender. The rated characteristics for short line faults shall be in accordance with stipulation contained in clause 8.0 of IEC-56(2)-1971. 12.0 AUTOMATIC RAPID RECLOSING and OUT OF PHASE SWITCHING 12.1 12.2 36 KV circuit breaker shall be suitable for 3 pole rapid reclosing. The dead time of the breaker shall be adjustable and the limits of the adjustment shall be stated in the tender. The circuit breaker shall be capable of satisfactory operation even under conditions of phase opposition that may arise due to faulty synchronization. The maximum power that the breaker can satisfactorily interrupt under "Phase Opposition" shall be stated in the bid". 13.0 TEMPERATURE RISE 13.1 The maximum temperature attained by any part of the equipment when in service at side and under continuous full load conditions and exposed to the direct rays of the sun shall not exceed the permissible limits fixed by IEC. When the standards specify the limits of temperature rise these shall not be exceeded when corrected for the difference between ambient temperature specified in the approved specification. 13.2 The limits of temperature rise shall also be corrected for altitude as per IEC and stated in the bid. 14.0 INSULATORS SUPPORTS AND HOUSING 14.1 The basic insulation level of the external insulator supporting shall be as stated in the "Technical Parameters" and these shall be suitable for use under climatic conditions as stated elsewhere in the specification. The porcelain used shall be homogenous, free from cavities and other flaws. 14.2 The insulators shall be designed to have ample insulation, mechanical strength and rigidity for satisfactory operation under conditions specified above. 14.3 All bushings of identical rating shall be interchangeable. The puncture strength of bushing shall be greater than the flash over value. The design of bushing shall be such that the complete bushing in a self-contained unit and no audible discharge shall be detected at a voltage upto a working voltage (Phase Voltage) plus 10%. The support insulator shall conform to IEC-137. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 45 Technical Specification 14.4 14.5 Minimum clearance between phases, between live parts and grounded objects shall be as per IS-3072-1975 and should conform to Indian Electricity Rules1956. The minimum creepage distance for severely polluted atmosphere shall be 27 mm/KV. . The air clearance of bushing should be such that if the bushings were tested at an altitude of less than 1000 meters, air clearance would withstand the application of higher voltages (IS-2099-1973 para 6.1). In order to avoid breakdown at extremely low pressures the support insulators should not be covered by moisture and conducting dust. Insulators should therefore be extremely clean and should have anti-tracking properties. Sharp contours in conducting parts should be avoided for breakdown of insulation. The insulators shall be capable to withstand the seismic acceleration of 0.5 g in horizontal direction and 0.6g in vertical direction. 15.0 OPERATING MECHANISM GENERAL REQUIREMENTS 15.1 The operating mechanism shall be stored energy type and capable of giving specified duty of the breaker The breaker shall also pass the operational test which ascertain the capabilities of operating mechanism. The operating mechanism shall be capable to perform the following functions efficiently. i) To provide means where the circuit breaker can be closed rapidly, without hesitation at all currents from zero to rated making current capacity. ii) To hold the circuit breaker in closed positions by toggles or latches till the tripping signal is received. iii) To allow the circuit breaker to open without delay immediately on receiving tripping signal. iv) Operating mechanism should also be suitable for three phase auto reclose duty. The closing spring shall be automatically charged by motor immediately after closing operation. v) In case of failure of supply to the spring charging motor, the spring shall be chargeable by hand crank. vi) The contact pressure spring and tripping spring shall be chargeable during closing operation to ensure the breaker is ready to open. vii) Mechanically ON/OFF indicator, spring charged indicator and operation counter shall be provided on the front of the control cubicle. For tripping, the spring provided shall ensure the trippings. 16.0 Tripping/Closing Coils 16.1 The circuit breakers shall be provided with two trip coils and one closing coil per breaker. First trip coil shall be utilized for tripping the breaker on main protection fault detection. Whereas second trip coil shall be used to trip the breaker when first trip coil fails to trip the breaker and backup protection comes into operation and shall also be used to trip the breaker on command. 16.2 The trip coils shall be suitable for pre-closing and after closing trip circuit supervision. All the breakers shall have provision for independent electrical operation of trip coils from local as well as remote through local/remote selector switch. The breaker shall be provided with suitable protection device against discrepancies in the operation of individual pole. 16.3 Closing coil shall operate correctly at all value of voltage between 85% and 110% of the rated voltage. Shunt trip coils shall operate correctly under all operating conditions of the circuit breaker upto the rated breaking capacity and at all values of supply voltage between 70% and 110% of rated voltage. 16.4 Trip Free Features a. When the breaker has been instructed to close by manual instructions by pushing of push button, the operating mechanism will start operating for closing operations. If in the mean time a fault has taken place, the relay provision shall be such that it should close the trip circuit simultaneously interrupting the live circuit of closing coil which has been instructed for close Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 46 Technical Specification command. b. The trip free mechanism shall permit the circuit breaker to be tripped by the protective relay even if it is under the process of closing. An antipumping device to prevent the circuit breaker from reclosing after an automatic opening shall be provided to avoid the breaker from pumping i.e., anti pumping relay should interrupt the closing coil circuit. 17.0 Controls 17.1 The circuit breaker shall be controlled by a control switch located in the control room. The control arrangement shall be such as to disconnect the remote control circuits of the breaker, when it is under test. 17.2 Local control devices, selector switch and position indicator shall be located in weather and vermin-proof cabinet. 17.3 The circuit breaker control scheme shall incorporate trip circuit supervision arrangement. Local/remote selector switch shall be provided for all breakers for selection of "Local" control/remote control. Provision shall be made for local manual, electrical and spring controls. Necessary equipment's for local controls shall be housed in the circuit breaker cabinet of weather-proof construction. In addition to this, a hand closing device for facilitating maintenance shall also be provided. 17.4 Each circuit breaker shall have a mechanical open/closed and spring charge indicator in addition to facilities for provisions for semaphore indicators for breakers which are required for the mimic diagram in the control room. 17.5 Lamps for indicating, 'close/open' position of the breaker shall also be provided. 17.6 Mechanical indicator, to show the 'open' and 'close' position of the breaker shall be provided in a position where it will be visible to a man standing on ground with mechanism housing open. An operation counter, visible from the ground even with the mechanism housing closed, shall be provided. Electrical tripping of the breaker shall be performed by shunt trip coils. 17.7 Operating mechanism and all accessories shall be enclosed in control cabinet. A common marshalling box for the three poles of the breaker shall be provided, along with supply of tubing, cables from individual pole operating boxes to the common marshalling box, local. 18.0 SPRING OPERATED MECHANISM and MOTOR 18.1 The motor compressed spring mechanism shall consist of a closing spring which is wound or compressed by an electric motor immediately after the breaker closes. The closing action shall also wind or compress a tripping springs shall be wound. 18.2 After the breaker has tripped, the tripping spring shall remain in the released position as long as the breaker is open, but the closing spring shall remain wound and ready for closing operation. Spring charging motor shall be standard single phase universal motor suitable for 220 volts supply. i) Operating voltages for closing/tripping coils shall be 110 Volts DC. ii) Operating voltages for heater elements shall be 220V AC 50 HZ. Other features of the spring operated mechanism shall be as follows. 18.3 The spring operating mechanism shall have adequate energy stored in the operating to close and latch the circuit breaker against the rated making current and also to provide the required energy for tripping mechanism in case the tripping energy is derived from the operating mechanism. 18.4 The mechanism shall be capable of performing the rated operating duty cycle of 0-0.3Sec-CO-3 Min-CO as per IEC-56. 18.5 The spring charging motor shall be AC/DC operated and shall not take more than 30 sec., to fully charge the closing spring made for automatic charging. Charging of spring by the motor should not - interfere with the operation of the breakers. 18.6 The motor shall be adequately rated to carry out a minimum of one duty cycle. Also provision shall be made to protect the motor against overloads. 18.7 In case of failure of power supply to spring charging motor, the mechanism shall be capable of performing one open-close-open operation. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 47 Technical Specification 18.8 18.9 19.0 19.1 19.2 19.3 19.4 19.5 19.6 19.7 19.8 Mechanical interlocks shall be provided in the operating mechanism to prevent discharging of the closing springs when the breaker is already in closed position. Provision shall be made to prevent a closing operation to be carried out with the spring partially charged. Facility shall be provided for manual charging of closing springs. CONTROL CABINET The switchgear operating mechanism, the control equipment such switch for closing and tripping the breakers, various control relays, antipumping device, timer for adjusting breaker reclosing, a set of terminal blocks for wiring connections, MCB's for disconnecting the control auxiliary power supplies. Including relays, etc., shall be enclosed in a cabinet to 'be mounted on a suitable structure at a convenient working height at the end of the breaker in the outdoor switchyard. The supporting structure and the enclosure shall be capable of withstanding the typical tropical climatic conditions, change of ambient temperature, severe dust-storms, very high relative humidity those are prevailing at the site of location of switchgear . The enclosure shall be made out of stretched level steel plates not less than 3.15 mm thick and of light section structural steel. It should be weather proof as well as vermin proof and conforming to IP: 55 degree of protection. Each cabinet section shall have full width and full length hinged doors mounted on the front that swing fully open. The doors shall be provided with latches to securely hold it with the cabinet. Doors shall be of sturdy construction, with resilient material covering, to provide dust protection and prevent metal to metal contact except at the latch points. Filtered ventilation shall be provided along with the rigid supports for control and other equipment, measuring instruments, mounting cabinet members and equipment shall not restrict easy access to terminal blocks for terminating and testing external connection or to equipment for maintenance. All screws and bolts used for assembling and mounting wire and cable termination, supports, devices and other equipment shall be provided with lock washers or other locking devices. All metal parts shall be clean and free of weld splatter, rust and mill scale prior to application of double coat of zinc chromate primer which should be followed by an Polyurethane paint to serve as base and binder for tile finishing coat. The exterior of the cubicle shall be painted matty grey to shade NO.692 of IS-5 or shade No.631 and interior to white shade. Sufficient quantity of paints shall also be supplied along with the cubicle to restore at site any damage during transportation. The mounting structure shall be galvanized and shall be as per IS-802-11-1978. Suitable heaters shall be mounted in the cabinet to prevent condensation. Heaters shall be controlled by thermostat ON/OFF switches and fuses shall be provided. Heaters shall be suitable for 240 V AC supply voltage. At least one 20 watts fluorescent tube fixture and lamp holder working on 240V, 50 c/s AC supply shall be provided in each switchgear control cubicle section and shall be located to provide adequate interior lighting of the cubicle. Ballasts shall be rated at not less than 0.90 power factor. A single pole 20 Amp. ‗T‘ rated lighting switch shall be provided for each cubicle, flush-mounted on the left end. One duplex 220 volt convenience outlet shall be provided inside each door or pair of doors inside each cubicle. The lighting and convenient outlet circuits shall be completely wired in conduit and terminated on cubicle terminal blocks. Unless otherwise specified control wire shall be stranded tinned copper stranded wire with 1.1 KV PVC insulation conforming to the requirements of IS-1554. All the control circuit and secondary wiring shall be wired completely and brought out preferably to a vertical terminal block ready for external connections in the control cabinet. The control wire shall not be of cross-section less than 2.5 mm2 copper. All spare auxiliary contacts of the circuit breaker shall be supplied wired upto terminal block.At least 20 number spare terminals shall be provided over and above the number required. All wiring termination on terminal blocks shall be made through lugs. For current and DC supply circuits disconnecting sturdy type terminal blocks will be provided. For other control circuits, non-disconnecting snap on type terminal blocks shall be provided. All wires shall be identified with non-metallic sleeve or tube type markers at each Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 48 Technical Specification terminations. Terminal blocks shall be made up of molded non-inflammable plastic material with blocks and barriers molded integrally have white marking strips for circuit identification and moulded plastic covers. 19.10 A ground bus of copper bar not less than 6 mm by 25 mm shall be provided along the inside of the front or rear of the each cubicle and equipment rack. The ground bus shall be bolted to the frame of each panel in such a way as to make good electrical contact with each panel or section. Lugs shall be provided for connection of the ground bus to the station ground bus/earth mat. 19.9 20.0 20.1 ACCESSORIES Each circuit breaker assembly shall be supplied with the following accessories. i) Line and earthing terminals and terminal connectors. ii) Control housing with: a) One auxiliary switch with adequate number of auxiliary contacts, but not less than 12 nos. (6 No + 6 NC) for each breaker. These shall be over and above the No. of contacts used for closing, tripping and 'reclosing' and interlocking circuit of the circuit breaker. All auxiliary contacts shall be capable of use as "Normally closed" or "Normally open" contacts. Special auxiliary contacts required for the reclosing circuit if any, shall also be provided. There shall be provision, to add more auxiliary contacts at a later date, if required. b) Operation counters c) Position indicator (Close/Open) d) Necessary cable glands e) Fuses f) Manual trip device and local test push buttons g) Terminal blocks and wiring for all control equipment and accessories h) Adequate number of heaters for continuous operation to prevent moisture condensation in the housing of operating mechanism i) Selector switch for local/remote control. 21.0 SUPPORTING STRUCTURE 21.1 The circuit breakers shall be supplied complete with necessary galvanized steel supporting structures, foundation and fixing bolts, etc., the galvanizing shall be as per IS. The mounting of the breaker shall be such as to ensure the safety of the operating staff and should conform to Indian Electricity Rules, 1956. Minimum ground clearance of live part from ground level shall be 4000 mm inclusive of foundation (300mm above GL). 21.2 The bidder shall submit detailed design calculations and detailed drawings in respect of supporting structures suitable for the equipment offered. The tenders shall specify the loads which shall be transmitted to the equipment foundation under most adverse operating conditions of the breaker. 21.3 Facility to earth the circuit breaker structure at two points shall be provided. 22.0 GALVANISING All ferrous parts including all sizes of nuts, bolts, plain and spring washers, support channels, structures, shall; be hot dip galvanized conforming to latest version of 18:2629 or any other equivalent authoritative standard. 23.0 CABLE TERMINATION Suitable cable glands for terminating the multi-core cable shall be provided wherever required. 24.0 TERMINAL CONNECTIONS AND EARTH TERMINALS 24.1 Each circuit breaker connected with incoming and outgoing feeders shall be provided with solder less clamp type bimetallic connectors suitable for ACSR/AAAC conductor mentioned in 'Technical Parameter' Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 49 Technical Specification 25.0 INTERTERLOCKS 25.1 Necessary interlocks to prevent closing or opening of the breaker under low pressure of the contact spring and devices for initiating alarm shall be provided. Provision shall also be made to enable electrical interlocking with the isolators associated with the breaker to prevent opening or closing of the isolators. 26.0 TYPE TESTS 26.1 Type test certificates for the following tests, as per IS:13118 or IEC 62271-100 with latest amendment thereof, from any of the NABL accredited Laboratory shall invariably be furnished a. Short circuit duties test b. Short time withstand current and peak withstand current tests c. Temperature rise test d. Mechanical endurance test e. Lightning impulse voltage withstand test f. Power Frequency withstand voltage test (dry & wet) g. Single Capacitor bank switching test h. Degree of protection IP-55 as per IS:13947:93(Part-I)/IEC 60529:89 26.2 26.3 26.4 27.0 Type test certificates must accompany drawing of type tested equipment, duly sealed & signed by type testing authority. Type tests conducted on the equipment should not be earlier than 3 years from the date of opening of bids. In case of any change in design/type of breaker already type tested and the one being offered against this specification, the Employer reserves the right to demand repetition of some or all tests without any extra-cost at NABL accredited lab. ACCEPTANCE AND ROUTINE TEST :27.1 Employer shall have access at all times to the works and all other places of manufacture where the Circuit Breakers are being manufactured and the Bidder shall provide all facilities for unrestricted inspection of the Bidder/manufacturer‘s works, raw materials, manufacture of all the accessories and for conducting necessary tests as detailed herein. The Employer reserves the right to insist for witnessing acceptance/routine testing of the bought out items. The Bidder/manufacturer shall submit the routine test certificates of bought out items and raw material also, at the time of routine testing of the fully assembled breaker 27.2 No material shall be dispatched from its point of manufacture unless the material has been satisfactorily inspected and tested. 27.3 Bidders shall indicate the inspections and checks carried out at various stages of manufacture of the circuit breakers. Complete record of stage inspection would be kept by the Bidder/manufacturer and this record should be made available for inspection by the representative of the Employer. Bidder/manufacturer should indicate the manufacturing programme and the The Employer will have a right to depute inspecting officers during the manufacture of the equipment. The Employer reserves the right to carry out stage inspections at all stages, for which advance intimation shall be given and all necessary cooperation shall be rendered by the manufacturer. 27.4 At the time of inspection, Bidder/manufacturer shall identify each and every item/accessories of the particular Circuit Breaker under testing. Unless all the items are identified, the manufacture will not be treated as complete. Various tests stipulated in IS/IEC shall be performed in the presence of the Employer‘s engineers or when the inspection waiver has been given, in such a case, testing shall be done at the manufacturer's works as per IS/IEC stipulations and same should be confirmed by documentary evidence by way of Test Certificate which shall be got approved by the Employer. 27.5 It is expected that before circuit breaker is finally offered for inspection, internal testing of the same for various important parameters are already done. Routine Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 50 Technical Specification 27.6 27.7 test report for such tests shall also accompany the letter of inspection call so that the Inspecting Officer at the time of inspection may verify the parameters brought out in the preliminary report. Details of all tests should be clearly brought out. In case for any reason, inspection is not completed or equipment is not found to be complete with all accessories as per confirmation given with the letter of inspection call, the Employer will reserve the right to recover complete cost of deputation of inspecting team to the works of the manufacturer. Acceptance of any quantity of circuit breaker & its accessories shall in no way relieve the successful bidder of his responsibility for meeting all the requirement of this specification and shall not prevent subsequent rejection if such equipments are later found to be defective. 28.0 RATING PLATES & SURFACE FINISH PAINTING & GALVANISING:28.1 Each circuit breaker shall be provided with a detailed rating plate. Details on the rating plate shall be as per ISS and shall also indicate manufacturer name, serial no., order no. and month & year of dispatch and Name of Project--RAPDRP. 28.2 All interiors and exteriors of tanks, mechanism, enclosures, cabinets and other metal parts shall be thoroughly cleaned to remove all rust, scales, corrosion, greases or other adhering foreign matter. All steel surfaces in contact with insulating oil, as far as accessible, shall be painted with not less than two coats of heat resistant, oil insoluble, insulating paint. 28.3 All metal surfaces exposed to atmosphere shall be given two primer coats of zinc chromate and two coats of epoxy paint with epoxy base thinner or hot dip galvanized or two packs of aliphatic polyurethane finished paint. All metal parts not accessible for painting shall be made of corrosion resistant material. All machine finished or bright surfaces shall be coated with a suitable preventive compound and suitably wrapped or otherwise protected. Paints shall be carefully selected to withstand tropical heat and extremes of weather within the limits specified. 28.4 Paint shall not scale off or wrinkle or be removed by abrasion due to normal handling. All external paintings shall be as per shade no. 697 or any other suitable shade of IS:5 or polyurethane paint 28.5 All ferrous parts & steel structure including all sizes of nuts, bolts, plain and spring washers, support channels, structures, etc. shall be hot dip galvanized or stainless steel or electro-galvanized. 29.0 DOCUMENTATION: 29.1 List of Drawings and Documents: Bidders shall furnish four sets of relevant descriptive and illustrative published literature, pamphlets and following drawings for preliminary study; (a) General outline drawings showing dimensions and shipping weights. (b) Sectional views showing the general constructional features of the circuit breaker including operating mechanism, arcing chambers, contacts with lifting dimensions formaintenance. (c) All drawings & data typical and recommended schematic diagram for control supervision & reclosing shall be annotated in English. . (d) Schematic diagrams of breaker offered for control supervision and reclosing. (e) Structural drawing, design calculations and loading data for support structures. (f) Short circuit oscillogram & certificates for similar type tested breakers. General arrangement of foundation and structure mounting plan including weights of varnish components and impact loading data for foundation design. (g) Type test reports. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 51 Technical Specification 29.2 29.3 29.4 29.5 30.0 Successful bidders shall, within two weeks of placement of order, submit four sets of final version of all the above drawings for the Employer's approval. The Employer shall communicate his comments/approval on the drawings to the Bidder/manufacturer within two weeks. Bidder/manufacturer shall, if necessary, modify the drawings and resubmit four copies of the modified drawings for the Employer's approval within two weeks from the date of comments. After receipt of the Employer's approval, the Bidder/manufacturer shall, within three weeks, submit 4 prints per breaker and two set of good qualities reproducible of the approved drawings for the Employer's use. Successful bidders shall also furnish two sets each of bound manuals covering erection, commissioning, operation and maintenance instructions and all relevant information and drawings pertaining to the main equipment as well as auxiliary devices along with each breaker. Marked erection drawings shall identify the component parts of the equipment as shipped to enable erection by the Employer‘s own personnel. Each manual shall also contain one set of all the approved drawings, type test reports as well as acceptance reports of the corresponding consignment dispatched. Manufacturing of equipments shall be strictly in accordance with the approved drawings and no deviation shall be permitted without the written approval of the Employer. Approval of drawings/work by the Employer shall not relieve the bidders of any of his responsibility and liability for ensuring correctness and correct interpretation of the drawings for meeting the requirements of the latest revision of the applicable standards rules and codes of practices. Equipment shall conform in all respects to high standards of engineering, design, workmanship and latest revisions of relevant standards at the time of supply and the Employer reserves the right to reject any equipment or material which, in his judgment, is not in full accordance therewith. PACKING AND FORWARDING: 30.1 Equipment shall be prepared for ocean shipment (foreign equipment) or rail road transport (local equipment). Equipment shall be packed in suitable crates in such a manner to protect it from damage and withstand handling during transit. Bidder/manufacturer shall be responsible for and make good at his own expense any or all damage to the equipment during transit, due to improper and inadequate packing and handling. Easily damageable materials shall be carefully packed and marked with the appropriate caution symbols. Wherever necessary, proper arrangement for lifting such as lifting hooks etc. shall be provided. Any material found short inside the packing cases shall be supplied by the Bidder/manufacturer without any extra cost. Each consignment shall be accompanied by a detailed packing list containing the following information: (a) Name of the consignee. (b) Details of consignment. (c) Destination. (d) Total weight of consignment. (e) Sign showing upper/lower side of the crate. (f) Handling and unpacking instructions. (g) Bill of material indicating contents of each package and spare material. 31.0 COMPLETENESS OF EQUIPMENT AND BOUGHT OUT ITEMS: 31.1 Bidders must furnish following information along with technical bid. A list of all the accessories which will be supplied with the breakers should be furnished. While furnishing the list of accessories, items which will be manufactured by the Bidders and balance items, which will be procured from subBidder/manufacturers should be clearly identified and stipulated in the bid. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 52 Technical Specification 32.0 SN 1. GUARANTEED TECHNICAL PARTICULARS: 32.1 It is obligatory on the part of bidders to furnish Guaranteed Technical Particulars enclosed with the bid document duly filled in complete in all respects. In case Guaranteed Technical Particulars duly filled in complete in all respects is not furnished, the bid may be treated as non-responsive. 32.2 The salient technical particulars of the VCB should be as follows: Type of Circuit Breaker Standards Applicable 2. Nominal System Voltage (KVrms) 3. Highest system voltage 4. Rated continuous current at design temperature of 50 deg.C (Amps) Rated Frequency (Hz) 5. Design ambient temperature 6. Maximum temperature rise for main contacts over desugn 7. ambient temperature of 50 deg.C Short time current rating (kA) 8. Rated Operating Duty 9. Operating Mechanism 10. a) Type of operating mechanism for i) Closing 11. ii) Opening Dielectric withstand voltage 12. i) One minute dry & wet power frequency withstand voltage a) Between live terminal and ground (kVrms) b) Between terminals with breaker contacts open (kVp) 13. ii) 1.2/50 micro second impulse withstand test voltage a) Between live terminal and ground (kVp) b) Between terminals with breaker contacts open (kVp) Vacuum ,Outdoor IEC 62271-100 & IS 13118 33 kV 36kV 1250A 50 50 deg 40 deg.C 25 kA for 3 sec 0-0.3 sec-CO-3 min-CO Spring Charging Spring Charging Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 70 70 170 170 53 Technical Specification TECHNICAL SPECIFICATION OF 33 KV & 11KV 2.13 1.0 TECHNICAL SPECIFICATION FOR 33 KV and 11 KV AUTO RECLOSER WITH COMMUNICATION MODEM SCOPE The specification covers the design, manufacturing, testing, supply, installation, testing and commissioning of 33/11kV Un-manned substation made with outdoor pole mounted auto-recloser that have programmable protection features and integrated remote operation capability and that are intended for distribution networks at nominal A.C. voltages of 36/12 kV. A primary objective of this specification is to foster modularity and a maximum level of interchangeability and integration to central SCADA system by supporting MODBUS/DNP3/IEC-103 and IEC60870-5-101/ IEC60870-5-104 communications protocols. 2.0 APPLICABLE STANDARDS The following standards contain provisions that, through reference in the text, constitute requirements of this specification at the time of publication the revisions indicated were valid. All standards are subject to review and parties to purchasing agreements based on this specification are encouraged to investigate the possibility of applying the most recent revisions of the standards listed below. ANSI/IEEE C37.60-1981: Requirements for overhead, pad mounted, dry vault, and submersible automatic circuit reclosers and fault interrupters for AC systems (RI993) IEC 60255, Electrical relays IEC 60056:1987, High-voltage alternating-current circuit breakers. Amendment No. 1:1 992. IEC 60529:1989, Degrees of protection provided by enclosures (IP Code). UNIPEDE NORM (SPEC) 13 (1995): Automation and Control Apparatus for Generating Stations and Substations: Electromagnetic Compatibility Immunity Requirements. 2.1 CLIMATIC CONDITIONS The Substation shall be suitable for satisfactorily working under the following climatic conditions: Max. Ambient Temperature Min. Ambient Temperature Max. Relative Humidity Min. Relative Humidity Altitude 550 C 20 C 100 % 56 % Below 1000 meters above mean sea level. The switch Switchgears and Auto-reclosers used shall be suitably designed and treated for normal life and satisfactory operation under the hot and hazardous tropical climate conditions and shall be dust and vermin proof. All interior and exterior ferrous surfaces of auto-reclosers and control cabinets shall be manufactured from marine grade stainless steel. All support structures and associated bolts and nuts with these parts, shall be hot-dip galvanized. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 54 Technical Specification 3.0 TECHNICAL DATA SHEET FOR AUTO RECLOSER Sl. No. 1 Particulars 2 No of poles 3 4 5 6 Service Rated System Voltage Highest System Voltage System earthing 7 8 12 13 Rated Voltage of AR kV Rated Continuous Current Amps a) For lines b) For Transformers Rated Frequency Hz Rated Short Circuit breaking kA RMS current ( I ) - 3secs – symmetrical Rated Short Circuit making current kA PEAK Interrupting medium Insulation medium 14 15 16 17 Closing mechanism Opening mechanism Mounting type Enclosure 18 19 Duty cycle 20 Insulation level 21 i) Power Frequency with Stand kV RMS Voltage ii) Impulse withstand Voltage kV Peak Minimum clearance between mm phases Minimum clearance between phase to earth 9 10 11 22 23 Unit Type Minimum Creepage Distance (Total) Operating mechanism: kV kV Data for 33kV AR SF6 Data for 11kV AR Solid 3 (3 Phase Ganged Unit) 3 (3 Phase Ganged Unit) Outdoor 33 38 Solidly earthed system 36 Outdoor 11 15.5 Solidly earthed system 12 800 400 50 16 630 630 50 12.5 2.5*I 2.5*I Vacuum SF6 /Solid Dielectric LV Solenoid Springs Single pole 316 grade stainless steel Vacuum Solid dielectric LV Solenoid Springs Single pole 316 grade stainless steel O-1strt-CO-2ndrt-CO-O-1strt-CO-2ndrt-CO3rd 3rd rt-CO rt-CO CO CO mm 70 60 170 400 110 375 400 295 1100 780 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 55 Technical Specification Sl. Particulars No. a) Type Unit Data for Data for 33kV AR 11kV AR Solenoid-Spring Solenoid-Spring .c) Rated voltage of Shunt trip coil & operating range V. DC 110[50% - 110%] d) Rated voltage of Closing coil & operating range e) No. of trip coils f) No. of closing coils g) Nos of expandable auxiliary I/O contacts & contact rating (Required for transformer & Incomer AR) V. DC 110 [80% - 110%] 110 [50% 110%] 110 [80% 110%] No 2 per AR 2 per AR No 1 per AR 1 per AR Nos 12 I/P+8 O/P 12 I/P+8 I/P (per AMPS (per AR) CB) 10 A at 240V AC 10 A at 240V AC & 10A at 110V DC & 10A at 110V DC h) Minimum thickness of sheet steel mm 3 3 for control cabinet i) Enclosure Protection IP55 IP55 24 Reclosing Three Phase Three Phase auto reclosing auto reclosing 25 Support structure Galvanised Galvanised (Painted / Galvanised) 26 All other parts (Painted / Synthetic enamel Synthetic Galvanised) shade enamel shade 631 of IS5 631 of IS5 (125 microns) (125 microns) 27 28 29 Minimum size of control wiring (Copper) Protection a) For transformer b) For line 30 Measurement 31 Communication Protocol 32 Communication Port 33 Supervisory Sq. mm 2.5 Numeric O/C, E/F, SEF, relay Differential, OTI, WTI, PRV, Buchholz, OSR with Backup -doScheme O/C, E/F, SEF 2.5 O/C, E/F, SEF Differential, REF, with Backup Scheme O/C, E/F, SEF Digital Real time current, Real time voltage, PF current, voltage, PF IEC60870-5-101/ IEC60870-5-101/ IEC60870-5-104 IEC60870-5-104 and IEC and IEC 103/DNP 103/DNP 3/MODBUS for 3/MODBUS for meters & Relays meters & Relays RS 232, RS 485 RS 232, RS 485 & Ethernet & Ethernet RTU RTU Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 56 Technical Specification 4.0 DEFINITIONS AND ABBREVIATIONS 4.1 Auto-recloser (AR): A mechanical switching device that, after opening, closes automatically after a predetermined time. Several reclosures could occur before lockout. 4.2 Cold load pick-up (CLP) feature: A feature that allows modification of the overcurrent protection characteristics in order to prevent relay maloperation under conditions of system energisation. Dead time: The time between the instant that the current is interrupted by the AR and the instant the contact of the AR closes as a result of an automatic reclose operation. [IEC 50-448-04-09] Definite time lag (DTL) protection element: A protection element with a settable time delay that is constant above the pick-up current setting. Delayed protection operation: The protection functionality enabling delayed circuit-breaker operation, whether this is due to an IDMTL or DTL protection element. Disc reset time: The time required for the disc of an electromechanical IDMTL protection relay to turn back to its original position after it has turned to the position where a protection operation was initiated. Effectively earthed system: An earthed system in which the healthy phase power frequency phase-to-earth over voltages associated with earth faults are limited to 80% of the highest phase-to-phase voltage of the system. Fast curve protection element: A family of curves with operating times approximately constant (slightly inverse) relative to the multiple of pick-up setting. Instantaneous protection element: An element with no intentional time delay active above a pre-determined pick-up current setting. Inverse definite minimum time (IDMT) protection element: A protection element the minimum operating time of which is adjustable and is inversely proportional to the fault current. Pole-mounted remote terminal unit (PMRTU): A remote terminal unit that is designed for pole mounting and that operates specific pole-mounted equipment remotely. Rapid protection operation: The protection functionality enabling rapid circuitbreaker operation, whether this is due to an instantaneous, fast curve, or a definite time delay protection element with relatively short definite time delay. Reset time: The time duration after a circuit-breaker close operation for which the measured currents are below a fault detecting level. On the expiry of this time the protection sequence resets. Secure control: A single mechanically non-latching switch that effects one state of a control function only. An example of which is either a non-latching switch or two separate push buttons that effect one state of a control function only in each position. If a control is activated repeatedly it only effects that state and does not change the state of the control. Sensitive earth fault (SEF) relay: A relay that is sensitive to very low earth fault currents and in which the operating settings are for current magnitude and definite time delay. Supervisory: Remote control and indications of an AR or a PMRTU by means of a telecommunications link. Toggled control: A single mechanically non-latching switch/push-button that enables a single control function on the first operation of the switch/push-button and disables the function on the second operation of the same switch/push button. 4.3 4.4 4.5 4.6 4.7 4.8 4.9 4.10 4.11 4.12 4.13 4.14 4.15 4.16 4.17 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 57 Technical Specification 4.18 Zone sequence co-ordination (ZSC): The feature that allows protection devices to maintain sequence co-ordination for combinations of rapid and delayed protection operations. 5.0 Mounting 5.1 The AR shall be suitable for single pole mounting. 5.2 Adequately rated lifting eyes shall be provided and they shall be designed to allow the completely assembled AR (surge arresters fitted) to be lifted without recourse to a sling spreader. The diameter of the eyes shall be a minimum of 30mm. Suitable mounting brackets for surge arresters shall be provided on the line side and on the load side of the AR, adjacent to the bushings. The AR shall be fitted with an external M12 earthing stud, complete with a nut, lock nut and spring washer. The AR shall have laser cut markings on each bushings marked U1 V1 W1 for the normal line side and U2 V2 W2 for normal load side. A detailed drawing of the single pole AR mounting arrangement with surge arresters fitted shall be provided. The minimum phase-to-earth clearances shall be as per relevant IS and is to be indicated on the drawing. The mass of the mounting hardware, the AR and the control cabinet and cable shall be stated in the tender documentation. Bushings 5.3 5.4 5.5 5.6 5.7 6.0 6.1 Terminals a) For 33KV AR, the preferred arrangement for bushing is a fully insulated bushing arrangement achieved by using cyclo aliphatic epoxy resign bushings and silicone rubber bushing boots together with 3 meters 185 mm2, single core, XLPE insulated aluminum water blocked cable tails to provide a fully insulated bushing arrangement. b) For 11 KV AR, the preferred arrangement for connection to overhead conductor is using crimp lugs with holes. 6.2 Material The following bushing materials are acceptable: a) Outdoor Cyclo aliphatic epoxy resin and/or Silicone rubber b) Porcelain bushings and EPDM rubber are not acceptable. c) Minimum acceptable creepage is 1100 mm for 33 KV AR and 780 mm for 11KV AR.. 7.0 Finish a) All interior and exterior ferrous surfaces of auto-reclosers and control cabinets shall be manufactured from 316 marine grade stainless steel. All support structures and associated bolts and nuts with these parts, shall be hot-dip galvanized. b) Suitable precautions shall be implemented to prevent corrosion due to the use of dissimilar materials. 8.0 Control equipment 8.1 Control cabinet a) b) c) Cabinets that house equipment for protection and control shall be mounted independently of the AR. Suitable ultraviolet-resistant cable, shall be provided to connect the AR to the control cabinet. It shall be possible to disconnect the cable at the AR while the AR is connected to the power system, without causing damage or mal-operation: care shall be taken that CTs are not open circuited. A robust, multi-pin weatherproof connector shall be supplied. The female part of the connector shall be mounted on the AR and the male part shall be mounted Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 58 Technical Specification on the cable. Preference will be given to products supplying connectors at both the AR and the control cabinet. d) Cabinets shall be adequately sealed and dust protected and shall be internally treated to prevent moisture condensation. The degree of protection shall be IP 55. e) The supplier shall ensure that the equipment housed in the control cabinet can withstand the heating effect of direct solar radiation without causing failure and/or mal-operation. Details shall be provided in the tender documentation. f) The cabinet shall make provision for bottom entry of three cables. This shall be done with a pre-punched suitable sized diameter holes. The holes shall be suitably blanked off. g) The cabinet shall be fitted with an external M12 earthing stud with a nut, lock nut and a serrated washer. h) The door of the cabinet shall be fitted with a robust fastening arrangement that is capable of being secured by a padlock that has a shackle of 8 mm diameter. i) The cabinet shall be easily removable for workshop repair purposes. 8.2 Electronic control equipment 8.3 The controls shall not suffer any damage if one or more poles of the circuit breaker fail to respond to either a trip or a close command. 8.4 Electronic modules shall perform continuous diagnostic monitoring and shall contain hardware and software watchdog checking. 9.0 Protection characteristics 9.1 General 9.2 The ratio of drop-off current to pick-up current shall be at least 95 % for all protection functions. The E/F and SEF functions shall be equipped with harmonic filtering to prevent operation when harmonics are present in the primary residual earth currents. A low pass filter with: a) 2nd harmonic rejection > 6 1; and b) 3rd harmonic rejection > 50 1 shall be supplied. Both the SEF function and its filter shall be described in the tender documentation All protection functions, i.e. over-current (O/C), earth fault (E/F) and sensitive earth fault (SEF) shall have elements with characteristics that comply with IEC 255. The sequence of trip and auto-reclose characteristics for O/C, E/F and SEF shall be programmable to enable: a) the selection of any combination of the available elements for each trip in the trip-and-reclose sequence; and b) separate trip-and-reclose sequences for O/C, E/F and SEF. In case of IDMTL protection elements the AR shall preferably be provided with a disc reset timer that simulates the resetting functionality of an upstream electromechanical induction disc relay by implementing a disc reset timer. The length of the time delay shall preferably be settable to be able to simulate the upstream device (settable between 5s and 20 s), however, if a fixed time delay is provided it should be between 4s and 5s. A zone sequence co-ordination (ZSC) feature shall be provided to ensure tripclose sequence co-ordination for combinations of rapid and delayed protection operations applied to series ars. ZSC functionality shall be such that: 9.3 9.4 9.5 9.6 9.7 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 59 Technical Specification a) an AR senses the presence of an over-current or earth fault, as well as the clearance of that fault by another device and proceeds to the next protection operation in its own sequence; and b) it proceeds in its sequence of rapid protection operations only, allowing the full number of delayed operations to be executed for in-zone conditions. 9.8 Loss of Phase (LOP) protection shall be provided to ensure the protection functionality of AR as below: a) AR should trip with no auto-reclose in case if there is a loss of voltage on one or two phases on the upstream part of the line. Loss of supply on all three phases shall not generate the protection trip. b) Facility to turn LOP ON or OFF without affecting other protection functions of the device. Pass-word or other form of access control shall be provided c) The parameters of configuration of LOP shall include the voltage level (phase to ground) and time of loss of supply on one or two phases. The voltage level shall be configurable from 5000 to 19000 Volts (for 33KV) and 5000 to 9000 (for 11KV) with steps not greater then 250 V. Time range shall be configurable from 1 to 60 sec with steps not greater then 1 sec. 9.9 The information about LOP operation in case of the protection trip shall be recorded accordingly with indication of the phase(s) causing the trip of AR. The information about LOP operation shall be easily assessable. d) Rapid protection operation shall be possible by selecting a fast curve or instantaneous protection element. Co-ordination of the fast curves or instantaneous protection elements between two devices in series shall be possible either by selecting suitable curves from a family or by addition of a selectable time increment, typically 0,05s to 3s, in 0,05s steps, or any other acceptable solution. 9.10 Long protection operating times associated with fault levels marginally above the pick-up setting of the IDMTL protection element shall be avoided by the provision of a Low Set Definite Time element with the following features: a) it shall be possible to enable or disable the element. When enabled it shall be active simultaneously as an overlay with all selected elements; b) the element shall have the same pick-up current setting as the IDMTL element; and c) the time delay shall be selectable from 2s to 10s, in 1s steps. The time delay shall be independent of any curve manipulation. 9.11 A High Set Instantaneous element with a selectable time delay shall be provided, with the following features: a) it shall be possible to enable or disable the element. When enabled it shall be active simultaneously as an overlay with all selected elements; b) circuit-breaker lock-out as a result of an operation due to the High Set Instantaneous element shall be selectable; c) the pick-up setting range of this element shall be at least 100 % to 1500 % of the over-current setting and shall be independent of any curve manipulation; and d) the time delay shall be selectable from instantaneous to 1s, in 0,05 s steps. The time delay shall be independent of any curve manipulation. 9.12 A cold load pick-up (CLP) feature shall be provided that allows user selectable modification of protection element characteristics under conditions of system energization. The CLP function may be provided in one of the following two ways: a) The instantaneous O/C element and the Low Set Definite Time O/C element could be blocked for the CLP time duration; and b) The pick-up current setting of the IDMTL O/C element and the Low Set Definite Time O/C element may be modified with a settable factor to Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 60 Technical Specification increase the pick-up current of these elements for the CLP duration. The instantaneous O/C element should be blocked for this time. This is the preferred method. The CLP function shall have the following characteristics: i. the CLP function shall not in any way interfere with any of the other functions'/elements' pick-up current settings except as mentioned above; ii. the CLP functionality shall be such that the active duration of the CLP is selectable from 0 min to 20 min in 1 min steps; and iii. the modification factor should be settable from 1 to 2 in steps of 0,1. 9.13 Earth fault function 9.14 The earth fault setting range shall detect primary earth fault currents down to 20 A. 9.15 Delayed protection operation shall be possible by selecting an IDMTL element with NI, VI or El curve, or a definite time protection element with time delay from 0.05s to 10s, in 0,05s steps. 9.16 Rapid protection operation shall be possible by selecting a fast curve or instantaneous protection element. Co-ordination of the fast curves or instantaneous protection elements between two devices in series shall be possible either by selecting suitable curves from a family or by addition of a selectable time increment, typically 0.05s to 3s, in 0.05s steps, or any other acceptable solution. 9.17 A High Set Instantaneous element with a selectable time delay shall be provided with the following features: a) it shall be possible to enable or disable the element. When enabled it shall be active simultaneously as an overlay with all selected elements; b) circuit-breaker lockout as a result of an operation due to the High Set Instantaneous element shall be selectable; c) he pick-up setting range of this element shall be at least 100 % to 1500 % of the earth fault setting and shall be independent of any curve manipulation; and d) he time delay shall be selectable from 0,05s to 1s, in 05s steps. The time delay shall be independent of any curve manipulation. 9.18 Sensitive earth fault (SEF) function 9.19 A primary earth fault current of 4A to 20A in steps not exceeding 1A shall be detectable. 9.20 Delayed protection operation shall be possible by selecting a definite time protection element with time delay from 3s to 25s, in 1s steps. 10.0 Auto-reclose operation parameters 10.1 The number of sequential trips to reach lockout shall be selectable to be either 1,2,3 or 4. 10.2 Reset times shall ideally be separately selectable for SEF and the combination of over-current and earth fault functions. The reset time shall be selectable from 5s to 120s in 1s steps. 10.3 Dead times shall ideally be separately selectable for SEF and the combination of over-current and earth fault functions. The dead time between each successive reclosure shall be independently selectable from instantaneous to 5s for the first reclosure and from a minimum of 2s up to a maximum of 120s for subsequent reclosures. 10.4 A close instruction initiated locally or remotely during a dead time shall result in lockout if the fault is still present upon closure. 11.0 Statistical measurement functions 11.1 The characteristics of the statistical measurement functions shall be as follows 11.2 Measurement shall be done with three-phase-4-wire method. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 61 Technical Specification 11.3 Quantities to be measured / calculated with class 0.5 accuracy are: a) r.m.s. phase-to-phase and phase-to-neutral voltage of all three phases: b) r.m.s current per phase c) three phase active power in kW d) three phase reactive power in kvars e) total three-phase active energy in kWh f) Power factor g) Maximum demand h) Harmonic analysis i) Wave form capture j) Fault stimulator 11.4 The real power energy, reactive energy and apparent energy measurement should be cumulative. While maximum demand measurement shall be integrated with respect to time. With selectable time integration periods of 5 min, 15 min, 30 min or 60 min. The data buffer shall work on the FIFO principle and a minimum size for the data buffer shall store values for 4 months. 11.5 The voltage factor of the voltage transformers shall be a minimum of 1.9 for 8 hours. 11.6 CB and Control element shall have the facilities to record the number and duration of outages. The information shall be assessable locally or remotely using SCADA system. The following parameters shall be recorded: a) Cumulative total number of outages b) Cumulative total outage duration c) Time and duration of each outage 12.0 Local control and indication: 12.1 The local control and indication shall be as given in Table-1: Table-1- Minimum specification of local controls ad indications: Item Features Remarks Local control Local/Remote 2 position key switchable (See note 1) Circuit-breaker open (see note 3) Circuit-breaker close Secure control ARC ON/OFF Secure control SEF ON/OFF Secure or toggled control Secure or toggled control Local indication Local/Remote (see note 3) (See note 1) Circuit-breaker open Circuit-breaker close Circuit-breaker lock-out ARC ON/OFF SEF ON/OFF Protection operation See 12.7 Controller not healthy (see note 2) SF , Alarm See 12.9 AC fail DC abnormal See 17.7 DC fail Charger fail Local Analog indication (See note 1) r.m.s phase-to-phase to neutral voltage of all three phases r.m.s current per Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 62 Technical Specification phase three phase active power in KW three phase reactive power in kvars total three-phase active energy in kWh Power factor Maximum demand NOTES: Note 1: The local control and the local indication features on the control panel shall be labeled as presented in column 2, where applicable. The type of switch used for local control shall not allow for a conflict to exist between the switch position and the function status. Note 2: The Controller not healthy indication shall indicate the control equipment not healthy (watchdog) function operated. It shall not operate during the normal pole mounted switch operating cycle. This indication should remain active until the unhealthy state that initiated it returns to normal. Note 3: The three-position switch (labeled as below) shall allow the AR controller to be set in the following modes: Remote: In this mode a local operator can trip the AR and change the mode. A remote operator can trip or close the AR and change configuration parameters. All reporting functions are active. Local: In this mode a local operator can trip and close the AR and change configuration parameters. All reporting functions are active. 12.2 All local controls and indications shall be accessible in adverse weather condition. 12.3 The AR shall be provided with external levers to permit manual operation, using an insulated operating stick, to open, close, lock-out and reset the AR from ground level . Where these operations can be performed at the control cabinet, it shall only be necessary to provide a mechanical means to open and lockout the circuit breaker using an insulated operating stick. 12.4 The AR status shall be clearly visible from ground level. ―Opened‖ shall be indicated with a green ―O‖. ―Closed‖ shall be indicated by a red ―I‖. Alternative indications shall be subject to approval by the purchaser. 12.5 Pressure relief facilities shall be provided to enable the AR to withstand safely the effects of excessive pressure rise due to an internal fault. 12.6 Malfunction of the AR shall not pose a safety hazard to the operator due to the recoil or backlash of items such as external operating rods, ranks and levers. 12.7 Easily available (i.e maximum of one keystroke) local indication of protection operation shall be provided for at least the last operation of the AR. The function, phase involved and the current magnitude shall be indicated. 12.8 Switches used for local control shall offer the type of control described in table 1 i.e. secure or toggled control. Electronic keypad controls shall offer ‗quick key‘ (maximum of one keystroke) access to the controls in table1 if not implemented with switches 12.9 ARs using SF, as an arc extinguishing/Insulating medium shall: a) Provide a low gas pressure indication at a gas pressure that enables safe operation of the AR b) Prevent closing of the AR after it has opened under the abovedescribed condition Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 63 Technical Specification c) Be provided with a method of inhibiting any operation of the AR in the event of the gas pressure dropping below a safe pressure. 13.0 Remote control and indication 13.1 The remote controls and indication shall be as given in table 2 Table 2- Minimum specification of remote controls and indications 1 2 3 Item Features Remarks Remote control Circuit-breaker open Secure control Circuit-breaker close Secure control ARC On Secure control ARC OFF Secure control SEF ON Secure control SEF OFF Secure control Remote indication Local/Remote (See note 2) (See note 3) Circuit-breaker open Circuit-breaker close ARC On ARC OFF SEF ON SEF OFF IDMTL O/C Trip Low Set DTL O/C Trip Rapid E/F Trip High Set E/F Trip SEF Trip ARC (see note 4) Controller not healthy (see note 1) SF, Alarm See 8.9 AC fail DC abnormal DC fail See 17.7 Charger fail Analog indication r.m.s phase-to-phase and phase to (See note 3) neutral voltage of all three phases r.m.s current per phase three phase active power in KW three phase reactive power in kvars total three-phase active energy in kWh Power factor Maximum demand Note 1: The Controller not healthy indication shall indicate the control equipment not healthy (watchdog) function operated. It shall not operate during the normal pole mounted switch operating cycle. This indication should remain active until the unhealthy state that initiated it returns to normal. Note 2: The two-position switch (labeled as below) shall allow the AR controller to be set in the following modes: Remote: In this mode a local operator can trip the AR and change the mode. A remote operator can trip or close the AR and change configuration parameters. All reporting functions are active. Local: In this mode a local operator can trip and close the AR and change configuration parameters. Only monitoring functions are available to remote operators. The local and remote positions shall be indicated separately. Note 3: The ARC indication shall give alarm with any ARC attempt. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 64 Technical Specification 14.0 Local Engineering 14.1 The AR controller shall contain a real time clock (with leap year support) that can be set both locally and remotely. It shall be possible to synchronise the clock with the control center SCADA using ant of the time synchronising standards (IEC-101/IEC-104 or SNMP protocol. 14.2 A facility for selecting all the protection, operating and communications characteristics shall be locally available in the control cabinet. Optional password protection against unauthorized changes shall be available. 14.3 Non-Volatile memory storage shall be sized to store the following minimum data: All operating , protection and communications parameters. a) An event record containing at least 3000 events (a protection event is defined as all operations in a sequence until successful sequence reset or lockout). The actual number available shall be stated in the tender documentation. 14.4 Refer to clause 11.4 Maximum demand information Maximum demand shall have the facilities to be configured for weekly or monthly demand. 14.5 A pointer shall be provided to indicate up to where the data was last read. This will enable regular uploading of the data without re-loading of previously read data. 14.6 All events shall be time and date stamped with a resolution of at least loms relative to the onboard real time clock. 15.0 Tele-control requirements 15.1 The AR controller shall detect and report disconnection of the control cable between the controller and AR. 15.2 It shall be possible to operate AR, change the active protection group, turn AutoRecloser capabilities ON/OFF and turn E/F and SEF ON/OFF remotely using the protocol specified in 16.6 This functionality shall be subject to the limitations of the selected protocol. Details shall be provided in the tender documentation. Communications 16.0 16.1 Communication Overview 16.1.1 Technical Requirement for Unmanned Substation Communication. 16.1.2 A local control room in the substation shall have all the controls from local PC connected to a) All VCB Control Cubicles having RTUs, Datalogger and Numerical relays over IEC 104 Protocol b) All meters (TVMs) should be with DLMS protocolover IEC 104 through suitable Data Concentrator to conver Modbus port on meters to IEC 104. c) RTCC panel with modbus port through suitable Data Concentrator to convert Modbus to IEC 104. (Note : As per the norms of PFC for R APDRP, all the base line information of the substation shall be available to the divisional staff on a Web based tool through internet including Meter Data, Feeder state and Tap position etc. This will be independent of the Local or Remote PC. The communication media Modems/routers etc. shall be made available by the employer when the remote access function will be utilized. Until then web access on the local PC shall be demonstrated and commissioned.) 16.1.3 The proposed substation will be connected in future to the remote control station with SCADA/DMS and all other software tools for the relay configuration, meter data reading etc . The hardware & software supplied should be complete in all respects regardless of the location of the PC. When employer Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 65 Technical Specification decides to implement remote control, this PC shall be shifted to the remote control center. In such situation, employer will provide only the Modems/other Communication media with Ethernet port only at each end. 16.1.4 The bidder is responsible for the compatibility of the equipment installed for future communication with SCADA For any communication problem that may arise in future connectivity with SCADA, the bidder is fully responsible to make SCADA communication operative at free of cost. 16.1.5 The bidder is to supply, install, testing & commissioning including training, of Base computer system along with software for remote control & data collection from 33/11 KV s/s and its analysis and Possibility to Integrate the same with a State-Of-The-Art latest SCADA for substations in future. 16.1.6 The entire sub station shall be linked to the remote control & Monitoring station through a single communication tunnel using GPRS Routers/any other TCP/IP based network communication media. The s/s will be ready to be hooked to the SCADA / EMS / DMS Software in future 16.1.7 For the Local & Remote control, monitoring and adjustments software solutions shall be provided to carryout following tasks as minimum o ON/OFF Operations o Change the protection and control settings o Up-Load the Event / Data and Demand Log o Monitor Contact wear and Breaker health o Monitor VCB Battery and Battery Charger o Communications settings o Apply Work-Tags for maintenance o Call-out configuration (In the event of pre-programmed alarm for call-out, the device calls back the remote station to log the alarm) o Send messages to the concerned field staff, in case of a call-out, by means of SMS, Voice Call, E-Mail etc. (Depending on the local resources available, GSM Service, LAN Administrator etc.) 16.1.8 Event Logging, configured History & Demand Reports The system is capable of logging very comprehensive data in three different categories a) Event Logging This log should have all the events observed by the device including ON/OFF operation, Local commands, protection element pick-up and trip, change of settings, Aux supply, fault level (Interrupted current valus) Battery low etc. b) Demand Logging Should upload from the devices all records of weekly and monthly demand, which can be uploaded by the software from any remote location and used for analysis of load behavior on each feeder including the total no of outages and duration of outages c) Configured History Should be able to up-load recorded user defined parameters periodically at user defined frequency ie. 15/30/60 min. This data can be up-loaded from local or remote software d) Alarms / Call-outs There are several type of alarms, that can be configured to initiate an emergency call-out. If any of the user defined alarm occurs in any of the substation feeders, the device immediately calls up the Remote Control Center which in turn initiates a alert system by sending SMS messages, Pre-recorded Voice Messages and E-Mails etc. to user configured locations Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 66 Technical Specification e) Provision for GPRS Routers with built-in Modbus/IEC Gateways for data transmission, connecting cords/cables, antenna etc. shall be kept. The utility in its discretion may also ask for commissioning and training/handholding, troubleshooting from the supplier f) Computer System The firm will also offer a Xeon Server and a node of the good quality suitable computer system (IBM, HP or Dell make) with latest configurations g) Specification of Server a. Intel Xeon processor (Dual CPU) Upgradeable b. 3.2 GHz or higher speed c. 2 MB or higher L2 ECC Cache d. Ultra fast Throughput with 800 MHz FSB e. 2 GB of DDR2 RAM operating at 400 MHz or higher expendable up to 16GB f. Server works/Intel server class chipset g. 3x73 GB Ultra Wide SCSI-III Disk(15000rpm) Hot Swap h. Dual Channel Ultra-III SCSI Controller (320MBPS) with RAID(0,1,5) having 128MB RAM i. Minimum 5 PCI/PCI-X Slot j. Auto-sensing full duplex 10/100/1000 MBPS Ethernet Card k. Minimum 6 Hot Swap 1.0‖ drive bays & two 5.25‖ bays free l. DVD Writer m. 17‖ LCD Color Monitor n. 1.44MB FDD o. PS/2 104Keys Keyboard p. Server Management features q. Server Configuration and Software Loading Facility r. Windows 2000/2003 Server s. UPS 1 KVA battery with 1 hrs backup t. GSM Modem for SMS u. Multimedia Speakers for alarm annunciation h) Specification of Laptop a) HP/Compac/Acer b) Windows XP c) Intel Core 2 Duo, 60 GB HDD, 1 GB RAM, DVD R/W d) Internal Modem The firm shall also offer Computer room furniture (two computer desks & Six chairs) of reputed make and ACs of standard make to be installed, at Central Stations. 16.2 As a minimum, following independent communication ports will be provided, that allow for simultaneous operation 1. RS 232 (Configurable for Modbus, DNP3, IEC 101 2. RS 485 (Configurable for Modbus, DNP3, IEC 101 3. Ethernet.(Configurable for IEC 104) 4. USB Port for Local connection of Laptop PC 16.3 To upload the non-volatile data to and from a personal computer. The requirements of the personal computer shall be stated in the tender documentation. 16.4 To interface to remote communications equipment (e.g. GSM / CDMA / GPRS / PSTN modems, radio-modems and Fiber Optic Modems). 16.5 One of the RS-232 port shall support full asynchronous V.24 functionality. 16.6 The protocol to be supported by the AR controller for remote communications shall be as follows: Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 67 Technical Specification a) Support of IEC 870-5-101 & IEC 870-5-104 protocol for Remote SCADA b) MODBUS protocol over RS 485 to communicate with the External Numerical Relays/Energy meters/RTCC Panels The communication interface should be designed in such a way that the RTU can communicate both local remote station as well as SCADA. The controller should include on board RTU and a radio power supply user programmable between 5-15 V dc and rated for 3 A continuous, or 5 A for 30 seconds with a 20 % duty cycle. 17.0 Power supplies 17.1 The AR system shall provide power for the electronics, operation of the AR and operation of the communications equipment (e.g. radio or GSM-modem). 17.2 Primary supply: Preference will be given to the ability to obtain primary power directly from the HV power system requiring no additional primary supply connection. Test supply: The AR shall accept an external AC 230 V 50 Hz supply. Auxiliary supply: An auxiliary supply with the following minimum characteristics shall be provided 17.3 17.4 17.5 17.6 17.7 17.8 18.0 18.1 One battery and constant voltage charger with current limiting shall be part of the AR. Battery standby time shall not be less than 24 h, allowing for ten AR operations and a Transmit: Receive: Standby duty cycle of 5:5:90 from a 5 W output ratio. The battery shall recharge to 80 % of its capacity in a maximum of 15 h. The total number of circuit-breaker operations under the above communications scenario shall be at least 10 AR operations preventing closing if the battery will not have enough stored energy to open the circuit- breaker for a protection trip condition. Details will be stated in the tender documentation. Batteries shall be disconnected at the manufacturer's specified minimum voltage. Battery Low' indication shall be available locally and remotely and shall include a battery test. The indication of "Battery Low" status shall allow for a further ten AR operations. The minimum battery life expectancy shall be 5 years. Details of the guaranteed life expectancy of the battery shall be stated in the tender documentation. Maintenance and commissioning All the communications equipment shall be easily accessible in the control cabinet. Wiring of "communications links in the control cabinet shall permit the connection of a temporary protocol-Monitor. It shall be possible to perform secondary injection testing while the AR is communicating with the center. It shall be Possible to disconnect the AR circuit breaker and connect a simulated breaker to the control cabinet for testing purposes. 18.2 The AR shall not malfunction while the radio is transmitting via an antenna in close proximity and the control cabinet door is open. 18.3 Provision shall be made in the control cabinet for individually isolating the power supply to/from the following: a) battery; b) battery charger; c) radio; and d) primary supply to the control cabinet electronics. 19.0 Rating plate Each AR shall bear a rating plate of an intrinsically corrosion-resistant material, indelibly marked with the sea-level rating for which the equipment has been type tested. The rating plate shall be indelibly marked with: a. the manufacturer's name; b. the equipment type designation and serial number of the ar; c. the mass, in kilograms; Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 68 Technical Specification d. the date of manufacture; e. the voltage transformer ratio, class and burden. auxiliary supply voltage (if applicable); and 20.0 Additional information The following shall be submitted with the tender. 20.1 Circuit breaker details 20.2 20.3 20.4 20.5 20.6 20.7 20.8 20.9 20.10 20.11 20.12 20.13 20.14 20.15 20.16 20.17 21.0 a) manufacturer; b) type designation; c) place of manufacture; d) short circuit breaking capacity; 3s 1s e) asymmetrical breaking current; f) peak making current; and g) critical current (maximum instantaneous peak). A schematic-wiring diagram of the AR offered. A general-arrangement drawing of the AR offered. Details of the maintenance and operating equipment and procedures needed and a detailed parts list of the various components. A description of the AR operation, with instruction and maintenance manuals, including maintenance schedules, protection characteristics, communications facilities, the method of applying settings to relays and controls, together with any software required and the cost thereof. The software requirements shall be stated in the tender documentation. Details and the cost of any available portable calibration and diagnostic test set that may be used to perform the functionality described in clause 18.1, 18.2 and 18.3. Details of the test set shall be given in the tender document. A list of recommended spares and tools, quoting the prices of each item and its availability. If protection setting changes are accomplished by resistors, electronic cards or modules or computer programs, the price and range of such items. The method of changing protection settings shall be stated in the tender documentation. Details of technical back-up facilities available. These details shall be stated in the tender documentation. Details of the class, ratio(s) and burden of the protection current transformer and voltage transformer, if supplied, shall be stated in the tender documentation. The supplier shall include the following details of measurement current transformers (not internal to the AR) that can be supplied with the AR. The following details shall be provided: a) available ratio(s) and accuracy class; b) method of fitting; and c) effect on creepage distance and BIL Where applicable details of the low gas pressure alarm/lock-out philosophy; Details of AR service history: a) how many in service, where and for what period; and b) contact names and numbers. Details of LV trip/close coil if available as an option Power requirements for a close operation The maximum achievable separation between the control unit and the circuit breaker. Full details of the protocol implementation and the complete point database. TESTS 21.1 Type tests a) The AR shall have been type tested in accordance with, and found to comply with, the requirements of either IEC 60056 or ANSI/IEEE C37.60-1981 for the Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 69 Technical Specification following, and the appropriate values shall be stated in the tender documentation: b) Interrupting performance (automatic operation). c) Interrupting performance (manual operation). d) Operating duty. e) Making current. f) Minimum tripping current. g) Insulation (dielectric tests). h) Radio interference voltage. i) Temperature rise. j) Mechanical operations. k) Control equipment surge withstand capability. 21.2 The control cabinet and associated electronics shall have been type tested in accordance with UNIPEDE NORM (SPEC) 13 (1995): Automation and Control Apparatus for Generating Stations and Substations: Electromagnetic Compatibility Immunity Requirements. The environment shall be considered as failing in the HV substation category, according to NORM (SPEC)13. 21.3 Test records (on identical equipment) in the form of validated copies of test certificates issued by a recognized testing authority shall be submitted with the tender documentation. 21.4 Routine tests Routine tests, as required in the relevant standards, shall be carried out as a normal requirement of the contract and, unless otherwise agreed upon, shall be witnessed by the purchaser or by his appointed representative. No additional charge shall be levied for such tests or for the production or presentation of documentation related to routine tests. Duplicate copies of routine test certificates shall be supplied together with the equipment when the latter is delivered to the final destination stated in the order. 22.0 PACKING/DOCUMENTATION 22.1 Packing All equipment shall be carefully packed to prevent damage or deterioration during normal transportation, handling and storage. Each container shall bear the following information on the outside of the container: a) The address of the destination b) The gross mass, in kilograms c) The name of the manufacturer d) The purchaser's order number and port of destination 23.0 Documentation Each AR shall be supplied complete with the documentation specified in Items as per clause 20.1 20.2 . 20.3 and 20.4, together with the routine test certificates specified in clause 21.4. 24.0 SPECIAL TOOLS AND TACKLES 24.1 The Bidder shall furnish a list of any special tools and tackles required for maintenance and operation purposes with recommended quantities for each substation. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 70 Technical Specification 2.14 1.0 TECHNICAL SPECIFICATION OF 33 KV & 11KV SELF POWERED AUTO RECLOSER SCOPE The specification covers the design, manufacturing, testing, supply, installation, testing and commissioning of 33/11kV Un-manned substation made with outdoor pole mounted auto-recloser that have programmable protection features and integrated remote operation capability and that are intended for distribution networks at nominal A.C. voltages of 36/12 kV. 2.0 APPLICABLE STANDARDS The following standards contain provisions that, through reference in the text, constitute requirements of this specification at the time of publication the revisions indicated were valid. All standards are subject to review and parties to purchasing agreements based on this specification are encouraged to investigate the possibility of applying the most recent revisions of the standards listed below. ANSI/IEEE C37.60-1981: Requirements for overhead, pad mounted, dry vault, and submersible automatic circuit reclosers and fault interrupters for AC systems (RI993) IEC 60255, Electrical relays IEC 60056:1987, High-voltage alternating-current circuit breakers. Amendment No. 1:1 992. IEC 60529:1989, Degrees of protection provided by enclosures (IP Code). UNIPEDE NORM (SPEC) 13 (1995): Automation and Control Apparatus for Generating Stations and Substations: Electromagnetic Compatibility Immunity Requirements. 2.1 CLIMATIC CONDITIONS The Substation shall be suitable for satisfactorily working under the following climatic conditions: Max. Ambient Temperature Min. Ambient Temperature Max. Relative Humidity Min. Relative Humidity Altitude 550 C 20 C 100 % 56 % Below 1000 meters above mean sea level. The switch Switchgears and Auto-reclosers used shall be suitably designed and treated for normal life and satisfactory operation under the hot and hazardous tropical climate conditions and shall be dust and vermin proof. All interior and exterior ferrous surfaces of auto-reclosers and control cabinets shall be manufactured from marine grade stainless steel. All support structures and associated bolts and nuts with these parts, shall be hot-dip galvanized. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 71 Technical Specification 3.0 TECHNICAL DATA SHEET FOR AUTO RECLOSER Sl. No. 34 Particulars 35 No of poles 36 37 38 39 Service Rated System Voltage Highest System Voltage System earthing 40 41 45 46 Rated Voltage of AR kV Rated Continuous Current Amps c) For lines d) For Transformers Rated Frequency Hz Rated Short Circuit breaking kA RMS current ( I ) - 3secs – symmetrical Rated Short Circuit making current kA PEAK Interrupting medium Insulation medium 47 48 49 50 Closing mechanism Opening mechanism Mounting type Enclosure 51 52 Duty cycle 53 Insulation level 54 i) Power Frequency with Stand kV RMS Voltage ii) Impulse withstand Voltage kV Peak Minimum clearance between mm phases Minimum clearance between phase to earth 42 43 44 55 56 Unit Type Minimum Creepage Distance (Total) Operating mechanism: kV kV Data for 33kV AR SF6 Data for 11kV AR Solid 3 (3 Phase Ganged Unit) 3 (3 Phase Ganged Unit) Outdoor 33 38 Solidly earthed system 36 Outdoor 11 15.5 Solidly earthed system 12 800 400 50 16 630 630 50 12.5 2.5*I 2.5*I Vacuum SF6 /Solid Dielectric LV Solenoid Springs Single pole 316 grade stainless steel Vacuum Solid dielectric LV Solenoid Springs Single pole 316 grade stainless steel O-1strt-CO-2ndrt-CO-O-1strt-CO-2ndrt-CO3rd 3rd rt-CO rt-CO CO CO mm 70 60 170 400 110 375 400 295 1100 780 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 72 Technical Specification Sl. Particulars No. a) Type Unit Data for Data for 33kV AR 11kV AR Solenoid-Spring Solenoid-Spring .c) Rated voltage of Shunt trip coil & operating range V. DC 110[50% - 110%] d) Rated voltage of Closing coil & operating range e) No. of trip coils f) No. of closing coils g) Nos of expandable auxiliary I/O contacts & contact rating (Required for transformer & Incomer AR) V. DC 110 [80% - 110%] 110 [50% 110%] 110 [80% 110%] No 2 per AR 2 per AR No 1 per AR 1 per AR Nos 12 I/P+8 O/P 12 I/P+8 I/P (per AMPS (per AR) CB) 10 A at 240V AC 10 A at 240V AC & 10A at 110V DC & 10A at 110V DC h) Minimum thickness of sheet steel mm 3 3 for control cabinet i) Enclosure Protection IP55 IP55 57 Reclosing Three Phase Three Phase auto reclosing auto reclosing 58 Support structure Galvanised Galvanised (Painted / Galvanised) 59 All other parts (Painted / Synthetic enamel Synthetic Galvanised) shade enamel shade 631 of IS5 631 of IS5 (125 microns) (125 microns) 60 61 62 Minimum size of control wiring (Copper) Protection a) For transformer b) For line 63 Measurement Sq. mm 2.5 Numeric O/C, E/F, SEF, relay Differential, OTI, WTI, PRV, Buchholz, OSR with Backup -doScheme O/C, E/F, SEF 2.5 O/C, E/F, SEF Differential, REF, with Backup Scheme O/C, E/F, SEF Digital Real time current, Real time voltage, PF current, voltage, PF 4.0 DEFINITIONS AND ABBREVIATIONS 4.1 Auto-recloser (AR): A mechanical switching device that, after opening, closes automatically after a predetermined time. Several reclosures could occur before lockout. 4.2 Cold load pick-up (CLP) feature: A feature that allows modification of the overcurrent protection characteristics in order to prevent relay maloperation under conditions of system energisation. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 73 Technical Specification 4.3 Dead time: The time between the instant that the current is interrupted by the AR and the instant the contact of the AR closes as a result of an automatic reclose operation. [IEC 50-448-04-09] 4.4 Definite time lag (DTL) protection element: A protection element with a settable time delay that is constant above the pick-up current setting. 4.5 Delayed protection operation: The protection functionality enabling delayed circuit-breaker operation, whether this is due to an IDMTL or DTL protection element. 4.6 Disc reset time: The time required for the disc of an electromechanical IDMTL protection relay to turn back to its original position after it has turned to the position where a protection operation was initiated. 4.7 Effectively earthed system: An earthed system in which the healthy phase power frequency phase-to-earth over voltages associated with earth faults are limited to 80% of the highest phase-to-phase voltage of the system. 4.8 Fast curve protection element: A family of curves with operating times approximately constant (slightly inverse) relative to the multiple of pick-up setting. 4.9 Instantaneous protection element: An element with no intentional time delay active above a pre-determined pick-up current setting. 4.10 Inverse definite minimum time (IDMT) protection element: A protection element the minimum operating time of which is adjustable and is inversely proportional to the fault current. 4.11 Pole-mounted remote terminal unit (PMRTU): A remote terminal unit that is designed for pole mounting and that operates specific pole-mounted equipment remotely. 4.12 Rapid protection operation: The protection functionality enabling rapid circuitbreaker operation, whether this is due to an instantaneous, fast curve, or a definite time delay protection element with relatively short definite time delay. 4.13 Reset time: The time duration after a circuit-breaker close operation for which the measured currents are below a fault detecting level. On the expiry of this time the protection sequence resets. 4.14 Secure control: A single mechanically non-latching switch that effects one state of a control function only. An example of which is either a non-latching switch or two separate push buttons that effect one state of a control function only in each position. If a control is activated repeatedly it only effects that state and does not change the state of the control. 4.15 Sensitive earth fault (SEF) relay: A relay that is sensitive to very low earth fault currents and in which the operating settings are for current magnitude and definite time delay. 4.16 Supervisory: Remote control and indications of an AR or a PMRTU by means of a telecommunications link. 4.17 Toggled control: A single mechanically non-latching switch/push-button that enables a single control function on the first operation of the switch/push-button and disables the function on the second operation of the same switch/push button. 4.18 Zone sequence co-ordination (ZSC): The feature that allows protection devices to maintain sequence co-ordination for combinations of rapid and delayed protection operations. 5.0 Mounting 5.1 5.2 The AR shall be suitable for single pole mounting. Adequately rated lifting eyes shall be provided and they shall be designed to allow the completely assembled AR (surge arresters fitted) to be lifted without recourse to a sling spreader. The diameter of the eyes shall be a minimum of 30mm. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 74 Technical Specification 5.3 Suitable mounting brackets for surge arresters shall be provided on the line side and on the load side of the AR, adjacent to the bushings. 5.4 The AR shall be fitted with an external M12 earthing stud, complete with a nut, lock nut and spring washer. 5.5 The AR shall have laser cut markings on each bushings marked U1 V1 W1 for the normal line side and U2 V2 W2 for normal load side. 5.6 A detailed drawing of the single pole AR mounting arrangement with surge arresters fitted shall be provided. The minimum phase-to-earth clearances shall be as per relevant IS and is to be indicated on the drawing. 5.7 The mass of the mounting hardware, the AR and the control cabinet and cable shall be stated in the tender documentation. 6.0 Bushings 6.1 Terminals c) For 33KV AR, the preferred arrangement for bushing is a fully insulated bushing arrangement achieved by using cyclo aliphatic epoxy resign bushings and silicone rubber bushing boots together with 3 meters 185 mm2, single core, XLPE insulated aluminum water blocked cable tails to provide a fully insulated bushing arrangement. d) For 11 KV AR, the preferred arrangement for connection to overhead conductor is using crimp lugs with holes. 6.2 Material The following bushing materials are acceptable: d) Outdoor Cyclo aliphatic epoxy resin and/or Silicone rubber e) Porcelain bushings and EPDM rubber are not acceptable. f) Minimum acceptable creepage is 1100 mm for 33 KV AR and 780 mm for 11KV AR.. 7.0 Finish c) All interior and exterior ferrous surfaces of auto-reclosers and control cabinets shall be manufactured from 316 marine grade stainless steel. All support structures and associated bolts and nuts with these parts, shall be hot-dip galvanized. d) Suitable precautions shall be implemented to prevent corrosion due to the use of dissimilar materials. 8.0 Control equipment 8.1 Control cabinet j) k) l) m) n) Cabinets that house equipment for protection and control shall be mounted independently of the AR. Suitable ultraviolet-resistant cable, shall be provided to connect the AR to the control cabinet. It shall be possible to disconnect the cable at the AR while the AR is connected to the power system, without causing damage or mal-operation: care shall be taken that CTs are not open circuited. A robust, multi-pin weatherproof connector shall be supplied. The female part of the connector shall be mounted on the AR and the male part shall be mounted on the cable. Preference will be given to products supplying connectors at both the AR and the control cabinet. Cabinets shall be adequately sealed and dust protected and shall be internally treated to prevent moisture condensation. The degree of protection shall be IP 55. The supplier shall ensure that the equipment housed in the control cabinet can withstand the heating effect of direct solar radiation without causing failure and/or mal-operation. Details shall be provided in the tender documentation. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 75 Technical Specification o) The cabinet shall make provision for bottom entry of three cables. This shall be done with a pre-punched suitable sized diameter holes. The holes shall be suitably blanked off. p) The cabinet shall be fitted with an external M12 earthing stud with a nut, lock nut and a serrated washer. q) The door of the cabinet shall be fitted with a robust fastening arrangement that is capable of being secured by a padlock that has a shackle of 8 mm diameter. r) The cabinet shall be easily removable for workshop repair purposes. 8.2 Electronic control equipment 8.3 The controls shall not suffer any damage if one or more poles of the circuit breaker fail to respond to either a trip or a close command. 8.4 Electronic modules shall perform continuous diagnostic monitoring and shall contain hardware and software watchdog checking. 9.0 Protection characteristics 9.1 9.2 9.3 9.4 9.5 9.6 9.7 9.8 General The ratio of drop-off current to pick-up current shall be at least 95 % for all protection functions. The E/F and SEF functions shall be equipped with harmonic filtering to prevent operation when harmonics are present in the primary residual earth currents. A low pass filter with: c) 2nd harmonic rejection > 6 1; and d) 3rd harmonic rejection > 50 1 shall be supplied. Both the SEF function and its filter shall be described in the tender documentation All protection functions, i.e. over-current (O/C), earth fault (E/F) and sensitive earth fault (SEF) shall have elements with characteristics that comply with IEC 255. The sequence of trip and auto-reclose characteristics for O/C, E/F and SEF shall be programmable to enable: b) the selection of any combination of the available elements for each trip in the trip-and-reclose sequence; and b) separate trip-and-reclose sequences for O/C, E/F and SEF. In case of IDMTL protection elements the AR shall preferably be provided with a disc reset timer that simulates the resetting functionality of an upstream electromechanical induction disc relay by implementing a disc reset timer. The length of the time delay shall preferably be settable to be able to simulate the upstream device (settable between 5s and 20 s), however, if a fixed time delay is provided it should be between 4s and 5s. A zone sequence co-ordination (ZSC) feature shall be provided to ensure tripclose sequence co-ordination for combinations of rapid and delayed protection operations applied to series ars. ZSC functionality shall be such that: c) an AR senses the presence of an over-current or earth fault, as well as the clearance of that fault by another device and proceeds to the next protection operation in its own sequence; and d) it proceeds in its sequence of rapid protection operations only, allowing the full number of delayed operations to be executed for in-zone conditions. Loss of Phase (LOP) protection shall be provided to ensure the protection functionality of AR as below: e) AR should trip with no auto-reclose in case if there is a loss of voltage on one or two phases on the upstream part of the line. Loss of supply on all three phases shall not generate the protection trip. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 76 Technical Specification f)Facility to turn LOP ON or OFF without affecting other protection functions of the device. Pass-word or other form of access control shall be provided g) The parameters of configuration of LOP shall include the voltage level (phase to ground) and time of loss of supply on one or two phases. The voltage level shall be configurable from 5000 to 19000 Volts (for 33KV) and 5000 to 9000 (for 11KV) with steps not greater then 250 V. Time range shall be configurable from 1 to 60 sec with steps not greater then 1 sec. 9.9 The information about LOP operation in case of the protection trip shall be recorded accordingly with indication of the phase(s) causing the trip of AR. The information about LOP operation shall be easily assessable. h) Rapid protection operation shall be possible by selecting a fast curve or instantaneous protection element. Co-ordination of the fast curves or instantaneous protection elements between two devices in series shall be possible either by selecting suitable curves from a family or by addition of a selectable time increment, typically 0,05s to 3s, in 0,05s steps, or any other acceptable solution. 9.10 Long protection operating times associated with fault levels marginally above the pick-up setting of the IDMTL protection element shall be avoided by the provision of a Low Set Definite Time element with the following features: d) it shall be possible to enable or disable the element. When enabled it shall be active simultaneously as an overlay with all selected elements; e) the element shall have the same pick-up current setting as the IDMTL element; and f) the time delay shall be selectable from 2s to 10s, in 1s steps. The time delay shall be independent of any curve manipulation. 9.11 A High Set Instantaneous element with a selectable time delay shall be provided, with the following features: e) it shall be possible to enable or disable the element. When enabled it shall be active simultaneously as an overlay with all selected elements; f) circuit-breaker lock-out as a result of an operation due to the High Set Instantaneous element shall be selectable; g) the pick-up setting range of this element shall be at least 100 % to 1500 % of the over-current setting and shall be independent of any curve manipulation; and h) the time delay shall be selectable from instantaneous to 1s, in 0,05 s steps. The time delay shall be independent of any curve manipulation. 9.12 A cold load pick-up (CLP) feature shall be provided that allows user selectable modification of protection element characteristics under conditions of system energization. The CLP function may be provided in one of the following two ways: c) The instantaneous O/C element and the Low Set Definite Time O/C element could be blocked for the CLP time duration; and d) The pick-up current setting of the IDMTL O/C element and the Low Set Definite Time O/C element may be modified with a settable factor to increase the pick-up current of these elements for the CLP duration. The instantaneous O/C element should be blocked for this time. This is the preferred method. The CLP function shall have the following characteristics: iv. the CLP function shall not in any way interfere with any of the other functions'/elements' pick-up current settings except as mentioned above; v. the CLP functionality shall be such that the active duration of the CLP is selectable from 0 min to 20 min in 1 min steps; and vi. the modification factor should be settable from 1 to 2 in steps of 0,1. 9.13 Earth fault function Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 77 Technical Specification 9.14 The earth fault setting range shall detect primary earth fault currents down to 20 A. 9.15 Delayed protection operation shall be possible by selecting an IDMTL element with NI, VI or El curve, or a definite time protection element with time delay from 0.05s to 10s, in 0,05s steps. 9.16 Rapid protection operation shall be possible by selecting a fast curve or instantaneous protection element. Co-ordination of the fast curves or instantaneous protection elements between two devices in series shall be possible either by selecting suitable curves from a family or by addition of a selectable time increment, typically 0.05s to 3s, in 0.05s steps, or any other acceptable solution. 9.17 A High Set Instantaneous element with a selectable time delay shall be provided with the following features: e) it shall be possible to enable or disable the element. When enabled it shall be active simultaneously as an overlay with all selected elements; f) circuit-breaker lockout as a result of an operation due to the High Set Instantaneous element shall be selectable; g) he pick-up setting range of this element shall be at least 100 % to 1500 % of the earth fault setting and shall be independent of any curve manipulation; and h) he time delay shall be selectable from 0,05s to 1s, in 05s steps. The time delay shall be independent of any curve manipulation. 9.18 Sensitive earth fault (SEF) function 9.19 A primary earth fault current of 4A to 20A in steps not exceeding 1A shall be detectable. 9.20 Delayed protection operation shall be possible by selecting a definite time protection element with time delay from 3s to 25s, in 1s steps. 10.0 Auto-reclose operation parameters 10.1 The number of sequential trips to reach lockout shall be selectable to be either 1,2,3 or 4. 10.2 Reset times shall ideally be separately selectable for SEF and the combination of over-current and earth fault functions. The reset time shall be selectable from 5s to 120s in 1s steps. 10.3 Dead times shall ideally be separately selectable for SEF and the combination of over-current and earth fault functions. The dead time between each successive reclosure shall be independently selectable from instantaneous to 5s for the first reclosure and from a minimum of 2s up to a maximum of 120s for subsequent reclosures. 10.4 A close instruction initiated locally or remotely during a dead time shall result in lockout if the fault is still present upon closure. 11.0 Statistical measurement functions 11.1 The characteristics of the statistical measurement functions shall be as follows 11.2 Measurement shall be done with three-phase-4-wire method. 11.3 Quantities to be measured / calculated with class 0.5 accuracy are: k) r.m.s. phase-to-phase and phase-to-neutral voltage of all three phases: l) r.m.s current per phase m) three phase active power in kW n) three phase reactive power in kvars o) total three-phase active energy in kWh p) Power factor q) Maximum demand r) Harmonic analysis s) Wave form capture Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 78 Technical Specification t) Fault stimulator 11.4 The real power energy, reactive energy and apparent energy measurement should be cumulative. While maximum demand measurement shall be integrated with respect to time. With selectable time integration periods of 5 min, 15 min, 30 min or 60 min. The data buffer shall work on the FIFO principle and a minimum size for the data buffer shall store values for 4 months. 11.5 The voltage factor of the voltage transformers shall be a minimum of 1.9 for 8 hours. 11.6 CB and Control element shall have the facilities to record the number and duration of outages. The information shall be assessable locally or remotely using SCADA system. The following parameters shall be recorded: d) Cumulative total number of outages e) Cumulative total outage duration f) Time and duration of each outage 12.0 Local control and indication: 12.1 The local control and indication shall be as given in Table-1: Table-1- Minimum specification of local controls ad indications: Item Features Remarks Local control Local/Remote 2 position key switchable (See note 1) Circuit-breaker open (see note 3) Circuit-breaker close Secure control ARC ON/OFF Secure control SEF ON/OFF Secure or toggled control Secure or toggled control Local indication Local/Remote (see note 3) (See note 1) Circuit-breaker open Circuit-breaker close Circuit-breaker lock-out ARC ON/OFF SEF ON/OFF Protection operation See 12.7 Controller not healthy (see note 2) SF , Alarm See 12.9 AC fail DC abnormal See 17.7 DC fail Charger fail Local Analog indication (See note 1) r.m.s phase-to-phase to neutral voltage of all three phases r.m.s current per phase three phase active power in KW three phase reactive power in kvars total three-phase active energy in kWh Power factor Maximum demand Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 79 Technical Specification NOTES: Note 1: The local control and the local indication features on the control panel shall be labeled as presented in column 2, where applicable. The type of switch used for local control shall not allow for a conflict to exist between the switch position and the function status. Note 2: The Controller not healthy indication shall indicate the control equipment not healthy (watchdog) function operated. It shall not operate during the normal pole mounted switch operating cycle. This indication should remain active until the unhealthy state that initiated it returns to normal. Note 3: The three-position switch (labeled as below) shall allow the AR controller to be set in the following modes: Remote: In this mode a local operator can trip the AR and change the mode. A remote operator can trip or close the AR and change configuration parameters. All reporting functions are active. Local: In this mode a local operator can trip and close the AR and change configuration parameters. All reporting functions are active. 12.2 All local controls and indications shall be accessible in adverse weather condition. 12.3 The AR shall be provided with external levers to permit manual operation, using an insulated operating stick, to open, close, lock-out and reset the AR from ground level . Where these operations can be performed at the control cabinet, it shall only be necessary to provide a mechanical means to open and lockout the circuit breaker using an insulated operating stick. 12.4 The AR status shall be clearly visible from ground level. ―Opened‖ shall be indicated with a green ―O‖. ―Closed‖ shall be indicated by a red ―I‖. Alternative indications shall be subject to approval by the purchaser. 12.5 Pressure relief facilities shall be provided to enable the AR to withstand safely the effects of excessive pressure rise due to an internal fault. 12.6 Malfunction of the AR shall not pose a safety hazard to the operator due to the recoil or backlash of items such as external operating rods, ranks and levers. 12.7 Easily available (i.e maximum of one keystroke) local indication of protection operation shall be provided for at least the last operation of the AR. The function, phase involved and the current magnitude shall be indicated. 12.8 Switches used for local control shall offer the type of control described in table 1 i.e. secure or toggled control. Electronic keypad controls shall offer ‗quick key‘ (maximum of one keystroke) access to the controls in table1 if not implemented with switches 12.9 ARs using SF, as an arc extinguishing/Insulating medium shall: d) Provide a low gas pressure indication at a gas pressure that enables safe operation of the AR e) Prevent closing of the AR after it has opened under the abovedescribed condition f) Be provided with a method of inhibiting any operation of the AR in the event of the gas pressure dropping below a safe pressure. 12.10 Event Logging, configured History & Demand Reports The system is capable of logging very comprehensive data in three different categories i) Event Logging This log should have all the events observed by the device including ON/OFF operation, Local commands, protection element pick-up and trip, change of settings, Aux supply, fault level (Interrupted current valus) Battery low etc. j) Demand Logging Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 80 Technical Specification Should upload from the devices all records of weekly and monthly demand, and used for analysis of load behavior on each feeder including the total no of outages and duration of outages 13.0 Power supplies 13.1 13.2 13.3 13.4 14.0 14.1 Auxiliary supply for closing, tripping and normal functioning of the VCB must be derived from a 48 volts dc, sealed-maintenance-free, valve regulated lead acid (VRLA) battery, provided in outdoor control panel. The battery should be charged through the charger circuit provided in the control panel. The charger input shall be derived from the secondary of the potential transformer mounted on the same pole or from any other auxiliary source within the range 85 to 265 volts ac or dc. AC input auxiliary power supply interface with filter unit for impulse noise protection 48 volts rechargeable sealed-maintenance-free battery to provide uninterruptible dc auxiliary power supply for numeric data processing, VCB numeric control & monitoring and to the communication modem (when provided). Battery must have A-H capacity rating suitable to provide back-up supply up-to 48 hours after loss of ac input auxiliary supply (without communication). Battery should have an average life expectancy of around 5 years. A thermal sensor should continuously monitor the healthiness of the battery and any battery unhealthy condition must be recorded as a malfunction event. The battery shutdown capacity, ampere-hour capacity, RTU shutdown level / supply voltage, should all be programmable through the recloser control module Maintenance and commissioning All the communications equipment shall be easily accessible in the control cabinet. Wiring of "communications links in the control cabinet shall permit the connection of a temporary protocol-Monitor. It shall be possible to perform secondary injection testing while the AR is communicating with the center. It shall be Possible to disconnect the AR circuit breaker and connect a simulated breaker to the control cabinet for testing purposes. 14.2 The AR shall not malfunction while the radio is transmitting via an antenna in close proximity and the control cabinet door is open. 14.3 Provision shall be made in the control cabinet for individually isolating the power supply to/from the following: e) battery; f) battery charger; g) radio; and h) primary supply to the control cabinet electronics. 15.0 Rating plate Each AR shall bear a rating plate of an intrinsically corrosion-resistant material, indelibly marked with the sea-level rating for which the equipment has been type tested. The rating plate shall be indelibly marked with: f. the manufacturer's name; g. the equipment type designation and serial number of the ar; h. the mass, in kilograms; i. the date of manufacture; j. the voltage transformer ratio, class and burden. auxiliary supply voltage (if applicable); and 16.0 Additional information The following shall be submitted with the tender. 16.1 Circuit breaker details h) manufacturer; i) type designation; j) place of manufacture; k) short circuit breaking capacity; 3s 1s l) asymmetrical breaking current; m) peak making current; and Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 81 Technical Specification n) critical current (maximum instantaneous peak). 16.2 A schematic-wiring diagram of the AR offered. 16.3 A general-arrangement drawing of the AR offered. 16.4 Details of the maintenance and operating equipment and procedures needed and a detailed parts list of the various components. 16.5 A description of the AR operation, with instruction and maintenance manuals, including maintenance schedules, protection characteristics, communications facilities, the method of applying settings to relays and controls, together with any software required and the cost thereof. The software requirements shall be stated in the tender documentation. 16.6 Details and the cost of any available portable calibration and diagnostic test set that may be used to perform the functionality described in clause 14.1, 14.2 and 14.3. Details of the test set shall be given in the tender document. 16.7 A list of recommended spares and tools, quoting the prices of each item and its availability. 16.8 If protection setting changes are accomplished by resistors, electronic cards or modules or computer programs, the price and range of such items. The method of changing protection settings shall be stated in the tender documentation. 16.9 Details of technical back-up facilities available. These details shall be stated in the tender documentation. 16.10 Details of the class, ratio(s) and burden of the protection current transformer and voltage transformer, if supplied, shall be stated in the tender documentation. 16.11 The supplier shall include the following details of measurement current transformers (not internal to the AR) that can be supplied with the AR. The following details shall be provided: d) available ratio(s) and accuracy class; 16.12 16.13 16.14 16.15 16.16 16.17 17.0 e) method of fitting; and f) effect on creepage distance and BIL Where applicable details of the low gas pressure alarm/lock-out philosophy; Details of AR service history: c) how many in service, where and for what period; and d) contact names and numbers. Details of LV trip/close coil if available as an option Power requirements for a close operation The maximum achievable separation between the control unit and the circuit breaker. Full details of the protocol implementation and the complete point database. TESTS 17.1 Type tests l) The AR shall have been type tested in accordance with, and found to comply with, the requirements of either IEC 60056 or ANSI/IEEE C37.60-1981 for the following, and the appropriate values shall be stated in the tender documentation: m)Interrupting performance (automatic operation). n) Interrupting performance (manual operation). o) Operating duty. p) Making current. q) Minimum tripping current. r) Insulation (dielectric tests). s) Radio interference voltage. t) Temperature rise. u) Mechanical operations. v) Control equipment surge withstand capability. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 82 Technical Specification 17.2 The control cabinet and associated electronics shall have been type tested in accordance with UNIPEDE NORM (SPEC) 13 (1995): Automation and Control Apparatus for Generating Stations and Substations: Electromagnetic Compatibility Immunity Requirements. The environment shall be considered as failing in the HV substation category, according to NORM (SPEC)13. 17.3 Test records (on identical equipment) in the form of validated copies of test certificates issued by a recognized testing authority shall be submitted with the tender documentation. 17.4 Routine tests Routine tests, as required in the relevant standards, shall be carried out as a normal requirement of the contract and, unless otherwise agreed upon, shall be witnessed by the purchaser or by his appointed representative. No additional charge shall be levied for such tests or for the production or presentation of documentation related to routine tests. Duplicate copies of routine test certificates shall be supplied together with the equipment when the latter is delivered to the final destination stated in the order. 18.0 PACKING/DOCUMENTATION 18.1 Packing All equipment shall be carefully packed to prevent damage or deterioration during normal transportation, handling and storage. Each container shall bear the following information on the outside of the container: e) The address of the destination f) The gross mass, in kilograms g) The name of the manufacturer h) The purchaser's order number and port of destination 19.0 Documentation Each AR shall be supplied complete with the documentation specified in Items as per clause 16.1, 16.2 . 16.3 and 16.4, together with the routine test certificates specified in clause 17.4. 20.0 SPECIAL TOOLS AND TACKLES 20.1 The Bidder shall furnish a list of any special tools and tackles required for maintenance and operation purposes with recommended quantities for each substation. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 83 Technical Specification 2.15 TECHNICAL SPECIFICATION OF 33 KV OUTDOOR SF6 CIRCUIT BREAKERS (AIS TYPE) 1.0 SCOPE 1.1 The intention of this Section of the Specification is to cover design, manufacture, testing at manufacturer‟s works of 132 and 33 KV Circuit Breakers with all fittings and accessories including mounting structures as specified hereunder. 2.0 GENERAL REQUIREMENTS 2.1 The circuit breaker shall be of three phase unit (gang operated) (or) three identical single phase units (as said in data sheet), outdoor, single pressure puffer type. The operating mechanism shall be electrically and mechanically trip/free with antipumping facility suitable for remote electrical closing, tripping as well as local Operation facility as specified. The CBs are meant for installation with Transformers & Lines. 2.2 The circuit breaker shall be so designed to withstand the effects of temperature, wind load, short circuit conditions and other adverse conditions. 2.3 The circuit breaker shall be capable of switching transformer magnetizing currents and shall be restrike - free. 2.4 All similar parts, particularly removable ones, shall be interchangeable with one another. 2.5 All cable ferrules, lugs, tags, etc. required for cabling from equipment control cabinet/operating mechanism to the central control cabinet of the breaker shall be supplied loose as per approved schematics. 2.6 The SF6 breaker shall be designed to ensure that condensation of moisture is controlled by proper selection of organic insulating materials having low moisture absorbing characteristics. 2.7 The support structure of circuit breaker shall be hot dip galvanised. Sufficient galvanising thickness shall be achieved with 615 gm/m². All other parts shall be painted as per painting specification enclosed separately. 3.0 OPERATING MECHANISM 3.1 A power spring operated mechanism for closing and tripping shall be provided in the breaker control cabinet. This device shall be so interlocked that while it is under maintenance, the breaker cannot be operated from remote. A slow acting, manually operated device shall be provided for inspection and maintenance purposes. 3.2 Circuit breaker operating mechanism shall be capable of storing energy for atleast two complete closing and tripping operations. 3.3 Each mechanism shall have an operation counter. 3.4 The operating mechanism shall be mounted and enclosed in a weather proof, vermin-proof, sheet steel cabinet conforming to IP: 55 degree of protection. Sheet steel thickness shall be as specified in data sheet. The cabinet shall also house relays, control and auxiliary equipment of each breaker and provision for terminating all control, alarm and auxiliary circuits. It shall be provided with hinged doors with provision for locking and removable gland plates to be drilled at site. Inspection window shall be provided for observation of the instruments without opening the cabinet. It shall be mounted so as to provide convenient access from ground level. 3.5 The cabinet shall be fitted with a thermostatically controlled anti-condensation heater, a 15A, 1 phase, 5 pin socket outlet with switch and a cubicle illuminating lamp suitable for operation on 240 V AC 50Hz supply. 3.6 Circuit breakers shall feature high repeatability of absolute closing time over a wide range of parameters (ambient temperature, pneumatic pressure, control voltages, etc). 3.7 Main poles shall operate simultaneously. There shall be no objectionable rebound and the mechanism shall not require any critical adjustment. It shall be strong, rigid, positive and fast in operation. 3.8 Disagreement circuit shall be provided which shall detect pole position discrepancy. 3.9 The design of the circuit breaker shall be such that contacts will not close automatically upon loss of gas/ air pressure. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 84 Technical Specification 3.10 Closing release shall be capable of operating within the range of the rated voltage as specified in the data sheet. Shunt trip shall operate satisfactorily under all operating conditions of the circuit breaker up to the rated breaking capacity of the circuit breaker with in the range of the rated voltages specified in the Data sheet. 3.11 Working parts of the mechanism shall be of corrosion resisting material. Bearings which require grease shall be equipped with pressure type grease fittings. Bearing pin, bolts, nuts and other parts shall be adequately pinned or locked to prevent loosening or changing adjustment with repeated operation of the breaker. 3.12 All controls, gauges, relays, valves, hard drawn copper piping and all other accessories as necessary shall be provided including the following: 3.13 Low pressure alarm and lock out relay with adjustable pressure setting suitable for operation on DC system 3.14 A no-volt relay for remote indication of power failure for compressor motor/ Spring Charge motor. 3.15 As long as power is available to the motor, continuous sequence of closing and opening operations shall be possible. 3.16 After failure of power supply to the motor, at least one open-close-open operation of the circuit breaker shall be possible. 3.17 Motor rating shall be such that it requires only about 30 seconds for full charging of the closing spring. 3.18 Closing action of the circuit breaker shall compress the opening spring ready for tripping. 3.19 During closing, springs are discharged and after closing of breaker, springs shall automatically be charged for the next operation. Facility for manual charging of closing springs shall be provided. Mechanical interlocks shall be provided in the operating mechanism to prevent discharging of closing springs when the breaker is already in the closed position. 4.0 OPERATING MECHANISM CONTROL 4.1 The breaker shall normally be operated by remote electrical control. Two electrically independent trip circuit including two trip coils per pole shall be provided. However, provision shall be made for local electrical control. For this purpose a local/remote selector switch, close and trip control switch/push button shall be provided in the breaker central control cabinet. 4.2 The trip coils shall be suitable for trip circuit supervision during both open and close position of the breaker. Necessary terminals shall be provided in the central control cabinet of the circuit breaker by the Supplier. 4.3 The auxiliary switch of the breaker shall be positively driven by the breaker operating rod. 4.4 A conveniently located manual tripping lever or button shall also be provided for local tripping of the breaker and simultaneously opening the reclosing circuit. A local manual closing device which can be easily operated by one man standing on the ground shall also be provided for maintenance purpose. Direction of motion of handle shall be clearly marked. 4.5 When the spring get fully charged either through motor or hand cranking, the spring charging motor and the hand cranking device should get disengaged mechanically from the charged spring and this should not be depended upon only the limit switch. 5.0 SF6 GAS SYSTEM 5.1 SF6 gas shall serve as an arc-quenching medium during opening/closing operation and as an insulating medium between open contacts of the circuit breaker. 5.2 The circuit breaker shall be single pressure type. The design and construction of the circuit breaker shall be such that there is a minimum possibility of gas leakage and entry of moisture. There should not be any condensation of SF6 gas on the internal insulating surfaces of the circuit breaker.. 5.3 All gasketted surfaces shall be smooth, straight and reinforced, if necessary, to minimise distortion and to make a tight seal, the operating rod connecting the Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 85 Technical Specification 5.4 5.5 5.6 5.7 operating mechanism to the arc chamber (SF6 media) shall have adequate seals. The SF6 gas leakage should not exceed 1% per year In the interrupter assembly there shall be an absorbing product box to minimise the effect of SF6 decomposition products and moisture. The material used in the construction of the circuit breakers shall be such as fully compatible with SF6 gas decomposition products. Each pole shall form an enclosure filled with SF6 gas independent of two other poles and the SF6 density of each pole shall be monitored. For CBs of voltage class of 36 kV, a common SF6 scheme/density monitor shall be acceptable. The dial type SF6 density monitor shall be adequately temperature compensated to model the pressure changes due to variations in ambient temperature within the body of circuit breaker as a whole. The density monitor shall have graduated scale and shall meet the following requirements: It shall be possible to dismantle the density monitor for checking/replacement without draining the SF6 gas by providing suitable interlocked non return valve coupling. 6.0 BUSHINGS AND INSULATORS 6.1 Bushings and Insulators shall be of Porcelain, Solid core type. Porcelain used for the manufacture of bushings and insulators shall be homogeneous, free from defects, cavities and other flaws or imperfections that might affect the mechanical or dielectric quality and shall be thoroughly vitrified, tough and impervious to moisture. 6.2 Glazing of the porcelain shall be of uniform brown colour, free from blisters, burns and other similar defects. Bushings shall be designed to have sufficient mechanical strength and rigidity for the conditions under which they will be used. All bushings of identical ratings shall be interchangeable. 6.3 Puncture strength of bushings shall be greater than the dry flashover value. When operating at normal voltage, there shall be no electric discharge between the conductors and bushing which would cause corrosion or injury to conductors, insulators or supports by the formation of substances produced by chemical action. No radio interference shall be caused by the bushings when operating at the normal rated voltage. 6.4 Bushings shall satisfactorily withstand the insulation level specified in data sheet. . 7.0 FIXED AND MOVING CONTACTS 7.1 Main contacts shall have ample area and contact pressure for carrying the rated current and the short time rated current of the breaker without excessive temperature rise which may cause pitting or welding. Contacts shall be adjustable to allow for wear, easily replaceable and shall have minimum moving parts and adjustments to accomplish these results. Main contacts shall be the first to open and the last to close so that there will be little contact burning and wear out. 7.2 Arcing contacts, if provided, shall be the first to close and the last to open and shall be easily accessible for inspection and replacement. Tips of arcing and main contacts shall be silver faced. 7.3 If multi-break interrupters are used, they shall be so designed and augmented that a fairly uniform voltage distribution is developed across them. 7.4 8.0 INTERLOCKS 8.1 Key release mechanical interlocks shall be incorporated in the operating mechanism for interlocking with the associated isolators, so that operation of the circuit breaker is dependent on a "key-trapped" situation. In addition, electrical interlocks with associated isolators shall be provided. 9.0 ADDITIONAL DUTY REQUIREMENTS 9.1 Circuit breakers shall be capable of clearing short line faults with the same impedance behind the bus corresponding to the rated fault current. 9.2 Circuit breakers shall be capable of breaking 25% of rated fault current at twice rated voltage under out of phase conditions. 9.3 The Bid shall highlight the design features provided to effectively deal with: Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 86 Technical Specification 10.0 a) Breaking of inductive currents and capacitive currents. b) Charging of long lines and cables. c) Clearing developing faults within the full rating of the breaker. d) Opening on phase opposition. ACCESSORIES 10.1 Gas Pressure Detector The circuit breaker shall be provided with gas pressure monitor with temperature compensation for initiating alarm and locking the operating mechanism in the event of abnormality. Gas pressure monitor shall be provided for each pole individually for 33 kV Circuit Breakers. 10.2 Position Indicator Each pole of the circuit breaker shall be provided with a position indicator. 10.3 Terminals Each circuit breaker shall be provided with suitable terminal pads of high conductivity aluminium alloy for connecting to the line. 10.4 Auxiliary Switches Each circuit breaker shall be equipped with auxiliary switches with sufficient number of contacts for control, indication and interlocking purposes. Ten normally open and ten normally closed contacts shall be provided as spares. All contacts shall be rated for the DC voltage specified in data sheet. 10.5 Terminal Blocks All accessories and control devices shall be completely wired. All wirings which are connected to external circuit shall be terminated on terminal blocks installed in the control cabinet. The terminal blocks provided shall have twenty (20) percent spares 10.6 Operating mechanism housing shall be supplied with all required accessories including the following: 11.0 12.0 13.0 a) Padlocks and duplicate keys. b) Space heaters equipped with automatic thermostatic control. c) Local/remote changeover switch. d) Manually operated tripping push button/lever (mechanical) conveniently located to trip all three phases simultaneously. e) Control switches to cut off control power supplies. f) Fuses as required. g) Two earthing terminals. h) Auxiliary relays required for satisfactory operation. i) Motor contactor with thermal release j) Provision for mechanical interlock with isolator. SUPPORT STRUCTURES 11.1 The Circuit Breakers shall be suitable for mounting on steel structures. 11.2 The support structure shall be of steel hot dip galvanised type. The height of support structure shall be designed to keep the bottom most live part and bottom of insulators of circuit breakers at minimum clearance from the plinth as specified in data sheet. 11.3 All necessary galvanised bolts, nuts and washers to complete the erection shall be furnished including the embedded anchor bolts for securing the supporting structure to the concrete foundations. NAME PLATES 12.1 All equipment shall have non-corrosive name plates fix at a suitable position indelibly mark with full particular there on in accordance with the standard adapted. EARTHING 13.1 Two earthing pads shall be provided on each supporting structure. Each control cabinet or terminal box mounted on the supporting structure shall also be connected to an earthing pad. Separately mounted control cabinets shall be provided with two Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 87 Technical Specification 14.0 15.0 16.0 earthing pads adjacent to the base of the cabinet. The earthing connection shall be bolted type and suitable for receiving 65mm x 12mm MS strip. TERMINAL CONNECTORS 14.1 The equipment shall be supplied with required number of terminal connectors of approved type suitable for ACSR conductors. The type of terminal connector, size of connector, material, and type of installation shall be approved by the Employer, as per installation requirement while approving the equipment drawings. TESTS 15.1 All routine tests shall be carried out in accordance with relevant IS. All routine/acceptance tests shall be witnessed by the Employer/his authorised representative. The tests shall include the following: a) Routine/Acceptance Tests (all units) i) Mechanical Operation tests ii) Power frequency voltage withstand test (dry) iii) Tests on auxiliary & control circuits iv) Measurement of resistance of the main circuit. b) Type Tests: The bidder shall furnish type test certificates and results for the following tests along with the bid for breaker of identical design. i) Breaking and making capacity test ii) Short-time current test iii) Temperature rise tests iv) Lightning Impulse voltage test c) Test Certificates Copies of routine/acceptance test certificates shall be produced with the endorsement of the inspecting authority to the Employer before effecting despatch. The test report shall contain the following information. i) Complete identification data, including serial No. of the breaker. ii) Method of application, where applied, duration and interpretation of results in each test. PRE-COMMISSIONING TESTS 16.1 Contractor shall carry out following tests as pre-commissioning tests. Contractor shall also perform any additional test based on specialties of the items as per the field instructions of the equipment Supplier or Employer without any extra cost to the Employer. The Contractor shall arrange all instruments required for conducting these tests along with calibration certificates and shall furnish the list of instruments to the Employer for approval. (a) Insulation resistance of each pole. (b) Check adjustments, if any suggested by manufacturer. (c) Breaker closing and opening time. (d) Slow and Power closing operation and opening. (e) Trip free and anti pumping operation. (f) Minimum pick-up voltage of coils. (g) Dynamic Contact resistance measurement. (h) Functional checking of control circuits interlocks, tripping through protective relays and auto reclose operation. (i) Insulation resistance of control circuits, motor etc. (j) Resistance of closing and tripping coils. (k) SF6 gas leakage check. (l) Dew Point Measurement (m) Verification of pressure switches and gas density monitor. (n) Checking of mechanical „CLOSE‟ interlock, wherever applicable. (o) Testing of grading capacitor. (p) Resistance measurement of main circuit. (q) Checking of operating mechanisms (r) Check for annunciations in control room. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 88 Technical Specification 17.0 SPECIAL TOOLS AND TACKLES 17.1 The Bidder shall furnish a list of any special tools and tackles required for maintenance and operation purposes with recommended quantities for each substation. TECHNICAL DATA SHEET FOR CIRCUIT BREAKER 18.0 Sl. No. Particulars Unit Data for 1 2 Type No of poles SF6 3 4 5 6 Service Rated System Voltage Highest System Voltage System earthing 7 8 9 kV Amps Hz kA RMS 10 Rated Voltage of Breaker Rated Continuous Current Rated Frequency Rated Short Circuit breaking current ( I ) - 3secs - symmetrical 11 12 Rated Short Circuit making current Duty cycle kA PEAK 13 14 First pole to clear factor Opening time i) Opening Time 2.5*I 0-0.3 Sec - CO -3 Min -CO 1.3 ms ii) Closing Time ms Not exceeding 50 ms Not exceeding 120 ms 33 kV CB 15 kV kV 18 Insulation level i) Power Frequency with Stand Voltage ii) Impulse withstand Voltage Minimum clearance between phases Minimum clearance between phase to earth Minimum Ground clearance (from bottom most live part to plinth level) 19 Minimum clearance from bottom support insulator to plinth level 16 17 20 21 22 3 (3 Phase Ganged Unit) Outdoor 33 36 Solidly earthed system 36 1250 50 25 kV RMS kV Peak mm mm 70 170 320 320 mm 4000 of mm 2500 i) Minimum Creepage Distance (Total) mm ii) Minimum Creepage Distance mm (Protected) Arcing horn Operating mechanism: a) Type b) Rated 3 Phase, 50Hz Voltage for Drive V Motor .c) Rated voltage of Shunt trip coil & V. DC operating range d) Rated voltage of Closing coil & V. DC 900 460 Yes Spring Charged 415 220 or 110 [50% 110%] 220 or 132 [80% - Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 89 Technical Specification operating range e) No. of trip coils f) No. of closing coils g) No of spare auxiliary contacts & contact rating No No Nos AMPS h) Minimum thickness of sheet steel for mm control cabinet i) Enclosure Protection Reclosing 23 24 Support structure (Painted / Galvanised) 25 All other parts (Painted / Galvanised) 26 Minimum size of control wiring (Copper) Sq. mm 110%] 2 per CB 1 per CB 10 N/O+10 N/C (per CB) 10 A at 240V AC & 2A at 220V/ 110V DC 3 IP55 Three Phase auto reclosing Galvanised Synthetic enamel shade 631 of IS5 (125 microns) 2.5 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 90 Technical Specification 2.16 TECHNICAL SPECIFICATION FOR 33 KV CONTROL AND RELAY PANELS FOR TRANSFORMERS & FEEDERS 1.0 SCOPE 1.1. This specification provides for design, engineering, manufacture, assembly, shop testing, inspection and testing at works, transport to site, insurance, storage, erection and commissioning of Control, Relay, Alarm and Annunciation Panels for 33/11 KV, Substations. 1.2. It is not the intent to specify completely herein all details of the design and construction of equipments. However, the equipment shall conform in all respects to high standards of engineering, design and workmanship and shall be capable of performing in continuous commercial operation acceptable to the purchaser, who will interpret in a manner the meanings of drawings and specifications and shall have the power to reject any material which in his judgment is not in accordance therewith. The equipment offered shall be complete with all components necessary for its effective and trouble free operation. Such components shall be deemed to be within the scope of Bidder's supply, irrespective of whether these are specifically brought out in this specification and/or the commercial order or not. 1.3. It may be noted that the Control & Relay Panels must meet the following minimum criteria. Failure to comply with the requirements may results in rejection of the BID as non-responsive: 1.3.1. The Manufacturer must have designed, manufactured, type tested and supplied Control 7 Relay Panels in at least two power utilities of similar rating which are in successful operation for at least 5 (Five) years as on the date of bid opening. Which should be substantiated by furnishing performance report by the official of the rank of minimum DGM/SE 2.0 STANDARDS All equipment provided under this specification shall in general conform to the latest revision/amendment etc. of the following: Sl No. 1 4 Standard IS: 3231, IEC 255 Part-I to III, BS: 89 IS: 1248; IS: 2419; BS: 89 IS-13010; IS: 722(Part-I to IX) IEC 521; BS 3T IS: 4237 5 IS: 375 6 7 IS: 8686, IEC-255 Part V &VI IEC 801-4 IEC 337; IEC: 337-1; IS: 6875 8. IS: 2516 9 10 11 IS: 4047 IS: 2208 IS: 2705; IEC-185 2 3 Title Electrical relays for power system protection. Indicating instruments Energy meters General requirement of switchgear and control gear for voltages not exceeding 1 KV Marking arrangement for switchgear, busbars, main connection & auxiliary wiring. Specification for static protective relays and tests Control switches ( LV switching devices for control and auxiliary circuits) MCCB sand load break switches having a break capacity of 30 KVA rms at 415 V. Fuse switching units HRC fuse links Current transformers Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 91 Technical Specification 12 13 IS: 3156; IEC: 186 IS: 8623 14 IEC: 439 15 IS: 4237 16 IS: 2147 17 18 IS: 5028 IS: 1897 19 20 IS: 3618; IS : 6005 IS: 4064 21 22 IS: 9224 Part II IS: 5578 23 IS: 2032 24 IEC 25 ISO 26 IS Potential transformers Factory built assemblies of switchgear & control gear for voltages upto & including 1000V AC & 1200 V DC Low voltage switchgear and control gear assemblies General requirement of switchgear & control gear for voltages not exceeding 1000V Degree of protection provided by enclosures for low voltage switchgear and control gear Aluminium alloy bars Copper strips for electrical purpose Code of practice for phosphate Air break switches, air break disconnectors, air break disconnectors & fuse combination units for voltages not exceeding 1000 V AC or 1200 V DC. HRC cartridge fuses Guide for making of insulated conductors Graphical symbols Ref-abbreviations Name and Address Institution Electro Technical Bureau. Central dale commission Electro Technique International. 1. Rue de vermbe Geneva Switzerland International Organization for standardization. Danish Board of Standardization..Danish Standardizating Sruat Aurehoeqvaj-12 DK- 2990, Heel prup Denmark Bureau of Indian Standard Standards Manak Bhawan 9, Bahadur Shah Zafar Marg, New Delhi- 110 002, India. 2.1. Equipment meeting with the requirements of other authoritative Standards, which ensure equal or better performance than the standards mentioned above, shall also be considered. When the equipment offered by the Bidder conforms to other standards, salient points of difference between standards adopted and the standard specified in this specification shall be clearly brought out in the relevant schedule. Four copies of such standards with authentic translation in English shall be furnished along with the offer. 3.0 CLIMATIC CONDITIONS 3.1. The climatic and isoceraunic conditions at site under which the equipments shall operate satisfactorily under the tropical conditions specified in this bidding documents. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 92 Technical Specification 3.2. The reference ambient temperature assumed for the purpose of this specification are as follows: i. Maximum ambient temperature ii. Maximum average daily ambient temperature iii. Maximum average yearly ambient temperature : 40° C : 35° C : 30° C 4.0 PRINCIPAL PARAMETERS 4.1. The details of Current Transformer are given below: Core No. 1 2 3 Accuracy Burden class Minimum knee Purpose point voltage as per Formula 33 KV side Transformer CT Ratio: 200-100/5-5-5 A 5 P 20 20 VA ----O/L & E/F Protection PS ---Min. Vk = 100 V Transformer Max. Im= 0.03 A differential protection accuracy 15 VA -----Metering 0.5, Instrume nt security factor < 5 33 KV side Feeder CTs Ratio: 400-200/5-5 A 11 KV side Transformer CT Ratio: 600-300/5-5 -2.89 A 1 2 5 P 10 PS 20 VA ---- 3 Accuracy 0.5 15 VA ---Min. Vk = 200 V Max. Im= 0.03 A ------ O/L & E/F Protection Transformer differential protection Metering 11 KV side Feeder CT Ratio: 400-200/5-5 A 4.2. Breakers for HV & LV sides of transformer HV side breaker : VCB, Outdoor LV (11KV ) side breaker : Vacuum type, Indoor/Outdoor Rating of closing coil & Trip coil : 110 V DC, Number of auxiliary contact : 6 N/O and 6 N/C Both HV & LV breakers are provided with two sets of trip coils( Each set common to all three phases) 5.0 Drawing, Manuals, Literatures etc. 5.1. The tenderer shall furnish along with his tender fully dimensioned drawings of the equipments offered, along with illustrated and descriptive literatures, for various component parts like relays, meters, control switches etc. to enable the purchaser for proper evaluation of the offer. The tenders shall also be accompanied with the schematic drawings showing protection, indicating metering schemes etc 5.2. Soon after the award of the contract and before proceeding with the manufacturing works, the successful tenderer shall furnish drawings in quadruplicate which shall include but not limited to the followings for approval of the purchaser: i) Principal layout drawings for the Boards showing the equipments on the panels with dimensions. A list of the equipments mounted on each panel shall be Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 93 Technical Specification prepared and tabulated in the same drawings. The drawings shall also show the constructional details, foundation details indicating foundation bolts, cable entries etc. ii) Elementary control drawings and other schematics for the equipments furnished, including protection, metering, annunciating and indicating circuit, breaker control ,circuits etc. All wires terminals shall be clearly marked and numbered as per general practice. iii) Single line and three line diagrams showing all AC and D.C power connections and all secondary connectors for relays, meters etc. iv) Internal wiring diagrams of all the panels and boards giving internal wiring connections for all the equipments in the panels. The drawings shall also clearly indicate the connections to be made at site or to the external equipments or between boards etc. with wires terminals marked properly. v) After approval of the drawings the tenderer shall furnish six copies of the each of the final drawings along with the literatures, instruction manuals etc. for purchaser's reference. 5.3. In addition to the above the successful bidders shall supply three sets each of the following relevant equipments supplied to each substation: a. All final drawings mentioned above. b. Literature describing construction, operation, adjustment, testing, calibration, maintenance of all protective and auxiliary relays, instruments, control switches etc. c. List of spare parts giving identification numbers of the parts. 6.0 GENERAL TECHNICAL REQUIREMENT 6.1. Control & Relay panels: Detailed Description The control and relay panels shall be of Simplex type. Each Simplex panel shall consist of a vertical front panel with equipment mounted thereon and having wiring access from the rear. It shall have double leaf door with lift off hinges at the back for panels of width more than 800 mm. Doors shall have handles with built-in locking facility. 7.0 Constructional Features 7.1. Panels shall be completely metal enclosed and shall be dust, moisture and vermin proof. The enclosure shall provide a degree of protection not less than IP-51 in accordance with IS:2147. 7.2. Panels shall be free standing, floor mounting type and shall comprise structural frames enclosed completely with specially selected smooth finished, cold rolled sheet steel of thickness not less than 3 mm for weight bearing members of the panels such as bass frame, front sheet and door frames, and 2.0 mm for sides, door top and bottom portions. There shall be sufficient reinforcement' to provide level Surface resistance to vibration and rigidity during transportation and installation. 7.3. All doors, removable covers and panels shall be gaskets all around with neoprene gaskets. Ventilation louvers to be provided having screens and filters. The screens shall be made of brass wire mesh. 7.4. Design, materials selection and workmanship shall be such as to result in neat appearance inside and outside with no welds, rivets or bolt head apparent from outside, with all exterior surfaces true and smooth. 7.5. All necessary anchor bolts and other materials required for foundation of panels shall be supplied 7.6. Cable entries to the panel shall be from the bottom. The plates of the panel shall be fitted with removable gland plates for fixing the cable glands. Necessary number of cable glands of sizes to suit owner's external cables to the panels shall be supplied by the bidder. Cable glands shall be screwed type, and shall be suitable for PVC cables. Cable gland plate fitted in the Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 94 Technical Specification bottom of the panel shall be connected to the earthing Panel / Station through a flexible braided copper conductor rigidly. 7.7. Relay panels of modern, modular construction would also be acceptable. 7.8. The total height of the panel shall be 2250 mm. The depth of the panel shall be 600 mm. The panels shall have suitable width required for mounting of all the equipments on the front panel. 7.9. The panels shall match with the existing panels in APDCL substations, the details of which will be furnished to the successful bidder. Matching includes height , depth of the panels, colour matching and mimic matching' and arrangement of equipment on the front. 8.0 Mounting 8.1. All equipment on and in panels shall be mounted and completely wired to the terminal blocks ready for external connection. The equipment on front of panel shall be mounted flush. 8.2. Equipment shall be mounted such that removal and replacement can be accomplished individually without interruption of service to adjacent devices and are readily accessible without use of special tools. Terminal marking shall be clearly visible. 8.3. The contractor shall carry out cutouts, mounting and wiring of the free issue items supplied by others, if any which are to be mounted in this panel in accordance with the corresponding equipment manufacturer's drawings. Cutouts if any, provided for future mounting of equipment shall be properly blanked off. 8.4. The center lines of switches, push buttons and indicating lamps shall be not less than 750 mm from the bottom of the panel. The center lines of relays, meters and recorders shall be not less than 450 mm from the bottom of the panel. 8.5. The center lines of switches, push buttons and indicating lamps shall be matched to give a neat and uniform appearance. Likewise the top lines of all meters, relays and recorders etc., shall be matched. 8.6. No equipment shall be mounted on the doors. 8.7. All the equipment connections and cabling shall be designed and arranged to minimize the risk of fire and damage which may be caused by fire. 9.0 Panel Internal Wiring and Other Accessory Equipment 9.1. Panels shall be supplied completely. with interconnecting wiring provided between all electrical devices mounted and wired in the panels and between the devices and terminal blocks for the devices to be connected to equipment outside the panels. When panels are arranged to be located adjacent to each other all inter panel wiring and connections between the panels shall be furnished and the wiring shall be carried out internally. These adjacent inter panel wiring shall be clearly indicated in the drawing furnished by the contractor. 9.2. All wiring shall be carried out with 1100 V grade, single core, stranded copper conductor wires with PVC insulation and shall be heat resistant grade and vermin and rodent proof. The minimum size of the stranded copper conductor used for internal wiring shall be as follows: i) All circuits except current transformer and potential transformer circuits one multi strand 2.5 Sq. mm per lead ii) Current transformer circuit : one 4.0 Sq. mm per lead. The minimum number of strands per conductor shall be three. 9.3. All internal wiring shall be securely supported, neatly arranged, readily accessible and connected to equipment terminals and terminal blocks. Wiring gutters and troughs shall be used for this purpose. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 95 Technical Specification 9.4. Auxiliary bus wiring for AC and DC supplies, voltage transformer circuits, annunciation circuits and other common services shall be provided near the top of the panels running throughout the entire length of the panels. 9.5. Wire termination shall be made with solder less crimping type and tinned copper ring type lugs which firmly grip the conductor and insulation. Insulted sleeves shall be provided at all the wire terminations. Engraved core identification plastic ferrules marked to correspond with panel wiring diagram shall be fitted at both ends of each wire. Ferrules shall fit tightly on the wire and shall not fall off when the wire is disconnected from terminal blocks 9.6. All wires directly connected to trip circuit of breaker or device shall be distinguished by the addition or red coloured unlettered ferrule. Number 6 and 9 shall not be included for ferrule purposes. 9.7. Longitudinal troughs extending throughout the full length of the panel shall be preferred for inter panel wiring. Interconnections to adjacent panel shall be brought out to a separate set of terminal blocks located near the slots or holes meant for taking the inter connecting wires. Arrangements shall permit easy inter connections to adjacent panels at site and wires for this purposes shall be provided by contractor looped and bunched properly inside the panel. 9.8. The Successful bidder shall be solely responsible for the completeness and correctness of the internal wiring and for the proper functioning of the connected equipment. 10.0 Terminal Blocks 10.1. All internal wiring to be connected to the external equipment shall terminate on terminal blocks preferably vertically mounted on the side of each panel. Terminal blocks shall be 1100 V grade and have 10 amps continuous rating ,complete with insulated barriers, stud type terminals, washers, nuts and lock nuts. Terminal block design shall include a white fibre markings strip with clear plastic slip-on terminal covers. Markings on the terminal strips shall correspond to wire number and terminal numbers on the wiring diagrams. 10.2. Terminal blocks for current transformer and voltage transformer secondary leads shall be provided with test links and isolating facilities. Also current transformer secondary leads shall be provided with short-circuiting and earthing facilities. 10.3. At- least 20 % spare terminals shall be provided on each panel and these spare terminals shall be uniformly distributed on all terminal blocks. 10.4. Unless otherwise specified. terminal blocks shall be suitable for connecting the following conductors of purchasers cable on each side i. ii. All circuits except current and potential transformer circuits : minimum of one of 2.5 sq.mm copper. All CT and PT circuits: minimum of two of 4.0 mm square copper. 10.5. There shall be a minimum clearance of 250 mm between the first row of terminal blocks and associated cable gland plate. Also the clearance between two rows of terminal blocks shall be minimum, of 150 mm. 10.6. Arrangement of the terminal block assembles and the wiring channel within the enclosure shall be such that a row of terminal blocks is run parallel and in close proximity along each side of wiring duct to provide for convenient attachment of internal panel wiring. The side of the terminal block opposite the wiring duct shall be reserved for purchaser's external cable connection. An adjacent terminal block shall also share this fired wiring corridor. A steel strip shall be connected between adjacent terminal block rows at 450 mm intervals for support of incoming cables. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 96 Technical Specification 10.7. The number and sizes of the Purchaser's multi-core incoming cable will be furnished to the Contractor after placement of the order. All necessary cable terminating accessories such as gland plates, packing glands, crimp type tinned copper lugs supporting clamps .and brackets, wiring troughs and gutters etc., for purchaser's cable shall be included in contractor's scope of supply. 11.0 Painting 11.1. All sheet steel work shall be phosphated, in accordance with the 18:6005 "Code of Practice for phosphating iron and steel". Oil, grease, dirt and sweat shall be thoroughly removed by emulsion cleaning. Rust and scale shall be removed by picking with dilute acid followed by washing with running water rinsing with a slightly alkaline hot water and drying. 11.2. After phosphating thorough rinsing shall be carried out with clear water followed by final rinsing with dilute dichromate solution and oven drying. The phosphate coating shall be sealed with application of two coats of ready mixed, stoved type zinc chromate primer. The first coat may be "flash dried" while the second coat shall be stoved . 11.3. After application of the primer, two coats of finishing synthetic enamel paint shall be applied, each coat followed by stoving. The second finishing coat shall be applied after completion of tests. The exterior Colour of the paint shall be selected by the purchaser at a later date. 11.4. Each coat of primer and finished paint shall be of a slightly different shade to enable inspection of the painting. The powder coat paint shade should Air Craft Grey (IS : 5) and thickness of 50-60 microns. A small quantity of finished paint shall be supplied for minor touching up required at site after installation of the panels. 11.5. In case the bidder proposes to follow any other established painting procedure like electrostatic painting, the procedure shall be submitted along with offer/bid for purchaser's review and approval. 12.0 Mimic Diagram 12.1. Coloured mimic diagram and symbols showing the exact representation of the system shall be provided in the front of control panels. 12.2. Mimic diagram shall be made preferably of anodized aluminum or plastic of approved fast Colour material which shall be screwed on to the panel and can be easily cleaned. Painted overlaid mimic is also acceptable. The mimic bus shall be 2 mm thick. The width of the mimic bus shall be 10 mm for bus bars and 7 mm for other connections. 12.3. Mimic bus Colour will be decided by the Purchaser and shall be obtained from the Purchaser by the successful Bidder. 12.4. When semaphore indicators are used for isolator position they shall be so mounted in the mimic that the isolator closed position shall complete the continuity of mimic. 12.5. Indicating lamp, one for each phase for each bus shall be provided on the mimic to indicate bus charged condition. 13.0 Name Plates and Markings 13.1. All equipment mounted on front and rear side as well as equipment mounted inside the panels shall be provided with individual nameplates with equipment designation engraved. Also on the top of each panel, on front as well as rear side, large and bold nameplates shall be provided for circuit/feeder designation. 13.2. AlI front mounted equipment shall be also provided at the rear with individual name plates engraved with tap numbers corresponding to the one shown in the panel internal wiring to facilitate easy tracing of the wiring. The nameplates shall be mounted directly by the side of the respective Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 97 Technical Specification equipment in a visible manner and shall not be hidden by the equipment wiring. 13.3. Nameplates shall be made of non-rusting metal or any other suitable material. Nameplates shall be black with white engraving lettering. The nameplates inscription and size of nameplates and letters shall be submitted to the purchaser for approval. 13.4. Each instrument and meter shall be prominently marked with the quantity measured e.g. kV, A, MW, etc. All relays and other devices shall be clearly marked with manufacturer's name, manufacturer's type, serial number and electrical rating data. 13.5. Each switch shall bear clear inscription, identifying its function e.g. "BREAKER" ,"52 A‘‘, "AMMETER" etc. Similar inscriptions shall also be provided on each device whose function is not otherwise identified. If any switch device does not bear this inscription separate name plate giving its function shall be provided for it. Switch shall also have clear inscription for each position indicating e.g. "TRIP-NEUTRAL-CLOSE", "ON-OFF", "R-Y-BN:-OFF", etc. 14.0 Miscellaneous Accessories and Supporting Steel 14.1. Plug point- An AC 240 Volts, single phase, 5A, 50 HZ AC plug point shall be provided in the interior of each cubicle with "ON-OFF" Switch for connection of hand lamps. 14.2. Interior lighting: Each panel shall be provided with a CFL lighting fixture rated for 240 volts, single phase, 50 HZ supply for the interior illumination of the panel during maintenance. The fittings shall be complete with switch fuse unit and switching of the lighting shall be controlled by the respective panel door switch. 14.3. One DC emergency lamp is to be fitted and should be complete with switch fuse unit. 14.4. Each control panel shall be provided with necessary arrangements for receiving, distributing, isolating and fusing of DC and AC supplies for various control signaling, lighting and space heater circuits. MCBs for the incoming circuits and fuses for sub-circuits shall be provided. Selection of the main and sub-circuit fuse rating shall be such as to ensure selective clearance of sub-circuit faults. Potential circuit for relaying and metering shall be protected by fuses. All fuses shall be HRC cartridge type conforming to IS : 2208 mounted on plug-in type fuse bases. All accessible live connection to fuse bases shall be adequately shrouded. Fuses shall have operation indicators for indicating blown fuse condition. Fuse carrier base shall have imprints of the fuse rating and voltage. 14.5. Supporting Steel: All necessary foundation anchor bolts and other parts of supporting and fastenings, of the panels shall be supplied by the contractor. 15.0 Earthing 15.1. All panels shall be equipped with an earth bus securely screwed. Location of earth bus shall ensure no radiation interference for earth systems under various switching conditions of isolators and breakers. The material and the sizes of the bus bar shall be at least 25 x 6 mm copper flat. 15.2. When several panels are mounted adjoining each other, the earth bus shall be made continuous and necessary connectors and clamps for this purpose shall be included in the scope of supply of contractor. Provision shall be made for extending the earth bus bars to future adjoining panels on either side. 15.3. Provision shall be made on each earth bus bars of the end panels for connecting purchaser's earthing grid. Necessary terminal clamps and connectors for this purpose shall be included in the scope of supply of Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 98 Technical Specification contractor. The wire or screens should be clearly bonded and earthed at the gland plate. 15.4. All metallic cases of relays, instruments and panel mounted equipment shall be connected to the earth bus preferably by independent copper wires of size not less than 2.5 Sq.mm. The colour code of earthing wires shall be green. Earthing wire shall be connected on terminals with suitable clamp connectors and soldering shall not be permitted. 15.5. Looping of earth connections which would result in loss of earth connection to other devices where the loop is broken shall not be permitted. However, looping of earth connections between equipment to provide alternative paths to earth bus shall be provided. 15.6. VT and CT secondary neutral or common lead shall be earthed at one place only at the terminal blocks where they enter the panel. Such earthing shall be made through links so that earthing may be removed from one group without disturbing continuity of earthing system for other groups. 16.0 Metering Instruments: Instruments and Meters 16.1. All instruments, meters, recorders and transducers shall be enclosed in dust proof, moisture resistant, black finished cases and shall be suitable for tropical use. They shall be calibrated to read directly the primary quantities. They shall be accurately adjusted and calibrated at works and shall have means of calibration, check and adjustment at site. All accessories including test switches and test plugs, where applicable shall be furnished. Their elements shall be shock resistant and shielded from external magnetic fields. 16.2. . Ammeters: 16.2.1. All ammeters shall be of analouge circular dial type and provided with direct reading triple range scale. Scale value of ammeters shall be equal to 1 to 1.3 times the rated primary current of the associated current transformer feeding it. The rated current shall be 5.0 Amp. Accurate reading of ammeter shall be possible at the lowest limit of 5 % of the rated current. Accuracy class 1.0 or better as per IS: 1248 16.3. Voltmeter: 16.3.1. All voltmeters shall be of analouge circular dial type . The maximum scale value of voltmeters shall be 50% in excess of the primary voltage of the associated PTs. The rated voltage of the voltmeter shall be 110 volts A.C., accuracy class 1.0 or better as per IS: 1248. 16.4. Watt meters 16.4.1. Analouge circular dial type watt meters wherever specified shall be 3 phase, 4 wire three element type provided with direct reading scales. The scale values of wattmeter shall be as per ratio of the measuring cores of respective CTs and PTs. The current coils shall be rated for 5/1 ampere and voltage coils for 110 volt continuous. The wattmeters shall be suitable for circuits with unbalanced loads to be usually met with in commercial service. Accuracy class will be 1.0 or better as per IS: 1248. 16.5. Energy Meters : 16.5.1. Energy meters shall be static type conforming to IEC 687 and suitable for bi-directional power flow. The static meter shall measure active and reactive energy both import and export, by 3 phases 4 wire principle suitable for ba1anced / unbalanced 3 phase load. Accuracy of meter shall. be 0.5for active energy and 0.5 for reactive energy. THE METER SHALL BE OF CATEGORY-A with DLMS protocol having RS 485 /232 & Optical ports as per detail APDCL Specification. Each meter shall have a unique identification code provided by purchaser and shall be marked permanently on the front and also on the non-volatile memory. The voltage monitoring of all the three voltages shall be provided. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 99 Technical Specification 16.5.2. The meter shall normally operate with power drawn from VT supplies. Power supply to the meter shall be healthy even with a single phase VT supply. An automatic back up shall be provided by a built in life time battery and shall not need replacement for at least ten years with a continuous VT interruption of even two years. Date and time of VT interruption and restoration shall be automatically stored in non-volatile memory. 16.5.3. The meter shall have an optical port at the front of the meter for data collection by a hand held device. The meter shall have means to test MWH accuracy and for connecting it to time of day tariff equipment. 16.5.4. The meter should have optical port for local communication. RS 232 and RS 485 port should be incorporated along with Ethernet port. 16.5.5. The bidder is to provide the software for meter for downloading and up loading to base computer along with one hand held common meter reading instrument along with software. 16.5.6. The meter should preferably be either Secure or L & T make as per APDCL‟s specification with DLMS protocol.For any other make approval is to be obtained. 17.0 Relays: 17.1. All relays shall conform to the requirements of IS:3231 or other applicable approved standards. Relays shall be suitable for flush or semi flush mounting on the front with connections from the rear. Relays shall be rectangular in shape and shall have dust tight, dull' black or egg shall black enamel painted cases with transparent cover removable from the front. 17.2. All protective relays shall be in draw out or plug-in type / modular cases with proper testing facilities. The testing facilities provided on the relays shall be specifically stated in the bid. Necessary test plugs shall be supplied loose and shall be included in Contractor's scope of supply. Test block and switches shall be located immediately below each relay for testing. As an alternative to test block and test plug arrangements the Bidder shall also quote alternative testing facility of protective relays by providing a push button which when pressed connects the testing equipment to the relay coils and injects current in the coil and automatically disconnects the trip circuits and on operation of relay gives a signal that the equipment and the circuits are correct. 17.3. The purchaser reserves the right for accepting anyone of the above two testing facilities. Unless otherwise specified all auxiliary relays and timers shall be supplied in non-draw out cases/plug in type modular cases. 17.4. All AC relays shall be suitable for operation at 50 Hz AC Voltage operated relays shall be suitable for 110 Volts VT secondaries and current operated relays for 5 Amp CT secondaries as specified in this specification. DC auxiliary relays and timers shall be designed for 110 V DC voltage and shall operate satisfactorily between 70 % and 110% of rated voltage. Voltage operated relays shall have adequate thermal capacity for continuous operation. 17.5. The protective relays shall be suitable for efficient and reliable operation of the protection scheme described in the specification. Necessary auxiliary relays and timers required for interlocking schemes for multiplying of contacts/suiting contact duties of protective relays and monitoring of control supplies and circuits, lockout relay monitoring of circuits etc., and also required for the complete protection schemes described in the specification shall be provided. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 100 Technical Specification 17.6. All protective relays shall be provided with at least two pairs of potential free isolated output contacts. Auxiliary relays and timers shall have pairs of contacts as required to complete the scheme. Contacts shall be silver faced with spring action. Relay cases shall have adequate number of terminals for making potential free external connections to the relay coils and contacts including spare contacts. Relay case size shall be so chosen as not to introduce any limitations on the use of available contacts on the relay due to in-adequacy of terminals. Paralleling of contacts, if any, shall be done at the terminals on the casing of the relay. 17.7. All protective relays, auxiliary relays and timers except the lock out relays and interlocking relays specified shall be provided with self-reset type contacts. All protective relays and timers shall be provided with externally hand reset positive action operation indicators, provided with inscription, subject to purchaser's approval. All protective relays which do not have built in hand reset operation indicators shall have additional auxiliary relays with operating indicators for this purpose. Similar separate operating indicator (auxiliary relays) shall also be provided in the trip circuits of protections located outside the board such as bucholz relays, temperature protection, fire protection. etc., 17.8. Timers shall be done of the electromagnetic or solid state type. Pneumatic timers are not acceptable. Short time delays in terms of milliseconds may be obtained by using copper slugs on auxiliary relays. In such case it shall be ensured that the continuous rating of the relay is not affected. Time delay in terms of milliseconds obtained by the external capacitor resistor combination is not acceptable. 17.9. No control relay which shall trip the power circuit breaker when the relay is de-energized shall be employed in the circuits. 17.10. Provision shall be made for easy isolation of trip circuits of each relay for the purpose of testing and maintenance. 17.11. All relays shall withstand a test voltage 2.5 kVrms voltage,50Hz for one second. 17.12. Auxiliary seal-in-units provided on the protective relays shall preferably be of shunt reinforcement type. If series relays are used the following, shall be strictly ensured: i. The operating time of the series seal-in-unit shall be sufficiently shorter than that of the trip coil or trip relay in series with which it operates to ensure definite operation of the flag indicator of the relay. ii. Seal-in-unit shall obtain adequate current for operation when one or more relays operate simultaneously. iii. Impedance of the seal-in-unit shall be small enough to permit satisfactory operation of the trip coil on trip relays when the DC supply voltage is minimum. 17.13. All protective relays and alarm relays shall be provided with one extra isolated pair of contacts wired to terminals exclusively for purchaser's use. 17.14. For numeric relays the following requirements shall be met with : 17.14.1. Numerical relay shall have both RS 485 and RS 232 communication ports. And ten numbers digital IO. Relay software is required. 17.14.2. The numerical relays shall be completely numerical with protection elements realized using software algorithm. 17.14.3. The relay should have high immunity to electrical and electromagnetic interference. Relay should confirm to following mandatory type test for safe operation of relay : a. b. High frequency disturbance test as per IEC 610 – 4-1 Fast transient disturbance test as per IEC 61000 – 4-4 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 101 Technical Specification c. d. e. 18.0 Electrostatic discharge as per IEC 61000 – 4-2 Radio frequency interference as per ANSI C 37.90.2 Impulse test as per IEC 6100 – 4-3 Annunciation System: 18.1. Alarm annunciation system shall be provided for the control board by means of visual and audible alarm in order to draw the attention of the operator to the abnormal operating conditions or the operation of some protective devices. The annunciation equipment shall be suitable for operation with 110 V DC voltage. 18.2. The visual annunciation shall be provided by annunciation facia, mounted flush on the top of the panels. The audible alarm shall be provided by alarm buzzer and bell for trip and non-trip alarm respectively. 18.3. The annunciator fascia shall be provided with translucent plastic window for alarm point with minimum size of 35 mm x 50 mm. The facia plates shall be engraved in black lettering with respective inscriptions which will be furnished to the Bidder by the purchaser. Alarm inscriptions shall be engraved on each window in not more than three lines and size of the let6tering shall not be less than 5 mm. 18.4. Each annunciation window shall be provided with two white lamps in parallel to provide safety against lamp failure. Long life lamps shall be used. The lamp circuit shall include series resistor of adequate rating. The cover plate of the facia windows shall be flush with the panel and shall be capable of easy removal to facilitate replacement of lamps. The transparency of cover plates and wattage of the lamps provided in the facia windows shall be adequate to ensure clears visibility of the inscriptions in the control room having high illumination intensity (500 lux) from the location of the operator's desk. 18.5. TRIP AND NONTRIP facia shall be differentiated. All TRIP facia shall have red colour and all NONTRIP facia shall have white colour. Sl. No. 1 2 3 4 5 Alarm condition Fault contact Open Close Close open Close Visual Annunciation Off Flashing Steady on Steady on On Audible Annunciation Off on Off Off Off Normal Abnormal Acknowledge push button is pressed Reset push button is pressed Lamp test push button pressed Open Steady on Off 18.6. Visual and audible annunciation for the failure of DC supply to the annunciation system shall also be provided and this annunciation shall operate on 240 volts AC supply with separate fuses. On failure of the power supply to the annunciation system for more than 3 seconds (adjustable setting) an indicating lamp shall light up and a bell shall sound. A separate push button shall be provided for cancellation of this audible alarm alone but the indicating lamp shall remain steadily lighted till the supply to the annunciation system is restored. The sound of the audible alarm (bell) provided for this annunciation shall be different from the audible alarm provided for this annunciation system. 18.7. A separate voltage check relay shall be provided to monitor the failure of supply (240 V AC) to the scheme mentioned above. If the failure of supply exists for more than 2 to 3 seconds, this relay shall initiate visual and audible Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 102 Technical Specification annunciation. The annunciation system described above shall meet the following additional requirements. 18.8. The annunciation system shall be capable of catering to all simultaneous signals at a time. i) One self resetting push button shall be provided on each panel for testing in fascia window lamps. Push buttons for testing flasher and audible alarm circuit of annunciation supply failure· monitoring shall also be provided. These testing circuits shall be so connected that while test is being done it shall not prevent the registering of any new annunciation that may land during the test. iii) One set each of the following push buttons shall be provided on each panel. a) Reset push button for annunciation system; b) Accept push button for annunciation system. iv) The annunciation shall be repetitive type and shall be capable of registering the fleeting signal. For fault contacts which open on a fault, it shall be possible at site to change annunciators from "close to fault" and vice versa. v) The annunciator shall be suitable for operation with normally open fault contacts which close on a fault. For fault contacts which open a fault, it shall be possible at site to change annunciators from "close to fault" and vice versa. vi) Only electro-magnetic relay type alarm and annunciation relay schemes are acceptable and static type annunciation schemes are not acceptable. Contactors are not acceptable for annunciation system. 19.0 Switches 19.1. Control and Instrument switches shall be rotary operated type with escutcheon plates clearly marked to show operating position and circuit designation plates and suitable for flush mounting with only switch front plate and operating handle projecting out. Handles of different shapes and suitable inscriptions on switches aS per clause 6.8 shall be provided as on aid switch identification. 19.2. The selection of operation handles for the different types of switches shall be as follows: 1 2 3 4 Breaker & isolator switches Selector switches Instrument switches Protection transfer switch Pistol grip, black Oval or knob, black Round, knurled, black Pistol grip, lockable & black 19.3. The control switch of breaker and isolator shall be of spring return to neutral type. The spring return type shall be provided with target which shall indicate the last operation of the switch. The control springs shall be strong and robust enough to prevent inadvertent operation due to light touch. The spring return type switch shall have spring return from close and trip positions to "after close" and "after trip" positions respectively. 19.4. Instrument selection switches shall be of maintained contact (stay put) type. Ammeter selection switches shall make-before-break type contacts so as to prevent open circuiting of CT secondaries when changing the position of the switch. They shall be of 5 position type viz R-Y-B-N-Off. Voltmeter transfer switches for AC shall be suitable for reading all line-to-line and lineto neutral voltages for non-effectively earthed systems and for reading all line to line voltages for effectively earthed systems . 19.5. Lockable type of switches which can be locked in particular positions shall be provided when specified. The key locks shall be fitted on the operating handles. 19.6. The contacts of all switches shall preferably open and close with snap action to minimize arcing. Contacts of switches shall be spring assisted and contact faces shall be with rivets of pure silver. Springs shall be used as current carrying parts. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 103 Technical Specification 19.7. The contact combination and their operation shall be such as to give completeness to the interlock and function of the scheme. The contact rating of the switches shall be as follows: Contact Rating in Amps a) Make and carry continuously b) Make and carry for 0.5 Sec. c) Break i) Resistive load ii) Inductive load with L/R= 40 20.0 110 V DC 10 30 240 V AC 10 30 3 0.2 7 7 Indicating Lamps 20.1. Indicating lamps shall be panel mounting type with rear terminal connections. Lamps shall be of LED type. Lamps shall have translucent lamp covers to diffuse light coloured red, green, amber, dear white or blue as specified. The lamp cover shall be of screwed type, un-breakable and moulded from heat resisting material. 20% of lamps actually used on the boards and 10% of the lamp bases of various colour actually used shall be supplied in excess to serve as spares. 20.2. The wattage and resistance of the lamps shall be as follows: 110 V -5 to 7 W - 1000 to 2000 Ohms 21.0 22.0 20.3. Bulbs and lenses shall be interchangeable and easily replaceable from the front of the panel. Tools, if required for replacing the bulbs and lenses shall also be included in the scope of supply. 20.4. The indicating lamps with resistors shall withstand 120% of rated voltage on a continuous basis. Position Indicators 21.1. Position indicators of 'SEMAPHORE' type shall be provided when specified as part of the mimic diagrams on panels for indicating the position of circuit breakers, isolating/earthing switches etc. The indicator shall be suitable for semi-flush mounting with only the front disc projecting out and with terminal connection from the rear. Their strips shall be of the same colour as the associated mimic. 21.2. Position indicator shall be suitable for either AC or DC operation as specified. When the supervised object is in the closed position, the pointer of the indicator shall take up a position in line with the mimic bus bars, and at right angles to them when the object is in the open position. When the supply failure to the indicator occur the pointer shall take up an intermediate position to indicate the supply failure. The rating of the indicator shall not exceed 2.5 W. 21.3. The position indicators shall withstand 120% of rated voltage on a continuous basis. Trip Circuit Supervision Relays 22.1. Trip circuit shall be supervised by means of relays. The scheme shall continuously monitor each trip coil in both pre-close and post-close of the breaker. The scheme shall detect. i) Failure of DC supply to each trip coil. il) Open circuit of trip circuit wiring and iii) Failure of mechanism to complete the tripping operation. 22.2. Also 2 Nos. indicating lamps to act in conjunction with trip circuit supervision relays for healthy trip indication of 2 sets of trip coils shall be supplied. 22.3. Necessary external resistors for trip circuit supervision relays shall be supplied. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 104 Technical Specification 23.0 Flag Relays Shall Have i) Hand reset flag indication ii) Two elements iii) Have necessary NO/NC contacts for each element/coil to meet scheme requirements. 24.0 Detailed Description of Protections The protection, auxiliary relay and timers and other equipment that are required to be provided are included in the detailed equipment schedule of panels vide Annexure.-I of this specification The detailed description of Back up protection and the associated equipment is described below: The setting ranges of relays given in specification are indicative. The setting ranges of the equipment offered, if different from the ones specified, shall also be acceptable if they met the functional requirements. The bidder shall quote the protection equipment, meeting the following requirements. 33/11 KV, TRANSFORMER a) Differential Protection It shall have i) Triple pole high speed percentage biased differential type. ii) An operating time not more than 30 milli Secs. At 5 times operating current setting of 20%. iii) Three instantaneous high set over current units iv) Second harmonic restraint feature and fifth harmonic by pass/restraint feature and also be stable under normal over fluxing conditions. v) an operating current setting of 20% or less, vi) Suitable for rated current of 5A and 1 Ampere vii) Adjustable bias setting range of 20% to 50% viii) Two bias windings per phase ix) Stable on heavy through faults x) Include necessary separate interposing CTs for angle and ratio correction or have internal features in the relay to take care of angle and ratio correction. xi) Shall be of numerical type. a) b) c) d) e) f) b) Over current and earth fault protection for transformer The relay should be triple pole non-directional with IDMT characteristics. It should either be numeric or electromagnet type, however offer for Areva make Micom series of relay will be preferred. c) Auxiliary relays for transformer protection devices Auxiliary relay required for bucholtz trip and alarm, HV winding temperature trip & alarm, LV winding temperature trip & alarm, oil temperature alarm & trip and low oil level alarm, PRV trip, shall be provided. Each auxiliary relay shall have 2 pairs of contacts and one hand reset flag indicators. The auxiliary relays may be of non-draw out type d) Inter Tripping Relays 1 No. inter trip relay to trip HV and LV breakers of the transformer and to isolate the transformer from supply shall be supplied. The inter trip relay shall be of high speed and shall be provided with hand reset operation indicator and 4 NO + 2 N/C hand reset contacts for 33 KV breaker and 13 NO + 3 N/C hand reset contacts for 11 KV breaker. The protection scheme shall function as follows: Differential relays operated: both HV, and LV breakers trip. OIC & E/F on HV operated: both H.V and LV breakers trip. Buchholz Relay Operated: both HV & L.V. breakers trip. Winding temperature trip contact closed: both HV & LV. breakers trip. Oil temperature - alarm only. PRV Operated: both HV & L.V. breakers trip. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 105 Technical Specification 24.1. Relay and Control Panels for 33 kV Feeders Following meters, relays etc shall be provided in the feeder panel, However. any other items which are not specifically mentioned in this specification but are required to complete the scheme and for satisfactory operation of scheme shall also be deemed to be included in this specification. 1) PROTECTIVE RELAYS: Over current relay 2 Nos Earth fault relay 1 No Relays for OIC and E/F protection shall I. be of numeric non-directional type II. be of triple pole type with two outer elements for O/C and the other forE/F protection. b III. a) b) c) d) a) b) c) d) a) b) c) d) e) 25.0 e with IDMT characteristics with a definite minimum time of 3 sec at 10 times settings. IV. have a variable setting range of 50-200% for over current and 20-80% for earch fault. V. be rated for 5/1 ampere VI. include hand reset flag indicator 2) INSTRUMENTS AND METERS Following meters and instruments shall be provided in the panel: One no. Ammeter Digital Type One no. Voltmeter Digital Type One no Watt meter of digital type Electronic Trivector meter ( as per specification) 3) CONTROLS Following control switches shall be provided in the panel: One no., three position (i.e. trip-neutral-close) breaker control switch. One no. Ammeter- selector switch. Push button for trip circuit healthy indication. Selector switch for voltmeter 4) INDICATION AND ALARMS Following indicating arrangement shall be provided in the feeder panel: Indicating lamps for CB ON/OFF positions 2 nos. Indicating lamp for TRIP CIRCUIT HEALTHY CONDITION 2 No Indicating lamp labeling Breaker Spring changed 1 No Indicating lamp for Auto-trip indication 1 No. Mimic diagram indicating the relevant position of the single Line diagram of the sub-station incorporating the Semaphore Indicators for circuit breakers Semaphore indicator for Isolators And for Earth switch 1 No. 2 Nos. 1 No. AUXILIARY SUPPLY Auxiliary supplies which shall be made available in substation are as follows: a) A.C. supply 415 V/240 volts, 50Hz three/single phase b) D.C. supply: 110 Volts 26.0 INSPECTION Inspection may be carried out by the purchaser or third party nominee at any stage of manufacture. The supplier shall grant free access to the purchaser's representative or third party nominee at a reasonable time when the work is in progress. Inspection and acceptance of any equipment under this specification by the purchaser shall not relieve the supplier of his obligation of furnishing equipment in accordance with the specification and shall not prevent subsequent rejection if the equipment is found defective. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 106 Technical Specification 3.4 TECHNICAL SPECIFICATION FOR 11 kV VACUUM CIRCUIT BREAKER (OUTDOOR). 1.0 SCOPE :1.1. This specification covers design, manufacturing, testing, of 11 KV Porcelain Clad Vacuum Circuit Breakers complete with all accessories required for its satisfactory operation for the Sub T transmission solidly grounded system. The Breaker shall be used for Feeder Control/ protection in the system. 1.2. It may be noted that the 11 KV Outdoor Vacuum Circuit Breaker must meet the following minimum criteria. Failure to comply with the requirements may results in rejection of the BID as non-responsive: 1.2.1. The Manufacturer must have designed, manufactured, type tested and supplied 11 KV Outdoor Vacuum Circuit Breaker in at least two power utilities of similar rating which are in successful operation for at least 5 (Five) years as on the date of bid opening. Which should be substantiated by furnishing performance report by the official of the rank of minimum DGM/SE 2.0 TYPE AND RATING :2.1. The circuit breaker shall be suitable for outdoor operation under the climatic conditions as specified in Tender Specification without any protection from sun and rain. The 11 KV circuit breakers shall have the following rating:- SN 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. Particulars Number of Poles Nominal System Voltage Highest System Voltage Frequency Interrupting capacity at nominal system voltage Rated continuous Current Short Circuit current Lightning Impulse Voltage One min power frequency withstand voltage Total break-time for any current up to the rated breaking current Control Circuit Voltage Operating Duty for gang operation Values 3 11kV 12kV 50 Hz 500MVA 630A 25kA for 3 sec 75 kVp 28kV rms 5 cycles 110Volt DC O-0.3sec.-CO-3 CO min- Minimum Clearances a) Phase to Phase b) Phase to Earth c) Live part to ground Minimum Creepage distance 280mm 190mm 2750mm 300mm 2.2. The above is minimum requirement. The suppliers may offer their standard design keeping in view the minimum requirements. 2.3. The circuit breakers shall comply with the requirements of IS:13118(1991) or IEC 62271-100 with latest amendment thereof 3.0 VACUUM INTERRUPTER 3.1. The design of the vacuum interrupter shall be such that it gives trouble free operation under normal load and fault conditions throughout the life of the equipment. As the efficiency of the breaker depends on the degree of vacuum inside, it has to be ensured by the that manufacturer that the it is maintained consistently during service. To know the residual life of vacuum interrupter, an indicator/means to indicate status of contact erosion should be provided. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 107 Technical Specification 3.2. Insulating ceramic body of the interrupter should have high mechanical strength and it should be capable of withstanding high temperature without any significant deterioration in its mechanical and electrical properties. 3.3. The metal/alloy used for the fixed and moving contacts shall have very low resistivity and low gas content. They should be resistant to arc erosion and the contact should have no tendency to get cold welded under the high vacuum in the interrupter. 3.4. The interrupter design should ensure rapid de-ionization of the gap so that normal electrical strength of the gap is restored instantaneously. 3.5. The metallic bellow or any other similar vacuum sealing arrangement should be provided at the moving contact and should have a long fatigue life. 3.6. Vacuum interrupter is to be supplied from reputed manufacturer such BEL, CGL, ABB or Areva. 3.7. . Manufacturer‘s catalogue of vacuum bottle, indicating all the details shall essentially be submitted and supporting document to be submitted. 4.0 INSULATION OF THE CIRCUIT BREAKER 4.1. The insulation to ground, the insulation between open contacts and the insulation between phases of the completely assembled circuit breaker shall be capable of withstanding satisfactorily di-electric test voltage corresponding to specified basic insulation level in the standard. 5.0 INSULATORS 5.1. Basic insulation level of the insulator and insulating porcelains shall be as specified and porcelain shall be homogenous and free from cavities and other flaws. They shall be designed to have ample insulation, mechanical strength and rigidity for satisfactory operation under conditions specified above. All insulators of identical ratings shall be inter-changeable. The puncture strength of the insulators shall be greater than the flash over value. 6.0 OPERATING MECHANISM 6.1. The circuit breaker shall be designed for remote control from the control room and in addition there shall be provision for manual operation of circuit breakers during maintenance and for local tripping and closing by normal means. 6.2. The circuit breakers shall have operation counter and mechanical ―open‖ and ―closed‖ indicator, in addition to facilities for remote electrical indication. An operation counter shall also be provided in the common operating mechanism. The mechanical indicator and operation counter shall be located in a position where it shall be visible to a man standing on the ground level with the mechanism housing doors are in closed position. 6.3. The operating mechanism shall be of the spring charging type, by electric control under normal operation. The mechanism shall be trip free electrically and mechanically. Mechanism shall also be capable of performing satisfactorily, the reclosing duty cycles. 6.4. All working parts in the mechanism shall be of corrosion resistant materials and all bearings which require greasing shall be equipped with pressured grease fittings. The mechanism shall be strong, quick in action and removable without disturbing other parts of the circuit breaker. 6.5. Mechanism and breaker shall be such that the failure of any spring will not prevent tripping and will not cause tripping or closing. 6.6. Operating mechanism should be motor operated spring charged type preferably without chain drive. 6.7. Motor for spring charging shall be suitable to perform satisfactorily for input supply voltage of 230V AC 50 Hz with a variation of (+) 10 and (-)20 percent. A.C. motor should have overload protection. 6.8. Provision should also be made for mounting of mechanism box at an adequate height and gear ratios shall be so chosen that one man should be able to charge the spring, without any additional efforts. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 108 Technical Specification 6.9. The mechanical arrangement should be provided to facilitate manual tripping of circuit breaker for emergency trip under emergent condition i.e. failure of DC supply, trip coil burnt, mechanism being defective while arc quenching media is healthy 7.0 MOTORS: 7.1. Motors shall be single phase self-starting induction motor of appropriate capacity for satisfactory operation for the application and duty as required for driving equipment. 7.2. Motors shall be of self ventilated type having TEFC (totally enclosed fan cooled) enclosure. Depending upon the capacity and loading conditions Bidder/manufacturer shall design suitable grease lubricated or oil lubricated bearings for above motors. Bearing shall be so constructed that the loss of grease and its creeping along with shaft into motor housing is prevented. It shall also prevent dirt and water from getting into the motor. 7.3. Continuous motor rating (name plate rating) shall be at least ten (10) percent above the maximum load demand of the driven equipment at design duty point and the motor shall not be overloaded at any operating point of driven equipment that will arise in service. 7.4. Motors shall be capable of giving rated output without reduction in expected life span when operated continuously in the system having the particulars as given in principle parameters. 7.5. All induction motors shall be suitable for full voltage direct-on-line starting. These shall be capable of starting and accelerating to the rated speed along with the driven equipment without exceeding acceptable winding temperature even when supply voltage drops down to 80% of the rated voltage. 8.0 CONTROL CUBICLE 8.1. A common control cubicle shall be provided to house electrical controls, monitoring devices and all other accessories, except those which must be located on individual poles. Cubicle shall be IP-55 of gasketed weather-proof construction, fabricated from sheet steel of minimum 2.5 mm. thickness. The cubicle shall have front access door with lock and keys. Space heater, internal illumination lamp, 3-pin 5A socket with individual ON-OFF switches. 8.2. For local operation following shall be provided: a) LOCAL/REMOTE selector switch b) TRIP/NORMAL/CLOSE control switches with pistol grip handle. 8.3. The control circuits shall be designed to operate on 110 DC and it shall be possible to adopt to work on other voltages by simply changing the operating coils. 8.4. Shunt tripping coils shall be designed to operate satisfactorily within 70% to 110% and shunt closing coil within 85% to 110% of the rated DC voltage. 8.5. AC Power supply for auxiliaries will be available at 230V single phase 50 Hz. 8.6. Necessary cable glands for the cables of the operating mechanism shall be provided. The cables used for operation are un-armoured 2.5 sq. mm. copper control cables of 1100 V grade. Cable glands provided may therefore be suitable for 1 no. 7 core and 2 nos. 4 core unarmoured 2.5 sq. mm. copper control cable. 8.7. Circuit breaker shall be provided with trip free mechanism so that tripping instructions could over-ride the closing instructions. An additional tripping coil shall also be provided in the trip circuit. The second coil shall have separate tripping lever arrangements in the mechanism, so as to avail full advantage of second trip coil. Also the two trip coils shall have separate DC circuits, so that in the event of any short circuit/ damage in any one of the trip coil, supply is available in the other one. 8.8. Circuit diagram of control circuit of VCB along with operating instructions (DO‘S/ DON‘T) shall be embossed on metallic plate duly laminated and the same shall be fixed on the rear door of the control cubicle from inside. 9.0 WIRING 9.1. Wiring shall be completed in all respects to ensure proper functioning of the control, protection, monitoring and interlocking schemes. 9.2. All wiring shall be carried out with 1100V grade PVC insulated stranded copper conductor of 2.5 sq. mm. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 109 Technical Specification 9.3. Each wire shall be identified at both ends with permanent markers bearing wire numbers as per wiring diagram. 9.4. Wire termination shall be done with crimping type connectors with insulating sleeves. Wires shall not be spliced between terminals. 9.5. All spare contacts of auxiliary switches etc. shall be wired up to terminal blocks in the control cubicle. 10.0 TERMINAL BLOCKS 10.1. Terminal blocks shall be of 1100V grade, box clamp type ELMEX 10 sq.mm or approved equivalent. Not more than two wires shall be connected to any terminals. Spare terminals, equal in number to 20% of active terminals, shall be provided. 10.2. Terminal block shall be such located that it allows easy access. Wiring shall be so arranged that individual wires of an external cable can be connected to consecutive terminals. 11.0 TERMINAL CONNECTORS 11.1. All circuit breakers shall be provided with 6 nos. terminal connectors suitable to receive Wolf ACSR/AAA conductors. Clamps shall be designed adequately to take care of any bimetallic effect. Terminal connectors shall be tested for short circuit current capability, temperature rise. 11.2. Terminal connector shall also meet the following requirements: a) Terminal connectors shall be manufactured & tested as per IS:5561. b) All castings shall be free from blow holes, surface blisters, cracks and cavities. All sharp edges and corners shall be blurred and rounded off. c) No part shall be less than 12 mm thick. d) Nuts, bolts & washers used in the current path shall be stainless steel. e) Bimetallic strips/sleeve copper alloy liner of minimum thickness of 2mm shall be cast integral with Aluminum body. f) All current carrying parts shall be designed and manufactured to have minimum contact resistance. g) Terminal connectors should be made of Aluminum Alloy and manufactured by gravity die-casting process only. Sand die-casted connectors are not acceptable. h) Size of terminal connector for which the clamp is designed and also rated current under site conditions shall be embossed/ punched on each part of clamps, except hardware. i) Conductor shall be tightened by at least four bolts. Conductor hold length must not be less than 60 mm. j) Surface of clamps to be tightened by bolts should be flat in shape, so that it may be possible to open the nuts and bolts by normal spanners. Therefore, any type of groove in the clamp body for fixing of nuts should be avoided. k) Portion of clamp to hold the conductor should be flat and straight and not zigzag in construction at both the sides, so that heating of clamp by throttling action of current may be avoided. l) Space of at least 50% of diameter of nuts should be available after hole at both the sides of conductor holding portion for better mechanical strength. 12.0 AUXILIARY CONTACTS 12.1. Eight numbers each of auxiliary contacts both of the normally open and normally closed types shall be provided in each circuit breaker for use in remote indication and control scheme of the circuit breaker and for providing safety interlocking. Special contacts for use with trip coils which permit for relative adjustment with respect to the travel of the circuit breaker shall also be provided. Wherever required, there shall be provision to add more auxiliary contacts at a later date, if required. All auxiliary contacts shall be placed in a weather proof casing and current rating of the contacts Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 110 Technical Specification shall be as mentioned in the bid. Provision shall be available to convert these spare ―normally-open‖ contacts to ―normally-closed‖ type and vice versa. 13.0 ACCESSORIES 13.1. Circuit breaker shall be supplied as a complete unit with internal wiring installed and terminated in mechanism box and equipped with the following accessories :(i) Motor operated spring charged mechanism : 1 No. (Motor voltage - 230 V AC, 50 Hz) (ii) Trip coil suitable for 110 V DC : 2 Nos. (iii) Closing coil suitable for 110 V DC : 1 No. (iv) Pistol grip C.B. Control switch having : 1 No. Trip /normal /close position (v) Local/remote selector switch : 1 No. (vi) Spring Charged indicator: 1 No. (vii) Manual operating handle for maintenance : 1 No. (viii) Facility for manual charging of spring : 1 No. (ix) Operation counter : 1 No. (x) Auxiliary contacts (8 NO - 8 NC) : 1 Set (xi) Anti pumping device suitable for 110 V DC : 1 No. (xii) Bimetallic terminal connectors suitable for : 6 Nos. connecting WOLF /RACCOON ACSR/AAA conductor. (xiii) Cubicle illuminating lamp with protective : 1 No. cage and on/off switch (xiv) Spare terminals block : 20% of the Total active terminals (xv) Mechanical ON/OFF Indicator : 1 No. (xvi) MCB for both AC and DC supply : 1+1 No. (xvii) Space heater with thermostat and : 1 No. ON/ OFF switch (xviii) 3-Pin 5 A socket with on/off switch : 1 Set (xiv) Earthing terminals : 2 Nos. (xx) Foundation Bolts : As per requirement (xxi) Cable glands : As per requirement 13.2. Other accessories which are not specified above, but are required for efficient and trouble free operation of breaker, should also be provided without any extra cost. 14.0 MOUNTING OF CTs 14.1. The offered steel structures for breakers should also have adequate strength to accommodate 3 nos. CTs on it with provision of suitable supports from ground. 15.0 TEMPERATURE RISE 15.1. The maximum temperature attained by any part of the equipment, when in service at site, under continuous full load conditions, exposed to the direct rays of the sun, shall not exceed 45˚ C above ambient temperature. The limits of temperature rise shall be as per relevant standard. . 16.0 TYPE TESTS 16.1. Type test certificates for the following tests, as per IS:13118 or IEC 62271-100 with latest amendment thereof, from any of the NABL accredited Laboratory shall invariably be furnished a. Short circuit duties test b. Short time withstand current and peak withstand current tests c. Temperature rise test d. Mechanical endurance test e. Lightning impulse voltage withstand test f. Power Frequency withstand voltage test (dry & wet) g. Single Capacitor bank switching test h. Degree of protection IP-55 as per IS:13947:93(Part-I)/IEC 60529:89 16.2. Type test certificates must accompany drawing of type tested equipment, duly sealed & signed by type testing authority. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 111 Technical Specification 16.3. Type tests should not have been conducted on the equipment earlier than 3 years from the date of opening of bids. 16.4. In case of any change in design/type of breaker already type tested and the one being offered against this specification, the Employer reserves the right to demand repetition of some or all tests without any extra-cost at NABL accredited lab. 17.0 ACCEPTANCE AND ROUTINE TEST :17.1. Employer shall have access at all times to the works and all other places of manufacture where the Circuit Breakers are being manufactured and the Bidder shall provide all facilities for unrestricted inspection of the Bidder/manufacturer‘s works, raw materials, manufacture of all the accessories and for conducting necessary tests as detailed herein. The Employer reserves the right to insist for witnessing acceptance/routine testing of the bought out items. The Bidder/manufacturer shall submit the routine test certificates of bought out items and raw material also, at the time of routine testing of the fully assembled breaker 17.2. No material shall be dispatched from its point of manufacture unless the material has been satisfactorily inspected and tested. 17.3. Bidders shall indicate the inspections and checks carried out at various stages of manufacture of the circuit breakers. Complete record of stage inspection would be kept by the Bidder/manufacturer and this record should be made available for inspection by the representative of the Employer. Bidder/manufacturer should indicate the manufacturing programme and the The Employer will have a right to depute inspecting officers during the manufacture of the equipment. The Employer reserves the right to carry out stage inspections at all stages, for which advance intimation shall be given and all necessary cooperation shall be rendered by the manufacturer. 17.4. At the time of inspection, Bidder/manufacturer shall identify each and every item/accessories of the particular Circuit Breaker under testing. Unless all the items are identified, the manufacture will not be treated as complete. Various tests stipulated in IS/IEC shall be performed in the presence of the Employer‘s engineers or when the inspection waiver has been given, in such a case, testing shall be done at the manufacturer's works as per IS/IEC stipulations and same should be confirmed by documentary evidence by way of Test Certificate which shall be got approved by the Employer. 17.5. It is expected that before circuit breaker is finally offered for inspection, internal testing of the same for various important parameters are already done. Routine test report for such tests shall also accompany the letter of inspection call so that the Inspecting Officer at the time of inspection may verify the parameters brought out in the preliminary report. Details of all tests should be clearly brought out. 17.6. In case for any reason, inspection is not completed or equipment is not found to be complete with all accessories as per confirmation given with the letter of inspection call, the Employer will reserve the right to recover complete cost of deputation of inspecting team to the works of the manufacturer. 17.7. Acceptance of any quantity of circuit breaker & its accessories shall in no way relieve the successful bidder of his responsibility for meeting all the requirement of this specification and shall not prevent subsequent rejection if such equipments are later found to be defective. 18.0 RATING PLATES & SURFACE FINISH PAINTING & GALVANISING:18.1. Each circuit breaker shall be provided with a detailed rating plate. Details on the rating plate shall be as per ISS and shall also indicate manufacturer name, serial no., order no. and month & year of dispatch. 18.2. All interiors and exteriors of tanks, mechanism, enclosures, cabinets and other metal parts shall be thoroughly cleaned to remove all rust, scales, corrosion, greases or other adhering foreign matter. All steel surfaces in contact with insulating oil, as far as accessible, shall be painted with not less than two coats of heat resistant, oil insoluble, insulating paint. 18.3. All metal surfaces exposed to atmosphere shall be given two primer coats of zinc chromate and two coats of epoxy paint with epoxy base thinner or hot dip galvanized Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 112 Technical Specification or two packs of aliphatic polyurethane finished paint. All metal parts not accessible for painting shall be made of corrosion resistant material. All machine finished or bright surfaces shall be coated with a suitable preventive compound and suitably wrapped or otherwise protected. Paints shall be carefully selected to withstand tropical heat and extremes of weather within the limits specified. 18.4. Paint shall not scale off or wrinkle or be removed by abrasion due to normal handling. All external paintings shall be as per shade no. 697 or any other suitable shade of IS:5 or polyurethane paint 18.5. All ferrous parts & steel structure including all sizes of nuts, bolts, plain and spring washers, support channels, structures, etc. shall be hot dip galvanized or stainless steel or electro-galvanized. 19.0 DOCUMENTATION: 19.1. List of Drawings and Documents: Bidders shall furnish four sets of relevant descriptive and illustrative published literature, pamphlets and following drawings for preliminary study; (a) General outline drawings showing dimensions and shipping weights. (b) Sectional views showing the general constructional features of the circuit breaker including operating mechanism, arcing chambers, contacts with lifting dimensions for maintenance. (c) All drawings & data typical and recommended schematic diagram for control supervision & reclosing shall be annotated in English. . (d) Schematic diagrams of breaker offered for control supervision and reclosing. (e) Structural drawing, design calculations and loading data for support structures. (f) Short circuit oscillogram & certificates for similar type tested breakers. General arrangement of foundation and structure mounting plan including weights of varnish components and impact loading data for foundation design. (g) Type test reports. 19.2. Successful bidders shall, within two weeks of placement of order, submit four sets of final version of all the above drawings for the Employer's approval. The Employer shall communicate his comments/approval on the drawings to the Bidder/manufacturer within two weeks. Bidder/manufacturer shall, if necessary, modify the drawings and resubmit four copies of the modified drawings for the Employer's approval within two weeks from the date of comments. After receipt of the Employer's approval, the Bidder/manufacturer shall, within three weeks, submit 4 prints per breaker and two set of good qualities reproducible of the approved drawings for the Employer's use. 19.3. Successful bidders shall also furnish two sets each of bound manuals covering erection, commissioning, operation and maintenance instructions and all relevant information and drawings pertaining to the main equipment as well as auxiliary devices along with each breaker. Marked erection drawings shall identify the component parts of the equipment as shipped to enable erection by the Employer‘s own personnel. Each manual shall also contain one set of all the approved drawings, type test reports as well as acceptance reports of the corresponding consignment dispatched. 19.4. Manufacturing of equipments shall be strictly in accordance with the approved drawings and no deviation shall be permitted without the written approval of the Employer. 19.5. Approval of drawings/work by the Employer shall not relieve the bidders of any of his responsibility and liability for ensuring correctness and correct interpretation of the Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 113 Technical Specification drawings for meeting the requirements of the latest revision of the applicable standards rules and codes of practices. Equipment shall conform in all respects to high standards of engineering, design, workmanship and latest revisions of relevant standards at the time of supply and the Employer reserves the right to reject any equipment or material which, in his judgment, is not in full accordance therewith. 20.0 PACKING AND FORWARDING: 20.1. Equipment shall be prepared for ocean shipment (foreign equipment) or rail road transport (local equipment). Equipment shall be packed in suitable crates in such a manner to protect it from damage and withstand handling during transit. Bidder/manufacturer shall be responsible for and make good at his own expense any or all damage to the equipment during transit, due to improper and inadequate packing and handling. Easily damageable materials shall be carefully packed and marked with the appropriate caution symbols. Wherever necessary, proper arrangement for lifting such as lifting hooks etc. shall be provided. Any material found short inside the packing cases shall be supplied by the Bidder/manufacturer without any extra cost. Each consignment shall be accompanied by a detailed packing list containing the following information: (a) Name of the consignee. (b) Details of consignment. (c) Destination. (d) Total weight of consignment. (e) Sign showing upper/lower side of the crate. (f) Handling and unpacking instructions. (g) Bill of material indicating contents of each package and spare material. 21.0 COMPLETENESS OF EQUIPMENT AND BOUGHT OUT ITEMS: 21.1. Bidders must furnish following information along with technical bid. A list of all the accessories which will be supplied with the breakers should be furnished. While furnishing the list of accessories, items which will be manufactured by the Bidders and balance items, which will be procured from sub-Bidder/manufacturers should be clearly identified and stipulated in the bid. 22.0 GUARANTEED TECHNICAL PARTICULARS: 22.1. It is obligatory on the part of bidders to furnish Guaranteed Technical Particulars enclosed with the bid document duly filled in complete in all respects. In case Guaranteed Technical Particulars duly filled in complete in all respects is not furnished, the bid may be treated as non-responsive Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 114 Technical Specification 3.5 SPECIFICATION FOR INDOOR CONTROL PANELS for 11kV OUTDOOR VCB 1.0 SCOPE 1.1. This section contains the technical specification for the multi circuit indoor control, indication, relay and metering panels for control of associated line or transformer through outdoor switchgear at various 33/11 KV sub-stations. The control and relay panels and other requirements specified under this section shall be complete in themselves with all main and auxiliary relays, annunciation relay, fuses, links, switches, wiring, labels, terminal blocks, earthing terminals, base frame, foundation bolts, illumination, cable glands etc. 2.0 PANEL FINISH AND COLOUR 2.1. The purchaser has standardized that the colour finish shall be opaline green as per color no. 275 of BS:381C (1948). Equivalent colors as per relevant Indian Standards or any other standard are also acceptable. This color finish shall be applied to all the exterior steel work of the panels. The exterior finish shall be semi glossy only and shall not be fully glossy. The interior of the panels shall be painted with egg shell white. 3.0 PROTECTIVE RELAYS AND INSTRUMENTS 3.1. The protective relays shall be manufactured, tested and supplied with the guaranteed particulars, as per following Indian Standard Specifications with latest amendment thereof :- (i) IS-3842 (Part-I):1967 : Application guide for electric relays for A.C. Systems over- current relays for Feeders and Transformers (ii) IS-3842 (Part-IV):1967 : Application guide for electric relays for A.C.system thermal protection relays (iii) IS-3231 (1965) : Electric relay for power system protection (iv) IS-1885 (Part-I&II) : Electro-technical vocabulary Electrical relays & Electrical power system protection (v) IS-4483 : Preferred panel cut-out (vi) IS-1248 : Indicating instruments (vii) All indicating instruments shall conform to IS-722 or BS-89 or any equivalent or better international standards... The equipment meeting any other authoritative standards which ensures equal or better quality than the standards mentioned above shall also be acceptable. Equipment for which Indian Standards are not available the relevant British Standards and IEC recommendations will be applicable. The bidder has to submit copies of all applicable standards other than Indian along with the offer. 4.0 TYPE/ ACCEPTANCE TEST CERTIFICATES FOR RELAYS:4.1. Following type test certificates of relays as per IS: 3231 or any equivalent international standard are required to be submitted by the bidder:- (i) Performance test and operating characteristic tests (ii) Thermal requirement test (iii) Accuracy test (iv) Re-set value test (v) Re-set time test (vi) Over shoot time test (vii)Rated burden & impedance test (viii)Insulation requirement test (ix) Mechanical requirement test (x) Contact performance test Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 115 Technical Specification 5.0 PANEL CUT OUT AND DIMENSIONS:5.1. The panels shall be fabricated from 2mm steel sheet free from all surface defects. The panels shall have sufficient structural re-enforcement to ensure a plane surface to limit vibration and to provide rigidity during dispatch and installation. All control panels and switchgear cubicles shall be made absolutely vermin-proof. Pre-treatment & painting of panels shall be done as per the procedure detailed in this schedule. 5.2. The panels shall have the following dimensions :- Height 1475 mm Depth 300 mm Width 600 mm No deviation in height and depth is permitted. However, to accommodate instruments, relays, control and indication gadgets of different make, increase in panel width alone is permitted, subject to specific approval of purchaser. 5.3. The preferred panel cut out dimensions for mounting of the relays shall be as per Indian Standard Specification IS-4483 (Part - I & II). 5.4. Design, material selection and workman-ship shall be such as to present a neat appearance, outside and inside with no works of welds, rivets, screw or bolts head apparent from the exterior surface of the Control Panels. 6.0 PANEL LIGHTING:6.1. For interior illumination, 11/15 Watt CFL operating at 230V AC 50 Hz with On/Off switch shall be provided in each panel. The lamp/tube shall be located at the ceiling and guarded with protective cage. The On/Off switch shall be mounted on one of the sidewalls and shall be easily accessible. 6.2. One 3 pin-5 Amp. receptacle socket with On/Off switch and fuse shall be provided in each control panel. 7.0 INDICATING LAMPS:7.1. The indicating lamps should be supplied with low voltage protection circuit (LVGP) and surge suppressor circuit having LED indication. Lamp assembly should be of fire retardant glass epoxy PCB, industrial heat resistant, fire resistant, non- hygroscopic DMC material, polycarbonate lens in desired color shades of Red, Green, Amber, Yellow etc. the intensity of light should be minimum 100 mcd at 20 mA. 8.0 AUXILIARY SUPPLY:8.1. For each Control Panel, the purchaser will provide the following :- i) 230V (+10% to -20%) single phase 2-wire, 50Hz neutral grounded A.C.supply, frequency variation ±4% ii) 110V (+ 10% to -15%) D.C. supply 9.0 CONTROL WIRING:9.1. The supplier shall provide complete wiring up to the terminal block for the equipment, instrument devices mounted in the control panel strictly according to the wiring diagram prepared by the supplier based on the purchaser‘s information and schematic diagram and get approved from the purchaser. 9.2. The wiring shall be complete in all respects so as to ensure proper functioning of control, protection and metering schemes. All unused potential free contacts of relays and switches if any shall be wired up to the terminal block. 9.3. The Control Panels shall be supplied completely wired, ready for purchaser‘s external connections at the terminal blocks. 9.4. For CT circuits, the wiring shall be carried out with 1100V grade PVC insulated stranded copper conductor of size 2.5 sq.mm. 9.5. For PT and for control circuits the wiring shall be carried out with 1100 V Grade PVC insulated stranded copper conductor of size 1.5 Sq.mm. 9.6. Color coded wires should be used to facilitate easy tracing, as under:- i) Three Phase A.C. Circuit: - Red for R Phase, Yellow for Y Phase, Blue for B Phase Black for Neutral,and Green for earthing. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 116 Technical Specification ii) Single Phase A.C. Circuit:-Red for Phase, Black for Neutral & Green for Earthing. iii) D.C. Circuit: - Red for Positive, Yellow for Negative. iv) Control Wiring: - Gray for annunciation and other control circuits. (f) Each wire shall be identified at both ends with wire designation number by plastic ferrules, as per wiring diagram based on latest revision of IS-375 to denote the different circuit functions. (g) All wire termination shall be made with compression type connectors. Wires shall not be tapped or spliced between terminal points. All wire shall have crimp type termination and direct connection at any place is not at all required. (h) All series connected devices and equipment shall be wired-up in sequence. Loop-in/loop-out system of wiring shall be avoided, as far as possible and the common buses shall normally be made through the terminal block for better reliability of testing and maintenance. (i) Fuses and links shall be provided for isolation of individual circuit from the bus wires without disturbing the other circuits and equipments. (j) The DC trip and DC voltage supplies and wiring to main protective gear shall be segregated from these for back up protection and also for protective apparatus for special purposes. Each such group shall be fed through separate fuses, either direct from main supply fuses or the bus wires. (k) Since, a number of wires will run from one point to another, it is desired that the support arrangement should be adequate and neat. The conventional method of bunching of wire should not be adopted, since the same may create problems in case any wire is to be removed. The wires should be accommodated in plastic channel with sliding plastic cover mounted inside the panel, suitably. Inspection/removal of wires should be possible by sliding the covers. (l) Blank plastic channels should be provided by the sides of the panel to accommodate the incoming cables from switchyard through the cable glands. (m) The circuit diagram of control circuit along with operating instructions (DO/DO‘NT) embossed on metallic plate duly laminated shall be provided on rear side of the door. 10.0 TERMINAL BLOCKS:10.1. Multi-way terminal blocks complete with necessary binding screws and washers for wire connections and marking strips for circuit identification shall be provided for terminating the panel wiring and outgoing cables. The terminal block shall be suitable for receiving at least 2x2.5 sq.mm stranded copper conductor wire per terminal. 10.2. Terminal blocks shall have shorting and disconnection facilities. The panel-side and outgoing wires should be dis connectable just by opening the disconnecting links, which slide up/down or left/right without dislodging the wires from their position. However, disconnectable type terminal connectors with shorting facility may be limited to CT & PT circuits only. 10.3. Instrument transformer wires shall be terminated through suitably mounted test terminal blocks for site testing facility. 10.4. The terminal blocks shall be grouped according to circuit functions and each terminal block group shall have at least 20% spare terminals. Adjacent rows of terminal block shall be spaced not less than 100 mm apart. These shall be mounted vertically at the sides of the cubicle and set obliquely towards rear doors to give easy access of terminating end to enable ferrule number to be read without difficulty. The bottom of terminal blocks shall be spaced at least 200 mm the cable gland of incoming multi-core cables. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 117 Technical Specification 11.0 CABLE ENTRY:11.1. The control panel shall have provision of cable entry from the bottom. The box base shall have 3 mm thick cover. 11.2. The cover plate of base box for 11 KV and 33 KV MULTI CIRCUIT C&R panels, shall be provided with 3 cable glands for 7 core, 5 cable glands for 4 core and 3 cable glands for 2 core 2.5 sq.mm unarmored copper control cable. 11.3. The gland plate shall be covered with dummy plate. The bidder has to provide all required material to ensure IP55 protection. The purchaser will arrange for necessary floor opening, below the panel and fixing of gland plate for control cable entry to suit the supplier‘s requirement. 11.4. The wiring through terminal blocks shall be such located so that it is convenient for floor opening. 11.5. For fixing cable glands on the box base cover, detachable gland plates of 4 mm thick shall be mounted at least 100 mm above the floor level. 11.6. The cable gland plate and rear door shall be properly rubber gasketted to ensure IP-55 protection. 11.7. Rigid supports shall be provided along the terminal block for holding plastic channel. Suitable clamps shall also be provided in plastic channel for holding cables. 12.0 GROUNDING:12.1. 25mm x 6mm x 250mm copper ground bus shall be provided inside the panel for effectively grounding all metal structures. Each continuous length of ground bus shall have provision of two terminals at two separate points for connection to main ground grid of the sub-station. 12.2. Potential and current transformer neutrals shall be grounded only at the terminal blocks where they enter the control panel from the instrument transformers. 12.3. Wherever a circuit is shown grounded in the drawings, a single wire for the circuit shall run independently to the ground bus and connected to it. 13.0 DOORS:13.1. Each panel shall be complete with end enclosing sheets on both sides and door in the rear. The rear door shall be fitted with handle and also turn twist locks at top and bottom. Proper rubber sealing gasket shall be provided on the door. A type test report from the recognized Government laboratory or NABL approved lab on degree of protection test IP-55 shall be furnished by the supplier. 14.0 CONTROL AND RELAY PANELS:14.1. The control panels required for installation at all the sub-stations shall be of simplex type for multi circuit control. The control and indication apparatus, all meters and relays shall be mounted in the front. The instruments and relays shall be flush mounted pattern. 14.2. The labeling for the circuits shall be provided at the front control panel, as well as on the inside wall. All indicating instruments, meters and important components shall have identification labels from inside also, in addition to outside. The terminal block shall have identification labels attached to them, clearly indicating type of supply ‗AC & DC identification circuits‘ control (metering/protection) and instruments identification. For example, the terminal block shall have an identification indicating that is for CT circuit, metering, protection etc. 14.3. A mimic diagram showing single bus arrangement, with semaphore for breaker position indicator etc. shall be provided for each circuit. 15.0 PROTECTION SCHEME:15.1. The control panels are required for protection of 11 KV Overhead lines The protection schemes are described in the following clause:15.2. Feeder Protection :- This will be in the form of a IDMT relay having 2 Nos. O/C and 1 No. E/F elements with high set. The current settings of O/C relay element shall be from 2 % to 150% in equal step of 1-2 % each and of E/F relay element from 2 % to 80%. They shall be suitable to work on 110 Volt D.C. supply. The secondary rating of C.T. shall be 5 Amps. The Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 118 Technical Specification numerical relays having programmable characteristics as per above requirements are required. The relay shall be of draw out type with CT shorting facility. Further, the relay shall have self re-set contacts and hand re-set flag arrangement. The tripping shall be routed through a high speed master trip relay with hand reset facility and flag relay. 16.0 CONTROL AND INDICATION CIRCUITS: - 11 KV feeders): 11 KV multi circuit control & relay panel for control of feeders shall have the following instruments, relays and accessories:1. Three pole 5 Amp Numeric IDMT relay 110 V DC with self-reset contacts and hand reset flag (Flush pattern) shall be suitable for selecting following settings :a. O/C Element (2% to 200%) and E/F Element (2% to 80%) with high set b. Operating Time plug setting With Multiple characteristics 2.Pistol grip Circuit Breaker Control switch T-N-C 3. Digital Ammeter of 96X96.mm size flush pattern CT operated sec 5 Amp with Accuracy class 1.0. 4. Ammeter selector switch 5. Hand Reset Master trip Relay 6. Indicating Lamps as follows a. CB-ON (RED) b. CB-OFF (GREEN) c. Trip ckt coil healthy (preclose and post close)- White d. Auto trip (Amber) e. Spring charged(Blue) f. DC Fail relay 7.Push buttons for a. Alarm accept b. Alarm reset 2 c. Pre close Trip Circuit check coil-1 d. Pre close Trip Circuit check coil-2 8 Alarm Bell for DC fail 9 Alarm Buzzer AC fail 10. Cable glands with dummy cover suitable for 2.5 sq.mm Unarmored copper control cable fitted on cover plate. For 2core, 4 core and 7 core. 11. Illumination CFL 11/15 Watt lamp with protective cage & On/Off Switch. 12 3 pin-5 A power socket with On/Off Switch. 1 13 MIMIC (10X3 mm) made of Aluminum strip painted black showing single bus and breaker position semaphore indicator for isolator 14 Semaphore CB position indicator 3.15.4 The bidders are required to submit C&R panel general arrangement and schematics indicating all relevant details of all relays and gadgets along with bill of material. . NOTE: Any other indications or control equipments which are required for proper protection/ operation of circuit breaker should be provided in control panel, without any extra cost. . should organize services of their engineer at any site if any problem is reported either by the purchaser or field units. 13.18 TESTS:18.1 Each control panel shall be completely assembled, wired, adjusted and tested at the factory, prior Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 119 Technical Specification to dispatch. 18.2 The tests shall include wiring continuity tests, insulation tests and functional tests to ensure operation of the control scheme and individual equipment. 18.3 The test procedures shall have prior approval of the purchaser. 18.4 All instruments, meters and relays shall be tested and calibrated in accordance with relevant standards. 17.0 TEST CERTIFICATE:- Each control & relay panel should be tested by the manufacturer at their works for all routine and acceptance tests and copies of test certificate in duplicate giving results of these tests shall be furnishedto the purchaser along with letter / offer for inspection. 18.0 WITNESSING OF TESTS The routine/ acceptance tests results shall be witnessed by purchaser‘s representative, if so desired by the purchaser, prior to dispatch of the equipment from the works. The supplier shall give at least Fifteen (15) days advance notice of the date when the tests are to be carried out. 19.0 TEST CERTIFICATE OF COMPONENTS:- Test certificate for important components like Ammeter, Voltmeter, Relays and Control Switch shall be produced at the time of inspection and shall be enclosed with the inspection report. 20.0 PRE-TREATMENT AND PAINTING PROCESS:20.1. The Control Panel sheet steel shall be subjected to pre-treatment process before painting. The process shall be carried out as under. The procedure can broadly be divided as ―Metal treatment‖ and ―painting‖. (A) METAL TREATMENT:i) DEGREASING :This can be achieved either by immersing in hot alkaline degreasing bath or in hot di-chloroethelene solution. In case degreasing is done by alkaline bath, rinse with cold water thoroughly. ii) PICKLING :This is to remove rust and metal scales by immersing in diluted sulphuric acid (approximately 20%) at nearly 80 degree centigrade until scale and rust are totally removed. iii) Rinse in cold water in two tanks to remove traces of acids. iv) Treat with phosphoric acid base neutralizer, for removal of chlorine from the above acid pickling and again wash with running water. v) PHOSPHATING :Immerse in grenadine Zinc phosphate solution for about 20 minutes at 80 to 90 degree centigrade. The uniform phosphate coating of 4 to 5 gms per sq. meter shall be achieved. vi) Swill in cold water. vii) Rinse in deorylyte bath at 70 to 80˚C to neutralize any traces of salts. viii) Seal the above phosphate coating with hot dilute chromate solution. ix) Dry with compressed air. (B) PAINTING:Sequence of process shall be as follows: i) Spray one coat on wet surface by specially developed, ―High Luster‖ Zinc chromate primer and stove at 150 to 160 degree centigrade for 25 to 30 minutes. Alternatively, Red-Oxide primer with zinc chromate content may be used. However, former process is preferred. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 120 Technical Specification ii) Rubbing and putting: - Apply putty to fill up scars, if any, to present smooth surface and stove 15 to 20 minutes. Apply putty several times to get the perfectly smooth finish. iii) Surfacing:- Sand down with mechanical abrasive and stove for 20 minutes. iv) Primer:- Spray second coat of primer as per (i) above or grey primer surface on wet and stove for 30 to 40 minutes at 150 degree centigrade. v) Finish Paint: - Rub down dry and spray first coat of synthetic enamel finish paint on wet and stove for 30 minutes. vi) Surfacing:- Sand down or rub dry to prepare for final finish. Spray 2 coats of synthetic enamel finish paint on wet and stove it at 150 degree centigrade for 30 minutes. NOTE:i) Necessary stiffeners may be welded between large cut outs to provide rigidity before painting process. ii) Painting process shall be done within 24 Hrs. of completion of metal treatment. iii) Small coating shall be supplied along with equipment for touching up at site. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 121 Technical Specification 3.6 TECHNICAL SPECIFICATION FOR 11kV INDOOR VACUUM SWITCHGEAR 1.0 SCOPE 1.1. This specification covers the manufacture, testing at manufactures works, transport to site, insurance, storage, erection and commissioning of indoor 11 KV ,9 unit Panel switch boards which includes 11KV circuit breakers with current transformers, voltage transformers, protective devices, protective relays measuring instruments and meters etc. and wired complete with all accessories as specified. 1.2. It may be noted that the 11 KV Indoor Vacuum Switchgear must meet the following minimum criteria. Failure to comply with the requirements may results in rejection of the BID as non-responsive: 1.2.1. The Manufacturer must have designed, manufactured, type tested and supplied 11 KV Indoor Vacuum Switchgear in at least two power utilities of similar rating which are in successful operation for at least 5 (Five) years as on the date of bid opening. Which should be substantiated by furnishing performance report by the official of the rank of minimum DGM/SE 1.2.2. The manufacturer of the VCB must use their own make Vacuum Interrupter and must have in-house manufacturing facility for Vacuum Interrupter & Breaker (including mechanism) 1.2.3. Internal Arc Proof Panel – 25 kA for 0.1 sec with explosion vents on each HT Compartment. 2.0 STANDARD 2.1. Latest issues of the following standards shall be applicable. I.S. 13118 I.S. 2705 I.S. 3156 I.S. 2099 I.S. 335 I.S. 1554 I.S. 3231 I.S. 1248 Circuit Breakers Current transformers Voltage transformers Porcelain Bushing, High Voltage Insulating oil Cables Electrical relays for power system protection Electrical indicating instruments. 3.0 DRAWINGS, MANUALS, LITERATURES ETC. 3.1. The successful tenderer shall be required to submit to the purchaser for his approval five copies of drawings and other details which include bue not limited to the following:a) General out line drawings with full dimensions. b) Detailed drawings showing the mounting arrangement of the switchboards, provisions for cable entries etc. c) Detailed drawings showing the provisions kept for extension of the switchboards. d) List of all component parts, fittings and accessories of the switchboards with maker‘s name, type, ratings etc. e) A.C. and D.C. schematic and wiring diagrams. 3.2. After approval of drawings the tender shall submit to the purchaser for the reference and record five copies of the above drawings including the following leaflets / manuals (in sic copies): a) Instruction books / operation and maintenance manuals for circuit breaker and other component parts. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 122 Technical Specification b) Descriptive literature/leaflets on construction and other details of circuit breakers and other component parts. 3.3. In addition to the above successful tenderer shall supply three sets of all the above final drawings, literatures, manuals etc under a common cover with each and every sets of switchboard. All the above drawings, literatures, manuals etc. shall from a part of the contract. 4.0 TECHNICAL SPECIFICATION: 4.1. The switchboard shall be metal enclosed, floor mounting, single front self supporting cubical type suitable for indoor. The switchgear shall be easily extendable in future. 4.2. The switchgear assembly shall be designed for the power system having the following parameters. a). Nominal system voltage: 11KV b). Highest system voltage: 12KV c). Frequency: 50 Hz. d). System earthing: Solidly earthed neutral e). System fault level: 250 MVA f). Degree of protection of switchgear assembly: 1PH3 as per IS: 3427 5.0 CONSTRUCTIONAL FEATURES: 5.1. The 11 KV switchgear panels shall be made of stretched leveled steel plates of thickness not less than 3 mm and structural steel having light sections. 5.2. The steel panel and frame work shall have rigorous surface treatment before application of suitable primer and two coats of paints, painting shall be a anticorrosive and anti-condensive type. 5.3. Each panel shall be divided into independent compartment completely isolated from one another to house the circuit breaker, instruments, relay, bus bar, cable boxes etc. The front compartment housing the breaker shall be such that the breaker can be taken out only when it is in open condition. 5.4. The switchgear boards shall have a single front, single tier, fully compartmentalized, metal enclosed construction, comprising of row of freestanding floor mounted panels. Each circuit shall have a separate vertical panel with distinct compartments for circuit breaker ,cable termination, main busbar and auxiliary control devices. The adjacent panels shall be completely separated by steel sheets except in busbar compartments where insulated barriers shall be provided to segregate adjacent panels. However, manufacturer‘s standard switchgear design without internal barriers in busbar compartment may also be considered. 5.5. The circuit breakers and bus PTs shall be mounted on withdrawable trucks, which shall roll out horizontally from service position to isolated position. The breaker truck shall be floor mounted so that it can easily be pulled out on the control room floor and the help of trolly etc. are not to be utilized. 5.6. The switchgear assembly shall be dust, moisture, rodent and vermin proof, with the truck in any position SERVICE, ISOLATED, TEST or removed, and all doors and covers closed. All doors, removable covers and glass windows shall be gasketted all round with synthetic rubber or neoprene gaskets. 5.7. The bus VT/relay compartments shall have degree of protection not less than IP : 52 in accordance with IS:2147. However, remaining compartments can have a degree of protection of IP:42. All louvers if provided shall have very fine brass or GI mesh screen, IPH-2 degree of protection as per IS: 3427 to all live parts shall (whether isolated or removed from panel) even when the breaker compartment door is open. Tight fitting garments / gaskets are to be provided at all openings in rely compartment. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 123 Technical Specification 5.8. Circuit breaker shall be vacuum; draw out type housed in a separate cubicle of the switchboard and shall be enclosed from all sides. A sheet steel hinged lockable door shall be at the front. It shall be possible to withdraw the circuit breaker to ‗Test‘ and ―Isolated‘ position with the door closed. Door interlock shall be provided such that the door can only be opened after withdrawing the breaker to ‗Isolated‘ position and the breaker cannot be racked into the ‗Service‘ position unless the door is closed. A visual indication as to show when the breaker is in „Service‟, „Test‟ of „Isolated‟ position shall be provided in front of the door. 5.9. The switchgear shall be cooled by natural airflow and cooling by any other method shall not be accepted. 5.10. Total height of the switchgear panels shall not exceed 2600 mm. The height of switches, pushbuttons and other hand-operated devices shall not exceed 1800 mm and shall not be less than 700mm. 5.11. Switchgear construction shall have a bushing or other sealing arrangement between the circuit breaker compartment and the busbar / cable compartments, so that there is no air communication around the isolating contacts in the shutter area with the truck in service position. 5.12. The breaker and the auxiliary compartments provided on the front side shall have strong hinged doors, busbar and cabling compartments provided on the rear side have bolted compartment covers with self retaining bolts. Breaker compartment doors shall have locking facility. 5.13. In the service position, the truck shall be so secured that it is not displaced by short circuit. Busbars, jumpers and other components of the switchgear shall also be properly supported to withstand all possible short circuit forces corresponding to the short circuit rating specified. 5.14. Suitable base frames made out of steel channels shall be supplied along with necessary anchor bolts and other hardware, for mounting of the switchgear panels. These shall be dispatched in advance so that they may be installed and leveled when the flooring is being done, welding of base frame to the insert plates as per approval installation drawings. 5.15. The switchboard shall have the facility of extension on the both sides Adopter panels and dummy panels required to meet the various busbar 6.0 CIRCUIT BREAKER RATING 6.1. FOR INCOMER(2 Nos.) 6.2. FOR BUS COUPLER(1 No.) 6.3. FOR OUTGOING FEEDER (6 Nos.) 7.0 CURRENT TRANSFORMER RATING 7.1. FOR TRANSFORMER INCOMING (i) Accuracy class : a) Core -I : 0.5 with ISF less than 5 b) Core –II : 5 P with ALF 10 c) Core –III : PS (for 3 core CT only) (ii) Rated Burden a) Core –I : 30 VA b) Core –II : 15 VA (iii) Knee point voltage : 100 volts (for core –III ) (v) Ratio: : 600-300-150/5-5-2.89 7.2. Current Transformers for outgoing (feeders) (i) Ratio : 400-200/5-5 (ii) Accuracy class : a) Core -I : 0.5 with ISF less than 5 b) Core –II : 5 P with ALF 10 (iii) Rated Burden : a) Core –I :30 VA Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 124 Technical Specification 7.3. b) Core –I : 15 VA Current Transformers for Bus Section (i) Ratio : a) 600-300/5-5 (ii) Accuracy class : a) Core -I : 0.5 with ISF less than 5 b) Core –II : 5 P with ALF 10 (iii) Rated Burden : a) Core –I : 15 VA b) Core –I : 15 VA 8.0 POTENTIAL TRANSFORMERS 8.1. . The tenderer shall quote for oil immersed or cast-resin type having the following particulars for the purpose of metering: 1. Rated voltage ratio : 11000/110 2. No. of phases : 3 Phases / star - star connected 3. Rated Burden : 100 VA per phase 4. Class of accuracy : 0.5 5 Primary wiring of the PTs shall be protected by suitable H.R.C. fuse. 8.2. Two sets of 11 KV/110 V PTs shall be provided 9.0 PROTECTIVE RELAYS: 9.1. All the incoming and outgoing switchgear units shall be provided protective relays to disconnect the faulty circuits with speed and certainty without interfering with healthy circuits. 9.2. The protective relays mounted on the panels shall be of the draw out type. The relavs must be capable of resetting without necessity of opening the case. The relays shall be provided with flag indicates to enable the type of fault conditions to be identified. 9.3. Incoming and outing feeders units and the bus coupler panel shall be provided with combined over current and earth fault relay with current range of 50-200% for O/C with inverse characteristics and 20-80% for E/F relay of time range 0.3 secs at 10 times current. 10.0 MEASURING INSTRUMENTS 10.1. All instruments shall be switchboard type, back connected, suitable for flush mounting and shall comply with the requirements of latent issues of relevant Indian Standards. The instrument cases shall be dust proof, water tight, vermin proof and specially constructed to adequately protect the instruments against damage or deterioration due to high ambient temperature and humidity. 10.2. All instruments shall be access adjustable and calibrated before dispatch and shall have means for calibration check and adjustment at site. 10.3. All ammeters shall be digital type with direct reading scales. The scale value of ammeters shall be as per the primary current ratings of the associated current transformers. The rated current of ammeter elements shall be 5 ampere and accuracy class 1.0 as per IS: 1248. 10.4. All voltmeters shall be of digital type with direct reading scales. The maximum scale value of voltmeters shall be 50% in access of the primary voltage of associated PT. The rated voltage of the voltmeters shall be 110 volts A.C. and accuracy class shall be 1.0 as per IS: 1248. 10.5. Indicating wattmeters shall be of digital type of accuracy class 1. 10.6. Energy meters shall be digital type of accuracy class 0.5.and of Secure make or L&T make preferably as per APDCL Spec Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 125 Technical Specification 11.0 SMALL WIRING AND TERMINAL BLOCKS 11.1. All panels shall be furnished completely factory wired up to terminal blocks ready for external connections. All wiring shall be switchboards type, with annealed copper wires with PVC insulation for 1100 volts complying with requirements of latest issue of IS: 1554 (Part-I). The sizes of the wiring for different circuits shall be go chosen as to provide ample margin for the purposes intended and shall be subjected to approval of the purchaser. However minimum cross section of wires t be used shall not be less than 1.5. sq.m. All the operating coils and small wires shall withstand a power frequency ten voltage of 2 KV for one minute. 12.0 SAFETY EARTHING 12.1. Earthing of current free metallic parts of metallic bodies of the equipment on the panel and the switchboards shall be done with soft drawn single conductor bare cooper. A copper ground bus extending the entire length of the panels shall be provided. Suitable clamp type terminals shall be provided for connecting both ends of the bus to the station earth system. The earth connection of instrument transformers wherever necessary shall be connected with the main earth wire of the panel earthing system. Multilpe earthing of any instrument transformer circuit shall be avoided. 13.0 CABLE BOXES AND CABLE GLANDS: 13.1. Cable boxes with cable glands shall be supplied with each of the panel. It should be of adequate dimension for terminals of 11 KV cables of sizes 300 and 185 sqmm and 180 sq.mm. 13.2. The 11 KV cable boxes shall preferably be located at the back of the switchboards and shall be suitably mounted for cables rising from cable trenches running at floor of the control room. The cable glands provided at the entrance shall facility for earthing of amounting. 13.3. All control/Wire entries should be by means of suitable cable glands such glands should be of brass and tinned. 14.0 DETAILS OF FITTING AND ACCESSORIES 14.1. The 11 KV switchboards shall consist of the following equipments for each incoming outgoing and bus-coupler panels as per single line diagram enclosed. 14.2. Incoming panel (Transformer panel) I. Circuit Breaker: 1 No. : - Triple pole circuit breaker. With continuous current rating of 800A. :Manually, charged independent spring closing, mechanism fitted with mechanical ―ON‖ and ―OFF‖ indications. 1 No. : Hand trip device. 1 No. : Shunt trip coil suitable for 110 D.C. II. Meters and Instrument: 1 No. : Ammeter with selector switch. 1 No. : Voltmeter with selector switch. 1 No. : Electronic Tri-vector Meter 1 No. : Test terminal block for meters. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 126 Technical Specification III. Relays: 1 Set 1 Set Indication : Over current and earth fault relay. : Testing links and terminals for relays. 2 No. : Indicating lamps for indication of „ON‟ and „OFF‟ position of breaker. 1 No. : Indicating lamp labeled “trip Circuit healthy” with push button. IV. Annunciation: Annunciation: No annunciation facia shall be provided for Outgoing panel V. Other Equipments and fitting: Same as for incoming panel but cable box shall be suitable for following size of cable: 1 No. : 3 core 11 KV cable of size up to 630 sq.mm. 14.3. BUS SECTION PANEL: Same as detailed for incoming panel in clause 7.16.1 but with following modifications/additions/deletions: I. Circuit Breaker: 800 A II. Current and potential transformer NO Potential transformer required, CT ratio as specified for bus section panel. III. Meters and Instruments: All meters except the ammeter with selection switch shall be deleted. IV. Relays: Only 1set O/C & E/F relay shall be provided. V. Indication: Indicating lamp labeled “Auto trip” with accept push button associated with Auto trip alarm shall be added. VI. Annunciation: No annunciation facia shall be provided for bus section panel. VII. Other Equipments and Fittings: Cable box shall be deleted. 14.4. I. COMMON ALARM AND ANNUNCIATION: Each switchboard shall be provided with a suitable common alam system for: a). D.C. Power supply failure. b). A.C. Power supply failure. c). Auto trip alarm. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 127 Technical Specification II. III. IV. An AC operated relay with AC buzzer and AC indicating lamp shall be provided for annunciation of DC failure. A DC operated relay with DC buzzer and DC lamp shall be provided for AC failure. Alarm and annunciation scheme shall be provided completed with horns, buzzers, relays, alarm connection push buttons, alarm test push buttons etc. 15.0 CIRCUIT LABELING: 15.1. Each switchgear shall be appropriately such as ‗INCOMING TRANSFORMER‘, OUTGOING – FEEDER and BUS – SECTION‘, Associated Circuit breaker ratings, CT & PT ratio and any other information, manufacturer feels necessary shall also be included in the label. 16.0 PERFORMANCE GUARANTEE 16.1. The bidder shall offer equipment performance guarantee for a minimum period of 1 year from the date of commissioning. 17.0 . SPECIAL TECHNICAL SPECIFICATIONS OF SWITCHGEAR: 17.1. Switchgear shall be installed on finished surfaces, concrete or steel sills. Contractor shall be required to install and align any channels sills, which form part of foundations. Circuit breaker trolley wheels shall move on channels, which shall form part of floor. The channel length shall be minimum of 1-meter form the door of switchgear panel. Power bus enclosure, ground and control splices of conventional nature shall be cleaned and bolted together with torque wrench of proper size or by other approved means. Tape or compound shall be spilled where called for in drawing Contractor shall take utmost care in handling instruments, relays and other delicate mechanism. Wherever the instruments and relays are supplied loose along with switchgear, they shall be mounted only after the associated switchgear panels have been erected and aligned. The blocking materials, employed for safe transit of instrument and relays shall be removed after ensuring that panels have been completely installed and no further movement of the same would be necessary. Any damage shall be immediately reported to Engineer. 17.2. Foundation work for all switchgear panels will be carried out by contractor. For R&M of existing substation foundation work shall be done wherever required as per site condition. 17.3. Circuit breaker may be provided with inter pole barriers of insulting materials, if the same is standard design of the manufacture. But use of inflammable materials like Hylam shall not be acceptable. 17.4. The control switch located on the switchgear would normally be used for operation of circuit breaker in service/isolated position, and for tripping it in an emergency. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 128 Technical Specification 17.5. Facilities shall be provided for mechanical tripping of the breaker. 17.6. Auxiliary contacts of breaker may be mounted in the fixed portion or in withdraw able truck as per the standard practice of the manufacture, and shall be directly operated by the breaker operating mechanism. 17.7. Auxiliary contacts mounted in the portion shall not be operable by the operating mechanism, once the truck is withdrawn from the service position, but remain in the position corresponding to breaker open position. Auxiliary contacts mounted on the truck portion and dedicated for use shall be wired out in series with a contact denoting breakers service position. With truck withdrawn, the auxiliary contacts shall be operable by hand for testing. 17.8. For Employer‘s use six (6) normally opened (NO) and six (6) normally closed (NC) auxiliary contacts shall be wired out to the terminal blocks. Contact multiplication, if necessary to meet the above contact requirement, shall be done through suitable latch relay of English Electric type VAJC-11 or equivalent. 17.9. It shall be possible to easily insert breaker contractor of one feeder into any one of the panel meant for same rating but at the same time shall be prevented from inserting it into panels meant for a different type of rating. 17.10. All bus bar and jumper corrections shall be of high conductivity copper or aluminium alloy. They shall be adequately supported on insulators to withstand electrical and mechanical stresses due to specified short circuit currents. 17.11. Busbar joints shall be bolted type. 17.12. Busbar cross-section shall be uniform throughout the length of switchgear. Busbar and other high voltage connection shall be sufficiently corona free at maximum working voltage. 17.13. Contact surfaces at all joints shall be silver plated or properly cleaned and no oxide grease applied to ensure an efficient and trouble free connection. All bolted joints shall have necessary plain and spring washers. All connection hardware shall have high corrosion resistance. Suitable bimetallic connectors shall be used for aluminium to copper connections. 17.14. Busbar insulators shall be of arc and track resistant high strength, non-hygroscopic, non-combustible type and shall be suitable to withstand stresses due to over-voltages, and short circuit current. Busbar shall be supported on the insulators such that the conductor expansion and contraction are allowed without straining the insulators. In case of organic insulator partial discharge shall be limited to 100 pico coulomb at rated voltage x1.1/ 3. Use of insulators and barriers of inflammable material such as Hylem shall not be accepted. 17.15. All busbur shall be colour coded. 17.16. The temperature of the busbars and all other equipment, when carrying the rated current continuously shall be limited as per the stipulations Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 129 Technical Specification of relevant India Standards, duly considering the specified ambient temperature (50 deg. C). The temperature rise of the horizontal and vertical busbars when carrying the rated current shall be in no case exceed 55 deg.C for silver plated joints and 35 deg.C for all other type of joints. The temperature rise at the switchgear terminals intended for external cable termination shall not exceed 35 deg.C. Further the switchgear parts handled by the operator shall not exceed a rise of 5deg.C. 18.0 PAINTING: 18.1. Al sheet steel work shall be pretreated in tanks in accordance with IS: 6005. Degreasing shall be done by alkaline cleaning. Rust and scale shall be removed by pickling with acid. After pickling, the parts shall be washed in running water. Then these shall be rinsed in slightly alkaline hot water and dried. The phosphated coating shall be Class ‗C‘ as specified in IS: 6008. The phosphated surface shall the rinsed and passivated prior to application of stoved lead oxide primer coating. After primer application, two coats of finishing synthetic enamel paint on panels shall be applied. Finishing paint on panels shall be shade 692 (smoke grey) of IS: 5 unless specified otherwise by the Owner. The inside of the panels shall preferably be glossily white. Each coat finishing shall be properly stoved. The paint thickness shall not be less than 50 microns. Finished surfaces from scratches, grease dirt‘s and oily spots during testing, transporation, handling and erection. 19.0 SWITCHGEAR WIRING 19.1. All switchgear panels shall be supplied completely wired internally upto the terminal block ready to receive external cabing. All inter cubicle wiring and connections between panels of same switchboard including all bus wiring for AC and DC supplies shall be provided by the Contractor. All internal wiring shall be carried out 650 grade, single core, 1.5 sq.mm, stranded copper wires having minimum of seven strands per conductor and colour coded, PVC insulation. CT circuits shall be wired with 2.5 sq.mm. wires which otherwise are similar to the above. Extra flexible wires shall be used for wiring between fixed and moving parts such as hinged doors. All wiring shall be properly supported neatly, readily accessible and securely connected to equipment, terminals and termenal blocks. Wiring troughs or gutters be used for this purpose. 19.2. Internal wire terminals shall be made with solder less crimping type tinned copper lugs, which shall firmly grip the conductor. Insulation sleeves shall be provided over the exposed parts of lugs. The lugs related to CT secondary circuit wiring shall be hole type. 19.3. Engraved core identification plastic ferrules marked to correspond with panel wiring diagrams be fitted at both ends of each wire number 6 and 9 shall not be used for wire identification. Ferrules shall fit tightly on wires and shall not fall off when wire is, disconnected from terminal. All wires directly connected to trip the circuit breaker shall be distinguished by the addition of a red coloured unlettered ferrule. 19.4. Inter connection to adjacent panels shall be brought out to a separate set of terminal blocks located near the slots or holes, meant for the Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 130 Technical Specification interconnecting wires. Arrangement shall permit neat layout and easy inter connections to adjacent panels at site and wires for this purpose shall be provided by Contractor looped and bunched properly inside the panels. The inter panel wires shall be cross ferruled i.e. it shall have details of emanating terminal and also where it is terminated. 19.5. Manufacturer shall be fully responsible for the completeness and correctness of the internal wiring and for the proper functioning of the connected equipment. 19.6. The Manufacturer shall provided the necessary clamps wiring troughs etc. for all wiring in side the switchgear enclosed including the power and control cables. 20.0 POWER CABLE TERMINATION: 20.1. The cable termination compartment shall received the stranded aluminium conductor, XLPE insulated, shielded, armoured / unarmoured, PVC jacketed, single core / three core unearthed / earthed grade power cable (s). 20.2. A minimum clearance of about 600 mm shall be kept between the cable lug bottom ends and gland plates for stress cone formation for XLPE Cable. Interphase clearance in the cable termination compartment shall be adequate to meet electrical and mechanical requirement besides facilitating easy connections and disconnections of cables. Dimensional drawing of cable connected compartment showing the location of lug, glands, CTS, gland plates etc. and the electrical clearances available shall be submitted Employer approval during detailed engineering. 20.3. Cable termination compartment shall be complete with power terminals, power lugs and associated hardware and removable undrilled gland plates. Fopr all single core cables grand plates shall be of nonmagnetic material. 20.4. Supply of the cable termination kit and cable termination shall be in scope of contractor. 21.0 TESTS: 21.1. The Contractor shall submit the type test reports of following type tests for approval of the Employer for circuit breaker, circuit breaker panels, of each voltage class and current rating: i). Short circuit duty test on circuit breaker, mounted inside the panel offered along with CTs, bushing and separator. ii). Short time withstand test – on circuit breaker, mount inside panel offered together with CTs, bushing and separator. iii). Power frequency withstand test on breaker and panel. iv). Lighting impulse withstand test on breaker and panel. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 131 Technical Specification v)The indoor VCB switchgear should have internal arc test conducted at CPRI 21.2. Temperature rise test on breaker and panel together. For this test, the test set up shall include three panels with breakers, the test breaker and panel being placed in the center. The adjacent panels shall also be loaded to their current capacity. Alternatively the test panel may be suitably insulated at the sides, which will be adjoining to other panels in actual site configuration. .. 21.3. . Switching over-voltage test as per clause 3.2(b) on each rating of breaker. a. Measurement of resistance of main circuit. b. Mechanical eduranc4e test on breaker. c. Mechanical operation test. Viii). Short circuit withstand test of earthing device (Truck / Switch). 21.4. For all the important components like instrument transformers, relays, instruments, switches, bushing, wires, insulators, timers, annunciation, terminal blocks and fuses etc. the contractor shall furnish satisfactory type test reports for Employer‘s approval. Such reports cover all applicable type test listed in relevant Indian Standards, for all components of type and rating being supplied. 22.0 COMMISSIONING CHECKS / TESTS 22.1. After installation of panels, power and control wiring and connect contractor shall perform commissioning checks as listed below to proper operation of switchgear / panels and correctness of all respects. 22.2. GENERAL a). Check name plate details according to specification. b). Check for physical damage. c). Check tightens of all bolts, clamps and connecting terminal. d). Check earth connections. e). Check cleanliness of insulators and bushings. f). Check heaters are provided. g). H.V. test on complete switchboard with CT & breaker / contractor lubricated in position. h). Check all moving parts are properly lubricated. i). Check all alignment of bus bars with the insulators to ensure alignment and fitness of insulators. j). Check for inter changeability of breakers. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 132 Technical Specification k). Check continuity and IR value of space heater. l). Check earth continuity of the complete switchgear board. 22.3. CIRCUIT BREAKER a). Check alignment of trucks for free movement . b). Check correct operation of shutters. c). Check show closing operation (if provided). d). Check control wiring for correctness of corrections, continuity and IR values. e). Manual operation of breakers completely assembled. f). Power closing / opening operation manually and electrically at extreme condition of control supply voltage. g). Closing and tripping time. h). Trip free and anti-pumping operation. i). IR values, resistance and minimum pick up voltage of coils. j). Simultaneous closing of all the three phases. k). Check electrical and mechanical inter locks provided. l). Checks on spring charging motor, correct operation of limit switches and time of charging. m). Check vacuum (as applicable). n). All functional checks Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 133 Technical Specification 3.7 1.0 1.1. 1.2. 1.3. 2.0 2.1. 2.2. 2.3. 3.0 3.1. 3.2. 3.3. 3.4. 3.5. 3.6. TECHNICAL SPECIFICATION FOR 33KV & 11 KV ISOLATORS SCOPE This section of the specification is intended to cover design specifications for manufacture and testing of 33 KV and 11 KV gang operated switch (Isolators) with all fittings and accessories. The Isolators are for outdoor installation suitable for horizontal/vertical mounting on mounting structures and for use at sub-stations. Isolators shall be supplied with Earth Switch as and where specified. GENERAL The Isolators and accessories shall conform in general to IS 9921 (or IEC: 62271-102) except to the extent explicitly modified in specification. All isolating switches and earthing switches shall have rotating blades and pressure releasing contacts. All isolating and earth switches shall operate through 90 angle from closed position to fully open position. Complete isolator with all the necessary items for successful operation shall be supplied including but not limited to the following: (i). Isolator assembled with complete base frame, linkages, operating mechanism, control cabinet, interlocks etc. (ii). All necessary parts to provide a complete and operable isolator installation, control parts and other devices whether specifically called for herein or not. (iii). The isolator shall be designed for use in the geographic and meteorological conditions as given in Section 1. DUTY REQUIREMENTS Isolators and earth switches shall be capable of withstanding the dynamic and thermal effects of the maximum possible short circuit current of the systems in their closed position. They shall be constructed such that they do not open under influence of short circuit current. The earth switches, wherever provided, shall be constructionally interlocked so that the earth switches can be operated only when the isolator is open and vice versa. The constructional interlocks shall be built in construction of isolator and shall be in addition to the electrical and mechanical interlocks provided in the operating mechanism. In addition to the constructional interlock, isolator and earth switches shall have provision to prevent their electrical and manual operation unless the associated and other interlocking conditions are met. All these interlocks shall be of failsafe type. Suitable individual interlocking coil arrangements shall be provided. The interlocking coil shall be suitable for continuous operation from DC supply and within a variation range as stipulated elsewhere in this specification. The earthing switches shall be capable of discharging trapped charges of the associated lines. The isolator shall be capable of making/breaking normal currents when no significant change in voltage occurs across the terminals of each pole of isolator on account of make/break operation. The isolator shall be capable of making/breaking magnetising current of 0.7A at 0.15 power factor and capacitive current of 0.7A at 0.15 power factor at rated voltage. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 ………………… Assam Power Distribution Company Ltd. 134 Technical Specification 4.0 CONSTRUCTIONAL DETAILS 4.1. All isolating switches and earthing switches shall have rotating blades and pressure releasing contacts. All isolating and earth switches shall operate through 90 angle from closed position to fully open position. 4.2. Contacts: a) The contacts shall be self-aligning and self-cleaning and so designed that binding cannot occur after remaining closed for prolonged periods of time in a heavily polluted atmosphere. b) No undue wear or scuffing shall be evident during the mechanical endurance tests. Contacts and spring shall be designed so that readjustments in contact pressure shall not be necessary throughout the life of the isolator or earthing switch. Each contact or pair of contacts shall be independently sprung so that full pressure is maintained on all contacts at all time. c) Contact springs shall not carry any current and shall not lose their characteristics due to heating effects. d) The moving contact of double break isolator shall have turn-and -twist type or other suitable type of locking arrangement to ensure adequate contact pressure. 4.3. Blades: a) All metal parts shall be of non-rusting and non-corroding material. All current carrying parts shall be made from high conductivity electrolytic copper/aluminium. Bolts, screws and pins shall be provided with lock washers. Keys or equivalent locking facilities if provided on current carrying parts, shall be made of copper silicon alloy or stainless steel or equivalent. The bolts or pins used in current carrying parts shall be made of noncorroding material. All ferrous castings except current carrying parts shall be made of malleable cast iron or cast-steel. No grey iron shall be used in the manufacture of any part of the isolator. b) The live parts shall be designed to eliminate sharp joints, edges and other corona producing surfaces, where this is impracticable adequate corona shield shall be provided.. c) Isolators and earthing switches including their operating parts shall be such that they cannot be dislodged from their open or closed positions by short circuit forces, gravity, wind pressure, vibrations, shocks, or accidental touching of the connecting rods of the operating mechanism. d) The switch shall be designed such that no lubrication of any part is required except at very infrequent intervals i.e. after every 1000 operations or after 5 years whichever is earlier. 4.4. Insulators: a) The insulator shall conform to IS: 2544 and/or IEC-60168. The insulators shall have a minimum cantilever strength of 400 Kgs. for 33/11 kV insulators respectively. b) Pressure due to the contact shall not be transferred to the insulators after the main blades are fully closed. 4.5. Base: Each isolator shall be provided with a complete galvanised steel base provided with holes and designed for mounting on a supporting structure. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 135 Technical Specification 5.0 EARTHING SWITCHES 5.1. Where earthing switches are specified these shall include the complete operating mechanism and auxiliary contacts. 5.2. The earthing switches shall form an integral part of the isolator and shall be mounted on the base frame of the isolator. 5.3. The earthing switches shall be constructionally interlocked with the isolator so that the earthing switches can be operated only when the isolator is open and vice versa. The constructional interlocks shall be built in construction of isolator and shall be in addition to the electrical interlocks. Suitable mechanical arrangement shall be provided for de-linking electrical drive for mechanical operation. 5.4. Each earth switch shall be provided with flexible copper/aluminum braids for connection to earth terminal. These braids shall have the same short time current carrying capacity as the earth blade. The transfer of fault current through swivel connection will not be accepted. 5.5. The frame of each isolator and earthing switches shall be provided with two reliable earth terminals for connection to the earth mat. 5.6. Isolator design shall be such as to permit addition of earth switches at a future date. It should be possible to interchange position of earth switch to either side. 5.7. The earth switch should be able to carry the same fault current as the main blades of the Isolators and shall withstand dynamic stresses. 6.0 6.1. 6.2. 6.3. 7.0 7.1. 7.2. 7.3. 7.4. OPERATING MECHANISM The bidder shall offer manual operated Isolators and earth switches.. Control cabinet/operating mechanism box shall be made of aluminum sheet of adequate thickness (minimum 3 mm). Gear should be of forged material suitably chosen to avoid bending/jamming on operation after a prolonged period of non-operation. Also all gear and connected material should be so chosen/surface treated to avoid rusting. OPERATION The main Isolator and earth switches shall be gang operated. The design shall be such as to provide maximum reliability under all service conditions. All operating linkages carrying mechanical loads shall be designed for negligible deflection. The length of inter insulator and interpole operating rods shall be capable of adjustments, by means of screw thread which can be locked with a lock nut after an adjustment has been made. The isolator and earth switches shall be provided with ―over center‖ device in the operating mechanism to prevent accidental opening by wind, vibration, short circuit forces or movement of the support structures. Each isolator and earth switch shall be provided with a manual operating handle enabling one man to open or close the isolator with ease in one movement while standing at ground level. Detachable type manual operating handle shall be provided. Suitable provision shall be made inside the operating mechanism box for parking the detached handles. The provision of manual operation shall be located at a height of 1000 mm from the base of isolator support structure. The isolator shall be provided with positive continuous control throughout the entire cycle of operation. The operating pipes and rods shall be sufficiently rigid to maintain positive control under the most adverse conditions and when operated in tension or compression for isolator closing. They shall also be capable of withstanding all torsional and bending stresses due to operation of the isolator. Wherever supported the operating rods shall be provided with bearings on either ends. The operating rods/ pipes shall be provided with suitable Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 136 Technical Specification universal couplings to account for any angular misalignment. 7.5. All rotating parts shall be provided with grease packed roller or ball bearings in sealed housings designed to prevent the ingress of moisture, dirt or other foreign matter. Bearings pressure shall be kept low to ensure long life and ease of operation. Locking pins wherever used shall be rustproof. 7.6. Signaling of closed position shall not take place unless it is certain that the movable contacts, have reached a position in which rated normal current, peak withstand current and short time withstand current can be carried safely. Signaling of open position shall not take place unless movable contacts have reached a position such that clearance between contacts is atleast 80% of the isolating distance. 7.7. The position of movable contact system (main blades) of each of the Isolators and earthing switches shall be indicated by a mechanical indicator at the lower end of the vertical rod of shaft for the Isolators and earthing switch. The indicator shall be of metal and shall be visible from operating level. 7.8. The contractor shall furnish the following details along with quality norms, during detailed engineering stage. (i) Current transfer arrangement from main blades of isolator along with millivolt drop immediately across transfer point. (ii) Details to demonstrate smooth transfer of rotary motion from motor shaft to the insulator along with stoppers to prevent over travel. 8.0 TEST AND INSPECTION 8.1. The switches shall be subjected to the following type test in accordance to with 8.2. 8.3. IS: 9920. I) Dielectric test (impulse and one minute) power frequency withstands voltage. II) Temperature rise test III) Rated off load breaking current capacity IV) Rated active load breaking capacity V) Rated line charging breaking capacity VI) Rated short time current VII) Rated peak withstand current VIII) Mechanical and Electrical Endurance The equipment shall be subjected to the following routine test. I) Power frequency voltage dry test II) Measurement of resistance of the main circuit III) Operating test. The porcelain will have pull out test for embedded component and beam strength of porcelain base. 9.0 CONNECTORS 9.1. Each isolator shall be provided with appropriate number of bimetallic clamping type connectors as detailed in the schedule of requirement. The maximum length of jumper that may be safely connected or any special instruction considered necessary to avoid under loads on the post isolators should be stated by the tenderer. 10.0 SUPPORTING STRUCTURES Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 137 Technical Specification 10.1. All isolators and earthing switches shall be rigidly mounted in an upright position on their own supporting structures. Details of the supporting structures shall be furnished by the successful tenderer. The isolators should have requisite fixing details ready for mounting them on switch structures. 11.0 PRE-COMMISSIONING TESTS 11.1. Contractor shall carry out following tests as pre-commissioning tests. Contractor shall also perform any additional test based on specialties of the items as per the field instructions of the equipment Supplier or Employer without any extra cost to the Employer. The Contractor shall arrange all instruments required for conducting these tests along with calibration certificates and shall furnish the list of instruments to the Employer for approval. (a) Insulation resistance of each pole. (b) Manual operation and interlocks. (c) Insulation resistance of control circuits and motors. (d) Ground connections. (e) Contact resistance. (f) Proper alignment so as to minimise to the extreme possible the vibration during operation. (g) Measurement of operating Torque for isolator and Earth switch. (h) Resistance of operating and interlocks coils. (i) Functional check of the control schematic and electrical & mechanical interlocks. (j) 50 operations test on isolator and earth switch. 12.0 TECHNICAL DATA SHEET FOR ISOLATORS SL Technical Particulars Isolators class No. 33 kV 11kV 1 Nominal system voltage, kV 33 11 2 Highest system voltage, kV 36 12 3 Rated frequency, Hz. 50 50 4. Type of Isolator Double Break, Double Break, center pole center pole rotating rotating 5 Rated continuous current, A 630 630/400 A 6 Rated short time current, kA 25 16 for 3sec 7 Rated duration of short time 3 3 current, Second 8 Rated lightning impulse withstand voltage, kV (peak) i) To earth & between poles 170 95 ii) Across isolating distance 170 95 9 Rated 1 minute power frequency withstand voltage, kV (rms) 70 28 i) To earth & between poles 80 40 ii) Across isolating distance 10 Minimum creepage distance of insulators, mm 900 400 11 Temperature rise As per relevant IS Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 138 Technical Specification 3.8 TECHNICAL SPECIFICATION OF OUTDOOR CURRENT AND POTENTIAL TRANSFORMERS 1.0 SCOPE OF CONTRACT 1.1. This Section of the Specification covers general requirements for design, engineering, manufacture, assembly and testing at manufacturer‘s works of 33kV and 11 kV outdoor Current and Potential Transformers. 2.0 STANDARDS 2.1. The equipment covered by this specification shall, unless otherwise stated be designed, constructed and tested in accordance with the latest revisions of relevant Indian Standards and shall conform to the regulations of local statutory authorities. 2.2. In case of any conflict between the Standards and this specification, this specification shall govern. 2.3. The current transformer shall comply also with the latest issue of the following Indian standard. (i) IS: 2705(Part- Current transformers: General requirement. I) (ii) IS: 2705(Part- Current transformers : Measuring Current II) transformers (iii) IS: 2705(Part- Current transformers : Protective Current III) transformers (iv) IS: 2705(Part- Current transformers: Protective Current IV) transformers for special purpose application. (v) IS: 3156(Part- Potential transformers: General requirement. I) (vi) IS: 3156 (Part- Potential transformers : Measuring Potential II) transformers (vii) IS: 3156 (Part- Potential transformers : Protective Potential III) transformers 3.0 GENERAL REQUIREMENTS 3.1. The cores of the instrument transformers shall be of high grade, non-aging CRGO steel of low hysteresis loss and high permeability. 3.2. Instrument transformers shall be of Dead Tank design or Live Tank design. 3.3. The instrument transformers shall be truly hermetically sealed POLYCRETE Type 3.4. A complete leak proof secondary terminal arrangement shall be provided with each instrument transformers, secondary terminal shall be brought into weather, dust and vermin proof terminal box. Secondary terminal boxes shall be provided with facilities for easy earthing, shorting, insulating and testing of secondary circuits. The terminal boxes shall be suitable for connection of control cable gland. 3.5. All instrument transformers shall be of single phase unit. 3.6. The instrument transformers shall be so designed to withstand the effects of temperature, wind load, short circuit conditions and other adverse conditions. 3.7. All similar parts, particularly removable ones, shall be interchangeable with one another. 3.8. All cable ferrules, lugs, tags, etc. required for identification and cabling shall be supplied complete for speedy erection and commissioning as per approved schematics. 3.9. The instrument transformers shall be designed to ensure that condensation Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 139 Technical Specification of moisture is controlled by proper selection of organic insulating materials having low moisture absorbing characteristics. 3.10. All steel work shall be degreased, pickled and phosphated and then applied with two coats of Zinc Chromate primer and two coats of finishing synthetic enamel paint. 4.0 COMMON MARSHALLING BOXES 4.1. The outdoor type common marshalling boxes shall conform to the latest edition of IS 5039 and other general requirements specified hereunder. 4.2. The common marshalling boxes shall be suitable for mounting on the steel mounting structures of the instrument transformers. 4.3. One common marshalling box shall be supplied with each set of instrument transformers. The marshalling box shall be made of sheet steel and weather proof. The thickness of sheet steel used shall be not less than 3.0 mm. It is intended to bring all the secondary terminals to the common marshalling. 4.4. The enclosures of the common marshalling boxes shall provide a degree of protection of not less than IP 55 (As per IS 2147). 4.5. The common marshalling boxes shall be provided with double hinged front doors with pad locking arrangement. All doors and removable covers and plates shall be sealed all around with neoprene gaskets or similar arrangement. 4.6. Each marshalling box shall be fitted with terminal blocks made out of moulded non-inflammable plastic materials and having adequate number of terminals with binding screws washers etc. Secondary terminals of the instrument transformers shall be connected to the respective common marshalling boxes. All out going terminals of each instrument transformer shall terminate on the terminal blocks of the common marshalling boxes. The terminal blocks shall be arranged to provide maximum accessibility to all conductor terminals. 4.7. Each terminal shall be suitably marked with identification numbers. Not more than two wires shall be connected to any one terminal. At least 20 % spare terminals shall be provided over and above the required number. 4.8. All terminal strips shall be of isolating type terminals and they will be of minimum 10 A continuous current rating. 4.9. All cable entries shall be from bottom. Suitable removable gland plate shall be provided on the box for this purpose. Necessary number of cable glands shall be supplied fitted on to this gland plate. Cable glands shall be screw on type and made of brass. 4.10. Each common marshalling box shall be provided with two numbers of earthing terminals of galvanised bolt and nut type. 4.11. All steel, inside and outside work shall be degreased, pickled and phosphated and then applied with two coats of Zinc Chromate primer and two coats of finishing synthetic enamel paint. The colour of finishing paint shall be as follows: 4.12. i) Inside: Glossy White 4.13. ii) Outside: Light Grey (Shade No. 697 of IS: 5) 5.0 TESTS 5.1. Routine/Acceptance Tests (all units) 5.2. All routine tests shall be carried out in accordance with relevant Standards. All routine/acceptance tests shall be witnessed by the Employer/his authorised representative. 5.3. Type Tests: The bidder shall furnish type test certificates and results for the all tests as per relevant Standards along with the bid for current and potential transformers of identical design. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 140 Technical Specification 5.4. Type test certificates so furnished shall not be older than 5 (five) years as on date of Bid opening. 6.0 NAME PLATES 6.1. All equipment shall have non-corrosive name plates fix at a suitable position indelibly mark with full particular there on in accordance with the standard adapted. 7.0 MOUNTING STRUCTURES 7.1. All the equipment covered under this specification shall be suitable for mounting on steel structures. Supply of mounting structures is also in the scope of this tender. 7.2. Each equipment shall be furnished complete with base plates, clamps, and washers etc. and other hardware ready for mounting on existing steel structures. 8.0 SAFETY EARTHING 8.1. The non-current carrying metallic parts and equipment shall be connected to station earthing grid. For this two terminals suitable for 40mm X 10mm GI strip shall be provided on each equipment. 9.0 TERMINAL CONNECTORS 9.1. The equipment shall be supplied with required number of terminal connectors of approved type suitable for ACSR/XLPE cable. The type of terminal connector, size of connector, material, and type of installation shall be approved by the Employer, as per installation requirement while approving the equipment drawings. 10.0 PRE-COMMISSIONING TESTS 10.1. Contractor shall carry out following tests as pre-commissioning tests. Contractor shall also perform any additional test based on specialties of the items as per the field instructions of the equipment Supplier or Employer without any extra cost to the Employer. The Contractor shall arrange all instruments required for conducting these tests along with calibration certificates and shall furnish the list of instruments to the Employer for approval. 10.2. Current Transformers (i) Insulation Resistance Test for primary and secondary. (ii) Polarity test. (iii) Ratio identification test - checking of all ratios on all cores by primary injection of current. (iv) Dielectric test of oil (wherever applicable). (v) Magnetising characteristics test. (vi) Tan delta and capacitance measurement (vii) Secondary winding resistance measurement (viii) Contact resistance measurement (wherever possible/accessible). 10.3. 11.0 Potential Transformers (i) Insulation Resistance test for primary (if applicable) and secondary winding. (ii) Polarity test. (iii) Ratio test (iv) Dielectric test of oil (wherever applicable). (v) Tan delta and capacitance measurement of individual capacitor stacks. (vi) Secondary winding resistance measurement. TECHNICAL DATA Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 SHEET FOR CURRENT Assam Power Distribution Company Ltd AND 141 Technical Specification POTENTIALTRANSFORMERS 11.1. For 33 kV/11kV CTs the instrument security factor at all ratios shall be less than 2.5 for metering core. 11.2. TYPE AND RATING: All instrument transformer shall be outdoor type, single phase, polycrete type suitable for mounting on steel structure. The instrument transformer shall have the following ratings and particulars. Item SL Ratings and Particulars No 33 KV 11 KV . A Nominal system voltage 33 kV 11 kV B Highest system voltage, kV 36 12 C Rated frequency ,HZ 50 50 D System earthing Solidly earth Solidly earth E Insulation level a) Impulse withstand voltage: kVp 170 70 b) One minute p.f. Withstand voltage, kV 70 28 (r.m.s.) F Short time current for one second, kA 16 12.5 G Minimum creepage distance, mm 900 360 H Temperature rise As per ISS As per ISS J TRANFORMER C.T. (i) No. of Cores 3 3 (ii) Transformation ratio 200-100/5-5- 600-300/5-5-2.89A 5A (iii) Rated out put (a) Core-1 30 VA 30 VA (b) Core-2 15 VA 15VA (C) Core-3 (iv) Accuracy class (a) Core-1 0.5 0.5 (b) Core-2 5P 5P (C) Core-3 PS PS (v) Accuracy limit factor (a) Core-1 (b) Core-2 10 10 (C) Core-3 (v) Instrument security factor (a) Core-1 Less than 5 Less than 5 (b) Core-2 (C) Core-3 (v) Minimum Knee point voltage, Volts (C) Core-3 100 Volts 100volts FEEDER CT (i) No. of Cores 2 2 (ii) Transformation ratio 400-200/5-5-5 400-200/5-5 (iii) Rated out put (a) Core-1 30 VA 30 VA (b) Core-2 15 VA 15 VA Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 142 Technical Specification Item SL No . (iv) Accuracy class (a) Core-1 (b) Core-2 (v) Accuracy limit factor (a) Core-1 (b) Core-2 (v) Instrument security factor (a) Core-1 (b) Core-2 POTENTIAL TRANSFORMER (a) Core Burden Ratings and Particulars 33 KV 11 KV 0.5 5P 0.5 5P 10 10 <=5 33kV/√3 /110V/√3 30 VA <=5 11kV/√3 /110V/√3 30 VA (b) Accuracy class 0.5 05 (c) Rated voltage factor 1.2 1.2 Note: (i) It is intended to use different ratios of the same CT at the same time for differential protections and metering cores. The CTS should therefore be suitable for the above purpose by secondary tapings only. The ratio change by secondary taps is acceptable as long as the required CT specifications are achieved at all ratios. (ii) The knee point voltage specified above shall be at higher ratio/ taps. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 143 Technical Specification 3.9 TECHNICAL SPECIFICATION FOR 33kV & 11kV LIGHTNING ARRESTORS 1.0 2.0 SCOPE This Section covers the specifications for design, manufacture, shop & laboratory testing before despatch of 33 kV and 11 kV 10 kA, Station class heavy duty, gapless metal (zinc) oxide Surge Arrestors complete with fittings & accessories. 3.0 STANDARDS The design, manufacture and performance of Surge Arrestors shall comply with IS: 3070( Part-3 )/1993 unless otherwise specifically specified in this Specification 4.0 GENERAL REQUIREMENT The surge arrestor shall draw negligible current at operating voltage and at the same time offer least resistance during the flow of surge current. The surge arrestor shall consist of non-linear resistor elements placed in series and housed in electrical grade porcelain housing/silicon polymeric of specified creepage distance. The assembly shall be hermetically sealed with suitable rubber gaskets with effective sealing system arrangement to prevent ingress of moisture. The surge arrestor shall be provided with line and earth terminals of suitable size. The ground side terminal of surge arrestor shall be connected with 25x6 mm galvanized strip, one end connected to the surge arrestor and second end to a separate ground electrode. The bidder shall also recommend the procedure which shall be followed in providing the earthing/system to the Surge Arrestor. The surge arrestor shall not operate under power frequency and temporary over voltage conditions but under surge conditions, the surge arrestor shall change over to the conducting mode. The surge arrestor shall be suitable for circuit breaker performing 0-0.3sec.-CO-3minCO- duty in the system. Surge arrestors shall have a suitable pressure relief system to avoid damage to the porcelain/ silicon polymeric housing and providing path for flow of rated fault currents in the event of arrestor failure. The reference current of the arrestor shall be high enough to eliminate the influence of grading and stray capacitance on the measured reference voltage. The Surge Arrestor shall be thermally stable and the bidder shall furnish a copy of thermal stability test with the bid. The arrestor shall be capable of handling terminal energy for high surges, external pollution and transient over voltage and have low losses at operating voltages. 5.0 ARRESTOR HOUSING The arrestor housing shall be made up of silicon polymeric housing and shall be homogenous, free from laminations, cavities and other flaws of imperfections that might affect the mechanical and dielectric quality. The housing shall be of uniform brown colour, free from blisters, burrs and other similar defects. Arrestors shall be complete with insulating bases, surge counters with leakage current meters (33 KV LA) and terminal connectors. The housing shall be so coordinated that external flashover shall not occur due to application of any impulse or switching surge voltage up to the maximum design value for arrestor. The arrestors shall not fail due to contamination. The arrester housings shall be designed for pressure relief class as given in Technical Parameters of the specification. Sealed housings shall exhibit no measurable leakage. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 144 Technical Specification 6.0 FITTINGS & ACCESSORIES The surge arrestor shall be complete with insulating bases, surge counters with leakage current meters (for 33 KV LA) and terminal connectors. The terminals shall be non-magnetic, corrosion proof, robust and of adequate size and shall be so located that incoming and outgoing connections are made with minimum possible bends. The top metal cap and base of surge arrestor shall be galvanized. The line terminal shall have a built in clamping device which can be adjusted for both horizontal and vertical takeoff. 7.0 SURGE MONITOR A self-contained discharge counter suitably enclosed for outdoor use and requiring no auxiliary or battery supply for operation shall be provided for each single pole unit. Leakage current meter with suitable scale range to measure leakage current of surge arrestor shall also be supplied within the same enclosure. The number of operations performed by the arrestor shall be recorded by a suitable cyclometric counter and surge monitor shall be provided with an inspection window. There shall be a provision for putting ammeter to record the current/alarm contacts in the control room if the leakage current exceeds the permitted value. Similar provision shall be considered for surge counter also. Surge monitor shall be mounted on the support structure at a suitable height so that the reading can be taken from ground level through the inspection window and length of connecting leads up to grounding point and bends are minimum. Surge monitor shall have to be provided for 33 KV class only. 8.0 TESTS Test on Surge Arrestors The Surge Arrestors offered shall be type tested and shall be subjected to routine and acceptance tests in accordance with IS: 3070 (Part-3). In addition, the suitability of the Surge Arrestors shall also be established for the following: - Residual voltage test Reference voltage test Leakage current at M.C.O.V P.D. test Sealing test Thermal stability test Aging and Energy capability test Watt loss test Each metal oxide block shall be tested for guaranteed specific energy capability in addition to routine/acceptance test as per IEC/IS. The surge arrestor housing shall also be type tested and shall be subjected to routine and acceptance tests in accordance with IS: 2071. Galvanization Test All Ferrous parts exposed to atmospheric condition shall have passed the type tests and be subjected to routine and acceptance tests in accordance with IS: 2633 & IS 6745. 9.0 NAME PLATE The name plate attached to the arrestor shall carry the following information: Rated Voltage Continuous Operation Voltage Normal discharge current Pressure relief rated current Manufacturers Trade Mark Name of Sub-station Year of Manufacturer Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 145 Technical Specification Name of the manufacture Purchase Order Number along with date 10.0 11.0 PRE-COMMISSIONING TESTS Contractor shall carry out following tests as pre-commissioning tests. Contractor shall also perform any additional test based on specialties of the items as per the field instructions of the equipment Supplier or Employer without any extra cost to the Employer. The Contractor shall arrange all instruments required for conducting these tests along with calibration certificates and shall furnish the list of instruments to the Employer for approval. 1. Operation check of LA counters. 2. Insulation resistance measurement. 3. Capacitance and Tan delta measurement of individual stacks. 4. Third harmonic resistive current measurement (to be conducted after energisation. TYPE AND RATINGS SL No. 1 2 3 4 5 6 7 9 10 Particulars Rated voltage of arrester, kV Rated frequency, Hz Nominal discharge current of arrester, kA Maximum residual voltage at nominal discharge current, kV (peak) Maximum steep current impulse residual voltage at kV (kVP) One minute power frequency withstand voltage of arrester insulation, kV (rms) 1.2 / 50 second impulse withstand voltage of arrester insulation, kV (peak) Line discharge class Insulator Housing a) Power frequency withstand test voltage (wet) (kV rms) b) Lightning impulse withstand tests voltage(KVp) c) Pressure Relief Class d) Creepage distance not less than (mm) Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Voltage class 33 kV 11 kV 30 9 50 50 10 10 108 40 130 50 70 28 170 95 2 2 70 28 170 95 40 900 40 400 Assam Power Distribution Company Ltd 146 Technical Specification 3.10 TECHNICAL SPECIFICATION OF 33 KV AND 11 KV GANG OPERATED SWITCH 1.0 SCOPE 1.1. This specification is intended to cover design manufacture, testing at manufacturer‟s works, transport to site, insurance, storage, erection and commissioning of 33 KV and11 KV gang operated switch (Isolators) with all fittings and accessories. 1.2. The Isolators are for outdoor installation suitable for both vertically and horizontally mounting on mounting structures or M.S. Channel and for use at sectionalizing/tapping points of 33 KV lines and at 33/11 KV substations. 1.3. 33 KV isolators shall be supplied with Earth Switch as and where specified 1.4. The successful bidders shall supply the necessary drawings and instructions for installation and commissionning of the Isolators. 2.0 CONSTRUCTIONAL DETAILS 2.1. The vertically mounted gang switches shall be manually operated triple pole type with single break operation. The operation of the equipment shall be through forward and backward motion of the mid-pole post insulator. The contacts shall be made of silver faced hard drawn copper. 2.2. The horizontally mounted switches, with or without earth switches shall have rotating blade features and pressure reliving features. Such isolators are required to be double break; three posts per phase, single through, gang operated three phase type. All isolators with/without earth switch shall operate through 900 from their fully closed position to fully open position 2.3. The switch shall be fitted with arcing horns and the horns shall be easily replaceable. All isolators shall be provided with suitably rated terminal connectors to directly receive ACSR conductor of required size. The termination shall have at least 3 pairs of holes to hold the conductor tight with nuts & bolts The terminals shall conform to all the test requirements of IS: 5561 and shall be designed as to avoid bimetallic corrosion. 2.4. The operating rod shall comprise of not less than 40 mm (nominal bore) Galvanised steel pipe as per IS 1161-1979. The length of the operating rod shall be suitable for operation as per installation methods. The rod shall be so threaded that the length can be adjusted. 2.5. The horizontal operation shaft shall be of solid Galvanised steel of square section suitable for fitting the insulator base of the switch. Length of the rod shall be such as to maintain the phase clearance as per I.S. 2.6. The operating handle shall have OFF/ON locking arrangement and provision for earthing the equipment. 2.7. The gang operating switch shall be provided with three post insulators per phase conforming to IS 5350 (Pt-III)-1971. The cast iron post shall be embedded in the insulators with sulphur cement. For embedded components, pull out strength should be such as to result in breakings of the porcelain insulators, the beam strength shall be as per relevant T.S. Creepage distance shall not be less than 900 mm and 300 mm for 33KV and 11 KV isolators respectively. 2.8. All similar materials and removable parts of similar equipments shall be Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 147 Technical Specification interchangeable with each other. 3.0 3.1. APPLICABLE STANDARD Unless otherwise stipulated in this specification, the Gang operated switch shall conform to IS. 9920 (Pt-I to Pt-IV). 4.0 Failure to meet guarantees and requirement of specification 4.1. If after installation, the operation of the switch proven to be unsatisfactory, to the purchaser, the tenderer shall have to take back or replace. 5.0 TEST AND INSPECTION 5.1. The switches shall be subjected to the following type test in accordance to with IS: 9920. IX) Dielectric test (impulse and one minute) power frequency withstands voltage. X) Temperature rise test XI) Rated off load breaking current capacity XII) Rated active load breaking capacity XIII) Rated line charging breaking capacity XIV) Rated short time current XV) Rated peak withstand current XVI) Mechanical and Electrical Endurance 5.2. The equipment shall be subjected to the following routine test. IV) Power frequency voltage dry test V) Measurement of resistance of the main circuit VI) Operating test. 5.3. The porcelain will have pull out test for embedded component and beam strength of porcelain base. 5.4. The manufacturer shall afford the inspection representing the purchaser or third party nominee all reasonable facilities, with charge, to satisfy him that the material is being furnished in accordance with this specification. The purchaser has the right to have the test carried out at his own cost by an independent agency whenever there is dispute regarding the quality of supply. 6.0 GUARANTEE The Bidder shall offer equipment performance guarantee for a minimum period of year from the date of commissioning. Any damaged part or defective part of the equipment, the bidder has to replace at his cost. 7.0 TECHNICAL SPECIFICATION Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 148 Technical Specification 1.0 1.1 1.2 1.3 SYSTEM DETAILS Nominal system voltage, KV Highest system voltage, KV Nominal frequency, Hz 2.0 2.1 2.2 2.3 GENERAL SPECIFICATION Rated voltage, KV Rated frequency, Hz Rated normal current, Amp 2.4 Rated lightning impulse withstand voltage i) To earth and between pole, KV 170 75 (Peak) ii) Across the isolating distance, KV 195 (Peak) Power frequency one minute withstand voltage, i) To earth and between pole, KV 70 28 (RMS) 80 ii) Across the isolating distance, KV (RMS) Temperature rise -as per relevant ISRated short time current 3 Sec, KA 25 16 Rated active load break capacity, 400 200 Amps Transformer OFF-Load current 10 10 breaking capacity, Amps Rated line changing breaking 6.3 6.3 capacity, A(rms) Rated Peak withstand current 25 KA 16 Electrical endurance 20 operations for 400 A ,200 operation for 200 A Mechanical endurance 1000 operation Minimum insulator creepage distance, 900 300 mm 2.5 2.6 2.7 2.8 2.9 2.10 2.11 2.12 2.13 2.14 33 36 50 11 12 50 36 50 400 A, 800 12 50 630, 3.11 TECHNICAL SPECIFICATION OF BATTERY BANK Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 149 Technical Specification 1.0 SCOPE This Section of the Specification covers the design, manufacture, and testing at manufacturer‘s work, of stationary type sealed, Valve Regulated Lead Acid Battery Bank, Battery Charger, complete with all required accessories for various Sub-stations. 2.0 BATTERY BANK 2.1 TECHNICAL PARTICULARS OF BATTERY BANK 1. Battery Rating 2. Type of battery 3. Battery specification 4. 5. Manufacturers cell designation No of Cells 6. Cycle life of Battery @ 27⁰ C 7. 8. 9. All efficiency WH Efficiency Self discharge/ Week Max, allowable ambient temp at 10. which cell can safely operate 11. Overall dimension of each cell 12. Overall weight of each cell 13. Recommended Max period of storage 14. Material of container 15. Type of separator 16. Type of +ve & -ve plates 17. Material of rack Method of connection between 18. cells 19. Recommended float charge 20. Recommended boost charge Time required for boost charge 21. from fully discharged condition at 27⁰ C 22. Voltage ripple allowable 23. Type of connectors 110 V-100 Ah to 1.75 ECV at C10 at 27⁰ C Maintenance free valve regulated lead acid (MF-VRLA) battery Batteries conforms to IS 15549:2005 Also conforms to International Standards (I) IEEE 1188 and 1189 (II) BS6290 Part 4/ IEC 896 F 100 P 55 Nos. 2000 cycles for 50 % depth of discharge or 1200 cycles for 80 % depth of discharge Above 90% Above 80 % < 1% of rated capacity 55⁰ C continuously and 70⁰ C short time (107.8 x 198.5 x 477)mm approx. 27 kg approx. 6 months from the date of manufacturing and the batteries shall be stored in covered area at 27⁰ C Polypropylene co-polymer Highly absorbent micro porous spun glass matrix (AGM) Flat pasted Mild steel coated with acid resistance paint Bolted Batteries shall be charged in constant potential mode with current limit Voltage: 2.23-2.25 Volts per cell Current: Recommended- charging current is 45 amps Voltage: 2.3 Volts per cell Current: Recommended- charging current is 45 to 90 amps 9 Hrs for 90 % state of charge (or) 24 hrs for 100 % state of charge < 2% of the RMS value Lead coated heavy duty copper strips 2.1.1 PLATES Positive plates shall be made of flat pasted type using lead-cadmium antimony Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 150 Technical Specification alloy for durability, high corrosion resistant, maintenance free, long life both in cyclic as well as in ,float applications. Negative plates shall be heavy duty, durable flat plate using lead calcium alloy pasted box grid. Negative plates shall be designed to match the life of positive plates and combination of negative and positive plates shall ensure long life, durability and trouble free operation of battery. PLC operated equipment should be deployed for preparation of paste to ensure consistency in paste quality. Conventional / manual type of paste preparation is not allowed. 2.1.2 CONTAINER AND LID The containers and lids shall be made of a special grade polypropylene copolymer plastic material. They shall be sufficiently robust and not liable lo deformation under internal operating pressures and within the temperature range naturally encountered, leak proof, non-absorbent and resistant to the acid with low water vapour permeability. 2.1.3 VENT PLUGS : Each cell shall be equipped with one-way safety valve with opening pressure of 5±1 psi and closing pressure 4±1 psi. The vent plug shall be made with suitable grade of fire retardant plastic material. Each valve opening shall be covered with flame barrier capable in preventing the ingress of flame into the cell interior when the valve opens and hydrogen / oxygen gas mixture is released. 2.1.4 SEPARATORS : Separator shall be made of spun glass, micro porous matrix and shall be resistant to Sulphuric Acid. It shall be capable of keeping the entire electrolyte and shall be electrically insulated. Sufficient separator overlap and PVC shield protection to top and bottom edges of the plates is to be provided to prevent short circuit formation between the edges of adjacent plates. 2.1.5 CONNECTORS : The connectors shall be lead coated copper of suitable size to join the cells. The connectors shall be suitably designed and coated to withstand corrosion due to sulphuric acid. The coating should be adequate and tenacious. All the copper inter cell connectors shall be provided with heal shrinkable sleeves except at the connecting points. 2.1.6 ELECTROLYTE: The electrolyte shall be prepared from the battery grade Sulphuric Acid confirming to ISS: 266. The batteries shall be supplied in factory filled and charged condition. 2.1.7 WATER Water required for preparation of electrolyte shall conform to IS: I069. 2.1.8 PLATE CONNECTION Lugs of plates of like polarity shall be connected by lead burning to a horizontal strap having an upstanding terminal post adopted for connection to external circuit. Strap and post shall be caste with lead alloy. The positive and negative terminal posts shall be clearly marked for unmistakable identification. 2.1.9 BOLTS AND NUTS Nuts and Bolts for connecting the cells shall be of superior grade passivated Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 151 Technical Specification Stainless steel. 2.1.10 TERMINALS Terminals shall be of integral lead terminal with solid copper core with M6 threading for fastening. The junction between terminal posts and cover and between the cover and container shall be hermetically sealed. 2.1.11 BATTERY RACKS Batteries shall be installed on MS racks to be supplied by the Contractor to fit in the battery room. Racks/Trays shall be powder coated with anti corrosive paint. Rack shall accommodate 55 cells plus 2 spares. Racks/Tray shall be suitably treated before painting for protection against fungus growth and other harmful effects due to tropical environment. The colour of the supporting racks shall conform to RAL 7032 shade. a) cy H.V. test / Insulation tests. 3.12 ECHNICAL SPECIFICATION OF STEEL STRUCTURES RS JOIST (GALVENISED) 1.0 SCOPE: 1.1. This specification calls for manufacture, stage testing, inspection and testing before dispatch, packing and delivery of R.S. Joists (Galvenised), 175x85mm and 150x80mm. 1.2. The materials shall conform, in all respect, to the high standard of design and workmanship and shall be capable of performing duties specified herein. Materials offered shall be complete in all respect. 2.0 STANDARDS: 2.1. Materials shall conform to the latest applicable Indian standards. In case bidders offer Steel Section and supports conforming to any other international specifications which shall be equivalent or better than IS, the same is also acceptable. sn 1 Standard IS 2062 IS 2062 IS:1852 Title Specification for R.S. Joists, M.S. Channels, M.S. Angles & M.S. Flats Chemical and physical composition of material Rolling and cutting tolerances for Hot rolled steel products. 2.2. In the paragraph above relevant Indian standards specification have been mentioned. However, the material meeting any other authoritative international standards, which ensures equal or better quality than the standards, mentioned shall also be acceptable. Material for which Indian Standards are not available, the relevant British standards and IEC recommendations will be applicable. Photocopy of all such standards according to which the materials have been offered should be attached. : 3.0 CLIMATIC CONDITIONS: The Steel Sections to be supplied against this specification shall be suitable for satisfactory continuous operation under the following tropical conditions:4.0 LENGTH:4.1. The materials to be supplied shall be in the following lengths: Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 152 Technical Specification 4.2. (i) R.S. Joists 175x85 mm 9 meters to 11 meters (ii) R.S. Joists 150x80 mm 1.5 meters Any tolerance on negative or positive side shall not be accepted. 5.0 CHEMICAL COMPOSITION AND PHYSICAL PROPERTIES OF R.S. JOISTS 5.1. C H E M I C A L C O M P O S I T I O N SN CHEMICAL COMPOSITION FOR Fe 410 WA GRADE C 0.23% MAX. Mn 1.5% MAX S . 0.050% MAX P 0.050% MAX. SI . 0.40% MAX CE 0.42% MAX (Carbon Equivalent) . 5.2. M E C H A N I C A L P R O P E R T I E S SN Tensile strength (min.) 1. 2. 3. 4. 5. 6. 42 Kgf/mm2 or 410 N/mm2 Yield stress Min. for thickness/diameter < 20 mm - 26 kgf/mm2 OR 250 N/mm2 20 – 40 mm - 24 kgf/mm2 OR 240 N/mm2 > 40 mm - 23 kgf/mm2 OR 230 N/mm2 Elongation %( min.) - 23% Bend test (internal Dia) Min-3 t (t – is the thickness of the material) 6.0 MARKING:6.1. It is desirable that the manufacture should put his identification marks on the finished materials. The mark shall be in legible English letters given with marking dies of minimum 18 mm size at the Interval of 3 meter mentioned as ― APDCL‖ 7.0 INSPECTION AND TEST CERTIFICATE: 7.1. The materials to be supplied will be subject to inspection and approval by the representative of Employer. The Bidder is required to offer the finished material for inspection well in advance to the Employer. 7.2. The BILLETS/INGOTS from which materials shall be re-rolled and supplied to us shall be of tested quality as per IS: 2830/6914 (Latest revision) respectively and shall be arranged from their own source. The chemical composition and physical properties of the finished materials shall be as per relevant specification. 7.3. The materials shall be tested in ISI approved Laboratory of the approved Manufacturer having all facilities available for conducting all the tests as Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 153 Technical Specification prescribed in relevant ISS. The Employer may get the material tested in the accredited laboratory by NABL. The testing charges whatsoever shall be to the Bidder‘s account. 7.4. The Bidder is required to specifically indicate that the approved manufacturer:(i) Holds valid ISI License against respective ISS. (ii) That the materials offered shall bear ISI certification marks. (iii) Is required to submit a copy of the valid ISI License clearly indicating size and range of roll-able product against respective ISS. 8.0 GUARANTEED TECHNICAL PARTICULARS OF R.S Joists 8.1. Guaranteed Technical Particulars are to be furnished along with the bid. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 154 Technical Specification 3.13 TECHNICAL SPECIFICATION FOR EXECUTION OF WORK (FOR 33KV AND 11 KV LINES) 1.0 SCOPE : ERECTION OF 33 KV AND LINES WITH 9.75 M PSC POLES The scope covers the survey of the proposed route, tree clearance wherever necessary transport of materials to the locations, erection of the line testing of the line and handing over to the APDCL as per specification. Materials such as steel, cement, PSC Poles, top cleats, clamps, washers, earth wires, HBG metal, sand, water, cost of bolts and nuts etc., as given in Annexure-1 are to be procured by the contractor cost of which shall be included in the bid. 1.1 General : The Contractor should be well acquainted with the IE Rules 1956 as amended from time to time and with the Indian Telegraph Act 1889 so that necessary provisions therein may be followed. 1.2 ELECTRICAL CLEARANCE As per Indian Electricity Rules, 1956 ( amended version ) Sl. Particulars 33 KV line No. 1 Minimum height of any 6.4 metres conductor of an overhead line across any street 2 Minimum height of any 6.1 metres conductor of an overhead line along any street 3 Minimum height of any 5.2 metres conductor (bare )of an overhead line erected elsewhere 4 Minimum height of any 4.0 metres conductor (insulated )of an overhead line erected elsewhere 5 Minimum Clearance of an 3.7mtr. (vertical ) overhead line from building 2.0 mtr. ( horizontal) 6 Clearance between over-head 2.130 meters line and communica-tion line 7 Minimum Clearance from 0.270 meters another line 8 Phase to phase clearance ( 1370 mm min) 9 Span 50 m 10 Minimum clearance between 6.1 LT line with 11 KV & 33 KV 1.3 11 KV Lines 6.2 SURVEY OF THE ROUTE The Tentative route map of the line to be erected will be furnished by the APDCL to the Contractor along with the copy of the concluded agreement. The Contractor is required to carry out the detailed survey of the route of the line and fix up the locations at the average span indicated in the schedule and mark the Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 155 Technical Specification locations and submit a detailed route map to the Engineer in charge of the work within 30 days for approval. In the course of surveying by the contractor, any conspicuous variations in the change and physical feature to those indicated in the route map and as actually existing are noticed, the deviations must be brought to the notice of the APDCL Engineer. The APDCL Engineer if considered necessary shall make alterations, which shall be carried out accordingly and the APDCL after inspecting the surveyed route and the revised route map shall be given for final approval in writing. The contractor shall not commence the work until the final approval of the route map is given by the Engineer in charge in writing to the contractor. 1.4 WAY LEAVES AND TREE CUTTINGS Proposals for way leaves and right of way shall be submitted by the contractor. Permission will be obtained by the APDCL within reasonable time for which due notice shall be given by the Contractor. The Contractor shall arrange for tree cutting or tree branches cutting also. The widths of tree clearance to be adopted for lines of various voltages are as detailed below: 1.4.1 33 KV LINE (Trunk Line) All growth within 6.096 M (20 ft) from the center line of support and all trees which may fall and foul the line. 1.4.2 The Contractor shall take all possible steps to see that standing crops, etc. are not damaged while attending to tree cutting. When such damage is inevitable the compensation will be borne by the APDCL provided the damage is with the prior concurrence of the Engineer. The Contractor shall bear the compensation for damage caused by the gangs without prior concurrence of the Engineer concerned. 1.4.3 No trees shall be cut until the APDCL has made necessary arrangement with the authorities concerned and permission is given to the Contractor to fell such trees. The contractor shall arrange to remove the obstacles as soon as possible. 1.4.4 At such times, when it may not possible for APDCL, to arrange right-of-way for excavation of pole pits or erecting the poles of stringing the line, then at all such times, the contractor shall shift his gangs to other areas. The rates quoted shall cover all such contingencies and no extra payments shall be claimed for such contingencies. 1.5 EXCAVATION OF POLE PITS, STAY PITS AND D.P. PITS 1.5.1 After the final survey of the line and after marking the pole locations with pegs, excavation work has to be commenced in accordance to the approved route map. Excavation is generally done by pick axes, crow V-bars and showers although some times earth augers are used. Excavation of pole pits in very hard or rocky soil or in rock beds, may involve blasting with suitable explosives. The pits for the supports are excavated in the direction of the line as this will facilitate the erection of support are excavated in the direction of the line as this will facilitate the erection of support, in addition to giving greater lateral stability, the depth of the foundation to be excavated for poles shall be in accordance with relevant sketch for the erection of pole or stay of D.P. etc. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 156 Technical Specification 1.6 ERECTION OF POLES : 1.6.1 PSC POLE : PSC poles should be erected perpendicular to ground level including excavation of earth pit having depth equal to 1/5 th the length of pole and cross-section 75 cm x 50 cm as directed by department including dragging and carrying of pole to site as per soil condition as given below. (i) earth filling with soil at bottom and surrounding with vigorous ramming; (ii) earth filling with soil at bottom and surrounding with vigorous with boulder packing including supply of boulder by contractor ( size of boulder 150mm x 200mm); (iii) grouting and mufflering in proportion 1:2:4 RCC foundation and filling of cement concrete as per specification including supply of cement , stone chips, shuttering etc. as directed ] 1.6.2 POLE CLAMP: The pole clamp is to be made of MS flat of size 40 mm x 6 mm with necessary drilling of holes and painting with primer and anti corrosive paint suitable for different size of steel tubular pole and PSC pole. 1.7 ERECTION OF SUPPORTS After the excavation of pits is completed the supports to be erected may be brought to the pits location. Then the pole may be erected inside the pit. Wooden support may be utilized to facilitate lifting of the pole at the pit locations. Before the pole is put into pit, RCC padding may be laid below the pole to increase the surface contact between the pole and the soil. The padding will distribute the weight of the pole uniformly on the soil. Having lifted the pole, the same should be kept in a vertical position with the help of manila rope of 25 mm dia using the rope as a temporary anchor. As the poles are being erected say from the pole already erected to the next location where the pole is being erected, the alignment of the poles are to be checked and set right by visual check. The verticality‘s of the poles are to be checked with a spirit level on both transverse and longitudinal directions. Having satisfied that the verticality and alignment are all right, earth filling or concreting is to be done. In swampy and special locations, however, before earth filing, the poles are to be concreted up to ground level of the pit. After the poles have been set the temporary anchors are to be removed. The supports shall be buried to a depth as per REC construction standard. 1.8 ERECTION OF D.P. STRUCTURES FOR ANGLE LOCATIONS (FOR 33 LINES): Generally, for angles of deviation more than 20° double pole structures of spacing 1.2 mts (4.0 ft) may be erected. The pits are to be excavated as per bisection of the angle of deviation. After the poles are erected, the horizontal / cross bracing should be fitted and the supports held in a vertical position with the help of temporary guys of manila rope of at least 25 mm dia. Ensuring that the poles are held in a vertical position (this can be checked with a spirit level) the concreting of the poles with cement, granite chips of size 20/30 mm mesh and sand in the ratio M400 conforming to ISS is to be done Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 157 Technical Specification from the bottom of the support to the ground level. Before lifting the pole in the pit, concrete padding of not less than 75 mm thickness may be put for the distribution of the load of the support on the soil. After the concreting is done, the pit may be filled with earth after curing of the concrete is completed. Four stays along the line, two in each direction and two stays along the bisection of angle of deviation are to be provided. Stay concreting may be done with M 400 concrete mixture The D.P. shall be erected as per the approved drawing. 1.9 ANCHORING AND PROVIDING GUYS FOR SUPPORTS Fitting of stay set on overhead line including digging of earth pit of area 90cm x 60 cm and depth of 1.4 m placing the stay rod with G.I stay wire Guy insulator on pole clamp , fixing of thimble bow etc with hard soil packing and ramming to fill up pit to ground level. Guys are to be provided to the supports at the following places (i) Angle locations, (ii) Dead end locations, (iii) Tee-off points, (iv) Steep gradient locations to avoid uplifted on the poles. The installation of guy will involve the following works: i) Excavation of pit and fixing of stay rod. ii) Fastening guy wire to the support. iii) Tightening guy wire and fastening to the anchor The marking of the guy pit for excavation, the excavation of pits and setting of the anchor rod must be carefully carried out. The stay rod should be placed in the position such that the angle of inclination of the rod with the vertical face of the point is 30°/45° as the case may be. The concreting of the stay at the bottom should then be carried out. The back filling and ramming must be well done thereafter, and allowed to set for at least 7 days. The free end of the guy wire is passed through the eye of the anchor rod, bent back parallel to the main portion of the guy and bound after inserting the G.I. Thimble. The loop is protected by the G.I. Thimble, where it bears on the anchor rod. Where the existence of guy wire proves hazardous, it should be protected with suitable asbestos pipe, filled with concrete of about 2 mts length above the ground level, duly painted with white and black stripe so that it may be visible at night. The turn buckle shall be mounted at the pole end of the stay and guy wire so fixed that the eye bolt turn buckle is half way in the working position, thus giving the maximum movement for tightening or loosening. Guy insulators are placed to prevent the lower part of the guy from becoming electrically energized by a contact of the guy when the conductors snap and fall on them of due leakage. No guy insulator shall be located less than 2.6 mts. from the ground. The anchoring and providing guys for supports (Single guy Bow guy fly guy) shall be done as per sketch enclosed. Bow guy and fly guy shall be provided as per field conditions. HT GUY INSULATOR Power line Voltage Designation of Insulator Dry one minute Wet one power minute power frequency frequency withstand withstand voltage voltage 33 KV C 27 KV ( r.m.s) 13 KV ( r.m.s) [ for 33 KV , 2 insulators to be used in series] Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Minimum failing load 88 KN Assam Power Distribution Company Ltd 158 Technical Specification 1.10 FIXING OF CROSS ARMS INSULATORS After the erection of supports and providing guys, the next step would be to mount the cross arms on the support erected. The lineman should climb the support having requisite tools with him and the cross arm is then tied to a hand line and pulled up by the ground man and should station himself well to one side so that if any material drops from the top of the pole it may not strike him. All the materials required should be lifted or lowered by means of the hand line. In no case, the materials of the tools should be dropped or thrown from the pole top. The fixing of 33 KV Cross arms shall be in accordance to spacing detailed in Sketch. G.I. bolts and nuts and spring washers of good quality only shall be used which will have to be procured by the contractor. 1.11 Back Clamps The back clamps for fixing of the seating channels, ―V‖ cross arms, horizontal cross arms and top cleats will have to be procured by the contractor and shall be in accordance with sketch enclosed and the clamp shall be fabricated with 75 X 8 mm M.S. Flat for 33 KV 1.12 Top Cleats The top cleats shall be got fabricated with M.S. Channel of size 75 X 40 mm for 33 KV and shall be in accordance with REC construction standard 1.13 INSULATORS The pins for insulators shall be fixed in the holes provided in the cross arms and the pole top brackets. The insulators shall be mounted in their places over pins and tightened. In the case of strain or angles supports, where strain fittings are provided for this purpose, one strap of the strain fitting is placed over the cross arm before placing the bolts in the hole of the cross arms. The nut of the strap is so tightened that the strap can move freely in horizontal direction, as this is necessary to fix the strain insulator. The insulator shall be cleaned and examined for defects before fixing, it shall be ensured that all the current carrying parts are smooth and without dirt, cracks or chips. Disc Insulator Strings Each insulator string shall consist of following numbers of Disc Insulator units. Sl .No Type of No of Disc Insulator Unit No of Disc Insulator Unit String for 33 KV for 11 KV 1. Suspension 3 2. Tension 4 1.14 STRINGING OF THE LINE CONDUCTORS For the guidance of the contractor certain do‘s and don‘ts are given below before the workmen actually commence the stringing work. 1.14.1 Do‟s and Don‟ts DO‟s ii. iii. iv. Use proper equipment for handling aluminum conductors at all times. Use skids, or similar method for lowering reels or coils from transport or ground. Examine reel before unreeling for presence of nails or any other Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 159 Technical Specification object, which might damage the conductor. v. Rotate the reel or coil while unwinding conductor. vi. Grip all strands while pulling out the conductor. vii. Control the unreeling speed with suitable braking arrangement. viii. Use wooden guards of suitable braking arrangement. ix. Use long straight, parallel jaw grip with suitable liners when pulling conductor thus avoiding nicking or kinking of the conductor. x. Use free running sleeves or blocks with adequate grooves for drawing/paving conductors. xi. Use proper sag charts. xii. Mark conductors with crayons or adhesive tape of such (other) material, which will not damage the strand. xiii. Make all splicing with the proper tools. xiv. Use a twisting wrench for twisting the joints. xv. Chromite or graphite conducting oxide-inhibiting grease should be used before cleaning with wire brush. DON‟Ts i. Do not handle conductors without proper tools at any stage. ii. Do not pull conductors without ensuring that there are no obstructions on the ground. iii. Do not pull out excess quantity of conductor than is required. iv. Do not make jumper connections on dirty or weathered conductor. v. Do not handle aluminum conductors in a rough fashion but handle it with care it deserves. 1.14.2 CONDUCTOR ERECTIONS The erection of overhead line conductor is a very important phase in construction. The erection of conductors can be sub-divided into 4 separate parts as follows: i. Transport of conductors to work site. ii. Paving and stringing of conductors. iii. Tensioning and sagging of conductors. iv. Joining of conductors. At the important crossing of roads, canals, navigable rivers, railways etc., flagmen should be in attendance to ensure that normal services are not unduly interrupted. These crossing should only be carried out in conjunction with and with the approval of the proper authorities concerned. The conductor drums shall be transported to the tension point without injuring the conductor, if, it is necessary to roll the drum on the ground for a small distance, it should be slowly rolled in the direction of the marked on the drum. The drum should be so supported that it can be rotated freely. For this purpose the drum should either be mounted on the cable drum supports of jacks or hung by means of chain pulley of suitable capacity, suspended from a tripod. In case if it is not possible to raise the conductor drum by any of the above method, a trench of suitable depth slightly bigger than the conductor drum may be dug, so as to facilitate free rotation of the cable drum when it is suspended in the trench by means of M.S. Shaft. While paving, care should be taken to see that conductor does not rub against any metallic fitting of the pole or on the bad/rocky ground. Wooden trusses should be used for this purpose to support the conductor. The conductor should be passed over the poles on wooden or aluminum snatch pulley blocks provided with low friction bearings. While conductor is being paved out slowly, some braking arrangement should be made so that the rotation of the drum may be stopped in emergency. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 160 Technical Specification In case the length of one piece of the conductor is less than the length of the section in which conductor paving is being done, it is easy to stretch one length of all phases from one end the remaining length from another end of the section any part of the conductor shall be left at a height of less than that of 5 meters, above the ground by rough sagging. 1.14.3 Mid Span Jointing of Conductors The mid span jointing of conductors should be carried by sleeves and twisting the joint at the ends and the wire should project a few centimeter, beyond the end of the sleeves. The projected wires are given a sharp bend to keep them from slipping out of the sleeve. The end of the sleeves are then held tightly by twisting wrenches and then 4 to 5 turns in one direction generally anti-clock wise direction. Crimping Tools are preferably to be used for joints and jumpers. 1.14.4 SAGGING AND TENSIONING On the completion of the paving of the conductors and making mid span joints if any, tensioning operations will commence. Temporary guys will have to be provided for both the anchoring supports in the section where the stringing has to be done. At the tensioning end, one of the conductors is pulled manually up to a certain point and then come along clamp is fixed to the conductor to be tensioned. The grip to the come along clamp is attached to double sleeve pulley block or the pulley lift machine and gradually tensioned. The conductor should then be sagged in accordance with the sag temperature chart for the particular conductor and span. The sag should then be adjusted in the middle span of the section. The sag chart is to be provided. The stretch of the conductor has to be taken out before stringing in order to avoid the gradual increase in sag due to the setting down of the individual wires. There are ways of accomplishing this: a) Pre-stressing In this method the conductor is pulled up to tension considerably above the correct figures, but never exceeding 50% of breaking load for a short period of say twenty minutes. As this method requires more time and involves the use of stronger tackle to secure the higher tension the other method of over tensioning is commonly adopted. b) Over-tensioning This method consists of pulling up the conductor to a tension a little above the theoretical tension for prevailing temperature and fixed it up at that tension with correspondingly reduced sag. After a certain time the conductor will settle down to the correct sag and tension. A tension of five to eight percent more than the theoretical value has been found to be suitable for the sizes of ACSR and AAAC conductors standardized by REC. The ambient temperature during sagging may be recorded correctly. Conductors can be sagged correctly only when the tension is the same in each span throughout the entire length of section. Use of snatch blocks reduces the friction and chances of inequality of tension in various spans. Sagging can be accomplished by several different methods but most commonly used method is ―Slighting‖. The slighting sag method of measuring sag is by the use of targets placed on the supports below the cross arms. The targets may be Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 161 Technical Specification light strip of wood clamped to the pole at a distance equal to the sag below the conductor when the conductor is placed in snatch block. The lineman sees the sag from the next pole. The tension of the conductor is then reduced or increased, until the lowest part of the conductor in the span coincides with the lineman‘s line of sight. When sagging is completed, the tension clamps shall be fixed. The clamp can be fitted on the conductor without releasing the tension. A mark is made on the conductor at a distance from the cross-arm equal to the length of complete strain insulator. Before the insulator set is raised to position, all nuts should be free. Come along clamp is placed on the conductor beyond the conductor clamp and attached to the pulling unit. The conductor is pulled in sufficiently to allow the insulator assembly to be fitted to the clamp. After the conductor is clamped to insulator, assembly unit may be released gradually. If the tension is released with a jerk, an abnormal stress may be transferred to conductor and support, which may result in the failure of the cross arm, stay or pole in some cases. After the stringing is completed, all poles, cross arms, insulators, fittings etc. are checked upto ensure that there have been no deformities etc. The next step is to place the conductor on the top of the pin insulator from the snatch block and removing snatch blocks. Conductors are then fastened to insulator by the use of aluminum wires. The following points should be observed: i) Proper size of the tie binding wire which can be readily handled and with adequate strength is to be used. ii) The length of tie wire should be sufficiently long for making complete tie including the end allowances for gripping with ends. iii) A good tie should provide a secure binding between the line conductor and insulator and should reinforce the conductor on either side of the insulator. iv) The use of cutting pliers for binding the tie wire should be avoided. v) The tie wire which has been used previously should be reused Before tying the conductor to the insulator two layers of Aluminum tapes should be wrapped over the conductor in the portion where it touches the insulator. The width and thickness of aluminum tape to be used for a specific size of conductors has been specified in hand books of aluminum conductor manufacturers and the same be referred to. The Aluminum tapes should also be used at the tension clamp and for proper grip. Normally in straight runs of line, the conductors are run on the top of insulators. When there is small of deviation the conductor is placed inside groove and bound. Accordingly, there are two methods of tying the conductors to insulators. The binding wire/tie wire has to be procured by the contractor and the bid price shall include the cost of this. The contractor shall be entirely responsible for any damage to the supports, other accessories and conductor. He shall also be responsible for proper distribution of the conductor drums to keep number and lengths of cut pieces of the conductor to a minimum. 1.14.5 CONDUCTOR DAMAGE AND REPAIR If the conductor is damaged for whatever reasons, and damage is not repaired Assam Power Distribution Company Ltd 162 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Technical Specification by aluminum sleeves, etc., it shall be brought to the notice of the Engineer and shall not be used without his approval. Even repairing of conductor surfaces shall be done only in case of minor damages, scuff marks etc., which are safe from both electrical and mechanical points of view. The final; conductor surface shall be clean, smooth, without any projection sharp points, cut or abrasion etc. giving satisfactory corona and R.I. performance. No joints or splice be made in span‘s crossing over main roads, railways, small rivers or intension spans. Not more than one joint per conductor shall be allowed in one span. The strength of the joint shall conform to IE Rule 75. 1.14.6 STRINGING. Whatever necessary ground clearances have to be measured to ensure obtaining adequate line clearance as per IE Rule 77 (i) GUARDING : When an overhead line crosses or is in proximity of any telecommunication line arrangement shall be made to provide protective device or guarding. When an overhead line crosses or is in proximity of to another over head line or overhead lines of different voltage on same supporting structure guarding arrangement shall be provided so as to guard against the possibility of their coming into contact with each other. Every guard-wire shall be an actual breaking strength of not less than 635 kg and if made of iron or steel shall be galvanize. Every guard-wire shall be connected with earth at each point at which its electricity continuity is broken. 1.15 EARTHING 1.15.1 PIPE EARTHING At D.P Locations, Pits are to be excavated the steel and metal parts are to be earthed by pipe earthing as per the drawing or sketch enclosed to this specification. Duly filling the pits with finely broken coke having granule sizes not more than 25 mm thick. The coke shall be maintained up to a distance of 300 mm for the pipe on all sides. The top edge of the pipe shall be at least 200 mm below the ground level. The CI strips shall be fixed not less than 300 mm deep from the ground level. The tenders shall quote the charges for earthing inclusive of the cost of coke, excavation and back filling. 1.15.2 Pole Earthing: All Supports shall be properly earthed. 1.16 CONCRETING The cement concrete used for the foundations shall be of M 400 grade. The full concreting for the poles if erected in excavated act shall be done so that the complete block will be of dimensions( 0.6 X 0.6 X 1.6) + 0.2 X 0.2 Mtr. (0.6 X 0.6 X 1/35) + 0.2 X 0.2 X 0.2 Mtrs. so as to maintain as exposed portion for 0.2 Mtrs height above the ground level. If augur is used for making pole pits, ramming shall be done after erection of pole. 1.17 WORKMANSHIP Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 163 Technical Specification The contractor shall entirely be responsible for correct erection of all support as per the approved drawings, and their correct setting and alignment, as approved by the engineer. If the supports and D.P. structures after the erection are found to differ from approved route maps and drawings or to be out of alignment, the contractor shall dismantle and re-erect them correctly at his own cost without extension of time. The supports must be truly vertical and in plumb after erection and no straining will be permitted to bring them to vertical position. Verticality of each support shall be measured by the contractor and furnished to the Engineer. 1.18 Location numbers for each pole shall be painted on the pole. 1.19 Anti-climbing devices, and danger boards are to be provided at all railway crossings and road crossings. No extra charges shall be admissible even though separate gangs may have to be sent by the contractor for fitting these accessories and attachments on the support at the appropriate time. 1.20 FINAL CHECKING, TESTING AND COMMISSIONING After the completion of the work final patrolling and checking of the line shall be done by the contractor to ensure that all foundations work, pole erection and stringing have been done as approved by the Engineer, and also to ensure that they are completed in all respects. Contractor shall prepare pole schedules and hand it over to the Engineer. All works shall be thoroughly inspected keeping in view of the following main points. i) Sufficient back filled earth is lying over each foundation pit and it is adequately compacted. ii) Concreting and coping of poles are in good and finally shaped conditions. iii) All the accessories and insulators are strictly as per drawings and are free from any defects or damages, what-so-ever. iv) All the bolts and nuts should be of G.I material and as per contractual provisions. v) The stringing on the conductor has been done as per approved sag and desired clearances are available. vi) No damage, minor or major to the conductor, earth wire, accessories and insulator strings still unattended are noticed. vii) For all points double jumpers shall be provided to each phase. The jumpers provided at the cut points are connected rigidly to the tension hardware utilizing all the jointing bolts provided for the purpose. The contractor shall submit a report to the above effect to the Engineer. In case, it is noticed later that some or any of the above are not fulfilled the Engineer will get such items rectified through other agencies and recover the cost of such works from the bills payable to the contractor against that contract or any other contract executed by him for APDCL. After final checking, the lines shall be tested for insulation in accordance with tests prescribed by the Engineer. All arrangements for such testing or any other tests desired by the Engineer shall be done by the Contractor and necessary labour, transport and equipment shall be provided by him. Any defects found out as a result of such tests, shall be rectified by the Contractor, forthwith, without any extra charges to APDCL,. In addition to the above, the Contractor shall be responsible for testing and ensuring that the total and relative sags of the conductors are within the Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 164 Technical Specification specified tolerance. Such tests shall be carried out at selected points along the route as required by the Engineer and the Contractor shall provide all necessary equipment and labour to enable the tests to be carried out. The APDCL, will arrange statutory inspection of the line and indicate the defects noticed. The Contractor has to rectify all such defects and intimate to APDCL, Engineer. After satisfactory tests on the line and an approval by the Engineer the line shall be energized at full operating voltage before handing over. 1.21 SUPPLY OF CONSTRUCTION MATERIALS BY THE CONTRACTOR The Contractor has to make his own arrangements for procurement, supply and use of construction materials like cement, M.S. rounds, HBG metal and sand. 1.22 CEMENT The contractor has to make his own arrangements for the procurement of cement to require specifications required for the work subjected to the follows: a) The contractor shall procure cement, required for the works only from reputed cement factories (Man producer) acceptable to the Engineer-in-Charge. The contractor shall be required to be furnished to the Engineer-in –Charge bills of payment and test certificates issued by the manufacturers to authenticate procurement of quality cement from the approved cement factory. The contractor shall make his own arrangement for adequate storage of cement. b) The contractor shall procure cement in standard packing of all 50 kg per bag from the authorized manufactures. The contactor shall make necessary arrangement at his own cost to the satisfaction of Engineer-in-Charge for actual weighment of random sample from the available stock and shall conform to the specification laid down by the Indian Standard Institution or other standard foreign institutions as the case may be. Cement shall be got tested for all the tests as directed by Engineer-in-Charge at least one month in advance before the use of cement hags brought and kept on site Godown. Cement bags required for testing shall be supplied by the contractor free of cost. However, the testing charges for cement will be borne by the APDCL. If the tests prove unsatisfactorily, then the charges for cement will be borne by the contractor. c) The contractor should store the cement of 60 days requirement at least one month in advance to ensure the quality of cement so brought to site and shall not remove the same without the written permission of the Engineer-in-Charge. The contractor shall forthwith remove from the works area any cement that the Engineer-in-Charge may disallow for use, an account of failure to meet with required quality and standard. d) The contractor shall further, at all times satisfy the Engineer-in-Charge on demand, by production of records and books or by submission of returns and other proofs as directed, that the cement is being used as rested and approved by Engineer-in-Charge for the purpose and the contractor shall at all times, keep his records upto date to enable the Engineer-in-Charge to apply such checks as he may desire. e) Cement which has been unduly long in storage with the contractor or alternatively has deteriorated due to inadequate storage and thus become unfit for use in the works will be rejected by the department and no claim will be entertained. The contractor shall forthwith remove from the work area, any cement the Engineer-in-Charge may disallow for use on work and replace it by cement complying with the relevant Indian Standards. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 165 Technical Specification 1.23 STEEL The contractor shall procure mild steel reinforcement bars, high yield strength deformed(HYSD) bars, rods and structural steel etc. required for the works only from the main or secondary producers manufacturing steel to the prescribed specifications of Bureau of Indian Standards or equivalent and licensed to affix ISI or other equivalent certification marks and acceptable to the Engineer-inCharge. Necessary ISI list certificates are to be produced to Engineer-in-Charge before use on works. The unit weight and dimensions shall be as prescribed in the relevant Indian Standard specification for steel. All steel materials shall be Galvenised. 1.24 INFORMATION AND DATA a) The information furnished is the best available however, the APDCL does not guarantee the correctness of interpretations, deductions or conclusions which are given as supplementary information in the Bid Documents or in any reports, maps, drawings, diagrams or in other reference information available to the bidder from APDCL of or otherwise. The information has been produced as found, communicated to ascertained or otherwise/learned by the APDCL. b) it will be the Bidder‘s responsibility to satisfy himself from the ―Reference Information‖ supplied and or inspection of the site that sufficient quantities of construction materials required for the works shall exist in the designated borrow areas or quarry sites. The APDCL does not accept any responsibility either in handing over the quarries or procuring the materials or any other facilities. The Tenderer will not be entitled for any extra rate or claim for the misjudgment on his part for the quantity and quality of materials available in the quarries. Failure by the Bidder to have done all the timings which is in accordance with this condition he is deemed to have done shall not relieve the successful Bidder of the responsibility for satisfactorily completing the work as required at the rates quoted by him. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 166 Technical Specification 3.14 TECHNICAL SPECIFICATION FOR PSC POLES [9.75 M] 1.0 SCOPE This covers design manufacturing, testing at works, transport to site, insurance, storage, erection and commissioning of PSC poles shall be of solid rectangular with an overall length of 9.75M suitable for use in overhead 33KV / 11 KV lines 2.0 Applicable Standards The pre-stressed concrete pole (psc ) shall comply with the relevant provisions mentioned' in the' following Indian Standards or the latest versions thereof. a) IS: 1678, Specification for pre-stressed concrete poles for overhead power, traction and telecommunication lines. b) IS: 2905, Method of test for concrete poles for overhead power and telecommunication lines. c) IS: 7321, Code of Practice for selection, handling and erection of concrete poles for overhead power and telecommunication lines. REQUIRED TECHNICAL PARAMETERS FOR 9.75 M PSC POLES 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 4.0 4.1 4.2 5.0 6.0 7.0 Terminology For the purpose of this specification, following definitions shall apply: Average Permanent Load That fraction of the working load which may be considered of long duration over a period of one year. Load Factor The ratio of ultimate transverse load to the transverse load at first crack. Transverse The direction of the line bisecting the angle contained by the conductor at the pole. In the case of a straight run, this will be normal to the run of the line. Transverse Load at First Crack For design, the transverse load at first crack shall be taken as not less than the value of the working load. Working Load The maximum load in the transverse direction, that is ever likely to occur, including the wind pressure on the pole. This load is assumed to act at a point· 600 mm below the top with the butt end of the pole planted to the required depth as intended in the design. Ultimate Failure The condition existing when the pole ceases to sustain a load increment owing to either crushing of concrete, or snapping of the pre-stressing tendon or permanent stretching of the steel in any part of the pole. Ultimate Transverse Load The load at which failure occurs, when it is applied at a point 600 mm below the top and perpendicular to the axis of the pole along the transverse direction with the butt end of the pole planted to the required depth as intended in the design. Application 9.75 M PSC Pole These poles shall be used for 33 kV lines, and for special locations in 11 kV lines, such as road crossings, etc. Material Cement The cement used in the manufacture of pre-stressed concrete poles shall be ordinary or rapid hardening Portland cement conforming to IS: 269 (Specification for ordinary and low heat Portland cement) or IS: 8041 E (Specification for rapid hardening Portland cement), or high strength ordinary Portland cement conforming to IS: 8112 (Specification of high strength ordinary Portland cement). Aggregates Aggregates used for the manufacture of pre-stressed concrete poles shall confirm to IS: 383 (Specification for coarse and fine aggregates from natural sources for concrete). Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 167 Technical Specification The nominal maximum size of aggregates shall in no case exceed 10 mm (for poles above 9.0 M) and 12 mm (for 7.5 and 8.0 M poles). 8.0 Water Water should be free from chlorides, sulphates, other salts and organic matter, Potable water will be generally suitable. 8.1 Admixture Admixture should not contain Calcium Chloride or other chlorides and salts which are likely to promote corrosion of pre-stressing steel. 8.2 Pre-stressing Steel The pre-stressing steel wires including those used as un-tensioned wires (See Annexure. I, II & III), should conform to IS: 1785 (part-I) (Specification for plain harddrawn steel wire for pre-stressed concrete. Part-I cold drawn stress relieved wire), IS: 1785 (part-II) (Specification for plain hard-drawn steel wire) or IS: 6003 (Specification for indented wire for pre-stressed concrete). The type designs given in Annexure-I, II and III are for plain wires of 4 mm diameter with a guaranteed ultimate strength of 175 kg/mm2. The concrete mix shall be designed to the requirements laid down for controlled concrete (also called design mix concrete) in IS: 1343 (Code of practice for prestressed concrete) and IS: 456 (Code of practice for plain and reinforced concrete), subject to the following special conditions: a) Maximum works cube strength at 28 days should be at least 400 kg/cm2 (for poles above 9.0 M) and 420 kg/cm2 (for 7.5 and 8.0 M poles). b) The concrete strength at transfer should be at least 200 kg/cm2 (for poles above 9.0 M) ·and 210 kg/cm2 (for 7.5 and 8.0 M poles). c) The mix should' contain at least 380 kg of cement per cubic meter of concrete. d) The mix should contain as Iowa water content as is consistent with adequate workability. If it becomes necessary to add water to increase the workability, the cement content also should be raised in such a way that the original value of water cement ratio is maintained. 9.0 DESIGN REQUIREMENTS The poles shall be designed for the following requirements: a) The poles shall be planted directly in the ground with a planting depth as per IS: 1678. b) The working load on the poles should correspond to those that are likely to come on the pole during their service life. Designs given in Annexure I,ll and III are for 140 kg, 200 kg, 300 kg, and 400 kg., applied at 0.6 M from top. c) The factor of safety for all poles above 9.5 M shall not be less than 2.0. For 7.5 M and 8.5 M poles, the factor of safety shall not be less than 2.5. d) The average permanent load shall be 40% of the working load. e) The F.O.S. against first load shall be 1.0. f) At average permanent load, permissible tensile stress in concrete shall be 30 kg/cm2. g) At the design value of first crack load, the modulus of rupture shall not exceed 53.0 kg/cm2 for M-400 concrete and 55.2 kg/cm2 for M-420 concrete. h) At the design value of first crack load, the modulus of rupture shall not exceed 53.0 kg/cm2 for M-400 concrete. i) The ultimate moment capacity in the longitudinal direction should be at least one fourth of that il1 the transverse direction. j) The maximum compressive stress in concrete at the time of transfer of pre-stress should not exceed 0.8 times the cube strength. k) The concrete strength at transfer shall not be less than half the 28 days strength ensured in the design, i.e., 400 x 0.5 = 200 kg/cm2 or 420 x 0.5 = 210 kg/cm2. 10.0 Service Conditions PSC poles have to be designed to suit the following climatic conditions: a) Maximum temperature of air in shade 40°C b) Minimum temperature of air in shade 2°C c) Maximum temperature of air in sun 45°C d) Maximum humidity Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 93% Assam Power Distribution Company Ltd 168 Technical Specification e) f) g) h) 11.0 12.0 12.1 13.0 14.0 15.0 16.0 Average number of thunder storm days per annum Maximum rainfall per annum Average rainfall per annum Wind pressure 45 Days 3500 mm 2200 mm 97.8 Kg/m2 i) Altitude above MSL 100 to 1000 M Dimensions and Reinforcements The cross-sectional dimensions and the details of pre-stressing wires should conform to the particulars given in Annexure-I, II and III. The provisions of holes for fixing cross-arms and other fixtures should conform to the REC standards . Manufacture Attire--stressing wires and reinforcements shall be accurately fixed as shown in drawings and maintained in position during manufacture. The un-tensioned reinforcement, as indicated in the drawings, should be held in position by the use of stirrups which should go round all the wires. AII wires shall be accurately stretched with uniform pre-stress in each wire. Each wire or a group of wires shall be anchored positively during casing. Care should be taken to see that the anchorages do not yield before the concrete attains the necessary strength. Cover The cover of concrete measured from the outside of pre-stressing tendon shall be normally 20 Nm. Welding and Lapping of Steel The high tensile steel wire shall be continuous over the entire length of the tendon. Welding shall not be allowed in any case. However, jointing or coupling may be permitted provided the strength of the joint or coupling is not less than the strength of each individual wire. Compacting Concrete shall be compacted by spinning, vibrating, shocking or other suitable mechanical means. Hand compaction shall not be permitted. Curing The concrete shall be covered with a layer of sacking, canvass, Hessian or similar absorbent material and kept constantly wet up to the time when the strength of concrete is at least equal to the minimum strength of concrete at transfer of pre-stress. Thereafter, the pole may be removed from the mould and watered at intervals to prevent surface cracking of the unit, the interval should depend on the atmospheric humidity and temperature. The pre-stressing wires shall be detensioned only after the concrete has attained the specified strength at transfer (i.e., 200 or 210 kg/cm2 as applicable). The cubes cast for the purpose of determining the strength at transfer should be cured, as far as possible, under conditions similar to those under which the poles are cured. The transfer stage shall be determined based on the daily tests carried out on concrete cubes till the specified strength indicated above is reached. Thereafter the test on concrete shall be carried out as detailed in IS: 1343 (Code of pr3ctice for pre-stressed concrete). The manufacturer shall supply, when required by the owner or his representative, result of compressive test conducted in accordance with IS: 456 (Code of practice for plain and reinforced concrete) on concrete cubes made from the concrete used for the poles. If the owner so desired, the manufacturer shall supply cubes for test purposes and such cubes shall be tested in accordance with IS: 456 (Code of practice for plain and reinforced concrete). The detensioning shall be done by slowly releasing the wires, without imparting shock or sudden load to the poles. The rate of detensioning may be controlled by any suitable means either mechanical (screw type) or hydraulic. The poles shall not be detensioned or released by cutting the pre-stressing wires using flames or bar croppers while the wires are still under tension. Separate eye-hooks or holes shall be provided for handling the transport, one each at a distance of 0.15 times the overall length, from either end of the pole. Eye-hooks, if Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 169 Technical Specification provided, should be properly anchored and should be on the face that has the shorter dimension of the cross-section. Holes, if provided for lifting purposes, should be perpendicular to the broad face of the pole. Stacking should be done in such a manner that the broad side of the pole is vertical. Each tier in the stack should be supported on timber sleeper located as 0.15 times the overall length, measured from the end. The timber supported in the stack should be aligned in a vertical line. Poles should be transported with their broad faces placed vertically and, in such a manner that the shocks are avoided. Supports should be so arranged that they are located approximately at a distance equal to 0.15 times the overall length from the ends. The erection of the pole should be carried out in such a way that the erection loads are applied so as to cause moment with respect to the major axis, i.e., the rope used for hoisting the pole should be parallel to the broader face of the pole. 17.0 Earthing 17.1 Earthing shall be provided by having length of 8 SWG GI wire embedded in concrete during manufacture and the ends of the wires left projecting from the pole to a length of 100 mm at 250 mm from top and 150 mm below ground level. 17.2 Earth wire shall not be allowed to come in contract with the pre-stressing wires. 17.3 Tests 18.0 Transverse Strength Test Poles made from ordinary Portland cement shall be tested only on the completion of 28 days and poles made from rapid hardening cement only on the completion of 14 days, after the day of manufacture. The poles may be tested in either horizontal or vertical position. If tested in horizontal position, provisions shall be made to compensate for the overhanging weight of the pole, for this purposed, the overhanging portion of the pole may be supported on a movable trolley or similar device. The pole shall be rigidly supported at the butt end for a distance equal to the agreed depth of planting. Load shall be applied at a point 600 mm from the top of the pole and shall be steadily and gradually increased to the design value of the transverse load at first crack. The deflection at this load shall be measured. A pre-stressed concrete pole shall be deemed not to have passed the test if visible cracks appear at a stage prior to the application of the design transverse load for the first crack. The load then be reduced to zero and increased gradually to a load equal to the first crack load plus 10% of the minimum ultimate transverse load, and held up for 2 minutes. This procedure shall be repeated until the load reaches the value of 80 per cent of the minimum ultimate transverse load and thereafter increased by 5 per cent of the minimum ultimate transverse load until failure occurs. Each time the load is applied, it shall be held for 2 minutes. The load applied to pre-stressed concrete pole at the point of failure shall be measured to the nearest five Kilograms. The pole shall be deemed not to have passed the test if the observed ultimate transverse load is less than the design ultimate transverse load. 19.0 Measurement of Cover After completion of the transverse strength test, the sample pole shall be taken and checked for cover. The cover of the pole shall be measured at 3 points, one within 1.8 meter from the butt end of the pole. the ·second within 0.6 meters from the top and the third at an intermediate point and the mean value compared with the specified value. The mean value of the measured cover should not differ by more than (±) 1 mrn from the specified cover. The individual values should not differ by more than (±) 3 mm from the specified value. If these requirements are not met, the workmanship with reference to aligning of the end plates and pre-stressing wires and assembly of moulds should be improved and inspection at pre-production stage tightened suitably. 20.0 MARKING The pole shall be clearly and indelibly marked with the following particulars either during or after manufacture but before testing at a position so as to be easily read after Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 170 Technical Specification erection in position. a) Month and year of manufacture b) Transverse strength of pole in Kg c) Maker's serial No and mark and Project . 21.0 SL NO 1 INSPECTION Inspection may be carried out by the purchaser or third party nominee at any stage of manufacture. The supplier shall grant free access to the purchaser's representative or third party nominee at a reasonable time when the work is in progress. Inspection and acceptance of any equipment under this specification by the purchaser shall not relieve the supplier of his obligation of furnishing equipment in accordance with the specification and shall not prevent subsequent rejection if the equipment is found defective. ITEM Type of Pole PARAMETERS 9.75 M P.S.C pole 9.75 Mts. 1.8 Mts. 350 mm 175 mm 120 mm 4 mm 22 Nos of 4mm dia. 175 KG / SQMM 1865 kg / wire As per IS : 1343 /1960 21.45 KG 3 4 5 6 7 8 9 Length of pole Depth of Plantation Bottom Depth Top Depth Breath Diameter of pre-stressing wire No. of tensioned wire per pole 10 11 Minimum Ultimate Tensile strength of 4 MM HT wire Minimum initial pull of 4 mm wire 12 Spacing HT wires 13 14 Quantity of HT wire/ pole Link & spiral 15 M.S spiral 16 17 18 19 20 21 22 Maximum Aggregate size Total weight per pole Minimum clear cover Factor of safety Concrete grade Ultimate Load Earthing shall be provided by 4 MM dia. Galvanized iron wire embedded in concrete 23 one marks to be provided at at 1.8 M ground level 28 days cube strength of concrete 420 KG ( Min) as per IS : 456/2000. SQ.CM 24 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 8.5 M PSC Pole 8.5 Mts. 1.5 Mts. 300 mm 162 mm 112 mm 4 mm 16 Nos of 4mm dia. 175 KG / SQMM 1865 kg / wire As per IS : 1343 /1960 13.60 KG 7.5 M P.S.C pole 7.5 Mts. 1.5 Mts. 250 mm 140 mm 105 mm 4 mm 12 Nos of 4mm dia. 175 KG / SQMM 1750 kg / wire As per IS : 1343 /1960 9.0 KG 4 nos ,5 mm in 4 nos ,5 mm in bottom & 4 nos bottom & 4 nos ,5 mm in top ) ,5 mm in top ) 3.540 KG ( 4 nos ,5 mm in bottom & 4 nos ,5 mm in top 3 mm dia of 150 c/c 12 mm 750 KG 20 mm 2.5 M-420 675 KG 3 mm dia of 3 mm dia of 150 150 c/c c/c 12 mm 12 mm 550 KG 360 KG 20 mm 20 mm 2.5 2.5 M-420 M-420 500 KG 350KG Projecting from the pole at length of 50 MM at 215 from top & 150 MM below ground level Projecting from the pole at length of 50 MM at 215 from top & 150 MM below ground level Projecting from the pole at length of 50 MM at 215 from top & 150 MM below ground level At 1.5 M At 1.25 M / 420 KG SQ.CM / 420KG/SQ.CM Assam Power Distribution Company Ltd 171 Technical Specification 3.15 TECHNICAL SPECIFICATION FOR STEEL TUBULAR POLES(GALVENISED) FOR OVERHEAD LINES 1.0 SCOPE : 1.1 This specification covers the general requirements towards design, manufacture, testing at manufacturers works, supply and delivery for tubular steel poles of circular cross section ( swaged type ) for overhead lines. 2.0 STANDARD : 2.1. The tubular steel poles shall conform to the latest edition of Indian Standard specification IS: 2713 ( Part – I, III ) : 1980 Specification for Steel Tubular poles The Steel Tubular Poles conforming to other internationally accepted, which ensure equal or higher quality than the standards, mentioned above also be acceptable. In case the bidder who wish to offer material conforming to the other standards, salient points of difference between adopted and specific standards with authentic English Translation shall be furnished. 3.0 Topography and Climatic Condition : 3.1. The materials offered, shall be suitable for operation in tropical climate and will be subjected to the sun and inclement weather and shall be able to withstand wide range of temperature variation. For the purpose of design, average atmospheric temperature may be considered to be 50 °C with humidity nearing saturation. 4.0 Materials : 4.1. The materials used in construction of tubular steel poles shall be of the tested quality of steels of minimum tensile strength 540 MPa ( : 55 Kgf/mm2 ). Or 410MPa as the case may be. 4.2. The materials, when analysed in accordance with IS : 228 ( Part-III : 1972 ) and IS : 228 ( Part-IX) shall not show sulpher and phosphorous contents of more than 0.060 percent each. 5.0 Types, Size and construction : 5.1. Tubular Steel Poles shall be swaged type. 5.2. Swaged poles shall be made of seamless or welded tubes of suitable lengths swaged and jointed together. No circumferential joints shall be permitted in the individual tube lengths of the poles. If welded tubes are used they shall have one longitudinal weld seam only : and thelongitudinal welds shall be staggered at each swaged joint. 5.3. Swaging may be done by any mechanical process. The upper edge of each joint shall be chamfered if at an angle of about 45o. The upper edge need not be chamfered if a circumferential weld is to be deposited in accordance with clause No. 5.3 2 of IS: 2713 ( Part-I) :1980. 5.4. The length of joints on swaged poles shall be in accordance with clause No. 5.4 of IS: 2713(Par-I): 1980. 5.5. Poles shall be well-finished, clean and free from harmful surface defects. Ends of the poles shall be cut square. Poles shall be straight, smooth and cylindrical. The weld joints, if any, shall be of good quality, free from scale, surface defects, cracks, etc. 5.6. Tolerances for outside diameter, thickness, length, weight and straightness shall be in accordance with IS: 2713 (Part-I) : 1980. 5.7. The poles shall be GALVENISED and coated with black bituminous paint conforming to IS : 158-1968 throughout, internally and externally, upto the level which goes inside the earth. 6.0 Earthing Arrangements : 6.1. For earthing arrangement a through hole of 14mm diameter shall be provided in each pole at a height of 300mm above the planting depth. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 172 Technical Specification 7.0 PRINCIPAL PARAMETERS SN ITEM DESCRIPTION PARAMETERS PARAMETER PARAMETERS 1. Type of Pole SP-76 SP-66 SP-60 2. Overall Length 14.5 M 12.0 M 12.0 M 3. Planting Depth 2.0 M 2.0 M 2.0 M 4. Load Applied from top at a distance of 0.60 M 0.60 M 0.60 M 5. Height above ground 12.5 M 10.0 M 10.0 M 6. Length of sections Bottom a. a 6.5 M 5.80 M 5.80 M Middle b. 4.0 M 3.10 M 3.10 M Top c. 4.0 M 3.10 M 3.10 M 7. Outside Diameter & thickness of section a Bottom, MM 219.1 x5.90 219.1 x5.90 165.1 x 5.40 b Middle ,MM 193.7 x4.85 193.7 x4.85 139.7 x 4.50 c Top,MM 165.1 x 4.5 165.1 x 4.5 114.3 x 3.65 8. Approx. Wt of pole 380 KG 322 KG 208 KG 9. crippling load 514 kgf 650 kgf 333 kgf 10. breaking load 724 kgf 916 kgf 469 kgf 11. Ultimate tensile strength 410 MPa ( 42 KGf / mm2 ) 410 MPa ( 42 KGf / mm2 ) 410 MPa ( 42 KGf / mm2 ) 12. Base Plate A Mild Steel base plate of size 400 mm x 400 mm x 8 mm shall be welded at the bottom of the pole. A Mild Steel base plate of size 400×400×8 mm shall be welded at the bottom of the pole. A Mild Steel base plate of size 400×400×8 mm shall be welded at the bottom of the pole. 13. Painting The complete pole shall be Galvenised as per IS 2629 and the inner side & outer underground The complete pole shall be Galvenised as per IS 2629 and the inner side & outer underground The complete pole shall be Galvenised as per IS 2629 and the inner side & outer underground portion of the Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 173 Technical Specification portion of the pole is to be painted with black bituminous paint conforming to IS : 158-1968 throughout,[ internally and externally, up to the level which goes inside the earth. portion of the pole is to be painted with black bituminous paint conforming to IS : 1581968 throughout,[ internally and externally, up to the level which goes inside the earth. pole is to be painted with black bituminous paint conforming to IS : 158-1968 throughout,[ internally and externally, up to the level which goes inside the earth. 8.0 Tests and Test Certificates : 8.1. The following tests shall be conducted on finished poles : A. Tensile test and chemical analysis for sulpher and phosphorous , B. Deflocation test, C. Permanent set test, and D. Drop test. 8.2. In addition to above verification of dimensions as per IS : 2713 (Part-III) : 1980 shall be carried out during acceptance of lots. 8.3. Number of poles selected for conducting different tests shall be in accordance to clause No.10.1.1 and No. 10.1.12: of IS: 2713 (Part-I) 1980. 8.4. Tests shall be carried out before supply of each consignment at the manufacturers woks and test certificates should be submitted to the purchaser for approval prior to delivery. 8.5. Re-tests, if any, shall be made in accordance with IS: 2713 (Part-I) 1980. 8.6. Purchaser reserves the right to inspect during manufacturing and depute his representative to inspect/test at the works. 8.7. If any extra cost is required for carrying out the above specified tests, the same shall be borne by the tenderer. 9.0 Marking : 9.1. The poles shall be marked with designation, manufacturer‘s identification, year of manufacture and name of the purchaser: APDCL 9.2. The poles may also be marked with the ISI certification mark if applicable. 10.0 Performance :10.1. The bidder shall furnish a list of the major supplies effected during the last 3 (three) years indicating the volume of supply and actual delivery dates alongwith the bids. 10.2. Bids may not be considered if the past manufacturing experience is found to be less that 3 (three) years. 11.0 Deviation :- 13.1 Any deviation in technical specification shall be clearly indicated with sufficient reasons thereof. Purchaser shall however reserve the right to accept and/or reject the same without assigning any reasons what-so-ever. 12.0 Guaranteed technical particulars : 12.1. The tenderer shall furnish all necessary guaranteed technical particulars in the prescribed proforma enclosed hereinafter. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 174 Technical Specification Annexure „B‟ TECHNICAL GUARANTEED AND OTHER PARTICULARS. (To be filled in by the Tenderer) 1. Type of Pole offered 2. a) Whether tubes are of seamless constn. Or welded type. b) Is it manually welded tubes? If so, state name/address of manufacturer c) It is ERW tubes? If so, state name/address of manufacturer 3. Overall length 4. Effective length of section a) Bottom b) Middle c) Top 5. Effective dia thickness of section a) Bottom b) Middle c) Top 6. Approximate weight (Kg.) 7. Breaking Load (Kg.) 8. Working Load (Kg.) 9. Weight/Mtr. i) Top Section (kg) ii) Middle Section (kg) iii) Bottom Section (kg) 10. Crippling load (kg) 11. Load for permanent set 12. Load for temporary deflection 13. Joint length Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 175 Technical Specification 3.16 TECHNICAL SPECIFICATION FOR GALVANIZED CHANNEL CROSS ARMS 1.0 3.0 SCOPE : This specification covers the design, manufacture, testing at manufacturer's works, transport to site, insurance, storage, erection and commissioning of Galvanized Cross Arm and channel used for 33KV, 11 KV & line complete with all accessories as specified. Standards The M.S Cross Arm and channel supplied under this specification shall conform the latest issue of the relevant Indian Standards IS – 226:1975, Regulations etc. except where specified otherwise. The rolling and cutting tolerance for steel product conforming to IS: 266 shall be those specified in the IS: 1852-1973 with latest revision. Galvanization conforming to latest version of 1S:2629 In the event of conforming to any standards other than the Indian Standards, the salient features of comparison shall be clearly set out separately 3.0 GENERAL REQUIREMENT : i. The cross arm shall be fabricated grade of mild steel of channel section as per requirement. ii. All steel members and other parts of fabricated material as delivered shall be free of warps, local deformation, unauthorized splices, or unauthorized bends. iii. Bending of flat strap shall be carried out cold. Straightening shall be carried out by pressure and not by hammering. Straightness is of particular importance if the alignment of bolt holes along a member is referred to its edges. iv. Holes and other provisions for field assembly shall be properly marked and cross referenced. Where required, either by notations on the drawing or by the necessity of proper identification and fittings for field assembly, the connection shall be match marked. v. A tolerance of not more than 1mm shall be permitted in the distance between the center lines of bolt holes. The holes may be either drilled or punched and, unless otherwise stated, shall be not more than 2mm greater in diameter than the bolts. vi. When assembling the components force may be used to bring the bolt holes together (provided neither members nor holes are thereby distorted) but all force must be removed before the bolt is inserted. Otherwise strain shall be deemed to be present and the structure may be rejected even though it may be, in all other respects, in conformity with the specification. vii. The back of the inner angle irons of lap joints shall be chamfered and the ends of the members cut where necessary and such other measures taken as will ensure that all members can be bolted together without strain or distortion. In particular, steps shall be taken to relieve stress in cold worked steel so as to prevent the onset of embitterment during galvanizing. viii. Similar parts shall be interchangeable. ix. Shapes and plates shall be fabricated and assembled in the shop to the greatest extent practicable. Shearing flame cutting and chipping shall be done carefully, neatly and accurately. Holes shall be cut, drilled or punched at right angles to the surface and shall not be made or enlarged by burning. Holes shall be clean-cut without torn or ragged edges, and burrs resulting from drilling or reaming operations shall be removed with the proper tool. x. Shapes and plates shall be fabricated to the tolerance that will permit fielderection within tolerance, except as otherwise specified. All fabrication shall be carried out in a neat and workmanlike manner so as to facilitate cleaning, painting, galvanizing and inspection and to avoid areas in which water and other matter can lodge. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 176 Technical Specification xi. xii. xiii. Contact surfaces at all connections shall be free of loose scale, dirt, burrs, oil and other foreign materials that might prevent solid seating of the parts. Welded joints not permissible. The rolling and cutting tolerance for steel product conforming to IS: 266 shall be those specified in the IS: 1852-1973 with latest revision. all dimensions are subject to the following tolerances: a) dimensions up to and including 50mm:+1mm: and b) dimensions greater than 50mm: +2% xiv. xv. The channel cross arm shall be properly brushed to make it free from rust. xvi. he raw materials and fabrication thereof in respect of cross arm shall be furnished along with dimension. The hole for fixing of insulator and pole clamp shall be provided as per requirement. One copy of the drawing of cross arm for each size shall be furnished along with the technical bid. xvii. xviii. a. For galvanized channel : All ferrous parts including all sizes of nuts, bolts, plain and spring washers, support channels, structures, shall; be hot dip galvanized conforming to latest version of 1S:2629 or any other equivalent authoritative standard. The zinc coating shall be smooth, continuous and uniform. It shall be free from acid spot and shall not scale, blister or be removable by handling or packing. There shall be no impurities in the zinc or additives to the galvanic bath which could have a detrimental effect on the durability of the zinc coating. Before picking, all welding, drilling, cutting, grinding and other finishing operations must be completed and all grease, paints, varnish, oil, welding slag and other foreign matter completely removed. All protuberances, which would affect the life of galvanizing shall also be removed. The weight of zinc deposited shall be in accordance with that stated in Standard IS 2629 and shall not less than 0.61kg/m² with a minimum thickness of 86 microns for items of thickness more than 5mm, 0.46kg/m² (64 microns) for items of thickness between 2mm and 5mm and 0.33kg/m² (47 microns) for items less than 2mm thick. REQUIRED TECHNICAL SPECIFICATION FOR GI CHANNEL CROSS ARM [100x50x6x3200 ] Sl Description Particular No. 1 Type of cross arm G.I Channel cross arm 2 Size 100 x 50x 6 x 3200 mm 3 Material Mild Steel channel 4 Length 3200 mm 5 Breath 100 mm 6 Width 50 mm 7 Thickness 6 mm 8 Hole for fixing of 26 mm insulator 9 Center to center 1525 mm distance of hole 10 Hole for pole clamp 18 mm 11 Weight 29.5 kg (approx) 12 Galvanization The cross arm shall be properly brushed to make it free from rust and hot dip galvanized confirming to IS: 2629. 13 Standard applicable IS: 266; IS: 1852-1973: Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 177 Technical Specification Sl No. 1 2 3 4 5 6 7 Description 10 Type of cross arm Size Material Length Breath Width Thickness Hole for foxing of insulator Center to center distance for hole Weight 11 Galvanization 8 9 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Particular GI Channel cross arm 75 x 40x 40x6 x 2200 mm Mild Steel channel( galvanized) 2200 mm 75 mm 40 mm 6 mm 20 mm 1070mm 16 kg (approx) The cross arm shall be properly brushed to make it free from rust and hot dip galvanized confirming to IS: 2629. Assam Power Distribution Company Ltd 178 Technical Specification 3.17 TECHNICAL SPECIFICATION FOR 33 KV & 11KV DISC INSULATOR (B&S) 70 KN 1.0 Scope: This specification covers design, manufacture, testing at manufacturers‘ works, supply and delivery of strain insulators use on 11 KV and 33 KV overhead power line. 2.0 Standard: 2.1. Strain insulators Ball & Socket type suitable for 11 kV & 33 kV lines shall be conforming to Indian standard Specification IS: 731:1971 and IS: 3188 with its latest amendments and revisions and having mechanical failing load of 70 KN. 2.2. Insulators conforming to any other internationally accepted standard which ensure equal or higher quality than the standard mentioned will be acceptable. 2.3. Where the material is offered according to the internationally accepted standard a copy of the specification shall be attached with the tender. 3.0 General requirements: 3.1. The porcelain shall be sound, free from defects, thoroughly vitrified and smoothly glazed. Unless and otherwise specified glaze shall be brown in colour. The glaze shall cover all the porcelain parts of the insulator except those areas which serve as support during firing or are left unglazed for purpose of assembly. 3.2. The design of the insulator shall be such that stress due to expansion and contraction in any parts in any parts of the insulator shall not lead to deterioration. The porcelain shall not engage directly with hard matel. 3.3. Cement used in the construction of insulator shall not cause fracture by expansion or loosening by contraction and proper care shall be taken to locate the individuals‘ parts correctly during commencing. The cement shall not give rise to chemical reaction with metal fittings and its thickness shall be uniform as possible. i) The insulator shall be multi petticoat type./The insulator shall be in one piece. 4.0 Basic Parameter: Sl no Particular 1 Type of insulator 2 Applicable Standard 3 Material 4 5 6 7 8 Type Colour Size Minimum failing load Socket cap 9 Ball pin 10 11 Security clip Creepage distance 12 Nominal System voltage Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Disc insulator, 70 KV (B&S type) IS: 731:1971 and IS: 3188, IS: 2544/1973 Porcelain [sound, free from defects, thoroughly vitrified and smoothly glazed] Ball & Socket Brown 255x145 mm 70 KN Malleable cast iron hot dip galvanized of size 16 mm dia High tensile/ forged hot dip galvanized Phosphor bronze ‗W‘ type 580mm ( for 33 KV)& 400 mm ( for 11 KV) 33kV/11 KV Assam Power Distribution Company Ltd 179 Technical Specification 13 Highest system voltage (rms) 14 Wet one minute power frequency test(rms) 15 Dry one minute power frequency test (rms) 16 Power frequency puncture withstand (rms) 17 Impulse voltage withstand test(Peak) 18 Power frequency flush and voltage (dry) Power frequency flush and voltage (wet) 19 Visible discharge test 20 36 KV/12 KV 75 KV/35 KV 75 KV /35 KV 180 KV /105 KV 170 KV / 75 KV 95 KV ( r.m.s) 80 KV ( r.m.s) 27 KV ( r.m.s) 5.0 Mechanical Load: 5.1. The minimum failing load of the insulator shall 70 KN and the load shall be applied transverse. 6.0 Creepage Distance: 6.1. The minimum total creepage distance for insulator shall be suitable for heavily polluted and humid atmospheric conditions and shall be 400mm (for 11KV) & 900mm (for 33 K) in vertical position. 7.0 Marking: 7.1. Each insulator shall be legibly and indelibly marked to show the following: i) Name and trade mark of the manufacturer ii) Month and year of manufacture iii) Minimum failing load in KN iv) Country of manufacturer. v) ISI certificate marking if any The marking on porcelain shall be printed and shall be applied before firing. 8.0 Packing: 8.1. All insulators shall be suitably packed and crated to standard packing practice as required under Railway Regulation to withstand rough handling during transit. 9.0 Tests: The insulator shall stand the entire following test as per IS: 731/1971 (incorporating latest amendments and revisions). 9.1. Type tests – The following type tests shall be conducted on the insulators (which have already passed the routine test): i) Visible discharge test (power frequency voltage) ii) Impulse voltage withstand test iii) Impulse voltage flashover test iv) Verification of dimension v) Wet one minute power frequency test and wet flashover tests vi) Visual examination vii) Mechanical failing load test viii) Porosity test 9.2. The tenderer shall furnish copies of test certificates of the type test carried on identical manufacturer with guaranteed performance data for the insulators which they offer for supply. The report of type tests (on the insulator which is passed the routine tests) tested in the National Test House, Alipore and or such similar Government recognized Test House/ Institutions shall be invariably submitted along with the tender. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 180 Technical Specification 9.3. Sample/ Acceptance tests: The samples (after withstanding the routine test) shall also be subjected to the following sample acceptance tests as per ISS. ix) Verification of dimensions x) Temperature cycle test xi) Mechanical failing load test xii) Power frequency puncture withstands test xiii) Porosity test 9.4. The following routine and factory tests shall be conducted at the time of manufacture as per ISS. xiv) Visual examination xv) Electrical test 10.0 1) 2) 3) a. b. c. d. e. 4) a. b. c. d. e. f. g. h. i. 5) 6) Guaranteed technical particulars: (To be filled by the tenderer) Name and address of manufacturer. Trade mark of manufacturer to the legibly marked in the insulator. Mechanical characteristic. Total creepage distance in mm. Overall height of insulator in mm Overall diameter of insulator in mm. Overall weight of insulator in Kg. Minimum failing load in KN. Electrical characteristic Visibly discharge voltage. (power frequency voltage) Dry one minute power frequency withstands voltage. Wet one minute power frequency withstands voltage. Power frequency puncture withstands voltage. Impulse (1/50 micro second wave) withstands voltage. Impulse flashover (1/50 micro second wave) voltage. Impulse flashover (1/50 micro second wave) voltage negative. Dry flash over voltage. Wet flash over voltage. Standard specification to which insulator will conform. Other particulars, if any. 11.0 Inspection: All tests and inspections shall be carried out at the place of manufacturer unless otherwise agreed by the purchaser and the manufacturer at the time of purchase. The manufacturer shall afford the inspector representing the purchaser all reasonable facilities, without charge to satisfy that the materials are being purchased as per specifications. The purchaser reserves the right to have tests carried out at his own cost by an independent agency, whenever there is dispute regarding the quality of the material supplied. 12.0 Drawing and Sample: Drawing specifically showing all dimensions is to be submitted along with technical bids. Sample should be furnished alongwith the tender for verifications. Firms whose samples have been approved earlier need not submit the same. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 181 Technical Specification 3.18 TECHNICAL SPECIFICATION FOR 33 KV COMPOSITE POLYMERIC DISC INSULATORS 70 KN 1.0 SCOPE This specification cover the design, manufactures, testing at manufacturer's works, transport to site, insurance, storage, erection and commissioning of 33 kV composite polymeric disc insulator for 33 kV line. 2.0 STANDARD Strain insulators Tongue and Clevis type/ ball and socket type, suitable for 33 KV lines shall be conforming to IEC : 1109 with its latest amendments and revision and having mechanical failing load of 70 K.N. Insulators conforming to any other internationally accepted standards which ensure equal or higher quality than the standard mentioned would also be acceptable. A high class quality, corrosion resistant, fiberglass reinforced rod is the core of every insulator with ultimate mechanical strength at least twice the maximum working load. Where the material is offered according to the inter-national accepted standard a copy of the specification shall be attached with the tender. 2.1 GENERAL REQUIREMENT: The composite polymer insulator should be uni-body design and injection molded directly to the rod and sealed to the end fittings with bead of silicon to give the insulator high dielectric strength and protect it from all environmental conditions. The design of the insulator shall be such that stress due to expansion and contraction in any part of the insulator shall not lead to deterioration. 2.2 The insulator shall be in one piece. 2.3 CLIMATIC CONDITIONS.: i. Maximum ambient temperature in shade ii. Minimum daily average ambient air temperature iii. Maximum yearly average ambient air temperature iv. Maximum ambient temperature v. Maximum relative humidity vi. Average number of thunder storms days per annum vii. Average number of rainy days per annum viii. Average annual rainfall ix. Number of months of tropical monsoon conditions x. Maximum wind pressure xi. Altitude not exceeding 2.4 BASIC INSULATION LEVEL The test voltage (minimum requirement) of the insulator shall be as follows: a) b) c) d) e) f) 2.5 : 40°C : 35°C : 30°C : 2°C : 93% : 45 days : 150 days : 2280 mm : 5 months : 150 Kg/sq.m : 1000 M Highest system voltage Min. Creepage distance Section length Rated mechanical tensile load Wet frequency 1 min. withstand voltage Dry lighting impulse withstand voltage : 36 KV(rms) : 1050mm : 680mm : 70 KN : 85KV : 230KV MARKING Each insulator shall be legibly and indelibly marked to show the following: a) Name or trade mark of the manufacturer b) Month and year of manufacture c) Minimum failing load in KN d) Country of manufacture e) ISI certificate mark and name of the project under "TDF 2010-11" The marking on insulator shall be printed and shall be applied before suitably. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 182 Technical Specification 3 TEST 3.1 Type test The following type tests shall be conducted on a suitable number of individual insulator unit, components, materials or complete strings: Verification of dimensions Thermal mechanical performance test Power frequency voltage withstand and flashover test (i) dry (ii) wet Impulse voltage withstand and flashover test (dry) Visible discharge test (dry) RIV test (dry) Mechanical failing Load Test (for pin insulator only) 24 hrs. mechanical strength test (for strain I string insulator only) 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 4.0 a) b) c) d) e) f) g) h) i) j) k) l) m) n) o) p) Acceptance Tests Visual examination Verification of dimensions Temperature cycle test Galvanizing test Mechanical performance test Test on locking device for ball and socket coupling Eccentricity test Metallurgical test Grain size Inclusion rating Chemical analysis Microstructure Mechanical failing load test (for Pin Insulator only) Electro-mechanical strength test (for Strain insulator only) Porosity test Puncture test (for strain Insulator only) 4.1 Routine Tests a. Visual Inspection b. Mechanical routine test for Strain Insulator only) c. Electrical routine test (for Strain Insulator only) 4.2 Tests During Manufacture On all components as applicable Chemical analysis of zinc used for galvanizing Chemical analysis, mechanical, metallographic test and magnetic particle inspection for malleable castings. Chemical analysis hardness tests and magnetic particle inspection for forgings Hydraulic Internal Pressure tests On disc insulator shells a) b) c) d) 4.3 4.4 4.5 4.6 4.7 Test Reports Copies of type test reports shall be furnished in at least six (6)' copies along with one original. One copy shall be returned duly certified by the Owner only after which the commercial production of the concerned materials shall start. Copies of acceptance test reports shall be furnished in at least six (6) copies. One copy shall be returned duly certified by the Owner, only after which the material shall be despatch. Record of routine test reports shall be maintained by the Contractor at his works for periodic inspection by the Owner's representative. Test certificates of test during manufacture shall be maintained by the Contractor. These shall be produced for verification as and 'When desired by the Owner. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 183 Technical Specification 5.0 5.1 INSPECTION The Owner's representative or third party nominee shall at all times be entitled to have access to the works and all places of manufacture, where insulator, and its component parts shall be manufactured and the representatives shall have full facilities for unrestricted inspection of the Contractor's and sub Contractor's works, raw materials, manufacture of the material and for conducting necessary test as detailed herein. 5.2 The material for final inspection shall be offered by the Contractor only under packed condition as detailed in the specification. The Owner shall select samples at random from the packed lot for carrying out acceptance tests. 5.3 After placement of award, the Contractor shall submit fully dimensioned insulator drawings containing all the details, in four (4) copies to Owner for approval. After getting approval from Owner and successful completion of all the type tests, the Contractor shall submit 20 more copies of the same drawing to the Owner for further distribution and field use at Owner's end. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 184 Technical Specification 3.19 TECHNICAL SPECIFICATION FOR 11 KV COMPOSITE POLYMERIC INSULATORS 1.0 SCOPE This section covers the specifications for design, manufacture, shop & laboratory testing before despatch of 11 kv composite polymeric pin insulators .The Composite insulator shall be pin insulator for straight line location and Long rod insulator for conductors in tension application at angle/ cut point, the insulator shall be of boll and socket type or tongue & Clevis type. 1.1 STANDARDS Sl. Indian No. Standard 1. 2. IS:731 3. 4. IS:2071 IS:2486 5. 6. IS:13134 7. 8. 12. 13. 14. 15. 16. IS:8263 IS:4759 IS:2629 IS:6745 IS:3203 IS:2633 17. 18. 19. Definition, test method and acceptance criteria for composite insulators for a. c. overhead lines above. Porcelain insulators for overhead power lines with a nominal voltage greater than 1000V Methods of High voltage testing Specification for insulator fitting for overhead power lines with a nominal voltage greater than 1000V General Requirements and tests Dimensional Requirements locking devices. Thermal mechanical performances test on string insulator units. Guide for the selection of insulators in respect of polluted conditions. Characteristics of string insulator units of the long rod type. Hydrophobicity classification 9. 10. 11. Title IS:4699 Radio interference characteristics of overhead power lines and high-voltage equipment Methods of RI test of HV insulators Standard for insulators- composite distribution dead end type Hot dip Zinc coatings on structural steel & other allied products. Recommendation of weight for hot, dip galvanization for iron and steel Determination of weight of Zinc coatings on zinc coated iron and steel articles Method of testing of local thickness of electroplated coating Testing of uniformity of coating of zinc coated articles Standard specification for glass fiber standards Standard test method for compositional analysis of thermogravimetry Specification for refined secondary Zinc Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 International Standard IEC:61109 IEC:60383 IEC:60060-1 IEC:60120 IEC:60372 IEC:60575 IEC:60815 IEC:60433 STRI GUIDE 1.92/1 CISPR:18-2 PART2 IEC:60437 ANSI c29.13-2000 ISO:1459 ISO:1461 ISO:1461(E) ISO:1460 ISO:2178 ASTM D 578-05 ASTME 1131- 03 Assam Power Distribution Company Ltd 185 Technical Specification 1.2 SERVICE CONDITION Maximum ambient temperature :* *480 C Minimum ambient temperature : - 50 C Relative humidity : 0 to 100% The size of composite insulator, minimum creepage distance and mechanical strength alongwith hardware fittings shall be as follows. Minimum Creepage Wet distance (mm) Nomi power Impuls Pin Type Visible nal Higest freque e ball Normal Hea Sl of dischar Min. syste system ncy withsta shan & vily . compo ge test Failing m voltage withst nd kdia moder pollu N site voltage load voltag KV and voltage mete ately ted o. insulat KV KN e KV (rms) voltag KV r pollute (25m or (rms (rms) e KV (rms mm d m/ (rms (20mm/ KV) KV) i Long 11 12 9 35 75 240 320 45 16 rod insula 33 36 27 75 170 720 900 45/70** tor ii Post/ 11 12 9 35 75 240 320 5 pin insula 33 36 27 75 170 720 900 10 tor Dimensional Tolerance of composite insulators ±(0.04d=1.5) mm when d < 300 mm ±(0.025d=6) mm when d < 300 mm REQUIRED TECHNLCAL PARICULARS OF COMPOSIT POLYMERIC INSULATOR FOR 11 KV , 5 KN PIN INSULATOR TYPE Sl. no Description Unit 11KV , 5 KN , PIN INSULATOR 1. Type of Insulator Composite polymeric Insulators 2. Standard according to which the IES-61109 with up to date Insulator manufacture and tested amendments 3. Name of material used in Silicon/ Polyolefin material manufacture Of the insulator with class/grade (a) Material of core (FRP rod) ECR glass boron content i) E-glass or ECR- glass free ii) Boron content (b) Material of housing &Weather 36% sheds Silicon content by weight (c) ( material of end fitting ) (d) 4. 5. (a) (b) Sealing compound for end fittings Color Electrical characteristics Normal system voltage Highest system voltage Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Hot dip galvanized high strength steel Silicon based sealants Grey/ Red KV(rms ) KV(rms) 11 KV 12 KV Assam Power Distribution Company Ltd 186 Technical Specification (c) Dry power Frequency withstand voltage (d) Wet power frequency withstand voltage (e) Dry flashover voltage (f) Wet flashover voltage (g) Dry lighting impulse withstand voltage a) Positive b)Negative (h) (i) (j) 6. (a) Dry lighting impulse flashover voltage c) positive d) Negative R/V at 1MHz when energized at 10KV/30KV(rms) under dry condition Creepage distance (mm) Mechanical characteristics Minimum failing load KV(rms ) 35 KV KV (rms ) 35 KV KV(rms) KV(rms) KV(peak) >35KV >35KV KV(peak) 75KV 75 KV KV(peak) 95KV 95 KV KV(peak) Microvolt As per IES specification mm 320 mm KN 5KN REQUIRED TECHNLCAL PARICULARS OF COMPOSIT POLYMERIC INSULATOR FOR 11 KV , 45 KN ( T & C ) TYPE Sl. no Description Unit 11KV , 45 KN , T& C type 1. Type of Insulator Composite polymeric Insulators 2. Standard according to which the IES-61109 with up to date Insulator manufacture and tested amendments 3. Name of material used in Silicon/ Polyolefin material manufacture Of the insulator with class/grade (a) Material of core (FRP rod) ECR glass boron content i) E-glass or ECR- glass free ii) Boron content (b) Material of housing &Weather 36% sheds Silicon content by weight (c) ( material of end fitting ) (d) 4. 5. (a) (b) (c) Sealing compound for end fittings Color Electrical characteristics Normal system voltage Highest system voltage Dry power Frequency withstand voltage Wet power frequency withstand voltage Dry flashover voltage Wet flashover voltage (d) (e) (f) Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Hot dip galvanized high strength steel Silicon based sealants Grey/ Red KV(rms ) KV(rms) KV(rms ) 11 KV 12 KV 35 KV KV (rms ) 35 KV KV(rms) KV(rms) >35KV >35KV Assam Power Distribution Company Ltd 187 Technical Specification (g) Dry lighting impulse withstand voltage a) Positive b)Negative (h) (i) (j) 6. (a) 7. Dry lighting impulse flashover voltage c) positive d) Negative R/V at 1MHz when energized at 10KV/30KV(rms) under dry condition Creepage distance (mm) Mechanical characteristics Minimum failing load Dimension of insulator KV(peak) KV(peak) 75KV 75 KV KV(peak) KV(peak) 95KV 95 KV Microvolt As per IES specification mm 320 mm KN 45KN Inter changeability The composite insulators including the end fitting connection shall be of standard design suitable for use with the hardware fittings of any make conforming to relevant IEC/IS standards. Corona and RI performance All surfaces shall be clean, smooth without cuts, abrasions or projections. No parts shall be subjected to excessive localized pressure. The insulator and metal parts shall be so designed and manufactured that it shall avoid local corona formation and not generate any radio interference beyond specified limit under the operating conditions. Core It shall be a glass – fiber reinforce epoxy resin rod of high strength (FRP rod). Glass fibers and resin shall be optimized in the FRP rod. Glass fibers shall be Boron free electrically corrosion resistant(ECR) glass fiber or boron free E- class and shall exhibit both high electrical integrity and high resistance to acid corrosion . the matrix of the FRP rod shall be Hydrolysis resistant. The FRP rod shall be manufactured through pultrusion process . the FRP rod shall be void free. Housing (Sheath) The FRP rod shall be covered by a seamless sheath of a silicon elastometric compound or silicon alloy compound of a thickness of 3 mm minimum. It should protect the FRP rod against environment influences, external pollution and humidity. It shall be excluded or directly moulded on the core and shall have chemical bonding with the FRP rod. The strength of the bond shall be greater than the tearing strength of the polymer. Sheath material in the bulk as in the sealing/ bonding area shall be free from voids. Weather sheds The composite polymer weather sheds made of silicon elastomeric compound of silicon alloy shall be firmly bounded to the sheath, vulcanized to the sheath or moulded as part of the sheath and shall be free from imperfections. The weather sheds should have silicon content of minimum 30% by weight. The strength of the weather sheds to sheath interface shall be greater than the tearing strength of the polymer. The interface, if any, between sheds and sheath (housing) shall be free from voids. End Fittings End fittings transmit then mechanical load to the core. They shall be made of spheroid graphite cast iron, malleable cast iron or forged steel or aluminium alloy. They shall be connected to the rod by means of a controlled compression technique. The gap between fitting and sheath shall be sealed by a flexible silicon elastomeric compound or silicon alloy compound sealant. System of attachment of end fitting to the rod shall provide superior sealing performance between housing, i.e. seamless sheath and metal connection. The sealing must be moisture proof. The dimensions of end fittings of Insulators shall be in accordance with the standard dimensions stated in IS:2486/IEC:60120 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 188 Technical Specification Equipment Marking 5.1 Each insulator unit shall be legibly and marked with the following details as per IEC61109 (a) Month & Year of manufacture (b) Min. Failing load/ guaranteed mechanical strength in kilo Newton followed by the word KN to facilitate easy identification. (c) Manufacture‘s name / trade mark. 5.2 One 10mm thick ring or 20mm thick spot of suitable quality of paint shall be marked on the end fitting of each composite long rod of [particular strength in case of 33 KV insulators for identification in case both type of insulators are procured by the utility. The paint shall be not have deteriorating effect on the insulator performance, following codes shall be used as identification mark: For 45 KN Long unit : Blue For 70 KN Long unit : Red 6.0 Bid Drawings 6.1 The full description and illustration of the materials offered. 6.2 The bidder furnish alongwith the bid the outline drawing ( 3 copies ) of each insulator unit including a cross sectional view of the long rod insulator unit. The drawing shall include but not be limited to the following information. (a) Long rod diameter with manufacturing tolerance. (b) Minimum creepage distance with positive tolerance. (c) Protected creepage distance. (d) Eccentricity of the long rod unit (i) Axial run out (ii) Radial run out (e) Unit mechanical and electrical characteristics (f) Size and weight of ball and socket/ tongue & cleaves (g) Weight of composite long rod units (h) Materials (i) Identification Mark (ii) Manufacturer‘s catalogue number 7.0 Type tests Sl. No. 1. Description of type test Test procedure / standard As per IEC 61109 (Clause 6.1) 2. 3. 4. Dry lightning impulse withstand voltage test Wet power frequency test Mechanical load- time test Radio Interference test 5. Recovery of Hydrophobicity test 6. Chemical composition test silicon content Brittle fracture resistance test 7. 8.0 8.1 for As per IEC 61109 (Clause 6.2) As per IEC 61109 (Clause 6.4) As per IEC 61109 (Clause 6.5) revised Annexure-B This test may be repeated every 3 yrs by the manufacturer Annexure-B or any other test method acceptable to the owner Annexure-B Acceptance (Sample) Tests For Composite Insulators A Verification of dimensions B Verification of the locking system ( if possible) C Galvanizing Test D Verification of the specified mechanical load Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Clause 7.2 IEC:61109 Clause 7.3 IEC:61109 IS 2633 / IS 6745 Clause 7.4 IEC:61109 Assam Power Distribution Company Ltd 189 Technical Specification 8.2 8.3 Routine Tests Sl. Description No. 1. Identification of marking 2. Visual Inspection 3. Mechanical routine test Standard As per IEC:61109 Clause 8.1 As per IEC:61109 Clause 8.2 As per IEC:61109 Clause 8.3 Tests During Manufacture Following tests shall also be carried our A Chemical analysis of zinc used for galvanizing B Chemical analysis, mechanical, metallographic test and magnetic particle inspection for malleable castings C Chemical analysis, hardness and magnetic particle inspection for forigngs Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 190 Technical Specification 3.20 TECHNICAL SPECIFICATION FOR HARDWARE FITTING FOR DISC INSULATOR, 70 KN( B& S) 1.0 Scope: This specification covers design, drawings, manufacture, testing at manufacturers‘ works, supply and delivery of hardware fittings for strain insulator of ball & socket type . The fitting shall consist of the following component : a) Cross arm strap conforming to IS: 2486 ( Pt-II)-1989. b) Forged steel ball eye for attaching the socket end of the strain insulator to the cross arm strap. Forging shall be made of steel as per IS : 2004-1978. c) Aluminium alloy thimble socket made out of permanent mould cast , high strength aluminium alloy for attaching to the strain insulator on one end and for accommodating the loop of the helically formed dead-end fittings at the other end in its smooth internal contour. The thimble socket shall be attached to the strain insulator with the help of locking pin as per the dimension given in IS: 2486(PT-II)-1989 d) Helically formed dead-end grip having a pre-fabricated loop to fit ito the grooved contour to the thimble on one end and for application over the conductor at the other end. The formed fitting shall conform to the requirement of IS:12048-1987. 2.0 Tests: The helically formed fittings for strain insulators shall be subjected to tests as per IS:12048-1987. The other hardware fittings shall be tested as per IS:2486 (Part-I) 3.0 Packing: For packing of strain clamps and related hardware, double gunny bags or wooden cases shall be used. The fittings shall be properly protected against damage. The gross weight of the packing shall not normally exceed 50 Kg. Helically formed fittings shall be packed in card board / wooden boxes. Fittings for different sizes of conductors shall be packed in different boxes and shall be complete with their minor accessories fitted in place and colour codes on tags / fittings shall be marked to identify suitability for different sizes of conductors as per IS:12048-1987 4.0 Inspection: All tests and inspections shall be made at the place of manufactur unless otherwise especially agreed upon by the manufacturer and purchaser at the time of purchase. The manufacturer shall afford the inspector representing the purchaser all reasonable facilities, without charge, to satisfy him that the material is being furnished in accordance with this specification. The purchaser has the right to have the tests carried out at his own cost by an independent agency whenever there is dispute regarding the quality of supply. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 191 Technical Specification 3.21 TECHNICAL SPECIFICATION FOR POLYMERIC 33 KV AND 11 KV PIN INSULATOR 1.0 Scope This specification covers design, manufacture, testing at manufacturer‘s works, transport to site, storage, insurance, erection and commissioning of polymeric 33 KV pin insulator for 33 kV lines. 2.0 Standard Polymeric compact insulator with suitable groove in upper pin and long threads in lower part of the pin with nuts, suitable for 33 KV lines shall be conforming to IEC : 1109 with its latest amendments and revision and having minimum mechanical failing load of 10 K.N. Insulators conforming to any other internationally accepted standards which ensure equal or higher quality than the standard mentioned would also be acceptable. A high class quality, corrosion resistant, fiberglass reinforced rod is the core of every insulator with ultimate mechanical strength at least twice the maximum working load. 3.0 General Requirements 4.0 The composite polymer insulator should be uni-body design and injection molded directly to the rod and sealed to the end fittings with bead of silicon to give the insulator high dielectric strength and protect it from all environmental conditions. The design of the insulator shall be such that stress due to expansion and contraction in any part of the insulator shall not lead to deterioration. 5.0 The insulator shall be in one piece. The dimensions of the pins insulator shall be as follows: 33 KV 11KV a) Composite insulator length 310 mm 210 MM b) Failing minimum load 10 KN 5 KN c) Creepage distance (min) mm 925 mm 580 mm d) Dry power frequency 1 min withstand voltage 70 kV (RMS) 70 kV(RMS) e) Wet power frequency 1 min withstand voltage 70 kV (RMS) 70 KV(RMS) f) Dry lightning impulse withstand voltage 170 Kvp 145 Kvp 6.0 Tests Pin shall comply with the following tests. 1.1 Type test: a) Visual examination test b) Verification of dimensions c) Checking of threads d) Galvanizing test e) Mechanical strength tests 1.2 Routine test: a) Visual examination test 1.3 Acceptance test: Checking of threads on heads a) Galvanizing test b) Mechanical test 7.0 Inspection All tests and inspections or shall be carried out at the place of manufacturers unless otherwise agreed by the purchaser and the manufacturers at the time of purchase. A manufacturer shall afford the inspector or third party nominee representing the purchaser all reasonable facilities, without charge to satisfy that the materials are being purchased as per specification. The purchaser reserved the right to have the test carried out at his co.st by an independent agency, whenever there is dispute regarding the quality of the materials supplied. 8.0 Marking The pins shall be marked with name of manufacturer, year and name of project. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 192 Technical Specification 3.22 TECHNICAL SPECIFICATION FOR 33 kV AND 11kV PIN INSULATOR 1.0 SCOPE This specification covers the design, manufacture, testing at manufacturer's works, transport to site, insurance, storage, erection and commissioning of insulators required for 33 kV and 11kV lines. 2.0 STANDARD 2.1 2.2 2.3 2.4 2.5 3.0 The pin insulators shall comply with the Indian Standard specification IS : 731/1971 as amended from time to time having mechanical failing load of 10 K.N for 33 kV insulator and 5KN for 11kV insulator. Insulators conforming to any other internationally accreted standards which ensure equal or higher quality than the standard mentioned would also be acceptable. Where the material is offered according to the inter-national standard a copy of the specification shall be attached with the tender. General requirement: The porcelain should be sound, free from defects, thoroughly vitrified and smoothly glazed. Unless otherwise specified, the glaze shall be brown colour. The glaze shall cover all the porcelain parts of the insulators except those areas which serve as support during firing or are left unglazed for purpose of assembly. The design of the insulator shall be such that stress due to expansion and contraction in any part of the insulator shall not lead to deterioration. The porcelain shall not engage directly with hard metal. Cement used in the construction of insulator shall not cause fracture by expansion or loosening by contraction and proper care shall be taken to locate the individual parts correctly during cementing. The cement shall not give rise to chemical reaction with metal fitting and its thickness shall be as uniform as possible. The insulator shall be multi-petty-coat type. BASIC PARAMETER: Sl No Particu lars 1 Type of insulator 2 Applicable Standard 3 Material 4 5 6 7 8 9 10 11 Dimension Minimum failing load Creepage distance Nominal System voltage Highest system voltage (rms) Wet one minute power frequency test(rms) Dry one minute power frequency test (rms) Power frequency flush over voltage (Dry) 33 KV Pin Insulator 11kV Pin Insulator IS : 731/1971 Porcelain sound, free from defects, thoroughly vitrified and smoothly glazed. 210x280x145 mm 155x160 mm 10 KN 5KN 580 mm 320mm 33kV 11kV 36 KV 12kV 75 KV 95 KV 95 KV Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 193 Technical Specification 12 13 14 4.0 Power frequency flush over voltage (Wet) Power frequency puncture withstand (rms) Impulse withstand voltage test(Peak) 80 KV 180 KV 170 KV MECHANICAL LOADS The minimum failing load of the insulators shall be 10 KN for 33 kV for 11kV and the load shall be applied in transverse direction. and 5KN 5.0 CREEPAGE DISTANCE The minimum total creepage distance for 33kV insulators shall be 580 mm and 320mm for 11 kV insulators. 6.0 MARKING Each insulator shall be legibly and indelibly marked to show the following: a. Name or trade mark of the manufacturer b. Month and year of manufacture c. Minimum failing load in KN d. Country of manufacture e. ISI certificate mark, if any f. Name of the Project The marking on porcelain shall be printed and shall be applied before firing. 7.0 Type Tests The following type tests shall be conducted on 'a suitable number of individual insulator unit, components, materials or complete strings: a) Verification of dimensions b) Thermal mechanical performance test c) Power frequency voltage withstand and flashover test (i) dry (ii) wet d) Impulse voltage withstand and flashover test (dry) e) Visible discharge test (dry) f) RIV test (dry) g) Mechanical failing Load Test (for pin insulator only) h) 24 hrs. mechanical strength test (for strain / string insulator only) 8.0 Acceptance Test a) Visual examination b) Verification of dimension c) Temperature cycle test d) Galvanizing test e) Mechanical performance test f) Test on locking device for ball and socket coupling g) Eccentricity test h) Metallurgical test i) Grain test j) Inclusion rating For metal fittings only (in black condition) k) Chemical analysis l) Microstructure. m) Mechanical failing load test (for Pin Insulator only) n) Electro-mechanical strength test (for strain insulator only) o) Porosity test p) Puncture test(for Strain Insulator only) Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 194 Technical Specification 9.0 ROUTINE TEST a) b) c) Visual Inspection Mechanical routine test (for Strain Insulator only) Electrical routine test (for Strain Insulator only) 10.0 Tests During Manufacture On all components as applicable a) Chemical analysis of zinc used for galvanizing b) Chemical analysis, mechanical, metallographic test and magnetic particle inspection for malleable castings. c) Chemical analysis hardness tests and magnetic particle inspection for forgings d) Hydraulic Internal Pressure tests On disc insulator shells 11.0 Test Reports Copies of type test reports shall be furnished in at least three (3) copies along with one original. One copy shall be returned duly certified by the Owner only after which the commercial production of the concerned materials shall start. 11.1 Copies of acceptance test reports shall be furnished in at least six (6) copies. One copy shall be returned duly certified by the Owner, only after which the material shall be despatch. 11.2 11.3 Record of routine test reports shall be maintained by the Contractor at his works for periodic inspection by the Owner's representative. Test certificates of test during manufacture shall be maintained by the Contractor. These shall be produced for verification as and when desired by the Owner. 12.0 Inspection a) The Owner's representative or third party nominee shall at all times be entitled to have access to the works and all places of manufacture, where. insulator, and its component parts shall be manufactured and the representatives shall have full facilities for unrestricted inspection of the Contractor's and ;1ub-Contractor's works, raw materials, manufacture of th::; material and for conducting necessary test as detailed herein. b) The material for final inspection shall be offered by the Contractor only under packed condition as detailed in the specification. The Owner shall select samples at random from the packed lot for carrying out acceptance tests. Insulators shall normally be offered for inspection in lots not exceeding 5000 nos. the lot should be homogeneous and should contain insulators manufactured in the span of not more than 3-4 consecutive weeks. c) The bidder shall keep the Owner informed in advance of the time of starting and the progress of manufacture of material in their various stages so that arrangements could be made for inspection. d) No material shall be dispatched from its point of manufacture before it has been satisfactorily inspected and tested unless the inspection is waived off by the Owner in writing. In the latter case also the material shall be dispatched only after satisfactory testing for all tests specified herein have been completed. e) The acceptance of any quantity of material shall be no way relieve the Contractor of his responsibility for meeting all the requirements of the specification and shall not prevent subsequent rejection, if such material are later found to be defective. 13.0 BID DRAWING The Bidder shall furnish full description and illustration of the material offered. The Bidder shall furnish along with the bid the outline drawing (6 copies) of each insulator unit including a cross sectional view of the insulator shell. The drawing shall include but not limited to the following information: a. Dimensions with manufacturing tolerances b. Minimum creepage distance with positive tolerance c. Protected creepage distance d. Eccentricity of the disc Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 195 Technical Specification i. Axial run out ii. Radial run out e. Unit mechanical and electrical characteristics f. Size and weight of Pin Ball Shank / ball and socket parts g. Weight of unit insulator disc h. Materials i. Identification mark j. Manufacturer's catalogue number After placement of award, the Contractor shall submit fully dimensioned insulator drawings containing all the details, in four (4) 'copies to Owner for approval. After getting approval from Owner and successful completion of all the type tests, the Contractor shall submit 20 more copies of the same drawing to the Owner for further distribution and field use at Owner's end. 14.0 Guaranteed Technical Particulars The guaranteed technical particulars in respect of the Pin Insulators offered shall be submitted along with the tender. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 196 Technical Specification 3.23 TECHNICAL SPECIFICATION FOR G.I. PIN OF 33kV and 11kV PIN INSULATOR 1.0 1.1. Scope This specification covers design, manufacture, testing at manufacturer‘s works, transport to site, storage, insurance, erection and commissioning of galvanized forged steel pins for use in 11 KV and 33 kV lines. 2.0 Standard 2.1. The galvanized Iron forged steel pins shall be of type L-230 N conforming to IS 2486 (PT-I/1971) and IS: 2486 (PT-11/1963) having stalk length of 300 mm and shank length of 150 mm with minimum failing load of 10 kN. Details of the pin are shown in the drawing. 2.2. The pins conforming to any other internationally accepted standards which ensure equal or higher quality than the standard mentioned would also be acceptable. 3.0 General Requirements 3.1. The pins shall be single piece obtained by process of forging. They shall not be made by joining, welding, shrink fitting or any other process for more than one piece of materials. They shall be of good finish, free from flaws and other defects. The finish of the collar and the shank is avoided. All ferrous pins, nuts spring washers shall be galvanized and small fittings like spring washers, nuts etc. may be electroplated with zinc. The threads of nuts and tapped holes etc. shall be rounded. The galvanizing should be as per ISS: 2633/1964. 3.2. 3.3. The dimensions of the 33kV Pins shall be as follows: Particulars Minimum failing load Stalk length Shank length Thickness of collar 33kV Pin 10KN 230mm 150 mm 6 mm 11kV Pin 5KN 165mm 150mm 5mm Diameter of collar Diameter of shank Threaded length of shank Diameter of stalk head Threaded length of stalk 50 mm 24 mm 100 mm 27.78 mm 47 mm 40mm 20mm 100mm 18.29 40mm 3.4. The pins shall have minimum failing load of 10 kN and 5KN for 33 kV.and 11kV Pin respectively. 3.5. Tests Pin shall comply with the following tests. Type test: 3.6. e) Visual examination test f) Verification of dimensions g) Checking of threads h) Galvanizing test e) Mechanical strength tests Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 197 Technical Specification 3.7. Routine test: a) Visual examination test 3.8. Acceptance test: Checking of threads on heads c) Galvanizing test d) Mechanical test 4.0 Inspection 4.1. All tests and inspections or shall be carried out at the place of manufacturers unless otherwise agreed by the purchaser and the manufacturers at the time of purchase. A manufacturer shall afford the inspector or third party nominee representing the purchaser all reasonable facilities, without charge to satisfy that the materials are being purchased as per specification. The purchaser reserved the right to have the test carried out at his cost by an independent agency, whenever there is dispute regarding the quality of the materials supplied. 5.0Marking 5.1. The pins shall be marked with name of manufacturer, year and name of project. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 198 Technical Specification 3.24 TECHNICAL SPECIFICATION FOR AAA “WOLF” & “RACCOON” CONDUCTOR 1.0 2.0 3.0 4.0 Scope This specification covers design, manufacture, testing at works, transport, insurance, storage, erection and commissioning of All Aluminum Alloy Stranded Conductors at site in 33 KV. Conductor Size 13.0 19/3.40 mm (175 mm² Alloy Area) – wolf 14.0 7/3.81 mm ( 80 mm² Alloy Area ) - Raccoon Applicable Standards Unless otherwise stipulated in this specification, the conductor shall comply with IS:398 (Part-IV)- 1994 or the latest version thereof. Properties of Wires The properties of Aluminium alloy wires to be used in the construction of the stranded conductors shall be as in the following Table-1 Table-1 Cross Maximum area of Diameter breaking nominal Mass Resistance at 20° C load after Dia stranding wire Nominal Min Max Max Stamdard 2 Mm mm mm mm Kg/Km KN Ohm/Km Ohm/Km 3.40 3.37 3.43 9.079 24.51 2.80 3.67 3.96 3.81 3.77 3.85 11.401 30.78 3.34 2.938 2.851 5.0 6.0 Properties of Conductors The properties of stranded all aluminium alloy conductors of various sizes shall be as in the following table-II All Aluminium Alloy Conductors ( AAAC) Nomin al Alloy Area Stranding & Wire dia Sectional area Approx. overall dia Approx. Mass 1 mm2 173 80 2 Mm 19/3.40 7/3.81 3 mm2 172.52 79.81 4 mm 17.00 11.43 5 Kg/Km 474.02 218.26 Calculate d resistanc e at 20° C (Max) 6 Ohm/Km 0.1969 0.425 Approx calculate d breaking load 7 KN 50.54 23.41 Free From Defects The wire shall be smooth and free from all imperfection such as spills, splits etc. 7.0 Joints in Wires Conductors containing three/seven wires. There shall be no joint in any wire of a stranded conductor containing three/seven wires except those made in the base rod or wire before final drawing. 8.0 Stranding 8.1 The wires used in the construction of a stranded conductor shall before stranding satisfy all the relevant requirements of this standard. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 199 Technical Specification 8.2 The lay shall be within the limits given in Table-III Lay Ratios for Aluminium Alloy Stranded Conductors No. of wires in conductors 7 19 Lay ration Min. 10 10 Max 14 16 8.3 The outer layer shall be right handed. The wires in each layer shall be evenly and closely stranded. 9.0 Climatic Conditions The conductor shall be designed to suit for the climatic conditions specified in these bidding documents. 10.0 Tests The samples of individual wires for the test shall normally be taken before stranding. The manufacturer shall carry out test on samples taken out at least from 10% of aluminium wire spools. However, when desired by the purchaser, the test sample may be taken form the stranded wires. However the minimum breaking load test shall be done on a sample taken from stranded wires and the minimum breaking load shall not be less than the value indicated in Table-I. The wires for alloy conductors shall comply with the following tests as per IS: 398(Part-IV)-1994 i) Breaking loads test. ii) Elongation test iii) Resistance test 11.0 Packing and Marking The conductors shall be owned in reels or drums conforming to the latest version of IS: 1778-1980 ― Specification for reels and drums for bare wire and name of the project TDF shall be indicated clearly on the drums. 10.1 Packing 10.1.1 The gross mass of packing of various conductors shall not exceed by more than 10% of the values given in the following table: Conductor size Gross Mass 2 175 mm alloy area ( 19/3.40mm) 2500 80 mm² Alloy Area (7/3.81 mm) 1600 KG 10.1.2 The normal length of various conductors shall be as given in the following table: Conductor size 175 mm2 alloy area ( 19/3.40mm) 80 mm² Alloy Area (7/3.81 mm) Normal Length 1.1 Km 1.3 KM 10.1.3 Longer lengths shall be acceptable. 10.1.4 Short length , not less than 50% of the normal length shall be acceptable to the maximum extent of 10% of the quantity ordered 10.2 marking. The following information be marked on each package. 14.1. Manufacturer‘s name. 14.2. Trade Mark, if any. 14.3. Drum or identification number. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 200 Technical Specification 14.4. Size of conductor 14.5. Number & lengths of conductor 14.6. Gross Mass of the package 14.7. Net mass of the conductor 14.8. ISI certification mark. 14.9. Name of the Project TDF 11 INSPECTION All tests and inspection shall be made at the place of manufacture. The manufacturer shall afford the inspection representing the purchaser or third party nominee all reasonable facilities without charge to satisfy him that the material is being furnished in accordance with this specification. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 201 Technical Specification 3.25 TECHNICAL SPECIFICATION FOR HARDWARE FITTINGS INCLUDING TENSION CLAMP ASSEMBLY (Aluminium Alloy) FOR “RACCOON” AND “WOLF” CONDUCTOR 1.0 2.0 3.0 4.0 Scope: This specification covers design, drawings, manufacture, testing at manufacturers‘ works, supply and delivery of suspension clamp for use with Raccoon (7/3.81mm-80 sqmm)/Wolf (19/3.4mm-175 sqmm )conductors within the state of Assam. Standard: The material and process adopted in the manufacture shall conform to the provision of the following standards amended up-to-date IS: 2486 specification for Insulator fitting for overhead power lines. General: The tension clamps offered shall be made of die cast high strength aluminium alloy and shall be suitable for use with ―Raccoon and Wolf‖ conductors together with one set of preformed armour rods. Suitable sheet metal liner shall be provided. The clamp shall move easy oscillation around horizontal axis. The bidder is to quote separately for suspension clamp: i) Envelope type ii) Bottom free centre type design. The single tension clamp shall consist of the following components: Description Quantity Material 1. Ball hook without provision for 1 no. Forged Steel Arching horn 2. Socket type without provision for 1set. MCI Arching horn 3. Tension clamp for AAAC 1 no Alumium alloy Raccoon /Wolf conductors The clamp shall be of high corrosion resistant, light in weight, have low effective power loss and small moment of inertia enabling it to follows freely the movements of the conductor The tension clamp shall also be provided with suitable socket or clevis eye for connecting it to the insulator string. The seat and clamping surface should be smooth, without any projections or sharp bends and should be formed to support the conductor on long, easy curves at the comparatively sharp bends. Minimum failing load = 70 KN. The slip strength of tension clamp shall not exceed 15% of the breaking load of the conductor. Tests: The hardware fittings shall be subjected to all the tests in accordance with relevant Indian Standard Specifications. The purchaser shall have the right to carryout acceptance tests, in the presence of representatives of the purchaser. The bidder shall submit type test certificate along with the tenders. The following tests shall be carried out. i) Type Test: (a) Slip Strength test for clamp. (b) Mechanical test for clamp & fittings (c)Heating cycle test. (d) Verification of dimensions. (e) Galvanizing / Electroplating test. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 202 Technical Specification (f) Visual examination test ii) Acceptance Test: a) Dimensional test. b) Galvanizing test. c) Mechanical test for clamp & fittings d) Electrical Resistance Test. iii) Routine Test: a) Visual examination test. b) Routine mechanical test. Guaranteed Technical Particulars (GTP) and drawing specifically showing all dimensions are to be submitted along with technical bids Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 203 Technical Specification 3.26 TECHNICAL SPECIFICATION FOR P.G CLAMP FOR AAA RACOON /WOLF CONDUCTOR 1.0 2.0 Style No. Scope: The scope covers design, manufacturing, testing at work, transport at site, insurance, storage, erection and commissioning of P.G. Clamp suitable for Conductor size Wolf/Raccoon/Weasel/3 Bolt Type strictly conforming to IS : 2121 and Galvanising conforming to IS : 2633 as per the following: Standards: P.G. Clamps suitable for conductor size, wolf/raccoon/weasel 3 bolt types strictly conforming to IS : 2121 and galvanizing conforming to IS: 2633 as per the following: P.G. clamp body to be made from aluminium alloy Clamps nuts and bolt and washer should be made of hot deep galvanized steel Spring washer be made of electro-galvanize special steel. Conducto r Maximum conductor diameter in mm A mm B mm C mm D mm E mm Dimensions No of Bolts Appro x. Weigh t Kg. A-83 Wolf 20.78 140 76 42 5/8 1 3 0.51 A-81 Racoon 14.45 95 57 30 1/2 2 2 0.18 3.0 Inspection may be carried out by the purchaser or third party nominee at any stage of manufacture. The supplier shall grant free access to the purchaser's representative or third party nominee at a reasonable time when the work is in progress. Inspection and acceptance of any equipment under this specification by the purchaser shall not relieve the supplier of his obligation of furnishing equipment in accordance with the specification and shall not prevent subsequent rejection if the equipment is found defective. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 204 Technical Specification 3.27 TECHNICAL SPECIFICATION OF XPLE CABLE FOR 11kV SYSTEM 1.0 SCOPE: The specification covers the design, testing, supply and delivery in proper packed condition of different grade of 1 or 3 core. Aluminium Conductor, Cross-linked polyethylene (XLPE) insulated, PVC sheathed, armoured, screened Power Cables. 2.0 1.1 1.2 3.0 LOCATION: The cables may be laid buried directly in ground at a depth of one metre in average, any where in Assam and terminate for outdoor connection to a power transformer or to overhead lines and also indoor connection for indoor switchgear. The cables may also be laid within covered cable trenches, in cable racks or open-air ladder trays etc. for certain portion of lengths. SYSTEM DETAILS: 3.1 Voltage grade (KV) of cable required 3.1 Service Voltage … 3.2 Highest Voltage 3.3 Earthing System 3.4 B.I.L. for Cables 3.5 Fault Level (Maxim.) … Reference source not found. 3.6 Frequency … … … 6.35/11 11 KV 12 KV Solidly Earthed 75 KV for 11 KV See Clause Error! 50 C/S. 4.1 STARDARDS: 4.2 The cable shall conform to the following standards to the extent of LAEDCL requirement is fulfilled. 1) IS : 7098 (Part – II) (Latest) :Specification for cross-linked polyethylene Insulated PVC Sheathed Cables for working Voltage from 3.3 KV up to and including 33 KV. 2) IS:8130 – 1984 :Specification for Conductors for insulated electric cables and flexible cords. 3) IS:5830 – 1984 :PVC insulation & sheath of electric cables. 4) IS:3975 – 1979 : Armour for cables (for 3 Crore). 5) IS:10810 – 1984 : Methods for test for cables. 6) IS:10418 – 1982 : Cable Drum for Electric Cables. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 205 Technical Specification 3.3 The cable, joints, outdoor and indoor termination and their accessories and fittings may conform to other Indian and/or equivalent standards or important publications to improve upon their performance, but shall not fall short of the requirement of this specification. The tenderer shall clearly indicate such standards in their offers. 4.0 ELECTRICAL CHARACTERISTICS & PERFORMANCE: 4.1 Description of Cable: a) 6.35/11 KV Grade 3-Crore : Same as above but insulation shielding with black semi-conducting tape not necessary. Inner sheath to be wrapped not extruded and strip armoured. The design shall fully conform to IS:7098 (Part – II). b) SPECIFIC TECHNICAL REQUIREMENTS Technical parameters of the cable shall be as follows: Sl No 1 2 3 4 5 Particulars Unit 11 KV Rated voltage Type of insulation Single Core Armoured /Unarmoured Material of Conductor KV - 6 7 8 9 10 System Highest System Voltage Material Voltage Grade Conductor Size KV - 11 Nominal dimention of Al. round wire 12 Nominal thickness of XLE insulationr sheath Approx overall cable diameter 11 XLPE Single , three Armoured Material to IS: 8130, H4 Grade Aluminium Conductor, Stranded compacted Circular 11 KV Earthed 12 Stranded Aluminium 6.35/11 KV 1x185,3x120 1x300 2.0mm[for 1x300sqmm ], 2.0mm [for 1x185sqmm & 2.5mm[3x120 sqmm], 3.6 mm 13 14 a Current rating In ground at 300C b In air at 400C 15 Maxm. Conductor Temp Sq. mm 61.50mm [for 3x120sqmm], 35.50mm [for 1x185sqmm] 40.00 mm [ for 1x300 sqmm], 219A(3x120sqmm), 296A(1x185sqmm) 381 A(1x300 sqmm) 288A(1x120sqmm), 378A(1x185sqmm) 512 A(1x300 sqmm 90 oC at maxm. Continuous current Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 206 Technical Specification 16 Short Ckt.Current for 1 second duration 17 19 Maxm.Permissible emergency overload temp. at 25% overload to 100 hrs. per year or 500 hrs. in life of cable Maxm. Permissible short circuit temperature Conductor Screening 20 21 Insulation Screening Conductor Screening 22 Insulation a Insulation Screening 18 b 23 Inner Sheathing 24 Armouring 25 Overall Sheathing 26 Approx. length of cable in a Drum End Sealing 27 a Max. ‗Tan-delta‘ at room temp. At nominal phase to neutral 11.3KA-for120 sqmm, 17.5 KA-for 185 sqmm, 28.3 KA – for 300 sqmm. 130 oC for one hour 250 oC for one hour Extruded, cross linked, semi-conducting compound of.5 mm for 11KV : Extruded, cross linked, semi-conducting compound of.5 mm for 11KV : XLPE of thickness, 3.6 mm (Nominal) for 11KV For Combination of black extruded semi33 conducting tape as the non-metallic part and KV : annealed copper 0.06 mm (minimum) thick tape lapping as metallic part. For 1 core cable, the non-magnetic metal Armour will act as metallic part insulation screening. For It is same but semi-conducting tape is not 11 required KV : : Black extruded PVC, Type ST-2 compound for 33 KV and wrapped PVC tape for 11 KV as per ISS. For 1 core there will be no inner sheath. : Single layer of round galvanized steel wires/strip for 33 KV and galvanized steel strips/wire for 11 KV (3 core) as per IS. For 1 core, there will be non-magnetic metal Armour. : Coloured PVC, type ST-2 compound to IS: 5831, extruded for both 33KV and 11KV thickness shall be as per ISS : 250 metres with a tolerance of ± 5% (for 3 core), 500 metres ± 5% (for 1 core) H.S. Caps (see clause 4.13.1) (Heat Shrinkable) 0.004 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 207 Technical Specification b 28 29 30 31 voltage (Uo): Maxm. Increment of ‗tan-delta‘ between 0.5 Uo to 2 Uo at room temp: Partial discharge value Impulse Tests H.V. Tests between Conductors & Screen/Armour Maxm. D.C. Rtance/Km : 0.002 20 Pc (Maxm.) at 1.6 Uo. 170 KV for 33 KV and as per ISS for 11 KV 48 KV (rms) for 33 KV for 5 minutes and as per ISS for 11 KV As per relevant I.S.S * NB the above parameters are applicable for three core and single core cable, if not otherwise specified. CABLE CONSTRUCTION: 4.3 XLPE underground cable is to be manufactured in continuous catenaries process at controlled elevated temperature and pressure in inert atmosphere with use of suitable materials for XLPE semiconducting, insulation and XLPE screen. The inner and outer semiconducting sheaths and main polyethylene insulation between the sheaths are to be simultaneously extruded during the Triple Extrusion Process of manufacturing and main insulation of the Cable is to be extruded unified. The XLPE Cables in this specification does not have any metal sheath and the short circuit rating of the cable will depend on the conductivity and continuity of the strands of the armour wires, which shall be ensured by guarding against corrosion. 4.4 CONDUCTOR SCREENING 4.5 A semi-conducting cross-linked polyethylene (XLPE) screening shall be extruded over the conductor to act as an electrical shield which together with elimination of the so called ―Strand Effect‖ prevents to a great extent air ionization on the surface of the conductor. 4.6 INSULATION: The main insulation of the Cable shall be extruded unfilled, chemically cross-linked polyethylene (XLPE) inert gas cured satisfying the requirement of ISS: 7098 (Part- II) 4.7 INSULATING SCREEN: The screen shall be made up as given in Clause 22the metal screen eliminates tangential stress electrostatic field surrounding the conductor and uniform electrical stress in the insulation. The semi conducting polyethylene (XLPE) screen shall be extruded over the main poly ethylene-insulating wall to prevent partial discharge at the surface of the insulation. The copper tape shall be wrapped over the semi conducting tape or extrusion as mentioned earlier for 3 core cables. The metal screen so formed around the cores shall be in contact with one Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 208 Technical Specification another as the cores are laid up at triangular configuration. For single core cable, Aluminium wires armoring shall constitute the metallic part of insulation screen. Conductor screening, insulation and insulation screening shall be extruded in triple extrusion processes so as to obtain continuously smooth interfaces. 4.8 The mechanical and chemical properties of the materials for semi conducting screens are much more important than their electrical properties, but for obtaining the high overall degree of electrical properties of an E.H.V. cable, the inner and outer semi conducting, sheaths and the main polyethylene insulation between the sheaths shall be simultaneously extruded during the manufacturing, process known as “triple extrusion”. The advantages are: i) The partial discharge level at the surface of the insulation is brought to a minimum. ii) There will be no displacement of the semi conducting screen and insulation during expansion and contraction due to load cycles and bending. iii) The semi conducting screens are easily removable during joining and termination operations. Note: Manufacturers not having “triple extrusion” process will be disqualified. The Tenderer shall have to produce necessary process line at the time of bidding. 4.9 LAYING UP: The phase identification of the cores shall be either by colour or numerals as per I.S.S. for 3 core cables only. Core Colour Numeral Red 1 Yellow 2 Blue 3 The screen cores shall be laid up with interstices filled with PVC fillers and taped a binder tape as to obtain a reasonably circular cable. 4.10 INNER SHEATH: The cable core shall be supplied with bedding of PVC (Inner sheath) in the form of extruded PVC sheath for 33 KV cables. Wrapped PVC tapes shall be used for 11KV thickness as per clause 23 of special technical parameters and as per relevant IS. 4.11 ARMOUR: The cable shall be wire armoured /steel strip in case of 33KV and wire/strip armoured 11 KV, three core cables to insure an adequate return path for the flow of fault current and also provide suitable mechanical protection. Steel wires/aluminum wire / steel strips of required size in requisite number as per clause 24 of special technical parameters shall be laid closely in the spiral formation to protect the circumference of the cable fully and to provide adequate cores section area for flow of maximum fault current within limits of specified Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 209 Technical Specification temperature rise and duration of fault. Direction of the lay of the armour shall be opposite to that of the cable cores in case of single core cable armour should be of non-metallic material. 4.12 OUTER SHEATH: A reliable surving shall be necessary for maintaining conductivity of the armour particularly under corrosive condition in the form of jacket. Cable shall be therefore finished with extruded PVC over sheath of thickness as per clause 25 of special technical parameters. The quality of PVC over sheath (jacket) shall be ensured for service reliability against moisture intrusion and shall confirm to type ST-2 of IS : 5831. The colour of the outer sheath shall be follows: For 11 KV cable : Blue The sheaths shall be protected against white ants, vermin and termites by suitable, durable and reliable measures. The suppliers shall suggest suitable materials for use, in the event of damage to the over sheath to prevent the passage of moisture along the cable. 4.13 CABLE IDENTIFICATION: The following shall be embossed on the outer sheath for the identification. Manufacturer‘s Name or Trade Mark. Voltage Grade. Nominal section and material of conductors and number of cores. Year of manufacture. Inscription of length of cables at 1.0 mtr interval. Name of purchaser LAEDCL; Marking ―Power‖ shall be embossed throughout the length of the cable at 10 mtr spacing. h) Type of insulation i.e. XLPE 4.13.1 CEILING OF CABLE ENDS: The cable ends of the cable in the wooden drum for delivery shall be sealed with heat shrinkable caps. a) b) c) d) e) f) g) 7.0 WOODEN DRUMS: The cable shall be packed in non-returnable wooden drums. The following information shall be marked on each drum. a) Drum identification number. b) Manufacturer‘s name, Trade name / Trade mark, if any. c) Nominal sectional area of the conductor of the cable. d) Number of cores e) Type of cable and voltage grade with cable code f) Length of cable in cable drum g) Direction of rotation of drum (by means of an arrow) h) Appox. Weight: tare: gross: i) Year and country of manufacture Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 210 Technical Specification j) Purchase order number k) Date of delivery l) Name of the purchaser. Drum shall be proofed against attack by white ant or termite conforming to IS: 10418. The Drums may also be marked with ISI certificate mark, as applicable. Safe pulling force : 30 N/mm2 (for conductor) 8.0 Tests to be performed as per IS:7098 (part II) Tenderer shall have to submit type test report (tested at CPRI Bangalore/Bhupal) along with the Bid. Bidder will be disqualified for non-submission of type test reports. 8.1 Type test all the test mentioned below are to be made as per details given in IS:10810 a) Test on conductor i. Tensile test (For aluminum) ii. Wrapping test for aluminum iii. Resistance test. b) Test for armuoring wire strips. c) Test for thickness of insulation and sheath. d) Physical test for insulation. i. Tensile strength and elongation at break ii. Ageing in air oven. iii. Hot test iv. Shrinkage test. v. Water absorption (Gravimetric) e) Physical tests for outer sheath i. Tensile strength and elongation at break ii. Ageing in air oven. iii. Shrinkage test. iv. Hot deformation v. Heat shock vi. Loss of mass in air oven vii. Thermal stability viii. Thermal Stability f) g) h) Partial discharge test Bending test Dielectric power factor test i. As a function voltage ii. As a function of temperature i) Insulation resistance (volume resistivity) test j) Heating cycle test k) Impulse with stand test l) High voltage test m) Flammability test Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 211 Technical Specification 8.2 The following test on screen cable shall be performed successfully on the same test sample of completed cable, not less than 10 m. in length between the test accessories. a) PD test b) Bending test followed by PD test c) Di-electric power factor as function of voltage d) Di-electric power factor as a function of temperature e) Heating cycle test followed by Di-electric power factor as a function of voltage and PD test. f) Impulse with stand test and g) High voltage test as per para 30 of special technical parameters If a sample fails in test (g) one more sample shall be taken for this test, preceded by test (b) and (e) 8.3 Acceptance test : the following shall constitute acceptance test: a) Tensile test (For aluminum) b) Wrapping test for aluminum c) Conductor resistance test d) Test for thickness of insulation and sheath e) Hot set test for insulation f) Tensile strength and elongation at break test for insulation and outer sheath g) PD test (Screen enables) only on full drum length h) High voltage test, and i) Insulation resistance ( volume resistivity) test J) Spark test on extruded un-insulated outer PVC sheath as per provision clause no 3.2 IEC standard (Publication no.229 of 1982) 8.4 Routine test: The routine test shall be carried out on all cables manufacturer in accordance with this specification. The following routine test shall be made on cable length as specified in ISS. a) Conductor resistance test b) Partial discharge test on full drum length c) High voltage test as per clause 29 of special technical parameters 8.5 Test witness a) All tests shall be performed in presence of purchaser representatives if so desired by the purchaser. b) The contractor shall give at least 15 days advance notice for witnessing such tests. 9.0 Test Certificate 9.1 9.2 Certified copies of all routine test carried out at work shall be furnished in 6 copies for approval of the Purchaser. The cable shall be dispatched from works only after receipt of Purchaser‘s written approval of shop test report. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 212 Technical Specification 9.3 10.0 Type test certificates of the cable offered shall be furnished. Otherwise the cable shall have to be type tested on similar rating as per clause 10 free of any charges to prove the design. Descriptive literatures test results etc. The following details for the cable shall be submitted with bid a) Manufacturers catalogue giving cable construction details and characteristics b) Manufacturing process in details for cables highlighting the steps of control i. Contamination ii. Formation of water trees iii. Effects of by products of cross linking iv. Stress control etc. c) Cross section drawing of the cable d) Cable current ratings for different types of installation inclusive of derating factors due to ambient temperature, grouping etc. e) Over-load characteristics of the cable without endangering the normal life and electrical quality of the insulation. f) Complete technical date of the cables. g) Type test certificate from government testing units/government authorized testing units. with the quality assurance plan submitted by the firm, the offer shall be liable for rejection. 11.0 Guarantee: The guarantee period should either be 60 (Sixty) month from the date of commissioning or 68 (Sixty eight) month from the date of material received at site. The tenderer shall have to replace the damage cable (electrical damage/physical deformation) within 30 days from reporting. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 213 Technical Specification 3.28 TECHNICAL SPECIFICATION FOR CABLE END TERMINAL KIT (OUTDOOR AND INDOOR) Heat shrinkable termination Kit for 6.35/11kV XLPE ,Cable ( 1-core,300 sq mm & 185 sqmm, 3-core -120 sqmm ) both for outdoor and indoor should be as per IS : 13753 and relevant international standard. The terminal cable kit should be for the following technical parameter of cable. SPECIFIC TECHNICAL REQUIREMENTS:Technical parameters of the cable shall be as follows: Sl No Particulars Unit 1 Rated voltage of cable KV 6.35/11kV 2 Type of insulation XLPE 3 Core Single , 4 Armoured /Unarmoured Armoured 5 Material of Conductor Aluminium 6 System Voltage 11 KV Earthed 7 Highest System Voltage KV 12 8 Conductor Size Sq. mm 300 Sq mm , 1- core 185 Sq mm , 1- core And 120 sqmm,3-core 9 Material Stranded Aluminium ELECTRICAL PERFORMANCE FOR TERMINAL KIT AC Dry withstand voltage 35 KV / 1 minute DC withstand voltage for 30 minute 48 KV Lighting impulse withstand voltage 75 KV Partial Discharge 12.7 KV < 5 pc Standard tail length for outdoor 600 mm Standard tail length for indoor 450 mm KIT COMPONENT Terminal Lug Heat Shrinkable Adhesive Lined Terminal Sleeve Lug Sealing Tape / Mastic Rain Shed for 12 KV System Anti Tracking Sleeve Stress Control Sleeve Stress Control Mastic Constant Force Spring Roll Copper Braid for Screen Earthing Worm Drive Clip Adhesive Line Gland Sleeve Tinned Copper Braid duly fitted with Terminal Lug at one end + Solder Bock Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 1 No 1 No 1 Strip 2 Nos. 1 No. 1 No 1 Strip 1 No 1 No 1 No 1 No 1 No Assam Power Distribution Company Ltd 214 Technical Specification 3.29 TECHNICAL SPECIFICATION OF CONTROL CABLES 1.0 SCOPE: 1.1 Specification calls for design, manufacture, stage testing, inspection and testing beforedispatch, packing and delivery of Copper control cables and Aluminum power cables for 33/11KV substations. 1.2 The control and power cables shall be ISI marked, 1.1 KV Grade. The cores shall have a size of 2.5 sq.mm for control cables and 4 sq. mm. power cable, using solid/stranded Copper conductor with different number of cores as specified below:1.3 COPPER CONTROL CABLES Unarmoured i) 12 Core 2.5 sq.mm, solid conductor ii) 7 Core 2.5 sq.mm., solid conductor. iii) 4 Core 2.5 sq.mm., solid conductor iv) 2 Core 2.5 sq.mm., solid conductor 2.0 STANDARDS: 2.1 The control and power cables shall conform to the latest applicable Indian Standards. In case bidders offer control and power cables conforming to any other International Standards which shall be equivalent or better than IS, the same is acceptable. Cables for which Indian Standards arenot available, the relevant equivalent International Standards will be applicable. Please attach photocopy of all such standards according to which the cables have been offered i) IS: 1554: PVC insulated (Heavy Duty) Control Cables for working voltage & including 1100 Volts. ii) IS: 3961: Recommended current ratings for PVC insulated and PVC sheathed heavy duty cables iii) IS: 4905: Methods of random sampling iv) IS: 5831: PVC insulation and sheath of electric cables v) IS: 8130: Conductors for insulated electric cables and flexible cords vi) IS: 10418: Wooden drums of electric cables vii) IS: 10810: Methods of tests for cables 3.0 GENERAL TECHNICAL REQUIREMENTS AND CONSTRUCTIONAL DETAILS: 3.1 Cables shall be suitable for laying on racks, in ducts, trenches, conduits and underground buried installation with chances of flooding by water. Cables shall be designed to withstand mechanical, electrical and thermal stresses developed under steady-state and transient operating conditions as specified elsewhere in this specification. 3.2 CONTROL CABLES Control cables shall be of 1.1 KV grade, multicore (as specified in Clause 1.3 above), PVC Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 215 Technical Specification insulated, PVC inner sheathed, un armoured, PVC outer sheathed with solid copper conductor conforming to latest version of IS: 1554 or equivalent International Standards. 3.3 3.4 The conductor shall be made from high conductivity copper rods complying with latest version of IS:613 or equivalent International Standards. The conductor shall consist of annealed copper wires complying with IS: 8130 with latest amendments or equivalent International Standards. POWER CABLES: Power cable shall be of 1.1 KV grade, multicore (as specified in Clause 1.3 above), PVC insulated, PVC inner sheathed, PVC outer sheathed with stranded conductor. 3.5 INSULATION: Conductor shall be provided with PVC insulation applied by extrusion in accordance with latest version of IS: 5831 or equivalent International Standards. The average thickness of insulation shall be in accordance with the IS: 1554 (Part-I) with latest amendments or equivalent International Standards. Insulation shall be so applied that it fits closely on the conductor and shall be possible to remove it without damages to the conductor. 3.6 CODE IDENTIFICATION: Colouring of insulation shall identify cores of the cables of upto 5 cores. Following colour schemes shall be adopted:SN 1 2 3 3.7 No of Cores 2 core 4 core 7 core Colour Scheme Red and Black Red, Yellow, Black, Blue and Grey a) Two adjacent cores (counting and direction core) in each layer, Blue and Yellow, remaining cores Grey or in accordance with the scheme given in IS 1554 b). Cables having more than 5 cores, as an alternate to the provision of (a) above, core identification may be done by numbers as indicated in latest version of IS: 1554 (PART-I) 10 core identification. LAYING UP OF CORES: In multi-core cables, the cores shall be laid up together with a suitable lay, the outer most layer shall have right-hand lay and successive layer shall be laid with opposite lay, where necessary, the interstices shall be filled with non hygroscopic materials. 3.8 INNER SHEATH: The laid up cores shall be provided with inner sheath applied by extrusion. It shall be ensured that the shape be as circular as possible. The inner sheath Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 216 Technical Specification shall be so applied that it fits closely on the laid up cores and it shall be possible to remove it without damage to the insulation. Thickness of inner sheath shall be conforming to latest version of IS: 1554 (Part-I) or equivalent International Standards. 3.9 FILLER AND INNER SHEATH: Filler and inner sheath shall be of the following: Unvulcanised rubber or thermoplastic material used shall not be harder than PVC used for insulation and outer sheath. Material shall be chosen to be compatible with temperature ratings of the cable and shall have no deterious effect on any other component of the cable. 3.10 OUTER SHEATH: inner sheath in case of unarmoured multicore cables Outer sheath shall be so applied that it fits closely over insulation / inner sheath / armouring. It shall be possible to remove it without damage to the insulation / inner sheath. The colour of the outer sheath shall be black.Thickness of outer sheath insulation shall conform to latest version of IS: 1554 Part-I or equivalent international standards. 4.0 IDENTIFICATION: 4.1 In addition to manufacurer‘s identification on cable as per clause-17.1 of IS: 1554 (Part-I) with latest amendments, following marking shall also be embossed over outer sheath at every three meters:- The embossing shall be in line throughout the length of the cable and shall be legible and indelible. 5.0 PACKING AND MARKING: 5.1 Cables shall be supplied in non-returnable drums. The surface of the drum and outer most cable layer shall be covered with waterproof layer. Both the ends of the cables shall be properly sealed with heat shrinkable PVC or rubber caps, secured by ‗U‘ nails so as to elliminate ingress of water during transportation storage and erection. Following information should be stenciled on the drum: -sectional area of the conductor ble on the drum Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 217 Technical Specification 5.2 6.0 As mentioned, the cable drum must bear relevant Indian/International Standard certification Mark. In this connection, a certified photostat copy of valid standard marking license rights duly attested must be submitted along with the inspection offer as documentary evidence. In absence of these documents, the inspection offer will not be considered. STANDARD DRUM LENGTH: 6.1 Standard drum length for cable shall be 500/250 metres. 6.2 TOLERANCE: Tolerance on the overall diameter of the Cable shall be ± 2 mm over the declared value in the techanical data sheets of Guaranteed Technical Particulars. Length per drum shall be subjected to maximum tolerance of ± 5% of the standard drum length. The Employer shall have option to reject cable drums with shorter length. Over all tolerance in total quantity for each type and size of cables shall be ± 2%. 7.0 TESTS: 7.1 All types and sizes of cable being supplied shall be subjected to Type tests, Additional test, Routine tests and Acceptance tests as specified below at the expense of manufacturer and according to relevant standards. 7.2 TYPE TESTS AND ADDITIONAL TESTS: It is essential to furnish all the type test reports for each type and size of cable as stipulated in latest version of IS: 1554 (Part-I) and following Additional Tests: l stability test Above tests shall be conducted in NABL approved Testing laboratories only. 7.3 ACCEPTANCE TEST Acceptance test shall be caried out on each type and size of cables on cable drums selected at random as per following plan :. Numbers of Drums in the Number of Drums to be S.No Tests taken as samples 1 2 3 4 5 Upto 50 51 to 100 From 101 to 300 From 301 to 500 From above 501 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 2 5 13 20 32 Assam Power Distribution Company Ltd 218 Technical Specification 7.4 The following shall constitute acceptance tests :- ageing at break of insulation and sheath rsion Test) 7.5 ROUTINE TESTS: Routine test shall be carried out for each drum of cables of all types and sizes. Following shall constitute routine tests : st at Room Temperature 7.6 i. ii. iii. iv. While preparing cable schedules for control/protection purpose following shall be ensured: Separate cables shall be used for AC & DC. For different cores of CT & PT/CVT separate cable shall be used At least one (1) cores shall be kept as spare in each copper control cable of 4C, 5C or 7C size whereas minimum no. of spare cores shall be two (2) for control cables of 10 core or higher size. For control cabling, including CT/PT circuits, 4.0 sq.mm. size copper cables shall be used per connection Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 219 Technical Specification 3.30 SPECIFICATION FOR 1.1 kV GRADE SINGLE CORE UNARMOURED L.T. XLPE CABLE 1.0 SCOPE: This specification covers design, engineering, manufacture, stage testing, inspection and testing before supply and delivery at site of 1.1 kV grade single core 16/25/50/95/120/185/240/300 Sq. mm. XLPE Cables for use with effectively earthed distribution system. 1.1. 1.2. 1.3. It is not the intent to specify completely herein all the details of the design and construction of material. However the material shall confirm in all respects to high standards of engineering, design and workmanship and shall be capable of performing in continuous commercial operation in a manner acceptable to the purchaser, who will interpret the meanings of drawings and specification and shall have the power to reject any work or material which, in his judgment is not in accordance therewith. The offered material shall be complete with all components necessary for their effective and trouble free operation. Such, components shall be deemed to be within the scope of Bidder‘s supply irrespective of whether those are specifically brought out in this specification and/or the commercial order or not. Normally the offer should be as per Technical Specification without any deviation. But any deviation felt necessary to improve performance, efficiency and utility of equipment must be mentioned in the ―Deviation Schedule‖ with reasons duly supported by documentary evidences and advantages of such deviation. Such deviation suggested may or may not be accepted. But deviation not mentioned in ―Deviation Schedule‖ will not be considered afterwards. Location The cables may be laid buried directly in ground at a depth of one metre in average, anywhere in Assam and terminate for outdoor connection to a distribution transformer or to overhead LT lines and also indoor connection for indoor switchgear 2.0 STANDARDS: 2.1 The materials shall conform in all respects to the relevant Indian Standard Specifications with latest amendments thereto. Title Indian Standard No. IS-7098 PartI/1988 Specification for Cross Linked Polyethylene Insulated PVC Sheathed Cables for working Voltages Up to and including 1100V Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Internationally Recognized standard IEC 502 (1983) Assam Power Distribution Company Ltd 220 Technical Specification IS-5831/1984 IS-8130/1984 IS 3975/1979 IS-10418/1982 3.0. IEC 502 (1983) IEC 228 (1978) Material conforming to other internationally accepted standards, which ensure equal or higher quality than the standards mentioned above, would also be acceptable. In case the Bidders who wish to offer material conforming to the other standards, salient points of difference between the standards adopted and the specific standards shall be clearly brought out in relevant schedule. Four copies of such standards with authentic English Translations shall be furnished along with the offer. . In case of conflict the order of precedence shall be (i) IS, (ii) IEC, (iii) Other standards. In case of any difference between provisions of these standards and provisions of this specification, the provisions contained in this specification shall prevail. Moderately hot and humid tropical climate, conducive to rust and fungus growth. SYSTEM DETAILS : The material shall conform to the following parameters: Sl. No. 1. 2. 3. 4. 5. 4.0 4.1 PVC insulation and sheath of electric cables Conductors for insulated electric cables and Flexible cords Specification for armouring Specification for cable drum Item Type of Installation System Voltage System Frequency No. of Phases System of earthing Specification Outdoor 433 V (+10% -15%) 50 Hz +/- 5% Three Solidly grounded TECHNICAL REQUIREMENTS: MAIN FEATURES: The power cables shall be of LT 1.1 kV Grade, stranded compacted, high conductivity, aluminum conductor, XLPE insulated, ST-1 type extruded PVC outer sheathed, conforming to relevant standards suitable for LT AC three phase, 50 c/s, effectively earthed distribution system. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 221 Technical Specification 4.2 MATERIALS AND CONSTRUCTION: 4.2.0 SPECIFIC TECHNICAL REQUIREMENTS Technical parameters of the cable shall be as follows Sl No Cable Size (Sq.m m) Al. Stra nd Min. Min. Min thickne thickne ss of Overall ss of Outer dia XLPE sheath (mm) (mm) (mm) Max. Max. A.C D.C Resis Resist tance ance at at 200C 700C (Ohm/ (Ohm Km) /Km) Min. current carrying capacity at 300C (Amps) Gro und Air Short Ckt curren t/sec (KA/1s ec) Min. weigh t. Kg/K m 1 25 7 0.9 1.8 11.0 1.200 1.540 96 98 2.4 169 2 120 19 1.2 1.8 19.0 0.253 0.325 225 268 11.3 538 3 240 Bc,x 4.2.1 CONDUCTOR: The cable conductor shall be made from stranded aluminum to form compacted shaped conductor having resistance within the limits specified in IS-8130/1984 4.2.2 INSULATION: The XLPE insulation shall be suitable for the specified system voltage. The manufacturing process shall ensure that the insulation is free from voids. The insulation shall withstand mechanical and thermal stresses under steady state as well as transient operating conditions. The extrusion method shall give smooth surface of insulation. The insulation shall be so applied that it fits closely on the conductor and it shall be easily possible to remove it without damaging the conductor. 4.2.3 OUTER SHEATH: Extruded PVC outer sheath of black colour shall he applied with suitable additives to prevent attack by rodents and termites. Outer sheathing shall be designed to offer high degree of mechanical protection and shall also be heat, oil, chemical, abrasion and weather resistant. Common acids, alkalies, saline solutions etc., shall not have adverse effects on the PVC sheathing material used. 4.2.4 CONSTRUCTION: 1) All materials used in the manufacture of cable shall be new, unused and of finest quality. All materials shall comply with the applicable provisions of the tests of the relevant Standards. 2) The PVC material used in the manufacture of cable shall be of reputed make.No recycling of the PVC is permissible. The purchaser reserves the right to ask for documentary proof of the purchase of Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 222 Technical Specification various materials to be used for the manufacture of cable and to check that the conductor is complying with quality control. 4) Cables shall have suitable fillers laid up with the conductors to provide a substantially circular cores section before the sheath is applied. Fillers shall be suitable for the operating temperature of the insulation & compatible with the insulation material 4.2.5 CURRENT RATING: The cables shall have current ratings and derating factors as per relevant Indian Standards. The current ratings shall be based on maximum conductor temperature of 90 deg. C with ambient site condition specified for continuous operating at the rated current. 4.2.6 OPERATION: Cables shall be capable of satisfactory operation, under a power supply system frequency variation of +/- 5 c/s, voltage variation of +10% or-15%. Cables shall have heat and moisture resistance properties; these shall be of type and design with proven record on Distribution Network service. 4.2.7 LENGTH: The cable shall be supplied in wooden drums and the standard drum length shall be as follows1x25 mm2 1000 meters +/- 5% 1x120 mm2 500 meters +/- 5% 1x240 Substandard drum length of not less than 100 meters upto a maximum of 5% of the quantities ordered shall be accepted. However substandard drum length upto a maximum of 5% shall be acceptable only in a particular lot offered for inspection 4.2.8 IDENTIFICATION: For identification of individual cores, coloured strips of red, yellow and blue colours respectively shall be used on the cores to identify phase conductors as per relevant ISS. 4.2.7 EMBOSSING: The cable shall be embossed through out the length with the name of the manufacturer and the letters "Property of APDCL., Specification No., voltage grade with cable size and the year of manufacture". The embossing shall be done only on the outer sheath, the distance between any two consecutive embossings shall not be more than 2 Meter. The cable shall also be embossed (clearly visible) for the verification of its length at intervals of 1 Meter say 1,2,3 up to full length. 4.2.8 GUARANTEED TECHNICAL PARTICULARS: The guaranteed technical particulars as detailed in the specification annexure-I shall be guaranteed and a statement of guaranteed technical particulars shall be furnished in the format along with the bid without which the Bid shall be treated as Non -Responsive. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 223 Technical Specification Immediately after completion of the electrical tests (during routine/acceptance tests), the ends of the cable shall be enclosed by rubber/PVC caps of wall thickness not less than 2.5 mm and then sealed by non hygroscopic material (the cores being suitably insulated from the cap). The cap shall be of robust construction and tight fit, and it shall have the trademark of the manufacturer embossed thereon 5.0. 5.1 TESTS: Type Test: The material offered shall be fully type tested at independent test laboratories by the Bidder as per the relevant standards but test reports shall not be more than five years old from the date of opening of bid. The bidder shall furnish complete set of following type test reports along with the bid. The bids received without these type test reports shall be treated as Non-responsive. 1. 2. 3. 4. 5. 6. Tests on conductors Test for thickness of insulation and sheath Physical tests for insulation Physical tests for outer sheath Insulation resistance test High voltage test 5.2. Acceptance and Routine test: All acceptance and routine tests as stipulated in the relevant standards shall be carried out by the supplier in presence of purchaser's representative. 6.0 INSPECTION: 6.1 The inspection shall be carried out by the purchaser‟s representative during manufacture and before dispatch. The supplier shall keep the purchaser informed in advance, about the manufacturing programme so that arrangement can be made for inspection. The manufacturer shall grant free access to the purchaser‘s representative, at a reasonable time, when the work is in progress. Inspection and acceptance of any equipment under this specification by the purchaser, shall not relieve the supplier of his obligation of furnishing the equipment in accordance with the specification and shall not prevent subsequent rejection if the equipment is found to be defective. 6.2 All Acceptance tests and inspection shall be made at the place of manufacturer unless otherwise especially agreed upon by the Bidder and purchaser at the time of purchase. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 224 Technical Specification The purchaser reserves the right to insist for witnessing the acceptance/ routine testing of the bought out items. The supplier shall give 15 days (for local supply)/ 30 days (incase of foreign supply) advance intimation to enable the purchaser to depute his representative for witnessing the acceptance and routine tests. Material shall be dispatched only after getting the dispatch authorization from Inspectors representing purchaser, after successful testing. 6.3 If successful type tests have been carried out on the offered design during last five years (counted from the date of tender opening), repetition of type tests is not required. On the other hand, if the offered design is not type tested during last five years, the cable shall be subjected to all type test in accordance with IS: 1554 (Part-I)/1988 and amendment thereof at recognized test house of repute. All charges/fee/transportation etc. to conduct these tests shall be borne by Contractor. Regular supply of the material shall commence only after successful type testing and dispatch authorization from the competent authority. However, the purchaser reserves the right to get cable type tested at any stage during the currency of contract at his own expenses in any reputed test house. The transportation and arrangement of testing of sample to test laboratory shall be the responsibility of the contractor. 6.4 Routine tests report shall be sent by the manufacturers with their offer for inspection, the following acceptance tests as laid down in the referred ISS (with latest amendments) shall be carried out by the inspecting officer of the APDCL on Samples selected at random as per Appendix `A ‗ in IS-1554 (Part-I) 1988. 1. Tests on conductor a) Tensile test b) Conductor resistance test 2. Test on armoring strips: a) Measurement of dimension b) Tensile test c) Elongation test & winding test d) Zinc coating 3. Test for thickness of insulation and sheath 4. Tensile strength and elongation at break of insulation and sheath 5. Insulation Resistance Test 6. High voltage test at room temperature 1988 Reference to I.S.S. IS: 8130-1984 IS: 8130-1984 IS: 3975 – 1979 IS: 3975 – 1979 IS: 3975 – 1979 IS: 2633 – 1984 IS: 5831 – 1984 IS:5831 – 1984 IS: 5831 – 1984 IS: 1554 (Part-I) – In addition to above, length/weight check and bending test on one drum per inspection shall also be carried out by the inspecting officers for which contractor will make all necessary arrangements and provide all necessary facilities at his own cost. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 225 Technical Specification 7.0 CALBE DRUMS: The cables shall be supplied in non-returnable substantially lagged wooden drums of heavy construction suitable for transportation by goods train or truck and for storage at site. The wood used for construction of the drum shall be properly seasoned and sound and wood preservative shall be applied to the entire drum. All ferrous parts shall be treated with a suitable rust preventive finish or coating to avoid rusting during transit or storage. The drum shall also conform to specn. No. IS: 10418-1982 with latest amendment thereof. Each drum shall have the following information marked on it with indelible ink alongwith other important information including technical data: 1. 2. 3. 4. 5. 6. 7. 8. 9. Property of APDCL & Specification No. – Designation of consignee & destination railway station. Drum Number. Aluminium Core Cable. Cable rating eg. Voltage grade, No. of cores, sizes etc. Height of empty drum. Length of Cable. Gross weight of drum with cable. Year of manufacture. 8.0 PACKING AND TRANSPORT: All the material covered under this specification shall be adequately packed for transportation by Rail/Road. A layer of waterproof paper shall be applied to the surface of the drums and over the outer cable layer. A clear space of atleast 40 mm shall be left between the cable and the laggings. The packing shall be adequate to protect the cable from damage, in transit and contractor shall be responsible for it and make good at his own expense any and all damages due to improper packing etc. 9.0 VARIATION OF QUANTITY: The supplied quantity can vary within Plus/Minus 1% of the ordered quantity. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 226 Technical specification 3.31 TECHNICAL SPECIFICATION FOR STAY SET (HT ) 1.0 Scope: 1.1. This specification covers the design, manufacture testing at manufacturer's works, transport to site, insurance, storage, erection and commissioning of the Stay Sets (HT) required from the distribution lines at designated locations. 2.0 Standard: 2.1. All the materials of stay sets shall comply in all respects with the requirements of the latest edition of the relevant Indian or British Standard specification except in so far as they are modified this specification. 3.0 Design Consideration: 3.1. Stay Rods shall be Galvanised and shall be of circular Cross-section with bow, thimble, nuts and bolts. The Rods shall be threaded at one end up to a minimum of 30 cm length and shall be complete with Galvanised M.S. Anchor Plates with all necessary accessories. All parts shall be heavily galvanised. 4.0 Testing: 4.1. Type and Routine Tests should be carried on different components of each stay sets as per relevant Indian Standard specification and certified copies of the above should be submitted along with the tender. 5.0 Schedule Requirement: Stay sets complete with Thimble bow stay Rod/Anchor plate with nuts etc. and made of Rolled mild Steel Rod and plates as per detailed given below: 5.1. Anchor Plate: I) II) III) IV) V) Thickness not below 5 mm. Size not below 300 mmX300 mm with smooth edges (for HT) Well galvanised Materials M.S. Rolled plate About 20 mm square hole at centre for locking the plate with the Anchor Rod (for HT) 5.2. Anchor Rod: VI) Length 1800 mm or above VII) Threaded length 30 cm or above VIII) Diameter 18 mm or above (for HT) IX) Anchor plate and head: square size 30mm X 30mm with thickness 25 mm having matching square size shank for locking the Anchor plate. X) One ratched lock nuts, grooves must match the grooves at bow flange XI) One check nut. XII) Materials H.S. XIII) Component well galvanised with extra care for the threaded portion. XIV) Both lock and check nuts should be matching to the Anchor Rod thread such that punching of thread after assembly at site safeguards them against removal. 5.3. Thimble: The match bow diameter and bend should be well galvanised. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 227 Technical specification 5.4. Bow: Rod diameter 12mm/16mm or above overall length 35cm/40cm or above. Flange with well formed locking grooves matching the locking nut, bow ends will be riveted securely with the flange. All items to be galvanised. 6.0 Inspection: 6.1. All tests and inspections shall be carried out at the place of manufacturer unless otherwise agreed by the purchaser and the manufacturers at the time of purchase. A manufacturer shall afford the inspector representing the purchaser or third party nominee, all reasonable facilities, without charge to satisfy that the materials are being purchased as per specification. The purchaser reserves the right to have the test carried out at his cost by an independent agency, whenever there is dispute regarding the quality of the materials supplied. 7.0 Marking 7.1. The equipments shall be marked with name of manufacturer, year and name of project. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 228 Technical specification 3.32 TECHNICAL SPECIFICATION FOR G.I. STAY WIRE 1.0 Scope The specification covers design, manufacturing and testing, transporting to site, insurance, storage, erection and commissioning of G.I. Stay Wire 7/10SWG and 7/14SWG. 2.0 Materials. The wire shall be manufactured from steel, made by any suitable process and shall not contain sulphur and phosphorus exceeding 0.065 percent each. The wires shall be coated with Zinc Grade Zn 98 of IS:209-1966 The general requirements for the supply of Galvanized stay strand shall be in accordance with IS:1387-1967 3.0 3.1 Construction Grades: The wire shall be of Grade-I and tensile strength range 45 up to and including Kg/mm The Galvanized stay strand shall be of 7/2 mm and 7/3.15 mm. the lay of the strands shall be of the length of 7/2 mm and Tables-I of IS: 2141-1963. the wires shall be so stranded together that when and evenly distributed pull is applied at the end of the completed strand each wire will take equal share of the pull. The length of the strand which may be supplied without joints in the individual wires comprising it, depend on the length of wire which may be carried by the bobbin in a normal stranding machine. The normal lengths of strand which shall be supplied without joints in the individual wires, excluding welds made in the rod before drawing shall be as given below. The lengths may be exceeded by agreement between the manufacturer and the purchaser. Diameter of wire in strand Normal length without joints of weld 3.15 mm 1000 M 2.0 mm 3000 M In cases where joints are permitted, they shall be made by welding of brazing joints in the same wire shall be separated by a length of not less than that shown in 3.3 and joints in different wires in a strand shall not be less than 20 M apart. 3.2 3.3 3.4 4.0 4.1 Freedom from Defects : Each coil shall be warranted to contain no weld joint or splice other than in the rod before it is drawn and those permitted in 3.4. The wire shall be circular and shall be free scale, irregularities imperfections flaws splits and other defects. The Zinc coating shall be smooth, even the bright. 5.0 5.1 Tests: Chemical Analysis: Unless otherwise agreed to between the purchaser and the supplier, the chemical analysis be carried out. 5.2 Tensile Test: The wire when tested in accordance with IS: 1521-1960, on gauge length of 100 mm shall have the minimum tensile strength specified in Tables 1 of IS : 2141/1968 according to the grade of the wire. 5.2.1 The tensile strength of the finalised strand shall be not less tI~an 93 percent of the aggregate of the single wires. 5.3 Delivery test: The wire shall be subjected to the wrapping test in accordance with IS : 1755/1961. When wrapped eight times round its own diameter and on being subsequently strengthened the wire shall not break or split. 5.3.1 Coating test: The uniformity of Zinc coating shall be tested by the method specified in IS : 2633/1964. The wire shall withstand the number or dips as specified in IS : 4826-1968. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 229 Technical specification 6.0 6.1 6.2 7.0 Marking: Each coil shall be provided with a label, fixed firmly on the inneJ part of the coil, bearing 'the following information. a. Manufacturer's name or trade mark b. Lot number and coil number c. A brief description and quality of the materials. d. Weight and e. Any other particulars specified by the purchaser f. Name of the project TDF. The label may also be marked with the ISI certification mark. Inspection: The test should be carried out in presence of the inspecting officer deputed by purchaser or third party nominee and the test should be in conformity with relevant IS. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 230 Technical specification 3.33 TECHNICAL SPECIFICATION OF HT GUY INSULATOR 1.0 Scope This specification covers design, manufacture, testing, transport to site, insurance, storage, erection and commissioning of the strain type porcelain Guy Insulator used in distribution overhead power lines. 5.0 Standard This insulators shall comply with Indian Standard specification IS: 5500/1969 and as amended from time to time except where they conflict with the requirements in this specification. Offers conforming to any other internationally accepted standard which ensure equal or higher quality than the standard mentioned will be acceptable. 6.0 General Requirements This porcelain shall be sound, free from defects, thoroughly vitrified and smooth glazed. The design of the insulator shall be such that stresses to expansion and contraction at any part of the insulator shall not load to its deterioration. The glaze, unless otherwise specified, shall be brown in colour. The glaze shall cover the entire porcelain surface parts except those areas that serves as supports during firing or area otherwise required to be left unglazed. 7.0 Insulator Characteristics The Guy Strain Insulators shall have the electrical and mechanical characteristics as shown below: H.T. Strain Type Porcelain Guy Insulator 1) Length 140 mm 2) Diameter 85 mm 3) Cable hole dia 25 mm + 1.5 4) Minimum failing load 88 KN 5) Creepage distance 48 mm 6) Dry one minute power frequency withstand 27 KV (rms) voltage 7) Wet one minute power frequency withstand 13 KV (rms) voltage 8.0 Test All insulators shall comply the following test as per IS : 5300 A) Routine test: The following shall be carried out as., routine test. a) Visual Examination Every insulators shall be visually examined. The insulators shall be free from physical distortion of shape and defects, and thoroughly verified and smoothly glazed. They should be free from cracks or any other defects likely to be prejudicial to the satisfactory performance in service. b) Type test: The following shall constitute the type test and those shall be conducted in the order given below: i. Visual examination ii. Verification of dimensions iii. Temperature cycle test iv. Dry one minute power frequency voltage withstand test Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 231 Technical specification v. Wet one minute power frequency voltage withstand test vi. Mechanical strength test vii. Porosity test. The number of samples for type test are to be agreed to between the purchaser and the supplier. c) Acceptance Test (to be conducted in the following order) i. Verification of Dimensions ii. Temperature cycle test iii. Mechanical strength test iv. Porosity test The number of samples for acceptance test shall be in accordance to IS: 5300. d) Type test certificate from National Test House/ Govt. recognized institutions/ Govt. recognized public Testing Laboratories are also to be submitted along with the offer, failing which the offer is liable for rejection. 9.0 Marking Each insulator shall be legibly and indelibly marked to shown the following: a.Name of trade mark of the manufacturer b.Year of manufacture and name of project TDF 2010-11 Marking on porcelain shall be printed and shall be applied before firing. Insulators may also be marked with the ISI certification mark. 10.0 Inspection All tests and inspections shall be carried out at the place of manufacturer unless otherwise agreed by the purchaser and the manufacturer at the time of purchase. The manufacturer shall afford the inspector representing the purchaser or the third party nominee, all reasonable facilities, without charge, to satisfy that materials are being furnished in accordance with the specification. The purchaser reserves the right to have the test carried out at his own cost by an independent agency whenever there is dispute regarding the quality of materials supplied. 11.0 Drawing Drawing specifically showing all dimensions is to be submitted along with technical bid. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 232 Technical specification 3.34 TECHNICAL SPECIFICATION FOR G.I. WIRE 1.0 2.0 3.0 4.0 4.1 4.2 5.0 Scope This specification covers the manufacturing, testing at works, transport to site, insurance, storage, erection and commissioning of Galvanised Iron Wire of sizes 4 mm and 5 mm diameter. General requirements It relating to the supply of mild steel wire shall be as per IS: 1387/1967 and the wire shall be drawn from the wire rods conforming to IS: 7887/1975. The requirements for chemical composition for the wires shall conform to IS:7887/1975. Mild steel wire for General Engineering purpose shall be of following sizes: I) 4mm - diameter (8 SWG) II) 5mm - diameter (6 SWG) Tolerance permitted on the diameter of wire shall be as per Table -1 of IS:280/1978. Climatic Conditions The cross arms should be suitable for the climatic condition mentioned In these bidding documents: Mechanical Properties Tensile Test: Tensile strength of wire when tested in accordance with IS: 1521-1972, shall be within the limits given in Table-2 of IS: 280/1978. Wrapping Test: Wires shall be subjected wrapping test in accordance with IS: 17551961. The wire shall withstand without breaking or splitting. being wrapped eight times round its own diameter and subsequently straightened. Surface finish a. The wire shall have galvanized finishes. The galvanized coating of steel wire shall conform to the requirements for anyone of the types of coatings given in IS: 4826-1968 as per agreement with the purchaser. b. The coating test for finishes other than galvanized, copper coated or tinned shall be subject to between the purchaser and the manufacturer. c. Unless otherwise agreed to the method of drawing representative samples of the material and the criteria for conforming shall be as prescribed in Appendix (A) of IS: 280/1978. d. All finished wires shall be well and cleanly drawn to the dimensions specified. The wire shall be sound, free from splits, surface flaws, rough jagged and imperfect edges and other harmful surface defects. e. Each coil of wire shall be suitably bound and fastened compactly and shall be protected by suitably wrapped. 6.0 Marking Each coil of wire shall be marked legibly with the finish size of wire, lot number and trade mark of the name of the manufacturer. The material may also be marked with the ISI certification mark and name of the project TDF. 7.0 INSPECTION Inspection may be carried out by the purchaser or third party nominee at any stage of manufacture. The supplier shall grant free access to the purchaser's representative or third party nominee at a reasonable time when the work is in progress. Inspection and acceptance of any equipment under this specification by the purchaser shall not relieve the supplier of his obligation of furnishing equipment in accordance with the specification and shall not prevent subsequent rejection if the equipment is found defective. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 233 Technical specification 3.35 TECHNICAL SPECIFICATION AND SCOPE OF WORKS OF Gas filled LT capacitor unit 1.0 SCOPE This specification covers design, manufacturing, testing, insurance, transportation, supply and installation of three phase, delta connected, 50 Hz., outdoor type, self healing, metalised polypropylene design, cylindrical LT shunt capacitor units filled with inert gas, intended for power factor improvement and to be installed on LT side of three phase distribution transformers of various ratings by way of suitable clamp. Gas filled capacitor unit shall be ISI Marked along with IP54 degree protection level. 2.0 STANDARDS Unless otherwise stipulated in the specification the capacitor unit shall generally comply with IS:13340 / 1993 (reaffirmed 1998) for self healing type, IS: 12672 / 1989 for internal fuses and internal over pressure disconnectors for shunt capacitors and 1S: 13341 / 1992 for requirements for ageing test, self healing test and destruction test on shunt capacitors of the self healing type for AC power systems having rated voltage up to and including 650 V (with latest version / amendments). The specification supercedes requirements in IS wherever applicable. 3.0 CLIMATIC CONDITIONS The equipment to be supplied against this specification shall be installed on one of the pole of distribution transformer DP structure and therefore shall suitable for satisfactory continuous operation at site under the following tropical climatic conditions: a) Maximum temperature of air in shade : 55°C b) Minimum temperature of air in shade : (-) 5 °C c) Maximum relative humidity : 95%. d) Minimum relative humidity : 10%. e) Height above main sea level : up to 1000 meters f) Average number of thunder storm : 40 days per annum. f) Dust storms likely to occur : from March to July. h) Average annual rain fall (depending on area) : 10 to 100 cms i) Number of months during which tropical monsoon: 4 Months, June to Sept. Conditions prevail 3.1 SYSTEM DETAILS / PARTICULARS The distribution transformers are connected to the 11 KV network on its HT side while LT side is connected to the 440 Volts LT network i. Nominal voltage : 440 / - 10% Volts ii. Rated Frequency : 50 + /- 3% Hz iii. No. of phases :3 3.2 RATING The stated output of capacitor units in KVAR at frequency of 50 Hz for upper limit of temperature category of 55 deg., shall be as per relevant Annexure of the IS. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 234 Technical specification 3.3 RATED VOLTAGE The rated voltage capacitor units shall be 440 Volts. The fluctuation in supply voltage as specified in IS: 585 /1962 and IS: 12360 / 1985 (with latest amendments) shall not affect normal working of the equipment. 3.4 GENERAL TECHNICAL REQUIREMENT The capacitor element used in unit shall have multilayer metallised polypropylene film (MPP) having low loss dielectric and impregnated with such impregnant, which shall have high dielectric constant, low viscosity and high chemical stability. The impregnant should be inert gas. Concentric winding shall be adopted to form three phases. The PP film should be a product manufacture by a company of international repute and should have such design that higher current carrying capabilities can be acheived. Active binding element shall be properly heated and than vacuum dried prior to encapsulation in gas impregnation. The contact area must be carefully prepared so as to achieve high in rush current and long life. The capacitor unit shall have over pressure disconnector protection. Discharge resistance shall reduce the residual voltage to less than 50 volts within one minute as required by IS: 13340. For easy identification of damaged units with naked eye; Visual Fault Indicator shall be provided. 3.5 CONSTRUCTION The capacitors should have 3 Phase having different KVAR rating, cylindrical unit housed in cylindrical aluminum container. The height and diameter of the capacitor shall be as per relevant standard. At the base of capacitor unit suitable arrangement for earthing preferably in form of M-12 size stud bolt having 16 mm outer (projected) length with toothed washer hexagonal nut & two numbers spring washer shall be provided in such a way that it should also serve facility for clamping capacitor unit on LT Poles. The outgoing terminals of capacitor unit should be covered by a UV resistant cap. The capacitor & unit with the cap should conform to IP:54 degree of protection. 3.6 INSTALLATION LT Capacitors are to be installed on one pole of DTR Double-Pole Structure or on LT Pole through suitable clamping arrangement. Clamp should have enough strength to hold the capacitor for long period. A suitable size of ISI marked with UV protection wire of reputed makes like Phinolex or Anchor, per phase should be used for connecting the capacitors with DTR. 3.7 PERMISSIBLE OVER LOADS For capacitors specified in this specification, the maximum permissible over loads shall not exceed anyone of the limits given in (i) and (ii) below as conforming to IS: 13340 / 1993 (re-affirmed 1998): i) Voltage: The permissible over loads shall not exceed limits set by IS: 13340 for self healing type capacitors. ii) Current: Capacitor units shall be suitable for continuous operation at r.m.s. Line current 1.30 times the current occurs at rated sinusoidal voltage and rated frequency, excluding transients (as per IS: 13340 for self healing type capacitors). iii) Inrush current: should be 200 times I nominal current. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 235 Technical specification 3.8 CAPACITOR LOSS The total capacitor loss excluding discharge resistor and cable should not be more than 0.5 watt / KVAR for self-healing type capacitors using metallised polypropylene. The bidder must state the loss of the capacitors offered. 3.9 CAPACITOR LIFE Life expectancy of capacitors shall not be less than 1,15,000 hours. 3.10 RATING PLATE A rating plate shall be provided on each unit with complete information marked indelibly in accordance with clause 10 ‗Marking‘ of IS: 13340 (with latest amendments). The words ―PROPERTY OF CSPDCL‘ shall he marked conspicuously on each capacitor unit with inedible marking along with details of S.No., P0 No. & Date, Rating etc. 3.11 SAFETY RQUIREMENT i) Capacitor unit shall be provided with directly connected discharge device metal oxide varistors (MOV) or resistors of suitable energy handling capacity and as per IS: 13340 /1993 (with latest amendment) for self-healing type capacitors. It should be ensured that there must be no switch, fuse or any other isolating device between the capacitor unit and the discharge device. ii) The discharge device shall reduce the residual voltage from the crest value of the rated voltage to 50 V or less within one minute after the capacitor is disconnected from the source of supply. iii) Capacitor shall comply with the relevant general safety regulations for power installation as per Indian Electricity Rules 1956. 3.12 MONITORING FACILITY For easy identification of damaged units with naked eye; Visual Fault Indicator shall be provided. 3.13 TESTS 3.13.1 Routine Tests: All individual capacitor units shall be subjected to the routine tests at the manufacturer‘s works (at the cost of manufacturer) for the test specified in clause no. 12.1.1 of IS: 13340/1993. A certificate detailing the results of such tests shall be furnished by the supplier along with inspection call to the purchaser. 3.13.2 Type Test: All the tests indicated at clause no. 12.2.2 of IS: 13340 / 1993 with latest amendment, if any shall constitute the type tests. All the type tests shall be carried out at the Govt. / Govt. laboratories accredited by National Accreditation Board of Testing and Calibration Laboratories (NABL) in accordance with the IS: 13340/ 1993. 3.13.3 IP: 54 Test: Capacitors should be tested for IP54 as per IS 12063- 1987. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 236 Technical specification 3.14.4 Routine / Acceptance Tests: The inspecting officer will carry Out the routine / acceptance tests specified as under as per IS:13340 / 1993 (with latest amendment) for self-healing type capacitors. i. Visual examination. ii. Sealing test. iii. Measurement of capacitance and output. iv. Insulation resistance test between terminals & capacitor container v. Capacitor loss tangent (tan delta) measurement at elevated temperature. vi. AC Voltage test between terminals. vii. AC Voltage test between terminals and containers. viii. Test for efficiency of discharge device. ix. Any other test as per relevant IS. The bidder shall furnish copies of type test reports as per relevant IS for the equipment offered or higher rating along with tender. The offer received without type test reports shall be ignored. The equipment offered shall be fully type tested as per the relevant standards for the entire type test specified in the IS at the Govt. / Govt. approved testing laboratories accredited by NABL. Type test shall not be older than 5 years from date of submission of tender. In respect of successful bidders, the purchaser reserves the right to demand repetition of some or all the type tests in the presence of purchaser‘s representative. 3.15 PACKING AND FORWARDING i. The equipment shall be suitably packed in order to avoid damages / losses or breakage during transit or handling. Each capacitor unit may be suitably packed in the first instance to prevent ingress of dust and moisture and than placed in cushion cartoon of suitable material to prevent damage due to shocks during transit. The lid of cartoon may be suitably sealed. A suitable number of sealed cartoons may be packed in a case of adequate strength with extra cushioning, if considered necessary. The cases may than properly sealed against accidental opening in transit. The packing cases may be marked to indicate the fragile nature of the contents. ii. The following information shall be furnished with the consignment: a. Name of the consignee. b. Details of consignment. c. Destination. d. Total weight of consignment. e. Sign showing upper / lower side of the crates. 1. Sign showing fragility of the material. g. Handling and unpacking instructions. h. Bill of material indicating contents of each package & spare material. iii. The supplier shall be responsible for all the damages / losses due to improper packing. Replacement shall be made free of cost regarding material pointed out defective by the consignees. 3.16 DRAWINGS AND DOCUMENTATION Tender must accompany relevant catalogues and sectional drawing showing necessary details of the equipment offered and installation arrangements along with bill of material. One copy of the dimensional drawing and internal constructional drawing shall be furnished with tender. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 237 Technical specification 3.17 RATINGS OF CAPACITORS TO BE INSTALLED LT Capacitors are to be installed as per details given hereunder:XMER Rating 25 kVA 63 kVA 100 kVA >100 kVA TOTAL No. of XMER 6446 16699 10618 4426 No. of XMER & kVAR rating for Rural area 6446 (5 kVAR) 15029 (12 kVAR) 8494 (20 kVAR) 0 No. of XMER & kVAR rating for Urban area 0 1670 (5 kVAR) 2124 (10 kVAR) 4426 (20 kVAR) 38189 Thus, number of capacitor rating-wise are to be installed as per details given below:S N 1 2 3 Particulars 5 kVAR No. of XMER in rural 6446 area, where capacitors are to be installed. No. of XMER in 1670 urban area, where capacitors are to be installed. Total No. of XMER 8116 10 kVAR 12 kVAR 20 kVAR 0 15029 8494 2124 0 4426 2124 15029 12920 3.18 GUARANTEED TECHNICAL PARTICULARS The Guaranteed Technical Particulars in prescribed Performa shall be furnished duly filled along with the tender. S C H E D U L E – IV SCHEDULE FOR GUARANTEED AND GENERAL PARTICULARS FOR EACH RATING OF CAPACITORS Sr. No 1 Description 2 3 4a 4b 4c 4d Manufacturer‘s Name & Trade mark Country of origin Whether ISI marked ISI mark License No. Valid up to Rating covered in license (enclosed copy of license) Shape of basic element Type of dielectric film used Thickness of PP film (Micron) Voltage stress (volts/micron) 5a 5b 5c 5d Details Type / Rating Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 238 Technical specification 5e (i) (ii) 6 (i) (ii) 7 8 9 10 10a 11 (i) (ii) 12 13 14 15 16 17 18 19 21 22 23 24 25 26 27 28 Voltage rating of each pack Without thickness of impregnate With thickness of impregnated Dielectric used Inflammable Type of dielectric Type of impregnated used Rated capacity of each capacitor unit Rated voltage of capacitor unit Maximum temperature rise Hot spot temperature rise Voltage proof test Test voltage between terminals Test voltage between terminals & container. Weight of each capacitor unit Material & dimension of container Whether protective cap & insulation block is suitable for outdoor operation/installation and safety for accidental contact provided Whether pressure sensitive device for internal faults provided Life expectancy in hours & percent failure rate Overload capacity (voltage/current) Dielectric loss per KVAR Total loss per KVAR Percentage tolerance on capacity Percentage drifting capacitance over a period of 5 year Details of type/routine &acceptance testing facilities available Characteristics of discharge devices (residual voltages & discharge time) Whether capacitor with and installation accessories are IE rules compliant Characteristics of gas used Whether capacitor unit suitable for mounting in any desired position Details of mounting arrangements (Drawing should be enclosed) Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 239 Technical specification 3.36 TECHNICAL SPECIFICATION 11 KV UTOMATICALLY SWITCHED CAPACITOR BANKS AT 33/11KV SUB-STATIONS FOREWORD: 11 KV capacitor bank controlled by manually switched devices like Isolators/Load Break Switch or circuit breakers has the following disadvantages as compared to modern automatically switched Capacitor Bank: • The ON/OFF operation of capacitor bank depends on one operator and it is difficult to regulate switching the capacitor bank as per varying load condition resulting in sub-optimal utilization of the investment made. • Quantum of reactive compensation in circuit can not be controlled in small steps. • This results in over compensation or under compensation of reactive power at varying load conditions. • Difficult to keep a close watch on various parameters such as current in each phase of the capacitor bank, system voltage, unbalanced operating conditions etc., to provide adequate protection to the capacitor bank against abnormal operating conditions thereby increasing the chances of capacitor failures. • The scheme eliminates conventional components like Electro Magnetic Relays etc. • A modern SF6 or Vacuum type circuit breaker is a costly equipment and designed for isolating faults rather than for reactive power switching duty. The breaker, there-fore is not ideal equipment for control of capacitor bank which may have to be operated a large number of times in a day. To overcome above shortcomings use of 11 KV Capacitor Switches (instead of circuit breakers) for operation of capacitor bank divided into suitable steps for optimum utilization is being adopted. The Circuit Breaker is replaced by no. of Capacitor Switches for utilizing the capacitor bank in various steps as required. However it should be noted that main incomer to capacitor bank shall be circuit breaker only. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 240 Technical specification 1. SCOPE: 1.1 This specification covers design, engineering manufacture, testing at manufactures works, supply and delivery, erection, testing and commissioning of 11 KV outdoor types 3 phase capacitor banks at site for out door installation along with necessary equipments in all respect. 1.2 The specification covers 3 phase, 50 Hz, Out door type automatically switched capacitor bank intended for installation at 11 KV side of 33/ 11 KV power transformers in various sub-stations. The equipment covered in this specification comprises of Capacitor banks in steps, 0.2 % Series Reactors, Capacitor switch, HT Fuses, RVT, CT etc. 2.Climatic condition: 1 . Max. ambient air temperature 2 2. Min. ambient air 3. Average Daily Max. ambient temperature 4. Max. yearly weighed average ambient temperature 5. Max. altitude above mean sea level 6. Minimum Relative Humidity (%aqe) (Meters) 7. Max. Relative Humidity (%aqe) 8. Avq, No. of Rainy days/year 9. Avq, annual rainfall 10. Maximum wind pressure 500C 5C C 40CC 32CC 1000 26 95 120 900 mm 195 Kq./m Sq. 3.0Applicable Standard: Unless otherwise modified in this specification, the capacitor shall comply with latest version of IS: 13925:1998. The other components such as Vacuum Circuit Breaker, Isolator, CT, PT, LA, Capacitor Switches, HT fuses, Series Reactors, Auxiliary equipment shall comply with the latest version of relevant Indian Standards/International standards. A. Capacitor banks: The capacitor banks are for use in a 3 phase 50 Hz 11 KV system. Capacitor bank shall consists of small units of capacitor cells series/parallel combination per phase, each with an out put rating of 100/150/200/400 kVAr, 7.3 KV single phase. Capacitor units should be connected in externally star with appropriate number of capacitors in parallel as per requirement. For Example 3 single units of 150 KVAr connected in star to obtain 450 and 2 capacitors Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 241 Technical specification units in parallel per phase with 3 phase connection in star to obtain 900 KVAr OR 3 single units of 100/200 KVAr connected in star to obtain 300/600 and 2 capacitors units of 200 KVAr in parallel per phase with 3 phase connection in star to obtain 1200 KVAR at 12.65 KV 3 phase. Necessary number of steps should be provided to meet requirement given in the schedule. Table 1.0: Capacitor Bank Rating: Type - I Sr. Transformer Capacitor Bank Step configuration kVAr Combination of Output available (KVAr) No. Rating at 12.89 450 XX 3No. Units I. Rating 5000 KVA 2250 KVAR + of 900 X 1 450, 900,1350,2250 kV II 8000 KVA 2700 KVAR 450 X 2 + 900 X 2 450, 900, 1350, 2250, 2700 III 10000 KVA 3600 KVAR 900 X 4 900, 1800, 2700 & 3600 Each capacitor unit should be provided with external expulsion fuse 12 KV class and suitable current rating. Capacitor shall meet following specifications: 4. Temperature Category: The capacitor shall be suitable for upper limit of temperature category 50 Deg. C as per IS: 13925. 5.Rated Voltage: The rated voltage of 3 phase capacitor banks shall be 12.65 KV (phase to phase). 6.Rated Output: The rated output of 3 phase capacitor banks shall 2250/3600 kVAr at the maximum operational voltage of 12.65 KV intended for use on power transformers ratings of 5MVA, 8 MVA, 10 MVA. The standard basic unit capacitors (single phase) shall be 100/150/200/400 kVAr. The unit connected in externally star formation with floating neutral. be 7. Permissible Overloads: For capacitor covered in this specification, the maximum permissible overloads with regard to voltage, current and reactive output shall not exceed the limits specified in IS:13925. 8. Power Loss: The power loss in capacitors shall not exceed 0.2 watt / KVAR (Subject to tolerance of + 10%). Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 242 Technical specification 9. Discharge device: Suitable discharge device shall be connected across the capacitor unit in accordance with IS:13925. The discharge device shall reduce the residual voltage from the crest value of the rated voltage to 50 V the or less within 10 Minutes after the capacitor is disconnected from the source supply. 10. Earthing Connections: The container of each capacitor unit shall be provided with suitable earthing terminal clearly marked with Earth symbol. 11. Protective Fuses : The capacitor units shall be provided with external Expulsion fuses together with fixing accessories. 12. General Requirements: The capacitor shall be of non-PCB type, using polypropylene film as the dielectric. Complete mounting brackets supporting insulators and all other components for formation of capacitor banks racks shall be supplied along with the capacitor units. Necessary foundation bolts I nuts shall also be supplied. The outside of the capacitor container and other structures should have smooth and tidy look and should be coated with the weather proof, corrosion-resistant paint of white or light grey. 13. Marking: The capacitor unit shall be provided with a rating plate and terminal markings as stipulated in IS: 13925. The bidder shall submit the type test report along with the bid. 14. TESTS: The switched capacitors shall be subjected to all the type, routine and acceptance test in accordance with IS: 13925. B AUTOMATIC CONTROL UNIT 15. Switching Arrangement: 1.1 The Automatic control unit shall be provided inside the control; room to continuously monitor total load KVAR on secondary side of the transformer and shall automatically switch ON or switch OFF the capacitor banks through the operation of 12KV Capacitor Switch in accordance with the parameter given in table no.1. Overriding provision shall also be made for electrical Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 243 Technical specification switching ON or OFF of the capacitor switch by the operator from the ACU control box. 16. Time Delay: The switching ON operation will take place after period of 10 minutes. The switching OFF operation of relevant steps will be instantaneous. 17. Controls: The Automatic control unit shall instantly switch OFF the incomer VCB of capacitor bank in the following contingencies occurring in any of the phases. a) Voltage increased by 10% above the rated voltage of 11 KV. b) Power transformer current impedance (due to single phasing and for any other reasons) between any of the two phases exceeding 20% of the lowest. c) Current increases in any capacitor unit by 30% above the rated current (only the relevant capacitor switch will open). Current between any of the two phases of the capacitor bank differs more than 15% of the lowest current of the 3 phases (only the relevant capacitor switch will open) 18. Monitoring Facility: A suitable display should be provided to indicate the capacitor current in each phases of the complete capacitor bank on the ACU panel inside the control room by putting anlogic circular dial ammeter. Indications shall also be provided to indicate ON & OFF status of each capacitor bank. 19. Control Power: The DC control voltage for operation of the ACU shall be taken from substation battery. The required control voltage shall be 110 VDC/110 VAC /230 VAC. 20. Temperature Variation: The control equipment and associate circuitry shall be suitable for operation at an ambient temperature in the range of + 5 deg C to (+) 50 deg C. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 244 Technical specification 21. Protection of ACU: Besides in-built protection against lines surges and transient over voltages, suitable fuses/ MCB shall be provided for protection against over current. The ACU shall remain fully functional during and after line surges and transient over voltages. 22. Control Unit Casing: Except for the terminals, the ACU shall be enclosed suitable casing so as to avoid ingress of dust. in a 23. Scope This specification covers 11 KV, 50 Hz, Outdoor type automatic Capacitor Switch suitable for switching capacitor steps of 300/450/600/900 & maximum up to 1200 kVAr 24. APPLICABLE STANDARDS Unless otherwise stipulated in this specification the Capacitor Switch shall comply with the latest version of IS:9920 (AC Switches for voltages above 1000 V). 25. RATED VOTAGE The rated voltage for the Capacitor Switch shall be 12 KV. This represents the highest system voltage corresponding to the nominal system voltage of 11 KV. 26. RATED CURRENT The standard rated normal current shall be 200A 27. RATED CAPACITIVE SWITCHING CURRENT The rated capacitive switching current shall not be less than 50 A Note: The capability of the Capacitor Switch shall also take into account the parallel switching of capacitor bank steps. 28. RATED SHORT TIME CURRENT The rated short time symmetrical current for 1 second shall be 10KA (rms AC. component). 29. RATED MAKING CURRENT The rated making current shall be 2.5 times the rms value of Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 245 Technical specification the a.c. component of rated short time capacity. 30. BASIC IMPULSE LEVEL (BIL) The rated basic impulse level of Capacitor Switch to earth as also across the open terminals shall be 75 KV. 31. CONTROL SUPPLY The control power for closing the Capacitor Switch shall be 230 V single phase AC supply. The closing mechanism shall be suitable for a voltage variation of (+) 10% to (-)20%. 32. DESIGN & CONSTRUCTION REQUIREMENSTS 32.1. TYPE The Capacitor Switch shall be of either vacuum or SF6 type. 32.2. The Capacitor Switch shall be of three construction and shall be suitable for operation. phase remote 32.3. The Capacitor Switch shall be suitable for outdoor installation and shall have sealed weather proof type construction. 32.4. The Capacitor Switch shall be provided with a mechanical indicator to show whether the contact is in open/closed position, locally, as also through indication on the ACU panel. 32.5. The metallic enclosure of the Capacitor Switch shall be provided with two earthing terminals marked with the earth symbol. 32.6 The bushings provided on the switch shall have clamp type of terminals to directly receive aluminium conductors up to 10mm dia in both horizontal and vertical directions. The terminal arrangement shall be such as to avoid bimetallic corrosion. 33.0PERATING MECHANSIM The operating mechanism shall be either solenoid or motor charged spring for which the control supply shall be as per clause 31. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 246 Technical specification 34. MECHANICAL AND ELECTRICAL ENDURANCE The Capacitor Switch shall be capable of performing not less than 10,000 mechanical operations and 10,000 electrical operations at 50A capacitive current without getting damaged. 35.MARKING The Capacitor Switch shall be provided with a legible and indelibly marked name plate with the following: a) Name of the manufacturer. b) Type, designation and serial number. c) Rated voltage and current. d) Rated frequency. e) Number of poles. f) Rated short time current (symmetrical). g) Rated making current. h) Rated capacitive switching current. 36. TESTS The Capacitor Switch shall be subjected to the following tests in accordance with the IS:9920 (Part-IV). 36.1. a) Type Tests Tests to verify the insulation level, including withstand tests at power frequency voltages on auxiliary equipment. b) Tests to prove that the temperature rise of any part does not exceed the specified values. c) Making and breaking tests including tests for the rated capacitive current. d) Tests to prove the capability of the switch to carry the rated short time current. e) Tests to prove satisfactory mechanical/electrical endurance. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 operation Assam Power Distribution Company Ltd and 247 Technical specification 36.2. Routine Tests a) Power frequency voltage dry tests. b) Voltage tests for auxiliary circuits. c) Measurement of the resistance of the main circuits. d) Tests to prove satisfactory operation. D. AUXILARY EQUIPMENTS 37. Isolator: 37.1. The Isolator shall be Outdoor type, 11 KV, 400/630/800Amp, Single throw, Double break, off load type, triple pole, Horizontal gang operated with earth switch. 37.2. Tests: The Isolator shall be type tested and shall be subjected to routine and acceptance test in accordance with IS: 1818-1972. 37.3. The bidder shall submit guaranteed particulars along with their bid. technical 38. 11 KV lndoor Vacuum Circuit Breaker with Panel: 1.0 Scope: The specification covers supply and installation of 3 pole, 50Hz at 11 KV, 350 MVA rupturing capacity, 400/600/800 Amp r a t e d current. V.C.B. shall comply the latest specification of APDCL. Vacuum circuit breaker having motor operated spring changing mechanism and electrical as well as manual closing facility for indoor installation matching / in conjunction with existing 11 KV panels including all necessary equipment such as CT(S) as per rating of capacitor bank, PT(S) and instruments such as Ammeter, Voltmeter Kvar and devices like relays as follows. i) ii) T h r e e No of Voltmeter (0-15 KV), 3 Nos. Ammeter of size (144 X144mm) of range 0-400/800Amp shall be fitted with each panel. The meters shall be analogic with circular dial. Relays: NUMERICAL a) Over Current = 2 Nos. + Earth Fault = 1 No combined one unit. b) Over Voltage Protection c) Unbalance Protection: Neutral displacement relay d) No voltage / Under Voltage Protection with 600 sec. timer e) Auxiliary relays to suit the purpose. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 248 Technical specification 1.1 Rating: The VCB shall comply with the following requirements: i) Nominal System Voltage: 11 KV. ii ) Maximum System Voltage: 12KV. iii) Rated Current: 400A/630A/800A. v) Frequency: 50 Hz. v) Insulation level: 28KV (rms) / 75KV (peak). vi) Operating Mechanism: Spring Charged Motor. vii) Auxiliary Voltage: 11OV DC& 240 VAC. viii) Creepage Distance: 25 mm/KV 1.2 Tests: The Vacuum Circuit Breaker shall be type tested and shall be Subjected to routine and acceptance test in accordance with IS: 13118. 1.3 Guaranteed technical Particulars: The bidder shall submit guaranteedTechnical particulars along with their bid. 39. Current Transformer: 1.0 The current transformers shall be dry type, suitable current ratio and burden for measuring the capacitor current, shall form part of the equipment to be supplied. These CT‘s shall be form an either an integral part of Indoor VCB or may be separate outdoor type on structure. The accuracy class for the purpose of measuring the current shall be1.0. 1.1 Tests: The Current Transformer shall be type tested and shall be subjected to routine and acceptance test in accordance with IS: 2705. 1.2 The bidder shall submit guaranteed technical particulars along with their bid. 40. Lightning Arrestor: 1.0 The specification covers the supply, delivery, erection, testing & commissioning of 9 KV, 10 KA, Station class heavy duty, gapless, metal (zinc) oxide surge arrestors complete along with clamps, complete fitting and accessories for installation on outdoor type 11 KV switchgear, transmission lines, transformers etc. 1.1 Tests: The Lightning Arrestors shall be type tested and shall be subjected to routine and acceptance test in Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 249 Technical specification accordance with IS: 3070. 1.2 The bidder shall submit guaranteed technical particulars along with their bid. 41.0 Residual Transformer: Voltage 1.0 The Residual Voltage Transformer shall be oil cooled type, 11 KV class, 5 Limb, with three windings i.e. Star/Star — Open delta. The Primary winding-I in Star, Secondary-I in Star for metering and Secondary-Il in Open delta for protection. 1.1 Tests: The residual Voltage Transformer shall be type tested and shall be subjected to routine and acceptance test in accordance with IS: 3156. 1.2 The bidder shall submit guaranteed technical particulars along with their bid. 43. Expulsion Fuses: 1.0 Suitable outdoor type 11 KV expulsion fuses along with the mounting insulators etc. to provide proper protection for the capacitor unit shall form part of the equipment to be supplied. 44. Series Reactors: 1.0 0.2 % Series reactor per phase per step of capacitor rating for inrush current restriction to be connected on neutral end as per IS: 5553. The rated voltage shall be 12 KV. The reactor shall be dry type single phase reactors mounted on post insulators and designed to carry 130 % of rated current continuously without exceeding the temperature rise & shall be applicable for thermal class of insulation used. The reactor shall be mounted on structure. 1.1 Tests: The series reactor shall be type tested and shall be subjected to routine and acceptance test in accordance with IS: 5553. 1.2 The bidder shall submit guaranteed technical particulars along with their bid. 45. 11 KV HT Cable (XLPE): A Power Cable: 1.0 11 KV power cable shall be hot cured XLPE of following size conforming to IS: 7098 (P-Il) amended latest. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 250 Technical specification 11 KV Incoming: Three/Single core, 95/125/240/400 Sq. MM. 11KV (E). Jointing kit shall be heat shrink type as per latest relevant IS specification for indoor and out door utilization matching with the above cables. 1.1 Cable Jointing: - Jointing should be heat shrink type. All materials required for such type of jointing of XLPE cable shall be supplied by the contractor. The work shall be carried out only by licensed / experienced cable jointer holding necessary license of cable jointing of appropriate grade. Sufficient surplus cable in the form of loop shall be left on both sides of the cable. B Control cable: The control cable shall conform to IS: 1554 (Part-I) 1976. All control cable shall be of copper and armored type. The bidder may furnish cable such schedule after finalization of sub-station layout, associated cable connection. 46. Capacitor Bank Structure : Capacitor bank shall be outdoor type, each individual step along with required current limiting reactors , capacitor switch, RVT etc.. shall be mounted on Suitable G.I. mounting and elevating structure , each capacitor unit shall be provided with an external expulsion fuses . Bank shall be complete with necessary 11 KV class post insulator ,aluminium bus bar etc. 47.SUBMISSION AND APPROVAL OF DRAWINGS: Following drawings and technical documents shall be submitted along with the bid. • Technical data sheet • GA drawings. • Bill of Material. General Technical Particulars. 47. INSTALLATION MAINTAINANCE: OPERATION AND The supplier shall provide: 1) Necessary manual on Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 installation, operation Assam Power Distribution Company Ltd and 251 Technical specification maintain ace as also the schedule for the routine testing or check ups of all the equipments covered by the installation. 2) List of recommended spares indicating prices and specialized test equipments required for the routine testing of the system. 48.GUIDANCEFOR PROCUREMENT: The entire equipment covered under this specification shall be covered as a single package to avoid the problem of mismatching for maintenance etc. 49. WARRANTY: The suppler shall guarantee satisfactory performance of the complete capacitor bank installation for a period of 36 months from the date from the date of commissioning, which ever is earlier. During the warranty period all repairs/replacements shall be carried out free of cost. 50. INSPECTION: All tests and inspection shall be made at the place of manufacturer unless otherwise especially agreed upon by manufacturer and the purchaser at the time of purchase. manufacturer shall afford the inspector representing purchaser, all reasonable facilities, without charge, to satisfy that the material being supplied is in accordance with specification. the the The the him the The purchaser has the right to get the tests carried out at his own cost from an independent agency, whenever there is a dispute regarding the quality of the supply. The manufacturer shall be responsible to pay penalty of Rs 20,000/- for each occasion at which the fake inspection call has been made or the material is rejected during testing/inspection by the authorized agency/representative of the Nigam. This penalty would be in addition to the expenses incurred by the Company in deputing the Inspecting Officer, carrying out such inspection 51. Challenge Clause:The material offered/received after the inspection by the authorized ]officer may again be subjected to the test for or any parameter from any testing house/in-house technique of the Company & the results if found deviating un-acceptable or not complying to approved GTP‘s the bidder shall arrange to supply the replacement within thirty (30) days of such detection at his cost including to & fro transportation. In addition, penalty @10% of cost of the inspected lot of material shall be imposed. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 252 Technical specification TECHNICAL SPECIFICATIONS FOR LT ABC CONDUCTORS CONNECTORS AND FITTINGS FOR LV – ABC Standards: NF C 33020, 33021, 33040, 33041, 33042 & ESI 43-14 Summary: 1. 2. 3. 4. 5. 6. 7. 8. 9. General conditions Anchoring clamps Suspension clamps Service clamps Transformer connections Junctions Insulation Piercing Connectors Distribution boxes Eye Hooks 1. General Conditions The products shall be in accordance with Indian standards and most of the European recognised standards used in LT ABC (NFC for example) or with any relevant standard. Marking: Each product shall be clearly identified with Manufacturer name or trade mark, reference and capacity of the item and batch No. Packaging: Manufacturer shall mention the packaging of each item. Installation instruction should be included in the packaging. Type tests: Each supplier should provide type test reports with the offer, carried out in accordance with one of the referenced standards in NABL accredited laboratory. Routine tests: Suppliers shall provide a control plan, which will be implemented on each item. Routine Test reports should be submitted by the manufacturer with the Inspection Call. Quality: All suppliers should be ISO 9000 certified. Anchoring and Suspension clamps should be installable on existing poles using appropriate devices (hooks, pigtails, brackets etc.) All crimped connectors should be installed with mechanical or hydraulic hand crimping tools. 2. Anchoring clamp for Insulated messenger: The clamps should be designed to anchor LV-AB Cable with insulated neutral messenger. The clamp should consists of an Aluminium alloy corrosion resistant castled body, bail of stainless steel and self-adjusting plastic wedges which shall anchor/hold the neutral messenger without damaging the insulation. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 253 Technical specification The clamp should be installed properly. No losable part in the process of clamping arrangement. The clamp should conform to the standard NF C 33041 and 042 or equivalent I.S., if any. The clamp body should be made of corrosion resistant Aluminium alloy, bail should be of stainless steel and wedges should be of weather and UV resistant polymer. Clamps should be fixed with pole by eye hook/bracket. Bracket should be made of corrosion resistant Aluminium alloy. Ultimate Tensile Strength of the clamp should not be less than 15 KN for 50/70 Sq.mm insulated messenger wire / 10 KN for 25/35 sq.mm insulated messenger wire. Slip load of the clamp should not be less than 3 KN for 50/70 Sq.mm insulated messenger wire/2 KN for 25/35 sq.mm insulated messenger wire. Design as per furnished drawing. 3. Suspension clamp for insulated neutral messenger: The clamps should be designed to hang LV-AB Cables with insulated neutral messengers. The neutral messengers should be fixed by an adjustable grip device. A movable link should allow longitudinal and transversal movement of the clamp body. The clamp should be installed properly. No losable part in the process of clamping arrangement. The clamp should conform to the standard NF C 33040 or equivalent I.S., if any. The clamp and the link made of the Polymer should provide an additional insulation between the cable and the pole. The clamps and the movable links should be made of weather and UV resistant glass fibre reinforced polymer. Clamps should be fixed with pole by eye hook/bracket. Bracket should be made of corrosion resistant aluminium alloy. Ultimate Tensile Strength of the clamp should not be less than 15 KN for 50/70 Sq.mm insulated messenger wire / 4.3 KN for 25/35 sq.mm insulated messenger wire. Maximum Allowable load of the clamp should not be less than 20 KN for 50/70 Sq.mm insulated messenger wire / 15 KN for 25/35 sq.mm insulated messenger wire The clamp should sustain to maximum angle of deviation of 60 degrees of the conductors. Design as per furnished drawing. 4. Service clamps The clamps should be designed to anchor insulated service lines (armoured or unarmoured) with 2/4 conductors. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 254 Technical specification The clamps should be made of weather and UV resistant polymer. The clamp should be installed properly. No losable part in the process of clamping arrangement. The clamp should conform to the standard NF C 33042 or equivalent I.S., if any. Breaking load of the clamp should not be less than 3 KN. Design as per furnished drawing. 5. Transformer connections The connection to the transformer should be made with Pre-Insulated Lugs for Phase and Street Lighting conductors and with an Aluminium Lug for Neutral Messenger. If the Bus Bars are of Copper, the Lugs should be preferably Bi-metallic type. The Barrel of the Lug normally insulated with an Anti-UV black Thermoplastic tube sealed with a Flexible ring. Die reference, size and strip length are indicated on the plastic. Sizes Covered: 16 – 70 & up to 150 mm² Aluminium XLPE insulated Referenced standard: NFC 33 021 or equivalent I.S., if any. Design as per furnished drawing. . 6. Junction sleeves The sleeves should be Pre - Insulated for Phases, neutral messengers and Street Lighting conductors. Sleeve should be made of Aluminium, insulated with an anti UV black thermoplastic tube hermetically sealed two ends with 2 flexible rings. Die reference, size and strip length are indicated on the sleeve itself. Sizes needed: 16 – 70 -& upto150 mm² for Aluminium XLPE insulated Referenced standard: NFC 33 021 or equivalent I.S., if any. Design as per furnished drawing. 7. Insulation Piercing Connectors as per the standard NF C 33020 or equivalent I.S., if any. Scope In the process of replacing the Bare Conductors with LT AB Cables to reduce power theft & Transmission Losses, it is important to analyze the proper method of providing service connection from AB Cables to our consumers without damaging the cable. Removal of Bare Conductor, Stringing of LT AB Cable & re-establishing the service connections should be simultaneous process. In this regard the Insulating Piercing Connectors are required- a) for providing 1-2 service connections from 8 mtr. PCC LT pole, b) for providing supply to Junction/ Distribution Box from AB Cable & c) for establishing Tee connection from LT ABC to LT ABC. This Insulating Piercing Connectors should not be exposed to any bare conductor in the environment during connection. The Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 255 Technical specification connectors should be totally Weather & Moisture proof so that no water or moisture can enter through the pierced holes on to the cable insulation. It must have Shear Head type mechanism to control the effective Torque during connection and to ensure perfect installation. Connectors should not have any losable parts, which may drop and then lost while installation at overhead conditions. For individual connectors Torque required for different conductor sizes should be mentioned in the equipment. Technical requisites Construction: Voltage Ratings: Moisture Ingress: Working Temp.: Materials: The connectors should be totally insulated with no loose parts. The connectors should be totally Weather & Moisture proof so that no water or moisture can enter through the pierced holes on the cable insulation. The maximum voltage withstand capacity should be 6 KV. The connectors should work at 30 cm under water bath for 30 min. & voltage applied of 6KV for 1 min. without any flashover/ failure & moisture ingress in it. Designed for installation from -10˚C upto +60˚C & operation experience with temperature from -20˚C upto +75˚C. Material used in the manufacturing process of the components of this product should be specified in the respective product drawings & can be summarized as follows: All the metallic part of the connector should be Corrosion resistance & should be proven in Salt Fog chamber & Wet SO2 gas chamber & there should not be any change in contact resistance & temperature after overloads & load cycling. The contact plates should be made of tinned Copper. Connector teeth should be factory greased & sealed to retard water or moisture ingress & corrosion. The insulation material should be made of weather & UV resistance, reinforced polymer. The outer metallic part should have potential free tightening bolts to allow safe installation on life lines. The bolts should be of Shear Head type so that it controls the effective applied Torque during installation & break off at a specified torque after establishing proper connection. The connector should not have any losable component. The cable end cap should be attached to the body. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 256 Technical specification Testing Standards: The Insulating Piercing Connector should conform to following std.Tests Tests Standard/ Test Procedure Corrosion As per NF C 33-020 (Jun‘98), or equivalent I.S., Qualification if any. Test Exposure in Saline Environment- The exposure should be carried out as per NF EN 60068-211(Aug‘99) std. requirement. The concentration of Saline solution must be of 5% ± 1% in mass, & the temperature of the test chamber must be maintained at 35˚C ± 2˚C. Exposure in Sulphur environment saturated of humidity - The exposure should be carried out as per NF T 30-055(Mar‘74) std. requirement. SO2 concentration in the chamber should be 0.067% in volume. The temperature of the test chamber should be increased to 40˚C ± 3˚C. The total test should include four identical periods of 14 days, in which 7 days of exposure in Saline environment & in other 7 days - 8 hrs cycles in SO2 environment & 16 hrs in laboratory environment. Electrical As per NF C 33-020 & NF C 33-004 (Jun‘98), or Ageing Test equivalent I.S., if any. Total no. of cycles-200, Heating time -60 mins., Cooling time- 45mins., Pause time – 2 mins. Dielectric As per NF C 33-020 (Jun‘98), or equivalent I.S., Investigation if any. Test in Water The connector should be placed in an ambient temperature between 15˚C & 30˚C & relative humidity between 25% & 75%. The tightening of the connectors should be at minimal value of the torque indicated by the manufacturer. The sample should be placed in tank full of water on 30cm height, after an immersion length of 30mins. The set is subjected to a dielectric test under a voltage of 6KV at industrial frequency during 1 min. No flashover/ breakdown should occur at 6KV during 1 min. Mechanical Tests As per NF C 33-020 (Jun‘98), or equivalent I.S., if any. For checking electrical continuity, shear heads & mechanical behaviour of the connector‘s suitable tests as per the above specification have to conduct. Referenced standard: NFC 33 020 or equivalent I.S., if any. 8. ABC Service main Distribution boxes Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 257 Technical specification Scope Technical requisites Construction: Current Ratings: Voltage Ratings: Working Temp.: Materials: This Distribution Box should be Weather & Moisture Proof with Spring loaded Bus Bar system & should be able to carry a current according to specified ampacity. It can have 1 /3-phase input & provision for 4 or 9 nos. of 3- phase or 1-phase outputs. The box should have the provision for special key for locking & Proper arrangement of sealing. The boxes should be assembled on the pole using Metal Tapes & Buckles or Bolts. No. of Boxes per pole may vary with supporting arrangement for more no. of service connections. Distribution Boxes should be designed with Bus Bars with spring action contact, so that no screw-bolt technique is required to operate & only insertion of the conductor into the specified groove of the Busbar is sufficient for proper connection. It should be used for multiple connections (3-phase or 1-phase) in low voltage Distribution Network. The boxes should be suitable for 1/ 3-phase (4 cores) inputs & provision for 4 or 9 nos. of 3- phase or 1-phase outputs. Bus bars should be with a continuous pair of contact bars with colour code to facilitate the identification of the correct energy phase. The box should be able to incorporate the input or output cable dia. of maximum 16mm. (Equivalent to 120Sqmm.) The Boxes should consist of special type Lock & key system as well as provision for sealing for complete protection of the service connection contacts. The maximum current rating should be 140A/ 200A/ 250A. & concerned authority should have the liberty to choose among the above ratings as per their requirement. The maximum voltage withstand capacity should be 600V. Safe working temperature should be around 80˚C for Outer Box & 100˚C for metallic Bus bars. Material used in the manufacturing process of the components of this product should be specified in the respective product drawings & can be summarized as follows: Outer Box (Base & Cap): With UV protection & Flame retardant characteristics (HB, as per UL 94- Tests for Flammability of Plastic materials) & preferably made up of ASA (Acrylonitrile Styrene Acrylate). Cable Grommets: Ethylene-Propylene Rubber. Safety Key: PA 6.6 (Nylon). Safety Screw: Stainless Steel or Plating Finished steel. Insulator protection as per IP 44 Bus bars or Terminal Blocks: PA 6.6 (Nylon), Stainless Steel & Copper. Button & Cable Holder: PA 6.6 (Nylon) with 50% Glass Fibre. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 258 Technical specification Locking System: Busbar Insulation: Polyamide. The boxes should consist of Special type Lock & Key arrangement as well as provision for sealing for complete protection of the service connection contacts. Testing Impact Resistance should be according to UL 746C. Insulation Protection should Standa be as per IP 44. The Outer Plastic box should conform to following std.rds: Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 259 Technical specification 9. Eye Hooks: Eye hooks should be designed as to hold Suspension Clamps and Dead end Clamps and to be installed with the Pole Clamps: Eye hooks should be made of forged Galvanised Steel. The clamps corrosion resistance should confirm to the standard IS: 2629 and IS: 2633 Bolt and nuts should be made of hot dip galvanised steel, according to VDE 0210 and VDE 0212. Ultimate Tensile Strength (UTS) of the clamp should be 20 KN. Design as per furnished drawing. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 260 Technical specification TECHNICAL DATASHEETS GUARANTEED TECHNICAL PARTICULARS for premoulded Straight joint FOR LT 1.1kv 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 17. 18. 19. Name & address of the Manufacturer Applicable standard Type of Cable jointing kit Application Nominal system voltage (kV) Maximum system voltage (kV) Number of cores Type of insulation Type of screening System Neutral Earthing Maximum performance AC voltage Load cycling 900C + 50C (no. of cycles) Impulse voltage Partial discharge voltage Thermal short circuit DC voltage Dynamic short circuit Authorised Signatory Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 261 Technical specification Guaranteed Technical Particulars for Insulating Piercing Connectors Type 1. 2. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. For Street Light For DB Charging For ABC to ABC TEE Name of the Manufacturer Is manufacturer of accessories as ISO 9001 2000 company a) Copies of Certificate Enclosed b) Are GA Drawing enclosed Applicable standard Type of connectors Application Is any metallic part carrying potential in operation exposed during installation Are end caps of branch cable a) Slide on type b) Rigid Are torque limiting shear heads provided to tightening bolts Range of cable sizes accommodated for main & branch Min. & Max. torque defined Torque for establishing connection between main and branch Max. tensile load for no breakdown of main conductor (for each crosssection) Max. tensile load on branch conductor for no break / slippage Voltage withstand under water emersion Is electrical Ageing test report enclosed No. of Cycles Max. temp at each cycle Marking and embossing on the connector Authorised Signatory Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 262 Technical specification Guaranteed Technical Particulars for Eye Hook Sl No Particulars Unit 1 Type of Clamp 2 Name of the Manufacturer 3 Place of Manufacture 4 Type of design 5 7 Type & grade Metallic / Nonmetallic material Type of hot dip galvanizing & thickness of Zinc coating Dimensions mm 8 Approximate weight Kg 9 Ultimate tensile strength KN 6 Bidder‘s Offer Authorised Signatory Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 263 Technical specification Guaranteed Technical Particulars for Suspension Clamps suitable for Insulated Messenger wire Sl Particulars No 1 Type of Clamp 2 4 Name of the Manufacturer Place of Manufacture Type of design 5 Standard 6 Loop anchor attachment (Open/Close) Installation (with/without disassembly) Type & grade Metallic / Nonmetallic material Marking 3 7 8 9 Unit 10 Colour of Nonmetallic parts 11 Dimensions Mm 12 Approximate weight Kg Bidder‘s offer Bidder‘s offer 13 Ultimate tensile KN strength 14 Maximum allowable KN load 15 Maximum angle of Degrees deviation of conductors Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 264 Technical specification Guaranteed Technical Particulars for Dead end Clamps suitable for Insulated Messenger wire Sl No 1 2 Particulars Bidder‘s Offer Bidder‘s Offer Type of Clamp 3 Name of the Manufacturer Place of Manufacture 4 Range of conductor size 5 Standard 6 Type of design 7 Installation (with/without disassembly) Type & grade Metallic / Nonmetallic material 8 Unit Sq mm 9 Marking 10 11 Colour of Nonmetallic parts Dimensions Mm 12 Approximate weight Kg 13 Ultimate tensile strength KN 14 Maximum allowable load KN 15 Slip load KN Authorised Signatory Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 265 Technical specification GUARANTEED TECHNICAL PARTICULARS for Waterproof preinsulated compression type bimetallic socket FOR LT 1.1kv 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 17. 18. 19. Name & address of the Manufacturer Applicable standard Type of Cable jointing kit Application Nominal system voltage (kV) Maximum system voltage (kV) Number of cores Type of insulation Type of screening System Neutral Earthing Maximum performance AC voltage Load cycling 900C + 50C (no. of cycles) Impulse voltage Partial discharge voltage Thermal short circuit DC voltage Dynamic short circuit Authorised Signatory Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 266 Technical specification GUARANTEED TECHNICAL PARTICULARS (GTP) FOR SPRING LOADED CONSTANT PREASSURE MULTI CONNECTION ASA DISTRIBUTION SYSTEM Bidder‘s offer Sl No Particulars 1 Name of the Manufacturer 2 Place of Manufacture 3 Type of Box 4 Type of design Application 5 6 Installation 7 8 9 Type & grade Metallic / Nonmetallic materials for Inner Contact Region Type of material for Outer Box Maximum Current Ratings 10 Maximum Voltage withstand capacity 11 Safe Working Temperature 12 Insulation Protection 13 Impact Resistance 14 16 Range of cable sizes can be accommodated Are special keys Available for theft protection Provision for Lead sealing 17 Marking 18 Colour of Non metallic parts 19 Dimensions 15 Authorised Signatory Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 267 Technical specification TECHNICAL SPECIFICATIONS FOR ACCESSORIES AND HARDWARE FITTINGS FOR HT – ABC Summary: 10. General conditions 11. Tee Connections with Surge protection . 12. Straight Through Joints. 13. Outdoor End Terminations. 14. C-wedge boltless connector 15. Anchoring clamps 16. Suspension clamps 17. Eye Hooks. 18. Pole Clamps. General Conditions The products shall be in accordance with Indian standards and most of the European recognised standards used in HT ABC with any relevant standard. Marking: Each product shall be clearly identified with Manufacturer name or trade mark, reference and capacity of the item and batch No. Packaging: Manufacturer shall mention the packaging of each item. Installation instruction should be included in the packaging. Type tests: Each supplier should provide type test reports with the offer, carried out in accordance with one of the referenced standards in NABL accredited laboratory. Routine tests: Suppliers shall provide a control plan, which will be implemented on each item. Routine Test reports should be submitted by the manufacturer with the Inspection Call. Quality: All suppliers should be ISO 9000 certified. Anchoring and Suspension clamps should be installable on existing poles using appropriate devices (hooks, Pole clamps etc.) All crimped connectors should be installed with mechanical or hydraulic hand crimping tools. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 268 Technical specification Specification of Tee Connection with Insulated Busbar & Surge Protection for 11kv AB Cable Scope In the process of drawing HT 11KV AB cable, in between Distribution Transformers has to be charged by the help of Tee off. While charging the Distribution Transformer it has to be noted that the main power cable is not discontinued. In this regard Tee connection with Insulated Bus bar application with suitable Aluminium Busbars, Insulating Heat shrinkable bus bar tubings, Polymeric Insulators for Busbar fixing & Polymeric Surge Arrester for Surge/ Lightning protection are used properly. The service may be taken from the Tee connector with the help of AAC bare/ Insulated conductor to the Distribution Transformer. Technical requisites Busbars Insulation: Insulator: Surge Protection: Suitable Aluminium rectangular Busbars of dimension 1m X 50mm X 6mm with provision for connecting two nos. of Cable end terminations at both ends & tap off point at the centre of the busbar. The Edges of the busbars should be free from any sharp edges/ nicks. The Bus bars should be fully insulated with Heat shrinkable busbar tubings to prevent any bird fault or accidental contact. Suitable polymeric pin type insulators should be used for fixing Busbars on the Pole structure. The housing of the Insulators should be made up of polymeric materials preferably Track resistant EVA materials & should conform the following properties: Mechanical Properties [kN] Specified Cantilever Load 12.5 Maximum Design Cantilever Load 5.5 Specified Tension Load 25 Routine Test Load 12.5 Electrical Properties [kV] AC Wet Withstand Voltage 61 AC Dry Withstand Voltage 95 AC Wet Flashover Voltage 72 AC Dry Flashover Voltage 104 Impulse Withstand Voltage 137 A metal oxide surge arrester with a housing made of polymeric material preferably Silicone rubber, without air voids neither between the housing and the metal-oxide resistors nor the housing itself. Arresters must have directly moulded housings. The arresters should be tested as per IEC 60099-4 & conform to the following criteria: Rated Voltage : 9KV Nominal Discharge Current : 5KA Distribution Class Creepage length : >300mm. Impulse Voltage 1.2/ 50µsec : 95KV Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 269 Technical specification Power frequency withstand voltage : 38KV Voltage Ratings: Nominal system voltage (kV) : 6.6KV(UE)/11KV (E) (phase to phase) Maximum system voltage (kV): 6.6KV(UE)/11KV (E) (phase to phase) Maximum performance : For 11KV (E) QUALITY ASSURANCE The manufacturer shall be certified in accordance with ISO 9001. The supplier has to provide a copy of a valid certificate along with his quote. Relevant Manuals or Drawings shall be presented upon request to customer/utility. PACKING AND SHIPMENT Tee Jointing Kits shall be securely packed, complete with all accessories, in strong non-returnable boxes, in such a manner as to prevent damage during shipment. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 270 Technical specification Specification of Straight Through Joint for 11kv AB Cable Scope Technical requisites Conductor Connection: Void filling & Stress Control: Insulation Build up & Insulation screen: Screen Continuity: Environmental sealing Voltage Ratings: testing Standards: In the process of drawing HT 11Kv AB cable, at the end of one drum of cable, to continue the drawing of the cable the cable from other drum has to be joined by Midspan Inline Straight through joints. In this regard, Straight through joint should be supplied with suitable Mechanical Connector, proper Stress Control, adequate Insulation, suitable screen continuity & sufficient environmental sealing should be achieved. Suitable Shear bolt type Al. Mechanical Connector has to be used. Suitable void filling Mastic & Heat shrinkable Stress control tube. By Heat shrinkable dual wall tube with extruded Insulation & semiconducting layers. With the help of Copper wire mesh.. Outer sealing should be with the help of Heat Shrinkable outer tube & with Proper sealing mastics. Nominal system voltage (kV) : 6.6KV(UE)/11KV (E) (phase to phase) Maximum system voltage (kV): 6.6KV(UE)/11KV (E) (phase to phase) Maximum performance : For 11KV (E) The Straight Through Joint should conform/ withstood the following test std.Tests Recommended Test values AC High voltage Load cycling 900C + 50C (no. of cycles) Load cycling 900C + 50C (no. of cycles) under 0.25 mtr. of water Impulse voltage Partial discharge voltage Thermal short circuit DC voltage 28.5KV (rms) 18 Cycles 12 Cycles 95KV (peak) At 12.75KV < 5 pc For 1 sec. KA will depend on conductor size. 38KV for 15 mins. QUALITY ASSURANCE The manufacturer shall be certified in accordance with ISO 9001. The supplier has to provide a copy of a valid certificate along with his quote. Relevant Manuals or Drawings shall be presented upon request to customer/utility. PACKING AND SHIPMENT Straight through Jointing Kits shall be securely packed, complete with all accessories, in strong non-returnable boxes, in such a manner as to prevent damage during shipment. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 271 Technical specification Specification of Outdoor End Termination for 11kv AB Cable Scope Technical requisites Conductor Connection: Void filling Stress Control, Environmental Sealing & Anti tracking Earthing Connection Continuity: Voltage Ratings: testing Standards: In the process of drawing HT 11Kv AB cable, at the end of the cabling system the cable has to be connected with the Transformer end or with the bare overhead line by Outdoor end terminations. In this regard, Outdoor end terminations should be supplied with suitable Crimping type lugs, proper Stress Control, adequate Insulation & sufficient environmental sealing should be achieved. Suitable Crimping type Al. lugs has to be used. Suitable void filling Mastic. By Heat shrinkable dual wall single tube has to be used for both stress controlling & Environmental sealing purpose. Minimum (one) no. of Heat shrinkable Rain shed can be used for increasing Creepage distance. With the help of Tinned Copper braid. Nominal system voltage (kV) : 6.6KV(UE)/11KV (E) (phase to phase) Maximum system voltage (kV): 6.6KV(UE)/11KV (E) (phase to phase) Maximum performance : For 11KV (E) The Outdoor End Termination should conform/ withstood the following test std.Tests Recommended Test values AC High voltage Load cycling 900C + 50C (no. of cycles) Load cycling 900C + 50C (no. of cycles) under 0.25 mtr. of water Impulse voltage Partial discharge voltage Thermal short circuit DC voltage 28.5KV (rms) 18 Cycles 12 Cycles 95KV (peak) At 12.75KV < 5 pc For 1 sec. KA will depend on conductor size. 38KV for 15 mins. QUALITY ASSURANCE The manufacturer shall be certified in accordance with ISO 9001. The supplier has to provide a copy of a valid certificate along with his quote. Relevant Manuals or Drawings shall be presented upon request to customer/utility. PACKING AND SHIPMENT Outdoor End Termination Kits shall be securely packed, complete with all accessories, in strong non-returnable boxes, in such a manner as to prevent damage during shipment. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 272 Technical specification Specification of C Wedge Boltless connectors Scope Technical requisites The C-Type fired wedge boltless connectors shall be of high strength and high conductivity Aluminium alloy. The same shall be suitable for use on all combinations of Aluminium to Aluminium, or Aluminium to Copper conductors. The components shall be properly proportioned to minimize stress concentration, corrosion and deterioration by galvanic action & should be used for taking tap off in AB Cable from Bare overhead line. Bolted connectors should be avoided. “C” TYPE FIRED WEDGE BOLT LESS CONNECTOR: The connector consists of tapered ―C‖ shaped member and wedge that made of Aluminium alloy. The connector should be bolt less and Fired wedge system. The ―C‖ member should be provided built-in spring tension to maintain constant pressure for a firm electrical contact. The connector shall be used for multiple combinations of solid/stranded AAC, AAAC, ACSR, copper combination etc. Copper to Copper connectors the ―C‖ member is composed of Aluminum Bronze alloy and the wedge of Copper alloy very close to pure copper. ―C‖ member wedge shall be factory coated with an inhibitor containing abrasive particles to help clean and contact surfaces during installation. The C-Type fired wedge boltless connectors shall conform to the latest editions of ANSI C 119.4 - 2004 Standards. The wedge type boltless connectors shall consists of CMember and wedge. The wedge shall be inserted at a speed of 40 m./Sec approx so as to be effective in abrading all sliding surface and disrupting surface oxide film to generate large number of contact spot in the electrical interfaces. The mechanical stresses during the wedge insertion shall cause elastic deformation of the C-Clamp and shall increase the geometrical conformation of the clamp to the conductor. An Oxidation inhibitor shall be applied to the surface thereby elimination of oxidation of metallic surface. The normal current carrying capacity of clamp shall not be less than the specified in the specification. If the connectors are to be installed by Powder actuated tool using cartridges with explosive, valid explosive license issued by the Government of India/State Government should be possessed. Clamps shall be corona free and shall carry an overload of at least 20% over the rated current. The connectors should be easily removable and reusable type. Reusable means that the connector may be removed from service and installed again. Prior to reuse, any instructions to be followed for reconditioning the reusable connector shall be furnished. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 273 Technical specification QUALITY ASSURANCE The manufacturer shall be certified in accordance with ISO 9001. The supplier has to provide a copy of a valid certificate along with his quote. Relevant Manuals or Drawings shall be presented upon request to customer/utility. PACKING AND SHIPMENT Outdoor End Termination Kits shall be securely packed, complete with all accessories, in strong non-returnable boxes, in such a manner as to prevent damage during shipment. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 274 Technical specification Anchoring Clamp for Bare messenger: The clamps should be designed to anchor HT-AB Cable with Bare neutral messenger. The clamp should consists of an Aluminium alloy corrosion resistant casted body and 3 U bolts which shall anchor/hold the neutral messenger without damaging the conductor strands. The clamp should be installed properly. No losable part in the process of clamping arrangement. The clamp should conform to the standard IS 2629 & 2633. The clamp body should be made of Galvanised Steel to the standard IS 2629 & 2633 & wedges should be made of corrosion resistant Aluminium alloy as per IS 617- 1975. Clamps should be fixed with pole by Eye hooks. Ultimate Tensile Strength of the clamp should not be less than 20 KN. Maximum Allowable load of the clamp should not be less than 20 KN. Design as per furnished drawing. Suspension clamp for Bare neutral messenger: The clamps should be designed to hang HT-AB Cables with bare neutral messengers. The neutral messengers should be fixed by an adjustable grip device with 2 U bolts. The clamp should be installed properly. No losable part in the process of clamping arrangement. The clamp should conform to the standard IS 2629 & 2633 & REC Constr. Standard E-34. The clamp body should be made of Galvanised Steel to the standard IS 2629 & 2633 & wedges should be made of corrosion resistant Aluminium alloy as per IS 617- 1975. Clamps should be fixed with pole by Eye hook. Ultimate Tensile Strength of the clamp should not be less than 20 KN. Maximum Allowable load of the clamp should not be less than 20 KN. The clamp should sustain to maximum angle of deviation of 60 degrees of the conductors. Design as per furnished drawing. Eye Hooks: Eye hooks should be designed as to hold Suspension Clamps and Dead end Clamps on the poles: Eye hooks should be made of forged Galvanised Steel. The clamps should be corrosion resistance & should confirm to the standard IS: 2629 and IS: 2633 Bolt and nuts should be made of hot dip galvanised steel, according to VDE 0210 and VDE 0212. Ultimate Tensile Strength (UTS) of the clamp should be 15 KN. Design as per furnished drawing. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 275 Technical specification Pole Clamps: Pole Clamps should be designed as to hold Eye hooks by two nut bolts on the poles: Pole Clamps should be made of forged Galvanised Steel. The clamps should be corrosion resistance & should confirm to the standard IS: 2629 and IS: 2633 Bolt and nuts should be made of hot dip galvanised steel, according to VDE 0210 and VDE 0212. It can be fabricated from 50 x 6 mm GI flat. Design as per furnished drawing. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 276 Technical specification Technical Data schedule: A. GUARANTEED TECHNICAL PARTICULARS FOR SUSPENSION CLAMP FOR BARE MESSENGER WIRE Sl.No Description 1. 2. 3. 4. 5. 6. Name & address of the Manufacturer Applicable standard Type of Clamp Type of design Voltage Grade (kV) Loop anchor attachment (open/close) Installation (with/without disassembly) Type & grade (metallic / non-metallic material) Type of hot dip galvanizing & thickness of Zinc coating Marking Colour of non-metallic parts Dimensions Approximate weight Ultimate tensile strength (KN) Maximum allowable load (KN) Max. angle of deviation of conductor (degrees) 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. Guaranteed particulars Authorised Signatory Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 277 Technical specification B. GUARANTEED TECHNICAL PARTICULARS FOR DEAD END CLAMP FOR BARE MESSENGER WIRE 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. Name & address of the Manufacturer Applicable standard Type of Clamp Type of design Voltage Grade (Kv) Loop anchor attachment (open/close) Installation (with/without disassembly) Type & grade (metallic / nonmetallic material) Type of hot dip galvanizing & thickness of Zinc coating Marking Colour of non-metallic parts Dimensions Approximate weight Ultimate tensile strength (KN) Maximum allowable load (KN) Authorised Signatory Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 278 Technical specification 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. C. GUARANTEED TECHNICAL PARTICULARS FOR END TERMINATION KIT Name & address of the Manufacturer Applicable standard Type of Cable jointing kit Application Nominal system voltage (kV) Maximum system voltage (kV) Number of main core Number of branch conductor Whether single tube is used for Stress control & anti-tracking Type of insulation Type of screening System neutral earthing Maximum performance AC voltage Load cycling 900C + 50C (no. of cycles) Load cycling 900C + 50C (no. of cycles) under 0.25 mtr. of water Impulse voltage Partial discharge voltage Thermal short circuit DC voltage Dynamic short circuit Authorised Signatory Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 279 Technical specification D. GUARANTEED TECHNICAL PARTICULARS FOR STRAIGHT JOINT FOR HT 11KV (E) Name & address of the Manufacturer 2. Applicable standard 3. Type of Cable jointing kit 4. Application 5. Nominal system voltage (kV) 6. Maximum system voltage (kV) 7. Number of cores 8. Type of insulation 9. Type of screening 10. System Neutral Earthing 11. Maximum performance 12. AC voltage 13. Load cycling 900C + 50C (no. of cycles) 14. Load cycling 900C + 50C (no. of cycles) under 0.25 mtr. of water 15. Impulse voltage 16. Partial discharge voltage 17. Thermal short circuit 18. DC voltage 19. Dynamic short circuit 1. Authorised Signatory Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 280 Technical specification 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. E. GUARANTEED TECHNICAL PARTICULARS FOR TEE CONNECTION WITH SURGE PROTECTION Name & address of the Manufacturer Applicable standard Application Nominal system voltage (kV) Maximum system voltage (kV) Number of main core Number of branch conductor Type of Busbar Type of insulation Type of Insulators Cantilever Load of Insulator Max. Design Cantilever load of Insulator Creepage Length of Insulator Specified Tension Load of Insulator AC Wet withstand voltage of Insulator AC Dry withstand voltage of Insulator AC Wet Flashover voltage of Insulator AC Dry Flashover voltage of Insulator Impulse withstand voltage of Insulator Type of Surge arresters Rated voltage of SA Nominal Discharge Current of SA Distribution Class of SA Creepage Length of SA Impulse Voltage of SA Power frequency withstand Voltage of SA Authorised Signatory Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 281 Technical specification 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. F. GUARANTEED TECHNICAL PARTICULARS FOR EYE HOOK Name & address of the Manufacturer Applicable standard Type of Clamp Type of design Type & grade (metallic / nonmetallic material) Type of hot dip galvanizing & thickness of Zinc coating Marking Colour of non-metallic parts Dimensions Approximate weight Ultimate tensile strength (KN) Authorised Signatory Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 282 Technical specification G. GUARANTEED TECHNICAL PARTICULARS FOR C FIRE WEDGE CLAMP No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Feature/Technical Details Manufacturer‘s Name Manufacturer‘s Location Brand Name Part Number Application Installation and Application Tooling Connector Removal Installation on Energized Lines Conductor Size Connector, Metallic Material Connector, Non-Metallic Material Voltage/Ampacity Operating Temperature Marking Industry Standards Overall Size Authorised Signatory Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 283 Technical specification TECHNICAL SPECIFICATION OF 3-Ф Distribution Transformers of 11kV/433-250V, 16, 25, 63, 100 and 200KVA SCOPE 1.1 This section of the specifications is intended to cover requirements for design, engineering, manufacture, testing/inspection at manufacturer‘ works before despatch, forwarding, packing, transporting and delivery at site of outdoor type naturally air-cooled, 11kV/433-350V Distribution Transformers of capacities 16, 25, 63, 100 and 200 KVA complete with all accessories/fittings, LV side protection and spare parts. The bidder shall quote the price of transformer complete with first filling of oil. 2.0 2.1 BIDDING Each Technical Proposal must be accompanied by each of the following information/ documents with sufficient details along with other documents and information mentioned elsewhere to enable the purchaser to make an appraisal of the quality and suitability of the material and equipment offered. (a) Type test certificates of equipment of similar design from a nationally recognised laboratory, preferably at CPRI/ERDA laboratory. The Type test certificates should not be more than 3 (three) years old. The type rest certificates should also be accompanied by the drawings of equipment tested so that the test certificates can be directly linked to the equipments offered. In this regard following points shall also be noted: Equipment which has never been tested for critical performance shall not be accepted. In such cases, a promise or agreement by a bidder to have the equipment tested after award of a contract is not acceptable. (b) (c) (d) Test reports to be acceptable must be related directly to the equipment offered. Test reports for a higher class/rating of equipment are acceptable with a commitment from bidder that the type test will be performed free of charge on the particular equipment after the award of contract. Guaranteed and Other Particulars in the formats given in Schedule - A at the end of this Section. The bid should also be accompanied by manufacturer‘s literatures and brochures. The bidder shall have to submit the Annexure-A as a first page of the technical offer. 2.2 Failure to meet the requirement of this Clause 2.0 shall render a Bid nonresponsive. 3.0 3.1 STANDARDS The Transformer and associated accessories shall conform to the latest issues of the standards as given below, except to the extent explicitly modified in this specification. (1) CBIP manual on Transformers. Publication no 275 (2) CEA Guidelines for Specification of Energy Efficient Outdoor Type three phase and single phase Distribution Transformers, 2008. (3) Power Transformers IS:2026, IEC 76 (4) Outdoor distribution Transformer up to and including 100 kVAIS: 1180 (5) Insulating oils for transformers and switchgears IS:335 (6) Bushings for alternating voltages above 1000 V IS:2099 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 284 Technical specification (7) (8) (9) (10) (11) (12) (13) (14) 3.2 4.0 4.1 Creepage distance (mm) IS: 3347 Outdoor Bushings IS:3347, DIN 42531 to 33 Specification for low voltage bushings IS:7421 Dimensions for clamping arrangements for bushings IS:4257 Specification for Al Wire rods IS: 5434, ASTM B-233 Specification for Insulating Kraft Paper IS:9335, IEC 554 Specification for Insulating Press Board IS:1576, IEC 641 Code of practice for installation and maintenance IS:10028 of transformers (15) Guide for loading of oil immersed transformers IS:6600 (16) Paper covered Aluminium conductor IS:6162 (17) Rectangular Electrical conductor for electrical machine IS:6160 (18) Electrical Power connector IS: 5561 (19) Colours for ready mix paints. IS: 5 (20) Ready mixed paint, brushing zinc chromate, priming IS 104 (21) Specification for Copper wire rod IS 12444, ASTM B-49 (22) Testing for steel sheets and strips and magnetic circuits IS-649 In case equipment conforms to other international standard which ensure equivalent or better performance than that specified under Clause 3.1, then relevant Standards shall be forwarded with the bid. GENERAL SERVICE CONDITION The climatic conditions at site under which the equipment shall operate satisfactorily are as follows:(a) Maximum temperature of air in shade 50º C (b) Minimum temperature of air in shade: (c) 400C (d) 320C (e) (f) 150 (g) 45 (h) 25 Maximum average daily ambient air temperature - 2º C Maximum yearly weighted average ambient temperature Maximum Humidity: Average of rainy days per annum: 100% Average number of days of thunderstorm per annum: Average number of days of dust storm per annum: (i)Average annual rainfall: (j) Number of months of tropical monsoon per annum: (k) Maximum wind pressure: (l) Altitude (above mean sea level): 5.0 5.1 5.2 2280 mm 5 (May to Sept) 195Kg/m2 200 to 1000 m GENERAL TECHNICAL SPECIFICATION The Distribution transformer shall be 3-phase; oil immersed and shall have wound/core type construction, and should be suitable for outdoor service in hot and humid tropical climate. The transformers and all its accessories shall be designed to withstand without injury, the thermal and mechanical effects of any external short circuit Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 285 Technical specification 5.3 5.4 5.5 5.6 5.7 5.8 5.9 5.10 5.11 5.12 5.13 6.0 6.1 6.2 to earth and of short circuits at the terminals of any winding of values and duration specified in IS-2026. Transformer shall be capable of withstanding thermal and mechanical stress caused by symmetrical or asymmetrical faults on any winding. The calculation for the same to be submitted along with the offer The transformer shall be capable of being loaded in accordance with IS: 6600. There shall be no limitation imposed by bushings etc. The transformer shall be suitable for continuous operation with frequency variation of ±5% from normal 50Hz.Combined voltage and frequency variation should not exceed the rated V/f ratio by 10%. Transformer shall accept, without injurious heating, combined voltage and frequency fluctuation, which produces the following over fluxing conditions: i) 125% for 1 minute or 140% for 5 seconds ii) Over fluxing withstand characteristics up to 140% shall be submitted along with the bid. The thermal ability to withstand short circuit shall be demonstrated by calculation. The maximum flux density in any part of the core and yokes, at normal voltage and frequency of transformer shall be such that the flux density under over voltage condition as per Clause 5.5 above shall not exceed 1.9 Tesla. The detail calculation is to be shown as per Annexure-I. The maximum magnetising current at 110% rated voltage shall not be more than 125% of that at 100% rated voltage. Accordingly, the operating flux density for design should be carefully chosen within the stipulated value to achieve the above requirement. The Bidder shall quote the practical achievable no load current at different percentages of rated voltage as per Guaranteed Technical Particulars which will be verified during no load test. The maximum current density in any winding shall not exceed 1.50A/sq.mm (Aluminium). The sources of prime materials, place of manufacture, testing and inspection should be shown as per the proforma enclosed in Annexure – VI. SUPPRESSION OF HARMONICS The transformers shall be designed with particular attention to the suppression of harmonic voltage, especially the third and fifth, so as to eliminate wave form distortion. CENTRE OF GRAVITY The center of gravity of the assembled transformers shall be low and as near to the vertical center line as possible. The transformer shall be stable with or without oil. If the center of gravity is eccentric relating to track either with or without oil, its location shall be shown on the outline drawing. GENERAL CONSTRUCTIONAL FEATURES GENERAL All material used shall be of best quality and of the class most suitable for working under the conditions specified and shall withstand the variations of temperature and atmospheric conditions without distortion or deterioration or the setting up of undue stresses in any part and also without effecting the strength and suitability of the various parts for the work which they have to perform. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 286 Technical specification 6.3 6.4 6.5 6.6 6.7 6.8 6.9 6.10 6.11 6.12 7.0 7.1 7.1.1 7.1.2 7.2 7.2.1 7.2.2 7.2.3 7.3 7.3.1 7.4 7.4.1 Similar parts, particularly removable ones, shall be interchangeable. Pipes, screws, studs, nuts and bolts used for external connections shall be as per the relevant standards. Steel bolts and nuts exposed to atmosphere shall be galvanized. Nuts, bolts and pins used inside the transformers shall be provided with lock washers or locknuts. Exposed parts shall not have any pockets where water can collect. Internal design of transformer shall ensure that air/gas is not trapped in any location. Material in contact with oil shall be such as not to contribute to the formation of acid in oil. Surface in contact with oil shall not be galvanized or cadmium plated. Labels, indelibly marked, shall be provided for all identifiable accessories. All label plates shall be of non corrodible material. All internal connections and fastenings shall be capable of operating under overloads and over-excitation, allowed as per specified standards without injury. Transformer and accessories shall be designed to facilitate proper operation, inspection, maintenance and repairs. No patching, plugging, shimming or other such means of overcoming defects; discrepancies or errors will be accepted. SURFACE PREPARATION & PAINTING GENERAL All paints, when applied in a normal full coat, shall be free from runs, sags, wrinkles, patchiness, brush marks or other defects. All primers shall be well marked into the surface, particularly in areas where painting is evident and the first priming coat shall be applied as soon as possible after cleaning. The paint shall be applied by airless spray according to manufacturer‘s recommendations. However, where ever airless spray is not possible, conventional spray be used with prior approval of purchaser. CLEANING AND SURFACE PREPARATION: After all machining, forming and welding has been completed, all steel work surfaces shall be thoroughly cleaned of rust, scale, welding slag or spatter and other contamination prior to any painting. Steel surfaces shall be prepared by shot blast cleaning (IS:9954) to grade Sq.2.5 of ISO 8501-1 or chemical cleaning including phosphating of the appropriate quality (IS :3618) Chipping, scraping and steel wire brushing using manual or power driven tools cannot remove firmly adherent mill-scale. These methods shall only be used where blast cleaning is impractical. Manufacturer to clearly explain such areas in his technical offer. PROTECTIVE COATING As soon as all items have been cleaned and within four hours of subsequent drying, they shall be given suitable anti-corrosion protection. PAINT MATERIAL Following are the types of paint which may be suitably used for the items to be painted at shop and supply of matching paint to site: Heat resistant paint (Hot oil proof) for inside surface. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 287 Technical specification 7.4.2 For external surfaces one coat of thermo setting powder paint or one coat of epoxy primer followed by two coats of polyurethane paint. These paints can be either air drying or stoving. 7.5 PAINTING PROCEDURE : 7.5.1 All prepared steel surfaces should be primed before visible re-rusting occurs or within 4 hours, whichever is sooner. Chemical treated steel surfaces shall be primed as soon as the surface is dry and while the steel surface is still warm. 7.5.2 Where the quality of film is impaired by excess film thickness (wrinkling, mud cracking or general softness) the supplier shall remove the unsatisfactory paint coating and apply another coating. As a general rule, dry film thickness should not exceed the specified minimum dry film thickness by more than 25%. 7.6 DAMAGED PAINTWORK : 7.6.1 Any damage occurring to any part of a painting scheme shall be made good to the same standard of corrosion protection and appearance as that was originally applied. 7.6.2 Any damaged paint work shall be made good as follows: 7.6.2.1 The damaged area, together with an area extending 25 mm around its boundary, shall be cleaned down to bare metal. 7.6.2.2 A priming coat shall be immediately applied, followed by a full paint finish equal to that originally applied and extending 50 mm around the perimeter of the original damage. 7.6.2.3 The repainted surface shall present a smooth surface. This shall be obtained by carefully chamfering the paint edges before and after priming. 7.7 DRY FILM THICKNESS : 7.7.1 The maximum extent practicable the coats shall be applied as a continuous film of uniform thickness and free of pores. Overspray, skips, runs, sags and drips should be avoided. The different coats may or may not be the same colour. 7.7.2 Each coat of paint shall be allowed to harden before the next is applied as per manufacturer‘s recommendations. 7.7.3 Particular attention must be paid to full film thickness at the edges. 7.7.4 The requirements for the dry film thickness (DFT) of paint and the materials to be used shall be as given below: Sl.No Paint type Area to painted 1. inside outside 01 01 of Total dry thickness (microns) 30 60 outside outside inside 01 02 01 30 25 each 35/10 2. Thermo setting powder paint Liquid Paint a) Epoxy (primer) b) P.U.Paint (Finish coat) c) Hot oil paint/Varnish be No. coats film (min) 7.8 TESTS FOR PAINTED SURFACE: 7.8.1 The painted surface shall be tested for paint thickness. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 288 Technical specification 7.8.2 The painted surface shall pass the cross hatch adhesion test and impact test as acceptance tests and Salt spray test and Hardness test as type test as per the relevant ASTM standards. Note: The paint work done shall be guaranteed for a minimum period of 5 years from the date of receipt of the equipment. 8.0 TRANSFORMER TANK 8.1 The Transformer tank and cover shall be fabricated from high-grade low carbon plate steel of tested quality. The transformer tank shall be of robust construction rectangular/octagonal/round/elliptical in shape. The sheet thickness of 3.15 mm for the bottom and top and not less than 2.5 mm sides upto and including 25 KVA, 5.0 mm and 3.15 mm respectively for transformers of more than 25 kVA and upto and including 100 KVA, above 100KVA it should be 6.0mm and 4.0 mm. Tolerances as per IS: 1852 shall be applicable. 8.2 Transformers upto 100 kVA, there shall be no joints at corners and there shall not be more than 2 joints in total. 8.3 The tank plate and lifting lugs shall be of such strength that the complete transformer filled with oil may be lifted by means of lifting shackle. 8.4 All beams, flanges, lifting lugs, braces and permanent parts attached to the tank, shall be welded and where practicable, they shall be double welded. 8.5 The main tank body of the transformer without oil, shall be capable of withstanding pressure of 225 mm of Hg. Permanent deflection, when subjected to vacuum, shall not be more than the values as given below: please check with 8.6 (All figures in mm) Horizontal length of flat plate Permanent deflection Up to and including 750 5.0 751 to 1250 6.5 1251 to 1750 8.0 1751 to 2000 9.5 2001 to 2250 11.0 2251 to 2500 12.0 2501 to 3000 16.0 Above 3000 19.0 8.6 8.7 8.8 The tank shall further be capable of withstanding a pressure of 0.8 kg/sq.cm (g) and a vacuum of 0.7 kg/sq.cm (g) without any deformation. All bolted connections to the tank shall be fitted with suitable oil-tight gaskets, which shall give satisfactory service under the operating conditions and guaranteed temperature rise conditions. Special attention shall be given to the methods of making the hot oil-tight joints between the tank and the cover as also between the tank cover and the bushings and all outlets to ensure that the joint can be remade satisfactorily at site and with ease, with the help of semi-skilled labour. Where compressible gaskets are used, stops shall be provided to prevent over-compression. The top cover gaskets should not be exposed to atmosphere. Suitable guides shall be provided for positioning the various parts during assembly or dismantling. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 289 Technical specification 8.9 9.0 9.1 9.2 9.3 9.4 9.5 9.6 9.7 9.8 9.9 9.10 10.0 10.1 10.2 10.3 10.4 10.5 10.6 10.7 Tank stiffeners shall be provided for general rigidity and these shall be designed to prevent retention of water. CORRUGATED TANK Corrugated tank may be offered for 63 and 100 kVA. The transformer tank shall be of robust construction corrugation in shape and shall be built up of CRCA sheets of 1.2 mm thick. The internal clearance of tank shall be such that, it shall facilitate easy lifting of core with coils from the tank, with CCA (core-coil assembly), HV & LV bushings mounted on top cover. All joints of tank and fittings shall be oil tight and no bulging should occur during service. The tank design shall be such that the core and windings can be lifted freely. The tank plate shall be such strength that the complete transformer when filled with oil may be lifted bodily by means of lifting lugs. Inside of the tank shall be painted with hot oil resistant paint. Corrugation panel shall be used for cooling. The transformer shall be capable of giving continuous rated output without exceeding the specified temperature rise. 2 Nos. welded heavy duty lifting lugs of MS plate 8 mm thick (min) suitably reinforced are to be provided. Top cover fixing bolts of galvanized iron and 6 mm Neoprene bonded cork gaskets conforming to IS 4253 Part-II shall be placed between tank and cover. The bolts outside tank shall have 2 flat washers and one spring washer. Tanks with corrugations shall be tested for leakage test at a pressure of 0.25kg/cm2 measured at the top of the tank. The transformers with corrugation should be provided with a pallet for transportation, the dimensions of which should be more than the length and width of the transformer tank with corrugations. TANK COVER The transformer top shall be provided with a detachable tank cover with bolted flanged gasket joint. The surface of the cover shall be suitably sloped so that it does not retain rainwater. Each tank cover shall be of adequate strength and shall not distort when lifted. Inspection opening shall be provided as necessary to give easy access to bushing. Each inspection opening shall be of ample size for the purpose for which it is provided, The tank cover and inspection cover shall be provided with suitable lifting arrangements. The tank cover shall be fitted with pockets for thermometer (at the center of the top cover). The thermometer pockets shall be fitted with a captive screw top to prevent the ingress of water. The tank cover is to enclose the flanged gasket. Bushings, covers of inspection openings, etc. shall be designed to prevent ingress of water into or leakage of oil from the tank. HV bushings are to be mounted on the top cover. However, for maintenance purpose, the termination point of HV leads should have easy accessibility. All bolted connection shall be fitted with weather proof, hot oil resistant gasket in between, for complete oil tightness. If gasket is compressible, metallic stoppers shall be provided to prevent over compression. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 290 Technical specification 11.0 Clamping etc of DTR 11.1 The suitable clamping device should be provided for top and bottom of the transformer in case where it will be mounted on pole. The clamping device should suitable for both PSC and Steel Tubular poles. 11.2 For pad mounted transformer, to prevent movement during earthquake, clamping devices shall be provided for fixing transformer to the foundation. The bidders shall supply necessary bolts for embedding of the concrete foundation. The arrangement shall be such that the transformer can be fixed to or unfastened from these bolts as desired. The fixing of the transformers to the foundations shall be so designed to withstand the seismic events to the extent that a static co-efficient of 0.5g, applied to the direction of least resistance to that loading will not cause the transformer or clamping devices as well as bolts to be over stressed. 12.0 CORE (MAGNETIC CIRCUIT) AND CONSTRUCTIONAL FEATURES OF CORE 12.1 The magnetic circuit shall be constructed from high grade cold rolled nonageing grain oriented silicon steel lamination of M4 or better with thickness of less than or equal to 0.27 mm. The material should be coated with hot oil proof insulation. The core shall be stress relieved by annealing under inner atmosphere if required. 12.2 Only primary core material is to be used. The bidder should offer the core for inspection and approval by the purchaser or third party Inspection Agency during the manufacturing stage. Bidder‘s call notice for the purpose should be accompanied with the following document as applicable as a proof towards use of Prime Core material. (a) Invoice of supplier, (b) Mill‘s test certificate. (c) Packing list, (d) Bill of loading, (e) Bill of entry certificate to customs Core material should be directly procured from either the manufacturer or their accredited marketing organisation of repute and not through any agent. It is preferable for the manufacturer to have in house numeric controlled Core cutting facility for better control of quality and also to avoid any mixing of Prime Core material with second‟s materials. Core cutting machine number and drawings are to be furnished. 12.3 The following procedure is to be adopted for those manufacturers who have no in-house core-cutting facility: (1) The bidder should specify the grade, thickness of core material in the offer along with submission of all graphs/ documents, relating to the grade of core material, offered by them. (2) The documents, as mentioned above should be submitted to APDCL along with the following informations: a) Purchase order No. & Date. b) No. of packed coils with package Nos. c) Gross weight. d) Net weight e) Port of loading. f) Port of discharge. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 291 Technical specification g) Grade and thickness of core material. i) Any other information, as mentioned on the body of packed coils. 12.4 12.5 12.6 12.7 12.8 12.9 12.10 12.11 12.12 12.13 12.14 13.0 13.1 13.2 (3) The manufacturer in its offer will mention the names of at least three Subvendors, to whom they intend to assign their core cutting. Such subvendors should have been approved by other Electricity Boards/ Electrical utilities and are accredited by some International recognised certification body like ISO: 9000 etc., to ensure that a minimum quality parameters and tolerances are maintained. The experience, the details of core-cutting facilities, finishing and testing facilities etc., as available with such subvendors should be clearly outlined in the bid. (4) On award of contract, the Transformer Manufacture is to assign the corecutting to such sub-vendor(s) for which approval is to be given by APDCL or its successor companies. The laminations shall be free of all burrs and sharp projections. Each sheet shall have an insulating coating resistant to the action of hot oil. The design of magnetic circuit shall be such as to avoid static discharges, development of short circuit paths within itself or to the earthed clamping structure and production of flux component at right angle to the plane of the lamination which may cause local heating. All steel sections used for supporting the core shall be thoroughly shot or sand blasted, after cutting, drilling and welding. The finally assembled core with all the clamping structures shall be free from deformation and shall not vibrate during operation. The core shall be carefully assembled and rigidly clamped to ensure adequate mechanical strength. The core clamping structure shall be designed to minimize eddy current loss. The framework and clamping arrangements shall be securely earthed. The supporting frame work of the cores shall be so designed as to avoid the presence of pockets which would prevent complete emptying of the tank through the drain valve or cause trapping of air during filling. The oxide/silicate coating given on the core shall be adequate; however, laminations can be insulated by the manufacturers if considered necessary. All parts of the cores shall be of robust design capable of withstanding any shocks to which they may be subjected during lifting, transport, installation and service. Adequate provision shall be made to prevent movement of the core and winding relative to the tank during transport and installation or while in service. No-load current shall not exceed 3% of full load current and will be measured by energizing the transformer at 433 volts, 50Hz frequency. Increase of voltage of 433 volts by 12.5% shall not increase the no-load current by 6% (maximum) of full load current. For AMORPHOS CORE METAL The core shall be high quality amorphous ribbons having very low loss formed into wound cores of rectangular shape, bolted together to the frames firmly to prevent vibration or noise. The complete design of core must ensure permanency of the core loss with continuous working of the transformers. The value of flux density allowed in the design shall be clearly stated in the offer. Curve showing the properties of the metal shall be attached with the offer. The transformer core shall be suitable for over fluxing (due to combined effect of voltage and frequency) up to 12.5% without injurious heating at full load Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 292 Technical specification 13.3 14.0 14.1 14.2 14.3 15.0 15.1 conditions and shall not get saturated. The bidder shall furnish necessary design data in support of this situation. No-load current shall not exceed 2% of full load current and will be measured by energizing the transformer at 433 volts, 50Hz frequency. Increase of voltage of 433 volts by 12.5% shall not increase the no-load current by 5% (maximum) of full load current. INTERNAL EARTHING EARTHING OF CORE CLAMPING STRUCTURE i) All internal metal parts of the transformer, with the exception of individual laminations, core bolts and their individual clamping plates shall be earthed. ii) The top clamping structure shall be connected to the tank by a copper strap. The bottom clamping structure shall be earthed by one or more of the following methods: a) By connection through vertical tie-rods to the top structure. b) By a connection to the top structure on the same side of the core as the main earth connection to the tank. EARTHING OF MAGNETIC CIRCUIT i) The magnetic circuit shall be connected to the clamping structure at one point only SIZE OF EARTHING CONNECTIONS Earthing strip should be tin copper and size will be approved by the purchaser after getting suppliers offer. WINDING GENERAL i) The current density of Aluminium in any part of the windings shall not exceed 1.50 Amps/Sq. mm. ii) All windings shall be made of electrolytic high conductivity Aluminum for transformer of capacity up to 200 KVA and shaped and braced to provide for expansion and contraction due to temperature changes. Winding shall be fully insulated as defined in IS: 2026. All neutral points shall be insulated for the voltage specified in IS: 2026. The winding shall be so designed that all coil assemblies of identical voltage, rating shall be interchangeable. iii) Number of HV coils per phase should not be less than four (4) for 63, 100 & 200 kVA and single HV coil for 16 & 25 kVA with the type Crossover/Sectional. Number of secondary (LV) coil should be one with spiral type winding construction. iv) LV winding shall be such that neutral formation will be at top. v) Conductor covering for HV winding conductor should be DPC with minimum 0.35 mm thickness and for LV conductor DPC with minimum 0.40 mm thickness. vi) Interlayer insulation shall be Nomex/Epoxy dotted Kraft Paper. vii) Distribution Transformers shall be designed to withstand the impulse and power frequency test voltages as per IS: 2026. viii) Magnitude of impulse surges transferred from HV to LV windings by induction and capacitance coupling shall be limited to B.I.L. of LV winding ix) The completed core and coil assembly shall be dried in vacuum at not more than 0.5mm of mercury absolute pressure and shall be Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 293 Technical specification immediately impregnated with oil after the drying process to ensure the elimination of air and moisture within the insulation. Vacuum may be applied in either vacuum over or in the transformer tank x) Winding shall be subjected to a shrinking and seasoning process, so that no further shrinkage occurs during service. Adjustable devices shall be provided for taking up possible shrinkage in service. xi) Winding shall not contain sharp bends which might damage the insulation or produce high dielectric stresses. No strip conductor wound on edge shall have width exceeding six times the thickness. xii) Varnish application on coil windings may be given only for mechanical protection and not for improvement in dielectric properties. In no case varnish or other adhesive be used which will seal the coil and prevent evacuation of air and moisture and impregnation by oil. xiii) The insulation of transformer windings and connection shall be free from insulating composition liable to soften, ooze out ,shrink or collapse during service and be non catalytic and chemically inactive in transformer oil. xiv) The coil clamping arrangement and the finished dimensions of any oil ducts shall be such as will not impede the free circulation of oil through the ducts. xv) Terminals of all windings shall be brought out of the tank through bushings for external connections xvi) The winding shall be so designed that all coil assemblies of identical voltage ratings shall be interchangeable and field repairs to the winding can be made readily without special equipment. The coils shall have high dielectric strength xvii) All leads from windings to terminals shall be rigidly supported to prevent injury from vibration. Guide tubes may be used where possible. 15.2 BRACING OF WINDINGS 15.2.1 The windings and connections of all transformers shall be braced to withstand shocks, which may occur during transport or due to switching and other transient conditions during service. i) Coil clamping rings shall be of suitable insulating material. ii) Permanent current carrying joints in the windings and leads shall be welded or brazed. Clamping bolts for current carrying parts inside oil shall be made of oil resistant material which shall not be affected by acidity in the oil steel bolts, if used, shall be suitably treated. iii) Adequate barriers shall be provided between coils and core and between high and low voltage coil. End turns shall have additional protection against abnormal line disturbances. iv) Coil should be clamped by 8 (eight) numbers of 12 mm dia tie rods between top and bottom yoke support channels. 16.0 BOLTS AND NUTS 16.1 Steel bolts and nuts exposed to atmosphere with suitable finishes like cadmium plated or zinc plated passivated will be used for diameter above 6 mm. 16.2 Brass bolts and nuts of less than 6 mm shall not be used for electrical connections. Where smaller size is required, stainless steel or phosphor bronze may be used. Sizes and threads will be as per Indian Standard, wherever, available, otherwise equivalent British Standard will be followed. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 294 Technical specification 16.3 All nuts and bolts and pins shall be locked in position with the exception of those external to the transformer. The bolts shall be fitted in such a manner that in the event of the nut working loose and falling off, the bolts will remain in position. 16.4 All bolts, nuts and washers in contact with non-ferrous parts which carry current and are exposed to atmosphere shall be of phosphor bronze, where transfer of current is through bolts. 16.5 If bolts and nuts are placed that are in accessible by means of ordinary spanners, suitable special spanners shall be provided by the supplier. 17.0 INSULATION MATERIAL: 17.1 Electrical grade insulation epoxy dotted Kraft Paper/Nomex and pressboard of standard make or any other superior material subject to approval of the purchaser shall be used. 17.2 All spacers, axial wedges / runners used in windings shall be made of precompressed Pressboard solid, conforming to type B 3.1 of IEC 641 – 3 – 2 . For cross-over coil winding of HV all spacers shall be properly sheared and dovetail punched to ensure proper locking. All axial wedges / runners shall be properly milled to dovetail shape so that they pass through the designed spacers freely. Insulation shearing, cutting, milling and punching operations shall be carried out in such a way, that there should not be any burr and dimensional variations. 17.3 INSULATING OIL 17.3.1 The insulating oil for the transformers shall be of EHV grade, generally conforming to IS: 335. No inhibitors shall be used in the oil. 17.3.2 The quantity of oil required for the first filling of the transformer and its full specification shall be stated in the bid. The bidder shall quote the price of transformer complete with first filling of oil. 17.3.3 The design and materials used in the construction of the transformer shall be such as to reduce the risk of the development of acidity in the oil. 17.3.4 The supplier shall warrant that oil furnished is in accordance with the following specifications. a) Appearance : The oil shall be clear and transparent and free from suspended matter or sediment o b) Density at 20 C Max: 0.89g/cm3 c) Kinematic Viscosity at 27oC Max: 27 CST d) Interfacial at 27oC Min.: 0.03 N/m e) Flash Point: 140oC o f) Pour Point Max: -6 C g) Neutralisation Value: 0.03 mg/KOH/g (Total Acidity) Max h) Electric Strength: 60 kV (Breakdown Voltage) Min. i) Dielectric dissipation factor: 0.05 tan delta at 90oC Max j) Minimum specific resistance: 1 x 1012 ohm cm (resistivity), at 90oC Min. k) Oxidation Stability i) Neutralisation value after Max: 0.40 mg/KOH/g ii) Total sludge after oxidation max: 0.10% by weight Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 295 Technical specification l) Presence of oxidation Inhibotor: The oil shall not contain anti-oxidant Additives 25 ppm m) Water content Max: 18.0 ACCESSORIES & FITTINGS 18.1 BUSHINGS: 18.1.1 The bushing shall conform to the relevant standards specified and shall be of outdoor type. The bushing rods and nuts shall be made of brass material 12 mm diameter for HT bushings. Both the HV & LV bushings should be mounted on top cover. The tests as per latest IS:2099 and IS:7421 shall be conducted on the transformer bushings. 18.1.2 Bushing can be of porcelain/epoxy material. Polymer insulator bushings conforming with relevant IEC can also be used. LV side bushings shall invariably be either of epoxy material or polymeric type. The bidder is to name at least 2/3 vendors of repute who are presently manufacturing epoxy/polymeric bushings and APDCL will select the vendor from those of offered at the time of detail engineering 18.1.3 For 11 KV, 17.5 kV class bushing and for 0.433 kV, 1.1 kV class bushing shall be used. 18.1.4 Dimensions of the bushings of the voltage class shall conform to the Standards specified and dimension of clamping arrangement shall be as per IS:4257. 18.1.5 Minimum external phase to phase and phase to earth clearances of bushing terminals shall be as follows : Voltage Clearance Phase to phase Phase to earth 11 kV 255 mm 140 mm 0.433 kV 75 mm 40 mm 18.1.6 Brazing of all inter connections, jumpers from winding to bushing shall have cross section larger than the winding conductor. All the Brazes shall be qualified as per ASME, section-IX. 18.2 TERMINAL CONNECTORS : 18.2.1 The HV bushing stems shall be provided with suitable terminal connectors as per IS: 5082 so as to connect the jumper without disturbing the bushing stem. Connectors shall be with eye bolts so as to receive conductor for HV. Terminal connectors shall be type tested as per IS:5561. 18.2.2 Bird guards are to be provided for all HV bushings. 18.2.3 All LV bushing shall be provided with connectors in accordance with IS : 3347 (Part 1 /Section 1 & 2) and the connector shall be universal type suitable for both horizontal and / or vertical take off.. The connector should have the capacity to accommodate connection of at least 1-core 70 sq.mm to 120 sq.mm XLPE cable. 18.2.4 The terminal connectors to be supplied for both H.V. and L.V. side 18.2.5 The type of terminal connector, size of connector, material, and type of installation shall be approved by the APDCL, as per installation requirement while approving the equipment drawings. 18.3 EARTHING TERMINAL: 18.3.1 Two earthing pads (each complete with two nos. (2) tapped holes, M 8 bolts, plain and spring washers) suitable for connection to 25x4 mm galvanised steel Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 296 Technical specification flat shall be provided each at position close to the two (2) diagonally bottom corners of the tank. 19.0 Protection & Measuring Devices A) Conservator Tank i. The conservator tank for 63KVA and above shall have adequate capacity between highest and lowest visible levels to meet the requirement of the expansion of the total cold oil volume in the transformer from minimum ambient temperature to 90°C. The total volume of conservator shall be 10% of total oil in the transformer. ii. It is desirable to create sump in the conservator for which the feed pipe extension of 25mm will be required and the design of feed pipe to transformer tank should be such that the oil from conservator does not fall directly to the core & coil assembly. iii. The conservator should have one oil filling hole of 32 mm size with gasketed cover. One air release plug of 15mm size will be required. iv. The conservator tank shall be bolted into position so that it can be removed for cleaning purposes. v. The conservator tank shall be fitted with prismatic oil level gauge with minimum and maximum marking. vi. The conservator tank shall be provided in a position not to obstruct the electrical connections to the transformers. B) Pressure Relief Device Pressure relief device may be provided at suitable locations which shall be of sufficient size for rapid release of any pressure that may be generated in the tank and which may result in damage to the equipment. The device shall operate at the static pressure of less than the hydraulic test pressure of transformer tank. It shall be mounted directly on the tank. C) Oil Preservation Equipment (i) Oil Sealing Breather The conservator shall be fitted with a dehydrating filter breather. It shall be so designed that, 1) Passage of air is through a dust filter & Silica gel 2) Silica gel is isolated from atmosphere by an oil seal. 3) Moisture absorption indicated by a change in colour of the crystals can be easily observed from a distance. 4) Breather is mounted not more than 1200 mm above rail top level. 5) The breather should have at least 500g of silica gel. 19.1 RADIATORS & VALVES 19.1.1 RADIATORS i) Radiators shall be of press steel having thickness of 1.2 mm Cold Rolled Continuously Annealed (CRCA) sheet and design should be such that all painted surface can be thoroughly cleaned by hand. ii) The inlet header of Radiators should be put below the LV bushings in such a way that in the event of oil leakage from LV bushings, the circulation of oil through radiators are continuing. The arrangement to be demonstrated at the time of detail engineering and will be verified Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 297 Technical specification during stage inspection. Failure of this arrangement will lead to total rejection of offered lot 19.2 VALVES 19.2.1 Each transformer shall be provided with following valves on the tank: a) One fully pilfer proof valve below the top cover. b) One 15 mm air release plug. 20.0 FITTINGS AND ACCESORIES 20.1.1 The following fittings shall be provided on each transformer: a) Conservator fitted with oil filling hole and cap. b) Prismatic type oil gauge c) Silica gel breather with oil seal. d) Pressure relief device for main tank. e) Pocket on tank cover (placed at mid position) for thermometers. f) 9 kV, 5 KA lightning arrestors on HT side – 3 No. g) Valve (32mm) shall be of globe type. h) Earthing terminals with lugs- 2 nos. i) Rating and diagram plate, non-detachable. j) Lifting lugs for main tank. k) Top tank clamping l) Terminal connectors on the HV/LV bushing m) Base channel of 75 x 40 mm, 460 mm long with holes to make them suitable for fixing on a platform or plinth. n) 5 year guarantee plate non detachable type 21.0 MISCELLANEOUS i) LIGHTNING ARRESTORS: 9 kV, 5 kA metal oxide lightning arrestors Distribution class type of make CGL/Oblum/Rechem/LAMCO conforming relevant standard, one number per phase shall be provided to be fitted under the HV bushing. The LA should be clamped to HV side bushing with a galvanized earth strip of size 25x4 mm with two nos of M8 size bolt hole along with galvanized nut & bolts and the strip should run near to pole for pole mounted transformer so that the riser from the ground can be connected properly ii) NAME PLATE Transformer rating plate shall contain the information as given in clause 15 of IS-2026 (Part-I). The details on rating plate shall be finalised during the detailed engineering. 22.0 LOSSES 22.1 The bidder shall guarantee the total losses at 50% and 100% load condition (at rated voltage and frequency and at 750C) as per Table – I below. . Table: I Rating Max. Losses at 50% loading Max. Losses at 100% loading (KVA) (Watts) (Watts) at 750C 16 150 480 25 210 695 63 380 1250 100 520 1800 200 890 2700 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 298 Technical specification 22.2 The above losses are maximum allowable and there would not be any “+ve” tolerance. Bids with higher losses than the specified values would be treated as non responsive. 22.3 The bidder shall guarantee individually the no-load loss and load loss (Table: II) without any positive tolerance. Table: II Rating No load in Watts Load losses DAMAGES in Watts (Max) at EXCESSIVE LOSSES CAPITALISATION OFloss LOSSES AND LIQUIDATED FOR 0 (KVA) (Max) 75 C 16 50 400 25 80 520 63 145 940 100 220 1180 200 380 2000 22.4 Transformers with losses less than those specified above will be capitalized during bid evaluation process as per Clause No 22.6 22.5 Since IS: 2026 allows certain tolerances on the transformer losses, the bidders are requested to indicate whether the figures given for guaranteed losses in the schedule of guaranteed technical particulars are with or without such tolerances. If tolerances are applicable, the limits for the same should be indicated. In the absence of any information to this effect, the figures for noload losses and load losses will be increased by 10% as provided in the IS. Any change in the figures assigned for transformer losses will not be permitted after opening of bids and bid evaluation will be carried out on the basis of information made available at the time of bid opening. 22.6 For the purpose of comparison of the different bids, the capitalised cost of each transformer shall be considered. Capitalised cost of the transformer for the purpose of tender evaluation only shall be calculated as given below: Capitalised cost in Rs = IC+328 Wi(g) +181 Wc(g) Where, IC= Quoted price of transformer in Rs Wi(g) = Guaranteed no load loss in Watt Wc(g)= Guaranteed load loss (copper loss) in Watt 22.7 The loss figures (both guaranteed & test) for the purpose of calculation shall be at rated frequency and voltage and at principal tap and 75º C. 22.8 If losses are quoted with tolerance limit, then upper positive value will be considered for capitalization. 22.9 Penalties will be applicable if any one or more test loss figures of no-load loss and total losses exceed the corresponding guaranteed figures. The penalties will be calculated as follows: (a) For No-load loss, Penalty (in rupees) = {Wi (t) – Wi (g)} x 2R1. (b) For load loss, Penalty (in rupees) = {WT (t) – Wi (t) - WI (g)} x 2R2 Where, WT (t) = Total loss (test value) in W. WT (g) = Total loss (guaranteed value) in W. Wi (t) = No-load loss (test value) in W. Wi (g) = No-load loss (guaranteed value) in W. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 299 Technical specification 22.10 22.11 23.0 23.1 23.2 24.0 24.1 25.0 25.1 W1 (g) = Load loss (guaranteed value) in W.( Copper loss ) R1 = Rs.328/R2 = Rs.181/For the purpose of penalty computation, the test figures of the no-load and the total losses of each transformer will be compared with the corresponding guaranteed figures. Calculation of detail losses including flux density and no load current are to be furnished for copper loss, iron loss indicating corresponding copper weight and core weight and considering all parameters and also supported by the drawings showings details of diameter and height of winding and core duly signed by manufacturer‟s design personnel. The loss calculation is to be shown as per proforma in Annexure – II. Temperature rise: The temperature rise over ambient shall not exceed the limit given below: Top oil temperature rise measured by thermometer : 350C Winding temperature rise measured by resistance method : 400C Bids not meeting the above limits of temperature rise will be treated as non-responsive. MCCB BOX MCCB of defined rating and make shall have to be put for LV side protection. The specification of MCCB and the box shall be as per Schedule-C TESTING AND INSPECTION TESTS (i) The Supplier shall carry out a comprehensive inspection and testing programme during manufacture of the transformer. An detail of inspection is given in this specification. The manufacturer will submit a testing and inspection plan at the time of bidding. (ii) The procedure for testing shall be in accordance with IS 1180/2026 as the case may be except for temperature rise test. (iii) The supplier shall carry out all routine tests on each transformers. (iv) Special tests other than type and routine tests, as agreed between purchaser and bidder shall also be carried out as per the relevant standards. (v) Before dispatch each of the completely assembled transformers shall be subjected to the routine tests at the manufacturer‘s works. (vi) The requirements of onsite tests are as listed in these specifications. (vii) Certified test report and oscillograms shall be furnished to the Purchaser for evaluation. The Supplier shall also evaluate the test results and rectify the defects in the equipment based on his and the Purchaser‘s evaluations of the tests without any extra charges to the Purchaser. Manufacturer‘s Test Certificates in respect of all associated auxiliary and ancillary equipment shall be furnished. (viii) The bidder shall state in his proposal the testing facilities available at his works. In case full testing facilities are not available, the bidder shall state the method proposed to be adopted so as to ascertain the transformer characteristics corresponding to full capacity testing. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 300 Technical specification 25.1.1 ROUTINE TESTS: (To be conducted on each transformer) 25.1.1.1 Ratio, polarity, phase sequence and vector group. 25.1.1.2 No Load current and losses at services voltage and normal frequency. 25.1.1.3 Load Losses at rated current and normal frequency. 25.1.1.4 Impedance Voltage test. 25.1.1.5 Resistance of windings at each tap. 25.1.1.6 Insulation Resistance. 25.1.1.7 Induced over voltage withstand test. 25.1.1.8 Separate source voltage withstand test. 25.1.1.9 Neutral current measurement- The value of zero sequence current in the neutral of the star winding shall not be more than 2% of the full load current. 25.1.1.10 Oil samples (one sample per lot) to comply with IS 1866. 25.1.1.11 Measurement of no load losses and magnetizing current at rated frequency and 90%, 100% and 110% rated voltage. 25.1.1.12 Pressure and vacuum test for checking the deflection. 25.1.2 TYPE TESTS TO BE CONDUCTED ON ONE UNIT: 25.1.2.1 Temperature rise test. 25.1.2.2 Impulse voltage test: with chopped wave of IS 2026 Part-III, BIL should be 95 KV peak. 25.1.2.3 Short circuit withstand test: Thermal and dynamic ability. 25.1.2.4 Air Pressure Test: As per IS – 1180. 25.1.2.5 Magnetic Balance Test. 25.1.2.6 Un-balanced current test: The value of unbalanced current indicated by the ammeter shall not be more than 2% of the full load current. 25.1.2.7 Noise level measurement. 25.1.2.8 Measurement of zero-phase sequence impedance. 25.1.2.9 Measurement of Harmonics of no-load current. 25.1.2.10 Transformer tank shall be subjected to specified vacuum. The tank designed for vacuum shall be tested at an internal pressure of 0.35 Kg/cm2 absolute (250 mm of Hg) The permanent deflection of flat plates after the vacuum has been released shall not exceed the value given below: Horizontal length of flat plate Permanent deflection Up to and including 750 5.0 751 to 1250 6.5 1251 to 1750 8.0 1751 to 2000 9.5 2001 to 2250 11.0 2251 to 2500 12.0 2501 to 3000 16.0 Above 3000 19.0 25.1.2.11 25.1.2.12 Pressure relief device test. Short Circuit Test and Impulse Voltage Withstand Tests: In case the transformers proposed for supply against the order are not exactly as per the tested design, the supplier shall be required to carry out the short circuit test and impulse voltage withstand test at their own cost in the presence of the representative of the purchaser. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 301 Technical specification 25.1.2.13 The supply shall be accepted only after such test is done successfully, as it confirms on successful withstand of short circuit and healthiness of the active parts thereafter on un-tanking after a short circuit test. 25.1.2.14 Apart from dynamic ability test, the transformers shall also be required to withstand thermal ability test or thermal withstand ability will have to be established by way of calculations. 25.1.2.15 It may also be noted that the APDCL reserves the right to conduct short circuit test and impulse voltage withstand test in accordance with the IS, afresh on each ordered rating at purchaser cost, even if the transformers of the same rating and similar design are already tested. This test shall be carried out on a transformer to be selected by the purchaser either at the manufacturer‘s works when they are offered in a lot for supply or randomly from the supplies already made to purchaser‘s stores. The findings and conclusions of these tests shall be binding on the supplier. 25.1.2.16 Type test certificates for the tests carried out on prototype of same specifications shall be submitted along with the bid. The purchaser may select the transformer for type tests randomly. 25.1.3 ACCEPTANCE TEST: 25.1.3.1 At least 10% transformers of the offered lot (minimum of one) shall be subjected to the following routine/acceptance in presence of APDCL‘s representative at the place of manufacture before dispatch without any extra charges. The testing shall be carried out in accordance with IS 1180 and IS 2026. 25.1.3.2 Checking of weights, dimensions, fittings and accessories, tank sheet thickness, oil quality, material, finish and workmanship as per GTP and contract drawings. 25.1.3.3 Physical verification of core coil assembly and measurement of flux density of one unit of each rating, in every inspection with reference to short circuit test report. 25.1.3.4 Temperature rise test on one unit of the total offered quantity. 25.1.3.5 At least one transformer of the supplied lot shall be subjected to tests by a third party (preferably ERDA or CPRI) at the purchaser’s cost. In case of Failure in such test, the entire lot will be rejected by APDCL and the cost of the tests will have to be borne by the supplier. 25.2 INSPECTION 25.2.1 Inspection and testing of transformer oil: 25.2.1.1 To ascertain the quality of transformer oil, the original manufacturer‘s test report should be submitted at the time of inspection. Arrangement should also be made for testing of transformer oil, after taking out the sample from manufactured transformers and tested in the presence of APDCL‘s representative. 25.2.2 STAGE INSPECTION: To ensure about the quality of transformers, the inspection shall be carried out by the APDCL‘s representative at following two stages:25.2.2.1 Online anytime during receipt of raw material and manufacture/assembly whenever the APDCL desires. 25.2.2.2 At finished stage i.e. transformers are fully assembled and are ready for dispatch. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 302 Technical specification 25.2.2.3 The stage inspection shall be carried out in accordance with Annexure – IV. 25.2.2.4 After the main raw-material i.e core and coil material and tanks are arranged and transformers are taken for production on shop floor and a few assembly had been completed, the firm shall intimate the APDCL in this regard, so that an officer for carrying out such inspection could be deputed, as far as possible within seven (7) days from the date of intimation. During the stage inspection a few assembled core shall be dismantled to ensure that the CRGO laminations used are of good quality. Further, as and when the transformers are ready for dispatch, an offer about the readiness of transformers, for final inspection for carrying out tests as per relevant IS shall be sent by the firm along with Routine Test Certificates. The inspection shall normally be arranged by the APDCL at the earliest after receipt of offer for pre-delivery inspection. The proforma for pre delivery inspection of Distribution Transformers is placed at Annexure – V. 25.2.2.5 In case of any defect/defective workmanship observed at any stage by the APDCL‘s Inspecting Officer, the same shall be pointed out to the firm in writing for taking remedial measures. Further processing should only be done after clearance from the Inspecting Officer/APDCL. 25.2.2.6 All tests and inspection shall be carried out at the place of manufacture unless otherwise specifically agreed upon by the manufacturer and APDCL at the time of purchase. The manufacturer shall offer the Inspector representing the APDCL all reasonable facilities, without charges, to satisfy him that the material is being supplied in accordance with this specifications. This will include Stage Inspection during manufacturing stage as well as active part inspection during Acceptance Tests. 25.2.2.7 APDCL shall have every right to appoint a third party inspection to carry out the inspection process. 25.2.2.8 The APDCL has the right to have the test carried out at his own cost by an independent agency wherever there is a dispute regarding the quality supplied. APDCL has right to test 1% of the supply selected either from the stores or field to check the quality of the product. In case of any deviation APDCL has every right to reject the entire lot or penalize the manufacturer, which may lead to blacklisting, among other things. 25.2.2.9 Test Reports for bought out items: The supplier shall submit the test reports for all bought out/sub contracted items for approval. Bushings, connectors, lightning arrestors and any other item required to complete the works. Porcelain, bushings, insulating oil and other associated equipment shall be tested by the supplier in accordance with relevant IS. If such equipment are purchased by the supplier on a sub-contract, he shall have them tested to comply with these requirements. 25.3 TEST REPORTS TO BE SUBMITTED ON THE FOLLOWING FACTORY TEST PRIOR TO INSPECTION: i) All standard routine tests in accordance IS: 2026 shall be carried out on each transformer.. ii) Following additional tests shall also be carried out as routine tests on each transformer: a) Magnetic Circuit Test b) Oil leakage test on transformer Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 303 Technical specification iii) Following type tests shall be conducted on the transformer of each rating: a) Temp. rise test as per IS: 2026 (Part-I). This test shall be carried out at maximum negative tap. b) Lightning Impulse Test shall be carried out in accordance with IS-2026 on one transformer of each rating. iv) Six (6) sets of certified test reports and oscillographs shall be submitted for evaluation prior to despatch of the equipment. The supplier shall also evaluate the test results and shall correct any defect indicated by his and Purchaser‘s evaluation of the tests without charge to the Purchaser. v) All auxiliary equipment shall be tested as per the relevant IS. Test certificates shall be submitted for bought out items. 25.4 TANK TESTS a) Routine Tests i) Fabrication Stage The tank shall be tested for leakage by being completely filled with air and applying a pressure equal to the normal pressure plus 35 KN/m 2 measured at the base of the tank. The pressure shall be maintained for a period of not less than one hour and during that time no leak shall occur. ii)Transformer assembly stage Oil pressure test to be conducted on tank and all other accessories and assembled for routine test by being completely filled with oil at a pressure equal to the twice the normal head of oil or to normal pressure plus 35 KN/m2 whichever is lower . The pressure shall be maintained for a period of eight hour and during that time no leak shall occur. b) Type Test Pressure Test Where required by the Purchaser, one transformer tank of each size together with its radiator, conservator vessel and other fittings shall be subjected to a pressure corresponding to twice the normal head of oil or to the normal pressure plus 35 KN/m 2 whichever is lower, measured at the base of the tank and maintained for eight hours during which no leakage shall occur. 25.5 PRE-SHIPMENT CHECK AT MANUFACTURERS WORKS: i) Check for proper packing and preservation of accessories like radiators, bushings, PRV, dehydrating breather, rollers, conservator etc. ii) Check for proper provision of bracing to arrest the movement of core and winding assembly inside the tank. iii) Gas tightness test to conform tightness. 25.6 RECEIPT AND STORAGE CHECKS a. Check and record condition of each visible parts of the transformers etc. for any damage. b. Check for oil and any leakage of oil from the transformer tank, radiators etc. c. Visual check HV/ LV bushings for any crack. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 304 Technical specification 26.0 26.1 27.0 27.1 d. Check for IR between HV-E, LV-E and HV – LV. e. Check for oil BDV and water content. f. Thermometer pockets are to be filled with oil. g. Colour of Silica gel is blue h. Bushing arcing horn is set correctly for required gap distance. i. Oil is at correct level in the bushing, conservator and tank. REJECTION The Purchaser may reject any transformer if during tests or service any of the following conditions arise: i) No load loss exceeds the guaranteed value by 20% or more. ii) Load loss exceeds the guaranteed value by 20% or more. iii) Impedance value exceeds the guaranteed value by ( -) 10% or more. iv) The difference in impedance values of any two phases during single phase short circuit impedance test exceeds 2% of the average value guaranteed by the vendor. v) Oil or winding temperature rise exceeds the specified value. vi) Transformer fails on impulse test. vii) Transformer fails on power frequency voltage withstand test. viii) Transformer is proved to have been manufactured not in accordance with the agreed specification. DRAWINGS and CALCULATIONS FOR SUBMISSION WITH THE BID The Bidder shall furnish with his bid following drawings incorporating the details mentioned hereunder. a) General outline drawing showing dimensions and overall dimensions, sectional view, core and coil assembly drawing, net weights and shipping weights, quantity of insulating oil, spacing of wheels, location off load tap changers etc. b) Details of the sectional view of core and winding showing the core frame size, coil dia and length, conductor size, lead support etc. c) Hot spot temperature calculation. d) Demonstration to withstand thermal ability as per IS:2026 e) Calculation of thermal time constant. f) Calculation for thermal and mechanical stress caused by symmetrical or asymmetrical faults on any winding. g) Calculation of detail losses including flux density and no load current are to be furnished for copper loss, iron loss indicating corresponding copper weight and core weight and considering all parameters and also supported by the drawings showings details of diameter and height of winding and core duly signed by manufacturer‘s design personnel. g) GA drawings/details of various types of bushings and connectors. h) Illustrative & descriptive literature of the Transformer i) List of customers to whom similar equipments have been supplied. j) Type test certificates from a recognized institute preferably CPRI of equipment of similar design and rating. k) Performance report of equipment of similar design and rating which is in satisfactory operation for at least three years. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 305 Technical specification Performance report issuing officer‘s rank should be S.E./ DGM and above of the utility. 28.0 QUALITY ASSURANCE PLAN: The bidders shall invariably furnish the following informations in respect of quality assurance, failing which, offers are liable to be ignored. (a) (i) List of important raw materials (CRGO laminations, wires and strips, transformer oil, insulating paper, press board, bushings and terminal connectors etc.) (ii) Name of Suppliers/ sub suppliers (iii) List of standards which are followed during testing of raw materials. (iv) List of test carried out on raw materials along with test certificate. (c) List of manufacturing facilities. (d) Level of automation achieved. (e) Quality control on stages of manufacturing process along with inspection reports. (f) List of testing equipments available along with valid calibration certificates. Manufacturer shall posses 0.1 accuracy class instruments for measurement of losses. Quality Assurance Plan (QAP) with hold points for Purchaser‘s Inspection as per Annexure – III. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 306 Technical specification 29.0 DATA SHEET SL NO DESCRIPTION 1. 2. 3. Continuous KVA Ratings (CMR) Number of phases Rated voltage kV i) Primary (HV) ii) Secondary (LV) 4. 5. 6. Highest System Voltage, kV i) Primary (HV) ii) Secondary (LV) Rated frequency, Hz. Connection of HV, LV 7. 8. 9. TRANSFORMER CLASS 11/0.433-0.250 KV 16,25,63,100, 200 KVA 3 11 0.433 12 1.1 50±5% HV Delta & LV Star with neutral solidly earthed Solidly earthed DYN 11 Method of system earthing Vector group Insulation Level: i) PF withstand voltage, kV 28 (rms.): HV ii) PF withstand voltage, kV 3 (rms.): LV iii) Lightening impulse voltage, kV 95 (peak) HV 10. Minimum Insulation resistance at HV- E : > 2000 MΩ 200C LV – E : > 1000 MΩ 11. 4.5% Percentage Impedance at 75C and at principal tap 12. Maximum flux density at rated 1.6 KVA, Maximum System voltage [12 KV/1.1 KV] and minimum system frequency [48.5 HZ], 13. Method of cooling ONAN 14. Type of tap changer No tapping 15. Clearance of air, mm a) phase to phase, HV / LV 285 / 75 phase to earth, HV / LV 140 / 40 16. Electrical Clearance, mm a) Core to LV: 3.5 (up to 100KVA) b) Between HV & LV 12 c) HV Phase to Phase 10 d) Between tank inside & top 150 of Yoke 40 e) Between yoke to bottom 17. Maximum current density Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 2.50 Amp / sq. mm for Copper 1.5 Amp/ sq.mm for Aluminium Assam Power Distribution Company Ltd 307 Technical specification SL NO DESCRIPTION 18. Temperature Rise, 0C (i) Winding (measured resistance. (ii) Top Oil (measured thermometer) Bushings: 1. Rated voltage in kV 19. TRANSFORMER CLASS 11/0.433-0.250 KV by 35 40 by 1.1 HV bushing 12 1.2 LV bushing 1.1 1.3 Neutral bushing 2. Rated current in Ampere 1.1 2.1 HV bushing As per IS: 3347 Part III (Section 1 & 2) As per IS: 3347 Part I (Section 1 & 2) As per IS: 3347 Part I (Section 1 & 2) 2.2 LV bushing 2.3 Neutral bushing 3. Rated impulse voltage in kV rms. withstand 3.1 HV bushing 4. One-minute power frequency withstand test in kV (rms.) 4.1 HV bushing 4.2 LV bushing 95 28 3 4.3 Neutral bushings 5. Minimum Creepage distance in mm 5.1 HV bushing 5.2 LV bushing 5.3 Neutral 3 350 55 55 30.0 DOCUMENTATION : 30.1 The bidder shall furnish along with the bid the dimensional drawings of the items offered indicating all the fittings. 30.2 Dimensional tolerances 30.3 Weight of individual components and total weight. 30.4 An outline drawing front (both primary and secondary sides) and end elevation and plan of the tank and terminal gear, wherein the principal dimensions shall be given. 30.5 Typical general arrangement drawing of the windings with the details of the insulation at each point and core construction of transformer. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 308 Technical specification 30.6 Typical general arrangement drawing showing both primary and secondary sides and end-elevation and plan of the transformer. 31.0 GUARANTEE: 31.1 The manufacturers of the transformers shall provide a guarantee of sixty (60) months from the date of commissioning and handover to APDCL. 31.2 In case of failure within the guarantee period the APDCL will immediately inform the supplier who shall take back the failed DTR within 15 days from the date of intimation at his own cost and replace/repair the transformer within thirty (30) days of date of intimation with a roll over guarantee. 31.3 The outage period i.e. period from the date of failure till unit is repaired/replaced shall not be counted for arriving at the guarantee period. 31.4 In the event of supplier‘s inability to adhere to the aforesaid provision, suitable penal action will be taken against the supplier which may inter alia include blacklisting of the firm for future business with the APDCL for a certain period. 32.0 SCHEDULES: 32.1 The bidder shall fill in the following schedule which will be part of the offer. If the schedule are not submitted duly filled in with the offer, the offer shall be liable for rejection. Schedule – A : Guaranteed Technical Particulars Schedule – B : Schedule of Deviations 33.0 DEVIATIONS: 33.1 The bidders are not allowed to deviate from the principal requirements of the Specifications. However, the bidder is required to submit with his bid in the relevant schedule a detailed list of deviations without any ambiguity. In the absence of a deviation list in the deviation schedule, it is understood that such bid conforms to the bid specifications and no post-bid negotiations shall take place in this regard. 33.2 The discrepancies, if any, between the specification and the catalogues and/or literatures submitted as part of the offer by the bidders, shall not be considered and representations in this regard shall not be entertained. 33.3 If it is observed that there are deviations in the offer in guaranteed technical particulars other than those specified in the deviation schedules then such deviations shall be treated as deviations. 33.4 All the schedules shall be prepared by vendor and are to be enclosed with the bid. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 309 Technical specification SCHEDULE - A GUARANTEED TECHNICAL AND OTHER PARTICULARS –DISTRIBUTION TRANSFORMERS (To be filled in by Bidder and shall be furnished with the Technical Bid) Sl. No Description 1. 2. 3. 4. 1Name of the Manufacturer 2Installation [indoor/outdoor] 3Reference standards 4Continuous Ratings a) b) c i ii d i ii e 5. 6. 7. 8. 9. 10. Type of cooling Rating [KVA] Rated voltage HV [KV rms.] LV [KV-rms.] Highest system voltage HV [KV rms.] LV [KV-rms.] Rated frequency with ±% variation f Number of phases g Current at rated full load i HV [Amps] ii LV [Amps] 5Connections HV LV 6Connection symbol and vector group 7Temperature rise a Temperature rise of oil above reference peak ambient temperature b Temperature rise of winding above reference peak ambient temperature c Temperature gradients between windings & oil. d Limit of Hot spot temperature for which the Transformer is designed [°C] 8i No load loss at rated voltage and frequency [WATT] 9Load loss at rated output, rated frequency, corrected for 75 °C winding temperature at:- [Copper loss] (WATT) 1Total losses Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification Sl. No Description 0 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. Maximum losses at 100% loading at 750C Maximum losses at 50% loading at 750C 1Positive sequence impedance on 1rated KVA base at rated current and frequency at 75°Centigrade winding temperature. (%) 1% reactance at rated KVA base at 2rated current and rated frequency (%) 1% resistance at rated KVA base at 3rated current and rated frequency [%] 1% Impedance at rated KVA base at 4rated current and rated frequency [%] 1a Polarisation index i.e. ratio of 5 Megger values at 600 secs to 60 secs, (H.V. to E, L.V. to E, & H.V.to L.V.). Measurement by 1.0 kV motorised megger. b Insulation Resistance in MΩ (At temp ……….0C) In Between H.V - E L.V. - E H.V – L.V. PI HV – E : LV – E : HV – LV : c Regulation at full load and 75°C winding temperature expressed as a percentage of normal voltage [%] 1Efficiency at 75°C winding Unity power 6temperature as derived from factor guaranteed loss figures and at a At full load [%] b At ¾ load [%] c At ½ load [%] 1i Maximum efficiency [%] 7ii Load at which maximum efficiency occurs[% of full load] 1Short time thermal rating of 8i HV winding in KA and duration in seconds ii LV winding in KA and duration in seconds 1Permissible over loading:9a HV winding b LV winding 2Terminal arrangement 0a High voltage [HV] b Low voltage (LV) Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 0.8 Power factor Assam Power Distribution Company Ltd Technical specification Sl. No Description 24. 2Insulating and cooling medium 1 2Test voltage 2 c 25. Neutral HV LV i 26. 27. 28. Lightning impulse withstand test voltage [KVP] ii Power frequency withstand test voltage [dry and wet][for 1 minute] [KV-rms.] 2External short circuit withstand 3capacity [MVA] and duration [seconds] 2Over-fluxing withstand capability of 4the Transformer 2DETAILS OF CORE 5a Type of core construction b Type of corner joints of the core c Maximum flux density at i Rated voltage [11/0.4 KV] & rated frequency 50 Hz][in Tesla] d No load current, no load loss and No load No Load No no load power factor at normal current Loss PF ratio and frequency [Amp/KW/p.f.] i 10 percent of rated voltage ii 25 percent of rated voltage iii 50 percent of rated voltage iv 85 percent of rated voltage v 100 percent of rated voltage vi 105 percent of rated voltage vii 110 percent of rated voltage vii 112.5 percent of rated voltage i ix 115 percent of rated voltage x 120 percent of rated voltage xi 121 percent of rated voltage xii 125 percent of rated voltage e Core laminations:i Material of core lamination [M4/HIB/AM] ii Grade of core laminations iii Thickness of core lamination [mm] iv Specific loss [watt/Kg.] at rated voltage and rated frequency v Specific loss [watt/Kg.] at highest system voltage and lowest system frequency Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Load Technical specification Sl. No Description vi vii vii i ix x f i ii iii iv v vi vii vii i ix x xi xii xii i xi v x v g 29. Whether specific core loss graph [flux density vs. watt/Kg. submitted VA/Kg at rated voltage and rated frequency VA/Kg. at highest system voltage and lowest system frequency Whether VA/Kg. Vs. flux density graph Submitted Insulation of core laminations CORE ASSEMBLY:Core diameter [mm] Core window height [mm] Core leg centre [mm] Gross core cross-sectional area [cm²] Whether details of core widths, stacks and calculation furnished as per enclosed annexure Distance between centers [mm] Total height of core [mm] 1) Details of core Clamping with nos. of core stud. 2) Material, grade & type 3) Width 4) Thickness 5) Fixing method Details of top end frame Details of Bottom end frame Details of clamp plate [Material, thickness, Insulation] Total core weight [kg] Core loss basing on core loss graph at operating flux density [rated voltage and rated frequency] [kw] Core stacking factor Net core area Sq. cm. Describe location/method of core grounding h Details of oil ducts in core if any i Peak value of magnetizing Inrush current (% of HV rated current). 2DETAILS OF WINDINGS. 6a Type of winding b Material of the winding conductor c Maximum current density of Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 HV LV Conductor Current density Assam Power Distribution Company Ltd Technical specification Sl. No Description windings [at rated current] and area [cm²] [A/cm²] conductor area i HV ii L.V. d Whether HV windings are crossover/ Sectional e Whether windings are preshrunk? f Whether adjustable coil clamps are provided for H.V. and L.V. windings? g Whether steel rings or perma wood are used for the windings? If steel rings used, whether these are split? h Winding Insulation. Type & class i H.V. ii LV Winding i Insulating material used for i H.V. ii L.V Winding j Insulating material used between i H.V. and L.V. winding ii Core and L.V winding iii H.V. winding and core iv H.V. to H.V. winding [between phases] V Inter coil spacers between HV sections (mm) Vi Type of block between HV sections Vi Oil duct between LV to cylinder (mm) : i Cylinder to HV (mm) : k Type of axial coil supports i H.V. winding ii LV winding l Type of radial coil supports i H.V. winding ii LV winding m Maximum allowable torque on coil clamping HV & LV bolts n Bare conductor size (mm). HV : LV : o Insulated conductor size (mm). HV : LV : p Number of coil per phase HV : LV : q No. of conductors in parallel HV : (Nos.). LV : Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification Sl. No Description r 30. No. of turns/phase HV coil : LV coil : s Inside diameter (mm). HV coil : LV coil : t Outside diameter (mm). HV coil : LV coil : u Axial height after shrinkage (mm). HV coil : LV coil : v D.C.RESISTANCE i L.V winding at 75 ° C (Ohms). ii HV winding at 75° C (Ohms). iii Total I²R losses at 75 ° C. (KW). iv Stray losses including eddy current losses in winding at 75°C (KW). v Any special measures taken to reduce eddy current losses and stray losses, mention in details vi Load losses at 75°C [I²R + stray].[Watt] w Details of special arrangement provided to improve surge voltage distribution in the windings 2BUSHINGS. HV LV 7 a i ii b c i ii d e f g h i Make and type Rated voltage class [KV-rms.] Rated current [Amps.] Lightning Impulse withstand test voltage [1.2/50 micro second][KVP] Power frequency withstand test voltage Wet for 1 minute [KV-rms] Dry for 1 minute [KV-rms] Minimum creepage distance in mm Weight of assembled bushing [Kg.] Minimum clearance height for removal of bushing [mm] Under oil flashover or puncture impulse voltage [KVP] Under oil flashover or puncture power frequency voltage (KVrms). Phase to earth clearance in air of live parts at the top of bushings Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Neutral Technical specification Sl. No Description 31. 2Minimum clearance [mm] 8 32. 33. In Oil Betwee Phase n to winding Groun s d Out of Oil Betwee Phase n to winding Groun s d HV LV a Radial clearance between LV and HV (mm) b Radial clearance between core to LV (mm) c End clearance of HV coil to yoke (mm) d End clearance of LV coil to yoke (mm) e Gap between yoke to bottom of tank (mm) 2Weight [Tolerance + 5%] 9[Approximate value is not allowed] a Core [Kg.] b Core with clamping [Kg.] c H.V. winding insulated conductor [Kg.] d L.V.winding insulated conductor [Kg.] e Coils with insulation [Kg.] f Core and winding [Kg] g Oil required for first filling [Liter/Kg.] h Tank and fittings with accessories [Kg.] i Untanking weight [Kg.] j Total weight with oil and fittings [kg.] 3DETAILS OF TANK 0 a b c i ii iii iv d i Material for Transformer tank Type of tank Thickness of sheet [No approximate value to be mentioned] Sides [mm] Bottom [mm] Cover [mm] Radiators [mm] Inside dimensions of main tank [No approximation in dimensions to be used] Length [mm] Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification Sl. No Description ii iii e 34. 35. Breadth [mm] Height [mm] Outside dimensions of main tank [No approximation in dimensions to be used] i Length [mm] ii Breadth [mm] iii Height [mm] f Thickness of spray galvanisation of tank bottom. g Vacuum recommended for hot oil circulation [torr] h Vacuum to be maintained during oil filling in Transformer tank [torr] i Vacuum to which the tank can be subjected without distortion [torr] l Type and make of pressure relief device and minimum pressure at which it operates [Kpa] 3CONSERVATOR 1a Total volume [Liters] b Volume between the highest and lowest visible oil levels [Litres] 3OIL QUALITY 2a Governing standard b c d e f g h i i ii j k l m i ii o i Density in gms/cu-cm Kinematics viscosity in CST Inter facial tension at 27°C in N/m Flash point in °C Pour point in °C Acidity [neutralization value] in mg of KOH/gm Corrosive sulfur in % Electric strength [breakdown voltage] As received [KV-rms.] After treatment [KV-rms.] Dielectric dissipation factor [tan delta] at 90°C Saponification value in mg of KOH/gm Water content in ppm Specific resistance At 90°C [ohm-cm] At 27 °C [ohm-cm] Oxidation stability Neutralization value after oxidation Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification Sl. No Description ii p 36. 37. 38. 39. 40. 41. 42. 43. Total sludge after oxidation Characteristic of oil after ageing test as per ASTMD-1934 i Specific resistance at 27°C [ohm-cms] 90°C [ohm-cms] ii Tan delta iii Sludge content iv Neutralization number v Details of oil preserving equipment offered 3RADIATORS 3a Overall dimensions lxbxh [mm] b Total weight with oil [Kg.] c Total weight without oil [Kg.] d Thickness of radiator tube [mm] e Types of mounting f Vacuum withstand capability g Total radiating surface in sq.m h Type and make of material used for the radiators i Total number of radiators/Banks for Transformer and dimensions of tubes j Thickness of hot dip galvanization of radiators 3APPROXIMATE OVERALL DIMENSIONS 4OF TRANSFORMER Length [mm] Breadth [mm] Height [mm] 3Transformers will be transported with 7oil. 3Types of terminal connectors and 8drawing No a HV b LV 3Details of painting, galvanization 9conforms to this Specification [Yes/No] 4No. of breathers provided [Nos.] 0 4Type of dehydrating agent and 1quantity used for breathers 4Valve sizes and numbers 2a Filter valves- mm-Nos b 44. 4a Sampling valves- mm-Nos Type and make of PRV Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification Sl. No Description 3b 45. 46. 47. 48. 49. 50. 51. No. of each type of devices per transformer c Min. pressure at which device operates 4Please enclose the list of accessories 4and fittings, being provided on transformer. Please confirm, these are as stipulated in the tender 4Whether the transformer, covered is 5fully type tested and if so, whether copies of type test certificates, enclosed with the tender 4What are the arrangements, available 8for jointing the winding. Preference shall be given to the tenderer using high-frequency brazing machines. In case other jointing techniques are used, adequacy of the same is to be recorded. Please note that bolted joints in the winding are not acceptable. This should be confirmed here 4Please confirm that you will 9guarantee maximum Impedance variation between phases within the limit of 2% only 5a Please confirm that the 0 transformer shall be dried by vapour/ vacuum-phase drying method. Please specify level of dryness b In case, other methods of drying are used, the level of dryness, so achieved should be identical to that by V/VPD. Adequacy of such system should be justified 5Whether the Tenderer has got In1House core-cutting facility for cutting core materials for the transformer ratings as tendered 5In case SL.50 is not confirmed, 2whether the tenderer is agreed to follow the procedures, as stipulated at clause 12.3 of this technical specification Signature of Bidder Representative: Name of Representative: Designation: Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Seal Date & Place: Assam Power Distribution Company Ltd Technical specification Sl. NO Clause NO. SCHEDULE - B Technical Deviation Sheet Deviations Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification TECHNICAL SPECIFICATION OF MICROPROCESSOR BASED MOULDED CASE CIRCUIT BREAKERS & Box 1. SCOPE 1.1. 1.2. 1.3. 1.4. 1.5. 2. 2.1. 2.2. 2.3. 2.4. 2.5. 2.6. 2.7. 2.8. This specification covers the general requirement of protection features of MCCB for satisfactory protection / operation of distribution transformers of rating 16, 25, 63, 100 and 200 kVA. Moulded-Case Circuit Breakers (MCCB) with microprocessor trip unit shall comply with IEC 60947-1, 60947-2, 60947-3 and IS 13947-1, 13947-2, 13947-3 standards or with the corresponding standards applicable in the member countries (VDE 0660, BS 4752, NF EN 60947-1/2): They shall be of category A with a rated service breaking capacity equal to the ultimate breaking capacity i.e. Ics =100% Icu. Icu should be 25kA and above. They shall have a rated operational voltage of 690 V AC (50±5% Hz). They shall have a rated impulse withstand voltage of 8KV. They shall have a rated insulation voltage of 800 V AC (50±5% Hz), They shall be suitable for isolation, as defined by IEC 60947 –1 and -2, § 7.1.7 for the Over-voltage Category IV for a rated insulation voltage up to 690 V according to IEC 60664-1. MCCBs shall be designed according to ECO-design complying with ISO 14062 Especially MCCB‘s materials shall be of halogen free type. MCCBs shall be of 4-pole type. MCCBs shall be designed for both vertical and horizontal mounting, without any adverse effect on electrical performance. It shall be possible to supply power either from the upstream or downstream side. MCCBs shall provide double insulation between the live power parts and the front parts where the operator works during normal operation. Construction, operation, environment The Microprocessor MCCB should be suitable for operation from -50C to + 700C and without any de-rating up to 500 C. MCCB should be supplied along with Extended Rotary handle for interlocking so that it should be possible to ON/OFF MCCB without opening the panel door. All poles shall operate simultaneously for circuit breaker opening, closing and tripping. MCCBs shall be actuated by a toggle switch for OF/OFF and a push button for trip. In order to ensure suitability for isolation complying with IEC 60947-2: The operating mechanism shall be designed such that the toggle switch can only be in OFF position (O) if the power contacts are all actually separated, In OFF position, the toggle shall indicate the isolation position. Isolation provided by the double break on the main circuit shall be preferred. MCCBs shall be able to receive a device for locking in the ―isolated‖ position, with padlocks, (8Ø maximum). MCCBs shall be equipped with a ―push to trip‖ button in front to test operation and to the opening of the poles. MCCB rating, ―push to trip‖ button, performances and contact position indication must be clearly visible and accessible from the front, through the front panel or the door of the switchboard. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification 2.9. MCCB shall be of Current Limiting Type. 2.10. MCCBs shall be equipped with a Microprocessor based Tripping unit. This unit will trip the circuit-breaker for high value short-circuits currents. The breaking will be carried out in less than 6ms for short-circuit currents above 8 times the rated current. 2.11. The electrical life of MCCBs as defined by IEC 60947-2 standard, shall be at least equal to 8000 electrical operations with number of hourly operation of 120 & above till 100 Kva and 4000 electrical operations with number of hourly operation of 60 & above from 200 Kva till 630 Kva . Also the Mechanical life of MCCB should be 25000 operations & above with number of hourly operation of 240 & above till 100 KVA and 20000 & above with number of hourly operation of 120 & above from 200 Kva till 630 KVA. 2.12. The MCCB shall trip in case the environmental conditions of the circuit- breaker get out of their specified range. However, it will be possible to overrule this feature. 2.13. Adjustable settings in Microprocessor based MCCB‘s should be through Dip Switched for precision & in lower steps of 0.04. 2.14. Auxiliaries and accessories 2.14.1. MCCBs shall be designed to enable safe on-site installation of auxiliaries such as voltage releases (shunt and under-voltage releases) and indication switches as follows: They shall be separated from power circuits, All electrical auxiliaries shall be of the snap-in type and fitted with terminal blocks, All auxiliaries shall be common for the entire range. Auxiliary function and terminals shall be permanently engraved on the case of the circuit breaker and the auxiliary itself, The addition of auxiliaries shall not increase the volume of the circuit breaker. 2.14.2. It shall be possible to equip MCCBs with devices indicating faults without tripping the circuit breaker. 2.15. The degree of protection of MCCB should be IP56 (with Rotary Handle) and IP40 with Toggle switch. 2.16. MCCB should have aux switch which indicates ON, OFF & Tripped indications individually. 3. Protection functions 3.1. General recommendations MCCBs shall be equipped with fully interchangeable trip units in order to ensure the protection against over current, Short-circuit and Ground fault. The trip units shall be of Microprocessor based. 3.2. Common features 3.2.1. Electronic Trip units shall be adjustable and it shall be possible to fit lead seals to prevent unauthorised access to the settings. 3.2.2. Electronic trip units shall comply with appendix F of IEC 60947-2 standard (measurement of RMS current values, electromagnetic compatibility, etc.) 3.2.3. Protection settings shall apply to all circuit breaker poles 3.2.4. The trip units shall not augment overall circuit breaker volume 3.2.5. All electronic components shall withstand temperatures up to 125 °C. 3.3. Electronic trip units 3.3.1. Characteristics Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification Long time protection (LT) Selectable Ir threshold settings from 36% to 100 % of the trip unit rating in the step of 0.04Ir with time delay. The time delay should be adjustable 3sec/6sec. 3.3.2. 3.3.3. 3.3.4. 3.3.5. Sl No. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Short time protection (ST) Ist threshold shall be adjustable from 1, 5 to 10 times the thermal setting Ir with time delay. The time delay should be adjustable 0.1sec/.25sec. Instantaneous protection The threshold shall be either adjustable or fixed (starting from 1.0 times In and up to a value between 10 times In with time delay. Four-pole devices shall be equipped for neutral protection: Load monitoring function The following monitoring functions shall be integral parts of electronic trip units: 2 LEDs for load indication, one lighted above 90 % of Ir, and one lighted above 105 % of Ir a test connector shall be installed for checks on electronic and tripping mechanism operation using an external device. Thermal memory In the event of repeated overloads, the electronic trip unit shall optimise protection of cables and downstream devices by memorising temperature variations. Options: It shall be possible to install all options for the electronic trip unit: High-threshold earth-fault protection, Auxiliary contact to indicate the cause of tripping long time, short time, instantaneous, earth fault if requested. Particulars Transformer Capacity (KVA) 16 25 63 100 200 Rated operating current, frame size Amp (Min.) Micro Processor MCCB with Rating Adjustable overload release setting Rated voltage (Volts) Rated Insulation level Number of poles Rated Ultimate breaking capacity Ics (KA) is 100% of Ultimate Breaking capacity, Icu Rated service breaking capacity ICS (KA) is 100% of ultimate breaking capacity, Icu Frequency Impulse withstand voltage High voltage withstands 32A 32A 32A 50A 50A 32A 100A 160A 320A 100A 160A 320A 100A 160A 318.8A 690V 1000V 4 690V 1000V 4 690V 1000V 4 690V 1000V 4 690V 1000V 4 10KA (Min) 10KA (Min) 25KA (Min) 25KA (Min) 25KA (Min) For All 50Hz ±3% 8 kV 3 KV Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 50Hz ±3% 8 kV 3 KV 50Hz ±3% 8 kV 3 KV Assam Power Distribution Company Ltd 50Hz ±3% 8 kV 3 KV Technical specification 4. 4.1. 4.2. 4.3. 4.4. 5. 5.1.1. 5.1.2. 5.1.3. 5.1.4. 5.1.5. 5.1.6. 5.1.7. 5.1.8. 5.1.9. 5.2. 5.2.1. 5.2.2. 5.3. 5.4. 5.5. 5.5.1. 5.5.2. voltage for 1 min. PRINCIPAL PARAMETERS: MCCBs shall have manually adjustable Current Settings up to range of 40100%. It should have inverse time characteristics for overload and trip time should be less than 10 msec. MCCBs should have finger-proof feature i.e, no live part(s) should be visible of MCCB. List of Approved Makes : SIEMENS/ ABB/L&T/Schnieder. GENERAL TECHNICAL REQUIREMENTS: The moulded case circuit breaker should be provided with auxiliary switch to differentiate ON/OFF & tripped indication. Material used in construction of circuit breaker shall be capable of withstanding the degree of protection & stress without distortion or failure of any part. The MCCB shall be supplied complete in all respect with necessary tools, bolts and other accessories considered necessary by tenderer‘s for satisfactory operation. The MCCB shall be completely maintenance free. All equipment accessories and wiring shall have tropical protection, involving special treatment of metal and insulation against fungus, insects and corrosion. The safety clearance of all live parts of the equipments shall be as per relevant standards. MCCB should be provided with microprocessor type release for the protection of the T/F against over loading and short circuit. The MCCB should be provided with disconnecting functions with positive isolation features. The MCCB should be provided with push to trip features also. OPERATING MECHANISM: The MCCB shall have an auxiliary switch with on and off & trip indicator. Microprocessor based type, quick break; quick make (trip free) mechanism should be provided in the MCCB. DESIGN AND OPERATING PRINCIPLE: The design & operating principle of moulded case circuit breaker should be of current limiting design with fast operating time and low thermal stress with compact size and independent manual operation. Moulded case circuit breaker should have the provision like position of switch different from ON & OFF state to indicate the tripping of MCCB. TIME/CURRENT CHARACTERISTICS: The MCCB shall not cause any tripping due to switching current of inductive and capacitive loads. The MCCB shall have the following time/current characteristics: Multiple of normal current setting Tripping time 1.05 More than 12 Hrs 1.20 <= 2 Hrs 1.30 <= 5 Minutes 1.40 <= 2 Minutes 2.50 <= 1 Sec 4.00 ,<= 40 m sec For the time/current characteristic, the reference calibration temperature of the breaker shall be 50oC. De-rating, if any up to 60oC operating temperature shall not exceed 10% of the current setting indicated in Para 5.5.1. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification 5.6. 5.7. 5.7.1. 5.7.2. 5.7.3. 5.7.4. 5.7.5. 5.7.6. 5.8. 5.9. 5.9.1. 5.9.2. 5.10. 5.11. TEMEPRATURE RISE LIMIT: The temperature rise on any part of equipment shall not exceed the maximum temperature rise limit specified in relevant ISS over an ambient temperature of o 40 C. MCCB BOX A tentative drawing of box showing general arrangement is enclosed as reference (Annexure-VII) as an integral part of the transformer which shall have to cover the LV side bushings.. The MCCB should be connected by insulated copper bus bar/ copper cable of appropriate size from the LV side bushings of the transformer and from MCCB to outgoing cable connector interface points. The transformer manufacturer has to design the box in such a way that the APDCL‘s workman will simply connect the outgoing cable at the connectors provided by the manufacturer. Cable size for different rating of transformer shall be as follows: For 16KVA – 3½-core, 16 sq.mm, 25KVA – 3½-core , 25 sq.mm, 63KVA – 3½-core 90 mm2, 100KVA 1-core, 1x90 mm2 and for 200KVA, 1-core, 2x120 mm2. Accordingly, the bidder has to submit detail drawing considering the requirements laid above for accorded of approval from APDCL. The MS sheet thickness of steel should not be less than 2.5 mm. The painting should be followed to that of transformer paintings procedure. The required cable glands and bi-metallic lugs as per cable size described above shall be supplied by the bidder. The gland plate should be non- magnetic material of adequate strength with pre-fabricated gland fitting hole. The MCCB box should be IP 55 grade. The door of the box should be of pad-lockable type. ERECTION TOOLS: Special tools and standard accessories required for assembly and for maintenance of the MCCB should also form a part of the supply. Necessary list should be supplied with the tender. CABLE: Copper cable of adequate size with ISI mark should be provided in the MCCB. Bakelite sheet should be used in the moulded case circuit breakers of make Hyalm, Super Hualm, milliborn or any reputed make. The MCCB should be fixed in side the metal box on the bakelite sheet. The bakelite sheet should be provided, for the MCCB, in L.T. Box having the following parameters:S.No. T/F Capacity Minimum size Minimum thickness 1. 16 & 25 kVA 150x250mm 4mm 2. 63 & 100 kVA 150x250mm 5mm 3. 200 kVA 250x350mm 6mm INDICATORS: The MCCB shall have a set of auxiliary contacts built in for indicating the healthiness of phases i.e. R,Y, & B. These normally open contacts shall form part of the signal light circuit. The signal light circuit shall consist of any auxiliary T/F capable of delivering 4 volt on the secondary side. RATING PLATE: MCCB shall be provided with a rating plate marked with but not limited to following data:i. Manufacturer‘s name, type of MCCB ii. Serial number iii.Owners name iv. Rated voltage Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification v. Rated normal continuous current vi. Rated insulation level vii. Rated frequency viii. Rated short time breaking current with rated duration ix. Total weight of breaker 6. TESTS: 6.1. TYPE TESTS: The equipment offered should be fully type tested as per relevant standards. In case the equipment of the type and design, offered, has already been type tested (not later than five years) the Bidder shall furnish for sets of the type test reports also with the offer. The purchaser reserves the right to demand repetition of the same all type tests in the presence of Purchaser‘s representative. For this purpose Bidder may quote unit rates for carrying out each type tests. For any change in the design/type already type tested viz-a-viz the design/type offered against the specification the purchaser reserves the right to demand the repetition of the same without any extra cost. In case the equipment has not been type tested earlier, the type tests as per relevant standard shall be carried out by the successful Bidder in the presence of Purchaser representative. The type test report(s) submitted by the bidder/ supplier from Govt. approved NABL accredited laboratory shall only be acceptable for participation of the bidder in the procurement/ empanelment process. In case NABL accredited laboratory happens to be that of manufacturer itself, added precaution shall be taken to get type test and other tests witnessed in the laboratory by APDCL representative at the time of acceptance of material. 6.2. ACCEPTANCE AND ROUTINE TESTS: 6.2.1. All acceptance and routine tests as per relevant ISS shall be carried out by the bidder in the presence of Purchaser representative. 6.2.2. ADDITIONAL TEST: The purchaser reserves the right to carry out any other type tests of a reasonable nature at the works of the supplier/laboratory or at any other recognized laboratory/research institute in addition to the above mentioned type, acceptance and routine tests at the cost of the purchaser to satisfy that the material complies with the intents of this specification and also if there is any dispute regarding quality of the equipment. 7. INSPECTION 7.1. The inspection may be carried out by the authorized representative of purchaser at any stage of manufacture. The successful bidder shall grant free access to the purchaser‘s representative at a reasonable time when the work is in progress. Inspection and acceptance of any equipment under this specification by the purchaser shall not relieve the bidder of his obligation of furnishing equipment in accordance with the specification and shall not prevent subsequent rejection, if the equipment is found to be defective. The Bidder shall keep the purchaser informed in advance about the manufacturing programme so that arrangement can be made for inspection. 7.2. The purchaser reserves the right to insist for witnessing the acceptance/routine testing of the bought out items. 7.3. No material shall be dispatched by manufacture unless the material has been satisfactorily inspected tested and further dispatch authorized by purchaser. 8. LIST OF DRAWINGS AND DOCUMENTS: The bidder shall furnish four sets of relevant descriptive and illustrative published literature pamphlets and the following drawings for preliminary study along with the offer. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification a). General outline drawings showing dimensions and shipping weights, quantity of insulating media etc. b). Sectional views showing the general constructional features of the circuit breaker including operating mechanism, arcing chambers, contacts with lifting dimensions for maintenance etc. c). Schematic diagrams of MCCB offered for control supervision and reclosing. 9. PACKING AND FORWARDING: The equipment shall be packed in suitable creates so as to withstand handling delivery transit. The bidder shall be responsible for any damage to the equipment during transit, due to improper and inadequate packing and handling. The easily damageable material shall be carefully packed and marked with the appropriate cautions symbols. Wherever, necessary proper arrangement for lighting such as lifting hooks etc. shall be provided. Any material found short inside the packing cases shall be supplied y the bidder without any extra cost. 10. GUARANTEE / WARRANTEE The supplier shall be responsible to replace, free of cost, with no transportation or insurance cost to the Purchaser, up to destination, the whole or any part of the material which in normal and proper use proves the defective in quality or workmanship, subject to the condition that the defect is noticed within 60 (sixty) months from the date of receipt of material in stores OR 54 (fifty four) months from the date of commissioning whichever period may expire earlier. The consignee or any other officer of APDCL actually using the material will give prompt notice of each such defect to the supplier. The replacement shall be effected by the supplier within a reasonable time, but not, in any case, exceeding 30 (thirty) days. The supplier shall, also, arrange to remove the defective within a reasonable period, but not exceeding 30 (thirty) days from the date of issue of notice in respect thereof, failing which, the purchaser reserve the right to dispose of defective material in any manner considered fit by him (Purchaser), at the sole risk and cost of the supplier. Any sale proceeds of the defective material after meeting the expenses incurred on its custody, disposal handling etc., shall however be credited to the supplier‘s account and set off against any outstanding dues of the purchaser against the supplier. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification 11. GUARNTEED TECHNICAL PARTICULARS GUARANTED TECHNICAL PARTICULARS OF MICROPROCESSOR BASED MCCB TO BE USED UP TO 200 kVA DISTRIBUTION TRANSFORMERS Sl No Descriptoin Technical Particulars A. Microprocessor Based MCCB Specification 1. Moulded case Circuit Breaker Microprocessor Based (MCCB) approved makes. 2. Type of Microprocessor Based MCCB, 3. Standards to which confirms to for a). Accuracy b). Protection/safety 4. Rated Operating Current, Frame size Amp. 5. Rated voltage, volts 6. Rated Insulation Level 7. Fixed overload release setting (Amp.) 8. Number of Poles 9. Rated Ultimate Breaking capacity, Icu (KA) as per IS: 13947/1933. 10. Rated service breaking capacity Icu (KA) is 75% of Ultimate Breaking capacity, Icu. 11. Power factor for short circuit (Max.) 12. Utilization capacity 13. Power loss & mill volt drop values 14. Protection against over load. 15. Impulse withstand voltage. 16. High voltage withstands voltage. 17. Type of mechanism 18. Design & Operating Principle. 19. Whether time-current characteristics is as per specifications with limit of derating with temperature rise. 20. Whether the MCCB is having disconnecting functions with positive isolation features. 21. Whether the Microprocessor Based MCCB is having flexible mounting with line-load reversibility features i.e. no change in rating and breaking capacity of MCCB when mounted in different orientations and with line and load connections changed. 22. Whether the Microprocessor Based MCCB is having push-to-trip feature. 23. Whether the Microprocessor Based MCCB is having provision like position of switch different from ON & OFF state to indicate tripping of MCCB. 24. Weight of the Microprocessor based MCCB. 25. Whether samples submitted with offer as specified. 26. Instructions and operating manual with sample Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification 27. B. 1. 2. 3. 4. 5. C. 1. 2. 3. 4. 5. 6. D. 1. 2. 3. 4. E. 1. 2. 3. 4. 5. 6. 7. 8. F. 1. 2. 3. Mfg. Type Test Report. CABLE Specification Copper cable approved makes Copper cable size per phases Copper cable size of Neutral Total copper cable required. Copper cable length THIMBLE/LUGS SPECIFICATION Makes. Metal to be use Size for phases Size for Neutral. Total no. of thimble/lugs to be fitted a. mm b. mm Crimping of thimble/Lugs BAKELITE SHEET Specification Bakelite Sheet approved Makes. Fixing of Microprocessor based MCCB inside of Box. Bakelite sheet Thickness. Bakelite Sheet Size. BOX Specification Size of box and fixing arrangement with box. Box inside look and outside look as per design. MS sheet thickness Air ventilation provided in Box. IP grade Microprocessor Based MCCB On/Off switch window to be provided with window shed. Danger Plate with operating instructions. Rubber glands. LED Indicators Specification LED indicators approved Makes. Colour & Nos. of indicators to be provided. Mounting of indicators. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification ANNEXURE – I MAXIMUM FLUX DENSITY AND CORE WEIGHT CALCULATION (To be filled in by Bidder and shall be furnished with the Technical Bid) Step No Width of steps [mm] Stack Thickness Gross Iron Area [mm] [mm²] 1 2 3 4 5 6 7 8 9 10 ---------------Bmax = E/(4.44 x f x Ai x N) Where E = L.V. winding phase voltage / phase f = Rated frequency = 50 HZ. Bmax. = Maximum flux density in Tesla. Ai = Net iron area in sq.m = Gross iron area x stacking factor in sq.m N = Number of L.V.winding, turns/phase Stacking Factor = 0.97 maximum Core weight calculation:Core dia [in mm] = Window height [in mm] = Limb center [in mm] = Weight of core = [3 x window height + 4 x limb centre + 2 x max. width] x Net iron area x Density of core NB: - 1 Specific loss vs. flux density graph for the type of core lamination to be used has to be furnished. 2. VA/Kg. Vs flux density graph for the core lamination to be used has to be furnished. 3. Any other factor assumed for above calculation to be explained with reasons. N.B.:- The bidder may use its own method of calculation towards determination of maximum flux density and weight of the core. But the same shall be supported with proper explanation and justification. Place: Date: Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Signature of Tenderer with seal of Company. Assam Power Distribution Company Ltd Technical specification ANNEXURE – II DETAILS OF LOSS CALCULATION (To be filled in by Bidder and shall be furnished with the Technical Bid) Sl. No 1. Particulars Values Flux density at (i) 12/1.1 kV & 50 Hz, Tesla (ii) 11/0.433 kV & 48.5 Hz, Tesla 2. Core Data (i) Core weight in Kg. (ii) Gross core area [mm²] (iii) Stacking factor. (iv) Net core iron area [mm²] [ii x iii] 3. Specific losses [W/Kg.] (i) At maximum flux density corresponding to 12/1.1 KV and 48.5 HZ. (ii) At maximum flux density corresponding to 11/0.433 KV and 50Hz. 4. Volt ampere/Kg (i) At maximum flux density corresponding to 12/1.1 KV and 48.5 HZ. (ii) At maximum flux density corresponding to 11/0.433 KV and 50Hz. 5. Calculated/guaranteed iron loss in KW at: (i) Rated voltage and rated frequency (ii) Rated voltage and rated frequency 6. Current density [A/Sq. mm] for (i) HV (ii) LV 7. Conductor size [in mm²] (i) HV winding a) Bare b) Insulated c) No of conductors in parallel (ii) LV winding a) Bare b) Insulated c) No of conductors in parallel 8. Copper weight (i) H.V. windings (ii) LV windings (iii) Total copper weight [i]+[ii] 9. 10. 11. 12. 13. 14. L.V. winding resistance in ohms at 75°C/Phase. H.V. winding resistance in ohms at 75°C/Phase. Stray losses and eddy current losses [in KW] at 75°C Resistively of copper to be used for winding I²R loss at 75°C Calculated guaranteed copper losses [in KW] at 75°C Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification Sl. No 15. Particulars Values [I²R loss + stray losses] Computed/guaranteed total loss in KW at rated voltage and rated frequency [Copper loss + Iron loss] NB: - 1 Approximate values in weight and losses etc. are not allowed. 2 Tolerance of + 5% in weights may be quoted without any approximation Place: Date Bidder‘s name: Signature, designation, seal Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification Annexure - III QUALITY ASSURANCE PLAN Manufacturer should submit for purchaser‘s approval a quality assurance plan in line with this with this document. Abbreviations: PS Plant Standard/ Process Specification. TR Test Report IS Indian/International Standards AD Approved Document such as Drawing, Purchase Order V verified by P Performed by W Witnessed by H Hold by Purchaser 1 Purchaser 2 Manufacturer 3 External laboratory 4 Sub vendor QC Notes: 1. Minor: The characteristic of a component, process or operation whose failure neither materially reduce the usability of the product in operation, nor does it affect the aesthetic aspects. 2. Major : The characteristic of a component, process or operation whose failure may cause operation failure which cannot be readily corrected, at site cause substandard performance, increase erection and maintenance cost, reduce life or seriously affect aesthetics. 3. Critical : The characteristic of a component, process or operation failure of which will will surely cause operating failure or intermittent troubles which is difficult to rectify at site or render the unit unfit for use or safety hazards. 4. ―Failure‖ of a characteristics means failure to meet the ‗accepted norms‘. 5. Sampling : generally sampling will be done in accordance with IS:2500. Sampling be as under If 100% ―Witness‖ of tests is carried out by Prime Supplier, Customer will witness on sample basis or if 100% ―Witness‖ of tests is carried out by Sub Vendor, Manufacture will witness on sample basis. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Technical specification QUALITY ASSURANCE PLAN FOR DISTRIBUTION TRANSFORMERS Sl No Component & Operations 1 2 RAW Materials 1 CRGO Aluminium /Copper Wire Rod 3 4 Kraft Paper Epoxy dotted Kraft paper Characteristics Class Type of Check Quantum of Check Reference Document Acceptance Norms 3 4 5 6 7 8 Dimensions Specific loss Chemical analysis Surface insulation resistance Transit damage Stacking factor Tensile strength Major Major Major Major Measurement Measurement Measurement Measurement 100% 100% Sample/lot 100% Major Major Major Visual Measurement Measurement 100% 100% 100% Elongation Dimensions Transit damages Cracks & twists Resistivity Chemical analysis Major Major Major Major Major Major Measurement Measurement Visual Visual Measurement Measurement Transit damages & Packing Conditions Dimensions Density Tensile strength Elongation Moisture content Ash content Dielectric strength Transit damages & Packing Conditions Dimensions Density Tensile strength Elongation Major Visual 100% 100% 100% 100% 100% One sample/consi gnment 100% Major Major Major Major Major Major Major Major Measurement Measurement Measurement Measurement Measurement Measurement Measurement Visual 10% of lot 100% 100% 100% 100% 100% 2 samples/lot 100% Major Major Major Major Measurement Measurement Measurement Measurement Moisture content Ash content Major Major Measurement Measurement 10% of lot 100% 100% One sample/ consignment 100% 100% Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Format of Record 9 Agency V P W 10 Remarks H 11 334 Technical specification Sl No 1 5 Component & Operations 2 Insulating Oil Characteristics Class Type of Check Quantum of Check Reference Document Acceptance Norms 3 4 5 6 7 8 Dielectric strength Thickness of resin coating Appearance Major Major Major Measurement Measurement Measurement Major Major Major Major Major Major Major Measurement Measurement Measurement Measurement Measurement Measurement Test 2 samples/lot samples/lot Sample from each tanker - do - do - do - do - do - do - do - Major Major Measurement Measurement - do - do - Major Measurement - do - Major Major Major Measurement Test Measurement Major Major Major Major Major Major Major Major Major Measurement Visual Measurement Measurement Measurement Measurement Measurement Measurement Measurement - do - do Sample from each tanker - do 10% of lot 10% of lot Sample/lot Sample/lot Measurement Measurement Measurement Measurement Major Major Major Major Major Major Major Visual Measurement Measurement Measurement Measurement Measurement Measurement 10% of lot 10% of lot Sample/lot Sample/lot Sample/lot Sample/lot Sample/lot 0 6 Insulating Press Board 7 Perma Wood Density at 27 C 0 Viscosity at 27 C 0 Interfacial tension at 27 C Flash point Pour Point Total acidity Corrosion Sulphur copper 0 strip.19 hours @ at 140 C BDV Dielectric dissipation factor 0 @ at 140 C Specific resistance 0 0 at 27 C & at 90 C Oxidation stability Accelerated ageing test Presence of oxidation inhibitor Water content Finish Appearance Dimensions Density Tensile strength BDV Ash content Moisture content Conductivity of aqueous extracts Finish Appearance Dimensions Density Tensile strength Cross breaking strength Impact strength Compressive strength Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Format of Record 9 Agency V P W 10 Remarks H 11 335 Technical specification Sl No 1 Component & Operations 2 8 Paper covered conductor 9 Enamel Covered Conductor 10 MS material (Plates, Flats, Angles & Channels 11 Hard Ware 12 Gaskets Characteristics Class Type of Check Quantum of Check Reference Document Acceptance Norms 3 4 5 6 7 8 Shear strength Moisture content Oil absorption Finish Appearance Dimensions Resistivity Tensile strength Elongation Covering thickness Finish Appearance Dimensions Resistivity Tensile strength Elongation Covering thickness Flexibility Test Adherence Heat Shock Hardness Solvent Resistance BDV Cut-through Test Finish Appearance Dimension Hardness Chemical composition Tensile strength Yield strength Elongation Bend test Dimensions Finish Appearance Finish appearance Dimensions Compressibility Tensile Strength Recovery% Oil immersion test Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Measurement Measurement Measurement Visual Measurement Measurement Measurement Measurement Measurement Visual Measurement Measurement Measurement Measurement Measurement Test Test Test Measurement Test Measurement Test Visual Measurement Measurement Measurement Measurement Measurement Measurement Test Measurement Visual Visual Measurement Measurement Measurement Measurement Measurement Sample/lot Sample/lot Sample/lot 100% Each bobbin Sample/lot Sample/lot Sample/lot Each bobbin Each bobbin Each bobbin Sample/lot Sample/lot 10% Each bobbin 40% 40% 40% 40% Sample/lot 40% Sample/lot 100% 2% of lot Sample/lot Sample/lot Sample/lot Sample/lot Sample/lot Sample/lot Sampling Sampling 5% 5% Sample/lot Sample/lot Sample/lot Sample/lot Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Format of Record 9 Agency V P W 10 Remarks H 11 336 Technical specification Sl No 1 Component & Operations 2 Characteristics Class Type of Check Quantum of Check Reference Document Acceptance Norms 3 4 5 6 7 8 Compression test at 110 C Major Measurement Sample/lot Finish appearance Dimensions Power frequency withstand test Porasity test Temperature cycle test Finish appearance Dimensions Finish appearance Major Major Major Visual Measurement Test 100% 10% of lot 5 Nos/lot Major Major Major Major Major Test Test Visual Measurement Visual 5 Nos/lot 5 Nos/lot 5% of lot 5% of lot 2% of lot Thickness of coating Appearance Viscosity Major Major Major Measurement Visual Measurement 2% of lot Sample/lot Sample/lot Appearance Shade Viscosity Shade Scratch Hardness Drying time Appearance Viscosity Shade Drying time Finish Scratch Hardness Flexibility & adhesion Shade Pencil hardness Major Major Major Major Major Major Major Major Major Major Major Major Major Major Major Visual Visual Measurement Visual Test Measurement Visual Measurement Visual Measurement Visual Test Test Visual Test 100% 100% Sample/lot 100% Sample/lot Sample/lot 100% Sample/lot 100% Sample/lot 100% Sample/lot Sample/lot 100% Sample/lot Cross hatch adhesion Curing cycle Finish appearance Dimensions Chemical compositions Finish appearance Major Major Major Major Major Major Test Measurement Visual Measurement Test Visual Sample/lot Sample/lot 100% 5% of lot 1 no/ lot 10% 0 13 Bushing a) Porcelain b) Metal Parts 14 Plating/Galvanizing/P hosphating 15 Epoxy resin 16 Paints a) Primer b) Hot oil Resistance paint C) Polyurathane paint d) Thermo setting Powder Paint 17 HV & LV Connectors 18 Oil level gauge Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Format of Record 9 Agency V P W 10 Remarks H 11 337 Technical specification Sl No 1 19 1 Component & Operations 2 Characteristics Class Type of Check Quantum of Check Reference Document Acceptance Norms 3 4 5 6 7 8 Dimensions Gel weight Gel colour Dimensions MANUFACTURING PROCESS & ASSEMBLY Transformer tank, Check of raw materials Conservator & Cutting of material as per accessories given drawing Finish dimensions & completeness as per drawing Conservator tank and tube dimensions Finish of weld Finish of material after gas cutting and welding Leak test Vacuum test Major Major Major Major Measurement Measurement Visual Measurement 10% 10% 100% 10% Major Major Visual Measurement 100% Sampling Major Measurement Sampling Major Measurement Sampling Major Major Visual Visual Sampling 100% Major Major Test Surface finish prior to pain application Check of inside painting Application of primer coating Application of first coat of paint Application of finish coat of paint Paint thickness Adhesion Hardness Check of raw materials Dimensions Weld finish Surface preparations Painting Major Test 100% One/each rating 100% Major Major Visual Visual 100% 100% Major Visual 100% Major Visual 100% Major Major Major Major Major Major Major Major Measurement Test Test Visual Measurement Visual Visual Visual 100% 10% 10% 100% Sampling Sampling 100% 100% Width Thickness Major Major Measurement Measurement Sampling Sampling Silicagel Breather 2 Frames & Channels welding 3 Core assembly a) Core cutting Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Format of Record 9 Agency V P W 10 Remarks H 11 338 Technical specification Sl No 1 Component & Operations 2 b) Core annealing c) Core assembly 4 5 6 7 Winding Insulation components Core & Coil assembly Drying of core coil assembly Characteristics Class Type of Check Quantum of Check Reference Document Acceptance Norms 3 4 5 6 7 8 Length Burr Angle of cutting Temperature & speed Major Major Major Major Measurement Measurement Measurement Measurement Formation of core section Core dia Stack thickness Leg length Window width Core weight Bindings of limbs Assembly of frame structures Pre-core losses Conductor size Forma dia Coil dimensions (ID,OD,AH,RD) Insulation arrangement Turns arrangements Transposition Finishing & lead position Dimensions Finishing Dimensions Axial & Radial insulation arrangements Electrical clearances Yoke filling Position of lead out HV & LV Connections Insulation and Finishing of brazed/crimped joints Ratio test Temperature Time duration Insulation Resistance Major Major Major Major Major Major Major Major Measurement Measurement Measurement Measurement Measurement Measurement Visual Visual Sampling Sampling Sampling Every one hour 100% 100% 100% 100% 100% 100% 100% 100% Major Major Major Major Measurement Measurement Measurement Measurement Sampling 100% 100% 100% Major Major Major Major Major Major Major Major Visual Visual Visual Visual Measurement Visual Measurement Measurement 100% 100% 100% 100% Sampling 100% 100% 100% Major Major Major Major Major Measurement Visual Visual Visual Visual 100% 100% 100% 100% 100% Major Major Major Major Test Measurement Measurement Measurement 100% 100% 100% 100% Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Format of Record 9 Agency V P W 10 Remarks H 11 339 Technical specification Sl No 1 8 Component & Operations 2 Characteristics Class Type of Check Quantum of Check Reference Document Acceptance Norms 3 4 5 6 7 8 Format of Record 9 Agency Tanking & Oil filling under vacuum Clamping of CCA Job locking Completeness Dimensions Electrical clearances Vacuum Oil temperature Fixing of accessories and fittings as per drawing Leak proof ness Major Major Major Major Major Major Major Major Visual Mechanical Visual Measurement Measurement Measurement Measurement Visual 100% 100% 100% 100% 100% 100% 100% 100% Major Pressure test Sampling a. Winding Resistance b. Voltage Ratio & Voltage Vector Relationship c. Load loss and Impedance voltage measurement d. No load loss & No load Current e. Neutral current measurement f. Insulation resistance g. Induced Over Voltage Test h. Separate source voltage withstand test i. Magnetic balance test a. Short Circuit Test Critical Critical Measurement Measurement 100% 100% IS : 2026 IS : 2026 IS : 2026 IS : 2026 TC TC 1 1 2 2 1 1 Critical Measurement 100% IS : 2026 IS : 2026 TC 1 2 1 Critical Measurement 100% IS : 2026 IS : 2026 TC 1 2 1 Critical Measurement 100% 1 2 1 Measurement Measurement 100% 100% CBIP Manual IS : 2026 IS : 2026 TC Critical Critical CBIP Manual IS : 2026 IS : 2026 TC TC 1 1 2 2 1 1 Critical Measurement 100% IS : 2026 IS : 2026 TC 1 2 1 Critical Critical Measurement Measurement TC 1 IS 2026 IS 2026 2 3 1 1 1 b. Temperature Rise Test Critical Measurement IS 2026 IS 2026 2 1 1 c. Lightining Impulse Voltage Test d. Vacuum Test Critical Measurement IS 2026 IS 2026 3 1 1 Critical Measurement IS 1180 IS 1180 2 1 1 e. Pressure Test Critical Measurement Sampling One/Each rating One/Each rating One/Each rating One/Each rating One/Each rating IS 1180 IS 1180 2 1 1 V P W 10 Remarks H 11 INSPECTION TESTING 2 TYPE TEST Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 340 Technical specification Annexure – IV PROFORMA FOR STAGE INSPECTION OF DISTRIBUTION TRANSFORMER (A) GENERAL INFORMATION 1. Name of firm: M/s. 2. Order No and Date: 3. Rating wise quantity offered: 4. Details of offer a) Rating b) Quantity c) Serial Numbers 5. Details of last stage inspected lot: a) Total quantity inspected b) Serial Numbers c) Date of stage inspection d) Quantity offered for final inspection of (a) above with date. (B) Availability of material for offered quantity: Details to be filled in (C) Position of manufacturing stage of the offered quantity a) Complete tank assembly b) Core and coil assembly ready c) Core assembled d) Coils ready for assembly (i) HV coils (ii) LV coils Note: (i) A quantity of more than 100 Nos shall not be entertained for stage inspection. (ii) The stage inspection shall be carried out in case:(a) At least 25% quantity offered has been tanked and (b) Core coil assembly of further at least 30% of the quantity offered has been completed. (iii) Quantity offered for stage inspection should be offered for final inspection within 15 days from the date of issuance of clearance for stage inspection, Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 341 Technical specification otherwise stage inspection already cleared shall be liable for cancellation. Sl No Particulars (D) Inspection of Core (i) Core Material (1) Manufacturer's Characteristic Certificate in respect of grade of lamination used. (Please furnish test certificate) (2) Remarks regarding rusting and smoothness of core (3) Whether laminations used for top and bottom yoke are in one piece (II) Core Construction: (i) No of Steps (2) Dimension of Steps Step No 1 2 3 4 5 6 As offered : W mm T mm As found : W mm T mm As offered As observed Deviations and Remarks 7 9 11 8 10 12 (3) Core dia (mm) (4) Total cross section area of core (5) Effective cross sectional area of core (6) Clamping arrangement (i) Channel Size (ii) Bolt size and No (iii) Tie rods size and No. (iv) Painting (a) Channels (b) Tie Rods (c) Bolts (7) Whether top yoke is cut for LV connection (8) If yes, at 7 above, whether Reinforcement is done. (9) Size support channels provided for core base and bottom yoke ( Single piece of channels are only Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 342 Technical specification acceptable) (10) Thickness of insulation provided between core base and support channel (11) Core length (leg center to leg center) (12) Window height (13) Core height (14) Core weight only (without channels etc) (E) INSPECTION OF WINDING (I) Winding material (1) Material used for (a) HV winding (b) LV winding (2) Grade of material for (a) HV winding (b) LV winding (3) Test certificate of manufacturer (enclose copy) for winding material of: (a) HV (b) LV (II) CONSTRUCTIONAL DETAIL (1) Size of cross sectional area of conductor for: (a) HV winding (b) LV winding (2) Type of insulation for conductor of: (a) HV winding (b) LV winding (3) Diameter of wire used for delta formation (MM) (4) Diameter of coils in (a) LV winding i) Internal dia (mm) ii) Outer dia (mm) (b) HV winding i) Internal dia (mm) ii) Outer dia (mm) Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 343 Technical specification (5) Current Density of winding material used for: (a) HV (b) LV (6) Whether neutral formation on top (7) HV Coils/Phase a) Number b) Turns/Coil c) Total turns (8) LV Coils/Phase a) Number b) Turns/Coil c) Total turns (9) Method of HV Coil Joints (10) Total weight of coils of (a) LV winding (kg) (b) HV winding (kg) (F) INSULATION MATERIALS (I) MATERIAL 1) Craft paper a) Make b) Thickness c) Test Certificate of manufacturer (enclose copy) 2) Press Board a) Make b) Thickness c) Test Certificate of manufacturer (enclose copy) 3) Material used for top and bottom yoke and insulation (II) Type and thickness of material used (mm) a) Between Core and LV b) Spacers c) Inter layer d) Between HV and LV winding e) Between phases f) End insulation (G) CLEARANCES : (mm) Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 344 Technical specification (I) Related to core and windings 2) Between HV and LV (Radial) 3) (i) Phase to Phase between HV conductor (ii) Whether two Nos. Press Board each of minimum 1 mm thick provided to cover the tie rods. 4) Thickness of locking spacers between LV coils (mm) 5) Axial wedges between HV and LV coils/ phase (Nos.) 6) No. of radial spacers per phase between HV coils 7) Size of duct between LV and HV winding (mm) (II) Between core - coil assembly and tank : (mm) 1) Between winding and body: a) Tank lengthwise b) Tank breadth wise 2) Clearance between top cover and top yoke (H) TANK: (I) Constructional details 1) Rectangular shape 2) Thickness of side wall (mm) 3) Thickness of top and bottom plate (mm) 4) Provision of slopping top cover towards HV bushing 5) Tank internal dimensions (mm) a) Length b) Breadth c) Height (i) On LV side (ii) On HV side (II) General details: 1) Inside painted by varnish/ oil corrosion resistant paint (please specify which type of coating done) 2) Gasket between top cover and tank i) Material ii) Thichness (mm) Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 345 Technical specification iii) Jointing over laps (mm) 3) Reinforcement of welded angle (specify size and No. of angle provided) on side walls of tank. 4) Provision of lifting lugs: a) Numbers b) Whether lugs of 8 mm thick MS Plate provided c) Whether reinforced by welded plates edge wise below the lug upto re-enforcing angle of the tank done 5) Pulling lug of MS Plate a) Nos b) Thickness (mm) c) Whether provided on breadth side or length side 6) Provision of air release plug 7) Provision of galvanized GI nuts and bolts with 1 no plain and 1 no spring washer. 8) Deformation of length wise side wall of tank when subjected to: a) Vacuum of (-) 0.7 kg/sq cm for 30 minutes. b) Pressure of 0.8 kg/sq cm for 30 minutes (I) RADIATORS 1. Fin radiators of 1.25 mm thick sheet a) Dimension of each fin (LxBxT) b) Fins per radiator c) Total number of radiators 2. Varification of manufacturer's test certificate regarding Heat Dissipation (excluding top and bottom) in w/sq m. 3. Verification of position of radiator with respect to bushing. (J) CONSERVATOR : 1. Dimensions (LxD) in mm 2. Volume (cu m) 3. Inside dia of conservator tank pipe (mm) 4. Whether conservator outlet pipe is projected approx. 20 mm inside the Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 346 Technical specification conservator tank. 5. Whether arrangement made so that oil does not fall on the active parts. 6. Whether die cast metal oil level gauge indicator having three positions at ( - 5, 30 and 98 degree C) is provided. 7. Whether drain plug and filling hole with cover is provided. 8. Inner side of the conservator Tank painted with. (K) BREATHER 1. Whether Die cast Aluminium body breather for silica gel provided. 2. Make 3. Capacity (L) TERMINALS 1. Material whether of Brass Rods/ Tinned Copper a) HV b) LV 2. Side (dia in mm) a) HV b) LV 4. Method of Connection of LV winding to LV bushing (end of winding should be crimped with lugs (Al/Cu) and bolted with bushing stud). 5. Method of Connection of HV winding to HV bushing (Copper joint should be done by using silver brazing alloy and for Aluminium, brazing rod or with tubular connector crimped at three spots). 6. Whether SRBP tube/ insulated paper used for formation of Delta on HV. 7. Whether Empire sleeves used on the portion of HV winding joining to HV bushing. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 347 Technical specification 8. Whether neutral formation is covered with cotton tape. (M) BUSHING : 1. Whether HV bushings mounted side wall or Top cover 2. Whether sheet metal pocket used for mounting bushing (pipes are not acceptable) a) HV b) LV 3. Whether arrangement for studs for fitting of HV bushing are in diamond shape (so that Arcing Horns are placed vertically) 4. Position of mounting of LV bushings. 5. Bushing Clearance: (mm) a) LV to Earth b) HV to Earth c) Between LV bushings (N) d) Between HV bushings TANK BASE CHANNEL/ROLLERS : 1. Size of Channel (mm) 2. Whether channels welded across the length of the tank 3. Size and type of roller (mm) (O) OIL 1. Name of supplier 2. Break down voltage of oil : (kV) i) Filled in tanked transformer ii) In storage tank (to be tested by inspecting officer) 3. Supplier‘s test certificate (enclose copy) (P) (Q) ENGRAVING : 1. Engraving of Sl.No. and name of firm i) On bottom of clamping channel of cor-coil assembly. ii) On side wall and top cover of tank along with date of dispatch. i) MS plate of size 125x125 mm welded on width side of stiffener Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 348 Technical specification ii) Following details engraved (as per approved GTP) (a) Serial Number (b) Name of firm (c) Order No. and Date (d) Rating (e) Name of inspecting Officer (f) Designation (g) Date of dispatch (R) NAME PLATE DETAILS : Whether Name Plate is as per approved drawing (S) COLOUR OF TRANSFORMER : 1. Tank body with smoke gray colour (T) 2. Conservator with white colour CHECKING OF TESTING FACILITIES : (Calibration certificate also to be checked for its validity) TESTS : 1. No Load Current 2. No Load Loss 3. % Impedance 4. Load Losses 5. Insulation Resistance Test 6. Vector Group Test (phase relationship) 7. Ratio and Polarity test relationship 8. Transformer Oil test (Break down voltage) 9. Magnetic Balance 10. Measurement of winding resistance (HV and LV both) 11. Induced over voltage withstand test (Double voltage and Double frequency) 12. Separate source power frequency withstand test at 28kV for HV and 3kV for LV (one minute) 13. Air pressure/Oil leakage test 14. Vacuum Test 16. Unbalanced current test Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 349 Technical specification 16. Temperature rise (Heat Run) Test We have specifically checked the (U) following and found the same as per GTP/ deviations observed as mentioned against each: i) Rustlessness of CRGO lamination used ii) iii) ii) Core steps iii) Core area iv) Core weight v) Winding cross sectional area a) LV b) HV vi) Weight of windings vii) Clearance between winding and wall of tank (mm) a) Length-wise b) Breadth-wise viii) Clearance between top of yoke/top most live part of tap changer to tank cover. a) LV b) HV ix) Details of Neutral formation x) Connections to bushings: a) LV b) HV xi) Slope of tank top xii) Position of mounting of bushings COMPANY‘S INSPECTING OFFICER FIRM‘S REPRESENTATIVE DATE OF INSPECTION: Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 350 Technical specification 1 Annexure - V PROFORMA FOR PRE-DELIVERY INSPECTION OF DISTRIBUTION TRANSFORMER Name of the firm : 2 Details of offer made : (i) Order No. and Date 3 4 5 (ii) Rating (iii) Quantity (iv) Sl. No. of transformers Date of stage inspection of the lot Reference of stage inspection clearance Quantity offered and inspected against the order prior to this lot (A) ACCEPTANCE TESTS TO BE CARRIED OUT SL PARTICULARS NO 1 (a) Ratio Test OBSERVATIONS AB/an BC/bn CA/cn 2 NO load loss measurement W1 W2 W3 TOTAL Multiplying Factor:CT Watt meter Total X MF NET LOSS 3 Load loss measurement W1 W2 W3 TOTAL Multiplying Factors:CT Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 351 Technical specification SL PARTICULARS NO Watt meter OBSERVATIONS PT Total X MF NET LOSS Loss at ambient temperature Loss at 750C (with calculation sheet) (watt) 4 Winding resistance: H.V. (in Ohms) (a) At ambient temperature of _________0C A–B B–C C–A (b) Resistance at 750C. A–B B–C C–A L.V. (in Ohms) (a) At ambient temperature of _________0C a–n b–n c–n (b) Per Phase Resistance at 750C a–n b–n c–n 5 Insulation Resistance (MΩ) HV – LV HV – E LV – E 6 Separate Source Voltage withstand test voltage: HV 28kV for 60 sec. LV 3 kV for 60 sec. 7 Induced over voltage withstand test at double voltage and double frequency 8 No load current at 100 HZ, 866 volts for 60 sec. 90% volts Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 352 Technical specification SL PARTICULARS NO 110% volts 9 Unbalance current 10 Vector group test 11 Percentage Impedance at 750C (enclosed calculation sheets) 12 Transformer oil test (BDV) 13 Oil leakage test 14 Heat run test 15 Bushing clearance (mm) OBSERVATIONS Diagram and readings should be shown in separate sheets. To be carried out once against each order. HV LV (a) Phase to Phase (b) Phase to Earth 16 17 18 19 Comments on compliance by the firm on the modifications done as per stage inspection clearance letter issued. Whether fittings of the order have been varified Whether aluminium die cast silicagel breather with the container is fitted on the transformer offered. Whether engraving of Sl.No and Name of firm on core clamping channel, side wall and top cover of tank has been verified. 20 Whether MS Plate of size 125x125 mm welded on with side of stiffener. 21 Whether engraving of name of firm, Sl.No and Rating of transformer, Order No. and date and date of Despatch on MS Plate. 22 Copy of calibration certificates of metering equipments be enclosed. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 353 Technical specification (B) POINTS TO BE SEEN/DIMENSIONS TO BE NOTED AT THE TIME OF DISMANTLING OF TRANSFORMERS: SL PARTICULARS OBSERVATIONS No. 1 Details of the transformer dismantled for physical verification (a) Rating (KVA) (b) Sl.No. 2 Whether GI Nut Bolts with one spring one plain washer provided for tightening the tank cover. 3 Details of gasket used between top cover and Tank Material: (i) Thickness (mm) (ii) Type of joints 4 Whether core is earthed properly with copper strip (one end should be tightened in between the core laminations and other end bolted on core clamping channel) 5 Connections from winding to bushings (describe the manner in which it has been done) (a) HV (b) LV (c) Formation of Star connection on LV side 6 Winding wire dia and cross sectional area: (a) HV (i) Dia (mm) (ii) Area (sq mm) (b) LV (i) L X W X Nos. of layer (ii) Area (sq mm) 7 Thickness of press board (s) provided between HV coils to cover the tie rods. 8 Whether painted with oil and corrosion resistant paint/varnish (a) Inside of the tank (b) Inside of the conservator tank (c) Core clamping and core base channels (d) Tie rods Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 354 Technical specification SL PARTICULARS No. (e) Core bolts OBSERVATIONS 9 Whether tie rods and core bolts insulated, if yes, material of insulation. 10 Whether flap on inner side of top cover provided to prevent direct falling of oil on core – coil assembly. 11 Method of joints (a) Between HV Coils 12 Whether engraving of Sl. No. and name of firm done on bottom channel of core coil assembly. 13 Diameter of copper wire, used for formation of Delta (should not be less than 1.5 times the dia of conductor). (mm) Whether empire sleeves provided upto to the end portion of HV winding joining to bushing. 14 15 HV coils (a) Inner dia (mm) (b) Outer dia. (mm) 16 LV coil (a) Inner dia (mm) (b) Outer dia. (mm) 17 Core dia 18 Core height including base channel and insulation in between (mm) 19 Leg Center of core 20 Clearance between (a) Core and LV (mm) (b) HV and LV (mm) (c) Phase to Phase of HV coils (mm) (d) Core coil assembly and tank body (mm) (i) Length-wise (ii) Width-wise (e) Top of yoke and top cover (mm) 21 Weight of core only (Kg) Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 355 Technical specification SL PARTICULARS No. 22 Weight of windings (Kg) OBSERVATIONS (a) LV (b) HV 23 Whether core laminations are in one piece, used for (a) Bottom Yoke (b) Top Yoke 24 25 26 27 Specific remarks regarding smoothness and rusting of core used Volume of oil filled (to be done once against the order) Weight of transformer (inclusive of all fittings, accessories, oil etc. complete) Inner dimensions of the tank (a) Length (b) Width (c) Height (i) LV side (ii) HV side 28 Remarks, if any: Note: Please ensure that complete details have been filled in the proforma and no column has been left blank. Signature of Inspecting Officer Signature of Firm‘s Representative (with name and designation) (with name and designation) Date of Inspection: Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 356 Technical specification ANNEXURE –VI SOURCE OF MATERIALS/PLACE OF MANUFACTURE, TESTING AND INSPECTION Sl. Item Source of Place of Place of testing No. Material Manufacture and inspection 1 Core Laminations 2 Aluminum Conductor 3 Insulated winding wires 4 Oil 5 Press boards 6 Kraft paper 7 MS Plates/Angles/Channels 8 Gaskets 9 Bushing HV/LV 10 Paints Signature of Firm Representative: (Name and Designation) Date: Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 357 Technical specification ANNEXURE –VII MCCB BOX WITH CU. BUS BAR WITH CABLE CONNECTION INTERFACE B MS BOX Y R N CU.Cable MCCB BAKELITE SHEET CONNECTOR BAKELITE FIXING NUT RUBBER GLAND OUTGOING CABLE LED INDICATORS FOR TR WINDOW SHED MCCB WINDOW FOR ON/OFF LED INDICATOR FOR MCCB Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 358 Technical Specification 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 ANNEXURE-A (To be submitted as First page of the technical offer) Name & Address of Manufacturer: Is the factory is free from dust pollution: Yes/No Year on which the manufacturing is started: (Voltage grade wise) Voltage grade wise yearly manufactured KVA capacity for last three years (year wise breakup): Voltage level up to which transformers are manufactured: Whether transformers are supplied to APDCL earlier: Yes/NO Are you manufactured Star Rated transformer, if so up to what level: No/Yes ( name the level) Do you have supplied star rated transformers to any utility, if yes, name the Utility and year & quantity of supply (enclosed photo copy of order) : Yes/NO Type test reports are enclosed along with the detail drawing: Yes/NO Name the laboratory where type test were carried out: Is the type test conform to specification as per the bid document: No/Yes Name the Vendors from where CRGO sheets are procured: Type of drying chamber: Is the testing facilities are available as per the specifications: Yes/Partial/No Are all the information attached as per specifications: Yes/Partial Signature of Firm Representative: (Name and Designation) Date: Seal: Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 359 Technical Specification TECHNICAL SPECIFICATION OF 3-Ф Distribution Transformers of 11kV/433-250V, 250, 315, 500 and 630 KVA 1.0 SCOPE 33.5 This section of the specifications is intended to cover requirements for design, engineering, manufacture, testing/inspection at manufacturer‘ works before despatch, forwarding, packing, transporting and delivery at site of outdoor type naturally air-cooled, 11kV/433-250V Distribution Transformers of capacities 250, 315, 500 and 630 KVA complete with all accessories/fittings, LV side protection and spare parts. The bidder shall quote the price of transformer complete with first filling of oil. 34.0 BIDDING 34.1 Each Technical Proposal must be accompanied by each of the following information/ documents with sufficient details along with other documents and information mentioned elsewhere to enable the purchaser to make an appraisal of the quality and suitability of the material and equipment offered. (e) (f) (g) (h) Type test certificates of transformer of identical design from CPRI/ERDA laboratory. The Type test certificates should not be more than 3 (three) years old. The type rest certificates should also be accompanied by the drawings of equipment tested so that the test certificates can be directly linked to the equipments offered. In this regard following points shall also be noted: (i) Equipment which have not been type tested as above shall not be accepted. A promise or agreement by a bidder to have the equipment tested after award of a contract is not acceptable. Type Test reports to be acceptable must relate directly to the equipment offered. Type Test reports for a higher class/rating of equipment are acceptable with a commitment from bidder that the type test will be performed free of charge on the particular equipment after the award of contract. Guaranteed and Other Particulars in the formats given in Schedule - A at the end of this Section. The bid should also be accompanied by manufacturer‘s literatures and brochures. The bidder shall have to submit the Annexure-A as a first page of the technical offer. 34.2 Failure to meet the requirement of this Clause 2.0 shall render a Bid nonresponsive. 35.0 STANDARDS 35.1 The Transformer and associated accessories shall conform to the latest issues of the standards as given below, except to the extent explicitly modified in this specification. (23) CBIP manual on Transformers. Publication no 275 (24) CEA Guidelines for Specification of Energy Efficient Outdoor Type three phase and single phase Distribution Transformers, 2008. (25) Power Transformers IS:2026, IEC 76 (26) Insulating oils for transformers and switchgears IS:335 (27) Bushings for alternating voltages above 1000 V IS:2099 (28) Creepage distance (mm) IS: 3347 (29) Outdoor Bushings IS:3347, DIN 42531 to 33 (30) Specification for low voltage bushings IS:7421 (31) Dimensions for clamping arrangements for bushings IS:4257 (32) Specification for Al Wire rods IS: 5434, ASTM B-233 (33) Specification for Insulating Kraft Paper IS:9335, IEC 554 (34) Specification for Insulating Press Board IS:1576, IEC 641 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 360 Technical Specification (35) Code of practice for installation and maintenance IS:10028 of transformers (36) Guide for loading of oil immersed transformers IS:6600 (37) Paper covered Aluminium conductor IS:6162 (38) Rectangular Electrical conductor for electrical machine IS:6160 (39) Electrical Power connector IS: 5561 (40) Colours for ready mix paints. IS: 5 (41) Ready mixed paint, brushing zinc chromate, priming IS 104 (42) Specification for Copper wire rod IS 12444, ASTM B-49 (43) Testing for steel sheets and strips and magnetic circuits IS-649 35.2 In case equipment conforms to other international standard which ensure equivalent or better performance than that specified under Clause 3.1, then relevant Standards shall be forwarded with the bid. 36.0 GENERAL SERVICE CONDITION 36.1 The climatic conditions at site under which the equipment shall operate satisfactorily are as follows:(a) Maximum temperature of air in shade 50º C (b) Minimum temperature of air in shade: - 2º C (c) Maximum average daily ambient air temperature 400C (d) Maximum yearly weighted average ambient temperature 0 32 C (e) Maximum Humidity: 100% (f) Average of rainy days per annum: 150 (g) Average number of days of thunderstorm per annum: 45 (h) Average number of days of dust storm per annum: 25 (i)Average annual rainfall: (j) Number of months of tropical monsoon per annum: (k) Maximum wind pressure: (l) Altitude (above mean sea level): 2280 mm 5 (May to Sept) 195Kg/m2 200 to 1000 m 37.0 GENERAL TECHNICAL SPECIFICATIONS: 37.1 The Distribution transformer shall be 3-phase; oil immersed and shall have core type construction, and should be suitable for outdoor service in hot and humid tropical climate. 37.2 The transformers and all its accessories shall be designed to withstand without injury, the thermal and mechanical effects of any external short circuit to earth and of short circuits at the terminals of any winding of values and duration specified in IS-2026. 37.3 The transformer shall be capable of being loaded in accordance with IS: 6600. There shall be no limitation imposed by bushings etc. 37.4 The transformer shall be capable of being operated without danger on any tapping at the rated kVA with voltage variation of plus or minus 10% corresponding to the voltage of that tapping with normal temperature rise. The design adopted to achieve this shall be indicated in detail in the offer. 37.5 The transformer shall be suitable for continuous operation with frequency variation of ±5% from normal 50Hz.Combined voltage and frequency variation should not exceed the rated V/f ratio by 10%. 37.6 Transformer shall be capable of withstanding thermal and mechanical stress caused by symmetrical or asymmetrical faults on any winding. The calculation for the same to be submitted along with the offer. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 361 Technical Specification 37.7 Transformer shall accept, without injurious heating, combined voltage and frequency fluctuation, which produces the following over fluxing conditions: i) 125% for 1 minute or 140% for 5 seconds ii) Over fluxing withstand characteristics up to 140% shall be submitted along with the bid. 37.8 The thermal ability to withstand short circuit shall be demonstrated by calculation. 37.9 The maximum flux density in any part of the core and yokes, at normal voltage and frequency of transformer shall be such that the flux density under over voltage condition as per Clause 5.5 above shall not exceed 1.9 Tesla. The detail calculation is to be shown as per Annexure-I. 37.10 The maximum magnetising current at 110% rated voltage shall not be more than 125% of that at 100% rated voltage. Accordingly, the operating flux density for design should be carefully chosen within the stipulated value to achieve the above requirement. The Bidder shall quote the practically achievable no load current at different percentages of rated voltage as per Guaranteed Technical Particulars which will be verified during no load test. 37.11 The maximum current density in any winding shall not exceed 2.50A/sq.mm for Copper and 1.50A/sq.mm for Aluminium. 37.12 The sources of prime materials, place of manufacture, testing and inspection should be shown as per the proforma enclosed in Annexure – VI. 37.13 SUPPRESSION OF HARMONICS The transformers shall be designed with particular attention to the suppression of harmonic voltage, especially the third and fifth, so as to eliminate wave form distortion. 37.14 CENTRE OF GRAVITY The center of gravity of the assembled transformers shall be low and as near to the vertical center line as possible. The transformer shall be stable with or without oil. If the center of gravity is eccentric relating to track either with or without oil, its location shall be shown on the outline drawing. 38.0 GENERAL CONSTRUCTIONAL FEATURES 38.1 GENERAL 38.2 All material used shall be of best quality and of the class most suitable for working under the conditions specified and shall withstand the variations of temperature and atmospheric conditions without distortion or deterioration or the setting up of undue stresses in any part and also without effecting the strength and suitability of the various parts for the work which they have to perform. 38.3 Similar parts, particularly removable ones, shall be interchangeable. 38.4 Pipes, screws, studs, nuts and bolts used for external connections shall be as per the relevant standards. Steel bolts and nuts exposed to atmosphere shall be galvanized. 38.5 Nuts, bolts and pins used inside the transformers and tap changer shall be provided with lock washers or locknuts. 38.6 Exposed parts shall not have any pockets where water can collect. 38.7 Internal design of transformer shall ensure that air/gas is not trapped in any location. 38.8 Material in contact with oil shall be such as not to contribute to the formation of acid in oil. Surface in contact with oil shall not be galvanized or cadmium plated. 38.9 Labels, indelibly marked, shall be provided for all identifiable accessories. All label plates shall be of non corrodible material. 38.10 All internal connections and fastenings shall be capable of operating under overloads and over-excitation, allowed as per specified standards without injury. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 362 Technical Specification 38.11 Transformer and accessories shall be designed to facilitate proper operation, inspection, maintenance and repairs. 38.12 No patching, plugging, shimming or other such means of overcoming defects; discrepancies or errors will be accepted. 39.0 SURFACE PREPERATION & PAINTING 39.1 GENERAL 39.1.1 All paints, when applied in a normal full coat, shall be free from runs, sags, wrinkles, patchiness, brush marks or other defects. 39.1.2 All primers shall be well marked into the surface, particularly in areas where painting is evident and the first priming coat shall be applied as soon as possible after cleaning. The paint shall be applied by airless spray according to manufacturer‘s recommendations. However, where ever airless spray is not possible, conventional spray be used with prior approval of purchaser. 39.2 CLEANING AND SURFACE PREPERATION: 39.2.1 After all machining, forming and welding has been completed, all steel work surfaces shall be thoroughly cleaned of rust, scale, welding slag or spatter and other contamination prior to any painting. 39.2.2 Steel surfaces shall be prepared by shot blast cleaning (IS:9954) to grade Sq.2.5 of ISO 8501-1 or chemical cleaning including phosphating of the appropriate quality (IS :3618) 39.2.3 Chipping, scraping and steel wire brushing using manual or power driven tools cannot remove firmly adherent mill-scale. These methods shall only be used where blast cleaning is impractical. Manufacturer to clearly explain such areas in his technical offer. 39.3 PROTECTIVE COATING 39.3.1 As soon as all items have been cleaned and within four hours of subsequent drying, they shall be given suitable anti-corrosion protection. 39.4 PAINT MATERIAL 39.4.1 Following are the types of paint which may be suitably used for the items to be painted at shop and supply of matching paint to site: Heat resistant paint (Hot oil proof) for inside surface. 39.4.2 For external surfaces one coat of thermo setting powder paint or one coat of epoxy primer followed by two coats of polyurethane paint. These paints can be either air drying or stoving. 39.5 PAINTING PROCEDURE : 39.5.1 All prepared steel surfaces should be primed before visible re-rusting occurs or within 4 hours, whichever is sooner. Chemical treated steel surfaces shall be primed as soon as the surface is dry and while the steel surface is still warm. 39.5.2 Where the quality of film is impaired by excess film thickness (wrinkling, mud cracking or general softness) the supplier shall remove the unsatisfactory paint coating and apply another coating. As a general rule, dry film thickness should not exceed the specified minimum dry film thickness by more than 25%. 39.6 DAMAGED PAINTWORK : 39.6.1 Any damage occurring to any part of a painting scheme shall be made good to the same standard of corrosion protection and appearance as that was originally applied. 39.6.2 Any damaged paint work shall be made good as follows: 39.6.2.1 The damaged area, together with an area extending 25 mm around its boundary, shall be cleaned down to bare metal. 39.6.2.2 A priming coat shall be immediately applied, followed by a full paint finish equal to that originally applied and extending 50 mm around the perimeter of the original damage. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 363 Technical Specification 39.6.2.3 The repainted surface shall present a smooth surface. This shall be obtained by carefully chamfering the paint edges before and after priming. 39.7 DRY FILM THICKNESS : 39.7.1 The maximum extent practicable the coats shall be applied as a continuous film of uniform thickness and free of pores. Overspray, skips, runs, sags and drips should be avoided. The different coats may or may not be the same colour. 39.7.2 Each coat of paint shall be allowed to harden before the next is applied as per manufacturer‘s recommendations. 39.7.3 Particular attention must be paid to full film thickness at the edges. 39.7.4 The requirements for the dry film thickness (DFT) of paint and the materials to be used shall be as given below: Sl.No 1. 2. Paint type Area to be painted No. of coats Thermo setting powder paint Liquid Paint a) Epoxy (primer) b) P.U.Paint (Finish coat) c) Hot oil paint/Varnish inside outside 01 01 Total dry film thickness (min) (microns) 30 60 outside outside inside 01 02 01 30 25 each 35/10 39.8 TESTS FOR PAINTED SURFACE: 39.8.1 The painted surface shall be tested for paint thickness. 39.8.2 The painted surface shall pass the cross hatch adhesion test and impact test as acceptance tests and Salt spray test and Hardness test as type test as per the relevant ASTM standards. Note: The paint work done shall be guaranteed for a minimum period of 5 years from the date of receipt of the equipment. 40.0 TRANSFORMER TANK 40.1 The Transformer tank and cover shall be fabricated from high-grade low carbon plate steel of tested quality. The tank and the cover shall be of welded construction. Minimum thickness of tank bottom and top should be 6 mm and the tank wall should be 4.0 mm. 40.2 The tank plate and lifting lugs shall be of such strength that the complete transformer filled with oil may be lifted by means of lifting shackle. 40.3 All beams, flanges, lifting lugs, braces and permanent parts attached to the tank, shall be welded and where practicable, they shall be double welded. 40.4 The main tank body of the transformer without oil, shall be capable of withstanding pressure of 225 mm of Hg. Permanent deflection, when subjected to vacuum, shall not be more than the values as given below: (All figures in mm) Horizontal length of flat plate Permanent deflection Up to and including 750 5.0 751 to 1250 6.5 1251 to 1750 8.0 1751 to 2000 9.5 2001 to 2250 11.0 2251 to 2500 12.0 2501 to 3000 16.0 Above 3000 19.0 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 364 Technical Specification 40.5 The tank shall further be capable of withstanding a pressure of 0.8 kg/sq.cm (g) and a vacuum of 0.7 kg/sq.cm (g) without any deformation. 40.6 All bolted connections to the tank shall be fitted with suitable oil-tight gaskets, which shall give satisfactory service under the operating conditions and guaranteed temperature rise conditions. Special attention shall be given to the methods of making the hot oil-tight joints between the tank and the cover as also between the tank cover and the bushings and all outlets to ensure that the joint can be remade satisfactorily at site and with ease, with the help of semi-skilled labour. Where compressible gaskets are used, stops shall be provided to prevent over-compression. The top cover gaskets should not be exposed to atmosphere. 40.7 Suitable guides shall be provided for positioning the various parts during assembly or dismantling. 40.8 Tank stiffeners shall be provided for general rigidity and these shall be designed to prevent retention of water. 41.0 TANK COVER 41.1 The transformer top shall be provided with a detachable tank cover with bolted flanged gasket joint. The surface of the cover shall be suitably sloped so that it does not retain rainwater. 41.2 Each tank cover shall be of adequate strength and shall not distort when lifted. Inspection opening shall be provided as necessary to give easy access to bushing. Each inspection opening shall be of ample size for the purpose for which it is provided, The tank cover and inspection cover shall be provided with suitable lifting arrangements. 41.3 The tank cover shall be fitted with pockets for thermometer (at the center of the top cover). 41.4 The tank cover is to enclose the flanged gasket. 41.5 The thermometer pockets shall be fitted with a captive screw top to prevent the ingress of water. 41.6 Bushings, covers of inspection openings, etc. shall be designed to prevent ingress of water into or leakage of oil from the tank. 41.7 HV bushings are to be mounted on the top cover. However, for maintenance purpose the, the termination point of HV leads should have easy accessibility. All bolted connection shall be fitted with weather proof, hot oil resistant gasket in between, for complete oil tightness. If gasket is compressible, metallic stoppers shall be provided to prevent over compression. 42.0 UNDER CARRIAGE 42.1 The transformer tank shall be supported on steel structure with detachable forged steel flanged wheels suitable for moving the transformer completely filled with oil. 42.2 Suitable locking arrangement along with foundation bolts shall be provided for the wheels to prevent accidental movement of the transformer. 42.3 The suitable clamping device should be provided for top and bottom of the transformer in case where it will be mounted on pole. The clamping device should suitable for both PSC and Steel Tubular poles. The clamps should be galvanized as per relevant IS. 42.4 To prevent movement during earthquake, clamping devices shall be provided for fixing transformer to the foundation. The bidders shall supply necessary bolts for embedding of the concrete foundation. The arrangement shall be such that the transformer can be fixed to or unfastened from these bolts as desired. The fixing of the transformers to the foundations shall be so designed to withstand the seismic events to the extent that a static co-efficient of 0.5g, applied to the Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 365 Technical Specification 43.0 43.1 43.2 direction of least resistance to that loading will not cause the transformer or clamping devices as well as bolts to be over stressed. CORE (MAGNETIC CIRCUIT) AND CONSTRUCTIONAL FEATURES OF CORE The magnetic circuit shall be constructed from high grade cold rolled non-ageing grain oriented silicon steel lamination of M4 or better with thickness of less than or equal to 0.27 mm Only primary core material is to be used. The bidder should offer the core for inspection and approval by the purchaser or third party Inspection Agency during the manufacturing stage. Bidder‘s call notice for the purpose should be accompanied with the following document as applicable as a proof towards use of Prime Core material. (f) Invoice of supplier, (g) Mill‘s test certificate. (h) Packing list, (i) Bill of loading, (j) Bill of entry certificate to customs Core material should be directly procured from either the manufacturer or their accredited marketing organisation of repute and not through any agent. Bidder to have in house numeric controlled Core cutting facility for better control of quality and also to avoid any mixing of Prime Core material with second‟s materials. Core cutting machine number and drawings are to be furnished. The following procedure is to be adopted for those manufacturers who have no in-house core-cutting facility: (1) The bidder should specify the grade, thickness of core material in the offer along with submission of all graphs/ documents, relating to the grade of core material, offered by them. (2) The documents, as mentioned above should be submitted to APDCL along with the following informations: a) Purchase order No. & Date. b) No. of packed coils with package Nos. c) Gross weight. d) Net weight e) Port of loading. f) Port of discharge. g) Name of the ocean vessel. h) Grade and thickness of core material. i) Any other information, as mentioned on the body of packed coils. (3) The bidder in its offer will mention the names of at least three Sub-vendors, to whom they intend to assign their core cutting. Such sub-vendors should have been approved by other Electricity Boards/ Electrical utilities and are accredited by some International recognised certification body like ISO: 9000 etc., to ensure that a minimum quality parameters and tolerances are maintained. The experience, the details of core-cutting facilities, finishing and testing facilities etc., as available with such sub-vendors should be clearly outlined in the bid. (4) On award of contract, the Transformer Manufacture is to assign the corecutting to such sub-vendor(s) for which approval is to be given by APDCL or its successor companies. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 366 Technical Specification 11.3 The laminations shall be free of all burrs and sharp projections. Each sheet shall have an insulating coating resistant to the action of hot oil. 11.4 The design of magnetic circuit shall be such as to avoid static discharges, development of short circuit paths within itself or to the earthed clamping structure and production of flux component at right angle to the plane of the lamination which may cause local heating. 11.5 All steel sections used for supporting the core shall be thoroughly shot or sand blasted, after cutting, drilling and welding. 11.6 The finally assembled core with all the clamping structures shall be free from deformation and shall not vibrate during operation. The core shall be carefully assembled and rigidly clamped to ensure adequate mechanical strength. 11.7 The core clamping structure shall be designed to minimize eddy current loss. 11.8 The framework and clamping arrangements shall be securely earthed. 11.9 The supporting frame work of the cores shall be so designed as to avoid the presence of pockets which would prevent complete emptying of the tank through the drain valve or cause trapping of air during filling. 11.10 The oxide/silicate coating given on the core shall be adequate; however, laminations can be insulated by the manufacturers if considered necessary. 11.11 All parts of the cores shall be of robust design capable of withstanding any shocks to which they may be subjected during lifting, transport, installation and service. 11.12 Adequate provision shall be made to prevent movement of the core and winding relative to the tank during transport and installation or while in service. 11.13 No-load current shall not exceed 1.5% of full load current and will be measured by energizing the transformer at 433 volts, 50Hz frequency. Increase of voltage of 433 volts by 12.5% shall not increase the no-load current by 4% (maximum) of full load current. 12.0 INTERNAL EARTHING 12.3 EARTHING OF CORE CLAMPING STRUCTURE iii) All internal metal parts of the transformer, with the exception of individual laminations, core bolts and their individual clamping plates shall be earthed. iv) The top clamping structure shall be connected to the tank by a copper strap. The bottom clamping structure shall be earthed by one or more of the following methods: c) By connection through vertical tie-rods to the top structure. d) By a connection to the top structure on the same side of the core as the main earth connection to the tank. 12.4 EARTHING OF MAGNETIC CIRCUIT ii) The magnetic circuit shall be connected to the clamping structure at one point only 12.5 SIZE OF EARTHING CONNECTIONS Earthing strip should be tin copper and size will be approved by the purchaser after getting suppliers offer. 13.0 WINDING 13.3 GENERAL xviii) The current density of in any part of the windings shall not exceed 2.50 Amps/Sq. mm. for copper and 1.50 Amps/Sq.mm for aluminium. xix) All windings shall be made of electrolytic high conductivity aluminium/copper for transformer of capacity 250 KVA and copper above 250kVA, and shaped and braced to provide for expansion and contraction due to temperature changes. Winding shall be fully insulated as defined in IS: 2026. All neutral points shall be insulated for the voltage specified in Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 367 Technical Specification IS: 2026. The winding shall be so designed that all coil assemblies of identical voltage, rating shall be interchangeable. xx) Number of HV coils per phase should not be less than six (6) with the type Crossover/Sectional. Number of secondary (LV) coil should be one with spiral type winding construction. xxi) Coil shall be clamped by 8 (eight) numbers of stud and the size should not be less than 20 mm. xxii) LV winding shall be such that neutral formation will be at top. xxiii) Conductor covering for HV winding shall be TPC with minimum 0.35 mm thickness and for LV conductor TPC with minimum 0.50 mm thickness. xxiv) Interlayer insulation shall be Nomex/Epoxy dotted Kraft Paper. xxv) Distribution Transformers shall be designed to withstand the impulse and power frequency test voltages as per IS: 2026. xxvi) Magnitude of impulse surges transferred from HV to LV windings by induction and capacitance coupling shall be limited to B.I.L. of LV winding. xxvii) The completed core and coil assembly shall be dried in vacuum at not more than 0.5mm of mercury absolute pressure and shall be immediately impregnated with oil after the drying process to ensure the elimination of air and moisture within the insulation. Vacuum may be applied in either vacuum oven or in the transformer tank xxviii) Winding shall be subjected to a shrinking and seasoning process, so that no further shrinkage occurs during service. Adjustable devices shall be provided for taking up possible shrinkage in service. xxix) Winding shall not contain sharp bends which might damage the insulation or produce high dielectric stresses. No strip conductor wound on edge shall have width exceeding six times the thickness. xxx) Varnish application on coil windings may be given only for mechanical protection and not for improvement in dielectric properties. In no case varnish or other adhesive be used which will seal the coil and prevent evacuation of air and moisture and impregnation by oil. xxxi) The winding shall be designed to reduce to a minimum, the out-of balance forces in the transformers at all voltage ratios. xxxii) The insulation of transformer windings and connection shall be free from insulating composition liable to soften, ooze out ,shrink or collapse during service and be non catalytic and chemically inactive in transformer oil. xxxiii) The coil clamping arrangement and the finished dimensions of any oil ducts shall be such as will not impede the free circulation of oil through the ducts. xxxiv) Terminals of all windings shall be brought out of the tank through bushings for external connections xxxv) The winding shall be so designed that all coil assemblies of identical voltage ratings shall be interchangeable and field repairs to the winding can be made readily without special equipment. The coils shall have high dielectric strength xxxvi) All leads from windings to terminals shall be rigidly supported to prevent injury from vibration. Guide tubes may be used where possible. 13.4 BRACING OF WINDINGS 13.4.1 The windings and connections of all transformers shall be braced to withstand shocks, which may occur during transport or due to switching and other transient conditions during service. v) Coil clamping rings shall be of suitable insulating material. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 368 Technical Specification vi) 14.0 14.3 14.4 14.5 14.6 14.7 15.0 15.1 15.2 16.0 16.1 16.2 16.3 16.4 Permanent current carrying joints in the windings and leads shall be welded or brazed. Clamping bolts for current carrying parts inside oil shall be made of oil resistant material which shall not be affected by acidity in the oil steel bolts, if used, shall be suitably treated. vii) Adequate barriers shall be provided between coils and core and between high and low voltage coil. End turns shall have additional protection against abnormal line disturbances. viii) Coil should be clamped by 8 (eight) numbers of 20 mm dia tie rods between top and bottom yoke support channels BOLTS AND NUTS Steel bolts and nuts exposed to atmosphere with suitable finishes like cadmium plated or zinc plated passivated will be used for diameter above 6 mm. Brass bolts and nuts of less than 6 mm shall not be used for electrical connections. Where smaller size is required, stainless steel or phosphor bronze may be used. Sizes and threads will be as per Indian Standard, wherever, available, otherwise equivalent British Standard will be followed. All nuts and bolts and pins shall be locked in position with the exception of those external to the transformer. The bolts shall be fitted in such a manner that in the event of the nut working loose and falling off, the bolts will remain in position. All bolts, nuts and washers in contact with non-ferrous parts which carry current and are exposed to atmosphere shall be of phosphor bronze, where transfer of current is through bolts. If bolts and nuts are placed that are in accessible by means of ordinary spanners, suitable special spanners shall be provided by the supplier. INSULATION MATERIAL: Electrical grade insulation epoxy dotted Kraft Paper/Nomex and pressboard of standard make or any other superior material subject to approval of the purchaser shall be used. All spacers, axial wedges / runners used in windings shall be made of precompressed Pressboard solid, conforming to type B 3.1 of IEC 641 – 3 – 2 . For cross-over coil winding of HV all spacers shall be properly sheared and dovetail punched to ensure proper locking. All axial wedges / runners shall be properly milled to dovetail shape so that they pass through the designed spacers freely. Insulation shearing, cutting, milling and punching operations shall be carried out in such a way, that there should not be any burr and dimensional variations. INSULATING OIL The insulating oil for the transformers shall be of EHV grade, generally conforming to IS: 335. No inhibitors shall be used in the oil. The quantity of oil required for the first filling of the transformer and its full specification shall be stated in the bid. The design and materials used in the construction of the transformer shall be such as to reduce the risk of the development of acidity in the oil. The supplier shall warrant that oil furnished is in accordance with the following specifications. a) Appearance : The oil shall be clear and transparent and free from suspended matter or sediment b) Density at 20oC Max: 0.89g/cm3 o c) Kinematic Viscosity at 27 C Max: 27 CST d) Interfacial at 27oC Min.: 0.03 N/m e) Flash Point: 140oC f) Pour Point Max: -6oC g) Neutralisation Value: 0.03 mg/KOH/g Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 369 Technical Specification (Total Acidity) Max h) Electric Strength: 60 kV (Breakdown Voltage) Min. i) Dielectric dissipation factor: 0.05 tan delta at 90oC Max j) Minimum specific resistance: 1 x 1012 ohm cm (resistivity), at 90oC Min. k) Oxidation Stability i) Neutralisation value after Max: 0.40 mg/KOH/g ii) Total sludge after oxidation max: 0.10% by weight l) Presence of oxidation Inhibotor: The oil shall not contain anti-oxidant Additives m) Water content Max: 25 ppm 17.0 ACCESSORIES & FITTINGS) 17.1 BUSHINGS: 17.1.1 The bushing shall conform to the relevant standards specified and shall be of outdoor type. The bushing rods and nuts shall be made of brass material 12 mm diameter for HT bushings. The tests as per latest IS:2099 and IS:7421 shall be conducted on the transformer bushings. 17.1.2 For 11 KV, 17.5 kV class bushing and for 0.433 kV, 1.1 kV class bushing shall be used. 17.1.3 Bushing can be of porcelain/epoxy material. Polymer insulator bushings conforming with relevant IEC can also be used. LV side bushings shall invariably be either of epoxy material or polymeric type. The bidder is to name at least 2/3 vendors of repute who are presently manufacturing epoxy/polymeric bushings and APDCL will select the vendor from those of offered at the time of detail engineering. 17.1.4 Dimensions of the bushings of the voltage class shall conform to the Standards specified and dimension of clamping arrangement shall be as per IS:4257. 17.1.5 Minimum external phase to phase and phase to earth clearances of bushing terminals shall be as follows : Voltage Clearance Phase to phase Phase to earth 11 kV 255 mm 140 mm 0.433 75 mm 40 mm kV 17.1.6 Brazing of all inter connections, jumpers from winding to bushing shall have cross section larger than the winding conductor. All the Brazes shall be qualified as per ASME, section-IX. 17.2 TERMINAL CONNECTORS : 17.2.1 The HV bushing stems shall be provided with suitable terminal connectors as per IS: 5082 so as to connect the jumper without disturbing the bushing stem. Connectors shall be with eye bolts so as to receive conductor for HV. Terminal connectors shall be type tested as per IS:5561. 17.2.2 Bird guards are to be provided for all HV bushings. 17.2.3 The terminal connectors to be supplied for both H.V. and L.V. side shall be universal type suitable for both horizontal and / or vertical take off. 17.2.4 The type of terminal connector, size of connector, material, and type of installation shall be approved by the APDCL, as per installation requirement while approving the equipment drawings. 17.3 EARTHING TERMINAL: Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 370 Technical Specification 17.3.1 Two earthing pads (each complete with two nos. (2) tapped holes, M 8 bolts, plain and spring washers) suitable for connection to 40x6 mm galvanised steel flat shall be provided each at position close to the two (2) diagonally bottom corners of the tank. Earthing strip up to the ground level shall be provided by the bidder. 18.0 Protection & Measuring Devices A) Conservator Tank vii. The conservator tank shall have adequate capacity between highest and lowest visible levels to meet the requirement of the expansion of the total cold oil volume in the transformer from minimum ambient temperature to 90°C. The total volume of conservator shall be 10% of total oil in the transformer. viii. The conservator feed pipe shall be extended 25 mm upwards from the conservator bed so that a sump is created. ix. The conservator should have one oil filling hole of 32 mm size with gasketed cover. One air release plug of 15mm size will be required. x. The conservator tank shall be bolted into position so that it can be removed for cleaning purposes. xi. The conservator tank shall be fitted with prismatic oil level gauge with minimum and maximum marking. xii. The conservator tank shall be provided in a position not to obstruct the electrical connections to the transformers. B) Pressure Relief Device Pressure relief device may be provided at suitable locations which shall be of sufficient size for rapid release of any pressure that may be generated in the tank and which may result in damage to the equipment. The device shall operate at the static pressure of less than the hydraulic test pressure of transformer tank. It shall be mounted directly on the tank. C) Oil Preservation Equipment (i) Oil Sealing Breather The conservator shall be fitted with a dehydrating filter breather. It shall be so designed that, 1) Passage of air is through a dust filter & Silica gel 2) Silica gel is isolated from atmosphere by an oil seal. 3) Moisture absorption indicated by a change in colour of the crystals can be easily observed from a distance. 4) Breather is mounted not more than 1200 mm above rail top level. 5) The breather should have at least 1000 gm of silica gel. 19.0 RADIATORS & VALVES 19.1 RADIATORS iii) Radiators shall be of press steel having thickness of 1.2 mm Cold Rolled Continuously Annealed (CRCA) sheet. and design should be such that all painted surface can be thoroughly cleaned by hand. iv) The inlet header of Radiators should be put below the LV bushings in such a way that in the event of oil leakage from LV bushings, the circulation of oil through radiators are continuing. The arrangement to be demonstrated at the time of detail engineering and will be verified during stage inspection. Failure of this arrangement will lead to total rejection of offered lot. 19.2 VALVES 19.2.1 Each transformer shall be provided with following valves on the tank: c) One fully pilfer proof valve below the top cover.. d) One 15 mm air release plug. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 371 Technical Specification 20.0 FITTINGS AND ACCESORIES 20.1 The following fittings shall be provided on each transformer: o) Conservator fitted with oil filling hole and cap. p) Prismatic type oil gauge q) Silica gel breather with oil seal. r) Pressure relief device for main tank. s) Pocket on tank cover (placed at mid position) for thermometers. t) 9 kV, 5 KA lightning arrestors on HT side – 3 No. u) Oil temperature indicator (for 500kV and above) v) Valves :i) Valve (32mm) shall be of globe type . w) Eearthing terminals with lugs- 2 nos. x) Rating and diagram plate, non-detachable. y) Lifting lugs for main tank and top cover. z) Top tank clamping aa) Inspection cover. bb) Terminal connectors on the HV/LV bushing cc) Bi-directional flanged rollers with locking and bolting device. dd) Base channel of 100 x 50 mm, 460 mm long with holes to make them suitable for fixing on a platform or plinth. ee) 5 (five) year guarantee plate of non-detachable type. 21.0 MISCELLANEOUS iii) Padlocks along with duplicate keys as asked for valves‘ iv) Foundation bolts for wheel locking devices of Transformer shall be supplied by the Supplier. v) The LA should be clamped to HV side bushing with a galvanized earth strip of size 40x5 mm with two nos of M8 size bolt hole along with galvanized nut & bolts and the strip should run near to pole for pole mounted transformer so that the riser from the ground can be connected properly. LA with polymer insulator housing (as per relevant IEC) is to be offered. LA with porcelain casing will be rejected. Preferred manufacturer list for procurement of 9kV, 5kA, metal oxide, distribution class LA shall be from CGL/Oblum/Rechem/LAMCO. ii) NAME PLATE Transformer rating plate shall contain the information as given in clause 15 of IS-2026 (Part-I). The details on rating plate shall be finalised during the detailed engineering. 22.0 LOSSES 22.1 The bidder shall guarantee individually the no-load loss and load loss without any positive tolerance. The bidder shall also guarantee the total losses at 50% and 100% load condition (at rated voltage and frequency and at 75 0C). Table: I Rating (KVA) Max. No-Load loss (Watts) Max. Load loss (Watts) at 750C 250 430 2600 315 550 2200 500 700 3600 630 850 4600 Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 372 Technical Specification Table: II Rating (KVA) Max. Losses at 50% loading Max. Losses at 100% loading (Watts) (Watts) at 750C 250 1050 3320 315 1100 3630 500 1600 5500 630 2000 6640 The above losses are maximum allowable and there would not be any “+ve” tolerance. Bids with higher losses than the specified values would be treated as non responsive. Transformers with losses less than those specified above will be capitalized during bid evaluation process as per Clause No 22.5. CAPITALISATION OF LOSSES AND LIQUIDATED DAMAGES FOR EXCESSIVE LOSSES: 22.2 For the purpose of penalty computation, the test figures of the no-load and the total losses of each transformer will be compared with the corresponding guaranteed figures. 22.3 Since IS: 2026 allows certain tolerances on the transformer losses, the bidders are requested to indicate whether the figures given for guaranteed losses in the schedule of guaranteed technical particulars are with or without such tolerances. If tolerances are applicable, the limits for the same should be indicated. In the absence of any information to this effect, the figures for no-load losses and load losses will be increased by 10% as provided in the IS. Any change in the figures assigned for transformer losses will not be permitted after opening of bids and bid evaluation will be carried out on the basis of information made available at the time of bid opening. 22.4 Penalties will be applicable if any one or more test loss figures of no-load loss and total losses exceed the corresponding guaranteed figures. The penalties will be calculated as follows: (g) For No-load loss, Penalty (in rupees) = {Wi (t) – Wi (g)} x 2R1. (h) For load loss, Penalty (in rupees) = {WT (t) – Wi (t) - WI (g)} x 2R2 Where, WT (t) = Total loss (test value) in W. WT (g) = Total loss (guaranteed value) in W. Wi (t) = No-load loss (test value) in W. Wi (g) = No-load loss (guaranteed value) in W. W1 (g) = Load loss (guaranteed value) in W.( Copper loss ) R1 = Rs.328/R2 = Rs.181/22.5 For the purpose of comparison of the different bids, the capitalised cost of each transformer shall be considered. Capitalised cost of the transformer for the purpose of tender evaluation only shall be calculated as given below: Capitalised cost in Rs = IC+328 Wi+181 WI(g)) Where, IC= Quoted price of transformer in Rs Wi(g) = Guaranteed no load loss in Watt WI(g)= Guaranteed load loss (copper loss) in Watt 22.6 The loss figures (both guaranteed & test) for the purpose of calculation shall be at rated frequency and voltage and at principal tap and 75º C. 22.7 If losses are quoted with tolerance limit, then upper positive value will be considered for capitalization. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 373 Technical Specification 22.8 Calculation of detail losses including flux density and no load current are to be furnished for copper loss, iron loss indicating corresponding copper weight and core weight and considering all parameters and also supported by the drawings showings details of diameter and height of winding and core duly signed by manufacturer‟s design personnel. The loss calculation is to be shown as per proforma in Annexure – II. 23.0 Temperature rise: The temperature rise over ambient shall not exceed the limit given below: 23.1 Top oil temperature rise measured by thermometer : 350C 23.2 Winding temperature rise measured by resistance method : 400C Bids not meeting the above limits of temperature rise will be treated as non-responsive. 24.0 MCCB BOX 24.1 MCCB of defined rating and make shall have to be put for LV side protection. The specification of MCCB and the box shall be as per Schedule-C. 25.0 TESTING AND INSPECTION 25.1 TESTS (ix) The Supplier shall carry out a comprehensive inspection and testing programme during manufacture of the transformer. A detail of inspection is given in this specification. The manufacturer will submit a testing and inspection plan at the time of bidding. (x) The procedure for testing shall be in accordance with IS 1180/2026 as the case may be except for temperature rise test. (xi) The supplier shall carry out all routine tests on each transformers. (xii) Special tests other than type and routine tests, as agreed between purchaser and bidder shall also be carried out as per the relevant standards. (xiii) Before dispatch each of the completely assembled transformers shall be subjected to the routine tests at the manufacturer‘s works. (xiv) The requirements of on site tests are as listed in these specifications. (xv) Certified test report and oscillograms shall be furnished to the Purchaser for evaluation. The Supplier shall also evaluate the test results and rectify the defects in the equipment based on his and the Purchaser‘s evaluations of the tests without any extra charges to the Purchaser. Manufacturer‘s Test Certificates in respect of all associated auxiliary and ancillary equipment shall be furnished. (xvi) The bidder shall state in his proposal the testing facilities available at his works. In case full testing facilities are not available, the bidder shall state the method proposed to be adopted so as to ascertain the transformer characteristics corresponding to full capacity testing. 25.1.1 ROUTINE TESTS: (To be conducted on each transformer) 25.1.1.1 Ratio, polarity, phase sequence and vector group. 25.1.1.2 No Load current and losses at services voltage and normal frequency. 25.1.1.3 Load Losses at rated current and normal frequency. 25.1.1.4 Impedance Voltage test. 25.1.1.5 Resistance of windings at each tap. 25.1.1.6 Insulation Resistance. 25.1.1.7 Induced over voltage withstand test. 25.1.1.8 Separate source voltage withstand test. 25.1.1.9 Neutral current measurement- The value of zero sequence current in the neutral of the star winding shall not be more than 2% of the full load current. 25.1.1.10 Oil samples (one sample per lot) to comply with IS 1866. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 374 Technical Specification 25.1.1.11 Measurement of no load losses and magnetizing current at rated frequency and 90%, 100% and 110% rated voltage. 25.1.1.12 Pressure and vacuum test for checking the deflection. 25.1.2 TYPE TESTS TO BE CONDUCTED 0N ONE UNIT: 25.1.2.1 Temperature rise test. 25.1.2.2 Impulse voltage test: with chopped wave of IS 2026 Part-III, BIL should be 95 KV peak. 25.1.2.3 Short circuit withstand test: Thermal and dynamic ability. 25.1.2.4 Air Pressure Test: As per IS – 1180. 25.1.2.5 Magnetic Balance Test. 25.1.2.6 Un-balanced current test: The value of unbalanced current indicated by the ammeter shall not be more than 2% of the full load current. 25.1.2.7 Noise level measurement. 25.1.2.8 Measurement of zero-phase sequence impedance. 25.1.2.9 Measurement of Harmonics of no-load current. 25.1.2.10 Transformer tank shall be subjected to specified vacuum. The tank designed for vacuum shall be tested at an internal pressure of 0.35 Kg/cm2 absolute (250 mm of Hg) The permanent deflection of flat plates after the vacuum has been released shall not exceed the value given below: Horizontal length of flat plate Permanent deflection Up to and including 750 5.0 751 to 1250 6.5 1251 to 1750 8.0 1751 to 2000 9.5 2001 to 2250 11.0 2251 to 2500 12.0 2501 to 3000 16.0 Above 3000 19.0 25.1.2.11 25.1.2.12 25.1.2.13 25.1.2.14 25.1.2.15 Pressure relief device test. Short Circuit Test and Impulse Voltage Withstand Tests: In case the transformers proposed for supply against the order are not exactly as per the tested design, the supplier shall be required to carry out the short circuit test and impulse voltage withstand test at their own cost in the presence of the representative of the purchaser. The supply shall be accepted only after such test is done successfully, as it confirms on successful withstand of short circuit and healthiness of the active parts thereafter on un-tanking after a short circuit test. Apart from dynamic ability test, the transformers shall also be required to withstand thermal ability test or thermal withstand ability will have to be established by way of calculations. It may also be noted that the APDCL reserves the right to conduct short circuit test and impulse voltage withstand test in accordance with the IS, afresh on each ordered rating at purchaser cost, even if the transformers of the same rating and similar design are already tested. This test shall be carried out on a transformer to be selected by the purchaser either at the manufacturer‘s works when they are offered in a lot for supply or randomly from the supplies already made to purchaser‘s stores. The findings and conclusions of these tests shall be binding on the supplier. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 375 Technical Specification 25.1.2.16 25.1.3 25.1.3.1 25.1.3.2 25.1.3.3 25.1.3.4 25.1.3.5 25.2 25.2.1 25.2.1.1 25.2.2 25.2.2.1 25.2.2.2 25.2.2.3 25.2.3 Type test certificates for the tests carried out on prototype of same specifications shall be submitted along with the bid. The purchaser may select the transformer for type tests randomly. ACCEPTANCE TEST: At least 10% transformers of the offered lot (minimum of one) shall be subjected to the following routine/acceptance in presence of APDCL‘s representative at the place of manufacture before dispatch without any extra charges. The testing shall be carried out in accordance with IS 1180 and IS 2026. Checking of weights, dimensions, fittings and accessories, tank sheet thickness, oil quality, material, finish and workmanship as per GTP and contract drawings. Physical verification of core coil assembly and measurement of flux density of one unit of each rating, in every inspection with reference to short circuit test report. Temperature rise test on one unit of the total offered quantity. At least one transformer of the supplied lot shall be subjected to tests by a third party (preferably ERDA or CPRI) at the purchaser’s cost. In case of Failure in such test, the entire lot will be rejected by APDCL and the cost of the tests will have to be borne by the supplier. INSPECTION Inspection and testing of transformer oil: To ascertain the quality of transformer oil, the original manufacturer‘s test report should be submitted at the time of inspection. Arrangement should also be made for testing of transformer oil, after taking out the sample from manufactured transformers and tested in the presence of APDCL‘s representative. STAGE INSPECTION: To ensure about the quality of transformers, the inspection shall be carried out by the APDCL‘s representative at following two stages:During receipt of raw material or any time during the process of manufacture/assembly as desired by APDCL. At finished stage i.e. transformers are fully assembled and are ready for dispatch. The stage inspection shall be carried out in accordance with Annexure – IV. After the main raw-material i.e core and coil material and tanks are arranged and transformers are taken for production on shop floor and a few assembly had been completed, the firm shall intimate the APDCL in this regard, so that an officer for carrying out such inspection could be deputed, as far as possible within seven (7) days from the date of intimation. During the stage inspection a few assembled core shall be dismantled to ensure that the CRGO laminations used are of good quality. Further, as and when the transformers are ready for dispatch, an offer about the readiness of transformers, for final inspection for carrying out tests as per relevant IS shall be sent by the firm along with Routine Test Certificates. The inspection shall normally be arranged by the APDCL at the earliest after receipt of offer for pre-delivery inspection. The proforma for pre delivery inspection of Distribution Transformers is placed at Annexure – V. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 376 Technical Specification 25.2.4 25.2.5 25.2.6 25.2.7 25.2.8 In case of any defect/defective workmanship observed at any stage by the APDCL‘s Inspecting Officer, the same shall be pointed out to the firm in writing for taking remedial measures. Further processing should only be done after clearance from the Inspecting Officer/APDCL. All tests and inspection shall be carried out at the place of manufacture unless otherwise specifically agreed upon by the manufacturer and APDCL at the time of purchase. The manufacturer shall offer the Inspector representing the APDCL all reasonable facilities, without charges, to satisfy him that the material is being supplied in accordance with this specifications. This will include Stage Inspection during manufacturing stage as well as active part inspection during Acceptance Tests. APDCL shall have every right to appoint a third party inspection to carry out the inspection process. The APDCL has the right to have the test carried out at his own cost by an independent agency wherever there is a dispute regarding the quality supplied. APDCL has right to test 1% of the supply selected either from the stores or field to check the quality of the product. In case of any deviation APDCL has every right to reject the entire lot or penalize the manufacturer, which may lead to blacklisting, among other things. Test Reports for bought out items: The supplier shall submit the test reports for all bought out/sub contracted items for approval. Bucholz relay, Oil temperature indicators, Bushings any other item required to complete the works. Porcelain, bushings, insulating oil and other associated equipment shall be tested by the supplier in accordance with relevant IS. If such equipment are purchased by the supplier on a sub-contract, he shall have them tested to comply with these requirements. 25.3 Test Reports to be submitted on the following factory test prior to inspection: i) All standard routine tests in accordance IS: 2026 shall be carried out on each transformer.. vi) Following additional tests shall also be carried out as routine tests on each transformer: c) Magnetic Circuit Test d) Oil leakage test on transformer vii) Following type tests shall be conducted on one transformer of each rating: c) Temp. rise test as per IS: 2026 (Part-I). This test shall be carried out at the lowest tap. d) Lightning Impulse Test shall be carried out in accordance with IS2026 on one transformer of each rating. viii) Six (6) sets of certified test reports and oscillographs shall be submitted for evaluation prior to despatch of the equipment. The supplier shall also evaluate the test results and shall correct any defect indicated by his and Purchaser‘s evaluation of the tests without charge to the Purchaser. ix) All auxiliary equipment shall be tested as per the relevant IS. Test certificates shall be submitted for bought out items. . 25.4 TANK TESTS c) Routine Tests i) Fabrication Stage Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 377 Technical Specification d) 25.5 i) ii) iii) The tank shall be tested for leakage by being completely filled with air and applying a pressure equal to the normal pressure plus 35 KN/m 2 measured at the base of the tank. The pressure shall be maintained for a period of not less than one hour and during that time no leak shall occur. ii)Transformer assembly stage Oil pressure test to be conducted on tank and all other accessories and assembled for routine test by being completely filled with oil at a pressure equal to the twice the normal head of oil or to normal pressure plus 35 KN/m2 whichever is lower . The pressure shall be maintained for a period of eight hour and during that time no leak shall occur. Type Test Pressure Test Where required by the Purchaser, one transformer tank of each size together with its radiator, conservator vessel and other fittings shall be subjected to a pressure corresponding to twice the normal head of oil or to the normal pressure plus 35 KN/m 2 whichever is lower, measured at the base of the tank and maintained for eight hours during which no leakage shall occur. PRE-SHIPMENT CHECK AT MANUFACTURERS WORKS: Check for proper packing and preservation of accessories like radiators, bushings, explosions vent, dehydrating breather, rollers, buchholz relay, fans, control cubicle connecting pipes & conservator etc. Check for proper provision of bracing to arrest the movement of core and winding assembly inside the tank. Gas tightness test to conform tightness. 26.0 RECEIPT AND STORAGE CHECKS j. Check and record condition of each visible parts of the transformers etc. for any damage. k. Check for oil and any leakage of oil from the transformer tank, radiators etc. l. Visual check HV/ LV bushings for any crack. m. Check for IR between HV-E, LV-E and HV – LV. n. Check for oil BDV and water content. o. Thermometer pockets are to be filled with oil. p. Colour of Silica gel is blue q. Bushing arcing horn is set correctly for required gap distance. r. Oil is at correct level in the bushing, conservator and tank. 27.0 REJECTION 27.1 The Purchaser may reject any transformer if during tests or service any of the following conditions arise: v) No load loss exceeds the guaranteed value by 20% or more. vi) Load loss exceeds the guaranteed value by 20% or more. vii) Maximum losses at 50% loading exceeds the prescribed value. viii) Impedance value exceeds the guaranteed value by ( -) 10% or more. ix) The difference in impedance values of any two phases during single phase short circuit impedance test exceeds 2% of the average value guaranteed by the vendor. v) Oil or winding temperature rise exceeds the specified value. vi) Transformer fails on impulse test. vii) Transformer fails on power frequency voltage withstand test. viii) Transformer is proved to have been manufactured not in accordance with the agreed specifications. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 378 Technical Specification 28.0 DRAWINGS and CALCULATIONS FOR SUBMISSION WITH THE BID 28.1 The Bidder shall furnish with his bid following drawings incorporating the details mentioned hereunder. l) General outline drawing showing dimensions and overall dimensions, sectional view, core and coil assembly drawing, net weights and shipping weights, quantity of insulating oil, spacing of wheels, location off load tap changers etc. m) Details of the sectional view of core and winding showing the core frame size, coil dia and length, conductor size, lead support etc. n) Hot spot temperature calculation. o) Demonstration to withstand thermal ability as per IS:2026 p) Calculation of thermal time constant. q) Calculation for thermal and mechanical stress caused by symmetrical or asymmetrical faults on any winding. g) Calculation of detail losses including flux density and no load current are to be furnished for copper loss, iron loss indicating corresponding copper weight and core weight and considering all parameters and also supported by the drawings showings details of diameter and height of winding and core duly signed by manufacturer‘s design personnel. r) GA drawings/details of various types of bushings and connectors. s) Illustrative & descriptive literature of the Transformer t) List of customers to whom similar equipments have been supplied. u) Type test certificates from a recognized institute preferably CPRI of equipment of similar design and rating. v) Performance report of equipment of similar design and rating which is in satisfactory operation for at least three years. Performance report issuing officer‘s rank should be S.E./ DGM and above of the utility. 29.0 QUALITY ASSURANCE PLAN: The bidders shall invariably furnish the following information along with the bid in respect of quality assurance, failing which, offers are liable to be ignored. (a) (i). List of important raw materials (CRGO laminations, wires and strips, transformer oil, insulating paper, press board, bushings and terminal connectors etc.) (ii). Name of Suppliers/ sub suppliers (iii). List of standards which are followed during testing of raw materials. (iv). List of test carried out on raw materials along with test certificate. (i) List of manufacturing facilities. (j) Level of automation achieved. (k) Quality control on stages of manufacturing process along with inspection reports. (l) List of testing equipments available along with valid calibration certificates. Manufacturer shall possess 0.1 accuracy instruments for measurement of losses. Quality Assurance Plan (QAP) with hold points for Purchaser‘s Inspection as per Annexure – III. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 379 Technical Specification 30.0 DATA SHEET SL NO DESCRIPTION 20. 21. 22. Continuous KVA Ratings (CMR) Number of phases Rated voltage kV iii) Primary (HV) iv) Secondary (LV) 23. 24. 25. Highest System Voltage, kV iii) Primary (HV) iv) Secondary (LV) Rated frequency, Hz. Connection of HV, LV 26. 27. 28. TRANSFORMER CLASS 11/0.433-0.250 KV 250, 315, 500 & 630 3 11 0.433 12 1.1 50±5% HV Delta & LV Star with neutral solidly earthed Solidly earthed DYN 11 Method of system earthing Vector group Insulation Level: iv) PF withstand voltage, kV 28 (rms.): HV v) PF withstand voltage, kV 3 (rms.): LV vi) Lightening impulse voltage, kV 95 (peak) HV 9.2 Minimum Insulation resistance at HV- E : > 2000 MΩ 200C LV – E : > 1000 MΩ 29. 5% Percentage Impedance at 75C and at principal tap 30. Maximum flux density at rated 1.6 KVA, Maximum System voltage [12 KV/1.1 KV] and minimum system frequency [48.5 HZ], 31. Method of cooling ONAN 32. Type of tap changer No tap switch for 250 &315 KVA. Off Load tap changer for 500 KVA and above Tr. 33. Number of taps (+)3% to (-)9% in 5 steps of 3% 34. Clearance of air, mm b) phase to phase, HV / LV 285 / 75 phase to earth, HV / LV 140 / 40 35. Electrical Clearance, mm a) Core to LV: 4.0 (up to 250KVA) 4.5 (for 315 KVA) 5 (500 KVA and above) b) Between HV & LV 12 c) HV Phase to Phase 10 d) Between tank inside & top 150 of Yoke 40 e) Between yoke to bottom 50 f)Between tap switch and inside Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 380 Technical Specification SL NO 36. 37. 38. DESCRIPTION TRANSFORMER CLASS 11/0.433-0.250 KV tank cover Maximum current density 2.50 Amp / sq. mm for Copper & 1.5 Amp/sqmm for Aluminium Temperature Rise, 0C (i) Winding (measured resistance. (ii) Top Oil (measured thermometer) by 35 40 by Bushings: 3. Rated voltage in kV 1.4 HV bushing 12 1.5 LV bushing 1.1 1.6 Neutral bushing 4. Rated current in Ampere 1.1 2.4 HV bushing As per IS: 3347 Part III (Section 1 & 2) As per IS: 3347 Part I (Section 1 & 2) As per IS: 3347 Part I (Section 1 & 2) 2.5 LV bushing 2.6 Neutral bushing 6. Rated impulse voltage in kV rms. withstand 3.2 HV bushing 7. One-minute power frequency withstand test in kV (rms.) 4.4 HV bushing 4.5 LV bushing 95 28 3 4.6 Neutral bushings 8. Minimum Creepage distance in mm 5.4 HV bushing 5.5 LV bushing 5.6 Neutral 3 350 55 55 31.0 DOCUMENTATION : 31.1 The bidder shall furnish along with the bid the dimensional drawings of the items offered indicating all the fittings. 31.2 Dimensional tolerances 31.3 Weight of individual components and total weight. 31.4 An outline drawing front (both primary and secondary sides) and end elevation and plan of the tank and terminal gear, wherein the principal dimensions shall be given. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 381 Technical Specification 31.5 Typical general arrangement drawing of the windings with the details of the insulation at each point and core construction of transformer. 31.6 Typical general arrangement drawing showing both primary and secondary sides and end-elevation and plan of the transformer. 32.0 GUARANTEE: 32.1 The manufacturers of the transformers shall provide a guarantee of sixty (60) months from the date of commissioning and handover. 32.2 In case of failure within the guarantee period the APDCL will immediately inform the supplier who shall take back the failed DTR within fifteen (15) days from the date of intimation at his own cost and replace/repair the transformer within thirty (30) days of date of intimation with a roll over guarantee. 32.3 The outage period i.e. period from the date of failure till unit is repaired/replaced shall not be counted for arriving at the guarantee period. 32.4 In the event of supplier‟s inability to adhere to the aforesaid provision, suitable penal action will be taken against the supplier which may inter alia include blacklisting of the firm for future business with the APDCL for a certain period. 33.0 SCHEDULES: 33.1 The bidder shall fill in the following schedule which will be part of the offer. If the schedule are not submitted duly filled in with the offer, the offer shall be liable for rejection. Schedule – A : Guaranteed Technical Particulars Schedule – B : Schedule of Deviations 34.0 DEVIATIONS: 34.1 The bidders are not allowed to deviate from the principal requirements of the Specifications. However, the bidder is required to submit with his bid in the relevant schedule a detailed list of deviations without any ambiguity. In the absence of a deviation list in the deviation schedule, it is understood that such bid conforms to the bid specifications and no post-bid negotiations shall take place in this regard. 34.2 The discrepancies, if any, between the specification and the catalogues and/or literatures submitted as part of the offer by the bidders, shall not be considered and representations in this regard shall not be entertained. 34.3 If it is observed that there are deviations in the offer in guaranteed technical particulars other than those specified in the deviation schedules then such deviations shall be treated as deviations. 34.4 All the schedules shall be prepared by vendor and are to be enclosed with the bid. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 382 Technical Specification SCHEDULE - A GUARANTEED TECHNICAL AND OTHER PARTICULARS (To be filled in by Bidder and shall be furnished with the Technical Bid) Sl. No 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Description Name of the Manufacturer 2Installation [indoor/outdoor] 3Reference standards 4Continuous Ratings a) Type of cooling b) Rating [KVA] c Rated voltage i HV [KV rms.] ii LV [KV-rms.] d Highest system voltage i HV [KV rms.] ii LV [KV-rms.] e Rated frequency with ±% variation f Number of phases g Current at rated full load and on principal tap i HV [Amps] ii LV [Amps] 5Connections HV LV 6Connection symbol and vector group 7Temperature rise a Top oil temperature rise b Winding Temperature rise c Temperature gradients between windings & oil. d Limit of Hot spot temperature for which the Transformer is designed [°C] 8Type of OFF load tap changing switch 9Tapping on windings for i Constant flux/variable flux/combined Regulation ii Tapping provided at iii Number of steps iv Range of tapping for variation [+ percent to - percent] 1i No load loss at rated voltage and Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 383 Technical Specification Sl. No Description 0 ii 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. frequency at principal tap [KW] No load loss at the voltage corresponding to highest tap [KW] 1Load loss at rated output, rated 1frequency, corrected for 75 °C winding temperature at:- [Copper loss] i Normal tap [In KW] ii Highest tap [In KW] iii Lowest tap [In KW] 1Total losses at normal ratio 3 Maximum losses at 100% loading at 750C Maximum losses at 50% loading at 750C 1Positive sequence impedance on rated 4KVA base at rated current and frequency at 75°Centigrade winding temperature at i Normal tap [%] ii Highest tap [%] iii Lowest tap [%] 1% reactance at rated KVA base at rated 5current and rated frequency at i Normal tap [%] ii Highest tap [%] iii Lowest tap [%] 1% resistance at rated KVA base at 6rated current and rated frequency at i Normal tap [%] ii Highest tap [%] iii Lowest tap [%] 1% Impedance at rated KVA base at 7rated current and rated frequency at i Normal tap [%] ii Highest tap [%] iii Lowest tap [%] 1a Polarisation index i.e. ratio of 8 Megger values at 600 secs to 60 secs, (H.V. to E, L.V. to E, & H.V.to L.V.). Measurement by 1.0 kV motorised megger. b Insulation Resistance in MΩ (At temp ……….0C) c In Between H.V - E L.V. - E H.V – L.V. PI HV – E : LV – E : HV – LV : Regulation at full load and 75°C winding temperature expressed Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 384 Technical Specification Sl. No 21. 22. 23. 24. 25. 26. 27. Description as a percentage of normal voltage i At unity power factor [%] ii At 0.8 power factor [lagging][%] 2Efficiency at 75°C winding temperature Unity power 0as derived from guaranteed loss figures factor and at a At full load [%] b At ¾ load [%] c At ½ load [%] 2i Maximum efficiency [%] 1ii Load at which maximum efficiency occurs[% of full load] 2Short time thermal rating of 2i HV winding in KA and duration in seconds ii LV winding in KA and duration in seconds 2Permissible over loading:3a HV winding b LV winding 2Terminal arrangement 4a High voltage [HV] b Low voltage (LV) 2Insulating and cooling medium 5 2Test voltage HV 6i Lightning impulse withstand test 0.8 Power factor LV voltage [KVP] Power frequency withstand test voltage [dry and wet][for 1 minute] [KV-rms.] 2External short circuit withstand capacity 7[MVA] and duration [seconds] 2Over-fluxing withstand capability of the 8Transformer 2DETAILS OF CORE 9a Type of core construction b Type of corner joints of the core c Maximum flux density at i Rated voltage [11/0.4 KV] & rated frequency 50 Hz][in Tesla] ii Highest system voltage [12/1.1 KV] and lowest system frequency [48.5Hz.][in Tesla] d No load current, no load loss and No load No Load No no load power factor at normal current Loss PF ratio and frequency [Amp/KW/p.f.] ii 28. 29. 30. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd Load 385 Technical Specification Sl. No Description i ii iii iv v vi vii viii ix x xi xii e i ii iii iv v vi vii viii ix x f i ii iii iv v vi vii viii 10 percent of rated voltage 25 percent of rated voltage 50 percent of rated voltage 85 percent of rated voltage 100 percent of rated voltage 105 percent of rated voltage 110 percent of rated voltage 112.5 percent of rated voltage 115 percent of rated voltage 120 percent of rated voltage 121 percent of rated voltage 125 percent of rated voltage Core laminations:Material of core lamination [M4/HIB] Grade of core laminations Thickness of core lamination [mm] Specific loss [watt/Kg.] at rated voltage and rated frequency Specific loss [watt/Kg.] at highest system voltage and lowest system frequency Whether specific core loss graph [flux density vs. watt/Kg. submitted VA/Kg at rated voltage and rated frequency VA/Kg. at highest system voltage and lowest system frequency Whether VA/Kg. Vs. flux density graph Submitted Insulation of core laminations CORE ASSEMBLY:Core diameter [mm] Core window height [mm] Core leg centre [mm] Gross core cross-sectional area [cm²] Whether details of core widths, stacks and calculation furnished as per enclosed annexure Distance between centers [mm] Total height of core [mm] 1) Details of core Clamping with nos. of core stud. 2) Material, grade & type 3) Width 4) Thickness Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 386 Technical Specification Sl. No 31. Description 5) Fixing method ix Details of top end frame x Details of Bottom end frame xi Details of clamp plate [Material, thickness, Insulation] xii Total core weight [kg] xiii Core loss basing on core loss graph at operating flux density [rated voltage and rated frequency] [kw] xiv Core stacking factor xv Net core area Sq. cm. g Describe location/method of core grounding h Details of oil ducts in core if any i Peak value of magnetizing Inrush current (% of HV rated current). 3DETAILS OF WINDINGS. 0a Type of winding b Material of the winding conductor c Maximum current density of windings [at rated current] and conductor area i HV ii L.V. d Whether HV windings are crossover/ Sectional e Whether windings are preshrunk? f Whether adjustable coil clamps are provided for H.V. and L.V. windings? g Whether steel rings or perma wood are used for the windings? If steel rings used, whether these are split? h Winding Insulation. i H.V. ii LV Winding i Insulating material used for i H.V. ii L.V Winding iii Tapping connection j Insulating material used between i H.V. and L.V. winding ii Core and L.V winding iii H.V. winding and core iv H.V. to H.V. winding [between phases] Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 HV LV Conductor area [cm²] Current density [A/cm²] Type & class Assam Power Distribution Company Ltd 387 Technical Specification Sl. No Description V Vi Vii k i ii l i ii m n o p q r s t u v i ii iii iv v vi vii viii a b Inter coil spacers between HV sections (mm) Type of block between HV sections Oil duct between LV to cylinder (mm) : Cylinder to HV (mm) : Type of axial coil supports H.V. winding LV winding Type of radial coil supports H.V. winding LV winding Maximum allowable torque on coil clamping HV & LV bolts Bare conductor size (mm). HV : LV : Insulated conductor size (mm). HV : LV : Number of coil per phase HV : LV : No. of conductors in parallel HV : (Nos.). LV : No. of turns/phase HV coil : LV coil : Inside diameter (mm). HV coil : LV coil : Outside diameter (mm). HV coil : LV coil : Axial height after shrinkage (mm). HV coil : LV coil : D.C.RESISTANCE L.V winding at 75 ° C (Ohms). HV winding at normal tap at 75° C (Ohms). HV winding and at highest tap at 75° C (Ohms). HV winding at lowest tap. (Ohms). Total I²R losses at 75 ° C. for normal tap. (KW). Total I²R losses at 75 ° C. for highest tap. (KW) Total I²R losses at 75 ° C for lowest tap.(KW). Stray losses including eddy current losses in winding at 75°C (KW). Normal tap position Highest tap position Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 388 Technical Specification Sl. No Description c d w a b c Lowest tap position. Any special measures taken to reduce eddy current losses and stray losses, mention in details Load losses at 75°C [I²R + stray]. Normal tap position [KW]. Highest tap position [KW]. Lowest tap position [KW]. w 32. 33. Details of special arrangement provided to improve surge voltage distribution in the windings 3BUSHINGS. HV LV Neutral 1a Make and type i Rated voltage class [KV-rms.] ii Rated current [Amps.] b Lightning Impulse withstand test voltage [1.2/50 micro second][KVP] c Power frequency withstand test voltage i Wet for 1 minute [KV-rms] ii Dry for 1 minute [KV-rms] d Minimum creepage distance in mm e Weight of assembled bushing [Kg.] f Minimum clearance height for removal of bushing [mm] g Under oil flashover or puncture impulse voltage [KVP] h Under oil flashover or puncture power frequency voltage (KVrms). i Phase to earth clearance in air of live parts at the top of bushings 3Minimum clearance [mm] In Oil Out of Oil 2 Betwee Phase Betwee Phase n to n to winding Groun winding Groun s d s d HV LV a Radial clearance between LV and HV (mm) b Radial clearance between core to LV (mm) Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 389 Technical Specification Sl. No Description c 34. 35. End clearance of HV coil to yoke (mm) d End clearance of LV coil to yoke (mm) e Gap between yoke to bottom of tank (mm) 3Weight [Tolerance + 5%] 3[Approximate value is not allowed] a Core [Kg.] b Core with clamping [Kg.] c H.V. winding insulated conductor [Kg.] d L.V.winding insulated conductor [Kg.] e Coils with insulation [Kg.] f Core and winding [Kg] g Oil required for first filling [Liter/Kg.] h Tank and fittings with accessories [Kg.] i Untanking weight [Kg.] j Total weight with oil and fittings [kg.] 3DETAILS OF TANK 4a Material for Transformer tank b Type of tank c Thickness of sheet [No approximate value to be mentioned] i Sides [mm] ii Bottom [mm] iii Cover [mm] iv Radiators [mm] d Inside dimensions of main tank [No approximation in dimensions to be used] i Length [mm] ii Breadth [mm] iii Height [mm] e Outside dimensions of main tank [No approximation in dimensions to be used] i Length [mm] ii Breadth [mm] iii Height [mm] f Thickness of spray galvanisation of tank bottom. g Vacuum recommended for hot oil circulation [torr] Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 390 Technical Specification Sl. No Description h 36. 37. Vacuum to be maintained during oil filling in Transformer tank [torr] i Vacuum to which the tank can be subjected without distortion [torr] j No. of bi-directional wheels provided l Type and make of pressure relief device and minimum pressure at which it operates [Kpa] 3CONSERVATOR 5a Total volume [Liters] b Volume between the highest and lowest visible oil levels [Litres] 3OIL QUALITY 6a Governing standard b Density in gms/cu-cm c Kinematics viscosity in CST d Inter facial tension at 27°C in N/m e Flash point in °C f Pour point in °C g Acidity [neutralization value] in mg of KOH/gm h Corrosive sulfur in % i Electric strength [breakdown voltage] i As received [KV-rms.] ii After treatment [KV-rms.] j Dielectric dissipation factor [tan delta] at 90°C k Saponification value in mg of KOH/gm l Water content in ppm m Specific resistance i At 90°C [ohm-cm] ii At 27 °C [ohm-cm] o Oxidation stability i Neutralization value after oxidation ii Total sludge after oxidation p Characteristic of oil after ageing test as per ASTMD-1934 i Specific resistance at 27°C [ohm-cms] 90°C [ohm-cms] ii Tan delta iii Sludge content iv Neutralization number v Details of oil preserving equipment offered Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 391 Technical Specification Sl. No 38. 39. 40. 41. 42. 43. 44. 45. 46. 47. 48. Description 3RADIATORS 7 a Overall dimensions lxbxh [mm] b Total weight with oil [Kg.] c Total weight without oil [Kg.] d Thickness of radiator tube [mm] e Types of mounting f Vacuum withstand capability g Total radiating surface in sq.m h Type and make of material used for the radiators i Total number of radiators/Banks for Transformer and dimensions of tubes j Thickness of hot dip galvanization of radiators 3TEMPERATURE INDICATORS 8a Make and type b Scale c Size [lxbxd] d Nos. 3APPROXIMATE OVERALL DIMENSIONS 9OF TRANSFORMER Length [mm] Breadth [mm] Height [mm] 4Transformers will be transported with 2oil. 4Types of terminal connectors and 4drawing No a HV b LV 4Details of painting, galvanization 5conforms to this Specification [Yes/No] 4No. of breathers provided [Nos.] 6 4Type of dehydrating agent and quantity 7used for breathers 4Valve sizes and numbers 8a Filter valves- mm-Nos b Sampling valves- mm-Nos 4a Type and make of PRV 9b No. of each type of devices per transformer c Min. pressure at which device operates 5Please enclose the list of accessories 0and fittings, being provided on Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 392 Technical Specification Sl. No 49. 50. 51. 52. 53. 54. Description transformer. Please confirm, these are as stipulated in the tender 5Whether the transformer, covered is 1fully type tested and if so, whether copies of type test certificates, enclosed with the tender 5What are the arrangements, available 4for jointing the winding. Preference shall be given to the tenderer using highfrequency brazing machines. In case other jointing techniques are used, adequacy of the same is to be recorded. Please note that bolted joints in the winding are not acceptable. This should be confirmed here 5Please confirm that you will guarantee 5maximum Impedance variation between phases within the limit of 2% only 5a Please confirm that the 6 transformer shall be dried by vapour/ vacuum-phase drying method. Please specify level of dryness b In case, other methods of drying are used, the level of dryness, so achieved should be identical to that by V/VPD. Adequacy of such system should be justified 5Whether the Tenderer has got In-House 7core-cutting facility for cutting core materials for the transformer ratings as tendered 5In case SL.53 is not confirmed, whether 8the tenderer is agreed to follow the procedures, as stipulated at clause 12.3 of this technical specification Signature of Bidder Representative: Name of Representative: Designation: Date & Place: Seal: Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 393 Technical Specification Sl. NO Clause NO. SCHEDULE - B Technical Deviation Sheet Deviations Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 394 Technical Specification 33.0 TECHNICAL SPECIFICATION FOR AC DISTRIBUTION CUBICLE FOR DISTRIBUTION TRANSFORMER 1. Scope This section of the specification covers the design, manufacture, testing at works transport to site insurance storage erection and commissioning of 415 volts AC 50Hz AC Distribution Board (Cubicle) complete with all equipments and accessories as described in subsequent clause for DTR of different capacity. 2. Constructional features A) The Cubicle shall be outdoor, made of sheet metal clad type, thickness 2.5mm in top and back side, 2.00mm in other sides painted with powder coated paints, comprising of combination MCCB units and bus bar chambers and equipped with the circuits and equipments as specified later. The enclosure shall conforming to IP-54 standard. The different circuits shall be mounted above and below the bus bar chamber to form a suitable arrangement except that the incomings will be located at the front and mounted below the busbar chambers. All equipments shall be suitable for the reception of the cables rising from the ground level the switch boards shall be so designed as to be readily extensible. B) Type TYPE Type of poles Rated current Rated operational voltage Rated insulation voltage Rated impulse withstand voltage Rated frequency Reference Ambient Temperature In Ue Ui Uimp A V V kV DN2-400/630 3/4 315, 400, 630 415 750 8 Hz ⁰C 50 40 Rated ultimate S.C. Breaking capacity (at 415V ac, 50 Hz) Rated service S.C. Breaking capacity (at 415 ac, 50 Hz) Type of release Icu kA 35,50,70 Ics kA 100% of Icu Current rating In Protectio n Overload Instantaneous A ThermalMagnetic 315, 400, 630 Microprocess or 315, 400, 630 0.8-1 In. 3-6 In/6-10/ In Adjustable 3. Combination MCCB Unit A) All MCCB shall be triple pole rotary operated type and shall open and close with snap action. The series combination MCCB shall conform to the provisions of latest issue of IS 13947-2 B) The MCCB shall be suitable for rated voltage of 415 volts AC., 50 Hz. The rated current of each unit shall be as specified before. MCCB should be reputed make such as Havell‘s/Seimen‘s/Schneider etc. 4. Bus Bars A) The phase and neutral bus bars shall be of high conductivity (as per IS 5082) Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 395 Technical Specification aluminium of adequate uniform cross section. The bus bars shall be insulated from the structure by means of durable non-hygroscopic, non-combustible and non-tracking materials. Bus bar joints shall be bolted type. The Bus bars Shall have complete insulation with Red, Yellow,Blue and Black colours for phases and neutral. 5. The 415 Volts, L.T. A.C. switchgear shall have following circuits and equipments: A) INCOMING:- incoming cable shall be directly connected to the Bus Bar with proper size Lug and GI Nuts & Bolts B) OUTGOING:- .(i) Four no 3-Ph(300Amp, Adjustable) and one 1-Ph (32A, Adjustable) MCCB as Out going for 500KVA DTR and Above. (ii) (iii) (iv) 6. 7. Three no 3- Ph (300Amp,Adjustable) MCCB and one 1-Ph (32Amps ,adjustable) MCCB as outgoing for DTR 315 & 250 KVA. Two no 3-Ph (200Amp,Adjustable) MCCB and one no 1-Ph (32 A,mp, adjustable) MCCB for DTR 100 & 63 KVA One 3-Ph(100Amp,Adjustable) and one 1-ph MCCB for 25 KVA DTR . Name Plate The board shall be provided with nameplate covering all technical data and also name of the project shall be clearly mentioned ―RAPDRP‖ Cubicle Supporting structure The Cubicle shall be fitted by fixing GI channels in poles or by means of some other supporting structures in convenient height for easy maintanace keeping sufficient clearance from ground. All nuts and bolts shall be of GI. 8. Inspection Inspection may be carried out by the purchaser or third party nominee at any stage of manufacture. The supplier shall grant free access to the purchaser‘s representative or third party nominee at a reasonable time when the work is in progress. Inspection and acceptance of any equipment under this specification by the purchaser shall not relieve the supplier of his obligation of furnishing equipment in accordance with the specification and shall not prevent subsequent rejection if the equipment is found defective. 9. The design and drawing should be submitted along with the offer. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 396 Technical Specification TECHNICAL SPECIFICATION FOR AC 3 PHASE 4 WIRE CT/CT- PT OPERATED FULLY STATIC THREE VECTOR ENERGY METER (AMR COMPATIBILITY WITH DLMS PROTOCOL FOR DTR METERING 1. OBJECTIVE & SCOPE This scope shall cover design, engineering, manufacture, assembly, inspection, testing at manufacturers works before dispatch, packing, supply and delivery at destination, subsequent storage, erection and commissioning at site (including insurance during transit and storage), of 0.5S accuracy class fully static 3 phase–4 wire CT operated three-vector energy meter for R-APDRP works along with other metering accessories such as metering cabinet, CTs of relevant accuracy class etc. detailed out in the specification. The meter shall be suitable for measurement of different electrical parameters as per the energy and power demand requirement in an AC balanced/unbalanced system over a power factor range of zero lag to unity. These meters should have communication port to interface for remote meter reading (AMR Compatible). 2. APPLICATION On Distribution Transformers – The pole mounted meter cabinets with the CTs and meters are to be installed for metering of Distribution Transformers. 3. WORKING ENVIRONMENT 3.1. As per IS 14697-1999 (reaffirmed 2004). Meter to perform satisfactorily under Non-Air Conditioned environment (within stipulations of IS) 3.2. The meter shall be suitable designed for satisfactory operation under the hot and hazardous tropical climate conditions and shall be dust and vermin proof. All the parts and surface, which are subject to corrosion, shall either be made of such material or shall be provided with such protective finish, which provided suitable protection to them from any injurious effect of excessive humidity. 3.3. The meter casing should have IP 51 degree of protection. 4. SERVICE CONDITION 4.1. The meter shall be suitable for satisfactory continuous operation under the following tropical conditions:a) Maximum ambient temperature in a closed box : 65 °C b) Maximum ambient temperature in shade : 55 °C c) Relative Humidity : 10 to 95%(noncondensing) d) Maximum annual rainfall : 2280 mm‘ e) Maximum wind pressure : 150 Kg/m. sq. f) Maximum altitude above mean sea level : up to1000 meters g) Isoceraunic level : 60 days/year h) Seismic level (Horizontal acceleration) : 0.3g i) Average number of thunderstorms/annum : 40 (5 months) k) Minimum ambient air temperature : -10°C 4.2. The climate is moderately hot and humid, conducive to rust and fungus growth. The climatic conditions are also prone to wide variations in the ambient conditions. Smoke is also present in atmosphere. Lighting also occurs during rainy season. 5. APPLICABLE STANDARDS Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 397 Technical Specification 5.1. Unless otherwise stated elsewhere in this specification the energy meter shall be of accuracy Class 0.5S for active/reactive /apparent energy and conform to relevant clauses of following standards or report to be read with up to date and latest amendments/revision thereof in all respect: 1. Guidelines on ―Data Exchange for Electricity Meter Reading, Tariff and Load Control – Companion Specification‖ related to IEC 62056 series of standards; 2. IS-14697/1999 (reaffirmed 2004) Specification for AC Static Transformer operated Watt Hour & VAR-Hour meters (class 0.5S & 0.2 S); 3. IS-15707 Specification for Testing, evaluation, installation & maintenance of AC Electricity Meters-Code of Practice; 4. CBIP Report No. 88 /No. 304 : Specification for AC Static Electrical Energy Meters. 5. Metering code for Assam Grid Regulations-2004 by AERC. 5.2. The equipment meeting with the requirements of other authoritative standards, which ensure equal or better quality than the standard mentioned above, also shall be considered; in case of conflict related with communication protocol, the Guidelines on ―Data Exchange for Electricity Meter Reading, Tariff and Load Control – Companion Specification‖ shall prevail upon. For any unresolved conflict related with other parts of this specification the order of priority shall be – 1. Standard Technical specification for 3p/4w CT/PT operated fully static AMR compatible Trivector energy meters for R-APDRP projects. II. IS 14697/1999 (reaffirmed 2004). 6. GENERAL TECHNICAL REQUIREMENT 1 TYPE 2 3 FREQUENCY ACCURACY CLASS SECONDARY VOLTAGE BASIC CURRENT (Ib) MAXIMUM CONTINUOUS CURRENT POWER FACTOR DESIGN 4 5 6 7 8 AMR Compatible Static, 3 Ph, 4 Wire Tri-Vector Energy Meter Import type for DTR 50 Hz ±5% 0.5S Suitable for operation for 3 x 415V -/5 Amps. as per requirement specified 2.0 Ib; (Starting and Short time current shall be as per IS-14697) 0.0 Lag -Unity- 0.0 Lead Meter shall be designed with application specific integrated circuit (basic) or micro controller; shall have no moving part; electronic components shall be assembled on printed circuit board using surface mounting technology; factory calibration using high accuracy (0.05 class) software based test bench. Assembly of electronic components shall be as per ANSI/IPC-A-610 standard. 7. GENERAL ELECTRICAL REQUIREMENT 7.1 STARTING CURRENT The meter shall start and continue to register at the current 0.1% of Ib. 7.2 RUNNING WITH NO LOAD When the 115% of rated voltage is applied with no current flowing in the current circuit, the meters shall not register any energy and test output of the meter shall not Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 398 Technical Specification be more than one pulse/count on "no load". 7.3 POWER SUPPLY VARIATION The extreme power supply variation (which an operating meter should withstand without damage and without degradation of its meteorological characteristics when it is subsequently operated under its operating conditions) is as follows. Voltage : 70% to 120 % of Vref Frequency : 45 Hz to 55 Hz The manufacturer can also offer meters, which can withstand higher variations. 7.4 ACCURACY The class of accuracy of the meter shall be 0.5S for DTRs . The class of accuracy of CT shall be 0.5. The accuracy should not drift with time. 7.5 POWER CONSUMPTION The active and apparent power consumption in each voltage circuit of the CT Operated meters at reference voltage; temperature and frequency shall not exceed the limit as specified by the latest amendment of IS 14697 per phase. The apparent power consumption in each current circuit for the CT Operated meters at basic current, reference frequency and reference temperature shall not exceed 1.0 VA per phase. 8. PERFORMANCE UNDER INFLUENCE QUANTITIES 8.1.The meters performance under influence quantities shall be governed by IS 14697-1999 (reaffirmed 2004). The meter should be designed and protected such that all external effects and influences shall not change its performance & shall work satisfactorily within guaranteed accuracy limits, as specified in IS 14697(latest version). 9. MANUFACTURING PROCESS, ASSEMBLY AND TESTING 9.1. Meters shall be manufactured using latest and ‗state of the art‘ technology and methods prevalent in electronics industry. The meter shall be made from high accuracy and reliable surface mount technology (SMT) components. All inward flow of major components and sub assembly parts (CT, PT, RTCs/Crystal, LCDs, LEDs, power circuit electronic components etc.) shall have batch and source identification. Multilayer ‗PCB‘ assembly with ‗PTH‘ (Plated through Hole) using surface mounted component shall have adequate track clearance for power circuits. SMT component shall be assembled using automatic ‗pick-and-place‘ machines, Reflow Soldering oven, for stabilized setting of the components on ‗PCB‘. For soldered PCBs, cleaning and washing of cards, after wave soldering process is to be carried out as a standard practice. Assembly line of the manufacturing system shall have provision for testing of sub-assembled cards. Manual placing of components and soldering, to be minimized to items, which cannot be handled by automatic machine. Handling of ‗PCB‘ with ICs/C-MOS components, to be restricted to bare minimum and precautions to prevent ‗ESD‘ failure to be provided. Complete assembled and soldered PCB should undergo functional testing using computerized Automatic Test Equipment. 9.2. Fully assembled and finished meter shall under go ‗burn-in‘ test process for 24 Hours at 50 degree Celsius (Max. temperature to not exceed 60 degree Celsius) under power-on no load condition. 9.3. Test points should be provided to check the performance of each block/stage of the meter circuitry. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 399 Technical Specification 9.4. RTC shall be synchronized with NPL time at the time of manufacture. Meters testing at intermediate and final stage shall be carried out with testing instruments, duly calibrated with reference standard, with traceability of source and date. 10. GENERAL & CONSTRUCTIONAL REQUIREMENTS 10.1. The case, winding, voltage circuit, sealing arrangements, registers, terminal block, terminal cover & name plate etc, shall be in accordance with the relevant standards. The meter should be compact & reliable in design, easy to transport & immune to vibration & shock involved in the transportation & handling. The construction of the meter should ensure consistence performance under all conditions especially during storms/heavy rains/very hot weathers. The insulating materials used in the meter should be non-hygroscopic, non-ageing & have tested quality. The meter should be sealed in such a way that the internal parts of the meter become inaccessible. 10.2. Meters shall be designed and constructed in such a way so as to avoid causing any danger during use and under normal conditions. However, the following should be ensured. a) Personal safety against electric shock b) Personal safety against effects of excessive temperature. c) Protection against spread of fire d) Protection against penetration of solid objects, dust & water e) Protection against fraud f) Protection against pilferage 10.3 The meter should be housed in a safe, high grade engineering plastic / polycarbonate casing, which is of projection mounting type and is dust/moisture proof, conforming to IP-51 of BIS 12063 / IEC 529, vermin proof and sturdy. 10.4. All insulating material used in the construction of meters shall be nonhygroscopic, non-ageing and of tested quality. All parts that are likely to develop corrosion shall be effectively protected against corrosion during operating life by providing suitable protective coating. 10.5. The meter shall be supplied with a transparent extended terminal block cover (ETBC). The meter base, meter cover, terminal block and ETBC shall be made of unbreakable high grade fire resistant non-flammable reinforced, polycarbonate (not bakelite) or equivalent high grade engineering plastic, which should form an extension of meter cases and have terminal holes and shall be of sufficient size to accommodate insulation of the conductors, meeting the requirement of IS 14697.1999 / CBIP.88. The extended terminal block cover should be separately sealable at two places and housed at the bottom of the meters and once sealed should prevent unauthorized tampering. The terminal block should have sufficient insulating properties, mechanical strength and should have house plated solid brass/steel terminals with two fixing screws per terminal. The terminals should be designed to withstand high overload with cage clamp. 10.6. The meter shall have an operation indication device such as a blinking LED. The operation indicator shall be visible from the front window and capable of being monitored conveniently with suitable testing equipment. 10.7. The meter-base, meter cover, terminal block and ETBC shall be made of unbreakable, high grade, fire resistant, reinforced, non-flammable, polycarbonate or equivalent high grade and good quality engineering plastic certified by NABL accredited Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 400 Technical Specification laboratory preferably CIPET 10.8. The meter cover shall have one window. The window shall be of transparent, high-grade engineering plastic certified by CIPET for easily reading all the displayed values/parameters, nameplate details and observation of operation indicator. The window shall be ultrasonically welded with the meter cover and the meter cover should be ultrasonically welded to the meter base such that it cannot be removed undamaged without breaking the meter cover. 10.9. The terminal block, the ETBC and the meter case shall ensure reasonable safety against the spread of fire. They should not be ignited by thermal overload of live parts in contact with them. 10.10. The meter shall have tin plated brass/steel terminals or nickel plated brass terminals. The terminals shall have suitable construction with barriers and cover to provide firm and safe connection of current and voltage leads of stranded copper conductors or copper reducer type terminal ends (thimbles). 10.11. The manner of fixing the conductors to the terminal block shall ensure adequate and durable contact such that there is no risk of loosening or undue heating. Screw connections transmitting contact force and screw fixing which may be loosened and tightened several times during the life of the meter shall be such that the risk of corrosion resulting from contact with any other metal part is minimized. Electrical connections shall be so designed that contact pressure is not transmitted through insulating material. The internal diameter of the terminal holes shall be 5.5 mm minimum. The clearance and creepage distance shall conform to relevant clause of IS 14697:1999/CBIP technical report No.88. 10.12. The entire and construction shall be capable of withstanding stresses likely to occur in actual service and rough handling during transportation. The meter shall be convenient to transport and immune to shock and vibration during transportation and handling. 10.13. Bidder will submit predefined copies (Qty. indicated in Bid Proposal Sheets) of all the software‘s (meter reading software for HHU/CMRI, Base computer software for meter data analysis and technical details). 10.14. It should be possible to check the healthiness of phase voltages by displaying all the voltages on the meter display. 10.15. The meter shall have three fixing holes, one at the top and two at the bottom. The top hole shall be provided with a special clip at the back of the meter so that holding screw is not accessible to the consumer after fixing the meters. The lower fixing screws shall be provided under the sealed terminal cover. The requisite fixing screws shall be supplied with each meter. 11. TROPICAL TREATMENT 11.1. All parts, which are subject to corrosion under normal working conditions, shall be protected effectively. Any protective coating shall not be liable to damage by ordinary handling or damage due to exposure to air, under normal working conditions. Meters shall withstand solar radiation. The meters shall be suitably designed and treated for normal life & satisfactory operation under the hot and hazardous tropical climatic conditions as specified in clause no. 2. The meter shall work from -10°C to +55°C and RH 95% non-condensing type. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 401 Technical Specification 12. QUALITY 12.1. Overall the quality of the meter should be good and the service life of the meter shall be more than the guarantee period. The material, components used for manufacturing the meter shall be of premium quality. The LCD display shall not fade with time and the display annunciators should be visible. Functionality of the meter shall not be affected by the harsh environmental conditions. Quality meters shall be given preference and the performance of previous installed meters shall be analyzed before awarding the tender. Aesthetically, the meter shall be of premium quality. 12.2. The meter shall have a design to operate satisfactory for 10 years under normal electrical condition and guaranteed life of 66 months from the date of commissioning against manufacturing and design defects. The meters found defective with in guaranteed period should be replaced/repaired by supplier free of cost with in one month of intimation. 13 SEALING OF METER 13.1. Reliable sealing arrangement should be provided to make the meter tamper proof and avoid fiddling or tampering by unauthorized persons. For this, at least two no. of seals on meter body, two no. of seals on meter terminal cover and one no. of seal on communication port and one seal for the meter cabinet shall be provided. All the seals shall be provided in front side only. Please refer technical specification for specification for sealing system. Except the meter cover seals all other seals should be provided loose. 14. MARKING OF METERS 14.1. The marking of meters shall be in accordance with IS: 14697 /1999 (reaffirmed 2004). Every meter shall have nameplate beneath the meter cover such that the nameplate cannot be accessed without opening the meter cover and without breaking the seals of the meter cover and the nameplate shall be marked distinctly and indelibly. The basic marking on the meter nameplate shall be as follows: a) R-APDRP Project (Details to be given later) b) Manufacturer‘s name & trade mark c) Type, Designation/ Category of Meter d) No. of phases & wires e) Reference Voltage f) Rated secondary Current of CT g) Reference Standard: IS 14697 h) Principal unit(s) of measurement i) Meter Constant ( imp/kwh, kvARh) j) Class index of meter k) Serial number l) Month and Year of manufacture m) ―Property of ―APDCL‖ Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 402 Technical Specification n) Purchase Order No. & Date o) Guarantee period 14.2. The meter shall also store name plate details as given in the table A5.1 of annexure of the guideline document. These shall be readable as a profile as and when required. 15. CONNECTION DIAGRAM The connection diagram of the meter shall be clearly shown for 3 phase 4 wire system, on inside portion of the terminal cover. The meter terminals shall also be marked and this marking should appear in the above diagram. 16. COMMUNICATION CAPABILITY 16.1. The meter shall be provided with two ports for communication of the measured/collected data as per the guideline document for DLMS/COSEM energy meters: 16.2. LOCAL COMMUNICATION PORT The energy meter shall have a galvanically isolated optical communication port located in front of the meter and complying with the hardware specifications detailed in IEC-62056-21 for data transfer to or from a hand held DLMS compliant Data Collection Device (Common Meter Reading Instrument, Hand Held Units etc.) with proper security and without error. 16.3 REMOTE COMMUNICATION PORT Meter shall have an additional communication port (RS 232/485) for periodic data transfer by remote access through suitable modem (GPRS/GSM/EDGE/CDMA/PSTN/). Meter shall operate on open DLMS protocol and will be individually addressable. Meters with similar kind of RS 485 ports shall be possible to hook up in multi-drop arrangement for exporting data to the remote end server through suitable communication medium. Both ports shall support the default and minimum baud rate of 9600 bps. 17. DATA COLLECTION DEVICE 17.1. To enable local reading of meters data a DLMS compliant data collection device (HHU, CMRI/Laptop etc;) shall be used. This device shall be as per specification given in the guideline document. It shall be compatible to the DLMS compliant energy meters that are to be procured /supplied on the basis of this specification. This device shall be supplied by the meter manufacturer along with the meter free of cost (one unit per 100 meters). 17.2. Preferred equipment is a laptop of general configuration so as to be compatible for data downloading with ease form DLMS compliant meters. 18. QUANTITIES TO BE MEASURED AND DISPLAYED The meter shall be capable of measuring and displaying the following electrical quantities within specified accuracy limits for poly-phase balanced or unbalanced loads: 18.1. Instantaneous Parameters such as phase and line voltages, currents, power factors, overall kVA, kW, kVAr, power factor, frequency etc as per details given in the table below and the guideline document annexure. 18.2. Block Load Profile Parameters such as kVAh, kWh, kVArh (lag, lead), Maximum Demand (MD) in kW & kVA, power factor, phase and line voltages, currents etc as per details given in the table below and the guideline document annexure. 18.3. Daily Load Profile Parameters such as cumulative energy kWh (import, export), cumulative kVAh (while kW- import/export), cumulative energy kVArh (quadrant-1/2/3/4), reactive energy high (V>103%)/low (V<97%), etc Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 403 Technical Specification as per details given in the table below and the guideline document annexure. 18.4. In addition to above the meter shall also record the Name plate details, programmable parameters (readable as profile), occurrence and restoration of tamper events along with the parameters (Table A5.1,A 5.2 and A 6.1 to A 6.8 respectively of guideline document). Detail of category wise parameters requirement suitable for specific location such as feeder/DT metering, interface points/boundary points is given in following tables : Category Parameter group GUIDELINE DOCUMENT Indian Companion Specification Annexe Substation Feeder/ Distribution Instantaneous parameters A2.1 Transformer meter Distribution Transformer/ Block Load Profile parameters Block Load Profile parameters Billing Profile parameters Name Plate details Programmable Parameters Event Conditions A2.2 A4.2 A4.3 A5.1 A5.2 A6.1 to A6.7 Logging parameters for each of Capture parameters for A6.8 the event event condition – shall be as applicable (Event Log selected Profile) The OBIS code for each parameter shall be as identified as per DLMS /COSEM protocol/ Indian companion standard. 18.5. Demand Integration period shall be selectable between 15/30 minutes, 19. DISPLAY OF MEASURED VALUE 19.1. The measured value(s) shall be displayed on seven segments, seven digit (with ± indication), parameter identifier, backlit Liquid Crystal Display (LCD) display unit/register, having minimum character height of 10 mm, wide viewing angle. LCD shall be suitable for temperature withstand of 70 degree centigrade. 19.2. The data should be stored in non-volatile memory. The non-volatile memory should retain data for a period of not less than 10 years under unpowered condition. Battery back-up memory will not be considered as NVM. 19.3. The meter should have facility of auto display mode where all parameters automatically scroll within the specified time and a manual mode where the parameters can be read by push button operation. In auto display mode each parameter shall on display for 10 seconds. The display ―off‖ period between two cycles shall not exceed 30 seconds. The register should not roll over in between this duration. 19.4. It should be possible to easily identify the single or multiple displayed parameters through symbols/legend on the meter display itself or through display annunciators. 19.5. Meter shall have Scroll Lock facility to display any one desired parameter continuously from display parameters for at least 5 minutes. 19.6. The register shall be able to record and display starting from zero, for a minimum of 1500 hours, the energy corresponding to rated maximum current at reference voltage and unity power factor. The register should not roll over in between this duration. The principle unit for the measured values shall be Wh/kWh/MWh for active Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 404 Technical Specification energy, VArh/kVArh/MVArh for reactive energy & VAh/kVAh/MVAh for apparent energy. Bidder shall mention the scale in which the meter displays the energy values. There should also be a provision through the push button mode to access a high resolution display of the principle unit of measurement for testing purpose. This high resolution display should provide for displaying the measured units up to 4 decimal point without any rounding off the digits in case of power failure. 20. DISPLAY PARAMETERS & DISPLAY SEQUENCE a) The meter shall display the following required parameters in two different modes as follows: A) Auto-Display Parameters for CT operated Static Meters:1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. LED/LCD test Date Real Time Cumulative Reset Count Phase to Neutral Voltages (R,Y,B) : Line Currents(R,Y,B). : Bill point Active Energy (Kwh) : History 1 Bill Point Average Power Factor : History 1 Bill Point Power-on-hours : History 1 Bill Point Tamper Count : History 1 Bill Point TOD Active Energy (Kwh - REG 1,2,3) : History 1 Bill Point TOD Maximum Demand (KVA - REG 1,2,3) : History 1 Instantaneous Average Power Factor Cumulative Current Active Energy (Kwh) Instantaneous Load (KW) Indication of any present occurrence of tamper (i.e. existing tamper) B) Push Button-Display (with back scroll facility) Parameters for CT operated Static Meters:1. LED/LCD test 2. Date 3. Real Time 4. Rising Demand (KVA) with elapsed time 5. Phase to Neutral Voltages (R,Y,B) 6. Line Currents (R,Y,B) : 7. Supply Frequency 8. Instantaneous Power Factor 9. Instantaneous Load, Active, Reactive, Apparent 10. Cumulative Reset Count 11. Bill Point Active Energy (Kwh) : History 1 12. Bill Point Apparent Energy (Kvah): History 1 13. Bill Point Average Power Factor : History 1 14. Bill Point Power-on-hours : History 1 15. Bill Point Tamper Count : History 1 16. Bill Point TOD Active Energy (Kwh - REG 1,2,3) : History 1 17. Bill Point TOD Apparent Energy (Kvah REG 1,2,3) : History 1 18. Bill Point TOD Maximum Demand (KVA - REG 1,2,3) : History 1 19. Cumulative Power-on-hours Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 405 Technical Specification 20. Cumulative Maximum Demand (KVA 0-24 HRS) 21. Cumulative Current Active Energy (Kwh) 22. Cumulative Current Reactive Lag Energy (Kvarh-Lag) 23. Cumulative Current Reactive Lead Energy (Kvarh-Lead) 24. Cumulative Current Apparent Energy (Kvah) 25. Cumulative Current TOD Active Energy (Kwh - REG 1,2,3) 26. Cumulative Current TOD Apparent Energy (Kvah REG 1,2,3) 27. Current TOD Maximum Demand (KVA - REG 1,2,3) 28. Indication of any existing Tamper 29. Cumulative tamper occurrence counts 30. Tamper information as mentioned in the relevant clauses of the specification should be recorded and displayed in the push button display 31 Connection Check. C) One high resolution display for Kwh & Kvarh suitable for easy dial testing of the meter. Data Transfer through HHU/CMRI: Apart from the display parameters (Auto display & Push Button) as specified above and the standard parameters as specified in the relevant clause of the guideline document, the meter should record in addition the following parameters and all these parameters as well as the displayed parameters should be retrievable/calculable at the BCS end through CMRI/HHU/LAPTOP through an additional and separate retrievable mode (i.e. other than the standard DLMS data downloading mode): 1. Bill Point TOD Reactive Energies (Kvarh) Lag & Lead 2. Current TOD Reactive Energies (Kvarh) Lag & Lead 3. Current Maximum Demand (KVA) ( 0 –24 HRS) 4. Instantaneous power factors of individual phases 5. Bill Point Power factors of individual phases 6. Detail Tamper information 7. Detail historical data of all the parameters for at least 6 calendar months 8. Information regarding following failures: a) Time & Calendar b) RTC battery c) Segment failure. d) Self diagnostic details e) Battery bad flag Note:- If for any reason a separate data downloading mode (i.e. other than the standard DLMS data downloading) cannot be provided or impossible to be implemented, then six months historical backup of energy and demand recordings of the meter should be made available in the push button display of the meter. b) Sub-station feeder and DTR meters The standard parameters as specified in the relevant clause of the guideline document shall be displayed in the auto display mode. Additional parameters if required for the push button mode and BCS mode will be notified in due course prior to ordering. However in addition to the daily accounting data, monthly or other periodic figures should also be available. 21. CALIBRATION & TEST OUTPUT 21.1 All the meters shall be tested, calibrated and sealed at works before dispatch. Further, no modification of calibration shall be possible at site by any means. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 406 Technical Specification However, it shall be possible to check the accuracy of energy measurement of the meter while in operation in the field by means of LED test output on meter, accessible from the front as well as through high-resolution display using suitable test equipment. Resolution of the test output shall be sufficient to enable the starting current test in less than 10 minutes. Test output device shall be provided in the form of preferably one common LED for KWh & KVARh or two separate LEDs, for the provision of selecting the parameter being tested. The test output device should have constant pulse rate in terms of pulse/unit energy. 22. REAL TIME INTERNAL CLOCK (RTC) 22.1. RTC shall be pre-programmed for 30 Years day/date without any necessity for correction. The maximum drift shall not exceed +/- 180 Seconds per year. The uncertainty of setting initial time shall not exceed + 30 Seconds with respect to Indian standard time (Ref. NPL New Delhi). The clock day/date setting and synchronization shall only be possible through password/Key code command from one of the following: a) Hand Held Unit (HHU) or Meter testing work bench and this shall need password enabling for meter; b) From remote server through suitable communication network or Sub-station data logger ‗PC‘ 23. . DEMAND INTEGRATION & MD REGISTRATION 24. 23.1. The meter shall continuously monitor and calculate maximum demand for each interval of time, which may be programmable as a block of 15 minutes or 30 minutes as per the user‘s choice through the communicating ports as and when required with proper password identification & authentication. At the end of every demand integration period the new calculated MD shall be compared with the previous MD and meter shall store whichever value is higher with date & time stamping. Under the current integration period, the rising demand should be displayed continuously along with the elapsed time. The rising demand with the elapsed time should be held in the memory in the event of interruption or switching off supply and it should not become zero on such instances. The registered demand and the number of times the MD is reset shall also be displayed and the information stored. 23.2. The display of Maximum demand should be as per the provision G-6 of IS 14697 : 1999 MD RESET It should also be possible to reset the MD using options. The meter shall have any of the following MD resetting options: 24.1 Automatic reset at the end of a certain predefined period by default (24:00 hrs of the last day of the month). 24.2 Resetting through a hand held terminal capable of communicating with the meter (i.e. through HHU with proper password identification & authentication). 24.3 Communication driven reset form the base terminal/server with proper password identification and authentication. 24.4 Note:- It should not be possible to reset the MD by the use of the local push button. 25. ELECTROMAGNETIC COMPATIBILITY The static energy meters shall conform to requirements listed in relevant standards and Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 407 Technical Specification shall also be protected against radiated interference from either magnetic or radiofrequency source. a. IMMUNITY TO ELECTROMAGNETIC DISTURBANCE The meter shall be designed in such a way that conducted or radiated electromagnetic disturbance as well as electrostatic discharge do not damage or substantially influence the meter and meter shall work satisfactorily under these conditions as per relevant standards NOTE: the disturbances to be considered are: (a) Harmonics (b) Voltage dips and short interruptions (c) Conducted transients (d) D.C. and A.C. magnetic fields (e) Electromagnetic HF fields (f) Electrostatic discharges (ESD) b. RADIO INTERFERENCE SUPPRESSIONS The meter shall not generate noise, which could interfere with other equipment, and meter shall work satisfactorily as per relevant standard 26. TAMPER & FRAUD MONITORING FEATURES The meter shall work satisfactorily under presence of various influencing conditions like External Magnetic Field, Electromagnetic Field, Radio Frequency Interference, Vibrations, harmonic Distortion, Voltage/Frequency Fluctuations, and electromagnetic High Frequency Fields etc. The meter shall be immune to abnormal voltage/frequency generating devices and shall record the occurrence and restoration of such tamper events along with parameters such as current, voltages, kWh, power factor, event code, date & time etc. (listed in Table A6.1 to A6.8 in the guideline document). Tamper details shall be stored in internal memory for retrieval by authorized personnel through either of the following: i) HHU. ii) Remote access through suitable communication network. Minimum 250 numbers of events (occurrences & restoration with date & time) should be available in the meter memory. The meter shall function properly under following common abnormal conditions: 1. Phase The meter shall keep working accurately irrespective of sequence the phase sequence of the supply. reversal 2. Missing Neutral The meter shall continue to record accurately according to electrical connections even if the Neutral of potential supply is accidentally or incidentally disconnected. 3. Current reversal / CT polarity reversal The meter shall log energy in forward direction even if the current is flowing in reverse direction in one or more phases. The meter shall also be capable of detecting and recording occurrence and restoration with date and time if the current is flowing in reverse direction in one or more Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 408 Technical Specification phases. 4. External magnetic influence The metering system shall be provided with adequate magnetic shielding so that any external magnetic field (AC Electro Magnet or DC Magnet) as per the values specified in CBIP Technical Report No.88 (with latest amendments) applied on the metering system shall not affect the proper functioning and recording of energy as per error limits prescribed by CBIP. Beside this the meter should have features to detect the occurrence and restoration of, at least, the following common abnormal events: a) Missing Potential & Potential imbalance: The meter shall be capable of detecting and recording occurrence and restoration with date and time the cases of Potential failure which could happen due to disconnection of potential leads (one or two), failure of phase line fuse from the Transformer primary side. Meter shall also detect and log cases of voltage unbalance (from 5 % for more than 5 minutes or more- programmable) of voltages. b) Voltage High / Voltage Low: In case the average 3 phase voltage remains less (below 0.75Vref by default) or more (above 1.15Vref by default) for a predefined period (15 minutes by default), the meter shall log such incidences with date & time. The voltage thresholds & persistence time shall be programmable using the CMRI & BCS. This abnormal condition shall be logged only when all the three-phase voltage is available. c) Current imbalance: The meter shall be capable of detecting and recording occurrence and restoration with date and time of Current unbalance (30% or more for more than 15 minutes- programmable). d) Current Circuit Short: The meter shall be capable of detecting and recording occurrences and restoration of shorting of any one or two phases of current circuit to identify events like CT saturation, CT lead shorting, CT inter turns short etc. e) Current Circuit Open: The meter shall be capable of detecting and recording occurrences and restoration of opening of any one or two phases of current circuit which can happen due to intentional / accidental disconnection of current circuits. The meter shall be able to log abnormality conditions in current open event like CT leads burns, loose connection, CT winding open etc in the meter memory. No load condition should not be recorded in meter memory as a Current circuit open event. f) Power on/off: The meter shall be capable to record power on /off events in the meter memory. All potential failure should be record as power off event. g) High Neutral Current: The meter shall be capable of recording incidences of excess neutral current (if In is in excess of x % of Ib – programmable) .The limits shall be define by the purchaser during the time of final supply. h) Over load/ low load Hours: The meter shall be capable of recording the over load / low load hours in KVA in the meter memory. The over loads limit shall be in terms of % of Transformer rating in KVA (programmable using HHU & BCS). The over load limits shall be define by the purchaser during the Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 409 Technical Specification time of final supply. i) The meter shall also be capable to withstand and shall not get damaged if phase-to-phase voltage is applied between phases to neutral for 10 minutes The meter shall record the total duration of the above abnormalities, time and date of their occurrences & restorations with a snap shot of electrical conditions viz. Voltage, current, kwh energy, PF etc. Logic for calculation of voltage and current imbalance shall be furnished by the tenderer. The meter shall keep records for the minimum last 250 events (occurrence + restoration) for above of abnormal conditions. It shall be possible to retrieve the abnormal event data along with all related snap- shots' data through the meter's optical port or through radio with the help of a hand held unit (HHU) and download the same to the BCS where it shall be available for viewing. All this information shall be made available in simple and easily understandable format. The above shall be selectable and will be in line with Table A6.8 of GUIDELINE DOCUMENT: Data Exchange for Electricity Meter Reading, Tariff and Load Control – Companion Specification. Note: DLMS guideline document should be followed as far as DLMS compatibility of the meter data and communication is concerned. Any additional features asked for in the TS are to be available for viewing (in the display if specifically asked for) and in the manufacturer specific BCS to be supplied along with. Programmability features related to persistence time and threshold values not supported by DLMS may be ignored. 27. TAMPER LOGIC Properly designed meter event logic should be provided. There shall be separate compartments for logging of potential related event, current related event and power on/off event. The bidder should explain the events details in each compartment under their offer. The logging of various events in each compartment should be as under: Once one or more compartments have become full, the last event pertaining to the same compartment will be entered and the earliest (first one)-event should disappear. Thus, in this manner each succeeding event will replace the earliest recorded event, compartment wise. Events of one compartment/category should overwrite the events of their own compartment/category only. Properly defined meter tamper logic should be provided. The tamper logic should be capable of discriminating the system abnormalities from source side and load side and it should not log/record tamper due to source side abnormalities. There shall be separate compartments for logging of different types of tampers/events as follows: Compartment No. 1: 40 % of the tamper memory space shall be allocated for the following current related tampers - CT polarity reversal - CT open circuit - CT short (bypass) Current unbalance Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 410 Technical Specification Compartment No. 2: 35 % of the tamper memory space shall be allocated for potential related tampers including power failure events. Compartment No. 3-7: 25 % of the tamper memory space shall be allocated for other events. 28. BILLING HISTORY & LOAD SURVEY The meter shall have sufficient non-volatile memory for recording history of energy parameters for minimum last six billing cycles (Bill date shall be 00 hrs of the 1st date of the calendar month by default – programmable) and information should be made available at the BCS end. Load survey parameters and data set required for different categories will be made known in due course after consultation with the bidders before ordering. It will be based on the guideline document. Load survey should be of 45 days with 30 minutes demand integration period. These load survey and history data can be retrieved with the help of Meter Reading Instrument on local interrogation or remotely using the remote communication interface. The above load survey data should be available in the form of bar charts as well as in spreadsheets. The BCS shall have the facility to give complete load survey data both in numeric and graphic form. 29. TOD METERING PROVISIONS There shall be a provision up to three Time of Day Zones for Energy (active import, reactive lag while active import & apparent import) and Demand (Apparent demand) registers. TOD provision shall however be as per the guideline document with maximum script identifiers (16) for energy and demand for future use. However at present only three time zones will be used : 06:00 Hrs to 17:00 Hrs, 17:00 Hrs to 22:00 Hrs and 22:00 Hrs to 06:00 Hrs. Number and timing of these TOD Zones shall be user programmable with proper security system. 30. HARMONICS MEASUREMENT THD up to 29th Harmonic shall be measurable that is at sampling rate of 3000/sec. The meter should be capable of measuring fundamental energy as well as total energy. Fundamental energy shall be made available on meter-display and the same only shall be used for billing purpose. The total energy shall be logged in the meter memory and be capable of down loading to the BCS through HHU as well as through the remote communication port and be available for analysis at the BCS end. Note: DLMS guideline document should be followed as far as DLMS compatibility of the meter data and communication is concerned. Any additional features asked for in the TS are to be available for viewing (in the display if specifically asked for) and in the manufacturer specific BCS to be supplied along with. For example total energy is to be used as the billing parameter as per DLMS. However fundamental energy is required to be available in the display or be downloadable in the manufacturer specific BCS. 31. SELF DIAGNOSTIC FEATURE The meter shall be capable of performing complete self-diagnostic check to monitor the circuits for any malfunctioning to ensure integrity of data memory location at all time. The meter shall have indication for unsatisfactory/non-functioning/malfunctioning of the following: a) Time and date on meter display b) All display segments on meter display c) Real Time Clock (RTC) status in meter reading prints out at BCS end Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 411 Technical Specification d) Non-volatile Memory (NVM) status in meter reading prints out at BCS end. e) While installing the meter, it should be possible to check the correctness of Current Transformer, Voltage connections to the meter and their polarity from the functioning of the meter for different voltage injections with the help of vector/phasor diagrams. It should also be possible to check the current and voltage sequence parity. For this purpose suitable software for field diagnosis of meter connections with the help of HHU/Meter Reading Instrument should be supplied. Note: Features not supported by DLMS should be available in the manufacturer specific BCS. 32. OTHER SALIENT FEATURES OF METERS a) It should be possible to check the healthiness of phase voltages by displaying all the voltages on the meter display. b) The meter must be readable in power off condition. For that a battery back-up of suitable capacity shall be provided. Push button for the normal display shall also be used for battery back-up display in power off condition for the manual mode reading of the auto display parameters. It must be possible to power up the battery by means of an external source or by the HHU itself for reading the meter in power off condition by the HHU. In case of an external source an inductive coupling arrangement shall be provided so that it should not be possible to damage the circuit of the meter by applying excess voltage directly in the meter. c) The meter should work accurately irrespective of phase sequence of the mains supply d) The meter should remain powered up and functional even when either of the two phases or one phase along with neutral is available to meter. e) The meter should continue to record accurately as per prevailing electrical conditions even if the neutral of the potential supply gets disconnected. 33. TEST AND TEST CONDITIONS Unless specifically waived off, all tests shall be witnessed by the purchaser. 33.1.1. The Energy meter offered shall be fully type tested at any of the NABL accredited test laboratories as per standards indicated in Clause 5 above. That is the meter offered should have successfully passed all type tests described in the IS 14697 and the meter Data Transfer and Communication capability as per the guideline document. 33.1.2. One (1) out of every one thousand (1000) meters or part thereof shall be subjected to the complete range of type tests after final assembly. In case of any failure to pass all specified tests, the bidder shall arrange to carry out the requisite modifications/replacements in the entire lot of meters at his own cost. After any such modifications and final assembly, two (2) meters selected out of the lot by the Owner's representative shall be subjected to the full range of type tests. The Owner shall accept the lot only after successful type testing. 33.1.3. Further Purchaser shall reserve the right to pick up energy meters at Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 412 Technical Specification random from the lots offered and get the meter tested at third party lab i.e. CPRI / agencies listed at Appendix-C of CBIP publication No-304 / NPL / CQAL/ ERTL / ERDA at the sole discretion of the Purchaser. The supplier has no right to contest the test results of the third party lab or for additional test and has to replace/take corrective action at the cost of the supplier 33.1.4..It shall be the responsibility of the supplier to arrange such tests and Purchaser shall be informed of the date and time of conduction of tests well in advance to enable him to witness such tests. Test charges of the testing authority, for such successful repeat type tests, shall be reimbursed at actual by the Purchaser. 33.1.5. The meters used for type testing shall be separately identified, duly marked, and supplied to the Owner in case they are fully functional and as good as other (new) meters, after necessary touching up/refurbishing. In case this is not possible, the bidder shall provide their replacements at no extra cost to Owner. 33.1.6 The Bidder shall arrange all type te sting specified above, and bear all expenses for the same. Type test certificate shall be submitted along with the offer and the same shall not be more than 36 months old at the time of bid submission. Make & type of major components used in the type-tested meter shall be indicated in the QAP. 33.2. Acceptance Test 33.2.1. All acceptance tests as per relevant standards shall be carried out in the presence of utility representatives. 33.2..2. Additional acceptance shall include Surge withstand (SWC) for 6 kVp, as per IEC 62052-11, Lightning impulse test and HF disturbance test as IS 14697. One sample meter per order from one of the offered lot shall be subjected to SWC/other semi-destructive tests. Meters after tests shall not be used. 33.2..3. Accuracy tests shall be performed at the beginning and at the end of the acceptance tests specified. 33.3 Routine Test 33.3.1. All routine tests as specified in table 18 of CBIP Technical Report No. 88 shall be carried out on each individual meter and routine tests certificates shall be submitted for approval of purchaser. 34. QUALITY ASSURANCE: 34.1. The manufacturer shall have a comprehensive quality assurance program at all stages of manufacture for ensuring products giving reliable, trouble free performance. Details of the bidder‘s quality assurance and test set up shall be furnished with the bid. A detailed quality assurance program shall be finalized with the successful bidder during the award stage. Bidder shall furnish following information along with his bid: i) Organization structure of the manufacturer and his main sub-suppliers (PCBs, SMT cards, CT/PT) with details of ‗QA‘ setup, overall workflow; ii) Copy of system manual showing ‗QAP‘ (Quality Assurance Plan) as actually practiced during manufacturing and final testing. iii) List of raw materials and critical components (ASIC chip, crystal clock, memory register Chip, transformers, optical ports etc.) with their suppliers; iv) Stage inspection of product before final testing; v) Procedure adopted for ‗In-situ‘ testing of PCBs, after placement of surface mounted component, for quantitative parametric variation of tolerance by self or sub-contractor. vi) Testing and calibration facility, date of calibration of test bench, manpower data Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 413 Technical Specification of bench operators; vii) Sample copies of test certificate of bought out components. 35. GUARANTEE 35.1. Equipment (Meter) supplied shall be guaranteed for a period of 66 months from the date of supply or 60 months from the date of installation, whichever is earlier. Bidders shall guarantee to repair or replace the meters and meter boxes and other accessories, which are found to be defective/ inoperative at the time of installation, or become inoperative/ defective during guarantee period. Replacements shall be effected within 1 month from the date of intimation. The bidder shall extend the guarantee of 5 years. However the backup bank guarantee provided by the bidders shall be valid for 2 years only. 36. FIXING & CONNECTION ARRANGEMENT Manufacturer shall ensure following technical points: i) Meter shall be suitable for mounting on Simplex type vertical panel with front door; CAT-M4 disconnecting type TBs to be used for Current circuit; Panel wiring to be properly dressed and harnessed; External cables to enter panel from bottom gland plate using double compression glands. ii) Meter installation and inter-connection from existing CT/PT connections to energy meters in the panel shall be in the scope of contractor/bidder. iii) Energy Meter terminals block shall be adequately sized with regard to maximum conductor dimension, commensurate with current rating of Energy Meter. 37. SOFTWARE 37.1. Licensed copies of the relevant software shall be made available for installation on each Hand Held Unit (HHU) /Common Meter Reading Instrument (CMRI) and Base computer software (BCS) for installation on the server and other terminals by the supplier. HHU/Common Meter Reading Instrument (CMRI) would be loaded with userfriendly software (windows based) for reading, downloading meter data and relevant programming transaction in the meter with proper security system. 37.2. Windows based user interactive Base Computer Software (BCS) shall have to be supplied for efficient and speedy recovery of data from HHU/CMRI/Meter(by remote communication) and downloading instructions from base computer software to HHU/CMRI/Meter(by remote communication). This BCS should have, amongst other requirements, features and facilities to communicate, download and display meter data as described in the “Guideline document – Data Exchange for Electricity Meter Reading, Tariff and Load Control (Companion Specification for IEC 62056 series of Standards)” from DLMS/COSEM meters. The BCS should also have facility to convert meter reading data into user definable DBF (Access) and spreadsheet format for integrating with the purchaser's billing system. Here again an "Export wizard" or similar utility shall be available whereby user can select file format, the variable data to export, the field width selection of each variable so that it may be possible for the user to integrate the same with the user‘s billing data and process the selected data in desired manner. The BCS shall also allow for viewing and easy analysis of the meter data acquired and for exporting that data in ASCII or CSV format. It should have in general the following features: Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 414 Technical Specification i) ii) iii) iv) v) vi) It shall allow collecting of meter data on direct communication with the meter through wires as well as through remote system. It shall be possible to view the meter data and details in user friendly manner (Windows Based Platform). New users with their level of access rights could be defined and managed by supervisors based upon their usage requirement. It shall be possible to maintain a meter information database, to add, edit, delete meters from the meter information database with proper authentication. The meter information database shall have amongst others the information relating to meter serial no, meter location, meter status, CT, PT ratios, KVA ratings etc. BCS must have provision to manage users and roles. It shall be possible to create a user and assign him privileges to perform specific types of operation according to the ―Role‖ assigned to him. It shall be possible to define a role and link it with ―Rights‖ of using different options. If rights are not assigned for a particular option, a ―User‖ with that ―Role‖ shall have no right to use or view that option. The software must have the user friendly GUI and User Interface should be customisable by the user. It shall be possible for a user to a) Display or hide a column in the Meter List Pane b) Change the column width c) Activate & apply column wise filter for displayed list d) Sort the order of the displayed list. The sorting can be enabled on any of the displayed field / column e) Group the meter list according to a field displayed in a column and then further sub-group the list according to another field 37.3. The software‘s shall have the flexibility to generate at least the following sets of reports amongst others Energy Accounting reports Billing Point reports Load survey reports Tamper information reports 37.4. Billing reports to include customer ID, Name & Address, connected Load, meter status, billing cycle, historical meter reading, date and time, current meter reading, date and time, Maximum Demand, date and time of Maximum Demand occurrence 37.5. .Load survey report for a pre determined time i.e. from ________ date to ___________ date, to include the following. Customer ID, meter number, Consumer Connectivity references i.e. identity & location of pole / Distribution transformer reference, feeder reference, subdivision reference, division reference, circle reference, time, date, maximum demand (kW),KVAR, kWh, power factor, kVAh, MD reset count, power on hours, outage duration, number of outages, Voltages max R, Y, B date time and duration, Voltages minimum R, Y, B date time and duration, load factor as (energy consumed/(maximum demand x power on hours)), average load as (energy consumed / power on hours), TOD max DEMAND and duration, Average current phase wise. 37.6. The load survey data should be available in the form of bar charts as well as in spreadsheets. The BCS shall have the facility to give complete load Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 415 Technical Specification survey data both in numeric and graphic form. The exact parameters set and the period for the load survey report for each category of meters will be specified in due course after consultation with the bidders prior to ordering. 37.7. Tamper reports to include for a pre determined duration or month wise, tamper count, tamper duration and tamper history for each of the meters. 37.8. Bidder will provide soft copy of all the software in CD form along with the meters supplied. 37.9. Bidder to install & demonstrate working of software programmes on the HHU/CMRI‘s of APDCL a) Base computer station software for accepting data from hand held unit/CMRI/ for Processing, generating reports and downloading instructions from the BCS to HHU/CMRI for onward transmission to DLMS/COSEM meters of specific makes.. b) Dial-up software for accepting data from the meter by remote communication means to the BCS, processing data, & generating reports. 38. SOFTWARE SECURITY The BCS shall have multilevel password for data protection and security. The first level shall allow the user to enter the system. The different software features shall be protected by different passwords. The configurable of passwords shall be user definable. The software installed on one PC shall not be copied on another PC without additional security. 39. HELP SYSTEM Exhaustive online & offline help shall be an integral part of the software so that user can use all the features of the software by pulling down the help contents from the user friendly menus for any references. 40. DATA SECURITY In addition to the basic security, selective advanced security with encryption and authentication by the use of NIST SP 800-38D as specified in the companion standard guideline document must be provided for. The security system must be adequate enough not to allow data manipulation at any stage. The system should be able to achieve security through authenticated transaction on the HHU/CMRI form the back office software only. Compatibility of the meter for any relevant security system to be developed by the SI for proper data protection is an essential requirement. For further elaboration, clause 7 of the Guideline Document related Association and Data Security may be seen. 41. Conformance Testing :Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 416 Technical Specification All the categories of meter are required to comply strictly with the Conformance Testing clause as detailed out in Annexure A of the Guideline Document. Conformance test certificates are to be provided with the sample meters. GUARANTEED TECHNICAL PARTICULARS FOR 3 PHASE 4 WIRE CT/CT PT OPERATED TRIVECTOR ENERGY METER Sl. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Item Bidder‟s data Type of Meter Application Standard to which the meter confirm Rated Voltage Rated Current Frequency Overload capacity Minimum starting current in % of base current Power Factor Range Power loss in potential circuit Power loss in current circuit Change in error due to a. Variation in frequency b. Variation in temperature c. Variation in voltage Accuracy Class Type of Energy Registration Mechanism. MD Reset Mechanism Dynamic Working range a) Voltage b) Current Type of load (linear, non linear, balanced /unbalanced at any P.F.) Total Weight of meter Dimension of the meter Details of meter base & cover Terminal Cover details Capability for fraud Prevention & detection Sealing and Locking Arrangement Display details i. Display Cycle (descriptive in order of display sequence) auto and manual Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 417 Technical Specification 25 26 27 28 29 30 31 32 33 34 35 ii. Period of display of each parameter iii. Display scroll-lock facility iv. Backlit LCD v. display off period between two cycles vI. No of digits of display and height of character. Memory Capacity Non volatile memory retention capacity Powering on facility in absence of mains Tamper data preservation capacity : a) on display b) with meter data downloading provisions. Tamper logic in detail Load Survey details : a) Parameter measured & Logged b) Logging interval c) No. of days of Load Survey Time of the day Zone Provision Type of communication: a) Local-Optical port details b) Additional Communication port for AMR compatibility Real Time Clock Self Diagnostic Features (Provide Details) Certification Marks Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 418 Technical Specification TECHNICAL SPECIFICATION FOR LT RESIN CAST RING TYPE CURRENT TRANSFORMER FOR OUTDOOR APPLICATION 41.0 SCOPE: The scope covers packing, supply and delivery at destination, subsequent storage, erection and commissioning at site (including insurance during transit and storage), of Resin cast Ring Type LT Current transformer (CT), of accuracy class 0.5 for Distribution transformer Metering. CT‘s should be outdoor type and suitable to be mounted on the bushing of LT side of transformer. Suitable fixing arrangement to mount the CT on the transformer‘s bushing shall be provided with each CT. Current Transformers are required for 25 KVA TO 1000 KVA‘s distribution transformers. 41.1 APPLICABLE STANDARDS: IS 2705 IS 4201 IS 2629 41.2 Current Transformers specifications Application guide for CT Hot dip galvanizing TYPE AND RATING OF L.T.CURRENT RANSFORMERS: LT CTs shall be of the following type and ratings: Sr. Characteristics no Nominal system voltage 1. Highest system voltage 2. Insulation level (HVPF test 3. voltage for 1 minute) Frequency 4. 5. Transformation ratios 6. Type 7. Rated output 8. Class of accuracy 9. Short time thermal current 10. Rated continuous thermal current 11. Instrument security factor 12. Ratio (current) error max. 13. Phase angle error max. 14. Temperature rise over values Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Values 415 Volts 660 Volts 3 KV 50 Hz 100/5, 200/5, 400/5A,600/5A,800/5A, 1000/5A, 1200/5A Ring type 5 VA (2.5VA for 100/5A) 0.5 Minimum 5 K Amp. For one second 120% of the rated Shall not exceed 5. Shall not exceed the values prescribed in IS: 2705/1992. Shall not exceed the values prescribed in IS: 2705/1992. Shall not exceed the values Assam Power Distribution Company Ltd 419 Technical Specification ambient temperature 55 deg C at rated continuous thermal current (1.2 Ip). 15. Supply system variation prescribed in IS: 2705/1992. Voltage: 70% to 120% Vref Frequency: 45 Hz to 55 Hz 41.3. GENERAL TECHNICAL SPECIFICATION OF RESIN CAST RING TYPE L.T. CURRENT TRANSFORMERS: 41.3.1 Current transformer shall have an opening in the center to accommodate a primary conductor that may be cable (with the lugs) / bus-bar / Secondary terminal of Distribution transformer. The current transformers shall have rated burden as 5 VA ( 2.5VA for 100/5A). The terminals should be complete with connecting lugs. 41.3.2 Current transformers shall be of Resin cast type, suitable for outdoor installation, class of insulation shall be ―F‖ as specified in IS:2705 made of cyclo elephatic resin should be used for manufacturing these CTs. The material of CT may be verified at material lab / Details of material shall be provide . 41.3.3 For above 100/5A & above ratio CTs internal diameter of LT CT shall be suitable to pass the cable of 120% current rating of CT and fit on bushing of Transformer of specified ratings above. 41.3.4 The polarity marking on the offered CT primary & secondary side should be embossed. 41.3.5 A three core (2.5sq. mm) HR FR PVC insulated flexible multi strand copper cable shall come out directly from the CT as secondary terminal. The length of the wire shall be around 3 Mtrs for 100/5, 200/5, 400/5 & 600/5A, 4 Mtrs for 1000/5A & above current ratings. Secondary wire shall directly connect to the energy meter‘s terminals. Pin type lugs shall be required on open end of cable. Proper colour coding/identification shall be used to identify the CT & PT leads. 41.3.6 LT CTs shall be of Brick red colour 41.3.7 Type test report of same design and out door type LT CTs shall be submitted along with the bid. One no sample of each rating is required to be submitted along with the bid document for verification otherwise bid will be considered non responsive. 41.3.8 CT shall be of similar design as shown in drawing attached. 41.4 TESTS: 41.4.1 ROUTINE TEST & ACCEPTANCE TEST a. Current Transformer shall comply with and shall be subjected to all routine tests prescribed in relevant IS: 2705/1992 b. Routine tests as per relevant standard along with accuracy test as per clause 7.2 of IS: 2705 (Part.II) c. All routine tests as stipulated in the relevant standards shall be carried out and routine tests certificates shall be submitted before inspection d. Schedule of routine & acceptance test for CT: i. Verification of terminal marking and polarity. ii. Determination of error according to the requirement of appropriate accuracy class at 20% and 120% with Full and Quarter Burden. 41.4.2 Type Test The CT offered shall be fully type tested at any of the NABL accredited test laboratories as per relevant standards. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 420 Technical Specification 41.4.3 Schedule of type test for CT (As per Reference Standard) to be conducted and certified by NABL Certified Lab / test house: a. b. c. d. e. f. 41.5 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. Verification of terminal marking and polarity. High voltage power frequency test. Over voltage inter-turn test. Determination of error according to the requirement of appropriate accuracy class at 5%, 20%, 100% and 120% with Full and Quarter Burden. Short time current test and Peak dynamic current test. Temperature rise test NAME PLATE AND MARKING: The ratio, VA burden, class of accuracy, name of manufacturer / year of manufacturing shall be printed on metallic nameplate of CT. The ratio & polarity should be marked on the body of the LT CTs. Self adhesive, laminated, printed label must be having following details: R-APDRP Works Manufacturer's name Manufacturing month and year. Batch No Property of ASEB Ratio, Burden & Accuracy Class Applicable Standard I.L. STC Rating Continuous thermal current Caution against open secondary Guarantee Period. 41.6 DRAWING APPROVAL: Party must get final drawing approval before commencement of commercial production/supply. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 421 Technical Specification GUARANTEED TECHNICAL PARTICULARS FOR LT CTs Sl. N 1. Type / Capacity 2. a) Rated Voltage Characteristics Bidders Data b) c) d) e) f) 3. Highest System Voltage Rated Primary Current Rated Secondary Current No. of Cores Rated Continuous Thermal Current temperature rise over ambient g) One minute withstand Power frequency Voltage Class of Accuracy - 0.5 4. Burden – a) 100/5A : 2.5 VA b) 200/5A & above 5 VA 5. Dimension in mm i. Inner Dia of CT ( CT Rating wise) ii. Length of secondary lead 100/5A, 200/5A,400/5A, 600/5A - 3 Mtrs. iii. Length of secondary lead 1000/5A & above current rating – 4 Mtrs. 6. Material i) Core ii) Conductor iii) Insulation ( Class : F as per IS 2705) Type Test Report Conformance Standards 7. 8. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 422 Technical Specification Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 423 Technical Specification TECHNICAL SPECIFICATION FOR SMC DTC METER BOXES COMPRISING METER 1) SCOPE: This scope shall cover design, engineering, manufacture, testing at manufacturers works before dispatch, packing, supply and delivery at destination, subsequent storage, erection and commissioning at site (including insurance during transit and storageof anti-corrosive, dust proof, rust proof, shock proof, self extinguishing property, resistant to heat, vermin & water proof, ultra violet stabilized and pilfer resistant SMC distribution transformer meter boxes made of thermosetting plastic i.e. Glass reinforced polyester sheet moulding compound (SMC) confirming to IS : 13410 (1992) and attached technical specification, drawing and IS : 14772:2000. 2) CONSTRUCTION OF METER BOX: a) The meter box shall comprise of moulded single base and doors. The construction the box shall be of single base type. The meter box shall generally comply with the provision of IS-14772. The boxes shall be suitable for outdoor/indoor application. Meter box shall have minimum inside size of 450 mm (H) X 375 mm (W) X 200 mm (D) and thickness minimum 2.0 mm as per enclosed drawing. Colour of the box shall be off white. The thickness of the box shall not be less than 2.0 mm on all sides including door. The top surface of meter box shall have tapering shape for easy flow of rainwater. b) The meter box shall have a groove all round to hold soft rubber gasket with corresponding tongue in door to ensure tongue & groove type sealing arrangement in addition to gasket sealing for protection against entry of dust and water. c) The door shall rest on the base of box in such a way that any access from outside to the meter is not possible. The door in closed position should be overlapped on collar of base such that direct entry of screwdriver or tool is not possible. d) The box shall confirm to ingress protection level IP-54 e) All corners of the meter box should be round and not pointed ones. Meter mounting in the box shall be fitted with raised SMC sheet of 4 mm thickness so as to facilitate mounting of the meter . f) The box should be capable to house of LT TVM and 1 No. GSM / GPRS modem. Door with locking and sealing arrangement should be provided. g) Meter box cover shall be fitted to base by concealed stainless steel strip hinges. The SMC meter boxes shall be closed by S.S.‘U‘ clamp of minimum 0.8 mm (+ 0.1mm) thickness for holding and locking of the door. The ―U‖ clamp shall have 4mm diameter hole through which it is possible to seal the box for sealing purpose. h) For meter reading the box should have a window with toughened/triplex glass fixed with S.S. frame from inside. The box should have a window of size 140mm X 120mm provided with glass as shown in the drawing. i) For CT secondary PT supply cable entry 1 Nos. hole having diameter of minimum 19mm shall be provided on bottom of box with good quality polymeric gland having diameter of minimum 19mm as shown in the drawing. j) One no. earth bolt of 6mm diameter x 25mm length with 2 number nuts and 2 nos. washers plus a spring washer shall be provided. The earthing arrangement shall be of M.S. with zinc passivated. Earthing symbol is to be provided near the earthing bolt. k) All metal parts shall be zinc passivated if not mentioned specifically. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 424 Technical Specification l) The meter door shall accommodate the 9-pin D type male connector of the cable used for interface between meter and HHU/CMRI as defined in class 4.2.1 of CBIP technical report no 88. This cable will have meter optical sensor terminating at the other end of the cable and permanently fixed to the optical port of the meter. The nine pin D type mail connector should be provided with a suitable sealable cap. For downloading data from meter through CMRI the operator has to break the seal of the cap, remove the cap download the data put back the cap and again seal the cap properly. This arrangement is provided to ensure that data stored in NVM is downloaded from the door of meter box without opening the door of the meter box and physically approaching the meter m) Similarly the RS-485 port should also be brought on the cover of the door with the proper sealing arrangement n) Printing: Metallic/engraved label containing the letters R-APDRP, Circle Name and the PO no and date shall be engraved/embossed on the top cover of the box. The name of manufacturer shall be engraved/embossed on the bottom half of the box. A blank sticker shall also be pasted on the o) meter box for use of field staff to indicate service no. etc. The front cover shall be embossed with following Notice: Property of APDCL Breaking of Seals or any Tempering With Meter is a Cognizable Offence p) The fixing arrangements shall not be complex and it shall be easily approachable for connections when the door is open and is completely tamper resistant once it is sealed. q) The box shall be robust and sufficient space for convenience in metering with adequate space for meter and proper arrangement for fixing up of communication modem (AMR compatibility provision). r) The dimensional drawing giving details of the meter box shall be enclosed with the bid. 3) 4) 5) 6) 7) 8) 9) GUARANTEED TECHNICAL PARTICULARS: Guaranteed technical particulars are given in enclosed annexure bidder shall submit the data in given Performa. INSPECTION AND TESTING The bidder has to offer the boxes for inspection at his works before dispatch. The manufacture will offer all facilities to inspectors without any charge. DESPATCH The SMC meter boxes shall be so dispatched as to ensure that no damage occurs during transport where they may be subject to rough handling. TYPE TEST CERTIFICATE: The bidder shall submit type test report as per IS-144772-2000 & IS-13410 : 1992 from CIPET, Ahmedabad/ ERDA, Baroda along with the offer. Type test certificate should not be older than 3 years as on the date of tender opening. TYPE TEST Type test report as per requirement of this specification shall be furnished before commencement of supply RAW MATERIALS The manufacturer has to submit the test certificate for the material used in the lot offered and document for purchase of raw material. ROUTINE TEST: Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 425 Technical Specification Manufacturer has to carryout routine test during production to check the essential requirements which are likely to vary during production. Manufacturer has to keep records of the same and to be produced for verification of inspector when asked at the time of inspection of lot. 10) ACCEPTANCE TEST: The acceptance tests shall be carried out on randomly selected samples. 11) FACILITY The bidder shall have facility to test the box for routine tests and acceptances as per IS-14772:2000 and IS-13410 at their works. The bidder has to submit list of machinery & equipment/testing instrument etc. 12) TENDER SAMPLE A sample as per specifications will have to be submitted for approval. 13. Pilfer Proof Box Tests Type Tests: The following tests are to be conducted on the pilfer proof box at an NABL accredited laboratory. I. II. III. IV. V. Test of material identification Test for mechanical strength as per IS 5133 Test for water absorption as per IS 5133 Test for stability at high temperature as per IS 5133 Test for withstanding temperature of boiling water for 5 minutes continuously for non-distortion or softening of material. VI. Glow wire test at 650oC as per clause 5.2.4 of CBIP Technical Report No.88 read with amendments. Acceptance and Routine Tests: a) Acceptance Tests: The following shall constitute acceptance test for box. i. Physical verification of dimensions of the box. ii. Compatibility of the box for housing the meter for ensuring ease of connections and reading the meter. b) Routine Tests i. Routine test certificates as per relevant standards shall be furnished for approval. ii. Physical verification Sd/Chief General Manager (Material):APDCL Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 426 Technical Specification GUARANTEED TECHNICAL PARTICULARS OF BOX Sr. No. 1 2 3 4 5 6 7 8 9. 10 11 12 PARTICULARS METER BOX DETAILED PARTICULARS TO BE OFFERED BY BIDDER Maker‘s name Material To be intimated by the supplier Glass reinforced polyester sheet moulding compound Grade of material SMC confirming to IS:13410:1992 grade S1 Properties of material of construction of meter box Flame retardant As per IS-11731 (Min FV0) test Exposure to flame Self-extinguishing (ref std IS:4249) Degree of IP-53 as per IS-12063/87 protection Heat distortion 1500C (min) as per IS:13411 temp. Inside dimension of To be mentioned by the supplier meter box a. height 450 mm (min) b. width 375 mm (min) c. depth 200 mm (min) d. thickness 02 mm (min) Earthing arrangement Earthing bolt One no. of earthing bolt of MS with 2 nuts and 2 washers shall be provided on RH side of box. Earthing sign has to be provided near to earthing bolt. Dia & length of Dia 6 mm length 25 mm earthing bolts Locking For holding & locking of door with base arrangement two nos (min.) of ―U‖ shaped clamps to be provided Sealing Holes for wire seal arrangement Cable entry holes Cable entry holes 1 nos with minimum 0 19MM polymeric gland on bottom of the box. Colour of box Off white Window having Window size 140mm X 120 mm triplex glass Fixing of glass Fitted from inside in such a way that it can not be replaced without opening door (with S.S. frame all around) Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 427 Technical Specification SECTION - 5 SPECIFICATION OF POLY CARBONATE SEALS REQUIRED FOR SEALING METERS & METERING SYSTEM 5.01 Seal should be made of polycarbonate with ultra violet additive & should not be affected by boiling water, muriatic acid. 5.02 The seal should withstand temperature up to 147 C. 5.03 Seal should be available in Clear / Red / Blue / Yellow / Amber / Green / Grey colour and should be transparent. 5.04 Every seal should have 6 ― twisted strand stainless steel wire. 5.05 Seal should have facility to print mono gram / name of company 5.06 Every Seals should have a unique seven-digit number. Numbers shall be printed on seal including the anchor cap-using laser marking which shall not be erased using any tool or by any chemical reaction. Both the seven digit seal numbers should be visible separately after closing the seal. 5.07 Seals should have tamper proof, internal ― anchor ― locking mechanism that permanently secures the wire upon closing. The mechanism should be designed in such a way that its original position can‘t be restored after any effort of tamper or breaking of seals 5.08 Sealing mechanism shall be designed in such a way that it can be sealed without using any pliers or tools. 5.09 Seal should be constructed of two parts, first the main body ( female type)& second the anchor (male type) having locking mechanism. Both the part should be designed in such a way that once the seal is closed the two parts can‘t be separated. 5.10 Seal should be patented. Copy of patent shall be submitted along with offer. 5.11 Packaging: Seals shall be supplied in packet of 100 seals. Each packet shall be labeled for following information Client Name Purchase order number &date Serial number range in the form of bar coding. 5.12 Seals shall be provided with tracking & recording software. The software shall have following features Software should have facility of defining the system controller Facility to enter serial number of seals with the help of bar code scanner. Receiving of seal in the system and with authentication like signature. Facility to identify the concern who is responsible for receiving of seals and nominated by system supervisor. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 428 Technical Specification Provision to define different type of seals for various uses. Software should have facility of report generation for inventory & issue records. Facility to track for relevant data for individual seal entered in the system. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 429 Technical Specification SPECIFICATION FOR HT COMBINED CT- PT SETS FOR 3P 4W METERING Combined 3 element CT-PT sets of specified PT and CT ratios of accuracy class 0.2S, earthed neutral shall be supplied for high tension 3 phase 4 wire metering with AMR compatibility for R-APDRP projects. The combined sets are to be supplied with metering cabinet of specified design along with other necessary accessories for installation and commissioning of the complete metering system for Ring Fencing Metering under the projects. The schematic diagram of the metering system with approximate dimensions are enclosed for ready reference. The core construction material for the metering cabinet may be same as that of the LT metering cabinet or MS steel of 18 gauze, properly coated with anti-corrosive paints. 1. APPLICABLE STANDARDS: IS 3156 Part 1 & 2 IS 2629 Voltage Transformers specifications Hot dip galvanizing 2. GENERAL TECHNICAL REQUIREMENT: Rated Voltage : Rated Secondary Ct (I Basic) 33 kV/110 V & 11 kV/110 V as per requirement : -/5 & -/1A as per requirement specified Rated Frequency : 50 Hz. Rated Burden : CT burden-15 VA, PT burden- 50 VA Accuracy class : 0.2S Power Factor : Unity to Zero (all power factor lag / or lead). Temperature : The standard reference ambient temperature for Performance shall be 40 °C. Supply system variation : Voltage Vref 70% to 120% Frequency : 45 Hz to 55 Hz Highest system voltage system : 12 kV for 11 kV system and 36 kV for 33 kV Current Transformer Ratio 25/1A, : 15/5A, 25/5A, 50/5A, 100/5A, 200/5A, 15/1A, 50/1A, 100/1A as per specified requirement 3. GENERAL CONSTRUCTIONAL REQUIREMENT a) The combined sets are to be of single ratio. b) In the primary studs terminal clamps suitable for Raccon conductors should be provided. c) Insulation cap in HT primary bushings and conductors should be provided with self locking system and sealing facility. Cap opening towards the conductor shall be extended by atleast 20 cms so that the insulation of the connecting conductor goes inside by atleast 10 cms, d) No HT fuses are to be provided in the sets. e) Arcing horns are not required in the sets. f) Pressure valve is to be provided in the main tank. g) Secondary terminal box has to be provided with double cover sealing Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 430 Technical Specification provisions h) Inspection manhole is not required in the sets. i) Sealing provision in the top cover has to be provided. 4. RATING PLATE Self adhesive, laminated, printed label must be having following details: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. R-APDRP Works Manufacturer's name Manufacturing month and year. Batch No Property of ASEB Ratio, Burden & Accuracy Class Applicable Standard I.L. STC Rating Continuous thermal current Caution against open secondary Guarantee Period. 5. DRAWING APPROVAL: Party must get final drawing approval before commencement of commercial production/supply. 9. TEST AND TEST CONDITIONS Type Test The CT offered shall be fully type tested at any of the NABL accredited test laboratories as per relevant standards. Routine & acceptance test Acceptance and routine test on the sets will be conducted as per the provisions of the relevant standards Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 431 Technical Specification GUARANTEED TECHNICAL PARTICULARS FOR CT- PT SETS S. No. SUPPLIER‟S DATA PARTICULARS 1. Manufacturers Name & Address 2. 3. Type / Capacity a) Rated Voltage b) Highest System Voltage c) Rated Primary current No. of cores d) Current/Secondary e) f) 4. 5. Rated Output Rated continuous Thermal Current Temperature rise over ambient g) One minute withstand Power Frequency Voltage Class of ACCURACY Limits of current error and phase displacement error as a percentage of the rated currents i) 5% ii) 20% i) 100% ii) 120% 6. Material i) Core ii) iii) Conductor Insulation iv) Base v) No. Of CTs 7. Secondary Termination 8. Standard length of cable 9. Conformance standards Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 432 Technical Specification GENERAL & OTHER REQUIREMENTS 1. Meter Testing Equipment The specified number of sets of complete equipment required for in situ functional checking and rough testing of accuracy of the meters shall be supplied to the Purchaser. It shall include secondary v oltage and current injection equipment (3-phase, balanced, variable power factor), precision instruments, timing device etc., which have a sturdy construction suitable for frequent transportation. The equipment shall be easily portable, and shall generally comply with IEC-736, for type and acceptance testing of Energy Meters of 0.5S/0.2S class (Table -1 of IEC 736, 1982). In addition to the above, a test output pulse counting device, with an accurate built-in timer, shall be provided, for independent checki ng of Wh measurement accuracy against Owner's precision instruments. 2. Installation and Commissioning The static energy meters specified above shall be installed at the premises The exact location and time -table for installation shall be finalized by the purchaser in due course, and advised to the bidder. The Bidder shall be responsible for total installation and commissioning of the meters (along with test blocks, if supplied separately) as per Owner's advice, including unpacking and inspection on receipt at site, mounting the meters, connection of input& output cables to the meters including any required rewiring, functional testing, commissioning and handing over. The Bidder's personnel shall procure/carry the necessary tools, equipment, materials and consumables (including insulated wires, lugs, ferrules, hardware etc.). As a part of commissioning of BCS/HHU/CMRI, the Bidder shall load the relevant software into the PCs at the Base computer stations and other equipments, and fully commission the total m eter scheme as per R-APDRP requirement. He shall also impart the necessary instructions to Utility engineers. Following technical information shall be furnished by the Bidders in their offers: i) ii) iii) iv) v) vi) Foreseen dimensions of proposed meter. Expected weight of proposed meter. Foreseen dimensions of HHU/CMRI Expected weight of HHU/CMRI Details of Meter testing equipment proposed to be supplied. Dimensions and weight of the test block, if supplied separately. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 433 Technical Specification 3. QUALITY ASSURANCE PLAN The bidder shall furnish the following information along with his bid; failing which his bid shall be liable for rejection. Information shall be separately given for individual type of material offered. I. The structure of Organization II. The duties and representatives assigned to staff ensuring Quality of work III. The system of purchasing, taking delivery and verification of materials IV. The system for ensuring quality of workmanship V. The quality assurance arrangements shall conform to the relevant requirement of ISO 9001 or ISO 9002 as applicable VI. Statement giving list of important raw materials names of sub-suppliers for the raw materials, list of sub-suppliers for the raw materials, list of standards according to which the raw materials are tested. List of test normally carried out on raw materials in presence of vendor‘s representative, copies of test certificates. VII. Information and copies of test certificates as in (i) above in respect of bought out accessories. VIII. List of manufacturing facilities available. IX. Level of automation achieved and lists of areas where manual procession exists. X. List of areas in manufacturing process, where stage inspections are normally carried out for quality control and details of such tests and inspections. XI. Lists of testing equipment available with the bidder for final testing of equipment specified and test plant limitation. If any, vis-à-vis the type, special acceptance and routine tests specified in the relevant standards. These limitations shall be very clearly brought out in schedule of deviations from specified test requirements. The vendor shall also submit following information: iii) List of raw materials as well as bought out accessories and the names of sub-suppliers selected from those furnished along with offers. iv) Type test certificates of the raw materials and bought out accessories if required by the utility. iii) Quality Assurance Plan (QAP) withholds points for purchaser‘s inspection. The quality assurance plan and purchasers‘ hold points shall be discussed between the purchaser and vendor before the QAP is finalized. Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 434 Technical Specification 4. DOCUMENTATION 4.1 All drawing shall conform to International Standards Organisation (ISO) ‗A‘ series of drawings sheet/India Standards Specification IS: 656. All drawings shall be in ink and suitable for microfilming. All dimensions and data shall be in S.I. Units. 4.2 List of Drawings and Documents: The bidder shall furnish the following along with bid. i) Two sets of drawings showing clearly the general arrangements, fitting details, electrical connections etc. ii) Technical leaflets (user‘s manual) giving operating instructions. iii) Three copies of dimensional drawings of the box for each quoted item. 4.3 The manufacturing of the equipment shall be strictly in accordance with the approved drawings and no deviation shall be permitted without the written approval of the purchaser. All manufacturing and fabrication work in connection with the equipment prior to the approval of the drawing shall be at the supplier‘s risk. 4.4 Approval of drawings/work by purchaser shall not relieve the supplier of his responsibility and liability for ensuring correctness and correct interpretation of the drawings for meeting the specification. 4.5 The requirements of the latest revision of application standards, rules and codes of practices The equipment shall conform in all respects to high standards of engineering, design, workmanship and latest revisions of relevant standards at the time of orde4ring and purchaser shall have the power to reject any work or materials which, in his judgment is not in full accordance therewith. 4.6 The successful Bidder shall, within 2 weeks of notification of award of contract, submit three sets of final versions of all the drawings as stipulated in the purchase order for purchaser‘s approval. The purchaser shall communicate his comments/approval on the drawings to the supplier within two weeks. The supplier shall, if necessary, modify the drawings and resubmit three copies of the modified drawings for their approval. The supplier shall within two weeks, submit 30 prints and two good quality report copies of the approved drawings for purchaser‘s use. 4.7 Eight sets of operating manuals/technical leaflets shall be supplied to each consignee for the first instance of supply. 4.8 One set of routine test certificates shall accompany each dispatch consignment. 4.9 The acceptance test certificates in case pre-dispatch inspection or routine test certificates in cases where inspection is waived shall be got approved by the purchasers. 5. INSPECTION 5.1 The inspection may be carried out by ASEB at any stage of manufacturing/ installation/ commissioning. Inspection and acceptance of any equipment under this clause shall not relieve the bidder of his obligation of furnishing the equipment in accordance with the specification and shall not prevent subsequent rejection if the equipment is found to be defective. 5.2 The bidder shall keep ASEB informed in advance about the status of manufacturing/ installation/ erection/ commissioning programme so that arrangements can be done for inspection. The purchaser (ASEB) reserves the right to insist for witnessing acceptance and routine tests of bought out items, Bidding Document for Part-B, R-APDRP, Version-1, May‟ 2012 Assam Power Distribution Company Ltd 435 Technical Specification with an advance intimation of two weeks. 5.3 The purchaser (ASEB) reserves the right to get any meter/box type-tested, from any of the lots offered for inspection received at any destination, at purchasers‘ expense and relevant clause will apply for rejection in case of failure to pass the tests. 5.4 The bidder shall indicate names of reputed agencies and inspection charges for each lot/ activity clearly. The purchaser reserves the right to appoint at own cost, any inspection agency to carryout inspection. 6. CAPACITY B