Department of Purchasing Services (305) 348-2161 FAX (305) 348-3600 March 19, 2010 ITB90-009 FOOTBALL STADIUM PRESS BOXES / ADDITION OF EAST & WEST SUITES, FM 090407 ADDENDUM #2 Re: Questions and Answers Add: Wiring Device Specification section and Subcontractor Reporting Form See attached VENDORS MUST ACKNOWLEDGE RECEIPT OF THIS ADDENDUM BY SIGNING BELOW AND SUBMITING THIS EXECUTED DOCUMENT WITH YOUR RESPONSE. FAILURE TO EXECUTE AND RETURN THIS ADDENDUM FORM WILL DISQUALIFY YOUR FIRMS’ RESPONSE. This Addendum shall become part of your firms’ competitive solicitation response and the subsequent contract documents if applicable. This addendum document must be attached to your Solicitation Response. Failure to execute this document and return of same with your firms’ competitive solicitation response will be grounds for immediate disqualification. Company Name _________________________________________________________ Address _________________________________________________________________ Telephone/Fax/Email________________________________________________________ Signature ________________________________________________________________ Form#PS008 CD04/03/07 ADDENDUM #2 Re: Questions and Answers Add: Wiring Device Specification section and Subcontractor Reporting Form FOOTBALL STADIUM PRESS BOXES / ADDITION OF EAST & WEST SUITES, FM 090407 1. Question In Your FIU FM 090407 Specifications requirements is missing 16140 Wiring Devices. Would you please send it to us by email. Answer Specification Section 16140 Wiring Devices is included in Addendum #2 2. Question What is the engineers cost estimate for the project? Answer In order to assure the most competitive bid proposals are submitted, Florida International University will not release the construction cost estimate for the project. 3. Question What are the MBE goals set for the project, if any other than encouragement to bid? Answer The project does not have any set MBE goals. However, the successful bidder will be required to report MBE information for project and University tracking purposes. Sample Report Form is included in Addendum #2. 4. Question Will there be a construction manager (i.e. owners representative) contract associated with this project? Answer Roles of the University Construction Project Manager and Project Architect/Engineer are described in the Bid Documents. No other entities will be involved in the management of the project. 5. Question Will there be any bonding requirements for the project? Answer Bid Bond and Payment & Performance Bond requirements are included in the Bid Documents. 6. Question Will this be an OCIP project? Answer This project will not be an Owner Controlled Insurance Program project. Requirements for insurance to be provided by the successful bidder are included in the Bid Documents. 7. Question We are interested in bidding the Football Stadium Press Boxes/Addition of East & West Suite, Bid date: 4.1.10. Can you tell me what the budget is on this project? Answer In order to assure the most competitive bid proposals are submitted, Florida International University will not release the construction cost estimate for the project. 8. Question Can you please let us know the budget for this project? Answer In order to assure the most competitive bid proposals are submitted, Florida International University will not release the construction cost estimate for the project. 9. Question Is this a Design-Build or are the plans already done? Answer This is not a Design-Build project. It is a conventional Design-Bid-Build project. Construction Documents are included in the posted Bid Documents. 10. Question Do we need to be prequalified? Answer There is no prequalification process for this project. Potential Bidders must meet qualification requirements included in the Bid Documents. 11. Question Do we need to be vendor with FIU? If yes, what is the process? Answer Potential Bidders need not be registered as a vendor with FIU in order to submit their bid. Potential Bidders can register as a vendor with FIU at any time. Upon posting of Intent to Award, the successful bidder will be required to initiate vendor registration with the University. Registration information can be found at http://finance.fiu.edu/purchasing/2vendor_forms.html. 12. Question Do we need to be Bonded? Answer Bid Bond and Payment & Performance Bond requirements are included in the Bid Documents. 13. Question We would like know if this project will be site built or pre-fabricated. Answer Design for this project is based on site-built structure and finishes. 14. Question Please can you let me know the Amount Value or Budget for the project mentioned above. The surety Bonding company request before they can processing the documents. Answer In order to assure the most competitive bid proposals are submitted, Florida International University will not release the construction cost estimate for the project. 15. Question Estimated Value (budget) of the project. Request by Bond Company. Answer In order to assure the most competitive bid proposals are submitted, Florida International University will not release the construction cost estimate for the project. 16. Question Under General Conditions Item 2.4 – “Vendors Conference & Site Visited” it is schedule for April 1st, 2010; the same day of the BID DUE DATE? Answer Mandatory Pre-Bid Meeting was held on Monday, March 15, 2010 and a walk through of the site was conducted afterwards. Another walk through of the site will be conducted on Monday, March 22, 2010 and is non-mandatory. 17. Question Can you advise whom to send any pre qualification or substation information to, in regards to the press box on this bid? Answer There is no prequalification process for this project. Potential Bidders must meet qualification requirements included in the Bid Documents. 18. Question Confirm in writing that the following will not be required, as was discussed in the mandatory prebid meeting: a. Prior prequalification with FIU b. MWBE\DBE Participation c. Permit Fees d. Prevailing wages. Answer a. There is no prequalification process for this project. Potential Bidders must meet qualification requirements included in the Bid Documents. b. The project does not have any set MBE goals. However, the successful bidder will be required to report MBE information for project and University tracking purposes. Sample Report Form is included in Addendum #2. c. Florida International University implements and administers its own Building Code Permit and Inspection Program. This program does not charge any fees for construction permits issued including subcontractors. d. This project is not federally funded and prevailing wage requirement or enforcement is not applicable. 19. Question What floor is existing panels "SLA & SL" located (not shown)? Answer Panels “SLA & SL” are in the serving pantry located at the center of the suite level corridor. 20. Question Need a fire alarm drawing showing tying to existing system (not shown). Answer Additional Fire Alarm devices are shown on electrical sheets. Devices shall be added to existing notification device loop. 21. Question Show existing on drawings (not shown). Answer Verify existing Fire Alarm devices on site and tie new into existing system. 22. Question After walk-through we notice existing wall pack's.. What happens with these? Answer Existing wall pack luminaires shall be carefully salvaged and returned to owner. 23. Question Is the half-shaded troffers shown require a Battery back-up Ballast? Answer Emergency lighting fixtures do not require a battery back-up ballast as they will be connected to emergency power panels. 24. Question Please provide specifications on the PVI Multifold Portable Aluminum Ramp. Answer PVI Multifold Portable Aluminum Ramp is a readily available product and was included as a standard. Approved equivalents will be accepted. 25. Question In reviewing the documents for the Construction Bid titled Football Stadium Press Boxes/Addition of Ease and West Suites FL 090407 on page 10 it did not list a bid guaranty as being required. However when I review the Project Manuel for Football Stadium Press Boxes Addition of East and West Suites Rev. 10-16-89 page 11 of 106 B-13 states a Bid Bond of 5% is required. Can you please clarify in a Bid Bond is required and if required is there a certain form FIU requires for the Bid Bond? Answer Bid Guarantee shall be in any form meeting the requirements set forth in section B-13 of the Project Manual. 26. Question What is the project budget? Answer In order to assure the most competitive bid proposals are submitted, Florida International University will not release the construction cost estimate for the project. 27. Question Will space within the stadium be made available to the successful bidder for use as an office for the duration of the project? Answer An existing ticket booth (approx 5’x8’) can be used by the successful bidder for use as an office for the duration of the project. Any costs for connection of phone/fax through University Technology Services department will be the responsibility of the successful bidder. 28. Question Will restroom facilities within the stadium be made available for the successful bidder’s use for the duration of the project? Answer Stadium restroom facilities will not be available for the successful bidder’s use. Successful bidder must make appropriate arrangements for restroom facilities for contractor use. 29. Question In addition to cost, what is the criteria for selection? Answer Lowest bid determined to be fully responsive to criteria in bid documents shall be the basis of award. SECTION 16140 - WIRING DEVICES PART 1 - GENERAL 1.1 A. SUMMARY This Section includes the following: 1. 2. 3. 1.2 Receptacles, and associated device plates. Snap switches and wall-box dimmers. Communications outlets. ACTION SUBMITTALS A. Product Data: For each type of product indicated. B. Shop Drawings: List of legends and description of materials and process used for premarking wall plates. C. Samples: One for each type of device and wall plate specified, in each color specified. 1.3 A. 1.4 CLOSEOUT SUBMITTALS Operation and Maintenance Data: For wiring devices to include in all manufacturers' packing label warnings and instruction manuals that include labeling conditions. QUALITY ASSURANCE A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use. B. Comply with NFPA 70. PART 2 - PRODUCTS 2.1 A. MANUFACTURERS Manufacturers' Names: Shortened versions (shown in parentheses) of the following manufacturers' names are used in other Part 2 articles: 1. 2. 3. Cooper Wiring Devices; a division of Cooper Industries, Inc. (Cooper). Hubbell Incorporated; Wiring Device-Kellems (Hubbell). Leviton Mfg. Company Inc. (Leviton). FM 090407 FIU FOOTBALL STADIUM PRESS BOXES Addition of East & West Suites 16140 - 1 4. 2.2 A. Pass & Seymour/Legrand; Wiring Devices & Accessories (Pass & Seymour). STRAIGHT BLADE RECEPTACLES Convenience Receptacles, 125 V, 20 A: configuration 5-20R, and UL 498. 1. 2. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the following: Products: Subject to compliance with requirements, provide one of the following: a. b. c. d. 2.3 Comply with NEMA WD 1, NEMA WD 6 Cooper; 5351 (single), 5352 (duplex). Hubbell; HBL5351 (single), CR5352 (duplex). Leviton; 5891 (single), 5352 (duplex). Pass & Seymour; 5381 (single), 5352 (duplex). GFCI RECEPTACLES A. General Description: Straight blade, feed -through type. Comply with NEMA WD 1, NEMA WD 6, UL 498, and UL 943, Class A, and include indicator light that is lighted when device is tripped. B. Duplex GFCI Convenience Receptacles, 125 V, 20 A: 1. 2. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the following: Products: Subject to compliance with requirements, provide one of the following: a. b. 2.4 Cooper; GF20. Pass & Seymour; 2084. SNAP SWITCHES A. Comply with NEMA WD 1 and UL 20. B. Switches, 120/277 V, 20 A: 1. 2. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the following: Products: Subject to compliance with requirements, provide one of the following: a. b. c. d. Cooper; 2221 (single pole), 2222 (two pole), 2223 (three way), 2224 (four way). Hubbell; CS1221 (single pole), CS1222 (two pole), CS1223 (three way), CS1224 (four way). Leviton; 1221-2 (single pole), 1222-2 (two pole), 1223-2 (three way), 12242 (four way). Pass & Seymour; 20AC1 (single pole), 20AC2 (two pole), 20AC3 (three way), 20AC4 (four way). FM 090407 FIU FOOTBALL STADIUM PRESS BOXES Addition of East & West Suites 16140 - 2 2.5 A. COMMUNICATIONS OUTLETS Telephone Outlet: 1. 2. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the following: Products: Subject to compliance with requirements, provide one of the following: a. b. 3. B. Description: Single RJ-45 jack for terminating 100-ohm, balanced, four-pair UTP; TIA/EIA-568-B.1 complying with Category 5e. Comply with UL 1863. Combination TV and Telephone Outlet: 1. 2. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the following: Products: Subject to compliance with requirements, provide one of the following: a. b. 3. 2.6 A. 2.7 A. Cooper; 3562. Leviton; 40595. Description: Single RJ-45 jack for 100-ohm, balanced, four-pair UTP; TIA/EIA568-B.1; complying with Category 5e; and one Type F coaxial cable connector. WALL PLATES Single and combination types to match corresponding wiring devices. 1. 2. 3. 4. B. Cooper; 3560-6. Leviton; 40649. Plate-Securing Screws: Metal with head color to match plate finish. Material for Finished Spaces: Per Building Standard. Material for Unfinished Spaces: Galvanized steel. Material for Damp Locations: Cast aluminum with spring-loaded lift cover, and listed and labeled for use in "wet locations." Wet-Location, Weatherproof Cover Plates: NEMA 250, complying with type 3R weather-resistant, die-cast aluminum with lockable cover. FINISHES Color: Wiring device catalog numbers in Section Text do not designate device color. 1. 2. 3. Wiring Devices Connected to Normal Power System: Per Building Standard Wiring Devices Connected to Emergency Power System: Red. TVSS Devices: Blue. FM 090407 FIU FOOTBALL STADIUM PRESS BOXES Addition of East & West Suites 16140 - 3 PART 3 - EXECUTION 3.1 INSTALLATION A. Comply with NECA 1, including the mounting heights listed in that standard, unless otherwise noted. B. Coordination with Other Trades: 1. 2. 3. 4. C. Take steps to insure that devices and their boxes are protected. Do not place wall finish materials over device boxes and do not cut holes for boxes with routers that are guided by riding against outside of the boxes. Keep outlet boxes free of plaster, drywall joint compound, mortar, cement, concrete, dust, paint, and other material that may contaminate the raceway system, conductors, and cables. Install device boxes in brick or block walls so that the cover plate does not cross a joint unless the joint is troweled flush with the face of the wall. Install wiring devices after all wall preparation, including painting, is complete. Conductors: 1. 2. 3. 4. Do not strip insulation from conductors until just before they are spliced or terminated on devices. Strip insulation evenly around the conductor using tools designed for the purpose. Avoid scoring or nicking of solid wire or cutting strands from stranded wire. The length of free conductors at outlets for devices shall meet provisions of NFPA 70, Article 300, without pigtails. Existing Conductors: a. b. c. D. Cut back and pigtail, or replace all damaged conductors. Straighten conductors that remain and remove corrosion and foreign matter. Pigtailing existing conductors is permitted provided the outlet box is large enough. Device Installation: 1. 2. 3. 4. 5. Replace all devices that have been in temporary use during construction or that show signs that they were installed before building finishing operations were complete. Keep each wiring device in its package or otherwise protected until it is time to connect conductors. Do not remove surface protection, such as plastic film and smudge covers, until the last possible moment. Connect devices to branch circuits using pigtails that are not less than 6 inches (152 mm) in length. When there is a choice, use side wiring with binding-head screw terminals. Wrap solid conductor tightly clockwise, 2/3 to 3/4 of the way around terminal screw. FM 090407 FIU FOOTBALL STADIUM PRESS BOXES Addition of East & West Suites 16140 - 4 6. 7. 8. 9. E. Use a torque screwdriver when a torque is recommended or required by the manufacturer. When conductors larger than No. 12 AWG are installed on 15- or 20-A circuits, splice No. 12 AWG pigtails for device connections. Tighten unused terminal screws on the device. When mounting into metal boxes, remove the fiber or plastic washers used to hold device mounting screws in yokes, allowing metal-to-metal contact. Receptacle Orientation: 1. Install ground pin of vertically mounted receptacles down, and on horizontally mounted receptacles to the right. F. Device Plates: Do not use oversized or extra-deep plates. Repair wall finishes and remount outlet boxes when standard device plates do not fit flush or do not cover rough wall opening. G. Dimmers: 1. 2. 3. H. 3.2 A. Arrangement of Devices: Unless otherwise indicated, mount flush, with long dimension vertical and with grounding terminal of receptacles on top. Group adjacent switches under single, multigang wall plates. IDENTIFICATION Comply with Division 16 Section "Electrical Identification." 1. 3.3 A. Receptacles: Identify panelboard and circuit number from which served. Use hot, stamped or engraved machine printing with black -filled lettering on face of plate, and durable wire markers or tags inside outlet boxes. FIELD QUALITY CONTROL Perform tests and inspections and prepare test reports. 1. 2. B. Install dimmers within terms of their listing. Verify that dimmers used for fan speed control are listed for that application. Install unshared neutral conductors on line and load side of dimmers according to manufacturers' device listing conditions in the written instructions. Test Instruments: Use instruments that comply with UL 1436. Test Instrument for Convenience Receptacles: Digital wiring analyzer with digital readout or illuminated LED indicators of measurement. Tests for Convenience Receptacles: 1. 2. 3. Line Voltage: Acceptable range is 105 to 132 V. Percent Voltage Drop under 15-A Load: A value of 6 percent or higher is not acceptable. Ground Impedance: Values of up to 2 ohms are acceptable. FM 090407 FIU FOOTBALL STADIUM PRESS BOXES Addition of East & West Suites 16140 - 5 4. 5. 6. GFCI Trip: Test for tripping values specified in UL 1436 and UL 943. Using the test plug, verify that the device and its outlet box are securely mounted. The tests shall be diagnostic, indicating damaged conductors, high resistance at the circuit breaker, poor connections, inadequate fault current path, defective devices, or similar problems. Correct circuit conditions, remove malfunctioning units and replace with new, and retest as specified above. END OF SECTION 16140 FM 090407 FIU FOOTBALL STADIUM PRESS BOXES Addition of East & West Suites 16140 - 6 PAY REQUEST AMOUNT: CONTRACT AMOUNT: CONTRACT #: PROJECT NAME: A/E; CM; GC NAME ADDRESS: MBE VENDOR# MBE ID CONTRACT VALUE AMOUNT REQUESTED THIS PAY TOTAL COMPLETED TO DATE NAME: DATE: full accordance with the terms of this Contract, and the above values are represented in the Certificate of Payment. believe, the Above is a true statement of the value of the work performed by this MBE; that all work has been performed and material supplied in BALANCE REMAINING W=WOMAN Y=SERVICE-DISABLED VETERAN CERTIFICATION BY THE CONSTRUCTION MANAGER: I certify that I have checked and verified this MBE: that to the best of my knowledge and MINORITY BUSINESS ENTERPRISE MBE ID'S: H=AFRICAN AMERICAN I=HISPANIC J=ASIAN AMERICAN K=NATIVE AMERICAN PAY REQUEST# PROJECT# PROJECT#: FLORIDA INTERNATIONAL UNIVERSITY - FACILITIES PLANNING DEPARTMENT MINORITY BUSINESS DATA FORM VII. Facilities SMBE Subcontractor Reporting