Scottish Hydro Electric Transmission Scottish Hydro Electric Transmission (SHE Transmission) owns and maintains the high voltage electricity network that serves the north of Scotland. Overview of Transmission projects The landscape and environment that contribute to the challenges we face also give the area a rich resource for renewable energy generation. There is a high demand to connect from new wind, hydro and marine generators which rely on SHE Transmission to provide a physical link between the new sources of power and electricity users. Orkney Existing infrasturcture Recently completed Under construction Potential Development In total, we maintain about 5,000km of overhead lines and underground cables – easily enough to stretch across the Atlantic from John O’Groats all the way to Boston in the USA. Our network crosses some of the UK’s most challenging terrain – including some circuits which are over 750 metres above sea level and up to 250km long. Shetland Dounreay Spittal Western Isles Moray Firth Mossford Beauly Skye Peterhead Blackhillock Kintore Aberdeen Perth SHE Transmission is delivering a major programme of investment to ensure that the network is ready to meet the needs of our customers in the future. Denny Kincardine Hunterston Kintyre Arran East Coast Subsea Link SHE Transmission’s recently completed Corriemoillie substation, near Garve, with Lochluichart wind farm shown in the distance. Caithness to Moray Transmission Reinforcement Renewable generation in the northernmost part of Scotland, Orkney and Shetland is forecast to grow in the years ahead to around 3 Gigawatts (3000MW). Work was completed in early 2013 to add extra capacity to the existing 275 kilovolt (kV) overhead line which runs between Dounreay and Beauly, but significant further investment is now required to accommodate additional power generated from the wind, waves and tides. SHE Transmission is proposing to invest around £1.3 billion in a project centred on an underground and subsea cable between Spittal in central Caithness and Blackhillock, near Keith, in Moray. The existing onshore network would also be further reinforced between Dounreay and Mybster in Caithness and – further south – between Loch Buidhe, near Bonar Bridge, and Beauly. Work would take place at 8 substation sites and would include the construction of 2 converter stations at either end of the proposed cable. The cable itself would run for over 160 kilometres (100 miles) and be capable of transporting up to 1200MW of electricity beneath the Moray Firth. Caithness-Moray project website www.ssepd.co.uk/CaithnessMoray Subject to approval by the energy regulator, Ofgem, the whole project could be completed as early as 2018. The Oyster wave energy device in use off Orkney. Photo: Aquamarine Power OpenHydro’s tidal machine on the dockside, ready for testing. Photo: OpenHydro Planned onshore and offshore wind generation is forecast to grow. High Voltage Direct Current The underground and subsea cable at the heart of SHE Transmission’s proposals would use a technology called High Voltage Direct Current (HVDC). This is different to the existing onshore network, which carries high voltage electricity as Alternating Current (AC). HVDC is a well established technology which is in growing use all over the world – including at a number of locations around the UK. It allows the efficient transmission of large quantities of electricity across long distances – with much reduced electrical losses compared with AC. It also introduces greater flexibility and resilience in the operation of the network and the management of variable output from renewable generation. The Caithness to Moray project as a whole would keep the amount of new onshore transmission infrastructure to a minimum. Individual sites have been carefully selected and designed to keep their impact on the landscape and the wider environment to a minimum. Careful site selection, planting and landscaping will help key sites like Spittal to blend into their surroundings over time. Modern Gas Insulated substation equipment within the newly built Dounreay substation. Similar technology will be used in the construction of the AC substation at Spittal, from which electricity will be transferred into the HVDC converter station for onward transmission. Onshore HVDC Construction The HVDC cable will run between two converter stations at Spittal in Caithness and Blackhillock in Moray. Onshore cable burial: The project involves 48km of onshore underground cable, from Spittal to Noss Head in Caithness; and from Portgordon to Blackhillock in Moray. Along this section: The proposed layout of the Spittal site, with the HVDC converter station shown at the top right. • A working corridor up to 20 metres wide will be established. • A temporary access track will be built. • A trench will be excavated to allow installation of the cable circuit. • The cables will be laid in sections and ‘jointed’ in temporary covered bays along the route. • Once installation is complete, the soil and topsoil will be carefully reinstated and the access tracks removed. Directional drilling: At the cable landfalls, it is proposed to use ‘horizontal directional drilling’ to enable the cable to be installed with minimal disturbance to the coastline. At the locations: The proposed layout of the Blackhillock site, with the HVDC converter station at the bottom left. A 20 metre working corridor will be created to allow the installation of the cable underground between Spittal and Noss Head in Caithness; and between Portgordon and Blackhillock in Moray. • A specialist drilling rig will bore a hole through which the cable can be fed without disturbing the surface of the ground. • This method on a smaller scale can also be used at major road and river crossings. Offshore HVDC Construction Some of the most challenging construction work work takes place on the subsea section of the route. Extensive surveys of the seabed have already been completed to find the best route – and every stage of the installation process will be closely monitored to ensure the cable is buried or protected safely. Offshore: The subsea part of the cable runs from Noss Head, north of Wick, to a landfall near Portgordon in Moray. • Detailed surveys of the seabed are completed to identify the most suitable route and to minimise impact on sensitive marine habitats. • A specialist submarine plough is used to clear any boulders from the seabed and then to create a trench around 1 metre deep into which the cable can be laid. • The cable is laid from a large specialist cable-laying vessel and guided into the trench. • Remotely operated vehicles are used to allow engineers and environmental experts on board the vessel to monitor each stage of the process. • The submarine plough is then used to backfill the trench, burying the cable. • On sections where seabed conditions mean that cable burial is not possible, a protective layer of rock will be laid over the cable, creating an artificial reef. Onshore network reinforcements As well as the major sites at Spittal and Blackhillock – and the work which will take place along the cable route itself – further reinforcements will be completed on two sections of the existing onshore transmission network that serves the north of Scotland. Dounreay to Mybster: Between Dounreay and Spittal, the existing 132kV overhead line will be replaced by an upgraded 275kV overhead line. As part of this project a new transmission substation will be built south of Thurso on the west side of the A9 and the existing substation on the east side of the road will be dismantled. The existing substation at Mybster will be extended and an additional 132kV overhead line will be built between Spittal and Mybster. Helicopters are used in the ‘stringing’ of the conductors (wires) on to the steel towers that support most overhead transmission lines. Loch Buidhe to Beauly: Further south on the existing network, two new transmission substations will be built at Loch Buidhe, north of Bonar Bridge, and at Fyrish, near Alness. The wires on the west side of the existing 275kV overhead line will be replaced between Loch Buidhe and Beauly. The combined effect of these projects is to strengthen the network for transporting electricity from generation sites to where it is needed – either via Spittal and the new HVDC system; or via Beauly and the existing onshore network. Benefits of the project The Caithness to Moray project has the potential to generate significant benefits to the local, regional and national economy during construction and operation. It would deliver an important step towards a modern electricity network that is ready for the future. •D uring the construction phase, the project would generate hundreds of direct jobs and training opportunities at sites in Caithness, Sutherland, Ross-shire and Moray. •A wide range of businesses would benefit, both directly through opportunities to provide services and indirectly through the value added to the local and regional economy. CASE STUDY: In the first two years alone of constructing the Beauly to Denny transmission project, a study has estimated that the work generated approximately £86 million in Gross Value Added (GVA) to the Scottish economy and created around 1,500 jobs in total. SHE Transmission has set up an award-winning transmission trainee programme in partnership with Inverness College UHI and Balfour Beatty to deliver the skilled workforce of the future. The class of 2013/14 successfully completed the college-based part of the course in December 2013. • The Caithness to Moray proposals can be delivered by 2018, providing the capacity needed by the north’s growing renewable energy industry when it is needed. • The innovative design of the project allows for additional HVDC connections in future, potentially including links for Orkney and Shetland. With the first stage in place, future works could be delivered faster and at reduced cost. • HVDC enables significantly more efficient transmission of power across long distances – greatly reducing electrical losses when compared with a conventional AC alternative. • The HVDC system provides greater flexibility in the operation of the network. It allows more efficient management of the output from renewable generation and can also contribute to a more resilient network for all our customers. • The project as a whole has been carefully planned to deliver an efficient solution which minimises impacts on people and the environment. Its construction would reduce the requirement for major new onshore transmission infrastructure in the north. Keeping the light on and supporting growth SHE Transmission is committed to working closely with local communities to deliver a modern electricity network that is ready to meet the challenges ahead. Britain’s safest power company Safety is our first priority in everything we do. We aim to be among the safest companies in the world and will keep looking for new ways to keep our staff, contractors and the public safe. Last year our staff made 96 visits to schools in their own communities to teach children how to be safe around electricity. When it comes to safety, we think you can’t start early enough. Investing in skills for the future We are committed to investing in the long term future of our business and of the communities where we work. That’s why we offer a range of industry-leading training and apprenticeship programmes, with opportunities for everyone from school-leavers to graduate engineers. In recent years, we have also delivered an award-winning transmission trainee programme in partnership with Inverness College UHI and Balfour Beatty. To find out more about our training and career opportunities, check regularly at www.sse.com/careers. Proud to be an active part of the communities we serve Our Community at Heart scheme means every member of our staff can take a day of their time each year to work on a community project of their choice. Last year, around 1500 days of volunteering took place through the scheme. If there is a community or charity project that you think our staff might be able to help with, just ask our team for a form and let us have the details. If you have a question or concern about our work, please get in touch and we will do our best to help: Caithness: Gavin Steel SSE, 10 Henderson Road, Inverness, IV1 1SN E:gavin.steel@sse.com T: 01463 728109 M:07584 313481 Moray: Sam O’Connor SSE, Inveralmond House, 200 Dunkeld Road, Perth, PH1 3AQ E:sam.oconnor@sse.com T: 01738 453224 M:07584 313059