Part B Electrical Works Section I General Instructions Section II Specification and List of Make Section III Item Specification Section II Specifications and List of Make Electrical Works – Specifications and List of Make E- 2 Section II: Electrical Works - Specifications, Testing and Make of Material Contents Part A – Electrical Specification .................................................................................................................... 3 E1. Internal Wiring ............................................................................................................................... 3 E2. Distribution Boards...................................................................................................................... 11 E3. Cable Trench............................................................................................................................... 13 E4. Cable Trays ................................................................................................................................. 13 E5. Medium Voltage Cables .............................................................................................................. 24 E6. Cable Termination....................................................................................................................... 28 E7. Medium Voltage Panel Board / Mv Switch Gear ......................................................................... 28 E8. Lighting Fixtures & Accessories .................................................................................................. 54 E9. Earthing ....................................................................................................................................... 60 E10. Street Lighting Poles: .................................................................................................................. 67 E11. Telephone & Data Distribution .................................................................................................... 72 E12. HT GOD& HT Work .................................................................................................................... 77 E13. Diesel Generator Set................................................................................................................. 106 Part B: Testing .......................................................................................................................................... 123 Part C: Erection, Testing & Commissioning Of Electrical Installations ..................................................... 125 Part - D: List Of Approved Make For Electrical Materials ......................................................................... 129 Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 3 Part A – Electrical Specification E1. Internal Wiring This section covers, definition of point wiring, system of wiring and supply, installation, connection, testing and commissioning of point wiring for light points, ceiling fan points, exhaust fan points, convenience socket outlet points, power socket outlet points etc. including fixing of light fixtures, ceiling fan, exhaust fan, wall fan etc. 1.1 Standards The following standards and rules shall be applicable: Standard no. Particular IS : 732 Code of practice for electrical wiring installation (System voltage not exceeding 650 V) IS : 1646 Code of practice for fire safety of buildings (General) Electrical installation. IS : 2509 Rigid non-metallic conduits for electrical wiring. IS : 6946 Flexible (Pliable) non-metallic conduits for electrical installation. IS : 1293 3 pin plugs and sockets. IS : 8130 Specifications of conduits for electrical installation. IS : 3854 Switches for domestic purpose. IS : 3415 Fittings for rigid non-metallic conduits. IS : 4648 Guide for electrical layout in residential building Indian electricity act and rules. Regulations for the electrical equipment in buildings issued by the Bombay Regional Council of Insurance Association of India. All standards and codes mean the latest. 1.2 Point Wiring A point shall consist of the a switch as required, including the ceiling rose or pendant holder or swan holder, or ceiling fan box or socket or suitable termination. A point shall include, in addition, the earth continuity conductor / wire from the Switch Board to the earth pin / stud of the outlet / switch box and to the outlet points. The point wiring shall be carried out in the under mentioned manner 1.2.1. Supply, installation, fixing of conduits with necessary accessories, junction / pull / inspection / switch boxes and outlet boxes. ( Refer BOQ Item for Pipe Supply ) 1.2.2. Supplying and drawing of wires of required size including earth continuity wire. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 1.3 E- 4 1.2.3. Supply, installation and connection of flush type switches, sockets, cover plates, switch plates, etc. 1.2.4. The point shall be complete with the branch wiring from the Switch board to the outlet point, Pre laid conduit with accessories, junction, pull, inspection boxes, control switch, socket, outlet boxes, ceiling roses, button / swan holder, connector etc. Point Rate The rate per point shall include supply, installation, connection, testing and commissioning of point as described under “point wiring”. The measurements of the points will be enumerated. Rate for the point shall consist of wiring from the out let point to the switch board as required with a connector/ plate/ ceiling rose fan box with hook socket with switch. The point rate shall include phase and neutral wire a PVC insulated earth continuity wire from switch to outlet. The unit rate for the point shall consist of wiring from switchboard to outlet point through switch and/or socket, switch board as required and including the outlet points with connector, fan hook box or sockets etc… 1.4 System of Wiring Unless otherwise mentioned on the drawings, the system of point wiring shall be as follows: The system of wiring shall consist of single core, PVC insulated, 650/1100 volt grade, copper conductor FRLS wires laid through exposed (surface mounted) PVC conduits as directed. 1.5 General The contractor shall submit for approval, the shop drawing of conduit layout indicating the route of the conduits, number and size of the conduits, location of junction / inspection / pull / outlet boxes, size and location of switch boxes, number and size of wires pulled through each conduit and all other necessary relevant details prior to laying of conduits. Only after the drawings are approved, the contractor shall proceed with the work of conduit laying. Prior to laying and fixing of conduits, the contractor shall carefully examine the working drawings prepared by him and approved by the Consultant indicating the layout, satisfy himself about the sufficiency of number and sizes of conduits, location of junction boxes, sizes and location of switch boxes and other relevant details. Any discrepancy found in the drawings shall be brought to the notice of the Owner’s site representative. Any modifications suggested by the contractor shall be gotten approved before the actual laying of conduits is commenced. In laying of conduits it is important that not more than two right angle bends are provided for each circuit and as far as possible. No junction box shall be provided in the entire length of conduit run for drawing of wires. Only switch outlets, lighting fixture outlets, equipment power outlets and socket outlets shall be considered for drawing of wires. 1.6 Material 1.6.1 PVC Conduits All non-metallic PVC conduits shall conform to IS: 9537. The conduit shall be plan and type as specified in IS: 9537 and shall be used with the corresponding accessories (Refer IS: 3419 specification for fittings for rigid non PVC metallic conduits). PVC conduits shall be rigid unplasticized, medium gauge having 1.6 – 1.8 mm. wall thickness up to 20 mm. diameter conduit and 1.8 - 2 mm. wall thickness for all sizes above 20 mm. diameter. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 5 1.6.2 Boxes All the boxes for switches, sockets and other receptacles, junction boxes, pull boxes and outlet boxes shall be fabricated from 2.0 mm. thick mild sheets painted with two coats of red-oxide and then two coats of enamel paints as called for. Colour of the paints shall be as approved by the client. The boxes shall have smooth external and internal finished surface. Boxes in contact with earth or exposed to the weather shall be of 2 mm. mild steel and hot dip galvanized after fabrication. Separate screwed earth terminal shall be provided in the box for earthing purpose. All boxes shall have adequate no. of knock out holes of required diameter for conduit entry. Switch boxes to receive switches, socket outlets, power outlets, telephone outlets, fan regulators, etc. shall be fabricated to the approved shape and size to accommodate all the devices without overcrowding. Outlet boxes to receive ceiling fan shall be fitted with adequately sized rod / hook to fix ceiling fan. The boxes shall be of minimum depth of 65 mm. 1.6.3 Cover Plate The cover of the boxes to receive outlet points shall be of best anodized sheet cut to shape and size or plate of approved manufacturers of switches. 1.6.4 Cables The cables shall conform to IS: 694. For all internal wiring FRLS wires of 650 / 1100 volts grade, single core shall be used. The conductors shall be plain annealed copper conductors complying with IS: 1554. The conductors shall be circular copper conductor. The insulation shall be XLPE compound complying with the requirements of IS: 694. It shall be applied by an extrusion process and shall form a compact homogenous body. The thickness of XLPE insulation shall be as set out in the relevant standards The cores of all cables shall be identified by colours in accordance with the following sequence. Single phase - Red Three phase - Red, Yellow, Blue Neutral - Black Earth - Green or Green/Yellow Means of identifying the manufacturer shall be provided throughout the length of cable. Unless otherwise specified in the drawings the size of the cables used for internal wiring shall be as follows: In case of circuit wiring for lights, exhaust fans, convenience socket outlet points (P+N+E): 2 nos. of 2.5 mm² + 1 no. of 1.5 mm.² -From MCB at Panel/DB to switch boards. 3 nos. of 1.5 mm.² -From switch boards to outlet points 2 nos. of 4.0 mm.² + 1 no. of 2.5 mm.² -From MCB at Panel/DB to 16/20 Amp socket. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 6 1.6.5 Switches Switches shall conform to IS: 3854, IS: 1293 and IS: 4615. The switches shall be single pole, single or two way and shown on the drawings or as specified. They shall be of moulded type rated for 250 volt, and of full 5 / 15 A capacity. They shall be provided with insulated dollies and covers. The switches shall be rocker operated with a quite operating mechanism with bounce free snap action mechanism enclosed in an arc resistant chamber. The switches shall have pure silver and silver cadmium contacts. The switches shall be flush modular type the make of the switches shall be as indicated in the drawings or BOQ or make of material or as suggested and approved by the client. The switches installed in outdoor area shall be industrial, metal clad type, and shall be provided in weather proof enclosures, complete with weather proof gasketed covers. 1.6.6 Sockets The sockets shall conform to IS: 1293. Each socket shall be provided with control switch of appropriate rating. The sockets shall be moulded type, rated for 250 volts, and either of full 5 A or 15 A capacity, as mentioned on the drawings. Sockets shall be of three pin type, the third in being connected to earth continuity conductor. The socket shall be flush modular type. The sockets installed in machine room, plant room or wet / damp area shall be metal clad weather proof type. The finishing and make of all the sockets shall be same as light switch. The socket shall have fully sprung contacts and solid brass shrouded terminals to ensure positive electrical connections. The sockets shall be provided with automatic shutters, which open only when earth pit of the plug inserts in the socket. The socket shall be provided with three pin plug top suitable to the socket and of the same make as socket. 1.6.7 Under Floor Raceways The under floor duct for “in screed” system shall be “galvanized sheet” steel of 1.6mm thick with top and bottom plates are double folded and spot welded together to give required rigidity and to prevent the seepage of concrete and screed water. The duct must have two or three compartments to accommodate cables of different voltage ratings ( Power , Data & Communication ). The standard length of the duct shall be of 2.5 mtrs with a width of 100 / 200 /250 (or) 300 mm and with a height of 28 / 38 (or) 48mm. Coupler have to be used to connect the standard sizes of the ducts in screed covered system. The end cap should lock in to the duct with out additional accessories to protect against dust or other foreign particles inside the duct. The riser bends should be easily mounted as well for quick entry of cables in the under floor system. Under floor Junction & Service Outlet Access Boxes The floor boxes must be of high quality material and should withstand heavy load and should have corrosion protection. The Underfloor Junction and Service Outlet Boxes shall be robust in its construction with a base plate and side walls manufactured from minimum 1mm thick galvanized steel and main leveling frames from diecast/extruded aluminium. Height of the Underfloor Service outlet and Junction Boxes shall be adjustable from 70 to 125mm inline with the height of the screed level for higher screed structures. The Junction and Service outlet boxes shall have suitable dimensions to eliminate congestion and to provide ample working space within the box. Junction Box shall be supplied with crossover bridges for segregation of power, voice and data cables. The sides of the Underfloor boxes shall be pre punched on all the sides for quick and easy installation of Underfloor Ducts at site. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 7 The Frame cassette for Stone finished application shall be manufactured from Stainless steel cassette with 10/15/20/25/30 & 40mm height options to support floor finishing stone of different heights. The cassettes shall also be fitted with a 4mm thick sheet steel plate for ensuring maximum rigidity and providing adequate load bearing capacity. The cassette shall be supported on the Underfloor boxes with the help of four part cassette frame screwed on the underfloor box firmly in place. The frame shall also house a square shaped gasket in single piece to prevent ingress of dirt and water through the gap between the cassette and frame. Installation: Underfloor trunking system shall be installed strictly as per manufacturer’s instructions and to a level of workmanship to ensure that all the underfloor boxes are consistently in level with the screed level and any part of the boxes is not detected below and or above the floor slab. Failure to comply in this respect, the affected boxes shall be re-installed by the contractor, as required by the engineer. Cross-over bridges shall be installed at the junctions as required, to ensure that adequate segregation of power, voice and data service cables is maintained. Service outlets shall be installed within floor boxes after installation is completed and wiring is carried out, on to cover plates which are provided with suitable blanks for installation of service outlets. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 8 1.6.8 Under Floor PVC Raceways 1.7 Drawing Of Conductors The drawing and joining of copper conductor or wires shall be executed with due regard to the following precautions, while drawing insulated wires into the conduits, care shall be taken to avoid scratches and kinks which may cause breakage of conductors. There shall be no sharp bends. Insulation shall be shaved off for a length of 15 mm at the end of wire like sharpening of a pencil and it shall not be removed by cutting it square or ringing. PVC insulated copper conductor wire ends before connection shall be properly soldered (at least 15 mm length) with soldering flux / copper solder, for copper conductor. Strands of wires shall not be cut for connecting to the terminals. The connecting brass-screws shall have flat ends. All looped joints shall be soldered and connected through terminals block / connectors. The pressure applied to tighten terminal screws shall be just adequate, neither too much nor too less. Conductors having nominal cross section are exceeding 4 sq. mm shall always be provided with crimping type cable sockets. At all bolted terminals, brass flat washer of large area and approved steel spring washers shall be used. Brass nuts and bolts shall be used for all connections. Only certified wire man and cable jointers shall be employed to do joining work. For all internal wiring PVC insulated wires of 650 / 1100 volts grade shall be used. The sub-circuit wiring for point shall be carried out in looping system and no joint shall be allowed in the length of the conductors. No wire shall be drawn in to any conduit, until all work of any nature that may cause injury to wire is completed. Care shall be taken in pulling the wires so that no damage occurs to the insulation of Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 9 the wire. Before the wires are drawn into the conduits the conduits shall be thoroughly cleaned of moisture, dust, and dirt or any other obstruction by forcing compressed air through the conduits. Maximum permissible number of 1100 volt grade PVC insulated wires that may be drawn into rigid non metallic or PVC Conduits are given below: 1.8 Size of wires Nominal Cross Maximum size(mm) number of wires within conduit Section Area (Sq. mm.) 20 25 32 40 50 1.5 5 10 14 -- -- 2.5 5 8 12 -- -- 4 3 7 10 -- -- 6 2 5 8 -- -- 10 -- 3 5 6 -- 16 -- 2 3 -- 6 25 -- -- 2 4 6 35 -- -- -- 3 5 Joints The wiring shall be by looping back system, and hence all joints shall be made at main switches, distribution boards, socket outlets, lighting outlets and switch boxes only. No joints shall be made inside conduits and junction boxes. Joints where unavoidable, due to any specified reasons, prior permission in writing shall be obtained from the client before making such connections. Joints by twisting conductors are prohibited. 1.9 Load Balancing Balancing of circuit in three phase installation shall be planned before the commencement of wiring and shall be strictly adhered to. 1.10 Earthing All earthing systems shall be in accordance with IS: 3043 - 1985 code of practice for earthing. 1.11 Testing Of Installation Before a completed installation is put into service, the following tests shall be complied with 1.11.1 Insulation Resistance The insulation resistance shall be measured by applying 500 volt megger with all fuses in places, circuit breaker and all switches closed. The insulation resistance in mega ohms of an installation, measured shall not be less than 50 mega ohms divided by the number of points on the circuit. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 10 The insulation resistance shall be measured between EARTH TO PHASE EARTH TO NEUTRAL PHASE TO NEURAL PHASE TO PHASE 1.11.2 Earth Continuity Path The earth continuity conductors shall be tested for electrical continuity and the electrical resistance of the same along with the earthing lead but excluding any added resistance or earth leakage circuit-breaker measured from the connection, with the earth electrode to any point in the earth continuity conductor in the completed installation and shall not exceed one ohm. 1.11.3 Polarity Of Single Pole Switches A test shall be made to verify that every no-linked, single pole switch is connected to one of the phase of the supply system. 1.11.4 Completion Certificates All the above tests shall be carried out in presence of client and the results shall be recorded in prescribed forms. Any default during the testing shall be immediately rectified and that section of the installation shall be re tested. The completed test result from shall be submitted to the client for approval. On completion of an electric installation a certificate shall be furnished by the contractor, countersigned by the certified supervisor under whose direct supervision the installation was carried out. This certificate shall be in a prescribed form as required by the local electric supply authority. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 11 E2. Distribution Boards Distribution Boards (DB’s) shall be suitable for operation on 3 Phase/single phase, 415/240 volts, 50 cycles, neutral grounded at transformer. The DB shall be minimum di-electric strength of 2.5 KV / Sec. All Distribution Boards shall manufactured by a manufacturer listed in Appendix-I. DB’s shall comply with the latest Relevant Indian Standards and Electricity Rules and Regulations and shall be as per IS-13947-1993. 1.1 Construction Features DB’s shall be IP 43 & made out of 1.6 mm thick high quality CRCA sheet steel and shall be pre-treated and powder coated sheet steel used in the construction of DB shall be folded and braced as necessary to provide a rigid support for all component. DB shall be suitable for indoor / outdoor installation, wall mounting free standing type, in double door construction. The Distribution Boards shall be totally enclosed, completely dust and vermin proof and shall be with hinged doors, Neoprene gasket, padlocking arrangement. All removable/ hinged doors and covers shall be grounded by 4.0 sq mm tinned stranded copper connectors. Distribution Boards shall be suitable for the climatic conditions. Joints of any kind in sheet metal shall be seam welded, all welding, slag shall be rounded off and welding pits wiped smooth with plumber metal. The general construction shall confirm to IS-8623-1977 (Part-1) for factory built assembled switchgear & control gear for voltage up to and including 1100 V AC. All panels and covers shall be properly fitted and square with the frame, and holes in the panel correctly positioned. Fixing screws shall enter into holes tapped into an adequate thickness of metal or provided with wing nuts. Self threading screws shall not be used in the construction of DBs. Three phase boards shall have phase barriers and a wire channel on three sides. Neutral bars shall be solid tinned copper insulated bars with tapped holes and chase headed screws. For 3 phase DB’s, 3. Independent neutral insulated bars shall be provided. All DB’s shall be internally pre-wired using copper insulated PVC wires brought to a terminal strip of appropriate rating for outgoing feeders. Knockout holes of appropriate size and number shall be provided in the DB’s in conformity with the location of cable/conduit connections. Detachable sheet steel gland plates shall be provided at the top / bottom to make holes for additional cable entry at site if required. Distribution Boards shall comprise of the following: 1.1.1. A panel for mounting where appropriate incoming supply circuit breaker & other auxiliaries for Control & distribution as required. 1.1.2. Installation accessories shall be part of the DB for fixing conductor and rails for mounting MCB’s and RCCB’s etc... Neutral bus bars & earthing bus bars required in the circuit. All bus bars in the FDB shall be insulated type. 1.1.3. Service cable /interconnection shall be part of the Distribution Boards. 1.1.4. The board shall be installed at a height such that the operating is within reach of the normal human height i.e. 1.2 to 1.8 meters from finish floor level. 1.1.5. Degree of protection shall be IP-52 for indoor application, IP-54 for kitchen & laundry and IP-55 for outdoor application. 1.1.6. All three phase distribution boards shall have 4 rows and single phase distribution boards shall have single rows for housing of MCB’s and RCCB’s unless noted otherwise. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 12 1.1.7. Phase segregation to be maintained in all three phase distribution boards. 1.1.8. Earthing shall be provided in each FDB’s. 1.2 Miniature Circuit Breaker (MCB) Miniature Circuit Breaker shall comply with IS-8828-1996/IEC898-1995. Miniature circuit breakers shall be quick make and break type for 240/415 VAC 50 Hz application with magnetic thermal release for over current and short circuit protection. The breaking capacity shall not be less than 10 KA at 415 VAC. MCB’s shall be DIN mounted. The MCB shall be Current Limiting type (Class-3). MCBs shall be classified (B, C, D ref IS standard) as per their Tripping Characteristic curves defined by the manufacturer. The MCB shall have the minimum power loss (Watts) per pole defined as per the IS/IEC and the manufacturer shall publish the values. MCB shall ensure complete electrical isolation & downstream circuit or equipment when the MCB is switched OFF. The housing shall be heat resistant and having high impact strength. The terminals shall be protected against finger contact to IP20 Degree of protection. All DP, TP, TPN and 4 Pole miniature circuit breakers shall have a common trip bar independent to the external operating handle. MCB should be having an integrated label holder with dual side din rail locking facility. Incoming & Outgoing should have facility for termination of Busbar & Cable separately. Cable termination facility should be up to 35 sq. mm. 1.3 Residual Current Circuit Breaker Current Operated Type ( RCCB) I. System Of Operation Residual Current Circuit Breaker shall confirm to IEC 61008.RCCB shall work on the principle of core balance transformer. The incoming shall pass through the torrodial core transformer. As long as the currents in the phase and neutral shall be the same, no electro motive force shall be generated in the secondary winding of the transformer. In the event of a leakage to earth, an unbalance shall be created which shall cause a current to be generated in the secondary winding, this current shall be fed to a highly sensitive miniature relay, which shall trip the circuit if the earth leakage current exceeds a predetermined critical value. RCCB shall be current operated independent of the line voltage; current sensitivity shall be of 30 / 100 mA at 240/415 volts AC and shall have a minimum of 20,000 electrical operations. It should provide full protection as envisaged by IE rules – 61-A, 71 – ee, 73 – ee, 1985 and also rule 50 of IE rule1956. Ii. Mechanical Operation The moving contacts of the phases shall be mounted on a common bridge, actuated by a rugged toggle mechanism. Hence, the closing /opening of all the three phases shall occur simultaneously. This also shall ensure simultaneous opening of all the contacts under tripping conditions. Iii. Neutral Advance Feature The neutral moving contact shall be so mounted on the common bridge that, at the time of closing, the neutral shall make contact first before the phases; and at the time of opening, the neutral shall breaks last after allowing the phases to open first. This is an important safety feature which is also required by regulations. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 13 MCB should be having an integrated label holder with dual side din rail locking facility. Incoming & Outgoing should have facility for termination of Busbar & Cable separately. Cable termination facility should be up to 35 sq. mm. Iv. Testing Provision A test device shall be incorporated to check the integrity of the earth leakage detection system and the tripping mechanism. When the unit is connected to service, pressing the test knob shall trip the ELCB / RCCB and the operating handle shall move to the "OFF" position. 1.4 Earthing Earthing shall be provided as per IS: 3043-1987. 1.5 Painting All sheet steel work shall undergo a process of degreasing, pickling in acid, cold rinsing, phosphating, passivaiting (seven tank processing) and then painted with electrostatic paint (Powder coating). The shade of colour of panel inside/outside shall be of Siemens gray paint shade no. RAL-7032 of IS Code No.5. 1.6 Labels Engraved PVC labels shall be provided on all incoming and outgoing feeder. Circuit diagram showing the arrangements of the circuit inside the distribution panels shall be pasted on inside of the panel door and covered with transparent plastic sheet. 1.7 Testing Testing of panels shall be as per following codes: IS: 8623 (Part -I) 1977 for factory built assemblies of switch gear for voltages up to and including 1000 VAC. IS: 13947: 1993 Degree of protection 1.8 Wiring In wiring a distribution panel it shall be insured that total load of various distribution panel and/or consuming devices is divided evenly between the phases and number of ways as per Consultants drawing. E 3 . C a b l e Tr e n c h Not Applicable E 4 . C a b l e Tr a y s General Requirement:- Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 14 Cable Tray and Cable Ladder systems are intended for the support and accommodation of cables and possibly other Electrical equipment in Electrical/Instrumentation/Communication systems. Design and Fabrication of Cable Trays / Ladders:The cable trays / ladders shall be fabricated according to the design specified by IEC 61537 and should be tested for Safe Working Load (SWL). The relevant details of SWL and the load chart with respect to SWL, supporting distance and the deflection should be according to the following chart. Safe Working Load (SWL) with a span length up to 3 meters Span length (in meters) Side Width Description Height 1.5m 2m 2.5m 3m (in mm) (in mm) Permitted Load (in kg/meter) 35 50 - 300 125 90 50 - 60 50 - 600 150 100 50 - 85 100 - 600 175 110 50 - 100 / 110 100 - 550 185 130 75 60 45 200 - 600 180 140 100 55 60 200 - 600 - 225 150 100 100 / 110 200 - 600 - 310 200 140 Perforated Cable Tray Cable Ladder Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 15 Safe Working Load (SWL) with a span length up to 10 meters Span length (in meters) Side Width Description Height 4m 5m 6m 7m 8m 9m 10m (in mm) (in mm) Permitted Load (in kg/meter) 200 - 300 160 110 75 - 20 - - 400 - 600 200 150 100 - 40 - - 200 - 300 230 180 140 100 70 - - 400 - 600 250 200 160 130 100 - - 200 - 300 160 110 80 40 - - - 400 - 600 210 150 100 70 - - - 200 - 300 230 180 140 100 70 - - 400 - 600 250 200 160 130 100 - - 200 - 600 - - 300 250 200 140 100 100 / 110 Perforated Cable Tray for long span distance 160 100 / 110 Cable Ladder for long span distance 160 200 Fabrication of Tray / Ladder and accessories at site and welding is not permitted. In unavoidable circumstances, If any cut or holes are made in the trays/Ladder/accessories, zinc spray need to be applied over the surface. The metal edge has to be protected by edge protection sleeves to avoid cable damage. Edge of the supports has to be protected with plastic END caps. Screwed connections and internal fixing Devices should not create any damage to the cable when correctly fixed. Sudden or jerky motions shall not be used to tighten reusable screw connections. Cables shall run in cable tray/ladder mounted horizontally or vertically on cable tray support system which in turn shall be supported from floor, ceiling, overhead structures, trestles, pipe racks, trenches or other building structures using mounting accessories Cable Tray:The cable tray and all accessories shall be fabricated from sheet steel and has to be hot dip galvanized against corrosion confirming to ISO 1461-1999 for installations in both indoor and outdoor applications & should have a Base Perforation Class B according to IEC 61537. The cable trays shall be supplied in standard lengths of 3000mm and the width of the tray shall be as follows. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 16 Width: 50, 100, 150, 200, 300, 400, 500, 600, 750 & 1000 mm. All the cable tray accessories like Bend’s, TEES’s, Cross over’s etc should be designed in accordance with IEC 61537 and shall be factory fabricated. The accessories shall be from the same material as of the tray and modular type, it should be connected with the trays by using fasteners. Typical details of trays, fittings and accessories.etc are shown in the enclosed drawings. For Cable trays designed, tested and confirming to IEC 61537, thickness of cable tray should be according to the manufacturers catalogue. For locally fabricated and non tested tray, thickness should be 2 mm up to span length of 1.5 meter, 2.5 mm for span length between 2 to 3 meter and 3 to 4 mm for span length between 4 and 10 meter Cable ladder:The cable Ladder and all accessories shall be fabricated from sheet steel and has to be hot dip galvanized against corrosion confirming to ISO 1461-1999 for installations in both indoor and outdoor applications & should have a Free Base Area classification Y according to IEC61537. The cable ladders shall be supplied in standard lengths of 3000/6000 mm and the width of the tray shall be as follows. Width: 200 to 1200 mm in multiples of 100 mm Maximum rung spacing in the ladder shall be 300mm. The rung’s should be made of C profiles suitable to fix cables by special metal clamps according to the drawing. The ladder shall be of riveted and foldable type for easy transportation and to avoid damage during transportation and storage. All the ladder accessories like Bend’s , TEES’s, Cross over’s etc should be designed in accordance with IEC 61537 and shall be factory fabricated . The accessories shall be made from the same material as of the ladder and modular type, it should be connected with the ladder by using fasteners. The details of ladders, fittings and accessories .etc are shown in the enclosed drawing. For Cable Ladders designed, tested and confirming to IEC 61537, thickness of cable Ladder should be according to the manufacturer’s catalogue. For locally fabricated and non tested Ladder, thickness should be 2.5 mm up to span length of 1.5 to 2 meter, 3 mm for span length between 2.5 to 4 meter and 3 to 4 mm for span length between 5 and 10 meter Cover for Cable Trays / Ladders:Cover for trays/ladders to protect the cable insulation from falling objects, water droplets, harmful effects of ultraviolet rays and accumulation of dust. The cover shall be made either from Hot Dip Galvanized sheet steel or superior quality Double Dip Galvanized Sheets. For Outdoor application, Double dip Galvanized material shall be used. The covers should be fitted properly to the Ladder / Tray by using pre fixed and tested locks which ensure that covers are fitted rigidly to Tray / Ladder. For outdoor application in high wind areas, additional cross over beadings to be used for fixing the cover on tray / ladder of width more than 500 mm. Mounting Accessories (supports and Brackets):- Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 17 The mounting accessories shall be fabricated from steel and has to be hot dip galvanized against corrosion confirming to ISO 1461-1999 for installations in both indoor and outdoor applications and should be of completely modular type. All supports and Brackets should be factory made, hot dip galvanized after completing welding, cutting, drilling, other machining operations and tested according to IEC 61537 according to the arrangements in the enclosed drawing. The system shall be designed such that it allows easy assembly at site by using Bolts and Nuts. The main support and brackets shall be fixed at site using necessary brackets, clamps, fittings, bolts, nuts and other hard ware etc to form various arrangements required to support the cable trays. Welding of the components at the site shall not be allowed. Corrosion Protection:The cable tray / ladder/accessories shall be of HOT DIP Galvanized (ISO 1461-1999) for installations in corrosive atmospheres both indoor and outdoor application. Sample tray / ladder / accessories / mounting accessories and supports should be salt spray tested according to ISO 9227 for > 500 hours. (*550 hours according to class 6 for Hot dip Galvanized surface as per ISO) Testing and Certification:Cable tray / Ladder, bend, T Bend, cross, and all supports are to be tested for Safe Working Load (SWL), deflections, Impact resistance, Salt Spray & Electrical continuity test according to IEC 61537. The cable th tray/ladder should not deflect more than 1/100 of the span length at SWL in Mid span and the transverse th deflection of all mounting accessories at SWL shall not exceed 1/20 of the length. The cable tray / cable ladder should be tested up to 1.7 times SWL at minimum and maximum room temperature. The temperature classification of cable tray system should be - 5 to + 150°C. Marking, Documentation, Compliance and Inspection:Each system component shall be durably and legibly marked with: -the manufacturer’s or responsible vendor’s name or trade mark or identification mark; -a product identification mark which may be, for example, a catalogue number, a symbol, or the like. When system components other than cable tray lengths and cable ladder lengths are supplied in a package, the product identification mark may be, as an alternative, marked on the smallest package unit. Marking shall be applied, by moulding, pressing, engraving, printing, adhesive labels, or water slide transfers. Compliance is checked by inspection and, for marking on the product, by rubbing by hand for 15 s with a piece of cotton cloth soaked with water and again for 15 s with a piece of cotton cloth soaked with petroleum spirit. Marking made by moulding, pressing, or engraving is not subjected to the rubbing test. After the test, the marking shall be legible. If a system component is stored and transported at a temperature outside the declared minimum and maximum temperatures, the manufacturer or responsible vendor shall declare the precautions and the alternative temperature limits. Compliance is checked by inspection. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 18 The manufacturer or responsible vendor shall provide in his literature all information necessary for the proper and safe installation and use of the cable tray system and cable ladder system. The SWL and impact resistance is valid for the whole temperature classification declared. The information shall include a. Instructions for the assembly and installation of system components and for the precautions required to avoid excessive transverse deflection, which could cause damage to the cables. b. Thermal Expansion properties and precautions to be taken, if necessary, c. Material, Surface Treatment and Salt Spray Test certificate d. Relative humidity if it affects the material and Surface Treatment e. Information on holes or devices provided for equipotential bonding or to run Earth Bonding Bar f. Precautions for transport and storage outside the declared temperature classification, where applicable g. Product dimensions h. Torque setting in Nm for screwed connections and internal fixing Devices. These devices should not create any damage to the cable when correctly fixed. Sudden or jerky motions shall not be used to tighten reusable screw connections. To test the screwed connections, it shall be tightened and removed. i. End Span Distance j. Position and type of coupling along the span k. SWL in kg/m for the fittings when not directly supported l. Fixing method for installing cable tray or cable ladder to the supports m. SWL in kg/m for the cable tray lengths or the cable ladder lengths including joints for various Span Distances. SWL information can be given in the form of a diagram, table or similar. Compliance is checked by inspection n. SWL in kg for cantilever brackets o. SWL for pendants as a bending moment in kg and /or as a force in N p. The appropriate material specification and environmental conditions, chemical environments or aggressive agents for which the product is suitable SPECIFICATION FOR WIRE MESH CABLE TRAY GENERAL:Wire Mesh Cable Tray System intended for the support and accommodation of power, Instrumentation, data network, voice, video and other low-voltage cables and possibly other Electrical equipment in Electrical / Communication systems. The SYSTEM shall support commercial, industrial, and utility applications and should be designed, constructed and tested according to IEC 61537. Design and Fabrication of Mesh trays:The wire mesh cable tray shall be manufactured according to the design specified by IEC 61537 and should be tested for Safe Working Load (SWL). The relevant details of SWL and the load chart with respect to SWL, supporting distance and the deflection should be according to the following chart. Safe Working Load (SWL) with a span length up to 2 meters Span length (in meters) Side Width Description Height (in mm) (in mm) Consultant : JIT Engineering Services Consultant 1m 1.5m 2m Permitted Load (in Kg/meter.) Sign of Bidder Electrical Works – Specifications and List of Make 35 Mesh cable tray 55 105 E- 19 50 - 150 25 11 10 200 30 14 10 300 75 22 15 50 - 150 25 12 8 200 - 400 60 28 25 500 - 600 75 38 25 100 – 200 80 55 37 300 – 400 110 75 53 500 – 600 125 85 60 Each section of mesh tray shall have a length of 3 meter of continuous, rigid, welded steel wire mesh. Consecutive straight length of 3 meter mesh trays shall be connected without couplers or connecting tools Screwed connections and internal fixing Devices should not create any damage to the cable when correctly fixed. Sudden or jerky motions shall not be used to tighten reusable screw connections Cables shall run in cable tray mounted horizontally or vertically on cable tray support system which in turn shall be supported from floor, ceiling, overhead structures, trestles or other building structures using mounting accessories SURFACE TREATMENT: Electro Galvanized confirming to DIN E 12329 with minimum 10 microns zinc coating for indoor closed and dry atmospheric application Hot Dipped Galvanized confirming to ISO 1461 – 1999 with minimum 60 microns zinc coating for outdoor or open area applications Stainless steel 304 for Food/Beverage/Pharmaceutical and clean room application Stainless steel 316 for highly corrosive atmospheric areas like chemical plant & Offshore platforms According to area of application, Surface treatment of material can be selected. Eg. Electro Galvanised cable tray and accessories should never be used in outdoor or open areas. CONSTRUCTION:The Tray shall be constructed using 50 mm x 100 mm grid except for 50mm wide tray to ensure maximum ventilation of cables and dissipation of heat. For 50 mm wide tray, the grid size should be 20 Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 20 mm x 100 mm. All exposed fabricated edges shall be tapered to ensure safe handling and installation of the product. One end of each straight section of formed wire mesh cable tray shall be of integrated interlocking ends. The diameter of the steel wire shall be minimum 3.5 mm for trays up to 150 mm width and minimum 4.5 mm for trays up to 600 mm width. Screw less straight connection of mesh cable tray shall be made without couplers and special tools for straight consecutive lengths. All tray fittings (eg., change in direction) shall be constructed at site by using bolt cutters and fastened using joint connectors, clamps & corner connectors with M6x20 bolt and combination nut. The connectors and clamps should be same or higher corrosion resistance class of the tray. Mounting Accessories (supports and Brackets):The mounting accessories shall be fabricated from steel and has to be hot dip galvanized against corrosion confirming to ISO 1461-1999 for installations in both indoor and outdoor applications and should be of completely modular type. All supports and Brackets should be factory made, hot dip galvanized after completing welding, cutting, drilling, other machining operations and tested according to IEC 61537 according to the arrangements in the enclosed drawing. The system shall be designed such that it allows easy assembly at site by using Bolts and Nuts. The main support and brackets shall be fixed at site using necessary brackets, clamps, fittings, bolts, nuts and other hardware etc to form various arrangements required to support the mesh trays. Welding of the components shall not be allowed. Corrosion Protection Testing:Sample tray / accessories / mounting accessories and supports should be salt spray tested according to ISO 9227 as below # Corrosion class resistance Material Surface Treatment Salt spray test duration 1 1 Electro Galvanised 24 Hours 2 6 Hot Dip Galvanised 550 hours 3 6 Double Dip Galvanised 550 Hours 4 9 A to 9 D Stainless Steel Not applicable Testing and Certification:Mesh tray and all mounting supports are to be tested for Safe Working Load (SWL), deflections, Impact resistance, Salt Spray & Electrical continuity test according to IEC 61537. The cable tray should not th deflect more than 1/100 of the span length at SWL in Mid span for mesh trays and the transverse Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 21 th deflection of all mounting accessories at SWL shall not exeed 1/20 of the length. The mesh tray should be tested up to 1.7 times SWL at minimum and maximum Temperature. The temperature classification of mesh tray system should be - 5 to + 150°C. Marking, Documentation, Compliance and Inspection:The manufacturer or responsible vendor shall provide in his literature all information necessary for the proper and safe installation and use of the mesh tray system. The SWL and impact resistance is valid for the whole temperature classification declared. The information shall include a. Instructions for the assembly and installation of system components and for the precautions required to avoid excessive transverse deflection, which could cause damage to the cables. b. Thermal Expansion properties and precautions to be taken, if necessary, c. Material, Surface Treatment and Salt Spray Test certificate d. Relative humidity if it affects the material and Surface Treatment e. Information on devices provided for equipotential bonding or to run Earth Bonding Bar if necessary for routing power cables f. Product dimensions g. Torque setting in Nm for screwed connections and internal fixing Devices. These devices should not create any damage to the cable when correctly fixed. Sudden or jerky motions shall not be used to tighten reusable screw connections. To test the screwed connections, it shall be tightened and removed. h. End Span Distance i. Position and type of coupling along the span j. SWL in Kg/m for the fittings when not directly supported k. Fixing method for installing mesh tray or to the supports l. SWL in Kg/m for the mesh tray lengths or the lengths including joints for various Span Distances. SWL information can be given in the form of a diagram, table or similar. Compliance is checked by inspection m. SWL in KG for cantilever brackets n. SWL for pendants as a bending moment in Kg and /or as a force in N o. The appropriate material specification and environmental conditions, chemical environments or aggressive agents for which the product is suitable INSTALLATION Prior to and during installation, refer to SYSTEM layout drawing containing all elements of the SYSTEM. Installer shall comply with manufacturer’s installation procedures. Support and cable loading shall be done in accordance with manufacturer’s load diagram. 1.0 Cable Trays shall be Galvanized and factory fabricated out of MS channels, angle iron, tee, bends, sections, flats and perforated sheet for different loads and number and size of cables as given below : Cable trays shall be galvanized as per Specification given elsewhere. a. 1500 mm wide Runners 25 x 100 x 25 x 3 mm Rungs 20 x 40 x 20 x 3 mm 250 mm C/C Suspenders 2 Nos. 40 x 40 x 5 mm GI angle 1200 mm C/C Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make b. E- 22 1200 mm wide Runners 25 x 100 x 25 x 3 mm Rungs 20 x 40 x 20 x 3 mm 250 mm C/C Suspenders 2 Nos. 40 x 40 x 5 mm GI angle 1200 mm C/C c. 1000 mm wide Runners 25 x 100 x 25 x 3 mm Rungs 20 x 40 x 20 x 3 mm 250 mm C/C Suspenders 2 Nos. 40 x 40 x 5 mm GI angle 1200 mm C/C d. 750 mm wide Runners 25 x 100 x 25 x 3 mm Rungs 20 x 30 x 20 x 2.5 mm 250 mm C/C Suspenders 2 Nos. 32 x 32 x 5 mm GI angle 1200 mm C/C e. 600 mm wide Runners 25 x 100 x 25 x 3 mm Rungs 20 x 30 x 20 x 2.5 mm 250 mm C/C Suspenders 2 Nos. 32 x 32 x 5 mm GI angle 1500 mm C/C f. 450 mm wide Runners 25 x 100 x 25 x 3 mm Rungs 20 x 30 x 20 x 2.5 mm 250 mm C/C Suspenders 2 Nos. 25 x 25 x 4 mm GI angle 1500 mm C/C g. Supply and fixing of perforated type cable trays of the following sizes of pre-galvanized iron. 600 x 100 x 100 x 2 mm thick 450 x 100 x 100 x 2 mm thick 300 x 100 x 100 x 2 mm thick 150 x 100 x 100 x 2 mm thick Note: Suitable length of 8 mm dia. GI rod suspenders at 1200 mm intervals shall be included in the item for perforated type cable tray. 2.0 Specification for hot dip galvanizing process for mild steel used for earthing, cable trays or junction boxes for electrical installation Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 1.2 General Requirements I. Quality Of Zinc E- 23 Zinc to be used shall conform to minimum Zn 98 grade as per requirement of IS: 209-1992. Ii Coating Requirement Minimum weight of zinc coating for mild steel flats with thickness up to 6 mm in accordance with IS:67451972 shall be 400 g/sqm. The weight of coating expressed in grams per square metre shall be calculated by dividing the total weight of Zinc by total area (both sides) of the coated surface. The Zinc coating shall be uniform, smooth and free from imperfections as flux, ash and dross inclusions, bare patches black spots, pimples, lumpiness, runs, rust stains bulky white deposits, blisters. Mild steel flats / wires shall undergo a process of degreasing pickling in acid, cold rinsing and then galvanizing. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 24 E 5 . M e d i u m Vo l t a g e C a b l e s 1.1 Scope This section shall cover supply of medium voltage cables. 1.2 Standards The following standards and rules shall be applicable: IS: 1554 PVC insulated electric cables (heavy duty). IS: 1753 Aluminium conductors for insulated cables. IS: 3961 Recommended current ratings for cables. IS: 8130 Aluminium conductors for insulated cables Indian Electricity Act and Rules. 1.3 Measurements The cables will be measured in meters. The unit rate shall include cutting the cable into required lengths, packing, loading, unloading, insurance, transportation, delivery to stores/site as per work order, stocking in stores, testing of cables at stores etc. of medium voltage cable. 1.4 General The medium voltage cables shall be supplied, laid, connected, tested and commissioned in accordance with the drawings, specifications, relevant Indian Standards specifications, manufacturer’s instructions. The cables shall be delivered at site in original drums with manufacturer’s name, size, and type, clearly written on the drums. 1.5 Material The MV cables shall be cross linked polyethylene (XLPE) insulated PVC sheathed of 1100 volts grade aluminium or copper conductor, armoured and unarmoured heavy duty, conforming to IS : 7098 Part I IS : 1988 Part I. as asked for in the schedule of quantities. 1.5.1. All XLPE Aluminium/Copper Power cables shall be 1100 Volts grade, multi core constructed as per IS : 7098 Part-I of 1988 as follows : a. Stranded Aluminium /Copper conductor of high conductivity up to 4 mm.² size, the conductor shall be solid and above 4 mm.², conductors shall be concentrically stranded as per IEC: 228. b. Cores laid up c. The inner sheath should be bonded over with thermo-plastic material for protection against mechanical and electrical damage. d. Armoring should be provided over the inner sheath to guard against mechanical damage. Armouring should be Galvanized steel wires or galvanized steel strips. (In single core cables used in A.C. system armouring should be non-magnetic hard aluminium Wires/Strips. Round Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 25 steel wires should be used where diameter over the inner sheath does not exceed 13 mm; above 13 mm flat steel armour should be used. Round wire of different sizes should be provided against specific request.) e. The outer sheath should be specially formulated heat resistant black PVC compound conforming to the requirement of type ST2 of IS: 5831-1984 extruded to form the outer sheath. 1.5.2. Conductor shall be of electrolytic Aluminium/Copper conforming to IS : 8130 and are compact circular or compact shaped. 1.5.3. Insulation shall be of XLPE type as per latest IS general purpose insulation for maximum rated conductor temperature 70 degree centigrade. 1.5.4. In Inner sheath laid up cores shall be bonded over with thermoplastic against mechanical and electrical damage. material for protection 1.5.5. Insulation, inner sheath and outer sheath shall be applied by extrusion and lapping up process only. 1.5.6. Armouring shall be of galvanized steel wire/flat. Galvanized steel flat strip / round wires applied helically in single layers complete with covering the assembly of cores. For cable size up to 25 Sq. mm: Armour of 1.4 mm dia. G.I. round wire For cable size above 25 Sq. mm: Armour of 4 mm wide 0.8 mm thick G.I. strip 1.5.7. Repaired cables shall not be used. 1.5.8. Current ratings of the cables shall be as per IS: 3961. 1.5.9. The XLPE insulated cables shall conform to latest revision IS read along with this specifications. The Conductor shall be stranded Aluminium/Copper circular/ sector shaped and compacted. In multi core cables the core shall be identified by red, yellow, blue and black coloring of insulation as following. Core identification: Two cores : Red and Black Three cores : Red, Yellow and Blue Four core : Red, Yellow, Blue and Black Single core : Green, Yellow for earthing Black shall always be used for neutral. 1.5.10. The XLPE insulated 1100 Volts grade power cables shall conform to latest IS and shall be suitable for a steady conductor temperature of 70 degree centigrade. The conductor shall be stranded Aluminium/Copper as called for in the Schedule of quantities. The outer sheath shall be as per the requirement of type ST-2 of IS: 5831 of 1984. 1.5.11. The cables shall be suitable for laying in racks, ducts, trenches, conduits and underground buried installation with uncontrolled back fill and chances of flooding by water. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 26 1.5.12. Progressive automatic in line sequential marking of the length of cables in meters at every one meter shall be provided on the outer sheath of all cables. 1.5.13. Cables shall be supplied in non returnable wooden drums as per IS: 10418. Both ends of the cables shall be properly sealed with PVC/Rubber caps so as to eliminate ingress of water during transportation, storage and erection. 1.5.14. The product should be coded as per IS: - 7098 Part-I as follows:- 1.6 Aluminium Conductor A XLPE Insulation 2X Steel round wire armour W Steel strip armour F Steel Double round wire armour WW Steel Double strip armour FF Non-magnetic (Al.) round wire armour Wa Non-magnetic (Al.) strip armour Fa PVC outer sheath Y General All cables shall be adequately protected against any risk of mechanical damage to which they may be liable in normal conditions of handling during transportation, loading, unloading etc. The cable shall be supplied in single length i.e. without any intermediate joint or cut unless specifically approved by the client. The cable ends shall be suitably sealed against entry of moisture, dust, water etc. with cable compound as per standard practice. 1.7 Testing 1.1.1 Finished Cable T ests At M anufacturer’s Works The finished cables shall be tested at manufacturer’s works. Following routine tests for each and every length of cable and copy of test results shall be furnished for each length of cable along with supply. If specified, the cables shall be tested in presence of clients' representative. a. Voltage test Each core of cable shall be tested at room temperature at 3 KV A.C. R.M.S. for duration of 5 minutes. b. Conductor resistance test The D.C. Resistance of each conductor shall be measured at room temperature and the results shall be corrected to 20° c. to check the compliance with the values specified in IS 8130 - 1976. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 27 Prior to dispatching cables and at the time of delivering the cables at stores, following tests shall be carried out:Insulation Resistance test between phases and phase to Neutral and phase to earth Continuity test of all the phases, neutral and earth continuity conductor Sheathing continuity test Earth resistance test of all the phases and neutral All tests shall be carried out in accordance with relevant Indian Standard Code of practice and Indian Electricity Rules. The Vendor shall provide necessary instruments, equipments and labour for conducting the above test and shall bear all expenses in connection with such tests. All tests shall be carried out in the presence of the client and results shall be recorded in the prescribed forms. 1.8 Cable Marking Embossing On Outer Sheath The outer sheath shall be legibly embossed with following legend: ELECTRIC CABLE: 1100 V, SIZE: 3.5 C x ----- mm ². Manufacturer’s Name & year of manufacturing. 1.9 Sealing, Drumming & Packing After tests at the manufacturer’s works, both ends of the cable shall be sealed to prevent the ingress of moisture during transportation and storage. Cable shall supply in length of 500 ± 10% meters on packed non-returnable drums of sufficiently sturdy construction. Cables of length more than 250 meters shall also be supplied on non-returnable drums. The spindle hole shall be 110 mm minimum diameter. Each drum shall bear on the outside flange, legibly and indelibly in the English literature, a distinguishing number, the manufacturer’s name and particulars of the cable i.e. voltage grade, length, conductor size, cable type, insulation type and gross weight shall also be clearly visible. The direction for rolling shall be indicated by an arrow. The drum flange shall also be marked with manufacturer’s name and year of manufacturing etc. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 28 E 6 . C a b l e Te r m i n a t i o n Not Applicable E 7 . M e d i u m Vo l t a g e P a n e l B o a r d / M v S w i t c h G e a r 1.1 Scope This scope shall cover design, manufacture, check test, and supply, installation, testing (Scope to assist the Ele. Contractor for installation, all the sections of panels & Internal Control wiring should be done by panel vendor on site ), testing and commissioning of various medium voltage Panel Board as described in Bills of quantities and drawings. The Panel manufacturer should have a design validated by CPRI / ERDA for breaking capacity of at least 100 KA for 1 Sec. Medium voltage Panel Board will be installed indoor and is connected through the cables. 1.2 Service Conditions At Site Ambient Temperature : Max. / Min. = 45° C. / 6° C. Design temperature : 50 Degree C. Relative humidity : 95% max. Voltage 1.3 : 415+/- 10%, TPN Frequency : 50 Hz. + 3% to -6% Neutral : Solidly / earthed neutral. Fault level : 15KA, Symmetrical at 415V solidly earthed. Documentation 1.3.1. Vendor shall furnish drawings General arrangement drawing indicating accessories and dimensions. Foundation plan and loading. Termination arrangement with dimensions. Three phase wiring diagrams SLD’s and control schemes Terminal plans Bill of quantity for each panel. 1.3.2. Documents to be submitted after placement of order, before starting of the Fabrication of the Panels As per above for comments and approval for manufacture. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 29 Schematic and sectional drawing. 1.3.3. Final documents - data and manuals in six sets along with equipment supplied. As built drawings with RTP (Reproducible Tracing Paper). Instruction and maintenance manual - Six copies. Test certificates - Six copies. 1.4 General Specifications All the Panels shall be metal clad, totally enclosed, rigid, floor / wall mounting, air insulated, cubicle type suitable for operation on three phase / single phase, 415 V / 230 V / 240 V, 50 Hz., neutral effectively grounded at transformer and short circuit level as mentioned in the drawings. Degree of protection for following type of distribution panel enclosure shall be as per IS: 13947-1993. a. IP 52 for indoor panels. b. IP 54 for kitchen and laundry panels. c. IP 55 for outdoor panels. The painting of all the metal part shall be with seven tank process followed by powder coating as per the standard. The Panels shall be designed to withstand the heaviest condition at site, with maximum expected ambient temperature of 50° c., 95% humidity. 1.5 Standards And Codes: The Panels shall comply with the latest edition of relevant Indian Standards and Indian Electricity Rules and Regulations. The following Indian standards shall be complied with: Standard no. Particular IS : 4237 General requirements for switchgear and control gear for voltages not exceeding 1000 V A.C. or 1200 V D.C. IS : 5578 Guide for marking of insulated conductors. IS : 11353 Guide for uniform system of marking and identification of conductors and apparatus Terminals. IS : 13947 Low voltage switchgear and control gear. IS : 8197 Terminal marking for electrical measuring instrument and their accessories. IS : 2551 Danger notice plates IS : 10118 Code of Practice for selection, installation and maintenance of switchgear and control gear. IS : 8623 Specification for factory built assemblies of switchgear and Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make Standard no. E- 30 Particular control gear for voltage up to and including 1000 V A.C. and 1200 V D.C. IS : 8828 Miniature circuit breakers. IS : 9224 HRC fuse links IS : 2705 Current transformer IS : 3156 Voltage transformer IS : 3231 Electrical relay for protection IS : 1248 Indicating instrument IS : 722 Integrating instrument IS : 6875 Control switches and push buttons IS : 1822 A.C. motor starters of voltage not exceeding 1000 V Indian Electricity Act and Rules (as amended up to date) and approval of FIA of India. The Panels also require approval of the consultant at various stage of their manufacture such as design, selection, construction, testing, shipping etc. 1.6 Construction 1.6.1 Cubical Type Panels A. Structure The Panels shall be of compartmentalized design so that circuit arc / flash products do not create secondary faults and be fabricated out of high quality CRCA sheet, suitable for indoor installation having dead front operated and floor / wall mounting type. The type of construction shall be 4b. All CRCA sheet steel used in the construction of Panels shall be 2 mm. thick and shall be folded and braced as necessary to provide a rigid support for all components. Joints of any kind in sheet steel shall be seam welded, all welding slag grounded off and welding pits wiped smooth with plumber metal. The Panels shall be totally enclosed, completely dust and vermin proof and degree of protection being not less than IP: 51 to IS: 2147. Gaskets between all adjacent units and beneath all covers shall be provided to render the joints dust proof. All doors and covers shall be fully gasketed with foam rubber and /or rubber strips and shall be lockable. All panels and covers shall be properly fitted and screwed with the frame and holds in the panel correctly positioned. Fixing screws shall enter into holes, taped into an adequate thickness of metal or provided with bolts and nuts. Self threading screws shall not be used in the construction of Panels. A base channel of 75 mm. x 40 mm. x 6 mm. thick shall be provided at the bottom. A clearance of 300 mm. between the floor of the Panels and the bottom of the lower most units shall be provided. Panels shall be preferably arranged in multi-tier formation. The Panels shall be of adequate size with a provision of 20% spare space to accommodate possible future additional switchgear. The size of the Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 31 Panels shall be designed in such a way that the internal space is sufficient for hot air movement and the electrical component does not attain temperature more than 50c. If necessary, openings shall be provided for natural ventilation, but the said openings shall be screened with fine weld mesh. The entire electrical component shall be derated for 50c. Knock out holes of appropriate size and number shall be provided in the Panels in conformity with the number, and the size of incoming and outgoing conduits / cables. Alternately, the Panels shall be provided with removable sheet steel plates at top and bottom to drill holes for cable / conduit entry at site. The Panels shall be designed to facilitate easy inspection, maintenance and repair. The Panels shall be sufficiently rigid to support the equipment without distortion under normal and under short circuit condition. They shall be suitably braced for short circuit duty. A1. Structure & Construction for IP 65 Panel / Feeder Pillar Feeder Panels shall be lockable IP65 & 3 mm thick sheet steel cabinet for Outdoor installation, dead front, floor mounting type and shall be form 3b construction. The Distribution panels shall be totally enclosed, completely dust and vermin proof and shall be with hinged doors, Neoprene gasket, padlocking arrangement and bolted back. All removable/ hinged doors and covers shall be grounded by flexible standard connectors. Distribution panel shall be suitable for the climatic conditions as specified in Special Conditions. Steel sheets used in the construction of Distribution panels shall be 3 mm thick and shall be folded and braced as necessary to provide a rigid support for all components. Joints of any kind in sheet metal shall be seam welded, all welding, slag shall be rounded off and welding pits wiped smooth with plumber metal. The general construction shall confirm to IS-8623-1977 (Part-1) for factory built assembled switchgear & control gear for voltage up to and including 1100 V AC. All panels and covers shall be properly fitted and square with the frame, and holes in the panel correctly positioned. Fixing screws shall enter into holes tapped into an adequate thickness of metal or provided with wing nuts. Self threading screws shall not be used in the construction of Distribution panels. A base channels of 75 mm x 40 mm x 5 mm thick & Suitable Size Stand with the 3 mm Sheet Cover the bottom for floor mounted panels. Minimum clearance of 450 mm shall be provided between the floor of Distribution panels and the lowest unit. The Internal electrical switchboard (panel) shall be made up of high quality polycarbonate thermoplastic, shock proof, anti-corrosive, acid & chemical resistant, fire retardant, self extinguishing, highly impact resistant, halogen free, silicon free, recyclable, having internally embedded gasket. The switchboard (panel) shall have provision for future expansion & shall be modular in construction. The bus bars shall be connected with C type clamps without any drilling on the bus bars. The panel shall be in accordance with IEC 60 439 – 1 (Fully TTA). The Degree of Ingress Protection shall be in accordance with IEC 60 529. Panel Enclosure (Internal) has to be thermoplastic polycarbonate or of the material which has equivalent or exceeds the inherent features of thermoplastic polycarbonate. Said enclosures, in addition to containing the devices and components that constitute the electrical panel, must have certain properties and characteristics that are specific for their practical use; for e.g. they must provide a suitable degree of electrical insulation, have sufficient structural strength, be easy to handle, ensure adequate resistance to the aggression of chemical and atmospheric agents, be self extinguishing, etc. It should be clean and aesthetically appreciable. Internal panel should be totally insulated FEEDER PILLAR PANEL made out of Modular Panel Box System, Degree of Protection IP 65, in accordance with IEC 60 529, type tested in accordance with IEC 60 439 – 1. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 32 The manufacturer of board/panel shall submit a copy of CPRI test report of Degree of Ingress Protection IP 65 in accordance with IEC 60529. The gasket material shall be Polyurethane; while the gasket shall be internally embedded. The manufacturer of board / panel shall submit a copy of type test report of a board made out of Polycarbonate thermoplastic panel in accordance with IEC 60439-1. The report shall have mention of following tests performed and passed out satisfactorily: 1. 2. 3. 4. 5. 6. Temperature Rise. Dielectric Properties. Short circuit withstand current – Rated peak & short time withstand current and Rated Conditional Short Circuit Current. Effectiveness of Protective Circuits. Clearance & Creep age Distance. Mechanical Operation For better safety the Polycarbonate encl shall be fire retardant & self extinguishing in accordance with IEC 60 695-2-11, DIN VDE 0304 Part 3, UL Subject 94 for Flammability V-2. It should be tested at Glow Wire test for 960 deg. Cent. The impact strength of polycarbonate enclosures / boards i.e. the Degree of Protection against Mechanical load shall be in accordance with EN 50298-98 for IK 08. The lid closing and opening shall be done by quick fastening spring mechanism latches. Compactness of the boards is main criteria due to space constraints. The board / panel should be made compact meeting the technical requirements in accordance with relevant standards and also keeping adequate space for technicians to work. The MCB/ RCCB switching operations / accessing the MCB dolly should be preferably by opening of a window flap. Window flap must be integral part of body of the box. Window flap Additional screwing by cutting the front of the box for MCB or any accessories will not be acceptable. Note: The board manufacturer must submit the copy of type test reports for Polycarbonate Thermoplastic Board only with final arrangements as per approved GA. Test Reports submitted of other material of construction like MS, SS will not be applicable. Each Board shall have individual routine test report of the manufacturer. Internal Insulated enclosures of protection class II shall be made out of environment friendly, recyclable polycarbonate thermoplastic, UV Resistant, halogen & silicon free, highly impact resistant, Anti Acid, Anti corrosive : Resistant against demands caused by rains, water and corrosive atmosphere, Degree of Protection against mechanical load IK 08 in acc. with DIN EN 50 102, Color Gray RAL 7032, fire retardant, Glow Wire Tested at 960 deg. cent in acc. with IEC 60 695–2-1, DIN VDE 0304 Part 3. UL Subject 94, V – 2, Flame Retardant, Self Extinguishing, with transparent / opaque lids having tool operated / sealable / hand operated / lockable quick fastening mechanism. Modular panel box doors especially for circuit breakers should be the integral part of the top cover, Additional flap mounted on the box shall not be allowed. Incoming & Outgoing Cable from all the directions…. Mounting Type: Free Standing Type with Canopy of 3 mm thick CRCA Sheet. Protection Measure: Totally Insulated Degree of Protection: IP 65 in acc. with IEC 60 529 Rated Voltage: 690 / 1100 V Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 33 Bus Bar System: electrolytic grade square type copper bus bars as per description with insulated supports. Interconnection between solid bus bars and equipment shall be connected by means of bus bar connectors to avoid tapings on solid bus bars… Temperature Resistance: - 40 deg. cent to + 120 deg. cent. Distribution panels shall be of adequate size with a provision of spare switchgear as indicated on the Single Line Diagram. Switches shall be arranged in multi-tier. Knockout holes of appropriate size and number shall be provided in the Distribution panels in conformity with the location of cable / conduit connections. Removable sheet steel plates shall be provided at the Bottom to make holes for additional cable entry at site if required. Every cabinet shall be provided with Trifoliate or engraved metal name plates. All panels shall be provided with circuit diagram engraved on PVC sheet. All live accessible connections shall be shrouded and shall be finger touch proof and minimum clearance between phase and earth shall be 20 mm and phase to phase shall be 25 mm. Sr. No. Criteria / Parameter SMC required specification 1. Material of Construction of Main Feeder Pillar Panel Polycarbonate 2. Degree of Protection IP 65 in accordance with IEC 60 529 3. Gasket Material enclosure Sr. No. 4. Ingress of Vendor specification Polyurethane Criteria / Parameter SMC required specification Test Report The Polycarbonate Panel manufacturer shall submit the test report The Polycarbonate Panel manufacturer shall submit the test report for following type tests. Vendor specification 1. Temperature Rise. 2. Dielectric Properties. 3. Short circuit withstand current – Rated peak & short time withstand current and Rated Conditional Short Circuit Current. 4. Effectiveness of Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 34 Protective Circuits. 5. Clearance & Creepage Distance. 6. Mechanical Operation B. 5. Fire Retardant & SelfExtinguishing Test The PC Enclosures shall be tested for Glow Wire Test at 960 deg. cent. in accordance IOEC 60 695 – 2 – 11 6. Impact Test The PC Enclosure shall be rated for IK 08 for mechanical impact test in accordance with EN 50298-98 Protection Class All the indoor Panels shall have protection class of IP : 51 C. Painting The painting shall be seven tank process followed by powder coating. D. Circuit Compartments Each circuit breaker and switch fuse unit shall be housed in separate compartments and shall be enclosed on all sides. Sheet steel hinged lockable door shall be duly interlocked with the breaker in `ON’ and `OFF’ position. The door shall not form an integral part of draw out position of the circuit breaker. All instruments and indicating lamp shall be mounted on the compartment door. Sheet steel barriers shall be provided between the tiers in a vertical section. E. Instrument Compartments Separate adequate compartment shall be provided for accommodating instruments, indicating lamps, control contactors / relays and control fuses etc. These components shall be accessible for testing and maintenance without any danger of accidental contact with live parts of the switchgear / control gear, busbar and connections. F. Busbars The busbar shall be air insulated and made of high quality, high conductivity, and high strength Aluminium / Copper. The busbar shall be of 3 phases and neutral system with separate neutral and earth bar. The size of neutral busbar in all main panels or lighting panels and feeders for LDB shall be equal to phase busbar. The busbar and interconnection between busbars and various components shall be of high conductivity Aluminium / Copper. The busbar shall be of rectangular cross-section designed to withstand full load current for phase busbars and half rated current for neutral busbars in case of APFCR panels only and Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 35 shall be extensible on either side. The busbar size shall be as per drawing. The busbar shall have uniform cross-section throughout the length. The busbars and interconnections shall be insulated with epoxy coated bus sleeves. The busbar shall be supported on bus insulators of SMC/DMC type at sufficiently close intervals to prevent busbars sag and shall effectively withstand electromagnetic stresses in the event of short circuit capacity of 15 KA RMS symmetrical for 1 sec. The busbar shall be housed in a separate compartment. The busbar shall be isolated with 3 mm. thick Bakelite sheet to avoid any accidental contact. The busbar shall be arranged such that minimum clearance between the busbar is maintained as below: Between phases : 27 mm. minimum Between phases and neutral : 27 mm. Between phases and earth : 27 mm. Between neutral and earth : 20 mm. minimum All busbar connections shall be done by drilling holes in busbars and connecting by chromium plated or tinned plated brass bolts and nuts. Additional cross-section of busbar shall be provided in all Panels to cover up the holes drilled in the busbar. Spring and flat washers shall be used for tightening the bolts. All connections between busbars and circuit breakers / switches and cable terminals shall be through aluminium / Copper strips of proper size to carry full rated current. These strips shall be insulated with insulating tapes. Panel to panel entry of bus bar shall be effectively sealed by electrical and thermal insulation barriers so that products of flashover do not travel from one panel to another panel creating multiple faults. Busbar shall be calculated on 50 deg. C. ambient temp. and 85 deg. C. for continuous and short time rating. Busbar surrounding air temp. shall be considered 70 deg. C. for busbar calculation All joint shall have non-flammable insulation shrouds for secondary insulation purpose G. Electrical Power And Control Wiring Connection: Terminal for both incoming and outgoing cable connections shall be suitable for 1100 V grade, aluminium / copper conductor PVC insulated and PVC sheathed, armoured cable and shall be suitable for connections of solderless sockets for the cable size as indicated on the appended drawings for the Panels. Power connections for incoming feeders of the main Panels shall be suitable for 1100 V grade aluminium conductor (PVC) cables. Both control and power wiring shall be brought out in cable alley for ease of external connections, operation and maintenance. Both control and power terminals shall be properly shrouded. Clip on type terminals shall be provided up to 10 sq.mm conductor and above 10 sq.mm bolt type terminals shall be used. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 36 10% spare terminals shall be provided on each terminal block. Sufficient terminals shall be provided on each terminal block, so that not more than one outgoing wire is connected per terminal. Terminal strips for power and control shall preferably be separated from each other by suitable barriers of enclosures. Wiring inside the modules for power, control, protection and instruments etc. shall be done with use of 660 / 1100 V grade; PVC insulated copper conductor wires conforming to IS: 694 & 8130 Power wiring inside the starter module shall be rated for full current raring of respective contactor, but not less than 4.0 sq.mm. cross-section area. For current transformer circuits, 2.5 sq.mm. copper conductor wire shall be used. Other control wiring shall be done with 1.5 sq.mm. copper conductor wires. Wires for connections to the door shall be flexible. All conductors shall be crimped with solderless sockets at the ends before connections are made to the terminals. Control power supply to modules through the control transformer only. Control power wiring shall have MCB for circuit protection. All indicating lamps shall be protected by MCB. Particular care shall be taken to ensure that the layout of wiring is neat and orderly. Identification ferrules shall be fitted to all the wire termination for ease of identification and to facilitate checking and testing. Spring type washers shall be used for all copper and aluminium connections. Final wiring diagram of the Panels power and control circuit with ferrules numbers shall be submitted along with the Panels as one of the documents against the contract. H. Terminals The outgoing terminals and neutral link shall be brought out to a cable alley suitably located and accessible from the panel front. The current transformers for instruments metering shall be mounted on the disconnecting type terminal blocks. No direct connection of incoming or outgoing cables to internal components of the distribution board is permitted and only one conductor may be connected in one terminal. I. Wireways A horizontal / vertical metal / Al. wire way with screwed covers shall be provided at the top to take interconnecting control wiring between different vertical sections. J. Cable Compartments Cable compartments of minimum 300 mm size shall be provided in the Panels for easy termination of all incoming and outgoing cables entering from bottom or top. Adequate supports shall be provided in the cable compartments to support cables. All outgoing and incoming feeder terminals shall be brought out to terminal blocks in the cable compartment. K. Earthing Copper earth bars of 25 mm 6 mm shall be provided in the Panels for the entire length of the panel. The frame work of the Panels shall be connected to this earth bar. Provisions shall be made for connection from this earth bar to the main earthing bar coming from the earth pit on both sides of the Panels. The earth continuity conductor of each incoming and outgoing feeder shall be connected to this earth bar. The armour shall be properly connected with earthing clamp, and the clamp shall be made for connection from this earth pit on both sides of the Panels. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 37 The earth continuity conductor of each incoming and outgoing feeder shall be connected to this earth bar. The armour shall be properly connected with earthing clamp, and the clamp shall be ultimately bonded with the earth bar. L. Labels Engraved PVC labels shall be provided on all incoming and outgoing feeders. Single line circuit diagram showing the arrangements of circuit inside the distribution board shall be pasted on inside of the panel door and covered with transparent laminated plastic sheet. M. Name Plate A name plate with the Panel's designation in bold letters shall be fixed at top of the central panel. A separate name plate giving feeder details shall be provided for each feeder module door. Inside the feeder compartments, the electrical components, equipments, accessories like switchgear, control gear, lamps, relays etc. shall suitably be identified by providing stickers. Name plate shall be engraved in Gujarati language be of 3 ply, (Red-White-Red or Black-White-Black) lamicold sheet. However, black engraved perpex sheet name plates shall also be acceptable. Engraving shall be done with square groove cutters. Name plate shall be fastened by counter send screws and not by adhesives. N. Danger Notice Plates The danger notice plate shall be affixed in a permanent manner on operating side of the Panels. The danger notice plate shall indicate danger notice both in Hindi and English and with a sign of skull and bones. The danger notice plate, in general, meets the requirements of local inspecting authorities. Overall dimensions of the danger notice plate shall be 200 mm. wide x 150 mm. high. The danger notice plate shall be made from minimum 1.6 mm. thick mild steel sheet and after due pretreatment to the plate, the same shall be painted white with vitreous enamel paint on both front and rear surface of the plate. The letters, the figures, the conventional skull and bones etc. shall be positioned on plate as per recommendation of IS: 2551-1982. The said letters, the figures and the sign of skull and bones shall be painted in signal red colour as per IS: 5-1978. The danger plate shall have rounded corners. Location of fixing holes for the plate shall be decided to suit design of the Panels. The danger notice plate, if possible, is of ISI certification mark. O. Internal Components: The Panels shall be equipped complete with all types of required number of MCCB’s, contactors, relays, fuses, meters, instruments, indicating lamps, push buttons, fittings, busbars, cable connectors etc. and all the necessary internal connections / wiring as required and as indicated on relevant drawings. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 38 Components necessary for the proper and complete functioning of the Panels but not indicated on the drawings shall be supplied and installed on the Panels. All parts of the Panels carrying current including the components, connections, joints and instruments shall be capable of carrying their specified rated current continuously, without temperature rise exceeding the acceptable values of the relevant specifications at the part of the Panels. All units of the same rating and specifications shall be fully interchangeable. 1.7 Components 1.7.1 General The type, size and rating of the components shall be as indicated on the relevant drawings. While selection of the capacity of the components resulting from the prevailing conditions like ambient temperature shall be allowed for the thermal and magnetic trip rating shall be compensated for the ambient temperature. The rating indicated on the drawing is ratings anticipated at prevailing site conditions. 1.7.2 Air Circuit Breaker A. Construction The ACBs shall have following features: Motorized with 230 V A.C. motor. 230 V A.C closing and shunt trip coil Drawout type with "service", "test", "isolated" and "maintenance" position. Safety shutter of Fibre glass / polycarbonate sheet of 2mm thickess shall be provided Mechanically trip free plus antipumping feature is to be provided. Electrical trip free plus anti pumping shall be provided with relay ONLY and not by contactors. Electrical/Mechanical operation counter shall be provided. Door interlock with defeat features to be provided. ACB shall be lockable in isolation position. B. Release Microprocessor based release shall be direct acting type, tripping ACB mechanically. Short circuit, overload and earth fault protection shall be provided. Vendor to suggest release type for feeders of supply range characteristic and accuracy. C. Acb Performance ACB performance inside panels at ambient 50 Degree. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make The Symmetrical breaking, 50KA Making capacity peak 87.5 KA Short time rating , 1sec. 50KA D. E- 39 Incomer Acbs All incomer ACBs shall have following additional protections other than mentioned above. Under and over voltage Under and over frequency Restricted Earth Fault protection Trip Circuit supervision with PS class CT’s. Undercurrent, ( DG set only) Reverse power ( DG set only) Phase sequence reversal ( DG set only) Load shedding and reconnection thru programmable contacts. Release should display the Contact wear indication. The release should provide local indication of actual %age loading at any instant. The release should be able to communicate on MODBUS RTU protocol using inbuilt RS485 port and shall be integral part of supply with trip unit.Parameters of the Protection Release should be changeable from Release as well as thru communication network. Release should have graphical LCD for display of power parameters. The release should provide comprehensive metering with the following parameters Phase currents (running, avg & max) – All parameters in single window. Release should be able to capture short circuit current on which ACB has tripped.The last ten trips and alarms shall be stored in memory with the date & time stamping along with type of fault and alarm. The sensing CT Should be Rogowsky type with measurement precision of 1%. Release should be self powered . Release should have facility to select different type of IDMTL protection(DT,SIT,VIT,EIT,HVF) for better co-ordination with HT Breaker/Fuse. Phase voltages (running, avg & max) Energy & power parameters (active, reactive and apparent) PF Frequency Maximum Demand ( KVA & KW) Total Harmonics distortion Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E. E- 40 O/G Acbs All O/G ACBs shall have following functions. Protection The ACB control unit shall offer the following protection functions as standard: Long-time (LT) protection with an adjustable current setting and time delay; Short-time (ST) protection with an adjustable pick-up and time delay; Instantaneous (INST) protection with an adjustable pick-up and an OFF Position. Current and time delay setting shall be indicated in amperes and seconds respectively On a digital display. Earth-fault protection with an adjustable pick-up and time delay shall be provided if indicated on the appended single-line diagram. Measurements An ammeter with a digital display shall indicate the true rms values of the currents for each phase. Release shall acknowledge the current & time delay settings done by user on the LCD display. A LED bargraph shall simultaneously display the load level on the three phases. A maxi meter shall store in memory and display the maximum current value observed since the last reset. The data shall continue to be stored and displayed even after opening of the circuit breaker. Safety Features i. The safety shutter shall prevent inadvertent contact with isolating contacts when breaker is withdrawn from the Cradle. ii. It shall not be possible to interchange two circuit breakers of two different thermal ratings. For Drawout breakers, an arrangement shall be provided to prevent rating mismatch between breaker and cradle. iii. There shall be provision of positive earth connection between fixed and moving portion of the ACB either thru connector plug or sliding solid earth mechanism. Earthing bolts shall be provided on the cradle or body of fixed ACB. iv. The incoming panel accommodating ACB shall be provided with indicating lamps for ON-OFF positions, digital voltmeter and ammeter of size not less than 96 mm x 96 mm, selector switches, MCB for protection circuit and measuring instrument circuits. v. It shall be possible to bolt the draw out frame not only in connected position but also in TEST and DISCONNECTED position to prevent dislocation due to vibration and shocks. vi. Draw out breakers should not close unless in distinct Service/Test/Isolated positions. vii. The insulation material used shall conform to Glow wire test as per IEC60695. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make viii. E- 41 The ACB shall provide in built electrical and mechanical anti-pumping. ix. All EDO ACB`s Shall have Ready to Close Contact to ensure that the ACB gets a command only when it is ready to close for applications of Remote Control, AMF, Synchronization and Auto Source Change Over Systems. 1.7.3 Moulded Case Circuit Breaker The moulded case circuit breaker (MCCB) shall be air break type and having quick make - quick break with trip free operating mechanism. Housing of the MCCB shall be of heat resistant and flame retardant insulating material. Operating handle of the MCCB shall be in front and clearly indicate ON/OFF/TRIP positions. The electrical contacts of the circuit breaker shall be of high conducting non deteriorating silver alloy contacts. The MCCB shall be provided with thermal / magnetic type bi-metal overload release and electromagnetic short circuit protection device. All the releases shall operate on common trip busbar so that in case of operation of any one of the releases in any of the three phases, it will cut off all the three phases and thereby single phasing of the system is avoided. The MCCB wherever called for in the appended drawings shall provide an earth fault relay. The MCCB shall provide two sets of extra auxiliary contacts with connections for additional controls at future date. The electrical parameters of the MCCB shall be as per the description given in the appended drawings. Draw out type MCCB shall be provided for the feeder indicated in the single line diagram. The MCCB shall be provided with 230 V A.C motor for closing and tripping / switching off for the feeders if indicated in single line diagram. MCCB should be with following: i. Free Alarming for O/L, Healthiness check of the Breaker, Fault Differentiation on front of the MCB from Display / LED. ii. All MCCB should be Communicable & have all kind of communication accessories with in built metering should support open / Modbus protocol. iii. MCCB should provide switch board display unit for panel cutout. 1.7.4 Fuse Fuses shall be of high rupturing capacity (HRC) fuse links and shall be in accordance with IS: 2000-1962 and having high rupturing capacity of not less than 15KA at 415 V. The back-up fuse rating for each motor / equipment shall be so chosen that the fuse does not operate on starting of motors / equipment. HRC fuses shall be of the make as specified in Make of Material. 1.7.5 Miniature Circuit Breakers Miniature Circuit breakers shall be current limiting type conformed with British standard BS: 3871 (Part I) 1965 and IS: 8828. The housing of MCBs shall be heat resistant and having high impact strength. The Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 42 fault current of MCBs shall not be less than 10KA at 230 V. The MCBs shall be flush mounted and shall be provided with trip free manual operating mechanism with mechanical `ON’ and `OFF’ indications. The circuit breaker dollies shall be of the trip free pattern to prevent closing the breaker on a faulty circuit. The MCB contacts shall be silver nickel and silver graphite alloy and tip coated with silver. Proper arc chutes shall be provided to quench the arc immediately. MCBs shall be provided with magnetic fluid plunger release for over current and short circuit protection. The overload or short circuit device shall have a common trip bar in the case of DP and TPN miniature circuit breakers. All the MCBs shall be tested and certified as per Indian Standards, prior to installation. 1.7.6 Contactors The contactors shall meet with the requirements of IS: 13947 and BS: 771. The contactors shall have minimum making and breaking capacity in accordance with utilization category AC3 and shall be suitable for minimum Class II intermittent duty. If the contactor forms part of a distribution board then a separate enclosure is not required, but the installation of the contactor shall be such that it is not possible to make an accidental contact with live parts. 1.7.7 Voltmeter Voltmeter shall be digital. The dial of the meter shall be square in shape of 96 x 96 mm. The voltmeter selector switch shall be arranged to provide line to line voltage reading and line neutral voltage. 1.7.8 Ammeter Ammeter shall be digital. The dial of the ammeter shall be square in 96 x 96 mm. Separate current transformer shall be provided for all ammeters. 1.7.9 Current Transformer Where ammeters are called for C.T.s shall be provided for current measuring. Each phase shall be provided with separate current transformer of accuracy Class I and suitable VA burden for operation of associated metering and controls. Current transformer shall be in accordance with IS: 2705 - 1992 as amended up to date. 1.7.10 Push Buttons The push button unit shall comprise of the contact element, a fixing holder, and a push button actuator. The push button shall be momentary contact type. The contacts shall be of silver alloy and rated at 10 Amps. Continuous current rating. The actuator shall of standard type and colour as per its usage for ON, OFF and TRIP. Wiring for Remote ON, OFF push button is to be required. 1.7.11 Indicating Lamps Indicating lamps assembly shall be screw type with built in resistor having non fading color lens. LED type lamps are required. Wiring for Remote ON, OFF, TRIP indicating lamp is required. Colour shade for the indicating lamps shall be as below: ON indicating lamp : Consultant : JIT Engineering Services Consultant Red Sign of Bidder Electrical Works – Specifications and List of Make E- 43 OFF indicating lamp : Green TRIP indicating lamp : Amber PHASE indicating lamp : Red, Yellow, and Blue TRIP circuit healthy lamp Consultant : JIT Engineering Services Consultant : Milky Sign of Bidder Electrical Works – Specifications and List of Make E- 44 B. Power Factor Correction System With Detuned Filter 1.1 Scope Design, manufacture, supply, erection, testing and commissioning of Indoor type power correction capacitor banks for power factor improvement as per specification given below: 1.2 Standard Unless otherwise stated below, the capacitor shall comply with the following standards (and their latest amendments): IS 13340-1993, IS 13341-1992, IEC 60831-1+2 1.3 Rating 50 KVAR (or less) capacitor units as specified in the BOQ shall be used to form a bank of capacitors of desired capacity. 1.4 Enclosure The panel shall be indoor type, free standing, and floor mounting with IP42 degree of protection. It shall be completely made of CRCA sheet steel. The enclosure shall have sturdy support structure with angle supports as necessary and shall be finished with powder coating in the approved colour shade/s to match the colour of the other panels. The thickness of powder coating should be minimum 60-80 microns. Suitable provisions shall be made in the panel for proper heat dissipation. Air aspiration louvers for heat dissipation shall be provided as a necessary. The front portion shall house the switchgear and the rear portion shall house capacitors and series reactors. The enclosure is to be suitably sized to accommodate all the components, providing necessary air clearance between live and non-live parts, providing necessary working clearance. 1.5 Apfc Relay / Controller Microprocessor based IPFC relay (Intelligent VAr controller) shall sense the PF in the system and automatically switch ON / OFF the capacitor unit or stage to achieve the preset target PF. The controller shall have the following features: Digital settings from all the 3 phases for parameters like PF, Switching time delay, Step limit etc. Indication of PF, preset parameters. Minimum threshold setting of 1% of CT current. No-volt release. Protective shut down in case of harmonic overload. Indication for Failure to achieve the target PF, Harmonic overloading, Step failure etc. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 1.6 E- 45 Construction Each basic unit of mixed dielectric extra low loss / All Poly Propylene (APP) / GAS Filled capacitor shall be built with a number of elements. These elements shall be combination of capacitor tissue paper and biaxially oriented polypropylene film impregnated with non PCB bio-degradable impregnant or Film Foil capacitor manufactured using Poly propylene film placed between 2 layers of metal foil and winding. The elements shall be connected to the external bus bars through these leads in a series parallel connection to form a three phase unit. The capacitor units shall be floor mounting type using minimum floor space. The container of capacitors shall be made out of 2 mm thick M S sheet steel of polyester paint coated finish. Each standard unit shall be provided with internal fuses (operation co-ordinate with case-rupture characteristics to avoid rusting). Total Harmonic Distortion (THD) of up to 5% on voltage and current waveforms shall not affect the life of capacitors. 660±10% variation in line voltage shall not affect the life of the capacitors. 1.7 1.8 Capacitors General specifications: 3 phase, delta connected, 50 Hz. Voltage: Must be designed to withstand system over voltage, increased voltage due to series reactor and harmonics. Capacitor type: Super heavy duty with double side metalized capacitor tissue paper. Gas Filled and self-healing type with bi-axially oriented polypropylene film shall be fitted with pressure sensitive disconnector in each individual capacitor cell. Over voltage +10% (12h / 24h), + 15% (30m / 24h), + 20% (5m), +30% (1m) as per Clause 6.1 of IS 13340-1993. Over current : 2.5 x In Peak Inrush current withstand : 350 x In Total watt-losses including discharge resistors: < 0.45 W / k V Ar. Temperature category: -25 deg. C to 70 deg. C. Capacitor shall be self-heating type and oil impregnated for longer life. The impregnant shall be non-PCB, biodegradable type, must be properly treated and de-gasified, so as not to have any degeneration properties and shall be non-oxidizing. The design shall be modular for simple mechanical assembly, no extra accessories / metal parts to be required. Unit must be free standing with an IP 41 protection level. Discharge Resistance Capacitors shall be provided with permanently connected discharge resistors so that residual voltage of capacitors is reduced to 50 volts or less within one minute after the capacitors are disconnected from the source of supply. 1.9 Terminals Each capacitor bank shall be provided with a terminal chamber and cable glands suitable for PVC insulated aluminum conductor armoured cables as specified. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 1.10 E- 46 Earthing Two separate earthing terminals shall be provided for earth connection of each bank. 1.11 Low Voltage Filter Reactor Filter reactor shall be series type having a three phase, iron core construction suitable for indoor use. The reactor shall be air cooled and the layout shall be in accordance with IEC 76. The complete unit shall be impregnated under vacuum and over-pressure in impregnation resin and shall be suitable for temperature class H operation. The reactor coils shall be wound with high grade aluminum / copper and termination shall be provided with suitably designed copper bars. 1.12 Testing The reactor shall be tested `using a separate source voltage test of 3 KV (coil to core) for one minute as per IEC 76/3. The reactor shall be fitted with a temperature sensitive micro-switch in the centre coil (normally open) for connection to trip circuit in case of high operating temperature. 1.13 Series Reactor Application LV Harmonic Filters shall be used with harmonic filter duty power capacitors to mitigate harmonics, improve power factor and avoid electrical resonance in LV electrical networks. Construction, Testing & Protection The low voltage filter reactor shall be series type having a three phase, iron core construction suitable for indoor use (IP 00). The reactor shall be air cooled and the layout shall be in accordance with IEC 60076. The complete unit shall be impregnated under vacuum and over-pressure in impregnation resin and shall be suitable for temperature Class H (T60/H) operation. The reactor shall be tested using a separate source voltage test of 3.0kV (coil to core) for 1 minute as per IEC 60076/3. The permitted tolerance of inductance shall be + 3% of rated inductance value. Reactor tuning factor shall be 13% and the current rating of the reactor shall include the effects of harmonics and other possible over-currents. The limit of linearity of inductance of the filter reactor shall be as follows 1.2 with L = 0.95 LN The reactor shall be fitted with a temperature sensitive micro-switch in the centre coil (normally open) for connection to trip circuits in case of high operating temperatures. 1.14 Switchgear & Protection Incomer switchgear shall be TP&N breaker appropriate rating. Suitable contactor for each step shall be used and must be capable of capacitor switching duty at each step for short circuit protection. Busbars shall be suitably colour coded and must be mounted on appropriate insulator supports. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 47 Power cables used shall have superior mechanical, electrical and thermal properties, and shall have the capability to continuously operate at very high temperatures up to 125 deg.C. Internal wiring between main bus-bars, breaker, contactor and capacitors shall be made with 1100 V grade, PVC insulated, copper conductor cable of appropriate size, by using suitable copper crimping terminal ends etc. Suitable bus links for input supply cable termination shall be provided. 1.15 Control Circuit & General Protection The control circuit shall be duly protected by using suitable rating MCB. An emergency stop push button shall be provided to trip the entire system (22.5 mm dia., mushroom type, press to stop and turn to reset). Wiring of the control circuit shall be done by using 1.5 sq.mm, 1100 V grade, PVC insulated, multistranded copper control wire. Inspection terminal strip, number ferruling, labeling etc. shall be provided. 440 V caution board on the panel shall be provided. 1.16 Testing The capacitor bank shall be subject to tests as specified in relevant Indian Standards at the factory and the test certificates shall be furnished in quadruplicate. 1.17 Installation Capacitors banks shall be installed as per installation manual of supplier and shall conform to relevant Indian Standards. All interconnections in the control panel shall be checked before commissioning. Cable end boxes shall be sealed after cable connections to prevent absorption of moisture. 15 mm thick rubber matting of an approved make over a 100 mm high Timber platform shall be provided in front of the full length of the capacitor bank and control panel. 1.18 T esting And Commissioning i. Insulation resistance shall be tested with a 1000 volts megger between phases and phase to earth. ii. Residual voltage shall be measured after switching of the capacitors and the same shall not be more than 50 volts after one minute. iii. Each discharge resistor shall be tested for its working. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make C Lightning And Surge Voltage Protection 1.1 Scope E- 48 The work required under this section shall include all material, labour and auxiliaries required to furnish and install complete Surge Protection Devices at main LT Panel incoming feeders (Stage I / Class B) & Distribution Boards (Stage II / Class C) for the protection of Building electrical and Electronics system from the effect of Lightning discharges, line induced transient surge voltage or switching surges as per the details. 1.2 Codes & Standards The following standards & publications as referred in the various parts of this Specification shall apply. 1.3 IEC-61643-11, IEC-61643-12 IEC 60 364 – 5 – 5 53 IEC 62 305 - 4 Product Specifications 1.3.1 Surge Protector At Stage I / Class B (L T Panel Protector ) The Surge Protection Device (SPD) manufacturer shall offer a complete line of Surge Protection Devices to support the requirements for Main LT Panel Incoming feeders. The surge protector at this stage shall be provided to protect the downstream electrical and electronics against any lightning discharges surges that may enter into the system through Mains panel. The Protection unit shall be based on single arc spark gap technology and shall be able to withstand 10/350 microsecond surge currents associated with external lightning discharges. 1.3.2 Protection Network Configuration The work required under this section consists of furnishing, installing and connecting SPD device as specified and as asked for in BOQ. The SPD device shall be installed in a NETWORK configuration, consisting of one set of SPD panel device at the service entrance of switchboard. All SPD devices in this network configuration shall be of same manufacturer. All SPD devices shall be modular, mountable on 35 mm DIN rail. Unit status indicator shall be provided to indicate the status of complete Protection unit. Protection shall be manufactured for the specific type and voltage of the electrical Service and shall provide clamping for both normal (L-N) and common (N-G) mode operation. Protection shall be manufactured to withstand a maximum continuous operating voltage of not less than 115% of normal RMS Line voltage of 240 V. The Protection shall be provided with safety MCB’s to be connected in series between Line/s to neutral & neutral to earth as per the TNS configuration of wiring. It shall be testable on line for routine maintenance, module failure and in order to prevent catastrophic failure modes. Protection shall be a fail-safe type device, shall have a follow through current quenching capacity up to 25 KA r.m.s., shall have repeated surge capability state, shall be self restoring and be fully automatic in all mode of operation. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 49 Protection shall comply with IEC 61643 and shall be approved for the location in which they are listed. o o Protection shall have an operating temperature ranges from -20 C to 60 C. 1.3.3 Protection Criteria The maximum continuous operating voltage (Rated Voltage) for SPD devices connected to phaseneutral shall not be less than the values shown in table: Nominal Voltage Rating per phase Maximum Voltage (Vrms) (Vrms) 240 320 Continuous Operating Listing The surge protective device and associated hardware must comply with IEC 61643-11. The Protection voltage of the complete rail mount surge protective device shall be type test to the figures as indicated in table below, which must not exceed the values shown. Service Voltage / per phase Protection Voltage @ In (Nominal discharge current) / Protection Level 240 V < 2.5 k V (between Line to Neutral) 1.5 kV (between Neutral to Earth) Surge protective device application at Low Voltage AC main LT Panel incoming feeder surge impulse current withstanding capacity as shown in table below. Application Panel Location Max. Single Withstand Surge Current (of 10/350 μs Impulse) Service Entrance (Main LT Panel) 25 KA, 10/350μs (between Line to Neutral 100 KA, 10/350 (between neutral to Earth) Compliance to this specification must be provided in the form of a certificate from an independent testing laboratory. Response time of stage-I class –B arrester should not be < 100 ns. 1.3.4 Surge Protector At Stage II / Class C (Final Distribution Board Protector) The surge Protection manufacturer shall offer a complete line of surge Protection product to support the requirements for the Distribution Board. The surge protector at this stage shall be provided to protect the downstream electrical and electronics against any induced switching surges that may be passed on to the downstream electrical & electronic system. The Protection unit shall be based on Single High Capacity Metal Oxide Varistors (MOV), capable of handling 8/20 μs surges and shall be able to give an indication in the event module failure and Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 50 be pluggable to facilitate the in-service replacement without distributing the lines. One extra set of replacement module shall be furnished to the job site. Protection Network Configuration - The work required under this section consists of furnishing, installing and connecting SPD device as specified and as shown in the drawings. The SPD device shall be installed in a NETWORK configuration, consist of one set of SPD panel device at the service entrance of switchboard. All SPD devices in this network configuration shall be of same manufacturer. All SPD devices shall be modular, mountable on 35 mm DIN rail and be field replaceable without interruption of electrical distribution circuit. Unit status indicator shall be provided to indicate the status of complete Protection unit on the product as well as provision for remote indication must be provided. Protection shall be manufactured for the specific type and voltage of the electrical Service and shall provide clamping for both normal (L-N) and common (N-G) mode operation. Protection shall be manufactured to withstand a maximum continuous operating voltage of not less than 115% of normal RMS Line voltage of 240 VAC. The Protection shall be provided with internal safety fusing if required, to be connected in parallel between Line/s to neutral & neutral to earth as per the TNS configuration of wiring. It shall be testable on line for routine maintenance, module failure and in order to prevent catastrophic failure modes. Protection shall be a fail-safe type device, shall have no follow through current shall have repeated surge capability, shall be solid state, shall be self restoring and be fully automatic in all mode of operation. It shall have thermal disconnection and indication against overloading of the device. Protection shall comply with IEC 61643 standards. o o Protection shall have an operating temperature ranges from -20 C to + 60 C. Protection Criteria The maximum continuous operating voltage (Rated voltage) for SPD devices connected to phase-neutral shall not be less than the values as shown in table below: Nominal Voltage Rating per phase Maximum Voltage (Vrms) (Vrms) 120 150 240 320 350 440 480 600 Continuous Operating Listing The surge protective device and associated hardware must comply with IEC 61643-11. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 51 The Protection voltage of the complete rail mount surge protective device shall be type test to the figures as indicated in table below, which must not exceed the values shown. Service Voltage / per phase Protection Voltage @ In (Nominal discharge current) / Protection Level 240 V 1500 V Nominal Withstand Surge Current. Surge Protective device (including all fusing and over current protection) for application at sub-Distribution Panels shall have a Nominal surge current withstand capacity as shown in table below. The failure or operation of any fuse / over – current device during the test is not permissible. Application Panel Location Max. Single Withstand Surge Current Of 8/20 µs Impulse) Sub-Distribution Panel 10KA for 8 / 20 μs (between Line to Neutral) Final Distribution Board 25 KA for Earth) 10/350 μs (between Neutral to Compliance to this specification must be provided in the form of a certificate from an independent testing laboratory. Response time of Class C arrestor should not be <25 ns. - : Incoming ACB/MCCB/SFU -: Back up fuse / MPCB / MCB for Surge Arrester -: RYB and N Bus bar or looping after the incomer - : Earth Bus bar in the panel - : Surge Arrester to connect between Line and - : SPD to connect between Neutral and Earth. F4, F5, F6 R,Y,B and N PE SPD1,2,3 Neutral SPD 4 B F1 F2 F3 SPD 1 F4 F5 F6 SPD 3 Y SPD 2 R F1, F2, F3 Connection diagram for SPD for 3 phase 4 wire network SPD 4 N PE Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make F1, F2, F3 - : Incoming ACB/MCCB/SFU F4, F5, F6 -: Back up fuse / MPCB / MCB for Surge Arrester R, Y, B and N -: RYB and N Bus bar or looping after the incomer PE - : Earth Bus bar in the panel SPD1, 2, 3 - : Surge Arrester to connect between Line and Neutral SPD 4 - : SPD to connect between Neutral and Earth. 1.8 Shop E- 52 Drawings Prior to fabrication of the Panels the supplier / contractor shall submit for consultant’s approval the shop / vendor drawing consisting of G.A. drawing, sectional elevation, single line diagram, bill of material etc. and design calculations indicating type, size, short circuiting rating of all the electrical components used, busbar size, internal wiring size, Panels dimension, colour, mounting details etc. in 6 sets.. The contractor shall also submit manufacturer’s catalogues of the electrical components installed in the Panels along with the drawing. The following shall be furnished as part of the Tender: a) General arrangement showing plan, elevation and typical sectional views. b) Technical literature on the various equipments. c) The following shall be furnished after award of contract for Purchaser's approval : i. General arrangement showing plan, elevation and typical section views. ii. Foundation plan showing location of fixing channels, floor opening etc., iii. Schematic wiring drawings for each feeder. 1.8.1 DOCUMENTATION : 1.8.1.1 Vendor shall furnish drawings, data and manuals in six sets along with equipment supplied. - General arrangement drawing indicating accessories and dimensions. Foundation plan and loading. Termination arrangement with dimensions. Three phase wiring diagrams SLD’s and control schemes Terminal plans Bill of quantity for each panel. 1.8.1.2 Documents to be submitted after placement of order. 1.8.1..3 As per 2.1 above for comments and approval for manufacture. Schematic and sectional drawing. Final documents - As built drawings with RTP ( Reproducible Tracing Paper ). Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make - E- 53 Instruction and maintenance manual - Six copies. Test certificates - Six copies 1.9 Inspection At all reasonable times during production and prior to transport of the Panels to site, the supplier / contractor shall arrange and provide all the facilities at their plant for inspection. 1.10 Test Certificates Testing of Panels shall be carried out at factory and at site as specified in Indian standards in the presence of consultant. The test results shall be recorded on a prescribed form. The test certificate for the test carried out at factory and at site shall be submitted in duplicate to the consultant for approval. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 54 E8. Li ghti ng Fi xtur es & Accessor i es The light fixtures and fittings shall be assembled and installed in position complete and ready for service, in accordance with details, drawings, manufacturer's instructions and to the satisfaction of the Project Manager. Scope 1.1 Scope of work under this section shall include inspection at suppliers/manufacturer’s premises at site, receiving at site, safe storage, transportation from point of storage to point of erection, erection and commissioning of light fittings, fixtures and accessories including all necessary supports, brackets, down rods and painting etc as required. 1.2 Standards The lighting and their associated accessories such as lamps, reflectors, housings, ballasts etc., shall comply with the latest applicable standards, more specifically the following: General and safety requirements for Luminaires : Part-1 Tubular flourescent lamps - IS – 1913 (Part-1) Industrial lighting fittings with metal reflectors - IS - 1777 Decorative lighting outfits - IS - 5077 Bayonet lamp holders - IS - 1258 Bi-pin lamp holders for tubular fluorescent lamps Electronic Ballasts for fluorescent lamps – General & Safety requirement Electronic Ballasts for fluorescent lamps – Performance requirement - IS – 13021 (Part-2) Ballast for HP MV lamps - IS - 6616 Tubular Fluorescent lamps - IS - 2418 (Part-1 to 4) Luminaries – General requirement - IS – 10322 (Part-1) Luminaries – Constructional requirement Luminaries – Screw and Screwless termination Luminaries – Methods of Tests Particular requirement – General purpose Luminaries - IS–10322 (Part-5/Sec-1) Particular requirement – Recessed Luminaries - IS–10322 (Part-5/Sec-2) Particular requirement – Luminaries for Road and Consultant : JIT Engineering Services Consultant - - - IS - 3323 IS – 13021 (Part-1) IS – 10322 (Part-2) - - IS – 10322 (Part-3) IS – 10322 (Part-4) Sign of Bidder Electrical Works – Specifications and List of Make Street lighting E- 55 - IS–10322 (Part-5/Sec-3) Particular requirement – Portable General purpose Luminaries - Particular requirement – Flood Lighting - IS–0322 (Part-5/Sec-5) High pressure mercury vapour lamps - IS–9900 (Part-1) Tungsten filament general electric lamps 1.3 - IS–10322 (Part-5/Sec-4) IS - 418 Light Fittings-General Requirements: a) Fittings shall be designed for continuous trouble free operation under atmospheric conditions without reduction in lamp life or without deterioration of materials and internal wiring. Degree of protection of enclosure shall be IP-65 for outdoor fittings except bulkhead fitting. Bulkhead fitting shall be provided with IP-54 protection. b) Fittings shall be so designed as to facilitate easy maintenance including cleaning, replacement of lamps/ ballasts. c) All fittings shall be supplied complete with lamps. All mercury vapour and sodium vapour lamp fittings shall be complete with accessories like ballasts, power factor improvement capacitors, starters, etc. Outdoor type fittings shall be provided with weather proof junction boxes (IP-55) and IP-54 Control gear boxes. d) Each fitting shall have a terminal block suitable for loop-out connection by 1100 V PVC insulated copper conductor wires up to 4 sq.mm. the internal wiring should be completed by the manufacturer by means of standard copper wire and terminated on the terminal block. e) All hardware used in the fitting shall be suitably plated or anodized and passivated. f) Earthing: Each lighting fitting shall be provided with an earthing terminal. All metal or metal enclosed parts of the housing shall be bonded and connected to the earthing terminal so as to ensure satisfactory earthing continuity throughout the fixture. g) Painting/Finish: All surfaces of the fittings shall be thoroughly cleaned and degreased and the fittings shall be free from scale, rust, sharp-edges, and burns. h) The housing shall be powder coated/stove-enameled or anodized as required. The surface shall be scratch resistant and shall show no sign of cracking or flaking when bent through 90 deg. over 12 mm dia. mandrel. i) 1.4. Metal used in BODY of lighting fixtures shall be not less than 22 SWG or heavier if so required to comply with specification of standards. Sheet steel reflectors shall have a thickness of not less than 20 SWG. The metal parts of the fixtures shall be completely free from burns and tool marks. Solder shall not be used as mechanical fastening device on any part of the fixture. Light Fittings – Special Requirements Assymetric Distribution Flood Light Fittings Flood light fitting shall be provided with Housing made of die-cast aluminium with powder-coated finish for sturdiness and excellent corrosion resistance. The lamp compartment comprises of electrochemically brightened, high purity, pre-anodized aluminium reflector for long life and superior reflectivity. Outstanding glare suppression is secured by high grade asymmetric optics that achieve maximum intensity at around Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 56 60 deg with accurate beam control and uniform light distribution. There should be no direct light above the horizontal plane through the luminaire - As per the ICAO specs. Necessary supporting vertical grid calculations to be provided. Heat-resistant toughened front glass fixed to the housing with the help of specially designed stainless steel toggles with specially designed hinging mechanism for quick and easy lamp replacement, with no, sky Pollution. Hot dip Galvanized MS mounting bracket with calibrated disk for ease of mounting and aiming. Heat-resistant long life EPDM/Silicon gasket renders the luminaire dust tight and jet proof with ingress protection classification of IP 65. The twin lamp version offers switching facilities that permits tailoring to the user’s needs while allowing energy savings. Rugged all weather construction designed for easy aiming, simple cleaning and speedy maintenance Horizontal mounting for optimum light distribution is recommended with maximum rotational adjustment of 12 from the horizontal. Symmetric Distribution Flood Light Fittings Extremely high efficiency due to the ‘small’ lamp in combination with the patented coated reflector system: to provide up to 35 % higher energy (W/m2) than other solutions. Excellent uniform light distribution with an asymmetric beam (A-) or a bi-directional beam (-BD) to create outstanding illuminances on vertically oriented objects. The CDM-TD 150 W with colour temperature 4200 K, in combination with the colour rendering of 96, creates a daylight impression. Safety and minimum glare are assured, as the observer's eyes are shielded from the burner by a patented louver system. More sparkle, because the bright, compact burner is reflected on cars or glossy merchandise. Silicone gasket bonded to the housing renders the luminaire. Should be dustproof and jet proof to IP65. Galvanised white-coated steel mounting frame, for firm recessed fixing in cladding. Housing consists of an injection-moulded base plate, to which deep-drawn aluminium hood in connected. Thermally hardened glass, enclosed by an IP65 siliconerubber sealing gasket. Finishing in white (WH) Ballasts Specifications: Impregnated electromagnetic ballasts of copper – iron construction for use in combination with external ignitor with watt loss not more than 42 watts (400 watts) & not more than 21 watts (150 watts) and should with stand a maximum winding temperature of 130 Degree. The Power factor should be >0.85 with mains current not more than 2.15 A at stabilization. Ortho cyclic winding process for limited ballast coil volume and reduced weight with minimum ballast losses. Compact size reduces space requirement within the luminaire. Earthing-while-mounting facility. Ballast equipped with screw terminal blocks. Compliance with IEC 922 (safety), IEC 923 (performance) standards. Semi – parallel ignition system in combination with SN 58 ignitor ensures longer life for control gear components. Box Channel Type Industrial Fittings Box type slim line channel must be in screw less construction manufactured from M.S. CRCA sheet steel powder coated with MS CRCA cover, powder coated white. Light reflection surface in Box/Channel type fittings shall be in a POLYESTER PRECOATED STEEL having a reflection factor of not less than 80%. SCREWLESS DESIGN & CONSTRUCTION Light fixtures shall be preferred due to their ease of maintenance, especially for box/channel for box/channel type fixtures. Moisture Proof Industrial Fittings Surface mounted totally enclosed moisture proof fixtures must be in polycarbonate body and diffuser with transparent prismatic interior and smooth exterior and frosted end. Fixture must be completely sealed with polyerethane double gasket to achieve IP 65 protection. Fixture is complete with CRCA steel white powder coated / enamelled finish reflector. 18 W / 36 W Fluorescent And 36 W CFL Low Glare Light Fittings Recessed mounted, modular fluorescent lighting fixture made of CRCA Sheet steel powder coated (white) housing, electro chemically brightened and anodised reflector, three dimensional cross louvers with Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 57 2 concave contours, Fresnel top at louver saddle to increase efficiency. The luminance of <200 cd/M at 63 degree viewing angle in all directions so as to confirm Cat-2 classification of CIBSELG3 Highbay Industrial Fittings Industrial Highbay luminaries shall be provided with pressure die cast housing along with all accessories, orthocyclically woundopien construction ballast, and capacitor & semi parallel ignitor connected to terminal block and mounted on the gear plate. The gear shall have side entry for ease in maintenance. The spun aluminium reflector is suitable for narrows well as wide beam distribution. The luminaire will be suitable for metal halide lamp HPI BU + 250 W which has 25500 lumens and 2.5 min restrike time (when operate with son gear). 1.5 Accessories For Light Fittings Reflectors The reflectors shall be made of CRCA sheet steel/aluminium /Silvered glass/Chromium plated sheet copper as required. The thickness of reflectors shall be as per relevant standards. Reflectors made of steel shall have stove enamelled/ vitreous enamelled/epoxy coating finish. Aluminium used for reflectors shall be anodized/epoxy stove enamelled /mirror polished. The finish for the reflector shall be as specified. The reflectors shall be free from scratches / blisters and shall have a smooth and glossy surface having optimum light reflecting coefficient. Reflectors shall be readily removable from the housing for cleaning and maintenance without use of tools. 1.6 Lamps 1.6.1 Tld Lamp shall be environment friendly low pressure mercury discharge lamp with mercury content less than or equal to 5 mg. The lamp shall have minimum lumen maintenance of 85 and CRI of 85. The lamp must comply with ROSH (Restriction of Hazardous substances) and covered by WEEE. Lamp should be fully re-cyclable. The lamp should be low on maintenance with life of 40 K hours in case of electromagnetic ballast and 65 K hours in case of HF ballast up to 10% failure. The discharge glass shall be lead free. TLD Lamps shall be minimum tri-phosphor type and have bi-pin bases. Colour spectrum of light shall be equivalent to “PHILIPS colour 84 or colour 86 colour 82 or “OSRAM colour 21 or colour 11 or colour 41 (as required at site)”. The fluorescent Tubes (TLD) should have cool daylight colour designation. But Architects reserve the right to prescribe either Cool Daylight or Bright White or Incandescent Colour Designations for TLD. NO extra payment will be made over the quoted rate of bidder for this. The 36 W fluorescent tubes will have Nominal Luminous Flux of not less than 3350 lumens whether so mentioned in the Schedule of Quantities or not. T 5 – High efficiency eco-friendly lamps T-5 lamp shall be environment friendly low pressure mercury discharge lamp with mercury content less than or equal to 3 mg. lamp should have lowest CO2 emission compared to any other comparable light source (40% less than a TL-D standard lamp, 26% less than TL-D / 80). T-5 lamp shall be 100% lead free. T-5 lamp shall be designed for operation with electronic gear and well suited for dimming. Maximum o o lumen output to be reached at approx 35 C in free burning position. T-5 lamp can be ignited from -15 C to o + 50 C. Lamp should be fully recyclable and must comply with ROSH (Restriction of Hazardous substances) and shall be covered by WEEE. T-5 shall have 16 mm in diameter service life of TL-5 lamp should be 10% more than TL-D lamps. T-5 lamp shall have lumen efficacy of up to 104 Lux / W and shall have excellent colour rendering to En 12464 (Ra 80 to 89). Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 58 1.6.2 Compact fluorescent lamp shall have same luminous flux and power consumption as fluorescent tubes but less than half the length and more compact than U-shaped and circulator lamps. CFL shall be suitable for use with conventional control gear & standers and for HF electronic control gear. CFL lamp shall be non integral type of OSRAM / GE / PHILIPS/ Havells Sylvania only. 1.6.3 150 W CDM-TD Lamp Warm or cool white colour impression Colour rendering good to excellent > 96. Retrofit in double-ended luminaries for quartz metal halide lamps (MHN/W-TD), thereby allowing to reduce operating costs and improve colour quality Burning position horizontal +/-45° Initial Lumen Output not less than 13250 Lumens. Luminous efficacy should not be less than 84. 1.6.4 Lamp Specifications: 400W SON-T Sont Pia Plus 400w High pressure sodium vapour lamp with a specially designed integrated antenna to improve lumen output and luminous efficacy for the source. Initial lumen output should not be less than 56500 lumens Initial luminous efficacy should not be less than 130 lumen per watt The lumen maintenance at 5000 burning hours should be greater than 94% and at 10,000 burning hours should not be less than 90% The rated average life at 50% failure should not be less than 20,000 burning hours. 1.7 High Frequency Electronic Ballast High frequency electronic ballast shall be used with fluorescent / Compact Fluorescent Lamps wherever specified in the schedule of quantities. High frequency electronic ballast shall comply with the following: IEC 927, IEC 928 for ≤10% total harmonic distortion. EMI / RFI – Confirming to FCC / VDE Class A/B. Line Transient as per IEEE C62.41. Ballast Crest Factor C1.7%. No Stroboscopic Effect Constant Wattage / Light output between 240 V ± 10%. Circuit protection for surge current and inrush current. Short circuits, open lamp protection Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 59 PF > 70 for fluorescent / T5 lamp and CFL. Deactivated lamp protection Suitable for use with single and twin lamps RFI < 30 MHz Total Harmonic Distortion (THD) ≤10% Immunity to interference EN 61547 Safety EN 60928 / IEC 928 / IS 13021 (Part I) Performance Vibrations & Bump tests IEC 9001 Quality Standard Environmental Standard DC Operation EN 60924 Emergency Lighting Operation VDE 0108 EN 55015 EN 60929 / IEC 929 / IS 13021 (Part II) IEC 68-2-6 FC ISO 9001 ISO 14001 Total System consumption (lamps + ballast) for 1 x 36 W TLD, shall not exceed 40 W 1 x 28 W T-5, shall not exceed 32 W 1 x 35 W T-5, shall not exceed 40 W 1 x 14 W T-5, shall not exceed 16 W 1 x 18 W CFL, shall not exceed 20 W 1 x 36 W CFL, shall not exceed 40 W Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 60 E9. Earthing 1.1 Earthing The system shall be TNS with four wire supply system (R, Y, B, N and 2 Nos. E) brought from the main L T Panel. All the non-current carrying metal parts of electrical installation and all metal conduits trunking, cable sheaths, switchgear, distribution panels, light fittings and all other parts made of metal shall be bonded together and connected by means of specified earthing conductors to an efficient earthing system. All metal work such as pipe lines, ducts, cable trays, stair case railing etc shall be bonded to earth. All earthing shall be in conformity with IS: 3043 1987, and the basic system of earthing shall be TNS. 1.2 Earthing Conductors Earthing conductors shall be of copper / GI as mentioned in schedule of quantities and shall be protected against mechanical injury and corrosion. 1.3 Sizing Of Earthing Conductors The cross sectional area of earthing conductor shall not be smaller than half of the largest current carrying conductor subject to an upper limit of 80 Sq.mm. If the area of the largest current carrying conductor or bus bar exceeds 160 sq.mm then two or more earthing conductors shall be used in parallel, to provide at least half the cross sectional area of the current carrying conductor or bus bars. All fixtures, outlet boxes, junction boxes and power circuits up to 15 amps shall be earthed with PVC insulated copper wire. All 3 phase switches and distribution panels up to 60 amps rating shall be earthed with 2 Nos. distinct and independent 4 mm dia. copper / GI wires. All 3 phase switches and distribution panels upto 100 amps rating shall be earthed with 2 Nos. distinct and independent 6 mm dia. copper / GI wires. All switches, bus bar, ducts and distribution panels of rating 200 amps and above shall be earthed with minimum of 2 nos. separate and independent 25 mm x 3 mm copper / GI tape. 1.4 Connection Of Earthing Conductors Main earthing conductors shall be taken from the earth connections at the main L T panel to an earth electrode with which the connection is to be made. All joints in tapes shall be with four rivets and shall be brazed in case of copper and by welding bolting in case of GI, wires shall be connected with crimping lugs, all bolts shall have spring washers. Sub- mains earthing conductors shall run from the main distribution panel to the sub distribution panel. Final distribution panel earthing conductors shall run from sub-distribution panel. Circuit earthing conductor shall run from the exposed metal of equipment and shall be connected to any point on the main earthing conductor, or its distribution panel. Metal conduits, cable sheathing and armouring shall be earthed at the ends adjacent to distribution panel at which they originate, or otherwise at the commencement of the run by an earthing conductor in effective electrical contact with cable sheathing. Where equipment is connected by flexible cord, all exposed metal parts of the equipment shall be earthed by means of an earthing conductor enclosed with the current carrying conductors within the flexible cord. Switches, accessories, lighting fitting etc. which are rigidly secured in effective electrical contact with a run of metallic conduit shall not be considered as a part of the earthing conductor for earthing purposes, even though the run of metallic conduit is earthed. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 61 The plate/pipe electrode, as far as practicable, shall be buried below permanent moisture level but in any case not less than 2.5 M below finished ground level. The plate/pipe electrode shall be kept clear of the building foundation and in no case, it shall be nearer by less than 2 M from outer face of the respective building wall / column. The plate electrode shall be installed vertically and shall be surrounded with 150 mm. thick layers of Charcoal dust and Salt mixture. 19 mm. dia. G.I. pipes for watering shall run from top edge of the plate / pipe electrode to the mid level of block masonry chamber. Top of the pipe shall be provided with G.I. funnel and screen for watering the earth / ground through the pipe. The funnel with screen over the G.I. pipe for watering to the earth shall be housed in a block masonry chamber as shown in the drawing. The masonry chamber shall be provided with a Cast Iron hinged cover resting over the Cast Iron frame which shall be embedded in the block masonry. Construction of the earthing station shall in general be as shown in the drawing and shall conform to the requirement on earth electrodes mentioned in the latest edition of Indian Standard IS: 3043, Code of Practice for Earthing Installation. The earth conductors (Strips / Wires copper / hot dip G.I.) inside the building shall properly be clamped / supported on the wall with Galvanised Iron clamps and Mild Steel Zinc Passivated screws / bolts. The conductors outside the building shall be laid at least 600 mm. below the finished ground level. The earth conductors shall either terminate on earthing socket provided on the equipment or shall be fastened to the foundation bolt and / or on frames of the equipment. The earthing connection to equipment body shall be done after removing paint and other oily substances from the body and then properly be finished. Over lapping of earth conductors during straight through in joints, where required, shall be of minimum 75mm. long. The earth conductors shall be in one length between the earthing grid and the equipment to be earthed. Earth Leads And Connections Earth lead shall be bare copper or Galvanised steel as specified with sizes shown on drawings. Copper lead shall have a phosphor content of not over 0.15 %. G.I strips buried in the ground shall be protected with bitumen and hessian wrap or polythene faced hessian and bitumen coating. At road crossing necessary Hume pipes shall be laid. Earth lead run on surface of wall or ceiling shall be fixed on saddles so that strip is at least 8 mm away from the wall surface. The complete earthing system shall be mechanically and electrically bonded to provide an independent return path to the earth source. 1.5 Prohibited Connections Neutral conductor, sprinkler pipes, or pipes conveying gas, water or inflammable liquid, structural steel work, metallic enclosures, metallic conduits and lightning protection system conductors shall not be used as a means of earthing an installation or even as a link in an earthing system. The electrical resistance measured between earth connection at the main L T panel and any other point on the Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 62 completed installation shall be low enough to permit the passage of current necessary to operate or circuit breakers, and shall not exceed 1 ohm. All switches carrying medium voltage shall be connected with earth by two separate and distinct connections. The earthling conductors inside the building wherever exposed shall be properly protected from mechanical injury by running the same in G I pipe of adequate size. The overlapping in strips at joints where required shall be minimum 75 mm. The joints shall be riveted and brazed in case of copper and by welding / bolting in case of GI in an approved manner. Sweated lugs of adequate capacity and size shall be used for termination of all conductor wires above 6 sq.mm size. Lugs shall be bolted to the equipment body to be earthed after the metal body is cleaned of paint and other oily substances and properly tinned. Equipotential bonding of all metallic structures shall be done. 1.6. Earthing The following must always be ensured in earthing system. All earths must be interconnected at the earth pits. This includes generator neutrals, transformer neutrals, transformer body, lightning protection system earths, UPS earths etc. Extraneous conductive parts such as gas pipes, other service pipes and ducting risers and pipes of fire protection equipment and exposed metallic parts of the building structure. The Contractor shall get the soil resistivity test done at his own cost of the area where earthing pits are to be located before starting the installation. 1.8 Resistance To Earth The resistance of earthing system shall not exceed 1 ohm. 1.9 Specification For Hot Dip Galvanizing Process For Mild Steel Used For Earthing For Electrical Installation General Requirements I. Quality Of Zinc Zinc to be used shall conform to minimum Zn 98 grade as per requirement of IS: 209-1992. Ii. Coating Requirement Minimum weight of zinc coating for mild steel flats with thickness up to 6 mm in accordance with IS:67451972 shall be 400 g/sqm. The weight of coating expressed in grams per square metre shall be calculated by dividing the total weight of Zinc by total area (both sides) of the coated surface. The Zinc coating shall be uniform, smooth and free from imperfections as flux, ash and dross inclusions, bare patches black spots, pimples, lumpiness, runs, rust stains bulky white deposits, blisters. Mild steel flats / wires shall undergo a process of degreasing pickling in acid, cold rinsing and then galvanizing. Jointing of earthing tape shall be by welding. All joints and cut ends shall be properly painted with aluminium paint. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 63 1.10 Chemical Earthing System – specification Earthing system should offer a resistance of less than 2 ohms throughout the year. In places where Soil resistivity is more, total length of the earthing rod has to be increased by adding 1m length rods (one over the other) to achieve low and stable resistance value. In rocky places ,multiple earth rods have to be installed and inter-connected to get the required value. Solid Copper coated rods are recommended as earth electrode than a pipe due to the fact that solid rods have much longer life and can be easily driven by electric/hydraulic hammers. Copper has much longer life than all other materials as explained in IS 3043. Deep driven rods provide more stable and less Earth Resistance. Doubling the length of the rod will reduce earth resistance up to 40 %, whereas doubling the diameter will reduce the resistance by only 10 %, but may increase the cost by 4 times.Lower earth resistance can also be achieved by increasing the number of earth rods. E.g. 40 % reduction in earth resistance is possible if the rods are increased from 1 to 2. The minimum spacing between earth pits should be equal to TWICE the length of the rod. Increasing the spacing between earth pits also reduces the earth resistance significantly. Need and importance of Earthing: Human and Personnel safety. Equipment protection. Provides low impedance path for fault currents. To ensure good quality power. Protection against lightning and transient currents, noise reductions, Limitation of EMI. References: IEC 60364: Low Voltage Electrical Installations-Part 5-54: Selection & Erection of Electrical Earthing arrangement & protective conductors. equipment- IEC 62561: Lightning Protection system Components. Part 1 to 7. IEC 62305: Protection Against Lightning –Part 3: Protection of structures & life Hazards IS 2309: Code of practice for protection of buildings & allied structures from lightning IS 3043: Code of practice for earthing. Components of earthing system: Earth electrode Connectors and fasteners Inspection Chamber (Earth Pit) Earth enhancement material Connecting cable/tape/strip with accessories. Earth Electrode: Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 64 Copper coated Solid steel Rods shall be made of high tensile low carbon steel rod, molecularly bonded with 99.9% electrolytic copper with minimum coating thickness of 250 microns as per IEC 62561 part -2: Requirement for Conductor & Earth Electrodes. The length of the earth rod shall be 1 meter so that driving into the ground is easier (scaffolding is not necessary). For dry areas, length of the rods can go up to several meters by driving the rods one over the other. Earth rods should be of diameter 20 mm. These rods should have facility to couple with hammer inserts so that they could be driven easily with an electric/hydraulic hammer. Additional rods should be added without external couplers. The earth rods should have peg & bore arrangement so that additional rods are added without external couplers. Interconnecting Strips / Earthing Conductor: Copper coated steel strips / tapes should be used to interconnect different earthing rods as well as horizontal earthing (Ring earthing). These strips should have a coating thickness of minimum 70 microns. Couplers / Connecting clamps: Connectors/fasteners for connecting Electrode with Earthing conductor/strip should be of Stainless Steel as it is compatible with all other materials viz Copper, GI etc. Fasteners should be made of Stainless steel Inspection Chamber : Should have an inner dimension of 250 mmX 250 mm X 250 mm made of FRP material. Flush Mounted, removable cover of the earth pit should be able to withstand moderate loads. The area inside the inspection chamber should be such that, the UNIVERSAL CLAMP/EBB/Bus bars not too deep inside the inspection chamber or projecting out of inspection chamber. The chamber should have facility for marking earth resistance and latest testing date by paint at the cover and previous recorded values inside the cover. Earth Enhancement material: This is a conductive mineral compound to provide low resistance to the earth termination system. Earth enhancing compound should contain minerals which in normal use is reliable and without creating any hazards to persons and the surroundings. The material shall be chemically inert to sub soil and shall not pollute the environment. It shall provide a stable environment in terms of physical and chemical properties and exhibit low resistivity. It shall not be corrosive to the earth electrode itself. The material should have a resistivity less than 50 Ohm meter Installation: Dig a pit of 1m* 1m * 0.5m depth. At the center of the pit, Earth rod of 1 m has to be hammered electrically or hydraulically. The number of Earth rods can be added one over the other to get the required length. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 65 Fill the dug up area with Earth enhancing compound mixed with water & soil to get slurry form in such a way that the earth inspection pit is in flush with the earth surface. Connect the connectors with fasteners & connect the down conductors. Close the lid of earth inspection pit. Inspection & maintenance: Maintenance of the earthing system has to be done at least once in 6 months, preferably before the monsoon period and a record should be maintained to verify earthing system conductors and components, electrical continuity, earth resistance value, re-fastening of components viz-nuts, bolts etc. 1.11 Test The entire earthing installation shall be tested as per requirements of Indian Standard Specification IS: 3043. The following earth resistance values shall be measured with an approved earth megger and recorded. 1) Each earthing station 2) earthing system as a whole 3) Earth continuity conductors 4) Earth conductor resistance for each earthed equipment shall be measured which shall not exceed 5 ohm in each case. Measurements of earth resistance shall be carried out before earth connections are made between the earth and the object to be earthed. All tests shall be carried out in presence of the client’s representative. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make Consultant : JIT Engineering Services Consultant E- 66 Sign of Bidder Electrical Works – Specifications and List of Make E10. E- 67 Street Lighting Poles: The street light poles shall be fabricated from heavy duty cold-rolled steel tubes conforming to IS: 1239 and hot dip galvanized or painted as specified. The street light pole shall be fabricated as per the details and dimensions shown in the drawing. The street light poles shall have base plate, a Junction Box, and necessary fixture mounting bracket at top. The Junction box shall provide easy access to a multiway connector and MCB, to be mounted inside the pole. The access shall be specially fabricated with adequate reinforcement and weather protection gasket to prevent ingress of moisture and vandal proofed. Poles shall have large diameter entries for incoming and outgoing cables and two earth studs & Spiral earthing. The poles fabricated shall conform to the drawings and where such drawing is not available, the contractor shall make such drawing and have it approved before fabricated. The pole shall house a multi way Wohner type terminal block and MCB as shown on the drawings. Poles shall have concrete coping. 1.00 SCOPE: The scope of this specification covers the manufacture, transport, installation, testing and commissioning of the Raising and Lowering type of High mast Towers, Poles, including the Civil Foundation Works with all items required for the safe and efficient operation and maintenance of the lighting system, including the high mast, whether explicitly stated in the following pages or not, shall be included by the Contractor. 2.00 PRE-QUALIFICATION The Supplier shall have own quality systems confirming to ISO 9001 for carrying out the job. Poles & High mast manufacturing unit shall be ISO 14001 & ISO 18001 certified. They shall also have enough experience in supply and installation of high masts & Poles in the country and must have installed minimum of 100 similar masts & 1000 nos. of similar poles till date. Proof for the experience shall be produced before issue of tender documents to the party. The bidder shall produce proof of the following before issue of the tender documents to them. a) b) c) d) e) Contractor license for the state of Gujarat. ISO 9001 certificate for High mast system and Poles. ISO 14001 certificate for the manufacturing plant. ISO 18001 certificate for the manufacturing plant. Proof of completion of similar jobs in the port sector with single job value more than 2 crores. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 68 3.00 APPLICABLE STANDARDS: The following shall be the Reference Standards for the loading of the High mast: Code No. Title a). I.S.875 (Part III) 1987. Code and practice for design loads for Structures. b). BSEN 10025. Grades of MS. Plates. c). BS.ISO 1461. Galvanizing. e). TR. No.7 1996 of ILE, UK. Specification for Mast and foundation. 3.1 LIGHTING POLES : The street light poles shall be fabricated from heavy duty cold-rolled steel tubes conforming to IS:1239 and hot dip galvanized or painted as specified. The street light pole shall be fabricated as per the details and dimensions shown in the drawing. The street light poles shall have base plate, a Junction Box, and necessary fixture mounting bracket at top. The Junction box shall provide easy access to a multiway connector and MCB, to be mounted inside the pole. The access shall be specially fabricated with adequate reinforcement and weather protection gasket to prevent ingress of moisture and vandal proofed. Poles shall have large diameter entries for incoming and outgoing cables and two earth studs & Spiral earthing. The poles fabricated shall conform to the drawings and where such drawing is not available, the contractor shall make such drawing and have it approved before fabricated. The pole shall house a multi way Wohner type terminal block and MCB as shown on the drawings. Poles shall have concrete coping. 3.1.1 CONICAL POLES Design The Conical Poles shall be designed to withstand the maximum wind speed as IS 875. The top loading i.e. area and the weight of fixtures are to be considered to calculate maximum deflection of the pole and the same shall meet the requirement of BSEN 40-3- 1:2000, pr EN-40-3-3. Pole Shaft The pole shaft shall have circular cross section and shall be continuously tapered with single longitudinal welding. There shall not be any circumferential welding. The welding of pole shaft shall be done by Submerged Arc Welding (SAW) process. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 69 All conical pole shafts shall be provided with the rigid flange plate of suitable thickness with provision for fixing 4 foundation bolts. This base plate shall be fillet welded to the pole shaft at two locations i.e. from inside and outside. The welding shall be done as per qualified MMAW process approved by Third Party Inspection agency. Door opening The conical poles shall have door of approximate 500 mm length at the elevation of 500 mm from the Base plate. The door shall be vandal resistance and shall be weather proof to ensure safety of inside connections. The door shall be flush with the exterior surface and shall have suitable locking arrangement. There shall also be suitable arrangement for the purpose of earthing. The pole shall be adequately strengthened at the location of the door to compensate for the loss in section. Material Conical Poles shaft : Conforming to grade S355JO. Base Plate : Fe 410 conforming to IS 226 / IS 2062 Foundation Bolts : EN 8 Grade Welding The welding shall be carried out confirming to approved procedures duly qualified by third party inspection agency. The welders shall also be qualified for welding the conical shafts. Pole sections The conical poles shall be in single section up to 12 mtr. There shall not be any circumferential weld joint. Bracket Arm The bracket will have a sleeve as cap of suitable diameter fitted with pinching bolts. The length of bracket shall be as per illumination design. Galvanization The poles shall be hot dip galvanised as per IS 2629 / IS 2633 / IS 4759 standards with average coating thickness of 70 micron. The galvanizing shall be done in single dipping. Fixing Type The conical poles shall be bolted on a pre-cast foundation with a set of four foundation bolts for greater rigidity. Top Mountings The galvanized mounting bracket shall be supplied along with the conical poles for installation of the luminaries Pole Testing Facility The manufacturing unit shall have in-house pole testing facility for validation of structural design data. The pole testing facility shall conform to BS EN 40-3-2-2000 part 3-2. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 3.1.2 E- 70 Octagonal Poles Design The Octagonal Poles shall be designed to withstand the maximum wind speed of 160 km / hr. The top loading i.e. the weight and the area of top luminaries are to be considered to calculate maximum deflection of the pole and the same shall meet the requirement of BS: 5649 Part VI 1982. Pole Shaft The pole shaft shall have octagonal cross section and shall be continuously tapered with single longitudinal welding. There shall not be any circumferential welding. The welding of pole shaft shall be done by Submerged Arc Welding (SAW) process. All octagonal pole shafts shall be provided with the rigid flange plate of suitable thickness with provision for fixing 4 foundation bolts. This base plate shall be fillet welded to the pole shaft at two locations i.e. from inside and outside. The welding shall be done as per qualified MMAW process approved by Third Party Inspection agency. Door opening The octagonal Poles shall have door of minimum size of 250 mm X 65 mm at the elevation of 500 mm from the Base plate. The door shall be vandal resistance and shall be dust proof to ensure safety of inside connections. The door shall be flush with the exterior surface and shall have suitable locking arrangement. There shall also be suitable arrangement for the purpose of earthing. The pole shall be adequately strengthened at the location of the door to compensate for the loss in section. Material Octagonal Poles : Conforming to St 35 grade. Base Plate : Fe 410 conforming to IS 226 / IS 2062 Foundation Bolts : 6.8 Gr. As per IS 1367 Welding The welding shall be carried out confirming to approved procedures duly qualified by third party inspection agency. The welders shall also be qualified for welding the octagonal shafts. Pole sections The Octagonal Poles up to the length of 11.5 meters shall be in single piece with single longitudinal welding joint. There shall not be any circumferential weld joint. However, the pole with length of 12 meters and above shall be of 2 sections with telescopic fitment with minimum overlap of 1.5 times the diameter. Galvanization The poles shall be hot dip galvanized as per IS 2629 / IS 2633 / IS 4759 standards with average coating thickness of 65 micron. The galvanizing shall be done in single dipping. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 71 Fixing Type The Octagonal Poles shall be bolted on a pre-cast foundation with a set of four foundation bolts for greater rigidity. Top Mountings The galvanized double / single arm shall be supplied along with the Octagonal Poles for installation of the luminaries. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E11. 1.1 E- 72 Te l e p h o n e & D a t a D i s t r i b u t i o n Scope This document defines the cabling system and subsystem components to include cable, termination hardware, supporting hardware, and miscellany required to furnish, and to install a complete cabling infrastructure supporting voice and video. The intent of this section is to provide pertinent information to allow the vendor to bid the labour, supervision, tooling, materials, and miscellaneous mounting hardware and consumables to install a complete system. However, it is the responsibility of the vendor to propose any, and, all items required for a complete system whether or not it is identified in the specification, drawings and bill of materials attached to this specification. 1.2 Applicable Documents: The cabling system described in this specification is derived in part from the recommendations made in industry standard documents. The list of documents below (or the latest revisions) has bearing on the desired cabling infrastructure are incorporated into this specification by reference: 1) This Technical Specification and Associated Drawings 2) ANSI/TIA/EIA 568-B Commercial Building Telecommunications Cabling Standard – March 2001 3) ANSI/EIA/TIA-569-A Commercial Building Standard for Telecommunications Pathways and Spaces - February, 1998 4) ANSI/EIA/TIA-606 Administration Standard for the Telecommunications Infrastructure of Commercial Buildings - February, 1993 5) ANSI/TIA/EIA-607 Commercial Building Telecommunications - August, 1994 2.0 Grounding and Bonding Requirements for Conduits: Conduits shall be as given below: Indoor: medium gauge Rigid PVC conduit. The conduit shall generally be as specified under section `CONDUIT WIRING'. 3.0 Cables And Wires: 3.1. The type of cables and the services shall be as follows: Indoor Multi pair, PVC insulated sheathed armoured and sheathed. Inside Twin core PVC insulated with conduit twisted cores. 3.2. All multi core cables and wires shall be of tinned copper conductor of not less than 0.5 mm dia. and shall be colour coded twisted pairs with rip cord. 3.3. The conductor resistance shall be less than 150 ohms per KM and the insulation resistance between the conductor's not less than 50 mega ohms and the nominal capacitance of about 0.1 micro farad per kilometre. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 73 3.4. Cables lay underground or locations subject to dampness and flooding shall be filled with polyethylene compound and shall have sufficient protection against moisture and water ingress. 3.5. All armouring shall be of galvanized steel wires and protected against corrosion by an outer sheath of PVC in the case of indoor cables and polyethylene in the case of outdoor cables. Outer sheathing must be fire retarding and anti-termite. 3.6. All unarmoured single core cables and inner sheath of armored cables shall be provided with rip cord. 3.7. All single pair cables for final extension to the telephone outlet box shall be unarmoured tinned copper conductors of not less than 0.6 mm. diameter and shall be drawn in conduits. All telephone outlets shall consist of 2 A 2 pair polythene connector in G.I box with 6 mm perspex cover with bevelled edges and chromium plated brass hardware. 4.0 Tag Blocks 4.1. The telephone tag blocks shall be suitable for the multi core telephone cables and shall have two terminal blocks, cross connect type. All incoming and outgoing cables shall be terminated on separate terminal blocks and termination shall be silver soldered. The cross connecting jumpers shall be insulated wires of same diameter and screw connected. 4.2. The tag blocks shall be mounted inside fabricated sheet steel boxes with removable hinged covers and shall be fully accessible. The enclosure shall be painted with 2 coats of red oxide and stove enamelled. 5.0 Installation 5.1. The installation of conduits shall generally be as specified under section `CONDUIT WIRING'. 5.2. All cables shall be on cable racks and neatly stitched together. 5.3. The connection at the tag blocks shall be silver soldered so as to achieve minimum contact resistance. 5.4. The final branch connections with single pair cables in conduits and the maximum number of cables in each conduit shall be as follows: Conduit diameter Max. No. of cables inch mm. 3/4" 20 2 Nos. single pair 1" 25 6 Nos. single pair 1¼" 32 12 Nos. single pair 1½" 40 18 Nos. single pair Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 6.0 E- 74 Mode Of Measurement 6.1. The main telephone cables shall include supply and laying of multi pair cables on ceiling/wall/on cable trays/racks including all supports and shall be measured and paid on running length basis. Cable trays/racks shall be paid for separately. 6.2. The multi pair tag blocks shall consist of two telephone connector's strips, jumpered interconnections silver soldered enclosure etc. and shall be measured and paid as one unit. 6.3. The conduit wiring for telephone shall include single pair 0.6 diameter cable in heavy duty rigid, PVC conduits and shall include junction boxes, pull boxes, 2 pair 2 A connector in GI box, Perspex cover etc. and shall from one point. 7.0 Cabling For Tv System 7.1. The Co-axial cable shall be of wideband type with operation capability up to 500 MHz 7.2. The ageing resistance of the co-axial cable shall comply with DIN 47252, Part 2, i.e. max. 5% increase in attenuation at 200 MHz measured by artificial ageing (14 days at 80 deg. C) 7.3. Cables shall meet or exceed the following specifications. Construction RG-6 MATV Type RG-11 MATV Type a Centre Conductor 18 AWG tinned copper 14 AWG tinned copper b. Dielectric Foam Polyethylene Foam Polyethylene Nom. dia. 0.180 Nom. dia. 0.280 Foil - 0.003 AI. Tape Foil - 0.003 AI. Tape Braid - 34 AWG 4 end Braid - 34 AWG 6 end AL. 60% coverage dia. 0.212 AL.60%coverage dia. 0.314. Black PVC flame-retardant Black PVC flame retardant dia. dia. over jacket 0.272 + overjacket0.405+0.010 0.008 Min. spot 0.023 Min. spot 0.032. c. d. Shield Jacket Electrical Properties Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make a. Dielectric Strength E- 75 Conductor to shield Conductor to shield 2000 VDC 1500 VDC 16.2 PF / FT. Nom b. Capacitance 16.2 PF / FT, Nom c. Impedance 75.0 + 3.0 ohms d. Attenuation DB/100 ft. e. 75.0 + 3.0 ohms. DB/100 ft. 0.65 DB @ 5 MHZ 0.35 DB @ 0.76 DB @ 10 MHZ 0.96 DB @ 20 MHZ 1.28 DB @ 100 MHZ 1.98 DB @ 100 MHZ 1.78 DB @ 200 MHZ 4.21 DB @ 450 MHZ 2.20 DB @ 300 MHZ 4.80 DB @ 550 MHZ 6.49 DB @ 1000 MHZ 4.30 DB @ 0.94 DB @ 2.75 DB @ 5 MHZ 50 MHZ 450 MHZ 1000 MHZ Velocity of Propagation 82.0% Nom 82.0% Nom f. DCR 35.47 ohms / 1000 ft. 14.29 ohms / 10000 ft. g. SRL 30 DB (10 MHz to 300 MHz) 20 DB (5 to 450 MHz) 7.4. DIRECTIONAL COUPLERS These shall be of Ultra Wideband type and of hybrid circuit design. These shall have a near flat frequency response over the entire operating range. These shall have aluminium cast housing for high frequency radiation resistance. These shall have ‘F’ sockets for all input, output and branch ports. The Tapoffs shall be available in one way, two way and four way configurations. The splitters shall be available in two way, three way and four way configurations. The Tapoffs shall be available in different tap values ranging from 11 dB, 15 dB, 20 dB, 25 dB and 30 dB. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 76 These shall meet or exceed the following specifications Tap off Splitters a. Tap Loss 11-30 dB b. Through Loss 0.5-4 dB 4..0 - 8.0 dB c. Isolation > 22 dB > 22 dB d. Screening factor > 50 dB > 50 db Consultant : JIT Engineering Services Consultant -- Sign of Bidder Electrical Works – Specifications and List of Make E12. HT GOD& HT Work 12.1 11 Kv Switchyard 1.1 E- 77 Two Pole Structure The scope of work includes fabrication, supply, erection, painting as per the drawing and IS, and getting the two pole as well as four pole structure approved from I.M & E department. The pole structure comprising of following items. All M.S. elements of channels, angles and flat shall be painted with two coats of primer and further painted with two coats of Aluminium paint. All nut & bolts, washer etc. used shall be hot dip galvanized. 1.1.1. Vertical pole of minimum ISMB - 175 (175 mm x 90 mm) size of approximately 9.0 / 10.0 mtr. length as indicated in the drawing, with 400 x 400 x 8 mm size base plate welded to one end of both the joists. 1.1.2. Cross member of minimum ISMC - 100 (100 mm x 50 mm) size channels approximately 3.5 mtr. each Length wherever required as indicated in the drawing. 1.1.3. Cross bracing angle of minimum ISA - 50 (50 mm x 50 mm x 6 mm) size of 4.5 mtr. each Length wherever required as indicated in the drawing. 1.1.4. Side clamps, stay clamps, cleats, patties, etc. Fabricated from minimum 50 mm x 6 mm size M.S flats as per actual requirement. 1.1.5. All nuts, bolts, washers etc. shall be of minimum 15 mm size. 1.1.6. Erection of poles and fixing of all structural members as per drawing and instruction of Site engineer. The structure shall be erected in plumb, line level, properly facing the incoming and outgoing lines. Cross member shall be firmly tightened. 1.1.7. All members shall be fabricated to suit the mounting / fixing of GOD, L.A, DOF, DISC/PIN/POST insulators, cable end termination kit / box etc. as per the drawing. 1.1.8. All necessary hardware, nut-bolts, extra members, sundry items are included in the scope of work. 1.1.9. All M.S parts shall be painted with primer and aluminium paint. 1.1.10. Earthing terminal shall be provided by welding 12 mm size bolt / cleat of 50 x 6 mm size M.S flat shall be fixed to each joist with a hole of 15 mm size and cadmium coated nuts, bolts, washers shall be provided as earthing terminals. Fixing or joining of any members is allowed by nut and bolt only welding is strictly not allowed. 1.1.11. Suitable M.S. flat supports and cleats shall be fixed to ISMB poles for supporting / fixing the earthing protection strip in the manner approved by the Client. 1.1.12. All drawing shall be prepared and submitted to Industry Mines & energy Dept. for approval. Obtain the approval from I.M. & E. Dept. 1.1.13. Vitreous enamelled caution boards or any other requirements shall be provided. 1.1.14. C.T.P.T. mounting channels, clamps, bracing angles, nut-bolts, hardware, etc. shall be supplied and erected. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 1.2 E- 78 Air Break Sw itch The air break switch should be constructed as per IS: 9920 / 1985. are provided with test certificate. The A.B. switch should be triple pole type with movable centre pole. All the poles should be opened / closed simultaneously by a lockable operating mechanism. The porcelain insulator shall be sound free from defects, thoroughly vitrified and smoothly glassed. Insulators shall have compressing type glassed with a good lustre and of uniform brown color. The air break switch should be provided with 1 year guarantee and the test report. The A.B. switch should be manually operated and shall be able to: Carry rated current without excessive temperature rise. Withstand the short circuit forces developed during fault. Carry the inrush current of transformer. Interrupt small inductive / capacitive current. The contacts shall be of silver faced copper ensuring sufficient contact pressure. The male & female contacts should be of self aligning type to ensure trouble free operation during opening and closing. Mild steel arcing horn capable of breaking the magnetizing current shall be provided. 1.3 Drop Out Fuse The D.O. Fuse assembly should be suitable for 33 KV supply and in accordance with IS 9385 / 1985 and provided with a test certificate The assembly shall be mounted on double pole structure complete with 3 fuse elements of required ampere rating. The fuse link shall consist of iron channel base, stack insulator per phase, fuse carrier bakelite tube, non-ferrous metal parts and spring loaded phosphor-bronze contacts. The insulator shall comply with impulse voltage test in accordance with IS 3106. 1.4 Lightning Arrestor 1.4.1 Type And Rating: Lightning arrestor shall be station class, heavy duty, and non-linear resistance type with rating as 33 KV. The arrestor shall have adequate thermal discharge capacity for severe switching surges, long duration surges and multiple strokes. 1.4.2 Constructional Features The arrestor shall be single pole and hermetically sealed off. It shall be of robust construction with excellent electrical and mechanical characteristics. Insulators must be non-hygroscopic and shall be wet process porcelain, brown glazed and free from imperfection. All metal parts and hardware shall be hot dip galvanized. Creepage distance shall correspond to heavily polluted atmosphere. Grading ring if required shall be provided to maintain voltage gradient within permissible limit. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 79 The arrestor shall be provided with pressure relief device if applicable to prevent shattering of approach in case excessive gas pressure builds up. 1.4.3 Accessories Lightning arrestor shall be furnished complete with insulating base, surge counter and anchoring hardware for mounting on steel structure. A surge counter shall be mounted at a convenient height for reading counter Terminals shall be such as to permit connections with minimum bends. A leakage current detector shall be furnished with the counter as an integrate part. This is for monitoring the leakage to indicate any possible breakdown. A suitable sized bypass shunt along with necessary terminals shall be furnished for bypassing the discharge counter if required. 1.4.4 Terminals All connection terminals shall be of corrosion resistant material and shall be provided with complete connection hardware. High voltage line terminal connector suitable for ACSR conductor. 1.5 Related Civil Work Foundation require for two pole structure in switch yard area shall be carried out by vendor with respective civil material as required to complete the job successfully as mentioned in our drawing. 12.2 H. T. VCB 1.1 VCB Scope Manufacturing, testing and supplying of integrated cubicle type metal clad, form 3 a, floor mounted and draw out type free standing, front operated indoor type 11 KV switchgear as per specifications given below: System The switchgear enclosure shall conform to degree of protection IP 4 X. The switchgear shall be made from MS sheet steel 2 mm thick (CRGO) and shall be folded and braced as necessary to provide a rigid support for all components. The switchgear assembly shall form a continuous dead front line up of free standing vertical cubicles. Each cubicle shall have a lockable front hinged door and a removable bolted back cover. All covers and doors shall be provided with neoprene gaskets. Suitable arrangement for lifting of each cubicle shall be provided. Design and construction of the switchgear shall be such as to permit extension at either end. Vacuum Circuit breaker shall be provided with surge arresting device for protection against lightning and switching over voltage. Two separate and distinct connections to earth shall be provided for each surge arrestor. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 1.1.2 E- 80 Breaker Compartment Vacuum Circuit Breaker shall be mounted in draw out truck with front plate which covers the cubicle when the breaker is in service position. This front plate shall be provided with view glass to facilitate observation of mechanical ON/OFF indication of Circuit breaker, spring charged / discharged indication and operation counter. Necessary orifice shall be provided for manual charging of the springs. ON/OFF push button for opening and closing of the circuit breaker shall also be provided. All draw out circuit breaker trucks/trolley of the same rating for all outgoing breakers shall be identically wired / equipped for complete interchange ability at site. `Service', `Test', `Draw Out' positions of the draw out carriage of the switchboard shall be provided. Automatic safety shutters shall be provided to ensure the inaccessibility of all live parts after the breaker is drawn out. Dummy panels required for rear extensions for cable terminations or to mount the components shall be included in the offer and details of each type of such panels shall be furnished along with offer. 1.1.3 Bus Bar Compartment Bus bars of rectangular cross section of copper conductor supported by cast epoxy insulator to withstand full short circuit currents up to 18.4 KA for one second for 11 KV systems shall be provided at the rear. Bus bar chamber shall be provided with inter panel barriers with epoxy cast seal off bushings. 1.1.4 CT And Cable Compartments At the rear of the panel sufficient space shall be available to accommodate three numbers epoxy CT’s of double core and two numbers three core cable termination. The cable entry shall be from the top / bottom. 1.1.5 Separate Compartments Circuit breakers, instrument transformer, bus bars, cable etc shall be housed in a district different compartments as required for form 3 a, compartmentalization. All relays, switches, lamps, etc. comprising the control, indication and protective devices shall be housed in a separate compartment on the front of the cubicle. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 1.1.6 E- 81 Technical Particulars Of Vcb Circuit Breaker S.NO. DESCRIPTION 6.6 KV 11 KV 22 KV 33 KV A Rated Current 400 A 400 A 630 A 630 A B Rated Voltage 7.2 KV 12 KV 24 KV 36 KV C Rated Frequency 50Hz 50 Hz 50Hz 50Hz D Rated Short Circuit breaking Current 18.4 KA for 1 sec. 18.4 KA for 1 sec. 26.3 KA for 1 sec 26.3 KA for 1 sec E Rated (KAP) 50 KA 50 KA 66 KA 66 KA F Insulation level (KV rms/KVP) 20 KV / 60 KV 28KV / 75 KV 50 KV / 125 KV 70 KV / 170 KV 1.1.7 short circuit making current Earthing Switch Cable earthing switch shall be provided in the cable chamber and shall be operated from the front of the panel. The ON/OFF position of switch shall be indicated by mechanical indicator. The earthing switch shall be suitably interlocked with the breaker, so that it can be operated only when the breaker is in OFF position. Earthing switch shall also be provided on bus bar side. The ON/OFF Switch shall be indicated by mechanical indicator. The earthing switch shall be suitably interlocked with the breaker, so that it can be operated only when the breaker is in OFF position. 1.1.8 Isolating Contacts The breaker isolating contacts shall consist of two parallel flat silver plated copper bars with ball point contacts to give a vertical tolerance of ±10 mm. 1.1.9 Low Voltage Plug And Socket Connector A twenty pin plug and socket connection along with flexible leads shall be provided to connect control instrumentation and interlock circuits on the breaker truck and in the panel. The plug and socket assembly shall be suitably interlocked with the truck positions like service and test/isolated position 1.1.10 Interlocks And Safety Devices The following interlocks shall be provided: a. The truck cannot be moved from either test to service position or vice versa, when the circuit breaker is ‘ON’. b. The circuit breaker cannot be switched ‘ON’ when the truck is in any position between test and service position. c. Front part of the truck cannot be removed when the breaker in ‘ON’ position. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 82 d. The low voltage plug and socket cannot be disconnected in any position except test/isolated position. e. The truck cannot be moved inside the panel, when the LT plug and socket is disconnected. f. Earthing switch cannot be switched ‘ON’ when the truck is inside the panel. g. The truck cannot be inserted when the earthing switch is ‘ON’. 1.1.11 Safety Devices The following Safety devices shall be provided for the safety of the operating personnel: a. Individual explosion vents shall be provided for breaker/bus bar/cable chambers on the top of the panel to let out the gases under pressure generated in case of fault inside the panel. b. Cubicle with front plate to withstand the pressure for internal arc fault as per PEHLA recommendation. c. Circuit breaker and sheet metal enclosure shall be fully earthed. d. Self locking shutters shall be provided which shall close automatically when the truck is withdrawn to ‘Test position’ and no separate padlocking of the shutter shall be required. 1.1.12 Protective Earthing The earthing connection between the truck and the cubicle shall be by means of sliding contacts so that the truck is earthed in the isolated position when inserted and remains earthed when the truck is pushed further into the connected position or when the truck is being withdrawn until the truck has moved part the isolated position. 1.1.13 Current Transformer I. GENERAL REQUIREMENTS Accommodation shall be provided in the circuit breaker panel, to mount one set of duel ratio CT. Access to the CTS for cleaning, testing or changing shall be from the front, back or top of the panel. II. RATING Duel ratio CTS of suitable burden (but each not less than 15 VA) shall be preferred with 5 amps secondaries. Instrument Security Factor (ISF) of each CT shall not be more than 5. The CTs shall conform to relevant Indian Standards. The design and construction shall be dry type, epoxy resin cast robust to withstand thermal and dynamic stresses during short circuits. CT terminals shall be shorting type. Current & voltage circuits shall be laid in separate wire ways. Secondary terminals of CTS shall be brought out to a suitable terminal block which will be easily accessible for terminal connections. Test terminal block shall be provided in the front side of the panel for testing purpose. CT’S shall have 2 Nos. of cores for following application: Core -1 for metering Core -2 for over current & earth fault protection. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 83 Class of accuracy of each winding Metering class 1 Protection class 5P10 1.1.14 Potential Transformers The potential transformers shall be confirming to IS 3156/ IEC 60185.The primary windings of the potential transformers shall be insulated and shall be of the cast rest in type. Potential transformer (PT’S) shall be mounted on a draw out trolley and housed in separate metal compartment and shall have control fuses on the H.V. side and a miniature circuit breaker on the L.V. side of the windings.HT HRC Control fuses shall be confirming to IS – 9385/ IEC –60282.Miniature Circuit breaker shall comply with IS – 8828/ IEC – 60898. Padlocking facilities shall be provided for both service and isolated position. The potential transformer shall be as specified below: Ratio : 11000 V3/ 110/ V3/ 110 V V A Burdan : 100 V A for 100/V3 and 110 V winding Class : CL –1 for both the windings. Basic Insulation level : Same as mentioned for VCB in clause -6. Over voltage factor : 1.2 Continuous Single phase PT’S shall be used and shall be connected in Star/ Star. 1.1.15 Protection And Tripping Arrangement & Devices PROTECTION All protection relay shall be numeric type of approved make. The protection and tripping arrangement of circuit breaker shall be: 1) Numeric type instantaneous short circuit protection Device No.50 Range 500 – 2000% shall be provided on all phases. 2) Numeric type back up over current protection for Phase faults Device No.51 Range 50 – 200% shall be provided on all phases. 3) Numeric type ground fault protection Device No.50G. CT’s. Range 20 – 80% shall be provided. 4) Lockout and trip supervisory relays etc shall be provided with manual reset facility. 5) Auxiliary relay for transformer fault like OT & WT. 6) Surge Arrestor BREAKER TRIPPING & CLOSING DEVICE Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 84 Breaker tripping and closing devices shall be operated on D.C. supply. The rated D.C. voltage shall 110 V D.C. through power pack with storage facility for one tripping and one closing. The supply for breaker opening, closing and indication devices shall be provided as under: One D.C. feeder shall be provided for each bus section. The Bus coupler panel may be fed from any of the two supplies. One separate 240 V AC supply shall be provided for space heater, motor auxiliary supply etc. Mechanical indication for breaker positions such as ON, OFF, spring charged, test position/Service position shall be provided. Various Electrical indications with colours are indicated below shall be provided. a) Breaker `ON' - Red lamp b) Breaker `OFF' - Green Lamp c) Breaker `Auto Trip' - White lamp d) Trip circuit healthy - White lamp e) DC fail - Blue lamp. f) Red phase ON - Red g) Yellow phase ON - Yellow h) Blue phase ON - Blue 1.1.16 Control Wiring The control wiring shall be carried out with minimum 2.5 sq. mm. PVC insulated copper conductor cables. The wiring shall be securely fixed and neatly arranged to enable easy tracing of wires. Identification PVC ferrules shall be fitted to all wire terminals to render easy identification and facilitate checking in accordance with IS 5578 and 11353. 1.1.17 Metering Instrument Panel Accessories i. METERING Digital type Trivector meter of approved make (Smart demand controller) shall be provided on the incomer feeder. Specification of the meter shall be as follows: Accuracy : Class 0.5, compliant to revenue class certification. : Real time measurement per phase & average : V, I, PF, KW, KVAR, KVA : Peak demand, sliding window. Protected. : V & I unbalance Phase reversal : Time of Use (TOU) Power Quality Measurement: Total Harmonics Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 85 Logging & recording for all measurements: Alarming : Interval or event-based, 32 channel measurement & recording : Event logging : “Bust” data recording : Min/ Max recording : Over & under measurement detection by 24 set point Functions. Multi port Communication ii. : One each of RS 485 and RS 232 ports. INSTRUMENT PANELS The instrument panel shall be part of the housing. Relays, meters and instruments shall be mounted as per general arrangement drawings to be submitted by the vendors. They shall be of flush mounting type. iii. INSTRUMENTATIONS a. Digital type Voltmeter of class 1.0 accuracy and Suitable in size as per IS-1248 shall be provided at incomer panel, with selector switch. The instrument shall be calibrated for the ranges specified. b. Digital type Power factor meter of class of 1.0 accuracy conforming to IS: 1248 shall be provided at incomer panel. c. Digital type Ammeter with Inbuilt Selector Switch of specified range to class 1.0 accuracy and Suitable in size as per IS - 1248 shall be provided at both incomer and outgoing panels along with necessary selector switches. d. Digital type frequency meter class of 1.0 accuracy conforming to IS: 1248 shall be provided at incomer panel. e. Digital Type Load Manager of Schneider makes PM 210 with RS 485 port. iv. The following minimum indication lamps shall be provided in the front of cubicle Breaker open / closed / tripped, spring charged trip circuit healthy and control supply healthy. Lamps shall be clustered LED type and trip circuit supervision scheme shall be of continuous supervision type. v. After meeting all necessary control and indication requirements 2 nos. NO and 2 nos. NC auxiliary of the breaker shall be made available for the owner, wired up to terminal block. vi. Separate MCB’s shall be provided for lamps, heaters and other instrumentation etc. on each panel. vii. Anti-condensation space heaters suitable for operation on 240 V single phases, 50 Hz A.C. for each cubicle and with thermostat control one incandescent lamp with switch and 3 pin 5 amps plug socket. viii. Earthing Conductor of 30 x 6 mm should be provided in continuous length of the panel. 1.1.18. Drawings/Documents Required For Review/Approval Following drawings documents shall be submitted by the manufacturer for approval. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 86 1) General arrangement (GA) of equipment layout. 2) Equipment list. 3) Relay and metering system schematics. 4) Supply and erection schedule. 5) Catalogue and specification sheets. 1.1.19. Inspection And Testing After manufacturing of switchgear panels tests shall be carried out on the equipment as per relevant IS and Electricity Regulations. 1.1.20. Quality Assurance Vendor shall submit in substantial detail a quality assurance plan indicating all activities step by step at various manufacturing/fabrication stages to meet the requirement of this specification and various standards/regulations/practices to enable comprehensive assessment of its merits and reliability. 1. Technical Data For Switchgear Cubicle Type With Breaker VCB Tenderer must fill in the following technical data VCB 1.1 1.2 Switchgear cubicle i. Make ii. Type iii. Reference Standard iv. Voltage (System/Rated) v. Phase/Frequency vi. Short Circuit Rating a. Interrupting Symmetrical b. Short time for 1/3 sec. Construction i. Draw out feature for Circuit Breaker with Service Test & Disconnected ii. Minimum clear space required at: a. Front for breaker withdrawal b. Rear Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make iii. 1.3 1.4 E- 87 Overall dimension & Operating weight BUS BAR i. Material & grade (Cu. Only) ii. Reference standard iii. Cross sectional area size iv. Continuous current at 40 deg C v. Max temp rise over for 40 deg C vi. Short time current for 1/3 sec. vii. Min clearance of bare bus bar & connection a. Phase to phase b. Phase to ground Circuit breaker i. Make ii. Type iii. Rated voltage iv. Rated frequency v. No. of poles vi. Rated current a. Continuous at 40 deg C & within b. Short time current for 1 sec/3 sec 1.5 Max. temp rise over 40 deg C ambient 1.6 Rated operating duty 1.7 Interrupting capacity at rated voltage and operating duty cubicle a. Symmetrical 1.8 Rated making current 1.9 No. of breaker operations permissible Without requiring inspection for refilling SF6 gas replacement of contacts & other main parts a. Not Applicable At 100% rated current Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make b. 1.10 1.11 1.12 1.13 1.14 E- 88 At 100% rated short circuit current Type of contacts a. Main b. Arcing Min clearance in air a. Between poles b. Between live parts & ground Operating mechanism a. Type b. No. of breaker operations stored c. Trip free or fixed trip? d. Antipumping features provided Closing Coil a. Voltage b. Permissible voltage variation c. Power required at rated voltage Breaker/breaker cubicle provided with the following: a. Mech. safety interlocks b. Automatic safety shutter c. Emergency manual trip d. Mech. ON/OFF indicator e. Operation counter f. Spring charge/discharge indications g. Manual spring charging facility h. Mechanical Antipumping 1.15 Net weight of the breaker 1.16 Impact load for foundation design 1.17 Overall dimensions in mm Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 12.3 1.1 E- 89 DRY Type Transformers With Off Load Tap Changer Scope Design, manufacture, testing, supplying and commissioning of 11 KV/433 volts step down, transformer complete with all the accessories and fittings for efficient and trouble free operation. 1.2 CODES And ST ANDARD Transformer shall Conform to Indian Standard IS: 2026-1977 (Part I to IV), IS: 11171 - 1985 IEC 60726, ECBC-2007. 1.3 Rating Transformer shall be suitable for continuous operation and maximum rating shall be as given in the schedule of quantities. 1.4 Connections And Vector Group Delta on High Voltage side and star on low voltage side with neutral terminal brought out for solid earthing corresponding to the Vector Symbol Dyn - 11. 1.5 System Of Supply 3 phase, 50 Cycles, 33 KV earthed system. 1.6 Tappings Off load tap changing on HV side. The tapings to be provided for variation on HV side from +7.5% to 7.5% in steps of 2.5 % each. 1.7 Temperature Rise o Continuously rated for full load, temperature rise not exceeding 90 C corresponding to Class “H". 1.8 Type Outdoor type. 1.9 Terminals The cable box with glands on H T side shall be suitable for 3 core XLPE cable of specified capacity. Flanges with cable box / bus duct on LT side shall be suitable for aluminium conductor armoured cables / LT bus duct of size mentioned in BOQ. All cable glands shall be earthed. 1.10 Cooling Air Cooled 1.11 Insulation Glass fibre reinforced epoxy and class `H'. 1.12 Earthing Two earthing terminals shall be provided at the bottom on both sides. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 1.13 E- 90 Fittings And Accessories The following fittings and accessories shall be provided. a. Transformer shall be provided with 4 Nos. bi-directional rollers fitted on cross channels to facilitate the movement of the transformer in both direction. b. Lifting lugs c. Diagram and rating plate shall be provided indicating the details of transformer, connection diagram, Vector group, tap changing diagram etc. d. Thermistors for Alarm and Trip. e. HV Cable terminating facility for XLPE cable. f. LV Cable terminating facility /bus duct termination flange. g. Winding Temperature Relay unit. h. Winding Temperature indicator. i. 1.14 Disconnecting chamber shall be provided for cable termination. Iron Core The core shall consist of grain oriented laminations which shall be insulated on both sides for low losses. 1.15 Winding High Voltage and Low Voltage windings shall be made of copper and insulation shall be of class F. High voltage and low voltage windings, shall be completely impregnated and cast under vacuum into moulds. This process shall form the insulation system of uniform glass fibre epoxy laminate of highest electrical and mechanical quality, into which windings shall be voidlessly embedded. Both the high voltage and low voltage windings of each phase shall be separately cast as one rigid tubular coil. 1.16 Enclosure The transformer shall be housed in 2 mm thick CRCA sheet steel enclosure mounted on bi-directional rollers. Enclosure shall be provided with metal screen at top and bottom for ventilation. Degree of protection of enclosure shall be IP-43. 1.17 Draw ings And Leaflets Three copies of manual giving complete instructions for the installation, operation and maintenance with circuit diagram, foundation and trenching details shall be provided with the transformer. 1.18 M aximum Allow able Pow er T ransformer Losses Maximum allowable losses for Oil type distribution transformers with highest voltage for equipment up to 50 KV, at 50 % and 100 % of the load. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 91 TRANSFORMER CAPACITY KVA MAXIMUM ALLOWABLE LOSSES AT 50% KVA OR LOAD (%) MAXIMUM ALLOWABLE LOSSES AT FULL LOAD / RATED KVA (%) 100 1.88 2.44 160 1.61 2.07 200 1.50 1.90 250 1.36 1.73 400 1.19 1.51 500 1.12 1.45 630 1.06 1.40 1000 0.90 1.20 1600 0.79 1.05 2000 0.75 1.00 Measurement And Reporting Of Transformer Losses Tests All routine tests as per IS2026-1977 / IS: 11171-1985 which is applicable shall be carried out at the factory and copies of test reports shall be submitted for approval and records. Heat Run Test shall be carried out at an approved test lab as per IS: 2026-1977 at no extra cost. Impulse test shall be carried out at an approved test lab as per IS:2026-1977 Measurement of winding resistance. Ratio polarity and phase relationship. Impedance voltage. Load Losses. No-Load losses and no-load current. Insulation resistance. Induced over voltage with-stand. Temperature rise. 1.19 Testing The transformer shall be subject to the following tests at the factory before dispatching the same and test certificates shall be furnished. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 92 a. Measurement of winding resistance. b. Ratio polarity and phase relationship. c. Impedance voltage. d. Load losses. e. No-load losses and no-load current. f. Insulation resistance. g. Induced over voltage withstand. h. Separate - source voltage withstand. i. Temperature rise. 1.20 Draw ings/Documents Required For Review /Approval Following drawings documents shall be submitted by the manufacturer for approval. a. General arrangement (GA) of equipment layout. b. Equipment list. c. WTI schematics. d. Supply and erection schedule. e. Catalogue and specification sheets. 1.21 Inspection And T esting After manufacturing of switchgear panels tests shall be carried out on the equipment as per relevant IS and Electricity Regulations. 1.22 Quality Assurance Vendor shall submit in substantial detail a quality assurance plan indicating all activities step by step at various manufacturing/fabrication stages to meet the requirement of this specification and various standards/regulations/practices to enable comprehensive assessment of its merits and reliability. 1.23 Technical Data For Transformer Tenderer must fill in the following technical data S. No. Technical Parameters Dry Type Transformer 1. Type and class of insulation 2. Output in KVA (Continuously rated) Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 3. 4. E- 93 Rated Voltage a. HV (Volts) b. LV (Volts) Rated Current a. HV (amps) b. LV (amps) 5. No. of phase 6. Type of cooling 7. Frequency 8. Winding Connection 9. Tapings 10. Vector Group 11. Ref. Ambient temperature Temperature rise winding Class of insulation 12. 13. Physical Dimensions a. Length (in mm) b. Width (in mm) c. Height (in mm) % Impedance S. No. Technical Parameters 14. X/R ratio 15. Iron losses at normal voltage ratio 16. Copper loses at normal voltage ratio Dry Type at full load 17. Efficiency at unity power factor a. Full load Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 12.4 b. 75% load c. 50% load 18. Regulation at unit power factor 19. Regulation at 0.8 power factor 20. Approximate weight a. Core & winding (Kgs.) b. Total Weight (Kgs.) E- 94 Ht Cable 11 / 11 Kv Grade XLPE 1.1 General Cables shall be aluminium conductor, cross linked polyurethane construction and shall be supplied, inspected, laid, tested and commissioned in accordance with drawings, specifications, relevant Standard Specifications and cable manufacturer's instructions. 1.2 Material a. Conductor The Conductor shall be made from electrical purity aluminium stranded wires compacted together. b. Conductor Screen The conductor screen shall consists of an extruded layer of thermosetting semi-conducting compound which shall be extruded simultaneously with the core insulation c. Insulation High quality TROPOTHEN - X (XLPE) unfilled insulating compound of natural colour shall be used for insulation. Insulation shall be applied by extrusion process and shall be chemically cross linked in continuous vulcanization process. d. Shielding Cables shall be provided with conductor shielding as well as insulation shielding and shall consist of extruded semi-conducting compound, additionally insulation shield shall be provided with semiconducting and metallic tape shield over the extruded insulation shield. XLPE insulation and outer core shielding shall be extruded in one operation. e. Armouring Armouring shall be applied over the inner sheath and shall comprise of flat steel wires (strips). f. Outer Sheath Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 95 Tough outer sheath of heat resisting PVC compound shall be extruded over the armouring in case of armoured cables or over extruded over the armouring in case of armoured cables or over inner sheath in the case of unarmoured cables. Cable Marking g. Embossing of outer sheath: The PVC outer sheath shall be legibly embossed with the legend: "ELECTRIC CABLE 3300/33000 VOLT" The letter and figures shall be raised and shall consist of upright block characters. The maximum size of the characters shall be 13 mm and the minimum size 15 % of the cable circumference or 3 mm whichever be the greater. The gap between the end of one set of embossed characters as above and the beginning of the next shall not exceed 150 mm. Identification of Manufacturer & year of manufacture An identification of the manufacturer and indication of the year of manufacture shall be embossed at regular intervals on the PVC outer sheath. This shall not affect the spacing between repetitions of the legend as given above. 1.3 Tests Cables shall be type tested and routine tested in accordance with IS: 7098 (Part II). a. Conductor resistance test. b. Partial discharge test. c. High Voltage test. The following tests shall be carried out at site for insulation between phases and between phase and earth before and after cable laying. a. Insulation Resistance Test. b. Continuity resistance test. c. Sheathing continuity test. d. Earth test. e. High Voltage test. Cables shall be laid with a clearance of at least 75 mm between two cables. 1.4 End Termination Of Ht Cable Pre-moulded cable terminations for XLPE cable shall be used as per manufacturer’s instructions. The steel cone of Push-On shall consist of highly track resistant insulating section vulcanized to a semiconducting section. The pad material shall have cold-flow properties and shall be flame retardant. Each end terminal shall undergo Hi Pot Test. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 1.5 E- 96 Laying Of Ht Cables Direct In Ground The work shall involve excavation of trench and laying of cable(s) as indicated in drawing and Schedule of Quantities. The depth of the excavation shall not be less than 900 mm for 6.6 / 11 KV and 1050 mm for 22 / 33 KV plus radius of cable, from the upper surface of ground. Where more than one multi core cable is laid in the same trench, a horizontal inter spacing of 250 mm shall be left in order or reduce mutual heating and also to ensure that fault occurring on one cable will not damage the adjacent cable. Cable shall be laid in cement pipes encased in concrete or hume pipes at all road crossing. Cables shall be laid in trenches over rollers placed inside the trenches. After the cable has been properly laid and straightened, it shall be covered with 80 mm thick layer of sand. Cable shall then be lifted and placed over this sand cushion. Again, the cable shall be covered with an 80 mm layer of sand. Over the sand a layer of cable protection tiles shall be placed by overlapping 50 mm on either side. Trenches shall then be back-filled with earth and shall be consolidated. Suitable cable markers made of cast iron with aluminium paint indicating the voltage grade and direction of run of the cables shall be installed at regular intervals. 12.5 Compact Sub Station / Unitise Sub Station 1.1 SCOPE This scope shall cover design, manufacture, check test, and supply, installation, testing and commissioning of Compact Package Substation as described in Bills of quantities and drawings. 1.2 CODE & STANDARDS: All equipment and material shall be designed manufactured and tested in accordance with the latest applicable Indian Standard / IEC standard. Equipment and material confirming to any other standard which ensures equal or better quality may be accepted. In such case copies of English version of the standard adopted shall be submitted. The electrical installation shall met the requirement of Indian Electricity Rules as amended up to date relevant IS code of practice and Indian electricity act. The Compact Secondary Sub-station offered shall in general comply with the latest issues including amendments of the following standards but not restricted to it. Title High Voltage Low Voltage Pre-Fabricated Substation Indian Standards IEC:1330 11 / 11 kV Switchgear cubicles IS:13118, IS:3427, IEC:694. IEC:298 Ring main unit 11 / 11 kV grade IS:9920, IEC:265 Code of practice for selection, installation and maintenance of Switchgear Distribution Transformer IS:10118 Consultant : JIT Engineering Services Consultant IS: 2026 Sign of Bidder Electrical Works – Specifications and List of Make 1.3 E- 97 Dry Type Power Transformer IS:11171 Colour for ready mix paints IS:5 Enamel synthetic, exterior a)Undercoating b) finishing IS:2932 Indian Electricity Rules 1956 Indian Electricity Act 1910 DESIGN CRITERIA Compact Secondary Sub-station consisting of 11kV Non-Ext Compact SF6 RMU(1no. SF6 circuit Breaker) + Transformer + L.T. Switchgear with all connection accessories, fitting & auxiliary equipment in an Enclosure to supply Low-voltage energy from high-voltage system as detailed in this specification. The complete unit shall be installed on a substation plinth (base) as Outdoor substation located at very congested places. The HT Circuit Breaker shall be used to control and isolate the 11kV/433V Distribution transformer. The transformer L.T. side shall be connected to L.T. switchgear. The connection cables to Feeder Pillars shall be taken out from the L.T. switchgear. The prefabricated-Compact Secondary substation shall be designed for a) Compactness, installation, c) maintenance free operation, d) safety for worker/operator & public. b) fast The Switchgear and component thereof shall be capable of withstanding the mechanical and thermal stresses of short circuit listed in ratings and requirements clause without any damage or deterioration of the materials. For continues operation at specified ratings temperature rise of the various switchgear components shall be limited to permissible values stipulated in the relevant standard and / or this specification. 1.4 Service Conditions: The equipment offered shall be suitable for continuous satisfactory operation in tropical area of Installation. 1.5 Enclosure: The Enclosure, High Voltage switchgear-control gear, Low Voltage switchgear-control gear & Transformer of the Compact Secondary substation shall be designed to be used under normal outdoor service condition as mentioned. The enclosure should take minimum space for the installation including the space required for approaching various doors & equipment inside. The enclosure construction shall be such that it fully protects ingress of rain water &rusting .For this purpose, construction without welded joint is preferred. 1.6 SPECIFIC REQUIREMENT The main components of a prefabricated-Compact Secondary substation are Transformer, High-voltage switchgear-control gear, Low-voltage switchgear-control gear, corresponding interconnections (cable, flexible, bus bars) & auxiliary equipment. The components shall be enclosed, by either common enclosure or by an assembly of enclosure. All the components shall comply with their relevant IS/IEC standards. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 1.7 E- 98 Ratings: Description Value Rated Voltage/ Operating Voltage 11 kV rms Rated frequency & Number of phases50Hz & 3nos. Rated maximum power of sub-stationAs given in B.O.Q. Rated Ingress protection class of Enclosure IP-23D for substation enclosure and IP:54 for LT Switchgear & HT Switchgear enclosure HV Insulation Level Rated withstand voltage at power frequency of 50 Hz 50 kV rms Rated Impulse withstand Voltage 125 kV peak HV Network & Busbar 1.8 Rated current 400 Amp Bus Bar current density (Cu) 1 Amps/sq. mm Rated short current 18.4 kA rms/1sec time withstand Making capacity for switchdisconnector & earthing switches 52.5 kA peak Breaking capacity of Isolators (rated full load) 400 A Tap off Breaker 400 A LT Network 1 No. ( rating As per BOQ ) , 4P, 50 / 65 kA ACB with micro-processor based release as incomer with Communicable Accessories with 1 no. of 160 Amp. TP MCCB with Capacitor duty Contactor with time delay relay with 50 KVAR Gas Field Capacitor & Metering as shown in SLD Outdoor enclosure: The enclosure shall be made of Galvanized Iron tropicalised to Indian whether conditions. The metal base shall ensure rigidity for easy transport & installation. The structure of the substation shall be capable of supporting the gross weight of all the equipment & the roof of the substation compartment shall be designed to support adequate loads. The protection degree of the Enclosure shall be IP54 for LT & HT switchgear compartment & IP23D for Transformer compartment. Proper / adequate ventilation aperture shall be provided for natural ventilation by way of Louvers etc. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 99 The doors shall be provided with proper interlocking arrangement for safety of operator. The H.V. & L.V. outgoing of the transformer are to be connected to HT Breaker & incomer of the L.V. 1.9 Internal Fault : Failure within the Compact Secondary substation due either to a defect, an exceptional service condition or mal-operation may initiate an internal arc. Such an event may lead to the risk of injury, if persons are present. It is desirable that the highest practicable degree of protection to persons shall be provided. 1.10 Covers & Doors : Covers & doors are part of the enclosure. When they are closed, they shall provide the degree of protection specified for the enclosure. Ventilation openings shall be so arranged or shielded that same degree of protection as specified for enclosure is obtained. Additional wire mesh may be used with proper Danger board for safety of the operator. All covers, doors or roof shall be provided with locking facility or it shall not be possible to open or remove them before doors used for normal operation have been opened. The doors shall open outward at an angle of at least 90° & be equipped with a device able to maintain them in an open position. 1.11 Earthing : All metallic components shall be earthed to a common earthing point. It shall be terminated by an adequate terminal intended for connection to the earth system of the installation, by way of flexible jumpers/strips & Lug arrangement. The continuity of the earth system shall be ensured taking into account the thermal & mechanical stresses caused by the current it may have to carry. The components to be connected to the earth system shall include: a) b) c) d) e) The enclosure of Compact Secondary / prefabricated substation, The enclosure of High voltage switchgear & control gear from the terminal provided for the purpose, The metal screen & the high voltage cable earth conductor, The transformer tank or metal frame of transformer, The frame &/or enclosure of low voltage switchgear, There shall be arrangement for internal lighting activated by associated switch for HV, Transformer & LT compartments separately. 1.12 Labels : Labels for warning, manufacturer’s operating instructions etc. & those according to local standards & regulations shall be durable & clearly legible. 1.13 Cleaning & Painting : i) The paints shall be carefully selected to withstand tropical heat rain. The paint shall not crinkle or be removed by abrasion due to normal handling. scale off or ii) Special care shall be taken by the manufacturer to ensure against rusting of nuts, bolts and fittings during operation. All bushings and current carrying parts shall be cleaned properly after final painting. 1.14 11kV Non-Ext RMU: ( Refer HT VCB Spects Also ) Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 100 The requirement of 11kV Switchgear is as under. VCB Non-extensible Units with HT Circuit Breaker comprising of panel as indicated below: VCB (Feeding to transformer) complete with operating mechanism, protection system and One Number of cable box accessible from the front suitable for terminating of suitable size XLPE cables (Details to be frozen while detailed engineering) The above Breaker , Busbars should be mounted inside a robotically welded sealed for life , stainless steel tank of 3 mm thick sheet metal. The degree of protection for gas tank should be IP67. The VCB is required to control 11 kV/433 volts distribution Transformer of suitable rating and relay settings shall be selected accordingly. 1.14.1 General Finish: Totally enclosed, metal clad, vermin and dust proof suitable for tropical climate use as detailed in the specification. 1.14.2 Ratings: The busbars shall have continuous rating of 630 Amps. The isolator shall have a continuous rating of 630 Amps VCB Breaker shall have a continuous rating of 400 Amps. in accordance with relevant IS / IEC standard 1.14.3 Breaking & Making Capacity : The VCB, Breaker shall be capable of having rupturing capacity of 26.3kA symmetrical at 11000 volts three phase. 1.14.4 Busbar: Switchgear shall be complete with all connection, bus-bars etc. Copper busbars continuous rating shall be 630 Amps. 1.14.5 Remote Operation: Provision of remote operation of the RMU’s Isolators & Breaker CB shall be possible using Motors fitted to the operating mechanism. It shall be possible to fit the motors either directly in manufacturing plant or on site as & when required. Installation on site shall be possible (optional – all required provisions to be made) 1.14.6 Switchgear : The RMU shall be Sealed for life, the enclosure shall meet the “sealed pressure system” criteria in accordance with IEC:298 (a system for which no handling of gas is required through out service life of approximate 25 years.) There shall be no requirement to ‘top up’ the SF6 gas. In addition, manufacturer shall confirm that maximum leakage rate is lower than 0.1% per year. It shall provide full insulation, making the switchgear insensitive to the environment. Thus assembled, the active parts of the switchgear unit shall be maintenance free. The switchgear & switchboard shall be designed so that the position of different devices is visible to the operator on the front of the switchboard & operation are visible as well. The switchboard shall be designed so as to prevent access to all live parts during operation without the use of tools. RMU should be tested for internal arc fault test. 1.14.7 Isolator : The Isolators offered shall conform to IEC60129. The isolator shall be triple pole, spring assisted, hand operated, non-automatic type with quick break contacts. The operating handle shall have three positions ‘ON’, ‘OFF’ and ‘EARTH’ which shall be clearly marked with suitable arrangement to padlock in any position. A safety arrangement for locking shall be provided by which the isolator operation shall be prevented from ‘ON’ position to ‘EARTH’ position or vice versa in a single operation. 1.14.8 VCB: Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 101 The Unit shall consist 400 A Tee-off spring assisted, three pole VCB circuit Breaker, with integral fault making / dead breaking earth switch. The function shall be naturally interlocked to prevent the main & earth switch from being switched ‘ON’ at the same time & the CB not allowed to trip in ‘Earth On’ position. The selection of the main/earth switch lever on the panel, which is allowed to move only if the main or earth switches in the off position. The lever shall be able to pad locked in either the main or earth position. The manual operation of the circuit breaker shall not have an effect on the trip spring. This should only be discharged under a fault (electrical) trip condition, the following manual reset operation should recharge the trip spring & reset the CB mechanism in ‘main off’ position. 1.14.9 Protection : Protection Relays: The CB shall be fitted with microprocessor based self powered relay inside the front cover to avoid any tampering. 1.14.10 Cable Box : Every isolator / VCB shall be provided with suitable and identical cable boxes for connecting 3 core, 11kV cable from vertically below. The cable boxes shall be so located at convenient height to facilitate easy cable jointing work. The Cable termination shall be done by Heat shrinkable Termination method so adequate clearances shall be maintained between phases for Termination. Access to all the cables should be possible form the front of RMU. 1.14.11 Locking Arrangement : Suitable padlocking arrangements shall be provided as stated below… a) b) c) CB manual operating handle in the “OFF” position. Each feeder Panel operating handle in ‘Closed’ ‘Open” or ‘Earth’ position. Each isolator operating handle in ‘Closed’, ‘ Open’, or ‘Earth’ position. 1.14.12 Ratings : Non-Extensible switchgear with VCB a) b) c) d) e) f) g) h) i) j) a) b) c) d) e) f) Switchgear Data Service Type Number of phases Voltage Rated Frequency Rated Current Short Circuit rating i) Breaking ii) Short time withstand for 3 Sec. iii) Rated S/c making Short duration power frequency Insulation Level System earthing Breaker Type Rated voltage Breaking current i) Load breaking Making current Rated current No. of poles Consultant : JIT Engineering Services Consultant Outdoor but inside Enclosure Metal clad 3 11 KV 50 Hz 400 Amp 18.4 kA rms for Breaker 28.3 kA rms 52.5 kA peak for Breaker 50 kV 125 kV peak Solidly earthed at substation VCB in SF6 tank 11 KV 18.4 kA rms. 52.5 kA peak 400 Amps. 3 Sign of Bidder Electrical Works – Specifications and List of Make g) Operating mechanism. a) b) c) Busbars ( If any) Material Type Rated Current E- 102 Trip free & free handle type with mechanically operated indication & pad locking. Copper SF6 insulated 400 Amps 1.14.13 Tests For Breaker: Each type of 11 / 11kV Switchgear shall be completely assembled, wired, adjusted and tested at the factory as per the relevant standards i.e. IS : 9920, IS : 3427, IS : 13118, IEC : 265, IEC : 298 and during manufacturing and on completion Routine Tests : The tests shall include but not necessarily limited to the following a) Operation under simulated service condition to ensure accuracy of wiring, correctness of control scheme and proper functioning of the equipment. b) All wiring and current carrying part shall be given appropriate High Voltage test. 1.15 DISTRIBUTION TRANSFORMER ONAN Type Transformer : 1.15.1 Requirement: 11 / 0.433 KV DRY Type , ( KVA as per B.O.Q.) KVA, AN cooled suitable for installation at outdoor in Enclosure for ground mounting. 1.15.2 Voltage Ratio : No load voltage 11000/433 volt within tolerance as stipulated in IS. 1.15.3 Rating : The transformer shall have a continuous rating as specified at any of the specified tapping position and with the maximum temperature rise specified. 1.15.4 Magnetic Core : The Core will be made from Laminations of grain oriented silicon steel, insulated with mineral oxide and will be protected against corrosion with coat of varnish. The choice and grade of steel and the cutting pattern and method of assembly minimizes the loss level and the no load current with the effect of a very low noise level. 1.15.5 Fittings / Accessories 1) 2) 3) 4) 5) 6) 7) 8) 2 nos. earthing terminals Rating and diagram plate 1 no. Winding temperature indicator Off circuit tapping links +/- 10 % in 2.5% step 4 nos. flat bi-directional rollers Lifting lugs Cooling fans Marshalling box Technical Particulars of Transformer Description Unit Consultant : JIT Engineering Services Consultant Value Sign of Bidder Electrical Works – Specifications and List of Make Service Type Rating Rated frequency Number of Phase HV Side LT Side Rated Voltage HV Side LT Side Vector Group Type of Cooling Class of Insulations Insulation Level 1 2 3 4 5 6 8 9 10 a) Power Frequency withstand Impulse Withstand Method of earthing-LT Duty Taps a) range b) No. of Steps c) In steps of d) Tapping provided on HV Side Tap Changer Type Impedance Voltage at 75°C a) At Principal tapping Temperature Rise above 50°C ambient 11 12 13 14 15 16 a) Winding by Resistance Terminals a) HV Side b) LT Side Losses (at 75°C and principle Tapping) (IS Tol.) a) No Load at rated Voltage and Frequency 17 18 b) Load loss at Rated Current c) Total Loss at maximum Rated Power Efficiency at 75°C and unity P.F. a) At Full Load b) At 75% Load c) At 50% of Load Hot spot temperature of winding limited to 19 20 kVA Hz Outdoor AN Type As per B.O.Q 50 3 phase 3 wire 3 phase 4 wire kV kV kV rms kV Peak 11 0.433 DYN-11 AN CLASS H 50KV 125KV INDIAN TNS Continuous % % +10% to -10% 9 2.5% each Yes OFF Load % As per IS Code ±10% °C 65°C for Class H Cable Box Flexible Copper connection KW KW KW Should be less than allowed in ECBC2007. Should be less than allowed in ECBC2007. Should be less than allowed in ECBC2007. % % % Should be better than allowed in ECBC. Should be better than allowed in ECBC. Should be better than allowed in ECBC. °C 90°C for Class F/ 115°C for Class H Reference Standards 21 1.16 E- 103 IS-2026, IS-11171, IEC 60726, ECBC2007 ISOLATOR PANEL : System:- Declared voltage :– 3 Phase,415V (±10%) 50 Hz, Neutral :– Solidly earthed at substation. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 104 1.16.1 General finish :- Tropical, totally enclosed, metal-clad, weather-proof, vermin and dust proof. 1.16.2 Enclosure :- Type of enclosure shall be able to provide the degree of protection IP : 4X . 1.16.3 Circuit Ways for kVA ( as per B.O.Q.) CSS : Incoming of 1 No. rating as per BOQ, 4P, 50 / 65 kA ACB with micro-processor based release as incomer with Communicable Accessories with 1 no. of 160 Amp. TP MCCB with Capacitor duty Contactor with time delay relay with 50 KVAR Gas Field Capacitor & Metering as shown in SLD. Cable connection box should be at least 750 mm above from Gland Plate with necessary space to terminate 4 nos. of 400 Sq. mm. x 3.5 C Cables. 1.16.4 Construction : The terminals shall be of sufficient mechanical strength and shall provide adequate electrical contact for the appropriate size of cable used. They shall be capable of receiving appropriate size of Aluminum conductors / Bus Duct. They shall be provided with stainless steel nut bolts, plane washers and spring washers for cable connection. The enclosure of LT Shall be constructed using 2mm CRCA sheet steel. No contact pressure shall be transmitted through insulating material & the gripping of the conductor shall take place between metal faces. 1.16.5 Earthing : Earthing arrangement shall be provided for earthing each cable / Bus Duct, PVC cable gland, neutral busbar, chassis and frame work of the cubicle with separate earthing terminals at two ends. The main earthing terminals shall be suitably marked .The earthing terminals shall be of adequate size, protected against corrosion, and readily accessible. These shall be identified by means of sign marked in a legible manner on or adjacent to terminals. Neutral bus bar strip shall be connected to Earthing terminal with help of copper strip of suitable capacity & nut-bolt arrangement. 1.16.6 Accessories: The following accessories shall be supplied duly mounted. One incandescent lamp (with necessary fuse) to illuminate the fuse board internally. 1.16.7 Metering : As per BOQ & SLD 1.17 SHOP DRAWINGS Prior to fabrication of the Panels the supplier / contractor shall submit for consultant’s approval the shop / vendor drawing consisting of G.A. drawing, sectional elevation, single line diagram, bill of material etc. and design calculations indicating type, size, short circuiting rating of all the electrical components used, busbar size, internal wiring size, Panels dimension, colour, mounting details etc. in 6 sets.. The contractor shall also submit manufacturer’s catalogues of the electrical components installed in the Panels along with the drawing. The following shall be furnished as part of the Tender : Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 105 (a) General arrangement showing plan, elevation and typical sectional views. (b) Technical literature on the various equipments. (c) The following shall be furnished after award of contract for Purchaser's approval : 1.18 i. General arrangement showing plan, elevation and typical section views. ii. Foundation plan showing location of fixing channels, floor opening etc., iii. Schematic wiring drawings for each feeder. TYPE / ROUTINE TEST ON COMPACT SECONDARY SUBSTATION : Type Tests: The offered Compact Secondary substation should be fully type tested as per the IEC-1330 Routine Tests : The routine tests shall be made on each complete prefabricated substation. a) Voltage tests on auxiliary circuit. b) Functional test. c) Verification of complete wiring. Test Witness: Routine test shall be performed in presence of Owner’s representative if so desired by the Owner. The Contractor shall give at least fifteen (15) days advance notice of the date when the tests are to be carried out. 1.19 Test Certificates: Test report for the test mentioned under Type tests clause shall be submitted along with offer. Certified reports of all the tests carried out at the works shall be furnished in three (3) copies for approval of the Owner. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E13. E- 106 Diesel Generator Set 2.0 Uninterruptable Power Supply 2.1 General Requirements 2.1.1. The scope of work for supply and installation of UPS system shall include design manufacture, supply, installation, testing and commissioning of all related equipments together with all accessories and auxiliaries as per specifications. The system shall be fully operational and shall comply with the specified codes and standards. The contractor shall be responsible for providing all materials, equipments and engineering services specified or which are required to fulfil the intent of ensuring reliability of the total work covered under these specifications within his quoted price. 2.1.2. Supply and installation of the UPS system covered under this specification shall conform to the latest editions of codes and standards mentioned below and all other applicable Standards. a) IEEE Standard 446-1987 : b) IEEE Standard 450-1975 : c) IEEE Paper 4-177: Some discharge characteristics of lead acid batteries. d) IEC 60140-3 e) IEC 60140-2 : Electro Magnetic Compatibility f) IEC 60140-1 : Safety e) ANSI C 37.90a, : Emergency and standby power systems. UPS Performance IEEE Standard 472 : Surge withstand capability test. f) ANSI C 34.2 : Practices and requirements for semiconductor power rectifiers. g) ANSI C 37.90 : Relays and relay system associated with electrical apparatus. h) NEMA PE-1-1983 : Uninterrupted Power System Standard i) IS 2208 & IS 9224 : Cartridge fuses for voltages up to and including 650 V power (Part 1 & Part 2) (I.E.C. 269) j) IS 9224 (Part - 4) : Fuses for protection of semiconductors. k) BS 2709 (I.E.C 119) : The Electrical Performance of Semiconductor Rectifiers. (Metal Rectifiers) l) BS 4417 (I.E.C 146) : Semi-conductor Rectifier Equipments. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 107 m) IS 13947: 1993 : Specification for Low voltage Switchgear & Control gear n) IS 3961(Part 2):1967 : Recommended current rating for PVC insulated Cables o) IS 1652 & IS 1652 : Lead-acid stationary cells and batteries. p) BD 9720 : Custom-built transformers and inductors of assessed quality. q) IP20 : Degree of protection. r) IEC : Semi Conductor Convertor Standards. s) JEC : Standard of the Japanese Electro technical committee t) JIS : Japanese Industrial Standard. u) JEM : The standard of the Japan Electrical Manufactures Association. v) ISO 9001 approved 2.1.3. The vendor shall submit his offer for UPS systems as indicated in the tender document. 2.1.4. All components of the UPS equipment shall have Surge Withstand Capability (SWC) to meet the requirements of ANSI C62.41-1980. ANSI C 37.90a, IEEE Standard 472-1974. 2.1.5. All components of UPS system shall withstand short circuit current without any damage. 2.1.6. Following general requirements shall be met for ensuring proper circuit protection. a. Fuses shall not be larger than 125% of the transformer primary circuit current where the secondary circuit fuse protection has not been provided. b. Where the secondary fuses are sized not larger than 125% of the secondary current of the transformer, fuses shall not be required in the primary circuit, provided the primary feeder fuses are not larger than 250% of the transformer primary current. c. All the neutral conductors in three phase UPS systems shall be sized equal to at least 150% of the maximum phase current. In addition, all the isolators and circuit breakers used in three phase UPS system shall also to be rated such that the neutral poles shall take at least 150% of the maximum phase current. d. All control shall be designed and positioned such that possibility of inadvertent or operations is eliminated. accidental e. All UPS system cabinets, frames and power equipment shall be double earthed. 2.1.7. The UPS design shall ensure that a single component/ device failure shall not result in failure of the entire UPS system. The design of UPS System shall be modular to permit easy maintenance. 2.1.8. The various overload capacities of inverters, static switch, and step down transformer/voltage stabilizer as specified herein are the minimum requirements. However, if the Contractor’s offered system has better overload capacities for the above devices, the same shall be highlighted by the Bidder in his bid. 2.1.9. The UPS system offered by the contractor shall be suitable for operating continuously at the rated capacity indicated in tender with in ambient temperature 0-40 deg.C and relative humidity of 0 to 95%. Also the UPS system shall be suitable for operation as per full rating up Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 108 to 1000 meters above sea level without derating. The Contractor shall furnish a certificate towards compliance on ambient conditions permissible. 2.1.10. The UPS system to be supplied by the contractor shall have maximum humming noise level of 65 DB one meter away from the UPS cabinets. Shall not exceed 69 dBA measured 5 feet from surface of the UPS. 2.1.11. Suppression of Radio Interference shall be provided to meet statutory requirements. 2.1.12. Detailed literature should be provided showing Quality Assurance Procedure adhered to. 2.1.13. The contractor shall submit detailed item by item compliance statement along with the tender. 2.2 Functional Requirements 2.2.1. Contractor shall furnish On-Line Uninterruptible Power Supply (UPS) system of continuous duty of the ratings mentioned in Bill of Quantities. Each UPS shall give regulated filtered & uninterruptible power supply as described in the specifications. 2.2.2. Contractor shall note that the KVA ratings of the UPS systems shall be guaranteed at 40 deg.C ambient temperature. In case contractor’s standard UPS KVA rating are based at a lower temperature, the contractor must consider a derating factor of at least 1.5% per deg.C for arriving at the specified UPS capacity at 40 deg.C ambient temperature. 2.2.3. In case the calculated /specified UPS capacity is not the same as one of the standard KVA ratings of the UPS manufacturer, the next higher standard KVA rating shall be selected. UPS of non standard rating shall not be acceptable. 2.2.4. UPS system supplied by the contractor shall be the latest state of the art technology system fully digitalized using microprocessor controlled full wave rectification and IGBT inverter. 2.2.5. Batteries shall be valve regulated lead acid specially ment for UPS application. 2.2.6. Monitoring and control system shall also be state of the art technology LCD touch panel type providing all relevant data described in this document. 2.2.7. The monitoring and control system shall be capable of RS485 with MODBUS protocol input software for connecting to customer’s computer system for data display and monitoring. 2.2.8. All necessary components required for protecting UPS equipment and connected inputs and outputs shall be furnished by the Contractor as an integral part of the UPS system. 2.2.9. The control logic power supply shall have redundant power supply AC input and the system battery as power sources. 2.2.10. The UPS systems shall include but not be limited to the following equipment: a. UPS system including 100% capacity float-cum-boost charger with 100% sealed valve regulated lead acid batteries with guaranteed battery life of 5 years. b. Suitable factory built battery cabinet for housing the batteries, including terminal isolator / breaker and power disconnect device. The enclosure shall conform to IP 20 as minimum. c. All cables, connectors, accessories like turning, cable trays, conduits etc. required for connection between battery and the UPS unit. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 3. Static Converter 3.1 General E- 109 The static converter (rectifier) shall be a multi-functional converter providing functions of power conversion, battery charging and shall have the additional functions of input power factor improvement and current harmonics reduction. The converter equipment shall include all necessary control circuitry and device to conform requirements like voltage regulation, current limiting, wave shaping, transient recovery, automatic synchronization etc. as given below. The converter shall be a solid state static PWM converter utilizing utilize Insulated Gate Bipolar Transistors (IGBT) or Intelligent Power Module (IPM) transistors and shall include intelligent features like the drive circuitry, over current protection, over temperature protection, control power failure protection and short circuit protection. The IGBT / IPM transistors shall enable high speed switching at 6 KHz thus reducing the heat dissipation in the UPS and thereby providing high efficiency. The PWM converter shall utilize the above and achieve unity power factor and reduce input current harmonics as given earlier and thus improve the overall power factor of the converter achieving input KVA savings. During any step inverter load change (0-100%) the converter shall only supply 100% current to the inverter. The battery shall not be cycled at any time during this step load changes. 3.2 Input Current Limit The converter logic shall provide input current limiting by limiting the DC output current. Two (2) line-side current transformers shall be employed as a means of sensing the current amplitude. The converter logic shall also be capable of providing auxiliary current limited when the logic is signalled to do so via an external dry contact closure (e.g. UPS fed from generator). The converter shall be capable of supplying overload current in excess to the full load rating. It shall also have sufficient capacity to provide power to a fully loaded inverter while simultaneously recharging the system battery to 95% of full capacity within 10 times the discharge time. The DC output current limit values shall be as follows: Rectifier output current (maximum) 100%. Rectifier output current (aux.) 25% - 100% variable. Note: 100% current shall be under the battery recharging mode. 3.3 Battery Charge Current Limited The converter logic shall provide current limiting function of battery charging to prevent the battery from damage. The following battery current limit and protection shall be provided. Battery charge current limit 10% of battery Ah rate. Over-current protection at 120% of above item. 3.4 Voltage Regulation The rectifier / charger output voltage including variation effects of input voltage does not deviate by more than +/- 1% of the nominal output voltage, due to the following conditions: From 0 to 100% loading. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 3.5 E- 110 Rectifier input variations of voltage and frequency within the limitations set in Section 3.10. Environmental condition variations within the limitations set in Section 3.10. Automatic Input Current Walk -In The converter logic shall employ circuitry to allow a delayed and timed ramping of input current. Subsequent to energizing the converter input, the ramping of current shall be delayed by a maximum of 3 seconds. Upon starting the walk-in process, the ramping of current is timed to assume the load gradually within 1 through 60 seconds (every 1 second selectable). 3.6 Input Overload Protection The A/C input fuses shall be provided at the converter input as a means of overload protection. The AC maximum current shall be controlled by the Converter. 3.7 Equalizing Charge Timer The UPS logic shall provide an electronic automatic equalize charge timer which shall be selectable 24 hours for Lead Acid type or 8 hour for alkaline type batteries. The timer circuit, once activated shall provide a high rate equalizing charge voltage to the system battery for the selected time. The circuit shall also be capable of manual activation via the LCD touch panel mounted on the front door. The level of equalizing voltage shall be equal to that stated by the battery manufacturer. Upon completion of the timer count, the converter output voltage shall automatically return to the specified float voltage. 3.8 Step Load Change During any step inverter load change (0-100%), only the converter shall supply 100% current to the inverter. The batteries SHALL NOT is cycled at any time during these step load changes. 3.9 Input Voltage The converter shall be fed from the Normal Power Supply source. The converter shall meet the following specifications in addition to other requirements stated herein: Nominal Voltage : 415V, 3 Phase, 3 Wire Voltage Range. : + 15% / - 30% AC Normal Frequency : 50 Hz + 8 % Frequency Range : + 8% (+ 4 Hz) Input Power Factor : 0.9 lagging or more at full load (PF improvement) Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make Input Harmonic Current THD E- 111 : 3% typical at 100% load 6% maximum at 50% load Duty : Continuous at 40 deg.C Cooling : Forced cooling using fans with thermal relays using a latched cut out for resetting as protection for cooling fans. Each individual fan shall have its own thermal relay. Ambient operating temperature range : Operating - 0 to 40 deg.C maximum. Storage & Transport -20C to 70C Operating Relative Humidity : 0-95% non-condensing. Operating Altitude : Altitude Operating: to 3,000 ft. (1,000 meters) above Mean Sea Level. Derated for higher altitude applications. Storage/Transport: to 40,000 ft. (12 200 meters) above Mean Sea Level Magnetized sub-cycle in rush current : Typically 8 times normal full load current Converter Walk-in time : 1 through 60 seconds (every 1 second selectable, (0 to 100% rated load) Input : Suitable terminals shall be provided for termination of cables from the AC distribution board. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 4. Static Inverter 4.1 General E- 112 The static inverter shall be of solid state type using proven Pulse Width Modulation (PWM) technique. The inverter equipment shall include all necessary control circuitry and devices to conform requirements like voltage regulation, current limiting, wave shaping, transient recovery, automatic synchronization etc. as given below. The inverter shall utilize Insulated Gate Bipolar Transistors (IGBT) or Intelligent Power Module (IPM) Transistors which shall provide intelligent features like the drive circuitry, over-current protection, over temperature protection, control power failure protection and short circuit protection. The IGBT / IPM transistors shall enable high speed switching of 6 KHz thus reducing the heat dissipation in the UPS and thereby providing high efficiency. The UPS shall utilize both Voltage and Current feedback control circuits so that the inverter shall act not only as a constant voltage source but also as a load required current source. This shall enable the inverter to quickly adapt to the changing load current value and wave shape. 4.2 Voltage Regulation The inverter output voltage shall not deviate by more than + 1% RMS due to the following steady state conditions: 4.3 From 0 to 100% loading Inverter DC input voltage varies from maximum to minimum. Environmental conditions variations within the limitations set in the section 4.8. Frequency Control The inverter output frequency shall be controlled by an oscillator internal to the UPS module logic. It shall be capable of synchronizing to an external reference (e.g. the bypass source or another UPS module) or operating asynchronously. The oscillator shall maintain synchronization with the external reference within the limitations set hereunder. The inverter shall operate on self run mode without synchronism if the bypass frequency exceeds the set value. The oscillator, while running asynchronously, shall maintain the frequency as 50 Hz + 0.01% (or + 0.005 Hz). Automatic adjustment of phase relationship between inverter output and standby bypass source shall be gradual at a controlled slew rate which shall be adjustable at the rate of 0.5, 1.0, 2.0, 3.0 Hz / second. (Default 2.0 Hz / second). The inverter output frequency shall not vary during steady state or transient operation due to the following conditions: 4.4 a. From 0 to 100% loading. b. Inverter DC input varies from maximum to minimum. c. Environmental condition variations within the limitations set in section 4.8. Output Voltage Harmonic Distortion The inverter output shall limit the amount of harmonic content to the values stated in section 4.9. The use of excessive or additional filtering shall not be required to limit the harmonic content thus maintaining a high level of efficiency, reliability and original equipment footprint. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 4.5 E- 113 Output Overload Capability The inverter output shall be capable of providing an overload current while maintaining rated output voltage to the values stated in section 4.8. An LED indicator shall be located on the control panel to identify this condition. If the time limit associated with the overload condition expires or the overload is in excess of the set current amplitude, the load shall be transferred to the bypass source without interruption. 4.6 Inverter Current Limit The inverter output shall be limited to 150% of rated load current. The two sensing locations shall operate separately and independently thus providing redundancy and, in the event of a failure, preventing unnecessary damage to power transistor components / fuses. Load current above 150% shall cause an immediate transfer of the load to the bypass source for fault clearing. 4.7 Inverter Overload Protection The AC output from the inverter shall utilize fuses for overload protection. The inverter shall utilize a contactor to isolate the inverter output from the critical bus. The inverter fuses shall be the fast acting semiconductor type. The inverter output isolation contactor shall be located in the UPS module and shall be controlled by the internal UPS module system logic. 4.8 Inverter Specifications The inverter shall meet the following specifications in addition to other requirements stated herein: Voltage Input : Three Phase UPS : Nominal 360 V DC (Range 290 V to 414 V DC to maximum DC bus voltage during charging the batteries). 415 V + 1% AC 3 Phase, 4 Wire Nominal Voltage Output : Inverter Capacity : Voltage Regulation : a. : < + 1% : < + 1% : < + 1% For 0 to 100% loading b. Inverter DC input voltage vary from maximum to minimum c. Environmental given below conditions Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 114 Transient Voltage Regulation : a. AT 100% step load change : < + 3% b. At loss or return of AC input : < + 1% : < + 3% : 20 milli seconds : 50 Hz : + 0.01% : 49 Hz to 51 Hz. d. Field adjustment range for above : 50 + 0.25 Hz to 50 + 1.5 Hz Total voltage harmonic distortion : < 2% THD for 100% linear load c. At load transfer from bypass to inverter Time to recover from transient to normal voltage Wave form a. Normal frequency b. Frequency regulation for all conditions of input supplies, loads and temperature occurring simultaneously or in any combination (automatically controlled) c. Synchronization limits for synchronism between the inverter and standby AC source. 4.9 < 4% THD for 100% non-linear load Duty : Continuous Cooling : Forced cooling using fans. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 4.10 E- 115 Ambient operating temperature range : 0 to 40deg.C maximum continuous. Operating relative humidity : 0-95% non-condensing. Operating altitude. : Sea level to 1000 meters. Output : Suitable terminals are provided for termination of cables for connecting inverter output to AC distribution board. Built-In Isolation Transformer This shall provide neutral separation which shall mean that output neutral will be independent of incoming neutral, hence critical load shall be isolated from the problems like incoming neutral open or, short or, variations in neutral to earth voltage due to sudden loading in neighbouring installation. 4.11 Reverse Phase Sequence Protection In the event of Phase sequence reversal at the input, UPS system shall continue to work on the main power supply, or UPS systems shall go into battery mode, and shall not trip the UPS system. 5. Bypass And Static T ransfer Sw itch 5.1. A bypass circuit shall be provided as an alternate source of power other than the inverter. A high speed switch and wrap-around contactor shall be used for the critical load during automatic transfers to the bypass circuit. The static switch and wrap-around contactor shall drive power from an upstream bypass feed circuit breaker internal to the UPS module provided for overload protection. The wraparound contactor shall be electrically connected in parallel to the static switch and shall at the same time as the static switch, energize and upon closure, maintain the bypass source. The static switch shall only be utilized for the time needed to energize the wrap-around contactor thus increasing reliability. The bypass circuit shall be capable of supplying the UPS rated load current and also provide fault clearing current. The UPS system logic shall employ sensing which shall cause the static switch to energize within 150 microseconds thus providing an uninterrupted transfer to the bypass source when any of the following limitations shall exceed: Inverter output under voltage or over voltage. Overload beyond the capability of the inverter DC circuit under voltage or over voltage Final end voltage of system battery is reached. Bypass source present and available System failure (e.g. Logic fail, fuse blown, etc.) 5.2. Keeping the above requirements in view, the static switch shall have the following minimum rating. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 116 Capacity continuous equal to 100% of continuous rating of the inverter. Capacity overload equivalent to overload characteristics specified for UPS. 5.3 Nominal bypass input voltage : 415 V / 240 V, 3 phase, 4 wire Voltage Range : + 10% of nominal Nominal Frequency : 50 Hz Frequency range : + 2% Please refer to selectable range of Inverter given in point 4.3 & 4.8 Output Fault Clearing : Current : 1000% Duration : 20 milli seconds Ambient operating temperature : 0 to +40 degree C continuous Operating relative humidity : 0-95% non-condensing Operating altitude : Sea level to 1000 meters Cooling : Natural Convection Duty : Continuous Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 5.4 E- 117 Automatic Re-T ransfer In the event that the critical load must be transferred to the bypass source due to an overload, the UPS system logic monitors the overload condition and, upon the overload being cleared, performs an automatic re-transfer back to the inverter output. The UPS system logic shall only allow a re-transfer to occur three times within a ten minute period. Re-transfer shall be inhibited on the fourth transfer due to the likelihood of a recurring problem at the UPS load distribution. The re-transfer a load to the inverter shall also be inhibited due to the limitations set in section 5.3. 5.5 Manual Transfer The UPS shall be capable of transferring the critical load to / from the bypass source via LCD touch panel. When performing manual transfer to inverter or automatic re-transfers, the UPS system logic shall force the inverter output voltage to match the bypass input voltage and then parallel the inverter and bypass source providing a make-before-break transition allowing a controlled walk-in of load current to the inverter. 5.6 Maintenance Bypass Switch (Mbs) The UPS shall include as standard equipment, a zero energy maintenance bypass switch. Full UPS wraparound enables personnel to do work inside the UPS module or maintenance bypass switchboard without danger for high voltage conditions. 6 UPS Battery System a. The UPS system shall, as an integral part, provide battery system for backup time as specified in the Schedule (Full Load) standby capacity. b. The latest state of the art Valve Regulated Sealed Maintenance Free Lead Acid Batteries shall be used with a 20 hours discharge rating. c. The battery system shall be sized to provide backup time as specified in the schedule of quantity when the UPS is supplying 100% rated load at 0.8 load power factor. d. An ageing factor of 15% shall be applied to the capacity arrived at, to allow for compensation against capacity loss during float operation. e. The battery system design shall be provided with necessary devices to prevent deep discharge beyond recommended limits to prevent the batteries discharging beyond end cell voltage specified by the battery maker. The connections from battery to battery shall be by using copper bus bar strips and the entire battery system shall be used in IP20 steel cabinet enclosure and shall be similar to the UPS enclosure. f. All batteries shall be clearly identified and identification numbers marked on the batteries and a schematic diagram along with the complete calculations, including manufacturers supporting curves, shall be submitted with the tender. g. The UPS shall have a properly rated and sized circuit breaker to isolate it from the battery 7. Operation a. Under normal operation, the UPS load will be fed from the Inverter with the bypass switch inhibited. The Converter, apart from providing DC power to the Inverter, also charges the battery under the float charge mode. The battery charge system shall have float charge, equalising charge and recovery charge modes, to replenish the batteries self-discharging part while the battery is fully charged, Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 118 equalising the battery cell voltage to a constant value forcibly, and recharging the battery system to the required values when the batteries have been used, respectively. b. The Inverter shall constantly monitor the AC source frequency and shall be in synchronisation with the AC input source till the frequency of the AC input source is within synchronising limit and if the frequency of the standby source exceeds the synchronising limit the Inverter will work on its own internal oscillator maintaining an output frequency of 50 Hz +/- 0.01% under all conditions of load. When the Inverter operates on its internal oscillator, it shall continuously monitor the frequency of the input source and when the input source frequency returns to within synchronisation limit, the Inverter shall automatically synchronise itself with the input A/C source frequency and use it as a signal for Inverter output frequency control. c. Battery Operation: i. When the A/C input voltage drops below specified limits or in case of a power failure the Inverter continues to supply AC power of constant voltage and constant frequency utilising the battery system as a power source until the input voltage returns to normal requirement. When the power supply is resumed or the input voltage returns to limits, the Converter shall automatically start and the load fed for normal operation status. ii. If the power failure continues beyond battery backup time or the battery voltage drops to the final discharge voltage, the Inverter should automatically stop and at the same time transferring the load to the bypass circuit. On resumption of power supply, the Converter shall automatically restart the operations and charge the batteries whereas the Inverter should inhibit automatic start and should be started manually. d. Bypass Operation: When power is supplied from the Inverter in synchronisation with the bypass, it shall accomplish the following: i. When the UPS output current reaches overload status it shall automatically transfer the load to bypass circuit with no interruption and when the overload status is cleared it automatically re-transfers the load to Inverter. ii. When the battery final discharge condition is reached, the load shall automatically be transferred to the bypass circuit without interruption. iii. In case of failure of the UPS, the load shall be automatically transferred to the bypass circuit with no interruption and when the failure is cleared, re-transfer the load to the Inverter shall be done manually. iv. There should be provision made in the system to prevent, when necessary, asynchronous transfer. v. When the UPS goes on bypass mode in any of the conditions described above and if at that time there is no bypass power supply available due to power failure, the UPS shall remain in standby mode and as soon as the bypass power supply is available will transfer the load to bypass. vi. A maintenance bypass transfer switch shall be provided with lock and key arrangement and should be manually done by authorised personnel only. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 8. E- 119 Battery Monitoring System a. The Battery Monitoring System shall provide for the automatic acquisition, trending, alarming and storage of information from every cell or jar in a battery bank. It will have the interactive ability to first identify and then provide an isolated equalizing charge current to any individual cell or jar that deviates below a user-specified set point, from the cell average, within the same string or bank. b. The Battery Monitoring System shall test the relative charge state and health of each individual cell or jar by injecting a DC current, recording the magnitude of this current & comparing it to previous benchmark values. Systems that require battery discharge for testing are not acceptable. The system shall provide estimated backup time remaining during an actual discharge. c. The Battery Monitoring System shall monitor and maintain historical files for: Individual cell or jar voltage Total bank voltage Discharge current Ambient and pilot cell temperature Relative current response value d. Display shall be via local LCD display, with capability for viewing at a remote terminal. All files shall be written to a fixed solid state disk within the enclosure. All functions shall be accessible via modem using common communications software. e. The system shall operate a “form C” relay contact when any parameter is in alarm. Alarm data shall be written to a file in ASCII format for future retrieval. f. The system shall be capable of remote communications for remote access to all functions via modem or ANSI terminal. g. The Battery Monitoring System shall be capable of monitoring a minimum 264 jars per string, 9 parallel strings per system, and 6 cells per jar. h. Resolution shall be 12 bit accuracy, with up to 10 per second channel test rate. 8. i. Cell voltage measurements must be made to within plus or minus 5 milli volts over the entire operating and temperature range. j. Documentation. Manuals and installation documentation for the equipment shall be provided which lists block diagrams, schematics parts list and theory of operating for each unique component of the system. Installation drawings and documentation shall be site specific for each string at this facility. Marked up building drawings shall be provided to show any changes to building wiring including power wiring and communications cables. k. The system shall be factory tested fully and completely before shipment. Cabinet And Enclosures 8.1 The entire UPS system, including all components like inverter, static switch, maintenance bypass, shall be housed in free-standing steel type factory-finished enclosures complying with the protection standards of IP20. The enclosure shall be open able using a special tool for internal access. The colour shall be light grey. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 8.2 E- 120 Ventilation Forced air-cooling shall be provided to allow components to operate within their rated temperature specified. The cooling fans shall have thermal relays protection using a latched cut fire re-setting, as a protection for the cooling fans. Similarly, the backup battery system shall also be housed as described earlier in an IP20 cabinet. 9. Control And M onitoring a. The UPS shall utilise state of the art full DDC control software driven Control and Monitoring System. b. It shall be provided with LED displays. Metering should display the following parameters on the control panel 1. Input AC voltage line-to-line and line-to-neutral for each phase 2. Input AC current for each phase 3. Input frequency 4. Battery voltage 5. Battery charge/discharge current 6. Output AC voltage line-to-line and line-to-neutral for each phase 7. Output AC current for each phase 8. Output frequency 9. Percent of rated load being supplied by the UPS 10. Battery time left during battery operation. 11. Bypass power available. Following alarm messages to be displayed at the control panel: a. Input power out of tolerance b. Input phase rotation incorrect c. Incorrect input frequency d. Charger in reduced current mode e. Battery Charger Problem f. Battery failed test g. Low battery warning (adjustable 1 to 99 minutes) h. Low battery shutdown i. DC bus overvoltage Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make j. Bypass frequency out of range k. Load transferred to bypass l. Excessive retransfers attempted E- 121 m. Static switch failure n. UPS output not synchronized to input power o. Input power single phased p. Input voltage sensor failed q. Inverter leg over current in X-phase r. Output under voltage s. Output overvoltage t. Output over current u. System output overloaded v. Load transferred to bypass due to overload w. Overload shutdown x. Control Error y. Critical power supply failure z. Load transferred due to internal protection aa. External shutdown (remote EPO activated) bb. Fan failure cc. Over temperature shutdown impending dd. Over temperature shutdown. ee. Lamp test. c. The UPS logic should provide one set of normally open dry contact / relay output to allow interfacing of UPS operating status to an external system and should be capable of providing, as a minimum, 10 numbers status and, should the UPS manufacturer’s standard product does not provide such software, the bidder must add additional equipment and cost for the same. d. The UPS shall also have an RS485 port with MODBUS interface card if required for interfacing to BAS system or client's centralized computer network. e. LCD touch panel (Optional) i. The UPS shall be provided with an operator friendly large scale LCD touch panel. ii. The LCD touch panel shall also include graphic measurement display, operational procedures of each activity, fault status display and also have capability to record at least 50 faults. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 10. E- 122 iii. The touch screen panel shall clearly define specified areas for operational function, execution and message display. iv. It should be possible to operate the entire UPS system and its components and obtain all measurements and data through the touch screen operation. The measurement software should provide capability to measure phase voltage, current in each phase, frequency, power factor, available battery time etc. v. Under all operating conditions, the system software should have capability for displaying fault alarm automatically. The tenderer should describe in detail the faults that would be displayed under this mode. UPS Testing a. The Contractor shall perform the following tests, as a minimum, at site prior to handing over, to confirm the functional and the performance specification of the UPS as specified. All required test equipment like Digital Oscilloscope, Voltage Regulator, and Measurement Meters etc. shall be the responsibility of the Contractor without any additional cost. b. The Contractor shall demonstrate as a minimum the following features on site by providing all required test equipment, such as power factor improvement, input current THD, output voltage THD, output frequency and all other performance monitoring requirements detailed before as required by the Owner. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 123 Part B: Testing 1.1 General At the completion of the work, the entire installation shall be subject to the following tests in the presence of the Owner’s site representative. Wiring continuity test. Insulation resistance test. Earth continuity test. Earth resistivity test. Test as per Appendix `E' of IS:732 -1989 Besides the above, any other test specified by the local authority shall also be carried out. All tested and calibrated instruments for testing, labour, materials and incidentals necessary to conduct the above tests shall be provided by the Contractor at his own cost. 1.2 Testing Of Wiring All wiring systems shall be tested for continuity of circuits, before installation is energized. 1.3 and earthing after wiring is completed and Insulation Resistance Test The insulation resistance shall be measured between earth and the whole system of conductors, or any section thereof, with all switches closed and except in concentric wiring all lamps in position of both poles of the installation otherwise electrically connected together, a direct current pressure of not less than twice the working pressure provided that it does not exceed 660 volts for medium voltage circuits. Where the supply is derived from AC three phase system, the neutral pole of which is connected to earth, either direct or through added resistance, pressure shall be deemed to be that which is maintained between the phase conductor and the neutral. The insulation resistance measured as above shall not be less than 50 divided by the number of points provided on the circuit; the whole installation shall have an insulation resistance greater than one mega ohms. The insulation resistance between the frame work of housing of power appliances and all live parts of each appliance shall not be less than that specified in the relevant standard specification or where there is no such specification, shall not be less than one a mega ohms. All equipments, cables shall be inspected at works by the Architect as per relevant IS and testing commissioning of installation as per Appendix `E' of IS: 732-1989 shall be done and all record to be maintained. 1.4 Testing Of Earth Continuity Path The earth continuity conductor metallic envelopes of cables shall be tested for electric continuity and the electrical resistance of the same, along with the earthing lead but excluding any added resistance or earth leakage circuit breaker, measured from the connection with the earth electrode to any point in the earth continuity conductor in the completed installation, shall not exceed one ohm. 1.5 Testing Of Polarity Of Non-Linked Single Pole Switch In a two wire installation a test shall be made to verify that all non-lined single pole switches have been connected to the same conductor throughout, and such conductor shall be labelled or marked for connection to an outer or phase conductor or to the non-earthed conductor of the supply. In the three or Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 124 four wire installation, a test shall be made to verify that every non-linked single pole switch is fitted to one of the outer or phase conductor of the supply. The entire electrical installation shall be subject to the final acceptance of the Owner’s site representative as well as the local authorities. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make Part C: Erection, Testing Electrical Installations 1.1 E- 125 & Commissioning Of Scope The intent of this specification is to define the requirements for the installation, testing and commissioning of the electrical system like transformer, M.V panels, Cables, earthing network, Internal and External lighting, Light fixtures etc. Requirement of this project shall be as specified in bill of quantities / approved drawings / general specifications or as per the battery limits fixed by the owner / consultant. 1.2 Standards The work shall be carried out in the best workman like manner in conformity with this specification, the relevant specification / codes of practice of the Indian Standards Institution, approved drawings and the instructions issued by the authorised representative, from time to time. Some of the relevant Indian Standards are listed elsewhere in this tender document. In addition to the standards mentioned in 2.1, all works shall also conform to the requirement of the following: 1.3 Indian Electricity Act and Rules framed there under. Fire Insurance Regulations. Regulations laid down by the Chief Electrical Inspector of the State / State Electricity Board / Union Territory. Regulations laid down by the Factory Inspector of the State / Union Territory. Any other regulations laid down by the local authorities. Installation & operation manuals of original manufacturers of equipment. Equipment, M aterial And Accessories Specifications This defines specifications and requirements mainly for the equipment and accessories, which are generally supplied by the erection agency. All materials, accessories, consumable to be supplied by the contractor shall be selected from the list of specified make of material in consultation with the Client/Architect/Consultant without any extra cost and shall conform to the specification given here under. The equipment shall be manufactured in accordance with current Indian Standard specifications wherever they exist or with the BS or NEC specifications, if no such IS standards are available. In the absence of any specification & if any item not mentioned in the make of the material & anywhere else, the materials shall be as approved by the owner / consultant or his authorised representative in writing manner. All similar materials and removable parts shall be uniform and interchangeable with one another. Makes of bought out items selected by the contractor must be furnished by him as per the pro forma given in elsewhere in this tender document. Tenderer should have to specify the list of makes considered in the tender while quoting the rates in the tender, in covering letter of separate letter enclosure. However, the final decision for accepting make specified by tenderer would be of client/Architect/Consultants. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 126 Within a week of work order, the contractor shall submit the sample of each item / component of above mentioned approved make for the approval of the Client/Architect/Consultant. Bidder to submit authorization letter for supply of light fixtures and lamps only from regional sales manager/director-sales of lighting company with duly signed and stamped with mentioning the name of project, total quantity, type of light fitting etc. The letter should be submitted with valid proof and original documents to consultant. These authorizations are to be obtained prior to supply of material and should be approved by electrical consultant/architect. 1.3.1 Control Cables Control cables for use on 415 V system shall be of 1100 volts grade, copper conductor, PVC insulated, PVC sheathed, armoured and overall PVC sheathed, strictly as per IS: 1554 (Part-I) 1976. Unarmoured cables to be used only if specifically mentioned in schedule of quantities. The size of these cables shall be as specified in bill of quantities or as per approved drawing. The minimum conductor size shall be 2.5 sq.mm. (Cu.). 1.3.2 Cable Trays These shall be channel type, fabricated from structural steel, hot dip galvanised, complete with all accessories such as bends, tees and reducers. Only aluminium flat clamps with G.I. / Chrome plated bolts, nuts/screws to be used for clamping cables. Sizes of these trays shall be as specified in bill of quantities or approved by client. 1.3.3 Cable Glands Cable glands shall be heavy duty compression type of brass, chrome plated. These shall have a screwed nipple with conduit electrical thread and check nut. These shall be suitable for armoured/Unarmoured cables, which are being used. 1.3.4 Cable Connectors Cable connectors, lugs/sockets, shall be of copper/aluminium alloy, suitably tinned, solderless, crimping type. These shall be suitable for the cable being connected and type of function (such as power, control or connection to instruments etc.). 1.3.5 Cable Indicators These shall be self sticking type of 2 mm. thick lead strap for overall cable. PVC identification number, ferrules shall be used for each wire. 1.3.6 G.I. Pipe For Cables For laying of cables under floor, G.I. class “A” pipes shall be used. M.S. conduits are not acceptable for this purpose. All accessories of pipes shall be threaded type. Size of pipe shall depend upon the overall outer diameter of cable to be drawn through pipe. NO G.I. pipe less than 40 MM. I.D. shall be used for this purpose. To determine the size of pipe, assume that 40% area of pipe shall be free after drawing of cable. 1.3.7 Push Button Stations These shall be floor / wall mounted type as specified in bill of quantities. These shall be fabricated from 1.6 mm. thick stainless steel sheets (SS 304). In case of floor mounted station, these shall be supported on 51 mm. “A” class G.I. pipe. Front cover shall be removable type with suitable rubber gaskets to make them dust vermin and moisture proof. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 127 Each feeder shall be provided with “ON” (green) push button, “OFF” (red) push button, name plate (white bakelite), indication lamp etc. Green & red push buttons shall have contact elements having 1NO + 1NC. “OFF” push button shall be provided with lockable (key operated) arrangements to prevent accidental starting. No. of feeders shall be specified in bill of quantities. The indication lamp can be combined with “ON” push button. 1.4 Erection The contractor shall make his own arrangement for safe transportation of all the items to the erection site and also carry out complete loading / unloading during transportation. Equipment shall not be removed from packing cases unless the floor has been made ready for installing them. The cases shall be opened in presence of the client / consultant or his authorized representative. The empty packing cases shall be returned to the stores and any document if found with the equipment shall be handed over to the client's representative. Any damage or shortage noticed shall be reported to the client / consultant in writing immediately after opening of packing cases. 1.5 General Notes For Street Lighting For supplying and laying of cables, technical specification (wiring) shall be applicable reference shall be made under heading Cable Work elsewhere in the tender. For street light poles along roads, nearest finished road level shall be taken as ground level and for poles along compound wall / away from roads, existing ground / finished ground shall be taken as ground level. Distance of 1 mtr. shall be maintained between centre of pole and centre of kerb of road. For compound wall poles, distance between compound wall and poles shall be 3 mtrs. A loop of 1.5 mtr. of cable shall be provided near each street light pole for all incoming and outgoing cable. 1.6 Completion Tests After supply and installation of complete project or a particular building / area, following tests shall be carried out by the contractor before switching on the power to installation and the results shall be recorded and submitted to the Site-Engineer. If results are not satisfactory / as per standards set herewith, the contractor shall identify the defects / short coming and shall rectify the same. Nothing extra shall be paid for carrying out these tests and contractor has to arrange all necessary instruments. 1.6.1 Insulation Resistance To Earth This is to be measured with all fuse links in place, all switches ON, all lamps and appliances in position by applying a voltage not less than twice the working voltage (subject to a limit of 500 V). Insulation resistance of the whole or any part of the installation to earth must not be less than 50 mega-ohms divided by the number of outlets (points and switch positions) except that it need not exceed one mega-ohm for the whole installation. 1.6.2 Insulation Resistance Between Conductors: Tests to be made between all the conductors connected to one pole or phase conductor of the supply and all the conductors connected to the middle wire or neutral or the other pole or phase conductors of the supply. For this test, all lamps shall be removed and all switches put ON. The result of the test must be 50 mega-ohms divided by the number of outlets (points and switch positions) but need not exceed 1 megaohm for the whole installation. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make 1.6.3 E- 128 Polarity Of Single Pole Switches: Tests shall be made to verify that all non-linked single pole switches are on phase conductor (live) and not on neutral or earth conductor. This can be done by connecting test lamps between two terminals of switch and earth. If the lamp lights up when switch is ON and either terminal is touched, the switch is correctly installed. 1.6.4 Resistance Of Metal Conduits / Sheets (Earth Continuity Test): In case of cables encased in metal whether conduit of metallic sheathing, the total resistance of the conduit or sheathing from the earthing point any other position in the completed installation shall not exceed 2 ohms. This can be carried out by following circuit: One end of the load is connected to the ECC and its connection with the electrode and the other to the farthest point of the ECC. First, current through the circuit is measured with the resistance of 2 ohms short circuited by the link. Next, current is measured through the two ohms resistance by disconnecting the two leads from the ECC and joining them together. If current is more in the first case, the resistance of ECC is less than 2 ohms. 1.7 Handing Over / Taking Over: After completion of works and tests specified above, the various installations of the project can be taken over by the employer as and when these are ready in all respects. The defect liability period of 24 months shall start from the date, when all the installations of the project have been executed, tested as described above, successfully commissioned and handed over. The Contractor has to produce the Final As – Built drawings duly signed by Engineer In charge, Consultant, Architect & Client before finalizing the Final bill. The cost for as built drawing to be borne by the contractor. Final bill will not be considered if as built drawings not provided by contractor as following. Process of as built Drawings: 1 set of Hard copy & editable soft copy should be submitted to Engineer In charge. After incorporating the comments received from Engineer in charge Final As built documents as mentioned to be submitted. Final As built documents As built drawings with RTP (Reproducible Tracing Paper). : 1 Set As built drawings with Coloured Print out: 4 Sets Editable Soft Copy of the same: 6 Copies Instruction and maintenance manual - Six copies. Test certificates - Six copies. Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make Part - D: Materials List Of E- 129 Appr oved Make For Electrical S. No. Item Approved Make 1) Rigid PVC Conduit ( FRLS only ) Accessories for conduit Precision Plastic Industries, Nihir, Finolex Flexible Copper Wires (FRLS) Switches R.R. Kable, Finolex Lapp Cable, Avocab, Poly Cab. 2) 3) 4) 5) Use different colour switch Accessories for Raw & UPS Power Main Switch fuse up to 60 Amps - AC 23 duty Same make as of pipe. Legrand (Myrius), Gewiss, MK (Blenze), Schneider (Opale) & Schneider MG, L&T, GE 6) Above 60 Amps-A.C. 23 Duty Schneider MG, L&T, GE 7) HRC Fuses Schneider MG, L&T, GE 8) MCBs/ELCBs/ELMCBs / Contactor Time Switch ( Timer ) Distribution boards IK 43 For TPN & SPN DB Legrand (MDS-lexic), Schneider MG ( Multi 9) For VTPN DB Legrand (Lexic), Schneider MG Factory fabricated. double door type, PPI only with additional JB on both side 10) Rewireable Porcelain Fuse CPL, KEW. 11) Telephone wires Finolex, Delton, RR cable, Avocab, National, Poly Cab. 12) Telephone cables Jelly Filled PVC tape Finolex, Delton, GTCL, National, Avocb, Poly Cab. 14) Main Cables down Stream XLPE armoured cable for 1.1 KV as per ISI 1554. Finolex, Torrent, Avocab, Primecab, RR Kable, Poly Cab. 15) Glands Compression type, Heavy duty and deep threading with rubber ring and double washers. HMI, Raychem 9) 13) Hensel, Spelsberg, Legrand Flexi DB. Steel grip, Anchor Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 130 Sr. No Item Approved Make 16) Cable Lugs Dowells, 3-D, Raychem. 17) Metal Clad Plugs Indoor - MDS, Crompton, BCH. Outdoor -Clipsal, Gewiss, RR PCE, MDS. 18) Connectors Technoplast, Porcelain. 19) Anchor, CPL 20) Button holder, Angle holder, ceiling rose M.S. Conduit ISI 21) Anti vibration Ball Aluminum (sample to be approved). 22) M.S. Boxes Fabricated out of 16 gauge continuously welded (sample to be approved) with Powder coating. 23) Telephone tag block Krone. 24) MCCB With all kind of communication accessories Meter ( Analog Only ) Digital Meter Steel Wire Rain Forced PVC Flexible Hose Schneider MG ( NSX ) , Legrand(MDS) 27) Cable Tray i) Ladder/Perforated - Hot deep GI - Legrand, OBO Better man, Peaton ii) Wired Cable Tray : Legrand, Obo Betterman 28) TV Cable/CCTV Cable Finolex, RR Cable, Avocab. 29) Panel Fabricators Peaton Electric, Schneider, Siemens. 30) Changeover Switch On load type – HPL, C &S, Havell's (Euroload) 31) Fire Extinguisher Should be of ISI approved - Safex,Firex,Safeline 32) D G Set /Alternator with Engine Control Panel Cummins, Caterpillar, Kirloskar, Jackson. 25) 26) BEC, Steel Craft, AKG Rushabh, L &T,Conzerv, Schneider Schneider, Conserve, Secure Meter, L&T Flaxi - Hose Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 131 Sr. No Item Approved Make 33) R G 6 / 11 wire Finolex, RR Kable, Avocab 34) Cat 6 Wire Finolex, RR Kable, Delton, Legrand 35) ACB With all kind of communication accessories UPVC Cable truncking & Under floor trunking Schneider ( Masterpact - 6.0 Micrologic), L & T (U Power - UNRS 2.5GL), Siemens (WL - ETU 75 B), Legrand. Must be EDO type & Microprocessor base only Legrand, OBO Betterman. 37) Call Bell Anchor 38) DIGITAL meters, Load Manager Schneider, Conserve, Secure Meter, L&T 39) Light Fixture 38) Lamps ( As specified in the BOQ & Sample to be approved ) No other make will be allowed other than specified in Tender Philips, Osram 39) Ballast Philips, Vossloh, Tridonics 40) LPI, Ashlok, OBO Betterman. 41) Chemical Type Earthing ( Copper Road only ) Energy Meter 42) CT AE, Ashok, Kappa, C&S 43) DWC Pipe ( Anti Rodent Type Only ) Tirupati Plasto, REX, Duraline 44) 45) 46) Fan PVC Junction Box Contactor Crompton, Usha, Havells, GE, Bajaj Gewiss, Hensel, Spelsberg, OBO Betterman. Telemechanique, L & T, Schneider, Legrand 47) Panel Accessories Telemechanique, L &T, Siemens 48) Emergency Light Sigma 49) Water tight Plugs enclauser Gewiss, Hensel, Spelsberg 50) Compacy Sub Station Schneider, Peaton, Crompton, Areva, Kirlosker, Siemens. 36) L &t, Conserve, Schneider, Secure Meter Consultant : JIT Engineering Services Consultant Sign of Bidder Electrical Works – Specifications and List of Make E- 132 Sr. No Item Approved Make 51) Oil/ Dry type Transformer 52) 54) 55) H T VCB Breaker Capacitor ( MPPH Gas Filled Type ) Thyristors, Reactors Relay Schneider, Voltamp, Kirloskar, Areva, Crompton, BHEL, Danish. Schneider, ABB, Areva, BHEL, Crompton, Siemens L & T, Epcos, Neptune, Electronicon, Ducati, Areva. 56) IPFC Relay Conserve, Secure, Schneider, BCH, Ducati, Electronicon. 57) PLC Schneider, Siemens, ABB, Allen Bradley 58) Surge Protector Emerson, Obbo Betterman 59) H. T. Cable 33 / 33 KV Torrent, Finolex, Nicco, Polycab, Avocab, Gloster, Universal, CCI, Ravin Cab 60) RJ 11 telephone outlet Same make as switch 61) RJ 45 Data outlet Legrand, D Link, Schneider 62) Addressable Fire Detection System Xtralis, OSID, GE, Notifier 63) 64) Access Control System CCTV Schneider (Continuum) / Honeywell / Seimens Pelco, Bosch, Honey well 65) Monitors (Analogue & SVGA) Samsung, HP, Sony 66) P.A. System As specified in tender 67) Amplifier Bosch, Philips, Bose, Aetis, Yamaha 68) UPS Should be on line UPS only HT Cable Jointing KIT Exhaust Fan ( Should be with louvers ) Timers Octagonal / Conical Poles Emerson, APC, DB Power 69) 70) 71) 72) Alsthom, Siemens, Schneider, ABB, L&T. Raychem Usha, Havells, Crompton Theben, Legrand, Schneider Bajaj, BP, Schreder, Wallmont, PIGL Refer Clause no. 1.3 of Part C- Erection Testing, & Commisioning of Electrical Installation before Quoting. Consultant : JIT Engineering Services Consultant Sign of Bidder