Consequences of Switch Shunt on an Unsymmetrical Fault in Power System Chanuan Uakarn1 and Chart Rithirun2 Electrical Engineering Dept, Faculty of Engineering, Kasem Bandit University, Thailand 1 cuakarn@gmail.com 2 chart20052548@yahoo.com Abstract - This paper presents to calculate the magnitude of current, voltage at the bus location of any on the unsymmetrical faults in three-phase power systems. For power system analysis in per-unit, they are on without switched shunt and with switched shunt into the bus and make solved powerflow fault calculation program Power World Simulator PWS-16. The results show the active, reactive and appearance power factor, phase angle in a real time comparison with the solved power flow in accordance with standard IEC-909 without switched shunt in the consequence of switch shunt on an unsymmetrical fault in power system. location. As such the computation of fault current is greatly simplified by the use of sequence networks besides the above controls, the power flow program can be used to investigate the consequence of switching in or out lines, transformers, loads, and generators. Proposed system changes to meet future load growth, including new transmission, new transformers, and new generation can also be investigated. Power-flow design studies are normally conducted by trial and error. Using engineering judgment, adjustments in generation levels and controls are made until the desired equipment loadings and voltage profile are obtained. II. THEORY Keywords - Unsymmetrical Faults, Solved Power Flow, IEC-909, Switched Shunt I. INTRODUCTION Short circuits occur in three-phase power systems are unsymmetrical faults, which may consist of unsymmetrical short circuits, the unsymmetrical faults occur as single line-toground faults, line-to-line faults, double lineto-ground faults, and balanced three-phase faults [1]. The path of the fault current may have either zero impedance, which is called a bolted short circuit, or nonzero impedance. Other types of faults include one-conductor open and two-conductors open, which can occur when conductors break or when one or two phases of a circuit breaker inadvertently open. When an unsymmetrical fault occurs in an otherwise balanced system, the sequence networks are interconnected only the fault Control of power flow: The following means are used to control system power flows: 1. Prime mover and excitation control of generators 2. Control of tap-changing and regulating transformers 3. Switching of shunt capacitor bank, shunt reactors, and static var systems A simple model of generator operating under balance steady-state conditions is the Thevenin equivalent shown in fig. 1. Vt is the generator terminal voltage, Eg is the excitation voltage, δ is the power angle, and Xg is the positive sequence synchronous reactance [2, 3]. International Journal of the Computer, the Internet and Management Vol.23 No.2 (May-August, 2015) pp. 54-59 54 Chanuan Uakarn and Chart Rithirun + Eg = E g δ However, when δ is less than 15o, the increase in P is much larger than the decrease in Q. From the power-flow standpoint, an increase in prime-mover power corresponds to an increase in P at the constant-voltage bus to which the generator is connected. The power-flow program computes the increase in δ along with the small change in Q. Q P + jXg - Vt = Vt 0 0 - Fig 1. Generator the Venin Equivalent Equation (5) shows that reactive power output, Q, increases when the excitation voltage, Eg, increases. From the operational standpoint, when the generator exciter output increases while holding the prime-mover (1) power constant, the rotor current increases. As the rotor current increases, the excitation And the complex power delivered by the voltage, Eg, also increases, causing an increase generator is in generator reactive power output Q. There is also a small decrease in δ required to hold P constant in (4). From the power-flow standpoint, an increase in generator excitation corresponds to an increase in voltage (2) magnitude at the constant-voltage bus to which the generator is connected. The power-flow program computes the increase power Q suppied by the generator along with the small change in δ. (3) The consequence of adding a shunt The real and reactive power delivered are capacitor in the fig. 2 bank to a power system then bus. The system is modeled by its Thevenin equivalent. Before the capacitor bank is connected, the switch, SW, is opened and the (4) bus voltage equals to Eth. After the bank is connected, the switch, SW, is closed, and the capacitor current, Ic, leads the bus voltage, Vt, by 90o.The phasor diagram shows that Vt is (5) larger than Eth when SW is closed. From the power-flow standpoint, the addition of a shunt Equation (4) shows that the real power P capacitor bank to a load bus corresponds to the increases when the power angle δ increases. addition of a negative reactive load, since a From an operational standpoint, when the capacitor absorbs negative reactor power. The prime mover increases the power input to the power-flow program computes the increase in generator while the excitation voltage is held bus voltage magnitude along with the small constant, the rotor speed increases. As the change in δ. Similarly, the addition of a shunt rotor speed increases, the power angle δ also reactor corresponds to the addition of a increases, causing an increase in generator real positive load, wherein the power-flow program power output P. There is also a decrease in computes the decrease in voltage magnitude reactive power output Q, Given by (5). [4, 5, 6]. The generator current is International Journal of the Computer, the Internet and Management Vol.23 No.2 (May-August, 2015) pp. 54-59 55 Consequences of Switch Shunt on an Unsymmetrical Fault in Power System Transformer impedance and admittance: SW + jXth Eth _ Rth + Vt C _ IC IC Eth jXthIC RthIC Vt a) Equivalent Circuit. b) Phasor Diagram with SW Closed. Base power = 100MV; base voltage at bus 1, 3 = 15 kV; base voltage at bus 2, 4, 5 = 345 kV Fault impedance : Fig 2. Consequence of Adding a Shunt Capacitor Bank to a Power System Bus. III. EXPERIMENT A capacitor’s Mvar rating is based on an assumed voltage of 1.0 per unit. V =1.05+j0.0 pu. 3 3 4 T2 80 km. 345 kV 1 Line 3 322 km. 400 kVA 15/345kV 800 MVA 15 kV 345 kV G Line 1 345 kV 400 MVA 15 kV Line 2 G 5 T1 160 km. Open Power World Simulator case study. This case is identical to fig. 4, 5, and 6 except that a 200-Mvar shunt capacitor bank has been added at bus 2. Initially this capacitor is opened. Click on the capacitor’s circuit to close the capacitor and then select Single Solution to solve the case. The capacitor increases the bus 2 voltage from 0.834 per unit to a more acceptable 0.959 per unit. Notice that the amount of reactive power actually supplied by the capacitor is only 184 Mvar. This discrepancy arises because capacitor’s reactive varies with the square of the terminal voltage, V =1.0+j0.0 pu. 1 1 2 800 kVA 345/15 kV Bus 2 2 200 MVAR 80 MW+j40 MVAR 800 MW+j280 MVAR Fig 3. This Five-Bus Power System is Modeled in Fault Calculation. Power: The figure shows a single-line diagram of a five-bus power system. Input data is given in following: Bus voltage: and Line impedance and line admittance: As shown in Fig. 3 at bus 1, to which a generator is connected, it is the swing bus. Bus 1, to which a generator and a load are connected, is a voltage-controlled bus. Buses 2, 4, and 5 are load buses [1]. The elements of [Ybus] are computed from Fig. 3. Since buses 1 and 3 are not directly connected to bus 2, Mutual admittance: , International Journal of the Computer, the Internet and Management Vol.23 No.2 (May-August, 2015) pp. 54-59 56 Chanuan Uakarn and Chart Rithirun , One -37 Mvar , Five Four One Five A Four MVA Three A MVA 160 Mvar 1.005 pu -4.432 Deg A A MVA MVA 1.036 pu -2.685 Deg MVA 1.050 pu -0.415 Deg 1.005 pu -4.432 Deg A A MVA MVA 1.036 pu -2.685 Deg 80 MW 40 Mvar 1.050 pu -0.415 Deg 0.959 pu -19.779 Deg Two 0.0 Mvar Fig 4. This Five-Bus Power System is Modeled in Power World Simulator Case without Switch Shunt. One A Five Four MVA A Three slack 1.000 pu 0.000 Deg A A MVA MVA 1.000 pu 0.000 Deg Fig 6. This Five-Bus Power System is Modeled in Load Condition in Power World Simulator Case with Switch Shunt. TABLE I POSITIVE AND NEGATIVE SEQUENCE 160 Mvar MVA 1.000 pu 0.000 Deg 184.0 Mvar 520 MW MVA A -36 Mvar 800 MW 280 Mvar This five-bus power system is modeled in Power World Simulator case fig. 4 and 5. For larger networks, most of the elements of the elements of the [Ybus] can be saved in a Matlab Format file by first right clicking within the Ybus matrix to display the local menu, and than selecting “Save [Ybus] in Matlab Format” from the menu. Finally, notice that no flows is showing on the one-line, because the nonlinear power-flow equations have not yet been solved. We cover the solution of these equations next in Table I, II. 800 MW 280 Mvar 385 MW Two Where half of the shut admittance to bus is included in Y22 (the other half is located at the other ends of these lines). 160 Mvar slack 1.000 pu 0.000 Deg 80 MW 40 Mvar 520 MW A -36 Mvar 520 MW slack 0.959 pu -19.779 Deg 385 MW Three MVA , , Determine the consequence of adding a 200 Mvar shunt capacitor bank at bus 2 on the power system in the fig. 4, 5, and 6. A MVA A 1.000 pu 0.000 Deg Self admittance: A MVA 385 MW 1.000 pu 0.000 Deg 80 MW 40 Mvar 1.050 pu 0.000 Deg Two 800 MW 280 Mvar 200.0 Mvar Fig 5. This Five-Bus Power System is Modeled in Initial Condition in Power World Simulator Case with Switch Shunt. International Journal of the Computer, the Internet and Management Vol.23 No.2 (May-August, 2015) pp. 54-59 57 Consequences of Switch Shunt on an Unsymmetrical Fault in Power System TABLE II ZERO SEQUENCE Fig 9. IEC-909, Fault Calculation (+Zero Sequence) without Switched Shunt Fig 7. Solved Power-Flow Fault Calculation without Switched Shunt. Fig 10. IEC-909, Fault Calculation (+Zero Sequence) with Switched Shunt IV. CONCLUSIONS The results are from the test bus standard 5 bus Power World Simulator case to calculate the current fault Asymmetry. Compared to having switched shunt and not having switched shunt when the fault in a differentiation in power system of Fig. 7, 8, 9, and 10, respectively. According to the requirements of IEC-909 program, PWS 16 is used to find short-circuit current value. Open circuit and current asymmetry have the correct value and fast. The analysis of power systems determine the CT, PT, precisely to prevent power system, Electrical system will be stable. Fig 8. Solved Power-Flow Fault Calculation with Switched Shunt. International Journal of the Computer, the Internet and Management Vol.23 No.2 (May-August, 2015) pp. 54-59 58 Chanuan Uakarn and Chart Rithirun REFERENCES (Arranged in the order of citation in the same fashion as the case of Footnotes.) [1] [2] [3] [4] [5] [6] Grainger, J.J. and Stevenson, W.D. (1994). “Power System Analysis”. McGraw-Hill Book Co. Anderson, P.M. (1999). “Power system protection”. McGraw-Hill. Dommel, H. (1986). “Electromagnetic Transient Program”. BPA, Portland, Oregon. Eriksson, L., Saha, M.M., and Rockefeller, G.D. “An accurate fault locator with compensation for apparent reactance in the fault resistance resulting from remote-end infeed”. IEEE Trans. on PAS, Vol.PAS-104, No.2, February 1985, pp. 424-436. Saha, M.M., Izykowski, J., Rosolowski, E., and Kasztenny, B. “A new accurate fault Locating algorithm for series compensated lines”. IEEE Transactions on Power Delivery, vol.14, no.3, July 1999, pp. 789-797. Das, J.C. (2002). “Power System Analysis: Short-Circuit Load Flow and Hamonics”. Marcel Dekker, Inc. International Journal of the Computer, the Internet and Management Vol.23 No.2 (May-August, 2015) pp. 54-59 59