PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO. 220-221, SECTOR 34-A, CHANDIGARH Petition No. 30 of 2012 Date of Order: 12.11.2012 In the matter of : Petition under Section 86(1)(f) of the Electricity Act, 2003 in relation to disputes arising under the PPA dated 18.01.2010 between the petitioner herein – Nabha Power Limited and Punjab State Power Corporation Limited (PSPCL), a successor entity of the Punjab State Electricity Board (PSEB) - 2x700 MW Rajpura Thermal Power Project being executed by Nabha Power Limited under the PPA dated 18.01.2010 - Changes in the Mega Power Policy, 2006 and the Foreign Trade Policy, 2009 – 2014 and the corresponding claims of the parties under Article 13.1 of the PPA dealing with „Change in Law‟ provision. AND In the matter of 1. Nabha Power Limited, SCO 32, Sector 26-D, Madhya Marg, Chandigarh -160019. 2. L & T Power Development Limited, Powai Campus, Gate No.1, C Building, 1st Floor, Saki Vihar Road, Mumbai – 400072. Versus Punjab State Power Corporation Limited, Patiala Present: Smt.Romila Dubey, Chairperson Shri Virinder Singh, Member Shri Gurinderjit Singh, Member ORDER Nabha Power Limited (NPL), the petitioner No.1, is a company incorporated under the Companies Act, 1956, for Thermal Power Project (Project) at developing the Rajpura village Nalash, near Rajpura, District Patiala. L & T Power Development Limited and the petitioner No.2 is also a company, which participated in competitive bidding under Case 2 for development of the project and emerged as successful bidder. The petitioners 1 have filed this petition under Section 86(1)(f) of the Electricity Act, 2003 (Act) in relation to disputes arising out of Power Purchase Agreement (PPA) dated 18.01.2010 between NPL and Punjab State Power Corporation Limited (PSPCL). 2. The case of the petitioners is that : (i) The erstwhile PSEB (now succeeded by PSPCL and PSTCL after unbundling on 16.4.2010) invited competitive bids on 10.06.2009 under Section 63 of the Electricity Act 2003 through NPL, then a Special Purpose Vehicle (SPU) as its authorized representative for development of the project and procurement of power on long term basis. (ii) Pursuant to the bids, petitioner No.2, was the successful bidder. Petitioner No.2 acquired NPL, as per terms of the bid documents. NPL and PSPCL signed PPA dated 18.01.2010. (iii) The petitioners have submitted that petitioner No.2 had considered fiscal benefits under two policy regimes i.e. under the Foreign Trade Policy 2009-14 (“FTP”) and Mega Power Policy 2009 (“Mega Policy, 2009”) before submitting its bid for development of the Project. Under FTP the following benefits were available: (a) Advance Authorization / Advance Authorization for annual requirement / Duty free import Authorization (“DFIA”) ; (b) Deemed Export Drawback ; (c) Exemption from terminal excise duty (“TED”) where supplies are made against International Competitive Bidding (“ICB”). In other cases (supplies not against ICB), refund of TED is to be given. As regards Mega Policy, 2009, the petitioner has submitted that the Union Cabinet‟s decision to modify Mega Policy 2006, removing the condition of selling power to two or more states of Thermal Projects of 1000 MW or more capacity to be eligible for 2 benefits under the policy was taken on 01.10.2009 and was reported in Press Information Bureau (PIB) on 01.10.2009 whereby the Project became eligible as Mega Power Project (MPP) for the benefits under Mega Policy 2009. (iv) RfP provided that quoted tariff shall be an inclusive tariff and bidder was to take into account all costs including taxes and duties. (v) The petitioners have further submitted that similar fiscal benefits were concurrently available under FTP irrespective of the Project being MPP or Non-MPP. (vi) The petitioners have submitted that decision of Union Cabinet was taken and reported on 01.10.2009, eight (8) days before the last date for submission of bids which was 09.10.2009. The petitioner No.2 requested for extension of bid deadline vide letter dated 02.10.2009 on account of „recent changes‟ in Mega Policy, 2006. The petitioner No.2 again submitted letter dated 06.10.2009 which stated that bid was being submitted in the light of changes approved by the Union Cabinet. Thereafter Department of Revenue, Ministry of Finance, Govt. of India, amended the Principal Customs Notification No.21/2002 dated 01.03.2002 vide Notification No.137/2009 – Customs dated 11.12.2009 (Custom Amendment Notification) exercising its powers under Section 25 of the Customs Act, 1962, whereby eligibility criteria for Mega Power Project under Entry 400 was amended. Prior to the amendment, a project to qualify as MPP was required to have an inter-state sale of power, which condition was removed vide notification dated 11.12.2009 for thermal power plants with capacity of 1000 MW or more. Thereupon an office memorandum dated 14th December 2009 on revised Mega Power Project policy was issued by Ministry of Power, Govt. of India. (vii) The petitioners have further submitted that petitioner No.1 (NPL) signed a contract with M/s Larsen & Toubro Limited on EPC basis which included supply of thermal power generation equipment. 3 Larsen & Toubro Limited had in turn entered into a contract with Larsen & Toubro MHI Boilers Ltd. to import the goods. For availing concessional custom duty available for MPP, the order for the concessional customs duty certificate was required to be issued to the Customs Authorities at Mundra Port by the Principal Secretary, Department of Power, Govt. of Punjab. Accordingly, the Engineer-in-Chief No.NPL/SKN/PSPCL-070 PSPCL dated was 24.01.2011 requested enclosing vide MPP certificate for the Project issued by MoP, GoI, vide letter dated 30.07.2010 to recommend the case to GoP for issuance of necessary orders. (viii) The respondent PSPCL replied vide letter dated 04.02.2011 and requested NPL to provide : (a) copies of all the contracts along with their amendments in terms of which goods for the Project are to be imported ; (b) an affidavit indemnifying the Respondent against adverse consequences arising out of wrong claim of benefits (if any) by the Petitioner No.1 for the Project in the enclosed format ; and (c) an affidavit stating that the benefits of mega status granted to the Project will be passed on to the Respondent as per Article 13.3 of the PPA in the enclosed format. The petitioner No.1, NPL, replied vide letter dated 17.02.2011 and provided documents as requested at (a) & (b) but in relation to (c) above the NPL stated that it had already factored in the benefits available to a MPP in its quoted tariff in the bid in view of Union Cabinet decision dated 01.10.2009 and therefore there was no basis for submission of affidavit to ensure passing on such benefits to PSPCL at the future date. (ix) The respondent PSPCL again asked NPL vide letter dated 04.03.2011 to submit affidavit mentioned at (c) of para (viii) above because MPP status was not available to the Project at the time of 4 submission of bids. The petitioner replied vide letter dated 10.03.2011 and submitted relevant contracts as demanded by PSPCL in its letter dated 04.03.2011 along with the affidavit indemnifying PSPCL against adverse consequences but did not agree to submit the affidavit undertaking to pass on the custom duty benefits available to MPP. PSPCL refused to accept the explanation of NPL and reiterated its request vide letter dated 28.03.2011 to furnish the affidavit on the format already supplied. NPL again requested PSPCL not to hold up the recommendation to the GoP for issuance of Essentiality Certificate vide letter dated 07.04.2011 as the consignment of imported equipment for project was due by mid April 2011. (x) PSPCL vide letter dated 20.05.2011 to NPL conveyed that Project was granted the mega power status vide Ministry of Power‟s letter dated 30.07.2010 post issuance of Mega Policy 2009 by way of Office Memorandum dated 14.12.2009 and hence „Change in Law‟ provision under Article 13 of the PPA was applicable. The benefits had accrued to the Project after submission of the bid and as such NPL was required to pass on the benefits to PSPCL in terms of formula set out at Article 13.2(a) of the PPA. The petitioner No.1 and respondent reiterated their position on the issue vide letter No.NPL/CE/PSPCL/022 dated 23.05.2011 and No.4726/27/DPT-97 dated 23.05.2011 respectively. (xi) The Department of Power, Govt. of Punjab vide letter dated 16.06.2011 issued the Essentiality Certificate for first consignment for the Project. The Department of Power allowed the entry of goods at concessional customs duty subject to the right of PSPCL to seek appropriate reduction in tariff on account of decrease in the capital cost of the Project in terms of Article 13 of the PPA dated 18.01.2010. After exchange of further correspondence, the Department of Power, Govt. of Punjab issued Essentiality Certificate for further consignments to Custom Authorities vide 5 letter dated 13.12.2011 on identical conditions as issued vide letter dated 16.06.2011 and has allowed the entry of goods at concessional custom duty subject to the right of PSPCL to seek reduction in tariff on account of decease in capital cost of the Project under Article 13 of the PPA. 3. The petitioners have also submitted an alternative prayer to declare that the petitioners shall be entitled to claim „Change in Law‟ against respondent‟s claim under „Change in Law‟ (Article 13 of PPA) due to Mega Policy 2009, on the basis of withdrawal of fiscal benefits allegedly available o the petitioners under FTP. Here the case of the petitioner is as under:(i) Similar fiscal benefits were available to the Project under FTP at the time of bidding regardless of the status of the Project under Mega Power Policy, which was withdrawn by relevant GoI authorities subsequent to change in Mega Policy 2006 vide Mega Policy 2009. Therefore the petitioners have also a claim under „Change in Law‟ provision under Article 13 of the PPA. (ii) Under the prevailing FTP effective from 27.8.2009 upto 31.03.2014 the benefits were available to the „Deemed Exports‟ i.e. those transactions in which goods supplied do not leave India and payment for such supplies is received either in Indian rupee or in free foreign exchange. Para 8.2 of the FTP specifies the categories of supply which are regarded „Deemed Exports‟ provided such goods are manufactured in India. Setting up of power plant is covered under the definition of „manufacture‟. Accordingly petitioner No.2 has submitted that fiscal benefits were available to Non-MPP under FTP on the date of bidding in terms of para 8.3 of FTP, which provides that any or all of benefits were available to manufacturer and supply of goods qualifying as „deemed exports‟ as under : (a) Advance Authorization / Advance Authorization for annual requirement / DFIA ; (b) Deemed Export Drawback ; 6 (c) Exemption from TED where supplies are made against International Competitive Bidding (ICB). In other cases (supplies not against ICB), refund of TED is to be given. (iii) The petitioners have submitted that following benefits were available to Non-MPP, in terms of paragraph 8.3 of the FTP: (i) Customs duty benefits under para 8.3 (a) or 8.3 (b) were available as under 8.3 (a) no custom duty was payable whereas under 8.3 (b) & (c) the TED was refundable. (iv) At the time of bidding, the Director General of Foreign Trade (DGFT) was actually granting refund of Terminal Excise Duty (TED) both through direct and draw-back routes. On this basis, Non-MPP developer could have considered that refund of TED would be available for the Project. (v) The petitioner No.1 had sought the opinion from BMR Mumbai and Ernest & Young Private Ltd. Ahmedabad which had confirmed that benefits available to MPP and non-MPP on bid submission date was identical. (vi) The petitioner No.1, took up the matter vide letter dated 27.01.2012 with the respondent stating that at the time of bidding, the Project was entitled to identical benefits under Mega Policy 2009 and the FTP 2009-14 as FTP benefits were available till the recent changes. „Change in Law‟ claim on basis of FTP was made by the petitioner No.1 in view of „Change in Law‟ claim by the respondent on basis of Mega Power Policy 2009. The petitioner No. 1 requested respondent to revisit the case and consider the claim of the petitioner No.1 under „Change in Law‟ provisions on the basis of withdrawal of fiscal benefits available to the petitioners under FTP against accrual of claim to the respondent under Mega Power Policy, 2009. The respondent replied vide letter dated 12.03.2012 stating therein that there had been no „Change in Law‟ effected by DGFT to the FTP provisions and that the Project could not have availed TED or custom duty benefits unless and until the Project qualified to 7 have a MPP status which was actually granted to it by the Ministry of Power on 30.07.2010. (vii) The petitioners have however submitted that after the award of Project and signing of PPA, Policy Interpretation Committee (PIC) vide its meeting No.10/AM 11 held on 15.03.2011 issued clarification regarding application of para 8.3 (b) and 8.3 (c) regarding draw-back and refund of TED to a non-Mega Power Project and held that same was not available for non-Mega Power Project. Thereafter DGFT circulated letter No.01/12/180/AM 05 PC VI PF/18 dated 27/28 April, 2011 to give effect to the decision of PIC. The petitioners submitted that benefits to the Project were therefore available prior to 27/28.4.2011. 4. In view of above submissions made in the petition, the petitioner made following prayer : (a) to declare that the Union Cabinet‟s decision dated 01.10.2009 modifying the Mega Policy 2006 reported vide Press Information Bureau on the same date does not amount to „Change of Law‟ under Article 13 of the PPA ; (b) following the declaratory relief sought by the Petitioners, to hold that consequential relief as set out under Article 13.2 of the PPA has not triggered and no consequential benefits under Article 13 have to be passed on to the Respondent by the Petitioner under the PPA on account of Union Cabinet‟s decision to change the Mega Policy 2006 dated 01.10.2009; (c) In alternative, if reliefs sought under para (a) and (b) above are not granted, then to direct and allow that the Petitioners shall be entitled to claim „Change in Law‟ against the Respondent‟s claim on the basis of withdrawal of fiscal benefits which were available to the Project under the FTP on the date of bidding on standalone basis, without considering Mega Policy, 2009 ; (d) award cost in favour of the Petitioners ; 8 (e) pass such other and further Commission may deem orders / directions as the appropriate in the facts and circumstances of the case. 5. PSPCL filed reply to the petition vide C.E./ARR & TR memo No.5613 dated 25.07.2012 and submitted that there was no merit in the petition. Brief submissions of PSPCL were as under:(i) Cut-off date of bid was 02.10.2009. Notification for Mega Power Policy, 2009 under which the Project got status as MPP was issued by Ministry of Power, Government of India on 11.12.2009. The fiscal benefits of Mega Power status was not available on the cut-off date and therefore „Change in Law‟ claim is required to be passed on to PSPCL by way of reduction in tariff benefiting the consumers at large. (ii) PSPCL submitted that the petitioners claim that such „Change in Law‟ had occurred prior to cut off date on account of Press Release by PIB dated 01.10.2009, a day before cut off date of bid and was accounted for in the bid by the petitioner No.2, was wrong. After statutory Notification was issued on 11.12.2009 when terms and conditions for grant of Mega Power status were notified, the other notifications giving reduction and remissions from duties were issued subsequently. Each of above were much after the cut off date for bids (i.e. 2.10.2009) hence benefits under „Change in Law‟ under Article 13 of PPA, were required to be passed on to PSPCL, by way of tariff reduction. As per Notification dated 11.12.2009, a number of conditions were required to be fulfilled by Govt. of Punjab so as to make a non-MPP eligible for MPP status under Mega Power Policy, 2009, These conditions were fulfilled by Government of Punjab only on 16.4.2010 by unbundling of erstwhile PSEB into PSPCL and PSTCL. At the time of issue of bid documents and submission of bids, the proposed Project was under prevalent legal framework for concessions and incentives under Mega 9 Power Policy, 2006. Bids were submitted by bidders including petitioner No.2 on 09.10.2009 when the prevalent policy of Government of India was Mega Power Policy 2006, notified on 02.08.2006, which did not recognize the Project of the kind which was subject matter of the bid to be a Mega Power Project (MPP). (iii) „Law‟ is defined in the PPA as „all Laws including Electricity Laws in force in India and any statute, ordinance, regulation, notification or code or rule or any interpretation of any of them by an Indian Government Instrumentality‟. Clearly „Change in Law‟ would occur through change in any of these. The press release by the Government providing for the proposal to amend Mega Power Policy is not law within the meaning of definition of law given in PPA. Press release does not even mention the terms and conditions for Mega Power status. Subsequent to press release dated 01.10.2009 Govt. of India issued Memorandum dated 14.11.2009 and circulated the same ; various conditions to be fulfilled, the process to be adopted and details to claim the benefits of Mega Power Policy were provided for in the Memorandum. Thereupon the Government of India issued a communication dated 03.12.2009 to all States and U.Ts specifying the Distribution Reforms required to be undertaken in order for a generating company selling power to the State to be eligible for MPP status. (iv) The Customs Notification under Section 25 of the Customs Act, 1962 was issued by Govt. of India on 11.12.2009. Only this Notification has the force of Law. Even on this date Project was not eligible for benefits under the notified Policy, as the requisite Distribution reforms which was condition to be fulfilled had not been yet carried out by the State of Punjab. This condition was fulfilled through Govt. of Punjab Notification of the Transfer Scheme Rules, 2010 dated 16.04.2010 under Section 131 of the 10 Electricity Act, 2003, unbundling the erstwhile PSEB into PSPCL and PSTCL. (v) Only after this, petitioner No.1 submitted application dated 11.05.2010 to Ministry of Power, GoI, for granting MPP status to the Project. Thereafter MPP status was granted by Govt. of India to the Project on 30.07.2010. As such „Change in Law‟ occurred much later after cut off date of 2.10.2009 (seven days before last day of submission of bids) under Article 13 of PPA. (vi) PSPCL has further submitted that contention of the petitioners that under Foreign Trade Policy 2009-2014 identical benefits were available under law de-hors the Mega Power Policy, which were withdrawn vide clarifications by PIC dated 15.03.2011 and clarification dated 28.12.2011 issued by the Director General of Foreign Trade (DGFT) was baseless and misconceived. In the Policy Interpretation Committee (PIC) meeting held on 15.03.2011, it was clarified that under FTP 2009-14, the benefits of refund of Terminal Excise Duty (TED) were not available to non-Mega Power Projects. The communication of DGFT dated 27/28.04.2011 states as under :“(iii) Regarding refund of Terminal Excise Duty (TED) for supplies to non-mega power projects, it was clarified that para 8.4.4 (iv) of Foreign Trade Policy, 2009-14 clearly stipulates that benefits of refund of TED under para 8.3 (c) of the policy is not available for such supplies. In such cases excise duty paid at the terminal stage of supply (last instance of excise duty paid in the chain of manufacture process in supply) is not to be refunded in any manner including as drawback [para 8.3 (b) of Policy]”. The clarificatory nature of the circular dated 27/28.04.2011 of the DGFT is evident from para 3 of the same. The reliance of the 11 petitioners on a clarificatory policy circular issued by DGFT to contend that benefits were earlier available to non-Mega power placed is totally misplaced. (vii) PSPCL denied that the Cabinet Meeting decision and its press release by PIB on 01.10.2009 by itself amounted to „Change in Law‟ and Mega Power Policy stood amended on that date. (viii) PSPCL submitted in its reply that in view of circumstances explained in the reply, there was no merit in the petition and same was liable to be dismissed with exemplary costs. The respondent, PSPCL, was entitled to the benefits of the Mega Power Policy being granted to the petitioner No.1, by way of „Change in Law‟ under Article 13 of the PPA dated 18.1.2010. 6. (i) The petitioners filed rejoinder to the reply of the respondent (PSPCL) vide Reference dated 07.09.2012 and inter-alia submitted that the powers vested in Govt. of India (GoI) are exercised by the Union Cabinet through various fiscal policy formulations such as Mega Power Policy. In case goods are meant for use in development of particular class of Power Projects such as Mega Power Project (MPP), the exercise of power takes the shape of policy. Once the Mega Power policy was formulated / amended by the Union Cabinet, the issuance of consequent notifications under respective Acts to carry out the mandate of the Mega Power Policy by providing necessary exemptions / remissions for MPPs, was only a ministerial job. Once the Union Cabinet had taken up the decision to approve modifications and adopt changes in the then existing Mega Power Policy 2006 on 01.10.2009, the concerned ministries were bound by that decision and were inevitably required to effect that decision of the Union Cabinet being final authority to approve changes. Hence the decision modifying policy so as to allow projects supplying power to only one State to get all fiscal benefits taken by the Union Cabinet provided sufficient legal 12 basis for the petitioner No.2 to arrive at a conclusion that project shall be eligible for benefits under such modifications in the Mega power policy. As per the petitioners „adoption‟ of law is included in term „Change in Law‟ under Article 13.1.1 of the PPA. The petitioners have submitted decision of Union Cabinet amounts to adoption of the changes / modifications. The petitioners have further submitted in the rejoinder that PSPCL can not rely on issuance of subsequent instruments to raise „Change in Law‟ claim since the situation brought into effect by these subsequent instruments such as notifications by the Ministries had not altered the legal position. The petitioner No.2 considering the eligibility for exemption available to a MPP in view of Union Cabinet decision dated 01.10.2009 had factored in the available benefits under Mega Policy 2009 while submitting its bid and as such the benefits available to a MPP had already been passed on to the respondent in the form of lowest tariff in the bid by the petitioner No.2. RFP provided that the bidders are required to familiarize with all the acts, laws, rules and regulations prevailing at the time of bid. The petitioner No.2 was, therefore, fully justified in taking cognizance of the decision of the Union Cabinet before submission of the bid. (ii) As regards the availability of benefits under Foreign Trade Policy (FTP), the petitioner has submitted again in the rejoinder that identical benefits were available to the Project on the date of bidding irrespective of the fact whether the Project was a MPP or non-MPP and the petitioner No.2 considered the benefits from the perspective of Mega Power Policy, 2009 The petitioners have submitted that benefits available under FTP were withdrawn after submission of bids by DGFT. The petitioners submitted at the first place no benefits have to be passed on to PSPCL under Article 13 of the PPA as the change in Mega Power Policy, 2006, took place on 01.10.2009, 8 days prior to bid deadline ; however, if it is to be held that change in 13 policy amounts to „Change in Law‟ under PPA, then in view of FTP regime prevailing prior to the submission of bids, there was no economic impact due to „Change in Law‟. On account of withdrawal of benefits under FTP, the petitioners have also a similar claim under „Change in Law‟ as per Article 13 of the PPA. In the rest of the rejoinder the petitioners have made submissions in respect of FTP to establish that the fiscal benefits to the non-MPPs such as this Project were available. 7. The arguments on behalf of the petitioners and respondent were heard in detail on 11.09.2012 and after hearing the arguments, both parties were directed to submit written submissions by 26.09.2012 vide Order dated 13.09.2012. With regard to Mega Power Policy the petitioners filed written submissions vide Ref: NPL/PSERC/30/005 dated 26.09.2012. The petitioners supported their contention that Union Cabinet decision to amend Mega Power Policy was conclusive in itself by citing decisions of Hon‟ble Supreme Court in case of Rai Sahib Ram Jawaya Kapoor and others Vs. State of Punjab (1955) 2 SCR 225 and R.K.Jain Versus Union of India and others (1993) 4 SCC 119. They further relied upon the decision of the Division Bench of the High Court of Gauhati in the case of Union of India and Ors V. Shree Ganapati Rolling Mills (P) Ltd. and Ors 2006 (4) GLTI, decision of Hon‟ble Punjab and Haryana High Court in Nestle India Limited and Anr. Vs State of Punjab and Ors (1998) 120 PLR 367 and Hon‟ble Supreme Court decision in the case of State of Bihar and Ors V. Suprabhat Steel Ltd. and Ors. (1999) 1SCC 31 and decision in the case of State of Jharkhand v. Tata Commins Ltd. and Anr., (2006) 4SCC 57. 8 (i) PSPCL filed written submissions dated 01.10.2012. PSPCL reiterated that the project of the petitioners became entitled to the mega power status only under and after the notification dated 11.12.2009 of Ministry of Power, Govt. of India well after dead line for submission of the bids under the bidding documents issued by erstwhile PSEB (now PSPCL). 14 Respondent PSPCL gave the detail of dates of each event in chronological order to establish their contention that MPP status to the Project was granted on later date much after the last date for submission of bids. PSPCL submitted that the petitioners made no representation during process of bidding that they would be entitled to Mega Power status as per revised decision of Union Cabinet and Press Release dated 01.10.2009. (ii) PSPCL also submitted that alternative claim de-hors the Mega Power Policy under Foreign Trade Policy (FTP) which according to petitioners was subsequently withdrawn vide PIC clarification dated 15.03.2011 and DGFT clarification dated 27/28.12.2011 and hence they were entitled to benefits under „Change in Law‟ was baseless and misconceived. PSPCL submitted that as per clause 8.2, sub-clauses (d), (e), (f) and (g) and clause 8.3 – sub-clauses (a), (b) and (c) and clause 8.4.4(i)(f) and clause 8.4. 4 (iv), taken together, it was clear that benefits of exemption from terminal excise duty (TED) was available only to the Mega Power Projects and not to the non- Mega Power Projects. At the time of submission of bids, the petitioners „ project admittedly was not a Mega Power Project and also did not fulfill the conditions entitling it to the benefits under FTP. PSPCL submitted in its written submissions dated 01.10.2012 that there was no merit whatsoever in the present petition filed by the petitioners and the same was liable to be dismissed with exemplary costs. The respondent and consequently consumers in the State were entitled to the benefits of „Change in Law‟ namely the Mega Power Project status available to the petitioners‟ Power Project. 9. The matter was further argued by the counsels on behalf of the petitioners and respondent. The counsel for the petitioners filed a copy of the Judgement dated 30.06.2006 of the High Court of Gauhati in the case of Union of India and Others Versus Shri Ganpat Rolling Mills (P) Ltd. 15 and Others. A compilation consisting of a copy of chapter 8 (Deemed Exports) of Handbook of Procedure (Vol 1), copy of one of the Refund Orders, copy of Minutes of Meeting dated 15.03.2011 of Policy Interpretation Committee (PIC), copy of DGFT letter dated 27/28.04.2011, DGFT amendment Notification dated 28.12.2011 and DGFT Notification dated 21.03.2012 was filed. Counsel for the respondent filed copy of Judgement dated March 12, 2003 in Civil Appeal No.5982 of 2001 in the case of J.P.Bansal versus State of Rajasthan and Another in support of arguments on behalf of respondent. After arguing the case at length on 03.10.2012, the Counsels of the petitioners and respondent submitted that they would file supplementary written submissions in addition to the written submissions already filed by them. The Commission vide Order dated 08.10.2012 directed that Comprehensive Written Submissions shall be filed by the petitioners and respondent by 15.10.2012. 10. Comprehensive Written Submissions were filed by respondent vide C.E./Thermal Designs memo No.6773 dated 15.10.2012. After re-iterating the written submissions dated 01.10.2012 already filed by respondent, it was further submitted that Section 25(1) of the Custom‟s Act, 1962, contemplate issuance of specific notification and its publication in the official Gazette of GoI as the mode for bringing into effect any exemption. In the present case the notification having been published only on 11.12.2009, there can be no question of the petitioners claiming any amendment to the law and any benefit of Customs duty exemption being available under the law at any time prior to 11.12.2009. The respondent relied upon the decisions of Hon‟ble Supreme Court in the following cases : a. Gujrat Urja Vikas Nigam Limited v. Essar Power Limited (2008) 4 SCC 755. b. B.K.Srinivasan v. State of Karnatka (1987) 1SCC 658. c. J.P.Bansal v. State of Rajasthan and Another, (2003) 5SCC 134 d. Bimla Nand Prasad and Others v. State of Bihar & Others 1994 Supp (3) SCC 753. 16 PSPCL further submitted in the Comprehensive Written Submissions that reliance of the petitioners on the Judgment of Hon‟ble High Court of Guwahati in Union of India v. Shri Ganpat Rolling Mlls Pvt Limited (2006) 3 GLR 586 does not help the case of the petitioners as the Judgement deal with a case of Promissory Estoppel and equitable relief stands on different considerations. PSPCL submitted with regard to applicability of FTP that the very fact that the petitioners actually claimed benefits under Mega Power Policy and not under FTP, which according to the petitioners was in existence prior to the bidding, establishes beyond doubt that alternate plea under FTP was an after-thought. PSPCL re-iterated that PSPCL and consequently consumers of the State are entitled to benefits under Mega Power Policy, 2009. 11. The petitioners filed written submissions vide NPL/PSERC/30/007 dated 15.10.2012 and maintained that Union Cabinet‟s Policy decision to modify Mega Policy 2006 was conclusive and actionable. The petitioners quoted from Press Information Bureau Manual issued under Right to Information Act, 2005 regarding sanctity of the reporting done by PIB, considering which the petitioner No.2 had all the reasons to have acted upon the Union Cabinet‟s policy decision dated 01.10.2009. The petitioners in the written submissions dated 15.10.2012 cited number of Judgements giving gist of Facts and Judgements of the cases to advance their arguments. The petitioners emphasis remained that Notification issued pursuant to an actionable policy decision can not go against such policy decision. However if such Notification is contrary to the policy decision, same is liable to be set aside. The petitioner re-iterated that identical benefits were available to the Project under Mega Power Policy and Foreign Trade Policy. After considering the written submissions filed by the petitioners and respondent, the Commission decided to close further hearing of the petition vide Order dated 01.11.2012. The Order was reserved. 17 12. After going through the petition, reply, rejoinder, written submissions and arguments filed by the petitioners and the respondent and hearing the parties on their respective submissions, the Commission, with regard to the prayer of the petitioners, proceeds to give its observations, findings and decision in the matter hereunder: Prayer: The petitioners have prayed as under: (a) declare that the decision of the Union Cabinet dated 01.10.2009 modifying the Mega Power Policy 2006 reported vide Press Information Bureau on the same date does not amount to „Change in Law‟ under Article 13 of the PPA; (b) following the declaratory relief sought by the petitioners, hold that consequential relief as set out under Article 13.2 of the PPA has not triggered and no consequential benefits under Article 13 have to be passed on to the respondent by the petitioner under the PPA on account of Union Cabinet‟s decision dated 01.10.2009 to change the Mega Power Policy 2006; (c) in alternative, if reliefs sought under para (i) and (ii) above are not granted, then to direct and allow that the petitioners shall be entitled to claim „Change in Law‟ against the respondent‟s claim on the basis of withdrawal of fiscal benefits which were available to the Project under the Foreign Trade Policy on the date of bidding on standalone basis, without considering Mega Power Policy, 2009; (d) award cost in favour of the petitioners; (e) pass such other and further order/directions as the Commission may deem appropriate in the facts and circumstances of the case. 13. Mega Power Policy Observations: i) The erstwhile PSEB (predecessor of the respondent) intending to procure power through competitive bidding under section 63 of the Electricity Act, 2003 and the “Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees”, 18 issued by the Ministry of Power, Government of India in 2005 decided to invite bids (under Case-2) from power project developers for setting up the Project (2x700MW) at village Nalash near Rajpura Distt. Patiala, Punjab. In terms of the Guidelines, the PSEB incorporated a special purpose vehicle (SPV) in the name of Nabha Power Ltd. (NPL) to act as its authorised representative for carrying out pre-bid activities on behalf of PSEB in relation to the Project. Accordingly, on 10.6.2009, NPL on behalf of PSEB issued Request for Qualification (RfQ) and Request for Proposal (RfP) for selection of a developer through Tariff based competitive bidding process for procurement of power on long term basis from the above Project. ii) Pursuant to the bid process, petitioner no. 2 was selected as the successful bidder and on acquisition of the SPV NPL by it as per the RfP, the PPA was signed on 18.01.2010 between NPL, as the Seller, on behalf of petitioner no. 2 and the then PSEB, as the Procurer. iii) As per the petitioners, while preparing the bid for the Project, the petitioner no.2 considered various fiscal benefits and concessions available to an entity executing a thermal power project of capacity above 1000 MW. Two policies regimes i.e. the Foreign Trade Policy, 2009-2014 and the Mega Power Policy, 2009 were stated to be in vogue at the time of bidding which provided for various benefits for a Project of this nature. iv) As per the pleadings, the petitioner no.2 took note of the announcement made in press release of the Press Information Bureau, Govt. of India on 01.10.2009 under the heading „Modifications to the Mega Power Policy‟ (Annexure-P/1 of the petition) with respect to the modifications approved by the Union Cabinet on that day. Perusal of the same indicates that the said modifications were with regard to the Mega Power Policy introduced in November 1995 for providing impetus to development of large size power projects in the country which had earlier been modified in 1998 and 2002 and last amended in April, 2006 to rationalise the same to bring it in consonance with the National 19 Electricity Policy 2005 and Tariff Policy 2006. The following modifications were envisaged: (a) The existing condition of privatization of distribution by power purchasing states would be replaced by the condition that power purchasing states shall undertake to carry out distribution reforms as laid down by the Ministry of Power. (b) The conditions requiring inter-state sale of power for getting mega power status would be removed. (c) The present dispensation of 15% price preference available to the domestic bidders in case of cost plus projects of PSUs would continue. However, the price preference will not apply to tariff based competitively bid projects of PSUs. A Committee would be set up under the Planning Commission, with DHI, MoP and DoR as members which would suggest options and modalities to take care of the disadvantages suffered by the domestic industry related to power sector keeping all factors in view. (d) The benefits of Mega Power Policy will also be extended to supercritical projects to be awarded through ICB with the mandatory condition of setting up indigenous manufacturing facility provided they meet the eligibility criteria. (e) The requirement of undertaking international competitive bidding (ICB) by the developers for procurement of equipment for mega power projects would not be mandatory, if the requisite quantum of power has been tied up through tariff based competitive bidding or the project has been awarded through tariff based competitive bidding. (f) A basic custom duty of 2.5% only would be applicable on brown field expansion of existing mega projects. All other benefits under mega power policy available to Greenfield projects would also be available to expansion unit(s) (brownfield projects) even if the total capacity of expansion unit(s) is less than the threshold qualifying capacity, provided the size of the unit(s) is not less than that provided in the earlier phase of the project granted mega power project certificate. All other conditions for grant of the mega power status shall remain the same. (g) Mega Power Projects would be required to tie up power supply to the distribution companies/utilities through long term PPA(s) and may also sell power outside long term PPA(s) in accordance with the National Electricity Policy 2005 and Tariff Policy 2006 of Government of India, (as amended from time to time).. 20 v) The petitioner no.2 vide its letter dated 02.10.2009 (Annexure P/2 of the petition) while intimating the Procurer regarding recent development on Mega Power Policy requested to extend the bid deadline by one month, to enable it to go through the changes and ascertain the impact on the bid, to give a level playing field to all bidders. Further vide letter dated 06.10.2009, the petitioner no.2 informed the Procurer that, in view of the modifications in the Mega Power Policy announced on 01.10.2009 in respect of scrapping of the conditions with regard to (i) the Projects (with Mega Power Status) requiring the sale of electricity to more than one State and (ii) the States purchasing power from such Projects not required to privatize distribution sector, it has taken into consideration, the benefits associated with the Mega Power Status in its evaluation of the Project. As per the petition, the letter dated 06.10.2009 was withdrawn by the petitioner no.2 at the instance of the Procurer who informed that the said letter was extraneous to the requirements of the bid documents and hence would not be entertained. vi) Vide letter dated 03.12.2009 (Annexure A of PSPCL‟s reply dated 25.07.2012), the Ministry of Power, Government of India notified to all the States and Union Territories, the Distribution Reforms required under the modified Mega Power Policy. The condition specified by the Ministry of Power inter alia, included (a) timely release of subsidy as per Section 65 of the Electricity Act 2003. (b) ensure that Discoms (Distribution companies) approach the State Electricity Regulatory Commissions for approval of annual revenue requirement/tariff determination in time according to the Regulations. (c) setting up special courts as provided in the Electricity Act, 2003 to tackle theft related cases. (d) ring fencing of State Load Despatch Centres. 21 vii) The Ministry of Power, issued the Office Memorandum No. A118/2003-IPC dated 14.12.2009 (Annexure P/5 of the petition) in this regard stating “Policy guidelines for setting up of mega power projects were last revised and issued vide this Ministry‟s letter of even number dated 2nd August, 2006. The Government of India has modified the Mega Power Policy to smoothen the procedures further. The modified Mega Power Policy is as follows: (i)The power projects with the following threshold capacity shall be eligible for the benefit of mega power policy: (a) A thermal power plant of capacity 1000 MW or more; or ……………. (ii) Mandatory condition of Inter-State sale of power for getting mega power status has been removed. (iii)Goods required for setting up a mega power project, would qualify for the fiscal benefits after it is certified by an officer not below the rank of a Joint Secretary to the Govt. of India in the Ministry of Power that (i) the power purchasing States have constituted the Regulatory Commissions with full powers to fix tariffs and (ii) power purchasing states shall undertake to carry out distribution reforms as laid down by Ministry of Power. (iv) Mega Power Projects would be required to tie up power supply to the distribution companies/utilities through long term PPA(s) in accordance with the National Electricity Policy 2005 and Tariff Policy 2006, as amended from time to time, of Government of India. (v) There shall be no further requirement of ICB for procurement of equipment for mega projects if the requisite quantum of power has been tied up or the project has been awarded through tariff based competitive bidding as the requirements of ICB for the purpose of availing deemed export benefits under Chapter 8 of the Foreign Trade Policy would be presumed to have been satisfied. In all other cases, ICB for equipments shall be mandatory. (vi)The present dispensation of 15% price preference available to the domestic bidders in case of cost plus projects of PSUs would continue. However, the price preference will not apply to tariff based competitively bid project/s of PSUs. …………” 22 viii) As per the petition, Department of Revenue, Ministry of Finance, Govt. of India, in order to implement the decision of the Union Cabinet, while exercising the power under section 25 of the Customs Act, 1962 vide its Notification No. 137/2009-Customs dated 11.12.2009 (Annexure P/4 of the petition) amended its Notification No.21/2002-Customs dated 01.03.2002 in respect of Entry at S. No. 400 of the Table which was substituted as “Goods required for setting up of any Mega Power Project, so certified by an officer not below the rank of a Joint Secretary to the Government of India in the Ministry of Power, that is to say(a) a thermal power plant of a capacity of 700 MW or more, located in the States of Jammu & Kashmir, Sikkim, Arunachal Pradesh, Assam, Meghalaya, Manipur, Mizoram, Nagaland and Tripura; or (b) a thermal power plant of a capacity of 1000 MW or more, located in States other than those specified in clause (a) above; or ……………….” Further in the Annexure, in Condition no. 86, for sub-clause (ii) of clause (a), the following was substituted: “(ii) the power purchasing states shall undertake to carry out distribution reforms as laid down by Ministry of Power.” ix) The Government of Punjab, by virtue of Notification dated 16.04.2010 (Annexure-B of the respondent‟s reply dated 25.07.2012) unbundled the erstwhile Punjab State Electricity Board into separate companies including the respondent PSPCL under Section 131 of the Electricity Act, 2003. x) On 30.04.2010, the Department of Power, Government of Punjab informed Ministry of Power, Government of India in regard to the distribution reforms undertaken, as laid down by the Ministry of Power in its communication dated 03.12.2009. xi) The petitioner no.1 vide letter dated 11.05.2010 (Annexure-C of the respondent‟s reply dated 25.07.2012) applied for grant for Mega Power Status for the 2x700MW Rajpura Thermal Power Project to the Ministry of Power, GOI and while providing all the details of the Project stated 23 “We eagerly look forward to the issuance of Mega Power Status for the Project at the earliest.” xii) In response to the application of NPL dated 11.05.2010, the Ministry of Power, vide its letter dated 30.07.2010 (Annexure-D of the respondent‟s reply dated 25.07.2012) forwarded the mega status certificate for the said Project. The certificate dated 30.07.2010, issued on the basis of PPA dated 18.01.2010 and undertaking from the State Government that they would carry out the distribution reforms measures in accordance with Govt. of India‟s letter no. A-118/2003IPC(Vol.II) dated 03.12.2009, certifies that (a) the Project is a thermal power plant of capacity 1400(2x700MW) and (b) the power purchasing States have constituted the Regulatory Commissions with full powers to fix Tariff and shall undertake to carry out distribution reforms as laid down by Ministry of Power. xiii)The petitioner no.1 vide its letter NPL/CE/PSPCL/022 dated 23.05.2011(Annexure P/19 of the petition) submitted the undertaking to pass on the fiscal benefits attached to the mega power status with regard to exemption of Customs duties to the respondent as per provisions of the PPA due to Change in Law (i.e. grant of aforesaid mega status) as desired by respondent as a pre-condition for recommending to the Government of Punjab for granting „Essentiality Certificate‟ required for clearance of capital goods for the Project at concessional duty. It has been stated that the said undertaking was given by petitioner no.1 under protest and without prejudice to its legal rights and contentions. xiv)The Secretary to Government of Punjab, Department of Power, vide its letter no. 10/5/2011-PE2/2238 dated 16.06.2011(Annexure P/23 of the petition) addressed to the Commissioner of Customs recommended for allowing duty concessions as admissible for import of goods required for the Project. In the endorsement to the said letter addressed to the petitioner no. 1, it was informed that the recommendation for the concessional duties has been made subject to PSPCL‟s right for the appropriate decrease in tariff on account of 24 reduction in the capital cost of the Project due to concessional Customs duties in term of Article 13 of the PPA. The said letter was further endorsed to the respondent for taking necessary action as per provisions in the PPA with respect to Change in Law. xv) The petitioner no.1 vide its letter dated 23.11.2011 (Annexure P/32 of the petition) again submitted a similar undertaking for the goods to be imported in the second round as required by the respondent. Subsequently, the Secretary to Government of Punjab, Department of Power, vide its 13.12.2011(Annexure Commissioner of letter P/33 no. of Customs the 10/5/2011-PE2/4116 petition) recommended addressed for dated to allowing the duty concessions as admissible for import of goods required for the Project. Again, in the endorsement to the said letter addressed to the petitioner no. 1, it was informed that the recommendation for the concessional duties has been made subject to PSPCL‟s right for the appropriate decrease in tariff on account of reduction in the capital cost of the Project due to concessional Customs duties in term of Article 13 of the PPA. Also, the said letter was further endorsed to the respondent for taking necessary action as per provisions in the PPA with respect to Change in Law. 14. Findings: The contention of the petitioners is that Article 13 of the PPA executed between the petitioner no.1 and the respondent dealing with Change in Law has no application in the present case as the amendment to the Mega Power Policy was announced by the Union Cabinet in the press release dated 01.10.2009. However, The contention of the respondent is that the Change in Law in the form of amendment to the Mega Power Policy came into force not on the date of the press release on 01.10.2009 but much after the cut-off date of 02.10.2009, being 7 days prior to date for submission of bids i.e. 09.10.2009 and therefore, Article 13 applies to the respondent for getting the benefit accruing due to concessional duties etc. 25 Considering the aforementioned observations, the Commission finds that irrespective of the difference in opinion regarding the date of availability of the Mega Power Status to the Project under the Mega Power Policy of the Ministry of Power, Government of India i.e. date of the decision of the Union Cabinet (01.10.2009) or the date of the notification(s) by Government of India, through Ministry of Power dated 14.12.2009 and Ministry of Finance dated 11.12.2009, the Mega Power Status was to be made available to the Project subject to, the State in which the Project was being set up, undertaking the reforms intimated vide Ministry of Power‟s letter dated 03.12.2009. The Commission notes that the same were undertaken by the Government of Punjab on 16.04.2010 and intimated to the Central Government vide its letter dated 30.04.2012. The Commission further notes that the respondent no.1, thereafter, made an application, vide its letter dated 11.05.2010, to the Ministry of Power specifically informing that as per its understanding, the Government of Punjab vide letter dated 30.04.2010 has fulfilled the conditions required in respect of carrying out the necessary reforms for enabling a Project being set up in the State for grant of Mega Power Status and has carried out the requisite reforms, and therefore, the Project is eligible for grant of Mega Power Status, which was granted by the Ministry on 30.07.2010. This clearly establishes that the Project became eligible for grant of Mega Power Status and acquired the same only after the State Government carried out the requisite reforms and thereafter the Mega Power Status was granted to the Project. The grant of Mega Power Status under the Mega Power Policy was contingent upon the concerned State carrying out the reforms which was done by the Government of Punjab on 16.04.2010. Rightly so, the petitioner no.1, applied for the Mega Power Status on 11.05.2010 i.e. after the date of reforms carried out by the Government of Punjab on 16.04.2010 and not immediately after the decision of Union Cabinet on 01.10.2009 or the notifications of the Ministry of Finance dated 11.12.2009 and Ministry of Power dated 14.12.2009. Even the recommendations by the Government of Punjab to the Customs authorities for custom duties concession/exemption, in view of the Mega Power Status of the Project, were subject to PSPCL‟s right for appropriate decrease in Tariff on account of reduced capital cost of the 26 Project in terms of Article 13 of the PPA with respect to provision of Change in Law. Furthermore, the Commission is of the view that the benefit of Mega Power Status can not be granted w.e.f. 01.10.2009 considering that it is only after the gazette notification that public at large is informed of the decisions of the Government. As submitted by the respondent, the Commission notes that all the detailing in respect of the amendment in the Mega Power Policy was not available in the press release dated 01.10.2009. The same was covered in the letter dated 03.12.2009 of the Ministry of Power to the States and in the notification of the Ministry of Power dated 14.12.2009. The Commission also notes the submission of the respondent that the press release itself provided for the disclaimer that though all efforts have been made to ensure the accuracy and currency of the content on the website of the Press Information Bureau, Government of India, the same should not be construed as a statement of Law or used for any legal purposes. Also, the Commission notes that as submitted by the respondent, Section 25 of the Customs Act, 1962 provides that, unless otherwise provided, every notification issued under subsection(1) or (2A) shall come into force on the date of its issue by the Central Government for publication in the Official Gazette. In view of the above findings, the Commission holds that since the Mega Power Status was granted to the Project under the Mega Power Policy by the Ministry of Power on 30.07.2010 on the application dated 11.05.2010 filed by the respondent no.1, having become eligible on 16.04.2010, the benefits, if any, accruing thereunder to the Project would be applicable only from 30.07.2010 and not from any prior date, notwithstanding that the decision for granting the Mega Power Status was taken/announced on 01.10.2009 or the notifications in respect of the said decision of the Union Cabinet were issued by the concerned Ministries of the Government of India on 11.12.2009 and 14.12.2009. Accordingly, the Commission is unable to grant the aforementioned prayers (a) and (b) in this petition. 15. Foreign Trade policy Observations and Findings: With regard to the aforementioned prayer (c) in this petition, the Commission notes that the petitioners have stated that before 01.10.2009, the 27 petitioner no.2 was considering fiscal benefits available to the Project under the Foreign Trade Policy (FTP). It has been submitted that pursuant to the revision in the Mega Power Policy 2006 by the Union Cabinet on 01.10.2009, the petitioner no.2 considered the benefits available to the Project from the prospective of this Policy since the benefits were identical to that under the FTP. The petitioners have further submitted that without prejudice, if in terms of the PPA, the change in the Mega Power Policy amounts to Change in Law, in view of the prevailing FTP prior to the submission of the bids, there is no economic impact on account of such Change in Law as the benefits under the FTP would in any case be available to the Project regardless of the status of Mega Power Project. The petitioners have further submitted that the benefits under the FTP which were available to the Project at the time of bidding, irrespective of it being having the Mega Power Status have since been withdrawn by the relevant authorities of the Government of India. The petitioners have averred that, therefore, the petitioners have a claim under the Change in Law provision under Article 13 of PPA for withdrawal of benefits available to the Project without considering its status under the Mega Power Policy as on the date of bidding. 16. The Commission notes that a holistic reading of the relevant extracts of the Foreign Trade Policy 2009-14 as prevalent at the time of bidding, the decision of the Policy Interpretation Committee (PIC) dated 15.03.2011 and subsequent clarifications issued by the Director General of Foreign Trade (DGFT) vide letter/circular dated 27/28.04.2011 and notifications of the Ministry of Commerce and Industry dated 28.12.2011 and 21.03.2012 make it clear that the benefits under FTP were not available to the Project. Probably for this very reason, the petitioners did not rely upon FTP for claiming the benefits and opted for the identical benefits purported to be available under the Mega Power Policy on the date of bidding. The Commission opines that if the benefits under the FTP were available to the petitioners on the date of bidding, there was no necessity for the petitioner no.2 to inform the Procurer vide letter dated 06.09.2009 stating that benefits associated with the Mega Power Status have also been taken into consideration in its evaluation of the Project and take further actions to apply and obtain the Mega Power Status as 28 also to request for the essentiality certificate from the Government of Punjab. Furthermore, the Commission notes that the Mega Power Status was granted to the Project on 30.07.2010 and the alleged change in the FTP was announced in 2011. The Commission opines that if the FTP in the year 2010 provided the benefits to the petitioners, there was no occasion for the petitioner no.1 to claim the benefit under the Mega Power Policy and obtain the essentiality certificate from the Government of Punjab and claim the benefit of Customs duty concession/exemption under the notification dated 11.12.2009 of the Government of India. The Commission is of the considered opinion that the petitioners claiming the benefits under Mega Power Policy itself sufficiently establishes that the benefits under the FTP were not applicable to the petitioners‟ Project. Notwithstanding the discussion above, the Commission is of the opinion that even if it is assumed for the sake of argument, that benefits were available to the Project under the FTP on the date of bidding, the petitioners forfeited their right to subsequently claim the benefits under the FTP by opting out of the same having claimed the benefits under the Mega Power Policy. Accordingly, the Commission decides that the prayer (c) of the petitioner also cannot be granted. The petition is accordingly disposed of without any cost. Sd/(Gurinderjit Singh) Member Sd/(Virinder Singh) Member Sd/(Romila Dubey) Chairperson Chandigarh Dated: 12.11.2012 29