POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230KV EXTENSION IN EXISTING 230/132KV SUBSTATIONS AT KHULNA SOUTH ON TURNKEY BASIS [CONTRACT NO. PGCB/230kV/SS/KS] VOLUME 3 OF 3 BID FORM, PRICES AND SCHEDULES DECEMBER 2014 POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230KV EXTENSION IN EXISTING 230/132KV SUBSTATIONS AT KHULNA SOUTH ON TURNKEY BASIS INDEX TO VOLUMES Volume 1 of 3 Section 1 - Instruction to Bidders Section 2 - Bid Data Sheet Section 3 - Evaluation and Qualification Criteria Section 4 - Bid Forms Section 5 - Eligible Countries Section 6 - Employer’s Requirements Section 7 - General Conditions of Contract Section 8 - Special Conditions of Contract Section 9 - Contract Forms Volume 2 of 3 Scope of Work Technical Specifications Drawings forming Part of Specifications Volume 3 of 3 Bid Forms Schedule A Schedule B Schedule C Schedule D Schedule E Schedule F Schedule G Schedule H Schedule I Schedule J Schedule A: Requirements Introduction & Preamble to the Price & Technical Schedules Bid Prices Bar Chart Programme of Key Activities Manufacturers, Places of Manufacture and Testing Technical Particulars and Guarantees Departure from Specifications Proposed Alternative Standards to which Equipment shall Provided Proposed Contract and Site Organization Drawings and Documents to be Submitted with Bid Proposed Subcontractors SA-2 POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230KV EXTENSION IN EXISTING 230/132KV SUBSTATIONS AT KHULNA SOUTH ON TURNKEY BASIS [CONTRACT NO. PGCB/230kV/SS/KS] SCHEDULE A INTRODUCTION & PREAMBLE TO THE PRICE & TECHNICAL SCHEDULES Schedule A: Requirements SA-3 SCHEDULE A: INTRODUCTION & PREAMBLE TO THE PRICE & TECHNICAL SCHEDULES BRIEF DESCRIPTION OF THE WORKS 1) SECTION OF WORK NO. 1: 230KV EXTENSION IN EXISTING 230/132KV KHULNA SOUTH SUBSTATION 230 kV Outdoor Double busbar with Circuit breaker bypass arrangement Switchyard The existing 230kV outdoor switchyard has two spare bays for the connection of two overhead line circuits to upcoming Mongla 230kV substation. This contract includes the design, supply, installation & testing & commissioning of new overhead lines terminal equipment in the switchyard, associated line control, protection & metering equipment, extension of fiber optic multiplexer equipment for protection & communication and extension of existing digital fault recorder (SIMENS, Germany make) & integration with the existing NLDC system and associated equipments with all related civil works. The contract also includes supply of line protection panels for two overhead lines and fiber optic multiplexer equipment for the remote station at Mongla. DESCRIPTION OF THE WORKS The descriptions presented below outline the basic requirements for each Section of the Works. This schedule is not intended to detail each and every item necessary to complete the works, but to outline the facilities to be provided under the contract. The Contractor shall be responsible for ensuring that all items necessary for the safe, efficient and complete functioning of the work in compliance with the Specification are provided, be they described or not. The following method of reference shall be used to identify the various items required. ITEM A B C D E F G H I J PLANT DESCRIPTION 230 kV Switchgear Control, Protection, Metering. Multicore Cables Earthing and Lightning Protection Batteries, Chargers and DC Distribution LVAC Distribution Civil Works and Foundations Building Lighting, Small Power and Air Conditioning Fiber Optic Multiplexer Equipment for Communication and Protection and necessary RTUs required for and integration with the existing NLDC system. Digital Fault and Disturbance Recorder (DFDR) The Contractor is to carry out the works taking full account of the limitations imposed by existing sites and the requirement to maintain all existing supplies during the construction works. Any temporary works, structures, connections, etc, necessary to achieve this requirement are to be included in the bid price. Schedule A: Requirements SA-4 SCHEDULE A REQUIREMENTS I) SECTION OF WORK NO.1: EXTENSION OF EXISTING KHULNA SOUTH 230KV SUBSTATION FOR TWO NOS. LINE BAYS TO MONGLA The equipment to be supplied, installed and commissioned is shown on Drawing No. PGCB/DESIGN/2014/SS/KS-02 & 03, with single line diagram of main connections, control and protection requirements shown in drawing no. PGCB/DESIGN/2014/SS/KS-01:The Contractor shall be deemed to have visited site, inspected, gathered data and verified details of the as-built system in order to design supply and interface his new equipment. All necessary materials, adjustment, dismantling, remedial, and tidying up work in order to complete the work specified shall be included in the contract price. This includes all ancillary equipment such as cabling, earthing, LVAC and DC supplies, steel support structures, lightning protection, switchyard lighting and associated civil works, foundations, drainage, cable trenching and site finishes. Item 1A Description 245 kV Switchgear, equipment connection and steel structures The 245 kV switchgear shall comply with the particular requirements as detailed in the Schedule of Technical Requirements included as Appendix A1 to this section and shall comprise the following:Design, supply, delivery, installation, testing & commissioning of two spare 230 kV Overhead Line circuit bays in the existing 230kV double busbar switchyard arrangement to connect two 230kV overhead line circuits from upcoming Maitree Super Thermal Power Project (STPP) 230kV substation complete with all necessary ancillary equipment and associated works. 1A1 Design, supply, delivery, installation, testing & commissioning of new two (2) sets of 245 kV, 3150A, 40kA, 50Hz, 1050kVp BIL, live tank type, single-pole operation, SF6 gas circuit breakers with spring-stored energy operating mechanism. 1A2 Design, supply, delivery, installation, testing & commissioning of new two (2) sets of 245kV, 1600A, 40kA, 50Hz, 1050kVp BIL, single throw horizontal center air break , post type, motor operated disconnectors with motor and manual operated earthing switches. 1A3 Design, supply, delivery, installation, testing & commissioning of new eight (8) sets of 245kV, 1600A, 40kA, 50Hz, 1050kVp BIL, single throw horizontal center air break, center rotating post type, motor operated disconnectors. 1A4 Design, supply, delivery, installation, testing & commissioning of new six (6) nos. of single-phase, 4-core, multi ratio, 245kV, 1600A, 40kA, 50Hz, 1050kVp BIL, post type current transformer. Schedule A: Requirements SA-5 1A5 Design, supply, delivery, installation, testing & commissioning of new six (6) nos. of single-phase, 245kV, 40kA, 50Hz, 1050kVp BIL, capacitor type voltage transformers. 1A6 Design, supply, delivery, installation, testing & commissioning of six (6) nos. of 186kV continuous operating voltage, 10kA nominal discharge current, 50Hz, Heavy duty station class, gapless metal oxide type, single phase surge arresters. 1A7 One (1) lot of conductors for jack bus , jumper & equipment connections as required to complete 245kV switchgear as specified in the technical specifications and bid drawings. 1A8 Design, supply, delivery, installation, testing & commissioning of four (4) nos. of 245kV post type support insulators required for completing 245kV switchgear connections. 1A9 One (1) lot of insulators and fittings including all necessary clamps and connectors required for completing 245kV switchyard specified in the technical specifications and bid drawings. 1A10 One (1) lot of steel structures for gantry and equipment supports structures including nuts & bolts and cable tray including all necessary fitting & fixing accessories required for completing 245kV switchgear specified in the technical specifications and bid drawings. 1B Control, Protection and Metering All control, protection, alarm and metering panels are to be installed in the existing control building. The equipment to be supplied, installed and commissioned is shown on Drawings nos. PGCB/DESIGN/2014/SS/KS-01:- 1B1 Complete Control & protection panels for two (2) sets of overhead line circuits to Mongla (Mongla -1 & 2). 1B2 Extension, connection and modifications to existing busbar protection to accommodate two new lines and synchronization with existing system. 1B3 Supply, delivery and installation of Tariff meter in the existing panels. The tariff meters shall be programmable & recordable digital 3-phase, 4-wire import and export MWh and MVArh meters (accuracy class 0.2) including necessary software for two Overhead Line feeder circuit. For each feeder minimum two meters (one main & one check) shall be provided. Tariff Metering is to be supplied from Europe, USA or Japan origin. Printed catalogue, operation and service manual are to be provided. Schedule A: Requirements SA-6 1B4 Complete line protection panels for two (2) sets of overhead line circuits from Khulna South (Khulna South-1 & 2) at Mongla. The panels shall be supplied only and handover for future installation by other contractor at Mongla. 1C Multicore Cables 1C1 Complete set of multicore low voltage XLPE auxiliary power and control cables required for connection of all items and equipment supplied under the Contract shall be supplied, installed, glanded, terminated and have individual cores identified. 1D Earthing and Lightning Protection 1D.1 Complete set of design, supply and installation for extending of earthing system and lightning protection screen including connections, connectors and clamps, for the additional switchgear and ancillary equipment being installed. 1E DC Distribution Connection 1E1 One (1) lot of modification of existing DCDB system by necessary additional switchgear (MCB/MCCB), cables, connectors etc. required for the additional plant being installed, shall be provided. 1F LVAC Distribution Connection 1F1 One (1) lot of modification of existing LVAC existing systems for substation services including supply of all necessary additional switchgear (MCB/MCCB), bus material, connection cables, lugs etc. to provide the 415/240V supplies to all equipment being supplied under this turnkey bid. 1G Civil Works and Foundations 1G1 Complete design, supply and construction of all civil items required for the outdoor works suitable for switchyard gantry & equipment foundations, cable trenches, surfacing, gravel laying and drainage system etc. 1H Lighting & Small Power. 1H1 Complete design and calculations, supply, installation and commissioning of equipment to provide lighting (sodium light) for security, roadway and switchyard and emergency DC lighting at strategic locations for equipment operations and inspections to suit the substation overall arrangement for the additional switchgear and ancillary equipment to be installed under this turnkey bid. 1I Fibre Optic Multiplexer Equipment for Teleprotection and Communication 1I1 The equipment to be supplied, installed and commissioned shall be as shown on Drawing Nos. PGCB/DESIGN/2014/SS/KS-04. The scope of supply is summarised as follows:1 set - Extension of existing teleprotection equipment (AREVA, France make DIP 5000 type) and fibre optic multiplexer equipment (AREVA, France make MSE 5010 type/ABB, Switzerland make FOX515 type) at Khulna (South) Substation for two new line circuits (Mongla 1 & 2) for protection and communication (voice and data) Schedule A: Requirements SA-7 1I2 One (1) lot of underground optical fibre (48 cores) cables from terminal box at 230kV gantry structures (For Mongla-1 & 2 line feeders) to MDF (Main distribution Frame) in control room. The Contract includes supply and installation of underground optical fibre and pigtail cables with adequate length. 1I3 Extension of existing Remote Terminal Units (RTU, AREVA, France make C262 type) system for new two line bays and connection & integration with the existing NLDC (National Load Despatch Center) system. 1I4 One (1) lot complete set of design, supply, installation and commissioning of fibre optic multiplexer equipment covering five (5) related substation optical interfaces with necessary works to interface with existing system is to be provided for: 21 relay for each transmission line protection (through fibre cores) 21 relay carrier signal (main and back-up) SCADA data from switchgear and control system Hot-line telephone system Substation LAN system This equipment including panels shall be for supply only and handed over for future installation by other contractor at Mongla. 1J Digital Fault Disturbance Recorder 1J1 Extension and modification of existing Digital Fault Disturbance Recorder (DFDR) system (SIEMENS, Germany make SIMEAS model DFR) to monitor the proposed Mongla 1 & 2 line feeders using available analog and digital inputs in existing DFDR system. Schedule A: Requirements SA-8 APPENDIX A1 SCHEDULE OF TECHNICAL REQUIREMENTS OF 245kV AIR INSULATED SWITCHGEAR (AIS) Sl. No. Description 1. 2. 3. Site Condition Max. Altitude above sea level Max. Ambient temperature outdoor Min. Ambient temperature outdoor Max. Ambient relative humidity Max. Seismic acceleration at floor level - horizontal - vertical Unit M 230kV % not more than 1000 +45 +4 100 G G 0.2 0.2 Electrical Data Rated Voltage Rated Frequency Insulation Level - lightning impulse withstand - switching impulse withstand - 50 Hz withstand 1 minute Rated continuous current at 40 ambient temperature - main busbar - line bay Rated short time withstand - current - duration Rated peak withstand current Secondary Circuit Auxiliary voltage - for control and signal - for remote control V dc V dc 110 110 V ac % 415/240 -15/+10 - for heating - tolerances Schedule A: Requirements KV Hz 245 50 kVp kVp KV 1050 — 460 A A 2000 1600 KA Sec KA 40 1 100 SA-9 4.1 245kV Class Circuit Breakers 1 Type Outdoor, SF6 insulated, live tank type 2 Standard IEC 62271-100 3 Rated voltage 245 kV 4 Rated short-duration power frequency withstand voltage (1 min.) - Between line terminal and ground - Between terminals with CB open - Between terminals with isolator open 460 kV rms 460 kV rms 530 kV rms Rated lightning impulse withstand voltage - Between line terminal and ground - Between terminals with CB open - Between terminals with isolator open 1050 kV peak 1050 kV peak 1200 kV peak 6 First pole to clear factor 1.5 7 Rated current 3150 A 8 Rated short circuit breaking current 40 kA rms 9 Rated short circuit making current 100 kA peak 10 Short time withstand current for 1 sec. 40 kA rms 11 Max. radio interference voltage for frequency between 0.5MHz 1000 micro V and 2MHz in all positions (at 156 kV rms) 12 Total closing time Not more than 150 ms 13 Total breaking time 65 ms 14 Operating mechanism Spring or Springhydraulic combination 15 Rated duty cycle O-0.3S-CO-3min-CO 16 Reclosing Single phase & Three phase auto-reclosing 17 Creepage distance 25 mm/kV 18 Number of closing coils 1 19 Number of tripping coils 2 20 Number of auxiliary contacts for: - Making - Breaking - Middle position Min. 12 Min. 12 0 Protection class IP55 5 21 Schedule A: Requirements SA-10 5. 245kV Disconnector Switches/Isolators and Earthing Switch 1 Type Outdoor, single throw horizontal center air break, center rotating post type, 2 Standard IEC 62271-102 3 Rated voltage 245 kV 4 Rated short-duration power frequency withstand voltage (1 min.) 460 kV rms - To earth 530 kV rms - Across isolating distance 5 Rated lightning impulse withstand voltage - To earth - Across isolating distance 6 1050 kV peak 1200 kV peak Rated normal current - Line bay 1600 A 7 Rated short circuit current (Ith), 1s 40 kA rms 8 Rated short circuit current (Idyn) 100 kA peak 9 Creepage distance of insulator 25 mm/kV 10 Operating mechanism of isolator / earthing switch AC motor operated 11 Number of auxiliary contacts for main switch - Making - Breaking - Middle position Min. 6 Min. 6 Min. 1 Number of auxiliary contacts for earthing switch - Making - Breaking - Middle position Min. 6 Min. 6 Min. 1 12 13 Radio interference level for 0.5 MHz to 2 MHz 6. Instrument Transformers 6.1 Instrument Transformers 1000 micro V (at 156 kV rms) 245 kV 1 Rated lightning impulse withstand voltage 2 Rated switching impulse withstand voltage 3 1050 kVp - Power frequency withstand voltage (1 min.) Schedule A: Requirements 460 kVrms SA-11 - 4 Corona extinction voltage 156 kVrms 5 Radio interference level for 0.5 MHz to 2 MHz 1000 micro V (at 156 kVrms) 6 Partial discharge level 10 pC 7 Type of insulation Class A 6.2 1 245kV Class Current Transformers Core Nos. 4 2 Ratio 1600-800/1 3 Class of accuracy 4 Burden (VA) 5 Min. knee point voltage at lowest ratio (Volts) 6 Max. magnetizing current guaranteed at knee point voltage & the lowest ratio(mA) M.R. 7 Max. resistance of secondary winding at 75 0C and at lowest ratio(ohms) M.R. 6.3 1 - - Protection : 5P20 - Metering : Class 0.2 30VA 245kV Class Voltage Transformer Rated voltage levels >1kV@ max ratio for protection core <150V@ max ratio for metering core 245 kV 2 High frequency capacitance for entire Within 80% to 150% of rated capacitance carrier frequency range 3 Rated Voltage Factor 1.2 continuous; 1.5 for 30 seconds 4 Rated total capacitance(pF) 4400, +10% and -5% 5 Phase angle error (minutes) 20 6 Acceptable limit of variation of total + 50% and -20% of the rated capacitance capacitance over the entire carrier frequency range 7 Equivalent series resistance over the entire Less than 40 carrier frequency range or temperature range (ohms) 8 Stray capacitance and stray conductance As per IEC-358 of low voltage terminal over the entire capacitance. 9 Standard reference range of frequencies 97% to 103% for protection for which the accuracies are valid 99% to 101% for metering Schedule A: Requirements SA-12 10 Core details Core-I : Core-II : 11 Purpose Protection Metering 12 Secondary Voltage 110/√3 110/√3 13 Burden (VA) 150 150 14 Class of accuracy 3P 0.5 15 Rated total thermal burden(VA) 150 150 16 One minute power frequency 4(10 if the low voltage terminal is exposed) withstand voltage between LV terminal and earth(kV rms) 17 Withstand voltage for secondary winding 2 (kV rms) 7 1 Surge Arresters Max. highest system voltage 245kV 2 Type Outdoor type, ZnO, Gapless 3 Standard IEC 60099-4 4 Rated voltage 186kV 5 Max. continuous operating voltage 160kVrms 6 Nominal discharge current 10kA 7 Discharge class Heavy duty 3 8 Surge counter Yes 9 Leakage current detector Yes Schedule A: Requirements SA-13 APPENDIX A2 SCHEDULE OF TECHNICAL REQUIREMENTS OF FIBRE OPTIC MULTIPLEXER EQUIPMENT UNIT SL.Nos. DESCRIPTION 1.0 GENERAL: 1.1 1.2 1.3 1.4 1.5 1.6 1.7 2.0 2.1 3.0 3.1 3.2 Type of multiplexer Complying to ITU-T rec. Transmission Capacity Access capacity on 64 kbit/s Access capacity on 2 Mbit/s Redundant central processor Digital cross connect function Available AGGREGATES: Optical aggregates (ITU-T G.957) Available TRUNK INTERFACES: HDB3, 2 Mbit/s interfaces per module Complying to ITU-T rec. 3.3 HDSL, 2Mbit/s interface: no of copper wires Capacity on 2Mbit/s or on 1Mbit/s Capacity selectable 4.0 4.1 4.1.1 4.1.2 Available USER INTERFACES Voice interfaces for trunk lines: 1 + 1 com path protection, available for all Analogue, 4wire with E&M: Input level Output level Analogue, 2wire with E&M: Input level Output level Digital, 2Mbit/s CAS or PRI Voice interfaces for remote subscriber: 2wire, subscriber side 2wire, PABX side Integrated teleprotection Interface for Commands: Number of independent commands Transmission time max. Signal voltage 1 + 1 com path protection Interface(s) for Differential Protection: Electrical interface: G.703 Optical Interface Data: channels per module 4.1.3 4.1.4 4.2 4.2.1 4.2.2 4.3 4.3.1 4.3.1.1 4.3.1.2 4.3.1.3 4.3.1.4 4.3.2 4.3.2.1 4.3.2.2 4.4 Schedule A: Requirements SA-14 Mbit/s channels channels REQUIRED SDH: ADM Yes STM-4: 620 Minimum 200 Minimum 40 Shall be available Fully non-blocking L-1.1, L-1.2 Nos. Nos. ch ch / pair of wire Minimum 8 G.703, transparent G.704, selectable 4 or 2 30 or 15 30 / 2 pairs 30 / 1 pair 15 / 1 pair Yes dBr +7.5 .. –16 +7.0 .. –16.5 +6.5 .. –12.5 –1.0 .. -20 dBr Yes dBr dBr Nos. ms Vpeak kbit/s kbit/s -5 .. +4 / -7.5 .. -1 -5 .. +4 / -7.5 .. -3 4 6 250 Yes 64 Minimum 64 4.4.1 4.4.2 4.4.3 4.4.4 4.4.5 4.4.6 4.4.7 4.5 4.5.1 4.5.2 4.6 4.6.1 4.6.2 4.6.3 4.6.4 1 + 1 com path protection, available for all V.24/V.28 (RS-232): up to 38.4kbit/s V.11/X.24 (RS-422): 64kbit/s V.35: 64kbit/s V.36 (RS-449): 64kbit/s G.703: 64kbit/s Ethernet: 10/100 BaseT WAN capacity Protocols Integrated alarm gathering module: Number of external alarms per module Auxiliary power supply for ext. contacts Network Management System Type/Name of configuration tool For fault / configuration management For local / remote operation Data communication network (DCN) 4.7 4.7.1 4.7.2 4.7.3 4.8 4.8.1 4.8.2 Ambient Conditions: Storage: ETS 300 019-1-1, class 1.2 Transport: ETS 300 019-1-2, class 2.2 Operation: ETS 300 019-1-3, class 3.1E Power Supply Operation Fully redundant power supply Schedule A: Requirements SA-15 Nos. Nos. Nos. Nos. Nos. Nos. Mbit/s Nos. Yes 4 4 4 2 8 1 Min: 2x 2Mbit/s Min.: IP Min. 20 Yes Yes / yes Yes / yes Ethernet / IP Ethernit / OSI °C / % hum °C / % hum °C / % hum VDC -25 .. + 55 / class 1.2 -25 .. + 70 / class 2.2 -5 .. +45 / class 3.1E 48 / 60 Yes (-15/+20%) or APPENDIX A3 SCHEDULE OF TECHNICAL REQUIREMENTS OF INSULATOR 1 2 3 4 5 6 7 8 Rated Voltage Lightning impulse withstand positive and negative (kVp) (Dry and wet) Switching impulse withstand voltage (kVp) One min. power freq. withstand voltage (kVrms) (Wet and Dry) Total creepage distance (mm) pedestal Total min. cantilever strength (kg) Corona extinction voltage (kVrms) Total min. height of insulator (mm) 245kV 1050 460 - 6125 800 156 2500 APPENDIX A4 SCHEDULE OF TECHNICAL REQUIREMENTS OF INSULATOR STRING 1 2 3 4 5 6 7 8 9 10 11 12 Rated voltage Type Size of insulators units (mm) Creepage distance of individual insulator unit (Minimum or as required to obtain total creepage distance, mm) Electromechanical strength (kN) Power frequency withstand voltage of the complete string (kVrms) Lightning impulse withstand voltage of the complete string with C.C. ring (Dry and wet, kVp) Switching surge withstand voltage of the complete string with C.C. rings(Dry & wet, kVp) Power frequency puncture withstand voltage for a string insulator unit Minimum corona extinction voltage level of the complete string with C.C. ring (Dry, kVrms) R.I.V. Level of the complete string with C.C. ring. (micro V) Total creepage distance of complete insulator string (mm) Schedule A: Requirements SA-16 245kV Anti FOG 255 x 145 430 120 460 1050 1.3 times the actual wet flashover voltage of the unit. 156 1000 6125 . Sl. (A) APPENDIX A5 SCHEDULE OF TECHNICAL REQUIREMENTS DIGITAL FAULT AND DISTURBANCE RECORDER [DFDR] FOR KHULNA SOUTH SUBSTATION ITEM UNITS GENERAL 1 2 3 Manufacturer’s name & address Type Power Supply -Power supply for printer (B) ANALOGUE INPUTS 1 Number of Channel 2 3 Nominal Current Nominal voltage - Current Frequency response Cut-off frequency (a) Bandwidth (b) Attenuation at (c) Auto adjusted anti-aliasing filters for chosen sampling rate Simultaneously programmable sampling rate for all feeders/inputs -Locally Changeable -Remotely Changeable 4 5 d e Possible sampling rates 6 7 8 9 DC coupled inputs Resolution Accuracy Burden 1. Current Circuit at IN 2. Voltage Circuit Over load 1. Current 2. Voltage circuit 10 (C) VDC VAC 4-for current & 4 for voltage Total 8 for 230kV Amp Vac/Vdc mA/Amp dB dB Yes/No 1A/5A Yes Min 2 for FAST and SLOW Recording Yes/No Yes/No Yes Yes 3 different samplig rates: Samples/sec Slow. 1Hz-500Hz Samples/sec fast: 0.5 kHz – 6kHz Samples/sec continuous (variable rate) Yes/No Yes bits 12 or better % Min 0.5 VA VA % In % Vn DIGITAL INPUTS Schedule A: Requirements 110 230 SA-17 100% In continuously, Min 600 % in for 1 Second 2Vn and max. 350 Vn 16 for 230kV min. 360 1 Number of Channel 2 3 -Expandability (Without and time skew) Selectable input level Vdc Type 4 Resolution (D) MEMORY 1 2 3 4 5 6 Size Type Pre-fault time (fast scanning rate) Post-fault (fast scanning rate Pre and Post-fault time (slow scanning rate) In-Built hard disk (auto-maintained Sl. (E) ITEM UNITS SENSORS/ TRIGERRING CRITERIA N/O or N/C, 110 VDC Potential or potential free contact ms MB sec sec sec 64 MB or Higher Solid State 0.1-2 user programmable 0.1-2 user programmable min. 180 user programmable GB min. 4 GB 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. All sensors/trigerrs are preferable Programmable and Virtually recordable Logical combination sensor Three phase over or under Voltage / Current Mono phase over or under Voltage / Current *du/dt, dp/dt, dq/dt, [Single/3 Phases], df/dt. etc. RMS [Voltage / Current] Zero Sequence Negative, Positive Sequence Frequency DC Step Pendling / Swing Digital level and edge Sensor trigger Event Trigger Manual Trigger Remote Trigger (F) CLOCK SYSTEM 1. 2. 3. 4. Internal Clock Yes/No Accuracy External Synchronization Yes/No Time resolution between 2 synchronized pulses 1. 2. 3. 4. Schedule A: Requirements SA-18 Yes/No Yes Yes/No Yes/No Yes Yes Yes/No Yes Yes/No Yes Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes (G) OUTPUT CONTACT ALARM RELAY 1. Max. operation Voltage DC/AC 2. 3. 4. Make and carry for 0.5 sec Carry Continuously Break ( DC ) – resistive (H) INTERFACE FOR COMMUNICATION 1. 2. 3. 4. 5. Full definition compression Maximum transmission rate Standard serial port ( EIA-232-D) Printer Port Dedicated serial port for modem (I) PRINTER DATA 1. 2. 3. 4. Vac Vdc A A W / 250 Vac or above, 60 Vdc or above Min 8A Min 5A DATA Yes/No bits / Sec Yes / No Yes/No Yes/No Yes Yes Yes Yes Printer amplitude (scaling peak to peak) Time Scal (mm / s ) Printer resolution Auto printing mm Yes/No Yes (J) Fault Priority transmission Yes/No Yes (K) Fault location (distance calculation) Yes/No Yes (L) Test certificates from internationally Yes/No recognized Laboratories Yes (M) COMMUNICATION AND REMOTE ANALYZING UNIT 1. Processor Pentium (MHz) Yes/No Yes/No (Mb) Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No 2. Co-Processor Pentium 3. Main memory capacity 4. Color graphics board S-VGA 5. Screen S-VGA 6. Hard disk unit 7. Printer 8. Modem Yes, at least 450 MHz Pentium Yes Yes, at least 64 MB Yes Yes Yes, at least 40 GB Yes Yes. *Note: du/dt=Change of voltage, dp/dt=Change of active power, dq/dt=change of reactive power, df/dt=Change of frequency. Schedule A: Requirements SA-19 Schedule A: Requirements SA-20 DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132kV KHULNA SOUTH SUBSTATION ON TURNKEY BASIS Item Description Schedule B1: Plants Supplied from Outside the Employer's Country Foreign Currency(F/C) Price ………. Unit Qty Country Unit Price Total Price Insurance Freight Total Price of origin FOB FOB CIF 1 1A 2 245 kV Air Insulated Switchgear 1A.1 SF6 Circuit breaker, live tank, single pole operating sets 2 1A.2 Single throw horizontal center air break , post type disconnector switch with E/S , 1600A sets 2 1A.3 Single throw horizontal center air break, center rotating post type disconnector switch without E/S , 1600A sets 8 1A.4 Single phase current transformer nos. 6 1A.5 Single phase capacitive voltage transformer CVT nos. 6 1A.6 Single phase surge arrester nos. 6 1A.7 Flexiable Conductor for jackbus , jumper & equipment connection lot 1 1A8 Post insulators nos. 4 1A.9 Strain Insulators and fittings including all necessary clamps and connectors lot 1 i) ii) iii) 1A.10 Insulator Fittings Clamps & Connectors Steel Structures & cable tray lot lot lot 1 1 1 i) Gantry Column including nuts bolts lot ii) Gantry Beam including nuts bolts iii) Equipment support structures including nut&bolts lot 1 iv) Cable tray including fitting, fixing accessories lot 1 Schedule B1-1 3=1x2 4 5 6=3+4+5 Local Currency(L/C) Price (in Taka) Local Local Total L/C transport & Insurance Cost handling cost to destination to destination 7 8 9=7+8 DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132kV KHULNA SOUTH SUBSTATION ON TURNKEY BASIS Item Description Schedule B1: Plants Supplied from Outside the Employer's Country Foreign Currency(F/C) Price ………. Unit Qty Country Unit Price Total Price Insurance Freight Total Price of origin FOB FOB CIF 1 1B 1B.1 Control, Protection and Metering Complete control & protection panel for two sets of overhead line circuits to Mongla (Mongla -1 & 2) set 2 1B.2 Extension, connection and modification to existing busbar protection and sunchronizing with existing system lot 1 1B.3 Tariff meters(Imp & exp) for two new lines lot 1 set 2 lot 1 lot lot 1 1 lot lot 1 1 Lot 1 Lot 1 lot 1 1B.4 1C. 1C.1 i) ii) 1D.1 i) ii) 1E 1E.1 1F Complete protection panels for two (2) sets of overhead line circuits from Khulna South (Khulna South-1 & 2) at Mongla Multicore Cables Multicore Low Voltage power and control cable LV power Cable LV Control Cable Earthing and Lightning Protection System Earthing System Lightning Protection System DC Distribution Connection Extension of existing DC distribution system with necessary MCB/MCCB etc. for connecting the new line feeder equipment with 110V & 48V DC system 1F.1 LVAC Distribution Extension of existing LVAC system for connecting the new line feeder equipment 1H 1H1 Lighting and small power Lighting & Small power 2 Schedule B1-2 3=1x2 4 5 6=3+4+5 Local Currency(L/C) Price (in Taka) Local Local Total L/C transport & Insurance Cost handling cost to destination to destination 7 8 9=7+8 DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132kV KHULNA SOUTH SUBSTATION ON TURNKEY BASIS Item Description Schedule B1: Plants Supplied from Outside the Employer's Country Foreign Currency(F/C) Price ………. Unit Qty Country Unit Price Total Price Insurance Freight Total Price of origin FOB FOB CIF 1 1I 2 Fiber Optic Multiplexer Equipment for Teleprotection and Communication 1I.1 Extension of Indoor type Fibre Optic Multipexer Equipment for communication and protection for Mongla 1 & 2 Lot 1 1I.2 Fibre Optic cable(48 cores) and termination box Lot 1 1I.3 Necessary works for integration of New bays with existing Areva, France make NLDC system. Lot 1 1I.4 i) Fibre Optic Multipexer Equipment for communication & protection at Mongla Lot 1 ii) Hot line Telephone system Lot 1 Lot 1 1J Digital Fault Disturbance Recorder 1J1 Extension and modification of existing digital fault disturbance recorder Total price Schedule B1-3 3=1x2 4 5 6=3+4+5 Local Currency(L/C) Price (in Taka) Local Local Total L/C transport & Insurance Cost handling cost to destination to destination 7 8 9=7+8 DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132kV KHULNA SOUTH SUBSTATION ON TURNKEY BASIS Item Description Schedule B1: Plants Supplied from Outside the Employer's Country Foreign Currency(F/C) Price ………. Unit Qty Country Unit Price Total Price Insurance Freight Total Price of origin FOB FOB CIF 1 2 Schedule B1-4 3=1x2 4 5 6=3+4+5 Local Currency(L/C) Price (in Taka) Local Local Total L/C transport & Insurance Cost handling cost to destination to destination 7 8 9=7+8 DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132kV KHULNA SOUTH SUBSTATION ON TURNKEY BASIS Schedule B2: Plants Supplied from within the Employer's country Unit Item Qty Description 1 1A 245 kV Air Insulated Switchgear 1A.1 SF6 Circuit breaker, live tank, single pole operating sets 2 1A.2 Single throw horizontal center air break , post type disconnector switch with E/S , 1600A sets 2 Single throw horizontal center air break, center 1A.3 rotating post type disconnector switch without E/S , 1600A sets 8 1A.4 Single phase current transformer nos. 6 nos. 6 nos. 6 lot 1 Single phase capacitive voltage transformer CVT 1A.6 Single phase surge arrester 1A.5 1A.7 Flexiable Conductor for jackbus , jumper & equipment connection 1A8 Post insulators nos. 4 Strain Insulators and fittings including all 1A.9 necessary clamps and connectors lot 1 i) ii) iii) lot lot lot 1 1 1 insulator Fittings Clamps & Connectors Country of origin Foreign Currency in …….. Local Currency in Taka Unit Price Total Price Unit Price Total Price Transport Insurance Total L/C EXW EXW EXW EXW & Handling Cost Excluding VAT Excluding VAT Excluding VAT Excluding VAT to distination Excluding VAT on EXW 2 3=1x2 4 5=1x4 6 7 8=5+6+7 1A.10 Steel Structures & cable tray i) Gantry Column including nuts bolts lot ii) Gantry Beam including nuts bolts Equipment support structures including nut&bolts Cable tray including fitting, fixing accessories lot 1 lot 1 iii) iv) Schedule B2-9 DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132kV KHULNA SOUTH SUBSTATION ON TURNKEY BASIS Schedule B2: Plants Supplied from within the Employer's country Unit Item Qty Description 1 Control, Protection and Metering Complete control & protection panel for two 1B.1 sets of overhead line circuits to Mongla (Mongla -1 & 2) Country of origin Foreign Currency in …….. Local Currency in Taka Unit Price Total Price Unit Price Total Price Transport Insurance Total L/C EXW EXW EXW EXW & Handling Cost Excluding VAT Excluding VAT Excluding VAT Excluding VAT to distination Excluding VAT on EXW 2 3=1x2 4 5=1x4 6 7 8=5+6+7 1B set 2 lot 1 1B.3 Tariff meters(imp & exp) for two new lines Complete protection panels for two (2) sets of lot 1 1B.4 overhead line circuits from Khulna South set 2 lot 1 lot lot lot lot lot 1 1 1 1 1 Lot 1 Lot 1 lot 1 1B.2 1C. Extension, connection and modification to existing busbar protection and sunchronizing (Khulna South-1 & 2) at Mongla Multicore Cables Multicore Low Voltage power and control cable i) LV power Cable LV Control Cable ii) 1D.1 Earthing and Lightning Protection System i) Earthing System ii) Lightning Protection System 1E DC Distribution Connection 1E.1 Extension of existing DC distribution system with necessary MCB/MCCB etc. for connecting the new line feeder equipment with 110V & 48V DC system 1C.1 1F LVAC Distribution 1F.1 Extension of existing LVAC system for connecting the new line feeder equipment 1H Lighting and small power 1H1 Lighting & Small Power Schedule B2-10 DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132kV KHULNA SOUTH SUBSTATION ON TURNKEY BASIS Schedule B2: Plants Supplied from within the Employer's country Unit Item Qty Description 1 Country of origin Foreign Currency in …….. Local Currency in Taka Unit Price Total Price Unit Price Total Price Transport Insurance Total L/C EXW EXW EXW EXW & Handling Cost Excluding VAT Excluding VAT Excluding VAT Excluding VAT to distination Excluding VAT on EXW 2 3=1x2 4 5=1x4 6 7 8=5+6+7 1I Fiber Optic Multiplexer Equipment for Teleprotection and Communication 1I.1 Extension of Indoor type Fibre Optic Multipexer Equipment for communication and protection for Mongla 1 & 2 Lot 1 1I.2 Fibre Optic cable(48 cores) and termination box Lot 1 1I.3 Necessary works for integration of New bays with existing Areva, France make NLDC system. Lot 1 1I.4 i) Fibre Optic Multipexer Equipment for communication & protection at Mongla Lot 1 ii) Hot line Telephone system Digital Fault Disturbance Recorder Lot 1 Lot 1 1J 1J1 Extension and modification of existing digital fault disturbance recorder Total Price Sub Total Price in words............................................................................................................................................................................ Schedule B: Bid Price Schedule B2-11 DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132kV KHULNA SOUTH SUBSTATION ON TURNKEY BASIS Schedule B2: Plants Supplied from within the Employer's country Unit Item Qty Description 1 Country of origin Foreign Currency in …….. Local Currency in Taka Unit Price Total Price Unit Price Total Price Transport Insurance Total L/C EXW EXW EXW EXW & Handling Cost Excluding VAT Excluding VAT Excluding VAT Excluding VAT to distination Excluding VAT on EXW 2 3=1x2 4 5=1x4 6 7 8=5+6+7 Schedule B2-12 DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230KV EXTENSION IN EXTENSION 230/132KV SUBSTATIONS AT KHULNA SOUTH ON TURNKEY BASIS CONTRACT NO : PGCB/230KV/SS/KS Schedule No. B3 : Design Services Design Local Currency in Taka Item Desctiption Unit Qty Foreign Currency - All Design Cost for this Contract is deemed to be included in Schedule Nos. B1, B2, and B4. - - Not applicable Not applicable - - Total Price carried to Summary of Price Schedule Schedule B3-1 DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132kV KHULNA SOUTH SUBSTATION ON TURNKEY BASIS Schedule_B4 -Installation & Other Services Item 1A Description Unit Qty (1) 245 kV Air Insulated Switchgear 1A.1 SF6 Circuit breaker, live tank, single pole operating sets 2 1A.2 Single throw horizontal center air break , post type disconnector switch with E/S , 1600A sets 2 1A.3 Single throw horizontal center air break, center rotating post type disconnector switch without E/S , 1600A sets 8 1A.4 Single phase current transformer nos. 6 1A.5 1A.6 nos. nos. 6 6 lot 1 nos. 4 i) Single phase capacitive voltage transformer CVT Single phase surge arrester Flexiable Conductor for jackbus , jumper & equipment connection Post insulators Strain Insulators and fittings including all necessary clamps and connectors Insulator lot 1 ii) Fittings lot 1 Clamps & Connectors Steel Structures & cable tray lot 1 i) Gantry Column including nuts bolts lot ii) Gantry Beam including nuts bolts Equipment support structures including nut&bolts 1A.7 1A8 1A.9 iii) 1A.10 iii) iv) Cable tray including fitting, fixing & accessories lot 1 lot 1 Local Currency Prices in Bangladesh Taka Unit Price (2) DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132kV KHULNA SOUTH SUBSTATION ON TURNKEY BASIS Schedule_B4 -Installation & Other Services Item 1B Description Unit Qty (1) Control, Protection and Metering 1B.1 Complete control & protection panel for two sets of overhead line circuits to Mongla (Mongla -1 & 2) set 2 1B.2 Extension, connection and modification to existing busbar protection and synchronization with existing system lot 1 1B.3 Tariff meters (imp & exp) for two new lines lot 1 1C. Multicore Cables 1C.1 Multicore Low Voltage power and control cable lot 1 i) ii) 1D.1 lot lot lot 1 1 1 i) LV power Cable LV Control Cable Earthing and Lightning Protection System Earthing System lot 1 ii) Lightning Protection System lot 1 1E DC Distribution Connection Lot 1 Lot 1 1E.1 1F 1F.1 Extension of existing DC distribution system with necessary MCB/MCCB etc. for connecting the new line feeder equipment with 110V & 48V DC system LVAC Distribution Extension of existing LVAC system for connecting the new line feeder equipment Local Currency Prices in Bangladesh Taka Unit Price (2) DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132kV KHULNA SOUTH SUBSTATION ON TURNKEY BASIS Schedule_B4 -Installation & Other Services Item 1G1 Description Unit Qty (1) Civil Works and Foundation i) Outdoor gantry foundation Lot 1 ii) Outdoor equipment Foundation Lot 1 iii) Cable trench extension Lot 1 iv) Surface drain extension Lot 1 v) vi) vii) Internal Road extension Switchyard surface finishing Gravel laying Lot Lot Lot 1 1 1 1H Lighting and small power 1H1 Lighting & Small Power lot 1 1I Fiber Optic Multiplexer Equipment for Teleprotection and Communication 1I.1 Extension of Indoor type Fibre Optic Multipexer Equipment for communication and protection for Mongla 1 & 2 Lot 1 1I.2 Fibre Optic cable(48 cores) and termination box Lot 1 1I.3 Necessary works for integration of New bays with existing Areva, France make NLDC system. Lot 1 1J Digital Fault Disturbance Recorder 1J1 Extension and modification of existing digital fault disturbance recorder system Lot 1 Total: Local Currency Prices in Bangladesh Taka Unit Price (2) DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132kV KHULNA SOUTH SUBSTATION ON TURNKEY BASIS Schedule_B4 -Installation & Other Services Item Description Unit Qty (1) Local Currency Prices in Bangladesh Taka Unit Price (2) kV EXTENSION IN KEY BASIS rency Prices in Bangladesh Taka Total Price (3) kV EXTENSION IN KEY BASIS rency Prices in Bangladesh Taka Total Price (3) kV EXTENSION IN KEY BASIS rency Prices in Bangladesh Taka Total Price (3) kV EXTENSION IN KEY BASIS rency Prices in Bangladesh Taka Total Price (3) DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132kV KHULNA SOUTH SUBSTATION ON TURNKEY BASIS SCHEDULE B5: SUMMARY OF PRICE SCHEDULE Foreign Currency Price: Foreign Currency Prices Description of Works 1 Extension of Khulna South Substaton Outside Employer's Country Total Price FOB Insurance Freight Total CIF Price 2 3 4 5=(2+3+4) Outside Employer's Country (Schedule B1) Within the Employer's Country Total EXW Price Total Excluding VAT EXW 6 F/C Cost Excluding VAT on 7=5+6 N/A Within Employer's Country (Schedule B2) N/A N/A N/A N/A Design Service (Schedule B3) N/A N/A N/A N/A N/A ` N/A TOTAL FOREIGN CURRENCY AMOUNT Local Currency Price: Local Currency Prices in Bangladesh Taka Within the Emplyoer's Country Description of Works 1 Outside Employer's Country (Schedule B1) Extension of Khulna South Substaton Total Price EXW incuding VAT Transportation & Handling to destination Insurance to Destination Installaton and other services Total Amount Local Insurance to Destinaton Local Transportaton & Handling Cost to Destinaton 2 3 4 5 6=2+3+4+5 7 8 N/A N/A N/A N/A N/A N/A N/A N/A N/A Within Employer's Country (Schedule B2) Installation & other Service (Schedule B4) Outside the Employer's Country N/A N/A N/A N/A TOTAL AMOUNT (Bangladesh Taka) TOTAL CONTRACT PRICE in words . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . The above price shall appear on the FORM OF PRICE BID N/A: Not applicable. plus Bangladesh Taka . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Schedule B: Bid Price Schedule B5-1 Total L/C Cost excluding VAT on EXW 9=6+7+8 Schedule B5-2 POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230KV EXTENSION IN EXISTING 230/132KV SUBSTATIONS AT KHULNA SOUTH ON TURNKEY BASIS [CONTRACT NO. PGCB/230kV/SS/KS] SCHEDULE C BAR CHART PROGRAMME OF KEY ACTIVITIES SC-1 POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132KV KHULNA SOUTH SUBSTATION ON TRUNKEY BASIS. SCHEDULE C TIMES FOR DELIVERY AND COMPLETION The individual dates are all contractually binding. The times given under Column D are the commissioning target dates at present planned to be achieved and may be the subject of mutual adjustment. Column A details the earliest dates by which access to site can be given for storage purposes. The times entered under column B are to be the dates guaranteed for arrival at Site of the first shipment of parts for the circuits in question being also the dates when the contract requires access to the Site for plant erection, to the extent necessary to enable him to proceed with work to meet the dates under column C guaranteed for complete delivery, erection and commissioning of the shipment. The times include all necessary control, relay, metering, auxiliary power ancillary equipment to enable the respective circuit or item of plant to be completely commissioned and put into commercial operation, together with such other associated equipment, e.g. busbars, etc as will ensure that subsequent shutdown are unnecessary or at least only of a temporary or short time nature. The dates assume an order is placed by . . . . . . . . . . . . . . . . . . . . . (to be advised or stated by Bidder) Site Khulna South A* Latest Access Permitted 7 days from the date of signing of the Contract B* Guaranteed Arrival of first shipment C* Guaranteed Completion 365 days D* Target Completion * Time in days, from contract effective date. Preliminary SLD, overall layout and control building drawings of the Technical Specifications shall be provided within 2.0 months of the contract commencing date. SC-2 Design, Supply, Erection, Testing & Commissioning of 230kV Extension of Existing 230/132kV Khulna South Substation SCHEDULE C BAR CHART PROGRAM M E OF K EY ACTI VI TI ES 1 2 3 Equipment Drawings of single line diagram Drawings of 132kV and 33kV Switchgear Layout Drawings of 132kV Switchgear Equipment Manufacture of 132kV &33kV Switchgear Equipment Manufacture of Control, Protection, and Metering System Factory Routine Test Delivery of equpment to site Foundation Calculation/Drawings of gantry structures and equipment supports Calculaiton /Drawings of control building Calculaiton /Drawings of earthing System Construction and Installation Works Site Survey Geo-technical survey Switchyard - Piling - Foundation works incl. earthing - Cable trenches - Gantry and equpment support installation switchgear equipment installation - Busbars, Jumper condcutors and OH earthwire installation Construction of Control Building/GIS Bulding Cable laying & Termination Installation of LVAC & DC system Installation of Indoor equipment (Control, protection, metering & FOX and DFDR etc.) Testing & Commissioning Note: Time to complete the plant and services from the effective date is 12 months SC-3 4 5 6 7 8 9 Time Period in month 10 11 12 POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230KV EXTENSION IN EXISTING 230/132KV SUBSTATIONS AT KHULNA SOUTH ON TURNKEY BASIS [CONTRACT NO. PGCB/230kV/SS/KS] SCHEDULE D MANUFACTURERS, PLACES OF MANUFACTURE AND TESTING Schedule D: Manufactures, place of manufacture and testing SD-1 POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY,ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132KV KHULNA SOUTH SUBSTATION ON TRUNKEY BASIS. SCHEDULE D MANUFACTURERS, PLACES OF MANUFACTURE AND TESTING The following Subcontractors and/or manufacturers are proposed for carrying out the item of the facilities indicated. Bidders are free to propose more than one for each item. Item 1 Description Proposed Subcontractors/ Manufacturers 245 kV AIS SWITCHGEAR Steel Structure Circuit Breaker Disconnector Current Transformer Voltage Transformer Surge Arrester Flexible Conductor Earth Wire Clamps Connectors Insulator -Post -Disc Schedule D: Manufactures, place of manufacture and testing SD-2 Place of Manufacture Place of Testing and Inspection Item Description Proposed Subcontractors/ Manufacturers Fittings Steel Structures 2 PROTECTION METERING AND CONTROL Panels Instruments Protective relays Meters Transducers Energy Meter 3 4 DFDR DC EQUIPMENT Distribution Boards 5 6 415 kV SWITCH FUSE BOARD MULTICORE CABLES XLPE Insulated Cables Cable trays 7 EARTHING Copper flatbar/ Copper conductor Insulated copper Schedule D: Manufactures, place of manufacture and testing SD-3 Place of Manufacture Place of Testing and Inspection Item Description Proposed Subcontractors/ Manufacturers Conductor Earthing Rod Exothermic Joint 8 FIBRE OPTIC MULTIPLEXER EQUIPMENT 9 SITE ERECTION AND COMMISSIONING BY CIVIL WORKS Design to be performed by:Constructed by:- Schedule D: Manufactures, place of manufacture and testing SD-4 Place of Manufacture Place of Testing and Inspection Item Description Schedule D: Manufactures, place of manufacture and testing Proposed Subcontractors/ Manufacturers SD-5 Place of Manufacture Place of Testing and Inspection POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230KV EXTENSION IN EXISTING 230/132KV SUBSTATIONS AT KHULNA SOUTH ON TURNKEY BASIS [CONTRACT NO. PGCB/230kV/SS/KS] SCHEDULE E TECHNICAL PARTICULARS AND GUARANTEES Technical particulars & Guarantees SE-1 SCHEDULE E TECHNICAL PARTICULARS AND GUARANTEES General 230kV AIR INSULATED SWITCHGEAR (AIS) Sl. No. Description Unit 1. Site Condition Max. Altitude above sea level m Max. Ambient temperature outdoor ℃ Min. Ambient temperature outdoo ℃ r Max. Ambient relative humidity % Max. Seismic acceleration at floor level - horizontal g - vertical g 2. Electrical Data Rated Voltage kV Rated Frequency Hz Insulation Level - lightning impulse withstand kVp - switching impulse withstand kVp - 50 Hz withstand 1 minute kV Rated continuous current at 40℃ ambient temperature - main busbar and bus coupler A - transformer bay A - line bay A Rated short time withstand - current kA - duration Sec Rated peak withstand current kA 3. Secondary Circuit Auxiliary voltage - for control and signal V dc - for remote control V dc - for heating - tolerances V ac % Technical particulars & Guarantees SE-2 230kV PART 1 - SWITCHGEAR 1.1 HV OUTDOOR CIRCUIT BREAKERS Bidders Data Sl. No. Description 1 Manufacturer 2 Type Reference (Manufacturer’s designation) 3 Number of Poles 4 Rated Voltage 5 Rated frequency 6 Rated normal current-feeder/transformer/bus coupler A 7 Rated breaking currents: Line charging Cable charging Small inductive kA rms 8 Rated short-circuit breaking current kA,rms 9 First pole to clear factor 10 Rated transient recovery voltage for terminal faults if other than standard 11 Rated characteristics for short-line faults 12 Rated short-circuit making current 13 Rated operating sequence 14 Rated duration of short-circuit s 15 Rated out of phase breaking current kA 16 Rated opening time ms 17 Rated break time ms 18 Rated closing time ms 19 Unit kV kA Maximum arcing time of any duty cycle to IEC 56 ms 20 Is circuit-breaker re-strike free Yes/No 21 Test Authority 22 Test Certificate ref. 23 Rated short time withstand current kA 24 Rated duration of short-circuit s 25 Rated peak withstand current kA 26 Rated insulation levels:- 26.1 Lightning impulse withstand to earth kV pk (wave shape 1.2/50µs) Technical particulars & Guarantees SE-3 245kV Bidders Data Sl. No. Description Unit 26.2 Lightning impulse withstand across open kV pk contacts (wave shape 1.2/50µs) 26.3 Power frequency voltage withstand to earth kV rms 26.4 Power frequency voltage withstand across open contacts kV rms 27 Rated supply pressure of gas for interruption MPa (g) 28 Limits for correct operation max min MPa (g) MPa (g) 29 Frequency of operation yr-1 30 Operating mechanism Manufacturer 31 Mechanism Type: 32 Trip free/or fixed trip 33 Is lockout facility fitted? 34 Closing supply Volts Amps V A max/min 35 Rated supply voltage of shunt opening release V 36 Current required at rated supply voltage to open circuit-breaker Spring charging motor - Current - Voltage AC/DC A 37 A V 38 Number of auxiliary switch contacts - normally open - normally closed - adjustable 39 Other auxiliary loads: Voltage: Current: 40 Degree of Protection for (a) auxiliary circuits (b) moving parts 41 Minimum clearances in air: (a) between phases (b) phases to earth (c) across interrupters (d) live parts to ground level mm mm mm mm Minimum creepage (a) to earth (b) across interrupter terminals mm mm Radio interference voltage μV 42 43 Technical particulars & Guarantees SE-4 245kV Bidders Data Sl. No. Description Unit 44 Guaranteed maximum gas leakage % per annum 45 Number of interrupters per pole 46 Material of interrupter chamber 47 Wall thickness of interrupter chamber 48 Material of contact surfaces primary arcing 49 Length of each break mm 50 Length of stroke mm 51 Operating rod for moving contact(s) material dimensions, etc. 52 Weight of circuit-breaker unit complete 53 Maximum shock load imposed on floor or foundations when opening under fault conditions (state whether tension or compression) 245kV mm kg kg 54 Quantity of gas in complete three-phase circuit breaker 55 Maximum pressure rise in circuit breakers due to the making or breaking of rated current 56 Routine pressure test on circuit-breaker tanks or containers 57 Pressure type test on circuit-breaker tanks or containers 58 Interrupting gas pressure at 20C Normal 59 Limits of gas pressure at 20C Maximum Minimum 60 Period of time equipment has been in commercial operation 61 Number of the same type of circuit breakers supplied to date 1.2 DISCONNECTORS AND EARTHING SWITCHES Bidders Data Sl. No. Description 1 Manufacturer 2 Type Number 3 Operating type (a) Unit horizontal/vertical break Technical particulars & Guarantees SE-5 245kV Sl. No. Bidders Data Description Unit (b) Pantograph (c) Number of support insulation for pole (d) Number of breaks per pole (e) Material of contact surfaces (f) Type of Contacts 4 Rated normal current A 5 Rated short time withstand current kA, rms 6 Rated duration of short time current s 7 Rated peak withstand current kA pk 8 Rated insulation levels: 8.1 Lightning impulse withstand to earth (waveshape: 1.2/50µs) kV pk 8.2 Lightning impulse withstand across open contacts (waveshape: 1.2/50µs) kV pk 8.3 Power frequency voltage withstand to earth kV rms 8.4 Power frequency voltage withstand across open contacts kV rms 9 Method of operation 10 Type of operating mechanism manual/power 11 Operating power 12 Voltage/pressure rated max min V/MPa(g) V/MPa(g) V/MPa(g) 13 Consumption electric A 14 Operating time: open max min ms ms 15 Operating time: close max min ms ms 16 Manual operating torque kNm 17 Load switching capability A 18 Mechanical Terminal Load N 19 Insulator Creepage mm 20 Radio interference voltage mV 21 Number of auxiliary switches normally open normally closed adjustable Technical particulars & Guarantees SE-6 245kV Sl. No. Bidders Data Description 22 Other auxiliary loads voltage current 23 Mechanical endurance: Unit 245kV Number of operations carried out for mechanical operation test 24 Degree of protection for 1) auxiliary circuits 2) moving parts 25 Total weight of three pole disconnector complete 26 Type test certificate date/reference 27 Period of time equipment has been in commercial operation 28 Number of the same type of disconnectors supplied to date 1.3 kg CURRENT TRANSFORMERS (line bay) Sl. No. Bidders Data Description 1 Manufacturer/type 2 Rated primary current A rms 3 Rated secondary current A rms 4 Rated frequency Hz 5 Highest voltage for equipment kV 6 Rated insulation level - primary winding kV 7 Lightning impulse withstand kV pk 8 (a) (b) kV rms kV rms 9 Insulator creepage (phase to earth) 10 Electrical dissipation factor at power frequency test voltage 11 Radio influence voltage measured at U/3 1 MHz µV 12 13 Rated short term thermal current for 1s Rated short term thermal current for 3s A rms A rms 14 Rated dynamic current kA pk 15 Insulation class 16 Number of secondary windings Location of core Unit Power frequency withstand (dry) Power frequency withstand (wet) Technical particulars & Guarantees mm SE-7 245kV 17 18 Core 1 Rated output Accuracy class * Accuracy limit factor Core 2 Rated output Accuracy class * Accuracy limit factor Core 3 Rated output Accuracy class * Accuracy limit factor Core 4 Rated output Accuracy class * Accuracy limit factor Class x winding: Rated knee point emf Exciting current *including instrument security factor where applicable Is earth screen fitted between primary and secondary windings Type test certificate ref/date 1.4 Sl. No. V A VOLTAGE TRANSFORMERS Description Unit Bidder’s Data 245kV 1 Manufacturer - 2 Type No. - 3 Transformer type - 4 Rated primary voltage kV rms 5 Rated secondary voltage for each secondary winding kV rms 6 Accuracy class for each winding Rated output for each winding Rated volt-ampere rating for each winding 7 Rated voltage factor 8 Type of Insulation 9 Maximum temperature rise C 10 Short-circuit withstand capability kA rms 11 Primary insulation 11.1 Lightning impulse withstand dry kV pk 11.2 (a) (b) kV rms kV rms 12 Partial discharge magnitude pC 13 Total external creepage distance mm VA VA Power frequency withstand wet Power frequency withstand dry Technical particulars & Guarantees SE-8 Sl. No. Description Unit 245kV 14 Radio influence voltage measured at 11 Um/3 at 1 MHz µV 15 Total installed weight kg 16 Capacitor 16.1 High voltage capacitor (C1) pF 16.2 Intermediate - voltage capacitor (C2) pF 16.3 Total Capacitor (Cn) pF 17 18 19 20 Open circuit intermediate voltage Rated open-circuit intermediate voltage Reference range of frequency Reference range of temperature kV kV +/- Hz o C 21 Protective device to limit overvoltage 1.5 SURGE ARRESTERS Sl. No. Description 1 Manufacturer 2 Model Number 3 Type: 4 Continuous operating voltage kV rms 5 Rated voltage kV rms 6 Standard nominal discharge current kA 7 Reference current at ambient temperature mA 8 Reference voltage for above kV rms 9 Steep current impulse residual voltage kV pk 10 Lightning impulse residual voltage at 5kA 10kA 20kA kV pk kV pk kV pk 11 Bidder’s Data Unit Bidder’s Data 245kV Duty Class 12 Discharge class 13 Pressure relief class 14 Nominal diameter of resistor blocks 15 Number of resistor blocks connected electrically in parallel Technical particulars & Guarantees mm SE-9 16 Number of separately housed units per phase 17 Overall height of arrester (without supporting structure) m 18 Overall height of arrester including grading ring if applicable mm 19 Clearances: phase to earth (from centre line) phase to phase (centre line to centre line) mm mm 20 Overall Weight of arrester (without supporting structure) kg 21 Maximum cantilever strength Nm 22 Maximum force due to wind (at maximum specified gust speed) Nm 23 Minimum creepage distance over insulator housing mm 24 Insulator shed profile - Reference Document 25 Terminal palm details - Drawing No. 26 Earthing terminal - Drawing No. 27 Type & Description of surge monitoring device 28 Type test certificate ref/date 29 Number of the same type of surge arresters supplied to date 1.6 POST TYPE INSULATORS Sl. No. Nominal System Voltage 1 Manufacturer 2 Insulator material 3 IEC.273 reference 4 Insulator type and manufacturer’s reference 5 Maximum working vertical load: tension compression kN kN 6 Minimum failing load (tension) kN 7 Maximum bending working load kN 8 Minimum failing load (torsion) Nm Technical particulars & Guarantees 245 kV SE-10 9 Minimum failing load (bending) 10 Shed profile (to be enclosed with Tender) Drawing No. 11 Greatest diameter 12 Number of units in one insulator 13 Overall length per complete post mm 14 Weight of complete post kg 15 Electrostatic capacity pF 16 Power frequency withstand voltage (dry) kV 17 Power frequency withstand voltage (wet) kV 18 Dry lightning impulse withstand voltage 1.2/50 micro sec. Wave kV Minimum creepage distance: (a) Specified, subject to acceptable shed profile (b) Guaranteed mm mm 20 Protected creepage distance mm 21 Radio influence voltage measured at Um/3 at 1 MHz µV 19 1.7 kN mm INSULATOR STRINGS Sl. No. Nominal System Voltage 1 Manufacturer 2 Insulator type (normal) and manufacturer’s reference 3 Insulation material 4 Number of units per string 5 Outside diameter mm 6 Distance between centres mm 7 Length of string overall mm 8 Maximum working load kN 9 Minimum failing load per unit kN Technical particulars & Guarantees 245 kV SE-11 10 Mechanical routine load test kN 11 Electro-mechanical failing load kN 12 Mechanical failing load kN 13 Electrostatic capacity pF 14 Weight of complete string kg 15 50 Hz 1 minute withstand voltage of unit (dry) kV 16 50 Hz 1 minute withstand voltage of unit (wet) kV 17 Minimum 50 Hz puncture voltage kV 18 Dry lightning impulse withstand voltage of string1.2/50 micro sec. Wave kV Minimum creepage distance per unit: (a) Specified, subject to acceptable shed profile (b) Guaranteed mm mm 20 Protected creepage distance per unit mm 21 Radio influence voltage measured at Um/3 at 1 MHz µV 1.8 CONDUCTORS AND CONNECTIONS 19 Sl. No. Nominal System Voltage A. FLEXIBLE CONDUCTORS Manufacturer 1 2 3 245 kV 4 Conductor material Material specification aluminium alloy Minimum use of grease 5 Number of sub conductor per phase 6 7 8 Nominal diameter of conductor Rated current (site rating) Temperature rise at rated current 9 10 11 Short time withstand current for 1 sec Peak withstand current Conductor spacer type description reference: Technical particulars & Guarantees SE-12 / C 12 Creep period of conductor B. 1 SHIELD WIRES Manufacturer 2 3 Conductor material Material specification aluminium alloy C. CLAMPS AND FITTINGS Manufacturer years Types Maximum working stresses D STEEL STRUCTURES 1 Manufacturer 2 Proposed standards for steel Technical particulars & Guarantees SE-13 2. AUXILIARY POWER AND MULTICORE CONTROL CABLES Item Number of core Core section Core diameter Conductor insulation Type of filler Type of tape Sheath thickness Sheath outer diameter Armour wires Armour wires diameter Outer covering Outer covering thickness Completed cable: diameter weight per metre maximum drum length Minimum installed bending radius Maximum conductor temperature 01 02 03 04 mm2 mm mm mm mm no. mm type mm kg m mm C SE-14 05 06 07 08 09 10 11 12 13 14 15 PART 3- FOR DCDB & LVAC EQUIPMENT Sl.No. 3.1 Description Bidder's Data Miniature Circuit Breakers For DCDB 1 Manufacturer 2 Manufacturer’s type designation 3 Rating Amps 4 Fault Rating for 1 sec KA 5 Voltage Volts 3.2 Miniature Circuit Breakers for LVAC 1 Manufacturer 2 Type 3 Rating Amps 4 Fault Rating for 1 sec kA PART 4 - PROTECTION 4.1 LINE PROTECTION FOR 230 kV OVERHEAD LINE BETWEEN KHULNA –MONGLA Bidders Data MAIN 1 DISTANCE PROTECTION 1 Manufacturer 2 Manufacturer’s type designation 3 Phase switched Yes/No 4 Zone switched Yes/No 5 Number of zones 6 Shape of impedance characteristic Zone 1 Zone 2 Zone 3 7 Reverse looking element (blocking signal initiation) 8 Sensitivity: 8.1 Minimum operating current Earth faults Phase faults amps amps SE-15 8.2 8.3 8.4 8.5 8.6 Minimum necessary voltage for fault at zone 1 reach point (if applicable) Earth faults Phase faults Volts Volts Minimum zone 1 ohmic impedance to which relay can be set Ohms Maximum zone 1 ohmic impedance to which relay can be set and maintain accuracy Ohms Minimum zone 2 ohmic impedance to which relay can be set Ohms Maximum zone 2 ohmic impedance to which relay can be set and maintain accuracy Ohms MAIN 1 DISTANCE PROTECTION (Continued) 8.7 Maximum zone 3 ohmic reach Forward reach Reverse reach ohms ohms Arc forward and reverse reach setting independent of each other? Yes/No Can resistance and reactance reaches be set independent of each other Yes 11 Directional sensitivity volts 12 Current transformer requirements 13 Voltage transformer requirements 14 Back up zone time ranges Zone 2 Zone 3 9 10 15 secs secs Method used to clear close-in faults (a) which occur when line is already energised in service (b) which exist upon line energisation SE-16 16 Has distance protection previously been used in the type of blocking scheme offered for this contract? If yes: (a) (b) 17 number of schemes in service year first in service Approximate number of years distance relay in service. (A complete reference list should be submitted stating client, system voltage and year of going into service). SE-17 Yes/No MAIN 1 DISTANCE PROTECTION (Continued) 18 Zone 1 operating times when relay fed from capacitive voltage transformer. This section must be completed in addition to supplying diagrams showing the effect of source to line ratio and fault position on operating times. 18.1 Earth faults: Operating time m.sec Source to Line Ratio Fault Position % of Relay Setting 1 0 (relay point) 50 90 10 0 50 90 30 0 50 90 18.2 Minimum Maximum Phase to Phase Faults Operating time m.sec Source to Line Ratio Fault Position % of Relay Setting 1 0 (relay point) 50 90 10 0 50 90 30 0 50 90 SE-18 Minimum Maximum 18.3 Three Phase Faults: Operating time m.sec Source to Line Ratio Fault Position % of Relay Setting 1 0 (relay point) 50 90 10 0 50 90 30 0 50 90 19 Minimum Directional Earth Fault Protection Associated with Main 1 Distance Protection 19.1 Manufacturer 19.2 Manufacturer’s type designations 19.3 Current setting range: (a) Forward element (b) Reverse element 19.4 A A Minimum polarising quantity required for correct directional decision Voltage (a) Forward element V (b) Reverse element V Current (a) Forward element (b) Reverse element 19.5 Characteristic angle 19.6 Time ranges: (a) Blocking scheme (b) Back-up 19.7 19.8 V V degrees sec sec Has protection previously been used in the blocking scheme offered for this contract? CT requirements SE-19 Yes Maximum 4.2 LINE PROTECTION FOR 230 kV OVERHEAD LINE BETWEEN KHULNA –M0NGLA MAIN 2 DISTANCE PROTECTION Bidders Data 1 Manufacturer 2 Manufacturer’s type designation 3 Phase switched Yes/No 4 Zone switched Yes/No 5 Number of zones 6 Shape of impedance characteristic Zone 1 Zone 2 Zone 3 7 Reverse looking element (blocking signal initiation) 8 Sensitivity: 8.1 Minimum operating current Earth faults Phase faults amps amps Minimum necessary voltage for fault at zone 1 reach point (if applicable) Earth faults Phase faults Volts Volts Minimum zone 1 ohmic impedance to which relay can be set ohms Maximum zone 1 ohmic impedance to which relay can be set and maintain accuracy ohms Minimum zone 2 ohmic impedance to which relay can be set ohms Maximum zone 2 ohmic impedance to which relay can be set and maintain accuracy ohms 8.2 8.3 8.4 8.5 8.6 SE-20 4.2 MAIN 2 DISTANCE PROTECTION (Continued) 8.7 Maximum zone 3 ohmic reach Forward reach Reverse reach ohms ohms Arc forward and reverse reach setting independent of each other? Yes/No Can resistance and reactance reaches be set independent of each other Yes 11 Directional sensitivity volts 12 Current transformer requirements 13 Voltage transformer requirements 14 Back up zone time ranges Zone 2 Zone 3 9 10 secs secs 15 Method used to clear close-in faults (a) which occur when line is already energised in service (b) which exist upon line energisation 16 Has distance protection previously been used in the type of blocking scheme offered for this contract? If yes: (a) number of schemes in service (b) year first in service 17 Approximate number of years distance relay in service. (A complete reference list should be submitted stating client, system voltage and year of going into service). SE-21 Yes/No 4.2 MAIN-2 Distance Protection (continued) 18 Zone 1 operating times when relay fed from capacitive voltage transformer. This section must be completed in addition to supplying diagrams showing the effect of source to line ratio and fault position on operating times. 18.1 Earth faults: Source to Line Ratio 1 30 Phase to Phase Faults Source to Line Ratio 1 30 10 30 Operating time m.sec Minimum Maximum Three Phase Faults: Source to Line Ratio 1 Fault Position % of Relay Setting 0 (relay point) 50 90 0 50 90 0 50 90 10 18.3 Operating time m.sec Minimum Maximum 0 (relay point) 50 90 0 50 90 0 50 90 10 18.2 Fault Position % of Relay Setting Fault Position % of Relay Setting 0 (relay point) 50 90 0 50 90 0 50 90 SE-22 Operating time m.sec Minimum Maximum 19 Directional Earth Fault Protection Associated with Main 1 Distance Protection 19.1 Manufacturer 19.2 Manufacturer’s type designations 19.3 Current setting range: (a) Forward element (b) Reverse element 19.4 A A Minimum polarising quantity required for correct directional decision Voltage (a) Forward element V (b) Reverse element V Current (a) Forward element (b) Reverse element 19.5 Characteristic angle 19.6 Time ranges: (a) Blocking scheme (b) Back-up 19.7 19.8 V V degrees sec sec Has protection previously been used in the blocking scheme offered for this contract? Yes CT requirements 4.3 230 kV AUTO RECLOSE EQUIPMENT 4.3.1 Auto Reclose Relay 1 Manufacturer 2 Manufacturer’s type designations 3 Dead time ranges: (a) High speed single phase reclosure (b) Delayed three phase reclosure secs secs 4 Reclaim time range secs 5 Does the circuit breaker duty cycle permit any combination of dead time and reclaim time within the above ranges? Yes/No 4.3.2 Dead Line Check Relays 1 Manufacturer SE-23 2 Manufacturer’s type designations 3 Voltage setting ranges (a) Busbar voltage (b) Line voltage volts volts 4 Any time delays (specify function and value) 4.3.3 Synchronising Check Relays 1 Manufacturer 2 Manufacturer’s type designations 3 Setting ranges (a) Phase angles (b) Voltage difference (c) Frequency degrees volts Hz 4 Any time delays (specify function and value) 4.4 BUSBAR PROTECTION 1 Manufacturer 2 Manufacturer’s type designations 3 Operating principle, e.g. high impedance 4 Minimum relay setting 5 Sensitivity of scheme, (allowing for CT magnetising current, etc) 6 Maximum through fault current at which protection is stable A A 7 CT requirements 8 Estimated magnetising current at relay setting A 9 Operating time at twice relay minimum setting msec 10 Operating time at ten times relay minimum setting msec 4.5 4.5.1 1 CIRCULATING CURRENT PROTECTION T-Point Protection 2 Manufacturer’s type designations 3 Operating principle, e.g. high impedance 4 Minimum relay setting Manufacturer A SE-24 5 Sensitivity of scheme, (allowing for CT magnetising current, etc) 6 Maximum through fault current at which protection is stable A 7 CT requirements 8 Estimated magnetising current at relay setting A 9 Operating time at twice relay minimum setting FEEDER END Protection msec 4.5.2 1 Manufacturer 2 Manufacturer’s type designations 3 Operating principle, e.g. high impedance 4 Minimum relay setting 5 Sensitivity of scheme, (allowing for CT magnetising current, etc) 6 Maximum through fault current at which protection is stable A A 7 CT requirements 8 Estimated magnetising current at relay setting A 9 Operating time at twice relay minimum setting msec SE-25 4.6 INVERSE TIME OVERCURRENT AND EARTH FAULT PROTECTION 1 Manufacturer 2 Manufacturer’s type designations 3 Inverse time element 3.1 Range of current settings: - overcurrent - earth fault amperes amperes 3.2 Range of operating times at highest timing setting at ten times current setting seconds 3.3 Range of operating times at highest timing setting at twice current setting seconds 4 High set instantaneous element Range of settings: - overcurrent - earth fault amperes amperes 5 Transient overreach at X = 10 R 6 Operating time with Maximum offset current at 5 times current setting 7 Burden of relay on minimum inverse time element current setting at a current ten times setting - overcurrent - earth fault SE-26 msecs VA VA 4.7 BREAKER FAILURE PROTECTION 1 Manufacturer 2 Manufacturer’s type designations 3 Setting of current elements: - phase faults - earth faults amperes amperes 4 Timer setting range seconds 5 Burden of relay at minimum current setting at 10 times CT secondary rated current during: - phase fault - earth faults VA VA 6 Operating time reset time m secs m secs 4.8 TRIPPING RELAYS 1 Manufacturer 2 Manufacturer type designation 3 Nominal operating voltage V 4 Minimum operating voltage V 5 Operation indicator 6 Operating time at nominal voltage m sec 7 Contact rating: Make and carry continuously Make and carry for 3 secs Break: resistive Inductive VA VA watts VA 4.9 OVERALL FAULT CLEARANCE TIMES AT KHULNA 1 Busbar Faults 2 Main protection relay operating time ms Auxiliary and tripping relay time (where used) ms Circuit breaker time ms Total ms KHULNA –MONGLA 230kV Line Faults SE-27 2.1 2.2 Fault Clearance at Khulna (Main 1) Distance protection maximum operating time ms Permissive scheme time delay ms Auxiliary relay time (where used) ms Circuit breaker time ms Total clearance time at Khulna ms Fault Clearance at Khulna (Main 2) Distance protection maximum operating time ms Permissive scheme time delay ms Auxiliary relay time (where used) ms Circuit breaker time ms Total clearance time at Khulna ms 4.10 OVERALL FAULT CLEARANCE TIMES AT Mongla 1 Busbar Faults 230 kV Main protection relay operating time ms Auxiliary and tripping relay time (where used) ms Circuit breaker time ms Total ms 2 KHULNA-MONGLA 230kV Line Faults 2.1 Fault Clearance at Mongla (Main 1) 2.2 Distance protection maximum operating time ms Permissive scheme time delay ms Auxiliary relay time (where used) ms Circuit breaker time ms Total clearance time at Mongla ms Fault Clearance at Mongla (Main 2) Distance protection maximum operating time SE-28 ms Permissive scheme time delay ms Auxiliary relay time (where used) ms Circuit breaker time ms Total clearance time at Mongla ms SE-29 PART 5 Digital Fault and Disturbance Recorder [DFDR] 5.1 Digital Fault and Disturbance Recorder [DFDR] (A) GENERAL 1 2 3 (B) 1 2 3 4 5 d e 6 7 8 9 10 (C) 1 2 3 4 (D) 1 2 3 4 5 6 Manufacturer’s name & address Type Power Supply -power Supply for printer UNITS VDC VAC ANALOGUE INPUTS Number of Channel -Expandability Nominal Current Nominal voltage - Current Frequency response Cut-off frequency (a) Bandwidth (b) Attenuation at (c) Auto adjusted anti-aliasing filters for chosen sampling rate Simultaneously programmable sampling rate for all feeders/inputs -Locally Changeable -Remotely Changeable Possible sampling rates DC coupled inputs Resolution Accuracy Burden 1. Current Circuit at IN 2. Voltage Circuit Over load 1. Current 2. Voltage circuit DIGITAL INPUTS Amp Vac/Vdc mA/Amp dB dB Yes/No Yes/No Yes/No Samples/sec Samples/sec Samples/sec Yes/No bits % VA VA % In % Vn Number of Channel -Expandability (Without and time skew) Selectable input level Type Resolution Vdc ms MEMORY Size Type Pre-fault time (fast scanning rate) Post-fault (fast scanning rate Pre and Post-fault time (slow scanning rate) In-Built hard disk (auto-maintained MB sec sec sec GB SE-30 BIDDER’S DATA Sl. (E) ITEM SENSORS/ TRIGERRING CRITERIA UNITS Yes/No 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. All sensors/trigerrs are preferable Programmable and Virtually recordable Logical combination sensor Three phase over or under Voltage / Current Mono phase over or under Voltage / Current *du/dt, dp/dt, dq/dt, [Single/3 Phases], df/dt. etc. RMS [Voltage / Current] Zero Sequence Negative, Positive Sequence Frequency DC Step Pendling / Swing Digital level and edge Sensor trigger Event Trigger Manual Trigger Remote Trigger (F) CLOCK SYSTEM 1. 2. 3. 4. Internal Clock Accuracy External Synchronization Time resolution between 2 synchronized pulses (G) 1. 2. 3. 4. (H) BIDDER’S DATA Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No OUTPUT ALARM RELAY CONTACT Max. operation Voltage DC/AC Make and carry for 0.5 sec Carry Continuously Break ( DC ) – resistive Vac / Vdc A A W INTERFACE FOR DATA COMMUNICATION 1. 2. 3. 4. 5. Full definition compression Maximum transmission rate Standard serial port ( EIA-232-D) Printer Port Dedicated serial port for modem Yes/No bits / Sec Yes / No Yes/No Yes/No (I) PRINTER DATA 1. 2. 3. 4. Printer amplitude (scaling peak to peak) Time Scal (mm / s ) Printer resolution Auto printing mm Yes/No (J) Fault Priority transmission Yes/No (K) Fault location (distance calculation) Yes/No (L) Test certificates from internationally recognized Laboratories Yes/No (M) COMMUNICATION AND REMOTE ANALYZING UNIT (MHz) Yes/No 1. Processor Pentium 2. Co-Processor Pentium Yes/No 3. Main memory capacity (Mb) Yes/No 4. Color graphics board S-VGA Yes/No 5. Screen S-VGA Yes/No 6. Hard disk unit Yes/No 7. Printer Yes/No 8. Modem Yes/No *Note: du/dt=Change of voltage, dp/dt=Change of active power, dq/dt=change of reactive power, df/dt=Change of frequency. SE-31 SE-32 PART-6: Extension of Existing AREVA, France make Fibre Optic Multiplexer Equipment For Communication and Protection 6.1 FIBRE OPTIC MULTIPLEXER EQUIPMENT 6.1.1 6.1.1.1 6.1.1.2 6.1.1.3 GENERAL: Name of the Manufacturer Model No. Type: Unit Bidders Data Bidder shall provide all necessary information which deem to be necessary to complete the project in all respects. SE-33 PART-7: Extension of Existing AREVA, France make Remote Terminal Unit (RTU) Equipment For SCADA 7.1 REMOTE TERMINAL UNIT (RTU) EQUIPMENT 7.1.1 7.1.1.1 7.1.1.2 7.1.1.3 GENERAL: Name of the Manufacturer Model No. Type: Unit Bidders Data Bidder shall provide all necessary information which deem to be necessary to complete the project in all respects. SE-34 PART 8 - FIBRE OPTIC MULTIPLEXER EQUIPMENT SL. No. 1 2 3 Description Unit GENERAL: Manufacturer Model No. Type Type of multiplexer Complying to ITU-T rec. Transmission Capacity Mbit/s channels channels Access capacity on 64 kbit/s Access capacity on 2 Mbit/s Redundant central processor Digital cross connect function Available AGGREGATES: Optical aggregates (ITU-T G.957) Available TRUNK INTERFACES: HDB3, 2 Mbit/s interfaces per module No. Complying to ITU-T rec. HDSL, 2Mbit/s interface: no of copper wires - Capacity on 2Mbit/s or on 1Mbit/s - Capacity selectable 4 5 6 7 8 9 10 11 Available USER INTERFACES Voice interfaces for trunk lines: 1 + 1 com path protection, available for all Analogue, 4wire with E&M: Input level Output level Analogue, 2wire with E&M: Input level Output level Digital, 2Mbit/s CAS or PRI Voice interfaces for remote Subscriber: 2wire, subscriber side 2wire, PABX side Integrated teleprotection No. ch ch / pair of wir e dBr dBr dBr dBr dBr dBr Interface for Commands: Number of independent commands Transmission time max. Signal voltage 1 + 1 com path protection Interface(s) for Differential Protection: Electrical interface: G.703 Optical Interface Data: channels per module 1 + 1 com path protection, available for all V.24/V.28 (RS-232): up to 38.4kbit/s V.11/X.24 (RS-422): 64kbit/s V.35: 64kbit/s V.36 (RS-449): 64kbit/s G.703: 64kbit/s Ethernet: 10/100 BaseT WAN capacity Protocols No. ms Vpeak kbit/s kbit/s No. No. No. No. No. No. Mbit/s Mbit/s Integrated alarm gathering module: Number of external alarms per module Auxiliary power supply for ext. contacts No. SE-35 Bidder’s Data SL. No. 12 13 14 Description Unit Network Management System Type/Name of configuration tool For fault / configuration management For local / remote operation Data communication network (DCN) Ambient Conditions: Storage: ETS 300 019-1-1, class 1.2 Transport: ETS 300 019-1-2, class 2.2 Operation: ETS 300 019-1-3, class 3.1E Power Supply Operation Fully redundant power supply Bidder’s Data °C / % hum °C / % hum °C / % hum VDC Bidder shall provide all necessary information which deem to be necessary to complete the project in all respects. SE-36 POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230KV EXTENSION IN EXISTING 230/132KV SUBSTATIONS AT KHULNA SOUTH ON TURNKEY BASIS [CONTRACT NO. PGCB/230kV/SS/KS] SCHEDULE F DEPARTURES FROM THE SPECIFICATION Schedule F: Departure from Specification SF-1 POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY,ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132KV KHULNA SOUTH SUBSTATION ON TRUNKEY BASIS. SCHEDULE F DEPARTURES FROM THE SPECIFICATION Bidders are to list all departures from the requirements of the specification in this schedule. All departures whether they be commercial, financial, technical or of a contractual nature are to be included and shall be submitted with the Technical proposal Any item that does not have a departure listed in this schedule will be deemed to be in full accordance with the requirements of the specification. No other document or detail accompanying the tender will be considered in evaluating departures. Bidders are not permitted to offer any alternative to this schedule. Item Volume Clause Schedule F: Departure from Specification Detail of Departure from Specification SF-2 POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230KV EXTENSION IN EXISTING 230/132KV SUBSTATIONS AT KHULNA SOUTH ON TURNKEY BASIS [CONTRACT NO. PGCB/230kV/SS/KS] SCHEDULE G PROPOSED ALTERNATIVE STANDARDS POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132KV KHULNA SOUTH SUBSTATION ON TRUNKEY BASIS. SCHEDULE G PROPOSED ALTERNATIVE STANDARDS TO WHICH EQUIPMENT SHALL BE PROVIDED The bidder shall list below all the alternative engineering and design Standards, which he proposes to use in his design, manufacture and testing of equipment to be supplied. Should these standards differ from the specified standard in any respect, the bidder shall detail the differences between the proposed and specified standard. Compliance with any standard equal or superior to those specified will be considered acceptable. In the absence of any listed alternative standard, it is deemed that the standards specified in the Tender documents are fully complied with. Specified Standard Schedule G: Proposed Alternative standards Alternative Standard Number Title SG-2 POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230KV EXTENSION IN EXISTING 230/132KV SUBSTATIONS AT KHULNA SOUTH ON TURNKEY BASIS [CONTRACT NO. PGCB/230kV/SS/KS] SCHEDULE H PROPOSED CONTRACT AND SITE ORGANISATION Schedule H: Proposed contract & site organization and site resources SH-1 POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132KV KHULNA SOUTH SUBSTATION ON TRUNKEY BASIS. SCHEDULE H PROPOSED CONTRACT & SITE ORGANISATION Personnel Bidders should provide the names of suitably qualified personnel to meet the requirements specified in Section 3 (Evaluation and Qualification Criteria) of Volume 1 of 3 of the Bidding Document. The data on their experience should be supplied using the Form below for each candidate. Form PER – 1: Proposed Personnel 1. Title of position* Name 2. Title of position* Name 3. Title of position* Name 4. Title of position* Name *As listed in Section 3 (Evaluation and Qualification Criteria). Schedule H: Proposed contract & site organization and site resources SH-2 Form PER – 2: Resume of Proposed Personnel Position Personnel information Name Date of birth Professional qualifications Present employment Name of employer Address of employer Telephone Contact (manager / personnel officer) Fax E-mail Job title Years with present employer Summarize professional experience in reverse chronological order. Indicate particular technical and managerial experience relevant to the project. From To Company / Project / Position / Relevant technical and management experience Schedule H: Proposed contract & site organization and site resources SH-3 POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230KV EXTENSION IN EXISTING 230/132KV SUBSTATIONS AT KHULNA SOUTH ON TURNKEY BASIS [CONTRACT NO. PGCB/230kV/SS/KS] SCHEDULE I DRAWING AND DOCUMENTS TO BE SUBMITTED WITH BID Schedule I: Drawings and Documents SI-1 POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132KV KHULNA SOUTH SUBSTATION ON TRUNKEY BASIS. SCHEDULE I DRAWINGS AND DOCUMENTS TO BE SUBMITTED WITH TENDER Please refer to Volume 1 of 3 in Section 6 (Employers Requirements) of the Bidding Document. Schedule I: Drawings and Documents SI-2 POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230KV EXTENSION IN EXISTING 230/132KV SUBSTATIONS AT KHULNA SOUTH ON TURNKEY BASIS [CONTRACT NO. PGCB/230kV/SS/KS] SCHEDULE J PROPOSED SUBCONTRACTORS Schedule J: Proposed Subcontractor SJ-1 POWER GRID COMPANY OF BANGLADESH LIMITED BIDDING DOCUMENT FOR DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 230kV EXTENSION IN EXISTING 230/132KV KHULNA SOUTH SUBSTATION ON TRUNKEY BASIS. SCHEDULE J PROPOSED SUBCONTRACTORS The bidder shall propose a list of the Sub-contractors in the following table as per sub-clause 2.6, Item 7, Section-3, Evaluation and Qualification Criteria, Volume 1 of 3 of the Bidding Document. Sl. No. Name and Address of the Subcontractor Signature Date Schedule J: Proposed Subcontractor SJ-2 -------------------------------------------------------------------