ADDITIONAL DETAILS SOUGHT BY EAC (INDUSTRY-1), MOEF&CC, NEW DELHI FOR ENVIRONMENTAL CLEARANCE FOR THE PROPOSED 10.0 MTPA INTEGRATED STEEL PLANT, 900 MW CAPTIVE POWER PLANT AND TOWNSHIP NEAR BARENDA VILLAGE, SONAHATU BLOCK, RANCHI DISTRICT, JHARKHAND STATE Project Proponent JSW JHARKHAND STEEL LIMITED RANCHI, JHARKHAND Environmental Consultant: Vimta Labs Limited 142, IDA, Phase-II, Cherlapally, Hyderabad–500 051, www.vimta.com (QCI/NABET Accredited EIA Consultancy Organization NABL/ISO 17025 Certified Laboratory, Recognized by MoEF, New Delhi) October, 2015 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State I INTRODUCTION M/s. JSW Jharkhand Steel Limited proposes to establish 10.0 Million Tonnes Per Annum (MTPA) capacity Integrated Steel Plant (ISP) along with 900 MW Captive Power Plant (CPP) and township near Barenda village, Sonahatu block in Ranchi district of Jharkhand state. II PURPOSE OF THE REPORT The proposed project proposal was considered by the reconstituted Expert Appraisal Committee (Industry) in its 6th meeting held during 5th- 7th March, 2013 and further reconsidered in its 8th meeting held during 16th and 17th May 2013, for prescribing TORs vide their letter no. F. No. J-11011/377/2012-IA-II (I) dated 24th June, 2013 for undertaking detailed EIA/EMP study. EIA/EMP has been prepared and submitted to state PCB for conducting public hearing which was held on 21/9/2014 and public concerns and comments were taken into consideration for preparing the final EIA/EMP report. Final EIA/EMP report was submitted to MoEF&CC on 18/03/2015. The project proposal was considered by 37th Expert Appraisal Committee, MoEF&CC for Environmental Clearance during meeting held on 1st May, 2015 at New Delhi. After detailed deliberations, the committee sought the following additional information to be submitted for further consideration. SR. NO 1 2 3 4 5 6 7 8 9 10 11 12 13 ADDITIONAL INFORMATION POINTS Land details provided in the EIA report at page C2-10 should be resubmitted clearly indicating the type of land and actual land in possession. The unit should be in Ha Detailed plan should be submitted for the storage of raw material with emission mitigation measures Complete details for the proposed ETP for the Blast Furnace and Coke oven plant, including design of ETP to meet the cyanide standards stipulated by MoEF under EPA Act 1986 should be provided Details regarding use of SMS and BF slag / flyash in cement manufacturing should be provided Revise ash balance and ash equalization plan should be submitted Trace element report should be corrected and submitted Iron ore analysis to be rechecked and submitted Stamp charging + HPLA commitment in coke oven plant to be provided Commitment for the use of CDQ to be submitted Details regarding Poly aromatic hydro carbon monitoring should be submitted SMS slag utilization scheme to be submitted SMS plant-dog house details for fugitive emission centres should be submitted SMS–dry system to be adopted and details should be submitted VIMTA Labs Limited, Hyderabad PAGE NO. 2 5 16 26 32 32 32 33 33 33 33 33 40 1 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State 14 15 16 17 18 19 20 21 22 23 24 Sinter plant–secondary emission mitigation detail should be provided Advanced CO monitoring system should be established and details should be provided Specific water consumption and water balance should be submitted SOx, NOx line emission data used for all the units, including flow rate taken should be submitted Revised table for pollution control measures should be submitted Details on benzol plant as Tar utilisation should be provided Action plan for waste management for each component should be submitted The Committee prescribed an amount of Rs. 700 cr over a period of 10 years for the CSR related activity. A detailed plan in this regard should be submitted Town plan detail should be submitted including the layout of the buildings, green belt, internal roads, STP, parking plan etc Details regarding the proposed captive thermal power plant should be submitted Commitment to achieve zero effluent discharge in coke oven as BF to be provided 44 46 49 51 51 53 63 71 73 75 100 The present report includes the replies to the above points sought by EAC, MoEF&CC, New Delhi. III POINT WISE REPLY ON THE QUERIES 1.0 LAND DETAILS PROVIDED IN THE EIA REPORT AT PAGE C2-10 SHOULD BE RESUBMITTED CLEARLY INDICATING THE TYPE OF LAND AND ACTUAL LAND IN POSSESSION. THE UNIT SHOULD BE IN HA. The proposed project will be developed over an area of 1538 ha of land falling in 7 villages. There are mainly 3 types of land involved, (a) Raiyati land (Non-CNT land) (b) Raiyati land (CNT land) and (c) Government land (GM land). The details of actual land in possession (land in ha) till date is given below: VIMTA Labs Limited, Hyderabad 2 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State VIMTA Labs Limited, Hyderabad 3 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State VIMTA Labs Limited, Hyderabad 4 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State 2.0 DETAILED PLAN SHOULD BE SUBMITTED FOR THE STORAGE OF RAW MATERIAL WITH EMISSION MITIGATION MEASURES. Facilities to be provided for receipt, unloading, stacking, reclamation, blending and distribution of different raw materials have been described below. 2.1 Raw Material Handling Systems (RMHS) The major raw material include iron ore fines, iron ore lumps, coking coal, non-coking coal (for CDI), limestone and dolomite. The locations of major raw material storage and handling facilities shall be planned carefully to have optimum conveyor length from storage yards and to the wagon tipplers. The annual requirement of major raw materials required for the proposed steel plant is indicated in TABLE-2.1. TABLE-2.1 PROJECTED ANNUAL REQUIREMENT OF MAJOR RAW MATERIALS Sr. No. Raw Material 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Iron Ore fines for Beneficiation Plant Iron Ore Lumps Limestone (BF Grade) Dolomite (BF Grade) Quartzite Limestone (SMS Grade) Dolomite (SMS Grade) Coking Coal for Captive Mines Imported Coking Coal Non-Coking Coal for PCI Thermal Coal Bentonite Ferro Alloy Limestone/clinker (Cement/Grinding unit) Gross Annual Requirement (Million Tonnes) 29.00 0.90 1.30 1.10 0.14 1.60 0.70 5.52 4.80 2.30 3.00 0.40 0.20 6.00 Following points have been considered while finalizing the system design concept. i. ii. iii. iv. v. The major raw materials like iron ore fines, iron ore lump, coking coal, fluxes, limestone and dolomite will be brought to the plant by railway wagons and unloaded by wagon tipplers. Transportation of raw materials like iron ore fines, iron ore lump coking coal and limestone and dolomite from RMHS to respective hoppers/bunkers of consuming units will be done accordingly. The limestone required for pellet plant, may be transported from RMHS yard to pellet plant by truck/dumpers since the quantity is small. RMHS yard will be designed for minimum storage requirement of all major raw materials which will be finalised during detailed engineering. Pellet storage facilities will be provided inside the pellet plant. The finished product i.e. pellets can either be transported to DR plant or blast furnace by belt conveyor or may be stored in the pellet storage yard with the help of a movable tripper. Pellets will be reclaimed from the yard as and when required and sent to DR plant and blast furnace by the belt conveyor system. VIMTA Labs Limited, Hyderabad 5 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State vi. vii. viii. ix. x. xi. SMS grade limestone and dolomite will be reclaimed from RMHS yard and sent to lime calcinations plant (LCP) by belt conveyor. Burnt lime and calcined dolomite from LCP to SMS will also be transported by belt conveyors. Coking coal from RMHS yard to coke oven will be transported by means of belt conveyor system. Sinter plant raw material will be transported from RMHS to sinter plant by belt conveyor system. The blast furnace will receive its ferrous burden from sinter plant and pellet plant. Coke will be transported from coke oven to BF by belt conveyor system and the additives will also be transported from RMHS to stock house by belt conveyor system The slag generated from the blast furnace will be transported to slag grinding unit after granulation. Design of Raw Material Handling System is indicated in TABLE-2.2. TABLE-2.2 DESIGN OF RAW MATERIAL HANDLING SYSTEM Material Req. for 10.0 Mtpa Steel Plant Bulk Density t/yr t/m3 Size Nos. Storage (t) Days Iron Ore Fines 29,900,000 2.3 500m x 36m x 11m 4 910,800 10 Iron Ore Concentrate 22,000,000 2.1 500m x 36m x 11m 2 415,800 7 Base Mix Raw Material 2.2 Longitudinal Covered Storage Stockpile Size Storage Capacity 16,500,000 1.9 500m x 36m x 11m 4 752,400 16 Indigenous Flux 8,540,000 1.5 500m x 36m x 11m 3 445,500 17 Imported Flux 2,300,000 1.5 500m x 36m x 11m 1 148,500 21 PCI Coal 1,600,000 0.8 500m x 36m x 11m 1 79,200 16 Unwashed Coking Coal 7,820,000 0.8 500m x 36m x 11m 3 237,600 10 Washed Coking Coal 3,900,000 0.8 500m x 36m x 11m 1 79,200 7 Imported Coking Coal 4,800,000 0.8 500m x 36m x 11m 5 396,000 26 Thermal Coal 3,000,000 0.8 500m x 36m x 11m 2 158,400 17 Brief Description of RMHS Wagon tipplers in combination with side arm chargers have been envisaged for unloading BOX/BOXN and other types of tippable wagons. The track system provided along with tipplers and track hoppers are adequate to handle a full train consisting of 45 Nos. of BOBS wagons or 58 Nos. of BOXN wagons and also to cater to the future increased number of wagons per train. The incoming materials from wagon tipplers will be conveyed from unloading yard to the storage yard for stock piling through conveyor systems. Each line of the conveyor system between raw materials unloading yard and raw materials storage yard are designed to convey materials at a suitable rate which shall be finalised during detailed engineering. VIMTA Labs Limited, Hyderabad 6 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Pellet Handling System Pellets from the pellet plant can either go to the screen house or stored in the pellet yard through a stacker-cum-reclaimer. After screening, over size is carried to DR plant and under size is stored in bunker for evacuation and reuse. Also, pellets will be transported to BF stock house by conveyor from Pellet plant. Product Handling System DRI from product bins of DR plant will be conveyed to the storage bunkers of DRI in steelmaking shop. Required quantity of DRI, lime and dolomite will be drawn from the storage bunkers in SMS by belt weigh feeders which will discharge the material on to another conveyor which can feed the material either to BOF or to the ladle furnace through movable type vibro feeder and chute. The materials will be dribble fed into BOF during melting operation. Ferro Alloy Handling System Ferro alloys i.e., ferro-manganese, ferro-silicon and other materials like spar, etc. will be brought to SMS from central stores by trucks in self discharging type containers. The containers will be lifted crane and materials discharged into the storage bunkers by placing the containers on the storage bunkers. The empty containers will be sent back to the central stores for refilling. Required quantity of ferro alloys and other additives will be drawn from the storage bunkers by electromagnetic vibro feeders and weigh hoppers which will discharge the material on to another conveyor which can feed the material either to ladle or to the ladle furnace on to the RH-TOP through conveyor. Provision will be kept for programmed charging of bulk materials and ferro alloys in the BOF, ladle furnace and RH-TOP. Suitable provision of suction of dust through suitably designed duct network will be kept. The same will be cleaned and discharged to the atmosphere through tall stacks. Ore and Flux Supply System to Sinter Plant Iron ore fines, limestone, dolomite and coke breeze will be reclaimed from the storage yard by respective stacker–cum-reclaimer and these materials will be transported to sinter plant bins through a system of conveyors. Miscellaneous plant arising’s from lime and dolo calcination plant, mill scale, flue dust, return sinter fines will be transported by belt conveyor to sinter plant bins. Transportation of Material to Blast Furnace Sinter from sinter plant and pellet from pellet plant will be conveyed to blast furnace stock house by belt conveyors. Sized coke will be transported to BF stock house directly from coke oven battery through a well-developed conveyor system. Coal Handling System Coal will be received in railway wagons and unloaded by wagon tippler. Coal will be conveyed to coal storage yard by belt conveyors and stock pile will be made by stacker–cum-reclaimer. Reclaimed coal will be sent to coal preparation unit for processing prior to charging to ovens and also to CPP and Coal Dust injection for Blast Furnaces. VIMTA Labs Limited, Hyderabad 7 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State List of Major Equipment in RMHS Major equipment of Material Handling System are:• • • • • • • • • • • • • • Belt Conveyors and related equipment, Belt Feeder, Shuttle Conveyor and Reversible Shuttle Conveyor System Vibratory Feeders Gates Motorised Diverter Gate Weigh Hoppers Belt Weigh Scales (BWS) Vibration Isolation System Travelling Tripper and Bunker Sealing Arrangement In-line Magnetic Separator (ILMS) & Suspended Magnetic Separators Metal Detectors (MD) & Magnet Charging hatches Cranes and Hoists Transfer Cars Vulcanising Machine and Mobile Belt Changing units However for liners in different area such as all storage bins/ bunkers, chutes, skirts, flap gates etc. shall be provided with suitable wear liners ensuring the flow ability. The liner schedules are as follows: Bunkers and wagon tippler hopper For lump size between 20 mm to 80 mm, Special Steel reinforced rubber liner of 40 mm thick (min) / ceramic impregnated rubber liner shall be used for conical portion and 1 m vertical height. Chutes For lumps of 40 mm thick and above material special Steel reinforced rubber liner of 40 mm thick (min) in secondary impact zone and 60 mm thick special steel reinforced rubber liner in primary impact zone shall be considered. For material less than 40 mm, 20 mm thick PU liner/SS-409 M (8 mm)/ ceramic impregnated rubber liner min 30 mm thick may be used. Skirts, Fixed hopper & Gates SS409M Liner shall be used. Belt Weigher The accuracy of belt weigher scale shall be 0.5%. Any conveyor drives where motor power requirement is more than 200 KW rating shall be provided with double drives on either side of the conveyor drive pulley. Other equipment envisaged in this RMHS are: (a) Wagon Tippler with Side Arm Charger Side Arm Charger The Side Arm Charger mainly consists of the following. VIMTA Labs Limited, Hyderabad 8 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Trolley with wheels and side guide roller, universal coupling arm along with hydraulic system for lifting. Travel drive complete with hydraulic motor, brakes, and hydraulic power pack. Rails with foundation bolts & nuts, racks & pinions. End stops, Festoon Cable & Trolley with heavy duty carriage and supporting structures. Hydraulic Side Arm Charger coupler / decoupler. Operator's cabin mounted on trolley of Side Arm Charger. Any other item/ accessory/ fixtures to complete supply of the equipment. Application The Side Arm Charger shall be used for wagon positioning at the wagon tippler for unloading of materials. It shall be used for pushing/pulling a rake of 58 wagons of 110 T gross weight each and locating wagons one by one on tippler. The system shall be considering future scenario of additional wagons and weight per rake. Working A train of 58 loaded wagons shall be brought in by a locomotive pushing/ pulling and stopped with the leading wagon within range of the side arm charger using track side marker boards. The loco will be decouple and dispatch and the charger shall be driven to the leading wagon. Its arm shall be lowered and it shall be coupled to the first wagon of the train. The train shall be hauled forward by the charger until the front of the first wagon is about 4 m away from the tippler. The charger shall stop and the first wagon shall be uncoupled from the train. The charger shall then inch forward to the leading wagon on to the tippler, automatically decouple itself & arm is raised before it travels back to the train. The tippler shall rotate for tippling the wagon. On reaching near the standing train, the charger arm shall be lowered and shall be coupled to the train ready for repeating the cycle. In the next cycle the train shall be drawn up by one wagon length, the front wagon will be decoupled & the next cycle will be repeated. When the next wagon is located on the tippler table the previously tippled wagon shall be ejected simultaneously. On the out haul side the empties form a new train ready for collection by a locomotive. Wagon Tipplers Wagon Tippler with hydraulic clamping mainly consists of the following. Tippler Table with rails, end frame with necessary rack segments, side beam with rubber pads. Wagon Tippler hydraulic drive with cylinders, power pack, necessary hoses etc. Hydraulic clamping system with cylinders, power pack, necessary hoses etc. Vibrator assembly mounted on tippler. All foundation bolts. Control Cabin for the Wagon tippler and Side Arm Charger can be operated jointly or independently. Separate water spray system shall be provided for sprinkling water on the material in the wagon just before entering the wagon tippler. Any other item / accessory / fixtures to complete supply of the equipment. Emergency stopper for inhaul wagon rake once it is within operating range of the side arm charger. VIMTA Labs Limited, Hyderabad 9 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Dust suppression system. All related electrics and electrical equipment. Application Wagon Tippler shall be used for mechanised unloading of broad gauge wagons carrying raw materials such as lump iron ore, iron ore fines, Mn ore, Quartzite, limestone, Dolomite, coal etc. The wagon tippler shall be fed with loaded wagons one by one by Side Arm Charger. Tippled empty wagons shall be collected on the empty side by ejection while placing loaded wagons on the tippler. The wagon tippler shall unload the materials into receiving hoppers for onward transportation to stock yard. The system shall be considering future scenario of additional wagons and weight per rake. Typical Technical Parameters Type Capacity No. of tips/hour Rail gauge Angle of tippling Duty Type of clamping Type of drive : Hydraulic indoor type : 110 T gross : 20-25 : 1676 mm : Minimum 175 deg. anti-clockwise looking from wagon entry side. : 24 hrs/day (continuous) : Hydraulic : Hydraulic motor (b) Stacker Reclaimer These equipment are meant to stack the raw material in the yards and also to reclaim the same for conveying to the consuming departments. Typical Technical Specification Stacking rate Coal Ore Reclaiming rate Coal/Ore Long travel speed No of buckets Type of drive : : : : : : 1000 TPH 1200 TPH 500 TPH-750 TPH 15 m/min 8 Hydraulic (c)Twin Boom Stacker: This equipment is meant to stack iron ore fines/coal in the yards. Typical Technical Specifications: Stacking capacity Rail centers Boom Luff speed Boom inclination Long travel speed VIMTA Labs Limited, Hyderabad : : : : : 1200 TPH 7000 mm 4 m/min -12 deg to 16 deg 20 m/min 10 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State (d) Barrel Reclaimer This equipment is meant to reclaim iron ore fines for conveying to pellet plant. Typical Technical Specification: Reclaiming capacity : 1000 TPH Barrel speed/Cutting speed : 2.4 rpm/41.09 m/min Bucket volume : 322 lts Barrel cutting dia : 5450 mm Stock Yard Details To meet the need of raw materials for 10 MTPA Integrated Steel Plant and 900 MW Captive Power Plant with 6.0 MTPA Cement/Grinding Plant, a stock yard and related bulk material handling system will be put up in the designated area in the plant. Open type Longitudinal Yard Large quantities of raw materials are handled by following systems. Wagon tipplers - It is used to unload the cargo from railway wagons Stacker cum reclaimers - It is used to stack the raw materials and reclaim from the stack as per the need. Twin boom stackers Long conveyor belts • • • • Proposed Stockpile Details Length of stockpiles – 800 m Width of stockpiles - 36 m Height of stockpiles - 11 m Closed Type Circular and Longitudinal Yard The shed type storage facility is composed with a concrete wall on each side and divided by sections to store raw material. Raw material is charged by belt conveyor and tripper installed on top of the wall and discharged by a semi-portal reclaimer. Shed type storage facility is applied when storing two (2) or more different types of raw material. Circular dome storage is shown in Figure-2.2.1. Equipment Description 1. Tipper Tipper stacks raw materials into the designated place in the shed storage. This is rail mounted and moves along the rail front and back. Receiving belt is connected into this tipper. 2. Semi-portal Reclaimer Semi-portal reclaimers are sorted for ore, coal and sub-material. All of them are operated automatically in base, remotely at Main Control Room (MCR) and manually for emergency. They have CCTV that have up and down tilting, right and left rotating and zooming functions for supervising facilities and automatic VIMTA Labs Limited, Hyderabad 11 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State remote control. CCTV shall have degree of full visibility that make out the fall of raw materials through the screen at night. 3. Scraper Boom The scraper boom's sides shall have proper shapes to eliminate the attached material on side walls. The attached material on side walls after reclaiming shall be less than 350 mm. 4. Belt Conveyor Receiving line It is conveying belt system which receives iron ore, coal and limestone from yard. Discharging Line After raw material is stored, it discharges with certain amount reclaimed into the conveying system which discharges to the plant respectively as required. Advantages of Closed Stock Yard Larger Capacity Storage capacity increased by 1~2 times Land reduced by about 50% Manning reduced over 30% Transfer process reduced by 40% Fully-automation Energy Saving Compact Layout & small logistic Reducing over 85% material loss Reducing consumption in Sintering coking & iron making Small maintenance of spare parts Reducing operation cost Obtain high quality of raw material Least Disturbance Wind and rain protection Thunderstorm protection Reducing shattering of Lump materials Stabilizing material features Prevents contamination of water from bad weather Moisture content is less affected by rains The closed yards can be either circular dome type or longitudinal type. The final selection of open/closed yards would be done during detailed engineering. VIMTA Labs Limited, Hyderabad 12 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State 2.3 Environmental Pollution Control & Mitigation Measures The main environmental issue relating to raw materials handling and storage is the fugitive emission of particulate matter arising from material transfers, dumper and other vehicular traffic, and wind erosion of the piles of the raw material storage. A secondary concern is the suspended solids and, in some cases, oil contained in the runoff water from the storage areas. Fugitive emissions of particulate matter are normally controlled by spraying stockpiles with water or crusting agents and ensuring that roads and wheels of dumpers and other vehicles are kept clean. The water runoff is generally directed to a wastewater treatment plant. The equipment selected would be adequate to maintain the government stipulated norms. Air Pollution Control The raw material and handling facilities shall include the dust suppression systems for the wagon tippler, all conveyor transfer points and junction houses from wagon tippler to existing yard and conveying system and transportation of lump ore in intermediate building. Plain water dust suppression system with nozzles shall be provided at wagon tippler top. Dual fluid (Dry fog) type of dust suppression system (DFDS) shall be provided for wagon tippler bottom, all conveyor transfer points and junction houses and receiving and transportation of lump ore in intermediate building. The water addition in DFDS shall not be more than 0.1% of the weight of material being handled. Equipment and System Description The dual fluid dust suppression (DFDS) works of the principle of agglomeration. Dust particles released from a material handling or processing plant which becomes air borne, are made to pass through a blanket of extremely fine fog. The dust particles and the micron sized fog droplets collide and adhere to each other, thus increasing their mass. After a series of such collisions, the mass becomes heavy enough to cause settlement of the agglomerates on to the larger mass of the material being handled. The system uses an air driven acoustic oscillator nozzle which is capable of producing super fine atomization of water droplets that greatly increase the dust particle to water droplet contact resulting in settlement of dust. The fine droplets evaporate before wetting anything but the dust. The water addition is 0.1% of the weight of material being handled. The DFDS system comprises of main equipment installed at the application points and auxiliary equipment installed at central water and compressed air supply point. Plain Water Dust Suppression System for Wagon Tippler Top Plain water dust suppression system shall be provided at wagon tipper top at the time of tippling. Necessary pumps with 100% standby, pipes, fittings, valves, VIMTA Labs Limited, Hyderabad 13 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State nozzles, etc. as required shall be provided. The operation of this dust suppression system shall be interlocked with the operation of the wagon tippler. Fugitive Emission Control A typical Fugitive Emission Control system practised in the following areas at similar steel plants are described below• • • • • • Dust Suppression System Wind curtains Paved areas Vacuum Cleaning Tyre washing Cyclones & bag filters Fig.I: Foam Dust Suppression System VIMTA Labs Limited, Hyderabad Fig.II:Dust Suppression System 14 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Fig.III:Spraying of Stockyards with Latex Fig.IV:Wind Curtain in Coal Yard Fig.V:Vaccum Sweeping of Roads Fig.VI:Water Spraying in Coal Yards Source:-Existing practices at JSW Vijayanagar Steel Plant --------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- VIMTA Labs Limited, Hyderabad 15 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State 3.0 COMPLETE DETAILS FOR THE PROPOSED ETP FOR THE BLAST FURNACE AND COKE OVEN PLANT, INCLUDING DESIGN OF ETP TO MEET THE CYANIDE STANDARDS STIPULATED BY MOEF UNDER EP ACT 1986 SHOULD BE PROVIDED. 3.1 Effluent Treatment Plant – Coke Oven Plant In the process of treating coke oven gas from the batteries, surplus liquor is generated. This liquor is treated for removal of ammonia, cyanide in ammonia stills by distillation and then further treated in a biological oxidation unit called the BOD unit. The unit comprises aerobic and anaerobic action to reduce phenols, cyanides, ammonia to the desired levels. Effluent Treatment Quantity and Water Quality – BOD Treatment The estimated effluent quantity to be treated shall be 2 x 295 m³/h. Considering certain fluctuation of the domestic effluent produced in the plant area and redundancy of the effluent treatment device, 2 x 350 m³/h will be taken as for biochemical treatment quantity. Inlet Water Quality (Mixed Water) Sr. No 1 2 3 4 5 6 7 8 Parameters COD BOD3 NH3-N Phenol Sulfide HCN Oil SS Ranges 1500~3000 mg/l 600~1300 mg/l 150~250 mg/l 500~650 mg/l 20 ~ 50 mg/l 8 ~ 20 mg/l 200 ~ 300 mg/l 100~350 mg/l Effluent Treatment process As for the high content of COD and ammonia nitrogen in the effluent, which is highly toxic, biochemical treatment flow shall adopt effective process targeting to coking effluent water: “pretreatment + anaerobism + pre-SND-Nitration + Bio-oxidization + advanced treatment or as commonly referred “Pre-treatment+ A2/O2+ advanced treatment” . Process Block Diagram of BOD Plant is shown in Figure-3.1.1. VIMTA Labs Limited, Hyderabad 16 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State FIGURE-3.1.1 PROCESS BLOCK DIAGRAM OF BOD PLANT VIMTA Labs Limited, Hyderabad 17 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Process Description The entire effluent treatment flow is divided into 3 stages: First Stage Treatment Second Stage Treatment Third Stage Treatment Physiochemical treatment/Pre-treatment Removes Tar, Light Oil & Emulsions Physiochemical Process Biological Treatment • Anaerobic • Anoxic • Aerobic • Contact Oxidation Final Treatment • Coagulation • Filtration using The first stage is pre-treatment: including oil separation pool and air floatation pool; Firstly, the effluent enters into the oil separation pool for removing light oil and heavy oil. The collected light oil and heavy oil will be transferred to the condensing/blowing section for recycling and reusing. The effluent, which had the light oil and heavy oil removed, will enter air floatation pool to remove emulsified oil and gelled oil. The second step is biologic treatment stage: including anaerobic pool, anoxia pool, aerobic pool and contact oxidization pool; The effluent is regulated and enters anaerobic pool, in which, polycyclic compounds can be allosteric and delink by anaerobe, and some stuff that is difficult to be degraded by aerobic and facultative biology can be converted to substance that is easy to be degraded. The macro mole organic will be acid fermented and decomposed into small organic molecules. The effluent biodegradability is further improved. In anoxia pool, where there’s no O2. The facultative denitrifying bacteria will utilize the organic substance contained in coking effluent entered into anoxia pool as carbon source, and use the [O] of NO 3-, NO2- in the returned nitrified solution to carry out anaerobic respiration and decomposing the COD substance within the effluent. At the same time, the NO 3-, NO2- ions of the effluent will be restored into N2 and etc., and the denitrifying of NO3- and NO2- is accomplished. In the aerobic pool, sufficient air will be blown in and various nutrition stuff needed by biologic will be added. The cultivated aerobic microorganism is used to remove the remained COD and etc. pollutant. At the same time, in the aerobic pool, the nitrifying bacteria and nitrite bacteria are used to oxide the NH3-N in effluent into NO3-or NO2- ions. Outlet water passing through the intermediate sedimentation pool will enter into the contact oxidization pool to conduct further nitration treatment against effluent and reduce the content of ammonia and nitrogen compound in the water further. The third stage is of further treatment stage: final sedimentation and filter; Outlet water will be treated in coagulative sedimentation and lifted into the strainer to further remove organic substances and turbidities from water; all filtered effluent VIMTA Labs Limited, Hyderabad 18 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State water will be sent to the coke quenching section for reusing and no water will be drained outside the plant premises. This remaining mud will be put into the sludge concentrating pool for concentrating, and then be conveyed to the pressure filter being pressure filtered; mud cake will be mixed into coke making coal. In order to ensure biochemical treatment system proper operating and the quality of outlet water, during operation, the central control lab shall conduct chemical analysis regularly on water quality of all stages; the system also will be monitored and measured via level indicators, pressure meters, flow meters, etc. instruments. The effluent output shall meet the standards prescribed by CPCB, for integrated Iron & Steel plants GSR-277(E) dated 31st March, 2012. Quality of Output Water Sr. No 1 2 3 4 5 6 7 8 Parameters Ranges ≤250 mg/l ≤30 mg/l ≤50 mg/l ≤1 mg/l ≤0.2 mg/l ≤10 mg/l ≤100 mg/l 6.0-8.5 COD BOD3 NH3-N Phenol HCN Oil SS pH Sludge Handling The excess and waste sludge generated from the sedimentation tanks is pumped to the sludge concentration pool; After concentration the sludge dewatered by dosing cationic PAM and pressed to cake with press filter; The sludge cake is shifted to mix with the coal in coke plant; and The water separated during sludge concentration and pressing taken back to the primary stage of system; Chemical Addition Sr. No. Name of Chemical 1 SPFS (Solid Poly Ferric Sulphate) 2 Anionic Poly Acrylamide 3 Cationic Polyacrylamide 4 5 Area of Use Purpose a) Air floatation pool b) Coagulation reactor a) Air floatation pool b) Coagulation reactor Filter press unit De-hydrating the sludge Mono Sodium Phosphate a) Regulation pool b) Aerobic pool As a “P” source to maintain C:N:P Sodium Carbonate Aerobic pool To maintain pH between 7 to 7.5 Coagulant Flocculent [ VIMTA Labs Limited, Hyderabad 19 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Reusing water system In order to enhance the re-usage of water thus to reduce the consumption of fresh water, reusing water system is considered in the project, and it is composed of BOD water reusing system and regenerated water reusing system. BOD Water Reusing System In common operation, the water BOD treatment after being pressurized will be sent to coke oven battery, coal preparation, coke handling system and flue gas waste heat recovery system for re-using, and re-using water volume is 2 x 115 m3/h. The rest of BOD water will be sent to regeneration water plant for deeper and further treatment. When wet quenching is started, some of BOD water will go directly to wet quenching instead of going to regeneration water plant. This reusing water system will be arranged together with BOD system, and the designed water volume is 2 x 295 m3/h. Regenerated Water Reusing System This regenerated water reusing system is to combine some of BOD water with all the plant clear drainage water and then send it to regeneration water system for deeper and further treatment, thus the outlet water quality shall be achieved in such that it could be used as replenish water of water circulation system and sent to by-product water circulation system and condensing/blowing water circulation system as replenish water. The recommended designed water system is 2 x 150 m3/h, and this reusing water system shall be planned and supplied in together with regeneration water system. The above system parameters will be finalised during detailed engineering. Typical RO-Zero Liquid Discharge (ZLD) Plant JSW proposes to install RO-ZLD unit in phases. Stages of Treatment The plant comprises four stages of treatment. Pre-treatment • • Biological Treatment • • • • Pre Anoxic Aerobic Post Anoxic Ultra filtration Membrane Bio Reactor (MBR) Reverse Osmosis • • Equalization Ozonation Two Stages with Sea Water membranes Single Pass with Brackish Water membranes Evaporation • Crystallizer VIMTA Labs Limited, Hyderabad 20 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Process flow diagram of RO-ZLD Plant is shown below: Biological Treatment First RO System VIMTA Labs Limited, Hyderabad 21 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Second RO System ZLD System VIMTA Labs Limited, Hyderabad 22 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Crystalliser System Source: JSW Vijayanagar Plant The mixed salt from centrifuge of Crystallisation System is proposed to dispose to MoEF approved Hazardous Waste Disposal Company for secured landfilling. Inlet and outlet water quality parameters are given below: Sr. No 1 2 3 4 5 6 7 8 9 10 11 12 3.2 Parameters COD BOD pH Phenols Ammonical Nitrogen Cyanide Oil & grease Total suspended solids Total dissolved solids Alkanity as CaCO3 Total hardness Reactive silica Inlet Details 300 ppm 100 ppm 7-8 20 ppm 50 ppm 5 ppm 12 ppm 50-100 ppm 300 ppm 332 ppm 160 ppm 40 ppm Outlet Details <5 ppm 50 ppm 7-8 0.05 ppm <1 ppm 0.05 ppm BDL <2 ppm 250 ppm 80 ppm 70 ppm 5 ppm Effluent Treatment Plant – Blast Furnace The wastewater is treated in clarifiers and the treated water is recycled to the process. The blow down from the system is sent to gas cleaning and slag quenching. The wet gas cleaning plant may be subdivided into the following subsystems: Axial Cyclone, Scrubber and Demister VIMTA Labs Limited, Hyderabad 23 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Axial Cyclone The BF gas from the down comer axially enters the cyclone. A vortex is created in the separation chamber of the cyclone by means of diverter vanes. The resulting centrifugal force draws the dust particles contained in the gas to the chamber wall. The particles slide down the chamber wall into the dust-collecting chamber. The gas stream is diverted by the cone at the bottom of the separation chamber towards the top. The clean gas leaves the cyclone via the inner cylinder at the top of the separation chamber. Scrubber The BF gas stream coming from the cyclone enters the scrubber from the top. The gas enters the spraying zone of the scrubber and passes through the water curtains emitted by the injecting nozzles. The coarse dust particles contained in the gas stream are fixed into the water droplets produced by the spray nozzles. The dust loaded water droplets are collected in the sump for the spraying chamber and discharged to the water treatment plant. After having passed the water curtains, the gas is pre-cleaned. A certain amount of the pre-cleaned gas can be used for the pressurising of the hoppers of the Bell-Less Top. Downstream of the spraying chamber, the gas flows through the annular gap passage. Here, water is injected on top of the annular gap element before the gas flows through the annular gap. When entering the annular gap the gas flow is accelerated. The high gas velocity produces strong turbulence, so that the gas is mixed with the injected water. During this mixing, even very small dust particles are fixed by the water droplets and are removed from the gas. The dust laden water is collected in the annular gap zone sump and recycled to the spray nozzles at the top of the scrubber via recirculation pumps. The clean gas that may still contain free water droplets leaves the scrubber in direction of the demister. Demister The gas stream entering the demister passes through vanes inducing the gas stream an angular momentum. Inertia moves the water droplets contained in the gas stream to the wall. Here the water is collected at the bottom of the demister and is discharged to the recirculation pumps of the scrubber. The ‘dry’ gas leaves the demister via the outlet duct. Water Treatment Plant for the GCP Process Description Gas produced during the operation of the blast furnace is contaminated with particulate material. The gas cleaned by a wet scrubber producing wash water that contains the particulate material in suspension. In order to have proper water recirculation in the scrubbing system, solids must be removed and the water must be re-cooled to levels that are acceptable for the gas cleaning process. VIMTA Labs Limited, Hyderabad 24 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Correction of pH is made by addition of ferric chloride or sodium hydroxide in the carbon steel trough by means of automatic dosing pumps controlled by a pH meter located in the clarifier outlet pipe. Polyelectrolyte is also dosed in the inlet clarifier feed pipe to enhance solids separation in the clarifier. The water is fed to the clarifier where the solids settle and form sludge. The clarified water is discharged by gravity into a cooling tower and the cold water pumped back to the gas clearing unit. The sludge produced by the clarifiers is pumped to sludge buffer tank and, by piston diaphragm pumps to the press filters. The cake produced by the press filter is discharged directly to wheel loaders and trucks. Sludge Pumps Suction lines will be provided for the sludge pumps to allow for complete cleaning. Cooling Tower The cooling tower composed with three cells, one as stand by, each cell half flow-rate capacity. Filling (splash bars) and drop eliminator material will be made of polypropylene V2 class. The fan blades will be made of aluminium or fibre reinforced polyester. Bolts, nuts, and washers will be made of stainless steel. A platform for maintenance with handrails and an access door in each diffuser will be provided. Chemical Addition Installations For all chemical dosing stations the necessary pipes, valves and accessories from the dosing pumps up to the dosing points will be supplied. All chemical dosing station will be skid mounted type. Pumping Stations The above mentioned pumps will be executed according to the following considerations: Manifold installation will be foreseen with each suction line equipped with manual butterfly valve; the head line will be equipped with a mounting joint, check valve and butterfly pneumatic valve. Sludge lines will be provided with diaphragm or knife valves. Each pump group will have a standby unit; the pumps will have automatic failure detection and protection devices. Pumps for water containing suspended solids will be of special material, abrasion resistant, as required. --------------------------------------------------------------------------------------- VIMTA Labs Limited, Hyderabad 25 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State 4. DETAILS REGARDING USE OF SMS AND BF SLAG / FLYASH IN CEMENT MANUFACTURING SHOULD BE PROVIDED. 4.1 SMS Slag Utilisation The estimated SMS slag generation is 1.48 MTPA. The proposed BOF process of steel making leads to generation of following a) Converter slag : (160 – 180 kg/tcs) called convertor slag b) Hot metal pre-treatment slag : (20 kg/tcs) and c) Ladle furnace slag : (20 kg/tcs). Hot Metal Pre-Treatment Slag (HMPT): This slag is produced in the pre-treatment stage of steel making predominantly in the desulphurization stage. The composition of HMPT slag is given below; Particulars Fe2O3 SiO2 Al2O3 CaO MgO SO3 7.4 24.3 9.7 49.9 4.3 1.1 Percentage % HMPT slag is separately collected, crushed, and the iron bearing materials are removed. The non-metallic slag, is fed to sinter plant through base mix or through proportioning bins as a replacement of limestone in sintering. Converter Slag: (BOF or LD slag or steel slag) This slag is produced in the process of steel making in BOF convertors. The composition of steel slag is given below; Particulars Percentage % Fe2O3 SiO2 Al2O3 CaO MgO SO3 6.1 24.4 11.9 49.1 4.2 2.2 The molten slag is poured into pits in the slag bay and is allowed to cool. Water is sprayed on the hot slag to facilitate faster cooling. The slag is then processed in a series of crushers and screens to separate metallic components. The metallic component (10% – 15%) is recycled back to the BOF convertors as coolant. Due to the presence of free lime, the BOF slag cannot be used as an aggregate. Weathering (natural or accelerated) will ensure the removal of free lime to acceptable levels (<5%) for use in roads. JSW has developed the process of accelerated steam ageing which will help in removal of free lime in about a week. It is proposed to set up this system to produce aggregates. Further, large portion (approx. 50%) of BOF slag after processing becomes fines, which are then mixed with BF slag to make cementation roads which have a longer life. With the above measures, it is proposed to use 100% of BOF slag generated in the process. Ladle Furnace Slag: This slag is produced in the secondary metallurgical operations carried out in ladle furnaces. This slag is essentially in powder form and contains higher amount of VIMTA Labs Limited, Hyderabad 26 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State alumina and cannot be used internally in steel making. The composition of slag is given below: This material is extensively used in manufacture of ladle covering compound and also in production of high alumina cements. For this, the material will be screened to remove larger size which is used in convertors for producing steel. Non-metallic component is sent to produce cement. Particulars Fe2O3 SiO2 Al2O3 CaO MgO SO3 2.5 22.1 11.6 35.5 13.8 <1.0 Percentage % a) Slag of less than 5 mm ( fine steel slag) (i) Used in producing ordinary portland cement (up to 5% in OPC). The slag is used as performance improver and also provides the requisite colour to the OPC and slag cement. (ii) Used as fine aggregate in civil construction: The fine slag does not contain free lime, which is one of the reasons for its poor utilization. The BOF slag has been permitted for use as replacement of river sand by BIS. These material being heavy can be used in pavements, bricks road making etc. b) Slag more than 5 mm - 60 mm: (i) The non-metallic portion of LD slag contains free lime and magnesia. This advantage has been used in construction of roads / highways as slag bound materials. In this process, LD slag and granulated BF slag in different proportions are mixed and rolled to produce a cementations base for roads. This concept is widely practiced in Europe and Japan. This is being investigated in Indian steel plants. This has the potential to reduce the thickness of highways by 25-30% and can help greatly in reducing the use of natural materials in the construction sector. This process can also be used for producing gabions, boulders etc., for use in protection of coastal areas. In Japan, these are called “ferro form”. (ii) BOF slag as construction aggregates: The BOF steel slag has excellent properties and is ideally suited for use in the following area. a) Ballast in railways b) Aggregates in highways / roads The preferred application is highways due to higher angle of friction high PSV heavy weight etc. However, for use as road aggregate, the steel slag needs to be weathered. Though several options of weathering (natural, accelerated etc.) are available, it is intended to carryout weathering using steam. This reduces the weathering time to less than a week. This has been investigated and the process is established at JSW Vijayanagar. The proposed utilization of slags will be as below: a) HMPT Slag b) Convertor Slag VIMTA Labs Limited, Hyderabad : : : : : : 90-95% in sinter making 5-10% metallics to convertor 10% metallics in steel making 10-15% in sinter making 2% in cement plants 70-75% Road construction 27 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State c) 4.2 : 5% Railway ballast : 95% in cement making : 5% in steel making LHF Slag Blast Furnace Slag Utilisation The estimated BF slag generation shall be about 3.0 MTPA. It is proposed to set up 6.0 MTPA cement/grinding unit suitable for grinding Granulated Blast Furnace Slag (GBS) from the steel plant and clinker which would be procured from market sources. The capacity of the plant is estimated at 6 MTPA which consists of three finished products viz. GGBS (Ground Granulated Blast Furnace Slag), OPC (Ordinary Portland Cement) and PSC (Portland Slag Cement). Raw Material Slag Clinker Gypsum (Chemical/Mineral) Specific Power Consumption : Generated from blast furnace : Domestic / International market -China / Vietnam / Thailand : Domestic/International markets or from fertilizer/chemical Industries (Paradeep Phosphates / Tata Chemicals), Haldia. : 34 KWh/ t Clinker Grinding : 38 KWh/ t Slag Grinding : Coal/mixed gas is proposed to be used as a fuel. Fuel for HAG Product Mix: Clinker / OPC Gypsum GBS / GGBS IS Standards PSC 36-51% 4% 45-60% PSC: IS 455: 1989, OPC: IS 12269: 1987 OPC 95% 5% OPC: IS 12269: 1987 GGBS 100% There is no IS Code for GGBS and as such the same will be manufactured as per customer requirements. The ingredients in any product may differ based on raw material quality & finished product requirements. Additives Gypsum Gypsum is available from Local Fertilizer Plants. The composition of the gypsum is as below Quality of Gypsum Material Chemical composition (%) Chemical gypsum SiO2 Al2O3 Fe2O3 CaO MgO SO3 LOI 4.36 1.04 0.30 30.80 0.51 42.51 21.24 Slag The slag source is inhouse generation from the Blast Furnace. Material Blast furnace slag SiO2 30-34 Al2O3 15-19 VIMTA Labs Limited, Hyderabad Fe2O3 0.31 CaO 30-34 Chemical composition (%) MgO SO3 MnO K2O 8.65 0.86 0.17 0.57 Na2O 0.27 Moisture 8-10 28 Glass 92 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Coal The properties of coal has been considered as below: Moisture : 12 % Ash : 18-38% GCV (Kcal/kg): 3500 – 6500 Utilities Power The power demand for the slag/clinker grinding unit at has been estimated as about 50 MVA. Water Water is required for equipment cooling, drinking, sanitation, horticulture, etc., Approximately 4500 m3/day of water will be required for all the purposes. Sizing Norms for Main Machinery and StorageThe main machinery and storages shall be sized in accordance to capacities of similar plants. These norms are summarized as below – Sr. No. 1 2 3 4 Department Coal Mill Cement Mills (RP) Packing Plant Wagon Tippler Operating Hrs./day 15 24 16 10 Operating Days/Year 330 330 365 330 Operating Hrs./Year 6600 6800 6000 3000 Design Safety Factor 1.10 1.10 1.10 1.10 The fuel firing equipment shall comprise of: The firing system HAG shall include required oil pumps, filters, pipes, valves, safety instruments, fans, dampers, etc., Coal Drying and Grinding It is recommended to install the VRM for coal grinding. The brief technical details of the coal mill drying & grinding system are as follows: Coal Mill Hopper For mill feeding, 1 No. RCC hopper of mass flow design shall be installed. Coal mill feeding Material from the raw coal hopper shall be fed into the coal mill through weigh feeders beneath the hopper. Drying Hot gases from the HAG shall be used for drying of coal in the coal mill. Mill system It is recommended to install the VRM for the plant. Mill vent gas shall be transported to the coal mill bag filter. Fine coal product collected at the bottom of the bag filter shall be transported to the respective fuel bins through screw conveyors. VIMTA Labs Limited, Hyderabad 29 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Product collection Material collected at the bottom of Bag house (VRM Section) shall be transported by the dedicated Pumps to respective HAG Bins of RP Section. Mill dedusting A bag filter will be used for mill dedusting. Bag filter will be designed to meet the requirements of prevalent environmental norms. Cement Grinding System The brief technical details of the system are as follows: The plant will adopt either of two kinds of grinding mills viz. Roller Press Combination Technology (RP) or Vertical Roller Press (VRM) in the whole process of OPC / GGBS / PSC production line. The salient features of the technology are highlighted below: o o o o o o The Roller Press mill or VRM consists of rollers which grind Clinker and Gypsum to produce Ordinary Portland Cement (OPC). On the other hand, slag alone is finely ground in Slag Mill RP or VRM to produce GGBS. Both the OPC and GGBS are stored in separate silos. For the production of Portland Slag Cement (PSC), GGBS and OPC are extracted from the respective silos and blended in definite proportion in a paddle mixer and stored in PSC silo. Cement is packed in bags by means of Electronic Roto Packers. Cement as well as GGBS can also be loaded in bulkers through Bulk loading system. Modern high technology features will ensure high quality product, high yield in energy savings, environmental protection, as well as large- scale automation. Cement Storage The product will be stored in separate silos. The capacities of the silos will be about 15000 MT each for GGBS, OPC & PSC, however exact silo capacities will be determined at engineering stage. From the Storage Silo, cement shall be transported to the packers, with the help of a set of air slides and bucket elevators. Provision for bulk loading shall also be provided keeping in view the future demand for bulk cement. Cement Packing and Dispatch Requirement of packing depends upon the market requirements i.e. extent of bulk and bagged cement sales, by truck / wagon loading. For cement packing, electronic packing machine of suitable capacity shall be considered for the proposed plant. Truck loaders shall be provided for loading of bags. VIMTA Labs Limited, Hyderabad 30 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Utility Systems Power System The details has been provided in subsequent pages. The power requirement shall be about 50 MVA. Water Supply Water demand at the Grinding plant shall be met by pumping water from the system developed for the steel plant. The requirement of water is about 4500 m3/day. Compressed Air Supply It is proposed to install the compressors/ roots blowers, for compressed air requirements, at one centralized location in the plant suitable for complete plant. Fuel Supply The proposed plant shall be suitably designed on local coal/mixed gas from the steel plant. Fire Fighting System A complete fire fighting system shall be provided comprising of: 4.3 A suitable high-pressure system of fire hydrants consisting of suitable number of fire hydrants. A complete separate fire fighting water piping network for feeding the hydrants. Heavy-duty ABC powder type fire extinguishers shall be hung at particularly important electrical equipment areas. Portable CO2 extinguishers shall be provided throughout the plant. Automatic fire extinguishing, water system shall be considered for empty bags store in the packing plant. Fly Ash Utilisation The main solid waste from the CPP will be the ash (fly ash and bottom ash). The equivalent coal consumption in the captive power plant will be 3.0 MTPA thermal coal and 2 MTPA middlings. The total ash generation will be about 0.75 MTPA. Out of this, the bottom ash will be about 0.15 MTPA (20% of the total ash) and the balance fly ash will be 0.6 MTPA. It is proposed to sell the entire quantity of fly ash to external companies for cement/brick manufacturing. The following activities will be carried out to comply as per the new fly ash notification, S.O. 2623 (E) dated on 6 th November 2008 issued by MoEF. • • • • The bottom ash will be stored in properly designed ash dykes as per CPCB guidelines to prevent leaching to the sub-soil and underground aquifer; The ash disposal area will be lined with HDPE/LDPE impervious lining to prevent seepage of rain water from the disposal area in the ground and pollute ground water; Shall maintain a record of all sale and/ or disposal of the fly ash; and Shall submit annual compliance report including record of sale and/or disposal of the fly ash. VIMTA Labs Limited, Hyderabad 31 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State The Proposed major usage of Ash Fly Ash Bricks / Blocks Cellular Concrete Products Light Weight Aggregates Concrete and Mortar Cement Manufacturing Road Construction Embankment/Back Fills/Land Development Controlled Low Strength Fill Material (CLSM) --------------------------------------------------------------------------------------------------5.0 REVISE ASH BALANCE AND ASH EQUALIZATION PLAN SHOULD BE SUBMITTED The ash generation details and its utilisation is covered in the Point-4 under section 4.3 and Point -23 under section 23.6. ------------------------------------------------------------------------------------------------------------------------------------------------- 6.0 TRACE ELEMENT REPORT SHOULD BE CORRECTED AND SUBMITTED The details of trace element in iron ore is given below in Table-6.1. TABLE-6.1 TRACE ELEMENT Sr. No 1 2 3 4 5 6 7 8 Trace Elements / Metals Arsenic (As) Cadmium (Cd) Chromium (Cr) Copper (Cu) Lead (Pb) Mercury (Hg) Nickel (Ni) Zinc (Zn) Iron Ore (µg/g) 0.002 0.005 0.03 2.02 1.52 BDL 0.024 0.319 --------------------------------------------------------------------------------------7.0 IRON ORE ANALYSIS TO BE RECHECKED AND SUBMITTED Iron ore analysis is given in Table-7.1. TABLE-7.1 IRON ORE ANALYSIS Sr. No. 1 2 3 4 5 6 7 8 Parameters Silica (as SiO2) Aluminium (as Al2O3) Iron (as Fe2O3) Calcium (as CaO) Magnesium (as MgO) Sodium (as Na2O) Phosphorous (P) Loss on ignition Iron Ore (%) 8.89 4.52 83.18 0.056 2.87 ------------------------------------------------------------------------------------------------------------------------------------------------------- VIMTA Labs Limited, Hyderabad 32 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State 8.0 STAMP CHARGING + HPLA COMMITMENT IN COKE OVEN PLANT TO BE PROVIDED JSW commits to install Stamp charging/partial briquetting and High Pressure Liquor Aspiration (HPLA) system in coke oven plant. 9.0 10.0 ------------------------------------------------------------------------------------------COMMITMENT FOR THE USE OF CDQ TO BE SUBMITTED JSW commits to install CDQ along with wet quenching system for emergency purpose in phases. ------------------------------------------------------------------------------------------DETAILS REGARDING POLY AROMATIC HYDRO CARBON MONITORING SHOULD BE SUBMITTED PAH monitoring will be carried out during post project monitoring stage. The monitoring will be carried out at coke oven, by product plant of coke oven and surrounding villages. The PAH test reports of existing JSW- Vijayanagar Plant is enclosed in Annexure-I. -------------------------------------------------------------------------------------------- 11.0 SMS SLAG UTILIZATION SCHEME TO BE SUBMITTED Details of SMS slag utilization scheme are provided in point-4 under section-4.1. --------------------------------------------------------------------------------------------- 12.0 SMS PLANT - DOG HOUSE DETAILS FOR FUGITIVE EMISSION CENTRES SHOULD BE SUBMITTED Dog House Details for Fugitive Emission Centres – SMS Plant 12.1 Secondary Dedusting Plant comprises the following units Waste Gas Cooling and Collecting a. Material Handling Suction High level bin fume suction assembly Material handling for LF fume suction assembly Material handling for RH fume suction assembly b. Auxiliary Suction Points Ladle maintenance area fume suction assembly c. Furnace secondary suction Charging fume suction assembly Tapping fume suction assembly DeS/Deslagging fume suction assembly Ladle furnace fume suction assembly Waste Gas Cleaning a. Fabric filter equipment Pulse jet filter assembly Compressed air station VIMTA Labs Limited, Hyderabad 33 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Conveying Equipment a. Uncooled Ducts Raw gas collection duct assembly Clean Gas Duct b. Fans Radial Low Pressure ID Fan Station Raw gas booster fan station c. Silencer and Stack Clean Gas Stack Assembly 12.2 Residual Handling and Recycling Dust Handling and Storage Mechanical Dust Conveying Chain Conveyor Feeding screw conveyer Bucket elevator Discharge screw conveyer Silo assembly Dust Silo Silo top filter unit Shut-off device assembly Fluidisation unit Rotary valve for dust discharge Secondary Dedusting System The secondary dedusting system serves to collect the diffuse emissions occurring during the different operation phases such as converter charging and tapping, DeS, LF, material handling in order to fulfil the environmental and workplace impact regulations. The dust-laden fumes are collected by fume hoods which are designed to allow a maximum suction efficiency. The suction volume is controlled for each suction point by electric driven control dampers according to preset values. All dampers are of louver type design and equipped with limit switches and position indication. The dust fumes from the various sources are conveyed via ducts of appropriate cross section to the mixing duct. Downstream of the mixing duct the dust cleaning equipment is situated. The gas is cleaned in a two-row pulse jet filter with raw-and clean gas dampers for isolation of the individual chambers. The dust collected from the dust cleaning equipment falls down into the dust hoppers. The collected dust is discharged to the dust silo through the dust conveying system. The clean gas is conveyed via the clean gas duct to the exhaust stack and from there to the atmosphere. Two or three double-inlet radial fans generate the necessary suction. For noise protection, the ID- fans and the clean gas duct are insulated. A silencer installed in the base of the stack is further attenuating the noise. The control of the dedusting system will be done by measurement of the negative pressure in front of the bag-filter. The actual negative-pressure is following the adjusted set point. Depending on deviations of the set point of the negative-pressure the ID-fan speed will be adjusted by means of a VVVF. This will adjust the flow rates on the different suction points depending on the requirement automatically. VIMTA Labs Limited, Hyderabad 34 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Depending on the temperature and composition of the dust fines to be cleaned they run through different conditioning steps. Very high temperature fines e.g. from converter charging pass through the total treatment line. Hot gases do not need to go through the static cooler and dust from suction point with ambient air temperature or directly conducted into the filter. The highest amounts of dust are generated during converter charging and tapping. For this reason this area requires the greatest attention. The individual components of the secondary dedusting line are: a. Static Cooler It serves the purpose to absorb the heat energy peaks generated during HM converter charging. Between the charging operation the cooler releases the heat to the air sucked through the system. The static coolers are located in each branch of the charging duct close to the charging hood. The heat storage surface is maximized by using a multi-plate design with the plates hanging in longitudinal direction in order to minimize pressure loss and wear. The coolers consist of several individual packages which are flange connected and can be exchanged individually. b. Spark Separator It is used in those areas with the danger that sparks are sucked into the system and damage the filter bags. The sparks are captured in the special internal components of the separation chamber. c. Mixing Chamber In case a mixing chamber is necessary it is used for temperature adjustment and homogenisation of the off gas stream before the filter by special guiding/ homogenisation system in the chamber. d. Pulse Jet Bag-Filter The fumes captured in the system will be conveyed to the inlet manifold of the pulse jet filter. The single filter compartments can be isolated from the clean gas side via pneumatically operated flaps and from the crude gas side via manually operated dampers. So it is possible to take a filter compartment out of operation for maintenance. The dust is collected on the outside of the filter bags. The pulse jet air for cleaning passes through from bag inside. The cleaning of the filter bags is in off-line mode, that means the section to be cleaned is disconnected from the filtration process by closing the pneumatic clean gas dampers of the clean gas channel. To clean the filter bags, short compressed air pulses are injected in certain intervals into the filter bags. The filter cleaning system is controlled via the central de-dusting control PLC. On the filter control unit two different automatic modes are available. One mode is a fixed cycle time based mode and the other one is based on the filter different pressure. Normally the differential pressure mode shall be selected on the control unit so the cleaning cycle operates depending on the measured differential pressure. Supporting cages in split design prevent collapsing of the bag. The bag material is polyester needle felt. Into of the filter a penthouse is situated, ventilated by natural ventilation. To lift the compartment covers manually operated lifting hoists are provided. The inclination of the walls of the filter hoppers is steep enough to allow a free flow of the separated dust to the bottom outlet. VIMTA Labs Limited, Hyderabad 35 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Additionally, compressed air feeding pipes will be provided in the bottom of each filter hopper. Solenoid valves controlled short air blasts will prevent material hang up. e. ID-Fan Station and Clean Gas Duct/ Stack The necessary suction for the complete dedusting system is produced by three radial type fans. The exhaust fans are designed as a double inlet suction type fan. The fans, located downstream of the bag filter at the clean gas side draws off the cleaned gas via the clean gas channel of the filter and the clean gas duct and direct it into the atmosphere via the clean gas stack. The fan is of heavy industrial design. The fans are driven by electric motors. The suction performance is controlled with a VVVF for energy saving. The final fan pressure increase will be fixed during the engineering phase and technical layout clarification. The operation of the bearings is monitored by a temperature measurement (each fan bearing) and vibration monitoring (fixed bearing only, radial direction, indication in mm/s). To avoid excessive under pressure of the equipment upstream the ID-fan, a hardwired pressure switch is installed for switching off the fan. At the outlet gate plates are provided to isolate each fan for maintenance. Gas ducts and supporting structures are foreseen for the transporting of the clean fumes between dust collector and clean gas stack. Expansion joints for the compensation due to heat expansion, necessary supports and inspection openings for the ducts are provided. The stack is of self-supporting design. A platform with ladders for measurement of the clean gas dust content is provided. For noise attenuation, the stack base will be designed as casing for the exhaust silencer. f. Dust Conveying System The dust conveying system comprises: • • • • Collecting chain conveyor with drive Screw conveyor for bucket elevator incl. drive Feeding bucket elevator with drive Screw conveyor to dust silo with drive g. Dust Silo The silo assembly for dust mainly consists of: • • • • • • • • • • Dust silo shell Access ladder and platforms for dust silo Supporting structure for dust silo Top filter unit for dust silo Fluidisation unit for dust silo Rotary valve with drive below dust silo Loading device for dust silo Cladding for dust silo Manual slide gate for dust silo Manual slide for emergency outlet VIMTA Labs Limited, Hyderabad 36 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State h. Converter Charging/ Tapping Hood The charging hood is integrated in the doghouse structure and located on the charging side in the doghouse roof. The hood is designed in welded steel plate structure with the necessary supports. The hood is lined with refractory material or hematite for heat protection. Gas ducts with individual dampers will be connected on both sides of the hood in order to maintain a uniformly suction of the gases. A static cooler is provided in each branch of the charging suction duct. The static coolers are buffering the heat generated during hot metal charging and thus decrease the gas temperature which leads to an increased suction efficiency. The tapping hood is integrated in the doghouse structure and located on the tapping side in the doghouse roof. The hood is designed in welded steel plate structure with the necessary supports. The hood is lined with refractory material. i. Other Suction Hoods The hoods cover the respective position to be dedusted. If required they have openings to feed materials. They are generally of welded design and where necessary protected against overheating. j. Raw Gas Ducts Gas ducts with proper stiffeners and supporting structure are foreseen for the transporting of the fumes from the fume hoods to the dust collector. Expansion joints for the compensation due to heat expansion, necessary supports, cleaning and inspection openings for the ducts are provided. Dampers in the related gas duct are operated automatically from the related control rooms via push button for start. In the raw gas collection duct a good mixture of the gases with different temperatures is achieved by a static mixer. k. Control Dampers The dampers are designed as multi-louver damper in a sturdy frame. The damper blades are overlapping to provide a good sealing in closed position and ensure good movability also under changing temperature load (tightness approx. 96-98%). The dampers mainly consist of: • Damper frame • Damper blades with shaft and stuffing boxes • Drive mechanism (levers and rods) • Actuator (electric or pneumatic) l. Compressed Air Station The pulse jet bag filter requires bone dry compressed air for periodical cleaning of the filter bags. Therefore an independent compressed air station is provided consisting of: • 2 compressors • 2 adsorption dryers • 1 buffer vessel VIMTA Labs Limited, Hyderabad 37 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State 12.3 Major Process Equipment Parameters The proposed major process equipment for 5.0 MTPA SMS shop are given below. Pulse Jet Filter Assembly The filter plant is designed as bag filter and subdivided into individual chambers. The dust-laden gas first enters from the raw gas channel into the dust bin underneath and then the filter chamber located above, and is filtered to the admissible clean gas dust content. The dust accumulates on the outside of the filter bags. Supporting cages prevent collapsing of the bag. The bag material is polyester needle felt with a special treated surface. The filter consists of separate compartments each of which can be completely isolated from the gas flow during maintenance. The bags are cleaned periodically with compressed air at an electronically controlled cycle. The cleaning is at off-line operation; that means single chamber cleaning is applied. The dust falls into the dust bins of each compartment during the cleaning cycle. In order to have additional protection of the filter bags against excessive temperature in case of emergency, sufficient cooling air can be added through the emergency air damper located upstream of the filter. The pulse jet filter assembly comprises: • • • • • • • • • • • • • Filter head Filter bags and cages Filter supporting structure Access to filter Filter casing Filter penthouse and cladding Maintenance crane Raw gas dampers Clean gas dampers Filter hoppers Filter hopper dust transport Rotary valve below chain conveyor Filter control unit Technical Data No. of Bag Filters Type of design Wall thickness casing Gas volume max. Gas temperature Number of chambers No. of bags in one chamber VIMTA Labs Limited, Hyderabad : : : : : : : 1 suction filter with jet cleaning (offline) 4 mm approx. 2,000,000 m3/h max. 150° C 16 2 x 170 38 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Dimension of bags Total filter surface Air-to-cloth ratio – offline cleaning Filter bag material Differential pressure (normal) Compressed air demand : : 165 x 8,000 mm 22,274 m² : : approx. 1.53 m³/m2.min PE 550 g/m2 : max. 25 mbar (inlet-outlet) : approx. 1600 Nm3/h 6 bar, free of oil, free of solids, dew point -40 °C) Compressed Air Station The compressed air station provides compressed air for: • Cleaning the bags of the pulse jet filter • Several services of dust handling and storage Technical Data Operating pressure Flow rate Dew point Drive type Motor power : : : : : 6 bar g approx. 1900 Nm³/h -40 °C electric approx. 250 kW The compressed air station comprises: • • • • • • Compressor unit Buffer vessel Pre filter Post filter Oil separator Refrigerant dryer Fans Radial Low Pressure ID Fan Station The ID fan station provides the required induced draught to overcome the pressure drop of the gas flow. The fans, located downstream of the filter plant at the clean gas side draw off the cleaned gas and direct it into the atmosphere via the clean gas stacks. The fans are driven via a VVVF, which provides variable speed control by an electric motor with variable speed. The fan casing and the ducts between fan station and stack are covered with acoustic insulation to achieve the specified noise pressure level. Technical Data Quantity of fan Function Type of design Impeller type Mounting Flow control VIMTA Labs Limited, Hyderabad : : : : : : 3 set (s) provide induced draught to overcome gas pressure loss radial backward curved base frame on concrete block by VVVF 39 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State ID fan data per fan: Bearing type Effective conveying capacity @ 130°C Design total compression (estimate) Noise level max. Drive type Motor capacity Speed of ID-Fan : roller bearing : approx. 685,000 Am³/h : : : : : approx. 65 mbar 85 dB (A) in 1 (one) meter distance from the fan electric approx. 1,700 kW max. 1000 RPM ------------------------------------------------------------------------------------------13.0 SMS – DRY SYSTEM TO BE ADOPTED AND DETAILS SHOULD BE SUBMITTED Dry Type Gas Cleaning System The Primary Gas Treatment System (PGT-System) is designed for collecting and treating the gas which is generated during the steel making process in the converter. The complete plant is sealed gas tight against uncontrolled intake of ambient air. The actual flow of gas generated inside the vessel is strongly affected by the blowing rate of oxygen through the lance and the reaction of other oxygen containing substances charged into the vessel, (suppressed combustion) by controlled intake of ambient air. The partly combusted gas will be named “LD Gas”. The flow rate of primary gas and therefore also the total flow rate of LD-gas during the blowing period is not constant but fluctuates over a wide range. To assure a good capture efficiency and high LD-gas quality, the flow of LD-gas through the system has to be carefully and accurately controlled. This is assured by continuously adjusting the flow rate in such way, that the pressure at the cooling stack inlet varies only insignificantly around a very low pre-set pressure. It is proposed to adopt a cascade control concept based on a radial type ID fan (RT IDF) equipped with an inlet guide van damper (IGVD). Small adjustments of the gas flow rate will be controlled by the IGVD; larger fluctuations will be controlled by the revolution speed of the RT IDF by means of a VVVF-control unit (frequency converter). For the best control results, the measurement probe is to be located as close as possible to the inlet of the cooling stack. To ensure reliable function, the pressure probe should not directly be exposed to the off gas. An accurate control pattern will maintain a good and efficient collection of the Primary Gas from the converter and further minimizes the risk of inflammable gas mixtures. Both are the basis for the failsafe operation of the Primary Gas Treatment plant under all operational conditions. The Primary Gas Treatment system basically consists of three Sub-Systems: • Gas Cooling System: • Gas Cleaning System (DRY type) with: - Gas Conditioning Tower (GCT) - 2nd generation dry-type electrostatic precipitator (ESP) - ID-Fan (IDF) - Flare Stack (FS) VIMTA Labs Limited, Hyderabad 40 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State • Gas Recovery System with: - Switch-Over-Station (SOS) - Gas cooler (GK) - Gas-Holder (GH) - Gas Export Station (BFS) Gas Cooling System The inlet cone of the gas conditioning tower will be provided with indirect cooling for proper gas distribution purposes which results into a lower temperature at inlet Gas Conditioning Tower (GCT). Gas Cleaning System (DRY Type) The BOF waste gas cleaning system is designed as a dry-type electro static precipitator for high-efficient cleaning the LD-gas. The system is designed for subsequent converter gas recovery. The Gas Cleaning System is only in operation with full capacity during blowing time. After passing through the cooling stack (CS), within that the gas temperature is reduced, the LD gas enters the adjacent gas conditioning tower (GCT) with a temperature of approx. 850 - 900°C. The gas is heavily laden with dust particles from the converter process, mainly with iron, iron oxide but also other particles from slag, flux charges (lime and others). The range of particles sizes vary from approx. 0.1 micron up to some millimetres. In the gas conditioning tower (GCT), connected gas tight via a special designed high temperature compensator, the LD-gas is being cooled and conditioned by evaporation of injected water. Coarse dust particles are separated in dry state and transported to the coarse dust silo. The conditioned LD-gas exits the GCT at about 180°C. By means of the following horizontal cylindrical shaped electrostatic precipitator (ESP), connected via a gas duct with the Gas Conditioning Tower and located outside The Steel Shop Building, the remaining fine dust load is further reduced to the requested clean gas dust content. The dust is also collected in dry state and transported to the fine dust silo. The system is capable of reducing the dust content of the clean gas down to ≤ 10 mg/Nm3. The gas is transported through the Gas Cleaning System to the flare stack (FS) or to the gas recovery system by means of an induced draft fan (IDF). As explained above it is recommended to use a radial type IDF (RT IDF). Advantages of a RT IDF are: lower temperature increase due to better efficiency (delta to axial fan approx. 10°C) wider control range than AX IDF maintenance friendly design of RT IDF larger tip clearance than AX IDF short maintenance downtime Gas Recovery System Depending on the actual CO content a switch-over station (SOS) will direct the gas either to the Flare Stack (FS) or with sufficient CO content to the gas holder (GH). VIMTA Labs Limited, Hyderabad 41 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State At the beginning of the blow, the LD gas is exhausted into the atmosphere and the CO is burned at the flare stack if burnable, which will be the case usually after few seconds of the blow subject to a minimum 20 – 30% CO. After a while in the blowing process, the CO content will rise to a pre-set value and the recovery system will be switched to a gas holder where the gas is stored for further usage. It can continuously be fed into the plant LD-Gas-Net via the Gas Export Station (BFS). The switch-over of the gas from flare mode to recovery mode will be interlocked with the oxygen level in the off-gas as well as the gas holder level. At the end of the blowing phase the CO content will decrease, and the system switches back to flare mode. During flare mode the off-gas will be directed through the flare stack equipped with a flare burner head and pilot burners. In order to avoid CO being released into atmosphere it will be ignited by the pilot burners. A goggle valve is installed downstream of the SOS / recovery valve. The Gas Cooler can be installed downstream or upstream of the SOS for further cooling down the LD Gas to temperatures from approx. 150°C -180°C inlet temperature down to below 70°C appropriate for the gasholder operation. This is vital for a long lifetime of the gasholder sealing. As a side effect, the cooling reduces the gas volume. The gas will then be fully saturated. The Gas Cooler is designed as a counter-flow cooler, which means the gases enter the cooler in the lower part and leave at the top. Cooling water is injected through nozzlebanks with several individual nozzles. The cooling water is internally circulated by pumps. At least one pump is in operation, while one is always in stand-by mode. In order to keep the dust concentration in the re-circulated water on the desired level, a small amount of water will be continuously exchanged. Safety Philosophy BOF steel making plants operating with suppressed combustion require a thoroughly elaborated safety concept especially with respect to the gas cleaning and recovery system. Flammable gas mixture of O2, CO and also H2 may develop, and especially the ESP is a potential source of ignition. Both, formation of combustible gas mixtures, and sources of ignition cannot completely be avoided. Therefore, the system is designed to at least minimize the formation of such gas mixtures and sources of ignition. Furthermore, all necessary measures are taken into consideration to prevent personnel and the system from damage in case a deflagration occurs. During non-blowing normal O2 containing air is being sucked into the off-gas system. During blowing phase the off-gas exiting the BOF mouth contains up to approx. 90%. At the beginning of blowing the movable skirt is not yet closed, and hence, enough O 2 containing air is being sucked into the system resulting into complete post-combustion of CO into CO2. Closing down the skirt after start of O2-blowing and ignition takes less than one minute, this delay in shielding the off-gas system against O2 for CO postcombustion leads to an CO2 /N2 inert gas cushion between O2 and CO containing offgas. VIMTA Labs Limited, Hyderabad 42 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State The equipment is designed to allow an optimum plug-flow. Transitions from small to wide diameters (i.e. GCT inlet and ESP inlet) are equipped with gas distribution internals. Such measures prevent the system from turbulences, and hence, during normal operation conditions of the converter no combustible mixtures of CO and O 2 will occur. However, by no means it is possible to fully prevent the system from forming combustible gas mixtures. For example, it may happen as a consequence of a rapid stop of blowing. Also, it is not possible to prevent the system (valid for dry and wet systems) from developing H2 which strongly influences the critical gas composition. For example, wet scrap, humid or oily charging material, damages/leakages of the cooling stack and other reasons may lead to an increased H 2 content. To detect critical a critical gas composition containing CO, H2 and O2 a redundant gas analyzer is mandatorily installed in the cooling stack. Measurements beyond the critical values of gas mixtures will trigger a stop of blowing as well as in case of dry system an immediate earthing of the ESP high tension. Gas Cooling System (CS) The CS will be protected by relief flaps at the top of the deflection bend against pressure surges due to sudden evaporation inside the BOF vessel (water explosion) or deflagrations inside the CS. Gas Cleaning System Main source of ignition surely is the ESP. Even though being controlled by a highly sophisticated thyristor control unit the incidence of flash-overs cannot fully be prevented. Only the coincidence of combustible gas mixtures and – at the same time – a source of ignition will lead to a deflagration. The frequency of such incidences cannot be predicted. It is depending on various factors, such as operating conditions, maintenance and plant condition, quality of raw materials, etc. The ESP is equipped with a sufficient number of pressure vent valves which in any case will reduce the maximum pressure to below 2 bar, for which the ESP casing is designed for. Gas Recovery System Same as in the wet system the plant is equipped with a Nitrogen injection/ purging system. By purging with Nitrogen through the several duct sections an undesirable formation of air and gas cushions will be avoided. The gas analyzing systems (hot gas analyzer and clean gas analyzer) measures the gas composition and controls the switch-over process. The main safety features of the cup valve station are: a) Nitrogen buffered hydraulic station VIMTA Labs Limited, Hyderabad 43 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State b) Gravity driven cup valves in case of black-out in order to switch over to the Flare Stack(FS) c) N2 Purging System such as purging of flare stacks when switching over to avoid air entrance into the clean gas stack during the recovery phase or purging the gas duct between Gasholder Cup Valve and shut off damper. d) Emergency N2 purge (thru venturi) to prevent flashback in case of power failure at the ID fan or break down of the ID fan or during interruption of the oxygen blowing process. --------------------------------------------------------------------------------------------------- 14.0 SINTER PLANT – SECONDARY EMISSION MITIGATION DETAIL SHOULD BE PROVIDED. Plant Dedusting All transfer stations in the area of the sinter plant (direct vicinity) generating dust are covered with exhaust hoods. The receiving point and material falling point of belt conveyor is equipped with local sealing hood, the vibrating screen is equipped with integrated sealing hood, the movable unloader at top of fuel silo, flux silo and finished product bin is adopted with the movable ventilation device, all crushers are sealed strictly and equipped with local sealing hood. The plant is equipped with the mechanical dedusting system based on above configuration, which is executing induced draft to form certain negative pressure inside sealing hood, to avoid dust escape, and to achieve the desired parameters. The plant adopts high efficiency bag dedusting equipment as purification equipment of dedusting system. Bag filter removes particulate by straining, impingement, interception, diffusion, and electrostatic charge. The fabric used in bag filter may be constructed of any fibrous material, either natural or man-made. The fabric represents a porous mass through which the gas is passed unidirectional such that dust particles are retained on the dirty side and the cleaned gas passed on through to stack. The combination of fabric and collected dust becomes increasingly efficient as the dust cake accumulates on the fabric surface. The dust-loaded gas/air is cleaned in the bag filter and is discharged into the open atmosphere through a stack. The dust separated by the bag filter is withdrawn by chain conveyors and finally recycled to the sinter process. The suction required for the proper functioning of the dust collecting system, is created by the plant dedusting fan. One silencer is provided for noise level reduction. The branch pipe for each dust collecting point of system is equipped with manual or electric regulating valve, to balance the air quantity of each dust collecting point. The bag filter is designed to achieve dust content in the clean gas at the outlet-end of the bag filter of 50 mg/Nm³. The dust collected will be transferred to process belt conveyor through scraper or transport outside after humidifying by humidifier. VIMTA Labs Limited, Hyderabad 44 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Typical Plant De-Dusting Bag Filter Parameters Designation Quantity Gas flow rate nominal Gas flow rate design Gas temperature, average Gas temperature, range Dust load at inlet Negative pressure Clean gas dust concentration Ca(OH)2 Consumption (SO3 removal) Unit Set m³/s m³/s °C °C mg/Nm³ (dry) mm WC mg/Nm³ (dry) Kg/h Value 1 290 333 approx. 150 110 - 200 150 160 ≤10 Approx.. 100 Dust Handling Dust transportation from dedusting equipment will be done by pneumatic conveying system. Dust will be recycled and is charged into the dust bin. Dust will be conditioned in a granulator, prior to charging into collecting conveyor for raw material. For pneumatic conveying of dust to the proportioning building two separates lines for Waste Gas ESP and Plant Dedusting bag filter are envisaged. The typical parameters of environmental mitigation measures for the Sinter Plant is given below: Fan Details Fan volume, m3/h Inlet static pressure Bag filter Details Filtration area, m2 Bag dimension Filtering velocity, m/s ΔP, mm WC Compressed air requirement, Nm3/h 1 2 3 4 5 6 7 8 9 10 11 12 13 14 16 17 18 Typical Bag filter Details Crusher Bldg MND Bldg 35000 60000 300 300 Screening Bldg 60000 300 516 152 X 4500 1.14 130 819 152 X 6000 1.22 130 819 152 X 6000 1.22 130 13 20 20 Typical Dedusting ESP details No. of fields 3 Collecting electrodes in one field 22 Discharge electrodes in one field 21 Total no of collecting electrodes 44 Total no of discharge electrodes 63 Inlet dust load in g/m3 15 Outlet dust emission (mg/nm3) 50 Projected collection area in m2 6214 Specific collection area (m2/m3/sec) 64.65 TR sets 3 Inlet gas temp (°C) 70 Normal operating pressure in Pa -3500 Gas velocity inside ESP (m/s) 1.15 Gas Flow (m3/hr) 346000 TR sets rating 110kV, 800mA Retention time in Sec 12.94 No. of Gas pass 19 Source: JSW Vijayanagar Plant: SP-4 -------------------------------------------------------------------------------------VIMTA Labs Limited, Hyderabad 45 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State 15.0 ADVANCED CO MONITORING SYSTEM SHOULD BE ESTABLISHED AND DETAILS SHOULD BE PROVIDED It is proposed to install advanced CO monitoring system such as Sensepoint XCD. The Sensepoint XCD range provides comprehensive monitoring of flammable, toxic and Oxygen gas hazards in potentially explosive atmospheres, both indoors and outdoors. Users can modify detector operation using the LCD and magnet switches without ever needing to open the unit. This enables one-man, non-intrusive operation and reduces routine maintenance time and costs. A tri-colour backlit LCD clearly indicates the unit’s status at a glance, even from a distance. A steady green backlight indicates normal operation, flashing yellow indicates fault and flashing red indicates an alarm. All detectors are supplied preconfigured and include 2 programmable alarm relays, 1 programmable fault relay as well as an industry standard 4-20 mA output (sink or source selectable) and MODBUS*. The scale, range, relay operation, alarm set point and electronic tag number of the detector can be adjusted using the transmitter's LCD and non-intrusive magnetic switches. Outputs are automatically inhibited during adjustment, thereby reducing the risk of false alarm at the control panel during maintenance. Sensepoint XCD has an integral mounting plate for surface mounting or can be mounted to a horizontal or vertical pipe using the optional pipe mounting bracket. Electrical installation can be made using either conduit or cable with suitable mechanical protection. Two M20 or ¾”NPT entries are provided (depending on certification). A weatherproof cap is also included for use in the harshest outdoor Conditions. Other optional accessories include a sunshade/deluge protection, duct mounting kit, collecting cone and remote mounting sensor socket*. Sensepoint XCD ensures easy installation and the fastest routine operation by removing the need for hot work permits in hazardous areas. Using easy to replace plug-in sensors, downtime is also reduced and on-going costs are minimised through the use of poison resistant flammable sensors, poison immune infrared Hydrocarbon sensors and patented Surecell™ toxic sensors. VIMTA Labs Limited, Hyderabad 46 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State There are three different types of the XCD transmitter for use with three different families of sensors. The mV type transmitter is for use with the mV family of XCD sensors including catalytic sensors to detect flammable gases in the range 0-100% LEL and infrared (IR) sensors for detection of Hydrocarbon gases in the range 0100% LEL and 0-100% Vol, as well as Carbon Dioxide (CO2) in the range 0-2% Vol. The EC type transmitter is for use with the EC family of XCD sensors including Carbon Monoxide (CO), Hydrogen Sulphide, (H2S) and Hydrogen (H2). The Oxygen transmitter is for use with the Oxygen (O2) XCD sensors. A transmitter can auto-recognise any sensor from within its sensor family. The sensor simply plugs into the bottom of the transmitter and the transmitter automatically configures itself accordingly. VIMTA Labs Limited, Hyderabad 47 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State --------------------------------------------------------------------------------------------------- VIMTA Labs Limited, Hyderabad 48 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State 16.0 SPECIFIC WATER CONSUMPTION AND WATER BALANCE SHOULD BE SUBMITTED The water consumption details for various units are given below: Sl. No. Plant Facilities 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Main Steel Plant Facilities RMHS Pellet Plant Coke Oven Plant Sinter Plant Blast Furnace with PCM Direct Reduction Plant SMS & Casters Wire Rod Mill Medium Section Mill Heavy Section Mill Hot Strip Mill Bar Mill Cold Rolling Mill Complex Oxygen plant Lime & Dolo Calcination Plant 16 17 18 19 20 20 21 22 Township Additional Units Miscellaneous Drinking water to plant Total Process Water (Main Plant) Iron Ore Beneficiation Plant Captive Power Plant Cement Plant Coking & Non-Coking Coal Washery Sub Total Treatment Loss Total Raw Water required VIMTA Labs Limited, Hyderabad Capacity 2 x 4.0 Mt/yr 3 x 2.0 Mt/yr 3 x 7.8 Mt/yr 2 x 4.9 Mt/yr 1.2 Mt/yr 10.4 Mt/yr 1.0 Mt/yr 1.2 Mt/yr 2 x 1.1 Mt/yr 4.5 Mt/yr 1.0 Mt/yr 2.3 Mt/yr 3 x 2500 tpd 5 x 600 tpd 2 x 600 tpd TPA Sp. Cons. (m3/unit) 53737429 8000000 6000000 15600000 9800000 1200000 10400000 1000000 1200000 2200000 4500000 1000000 2300000 1750000 1386000 0.02 0.04 1.24 0.07 0.7 1 0.7 0.4 0.4 0.4 0.37 0.4 0.45 0.5 0.12 Total Water Consumption (m3/annum) 10,74,749 3,20,000 74,40,000 10,92,000 68,60,000 12,00,000 72,80,000 4,00,000 4,80,000 8,80,000 16,65,000 4,00,000 10,35,000 8,75,000 1,66,320 4,20,000 24,00,000 32,00,000 22,40,000 3,71,88,069 29.0 Mt/yr 3 x 300 MW 6.0 Mt/yr 5.52 Mt/yr 2.30 Mt/yr 29000000 900 6000000 7820000 0.25 2.5 0.25 0.047 72,50,000 1,80,00,000 15,00,000 3,67,540 2,71,17,540 32,15,280 6,75,20,889 8,440 45 49 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State ------------------------------------------------------------------------------------------------------------------------------------ VIMTA Labs Limited, Hyderabad 50 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State 17.0 SOX, NOX LINE EMISSION DATA USED FOR ALL THE UNITS, INCLUDING FLOW RATE TAKEN SHOULD BE SUBMITTED The details of stack emissions are provided in Annexure-II. Calculation for one stack is described below: General Calculations Area Calculations 3.14 x (Top Stack Diameter ) 2 = 3.14 X (5)2/4 = 19.625 m2 Area (m ) 4 2 Temperature Correction Temperature correction is calculated based on standard ambient temperature of 25 C. Temperature Correction 273 25 0 C = 298/388 = 0.76 273 StackTemperature 0 C Particulate Matter Emissions Emission rate = 50 mg/Nm3 X 15,00,000 /3600/1000 = 20.8 g/s Emission Calculations Sulphurdioxide Emission rate = 30 mg/Nm3 X 15,00,000 /3600/1000 = 12.5 g/s NOx Emissions Emission rate = 140 mg/Nm3 X 15,00,000 /3600/1000 = 58.33 g/s --------------------------------------------------------------------------------------------18.0 REVISED TABLE FOR POLLUTION CONTROL MEASURES SHOULD BE SUBMITTED Sources of Emission & Pollution Control Measures The sources of emissions from the proposed steel plant and the control measures adopted are given below. In addition to the measures taken to control pollution, it is also proposed to limit the design emission norms to a maximum of 50 mg/Nm3 of particulates. VIMTA Labs Limited, Hyderabad 51 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Sr. No 1 2 Area of Operations Raw material handling Fugitive emissions in material handling Coke ovens Coal & Coke handling Coal charging Carbonization Coke pushing Coke quenching 3 7 8 Sinter Plant Sintering process Raw material preparation and handling Sinter screening and transport Pellet Plant Raw material preparation and handling Mixed material drying unit In-duration unit system (grate-kiln-cooler) Blast Furnaces Sinter, coke and flux handling in stock house BF processes Cast house Stoves heating BOF Material handling operations Converters Desulphurisation, RHFs, LHFs etc Billet/bloom casters Rolling mills 9 Incinerator 4 5 6 10 11 Cement grinding unit Power Plant Air Pollution Control Measures Proposed to be Adopted Design Limits • Dust suppression systems (chemical and dry fog type) • Water sprinklers • DE systems with bag filters in case of conveyors, lime handling • Work area 5.0 mg/Nm3 • Stack: 50 mg/Nm3 • DE systems • On main charging with HPLA aspiration • CGT car for aspirating gas into adjacent ovens • Leaking of doors, lids etc. • Use of lean gas for under firing • Low NOx burners • Land based pushing emission control • Stack: 50 mg/Nm As per MOEF norms applicable for coke ovens As per MOEF norms applicable for coke ovens As per MOEF norms applicable for coke ovens As per MOEF norms applicable for coke ovens • Dry quenching with stand by wet quenching facility • ESP for collected waste gases • Centralised De-dusting system with bag filiter common for both areas 50 mg/Nm3 50 mg/Nm3 • Dust suppression system • Multicyclone-scrubber based de-dusting Work area mg/m3 50 mg/Nm3 • ESP 50 mg/Nm3 • Bag filters 50 mg/NM3 • Gas cleaning in venture Scrubbers • FE systems with ESP/Bag filter • Use of lean gas• Use of lean gas 5 mg/NM3 50 mg/NM3 50 mg/NM3 • Bag filters 50mg/NM3 • Secondary fume extraction system • Spark arresters followed by Bag filters 50mg/NM3 • • • • Use of low sulphur gases for SO2 control Use of low sulphur gases for SO2 control Low NOx burner Scrubber and alkali treatment • Bag filters • ESP/Bag filters • Low NOx burners 5.0 50 mg/NM3 As per CPCB regulations 50 mg/NM3 50 mg/NM3 -------------------------------------------------------------------------------------------------- VIMTA Labs Limited, Hyderabad 52 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State 19.0 DETAILS ON BENZOL PLANT AND TAR UTILISATION SHOULD BE PROVIDED Benzol & BTX Plant Process Technology It is proposed to install Benzol Recovery Plant and BTX plant of 90,000 t/yr capacity for the coke oven plants to produce value added products like Benzol, Benzene, Toluene & Xylene. Block Diagram of the Proposed Plant COG from CO Benzol Recovery CO gas back to Steel Plant Network COG from Steel Plant Network PSA H2 Recovery To Steel Plant Network H2 Gas COG after Benzol Recovery Aromatics Recovery & Separation Benzol Hydro Refining Raffinates Xylene Toluene Benzene The flow and composition of coke oven gas before and after benzol recovery plant is given below: Description Gas before Benzol Recovery Plant Gas after Benzol Recovery Plant 330,000 Nm3/h 330,000 Nm3/h Ammonia 3 0.1 g/Nm 0.1 g/Nm3 H2S 0.3 g/Nm3 0.3 g/Nm3 HCN 0.28 g/Nm 0.28 g/Nm3 32-35 g/Nm3 2-5 g/Nm3 0.4 g/Nm3 0.2 g/Nm3 Gas Flow of coke oven plant Benzol Naphthalene Tar Temperature Pressure VIMTA Labs Limited, Hyderabad 3 Traces Traces 30-35 °C 25-27 °C 0.0085 Mpa 0.0075 MPa 53 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Benzol Recovery Plant The Benzol Recovery Plant will consists of three sections 1. Cooling section 2. Benzol scrubbing 3. Benzol recovery Process Description Coke Oven Gas (COG) after the existing ammonia removal & recovery unit is pressure boosted by the exhauster and fed to Benzol Scrubbing unit. COG is cooled from 35oC to 22-25oC in the cooling towers in heat exchanger with chilled water. After heat exchanger, the gas is passed into benzol scrubbing tower from the bottom and comes in contact in counter flow with the circulating scrubbing oil which is sprayed from top of tower. The benzol in the gas is absorbed by the circulating wash oil, and is then sent through the fog precipitator for the removal of fog. The rich oil at the bottom of benzol scrubbing tower is pressurized by lean and rich pumps and delivered to crude benzol condenser for heat exchange with crude benzol from top of benzol removal tower to be preheated upto 60°C. It is then sent to oil-oil heat exchangers for heat exchange with lean oil from bottom of benzol removal tower, wherein the temp increased from 60°C to 140°C. Finally, it enters into tube type heat furnace for heating upto 180°C and then passes into benzol removal tower. The crude benzol oil-water gas which is distilled from top of benzol removal tower enters into crude benzol condenser wherein its temperature is lowered down to 30°C by rich oil from bottom of benzol scrubbing tower and 16°C chilled water, and then it enters into crude benzol oil-water separator. The separated crude benzol enters into crude benzol backflow tank, and part of crude benzol is sent to benzol removal tower for back flowing by crude benzol backflow pumps. The balance part is sent to crude benzol storage tank and is delivered to tanks area by crude benzol delivery pumps for storage. The separated oil-water compound enters into control separator, wherein the scrubbing oil is separated and sent to underground emptying tank. From there it is further delivered to lean oil tank by submerged pump, and the separated water self flows into condensation liquid storage tank. The hot lean oil after benzol removal flows out of the bottom of benzol removal tower, and self-flows to oil-oil heat exchangers for heat exchange with rich oil, lowing down its temperature to ~90°C, and enters to lean oil tank. After that, it is pressurized by rich and lean oil pumps and delivered to lean oil coolers to be cooled down to 30°C respectively by 35°C circulating water and 16°C chilled water. Then it is sent to benzol scrubbing tower for spraying and scrubbing gas. The new scrubbing oil, as make-up for circulating scrubbing oil, is delivered from tanks area into lean oil tank. The 0.5 MPa (gauge) steam is heated upto 400°C by tube type heat furnace. One part is used as heat source for scrubbing oil regenerator, and the other enters as heat source into the bottom of benzol removal tower. The fuel of tube type heat furnace is supplied by the gas after benzol scrubbing and filtered by gas filter. During the operation of benzol scrubbing and removal, the quality of circulating scrubbing oil deteriorates gradually. In order to ensure the quality of scrubbing oil, part of scrubbing oil will be regenerated by scrubbing oil regenerator. VIMTA Labs Limited, Hyderabad 54 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State It is heated by hot steam, and the oil vapors thus distilled enters into benzol removal tower. The residue could be discharged to residue oil tank and delivered to coal storage yard periodically, or it could be used as fuel. In order to reduce naphthalene contents in scrubbing oil, there are baffle plates at the top of benzol removal tower, for capturing naphthalene. The naphthalene oil flows into naphthalene liquid tank and pressurized by steam to be sent to the tar tanks in the tanks area. The condensation liquid which is produced from final cooling tower enters into water sealing tanks of final cooling tower, and then over-flows into condensation liquid storage tanks, wherein it is circled via condensation liquid pump to final cooling tower for spraying. The redundant part is delivered to condensation/blowing section. The process flow diagram for obtaining Crude benzol is shown below. Benzol Hydro-Refining Unit Benzol hydro-refining unit will utilize the crude benzol as raw material and remove the harmful impurities such as hydrocarbon, hydrogen sulfide, ammonia and water etc. containing the sulfur, nitrogen, oxygen through chemical and physical methods, in order to get high purity benzene, toluene, xylene. The process diagram is shown below with process description. VIMTA Labs Limited, Hyderabad 55 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Process Description Hydro-refining unit removes the impurities from the crude benzol through twostage hydrogenation reaction, including de-heavy component of raw material, hydrogenation reaction, hydrogenation oil stabilization and the hydrogenation oil pre-distilling part. Typical benzol feed to hydro refining unit is as below. Component Benzene Toluene Olefins/ Aromatics Thiophene CS2 Pyridine Others Total VIMTA Labs Limited, Hyderabad wt % 73.80 11.40 8.50 0.56 0.08 0.40 5.26 100 56 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Pre-fractionation of Benzol (Deoctanizer) The crude benzol from tank area pump enters the de-octanisation column. This column operates under slight vacuum. The column separates the light and heavy components from benzol. The overhead vapour (C8 aromatics & below) are condensed in air cooled condenser and are ready to be hydro treated. 1st Stage Hydro-Refining The C8- cut from Deoctanizer is pumped to the reactor by the high-pressure reactor feed pump. Make-up hydrogen is pressure boosted by the makeup hydrogen compressor and then combined with the reactor feed and heated to the required inlet temperature of the 1st stage hydro-refining (HDT) reactor by exchanging heat with the 2nd stage reactor effluent. The combined feed stream is then passed through the 1st stage reactor, where saturation takes place. The reactor operates in mixed phase with a high liquid content to prevent reactor plugging caused by potential polymer by-products. 2nd Stage Hydro-Refining The effluent from 1st stage hydro-refining is heated through exchanger with hot 2nd stage reactor effluent before being sent to Vaporizer for full vaporization. Recycled hydrogen is preheated with high pressure (HP) steam and then combined with 1st stage reactor effluent. The 1 st stage reactor effluent – hot hydrogen mixture is brought at the outlet of exchangers in full vapor phase conditions. Any polymeric material present in the full vaporized stream, is separated in vaporizer and drawn off the bottom of the vaporizer. This liquid draw is eventually recycled back to the Deoctanizer for polymer removal with the C9+ material. Vapor is further pre-heated in fired heater to the required reactor inlet temperature and then sent to the 2 nd stage HDT reactor. In the 2nd stage HDT reactor, desulfurization, denitrogenation, and mono-olefin saturation occur. The 2nd stage reactor effluent is cooled/ condensed by preheating the feed to the 2nd stage reactor followed by preheating the feed to the 1 st stage HDT reactor, and then preheating the feed to Deoctanizer. The reactor effluent is finally cooled in 2nd stage reactor effluent air-cooler and finally by a water-cooled exchanger and supplied to the 2nd stage HDT separator. In the separator the hydrogen and light hydrocarbon gases are separated from the hydrotreated product. Separator offgas is routed to the MEA system, for H2S and NH3 removal, before being recycled to the vaporizer by the recycle gas compressor. A small purge stream is purged out of the system to control the level of impurities in the recycled gas. Water is recycled around the last cooler and separator in order to prevent plugging. The liquid product from the separator drum is sent to the stabilizer to remove the light ends, remaining dissolved H2S and water. Stabilizer The hydrotreated liquid from the separator is introduced into the stabilizer. Feed is preheated by exchanging heat with the stabilizer bottom stream. Overhead vapors from the stabilizer is condensed in water-cooled condenser and collected in overhead receiver. The stabilizer removes the light ends, hydrogen, H 2S as noncondensable vapor and water as liquid. The water is purged out of the system while VIMTA Labs Limited, Hyderabad 57 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State the offgas is sent to the BL. Remaining overhead liquid is sent back to the stabilizer as reflux. The bottom product is sent to Deheptanizer for further processing. MP steam is used for reboiling Stabilizer in reboiler. Deheptanizer The stabilized product is sent to Deheptanizer, where C8 aromatics are separated to the bottom of the column. Overhead vapors, mostly C6-C7 hydrocarbons, are condensed in air-cooled condenser and collected in overhead receiver. Overhead liquid is then sent to extraction unit for aromatics production by deheptanizer overhead pump. Deheptanizer bottoms is cooled down to storage temperature using cooling water and sent to the BL by deheptanizer bottom pump. Deheptanizer is reboiled using MP steam in reboiler. Recycle Gas H2S Removal Methyl diethanolamine (MDEA) is used for H2S absorption from recycle gas. The absorption takes place in H2S absorption column. Recycle gas is supplied at the bottom of the column while lean MDEA is supplied at the top of the column. The vapor stream leaving the top of the absorber is free of H 2S and can be recycled back to the hydro-refining reactor. The bottom liquid represents the rich MDEA which is sent to the amine regenerator column. Overhead vapor is condensed and collected in overhead receiver. The sour water is returned as reflux; a small slip stream is purged to the BL, to the sour water stripper. The non-condensable consisting mainly in H2S vapor is supplied to the sulfuric acid unit for recovery and further processing. The bottom product of the amine regenerator represents the lean solvent which will be returned in a close circulating loop to the top of the H 2S absorber. The lean MDEA is cooled down by preheating the rich MDEA feed to the column and finally cooled down to the H2S absorber feed temperature by using an air-cooled heat exchanger. The lean MDEA is passed through a series of filters for removing any solid particles which can build up in the system and affect the operation of the absorber PSA Hydrogen Unit The hydrogen used for this device is produced by PSA hydrogen producing unit. PSA hydrogen producing device uses the plant COG gas for hydrogen production. The COG gas composition is complex, and product hydrogen purity requirement is high, so, the process of this device is composed of the compressing process, pretreatment process, the pressure swing adsorption process and purification process. Process is briefly described as follows: Compression Compressing process is composed of 2 sets (1 in operation and 1 in standby) of 3/4-stage reciprocating compressors. The COG gas is compressed by first stage of the compressor to ~ 0.22 MPa (G), then enters pretreatment system to remove the naphthalene, tar, NH3, H2S, organic sulfur and other aromatic chemical compound (s). After the treated COG gas is compressed by the second, third or fourth stages of compressor to ~ 2.7 MPa(G), it enters the pre-treatment system. VIMTA Labs Limited, Hyderabad 58 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Pre-treatment Process The pre-treatment system is composed of mist separator, 2 pre-absorbers and one set of superfine filter. The two absorbers are working alternately to realize the gas purification. The working process of pretreatment column includes: Adsorption process, pressure-reducing process, heating and impurities desorbing, cooling adsorbent and pressure boosting process. Pressure Swing Adsorption Process The pressure swing adsorbing process is designed as 5-1-3 PSA configuration. Sometimes 6-1-4 configuration is also adopted. The technological process consists of adsorption, boosting and pressure reducing, pathwise pressure releasing, reverse pressure releasing, washing, pressure equalizing and boosting and the final boosting of the product etc. Purification Process The 99.9% hydrogen, still containing some oxygen, needs to be purified further. The crude hydrogen first enters the normal temperature deoxidizing column and under Pallidium (Pd) based catalyst. Oxygen reacts with hydrogen to form water. The gas is then cooled to normal temperature in the cooler, enters pressureequalized TSA drying system composed of two drying column, one pre-drying column, one liquid separating tank and two heat exchangers etc. The product hydrogen can reach requirement with purity of 99.99% and oxygen content is guaranteed to be less than 10ppm (usually less than 1ppm) and dew point that is lower than – 60 °C. The process flow of PSA hydrogen generation unit is given below: VIMTA Labs Limited, Hyderabad 59 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Control Philosophy The complete complex shall be monitored, controlled and protected using a new state of the art control system. The control system shall houses the substation switchgear equipment, the control system equipment / operator room and the administration area. The safeguarding system will incorporate the following systems: Basic Process Control Systems / Distributed Control System (DCS) Emergency Shutdown system (ESD) Fire & Gas System (F&G System) In general, the first layer of protection is from DCS. The DCS will perform basic control functions by regulating process variables such as pressure, temperature, flow, level etc. Many of the products that this facility processes are inherently hazardous. Therefore and ESD system is being employed to provide a second layer of protection to help mitigate many of the risks associated with the process. VIMTA Labs Limited, Hyderabad 60 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State The main operator interface shall be through DCS which consists of operator consoles, engineering consoles, alarm management, history and reporting, control, sequence, logic and monitoring functions. The ESD system shall be programmable Logic Controller which can automatically detect any abnormal operation or equipment conditions and alert the operator and also take automatic safety action to protect personnel, plant facilities and environment. The F&G system shall continuously monitor and detect fire, heat, smoke and flammable and toxic gases in the pant area. The F&G system which on detection shall initiate audible and visual alarms to alert personnel and initialize the fire protection system as desired. The control room shall be segregated in to two main sections - The rack room and the operator room. The rack room shall consist of all the control system cabinets, racks etc. The operator room shall consist of the Human Machine Interface (HMI) graphics displays, hardwired matrix panels that have critical alarm annunciators, push buttons and lamps, printers etc. Product Mix The expected quantity of products from the Hydro-Refining plant is given below: Description Benzene Toluene Mixed Xylene Raffinates Unit 63,000 t/yr 11,700 t/yr 5,400 t/yr 9,900 t/yr Percentage 70.0% 13.0% 6.0% 11% Crude Benzol Specification Specifications of crude benzol are given below. Item Appearance Density (20oC) Unit g/ml Specification Yellow Transparent Liquid 0.871 - 0.900 Distillation range Distillation capacity below 75 oC (volume), % not more than - Distillation capacity below 180 oC (volume), % not more than 93 Temperature at 96% distillation volume, oC not more than - Water Content No visible insoluble water at ambient temperature (18-25 oC) by visual method. Benzene Specification The main product of the proposed plant is Benzene. Its output from crude benzol is 65-70%. Benzene is an organic chemical compound. It is composed of six carbon atoms in a ring, with one hydrogen atom attached to each carbon atom, with the VIMTA Labs Limited, Hyderabad 61 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State molecular formula C6H6. Specifications of pure benzene for export grade are given below. Chemical and Physical Analysis Item Appearance Sp.Gr (20oC) Benzene Purity Non-aromatics hydrocarbons & Toluene Total Sulfur Thiophene wt Crystallization point Evaporation residue Acid wash colorimetry Residual Solvent Moisture Test for Neutrality Unit wt% Specification Colourless Transparent Liquid 0.878 - 0.881 99.95 min wppm 500 max wppm wppm o C 100 ml 0.5 max 0.5 max 5.5 min 5 mg max 0.05 g/K2Cr2O7/L 1.0 max 400 max Neutral wppm wppm Toluene Toluene, also known as Methylbenzene, is a clear, water-insoluble liquid with the typical smell of paint thinners. It is a mono-substituted benzene derivative, i.e., one in which a single hydrogen atom from the benzene molecule has been replaced by a univalent group. The molecular formula of toluene is C7H8 or C6H5CH3. Toluene is used: In the manufacture of foam mattresses e.g. polyurethanes. For making dyes, plasticiser, pharmaceuticals, phenol, benzoic acid, diisocyanate (used in polyurethane manufacture), benzene etc. As a solvent and diluent in coatings. For making the explosive 'Trinitrotoluene' (TNT). The chemical analysis of Toluene is indicated below: Item Appearance Sp.Gr (15.6/15.6oC) Pt-Co color Toluene Purity Benzene Non-aromatics Total Sulfur C8 Aromatics Basic Nitrogen Residual Solvent VIMTA Labs Limited, Hyderabad Unit wt% wppm wppm wppm wppm wppm wppm Specification Clear, White 0.869 - 0.873 20 max 99 min 200 max 9600 max 1 max 200 max 0.2 max 1 max 62 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Xylene Specification Xylene, also known as Dimethyl benzene is used as a solvent for paints pharmaceuticals etc. It can be converted to toluene and benzene for subsequent uses. The chemical analysis of Xylene is indicated below: Item Appearance Sp.Gr (20 °C) Pt-Co color Total Sulfur Distillation range Evaporated residues Unit wppm °C mg/100ml Specification Clear, White 0.860 - 0.870 20 max 3 max 10 5 max Tar Utilisation 20.0 Tar generated from coke oven plants will be about 3,00,000 T/annum, which is proposed to sold in the open market. ------------------------------------------------------------------------------------------ACTION PLAN FOR WASTE MANAGEMENT FOR EACH COMPONENT SHOULD BE SUBMITTED The details of waste generated from the proposed integrated steel plant are presented in the following sections. 20.1 Non-Hazardous Waste The main solid waste generated in the proposed steel plant will be BF slag, BOF slag and slime which is non-hazardous waste. Other solid waste includes gas cleaning plant sludge, dust from ESP, bag filter and dust extraction system and refractory debris etc. this solid waste except refractory will be completely reused in sinter plant and coal fines will be used in the power plant. Further, oil soaked cotton waste; organic wastes from steel plant, paper, plastics and waste bag filters will be generated. The details of solid waste generated from the proposed steel plant is given in Table-20.1. TABLE–20.1 SOLID WASTE GENERATION AND DISPOSAL Sr. No. Solid Waste Generation (TPA) Proposed Disposal 1 Slag a Iron Making slag 3,000,000 98% granulated and sold to cement plants, 2% treated in dry pits and used for land fill b Steel making slag 1,480,000 BOF slag is granulated, metallic separated and used in construction 2 Sludge a Iron making sludge 129,000 Used in pellet plant after dewatering b Steel making sludge 151,000 Used in sinter plants after dewatering 3 Slimes from Beneficiation Plant VIMTA Labs Limited, Hyderabad 5,800,000 Stored in secured land fill 63 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Sr. No. 4 Mill scales a Steel making shop b Rolling mills 5 Dusts A Generation (TPA) Proposed Disposal 38,000 Used in sinter plants 149,000 Used in sinter plants Flue dust from Blast furnace 106,572 Used in sinter plants B Dust from bag filter 343,428 Used in sinter plants 6 Lime / Dolo dusts 38,000 Used in sinter plants 7 Ash 8 Reject from Coal Washery (Middling’s) 9 20.2 Solid Waste 750,000 Refractory waste 1,600,000 50,000100,000 Sold to cement plants and manufacturing fly ash bricks used for Will be used in power plant Will be disposed in secured land field Hazardous Waste The hazardous waste such as waste oil, lead acid batteries and oil soaked cotton waste will be generated. The waste oil generated will be utilized in recovery coke oven for process improvements. Lead acid batteries will be sold to authorized users/recyclers approved by JSPCB. The oil soaked cotton waste will be incinerated in BOF. The hazardous waste generated from the proposed steel plant is given in Table-20.2. TABLE-20.2 HAZARDOUS WASTE GENERATION AND ITS DISPOSAL Sr. No. 1 Category Waste oil & Used oil Quantity kl or t/yr @10 MTPA 2750 KL / Year 2 3 4 Acid and alkali residue from CRM Waste pickled liquor from CRM Tar sludge from coke oven 5 Water treatment sludge 8172 t 6 Spent activated carbon, catalyst & Oil soaked filter Sludge from hazardous waste treatment process, incinerator & Waste sulphur 8.7 t/y 7 450 t 73216000 KL 315 t 59 t/y Proposed Disposal Sold to authorised parties Regenerated in ARP Regenerated in ARP Used back in Coke oven Sent to hazardous waste land fill Incinerated Sent to hazardous waste disposal site The utilisation schemes for BF, SMS and fly ash are covered under point no.4. 20.3 Utilization (Recycle & Reuse) of Solid Waste Different types of solid wastes are generated from integrated steel plant. The source of solid waste generation along with their re-use, re-cycle, utilization and disposal methodology are given in Table-20.3. VIMTA Labs Limited, Hyderabad 64 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State TABLE-20.3 SOLID WASTE GENERATION ALONG WITH THEIR RE-USE, RE-CYCLE, UTILIZATION AND DISPOSAL Sr. No. Type of Solid Waste Recycle 1 BF slag 2 BOF Slag 3 BOF Scales & Reused in Scrap sinter plant as sinter mix. Mill Scrap Used in BF Fly ash 4 5 6 7 8 9 10 11 - Re-utilization Dump for Future Re-use Use Within Plant Sold Cement plant Sold to cement manufacturer/glass manufacturers Granulated and Will be sold to parties partly used in for building roads plant (aggregate for road Balance will be making, rail track crushed & used ballast, land filling, for making after conditioning as roads, civil it contains lime which works, etc. if used before conditioning then it swells), civil engineering works, etc. Used in sinter plant - Sold to cement manufacturers/road making/brick making Bottom Ash Ash Waste -Used in plant for Sold as material for Refractory making making road refractory mortars embankment or for filling in captive low lying areas mortar shops - Making / repairing plant roads Lime/dolomite Re-used in sinter Fines plant Mill scale -Reused in sinter plant - Reused as a reductant input material in BF BF flue dust Reused in Used in pellet sinter plant plant as sinter mix. BF GCP Reused in Used in sinter sludge sinter plant plant after as sinter pelletisation mix after pelletisation VIMTA Labs Limited, Hyderabad - dump - - - 65 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Sr. No. • • Type of Solid Waste Re-utilization Dump for Future Re-use Use Within Plant Sold 12 BOF sludge Reused in Used in sinter sinter plant plant & BF 13 Sinter ESP Recycled in dust sinter plant Recycle of waste means utilization of waste in the same process from which it has been generated Reuse of waste means utilization of the waste in any process other than the process from which the waste has been generated. The process utilizing the waste may be within the plant or outside the plant. In case of utilization outside plant, the waste is sold to firm utilizing the waste • Disposal means dumping of waste in designated areas. Recycle The following shop wise specific management measures will be adopted for solid waste: Sinter Plants 100% recycling of LD sludge, mill scale, lime and dolomite dust, SP sludge, and ESP dust; • 100% recycling of return sinter fines; • Utilization of 10 mm LD slag; and • BF flue dust utilization in Sinter Plant. DR Plant • • DRI process dust 100% used - reused in sinter plant as sinter mix. Unused quantity sold to parties for brick making, land filling and to oil refineries as replacement of activated carbon; and DRI de-dusting dust 100% used - reused in sinter plant as sinter mix. Unused quantity sold to parties for brick making & land filling. Blast Furnaces • • • • • 100% cast house slag granulation for sale to cement plants; Recovery of iron scraps at BF slag dump; Use of cast-able material in cast house runners, in place of ramming mass, which will reduce scrap generation by 1%; Recycling of BF flue dust in sinter plant and sold; and Recycling of used refractory. Steel Melting Shops • • Recycling of LD sludge will be explored; and LD slag – after granulation partly used in sinter plants, blast furnaces and steel melting shop for conserving limestone & dolomite. Balance used for making roads, civil works etc. Refractory Material Plant • • • Under size limestone, dolomite & lime fines recycled 100% to sinter plant; Utilisation of refractory grog made from used refractory bricks for mortar manufacturing of different grades (25% raw material input is from grog); Ladle covering compound in SMS using LD slag; VIMTA Labs Limited, Hyderabad 66 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State • Waste Mg-C bricks for production of new bricks for converter bottom, coating and patching materials for converter vessels; and Rolling Mills • 100% recycling of mill scales. Coal Based Power Plant • 100% used in Fly-ash brick making plant and sold to cement plants. 20.4 Solid Waste Management at JSW Steel-Vijayanagar Plant The following practices were started in JSW Vijayanagar Plant, to effectively utilise the micro fine dusts and mill scale dusts in Sinter Plant and SMS Plant after agglomeration. A. Micro Pelletizing Plant During iron and steel making a wide range of by-products are produced. Among these large amounts of micro fine dust and sludge are generated from the air and water pollution control equipment. These non-iron/steel by-products are often termed wastes. This has been especially true in the past when large quantity of these materials were land filled. In today’s green manufacturing world it is becoming increasingly difficult and costly to continue with land filling. To term these materials as waste ignores the potential value that exists in them and the benefits that they can have on the iron and steel making process. Correct management of these by-products can recover their value and reduce existing cost of land filling. Micro-Pelletization is a process that converts individual by-products into a homogenized agglomerated form that can be handled in conventional iron and steel making units i.e. blending of BOF Sludge from Steel Melting Shop, Blast Furnace sludge from Gas cleaning plant slurry, Bag filter dust, ESP dust, Lime & dolomite dust, Blast Furnace Flue Dust and LD Slag (<6mm) from steel melting shop, to produce a blend suitable for micro-pelletization. The aim of the process is to produce a consistent blend in terms of ‘handleability’, temperature and moisture content that can then be used to produce micro-pellets of the desired quality, which can be used in sinter making in conventional Iron & steel making. Application Large amount of iron ore fines and micro fine dust are utilized for sinter making, Earlier at JSW Steel, there micro fines dust were used in sinter making routing through the basemix( Raw material pile). Since these micro fine dusts wholly do not take part in the process of sinter making, the inlet dust concentration increases due to which there is high emission from the sinter plants are observed. Use of these micro pellets in sinter making reduces emission level. Working Philosophy The micro pellet plant converts the input materials into useable agglomerated products. The plant comprises a mixing, micro pelletizing and discharge circuit. A 0.6 MTPA micro pellet plant has been commissioned in Aug 2013 at JSW Steel Vijayanagar works. Micro pellets are produced using the dust, sludge and slag as mentioned above and water is added to create the micro pellet feed mix. Micro pellet production is made in to a predetermined recipe with a moisture content of 10%. The recipe specifies the VIMTA Labs Limited, Hyderabad 67 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State amount of each component that is used within the batch, the moisture content and the mixing time to be used and the settings to be used for the pelletising disk. Process Description The mix will be discharged from the mixer and conveyed to a pelletizing disc and this will agglomerate the mix to produce micro pellet of the desired size ( 6 mm by adjusting, speed and angle of inclination of the disc). The micro pellets will be discharged from the disc onto a conveyer. Micro pelletizing plant is shown in Figure20.1. Any fines or spillages generated by the process will be conveyed back to the front end of the plant and combined with the mix such that they are fully recycled at the facility. The micro pellets are released from the pelletizing disc onto a series of discharge conveyers. From the conveyer, the micro pellets pass down a discharge chute onto a rotary stacking conveyer. It stacks the micro pellets into one of four 2500 tonne stockpiles. Micro pellets are left to cure in their initial stockpiles from 48 to 72 hours or depending on production and then sent to base mix for further use in sinter making. Micro Pellet Typical Composition By-products BOF sludge Bag filter dust Flue dust <6mm slag Lime & Dolomite dust Burnt lime Water Total % of byproduct Used 30 14 30 17 6 2 1 100 Product Quality The Fe (T) in micro pellets is about 38% Benefits 1. Increased consumption of waste material in the base mix. It has been observed that the waste utilization has increased from 45 to 70 kg/ton of base mix. 2. Reduction in Stack Emission in Sinter Plants. 3. Reduction of -100 mesh in base mix by 2.5% is expected to increase sinter productivity by 0.5 T/Sq.m/Day. 4. Regular Disposal of Dust from Bag Filters leading to improved performance. 5. Increase in solid waste utilization. VIMTA Labs Limited, Hyderabad 68 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State FIGURE-20.1 MICRO PELLETIZING PLANT B. Mill Scale Briquetting Plant:- 0.2 MTPA In an integrated steel plant during iron and steel making, large amount mill scales from mills, iron bearing dusts are generated from the blast furnace cast house and secondary fume extraction system of steel melting shop. Conventionally the mill scale consisting of > 72% Fe (total) is used for sinter making in steel making. Due to the high iron content of these kinds of dust and waste materials, an innovative technique of briquetting these kind of wastes was implemented at JSW Steel for better and gainful utilization in LD converters in steel melting shop. Mill scale briquetting plant converts individual by-products into a homogenized agglomerated form that can be handled in steel making facilities. Application LD converters in Steel Melting Shop (SMS) requires large amount of iron fines as coolant in the process. These briquetting can be used as alternative source of these iron ore. Where in it reduces iron ore input to steel making. Earlier at JSW Steel, there iron fines were used in steel making as coolant. Since these iron fines wholly do not take part in the process of steel making (as blowing oxygen will carry away the dust particles) the inlet dust concentration increases due to which there is high emission from the roofs of steel making shops are observed. Use of mill scale briquettes in steel making as drastically reduced emission. Working Philosophy Mill scale briquetting is a process that converts individual by-products into a homogenized agglomerated form that can be handled in conventional steel making units i.e. blending of Mill scale, CRM dust, Hydrated lime and molasses, in required quantity VIMTA Labs Limited, Hyderabad 69 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State to produce a blend suitable for Mill scale briquetting. The aim of process is to produce a consistent blend in terms of ‘handle ability’, temperature, density and moisture content that can then be used in steel making. Proposed Technology About 500 TPD of the mill scale and iron bearing dust from blast furnace, CRM and steel melting shops. is generated from the various sources is briquetted to further directly used as coolant in LD converter. Mill scale is mixed with required proportion of hydrated lime, molasses, CRM pickling dust and bag filter dust to produce briquettes of size 75 x 50 x 25 mm, having adequate strength and chemical properties suitable for LD converter to be used as a coolant. Environment Friendly Product The mill scale briquettes produced contains high Fe content, which can be directly used in the LD converter as a coolant, there by replacing equivalent amount of Iron ore/DRI or Scrap. This is an environment friendly product as it usage in LD converter in steel melting shops would considerably reduce usage of raw material (Iron ore) or Direct reduced Iron produced from the DRI plant or metal scraps. MILL SCALE BRIQUETTE TYPICAL COMPOSITION Consumption Mill Scale Bag Filter Dust CRM Dust Hydrated lime Molasses % 77.97 7.97 4.05 2.02 8.00 Product Quality The Fe (T) in mill scale briquettes is about 65% Benefits 1. The mill scale briquettes produced contains high Fe content, which can be directly used in the LD converter as a coolant, there by replacing equivalent amount of Iron & ore/DRI or Scrap. 2. This is an environment friendly product as it usage in LD converter in steel melting strips would considerably reduce usage of raw material (Iron ore) or Direct reduced Iron produced from the DRI plant or metal scraps. 3. Lime consumption is marginally reduced. 4. Yield is marginally increased 5. Re-blow is reduced ---------------------------------------------------------------------------------------------- VIMTA Labs Limited, Hyderabad 70 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State 21.0 THE COMMITTEE PRESCRIBED AN AMOUNT OF RS. 700 CR OVER A PERIOD OF 10 YEARS FOR THE CSR RELATED ACTIVITY. A DETAILED PLAN IN THIS REGARD SHOULD BE SUBMITTED. JSW conducted need based survey of sustainable development in the study area (10 km radius) and identified needs of the local peoples including valid concerns expressed during public consultation, mitigation issues merging from social impact assessment and R&R plan. It is therefore, total Rs. 175 corers (capital & recurring cost) is proposed towards CSR related activities and also detailed plan covering the activity wise cost involved is submitted below: PROPOSED CSR BUDGET Sr. No. 1 2 3 4 5 6 7 8 Category Health programs Water and sanitation Education programs Sports and culture Livelihoods Community infrastructure development including green belt development Supporting vulnerable persons Management cost (Rs. in Crores) Grand Total Capital Expenses (Rs. In Crores) Recurring Expenses (Rs. In Crores) Total 25.00 18.00 06.28 04.00 10.00 20.33 10.35 04.00 04.40 05.25 (Rs. In Crores) 45.33 28.35 10.28 08.40 15.25 25.00 08.98 33.98 0 03.41 05.00 25.00 93.28 81.72 03.41 30.00 175 DETAILED CSR BUDGET AND ACTION PLAN Sr. No. 1 CSR Programs Health Programme VIMTA Labs Limited, Hyderabad Action Plan Mobile medical unit (MMU) with doctor, pharmacist, lab technician, community health worker and diagnostic facilities in collaboration with technical support agencies like Help-age India (Best Practice) Partnership with government primary health center for supplementing national health programs like polio, TB, and malaria etc. Health camps for family planning HIV/aids and other communicable diseases Promoting rural health insurance by creating awareness and subsidy Training and awareness programs for health, hygiene and sanitation volunteers Total Approx. Budget in Crores 16.5 10 7 7 4.83 71 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Sr. No. 2 CSR Programs Water and Sanitation Programme Action Plan Establishing water treatment and distribution system in periphery villages @ 20 lts. to each family (Tata trust model of drinking water treatment plant can be adopted) Ensuring supplying of drinking water to the periphery villages in summer by providing tankers, wherever is required. Providing proper sanitation facilities to the villages and developing nirmal gram puraskar villages (national program) Total Approx. Budget in Crores 45.33 20 7 1.35 28.35 3 4 5 Education Programme Sports & Cultural Livelihoods Development Programme Strengthening of school buildings/ establishing model Aganwadies/ Balwadies in collaboration with ICDS and adult education centers drinking water supply and toilets in schools Setting up of village school, library ,computer training, ITI's Strengthening of mid - day meal program by improving quality of food, kitchen in the school, plates and tumblers etc. Sponsorship of bright students of adjoining villages Promoting rural sports through coaching and sports material support in project periphery villages Facilitation and sponsorship to local talent for competitions and state, national & international level coaching Organizing local and district level sports meets Developing play grounds in each affected village Short term courses for employability skill training in collaboration with Rajiv Gandhi youth employability skill development program Sponsorship and promotion of full time vocational training course Promoting micro-enterprises and small business Agriculture, horticulture and animal husbandry development program 0.94 1.54 6.3 1.5 10.28 2.1 1.4 1.4 3.5 8.4 2 1.25 7 5 15.25 6 Community Infrastructure VIMTA Labs Limited, Hyderabad Construction of roads, public utilities, bus shelters, religious places etc. in all project affected villages and the study area as per requirement. Laying of drainage system, improving sanitation facilities, construction of toilets. Construction of community center in project periphery villages 28 3.5 0.7 72 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Sr. No. CSR Programs Action Plan Construction of health center Veterinary service center Developing grazing lands 7 8 Supporting Vulnerable Persons Management Cost Ensuring life-long pension to vulnerable (elderly/widows/special disabilities) from the government schemes through community facilitation services Gainful engagement on priority to vulnerable persons and creation/adoption of old age homes Human resource and establishment of foundation and administration Total (Rs in Crores) Total Approx. Budget in Crores 1 0.3 0.48 33.98 2.71 0.7 3.41 30 175 --------------------------------------------------------------------------------------------22.0 TOWN PLAN DETAIL SHOULD BE SUBMITTED INCLUDING THE LAYOUT OF THE BUILDINGS, GREEN BELT, INTERNAL ROADS, STP, AND PARKING PLAN ETC. The township is to serve a large steel plant of 10 MTPA capacity and CPP of 900 MW capacity. The proposed township is planned over an area of 121.41 ha in Barenda village and may have up to 9620 dwellings of various categories. Adequate green belt/green cover will be developed in the township. The township will be located in the northeast direction to the plant and falls in the cross-wind direction to the proposed plant site. The existing layout of JSW-Vidyanagar township is shown below. The township will be developed with all facilities including green belt, open spaces for car parking, community centre, school, temple, health centre, STP and water treatment plant etc. The township layout will be finalised during the detailed engineering stage. JSW has already constructed townships at the following locations 1) 2) 3) 4) 5) Vijayanagar, Karnataka Barmer, Rajasthan Jaigarh, Maharashtra Salem, Tamil Nadu Vasild, Maharashtra The proposed township at Barenda village shall also be in the same lines as described above. VIMTA Labs Limited, Hyderabad 73 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State VIDYANAGAR TOWNSHIP LAYOUT PLAN ------------------------------------------------------------------------------------------------- VIMTA Labs Limited, Hyderabad 74 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State 23.0 DETAILS REGARDING THE PROPOSED CAPTIVE THERMAL POWER PLANT SHOULD BE SUBMITTED. It is proposed to install a 900 MW CPP for the proposed plant for which 3.0 MTPA of thermal coal and 2.0 MTPA of middling’s generated from the captive coal washery of the plant will be required. Thermal coal would be replaced by the surplus plant gas to the extent possible. The configuration of the CPP shall be 3 x 300 MW. The plant and equipment for captive power plant of capacity 300 MW (1 unit) are enumerated below. The typical flow diagram of captive power plant is shown in Figure -23.1. Steam Boiler & Accessories The steam boiler (SB) would be designed for firing 100% imported coal and would be natural circulation drum type. The SB would be of two pass design, radiant, single reheat, balanced draft, semi-outdoor type, rated to deliver 1015 t/hr of superheated steam at 173 ata, 541 0C when supplied with feed water at a temperature of 2790C at the economiser inlet. The reheat steam temperature would also be 5410C. The steam boiler would be provided with coal mills along with individual raw coal gravimetric feeders and coalbunkers. Sampling arrangement at mill outlet would be provided for purpose of establishing the average gross calorific value of coal as well as coal fineness. The coal mills would be provided with steam blanketing system for the purpose of fire protection. The SB would be designed to handle and burn HFO as secondary fuel up to 22.5% MCR capacity for start-up and for flame stabilisation during low-load operation. For unit light up and warm up purposes LDO shall be fired. The required fuel oil pressurising units and fuel oil heating equipment would be provided. High-energy electric arc ignitors would be provided to ignite the fuel oil guns. The steam boiler would consist of water cooled furnace, radiant and convection super-heaters, re-heaters, economiser, regenerative air heaters, steam coil air preheaters, etc. Soot blowers would be provided at strategic locations and would be designed for sequential fully automatic operation from the unit control room. The plant would comprise of primary air fans, forced draft fans, and induced draft fans. Electrostatic precipitator (ESP) and fly ash hoppers would be provided for the collection of fly ash. The ESP shall be designed to achieve an outlet dust concentration of 50 mg/Nm³. Steam Turbine Generator & Accessories The selected steam turbine generator (STG) would be rated for 300 MW maximum continuous output at the generator terminals, with throttle steam conditions of 165 ata and 538OC / 538OC steam temperature and 0.1 bar (a) back pressure. The steam turbine would be a reheat extraction-condensing turbine. The turbine-generator would be complete with all accessories such as protection system, lube and control oil systems, seal oil system, jacking oil system, seal steam system, turbine drain system, 60% MCR HP/LP bypass system, electro-hydraulic control system, automatic turbine run-up system, on-line automatic turbine test system and turbine supervisory instrumentation. The turbine-generator would also have all necessary indicating and control devices to permit the unit to be placed on turning gear, rolled, accelerated and synchronized automatically from the control room. Other accessories of the turbine-generator would include an oil purification unit with transfer pumps and clean and dirty oil storage tanks of adequate capacity. VIMTA Labs Limited, Hyderabad 75 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Feed Cycle Equipment Condensate Extraction Pumps 2 x 100% capacity condensate extraction pumps, one working and one standby, would be provided. The pumps would be vertical, canister type, and multistage centrifugal pumps driven by AC motors. Generator Water Treatment Raw Water Turbine D.M Makeup Deaerator LP Heater Boiler Reservoir C.W Pump Neut Pit BFP H P Heater Mill CEP Intake Pump RIVER Economisar Condenser Coal Bunker Makeup Cooling Tower Ash Water Pump House Central Monitoring Basin Air Preheater FD Fan To Ash Handling System Dust Supression/ Sanitation/ Green Belt Dev. PA Fan Electrostatic Precipitator Bottom Ash ID Fan Chimney Fly Ash Collection/ Disposal FIGURE -23.1 TYPICAL FLOW DIAGRAM OF CAPTIVE POWER PLANT VIMTA Labs Limited, Hyderabad 76 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Boiler Feed Pumps 3 x 50% capacity boiler feed pumps would be provided to pump the feed water from the de-aerator to the steam generator through the high pressure heaters. The boiler feed pumps would be horizontal, multistage, AC motor driven centrifugal pumps of barrel type with variable speed hydraulic coupling. Low Pressure Heaters The low-pressure heaters would be of shell & tube type with U-shaped carbon steel tubes, with their ends rolled in carbon steel tube sheets. De-Aerator The de-aerating feed water heater would be a direct contact, variable pressure type heater with spray-tray type or spray type of de-aeration arrangement. The feed water storage tank would have a storage capacity adequate to feed the steamgenerator for 6 minutes when operating at MCR conditions. High Pressure Heaters The high-pressure heaters would be of shell & tube type with carbon steel U-tubes welded into carbon steel tube sheets. The HP heaters would be provided with a desuperheating zone and a drain-cooling zone in addition to the condensing zone. Gland Steam Condenser A surface type gland steam condenser would be used to condense the gland steam exhausted from the turbine glands. The gland steam condenser would be of singlepass type with the main condensate flowing through the tubes to condense the steam. Exhausters would be provided to evacuate the air from the shell side and maintain the shell at the required negative pressure. Turbine Lube Oil Purification System In the lubrication cycle for the turbine-generator, the lube oil comes in contact with water, air and metal particles, which cause deterioration of the lube oil. In order to prolong the life of the lubricating oil and the parts served by the lube oil, suitable purification equipment is required to be provided to remove the contamination and restore the oil to acceptable conditions. Fuel Oil System The fuel oil system would be designed for the use of heavy fuel oil (HFO) for startup and flame stabilisation purposes. Light diesel oil (LDO) shall be used as fuel for light up and warm up purposes. The peak requirement of LDO would be during light up and commissioning whereas the peak requirement of HFO would be during the trial operation. Chemical Dosing System Phosphate dosing system would be provided to ensure chemical conditioning of the steam generator drum water so as to prevent scale formation. In addition, ammonia/hydrazine-dosing system would be provided to ensure chemical conditioning of the feed water by removing the dissolved oxygen and carbon dioxide present in the feed water. VIMTA Labs Limited, Hyderabad 77 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Instrumentation And Control System Distributed Microprocessor Based Instrumentation Microprocessor based distributed control system with state of art Man - Machine Interface (MMI) is proposed to provide a comprehensive integrated instrumentation and control system including the functions of Data Acquisition System (DAS) to operate, control and monitor the steam generator and auxiliaries, steam turbine generator and auxiliaries and the balance of plant systems with a hierarchically distributed structure. Utility Packages Utility packages are proposed with dedicated stand-alone I&C system. However, these panels are proposed to be located in the unit control room. Unit Control Desk The unit, functional group / drive level control and operation of all main plant equipment including generator, transformers and auxiliaries would be from a set of monitors mounted on a control desk. Control Room A common control room is proposed with all the facilities of main control room, electronic cubicle room, Shift Charge Engineer’s room, auxiliary electronics room & UPS room. Auxiliary Systems Compressed Air System Two (2) (one operating & one standby) screw would be provided for the proposed unit. Air Conditioning System It is proposed to air-condition the unit control room, electronic cubicle room, shift charge engineer’s room, ESP control room, SWAS, analyzer panel room, coal handling control room, DM plant control room and switchyard control room. Ventilation System For the ventilation of the station building, evaporative cooling system (Air washer type) is envisaged. For ventilation of other buildings, supply air fans, exhaust air fans, roof extractors or a suitable combination of these would be provided. Hydrogen Gas System Hydrogen gas with a purity of 99.9% (by volume) is required for cooling of the generator. It would be required for the initial filling and continuous make-up during normal operation for maintaining the required purity in the generator. Cranes and Hoists Station Building Cranes Two nos. Overhead, cabin / pendent operated electric overhead traveling (EOT) VIMTA Labs Limited, Hyderabad 78 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State cranes, of 125 / 20 tons capacity would be provided for the proposed Unit also for handling of various main plant equipment. Turbine & generator erection would also be carried out by using the above cranes. CW Pump House EOT Crane Mobile crane would be provided to facilitate erection and maintenance of pump components and drive motors. EOT Crane for Lifting Boiler Feed Pumps (BFP) An EOT crane of 12 tons capacity crane is proposed to be provided for maintenance of BFPs for the proposed Unit. Miscellaneous Lifting Tackles / Hoists For the equipment, which weighs above 1000 kg, electrically operated type of hoists and trolleys would be provided. For the equipment weighing less than 1000 kg, manually operated hoists and trolleys would be provided. Workshop Equipment It is proposed to utilize the work shop equipment available in the existing power plant and no separate work shop equipment are proposed to be procured for the expansion plant. Electrical Systems Generator The generator would be rated to deliver 300 MW, at 20 kV, 50 Hz, 0.85-power factor, at 3000 rpm. The generator winding would be star connected with the phase and neutral terminals brought out to an accessible point. The generator will deliver rated MVA output under ± 5% variation in voltage and +3 to -5% variations in frequency. The star point of the generator would be connected to earth through an earthing transformer, the secondary of which will be loaded by a resistance. The generator Stator winding and terminal bushing are water inner-cooled, rotor winding is hydrogen inner-cooled and stator core hydrogen cooled. Hydrogen coolers would be built into the stator frame of the generator and would be sized to ensure at least 80% of the rated output when one hydrogen cooler is taken out for maintenance. The generator would be provided with either brush-less or static excitation system. Suitable fast acting non-dead band type continuous acting voltage regulator would be provided and mounted in sheet steel clad cubicles. The excitation cubicles will have necessary sections to house the apparatus and accessories required for field flashing and control. The generator would be provided with Class – F insulation. However, temperature rise would be limited to Class – B. Generator Bus Duct The terminals of the generator will be connected to the generator transformer through Isolated Phase Bus Duct (IPBD) of adequate short circuit withstand capability with suitably rated tap-offs to the unit auxiliary transformers. The bus VIMTA Labs Limited, Hyderabad 79 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State duct will be natural air-cooled and will run partly indoors and partly outdoor. The rating of the generator bus duct will be as furnished in table below. GENERATOR ISOLATED PHASE BUS DUCT (IPBD) Sr. No. 1 2 3 4 5 6 7 Particulars Type of Bus Duct Nominal Service Voltage / frequency Rated voltage Continuous current rating Basic impulse insulation level (1.2/ 50 micro-sec) Bus bar conductor material VT & SP cubicle Voltage transformer Lightning Arrestor 8 Bus duct material Rating IPBD / Natural air cooled 20 kV / 50 Hz 24 kV 12,500 A 125 kV peak. Aluminium / as per IS 5082 20 / 3 kV / 110 / 3 V / 110 / 3 V, 3 nos., 100 VA / ph. 24 kV Metal oxide type, with nominal discharge current of 10 kA. Aluminium / as per IS 5082 Generator Transformer The generator will be connected to the 400 kV switchyard through the generator transformer (GT). The GT will be 355 MVA, 3 phase ONAN / ONAF / OFAF cooled and will be provided with on-load taps in steps of 2.5%. The BIL of the transformer will be 1300 kV. The rating and details of the generator transformer are as in table below. GENERATOR TRANSFORMER Sr. No. 1 2 3 4 5 6 7 8 9 Particulars Type of cooling Rating No load voltage ratio Vector group Percentage impedance Type of tap changer Tap range Impulse voltage withstand (1.2/ 50 micro-sec) Terminal connection LV Side 10. Applicable standard Rating ONAN / ONAF / OFAF 355 MVA, 3 phase 20 kV / 420 kV Ynd1 14.5% On-load + 5% to –10% in steps of 1.25% 1300 kV peak. HV side Terminals on bushings for overhead line connection. Throat type with matching flanges for connection to IPBD. IS 2026. Station Transformer One Station transformer of three – winding, three phase, 50 / 25 /25 MVA, 220 kV / 6.9/6.9 kV, with on load tap changer +5% to -15% in steps of 1.25% will be provided. The ST-6 shall be connected to the existing 220 kV switchyard. The ratings and details of the station transformer are as in table below. Station Transformer Sr. No. 1 2 Particulars Type of cooling Rating VIMTA Labs Limited, Hyderabad Station Transformer ONAN / ONAF 50/25/25 MVA 80 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State 3 4 5 6 7 8 No load voltage ratio Vector group Type of tap changer Tap range Impulse voltage withstand (1.2/ 50 micro-sec) Terminal connection LV Side 9 Applicable standard 220 kV / 6.9/6.9 kV YN yno (yno) on-load +5% to –15% in steps of 1.25% 950 kV peak. HV side Terminals on bushings for overhead line connection. Throat type with matching flanges for connection to SPBD. IS 2026 Steel Plant Transformers Two transformers of three – winding, three phase, 210/ 150 /60 MVA, 400 kV /34.5/11.5 kV, would be connected to 400 KV to evacuate power to the steel plant. The ratings and details of the transformers are as in table below. 400 KV Transformers Sr. No. 1 2 3 4 Particulars Type of cooling Rating No load voltage ratio Percentage of Impendence Transformer-1 ONAN / ONAF/ OFOF 210/ 150 /60 MVA 400 kV /34.5/11.5 Kv 10% on 50 MVA base for 50 MVA rating Transformer-2 ONAN / ONAF/ OFOF 210/ 150 /60 MVA 400 kV /34.5/11.5 Kv 12% on 150 MVA base for 150 MVA rating 400 KV Switchyard The technical parameters of the switchyard are indicated in table below. 400 KV Switchyard Sr. No. Parameters 1.0 1.1 (a) (b) (c) (d) 1.2 (a) (b) (c) (d) 2.3 3.0 3.1 Technical Data for Switchyard Design Voltage Levels Nominal Voltage Highest system voltage Basic impulse level Fault level Minimum Clearances Phase to Phase Phase to Earth Section Clearance Minimum height of live point above finished grade Minimum creepage distance Circuit Breakers Type of breaker Short circuit breaking and making current Applicable standards Isolators Type of mounting and execution of poles 3.2 4.0 Applicable Standards Current transformers 1.3 2.0 2.1 2.2 VIMTA Labs Limited, Hyderabad Ratings, 400 kV Switchyard Ratings, 220 kV Switchyard 400 kV 420 kV 1425 kV peak. 40 kA rms for 1 sec. 220 kV 245 kV 1050 kV peak. 40 kA rms for 1 sec. 4100 3400 6500 2440 2400 2100 4000 2440 mm mm mm mm mm mm mm mm 31 mm /kV 31 mm / kV SF6 40 kA rms / 100 kA peak. IEC - 56 SF6 40 kA rms / 100 kA peak. IEC - 56 Centre break, horizontal upright IS 9721 Centre break, horizontal upright IS 9721 81 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Sr. No. Parameters 4.1 Type 4.2 Accuracy class for metering cores 4.3 4.4 No. of cores per CT Applicable standards 5.0 5.1 Capacitive voltage transformer Type 5.2 Rated voltage factor 5.3 5.4 5.5 6.0 6.1 6.2 6.3 6.4 6.5 6.6 7.0 7.1 7.2 Method of connection Accuracy class for metering cores Applicable standards Lightning Arrestor Type Rated voltage Nominal discharge current Low current / long duration class Pressure relief class Applicable standards Line traps Continuous current rating Quantity 7.3 8.0 8.1 Applicable standards Coupling devices Applicable standards Ratings, 400 kV Switchyard Outdoor, oil immersed. 0.2 for revenue metering and 0.5 for other 5/6 IS 2705 Ratings, 220 kV Switchyard Outdoor, oil immersed. 0.2 for revenue metering and 0.5 for other 5/6 IS 2705 Capacitor, outdoor, oil immersed 1.2 continuous 1.5 for 30 secs. Star 0.2 IS 3156 Capacitor, outdoor, oil immersed 1.2 continuous 1.5 for 30 secs. Star 0.2 IS 3156 Zinc oxide, gap less 360 kV 10 kA III A IEC – 99 Zinc oxide, gap less 198 kV 10 kA III A IEC – 99 2000A Two (2) for each line circuit. IEC 353 2000A Two (2) for each line circuit. IEC 353 IEC 481 IEC 481 Auxiliary Power Supply System Various auxiliaries will be supplied at the following nominal voltages depending upon their ratings and functions: a) 6600 V, 10%, 50 Hz 5%, 3 phase, 3 wire, non-effectively grounded AC supply for motors rated above 175 kW b) 415 V, 10%, 50 Hz 5%, 3 phase, 3 wire, solidly grounded AC supply for motors rated 175 kW and below and other L.T. services c) 240 V, 10%, 50 Hz 5%, 1 phase AC supply for lighting, space heating of motors and panels, single phase motors, etc. d) 220 V, ungrounded DC supply for protection, control and indication e) 220 V, 1 phase AC uninterruptible power supply for panel-mounted instruments, CRT units, printers, analysers, etc., forming a part of the plant instrumentation and control system. Unit Auxiliary Transformers (UAT) Two unit auxiliary transformer will be provided for the unit to feed auxiliary unit loads. This will be 16/20 MVA, 20 / 6.9 kV, 3 phase, 50 Hz, with + 5% off-circuit taps in steps of 2.5% on the HV side. The unit auxiliary transformers will be ONAN cooled with a vector group of Dyn11.The LV neutral will be earthed through a resistance loaded single phase transformer. VIMTA Labs Limited, Hyderabad 82 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Service Transformers The details of service transformers are indicated in table below: Unit Auxiliary Transformer / Service Transformers Sr. No Particulars Unit Auxiliary Transformer Unit Service Transformer Other Service Transformer 1 MVA rating 20 2.5 1.6 2 Type of cooling ONAN /ONAF ONAN ONAN 3 No load ratio 20 kV / 6.9 kV 6.6 kV / 433 V 6.6 kV / 433 V 4 Vector group Dyn 11 Dyn 11 Dyn 11 5 Type of changer Off load Off-circuit Off-circuit 6 Tap range & Steps. +/-5% in steps of 2.5% +/-5% in steps of 2.5% +/-5% in steps of 2.5% 7 Impulse withstand (1.2/50 micro-sec.) 125 kV peak / 60 kV peak 60 kV peak 60 kV peak 8 Power frequency withstand HV/LV 50 kV rms / 20 kV rms 20 kV rms / 3 kV rms 20 kV rms / 3 kV rms 9 Applicable standards voltage tap IS 2026 6.6 KV Switchgear Technical parameters of 6.6 kV switchgear are given in table below: 6.6 KV Switch Gear Sr. No. 1.0 1.1 1.2 1.3 1.4 1.5 2.0 2.1 2.2 2.3 2.4 2.5 2.6 3.0 3.1 3.2 4.0 4.1 Particulars Switch gear Nominal system voltage, phases & frequency System Neutral Earthing Power frequency with stand / impulse withstand (1.2 / 50 micro-sec). Short time withstand / dynamic rating Applicable standards Circuit breaker Type Operating duty Rated current Rated breaking / making current Short time rating Mechanism Contactors Type Application HRC Fuses Type VIMTA Labs Limited, Hyderabad Rating 6600 V, 3 Phase, 50 Hz Non-effectively earthed 27 kV rms / 60 kV peak. 40 kA for 1.0 sec / 100 kA peak. IS 3427 Vacuum / SF6, drawout type 0 – 3 min - CO-3 min-CO. As required 40 kA rms / 100 kA peak. 40 kA for 1.0 sec. Motor charged spring closing Vacuum For motors in CH & AH system Current limiting HRC fuses 83 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Sr. No. 4.2 4.3 4.4 Particulars Application Symmetrical Breaking capacity Applicable standards Rating Short-circuit protection of 6.6 kV motor feeders with vacuum contactors 40 kA rms IS 9224. 415 V System The technical particulars of 415V switch gear are as given in table below. 415 V SWITCH GEAR Sr. No. 1.0 1.1 1.2 1.3 Particulars 1.4 1.5 1.6 2.0 2.1 Switch gear & Bus bar rating Rated voltage/No. of phases/frequency System neutral earthing One minute power frequency withstand voltage (a) Power circuit (b) Control circuit (c) Aux. circuits connected to CTs Maximum allowable Temperature of Bus bars Short circuit withstand of Bus bars Dynamic rating of busbars Circuit breakers Type 2.2 2.3 Operating duty Rated breaking current / Making current 2.4 3.0 3.1 3.2 3.3 4.0 Short circuit withstand current Starters Type Contactor rated duty as per IS 2959 & IS 8544 Utilisation categories as per IS 2959 Applicable standards Rating 415V / 3 Ph / 50 Hz Solidly earthed 2500 V 1500 V 2000 V 900C 50 kA for 1 sec. 100 kA peak Air break, motor charged spring closing mechanism 0 – 3 min – CO-3 min – CO 50 kA at 415V AC & 0.25 pf / 84 kAP 50 kA for 1 sec. DOL & Reversible. Continuous & Intermittent AC 3 & AC 4 IS 2516 DC System The unit will be provided with a 1x100% capacity 220 V battery bank with associated 1x100% capacity chargers with separate float & boost units which will feed a DC switchboard. The incoming and outgoing feeder circuits in DC switchboard will be provided with switch-fuse units, which will have suitable supervisory devices against, fuse failure. Emergency Power Supply To enable the unit to shut down safely during complete A.C supply failure in the station, certain important plant auxiliaries will be provided with a reliable A.C power supply through a separate source. For this purpose, one (1) 415V quick starting diesel generator set with automatic mains failure (AMF) will be provided for the unit. The rating of the DG set will be 630 kVA. VIMTA Labs Limited, Hyderabad 84 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Un-Interruptible Power Supply System For panel-mounted instruments, CRTs, printers, analysers, recorder, etc., 220 V single phase A.C un-interruptible power supply will be made available. Generator And 400 KV Switchyard Protections And Control The details of the protections that will be provided for the various electrical equipment viz., Generator, generator transformer (GT), station transformers (ST), unit auxiliary transformer (UAT), service transformers, 400 kV switching equipment & transformers, 400 kV lines, motors, switch gear, etc., are indicated below. Generator Protections One generator relay panel (GRP) will be provided for the unit. This panel will be located in the unit control room. The following protection schemes will be provided in the GRP and the protections will be divided into two groups; each group being 100% redundant and on separate DC supply, so that even if one group of protections is not available or under maintenance, the generator is protected by the other group a) Generator differential protection (87G1) b) Generator stator 0 – 95% earth fault protection (64 GI) c) Generator stator earth fault (95 – 100%) protection (64G2) d) Generator back-up stator earth fault (0-95%) protection (64G3) e) Rotor earth fault protection (2 stage) (64F) f) Generator negative phase sequence protection (46GI & 46G2) g) Generator reverse power protection (32G1 & 32G2) h) Generator loss of excitation protection (40G1 & 40G2) i) Generator pole slipping protection (78G) & Directional pole slip unit 78G (32) j) Generator under frequency protection (81G & 81G2) k) Generator over-voltage protection (59G) l) Generator backup impedence protection (21G) m) Generator stator overload protection (50GS) n) Generator VT fuse failure protection (60G) o) Dead machine protection (61B) p) Generator field over-voltage protection (59F) q) Generator, Generator Transformer and Unit Auxiliary Transformers overfluxing protection (99G1 & 99G2) r) Stator Inter turn protection s) Over frequency protection Generator Transformer Protections The following protections will be provided for the Generator Transformer: a) Generator transformer HV winding restricted earth fault protection (64 GT) b) Generator, generator transformer and unit auxiliary transformers overall differential protection (870A) c) Generator transformer differential protection (87GT) d) Generator transformer over-current protection (51GT) e) Buchholz (63), winding temperature (49WT) and oil temperature (490T) protections f) Generator transformer pressure relief protection (63PTX) VIMTA Labs Limited, Hyderabad 85 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State g) Generator transformers fire protection trip Unit Auxiliary Transformer Protections The protections that will be provided for the unit auxiliary transformers: a) UAT differential protection (87UAT) and short circuit protection (50UAT) b) UAT back-up over current protection on HV and LV sides (51) c) Neutral displacement relay on LV side (64N2) d) Buchholz (63), winding temperature (49WT) and oil temperature (490T) protection e) UAT pressure relief protection (63PTX) f) UAT fire protection and trip (63 RTX) 6600 V / 433 V Service Transformer Protections The following protections will be provided for service transformers: a) Over current protection on HV and LV sides (51) and short circuit protection (50) on HV side b) Earth fault current protection on HV and LV sides (50N & 5IN). c) Buchholz (63), winding temperature (49WT) and oil temperature (490T) protections 400 KV Lines Protection The 400 kV lines will have the following protections: a) Distance protection (21-1) b) Distance protection (21-2) or Directional inverse time phase over current with high set unit (67 / 50) c) Fuse fail relay (FFR) for each secondary of CVT d) Directional inverse time earth fault protection (67N) e) Under voltage relays for live – line / dead bus and dead – line / live bus closing and safe grid establishment (27-1, 27-2, 27S) f) Fault locator (FL) g) Neutral impedance replica of distance relay (21NTR) h) Fault recorder (FR). 400 KV Bus Bar Protections Tuned high-impedance high-speed bus fault relay is proposed for detecting the fault on 400 kV buses. The bus bar protection scheme will have detecting elements for each of the main buses and one check zone element. The main and check zone elements will be connected to two different secondaries of CTs and tripping will be initiated only when respective bus element and check zone elements operate. Bus wire supervision relays to guard against faults in the CT secondary wiring and bus wire shorting relay to short CT secondary bus wires on fault are also proposed. Steel Plant Transformer Protections The Steel plant transformer bays will have the following protections: a) The transformer HV winding restricted earth fault protection (64) b) Transformer differential protection (87) VIMTA Labs Limited, Hyderabad 86 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State c) Transformer over-current protection (51) d) Buchholz (63), winding temperature (49WT) and oil temperature (490T) protections e) Transformer pressure relief protection (63PTX) f) Transformers fire protection trip Local Breaker Back-Up (50 LBB) All 400 kV circuit breakers including generator transformer breaker will be provided with local breaker back-up protection. For generator transformer breaker, an additional relay will be provided to detect breaker failure for ground and phase fault in the generator circuit and other low magnitude faults also. The local breaker back-up protection relay will be a triple pole over-current relay with high drop-off to pick-up ratio with fast acting feature. This will provide protection against stuck breaker condition for the 400 kV systems. This protection will be initiated by primary fault detecting relays and time delayed to permit the breaker to trip. Circuit Breaker Protection All the trip coils of the circuit breakers will be supervised. protections will also be included: a) Pole discrepancy protection b) Trip coil supervision relay for each trip coil (98L1 to L6). c) Anti pumping device for breaker closing (94). The following Protection Of 6.6 KV Motors All 6.6 kV motors will be provided with the following protections: a) Thermal overload protection b) Overload alarm protection c) Instantaneous over current protection d) Locked rotor protection e) Negative sequence protection f) Differential protection (For motor ratings of 1000 kW and above) g) Earth fault h) Bus under voltage i) Bearing temperature monitor j) Water flow monitor for CACW motors k) Lube oil pressure monitor l) Winding temperature monitor Protection Of 415 V Motors Motors rated below 100 kW will have bi-metallic relays for thermal overload protection and HRC fuses for short circuit protection. Motors rated 100 kW to 175 kW will be provided with locked rotor protection in addition to above. VIMTA Labs Limited, Hyderabad 87 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Power Supply And Lightning Circuits The power supply feeders will have properly rated HRC fuses for short-circuit protection. Lighting circuits will be protected by miniature circuit breakers. 400 kV / 220 kV Switchyard Control All breakers will be controlled from switchyard mimic control panels (SCP) located in main control room. All control operations like closing and opening of circuit breakers and isolators will be performed from the respective control panels. Discrepancy type control switches will be provided on the control panel. In addition to the control switches, the control panels shall consists of the following: a. b. c. d. e. Mimic of bay layout Metering Facia annunciation Indicating and monitoring lamps Synchronising facilities, etc. Cabling System Power cables would be selected based on the following criteria: a) Continuous circuit current rating b) De-rating factors for ambient temperature and grouping c) Short circuit rating of the circuit d) Voltage dip e) Standardisation of cable sizes to reduce inventory. Lighting System Suitable illumination necessary to facilitate normal operation and maintenance activities and to ensure safety of working personnel would be provided. Safety Earthing And Lightning Protection A safety earthing system comprising buried steel conductor earthing grid would be provided for the switchyard and other outlying areas. Communication System For effective communication in the plant, public address system, private automatic branch exchange system (EPABX), radio paging system and P&T telephone system will be provided. Fire Detection / Alarm And Fire Proof Sealing System A fire alarm system would be provided to facilitate visual and audible fire detection at the incipient stage of fire in the power station. VIMTA Labs Limited, Hyderabad 88 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Evacuation of Power The power generated from proposed 1x 300 MW captive plant would be connected to 400 KV switchyard and power will be evacuated to the steel plant through two Nos. of 210MVA 400/33KV transformers and through two numbers of 315 MVA - 400KV/220KV inter connecting transformers. Services, Utilities & Manpower Requirement General Besides raw materials i.e. coal, other major requirements of the plant are water, power and fuel. Water System The requirement of make-up for the proposed power plant (3X300 MW) is about 2250 m3/hr. The source of raw water would be clarified water from the existing steel plant. Water would be used for condenser cooling, cooling of Steam Generator & Turbine Generator auxiliaries and various other requirements like Steam Generator make-up, service and potable water. The water systems consist of various sub-systems are listed below: a) b) c) d) e) f) g) h) Raw water system Condenser cooling water (CW) system Make up water system Auxiliary cooling water (ACW) system Water treatment (WT) system Service & potable water system Fire protection system Effluent Reuse and Recycling System Clarified Water (CW) would be directly fed into the CW fore bay as make-up to CW System and a part of it to the Clarified Water Storage Tank (CWST) to meet the other water requirements of the plant like service water and fire protection system. CWST will be provided in 2 compartments with a common sump to facilitate cleaning and maintenance. CWST would be sized for storing water for plant service water requirements plus reserve storage for fire protection system. The CWST is a closed structure. The total plant make-up water requirement is summarised in table below. Plant Make-up Water Requirements Item Make-up water for condenser and other auxiliaries Plant service water and fire water make- up For DM plant input Air washer make-up & misc. Plant potable water Net amount of water required VIMTA Labs Limited, Hyderabad Estimated Qty (m3/hr) 2010 Quality Clarified water 54 Clarified water 78 105 3 2250 Filtered water 89 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Clarified Water Chemical Dosing System About 1.5% of the total CW flow is considered to be treated through side stream filters. Water to these filters will be fed directly from the discharge of CW pump header. The treated water from side stream filters is fed back to the CW fore bay. Backwash for the filters is from the CW header itself. The back wash effluent from the back wash filters would be led to the cooling pond. Chemical dosing system would comprise of chemicals with anti-scalant / anticorrosive and dispersant properties. For each type of chemical the dosing system would consist of 2 x 100% dosing pumps with PP / SS material of construction with one dosing tank. Acid dosing system with 1 No. bulk acid storage tank and dosing pumps would be provided to control the alkalinity in the system. To prevent / control algae growth in the CW system, chlorine dosing would be provided. 1x100% capacity evaporator type chlorinator of capacity 60 kg/hr would be provided to dose chlorine in the CW system. 5 chlorine cylinders, each of 1 tonne capacity would be provided to cater to about 8 days of chlorine demand. Chlorinator system proposed for this unit will be located in the separate chlorination room. Continuous dosing would be done at the rate of 1 ppm and shock dosing would be done at a rate of 3 ppm. Chlorine leak detection and absorption system would be provided to trap chlorine leakages from chlorine tonners. Water Treatment Plant The water treatment plant broadly consists of a filtration plant, DM plant and an Ultra Filtration plant. The Filtration plant consists of pressure sand filter of capacity 2 x 70 m 3 / hr, to remove turbidity and suspended solids. Alum would be dosed at the inlet to filters to aid filtration process. Demineralisation (DM) Plant The Demineralisation (DM) plant meets the requirement of steam boiler (SB) feed water make-up and Auxiliary Cooling Water (ACW) system make-up. From DM water storage tank, three (3) nos. of DM water transfer pumps will cater to the DM water transfer requirements of all the units. The condensate storage tank would be sized to meet maximum requirement of DM water when the unit is under start-up. Service and Potable Water Systems The service water system supplies water required for air washer system and miscellaneous services like cleaning, washing etc. One (1) no. service water pump would pump water from the CWST to a service water overhead tank. This tank will be located on the de-aerator floor from where further distribution to other customers will be gravity. For distribution to the boiler platforms at higher elevations, 2 x 100% capacity service water booster pumps will be provided. Requirements of the plant potable water system would be met from the filtered water storage tank. A tap off will be provided to a potable water overhead tank located de-aerator floor from where further distribution to other customers in the plant will be gravity. VIMTA Labs Limited, Hyderabad 90 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Chemical Laboratory Equipment The existing quality control laboratory, with modern equipment, shall be utilized for the proposed Captive Power Plant. The main functions of the laboratory will be to analysis the coal, water and steam samples from the plant. Fire Protection System Fire protection system would be provided covering all the buildings of the proposed power plant boundary. The water would be drawn from the CWST in which a reserve storage capacity will be earmarked for the system. The following fire protection systems are proposed: a) Hydrant system b) Automatic High Velocity Water Spray (HVWS) system for the protection of transformers and manual HVWS system for the protection of turbine oil tanks. c) Automatic Deluge/ Medium Velocity Water Spray (MVWS) system for the protection of cable vaults and overhead conveyors. d) Heavy duty portable or trolley mounted fire extinguishers for the protection of control rooms. e) Portable fire extinguishers for different areas. Adequate number of pumps will be provided and system would be designed to conform to the rules and regulations of fire safety standards as per TAC. Power System The total annual power consumption for the 300 MW Captive Power Plant is 28 MW considering 8% auxiliary power consumption. The power generated from proposed 300 MW captive power plant would be connected to 400 KV switchyard and power will be evacuated to the Steel Plant through transformers. The loads will be segregated as unit loads and common service loads. The unit auxiliary loads will be supplied through unit auxiliary transformers connected directly to the generator through isolated phase bus ducts. Start-up for the auxiliaries will be supplied through station transformer with GT breaker kept open. Once the unit is started and the generator picks up rated speed & voltage, GT breaker is closed after synchronising with grid. Tie feeder will be provided from 6.6 kV station switch gear to 6.6 kV unit switch gears of the unit so that during non availability of one unit auxiliary transformer, the station transformer will feed the loads connected to that unit auxiliary transformer. An uninterrupted power supply (UPS) system would be provided to cater to 220V AC, single phase, 50 Hz, 2 wire power supply requirements of instrumentation and control systems viz. man-machine interface equipment, analysers, receiver instruments, Closed loop controls, sequence controls, protection and interlock system, annunciation system and sequence of events recording system. To enable the unit to shutdown safely during complete A.C supply failure in the station, certain important plant auxiliaries will be provided with a reliable A.C power supply through a separate source. For this purpose, one (1) 415V quick starting diesel generator set with automatic mains failure (AMF) will be provided for the unit. The rating of the DG set will be 630 kVA. VIMTA Labs Limited, Hyderabad 91 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State The diesel generator will feed an emergency 415V switch gear, to which all the essential loads such as the A.C emergency bearing lube oil and seal oil pumps, turning gear motor, battery chargers, emergency lights, and essential instrument power supply feeders will be connected. When the station A.C supply is healthy, the emergency switchgear will be fed from the unit service switchgear. When the station A.C supply fails, the DG set will start automatically and will feed the loads connected to the emergency switchgear. When the normal A.C supply is restored, these essential loads will be manually changed over to the normal power supply. Instrumentation and Control System The Automation, Instrumentation and Control System (I&C) shall be sufficient to monitor and control all significant variables in accordance with the process requirement, provide all operating requirements and necessary sequencing, interlocking and safety functions including alarms for abnormal conditions of the proposed Captive Power Plant. Process Automation System The automation system for process control and monitoring will be based on a modern Distributed Control System latest version (hereafter referred to as DCS). The DCS system structure is based on an integrated distribution system with inherent open type architecture. The system will have mainly two functional levels. Communication System The existing telephone system will cater the requirement of the communication inside as well as outside the power plant. Repair and Maintenance Facilities The existing steel plant repair and maintenance facilities will take care of routine repair and periodical maintenance work of the captive power plant. Major repairing works involving machining, fabrication and assembly of heavy and critical jobs of specialized nature are envisaged to be contracted to outside agencies. Warehouse The existing warehouse will be utilised to keep spares of equipment, hardwares and consumables. A Part of the building will be utilised for easy manual loading and unloading of the materials from trucks. Forklifts will be used for movement of materials inside the stores building. Ancillary Facilities Existing ancillary facilities such as administrative building, canteen, car park, cycle and scooter stand, first-aid station etc. shall take care of the proposed plant manpower. Drainage and Sewerage System Open type drain has been envisaged for the plant storm water drainage. The drains will be laid generally by the side of the roads. Storm water run-off, collected through arterial and trunk drain, will be discharged suitably for minimum pollution. VIMTA Labs Limited, Hyderabad 92 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Sanitary faecal sewage will be collected from the ablution blocks through pipeline and the same will be connected to a sewage treatment plant. The effluent from the sewage treatment plant will be utilized for the development and maintenance of greenery Roads Adequate plant road system will be provided. The road system will be integrated with the existing roads. Ash Handling System Ash formed due to combustion of pulverized coal in the steam generator will be collected as bottom ash in the bottom ash hopper, coarse ash in economizer APH and duct hoppers and fly ash in ESP and stack hoppers. Bottom ash will be collected in the water impounded bottom ash hopper and conveyed to ash slurry sump through jet pumps. The ash slurry conveyed to ash slurry sump will be further conveyed to ash disposal area by means of ash slurry pumps. Coarse ash will be automatically extracted and conveyed to the feeder ejectors located below each hopper. Necessary vacuum/momentum required for extracting the ash from the hoppers shall be created by the feeder ejectors. The coarse ash slurry thus produced shall be routed to coarse ash tank located in boiler area. The slurry collected in the coarse ash tank shall be conveyed to the proposed ash slurry sump through coarse ash slurry pumps. The fly ash from electrostatic precipitator and stack hoppers will be extracted through vacuum and conveyed to fly ash silos through pressure conveying system. The fly ash will be further disposed in dry form through trucks or in wet form to ash disposal area through HCSD system. Bottom Ash Handling System Bottom Ash (BA) will be collected continuously in a W-shaped, water impounded, storage type, water cooled refractory lined, bottom ash hopper. BA hopper will be located directly below the bottom water wall header of boiler and will have an effective storage capacity of 8 hours bottom ash and coarse ash generated while firing worst coal. The bottom ash of unit collected in BA hopper will be removed in two (2) hours once in a shift of 8 hours. To unload contents of the BA hopper, its feed gates will be opened by a remotely controlled/ operated four way solenoid valve and air water converter unit. It will be ensured that full quantity of ash slurry is removed during de-ashing cycle. BA hopper will consist of two sections; each section provided with two clinker grinders with electric drives installed directly below the feed gate assembly to limit the size of clinkers to maximum 25 mm. Out of two clinker grinders provided for each V section of BA hopper, one grinder will operate while the other will be standby. Operation of the grinder motor will be electrically interlocked with the grinder seal water pressure, jet pump water pressure and BA disposal line discharge pressure. The slurry (mixture of bottom ash and water) from the clinker grinder will be conveyed to ash slurry sump by jet pumps through cast iron to IS 1536 Class D. Bottom Ash hopper overflow will be routed through overflow seal box to a drain sump. The contents of this drain sump will be discharged to ash slurry system clarifier. VIMTA Labs Limited, Hyderabad 93 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Coarse Ash Handling System Coarse ash will be automatically extracted and conveyed to the feeder ejectors located below each hopper. Necessary vacuum/momentum required for extracting the ash from the hoppers shall be created by the feeder ejectors. The coarse ash slurry thus produced shall be routed to coarse ash tank located in boiler area. The slurry collected in the coarse ash tank shall be conveyed to the proposed ash slurry sump through coarse ash slurry pumps. The water required for feeder ejectors will be drawn from HP Water Pumps. The coarse ash slurry collected in the coarse tank will be removed in 45 minutes once in a shift of 8 hours. Fly Ash Handling System Fly ash collected in various ESP and stack hoppers will be extracted and conveyed to buffer hoppers automatically and sequentially by means of vacuum generated by mechanical exhauster and will be transported to fly ash silos by means of pressure conveying system. Adequately rated oil free rotary screw type Conveying Air Compressors will be provided to supply compressed air required for conveying fly ash from buffer hoppers to fly ash silos. One (1) buffer hopper will be provided for each vacuum stream. Adequately sized bag filters will be mounted on buffer hopper. Four (4) streams are proposed for evacuating the fly ash from fly ash hoppers to fly ash silos. Below each buffer hopper, two ash vessels will be provided to convey ash to fly ash silos. One (1) fly ash storage silo in RCC construction will be provided, each having an effective storage capacity of storing 16 hours. Fly ash silo will be provided with four outlets; one for unloading ash in dry form into closed trucks through telescopic chute; one for unloading ash in conditioned form into open trucks through ash conditioner, one for unloading ash to mixing tanks and fourth outlet blind flanged for future use. Fly ash storage silo will be provided with adequately rated vent filter on silo roof. The silo will be located adjacent to the existing silos. Two (2) adequately rated low speed, oil free, lobe type fluidizing air blowers with heaters will be provided for fluidizing ESP Hoppers. Two adequately rated low speed, oil free, lobe type fluidizing air blowers with heaters will be provided for fly ash silo; one working and one standby. Two adequately rated oil free screw compressors with refrigerant type air driers and air receivers will be provided for supplying instrument air for various valves and cleaning of pulse jet type bag filters. Ash Disposal System The bottom and coarse ash slurry collected in the ash slurry sump will be pumped to ash disposal area. Two (2) ash slurry pumps with associated pipes and valves will be installed to dispose ash slurry to the ash disposal area. Existing ash water recovery system will be used for recovering the decanted water for re-use in ash disposal system. Out of the two series, one series will normally operate and other will be standby. VIMTA Labs Limited, Hyderabad 94 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Fly Ash Slurry Disposal System The ash from fly ash silos will be fed by rotary feeders and ash conditioners into the slurry mixing tank, the level of which will be controlled. The conditioned dry fly ash will be wetted out by water to be added in the mixing tank and the entire ash will blended to a uniform consistency by mixer. One mixing tank and one (1) ash slurry pump (HCSD type) will be provided for fly ash silo. Each slurry pump discharge piping will be provided up to the disposal area with all necessary isolation valves, line flushing valves etc. The ash slurry pump will be suitably designed for high concentration slurry disposal (HCSD) system and necessary pulsation dampeners/accumulator immediately after slurry pump discharge and/or on discharge lines. The mixing tank will be sufficiently large to provide a reasonable residence time so that short terms fluctuations in concentration can largely be blended out. The ash mixing and pumping process will operate in cyclic mode and automatically dispose of ash so as to accommodate changes in ash production caused by fluctuating boiler loads or other variables. Ash disposal pipelines will be installed above ground with flange joints wherever necessary and it will suit the maximum pressure encountered in the pipeline or otherwise pipelines will be welded. The ash slurry disposal will be designed for 6570% concentration (solids by weight). The disposal area will be filled in such a way that the deposits can reach the required height within the area and suitable the engineering of the ash pond will be done. 23.7 Environmental Management The proposed plant would result in air, water and land pollution of varying nature and degree. The following sections briefly outlines the nature and sources of pollution and also suggests broad environmental protection measures to be adopted for limiting pollution within permissible levels. Nature of Pollution The inputs to the Power Plant will comprise raw materials i.e. coal along with water, fuel and power. These would therefore lead to release of emissions to the air, generation of wastewater and solid wastes. The Process would not be generating any Hazardous Waste, as there is no Hazardous Chemical involved in the process. The sources of pollution from the proposed project and the types of environmental pollution likely to occur are summarized as below. Section / Units Materials Operation Pollutants Recipient Form of Pollution Air Pollution Air Pollution Coal conveyors/Transfer Coal Conveying Dust Air Coal mill Coal Crushing Dust Air Flue gas Combustion of coal and steam generation Dust , SO2, NOx Air Air pollution Ash handling Dust Work zone Air pollution Discharges Thermal pollution Water environment Water pollution Stack emissions Bottom and fly ash Ash handling Boiler section cooling water and Boiler blow downs/cooling VIMTA Labs Limited, Hyderabad 95 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State tower blow down DM plant Acids / alkalies Plant operation Spent regenerate --- --- H2SO4 and NaOH Noise, Heat Water environment Work zone Water pollution Noise pollution and thermal stress Pollution Prevention and Control Measures In consideration of the above stated pollution potential of the power plant, the following mitigation schemes are envisaged in order to control environmental pollution within the permissible norms and keep the environment fairly clean. Ambient Air Quality Stations will be installed for monitoring the continuous Ambient Air Quality based on meteorological conditions, wind direction pattern, etc. for measurement of following parameters in the ambient air. • • • • • • Suspended Particulate Matter Respirable Particulate Matter SO2 NOx CO2 CO Provision for checking Ambient Air Quality outside the plant boundary will also be made. High volume samplers with attachments for gaseous sampling and particulate matter sampler will be envisaged for this purpose. Air Environment Protection The air polluting emission from the power plant are as follows: Dust particulates from fly ash in flue gas Sulphur dioxide (SO2) in flue gas Nitrogen oxides (NOx) in flue gas Coal dust particles due to handling of coal Fly ash dust particles from ash silos and ash disposal area Dust particulates from Fly Ash in Flue Gas The standard for particulate emission applicable to this project is 50 mg/ Nm3. The electrostatic precipitators (ESP) proposed to be installed in this project would be designed to limit the emission level of the particulate matter to 50 mg/N m3. Sulphur dioxide (SO2) in Flue Gas One stack (chimney) of height 275 M is proposed to be constructed. Nitrogen oxides (NOx) in Flue Gas To reduce NOx emissions, over-fire air system equipment with air ports would be installed for the furnace. Further, the steam generators would be fitted with VIMTA Labs Limited, Hyderabad 96 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State advanced low NOx burners. The NOx emissions would be checked for ground level concentrations (GLC) as per the above indicated Indian Emission Regulations. Coal dust particles due to handling of coal Coal dust would be generated generally at the conveyor transfer points. Hence, coal transfer points would be provided with dust suppression / dust extraction facilities. Further, in order to arrest the coal dust generation, all conveyors would be provided with enclosed galleries. Dust collection system would also be provided in coal bunkers to evacuate dust from the coal bunkers. Collected dust would be returned to either the associated belt conveyor or to the coal bunker. The dust collector outlet emission would be restricted to 50 mg/Nm³. Fly ash dust particles from ash silos and ash disposal area One fly ash storage silo for the unit is proposed to be provided. Fly ash evacuated from the ESP collecting hoppers would be transported in closed pipe lines by pneumatic means. At the time of unloading fly ash in to the silo, some ash laden air would get vented out. In order to restrict the fly ash dust particles to the limits of 50 mg/Nm3, a vent filter would be installed on top of the fly ash silo at the vents. The following pollution control measures would be installed for ash disposal: a) To reduce the dust nuisance while loading the ash into the trucks from fly ash silo, the fly ash would be conditioned with water spray. b) It is proposed to cover the ash in the open trucks with tarpaulin to prevent flying of fine ash during transportation. c) Water sprinkling system would be provided in the ash disposal area to restrain flying of fine ash due to wind. d) The ash disposal area would be lined with impervious lining to prevent seepage of rain water from the disposal area in to the ground and pollute ground water Noise environment protection The plant is expected to increase the noise level in the surrounding due to operation of plant and machinery. The main sources of noise in a power plant are: Steam turbine generator Other rotating equipment Combustion induced noises Flow induced noises Steam safety valves Necessary noise control and abatement measurers will be adopted to minimize the noise level from the plant during construction and operation phase to a maximum of 85 db (A) as per the requirement of OSHA (Occupational Safety and Health Administration) Standards. All rotary equipment like fans, blowers, pumps & compressors would be of low noise design. The grouting of these equipment’s will be made free from vibrations. Noise absorbing cladding around drying ball mill will be provided to reduce the noise level. VIMTA Labs Limited, Hyderabad 97 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State The work zone noise exposure of the operating personnel would be avoided by remote operation from the control rooms by using required safety equipments. Water Environment Protection The water pollutants are: Cooling tower blow down water Boiler blow down water Water treatment plant effluent Effluent from Bottom ash handling system Air pre-heater wash water effluent Plant wash down water Floor and Equipment drainage effluent Rain water drainage Sewage from various buildings in the plant The cooling tower blow down water would be used for ash handling system purposes and the excess blow down would be led to the existing cooling pond. The boiler blow down does not require treatment to achieve the limits but relies on operating at sufficient blow down levels to prevent the build-up of contaminants. The boiler blow down is also directed to the existing cooling pond. The effluent from the regeneration of the cation resin units in the water treatment plant (DM Plant) are generally acidic in nature and from the anion resin units are alkaline in nature. The combined wastewater from the DM plant would be neutralised in an existing neutralising pit. The neutralised effluent is expected to have suspended solids less than 5 ppm and pH in the range of 6.5 to 8.5. This would also be led to the existing cooling pond. The drain and overflow water from the bottom ash handling system would be collected at the bottom ash sump where the ash would be settled and clarified ash water overflows to clear well section of the basin. This would be sent to the existing cooling pond. Frequently, the air pre heaters of the boilers need to be washed. The washed water would be led to the nearest drains. These drains would also be led to the existing cooling pond. In the power plant, some specific locations require washing to maintain good plant housekeeping and prevent build-up of dirt and waste material. The waste water would be led to the bottom ash sump. The function of this system is to provide a means for collecting and draining water from floors in process areas of the plant and collecting and disposing of water and other liquids from process equipment, discharged fire protection water and oil storage tanks. In the turbine building, the ground floor slabs would be sloped to drain out floor drains. The equipment drains are piped directly to the drain system. Drains are collected and directed to the sumps inside the buildings from where it would be pumped to the oil – water separator. Oily effluent if any would be collected and disposed while clear water would be led to drains. The rain (storm) water removed from the building roofs and yard area grade level VIMTA Labs Limited, Hyderabad 98 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State surfaces would be directed through the open ditches and culverts to the storm drainage piping. All drain would be concrete lined and located along the roads. All drainage ditches would be located to provide the shortest practical drainage path while providing efficient drainage for the yard. Grade level would be contoured such that storm water runoff is directed on the ground by sheet flow, to well defined drainage paths leading to the ditches. Sewage from various buildings in the power plant area would be conveyed through separate drains to septic tanks. The effluent from septic tanks would be disposed off in the soil by providing dispersion trenches. There would be no ground pollution because of leaching. Sludge shall have to be removed and disposed off in landfill. The waste water generated from the indirect cooling circuit would be routed through the cooling tower and pressure filter for recycling purpose. The plant sanitary wastewater will be treated in sewage treatment plant and the treated whole water will be used for dust suppression and maintenance of plant green belt. Solid Waste 1. During construction phase, solid waste such as excavated soil, debris, some metal waste and very small amount of oil & grease from construction machines will be generated. This waste may contaminate soil at plant site temporarily and would be restricted to a small area. 2. Used/Spent oil and grease will be generated during maintenance of equipment and machine. 3. Solid waste consisting of coal fine particles, fly ash and bottom ash will be generated in the plant. Coal fine particles will be reused in the plant, fly ash will be sold to the cement plant. Fly Ash Utilisation The main solid waste from the CPP will be the ash (fly ash and bottom ash). The total ash generation will be about 0.75 MTPA. Out of this, the bottom ash will be about 0.15 MTPA (20% of the total ash) and the balance fly ash will be 0.6 MTPA. It is proposed to sell the entire quantity of fly ash to external companies for cement/brick manufacturing. The following activities will be carried out to comply as per the new fly ash notification, S.O. 2623 (E) dated on 6 th November 2008 issued by MoEF. • • • • The bottom ash will be stored in properly designed ash dykes as per CPCB guidelines to prevent leaching to the sub-soil and underground aquifer; The ash disposal area will be lined with HDPE/LDPE impervious lining to prevent seepage of rain water from the disposal area in the ground and pollute ground water; Shall maintain a record of all sale and/ or disposal of the fly ash; and Shall submit annual compliance report including record of sale and/or disposal of the fly ash. VIMTA Labs Limited, Hyderabad 99 Additional Details for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State Plant Safety Plant safety measures would form an integral part of the environment protection plan of the proposed plant. Workers’ safety would be of highest degree of concern so as to avoid any form of personal injury or untoward accident. In-build safety features of the plant and machinery would be made adequate in order to avoid hazardous events causing damage to the life and property. Efforts would be made to afford the best safety measures and health services with a view to keep the workplace free of hazards to the extent possible. Standard programs will be framed and followed for regular medical check-up, lung function test, audiometry, vision test, etc. for the workers on a regular basis so as to prevent and to detect occupational diseases and to promote their general well-being. Greenbelt and Landscaping Adequate space would be reserved for gardening and tree plantations at the site. This would improve the plant aesthetics as well as prevent the fugitive dust emissions. Unpaved areas, if any, within the plant boundary would be provided with grass cover. This would not only act as ‘lung space’ but would also improve the plant aesthetics. ------------------------------------------------------------------------------------------24.0 COMMITMENT TO ACHIEVE ZERO EFFLUENT DISCHARGE IN COKE OVEN AND BF TO BE PROVIDED. JSW will make all efforts to attain Zero Effluent Discharge in coke oven and blast furnace units in phases. -------------------------------------------------------------------------------------**** VIMTA Labs Limited, Hyderabad 100 Annexure-II Stack Emission Calculations Final Sr. No. Plant Name Pellet Plant 1 Pellet Plant-1 2 Pellet Plant-1 3 Pellet Plant-2 4 Pellet Plant-2 Sinter Plant 1 Sinter Plant-1A 2 Sinter Plant-1A 3 Sinter Plant-1A+B 4 Sinter Plant-1B 5 Sinter Plant-1B 6 Sinter Plant-2A 7 Sinter Plant-2A 8 Sinter Plant-2A+B 9 Sinter Plant-2B 10 Sinter Plant-2B DR Plant 1 DR Plant-1 2 DR Plant-1 3 DR Plant-1 Blast Furnace 1 Blast Furnace-1 2 Blast Furnace-1 3 Blast Furnace-1 4 Blast Furnace-1 5 Blast Furnace-2 6 Blast Furnace-2 7 Blast Furnace-2 8 Blast Furnace-2 Coke Oven 1 Coke Oven-1 2 Coke Oven-1 3 Coke Oven-1 4 Coke Oven-1 5 Coke Oven-1 6 Coke Oven-2 7 Coke Oven-2 8 Coke Oven-2 9 Coke Oven-2 10 Coke Oven-2 Steel Melting Shop 1 SMS-1 2 SMS-1 3 SMS-1 4 SMS-1 5 SMS-1 6 SMS-1 7 SMS-2 8 SMS-2 9 SMS-2 10 SMS-2 11 SMS-2 Reheating Furance 1 HSM 2 Wire Rod Mill 3 Bar Mill 4 Medium Section Mill 5 Heavy Section Mill-1 6 Heavy Section Mill-2 7 Plate Mill 8 Tin Plate Mill Stack attached to Pollution Control Equipment Final Norms Norms Norms Emission Rate Emission Rate Emission Rate Nox Height Dia. Temp. Velocity Temp. Correction Flow rate PM SO2 Nox PM SO2 m m oC m/s oC Nm3/hr mg/Nm3 mg/Nm3 mg/Nm3 g/s g/s g/s Pellet ESP Machine Discharge Pellet ESP Machine Discharge ESP Bag Filter ESP Bag Filter 100 30 100 30 5 1.5 5 1.5 115 45 115 45 27.63 18.66 27.63 18.66 0.77 0.94 0.77 0.94 15,00,000.0 1,11,220.0 15,00,000.0 1,11,220.0 50 50 50 50 30 30 - 140 140 - 20.83 1.54 20.83 1.54 12.5 12.5 - 58.3 58.3 - Sinter Machine Dedusting Sinter Storage Dedusting Sinter Machine Dedusting Sinter Machine Dedusting Sinter Storage Dedusting Sinter Machine Dedusting ESP Bag Filter Bag Filter ESP Bag Filter ESP Bag Filter Bag Filter ESP Bag Filter 130 65 65 130 65 130 65 65 130 65 7.7 4.5 4 7.7 4.5 7.7 4.5 4 7.7 4.5 190 60 30 190 60 190 60 30 190 60 20.15 7.73 4.45 20.15 7.73 20.15 7.73 4.45 20.15 7.73 0.64 0.89 0.98 0.64 0.89 0.64 0.89 0.98 0.64 0.89 21,74,400.0 3,96,000.0 1,98,000.0 21,74,400.0 3,96,000.0 21,74,400.0 3,96,000.0 1,98,000.0 21,74,400.0 3,96,000.0 50 50 50 50 50 50 50 50 50 50 150 150 150 150 - 150 150 150 150 - 30.20 5.50 2.75 30.20 5.50 30.20 5.50 2.75 30.20 5.50 90.6 90.6 90.6 90.6 - 90.6 90.6 90.6 90.6 - Flue gas ejector Reduction Furnace Product Silo Dust Collector Reformer Bag Filter 40 30 30 4.5 0.9 0.9 180 65 55 32.60 10.68 12.69 0.66 0.88 0.91 12,28,034.0 21,562.0 26,411.0 1.48 47.67 40.32 - 281 21 - 0.50 0.29 0.30 - 95.9 0.1 - Stove Casthouse East Casthouse West Stockhouse Stove Casthouse East Casthouse West Stockhouse ESP Bag Filter Bag Filter Bag Filter ESP Bag Filter Bag Filter Bag Filter 60 40 40 40 60 40 40 40 3.5 5 5 3.5 3.5 5 5 3.5 200 40 40 40 200 40 40 40 20.62 24.52 24.52 19.71 20.62 24.52 24.52 19.71 0.63 0.95 0.95 0.95 0.63 0.95 0.95 0.95 4,50,000.0 16,50,000.0 16,50,000.0 6,50,000.0 4,50,000.0 16,50,000.0 16,50,000.0 6,50,000.0 30 30 30 30 30 30 30 30 30 30 - 50 50 - 3.75 13.75 13.75 5.42 3.75 13.75 13.75 5.42 3.8 3.8 - 6.3 6.3 - Coke Oven Battery-1&2 Coke Oven Battery-3&4 CO Pushing Emission-1 CO Pushing Emission-2 Ammonia Cracker-1 Coke Oven Battery-1&2 Coke Oven Battery-3&4 CO Pushing Emission-1 CO Pushing Emission-2 Ammonia Cracker-1 ESP ESP Bag Filter Bag Filter ESP ESP ESP Bag Filter Bag Filter ESP 165 165 40 40 50 165 165 40 40 50 4.2 4.2 3 3 2 4.2 4.2 3 3 2 200 200 55 55 150 200 200 55 55 150 11.93 11.93 20.76 20.76 15.06 11.93 11.93 20.76 20.76 15.06 0.63 0.63 0.91 0.91 0.70 0.63 0.63 0.91 0.91 0.70 3,75,000.0 3,75,000.0 4,80,000.0 4,80,000.0 1,20,000.0 3,75,000.0 3,75,000.0 4,80,000.0 4,80,000.0 1,20,000.0 50 50 50 50 50 50 50 50 - 400 400 60 60 400 400 60 60 - 350 350 50 50 350 350 50 50 - 5.21 5.21 6.67 6.67 5.21 5.21 6.67 6.67 - 41.7 41.7 8.0 8.0 41.7 41.7 8.0 8.0 - 36.5 36.5 6.67 6.67 36.5 36.5 6.67 6.67 - BOF-1 BOF-2 BOF-3 Fume Extraction System LHF - 3 Nos. RH - 1 BOF-1 BOF-2 Fume Extraction System LHF - 2 Nos. RH - 1 ESP ESP ESP Bag Filter Bag Filter Bag Filter ESP ESP Bag Filter Bag Filter Bag Filter 60 60 60 40 60 30 60 60 40 60 30 2 2 2 5.5 3 0.6 2.5 2.5 5.5 3 0.8 60 60 60 60 50 60 60 60 60 50 60 14.82 14.82 14.82 20.90 12.78 10.98 15.81 15.81 20.90 12.78 12.35 0.89 0.89 0.89 0.89 0.92 0.89 0.89 0.89 0.89 0.92 0.89 1,50,000.0 1,50,000.0 1,50,000.0 16,00,000.0 3,00,000.0 10,000.0 2,50,000.0 2,50,000.0 16,00,000.0 3,00,000.0 20,000.0 50 50 50 30 30 30 50 50 30 30 30 100 100 100 100 100 - 200 200 200 200 200 - 2.08 2.08 2.08 13.33 2.50 0.08 3.47 3.47 13.33 2.50 0.17 4.17 4.17 4.17 6.94 6.94 - 8.33 8.33 8.33 13.89 13.89 - Reheating Furnace-3 Nos. Reheating Furnace Reheating Furnace Reheating Furnace Reheating Furnace Reheating Furnace Reheating Furnace Reheating Furnace ESP ESP ESP ESP ESP ESP Bag Filter Bag Filter 100 80 80 80 80 80 65 47 4.2 3 3 3 3 3 4.5 1.5 293 318 318 325 320 320 300 150 9.52 5.85 5.85 7.10 6.26 6.26 5.04 22.31 0.53 0.50 0.50 0.50 0.50 0.50 0.52 0.70 2,50,000.0 75,000.0 75,000.0 90,000.0 80,000.0 80,000.0 1,50,000.0 1,00,000.0 30 30 30 30 30 30 15 40 50 50 50 50 50 50 50 40 100 100 100 100 100 100 150 70 2.08 0.63 0.63 0.75 0.67 0.67 0.63 1.11 3.5 1.0 1.0 1.3 1.1 1.1 2.1 1.1 6.94 2.08 2.08 2.50 2.22 2.22 6.3 1.9 Annexure-II Stack Emission Calculations Cold Rolling Mill 1 Cold Rolling Mill 2 Cold Rolling Mill 3 Galvanizing Line 4 Colour Coating Line 5 Electrical Steel Lime Plant 1 Lime Plant-1 2 Lime Plant-2 3 Lime Plant-3 4 Lime Plant-4 5 Lime Plant-5 Dolo Plant 1 Dolo Plant-1 2 Dolo Plant-2 Cement Plant 1 Slag Cement Plant 2 Raw mill/Kiln 3 Cement Mill 4 coal mill 5 cooler 6 Packer-I 7 Packer-II 8 Packer-III Captive Power Plant 1 Power Plant-1 2 Power Plant-2 3 Power Plant-3 Incinerator 1 Incinerator-1 2 Incinerator-2 Pickling Line Annealing Furnace Annealing Furnace CCL HDGL Stack Bag Filter Bag Filter Bag Filter Bag Filter Bag Filter 30 40 40 40 65 1.2 1.5 1.5 1 2 45 120 120 40 150 9.44 9.54 4.15 18.57 12.55 0.94 0.76 0.76 0.95 0.70 36,000.0 46,000.0 20,000.0 50,000.0 1,00,000.0 25 40 40 50 40 40 20 80 80 40 0.25 0.51 0.22 1.39 0.5 0.2 0.6 1.0 0.4 1.1 Kiln Kiln Kiln Kiln Kiln Bag Filter Bag Filter Bag Filter Bag Filter Bag Filter 55 55 55 55 55 2 2 2 2 2 130 130 130 130 130 14.35 14.35 14.35 14.35 14.35 0.74 0.74 0.74 0.74 0.74 1,20,000.0 1,20,000.0 1,20,000.0 1,20,000.0 1,20,000.0 30 30 30 30 30 9 9 9 9 9 5 5 5 5 5 1.00 1.00 1.00 1.00 1.00 0.30 0.30 0.30 0.30 0.30 0.17 0.17 0.17 0.17 0.17 Kiln Kiln Bag Filter Bag Filter 55 55 2 2 130 130 14.35 14.35 0.74 0.74 1,20,000.0 1,20,000.0 30 30 9 9 5 5 1.00 1.00 0.30 0.30 0.17 0.17 ESP ESP/Bag House ESP/Bag House ESP/Bag House ESP/Bag House ESP/Bag House ESP/Bag House ESP/Bag House 40 100 35 62 62 30 30 30 1.5 5 1.4 2.3 4.5 0.8 0.8 0.8 60 140 90 40 230 40 40 40 10.54 15.00 7.00 7.00 12.00 7.00 7.00 7.00 0.89 0.72 0.82 0.95 0.59 0.95 0.95 0.95 60,000.0 212.0 8.8 27.6 112.6 3.3 3.3 3.3 50 50 50 50 50 50 50 50 - 750 0.83 10.60 0.44 1.38 5.63 0.17 0.17 0.17 69.4 - 159.00 - CPP-1 CPP-2 CPP-3 ESP ESP ESP 275 275 275 5.5 5.5 5.5 150 150 150 24.89 24.89 24.89 0.70 0.70 0.70 15,00,000.0 15,00,000.0 15,00,000.0 100 100 100 1,200 1,200 1,200 800 800 800 41.67 41.67 41.67 500.0 500.0 500.0 333.3 333.3 333.3 Incinerator-1 Incinerator-2 ESP ESP 30 30 0.5 0.5 50 50 9.20 9.20 0.92 0.92 6,000.0 6,000.0 50 50 120 120 200 200 0.08 0.08 0.20 0.20 0.33 0.33 SCP Kiln Cement mill coal mill cooler cooler Packer i Packer ii Packer iii