International Journal of Advances in Engineering & Technology, Nov. 2013. ©IJAET ISSN: 22311963 IMPROVED TRANSMISSION LINE CONTINGENCY ANALYSIS IN POWER SYSTEM USING FAST DECOUPLED LOAD FLOW Amit Kumar Roy1, Sanjay Kumar Jain2 Asst.Professor, Department of Electrical Engineering, JSS Academy of Technical Education, Noida, India 2 Associate Professor, Department of Electrical & Instrumentation Engineering, Thapar University, Patiala, India 1 ABSTRACT Contingency analysis technique is being widely used to predict the effect of outages in power systems, like failures of equipment, transmission line etc. The off line analysis to predict the effect of individual contingency is a tedious task as a power system contains large number of components. Practically, only selected contingencies will lead to severe conditions in power system like violation of voltage and active power flow limits. The process of identifying these severe contingencies is referred as contingency selection and this can be done by calculating performance indices for each contingencies. In this paper, the contingency selection by calculating two kinds of performance indices; active power performance index (PIP) and reactive power performance index (PIV) for single transmission line outage have been done with the help of Fast Decoupled Load Flow (FDLF) in MATLAB environment. The ranking of most severe contingency has been done based on the values of performance indices. Simultaneously the value of bus voltages and active power flow before and after the most severe transmission line contingency has been analyzed. The effectiveness of the method has been tested on 5-Bus, IEEE-14 Bus and IEEE-30 Bus test systems. It can be seen from the results that, based on the knowledge of PIP & PIV the most severe transmission line contingency can be identified and the effect of this contingency on the rest of the system can also be seen via post contingency analysis. KEYWORDS: I. Contingency, contingency selection, performance indices, fast decoupled load flow. INTRODUCTION It is well known that power system is a complex network consisting of numerous equipments like generators, transformers, transmission lines, circuit breakers etc. Failure of any of these equipments during its operation harms the reliability of the system and hence leading to outages. Whenever the pre specified operating limits of the power system gets violated the system is said to be in emergency condition. These violations of the limits result from contingencies occurring in the system. Thus, an important part of the security analysis revolves around the power system to withstand the effect of contingencies. The contingency analysis is time consuming as it involves the computation of complete AC load flow calculations following every possible outage events like outages occurring at various generators and transmission lines. This makes the list of various contingency cases very lengthy and the process very tedious. In order to mitigate the above problem, automatic contingency screening approach is being adopted which identifies and ranks only those outages which actually causes the limit violation on power flow or voltages in the lines. The contingencies are screened according to the severity index or performance index where a higher value of these indices denotes a higher degree of severity. The importance of power system security assessment for prediction of line flows and bus voltages following a contingency has been presented in [1-2]. The paper also details the challenges faced for the practical implementation of security analysis algorithms. The approximate changes in the line flow due to an outage in generator or transmission line is predicted based on distribution factors [3-4]. The use of AC power flow solution in outage studies has been dealt in [5].Contingency screening or contingency selection is an essential task in contingency analysis. This helps to reduce 2159 Vol. 6, Issue 5, pp. 2159-2170 International Journal of Advances in Engineering & Technology, Nov. 2013. ©IJAET ISSN: 22311963 the numerous computations; the bounding method [6] reduces the number of branch flow computation by using a bounding criterion that helps in reducing the number of buses for analysis and is based on incremental angle criterion. The 1P-1Q method for contingency selection has been presented in [7]. In this method the solution procedure is interrupted after an iteration of fast decoupled load flow. Zaborzky et al. introduced the concentric relaxation method for contingency evaluation [8] utilizing the benefit of the fact that an outage occurring on the power system has a limited geographical effect. The use of fast decoupled load flow [9] proves to be very suitable for contingency analysis. Contingency selection criterion based on the calculation of performance indices has been first introduced by Ejebe and Wollenberg [10] where the contingencies are sorted in descending order of the values of performance index (PI) reflecting their severity. The practical implementation of contingency screening can be done by installing the phasor measurement units which are being used to capture the online values of bus voltages and angles [11]. The fast estimation of voltages in power system is essential for contingency analysis and this was proposed in [12]. Apart from performance index other index like voltage stability criteria index can also be chosen contingency ranking [13]. Multiple contingency can occur in the power system at the same time, hence its identification and analysis is a more complicated task, the multiple contingency screening in power system has been illustrated in [14]. The analysis of power system contingency becomes more challenging when the system is connected to a variable generation units like wind or solar systems, where the firm capacity is variable. In [15] the contingency analysis by incorporating sampling of Injected powers has been done. In this paper, the values of active power performance index (PIP) and reactive power performance index (PIV) have been calculated for 5-bus, IEEE-14 bus and IEEE-30 bus systems using the algorithm implemented in MATLAB software. Based on the values of PIV, contingencies have been ranked where a transmission line contingency leading to high value of PIV has been ranked 1 and a least value of PIV have been ranked last. The load flow analysis following the most severe transmission line contingency has been simulated and the results of active power flow in various transmission lines and the bus voltages has been analyzed. II. CONTINGENCY ANALYSIS USING LOAD FLOW SOLUTION 2.1 Contingency Selection Since contingency analysis process involves the prediction of the effect of individual contingency cases, the above process becomes very tedious and time consuming when the power system network is large. In order to alleviate the above problem contingency screening or contingency selection process is used. Practically it is found that all the possible outages does not cause the overloads or under voltage in the other power system equipments. The process of identifying the contingencies that actually leads to the violation of the operational limits is known as contingency selection. The contingencies are selected by calculating a kind of severity indices known as Performance Indices (PI) [1]. These indices are calculated using the conventional power flow algorithms for individual contingencies in an off line mode. Based on the values obtained the contingencies are ranked in a manner where the highest value of PI is ranked first. The analysis is then done starting from the contingency that is ranked one and is continued till no severe contingencies are found. There are two kind of performance index which are of great use, these are active power performance index (PIP) and reactive power performance index (PIV). PIP reflects the violation of line active power flow and is given by (1) P PIP = ∑Li=1(P i )2n (1) imax where, Pi = Active Power flow in line i, Pimax = Maximum active power flow in line i, n is the specified exponent, L is the total number of transmission lines in the system. 2160 Vol. 6, Issue 5, pp. 2159-2170 International Journal of Advances in Engineering & Technology, Nov. 2013. ©IJAET ISSN: 22311963 If n is a large number, the PI will be a small number if all flows are within limit, and it will be large if one or more lines are overloaded, here the value of n has been kept unity. The value of maximum power flow in each line is calculated using the formula V ∗V Pimax = i𝑋 j (2) where, Vi= Voltage at bus i obtained from FDLF solution Vj= Voltage at bus j obtained from FDLF solution X = Reactance of the line connecting bus ‘i’ and bus ‘j’ Another performance index parameter which is used is reactive power performance index corresponding to bus voltage magnitude violations. It mathematically given by (3) 𝑁𝑝𝑞 2(𝑉𝑖−𝑉𝑖𝑛𝑜𝑚) 2 PIV=∑𝑖=1 [𝑉𝑖𝑚𝑎𝑥−𝑉𝑖𝑚𝑖𝑛] (3) where, Vi= Voltage of bus i, Vimax and Vimin are maximum and minimum voltage limits, Vinom is average of Vimax and Vimin, Npq is total number of load buses in the system. III. ALGORITHM LOAD FLOW FOR CONTINGENCY ANALYSIS FAST DECOUPLED USING The AC power flow program for contingency analysis by the Fast Decoupled Power Flow (FDLF) [9] provides a fast solution to the contingency analysis since it has the advantage of matrix alteration formula that can be incorporated and can be used to simulate the problem of contingencies involving transmission line outages without re inverting the system Jacobian matrix for all iterations. Start Start Read the system bus data and line data Read Bus Data & Line Data Set the contingency counter K=0 Formulate the YBus matrix of the system and set counter K=0 Set |V i | 1.0 and i 0 for PQ bus and i 0 for PV bus Simulate the line outage contingency (0) (0) (0) Calculate P i and Q and P & Q for load bus (k ) Calculate the MW flows in all the transmission line and PMax using FDLF (k ) (k ) (k ) i i i Calculate PIP using (1) Calculate Pi and Pi for voltage-controlled buses (k ) Calculate the voltage at all the buses using FDLF (k ) P Calculate |V | Calculate PIV using (2) Yes Last contingency reached ? Yes Increment counter K=K+1 for next iteration Does P converge ? No No Does Q Yes converge ? No Calculate Increment the counter K=K+1 Rank the contingencies as per the highest value of PIP & PIV Do the power flow analysis for the most severe contingency case Print the results ' P [ B ]1 |V | Print Results Stop Q Calculate | V | Yes Does P converge ? Yes Does Q converge ? No No Q V [ B ] |V | '' 1 Stop Figure 1 Flow Chart for Contingency Analysis by FDLF 2161 Vol. 6, Issue 5, pp. 2159-2170 International Journal of Advances in Engineering & Technology, Nov. 2013. ©IJAET ISSN: 22311963 Hence to model the contingency analysis problem the AC power flow method, using FDLF method has been extensively chosen. Algorithm that is to be followed for calculating the load flow solution using FDLF [9] has been summarized in form of a flow chart. The algorithm steps for contingency analysis using fast decoupled load flow solution have been summarized in pictorial form in the flow chart as shown in Figure 1. IV. RESULTS AND DISCUSSIONS The algorithm described in Figure 1, has been programmed in MATLAB software and its results for various test bus system has been summarized in the following subsections. For calculation of PIV, it is required to know the maximum and minimum voltage limits, generally a margin of + 5% is kept for assigning the limits i.e., 1.05 P.U. for maximum and 0.95 P.U. for minimum. It is to be noted that the above performance indices is useful for performing the contingency selection for line contingencies only. To obtain the value of PI for each contingency the lines in the bus system are being numbered as per convenience, then a particular transmission line at a time is simulated for outage condition and the individual power flows and the bus voltages are being calculated with the help of fast decoupled load flow solution. 4.1 Results of 5-Bus System Case Study The system as shown in Figure 2 consists a slack bus numbered 1 and 4 load buses numbered 2, 3, 4 and 5. It has total seven transmission lines and the active power flow in each transmission lines that has been obtained using FDLF corresponding to the base case loading condition is shown in Figure 2, this base case analysis is also referred a Pre- contingency state. The load flow analysis is then carried out by considering the one line outage contingency at a time. Table 1 Performance Indices & Contingency ranking using FDLF for 5-bus system Outage Line No. 1 2 3 4 5 6 7 PIP PIV 0.2800 0.3619 0.3377 0.3790 0.4221 0.2995 0.3036 3.1916 0.2699 0.6557 0.6173 0.2653 0.8599 0.8799 Ranking 1 6 4 5 7 3 2 The active and reactive power performance indices (PIP & PIV) are also calculated considering the outage of only one line sequentially and the calculated indices are summarized in Table 1. It can be inferred that outage of line number 1 is the most vulnerable in the whole system; the highest value of PIV for this outage suggests that the highest attention be given for this line during the operation. It is seen that the contingency in the line connected between buses (1-2) results in highest value of the reactive power performance index and thus it is ranked first for the contingency selection, hence the post contingency state of the system corresponding to this contingency has been analyzed. Since, the value of PIV indicates the severity that is occurring in the system due to violation in voltage limit; hence analysis of pre-contingency and the post contingency voltages at the buses of the entire system have been detailed in Table 2. The MW flows corresponding to the pre contingency state and the post contingency state have been detailed in Table 3. 2162 Vol. 6, Issue 5, pp. 2159-2170 International Journal of Advances in Engineering & Technology, Nov. 2013. ©IJAET ISSN: 22311963 5 (1.018 P.U) 6.33 MW 22.23 MW 4 4 (0.861 P.U) 5 54.82 MW (1.060 P.U) 39.07 MW 1 27.93 MW (0.891 P.U) (1.047 P.U) 88.86 MW 40.72 MW 0 MW 143.63 MW 24.69 MW 2 1 15.33 MW 2 (1.060 P.U) 18.87 MW 3 4.00 MW (0.880 P.U) (1.024 P.U) 66.8 MW 3 (0.886 P.U) (1.024 P.U) Figure 2.Pre-Contingency State & Post Contingency state of 5-Bus system Table 2 Bus voltages in the Pre and Post Contingency State Bus Number Pre-contingency voltage (P.U) Post-contingency voltage (P.U) 1 2 3 1.060 1.047 1.024 1.060 0.891 0.886 4 1.024 0.880 5 1.018 0.861 Table 3 Active Power Flow in the Pre and Post Contingency State Line No. Start Bus End Bus Pre Contingency MW flow 88.86 MW 40.72 MW 24.69 MW Post Contingency MW flow 0 MW 143.63 MW 15.33 MW 1 2 3 1 1 2 2 3 3 4 5 6 2 2 3 4 5 4 27.93 MW 54.82 MW 18.87 MW 4.00 MW 39.07 MW 66.80 MW 7 4 5 6.33 MW 22.23 MW 4.2 Results of 14-Bus System Case Study The system has a total 20 number of transmission lines, hence we evaluate for 20 line contingency scenarios by considering the one line outage contingency at a time. The performance indices are summarized in the Table 4 where it can be inferred that outage in line number 16 is the most vulnerable one and its outage will result a great impact on the whole system. The high value of PIV for this outage also suggests that the highest attention be given for this line during the operation. The contingencies have been ordered by their ranking where the most severe contingency is being ranked 1 and the least has been ranked 20. The values & variation of reactive performance index with their ranking has been shown in the Figure 3. It is clear from the result of different PIV that the contingency number 16 which the line outage contingency corresponding to the line connected between buses (910) is the most severe contingency. The system as shown in Figure 4 consists of 1 slack bus, 9 load buses and 4 generator buses. There are three synchronous compensators used only for reactive power support. The active power flow in each transmission lines that has been obtained using FDLF corresponding to the base case loading condition is also shown in Figure 4. This state of the system corresponds to the pre contingency state. The MW flows corresponding to the pre contingency state and the post contingency state has been detailed in Table 5. 2163 Vol. 6, Issue 5, pp. 2159-2170 International Journal of Advances in Engineering & Technology, Nov. 2013. ©IJAET ISSN: 22311963 Table 4 Performance Indices & Contingency Ranking using FDLF for 14-Bus System Outage Line No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 PIP PIV 1.1693 0.9807 1.1654 0.9999 0.9820 0.9640 0.9915 1.0747 0.9807 1.2396 1.0142 1.0127 1.0569 1.0072 1.0759 1.0114 1.0164 1.0030 1.0008 1.0076 Ranking 7.3032 7.6696 10.0014 7.3213 8.8759 13.2572 0.3566 1.1753 10.5776 1.6047 9.5907 1.8089 1.3669 10.4518 0.0844 13.3464 2.3482 10.5217 12.5538 2.2891 10 11 7 12 9 2 19 17 4 16 8 15 18 6 20 1 13 5 3 14 14 14 12 12 10 10 8 PIv PIv 8 6 6 4 4 2 2 0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Outage Line Number 15 16 17 18 19 20 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Rank of Line outage Contingency Figure 3 Values of PIV for 14-Bus system & Contingency Ranking and PIV of 14-Bus System 2164 Vol. 6, Issue 5, pp. 2159-2170 International Journal of Advances in Engineering & Technology, Nov. 2013. ©IJAET ISSN: 22311963 G GENERATORS G GENERATORS C SYNCHRONOUS COMPENSATORS C SYNCHRONOUS COMPENSATORS 13 13 4.33 MW 6.14 MW 12 1.82 MW 18.2 MW 11 12 14 4.32 MW 16.67 MW 11 8.94 MW 10 7.93 MW 9 4.72 MW 8 44.74 MW C G 7 15.8 MW 6 9 0 MW C 74.7 MW 10 10.7 MW 12.79 MW G C 9.09 MW 7.58 MW 7.96 MW 1 14 1.4 MW 1 7 14.9 MW 6 C 8 48.2 MW 4 75 MW 60.19 MW 4 57.6 MW 5 5 156.8 MW 157.3 MW 56 MW 56.3 MW 42.3 MW 42.03 MW 23 MW 23.19 MW 2 2 71.5 MW 71.6 MW 3 G 3 G C C Figure 4 Pre-Contingency & Post-Contingency State of 14-Bus System Table 5 Active Power Flow in the Pre and Post Contingency State Line No. Start Bus End Bus 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 1 1 2 2 2 3 4 4 4 5 6 6 6 7 7 9 9 10 12 13 2 5 3 4 5 4 5 7 9 6 11 12 13 8 9 10 14 11 13 14 Pre contingency MW flow 157.3 MW 74.7 MW 71.6 MW 56.3 MW 42.03 MW 23.19 MW 60.19 MW 27.38 MW 15.8 MW 44.74 MW 7.96 MW 7.93 MW 18.21 MW 0.0 MW 27.39 MW 4.72 MW 8.94 MW 4.32 MW 1.82 MW 6.14 MW Post contingency MW flow 156.8 MW 75 MW 71.5 MW 56 MW 42.3 MW 23 MW 57.6 MW 25.5 MW 14.9 MW 48.2 MW 12.79 MW 7.58 MW 16.67 MW 0.0 MW 25.5 MW 0 MW 10.7 MW 9.09 MW 1.4 MW 4.33 MW 4.3 Results of 30-Bus System Case Study The IEEE-30 bus system has 6 PV buses, 24 PQ buses and 41 lines [38], hence for the PIP and PIV calculation a total number of 41 line contingency cases are performed. The system consists of 41 transmission lines; the load flow analysis is carried out for 41 line contingency case considering one line outage at a time. From Table 6 it can be inferred that outage of line number 9 is the most vulnerable one and its outage will result a great impact on the whole system. Table 6 Performance Indices & Contingency Ranking using FDLF for 30-Bus System Outage Line No. 1 2 3 4 2165 PIP 1.5919 1.2754 1.2724 1.2740 PIV 3.9995 23.0290 24.5949 26.6730 Ranking 40 32 26 18 Vol. 6, Issue 5, pp. 2159-2170 International Journal of Advances in Engineering & Technology, Nov. 2013. ©IJAET ISSN: 22311963 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 1.5029 1.2978 1.2982 1.2692 1.2803 1.3611 1.3691 1.2786 1.2996 1.3727 1.5285 1.2967 2.2972 1.3477 1.3084 1.2928 1.2964 1.3078 1.2983 1.3005 1.3081 1.3000 1.3183 1.2953 1.2954 1.3109 1.3086 1.2960 1.2948 1.9801 1.3111 1.4453 1.3073 1.3211 1.2893 1.2964 1.3282 30 23.3686 24.1327 23.0787 27.3376 29.5544 29.1055 26.2201 26.3051 18.6875 14.5771 9.6712 14.2764 0.3451 17.2591 24.5808 27.9804 27.6818 24.8931 27.8178 25.2770 20.4257 26.1714 24.0073 27.0173 28.2909 25.7308 27.1708 28.3973 29.1538 27.6726 26.1241 16.6797 27.8202 27.7249 28.0231 28.1952 28.1188 30 28 31 15 1 3 20 19 34 37 39 38 41 35 27 9 13 25 11 24 33 21 29 17 5 23 16 4 2 14 22 36 10 12 8 6 7 30 25 25 20 PIv PIv 20 15 15 10 10 5 5 0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 Outage Line Number 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 Rank of Line outage Contingency Figure 5 PIV Values & Contingency ranking and PIV of 30-Bus system 2166 Vol. 6, Issue 5, pp. 2159-2170 International Journal of Advances in Engineering & Technology, Nov. 2013. ©IJAET ISSN: 22311963 Figure 5 shows the contingency ranking of this system with respect to the PIV values. Since for the IEEE-30 bus system contingency number 9 which is the line connected between buses (6-7) is the most critical contingency, the post contingency analysis following the outage of this line has been done and the power flow in the post contingency state has been detailed in Figure 6. Here the system’s bus voltages corresponding to the pre contingency and the post contingency state has been obtained, the results are detailed in Table 7. The active power flow in all the lines during the pre-contingency and post contingency state has been detailed in Table 8. 1 G 177.77 MW 2 G 83.22 MW 45.71 MW 14 3 13 1.55 MW C 7.89 MW 15 4 5.005 MW 17.82 MW 61.9 MW 12 16 83 MW 70.12 MW 23 24 7.20 MW 18 3.65 MW 2.78 MW 6.74 20 MW 9.02 MW 10 5 C 14.35 MW 17 9 7.09 MW 19 5.64 MW 15.73 MW 27 29 4.90 MW 22 7.58 MW 25 7 29.5 MW 3.70 MW 1.33 MW 21 6 37.52 MW 30 6.02 MW 28 11 C 18.81 MW 3.53 MW 26 0.57 MW 8 C Figure 6 Pre & Post contingency state of the 30-Bus System Table 7 Bus Voltages in the Pre and Post Contingency State Bus Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 2167 Pre-Contingency voltage (P.U) 1.060 1.043 1.022 1.013 1.010 1.012 1.003 1.010 1.051 1.044 1.082 1.057 1.071 1.042 1.038 1.045 1.039 1.028 Post-contingency voltage (P.U) 1.060 1.043 1.024 1.016 1.010 1.015 0.988 1.010 1.053 1.047 1.082 1.059 1.071 1.044 1.039 1.046 1.041 1.030 Vol. 6, Issue 5, pp. 2159-2170 International Journal of Advances in Engineering & Technology, Nov. 2013. ©IJAET ISSN: 22311963 19 20 21 22 23 24 25 26 27 28 29 30 1.025 1.029 1.032 1.033 1.027 1.022 1.019 1.001 1.026 1.011 1.006 0.995 1.027 1.031 1.034 1.035 1.029 1.024 1.021 1.004 1.028 1.013 1.009 0.997 Table 8 Active Power Flow in the Pre and Post Contingency State Line No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 23 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 2168 Start Bus 1 1 2 3 2 2 4 5 6 6 6 6 9 9 4 12 12 12 12 14 16 15 18 19 10 10 10 10 21 15 22 23 24 25 25 28 27 27 29 8 6 End Bus 2 3 4 4 5 6 6 7 7 8 9 10 11 10 12 13 14 15 16 15 17 18 19 20 20 17 21 22 22 23 24 24 25 26 27 27 29 30 30 28 28 Pre contingency MW flow 177.77 MW 83.22 MW 45.71 MW 78.01 MW 82.99 MW 61.91 MW 70.12 MW 14.35 MW 37.52 MW 29.5 MW 27.69 MW 15.82 MW 0.00 MW 27.69 MW 44.12 MW 0.00 MW 7.89 MW 17.82 MW 7.20 MW 1.55 MW 3.65 MW 6.02 MW 2.78 MW 6.74 MW 9.02 MW 5.37 MW 15.73 MW 7.58 MW 1.87 MW 5.00 MW 5.64 MW 1.77 MW 1.33 MW 3.53 MW 4.90 MW 18.18 MW 6.18 MW 7.09 MW 3.70 MW 0.57 MW 18.81 MW Post contingency MW flow 187.77 MW 74.80 MW 32.14 MW 70.13 MW 123.95 MW 43.81 MW 50.83 MW 23.06 MW 0 MW 29.55 MW 28.42 MW 16.25 MW 0.00 MW 28.42 MW 42.66 MW 0.00 MW 7.69 MW 17.23 MW 6.53 MW 1.43 MW 2.98 MW 5.65 MW 2.41 MW 7.10 MW 9.39 MW 6.03 MW 15.81 MW 7.63 MW 1.79 MW 4.59 MW 5.71 MW 1.36 MW 1.60 MW 3.54 MW 5.17 MW 18.45 MW 6.18 MW 7.08 MW 3.70 MW 0.55 MW 19.07 MW Vol. 6, Issue 5, pp. 2159-2170 International Journal of Advances in Engineering & Technology, Nov. 2013. ©IJAET ISSN: 22311963 V. CONCLUSIONS In this paper, the calculation of active and reactive power performance indices for contingency selection has been done using FDLF for various test bus systems. The post-contingency analysis following the most severe contingency, where the bus voltages and the power flow in the entire system has been calculated. From the results of PIP and PIV it can be concluded that for the 5-bus test system, outage in the transmission line number 1, in IEEE 14-bus system transmission line contingency in line number 16 and for IEEE 30-bus system, a transmission line outage in line number 9 are the most critical contingencies. An outage in these lines has the highest potential to make the system parameters to go beyond their limits. It can be further concluded that these lines require extra attention which can be done by providing more advanced protection schemes or load shedding schemes. VI. FUTURE WORK The work discussed in this paper can be extended further by incorporating other kind of indices as discussed in [12-13]. Calculation of the performance indices by using artificial intelligence techniques like artificial neural networks [12] or by fuzzy logic can be taken up as future work. The contingency analysis techniques can be further explored by considering multiple equipment failures or by incorporating renewable energy sources in the power system. REFERENCES [1] Wood A.J and Wollenberg B.F., “Power generation, operation and control”, John Wiley & Sons Inc., 1996. [2] Stott B, Alsac O and Monticelli A.J, “Security Analysis and Optimization”, Proc. IEEE, vol. 75,No. 12, pp. 1623-1644,Dec 1987. [3] Lee C.Y and Chen N, “Distribution factors and reactive power flow in transmission line and transformer outage studies”, IEEE Transactions on Power systems, Vol. 7,No. 1,pp. 194-200, February 1992. [4] Singh S.N and Srivastava S.C, “Improved voltage and reactive distribution factor for outage studies”, IEEE Transactions on Power systems, Vol. 12, No.3, pp.1085-1093, August 1997 [5] Peterson N.M, Tinney W.F and Bree D.W, “Iterative linear AC power flow solution for fast approximate outage studies”, IEEE Transactions on Power Apparatus and Systems, Vol. PAS-91, No. 5, pp. 2048-2058, October 1972. [6] Brandwjn V and Lauby M.G, “Complete bounding method for A.C contingency screening”, IEEE Transactions on Power systems, Vol. 4, No. 2, pp. 724-729, May 1989. [7] Albuyeh F, Bose A and Heath B, “Reactive power consideration in automatic contingency selection”, IEEE Transactions on Power systems, Vol. PAS-101, No. 1, pp. 107-112, January 1982. [8] Zaborzky J, Whang K.W and Prasad K, “Fast contingency evaluation using concentric relaxation”, IEEE Transactions on Power systems, Vol. PAS-99, No. 1, pp. 28-36, February 1980. [9] Stott B and Alsac O, “Fast decoupled load flow”, IEEE Transactions on Power Apparatus and Systems, Vol. PAS-91, No. 5, pp. 859-869, May 1974. [10] Ejebe G.C and Wollenberg B.F, “Automatic Contingency Selection”, IEEE Transactions on Power Apparatus and Systems, Vol. PAS-98, No. 1, pp. 97-109, January 1979. [11] Innocent Kamwa, Robert Grondin and Lester Loud, “Time- Varying Contingency Screening for Dynamic Security Assessment Using Intelligent-Systems Techniques”, IEEE Transactions on Power Systems, Vol. 16, No. 3, pp. 526-537, August 2001 [12] T.Jain, L.Srivastava, S.N. Singh and Arvind Jain, “Parallel Radial Basis Function Neural Network Based Fast Voltage Estimation for Contingency Analysis”, IEEE International Conference on Electric Utility Deregulation, Restructuring and Power Technologies, Hong Kong, April 2004. [13] F. Fatehi, M.Rashidinejad and A.A Gharaveisi, “Contingency Ranking Based on a Voltage Stability Criteria Index”, IEEE Transactions in Power System, 2007 [14] Vaibhav Donde, Vanessa Lopex, Bernard Lesieutre, Ali Pinar, Chao Yang and Juan Meza, “Severe Multiple Contingency Screening in Electric Power Systems”, IEEE Transactions on Power Systems, Vol.23, No.2, pp. 406-417, May 2008. [15] Magnus Perninge, Flip Linskog and Lennart Soder, “Importance Sampling of Injected Powers for Electric Power System Security Analysis”, IEEE Transactions on Power Systems, Vol.27, No.1, February 2012. 2169 Vol. 6, Issue 5, pp. 2159-2170 International Journal of Advances in Engineering & Technology, Nov. 2013. ©IJAET ISSN: 22311963 AUTHORS BIOGRAPHIES Amit Kumar Roy was born in West Bengal, India on February, 1988. He received his B.E degree in Electrical & Electronics Engineering from Sathyabama University, Chennai in 2009 and M.E degree in Power Systems & Electric drives from Thapar University, Patiala in 2011. He had secured Gold Medal in his M.E degree and 2 nd position in his B.E degree. He is also a life member of Indian Society of Technical Education (ISTE), New Delhi. At present he is working as an Assistant Professor in the Department of Electrical Engineering at JSS Academy of Technical Education, Noida, U.P. where he is actively involved in the academic activities and research work. His area of interest includes intelligent techniques applications to Power Systems, Power Converters and Electric Drives. Sanjay Kr. Jain was born in Madhya Pradesh, India on December, 1971. Awarded B.E. (Electrical Engineering) from SGSITS Indore in 1992. Awarded M.E. (Power System) from University of Roorkee (UOR), Roorkee in 1995. Awarded Ph.D. from IIT Roorkee in 2001. Dr. Jain has a vast teaching experience of 13 years since 2001. At present he is working as an Associate Professor in the Department of Electrical & Instrumentation Engineering at Thapar University, Patiala, Punjab. His main area of interest lies in various techniques in Powers System Optimization and modeling of Self Excited Induction Generators. 2170 Vol. 6, Issue 5, pp. 2159-2170