Drawings and Specifications

advertisement
Scope of Work – Section 16000
PART 1.
1.1
1.2
1.3
1.4
GENERAL
Description of Work
.1
The Contractor shall furnish, install and commission all equipment, labour, materials, tools, and
provide all necessary supervision and other services as required to execute the work and to realize
the intent of the City of Guelph Lift Stations SCADA Upgrades.
.2
The supply and installation of electrical items must be in accordance with the Specifications and
Drawings of this contract.
.3
These Specifications and Drawings constitute the full scope of the project. All items required but
not shown on the Drawings or not mentioned in the Specifications that are necessary for a
complete electrical installation shall be regarded as included in the contract requirements.
.4
The Contractor shall furnish all equipment and accessories specified herein including all other
accessories and details not specifically mentioned or fully detailed but which required to make a
complete and well integrated product within the scope of this Specification.
Reference
.1
Comply with the requirements of the Request for Quotation General Conditions. Be responsible for
all the requirements of this Section and of the General Conditions No additional cost will be
considered for non-coordination between this Section and the other Sections in the Specification.
.2
Refer to Division 16, in particular Section 16010 Basic Electrical Requirements, Section 16423
Control Devices, Section 16122 Wiring and Cables, for instructions which apply to the Work of
Section 16900.
.3
Have the material, equipment, installation and workmanship also meet the latest edition and
requirements of the following:
.1
Ontario Electrical Safety Code
.2
Canadian Standards Association (CSA)
.3
Canadian Electrical Manufacturers Association (CEMA)
.4
National Electrical Manufacturers Association (NEMA)
.5
Electrical and Electronic Manufacturers Association of Canada (EEMAC)
.6
International Society for Measurement and Control (Formerly the Instrument Society of
America, ISA)
.7
Electronic Industries Association / Telecommunications Industries Association (EIA/TIA
606)
.4
Design and Construction Specifications for City of Guelph.
.5
SCADA Standards for the City of Guelph, Wastewater Services Division (WSD).
Contractor Use of Premises
.1
Use of premises shall be limited to the specific areas of the work.
.2
Assume full responsibility for protection and safekeeping of products under this Contract.
.3
Coordinate use of premises under direction of the Owner’s Representative.
.4
Standard work hours are between 7:30 a.m. and 4:30 p.m. Generally work shall be done during
these hours. Work may be done outside of the standard working hours only when permission is
given by the Owner.
City Procedures
.1
The Contractor shall conform to the City of Guelph Procedures while undertaking activities within
facilities owned and operated by the City of Guelph. These may require efforts or procedures that
are greater than those required by the regulatory agencies.
The City of Guelph
Lift Stations SCADA Upgrades
Page 1 of 9
November, 2008
Scope of Work – Section 16000
1.5
.2
Where existing systems or equipment need to be isolated, dewatered, decommissioned, or deenergized, the WSD Operations Staff will operate all existing valves, gates, disconnects or
equipment to isolate, dewater, decommission, or de-energize the existing systems, or equipment.
The Contractor prior to starting work on existing systems or equipment, shall check, and test all
systems or equipment to determine that conditions are safe to proceed with the required work.
.3
The facilities under this contract are fully operational wastewater pumping stations, and as such,
may include confined spaces and/or hazardous chemicals may be present. These areas are to be
considered as confined spaces. The Contractor shall submit his/her confined space entry
procedures and experience working in confined space to the City for review prior to commencing
any work. The Contractor is responsible for providing all necessary safety equipment for use by
their employees. The Contractor shall also provide all necessary safety equipment for use by the
Engineer’s inspection personnel. The equipment shall meet the requirements of the Occupational
Health and Safety Act.
.4
Payment milestones shall be at 30%, 50% and 90% completion. Alternate terms of payment may
be proposed by the Proponents in their proposal and will be reviewed by the City. The City
reserves the right to accept or reject any alternate proposal at their sole discretion.
Electrical, I&C Work
.1
The electrical work to complete the project shall be executed so as to minimize the existing
pumping stations shut down durations as new works are brought on line. The pumping stations
must remain in operation during the construction of the upgrades and be provided with any specific
items that are required to keep the station operational.
.2
Generally, the major work involved under the contract for the Lift Stations SCADA Upgrades
include the items detailed in Division 16 and as identified herein. During the quotation period, visit
the site and ascertain the actual conditions and the extent of the work. All items to be disposed by
contractor unless noted.
.1
Gordon Street Lift Station:
1.
Supply and install new PLC control panel, complete with PLC components,
power supply, Instrumentations, UPS, fuses, breakers, terminal blocks, and
additional components.
2.
Integrate PLC control into the pump starters for automated control.
3.
Re-Tagging of existing instruments.
4.
Commissioning and testing of the works.
.2
Barton Estates Lift Station:
1.
Supply and install new PLC control panel, complete with PLC components,
power supply, Instrumentations, UPS, fuses, breakers, terminal blocks, and
additional components.
2.
Integrate PLC control into the pump starters for automated control.
3.
Re-Tagging of existing instruments.
4.
Commissioning and testing of the works.
.3
In general, the work involves the supply installation, modification and commissioning of the
necessary hardware for the SCADA system upgrades at two (2) wastewater pumping stations
within the City of Guelph as indicated on the drawings. Automatic control will be performed by a
new Allen Bradley PLC based control system which will interface to most of the station’s
instrumentation, transducers, level switches, etc. and will report to the Plant SCADA.
Communication back to the City of Guelph wastewater plant SCADA system will be accomplished
via Bell Canada circuits. This includes, but is not limited to the following major items:
.1
Provide, test and commission all field instrumentation, instrument control panels, and
control system hardware including all lightning & surge protection, and all peripheral
devices necessary.
.2
Provide, test and commission the programmable logic controller (PLC) and associated
equipment.
.3
Provide all interconnecting cabling for PLC equipment and tie ins.
.4
Work with the City’s Engineer to commission the programmable logic controller (PLC) and
associated equipment. All programming of PLC/HMI to be completed by the City’s
representative. Coordinate closely with the Engineer when carrying out all work to
demonstrate system integrity, allowing sufficient time for the essential portions of control
software to be installed and tested.
The City of Guelph
Lift Stations SCADA Upgrades
Page 2 of 9
November, 2008
Scope of Work – Section 16000
.5
.6
.7
.8
.9
.10
.11
.12
.13
1.6
Provide all programming and microprocessor-based instrument configuration.
Provide a Panel Factory Acceptance Testing (FAT) to demonstrate the operational
functionality of new control panels. Notify the Engineer ten (10) days (minimum) in
advance of FAT such that this test may be witnessed by the appropriate parties.
Provide the services of qualified manufacturer’s service representatives for installation,
setup, calibration, testing, commissioning of instrumentation and control devices and
guarantee and warranty period activities.
Provide testing and commissioning services including those associated with installing and
testing software prepared by others. Allow for a minimum of five (5) working days, based
on an 8 hour working day, for software testing during which time, the Contractor’s staff are
to be available. Not all days will be necessarily full days or concurrent. It is expected that
the project will be commissioned in a staged approach. Allow in the Quotation, for any
additional time deemed necessary to meet the testing and commission requirements.
Demonstrate instrument calibration and loop checks. Before requesting witnessed loop
checks, carry out Contractor’s own field and loop check tests to verify that the equipment
operates as intended. Correct problems or deficiencies prior to requesting witnessed
checks.
Loop checks must exercise the entire loop, stroking motorized or actuated field
equipment, monitored and operated through SCADA and PLC I/O as well as locally. Each
loop check must be witnessed by, and successfully demonstrated to, the Engineer for
sign-off approval.
Provide assistance during the software Site Acceptance Testing (SAT) to demonstrate the
correct operation of control system with both hardware and software in place. This site
acceptance testing forms part of commissioning and must be completed satisfactorily prior
to application software being loaded.
Maintain record drawings (as-builts) for all drawings.
Provide training.
Contractors Submittals
.1
This section covers Contractor’s submittals to Engineer including but not limited to interference
drawings, shop drawings, shop drawings for temporary works, construction schedule, samples,
safety plan, administrative submittals, checkout plan, Record Drawings, construction facilities plan,
quality control plan, quotation breakdown, applications for progress payments, manufacturer’s field
reports, and environmental controls.
.2
The proponent shall submit, as part of this proposal, a detailed workplan and implementation
schedule. A workplan and schedule shall indicate the sequence and duration of events necessary
to carry out the work included under this contract. The workplan and schedule must be approved by
the engineer prior to commencement of any work. The proposed work schedule is to include
implementation details, milestone dates, etc. The workplan is to be developed in MS-Project (latest
version).
.3
Summary
.1
Submit all submittals to Engineer.
.2
Submit following items for review within 20 business days of official order to commence
work:
1.
List of submittals with scheduled submission dates including Section number,
description of submittal, scheduled submission date, and anticipated approval
date. Allow for minimum of one resubmittal or each shop drawing and sample.
As a minimum, the following major milestones to be included:
1.
Hardware shop drawings submission – including initial issue of Product
Data Sheets
2.
Preliminary issue of operating and maintenance instruction manual
3.
Panel inspection and factory acceptance testing (FAT)
4.
Site installation, inspection, and loop checks
5.
Final submission and sign-off of Product Data Sheets as per this
Section
6.
Ready for PLC program installation and testing
7.
Site acceptance testing (SAT)
8.
Operator & maintenance training sessions
9.
System commissioning
The City of Guelph
Lift Stations SCADA Upgrades
Page 3 of 9
November, 2008
Scope of Work – Section 16000
2.
.3
.4
.5
.6
.7
.4
List of permits and licenses to obtain, indicating agency required to grant permit,
expected date of submittal for permit, and required date for receipt of permit.
3.
Provide mobilization schedule.
Contractor shall submit six (6) copies of initial and updated interference drawings before
installation indicating structures, mechanical and electrical equipment, and systems on
same drawing.
Contractor shall provide interference drawings with dimensions and unit designations in SI
metric units.
Contractor shall submit updated interference drawings as work progresses.
Contractor shall make necessary relocations due to interference of trades as a result of
incomplete interference drawings at no additional cost to Owner after discussion with
Engineer.
Contractor is responsible for locating all underground services prior to commencing work.
Shop Drawings
.1
Contractor shall submit ten (10) copies of each shop drawing submittal to Engineer.
Engineer shall retain five (5) copies, three (3) of which will be submitted to the City of
Guelph.
.2
Contractor’s shop drawings shall include, as a minimum, detailed design calculations,
detailed equipment drawings, fabrication and installation drawings, mounting drawings,
lists, graphs, catalogue sheets, data sheets, and other similar items.
.3
Contractor shall submit, as applicable, the following items for prefabricated or
manufactured structural, mechanical, electrical, and instrumentation systems and
equipment:
1.
Wiring and control diagrams of systems and equipment.
2.
Complete manufacturer’s specifications, including materials description and paint
system.
3.
Finish colour will be ANSI 61 Light Grey.
4.
Requirements for storage and protection prior to installation.
5.
Installation procedures.
6.
Detailed written list of requested exceptions to Contract Documents and/or
variations from specified equipment, referenced to Article number.
.4
Contractor shall sequentially number shop drawing transmittal forms. State original
number with alphabetic suffix on resubmittals.
.5
Contractor shall identify Contract, Contract Number, Contractor, Sub-contractor and/or
Supplier, pertinent drawing sheet and detail number(s), specification section number,
article number, and equipment number on transmittals.
.6
Contractor shall indicate model and option being proposed and strike out all non-relevant
data on standard drawings or data sheets.
.7
Contractor shall submit separate transmittal form for each specific item, class of material,
and equipment for which submittal is required. Transmittal of submittal of various items
using single transmittal form will be permitted only when items taken together constitute a
manufacturer’s “package” or are so functionally related that expediency indicates review of
group or package as a whole.
.8
Contractor shall collate multiple-page submittals into sets. Staple or bound each set, as
appropriate, prior to transmittal to Engineer.
.9
All sets except those retained by the Engineer of each submittal will be returned to
Contractor with comments noted, as applicable.
.10
It is considered reasonable that Contractor makes complete and acceptable submittal to
Engineer by second submission of submittal item. Owner reserves right to withhold
review beyond second submittal.
.11
Contractor shall submit shop drawings in SI metric units. Shop drawings submitted in
Imperial Units will not be reviewed by Engineer and will be returned to Contractor.
.12
Contractor shall submit shop drawings well in advance of time when product is required
for use. Co-ordinate shop drawings prepared by different trades so that information is
available to allow proper review and sufficient review time, where work of one trade
interfaces with or affects work of another trade. Recognize extensive engineering review
time required for complex equipment or systems. Contractor shall allow for a minimum
review time of one (1) week of each shop drawing submitted.
.13
Review of shop drawings is subject to following:
1.
Final review of equipment and materials in place.
2.
After commissioning of equipment.
The City of Guelph
Lift Stations SCADA Upgrades
Page 4 of 9
November, 2008
Scope of Work – Section 16000
.14
.15
.16
.17
.18
.19
.20
.21
.22
.23
.24
.25
.26
.27
.28
.29
.30
.5
3.
After guarantees are fulfilled.
4.
After operation of equipment and materials.
Contractor shall carefully review shop drawing submittals prior to submission to Engineer.
Contractor shall date, sign, and certify each submittal, as being correct and in strict
conformance with Contract Documents. Date, sign, and certify each sheet in shop
drawing.
Engineer will only review shop drawings certified by Contractor. All non-certified
submittals will be returned to Contractor without action taken by Engineer. Any resulting
delays are responsibility of Contractor.
Review of shop drawings by Engineer is to assist Engineer in appraising contractual
compliance.
Engineer’s review of shop drawing submittals does not relieve Contractor of responsibility
of work to conform to Contract Documents and for correctness of details and dimensions.
Contractor shall assume responsibility and risk for misfits due to errors in submittals.
Contractor shall be responsible for dimensions and design of adequate connections and
details.
Each submission will be stamped either “REVIEWED”, “REVIEWED AS NOTED”,
“REVISE AND RESUBMIT” or “NOT REVIEWED”.
Formal revision and resubmission of submittal is not required, if copies of submittal are
returned to Contractor marked “REVIEWED”.
Revise and resubmit required number of copies of submittal to Engineer, if copies of
submittal are returned to contractor marked “REVISE AND RESUBMIT”.
Fabricate items after Engineer has returned copies to Contractor marked either
“REVIEWED” or “REVIEWED AS NOTED”.
Contractor shall incorporate corrections on submittals to meet requirements of Contract
Documents. Do not misconstrue corrections as basis for changes to contract
requirements.
Contractor shall clearly identify changes on re-submission and include revision dates.
Changes to re-submissions that were not identified as noted by the Engineer on the
preceding submission(s) must be clearly identified. Re-submissions not incorporating
changes noted by the Engineer on earlier submissions, and re-submission that omit- or
modify original drawings that are not identified by the Engineer does not mean acceptance
of the changes by the Engineer.
Fabrications, erection, installation or commissioning may require modifications to
equipment or systems to conform to design intent. Revise and resubmit applicable shop
drawings to Engineer for review.
Material and equipment delivered to site will not be paid for until applicable shop drawings
have been approved by Engineer.
Engineer will withhold deductions from progress payment certificates for incomplete shop
drawings.
No claims will be allowed due to delays in re-submissions and review of shop drawings.
Do not place information on back of shop drawings.
Shop Drawings for Temporary Works
.1
Contractor shall submit shop drawings of temporary work to Engineer for review that:
1.
Impose loads on parts of work still under construction or on existing structures.
2.
Control dimensions and locations of any part of structures to be constructed
under Contract.
3.
Provide temporary electrical power to facility. (add other specifics if applicable)
.2
Contractor shall submit sufficient copies of shop drawings of temporary works prepared in
SI metric units for review.
.3
Payment will not be authorized for work started without Engineer’s completed review.
.4
Contractor shall submit shop drawings of temporary works well in advance of time when
they are required for work.
.5
Contractor shall co-ordinate shop drawings of temporary works prepared by different
trades so that information is available to prevent conflict or errors where work of one trade
affects work of another trade.
.6
Engineer will review shop drawings of temporary works for compliance with required
arrangement and dimensions of permanent structures and for general conformity with
Contract Documents.
The City of Guelph
Lift Stations SCADA Upgrades
Page 5 of 9
November, 2008
Scope of Work – Section 16000
.7
.8
.9
.10
.11
Contractor to review and incorporate comments made by Engineer if resubmittal is
requested by Engineer. Resolve issues noted on shop drawings of temporary works and
then resubmit shop drawings with necessary revisions.
Contractor shall not construct temporary works until Engineer’s review of shop drawings is
complete.
Engineer’s review of shop drawings of temporary works does not relieve Contractor of
responsibility for results arising from errors or omissions of design or from use or abuse of
temporary works.
Maintain one copy of each stamped, reviewed shop drawing of temporary works at site for
reference during work.
Contractor shall not change shop drawings of temporary works after Engineer’s review.
.6
Product Data Sheets:
.1
Product Data Sheets specifying instruments and equipment form part of this document.
Complete the blank spaces on these sheets with the information noted below and any
other data pertinent to the equipment and the application.
.2
Initial Submission for review to accompany Shop Drawings:
1.
The product manufacturer and the supplier or representative
2.
The complete model or catalogue number(s) including any special options
3.
The available adjustment range(s) and the project operating range(s)
.3
Second Submission during pre-commissioning, testing and calibration period:
1.
Serial numbers, part numbers, dates of installation and calibration;
2.
Any special procedures required to duplicate calibration.
1.
This submission is for signature by the Contractor and the Engineer
following acceptance of the operation of each instrument
3.
Final Submission of signed-off Product Data Sheets included with Operating and
Maintenance Instruction Manuals:
1.
All of the above information and
2.
Phone and fax numbers of contact person for product support/service
.7
Progress Schedule
.1
Submit updated progress schedule to Engineer four (4) business days prior to each
progress site meeting. Include forecast and actual data in updated progress schedule.
1.
Forecast data shows Contractor’s intended plan for remainder of Contract
duration.
2.
Actual data records when and how work was performed.
3.
Prepare progress schedule update in precedence diagram and/or bar chart
format with appropriate logic ties between bars. Include following items with
each updated progress schedule:
1.
Current status of each activity.
2.
Remaining duration of each activity.
3.
Actual start and finish date for each activity in progress or completed.
4.
Estimated start of activities, resequencing of work or proposed changes
in logic or duration for activities in future.
.2
Submit mobilization schedule to Engineer seven (7) business days prior to preconstruction meeting with summary schedule of approximately 20 activities containing the
following:
1.
Major construction activities.
2.
Contract procurement activities for major equipment with delivery duration of
greater than six weeks.
3.
Contract cash flow profile.
4.
Major milestone events including start and completion dates for facility start up of
each individual facility:
1.
Mobilization on site.
2.
Start and completion dates for electrical work.
3.
Start and completion dates for equipment installation.
4.
Start and completion dates for testing.
.3
Maintain at Site one complete set of drawings and specifications showing work performed
to date. Make available to Owner’s Representative at any time
.8
Safety Plan
The City of Guelph
Lift Stations SCADA Upgrades
Page 6 of 9
November, 2008
Scope of Work – Section 16000
.1
.2
Contractor shall submit two copies of contract specific Safety and Security Plan. Engineer
will review Plan to ensure that following items are addressed. Engineer will not review
Plan for adequacy of following items. Plan will:
1.
Generally address safe work procedures for activities within Contractor’s scope
of work.
2.
Include provisions to protect Contractor’s employees on work and other persons
and organizations who may be affected by work from injury, damage or loss.
3.
Comply with OHSA and applicable safety codes and regulations.
4.
Include designation of on-site qualified safety representative responsible for
enforcement of applicable statutes and safety rules.
5.
Include emergency response plans.
6.
Include confined space entry procedures.
7.
Address hazards communications.
8.
Security provisions for Contractor’s work, tools and equipment.
9.
Capability of providing Engineer with documentation of compliance with plan,
plus accident and investigation reports.
10.
Address any other contract specific requirements.
Review of safety plan by Engineer does not impose any duty or responsibility upon
Engineer for Contractor’s performance of work in safe manner. Contractor is fully
responsible for safety during performance of work.
.9
Administrative Submittals
.1
Contractor shall provide submittals required by regulatory agencies, Supplemental
General Conditions, and as required by Contract Documents.
.2
Contractor shall submit copy of letters relative to Contract, transmitting notifications,
reports, certifications that Contractor submits directly to federal, provincial or other
governing agencies.
.3
Contractor shall maintain on daily basis and submit to Engineer full and correct
information as to number of persons employed in connection with each subdivision of
work, classification, cost, source, and amount of each class of materials delivered,
equipment received, and major construction equipment used in each subdivision of work.
.4
When requested by Engineer, Contractor shall submit copies of each purchase order and
bill of material for materials and equipment furnished. Include supplier’s name,
manufacturer’s name, materials, type, model number, size, quantity, accessory list, and
requested delivery date of material and equipment ordered on each purchase order on
letter size paper arranged and bound in 3-ring binders organized by section number.
.10
Test Plan
.1
Contractor shall submit Test Plan including schedule and procedures for physical
checkout, shop testing, and field testing of equipment and systems.
.11
Record Drawings
.1
Contractor shall maintain and submit Record Drawings. Failure to maintain updated
Record Drawings may result in delaying Contractor’s monthly progress payments until
Record Drawings are updated.
.12
Construction Facilities Plan
.1
Contractor shall submit Construction Facilities Plan.
.13
Quality Control Plan
.1
Inspection at Place of Manufacture
1.
Products, materials and equipment are subject to inspection by Engineer at place
of manufacturer, unless otherwise indicated.
2.
Presence of Engineer at place of manufacturer does not relieve Contractor of
responsibility for furnishing product, materials, and equipment complying with
requirements of Contract Documents.
3.
Provide Engineer ten (10) business days advance notice of testing at place of
manufacturer, unless otherwise noted.
.2
Testing
1.
Carry out testing in accordance with specified methods in current standards of
ASTM, as applicable to class and nature of article or materials. Owner, however,
reserves right to use generally-accepted system of testing that, in opinion of
The City of Guelph
Lift Stations SCADA Upgrades
Page 7 of 9
November, 2008
Scope of Work – Section 16000
.3
.14
1.7
1.8
Engineer, will insure Owner that quality of workmanship meets requirements of
Contract Documents.
2.
Waiver by Owner of specific testing or other quality assurance measures,
whether or not such waiver is accompanied by guarantee of substantial
performance as relief from specified testing or other quality assurance
requirements as originally specified, and whether or not guarantee is
accompanied by performance bond to assure execution of necessary corrective
or remedial work, should not be construed as waiver of requirements of Contract
Documents.
3.
Engineer reserves right to make independent investigations and tests. Failure of
portion of work to meet requirements of Contract Documents is cause for
Engineer to require removal, correction and reconstruction of work in accordance
with Contract Documents.
Contractor’s Quality Control
1.
Arrange and pay for:
1.
Testing, adjusting and balancing of electrical and mechanical equipment
and systems.
2.
Mill tests and certificates of compliance.
3.
Inspection and testing required by laws, rules, regulations, ordinances
or orders of public authorities.
4.
Inspection and testing performed exclusively for Contractor’s
convenience.
5.
Bear cost of retesting further specimens should initial test specimens fail
to meet specified requirements.
Manufacturer’s Field Reports
.1
Contractor shall submit manufacturer’s field and installation services report.
Project Record Documents
.1
Engineer will provide two (2) sets of white prints for record drawing purposes to the Contractor.
.2
Contractor shall maintain project record drawings and record accurately deviations from Contract.
.3
Contractor shall mark changes in red.
.4
As a minimum, Contractor shall record following information:
.1
Horizontal and vertical location of Panels and appurtenances referenced to permanent
improvements.
.2
Location of Panels and appurtenances concealed in construction, referenced to visible
and accessible features of structure.
.3
Field changes of dimension and detail.
.4
Any wiring, location or design changes.
.5
At substantial performance of project and prior to inspection, neatly transfer notations to
second set and submit both sets to Engineer.
Operation and Maintenance Manuals
.1
Prepare six (6) copies of documentation including as-constructed shop drawings to instruct the
owner’s operations and maintenance staff in the operation and associated maintenance of each
piece of equipment and system as supplied and installed. The documentation shall be as follows:
Provide 210 x 280 mm binders ACCO #05426, hot stamped in white lettering on front and spine to
accommodate the documentation.
Volume 1 – Operations and Maintenance
The number of volumes shall be increased and renumbered as necessary to accommodate the
documentation. Each set shall be permanently numbered 1 to 6.
The cover and spine of the binders shall be lettered with the full identification title of the project, the
Owner’s full identification and contract number, the Engineer’s full identification, and the
Contractor’s full identification as follows:
The City of Guelph
Lift Stations SCADA Upgrades
Page 8 of 9
November, 2008
Scope of Work – Section 16000
City of Guelph
Lift Stations SCADA Upgrades
Contract No. XXXXX
Operations and Maintenance Manual
Engineer: Eramosa Engineering Inc.
General Contractor: __________
Volume __
Set __ of 6
.2
The binders shall be arranged to the Construction Specifications Institute Master Format – Master
List of Sections, Titles and Numbers utilizing laminated Mylar plastic divider tabs and colour coded
according to section. Colour shall be as follows:
.1
Division – white
.2
Systems – orange
.3
Certification and Testing – green
.4
Shop Drawings and Maintenance Bulletins – yellow
.5
Safety and Maintenance – red
.3
The following information shall be provided for each system and major piece of equipment. Each
piece of equipment shall be referred to by its tag number. Where manufacturer’s literature covers
several models or options, the applicable information shall be highlighted or redundant information
crossed out.
.1
Index of information in that section in order of appearance.
.2
Description of system, components and technical data. Include interfaces, sequences,
operational characteristics, and changes for seasonal operation.
.3
Maintenance and operating instruction.
.4
Recommended spare parts lists.
.5
Bill of Materials.
.6
Schematics, single line, and wiring diagrams (as-constructed).
.7
Service representatives – name, address, and telephone number.
.8
Suppliers for replacement parts – name, address, and telephone number.
.9
Test results, witness testing, and commissioning test results.
.10
Certification, guarantee, warranty.
.11
Troubleshooting data.
.12
Preventative maintenance program complete with suggested check list sheets.
.13
Inspection approval certificates for electrical system.
.4
Each binder shall be made up as follows:
Tab: Table of Contents – details the titles of various divisions of the included divider tabs.
Tab: Introduction to manual – provide written explanation of the layout of the manual and
intended use. Include separately the following:
Engineer: name, address, and telephone number.
Subcontractors: name, address, and telephone number.
Distributors: name, address, and telephone number.
Manufacturers: name, address, and telephone number.
.5
Tab: Operations Manual – the Contractor shall allow approximately 32 mm of binder thickness for
the Engineer’s Operation manual narrative at the beginning of each Volume 1 binder.
.6
Submit six (6) copies of operation and maintenance data two (2) weeks prior to substantial
performance.
END OF SECTION
The City of Guelph
Lift Stations SCADA Upgrades
Page 9 of 9
November, 2008
Electrical General Requirements – Section 16010
PART 1.
1.1
1.2
GENERAL
Description of Work
.1
The Contractor shall furnish all labour, material, tools, equipment, supervision and other services
as may be required to execute the work described in the specification and on the accompanying
drawings.
.2
Misinterpretation of any requirements of either the drawings or specifications will not relieve the
Contractor of responsibility to complete the work, if in doubt contact the Engineer for written
clarification prior to submitting tender price.
Site Examination
.1
1.3
1.4
1.5
Codes and Standards
.1
Do the complete installation in accordance with the latest edition of the Ontario Electrical Safety
Code. Confirm area classifications prior to commencing work.
.2
Comply with Ontario Hydro Inspection Electrical Bulletins in force at time of tender submission.
While not identified and specified by number in this Division, bulletins are to be considered as
forming part of related standards.
.3
Comply with current regulations of the National Building Code, and the requirements of all
applicable Municipal and Provincial Codes and regulations.
.4
Abbreviations for electrical terms: to CSA Z85-1983.
Permits and Fees
.1
Obtain and pay for all permits and fees required for the execution and inspection of the electrical
work and pay all charges incidental to such permits.
.2
Submit to Inspection Department of Electrical Supply Authority necessary number of drawings and
specifications for examination and approval prior to commencement of work. In addition, if required
by the Inspection Department of Electrical Supply Authority, prepare and submit any other drawing
required for approval.
.3
Arrange and pay for all special inspection of equipment specified as required.
Inspections
.1
1.6
Before submitting quotations, carefully examine all drawings and all specifications having a bearing
on the work, visit the site and thoroughly ascertain that the work can be carried out satisfactorily
without any changes to the drawings or specifications. No extras will be allowed for anything,
which would have been revealed in the course of such an examination.
Contractor to obtain all inspections required by code. Furnish a Certificate of Acceptance from
Inspection Department on completion of work. Correct installed work as directed by authorized
inspector of authorities having jurisdiction.
Cooperation of Trades
.1
Read complete specifications and drawings and conform with their requirements before proceeding
with any work specified in this Division related to other Divisions.
.2
Co-operate with all other trades on the job, so that all equipment can be satisfactorily installed, and
so that no delay is caused to any other trade.
The City of Guelph
Lift Stations SCADA Upgrades
Page 1 of 7
November, 2008
Electrical General Requirements – Section 16010
1.7
1.8
Materials and Equipment
.1
Use new materials and equipment unless otherwise specified.
.2
Provide material and equipment of specified design and quality, performing to published ratings
and for which replacement parts are readily available.
.3
Use products of one manufacturer or equipment for material of same type of classification unless
otherwise specified.
.4
Materials and equipment of manufacturer specified have been incorporated on the drawings with
space and area required for the respective manufacturer’s equipment.
.5
Equipment and materials to be CSA certified.
Equipment Withstand Ratings
.1
1.9
Shop Drawings
.1
1.10
1.11
All overcurrent protection shall be capable of interrupting the available fault current as per Rule 14012 of the OESC. All electrical equipment required to have a withstand rating shall be capable of
withstanding the available fault current as per Rule 2-034 of the OESC.
Submit shop drawings, as a minimum, in accordance with Division 16 for:
.1
Electrical - Trenches, Cabletrays & Power and Controls Cabling
.2
Control Panels, Network Equipment and Network Cabling
.3
PLC Components
.4
Integration Loop Drawings
.5
Instrumentation
.6
Lighting
Drawings
.1
Drawings, which accompany these Specifications, are diagrammatic and show the general location
of the electrical and instrumentation equipment.
.2
Do not scale Drawings but use only dimensions that are shown. Where exact building dimensions
and details are required, use only figured dimensions as shown on Drawings for jobsite
dimensions.
.3
Make changes or additions to the electrical/instrumentation system as dictated by the civil,
structural or mechanical conditions at no extra cost to the Owner.
Location of Electrical Equipment
.1
.2
.3
1.12
The location of any panel, equipment, outlet, raceway and wiring may be changed by the
Engineer if the new location is within a limit of 3100 mm radius of the original location.
Provide changes without extra cost if requested before installation in the original locations.
Confirm the exact locations of all equipment and devices on site to ensure mounting
heights, accessibility and ascertain location and elevations of connecting conduits, piping
and other interferences.
Confirm the location of all mechanical equipment, existing equipment and equipment
supplied by others in reference to the connections, locations and connection requirements
prior to the installation of conduit and wiring to the equipment.
Mounting Heights
.1
Mounting height of equipment is from finished floor to centreline of equipment unless specified or
indicated otherwise.
.2
If mounting height of equipment is not specified or indicated, verify before proceeding with
installation.
The City of Guelph
Lift Stations SCADA Upgrades
Page 2 of 7
November, 2008
Electrical General Requirements – Section 16010
.3
1.13
Install electrical equipment at following heights unless indicated otherwise.
.1
Local switches: 1300 mm
.2
Wall receptacles:
1.
General: 1300 mm
.3
Panelboards: as required by Code or as indicated.
.4
Wall mounted telephone outlets: 1500 mm
.5
Individual safety switches: 1300 mm
.6
Thermostats: 1300 mm
Labels and Signs
.1
Unless otherwise specified, signs shall comply with CAN/CSA-Z321-96 Signs and Symbols for the
Workplace.
.2
Manufacturer nameplates and CSA labels to be visible and legible after equipment is installed.
.3
Provide engraved lamacoid nameplates for all new, major electrical equipment such as disconnect
switches, panelboards, control panels, instrumentation etc.
.4
Lamacoid 3 mm thick plastic engraving sheet, black face, white core, mechanically attached with
corrosion resistant, self tapping screws.
.1
NAMEPLATE SIZES
1.
Size 1 10 x 50 mm
1 line
3 mm high letters
2.
Size 2 12 x 70 mm
1 line
5 mm high letters
3.
Size 3 12 x 70 mm
2 lines
3 mm high letters
4.
Size 4 20 x 90 mm
1 line
8 mm high letters
5.
Size 5 20 x 90 mm
2 lines
5 mm high letters
6.
Size 6 25 x 100 mm
1 line
12 mm high letters
7.
Size 7 25 x 100 mm
2 lines
6 mm high letters
.5
Provide warning signs as specified or to meet requirements of Ontario Electrical Safety Code.
.6
Wording on nameplates and labels to be approved by the Owner's representative prior to
manufacture.
.7
Nameplates for junction boxes, terminal boxes, pullboxes, etc., larger than 100 mm square to
indicate system and voltage characteristics.
.8
Field mounted control devices shall be identified by the equipment name, device control function
and panel number that provides the source of power.
.9
Individual pilot devices on control stations, contactors and starters shall be identified with small
lamacoid plates indicating the function that it provides.
.10
Transformers: nameplates to indicate designation, capacity, primary and secondary voltages.
.11
Panelboard nameplates to indicate designation, voltage and supply source.
.12
Control devices nameplate to indicate device tag, panel and PLC I/O number. Provide size 5
nameplate.
.13
Provide size 7 nameplate on all PLC panels indicating panel name, number, voltage, current,
frequency.
.14
Submit with the Shop Drawings, typed lists indicating all nameplate wording as well as proposed
size, colour, description to the Owner's representative for approval prior to ordering.
.15
Provide self adhesive labels within the interior of all control panels and control stations to indicate
the specific device (pushbutton, pilot light, etc.) reference number.
.16
Use the City’s tag identifier and designated service and with the approved wording submitted in
shop drawings. Instrument tag names conform to City’s conventions and to the P&ID issued.
Refer to the contract drawings for the correct tag prefixes, loop numbers and service descriptions.
The City of Guelph
Lift Stations SCADA Upgrades
Page 3 of 7
November, 2008
Electrical General Requirements – Section 16010
1.14
1.15
.17
Nameplates on field equipment and external to control panels to be black background with white
lettering. Internal panel labels to be black background and white lettering.
.18
Identify transducers and miscellaneous hardware with stainless steel labels denoting tag name
only. Permanently fastened to either the transducer housing or cable.
.19
Wiring:
.1
Identify all PLC I/O signals on field terminal rails with appropriate tag
.2
Identify all wiring at both ends with appropriate, permanent wire markers.
Sleeves, Inserts
.1
Contractor is responsible for supplying and setting of all sleeves and inserts for conduit.
.2
Floor sleeves, where required, shall extend 100 mm above floor. All sleeves to be made from
schedule 40 steel pipe.
.3
Seal all sleeves with an approved fire stop material after installation of all conduits. Ensure all
penetrations to hazardous location are sealed with EYS fittings to meet the requirements of the
OESC.
Concrete Bases, Curbs, and Steel Supports
.1
1.16
1.17
Contractor shall furnish and install all structural steel supports, platforms, braces, tie rods, etc.,
required to support or hang all equipment installed under the electrical contract. All supports shall
be attached to the building structure. Supporting electrical equipment, wiring, conduit, etc., from
ductwork, piping, equipment, etc., will not be accepted.
Cutting and Patching
.1
All cutting of openings to walls, floors, foundations, footings, ceilings, plaster and drywall ceilings,
roof or any other surfaces or finishes shall be performed by qualified tradesman specializing in that
particular field.
.2
All patching, painting and making good of walls, floors, ceiling, partitions and roof shall be done by
a qualified tradesman specializing in that particular field.
.3
Under no circumstances shall any cutting or burning of the structural parts of the building be
undertaken without the written authority of the Engineer.
.4
Provide patching and sealing of all new and existing openings for conduits passing through walls,
floors, ceiling and roof.
.5
At completion of installation of all electrical equipment the contractor is responsible for painting any
area around new equipment to match existing walls and any areas that are now exposed due to
equipment removal.
Grounding
.1
Provide all equipment grounding as required regardless whether it has been shown on the
drawings or called for in this specification as per the requirements of the Ontario Electrical Safety
Code.
.2
Arrange grounds so that under normal operating conditions no injurious amount of current will flow
in any grounding conductor.
.3
Include a separate ground wire to all devices, which are rewired and to all new devices. The
conduit system is not to be used as the sole grounding path.
.4
Bond to ground all exposed, non-current carrying metal parts of fixed equipment if the equipment is
located in a wet location and is not isolated or is located in a hazardous location, or as per the
OESC rule 10-400.
The City of Guelph
Lift Stations SCADA Upgrades
Page 4 of 7
November, 2008
Electrical General Requirements – Section 16010
1.18
1.19
Disconnection of Existing Equipment
.1
Contractor shall include for disconnecting and removal of all existing electrical/instrumentation
equipment and wiring within the existing facility that is to be relocated, decommissioned,
abandoned or not re-used.
.2
Include to disconnect and remove all electrical wiring and conduit back to the point of supply for all
equipment not being re-used.
.3
Include to remove all existing redundant conduit and wiring back to the point of supply and patch all
holes in existing walls, structures, bases, ceilings, etc., resulting from conduit removal.
.4
All removed electrical equipment, conduit and wire shall remain the property of the Owner and be
delivered to the Owner's designated storage location on the site or disposed of by the contractor at
the Owner’s discretion. Confirm with Engineer prior to removal.
.5
Include to relocate, make temporary connections, reinstall and reconnect any equipment as
required for the installation of the new equipment as required under this project.
.6
Refer to Division 16 for timing and phasing of the work. Include to make all temporary connections
as required to maintain station operation during the construction phases and equipment
replacement.
Control of Debris
.1
1.20
1.21
1.22
At all times keep the premise free from all accumulations of debris resulting from the electrical
work.
Continuity and Responsibility
.1
Schedule the electrical work so that disruption to the rest of the circuitry will be kept to a minimum.
Co-ordinate with the Owner to schedule shutdowns required for system connection for equipment
replacement.
.2
Obtain Owner’s authorization when a circuit is to be de-energized or energized.
.3
Ensure service continuity to existing circuits not affected by the construction work. Make temporary
connections if necessary.
.4
Contractor is responsible for any damage resulting from modifications to existing facilities such as
underground cables, hard surface areas, watermains, and other utilities. Contractor to restore,
replace or repair all such damage to the satisfaction of the Engineer. Wherever possible obtain
locates prior to commencing work.
Load Balance
.1
Measure phase current to panelboards with normal loads operating at time of acceptance. Adjust
branch circuit connections as required to obtain best balance of current between phases and
record changes.
.2
Measure phase voltages at loads and adjust transformer taps to within 2% of rated voltage of
equipment.
.3
Submit, at completion of work a report listing phase and neutral currents on panelboards,
transformers and motor controls operating under normal load. State hour and date on which each
load was measured, and voltage at time of test.
Field Quality Control
.1
Test electrical equipment and systems for electrical or mechanical defects and rectify same prior to
requesting inspection by the Owner's representative.
The City of Guelph
Lift Stations SCADA Upgrades
Page 5 of 7
November, 2008
Electrical General Requirements – Section 16010
1.23
1.24
.2
At completion of the work, test ground resistance and voltage in the presence of the Owner's
representative. Make corrections where necessary and as directed at no additional cost to the
Owner. Give adequate notice to the Owner's representative prior to the date of the test.
.1
Perform insulation tests for all equipment and wiring using a Megger insulation tester
suitably rated for the equipment to be tested.
.2
Control wiring shall be Megger tested before conductors are terminated on the controller.
.3
Instrument and data transmission cables shall not be Megger tested but checked for
continuity only. All Ethernet cabling (copper/Fiber) to be tested to TIA/EIA standards for
Category 6 certification.
.4
Defective wiring shall be replaced prior to submission of final results.
.5
Record readings obtained for reference and deliver a set to the Engineer.
.3
Under no circumstances is power to be applied to the equipment until the Owner's representative
and equipment manufacturer's representative are present on site to supervise the testing and startup procedures.
.4
Under the direction of Owner's representative and manufacturer's representative, check all settings,
wiring, grounding and motor rotation.
.5
Adjusting and start-up:
.1
Contractor shall conduct acceptance tests to demonstrate that the equipment and systems
meet the specified requirements. Preliminary tests may commence as soon as conditions
permit. Contractor shall make all changes, adjustments, or replacements required as the
preliminary tests may indicate prior to the final tests.
.2
Tests shall be as specified in various sections of this Specification.
.3
Carry out tests in presence of Engineer, Owner or his representative.
.4
Provide instruments, meters, equipment and personnel required to conduct tests during
and at conclusion of project.
.5
Contractor shall be in charge of the system during tests. He shall assume responsibility
for damages in the event of injury to the personnel, building, equipment, and shall bear all
costs for liability, repairs, and restoration in this connection.
.6
Verify correct voltages on all transformer primary and secondary connections at No-Load.
Adjust transformer tap changes as required in order to achieve nominal voltage required
for equipment operation. Verify transformer voltages under operation with connected load
applied.
.7
Submit directly to the Owner's representative two (2) bound portfolio's containing all test
reports, certified by the testing technician and the Owner's representative authorized to
witness the tests.
Safety
.1
Contractor shall be responsible for the safety of his workmen and the equipment on the project in
accordance with all applicable safety legislation passed by Federal, Provincial, and local authorities
governing construction safety. The more stringent regulations shall prevail.
.2
Contractor is to work in accordance of all safety regulations such as, but not limited to, confined
space entry and arc flash.
Workmanship
.1
Only first class workmanship will be accepted, not only in regards to durability, efficiency and
safety, but also in regards to neatness of detail. Present a neat and clean appearance on
completion to the satisfaction of the Engineer. Any unsatisfactory workmanship shall be replaced
by Contractor at no extra cost.
.2
Conform to the best practices applicable for this type of work. Install all equipment and systems in
accordance with the manufacturer's recommendations, but consistent with the General
Requirements of this Specification.
.3
Unless otherwise noted, all equipment shall be factory finished with a prime coat and two coats of
good quality finish paint.
The City of Guelph
Lift Stations SCADA Upgrades
Page 6 of 7
November, 2008
Electrical General Requirements – Section 16010
1.25
.4
Minor damages to finish on factory finished equipment shall be touched up to the Engineer’s
satisfaction. Items suffering major damage to finish shall be replaced at the direction of the
Engineer.
.5
Protect work so that finishes will not be damaged or marred during construction. Maintain the
necessary protection until completion of the work.
.6
Store all electrical equipment and materials in dry locations. Confirm location does not interfere
with daily operations of the facility.
.7
Contractor shall not employ an unfit person and shall not employ anyone not skilled in the work
assigned to him.
Cleaning
.1
Conduct cleaning and disposal operations to comply with local ordinance and antipollution laws,
including requirements of WHMIS.
.2
Prevent accumulation of waste which creates hazardous conditions.
.3
Maintain the work during construction, at least on a daily basis free from the accumulations of
waste materials and debris.
.4
Provide on-site containers for collection of waste materials and debris.
.5
Schedule cleaning operations so that resulting dust, debris and other contaminants will not fall on
wet, newly painted surfaces nor contaminate building systems.
.6
Vacuum clean all building interiors prior to paint application. Continue to vacuum clean finished
areas until final completion.
.7
Final Cleaning
.1
In preparation for acceptance of the project on an Interim or Final Certificate of
Completion, perform final cleaning.
.2
Remove grease, dust, dirt, stains, fingerprints and other foreign materials from interior and
exterior finished surfaces including glass and other polished surfaces.
.3
Cleaning lighting reflectors, lenses and other lighting surfaces.
.4
Broom clean paved surfaces and floors; rake clean other surfaces of ground.
.5
Remove debris and surplus materials from crawl areas and other accessible concealed
spaces.
.6
Restore any damaged grass by seeding or sodding to match existing site conditions.
END OF SECTION
The City of Guelph
Lift Stations SCADA Upgrades
Page 7 of 7
November, 2008
Fastenings and Support – Section 16071
PART 1.
1.1
GENERAL
Summary
.1
PRODUCTS
PART 2.
2.1
Support Channels
.1
U shape, size 41x41mm, 2.5mm thick, surface mounted, unless otherwise indicated.
.2
Every raceway and cable shall have at least one support and a maximum spacing of 3000 mm.
Use only approved conduit hangers and cable clamps. Perforated pipe straps, tie wires and other
such items will not be permitted.
PART 3.
3.1
Comply with Section 16010 – Electrical General Requirements.
EXECUTION
Installation
.1
Secure equipment to solid masonry, tile and plaster surfaces with lead anchors or nylon shields.
.2
Secure equipment to poured concrete with expandable inserts.
.3
Secure surface mounted equipment with twist clip fasteners to inverted T bar ceilings. Ensure that
T bars are adequately supported to carry weight of equipment specified before installation.
.4
Support equipment, conduit or cables using clips, spring loaded bolts, cable clamps designed as
accessories to basic channel members.
.5
Fasten exposed conduit or cables to building construction or support system using straps.
.1
One-hole steel straps to secure surface conduits and cables 50mm and smaller
.2
Two-hole steel straps for conduits and cables larger than 50mm
.3
Beam clamps to secure conduit to expose steel work.
.6
Suspended support systems.
.1
Support individual cable or conduit runs with 6 mm dia threaded rods and spring clips.
.2
Support 2 or more cables or conduits on channels supported by 6 mm dia threaded rod
hangers where direct fastening to building construction is impractical.
.7
For surface mounting of two or more conduits use Unistrut channels at 10m oc spacing.
.8
Provide metal brackets, frames, hangers, clamps and related types of support, structures where
indicated or as required to support conduit and cable runs.
.9
Support vertical runs of cables every 1800mm.
.10
Support horizontal runs of cables every 1200mm.
.11
Ensure adequate support for raceways and cables dropped vertically to equipment where there is
no wall support.
.12
Do not use wire lashing or perforated strap to support or secure raceways or cables.
.13
Do not use supports or equipment installed for other trades for conduit or cable support except with
permission of other trade and approval of client.
.14
Install fastenings and supports as required for each type of equipment cables and conduits, and in
accordance with manufacturer’s installation recommendations.
END OF SECTION
The City of Guelph
Lift Stations SCADA Upgrades
Page 1 of 1
November, 2008
Wiring Devices – Section 16141
PART 1.
1.1
GENERAL
Shop Drawings and Product Data
.1
PRODUCTS
PART 2.
2.1
2.2
Submit shop drawings and product data in accordance with General Conditions.
Switches
.1
15A, 120V, single pole and three-way switches.
.2
Manually-operated general purpose AC switches with following features:
.1
Terminal holes approved for No. 10 AWG wire.
.2
Silver alloy contacts.
.3
Urea or melamine molding for parts subject to carbon tracking.
.4
Suitable for back and side wiring.
.5
Ivory toggle.
.3
Toggle operated fully rated for tungsten filament and fluorescent lamps, and up to 80% of rated
capacity of motor loads.
.4
Hazardous locations: Products approved for the specific area classification and wiring application.
.5
Switches of one manufacturer throughout project.
.6
Acceptable manufacturers: Leviton, Hubbell, Appleton.
Receptacles
.1
Duplex receptacles, CSA type 5-15 R, 125 V, 15 A, U ground, with following features:
.1
Ivory urea molded housing.
.2
Suitable for No.10 AWG for back and side wiring.
.3
Break-off links for use as split receptacles.
.4
Eight back wired entrances, four side wiring screws.
.5
Triple wipe contacts and riveted grounding contacts.
.2
Single receptacles CSA type 5-15 R, 125 F, 15 A, U ground with following features:
.1
Ivory urea molded housing.
.2
Suitable for No.10 AWG for back and side wiring.
.3
Four back wired entrances, 2 side wiring screws.
.3
UPS receptacles CSA type NEMA 5-20 R, 120 V, 20A, U ground with following features:
.1
Ivory urea molded housing.
.2
Suitable for No.10 AWG for back and side wiring.
.3
Four back wired entrances, 2 side wiring screws.
.4
Other receptacles with ampacity and voltage as indicated.
.5
Receptacles with ground fault circuit interrupters of the Class A type shall be installed within 3
meters of any water sources and where indicated on the drawings.
.6
Receptacles installed outside or that may be exposed to weather shall be provided with
weatherproof cover plates fitted so as to make a proper weatherproof seal.
.7
Receptacles of one manufacturer throughout project.
.8
Acceptable manufacturers: Leviton, Hubbell, Appleton.
.9
Six (6) receptacle power bar: Trip-Lite Isotel 6 Ultra, or approved equivalent.
The City of Guelph
Lift Stations SCADA Upgrades
Page 1 of 3
November, 2008
Wiring Devices – Section 16141
.10
2.3
Ethernet pass through connector, RJ045 and 120VAC receptacle: Phoenix Contact 5500521, or
approved equivalent.
Special Wiring Devices
.1
2.4
2.5
Wiring Devices for Computer Rooms
.1
Computer receptacles to be connected using isolated ground and having orange colour.
.2
All receptacles in computer/control room to be split receptacles.
Cover Plates
.1
Cover plates for wiring devices.
.2
Cover plates from one manufacturer throughout project.
.3
Sheet steel utility box cover for wiring devices installed in surface-mounted utility boxes.
.4
Plastic ivory cover plates, thickness 2.5mm for wiring devices mounted in flush-mounted outlet box.
.5
Sheet metal cover plates for wiring devices mounted in surface-mounted FS or FD type conduit
boxes.
.6
Weatherproof double lift spring-loaded cast aluminum cover plates, complete with gaskets for
duplex receptacles as indicated
.7
Weatherproof spring-loaded cast aluminum cover plates complete with gaskets for single
receptacles or switches.
PART 3.
3.1
Special wiring devices:
.1
Clock hanger outlets, 15 A, 125 V, 3 wire, grounding type, suitable for No. 10 AWG for
installation in flush outlet box.
.2
Electric shaver outlets, 15 A, 125 V, ac with 20 VA isolating transformer with stainless
steel cover plate marked RAZOR ONLY.
.3
Pilot lights as indicted, with neon type 0.04 W, 125 V lamp and red plastic lense flush type.
EXECUTION
Installation
.1
Switches:
.1
Install single throw switches with handle in “UP” position when switch closed.
.2
Install switches in gang type outlet box when more than one switch is required in one
location.
.3
Mount toggle switches at height specified in Section 16010 – Electrical General
Requirements or as indicated.
.2
Receptacles:
.1
Install receptacles in gang type outlet box when more than one receptacle is required in
one location.
.2
Mount receptacles at height specified in Section 16010 – Electrical General Requirements
or as indicated.
.3
Where split receptacle has one portion switched, mount vertically and switch upper
portion.
.3
Cover plates:
.1
Protect stainless steel cover plate finish with paper or plastic film until painting and other
work is finished.
.2
Install suitable common cover plates where wiring devices are grouped.
.3
Do not use cover plates meant for flush outlet boxes on surface-mounted boxes.
The City of Guelph
Lift Stations SCADA Upgrades
Page 2 of 3
November, 2008
Wiring Devices – Section 16141
.4
Contractor to submit a conduit routing and layout plant for the low voltage for review by the
Engineer prior to commencing work.
END OF SECTION
The City of Guelph
Lift Stations SCADA Upgrades
Page 3 of 3
November, 2008
Wires and Cables (0-1000V) – Section 16122
PART 1.
1.1
1.2
1.3
1.4
GENERAL
Summary
.1
Comply with Section 16010 – General Electrical Requirements.
.2
Conform to Owner’s Standards, including SCADA Standards, where applicable.
Reference
.1
CSA C22.2 No. 131 Type TECK 90 Cables.
.2
CSA C22.2 No. 38 Thermoset Insulated Wires and Cables.
.3
CSA C22.2 No. 174 Cables and Cable Glands for use in Hazardous Locations.
.4
CSA C68.3 Power Cables with Thermoset Insulation.
.5
CSA C21.1 600 V Control Cable.
.6
CSA C21.2 300 V Control Cable.
Submittals
.1
Submit within three weeks of contract award shop drawings of the proposed complete conduit, tray,
bus and cable layout system to be installed or modified, showing dimensional layouts construction
details, and wiring between equipment and devices for approval.
.2
Submit final record conduit layout diagrams at completion of project. Include changes made during
field installation and start-up.
Design Requirements
.1
Number and sizes of wires and associated raceways indicated are a guide only and are not
necessarily the exact number and sizes required. Wire or cable sizes smaller than indicated are
not acceptable.
.2
Unless otherwise indicated, combine motor or electric heater branch power wiring (below 1000 V
systems) and associated local operator control or field control device wiring into a common conduit
between motor or heater and its start or motor control centre, provided all of the following
conditions are met
.1
Motor circuit voltage not to exceed 600 V.
.2
Conductors and termination fittings for power and control circuits are rated 600 V
minimum.
.3
Control circuits are designed to operate at 120 VAC or higher. Install wiring for control
circuits operating below 100 VAC or with DC in a separate conduit system.
.4
Power conductors do not exceed #2 AWG in size.
.5
Control circuit wiring solely associated with respective motor or heater. Install wiring for
control circuits of other equipment and systems, or wiring common to two or more pieces
of equipment in separate conduits.
.3
Supply spare conductors in control, communication and instrumentation cable circuits as follows:
.1
20% or two (2) spare conductors per conduit, whichever is greater.
.4
Wire smaller than #12 gauge shall not be used except for control signals.
.5
No control wire smaller than No. 14 AWG shall be used except where so indicated on the drawings
or as specified in other Sections.
.6
Wire and cable shall be colour coded as follows:
.1
Line and load circuits 120 Vac power - 1 phase - Black (Hot) - White (Neutral)
.2
TECK 90 - 600V Black
The City of Guelph
Lift Stations SCADA Upgrades
Page 1 of 9
November, 2008
Wires and Cables (0-1000V) – Section 16122
.3
.4
.5
.6
.7
.8
.9
.10
1.5
Storage
.1
Cap cable ends to prevent water penetration into cable. Reseal after cutting length of cable.
.2
Cables stored with ends unsealed will be immediately removed from site at contractors cost. At no
extra cost to the Owner, replace cables to the satisfaction of the Engineer.
PRODUCTS
PART 2.
2.1
Lighting - White – Grounded, Neutral Conductor, Red, Black, Blue – Ungrounded
Conductor
AC control circuits – Red
DC control circuits – Dark Blue
Analogue Twisted Pairs - White (+) and Black (-)
DC signal grounding conductors - Green/White Stripes
Equipment grounding conductors – Green
Foreign source interlock control circuits – Yellow
Intrinsically safe circuits – Light Blue
Manufactured Products
.1
Comply with standards.
.2
Low Voltage Unarmoured Wire and Cable (1000 V and Below).
.1
Acceptable manufacturers: Phillips Cables Limited, Alcatel Canada Wire Inc., Pirelli
Cables Inc., United Wire of Canada.
.2
Construction: Stranded, annealed copper conductors, 1000 V, rating RWU90 cross-linked
polyethylene (XLPE) insulation for all cables outside of buildings and RW90 cross-linked
polyethylene (XLPE) insulation for cables within the building unless noted otherwise.
.3
Direct buried installations or installation in direct buried polyethylene pipe: Cross-linked
polyethylene (XLPE), RWU90 insulation, 1000 V minimum rating.
.4
Standard: CSA C22.2 No. 38.
.5
Minimum conductor sizes: Unless otherwise indicated, #12 AWG for power and current
transformer circuit.
.6
Multi-conductor cables: PVC flame retardant jacket overall, flame test rated.
.3
Low Voltage Unarmoured Wire and Cable (600 V and Below).
.1
Acceptable manufacturers: Phillips Cables Limited, Alcatel Canada Wire Inc., Pirelli
Cables Inc., United Wire of Canada.
.2
Construction: Stranded, annealed copper conductors, 600 V rating, UL1015-105°C PVC
insulation for indoor applications.
.3
Standard: CSA
.4
Minimum conductor sizes: Unless otherwise indicated, #12 AWG for power and current
transformer circuit.
.5
Multi-conductor cables: PVC flame retardant jacket overall, UL-VW-1 vertical flame test
rated.
.4
Low Voltage Armoured Wire and Cable (1000 V and Below).
.1
Acceptable manufacturers: Phillips Cables Limited, Alcatel Canada Wire Inc., Pirelli
Cables Inc., United Wire of Canada.
.2
Construction: Stranded, annealed copper conductors, 1000 V rating, RW90 cross-linked
polyethylene (XLPE) insulation.
.3
Power cabling: TECK construction.
.4
Control cabling: TECK construction.
.5
Minimum conductor size: Unless otherwise indicated, #12 AWG for power and current
transformer circuits and #14 AWG for control and fire alarm circuits.
.6
Grounding conductor: Standed, soft, bare copper conductor in multiconductor cables,
concentric copper wires over insulation in single conductor cable.
.7
Multi-conductor cables: With inner PVC jacket.
.8
Interlocking armour: Flexible, galvanized steel or aluminum for multi-conductor cables
and aluminum for single conductors, spirally wound over inner jacket.
The City of Guelph
Lift Stations SCADA Upgrades
Page 2 of 9
November, 2008
Wires and Cables (0-1000V) – Section 16122
.9
.10
Outer jacket: PVC, flame-retardant, FT4 flame test rated, low acid gas evolution, outer
jacket extruded over the armour.
Hazardous area installations: Where indicated, TECK cables and fittings accepted for the
application. Stamp outer jacket, “HL”.
.5
Low Voltage Armoured Cable for VFD Application
.1
Designed to reduce high frequency noise interference with data and controls signals.
.2
Three bonding conductors - soft bare copper.
.3
Cross-linked polyethelene RW90 insulation on main conductors.
.4
Continuously corrugated, corrosion resistant aluminum sheath with matching connectors.
.5
With overall PVC jacket rated FT4.
.6
As manufactured by Nexans "DriveRx" with "D" or "W" connectors or equivalent.
.6
RTD Cables
.1
Belden 8770
1.
#18 AWG.
2.
16-stranded copper.
3.
Beldfoil aluminum polyester shield.
4.
Twisted shielded pair.
5.
Bare #20AWG copper drain wire.
.7
RS-485 Cables
.1
EIA Industrial RS-485
.2
Conductors: Twisted pair, each conductor No. 22 AWG stranded copper
1.
Pairs: 2.
2.
Shield: Aluminum-polyester and 90% copper tinned braid.
3.
Jacket: Black UV resistant PVC.
4.
Electrical Characteristics at 20oC.
1.
Capacitance: 36.1 pF/m
2.
Impedance: 120 ohms
3.
Propagation Velocity: 78%
5.
Belden Datalene Insulated 3107A.
.8
CAT6 Cables
.1
Conform with the requirements of the TIA/EIA 568-B specification for Category 6
Unshielded Twisted Pair (UTP) cable:
1.
Cable shall be tested up to 200MHz with a guaranteed performance that meets
or exceeds the ANSI/TIA/EIA-568B/ISO/IEC 11801 horizontal cable requirements
for PS-NEXT, attenuation, structural return loss and attenuation to crosstalk ratio
(ACR).
2.
Constructed from 0.54mm (24AWG), bare copper wire insulated. Two (2)
insulted conductors twisted together to form a pair and four (4) pairs laid up to
form the basic unit.
3.
Cable shall be jacketed in flame retardant PVC. Cable run in conduit shall meet
or exceed FT4 rating. Cable not run in conduit shall meet or exceed FT6 rating.
4.
Cabling run in conduit shall be Belden #24566945 or approved equal.
5.
Cabling not run in conduit shall be FT6 rated Belden #24567945 or approved
equal.
.9
Instrumentation Cables (4-20mA)
.1
Belden #22416
1.
#16 AWG.
2.
7x24-stranded copper.
3.
Beldfoil aluminium polyester shield.
4.
Twisted shielded pair.
5.
Bare #18AWG copper drain wire.
.10
Serial Cables
.1
Belden #9945
1.
#22AWG.
2.
7-stranded copper.
3.
Overall Beldfoil aluminium polyester shield plus 65% minimum tinned copper
braid shield.
The City of Guelph
Lift Stations SCADA Upgrades
Page 3 of 9
November, 2008
Wires and Cables (0-1000V) – Section 16122
4.
5.
9 conductors. Select Belden trade number to suit number of conductors required
for the specific application – Belden #99xx.
EIA RS-232 applications.
.11
Fiber Optic Cable
.1
Fibre terminations to be in wall mounted network access closets. Panduit FRME3 36/72
Fibre Optic Rack Mount Enclosure, Panduit FAP3WEIDSC SC Multimode Duplex Fibre
Adapter Panel, Panduit FAP3WBUDSCZ Singlemode Duplex Fibre Adapter Panel.
.2
Fiber count to be 24 strands minimum.
.3
Fiber Optic Cable to be as manufactured by Optical Cable Corporation 24 Channel Hybrid
tight buffered distribution fibre optic cable type OFNR P/N DX24-085D-12WLX12SLX/900-OFNR-WB Laser Ultra Fox.
.4
Fiber Performance: Multimode: 62.5/125um core/cladding, Single Mode: 8.3/125um
core/cladding.
.5
Minimum LED Bandwidth: 200/500- MHz*km.
.6
Tensile Load (Installation): 3000N.
.7
Tensile Load (Operating): 1000N.
.8
Minimum Installation Bend Radius: 12.75cm.
.9
Minimum Operating Bend Radius: 8.5cm.
.10
Jacket: Flame Retardancy UL Listed Type OFNR (1666).
.12
Control Wiring
.1
For instruments: 4-20mA dc circuits shall be wired with #16 twisted
shielded pair in separate conduit, maintain minimum 300mm clearance between
instrumentation conduits (4-20mAdc circuits) and conduits carrying control and power
circuits (120V and up).
.13
Wiring Accessories
.1
Wire Markers: Identify all wiring with heat shrinkable slip-on markers c/w type written tag
numbers, black letters on white background. PHM 2 by Thomas & Betts Ltd., or approved
equivalent
.2
Cable markers: For cables or conductors greater than 13 mm diameter, strap-on type,
semi rigid PVC carrier strip. Type K by Wieland Electric Inc.
.3
Terminal blocks: 600 V, 25 A minimum rating, modular, 35 mm DIN rail mounted,
provision for circuit number labelling, individually removable, sized to accommodate
conductor size and circuit current. UK Series by Phoenix Terminal Blocks Ltd., Entrelec,
Sak Series by Weidmuller Ltd., WK Series by Wieland Electric Inc.
.4
Fused Terminal Blocks: 300 V, 25 A minimum rating, modular, 35 mm DIN rail mounted,
provision for circuit number labelling, individually removable, sized to accommodate
conductor size and circuit current., 5x20mm fuse, 100-250V AC/DC with Blown Fuse
Indication, KDKS Series by Weidmuller Ltd., or approved equivalents from Phoenix
Terminal Blocks Ltd., Entrelec, Wieland Electric Inc.
.5
Field wiring terminations: Where screw-type terminal blocks are provided, supply
insulated fork tongue terminals. Sta-Kon by Thomas & Betts Ltd., Scotchlok by 3M
Canada Inc.
.6
Splice connectors for equipment pig-tail, lighting and receptacle circuits: For wire sizes
#12 and #10 AWG inclusive, twist-on compression spring type. Wing-Nut by Ideal.,
Marrette Type II by Marr Electric Ltd.
.7
Moisture and waterproofing: In wet locations, with Liquid Tape by Ideal.
.8
Equipment pig-tail power circuit connections: For wire sizes #8 AWG minimum, split-bolt
type, sized to suit number and size of conductors. Servit Type KS by Burndy Inc.
.9
Low voltage (1000 V and lower) motor terminations: Heat shrinkable connection kit,
including sleeves, caps and sealant. Type MCK by Raychem Canada Ltd.
.10
Cables ties: Nylon, one-piece, self-locking type, by Thomas & Betts Ltd., Burndy Inc.,
Wieland Electric Inc.
.11
TECK cable connectors in hazardous locations: Approved for application.
.12
TECK cable connectors in wet or outdoor areas: Watertight type.
.13
Electrical insulating tape: Scotch 33 by 3M Canada Inc.
.14
Cable grips: To accommodate type and geometry of cable supported, single weave,
variable mesh design, by Thomas and Betts Ltd., Crouse Hinds, Woodhead Canada Ltd.
.15
Cable pulling lubricant: Compatible with cable covering and not to cause damage or
corrosion to conduits or ducts. Yellow 77 by Ideal.
The City of Guelph
Lift Stations SCADA Upgrades
Page 4 of 9
November, 2008
Wires and Cables (0-1000V) – Section 16122
PART 3.
3.1
3.2
EXECUTION
Coordination
.1
Prior to installation of wiring, compare Contract Drawings with latest issue of Vendor shop
drawings.
.2
Report discrepancies promptly to Engineer.
Installation
.1
All wire and cable must be sized and installed in accordance with the OESC Requirements.
.2
Provide wires of number and size (including corresponding raceways) required, with space
conductors as indicated. Provide adequate wiring for actual equipment installed.
.3
Provide wire and cable according to the Drawings and electrical system requirements.
.4
Pull cable into ducts, conduits and cable trays in accordance with cable manufacturer’s
recommendations. Use patented cable grips suitable for cable type, or pulling eyes fastened
directly onto cable conductors.
.5
Limit pulling tension and minimum bending radii to those recommended by manufacturer.
.6
Prevent damage to cable jackets by utilizing adequate lubricant when pulling cables through ducts
and conduits.
.7
Support cables in manholes and utility tunnels on cable trays or cable racks.
.8
Arrange cables in parallel rows on cable trays. Maintain cable spacing by fastening cables, with
cable ties, every 2000 mm minimum on straight horizontal runs and to each rung at bends,
including two rungs of adjoining straight sections. Fasten cables on vertical tray runs every 1000
mm.
.9
Connect cables to electrical boxes and equipment enclosures located in wet or sprinkled areas with
watertight cable connectors.
.10
Provide cable grips for vertical, horizontal and catenary cable suspension installations to reduce
cable tension at connectors and at cable bends.
.11
Install through wiring in junctions and pull boxes having no connection within the box. Leave 150
mm minimum of slack inside box.
.12
Facilitate making of joints and connections by leaving sufficient slack in each conductor at
panelboards, outlet boxes and other devices.
.13
Do not connect more than three lighting circuits for three phase panels and two lighting circuits for
single phase panels to a common neutral.
.14
Use #10 AWG minimum for home runs to lighting panels exceeding 25 m.
.15
Install instrumentation signal and thermocouple extension wires in separate raceways from power
and control wiring.
.16
Provide mechanical protection for cables within 1500 mm of the floor in buildings and within 2000
mm above grade outdoors.
.17
Identify each cable by attaching a cable marker at each end, in all intermediate manholes, junction
boxes and pull boxes.
.18
Install cables to conserve headroom in exposed locations and to cause minimum interference in
spaces through which they pass.
.19
Do not install horizontal runs in hollow masonry walls.
The City of Guelph
Lift Stations SCADA Upgrades
Page 5 of 9
November, 2008
Wires and Cables (0-1000V) – Section 16122
3.3
.20
Passage through any structural member or precast slab must be approved by the Engineer.
.21
Where exposed, install raceways and cables parallel with building lines and group neatly.
.22
Maintain the integrity of all fire separations by sealing around all cables where they pass through
any fire barriers. Generally this includes all floors ceilings and concrete and masonry walls.
.23
As far as is practicable, all feeder wiring shall be continuous from origin to panel termination without
running splices in intermediate pull boxes or splicing chambers. Sufficient slack shall be left at the
termination point to make proper connections to the equipment.
.24
Do not embed armoured cables in concrete.
.25
Conform with the following for Patch Cords:
.1
Provide CAT06 unshielded twisted pair (UTP) RJ45 patch cords complete with cable
strain relief connector boots, factory assembled and tested by the manufacturer.
.2
Certify that the patch cords supplied under this Contract meet or exceed the requirements
for CAT06 UTP patch cords. Provide written certification from the manufacturer at the time
of shop drawing review.
.3
The Contractor is responsible for determining the length of patch cords.
.4
Use durable non-fading sleeve type wire markers to identify all network cables. Identify
both ends.
.5
Provide 2 – 3 meter CAT06 UTP patch cords complete with connector boots spare and
leave in the print pocket of the ICP.
Testing
.1
Cable and Wire – 1000 Volt and Below
.1
Conduct insulation resistance measurements using a “Megger” (500 V instrument for
circuit up to 350 V system, 1000 V instrument for 351-600 V systems).
.2
Record test results in a log book and submit to Engineer for reference. Replace or repair
circuits which do not meet inspection Authority requirements. With equipment
disconnected, measure insulation resistance of the following circuits:
1.
Power, lighting, heater and motor feeders: Phase-to-phase, phase-to-ground.
2.
Control circuits: To ground only.
.3
Do not perform “Megger” tests on equipment containing solid-state components.
.4
Disconnect power factor correction capacitors from system prior to testing.
.2
Instrumentation and Thermocouple Extension Wiring
.1
Check continuity of each conductor using ohmmeter of DC buzzer. Megger or 120 volt
filament lamp testing is not acceptable.
.2
Test thermocouple wiring for continuity and polarity in accordance with manufacturer’s
recommendations.
.3
Fibre Optic Cables
.1
This section specifies the inspection, test, and acceptance requirements for the structured
cabling of the Process Control System (PCS) Local Area network.
.2
Provide all of the test equipment required to conduct acceptance tests.
.3
Submit acceptance documentation as defined in this section.
.4
All of the installed cabling must be tested and successfully pass all test criteria.
.5
Standards referenced in this section include:
1.
TIA/EIA-568-B: Telecommunications Cabling Standard. All standards referenced
within the TIA/EIA-568-B, where applicable, constitute standard provisions of this
specification.
2.
TIA/EIA-526-14-A: Optical Power Loss Measurement, Multimode
.6
Visually inspect all cables, cable reels, and shipping cartons to detect possible cable
damage incurred during shipping and transport. Visibly damaged goods are to be returned
to the supplier and replaced at no additional cost to the City.
.7
The City reserves the right to conduct, using Contractor equipment and labour, a random
re-test of up to five (5) percent of the cable plant to confirm documented results. Any failed
cabling shall be re-tested and restored to a passing condition. In the event more than two
(2) percent of the cable plant fails during re-test, the entire cable plant shall be re-tested
and restored to a passing condition at no additional cost to the Owner.
The City of Guelph
Lift Stations SCADA Upgrades
Page 6 of 9
November, 2008
Wires and Cables (0-1000V) – Section 16122
.8
.9
.10
.11
.12
.13
Acceptance shall be subject to completion of all work, successful post-installation testing
which yields 100% PASS rating, and receipt of full documentation as specified.
The City may agree to allow certain cable runs to exceed acceptable standardised
performance criteria. If required these cable runs will be exempt from meeting the
specified standards. However, the Contractor will still be required to test these cable runs
to validate component and installation performance.
Backbone Fibre Optic Testing
1.
Backbone fibre optic cable shall meet or exceed the permanent link, performance
requirements specified in TIA/EIA-568-B.3 for 50/125, multi-mode fibre.
2.
Test link attenuation in accordance with TIA/EIA-526-14A. make reference
measurements in accordance with method B or equivalent. Measure optical loss
on each fibre at 850 nm and 1300 nm. Measure loss on each fibre from each
direction (bi-directionally).
3.
Measure link length optically or calculate using cable sheath length markings.
4.
Backbone fibre optic cabling shall meet the following loss and length criteria:
1.
Attenuation @ 850 nm shall be less than or equal to: fibre length (km) x
3.75 dB/km + number connector pairs x 0.75 dB + number of splices x
0.3 dB.
2.
Attenuation @ 1300 nm shall be less than or equal to: fibre length (km)
x 1.50 dB/km + number connector pairs x 0.75 dB + number of splices x
0.3 dB.
3.
Length shall be less than or equal to 2000 metres.
Fibre Optic Test Equipment
1.
All test equipment of a given type shall be from the same manufacturer, and have
compatible electronic results output. Acceptable test equipment manufacturers
are Fluke, HP, or MicroTest.
2.
Fibre optic test equipment shall meet the following minimum criteria.
1.
Test equipment shall be capable of measuring relative or absolute
optical power in accordance with TIA/EIA-526-14A, "Optical Power Loss
Measurement of Installed Multimode Fibre Cable Plant."
2.
Test equipment shall not include the loss or length of the test jumpers in
the cable plant measurements.
3.
Multimode test equipment shall incorporate both 850 nm and 1300 nm
sources. The coupled output power into multimode fibre shall be >= -20
dBm at each wavelength. Detectors shall have a dynamic range of at
least +3 dB to -55 dB.
4.
Sources and meters shall automatically synchronize wavelengths to
prevent calibration-related errors.
5.
Test equipment shall employ a serial port to facilitate uploading of saved
information from tester to PC.
6.
The time-of-flight methodology shall be employed when optically
measuring fibre length.
7.
Test equipment capable of measuring a Tx/Rx fibre pair simultaneously
is recommended to enhance productivity.
Cable Test Results Manual
1.
Submit test reports in both a hardcopy and electronic format. Hand-written test
reports are not acceptable. Submit electronic files on a CD format disk in a PDF
format. If test results cannot be converted to a PDF format then provide any
necessary proprietary software to view the results at no cost to the City.
2.
Fibre optic backbone cable test results shall be incorporated in the PCS Network
– Cable Test Results manual. Submit five (5) copies of the Cable Test Results
manual for each plant. The manual consists of hardcopy test result reports
placed into lockable ‘D’ ring binders with a cover and spline that clearly indicates
the title of the manual. Put a CD with the electronic copies of test reports in a
pocket in the Cable Test Results manual.
3.
Both the Contractor and Contract Administrator must sign hardcopy reports.
Fibre Optic Documentation. As a minimum, test reports shall include the following
information for each fibre optic cabling element (fibre) tested.
1.
Actual measured attenuation, maximum allowable attenuation (loss) and the
attenuation margin at the specified wavelengths. An individual test that fails the
link criteria shall be marked as FAIL.
2.
Reference method.
The City of Guelph
Lift Stations SCADA Upgrades
Page 7 of 9
November, 2008
Wires and Cables (0-1000V) – Section 16122
3.
4.
.14
.15
.16
Number of mated connectors.
Actual length and maximum allowable length. Any individual test that fails the link
length criteria shall be marked as FAIL.
5.
Group refractive index (GRI) for the type of fibre tested, if length was optically
measured.
6.
Tester manufacturer, model, serial number and software version.
7.
Circuit ID number (Cable Tag Id) and facility (Plant).
8.
Link criteria used.
9.
Overall pass/fail indication.
10.
Date and time of test.
Horizontal twisted pair cable shall meet or exceed the permanent link, performance
requirements specified in TIA/EIA-568-B.2-1 for Category 6, Unshielded Twisted Pair
(UTP).
Category 6 Test Equipment. Category 6 test equipment shall meet the following minimum
criteria:
1.
All test equipment of a given type shall be from the same manufacturer, and have
compatible electronic results output. Acceptable test equipment manufacturers
are Fluke, HP, or MicroTest.
2.
Test adapters must be approved by the manufacturer of the test equipment.
Adapters from other sources are not acceptable.
3.
Baseline accuracy of the test equipment must exceed TIA Level III, as indicated
by independent laboratory testing.
4.
Test equipment must be capable of certifying Category 6 UTP to TIA/EIA-568B.2-1 standards.
5.
Test equipment must have a dynamic range of at least 200 dB to minimize
measurement uncertainty.
6.
Test equipment must be capable of storing full frequency sweep data for all tests.
7.
Test equipment must include S-Band time domain diagnostics for NEXT and
return loss (TDNXT and TDRL) for accurate and efficient troubleshooting.
8.
Test equipment must be capable of running individual NEXT, return loss, etc.,
measurements in addition to autotests. Individual tests increase productivity
when diagnosing faults.
9.
Test equipment must make swept frequency measurements in compliance with
TIA/EIA-568-B standards.
10.
The measurement reference plane of the test equipment shall start immediately
at the output of the test equipment interface connector. There shall not be a time
domain dead zone of any distance that excludes any part of the link from the
measurement.
Category 6 (UTP) Documentation. As a minimum, test reports shall include the following
information for each UTP CAT6 cabling element tested::
1.
Wiremap results that indicate the cabling has no shorts, opens, mis-wires, split,
reversed, or crossed pairs, and end-to-end connectivity is achieved.
2.
Attenuation, NEXT, PSNEXT, Return Loss, ELFEXT, and PSELFEXT data that
indicate the worst case result, the frequency at which it occurs, the limit at that
point, and the margin. These tests shall be performed in a swept frequency
manner from 1 MHz to highest relevant frequency, using a swept frequency
interval that is consistent with TIA and ISO requirements. Information shall be
provided for all pairs or pair combinations and in both directions when required
by the appropriate standards.
3.
Length (in metres), propagation delay, and delay skew relative to the relevant
limit.
4.
Any individual test that fails the relevant performance specification shall be
marked as a FAIL.
5.
Cable manufacturer, cable model number/type, and NVP.
6.
Tester, manufacturer, model, serial number, hardware version, and software
version.
7.
Circuit ID number (Cable Tag Id).
8.
Test criteria used.
9.
Overall pass/fail indication.
10.
Date and Time of test.
The City of Guelph
Lift Stations SCADA Upgrades
Page 8 of 9
November, 2008
Wires and Cables (0-1000V) – Section 16122
3.4
Wiring Identification
.1
Identify wiring including fibre optic cabling, wire markers.
.2
Colour code power, feeder and branch conductors at both ends with coloured plastic tapes. Tapes
are not required where conductors are identified by jacket colour. Maintain phase and colour
sequence throughout.
.3
Identify each conductor, including spares, with a unique alphanumeric designation to facilitate
troubleshooting and maintenance.
.4
Identify PLC wiring at terminal blocks and connection points with tagging as identified on the
contract drawings.
END OF SECTION
The City of Guelph
Lift Stations SCADA Upgrades
Page 9 of 9
November, 2008
Outlet Boxes, Conduit Boxes, and Fittings – Section 16132
PART 1.
1.1
GENERAL
Summary
.1
1.2
Submittals
.1
Manufactured Products
.1
Concealed or recessed outlet boxes. NEMA 4X enclosures in all process area, NEMA 1
enclosures in all other areas unless noted otherwise, standard galvanized stamped steel, minimum
50 mm deep with cover and integral vapour barrier where required by Provincial Building Code, by
Temco Electric Products Company Inc., Iberville Commander Electric Materials Inc.
.2
Surface-mounted outlet boxes, 150 x 150 mm maximum: Cast construction, corrosion resistant,
ferrous alloy or copper free aluminium, with threaded conduit hubs and gasketted covers.
Rectangular box, FS or FD Type by Appleton Electric Ltd., Crouse-hinds, Killark Electrical
Manufacturing Co. Round box, VJ Series by Killark Electric Manufacturing Co., GRF or VXF Series
by Crouse-Hinds, GS Series by Appleton Electric Ltd.
.3
Surface mounted multi-gang outlet boxes: Case ferrous alloy or copper free aluminium, corrosion
resistant, single gang cover, FSO or FDO Series by Crouse-Hinds, FSQ or FDQ Series by Killark
Electric Manufacturing Co., FD-XL Series by Appleton Electric Ltd.
.4
PVC coated metallic conduit system: PVC coated junction and pull boxes 150 x 150 mm
maximum, by Robroy Industries Ltd. Junction and pull boxes 150 x 150 mm minimum, epoxy
coated, by Crouse Hinds non- metallic by Columbex, Robroy Industries Ltd., Carlon. Code gauge
thickness galvanized steel.
.5
Rigid PVC conduit system outlet boxes, 150 x 150 mm maximum: Moulded PVC, F Series by IPEX
Inc., Carlon.
.6
Hazardous locations: Products approved for the specific area classification and wiring application,
by Crouse-Hinds, Killark Electrical Manufacturing Co., Appleton Electric Ltd.
.7
Grounding: Ground stud in junction and pull boxes.
.8
Where set in concrete or in masonry walls, special boxes for this service not less than 50mm deep
shall be used.
.9
Use multi-gang boxes where required for more than one device at a location.
.10
Size boxes in accordance with electrical safety code.
.11
Use 100mm spare or larger outlet boxes as required for special devices.
.12
Use 100mm octagonal boxes for light fixture outlets.
PART 3.
3.1
Mark location and size of outlet and conduit boxes on record drawings.
PRODUCTS
PART 2.
2.1
Comply with General Conditions and Section 16010 – Electrical General Requirements.
EXECUTION
Coordination
.1
Prior to installation of wiring, compare Contract Drawings with latest issue of Vendor shop
drawings.
.2
Report discrepancies promptly to Engineer.
The City of Guelph
Lift Stations SCADA Upgrades
Page 1 of 2
November, 2008
Outlet Boxes, Conduit Boxes, and Fittings – Section 16132
3.2
Installation
.1
Where ground stud not provided by manufacturer, drill and tap enclosure housing and install
ground stud. Maintain enclosure integrity.
.2
Neatly make cut-outs for outlet boxes recessed in walls of minimum practical size.
.3
Install boxes clear of building and mechanical services equipment.
.4
Where two or more devices are shown at one location, utilize multi-gang boxes, complete with
metal barriers where required by Inspection Authority.
.5
Supply all outlet boxes with covers or plaster rings. For flush installations, mount outlets flush with
finished wall using plaster rings to permit wall finish to come within 6mm of opening.
.6
Size boxes to accommodate the number of conduits, conductors and terminal blocks in accordance
with Inspection Authority requirements.
.7
Securely fasten surface-mounted boxes to building or mounting structure, support independently
and not from conduits entering the box.
.8
All raceways concealed in walls shall terminate in sheet steel outlet boxes approved for type of wall
use.
.9
Fill boxes with paper sponges, or foam or similar approved material to prevent entry of construction
materials.
.10
Gang boxes where wiring devices are grouped.
END OF SECTION
The City of Guelph
Lift Stations SCADA Upgrades
Page 2 of 2
November, 2008
Conduits, Conduit Fastenings and Conduit Fittings – Section 16133
PART 1.
1.1
GENERAL
Summary
.1
1.2
1.3
Reference
.1
CAN/CGSB-1.108 Bituminous Solvent Type Paint.
.2
EEMAC TC2 Electrical Plastic Tubing (EPT) and Conduit (EPC-40 and EPC-80).
.3
EEMAC TC3 PVC Fittings for use with Rigid PVC Conduit and Tubing.
.4
CSA C22.2 No. 211.2 Rigid PVC (Unplasticized) Conduit.
.5
EEMAC RN1 Polyvinyl-Chloride (PVC) Externally Coated Galvanized Rigid Steel Conduit and
Intermediate Metal Conduit.
.6
CAN/CSA C22.2 No. 18-[98], Outlet Boxes, Conduit Boxes, and Fittings and Associated Hardware.
.7
CSA C22.2 No. 45[M1981(R1922)], Rigid Metal Conduit.
.8
CSA C22.2 No. 56-[1977(R1999)], Rigid Metal Conduit.
.9
CSA C22.2 No. 56-[1977(R1999)], Flexible Metal Conduit and Liquid-Tight Flexible Metal Conduit.
.10
CSA C22.2 No. 83-[M1984(R1999)], Electrical Metallic Tubing.
.11
CSA C22.2 No. 211.2-[M1984(R1999)], Rigid PVC (Unplasticized) Conduit.
.12
CAN/CSA C22.2 No. 227.3-[M91(R1999)], Flexible Nonmetallic Tubing.
Submittals
.1
Submit with three weeks of contract award shop drawings of the proposed complete conduit, tray,
bus and cable layout system to be installed or modified, showing dimensional layouts construction
details, and wiring between equipment and devices for approval.
.2
Submit final record conduit layout diagrams at completion of project. Include changes made during
field installation and start-up.
PRODUCTS
PART 2.
2.1
Comply with General Conditions and Section 16010 – Electrical General Requirements.
Manufactured Units
.1
Comply with relevant standards.
.2
Rigid steel conduit: Conduit, including threaded elbows and fittings, hot-dip galvanized inside and
outside, by Robroy Industries Ltd., Longtin Conduits Inc., MBF Electrical Products Inc.
.3
Corrosion resistant rigid steel conduit: Conduit, including elbows and fittings, hot dipped
galvanized steel with epoxy-polyester exterior and epoxy-acrylic interior coating, by Co-Na-Cote
Inc., Green-guard II by Colombex Inc., CoroGard by Longtin Conduits Inc.
.4
Rigid PVC conduit: Conduit, including elbows and fitting, Schedule 40 wall thickness, solvent weld
connections, by IPEX Inc., Carlon.
.5
Liquid-tight flexible conduit: Aluminium or galvanized steel, spirally wound interlocking armour
construction, extruded PVC jacket overall. Metal Hose Sealtite by Anaconda, type CSA by Eastern
Wire & Conduit.
The City of Guelph
Lift Stations SCADA Upgrades
Page 1 of 4
November, 2008
Conduits, Conduit Fastenings and Conduit Fittings – Section 16133
.6
PVC Encapsulated Rigid Metal Conduit: Hot dip galvanized inside and out with hot galvanized
threads, UL Listed PVC coated galvanized rigid conduit, by Rob Roy
.7
Conduit straps for rigid steel and PVC conduit: Malleable iron, hot-dip galvanized, single hole type
for conduits up to 50 mm, two-hole type for conduits larger that 50 mm.
.8
Beam clamps: Hot dip galvanized steel designed to clamp onto both sides of the flange. Cat.
#S997BC-HG (100-230 mm flange) by Sasco Tube & Roll Forming Inc., Cat. #S999BC-HA (175430 mm flange) by Sasco Tube & Roll Forming Inc., type CS91 by Construt Inc.
.9
Rigid steel conduit connectors: Malleable iron or steel, hub type with nylon insulated throat or
bushing, recessed neoprene O ring, pressure type terminals for grounding wire connections when
required, by Thomas & Betts Ltd., Swift Devices Ltd., Elliot Electrical Manufacturing Co.
.10
Liquid-tight flexible conduit connectors: With threaded grounding core, nylon compression ring and
gland, insulated throat, male thread and locknut or male bushing with integral O ring seal, by
Thomas & Betts Ltd., Elliot Electrical Manufacturing Co.
.11
Rigid PVC conduit connectors: Adapter type with threaded male portion, by IPEX Inc., Carlon.
.12
Locknuts for metallic conduits: Bonding type with sharp edges for digging into metal wall of
enclosure.
.13
Expansion couplings: With ground straps or clamps. Type XJ by Crouse-Hinds.
.14
Swivel couplings: Threaded, one piece, by Elliot Electrical Manufacturing Co. Running threads are
not acceptable.
.15
Conduit spacers: Malleable iron, sized to suite conduit size, by O-Z/Gedney Co., 1300 Series by
Thomas & Betts Ltd.
.16
Conduit seals and fittings for hazardous locations: Suitable for applications in designated area, by
Crouse-hinds, Killark Electrical Manufacturing Co., Appleton Electric Ltd.
.17
Hazardous area seal filling compound: As recommended by seal manufacturer.
.18
Pull cords: 6 mm polypropylene or nylon material. Pro-pull rope by Ideal.
.19
Bituminous backpaint: CAN/CGSB-1.108.
PART 3.
3.1
EXECUTION
Installation
.1
Refer to other Sections of Division 16 for additional conduit installation requirements relating to
wiring separation by signal level. Unless otherwise required, PVC conduit shall be used.
.2
Connect conduits to electrical boxes and electrical equipment enclosures in wet or sprinklered
areas with watertight conduit connectors.
.3
Install conduits to conserve headroom in exposed locations and cause minimum interference in
spaces through which they pass.
.4
Install conduits 150 mm minimum clear of steam and hot water pipes and 1000 mm minimum clear
of heaters.
.5
Provide rigid galvanized steel conduits, minimum trade size 19 mm for concealed or exposed
conduits and 25 mm for conduits embedded in concrete.
.6
Provide rigid PVC conduit underground or in corrosive areas. Provide 50 mm thick concrete tiles to
protect direct buried PVC conduit.
.7
For conduit systems in or running through hazardous areas, provide conduit, fittings, seals and
associated components complying with requirements of applicable Codes and Standards.
The City of Guelph
Lift Stations SCADA Upgrades
Page 2 of 4
November, 2008
Conduits, Conduit Fastenings and Conduit Fittings – Section 16133
.8
Install exposed conduits symmetrical with building construction and with accepted bends or pull
boxes where conduits change direction.
.9
Provide expansion fittings in straight conduit runs exceeding 60 m and at building expansion joints.
.10
Install conduits and fittings surface mounted.
.11
Install conduits recessed in brick or bare concrete block walls as walls are being erected. Do not
cut into walls after walls are in place. Do not install horizontal runs in masonry walls. Do not install
conduits in terrazzo or concrete toppings.
.12
Attached exposed conduits in place with galvanized steel hangers one-hole straps spaced at 1300
mm centres maximum. Group conduits together whenever possible. Use galvanized steel hangers
and supports. Perforated straps are not acceptable.
.13
Provide pipe spacers for exposed conduits on concrete or masonry walls.
.14
Provide drill-in type expansion bolts and machine screws for supporting hangers and straps.
.15
Locate conduits penetrating floors, permitting direct vertical connection with minimal bending.
.16
Provide flexible liquid-tight conduit between rigid conduit system and equipment subject to vibration
or adjustment, such as motors or motorized equipment.
.17
Provide flexible metal conduit between junction boxes and luminaries in office areas and outlets
within office partitions.
.18
For building interior concrete wall and floor penetrations excluding penetrations into wet wells or
hazardous chambers, install Schedule 40 galvanized steel pipe conduit sleeves, protruding 50 mm
through floors and flush with wall surfaces prior to pouring concrete. Size sleeve for free passage
of conduit. Seal all penetrations.
.19
Size conduits according to Inspection Authority requirements.
.20
Route conduits to avoid beams, columns and other obstructions.
.21
To prevent corrosion of concrete embedded conduits, prior to concrete placement, apply 40
microns minimum of bituminous backpaint to conduit exterior surface at concrete entry points (150
mm inside and 100 mm outside the concrete).
.22
Embedded conduits: Ensure maximum outside diameter of concrete embedded conduit is 1/3
structural slab thickness measured at thinnest point. Ensure minimum space between each
conduit running parallel is 3 times O.D. of largest conduit. Do not run conduits running parallel to
beam axes, directly above beams. Offset conduits running parallel to beams by 300 mm minimum
from face of beam to outside wall of conduit. Cross conduits at right angles wherever possible.
Run conduits in space between layers of reinforcing steel without deforming reinforcing steel
pattern.
.23
Cut PVC jacket conduit thread removing plastic jacket. Coat exposed metal with zinc rich primer.
Tighten conduit utilizing strap wrenches. Coat damaged conduit surfaces and exposed threads as
recommended by conduit manufacturer.
.24
Coat damaged surfaces and exposed threads of corrosion resistant conduit as recommended by
conduit manufacturer.
.25
Ream cut conduits to remove burrs; paint completed galvanized steel joints and field cut threads
with zinc rich primer paint.
.26
Clean conduit run with an accepted cleaner equipped with a mandrel.
.27
Provide watertight, steel capped bushings on ends.
.28
Install expansion fittings on dry side of plastic water stops where required.
.29
Where conduits pass through a waterproof membrane, provide an oversized sleeve before
membrane is installed. Use cold mastic between sleeves and conduits.
The City of Guelph
Lift Stations SCADA Upgrades
Page 3 of 4
November, 2008
Conduits, Conduit Fastenings and Conduit Fittings – Section 16133
3.2
.30
Do not commence surface conduit installation work until masonry ceiling, wall and floor finishes are
completed. Finish surface mounted conduit installation work prior to painting.
.31
Touch up and repair coated conduits and fittings including any exposed threads with compound
material supplied by conduit manufacturer.
.32
For flush mounted panelboards, provide two 25 mm empty conduits (minimum) up to ceiling space
and where applicable, two 25 mm empty conduits (minimum) down through floor into ceiling or
basement space below.
.33
Provide pull cords in conduits with 1000 mm slack at each end.
Installation in Hazardous Locations
.1
Connect to explosion proof motors with explosion proof flexible conduit sections and connectors.
.2
Install conduit sealing fittings in hazardous areas where required. Fill with compound.
.3
Install approved explosion proof drain fittings at low points in conduit system. Install combination
drain/for either fittings in accordance with manufacturers recommendations and Inspection
Authority regulations.
.4
Conduit in wetwells shall be continuous.
.5
Rigid steel conduit to be used for cable run between sensor head and transmitter on all ultrasonic
applications.
END OF SECTION
The City of Guelph
Lift Stations SCADA Upgrades
Page 4 of 4
November, 2008
Moulded Case Circuit Breakers – Section 16412
PART 1.
1.1
GENERAL
Product Data
.1
Submit product data in accordance with Section 16010.
.2
Include time-current characteristic curves for breakers with interrupting capacity of 22,000A
symmetrical (rms) and over at system voltage.
PART 2.
2.1
2.2
PRODUCTS
Breakers - General
.1
Bolt-on moulded case circuit breaker: quick- make, quick-break type, for manual and automatic
operation with temperature compensation for 40ºC ambient.
.2
Plug-in moulded case circuit breakers: quick- make, quick-break type, for manual and automatic
operation with temperature compensation for 40ºC ambient.
.3
Common-trip breakers: with single handle for multi-pole applications.
.4
Magnetic instantaneous trip elements in circuit breakers to operate only when value of current
reaches setting. Trip settings on breakers with adjustable trips to range from 3-8 times current
rating.
.5
Circuit breakers with interchangeable trips as indicated.
.6
Circuit breakers to have minimum of 30,000 A symmetrical rms interrupting capacity rating.
Thermal Magnetic Breakers
.1
2.3
Magnetic Breakers
.1
2.4
Fused thermal magnetic breakers with current limiting fuses internally mounted. Time current
limiting characteristics of fuses coordinated with time current tripping characteristics of circuit
breaker. Coordination to result in interruption by breaker of fault-level currents up to interrupting
capacity of breaker. Fuses individually removable and interlocked with breaker. Removal of fuse
cover, blowing of a fuse or removal of a fuse, to trip breaker.
Solid State Trip Breakers
.1
2.6
Moulded case circuit breaker to operate automatically by means of magnetic tripping devices to
provide instantaneous tripping for short circuit protection.
Fused Thermal Magnetic Breakers
.1
2.5
Moulded case circuit breaker to operate automatically by means of thermal and magnetic tripping
devices to provide inverse time current tripping and instantaneous tripping for short circuit
protection.
Moulded case circuit breaker to operate by means of a solid-state trip unit with associated current
monitors and self-powered shunt trip to provide inverse time current trip under overload condition,
and long time, short time, and instantaneous tripping for phase and ground fault short circuit
protection.
Optional Features
.1
Include:
.1
On-off locking device.
The City of Guelph
Lift Stations SCADA Upgrades
Page 1 of 2
November, 2008
Moulded Case Circuit Breakers – Section 16412
.2
VEXECUTION
PART 3.
3.1
Handle mechanism.
Installation
.1
Install equipment as indicated on drawings.
.2
Follow manufacturer’s recommendations for installation.
END OF SECTION
The City of Guelph
Lift Stations SCADA Upgrades
Page 2 of 2
November, 2008
Disconnect Switches – Section 16414
PART 1.
1.1
GENERAL
Product Data
.1
PRODUCTS
PART 2.
2.1
2.2
Disconnect Switches
.1
Fusible disconnect switch in CSA Enclosure, size as indicated.
.2
Provision for padlocking in off switch position by three locks.
.3
Mechanically interlocked door to prevent opening when handle in ON position.
.4
Fuses: size as indicated.
.5
Fuseholders: suitable without adaptors, for type and size of fuse indicated.
.6
Quick-make, quick-break action.
.7
ON-OFF switch position indication on switch enclosure cover.
.8
Disconnect status contact that opens before actual disconnect opens for remote disabling of VFDs
etc.
.9
Enclosure Ratings:
.1
Dry areas: Rigid, dead front, 2 mm steel sheet, NEMA/EEMAC 12.
.2
Wet and damp, indoor and outdoor, and process areas: Rigid, dead front, 2 mm, 304
stainless steel sheet, NEMA/EEMAC 4X, with stainless steel hardware.
.3
Corrosive areas: Rigid, dead front, moulded fiberglass reinforced polyester,
NEMA/EEMAC 4X.
.4
Hazardous areas: Assembly and components suitable for application in specific areas
indicated, Explosion Proof NEMA7.
Equipment Identification
.1
Provide equipment identification in accordance with Section 16010.
.2
Indicate name of load controlled on size 4 nameplate.
EXECUTION
PART 3.
3.1
Submit product data in accordance with Section 16010.
Installation
.1
Install disconnect switches complete with fuses if applicable.
END OF SECTION
The City of Guelph
Lift Stations SCADA Upgrades
Page 1 of 1
November, 2008
Control Devices – Section 16423
PART 1.
1.1
1.2
GENERAL
General
.1
Where an item is shown on the drawings and is specified in this section, such item shall conform to
this section.
.2
Control devices are to be installed on the local control panels, MCC panels and on other panels
where required and as indicated on the drawings.
.3
Refer to Section 16900 also.
Shop Drawings
.1
1.3
Colour Coding
.1
Pilot lights and control switches to be coloured per CAN/CSA-Z431-96 Colours of Indicator Lights
and Push-Buttons.
.2
Generally, pilot lights shall be coloured as follows (unless shown otherwise on drawings):
.1
Running
Red
.2
Stopped
Green
.3
Power On/Ok
White
.4
Fault
Amber
.5
Auto Bypass
White
.6
Communications Ok
Orange
.7
PLC Ok
Green
.3
Generally, push-buttons and selector switches shall be coloured as follows:
.1
Stop, Off
Red
.2
Start, Run
Green
.3
Other Function
Black
PRODUCTS
PART 2.
2.1
2.2
Submit shop drawings in accordance with Specification 16010. Include:
.1
Schematic
.2
Wiring
.3
Interconnection Diagrams
AC Control Relays
.1
Universal pole type: electrically held with 3 poles, convertible from NO to NC by changing wiring
connections. Coil rating: 120V, 3VA. Contact rating: 120V, 10A Provision for padlocking in off
switch position by three locks.
.2
Allen-Bradley 700E, Cutler Hammer, Square D.
Solid State Timing Relays
.1
Construction: AC operated electronic timing relay with solid-state timing circuit to operate output
contact. Timing circuit and output contact completely encapsulated to protect against vibration,
humidity and atmospheric contaminants.
.2
Operation: on-delay or off-delay, as indicated on drawings.
.3
Potentiometer: self contained to provide time interval adjustment.
.4
Supply Voltage: 120VAC, 60Hz .
The City of Guelph
Lift Stations SCADA Upgrades
Page 1 of 5
November, 2008
Control Devices – Section 16423
2.3
2.4
.5
Temperature range: minus 20°C to 60°C.
.6
Output contact rating: maximum voltage 120V ac or dc. Current: EEMAC B300.
.7
Timing ranges: minimum 1.0s, maximum 60s, unless otherwise specified.
.8
Allen-Bradley 700HT, Omron, Potter & Brumfield, Square D.
Interposing PLC Panel Relays
.1
Provide crystal relays as required.
.2
120VAC Crystal Relays:
.1
Contacts: Three (3) form “C” SPDT dry contacts.
.2
Contact Rating: 10Amp/120Vac.
.3
Contact Material: Silver Cadmium Oxide (AgCdO).
.4
Coil Voltage: 120VAC, 60 Hz.
.5
Surge Suppression: AC surge suppression on coil.
.6
Socket: 11 pin octal, DIN rail mounting.
.7
Indication: Status light and mechanical flag.
.8
Typical Mechanical Life: 100 million operations.
.9
Protection Class: Enclosed IP40.
.10
Accessories:
1.
Push To Test button (colour coded)
2.
Retaining Clip (S3-CT)
3.
I.D. Labels
.11
Time Delay Cube: As required
.12
Manufacturers:
1.
Releco m/n C3-A30~X/120 Vac
2.
Potter & Brumfield m/n KUP
3.
Idec m/n RR3PA~LC~120Vac
.3
24VDC Crystal Relays:
.1
Contacts: Two (2) form “C” SPDT Dry Contacts
.2
Contact Rating: 4-20mA/24VDC.
.3
Contact Material: 4020mA Application: solid silver with 5 microns gold plating ((Ag + 5 µ
Au GP); General Purpose Application: Cadmium Oxide (AgCdO).
.4
Coil Voltage: 120VAC, 60 Hz.
.5
Surge Suppression: DC surge suppression on coil.
.6
Socket: 8 pin octal, DIN rail mounting.
.7
Indication: Status light and mechanical flag.
.8
Typical Mechanical Life: 100 million operations.
.9
Protection Class: Enclosed IP40.
.10
Accessories:
1.
Push To Test button (colour coded)
2.
Retaining Clip (S3-C)
3.
I.D. Labels
.11
Time Delay Cube: As required.
.12
Manufacturers:
1.
Releco m/n C2-A29~X/120 Vac
2.
Potter & Brumfield m/n KUP
3.
Carlo Gavazzi m/m RCP
Pushbuttons
.1
Oil tight. Operator extend type 30mm diameter. Black with NO and NC 120V contacts rated at 720
VA ac, labels as indicated. Stop pushbuttons coloured red. Start pushbuttons coloured green.
Reset buttons coloured black.
.2
Allen-Bradley 800E, Cutler Hammer, Square D.
The City of Guelph
Lift Stations SCADA Upgrades
Page 2 of 5
November, 2008
Control Devices – Section 16423
2.5
2.6
2.7
2.8
2.9
2.10
Selector Switches
.1
Maintained unless otherwise indicated, labeled as indicated, heavy duty, 30mm diameter oil-tight
standard operators, contact arrangement as indicated, rated 120V, 720 VA ac.
.2
Provide number of positions as shown on the drawings.
.3
LOCAL-REMOTE switches to be make-before-break.
.4
Allen-Bradley 800E, Cutler Hammer, Square D.
Indicating Lights
.1
Oil-tight, LED lamp, transformer type, 30mm diameter, lens colour: as indicated, supply voltage:
120V, labels as indicated.
.2
Allen-Bradley 800E, Cutler Hammer, Square D.
Control and Relay Panels
.1
CSA EEMAC 4X, or Type 7, depending on location, enclosure with hinged padlockable access
door, accommodating relay timers, labels, as indicated, factory installed and wired to indentified
terminals.
.2
Hammond, Ralston, Hoffman.
Control Circuit Transformers
.1
Single phase, dry type.
.2
Primary: 600Vac, 60Hz (fused).
.3
Secondary: 120Vac.
.4
Rating: power rating 20% greater than load.
.5
Hammond, Rex.
Control Circuit Breakers
.1
Rail mounted, thermomagnetic, toggle operated.
.2
Entrelec, Weidmuller, Phoenix.
Terminal Blocks
.1
Provide European DIN style terminal blocks rated at no less than 25 Amps at 600 Vac modular, 35
mm DIN rail mounted, provision for circuit number labeling, individually removable, sized to
accommodate conductor size and circuit current with minimum of 20% spare of each type.
.1
Manufacturer: Phoenix UK Series, Phoenix UKK Series, Weidmuller SAK Series, Wieland
WK Series or Entrelec M Series.
.2
Provide end plates, partition plates, jumper bars, and end stoppers where required.
.3
All terminal blocks including those on PLC terminals shall be uniquely identified and permanently
marked.
.4
Reserve one side of each terminal strip for field incoming conductors. Do not make common
connections and jumpers required for internal wiring on the field side of the terminal.
.5
Provide jumper bars (not wires) to connect common wires and terminals.
The City of Guelph
Lift Stations SCADA Upgrades
Page 3 of 5
November, 2008
Control Devices – Section 16423
2.11
2.12
2.13
.6
Provide "knife switch" type terminal blocks on all analog 4-20 ma loops to connect an ammeter in
series or to electrically isolate the loop.
.1
Manufacturer: Phoenix Series MTK, Wieland WKF Series.
.7
Provide fused terminal blocks (5X20mm) c/w neon "fuse blown" indicator on a knife switch for all
digital loops, minimum rating: 300 V, 25 A, modular, 35 mm DIN rail mounted, provision for circuit
number labelling, individually removable, sized to accommodate conductor size and circuit current .
Supply five (5) spare fuses of each type.
.1
Manufacturer: Phoenix UK Series, Weidmuller KDKS series, Weidmuller SAKS series,
Wieland WK Series or Entrelec M Series.
.8
Fuse instrument loops individually and supply five (5) spare fuses of each type.
.9
Provide 249 Ω/250 Ω precision resistor at terminal blocks where required.
.1
Manufacturer: Phoenix UDK Series, Weidmuller WDK Series.
.10
Use only Thermocouple terminals and thermocouple wires for thermocouple loops.
Uninterruptible Power Supply
.1
Provide uninterruptible power supply (UPS) suitable for powering and protection of PLC processor,
instruments and modem during the main power source outage.
.2
UPS shall be on-line, no-break, batteries continuously in circuit with static bypass loads. Minimum
rating 1000 VA, 120Vac, 60Hz and minimum 60 minutes run time, unless otherwise specified.
.3
Surge protection shall comply with Category B, ANSI/IEEE C62.41 and 45 and shall have
automatic low and high voltage protection.
.4
Battery: sealed, maintenance free, minimum 6 years life and LED warning light for battery
replacement.
.5
UPS shall have On/Off test pushbutton, “on” battery LED, “on”-line LED and hardwired input and
output.
.6
Contractor must provide the SNMP Ethernet communications card and provide a CAT6 patch cable
from UPS to Ethernet switch.
.7
Contractor to use UPS to power communication equipment.
.8
UPS to be Powerware PS9120 Series (1000VA minimum, unless specified otherwise).
.1
1500VA unless specified otherwise.
.2
Dry contact relays.
24V Power Supply
.1
Input: 100 - 240VAC, 60Hz (fused).
.2
DIN rail mount, DC OK Output.
.3
Output: 24-28VDC, 50W (Output is to be confirmed by the contract for the load requirements).
.4
Maximum Output Ripple: <50mV peak to peak.
.5
Protection: short circuit, overload, diode protected.
.6
IDEC PS5R-SF24 series.
PLC Panel Door Contact
.1
Integrated for control of PLC luminaries.
.2
Quantity: As required.
.3
Approved supplier:
The City of Guelph
Lift Stations SCADA Upgrades
Page 4 of 5
November, 2008
Control Devices – Section 16423
.1
.4
2.14
3.2
Location: PLC panels
Door Contact
.1
GE Security:
.1
Supply magnetic door switches for all exterior doors and hatches under this contract at the
facility.
.2
GE Security 2500 Industrial Switches
.3
Hermetically sealed magnetic reed contact.
.4
SPDT 24V contacts.
.5
Cover to conceal fasteners and terminals.
.2
Quantity: As required.
PART 3.
3.1
Omron: P/N 2-15GW2-B-7K.
EXECUTION
Installation
.1
Install control devices and interconnect as indicated.
.2
Install instruments and interconnect as indicated.
.3
Use Lamacoid labels for control switches, lamps and pushbuttons.
Field Quality Control
.1
Perform tests in accordance with Specification 16010.
.2
Depending upon magnitude and complexity, divide control system into convenient sections,
energize one section at a time and check out operation of section.
.3
Upon completion of sectional test, undertake group testing.
.4
Check out complete system for operational sequencing.
.5
Submit to Contract Administrator one copy of test results.
END OF SECTION
The City of Guelph
Lift Stations SCADA Upgrades
Page 5 of 5
November, 2008
Panelboards – Section 16441
PART 1.
1.1
1.2
GENERAL
Shop Drawings
.1
Submit shop drawings in accordance with Division 16000.
.2
Drawings to include electrical detail of panel, branch breaker type, quantity, ampacity and
enclosure dimension.
Plant Assembly
.1
PRODUCTS
PART 2.
2.1
2.2
2.3
Install circuit breakers in panelboards before shipment.
Panelboards
.1
Panelboards: Wall mounted as shown on drawings. Cutler Hammer, Square D, Federal Pioneer.
.2
250 and 600 V panelboards: bus and breakers rated for 22 kA (symmetrical) interrupting capacity
or as indicated.
.3
Sequence phase bussing with odd numbered breakers on left and even on right, with each breaker
identified by permanent number identification as to circuit number and phase.
.4
Panelboards: mains, number of circuits, and number and size of branch circuit breakers as
indicated.
.5
Hinged, lockable covers two keys for each panelboard and key panelboards alike.
.6
Copper bus with neutral of same ampere rating as mains.
.7
Mains: suitable for bolt-on breakers.
.8
Trim and door finish: ANSI 61 – grey.
.9
Directory in plastic pocket inside cover.
Breakers
.1
Bolt-on molded case circuit breaker: quick-make, quick-break type, for manual and automatic
operation with temperature compensation for 40°C ambient.
.2
Molded case circuit breaker to operate automatically by means of thermal and magnetic tripping
devices to provide inverse time current tripping and instantaneous tripping for short circuit
protection.
.3
Common-trip breakers: with single handle for multi-pole applications.
.4
Main breaker: separately mounted on top or bottom of panel to suit cable entry. When mounted
vertically, down position should open breaker.
.5
Lock-off devices as indicated on drawings.
Equipment Identification
.1
Provide equipment identification in accordance with Section 16010 – Basic Electrical
Requirements.
.2
Nameplate for each panelboard size 4 engraved as indicated.
.3
Complete circuit directory with typewritten legend showing location and load of each circuit.
The City of Guelph
Lift Stations SCADA Upgrades
Page 1 of 2
November, 2008
Panelboards – Section 16441
PART 3.
3.1
EXECUTION
Installation
.1
Locate panelboards as indicated and mount securely, plumb, true and square, to adjoining
surfaces.
.2
Mount panelboards to height specified in Section 16010 - Basic Electrical Requirements or as
indicated.
.3
Connect loads to circuits.
.4
Connect neutral conductors to common neutral bus.
.5
Rearrange the connection of branch circuits as required to provide an evenly balanced load across
all phases of each panelboard.
.6
Provide load balancing and testing of all circuits as indicated in Section 16010.
.7
At completion of work provide a typed panel schedule to be mounted in the door of the panel.
END OF SECTION
The City of Guelph
Lift Stations SCADA Upgrades
Page 2 of 2
November, 2008
Surge Protection Equipment – Section 16612
PART 1.
1.1
1.2
GENERAL
Surge Protection Scope
.1
Supply, install, test, and commission surge protection units, associated cabling and devices as
specified in the contract documents and drawings.
.2
The TVSS units and all components shall be designed, manufactured and tested in accordance
nd
with latest applicable UL Listed Standard (UL 1449, 2 Edition), UL 1283, and certified as per CSA
22.2.
Shop Drawings and Product Data
.1
1.3
Submit shop drawings and product data in accordance with General Conditions and Division 16.
.1
Provide verification that the Transient Voltage Surge Suppression (TVSS) device complies
with the required UL 1449 2nd Edition and CSA Approvals.
.2
For retrofit mounting applications, electrical/mechanical drawings showing unit
dimensions, weights, installation instruction details, and wiring configurations.
.3
Provide documentation and/or test reports verifying the suppressor components can
survive the published surge current rating on both a per mode and per phase basis using
IEEE C62.41, 8x20 micorsecond current wave.
.4
Provide actual let-through voltage test data results for the ANSI/IEEE C62.41 Category C3
& C1 (combination wave) and B3 (ringwave) tested in accordance with ANSI/IEEE
C62.45.
Voltage Surge Suppression - General
.1
Unit operating voltage – refer to drawings for operating voltage and unit configuration.
.2
Maximum Continuous Operating Voltage (MCOV) shall be greater than 115% (125% for critical
load filter application) of the nominal system operating voltage.
.3
Protection Modes – for a Wye configured system, the device must have directly connected
suppression elements between line-neutral (L-N), line-ground (L-G), and neutral-ground (N-G). For
a delta configured system, the device must have suppression elements between line to line (L-L)
and line to ground (L-G).
.4
UL 1449 2nd Edition SVR – The maximum UL 1449 2nd Edition SVR for the device must not exceed
the following:
Modes
L-N, L-G, N-G
L-L
.5
600Y/347
1000V
1800V
208Y/120
470V
480Y/277
900V
600Y/347
1300V
ANSI/IEEE Category B3 Let Though Voltage – The let through voltage based on IEEE C62.41 and
C62.45 recommended procedures for Category B3 ringwave (6kV, 5000A) shall be less than the
following:
Modes
L-N
.7
480Y/277
800V
1500V
ANSI/IEEE Category C3 Let Through Voltage – The let through voltage based on IEEE C62.41 and
C62.45 recommended procedures for Category C3 surges (20kV, 10kV) shall be less than the
following:
Modes
L-N
.6
208Y/120
400V
700V
208Y/120
150V
480Y/277
200V
600Y/347
300V
The TVSS device shall distribute the surge current equally to all MOV components to ensure equal
stressing and maximum performance. The surge suppression platform must provide equal
impedance paths to each matched MOV. Designs incorporating RVSS modules shall not be
accepted unless specifically approved by Contract Administrator and owner.
The City of Guelph
Lift Stations SCADA Upgrades
Page 1 of 5
November, 2008
Surge Protection Equipment – Section 16612
1.4
.8
Each unit shall include a high-performance EMI/RFI noise rejection filter. Noise attenuation for the
electrical line noise shall be 55dB at 100kHz using MILS-STD-220A insertion loss test method.
.9
No plug-in component modules or printed circuit boards shall be used as surge current conductors.
All integral components shall be hardwired with connections utilizing low impedance conductors
and compression fittings.
.10
For units providing safety and diagnostic monitoring, each unit shall be equipped with 200kAIC
internal fuses. Diagnostics to provide the following minimum functions:
.1
Continuous monitoring of fusing system.
.2
Internal sensor system for monitoring individual MOVs (including N-G) and identification
of open circuit failures.
.3
Thermal detection circuits to monitor overheating in all modes due to thermal runaway.
.4
LED status indicators on each phase, unit fault/damage LED.
.11
Provide minimum 5-year manufacturer warranty on TVSS device components.
.12
Where remote indication of TVSS unit status and/or alarms is specified (remote status monitor), the
TVSS must include a minimum of one (1) dry contact, preferably form C. The remote alarm contact
shall change state if any of the monitoring systems detects a fault condition.
System Application - General
.1
TVSS device located in Branch Panels shall be tested and demonstrate compliance with
ANSI/IEEE C62.41 Category C1 environments.
.2
The minimum total surge current 8x20 microsecond waveform that the device is capable of
withstanding shall be as shown in the following table, unless otherwise noted.
Application
Service Entrance
(Switchboards, Switchgear,
MCC Main Entrance)
Distribution Panelboards
High Exposure Roof Top
Locations
Branch Locations
(Panelboards, MCC’s,
Busway)
1.5
Minimum Surge Current
Per Phase
250 kA
Minimum Surge Current
Per Mode
125 kA
160 kA
160 kA
80 kA
80 kA
120 kA
60 kA
Panelboards and Bus Plug Requirements
.1
TVSS device shall be tested and demonstrate compliance with ANSI/IEEE C62.41 Category C1
environments.
.2
Distribution and panel suppressors shall be installed inside the panelboard or bus plugs at the
manufacturer’s factory.
.3
A direct bus bar connection shall be used to mount the TVSS component to the panelboard bus bar
or the bus plug disconnect to reduce the impedance of the shunt path.
.4
The TVSS panelboard shall be constructed using a direct bus bar connection (cable connection
between bus bar and TVSS device is not acceptable).
.5
Suppression shall be included and mounted within the panelboard and bus plug by the
manufacturer of the panelboard or bus way.
.6
For retrofit application where suppressor is externally mounted the maximum conductor lead length
between breaker and suppressor shall not exceed 14 inches unless otherwise specified by the
Contract Administrator. Comply with manufacturer’s recommended installation methods and
practices.
The City of Guelph
Lift Stations SCADA Upgrades
Page 2 of 5
November, 2008
Surge Protection Equipment – Section 16612
1.6
1.7
1.8
1.9
Switchgear, Switchboard and MCC Requirements
.1
TVSS device shall be tested and demonstrate compliance with ANSI/IEEE C62.41 Category C1
environments.
.2
Service entrance suppressor shall be installed by manufacturer.
.3
Service entrance suppressor shall be in assembly.
.4
Locate suppressor on load side of main disconnect device, as close as possible to the phase
conductors and ground/neutral bar.
.5
Provide 30A disconnect. The disconnect shall be directly integrated to the suppressor and
assembly bus using bolted bus bar connections.
.6
The suppressor and integral disconnect shall be installed to the switchboard using a direct bus bar
connection (no cable connection between the bus bar and TVSS).
.7
All monitoring diagnostic features such as indicator lights, trouble alarms and surge counter (if
specified) shall be mounted on the front of the switchboard.
TVSS Enclosure Requirements
.1
All enclosed equipment shall have NEMA 12 general purpose enclosures or indoor applications
unless otherwise noted.
.2
Provide NEMA 4 enclosures for TVSS equipment where application may be exposed to water,
splashing of liquid, moisture, or in any outdoor application.
Application for 3-15 Amp Loads (Single Phase) – PLC Panels
.1
Total surge current per phase (based on 8x20 microsecond waveform) that the device is capable of
surviving shall not be less than 39,000A.
.2
Let Through Voltage based on IEEE C62.41 and C62.45 shall be included in the shop drawings
submittal and shall be less than 10V for Categories A3 and B3 Ringwaves and less than 115V for
the Category B3/C1 impulse.
.3
Each unit shall include a high performance EMI/RFI noise rejection filter. Noise attenuation for
electric noise shall be 85B at 100kHZ using the MIL-STD-220A insertion loss test method.
.4
TVSS to be DIN rail mountable.
.5
All enclosed equipment shall have NEMA 12 general purpose enclosures or indoor applications
unless otherwise noted.
Application for 20-100 Amp Loads (1-3 Phase Loads)
.1
Total surge current per phase (based on 8x20 microsecond waveform) that the device is capable of
surviving shall not be less than 80,000A per phase.
.2
Balance surge plane construction. For each phase, all surge current shall be distributed equally to
all MOV components to ensure equal stressing and maximum reliability.
.3
TVSS to be flange mountable.
.4
Each conductor shall be rated to carry a high harmonic current. The actual current rating must be
150% or greater of the nominal phase current. The neutral conductor, if present, must be rated
250% or greater of the nominal phase current.
.5
Terminals to consist of copper alloy. Aluminum connectors rated Cu/Al mounted on the terminals is
acceptable.
The City of Guelph
Lift Stations SCADA Upgrades
Page 3 of 5
November, 2008
Surge Protection Equipment – Section 16612
1.10
1.11
Data Communication and Telephone Line Communication Protection
.1
For customer owned data/signal lines < 20,000 baud and < 200mA (4-20mA, RS-232, Zone, Loops,
etc) the surge protection unit must conform to the following parameters:
.1
Peak Surge Current (per pair): 400A (10x700 microsecond).
.2
Occurrances at Peak Current: > 100.
.3
Response Time: <1 nanosecond.
.4
Protection mode: L-L, L-G.
.5
Clamp Volts (peak surge current): <2 times peak operating voltage.
.2
For customer owned data/signal lines < 20,000 baud and < 2.5A (Speakers, Bells, Strobes, etc) the
surge protection unit must conform to the following parameters:
.1
Peak Surge Current (per pair): 5kA (8x20 microsecond).
.2
Occurrances at 2kA: 50 typical.
.3
Response Time: <1 nanosecond.
.4
Protection mode: L-L, L-G.
.3
For customer owned data/signal lines >20,000 and <10M baud and < 200mA (RS485, RS422,
RS423, etc) the surge protection unit must conform to the following parameters:
.1
Peak Surge Current (per pair): 400A (10x700 microsecond).
.2
Occurrances at Peak Current: > 100.
.3
Response Time: <1 nanosecond.
.4
Protection mode: L-L, L-G.
.5
Clamp Volts (peak surge current): <2 times peak operating voltage.
.4
For customer owned data/signal lines >10M and <100M baud and < 200mA (10BASET – Ethernet)
the surge protection unit must conform to the following parameters:
.1
Peak Surge Current (per pair): 40A (10x700 microsecond).
.2
Occurrences at Peak Current: > 100.
.3
Response Time: <1 nanosecond.
.4
Protection mode: L-L, L-G.
.5
Clamp Volts (peak surge current): <2 times peak operating voltage.
.6
Category 5 cert.: L CAT5 Cert. Per.
.5
For analog telephone networks (with ring voltage) the surge protection unit must conform to the
following parameters:
.1
Peak Surge Current (per pair): 200A (10x1000 microsecond).
.2
Occurrences at Peak Current: > 100.
.3
Response Time: <= 1 nanosecond.
.4
DC Breakdown Voltage: 200-310VDC.
.5
Max Continuous Current: 145mA.
Maintenance
.1
PRODUCTS
PART 2.
2.1
Provide maintenance data for surge protection equipment for incorporation into manual specified in
Division 1 and Section 16000 – Scope of Work.
Surge Suppression Unit 120V – PLC Panels
.1
Maximum continuous operating Voltage: 130 V (L-N, L-G, N-G).
.2
Peak surge current: 65 kA total, 45 kA phase.
.3
Energy: 700 Joules total, 490 Joules phase.
.4
Response time: 1 nanosecond maximum.
.5
Protection modes: line to neutral, neutral to ground, and line to ground.
.6
120 V, single phase.
The City of Guelph
Lift Stations SCADA Upgrades
Page 4 of 5
November, 2008
Surge Protection Equipment – Section 16612
2.2
.7
Current rating: 30 A, unless otherwise specified.
.8
Active sine-wave Voltage tracking network.
.9
Approved Suppliers:
.1
Cutler-Hammer: “AEGIS Powerline Filters”, model: AGSHW CH120N-15-XS
.2
Tycor, model: AGS 12015X.
Surge Suppression Unit – 600V
.1
Maximum continuous operating Voltage: 600 V (L-L, L-N, L-G, N-G).
.2
Peak surge current: 250 kA total per phase, 125 kA current mode per phase.
.3
Filter Attenuation at 100kHz: 55 Db.
.4
Response time: 1 nanosecond maximum.
.5
Protection modes: line to line, line to neutral, neutral to ground, and line to ground.
.6
600V, three (3) phase.
.7
Provide 30 A breaker or as per manufacturer recommendations.
.8
Let-Through Rating for 600Y/347V (L-N/L-L): 1600/2200 C3 wave, 1200/2000 C1 wave, 900/1800
UL 1449.
.9
Contractor to supply and install surge protection device into MCC as shown on the drawings. Surge
device to be connected directly to bus bar as per manufacturer recommendations.
.10
Approved Suppliers:
.1
Cutler-Hammer: “Clipper Power System”, model: CPS HX CH600Y SD RC2 CX.
PART 3.
3.1
EXECUTION
Installation
.1
Supply, install, test and commission 120V surge protection in PLC Control Panels.
.2
Supply, install, test, and commission incoming 600V surge protection as shown on the drawings.
Surge suppression unit to be connected directly to bus wherever possible. Surge suppression unit
display interface to be visible from MCC without opening MCC cell door.
.3
Mount surge protector so that the minimum practicable conductor length is achieved. Contract
Administrator will reject installation of surge protector if this condition is not met.
END OF SECTION
The City of Guelph
Lift Stations SCADA Upgrades
Page 5 of 5
November, 2008
Instrumentation and Control – Section 16900
PART 1.
1.1
1.2
GENERAL
Description of Work
.1
This section specifies the supply, installation, field-testing, and placing into operation of flow, level,
analyzers, and other instruments.
.2
In general new PLC controllers, and instrumentation are to be installed at the facilities as identified
in the documents. At facilities with existing PLCs, modifications to the existing control panels are to
be executed as identified in the documents. Refer also to Section 16000 Scope of Work
References
.1
1.3
1.4
Refer to Division 16, in particular Section 16000 Scope of Work, Section 16010 Basic Electrical
Requirements, Section 16423 Control Devices, Section 16122 Wiring and Cables, for instructions
which apply to the Work of Section 16900.
Scope of Work
.1
The Work in this Section generally consist of the supply of all labour, tools, services and provision
of all products required, for a complete, integrated, operational instrumentation and control system
for the City of Guelph Wastewater System in accordance with the Contract Specification and
Drawings.
.2
As parts of the Process Control system and certain areas of the process are brought on-line,
ensure all related equipment and services stay powered up and in proper working order. Ensure
other ongoing activities, in close proximity or otherwise, do not disturb or interrupt the operation of
the existing systems or the work already commissioned or placed into operation. Should any such
activity pose a risk to this work, or to the system operation, advise the Engineer and the City
immediately.
.3
In general, the work involves the supply installation, modification and commissioning of the
necessary hardware for the SCADA system upgrades to the City of Guelph Lift Stations as
indicated on the drawings. Automatic control will be performed by a new Allen Bradley PLC based
system and will report to the Plant SCADA. Existing auto dialer alarming systems will be
maintained. Communication to the plant SCADA will be accomplished via Bell Canada circuits.
Also refer to Section 16000.
General Requirements
.1
Take care to ensure the continuous operation of the existing systems.
.2
All functionality described in the Documents shall be fully implemented.
.3
Demonstrate operational system and put all equipment into operational service to the satisfaction of
the Engineer. Satisfactory performance of the system shall be assessed on the basis of the entire
control system being fully operational and in use under peak load conditions during the process
run.
.4
All performance requirements shall be based upon worst case scenarios.
.5
Provide documentation in timely manner and as specified.
.6
At all times, ensure that work being carried out by the Engineer or the Owner’s operations staff are
properly coordinated with all ongoing construction activities and are unhampered by unnecessary
delays or obstructions. Costs incurred by the Engineer or Owner resulting from undue
impediments, whether caused by lack of coordination, non-compliance with the specification, or
poor cooperation among trades, can be billed directly to you, or alternatively, claimed against the
maintenance holdback.
The City of Guelph
Lift Stations SCADA Upgrade
Page 1 of 17
November, 2008
Instrumentation and Control – Section 16900
1.5
1.6
Related Work Specified in Other Sections
.1
Division 16
Scope or Work
.2
Division 16
Electrical
Submittals
.1
1.7
1.8
1.9
Submit shop drawings in conformance with the General Conditions and Section 16000.
Instrument and Equipment Manufacturers
.1
When a product is specified in succeeding Sections of the Specification with a manufacturer's
name and specific identification or model number, and the words "or approved equal" are not
included, and acceptable manufacturer's are not specified, then the specified product must be
supplied. Alternative or substitute products will not be acceptable.
.2
When a product is specified in succeeding Sections of the Specification with two or more
manufacturer's names and respective specific product identification, and the words "or approved
equal" are not included, then the product supplied must be one of those specified.
.3
When a product is specified in succeeding Sections of the Specification with a generic description
and performance data, or by manufacturer's name and product data with the words "or approved
equal", the Engineer will decide at the time of shop drawing review whether or not the product
proposed is acceptable, and the Engineer’s decision will be final.
.4
Design is based on the first named manufacturer. If the Contractor proposes the use of a product
other than the first named, and the submission is accepted; if some redesign is required, it shall be
completed by the Contractor at no additional cost to the Contract.
.5
For the purposes of limiting support costs and maintenance costs, use one instrument
manufacturer/distributor for as many products as is practical.
.6
Pre-Quotation approval of equivalents and alternatives will not be given.
System Suppliers
.1
Unless otherwise specified, the supply and installation of instruments and control system hardware,
including testing, calibration, commissioning must be performed as a complete package by an
experienced, reputable instrumentation and control subcontractor. Include for service technicians
qualified by the manufacturer to be on-site if requested by the Engineer, or if correct methods for
installation, setup and calibration are uncertain. Unless otherwise stipulated, only the
manufacturer’s technicians are acceptable where control system hardware, analyzers or flow
meters are concerned. This includes subcontracting main suppliers and their services as
necessary, and especially if called for in the Specification.
.2
Submit to the Engineer documentation verifying that the company proposed as subcontractor is
experienced in the instrumentation and control work and is capable of properly carrying out that
work. Documentation is to include a list of at least five projects successfully completed this type of
work as well as the name of the Consulting Engineer and the name of his field representative for
each project. Acceptance or rejection of a proposed specialist company rests solely with the
Engineer.
.3
All on-site control and instrumentation work is to be performed under the direct supervision of a
qualified and experienced supervisor employed by the instrumentation and control subcontractor.
Operating and Maintenance Instruction Manuals
.1
In addition to requirements for operating and maintenance instruction manuals specified in earlier,
include the following:
.1
Manufacturer’s hardware and software manuals
The City of Guelph
Lift Stations SCADA Upgrades
Page 2 of 17
November, 2008
Instrumentation and Control – Section 16900
.2
.3
.4
.5
.6
.7
.8
.2
Provide operating and maintenance instruction manual for Instrumentation & Controls in a separate
indexed and tabbed manual, or separate indexed and tabbed section of the overall manual binder.
Arrange sections in a logical, concise manner, and provide a cross- reference to enable all
equipment/instruments to be located from its correct ISA tag.
.3
Prior to submission of final operating and maintenance instruction manuals, and at least thirty (30)
days prior to instrumentation and control system testing and commissioning commencing, submit to
and review with the Engineer, two copies of the proposed data for the instrumentation and control
work Section of the operating and maintenance instruction manuals.
.4
The delivery of manuals must be complete prior to application for a Certificate of Substantial
Performance of the Work.
PART 2.
2.1
Special instructions or procedures, including System, Software, and Instrument Troubleshooting techniques
Systematic procedures for operations personnel to start up, shut-down, manually override
and locally operate all related equipment in accordingly titled manual sections
Recommendations on equipment maintenance and suggested spare parts
Final Shop Drawings and signed-off Product Data Sheets as defined in this Specification
Copies of Record drawings of all Purpose-made Drawings
Name(s), address(s) and telephone number(s) for local qualified system and/or product
service representatives
Calibration certificates from the manufacturers for each calibrated instrument
PRODUCTS
Instrument General Requirements
.1
General requirements applicable to instruments are as follows:
.1
Unless otherwise shown or specified, enclosures for all instruments located indoors in dry
non-hazardous areas are to be as a minimum EEMAC 12
.2
Unless otherwise shown or specified, instruments located outdoors must be suitable for
the surrounding climate and appropriately installed with:
1. An EEMAC 4 enclosure including gasketed windows for displays, containing a
thermostatically controlled heater and disconnect switch - minimum typical
enclosure to be an O Brien VIPAK series or equal.
2. A combined rain/ice/snow protection shield and sun shade for all electronic
instruments which are already provided with sturdy EEMAC 4 enclosures
by the manufacturer. Supply tip-up type hoods for access for routine
calibration and maintenance.
3. Drawing submissions must clearly show the enclosures proposed for each
instrument.
.3
Electrically heat trace sensing lines for instruments where sensing lines are liable to
freezing.
.4
Unless otherwise shown or specified, provide instruments located hazardous areas with
Canadian Electrical Code ratings for class, group, and division as shown.
.5
Unless otherwise shown or specified, provide instruments located areas subject to
flooding with submergence rated enclosures.
.6
All line voltage powered instruments are to be suitable for a 120 volt AC power supply.
Any line voltage AC powered instrument not CSA certified must bear an Ontario Hydro
Special Approvals Branch label.
.7
Normal electrical power supply for the project is 120VAC. Emergency electrical power is
from a diesel generator. Provide all line powered instruments suitable for use on these
supplies with appropriate CSA approval.
.8
As applicable, instrument control output is to be from 4 to 20 ma, linear, isolated, capable
of driving a maximum load of 600 ohms, unless otherwise specified.
.9
Provide all the necessary mounting hardware, electrical connections, transducer junction
boxes, power supplies and all accessory items or options required to satisfy each
application.
The City of Guelph
Lift Stations SCADA Upgrades
Page 3 of 17
November, 2008
Instrumentation and Control – Section 16900
.10
.11
.12
.13
.14
.15
.16
.17
.18
.19
.20
.21
Provide equipment made of appropriate materials for the service indicated on each
Instrument Specification Sheet, and for the process fluids present, which all exposed
equipment and materials must withstand.
Provide corrosion resistant stainless steel screws, bolts, fasteners etc. in all applications.
Provide all special instrumentation communication cables, transducer cables, power
cables, process sensing/sampling lines and capillary tubing in field measured lengths
without joins as required by manufacturer. Allow adequate cable/capillary etc., to allow
removal of instrument/transducer from process. Agree instrument-mounting locations with
Engineer to ensure accurate field measurements.
Provide mechanical protection for capillaries and transducer cables and adequately
secure to eliminate sagging.
Provide suitable shields, stilling wells or mounting plates to protect transducers.
Instruments on liquid service shall be mounted below sensing lines, with process tapping
points taken from the side of the process line.
Instruments on gas service shall be mounted above the sensing lines, with process
tapping points taken from the top of the process line.
All instruments shall be provided with process and electrical isolating devices. Valves
must be utilized on all instrument lines for easy removal without disruption to the process.
Electrical switches must be located near the equipment to allow for isolation while
servicing or installing instruments.
Local indicators must be provided for all transmitters. Local indicators shall read as
follows:
1. Temperature
Direct Reading in ºC
2. Level
0 – 100 as a percentage (%) of calibrated range
3. Flow
Direct reading in l/sec
4. Pressure
Direct reading in kPa
Where manual operation of valves is required, based on a transmitter signal value, the
indicator should be located adjacent to the valve or equipment local control panel.
Provide one (minimum) smart instrument calibration device for every ten (10) smart
instruments. Provide Rosemount model 375 HART Communicator c/w memory pack 100
and AA battery pack or vendor equivalent.
Supply any spare parts required to commission instruments. Include five (5) spare fuses
of each type and five (5) spare pilot lamps of each type in Instrument Panel.
.2
Purchase all equipment via official Ontario distribution channels that are authorized to sell, service,
and support the equipment and have the responsibility to warranty its performance. Equipment that
bypasses the manufacturer’s authorized distribution channels is not acceptable. The contractor is
responsible for any costs associated with return, repair and/or replacement of equipment later
discovered to be obtained in such a way.
.3
Supplied Instruments should be of current design. Obsolete equipment, or equipment which has
been identified for withdrawal from the market by the manufacturer before date of Substantial
Performance of the Work shall not be accepted.
.4
Supplied equipment should be new and of best quality. No used or reconditioned equipment will be
accepted.
.5
In addition to the insurance coverage required in the General Conditions, provide insurance
coverage against theft or damage for any equipment turned over to the Engineer/City during transit
to and from the place of delivery and for the period when the equipment remains on the
Engineer’s/City’s premises. Maintain coverage until equipment returned to Contractor or installed.
.6
Replacement electronics, sensors and transmitters to be stocked locally.
.7
Nonstock hardware should be available no longer than three days.
.8
On-site technical support should be available within 24 hours.
.9
Level Transmitter:
.1
Level transmitter to be Siemens Milltronics MultiRanger 100 Series with transducer:
1. Level proportional 4-20mA isolated analog output into 1000 ohm load.
2. EEMAC 4X polyester/polycarbonate alloy enclosure.
3. Measured-surface sonic intelligence echo discriminating signal processing.
4. Ambient operating temperature: -20°C to +50°C.
The City of Guelph
Lift Stations SCADA Upgrades
Page 4 of 17
November, 2008
Instrumentation and Control – Section 16900
5. Integral Digital Indicator.
6. Transducer to be XPS-10 complete with Teflon Face, transducer cabling and
submergence shield suitable for harsh environments.
7. Supply and install flange for wetwell installation
1.
6” flange suitable for wetwell
2.
All required mounting hardware and couplings.
3.
Sway rings to be installed as per manufacturer recommendations
.10
Intrinsically Safe Barriers
.1
All I/O from hazardous area to non-hazardous area to be through ISRs.
1. Two channel, Pepperl & Fuchs KFA5-SR2-Ex2.W
2. 120 VAC supply.
3. Contacts SPDT.
.2
Quantity: As required.
.11
Level Float Switch
.1
Flygt:
.2
Level switch (single) Flygt ENM-10.
.3
Contacts SPDT.
.4
Complete with lead wires to provide adequate length so that termination can be
in a dry location.
.5
EYS conduit seals for all wet well locations.
.6
Install I.S.R. for all wastewater applications.
.7
Qty: As required.
.12
Building Temperature Switch
.1
Honeywell T631A-C:
1. Output: 1 SPDT.
2. Sensor Element: Coiled copper tube.
3. Differential Temperature: 1.1°C.
4. Red Finish.
5. Wire switches in series to provide single alarm on temperature HIGH or
temperature LOW.
.13
Building Smoke Detector
.1
.2
Heat Detector
.1
.2
Simplex:
.1
Power Supply: 120V AC or 24V DC source from control panel.
.2
ULC Listed.
Contact rating 3.0 A, 120V AC.
.3
Wire detectors in series to provide a single fail-safe point to PLC for each area.
Security Key Switch
.1
2.2
Simplex Model 12098:
.1
Power Supply: 120V AC or 24V DC source from control panel.
.2
ULC Listed.
.3
Contact rating 3.0 A, 120V AC.
.4
Wire detectors in series to provide a single fail-safe point to PLC for each area.
Allen-Bradley:
.1
SPST, 120VAC, 10A keyed to Owner’s master.
.2
Allen-Bradley: P/N: 800T-H31D1
Instrument and Sensing Tubing Connections to Process Lines
.1
It is assumed that the first sensing/sample line (root) isolation valve is part of Division 16. Where an
instrument is distant (> 5m) or not visible from the process tapping point, provide isolation valves
local to the instrument, appropriate for the process fluid.
.2
Provide process sensing/sampling lines of 316 S. S. tubing, minimum diameter of 12mm (1/2”)
adequately supported and protected throughout its length. Compensate for relative movement
The City of Guelph
Lift Stations SCADA Upgrades
Page 5 of 17
November, 2008
Instrumentation and Control – Section 16900
between process pipe and instrument via a coiled or flexible sensing installation where application
requires this (vibration, high temperature etc.).
2.3
.3
Use full length tubing and minimize fittings and unions as much as possible.
.4
Provide test/calibration connection with isolating valves and removable end-caps between pressure
sensing instruments and root isolation valves. Test connection must be easily accessible.
.5
Locate all drain plugs below the lowest tubed fitting, union or valve. Slope horizontal tubing toward
drain plug by minimum 1 cm per meter. Provide drain plugs on all tubed instrument systems.
.6
Provide tubing and tube fittings from Swagelok (Avon Valve and FittingCo. (416) 438-1239)
Instrument Panel Requirements
.1
In addition to specific panel requirements set out in the Scope of Work, general requirements for
new control panels and enclosures include:
.1
The panel shop constructing the panel must be CSA certified and ISO 9002 certified.
.2
The panel shall be assembled wired and tested in entirety in the shop before shipping to
site.
.2
For new panels, provide wall mounted, CSA approved, EEMAC 12 instrument control panels
generally as follows below. For existing panel modifications the general requirements below are to
be followed.
.1
Finish:
1. Fabricate of high grade cold rolled steel (14 gauge), phosphatize, prime, and
paint with ANSI 61 Light Grey.
2. Baked enamel inside and out except on stainless steel. Subpanels to be on 12
gauge CRS finished with white baked-enamel.
3. All screws, bolts, fasteners, hinges, door handles, etc. shall be corrosion
resistant stainless steel.
4. Seal all conduits and gaps, panels must maintain their appropriate EEMAC
rating.
5. Provide 50mm stainless steel spacers between panel and wall.
.2
Panel Sizing:
1. Panel minimum width is 760mm (30''), panel minimum depth is 610 mm (24").
2. Provide 20% back panel space for additional components.
3. Provide 20% spare power circuits with secondary circuit breakers wired to
terminals.
4. Provide minimum of 20% spare terminals (no wires terminated) and 20% space
for spare terminal on the DIN rail.
5. Provide space for one additional PLC/RTU rack.
6. Provide 20% spare IO points on the installed I/O cards.
7. Provide space for LAN equipment.
.3
Wiring:
1. Refer to Section 16122.
2. Physically separate power supply cables from analogue signals and
communication cables using plastic wireways, minimum 6" wide x 3" deep
for incoming field wiring, and minimum 4" wide x 3" deep for internal wiring.
Segregate signal wiring from control power wiring according to the following
categories: 120 Vac, 24 Vdc analogue, 24 Vdc digital, communication
wiring.
3. Provide Velcro tie wraps (Hubbell or Panduit) for bundling and securing all wiring
not enclosed in duct.
4. Internal wiring not less than 16 AWG 300V single conductor stranded copper with
TEW insulation.
5. Identify all wiring with heat shrinkable slip-on markers c/w type written tag
numbers.
6. Terminate field wiring at terminal blocks with no more than two wires on each
side of the block.
7. Terminate all PLC I/O points at terminal blocks within the cabinet.
8. Tag all equipment and wire ways inside the panel with Thermal Printed Metalized
Tape.
The City of Guelph
Lift Stations SCADA Upgrades
Page 6 of 17
November, 2008
Instrumentation and Control – Section 16900
.4
.5
.6
.7
.8
9. Tag all equipment on the outside of the panel with Lamacoid Tags. Tags shall be
black with white letters.
Terminal Blocks:
1. Refer to Section 16423.
2. Provide European DIN style terminal blocks with minimum of 20% spare of each
type.
3. All terminal blocks including those on PLC terminals shall be uniquely identified
and permanently marked.
Power Distribution:
1. Refer to Section 16423.
2. Provide a 15A 120 VAC duplex receptacle powerd from UPS for networking
equipment. Tag “Communication Equipment”.
3. For UPS feed, provide a 20A 120 VAC duplex receptacle with ground fault
detector . Tag "UPS Feed."
4. Provide 120 Vac/24 Vdc (2 Amp Min.) diode protected, fail contact, power
supplies as required.. N-Tron NTPS series or approved equivalent.
5. Provide power fail relay. "Omron"H3CR-A8 c/w Base.
6. Power field mounted process instrumentation from the Instrument Control Panel.
Provide individual terminal block type secondary circuit breakers to isolate
field devices. Provide 20% spare (3 minimum) secondary circuit breakers.
7. Provide a Cutler Hammer "Aegis-HW" (15 amp, "X" enclosure, and Form C
contact) surge suppression unit for the instruments being powered from the
ICP, but not on the UPS.
8. Provide and wire UPS c/w Maintenance Bypass Switch.
Equipment:
1. Provide all signal isolators as required. Provide two minimum and two
spare.("Pribusin" ITC model or equal)
2. Provide signal isolators on all analogue signals between the control panel and
any variable speed drives.
3. Provide separate signal line transient protection units on each control signal line
that runs outside. "Entrelec" "Pheonix" or equal.
4. Provide all one-to-one isolating relays as required. Provide two minimum and two
spare. "Omron" G2R-2-SN DPDT c/w Base.
5. Provide 200 watt heater c/w thermostat and fan. ("Rittal" m/n SK 3116 or equal)
6. Provide 22.5 mm IP66 NEMA type 4/13 push buttons, pilot lights (push to test),
and selector switches as required. ."AB" 800E Series.
Grounding:
1. Ground the power system and PLC chassis in accordance with the PLC
manufacturer's recommendations.
2. Provide grounding bus bar c/w ground screws.
3. Provide vinyl insulated ring type crimp connectors for all ground connections.
4. Provide 2 ground buses, one for shield and cabinet grounding, and one for signal
grounding.
Doors:
1. Brace front access door to ensure rigidity in the open position.
2. All wiring to instruments mounted on doors shall be twisted into one bundle and
shall cross from the cabinet to the door at a shallow angle using
expandable sleeving. Provide spare wires.
3. Provide door with 3 point latches and lockable, recessed door handles c/w six
sets of keys.
4. Provide S.S. butterfly type "twist latch" door fastners for EEMAC 4x applications.
5. Provide minimum 457 x 457 mm (18 x 18 in) folding equipment shelf and mount
on the inside of the panel door.
6. All door mounted equipment shall be designed for flush mounting and shall be
properly sealed to retain the panel's EEMAC rating.
7. Locate front of panel mounted equipment so that when the panel is installed, all
devices are mounted between 75 cm (30 ") and 180 cm (72") relative to the
floor.
The City of Guelph
Lift Stations SCADA Upgrades
Page 7 of 17
November, 2008
Instrumentation and Control – Section 16900
2.4
2.5
Control Processors – PLCs, RTUs, etc.
.1
Control processors are to be suitable in all respects to perform the automated functions as outlined
in this specification and as indicated on the Process and Instrumentation Drawing(s). They must
be fully "stand-alone", capable of "distributed data processing" as well as "distributed process
control", and completely independent of external computer applications other than for supervisory
interfaces.
.2
Control related equipment is to be housed in EEMAC enclosures suitable for the application and
environment, and as a minimum are to be EEMAC 12. Instrument Control Panels are to have fully
hinged doors and key locks matching the City’s existing panels (if any).
.3
Provide all software associated with the controllers licensed in the City’s name, on original storage
media in original storage packaging:
.1
License to:
The City of Guelph – Wastewater Services Division.
.4
Provide all cables, line extenders and connection devices required for the connection of the system
and for connection of any associated programming or operator interface devices. Provide double
insulated cables unless otherwise specified. Select and provide connectors with electrical contact
surfaces gold-plated, and D-shell connectors with metal or metalized plastic (shielded type) hood.
.5
Provide components rated for continuous service under the following conditions:
.1
Temperature
0 to 60°C
.2
Relative Humidity
5 to 95%
.3
Vibration
0.25G from 5 to 100 Hertz
.4
MTBF/MTTR
> 100,000 hours/3 hours
.6
Provide a written confirmation from the manufacturer of each product stating that it is a current
product and that it will be supported (spare parts, software drivers, service, etc.) for a period of not
less than 5 years from the date of purchase. Submit confirmation with Shop Drawings.
Wire and Cable
.1
Refer to Section 16122.
.2
All wire and cable must be sized and installed in accordance with the OESC Requirements.
.3
Provide all concrete coring between floors as required.
.4
Provide adequate slack on cable harnesses to permit easy removal of I/O and other printed circuit
cards and/or modules and instruments during service or repair.
.5
All feeders shall be run in continuous lengths between power supply point and the load with no
splices.
.6
All wiring for signal system shall be identified as to circuit numbers with approved markers on the
cables at all panels and terminal strips. Where hand written markers are necessary, use the
manufacturers recommended indelible marker pen. Printing must be neat, capital alpha
characters.
.7
Include all patch panels, connect blocks, and patch cords, for a complete installation as indicated in
the tender documents. Visit the Site during the tendering period, to ascertain the actual conditions
and the extent of the work.
.8
Provide certified network test reports.
.9
Provide Site Acceptance Test with all equipment connected.
.10
Routing, installation, testing and commissioning of complete network to be carried out by a
contractor specializing in network design.
.11
Provide CAT6 unshielded twisted pair (UTP) RJ45 patch cords complete with cable strain relief
connector boots, factory assembled and tested by the manufacturer.
The City of Guelph
Lift Stations SCADA Upgrades
Page 8 of 17
November, 2008
Instrumentation and Control – Section 16900
2.6
.12
Certify that the patch cords supplied under this Contract meet or exceed the requirements for CAT
6 UTP patch cords as described in the TIA/EIA-568-B standard. Provide written certification from
the manufacturer at the time of shop drawing review.
.13
The Contractor is responsible for determining the length of patch cords.
.14
Use durable non-fading sleeve type wire markers to identify all network cables. Identify both ends.
.15
Provide 2 – 3 meter CAT6 UTP patch cords complete with connector boots spare and leave in the
print pocket of the ICP.
Expendable Media
.1
EXECUTION
PART 3.
3.1
3.2
For any instrument or system peripheral which uses expendable media such as recorder chart
paper, printer paper, diskettes, analyzer reagents & membranes, filters, etc., supply enough media
sufficient for one year of operation from the date of Substantial Performance of the Work and
deliver the media to the Engineer prior to application for the Certificate of Substantial Performance.
Coordination
.1
Carefully examine and monitor for compatibility, any instrumentation and control Work provided as
part of the Work of Sections of the Specification other than the Sections governed by this Section,
or the City, and ensure that all trades involved are aware of any coordination problems or details.
.2
Incompatible work, such as instrument process connections, mounting of equipment, analogue,
discrete or communication wiring, voltages, or inconsistencies resulting from insufficient
coordination of other related work, is to be satisfactorily resolved at no additional cost to the
Contract.
.3
When scheduling site inspection, FAT, commissioning or SAT with the Engineer, allow at least ten
(10) working days advance notice.
Manufacturer’s Services and Certification of Installation
.1
Allow in the tender for all the necessary services and expenses of trained, qualified manufacturer’s
representative for each piece of equipment to ensure correctness of installation, testing, start-up,
commissioning and training. The qualified representative to:
.1
Provide onsite supervision of installation for the initial and critical stages of the work as
agreed with the manufacturer/supplier and as required by the Engineer.
.2
Supervise testing and calibration of equipment. Supervise retesting and recalibration of
equipment at no additional cost to the City.
.3
Provide written certification stating that the work has been completed satisfactorily.
.4
Provide a complete Installation, Start up Check list and sign off on the start up work
completed.
.5
Provide operation and maintenance instruction to the City’s operating staff.
.2
Provide supervision of installation as required by the manufacturers for all equipment in this
Division. The City/Engineer may order additional supervision at no cost to the City if, in their
opinion, installation procedures are compromised.
.3
Provide all materials, labour and equipment to make any adjustments to the installation as required
by the manufacturer or the Engineer to effect performance.
.4
On completion of installation and testing, obtain certification from the manufacturers that the
equipment is installed correctly, is in full operating condition, and is operating in accordance with its
design rating. Submit the original certificate to the Engineer.
.5
Include the service of the trained personnel to inspect and commission the equipment when ready
for starting and to instruct the operating personnel in the operation and maintenance of the
equipment. Time spent on site by the trained personnel must be witnessed by the Engineer.
The City of Guelph
Lift Stations SCADA Upgrades
Page 9 of 17
November, 2008
Instrumentation and Control – Section 16900
3.3
3.4
.6
Include above services for all equipment specified in relation to this Section and as a minimum
provide commissioning and training as follows:
.1
Major process equipment - See the list below. Split the specified time into three stages:
inspection during installation, start up and commissioning, staff training.
.2
2 (8 hr) days for all other process equipment, where not specifically mentioned, of which
0.5 days minimum dedicated to training.
.7
As a minimum requirement, allow for in the Quotation Price, the following on site time for the
services’s of a qualified manufacturer’s technical representative. Not all days will necessarily be
concurrent. If additional days are required to complete the Work, include these additional days and
trips in the Quotation Price.
.1
Ultrasonic Level Transmitters
2 days
.2
Magnetic Flow Meter
1 day
.3
Pressure Transmitters
1 days
.4
Pressure Switches
1 day
.5
Uninteruptable Power Supplies
1 day
.6
Equipment not mentioned
2 days
Panel Inspection & Factory Acceptance Testing (FAT)
.1
Make all of the necessary arrangements with equipment supplier(s) for panel inspection and FAT
prior to delivery. Required for new control panels to be supplied under this contract.
.2
Schedule the session(s) with the Engineer a minimum of ten (10) working days in advance. Allot
enough time for thorough testing and corrections to take place.
.3
Panel inspection and FAT is to be performed in the presence and to the satisfaction of the
Engineer, and is to include all devices necessary to simulate actual operating conditions.
.4
Configure the PLC, Network, and SCADA Station with a suitable “dummy” or shell program,
establish communication, temporarily wire digital inputs to test switches and digital outputs to
indicating lights, analogue inputs to 4-20mA generators and analogue outputs to panel meters to
demonstrate functionality of all hardware and software. Exercise the hardware (i.e. I/O,
communications, panel mounted instruments, etc.) with appropriate software in place to
demonstrate/monitor operation of all connected equipment and wiring.
.5
Make the necessary corrections as indicated by the tests, or as directed by the Engineer.
Shipment of equipment to site is contingent on the Engineer's approval.
General Installation Requirements
.1
Unless otherwise specified, install and calibrate instrumentation and control system hardware in
strict accordance with the manufacturer's instructions and/or recommendations.
.2
Advise the Engineer of any perceived problems regarding implementation of installation details or
standard practices for the particular Project application in sufficient time to avoid delays to the
Project.
.3
If any requirements of this Specifications, or a drawing detail, contradicts the equipment
manufacturer's instructions or recommendations in a manner which could be detrimental to its
operation, including the possibility of inducing adverse side effects elsewhere to the system,
immediately notify the Engineer in writing and refrain from installing until the problem is resolved.
.4
Confirm the correct locations for equipment with the Engineer prior to installation and/or roughingin.
.5
Supply any materials and/or test facilities necessary for commissioning. The use of the City's
facilities, if suitable, may be considered, but not guaranteed, upon written request.
.6
Prior to the shutdown of any operating equipment, provide a written notice 48 hours in advance to
the City/ Engineer. Shut down of equipment is limited to a length of time determined by the City,
make all arrangements to minimize down time.
The City of Guelph
Lift Stations SCADA Upgrades
Page 10 of 17
November, 2008
Instrumentation and Control – Section 16900
3.5
Installing Instruments
.1
Install, test, calibrate and commission instruments in accordance with this specification, drawings
for construction and any special details where they apply. Where installation details are not
indicated, conform to the manufacturer's instructions and/or API RP550 recommendations.
.2
Unless otherwise shown or specified, all required mounting hardware, enclosures, termination's,
junction boxes, etc., are to be provided. Refer to the contract drawings and the manufacturer's
documentation to confirm the necessary hardware and construction for specific mounting
assemblies where such details are not specified herein.
.3
Do not mount instruments on vibrating structures (e.g. handrails), or on piping or near equipment
which induces vibration. Do not mount instruments below or directly adjacent to lines conveying
corrosive chemicals or near sources of leakage or spillage.
.4
Prepare metal surfaces and paint supports or frames the same colour as the member the complete
assembly is mounted on.
.5
Locate instruments and their associated sensors, local isolation valves, isolation switches and other
related accessories so that they are readily accessible for operation, maintenance or removal.
Ensure that instrument displays are properly oriented so as to be easily viewed. Unless otherwise
shown or specified, mount instruments 1.4 m above finished floors, grade or platforms. Allow for
cabinet plinth/floor-pad heights when locating panel instruments. Any instrument which is not easily
accessible for operation or maintenance, or any indicator that is not easily and readily visible must
be relocated as directed by the Engineer at no charge to the contract.
.6
When drilling or installing conduit entry points in instruments, protect internally mounted equipment
from vibration, shock and metal filings. Conduit entries must maintain the equipment or panel
EEMAC rating.
.7
Field measure lengths for transducer cables, and similar items prior to ordering. Mechanically
protect cables and adequately secure in place without sagging.
.8
For location, power, mounting and other related details, refer to the manufacturer’s installation
details and to the instrument and electrical drawings issued for construction.
.9
Provide isolation valves for all instruments.
.10
Protect all instruments with capillaries throughout their length without sagging, by using
painted/galvanised angle iron and clips. Avoid sharp bends in capillary and coil any excess close
to the sensor end. Protect the coiled capillary by clipping to a steel plate or other safe method.
.11
Sensing and sample lines are to be run in 1/2" stainless steel tubing with “Swagelok” compression
type fittings.
.12
Electrically heat trace all instrument sensing and sample lines liable to freezing.
.13
Install process sample piping and sensing lines to avoid accumulation of vapour or gas (in liquid
service) and of liquid or condensate (on vapour or gas service) as appropriate.
.14
Position instruments so that they do not block or obstruct walkways or access points and provide
adequate space around installation for removal of covers, etc.
.15
Standard instrument process connections of 1/2" NPT female are to be provided (Pressure gauges
normally 1/2" NPT male).
.16
Instrument support brackets may not be welded to process piping or equipment, but should
generally be pedestal or wall mounted.
.17
Run field cables for analogue signals in separate conduit from 120Vac/24Vdc control or 120 Vac
power supply cables.
.18
Use field junction boxes suitable for the area classification to "marshal" groups of signals of the
same type in an area and cable back to buildings and local control panel with multicore cables.
The City of Guelph
Lift Stations SCADA Upgrades
Page 11 of 17
November, 2008
Instrumentation and Control – Section 16900
3.6
3.7
.19
Junction boxes may be FRP (fibreglass reinforced plastic) or similar material suitable for the area
and rust and weather resistant. Terminals inside field junction boxes are to be DIN rail mounted.
.20
Provide the necessary mechanical shields, mounting plates to properly secure and protect
transducers. Provide stilling wells wherever turbulence can adversely affect measurement.
.21
Once an instrument has been inspected by the Engineer and initially calibrated, it is to remain
powered up at all times unless servicing the instrument itself. Immediately install keepers on all
panel circuit breakers powering instruments.
.22
Instrument calibration, setpoints and other programmable parameters are to be confirmed with the
Engineer during on-site inspection as soon as site conditions are sufficiently ready. Final
calibration values will be confirmed on site at no extra cost to the Contract.
Installing Control Equipment
.1
Install, test, and commission controllers in accordance with requirements of this specification,
drawings for construction, and any special details as they apply. Where installation details are not
indicated, conform to the manufacturer's instructions and/or API RP550 recommendations.
.2
Install PLC and other related peripherals in EEMAC panels as indicated on the drawings. Mount
floor-standing panels on a 100mm (4”) concrete pad if stand-alone, at the same height as other
panels if part of an existing suite or MCC installation.
.3
Locate and install controllers and panels so as to be easily accessible for maintenance and
readability of displays.
.4
Displays and keyboards are to be protected during the construction and commissioning period, but
remain readily accessible on the panel's exterior.
.5
When drilling conduit entry points in panels, protect internally mounted equipment from vibration,
shock or metal filings. Panels and conduit installations made to them must maintain their
appropriate EEMAC rating. Confirm panel location with Engineer/City prior to fixing.
.6
Following Site Acceptance, provide to the Engineer a minimum of six (6) identified control panel
keys for each panel.
.7
Wire all spare I/O to terminal strips and terminate according to the Manufacturer’s
recommendations.
.8
Follow the Manufacturer’s recommendations for loading resistors on digital outputs to limit the
affect of leakage currents through triac and relay outputs.
.9
Follow the Manufacturer’s recommendations for surge suppression on inductive loads.
.10
Once ICP’s are installed and sufficient field wiring is in place to power up the PLC’s, immediately
install keepers on any lighting panel or MCC circuit breaker feeding the ICP. Unless otherwise
authorized by the Engineer, the ICP and PLC are to remain powered up at all times.
.11
Once PLC’s are installed at site and sufficient field wiring is in place to begin commissioning
software, take the necessary steps to prevent hardware failure or unauthorized tampering with
running control programs. Ensure ICP’s and PLC’s are not inadvertently switched off or crashed by
unsanctioned activity.
System Wiring Requirements
.1
Refer to Section 16122.
.2
Provide all required system wiring. All wiring shall conform to the latest revision of the Canadian
Electrical Code and to the Electrical Area Classification for Hazardous Locations where applicable.
.3
Where specific wiring types are not specified (except AC power wiring) provide types of wiring as
recommended by the system component manufacturers.
.4
Seal all conduit termination's to prevent moisture penetration.
The City of Guelph
Lift Stations SCADA Upgrades
Page 12 of 17
November, 2008
Instrumentation and Control – Section 16900
3.8
3.9
.5
Install lightning and surge protection on all analogue signal cabling entering or exiting buildings.
Provide two spare units.
.6
Install signal isolators (24Vdc externally powered if not loop-powered devices) on all analogue
loops and LAN systems with cabling running outside buildings, speed control signals into variable
frequency drives and soft starts, and any situation where potential EMF could damage electronic
equipment. Provide two spare isolators.
.7
Unless specifically shown otherwise, wire all digital alarm contacts “normally open”, “close to trip”.
.8
Use only manufactured molded cable assemblies between computer and peripherals, such as
printers, RS-232, Ethernet, etc. Unless otherwise approved by the Engineer, do not supply
custom-made cables. Where custom cables are allowed, connectors must be complete with proper
shells and able to withstand physical bending and twisting.
Identification and Tagging
.1
Refer to Section 16010.
.2
Use the City tag identifier and designated service and with the approved wording submitted in shop
drawings. Instrument tag names conform to City conventions and to the P&ID issued. Refer to the
contract drawings for the correct tag prefixes, loop numbers and service descriptions.
Instrumentation & Controls Field Pre-Commissioning
.1
All field testing, calibration procedures, commissioning procedures, etc. shall be approved by the
Engineer.
.2
Prepare Instrument Calibration Forms for every field instrument and Loop Check Sheets for every
Control Loop. Submit the forms for approval prior to commencing commissioning activities.
.3
Supply all materials, equipment and labor necessary for testing calibration pre-commissioning,
commissioning and repair and be prepared to present proof of recent calibration for test equipment.
.4
For Control Loop Checkout/ Verification, arrange for the Contractor, electrical, instrumentation and
control sub-contractors for testing of loop wiring between instrument and field devices and advise
the Engineer to be present for the procedure.
.5
When testing instrumentation loops, perform the testing of each loop in sequence. The testing of
instrument loops will be graded on a pass/fail basis. If instrument loops fail the loop checkout,
loops will be deemed to have failed the checkout. When the failed loops have been repaired, the
loops must be retested.
.6
Prior to installation of application programs for automatic control, all installations must be proved
correct and fully operational as outlined below.
.7
After the instrumentation and control system has been initially visually inspected for proper
installation, including any specified vendor inspection, but prior to any introduction of process
fluids/materials to the facility (if retrofit on existing process, submit proposed testing method),
energize the system loop by loop and:
.1
Check and test the operation of each and every system component, and adjust or repair
as necessary
.2
Confirm all instrument calibration parameters, i.e. 4-20mA span and displayed ranges,
with the Engineer
.3
Check the calibration of each instrument, and where necessary, re-calibrate in accordance
with the manufacturer's instructions
.4
Ensure that calibration and commissioning work is carried out by qualified technicians,
and have the work performed by the manufacturer's service representatives if so specified
.5
Prepare typewritten record on each Instrument Calibration Form of the calibration, repair
or replacement work performed and submit to the Engineer. Enter the calibration
information and any other relevant details about each instrument on the Product Data
Sheets as per Section 1.0 of this Specification.
.6
Loop check all field signal wiring for continuity and correct contact polarity. Ringing wires
from terminal strips is insufficient. Check each loop by interrogating the controller I/O via
The City of Guelph
Lift Stations SCADA Upgrades
Page 13 of 17
November, 2008
Instrumentation and Control – Section 16900
.7
.8
.8
3.10
on-line utilities and exercising field equipment to confirm correct field operation. Field
actions include power-up instruments, set-up calibration, energize MCC starters (disabling
power feeds as appropriate) testing hand-off-auto switches, tripping field pressure, float
and level switches etc.
Do not perform insulation tests or “megger” tests on any instrument wiring connected to
field or panel equipment
When the inspection, testing, and calibration is complete, submit Instrument Calibration
Forms, Loop Check Sheets and Product Data Sheets and advise the Engineer in writing
that all equipment has been checked and is ready for introduction of process fluids or
material
Once process fluids or material have been introduced to the facility, or part of process:
.1
Repeat the above checks to confirm that the equipment operates correctly when actuated
by actual process fluid or material: e.g. that high level alarm float switches are actuated at
the correct height by a rising fluid, and low level switches operate correctly on a falling
fluid level.
.2
Prove the operation of all equipment in manual mode before attempting automatic control.
In the event that automatic control is achieved by a software application program, the
latter will not be loaded until manual operation is proved.
.3
Forward to the Engineer a letter certifying that the instrumentation and control system is
complete, operational, and ready for site acceptance.
.4
Each and every Instrument calibration, Final Loop Check and equipment operation checks
will be witnessed by the Engineer. Upon satisfactory demonstration of instrument and/or
loop operation, the Engineer will sign off the Product Data Sheets, Calibration Forms and
Control Loop Check Sheets. The instrumentation and control system will then be
considered ready for testing control software, and finally Site Acceptance Testing.
.5
Instruments, loops and equipment which are found to be inoperable or improperly
calibrated, will immediately be rejected. The associated equipment must be rectified, recalibrated and sheets revised and resubmitted as soon as the problem is resolved.
.6
If three or more such instances occur, the Contractor will be requested to repeat all precommissioning checks.
.7
When all equipment, instruments and systems have been demonstrated and Product Data
Sheets, Instrument Calibration Forms and Loop Check Sheets have all been signed off,
forward a complete set of the signed sheets to the Engineer.
Controller Application Program Installation, Testing & Control System Commissioning
.1
When field pre-commissioning of the instrumentation and control system has been completed as
specified above, schedule with the Engineer the installation and testing of the Application Program.
.2
Schedule a minimum of ten (10) working days for installation of the Controller/SCADA programs
and the associated testing.
.3
Include for the presence of qualified instrument technicians and component manufacturers
representatives to assist the installation and testing of the Application Program. Testing is to
include proper operation and integration of all aspects of the system under all operating conditions.
.4
Coordinate all commissioning activities with sub-contractors as required. Supply all labor and
materials required to coordinate instrument and controls commissioning with other trades.
.5
Provide all labour and materials necessary to commission and operate the system for the fourteen
(14) day wet test. During this time all equipment is expected to run in automatic mode.
.6
Perform the commissioning activities associated with operation of the plant under control by the
software program, in co-ordination with the City/Engineer.
.7
Take all necessary steps to ensure that all equipment or parts of system successfully tested and
deemed ready for its intended use stays in operation.
.8
Provide clear signs/marking as to required status on the equipment which is to remain powered up,
left in Auto, or remain Off etc., during the commissioning period. Agree the method of achieving this
with the Engineer/City and ensure safe and compliant operation of the facility and equipment at all
times.
The City of Guelph
Lift Stations SCADA Upgrades
Page 14 of 17
November, 2008
Instrumentation and Control – Section 16900
3.11
3.12
3.13
.9
Adopt a recognized lock-out policy and agree on it with Engineer. Coordinate the requirement for
lock-out for safety reasons with the schedule commissioning program so that all equipment needed
to commission a process/area is available concurrently.
.10
Make minor corrections/additions to wiring, terminations, instrument calibrations and settings as
normally expected necessary to resolve operational problems during commissioning at no
additional cost.
Site Acceptance Testing (SAT)
.1
When initial site inspections and commissioning of the instrumentation and the control system is
satisfactorily complete, schedule Station Commissioning with the Engineer/City to demonstrate the
entire system in operation.
.2
Prepare and submit an itemized Test Plan for the SAT based on the current City of Guelph WSD
standards.
.3
Include for the presence of qualified instrument technicians and equipment manufacturer's
representatives to supervise the test if requested by the Engineer. Testing is to demonstrate the
proper operation of all aspects of the system under actual operating conditions to the satisfaction of
the Engineer. This includes proper operations and communications between PLC’s, and all
peripherals devices. Supply all labor, instruments and materials to perform the testing.
.4
The SAT must be satisfactorily completed prior to applying for a Certificate of Substantial
Performance.
.5
Deliver all software, panel keys etc. to the Engineer.
Training
.1
Supply site training program for the plant operating personnel to consist of:
.1
Maintenance Training (8 hours) in two groups of 4 hours each by Instrument Supplier
and/or appropriate equipment manufacturer’s representatives.
.2
Operator training (8 hours) in 4 groups of 2 hours each by Instrument Supplier.
.2
Dates and personnel receiving training will be coordinated by the City.
.3
The training program is to be conducted by qualified instrument technicians and competent
manufacturer’s personnel experienced both with the product and with instruction, and is to use
system operation and maintenance manual data as the basis for demonstrations and instructions.
.4
Training shall take place at the site or at the equipment itself. Operation and maintenance manuals
shall be submitted to the City a minimum of fifteen (15) days prior to the training occurring for use in
the training course.
.5
The training program is to include routine maintenance of the equipment.
.6
The site training program must be complete prior to application for a Certificate of Substantial
Performance of the Work.
.7
Pay all cost associated with the training program, with the sole exception of salaries associated
with the operating personnel being trained.
.8
Submit a course outline to the Engineer for approval fifteen (15) days prior to the start of the
course. The Engineer reserves the right to modify the course content.
Process Performance Operation (Wet Test)
.1
Provide all labor and materials necessary to support the process and the instrumentation and
control system for the duration of the contract performance run. During this operation all equipment
is expected to run in automatic mode.
The City of Guelph
Lift Stations SCADA Upgrades
Page 15 of 17
November, 2008
Instrumentation and Control – Section 16900
3.14
Warranty and Guarantee Period Activities
PART 4.
.1
During the warranty period, hardware service should be provided by a factory trained service
representative who shall be on-site within 24 hours of a service request, 7 days/week, including
weekends and holidays. The service representative shall be equipped with all necessary tools,
testing equipment, spare parts, and expertise to perform the service in one visit.
.1
For each service call submit a report giving the following information:
1. Part numbers, description and prices for items replaced
2. Revised hard copy/soft copy listings of program and configuration changes
3. Hours worked by maintenance personnel
4. Reason for the service call, and whether preventative, unscheduled or corrective
maintenance was carried out
5. Name of City’s technician present during repairs. Explain the problem and
solutions to the City’s technician(s)
6. Description of problem as discovered on arrival at site and itemized report of
activities performed to isolate and correct problem
7. Identification of any required actions to prevent similar future occurrence
8. Name of attending operations representative, time of call and time of arrival on
site
.2
A single contact point shall be provided for all hardware such that the City's representative need
only call a single phone number irrespective of which piece of hardware had failed.
.3
The City’s technician(s) may be present during repairs. Explain the problem and solutions to the
City’s technician(s).
.4
Free telephone support shall be provided for the total system and all parts thereof during the first
year after commissioning.
.5
Spare Components / Firmware & Software Upgrades:
.1
The supplier should have access to a dedicated spare parts inventory for each component
provided. Parts shall be available within 24 hours of a service parts request, 7 days/week.
.2
Include key spare parts which are not normally available immediately from stock, in the
Recommended Spare Parts List.
.3
Provide, install, test and place in operation (see item 4. below) any firmware upgrades
issued by manufacturers to address shortcomings in delivered products during the
warranty period at no cost to the project.
.4
Provide and install all software upgrades relevant to correcting deficiencies during the first
year after commissioning at no cost. Such upgrades must be coordinated through the
authors of the original application software. Similarly advise the City of any software
upgrades and enhancements which would be of benefit for the installed system.
.5
Advise the City/Engineer of software upgrades and new versions which become available
that would benefit or enhance the installed system.
DRAWINGS AND DOCUMENTATION
.1
.2
.3
Process & Instrumentation Block Diagrams (Supplied)
1. Issued P&ID's summarize physical signals as well as a limited portion of pseudo
signals, each identified by their corresponding ISA tag name, and
graphically depicts the various process relationships and strategies
required to monitor and control specific field equipment or areas of the
process. P&ID's form the basis of all automated field tasks of control
system, including the application of each field instrument. P&ID's are
intended as the main reference for all matters related to instrumentation,
the control system or methods governing plant operation
I/O & Auto Dialer Listings
1. Normally issued as part of this Section, I/O Listings identify each controller's
physical inputs and outputs, their function, including derived pseudo
variables. Variables are referred to as "signals" or "signal records", and
each signal identified by a globally unique ISA tag name.
Control Description
1. This is a written description of how the Process is to be controlled
The City of Guelph
Lift Stations SCADA Upgrades
Page 16 of 17
November, 2008
Instrumentation and Control – Section 16900
.4
.5
4.2
Loop Termination Diagrams (By Contractor)
1. In conjunction with, or in the absence of I/O, Loop Termination Diagrams or
"Loop Sheets" depict physical signals or "field I/O wired to controllers".
Each physical signal or wired loop is identified by its corresponding ISA tag
name. These drawings may be used to ascertain the approximate I/O
count and assignment of each controller.
2. The Contractor is required to prepare and submit red lined versions of these
drawings updated with "as-constructed" details regarding termination
numbers, communications & power supply connections, added or deleted
I/O, etc.. For further details, refer to Part 1 of this Section.
Workstation Software (By Contractor)
1. Deliver copies of Work Station Application Software with manuals
Magnetic Media
.1
Provide six (6) copies in three-ring binder sleeves containing CDs with the following:
1. O&M Manuals
2. Product Data Sheets
END OF SECTION
The City of Guelph
Lift Stations SCADA Upgrades
Page 17 of 17
November, 2008
Download