Energy Performance Contracting for street lighting Christiane Egger OÖ Energiesparverband christiane.egger@esv.or.at www.esv-en.at www.streetlight-epc.eu www.streetlight-epc.eu The challenge • 56 million street light luminaires (62 million street lamps) in operation in Europe, estimated electricity consumption of 35 TWh • For municipalities with older, inefficient systems, street lighting accounts for 30-50% of their total electricity consumption, with enormous savings potentials: often 30-70 % • Savings potential recognised by EU policies: phasing out of nearly 80 % of all lamps currently in operation until 2017 (meaning: they can not be purchased anymore - similar to incandescent light bulbs) www.streetlight-epc.eu What can municipalities do? • Lamps only replacement - "plug-in" ("re-lamping") often technically not possible (no lamps available) and even if, technical problems likely low savings • Replacing both lamps and ballasts lamps and luminaires then often do not fit well likely to result in a loss of warranty on the whole system • Reduction street lighting services on "an ad-hoc basis" (broken lamps are not replaced anymore) negative impacts on safety and public perception risk of liability for accidents (in cases of a legal obligation) • Replacing luminaires (including lamps and ballasts) by efficient and long-lasting systems (usually LEDs) high upfront investment costs www.streetlight-epc.eu LED streetlighting - life cycle costs Costs over the lifetime Costs in 5 Lamp type years (Euro/lamp) Costs in 15 years (Euro/lamp) Investment Electricity Maintenance Total costs Investment Electricity Maintenance Total costs High Pressure Mercury Lamp 4 321 230 555 12 964 690 1666 High Pressure Sodium Lamp 20 214 230 464 68 623 690 1401 160 67 75 302 319 201 225 745 LED www.streetlight-epc.eu Energy Performance Contracting • a key instrument to finance and implement economic energy efficiency investments • streetlighting refurbishment an "ideal" application field! • Energy performance contracting is (from the EED): - a contract between a client (= municipality) and a provider of an energy efficiency measure (= ESCO) - investments (work, supply or service) are paid in relation to a - contractually agreed level of energy efficiency improvement (or another criterion, such as financial savings) - verified and monitored during the whole term of the contract www.streetlight-epc.eu What is "Energy Performance Contracting"? Example OÖ Energiesparverband energy cost reduction contract start energy costs after investment before investment energy costs refinancing investment contract end time Energy efficiency investments are pre-financed and implemented by an energy service company (ESCO), the annual energy savings then cover the investment and capital costs. After the expiration of the contract, the client benefits from the energy and cost savings. www.streetlight-epc.eu Overcoming "the chicken or the egg" problem The "no demand, no supply" challenge ESCOs • specialists in energy efficiency • qualified in technical operation of plants/buildings • good understanding of contractual & financial issues • able to finance the investments The clients (= municipalities) • understand the business model • develop trust • overcome legal constraints Pressure created by phasing out of streetlamps is a real opportunity for starting EPC markets! www.streetlight-epc.eu New IEE project: Triggering the market uptake of energy performance contracting through street lighting refurbishment projects Streetlight-EPC Project duration: 1 April 2014 – 31 March 2017 www.streetlight-epc.eu www.streetlight-epc.eu Background So far, in most European regions, energy performance contracting (EPC) has not been able to develop significantly. Street lighting is a good "learning and testing ground" for EPC due to its lower technical and economic complexity. The recent market introduction of LED technology for street lighting offers high savings with comparatively short pay-back times. This creates an opportunity: • to establish EPC markets & trigger the uptake of guaranteed energy services • to support the market introduction of efficient lighting technologies and • to support municipalities in "phasing-out" of street lighting lamps www.streetlight-epc.eu Project summary • creates demand and supply for EPC projects in 9 regions by setting up regional EPC facilitation services (providing comprehensive support both to municipalities and to SMEs as potential ESCOs). • performs real-life procurement of 36 EPC street lighting projects during the project life, creating knowledge and trust in both LED and other street lighting technologies and the EPC model. • The project team: 9 regional agencies/organisations (providing the EPC facilitation services) and 9 municipalities (committed to implement EPC projects) www.streetlight-epc.eu Main project activities Triggering the market uptake of energy performance contracting through street lighting refurbishment projects: • • • • • • • • • Organising 45 regional meetings with a total of over 500 participants Completing 90 "Streetlight-EPC quick-checks" Providing advice to 270 enquiries Reaching out to more than 4,000 municipalities Supporting 50 SMEs Making regional learning and feedback processes happen Trans-regional learning and exchange of experiences Extending the learning to indoor lighting applications Transferring the knowledge to other European regions www.streetlight-epc.eu Partners • 19 partners in 9 countries • 9 regional partners, 9 city partners, 1 European network • co-ordinator: OÖ Energiesparverband Region Upper Austria/Austria North-West Croatia South Bohemia/Czech Republic Pomerania/Poland Carlow & Kilkenny County/Ireland South East Sweden Podravje/Slovenia Macedonia North/Central Spain (regions of Madrid, Castilla y Léon, Cantabria) Regional partner ESV REGEA ECCB BAPE CKEA ESS ENERGAP MACEF ESCAN www.streetlight-epc.eu City/county partner City Wels Zagreb County City of Trhové Sviny City of Gdansk Kilkenny County City of Kalmar City of Maribor City of Skopje City of Santander EPC facilitation services Upper Austria (1) • programme managed by the OÖ Energiesparverband which combines financial incentives and information activities • targeting the "supply" (ESCOs) and the "demand" (potential clients, e.g. municipalities) of EPC services • continuous information and awareness raising activities ESCOs: information & training Clients: targeted information to target groups Promotion of successful examples Support the desicion making process www.streetlight-epc.eu EPC facilitation services Upper Austria (2) • Project advice: Individual advice both to ESCOs and clients, pre-check of contracts • Comprehensive information on our website, e.g.: a list of ESCOs, project examples, contract information, funding sources, FAQs • Publications • Training courses (e.g. "Energie-Contracting" in the Energy Academy) • Conferences & events (e.g. "Breakfast for Mayors" on streetlighting) • Including EPC in many other information channels (e.g. energy advice programme for company, training courses etc.) www.streetlight-epc.eu The EPC facilitation services Upper Austria (3) What did we learn? • We need "in-house know-how": building up know-how within the organisation at a first step • "explain, explain, explain": the EPC concept and its the concrete implementation need significant and continuous efforts in explanation • providing targeted advice at all project stages • taking a "quality approach" (better fewer projects, but these are very good) • main bottleneck: limited number of ESCOs reasons: - access to capital (after the first few projects) - risks associated with the provision of EPC services www.streetlight-epc.eu ! The EPC facilitation services Upper Austria (4) • more than 100 projects realised • the first years were challenging and the programme started very slowly ("Nigerian eMail phenomenon") • 15 ESCOs are listed on ESV website and in total more than 30 ESCOs are established which offer ESCO services in Upper Austria • EPC has found its place in the portfolio of sustainable energy solutions in Upper Austria www.streetlight-epc.eu Example Kremsmünster: In 2 Steps • population: 6,400 First step: • LEDs tested at the main square (12 luminaires ) • Increase of level of illumination from 1.5 to 10 lux • Investment: 6,700 € • Savings: 2.300 kWh (about 20%), 220 €/a electricity costs, 300 €/a maintenance Second step: • Renovation of total streetlighting (693 luminaires) • Investment: 598,700 € • Savings: 48,882 €/a, 146,020 kWh/a (53.5%) • Contract duration: 10 years (2013-2023) www.streetlight-epc.eu Example: City of Wels • streetlighting renovation project in the city of Wels (population: 61,000) • 4,200 luminaires (50 % of all luminaires), including all lamps older than 15 years, replaced by LEDs • improved control systems (e.g. 1/3 of the lamps are now dimmed between 21:30 - 05:00) • Investment: 2,100,000 € • Savings: - 47% guaranteed by the ESCO - 1,300,000 kWh/a - 250,000 €/a, 60,000 €/a maintenance costs • Contract duration: 10 years (2012 – 2021) www.streetlight-epc.eu World Sustainable Energy Days 2015: 25 - 27 February European Nearly Zero Energy Buildings Conference Energy Efficiency Policy Conference Young Researchers' Conference European Pellet Conference Trade Show - Energiesparmesse: +1,600 exhibitors Call for Papers: 10 October 2014 www.wsed.at Streetlighting & EPC now is the time to get active! Christiane Egger OÖ Energiesparverband christiane.egger@esv.or.at www.esv-en.at www.streetlight-epc.eu www.streetlight-epc.eu “Phasing out” • Phasing out means that these product groups will no longer be placed on the market and can not be purchased any more. • Nearly 80 % of all lamps currently in operation will be affected by the phase-out: among them 26 million High Pressure Sodium (HPS) and 18 million High Pressure Mercury (HPM) lamps. 2012 2015 2017 Ausphasen von T12 (38 mm) Leuchtstofflampen ("dicke Leuchtstofflampen") Natriumdampf-Hochdrucklampen und Halogen-Metalldampflampen müssen bestimmte Effizienzkriterien erfüllen Ausphasen von Quecksilberdampf-Hochdrucklampen und von Natriumdampf-Hochdruck-Plug-In-Lampen*/Retrofit-Lampen höherer Wattagen (Plug-inLampen müssen Super/Plus HPS Level entsprechen) (*oft als Ersatz für Quecksilberdampf-Hochdrucklampen beworben) höhere Anforderungen an Halogen-Metalldampflampen Ausphasen konventioneller magnetischer Vorschaltgeräte. Nur mehr elektronische Vorschaltgeräte (EVG) sind zugelassen. Folgende Auslaufphasen sind im Wesentlichen vorgesehen: Weitere Details siehe EU-Verordnung 245/2009 (http://eur-lex.europa.eu/de/index.htm). www.streetlight-epc.eu ESCO contracts - requirements Crucial points that have to be decided in the contracts (examples): • what happens in case of bankruptcy of a contracting party? • what happens if the designated use of the building changes? • what are the provisions for changes of energy prices? • what happens in case of damages or losses (maintenance?) • ownership issues after the contract end? • what happens if the building is sold? • for efficiency contracting: consequences if the agreed savings are not achieved In addition, the Upper Austrian programme requires the following criteria: • the ESCO has to prove that it has the necessary technical skills • proof of their financial standing ("Bonität") has to be provided by the ESCO and the client • a detailed energy analysis of the project has to be carried out But not standard contracts or contract templates! www.streetlight-epc.eu ESCOs A qualified ESCO: • has a list of references • is able provide proof of its financial standing • prepares the project well and provides a clear cost-/benefits analysis • involves and trains buildings staff and users • proposes a clear devision of tasks between ESCO and client • proposes a well structured contract which also includes provisions for "difficult" situations (e.g. bankruptcy, changes of ownership etc.) www.streetlight-epc.eu Wirtschaftlichkeit von LED Investitionen • Soll der Ersatz einer bestehenden Leuchte ausschließlich über die Energieeinsparung finanziert werden, kann unter Zugrundelegung folgender Konditionen (15 ct/kWh, 4 % Verzinsung/a), bezogen auf die Lebensdauer der LED von 50.000 Stunden (bei Brenndauer von 4.100 h/Jahr ca. 12 Jahren) von folgender Faustformel ausgegangen werden: • Pro kWh Einsparung können ca. 1,41 Euro investiert werden • jede jährlich eingesparte kWh bringt, hochgerechnet auf die typische Lebensdauer der LED (12 Jahre bei 4.100 h/a), eine finanzielle Ersparnis von ca. 1,41 Euro (inkl. USt.). • Dies gilt bei einem konstanten Strompreis (werden Verzinsung und Strompreissteigerung gleichgesetzt, liegt der Wert bei 1,8 Euro). • Aus unserer Broschüre www.streetlight-epc.eu EPC facilitation services Upper Austria (2) • programme started in 1998 • supports energy efficiency contracting ("Einspar-Contracting") and renewable energy supply contracting ("Anlagen-Contracting") • clients can be companies, institutions or municipalities • the programme combines: - comprehensive promotion activities (awareness raising, training, events, publications, advice to both ESCOs and clients on their specific projects) - a subsidy (up to 20 % for energy efficiency and up to 13.5 % for renewable supply contracting), contract periods of max. 10 years, supported investments: 50,000 - 500,000 Euro www.streetlight-epc.eu City of Wels – LED Großprojekt • Die Straßenbeleuchtung in Wels umfasst rd. 7.700 Leuchten mit 9.100 Lichtpunkten. • Vor der Sanierung 2011 waren QuecksilberdampfHochdrucklampen (HQL), Natriumdampflampen, Plug-in-Lösungen, Leuchtstofflampen im Einsatz. • alle Lampen älter als 15 Jahre, im gesamten Stadtgebiet (Bundesstraßen, Siedlungsgebiete und Fußgängerzonen) getauscht. • Ein Drittel der Straßenbeleuchtung wird von 21.30 Uhr bis 5.30 Uhr auf 50 % abgesenkt • Einsparung: 36% (garantiert),1,2 Mio kWh/a (rd. 30%), 230.000 €/a, 60.000 Euro Wartungskosten • Investitionskosten: 2.100.000 Euro www.streetlight-epc.eu