No Slide Title - Marine Technology Society

advertisement
MTS Meeting
March 25, 2004
Agustin Ferrufino
Director, Engineering & Construction
Gulfstream Offshore
Gulfstream Overview
What is Gulfstream?
• 587-mile transmission gas pipeline
! 437 miles of 36” offshore pipeline
! 134 miles of onshore pipelines in FL
! 16 miles in AL & MS
!Compression & gas treatment in AL
• Placed into service May 2002
• Cost: $1.468 billion
• Design capacity: 1.1 Bcf/d
! Enough to create electricity for 4.5 million Florida homes
• Partnership between Williams & Duke Energy
Gulfstream Overview
Phase I
May 2002
Gulfstream Overview
Jackson County,
MS
Sta.
Sta. 015
015
Sta. 025
025
Mobile County, AL Sta.
Sta.
Sta. 045
045
MBPP
MBPP (600)
(600)
ExxonMobil
ExxonMobil (150)
(150)
Gulf
Gulf South
South (250)
(250)
Sta.
Sta. 050
050
Sta.
Sta. 035
035
Williams
Williams (300)
(300)
Sta.
Sta. 055
055
Destin
Destin (600)
(600)
Compressor
Compressor
Sta.
Sta. 410
410 –– Coden
Coden
Sta.
Sta. 005
005
DIGP
DIGP 20”
20”
(250)
(250)
Line
Line 060
060
Mississippi Sound
Gulf of Mexico
Line
Line 200
200
Gulfstream Overview
What made Gulfstream unique?
• First natural gas transmission pipeline built in the Gulf of Mexico
• Largest pipeline in the Gulf of Mexico
! 420 miles of 36" OD, high pressure rating of 2180 psig MAOP
• Designed with no compression offshore
• First pipeline on east side of the Gulf of Mexico
• Florida’s first natural gas transmission pipeline in 40 years
• Only offshore gas pipeline to make landfall in Florida
! Strict dry gas specs ensure minimal quantity of liquids delivered
• Other technological breakthroughs during construction and
commissioning
Challenges
Route Selection
Permitting
Schedule
Construction
Sunshine Skyway Bridge
• Protecting steel plates: 72" ID half circle x 3” thick
• Distance: Continuous 300 feet on each side of the bridge
• Cover: 3 feet below bottom
Route Selection
Route Selection
Schedule
Phase I Schedule
Filed
Filed for
for FERC
FERC
Certificate
Certificate
Oct.
Oct. 1999
1999
Received
Received
Started
Started
FERC
FERC
Offshore
Offshore
Approval
Approval Construction
Construction
Feb.
Feb. 2001
2001 July
July 2001
2001
In-Service
In-Service
May
May 2002
2002
Build
Build Additional
Additional
Facilities
Facilities
As
As Needed
Needed
Williams/Duke
Williams/Duke
Purchased
Purchased
The
The Project
Project
January
January 2001
2001
Florida
Florida
DEP
DEP Permit
Permit
March
March 2001
2001
Started
Started
Onshore
Onshore
Construction
Construction
Oct.
Oct. 2001
2001
Permits
Significant Milestones
• Final EIS received in January 2001
• FERC certificate issued in February 2001
• Florida DEP permits received in March 2001
• Implementation plan filed in April 2001
• Alabama COE permit received in May 2001
• MMS permit received in June 2001
Onshore Construction
Station 410
• Harmony Corporation lead construction contractor
• Dual Train Mole Sieve Gas Dehydration
• Dual Train Propane Refrigeration Hydrocarbon Dew Pt. Control
• Rolls-Royce RB211 turbines
• Dresser Rand D10RS comp.
• 2 Operating, 1 Spare
• 119,100 ISO HP Installed
Station 410
Coden, AL
Onshore Construction
Station 410
Onshore Construction
Onshore pipelines
•
134 miles of 16”, 24”, 30” & 36” pipelines
installed in 2001 & 2002.
•
4,000 feet installed per day
•
MAOP 1480 psig
•
13 meter stations
•
10 HDDs
Offshore Construction
Construction Facts
•
Started June 2001
•
Stolt Offshore prime offshore contractor
•
PCS lead design consultant
•
Offshore pipe
!
!
!
!
2180 psi design pressure
Mostly 36” X-70 pipe with 0.820
wall thickness
CWC designed for stability in 100year storm with specified densities
up to 205 pcf
Water depth up to 800’
Offshore Construction
Lay Barge 200
•
Used in water depths greater than 50’
•
Set a world record welding 274 double joints (548 single
jts) in 24 hours
•
5 fully automated welding stations, 1 AUT and 2 field
joint coating stations
•
550’ long (1,000’ w/stinger)
•
400 workers
•
Lays 3-4 miles per day
Offshore Construction
Lay Barge 200
Offshore Construction
Derrick Lay Barge 801
•
Used in intermediate water depths (20’ to 50’) in AL
and in FL State waters
•
Capable of laying 1 mile of pipe per day
•
7 work stations
•
1 AUT stall
•
351’ long
•
233 workers
Offshore Construction
Spud Barge
•
130 workers
•
Shallow water lay barge; Ms. Sound in Al. and Ms.
•
Capable of laying 4,000’ of pipe per day
•
7 work stations
•
1 AUT stall
•
500’ long
•
4 spuds
Offshore Construction
Other Vessels:
•
Saipem Castoro 10: jetting OCS and installations of
WSSTI
•
Horizon Pecos: jetting offshore Ala to WSSTI
•
Stolt DLB 801: installation of offshore mainline valve
•
Stolt DSV Hawk: installation of offshore mainline valve
•
Saipem Far Sovereign: plowing in
Florida
•
250 Jack-up: Pipeline flooding
support at ESSTI
•
145 Jack-up: Installation of mainline
valve in Tampa Bay, near fishing
pier
Offshore Design
36” ANSI 900 Wishbone Wye
• 36” X 36” X 36”, 75 yield material
• Weight: 46,821 lbs (23.4 Tons)
• Overall shipping dimensions: 20.25’ x 9.75’
• For future expansion options
Pipe Order
DSAW Pipe Order Summary
• Order placed -- 12/00
• First slab deliveries to Europe -- 1/01
• Pipe rolling started -- 2/01
• First shipment arrived in US -- 4/01
• 13 ships delivered pipe to AL/FL from
Europe
• 119 barge loads of pipe delivered to
AL/FL from Panama City, FL
Pipe Order
DSAW Pipe Order Summary
• Summary of pipe delivered in 2001
! Total footage = 2,905,700’
! Total est. pieces = 73,600
! Net tons = 449,900 tons
• Summary of pipe delivered 2002
! Total footage = 521,200’
! Total est pieces = 13,200
! Net tons = 37,800 tons
Pipe Coating
Summary
• Pipe coating suppliers included Dupont, Jotun, 3M, Lilly, BASF
• Powder supplied through 2003
! FBE – 2,354 tons
! Anti Slip – 270 tons
! Abrasion Resistant – 106 tons
• Raw materials required
! Iron ore – 250,000 MT
! Cement – 70,000 MT
! Reinforcing wire – 50 million sq. ft.
! Plastic – 24 million sq. ft.
Pipe Coating Plants
Theodore, AL
Pipe Coating Plants
Port Manatee, FL
Pipe Delivery
Load In vs CWC Production
36" x 0.820"
Load In vs. CWC Production
27,000
25,500
24,000
22,500
21,000
19,500
18,000
15,000
13,500
12,000
10,500
9,000
7,500
6,000
Pipe Load In
4,500
3,000
CWC Production
1,500
37255
37247
37239
37231
37223
37215
37207
37199
37191
37183
37175
37167
37159
37151
37143
37135
37127
37119
37111
37103
37095
37087
37079
37071
37063
37055
37047
37039
37031
37023
37015
37007
36999
0
36991
Pipes
16,500
Pipe Delivery
Load Out vs CWC Production
Gulfstream Project - CWC Performance
40,000
Actual Prod.
35,000
Actual Load out + projection
@450 jts/day
30,000
20,000
15,000
10,000
5,000
12/18/01
12/4/01
11/20/01
11/6/01
10/23/01
10/9/01
9/25/01
9/11/01
8/28/01
8/14/01
7/31/01
7/17/01
7/3/01
6/19/01
6/5/01
5/22/01
5/8/01
4/24/01
0
4/10/01
Pipes
25,000
05 Ju l09 - 01
Ju l13 - 01
Ju l17 - 01
Ju l21 - 01
Ju l25 - 01
Ju l29 - 01
Ju l0
02 Aug 1
-0 1
06 Au
10 - g-0 1
Aug
-0
14 Au 1
18 - g-0 1
Aug
-0 1
22 Aug
-0 1
26 Au
30 - g-0 1
Aug
-0
03 Se 1
07 - p-0 1
Se
11 - p-0 1
Sep
-0
15 Se 1
19 - p-0 1
Se
23 - p-0 1
Sep
-0 1
27 Sep
01 - -0 1
Oc
05 - t -0 1
Oct
09 - -0 1
Oc
13 - t -0 1
Oc
17 - t -0 1
Oct
21 - -0 1
Oc
25 - t -0 1
Oct
29 - -0 1
Oc
02 - t -0 1
Nov
-0 1
06 No
10 - v -0 1
No
14 - v -0 1
Nov
-0
18 No 1
22 - v -0 1
No
26 - v -0 1
Nov
-0
30 No 1
04 - v -0 1
De
08 - c -0 1
Dec
-0
12 Dec 1
-0 1
16 De
20 - c -0 1
Dec
-0 1
Daily Production (SJ)
600
550
500
400
350
250
100
30000
300
25000
TS 'BARRY'
WSSTIA
28-29 July-01
TS 'GABRIELLE'
PINNACLES
18-20 Aug-01
MLV 2D
9-Sep-01
Daily Production
HR 'MICHELLE'
MLV 2E
19-Oct-01
Cumulative Production
20000
200
150
15000
MLV 2F
21-Nov-01
50
0
Cumulative Production (SJ)
Laying Pipeline
LB-200 Daily Production
GULFSTREAM PROJECT - LB200 Daily Production
As Built Up to December 20th
50000
48,802 SJ
45000
450
40000
35000
10000
5000
0
20-Dec-01
Lay Dow n
Com plete
Commissioning
Preparing for service
• Flooding the pipelines for hydrotest
• Hydrotesting the segments
• Dewatering the supply & mainline
• Drying the mainline
• Purging & commissioning the
mainline
Largest Dewatering Spread
Valve Diagrammatic
Environmental
Offshore Mitigation
Developed mitigation plan in conjunction with the Florida
Department of Environmental Protection, the Florida Marine
Research Institute, the U.S. Army Corps of Engineers, the
Hillsborough County Environmental Protection Commission, the
Minerals Management Service, and the National Marine Fisheries
Service.
Federal Waters
• Added new limestone hard bottom
• 49.4 acres of mitigation
• 153 man-made reef modules
• 130,000 tons of limestone
• Monitoring up to 10 years
Environmental
Offshore Mitigation
State Waters
•
19.74 acres of mitigation
•
Accomplished using 100 20X24
shallow water reef habitat modules
•
Required 5,000 tons of Florida
limestone
•
Required that divers physically
remove and transplant soft and
hard coral from the proposed pipe
lay area
Environmental
Environmental Mitigation
Onshore
• Spoil Island (65 acres)
!Created bird sanctuary w/ Audubon & Port
• Harbor Key (100 acres)
!Exotic plant removal
• Lake Wales Site (398 acres)
!Created and enhanced wetlands & uplands
!Planted over 117,000 trees
• Manatee Site (181 acres)
!Exotics removal, creating wetlands
!Planted 3,500 trees & 500,000 plants
What’s Next?
Phase II Extension
In May 2003 Gulfstream announced an agreement with Florida Power &
Light to provide 350 MMcf/d for its Martin & Manatee plant expansions.
• 103 miles
• 30-inch diameter pipe
• 1 meter station
• Construction begin Spring 2004
• In service Winter 2004
2004 Facilities
Download