DAVID J. KVALTINE, PE GAINESVILLE REGIONAL UTILITIES Gainesville, Florida LIGHTNING PROTECTION - A STROKE OF LUCK, THEORY AND APPLICATION 2005 APPA ENGINEERING AND TECHNICAL CONFERENCE APRIL 18, 2005 Memphis, Tennessee GRU Service Territory Number of Electric Customers Service Area Transmission Underground Distribution Overhead Distribution Distribution Substations 86,000 127 square miles 597 circuit miles 1340 circuit miles (55%) 743 circuit miles (45%) 9 (138 kV/12.47 kV) LIGHTNING PERFORMANCE OF DISTRIBUTION LINES The Utility must determine the level of performance they would like to achieve Overhead line performance is dependent on the following • Line insulation flashover due to indirect strikes • Line insulation flashovers due to direct strikes • Line insulation flashovers due to equipment failures FLASHOVERS DUE TO INDIRECT STRIKES Generally designing a structure with a minimum BIL of 300 kV will minimize line flashovers due to nearby lightning strikes. FLASHOVERS DUE TO INDIRECT STRIKES BIL Calculations for Wood Poles: BIL = CFO(0.9) Insulator BIL= 155(.9) = 139.5 kV Total Insulator BIL = 2 x (139.5) = 279 kV Wood does add some additional insulating value depending on the length of the wood. 100 kV/foot 90 kV/foot 75 kV/foot 10-30 kV/foot 10" 20" 10" 20" 10" CFOair 200 kV/foot CFOair = 200 kV x 2.5 feet = 500 kV 66" TYP. 96" M AX. FLASHOVERS DUE TO INDIRECT STRIKES BIL Calculations for Concrete Poles: 10" BIL = CFO(0.9) 20" Insulator BIL = 203(.9) = 183 kV Total Insulator BIL = (183) kV 10" Concrete does not add any additional insulating value. The insulators provide all the insulation 20" CFOair 200 kV/foot 10" CFOair = 200 kV x 2.5 feet = 500 kV 66" TYP. 96" MAX. FLASHOVERS DUE TO DIRECT STRIKES • Determine flashovers per mile of line in open country • Estimate shielding of line from other structures and trees • Calculate the number of flashovers per mile of line due to direct strikes FLASHOVERS DUE TO DIRECT STRIKES LIGHTNING STRIKES TO AN OVERHEAD LINE IN OPEN COUNTRY Noc = GFD x 0.0085 x H 0.6 x L Noc - Number of strikes to a line without any shielding GFD - Ground Flash Density - strikes/sq. mile/year H - Height above ground in feet L - Length of the distribution line in miles Ground Flash Density (GFD) Contour Map for Florida Gainesville Ground Flash Density (GFD) in the area shown ranges from 26 -36 strikes/sq. mile/year with an average of 31 strikes/sq mile/year LIGHTNING STRIKES TO OVERHEAD LINE IN OPEN COUNTRY Calculation: GFD = 36 strikes/sq mile/year L = 1 mile H - top phase above ground = 47 feet Noc = 36 x 0.0085 x (47) 0.6 x 1 Noc = 3 strikes/mile/year Typical Shielding Factors Sf -Shielding factor, the number of lightning strikes that are intercepted by other objects other than the distribution line. Nsh - Number of strikes to the shielded line Nsh = Noc x (1-Sf) For shielding factor of: Sf = 0.7 Nsh = 3 x (1-.0.7) Nsh = 0.9 or approximately 1 strike/mile of line/year Sf = 0.4 Nsh = 3 x (1- 0.4) Nsh = 1.8 or approximately 2 strikes/mile of line/year MUST CONSIDER SHIELDING ON BOTH SIDES OF THE LINE EVEN TREES, 1/2 THE HEIGHT OF THE LINE WILL PROVIDE SOME SHIELDING Shielding by trees Sf = 1.0 Shielding by trees Sf = 0.7 Shielding by trees Sf = 0.4 METHODS OF LIGHTNING PROTECTION SHIELDING The process where a lightning flash terminates on an overhead wire above the phase conductors and the lightning current is channeled to ground through a ground wire. The lightning current does not flow through the phase conductors. Two Methods of Shielding include: •Overhead static •Overhead neutral METHODS OF LIGHTNING PROTECTION SHIELDING - OVERHEAD STATIC •30 degree shielding angle above phase conductors •BACKFLASH V = Ri + Ldi/dt •Typical L value is 0.4 uH/foot •Rise times can be 1-10 usec. •Maximum recommended ground resistance is 10 ohms •Recommended structure BIL 500-600 kV •Overhead shields can reduce flashovers from induced voltages SHEILDING - OVERHEAD STATIC METHODS OF LIGHTNING PROTECTION SHIELDING - OVERHEAD NEUTRAL •Same basic issues as OH static •Does not provide any additional reduction from nearby strikes •Shorter poles may be able to be used SHIELDING--OVERHEAD NEUTRAL SHIELDING WILL WORK ON DISTRIBUTION LINES IF PROPERLY DESIGNED METHODS OF LIGHTNING PROTECTION SHUNTING The process where a lightning flash is allowed to terminate on a phase conductor and the surge current is shunted to ground by either an insulation flashover or through a lightning arrester. Would prefer to shunt the lightning current through an arrester. GRU ARRESTER APPLICATION GUIDELINES Placement of Arresters for Overhead Line Protection Framing Configuration Approximate Distance From Deadend Min Max Maximum Number Of Spans Approximate Distance Between Arresters Min Max Maximum Number Of Spans Wood Poles Triangular and vertical without static 200' 300' 1 1150' 1350' 6 Concrete Poles Horizontal, triangular and vertical without static 200' 300' 1 400' 3 All Equipment All Switches All Deadends 600' GRU ARRESTER APPLICATION GUIDELINES Transformer Lead Lengths Try to keep lead lengths 3 feet or less GRU ARRESTER APPLICATION GUIDELINES Placement of Arresters for UG Line Protection • Open Loops • Radial Cable Terminations • Terminal Poles GRU ARRESTER APPLICATION GUIDELINES Single Phase Open Loop Transformer Three Phase Open Loop Transformer GRU ARRESTER APPLICATION GUIDELINES Single Phase Radial Transformer Radial Configuration Radial Type Three Phase Transformer Radial Configuration Loop Type Three Phase Transformer GRU ARRESTER APPLICATION GUIDELINES Termination Pole Lead Lengths • Typical designs use 1.6 kV per foot but can be as high as 6-10 kV/ft • Try to keep lead lengths 3 feet or less Incorrect Correct IEEE UG APPLICATION GUIDELINES • Use termination, open point and mid point arresters (mid point should not be closer than 150 - 350 feet) • Should consider using rise times of 1 - 2 usec or 3 - 8 kV/ft • Minimize arrester lead lengths at terminal poles SUMMARY Determine Level of Protection Keeping Structure BIL at 300 kV will protect lines from Indirect Strikes Two Methods of Protection from Direct Strikes • Shielding • Shunting Typically distribution lines use lightning arrester for protection GRU ARRESTER APPLICATION GUIDELINES Introduction The protection of distribution circuits from lightning induced interruptions is dependent on a number of factors which must be considered in the design and construction of any overhead line. An overhead line should have due consideration for basic insulation levels, line configuration, ground resistance and arrester application. In this guideline an attempt has been made to outline a consistent set of rules for the application of arresters on the distribution system. These rules are primarily applicable to overhead distribution lines, but certain special consideration has been given to arrester protection of cable and equipment on underground systems. GRU ARRESTER APPLICATION GUIDELINES cont. I. Basic Considerations A. Standard Arrester Types The standard arrester for use on this system is the metal oxide varister (MOV) design. Three types of MOV arresters are available for use in specific applications: 1) Stock # 58930-6, standard distribution arrester for general overhead line applications. 2) Stock # 58935-7, riser type arrester for underground terminations from the overhead system. 3) Stock # 78266-1, elbow arrester for use in elbow connected pad mounted equipment. 4) Stock # 62245-1, parking stand arrester. GRU ARRESTER APPLICATION GUIDELINES cont. B. Proper Lead Lengths/Placement 1) Regardless of the type of arrester installed one basic principle should always be observed in order that the full protective capability of the arrester is utilized. The arrester line lead and ground lead should be as short as possible. Often this can be accomplished by carrying the line and ground connections to the arrester terminals first, and then on to the equipment terminals of the protected equipment. (See Fig. 1a,b) 2) Arresters should be positioned such that a blown ground lead isolator will not effect other energized equipment. 3) Arresters should be installed on source side of cutouts to avoid possible fuse operation on current inrush. Incorrect Fig. 1a Correct Fig. 1b GRU ARRESTER APPLICATION GUIDELINES cont. II. Required Applications (using standard distribution arrester) A. Overhead Oil-filled Equipment - The following overhead mounted equipment shall have the standard distribution arrester (stock # 58930-6) applied: 1) 2) 3) 4) 5) B. Overhead Switches - The following overhead equipment shall have the standard distribution arrester (stock # 58930-6) applied on both sides of a switch on the same pole which can be source fed from both directions: 1) 2) 3) C. Transformers. Reclosers (apply @ both sides). Sectionalizers (source side only when used at underground termination). Regulators (apply @ both sides). Capacitors. All normally open hook stick operated switches. All group operated switches. Normally open in-line switches (may be installed on adjacent poles). Other Overhead Locations - The following overhead equipment shall have the standard distribution arrester (stock no. 58930-6) applied: 1) 2) 3) All deadends (not including double deadends that are jumpered across or corner poles). Distribution lines built under transmission lines shall have arresters applied in same manner as any other distribution line. Arresters shall be applied for line protection in accordance with the following table: GRU ARRESTER APPLICATION GUIDELINES cont. Placement of Arresters for Overhead Line Protection Framing Configuration Approximate Distance From Deadend Min Max Maximum Number Of Spans Approximate Distance Between Arresters Min Max Maximum Number Of Spans Wood Poles Horizontal & vertical with static Horizontal without static Triangular and vertical without static 400‘ 200' 200' 600' 300' 300' 2 1 1 2400' 2600' 400' 600' 1150' 1350' 12 3 6 Concrete Poles Horizontal & vertical with static Horizontal, triangular and vertical without static 200' 200' 300' 300' 1 1 1150' 1350' 400' 600' 6 3 NOTE: 1) Arresters applied on all three phases for equipment protection may also be considered as line protection. 2) Distances for spacing of arresters are approximate, and are intended as a guideline to good practice. Actual spacing will depend on actual span lengths. GRU ARRESTER APPLICATION GUIDELINES cont. III. Required Applications (using riser type arrester) A. Overhead to Underground Terminations - The following terminations shall have the riser pole arrester (stock # 58935-7) applied: 1) All modular type terminations and porcelain terminations with or without disconnect switches. 2) All switchgear. IV. Required Applications (using elbow type arrester) A. Radial and Open Loop Points - The following terminations shall have the elbow type arrester (stock # 78266-1) applied: (See Fig. 2a, 2b) 1) Single phase pad transformers fed radially. 2) Single phase pad transformers fed in a loop, applied at the open loop point on both cables. 3) Any other elbow connected equipment with an unused bushing which is fed radially or which is located at an open loop point. B. Radial three phase transformer configurations. 1) Three phase radial type transformers fed radially. (See Fig. 3a) GRU ARRESTER APPLICATION GUIDELINES cont. B. Radial three phase transformer configurations. 1) Three phase radial type transformers fed radially. (See Fig. 3a) Radial Fig. 2a Radial Configuration Radial Type Transformer Fig. 3a Open Loop GRU ARRESTER APPLICATION GUIDELINES cont. 2) Three phase loop type transformers fed in a loop, applied at the open loop point on both cables. (See Fig. 3b) Line B Only Line A Only Feed Thru 3) Any other elbow connected equipment with an unused bushing which is fed radially or which is located at an open loop point. (See Fig. 3c) Line A&B Radial Configuration Loop Type Transformer NOTE: Three phase loop-configuration transformers are equipped with a four-way switch which permits feed-through (with transformer de-energized), line A only, line B only and line A + B operation. Switch is normally in the line A + B position. Loop Configuration Loop Type Transformer REFERENCES IEEE Std. C62.11-1999, IEEE Standard for Metal Oxide Surge Arresters for AC Power Circuits >1000 volts IEEE Std C62.22-1997, IEEE Guide for the Application of Metal Oxide Surge Arresters for Alternating Current Systems IEEE Std 1299/C62.22.1-1996, IEEE Guide for the Connection of Surge Arresters to Protect Insulated Shielded Electric Power Cable Systems IEEE Std 998-1996, IEEE Guide for Direct Lightning Stroke Shielding of Substations EPRI Report EL-6782 "Characteristics of Lightning Surges on Distribution Line", Project RP2542-1, First Phase, May 1990 EPRI Report TR-100218, "Characteristics of Lightning Surges on Distribution Lines", Project RP2542-1, Final Report, December 1991. "Lightning Protection Manual for Rural Electric Systems" Rural Electric Research Project 92-12, National Rural Electric Cooperative Association, 1993 "Electrical Distribution-System Protection", Cooper Power Systems, Third Edition "Insulation Coordination for Power Systems", Andrew R. Hileman, Marcel-Dekker Inc. 1999 Parrish, D.E.; "Lightning-Caused Distribution Circuit Breaker Operations"; Power Delivery, IEEE Transactions on, Vol 6, Issue 4, October 1991, Pages 1395-1401 Parrish, D.E.; "Lightning-Caused Distribution Transformer Outages on a Florida Distribution System", Power Delivery, IEEE Transactions on, Vol 6, Issue 2, April 1991, Pages 880-887 Parrish, D.E.; Kvaltine, D.J.; "Lightning Faults on Distribution Lines", Power Delivery, IEEE Transactions on, Vol 4, Issue 4, October 1989, Pages 2179-2186 REFERENCES cont. Barker, P.P; Mancao, R.T.; Parrish, D.E.; Kvaltine, D.J.; "Characteristics of Lightning Surges Measured at Metal Oxide Distribution Arresters" Power Delivery, IEEE Transactions on, Vol 8, Issue 1, January 1993, Pages 301-310 Jacob, P.B.; Grzybowski, S.; Ross, E.R.; "An Estimation of Lightning Insulation Level of Overhead Distribution Lines"; Power Delivery, IEEE Transactions on, Vol 6, Issue 1, January 1991, Pages 384-390 Ross, E.R.; Grzybowski, S.; "Application of the Extended CFO Added Method to Overhead Distribution Configurations"; Delivery, IEEE Transactions on, Vol 6, Issue 4, October 1991, Pages 1573-1578 "Working Group Report: Calculating the Lightning Performance of Distribution Lines", Power Delivery, IEEE Transactions on, Volume 5, Issue 3, July 1990, Pages 1408-1417