DESIGN OF REAL-TIME SYNCHRONIZATION CONTROLLER IN ELECTRIC SHIP POWER SYSTEMS Technical Report Submitted to: The Office of Naval Research Contract Number: N0014-08-1-0080 Submitted by: Enrico Santi, Huaxi Zhang, Yucheng Zhang December 2013 Approved for Public Release – Distribution Unlimited Any opinions, findings, conclusions or recommendations expressed in this publication are those of the author(s) and do not necessarily reflect the views of the Office of Naval Research. MISSION STATEMENT The Electric Ship Research and Development Consortium brings together in a single entity the combined programs and resources of leading electric power research institutions to advance near- to mid-term electric ship concepts. The consortium is supported through a grant from the United States Office of Naval Research. 2000 Levy Avenue, Suite 140 | Tallahassee, FL 32310 | www.esrdc.com TABLEOFCONTENTS Executive Summary ........................................................................................................................ 2 1 Motivation ............................................................................................................................... 2 2 Control Scheme of Real-Time Synchronization Controller .................................................... 4 3 2.1 Frequency Control and Phase Control ............................................................................. 4 2.2 Design of Low-Pass Filters .............................................................................................. 7 Validation of Real-Time Synchronization Controller ............................................................. 8 3.1 Simulation Test of System Reconfiguration during Normal Operation ......................... 10 3.2 Simulation Test of System Reconfiguration under Fault Condition .............................. 13 4 Conclusion ............................................................................................................................. 15 5 Acknowledgements ............................................................................................................... 16 6 References ............................................................................................................................. 16 LISTOFFIGURES Figure 1 Notional Baseline MVAC Ship Power System with a Three-Phase Bolted Fault ........... 3 Figure 2 Large Phase Difference between Subsystem Voltages Leading to Transient High-Peak Current through CBs during System Reconfiguration Process....................................................... 3 Figure 3 4% Droop Function of Speed Regulator without RTSC (top) and with RTSC (bottom). 5 Figure 4 Structure of the RTSC Consists of Frequency Control and Phase Control ...................... 6 Figure 5 Voltage Signal Measured at the Port Bus of MVAC ESPS ............................................. 8 Figure 6 FFT Analysis of the Voltage Signal before Filtering ....................................................... 8 Figure 7 System start-up under Normal Conditions with RTSC Activated.................................. 10 Figure 8 System Reconfiguration Process during Normal Operation .......................................... 12 Figure 9 System Reconfiguration Process when a Three-Phase Bolted Fault Occurs ................. 15 i Executive Summary In medium-voltage AC (MVAC) and high-frequency AC (HFAC) power distribution systems for an Electric Ship, system reconfiguration may cause previously disconnected parts of the electrical distribution system to be interconnected. This may lead to large transients, if the overall system is not properly synchronized. This report proposes a Real-Time Synchronization Controller (RTSC), which solves this problem by keeping all parts of the electrical distribution system phase-synchronized at all times. The RTSC augments the conventional frequency droop control for generators. Simulation results demonstrate the effectiveness of the approach in reducing reconfiguration transients. 1 MOTIVATION An Electric Ship Power System (ESPS) is a micro-grid which is powered by multiple synchronous generators. These generators are required to operate in either standalone or interconnected modes depending on generator statuses, load requirements and other system contingencies, such as faults. Demands for system reconfiguration may occur anytime, which means that it must be possible to connect any generator to the grid reliably and successfully at any time. Additionally, system reconfiguration should be smooth enough so that normal operation of system loads is not interrupted. The ESPS is a megawatt level micro-grid which could be partitioned in different ways according to different requirements such as load demands, reliability and efficiency. Before system reconfiguration, the ESPS might be partitioned into two or more subsystems. Each subsystem might be running at a different frequency depending on its loading condition. Even assuming that two subsystems are operating at the same frequency, the voltage at each subsystem might not be in phase with each other. Directly connecting these unsynchronized generators/subsystems would lead to unacceptable transient oscillation in ESPS and to other undesirable side effects. The effects of synchronization or lack thereof on transient stability of Medium Voltage AC (MVAC) ESPS is now illustrated through a simulation, which shows the detrimental effects that occur when the generators/subsystems are not synchronized before they are connected to a larger network. Figure 1 shows the structure of notional MVAC ESPS [1, 2]. In this testing scenario, a three-phase bolted fault is set to occur in the middle of Port Bus at t = 1 s. Before the fault occurs, the system is operating in split mode: Zone 1, Radar and Port Bus Propulsion Motor are fed from Port Bus which is powered by Main Turbine-Generator 2 (MTG2) and Auxiliary Turbine-Generator 2 (ATG2); Zones 2, 3, 4, High Power Pulsed Load and Starboard Bus Propulsion Motor are fed from Starboard Bus which is powered by MTG1 and ATG1 generators. Each MTG or ATG is composed of one gas turbine and one synchronous generator [1]. After the fault occurs, the circuit breakers (CBs) on both sides of the fault location are tripped off in order to isolate the fault and the CBs on the Bow and Stern sides are required to close in order to ensure that adequate power be delivered to each load in the system. For example, after fault isolation, auxiliary generator ATG2 would not have enough power capability to supply Port Bus Propulsion Motor. Figure 2 (a) shows the large transient high-peak current through CBs on Stern Bus Tie – note that the transient current is ten times the steady-state current. This current is due to the large phase difference between the voltages at Starboard Bus and Port Bus, as shown in Figure 2 (b). The Port Bus voltage is measured at the location of the three-phase bolted fault. The adverse impact of this transient current includes: high machine winding stresses, large rotor iron currents, pulsating torques, and mechanical resonances that pose risk of potential damage to 2 machines. Additionally, the large transient currents may trip off CBs and cause the reconfiguration process to fail. Figure 1 Notional Baseline MVAC Ship Power System with a Three‐Phase Bolted Fault 40 20 0 -20 -40 0 1 2 3 4 5 6 Time (s) 7 8 9 10 11 (a) Large Transient Current (in kA) through CBs on Stern Bus (b) 180⁰ Phase Difference between Voltages at Port Bus and Starboard Bus Figure 2 Large Phase Difference between Subsystem Voltages Leading to Transient High‐Peak Current through CBs during System Reconfiguration Process 3 From the example described above, it can be learned that phase difference between bus voltages poses hazard to the successful and reliable system reconfiguration. Frequency difference between generators in different subsystems due to loading condition also adversely affects the system reconfiguration process. When subsystems are connected with frequency difference present, generators in one subsystem will oscillate against those in other subsystems, which results in longer time for the whole ESPS to reach steady state. If the frequency difference is too large, it may even cause transient stability issues which may eventually lead to system reconfiguration failure. Therefore, generators in each subsystem must be synchronized both in frequency and phase before they are connected into a single network. Before connecting subsystems, the differences in frequency and phase should be minimized. When these synchronization criteria are satisfied, subsystems can be successfully connected to a large network by closing CBs. The Real-Time Synchronization Controller (RTSC) described in this report is able to enforce synchronization of generators at any time when the ESPS is in service. It is highly critical to the success of system reconfiguration. The requirement of flexibility, stability and reliability for the reconfiguration process can be addressed as well by implementing the RTSC. Note that this controller is designed based on MVAC ESPS and has been tested on the Notional Baseline MVAC ESPS model. However, with its parameters properly tuned, the RTSC could be implemented in the High Frequency AC (HFAC) system as well. 2 CONTROL SCHEME OF REAL‐TIME SYNCHRONIZATION CONTROLLER The Real-Time Synchronization Controller (RTSC) is designed to be a part of the supervisory control for generators. Its goal is to maintain all generators/subsystems in the ESPS synchronized at all times during operation, even when there is no physical connection or power flow between them, so that they can be successfully connected together at any time. The RTSC is based on droop control in frequency and consists of two control loops: 1) frequency control (FC); and 2) phase control (PC). Also, to prevent jitter caused by harmonics in voltage measurement and to avoid interference between frequency control and phase control, low-pass filters are utilized in the RTSC. 2.1 Frequency Control and Phase Control The function of frequency control is to force all generators to operate at rated system frequency (e.g. 60 Hz in MVAC ESPS and 240 Hz in High Frequency AC ESPS). FC is implemented by adding a variable offset dynamically to the speed regulator reference in each generator. In order for generators to operate reliably in parallel and share generated power in proportion to their respective power rating, speed regulators of generators are set in droop mode, so that the generator frequency has a constant proportional relationship to the turbine’s output mechanical power, as shown in Figure 3 (top). The droop setting is 4% in MVAC ESPS. As a result of droop control, the generator frequency may drop up to 4% below nominal as a function of load. To remedy this, the RTSC frequency control introduces an offset ∆ in the droop function, so that in steady state the per-unit frequency is exactly one, as shown in Figure 3 (bottom). 4 Figure 3 4% Droop Function of Speed Regulator without RTSC (top) and with RTSC (bottom) The offset of frequency control for the ith Generator is calculated by the RTSC control as in Eq. 1. ∆ ∗∑ ∑ (1) _ where, ∆ is the offset of frequency control for the ith Generator, is the droop setting of the speed regulator in the ith Generator (e.g., 4% as in Fig. 3), _ is the rated active power of the jth Generator, is the instantaneous total output power of the jth Turbine Engine. represents the relationship between the Generators i and j: 1 if the two 0 if the two generators are located in generators are located in the same subsystem; different subsystems; is the total number of generators in the ESPS. The ratio in the right hand side of Eq. 1 represents the percentage loading of the generators in the subsystem containing Generator with respect to their combined rated power. When implementing the RTSC in an ESPS, one subsystem is chosen as the reference subsystem and the other subsystems are set as the target subsystems. Note that different subsystems are not connected to each other, i.e., they are islanded. The criterion to choose the reference subsystem is that it should have the largest power rating among all subsystems. As the control is implemented in software, the reference subsystem can be chosen dynamically according to system operating state. The complete structure of the RTSC is depicted in Figure 4. 5 Figure 4 Structure of the RTSC Consists of Frequency Control and Phase Control In the figure only two subsystems are shown for simplicity: a reference subsystem, consisting of Generators 1 – m, and a target subsystem, consisting of Generators m+1 – n. Additional subsystems would be shown as separate target subsystems. Both the reference and the target subsystem have frequency control, but only the target subsystem has phase control. The goal of frequency control is to ensure that all subsystems operate at the same frequency, whereas the goal of phase control is to keep voltages of the target subsystem(s) and the reference subsystem in phase. Frequency control calculates for each generator the offset of frequency control ∆ as a function of real power generated using Eq. 1. In the phase control block, three-phase voltage measurements are taken at the generator terminals in the target subsystem and the reference subsystem. The harmonics resulting from non-linear load current are eliminated by Low-Pass Filter I (LPF-I). In the “Phase Calculation” blocks in Figure 4, using Eq. (2) the three-phase voltage measurements are transformed to the static axis frame and , is calculated. the phase, , of the space vector 6 √ (2) √ 2 , where , , are the three-phase measured voltages; is the voltage portion on static axis; is the voltage portion on static axis; is the phase of space vector , . The phase difference, ∆ , between the target subsystem and the reference subsystem, calculated as ∆ , goes into the “Signal Processing” block and its value is constrained from [-2π, 2π] to [-π, π] using phase wrap. The offset of phase control is produced by the proportional (P) “Gain” controller in Figure 4. According to synchronization criterion, the slip frequency between two subsystems must be lower than 0.1 Hz for 60 Hz power system. So the gain of P controller, , in the phase control can be chosen according to Eq. (3). . ∗ (3) As a result of the RTSC control of Figure 4, in steady state all subsystems operate at the nominal frequency (p.u. frequency of one) and the voltages of all target subsystems are in phase with the reference subsystem. 2.2 Design of Low‐Pass Filters There are two low-pass filters (LPF_I and LPF_II) in the RTSC, as shown in Figure 4. They strongly influence the performance of the RTSC and must be designed carefully. Both filters are implemented as first-order low-pass filters in the RTSC. Their cut-off frequency is determined by the load condition and other parameters such as the inertia constants of generators and the time delay of turbine engines. Design of LPF_I: Due to the nonlinear loads like the diode-rectifier in ESPS, the measured voltage contains 2nd and high-order harmonic components. To help design LPF_I, Fourier analysis is performed to determine the filter cut-off frequency. Figure 5 shows the voltage signal measured at the Port Bus of the MVAC system without RTSC, and its FastFourier Transform (FFT) is shown in Figure 6. As these figures show, in addition to the 60 Hz fundamental component, some high-order harmonics are present. Based on the result of FFT, the cut-off frequency of LPF_I is set to 100 Hz for the RTSC in the MVAC ESPS. 7 Voltage (V) 5000 0 -5000 21 21.05 Time (s) 21.1 Figure 5 Voltage Signal Measured at the Port Bus of MVAC ESPS Figure 6 FFT Analysis of the Voltage Signal before Filtering Design of LPF_II: The measured instantaneous power signal at the input of the frequency control block relates to the droop setting, the delay of speed regulator, inertia constant of generator, and loading condition. To avoid interference between the frequency control and the phase control, the cut-off frequency of LPF_II can be determined by Eq. (4). (4) where is the cutoff frequency of LPF-II, is the inertia constant of generator, is the delay in speed regulator and turbine engine combined. The inertia constants of the generators in MVAC ESPS are 4 s and 3.5 s for main and auxiliary generators, respectively. Since the delay is less than 1 s, the cut-off frequency is chosen as 0.2 Hz. 3 VALIDATION OF REAL‐TIME SYNCHRONIZATION CONTROLLER The effectiveness of the proposed RTSC is verified via simulation tests based on the waveform-level notional baseline MVAC ESPS [1]. The MVAC ESPS has two subsystems, the Port Bus and Starboard Bus as shown in Figure 1. The details of the MVAC ESPS including each subsystem structure and parameters are documented in [1]. The only modification with respect to the MVAC ESPS described in [1] is that various loads that are connected to each bus are replaced with a lumped load for each bus. The lumped load on Port Bus is 30 MW, 15 MVar and the one on Starboard Bus is 18 MW, 9 MVar. The cut-off frequency for LPF-I and LPF-II are 100 Hz and 0.2 Hz, respectively. 8 When the system operates in steady state, the two subsystems operate in standalone mode. When certain system contingencies occur, such as a step change in power demand or a fault, system reconfiguration will be needed. The CBs at Stern and Bow sides in Figure 1 will close and the two subsystems will combine to form a ring bus. Power generation from four generators will be shared via the ring bus and the contribution from each generator is proportional to its power rating. To demonstrate the necessity of the RTSC in such system contingencies, two scenarios are tested: a) system reconfiguration during normal operation; and b) system reconfiguration under fault condition. In both testing scenarios, system transient performance will be compared for two cases: with and without the RTSC activated. The system start-up process is now described. Figure 7 shows the frequency profile and the phase difference between voltages at Port Bus and Starboard Bus for the case with the RTSC activated (frequency control activated at 150 s and phase control activated at 180 s). The ESPS is operating in split mode and each subsystem reaches steady state before 150 s. Since frequency control is not active yet, the droop characteristic of Figure 3 (top) causes the frequencies of the two buses to be less than 1.0 p.u. and different from each other, due to different loading conditions. After the frequency control is activated at 150 s, the frequency of two subsystems return back to 1.0 p.u. in approximately 10 s and the phase difference between them takes a nonzero value that does not change any longer after that. After the phase control is activated at 180 s, the phase difference between subsystems becomes zero in about 10 s with minor oscillations in the frequency profile. (a) Frequency of Port and Starboard Subsystems in Per Unit 9 4 3 2 1 0 -1 -2 -3 -4 140 150 160 170 180 190 200 210 220 Time (s) (b) Phase Difference between Port and Starboard Subsystems in Radian Figure 7 System start‐up under Normal Conditions with RTSC Activated 3.1 Simulation Test of System Reconfiguration during Normal Operation During normal operation, responding to the requirements of energy efficiency and generation power redundancy, the Port and Starboard Buses may need to be connected together to form a ring bus, so that the total load can be shared among all four generators. The transient dynamics during the reconfiguration process (frequency and voltage waveforms) are shown in Figure 8 for two cases: RTSC disabled and RTSC enabled. The system reconfiguration occurs at 219.6 s. Figure 8 (a) ~ (c) depict the reconfiguration process without RTSC activated. At 219.6 s, the phase difference between the two subsystems is 180°, which is the worst case for connecting two subsystems. After the CBs on both Stern and Bow sides are closed, the current through CBs reaches a peak value of 55.9 kA with transient ac rms component of 21 kA. The starboard bus voltage drops to 240 V peak (96% deviation from rated voltage of 4160 V) and it takes 2.0 s to recover. The maximum transient deviation in frequency reaches 0.024 p.u. (1.46 Hz) and it takes about 2.5 s for the four generators to reach a steady state condition in which they operate synchronously. Due to the large transient current through the CBs, the CBs might trip off, which would result in reconfiguration failure. Figure 8 (d) ~ (f) show the reconfiguration process with RTSC activated prior to it (as shown in Figure 7). Neither large transient current through CBs nor significant voltage sag appears. The maximum transient deviation in frequency is only 0.006 Hz. The reconfiguration is almost transient-free. The current through the CBs on the Stern Bus increases steadily until the reconfigured system reaches steady state in 4.0 s. Thus, the transient stability of reconfiguration process during normal operation is greatly improved by implementing the RTSC. 10 phase a phase b phase c 60 40 20 0 -20 -40 -60 219.4 219.6 219.8 220 220.2 220.4 220.6 Time (s) (a) Three‐Phase Currents (in kA) through CBs on Stern Side without RTSC Activated 8000 6000 4000 2000 0 -2000 -4000 -6000 -8000 218 219 220 221 222 223 224 225 Time (s) (b) Voltage (in Volt) on Starboard Bus without RTSC Activated 1.02 MTG1 MTG2 ATG1 ATG2 1.01 1 0.99 0.98 0.97 0.96 0.95 0.94 0.93 0.92 218 219 220 221 222 223 224 225 226 227 Time (s) (c) Frequency (in Per Unit) of Generators without RTSC Activated 11 228 1 phase a phase b phase c 0.8 0.6 0.4 0.2 0 -0.2 -0.4 -0.6 -0.8 -1 219.4 219.6 219.8 220 220.2 220.4 220.6 Time (s) (d) Three‐Phase Currents (in kA) through CBs on Stern Side with RTSC Activated 8000 6000 4000 2000 0 -2000 -4000 -6000 -8000 218 219 220 221 222 223 224 225 Time (s) (e) Voltage (in Volt) on Starboard Bus with RTSC Activated 1.0005 MTG1 MTG2 ATG1 ATG2 1.0004 1.0003 1.0002 1.0001 1 0.9999 0.9998 0.9997 0.9996 0.9995 218 219 220 221 222 223 224 225 226 227 Time (s) (f) Frequency (in Per Unit) of Generators with RTSC Activated Figure 8 System Reconfiguration Process during Normal Operation 12 228 3.2 Simulation Test of System Reconfiguration under Fault Condition In this section, the system reconfiguration process following a three-phase bolted fault is tested. At 219.6 s, a three-phase bolted fault occurs in the middle of Port Bus, which is the most severe fault to this system, as shown in Figure 1. Considering a typical fault clearance time of 3.5 cycles (equivalent to 0.058 s, 0.5 cycle of fault detection plus 3 cycles of fault clearance by tripping off CBs), the fault is cleared at 219.658 s and the CBs at Stern and Bow sides close instantaneously. From Figure 9 (a) – (c) it is found that without RTSC activated the current reaches a peak value of 60.1 kA with transient ac rms component of 23.4 kA. The voltage on Starboard Bus drops to 127 V peak (97.8% deviation from rated voltage) and it takes 2.0 s to recover. The maximum transient deviation in frequency reaches 0.023 p.u. (equivalent to 1.39 Hz) and it takes about 2.5 s for the four generators to reach a steady state condition in which they operate synchronously. The results are similar to those from test of reconfiguration during normal operation without RTSC activated. With RTSC activated, the transient responses are improved dramatically, as shown in Figure 9 (d) – (f). The transient current is reduced to a peak value of 13 kA with transient ac rms component of 3.8 kA. The voltage drops to 4968 V peak (15.5% deviation from rated voltage) and the system recovers in as short as 0.4 s. The maximum transient deviation in frequency is 0.0065 p.u. (equivalent to 0.39 Hz) and it takes about 1.0 s for the four generators to reach synchronism. With RTSC control, comparing the results for normal reconfiguration (Section 3.1) versus the results for fault condition, the transients under fault condition are somewhat larger, but still limited to a small and acceptable level. In conclusion, the transient stability of ESPS during reconfiguration under different system contingencies is greatly enhanced by embedding the RTSC into generator control. phase a phase b phase c 60 40 20 0 -20 -40 -60 219.4 219.6 219.8 220 220.2 220.4 220.6 Time (s) (a) Three‐Phase Currents (in kA) through CBs on Stern Side without RTSC Activated 13 8000 6000 4000 2000 0 -2000 -4000 -6000 -8000 218 219 220 221 222 223 224 225 Time (s) (b) Voltage (in Volt) on Starboard Bus without RTSC Activated 1.02 MTG1 MTG2 ATG1 ATG2 1.01 1 0.99 0.98 0.97 0.96 0.95 0.94 0.93 0.92 218 219 220 221 222 223 224 225 226 227 228 Time (s) (c) Frequency (in Per Unit) of Generators without RTSC Activated phase a phase b phase c 60 40 20 0 -20 -40 -60 219.4 219.6 219.8 220 220.2 220.4 220.6 Time (s) (d) Three‐Phase Currents (in kA) through CBs on Stern Side with RTSC Activated 14 8000 ( ) 6000 4000 2000 g 0 -2000 -4000 -6000 -8000 218 219 220 221 222 223 224 225 Time (s) (e) Voltage (in Volt) on Starboard Bus with RTSC Activated 1.02 MTG1 MTG2 ATG1 ATG2 1.015 1.01 1.005 1 0.995 0.99 0.985 0.98 218 219 220 221 222 223 224 225 226 227 228 Time (s) (f) Frequency (in Per Unit) of Generators with RTSC Activated Figure 9 System Reconfiguration Process when a Three‐Phase Bolted Fault Occurs 4 CONCLUSION A novel real-time synchronization controller for ESPS is described in this report. The controller is applicable to both MVAC and HFAC systems. Its goal is to keep multiple generators in synchronization at all times regardless of connectivity, which ensures successful and reliable system reconfiguration whenever it is needed. The RTSC consists of two parts, frequency control and phase control, which are described in the report. Low-pass filters are tuned to avoid interference between these two controls. To verify the effectiveness of the proposed RTSC, two scenarios reflecting different system contingencies are simulated based on MVAC Notional Baseline System. All test results demonstrate that the transient current level, voltage sag, and frequency deviation are all limited within an acceptable level to deliver a safe reconfiguration process. In conclusion, the transient stability of ESPS during reconfiguration process is greatly enhanced by applying the RTSC to the control system. Due to the high requirement for flexibility and reliability in ESPS, it is suggested that the RTSC be implemented in practice. 15 5 ACKNOWLEDGEMENTS 6 REFERENCES [1] James Langston, Mischa Steurer, Jonathan Crider, Scott Sudhoff, Yonggon Lee, Edwin Zivi, Roger Dougal, Yucheng Zhang, Robert Hebner, Abdelhamid Ouroua, “Waveform-Level Time-Domain Simulation Comparison Study of Three Shipboard Power System Architectures”, 2012 International Simulation MultiConference, Genoa, Italy, July 2012. [2] Norbert Doerry, “Next Generation Integrated Power System: NGIPS Technology Development Roadmap”, [Online]. Available: http://www.dtic.mil/cgi-bin/GetTRDoc?AD=ADA519753 16