Grid Integration of Wind Energy in the Western Cape Final Report December 2009 Grid Integration of Wind Energy in the Western Cape 1 Commissioned by: Deutsche Gesellschaft für Technische Zusammenarbeit (GTZ) GmbH Division Water, Energy, Transport TERNA Wind Energy Programme Dag-Hammarskjöld-Weg 1-5 D-65760 Eschborn Contact: Daniel Werner (daniel.werner@gtz.de) Department of Environmental Affairs and Development Planning (D:EA&DP) Contact: Dipolelo Elford (delford@pgwc.gov.za) Birgit Moiloa (bandrich@pgwc.gov.za ) Eskom Contact: Kevin Leask (LeaskK@eskom.co.za) Riaan Smit (Riaan.Smit@eskom.co.za) Consultant: DIgSILENT GmbH Heinrich-Hertz-Str. 9 72810 Gomaringen Germany Web:http://www.digsilent.de Contact: Markus Pöller (mpoeller@digsilent.de) Grid Integration of Wind Energy in the Western Cape 2 Table of Contents 1 Introduction ......................................................................................................................................... 5 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg ............................................................. 6 2.1 Grid Configuration ..................................................................................................................................6 2.2 Scope of Studies ....................................................................................................................................7 2.3 Considered Wind Farm Model ..................................................................................................................7 2.4 Analyzed Cases ......................................................................................................................................7 2.5 Impact on Thermal Limits in the Surrounding Subtransmssion Network.......................................................8 2.5.1 Probabilistic Assessment of the Non Delivered Energy in the Case of Wind Farm Limitation ......................9 2.5.2 Limit the Wind Farm Output in the Case of an Actual Line Failure ........................................................ 11 2.5.3 Dynamic Line Rating Systems ........................................................................................................... 11 2.6 Impact on Voltage Variations at the Connection Point and the Surrounding Subtransmission Network.......... 12 2.6.1 Reactive Power Control Modes.......................................................................................................... 12 2.6.2 Impact Studies................................................................................................................................ 13 2.7 Impact on Short Circuit Currents ........................................................................................................... 15 2.7.1 Special Modeling Considerations ....................................................................................................... 16 2.7.1.1 Short Circuit Currents of WTGs .................................................................................................... 16 2.7.1.2 Equivalent Synchronous Machine Model........................................................................................ 17 2.7.1.3 Model Aggregation...................................................................................................................... 18 2.8 Impact on Harmonics ........................................................................................................................... 19 2.8.1 Harmonic Current Injection Studies of Wind Farms ............................................................................. 19 2.8.1.1 Superposition ............................................................................................................................. 19 2.8.1.2 Wind Farms with Short Connection to the Grid .............................................................................. 20 2.8.1.3 Wind Farms with Long Cable Connection to the Grid ...................................................................... 20 2.8.1.4 Special Modelling Considerations.................................................................................................. 20 2.8.1.5 In-the-Field Measurements.......................................................................................................... 21 2.8.2 Results of Studies for the 150MW Wind Farm at Laingsburg ................................................................ 21 2.9 Impact on Flicker ................................................................................................................................. 21 2.9.1 General Methodology ....................................................................................................................... 21 2.9.2 Results of Studies............................................................................................................................ 22 2.10 Stage 1 – Summary ............................................................................................................................ 22 3 Stage 2: Connection of 750 MW of Wind Farms in Karoo Area to the 400 kV Grid. ........................ 24 3.1 Scenario Definition ............................................................................................................................... 25 3.1.1 Base Case Scenarios ........................................................................................................................ 25 Grid Integration of Wind Energy in the Western Cape 3 3.1.2 High Wind Scenarios........................................................................................................................ 26 3.2 Series Compensation at Komsberg 400 kV .............................................................................................. 27 3.2.1 Modified Series Compensation at Komsberg 400 kV ............................................................................ 27 3.3 Impact on Voltage Variations at the Wind Farm Connection Point ............................................................. 28 3.4 Results of Contingency Analysis for Stage 2 ............................................................................................ 29 3.5 Stage 2 - Summary .............................................................................................................................. 31 4 Stage 3: Feasibility Studies for up to 2800MW of Wind Generation in the Western Cape.............. 32 4.1 Background ......................................................................................................................................... 32 4.2 Scenario Definition ............................................................................................................................... 34 4.2.1 Base Case Scenarios ........................................................................................................................ 34 4.2.2 High Wind Scenarios........................................................................................................................ 34 4.3 Results of Load Flow Studies ................................................................................................................. 36 4.4 Additional Considerations ...................................................................................................................... 36 4.4.1 Balancing of Wind Variations ............................................................................................................ 37 4.4.2 Reactive Power/Voltage Control ........................................................................................................ 37 4.4.3 System Stability .............................................................................................................................. 38 4.5 Stage 3: Summary ............................................................................................................................... 38 5 Conclusions and Recommendations.................................................................................................. 39 6 Referenced Documents...................................................................................................................... 41 List of Annexes...................................................................................................................................... 42 Grid Integration of Wind Energy in the Western Cape 4 1 Introduction 1 Introduction The Western Cape is one of several South African regions with a particularly high wind regime. For this reason, a large number of project developers and other investors from inside and outside South Africa have the intention to develop these resources and to build and operate grid connected wind farms. Besides the regulatory and legal framework, the electrical grid could represent a potential constraint with regard to the extend up to which wind generation could potentially be exploited in the Western Cape. For this reason, GTZ asked DIgSILENT in cooperation with the Western Cape Department of Environmental Affairs and Development Planning (D: EA&DP) and ESKOM to carry out grid studies with the purpose of: • Demonstrating study approaches for the connection of wind farms to the subtransmission and transmission grid. • Carry out a feasibility study for the integration of up to 2800MW of wind generation in the Western Cape. For this purpose, the following three stages have been defined for this project: • Stage 1: Connection of a 150MW wind farm at Laingsburg to 132kV grid (see chapter 2) • Stage 2: Connection of 750MW of wind farms in the Karoo area to the 400kV grid (see chapter 3) • Stage 3: High level feasibility studies for the integration of up to 2800MW of wind generation into the Western Cape (see chapter 4). This report provides a comprehensive overview about approaches and results of the studies that have been carried out. The studies are part of a joint project carried out by the Department of Environmental Affairs and Development Planning (D:EA&DP), Eskom and the TERNA Wind Energy Programme of the German Technical Cooperation (GTZ). TERNA is funded by the German Federal Ministry of Economic Cooperation and Development (BMZ). Grid Integration of Wind Energy in the Western Cape 5 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg 2 Stage 1: 1: Connection Connection of a 150 MW Wind Farm at Laingsburg For demonstrating relevant approaches for studying the grid connection of individual wind farms at subtransmission levels (132kV), the example of a 150MW wind farm that shall be connected at the Laingsburg 132kV substation is described in the following sections. 2.1 Grid Configuration The projected connection point of the 150 MW wind farm is stated to be approximately at 5.4 km from the existing 132 kV transmission lines Laingsburg - Boskloof [1]. From this connection point one double circuit Wolf line of 4 km length were considered to connect the 150 MW wind farm. Figure 1 shows a schematic diagram of the wind farm connection near to Laingsburg. As shown in this diagram, both parallel paths of the existing double circuit line have been opened and connected to a new substation at the 132kV wind farm connection point. GEELB1_2 lod_70892.. lod_70892_1 RUITK1_2 KOUP1_2 GEMSB1_2 ANTJK1_2 2181WOLF 0,51 BAVIN1_2 ANTJIESK 2181WOLF 3,87 WHITH1_2 2181WOLF 2,08 BANTM2_2 2181WOLF 2,63 PIETM1_2 2181WOLF 2,07 QUARY1_2 KOUP GEELBEK BAVIANSK BANTAM BOSKLOOF 2 lod_70962_1 lod_72802_1 lod_72882_1 The cut-in of the wind farm into one circuit only has initially been considered too but even a very quick analysis has shown that this would not be a feasible option for the connection of such a large wind farm. For this reason, this option has not further been followed up on. BOTES_2 WELTV1_2 2181WOLF 74,80 LEEUG1_2 2181WOLF 11,41 2181WOLF 11,17 Continued on Bacchus 132kV diagram 2181WOLF 9,96 2181WOLF 12,93 2181WOLF 13,16 2181WOLF 14,20 2181WOLF 9,64 2181WOLF 24,09 2181WOLF 21,81 lod_70682_1 lod_72852_1 lod_72932_1 lod_70922_1 lod_70842_1 lod_70762_1 2181WOLF 12,41 lod_72962_1 2181WOLF 74,80 PIETM1_1 BANTM1_1 WHITH1_1 LEEUG1_1 2181WOLF 11,05 2181WOLF 12,93 BAVIN1_1 lod_70732_1 2181WOLF 21,81 2181WOLF 9,96 GEELB1_1 RUITK1_1 2181WOLF 13,16 2181WOLF 9,64 GEMSB1_1 KOUP1_1 2181WOLF 14,20 2181WOLF 24,09 BOTES_1 ANTJK1_1 WELTV1_1 To DROERIVIER 2181WOLF 11,45 QUARY1_1 2181WOLF 11,17 2181WOLF 12,40 2181WOLF 11,41 2181WOLF 22,49 BOSKLOOF 1 2181WOLF 11,05 trf_70682.. 2181WOLF 22,49 2181WOLF 11,45 LEEUG22 LAIN132B1 lod_70686_1 LAIN132B2 LAINGSBURG 2161WOLF WP51WOLF 14,45 14,45 LAIN WF Tr 1 LAIN132 WF WP51WOLF 6,00 2161WOLF 6,12 M1311CH 28,11 LAIN33 WF BUFPT1 LADIS13 trf_74002.. SWART1 trf_73002.. LAIN WF Tr 2 150 MW Wind Park 2181WOLF 9,40 2181WOLF 9,40 LAIN0.69 WF Ladismith SWART22 BUFPT22 Voltage Levels Laingsburg WF 400, kV 220, kV 132, kV 66, kV 33, kV lod_73006_1 lod_74006_1 Figure 1: Wind farm connection near to the Laingsburg 132kV substation Grid Integration of Wind Energy in the Western Cape 6 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg 2.2 Scope of Studies For analyzing the grid impact of a wind farm connection at 132kV, the following main aspects have to be studied: • Impact on thermal limits in the surrounding subtransmssion network • Impact on voltage variations at the connection point and the surrounding subtransmssion system: • Impact on short circuit levels • Impact on Power Quality aspects (Harmonics/Flicker, IEC 61400-21) Each of these aspects requires different types of studies and modelling approaches, which are described in the following sections. 2.3 Considered Wind Farm Model Model For studying the impact on thermal limits in the surrounding subtransmission network and for analyzing the impact on voltage variations at the grid connection point, an aggregated model of the wind farm is typically used, as shown in Figure 1. The wind farm is represented by the main step-up transformer, connecting the wind farm to the 132kV grid connection point, a number of n parallel step-up transformers, stepping the LV-side of the wind turbine generators (WTGs) up to the medium voltage level of the wind farm internal collector system and a number of n parallel generators. The impedance of the wind farm internal cables can be neglected when just looking at the impact on the surrounding 132kV network. In the case of this particular example, it was assumed that the wind farm would consist of 75 WTGs having a rating of 2MW each. However, for this type of grid impact study, the actual number and size of the individual turbines is irrelevant as long as the total wind farm size at the grid connection point is correct. 2.4 Analyzed Cases The studies described in the next section have been performed based on a model of the Western Cape network, which includes the complete Western Cape transmission network and all 132kV subtransmission networks. The basis of these studies is the “study year 2009”. The following operational scenarios were considered: • High Load in the Western Region Area • Low Load in the Western Region Area Grid Integration of Wind Energy in the Western Cape 7 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg Table 1: List of analyzed cases Name High Load Study Case description Base Case, High Load Low Load HL+150 MW Wind Farm Laingsburg LL+150 MW Wind Farm Laingsburg Base Case, Low Load High Load considering the connection of a 150 MW wind farm at Laingsburg 132 kV. Low Load considering the connection of a 150 MW wind farm at Laingsburg 132 kV. Project 0Western Region Master Project_Stage 1 and Laingsburg Wind Study_Stage 1 Wind speed diversity within the wind farm is initially not considered and all studies are based on the assumption that up to the registered capacity of 150MW will potentially be generated at the grid connection point. Only when encountering problems, such as overloaded lines under n-1 conditions, a more detailed assessment considering wind speed diversity will be carried out. This approach is generally recommended because the registered capacity is the only reliable information that is typically available at this stage of the wind farm planning process and any other assumption would lead to results without any margin. Only when encountering problems, it is advisable to look more into detail for avoiding uneconomic results. 2.5 Impact on Thermal Limits in the Surrounding Subtransmssion Network Network In a first step, it is required to verify that the existing network capacity is able to take the additionally generated power. For this purpose, credible contingencies, such as n-1 branch outages, have to be analyzed. An n-1 analysis based on load flow calculations of all surrounding lines leads to the conclusion that there is a thermal overload problem in the case that one circuit between Laingsburg and Boskloof is on outage and the wind farm production is above 120MW. For all other contingencies, no thermal problems can be identified. The worst case situation with a wind farm production of 150MW and the outage of one of the parallel circuits is depicted in Figure 2. As shown in this diagram, the circuit that will remain in service will carry a load of 127% of its thermal rating. The general options for mitigating such problems are: • Reinforce the existing line or build a new line. • Limit the wind farm during all times. • Limit wind farm output in case of actual line failure (manual or automatic inter-trip). • Consider dynamic line rating systems. Grid Integration of Wind Energy in the Western Cape 8 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg Generally, the most economic solution under the constraint that a secure network operation is ensured should be taken. However, the costs associated with each of the four options depend on • Length of the line • Number of hours per year during which the overload situation occurs (and during which the wind farm output would have to be limited) For this reason, only a probabilistic assessment considering the actual wind speed conditions at the site can provide an answer to the question, which mitigation option should finally be applied. GEELB1_2 RUITK1_2 KOUP1_2 GEMSB1_2 ANTJK1_2 2181WOLF 74,80 km 0,00 % 2181WOLF 22,49 km 0,00 % 2181WOLF 11,41 km 0,00 % 2181WOLF 11,17 km 0,00 % Continued on Bacchus 132kV diagram 2181WOLF 9,96 km 0,00 % 2181WOLF 12,93 km 20,17 % 2181WOLF 13,16 km 18,27 % BOTES_2 2181WOLF 14,20 km 17,12 % 2181WOLF 9,64 km 17,76 % 2181WOLF 24,09 km 16,59 % lod_72852_1 lod_72932_1 lod_70922_1 lod_70842_1 2181WOLF 12,41 km 0,00 % lod_72962_1 2181WOLF 74,80 km 110,86 % 2181WOLF 11,41 km 112,44 % 2181WOLF 22,49 km 111,37 % PIETM1_1 2181WOLF 11,17 km 115,48 % BANTM1_1 WHITH1_1 2181WOLF 9,96 km 115,69 % 2181WOLF 11,05 km 20,68 % 2181WOLF 12,93 km 22,62 % BAVIN1_1 GEELB1_1 RUITK1_1 2181WOLF 13,16 km 20,32 % 2181WOLF 9,64 km 17,88 % GEMSB1_1 KOUP1_1 2181WOLF 14,20 km 17,53 % To DROERIVIER 2181WOLF 11,45 km 22,97 % Loading <=127 % 2181WOLF 24,09 km 16,33 % BOTES_1 ANTJK1_1 2181WOLF 11,45 km 20,83 % QUARY1_1 2181WOLF 12,40 km 120,99 % BOSKLOOF 1 2181WOLF 11,05 km 19,67 % 2181WOLF 0,51 km 0,39 % BAVIN1_2 2181WOLF 3,87 km 1,37 % BOSKLOOF 2 WHITH1_2 2181WOLF 2,08 km 0,95 % BANTM2_2 2181WOLF 2,63 km 6,05 % PIETM1_2 2181WOLF 2,07 km 3,36 % off QUARY1_2 LAIN132B1 LAIN132B2 LAINGSBURG 2161WOLF WP51WOLF 14,45 14,45km km 15,97 15,72% % 180,00 MVA 86,01 % LAIN132 W F WP51WOLF 6,00 km 14,48 % 2161WOLF 6,12 km 14,59 % M1311CH 28,11 km 7,06 % LAIN33 WF BUFPT1 LADIS13 10,00 MVA 60,68 % 10,00 MVA 14,00 % SWART1 2,50 MVA 81,36 % 150 MW Wind Park 2181WOLF 9,40 km 31,04 % 2181WOLF 9,40 km 31,04 % LAIN0.69 WF Ladismith SWART22 BUFPT22 Laingsburg WF lod_73006_1 lod_74006_1 Figure 2: Outage of one of the parallel 132kV lines between Laingsburg and Boskloof 2.5.1 Probabilistic Assessment of the Non Delivered Energy in the Case of Wind Farm Limitation For analyzing the second mitigation option; that is, limiting the wind farm output to 120 MW during all times (80 % of rated output), the probability that the actually generated power exceeds a level of 80% of installed capacity has to be assessed. For this assessment, the following information is required in addition to a load flow model of the zone of interest: Grid Integration of Wind Energy in the Western Cape 9 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg • Equivalent power curve of the wind farm • Average wind speed and, if available, the Weibull-shape factor of the wind speed distribution. In the case that no more detailed information is available, which is usually the case in an early planning stage; a typical power curve of a wind generator can be used as equivalent wind farm power curve. Effects, like wind-farm internal losses etc. can be considered in the equivalent wind farm power curve. Based on average wind speed and shape factor, the distribution of wind-speeds can be calculated, based on a Weibull distribution. Together with the equivalent wind farm power curve, a wind generation duration curve for one wind farm can be calculated showing the probability for the case that the generated wind power exceeds a given level (see Figure 3). The energy that cannot be delivered to the system can then be evaluated by calculating the area between that part of the red curve that is above the blue line indicating the wind farm limit and the blue line itself. For a monetary analysis, this area has to be multiplied by the assumed tariff. In case of the wind farm at Laingsburg, there were no wind speed data available. For this reason, the corresponding assessment has been carried out for an assumed average wind speed of 7 m/s and 8 m/s. this assessment will provide a good idea about the order of magnitude of the monetary losses associated with a wind farm limitation and at the same time show the sensitivity of this value against average wind speed. Capping a single wind farm with 7m/s average wind speed at 80% results in a not delivered energy of approximately 5% of the totally available energy. This would be equivalent to around 19 000 MWh/year, which could not be delivered. Assuming a tariff of 1,25 Rand/kWh, the resulting economic losses to the wind farm operators would be in the order of magnitude of 23 750 000 R/year. If instead 8m/s average wind speed is assumed an considering also an 80% power output limit, the results indicate a not delivered energy of approximately 7,5% of the totally available energy. This would be equivalent to around 37 000 MWh/year, which could not be delivered, resulting in 46 250 000 R/year of losses. Grid Integration of Wind Energy in the Western Cape 10 DIgSILENT 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg 12,50 10,00 7,50 5,00 2,50 0,000 -2,50 0,500 1,500 2,500 3,500 4,500 5,500 6,500 7,500 8,500 9,500 10,50 11,50 12,50 13,50 14,50 15,50 16,50 17,50 18,50 19,50 20,50 x-Axis: Windpark Analysis: Wind Speed in m/s Windpark Analysis: Probability in % 160,00 Y =120,000 MW 16.624 % 120,00 80,00 40,00 0,00 -40,00 0,03 x-Axis: DIGSILENT 20,03 Windpark Analysis: Cummulative Probability in % Windpark Analysis: Generated Power in MW 40,03 60,03 80,03 High Load Voltage at Laingsburg Wind Farm Connection Point 100,03 Plots PV-Curve Date: 7/23/2009 Annex: 1 /3 Figure 3: Wind speed distribution and power duration curve for an average wind speed of 7 m/s 2.5.2 Limit the Wind Farm Output in the Case of an Actual Line Failure Alternatively, if network operation guidelines allow so, it would be much more economical to limit the wind farm output only under situations, in which one of the circuits between Laingsburg and Boskloof is actually out of service, e.g. because of a planned or an unplanned outage. In cases, in which there is only a minor overload on the remaining circuit, like in the situation here, it would be possible to limit the wind farm output by a manual post-fault action executed by the network operator. Alternatively, or in situations in which there is a major overload (above the emergency rating of the line) it is advisable to install an automatic intertrip-schemes that trips some of the wind turbines in the wind farm in the case that the circuit breakers of one of the two parallel circuits are opened. 2.5.3 Dynamic Line Rating Systems The rating of overhead lines depends on: • Ambient temperature Grid Integration of Wind Energy in the Western Cape 11 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg • Wind speed and wind direction In case of cool weather and/or under high wind speeds, overhead lines experience a much better cooling and hence have a much higher rating than under high temperature and/or low wind speed conditions. Because of the positive correlation between line rating and wind farm output, the installation of a dynamic line rating system at the critical double circuit line can be a very useful option for avoiding grid congestions. Dynamic line rating systems are either based on: • Measurement of the conductor temperature • Measurement of the line sag • Measurement of ambient conditions or combinations of some of the above listed measurements. Together with a thermal model of the line, it is possible to predict the actual rating of the line at any moment in time. In the example of the 150MW wind farm at Laingsburg it would be very likely that with the help of a dynamic line rating system any limitation of the wind farm output could be avoided because the line rating would automatically increase with increasing wind speeds and increasing wind farm outputs. 2.6 Impact on Voltage Variations at the Connection Connection Point and the Surrounding Subtransmission Network Network Besides the impact on thermal limits, load flow and contingency analysis studies allow analyzing the impact of wind generation on voltage variations during normal operations and during contingencies. In a wind generation impact study, the required level of reactive power support of wind farms need to be identified in an early planning stage. Therefore, studies are typically carried out aiming at: • Identifying the required var-control mode (voltage/droop/const. power factor) • Identifying the required reactive power range • Identifying the need of additional reactive compensation devices in the system. 2.6.1 Reactive Power Control Modes The least cost effective solution for a wind farm is the operation at constant power factor close to unity of each individual WTG, for which no park-controller is required. This is the classical approach for small wind farms (only a few turbines) connected to distribution grids (<=33kV) Grid Integration of Wind Energy in the Western Cape 12 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg In case of wind farms connected to subtransmssion or transmission levels, the system operators usually asks the wind farm operator to maintain a constant power factor, a constant reactive power setting or even the voltage at the grid connection point. Hardware costs of the WTGs depend on the required power factor range (or reactive power range) of each individual WTG. In case of wind farms connected to a transmission or subtransmission level, the power factor range required at the grid connection point is not equal to the power factor range of each WTG because the reactive power need of the step-up transformers and the main grid-transformer has to be covered by the WTGs too. For this reason, there is usually additional shunt capacitors connected near to the grid connection point for complying with reactive power requirements of the system operator. When requiring the operation with unity power factory at the grid connection point, the power factor range of typical WTGs is usually sufficient for covering the reactive power demand of wind farm internal components. When asking for a wider power factor range at the grid connection point, e.g. 0,95, WTGs with wider reactive power range and/or additional shunt capacitors are usually required. Voltage control requires a feed-back loop of the voltage and continuously varying reactive adjustment of the WTGs. Depending on the dynamic requirements (speed of operation) and the required reactive power range of the WTGs, it will be possible to realize voltage control by WTGs and additional shunt capacitors or even additional dynamic reactive power compensation devices, such as SVC or STATCOM might be required, which can have a very high cost impact. Droop control refers to a combined voltage-reactive power control defined by a v-Q characteristic, according to which reactive power is adjusted. Droop control is typically used for fast acting reactive power compensation devices, such as STATCOMs or SVCs. 2.6.2 Impact Studies The purpose of system impact studies should be to identify the required reactive power control mode, the required reactive power range and dynamic performance requirements. It is important to consider cost aspects, as described in the previous section for avoiding unnecessary investments. The feasibility of a wind farm consisting of wind generators that operate with constant power factor (at MV-side of WTG step-up transformers) can be evaluated by analyzing P-V-curves for normal operating conditions and for a set of critical contingencies. P-V curves can be used for analyzing voltage variations resulting from: • Varying wind speed (varying active power generation) • Contingencies The P-V curves depicted in Figure 4 apply to normal operating conditions (red curve) and three contingencies (line outages) in the neighborhood of the planned wind farm for the operation with a constant power factor of cos(phi)=1 at the MV-side of each WTG step-up transformer. Grid Integration of Wind Energy in the Western Cape 13 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg According to the results shown in Figure 4, the maximum voltage at the wind farm connection point would exceed the usual +5% limit and the voltage variation against active power variations would be in the range of approximately 5%. Hence operation with unity power factory would lead to unacceptable voltage variations. It can further be observed from Figure 4 that voltage step changes because of line outages in the neighborhood of the wind farm are within very reasonable limits (around 1%) and don’t cause any problem. The typical approach for mitigating voltage problems, which are due to varying active power levels, is to operate the wind farm with an active power dependent power factor (absorbing vars). This is a very cost effective solution because such a reactive power or power factor characteristic can easily be implemented inside the controller of each individual WTG and doesn’t require any voltage feed-back or global wind farm controller. 1,08 DIgSILENT The resulting PV-curve is depicted in Figure 5. These curves are based on a wind farm with a minimum power factor of 0,95 (absorbing) at the wind farm connection point. The voltage now stays within the required voltage band and voltage variations against active power variations stay within acceptable limits of less than 2%. X =150,000 MW 90.000 142.500 MW 1.070 p.u. 1.070 p.u. 1.065 p.u. 1,05 66.893 MW 59.690 MW 58.381 MW 57.418 MW 1.050 p.u. Y = 1,050 p.u. 1,02 0,99 0,96 0,93 7,50 x-Axis: 47,50 87,50 Laingsburg WF: Active Power in MW LAIN132 WF: Voltage in p.u. - Base Case LAIN132 WF: Voltage in p.u. - Lain132kV_Laingsburg_Off LAIN132 WF: Voltage in p.u. - Laingsburg_Boskloof_Off LAIN132 WF: Voltage in p.u. - Laingsburg_Droerivier_Off 127,50 167,50 207,50 Figure 4: PV-curves for wind farm operation with unity power factor at the connection point Grid Integration of Wind Energy in the Western Cape 14 DIgSILENT 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg X =150,000 MW 1,075 1.050 p.u. 1,050 Y = 1,050 p.u. 1.038 p.u. 1.037 p.u. 1.030 p.u. 1,025 1,000 0,975 0,950 7,50 x-Axis: 47,50 87,50 Laingsburg WF: Active Power in MW LAIN132 WF: Voltage in p.u. - Base Case LAIN132 WF: Voltage in p.u. - Lain132kV_Laingsburg_Off LAIN132 WF: Voltage in p.u. - Laingsburg_Boskloof_Off LAIN132 WF: Voltage in p.u. - Laingsburg_Droerivier_Off 127,50 167,50 207,50 Figure 5: PV Curves considering a cosphi(P) Characteristic 2.7 Impact on Short Circuit Currents In the case of a grid impact study, the main purpose of short circuit studies is to verify that the short circuit rating of existing equipment such as bus bars, circuit breakers, lines or cables remains within the required limits. Additionally, short circuit studies are required for verifying the settings of line or transformer protection relays in the network. Grid Integration of Wind Energy in the Western Cape 15 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg 2.7.1 Special Modeling Considerations DIgSILENT 2.7.1.1 Short Circuit Currents of WTGs 0,30 ip Fault Cleared 0,20 0,10 0,00 -0,10 -0,20 -0,30 -0,10 0,00 0,10 0,20 [s] 0,30 Tr2: Phase Current A/HV-Side in p.u. Tr2: Phase Current B/HV-Side in p.u. Tr2: Phase Current C/HV-Side in p.u. Figure 6: Short circuit currents of a DFIG (HV-side of step-up transformer) Modern, variable speed wind generators, which are either based on doubly-fed induction generators or generators with fully rated converter, are difficult to model for standard, steady state short circuit analysis (e.g IEC 60909 or ANSI C37) because of the following reasons: • If in the time frame of a few milliseconds only, these turbines are influenced by their controllers, making their behavior nonlinear, even during these short time periods. • Doubly-fed induction generators are usually equipped with special protection mechanisms (e.g. crow bar, Chopper-resistance) that trigger during voltage dips. The curves depicted in Figure 6 show the currents of a doubly-fed induction generator in case of a short circuit. The generator of this example is equipped with a crow-bar for protecting the rotor-side converter against high currents and high DC-voltages. Grid Integration of Wind Energy in the Western Cape 16 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg During the period, in which the crow-bar is inserted (first 50ms after fault insertion), AC-components of the short circuit currents are very low because of the field-damping effect of the crow-bar. After the crow-bar has been removed, the converter controllers support the voltage by increasing reactive currents. Therefore, AC components of the short circuit current are again increasing but stay in the range of normal operating currents. This means that doubly-fed induction machine wind generators have a considerable contribution to peak short circuit currents. In the longer term however, when the controllers have taken over again, fault currents will be in a range of normal operating currents, depending on the reactive current control concept of the turbines. Because there are many Grid Codes around the world that require the injection of reactive currents during situations of low voltages and because voltage support usually helps the turbines to ride through low voltage conditions, many wind generators inject reactive currents during situations of low voltages and thereby contribute to AC-components of short circuit currents. 2.7.1.2 Equivalent Synchronous Machine Model Because of the mentioned difficulties with the modeling of variable speed wind generators for steady state short circuit analysis, simplified modeling approaches are required for the inclusion of variable speed wind generators in IEC 60909 or ANSI C37-type short circuit calculations. The typical approach, which is used in many places around the world is nowadays based on an “equivalent synchronous machine” modeling approach, in which variable speed wind generators are approximated by an equivalent circuit with subtransient and transient reactance: • The subtransient reactance is typically defined in a way, that the WTG contribution to peak short circuit currents is reflected correctly. • The equivalent transient reactance typically defines the machine’s behavior during situations, in which the controllers have taken over again. Unfortunately, this approach is not able to provide very accurate results for the short circuit contribution of wind farms. It should only be used for planning studies, when the short circuit rating of existing substations, lines and transformers has to be verified. In the case that accurate short circuit currents have to be calculated, e.g. for analyzing malfunctioning of protection relays, time domain simulations based on accurate dynamic WTG models are required. Grid Integration of Wind Energy in the Western Cape 17 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg DIgSILENT 2.7.1.3 Model Aggregation Aggregation External Grid HV Tr1 PCC Windfarm Trf Tr2 MV N x Step-up Trf WT1 G ~ N x WTG G1 Figure 7: Aggregated Wind Farm Model for System Impact Studies In case of grid impact studies, where the impact of a new wind farm on short circuit ratings of existing equipment is analyzed, an aggregated wind farm model can be used. Typically, wind farms are modeled by one equivalent generator and one equivalent step-up transformer having n times the size of each individual WTG and step-up transformer (see Figure 7). The impedance of wind farm internal cables can be neglected if maximum short circuit currents are in the centre of interest of the studies. We can therefore summarize the following: • Double Fed Induction Generator (DFIG): - Considerable contribution to peak short circuit current. - Contribution to thermal short circuit ratings: approx 1 p.u. shc-current • WTG with fully rated converter: - Contribution to initial short circuit current: approx. 1 p.u. shc-current Grid Integration of Wind Energy in the Western Cape 18 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg - Contribution to thermal short circuit ratings: approx 1 p.u. shc-current In the case of a 150MW wind farm at Laingsburg this results in the following short circuit contribution from the wind farm: • Contribution to initial shc-current (Ikss): approx 2 kA (at 132kV) • Contribution to peak shc-current (ip): 4,4 kA • Contribution to transient shc-current (Iks): 0,67 kA The short circuit contribution of the wind farm is not critical in this particular example because the fault level at the wind farm connection point is very low and the substation is operated far below its short circuit rating. 2.8 Impact on Harmonics 2.8.1 Harmonic Current Injection Studies of Wind Farms Harmonic current injection studies are typically carried out based on wind turbine measurement report according to IEC 61400-21, which lists the worst-case harmonic current injection at each harmonic frequency at which a current injection >0,1% of rated current can be observed. 2.8.1.1 Superposition Because it is very much unlikely, the all wind generators in a wind farm inject worst case harmonic currents with the same phase angle at the same time, assumptions for the diversity with which harmonic currents are injected into the grid by the different wind generators can be made. The generally applied international standard that defines rules for these assumptions is IEC 61000-3-6. The basic consideration of these rules is that: • Low order harmonics are typically resulting from grid commutated converters or saturation effects. Their phase angle is therefore grid synchronized resulting in high correlation of the injected harmonic currents. • High order harmonics are typically resulting from self commutated power electronics converters. Their phase angel is therefore highly uncorrelated. For considering these effects, IEC 61000-3-6 defines formulas allowing calculating the superposition of harmonic voltage distortions resulting from harmonic current injection of different harmonic sources. For wind generation, Summation Law 2 according to IEC 61000-3-6 is typically applied. Summation Law 2 is based on the following formula for each harmonic order h and each harmonic source i: Grid Integration of Wind Energy in the Western Cape 19 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg Uh = α ∑U α hi (1) i with: • α=1 for h<=4 • α=1.4 for h<5 and h<=13 • α=2 for h>13 The practical application of this formula requires the calculation of the harmonic voltage distortion at the connection point caused by each harmonic source (wind generator) in the system and calculating the resulting harmonic voltage distortion by evaluating the formula above. 2.8.1.2 Wind Farms with Short Connection to the Grid For wind farms that are directly connected to the grid with a step-up transformer and without any considerable HV-AC cables, a simplified version of this formula can be applied, as proposed in IEC 61400-21. According to IEC61400-21, the harmonic current injections of the entire wind farm can be modelled by one equivalent harmonic current source at the grid connection point. The harmonic current injection at every harmonic frequency is calculated using (1) and by replacing voltage by current. In these cases, harmonic voltage distortion can simply by calculated by taking the harmonic impedance at the grid connection point with the highest magnitude and multiplying it with resulting harmonic current. 2.8.1.3 Wind Farms with Long Cable Connection to the Grid Wind farms that are connected to the grid via considerable HV-AC cable (e.g. offshore wind farms) require more sophisticated harmonic analysis because there is always a high risk for harmonic resonance problems because of the cable capacitance. The actual location of resonance frequencies may vary with the operating conditions of the transmission grid. Therefore, harmonic voltage distortion must be calculated for the full range of harmonic impedances at the PCC, as it has been worked out by the system operator and by applying (1) for considering the impact of all wind generators in the wind farm on harmonic voltage distortions. The worst case harmonic voltage distortion is then reported and the basis of filter sizing, if a filter will be required. 2.8.1.4 Special Modelling Considerations In some turbine designs, local filters are used, which can have a considerable impact, especially in the case of low order cable resonance problems in the system. Measurement reports according to IEC 61400-21 only report magnitude of harmonic currents measured at the LV-side. A worst case assumption consists of assuming that the entire harmonic contents appear either in positive or negative sequence system. In case of 3rd, 6th, 9th, etc. harmonics, this definitely represents a worst case assumption because the largest part of third order harmonic currents typically appears in the zero sequence. In Grid Integration of Wind Energy in the Western Cape 20 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg the case that the studies show problems at these frequencies, this should be further analyzed, e.g. by looking at harmonic currents measured at the HV-side of the wind turbine step-up transformers (MV-level). 2.8.1.5 InIn-thethe-Field Measurements It is common practice to install a power quality meter in the grid connection point that monitors harmonic voltages at the PCC and harmonic currents injected by the wind farm during wind farm operation. 2.8.2 Results of Studies for the 150MW Wind Farm at Laingsburg Laingsburg Because the actual type of wind generator that will be used at Laingsburg is not yet known at this stage of the connection application, only a rough assessment using a harmonic current spectrum that is typical for modern, variable speed wind turbines could be carried out. The result of corresponding harmonic studies led to a total harmonic voltage distortion (THD) of 0,75% at the 132kV connection point and to individual harmonic distortion levels, which are far below any critical values. This assessment confirms that no harmonic problems would have to be expected when connecting a large wind farm to the 132kV bus bar at Laingsburg. 2.9 Impact on Flicker 2.9.1 General Methodology Flicker, being a variation of the fundamental frequency voltage, can be a result of: • Continuous active power variations of the wind generators, e.g. resulting from wind turbulence. • Switching actions within in the wind farm. Flicker assessment for wind farms is typically carried out according to IEC 61000-3-7 and IEC 61400-21. The method requires the calculation of the minimum short circuit level and impedance angle at the PCC. Based on the impedance angle, the maximum values for: • Flicker coefficient c • Flicker step-factor kf • Flicker step-factor ku • Max. number of switching operations N10 • Max. number of switching operations N120 Grid Integration of Wind Energy in the Western Cape 21 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg for the relevant impedance angle at the grid connection point must be taken from a wind turbine measurement sheet according to IEC 61400-21. These values together with the minimum fault level at the grid connection point allow calculating: • Short-term and long term flicker value (Pst/Plt) during continuous operation. • Short-term and long term flicker value (Pst/Plt) due to switching actions. for one wind generator. For assessing the Flicker of an entire wind farm, IEC 61400-21 states that it can be assumed that the flicker relevant components of wind turbulence and other flicker-relevant aspects are uncorrelated within the wind farm. For this reason, the following formula can be applied for calculating the flicker of an entire wind farm with n turbines based on the flicker of one individual WTG: Pst = Plt = n Pstí With Psti being the short-term flicker of one individual WTG. This means in other words, that the total flicker of a wind farm with n WTGs is lower by a factor of 1 / n than the flicker that would be caused by an individual WTG with n times the size. 2.9.2 Results of Studies In this particular example, Flicker analysis was made using IEC 61400-21 data sheet of a typical variable-speed wind generator. The resulting Flicker levels are equal to: • Pst = 0,066 • Plt=0,08 The significance of the actual results is very limited because the actual results will depend on the number of turbines, their rating and the actual type of turbines that will be installed. However, because the calculated numbers are far below any critical values it can be assumed that flicker won’t cause any problem in the case of a 150MW at Laingsburg, assuming that modern variable speed WTGs will be used. 2.10 Stage 1 – Summary The example of a 150MW wind farm to be connected near to the Laingsburg 132kV substation is used for demonstrating relevant aspects for the grid connection of wind farms at subtransmission levels. Grid Integration of Wind Energy in the Western Cape 22 2 Stage 1: Connection of a 150 MW Wind Farm at Laingsburg In this particular example, there is an issue with regard to thermal overloads of the surrounding overhead lines under some n-1 situations. It is shown, that a probabilistic assessment of the power production of the planned wind farm is required for deciding on the most economic mitigation option. In this particular example, it would be recommended to cap the wind farm output under situations, in which only one circuit between Laingsburg and Boskloof would be available (planned outage/maintenance or as a post-fault action in case of a line trip). This could be achieved by an automatic active power limitation in the wind farm controller or by tripping around 20% of the wind turbine generators (WTGs) under these conditions. Voltage variations can potentially be an issue when operating the wind farm at a constant power factor of equal to one at the grid connection point during all times. For keeping wind-dependent voltage variations within reasonable limits (e.g. 2%), it is recommended in this particular case to operate the WTGs at an active power dependent power factor, which means that increasing voltages because of increasing active power production would automatically be compensated by increased absorption of reactive power. The example presented in this chapter further shows that a power factory range of cos(phi)>0,95 at the wind farm connection point would be sufficient for maintaining the voltage within a 2% limit. A feed-back voltage control would not be required in this particular case. The contribution of short circuit currents by the WTGs is difficult to model because relevant international standards for the calculation of short circuit currents don’t make provision for variable speed WTGs yet. For this reason, it is recommended to use an “equivalent synchronous generator” approach for assessing the required rating of substation equipment and cables. If more detailed analysis is required, only a time-domain simulation considering the actual behaviour of the planned WTGs during grid faults can lead to reliable results. Because it can be assumed that modern, variable speed WTGs based on IGBT technology will be installed, harmonics won’t cause any problem in this particular case. Harmonics emissions of modern IGBT based converters are typically in high frequency ranges and can therefore be filtered locally. There is only a very minor impact on low order harmonics. Flicker is typically not an issue when connecting large wind farms to subtransmission or transmission grids. Because flicker relevant frequencies of wind turbulence or other flicker-relevant effects (such as tower shadowing etc.) are stochastically quite independent, the corresponding power variations at the grid connection point are very well attenuated. This effect could be demonstrated by a flicker analysis according to IEC 61400-21. Only when connecting a small wind farm (only a few turbines) to a weak distribution grid or a small island network, flicker can be an important aspect that would require careful analysis. Grid Integration of Wind Energy in the Western Cape 23 3 Stage 2: Connection of 750 MW of Wind Farms in Karoo Area to the 400 kV Grid. 3 Stage 2: 2: Connection of 750 MW of Wind Farms Farms in Karoo Area to the 400 kV Grid. Grid. For demonstrating approaches and methodologies of connection studies for wind farms that will be integrated into the main transmission system, the planned wind generation in the Karoo Area has been selected. The total amount of wind generation that will be installed in that area, sums up to 750MW (see [1] and [2]). The projected connection point of 750 MW of wind farms is set to be approximately at 71 km from the existing Komsberg 400 kV series capacitor substation located in the Karoo area [1]. The connection of the wind farms to the 400 kV System is proposed to be carried out by means of a new substation that will “cut trough” the corridor Komsberg – Droerivier at the above mentioned distance. This new substation is from here on referred to as Nuweveld 400 kV substation [1]. In this particular example, Nuweveld 400 kV substation is scheduled to connect 5 wind farms of around 150 MW/each that will add together 750 MW of wind generation in the Karoo area. The suggested location of the 5 wind farms is depicted in Figure 8 and described in Table 2. The substation arrangement was considered as a double busbar configuration running solid. Planned connection point of the 750 MW wind farm Figure 8: Planned connection point of the 750 MW wind farms in the Laingsburg – Karoo Area. As before in case of the Laingsburg studies, it has been assumed that all wind farms will be built by 2MW variable speed wind generators. However, for this type of grid impact studies, only the total wind farm size is relevant, the individual turbine size has almost no influence on the results. Grid Integration of Wind Energy in the Western Cape 24 3 Stage 2: Connection of 750 MW of Wind Farms in Karoo Area to the 400 kV Grid. Table 2: Wind parks connected to the Nuweveld 400 kV substation Distance from Nuweveld Power 400kV Substation Output (MW) 20 150 Site 2 12 150 Site 3 35 150 Site 4 25 150 Site 5 24 150 Kronos 57,17 MW 82,31 Mvar Nuweveld 750 MW 0,00 104,71 Aries 400 RX2 -147,67 MW-146,80 MW 4,02 Mvar 6,64 Mvar -145,21 MW-146,27-146,37 MW MW 11,40 Mvar 8,24 Mvar 7,92 Mvar 104,21 5,40 1,35 Helios 400 RX2 Helios 22 Load TX Nuweveld Droerivier-Muldersvlei 400_2 S1 27,82 % 336,08 MW Droerivier-Muldersvlei 400_2 S2 27,85 % 308,41 -101,42 Droerivier-Muldersvlei 400 SCX1 Bypass -334,89 17,98 -308,41 MW 101,42 Mvar 427,15 1,07 5,10 Bacchus-Droerivier 400 SCX1 Droerivier-Muldersvlei 400 SCX2 334,89 MW -17,98 Mvar 420,08 1,05 10,54 Droerivier-Muldersvlei 400 SCX2 Bypass -84,67 Mvar 309,52 MW -136,28 Mvar 42,10 MW 66,13 Mvar Bacc-Droe 400 2 Bacchus-Droerivier 400_1 S1 12,46 % 27,14 % Droe-Mulde 400 2 12,46 % -109,54 MW 30,44 Mvar Victoria 109,54 MW -27,66 Mvar 108,02 MW -27,83 Mvar Droerivier-Victoria 400_1 .. 9,66 % L1-WF4 74,27 % L1-WF5 74,21 % L1-WF3.. 73,79 .. Nuweveld WF-.. Helios Nuweveld WF-.. L1-WF1.. 74,85 % -56,60 MW -177,57 Mvar -108,02 MW 30,54 Mvar Droerivier-Victoria 400_2 .. 9,74 % Nuweveld WF.. Droerivier-Hydra 400_3 .. 12,66 % Nuweve.. L1-WF2 74,46 % Aries-Helios 400_1 .. 16,14 % Nuweveld WF.. Aries 400 RX1 Hydra-Victoria 400_2 12,75 % Aries Hydra-Victoria 400_1 S1 (km) Site 1 Hydra-Victoria 400_1 S2 .. 12,64 % Wind Farm -109,32 MW -45,49 Mvar -107,80 MW -46,31 Mvar 42,10 MW 66,13 Mvar -41,85 MW -145,47 Mvar -41,85 MW -123,49 MW -145,47 Mvar 71,41 Mvar Droerivier 0,00 105,94 0,00 105,94 0,00 0,00 347,01 MW 105,94 105,94 -100,01 Mvar 66,60 16,69 Figure 9: Single line diagram showing the wind farms connected to the Nuweveld 400kV substation Because the total amount of 750MW and the installation of a new substation represent a considerable impact on the main transmission system of the Western Cape, a model of the complete ESKOM transmission network has been used for studying the impact of up to 750MW on the Western Cape transmission system. This model has been made available by ESKOM Tx. 3.1 Scenario Definition 3.1.1 Base Case Scenarios The studies carried out in the next section have been performed based on the “study year 2009”, which means that the planned 765kV line running into the Cape was not considered. The studies were based on the following base-case scenarios (without wind generation), which were defined by ESKOM Tx: Grid Integration of Wind Energy in the Western Cape 25 3 Stage 2: Connection of 750 MW of Wind Farms in Karoo Area to the 400 kV Grid. • High load, 1 Koeberg units in service • High load, 2 Koeberg units in service Unfortunately, ESKOM couldn’t make available standard low load scenarios because ESKOM’s study approaches are generally based on high load scenarios only. However, because in case of wind generation impact studies, low load conditions might sometimes be more problematic than high load situations, low load scenarios have been defined in cooperation of DIgSILENT and ESKOM under the following assumptions: • Demand during low load conditions approximately 60% of high load. Equally distributed across the whole system. • Generator dispatch defined by ESKOM Because these assumptions don’t match with the real behaviour of the system and because the reactive power dispatch, especially outside the cape, could not be defined in a way that all voltages under no-wind-low-load conditions remain within the required limits, only a rough feasibility analysis based on thermal line loadings could be carried out. The relevant low load scenarios are: • Low load, 1 Koeberg unit in service • Low load, 2 Koeberg units in service It is therefore strongly recommended to setup realistic low load scenarios and to carry out additional load flow and contingency analysis studies for credible low load scenarios. 3.1.2 High Wind Scenarios Based on the base case scenarios described in the previous chapter, high wind scenarios have been defined. For balancing the system, the addition of 750MW of wind generation must be compensated by a reduction of 750MW of other generation. The corresponding scenarios have been defined based on the following rules, which were given by ESKOM: 1. Disconnection of Gas Turbine Generators (or running in SCO mode where possible) 2. Reduction of pump storage generation at Palmiet. 3. Reduction of coal power plants outside the Cape (Tutuka, Grootvlei, etc.) On one additional note, if a reduction of coal plants outside the Cape is required, then a minimum dispatch level of 65% of the rated power plant output should be considered. Grid Integration of Wind Energy in the Western Cape 26 3 Stage 2: Connection of 750 MW of Wind Farms in Karoo Area to the 400 kV Grid. In the case of the stage 2 of the studies (750MW of wind generation in the Western Cape), the additional wind generation could be balanced by the gas turbine generators only. The other steps were only required for Stage 3 studies (2800MW of wind generation in the Western Cape, see chapter 4). 3.2 Series Compensation at Komsberg 400 kV In the analyzed study year (2009) several 400 kV series capacitors exist within the Western Cape area. In this example of wind farm integration, the series compensation located at Komsberg 400 kV was of particular interest because of the planned location of the Nuweveld 400 kV substation. Since this substation was assumed to “Cut Trough” the 400 kV Komsberg – Droerivier corridor, the degree of series compensation will be significantly modified. Under this assumption, several scenarios considering the actual series compensation as well as“resized” series compensation were analyzed in order to investigate its impact. In Table 3 the existing Series Compensation of the Komsberg – Droerivier corridor is detailed. Table 3: Actual Series Compensation at Komsberg 400 kV Total Line Transmission Line Series Lenght Reactance XL Capacitor Compensation degree (km) (Ohms) Reactance Xc (%) (Ohms) Droerivier-Bacchus Droerivier-Muldersvlei 401.3 127.3 81.6 64.0 405.2 130.2 74.8 57.4 3.2.1 Modified Series Compensation at Komsberg 400 kV As stated previously, the insertion of the Nuweveld 400 kV substation in the Komsberg – Droerivier corridor will affect the degree of series compensation on the existing lines. In Table 4, a case comparison considering a modified/unmodified series capacitor reactance is shown. Table 4: Case Comparison of the Series Compensation in Komsberg 400 kV Transmission Line Lenght (km) Total Line Series Capacitor Reactance XL Reactance Xc (Ohms) (Ohms) Compensation degree (%) C0.Base Case Droerivier-Bacchus 401.3 127.3 81.6 64.0 Droerivier-Muldersvlei 405.2 130.2 74.8 57.4 C1.Nuweveld; unmodified series capacitor reactance Nuweveld - Bacchus 276,3 88,2 81,6 92,6 Nuweveld-Muldersvlei 280,2 90,6 74,8 82,5 C2.Nuweveld; modified series capacitor reactance Nuweveld - Bacchus 276,3 88,2 56,3 63,9 Nuweveld-Muldersvlei 280,2 90,6 52,0 57,4 Grid Integration of Wind Energy in the Western Cape 27 3 Stage 2: Connection of 750 MW of Wind Farms in Karoo Area to the 400 kV Grid. Table 4 highlights that with the actual Komsberg series capacitor and considering the 400 kV Nuweveld Substation (C1), the degree of series compensation for Nuweveld-Bacchus and Nuweveld-Muldersvlei transmission lines would increase approximately to 92% and 82 % respectively. This would lead to high voltages in the surrounding area. For this reason, it is recommended to downsize the series compensation at Komsberg so that the compensation degree remains the same as prior to the insertion of the new substation at Nuweveld. Additionally, it is recommended to install around 400Mvar of shunt reactors at the 400kV connection point at the Nuweveld substation in order to bring the voltages within the required limits. Alternatively, it would be possible that the wind farms absorb reactive power. However, most WTGs can only provide or absorb reactive power when the wind speed is above the cut-in wind speed. Otherwise the LV breaker is opened and the generator is entirely disconnected from the system. There are a few WTGs, which allow remaining connected if wind speed drops below the cut-in wind speed. However, this feature is typically available at additional costs and additional losses (under no wind conditions). For this reason, the connection of around 400Mvar of shunt reactors would probably be the better option. 3.3 Impact on Voltage Variations at the Wind Farm Connection Point The P-V curves depicted in Figure 10 apply to normal operating conditions (red curve) and two contingencies (line outages) in the neighborhood of the planned wind farm. The PV-curve shows that the system is very strong at the 400kV connection point at that the voltage dependence on active power production is very small even under the assumption that the wind farm operates at unity power factor at the 400kV connection point. Grid Integration of Wind Energy in the Western Cape 28 DIgSILENT 3 Stage 2: Connection of 750 MW of Wind Farms in Karoo Area to the 400 kV Grid. X =750,000 MW 1,08 613.272 MW 1,05 1.052 p.u. 1.050 p.u. Y = 1,050 p.u. 1.045 p.u. 1.034 p.u. 1,02 0,99 0,96 0.950 p.u. 0,93 0,00 x-Axis: 200,00 400,00 Static Generator: Active Power in MW Static Generator: Voltage in p.u. - Base Case Static Generator: Voltage in p.u. Droerivier - Muldersvlei out Static Generator: Voltage in p.u. Droerivier - Bacchus out 600,00 Y = 0,950 p.u. 800,00 1000,00 Figure 10: Voltage at the wind farm connection point against varying active power levels and different contingencies 3.4 Results of Contingency Analysis for Stage 2 For verifying that a n-1 secure operation is possible when connecting up to 750MW of wind generation to the Nuveweld 400kV substation, load flow calculations and n-1 contingency calculations have been executed and it has been verified that no thermal overload of any line or no violation of voltage bands (except from those that already existed under base case/no wind conditions) would occur. The list of contingencies, which contains all 400kV lines in the Western Cape is listed in Table 5. The results of n-1 contingency analysis show that up to 750MW of wind generation can be connected without endangering the n-1 secure operation of the Western Cape transmission grid. Grid Integration of Wind Energy in the Western Cape 29 3 Stage 2: Connection of 750 MW of Wind Farms in Karoo Area to the 400 kV Grid. Table 5: List of Contingencies Name Acacia-Koeberg 400 Acacia-Muldersvlei 400 Acacia-Philippi 400 Ankerlig-Aurora 400 Ankerlig-Koeberg 400 Aries-Helios 400 Aries-Kronos 400 Aurora-Juno 400 Bacc-Droe 400 2 [Droerivier] Bacchus-Droerivier 400 Bacchus-Muldersvlei 400 Bacchus-Palmiet 400 Bacchus-Proteus 400 Droe-Mulde 400 2 [Droerivier] Droerivier-Hydra 400 Droerivier-Muldersvlei 400 Droerivier-Proteus 400 Droerivier-Victoria 400 Gourikwa-Proteus 400 Helios-Juno 400 Hydra-Kronos 400 Hydra-Luckhof (Beta) 400 Hydra-Luckhof 400_2 (Perseus 2) Hydra-Luckhof 400_3 (Perseus 3) Hydra-Poseidon 400 Hydra-Victoria 400 Koeberg-Muldersvlei 400 Koeberg-Stikland 400 Muldersvlei-Stikland 400 Palmiet-Stikland 400 Grid Integration of Wind Energy in the Western Cape 30 3 Stage 2: Connection of 750 MW of Wind Farms in Karoo Area to the 400 kV Grid. 3.5 Stage 2 - Summary The example of the connection of up to 750MW of wind generation in the Karoo area is used for demonstrating relevant approaches for grid connection studies of large wind farms to the main transmission level. In contrast to studies at subtransmission levels (see Stage 1/chapter 2), those studies have to consider the impact of wind generation on the complete transmission system. Especially, the definition of relevant scenarios, considering: • Load and wind generation levels; • Generator dispatch scenarios; is essential for studying the impact of wind generation of thermal aspects and voltage variations. With regard to wind generation levels, it is recommended to consider the maximum registered capacity at the grid connection point as maximum wind generation level. This will lead to results with sufficient margin for considering uncertainties and inaccuracies of model parameters and assumptions related to wind variations. Only in the case that issues related to high wind generation are identified a probabilistic assessment should be carried out for justifying potential mitigation options (see also, Stage 1 – section 2.5.1). This probabilistic assessment should consider technical availability of the WTGs and wind variation. With regard to the actual studies that have been carried out in this chapter, the following conclusions can be drawn: • Voltage variations because of varying wind generation are very small, even in constant power factor operation. • Operation with constant Q (var-control) is appropriate. (Slow) voltage control is possible and should be considered but is not necessarily required. • Series compensation at Komsberg should be resized for avoiding overcompensation. • 4x100Mvar shunt reactors are required at Nuweveld substation (or equivalent var-absorption of the wind farms) because of the proximity of the Nuweveld substation to the Komsberg series compensation. Power quality aspects such as flicker or harmonics are not relevant when connecting very large wind farms to transmission levels, as it has already been shown for stage 1 studies. For this reason, a detailed power quality assessment is not required in this case. Grid Integration of Wind Energy in the Western Cape 31 4 Stage 3: Feasibility Studies for up to 2800MW of Wind Generation in the Western Cape 4 Stage 3: Feasibility Studies for up to 2800MW of Wind Generation in the Western Cape 4.1 Background In stage 3 of the Western Cape wind impact studies, all wind farms for which applications existed in March this year have been considered and a high level feasibility study about their impact on the ESKOM transmission grid has been carried out. The total amount of installed wind generation capacity that will feed into each HV substation is listed in Table 6. Table 6: Totally installed wind generation per area and substation Area Substation Application (MW) Vredendal-Juno Juno (132 kV) 220 Aurora Aurora (132 kV) 400 Darling Koeberg (132 kV) 300 Overberg Bacchus (132 kV) 242 Laingsburg-Karoo Laingsburg (132 kV) 150 Laingsburg-Karoo Nuweveld (400 kV) 750 Beaufort West-Loxton-Hydra Droerivier (400 kV) 664 The main purpose of these studies was to analyse if the integration of up to 2800MW of wind generation in the Western Cape would be feasible without any major network upgrade (line upgrade). For this purpose, all wind generation projects, for which applications existed at the starting date of these studies (end of March 2009) have been summed up, lumped together and connected to the nearest 400kV substation (see Figure 11 to Figure 13). This means that the studies described in this chapter of this report explicitly exclude all issues that might come up at the 132kV subtransmission levels. It is evident that substantial line upgrades will be required for accommodating such a large amount of wind generation, wherever the distance to the next 400kV substation is too far. For studying the general feasibility of the planned wind farm projects, load flow calculations under base case and contingency scenarios have been carried out and it has been verified that all cases are n-1 secure without any thermal or voltage violations (except from those, which already existed in the base case/no wind scenarios). Grid Integration of Wind Energy in the Western Cape 32 4 Stage 3: Feasibility Studies for up to 2800MW of Wind Generation in the Western Cape ~ G ~ G Nama 66 Load TX Anke rlig-A urora 40 0_2 ~ G ~ G Aggeneis 66 Load TX Aggeneis Aggene is 220 RX1 220 R X2 Aurora Anker lig Gen 3 2 Ank erlig Ge n 4 2 Gromis 66 Load TX Anker lig Gen 3A1nkerlig Ge n 41 Anker lig Gen 4 3 ~ G Helios-Juno 400_1 S2 Juno Aurora-Juno 400_1 Anke rlig-A urora 40 0_1 Aurora WF L1-WFJ L1-WFA Juno WF Aurora 400 MW Juno 220 MW Ankerlig Power Station Ankerlig-Koeberg 400_1 Darling WF L1-WFD Darling G ~ G Ank erlig Ge n 1 2 G A nkerlig Ge n 22 ~ ~ Ankerlig Ge n 21 Ankerlig Ge n 11 Darling 300 MW Juno Juno 400 RX1 Juno 400 RX2 Juno 66 Load TX Aurora 132 LoadAurora TX Aurora 132Aurora CX2 132 CX 1 400 RX1 Koeberg-Muldersvlei 400_2 S2( Koeberg-Muldersvlei 400_2 S3 Koeberg-Muldersvlei 400_2 S3(1) Koeberg-Muldersvlei 400_2 S 1 Muld esrvlei Muldersvlei 132 L oad 66TX Load TX Muldersvlei Mulde13 rsvlei Mulde 2 C X3 13 rsvlei 2 C X2 13 2 CX1 Acac ia-M uldersvlei 40 0_1 S2 Acacia-Muldersvlei 400_1 S1 Acacia-Koeberg 400_1 S2 Bacchus-Muldersvlei 400_1 S1 Mulde rsvlei Muldersvlei S VCSVC SCX Muldersvlei SVC FCX Koeberg-Stikland 400_1 S2 Koeberg Gen1 SVS Koeberg 132 Load TX Koeberg-Stikland 400_1 S3 Koeberg Gen2 Acacia-Koeberg 400_1 S1 G ~ Acacia-Koeberg 132_2 G ~ Muldersvlei Koeberg-Stikland 400_1 S1 Koeberg Power Station Bacchus-Droerivier 400_1 S4 G ~ Ankerlig-Koeberg 400_2 Aurora Nuweveld Nuweveld 750 MW Nuweveld WF.. Helios 400 RX2Helios 22 Load TX Nuweveld Bacchus-Droerivier 400_1 S1 Droerivier-Muldersvlei 400_2 S2 Hydra-Poseidon 400_1 Victoria Droerivier-Victoria 400_2 L1-WF4 L1-WF5 Nuweveld WF-.. L1-WF3 L1-WF1 Nuweveld WF-.. Helios Droerivier-Hydra 400_3 Nuweve.. L1-WF2 Aries-Helios 400_1 Nuweveld WF.. Aries 400 RX2 Hydra-Victoria 400_2 Hydra-Victoria 400_1 S2 Kronos Droerivier Droerivier-Victoria 400_1 Aries Hydra-Victoria 400_1 S1 Figure 11: Wind Generation in the Western Cape – Substations Darling, Aurora and Juo Droerivier WF L1-WFD Droe-Mulde 400 2 Droerivier 664 MW Bacc-Droe 400 2 Bacchus-Droerivier 400_1 S2 Komsberg Series Capacitors Droerivier Droerivier-Muldersvlei 400_2 S1 Bacchus-Droerivier 400 RX1 Droerivier 132 Load TX Droerivier 22 Load TX Droerivier 400 RX1 L1-WFL Droerivier 400 RX2 Figure 12: Wind Generation in the Western Cape – Substations Nuweveld and Droerivier Grid Integration of Wind Energy in the Western Cape 33 4 Stage 3: Feasibility Studies for up to 2800MW of Wind Generation in the Western Cape Muldersvlei Komsberg Series Capacitors Bacchus-Droerivier 400_1 S2 SVS Droerivier-Muldersvlei 400_2 S1 Bacchus-Droerivier 400_1 S4 Bacchus-Muldersvlei 400_1 S2 Bacchus-Palmiet 400_1 Laingsburg Droerivier 132 Load TX Droerivier 22 Load TX L1-WFL Droerivier 400 RX1 Droerivier 400 RX2 Droerivier-Muldersvlei 400 RX2 Bacchus-Droerivier 400_1 S3 Muldersvlei-Stikland 400_1 Bacchus-Droerivier 400 RX1 Droerivier-Proteus 400_1 Muldersvlei Muldersvlei 132 Muldersvlei CX3 132 CX2 132 CX1 Bacchus-Muldersvlei 400_1 S1 Muldersvlei SVCSVC SCX Muldersvlei Muldersvlei SVC FCX Droerivier Laingsburg 150 MW Proteus 400 RX Bacchus-Proteus 400_1 ProteusProteus 66 Load 132 TXload TX Proteus Bacchus 132 Bacchus CX1 Bacchus 132 CX2 132 Load TX L1-WFO Bacchus Overberg Proteus 132 CX1 Gourikwa-Proteus 400_1 Bacchus 400 RX1 Gourikwa-Proteus 400_2 Overberg WF Gourikwa-Proteus 400_3 Ov erberg 242 MW Gourikwa Power Station G ~ G ~ G ~ G ~ G ~ Gen 13 Gourikwa GenGourikwa 12 Gourikwa Gen 11 Gourikwa Gen 22 Gourikwa Gen 21 Figure 13: Wind Generation in the Western Cape – Substations Overberg and Laingsburg 4.2 Scenario Definition 4.2.1 Base Case Scenarios The base case scenarios have been defined in the same way as in case of stage 2 (see section 3.1.1). As already stated in section 3.1.1, ESKOM could not make available approved low load scenarios. Therefore, approximate low load scenarios have been derived from the high load scenarios and used for the studies. Hence, the accuracy of the results obtained under low load conditions is very limited. 4.2.2 High Wind Scenarios Based on the base case (no wind) scenarios, high wind scenarios have been defined considering all wind farms according to Table 6. It has further been assumed that under high wind conditions, all wind farms will operate at rated active power. Additionally, losses that might occur at subtransmission levels, to which some of the wind farms will be connected, have been neglected. Obviously, this represents an extremely conservative worst case assumption. Grid Integration of Wind Energy in the Western Cape 34 4 Stage 3: Feasibility Studies for up to 2800MW of Wind Generation in the Western Cape Alternatively, the results can be interpreted in a way that up to 2800MW of wind generation can actually feed into the Western Cape transmission grid and that the actually installed wind generation capacity might even be higher when assuming realistic diversity factors. The analyzed scenarios are listed in Table 7 Table 7: List of analyzed scenarios Name Study Case description HL 1 Unit Koeberg High Load considering only 1 Koeberg unit in service. HL 2 Units Koeberg High Load considering 2 Koeberg units in service. HL 1 Unit Koeberg + WF 2800 MW High Load considering the connection of all Western Cape wind farms. 1 Koeberg unit in service. HL 2 Units Koeberg + WF 2800 MW High Load considering the connection of all Western Cape wind farms. 2 Koeberg units in service. LL 1 Unit Koeberg Low Load considering only 1 Koeberg unit in service. LL 2 Units Koeberg Low Load considering 2 Koeberg units in service. LL 1 Unit Koeberg + WF 2800 MW Low Load considering the connection of all Western Cape wind farms. 1 Koeberg unit in service. LL 2 Units Koeberg + WF 2800 MW Low Load considering the connection of all Western Cape wind farms. 2 Koeberg units in service. Project Grid Planning High Load_Stage 2 and 3 Grid Planning High Load_Stage 2 and 3 For balancing the additional generation, the same procedure as described in section 3.1.2 was applied, which is repeated here again: 4. Disconnection of Gas Turbine Generators (or running in SCO mode where possible) 5. Reduction of pump storage generation at Palmiet. 6. Reduction of coal power plants outside the Cape (Tutuka, Grootvlei, etc.) In contrast to the stage 2 studies described in chapter 3, it is necessary to reduce generation outside the Cape for balancing up to 2800MW of wind generation in the Western Cape. This effectively reduces the power import via the Cape Corridor and can even lead to power export from the Western Cape into the rest of the system via the Cape Corridor under low load – high wind conditions as shown in Figure 14. Grid Integration of Wind Energy in the Western Cape 35 238,53 MW -344,31 Mvar Hydra-Luckhof 400_3 (Perseus 3) 25,45 % Hydra-Luckhof (Beta) 400_1 21,99 % Hydra-Luckhof 400_2 (Perseus 2) 25,36 % Beta-Hydra 765_2 6,42 % 4 Stage 3: Feasibility Studies for up to 2800MW of Wind Generation in the Western Cape 250,16 MW 225,01 MW 253,87 MW -169,79 Mvar -134,50 Mvar -166,20 Mvar 967,56 MW -814,79 Mvar Hydra -458,95 MW 84,74 Mvar -452,87 MW 81,11 Mvar 452,91 MW -81,47 Mvar Hydra-Victoria 400_1 S2 .. 39,90 % -452,91 MW 81,47 Mvar -1912,25 MW 407,80 Mvar 362,80 MW -88,77 Mvar 373,31 MW -94,58 Mvar 736,12 MW -183,35 Mvar Hydra-Poseidon 400_2 32,30 % Hydra-Victoria 400_2 40,47 % -635,08 MW 147,56 Mvar Hydra-Victoria 400_1 S1 21,43 % -365,36 MW 94,39 Mvar Hydra-Poseidon 400_1 31,32 % Figure 14: Hydra substation under low load - high wind conditions 4.3 Results of Load Flow Studies For verifying that the ESKOM transmission grid could take up to 2800MW of wind generation without any major network upgrade (new transmission line), load flow calculations under base case an n-1 conditions have been carried out The focus of these studies has been the transmission system in the Cape. Potential issues in the network outside the Cape have been monitored but not analyzed in detail. Particularly operational issues resulting from situations, in which power is exported from the Cape Corridor, have not been part of the scope of these studies. The results of the load flow and n-1 studies that have been carried out for all scenarios according to Table 7 show that no thermal overload or voltage problems have to be expected and that a secure system operation with up to 2800MW of wind generation will not cause any grid congestion at the main transmission levels. 4.4 Additional Additional Considerations Besides grid congestions, there are many other aspects that have to be considered when evaluating the feasibility of up to 2800MW of wind generation in the Western Cape, which are mainly related to system operation. Grid Integration of Wind Energy in the Western Cape 36 4 Stage 3: Feasibility Studies for up to 2800MW of Wind Generation in the Western Cape These aspects mainly relate to: • Balancing of wind variations • Reactive power/voltage control • System stability. Even if none of these aspects have actually been analyzed as part of the presented studies, some general aspects should be highlighted, which show that it is indeed very likely that also none of these aspects will finally question the feasibility of up to 2800MW of wind generation in the Western Cape. 4.4.1 Balancing of Wind Variations In the Western Cape there is a total of around 2000 MW of gas turbine generators installed, which are currently used for balancing peak loads and for backing up the outage of the Koeberg nuclear power plant units. These gas turbine generators are peak load power plants with excellent dynamic properties (fast ramp-up/rampdown times, fast start-up times etc.). Technically, these gas turbine generators can be very useful for balancing the variations of wind generation in the Cape. As soon as the new 765kV line running into the Cape will be available (probably after 2013), there will other, potentially less expensive options for balancing wind fluctuations in the Cape using power plants outside the Cape. Additionally, there are around 400MW of pump storage capacity installed at Palmiet, which can additionally be used for balancing wind variations. 4.4.2 Reactive Reactive Power/Voltage Control A high number of gas turbine generators in the Western Cape is equipped with clutches and can be operated in synchronous condenser (SCO) mode. This means that the full reactive power/voltage control capability of those synchronous generators is also available under low load/high wind hours. The steady state studies that have been carried out for the integration of up to 2800MW of wind generation in the Cape don’t identify any need for additional reactive power-control capability in the Cape. However, dynamic studies are required for verifying that this also applies to short-term voltage stability aspects. The impact of wind generation export to the rest of the South African power system has not been part of the scope of these studies and it is strongly advisable to study those cases in more detail for identifying the impact of Cape-export scenarios on voltage and other relevant aspects of northern part of the South African transmission grid. Grid Integration of Wind Energy in the Western Cape 37 4 Stage 3: Feasibility Studies for up to 2800MW of Wind Generation in the Western Cape 4.4.3 System Stability Particularly during high import scenarios, the Cape transmission network is prone to voltage stability problems. With the addition of wind generation in the Cape however, power imports will be reduced during high wind hours and voltage stability problems will rather be reduced. In situations, in which the Cape will export power to the rest of the system (high wind – low load), it is very much unlikely that transient stability issues will represent a considerable constraints because modern, variable speed wind generators are not sensitive to any kind of rotor angle stability problem. 4.5 Stage 3: Summary High level feasibility studies for analyzing the impact of up to 2800MW of wind generation in the Western Cape on the 400kV transmission grid have been carried out. The results show that no considerable impact on the transmission grid has to be expected and that it will be possible to accommodate such a high level of wind generation without any major upgrades of the 400kV transmission grid. At the same time it is understood that the transmission capacity of subtransmission and distribution grids (voltage levels <=132kV) will be limited in some cases and that major network upgrades at these lower voltage levels will be required. For confirming the results of these initial feasibility studies, additional, more detailed studies will be required; especially on basis of well approved low load scenarios. Besides this, studies looking at operational aspects such as additional spinning reserve requirements, stability aspects, dynamic performance requirements for peak load power plants etc. have to be carried out for confirming the feasibility of up to 2800MW of wind generation in the Cape. However, many general aspects of the Western Cape system, such as • the availability of peak-load power plants (gas turbine) in the Cape; • generators allowing for synchronous condenser operation and • the fact that wind generation in the Cape will reduce power imports into the Cape can lead to the conclusion that the Western Cape transmission system is generally very well suited for the integration of high amounts of wind generation even if some of these aspects still have to be confirmed by additional, more detailed studies. Grid Integration of Wind Energy in the Western Cape 38 5 Conclusions and Recommendations 5 Conclusions and Recommendations The studies presented in this report describe general methodologies and approaches for studying the integration of wind generation in subtransmission and transmission networks by means of three different examples: • Stage 1: Connection of a 150MW wind farm to a 132kV subtransmission grid • Stage 2: Connection of up to 750MW of wind farms to the 400kV transmission grid. • Stage 3: Feasibility studies about the integration of up to 2800MW of wind generation into the Western Cape transmission system. The results of these studies highlight a number of aspects that have to be considered when studying the grid impact of wind generation in South Africa and show the general feasibility of the integration of up to 2800MW of wind generation in the Western Cape. For confirming the results of these feasibility studies, a number of additional studies will be required, as there are: • Load flow and n-1 studies with additional scenarios, particularly low load scenarios • Stability studies under various different operating conditions. For these studies, appropriate dynamic wind generator models are required. • Wind farm connection studies for each individual connection application • Studies about the operation of the ESKOM transmission system under scenarios in which the Cape exports power to the rest of the system. • Studies related to the expected total power variations of wind generation (variations, ramp-up and ramp-down speeds) for identifying additional reserve requirements have to be carried out. • Studies considering other renewable sources • Studies considering wind energy and other renewable energy sources outside the Western Cape Province. Besides these additional study requirements, the fact that • The Western Cape is an area having rather an import than an export problem under the present situation. • There are a high number of fast peak-load power plants and pump storage schemes available in the Western Cape with which it will be possible to balance wind variations. Grid Integration of Wind Energy in the Western Cape 39 5 Conclusions and Recommendations • Some of the gas turbine generators in the Western Cape can operate in synchronous condenser mode lead to the conclusion that the Western Cape transmission grid is very well suited for the integration of high amounts of wind generation. With regard to particular technical requirements of wind generators to be installed in South Africa, the following general recommendations can be made: • Frequency and voltage range of operation should be defined analogously to the existing South African practice. • A reactive power range at the grid connection point of (+/- 0,33 p.u./Prated, cos(phi)>0,95) under full load and partial load conditions will be sufficient. It is recommended to decide on a case-by-case basis, whether reactive power control capability during low and no wind hours will be required. • For wind farms that will be connected to subtransmission and distribution levels, operation with constant power factory will be sufficient. If required, an active power dependent reactive power characteristic should be foreseen (see section 2.6). • Wind farms that will be connected to the main transmission level should have the technical capability for controlling the reactive power or the voltage (feed-back voltage control) at the grid connection point. The required dynamic performance of such voltage control has to be identified with the help of additional, dynamic studies. • Because of the overall amount of planned wind generation in the Cape, all wind generators should be equipped with fault ride-through (FRT) capability for avoiding WTG trips in case of line faults. For standardizing the technical characteristics of wind generators in South Africa, it is recommended to extend the South African grid code by Connection Conditions for wind generation. These Connection Conditions should consider existing standards with respect to the connection of thermal and hydro power plants and make provision of the particular technical characteristics of wind generators. Grid Integration of Wind Energy in the Western Cape 40 6 Referenced Documents 6 Referenced Documents [1] ESKOM – Riaan Smit. Grid Integration Workshop. Working Document. [2] ESKOM. Wind Generation Sites. (file: Wind Gen Sites 20090327.xls) [3] M. Pöller: TERNA- Project Workshop, (file: WorkshopSummary.ppt) Grid Integration of Wind Energy in the Western Cape 41 ANNEXES List of Annexes Annexes • Annex A-1: PV-curves of Stage 1 – Studies • Annex A-2: Results of Contingency Analysis of Stage 2 – Studies • Annex A-3: Results of Contingency Analysis of Stage 3 – Studies Grid Integration of Wind Energy in the Western Cape 42