Eman A. Awad1, Ebrahim A. Badran 1,*, and Fathi M. H. Youssef J. Electrical Systems 10-4 (2014): 431-444 1 Regular paper Mitigation of Temporary Overvoltages in Weak Grids Connected to DFIG-based Wind Farms JES Journal of Electrical Systems The level of temporary overvoltage (TOV) has a strong effect on wind turbine power system reliability. TOV magnitude depends up on the state at which the circuit breaker contacts close. This paper investigates the mitigation of TOV in weak grids connected to DFIG-based wind farms. Preinsertion resistor (PIR), Controlled switching of circuit breaker, Shunt reactor, and Surge arresters are applied as protective devices to mitigate TOVs under various operation conditions such as symmetrical or unsymmetrical switching of circuit breaker. Alternating Transient Program (ATP) is used in this study to simulate of the investigated system and the elements of mitigation devices. Keywords: Temporary Overvoltage, Wind Turbine, DFIG, ATP Article history: Received 13 April 2014, Received in revised form 4 September 2014, Accepted 10 October 2014 1. Introduction Weak grids are usually found in more remote places where the feeders are long and operated at a medium voltage level [1]. Isolated wind farms away from the main grids are considered weak grids because of long feeders [2]. Temporary overvoltages (TOVs) are one of the most frequently encountred problems during switching procedures in wind turbine power system [3]. TOV has a frequency near to a harmonic of the power frequency, therefore, TOV also called power frequency overvoltage [4]. TOVs can last for over a hundred cycles and have slowly decaying amplitude. They can originate from line/ cable or transformer energisation, faults, load rejection and ferrorresonance [5]. The magnitude and shape of TOVs vary with the system parameters and network configuration. Even with the same system parameters and network configuration, TOVs are highly dependent on the characteristics of the circuit breaker operation and the point-on-wave where the switching operation takes place [3]. Circuit breaker plays the main role in changing the condition of operations. TOV magnitude depends up on the state at which the circuit breaker contacts close [4]. When a transmission line/cable is energized by closing the circuit breaker symmetrically, all the circuit breaker poles attempts to close at the same instant of the voltage wave, TOVs are generated not only on the transmission system but also in the supply network [6]. On the other hand, TOVs magnitude is increased by the virtue of the fact that the three poles of the circuit breaker do not close symmetrically [4]. Unsymmetrically switching as in the case of stack pole on the circuit breaker can result in ferroresonance. Ferroresonance appear due to the interaction between the feeder cable capacitance and the magnetic cores of generation unit transformers, particularly when the Wind Turbine Generators (WTGs) are not connected. Ferroresonance produces voltage several times normal magnitude on the open phases [5]. TOVs are a critical factor in wind plant insulation coordinates. Proper insulation * Corresponding author: Ebrahim A. Badran, Electrical Engineering Department, Faculty of Engineering, Mansoura University, Egypt, email: ebadran@mans.edu.eg; eabadran@ieee.org 1 Electrical Engineering Department, Faculty of Engineering, Mansoura University, Egypt. Copyright © JES 2014 on-line : journal/esrgroups.org/jes Eman A. Awad et al. Mitigation of Temporary Overvoltages in Weak Grids... coordination is important to achieve expected life from wind plant equipment [7]. Pre-insertion resistor (PIR), controlled switching of circuit breaker, shunt reactor, and surge arresters are used as protective devices to mitigate TOVs under various operation conditions such as symmetrical or unsymmetrical switching of circuit breaker [8, 9]. The use of doubly-fed induction generator (DFIG) is receiving an increased attention for wind generation purposes [10, 11]. DFIG is basically a standard, wound rotor induction machine with its stator windings directly connected to the grid and its rotor windings connected to the grid by electronic converters through slip rings [12]. DFIG is one of the most commonly used technologies nowadays, as these offer advantages such as the decoupled control of active and reactive powers and maximum power tracking. These capabilities are possible due to the power electronic converters used in this type of generator [13, 14]. In this paper, TOVs in weak grids connected to DFIG-based wind farms are investigated. Also, TOV mitigation methods are introduced, applied and compared. ATP is used for simulating the test power system, the connected DFIG-based wind farm, and the mitigation devices [15]. 2. The Investigated Offshore Wind Farm 2.1 Description of the Wind Farm The investigated wind farm consists of 72 wind turbines (WTs) with a rated power of 2.3 MW. The turbines are arranged in a parallelogram, formed by eight rows with nine WTs each, as shown in Fig. 1 [16, 17]. The WTs are connected in rows of 36 kV submarine cables. Each row is then connected to the platform by one root cable. The park transformer (132/33/33 kV) is in the central position. Each feeder is connected by a vacuum circuit breaker, followed by the root cable. There are eight rows, from A to H, where A, B, C and D are connected to one MV winding, and E, F, G, and H to the other medium voltage (MV) winding [16]. The submarine cable is connected on the bottom of each WT where the armor and the shield of the cables are grounded. Then the transformer (2.5 MVA, 33/0.69 kV) is connected via switch disconnector-fuse on the MV. The WTs are interconnected with 36 kV cables of 505 m of length. Furthermore, the high voltage (HV) grid (132 kV) sea cable (10.5 km) and land cable (18.3 km) are included in the model [17]. Fig. 1: The Investigated Offshore Wind Farm [17] 432 J. Electrical Systems 10-4 (2014) 431-444 2.2 Modeling of the Wind Farm ATP is used for modeling the components of the investigated offshore wind farm as illustrated in this section. Fig. 2 shows the ATP model of the investigated offshore wind farm. In this model, it is shown that: 1. The grid is modeled as a voltage source. 2. The HV, 132 kV, three-phase single-core sea and land cables are modeled as symmetrical, distributed parameter and lumped resistance models. 3. The wind farm transformers are modeled using HYBRID transformer model. 4. The rows B, C, and D are modeled as one three-phase single-core cables because they are connected in parallel. Also, the rows E, F, G, and H are modeled in the same way. 5. Only row A is modeled in details. Fig. 2 shows the nine identical wind turbine transformers (WTTs) in row A. To reduce the simulation time, the complexity of the wind farm model is reduced by equivalent models. The wind turbine generators (WTGs) in the wind farm are aggregated into a three separate equivalent model and the rest of the turbines in row A are modeled as very light loads connect on the low voltage (LV) side of the WTTs. The light load is modeled as a high resistance of 1200 Ω. Therefore, the nine WTTs of row A are considered as transformers under no-load. WTGs are considered as operating on an equivalent internal electrical network provided that the incoming wind velocity is identical or similar on all the WTs [17]. Wind Turbine #A9 XFMR V M3 Y I Wind Turbine #A8 XFMR V XFMR V XFMR V XFMR V XFMR V XFMR V XFMR V Y I Wind Turbine #A7 Y I Wind Turbine #A6 Y I Wind Turbine #A5 Y I Wind Turbine #A4 Y I Wind Turbine #A3 Y GROUP groupdef I Wind Turbine #A2 Y GROUP groupdef Root E,F,G,H LCC I XFMR M2 GROUP groupdef Wind Farm Transformer Land Cable XFMR Submarine Cable Wind Turbine #A1 Y V M2 LCC V M1 V V Y LCC Switching Point V Root B,C,D Sea Cable Wind Turbine Transformer Fig. 2: The ATP model of the investigated offshore wind farm 433 Eman A. Awad et al. Mitigation of Temporary Overvoltages in Weak Grids... 2.3- Modeling of Cables and Transformers The MV single-core submarine cables are the most distinctive electric component in the offshore wind farms. The 33 kV three-phase single-core submarine cables connect between the HV sides of the WTTs. The geometric configuration of the submarine cables which is calculated based on the power transferred through them [17], and the cable parameters are given in Table 1. Table 1: Dimensions of the 33 kV Single-Core submarine Cable Cross section of conductor [mm]2 Diameter of conductor [mm] Insulation thickness [mm] Diameter over insulation [mm] Cross section of screen [mm]2 Outer diameter of cable [mm] 240.0 18.1 8.0 35.7 35.0 45.0 In submarine cables, the armor is usually quite thick. Therefore, it is assumed in this study that, an armor of 5 mm steel wires thickness and a 5 mm outer insulation thickness are incorporated into the three-phase single-core submarine cable design. So, the overall outer diameter of the medium voltage single-core submarine cable is 65 mm. The MV (33 kV) singlecore submarine cables are modeled using the frequency dependent LCC model [15]. This model represents the frequency dependence of single-core submarine cable parameters so this model is much recommended for the electromagnetic transient studies [15]. The sea and land cables are modeled using the three phase Clark model [15] to avoid the numerical errors due to the long length of the HV cables. The model parameters are calculated from the cable dimensions and its materials using distributed parameters of three phase transposed model at 50 Hz. Both dimensions and materials of the HV sea and land cables are taken from [18]. Table 2 gives the positive and the zero sequence resistances, the inductive reactance and the capacitive reactance of the 132 kV land and sea cables, respectively. Both wind farm transformers and off-shore wind farm transformer are modeled using the HYBIRD transformer model. The wind turbine transformers of row A are modeled using three phase, two windings, HYBIRD model. The wind farm transformer is modeled as three winding transformer using the HYBIRD model, which is suitable for low and medium frequency transient studies [19, 20]. Table 3 gives the data required for transformers modeling. Table 2: The 132 kV Single Core Cables Data The 18.3 km/ 132 kV land cable (equivalent PI section model) +ve sequence resistance +ve sequence inductive reactance +ve sequence capacitive reactance zero sequence resistance zero sequence inductive reactance zero sequence capacitive reactance 0.087 [m ohm/m] 0.123 [m ohm/m] 9.092 [M ohm*m] 0.1865 [m ohm/m] 0.0551 [m ohm/m] 9.0915 [M ohm*m] The 10.5 km / 132 kV sea cable (equivalent PI section model) +ve sequence resistance +ve sequence inductive reactance +ve sequence capacitive reactance zero sequence resistance zero sequence inductive reactance zero sequence capacitive reactance 0.0864 [m ohm/m] 0.123 [m ohm/m] 9.0915 [M ohm*m] 0.1827 [m ohm/m] 0.0619 [m ohm/m] 9.0915 [M ohm*m] 2.4 Modeling of DFIG-based Wind Turbine A complete wind turbine model is used in this study [21]. The model includes the wind speed model, the aerodynamic model of the wind turbine, the mechanical model of the 434 J. Electrical Systems 10-4 (2014) 431-444 transmission system and models of the electrical components. The induction generator, PWM (Pulse Width Modulated) voltage source converters, transformers, and the control and supervisory system are modeled in details [21]. Fig. 3 illustrates the DFIG-based wind turbine model in ATP [21]. This model is used for accurate simulation of the DFIG-based wind farm. Also, Table 4 summarizes the data used to parameterize the DFIG. Table 3: Wind Farm and WT Transformers Data Wind Turbine Transformers Model Connection method Voltage Rated power Leakage reactance Copper losses No-load losses Y/∆ 0.69/33.0 [kV] 2.5 [MVA] 0.082573 [pu] 0.0084 [pu] 0.0022 [pu] Wind Farm Transformer Model Connection method Voltage Rated power Leakage reactance Copper losses No-load losses ∆/Y/∆ 33.0/132.0/33.0 [kV] 180.0 [MVA] 0.1 [pu] 0.004 [pu] 0.001 [pu] Table 4: Parameters of the DFIG-based wind turbine xxx8 xxx9 xxx10 xxx3 xxx45xxx46 xxx11 Turn-off snubb er xxx3 xxx46 xxx43 xxx3 U xxx18xxx3 SAT xxx7 xxx1 xxx43 xxx2 I V xxx20 xxx1 xxx2 + xxx19 V xxx1 xxx1 I xxx1 Switching xxx2 device (e.g. IGBT) with xxx6 conduction characteristic xxx3 Value 0.0025 Ω 0.097 mH 3 mH 0.0083 Ω 0.115 mH 4 2.400 Kg .m2 6.500 KVA I Parameter Stator resistance Stator leakage inductance Magnetization inductance Rotor resistance Rotor leakage inductance Electrical turn ratio Moment of inertia (inertia constant = 2 s.) Rated apparent power xxx47 xxx4 xxx3 xxx3 xxx5 xxx3 xxx5 xxx17 xxx16 xxx15 xxx4 xxx5 xxx14 xxx4 xxx13 xxx4 Crowbar xxx5 V xxx24 V xxx21 xxx21 xxx26 xxx33 xxx29 xxx24 I xxx25 IM xxx38 Power xxx35 measurement I xxx26 ωxxx29xxx28 V xxx34 xxx37 V xxx38 xxx27 I xxx29 xxx28 I xxx22 xxx5 V xxx32 xxx2 xxx36 xxx36 xxx35 xxx20 xxx44 Freewheeling diode (with characteristic) xxx2 xxx32xxx30 xxx29 xxx12 xxx4 xxx29 xxx30 xxx28 xxx31 TACS/MODELS controllable external torque (e.g. wind) Electrical network equivalent for the mechanical system Fig. 3: The DFIG-based wind turbine model in ATP [21] 435 Eman A. Awad et al. Mitigation of Temporary Overvoltages in Weak Grids... 3. Temporary Overvoltage Mitigation Methods Traditionally, the TOVs are limited through the adoption of PIR in the line circuit breakers. Another method to reduce TOV is the synchronous switching of circuit breakers. The installation of shunt reactors is also used to mitigate TOV. Furthermore, the surge arresters are used to limit the TOVs. Pre-Insertion Resistor (PIR): PIR is an effective mitigation method, although it presents a decreasing acceptance due to the high cost of implementation and maintenance [8]. The closing resistors are inserted in series with the cable, normally being short circuited after 10 ms, thereby damping TOV. In the present case, a 500 Ω resistor, with an insertion time equals the switching time, is installed. Synchronized Circuit Breakers: By means of switch synchronized controllers, both energizing and de-energizing operations can be controlled with regard to the point-on-wave position to mitigate harmful transients [6]. The suitable instant for controlled switching is the time in which the voltage across the circuit breaker contacts for each phase is zero and the predicted time span between the closing instant of the first and the last pole is as small as possible [22]. In this study, the closing order is given when the voltage of each phase crosses consecutives zero. Shunt Reactor: shunt reactor is used to damp TOVs and keep the system voltage within the permissible limits [23]. In the present case, the shunt reactor is modeled, as in many studies, by a simple lumped inductor (0.07 mH) with a series resistance (5 Ω). A parallel resistance (200 Ω) is added for realistic high frequency damping [24]. A shunt reactor is added nearby the switching point. Surge Arrester: Surge arrester provides a temporal path to earth which the superfluous charge is removed from the system [25]. With the information of volt-ampere characteristic of surge arrester, equivalent model of surge arrester is presented in [26, 27]. This model is used in this investigation. 4. Mitigation of Energization TOVs Generated due to Symmetrical Switching Operations The TOVs generated due to symmetrical switching opertions in weak grids connected to DFIG-based wind farms are investigated. The TOV due to the energization of row A is studied and mitigated; this is carried out by the symmetrical closing the three phases of the circuit breaker at the platform of row A. The symmetrical switching operation is applied at the voltage peak by closing the circuit breaker phases when the voltage of each phase crosses consecutives 90o. The three-phase voltage waveforms caused by the switching are investigated on both the HV (33.0 kV) side and the LV (0.69 kV) side of the WTTs of row A. Figs. 4 show the maximum TOVs at both the HV side and the LV side of the first WTT, respectively, with and without using of mitigation methods. Due to using PIR, the TOV at the HV side of the WTT of row A is reduced from 1.5266 pu (29.081 kV) to 1.108 pu (21.11 kV) and from 1.576 pu (1.087 kV) to 1.1965 pu (0.826 kV) at the LV side. The TOV due to using controlled switching of the circuit breaker at the HV side of the WTT of row A which is reduced from 1.5266 pu (29.081 kV) to 0.9929 pu (18.915 kV) and from 1.576 pu (1.087 kV) to 1.124 pu (0.7758 kV) at the LV side. Using of shunt reactor reduces the TOV at the HV side of the WTTs of row A from 1.5266 pu (29.081 kV) to 1.305 pu (24.859 kV) and at the LV side is reduced from 1.576 pu (1.087 kV) to 1.3047 pu (0.90024 kV). Also, due to using the surge arrester, the TOV at the HV side of the WTTs of row A is reduced from 1.5266 pu (29.081 kV) to 1.422 pu (27.087 kV) and at the LV side from 1.576 pu (1.087 kV) to 1.1266 pu (0.77735 kV). 436 J. Electrical Systems 10-4 (2014) 431-444 It can be concluded that the PIR and the controlled switching of circuit breaker introduce a better mitigation performance. They reduce the TOVs to acceptable values (around 1.0 pu). PIR and the controlled switching of circuit breaker have better mitigation effect than the shunt reactor and the surge arrestor. Fig. 4: TOVs at HV and LV sides of the first WTTs of row A with and without mitigation methods 5. Investigation of Ferroresonance TOVs Generated due to Unsymmetrical Switching Operations The ferroresonance TOVs due to unsymmetrical switching operations during deenergization procedures are investigated. The unsymmetrical switching operations are performed at two different wind turbines, the first and the last wind turbines in row A, in the offshore wind farm. The unsymmetrical switching is carried out by the de-energization of both phases B, and C of HV or LV sides of WTTs. The effect of ferroresonance on DFIG rotor angular speed and the turbine output voltage is investigated. Figs. 5 and 6 show the ferroresonance TOVs effect on DFIG rotor angular speed, 437 Eman A. Awad et al. Mitigation of Temporary Overvoltages in Weak Grids... and the turbine output voltage of the first and last WTs, respectively. When the switching is applied at HV side of the furthest (last) WTT, the rotor angular speed lasts a long time transient, turning into a pulsating speed centered on the steady state speed. This behavior differs from that of the first wind turbine; the rotor angular speed exposes a short time transient. When the switching is applied at LV side of the first and the ninth WTTs, the rotor angular speed increase rapidly. When the switching is applied at LV side of the first or the last WTTs, the switching causes the turbine output voltage in the open phases to increase equal six times the nominal voltage of the turbine. This overvoltage is due to the interaction between the feeder cable capacitance and the magnetic cores of WTG unit transformers, particularly when the transformer is still connected to the wind farm while the WTGs are not connected. However, when the switching is applied at HV side of the first or the last WTTs, there is a slight increase in the output voltage. It is seen from the exceeding results that the unsymmetrical de-energization at the LV side of WTT is, by all means, much worse than that by the unsymmetrical de-energization at the HV side of WTT. 438 J. Electrical Systems 10-4 (2014) 431-444 Fig. 5: Ferroresonance effect on DFIG rotor angular speed and the turbine output voltage of the first WT. Fig. 6: Ferroresonance effect on DFIG rotor angular speed and the turbine output voltage of the last WT 6. Mitigation of Ferroresonance TOVs Generated due to Unsymmetrical Switching Operations PIR, controlled switching of circuit breaker, shunt reactors, and surge arresters are used in this study to mitigate the effect of ferroresonance TOVs, especially when the switching is applied at LV side of WTTs, as it is the worst case. Figs. 7 and 8 show the maximum ferroresonance overvoltage at LV side of the first and the last wind turbine transformers, respectively, with and without using mitigation methods. Due to using PIR, the ferroresonance TOV at LV side of the first WTT is reduced from 6.0674 pu (4186.5 V) to 1.0907 pu (752.58 V). The ferroresonance TOV due to using controlled switching of the circuit breaker is reduced from 6.0674 pu (4186.5 V) to 0.974 pu 439 Eman A. Awad et al. Mitigation of Temporary Overvoltages in Weak Grids... (672.08 V). Using of shunt reactor reduces the ferroresonance TOV from 6.0674 pu (4186.5 V) to 1.3482 pu (930.28 V). Due to using surge arrester, the ferroresonance TOV is reduced from 6.0674 pu (4186.5 V) to 2.3538 pu (1624.1 V). 440 J. Electrical Systems 10-4 (2014) 431-444 Fig. 7: The maximum ferroresonance TOV at the first WTT with and without mitigation methods 441 Eman A. Awad et al. Mitigation of Temporary Overvoltages in Weak Grids... Fig. 8: The maximum ferroresonance TOV at the last WTT with and without mitigation methods Due to using PIR, the ferroresonance TOV at LV side of the last WTT is reduced from 6.0465 pu (4172.1 V) to 1.0178 pu (702.3 V). The ferroresonance TOV due to using controlled switching of the circuit breaker is reduced from 6.0465 pu (4172.1 V) to 0.996 pu (687.3 V). Using of shunt reactor reduces the ferroresonance TOV from 6.0465 pu (4172.1 V) to 1.3074 pu (902.1 V). Due to using surge arrester, the ferroresonance TOV is reduced from 6.0465 pu (4172.1 V) to 2.497 pu (1722.9 V). PIR and controlled switching of circuit breaker show a better mitigation performance than the other investigated methods. The reduction of TOVs due to shunt reactor is remarkable, but still lesser than the reduction values achieved by PIR and controlled switching of circuit breaker. Using surge arrester to reduce the ferroresonance TOV magnitude has limited influence comparing with the other mitigation methods. 7. Conclusion In this paper the mitigation of TOVs in weak grids connected to DFIG-based wind farms is investigated. The DFIG-based wind turbine model in ATP is used for the simulation of the wind farm. A wind farm which consists of 72 wind turbines is used for this analysis. In order to investigate the mitigation of TOVs due to the different symmetrical and unsymmetrical switching scenarios four different mitigation methods have been used and compared by each other. These are the pre-insertion resistor (PIR), the controlled switching of circuit breaker, the shunt reactor and the surge arrestor method. ATP is used in this study to simulate the investigated system and the mitigation devices. The results show that the TOVs due to the unsymmetrical switching are higher than those due to the symmetrical switching. And those TOVs due to the unsymmetrical switching at the LV side of the wind turbine transformer is higher than those at the HV side due to the transformer interaction in the circuit (ferroresonance effect). The comparison between the different mitigation methods show that the controlled switching of the circuit breaker as well as the PIR method are the best mitigation means to the TOVs. It is recommended by the study of TOVs in wind farms and their mitigation methods to take care of the TOVs caused due to ferroresonance unsymmetrical switching cases and to employ the controlled switching of circuit breakers as far as possible. REFERNCES [1] H. Bindner, “Power Control for Wind Turbines in Weak Grids: Concepts Development”, Risø National Laboratory, Roskilde, March 1999. [2] M. Rashed, S. Abulanwar, F. Youssef, “H∞ Robust Controller for a Long VSC-HVDC Link Connected to a Weak Grid”, Mansoura Engineering Journal, Vol. 35, No.1, March 2010, pp.E.53E.60. 442 J. Electrical Systems 10-4 (2014) 431-444 [3] D. Thukaram, H. Khincha, and S. Khandelwa, “Estimation of Switching Transient Peak Overvoltages During Transmission Line Energization using Artificial Neural Network”, Electric Power Systems Research, Vol. 76, 2006, pp. 259–269. [4] Cigre Working Group, “Switching Overvoltage in EHV and UHV systems with Special Reference to Closing and Reclosing Transmission Lines”, Electra, Vol 30, 1973, pp.70-122. [5] R. King, F. Moore, N. Jenkins, A. Haddad, H. Griffiths, and M. Osborne, “Switching Transients in Offshore Wind Farms – Impact on the Offshore and Onshore Networks”, International Conference on Power Systems Transients, IPST, Delft, The Netherlands, June 14-17, 2011. [6] M. S. Pasand, M. R. Dadashzadeh, and M. Khodayar, “Limitation of Transmission Line Switching Overvoltages using Switchsync Relays”, International Conference on Power Systems Transients, IPST’05, Montreal, Canada, June 19-23, 2005 Paper No. 87. [7] IEEE PES Wind Plant Collector System Design Working Group, “Wind Power Plant Grounding, Overvoltage Protection, and Insulation Coordination”, Power & Energy Society General Meeting, PES'09, Alberta, Canada, July 26-30, 2009. [8] P. Mestas and M. Tavares, “Comparative Analysis of Techniques for Control of Switching Overvoltage during Transmission Lines Energization”, International Conference on Power System Transients, IPST’07, Lyon, France, June 4-6, 2007, Paper No.116 [9] H. Seyedi, M. Sanaye-Pasand, and M. R. Dadashzadeh, "Application of Transmission Line Surge Arresters to Reduce Switching Overvoltages", International Conference on Power System Transients, IPST’05, Montreal, Canada, June 19-23, 2005, Paper No. 082 [10] A. Tapia, G. Tapia, J. Ostolaza, and J. Sáenz, “Modeling and Control of a Wind Turbine Driven Doubly Fed Induction Generator”, IEEE Transactions On Energy Conversion, Vol. 18, No. 2, June 2003. [11] Y. Amirat, M. E. H. Benbouzid, B. Bensaker, and R. Wamkeue, "Generators for Wind Energy Conversion Systems: State of the Art and Coming Attractions", Journal of Electrical Systems, Vol. 3, No.1, 2007, pp. 26-38. [12] B. Babypriya and R. Anita, “Modeling, Simulation and Analysis of Doubly Fed Induction Generator for Wind Turbines”, Journal of Electrical Engineering, Vol. 60, No. 2, 2009, pp.79–85. [13] J. C. Muñoz, and C. A. Cañizares, “Comparative Stability Analysis of DFIG-based Wind Farms and Conventional Synchronous Generators”, Power Systems Conference and Exposition, PSCE, Phoenix, USA, 20-23 March 2011. [14] A. F. Zobaa, “Technology of VAR Compensators for Induction Generator Application in Wind Energy Conversion Systems", Journal of Electrical Systems, Vol. 2, No. 3, 2006, pp.172-184. [15] L. Prikler and H. K. Høidalen, ”ATPDRAW version 5.6 Users' Manual”, November 2009. [16] I. A. Aristi, "Modeling of Switching Transients in Nysted Offshore Wind Farm and a Comparison with Measurements", M.Sc. Thesis, Technical University of Denmark, Denmark, June 2008. [17] E. A. Badran, M. M. Rizk, and M. H. Abdel-Rahman, “Investigation of Submarine Cable Parameters Impact on Energization Transients in Offshore Wind Farms”, International Conference on Power Systems Transients, IPST, Delft, The Netherlands, June 14-17, 2011, Paper No. 182. [18] “ABB XLPE Cables User’s Guide”, Technical documentation, available at www.abb.com. [19] N. Chiesa,” Power Transformer Modeling for Inrush Current Calculation”, Ph.D., Norwegian University of Science and Technology, Trondheim, Norwege, June 2010. [20] H. Høidalen, B. Mork, F. Gonzalez, D. Ishchenko, and N. Chiesa, "Implementation and Verification of the HYBIRD Transformer Model in ATPDraw”, International Conference on Power System Transients, IPST’07, Lyon, France, June 4-7, 2007. [21] P. La Seta, “Modeling and Control of Wind Turbines Based on Doubly-Fed Induction Generators (DFIG)”, EEUG Meeting 2009, TU Delft, the Netherlands, 2009. [22] K. Dantas, W. Neves, D. Fernandes, G. Cardoso, and L. Fonseca, “On Applying Controlled Switching to Transmission Lines: Case Studies”, The International Conference on Power Systems Transients, IPST09, Kyoto, Japan, June 3-6, 2009. [23] S. M. Elkhodary and A. S. Abdel-Munem, “New Proposed Method of Damping Temporary Overvoltages on Power System Interconnections”, Journal of American Science, Vol. 6, No. 11, 2010, pp. 336-342. [24] IEEE Modeling and Analysis of System Transients Working Group, “Modeling Guidelines for Switching Transients”, IEEE PES Switching Transients Task Force, August, 2009. 443 Eman A. Awad et al. Mitigation of Temporary Overvoltages in Weak Grids... [25] H. Xue and M. Popov, ”Analysis of Switching Transient Overvoltage in the Power System of Floating Production Storage and Offloading Vessel”, International Conference on Power Systems Transients, IPST, Vancouver, Canada, July 18-20, 2013. [26] A. Bayadi, N. Harid, K. Zehar, and S. Belkhiat, ”Simulation of Metal Oxide Surge Arrester Dynamic Behavior Under Fast Transients”, The International Conference on Power Systems Transients, IPST, 2003, New Orleans, USA. [27] Pablo M. Miguel, "Comparison of Surge Arrester Models", IEEE Transactions on Power Delivery, Vol. 29, No. 1, February 2014, pp. 21-28. 444