DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 PART 1 GENERAL 1.1 COMMISSIONING INTENT Page 1 of 30 .1 Undertake commissioning to bring the facility to a fully operational state and free of deficiencies in the most effective and timely manner available. .2 Commissioning incorporates inspection and quality assurance activities as construction progresses, including start up and demonstration, performance verification, fine tuning, and operator training. .3 Bear all costs associated with the required personnel and test equipment as outlined in specification sections and all costs with organizing and managing the activities of the applicable subtrades as identified in this section. .4 Fully document all tests and inspections performed during the construction, at start up, and during performance verification and fine tuning. Incorporate into final commissioning documentation. .5 Provide direct training to designated staff responsible for the operation and maintenance of the building equipment and systems. 1.2 RELATED SECTIONS .1 Section 01450 - Quality Control .2 Section 01740 - Cleaning .3 Section 01770 - Closeout Procedures .4 Section 01780 -Closeout Submittals .5 Divisions 2-14 .6 Division 15 - Mechanical .7 Division 16 - Electrical 1.3 QUALITY ASSURANCE .1 .Ensure qualified trades persons, certified testing agencies and/or factory authorized and approved by the Commissioning Team Leader participate in commissioning tasks. .2 Submit the names of all personnel for approval by the Commissioning Team Leader. Designate who has managerial responsibilities for coordination of entire testing, adjusting and balancing. .3 Submit documentation to confirm personnel compliance with quality assurance provision. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 1.4 Page 2 of 30 CONSTRUCTION INSPECTIONS AND QUALITY ASSURANCE .1 Complete inspection and verification activities as required by the specifications as construction progresses. This includes those activities that are necessary to ensure that the project is substantially complete to permit the execution of the commissioning process for the project. .2 Complete commissioning documentation manuals. Manuals will be provided to the Contractor by the Engineer/Architect during the construction stage. .3 Take responsibility to: .1 .2 .3 .4 .5 .6 .7 Review the documentation manuals with the commissioning team. Complete all items as identified in these manuals. This includes work by subcontractors, test agencies, equipment representatives and manufacturer agents. Review Contract Documents and inspect the Work to ensure completeness of the Work and compliance with the Contract Documents. Correct contract deficiencies and execute change orders as directed by the Engineer/Architect. Test, adjust and balance equipment and systems identified in Divisions 2-16. Submit the completed manuals and project record documents as specified. Update the documentation manuals prior to each project meeting. .4 The Substantial Completion Certificate will not be issued till the commissioning process is completed and the final reports and commissioning documentation are received. .5 Fifteen days prior to application for Substantial Completion, submit 3 copies of final commissioning manuals on applicable forms. .6 Submit reports of testing, adjusting and balancing postponed due to seasonal, climatic, occupancy, or other reasons beyond Contractor’s control, promptly after execution of those services. .7 Ensure each form bears signature of recorder and that of the Supervisor of the reporting organization. 1.5 COMMISSIONING .1 Conduct commissioning once identified pre-requisite activities are completed for a system and approved by the Commissioning Coordinator. .2 Engineer/Architect to issue a commissioning plan based on the complexity of building systems. Develop and implement a detailed schedule of commissioning related activities. .3 Test all building systems including architectural, structural, civil, mechanical and electrical components and operating procedures by challenging these systems to realistic operating conditions and train operational staff. .4 Attend meeting(s) of the Commissioning Team prior to the start up of the commissioning exercise to confirm commissioning activities, to review the commissioning plan, and finalize the Contractor’s detailed activity schedule. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 Page 3 of 30 .5 Notwithstanding all-inclusive requirements specified in this section, additional separate commissioning may be required at a later date for equipment and systems whose full operation is dependent on seasonal conditions. Job conditions for Peak Performance Verification are as follows: (1) Summer sequence commissioning to take place between June 1 and September 15 when outside ambient temperatures are at least 22°C; (2) Winter sequence commissioning to take place between November 1 and March 31 when outside ambient temperature is no greater than minus 10°C. .6 Take responsibility to: .1 .2 .3 .4 .5 1.6 Provide certified personnel, test equipment and documentation. Complete documentation as specified including but not limited to: .1 Confirmation that each piece of equipment, including a test data sheet, to record performance against specification .2 Completed test record and data sheet for each system to record performance against specification for each adjustable and non-adjustable set point .3 Written documentation describing startup, normal operation and shut down procedures and trouble shooting analysis .4 List of warranties and bonds .5 Supplier contacts .6 Recommended spare parts list .7 Project record drawings, shop drawings and manufacturer’s installation, operation and maintenance data and inspection/testing-reports. Correct contract deficiencies previously outstanding and as identified during commissioning. Execute change orders as directed by the Engineer/Architect. Repeat activities as required by Engineer/Architect following correction of deficiencies and execution of change order work. At completion of commissioning, scan completed manuals to electronic format on CD(s) in PDF format as required and submit to Owner. COMMISSIONING TEAM .1 The commissioning team shall consist of: (edit to suit specific project requirements) .1 .2 .3 .4 .5 .6 .7 .8 .9 .10 .11 .12 Commissioning Coordinator (Consultant Team Leader) Department of Transportation & Works’s Representative(s) User Representatives/Owner. .Resident Project Coordinator General Contractor Mechanical Contractor Fire Protection Contractor Controls Contractor Electrical Contractor Fire Alarm Contractor Security Systems Contractor Communications Systems Contractor DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .13 .14 Manufacturer’s startup Technicians. Testing Agencies. PART 2 PRODUCTS (NOT APPLICABLE) PART 3 EXECUTION 3.1 SCHEDULE .1 3.2 Provide a detailed schedule for on-site verification activity by the commissioning team based on the commissioning plan provided by the Engineer/Architect. Be responsible for resource allocation respecting the exact number and duration for personnel required to perform the tasks required. COMMISSIONING TASKS .1 3.3 Page 4 of 30 The following section summarizes the tasks to be conducted for the commissioning process with further specifics being provided within applicable specification sections and installations checks, verification activities and performance checks given within the manuals provided by the Engineer/Architect. (Note: Edit to suit specific project requirements) DISCIPLINE: CIVIL Systems to be Commissioned .1 Site Earth Works .1 .2 .3 .4 .5 .6 .7 .8 .9 .2 Confirm removal of all unsuitable materials. Confirm compliance with Geo-technical Report. Confirm construction of engineered rock mattresses. Ensure walls are compacted in lifts equally, inside and outside foundation walls. Ensure site grading is done in lifts and compacted to meet contract documents. Ensure materials quality compliance of sub-grade and bedding materials, supported by laboratory test reports. Ensure site sloped away from building Ensure site sloped to drainage system components. Provide reports on compaction testing results. Water Mains .1 .2 .3 .4 .5 .6 .7 Confirm pipe size and materials. Confirm proper jointing of pipes. Confirm gate valves and appurtenances meet contract requirements. Confirm and record location of valve boxes. Confirm fire hydrants meet municipal requirements. Confirm water piping has been swabbed (cleaned), flushed, and disinfected. Provide results of water quality laboratory testing. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .8 .9 .10 .11 .3 .3 .4 .5 Confirm weeping tiles operational prior to backfilling. Confirm pipe size and materials. Confirm proper grade for piping and proper bedding/filter fabric placed prior to backfilling. Confirm location of all clean outs and end plugs. Clean all piping prior to use. Guide Rails and Posts .1 .2 .3 .8 Confirm concrete meets quality requirement and incorporate test results. Confirm location and elevation of manholes and catchbasins, including invert elevations. Provide results of leakage testing. Foundation/Underslab Drainage .1 .2 .3 .7 Confirm pipe size and materials Confirm and record location and elevation of pipe/culvert inverts. Confirm proper pipe bedding installation and inspection prior to backfilling. Provide results of infiltration and exfiltration testing for piped storm sewers. Confirm cleaning of storm sewers. Confirm culvert headwall and gratings are properly installed. Verify slopes of drainage channels at culvert locations. Review system with facility operator. Manholes and Catchbasins .1 .2 .6 Confirm pipe size and materials. Confirm proper jointing of pipes. Confirm and record location and elevation of sewer inverts. Provide results of infiltration and exfiltration testing. Confirm cleaning of sanitary sewers. Provide reports of television and photographic inspections Review system with facility operator. Site Storm Drainage .1 .2 .3 .4 .5 .6 .7 .8 .5 Confirm placement of concrete thrust blocks prior to back filling. Confirm placement of sub-grade warning devices (e.g. tape, plank, concrete). Confirm pressure testing prior to backfilling and provide test records. Instruct operating staff on location, operation, and maintenance of water line valves and fire hydrants. Sanitary Sewer Mains .1 .2 .3 .4 .5 .6 .7 .4 Page 5 of 30 Confirm guide rails, posts and materials meet contract requirements. Verify cable guides and hardware meet contract requirements. Confirm placement of timber posts. Hard Landscaping - Asphalt/Concrete DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .1 .2 .3 .4 .5 .6 .7 .8 .9 .9 Confirm subbase, base granulars, asphalt, and concrete meet specification requirements. Provide records of acceptable compaction results for subbase and base granulars. Provide record of concrete strength, mix design, and temperature at time of placement. Provide records of asphalt testing results. Verify placement of control joints in concrete walkways, curbs and other exterior on grade concrete slabs. Confirm placement of concrete reinforcements. Ensure no ponding on asphalt areas. Ensure proper slope to drainage. Ensure all permanent markings are installed for parking stalls, handicap accessibility and directional signage. Soft Landscaping .1 .2 3.4 Page 6 of 30 Mowable grassed areas .1 Confirm topsoil meets contract requirements. .2 Confirm sodding/hydroseeding meets contract requirements. .3 Confirm fertilizer application. .4 Verify maintenance of grass in accordance with contract requirements. .5 Provide training on fertilizing and weed control. Shrubs/Evergreen Trees/Deciduous Trees .1 Confirm plants, trees and shrubs meet contract requirements .2 Provide pruning and shaping schedule of various plant types. .3 Demonstrate winter protection. .4 Provide training for watering/fertilizing new plants. DISCIPLINE: STRUCTURAL Systems to be Commissioned .1 Foundations .1 .2 .3 .4 .2 Confirm footing and top of wall elevations meet contract requirements. Confirm footings, concrete piers and walls have required reinforcement installed. Confirm proper placement and construction of concrete/ piers and walls. Confirm concrete meets quality requirements and incorporate test results. Structural Steel Frame .1 .2 .3 .4 .5 Provide copy of erector’s certification before construction beings. Confirm base plates are shimmed, level, grouted, and anchor bolts are correctly aligned. Confirm steel is properly primed and painted Confirm structural steel is properly welded to meet contract requirements. Confirm structural bracing is in place in accordance with erection drawings. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .6 .7 .8 .9 .10 .3 Confirm all welds are primed and painted. Confirm metal deck is correctly welded. Confirm structural third party inspection has been completed satisfactorily. Record all on site test results and project record information, prior to structural steel being covered by other trades. Provide certification of quality compliance from fabricator. Concrete Slabs on Grade .1 .2 .3 .4 .5 .6 .7 3.5 Page 7 of 30 Confirm concrete meets quality requirements and incorporate test results. Confirm location of thickened slabs meet contract requirements. Confirm location and installation of control joints. Confirm concrete floor curing (and sealer) applied as per manufacturer’s instructions and compatible with finish flooring materials. Confirm reinforcement is correctly placed in slab. Provide records of curing conditions for the first 14 days of the initial placement. Provide survey of finished floor elevations to confirm compliance with required “Level”tolerance. DISCIPLINE: ARCHITECTURAL Systems to be Commissioned .1 Thermal and Moisture Protection .1 .2 .3 .4 .5 .6 .7 .2 .Roof Assembly .1 .2 .3 .4 .5 .6 .7 .8 .3 Provide records of compliance regarding moisture content of building materials. Confirm insulation types and values meet contract requirements. Confirm rigid insulation is adhered as per manufacturer’s instructions. Ensure mechanical protection is provided for exposed insulation. Certify continuity of air barriers and vapour retarders. Provide records of independent leakage testing for air barrier assembly. Provide certificate of product quality compliance for insulation, air barriers, vapor retarders, etc. Confirm integrity of roof installation. Perform flood testing if required by the specifications. Verify slopes of roof provide positive water flow to roof drains. Ensure no ponding of water on roof. Confirm all flashing is in place and sealing is complete. Ensure the installation of all roofing accessories. Ensure the installation and weather tightness of roof access hatches. Include inspection reports from manufacturer representative as specified indicating all warranties are in place. Ensure that walkway traffic provisions are in place. Exterior Wall Assemblies DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .1 .2 .3 Page 8 of 30 Verify continuity of air/vapour retarders. Ensure weep and vent holes are open and clear of debris. Verify insect blocks are installed. .4 Exterior Cladding ( Note: Develop to suit materials incorporated in project.) .5 Doors and Windows .1 .2 .3 .4 Doors: .1 Confirm operation of all mechanical door hardware. .2 Confirm operation of all electrical/electronic door hardware including safety features. .3 Ensure tightness and continuity of smoke/sound stripping and accessories. .4 Ensure keying in place and properly recorded. .5 Confirm sign over to Client for use. .6 Provide training and warranties. Windows and Skylights: .1 Check all window glazing seals. .2 Confirm all sealant in place around frames. .3 Check operation of operable sections (if applicable). .4 Check operation of window latches (if applicable). .5 Check for water and air leakage. .6 Check performances of acoustically rated windows. .7 Provide training and warranties. .8 Door Operators .9 Confirm correct door operators installed. .10 Check for smooth operation, time for operator to act, hold open time and closure time. .11 Check switch integrity. Observe how switch operates. .12 Ensure proper operation of safety edges and of the safety features. .13 Provide training and warranties. Entrances and Exits .1 Confirm correct operation of all doors. .2 Confirm lock assembly operates as required. .3 Verify door closers operate correctly. Provide verification from manufacturer of proper operation of electronic closure. .4 Confirm if doors are/can be affected by wind conditions. .5 Confirm door entrance grilles free of debris and secure. .6 Confirm all weatherstripping in place and properly secured. .7 Confirm accessibility compliance for wheelchair users. .8 Demonstrate maintenance required. .9 Provide warranties. Acoustical Performance DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .1 .5 .6 .7 .8 .9 Page 9 of 30 Conduct thorough review of integrity of walls where specific STC ratings are required. .2 Confirm suitable application of caulking, infill material and sealing to prevent sound leakage. .3 Conduct sample sound transmission test on walls. .4 Provide Technical Support Inspector’s report of compliance for acoustical separations. Elevating Docks .1 Observe operation of elevating dock. .2 Demonstrate operation using typical trucks which will access site. .3 Confirm operation of safety features. .4 Provide training and warranties. Equipment –Kitchen .1 Check operation of all kitchen equipment. .2 Demonstrate operation of equipment. .3 Check for tight seals on doors and latches. .4 Provide training and warranties. Folding Panel Partitions .1 Ensure smooth operation. .2 Ensure operation of sound seals. .3 Check acoustical operation. .4 Provide maintenance requirements. .5 Provide warranty. Pre-fabricated Walk-in Coolers .1 Verify operation of cold storage equipment. Ensure systems are fully operational. .2 Measure storage temperatures and compare with control setpoints. .3 Simulate alarm conditions, observe and record actions resulting from exceeding temperature conditions. Observe and record alarm reactions. .4 Review all maintenance procedures. .5 Provide warranties. Room Fit-up & Finishes .1 Confirm all ceiling systems installed as per manufacturer’s requirements. .2 Confirm ceiling integrity. .3 Verify spare products provided and signed off by operating staff. .4 Confirm wall finishes. Include paint type, number and colour chip each location. .5 Confirm flooring used. Provide information on type of flooring, location, colour. .6 Provide and review all cleaning processes for ceiling, walls, flooring. Verify application processes of sealants, waxes, etc. as applicable. .7 Demonstrate maintenance required. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .8 .10 Page 10 of 30 Provide Technical Support Inspector’s report inspection report verifying finishes have met contract requirements. Occupant Safety and Accessibility .1 Fire Separations .1 Verify fire stopping and smoke seals in place. .2 Verify sleeves in hollow walls around piping. .3 Verify installation of angle iron around duct work installed as specified. .4 Verify fire dampers electrically wired into the F.A. P. installed as specified .5 Verify continuity and ratings of fire separations. .6 Verify proper fire separations at firewalls, including parapets. .7 Confirm fire ratings for door assemblies complies with door schedule. .8 Confirm door closures, smoke sweeps, hardware complies with hardware schedule. .9 Ensure positive pressure test to insure no infiltration to area of safe refuge. .10 Confirm power to area of safe refuge to be dedicated only to this area for 2 hours. .2 Escape Routes Within Facility .1 Confirm Fire walls as per fire ratings and plan location. .2 Verify length of travel meets design requirements. .3 Verify panic hardware installed as per section/specification. .4 Confirm fire rated doors/closures meet design requirement. .5 Confirm visual markers for visually impaired. .6 Test emergency lighting. .3 Doors in Fire Separations .1 Verify smoke sweeps/seals installed properly. .2 Verify door closures/hardware hinges installed properly and operating. .3 Verify door closure installed properly and operating .4 Verify hinges as per specification installed properly. .5 Verify doors closures meet Code requirements. .6 Verify ULC labels attached to door and frame. .4 Barrier-free Path of Travel, Exterior and Interior .1 Confirm exit doors meet contract requirements. .2 Confirm occupancy approval received from Government Services and Lands (GSL). .3 Verify service counters have barrier free sections .4 Verify displays, shelving, and fire extinguishers are installed in a manner which ensures barrier-free path of travel. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .5 .11 .12 Page 11 of 30 Confirm all ramps to and from area of refuge wheelchair accessible. .6 Confirm handicap parking is provided. .7 Verify dimensions of ramps. landings, and handrail heights meet contract requirements. .8 Confirm service counters to be maximum height of 865 mm. .9 Confirm all counters serving public have 1 area barrier free. .10 Verify operation of stair lifts. .11 Confirm travel to handicap washrooms not to exceed 45 m. .12 Confirm handrails in stairs and ramps meet NBC. .13 Confirm handrails have returns and finished to wall. .5 . Barrier- free Washroom and Shower .1 Confirm toilets set at heights specified. .2 Confirm barrier free washroom fixtures/vanities set at heights specified. .3 Confirm door to washroom stalls are proper dimensions and equipped with specified hardware. .4 Confirm shower stalls equipped with handicap shower attachments/folding stools. .5 Verify shower threshold 12 mm or less in height. .6 Verify shower base sloped to floor drain (approximately 1% grade). .7 Confirm shower curtains meet specification. .8 Ensure washroom accessories meet accessibility requirements (e.g. dimensions, size, placement, mounting heights of grab bars). Telephones: .1 Confirm telephone installation meets accessibility code .2 Confirm assisted hearing available on phones. Overhead Doors, Coiling Doors and Coiling Grilles .1 Confirm operation of mechanical door hardware. .2 Confirm operation of electrical/electronic hardware. .3 Confirm continuity and tightness of weatherstripping, smoke seals, and accessories. .4 Ensure operation of safety features on overhead doors, and overhead coiling doors. .5 Confirm operation of fire safety features. .6 Ensure keying in place and properly recorded. .7 Provide training and warranties. .8 Millwork .9 Ensure all dimensions and materials meet contract requirements. .10 Confirm installation and proper operation of all hardware. .11 Verify all systems installed level, plumb, and square. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .12 .13 .14 .15 .16 .17 .18 .19 .20 3.6 Page 12 of 30 Ensure proper fasteners are used to attach mill work to walls, floors, and ceilings. Confirm proper types of glazing used for trophy cases. Ensure all hinges have proper number of screws. Ensure all bumpers are installed. Ensure shelf supports and clips for shelves are installed. Ensure all locks are keyed the same. Ensure all toe kicks are finished Ensure counter tops meet contract requirements, back splash caulked, and matched end caps. Provide instruction to operating staff as required. DISCIPLINE: MECHANICAL Systems to be Commissioned .1 Sprinkler System Devices .1 .2 .3 .4 .5 .6 .7 .8 .2 Plumbing Fixtures .1 .2 .3 .4 .5 .6 .7 .8 .3 Verify connection to fire alarm system. Confirm signal to fire alarm system all devices. Confirm location on as-built drawings. Verify operation of all devices. Verify drain test location and demonstrate. Observe how water flows from outlets. Verify identification used for all devices. Demonstrate maintenance required and training. Provide Certification Certificate for total system. Confirm fixture installed matches contract documents. Verify fixture trim operation. Record flush time for all flush valves Confirm operation of hands free powered trim in normal and emergency power situations. Verify fixtures properly accessible and meet requirements for handicapped accessibility. Demonstrate maintenance operations for all fixtures and trim types. Verify cleaning methods for all fixtures. Demonstrate correct methods as required. Provide Certificate of Compliance for Accessibility. Domestic Water System .1 .2 .3 Confirm operation of recirculation pump. Confirm domestic water booster pump operation. Verify and record hot water temperature at each plumbing fixture. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .4 .5 .6 .7 .8 .9 .10 .11 .12 .4 Review operation procedures. Demonstrate operation. Simulate replacement and maintenance of filter system. Confirm alarm setpoints (if applicable). Provide copy of water test results Sterilize complete system prior to use. Instruct owner on the operation of shut-off valves Medical Gas System .1 .2 .3 .4 .5 .6 Verify and record setpoints of domestic hot water supply. Confirm pressure reducing valve operation. Confirm water meter operation. Confirm and record setpoints of tempered water devices. Measure and record outlet temperatures. Test recovery time for tanks. Drain tank, refill cold water, record time to reheat tank to setpoint. Provide copy of water test results Sterilize complete system prior to use. Instruct owner on the operation of shut-off valves Demonstrate maintenance required. Domestic Water Filtration .1 .2 .3 .4 .5 .6 .7 .5 Page 13 of 30 Confirm system verification by medical gas testing agency. Confirm interface of alarm system to the master alarm panels. Verify operation. Demonstrate alarm tests at all remote alarm and master alarm panels. Demonstrate maintenance requirements. Provide Certificate of Compliance issued by medical gas testing agency. Steam Generators –Boilers .1 .2 .3 .4 .5 .6 .7 .8 .9 .10 .11 Verify installation meets design requirements. Confirm Government Services Centre staff have witnessed and passed all required testing. Confirm operation of safety relief devices. Confirm operation of central control panels. Verify integrity of control device installation in control panels. Verify low/high cut off devices operation. Simulate start up of boilers. Simulate normal shut down. Verify sequencing of boilers in response to load changes and variable steam demand. Confirm firing rates of boilers. Confirm feed water pump operation. Simulate power loss/power return and confirm restart automatically of plant. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .12 .13 .14 .15 .16 .17 .18 .19 .20 .21 .22 .7 Simulate all alarm functions. Verify interface with Building Automation System (BAS). Record start/stop cycling times. Confirm relays and other devices are rated for operation cycling to be experienced especially light loading situations. Confirm results of combustion tests on boilers. Record all information. Verify manufacturer’s start-up data. Verify operation of blow down system (automatic). Demonstrate manual blow down operation. Demonstrate maintenance required and training Verify proper installation of breeching Verify fresh air intake system Verify steam pressure venting. Provide warranties. Chilled Water System –Chillers .1 .2 .3 .4 .5 .6 .7 .8 .9 .10 .11 .12 .13 .14 .15 .16 .8 Page 14 of 30 Verify operation of chillers. Perform during peak cooling season. Confirm interface with Building Automation System. Verify readings of chiller controls and readings obtained on the BAS. Observe operation of system capacity control. Verify sequencing of chillers and condenser fan system. Confirm operating pressures of refrigerant system. Simulate system shutdown upon alarm detection. Confirm signals sent to BAS and response observed. Measure operating range of the chilled water loop Simulate loss of chilled water flow. Simulate loss of electrical power supply. Simulate high head pressure situation. Observe control reaction. Demonstrate maintenance requirements for chiller. Confirm sufficient space present for maintenance procedures. Confirm presence of safety relief devices. Verify performance of refrigerant gas detection system. Simulate using procedures required by the manufacturer. Provide maintenance requirements and training Provide warranties Hot Water Heating System .1 .2 .3 .4 .5 .6 Confirm operation of all circulation pumps. Demonstrate normal power failure/emergency power start of all circulation pumps. Confirm interface of temperature, flow pressure and status points with BAS. Confirm operation of all heating valves, reheat coil valves, etc. Verify operation of bypass valves used for end of loop circulation. Confirm all balancing completed. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .7 .8 .9 .10 .11 .12 .13 .9 .2 .3 .4 .5 .6 .7 .8 Confirm circulation pump operation. Verify rotation direction, inlet/outlet pressures, flow rates, motor electrical power. Confirm all balancing completed. Measure and record inlet/outlet temperatures. Confirm all devices labeled. Demonstrate normal/emergency/normal power sequence and verify system function after normal power returned. Perform while system fully operational. Confirm interface of devices with BAS. Measure and record all temperatures and pressures and groups provided. Confirm ranges are acceptable for ease of use. Provide maintenance training. Humidification System .1 .2 .3 .4 .5 .6 .7 .11 Verify pump direction. Confirm inlet/outlet pressures. Measure motor amperage. Calculate flow rate. Verify across flow metering devices. Confirm all devices labeled. Confirm proper flow direction. Confirm flow in radiant in floor heating system. Verify loop temperatures. Record inlets and outlet temperatures. Demonstrate pump maintenance procedures and training. . Provide GSL Inspection certificates. Chilled Water System .1 .10 Page 15 of 30 Confirm all devices installed. Verify flow to units and ducts. Measure inlet/outlet air humidity level, across each humidifier. Verify control operation. Confirm setpoint of relative humidity sensing devices. Confirm interface with BAS. Insure all condensate drain lines are installed properly. Provide maintenance training. Air Handling Systems (Applicable for each system) .1 .2 .3 .4 .5 .6 .7 .8 .9 Confirm interface of all devices with BAS. Verify balancing report Check filter status. Install clean filters. Confirm damper operation. Ensure dampers operate freely and sufficient damper motors are provided. Verify dampers seal tight when closed. Ensure units are clean and washed down prior to final acceptance. Verify fan systems capacity control. Measure static pressures at various flow settings of fan. Confirm system is stable when operating. Confirm heating and cooling coil operation. Measure inlet/outlet temperatures. Verify humidifier control operation. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .10 .11 .12 .13 .14 .15 .16 .17 .18 .19 .12 .6 .7 Confirm correct installation as per manufacturer’s instructions. Confirm correct rotation. Measure and record motor amperage. Verify (if applicable) belt tension. Verify bearings are lubricated. Record lubrication from start-up to final turn over to Owner. Verify no vibration exists. Confirm balancing completed. Verify results. Isolation Room Systems .1 .2 .3 .4 .5 .6 .7 .14 Confirm suitable drain traps provided. Verify trap height and system static pressures. Confirm fire alarm devices in place and fully functional. Confirm operation of all interior lights for the unit. Measure for belt tension and confirm it is within manufacturer’s recommendation. Verify fan balance and confirm within tolerance. Verify bearing lubrication works correctly. Record bearing lubrication activities from start up to final turn over to Owner. Verify filters fit tight with minimal air leakage. Verify ease of accessibility for maintenance. Confirm capacity control for fan operation. Demonstrate maintenance required and training Fans .1 .2 .3 .4 .5 .13 Page 16 of 30 Confirm systems have been checked by manufacturer’s representative. Provide inspection certificates Demonstrate positive/negative/neutral operation. Record operations and verify space pressurization achieved. Verify alarm operation. Verify interface with BAS. Confirm operation during emergency power Review maintenance procedures with manufacturer’s representative and training. Provide Technical Services Inspector’s Report on Room Construction verifying installation contractual requirements. Pressurization/Smoke Control .1 .2 .3 .4 .5 Confirm systems have been checked by manufacturer’s control representative. Provide documents. Demonstrate positive/negative/neutral operation. Record operations and verify space pressurization achieved Verify alarm operation. Verify interface with BAS. Confirm operation during emergency power DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .6 .7 .15 .2 .3 .4 .5 .6 .7 Confirm systems have been checked by manufacturer’s control representative. Provide inspection certificates. Demonstrate positive/negative/neutral operation. Record operations and verify space pressurization achieved. Verify alarm operation. Verify interface with BAS. Confirm operation during emergency power situation. Review maintenance procedures with manufacturer’s representative and provide training. Provide Technical Services Inspector’s Report on construction of room to verify installation meets contractual requirements. DDC Controls .1 .2 .3 .4 .5 .6 .7 .8 .9 .10 3.7 Confirm correct heating coil installed. Confirm CV number on coil control valve. Confirm and record discharge temperature. Space Pressure .1 .17 Review maintenance procedures with manufacturer’s representative. Provide Technical Services Inspector’s Report on wall assembly construction verifying installation of wall assemblies meet contractual requirements. Reheat Coils .1 .2 .3 .16 Confirm all DDC points are connected and operating. Confirm all equipment controlled by the DDC system is functioning properly. Confirm all sensors are calibrated and installed correctly. Verify all building automation sequences. (Provide all necessary additional programming required to achieve a fully functional system) Verify all DDC alarms. Verify all graphical representations. Confirm all DDC systems and components are fully BACNET compatible. Confirm software is installed and operational on owner and DTW sites as directed. Confirm validity of password information for access to system. Confirm wiring method conforms to wire size and type, and is installed in accordance with specification. Review maintenance procedures with manufacturer’s representative and provide training. DISCIPLINE: ELECTRICAL Systems to be Commissioned .1 Page 17 of 30 Padmount Switchgear .1 .2 Check all connections for tightness Inspect all insulators. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .3 .4 .5 .2 Confirm installation in cable tray. Confirm cables are undamaged. Confirm type of cold shrink termination Confirm integrity of fire wrap for exposed 5 kV cabling system. Megger all conductors. Interior Feeders .1 .2 .3 .4 .5 .7 Check all factory made connections Remove all dirt and debris from inside enclosures. Check fuse size and breaker settings. Check door operation. Perform load tests Conductors: .1 .2 .3 .4 .5 .6 Check all factory made connections Remove all dirt and debris from inside enclosures. Check fuse size and breaker settings. Check door operation. Confirm connection to Building Automation System (BAS). Demonstrate alarm connection to Building Automation System. Perform load tests. Confirm information received from digital meters, transfer controls, air circuit breaker and molded case breakers to BAS. Air Circuit Breakers: .1 .2 .3 .4 .5 .5 Check operation over eight (8) hour period at least ten (10) times Check all connections. Demonstrate maintenance requirements. Interior Switchgear: .1 .2 .3 .4 .5 .6 .7 .8 .4 Check fuses for correctness and type. Training of staff by factory representative. Commissioning and start-up to be conducted by factory trained technician. Exterior Load Break Switches: .1 .2 .3 .3 Page 18 of 30 Confirm wire gauge, type & quantity. Install strap and box connectors. Confirm routing and support. Confirm bonding conductor. Megger all conductors. Energy Management System: .1 .2 Conduct tests of measurement devices accuracy. Confirm factory tests of all equipment. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .3 .4 .5 .6 .7 .8 .9 .8 .4 .5 .6 .7 .8 .9 .10 .4 .5 .6 .7 .8 Megger all cables. Confirm cables not damaged. Measure and record amperage and voltage on primary and secondary of transformer under normal load. Confirm proper grounding. Confirm flexible connections to transformer. Confirm transformer housing not damaged. Confirm installation of sprinkler guards Confirm installation of identification. Lightning Arrestor. .1 .2 .11 Megger all cables. Confirm cables undamaged. Measure and record amperage and voltage on primary and secondary of transformer under normal load. Confirm conduits properly installed. Confirm concrete as per detail. Confirm rebar installed as pre detail. Confirm crushed stone installed. Confirm routing of primary and secondary conduits. Confirm proper grounding. Confirm transformer not damaged. Dry Type Transformers Indoors. .1 .2 .3 .10 Confirm software developed matches National Energy Code of Canada requirements. Confirm operating ranges of transducers for current and potential match building operating range. Verify by field tests complete system including hardware, software and communication devices. Obtain manufacturer’s certification verifying correct installation Perform training Demonstrate maintenance procedures. Commissioning to be conducted by factory trained technician. Pad Mount Distribution Transformers. .1 .2 .3 .9 Page 19 of 30 Confirm all electrical connections. Confirm conductor installation. Overhead Service. .1 .2 .3 .4 Megger all conductors. Confirm attachment height. Inspect all conduits and supports. Drain and seal all LB fittings. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .5 .12 Megger all cables. Measure and record voltage and amperage on all conductors under normal load. Confirm grounding and bonding. Confirm all connections properly torqued. Confirm identification installed. Confirm final cleaning. Confirm rating of OCP devices and adjustments as per specifications. Motor Control Centres. .1 .2 .3 .4 .5 .6 .7 .8 .16 Confirm proper operation. Record resulting pf under normal load conditions. Confirm rating of capacitors. Confirm operation of switching system. Confirm all connections torqued. Confirm identification installed. Service Entrance Equipment. .1 .2 .3 .4 .5 .6 .7 .15 Megger all conductors. Inspect trenches for foreign materials and sharp obstacles. Confirm proper conduit bedding and installation. (i.e. glue, support) Confirm conduit sizes, spare conduit and pull rope. Confirm trench/conduit depth. Confirm marking system installed. Confirm proper backfill procedure. Power Factor Capacitors. .1 .2 .3 .4 .5 .6 .14 Verify attachment method and support systems. Underground Services. .1 .2 .3 .4 .5 .6 .7 .13 Page 20 of 30 Megger all feeder and load conductors. Measure and record voltage and amperage on all feeder and load conductors under2 normal load. Confirm grounding and bonding. Confirm all connections properly torqued. Confirm identification installed. Confirm final cleaning. Confirm operation of all starters/contactors. Confirm proper overloads installed and MCP devices adjusted to suit loads. Snow Melt Cables. .1 .2 .3 Megger all cables. Confirm conductor size correct. Measure amperage and voltage of conductor on normal loads and as per manufacturers recommendations. Record results. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .4 .5 .6 .7 .8 .17 .3 .4 .5 .6 .7 .3 .4 .5 Confirm all conduit and cable connections seated properly in enclosure. Confirm locknuts and bushings on all conduit connections. Double locknuts on RGS. Confirm proper grounding and bonding. Confirm proper support. Confirm identification installed. Wiring Devices. .1 .2 .3 .4 .5 .6 .21 Megger all conductors. Measure and record voltage and amperage on all conductors under normal load. Confirm grounding and bonding. Confirm all connections properly torqued. Confirm identification installed. Confirm final cleaning. Confirm proper rating of overcurrent devices installed. Equipment Enclosures, Splitters, Junction Boxes. .1 .2 .20 Megger all feeder conductors. Measure and record voltage and amperage on all feeder conductors under normal load. Confirm grounding and bonding. Confirm all connections properly torqued. Confirm panel identification installed. Confirm final cleaning. Confirm panel directory correct. Disconnect/Safety Switches. .1 .2 .3 .4 .5 .6 .7 .19 Confirm size and type of overcurrent protection.[GFCI as appropriate] Confirm operation of control system. Confirm identification installed. Train all designated personnel in proper operation of system. Commissioning to be conducted by factory trained technician. Distribution and Lighting Panelboards. .1 .2 .18 Page 21 of 30 Confirm devices installed in proper location. Confirm switches installed on latch side of doors. Confirm proper voltage/amperage rating. Confirm proper polarity. Confirm cover plate installed flush on wall. Confirm identification completed. Circuit Breakers. .1 .2 Confirm breaker size as specified. Confirm breaker properly torqued to panel bus. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .3 .4 .5 .6 .22 .6 .7 Confirm relays proper voltage and ampacity as specified. Confirm spare relays installed where indicated. Confirm relay enclosure ventilated. Confirm voltage and load on each relay. Record results. Confirm all electrical connections properly torqued. Commissioning to be conducted by factory trained technician. Confirm identification is installed. Patient Care Areas. .1 .2 .3 .4 .5 .6 .7 .8 .25 Confirm heater wattage and voltage are correct. Confirm heater connected to circuit indicated. Confirm heater controls operate properly. Confirm heater fastened securely to building. Confirm radiant heating panel electrical connections as per manufacturer’s recommendations. Confirm in-floor radiant heating sets installed and connected as per manufacturers recommendations. Measure voltage and amperage at heaters. Record results. Heating Control Panels. .1 .2 .3 .4 .5 .6 .7 .24 Confirm load conductors properly torqued to breakers. Confirm GFCI breakers operate properly. Confirm AFCI breakers operate properly. Confirm voltage and amperage load on all circuit breakers. Record results. Electric Heating. .1 .2 .3 .4 .5 .23 Page 22 of 30 Test all electrical receptacles to CSA-Z32.2-M89. Megger all conductors within patient care area back to source. Test all breakers supplying equipment in patient care areas to CSA-2.2-M89. Test all grounded systems within patient care areas for voltage drop in accordance with CSA-Z32.2-M89. Test voltage difference between ground points in patient care areas to CSAZ32.2-M89. Test receptacle retentive face and polarity to CSA-Z32.2-M89. Test ground return path voltage rise to CSA-Z32.2-M89. Provide test equipment and certified test personnel for all procedures noted above. Commissioning to be conducted by factory trained technician. Conduits. .1 .2 .3 .4 Confirm all conduits proper size and type. Confirm all conduits properly supported. Confirm conduit fill not exceeded. Confirm all in slab conduits noted on as-builts. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .5 .6 .26 Confirm pull ropes installed in all spare conduits. Confirm bonding conductor installed in all conduits. Emergency Power Generation. .1 .2 .3 .4 .5 .6 .7 .8 .9 .10 .11 .12 .13 .14 .15 .16 .17 .18 .19 .20 .21 .22 .27 Page 23 of 30 Confirm proper installation of generator. Verify installation of ventilation system. Confirm muffler drained to floor drain. Confirm exhaust is installed as per specification. Confirm wiring interconnections complete. Check system performance after startup. Run for 1 hour. Verify battery charging system operating correctly. Confirm generator neutral properly grounded. Confirm connections to generator switchboard. Demonstrate operation of unit. Demonstrate maintenance procedures and training. Perform test of all safety devices. Ensure all fuel controls are operational and monitored. Provide certification from manufacturer that system is operational and meets the specification. Megger all cables. Measure and record voltage and amperage on all conductors under normal load. Confirm grounding. Confirm all connections properly torqued. Confirm nameplate installed. Confirm final cleaning. Confirm fuel supply installation. Commissioning to be conducted by factory trained technician. Transfer Switches .1 .2 .3 .4 .5 .6 .7 .8 .9 .10 .11 .12 Check installation of relays and solid state monitors. Check operation in “Test”, “Manual”and “Engine Start Positions”. Verify operation in each mode. Perform tests. Demonstrate all maintenance procedures. Megger all cables. Measure and record voltage and amperage on all cables, on normal load. Confirm grounding. Confirm all cables properly torqued. Confirm nameplate installed. Confirm final cleaning. Generator Switchboard. Perform all performance checks as identified in Section 16443. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .13 .14 .15 .16 .17 .28 .2 .3 .4 .5 .6 .7 .8 .9 .10 .11 .12 Confirm all grounding system installed and connections made are secure. (Primary and secondary grounds.) Verify connections and conductors protected from mechanical injury. Ensure compliance with the specification. Confirm bonding wire used in all conduit systems. Confirm all grounding buses installed correctly. Perform continuity and resistance tests. Verify hospital OR suite ground system. Demonstrate normal maintenance requirements for grounding system. Confirm building steel grounded. Check main systems ground. Check data system ground. Check telephone system ground. Contactors .1 .2 .3 .4 .31 Confirm motor starters securely mounted. Verify all field power and control connections properly torqued... Confirm overload heaters installed. Verify operation of all units. Verify lubrication of all moving parts. Operate starters in sequence to confirm satisfactory performance. Perform start/stop functions and verify sequencing actions. Provide manufacturer’s representative for commissioning. Demonstrate maintenance procedures and training. Provide certification from manufacturer of installation. Grounding .1 .30 Demonstrate all maintenance procedures. Confirm meters operate and verify readings. Perform verification and performance tests as recommended by manufacturer Confirm synchronization of system as per specifications and manufacturer’s recommendations. Commissioning to be conducted by factory trained technician. Motor Starters .1 .2 .3 .4 .5 .6 .7 .8 .9 .10 .29 Page 24 of 30 Verify installation of contactors and components. Verify installation of secondary control devices. Confirm operation of all devices. Demonstrate maintenance requirements. Electrical Outlets .1 .2 Verify lamcoid labels are correct. Test receptacles to CSA Z32.2-M89 as applicable for health care facilities. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .3 .4 .5 .32 Verify test results report meets CSA requirements. Confirm installation meets specification. Provide copy of test results. Lighting .1 .2 .3 .4 .5 .6 .7 .8 .9 .10 .33 Page 25 of 30 Confirm all lighting systems are properly supported Confirm all fixture alignments. Perform light level testing in all rooms at night (2 readings per room). Confirm operation of all fixtures. Demonstrate maintenance procedures. Confirm spare parts are provided as specified. Verify outside lighting foundations are true and plumb. Verify operation of all exterior lighting. Provide copy of test results. Provide copy of warranties. Fire Alarm .1 .2 .3 .4 .5 .6 .7 .8 .9 .10 .11 .12 .13 .14 .15 .16 .17 .18 .19 .20 .21 .22 .23 .24 Verify that system components have been located and installed in accordance with the contract documents. Verify all wiring connections completed. Verify operation of all devices. Coordinate interconnection with Building Automation System. Test alarm operations for all areas and devices. Confirm graphic display mounted. Confirm location of Certificate of Compliance from manufacturer. . Simulate grounds and breaks with the system. Check and verify communication panels operate correctly. Verify system maintenance procedures. System verified Confirm all remote annunciators working. Confirm all interior and exterior audible devices working. Confirm all pull stations installed Confirm all visual signal devices operational. Check panel flush and level Training provided Warranties supplied Maintenance materials supplied Check tags for fire department, phone numbers at all pull stations Confirm sprinkler system connections operational. Confirm interconnections to mechanical systems operable Confirm interconnections to door closures operable Confirm interconnections to fire suppression system operable DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .25 .26 .27 .28 .34 .2 .3 .4 .5 .6 .2 .3 .4 .5 .6 .7 .8 Verify that system components have been located and installed in accordance with the contract documents. Verify operation of voice paging, CD player and AM/FM tuner. Verify microphone override for all microphone locations. Demonstrate all maintenance procedures. Verify and record sound levels throughout facility. Train all designated staff in proper operation of system. Commissioning to be conducted by factory trained technician. Provide copy of warranty. Nurse Call System .1 .2 .3 .4 .5 .6 .7 .38 Verify that system components have been located and installed in accordance with the contract documents. Conduct intelligibility and performance test. Provide manufacturer’s representative for testing. Demonstrate maintenance procedures and training. Commissioning to be conducted by factory trained technician. Provide copy of warranty. Public Address System. .1 .37 Verify UPS performance meets specification. Provide factory representative testing of this system. Verify system maintenance procedures and demonstrate training. Provide copy of test results and Certification Certificate. Commissioning to be conducted by factory trained technician. Provide copy of warranty. Intercom System .1 .36 Confirm auto phone dialer installed and operational Confirm exterior strobe installed Check all acoustic signal devices are audible from all locations. Commissioning to be conducted by factory trained technician. Uninterruptible Power Supply .1 .2 .3 .4 .5 .6 .35 Page 26 of 30 Verify that system components have been located and installed in accordance with the contract documents. Demonstrate maintenance procedures for all system components. Provide Manufacturer’s representative for testing of system. Demonstrate by operation all devices for the nurse call system. Train all designated staff in proper operation of system. Commissioning to be conducted by factory trained technician. Provide copy of warranty. Central Clock System DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .1 .2 .3 .4 .5 .6 .39 .2 .3 .4 .5 .6 .7 .2 .3 .4 .5 .6 Verify that system components have been located and installed in accordance with the contract documents. Confirm equipment installation. Demonstrate signal strength throughout system. Provide certification indicating installation meets specification. Commissioning to be conducted by factory trained technician. Demonstrate use of local channel for owners use. Security System Card Access: .1 .2 .3 .4 .5 .6 .7 .42 Verify that system components have been located and installed in accordance with the contract documents. Verify equipment installation. Conduct performance checks. Demonstrate maintenance procedures. Train all designated staff in proper operation of system. Commissioning to be conducted by factory trained technician. Provide copy of warranty. Television System .1 .41 Verify that system components have been located and installed in accordance with the contract documents. Demonstrate operation of system. Verify resetting capability and operation for normal and emergency power. Demonstrate maintenance procedures. Train all designated staff in proper operation of system. Commissioning to be conducted by factory trained technician. Central Dictation .1 .40 Page 27 of 30 Verify that system components have been located and installed in accordance with the contract documents. Demonstrate operation of all system components as required. Verify operation of system in normal and emergency power modes. Demonstrate all maintenance procedures as required. Train all designated staff in proper operation of system. Commissioning to be conducted by factory trained technician. Provide copy of warranty. Security System –CCTV .1 .2 .3 .4 .5 Verify that system components have been located and installed in accordance with the contract documents. Train all designated staff in proper operation of system. Confirm signal received from each camera meets specifications. Review operation procedures of central monitoring and control system. Verify low light operation of system. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .6 .7 .8 .9 .10 .11 .12 .13 .43 .2 .3 .4 .5 .6 .7 .8 .9 .2 .3 .4 .5 .6 Verify that system components have been located and installed in accordance with the contract documents. Confirm all testing as required completed and documented. Verify receipt of final certification documentation. Confirm handicap accessibility requirements are met. Commissioning to be conducted by factory trained technician. Provide copy of warranty. Assistive Listening System .1 .2 .3 .4 .5 .6 .7 .8 .9 .46 Verify that system components have been located and installed in accordance with the contract documents. Demonstrate equipment installed. Confirm performance requirements meet specifications. Demonstrate maintenance procedures and training. Provide certification indicating system is installed as per specification. Confirm connection to remote monitoring agency and receipt of applicable contact numbers by the monitoring agency. Commissioning to be conducted by factory trained technician. Train all designated staff in proper operation of system. Provide copy of warranty. Telephone Systems .1 .45 Confirm motion detection operation of system. Verify operation of weatherproof housing heater and blower. Demonstrate motorized lens function. Demonstrate time lapse recorder system. Perform user orientation as specified. Demonstrate maintenance procedures and training. Commissioning to be conducted by factory trained technician. Provide copy of warranty. Security System .1 .44 Page 28 of 30 Verify that system components have been located and installed in accordance with the contract documents. Verify operation of amplifier, receiver, transmitter, microphone and earbuds. Confirm operation of battery charger. Verify and record sound levels to earbuds. Confirm quantity of spare batteries. Train all designated staff in proper operation of system. Commissioning to be conducted by factory trained technician. Demonstrate all maintenance procedures. Provide copy of warranty. Stage Performance Lighting Systems DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .1 .2 .3 .4 .5 .6 .7 .8 .9 .10 .11 .12 .47 .2 .3 .4 .5 .6 Verify that system components have been located and installed in accordance with the contract documents. Confirm all testing as required completed and documented. Verify receipt of final certification documentation. Commissioning to be conducted by factory trained technician. Provide copies of data cable test results. Provide copy of warranty. Exit Lighting Systems .1 .2 .3 .4 .5 .6 .7 .49 Verify that system components have been located and installed in accordance with the contract documents. Confirm conduit and conductor size as specified. Confirm types and quantity of lighting fixtures. Confirm spare lamps turned over to owner. Confirm master and remote dimming controls operational. Confirm twist-lock receptacle and wire cages installed on fixtures. Confirm fixture color gels turned over to owner. Confirm power boosters installed where indicated. Orientate light fixtures to suit owner requirements. Demonstrate maintenance procedures and training. Commissioning to be conducted by factory trained technician. Provide copy of warranty. Data Cable Systems .1 .48 Page 29 of 30 Verify that system components have been located and installed in accordance with the contract documents. Verify all exit lights installed correctly and are operational. Confirm breaker for exit lights locked in on position. Confirm operation of integral batteries. Confirm integral emergency lighting heads are aimed properly. Demonstrate maintenance procedures. Confirm spare parts are provided as specified. Emergency Lighting Systems .1 .2 .3 .4 .5 .6 .7 .8 Verify that system components have been located and installed in accordance with the contract documents. Verify all emergency lighting units installed correctly and are operational. Confirm breaker for emergency lighting units locked in on position. Confirm batteries are fully charged. Confirm remote heads operational. Confirm conductor size to remote heads. Demonstrate maintenance procedures. Confirm spare parts are provided as specified. DTW Works Master Specification Section 01810 - Commissioning Issued 2005/06/01 .50 Electric Load Bank .1 .2 .3 .4 .5 .6 .51 Confirm proper operation. Record resulting amperage under normal load conditions. Confirm rating of resistive load. Confirm operation of test switching system. Confirm all connections torqued. Confirm identification installed. Cable Tray Systems .1 .2 .3 .4 .5 .6 .52 Page 30 of 30 Confirm all cable tray proper size and type. Confirm all cable tray supported in accordance with manufacturer’s instructions. Confirm cable tray fill not exceeded. Confirm all system dividers in place where applicable. Confirm identification installed on all cables at intervals as specified. Confirm bonding conductor installed in all tray and connecting all tray sections. Control Wiring .1 .2 .3 END OF SECTION Confirm conductor size and type in accordance with specification. Confirm cable shields grounded at source end only. Confirm wiring installed in accordance with specification.