Rail and Underground Panel Date: 10 July 2014 Item 8: Overnight Ballasted Track Renewals This paper will be considered in public 1 Summary 1.1 The accompanying presentation provides details of the Overnight Ballasted Track Renewals that are undertaken on the London Underground network. 1.2 The presentation highlights: (a) the objectives of the programme; (b) the status of the project; (c) examples of work which has been undertaken in engineering hours; (d) the future proposals for works of this nature; (e) undertaking drainage works in engineering hours; (f) the London Underground future Access Strategy; and (g) the developments being undertaken to further improve the programme. 2 Recommendation 2.1 The Panel is asked to note this paper and presentation. List of appendices to this report: Appendix 1: Presentation List of Background Papers: None Contact Officer: Number: Email: David Waboso, Capital Programmes Director, Rail and Underground 020 3054 8228 david.waboso@tube.tfl.gov.uk 1 Appendix 1 Overnight Ballasted Track Renewals Presentation to Rail and Underground Panel 10 July 2014 1 MISSION ‘To renew track on the surface and sub-surface network without closures’ OBJECTIVES • Develop methodologies for delivery of ballasted track renewal (BTR) without affecting passenger service • Develop a programme of overnight delivery projects as part of the ongoing BTR workbank • Enable corporate objectives of; • Track Access Strategy – reducing weekend closures • Night Tube • Access Transformation – maximising available working time and reducing unit rate. 2 PROJECT STATUS OVERVIEW • Delivery Team established and developing as programme grows • 2 x methodologies developed – mini excavators and DISAB • Four projects completed saving 3-4 weekend closures • 222m re-ballast Buckhurst Hill • 134m re-ballast re ballast Leytonstone • 283m BTR Leytonstone • 73m re-ballast High Street Kensington (S b S f ) (Sub Surface) • Two concurrent projects in progress • Ealing Common 230m BTR • Acton Town 221m BTR 3 BUCKHURST HILL TO WOODFORD JCN – 222m Re-Ballast • Completed 5 March • Best production shift = 10.3m • Typical available working time 2hr 15min (reduced due to Rail Adhesive Train) • Zero overruns Method – • Excavation by mini –excavator • Install Geotextile • Backfill new ballast by Road Rail Vehicles with trailers and ballast box • Manual compaction • 2 x follow up tamps 4 LEYTON TO LEYTONSTONE - 283m Re-ballast • • • • Completed April 2014 Best production shift = 22m Typical available working time 3hr Zero overruns 5 LEYTON TO LEYTONSTONE – 134m Full BTR Bullhead to Flat-bottom rail conversion • • • • Completed April 2014 Best production shift = 22m Typical available working time 3hr Zero overruns BTR Method • Re-rail to flat-bottom utilising NTF390 temporary baseplates. • Weld and stress site • Change sleepers to new concrete 1502 during reballasting process. 6 BAYSWATER TO HIGH ST KENSINGTON • First DISAB site for project • Scope = 73m Re Re-ballast ballast only • Delivery of site fully completed 22nd May • Best production shift = 7 7.3m 3m • Enabling works allowed full BTR scope to be delivered in one weekend possession • Zero overruns 7 ACTON TOWN TO SOUTH EALING • First full BTR site for project using DISAB • Scope p = 220m BTR • Start of second simultaneous work front • Complex site – single line working plus various signalling equipment complexities • Typical available working time 2hr 30min • Zero overruns 8 EALING BROADWAY TO EALING COMMON • First site for project interacting with depot • Scope = 215m BTR • Best p production shift = 6m • Typical available working time 2hr 15min • Access plant through Ealing Common Depot • Zero overruns 9 2014/15 • Plan to be delivering on 3-4 separate work fronts simultaneously by the end off 2014/15 • 2014/15 Programme – 3km BTR and Re-ballasting potentially over 8 t sites it separate Overnight BTR PROJECT 10 Overnight g Track Drainage g • Overnight delivery of new track drainage started in 2012 • Track Partnership are driving up the volume of overnight drainage replacement: • 6 646m 6 o of new e ttrack ac d drainage a age in 2012-13 0 3 • 2440m in 2013-14 • 3000m plus in 2014-15 • In addition also completed 4275m metres of drainage reconditioning with UV lining upgrades last year - mostly overnight. • Track drainage now being delivered as opportunity works in closures for other reasons, including track renewal, 125% increased delivery l t year (10 last (10,200m 200 vs 8 8,100 100 iin 2012 2012-13) 13) 11 • Access Transformation – “more time on tools” • Possessions redefined in Rule Book to expand working window at both ends of traffic day. (Reduced call back and quicker method for taking possessions an additional half hour.) • Current times - working with Timetables team all late and early current are avoided when designing paths around BTR • Access Transformation – “resource cost reductions” • Protection – multi-skilling SPC to undertake activities allows for 70% reduction in contracted protection staff • Using trains to reduce costs and increase scope • Plant modifications to maximise efficiencyy ((e.g. g increased excavator buckets and additional working lights) • Compaction improved to achieve greater track quality – introduction of Robel Vertical Handheld tampers 12 London Underground's Future Access Strategy Network periphery: Weekend or major closures are possible. Central London: Closures very rare. Closures only granted for work that cannot be delivered overnight. Inner suburban: Closures accepted only for work that cannot be delivered overnight or where central London train frequencies are unaffected ‘Central London’ to include Piccadilly line service to Heathrow 13 2014-15 programme: 3.3km BCV2028/2049 - Leyton to Leytonstone (417m) Minidiggers Completion of first ballasted trial site SSL2133 - Acton Town to South Ealing (221m) SSL2021 - Bayswater to High Street Kensington (73m) SSL2005 - Ealing Common (230m) Minidiggers First site preventing a closure of the Heathrow service - Underway DISAB First site in sub surface - Complete Minidiggers Underway SSL2030 - Stamford Brook to Hammersmith – (600m) DISAB First site on District/Piccadilly four track where large volumes to deliver JNP0427 - Hounslow West to Hatton Cross (624m of 1540m) DISAB First site in tunnel on Piccadilly line service to Heathrow BCV2160 - Ealing Broadway to West Acton (528m of 600m) Minidiggers JNP0378 - Finchley Road to West Hampstead (456m of 913m) Minidiggers • Very close to Chilterns with no cable run. Avoids need for a simultaneous Met/Jubilee/Chiltern (whole franchise) closure 2015-2020 Workbank – circa 25km 14 Development of future methods Oct 2013 suction trialed 3 /h 3m/hr Jan 2014 mini diggers/ ballast boxes 4m/hr Jan 2014 Automated rail handling solution Aug 2014 Gopher 3m/hr Aug 2014 Slotted bucket trial Pic Line 20m/hr Aug 2015 bespoke tamping units 2018? April 2014 DISAB implemented 6.5m/hr 2016 MFS & DISAB 125m/shift capacity 20 15 Overnight Ballasted Track Replacement – the challenge • Plant access critical • Additional investment in access points • Satellite ‘depot’ sites needed • Maximise work times: • Improved access rules • Prioritise overnight work • Last trains always to run on time, reform service to make happen 16 Current overnight sites vs Weekend sites on LU • Minidigger method unit rate – circa double the closure rate (as expected) • Early days for ‘DISAB’ - essential for future (limited space, buried services) • DISAB method unit rate – between double and treble cost • Current DISAB has limited capacity (maintenance tool) • Mini-digger method more flexible and cost effective than DISAB but cannot be used in restricted areas • We will develop methodology then invest in the right equipment – this is what will deliver low unit rates in future years • Progress is as expected • Even at a seemingly high unit rate, cost to London of overnight BTR is lower LU BTR Delivery vs Others • UK national rail weekend delivery – similar cost to LU at similar sites • UK national rail overnight work – longer hours, large machinery, more space • Paris, Paris New York – weekend delivery delivery, similar cost or higher • Buenos Aires – overnight delivery, high cost, effect on daily service 17