20160329-3039 FERC PDF (Unofficial) 03/29/2016 154 FERC ¶ 62,200 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Project Nos. 2375-105 and 8277-070 Verso Androscoggin Power LLC Andro Hydro LLC ORDER AMENDING LICENSES (March 29, 2016) 1. On February 26, 2016, Eagle Creek Renewable Energy, LLC submitted notice to the Commission that through its subsidiary Eagle Creek Development Holdings, LLC, it has acquired Verso Androscoggin Power LLC, licensee for the Riley-Jay-Livermore Project No. 2375,1 located on the Androscoggin River in Franklin, Androscoggin, and Oxford counties, Maine and the Otis Hydroelectric Project No. 8277,2 located on the Androscoggin River in Franklin, Androscoggin, and Oxford counties Maine. Also, Verso Androscoggin Power LLC filed notice advising the Commission that it had changed its name to Andro Hydro LLC. Verso Androscoggin Power LLC states that this is a change of name only and that there has been no change in the legal entity holding the licenses for the Riley-Jay-Livermore and Otis Hydroelectric Projects. The projects do not occupy any United States land. 2. The licensee should ensure that all of the references to “Verso Androscoggin Power LLC” are changed, including but not limited to, the projects’ Part 8 signs, any safety signs with the licensee’s name on them, and any other directional signs. The project should reflect the new licensee name “Andro Hydro LLC.” This change is administrative and does not change any other conditions or requirements of the projects. The licensee’s request to change its name is approved. The Director orders: (A) The licenses for the Riley-Jay-Livermore Project No. 2375 and the Otis Hydroelectric Project No. 8277 are amended to change the licensee’s name from Verso Androscoggin Power LLC to Andro Hydro LLC. 1 Order Issuing New License (Major Project), 84 FERC ¶ 62,235 (1998). 2 Order Issuing New License (Major Project), 84 FERC ¶ 62,234 (1998). 20160329-3039 FERC PDF (Unofficial) 03/29/2016 Project Nos. 2375-105 and 8277-070 -2- (B) Within 15 days from the date of this order, file updated contact information. An electronic copy of the Contact Form is available through the Commission’s Internet site at http://www.ferc.gov/industries/hydropower/gen-info/compadmin/contact.asp. (C) This order constitutes final agency action. Any party may file a request for rehearing of this order within 30 days from the date of its issuance, as provided in section (§) 313(a) of the Federal Power Act, 16 U.S.C. § 825l (2012), and the Commission’s regulations at 18 C.F.R. § 385.713 (2015). The filing of a request for rehearing does not operate as a stay of the effective date of this order, or of any other date specified in this order. The licensee’s failure to file a request for rehearing shall constitute acceptance of this order. Heather Campbell Deputy Director Division of Hydropower Administration and Compliance 20160329-3039 FERC PDF (Unofficial) 03/29/2016 Document Content(s) P-2375-105.DOC........................................................1-2