Attachment_1_Specifications-1

advertisement
FA4608-16-R-0013
Attachment 1
Page 1 of 79
SECTION 01010 - SUMMARY OF THE WORK
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of Contract, including General and Supplementary Conditions
and other Division 1 Specification Sections, apply to work of this Section.
PROJECT/WORK IDENTIFICATION
A.
General: Project name is "REPAIR PRIMARY DISTRIBUTION LINE, BODCAU TIE – AWUB
11-0052" as shown on Contract Documents prepared by S. E. Huey Co. and John J. Guth
Associates, Inc. Drawings and Specifications are dated OCTOBER 1, 2012.
B.
Summary by References: Work of the Contract can be summarized by references to the
Contract, General Conditions, Supplementary Conditions, Specification Sections, Drawings,
addenda and modifications to the Contract Documents issued as part of addenda subsequent to
the initial printing of this project manual and including, but not necessarily limited to, printed
material referenced by any of these. It is recognized that work of the Contract is also
unavoidably affected or influenced by governing regulations, natural phenomenon, including
weather conditions, and other forces outside the Contract Documents.
C.
Abbreviated Written Summary: Briefly and without force and effect upon the contract
documents, the work of the Contract can be summarized as follows:
1.
The work includes removal of and replacement of approximately 9000’ of underground
primary electrical distribution line.
D.
Sequence of Work: Sequence work for minimum power interruptions
E.
Utility Interruptions: Utility interruptions shall be held to a minimum and will be permitted only at
times approved by the User Agency. The User Agency may require that any outages be during
nights, weekends, etc. Provide any required overtime work at no additional cost to the Owner.
F.
Building Permits:
building projects.
G.
The Contractor shall be responsible for the printing costs for the reprinting of construction
documents for their use.
H.
The Contractor shall be responsible for meeting all applicable OSHA standards, including the
Hazard Communication Standards.
I.
Completion Date: As required by Instructions to Bidders, the Contractor is required to fully
complete construction of project within specified number of days. Contractor shall furnish
sufficient forces, construction plant and equipment, and work such hours, including weekend
and night shifts as may be necessary to insure prosecution of work in accordance with schedule
to the contracted completion date. If, in the opinion of the Engineer and Owner, Contractor falls
behind progress schedule, Contractor shall take steps as may be necessary to improve his
progress by such means as increasing number of men, number of shifts, days of work, and/or
amount of construction plant, all without additional cost to Owner. If access to building is
Local Building Permits are not required for Federal Government owned
FA4608-16-R-0013
Attachment 1
Page 2 of 79
required at other than normal building hours, Contractor shall make arrangements with
User Agency.
1.3
CONTRACTOR USE OF PREMISES
A.
General: The Contractor shall limit his use of the premises to the work indicated, so as to allow
for Owner occupancy with minimum interruptions.
B.
Use of the Site: Confine operations at the site to the areas permitted under the Contract.
Portions of the site beyond areas on which work is indicated are not to be disturbed. Conform to
site rules and regulations affecting the work while engaged in project construction.
C.
Keep existing driveways and entrances serving the premises clear and available to the Owner
and his employees at all times. Do not use these areas for parking or storage of materials.
D.
Do not unreasonably encumber the site with materials or equipment. Confine stockpiling of
materials and location of storage sheds to the areas approved by User Agency. If additional
storage is necessary, obtain and pay for such storage off-site. The Owner will not make
payments for materials stored off-site.
E.
Lock automotive type vehicles, such as passenger cars and trucks and other mechanized or
motorized construction equipment, when parked and unattended, so as to prevent unauthorized
use. Do not leave such vehicles or equipment unattended with the motor running or the ignition
key in place.
F.
Use of existing toilets within the buildings by the Contractor and his personnel will not be
permitted.
G.
General Requirements: Observe no smoking rules. All personnel must wear shirts. No radios
or similar items may be used.
H.
Asbestos: There is no asbestos abatement work included in this project. No asbestoscontaining materials have been identified on items that are indicated to be disturbed.
If asbestos-containing materials are encountered, comply with the following:
1.
2.
Upon encountering any previously unidentified materials which he suspects may contain
asbestos, the Contractor shall immediately cease all work in the immediate vicinity of the
suspected materials and notify the Designer and the Owner. The Owner shall retain
consultants to identify the suspected materials. Upon identification, the Owner reserves
the right to contract separately for the removal, or require the Contractor to remove said
materials in accordance with the following provision. In any case, the work shall be
performed by a licensed and certified Abatement Contractor.
The Louisiana Department of Environmental Quality (D.E.Q.) has issued the
Louisiana Emission Standards for Hazardous Air Pollutants.
Where asbestos is
encountered in a project, the Contractor shall comply with all laws and ordinances
pertaining to asbestos handling and abatement, including the latest revision of
LAC 33:111, Chapter 25, Subchapter F, Emission Standards for Hazardous Air Pollutants,
LAC 33:111, Chapter 27, Asbestos Containing Materials in Schools and Public Buildings
and LAC 33:111, Chapter 51, Subchapter M, Section 5151, Emission Standards for
Asbestos.
FA4608-16-R-0013
Attachment 1
Page 3 of 79
3.
Notification should be addressed to:
Asbestos Coordinator
Louisiana Department of Environmental Quality
Air Quality Division
Post Office Box 82135
Baton Rouge, Louisiana 70884-2135
4.
5.
1.4
If the Owner chooses to remove any previously unidentified materials by utilizing different
Contractors, the Contractor shall cooperate fully with the Owner's consultants and
asbestos abatement Contractor permitting them full access to the project, and shall not
resume work in the vicinity of the suspected materials until advised by the Designer and
the Owner that it is safe to do so.
Refer to Article 7 of the Supplementary Conditions if the Contractor is required to do this
work.
OWNER OCCUPANCY
A.
Full Owner Occupancy: The Owner will occupy the site during the entire period of construction.
Cooperate fully with the Owner and his representative during construction operations to
minimize conflicts and to facilitate Owner usage. Perform the work so as not to interfere with the
Owner's operations.
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION (Not applicable)
END OF SECTION 01010
FA4608-16-R-0013
Attachment 1
Page 4 of 79
SECTION 01045 - CUTTING AND PATCHING
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of Contract, including General and Supplementary Conditions
and other Division 1 Specification Sections, apply to this Section.
SUMMARY
A.
This Section specifies administrative and procedural requirements for cutting and patching.
B.
Refer to other Sections for specific requirements and limitations applicable to cutting and
patching individual parts of the work.
1.
1.3
Requirements of this Section apply to mechanical and electrical installations. Refer to
Division 15 and Division 16 Sections for other requirements and limitations applicable to
cutting and patching mechanical and electrical installations.
SUBMITTALS
A.
Cutting and Patching Proposal: Where approval of procedures for cutting and patching is
required before proceeding, submit a proposal describing procedures well in advance of the time
cutting and patching will be performed and request approval to proceed. Include the following
information, as applicable, in the proposal:
1.
2.
3.
4.
5.
6.
7.
1.4
Describe the extent of cutting and patching required and how it is to be performed;
indicate why it cannot be avoided.
Describe anticipated results in terms of changes to existing construction; include changes
to structural elements and operating components as well as changes in the building's
appearance and other significant visual elements.
List products to be used and firms or entities that will perform work.
Indicate dates when cutting and patching is to be performed.
List utilities that will be disturbed or affected, including those that will be relocated and
those that will be temporarily out-of-service. Indicate how long service will be disrupted.
Where cutting and patching involves addition of reinforcement to structural elements,
submit details and engineering calculations to show how reinforcement is integrated with
the original structure.
Approval by the Engineer to proceed with cutting and patching does not waive the
Engineer's right to later require complete removal and replacement of a part of the work
found to be unsatisfactory.
QUALITY ASSURANCE
A.
Requirements for Structural Work: Do not cut and patch structural elements in a manner that
would reduce their load-carrying capacity or load-deflection ratio.
1.
2.
3.
4.
Foundation construction.
Bearing and retaining wall.
Structural concrete.
Structural steel.
FA4608-16-R-0013
Attachment 1
Page 5 of 79
5.
6.
7.
8.
9.
10.
11.
12.
13.
B.
Lintels.
Timber and primary wood framing.
Structural decking.
Stair systems.
Miscellaneous structural metals.
Exterior curtain wall construction.
Equipment supports.
Piping, ductwork, vessels and equipment.
Structural systems of special construction in Division 11.
Operational and Safety Limitations: Do not cut and patch operating elements or safety related
components in a manner that would result in reducing their capacity to perform as intended,
or result in increased maintenance, or decreased operational life or safety.
1.
Obtain approval of the cutting and patching proposal before cutting and patching the
following operating elements or safety related systems:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
C.
Shoring, bracing, and sheeting.
Primary operational systems and equipment.
Air or smoke barriers.
Water, moisture, or vapor barriers.
Membranes and flashings.
Fire protection systems.
Noise and vibration control elements and systems.
Control systems.
Communication systems.
Conveying systems.
Electrical wiring systems.
Special construction specified by Division 13 Sections.
Visual Requirements: Do not cut and patch construction exposed on the exterior or in occupied
spaces, in a manner that would, in the Engineer's opinion, reduce the building's aesthetic
qualities, or result in visual evidence of cutting and patching. Remove and replace work cut and
patched in a visually unsatisfactory manner.
PART 2 - PRODUCTS
2.1
MATERIALS
A.
Use materials that are identical to existing materials. If identical materials are not available or
cannot be used where exposed surfaces are involved, use materials that match existing
adjacent surfaces to the fullest extent possible with regard to visual effect. Use materials whose
installed performance will equal or surpass that of existing materials.
PART 3 - EXECUTION
3.1
INSPECTION
A.
Before cutting existing surfaces, examine surfaces to be cut and patched and conditions under
which cutting and patching is to be performed. Take corrective action before proceeding,
if unsafe or unsatisfactory conditions are encountered.
FA4608-16-R-0013
Attachment 1
Page 6 of 79
1.
3.2
Before proceeding, meet at the site with parties involved in cutting and patching, including
mechanical and electrical trades. Review areas of potential interference and conflict.
Coordinate procedures and resolve potential conflicts before proceeding.
PREPARATION
A.
Temporary Support: Provide temporary support of work to be cut.
B.
Protection: Protect existing construction during cutting and patching to prevent damage.
Provide protection from adverse weather conditions for portions of the project that might be
exposed during cutting and patching operations.
C.
Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.
D.
Take all precautions necessary to avoid cutting existing pipe, conduit or ductwork serving the
building, but scheduled to be removed or relocated until provisions have been made to bypass
them.
3.3
PERFORMANCE
A.
General: Employ skilled workmen to perform cutting and patching. Proceed with cutting and
patching at the earliest feasible time and complete without delay.
1.
B.
Cutting: Cut existing construction using methods least likely to damage elements to be retained
or adjoining construction. Where possible review proposed procedures with the original installer;
comply with the original installer's recommendations.
1.
2.
3.
4.
C.
Cut existing construction to provide for installation of other components or performance of
other construction activities and the subsequent fitting and patching required to restore
surfaces to their original condition.
In general, where cutting is required use hand or small power tools designed for sawing or
grinding, not hammering and chopping. Cut holes and slots neatly to size required with
minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.
Cut through concrete and masonry using a cutting machine such as a carborundum saw
or diamond core drill.
Comply with requirements of applicable Sections of Divisions 15 and 16 where cutting
and patching requires excavating and backfilling.
By-pass utility services such as pipe or conduit, before cutting, where services are shown
or required to be removed, relocated or abandoned. Cut-off pipe or conduit in walls or
partitions to be removed. Cap, valve or plug and seal the remaining portion of pipe or
conduit to prevent entrance of moisture or other foreign matter after by-passing and
cutting.
Patching: Patch with durable seams that are as invisible as possible. Comply with specified
tolerances.
1.
2.
Where feasible, inspect and test patched areas to demonstrate integrity of the installation.
Restore exposed finishes of patched areas and extend finish restoration into retained
adjoining construction in a manner that will eliminate evidence of patching and refinishing.
FA4608-16-R-0013
Attachment 1
Page 7 of 79
3.4
CLEANING
A.
Thoroughly clean areas and spaces where cutting and patching is performed or used as access.
Remove completely excess material, paint, mortar, oils, putty and items of similar nature.
END OF SECTION 01045
FA4608-16-R-0013
Attachment 1
Page 8 of 79
SECTION 01090 - DEFINITIONS AND STANDARDS
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of Contract, including General and Supplementary Conditions
and other Division 1 Specification sections, apply to work of this Section.
DESCRIPTION OF REQUIREMENTS
A.
General: This section specifies procedural and administrative requirements for compliance with
governing regulations and codes and standards imposed upon the work. These requirements
include obtaining permits, licenses, inspections, releases, and similar documentation, as well as
payments, statements, and similar requirements associated with regulations, codes, and
standards.
B.
The term "Regulations" is defined to include laws, statutes, ordinances, and lawful orders issued
by governing authorities, as well as those rules, conventions, and agreements within the
construction industry which effectively control the performance of the work regardless of whether
they are lawfully imposed by governing authority or not.
1.3
DEFINITIONS
A.
General Explanation: Certain terms used in Contract Documents are defined in this Article.
Definitions and explanations contained in this Section are not necessarily complete, but are
general for the work to extent that they are not stated more explicitly in another element of the
Contract Documents.
B.
General Requirements: Provisions and requirements of other Division 1 Sections apply to the
entire work of the Contract and, where so indicated, to other elements which are included in the
project.
C.
Indicated: The term "indicated" is a cross-reference to graphic representations, notes, or
Schedules on the Drawings, to other paragraphs or schedules in the Specifications, and to
similar means of recording requirements in Contract Documents. Where terms such as
"shown," "noted," "scheduled," and "specified" are used in lieu of "indicated," it is for the purpose
of helping the reader locate the cross-reference, and no limitation of location is intended except
as specifically noted.
D.
Directed, Requested, Etc.: Terms such as "directed," "requested," "authorized," "selected,"
"approved," "required," "accepted," and "permitted" mean "directed by the Engineer," "requested
by the Engineer," and similar phrases. However, no such implied meaning will be interpreted to
extend the Engineer's responsibility into the Contractor's area of construction supervision.
E.
Approve: Where used in conjunction with the Engineer's response to submittals, requests,
applications, inquiries, reports, and claims by the Contractor, the term "approved" will be held to
limitations of the Engineer's responsibilities and duties as specified in General and
Supplementary Conditions. In no case will the Engineer's approval be interpreted as a release
of the Contractor from responsibilities to fulfill requirements of Contract Documents or
acceptance of the work, unless otherwise provided by requirements of the Contract Documents.
FA4608-16-R-0013
Attachment 1
Page 9 of 79
F.
Project Site: The term "project site" means the space available to the Contractor for
performance of the work, either exclusively or in conjunction with others performing other
construction as part of the project. The extent of the project site is shown on the Drawings,
and may or may not be identical with the description of the land upon which the project is to be
built.
G.
Furnish: The term "furnish" is used to mean "supply and deliver to the project site, ready for
unloading, unpacking, assembly, installation, and similar operations."
H.
Install: The term "install" is used to describe operations at project site including the actual
"unloading, unpacking, assembly, erection, placing, anchoring, applying, working to dimensions,
finishing, curing, protecting, cleaning, and similar operations."
I.
Provide: The term "provide" means "to furnish and install, complete and ready for the intended
use."
J.
Installer: The "installer" is "the entity" (person or firm) engaged by the Contractor, its
subcontractor, or sub-subcontractor for performance of a particular element of construction at
the project site, including installation, erection, application, and similar required operations. It is
a requirement that installers are experienced in the operations they are engaged to perform.
K.
Testing Laboratory: A "testing laboratory" is an independent entity engaged to perform specific
inspections or tests of the work, either at the project site or elsewhere, and to report and (if
required) interpret results of those inspections or tests.
1.4
INDUSTRY STANDARDS
A.
Applicability of Standards: Except where more explicit or stringent requirements are written into
the Contract Documents, applicable construction standards have the same force and effect as if
bound into or copied directly into the contract documents. Such industry standards are made a
part of the Contract Documents by reference. Individual specification sections indicate which
codes and standards the Contractor must keep available at the project site for reference.
B.
Referenced standards (standards referenced directly in the contract documents) take
precedence over standards that are not referenced but generally recognized in the industry for
applicability to the work.
C.
Unreferenced Standards: Except as otherwise limited by the Contract Documents, standards
not referenced but recognized in the construction industry as having direct applicability will be
enforced for performance of the work. The decision as to whether an industry code or standard
is applicable, or as to which of several standards are applicable, is the sole responsibility of the
Engineer.
D.
Publication Dates: Except as otherwise indicated, where compliance with an industry standard
is required, comply with standard in effect as of date of Contract Documents.
E.
Conflicting Requirements: Where compliance with two or more standards is specified,
and where these standards establish different or conflicting requirements for minimum quantities
or quality levels, the most stringent requirement will be enforced, unless the contract documents
specifically indicate otherwise. Refer requirements that are different, but apparently equal, and
uncertainties as to which quality level is more stringent to the Engineer for a decision before
proceeding.
F.
Minimum Quantities or Quality Levels: In every instance, the quantity or quality level shown or
specified is intended to be the minimum to be provided or performed. Unless otherwise
indicated, the actual work may either comply exactly, within specified tolerances, with the
FA4608-16-R-0013
Attachment 1
Page 10 of 79
minimum quantity or quality specified, or may exceed that minimum within reasonable limits. In
complying with these requirements, the indicated numeric values are minimum or maximum
values, as noted, or as appropriate for the context of the requirements. Refer instances of
uncertainty to the Engineer for decision before proceeding.
G.
Copies of Standards: The contract documents require that each entity performing work be
experienced in that part of the work being performed. Each entity is also required to be familiar
with industry standards applicable to that part of the work. Copies of applicable standards are
not bound with the contract documents.
H.
Where copies of standards are needed for proper performance of the work, the Contractor is
required to obtain such copies directly from the publication source.
I.
Although copies of standards needed for enforcement of requirements may be required
submittals, the Engineer reserves the right to require the Contractor to submit additional copies
as necessary for enforcement of requirements.
J.
Abbreviations and Names: Trade association names and titles of general standards are
frequently abbreviated. Where acronyms or abbreviations are used in Specifications or other
Contract Documents they are defined to mean the recognized name of the trade association,
standards generating organization, governing authority or other entity applicable to the context of
the text provision. Refer to the "Encyclopedia of Associations," published by Gale Research
Co., available in most libraries.
1.5
SUBMITTALS
A.
Permits, Licenses, and Certifications: For the Owner's records, submit copies of permits,
licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts
for fee payments, judgments, and similar documents, correspondence and records established
in conjunction with compliance with standards and regulations bearing upon performance of the
work.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 01090
FA4608-16-R-0013
Attachment 1
Page 11 of 79
SECTION 01200 - PROJECT MEETINGS
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of Contract, including General and Supplementary Conditions
and other Division 1 Specification Sections, apply to work of this Section.
RELATED SECTIONS
A.
1.3
Construction Schedule: Division 1 Section 01400, "Submittals."
PROGRESS MEETINGS
A.
Progress meetings will be scheduled as necessary during the construction period. Required
attendance shall be:
1.
2.
3.
4.
Engineer and his professional consultants, as needed.
Contractor.
Subcontractors, as appropriate.
Suppliers, as appropriate.
B.
The Owner shall be notified of such meetings and may be represented. It shall be the principal
purpose of these meetings or conferences to effect coordination, cooperation, and assistance in
every practical way to the end of maintaining progress of the project on schedule and completing
the project within the contract time.
C.
Suggested Agenda:
1.
2.
3.
4.
5.
6.
Review work progress since last meeting.
Note field observations, problems, and decisions.
Review off-site fabrication problems.
Revise construction schedule, as indicated.
Review submittal schedules, expedite as required to maintain schedule.
Review changes proposed by Owner for effect on construction schedule and effect on
completion date.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 01200
FA4608-16-R-0013
Attachment 1
Page 12 of 79
SECTION 01400 - SUBMITTALS
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of Contract, including General and Supplementary Conditions
and other Division 1 Specification Sections, apply to work of this Section.
RELATED WORK SPECIFIED ELSEWHERE
A.
Additional Submittal Requirements: Division 0 Section 00700, "AIA Document A201-2007
General Conditions of the Contract for Construction."
B.
Closeout Submittals: Division 1 Section 01700, "Project Closeout."
1.3
CONSTRUCTION SCHEDULE
A.
General: As required by Article 3.10 of the General Conditions, Contractor shall, within ten days
after signing the Contract, prepare and submit to Engineer for information purposes, a practical
schedule showing order in which Contractor proposes to carry on work, dates on which he will
start salient features of work, and contemplated dates for completion. Schedule shall meet or
better construction time included on Instructions to Bidders.
B.
Form of Schedule: Provide in form of horizontal bar chart. Provide separate horizontal bar
column for each trade or operation. Order shall be Table of Contents from Project Manual or
the chronological order of beginning of each item of work. Submit three copies to Engineer.
C.
Content of Schedule: Provide complete sequence of construction activity, dates for beginning,
and completion of each element of construction. Identify work of separate phases or other
logically grouped activities. Show projected percentage of completion for each item of work as
of first day of each month.
1.4
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
A.
Shop Drawings:
1.
2.
B.
Submit prints of original drawings prepared by Contractor, subcontractor, supplier,
or distributor which illustrate same portion of work; showing fabrication, layout setting, or
erection details.
Minor corrections needed on prints will be made by Engineer; for extensive modifications,
prints may be returned to Contractor for correction. When reviewed, Engineer will retain
two copies for record and return remaining copies to General Contractor for distribution.
Reproducible copies of shop drawings will not be reviewed.
Product Data:
1.
2.
Manufacturer's Standard Drawings: Modify drawings to delete information which is not
applicable to project. Supplement standard information to provide additional information
applicable to project.
Manufacturer's Catalog Sheet, Brochures, Diagrams: Clearly mark each copy to identify
pertinent materials, product, or models. Show dimensions and clearances required.
Show performance characteristics and capacities.
FA4608-16-R-0013
Attachment 1
Page 13 of 79
C.
Samples:
1.
2.
D.
General Submission Requirements:
1.
E.
7.
8.
9.
10.
1.5
Quantities: Submit the number of copies of product data and shop drawings that the
Contractor requires for distribution, plus two copies which will be retained by the Engineer.
Quantity of samples required shall be as specified in Specification Section for respective
product.
Submittals shall include:
1.
2.
3.
4.
5.
6.
F.
Physical examples to illustrate materials, equipment, or workmanship to establish
standards by which completed work is judged.
Office samples shall be of sufficient size and quantity to clearly illustrate functional
characteristics of product or material and full range of color and texture samples.
Project title.
Names of Contractor, Subcontractor, Supplier, Manufacturer.
Identification of Product.
Relation to adjacent structure or materials.
Field dimensions.
Reference to Engineer's drawing numbers, specification section, room numbers,
structural framing marks, and/or numbers.
Applicable standards: e.g., ASTM.
Blank space for Engineer's stamp.
Identification of deviations from Contract Documents.
Contractor's stamp, initialed or signed, certifying to review of submittal, verification of field
measurements, and compliance with Contract Documents.
These requirements are in addition to those in Article 3.12 of General Conditions.
SCHEDULE OF VALUES
A.
General: As required by Article 9.2 of General Conditions, submit to Engineer a Schedule of
Values at least ten days prior to submitting first Application for Payment. Upon request by
Engineer, support values with data that will substantiate their correctness. Use Schedule of
Values only as basis for Contractor's Application for Payment. Itemize separate line item cost
for work required by each section of this specification.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 01400
FA4608-16-R-0013
Attachment 1
Page 14 of 79
SECTION 01500 - TEMPORARY FACILITIES
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections, apply to the work of this Section.
BARRICADES, LIGHTS, AND WATCHMEN
A.
1.3
Where the work is constructed in or adjacent to any road, parking area, or public place,
the Contractor shall, at his own cost and expense, furnish and erect such barricades, lights,
and danger signals, shall provide such watchmen, and take such other precautionary measures
for the protection of persons and property and of the work, as are necessary. At the completion
of construction, all barricades and all traces thereof, shall be removed, holes filled, paving
repaired, etc.
TEMPORARY LADDERS, SCAFFOLDS, HOISTS, ETC.
A.
Contractor shall provide and maintain all equipment such as temporary ladders, ramps,
scaffolds, hoists, runways, derricks, chutes, etc., as required for the proper execution of the
work.
B.
All such apparatus, equipment, and construction shall meet all requirements of the Labor Law
and other Federal and State Laws applicable thereto.
C.
Contractor shall provide, maintain, and remove at completion of work all scaffolding required for
the execution of the work. Erect scaffolding on the side of the wall on which work occurs. No
scaffolding shall be built into any work.
D.
Scaffolding for all other work shall be provided, installed, maintained, and removed at
completion of work by the trade requiring such scaffolding.
1.4
STORAGE OF MATERIALS
A.
Contractor shall provide, on the premises where directed, suitable storage sheds
(substantial and watertight) in which he shall store all materials subject to damage by weather.
All storage sheds shall be of sufficient size to hold all materials required on the site at one time,
and shall have floors raised at least 6" above the ground on heavy joists or sleepers.
Storage sheds shall have neat appearance.
B.
Major subcontractors shall provide such temporary buildings as, in the opinion of the Engineer,
may be necessary to fully protect their materials, equipment, apparatus, etc., during the
progress of the work. Such buildings shall have neat appearance.
C.
Building materials, Contractor's equipment, etc., shall be stored on the premises in a manner so
that it may be observed at any time by the Engineer.
FA4608-16-R-0013
Attachment 1
Page 15 of 79
D.
All materials affected by the weather shall be covered and protected and kept free from damage
while being transported to the site.
E.
Subcontractors desiring to store materials scheduled for immediate use in the building may do
so only in locations as directed by the General Contractor and approved by the Engineer.
1.5
SANITARY FACILITIES
A.
1.6
Provide single-occupant, self-contained toilet units of the chemical, aerated recirculation,
or combustion type, properly vented and fully enclosed with a glass fiber reinforced polyester
shell or similar non-absorbent material. Contractor shall keep such place in sanitary condition
and remove at completion of contract. Facility fixtures shall not be used by workmen.
Comply with all applicable codes, utility, and safety regulations.
LAYING-OUT OF WORK
A.
Contractor shall compare all drawings and verify all dimensions, and shall take any and all
measurements necessary to verify the drawing dimensions in relation to conditions already
established at the job site before laying out the work. Contractor will be held responsible for
subsequent errors which could have been avoided by such checking.
B.
Any discrepancy which will affect the proper layout of the work shall be immediately called to the
attention of the Engineer by the Contractor. No work shall proceed until such discrepancy has
been rectified as directed by the Engineer.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 01500
FA4608-16-R-0013
Attachment 1
Page 16 of 79
SECTION 01600 - MATERIAL AND EQUIPMENT
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
The general provisions of the Contract, including General and Supplementary Conditions, apply
to the work specified in this Section. Refer to other Division 1 Sections for additional
requirements which may affect the work of this Section.
RELATED REQUIREMENTS
A.
Warranty: Division 0 Section 00700, "AIA Document A201-2007 General Conditions of the
Contract for Construction," Para. 3.5.
B.
Substitutions: Division 0 Document 00100, "Instructions to Bidders."
1.3
GENERAL PRODUCT REQUIREMENTS
A.
1.4
Provide products, materials, and equipment which comply with the requirements and which are
undamaged and unused at the time of installation, and which are complete with accessories,
trim, finish, safety guards, and other devices and details needed for a complete installation and
for the intended use and effect. Do not use material or equipment for any purpose other than
that for which it is designed or specified.
MANUFACTURER'S INSTRUCTIONS
A.
When Contract Documents require that installation of work shall comply with manufacturer's
printed instructions, obtain and distribute copies of such instructions to parties involved in the
installation, including two copies to Engineer. Maintain one set of complete instructions at the
job site during installation and until completion.
B.
Handle, install, connect, clean, condition, and adjust product in strict accord with such
instructions and in conformity with specified requirements. Should job conditions or specified
requirements conflict with manufacturer's instructions, consult with Engineer for further
instructions. Do not proceed with work without clear instructions.
C.
Perform work in accord with manufacturer's instructions. Do not omit any preparatory step or
installation procedure unless specifically modified or exempted by Contract Documents.
1.5
TRANSPORTATION AND HANDLING
A.
Arrange deliveries of products in accord with construction schedules, coordinate to avoid conflict
with work and conditions at the site. Deliver products in undamaged condition, in manufacturer's
original containers or packaging, with identifying labels intact and legible. Immediately on
delivery, inspect shipments to assure compliance with requirements of Contract Documents and
approved submittals, and that products are properly protected and undamaged.
FA4608-16-R-0013
Attachment 1
Page 17 of 79
B.
1.6
Provide equipment and personnel to handle products by method to prevent soiling or damage to
products or packaging.
STORAGE AND PROTECTION
A.
Store products in accord with manufacturer's instructions, with seals and labels intact and
legible. Store products subject to damage by the elements in weathertight enclosures.
Maintain temperature and humidity within the ranges required by manufacturer's instructions.
B.
Exterior Storage: Store fabricated products above the ground, on blocking or skids, prevent
soiling or staining. Cover products which are subject to deterioration with impervious sheet
coverings, provide adequate ventilation to avoid condensation. Store loose granular materials in
a well-drained area on solid surfaces to prevent mixing with foreign matter.
C.
Arrange storage in a manner to provide easy access for inspection. Make periodic inspections
of stored products to assure that products are maintained under specified conditions, and free
from damage or deterioration.
D.
Protection After Installation: Provide substantial coverings as necessary to protect installed
products from damage from traffic and subsequent construction operations. Remove when no
longer needed.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 01600
FA4608-16-R-0013
Attachment 1
Page 18 of 79
SECTION 01700 - PROJECT CLOSEOUT
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of Contract, including General and Supplementary Conditions
and other Division 1 Specification Sections, apply to work of this Section.
DESCRIPTION OF REQUIREMENTS
A.
Definitions: Project closeout is the term used to describe certain collective project requirements,
indicating completion of the work that is to be fulfilled near the end of the contract time in
preparation for final acceptance and occupancy of the work by the Owner, as well as final
payment to the Contractor and the normal termination of the Contract.
B.
Specific requirements for individual units of work are included in the appropriate Sections in
Division 2 through 16.
1.3
CLOSEOUT SUBMITTALS
A.
Submit to Engineer for review, four copies each of the following items and other items as
specified. Approved copies will be transmitted to Owner by Engineer.
B.
Operation and Maintenance Data: Refer to Article titled "Operation and Maintenance Manuals"
hereinafter this Section.
C.
Record Drawings:
required).
D.
Release of Liens: AIA Form G706A, refer to Article 9.10 of the General Conditions.
E.
Consent of Surety to Final Payment:
General Conditions.
1.4
Refer to "Record Drawings" article hereinafter this section (one copy
AIA Form G707, refer to Article 9.10 of
OPERATION AND MAINTENANCE MANUALS
A.
Purpose: Operation and maintenance manuals will be used for training of, and use by,
the Owner and his employees in the operation and maintenance of the systems and related
equipment as specified below. A separate manual or chapter shall be prepared for instructions
of each class of equipment or system.
B.
Contents: Manuals shall contain the following information on each item of equipment:
1.
2.
3.
4.
Routine maintenance operations.
Complete operating instructions.
Service instructions.
Complete control wiring.
FA4608-16-R-0013
Attachment 1
Page 19 of 79
5.
6.
Emergency procedure.
Equipment warranties or guarantees.
C.
Preparation: The manuals shall be prepared to provide for the optimum operation and
maintenance of the various systems outlined above and equipment forming a part of these
systems. Manufacturer's literature and data shall be that of the actual equipment installed under
contract for the particular facility. Each manual containing the systems noted shall be bound in
one or more volumes as required for convenience in handling. In addition to "hard" (paper)
copy manuals, provide "electronic files" on CD or DVD in Microsoft® Office or Adobe Acrobat.
D.
Quantity: Provide 3 sets of O&M Manuals in D-type, 3 ring binders.
1.5
INSTRUCTIONS
A.
1.6
Instruct Owner's personnel in operation of all systems, mechanical, electrical, and other
equipment in accordance with respective Specification Sections and manufacturer's instructions.
RECORD DRAWINGS
A.
Mark-Up Procedure: During progress of work, maintain a white-print set of Contract Drawings
and shop drawings, with mark-up of actual installations which vary substantially from the work as
originally shown. Mark whatever drawing is most capable of showing actual physical condition,
fully and accurately. Where shop drawings are marked up, cross-reference on contract
drawings at corresponding location. Mark with erasable colored pencil, using separate colors
where feasible to distinguish between changes for different categories of work at same general
location. Mark-up important additional information which was either shown schematically or
omitted from original drawings. Give particular attention to information on work concealed,
which would be difficult to identify or measure and record at a later date. Note alternate
numbers, change order numbers, and similar identification.
B.
Submittal: At the conclusion of the Contract, the final set of record prints shall be prepared by
the Engineer from information obtained from the Contractor.
1.7
CLEANING UP
A.
No rubbish shall be allowed to accumulate or be allowed to remain on the premises or job site
beyond a reasonable length of time. Trash shall be removed from within the building and from
the site daily. Particular attention shall be given to these requirements.
B.
All rubbish shall be removed by means of chutes, hoists, or receptacles. Under no
circumstances shall any rubbish or waste be dropped or thrown from one level to another within
or outside the buildings. Immediately after unpacking materials, all packing case lumber and
other packing materials, excelsior, wrappings, and other like flammable wastes shall be
collected and removed from the buildings and premises. Burning of trash on the site will not be
permitted.
C.
Care shall be taken by all workmen not to mark, soil, or otherwise deface any finishes. In the
event that any finishes become defaced in any way by mechanics or workmen, the Contractor or
any of his sub-contractors shall clean and restore such surfaces to their original condition.
D.
Each subcontractor engaged upon the work shall bear his full responsibility for leaving all work in
a clean and proper condition, satisfactory to the Owner and the Engineer.
FA4608-16-R-0013
Attachment 1
Page 20 of 79
E.
Final Cleaning: Beside the general broom cleaning, the following cleaning shall be done just
before final acceptance of the work:
1.
2.
3.
Remove all labels not intended for permanent installation.
Remove all marks, stains, fingerprints, and other soil or dirt from all painted work,
and clean as required to leave in first class condition.
Clean all equipment removing all stains, paint, dirt, and dust.
F.
Upon completion of the work, the Contractor will be required to thoroughly clean the building site
and surrounding ground, and all trash and rubbish left by him in the course of construction of the
work shall be removed and disposed of off the site of work.
G.
Contractor shall haul off all debris from the site to legal disposal areas and dispose of all debris
and excess materials resulting from project work. No burning of material or debris shall be done
at site. In hauling material from the site, it shall be the responsibility of the Contractor to prevent
debris from dropping from vehicles and littering the site and any public thoroughfare.
1.8
SUBSTANTIAL COMPLETION
A.
1.9
Inspection and other procedures for Contractor to follow to process Contract through Substantial
Completion are specified in General and Supplementary Conditions, Articles 9.8 and 9.9.
FINAL INSPECTION
A.
Contractor shall submit written certification that:
1.
2.
3.
4.
5.
Contract Documents have been reviewed.
Project has been inspected for compliance with Contract Documents.
Work has been completed in accordance with Contract Documents.
Equipment and systems have been tested in presence of Owner's Representative and are
operational.
Project is completed, and ready for final inspection.
B.
Engineer will make final inspection after receipt of certification.
C.
Should Engineer consider that work is not finally complete, he will notify Contractor, in writing,
stating reasons. Contractor shall take immediate steps to remedy the stated deficiencies, and
send second written notice to Engineer certifying that work is complete. Engineer will reinspect
work.
1.10
A.
FINAL PAYMENT
Application for final payment shall be submitted together with documents specified in
General and Supplementary Conditions, Article 9.10 "Final Completion and Final Payment".
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 01700
FA4608-16-R-0013
Attachment 1
Page 21 of 79
SECTION 01710 - CLEANING
PART 1 - GENERAL
1.1
DESCRIPTION
A.
Work included: Throughout the construction period, maintain the buildings and site in a
standard of cleanliness as described in this Section.
B.
Related Work:
1.
2.
1.2
A.
Documents affecting work of this section include, but are not necessarily limited to,
General Conditions, Supplementary Conditions, and Sections in Division 1 of these
Specifications.
In addition to standards described in this Section, comply with requirements for cleaning
as described in pertinent other Sections of these Specifications.
QUALITY ASSURANCE
Conduct daily inspection, and more often if necessary, to verify that requirements for cleanliness
are being met.
PART 2 - PRODUCTS
2.1
A.
COMPATIBILITY
Use only the cleaning materials and equipment which are compatible with the surface being
cleaned, as recommended by the manufacturer of the material.
PART 3 - EXECUTION
3.1
A.
PROGRESS CLEANING
General:
1.
2.
3.
B.
Retain stored items in an orderly arrangement allowing maximum access, not impeding
traffic or drainage, and providing required protection of materials.
Do not allow accumulation of scrap, debris, waste material, and other items not required
for construction of this Work.
At least twice each month completely remove all scrap, debris, and waste material from
the site.
Site:
1.
Daily, and more often if necessary, inspect the site and pick up all scrap, debris, and
waste material. Weekly, and more often if necessary, inspect all arrangements of
materials, restock if necessary.
FA4608-16-R-0013
Attachment 1
Page 22 of 79
C.
Structures:
1.
2.
3.
4.
Weekly and more often in necessary, inspect the structures and remove all scrap, debris,
and waste material.
Weekly, and more often if necessary, sweep interior spaces clean.
Following the installation of finished floor materials, clean the finish floor daily at all times
while work is being performed.
Clean all surfaces, interior and exterior, and maintain a reasonably clean structure at all
times.
END OF SECTION 01710
FA4608-16-R-0013
Attachment 1
Page 23 of 79
SECTION 01732 - SELECTIVE DEMOLITION
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections, apply to this Section.
SUMMARY
A.
This Section includes the following:
1.
2.
B.
Related Sections include the following:
1.
2.
3.
1.3
Demolition and removal of selected portions of a building or structure.
Repair procedures for selective demolition operations.
Division 1 Section 01010, "Summary of Work," for use of the premises and phasing
requirements.
Division 1 Section 01500, "Temporary Facilities," for temporary construction and
environmental-protection measures for selective demolition operations.
Division 1 Section 01045, "Cutting and Patching," for cutting and patching procedures for
selective demolition operations.
DEFINITIONS
A.
Remove: Detach items from existing construction and legally dispose of them off-site,
unless indicated to be removed and salvaged or removed and reinstalled.
B.
Remove and Salvage: Detach items from existing construction and deliver them to Owner.
C.
Remove and Reinstall: Detach items from existing construction, prepare them for reuse,
and reinstall them where indicated.
D.
Existing to Remain: Existing items of construction that are not to be removed and that are not
otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.
1.4
MATERIALS OWNERSHIP
A.
1.5
Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise
indicated to remain Owner's property, demolished materials shall become Contractor's property
and shall be removed from Project site.
QUALITY ASSURANCE
A.
Refrigerant Recovery Technician Qualifications:
program.
Certified by an EPA-approved certification
FA4608-16-R-0013
Attachment 1
Page 24 of 79
B.
Regulatory Requirements:
Comply with governing EPA notification regulations before
beginning selective demolition. Comply with hauling and disposal regulations of authorities
having jurisdiction.
C.
Standards: Comply with ANSI A10.6 and NFPA 241.
D.
Pre-Demolition Conference: Conduct conference at Project site to review methods and
procedures related to selective demolition including, but not limited to, the following:
1.
2.
3.
4.
5.
1.6
Inspect and discuss condition of construction to be selectively demolished.
Review structural load limitations of existing structure.
Review and finalize selective demolition schedule and verify availability of materials,
demolition personnel, equipment, and facilities needed to make progress and avoid
delays.
Review requirements of work performed by other trades that rely on substrates exposed
by selective demolition operations.
Discuss select material to be salvaged by Owner.
PROJECT CONDITIONS
A.
Owner will occupy portions of building immediately adjacent to selective demolition area.
Conduct selective demolition so Owner's operations will not be disrupted. Provide not less than
72 hours' notice to Owner of activities that will affect Owner's operations.
B.
Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.
1.
C.
Owner assumes no responsibility for condition of areas to be selectively demolished.
1.
D.
Do not close or obstruct walkways, corridors, or other occupied or used facilities without
written permission from authorities having jurisdiction.
Conditions existing at time of inspection for bidding purpose will be maintained by Owner
as far as practical.
Hazardous Materials: It is not expected that hazardous materials will be encountered in the
Work.
1.
If materials suspected of containing hazardous materials are encountered, do not disturb;
immediately notify Architect and Owner. Hazardous materials will be removed by Owner
under a separate contract.
E.
Storage or sale of removed items or materials on-site will not be permitted.
F.
Utility Service: Maintain existing utilities on roof in service unless indicated to be removed and
protect them against damage during selective demolition operations.
1.
G.
Maintain fire-protection facilities in service during selective demolition operations.
Notify Engineer of discrepancies between existing conditions and drawings before proceeding
with selective demolition.
FA4608-16-R-0013
Attachment 1
Page 25 of 79
1.7
WARRANTY
A.
Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or
damaged during selective demolition, by methods and with materials so as not to void existing
warranties.
PART 2 - PRODUCTS
2.1
REPAIR MATERIALS
A.
Use repair materials identical to existing materials.
1.
2.
B.
If identical materials are unavailable or cannot be used for exposed surfaces,
use materials that visually match existing adjacent surfaces to the fullest extent possible.
Use materials whose installed performance equals or surpasses that of existing
materials.
Comply with material and installation requirements specified in individual Specification Sections.
PART 3 - EXECUTION
3.1
EXAMINATION
A.
Verify that utilities have been disconnected and capped.
B.
Survey existing conditions and correlate with requirements indicated to determine extent of
selective demolition required.
C.
Inventory and record the condition of any items to be removed and salvaged.
D.
When unanticipated mechanical, electrical, or structural elements that conflict with intended
function or design are encountered, investigate and measure the nature and extent of conflict.
Promptly submit a written report to Engineer.
E.
Perform surveys as the work progresses to detect hazards resulting from selective demolition
activities.
3.2
UTILITY SERVICES
A.
Existing Utilities: Maintain services indicated to remain and protect them against damage
during selective demolition operations.
B.
Do not interrupt existing utilities serving occupied or operating facilities unless authorized in
writing by Owner and authorities having jurisdiction.
1.
C.
Provide at least 72 hours' notice to Owner if shutdown of service is required during
changeover.
Utility Requirements: Locate, identify, disconnect, and seal or cap off indicated utilities serving
areas to be selectively demolished.
FA4608-16-R-0013
Attachment 1
Page 26 of 79
1.
2.
3.
D.
3.3
Where required, Owner will arrange to shut off indicated utilities when requested by
Contractor.
If utility services are required to be removed, relocated, or abandoned, before proceeding
with selective demolition provide temporary utilities that bypass area of selective
demolition and that maintain continuity of service to other parts of building.
Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal
remaining portion of pipe or conduit after bypassing.
Utility Requirements: Refer to Division 15 and 16 Sections for shutting off, disconnecting,
removing, and sealing or capping utilities. Do not start selective demolition work until utility
disconnecting and sealing have been completed and verified in writing.
PREPARATION
A.
Site Access and Temporary Controls: Conduct selective demolition and debris-removal
operations to ensure minimum interference with roads, streets, walks, walkways, and other
adjacent occupied and used facilities.
1.
2.
3.
B.
Temporary Facilities: Provide temporary barricades and other protection required to prevent
injury to people and damage to adjacent buildings and facilities to remain.
1.
2.
3.
4.
C.
Provide protection to ensure safe passage of people around selective demolition area
and to and from occupied portions of building.
Provide temporary weather protection, during interval between selective demolition of
existing construction on exterior surfaces and new construction, to prevent water leakage
and damage to structure and interior areas.
Protect walls, ceilings, floors, and other existing finish work that are to remain or that are
exposed during selective demolition operations.
Cover and protect furniture, furnishings, and equipment that have not been removed.
Temporary Shoring: Provide and maintain interior bracing or structural support to preserve
stability and prevent movement, settlement, or collapse of construction to remain, and to
prevent unexpected or uncontrolled movement or collapse of construction being demolished.
1.
3.4
Do not close or obstruct streets, walks, walkways, or other adjacent occupied or used
facilities without permission from Owner and authorities having jurisdiction.
Provide alternate routes around closed or obstructed traffic ways if required by governing
regulations.
Erect temporary protection, such as walks, fences, railings, canopies, and covered
passageways, where required by authorities having jurisdiction.
Protect existing site improvements, appurtenances, and landscaping to remain.
Strengthen or add new supports during progress of selective demolition and before new
rooftop air conditioning units are placed on roof.
POLLUTION CONTROLS
A.
Dust Control: Use temporary enclosures and other suitable methods to limit spread of dust and
dirt.
1.
Do not use water when it may damage existing construction or create hazardous or
objectionable conditions.
FA4608-16-R-0013
Attachment 1
Page 27 of 79
2.
B.
Disposal: Remove and transport debris in a manner that will prevent spillage on adjacent
surfaces and areas.
1.
C.
3.5
Wet mop floors to eliminate trackable dirt and wipe down walls and doors of demolition
enclosure. Vacuum carpeted areas.
Remove debris from elevated portions of building by chute, hoist, or other device that will
convey debris to grade level in a controlled descent.
Cleaning: Clean adjacent structures and improvements of dust, dirt, and debris caused by
selective demolition operations. Return adjacent areas to condition existing before selective
demolition operations began.
SELECTIVE DEMOLITION
A.
General: Demolish and remove existing construction only to the extent required by new
construction and as indicated. Use methods required to complete the Work within limitations of
governing regulations and as follows:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Proceed with selective demolition systematically, from higher to lower level.
Complete selective demolition operations above each floor or tier before disturbing
supporting members on the next lower level.
Neatly cut openings and holes plumb, square, and true to dimensions required.
Use cutting methods least likely to damage construction to remain or adjoining
construction. Use hand tools or small power tools designed for sawing or grinding, not
hammering and chopping, to minimize disturbance of adjacent surfaces.
Temporarily cover openings to remain.
Cut or drill from the exposed or finished side into concealed surfaces to avoid marring
existing finished surfaces.
Do not use cutting torches until work area is cleared of flammable materials.
At concealed spaces, such as duct and pipe interiors, verify condition and contents of
hidden space before starting flame-cutting operations. Maintain fire watch and portable
fire-suppression devices during flame-cutting operations.
Maintain adequate ventilation when using cutting torches.
Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and
promptly dispose of off-site.
Remove structural framing members and lower to ground by method suitable to avoid
free fall and to prevent ground impact or dust generation.
Locate selective demolition equipment and remove debris and materials so as not to
impose excessive loads on supporting walls, floors, or framing.
Dispose of demolished items and materials promptly.
Return elements of construction and surfaces that are to remain to condition existing
before selective demolition operations began.
B.
Existing Facilities: Comply with building manager's requirements for using and protecting
building facilities during selective demolition operations.
C.
Existing Items to Remain: Protect construction indicated to remain against damage and soiling
during selective demolition. When permitted by Engineer, items may be removed to a suitable,
protected storage location during selective demolition and cleaned and reinstalled in their
original locations after selective demolition operations are complete.
D.
Roofing: Remove no more existing roofing than can be covered in one day by new roofing.
Refer to applicable Division 7 Section for new roofing requirements.
FA4608-16-R-0013
Attachment 1
Page 28 of 79
E.
3.6
Air Conditioning Equipment: Remove equipment without releasing refrigerants.
PATCHING AND REPAIRS
A.
General: Promptly repair damage to adjacent construction caused by selective demolition
operations.
B.
Patching: Comply with Division 1 Section 01045, "Cutting and Patching."
C.
Repairs: Where repairs to existing surfaces are required, patch to produce surfaces suitable for
new materials.
1.
Completely fill holes and depressions in existing masonry walls that are to remain with an
approved masonry patching material applied according to manufacturer's written
recommendations.
D.
Finishes: Restore exposed finishes of patched areas and extend restoration into adjoining
construction in a manner that eliminates evidence of patching and refinishing.
E.
Ceilings: Patch, repair, or re-hang existing ceilings as necessary to provide an even-plane
surface of uniform appearance.
3.7
DISPOSAL OF DEMOLISHED MATERIALS
A.
General: Promptly dispose of demolished materials. Do not allow demolished materials to
accumulate on-site.
B.
Burning: Do not burn demolished materials.
C.
Disposal: Transport demolished materials off Owner's property and legally dispose of them.
END OF SECTION 01732
FA4608-16-R-0013
Attachment 1
Page 29 of 79
SECTION 03300 - CAST-IN-PLACE CONCRETE
PART 1 - GENERAL
1.1
DESCRIPTION
A.
Work included: Provide cast-in-place concrete, including formwork and reinforcement, where
shown on drawings, as specified herein, and as needed for a complete and proper installation.
B.
Related work:
1.
1.2
Documents affecting work of this Section include, but are not necessarily limited to, General
Conditions, Supplementary Conditions, and Sections in Division 1 of these Specifications.
QUALITY ASSURANCE
A.
Use adequate numbers of skilled workmen who are thoroughly trained and experienced in the
necessary crafts and who are completely familiar with the specified requirements and the methods
needed for proper performance of the work of this Section.
B.
Comply with "Specifications for Structural Concrete for Buildings," ACI 301, except as may be
modified herein.
C.
Provide access for, and cooperate with, the inspector and testing laboratory.
D.
Do not commence placement of concrete until mix designs have been reviewed and approved by
the Engineer and all governmental agencies having jurisdiction, and until copies of the approved
mix designs are at the job site and the batch plant.
1.3
SUBMITTALS
A.
Secure concrete mix designs from the testing laboratory in accordance with provisions of testing,
and submit to the Engineer for review and approval.
B.
Distribute approved mix designs to testing laboratory, batch plant, job site, and governmental
agencies having jurisdiction.
1.4
A.
1.5
A.
PRODUCT HANDLING
Comply with pertinent provisions of Section 01600.
REFERENCE STANDARDS
American Concrete Institute (ACI)
1.
2.
3.
ACI 301 – Standard Specification for Structural Concrete
ACI 315 – Details and Detailing of Concrete Reinforcement
ACI 318 – Building Code Requirements for Reinforced Concrete
FA4608-16-R-0013
Attachment 1
Page 30 of 79
4.
B.
American Plywood Association (APA)
1.
C.
ACI 347 – Formwork for Concrete
Material grades and designations as specified.
Concrete Reinforcing Steel Institute (CRSI)
1.
Manual of Standard Practice
PART 2 - PRODUCTS
2.1
FORMS
A.
Design, erect, support, brace, and maintain formwork so it will safely support vertical and lateral
loads which might be applied until such loads can be supported safely by the concrete structure.
B.
Construct forms to the exact sizes, shapes, lines, and dimensions shown, and as required to
obtain accurate alignment, location, grades, and level and plumb work in the finished structure.
C.
Design of formwork is the Contractor's responsibility.
D.
Provide formwork sufficiently tight to prevent leakage of cement paste during concrete placement.
Solidly butt joints, and provide backup material at joints as required to prevent leakage and prevent
fins.
E.
Do not disturb or remove forms until the concrete has hardened sufficiently to permit form removal
with complete safety.
2.2
MOISTURE BARRIER
A.
Where so indicated on the Drawings, provide a moisture barrier consisting of:
1.
2.3
A.
"Visqueen" or equal 6 mil thick plastic sheeting, with all joints taped and sealed.
REINFORCEMENT
Comply with the following minimums:
1.
2.
3.
Bars: ASTM A615, grade 60 unless otherwise shown on the Drawings, using deformed
bars for number 3 and larger;
Welded wire fabric: ASTM A185;
Bending: ACI 318.
B.
Fabricate reinforcement to the required shapes and dimensions, within fabrication tolerances
stated in the CRSI "Manual of Standard Practices".
C.
Do not use reinforcement having any of the following defects:
1.
Bar lengths, depths, or bends exceeding the specified fabricating tolerances.
FA4608-16-R-0013
Attachment 1
Page 31 of 79
2.
3.
2.4
Bends or kinks not indicated on the Drawings or required for the Work;
Bars with cross-section reduced due to excessive rust or other causes.
CONCRETE
A.
Comply with the following as minimums:
1.
2.
3.
4.
5.
Portland Cement: ASTM C150, type I or II, low alkali.
Aggregate, general:
a.
ASTM C33, uniformly graded and clean,
b.
Do not use aggregate known to cause excessive shrinkage.
Aggregate, coarse: Crushed rock or washed gravel with minimum size between 3/4" and
1-1/4", and with a maximum size number 4.
Aggregate, fine: Natural washed sand of hard and durable particles varying from fine to
particles passing a 3/8" screen, of which at least 12% shall pass a 50-mesh screen.
Water: Clean and potable.
B.
Provide concrete with the compressive strengths shown on the Drawings. When such strengths
are not shown on the Drawings, provide a minimum compressive strength of 3000 psi.
C.
Surface treatment:
1.
D.
Color Pigment: Add color pigment to concrete mixture according to manufacturer’s written
instructions and to result in hardened concrete color consistent with approved mockup.
1.
2.5
A.
Construction joints:
Do not use horizontal construction joints except as may be shown on the Drawings.
If additional construction joints are found to be required, secure the Engineer's approval of
joint design and location prior to start of concrete placement.
Expansion joints:
1.
2.
3.
2.6
Add Davis No. 161 Red Oxide dye, sprinkle and float dye into concrete encasement of
primary feeder conduits.
JOINTS AND JOINT ACCESSORIES
1.
2.
B.
Where "sealer" or "hardener" is called for on the Drawings, provide "Ashford Formula"
manufactured by Curecrete Chemical Company of Orem, Utah.
Do not permit reinforcement or other embedded metal items that are being bonded with
concrete (except dowels) to extend continuously through any expansion joints.
Fill expansion joints full depth with premolded joint filler conforming to ASTM D1752, Type
III.
Expansion joint dowels shall be smooth steel conforming to ASTM A675, Grade 70. Bars
shall be coated with bond breaker on the expansion end of the dowel. Expansion caps shall
be provided on the expansion end. Caps shall allow for at least 1- ½ ” of expansion.
GROUT
FA4608-16-R-0013
Attachment 1
Page 32 of 79
A.
General: This section applies to all nonshrink cementitious grout and nonshrink epoxy grout. All
grout for reinforced masonry is included in Division 4.
B.
Nonshrink cementitious grouts shall meet or exceed requirements of ASTM C1107, Grades B or C
and CRD C-621.
1.
2.
3.
C.
Nonshrink epoxy grouts shall be pre-proportioned, three component, 100% solids systems
consisting of epoxy resin, hardener, and blended aggregate.
1.
2.
3.
2.7
A.
Grouts shall be portland cement based, contain a pre-proportioned blend of selected
aggregates and shrinkage-compensating agents, and shall require only the addition of
water.
Approved products are SikaGrout 212 by Sika Corp.; Set Grout by Master Builders, Inc.;
Gilco Construction Grout by Gifford Hill & Co.; Euco NS by the Euclid Chemical Co.; NBEC
Grout by U.S. Grout Corp.; or equal.
Installation: Place grout in designated areas in a manner which will avoid segregation or
entrapment of air. Do not vibrate grout to release air or to consolidate the material. Place
grout rapidly and continuously to avoid cold joints. Do not add additional water to the mix
after initial stiffening. Keep grout moist and within its recommended placement temperature
range for at least 24 hours after placement or longer if recommended by manufacturer.
It shall have a compressive strength of 14,000 psi in 7 days when tested in conformity with
ASTM C531.
Approved products are Ceilcote 648 CP by Master Builders Inc.; Five Star Epoxy Grout by
U.S. Grout Corp.; Sikadur 42 Grout-Pak by Sika Corp.; High Strength Epoxy Grout by the
Euclid Chemical Co.; or equal.
Installation: Place grout in the designated areas in a manner which will avoid trapping air.
Placement methods shall ensure the filling of all spaces and provide full contact between the
grout and adjoining surfaces. Provide grout holes as necessary. Finish grout by puddling to
cover all aggregate and provide a smooth finish. Epoxy grouts are self-curing and do not
require the application of water. Maintain the formed grout within its recommended
placement temperature range for at least 24 hours after placing, or longer if recommended
by the manufacturer.
OTHER MATERIALS
Provide other materials, not specifically described but required for a complete and proper
installation, as selected by the Contractor subject to the approval of the Engineer.
PART 3 - EXECUTION
3.1
A.
3.2
A.
SURFACE CONDITIONS
Examine the areas and conditions under which work of this Section will be performed. Correct
conditions detrimental to timely and proper completion of the Work. Do not proceed until
unsatisfactory conditions are corrected.
REINFORCEMENT
Comply with the following, as well as the specified standards, for details and methods of
FA4608-16-R-0013
Attachment 1
Page 33 of 79
reinforcing placement and supports.
1.
Clean reinforcement and remove loose dust and mill scale, earth, and other materials which
reduce bond or destroy bond with concrete.
2.
Position, support, and secure reinforcement against displacement by forms, construction,
and the concrete placement operations.
3.
Place reinforcement to obtain the required coverage for concrete protection.
4.
Install welded wire fabric in as long lengths as practicable, lapping adjoining pieces one full
mesh minimum.
5.
Unless otherwise shown on the Drawings, or required by governmental agencies having
jurisdiction, lap bars 24 diameters minimum.
6.
No reinforcing steel bars shall be welded either during fabrication or erection unless
specifically shown on drawings, specified herein, or unless prior approval has been obtained
from the engineer.
3.3
EMBEDDED ITEMS
A.
Do not embed piping, other than electrical conduit, in structural concrete.
1.
2.
B.
3.4
Locate conduit to maintain maximum strength of the structure.
Increase the thickness of the concrete if the outside diameter of the conduit exceeds 30% of
the thickness of the concrete.
Set bolts, inserts, and other required items in the concrete, accurately secured so they will not be
displaced, and in the precise locations needed.
MIXING CONCRETE
A.
Transit mix the concrete in accordance with provisions of ASTM C94.
B.
Mixing water:
1.
2.
3.
4.
C.
3.5
At the batch plant, withhold 2-1/2 gal of water per cu yd of concrete.
Upon arrival at the job site, add all or part of the withheld water (as required for proper
slump) before the concrete is discharged from the mixer.
Mix not less than five minutes after the withheld water has been added, and not less than
one minute of that time immediately prior to discharge of the batch.
Unless otherwise directed, provide 15 minutes total mixing time per batch after first addition
of water.
Do not use concrete that has stood for over 30 minutes after leaving the mixer, or concrete that is
not placed within 60 minutes after water is first introduced into the mix.
PLACING CONCRETE
A.
Preparation:
1.
2.
3.
4.
B.
Remove foreign matter accumulated in the forms.
Rigidly close openings left in the formwork.
Wet wood forms sufficiently to tighten up cracks, Wet other material sufficiently to maintain
workability of the concrete.
Use only clean tools.
Conveying:
FA4608-16-R-0013
Attachment 1
Page 34 of 79
1.
2.
3.
4.
C.
Placing concrete in forms:
1.
2.
D.
2.
3.
4.
A.
General:
2.
3.
A.
Deposit and consolidate concrete slabs in a continuous operation, within limits of
construction joints, until the placing of a panel or section is complete.
Bring slab surfaces to the correct, level with a straightedge, and then strike off.
Use bullfloats or darbies to smooth the surface, leaving the surface free from bumps and
hollows.
Do no sprinkle water on the plastic surface. Do not disturb the slab surface prior to start of
finishing.
CONSOLIDATION
1.
3.7
Deposit concrete in horizontal layers not deeper than 24", and avoid inclined construction
joints.
Remove temporary spreaders in forms when concrete has reached the elevation of the
spreaders.
Placing concrete slabs:
1.
3.6
Perform concrete placing at such a rate that concrete which is being integrated with fresh
concrete is still plastic.
Deposit concrete as nearly as practicable in its final locations so as to avoid separation due
to rehandling and flowing.
Do not use concrete which becomes non-plastic and unworkable, or does not meet required
quality control limits, or has been contaminated by foreign materials.
Remove rejected concrete from the job site.
Consolidate each layer of concrete immediately after placing, by use of internal concrete
vibrators supplemented by hand spading, rodding, or tamping.
Do not vibrate forms or reinforcement.
Do not use vibrators to transport concrete inside the forms.
CONCRETE FINISHING
Except as may be shown otherwise on the Drawings, provide the following finishes at the indicated
locations.
1.
2.
3.
Float finish:
a.
Apply to monolithic slab surfaces that are to receive trowel finish and other finishes
specified hereinafter;
Trowel finish:
a.
Apply to monolithic slab surfaces that are to be exposed to view, unless otherwise
shown, and to slab surfaces that are to be covered with resilient flooring, carpeting,
paint, or other thin-film finish coating system.
Non-slip broom finish:
a.
Apply to walks, stairs, drives, ramps, and similar pedestrian and vehicular areas.
FA4608-16-R-0013
Attachment 1
Page 35 of 79
3.8
A.
REMEDIAL WORK
Repair or replace deficient work as directed by the Engineer and at no additional cost to the
Owner.
END OF SECTION 03300
FA4608-16-R-0013
Attachment 1
Page 36 of 79
SECTION 16050 - BASIC ELECTRICAL MATERIALS AND METHODS
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
B.
Codes and Standards: Where indicated, the referenced edition shall govern.
indicated, the latest edition shall govern.
1.2
Where not
SUMMARY
A.
1.3
This Section includes the following:
1.
Supporting devices for electrical components.
2.
Electrical identification.
3.
Concrete equipment bases.
4.
Electrical demolition.
5.
Touchup painting.
SUBMITTALS
A.
1.4
Field Test Reports:
requirements.
Indicate and interpret test results for compliance with performance
DEFINITIONS
A.
General Explanation: A substantial amount of the contract document specification language
constitutes specific definitions for terms found in other contract documents, including the
drawings which must be recognized as diagrammatic in nature and not completely descriptive of
the requirements indicated thereon. Certain terms used repetitiously in the contract documents
are defined generally in this article.
B.
General Requirements: The provisions or requirements of the Division-1 sections. The General
Requirements apply to the entire work of the Contract, and where so indicated, to other
elements of work which are included in the project.
C.
Indicated: The term "Indicated" is a cross reference to details, notes or schedules on the
drawings, other paragraphs or schedules in the specifications, and similar means of recording
requirements in the contract documents. Where terms such as "shown", "noted", "scheduled"
and "specified" are used in lieu of "indicated", it is for the purpose of helping the reader locate
the cross reference, and no limitation of location is intended except as specifically noted.
D.
Directed, Requested, Etc.: Where not otherwise explained, terms such as "directed",
"requested", "authorized", "selected", "approved", "required", "accepted", and "permitted" mean
"directed by the Contracting Officer’s Representative", "requested by the Contracting Officer’s
Representative" etc. However, no such implied meaning will be interpreted to extend the
Contracting Officer’s Representative's responsibility into the Contractor's area of construction
supervision.
E.
Refer: Used to indicate that the subject is defined or specified in further detail at another
location in the contract documents, or elsewhere as indicated. Except as otherwise noted,
"refer" does not imply that the Contractor must purchase or subcontract the subject work in any
special manner.
F.
Approve: Where used in conjunction with the Contracting Officer’s Representative's response
to submittals, requests, applications, inquiries, reports and claims by the Contractor, the
meaning of the term "approved" will be held to the limitations of the Contracting Officer’s
FA4608-16-R-0013
Attachment 1
Page 37 of 79
Representative's responsibilities and duties as specified in the General and Supplementary
Conditions. In no case will "approval" by the Contracting Officer’s Representative be interpreted
as a release of the Contractor from responsibilities to fulfill the requirements of the contract
documents.
G.
Project Site: The space available to the Contractor for the performance of the work, either
exclusively or in conjunction with others performing other work as part of the project. The extent
of the project site may or may not be identical with the description of the land upon which the
project is to be built.
H.
Furnish: Except as otherwise defined in greater detail, the term "furnish" is used to mean
supply and deliver to the project site, ready for unloading, unpacking, assembly, installation,
etc., as applicable in each instance.
I.
Install: Except as otherwise defined in greater detail, the term "install" is used to describe
operations of the project site including unloading, unpacking, assembly, erection, placing,
anchoring, connecting utilities, applying, working to dimension, finishing, curing, protecting,
cleaning and similar operations, as applicable in each instance.
J.
Provide: Except as otherwise defined in greater detail, the term "provide" means furnish and
install, complete and ready for the intended use, as applicable in each instance.
K.
Installer: The entity (person or firm) engaged by the Contractor or its subcontractor or subsubcontractor for the performance of a particular unit of work at the project site, including
installation, erection, application and similar required operations. It is a general requirement
that such entities (Installers) be expert in the operations they are engaged to perform.
1.5
QUALITY ASSURANCE
A.
Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
B.
Comply with NFPA 70 (2011).
1.6
COORDINATION
A.
The electrical plans and specifications are a portion of the entire project. Other portions of the
project contain information and requirements that will affect the electrical work. It is the
responsibility of the Electrical Contractor to review all of the Contract documents and to include
those requirements in the bid.
B.
Coordinate chases, slots, inserts, sleeves, and openings with general construction work and
arrange in building structure during progress of construction to facilitate the electrical
installations that follow.
1.
Set inserts and sleeves in poured-in-place concrete, masonry work, and other structural
components as they are constructed.
PART 2 - PRODUCTS
2.1
SUPPORTING DEVICES
A.
Material: Cold-formed steel, with corrosion-resistant coating acceptable to authorities having
jurisdiction.
B.
Metal Items for Use Outdoors or in Damp Locations: Hot-dip galvanized steel.
C.
Slotted-Steel Channel Supports: Flange edges turned toward web, and 9/16-inch- (14-mm-)
diameter slotted holes at a maximum of 2 inches (50 mm) o.c., in webs.
FA4608-16-R-0013
Attachment 1
Page 38 of 79
2.2
ELECTRICAL IDENTIFICATION
A.
Identification Devices: A single type of identification product for each application category. Use
colors prescribed by ANSI A13.1, NFPA 70, and these Specifications.
B.
Cable Labels: Comply with ANSI A13.1, Table 3, for minimum size of letters for legend and
minimum length of color field for each cable size.
1.
Cable Tags in Manholes: Provide tags for each power cable or wire located in manholes.
The tags shall be polyethylene. Do not provide handwritten letters. The first position on
the power cable tag shall denote the voltage. The second through sixth positions on the
tag shall identify the circuit. The next to last position shall denote the phase of the circuit
and shall include the Greek "phi" symbol. The last position shall denote the cable size.
As an example, a tag could have the following designation: "11.5 NAS 1-8(PhaseA)500,"
denoting that the tagged cable is on the 11.5kV system circuit number NAS 1-8,
underground, Phase A, sized at 500 kcmil.
2.
Provide tags of polyethylene that have an average tensile strength of 3250 pounds per
square inch; and that are 0.08 inch thick (minimum), non-corrosive non-conductive;
resistive to acids, alkalis, organic solvents, and salt water; and distortion resistant to 170
degrees F. Provide 0.05 inch (minimum) thick black polyethylene tag holder. Provide a
one-piece nylon, self-locking tie at each end of the cable tag. Ties shall have a minimum
loop tensile strength of 175 pounds. The cable tags shall have black block letters,
numbers, and symbols one inch high on a yellow background. Letters, numbers, and
symbols one inch high on a yellow background. Letters, numbers, and symbols shall not
fall off or change positions regardless of the cable tags' orientation.
C.
Colored Adhesive Marking Tape for Wires, and Cables: Self-adhesive vinyl tape, not less than
3/4 inch wide by 3 mils thick (18 mm wide by 0.08 mm thick).
D.
Underground Warning Tape: Permanent, bright-colored, continuous-printed, vinyl tape with the
following features:
1.
Not less than 6 inches wide by 4 mils thick (150 mm wide by 0.102 mm thick).
2.
Compounded for permanent direct-burial service.
3.
Embedded continuous metallic strip or core.
4.
Printed legend that indicates type of underground line.
E.
Tape Markers for Wire: Vinyl or vinyl-cloth, self-adhesive, wraparound type with preprinted
numbers and letters.
F.
Engraved-Plastic Labels, Signs, and Instruction Plates: Engraving stock, melamine plastic
laminate punched or drilled for mechanical 1/8-inch (3.2-mm) minimum thickness for larger
sizes. Engraved legend in black letters on white background. Minimum size shall be one by 2.5
inches.
G.
Exterior Warning and Caution Signs: Comply with 29 CFR, Chapter XVII, Part 1910.145.
Weather-resistant, nonfading, preprinted, cellulose-acetate butyrate signs with 0.0396-inch (1mm), galvanized-steel backing, with colors, legend, and size appropriate to the application. 1/4inch (6-mm) grommets in corners for mounting. Provide warning signs for the enclosures of
electrical equipment having a nominal rating exceeding 600 volts.
1.
When the enclosure integrity of such equipment is specified to be in accordance with
NEMA C57.12.28 or NEMA C57.12.29, such as for pad-mounted transformers and padmounted SF6 switches, provide self-adhesive warning signs on the outside of the high
voltage compartment door(s).
2.
Sign shall be a decal and shall have nominal dimensions of 7 by 10 inches with the
legend "DANGER HIGH VOLTAGE" printed in two lines of nominal 2 inch high letters.
The word "DANGER" shall be in white letters on a red background and the words "HIGH
VOLTAGE" shall be in black letter on a white background. Decal shall be Panduit No.
PPSO710D72 or approved equal.
H.
Fasteners for Nameplates and Signs: Self-tapping, stainless-steel screws or No. 10/32
stainless-steel machine screws with nuts and flat and lock washers.
FA4608-16-R-0013
Attachment 1
Page 39 of 79
2.3
CONCRETE BASES
A.
Concrete Forms and Reinforcement Materials: As specified in Division 3 Section "Cast-in-Place
Concrete."
B.
Concrete: 3000-psi (20.7-MPa), 28-day compressive strength as specified in Division 3 Section
"Cast-in-Place Concrete."
2.4
TOUCHUP PAINT
A.
For Equipment: Equipment manufacturer's paint selected to match installed equipment finish.
B.
Galvanized Surfaces: Zinc-rich paint recommended by item manufacturer.
PART 3 - EXECUTION
3.1
ELECTRICAL EQUIPMENT INSTALLATION
A.
Clearances: Coordinate with existing conditions to maintain code required clearances above,
below and around electrical equipment.
B.
Equipment: Install to facilitate service, maintenance, and repair or replacement of components.
Connect for ease of disconnecting, with minimum interference with other installations.
3.2
ELECTRICAL SUPPORTING DEVICE APPLICATION
A.
Damp Locations and Outdoors: Hot-dip galvanized materials or nonmetallic, U-channel system
components.
B.
Selection of Supports: Comply with manufacturer's written instructions.
C.
Strength of Supports: Adequate to carry present and future loads, times a safety factor of at
least four; minimum of 200-lb (90-kg) design load.
3.3
SUPPORT INSTALLATION
A.
3.4
Install support devices to securely and permanently fasten and support electrical components.
IDENTIFICATION MATERIALS AND DEVICES
A.
Install at locations for most convenient viewing without interference with operation and
maintenance of equipment.
B.
Coordinate names, abbreviations, colors, and other designations used for electrical
identification with corresponding designations indicated in the Contract Documents or required
by codes and standards. Use consistent designations throughout Project.
C.
Self-Adhesive Identification Products: Clean surfaces before applying.
D.
Install continuous underground plastic markers during trench backfilling, for exterior
underground power, lines located directly above power lines. Locate 6 to 8 inches (150 to 200
mm) below finished grade. If width of multiple lines installed in a common trench or concrete
envelope does not exceed 16 inches (400 mm), overall, use a single line marker.
E.
Install warning, caution, and instruction signs where required to comply with 29 CFR,
Chapter XVII, Part 1910.145, and where needed to ensure safe operation and maintenance of
electrical systems and of items to which they connect. Install engraved plastic-laminated
instruction signs with approved legend where instructions are needed for system or equipment
operation. Install metal-backed butyrate signs for outdoor items.
FA4608-16-R-0013
Attachment 1
Page 40 of 79
3.5
CONCRETE BASES
A.
Construct concrete bases of dimensions indicated, but not less than 12 inches larger, in both
directions, than supported unit. Follow supported equipment manufacturer's anchorage
recommendations and setting templates for anchor-bolt and tie locations, unless otherwise
indicated. Use 3000-psi (20.7-MPa), 28-day compressive-strength concrete and reinforcement
as specified in Division 3 Section "Cast-in-Place Concrete."
B.
Block out windows. After curing blocks removed and windows filled with gravel to within 1” of
top and capped with mortar, caulk around all entrances and around mortar to prevent ant entry.
3.6
DEMOLITION
A.
Protect existing electrical equipment and installations not indicated to be removed. If damaged
or disturbed in the course of the Work, remove damaged portions and install new products of
equal capacity, quality, appearance and functionality.
B.
Accessible Work: Remove exposed electrical equipment and installations, indicated to be
demolished, in their entirety.
C.
Abandoned Work: Cut and remove buried raceway and wiring, indicated to be abandoned in
place, 2 feet (610 mm) below grade.
D.
Existing Work to Remain: Maintain feed, or provide new feed to equipment and devices that are
not being removed.
E.
Remove demolished material from Project site.
F.
Remove, store, clean, reinstall, reconnect, and make operational components indicated for
relocation.
G.
Interruption of Existing Electric Service: Do not interrupt feed to any service, feeder or branch
circuit feeding facilities occupied by Contracting Officer’s Representative or others unless
permitted under the following conditions and then only after arranging to provide temporary
electric service where required according to requirements indicated:
1.
Notify Contracting Officer’s Representative no fewer than seven days in advance of
proposed interruption of electrical service.
2.
Do not proceed with interruption of electrical service without Contracting Officer’s
Representative's written permission.
3.7
FIELD QUALITY CONTROL
A.
3.8
Inspect installed components for damage and faulty work, including the following:
1.
Supporting devices for electrical components.
2.
Electrical identification.
3.
Concrete bases.
4.
Electrical demolition.
5.
Touchup painting.
REFINISHING AND TOUCHUP PAINTING
A.
Refinish and touch up paint.
1.
Clean damaged and disturbed areas and apply primer, intermediate, and finish coats to
suit the degree of damage at each location.
2.
Follow paint manufacturer's written instructions for surface preparation and for timing and
application of successive coats.
3.
Repair damage to galvanized finishes with zinc-rich paint recommended by
manufacturer.
4.
Repair damage to PVC or paint finishes with matching touchup coating recommended by
manufacturer.
FA4608-16-R-0013
Attachment 1
Page 41 of 79
3.9
CLEANING AND PROTECTION
A.
Upon completion of installation, inspect exposed finish. Remove burrs, dirt, paint spots, and
construction debris.
B.
Protect equipment and installations and maintain conditions to ensure that coatings, finishes,
and are without damage or deterioration at time of Substantial Completion.
END OF SECTION 16050
FA4608-16-R-0013
Attachment 1
Page 42 of 79
SECTION 16060 - GROUNDING AND BONDING
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
SUMMARY
A.
1.3
This Section includes grounding of electrical systems and equipment in addition to overhead
line grounding. Grounding requirements specified in this Section may be supplemented by
special requirements of systems described in other Sections.
SUBMITTALS
A.
Product Data: For each type of product indicated.
B.
Field Test Reports: Submit written test reports to include the following:
1.
Test procedures used.
2.
Test results that comply with requirements.
3.
Results of failed tests and corrective action taken to achieve test results that comply with
requirements.
1.4
QUALITY ASSURANCE
A.
Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70
(2011), Article 100, by a testing agency acceptable to authorities having jurisdiction, and
marked for intended use.
1.
Comply with UL 467.
PART 2 - PRODUCTS
2.1
MANUFACTURERS
A.
2.2
Manufacturers: Subject to compliance with requirements, provide products by one of the
following:
1.
Grounding Conductors, Cables, Connectors, and Rods:
a.
Apache Grounding/Erico Inc.
b.
Chance/Hubbell.
c.
Copperweld Corp.
d.
Erico Inc.; Electrical Products Group.
e.
Ideal Industries, Inc.
f.
ILSCO.
g.
Kearney/Cooper Power Systems.
h.
O-Z/Gedney Co.; a business of the EGS Electrical Group.
i.
Raco, Inc.; Division of Hubbell.
j.
Thomas & Betts, Electrical.
GROUNDING CONDUCTORS
A.
Material: Copper.
B.
Bare Copper Conductors: Comply with the following:
1.
Solid Conductors: ASTM B 3.
2.
Stranded Conductors: ASTM B8.
FA4608-16-R-0013
Attachment 1
Page 43 of 79
2.3
CONNECTOR PRODUCTS
A.
Comply with IEEE 837 and UL 467; listed for use for specific types, sizes, and combinations of
conductors and connected items.
B.
Bolted Connectors: Bolted-pressure-type connectors, or compression type.
C.
Welded Connectors:
written instructions.
2.4
Exothermic-welded type, in kit form, and selected per manufacturer's
GROUNDING ELECTRODES
A.
Ground Rods: Copper-clad steel.
1.
Size: ¾” by 10’ in diameter.
PART 3 - EXECUTION
3.1
APPLICATION
A.
Use only copper conductors for bare grounding conductors in direct contact with earth,
concrete, masonry, crushed stone, and similar materials.
B.
Exothermic-Welded Connections: Use for connections to structural steel and for underground
connections to ground rods, except those at test wells.
3.2
GROUNDING OVERHEAD LINES
A.
Comply with IEEE C2 grounding requirements.
B.
Install 2 parallel ground rods if resistance to ground by a single, ground-rod electrode exceeds
25 ohms.
C.
Drive ground rods until tops are 12 inches (300 mm) below finished grade in undisturbed earth.
D.
Ground-Rod Connections:
connections to rods.
E.
Lightning Arrester Grounding Conductors: Separate from other grounding conductors.
F.
Secondary Neutral and Transformer Enclosure:
conductor.
G.
Protect grounding conductors running on surface of wood poles with molding extended from
grade level up to and through communication service and transformer spaces.
3.3
Install bolted connectors for underground connections and
Interconnect and connect to grounding
GROUNDING UNDERGROUND DISTRIBUTION SYSTEM COMPONENTS
A.
Comply with IEEE C2 grounding requirements.
B.
Grounding Manholes and Handholes: Install a driven ground rod through manhole or handhole
floor, close to wall, and set rod depth so 4 inches (100 mm) will extend above finished floor. If
necessary, install ground rod before manhole is placed and provide No. 1/0 AWG bare, tinnedcopper conductor from ground rod into manhole through a waterproof sleeve in manhole wall.
FA4608-16-R-0013
Attachment 1
Page 44 of 79
Protect ground rods passing through concrete floor with a double wrapping of pressuresensitive insulating tape or heat-shrunk insulating sleeve from 2 inches (50 mm) above to 6
inches (150 mm) below concrete. Seal floor opening with waterproof, nonshrink grout.
C.
Grounding Connections to Manhole Components: Bond exposed-metal parts such as inserts,
cable racks, pulling irons, ladders, and cable shields within each manhole or handhole, to
ground rod or grounding conductor. Make connections with No. 4 AWG minimum, stranded,
hard-drawn copper bonding conductor. Train conductors level or plumb around corners and
fasten to manhole walls. Connect to cable armor and cable shields as recommended by
manufacturer of splicing and termination kits.
D.
Pad-Mounted Switches:
1.
Install four ground rods, one at each corner, and ground ring around the pad installed at a
burial depth of 30” below finished grade.
2.
Ground pad-mounted equipment and noncurrent-carrying metal items associated with
substations by connecting them to underground cable and grounding electrodes. Provide
two (2) dedicated bare copper ground conductors connected to opposite corners of the
underground counterpoise into each switch compartment.
3.
Install copper conductor not less than No. 4/0 AWG for ground ring and for taps to
equipment grounding terminals. Bury ground ring not less than 30 inches (150 mm) from
the outside edge of the equipment pad.
3.4
INSTALLATION
A.
10’ x 3/4” Ground Rods: Install at each corner of equipment pads and within the primary and
secondary compartment of equipment. Ground rods shall be copper-clad steel, solid copper,
or stainless steel.
1.
2.
3.5
Drive ground rods until tops are 2 inches (50 mm) below finished floor or final grade,
unless otherwise indicated.
Interconnect ground rods with grounding electrode conductors. Use exothermic welds.
Make connections without exposing steel or damaging copper coating.
CONNECTIONS
A.
General: Make connections so galvanic action or electrolysis possibility is minimized. Select
connectors, connection hardware, conductors, and connection methods so metals in direct
contact will be galvanically compatible.
1.
Use electroplated or hot-tin-coated materials to ensure high conductivity and to make
contact points closer to order of galvanic series.
2.
Make connections with clean, bare metal at points of contact.
3.
Coat and seal connections having dissimilar metals with inert material to prevent future
penetration of moisture to contact surfaces.
B.
Exothermic-Welded Connections: Comply with manufacturer's written instructions. Welds that
are puffed up or that show convex surfaces indicating improper cleaning are not acceptable.
C.
Compression-Type Connections:
Use hydraulic compression tools to provide correct
circumferential pressure for compression connectors. Use tools and dies recommended by
connector manufacturer. Provide embossing die code or other standard method to make a
visible indication that a connector has been adequately compressed on grounding conductor.
3.6
FIELD QUALITY CONTROL
A.
Testing: Perform the following field quality-control testing:
1.
After installing grounding system but before permanent electrical circuitry has been
energized, test for compliance with requirements.
2.
Test completed grounding system at each location where a maximum ground-resistance
level is specified and at service disconnect enclosure grounding terminal. Measure
FA4608-16-R-0013
Attachment 1
Page 45 of 79
3.
4.
3.7
ground resistance not less than two full days after the last trace of precipitation, and
without the soil being moistened by any means other than natural drainage or seepage
and without chemical treatment or other artificial means of reducing natural ground
resistance. Perform tests, by the fall-of-potential method according to IEEE 81.
Provide drawings locating each ground rod and ground rod assembly and other
grounding electrodes, identify each by letter in alphabetical order, and key to the record
of tests and observations. Include the number of rods driven and their depth at each
location and include observations of weather and other phenomena that may affect test
results. Describe measures taken to improve test results.
a.
Equipment Rated 500 kVA and Less: 01 ohms.
Excessive Ground Resistance: If resistance to ground exceeds specified values, notify
Architect promptly and include recommendations to reduce ground resistance.
GRADING AND PLANTING
A.
Restore surface features, including vegetation, at areas disturbed by Work of this Section.
Reestablish original grades, unless otherwise indicated. If sod has been removed, replace it as
soon as possible after backfilling is completed. Restore areas disturbed by trenching, storing of
dirt, cable laying, and other activities to their original condition. Include application of topsoil,
fertilizer, lime, seed, sod, sprig, and mulch. Comply with Division 2 Section "Landscaping."
Maintain restored surfaces. Restore disturbed paving as indicated.
END OF SECTION 16060
FA4608-16-R-0013
Attachment 1
Page 46 of 79
SECTION 16124 - MEDIUM-VOLTAGE CABLES
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
SUMMARY
A.
1.3
This Section includes cables and related splices, terminations, and accessories for mediumvoltage electrical distribution systems.
DEFINITIONS
A.
1.4
NETA ATS: Acceptance Testing Specification.
SUBMITTALS
A.
Product Data: For each type of cable indicated. Include splices and terminations for cables and
cable accessories.
B.
Samples: 16-inch (400-mm) lengths of each type of cable indicated.
C.
Qualification Data: For testing agency, supervisor of cable terminator and cable splicer as well
as the cable terminator and cable splicer.
D.
Material Certificates: For each cable and accessory type, signed by manufacturers.
E.
Source quality-control test reports.
F.
Field quality-control test reports.
1.5
QUALITY ASSURANCE
A.
Installer: Engage a cable splicer, trained and certified by splice material manufacturer, to install,
splice, and terminate medium-voltage cable.
B.
Testing Agency Qualifications: An independent agency, with the experience and capability to
conduct the testing indicated, that is a member company of the InterNational Electrical Testing
Association or is a nationally recognized testing laboratory (NRTL) as defined by OSHA in
29 CFR 1910.7, and that is acceptable to authorities having jurisdiction.
1.
Testing Agency's Field Supervisor: Person currently certified by the InterNational
Electrical Testing Association or the National Institute for Certification in Engineering
Technologies to supervise on-site testing specified in Part 3.
FA4608-16-R-0013
Attachment 1
Page 47 of 79
C.
Source Limitations:
manufacturer.
D.
Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
E.
Comply with IEEE C2 and NFPA 70 (2011).
1.6
Obtain cables and accessories through one source from a single
PROJECT CONDITIONS
A.
Interruption of Existing Electric Service: Do not interrupt electric service to facilities occupied by
Owner or others unless permitted under the following conditions and then only after arranging to
provide temporary electric service according to requirements indicated:
1.
Notify Contracting Officer’s Representative no fewer than thirty days in advance of
proposed interruption of electric service.
2.
Do not proceed with interruption of electric service without Contracting Officer’s
Representative’s written permission.
PART 2 - PRODUCTS
2.1
MANUFACTURERS
A.
2.2
Manufacturers: Subject to compliance with requirements, manufacturers offering products that
may be incorporated into the Work include, but are not limited to, the following:
1.
Cables:
a.
American Insulated Wire Corp.; a Leviton Company.
b.
General Cable Technologies Corporation.
c.
Kerite Co. (The); Hubbell Incorporated.
d.
Okonite Company (The).
e.
Pirelli Cables & Systems NA.
f.
Rome Cable Corporation.
g.
Southwire Company.
2.
Cable Splicing and Terminating Products and Accessories:
a.
Engineered Products Company.
b.
G&W Electric Company.
c.
MPHusky.
d.
Raychem Corp.; Telephone Energy and Industrial Division; Tyco International Ltd.
e.
RTE Components; Cooper Power Systems, Inc.
f.
Scott Fetzer Co. (The); Adalet.
g.
Thomas & Betts Corporation.
h.
Thomas & Betts Corporation/Elastimold.
i.
3M; Electrical Products Division.
CABLES
A.
Cable Type: MV90.
B.
Comply with UL 1072, AEIC CS 8, ICEA S-93-639, and ICEA S-97-682.
C.
Conductor: Copper.
FA4608-16-R-0013
Attachment 1
Page 48 of 79
D.
Conductor Stranding: Compact round, concentric lay, Class B.
E.
Strand Filling: Conductor interstices are filled with impermeable compound.
F.
Conductor Insulation: Ethylene-propylene rubber.
1.
Voltage Rating: 15kV.
2.
Insulation Thickness: 133 percent insulation level.
G.
Neutral: Jacketed Concentric neutral
1.
3-Phase: One-third stranded.
2.
Single-Phase: Full Stranded.
2.3
SOLID TERMINATIONS
A.
2.4
Shielded-Cable Terminations: Comply with the following classes of IEEE 48. Insulation class is
equivalent to that of cable. Include shield ground strap for shielded cable terminations.
1.
Class 1 Terminations: Modular type, furnished as a kit, with stress-relief tube; multiple,
molded-silicone rubber, insulator modules; shield ground strap; and compression-type
connector.
2.
Class 1 Terminations: Cold-shrink type with heat-shrink inner stress control and outer
nontracking tubes; multiple, molded, nontracking skirt modules; and compression-type
stem connector or heavy long barrel 2-hole lugs to fit the application.
SEPARABLE INSULATED CONNECTORS
A.
Description: Modular system, complying with IEEE 386, with disconnecting, single-pole, cable
terminators and with matching, stationary, plug-in, dead-front terminals designed for cable
voltage and for sealing against moisture.
B.
Terminations at Distribution Points: Modular type, consisting of terminators installed on cables
and modular, dead-front, terminal junctions for interconnecting cables.
C.
Cable Terminators: Elbow-type units with continuous-current rating; coordinated with insulation
diameter, conductor size, and material of cable being terminated. Include test point on
terminator body that is capacitance coupled.
1.
Rating for Transformers: 200A load break.
2.
Rating for Switch Inputs: 600A non-load break.
D.
Dead-Front Terminal Junctions: Modular bracket-mounted groups of dead-front stationary
terminals that mate and match with above cable terminators. Two-, three-, or four-terminal units
as indicated, with fully rated, insulated, watertight conductor connection between terminals and
complete with grounding lug, manufacturer's standard accessory stands, stainless-steel
mounting brackets, and attaching hardware.
1.
Protective Cap: Insulating, electrostatic-shielding, water-sealing cap with drain wire.
2.
Portable Feed-Through Accessory: Two-terminal, dead-front junction arranged for
removable mounting on accessory stand of stationary terminal junction.
3.
Grounding Kit: Jumpered elbows, portable feed-through accessory units, protective
caps, test rods suitable for concurrently grounding three phases of feeders, and carrying
case.
4.
Standoff Insulator: Portable, single dead-front terminal for removable mounting on
accessory stand of stationary terminal junction. Insulators suitable for fully insulated
isolation of energized cable-elbow terminator.
FA4608-16-R-0013
Attachment 1
Page 49 of 79
E.
Test-Point Fault Indicators: Applicable current-trip ratings and arranged for installation in test
points of load-break separable connectors, and complete with self-resetting indicators capable
of being installed with shotgun hot stick and tested with test tool.
F.
Tool Set: Shotgun hot stick with energized terminal indicator, fault-indicator test tool, and
carrying case.
2.5
ARC-PROOFING MATERIALS
A.
Tape for First Course on Metal Objects: 10-mil- (250-micrometer-) thick, corrosion-protective,
moisture-resistant, PVC pipe-wrapping tape.
B.
Arc-Proofing Tape: Fireproof tape, flexible, conformable, intumescent to 0.3 inch (8 mm) thick,
compatible with cable jacket.
C.
Glass-Cloth Tape: Pressure-sensitive adhesive type, 1/2 inch (13 mm) wide.
2.6
FAULT INDICATORS
A.
Indicators: Manually reset fault indicator with inrush restraint feature, arranged to clamp to
cable sheath and provide a display after a fault has occurred in cable. Instrument shall not be
affected by heat, moisture, and corrosive conditions and shall be recommended by
manufacturer for installation conditions.
B.
Resetting Tool:
carrying case.
2.7
Designed for use with fault indicators, with moisture-resistant storage and
SOURCE QUALITY CONTROL
A.
Test and inspect cables according to ICEA S-97-682 before shipping.
B.
Test strand-filled cables for water-penetration resistance according to ICEA T-31-610, using a
test pressure of 5 psig (35 kPa).
PART 3 - EXECUTION
3.1
INSTALLATION
A.
Install cables according to IEEE 576.
B.
Pull Conductors: Do not exceed manufacturer's recommended maximum pulling tensions and
sidewall pressure values.
1.
Where necessary, use manufacturer-approved pulling compound or lubricant that will not
deteriorate conductor or insulation.
2.
Use pulling means, including fish tape, cable, rope, and basket-weave cable grips that
will not damage cables and raceways. Do not use rope hitches for pulling attachment to
cable.
3.
Pull cables downgrade with feed-in-point at the highest elevation in the pull.
FA4608-16-R-0013
Attachment 1
Page 50 of 79
4.
Cable pulling tensions shall not exceed the maximum pulling tension recommended by
the cable manufacturer.
C.
In manholes and cable vaults, train cables around walls by the longest route from entry to exit
and support cables at intervals adequate to prevent sag.
1.
Cable slack shall be accumulated at each manhole by training cable around the
perimeter to form a complete loop. Maintain allowable minimum bending radii when
forming such loops.
2.
Support cables on brackets and cable insulators at intervals not to exceed 18”.
D.
Install cable splices at pull points and elsewhere as indicated; use standard kits. Support cable
splices in underground structures by racks on each side of splice.
E.
Install terminations at ends of conductors and seal multiconductor cable ends with standard kits.
F.
Install separable insulated-connector components as follows:
1.
Protective Cap: At each terminal junction, with one on each terminal to which no feeder
is indicated to be connected.
2.
Portable Feed-Through Accessory: Three.
3.
Standoff Insulator: Three.
G.
Arc Proofing: Unless otherwise indicated, arc proof medium-voltage cable in manholes in
accordance with industry standards and at locations not protected by conduit, cable tray, direct
burial, or termination materials. In addition to arc-proofing tape manufacturer's written
instructions, apply arc proofing as follows:
1.
Clean cable sheath.
2.
Wrap metallic cable components with 10-mil (250-micrometer) pipe-wrapping tape.
3.
Smooth surface contours with electrical insulation putty.
4.
Apply arc-proofing tape in one half-lapped layer with coated side toward cable.
5.
Band arc-proofing tape with 1-inch- (25-mm-) wide bands of half-lapped, adhesive, glasscloth tape 2 inches (50 mm) o.c.
H.
Install fault indicators on each phase on each vista switch load interrupter switch way.
I.
Ground shields of shielded cable at terminations, splices, and separable insulated connectors.
Ground metal bodies of terminators, splices, cable and separable insulated-connector fittings,
and hardware.
J.
Identify cables according to Division 16 Section "Basic Electrical Materials and Methods."
3.2
FIELD QUALITY CONTROL
A.
Testing: Engage a qualified testing and inspecting agency to perform the following field tests
and inspections and prepare test reports:
1.
Perform each visual and mechanical inspection and electrical test stated in NETA ATS.
Certify compliance with test parameters.
2.
After installing medium-voltage cables and before electrical circuitry has been energized,
test for compliance with requirements.
3.
Perform dielectric strength test on cable in accordance with IEEE Standard 141, 1976,
Chapter 10, Page 354.
B.
Remove and replace malfunctioning units and retest as specified above.
FA4608-16-R-0013
Attachment 1
Page 51 of 79
END OF SECTION 16124
FA4608-16-R-0013
Attachment 1
Page 52 of 79
SECTION 16135 - UNDERGROUND DUCTS AND UTILITY STRUCTURES
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
SUMMARY
A.
1.3
This Section includes the following:
1.
Conduit, ducts, and duct accessories for concrete-encased duct banks.
2.
Manholes.
DEFINITION
A.
1.4
RNC: Rigid nonmetallic conduit.
SUBMITTALS
A.
Product Data: For the following:
1.
Duct-bank materials, including separators and miscellaneous components.
2.
Ducts and conduits and their accessories, including elbows, end bells, bends, fittings,
and solvent cement.
3.
Accessories for manholes.
4.
Warning tape.
B.
Shop Drawings for Precast or Factory-Fabricated Underground Utility Structures: Include plans,
elevations, sections, details, attachments to other work, and accessories, including the
following:
1.
Duct entry provisions, including locations and duct sizes.
2.
Reinforcement details.
3.
Frame and cover design and manhole frame support rings.
4.
Ladder details.
5.
Grounding details.
6.
Dimensioned locations of cable rack inserts, pulling-in and lifting irons, and sumps.
7.
Joint details.
1.5
QUALITY ASSURANCE
A.
Electrical Components Devices and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to the Contracting Officer’s representative, and
marked for intended use.
B.
Testing Agency Qualifications: Qualified according to ASTM E 329 for testing indicated.
FA4608-16-R-0013
Attachment 1
Page 53 of 79
C.
Comply with ANSI C2.
D.
Comply with NFPA 70 (2011).
1.6
DELIVERY, STORAGE, AND HANDLING
A.
Deliver ducts to Project site with ends capped. Store nonmetallic ducts with supports to prevent
bending, warping, and deforming.
B.
Store precast concrete underground utility structures at Project site as recommended by
manufacturer to prevent physical damage. Arrange so identification markings are visible.
C.
Lift and support precast concrete units only at designated lifting or supporting points.
1.7
COORDINATION
A.
Coordinate layout and installation of ducts and manholes with final arrangement of other
utilities, site grading, and surface features as determined in the field.
B.
Coordinate elevations of ducts and duct-bank entrances into manholes with final locations and
profiles of ducts and duct banks as determined by coordination with other utilities, underground
obstructions, and surface features. Revise locations and elevations from those indicated as
required to suit field conditions and to ensure that duct runs drain to manholes and as approved
by the Contracting Officer’s Representative.
PART 2 - PRODUCTS
2.1
CONDUIT
A.
Rigid Steel Conduit: Galvanized. Comply with ANSI C80.1.
B.
RNC: NEMA TC 2, Type EPC-40-PVC, UL 651, with matching fittings by same manufacturer as
the conduit, complying with NEMA TC 3 and UL 514B.
2.2
NONMETALLIC DUCTS AND DUCT ACCESSORIES
A.
Available Manufacturers: Subject to compliance with requirements, manufacturers offering
products that may be incorporated into the Work include, but are not limited to, the following:
1.
ARNCO Corp.
2.
Beck Manufacturing.
3.
Cantex, Inc.
4.
CertainTeed Corp.; Pipe & Plastics Group.
5.
Condux International, Inc.
6.
ElecSys, Inc.
7.
Electri-Flex Company.
8.
IPEX Inc.
9.
Lamson & Sessions; Carlon Electrical Products.
10.
Manhattan/CDT; a division of Cable Design Technologies.
FA4608-16-R-0013
Attachment 1
Page 54 of 79
11.
A.
2.3
Spiraduct/AFC Cable Systems, Inc.
RNC: NEMA TC 2, Type EPC-40-PVC, UL 651, with matching fittings by same manufacturer as
the conduit, complying with NEMA TC 3 and UL 514B.
1.
Duct Separators: Factory-fabricated rigid PVC interlocking spacers, sized for type and
sizes of ducts with which used, and selected to provide minimum duct spacings indicated
while supporting ducts during concreting or backfilling.
2.
Warning Tape: Underground-line warning tape specified in Division 16 Section "Electrical
Identification."
PRECAST MANHOLES
A.
Available Manufacturers: Subject to compliance with requirements, manufacturers offering
products that may be incorporated into the Work include, but are not limited to, the following:
B.
Manufacturers: Subject to compliance with requirements, provide products by one of the
following:
1.
Carder Concrete Products.
2.
Christy Concrete Products.
3.
Elmhurst-Chicago Stone Co.
4.
Oldcastle Precast Group.
5.
Riverton Concrete Products; a division of Cretex Companies, Inc.
6.
Utility Concrete Products, LLC.
7.
Utility Vault Co.
8.
Wausau Tile, Inc.
C.
Comply with ASTM C 858, with structural design loading as specified in Part 3 "Underground
Enclosure Application" Article and with interlocking mating sections, complete with accessories,
hardware, and features.
1.
Windows: Precast openings in walls, arranged to match dimensions and elevations of
approaching ducts and duct banks plus an additional 12 inches (300 mm) vertically and
horizontally to accommodate alignment variations.
a.
Windows shall be located no less than 6 inches (150 mm) from interior surfaces of
walls, floors, or roofs of manholes, but close enough to corners to facilitate racking
of cables on walls.
b.
Window opening shall have cast-in-place, welded wire fabric reinforcement for field
cutting and bending to tie in to concrete envelopes of duct banks.
c.
Window openings shall be framed with at least two additional No. 4 steel
reinforcing bars in concrete around each opening.
2.
Duct Entrances in Manhole Walls: Cast end-bell or duct-terminating fitting in wall for
each entering duct.
a.
Type and size shall match fittings to duct or conduit to be terminated.
b.
Fittings shall align with elevations of approaching ducts and be located near
interior corners of manholes to facilitate racking of cable.
D.
Concrete Knockout Panels: 1-1/2 to 2 inches (38 to 50 mm) thick, for future conduit entrance
and sleeve for ground rod.
E.
Joint Sealant: Asphaltic-butyl material with adhesion, cohesion, flexibility, and durability
properties necessary to withstand maximum hydrostatic pressures at the installation location
with the ground-water level at grade.
FA4608-16-R-0013
Attachment 1
Page 55 of 79
2.4
UTILITY STRUCTURE ACCESSORIES
A.
Available Manufacturers: Subject to compliance with requirements, manufacturers offering
products that may be incorporated into the Work include, but are not limited to, the following:
1.
Bilco Company (The).
2.
Campbell Foundry Company.
3.
Carder Concrete Products.
4.
Christy Concrete Products.
5.
East Jordan Iron Works, Inc.
6.
Elmhurst-Chicago Stone Co.
7.
McKinley Iron Works, Inc.
8.
Neenah Foundry Company.
9.
NewBasis.
10.
Oldcastle Precast Group.
11.
Osburn Associates, Inc.
12.
Pennsylvania Insert Corporation.
13.
Riverton Concrete Products; a division of Cretex Companies, Inc..
14.
Strongwell Corporation; Lenoir City Division.
15.
Underground Devices, Inc.
16.
Utility Concrete Products, LLC.
17.
Utility Vault Co.
18.
Wausau Tile, Inc.
B.
Manhole Frames, Covers, and Chimney Components: Comply with structural design loading
specified for manhole.
1.
Frame and Cover: Weatherproof, gray cast iron complying with ASTM A 48/A 48M,
Class 30B with milled cover-to-frame bearing surfaces; diameter, 29 inches (737 mm).
a.
Cover Finish: Nonskid finish shall have a minimum coefficient of friction of 0.50.
b.
Special Covers: Recess in face of cover designed to accept finish material in
paved areas.
2.
Cover Legend: Cast in. Selected to suit system.
a.
Legend: "ELECTRIC-HV" for duct systems with medium-voltage cables.
3.
Manhole Chimney Components: Precast concrete rings with dimensions matched to
those of roof opening.
a.
Mortar for Chimney Ring and Frame and Cover Joints: Comply with ASTM C 270,
Type M, except for quantities less than 2.0 cu. ft. (60 L) where packaged mix
complying with ASTM C 387, Type M, may be used.
C.
Manhole Sump Frame and Grate: ASTM A 48/A 48M, Class 30B, gray cast iron.
D.
Pulling Eyes in Concrete Walls: Eyebolt with reinforcing-bar fastening insert, 2-inch- (50-mm-)
diameter eye, and 1-by-4-inch (25-by-100-mm) bolt.
1.
Working Load Embedded in 6-Inch (150-mm), 4000-psi (27.6-MPa) Concrete: 13,000-lbf
(58-kN) minimum tension.
E.
Pulling-In and Lifting Irons in Concrete Floors: 7/8-inch- (22-mm-) diameter, hot-dip galvanized,
bent steel rod; stress relieved after forming; and fastened to reinforcing rod. Exposed triangular
opening.
1.
Ultimate Yield Strength: 40,000-lbf (180-kN) shear and 60,000-lbf (270-kN) tension.
F.
Bolting Inserts for Concrete Utility Structure Cable Racks and Other Attachments: Flared,
threaded inserts of noncorrosive, chemical-resistant, nonconductive thermoplastic material; 1/2inch (13-mm) ID by 2-3/4 inches (69 mm) deep, flared to 1-1/4 inches (32 mm) minimum at
base.
FA4608-16-R-0013
Attachment 1
Page 56 of 79
1.
Tested Ultimate Pullout Strength: 12,000 lbf (53 kN) minimum.
G.
Expansion Anchors for Installation after Concrete Is Cast: Zinc-plated, carbon-steel-wedge type
with stainless-steel expander clip with 1/2-inch (13-mm) bolt, 5300-lbf (24-kN) rated pullout
strength, and minimum 6800-lbf (30-kN) rated shear strength.
H.
Cable Rack Assembly: Steel, hot-dip galvanized, except insulators.
1.
Stanchions: T-section or channel; 2-1/4-inch (57-mm) nominal size; punched with 14
holes on 1-1/2-inch (38-mm) centers for cable-arm attachment.
2.
Arms: 1-1/2 inches (38 mm) wide, lengths ranging from 3 inches (75 mm) with 450-lb
(204-kg) minimum capacity to 18 inches (460 mm) with 250-lb (114-kg) minimum
capacity. Arms shall have slots along full length for cable ties and be arranged for secure
mounting in horizontal position at any vertical location on stanchions.
3.
Insulators: High-glaze, wet-process porcelain arranged for mounting on cable arms.
I.
Duct-Sealing Compound: Nonhardening, safe for contact with human skin, not deleterious to
cable insulation, and workable at temperatures as low as 35 deg F (2 deg C). Capable of
withstanding temperature of 300 deg F (150 deg C) without slump and adhering to clean
surfaces of plastic ducts, metallic conduits, conduit coatings, concrete, masonry, lead, cable
sheaths, cable jackets, insulation materials, and common metals.
J.
Cover Hooks: Heavy duty, designed for lifts 60 lbf (270 N) and greater. Two required.
2.5
SOURCE QUALITY CONTROL
A.
Test and inspect precast concrete utility structures according to ASTM C 1037.
PART 3 - EXECUTION
3.1
UNDERGROUND DUCT APPLICATION
A.
3.2
Ducts for Electrical Cables Over 600 V: RNC, NEMA Type [EPC-80] [EPC-40] [EB-40]-PVC, in
concrete-encased duct bank, unless otherwise indicated.
UNDERGROUND ENCLOSURE APPLICATION
A.
3.3
Manholes: Precast concrete.
1.
Units Located in Roadways and Other Deliberate Traffic Paths by Heavy or Medium
Vehicles: H-20 structural load rating according to AASHTO HB 17.
2.
Units Not Located in Deliberate Traffic Paths by Heavy or Medium Vehicles: H-10 load
rating according to AASHTO HB 17.
EARTHWORK
A.
Excavation and Backfill: Comply with Division 2 Section "Earthwork," but do not use heavyduty, hydraulic-operated, compaction equipment.
FA4608-16-R-0013
Attachment 1
Page 57 of 79
B.
Restore surface features at areas disturbed by excavation and reestablish original grades,
unless otherwise indicated. Replace removed sod immediately after backfilling is completed.
C.
Restore areas disturbed by trenching, storing of dirt, cable laying, and other work. Restore
vegetation and include necessary topsoiling, fertilizing, liming, seeding, sodding, sprigging, and
mulching. Comply with Division 2 Sections.
D.
Cut and patch existing pavement in the path of underground ducts and utility structures
according to Division 1 Section "Cutting and Patching."
3.4
DUCT INSTALLATION
A.
Slope: Pitch ducts a minimum slope of 1:300 down toward manholes and handholes and away
from buildings and equipment. Slope ducts from a high point in runs between two manholes to
drain in both directions.
B.
Curves and Bends: Use 5-degree angle couplings for small changes in direction. Use
manufactured long sweep bends with a minimum radius of 48 inches (1220 mm), both
horizontally and vertically, at other locations, unless otherwise indicated.
C.
Joints: Use solvent-cemented joints in ducts and fittings and make watertight according to
manufacturer's written instructions. Stagger couplings so those of adjacent ducts do not lie in
same plane.
D.
Duct Entrances to Manholes and Concrete and Polymer Concrete Handholes: Use end bells,
spaced approximately 10 inches (250 mm) o.c. for 5-inch (125-mm) ducts, and vary
proportionately for other duct sizes.
1.
Begin change from regular spacing to end-bell spacing 10 feet (3 m) from the end bell
without reducing duct line slope and without forming a trap in the line.
2.
Direct-Buried Duct Banks: Install an expansion and deflection fitting in each conduit in
the area of disturbed earth adjacent to manhole or handhole.
3.
Grout end bells into structure walls from both sides to provide watertight entrances.
E.
Sealing: Provide temporary closure at terminations of ducts that have cables pulled. Seal
spare ducts at terminations. Use sealing compound and plugs to withstand at least 15-psig
(1.03-MPa) hydrostatic pressure.
F.
Pulling Cord: Install 100-lbf- (445-N-) test nylon cord in ducts, including spares.
G.
Concrete-Encased Ducts: Support ducts on duct separators.
1.
Separator Installation: Space separators close enough to prevent sagging and deforming
of ducts, with not less than 4 spacers per 20 feet (6 m) of duct. Secure separators to
earth and to ducts to prevent floating during concreting.
Stagger separators
approximately 6 inches (150 mm) between tiers. Tie entire assembly together using
fabric straps; do not use tie wires or reinforcing steel that may form conductive or
magnetic loops around ducts or duct groups.
2.
Concreting Sequence: Pour each run of envelope between manholes or other
terminations in one continuous operation.
a.
Start at one end and finish at the other, allowing for expansion and contraction of
ducts as their temperature changes during and after the pour. Use expansion
fittings installed according to manufacturer's written recommendations, or use
other specific measures to prevent expansion-contraction damage.
FA4608-16-R-0013
Attachment 1
Page 58 of 79
b.
3.
4.
5.
6.
7.
8.
9.
10.
3.5
If more than one pour is necessary, terminate each pour in a vertical plane and
install 3/4-inch (19-mm) reinforcing rod dowels extending 18 inches (450 mm) into
concrete on both sides of joint near corners of envelope.
Pouring Concrete: Spade concrete carefully during pours to prevent voids under and
between conduits and at exterior surface of envelope. Do not allow a heavy mass of
concrete to fall directly onto ducts. Use a plank to direct concrete down sides of bank
assembly to trench bottom. Allow concrete to flow to center of bank and rise up in
middle, uniformly filling all open spaces. Do not use power-driven agitating equipment
unless specifically designed for duct-bank application. Sprinkle red-oxide dye on top.
Reinforcement: Reinforce concrete-encased duct banks where they cross disturbed
earth and where indicated. Arrange reinforcing rods and ties without forming conductive
or magnetic loops around ducts or duct groups.
Forms: Use walls of trench to form side walls of duct bank where soil is self-supporting
and concrete envelope can be poured without soil inclusions; otherwise, use forms.
Minimum Space between Ducts: 3 inches (75 mm) between ducts and exterior envelope
wall.
Depth: Install top of duct bank at least 36 inches (600 mm) below finished grade in areas
not subject to deliberate traffic, and at least 48 inches (750 mm) below finished grade in
deliberate traffic paths for vehicles, unless otherwise indicated.
Stub-Ups: Use manufactured PVC-coated rigid steel conduit elbows for stub-ups at
poles and equipment.
a.
Couple steel conduits to ducts with adapters designed for this purpose, and
encase coupling with 3 inches (75 mm) of concrete.
b.
Stub-Ups to Equipment: For equipment mounted on outdoor concrete bases,
extend steel conduit horizontally a minimum of 60 inches (1500 mm) from edge of
base. Install insulated grounding bushings on terminations at equipment.
Warning Tape: Bury warning tape approximately 12 inches (300 mm) above all concreteencased ducts. Align tape parallel to and within 3 inches (75 mm) of the centerline of
duct bank. Provide an additional warning tape for each 12-inch (300-mm) increment of
duct-bank width over a nominal 18 inches (450 mm). Space additional tapes 12 inches
(300 mm) apart, horizontally.
Rod Crossings: Install rigid galvanized steel and encapsulate with conduit as indicated
above and detailed on the drawings.
INSTALLATION OF CONCRETE MANHOLES, HANDHOLES, AND BOXES
A.
Precast Concrete Handhole and Manhole Installation:
1.
Comply with ASTM C 891, unless otherwise indicated.
2.
Install units level and plumb and with orientation and depth coordinated with connecting
ducts to minimize bends and deflections required for proper entrances.
3.
Unless otherwise indicated, support units on a level bed of crushed stone or gravel,
graded from 1-inch (25-mm) sieve to No. 4 (4.75-mm) sieve and compacted to same
density as adjacent undisturbed earth.
B.
Elevations:
1.
Manhole Roof: Install with rooftop at least 15 inches (380 mm) below finished grade.
2.
Manhole Frame: In paved areas and trafficways, set frames flush with finished grade.
Set other manhole frames 1 inch (25 mm) above finished grade.
C.
Drainage: Install drains in bottom of manholes where indicated. Coordinate with drainage
provisions indicated.
D.
Manhole Access: Circular opening in manhole roof; sized to match cover size.
FA4608-16-R-0013
Attachment 1
Page 59 of 79
1.
2.
Manholes with Fixed Ladders: Offset access opening from manhole centerlines to align
with ladder.
Install chimney, constructed of precast concrete collars and rings to support frame and
cover and to connect cover with manhole roof opening. Provide moisture-tight masonry
joints and waterproof grouting for cast-iron frame to chimney.
E.
Waterproofing: Apply waterproofing to exterior surfaces of manholes after concrete has cured
at least three days. After ducts have been connected and grouted, and before backfilling,
waterproof joints and connections and touch up abrasions and scars. Waterproof exterior of
manhole chimneys after mortar has cured at least three days.
F.
Hardware: Install removable hardware, including pulling eyes, cable stanchions, and cable
arms, and insulators, as required for installation and support of cables and conductors and as
indicated.
G.
Fixed Manhole Ladders: Arrange to provide for safe entry with maximum clearance from cables
and other items in manholes.
H.
Field-Installed Bolting Anchors in Manholes: Do not drill deeper than 3-7/8 inches (98 mm) for
manholes, for anchor bolts installed in the field. Use a minimum of two anchors for each cable
stanchion.
I.
Warning Sign: Install "Confined Space Hazard" warning sign on the inside surface of each
manhole cover.
3.6
GROUNDING
A.
3.7
Ground underground ducts and utility structures according to Division 16 Section "Grounding
and Bonding."
FIELD QUALITY CONTROL
A.
Perform the following tests and inspections and prepare test reports:
1.
Demonstrate capability and compliance with requirements upon completion of installation
of underground ducts and utility structures.
2.
Pull aluminum or wood test mandrel through duct to prove joint integrity and test for outof-round duct. Provide mandrel equal to 80 percent fill of duct. If obstructions are
indicated, remove obstructions and retest.
3.
Test manhole and handhole grounding to ensure electrical continuity of grounding and
bonding connections. Measure and report ground resistance as specified in Division 16
Section "Grounding and Bonding."
B.
Correct deficiencies and retest as specified above to demonstrate compliance.
3.8
CLEANING
A.
Pull leather-washer-type duct cleaner, with graduated washer sizes, through full length of ducts.
Follow with rubber duct swab for final cleaning and to assist in spreading lubricant throughout
ducts.
FA4608-16-R-0013
Attachment 1
Page 60 of 79
B.
Clean internal surfaces of manholes, including sump. Remove foreign material.
END OF SECTION 16135
FA4608-16-R-0013
Attachment 1
Page 61 of 79
SECTION 16315 - OVERHEAD ELECTRICAL DISTRIBUTION
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
SUMMARY
A.
1.3
This Section includes medium-voltage, overhead electrical power distribution and demolition
and upgrading of existing overhead electrical power distribution, and the following:
1.
Conductors, connectors, and splices.
2.
Wood poles and crossarms.
3.
Hardware and accessories.
4.
Surge arresters.
5.
Cutouts, switches, and fuses.
DEFINITIONS
A.
ACSR: Aluminum conductor, steel reinforced.
B.
BIL: Basic impulse level, stated in kilovolts.
C.
HDPE: High-density polyethylene.
D.
RUS: Department of Agriculture, Rural Utilities Service.
E.
Sag: The distance measured vertically from a conductor to the straight line joining its two points
of support, measured at the midpoint of the span, unless otherwise indicated.
1.
Final Sag: The sag of a conductor under specified conditions of loading and temperature
applied after it has been subjected, for an appreciable period, to the loading prescribed
for the loading district in which it is situated, or equivalent loading, and the loading
removed. Final sag includes the effect of inelastic deformation (creep).
2.
Initial Unloaded Sag: The sag of a conductor before the application of an external load.
F.
Secondary: Conductors and components for circuits operating at the utilization voltage of 600 V
or less.
G.
Service: Set of insulated conductors extending from a pole to the metering point or service
entrance connection at the location of utilization of electricity.
1.4
SUBMITTALS
A.
Product Data: For the following:
1.
Conductors.
2.
Poles.
3.
Crossarms.
4.
Insulators.
FA4608-16-R-0013
Attachment 1
Page 62 of 79
5.
6.
7.
8.
Switches.
Cutouts.
Surge arresters.
Guy assemblies.
B.
Qualification Data: For installer.
C.
Material Inspection Reports: From a qualified independent inspection agency indicating
compliance of wood poles and crossarms with requirements indicated. RUS quality mark
"WQC" on each item is acceptable in place of inspection as evidence of compliance.
D.
Material Certificates: For the following items, signed by manufacturers:
1.
Wood poles.
2.
Wood crossarms.
E.
Listing Documentation: Indicate products comply with RUS listing requirements specified in
"Quality Assurance" Article.
F.
Time-Current Coordination Curves:
involved in the Work of this Section.
G.
Field quality-control test reports.
H.
Source Quality-Control Test Reports: Factory inspection reports of wood poles.
I.
Operation and Maintenance Data:
maintenance manuals.
1.5
Illustrate optimum coordination of protective devices
For switches to include in emergency, operation, and
QUALITY ASSURANCE
A.
Inspection Agency Qualifications for Pole and Crossarm Inspection: An independent agency,
acceptable to authorities having jurisdiction, qualified to conduct inspections indicated.
B.
Testing Agency Qualifications: An independent agency, with the experience and capability to
conduct the testing indicated, that is a member company of the InterNational Electrical Testing
Association or is a nationally recognized testing laboratory (NRTL) as defined by OSHA in
29 CFR 1910.7, and that is acceptable to authorities having jurisdiction.
1.
Testing Agency's Field Supervisor: Person currently certified by the InterNational
Electrical Testing Association or the National Institute for Certification in Engineering
Technologies to supervise on-site testing specified in Part 3.
C.
Treatment Technician Qualifications for Field Treatment of Wood Poles and Crossarms:
Certified by authorities having jurisdiction over environmental protection at the location of
Project for field application of chemicals required.
D.
Electrical Components Normally Covered by Listing and Labeling Services: Listed and labeled
as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having
jurisdiction, and marked for intended use.
E.
Overhead-Line Components, Devices, and Accessories: Currently listed in RUS Informational
Publication 202-1 without restriction for the intended application.
F.
Comply with IEEE C2, except where stricter requirements are indicated or where local
requirements that are stricter apply.
FA4608-16-R-0013
Attachment 1
Page 63 of 79
G.
1.6
Strength of Line and Line Components Selected by Contractor: Provide grades of construction
and strength required by IEEE C2 for conditions encountered at Project site for heavy line
loading, unless otherwise indicated.
DELIVERY, STORAGE, AND HANDLING
A.
1.7
Wood Pole Storage and Handling: Comply with ANSI O5.1. Do not use pointed handling tools
capable of producing indentations greater than 1 inch (25 mm). Protect poles stored on the
ground from damage due to mowers etc.
PROJECT CONDITIONS
A.
1.8
Existing Utilities: Do not interrupt utilities serving facilities occupied by Owner or others unless
permitted under the following conditions and then only after arranging to provide temporary
utility services according to requirements indicated:
1.
Notify Contracting Officer’s Representative not less than ten days in advance of proposed
utility interruptions.
2.
Do not proceed with utility interruptions without Contracting Officer’s Representative
written permission.
COORDINATION
A.
1.9
Coordinate with Contracting Officer’s Representative lines specified in this Section, and make
final connections.
EXTRA MATERIALS
A.
Furnish extra materials described below that match products installed and that are packaged
with protective covering for storage and identified with labels describing contents.
1.
Fuses: One additional spare fuse(s) or fuse element(s) for each furnished fuse or fuse
element.
2.
Special Tools: Two sets of special-purpose tools required for maintenance of cutouts,
switches, and reclosers, complete with toolbox.
3.
Padlocks: One for each three installed, but no fewer than three.
4.
Insulators: One for every 10 of each type, but no fewer than three of each type.
PART 2 - PRODUCTS
2.1
MANUFACTURERS
A.
In other Part 2 articles where titles below introduce lists, the following requirements apply to
product selection:
1.
Manufacturers:
Subject to compliance with requirements, manufacturers offering
products that may be incorporated into the Work include, but are not limited to,
manufacturers specified.
FA4608-16-R-0013
Attachment 1
Page 64 of 79
2.2
CONDUCTORS, CONNECTORS, AND SPLICES
A.
Available Manufacturers - Conductors:
1.
AFC Cable Systems.
2.
Alcan Cable Co.
3.
BICC Cables Company.
4.
Brugg Telecom Inc.
5.
Florida Wire & Cable, Inc.
6.
General Wire & Cable Co.
7.
Hendrix Wire and Cable Inc.
8.
Kerite Company (The); Innovation Systems Inc.
9.
King Wire Inc.
10.
Nokia Cables USA Inc.
11.
Northern Lights Cable, Inc.
12.
Okonite Company (The).
13.
Rome Cable Corp.
14.
Southwire Company.
B.
Manufacturers - Connectors and Splices:
1.
AB Chance Co.; Hubbell, Inc.
2.
Connector Manufacturing Co.
3.
Cooper Power Systems.
4.
Hubbell, Inc.; Anderson Electrical Products, Inc.
5.
Hubbell, Inc.; Fargo Manufacturing Company.
C.
Medium-Voltage Line Conductors: Bare Aluminum Conductor, Steel Reinforced (ACSR),
complying with ASTM B 232/B 232M.
D.
Connectors, Splices, and Conductor Securing and Protecting Components: Items include wire
clamps, ties, conductor armor, fittings, connectors, and terminals. Listed for the specific
applications and conductor types and combinations of materials used. Descriptions as follows
for various applications:
1.
Aluminum Composition to Aluminum Composition: Aluminum alloy, complying with
UL 486B.
2.
Copper to Aluminum Composition: Type suitable for this purpose, complying with
UL 486B.
3.
Taps for Medium-Voltage Line Conductors: Shot on or Crimp connectors. Listed for the
combination of materials being connected.
4.
Splices under Tension: Compression type with strength exceeding the conductors
spliced.
5.
Splices and Terminations for Insulated Medium-Voltage Conductors: Comply with
requirements in Division 16 Section "Medium-Voltage Cables."
2.3
WOOD POLES
A.
Manufacturers:
1.
Bell Lumber & Pole Co.
2.
B. J. Carney & Co., Ltd.
3.
Brown Wood Preserving Co.
4.
GRA Services International, Inc.
5.
J. H. Baxter & Co.
6.
Koppers Industries, Inc.
7.
McFarland Cascade.
8.
Okonite Company (The).
9.
Taylor Lumber & Treating.
FA4608-16-R-0013
Attachment 1
Page 65 of 79
10.
Western Red Cedar Lumber Association.
B.
Description: 12 psi pressure treated creosote power pole. Wood poles comply with ANSI O5.1
and treated according to AWPA C4 with oil-borne preservatives and petroleum complying with
AWPA P8 and AWPA P9.
C.
Wood Species: Yellow pine. Class II, 40’ pole minimum requirement. The contractor shall verify
the pole height.
D.
Pole Marking (birthmark) Location: 12 feet (3 m) from the pole butt for poles 50 feet (15 m) long
or less. Birthmark shall include manufacturer’s brand, year of manufacture, species of timber,
class and length of pole and owners mark. The pole must be installed such that the birthmark
visible upon completion. The birthmark shall not be blocked.
E.
Factory Operations: Machine trim poles by turning smooth, full length. Roof, gain, and bore
poles before pressure treatment to REA specs.
2.4
CROSSARMS
A.
Description: Solid-wood distribution type, complying with RUS REA Bulletin 1728H-701 for
specified construction grade, and IEEE C2 for required climbing space and wire clearances.
B.
Braces: Galvanized, flat, ferrous-metal units; 1/4 inch (6 mm) thick by 1 1-/4 inches (30 mm)
wide, minimum, with length to suit crossarm dimensions.
2.5
HARDWARE AND ACCESSORIES
A.
Description: Ferrous-metal items include, but are not limited to, bolts, nuts, washers, crossarm
gains and braces, insulator pins, anchor rods, anchors, eyebolts, and staples.
1.
Comply with ANSI C135.1, ANSI C135.2, ANSI C135.4, ANSI C135.14, ANSI C135.22,
ANSI C135.33, and RUS Informational Publication 202-1 listings with the exception that
base material shall be malleable iron or ductile iron, and finish shall be hot-dip
galvanized.
B.
Guy Strand Assemblies: Cable and attachments. Include strain insulators where indicated and
if required by IEEE C2. Assemblies shall have uniform minimum breaking strength for
components of each assembly.
1.
Cable: Seven strand. Zinc-coated steel, complying with ASTM A 475.
2.
Cable Termination: Thimble eye.
C.
Anchor and Anchor-Rod Assemblies: Hot-dip galvanized steel.
1.
Anchors: Power-installed screw type.
2.
Anchor Rods for Power-Installed Screw Anchors: ASTM A 53/A 53M, Schedule 80 pipe,
with coupling, and twin thimble eye.
D.
Guy Markers: Round vinyl or PVC material, yellow color, 96 inches (2440 mm) long. Shatter
resistant at temperatures below 0 deg F (minus 18 deg C).
E.
Insulator Brackets: Hot-dip galvanized steel, style as indicated, designed to hold vertical-postor -pin-type insulators, with one-bolt attachment to pole.
F.
Pole Riser Shields: Galvanized steel with boot.
FA4608-16-R-0013
Attachment 1
Page 66 of 79
G.
Padlocks: ASTM F 883, Class PO1, Grade 1, Option A.
H.
Insulators: Units rated 6 kV and above shall be free from radio interference.
1.
Porcelain insulators shall be wet-process type, complying with the following types:
a.
b.
2.
Pin: ANSI C29.5.
Line Post: ANSI C29.7. Include mounting stud of length suitable for each
mounting arrangement used.
c.
Suspension: ANSI C29.2.
d.
Guy Strain: ANSI C29.4.
e.
Secondary Spool: ANSI C29.3, Class 53-2.
Polymer-composite, fiberglass-reinforced insulators shall comply with the following:
a.
b.
c.
I.
2.6
Line Post: Comply with CEA LWIG-02.
Dead End/Suspension: Comply with CEA LWIG-01.
Guy Strain: Fiberglass reinforced, epoxy finished. Designed specifically for use in
guy assemblies.
Grounding Materials: Comply with Division 16 Section "Grounding and Bonding," using
materials listed by RUS for the intended purpose without restriction.
1.
Conductors: No. 4 AWG, minimum; bare, solid, annealed copper, complying with
ASTM B 8, unless otherwise indicated.
2.
Ground Conductor Protectors: PVC or half-round wood molding, fir, pressure treated
according to AWPA C25.
SURGE ARRESTERS
A.
Manufacturers:
1.
Cooper Power Systems.
2.
General Electric Company; Transmission Systems.
3.
Joslyn Manufacturing Company.
4.
Ohio Brass Company; Hubbell, Inc.
5.
Tyco Electronics/Raychem.
B.
Intermediate-Class Surge Arresters: Porcelain-enclosed, gapless, metal-oxide type, complying
with IEEE C62.11 and NEMA LA 1.
1.
Voltage Rating: 9/10kV, unless otherwise indicated.
2.7
CUTOUTS, SWITCHES, AND FUSES
A.
Manufacturers:
1.
ABB Inc.; Distribution Automation Equipment Division.
2.
AB Chance Co.; Hubbell, Inc.
3.
Cooper Power Systems.
4.
S&C Electric Company.
B.
Description: Medium-voltage disconnect, protective units shall be rated for the line-to-line
voltage of the systems in which installed, unless higher ratings are indicated. BIL ratings 150
kV.
1.
Momentary Current Rating of Switching Devices: 40 kA, asymmetrical at nominal system
operating voltage.
2.
Fuse Characteristics: Time-current characteristics for each set of fuses selected
according to written recommendations of manufacturer of component protected by the
FA4608-16-R-0013
Attachment 1
Page 67 of 79
3.
C.
2.8
fuses and coordinated with upstream and downstream protective devices. Prepare timecurrent coordination curves according to IEEE 242 that illustrate optimum coordination of
devices in this Project.
Interrupting Rating of Fuses: 14,000 symmetrical A at nominal system operating voltage.
Fuse Cutouts: Open type, rated 200 A, continuous, complying with ANSI C37.42.
1.
Fuses: Enclosed link, Type K, complying with ANSI C37.42.
2.
Switching Application: Include switch link instead of fuse.
3.
Switch Current Interrupting Rating: 14,000 amperes symmetrical.
SOURCE QUALITY CONTROL
A.
Factory Tests:
standards.
Conduct routine tests of medium-voltage switches according to referenced
B.
Factory Inspections: Engage a qualified independent timber inspection agency to inspect poles
and crossarms before and after preservative treatment and report results of inspection.
PART 3 - EXECUTION
3.1
GENERAL INSTALLATION REQUIREMENTS
A.
Install underground power and metering circuits and those indicated to be in raceway according
to Division 16 Section "Underground Ducts and Utility Structures" and Division 16 Section
"Medium-Voltage Cables," and make splices and terminations for those circuits according to
those Sections.
B.
Verify dimensions by field measurement, and identify locations of poles, guy anchors, and other
features. Also identify locations of connection to new and existing supply lines and to primary
services. Notify Contracting Officer of discrepancies and field conditions that are not indicated
and that will affect installation.
C.
Ground equipment according to Division 16 Section "Grounding and Bonding."
D.
Apply warning signs and equipment labels according to Division 16 Section "Basic Electrical
Materials and Methods."
E.
Poles shall be labeled with 3” aluminum labels. Labels shall include the feeder number - pole
number and shall be visible from the road.
3.2
CONDUCTOR INSTALLATION, GENERAL
A.
Handle and string conductors to prevent cuts, gouges, scratches, kinks, flattening, or
deformation. Remove damaged sections and splice conductors.
1.
String new conductors to "initial" sag table values recommended by manufacturer for type
and size of conductor.
B.
Connections, Splices, and Terminations: Use kits listed for the specific type of connection and
combination of materials used in the connection, or recommended for the specific use by
manufacturer of material on which applied.
1.
Splice Location: Do not install within 10 feet (3 m) of a support.
FA4608-16-R-0013
Attachment 1
Page 68 of 79
2.
3.3
Splices and Terminations of Covered Conductors: Comply with manufacturer's written
instructions.
MEDIUM-VOLTAGE LINE CONDUCTOR INSTALLATION
A.
Application: Install bare conductors, unless otherwise indicated.
B.
Armor Rod: Install to protect conductors if line conductors are supported by insulators.
C.
Flat Aluminum Armor Wire: Install to protect conductors if they are supported by, or attached to,
galvanized or coated iron or steel clamps or fittings.
D.
Support line conductors and taps as follows:
1.
Use wire ties for conductor attachment to pin and vertical post insulators, unless
otherwise indicated.
2.
Install wire ties tight against conductor and insulator, and turn ends back, flat against
conductor, to eliminate exposed wire ends.
3.
Use wire clamps on horizontal post, dead end, and suspension insulators, unless
otherwise indicated.
3.4
POLE AND CROSSARM INSTALLATION
A.
Pole Orientation: Align curve of curved wood poles with straight-line runs of three or more
poles. Align gained surfaces perpendicular to runs.
B.
Elevation of Line above Grade: Install poles with top at same elevation, unless grade changes
dictate elevation change in poles, and according to the following:
1.
On level ground, set poles so tops of consecutive poles vary not more than 60 inches
(1500 mm) in elevation.
2.
Shorten wood poles by cutting off the top and make cuts to shed water. Apply
preservative to cuts.
C.
Set poles depth at 10% of pole length plus 2 foot with a minimum of 5’ depth according to the
following:
1.
Make pole holes vertical, uniform in diameter, and large enough to permit effective use of
tamping bars all around. Bore or excavate holes with an average diameter at grade less
than twice the diameter of the pole at the same grade.
2.
Use minimum depths indicated, except at locations where hole is partly or entirely in rock
and if hole is not vertical or has a diameter at grade larger than two times the pole
diameter at the same level; in these conditions, increase the depth of the hole by the
following increments before setting the pole:
a.
Poles up to 35 Feet (10.6 m) Long: 24 inches (600 mm).
b.
Poles 36 to 60 Feet (11 to 18.3 m) Long: 30 inches (760 mm).
c.
Poles 61 to 75 Feet (18.6 to 22.9 m) Long: 36 inches (900 mm).
3.
For poles on slopes, indicated hole depth is from finished grade at lowest side of hole.
4.
Set poles in alignment and plumb except at dead ends, angles, and points of extra strain;
rake poles against conductor strain 1 inch (25 mm) minimum, 2 inches (51 mm)
maximum, (after conductors are installed at required tension) for each 10 feet (3 m) of
pole length. Rake poles so they will not lean or bend in direction of strain when loaded.
5.
Backfill holes in 6-inch (150-mm) maximum lifts, and thoroughly tamp each layer before
starting the next.
6.
Place surplus earth around pole in a conical shape, and tamp thoroughly to provide
drainage away from pole.
FA4608-16-R-0013
Attachment 1
Page 69 of 79
7.
Set poles so alternate crossarm gains face in alternate directions, except at terminals and
dead ends; place gains on last two poles on side facing terminal or dead end.
D.
Field treat factory-treated poles and crossarms as follows:
1.
Poles Treated More Than One Year before Installation: Treat portion from 24 inches
(600 mm) above ground line to butt.
2.
Field-Bored Holes and Field-Cut Gains and Pole Tops: Treat cut portions.
3.
Unused Holes: Treat and plug with treated-wood-dowel drive pins.
4.
Engage the services of a technician certified according to Part 1 of this Section to apply
treatment. Comply with requirements in AWPA standards that govern original factory
treatment for field-applied treatment chemicals and application.
E.
Crossarm Installation: Set line crossarms at right angle to line for straight runs and for angles
45 degrees and more. Bisect angles less than 45 degrees. Install top line of crossarms a
minimum of four (4) feet below top of pole to allow for the installation of the static wire.
1.
Buck Arms: Install at corners and junction poles, unless otherwise indicated.
2.
Double Crossarms: Install at dead ends, corners, angles, and line crossings.
3.
Equipment Arms: Locate below lines and set parallel or at right angles to them,
whichever provides best climbing space.
4.
Gains: Install factory-cut or metal pole gains only. Do not cut gains in field without
specific written approval.
3.5
HARDWARE AND ACCESSORIES INSTALLATION
A.
Install washers against wood and under nuts, including eyenuts and locknuts.
B.
Install nuts and locknuts wrench-tight on threaded connections.
C.
Install guys to resist unbalanced loads, including those developed at angles, corners, and dead
ends. Install two or more guys if a single guy will not provide adequate strength. Install
separate guys if unbalanced loads are separated by 36 inches (900 mm) or more.
D.
Protect guy strands from damage. Replace damaged guy strands. Install guy insulators where
required to comply with IEEE C2 clearance requirements and elsewhere, where indicated.
E.
Select guy anchors having adequate strength and holding area to suit anchor load and soil
conditions at location of that anchor.
1.
Soil Anchors: Align anchors in soil with guy. Set with anchor rod pointing at guy
attachment on pole and rod projecting 6 to 9 inches (150 to 230 mm) from ground.
2.
Rock Anchors: Place anchors at right angles to guy, in hole drilled 12 inches (300 mm)
into solid rock, with rod projecting 4 to 6 inches (100 to 150 mm) from ground.
F.
Guy Markers: Install at anchor end of guys. Clamp to guy strand or anchor at top and bottom
of marker.
3.6
INSULATOR INSTALLATION
A.
Medium-Voltage Line Application: Install pin or post type, except install suspension type at
corners, angles, dead ends, and other locations where horizontal forces exceed rated values for
pin or line-post-type units.
1.
Install suspension insulators and hardware that have mechanical strength exceeding
rated breaking strength of attached conductors.
2.
Install horizontal line-post insulators for armless construction.
FA4608-16-R-0013
Attachment 1
Page 70 of 79
B.
Post-Insulator Conductor Support: Where installed horizontally and for line angles more than
15 degrees, install clamp-top conductor clamps.
C.
Install spool-type insulators for secondary lines mounted on clevis attachments or secondary
racks.
D.
Guy Strain Type: Install fiberglass-reinforced units.
3.7
SURGE ARRESTERS
A.
3.8
Install surge arresters to protect distribution, and other items indicated.
CUTOUT, SWITCH, AND FUSE INSTALLATION
A.
3.9
Hook-Stick-Operated Switches: Install to maximize safe operating access.
FIELD QUALITY CONTROL
A.
Manufacturer's Field Service: Engage a factory-authorized service representative to inspect
field-assembled components and equipment installation, including connections. Report results
in writing.
B.
Testing Agency: Perform the following tests and inspections and prepare test reports:
1.
Furnish instruments and equipment required for tests that comply with NETA ATS.
2.
Guy Anchors: Test one of each type and capacity installed. Apply rated pull-out force in
the same pull direction applied by the guy at the test location.
a.
Acceptable Test Results: Denoted by movement of less than 3/8 inch (10 mm) by
the holding component of the anchor in the earth or other medium in which it is
installed.
b.
Replace or reinstall, at Contracting Officer’s Representative’s option, all anchors of
same type and capacity as anchor type that fails this test.
3.
Ground Resistance: Comply with Division 16 Section "Grounding and Bonding."
Measure resistance of each separate grounding electrode, including pole grounds. Also
measure resistance of separate grounding electrode systems before bonding together.
a.
Perform tests and obtain acceptable results before energizing any portion of
overhead electrical distribution system.
b.
Results and Follow-up: If ground resistance for a single ground electrode or pole
ground, tested individually, exceeds 25 ohms, add a ground electrode not less
than 10 feet (3 m) away and interconnect with No. 2 AWG minimum bare
conductor buried at least 12 inches (300 mm) below furnished grade.
4.
Aerial Conductor Sag and Tension: Observe procedures used by Contractor to verify
that initial stringing sags and tensions comply with IEEE C2 and conductor
manufacturer's Product Data and written recommendations.
5.
Existing Surge Arresters: Disconnect and measure resistance between line and ground
terminals with a megger rated 600 V or more. Acceptable resistance values are 300
megohms and more.
6.
New Surge Arresters, Cutouts, and Switches: Inspect after installation and connection to
wiring. Verify that ratings and characteristics match approved submittals and comply with
system requirements. Verify that installation complies with requirements and that
clearances of units and connecting wiring comply with IEEE C2 requirements.
a.
Verify proper grounding of metallic equipment parts.
FA4608-16-R-0013
Attachment 1
Page 71 of 79
b.
c.
d.
C.
3.10
A.
3.11
A.
Fuses and Disconnect Links: Verify that ratings and characteristics match
submittals and comply with system requirements.
Switches:
1)
Manually operate each cutout and switch at least three times, to verify
proper operation.
2)
Verify correct contact alignment, blade penetration, travel stops, and arc
interrupter operation.
Verify that clearances of energized parts and connecting wires comply with
IEEE C2 requirements.
Remove and replace malfunctioning units and retest as specified above.
CLEANING
After completing equipment installation, inspect equipment. Remove spots, dirt, and debris.
Repair damaged finish to match original finish. For distribution transformer, use tank touchup
paint provided by manufacturer.
DEMONSTRATION
Engage a factory-authorized service representative to train Owner's maintenance personnel to
adjust, operate, and maintain overhead electrical distribution. Refer to Division 1 Section
"Closeout Procedures."
END OF SECTION 16315
FA4608-16-R-0013
Attachment 1
Page 72 of 79
SECTION 16355 – MEDIUM VOLTAGE PAD-MOUNTED SWITCHGEAR
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A.
1.2
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
SUMMARY
A.
1.3
This Section includes medium-voltage pad-mounted S & C vista switchgear.
DEFINITIONS
A.
GFCI: Ground-fault circuit interrupter.
B.
Switched way: A three phase circuit entrance to the bus through a switch. For single phase
switches, it is a single-phase entrance to the bus through a switch.
1.4
SUBMITTALS
A.
Product Data: Manufacturer's descriptive literature for the pad-mounted switchgear, high
voltage connectors, surge arrestors and electronic overcurrent control curves.
B.
Shop Drawings: For each panelboard and related equipment.
1.
Dimensioned plans, elevations, sections, and details. Show tabulations of installed
devices, equipment features, and ratings. Include the following:
a.
Enclosure types and details.
b.
Bus configuration, current, and voltage ratings.
c.
Short-circuit current rating of padmounted switchgear and overcurrent protective
devices.
d.
Single line diagram.
e.
Features, characteristics, ratings, and factory settings of individual overcurrent
protective devices and auxiliary components.
2.
Wiring Diagrams: Power, signal, and control wiring.
C.
Qualification Data: For testing agency.
D.
Field quality-control test reports including the following:
1.
Test procedures used.
2.
Test results that comply with requirements.
3.
Results of failed tests and corrective action taken to achieve test results that comply with
requirements.
E.
Operation and Maintenance Data:
For medium-voltage pad-mounted switchgear and
components to include in emergency, operation, and maintenance manuals. In addition to
items specified in Division 1, include the following:
1.
Manufacturer's written instructions for testing and adjusting overcurrent protective
devices.
FA4608-16-R-0013
Attachment 1
Page 73 of 79
2.
1.5
Time-current curves, including selectable ranges for each type of overcurrent protective
device.
QUALITY ASSURANCE
A.
Source Limitations: Obtain medium-voltage pad-mounted switchgear, overcurrent protective
devices, components, and accessories through one source from a single manufacturer.
B.
Product Options: Drawings indicate size, profiles, and dimensional requirements of mediumvoltage pad-mounted switchgear and are based on the specific system indicated. Refer to
Division 1 Section "Material and Equipment."
C.
Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
D.
Comply with ANSI C57.12.28 & C57.12.29.
E.
Comply with NFPA 70 (2011).
1.6
PROJECT CONDITIONS
A.
Environmental Limitations: Rate equipment for continuous operation under the following
conditions, unless otherwise indicated:
1.
Ambient Temperature: Not exceeding 104 degrees F (40 degrees C).
2.
Altitude: Not exceeding 6600 feet (2000 meters).
B.
Service Conditions: NEMA PB 1, usual service conditions, as follows:
1.
Ambient temperatures within limits specified.
2.
Altitude not exceeding 6600 feet (2000 meters).
C.
Interruption of Existing Electric Service: Do not interrupt electric service to facilities occupied by
Owner or others unless permitted under the following conditions and then only after arranging to
provide temporary electric service according to requirements indicated:
1.
Notify Contracting Officer's Representative no fewer than seven days in advance of
proposed interruption of electrical service.
2.
Do not proceed with interruption of electrical service without Contracting Officer's
Representative's written permission.
1.7
COORDINATION
A.
Coordinate size and location of concrete bases. Cast anchor-bolt inserts into bases. Concrete,
reinforcement, and formwork requirements are specified in Division 3.
PART 2 - PRODUCTS
2.1
SF6/HIGH-FIREPOINT FLUID INSULATED PAD-MOUNTED SWITCHGEAR (IEEE C37.74)
FA4608-16-R-0013
Attachment 1
Page 74 of 79
A.
Ratings and Test Requirements: The voltage rating of the switchgear shall be 15.5 kV, as
indicated. The corresponding ratings associated with the required switchgear voltage rating
shall be as follows:
1.
Rated Maximum Voltage, (kV): 15.5
2.
Rated Withstand Impulse voltage, (kV BIL): 95.
3.
Continuous and Load Interrupting Current, (A): 1200.
4.
Short-Time Current, (kA rms Sym): 25.0.
5.
Short-circuit Interrupting Current, (kA rms Sym): 25.0.
B.
Switchgear Construction: Medium-voltage pad-mounted switchgear shall be of dead front type
construction. Switch contacts and cable entrance terminations shall be contained in a sealed,
dielectric-filled stainless steel tank. Switchgear shall be shipped factory filled with appropriate
levels of SF6 gas conforming to ASTM D2472 or less-flammable, high-firepoint biodegradable
fluid conforming to ASTM D6871 and IEC 61099. Switchgear shall be configured with load
interrupting and fault interrupting switched ways of the configurations indicated on the drawings.
Switchgear shall have front accessible terminations suitable for cables entering from below with
the manual operating provisions either mounted on the rear or capable of hookstick operation.
Switch contact positions for switched ways shall be visible through viewing windows in the
switchgear tank located adjacent to the manual operating provisions. Provide internal gas
pressure gage or fluid level gage in viewable location from switch operating handle. Each
switched way shall have three position switch; Open, Closed, Ground and provisions for
grounding.
1.
Pad-Mounting Provisions: Provide enclosed switchgear suitable for installation on a
concrete pad. Switchgear support frame, enclosure base, and enclosure shall be
fabricated of ASTM A167 type 304 or 304L stainless steel. Paint enclosure including
base ASTM D1535 brown, Federal spec 20117. Paint coating system shall comply with
ANSI C57.12.28 and ANSI C57.12.29 regardless of equipment material.
2.
Each switch will have an 18” skirt.
C.
Load Interrupting Switched Ways: Load interrupter switched ways shall provide three-pole
group operated switching of the configuration indicated on the drawings.
D.
Fault Interrupting Switched Ways: IEEE C37.60, IEC 62271-111. Provide non-fused, nonreclosing, manual reset, vacuum interrupters consisting of vacuum interrupter and a spring
assisted operating mechanism. Each fault interrupting switched way shall utilize internally
mounted current transformers and an electronic overcurrent control to provide three-pole
ganged tripping as indicated for single phase and three-phase faults. The electronic
overcurrent control shall have provisions for a wide variety of field changeable time-current
characteristic curves with ten field changeable trip levels through a current range of 0-600
amperes. The electronic overcurrent control shall have an EIA-RS-485 communications port
that supports Modbus and DNP 3.0 Level 2 protocols. Fault interrupting switched ways shall
have provisions for remote tripping via an external dry contact device. Remote trip control
power shall be 120 Vac.
E.
Automatic Switch Controls: Provide an automatic switch control system to execute Manual,
Automatic Source-Transfer, and ASCADA operation of the load interrupting switch ways. The
automatic switch control shall accept 120 Vac control power and shall be powered from an
integral battery-charger DC supply system. Switch way operation shall be via motor operators
and associated motor operator controllers. The motor operator controllers shall have "Close,"
"Open," and "Ground" pushbuttons for manual operation. (The Source-Transfer controls shall
effect opening of an incoming switch way where voltage is lost and close to other incoming
switch way if voltage is present. The Source-Transfer controls shall include an overcurrentlockout feature that prevents automatic closing of a switch way into a system fault.) The
automatic switch control system shall execute remote commands received from a SCADA
master station and transmit switchgear operation information to a SCADA master station via
DNP 3.0 communications. Execution of remote commands shall include enabling of the
FA4608-16-R-0013
Attachment 1
Page 75 of 79
Source-Transfer controls and transfer of switch ways to "Close, "Open," and "Ground" positions.
Transmission of switchgear information shall include switch way positions, voltage and current
readings, and DC supply system status.
F.
Low Voltage Test Pins: Load interrupting switch ways shall have internal load side voltage
sensors and external test pins that allow for low voltage checks to confirm energized and inphase conditions using a standard high-impedance voltmeter.
G.
Dead-Front High-Voltage Bushings (IEEE 386): 15kV, 95kV BIL. Provide 600 ampere onepiece deadbreak apparatus bushings for each switched way.
1.
Parking stands: Provide a parking stand near each dead-front bushing.
2.
Provide insulated standoff bushings for parking of energized load-break connectors on
each parking stand.
H.
Finish: Barksdale brown. Federal Specification No. 20117. S & C Electric No. S121
2.2
INSULATED HIGH-VOLTAGE CONNECTORS (IEEE 386)
A.
Provide corresponding connector for each switched way. Connectors shall have a grounding
eye and test point.
B.
Load Interruptor:
1.
Amperage: 900 ampere, dead break connector.
2.
Voltage: 15.5kV continuous, 95kV BIL.
3.
Short Circuit: 25,000 amperes, symmetrical.
C.
Fault Interrupter:
1.
Amperage: 600 ampere, deadfront connector.
2.
Voltage: 15.5kV continuous, 95kV BIL.
3.
Short Circuit: 12,500 amperes, symmetrical.
D.
Connectors shall have a 200-ampere bushing interface for surge arrestors and transformers.
E.
Provide one set of three grounding elbows. Grounding elbows shall be delivered to 2 CES
‘Electric Shop POC Robert Gardner.
2.3
LIGHTING ARRESTORS (IEEE C62.11)
A.
2.4
Rated 9/10 kV as indicated, fully shielded, dead-front, metal-oxide-varistor, elbow type with
resistance-graded gap, suitable for plugging into inserts. Provide arresters on switched ways as
indicated.
SF6 REFILL CYLINDERS
A.
2.5
Provide two SF6 refill cylinders, minimum size of 6 pounds of SF6; include regulator, valves,
and hose for connection to the fill valve of the switch.
SOURCE QUALITY CONTROL
A.
Switchgear Design and Production Tests: Furnish reports which include results of design and
production tests performed according to IEEE C37.74 or IEEE C37.60. Production tests shall
FA4608-16-R-0013
Attachment 1
Page 76 of 79
be performed by the manufacturer on each switchgear assembly to ensure that design
performance is maintained in production.
PART 3 - EXECUTION
3.1
INSTALLATION
A.
Electrical installations shall conform to IEEE C2, NFPA 70, and to the requirements specified
herein.
B.
Install PMS on concrete bases.
1.
Construct concrete bases of dimensions indicated, but not less than 12 inches (254 mm)
larger in both directions than supported unit and 6 inches (200 mm) high.
2.
Use 3000-psi (20.7-MPa), 28-day compressive-strength concrete and reinforcement as
specified in Division 3 Section "Cast-in-Place Concrete."
3.
Place and secure anchorage devices. Use supported equipment manufacturer's setting
drawings, templates, diagrams, instructions, and directions furnished with items to be
embedded.
4.
Tack-weld or bolt PMS to concrete bases per manufacture installation instructions
5.
Block out windows in each section of the PMS. After curing, remove blocks and fill with
gravel to within 1” of top and cap with mortar. Caulk around all entrances and around
mortar to prevent ants from coming in.
C.
Signs: Danger High Voltage installed on all sides.
D.
Equipment Identification: see statement of work
3.2
GROUNDING
A.
3.3
NFPA 70 and IEEE C except that grounds and grounding systems shall have a resistance of
solid earth ground not exceeding 5 ohms. When work, in addition to that indicated or specified,
is directed to obtain the specified ground resistance, the provision of the contract covering
“Changes” shall apply.
1.
Grounding Electrodes: Four (4). Provide driven ground rods as specified in Section
16060, “Grounding and Bonding” at each corner of switchgear pad.
2.
Switchgear Grounding: Connect #1/0 bare copper conductor ground loop, not less than
30 inches below grade to the upper end of the ground rods by exothermic welds. Provide
#1/0 bare copper conductors connecting the switchgear grounding provisions to two
different ground rods. Connect at least one conductor to the counterpoise and bond in
each switch compartment.
3.
Connections: Make joints in grounding conductors and ground loop by exothermic weld
or compression connector. Exothermic welds and compression connectors shall be
installed as specified in Section 16060, “Grounding and Bonding.”
4.
Grounding and Bonding Equipment: UL 467, except as indicated or specified otherwise.
FOUNDATION FOR EQUIPMENT AND ASSEMBLIES
A.
Mount switch on concrete slab. Slab shall be at least 6 inches thick, reinforced with a 6 by 6 –
W2.9 by W2.9 mesh, placed uniformly 4 inches from the top of the slab. Slab shall be placed
on a 6 inch thick, well-compacted gravel base. Top of concrete slab shall be approximately 4
FA4608-16-R-0013
Attachment 1
Page 77 of 79
inches above finished grade. Edges above grade shall have ½ inch chamfer. Slab shall be of
adequate size to project at least 8 inches beyond equipment.
B.
3.4
Stub up conduits with bushings, 2 inches into cable wells in the concrete pad. Coordinate
dimensions of cable wells with switch cable training areas. Concrete work shall be as specified
in Division 3, “Cast-In-Place Concrete”.
FIELD QUALITY CONTROL
A.
Performance of Acceptance Checks and Tests: Perform in accordance with the manufacturer’s
recommendations, NFPA 70B, NETA ATS and referenced ANSI standards. Include the
following visual and mechanical inspections and electrical tests, performed in accordance with
NETA ATS.
1.
Switchgear:
a.
Visual and Mechanical Inspection:
1)
Compare equipment nameplate information wth specifications and approved
shop drawings.
2)
Inspect physical and mechanical condition.
3)
Check for proper anchorage, alignment, required area clearances, and
grounding.
4)
Perform mechanical operator tests in accordance with manufacturer’s
instructions.
5)
Verify that insulating SF6 gas pressure or dielectric flued lvevel is correct.
6)
Inspect all indicating devices for proper operation.
7)
Test interlock systems for proper operation and sequencing.
b.
Electrical Tests:
1)
Perform contact-resistance tests.
2)
Trip fault interrupters by operation of overcurrent control.
3)
Perform insulation-resistance test.
4)
Perform an over-potential test on each switched way pole with switched way
in the open position in accordance with the manufacturer’s instructions.
5)
Set fault interrupter overcurrent control in accordance with government
provided settings. Request settings from government, in writing, a minimum
of 30 days prior to scheduling electrical tests.
2.
Electrical Tests:
a.
Perform ground-impedance measurements utilizing the fall-of-potential method.
On systems consisting of interconnected ground rods, perform tests after
interconnections are complete. On systems consisting of a single ground rod
perform tests before any wire is connected. Take measurements in normally dry
weather, not less than 48 hours after rainfall. Use a portable ground testing
megger in accordance with manufacturer’s instructions to test each ground or
group of grounds. The instrument shall be equipped with a meter reading directly
in ohms or fractions thereof to indicate the ground value of the ground rod or
grounding systems under test.
b.
Submit t he measured ground resistance of each ground rod and grounding
system, indicating the location of the rod and grounding system. Include the test
method and test setup (i.e., pin location) used to determine ground resistance and
soil conditions at the time the measurements were made.
c.
Follow-Up Verification: Upon completion of acceptance checks and tests, and the
contractor shall show by demonstration in service that devices are in good
operating condition and properly performing the intended function. Test shall
require each item to perform its function not less than three times. As an
exception to requirements stated elsewhere in the contract, notify the Contracting
Officer’s Representative 5 working days in advance of the dates and times for
checks and tests.
FA4608-16-R-0013
Attachment 1
Page 78 of 79
END OF SECTION 16355
FA4608-16-R-0013
Attachment 1
Page 79 of 79
Division 1 – General Requirements
01010
01045
01090
01200
01400
01500
01600
01700
01710
01732
03300
Summary of the Work
Cutting and Patching
Definitions and Standards
Project Meetings
Submittals
Temporary Facilities
Material and Equipment
Project Closeout
Cleaning
Selective Demolition
Cast-in-Place Concrete
Division 16 – Electrical
16050
16060
16124
16135
16315
16355
Basic Electrical Materials and Methods
Grounding and Bonding
Medium Voltage Cables
Underground Ducts and Utility Structures
Overhead Electrical Distribution
Medium Voltage Pad-Mounted Switchgear
Download