DIVISION 1 1 Submittal Procedures Section 01330 Page 1 of 3 GENERAL 1.1 Administrative 1.1.1 Submit to the City submittals listed for review. Submit with reasonable promptness and in orderly sequence to allow opportunity for City review prior to ordering of materials or tendering of works for construction. Failure to submit in ample time is not considered sufficient reason for an extension of development, subdivision or project requirements and may cause delays in the scheduling works to be completed by City forces as part of the development, subdivision or project. No claim for extension by reason of such default will be allowed. 1.1.2 Work affected by submittal shall not proceed until review is complete. 1.1.3 Present shop drawings, product data, samples and mock-ups in SI Metric units. 1.1.4 Where items or information is not produced in SI Metric units converted values are acceptable. 1.1.5 Review submittals for projects prior to submission to City. This review represents that necessary requirements have been determined and verified, or will be, and that each submittal has been checked and coordinated with requirements of the Work and the Contract Documents. Submittals not stamped, signed, dated and identified as to specific project will be returned without being examined and shall be considered rejected. 1.1.6 Notify City in writing at time of submission, identifying deviations from requirements of Contract Documents and stating reasons for deviations. 1.1.7 Verify that field measurements and affected adjacent Work are coordinated. 1.1.8 The Owner’s, Developer’s or Contractor's responsibility for errors and omissions in submission is not relieved by the City's review of submittals. 1.1.9 The Owner’s, Developer’s or Contractor's responsibility for deviations in submission from requirements of Contract Documents is not relieved by the City review. 1.1.10 Keep one reviewed copy of each submission on site. 1.2 Shop Drawings and Product Data 1.2.1 The term "shop drawings" means drawings, diagrams, illustrations, schedules, performance charts, brochures and other data, which are to be provided by Contractor to illustrate details of a portion of Work. January 2004 DIVISION 1 Submittal Procedures Section 01330 Page 2 of 3 1.2.2 Indicate materials, methods of construction and attachment or anchorage, erection diagrams, connections, explanatory notes and other information necessary for completion of Work. Where articles or equipment attach or connect to other articles or equipment, indicate that such items have been coordinated, regardless of the Section under which adjacent items will be supplied and installed. Indicate cross-references to design drawings and specifications. 1.2.3 Allow ten days for City's review of each submission. 1.2.4 Make changes in shop drawings as City may require, consistent with Contract Documents. When resubmitting, notify City in writing of any revisions other than those requested. 1.2.5 Accompany submissions with transmittal letter containing: 1.2.6 1.2.6.1 Date. 1.2.6.2 Project title and number. 1.2.6.3 Contractor's name and address. 1.2.6.4 Identification and quantity of each shop drawing, product data and sample. 1.2.6.5 Other pertinent data Submissions shall include: 1.2.6.6 Date and revision dates. 1.2.6.7 Project title and number. 1.2.6.8 Name and address of: • • • 1.2.6.9 Contractor or Subcontractor. Supplier. Manufacturer. Contractor's stamp, signed by Contractor's authorized representative certifying approval of submissions, verification of field measurements and compliance with Contract Documents. 1.2.6.10 Submit 6 prints of shop drawings for each requirement requested in specification Sections and as City may reasonably request. One transparency of each shop drawing may be submitted in lieu of the multiple copies. Electronic copies may be used for submission upon approval by City. January 2004 DIVISION 1 Submittal Procedures Section 01330 Page 3 of 3 1.2.6.11 Submit 6 copies of product data sheets or brochures for requirements requested in specification Sections and as requested by City where shop drawings will not be prepared due to standardized manufacture of product. 1.2.6.12 Delete information not applicable to project. 1.2.6.13 Supplement standard information to provide details applicable to project. 1.2.6.14 If upon review by City, no errors or omissions are discovered or if only minor corrections are made, three copies will be returned and fabrication and installation of Work may proceed. If shop drawings are rejected, noted copy will be returned and resubmission of corrected shop drawings, through same procedure indicated above, must be performed before fabrication and installation of Work may proceed. 2 PRODUCTS (Not Applicable) 3 EXECUTION (Not Applicable) ______________________________________________ January 2004