SECTION 00100 PAGE 1 2011-06-03 INSTRUCTIONS TO BIDDERS IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 1. GENERAL .1 All articles in this Section are project specific Instructions to Bidders. 2. INVITATION TO TENDER .1 Sealed tenders will be received by the Engineer until 3:00pm, 22 June 2011 for the following project: Project Name: In-Stream Tidal Power Generating Plant Substation Development Old Black Rock Road Black Rock, Nova Scotia .2 Site access, for the purpose of reviewing existing site conditions, is unrestricted. The substation site is located on the Old Black Rock Road, approximately 500m to the north of the West Bay Road in Black Rock, Nova Scotia, approximately 10km west of Parrsboro, Nova Scotia. .3 The lowest price Tender will not necessarily be accepted. 3. SITE VISIT .1 A site visit has been scheduled for 10:00am, 10 June 2011. Prime Contractors and their Sub-Contractors shall meet at the Fundy Ocean Research Center for Energy Interpretive Center, located at 1156 West Bay Road, for a technical review of the project documents, followed by a visit to the Substation site, approximately one kilometer away. 4. TENDERS .1 Submit one (1) original tender on the enclosed Tender Form. Each item on the Tender Form shall be completed. Incomplete tenders will be rejected. The Tender shall be submitted in a sealed envelope clearly marked: TENDER: In-Stream Tidal Power Generating Plant Substation Development PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 00100 PAGE 2 2011-06-03 INSTRUCTIONS TO BIDDERS IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 4./ To: Fundy Ocean Research Center for Energy PO Box 2573 Halifax, Nova Scotia B3J 3N5 c/o Strum Engineering Associates Ltd. 80 Eileen Stubbs Ave. Dartmouth, Nova Scotia B3B 1Y6 .2 On the left hand upper corner of the envelope, show the name and address of the Bidder submitting the Tender. .3 Deliver the Tender on or before the advertised, or officially amended, tender time and date. .4 The Tender envelope shall contain the following documents: .1 Original copy of the Tender Form, officially signed. .2 Bid Bond or certified cheque in the amount of 10% of the Tender price. .5 The Bidder shall list, in the space provided in the Supplementary Information, the names and work tasks of each proposed Sub-Contractor. A change in Sub-Contractor from the list submitted shall require permission in writing. 5. CONTRACT FORM .1 CCDC 2 – Stipulated Price Contract shall be used as the formal contract document between the Prime Contractor and Fundy Ocean Research Center for Energy. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 00101 PAGE 1 2011-06-03 TENDER FORM IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT NAME OF PRIME CONTRACTOR: 1. TENDER PRICE .1 I/We, the undersigned, having carefully examined all of the Tender Documents and proposed Contract Documents and having examined the site and the site conditions affecting the work, hereby tender and offer to enter into a contract and agree to furnish all specified materials, labour, equipment and services necessary to complete the entire Work in accordance with the requirements of the official Tender Documents, for the Stipulated Sum of: $ /100 Dollars (Write Out in Full) to Addendum No. , inclusive and our .2 I/We, have examined Addendum No. Tender Price includes all labour, materials, etc. called for by said Addenda. 2. AGREEMENT .1 I/We, further agree that this Tender is to continue Open to acceptance and irrevocable until thirty (30) days after the Tender Close Date. .2 I/We, agree to be substantially completed and ready for occupancy by the Owner no later than 30 September 2011, but for a mutually agreed change due to unforeseen circumstances. Signed and submitted by: (Company Name) (Company Address) (Telephone No.) (Facsimile No.) (Name and Title of Authorized Signing Officer) (Signature of Authorized Signing Officer) Dated this day of PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 , 2011. CONTRACT NO. 023-478-7-11 SECTION 00101 PAGE 1 2011-06-03 SUPPLEMENTARY INFORMATION IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 1. REQUIREMENTS .1 A Bid Bond or certified cheque, in the amount of ten percent (10%) of the Tender Price shall be submitted with the Tender Form. .2 Within four (4) working days of acceptance of the Tender Price, the Contractor shall submit the following information to the Owner: .1 Construction Schedule highlighting milestone events. .2 A Breakdown of the Tender Price as follows: .1 Installation of Control Building Foundation $ .2 Installation of Concrete Foundations and Pads $ .3 Installation of Control Building Electrical/Mechanical $ Services, Cable Tray Systems, Conduit Systems .4 Substation Fence, Embedded Ground Grid, Drainage $ System, Substation Cable Trench, Substation Lighting .5 Erection of Structural Steel $ .6 Installation of Substation Power Distribution Equipment, 13.8kVSwitchgear, Station Battery, Padmount Transformers, Protection/Control/SCADA Panels $ .7 Installation and Termination of Power, Protection, Control, SCADA and Communication Cables $ .8 Other $ PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 00101 PAGE 2 2011-06-03 SUPPLEMENTARY INFORMATION IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 1./ .3 A List of Proposed Sub-Contractors: SUB-CONTRACTOR TRADE & TASKS 1 2 3 4 5 6 7 8 9 10 .4 A Letter of Good Standing from the Workers’ Compensation Board of Nova Scotia. .5 A Letter of Good Standing from the Nova Scotia Construction Safety Association. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE I 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT TABLE OF CONTENTS SECTION 1 2 3 DESCRIPTION PAGE GENERAL 1 1.1 1.2 1.3 1.4 1.5 1 2 2 3 4 OVERVIEW PREPARATORY WORK CARRIED OUT BY OTHERS MATERIALS TO BE SUPPLIED BY THE OWNER PROJECT SCHEDULE PROJECT DRAWINGS/REFERENCES INSTALLATION OF CONTROL BUILDING FOUNDATION 6 2.1 2.2 2.3 2.4 2.5 6 6 7 8 9 GENERAL INSTALLATION OF BASE AND FOUNDATION DRAINAGE SYSTEM INSTALLATION OF FOOTINGS, WALLS AND FLOOR SLABS CABLE TRAY VAULT (BASEMENT) ACCESS STAIRS BACKFILLING AND FINAL GRADING INSTALLATION OF EQUIPMENT FOUNDATIONS/PADS 10 3.1 3.2 3.3 10 10 3.4 3.5 3.6 3.7 3.8 3.9 3.10 3.11 3.12 GENERAL INSTALLATION OF A-FRAME DEADEND STRUCTURE PADS INSTALLATION OF LIGHTNING (SURGE) ARRESTERS AND VOLTAGE TRANSFORMERS SUPPORT STRUCTURE PAD INSTALLATION OF 138kV GROUP-OPERATED ISOLATING SWITCH PADS INSTALLATION OF 138kV CIRCUIT BREAKER PAD INSTALLATION OF LIGHTNING (SURGE) ARRESTERS (TRANSFORMER) SUPPORT STRUCTURE PAD INSTALLATION OF TRANSFORMER PAD WITH OIL CONTAINMENT SLAB INSTALLATION OF OIL/WATER SEPARATOR AND OIL CONTAINMENT DRAIN VALVE CHAMBER INSTALLATION OF VOLTAGE MATCHING TRANSFORMERS PADS INSTALLATION OF GROUNDING TRANSFORMERS PADS INSTALLATION OF STATION SERVICE TRANSFORMER PAD INSTALLATION OF STANDBY STATION SERVICE TRANSFORMER PAD PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 11 12 12 13 14 16 17 18 19 19 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE II 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT TABLE OF CONTENTS SECTION 4 5 DESCRIPTION INSTALLATION OF UNDERGROUND DRAINAGE SYSTEMS 20 4.1 4.2 4.3 4.4 20 20 21 22 7 23 5.1 5.2 23 23 25 26 27 6.1 6.2 6.3 27 27 28 GENERAL INSTALLATION OF CABLE TRENCH WALLS AND BASE SLAB INSTALLATION OF CABLE TRENCH COVER INSTALLATION OF SUBSTATION EMBEDDED GROUND GRID 29 29 GENERAL INSTALLATION OF SUBSTATION EMBEDDED GROUND GRID SYSTEM 29 INSTALLATION OF SUBSTATION PERIMETER FENCE SYSTEM 30 8.1 8.2 8.3 9 GENERAL INSTALLATION OF CONDUITS TO/FROM SUBSTATION CONTROL BUILDING INSTALLATION OF CONDUITS TO/FROM CABLE TRENCH INSTALLATION OF SUBSTATION YARD LIGHTING CONDUITS INSTALLATION OF CABLE TRENCH SYSTEM 7.1 7.2 8 GENERAL INSTALLATION OF CONTROL BUILDING DRAINAGE INSTALLATION OF CABLE TRENCH DRAINAGE INSTALLATION OF OIL/WATER SEPARATOR DRAINAGE INSTALLATION OF UNDERGROUND CONDUITS 5.3 5.4 6 PAGE GENERAL INSTALLATION OF SUBSTATION PERIMETER FENCE SYSTEMS INSTALLATION OF SUBSTATION INTERIOR FENCE SYSTEMS 30 30 31 FINAL SUBSTATION GRADING 32 9.1 9.2 32 32 GENERAL FINAL SUBSTATION GRADING PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE III 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT TABLE OF CONTENTS SECTION 10 11 12 13 14 DESCRIPTION PAGE INSTALLATION OF SUBSTATION CONTROL BUILDING SERVICES 10.1 GENERAL 10.2 PREPARATORY WORK CARRIED OUT BY OTHERS 10.3 INSTALLATION OF CONTROL BUILDING GROUNDING SYSTEMS 10.4 INSTALLATION OF CONDUIT AND CABLE TRAY SYSTEMS 10.5 INSTALLATION OF CONTROL BUILDING ELECTRICAL SYSTEMS 10.6 INSTALLATION OF CONTROL BUILDING MECHANICAL SYSTEMS 10.7 INSTALLATION OF 125VDC STATION BATTERY SYSTEM 10.8 INSTALLATION OF SUBSTATION YARD LIGHTING SYSTEM 33 33 34 34 35 36 38 39 40 ERECTION OF SUBSTATION STRUCTURAL STEEL 41 11.1 11.2 11.3 41 41 41 GENERAL MATERIAL SUPPLIED BY THE OWNER INSTALLATION OF SUBSTATION STRUCTURAL STEEL INSTALLATION OF SUBSTATION EQUIPMENT 42 12.1 12.2 12.3 42 42 42 GENERAL MATERIAL SUPPLIED BY THE OWNER INSTALLATION OF SUBSTATION EQUIPMENT INTERCONNECTION OF SUBSTATION EQUIPMENT 44 13.1 13.2 13.3 44 45 45 GENERAL FABRICATION OF ALUMINUM TUBULAR BUS ASSEMBLIES INTERCONNECTION OF SUBSTATION EQUIPMENT INSTALLATION OF 13.8kV SWITCHGEAR ASSEMBLY 47 14.1 14.2 47 47 GENERAL INSTALLATION OF 13.8kV SWITCHGEAR ASSEMBLY PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE IV 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT TABLE OF CONTENTS SECTION DESCRIPTION 15 INSTALLATION OF 13.8kV COLLECTOR CIRCUIT GROUNDING TRANSFORMERS 15.1 GENERAL 15.2 INSTALLATION OF 13.8kV COLLECTOR CIRCUIT GROUNDING TRANSFORMERS 16 17 18 48 48 48 SUPPLY AND INSTALLATION OF STATION SERVICE TRANSFORMER 16.1 GENERAL 16.2 STATION SERVICE TRANSFORMER SPECIFICATION 16.3 INSTALLATION OF STATION SERVICE TRANSFORMER 48 48 49 50 PROVSION OF UTILTIY SERVICES 50 17.1 17.2 17.3 17.4 50 51 51 52 GENERAL PROVISION OF NSPI 240/120V STANDBY STATION SERVICE PROVISION OF BELL-ALIANT TELEPHONE SERVICE PROVISION OF HIGH-SPEED INTERNET SERVICE INSTALLATION OF PROTECTION, CONTROL AND SCADA/ COMMUNICATION SYSTEM PANELS 18.1 18.2 19 PAGE GENERAL INSTALLATION OF PROTECTION, CONTROL AND SCADA/ COMMUNICATION SYSTEM PANELS INSTALLATION AND TERMINATION OF ELECTRICAL AND SCADA/COMMUNICATION SYSTEM CABLES 19.1 19.2 19.3 19.4 19.5 19.6 GENERAL INSTALLATION AND TERMINATION OF 13.8kV POWER CABLES INSTALLATION AND TERMINATION OF 240/120V POWER CABLES INSTALLATION AND TERMINATION OF 125VDC CABLES INSTALLATION AND TERMINATION OF PROTECTION AND CONTROL CABLES INSTALLATION AND TERMINATION OF SCADA/COMMUNICATION CABLES PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 52 52 53 53 53 54 55 56 56 58 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE V 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT TABLE OF CONTENTS SECTION DESCRIPTION PAGE 20 TESTING AND COMMISSIONING 60 21 CABLE TAGS AND EQUIPMENT NAMEPLATES 60 22 AS-BUILT DRAWINGS 60 APPENDIX A PERTINENT INFORMATION FROM THE GEOTECHNICAL INVESTIGATION FINAL REPORT APPENDIX B CCDC 2 – STIPULATED PRICE CONTRACT DOCUMENT PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 1 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 1. GENERAL .2 OVERVIEW The general purpose of this project is to provide civil and electrical contractor services, including supply of certain materials as specified, to develop a 138kV34.5kV intertie substation, designated 429N, for the Fundy Ocean Research Center for Energy (FORCE). In the near term, the substation will be operated at a primary voltage of 24.94/14.4kV and a secondary voltage of 13.8/7.967kV. Substation 429N will provide the tie between four (4) underground collector circuits and the Nova Scotia Power Inc. (NSPI) 138kV transmission (or 24.94kV distribution) system. Substation 429N will be located approximately 12km east of Parrsboro, Nova Scotia, on the Old Black Rock Road in Black Rock, Nova Scotia. The work will generally include, but is not necessarily limited to: .1 .2 .3 .4 .5 .6 .7 .8 .9 .10 .11 .12 .13 Installation of concrete foundations and pads for the support of electrical equipment. Installation of an oil containment system around the transformer pad. Installation of the control building foundation, basement and floor slabs. Supply and installation of oil containment, cable trench and control building drainage systems. Supply and installation of underground concrete encased and direct buried ducts and conduits. Supply and installation of a concrete cable trench system. Supply and installation of an embedded ground grid and the bonding of all electrical equipment and substation fence to the ground grid. Supply and installation of a chain-link fence complete with vehicular gates and man gates. Supply and installation of a Substation Yard lighting system. Supply and installation of gravel materials and substation surface grading. Supply and installation of the control building electrical services, including grounding systems, cable tray systems, 240/120V electrical services, 125Vdc station battery systems. Installation of structural steel assemblies, members and components. Supply and installation of 138kV insulators and aluminum tubular bus and associated mounting hardware and fittings. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 2 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 1.1/ .14 Installation of Owner supplied power distribution equipment, including 138kV and 13.8kV power distribution equipment, 125Vdc station battery and protection, control and communication panels. .15 Supply and installation of power, control, instrumentation and communication cables and bare conductors as required to supply, control and monitor the power distribution equipment. .16 Supply and installation of high speed wireless internet service. The internet service provider (ISP) shall be Seaside High-Speed Inc. .17 Provision of NSPI and Bell-Aliant utility services from West Bay Road through existing underground cable vaults and concrete encased duct banks. All work will be carried out on properties owned by or leased to the Fundy Ocean Research Center for Energy. Lengths, quantities, areas and volumes indicated on the drawings June not be exact and should not be used for assessing quantities in connection with the procurement of materials or the cutting of cables, conduit, steel or cable tray. The Contractor shall confirm all dimensions on site and shall be responsible for the lengths and quantities of materials specified herein. 1.2 PREPARATORY WORK CARRIED OUT BY OTHERS The following preparatory work has been carried out by Others: .1 Clearing, grubbing, grading and compaction of the substation site to an elevation of approximately 62.5m above mean sea level .2 Installation of underground concrete encased duct banks from the utility riser pole on the West Bay Road to the substation control building. 1.3 MATERIALS TO BE SUPPLIED BY THE OWNER Fundy Ocean Research Center for Energy (FORCE) has pre-purchased the following materials for installation by the Contractor: .1 Structural Steel Assemblies, Members and Components for the support of the 138kV Power Distribution Equipment. .2 Six (6), 21kV (17kV MCOV) Station Class Surge Arresters PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 3 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 1.3/ .3 .4 .5 .6 Two (2), 138kV Group-Operated Isolation Switches complete with support frames. One (1), 138kV SF6 Circuit Breaker complete with support frame. One (1), 5000/6667kVA, 24.94/14.4kV-13.8/7.967kV Power Transformer. One (1), 13.8kV, 2000A Switchgear Assembly complete with Circuit Breakers. .7 Four (4), 225kVA, 13.8/7.967kV Grounding Transformers. .8 One (1), 125Vdc Station Battery and Battery Charger .9 One (1), Pre-Engineered, Site-Erected Steel Control Building (to be installed by Others following the installation of the control building foundation, basement and floor slabs per this Contract). .10 Three (3), Protection, Control and Communication Panels. .11 Underground Cable Vaults and Concrete Encased Duct Banks from a Utility Riser Pole on the West Bay Road to the Substation Control Building. .12 One (1), 240V, 400A Revenue Meter Socket/Base mounted on the exterior of the Control Building (to be supplied and installed by Others following installation of the control building foundation, basement and floor slabs per this Contract). .13 Four (4), 350kcmil, 35kV Collector Circuits terminated on 35kV Deadend Separable Junctions on the east wall of the control building basement foundation (to be supplied and installed by Others following installation of the control building foundation, basement and floor slabs per this Contract) 1.4 PROJECT SCHEDULE .1 The purchase of all Contractor supplied equipment associated with the Substation Development can proceed immediately following award of the Contract. The Contractor shall submit shop drawings and/or product data sheets for review by the Owner’s Engineer for all Contractor supplied materials. .2 The preparation of the control building foundation, basement and floor slabs should proceed immediately following award of the Contract so as not to impede the schedule of other Contractors. .3 The preparation of the equipment foundations and pads, the oil containment system, the drainage system, the cable trench system, the embedded ground grid, the chain-link fence and the underground ducts and conduits can proceed immediately following award of the Contract. .4 All other work shall proceed on a timely schedule to achieve substantial completion by 30 September 2011. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 4 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 1./ 1.5 PROJECT DRAWINGS / REFERENCES The following electrical drawings have been prepared by Strum Engineering Associates Ltd. for this project: .1 Drawing No. 023-478-D-1100, Rev. A01 .2 Drawing No. 023-478-D-1101, Rev. A01 .3 Drawing No. 023-478-D-1102, Rev. A01 .4 Drawing No. 023-478-D-1103, Rev. A01 .5 Drawing No. 023-478-D-1104, Rev. A01 .6 Drawing No. 023-478-D-1105, Rev. A01 .7 Drawing No. 023-478-D-1106, Rev. A01 .8 Drawing No. 023-478-D-1107, Rev. A01 .9 Drawing No. 023-478-D-1108, Rev. A01 .10 Drawing No. 023-478-D-1109, Rev. A01 .11 Drawing No. 023-478-D-1110, Rev. A01 .12 Drawing No. 023-478-D-1111, Rev. A01 .13 Drawing No. 023-478-D-1112, Rev. A01 .14 Drawing No. 023-478-D-1113, Rev. A01 .15 Drawing No. 023-478-D-1114, Rev. A01 .16 Drawing No. 023-478-D-1115, Rev. A01 .17 Drawing No. 023-478-D-1116, Rev. A01 .18 Drawing No. 023-478-D-1117, Rev. A01 .19 Drawing No. 023-478-E-1131, Rev. A01 .20 Drawing No. 023-478-E-1132, Rev. A01 .21 Drawing No. 023-478-E-1133, Rev. A01 .22 Drawing No. 023-478-E-3002, Rev. A05 .23 Drawing No. 023-478-D-3021, Rev. A01 .24 Drawing No. 023-478-D-3022, Rev. A01 .25 Drawing No. 023-478-D-3023, Rev. A01 .26 Drawing No. 023-478-D-3024, Rev. A01 .27 Drawing No. 023-478-D-3025, Rev. A01 .28 Drawing No. 023-478-D-3031, Rev. A03 .29 Drawing No. 023-478-D-3032, Rev. A01 .30 Drawing No. 023-478-D-3033, Rev. A01 PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 5 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 1.5/ .31 Drawing No. 023-478-D-3034, Rev. A01 .32 Drawing No. 023-478-D-3035, Rev. A01 .33 Drawing No. 023-478-D-3036, Rev. A01 .34 Drawing No. 023-478-D-3037, Rev. A01 .35 Drawing No. 023-478-D-3038, Rev. A01 .36 Drawing No. 023-478-D-3039, Rev. A01 .37 Drawing No. 023-478-D-3040, Rev. A01 .38 Drawing No. 023-478-D-3201, Rev. A01 .39 Drawing No. 023-478-D-3901, Rev. A01 .40 Drawing No. 023-478-D-3902, Rev. A01 .41 Drawing No. 023-478-D-3903, Rev. A01 .42 Drawing No. 023-478-D-3904, Rev. A01 .43 Drawing No. 023-478-D-3905, Rev. A01 .44 Drawing No. 023-478-D-3906, Rev. A01 .45 Drawing No. 023-478-D-3907, Rev. A01 .46 Drawing No. 023-478-D-3908, Rev. A01 .47 Drawing No. 023-478-D-3909, Rev. A01 .48 Drawing No. 023-478-D-3910, Rev. A01 .49 Drawing No. 023-478-D-5000, Rev. A02 .50 Drawing No. 023-478-D-5001, Rev. A02 .51 Drawing No. 023-478-D-5002, Rev. A02 .52 Drawing No. 023-478-D-5003, Rev. A02 .53 Drawing No. 023-478-D-5004, Rev. A02 .54 Drawing No. 023-478-D-5005, Rev. A02 .55 Drawing No. 023-478-D-5006, Rev. A02 .56 Drawing No. 023-478-D-5007, Rev. A02 .57 Drawing No. 023-478-D-5008, Rev. A02 .58 Drawing No. 023-478-D-5009, Rev. A02 .59 Drawing No. 023-478-D-5010, Rev. A02 .60 Drawing No. 023-478-D-5011, Rev. A01 PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 6 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 2. INSTALLATION OF CONTROL BUILDING FOUNDATION 2.1 GENERAL .1 Drawing Nos. 023-478-D-1104, Rev. A01, 023-478-E-1131, Rev. A01, 023478-E-1132, Rev. A01 an d023-478-E-1133, Rev. A01 show in plan and elevation views, the dimensions, layout and details for the construction of the reinforced concrete footings, foundation walls, basement and floor slabs and exterior stairs, the supply and installation of a steel man-door complete with steel frame and hardware and the supply and installation of steel railings on the exterior of the stairs. .2 The concrete mix data shall be submitted for review by the Engineer prior to preparation of the first concrete batch. The minimum compressive strength of the concrete shall be 45MPa (6500psi) after 28 days. Test cylinders shall be obtained, and stored, at site during the pour for each batch of concrete supplied. 2.2 INSTALLATION OF BASE AND FOUNDATION DRAINAGE SYSTEM .1 The substation control building site shall be excavated to a depth not less than 600mm below the elevation of the finished floor of the basement level. This June require breaking of bedrock in some locations. Refer to the Geotechnical Investigation Report Data Sheet provided in Appendix A. .2 A 300mm layer of Nova Scotia Department of Transportation and Infrastructure Renewal (NSDOTIR) Class B gravel shall be supplied and compacted to form the base for the control building footings/foundation. .3 The control building footings shall be formed, complete with reinforcing steel, as indicated on the drawings. .4 150mm diameter PVC perforated pipe shall be installed around the perimeter of the footing/foundation and sloped to the north side of the substation, as indicated on the drawings. The perforated drain pipe shall be covered with NSDOTIR Class B gravel. .5 The location of the base of the exterior stairway shall be provided with 100mm (4”) diameter PVC drain pipe and fittings to collect water from the base of the stairs and drain it into the overall substation drainage system. A strainer shall be provided flush with the concrete base slab. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 7 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 2./ 2.3 INSTALLATION OF FOOTINGS, WALLS AND FLOOR SLABS .1 Concrete shall be placed for the control building footings and vibrated into all voids. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 75mm (3”), all-around. .2 The concrete footings shall be protected from rain and allowed to cure for at least 24 hours before proceeding with the forming of the control building walls. .3 The control building walls and floor slab support columns shall be formed, complete with reinforcing steel, as indicated on the drawings. .4 PVC conduit sleeves, complete with bell ends on the face of the inside wall, shall be supplied and installed in the locations indicated on the drawings. The inside diameter of each conduit sleeve shall be as indicated on the drawings. .5 An opening shall be provided in the north east corner of the control building for the installation of a man-door. The opening shall be sized to accommodate the steel frame of a standard exterior steel door. .6 Concrete shall be placed for the control building walls and support columns and vibrated into all voids. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 75mm (3”), allaround. The concrete walls and support columns shall be protected from rain and allowed to cure for at least 3 days. .7 Reinforcing steel shall be placed for the control building basement floor slab as indicated on the drawings. A sump pit shall be formed on the north side of the Control Building, as indicated on the drawings. .8 Concrete shall be placed for the control building basement floor and vibrated into all void areas. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 75mm (3”), allaround. The basement floor slab shall be smoothed using a power trowel. The floor slab shall be protected from rain and allowed to cure for at least 3 days. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 8 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 2.3/ .9 Reinforcing steel shall be placed for the control building main level floor slab as indicated on the drawings. Several areas on the main floor slab have been designated as “rebar-free”. The “rebar-free” areas will allow for the future core drilling of the main floor slab to access the basement area. .10 Anchor bolts, required for the installation of the steel control building by Others, shall be supplied and installed at the direction of the Engineer. The size and location of the anchor bolts will be determined following final review of the steel control building shop drawings. .11 Concrete shall be placed for the control building main level floor slab and vibrated into all void areas. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 75mm (3”), allaround. The main level floor slab shall be smoothed using a power trowel. The floor slab shall be protected from rain and allowed to cure for at least 14 days before removal of the formwork and supports. 2.4 CABLE TRAY VAULT (BASEMENT) ACCESS STAIRS .1 An exterior stairway consisting of a concrete base slab, retaining walls and stairs shall be formed, complete with reinforcing steel, to provide exterior access to the basement area, as indicated on the drawings. .2 Concrete shall be placed for the exterior stairway and vibrated into all void areas. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 75mm (3”), all-around. .3 A single man entry door, complete with steel frame and hardware shall be installed in the opening at the base of the stairway. The door shall open outward. The door shall have a 1-hour, fire-rating per the NFPA Standards. .4 The door lock shall be a Best Type 77K heavy duty cylinder lock set, for exterior use, with Best "B" cylinder. The operation of the door will be latch bolt by panic hardware from the inside and fixed handle and key from the outside. This selection of the lock set shall be coordinated with the Owner to match the control building door locks being provided by Others. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 9 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 2.4/ .5 The man-door shall be 915 mm wide by 2134 mm high by 45 mm thick, 16 gauge (ASTM A924) hot dipped zinc coated steel with continuously welded seams. It shall be an out-swinging, flush design with polyurethane insulated core chemically bonded to all interior surfaces, with a minimum insulating value of R-10. Reinforcement for locks, latches, hinges, closers and other hardware shall be in accordance with ANSI A115 unless otherwise specified. Finish shall be factory primed and finish coated (both sides of door). .6 The door frame shall be 2” mitered, factory welded cold rolled steel, 16 gauge minimum, reinforcing shall be 8 gauge steel for hinges, 12 gauge for closers and 14 gauge minimum for other hardware. Finish shall be factory primed and finish coated. Hinges shall be 1½ pair of 114 mm by 114 mm ball bearing type stainless steel, butt hinges with dull chrome finish. Hinge pins shall be non-removable type. .7 Weather stripping and thresholds shall be provided to give a positive weather seal around the door. An aluminum exterior threshold shall be installed to provide a complete weather seal. .8 The door and door frame shall be mortised, reinforced, drilled and tapped for hardware including surface mounted closers and panic exit devices, and shall be provided with all necessary anchors and rubber silencers. .9 A heavy-duty, automatic door closer shall be provided. 2.5 BACKFILLING AND FINAL GRADING .1 The exterior surface of the control building foundation walls shall be coated with a waterproofing sealer product to prevent water/moisture ingress to the basement area, such as Black Knight Foundation Coating. .2 When the concrete waterproofing sealant is sufficiently dry, the excavated space shall be backfilled and compacted using the native material. The backfilled material shall be compacted, to 95% Proctor Density, in 150mm (6”) layers. .3 The top 450mm should remain excavated until the embedded ground grid and other electrical and mechanical services are installed. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 10 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 3. INSTALLATION OF EQUIPMENT FOUNDATIONS/PADS 3.1 GENERAL .1 Drawing Nos. 023-478-D-1104, Rev. A01, 023-478-D-1107, Rev. A01 to 023-478-D-1116, Rev. A01, inclusive, show in plan and elevation views, the dimensions, layout and details for the construction of the reinforced concrete foundations/pads which will support the power distribution equipment located in the substation yard. .2 The concrete mix data for the equipment foundations/pads shall be submitted for review by the Engineer prior to preparation of the first concrete batch. The minimum compressive strength of the concrete shall be 30MPa (4350psi) after 28 days. Test cylinders shall be obtained, and stored, at site during the pour for each batch of concrete supplied. 3.2 INSTALLATION OF A-FRAME DEADEND STRUCTURE PADS .1 Drawing No. 023-478-D-1107, Rev. A01 shows in plan and elevation views, the dimensions, reinforcing steel layout, galvanized anchor bolt arrangement and details for the construction of the two (2) A-Frame Deadend Structure pads. .2 The A-Frame Deadend Structure foundation pad sites shall be excavated to the specified elevation for the base of the concrete pad. This June require breaking of bedrock. Refer to the Geotechnical Investigation Report Data Sheet provided in Appendix A. .3 The native soil shall be compacted to form the base for the A-Frame Deadend Structure pads. .4 The A-Frame Deadend Structure pads shall be formed, complete with reinforcing steel and anchor bolts, as indicated on the drawings. .5 Concrete shall be placed for the A-Frame Deadend Structure pads and vibrated into all void areas. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 100mm (4”), allaround. The surface of each A-Frame Deadend Structure pad shall be smoothed. The concrete shall be protected from rain and allowed to cure for at least 48 hours before removing the forms. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 11 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 3.2/ .6 The excavated space shall be backfilled and compacted using the native material. The backfilled material shall be compacted, to 95% Proctor Density, in 150mm (6”) layers. The top 450mm should remain excavated until the embedded ground grid and other electrical and mechanical services are installed. 3.3 INSTALLATION OF LIGHTNING ARRESTERS AND VOLTAGE TRANSFORMERS SUPPORT STRUCTURE PAD .1 Drawing No. 023-478-D-1108, Rev. A01 shows in plan and elevation views, the dimensions, reinforcing steel layout, galvanized anchor bolt arrangement and details for the construction of the Lightning Arresters and Voltage Transformers Support Structure pad. .2 The Lightning Arresters and Voltage Transformers Support Structure pad site shall be excavated to the specified elevation for the base of the concrete pad. This June require breaking of bedrock. Refer to the Geotechnical Investigation Report Data Sheet provided in Appendix A. .3 The native soil shall be compacted to form the base for the Lightning Arresters and Voltage Transformers Support Structure pad. .4 The Lightning Arresters and Voltage Transformers Support Structure pad shall be formed, complete with reinforcing steel and anchor bolts, as indicated on the drawings. .5 Concrete shall be placed for the Lightning Arresters and Voltage Transformers Support Structure pad and vibrated into all void areas. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 75mm (3”), all-around. The surface of the Lightning Arresters and Voltage Transformers Support Structure pad shall be smoothed. The concrete shall be protected from rain and allowed to cure for at least 48 hours before removing the forms. .6 The excavated space shall be backfilled and compacted using the native material. The backfilled material shall be compacted, to 95% Proctor Density, in 150mm (6”) layers. The top 450mm should remain excavated until the embedded ground grid and other electrical and mechanical services are installed. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 12 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 3./ 3.4 INSTALLATION OF 138kV GROUP-OPERATED ISOLATING SWITCH PADS .1 Drawing No. 023-478-D-1109, Rev. A01 shows in plan and elevation views, the dimensions, reinforcing steel layout, galvanized anchor bolt arrangement and details for the construction of the two (2) 138kV Group-Operated Isolating Switch pads. .2 The 138kV Group-Operated Isolating Switch pad sites shall be excavated to the specified elevation for the base of the concrete pad. This June require breaking of bedrock. Refer to the Geotechnical Investigation Report Data Sheet provided in Appendix A. .3 The native soil shall be compacted to form the base for the 138kV GroupOperated Isolating Switch pads. .4 The 138kV Group-Operated Isolating Switch pads shall be formed, complete with reinforcing steel and anchor bolts, as indicated on the drawings. .5 Concrete shall be placed for the 138kV Group-Operated Isolating Switch pads and vibrated into all void areas. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 75mm (3”), all-around. The surface of each 138kV Group-Operated Isolating Switch pad shall be smoothed. The concrete shall be protected from rain and allowed to cure for at least 48 hours before removing the forms. .6 The excavated space shall be backfilled and compacted using the native material. The backfilled material shall be compacted, to 95% Proctor Density, in 150mm (6”) layers. The top 450mm should remain excavated until the embedded ground grid and other electrical and mechanical services are installed. 3.5 INSTALLATION OF 138kV CIRCUIT BREAKER PAD .1 Drawing No. 023-478-D-1110, Rev. A01 shows in plan and elevation views, the dimensions, reinforcing steel layout, galvanized anchor bolt arrangement and details for the construction of the one (1) 138kV Circuit Breaker pad. .2 The 138kV Circuit Breaker pad site shall be excavated to the specified elevation for the base of the concrete pad. This June require breaking of bedrock. Refer to the Geotechnical Investigation Report Data Sheet provided in Appendix A. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 13 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 3.5/ .3 The native soil shall be compacted to form the base for the 138kV Circuit Breaker pad. .4 The 138kV Circuit Breaker pad shall be formed, complete with reinforcing steel, anchor bolts and PVC conduits, as indicated on the drawings. .5 Concrete shall be placed for the 138kV Circuit Breaker pad and vibrated into all void areas. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 100mm (4”), all-around. The surface of the 138kV Circuit Breaker pad shall be smoothed. The concrete shall be protected from rain and allowed to cure for at least 48 hours before removing the forms. .6 The excavated space shall be backfilled and compacted using the native material. The backfilled material shall be compacted, to 95% Proctor Density, in 150mm (6”) layers. The top 450mm should remain excavated until the embedded ground grid and other electrical and mechanical services are installed. 3.6 INSTALLATION OF LIGHTNING (SURGE) ARRESTERS (TRANSFORMER) SUPPORT STRUCTURE PAD .1 Drawing No. 023-478-D-1111, Rev. A01 shows in plan and elevation views, the dimensions, reinforcing steel layout, galvanized anchor bolt arrangement and details for the construction of the Lightning (Surge) Arresters Support Structure pad located on the primary side of the power transformer. .2 The Lightning (Surge) Arresters Support Structure pad site shall be excavated to the specified elevation for the base of the concrete pad. This June require breaking of bedrock. Refer to the Geotechnical Investigation Report Data Sheet provided in Appendix A. .3 The native soil shall be compacted to form the base for the Lightning (Surge) Arresters Support Structure pad. .4 The Lightning (Surge) Arresters Support Structure pad shall be formed, complete with reinforcing steel and anchor bolts, as indicated on the drawings. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 14 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 3.6/ .5 Concrete shall be placed for the Lightning (Surge) Arresters Support Structure pad and vibrated into all void areas. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 75mm (3”), all-around. The surface of the Lightning (Surge) Arresters Support Structure pad shall be smoothed. The concrete shall be protected from rain and allowed to cure for at least 48 hours before removing the forms. .6 The excavated space shall be backfilled and compacted using the native material. The backfilled material shall be compacted, to 95% Proctor Density, in 150mm (6”) layers. The top 450mm should remain excavated until the embedded ground grid and other electrical and mechanical services are installed. 3.7 INSTALLATION OF TRANSFORMER PAD WITH OIL CONTAINMENT SLAB .1 Drawing Nos. 023-478-D-1112, Rev. A01 and 023-478-D-1113, Rev. A01 show in plan and elevation views, the dimensions, reinforcing steel layout and details for the construction of the Transformer pad and associated Oil Containment slab. .2 The Transformer pad site shall be excavated to the specified elevation for the base of the concrete pad. This June require breaking of bedrock. Refer to the Geotechnical Investigation Report Data Sheet provided in Appendix A. .3 The native soil shall be compacted to form the base for the Transformer pad. .4 The Transformer pad shall be formed, complete with reinforcing steel and PVC conduits, as indicated on the drawings. Ensure that the top of each PVC conduit is above the top of the Oil Containment slab retaining walls to prevent water ingress into the conduit. .5 Concrete shall be placed for the Transformer pad and vibrated into all void areas. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 75mm (3”), all-around. The surface of the Transformer pad shall be smoothed. The concrete shall be protected from rain and allowed to cure for at least 48 hours before removing the forms. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 15 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 3.7/ .6 The excavated space shall be backfilled and compacted using the native material. The backfilled material shall be compacted, to 95% Proctor Density, in 150mm (6”) layers. .7 The Oil Containment slab site shall be excavated to the specified elevation for the base of the concrete slab. .8 The native soil shall be site shall be excavated to a depth not less than 300mm below the elevation of the base of the slab. .9 Asphalt impregnated fiberboard joint filler shall be installed on the outer vertical walls of the Transformer pad where the Oil Containment slab and Transformer pad meet. .10 The Oil Containment slab shall be formed to provide the shape and dimensions indicated on the drawing. The top of the curb shall be at the height specified above the finished grade of the concrete slab. .11 Reinforcing bars shall be installed and supported above the base materials. .12 A water drain system, consisting of a floor drain with cast iron grate and strainer, 4” PVC couplings, 4” PVC 90° elbow (16” radius) and Schedule 40 PVC pipe shall be supplied and installed on the west side of the Oil Containment slab. .13 Self-regulating trace heating cable (Raychem type 15QTVR-CT system or approved equal) shall be installed above the reinforcing steel, in the area around the Oil Containment slab water drain, as indicated on the drawings. As described in Section 4.4.10, the trace heating cable shall be extended to include the water drain pipe running between the Oil Containment slab, the Oil/Water Separator and the Oil Containment Drain Valve Chamber and drain control valve located in the Oil Containment Drain Valve Chamber. All necessary trace heating components, including power connectors, splice/junction boxes, straps/tapes, end seals, etc., shall be supplied and installed to form a complete system. .14 Concrete shall be poured in the formwork and vibrated into all void areas. A 1% slope, from east to west, shall be maintained over the entire length of the Oil Containment slab to provide natural drainage toward the sump pit. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 75mm (3”), all-around. .15 The Oil Containment slab shall be smoothed using a power trowel. The slab shall be protected from rain and allowed to cure for at least 48 hours. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 16 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 3.7/ .16 During the site inspection of the Oil Containment slab by the Engineer, the exact number and location of the control joints (saw cuts) shall be determined. Control joints shall be cut to a depth of 50mm (2”). The control joints shall be filled with an oil resistant, water-proof horizontal joint sealant, W.R. Meadows Type Gardox Horizontal Joint Sealant, or approved equal. .17 The entire surface of the Oil Containment slab and the surface and sides of the Transformer pad shall be primed using a surface primer such as Concrete Sealants Inc. ConSeal CS-300, or approved equal, and sealed with an oil resistant, water-proof sealer such as Concrete Sealants Inc. Type ConSeal CS440, or approved equal. .18 The excavated space shall be backfilled and compacted using the native material. The backfilled material shall be compacted, to 95% Proctor Density, in 150mm (6”) layers. The top 450mm should remain excavated until the embedded ground grid and other electrical and mechanical services are installed. 3.8 INSTALLATION OF OIL/WATER SEPARATOR AND OIL CONTAINMENT DRAIN VALVE CHAMBER .1 Drawing No. 023-478-D-1113, Rev. A01 shows in plan and elevation views, the dimensions and details for the installation of the Oil/Water Separator and Oil/Containment Drain Valve Chamber. .2 The Oil/Water Separator shall be assembled from 1800mm diameter precast concrete manhole sections comprising a mono base section, two intermediate shaft sections and a top concrete cover complete with cast iron frame and manhole cover, as supplied by Shaw Pipe or equal. .3 The Oil Containment Drain Valve Chamber shall be assembled as one (1) 1800mm diameter precast concrete manhole section with an open base and a top concrete cover complete with cast iron frame and manhole cover, as supplied by Shaw Pipe or equal. .4 The Oil/Water Separator and Oil Containment Drain Valve Chamber sites shall be excavated to a depth not less than 150mm below the bottom elevation of the mono base section. This June require breaking of bedrock. Refer to the Geotechnical Investigation Report Data Sheet provided in Appendix A. .5 A 150mm layer of NSDOTIR Class B gravel shall be supplied and compacted to form the base for both the Oil/Water Separator and Oil/Containment Drain Valve Chamber. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 17 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 3.8/ .6 The water drain piping shall be installed as described in Section 4.4. .7 The location of the inlet and outlet piping shall be determined by the drainage slopes required by the substation topography. .8 The inlet and outlet piping shall be grouted into place using waterproof / oil resistant, non-shrink grout material. .9 A 100mm diameter electrically operated butterfly ball valve assembly shall be supplied and installed in the Oil Containment Drain Valve Chamber, as indicated on the drawings and as fully described in Section 4.4. The electric actuator shall be rated 120Vac, 1Ø, 60Hz. .10 A 53mm diameter PVC rigid electrical conduit shall be installed between the cable trench and the Oil Containment Drain Valve Chamber, as described in Section 5.3. .11 The excavated space shall be backfilled and compacted using the native material. The backfilled material shall be compacted, to 95% Proctor Density, in 150mm (6”) layers. The top 450mm should remain excavated until the embedded ground grid and other electrical and mechanical services are installed. 3.9 INSTALLATION OF VOLTAGE MATCHING TRANSFORMERS PADS .1 Drawing No. 023-478-D-1114, Rev. A01 shows in plan and elevation views, the dimensions, reinforcing steel layout and details for the construction of the Voltage Matching Transformers pads. .2 The Voltage Matching Transformers pad sites shall be excavated to the specified elevation for the base of the concrete pad. This June require breaking of bedrock. Refer to the Geotechnical Investigation Report Data Sheet provided in Appendix A. .3 The native soil shall be compacted to form the base for the Voltage Matching Transformers pads. .4 The Voltage Matching Transformers pads shall be formed, complete with reinforcing steel and PVC conduits, as indicated on the drawings. Refer to Section 5.2 for a detailed description of the underground conduit system. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 18 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 3.9/ .5 Concrete shall be placed for the Voltage Matching Transformers pads and vibrated into all void areas. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 75mm (3”), allaround. The surface of the transformer pad shall be smoothed. The concrete shall be protected from rain and allowed to cure for at least 48 hours before removing the forms. .6 The excavated space shall be backfilled and compacted using the native material. The backfilled material shall be compacted, to 95% Proctor Density, in 150mm (6”) layers. 3.10 INSTALLATION OF GROUNDING TRANSFORMERS PADS .1 Drawing No. 023-478-D-1115, Rev. A01 shows in plan and elevation views, the dimensions, reinforcing steel layout and details for the construction of the Grounding Transformers pads. .2 The Grounding Transformers pad sites shall be excavated to the specified elevation for the base of the concrete pad. This June require breaking of bedrock. Refer to the Geotechnical Investigation Report Data Sheet provided in Appendix A. .3 The native soil shall be compacted to form the base for the Grounding Transformers pads. .4 The Grounding Transformers pads shall be formed, complete with reinforcing steel and PVC conduits, as indicated on the drawings. Refer to Section 5.2 for a detailed description of the underground conduit system. .5 Concrete shall be placed for the Grounding Transformers pads and vibrated into all void areas. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 75mm (3”), allaround. The surface of the transformer pad shall be smoothed. The concrete shall be protected from rain and allowed to cure for at least 48 hours before removing the forms. .6 The excavated space shall be backfilled and compacted using the native material. The backfilled material shall be compacted, to 95% Proctor Density, in 150mm (6”) layers. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 19 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 3./ 3.11 INSTALLATION OF STATION SERVICE TRANSFORMER PAD .1 Drawing No. 023-478-D-1116, Rev. A01 shows in plan and elevation views, the dimensions, reinforcing steel layout and details for the construction of the Station Service Transformer pad. .2 The Station Service Transformer pad site shall be excavated to the specified elevation for the base of the concrete pad. This June require breaking of bedrock. Refer to the Geotechnical Investigation Report Data Sheet provided in Appendix A. .3 The native soil shall be compacted to form the base for the Station Service Transformer pad. .4 The Station Service Transformer pad shall be formed, complete with reinforcing steel and PVC conduits, as indicated on the drawings. Refer to Section 5.2 for a detailed description of the underground conduit system. .5 Concrete shall be placed for the Station Service Transformer pad and vibrated into all void areas. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 75mm (3”), allaround. The surface of the transformer pad shall be smoothed. The concrete shall be protected from rain and allowed to cure for at least 48 hours before removing the forms. .6 The excavated space shall be backfilled and compacted using the native material. The backfilled material shall be compacted, to 95% Proctor Density, in 150mm (6”) layers. 3.12 INSTALLATION OF STANDBY STATION SERVICE TRANSFORMER PAD .1 Drawing No. 023-478-D-1116, Rev. A01 shows in plan and elevation views, the dimensions, reinforcing steel layout and details for the construction of the NSPI Utility Service Transformer pad. .2 The NSPI Utility Service Transformer pad site shall be excavated to the specified elevation for the base of the concrete pad. This June require breaking of bedrock. Refer to the Geotechnical Investigation Report Data Sheet provided in Appendix A. .3 The native soil shall be compacted to form the base for the NSPI Utility Service Transformer pad. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 20 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 3.12/ .4 The NSPI Utility Service Transformer pad shall be formed, complete with reinforcing steel and PVC conduits, as indicated on the drawings. Refer to Section 5.2 for a detailed description of the underground conduit system. .5 Concrete shall be placed for the NSPI Utility Service Transformer pad and vibrated into all void areas. The concrete shall meet the concrete specification as indicated on the drawings and as reviewed and stamped by the Engineer. The minimum concrete cover over reinforcing steel shall be 75mm (3”), allaround. The surface of the transformer pad shall be smoothed. The concrete shall be protected from rain and allowed to cure for at least 48 hours before removing the forms. .6 The excavated space shall be backfilled and compacted using the native material. The backfilled material shall be compacted, to 95% Proctor Density, in 150mm (6”) layers. 4. INSTALLATION OF UNDERGROUND DRAINAGE SYSTEMS 4.1 GENERAL .1 Drawing Nos. 023-478-D-1105, Rev. A01, 023-478-D-1113, Rev. A01 and 023-478-E-1131, Rev. A01 show in plan and elevation views, the dimensions, layout and details for the construction of the underground drainage systems. .2 All drains shall have a minimum slope of 2%, running from south to north through the substation yard. 4.2 INSTALLATION OF CONTROL BUILDING DRAINAGE .1 Drawing No. 023-478-D-1131, Rev. A01 shows in plan and elevation views, the dimensions and details for the construction of the control building drainage system. .2 A 150mm (6”) diameter main drain pipe shall be run between the north east corner of the control building footing and the north end of the FORCE property, outside the substation fence on the down-slope toward the Old Black Rock Road. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 21 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 4.2/ .3 The burial depth of the 150mm diameter drain pipe shall be as required to provide a minimum slope of 2% over the length of the pipe. The pipe shall be placed on a 75mm bed of compacted sand, then covered with a 75mm compacted sand layer. The native excavated soil shall be used to backfill the remainder of the trench. The backfill shall be compacted in 150mm intervals. Warning tape, indicating “Buried Services” shall be installed above the drain pipe, approximately 300mm below finished grade. .4 Rip-rap shall be placed below the outlet of the drain pipe to prevent erosion of the unprotected slope. .5 As described in Section 2.2, 150mm diameter PVC perforated drain pipe shall be installed around the perimeter of the footing/foundation and sloped to the north side of the substation. The weeping tile shall be connected to the main 150mm diameter drain pipe, as indicated on the drawings. The weeping tile shall be covered with NSDOTIR Class B gravel. The 100mm diameter weeping tile shall be connected to the 150mm drain pipe using a 150mm100mm reducer fitting. .6 Similarly, the 100mm diameter drain pipe serving as the exterior stairway drain shall be connected to the 150mm drain pipe. .7 A submersible sump pump shall be supplied and installed in the control building basement sump pit. The submersible pump shall be float activated and operate from a 120Vac, 15A, 1Ø circuit. 4.3 INSTALLATION OF CABLE TRENCH DRAINAGE .1 Drawing No. 023-478-D-1105, Rev. A01 shows in plan and elevation views, the dimensions and details for the construction of the cable trench drainage system. .2 Section 6.2 describes the construction of the cable trench walls and base slab. .3 At selected locations along the cable trench, 100mm (4”) diameter drain pipes shall be installed prior to the concrete pour for the cable trench base slab. The burial depth of the cable trench drain pipe shall be as required to provide a minimum slope of 2% over the length of each pipe section. The pipe shall be placed on a 75mm bed of compacted sand, and then covered with a 75mm compacted sand layer. The native excavated soil shall be used to backfill the remainder of the trench. The backfill shall be compacted in 150mm intervals. .4 The cable trench drain pipes shall be connected to the main 150mm drain pipe using 150mm-100mm reducer fittings. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 22 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 4./ 4.4 INSTALLATION OF OIL/WATER SEPARATOR DRAINAGE .1 Drawing No. 023-478-D-1113, Rev. A01 shows in plan and elevation views, the dimensions and details for the construction of the oil/water separator drainage system. .2 Section 3.8 describes the installation of the oil/water separator and oil containment drain valve chamber. .3 A 100mm (4”) diameter inlet drain pipe shall be supplied and installed between the oil containment slab and the oil/water separator. The burial depth of the drain pipe shall be as required to provide a minimum slope of 2% over the length of the pipe section. The pipe shall be placed on a 75mm bed of compacted sand, and then covered with a 75mm compacted sand layer. The native excavated soil shall be used to backfill the remainder of the trench. The backfill shall be compacted in 150mm intervals. .4 A 150mm (6”) diameter drain pipe shall be run between the oil/water separator and the oil drain valve located in the oil containment drain valve chamber. .5 The inlet and outlet piping inside the oil/water separator shall be configured to ensure that the inlet pipe is set above the maximum water level height and the outlet pipe draws water from the bottom of the oil/water separator. .6 The inlet and outlet piping shall be grouted into place using waterproof / oil resistant, non-shrink grout material. .7 A 150mm (6”) diameter drain pipe shall be run between the oil drain valve and the north end of the FORCE property, outside the substation fence on the down-slope toward the Old Black Rock Road. The burial depth of the 150mm diameter drain pipe shall be as required to provide a minimum slope of 2% over the length of the pipe. The pipe shall be placed on a 75mm bed of compacted sand, then covered with a 75mm compacted sand layer. The native excavated soil shall be used to backfill the remainder of the trench. The backfill shall be compacted in 150mm intervals. Warning tape, indicating “Buried Services” shall be installed above the drain pipe, approximately 300mm below finished grade. .8 Rip-rap shall be placed below the outlet of the drain pipe to prevent erosion of the unprotected slope. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 23 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 4.4/ .9 A 150mm butterfly valve with flanged cast iron body, EPDM seat and coated ductile iron disc per Bay Valve Series 31 shall be supplied and installed in the oil containment drain valve chamber. The drain valve shall be equipped with an electric actuator rated 120Vac, 60 Hz, 1Ø complete with On/Off control, manual override, valve status display, self-regulating heater and two auxiliary SPDT dry contact switches per Bray Series 70 R4 actuator. .10 Self-regulating trace heating cable (Raychem type 15QTVR-CT system or approved equal) shall be installed around selected sections of the drain pipe system, as indicated on the drawings. The trace heating cable shall be extended to include the water drain pipe running between the Oil Containment slab, the Oil/Water Separator and the Oil Containment Drain Valve Chamber and drain control valve located in the Oil Containment Drain Valve Chamber. All necessary trace heating components, including power connectors, splice/junction boxes, straps/tapes, end seals, etc., shall be supplied and installed to form a complete system. 5. INSTALLATION OF UNDERGROUND CONDUITS 5.1 GENERAL .1 Drawing No. 023-478-D-1106, Rev. A01 shows the location, arrangement and Bill of Material with item numbers for the underground conduits to be located inside the Substation Yard. 5.2 INSTALLATION OF CONDUITS TO/FROM SUBSTATION CONTROL BUILDING .1 As described in Section 2.3.4, conduit sleeves shall be installed in the Substation Control Building walls. Each of the conduit sleeves shall be extended outside the building foundation and connected to PVC conduits/ducts, sized per the conduit schedule. .2 The 129mm and 103mm diameter conduits associated with the TISEC Collector Circuits and the Utility and Telecoms Supply Circuits, located on the south wall of the Control Building, will be supplied and installed by Others and do not form part of this Contract. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 24 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 5.2/ .3 The conduits running between the Control Building and the cable trench shall be comprised of eight (8), 129mm (5”) ID PVC ducts, installed in a duct spacer system complete with steel reinforcing, and encased in concrete. .4 The conduits running between the Control Building and the Transformer 429N-T41 transformer pad shall be comprised of two (2), 129mm (5”) ID PVC ducts, installed in a duct spacer system complete with steel reinforcing, and encased in concrete. .5 Duct spacers shall be installed every 1800mm (6’) to ensure ducts do not sag during the concrete pour. The top of the duct spacer shall be a minimum of 1000mm (39”) below finished grade. .6 10M steel reinforcing bars shall be installed longitudinally in the four corners of each consecutive duct spacer to form a continuous reinforcing system. 10M steel reinforcing bars shall be added as required to strengthen the duct bank. .7 The duct bank shall be encased in concrete. The concrete mix data shall be submitted for review by the Engineer prior to preparation of the first concrete batch. The minimum compressive strength of the concrete shall be 30MPa (4350psi) after 28 days. Test cylinders shall be obtained, and stored, at site during the pour for each batch of concrete. The minimum concrete cover over the duct spacers shall be 38mm (1-1/2”), all-around. .8 The concrete encasement shall remain exposed to the air and allowed to cure for at least 24 hours before backfilling with the native excavated material. The backfilled material shall be compacted, to 95% Proctor Density, in 150mm (6”) lifts on layers. .9 The conduits running between the Control Building and the transformer pads located on the east side of the Control Building shall be comprised of direct buried 129mm (5”) ID and 103mm (4”) ID PVC ducts. .10 The conduits running between the Control Building and the substation lighting poles shall be comprised of direct buried 129mm (5”) ID and 103mm (4”) ID PVC ducts. .11 On the inside wall of the Control Building cable tray vault and at the location where the conduits rise above grade, each conduit/duct shall be clearly identified, using a permanent marker system, with the duct ID number, as indicated on the drawings. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 25 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 5.2/ .12 Each duct shall be thoroughly swabbed to remove any dirt and foreign material. A 3mm (1/8”) stranded polyethylene rope shall be installed in each duct running between each cable vault. .13 A continuous warning tape marker shall be laid approximately 300mm (12”) below finished grade over the full length of each concrete encased and direct buried conduit/duct bank. 5.3 INSTALLATION OF CONDUITS TO/FROM CABLE TRENCH .1 As described in Section 6.2, conduit sleeves shall be installed in the cable trench walls. Each of the conduit sleeves shall be extended beyond the cable trench wall and connected to PVC conduits/ducts, sized per the conduit schedule. .2 The conduits running between the Control Building and the cable trench shall be direct buried and comprised of eight (8), 129mm (5”) ID PVC ducts as described in Section 5.2. .3 The conduits running between the cable trench and yard lighting poles shall be direct buried and consist of one (1), 53mm (2”) ID PVC ducts as described in Section 5.4. .4 The conduits running between the cable trench and the voltage transformer concrete pad shall be direct buried and consist of one (1), 53mm (2”) ID PVC ducts as indicated on the conduit schedule. .5 The conduits running between the cable trench and the oil containment drain valve chamber shall be direct buried and consist of one (1), 53mm (2”) ID PVC ducts as indicated on the conduit schedule. .6 The conduits shall be placed on a 75mm bed of compacted sand, and then covered with a 75mm compacted sand layer. The native excavated soil shall be used to backfill the remainder of the trench. The backfill shall be compacted in 150mm intervals. .7 The conduits running between the Control Building and the transformer pads located on the east side of the Control Building shall be comprised of direct buried 129mm (5”) ID and 103mm (4”) ID PVC ducts. .8 The conduits running between the Control Building and the substation lighting poles shall be comprised of direct buried 129mm (5”) ID and 103mm (4”) ID PVC ducts. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 26 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 5.3/ .9 On the inside wall of the Control Building cable tray vault and at the location where the conduits riser above grade, each conduit/duct shall be clearly identified, using a permanent marker system, with the duct ID number, as indicated on the drawings. .10 Each duct shall be thoroughly swabbed to remove any dirt and foreign material. A 3mm (1/8”) stranded polyethylene rope shall be installed in each duct running between each cable vault. .11 A continuous warning tape marker shall be laid approximately 300mm (12”) below finished grade over the full length of each concrete encased and direct buried conduit/duct bank. 5.4 INSTALLATION OF SUBSTATION YARD LIGHTING CONDUITS .1 As described in Section 10.8, a substation yard lighting system shall be installed around the perimeter of the substation. .2 Two (2), 53mm (2”) conduit sleeves will be provided in the control building east foundation wall to serve the south east yard lighting pole and the internet service providers transmitter/receiver. The yard lighting circuit conduit shall be extended into the lighting pole junction box. The internet service provider (ISP) conduit shall be extended up the pole, at least 3m above finished grade. The open end of the conduit shall be sealed, following installation of the ISP cable. .3 One (1), 53mm (2”) conduit shall be supplied and installed between the south east yard lighting pole and the north east yard lighting pole. The conduit shall be extended into the lighting pole junction box. .4 One (1), 53mm (2”) conduit shall be supplied and installed between the cable trench and the north yard lighting pole. The conduit shall be extended into the lighting pole junction box. .5 One (1), 53mm (2”) conduit shall be supplied and installed between the cable trench and the north west yard lighting pole. The conduit shall be extended into the lighting pole junction box. .6 One (1), 53mm (2”) conduit shall be supplied and installed between the cable trench and the south yard lighting pole. The conduit shall be extended into the lighting pole junction box. .7 One (1), 53mm (2”) conduit shall be supplied and installed between the south yard lighting pole and the south west yard lighting pole. The conduit shall be extended into the lighting pole junction box. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 27 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 5.4/ .8 On the inside wall of the Control Building cable tray vault, in the cable trench and at the location where the conduits rise above grade, each conduit/duct shall be clearly identified, using a permanent marker system, with the duct ID number, as indicated on the drawings. .9 Each duct shall be thoroughly swabbed to remove any dirt and foreign material. A 3mm (1/8”) stranded polyethylene rope shall be installed in each duct running between each cable vault. .11 A continuous warning tape marker shall be laid approximately 300mm (12”) below finished grade over the full length of each concrete encased and direct buried conduit/duct bank. 6. INSTALLATION OF CABLE TRENCH SYSTEM 6.1 GENERAL .1 Drawing No. 023-478-D-1105, Rev. A01 shows the location, arrangement and Bill of Material with item numbers for the underground conduits to be located inside the Substation Yard. 6.2 INSTALLATION OF CABLE TRENCH WALLS AND BASE SLAB .1 The cable trench area shall be excavated to a depth not less than 500mm below the elevation of the cable trench base slab. This June require breaking of bedrock in some locations. Refer to the Geotechnical Investigation Report Data Sheet provided in Appendix A. .2 A 100mm layer of NSDOTIR Class B gravel shall be supplied and compacted to form the base for the cable trench base slab and walls. .3 The cable trench base slab and walls shall be formed, complete with reinforcing steel, as indicated on the drawings. The inside wall of the cable trench shall be provided with a 41mm x 42.5mm ledge for the installation of a cable trench cover, as described in Section 6.3. .4 100mm (4”) diameter drain pipes shall be installed in the cable trench base slab at selected locations, as indicated on the drawings. Refer to Section 4.3. .5 129mm (5”) and 3mm (2”) diameter conduit sleeves shall be installed in the cable trench walls at selected locations, as indicated on the drawings. Refer to Section 5.3. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 28 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 6.2/ .6 Concrete shall be placed for the cable trench base slab and walls and vibrated into all voids. A 1% slope, from south to north, shall be maintained over the entire length of the base slab to provide natural drainage toward each of the cable trench drains. The concrete mix data shall be submitted for review by the Engineer prior to preparation of the first concrete batch. The minimum compressive strength of the concrete shall be 30MPa (4350psi) after 28 days. Test cylinders shall be obtained, and stored, at site during the pour for each batch of concrete. The minimum concrete cover over the reinforcing steel shall be 38mm (1-1/2”), all-around. .7 The cable trench concrete shall be protected from rain and allowed to cure for at least 24 hours before proceeding with the forming of the cable trench walls. 6.3 INSTALLATION OF CABLE TRENCH COVER .1 A FRP cable trench cover system will be supplied and installed flush with the top of the concrete cable trench walls. .2 The composite fiberglass trench cover shall be a non-slip solid cover, molded grating (dark grey) as manufactured by Fibergrate Composite Structures (Contact: Tim MacKinnon-The Stoncor Group, Office:1-800-263-3112, Cell:1-506-651-1991, Fax:1-506-657-9195, Email: tmackinnon@stoncor.com ) .3 The shape, width and length of each cover section shall be custom designed to suit the cable trench. The Contractor shall forward a copy of the cable trench design drawing to Fibergrate Composite Structures for their reference. .4 Concrete inserts shall be supplied and installed in the concrete trench wall (drilled and set into the concrete wall ledges) at 2 m intervals along the length of the trench and at the 90° corners. .5 Stainless steel hardware (clamps, bolts and washers) shall be used to secure the Fibergrate cover to the concrete trench ledge. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 29 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 7. INSTALLATION OF SUBSTATION EMBEDDED GROUND GRID 7.1 GENERAL .1 Drawing Nos. 023-478-D-3021, Rev. A01 and 023-478-D-3023, Rev. A01 shows the location, arrangement and Bill of Material of the Substation embedded ground grid. 7.2 INSTALLATION OF SUBSTATION EMBEDDED GROUND GRID SYSTEM .1 Following installation of all underground services within the substation area, including drainage systems, concrete foundations and equipment pads and underground conduit systems, the surface of the substation site shall be graded and compacted to an elevation of 62.35m± above mean sea level. .2 The ground grid conductors shall be 4/0AWG stranded, bare copper conductor, supplied by the Owner. The parallel north-south conductors and the parallel east-west conductors shall cross at right angles and shall form a 5m x 5m grid, except as follows: .1 ground grid conductors shall extend 1m beyond the substation perimeter fence. .2 ground grid conductors shall be located 1m off the Substation Control Building walls. .3 Ground grid conductors shall be located halfway between equipment foundations/pads where a 5m spacing is not practical. .3 At the intersection of each north-south and east-west ground grid conductor, a 4/0AWG to 4/0AWG copper compression cross-connector shall be used to connect the conductors. .4 19mm diameter x 3m long copper clad galvanized ground rods shall be supplied and installed at twenty-seven (27) locations within the ground grid. The ground rods shall be connected to the 4/0AWG copper ground conductor using a conductor to rod copper compression connector. Two (2) of the ground rods shall be accessible from the surface for testing purposes, by placing an FRP ground electrode access enclosure directly above the ground rods. .5 At the location of each vehicular gate, the 4/0AWG copper ground grid conductor shall extend 3000mm beyond the perimeter fence, as indicated on the drawing. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 30 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 7.2/ .6 At selected points within the ground grid, a 4/0AWG copper ground pigtail shall be connected to the ground grid conductor using a 4/0AWG copper compression tee-connector. The copper ground pigtail shall have a minimum length of 3m and/or be of sufficient length to connect to the equipment ground pad/ground bus, as indicated. .7 At selected points around the Substation Control Building, 4/0AWG copper ground pigtails shall be connected to the ground grid conductor using a 4/0AWG copper compression tee connector. The copper ground pigtails shall be run into the Control Building cable tray vault through the 27mm conduit sleeves provided in the foundation walls. The ground pigtails shall be of sufficient length to connect to the copper ground buses mounted on the interior walls of the cable tray vault. .8 Following inspection of the ground grid by the Inspection Authority, the entire embedded ground grid shall be covered with a minimum of 150mm of native material and compacted to 95% Proctor Density. .12 Ground grid resistance testing will be carried out by Strum Engineering with the assistance of the Contractor. 8. INSTALLATION OF SUBSTATION PERIMETER FENCE SYSTEM 8.1 GENERAL .1 Drawing Nos. 023-478-D-1103, Rev. A01, 023-478-D-3022, Rev. A01 and 023-478-D-3032, Rev. A01 show the location, arrangement, details and Bill of Material of the Substation perimeter fence system. .2 The substation perimeter fence shall be supplied and installed to meet the requirements of Section 26-300 and Section 36 of the Canadian Electrical Code. 8.2 INSTALLATION OF SUBSTATION PERIMETER FENCE SYSTEMS .1 The substation perimeter fence shall run parallel with the north-south and east-west property lines to form an enclosed area measuring 60m x 70m. The fence shall be setback 2500mm from the east, south and west property lines. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 31 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 8.2/ .2 The substation perimeter fence shall consist of galvanized steel, chain-link fence secured to galvanized steel corner and tangent posts, vehicular gates, man gates and barbed wire. .3 Galvanized steel corner, tangent and vehicular gate posts shall be installed in a straight line between the four corners of the substation. The posts shall be installed in concrete-filled sonotubes, installed at a minimum setting depth of 1000mm below finished grade. The minimum height above the finished grade, excluding the barbed wire, shall be 1.8m. .4 Galvanized steel vehicular gates, complete with a man gate, shall be supplied and installed in the two locations indicated on the drawings. .5 Galvanized steel chain link fence fabric shall be installed on the outside face of the fence posts and secured to the fence posts using galvanized wire. .6 Galvanized steel post caps c/w barbed wire support bracket shall be supplied and installed on each fence post. .7 Three rows of galvanized barbed wire shall be run through the barbed wire support bracket and secured in place. .8 “Danger-High Voltage” warning signs shall be supplied and installed at horizontal intervals not exceeding 15m, in accordance with Section 36-006 of the Canadian Electrical Code. .3 The substation perimeter fence posts, vehicular and man gates, chain-link fabric, top rail and barbed wire shall be grounded using copper conductor and braided conductors as indicated on the drawings and as pursuant to Section 36-312. 8.3 INSTALLATION OF SUBSTATION INTERIOR FENCE SYSTEMS .1 An interior fence system shall be supplied and installed on the north and east sides of the substation Control Building to form an enclosed area which provide access to the control building without allowing access to the main substation yard. .2 The substation interior fence shall consist of galvanized steel, chain-link fence secured to galvanized steel corner and tangent posts. .3 The posts shall be installed in concrete-filled sonotubes, installed at a minimum setting depth of 1000mm below finished grade. The minimum height above the finished grade shall be 1.8m. The posts in front of Rooms 103 and 104 shall be arranged to allow vehicular access to the control building when the fence fabric is removed. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 32 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 8.3/ .4 Galvanized steel chain link fence fabric shall be installed on the outside face of the fence posts and secured to the fence posts using galvanized wire. The fence fabric in front of Rooms 103 and 104 shall be designed to be removable to allow vehicular access to the control building. .5 Galvanized steel post caps c/w barbed wire support bracket shall be supplied and installed on each fence post. .6 The substation perimeter fence posts, vehicular and man gates, chain-link fence fabric, top rail and barbed wire shall be grounded using copper conductor and braided conductors as indicated on the drawings and as pursuant to Section 36-312. 9. FINAL SUBSTATION GRADING 9.1 GENERAL .1 Drawing No. 023-478-D-1101, Rev. A01 shows the location, gravel layer thickness and description of the gravel materials required to achieve the final substation grade. 9.2 FINAL SUBSTATION GRADING .1 Following the covering and compaction of native material over the embedded ground grid, the installation of the substation perimeter fence posts and the field testing of the ground grid to confirm that the ground grid resistance value meets the design requirements, the Contractor June proceed with the installation of substation surface gravel materials. .2 A 300mm layer of NSDOTIR Class A gravel shall be installed over the compacted native backfill. The Class A gravel shall extend a minimum of 2m beyond the Substation perimeter fence line. The Class A gravel shall be compacted, to 95% Proctor Density, in 150mm (6”) layers. The copper ground pigtails shall secured above the concrete equipment pads during the grading and compacting work. .3 A 150mm layer of 19mm-25mm washed crushed stone shall be placed on the surface of the compacted Class A gravel. The top layer shall remain lose and shall not be compacted. .4 The final substation grading materials shall extend 2500mm beyond the substation perimeter fence. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 33 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 9.2/ .5 The final finished grade elevation shall be 62.95mm±. .6 The two (2) FRP ground grid access enclosures shall be installed directly above the two (2) test point ground rods, as indicated on the drawings. .7 An access walkway shall be provided on the exterior, east side of the substation, between the FORCE property line and the substation perimeter fence. The walkway shall extend from the north end vehicular gate to the Control Building. The walkway shall be covered by NSDOTIR Class A gravel. The purpose of the walkway is to provide personnel access to the Control Building without entering the high voltage substation area. 10. INSTALLATION OF SUBSTATION CONTROL BUILDING SERVICES 10.1 GENERAL .1 Drawing Nos. 023-478-D-3031, Rev. A01 to 023-478-D-3040, Rev. A01, show the location, details, schedules and Bill of Materials related to the Substation Control Building electrical and mechanical services. .2 Perform all work in accordance with the Canadian Electrical Code (CEC), the National Building Code of Canada and any and all local ordinances and laws. .3 Pay all permits and fees and obtain all inspections required by all laws, ordinances, rules and regulations. .4 All equipment and exposed non-current carrying metal conduits and parts shall be grounded to meet the requirements of CEC and the authority having jurisdiction. All conduits to have separate green ground wire in runs sized per Table 16 of the CEC. .5 Submit shop drawings/product data sheets for the disconnect switches, automatic transfer switch, panelboards, transformers, lighting fixtures, emergency lights, exit lights, unit heaters, air conditioning units, fire alarm panel and associated devices, security panels and associated devices, junction boxes and fuses. .6 All wire and cable shall be copper & conform to the CEC, CSA, EEMAC, ICEA and ASTM. Wiring insulation shall be XLPE, RW90, rated 600V. Conductors and shall be colour coded or have individual conductor numbers. .7 Panelboards shall have copper bus, ampacity as indicated on panel schedules, and be mounted 1900mm to top of panel above finished floor. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 34 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 10.1/ .8 Disconnect switches shall be of voltage and amperage as shown fused or unfused as indicated. They shall be heavy duty safety switches, general purpose enclosure type c/w fuses and lamicoid nameplates. .9 Supply and install specification grade duplex receptacles shown on plan, 450mm above finished floor, unless otherwise noted. 10.2 PREPARATORY WORK CARRIED OUT BY OTHERS The following preparatory work will be carried out by Others: .1 Supply and installation of underground conduits between the location of the NSPI standby station service transformer pad and the Control Building. .2 Supply and installation of a 240/120V, 400A single phase revenue meter base on the exterior wall of the Control Building. .3 Supply and installation of insulated power conductors between the NSPI standby station service transformer and the 240/120V, 400A single phase revenue meter base on the exterior of the Control Building. .4 Supply and installation of twelve (12), 35kV, 600A two-way deadbreak separable junctions supplied and installed on the east interior walls in the Control Building cable tray vault (basement level). .5 Openings in the floors and basement walls to facilitate routing of cables and ground conductors are indicated on Drawing No.’s 023-478-E-1131 and 023478-E-1132. All other openings that are required will be core drilled under this contract. 10.3 INSTALLATION OF CONTROL BUILDING GROUNDING SYSTEMS .1 As described in Section 7.2, 4/0 AWG copper conductors (pigtails) shall be extended from the substation embedded ground grid to Substation Control Building cable tray vault. .2 Connections to the substation main ground grid are made by five (5), 4/0 AWG bare copper grounding conductors which enter the Control Building cable tray vault through individual 27mm diameter conduit sleeves. These grounding conductors shall be connected to the Control Building grounding system at the basement level ground bars as indicated on the drawings. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 35 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 10.3/ .3 Five (5) copper ground bus systems of varying lengths, consisting of 50mm (2”) wide x 6mm (1/4”) thick copper bus bar and 600V polymer standoff insulators complete with stainless steel mounting hardware shall be supplied and installed in each of the main level Rooms, as indicated on drawings. .4 The ground bus system on the main level shall be mounted 300mm (12”) above the floor, in the locations indicated on the drawings. .5 Two (2) copper ground bus systems, consisting of 50mm (2”) wide x 6mm (1/4”) thick copper bus bar and 600V polymer standoff insulators complete with stainless steel mounting hardware shall be supplied and installed on the walls in the Control Building cable tray vault, as indicated on drawings. .6 The ground bus system on the walls in the cable tray vault shall be mounted 300mm (12”) below the entry point of each grounding conductor conduit sleeve, in the locations indicated on the drawings. .7 The copper bus bar shall be drilled on site to suit the connection of grounding and bonding conductor connectors. .8 The main level ground bus bars shall each be connected to the cable tray vault ground bus bars using two (2) 4/0 AWG green insulated copper conductors, using 4/0 AWG copper one-hole, long-barrel crimp-type compression connectors (Burndy Cat. No. YA28, or equal) and stainless steel hardware, as indicated on the drawings. The 4/0 AWG conductors shall be connected on opposite ends of each ground bar. 10.4 INSTALLATION OF CONDUIT AND CABLE TRAY SYSTEMS 1. Electrical Metallic Tubing (EMT) or rigid galvanized steel conduit shall be run between electrical equipment as indicated on the drawings. 2. Conduit hanger supports shall be supplied and installed from the roof joists using beam clamps. 3. Galvanized lock washers shall be used to secure the conduit to the equipment enclosures. 4. Conduit bushing fittings shall be installed on the ends of the conduit to prevent damage to the insulated conductors. 5. Aluminum, ladder type, cable tray shall be supplied and installed in the Substation Control Building cable tray vault (basement) and in the Control Building main level Rooms, as indicated on Drawing Nos. 023-478-D-3037, Rev. A01, 023-478-D-3038, Rev. A01 and 023-478-D-3039, Rev. A01. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 36 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 10.4/ 6. Cable tray sections located in the Control Building cable tray vault shall be supported on and secured to galvanized steel strut channels suspended from the concrete ceiling using anchor bolts and concrete inserts. 7. Cable tray sections located in the Control Building main level Rooms shall be supported on and secured to galvanized steel strut channels suspended from the steel roof joists using beam clamps. 8. A bare copper 4/0AWG conductor shall be installed in a continuous run over the full length of each cable tray assembly. The ground conductor shall be bonded to each cable tray section using a copper cable tray ground connector. The end of the cable tray grounding conductor shall be connected to one of the cable tray vault ground buses using a 4/0AWG, copper, one-hole, long barrel crimp type compression connector (Burndy Cat. No. YA28, or equal). 9. Warning signs marked “Danger - High Voltage” (Thomas & Betts Cat. No. BP0169) shall be attached at 10m intervals from all cable tray assemblies designated to support power cables rated above 600V. 10.5 INSTALLATION OF CONTROL BUILDING ELECTRICAL SERVICES .1 The building is designed to have two sources of 240/120V station service power to provide the Control Building electrical services. The primary source will be from a 100kVA padmount station service transformer (429N-T31). The standby, secondary source will be from a 100kVA utility (NSPI) supplied and installed padmount transformer and 240/120V, 400A single phase metered service. .2 The Contractor shall arrange and pay for the provision of the NSPI standby station service and revenue metering equipment between the riser pole on the West Bay Road and The Substation Control Building. .3 Plywood backboards (4’ high x ¾” thick x length as indicated), painted with grey fire retardant paint, shall be supplied and installed on the interior walls between metal framing channels provided by the building manufacturer. The plywood backboards shall be sized to accommodate all electrical equipment mounted on the interior building walls, as indicated on Drawing No. 023-478D-3031, Rev. A01. .4 Two (2), 240Vac, 400A, 2-pole fused disconnect switches shall be supplied and installed in Room 100 on the interior plywood backboard, as indicated on the drawings. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 37 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 10.5/ .5 One (1), 240Vac, 400A, 3 phase, 3-pole automatic transfer switch shall be supplied and installed in Room 100 on the interior plywood backboard, as indicated on the drawings. .6 Supply and install a 60 circuit, 240/120V, 400A, 1 phase, 3 wire copper panelboard (AC1), with 400A-2P main breaker and adequately sized branch breakers, as indicated on the panel schedule, in Room 100 of the Substation Control Building. Ground the panelboard enclosure to the building ground bus. .7 Supply and install a 100kVA, 13.8kV-240/120V, single phase, copper winding, padmount distribution transformer (429N-T31), complete with 4 x 2½% taps (2 – FCAN and 2- FCBN), on the station service transformer pad, as described in Section 16 and as indicated on the drawings. Ground the transformer neutral to the substation ground bus with a 4/0AWG copper conductor. Ground the distribution transformer ground bus to the substation ground grid using the 4/0 AWG pigtails described in Section 7.2. .8 Supply and install a 30 circuit, 240/120V, 100A, 1 phase, 3 wire copper panelboard, complete with a 60A-2P main breaker and adequately sized branch breakers, in each of the Rooms 101, 102, 103 and 104, as indicated on the drawings. Ground the panelboard enclosure to the building ground bus. .9 Supply and install 120V, fluorescent tube fixtures in the quantity and locations required to provide a minimum light level of 50 lux in all working spaces. The lighting system shall be controlled by a single pole toggle switch (surface mounted) located at the entrance to each room of the Control Building. .10 Supply and install electric, forced air, unit heaters, in the locations indicated on the drawings. The unit heaters shall be 5000W, 240V – 1 phase, supplied from each 240/120V panelboard. The unit heater shall be equipped with a forced fan unit and shall have integral thermostat control to ensure a room temperature between 10ºC to 25ºC. .11 Supply and install 70W, 120V lighting fixtures on the exterior wall above each mandoor and double equipment door, as indicated on the drawings. Each lighting fixture shall be equipped with an integral photoelectric control circuit. .12 Supply and install EXIT signs on the interior of each Room above the mandoor and the double equipment door, as indicated on the drawings. .13 Supply and install two (2) emergency lighting packs (battery units) in Rooms 100, 101 and 102 and one (1) emergency lighting pack in Rooms 103 and 104. Connect the emergency lighting packs to the same circuit as the fluorescent lighting fixtures. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 38 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 10.5/ .14 Supply and install 125V, 15A, U-ground convenience receptacles, complete with steel box and cover plate, on the interior walls (surface mounted), as indicated on the drawings. .15 Supply and install 125V, 15A, U-ground ground fault circuit interrupter receptacles, complete with weatherproof enclosure, on the exterior walls (surface mounted), as indicated on the drawings. .16 Supply and install aluminum, ladder type, cable tray sections and fittings between the 13.8kV switchgear and other equipment in Room 100, including SCADA/Communication Panel P1, 125Vdc distribution panelboard DC1 and the cable entry windows (openings) from the cable tray vault, as indicated on the drawings. .17 Supply and install a multi-zone security system control panel in Room 100 to monitor the door intrusion alarms in Room 100, the individual security system panels in Rooms 101, 102, 103 and 104, output alarm contacts from the fire alarm panel and output status and alarm contacts from the SCADA/ Communication panel .18 Supply and install a 10 zone conventional fire alarm panel in Room 100. The fire alarm panel shall provide monitoring of smoke detectors in each main level Room and in the cable tray vault (basement level). .19 Supply and install a smoke detector on the ceiling (roof joist) near the center of each Room, as indicated on the drawings. Each smoke detector shall be connected to the fire alarm panel located in Room 100. .20 Supply and install four (4) Pilot Cable junction boxes on the interior, south wall of the cable tray vault (beside Pilot Cable Junction Box JB3). Each junction box shall be fitted with a 600V, 50A, 6-pole heavy duty terminal block (GE Cat. No. IKU6C, or equal). .21 Supply and install type RW90 or XLPE insulated copper phase, neutral, ground and bonding conductors in EMT or rigid galvanized steel conduit to supply lighting and power distribution equipment within the Control Building. Conductors shall be sized and colour-coded per the Canadian Electrical Code. 10.6 INSTALLATION OF CONTROL BUILDING MECHANICAL SERVICES .1 Supply and install 5000W, 240V forced air unit heaters in each Control Building Room, as indicated on the drawings. The unit heaters shall be mounted approximately 3000mm above the finished floor; suspended from the roof joists or by wall brackets, per the manufacturer’s instructions. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 39 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 10.6/ .2 Supply each unit heater from panelboard AC1 using a 30A-2P (240V) branch breaker and insulated copper conductors in EMT or rigid galvanized steel conduit. Terminate the cable at the unit heater using flexible conduit to permit adequate rotation of the unit heater. .3 Supply and install a 10,800 BTU/hr (1 ton) air conditioning unit in each Control Building Room, as indicated on the drawings. The air conditioning units shall be mounted on the exterior building walls per the manufacturer’s instructions and as indicated on the drawings. .4 Inlet and Outlet openings shall be provided through the Control Building walls, positioned per the manufacturer’s instructions. .5 Supply each air conditioning unit from panelboard AC1 using a 15A-2P (240V) branch breaker and insulated copper conductors in EMT or rigid galvanized steel conduit. .6 Supply and install a wall-mounted thermostat/controller remote from the air conditioning unit. Ensure the thermostat/controller is located to provide optimum cooling. Connect the thermostat/controller to the air conditioning unit using the manufacturer’s recommended control cable. 10.7 INSTALLATION OF 125VDC STATION BATTERY SYSTEM .1 FORCE has pre-purchased a 125Vdc station battery system consisting of: one (1) 125Vdc, 152A-h VRLA station battery (60 cells) complete with intercell battery cell terminal links and rack system and one (1) 125Vdc battery charger. Refer to DC Schematic Drawing No. 023-478-D-3034, Rev. A01. .2 The Contractor shall transport the station battery components to the Substation Control Room. .3 The sixty (60) battery cells shall be installed and secured in the battery rack in the location indicated on the drawings. The individual battery cell terminals shall be interconnected using the copper bus links supplied by the manufacturer. The links shall be installed as specified by the manufacturer’s assembly drawings. .4 The battery charger shall be mounted on a plywood backboard, as indicated on the drawings. .5 The battery charger shall be supplied from a 15A-2P circuit in panelboard AC1 using insulated conductors in EMT or rigid galvanized steel conduit. .6 The output of the battery charger shall be connected to the 125Vdc station battery using insulated conductors in EMT or rigid galvanized steel conduit. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 40 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 10.7/ .7 The Contractor shall supply and install a 42 circuit, 240V, 225A, 1 phase, 2 wire copper panelboard (DC1), with 150A-2P, dc rated main breaker and adequately sized, two pole branch breakers, as indicated on the panel schedule. Panelboard DC1 shall be mounted on a plywood backboard in Room 100, as indicated on the drawings. Ground the panelboard enclosure to the Control Building ground bus. .8 The battery shall be connected to Panelboard DC1 using insulated conductors in EMT or rigid galvanized steel conduit. .9 An eye wash station shall be supplied and installed near the station battery. 10.8 INSTALLATION OF SUBSTATION YARD LIGHTING SYSTEM .1 The Contractor shall install six (6), Class 2 treated utility poles around the inside perimeter of the substation fence in the locations indicated on Drawing No. 023-478-D-3036, Rev. A01. .2 Five (5) of the poles shall be 13.7m (45’) long and one (1) pole (southeast) shall be 19.8m (65’) long. The top section of the southeast pole shall be used by the Internet Service Provider (ISP) for mounting of high-speed internet antenna. .3 Underground PVC conduits shall be supplied and installed as described in Section 5.4. .4 Two (2), 400W HPS lighting fixtures shall be mounted at an elevation of 11.1m (36.5’) above the substation finished grade. Each lighting fixture shall be connected to a pole top junction box using SOOW equipment cable. .5 A PVC junction box shall be supplied and installed on a plywood backboard mounted on each lighting pole. The underground conduit shall rise into the junction box utilizing an expansion joint fitting. .6 The pole top junction box shall be connected to the lower junction box using TECK cable attached to the pole using cable clamps. .7 A lighting control panel shall be fabricated based on the control schematic and the wiring diagram outlined on the drawings. The yard lighting circuits shall be supplied from six (6), 120V branch circuits in Panleboard AC1. The control panel and associated photocells shall be installed in the Substation Control Building in the location indicated on the drawings. .8 600V insulated tray cable shall be supplied and installed between the yard lighting control panel and each of the yard lighting junction boxes, as indicated on the drawings. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 41 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 11. ERECTION OF SUBSTATION STRUCTURAL STEEL 11.1 GENERAL .1 Drawing Nos. 023-478-D-5000, Rev. A01 to 023-478-D-5010, Rev. A01, inclusive, show the location, details, schedules and Bill of Materials related to the Substation Structural Steel. .2 Anchor bolts shall be supplied and installed as described in Sections 3.2, 3.3, 3.4 and 3.6. 11.2 MATERIAL SUPPLIED BY THE OWNER .1 All structural steel members will be designed, fabricated, galvanized and delivered to site by Others. .2 Each structural steel member will be identified with a unique tag per the Bill of Material list for that structural steel item. 11.3 INSTALLATION OF SUBSTATION STRUCTURAL STEEL .1 The steel members and components which make up the A-Frame Deadend structure shall be erected to form a complete assembly. .2 The steel members and components which make up the Lightning (Surge) Arresters and Inductive Voltage Transformers (429N-PT41) support structure shall be erected to form a complete assembly. .3 The steel members and components which make up the two (2) 138kV Isolating Switches (429N-401A and 429N-401B) and their support structures shall be erected to form two complete assemblies. Note the different orientation of each isolating switch with respect to circuit breaker (429N401). .4 The steel members and components which make up the Lightning (Surge) Arresters support structure at the transformer shall be erected to form a complete assembly. .5 Each structural steel column shall be bonded to the substation ground grid using the 4/0AWG bare copper pigtail provided and described in Section 7.2. Supply and install a copper mechanical connector (Burndy Cat. No. CL2929, or equal) on each structural steel grounding pad. Apply oxide-inhibiting compound (Burndy Penetrox or equal) to all outdoor electrical connections. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 42 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 12. ERECTION OF SUBSTATION EQUIPMENT 12.1 GENERAL .1 Drawing Nos. 023-478-D-1103, Rev. A01, 023-478-D-5000, Rev. A01, 023478-D-5001, Rev. A01, 023-478-D-3901, Rev. A01 and 023-478-D-3902, Rev. A01 show the location, details, schedules, nameplates and Bill of Materials related to the Substation Power Distribution Equipment. .2 Anchor bolts shall be supplied and installed as described in Sections 3.2, 3.3, 3.4 and 3.6. 12.2 MATERIAL SUPPLIED BY THE OWNER .1 The major pieces of power distribution equipment, including the lightning (surge) arresters, inductive voltage transformers, 138kV group-operated isolating switches, 138kV circuit breaker and 5000kVA power transformer have been pre-purchased and will be delivered to site by the Owner. 12.3 INSTALLATION OF SUBSTATION EQUIPMENT .1 Suspension insulators (designed and rated for 138kV transmission line service – minimum leakage distance of 25mm/kV (3450mm)) shall be supplied and installed on the A-Frame Deadend structure crossarm, as indicated on the drawings. .2 Three (3), 21kV (17kV MCOV) lightning (surge) arresters shall be mounted on the Lightning (Surge) Arresters support structure. A 4/0AWG bare copper grounding conductor shall be run and connected to the ground terminal of each lightning (surge) arrester and the substation ground grid. The grounding conductor shall be as short and as straight as possible between points of connection. .3 A NEMA 4 junction box shall be supplied and installed mounted on the east column (Grid C5) of the Inductive Voltage Transformer support structure. The junction box shall house the terminal blocks and fuses associated with each of the voltage transformer secondary circuits. Refer to Drawing No. 023478-D-3024, Rev. A01. .4 Three (3), 14.4kV-120/72V inductive voltage transformers shall be mounted on the Inductive Voltage Transformer support structure. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 43 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 12.3/ .5 Two (2) 138kV group-operated isolating switches (429N-401A and 429N401B) shall be mounted on their respective steel support structures, in accordance with the manufacturer’s installation instructions. The Contractor shall adjust the operating mechanism so that the three independent switch blades open and close in synchronism. .6 A gradient control (grounding) mat shall be supplied and installed at the base of the handle operator of each 138kV isolation switch. The gradient mat, switch operating handle and switch support structure shall be interconnected using multi-stranded, extra-flexible PVC insulated conductors, as indicated on the drawings. Copper ferrules shall be supplied and installed on the end of each switch mounted grounding conductor. .7 The 138kV Circuit Breaker (429N-401) shall be installed on the circuit breaker foundation and secured to the concrete pad using the anchor bolts supplied and installed as described in Section 3.5. The circuit breaker support frame shall be adjusted to provide the minimum vertical clearances specified on Drawing No. 023-478-D-5000. .8 A key interlock system shall be supplied and installed to provide a mechanical/electrical interlock between each of the 138kV group-operated isolating switches and the 138kV circuit breaker. The key interlock scheme shall be a two key scheme (Key A1 and Key B1) which will prevent the opening of either 138kV isolating switch without first opening and locking out the circuit breaker. An electrical Key Switch A1B1 (Key A1 and Key B1), consisting of two (2) independent, 125Vdc, 10Adc rated, key operated contacts, shall be supplied and installed in the circuit breaker control cabinet and wired to the circuit breaker trip circuit as indicated on the circuit breaker dc schematic diagram. Key Interlock A1 shall be a bolt-action mechanical interlock which shall be mounted on a bracket provided on the Isolating Switch 429N-401A operating shaft/mechanism. Key Interlock B1 shall be a bolt-action mechanical interlock which shall be mounted on a bracket provided on the Isolating Switch 429N-401B operating shaft/mechanism. Key A1 and Key B1 shall be held in Key Switch A1B1 at the circuit breaker. The operation of either Key A1 or Key B1 will result in the tripping and locking out of Circuit Breaker 429N-401. When Key A1 and Key B1 have been removed from Key Switch A1B1, each key can be used to open mechanical Key Interlocks A1 and B1 thus allowing each switch to be open. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 44 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 12.3/ .9 Three (3), 21kV (17kV MCOV) lightning (surge) arresters shall be mounted on the Lightning (Surge) Arresters support structure located beside the transformer oil containment basin. A 4/0AWG bare copper grounding conductor shall be run and connected to the ground terminal of each lightning (surge) arrester and to the substation ground grid. The grounding conductor shall be as short and as straight as possible between points of connection. .10 The 5000kVA, 24.94/14.4kV-13.8/8kV power transformer shall be installed on the transformer foundation/pad, as indicated on the drawings. The two (2), 129mm PVC conduits shall be extended into the transformer 13.8kV terminal box utilizing expansion fittings. At two diagonally opposite corners, the transformer shall be bonded to the substation ground grid using the 4/0AWG bare copper pigtail provided and described in Section 7.2. Supply and install a two-hole, long-barrel copper compression connector (Burndy Cat. No. YA28-2N, or equal) on each transformer tank grounding pad. Apply oxideinhibiting compound (Burndy Penetrox or equal) to all outdoor electrical connections. 13. INTERCONNECTION OF SUBSTATION EQUIPMENT 13.1 GENERAL .1 Drawing Nos. 023-478-D-1103, Rev. A01, 023-478-D-5000, Rev. A01, 023478-D-5008, Rev. A01 and 023-478-D-3901, Rev. A01show the location, details and Bill of Materials related to the aluminum tubular bus and ACSR conductors used to interconnect the primary terminals of the Substation Power Distribution Equipment. .2 Galvanized steel or stainless steel hardware, including bolts, nuts, lock washers and flat washers shall be supplied as necessary to secure the aluminum tubular bus and ACSR conductors to the substation equipment. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 45 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 13./ 13.2 FABRICATION OF ALUMINUM TUBULAR BUS ASSEMBLIES .1 The Contractor shall fabricate two (2) tubular bus assemblies, as indicated on Drawing No. 023-478-D-5008, Rev. A01. .2 Each tubular bus assembly shall consist of 103mm (4”), Schedule 40 electrical grade aluminum pipe, sealed on both ends and fitted with welded or bolted-on termination pads (4-hole NEMA pattern). A length of 556.5kcmil ACSR conductor shall be inserted into each tubular bus prior to sealing the ends. .3 The first tubular bus assembly (3 units) shall be installed between the lightning (surge) arresters located at Grid B-3/B-4/B-5 and the line side terminals of 138kV Isolating Switch 429N-401A. 4-hole NEMA pattern terminal pads and fittings shall be supplied and installed in the locations indicated on the drawings. .4 The second tubular bus assembly (3 units) shall be installed between the line side terminals of 138kV Isolating Switch 429N-401B and the lightning (surge) arresters located at Grid G-3/G-4/G-5. 4-hole NEMA pattern terminal pads and fittings shall be supplied and installed in the locations indicated on the drawings. 13.3 INTERCONNECTION OF SUBSTATION EQUIPMENT .1 The Contractor shall supply and install the aluminum tubular bus assemblies, as indicated on the drawings, using stainless steel hardware. .2 Supply and install 556.5kcmil (DOVE) ACSR conductors between the suspension insulators mounted on the A-Frame Deadnend Structure and the aluminum tubular bus assembly located at Grid B-3/B-4/B-5. 4-hole, long barrel aluminum compression connectors (Homac Cat. No. SAL650-4N, or equal) shall be supplied for connection to the aluminum tubular bus terminal pad using stainless steel hardware. Sufficient length shall be allowed at the deadend suspension insulators to make two (2) AMPACT connections to the NSPI transmission line conductors. Apply oxide-inhibiting compound (Burndy Penetrox or equal) to all outdoor electrical connections. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 46 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 13.3/ .3 Supply and install 556.5kcmil (DOVE) ACSR conductors between the load side terminals of 138kV Isolating Switch 429N-401A and the line side bushings of the 138kV Circuit Breaker 429N-401. 4-hole, long barrel aluminum compression connectors (Homac Cat. No. SAL650-4N, or equal) shall be supplied for connection to the isolating switch terminal pads and to the circuit breaker bushing pads, using stainless steel hardware. Apply oxideinhibiting compound (Burndy Penetrox or equal) to all outdoor electrical connections. .4 Supply and install 556.5kcmil (DOVE) ACSR conductors between the load side bushings of the 138kV Circuit Breaker 429N-401 and the line side terminals of 138kV Isolating Switch 429N-401B. 4-hole, long barrel aluminum compression connectors (Homac Cat. No. SAL650-4N, or equal) shall be supplied for connection to the isolating switch terminal pads and to the circuit breaker bushing pads, using stainless steel hardware. Apply oxideinhibiting compound (Burndy Penetrox or equal) to all outdoor electrical connections. .5 Supply and install 556.5kcmil (DOVE) ACSR conductors between the aluminum tubular bus terminal pad located at Grid G-3/G-4/G-5 and the primary bushings of the 5000kVA power transformer. 4-hole, long barrel aluminum compression connectors (Homac Cat. No. SAL650-4N, or equal) shall be supplied for connection to the aluminum tubular bus terminal pads and to the transformer bushings, using stainless steel hardware. Apply oxideinhibiting compound (Burndy Penetrox or equal) to all outdoor electrical connections. .6 Supply and install two (2) horizontal, 25kV interphase spacers (K-Line Insulators TD-IPS, or equal) between each 556.5kcmil (DOVE) ACSR conductor drop lead running from the aluminum tubular bus terminal pad located at Grid G-3/G-4/G-5 and the primary bushings of the 5000kVA power transformer. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 47 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 14. INSTALLATION OF 13.8kV SWITCHGEAR ASSEMBLY 14.1 GENERAL .1 Drawing Nos. 023-478-D-3002, Rev. A05, 023-478-D-3032, Rev. A01 and 023-478-D-3901, Rev. A01 show the location, details, cable schedule and Bill of Materials related to the 13.8kV Switchgear Assembly. .2 The 13.8kV switchgear assembly has been pre-purchased by FORCE and consists of six x 914mm cubicles, complete with circuit breakers, protection, control and metering equipment. The 13.8kV switchgear assembly will be shipped in two (2) pieces, each consisting of three cubicles. The approximate dimensions of the total switchgear assembly are: 5486mm wide x 2388mm high x 2388mm deep. The total weight is approximately 11,105kg. The switchgear manufacturer shall supply all necessary hardware and instructions to connect the two shipping sections. 14.2 INSTALLATION OF 13.8kV SWITCHGEAR ASSEMBLY .1 The Contractor shall receive the 13.8kV Switchgear Assembly from FORCE and install on the concrete floor of the Substation Control Building. .2 The 13.8kV switchgear assembly shall be positioned in the Control Building as indicated on the drawings. The switchgear assembly shall be aligned to be plump and level. The switchgear assembly shall be bolted to the concrete floor, using stainless steel bolts and concrete inserts, at the four corners of the switchgear. .3 Install 4/0AWG bare copper conductors through the 25mm floor conduit sleeves and terminate each end of the conductors on the switchgear ground bus and on the Control Building ground bus, using one-hole, long-barrel copper crimp type compression connectors. .4 Install the circuit breaker test cabinet on the interior wall (plywood backboard) of the Control Building, as indicated on the drawings. Supply and install the feeder cable from 125Vdc Panelboard DC1 to the circuit breaker test cabinet. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 48 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 15. INSTALLATION OF 13.8kV COLLECTOR CIRCUIT GROUNDING TRANSFORMERS 15.1 GENERAL .1 Drawing Nos. 023-478-E-3002, Rev. A05, 023-478-D-3032, Rev. A01, 023478-D-3037, Rev. A01 and 023-478-D-3901, Rev. A01 Drawing Nos. 023478-D-1101, Rev. A01 show the location, details, cable schedule and Bill of Materials related to the Grounding Transformers required on 13.8kV collector circuits. .2 The four (4), 225kVA, 13.8/7.97kV-600V grounding transformers have been pre-purchased by FORCE. The approximate dimensions of the each grounding transformer are: 1862mm wide x 1694mm high x 1324mm deep. The total weight is approximately 2260kg. 15.2 INSTALLATION OF 13.8kV COLLECTOR CIRCUIT GROUNDING TRANSFORMERS .1 The Contractor shall receive the four (4), 225kVA Grounding Transformers from FORCE and install on the concrete transformer pads, located outdoors on the east side of the Substation Control Building. .2 The 225kVA grounding transformers shall be positioned on the transformer pads, as indicated on the drawings. .3 Terminate the two (2) 4/0AWG bare copper ground grid pigtail conductors provided and described in Section 7.2 on the transformer ground bus, using one-hole, long-barrel copper crimp type compression connectors. 16. SUPPLY AND INSTALLATION OF STATION SERVICE TRANSFORMER 16.1 GENERAL .1 Drawing Nos. 023-478-E-3002, Rev. A05, 023-478-D-3032, Rev. A01, 023478-D-3037, Rev. A01 and 023-478-D-3901, Rev. A01 show the location, details, cable schedule and Bill of Materials related to the 100kVA Station Service Transformer 429N-ST31. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 49 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 16./ 16.2 STATION SERVICE TRANSFORMER SPECIFICATION .1 The Contractor shall supply one (1), 100kVA, 13.8kV-240/120V outdoor padmount station service transformer based on the following specification: .2 .3 .4 .5 .6 .1 Single-phase, dead front, sealed-tank, mineral-oil immersed, self-cooled, pad-mounted, compartmental-type distributions transformer in accordance with CSA C227.3-06. .2 100kVA, 60Hz .3 13.8kV primary, 95kV BIL .4 240/120V secondary, 10kV BIL .5 4 – 2 at 2.5% above nominal and 2 at 2.5% below nominal .6 Copper windings and internal connections .7 65°C average temperature rise .8 Standard impedance per CSA C227.3-06 .9 Tamper-resistant, NEMA 3R enclosure .10 Codes and Standards: CSA C227.3-06 and applicable standards in the IEEE C57.12 series The transformer shall be furnished with a medium voltage compartment located on the left and a low voltage compartment on the right. The medium voltage connections shall be via bushing wells and deadbreak separable connector system. The low voltage connections will be via 1000V bushings, each fitted with a 4-hole NEMA pattern tin-plated copper alloy terminal pad. The transformer tank shall be sealed tank design and constructed of heavy gauge steel with welded seams. Tank design shall include sufficient expansion volume to allow operation under full load conditions. The main cover shall be welded onto the tank. The insulating fluid shall be Voltesso 35, or equal, certified to contain no detectable PCB’s (<1 PPM) at the time of shipment and the nameplate shall be so labeled. The transformer shall be self-cooled. Tank grounding provisions shall consist of two ground pads welded to the tank wall on diagonally opposite corners. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 50 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 16.2/ .7 The transformer shall be furnished with a non-corrosive diagrammatic nameplate, permanently attached with non-corrosive hardware. The diagrammatic nameplate shall include the name of the manufacturer of the equipment as well as the location where the transformer was manufactured and tested. The nameplate shall contain all connection and rating information in accordance with CSA C227.3-06, plus the type and quantity of fluid, and the date of manufacture. .8 The transformer painting system shall be in compliance with IEEE C57.12.28. .9 The transformer shall receive all standard routine tests as required by CSA C227.3-06. A certified test report shall be submitted and shall contain the test data for the transformer serial number. The certified test report shall as a minimum contain the data as specified in CSA C227.3-06. .10 The transformer shall have the following ancillary devices: Oil level/fill plug, self-actuating pressure relief device, oil drain plug, cabinet compartment locking and tamper proof features, CSA safety labels. .11 Shop drawings shall be submitted to the Engineer for review prior to the start of manufacturing. .12 Final drawings and a detailed operating and maintenance manual shall be provided. 16.3 INSTALLATION OF THE STATION SERVICE TRANSFORMER .1 The 100kVA station service transformer 429N-ST31 shall be positioned on the station service transformer pad, as indicated on the drawings. .2 Terminate the two (2) 4/0AWG bare copper ground grid pigtail conductors provided and described in Section 7.2 on the transformer ground bus, using one-hole, long-barrel copper crimp type compression connectors. 17. PROVISION OF UTILITY SERVICES 17.1 GENERAL .1 Drawing Nos. 023-478-D-1103, Rev. A05, 023-478-E-3002, Rev. A01, 023478-D-3037, Rev. A01 and 023-478-D-3901, Rev. A01 show the location, details, cable schedule and Bill of Materials related to the 100kVA Utility Standby Station Service, the Telephone (Land Line) Service and the HighSpeed Internet Service. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 51 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 17./ 17.2 PROVISION OF NSPI 240/120V STANDBY STATION SERVICE .1 Arrange and pay for the provision of NSPI standby station service equipment between the riser pole on the West Bay Road and the Substation Control Building. .2 The standby station service shall be 240/120V, 400A, 60Hz, single phase, 3wire supplied from an NSPI owned and supplied outdoor padmount transformer. .3 The utility standby transformer pad shall be provided as described in Section 3.11. .4 The primary (2400V) NSPI circuit shall utilize the underground, concrete encased duct banks and utility supply vaults previously installed by Others between the riser pole on the West Bay Road and the NSPI Utility Service Transformer pad and between the NSPI Utility Service Transformer pad and the 240/120V, 400A revenue meter base located on the exterior south wall of the Control Building. The revenue meter base will be supplied and installed by Others. .5 Arrange and pay for the installation of a revenue meter and commercial account with NSPI, which shall be transferable to FORCE following substantial completion of the work. 17.3 PROVISION OF BELL-ALIANT TELEPHONE SERVICE .1 Arrange and pay for the provision of Bell-Aliant telephone service equipment between the riser pole on the West Bay Road and the Substation Control Building. This shall include the supply and installation of a multi-conductor telephone cable, telephone junction box and termination strips. .2 The telephone equipment shall allow for a minimum of six (6) individual voice and six (6) individual data circuits. .3 Supply and install a non-metallic, telephone junction box on the interior wall (plywood backboard) of the Control Building, as indicated on the drawings. The telephone junction box shall be fitted with a steel back panels for the mounting of a telephone cable terminal strip by Bell-Aliant. A small copper ground bus mounted on standoff insulators shall be provided on back panel of the junction box. .4 A 6AWG green PVC insulated grounding conductor shall be connected from the telephone junction box ground bus to the Control Building ground bus. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 52 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 17.3/ .5 27mm diameter EMT shall be supplied and installed between the telephone junction box and the plywood backboard in each Room on the main floor of the Control Building, as indicated on the drawings, for the future installation of a land-line telephone system by Others. 17.4 PROVISION OF HIGH-SPEED INTERNET SERVICE .1 Arrange and pay for the provision of high-speed, wireless internet service from SeaSide High-Speed Inc., the local Internet Service Provider (ISP). .2 The high-speed internet service shall include initial site signal strength testing, WiFi base-station unit, WiFi client unit, WiFi antenna unit, network switch, installation, configuration and testing. .3 Space will be provided in the SCADA/Communication Panel P1 to house the high-speed internet equipment. .4 27mm EMT shall be supplied and installed between the SCADA/ Communication Panel P1 and the plywood backboard in each Room on the main floor of the Control Building, as indicated on the drawings, An RJ45 receptacle shall be supplied and installed in a surface mounted device box on the plywood backboard in each room. A Cat 6 cable shall be installed between the SCADA/Communication Panel P1and each RJ45 internet receptacle and terminated at both ends. 18. INSTALLATION OF PROTECTION, CONTROL AND SCADA/ COMMUNICATION SYSTEM PANELS 18.1 GENERAL .1 Drawing No. 023-478-D-3032, Rev. A01 shows the location, details, cable schedule and Bill of Materials related to the Protection, Control and SCADA/Communication Panels. .2 For this phase of the project, one (1) Protection and Control Panel and one (1) SCADA/Communication Panel will be fabrication by Others and delivered to the Substation Control Building. Space shall be allowed for three (3) additional panels for future installation beside the panels installed as part of this phase of the project. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 53 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 18./ 18.2 INSTALLATION OF PROTECTION, CONTROL AND SCADA/ COMMUNICATION SYSTEM PANELS .1 The Contractor shall receive the two (2) Protection, Control and SCADA/Communication Panels, namely SCADA/Communication Panel P1 and 25kV Protection and Control Panel P3, from FORCE and install on the concrete floor of the Substation Control Building. .2 Panel P1 and Panel P3 shall be positioned in the Control Building, as indicated on the drawings. Provide a space between the two panels equal to the width of the panel plus 25mm. The Panels shall be aligned to be plumb and level. The Panels shall be bolted to the concrete floor, using stainless steel bolts and concrete inserts, at two opposite corners of each Panel. .3 Install 4/0AWG bare copper conductors through the 27mm floor conduit sleeves and terminate each end of the conductors on the Panel ground bus and on the Control Building ground bus, using one-hole, long-barrel copper crimp type compression connectors. .4 Install the GPS Antenna (supplied by Others) (part of the SEL protection relay clock synchronization system) on the exterior wall of the Control Building. Install the Gas Tube Surge Protector (supplied by Others) on the interior wall of the Control Building, as directed by the Engineer. 19. INSTALLATION AND TERMINATION OF POWER, CONTROL AND SCADA/COMMUNICATION SYSTEM CABLES 19.1 GENERAL .1 Drawing Nos. 023-478-D-3901, Rev. A01 and 023-478-D-3905, Rev. A01 to 023-478-D-3910, Rev. A01, inclusive, show the cable schedule and Bill of Materials related to the installation and termination of Electrical and SCADA/Communication Equipment Cables. .2 Several types of cables are specified for this project, as indicated on the Cable Schedules. The Contractor shall provide the cable type specified for each application, unless otherwise directed by the Engineer. .3 Similarly, cable glands shall be provided which are suitable for use with each distinct type of cable. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 54 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 19./ 19.2 INSTALLATION AND TERMINATION OF 13.8kV POWER CABLES .1 The Contractor shall supply and install all power cables and accessories required to interconnect the 13.8kV power distribution system equipment, as indicated on Dwg. No. 023-478-E-3002, Single Line Diagram. .2 Three (3), 350kcmil, 15kV, 133% XLPE insulated shielded conductors shall be run between the main incoming section (101B) of the 13.8kV switchgear assembly and the 5MVA power transformer, via the cable tray vault and 129mm conduit T1. 350kcmil, 2-hole, long barrel copper crimp type compression connectors shall be supplied and installed on the end of each conductor. 15kV synthetic terminations shall be supplied and installed on each conductor. The cable shield shall be grounded at the 13.8kV switchgear (source) end and isolated at the transformer (load) end of each conductor. Conductors shall be identified by colored tape (A=H1=Red, B=H2=Yellow, C=H3=Blue). .3 Three (3), 350kcmil, 15kV, 133% XLPE insulated shielded conductors shall be run between each of the four (4) switchgear cells (102B, 103B, 104B and 105B) in the 13.8kV Switchgear Assembly and each collector circuit 225kVA grounding transformer (429N-GT411, 429N-GT412, 429N-GT413, 429NGT414), via the cable tray vault and 129mm conduits H1, H2, H3 and H4. 2 AWG, 2-hole, long barrel copper crimp type compression connectors shall be supplied and installed on the end of each conductor. 15kV synthetic terminations shall be supplied and installed on each conductor. The cable shield shall be grounded at the 13.8kV switchgear (source) end and isolated at the grounding transformer (load) end of each conductor. Conductors shall be identified by colored tape (H1=Red,H2=Yellow, H3=Blue). .4 Two (2), 2 AWG, 15kV, 133% XLPE insulated shielded conductors shall be run between the Station Service feeder (106B) of the 13.8kV switchgear assembly and the 100kVA Station Service transformer 429N-ST31, via the cable tray vault and 129mm conduit S1. 2 AWG, 2-hole, long barrel copper crimp type compression connectors shall be supplied and installed on the end of each conductor. 15kV synthetic terminations shall be supplied and installed on each conductor. The cable shield shall be grounded at the 13.8kV switchgear (source) end and isolated at the station service transformer (load) end of each conductor. Conductors shall be identified by colored tape (H1=Red,H2=Black). PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 55 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 19./ 19.3 INSTALLATION AND TERMINATION OF 240/120V POWER CABLES .1 The Contractor shall supply and install all power cables and accessories required to interconnect the 240/120V station service equipment, as indicated on Drawing No. 023-478-D-3034, Rev. A01 and Cable Schedule Drawing No. 023-478-D-3903, Rev. A01. .2 Three (3), 500kcmil, 1kV, XLPE insulated conductors shall be run between the Station Service transformer 429N-ST31 and 240/120V, 400A fused disconnect switch 429N-101. 500kcmil, 2-hole, long barrel copper crimp type compression connectors shall be supplied and installed on the transformer end of each conductor. Conductors shall be identified by colored single phase conductors (X1=L1=Red, X3=L2=Black, X2=N=White). .3 Three (3), 500kcmil, 1kV, XLPE insulated conductors shall be run between the NSPI Utility Station Service transformer and the 240/120V, 400A revenue meter base. 500kcmil, 2-hole, long barrel copper crimp type compression connectors shall be supplied and installed on the transformer end of each conductor. NSPI will make the cable connections at the NSPI transformer. Conductors shall be identified by colored single phase conductors (X1=L1=Red, X3=L2=Black, X2=N=White). .4 Three (3), 500kcmil, 1kV, XLPE insulated conductors shall be run between the load terminals of the NSPI revenue meter base (standby source) and 240/120V, 400A fused disconnect switch 429N-102. 500kcmil, 2-hole, long barrel copper crimp type compression connectors shall be supplied and installed on the transformer end of each conductor. Conductors shall be identified by colored single phase conductors (L1=Red, L2=Black, N=White). .5 Three (3), 500kcmil, 1kV, XLPE insulated conductors shall be run between the load terminals of 240/120V, 400A fused disconnect switch 429N-101 and the “Normal” terminals of the 240/120V, 400A Automatic Transfer Switch and between the load terminals of 240/120V, 400A fused disconnect switch 429N-102 and the “Emergency” terminals of the 400A Automatic Transfer Switch. Conductors shall be identified by colored single phase conductors (L1=Red, L2=Black, N=White). .6 Three (3), 500kcmil, 1kV, XLPE insulated conductors shall be run between the “Load” terminals of the 240/120V, 400A Automatic Transfer Switch and the main incoming circuit breaker of Panelboard AC1. Conductors shall be identified by colored single phase conductors (L1=Red, L2=Black, N=White). PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 56 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 19.3/ .7 Supply, install and terminate all other cables and accessories associated with the 240/120Vac branch circuits supplied from 240/120Vac distribution Panelboard AC1, including all building services, Circuit Breaker 429N-401 heater circuits, 5MVA Transformer 429N-T41 fan control and auxiliary circuits, Oil Containment drain valve control circuit, Protection, Control and SCADA/ Communication Panel circuits and Substation Yard lighting circuits, and any other equipment or devices requiring 240/120Vac power. 19.4 INSTALLATION AND TERMINATION OF 125VDC CABLES .1 The Contractor shall supply and install all cables and accessories required to interconnect the 125Vdc equipment, as indicated on Drawing No. 023-478-D3034, Rev. A01 and Cable Schedule Drawing No. 023-478-D-3904, Rev. A01. .2 Two (2), 2/0 AWG, 1kV, XLPE insulated conductors shall be run between the 125Vdc Station Battery and the main incoming circuit breaker of 125Vdc Panelboard DC1. 2/0 AWG, 1-hole, long barrel copper crimp type compression connectors shall be supplied and installed on the “+POS” and “NEG” battery terminal end of each conductor. Conductors shall be identified by colored tape (Pos (+) = Red, Neg (-) = Black). .3 Supply, install and terminate all other cables and accessories associated with the 125Vdc branch circuits supplied from 125Vdc Panelboard DC1, including feeds to the 13.8kV switchgear assembly, circuit breaker test cabinet, Circuit Breaker 429N-401 protection and control circuits, 5MVA Transformer 429NT41 protection and control circuits and Protection, Control and SCADA/ Communication Panel circuits. Future 125Vdc circuits to Rooms 101, 102, 103 and 104 are not included in this work. 19.5 INSTALLATION AND TERMINATION OF PROTECTION AND CONTROL CABLES .1 The Contractor shall supply and install all cables and accessories required to interconnect and integrate the protection and control systems of the Substation power distribution equipment, as indicated on Cable Schedule Drawing Nos. 023-478-D-3905, Rev. A01 to 023-478-D-3909, Rev. A01, inclusive. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 57 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 19.5/ .2 Two (2) x 4C, 10 AWG 300V, XLPE insulated tray cables shall be run and terminated between the Voltage Transformer Junction Box 429N-JB1 and Protection and Control Panel P3. One cable is designated for the each voltage transformer secondary winding circuit. .3 Four (4) x 4C, 10 AWG 300V, XLPE insulated tray cables shall be run and terminated between Circuit Breaker 429N-401 and Protection and Control Panel P3. One 4C cable is designated for each set of three bushing current transformers. .4 One (1) x 20C, 14 AWG 300V, XLPE insulated tray cable shall be run and terminated between Circuit Breaker 429N-401 and Protection and Control Panel P3. This cable is designated for circuit breaker protection and control circuits. .5 Four (4) x 2C, 10 AWG 300V, XLPE insulated tray cables shall be run between 5MVA Transformer 429N-T41 and Protection and Control Panel P3. One 2C cable is designated for each current transformer. .6 One (1) x 20C, 14 AWG 300V, XLPE insulated tray cable shall be run and terminated between 5MVA Transformer 429N-T41 and Protection and Control Panel P3. This cable is designated for transformer protection and control circuits. .7 Two (2) x 20C, 14 AWG 300V, XLPE insulated tray cable shall be run and terminated between the 13.8kV Switchgear Assembly (Section 101A) and Protection and Control Panel P3. These cables are designated for protection and control circuits. .8 One (1) x 2C, 10 AWG 300V, XLPE insulated tray cable shall be run and terminated between each 225kVA grounding transformer and its respective 13.8kV Switchgear Assembly feeder breaker section (429N-GT411 to 102B, 429N-GT412 to 103B, 429N-GT413 to 104B, 429N-GT414 to 105B). Each 2C cable is designated for the current transformer circuit of the grounding transformer. .9 One (1) x 4C, 10 AWG 300V, XLPE insulated, shielded tray cables shall be run and terminated between Pilot Cable Junction Box JB3 and each of Junction Boxes JB3-A, JB3-B, JB3-C and JB3-D. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 58 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 19./ 19.6 INSTALLATION AND TERMINATION OF SCADA/COMMUNICATION CABLES .1 The Contractor shall supply and install all cables and accessories required to interconnect and integrate the SCADA and Communication systems of the Substation power distribution equipment, as indicated on Cable Schedule Drawing No. 023-478-E-3007, Rev. A01 to 023-478-D-3910, Rev. A01, inclusive. .2 One (1) x 20C, 14 AWG 300V, XLPE insulated tray cable shall be run between Circuit Breaker 429N-401 and SCADA/Communication Panel P1. This cable is designated for circuit breaker status and alarm circuits. .3 One (1) x 20C, 14 AWG 300V, XLPE insulated tray cable shall be run between 5MVA Transformer 429N-T41 and SCADA/Communication Panel P1. This cable is designated for transformer status and alarm circuits. .4 One (1) x 12C, 14 AWG 300V, XLPE insulated tray cable shall be run between each 225kVA grounding transformer and SCADA/Communication Panel P1. Each cable is designated for transformer status and alarm circuits. .5 One (1) x 12C, 14 AWG 300V, XLPE insulated tray cable shall be run between the 100kVA Station Service transformer 429N-ST31 and SCADA/Communication Panel P1. This cable is designated for transformer status and alarm circuits. .6 One (1) x 12C, 14 AWG 300V, XLPE insulated tray cable shall be run between the Oil Containment Drain Control Valve Chamber and SCADA/ Communication Panel P1. This cable is designated for drain valve control and status indication. .7 RG-6 coaxial cable (Schweitzer SEL-C960, or equal) shall be supplied, installed and terminated between the Schweitzer GPS Antenna and the Gas Tube Surge Protector and between the Gas Tube Surge Protector and the Schweitzer SEL-3354 located in SCADA/Communication Panel P1, as indicated on the Cable Schedules. .8 Serial communication cables (Schweitzer SEL-C273A, or equal) shall be supplied, installed and terminated between the Schweitzer protection relays mounted in Protection and Control Panel P3 and the Schweitzer SEL-3354 located in SCADA/Communication Panel P1, as indicated on the Cable Schedules. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 59 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 10.6/ .9 Serial communication cables (Schweitzer SEL-C273A, or equal) shall be supplied, installed and terminated between the Schweitzer SEL-2470, located in SCADA/Communication Panel P1, and the SEL-351 protection relays, located in the 13.8kV switchgear assembly, as indicated on the Cable Schedules. .10 Serial communication cables (Schweitzer SEL-C273A, or equal) shall be supplied, installed and terminated between the Schweitzer SEL-2470, located in SCADA/Communication Panel P1, and the SEL-501 protection relays, located in Protection and Control Panel P3, as indicated on the Cable Schedules. .11 Cat 6 Ethernet cables shall be supplied, installed and terminated between each of the 13.8kV switchgear assembly mounted Schweitzer SEL-351 protection relays and the Schweitzer SEL-3354 located in SCADA/Communication Panel P1, as indicated on the Cable Schedules. .12 Cat 6 Ethernet cables shall be supplied, installed and terminated between each of the 13.8kV Switchgear Assembly mounted ION 7650 revenue meters and the Schweitzer SEL-3354 located in SCADA/Communication Panel P1, as indicated on the Cable Schedules. .13 Cat 6 Ethernet cables shall be supplied, installed and terminated between the Ethernet switch/router located in the SCADA/Communication Panel P1 and the RJ45 receptacles located in each Control Building Room, as indicated on the Cable Schedules. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 PAGE 60 OF 60 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT 20. TESTING AND COMMISSIONING .1 The Contractor shall assist Strum Engineering Associates Ltd. personnel during the testing and commissioning of the Substation Power Distribution Equipment and Control Building Services Equipment. .2 The Contractor should allow a total of 300 hours of labour to assist in the testing program. 21. CABLE TAGS AND EQUIPMENT NAMEPLATES .1 The Contractor shall supply and install new lamicoid nameplates (white face, black lettering) for all new electrical equipment, junction boxes and power distribution circuits installed as part of this project. Refer to Drawing Nos. 023-478-D-3024, Rev. A01 and 023-478-D-3902, Rev. A01. .2 Metal cable ID tag shall be attached at both ends of all power, control, SCADA and communication cables. .3 Lamicoid nameplate lettering shall be subject to review and acceptance by the Engineer. 22. AS-BUILT DRAWINGS .1 Immediately after completion of the construction program, the Contractor shall provide, to the Engineer, one set of red-marked design drawings for this project indicating As-Built information. PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT APPENDIX A PERTINENT INFORMATION FROM THE GEOTECHNICAL INVESTIGATION FINAL REPORT PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 SECTION 01000 2011-06-03 DETAILED SCOPE OF WORK IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT APPENDIX B CCDC 2 – STIPULATED PRICE CONTRACT DOCUMENT PREPARED BY: STRUM ENGINEERING ASSOCIATES LTD. ISSUE DATE: June 2011 CONTRACT NO. 023-478-7-11 2 2 stipulated price contract 2 0 0 8 FUNDY OCEAN RESEARCH CENTER FOR ENERGY (FORCE) IN-STREAM TIDAL POWER GENERATING PLANT SUBSTATION DEVELOPMENT - CONTRACT No. 023-478-7-11 Apply a CCDC 2 copyright seal here. The application of the seal demonstrates the intention of the party proposing the use of this document that it be an accurate and unamended form of CCDC 2 - 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. TABLE OF CONTENTS AGREEMENT BETWEEN OWNER AND CONTRACTOR A-1 The Work A-2 Agreements and Amendments A-3 Contract Documents A-4 Contract Price A-5 Payment A-6 Receipt of and Addresses for Notices in Writing A-7 Language of the Contract A-8 Succession DEFINITIONS 1. Change Directive 2. Change Order 3. Construction Equipment 4. Consultant 5. Contract 6. Contract Documents 7. Contract Price 8. Contract Time 9. Contractor 10. Drawings 11. Notice in Writing 12. Owner 13. Place of the Work 14. Product 15. Project 16. Provide 17. Shop Drawings 18. Specifications 19. Subcontractor 20. Substantial Performance of the Work 21. Supplemental Instruction 22. Supplier 23. Temporary Work 24. Value Added Taxes 25. Work 26. Working Day GENERAL CONDITIONS OF THE STIPULATED PRICE CONTRACT PART 1 GENERAL PROVISIONS GC 1.1 Contract Documents GC 1.2 Law of the Contract GC 1.3 Rights and Remedies GC 1.4 Assignment PART 2 ADMINISTRATION OF THE CONTRACT GC 2.1 Authority of the Consultant GC 2.2 Role of the Consultant GC 2.3 Review and Inspection of the Work GC 2.4 Defective Work PART 3 EXECUTION OF THE WORK GC 3.1 Control of the Work GC 3.2 Construction by Owner or Other Contractors GC 3.3 Temporary Work GC 3.4 Document Review GC 3.5 Construction Schedule GC 3.6 Supervision GC 3.7 Subcontractors and Suppliers GC 3.8 Labour and Products GC 3.9 Documents at the Site GC 3.10 Shop Drawings GC 3.11 Use of the Work GC 3.12 Cutting and Remedial Work GC 3.13 Cleanup PART 4 ALLOWANCES GC 4.1 Cash Allowances GC 4.2 Contingency Allowance PART 5 PAYMENT GC 5.1 Financing Information Required of the Owner GC 5.2 Applications for Progress Payment GC 5.3 Progress Payment GC 5.4 Substantial Performance of the Work GC 5.5 Payment of Holdback upon Substantial Performance of the Work GC 5.6 Progressive Release of Holdback GC 5.7 Final Payment GC 5.8 Withholding of Payment GC 5.9 Non-conforming Work PART 6 CHANGES IN THE WORK GC 6.1 Owner’s Right to Make Changes GC 6.2 Change Order GC 6.3 Change Directive GC 6.4 Concealed or Unknown Conditions GC 6.5 Delays GC 6.6 Claims for a Change in Contract Price PART 7 DEFAULT NOTICE GC 7.1 Owner's Right to Perform the Work, Terminate the Contractor’s Right to Continue with the Work or Terminate the Contract GC 7.2 Contractor's Right to Suspend the Work or Terminate the Contract PART 8 DISPUTE RESOLUTION GC 8.1 Authority of the Consultant GC 8.2 Negotiation, Mediation and Arbitration GC 8.3 Retention of Rights PART 9 PROTECTION OF PERSONS AND PROPERTY GC 9.1 Protection of Work and Property GC 9.2 Toxic and Hazardous Substances GC 9.3 Artifacts and Fossils GC 9.4 Construction Safety GC 9.5 Mould PART 10 GOVERNING REGULATIONS GC 10.1 Taxes and Duties GC 10.2 Laws, Notices, Permits, and Fees GC 10.3 Patent Fees GC 10.4 Workers' Compensation PART 11 INSURANCE AND CONTRACT SECURITY GC 11.1 Insurance GC 11.2 Contract Security PART 12 INDEMNIFICATION, WAIVER OF CLAIMS AND WARRANTY GC 12.1 Indemnification GC 12.2 Waiver of Claims GC 12.3 Warranty The Canadian Construction Documents Committee (CCDC) is a national joint committee responsible for the development, production and review of standard Canadian construction contracts, forms and guides. Formed in 1974 the CCDC is made up of volunteer representatives from: Public Sector Owners Private Sector Owners Canadian Bar Association (Ex-Officio) * The Association of Canadian Engineering Companies * The Canadian Construction Association * Construction Specifications Canada * The Royal Architectural Institute of Canada *Committee policy and procedures are directed and approved by the four constituent national organizations. CCDC 2 is the product of a consensus-building process aimed at balancing the interests of all parties on the construction project. It reflects recommended industry practices. CCDC 2 can have important consequences. The CCDC and its constituent member organizations do not accept any responsibility or liability for loss or damage which may be suffered as a result of the use or interpretation of CCDC 2. CCDC Copyright 2008 Must not be copied in whole or in part without the written permission of the CCDC. Standard Construction Document CCDC 2 – 2008 AGREEMENT BETWEEN OWNER AND CONTRACTOR For use when a stipulated price is the basis of payment. This Agreement made on the day of in the year 2011 . by and between the parties FUNDY OCEAN RESEARCH CENTER FOR ENERGY (FORCE) hereinafter called the "Owner" and hereinafter called the "Contractor" The Owner and the Contractor agree as follows: ARTICLE A-1 THE WORK The Contractor shall: 1.1 perform the Work required by the Contract Documents for _____________________________________________________ IN-STREAM TIDAL POWER GENERATING PLANT - SUBSTATION DEVELOPMENT insert above the name of the Work located at ____________________________________________________________________________________________ BLACK ROCK, NOVA SCOTIA (10km WEST OF PARRSBORO, NS) insert above the Place of the Work for which the Agreement has been signed by the parties, and for which ___________________________________________ STRUM ENGINEERING ASSOCIATES LTD. insert above the name of the Consultant is acting as and is hereinafter called the "Consultant" and 1.2 do and fulfill everything indicated by the Contract Documents, and 1.3 day of in the year 2011 and, subject to adjustment in Contract commence the Work by the 30th day Time as provided for in the Contract Documents, attain Substantial Performance of the Work, by the of SEPT. in the year 2011 . ARTICLE A-2 AGREEMENTS AND AMENDMENTS 2.1 The Contract supersedes all prior negotiations, representations or agreements, either written or oral, relating in any manner to the Work, including the bidding documents that are not expressly listed in Article A-3 of the Agreement - CONTRACT DOCUMENTS. 2.2 The Contract may be amended only as provided in the Contract Documents. CCDC 2 – 2008 File 005213 1 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. ARTICLE A-3 CONTRACT DOCUMENTS 3.1 The following are the Contract Documents referred to in Article A-1 of the Agreement - THE WORK: − − − * Agreement between Owner and Contractor Definitions The General Conditions of the Stipulated Price Contract THE FOLLOWING DOCUMENTS SHALL BE PROVIDED BY XXXXXXXXXXXXXXXX: 1. A PERFORMANCE BOND OR CERTIFIED CHEQUE (PAYABLE TO "FUNDY OCEAN RESEARCH CENTER FOR ENERGY") IN THE AMOUNT OF 10% OF THE CONTRACT PRICE, $XXX,XXX.XX, TO BE HELD IN TRUST UNTIL SUBSTANTIAL COMPLETION OF THE WORK. THE FOLLOWING DOCUMENTS WILL BE PROVIDED BY FUNDY OCEAN RESEARCH CENTER FOR ENERGY: 1. DETAILED SCOPE OF WORK CONTRACT No. 023-478-7-11 2. CONSTRUCTION DRAWING SET SERIES 023-478, REV. C01 * (Insert here, attaching additional pages if required, a list identifying all other Contract Documents e.g. supplementary conditions; information documents; specifications, giving a list of contents with section numbers and titles, number of pages and date; material finishing schedules; drawings, giving drawing number, title, date, revision date or mark; addenda, giving title, number, date) CCDC 2 – 2008 File 005213 2 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. ARTICLE A-4 CONTRACT PRICE 4.1 The Contract Price, which excludes Value Added Taxes, is: XXXXXXXXXXXXXXXX /100 dollars 4.2 Value Added Taxes (of 15 XXXXX.XX $ XXXX.XX $ XXXXX.XX %) payable by the Owner to the Contractor are: XXXXXXXXXXXXXXXX ________________________________________________________________ /100 dollars 4.3 $ Total amount payable by the Owner to the Contractor for the construction of the Work is: XXXXXXXXXXXXXXXX /100 dollars 4.4 These amounts shall be subject to adjustments as provided in the Contract Documents. 4.5 All amounts are in Canadian funds. ARTICLE A-5 PAYMENT 5.1 Subject to the provisions of the Contract Documents, and in accordance with legislation and statutory regulations respecting holdback percentages and, where such legislation or regulations do not exist or apply, subject to a holdback of TEN 10 percent ( %), the Owner shall: .1 make progress payments to the Contractor on account of the Contract Price when due in the amount certified by the Consultant together with such Value Added Taxes as may be applicable to such payments, and .2 upon Substantial Performance of the Work, pay to the Contractor the unpaid balance of the holdback amount when due together with such Value Added Taxes as may be applicable to such payment, and .3 upon the issuance of the final certificate for payment, pay to the Contractor the unpaid balance of the Contract Price when due together with such Value Added Taxes as may be applicable to such payment. 5.2 In the event of loss or damage occurring where payment becomes due under the property and boiler insurance policies, payments shall be made to the Contractor in accordance with the provisions of GC 11.1 – INSURANCE. 5.3 Interest .1 Should either party fail to make payments as they become due under the terms of the Contract or in an award by arbitration or court, interest at the following rates on such unpaid amounts shall also become due and payable until payment: (1) 2% per annum above the prime rate for the first 60 days. (2) 4% per annum above the prime rate after the first 60 days. Such interest shall be compounded on a monthly basis. The prime rate shall be the rate of interest quoted by BANK OF NOVA SCOTIA (Insert name of chartered lending institution whose prime rate is to be used) .2 for prime business loans as it may change from time to time. Interest shall apply at the rate and in the manner prescribed by paragraph 5.3.1 of this Article on the settlement amount of any claim in dispute that is resolved either pursuant to Part 8 of the General Conditions – DISPUTE RESOLUTION or otherwise, from the date the amount would have been due and payable under the Contract, had it not been in dispute, until the date it is paid. CCDC 2 – 2008 File 005213 3 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. ARTICLE A-6 RECEIPT OF AND ADDRESSES FOR NOTICES IN WRITING 6.1 Notices in Writing will be addressed to the recipient at the address set out below. The delivery of a Notice in Writing will be by hand, by courier, by prepaid first class mail, or by facsimile or other form of electronic communication during the transmission of which no indication of failure of receipt is communicated to the sender. A Notice in Writing delivered by one party in accordance with this Contract will be deemed to have been received by the other party on the date of delivery if delivered by hand or courier, or if sent by mail it shall be deemed to have been received five calendar days after the date on which it was mailed, provided that if either such day is not a Working Day, then the Notice in Writing shall be deemed to have been received on the Working Day next following such day. A Notice in Writing sent by facsimile or other form of electronic communication shall be deemed to have been received on the date of its transmission provided that if such day is not a Working Day or if it is received after the end of normal business hours on the date of its transmission at the place of receipt, then it shall be deemed to have been received at the opening of business at the place of receipt on the first Working Day next following the transmission thereof. An address for a party may be changed by Notice in Writing to the other party setting out the new address in accordance with this Article. Owner FUNDY OCEAN RESEARCH CENTER FOR ENERGY (FORCE) name of Owner* P.O. Box 2573, HALIFAX, NOVA SCOTIA B3J 3N5 address N/A frank.leblanc@fundyforce.ca (Frank LeBlanc) facsimile number email address Contractor XXXXXXXXXXXXXXXXXXXXXXXXXXXX name of Contractor* XXXXXXXXXXXXXXXXXXXXXXXXXXXX address 902-XXX-XXX facsimile number XXXXXX@XXXXX email address Consultant STRUM ENGINEERING ASSOCIATES LTD. name of Consultant* 80 EILEEN STUBBS AVE., DARTMOUTH, NOVA SCOTIA B3B 1Y6 address 902-468-1908 facsimile number r.mccarthy@strumengineering.ca (Richard McCarthy) email address * If it is intended that the notice must be received by a specific individual, that individual’s name shall be indicated. ARTICLE A-7 LANGUAGE OF THE CONTRACT 7.1 When the Contract Documents are prepared in both the English and French languages, it is agreed that in the event of any apparent discrepancy between the English and French versions, the # Complete this statement by striking out inapplicable term. 7.2 English / French # language shall prevail. This Agreement is drawn in English at the request of the parties hereto. La présente convention est rédigée en anglais à la demande des parties. CCDC 2 – 2008 File 005213 4 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. ARTICLE A-8 SUCCESSION 8.1 The Contract shall enure to the benefit of and be binding upon the parties hereto, their respective heirs, legal representatives, successors, and assigns. In witness whereof the parties hereto have executed this Agreement by the hands of their duly authorized representatives. SIGNED AND DELIVERED in the presence of: WITNESS OWNER FUNDY OCEAN RESEARCH CENTER FOR ENERGY (FORCE) name of owner signature signature name of person signing name and title of person signing signature signature name of person signing name and title of person signing WITNESS CONTRACTOR XXXXXXXXXXXXXXXXXXXXXXX name of Contractor signature signature name of person signing name and title of person signing signature signature name of person signing name and title of person signing N.B. Where legal jurisdiction, local practice or Owner or Contractor requirement calls for: (a) proof of authority to execute this document, attach such proof of authority in the form of a certified copy of a resolution naming the representative(s) authorized to sign the Agreement for and on behalf of the corporation or partnership; or (b) the affixing of a corporate seal, this Agreement should be properly sealed. CCDC 2 – 2008 File 005213 5 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. Standard Construction Document CCDC 2 – 2008 DEFINITIONS The following Definitions shall apply to all Contract Documents. 1. Change Directive A Change Directive is a written instruction prepared by the Consultant and signed by the Owner directing the Contractor to proceed with a change in the Work within the general scope of the Contract Documents prior to the Owner and the Contractor agreeing upon adjustments in the Contract Price and the Contract Time. 2. Change Order A Change Order is a written amendment to the Contract prepared by the Consultant and signed by the Owner and the Contractor stating their agreement upon: - a change in the Work; - the method of adjustment or the amount of the adjustment in the Contract Price, if any; and - the extent of the adjustment in the Contract Time, if any. 3. Construction Equipment Construction Equipment means all machinery and equipment, either operated or not operated, that is required for preparing, fabricating, conveying, erecting, or otherwise performing the Work but is not incorporated into the Work. 4. Consultant The Consultant is the person or entity engaged by the Owner and identified as such in the Agreement. The Consultant is the Architect, the Engineer or entity licensed to practise in the province or territory of the Place of the Work. The term Consultant means the Consultant or the Consultant's authorized representative. 5. Contract The Contract is the undertaking by the parties to perform their respective duties, responsibilities and obligations as prescribed in the Contract Documents and represents the entire agreement between the parties. 6. Contract Documents The Contract Documents consist of those documents listed in Article A-3 of the Agreement - CONTRACT DOCUMENTS and amendments agreed upon between the parties. 7. Contract Price The Contract Price is the amount stipulated in Article A-4 of the Agreement - CONTRACT PRICE. 8. Contract Time The Contract Time is the time stipulated in paragraph 1.3 of Article A-1 of the Agreement - THE WORK from commencement of the Work to Substantial Performance of the Work. 9. Contractor The Contractor is the person or entity identified as such in the Agreement. The term Contractor means the Contractor or the Contractor's authorized representative as designated to the Owner in writing. 10. Drawings The Drawings are the graphic and pictorial portions of the Contract Documents, wherever located and whenever issued, showing the design, location and dimensions of the Work, generally including plans, elevations, sections, details, and diagrams. 11. Notice in Writing A Notice in Writing, where identified in the Contract Documents, is a written communication between the parties or between them and the Consultant that is transmitted in accordance with the provisions of Article A-6 of the Agreement – RECEIPT OF AND ADDRESSES FOR NOTICES IN WRITING. 12. Owner The Owner is the person or entity identified as such in the Agreement. The term Owner means the Owner or the Owner's authorized agent or representative as designated to the Contractor in writing, but does not include the Consultant. 13. Place of the Work The Place of the Work is the designated site or location of the Work identified in the Contract Documents. 14. Product Product or Products means material, machinery, equipment, and fixtures forming the Work, but does not include Construction Equipment. CCDC 2 - 2008 File 007100 6 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. 15. Project The Project means the total construction contemplated of which the Work may be the whole or a part. 16. Provide Provide means to supply and install. 17. Shop Drawings Shop Drawings are drawings, diagrams, illustrations, schedules, performance charts, brochures, Product data, and other data which the Contractor provides to illustrate details of portions of the Work. 18. Specifications The Specifications are that portion of the Contract Documents, wherever located and whenever issued, consisting of the written requirements and standards for Products, systems, workmanship, quality, and the services necessary for the performance of the Work. 19. Subcontractor A Subcontractor is a person or entity having a direct contract with the Contractor to perform a part or parts of the Work at the Place of the Work. 20. Substantial Performance of the Work Substantial Performance of the Work is as defined in the lien legislation applicable to the Place of the Work. If such legislation is not in force or does not contain such definition, or if the Work is governed by the Civil Code of Quebec, Substantial Performance of the Work shall have been reached when the Work is ready for use or is being used for the purpose intended and is so certified by the Consultant. 21. Supplemental Instruction A Supplemental Instruction is an instruction, not involving adjustment in the Contract Price or Contract Time, in the form of Specifications, Drawings, schedules, samples, models or written instructions, consistent with the intent of the Contract Documents. It is to be issued by the Consultant to supplement the Contract Documents as required for the performance of the Work. 22. Supplier A Supplier is a person or entity having a direct contract with the Contractor to supply Products. 23. Temporary Work Temporary Work means temporary supports, structures, facilities, services, and other temporary items, excluding Construction Equipment, required for the execution of the Work but not incorporated into the Work. 24. Value Added Taxes Value Added Taxes means such sum as shall be levied upon the Contract Price by the Federal or any Provincial or Territorial Government and is computed as a percentage of the Contract Price and includes the Goods and Services Tax, the Quebec Sales Tax, the Harmonized Sales Tax, and any similar tax, the collection and payment of which have been imposed on the Contractor by the tax legislation. 25. Work The Work means the total construction and related services required by the Contract Documents. 26. Working Day Working Day means a day other than a Saturday, Sunday, statutory holiday, or statutory vacation day that is observed by the construction industry in the area of the Place of the Work. CCDC 2 - 2008 File 007100 7 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. Standard Construction Document CCDC 2 – 2008 GENERAL CONDITIONS OF THE STIPULATED PRICE CONTRACT PART 1 GENERAL PROVISIONS GC 1.1 CONTRACT DOCUMENTS 1.1.1 The intent of the Contract Documents is to include the labour, Products and services necessary for the performance of the Work by the Contractor in accordance with these documents. It is not intended, however, that the Contractor shall supply products or perform work not consistent with, not covered by, or not properly inferable from the Contract Documents. 1.1.2 Nothing contained in the Contract Documents shall create any contractual relationship between: .1 the Owner and a Subcontractor, a Supplier, or their agent, employee, or other person performing any portion of the Work. .2 the Consultant and the Contractor, a Subcontractor, a Supplier, or their agent, employee, or other person performing any portion of the Work. 1.1.3 The Contract Documents are complementary, and what is required by any one shall be as binding as if required by all. 1.1.4 Words and abbreviations which have well known technical or trade meanings are used in the Contract Documents in accordance with such recognized meanings. 1.1.5 References in the Contract Documents to the singular shall be considered to include the plural as the context requires. 1.1.6 Neither the organization of the Specifications nor the arrangement of Drawings shall control the Contractor in dividing the work among Subcontractors and Suppliers. 1.1.7 If there is a conflict within the Contract Documents: .1 the order of priority of documents, from highest to lowest, shall be − the Agreement between the Owner and the Contractor, − the Definitions, − Supplementary Conditions, − the General Conditions, − Division 1 of the Specifications, − technical Specifications, − material and finishing schedules, − the Drawings. .2 Drawings of larger scale shall govern over those of smaller scale of the same date. .3 dimensions shown on Drawings shall govern over dimensions scaled from Drawings. .4 later dated documents shall govern over earlier documents of the same type. 1.1.8 The Owner shall provide the Contractor, without charge, sufficient copies of the Contract Documents to perform the Work. 1.1.9 Specifications, Drawings, models, and copies thereof furnished by the Consultant are and shall remain the Consultant's property, with the exception of the signed Contract sets, which shall belong to each party to the Contract. All Specifications, Drawings and models furnished by the Consultant are to be used only with respect to the Work and are not to be used on other work. These Specifications, Drawings and models are not to be copied or altered in any manner without the written authorization of the Consultant. 1.1.10 Models furnished by the Contractor at the Owner's expense are the property of the Owner. GC 1.2 LAW OF THE CONTRACT 1.2.1 The law of the Place of the Work shall govern the interpretation of the Contract. GC 1.3 RIGHTS AND REMEDIES 1.3.1 Except as expressly provided in the Contract Documents, the duties and obligations imposed by the Contract Documents and the rights and remedies available thereunder shall be in addition to and not a limitation of any duties, obligations, rights, and remedies otherwise imposed or available by law. 1.3.2 No action or failure to act by the Owner, Consultant or Contractor shall constitute a waiver of any right or duty afforded any of them under the Contract, nor shall any such action or failure to act constitute an approval of or acquiescence in any breach thereunder, except as may be specifically agreed in writing. CCDC 2 – 2008 File 007213 8 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. GC 1.4 ASSIGNMENT 1.4.1 Neither party to the Contract shall assign the Contract or a portion thereof without the written consent of the other, which consent shall not be unreasonably withheld. PART 2 ADMINISTRATION OF THE CONTRACT GC 2.1 AUTHORITY OF THE CONSULTANT 2.1.1 The Consultant will have authority to act on behalf of the Owner only to the extent provided in the Contract Documents, unless otherwise modified by written agreement as provided in paragraph 2.1.2. 2.1.2 The duties, responsibilities and limitations of authority of the Consultant as set forth in the Contract Documents shall be modified or extended only with the written consent of the Owner, the Contractor and the Consultant. 2.1.3 If the Consultant's employment is terminated, the Owner shall immediately appoint or reappoint a Consultant against whom the Contractor makes no reasonable objection and whose status under the Contract Documents shall be that of the former Consultant. GC 2.2 ROLE OF THE CONSULTANT 2.2.1 The Consultant will provide administration of the Contract as described in the Contract Documents. 2.2.2 The Consultant will visit the Place of the Work at intervals appropriate to the progress of construction to become familiar with the progress and quality of the work and to determine if the Work is proceeding in general conformity with the Contract Documents. 2.2.3 If the Owner and the Consultant agree, the Consultant will provide at the Place of the Work, one or more project representatives to assist in carrying out the Consultant's responsibilities. The duties, responsibilities and limitations of authority of such project representatives shall be as set forth in writing to the Contractor. 2.2.4 The Consultant will promptly inform the Owner of the date of receipt of the Contractor’s applications for payment as provided in paragraph 5.3.1.1 of GC 5.3 – PROGRESS PAYMENT. 2.2.5 Based on the Consultant's observations and evaluation of the Contractor's applications for payment, the Consultant will determine the amounts owing to the Contractor under the Contract and will issue certificates for payment as provided in Article A-5 of the Agreement - PAYMENT, GC 5.3 - PROGRESS PAYMENT and GC 5.7 - FINAL PAYMENT. 2.2.6 The Consultant will not be responsible for and will not have control, charge or supervision of construction means, methods, techniques, sequences, or procedures, or for safety precautions and programs required in connection with the Work in accordance with the applicable construction safety legislation, other regulations or general construction practice. The Consultant will not be responsible for the Contractor's failure to carry out the Work in accordance with the Contract Documents. The Consultant will not have control over, charge of or be responsible for the acts or omissions of the Contractor, Subcontractors, Suppliers, or their agents, employees, or any other persons performing portions of the Work. 2.2.7 Except with respect to GC 5.1 - FINANCING INFORMATION REQUIRED OF THE OWNER, the Consultant will be, in the first instance, the interpreter of the requirements of the Contract Documents. 2.2.8 Matters in question relating to the performance of the Work or the interpretation of the Contract Documents shall be initially referred in writing to the Consultant by the party raising the question for interpretations and findings and copied to the other party. 2.2.9 Interpretations and findings of the Consultant shall be consistent with the intent of the Contract Documents. In making such interpretations and findings the Consultant will not show partiality to either the Owner or the Contractor. 2.2.10 The Consultant’s interpretations and findings will be given in writing to the parties within a reasonable time. 2.2.11 With respect to claims for a change in Contract Price, the Consultant will make findings as set out in GC 6.6 – CLAIMS FOR A CHANGE IN CONTRACT PRICE. 2.2.12 The Consultant will have authority to reject work which in the Consultant's opinion does not conform to the requirements of the Contract Documents. Whenever the Consultant considers it necessary or advisable, the Consultant will have authority to require inspection or testing of work, whether or not such work is fabricated, installed or completed. However, neither the authority of the Consultant to act nor any decision either to exercise or not to exercise such authority shall give rise to any duty or responsibility of the Consultant to the Contractor, Subcontractors, Suppliers, or their agents, employees, or other persons performing any of the Work. CCDC 2 – 2008 File 007213 9 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. 2.2.13 During the progress of the Work the Consultant will furnish Supplemental Instructions to the Contractor with reasonable promptness or in accordance with a schedule for such instructions agreed to by the Consultant and the Contractor. 2.2.14 The Consultant will review and take appropriate action upon Shop Drawings, samples and other Contractor’s submittals, in accordance with the Contract Documents. 2.2.15 The Consultant will prepare Change Orders and Change Directives as provided in GC 6.2 - CHANGE ORDER and GC 6.3 - CHANGE DIRECTIVE. 2.2.16 The Consultant will conduct reviews of the Work to determine the date of Substantial Performance of the Work as provided in GC 5.4 - SUBSTANTIAL PERFORMANCE OF THE WORK. 2.2.17 All certificates issued by the Consultant will be to the best of the Consultant's knowledge, information and belief. By issuing any certificate, the Consultant does not guarantee the Work is correct or complete. 2.2.18 The Consultant will receive and review written warranties and related documents required by the Contract and provided by the Contractor and will forward such warranties and documents to the Owner for the Owner's acceptance. GC 2.3 REVIEW AND INSPECTION OF THE WORK 2.3.1 The Owner and the Consultant shall have access to the Work at all times. The Contractor shall provide sufficient, safe and proper facilities at all times for the review of the Work by the Consultant and the inspection of the Work by authorized agencies. If parts of the Work are in preparation at locations other than the Place of the Work, the Owner and the Consultant shall be given access to such work whenever it is in progress. 2.3.2 If work is designated for tests, inspections or approvals in the Contract Documents, or by the Consultant's instructions, or by the laws or ordinances of the Place of the Work, the Contractor shall give the Consultant reasonable notification of when the work will be ready for review and inspection. The Contractor shall arrange for and shall give the Consultant reasonable notification of the date and time of inspections by other authorities. 2.3.3 The Contractor shall furnish promptly to the Consultant two copies of certificates and inspection reports relating to the Work. 2.3.4 If the Contractor covers, or permits to be covered, work that has been designated for special tests, inspections or approvals before such special tests, inspections or approvals are made, given or completed, the Contractor shall, if so directed, uncover such work, have the inspections or tests satisfactorily completed, and make good covering work at the Contractor's expense. 2.3.5 The Consultant may order any portion or portions of the Work to be examined to confirm that such work is in accordance with the requirements of the Contract Documents. If the work is not in accordance with the requirements of the Contract Documents, the Contractor shall correct the work and pay the cost of examination and correction. If the work is in accordance with the requirements of the Contract Documents, the Owner shall pay the cost of examination and restoration. 2.3.6 The Contractor shall pay the cost of making any test or inspection, including the cost of samples required for such test or inspection, if such test or inspection is designated in the Contract Documents to be performed by the Contractor or is designated by the laws or ordinances applicable to the Place of the Work. 2.3.7 The Contractor shall pay the cost of samples required for any test or inspection to be performed by the Consultant or the Owner if such test or inspection is designated in the Contract Documents. GC 2.4 DEFECTIVE WORK 2.4.1 The Contractor shall promptly correct defective work that has been rejected by the Consultant as failing to conform to the Contract Documents whether or not the defective work has been incorporated in the Work and whether or not the defect is the result of poor workmanship, use of defective products or damage through carelessness or other act or omission of the Contractor. 2.4.2 The Contractor shall make good promptly other contractors' work destroyed or damaged by such corrections at the Contractor's expense. 2.4.3 If in the opinion of the Consultant it is not expedient to correct defective work or work not performed as provided in the Contract Documents, the Owner may deduct from the amount otherwise due to the Contractor the difference in value between the work as performed and that called for by the Contract Documents. If the Owner and the Contractor do not agree on the difference in value, they shall refer the matter to the Consultant for a determination. CCDC 2 – 2008 File 007213 10 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. PART 3 EXECUTION OF THE WORK GC 3.1 CONTROL OF THE WORK 3.1.1 The Contractor shall have total control of the Work and shall effectively direct and supervise the Work so as to ensure conformity with the Contract Documents. 3.1.2 The Contractor shall be solely responsible for construction means, methods, techniques, sequences, and procedures and for co-ordinating the various parts of the Work under the Contract. GC 3.2 CONSTRUCTION BY OWNER OR OTHER CONTRACTORS 3.2.1 The Owner reserves the right to award separate contracts in connection with other parts of the Project to other contractors and to perform work with own forces. 3.2.2 When separate contracts are awarded for other parts of the Project, or when work is performed by the Owner's own forces, the Owner shall: .1 provide for the co-ordination of the activities and work of other contractors and Owner's own forces with the Work of the Contract; .2 assume overall responsibility for compliance with the applicable health and construction safety legislation at the Place of the Work; .3 enter into separate contracts with other contractors under conditions of contract which are compatible with the conditions of the Contract; .4 ensure that insurance coverage is provided to the same requirements as are called for in GC 11.1 - INSURANCE and coordinate such insurance with the insurance coverage of the Contractor as it affects the Work; and .5 take all reasonable precautions to avoid labour disputes or other disputes on the Project arising from the work of other contractors or the Owner's own forces. 3.2.3 When separate contracts are awarded for other parts of the Project, or when work is performed by the Owner's own forces, the Contractor shall: .1 afford the Owner and other contractors reasonable opportunity to store their products and execute their work; .2 cooperate with other contractors and the Owner in reviewing their construction schedules; and .3 promptly report to the Consultant in writing any apparent deficiencies in the work of other contractors or of the Owner's own forces, where such work affects the proper execution of any portion of the Work, prior to proceeding with that portion of the Work. 3.2.4 Where the Contract Documents identify work to be performed by other contractors or the Owner’s own forces, the Contractor shall co-ordinate and schedule the Work with the work of other contractors and the Owner’s own forces as specified in the Contract Documents. 3.2.5 Where a change in the Work is required as a result of the co-ordination and integration of the work of other contractors or Owner's own forces with the Work, the changes shall be authorized and valued as provided in GC 6.1 – OWNER’S RIGHT TO MAKE CHANGES, GC 6.2 - CHANGE ORDER and GC 6.3 - CHANGE DIRECTIVE. 3.2.6 Disputes and other matters in question between the Contractor and other contractors shall be dealt with as provided in Part 8 of the General Conditions - DISPUTE RESOLUTION provided the other contractors have reciprocal obligations. The Contractor shall be deemed to have consented to arbitration of any dispute with any other contractor whose contract with the Owner contains a similar agreement to arbitrate. GC 3.3 TEMPORARY WORK 3.3.1 The Contractor shall have the sole responsibility for the design, erection, operation, maintenance, and removal of Temporary Work. 3.3.2 The Contractor shall engage and pay for registered professional engineering personnel skilled in the appropriate disciplines to perform those functions referred to in paragraph 3.3.1 where required by law or by the Contract Documents and in all cases where such Temporary Work is of such a nature that professional engineering skill is required to produce safe and satisfactory results. CCDC 2 – 2008 File 007213 11 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. 3.3.3 Notwithstanding the provisions of GC 3.1 - CONTROL OF THE WORK, paragraphs 3.3.1 and 3.3.2 or provisions to the contrary elsewhere in the Contract Documents where such Contract Documents include designs for Temporary Work or specify a method of construction in whole or in part, such designs or methods of construction shall be considered to be part of the design of the Work and the Contractor shall not be held responsible for that part of the design or the specified method of construction. The Contractor shall, however, be responsible for the execution of such design or specified method of construction in the same manner as for the execution of the Work. GC 3.4 DOCUMENT REVIEW 3.4.1 The Contractor shall review the Contract Documents and shall report promptly to the Consultant any error, inconsistency or omission the Contractor may discover. Such review by the Contractor shall be to the best of the Contractor's knowledge, information and belief and in making such review the Contractor does not assume any responsibility to the Owner or the Consultant for the accuracy of the review. The Contractor shall not be liable for damage or costs resulting from such errors, inconsistencies or omissions in the Contract Documents, which the Contractor did not discover. If the Contractor does discover any error, inconsistency or omission in the Contract Documents, the Contractor shall not proceed with the work affected until the Contractor has received corrected or missing information from the Consultant. GC 3.5 CONSTRUCTION SCHEDULE 3.5.1 The Contractor shall: .1 prepare and submit to the Owner and the Consultant prior to the first application for payment, a construction schedule that indicates the timing of the major activities of the Work and provides sufficient detail of the critical events and their inter-relationship to demonstrate the Work will be performed in conformity with the Contract Time; .2 monitor the progress of the Work relative to the construction schedule and update the schedule on a monthly basis or as stipulated by the Contract Documents; and .3 advise the Consultant of any revisions required to the schedule as the result of extensions of the Contract Time as provided in Part 6 of the General Conditions - CHANGES IN THE WORK. GC 3.6 SUPERVISION 3.6.1 The Contractor shall provide all necessary supervision and appoint a competent representative who shall be in attendance at the Place of the Work while work is being performed. The appointed representative shall not be changed except for valid reason. 3.6.2 The appointed representative shall represent the Contractor at the Place of the Work. Information and instructions provided by the Consultant to the Contractor’s appointed representative shall be deemed to have been received by the Contractor, except with respect to Article A-6 of the Agreement – RECEIPT OF AND ADDRESSES FOR NOTICES IN WRITING. GC 3.7 SUBCONTRACTORS AND SUPPLIERS 3.7.1 The Contractor shall preserve and protect the rights of the parties under the Contract with respect to work to be performed under subcontract, and shall: .1 enter into contracts or written agreements with Subcontractors and Suppliers to require them to perform their work as provided in the Contract Documents; .2 incorporate the terms and conditions of the Contract Documents into all contracts or written agreements with Subcontractors and Suppliers; and .3 be as fully responsible to the Owner for acts and omissions of Subcontractors, Suppliers and of persons directly or indirectly employed by them as for acts and omissions of persons directly employed by the Contractor. 3.7.2 The Contractor shall indicate in writing, if requested by the Owner, those Subcontractors or Suppliers whose bids have been received by the Contractor which the Contractor would be prepared to accept for the performance of a portion of the Work. Should the Owner not object before signing the Contract, the Contractor shall employ those Subcontractors or Suppliers so identified by the Contractor in writing for the performance of that portion of the Work to which their bid applies. 3.7.3 The Owner may, for reasonable cause, at any time before the Owner has signed the Contract, object to the use of a proposed Subcontractor or Supplier and require the Contractor to employ one of the other subcontract bidders. 3.7.4 If the Owner requires the Contractor to change a proposed Subcontractor or Supplier, the Contract Price and Contract Time shall be adjusted by the differences occasioned by such required change. CCDC 2 – 2008 File 007213 12 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. 3.7.5 The Contractor shall not be required to employ as a Subcontractor or Supplier, a person or firm to which the Contractor may reasonably object. 3.7.6 The Owner, through the Consultant, may provide to a Subcontractor or Supplier information as to the percentage of the Subcontractor's or Supplier's work which has been certified for payment. GC 3.8 LABOUR AND PRODUCTS 3.8.1 The Contractor shall provide and pay for labour, Products, tools, Construction Equipment, water, heat, light, power, transportation, and other facilities and services necessary for the performance of the Work in accordance with the Contract. 3.8.2 Unless otherwise specified in the Contract Documents, Products provided shall be new. Products which are not specified shall be of a quality consistent with those specified and their use acceptable to the Consultant. 3.8.3 The Contractor shall maintain good order and discipline among the Contractor's employees engaged on the Work and shall not employ on the Work anyone not skilled in the tasks assigned. GC 3.9 DOCUMENTS AT THE SITE 3.9.1 The Contractor shall keep one copy of current Contract Documents, submittals, reports, and records of meetings at the Place of the Work, in good order and available to the Owner and the Consultant. GC 3.10 SHOP DRAWINGS 3.10.1 The Contractor shall provide Shop Drawings as required in the Contract Documents. 3.10.2 The Contractor shall provide Shop Drawings to the Consultant to review in orderly sequence and sufficiently in advance so as to cause no delay in the Work or in the work of other contractors. 3.10.3 Upon request of the Contractor or the Consultant, they shall jointly prepare a schedule of the dates for provision, review and return of Shop Drawings. 3.10.4 The Contractor shall provide Shop Drawings in the form specified, or if not specified, as directed by the Consultant. 3.10.5 Shop Drawings provided by the Contractor to the Consultant shall indicate by stamp, date and signature of the person responsible for the review that the Contractor has reviewed each one of them. 3.10.6 The Consultant's review is for conformity to the design concept and for general arrangement only. 3.10.7 Shop Drawings which require approval of any legally constituted authority having jurisdiction shall be provided to such authority by the Contractor for approval. 3.10.8 The Contractor shall review all Shop Drawings before providing them to the Consultant. The Contractor represents by this review that: .1 the Contractor has determined and verified all applicable field measurements, field construction conditions, Product requirements, catalogue numbers and similar data, or will do so, and .2 the Contractor has checked and co-ordinated each Shop Drawing with the requirements of the Work and of the Contract Documents. 3.10.9 At the time of providing Shop Drawings, the Contractor shall expressly advise the Consultant in writing of any deviations in a Shop Drawing from the requirements of the Contract Documents. The Consultant shall indicate the acceptance or rejection of such deviation expressly in writing. 3.10.10 The Consultant's review shall not relieve the Contractor of responsibility for errors or omissions in the Shop Drawings or for meeting all requirements of the Contract Documents. 3.10.11 The Contractor shall provide revised Shop Drawings to correct those which the Consultant rejects as inconsistent with the Contract Documents, unless otherwise directed by the Consultant. The Contractor shall notify the Consultant in writing of any revisions to the Shop Drawings other than those requested by the Consultant. 3.10.12 The Consultant will review and return Shop Drawings in accordance with the schedule agreed upon, or, in the absence of such schedule, with reasonable promptness so as to cause no delay in the performance of the Work. CCDC 2 – 2008 File 007213 13 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. GC 3.11 USE OF THE WORK 3.11.1 The Contractor shall confine Construction Equipment, Temporary Work, storage of Products, waste products and debris, and operations of employees and Subcontractors to limits indicated by laws, ordinances, permits, or the Contract Documents and shall not unreasonably encumber the Place of the Work. 3.11.2 The Contractor shall not load or permit to be loaded any part of the Work with a weight or force that will endanger the safety of the Work. GC 3.12 CUTTING AND REMEDIAL WORK 3.12.1 The Contractor shall perform the cutting and remedial work required to make the affected parts of the Work come together properly. 3.12.2 The Contractor shall co-ordinate the Work to ensure that the cutting and remedial work is kept to a minimum. 3.12.3 Should the Owner, the Consultant, other contractors or anyone employed by them be responsible for ill-timed work necessitating cutting or remedial work to be performed, the cost of such cutting or remedial work shall be valued as provided in GC 6.1 – OWNER’S RIGHT TO MAKE CHANGES, GC 6.2 - CHANGE ORDER and GC 6.3 - CHANGE DIRECTIVE. 3.12.4 Cutting and remedial work shall be performed by specialists familiar with the Products affected and shall be performed in a manner to neither damage nor endanger the Work. GC 3.13 CLEANUP 3.13.1 The Contractor shall maintain the Work in a safe and tidy condition and free from the accumulation of waste products and debris, other than that caused by the Owner, other contractors or their employees. 3.13.2 Before applying for Substantial Performance of the Work as provided in GC 5.4 – SUBSTANTIAL PERFORMANCE OF THE WORK, the Contractor shall remove waste products and debris, other than that resulting from the work of the Owner, other contractors or their employees, and shall leave the Place of the Work clean and suitable for use or occupancy by the Owner. The Contractor shall remove products, tools, Construction Equipment, and Temporary Work not required for the performance of the remaining work. 3.13.3 Prior to application for the final payment, the Contractor shall remove any remaining products, tools, Construction Equipment, Temporary Work, and waste products and debris, other than those resulting from the work of the Owner, other contractors or their employees. PART 4 ALLOWANCES GC 4.1 CASH ALLOWANCES 4.1.1 The Contract Price includes the cash allowances, if any, stated in the Contract Documents. The scope of work or costs included in such cash allowances shall be as described in the Contract Documents. 4.1.2 The Contract Price, and not the cash allowances, includes the Contractor's overhead and profit in connection with such cash allowances. 4.1.3 Expenditures under cash allowances shall be authorized by the Owner through the Consultant. 4.1.4 Where the actual cost of the Work under any cash allowance exceeds the amount of the allowance, the Contractor shall be compensated for the excess incurred and substantiated plus an amount for overhead and profit on the excess as set out in the Contract Documents. Where the actual cost of the Work under any cash allowance is less than the amount of the allowance, the Owner shall be credited for the unexpended portion of the cash allowance, but not for the Contractor’s overhead and profit on such amount. Multiple cash allowances shall not be combined for the purpose of calculating the foregoing. 4.1.5 The Contract Price shall be adjusted by Change Order to provide for any difference between the amount of each cash allowance and the actual cost of the work under that cash allowance. 4.1.6 The value of the work performed under a cash allowance is eligible to be included in progress payments. 4.1.7 The Contractor and the Consultant shall jointly prepare a schedule that shows when the Consultant and Owner must authorize ordering of items called for under cash allowances to avoid delaying the progress of the Work. CCDC 2 – 2008 File 007213 14 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions.