ADDENDUM NO. 3 School Renovation Project Montezuma Community Schools January 4, 2013 ARCHITECT: Design Alliance, Inc. PROJECT NO: 211032 BID DATE: 1.10.2013 ________ This Addendum No. 3 is issued this date, prior to receiving bids, and shall supplement, amend and become part of the contract documents. Bids shall be based on these modifications. SPECIFICATIONS Architectural Items: Item No. 1 Section 00 7300 Supplementary Conditions and Addendum #2 Item # 5 Add the following to the existing sentence for Article 11.3.1.3: Owner’s deductible is $1,000. Item No. 2 Section 01 1000 Summary Change Article 1.03 H 2 to read “If existing High School Boilers can be removed without modifications to existing building openings, then remove boiler undamaged and place on Owner’s truck at a mutually acceptable time. If modifications are required, then Contractor shall have option of either, 1. making said modifications at Contractor’s expense and then removing boiler and placing on Owner’s truck, or 2. otherwise removing/disposing of existing boilers at Contractor expense.” Item No. 3 Section 03 3000 Cast-in-Place Concrete Add the following to Article 2.10 A: 4. Sidewalks and Paving: See Civil Notes. If not indicated there, use 4,000 psi air entrained concrete. Item No. 4 Section 07 4213 Metal Wall Panels Change the following in Article 2.01 A 1. to read, “Centria; IW Series” in lieu of, “Centria; Product Formawall.” Item No. 5 Section 09 6813 Tile Carpeting Replace Article 2.01 with the following: A. Bigelow; Elemental Factor, Heat, Solve, Structured Motion B. J+J Invision; City Blocks, Emerge, Evolve, Impact C. Lees; Brain Power, By the Book D. Patcraft; Idea, Speak in Color, Vivid, Vim E. Philadelphia Queen; Fuse, Unify F. Other Acceptable Manufacturers: 1. Substitutions: See Section 01 6000 – Product Requirements. Change Article 2.02 A 2. to read, “24x24 inch,” in lieu of, “18x36 inch.” Item No. 6 Section 09 9000 Painting and Coating Change Article 1.01 C to read, “Scope: Finish all interior and exterior surfaces exposed to view where indicated in the Room Finish Schedule on Sheet A4.1, unless fully factory-finished and unless otherwise indicated, including the following:” Item No. 7 Section 10 1400 Signage Change Article 2.01 A 1. to read, “…Pacific ADA manufacturers standard sizes.” in lieu of, “…Pacific ADA 9”x9”.” Remove Article 2.01 B. Change Article 2.01 C 1. to read, “MUTCD standard signage” in lieu of, “ Pacific 12” wide x 12” tall.” Change Article 2.01 C 1. to read, “Provide 2 Stop Signs.” In lieu of, “Provide Stop Sign.” Change Article 2.01 D 1. to read, “MUTCD standard signage” in lieu of, “Pacific 12” wide x 18” tall.” Add Article 2.01 E, to read: E. Exterior Do Not Enter Signs: 1. A.S.I Sign Systems: MUTCD standard signage. Curved post mount. 2. Other acceptable manufacturers: a. Best Sign Systems, Inc: www.bestsigns.com b. Mohawk Sign Systems, Inc: www.mohawksign.com c. Substitutions: See Section 01 6000 – Product Requirements Add Article 2.01 f, to read: E. Exterior One-Way Signs: 1. A.S.I Sign Systems: MUTCD standard signage. Curved post mount. 2. Other acceptable manufacturers: a. Best Sign Systems, Inc: www.bestsigns.com b. Mohawk Sign Systems, Inc: www.mohawksign.com c. Substitutions: See Section 01 6000 – Product Requirements Add the following to existing Article 2.03 B, “Basis for design Pacific Interiors 9.5”x9”.” Add the following to existing Article 2.03 C, “Basis for design Pacific Interiors 7.25”x6”.” Add the following to existing Article 2.03 D, “Basis for design Pacific Interiors 8.75”x9”.” Add the following to existing Article 2.03 E, “Basis for design Pacific Interiors 9.5”x9”.” Item No. 8 Section 31 2323 Fill Make changes as follows: Change Article 3.04 E 1. to read, “Use structural fill – granular or structural fill – subsoil.” Change Article 3.04 E 1 a. to read, “Depth: See plan sheets C2.1 and C3.1” Item No. 9 The following manufacturers are approved as substitute products of the named Base Bid manufacturer(s). Approval is contingent upon manufacturers fulfilling all specification requirements, tangible and intangible, equally as well or better then specified product. References/Item Manufacturer/Supplier Section 03 3000 – Cast-In-Place Concrete (2.06 C) Section 03 3000 – Cast-In-Place Concrete (2.07 A) Section 03 5400 - Cast Underlayment (2.01 B) Section 04 7200 – Cast Stone Masonry Section 07 2100 – Thermal Insulation (2.02 A) Section 07 2100 – Thermal Insulation (2.02 A) Section 07 2500 – Weather Barriers (2.02 A) Section 07 2500 – Weather Barriers (2.02 A) Section 07 2500 – Weather Barriers (2.02 A) Section 07 2500 – Weather Barriers (2.02 A) Section 07 2500 – Weather Barriers (2.02 A) Section 07 2500 – Weather Barriers (2.02 A) Section 07 9005 – Joint Sealers (2.02 A) Section 07 9005 – Joint Sealers (2.02 E) Section 08 4500 – Translucent Wall Assemblies Section 08 4500 – Door Hardware (2.03 A) Section 08 7100 – Door Hardware (2.09 A) Section 08 7100 – Door Hardware (2.09 A) Section 08 8000 – Aluminum Windows Section 09 3000 – Tiling Section 09 3000 – Tiling Section 09 6813 – Tile Carpeting Section 10 2113.19 – Plastic Toilet Compartments Sika Corp.; Sikadur 42 SpecChem Acrylic Bonder SpecChem Spec Flow Mark Stone, LLC DiversiFoam CertiFoam ACH Foam Technologies Poly Wall AirLok Flex Henry Air-Bloc 06 WB BASF - Enershield-I Poly Wall AirLok Flex TK–AirMax 2102NonPerm TK-AirMax 2103NonP WB SikaFlex 2c NS EZ Mix SikaFlex 1c SL US Daylighting – SF8 McKinney Besam AES – SW100 Record USA Series 8100 Oldcastle – Signature 3¼” Atlas Concorde Sark Tile, Inc. J+J Invision General Partitions DRAWINGS Item No. 10 Drawing PH1.2 Detail #5 Temporary Division Wall Change note to read, “5/8” Plywood – Paint” in lieu of, “5/8” Gypsum Board”. Add note, “See General Construction Notes on Sheet A1.0” Item No. 11 Drawing A1.1 Vestibule – 095: Delete window type tag 30. That type is not included in the scope of work. Item No. 12 Drawing A1.2 Keynotes on south elevation walls of rooms 065, 067 and 069 should read A2.09, A2.10 and A2.11 in lieu of A2.07, A2.08 and A2.09. Keynote A2.07 should remain as indicated at interior. Keynotes should match rooms 071 and 073 on Sheet A1.1. Item No. 13 Drawings A2.1, A2.2, A2.3, A2.4 and A2.5 Add General Ceiling Note as follows: “Where light fixtures are removed and/or replaced in hard ceilings, patch and paint to match adjacent. Locations include, but are not limited to, display and trophy cases.” Item No. 14 Drawing A2.5 Smoke Vents in Stage 093 ceiling shall be 4’x8’. Item No. 15 Drawing A4.1 Room Finish Schedule: Make the following changes: Computer Lab 059: Floor finish – VCT, Comments – Note 2 Office 083: Floor finish – VCT, Comments – Note 2 AD Office 155: Floor finish – Carpet Room Finish Legend: Add the following: SDT Static Dissipative Tile Details #12 and #13 - Window Type G Change casement windows to awning windows that project out. Layout to match Elevation #8 on Sheet A5.1. Item No. 16 Drawing A8.1 Detail #13 – Art 097 Change note to read, “Sink and Solid Surface Countertop & Backsplash” in lieu of, “Sink and P.Lam Countertop & Backsplash”. Detail #25 – Accessory Legend Switch AC-7 and AC-8 so that AC-7 reads, “Sanitary Napkin Disposal” and AC-8 reads, “Sanitary Napkin Dispenser.” Structural Items: DRAWINGS Item No. 17 Drawing S1.2 – 1/S1.2 Adjust Plan 1 Title Bar Notes to read thus: “- See Mechanical drawings for additional location and size information. - See Dtl. D1/S5.1 for typical angle frame notes, welds, and steel angle frame member sizes fro framing not otherwise specified. - See Dtl. E2/S5.1 for existing steel joist reinforcement where the angle frame connection is greater than 4” from the existing joist panel point. Field coordinate and verify locations, quantities, fits, dimensions, etc.” Item No. 18 Drawing S1.2 – 2/S1.2 The angles 6x4 shall extend fully between the existing 48L20 joist. Item No. 19 Drawing S1.2 – 8/S1.2 Move the note “For angle frame welds – see Dtl. D1/S5.1” below the title line. “L-4x3…” shall read: “L-4x3x1/4 LLV” Item No. 20 Drawing S5.1 – D1/S5.1 - Delete “0” at Typ. Weld notation. - Add the following note after “Typ.” at the weld sign: “Field weld as required; Provide fire watch protection and protect the existing construction from fire.” - Add the following note to the typical detail notes at the bottom of the detail reading thus: “The vertical face of the vertical angle leg’s cope shall be located less than a ½” from the edge of the existing supporting steel member; as required, carefully notch or peal back deck so as to facilitate connection.” Mechanical/Electrical/Plumbing Items: SPECIFICATIONS Item No. 21 General Clarification – Warranties a. All warranties shall start at the date of substantial completion for the last phase of construction. Provide extended warranties on equipment installed in earlier phases as required to coincide warranty start dates with the final phase substantial completion date. Item No. 22 Section 22 1005 – Plumbing Piping a. Article 2.04 – Add: Joints: Grooved mechanical couplings for copper piping larger than 2-inch. Victaulic, Gruvloc or engineer approved equivalent. Item No. 23 Section 23 0713 – Duct Insulation a. Article 2.03 Glass Fiber, Rigid, B, 4. Maximum Density shall be 3.0 lb/cu.ft. in lieu of 8.0 lb/cu.ft. b. Article 3.03 Schedules, I, 1. Two layers of 1-1/2” fire rated wrap may be used at the contractor’s option to achieve the required 2-hour rating. Item No. 24 Section 23 8125 – Computer Room Air Conditioners – Ceiling Mounted a. Eliminate Article K, Hot Gas Reheat. This will not be required. Item No. 25 Section 26 2416 – Panelboards a. Article 2.05.A.2.b – Change to: Series Rated Systems: Provide circuit breakers listed in combination with upstream devices to provide interrupting rating not less than the available short circuit current rating and NFPA requirements. Item No. 26 Section 26 0501 – Minor Electrical Demolition b. Article 3.03 – Add: K. Contractor is responsible for proper removal and disposal of lamps and ballasts including all associated recycling costs. Proof of disposal shall be submitted for review. Item No. 27 The following manufacturers are approved as substitute products of the named Base Bid manufacturer(s). Approval is contingent upon manufacturers fulfilling all specification requirements, tangible and intangible, equally as well or better then specified product. References/Item Manufacturer/Supplier Section 23 0516 – Flexible Connectors Section 23 0923 – Direct Digital Control System Section 23 2113.33 – Well Drilling Contractor Section 23 2113.33 – Geothermal Vault Wheatley American Auto-Matrix Shawver Well Company KWH Pipe, ISCO Section 23 2114 – Flow Controls and Hose Kits Section 23 2114 – Air Separator Section 23 2114 – Relief Valves Section 23 2123 – Base Mounted Pumps Section 23 3300 – Fire/Smoke Dampers Section 23 3300 – Flow Measuring Stations Section 23 3319 – Duct Silencers Section 23 3423 – Roof Exhausters Section 23 3700 – Fabric Air Dispersion Duct Section 23 3813 – Kitchen Hood Section 23 7413 – Make Up Air Unit (MUA-1) Section 23 7223 – Energy Recovery Ventilator Section 23 8216 – Electric Coils Section 26 2413 – Power Monitoring Panel Section 26 5100 – Interior Lighting – Type F2 Section 26 5100 – Interior Lighting – Type F2A Section 26 5100 – Interior Lighting – Type F3 Section 26 5100 – Interior Lighting – Type F4 Section 26 5100 – Interior Lighting – Type F5 Section 26 5100 – Interior Lighting – Type F6 Section 26 5100 – Interior Lighting – Type F7 Section 26 5100 – Interior Lighting – Type F7A Section 26 5100 – Interior Lighting – Type F7B Section 26 5100 – Interior Lighting – Type F7F Section 26 5100 – Interior Lighting – Type F8 Section 26 5100 – Interior Lighting – Type F9 Section 26 5100 – Interior Lighting – Type F9A Section 26 5100 – Interior Lighting – Type F9B Section 26 5100 – Interior Lighting – Type F9C Section 26 5100 – Interior Lighting – Type F9D Section 26 5100 – Interior Lighting – Type F9F Section 26 5100 – Interior Lighting – Type F9G Section 26 5100 – Interior Lighting – Type F9H Section 26 5100 – Interior Lighting – Type F10 Section 26 5100 – Interior Lighting – Type F11 Section 26 5100 – Interior Lighting – Type F11A Section 26 5100 – Interior Lighting – Type F11B Section 26 5100 – Interior Lighting – Type F11C Section 26 5100 – Interior Lighting – Type F12 Section 26 5100 – Interior Lighting – Type F12A Section 26 5100 – Interior Lighting – Type F13 Section 26 5100 – Interior Lighting – Type F15 Section 26 5100 – Interior Lighting – Type F15A Flow Design Armstrong Conbraco Armstrong Pottorff, Air Balance United Enertech Commercial Accoustics, Vibro-Acoustics Soler&Palau KE Fibertec Kees Venmar Venmar (1) Qmark GE EPM9650 Lumax Lumax Lumax Lumax Lumax Metalux Lightolier, Alera AL, Picasso Lightolier, Alera AL, Picasso Lightolier, Alera AL, Picasso Lightolier, Alera AL, Picasso Lightolier, Kenall, Alkco Corelite, Ledalite, Alera, Pinnacle Corelite, Ledalite, Alera, Pinnacle Corelite, Ledalite, Alera, Pinnacle Corelite, Ledalite, Alera, Pinnacle Corelite, Ledalite, Alera, Pinnacle Corelite, Ledalite, Alera, Pinnacle Corelite, Ledalite, Alera, Pinnacle Corelite, Ledalite, Alera, Pinnacle Alumen8, Nulite Alera Alera Alera Alera Lightolier Coffaire Lightolier Coffaire Metalux Focal Point, Finelite Focal Point, Finelite Section 26 5100 – Interior Lighting – Type E1 Section 26 5100 – Interior Lighting – Type E2A Section 26 5100 – Interior Lighting – Type X1 Section 26 5100 – Interior Lighting – Type X2 Section 26 5600 – Exterior Lighting – Type LF1 Section 26 5600 – Exterior Lighting – Type LP1 Section 26 5600 – Exterior Lighting – Type LP2 Section 26 5600 – Exterior Lighting – Type LP3 Section 26 5600 – Exterior Lighting – Type LS1 Section 26 5600 – Exterior Lighting – Type LW1 Section 27 1005 – Voice/Data Cabling Section 27 5315 – Wireless Clock System Lightolier Emergi-Lite Emergi-Lite, Lumax Emergi-Lite, Lumax Beacon, Gardco McGraw-Edison McGraw-Edison McGraw-Edison Gardco Beacon, Gardco Siemon, Belden American Time & Signal, Telecor (1) Unit is a packaged energy recovery unit with heating and cooling provisions provided by gas-fired roof top units specified in Section 23 7413. DRAWINGS Item No. 28 Drawing M1.0 a. Refer to the attached drawing for clarifications on the well field layout for the northeast well field. Item No. 29 Drawing M4.1 a. Clarification: Ventilation ductwork from ERV-8 above Backstage – 092 is exposed and shall be insulated as scheduled for Supply Ducts (Exposed). Item No. 30 Drawing M4.4 b. Clarification: Ventilation ductwork from RTU-4 above Shop Corridor – 121, Wood Shop – 125 and Ag Shop – 124 is exposed and shall be insulated as scheduled for Supply Ducts (Exposed). Item No. 31 Drawing E3.1 a. Gymnasium 032 – Clocks to be 16” diameter. b. Stage 093 – Change horn/strobe to speaker/strobe – 2 locations. Item No. 32 Drawing E3.3 a. Tech 152 – Add one smoke detector and one heat detector. b. Clarification – Smoke and heat detectors in Tech 152, Server 161, and FOT 163 are to be connected into the double pre-action sprinkler system. Refer to mechanical drawings and specifications for additional information. Item No. 33 Drawing E3.4 a. Gymnasium 138 – Clocks to be 16” diameter. Item No. 34 Drawing E5.1 a. Light Fixture Schedule – Type F7: i. Change model number to – 76PF-2T8-21-R-1-EB-SI-C-S72 b. Light Fixture Schedule – Type F7A: i. Change model number to – 76PF-2T8-14-R-1-EB-SI-C-S72 c. Light Fixture Schedule – Type F7B: i. Change model number to – 76PF-2T8-23-R-1-EB-SI-C-S72 d. Light Fixture Schedule – Type F7F: i. Change model number to – 76PF-2T8-17-R-1-EB-SI-C-S72 e. Light Fixture Schedule – Type LS1: i. Model Number – Change 1S to 5M ii. Model Number – Change first 12 to 06 iii. Model Number – Change 350 to 700 iv. Lamps – Change 264W LED to 137W LED f. Light Fixture Schedule – Type LW1: i. Model Number – Change first 12 to 06 ii. Model Number – Change 350 to 700 iii. Lamps – Change 132W LED to 137W LED g. Light Fixture Schedule – Add Type LC1: Ledalite 39-S-1-LED-A-K-Q-S-4-04-1120E h. Light Fixture Schedule – Type LP1: i. Include 10 year warranty for entire fixture including LED’s and drivers. i. Light Fixture Schedule – Type LP2: i. Include 10 year warranty for entire fixture including LED’s and drivers. . j. Light Fixture Schedule – Type LP3: i. Include 10 year warranty for entire fixture including LED’s and drivers.. General Interpretation Items: Item No. 35 Additional information related to Addendum #2, Item #20. The extent of existing lead based paint in the project is not known. Testing for lead has not been done, and it is not anticipated that lead testing will occur. Contractor shall conduct their own testing if needed to be compliant, and shall conduct their operations to be compliant, with State and Federal requirements. Attachments: Drawings – A1.1R, M1.0.1 END OF ADDENDUM #3 TOILET 012 CORNER GUARD 011 CORNER GUARD ISS #1 009 011A 012 NURSE 011 PRIVACY CURTAIN CORRIDOR 023 CORNER GUARD 008B FIRST FLOOR REF. CEILING PLAN A - NURSE'S CURTAIN 1/8" = 1'-0" Design Alliance Inc. 14225 University Suite 110 Waukee, Iowa 50263 TEL 515.225.3469 FAX 515.225.9649 Copyright: 2013 A1.1R 2 1 REVISIONS 01/03/13 DATE 211032 PROJECT NO. SUPPLEMENTAL DRAWING CORNER GUARD AND NURSE'S CURTAIN LOCATIONS TITLE Montezuma School District OWNER Montezuma School District - Renovation Project ADMINISTRATION 002 VEST. 001 008 002A 002 001 010 ISS #2 010 009 012 FIRST FLOOR PLAN A - CORNER GUARD LOCATIONS 1 1/8" = 1'-0" TOILET TOILET 2 S G:\Project Files\Montezuma - 211032 Montezuma CSD\02 - Drawing Files\01 - Arch\CDModel-MontezumaCSD_shuston.rvt 1/4/2013 10:13:24 AM