See Consultant Review Action
This submittal has been reviewed by Davis Partnership, P.C., where
applicable, for conformance to architectural requirements, and has been
reviewed by consultant(s) to Davis Partnership, P.C. for conformance
with the design concept of the Project and compliance with the
information given in the Contract Documents. Contractor is
responsible for dimensions to be confirmed and correlated at the job
site; for information that pertains solely to the fabrication processes or
to techniques of construction; and for coordination of the work of all
trades. Refer to comments noted on the Consultant(s) review stamp(s)
for further action.
SUBMITTAL REVIEW
Date:
Project Name:
Project Number:
Division:
Contractor:
bdk453@q.com
March 19, 2012
DAVIS PARTNERSHIP, P.C., ARCHITECTS
Peak Vista Women’s Health
3/19/13
Date_________________
By______________________________
12-01427
Plumbing
GH Phipps / Rial Heating and Air Conditioning, Inc.
Mark
No Exception Taken
Make Corrections Noted (Resubmit not required)
Revise and Resubmit (or Submit)
X
X
Action
None
Correct
Resubmit
The Consultant has reviewed and approved or rejected these contractor submittals, only for the
limited purpose of checking for conformance with the design concept and the information
expressed in the contract documents. This review does not include review of the accuracy or
completeness of details, such as quantities, dimensions, weights or gauges, fabrication
processes, construction means or methods, coordination of the work with other trades or
construction safety precautions, all of which are the sole responsibilities of the contractor.
Review of a specific item shall not indicate that the Consultant has reviewed the entire assembly
of which the item is a component. The Consultant shall not be responsible for any deviations
from the contract documents not brought to the attention of the Consultant in writing by the
contractor.
Notes: Well put together submittal; Thanks.
UH-1: No Exception Taken.
UH-2: No Exception Taken.
EF-1: Make Corrections Noted.
Coordinate with Electrical Contractor for variation in motor HP rom that which was specified.
Manual Volume Dampers: Make Corrections Noted. Verify sizes need prior to ordering.
Gravity Backdraft Damper: Make Correction Noted. Field verify existing duct size for damper,
prior to ordering.
GRD: Make Corrections Noted.
Tag A:
No Exception Taken.
Tag B:
Make Correction Noted. This is a 12x12 face diffuser and will need a plaster frame
to install into an Acoustical ceiling tile that is more than 12” wide, but less than 24”
wide.
1
Tag C:
No Exception Taken. Hinged face is not required.
Tag D:
Make Correction Noted. Hinged face is not required. Grille returns to plenum, so
needs largest square neck or no back panel.
Tag E:
Make Correction Noted. This is a 12x12 face grille and will need a plaster frame to
install into an Acoustical ceiling tile that is more than 12” wide, but less than 24”
wide.
Tag F:
No Exception Taken.
Tag G:
Make Correction Noted. Plaster frame will need to accommodate installation into a
gyp board ceiling in Janitor Closet, Room 216 and in an Acoustical ceiling tile in
Clean/Dirty, Room 221. Hinged face is not required.
No Exception Taken. You may want to discuss this installation with the Krueger
Manufacturer’s Representative, since round ceiling diffuser actually installs directly
onto duct, so will not have outer ring fit flush to a ceiling surface. The adjustable
cone may allow easy adaptation of airflow when adjacent ceiling does not exist.
Review duct attachment method prior to ordering.