An Alternative Approach to Improving SAIDI and SAIFI Indicators Philippe Deschamps - Schneider Electric Industries - France Jean-Christophe Orsini - Schneider Electric Industries - France Kaare Seest Rasmussen - DONG Energy - Denmark Summary Abstract....................................................................................................... p 1 Introduction.................................................................................................. p 2 DONG Energy's network.............................................................................. p 3 The concept of a SACSe substation............................................................. p 4 SACSe control unit architecture.................................................................... p 7 F200C: Possible further enhancement.......................................................... p 8 Conclusion................................................................................................... p 9 C I R E D - 20th International Conference on Electricity Distribution Prague, 8-11 June 2009 An Alternative Approach to Improving SAIDI and SAIFI Indicators Abstract Under the pressure of regulating authorities, utilities are being challenged to improve their SAIDI and SAIFI indicators. Usually, to reach this goal, more intelligence is put inside DMS, increasing at the same time the amount of data to be processed and the importance of communication in the network. An alternative way, discussed in this paper, consists of using local automation, allowing faster reactions, and therefore a drastic reduction of the number of customers affected by permanent faults, without requiring heavy communication infrastructure. In addition, this paper introduces a further enhancement allowing a faster power restoration for the remaining affected customers. C I R E D - 20th International Conference on Electricity Distribution Prague, 8-11 June 2009 Paper 0635 | 1 An Alternative Approach to Improving SAIDI and SAIFI Indicators Introduction Challenged by the Danish authorities, DONG Energy has for a long time experimented with several methods to optimize network management and particularly increase power availability. An important step was reached when it was decided to reduce the maximum time to reenergize a faulty location to less than a minute to avoid the outage to be counted as a long one, that is degrading the SAIDI and SAIFI indexes. C I R E D - 20th International Conference on Electricity Distribution Prague, 8-11 June 2009 Paper 0635 | 2 An Alternative Approach to Improving SAIDI and SAIFI Indicators DONG Energy's network DONG Energy is a major DNO in Denmark, however this experience involves only one part of its network. FLA04 3383 FLA10-622 FLA10-3722 823 4033 FLA03-4554 FLA10-6202 FLA10-7007 FLA03-4553 FLA10-3369 2017 3304 3320 4956 FLA03-3972 2365 FLA03-4524 FLA03-3971 FLA09-3024 FLA03-4914 2366 5199 2726 2928 FLA09-5562 2367 FLA03-3970 4915 4916 3568 FLA15-998 104 Fig.1 - Typical feeder (neighbouring feeders in white) The 10 kV grid in DONG Energy North, is a 100 The grid is mainly urban and consists of per cent underground radial network, with a high approximately 7000 substations on 600 feeders. degree of access to neighbouring feeders for backup, as shown in Fig. 1. C I R E D - 20th International Conference on Electricity Distribution Prague, 8-11 June 2009 Paper 0635 | 3 An Alternative Approach to Improving SAIDI and SAIFI Indicators The concept of a SACSe substation First of all, let’s clarify the management of The goal is to put in one strategic MV/LV phase‑to-phase and phase-to-earth faults in the substation, a line circuit breaker intended to split DONG Energy network: the feeder into 2 segments in order to minimize ••phase-to-phase faults: these cause the the number of customers affected by a fault, if it tripping of a breaker and therefore an outage happens on the downstream side. Time selectivity which explains how SACSe limits the number of is used to prevent primary substation CB from customers affected tripping simultaneously. In some cases, there ••phase-to-earth faults: the network is could be up to two line CBs on the feeder: in such Petersen‑coil grounded, allowing temporary a case they would use the same setting and trip operation with single earth fault. However, SACSe simultaneously. provides an earth-fault localization information because a second earth fault would cause a The second concept is a step further. In case tripping. of a phase-to-phase fault upstream in the same SACSe means "Sectionalizing And Changeover automatically isolated and the healthy ones to be System enhanced". The concept of SACSe automatically resupplied. This process is based on described below is the latest evolution of the local automation, allowing a fast reaction, and not network, which has already seen significant needing any human intervention or communication improvement over the last 10 years. infrastructure. The solution was developed in substation, it allows the faulty segment to be A first step was taken by deploying circuit breakers in the network [1]. collaboration with Schneider Electric, which offers a wide range of products for network automation. SACSe - Main principle First of all, in a given feeder, one or two substations Backup line are selected to support the automation. They are HV/MV sub MV/LV sub chosen because of their location: they divide the Feeder 1 SACSe MV/LV sub feeder into two or three segments, each supplying Feeder 2 roughly the same number of customers. They are Feeder n also chosen because of the ease of upgrading them. The principle of layout in the network of these substations is described in the ref [2]. Second, a backup line coming from the neighbour feeder is connected to these strategic MV/LV substations to allow a backup supply if required (Fig. 2). Fig. 2 - Principle of a SACSe substation layout in DONG Energy’s network These substations are equipped with a fourfunction switchgear (Fig. 3): ••1 fuse switch or circuit breaker for the transformer protection. It can be forgotten since it has no role in the concept. ••2 circuit breakers and 1 switch distributed among the incoming, the outgoing, and the Incoming/outgoing/backup MV/LV transformer Fig. 3 - Typical make-up of a switchgear in a SACSe MV/LV substation C I R E D - 20th International Conference on Electricity Distribution Prague, 8-11 June 2009 backup lines. There are two circuit breakers among the three to be sure that there will be at least one in the circuit in all network configuration cases. Paper 0635 | 4 An Alternative Approach to Improving SAIDI and SAIFI Indicators If a fault occurs downstream, the breaker opens instantaneously, isolating the downstream segment(s). The status of the switchgear is then Trip sent to the SCADA. If a fault occurs upstream, the switchgear acts as an auto changeover (ACO): the circuit breaker will not trip, but the lack of voltage releases the auto changeover process, Open + backup ordering the incoming to open and the backup Trip to close, which supplies the healthy downstream segment. This is the general principle. Two cases Open + backup are shown in Fig. 4. Since the breaker in the HV/ MV substation is delayed and those in the SACSe are not, the breaker in the HV/MV sub will only trip when the fault is in the first segment Case 1 (Fig. 4 - case 1). Fig. 4 - ACO - principle of fault restoration In a particular case (2 SACSe on the same feeder), In all cases, the time required to reconfigure is less a fault downstream in the second SACSe results than 20 seconds, saving automatically up to 2/3 of in both SACSe circuit breakers tripping. In order the customers normally affected by such a fault. Case 2 to resupply the segment between the two SACSe circuit breakers, the downstream one will act as a In addition, several logic processes are embedded Reverse Auto Changeover (RACO): based on the in the automation in order to avoid any improper CB tripping information, it will keep the incoming action in certain cases: closed, and order the backup to close, therefore ••once the ACO/RACO has operated, it is blocked resupplying the upstream segment until there is some human interaction from the (Fig. 5). control center to prevent further action in a nonstandard network configuration ••a logic process is in action to avoid any ACO and/or RACO action if the network is subject to a global outage, from the transport for instance. This event is detected by monitoring the voltage presence on the backup line. If an absence of voltage is observed on both incoming and backup Trip lines, then no action is taken ••in case of a frequency drop, a recovery process Trip + reserve backup exists in the HV/MV substation and it, it reacts by switching off some feeders. So in this case, the ACO/RACO is inhibited to allow the load-shedding process to be prioritized. Fig. 5 - ACO - principle of fault restoration C I R E D - 20th International Conference on Electricity Distribution Prague, 8-11 June 2009 Paper 0635 | 5 An Alternative Approach to Improving SAIDI and SAIFI Indicators Infrastructure Basically, the system does not require any means to know the real status of all switches and of communication to react properly and fulfil its breakers in the network all times. By these purpose. In fact this is even an advantage in terms means, other information available in the MV/LV of security and reliability. But of course, it is linked substation can also be transmitted. In this case, with the SCADA to report the outage on the faulty and thanks to good coverage of the area by GSM segment, in order to restore the power. In addition, infrastructure, GPRS has been chosen to transfer it reports its status to the operating staff, as Danish data in a very economical way. regulations require the operator Earth fault As explained above, SACSe also integrates All these features are embedded in a single box directional fault passage indicators (FPIs). These provided by Schneider Electric, which is described FPIs allow the staff to locate the fault in the field below. more accurately and faster, and therefore prevent a tripping due to a second fault. C I R E D - 20th International Conference on Electricity Distribution Prague, 8-11 June 2009 Paper 0635 | 6 An Alternative Approach to Improving SAIDI and SAIFI Indicators SACSe control unit architecture Functional description The unit integrates the following functions (Fig. 6): ••phase-to-phase fault protection ensured by two protection relays, for the incoming/outgoing and backup breakers ••phase-to-earth fault detection ensured by two directional fault passage indicators on the same functions ••voltage presence on incoming, outgoing, and backup cables ••automation ensuring the ACO/RACO logic ••communication with the SCADA on the status of the substation ••power supply with batteries to supply the unit under all conditions. Phase I protection I In addition, LV and MV measurement features have U Eart detection U I ACO RACO logic Com Power supply been included in the unit to provide a much better knowledge of the substation and the network load. Fig. 6 - General architecture of the SACSe system Design SACSe is designed as an industrial solution of robustness required by such an application, integrating existing or slightly modified products openness in terms of communication protocols, from the Schneider Electric Easergy offer: and a ready-to-use product to minimize the ••relays from the SEPAM range ••FPI for earth protection is based on the Flair settings on-site during the installation. All these range in a way to make it easy to integrate into DONG products are integrated in a single box (Fig. 7) ••automation is based on the Easergy T200 which Energy's existing installed base. No assembling is includes peripheral functions such as backup/main needed on-site, just the mounting of one box, and power supply and modem. the connection of the sensors and the commands All these products were designed specifically in the switchgear. for the network automation environment. As a consequence, they comply with the specificities of this application: harsh environment withstand (temperature, EMC, electrical insulation -10 kV on mains, dust, humidity, etc.), allowing the high level In terms of size, the system is made to be mounted directly on the wall of the substation. The dimensions allow it to be used even in a compact substation with reduced volume available. Interfaces are designed to make installation simple and minimize the risk of mistakes by using prefabricated cables and connectors to link the unit with sensors. The box is equipped with a transparent window on the front door, allowing all indicators of the status of the system to be read locally. If needed, Fig. 7 - SACSe control unit C I R E D - 20th International Conference on Electricity Distribution Prague, 8-11 June 2009 operating staff have access to the local operation by opening the front door. Paper 0635 | 7 An Alternative Approach to Improving SAIDI and SAIFI Indicators F200C: Possible further enhancement Thanks to the unit presented above, the SAIDI Accurate localization would ideally mean knowing index is drastically reduced, but ultimate quality which cable between the two substations is faulty. requires some additional instrumentation of the network: Schneider Electric has recently launched a new ••In case of a phase fault, only half (if 1 SACSe) or communicating fault passage indicator, the one third (of 2 SACSe) of the feeder customers are Flair 200C, combining in a single cost-effective affected by an outage more than one minute. product the phase-to-phase and phase-to-earth However, the half or third of customers in the faulty fault detection and the GPRS communication segment still need to get power back as soon as functions. This would suit the above purpose possible. particularly well. It should be noted that this new ••In case of an earth fault, the SACSe control Flair 200C embeds a new algorithm for detection unit can indicate whether the fault is upstream or of phase-to-earth faults on compensated networks downstream the SACSe substation. But a more not requiring voltage sensing. This allows the accurate localization is required in order to allow commissioning of such devices to be drastically faulty cable isolation without power interruption simplified, especially for retrofit in existing for any customer. substations, and it reduces the global cost. Of course, for obvious cost and complexity Additionally, the Flair 200C can optionally provide reasons, more than two SACSe substations on measurements, further increasing the knowledge a feeder are not possible. Increasing the number of network load. of SACSe substations is therefore not a way to achieve ultimate quality. This means a device allowing accurate localization of both phase faults and earth faults is needed in the other substations, both upstream and downstream from the SACSe. C I R E D - 20th International Conference on Electricity Distribution Prague, 8-11 June 2009 Paper 0635 | 8 An Alternative Approach to Improving SAIDI and SAIFI Indicators Conclusion Increasing pressure on SAIDI/SAIFI improvement The implementation of this requires a dedicated usually requires more performance from DMS, device to prevent complex commissioning from and at the same time the management of spoiling the solution, and therefore the Return On more and more information. A complementary Investment. solution involves the use of local automation able to perform simple actions quickly. By this means, when a fault occurs, a rough but fast reconfiguration is done while the operation is simplified. References [1] Peter Vinter, Henrik Vikelgaard, 2005, "A novel approach to distribution grid automation at NESA A/S", CIRED Conference 18th international conference on electricity distribution. Session 3. [2] Kåre Seest Rasmussen, 2009, "A real case of self healing distribution network", CIRED Conference 20th international conference on electricity distribution. Session 3. C I R E D - 20th International Conference on Electricity Distribution Prague, 8-11 June 2009 Paper 0635 | 9 35, rue Joseph Monier CS 30323 F- 92506 Rueil Malmaison Cedex RCS Nanterre 954 503 439 Capital social 896 313 776 www.schneider-electric.com 998-5592 This document has been printed on ecological paper 09-2011 © 2011 Schneider Electric. All Rights Reserved. Schneider Electric Industries SAS