KING ABDUL-AZIZ UNIVERSITY COLLEGE OF ENGINEERING ECE DEPARTMENT JEDDAH, SAUDI ARABIA Senior Project EE499 THE CONCEPTUAL DESIGN REPORT Project Title : "Design an internal distribution network of a building according to the international voltage level (230/400 V)" Member Name Emad Ahmed Azzahrani Mansoor Hassan Azzahrani Abdulaziz Sneed Almutairi Abdullah Hamed Obaid Comp. # 0704300 0704290 0704422 0704316 Major Power Power Power Power The Supervisor and Consultant : Dr. Ramzy Obaid. Customer's Name : Sharq 4 Hotel, Jeddah, Al-Sulimanyah Street. Date of submission : 9, January 2011 ABSTRACT Design an internal distribution network of a building according to the international voltage level (230/400 V) In the Kingdom of Saudi Arabia, electrical devices operate at two voltage levels namely: 127/220 and 220/380 volts. But, on Monday 31, August 2010, the Council of Ministers approved the change of voltage distribution of electricity in the whole network of Saudi Arabia to the international voltage level of 230/400 volts. The objective of our project is to redesign the internal electrical distribution network of a building according to the international voltage level (230/400 volts) to meet that change. The sources of our project specification are from Saudi Arabian Standards Organization (SASO), Saudi electricity company (SEC) and Saudi Building Code (SBC) the last two sources are related to SASO. Our specifications are that our system must be compatible with voltage of 230V line-to-neutral and 400V line-to-line, distributing the load approximately equally on the three phase, the distribution network must include proper earthing and using sockets and plugs of British type. There are many solutions to solve our problem. These solutions are : redesign the internal electrical distribution network of a building according to the international voltage level (230/400 volts). Or adding a three-phase distribution transformer before the internal distribution panel of a building with ratio (400/230 V to 220/127 V). Or using solar cells to feed the internal network of the building after conversion that electrical energy to alternating energy ( DC-AC converter ''inverter''). Then, make a new independent singlephase internal distribution network in our building of 127V and use it to feed low power devices. Or using the AC-AC converter to change the level of the voltage from (230/400 V) to (127/220 V) and keep the internal distribution network without any changes. The selected solution is to redesign the internal electrical distribution network of a building according to the international voltage level (230/400 volts). Because, it has higher safety and lower cost than the other alternative solutions. i TABLE OF CONTENTS ABSTRACT ........................................................................................................................ i TABLE OF CONTENTS .................................................................................................... ii LIST OF FIGURES ............................................................................................................iii LIST OF TABLES ..............................................................................................................iii CHAPTER-1 INTRODUCTION ........................................................................................ 1 1.1. SITUATION DESCRIPTION .................................................................................. 1 1.2. PROBLEM DEFINITION ........................................................................................ 1 1.3. OBJECTIVES ........................................................................................................ 2 1.4. PROJECT BACKGROUND .................................................................................... 2 1.4.1. Relevant Standards ......................................................................................... 7 1.4.2. Sources ........................................................................................................... 7 1.5. CURRICULAR RESOURCES ................................................................................ 8 1.6. SPECIFICATION DEVELOPMENT ........................................................................ 8 1.7. DESIGN SPECIFICATIONS AND CONSTRAINTS ................................................ 8 1.8. VALIDATION PROCEDURE .................................................................................. 9 CHAPTER-2 CONCEPTUAL DESIGN .......................................................................... 11 2.1. INTRODUCTION ................................................................................................. 11 2.2. ALTERNATIVE SOLUTIONS TO THE GENERAL PROBLEM ............................. 11 2.3. RELEVANT ALTERNATIVE SOLUTIONS ........................................................... 12 2.4. COMPARING THE ALTERNATIVES AND DECIDING ABOUT THE SOLUTION 12 2.4.1. Comparing The Alternatives Solutions To The General Problem ................... 12 2.4.2. Comparing The Relevant Alternatives Solutions ............................................. 14 2.5. DESIGN METHODOLOGY ................................................................................... 16 2.6. PROJECT TASKS AND TIMETABLE ................................................................... 17 2.7. TEAM ROLES AND CONTRIBUTION ................................................................. 17 REFERENCES ................................................................................................................ 19 APPENDICES ................................................................................................................. 20 APPENDIX - A : TEAM MEETINGS ........................................................................... 20 APPENDIX - B : IMPORTANT QUESTIONS ON VOLTAGE CHANGING.................. 26 ii LIST OF FIGURES CHAPTER-1 INTRODUCTION Figure 1.1: World map show the frequency and secondary distribution voltage level[2]. ..... 1 Figure 1. 2: The current situation of voltage distribution level as in Makkah....................... 4 Figure 1. 3: The current situation of voltage distribution level as in Jeddah. ...................... 4 Figure 1. 4: The new voltage level for all K.S.A cities. ....................................................... 4 CHAPTER-2 CONCEPTUAL DESIGN Figure 2. 1: The block diagram explain the steps of our design. ...................................... 16 LIST OF TABLES CHAPTER-1 INTRODUCTION Table 1.1: Curricular Resources. ....................................................................................... 8 Table 1.2: Specification, constrains and the effect on the society. ..................................... 9 CHAPTER-2 CONCEPTUAL DESIGN Table 2. 1: The pros and cons of the redesign the internal distribution network. .............. 13 Table 2. 2: The pros and cons of adding a three-phase distribution transformer. ............. 13 Table 2. 3: The pros and cons of using solar cells. .......................................................... 13 Table 2. 4: The pros and cons of using the AC-AC converter. ......................................... 14 Table 2. 5: The pros and cons of keeping the original home wiring system. .................... 15 Table 2. 6: The pros and cons of change the original home wiring system. ..................... 15 Table 2. 7: The pros and cons of keeping the original home wiring system. .................... 15 Table 2. 8: The pros and cons of change the original home wiring system. ..................... 15 Table 2. 9: Project tasks and timetable. ........................................................................... 17 Table 2. 10: Team roles. ................................................................................................. 17 Table 2. 11: Tasks Contribution. ...................................................................................... 18 iii CHAPTER-1 INTRODUCTION 1.1. SITUATION DESCRIPTION Electricity gives us many benefits such as heating, cooling, lighting, cooking and machinery operation, in addition to many other benefits produced by electrical devices. In the Kingdom of Saudi Arabia, electrical devices operate at two voltage levels namely: 127 and 220 volts. The reason for that is the diversity of the internal distribution network of houses. There are two ways to connect electrical devices: line-to-line connection (for high electrical power devices, such as air conditioners, and electrical ovens), and line-to-neutral connection (for low electrical power devices, such as television, and radio). Currently, only 9% of the world countries use (127/ 220 volts), while 70% of them use the international voltage level (230/400 volts) and the remaining 21% use other voltage levels (see figure 1.1)[1]. [2] Figure 1.1: World map show the frequency and secondary distribution voltage level . 1.2. PROBLEM DEFINITION On Monday 31, August 2010, the Council of Ministers approved the change of voltage distribution of electricity in the whole network of Saudi Arabia to the 1 international voltage level of 230/400 volts. This means that, there will no longer be 127 V available from the network for any consumer device requiring it, and all electrical devices in residential applications will need to have the 230 volt rating. 1.3. OBJECTIVES The objective of our project is to design the internal electrical distribution network of a building according to the international voltage level (230/400 volts) only. The aim is to have a building with an electrical system compatible with the near level and ready when the utility company makes the change. 1.4. PROJECT BACKGROUND The development of electricity in the Kingdom of Saudi Arabia can be divided into two stages: Stage 1: Initially, electricity generation was left to small, local companies. Such companies sold power at varying rates according to local costs. In 1961 (1381 AH), the Department of Electricity Affairs was established within the Ministry of Commerce, with a mandate to regulate the electricity generation sector and to issue permits and licenses to electricity companies and to encourage national investment in electric power generation. Stage 2: In 1972 (1392 AH), the Department of Electricity Services was established. This Department was separated from the Ministry of Commerce and was given the additional responsibility of planning electrical services for the Kingdom as a whole. In 1974 (1394 AH), the Ministry of Commerce was divided into the Commerce Agency and the Industry and Electricity Agency. In that same year, the electricity tariff was set for all companies at a level below their actual costs. In 1975 (1395 AH), the Government adopted ambitious plans for economic development requiring investment in industry and electrification. The Ministry of Industry and Electricity was formed, with an Industrial Affairs Agency and an Electricity Affairs Agency. The Electricity Affairs Agency expanded the planning, co-ordination and regulatory roles for providing electrical services. The Electricity 2 Corporation was established in 1976 (1396 AH) to coordinate the electricity plans contained in the Kingdom's Development Plan. From 1976 to 1981 (1396 - 1401 AH) all community electricity generation was gradually subsumed under the four regional Saudi Consolidated Electricity Companies (SCECOs), located in the Central, Eastern, Southern and Western regions. With the formulation of a coherent development plan and the establishment of the SCECOs, the Government was able to bring electricity to the towns, villages and settlements throughout the Kingdom. The number of electricity customers grew from 216,000 in 1970 (1390 AH) to 3,035,000 in 1996 and 4,955,906 in 2006. In May, 2003, electricity was made the responsibility of the Ministry of Water and Electricity[3]. The importance and the benefits of the electrical connection among regions: The benefits of the electrical connection among regions focus on the strategic , technical , operating and economical sides which can be shown as follow : Reducing the size of necessary investment for establishing new generating stations. Reducing the demanded reserve for each electrical system in the participant regions. Reducing the costs of operating as a result of the exchange of energy between the regions. Saving the electrical coverage to each regions for emergency case as losing the ability to generate electricity in any region. Achieving the economic factor by the commercial exchange of electrical energy among the regions. Improving the reliability in all the electrical energy systems in the regions. On the other hand, the distribution voltage in KSA is at different levels (127/220 and 220/380 V). for example, the electrical distribution network in Riyadh, Dammam and Jeddah is based on 127/220 V and in Makkah and other cities is based on 220/380 V. We can see the cons and pros of the continued application of 127/220 V and the cons and pros of change the voltage level to 230/400 V[4]. 3 Figure 1. 2: The current situation of voltage distribution level as in Makkah. Figure 1. 3: The current situation of voltage distribution level as in Jeddah. Figure 1. 4: The new voltage level for all K.S.A cities. 4 The cons of the continued application of 127/220 V are : 1- Isolation from the international voltage level (230/400 V). 2- Increased accidents (shocks, and damage organs, and fires) resulting from the use of homes as efforts (127 V and 220 V) due to faulty delivery effort is contrary to the rated voltage of the device. 3- The need to use the adapters to connect the devices to electricity, given the multiplicity of different types of plugs and Sockets, which weakens the security level, threatening the safety. Continue to allow devices to the markets of the Kingdom are designed on the efforts of less than 127 V, and lead run on nonsystematized effort to lower their operational lifetime, and low performance. 4- Difficulty in the application of certificates of conformity from the country of origin because of importing equipment, electric voltage regulated contrary to the effort to use in the Kingdom. 5- Difficult for factories that export of household electrical appliances to the Kingdom of the manufacture of devices that work hard 127 V, since this process requires additional costs to the consumer. The pros of the continued application of 127/220 V are : 1- Insulation of cables is less with lower voltages. 2- Saving money that will paid to change. The pros of change the voltage level to 230/400 V are : First: for State: 1- Efforts to achieve uniformity in the electrical distribution with the GCC, which would facilitate the standardization of the devices in the GCC, as well as for the rest of the Arab States and the countries of the world. 2- Improve the level of security in extensions, and therefore lack of fires caused by electricity. 3- Growth of exports of electrical appliances at competitive prices due to lower production costs, the application of international standards on the national industry. 4- A standardized procedure for examination and to allow electrical equipment for customs officials view of the consolidation effort. 5- Ease of testing devices and wiring, which is reflected in the performance of laboratories, whether government or private. 5 6- Integration with the global systems of effort, and thus benefit from the transmission of technical minimum of disruption. Second: for Saudi Electricity Company: 1- Reduce the cost of the meter and the electrical box installed by the consumer due to the low current, and therefore use smaller counters, and dispensing with the AC adapter in the counter. 2- Low energy lost in the networks, and distribution equipment. 3- To overcome the problem of low voltage distribution networks, thereby contributing to improving the performance and protection of home appliances. 4- Less than the number of cables used and the sectional area of the same value of electric power, and therefore less than the costs of establishing distribution networks. 5- Carrying capacity of the cutter, as well as the copper conductors inside the paintings. 6- Increasing the number of participants who can be hooked up to them one adapter in the same capacities in the present. 7- Unification of the LV for all categories of participants. 8- Standardization of equipment used in low voltage. Third: to the consumer: 1- Plug avoid the dangers of faulty hardware as a result of the presence of Two efforts currently. 2- Reduce the prices of hardware to match the specifications Saudi Arabia with international standards. 3- Improving the efficiency of devices and extend their life, where they will work best trophy. 4- The small size of the distribution panel inside the building and thus lower price. 5- Use of electrical wire with a cross-sectional area less than the extensions within the facility, and therefore less costs. 6- Low energy lost in the electrical wiring (saving in consumption). 7- To standardize the format plugs (Sockets) in the facility. 6 Fourth: to the factory owner and an importer of hardware: 1- Agree with the hardware specifications of international standards, and therefore increasing production opportunities for export. 2- Easy import of production equipment for factories is compatible with international standards, and ease of exporting the products of factories devices and electrical equipment. 3- No need for factory production lines, each effort is different, but becomes a unified product line, which reduces costs and facilitates the transfer of technology for the plant and reduce production costs, and therefore easier to sell it at a competitive price locally and abroad. 4- To reduce import costs as well as ease of re-export. The cons of change the voltage level to 230/400 V are : 1- Change all devices that work on 127 V. 2- Insulation of cables is more strong with higher voltages. 1.4.1. Relevant Standards International Electrotechnical Standards IEC-60364 (Electrical Installations of Buildings - Protection for safety - Protection against electric shock, Earthing requirements). Saudi Arabian Standards Organization (SASO/IEC/60364) (Electrical Installations of Buildings - Protection for safety - Protection against electric shock, Earthing requirements, according to IEC standards). Ministry of Water and Electricity (Technical Guidance for design an internal electrical distribution network for building according to 230/400 V). Saudi Building Code ( Electrical Requirements SBC 401) (Cross-section of conductors, types of wiring and methods of installation, protective equipment). 1.4.2. Sources The Supervisor (Dr. Ramzy Obaid). Step by Step Guide Book " Home Wiring"[5]. The Complete Guide to Home Wiring[6]. 7 1.5. CURRICULAR RESOURCES The following table 1.1 summarizes the related topics from the different courses the team members have taken that will be utilized in this project. Table 1.1: Curricular Resources. Course BASIC ELECTRICAL CIRCUITS (EE250) ELECTRICAL MEAS. & INSTR. (EE253) Related Topic - AC Power Analysis. - Three-Phase Circuits. Measurement techniques and types of errors and how to find error and tolerance. -Thermal Limits to Conductor POWER TRANSMISSIO -Load N & DIST. Characteristics. (EE453) -Grounding. SWITCHG. & PROT. OF POW SYS. I (EE454) -Circuit Breakers. - Fuses. Application of topic in the project Members who took the course Understand the RMS value, power factor and 3-phase calculations. Emad, Mansoor, Abdul-Aziz and Abdullah. Make sure from our calculations and the tolerances of the project Emad, Mansoor, Abdul-Aziz and Abdullah. Calculate current currying capacity ,how to estimate maximum load by known devices wattage and understand power system grounding. Emad, Mansoor, Abdul-Aziz and Abdullah. Understand the circuit breaker and fuses ratings. Emad, Mansoor, Abdul-Aziz and Abdullah. 1.6. SPECIFICATION DEVELOPMENT The sources of our project specification are from Saudi Arabian Standards Organization (SASO) , Saudi electricity company(SEC) and Saudi Building Code(SBC) the last two sources are related to SASO. 1.7. DESIGN SPECIFICATIONS AND CONSTRAINTS Engineering specifications, realistic constraints and the effect of the project on the society are listed in the following table (see table 1.2). 8 Table 1.2: Specification, constrains and the effect on the society. Specification / Constraints The system must be compatible with: line-to-neutral voltage of 230 V The system must be compatible with: line-to-line voltage of 400 V Distributing the load approximately equally on the three phase The frequency is 60 Hz The sockets Affect on the Society Political Political Economical, Safety Political Political The plugs Political The distribution network must include proper earthing. The system should be capable of withstanding voltage fluctuation of ± 5 %. Maximum Circuit Breaker rating of 20 A. Political, Ethical and Safety Political, Safety Safety 1.8. VALIDATION PROCEDURE There are some procedures that we should follow for confirming that the design has met all specifications and constraints, these procedures are: 1- Field measurements: Field measurements are the main procedure that we will use to confirm our design; we will use it to check: a) The line-to-neutral voltage is 230 V. b) The line-to-line voltage is 400 V. c) Distributing the load approximately equally on the three phase. d) The system should be capable of withstanding voltage fluctuation of ± 5 %. 2- checklist: We will use check list to double-check : a) The frequency is 60 Hz. 9 b) The sockets and plugs as in specification. c) The earthing system. d) Maximum Circuit Breaker rating of 20 A. 11 CHAPTER-2 CONCEPTUAL DESIGN 2.1. INTRODUCTION After the Council of Ministers approved the change of voltage distribution of electricity in the whole network of Saudi Arabia to the international voltage level of 230/400 volts we will go to redesign the internal electrical distribution network of a building according to that voltage level only. In this chapter we will discuss alternative solutions correspond to our solution and comparing it with that alternative solutions. 2.2. ALTERNATIVE SOLUTIONS TO THE GENERAL PROBLEM We have two main issues : a) Saudi Electricity Company (SEC) need (new voltage level : 230V line-to-neutral and 400V line-to-line only). b) Consumer need which is keeping the devices that operate on 127V level. Our solution is to redesign the internal distribution network for a building according to the new level of voltage. Our solution will verify SEC need only. But, there are alternative solutions to solve that problem, such as: Adding a three-phase distribution transformer before the internal distribution panel of a building with ratio (400/230 V to 220/127 V). Then, connect the low side of the transformer to the main distribution panel. So, the line-to-neutral voltage of the internal distribution network will be 127V and line-to-line be 220V that mean no need to make any change on the internal distribution network of the building. This solution will verify SEC need and consumer need. Using solar cells to feed the internal network of the building after conversion that electrical energy to alternating energy ( DC-AC converter ''inverter''). Then, make a new independent single-phase internal distribution network in our building of 127V and use it to feed low power devices, and use the coming energy from electricity company (220V line-to-neutral) to feed high power 11 devices by the main internal distribution network. This solution will verifying consumer need only. Using the AC-AC converter to change the level of the voltage from (230/400 V) to (127/220 V) and keep the internal distribution network without any changes. This solution will verify SEC need and consumer need. 2.3. RELEVANT ALTERNATIVE SOLUTIONS There are relevant solutions to our solution that is to design the internal distribution network for a building according to international voltage level (400/230 V), such as: Keeping the original home wiring system and CB's for the apartments of the building. Change the original home wiring system and CB's for the apartments of the building. Keeping the original home wiring system but change CB's for the apartments of the building. Change the original home wiring system but keep CB's for the apartments of the building. 2.4. COMPARING THE ALTERNATIVES AND DECIDING ABOUT THE SOLUTION 2.4.1. Comparing The Alternatives Solutions To The General Problem In this section, the comparison will be between; Redesign the internal distribution network ,Adding a three-phase distribution transformer before the internal distribution panel , Using solar cells to feed the internal network of the building by 127V and Using the AC-AC converter. a) Redesign the internal distribution network for a building according to the new level of voltage. The next table (table 2.1) summarizes the advantages and disadvantages of our selected solution. 12 Table 2. 1: The pros and cons of the redesign the internal distribution network. Pros Using the coming energy from Saudi Electricity Company directly. Improve the performance and correcting errors (if any) for old internal distribution network design. Avoiding the transformation problems and errors. There is no needs to adding new equipments to the network (solar cells generation system & transformer). Only one voltage level (230V line-to-neutral) (more safety). Cons Need to rewiring the network (line to line convert to line to neutral). The home devices works at 127V cannot be used (don’t meet consumer need). b) Adding a three-phase distribution transformer before the internal distribution panel as we explained in section 2.2. The next tables (table 2.2, 2.3 and 2.4) summarizes the advantages and disadvantages of remains suggested alternative solutions. Table 2. 2: The pros and cons of adding a three-phase distribution transformer. Pros Keep the internal distribution network without any change. The home devices works at 127V can be used. No need to rewiring the network. Cons Adding new equipment to the network ( transformer). Two voltage levels (lower safety). Cost of the transformer and its maintenance. Transformation problems and errors. The physical size of transformer and its place. The devices which work at 127V are not available in the markets (after few years). The distribution of the load will be unbalance. c) Using solar cells to feed the internal network of the building by 127 V as we explained in section 2.2. Table 2. 3: The pros and cons of using solar cells. Pros Keep the internal distribution network without any change. The home devices works at 127V can be used. No need to rewiring the network. Cons Adding new equipment to the network ( solar cells generation system). Two voltage levels (lower safety than one voltage level). Cost of the solar cells generation system and its maintenance. 13 Pros Cons Inverting problems and errors. The physical size of solar cells generation and its needed area. The devices which work at 127V are not available in the markets (after few years). The distribution of the load will be unbalance for the three-phase because the sockets of 127V will not be used. d) Using the AC-AC converter. Table 2. 4: The pros and cons of using the AC-AC converter. Pros Keep the internal distribution network without any change. The home devices works at 127V can be used. No need to rewiring the network. Cons Adding new equipment to the network (AC-AC converter). Two voltage levels (lower safety than one voltage level). Cost of the AC-AC converter(high cost). Converting problems and errors (specially in the frequency). The devices which work at 127V are not available in the markets (after few years). The distribution of the load will be unbalance for the three-phase because the sockets of 127V will not be used. So, we select redesign the internal distribution network solution because it has lower cost and higher safety and has many advantages as we said and its disadvantages are few comparing to advantages. 2.4.2. Comparing The Relevant Alternatives Solutions In this section, the comparison will be between; Keeping the original home wiring system but change CB's, Change the original home wiring system and CB's, Keeping the original home wiring system and CB's and Change the original home wiring system but keep CB's. a) Keeping the original home wiring system but change CB's. The next table (table 2.5) summarizes the advantages and disadvantages of our selected relevant solution. 14 Table 2. 5: The pros and cons of keeping the original home wiring system. Pros Keeping the way of home wiring without any change and no need to do a cracking of the floor and walls to make new path for wiring. Lower cost. Cons We cannot control the length of wires if wires length not optimize. Redesign CB's sizes (more safety). b) Change the original home wiring system and CB's. The next table (table 2.6, 2.7 and 2.8) summarizes the advantages and disadvantages of remains suggested relevant alternative solutions. Table 2. 6: The pros and cons of change the original home wiring system. Pros We can control the length of wires if wires length not optimize. Cons Change the way of home wiring without any change and need to do a cracking of the floor and walls to make new path for wiring. Redesign CB's sizes (more safety). higher cost c) Keeping the original home wiring system and CB's. Table 2. 7: The pros and cons of keeping the original home wiring system. Pros Keeping the way of home wiring without any change and no need to do a cracking of the floor and walls to make new path for wiring. Cons We cannot control the length of wires if wires length not optimize. Using old CB's sizes that of higher size (less safety). Lower cost. d) Change the original home wiring system but keep CB's. Table 2. 8: The pros and cons of change the original home wiring system. Pros We can control the length of wires if wires length not optimize. Cons Change the way of home wiring without any change and need to do a cracking of the floor and walls to make new path for wiring. higher cost Redesign CB's sizes (more safety). 15 So, we select to keep the home wiring system and change CB's sizes because when we compare its advantages are better than the other solutions. 2.5. DESIGN METHODOLOGY In the next block diagram (see Figure 2.1) explain the steps through which we will proceed to accomplish our design. Start Find an apartment or villa to make our design on it. Specifications Development Maximum load, Breakers & fuses sizes, Distributing the load equally on three-phase. Optimize the length of wires and calculate wires sizes. Check to validate and meet subsystem specification. No Yes Consider Reliability and flexibility in network Apply the design Project Validation End Figure 2. 1: The block diagram explain the steps of our design. 16 2.6. PROJECT TASKS AND TIMETABLE The table 2.9 below shows project tasks and distribution of them over the time. 30 28 26 24 22 20 18 16 14 12 10 8 6 4 Activity / Week 2 Table 2. 9: Project tasks and timetable. Selecting the problem and supervisor Problem Definition Specifications Development Searching for the project standards Preliminary design of the project Calculate the breakers and fuses sizes Calculate the wiring of the internal network sizes Prototype layout and constructing Test the project with the supervisor Report writing Submitting Seminars 2.7. TEAM ROLES AND CONTRIBUTION A good job is the product of good team members, and that is achieved when everyone takes the appropriate task according to their role in the project. These tasks and roles have been shown in the next tables (table 2.10 and 2.11) ,for more see information Appendix –A (team meetings and tasks distribution). Table 2. 10: Team roles. Member Role Emad Ahmed Team Leader Mansoor Hassan Team Recorder Abdulaziz Sneed Team Writer Abdullah Obaid Team Facilitator 17 Table 2. 11: Tasks Contribution. Activity M1 M2 M3 M4 Selecting the problem and supervisor Problem Definition Specifications Development Searching for the project standards Preliminary Design of the project Calculate the breakers and fuses sizes Calculate the wiring of the internal network sizes Prototype layout and constructing Test the project with the supervisor Report Writing Submitting Seminars 18 REFERENCES [1] http://www.mowe.gov.sa/newmowe/English/showarticle.aspx?id=394 ( last visited on December 13, 2010). [2]thttp://en.wikipedia.org/wiki/File:Weltkarte_der_Netzspannungen_und_Netzfreq uenzen.svg ( last visited on December 13, 2010). [3] http://www.saudinf.com/main/g61.htm (SAMIRAD, the Saudi Arabian Market Information Resource); (last visited on December 10, 2010). [4] http://www.mowe.gov.sa/newmowe/English/showarticle.aspx?id=394 (Ministry of Water and Electricity); (last visited on December 10, 2010). [5] Step by Step Guide Book " Home Wiring" , No.1, Step By Step Guide Book Co. Author: Ray McReynolds. (http://www.ebookonline.net/Step-by-Step-GuideBook-on-Home-Wiring_69815.html ). [6] The Complete Guide to Home Wiring: A Comprehensive Manual, from Basic Repairs to Advanced Projects (Black & Decker Home Improvement Library). 19 APPENDICES APPENDIX - A : TEAM MEETINGS Team meeting # 1 The date: Wednesday 27, October 2010 The time: 1:00 P.M. to 2:30 P.M. Place of the meeting : Central Library of the University. Team members in attendance: Emad Ahmed (Leader). Mansoor Hassan (Recorder). Abdul-Aziz Sneed (Writer). Abdullah Obaid (Facilitator). Team meeting # 2 The date: Wednesday 12 ,November 2010 The time: 10:00 P.M. to 12:00 P.M. Place of the meeting : Student hostel. Team members in attendance: Emad Ahmed (Leader). Mansoor Hassan (Recorder). Abdul-Aziz Sneed (Writer). Abdullah Obaid (Facilitator). Team meeting # 3 The date: Saturday 15 ,November 2010 The time: 11:00 A.M. to 12:20 P.M. Place of the meeting : Central Library of the University. Team members in attendance: Emad Ahmed (Leader). Mansoor Hassan (Recorder). Abdul-Aziz Sneed (Writer). Abdullah Obaid (Facilitator). Team meeting # 4 The date: Monday 24 ,November 2010 The time: 4:00 P.M. to 5:30 P.M. Place of the meeting : Central Library of the University. Team members in attendance: Emad Ahmed (Leader). Mansoor Hassan (Recorder). Abdul-Aziz Sneed (Writer). Abdullah Obaid (Facilitator). Team meeting # 5 The date: Monday,13 ,December 2010 The time: 4:00 P.M. to 6:30 P.M. Place of the meeting : Central Library of the University. Team members in attendance: Emad Ahmed (Leader). Mansoor Hassan (Recorder). Abdul-Aziz Sneed (Writer). Abdullah Obaid (Facilitator). 21 Team meeting # 6 The date: Tuesday 14, December 2010 The time: 2:30 P.M. to 3:15 P.M. Place of the meeting : Sharq 4 Hotel (The customer). Team members in attendance: Emad Ahmed (Leader). Mansoor Hassan (Recorder). Abdul-Aziz Sneed (Writer). Abdullah Obaid (Facilitator). Team meeting # 7 The date: Wednesday 15, December 2010 The time: 4:00 P.M. to 8:00 P.M. Place of the meeting : Central Library of the University. Team members in attendance: Emad Ahmed (Leader). Mansoor Hassan (Recorder). Abdul-Aziz Sneed (Writer). Abdullah Obaid (Facilitator). Team meeting # 8 The date: Thursday 23 ,December 2010 The time: 11:00 A.M. to 1:30 P.M. Place of the meeting : Sharq 4 Hotel (The Customer). Team members in attendance: Emad Ahmed (Leader). Mansoor Hassan (Recorder). Abdul-Aziz Sneed (Writer). Abdullah Obaid (Facilitator). Team meeting # 9 The date: Sunday 26 ,December 2010 The time: 3:00 P.M. to 4:30 P.M. Place of the meeting : Central Library of the University. Team members in attendance: Emad Ahmed (Leader). Mansoor Hassan (Recorder). Abdul-Aziz Sneed (Writer). Abdullah Obaid (Facilitator). Team meeting # 10 The date: Saturday 1 ,January 2011 The time: 11:00 A.M. to 12:30 P.M. Place of the meeting : Central Library of the University. Team members in attendance: Emad Ahmed (Leader). Mansoor Hassan (Recorder). Abdul-Aziz Sneed (Writer). Abdullah Obaid (Facilitator). 21 TEAM MEETING MINUTES Team meeting #: 1 The date: Wednesday 27, October 2010 The time: 1:00 P.M. to 2:30 P.M. Place of the meeting : Central Library of the University Team members in attendance: Emad Ahmed (Leader). Mansoor Hassan (Recorder). Abdul-Aziz Sneed (Writer) Abdullah Obaid (Facilitator) Recorder: Mansoor Hassan Meeting Facilitator: Abdullah Obaid AGENDA ITEMS: The problem definition of the project and the objective of it. Topic/Item Situation description The problem definition The objective of the project Project background Decision Unfinished subject Done Done Unfinished subject TASK WHO IS RESPONSIBLE Technical writing for the situation description Technical writing for the problem definition Technical writing for the objective of the project Searching about the background Mansoor Hassan Emad Ahmed Abdul-Aziz Sneed Abdullah Obaid 22 TEAM MEETING MINUTES Team meeting # 2 The date: Wednesday 12 ,November 2010 The time: 10:00 P.M. to 12:00 P.M. Place of the meeting : Student hostel Team members in attendance: Emad Ahmed (Leader) Mansoor Hassan (Recorder) Abdul-Aziz Sneed (Writer) Abdullah Obaid (Facilitator) Recorder: Mansoor Hassan Meeting Facilitator: Abdullah Obaid AGENDA ITEMS: Discussion the search about the object resources and revision of the object background. Topic/Item Background search Discussion background relevant standards Discussion background sources Search for the curricular resources TASK Technical writing for background relevant standards Technical writing for background sources Searching for the curricular resources Technical Writing for curricular resources Decision Done Done Done Unfinished WHO IS RESPONSIBLE Emad Ahmed Mansoor Hassan Abdul-Aziz Sneed Abdullah Obaid 23 TEAM MEETING MINUTES Team meeting # 5 The date: Monday,13 ,December 2010 The time: 4:00 P.M. to 5:30 P.M. Place of the meeting : Central Library of the University Team members in attendance: Emad Ahmed (Leader) Mansoor Hassan (Recorder) Abdul-Aziz Sneed (Writer) Abdullah Obaid (Facilitator) Recorder: Mansoor Hassan Meeting Facilitator: Abdullah Obaid AGENDA ITEMS: Design specification, constrains and validation procedure. Topic/Item Design specifications and constrains Validation procedure Decision Done Unfinished TASK writing the design specifications and constrains Search for validation procedure Writing specification development WHO IS RESPONSIBLE Writing validation procedure Abdullah Obaid Emad Ahmed Mansoor Hassan Abdul-Aziz Sneed 24 TEAM MEETING MINUTES Team meeting # 7 The date: Wednesday 15 ,December 2010 The time: 4:00 P.M. to 8:00 P.M. Place of the meeting : Student hostel Team members in attendance: Emad Ahmed (Leader) Mansoor Hassan (Recorder) Abdul-Aziz Sneed (Writer) Abdullah Obaid (Facilitator) Recorder: Mansoor Hassan Meeting Facilitator: Abdullah Obaid AGENDA ITEMS: The conceptual design of the project, visiting the work place of the project. Topic/Item Discussion of alternative solution of general problem Discussion relevant alternative solutions Discussion of chosen solutions Design methodology Studying the work place TASK Drawing a map for the previous internal network of the place Technical writing for the introduction of conceptual design Technical writing for alternative solution and relevant solution Technical writing for design methodology Preparing Gantt Chart for the project Distribute the tasks for each member Technical writing for chosen solutions Searching about the tools in market Decision Done Done Done Unfinished Unfinished WHO IS RESPONSIBLE Mansoor Hassan Abdullah Obaid Emad Ahmed Abdulaziz sneed Emad Ahmed Abdulaziz Sneed Mansoor Hassan Abdullah Obaid 25 APPENDIX - B : IMPORTANT QUESTIONS ON VOLTAGE CHANGING Q 1 - Do existing homes will be affected by this trend? A 1 - will not be affected by the existing home currently, and will change the voltage by 10 years after the decision to change to the international effort, in the light of a phased program of change adopted by the Ministry of Water and Electricity, and supervise its implementation, in cooperation with relevant services of electricity, including the best interest of a participant and the electricity company. Q 2 - What about new buildings in the neighborhoods of the list? A 2 - will conduct electricity to new buildings in existing neighborhoods and the voltage 220 volts only, and should be designed electrical wiring in these buildings to fit this effort, this effort will facilitate the conversion to 230 volts in a timely manner. Q 3 - What about the new schemes? A 3 - in the new schemes will lead electricity to houses international effort 230 volts, to factories and large commercial centers on the voltage 230/400 volts. Q 4 - Do I need to change the existing homeowner's devices? And which is supposed to be taken into account when purchasing household electrical appliances from now on? A 4 - does not require existing homes on the population change of the current, but when you buy new hardware must be on the voltage 220 volts, and everyone avoid buying any hardware running on 127 voltage or 110 volts. Q 5 - who will bear the cost of modifying internal wiring in existing homes after ten years? A 5 - will begin to modify the extensions of existing housing ten years after issuance of the decision, during a phased program over 15 years, under the supervision and financing of the electricity company, so it will bear the citizen costs of modifying extensions at home If you got electricity to his home before making that decision, or within one year of issuance , and reached a common electricity a year after the adoption of resolution costs borne by the amendment, if any, where you from making that decision, starting the implementation of electrical installations in accordance with the new effort. Q 6 - of the process of amending the extensions will be within the existing buildings? A 6 - will be a company or companies specialized and qualified to modify the internal networks of existing buildings under the supervision of the Saudi Electricity Company, according to the change program. Q 7 - Is there any risk of new effort for the safety of the user? A 7 - if he adheres to the requirements of security and safety in electrical wiring, and used plugs (Sockets)-specification Saudi Arabia, there is no danger to the user or the tenant. 26 Q 8 - Do you change your electricity meter and unequivocal, and will do so, who bears the costs? A 8 - all the required changes in the distribution network, including a change in the counter and unequivocal, if necessary, will be handled by the Saudi Electricity Company, and bear the costs. Q 9 - Home-based effort is currently fed (127/220) volt What are the procedures required of the occupant to do to become a voltage (230/400 volts)? A 9 - by not buying any new hardware on the voltage 127 volts, and when you need to replace any device that works on the voltage 127 volts, can be replaced by a device works on dual voltage 127/220 volts, and preferably replaced by a device works on the voltage 220 volts, which will facilitate the conversion in the future to international effort to 230 volts. Q 10 - When building a new house in a residential area or a new list, or set up a factory in an industrial area new, what is required? A 10 - must perform electrical wiring of homes and new facilities in line with the new effort, to be connected to electricity to this effort. Q 11 - existing plant is currently fed by the current industrial voltage (220/380 volts) Will it change the voltage to the international effort (230/400 volts)? A 11 - The difference between the current industrial voltage (220/380 volt) and the new international effort (230/400 volts) is located within the allowable voltage variation, and that the buildings and facilities that feed industrial voltage 220/380 volts will not be affected by the change to the effort 230/400 volts. Q 12 - What is the effect of changing the voltage on the import and manufacture of electrical devices that operate on the voltage 127 volts, the voltage (127/220) volt? A 12 - must immediately stop the import, manufacture devices that operate on the voltage 127 volts, and can continue to import and manufacture of devices that operate on the voltage (127/220) volt, the expansion in the manufacture and importation of devices that operate on the voltage of 230 volts. Q 13 - Do you use the new effort will bring savings in construction costs? A 13 - Yes, the change in this situation has economic benefits, along with the benefits of art, would reduce the volume of cables in the domestic distribution network, distribution panels, as well as bites of incisors, which saves well in construction costs, especially in homes and buildings. Q 14 - Will it affect electricity consumption for the home or factory as a result of this change? A 14 - electricity consumption is estimated by kilo watt hours, will not be affected by the change effort. Q 15 - Do you change the voltage effect on the frequency ? A 15- There is no trace of it, Hesitation in the power grid in the Kingdom of 60 hertz, and this change will not change effort. 27