Direct 400Vdc for the Data Center

advertisement

Direct 400Vdc for

Energy Efficient Data Centers

27 April 2009

Tomm Aldridge, Principal Engineer

Joint work prepared by:

Intel Corporate Technology Group

Emerson Network Power

EYP Mission Critical Facilities

Intel may have referenced third-party information throughout this presentation. Intel’s use of third-party copyrighted or trademarked materials are for reference only. Intel does not warrant the adequacy, accuracy or completeness of the third-party information nor does Intel claim that it has obtained a license to the third-party material. Copyright to the third-party referenced materials remain with their respective holders. LIMITED RIGHTS

Energy Systems Research Lab

Intel Corporate Technology Group

2

Summary Vision

Direct 400Vdc Facility Vision

DC

300-

400V

DC/DC

AC/DC

60 Hz AC

480V AC/DC

Lighting loads

DC/AC

Ballast

DC/DC

Electronic loads

VR

PSU

Motor loads

DC/AC

ASD

Energy Systems

Research Lab

3

Motivation

 Inefficiencies in data center power delivery are significant, expensive, and ecologically unsustainable

– 50% of power is lost in conversions, transformations, and distribution

– US data centers consumed 61B kWh ($4.5B) in 2006, doubling by 2011

– Worldwide data centers consumed 123B kWh in 2005, and is expected to increase 40% to 76% by 2010

– By 2011 the energy costs over the life of a server will exceed the purchase price

– Half of all data centers are already power constrained and unable to expand

– EPA estimates 10 new power plants will be required by 2011 just to support US data center growth

– By 2011, powering US data centers will be responsible for ~70M metric tons of atmospheric CO

2 per year

Energy Systems

Research Lab

4

Goals for Improved Power Delivery

 Higher efficiency

 Lower equipment and installation costs

 Easy integration with alternate power sources

(solar, wind, etc.)

 Applicable across entire data center (lighting, cooling, energy storage), not just compute loads

 Improved reliability

 Smaller footprint for power conversion equipment

Energy Systems

Research Lab

Motivation for improving power distribution

Power distribution - typical US data center today

MV

BLDG

PWR 480V

AC

?

UPS

480V

AC

PDU

208V

AC

L-L PSU

Rack

Server

12V

VR

Fans

Electr.

loads

Electr.

loads

5

Total

255W –

375W

Room cooling

50W – 150W

UPS

18W

PDU

4W

PSU

48W

Server fans

13W

VR

22W

~50% of power lost in power distribution

Energy Systems

Research Lab

100W

Server

480V

Optimizing Data Center Power Delivery

400V

AC/DC

400V

DC

DC/AC

F F

AC/DC

400V

DC

DC/DC

Baseline 480Vac

Direct 400Vdc

 Intel and partners working to make optimal power delivery a reality

6

>20% improvement in power delivery efficiency

Energy Systems

Research Lab

7

Facility 400Vdc

Facility 550V/48Vdc

Facility 48Vdc

Rack-level 400Vdc

Rack-level 48Vdc

Specialized AC UPS

400Vac

High efficiency AC

Baseline AC

50.0

Comparing Alternatives

~5%

~20%

55.0

60.0

65.0

Power delivery efficiency [%]

70.0

Power delivery loss reduction:

20%

60%

75.0

Key Conclusions

 400Vdc most efficient

 DC solutions simplify power management

– no harmonics or phase balancing

– easy to parallel sources

 AC solutions require additional conversions which degrade efficiency and reliability

 400Vdc requires only modest changes to existing equipment

 All techniques suffer increased losses at light loads

 48Vdc also promising, but suffers important drawbacks

– Requires ~100x more copper to distribute power

– Suffers greater conversion loss from utility to building entrance

– Other components less efficient at 48 V (e.g. lighting, adjustable speed drives,

HVAC)

Energy Systems

Research Lab

AC and DC power distribution : Benefits of 400Vdc

Why Direct 400Vdc Data Centers?

Analysis of 2009 Data Center Design*

 ~7% Facility energy savings, incl. cooling

– 7.7% at 50% load; 6.9% at 80% load

 33% Space Savings

– No PDUs, simplified switchgear

 200% Reliability improvement

– 2x lower probability of failure in 5 years

– 1000% reliability improvement if direct connect to batteries

 15% Electrical facility capital cost savings

– Electrical is ~40% of total facility cost, i.e. saves 15% of 40%

~ 6% of total

 Using fewer of the earth’s resources

– 15% Component volume reduction in every server power supply (PFC)

– Some additional reduction in battery cabinets without DC/DC ++

8

*Compared to a modern, high efficiency 480-208 Vac design

**++DC/DC assumed in other comparisons.

Energy Systems

Research Lab

9

AC and DC power distribution : Benefits of 400Vdc

And that’s not all …

 Additional benefits to DC distribution

– No phase balancing => reduces power strip & wiring complexity

– No synchronization required to parallel multiple sources

– No harmonics => no PFC circuits

– Fewer breakers required because of fewer stages

– Simplifies wiring, since only two wires required

– No need for complex interlocks - simpler procedures, less time

– Only resistive voltage drop in wires

 Additional benefits specific to higher voltage DC

– Simplifies wiring, especially at higher power densities

– Lower currents than at 48Vdc, so smaller physical wires

– Use fewer natural resources & less energy to process materials

– ~400Vdc bus in light ballasts and Adjustable Speed Drives (ASDs)

– Simpler/more efficient connection to renewable energy sources

– Photovoltaics, fuel cells, wind with variable frequency drives

Energy Systems

Research Lab

400Vdc Selection

 Why use 400Vdc and not a higher or lower voltage?

– 400Vdc link voltage already exists in power supplies

– Straightforward to extend across data center (UPS, PDU)

– Well within 600V safety limit

– Operates over standard 600V wiring and bussing systems

– Commercial solutions already emerging

10

400Vdc is a natural choice – efficient, safe, and commercially easy to adopt

Energy Systems

Research Lab

Intel facility for comparisons

11

 Two-story, vertical flow-through air design

 Designed for ~500 watts per square foot

 Centralized air cooling plant

 6,000 square feet of raised metal floor (RMF) per module

 240 cabinets per module (20 network)

Energy Systems

Research Lab

Modules C - E:

Future Full

Build Out

Facility used for comparisons

Module C (Next phase)

(220 racks x 25 kW/rack)

Module E Module D Module C

5.5MW IT

Load

Loading

Dock

Facility

Electrical

Room

Utility Spine

Chilled Water

Storage Tanks

Low-Temp

Chiller

Plant

High-Temp

Chiller

Plant

High-Temp

Chiller

Plant

Expansion

Module B

3.3MW IT

Load

Module A

3.3MW IT

Load

Modules A - B:

Existing

(220 racks x

15 kW/rack)

400Vdc proposal for Module C

- Intel

- Emerson Network Power

- EYP Mission Critical Facilities (HP)

12

Energy Systems

Research Lab

Comparisons : Efficiency

Estimated total energy savings

 Compare proposed 480V/208Vac & 400Vdc designs for Intel facility **

13

– For 5.5MW facility

– Iso-redundant 480Vac

– Distributed-redundant

400Vdc

– Assumed 2.15% total cable loss for both

– Non-redundant and

– redundant PSU cases modeled

Cooling estimates included in total energy savings

80

75

70

65

750

625

500

375

60

55

50

250

High eff 480VAC

Facility 400VDC

Facility 400Vdc (Red PSU)

High Eff 480Vac (Red PSU)

Total savings [kW]

125

0

0 10 20 30 40 50 60 70 80 90 100

Load [%] *Facility savings includes cooling power

400Vdc is the highest efficiency choice.

~7.5% Energy savings compared to 480/208Vac distribution

** Results will vary for different facilities and for different AC architectures

Energy Systems

Research Lab

AC versus DC distribution

MV

480V

AC

AC/DC

Chrg

Efficient AC Systems

UPS

DC/AC

PDU

208V

AC

L-L

AC/DC

400V

DC

DC/DC

PSU

Rack

12V

VR

Server

 Specialized UPSs avoid double conversion

• Include Delta conversion and Eco-mode double conversion

 End user concerns about line disturbance susceptibility remain

 480V/277Vac directly to PSU (server) has been proposed

 Remove PDU transformer

 Expect power supply to be more efficient than at 208V/230Vac

 Efficiency data not yet available

 Need new power supply since bus voltage > 430Vdc required

14

AC Claims it can be only 4-6% less efficient than DC

… But at what cost?

Energy Systems

Research Lab

AC and DC power distribution

Facility-level 480V/208Vac & 400Vdc

MV

480V

AC

UPS

AC/DC

Chrg

Bypass

DC/AC

208V

AC AC/DC

380-

410V

DC

DC/DC

PSU

12V

VR

Rack

Server

MV

Battery cabinet(s)

480V

AC

Rect

AC/DC

PDU

400V

DC

400V

DC

DC/DC

12V

VR

DC/DC PSU

Server

Battery cabinet(s)

PDU

Rack

 Proposed distribution bus of 400Vdc directly connected to batteries

 Optionally: Batteries connected through bi-directional DC/DC

– Battery voltage can be optimized since not directly connected to bus

15

Energy Systems

Research Lab

16

Direct connection of batteries to 400Vdc bus

480V

AC

Rect

AC/DC

400V

DC

(float)

400V

DC

DC/DC

12V

VR

Chrg PSU

Server

Battery cabinet(s)

Rack

 Batteries connected directly to the distribution bus

– Increased reliability

– Space and cost savings

 This implies a wide input range DC/DC

 UPS mostly used only till generators on-line, 30sec - 2min

– Typically size banks for 5 minutes  won’t reach discharge voltage

– Prototypes rated at 350Vdc for continuous operation

– Standard DC/DC designed to operate 20msec at 300V, bench test showed capable of running several hours at 320Vdc

Recommended implementation Energy Systems

Research Lab

17

400Vdc concept : Energy savings

Energy savings at rack

 Rack power reduced with higher efficiency PSU

– 400Vdc rack power ~ 0.98 x 208Vac rack power

 400Vdc power supplies are prototypes from Delta Electronics

– Will be able to optimize further, but not significantly so

100

95

90

85

80

75

0 0.2

Typical operating range

0.4

Load [pu]

0.6

2.5

2

1.5

1

208V ac eff

400V dc eff

400V dc est

Eff delta

Est eff delta

0.8

0.5

1

0

100

95

90

85

80

75

0 0.2

Typical operating range

0.4

Load [pu]

0.6

1

0.98

0.96

0.94

208V ac eff

400V dc eff

400V dc est

Pin ratio

Est Pin ratio

0.8

0.92

1

0.9

Energy Systems

Research Lab

Results & Comparisons

Data Center Facility AC design

AC design requires 50% more space for 5.5MW than 3.3 MW IT load

Module E Module D

Utility Spine extension

Module C

5.5MW IT

Load

Loading

Dock

Utility Spine

Facility

Electrical

Room

Chilled Water

Storage Tanks

High-Temp

Chiller

Plant

Module B

3.3MW IT

Load

Module A

3.3MW IT

Load

Low-Temp

Chiller

Plant

High-Temp

Chiller

Plant

Expansion

400 Vdc design can fit in the same space as 3.3MW facility

18

33% Space Savings: Fits within original Module C footprint

Research Lab

Results & Comparisons: Reliability

Reliability Analysis

 Relex calculations by EYP Mission Critical Facilities

Option Availability

AC Tier IV configuration

DC configuration **

DC Improvement

0.999996

0.999998

Unavailability Probability of failure in 5 years

3.9 e -06

2.4 e -06

62.5%

13.63%

6.72%

200%

2X lower probability of failure compared to equivalent Tier IV AC facility

19

** Reliability numbers for Rectifier from simulation of power train only, will be lower with all components included.

Assumes DC/DC converter between Battery & Bus – will be higher reliability in systems without converter.

Energy Systems

Research Lab

Relative Electrical Cost Comparison

Description Ratio Remarks

Labor

Materials

AC Data

Center

[pu]

0.193

0.215

DC Data

Center

[pu]

0.156

0.227

Owner furnished items

Electrical Cost of

Work (COW)

0.592

1.0

0.467

0.85

0.8

Due to smaller wiring sizes

1.06

Wire, pipes, Supports, Panel boards,

Busways etc

0.79

Equipment, UPS, static switches, transformers, etc.

Total cost to implement all the electrical work including equipment

UPS / Rectifier

480/208V

Transformers

Server Power

Supply

AC

1.0

1.0

1.0

DC

0

Remarks

0.83

Inclusive of batteries, DC/DC converter, input & output switchgear

Distribution transformers are eliminated in DC Data Center

1.0

Assumed same cost although 6% reduction in BOM cost estimated

20

Electrical cost for dc Data Center estimated 15% lower than for ac

Cost comparison for a 3.3 MW load rather than the 5.5 MW load due to available data.

Cost estimate for maturity, i.e. high volume.

Energy Systems

Research Lab

Power Supply Unit Volume Reduction

 “In typical high-power-density ac/dc power supply 60-65% of volume is taken by

EMI filter, PFC, and bulk capacitors”

Estimate ~15% for PFC stage

3 kW / 48 V

25 W/in 3

1U

BULK CAPS

DC/DC OUTPUT

STAGE

PFC

(no longer needed)

21

EMI FILTER

15% Fewer Components by Volume – Conserving the Earth’s Resources

M. Jovanovic, APEC 2006 keynote

Energy Systems

Research Lab

22

Making Direct 400Vdc a reality?

 Need new/modified equipment

– Much equipment already exists for other industries

 May need new standards

– International Standards already exist

– Unfamiliarity in the Server Industry can leave standards open to interpretation, so have to engage local authorities

 Market acceptance

– Need end users to demand it

– Put it in your Request for Proposals

Energy Systems

Research Lab

Equipment : PSU

400Vdc Server

 For servers, only power supply enabling required

 Remove PFC stage, re-use existing DC/DC stage

 Enabling circuit proposed only for input current > 5A

90 – 264Vac

50/60 Hz AC fuse

L

BOOST

+

EMI

Filter

(AC) s

BOOST

C

O

GND

400Vdc

GND

DC/DC

Chassis

-

Modified supply to accept 400Vdc input

DC fuse

EMI

Filter

(DC)

+

DC/DC

C

O

Chassis

EN

-

23

Energy Systems

Research Lab

12V

12V

24

Equipment : PSU

400Vdc Appliance Coupler

 Current PSU prototypes from Delta use Anderson Power

Products connector from their PowerPak series

– Power contacts rated for up to

30A @ 600V (Intel’s version is rated 10 A)

GND

(make first)

+ 400Vdc

– connectors have UL, CSA and TUV approvals.

– receptacle fits standard chassis opening for IEC320 C22 inlet

400Vdc return

Enable

(make last, break first)

 For the next step

– Receptacle compatible with the

IEC320 C14 chassis opening

– Molded rather than “modular” plug for reduced costs

– Proposed 15A continuous rating

– Expect 5 – 8A disconnect rating

– Prototype under development

– Will include 48Vdc keying option

Energy Systems

Research Lab

25

Equipment : CDU

400Vdc rack power strip

 No phase balancing

 IEC 309 connector

– Standard for international AC power strips

– Rated for hot disconnect

– Recommend mechanical interlock

– IEC specified for >250VDC

– Not currently UL listed in the US

Energy Systems

Research Lab

Comparisons : Efficiency

Elegance in distribution

 Expect lower conduction losses : 5 vs. 10 breakers

480Vac

3W + Grd

280Vac

4W + Grd

AC UPS

4000A

1600A

1600A

600A

12.47kV

12.47kV

10 breaker in series

480Vac

3W + Grd

2500A

1000A

DC UPS

Load

Bank

3000A

400Vdc

2W

Floor

Box

Busduct

26

5 breaker in series

** It may be possible to eliminate the 2,500A breaker at rectifier input

Energy Systems

Research Lab

100A

27

Maintenance

Maintenance

 Personnel access equivalent to AC system

 Power supply/server replacement

– Appliance couplers will have UL, CSA and TUV approvals

 Rack connection and disconnect

– DC rated IEC 309 or Anderson connectors

– Rated for hot disconnect, but propose mechanical interlock

 Rectifier servicing same as AC UPS

– Addressed by ability to isolate each rectifier

Energy Systems

Research Lab

28

Summary Vision

DC

300-

400V

Direct 400Vdc Facility Vision

Vs. Current

 28% Energy Savings

DC/DC DC/AC

Ballast

Lighting loads

AC/DC

60 Hz AC

480V AC/DC

Vs. Best AC

 7% Energy Savings

 15% Less Capital Cost

 15% fewer PSU components

 33% Datacenter Space Savings

 200% Reliability Improvement

DC/DC

Electronic loads

VR

PSU

Motor loads

DC/AC

ASD

Energy Systems

Research Lab

29

Energy Systems

Research Lab

Download