DAVID THOMAS QC David Thomas QC Keating Chambers, London Standard form construction and engineering contracts: current and recent developments One of the perceived benefits of standard forms of contract is stability. If successful, they are widely used in the industry and will become familiar. Parties and their advisers are used to their features, including general standpoint and tone, physical layout and any individual provisions which need scrutiny and may require amendment. While no contract will be uniformly acclaimed, familiarity leads to acceptance and a sense of ‘comfort’. I t is a matter of some significance when a standard form is changed. The UK has seen major changes in its principal forms within the last few months and those engaged in international work are awaiting the new edition of the FIDIC suite currently in the course of preparation. JCT 2011 The Joint Contracts Tribunal (JCT) is the most widely used of the British1 domestic forms of construction contract. JCT produces one of the biggest suites of contract documents in the world, with a whole range of different agreements from Minor Works, via Intermediate up to the Major Project Construction Contract and through a variety of pricing and procurement options: Design and Build, Management, Prime Cost, Measured Term, With and Without Quantities, as well as specialist Repair and Maintenance and Homeowner contracts. JCT has now produced its 2011 edition of the suite, which supersedes JCT 2005. This became the current edition on 1 October 2011. The date is significant because the main driver behind the revision was the effect of the Local Democracy Economic Development and Construction Act 2009 (‘LDEDC Act’) upon contracts entered into since that date. The LDEDC Act includes, among much unrelated material, amendments to the Housing Grants Construction and Regeneration CONSTRUCTION LAW INTERNATIONAL Volume 7 Issue 2 June 2012 Act 1996 (‘HGCR Act’) which since 1998 has imposed mandatory provisions on those (many) construction contracts caught by it, in relation to adjudication of disputes and mechanisms for payment. JCT produced amendments reflecting the LDEDC Act provisions in 2009 and these have been incorporated into the 2011 edition to coincide with the impact of the Act on post1 October 2011 contracts. JCT has also taken the opportunity for some other revisions, much of which can be characterised as ‘tidying’. ICE and Infrastructure Conditions of Contract The latter part of 2011 saw the conclusion of a remarkable train of events at the Institution of Civil Engineers (ICE). After over 60 years of publication, on 1 August 2011, the ICE officially withdrew its form of contract, which was in its 7th edition (1999). The ICE Contract was one of the best-known of the traditional engineer-based forms of contract and was indeed the original basis of the FIDIC suite; the 1957 1st Edition of the Red Book closely followed the ACE (Association of Consulting Engineers) form, which was a version for international use of the ICE 4th edition. The decision to withdraw the ICE forms was taken in 2009 by the Institution’s Council and appears to have generated some dissension amongst membership. It has two major 33 DAVID THOMAS QC consequences of note for industry users. First, perhaps to propitiate the dissenters who remain loyal to the traditional model, a successor to the ICE forms has been published jointly by the ACE and the Civil Engineering Contractors Association (CECA). The new suite, which includes Design and Construct, Measurement and Ground Investigation versions, has been named the Infrastructure Conditions of Contract.2 It too takes into account the LDEDC Act amendments and so can be regarded as ‘Construction Actcompliant’. The ACE and CECA launched the new suite on 1 August 2011, referring, presumably without intention of irony, to its basis in the ‘highly successful ICE Conditions of Contract’. Secondly, the withdrawal of the ICE suite has meant that the only form endorsed by the Institution is now NEC3. NEC3 There is no new edition of the New Engineering Contract (NEC), the current 3rd edition having been introduced in 2005. However, it continues to command widespread attention, not least because of its use on high-profile projects, the most notable of which is currently the London 2012 Olympic site. This has only been increased by its new status as the sole contract endorsed by the ICE, as explained above. It had also been the sole contract endorsed by the Office of Government Commerce (OGC) for public sector projects until the Arup Review at the end of 2008 also considered the merits for collaborative contracting purposes of the Project Partnering Contract and the JCT’s Constructing Excellence form. It is still much favoured in public sector circles and has also been used by Sainsbury’s for its supermarket construction and internationally, for example, on Abu Dhabi’s Al Raha Beach Development. It is not the case that all the attention focused on NEC3, however, is adulatory. The unique ‘narrative’ style of the text, for example, clause 30.3, ‘[t]he Contractor does the work so that the Condition stated for each Key Date is met by the Key Date’, continues to trouble lawyers and, apparently, judges. In Anglian Water Services Ltd v Laing O’Rourke Utilities Ltd [2010] EWHC 1529 (TCC), Mr Justice Edwards-Stuart in the Technology and Construction Court said that he had ‘[n]o doubt this approach to drafting has its adherents within the industry but... from the 34 point of view of a lawyer, it seems to me to represent a triumph of form over substance’. Notwithstanding criticism, NEC’s position as an alternative approach to engineering and construction3 contracts looks unassailable and its influence is likely only to grow. Keating on NEC3, by this author and a team from Keating Chambers, will be published by Sweet & Maxwell in May 2012. FIDIC A full appreciation of FIDIC developments must await the comprehensive review of the ‘Rainbow’ suite understood to be moving towards a new edition in 2013, which will be FIDIC’s centenary year. It is sufficient for present purposes to note the introduction in October 2011 of the official 1st Edition of the Sub-Contract, for use with the 1999 Red Book and Multilateral Development Bank (MDB) version of the Red Book, sometimes referred to as the Pink Book. The formal launch of the new Sub-Contract is the conclusion of the process begun by the introduction of the Test Edition in December 2009. Conclusion Nor mally, the life of standard for m construction and engineering contracts is characterised by the stability which is a main part of their attraction. The last few months have been a period of almost unprecedented change in this respect in the UK. Practitioners who advise the industr y on choices and interpretation of contracts are having to adapt to the features of the new landscape. Notes 1It should be noted in referring to ‘British’ or ‘UK’ forms that the Scottish Building Contract Committee is a member of the JCT and is responsible for adapting JCT contracts for use in Scotland and drafting Scottish documents where required. 2The infelicitous abbreviation to ICC opens up the possibility of confusion with the Model Turnkey Contract for Major Projects of the International Chamber of Commerce. 3 It should be noted that the title of the principal contract is the Engineering and Construction Contract; it is intended to be both. David Thomas QC is a member of Keating Chambers in London. He practises in the UK and internationally. His special areas of expertise include construction, engineering, infrastructure, energy and technology projects. CONSTRUCTION LAW INTERNATIONAL Volume 7 Issue 2 June 2012