SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM & PROJECT MANAGEMENT SECTION 6: QUALITY ASSURANCE APPROVED: PROCEDURE: PM 6.01 DATE: 7/31/13 TITLE: QUALITY ASSURANCE PROGRAM REVISION: 4 1. POLICY A successful Quality Management program results in facilities that work and are operable and maintainable. To maximize the ability to meet budgets and schedules, the Project Team, including Operations, must support and comply with the requirements and conditions of this program. The QA and Quality Control (QA/QC) activities described in this procedure apply to all capital improvement projects managed by Project Managers (PMs) from the Project Management Bureau (PMB), regardless of the work being produced internally by EMB, by other SFPUC Divisions, other City Departments, or consultants. The extent of these activities for the program as a whole, determined by the Infrastructure Division Bureau Managers, or for each individual project must be identified in the Project Management Plan. This way QC and QA activities are identified, and schedule, budget, and resources can be agreed on. Emergency contracts, Job Order Contracts (JOCs), and projects not managed by a PMB PM are exempt from this procedure’s requirements. 2. DEFINITIONS 2.1 Quality Control (QC): Those functions of quality management that are focused on fulfilling project requirements. For planning, design, and bid package preparation, QC is the responsibility of each Project Team, for thorough checking, inspection, testing and timely feedback to ensure that necessary corrective actions are taken. 2.2 Quality Assurance (QA): Those functions of quality management that are focused on providing confidence that the QC requirements are being fulfilled. The goal of QA is to achieve and maintain technical excellence through the establishment of organizational responsibilities and implementation of approaches to verify that QC activities are occurring in accordance with procedures implemented by each Project Team. QA activities ensure the Page 1 of 8 delivery of projects that will meet the requirements of the Operations Division and applicable regulatory agencies. 2.3 Quality Assurance Audits (QA Audits): QA Audits are planned and systematic verifications necessary to provide sufficient confidence that each Project Team consistently implements procedures and performs and properly documents QC activities. 2.4 Quality Management (QM): Uses measures and various types of project reviews to ensure the technical quality, completeness and accuracy of work products. It is a useful tool to manage the risks of design errors and omissions and minimize construction changes and claims. Refer also to Definitions List (eDOCS DM #488573) for other Definitions and Responsibilities. 3. RESPONSIBILITIES 3.1 Project Teams perform both QA and QC functions. 3.2 Assistant General Manager (AGM), Infrastructure Division, oversees the Infrastructure Division QA Program to enforce and ensure compliance to the requirements of Infrastructure Division Policies, Procedures, and Standards. 3.3 Project Management Bureau (PMB), Engineering Management Bureau (EMB), Construction Management Bureau (CMB), Contract Administration Bureau (CAB), and Bureau of Environmental Management (BEM) are responsible for enforcing and ensuring compliance to the QA requirements for their respective Bureau’s deliverables. Similarly, other City Departments, operations, and consultants are likewise responsible. 3.4 Chief Engineer—Quality & Standards (CEQS) is responsible for managing the Infrastructure Division QA Section (IQA). IQA is responsible for QA audits, administration of the Infrastructure Division Procedures, QA training and assistance for QA support, and verification of the official Project Reviews as listed in Attachments 1.0, 1.1 and 2. 4. IMPLEMENTATION The development of projects must include QA and QC activities, documented in the Project Management Plan (PMP). Project Teams perform the bulk of QC activities and also some QA activities while personnel outside a given project perform the bulk of the QA Activities. QC activities are embedded into the Infrastructure Division Procedures for designs. Thus, a work deliverable should be referenced to the applicable procedure to determine the QC requirements involved. When other City Departments and consultants are doing planning, design, and PM 6.01 Quality Assurance Program, Rev. 4, Page 2 of 8 construction management of a project, they are expected to perform their work following SFPUC Infrastructure Procedures and are to submit a Quality Plan explaining how the QA and QC requirements will be met. All projects must address various QC activities in addition to the QA/QC activities in the procedures. Refer to the list of required and optional activities as listed in Attachment 1.0 or Attachment 1.1. The extent of these QC activities is determined by the Infrastructure Division Bureau Managers, based on complexity, scope, and client requirements. Any deviations from Attachment 1.0 shall also have the concurrence of the respective Capital Improvement Program (CIP) Director. The following sections address QC and QA activities for a typical project. 4.1 QC, Project Reviews In addition to the QC requirements listed in the individual Infrastructure Division procedures, the Quality Management Program for CIPs include eight (8) different reviews at various milestones of the planning and design phases of projects, as listed in Attachment 1.0. Three (3) of these reviews – Technical Advisory Panel (TAP) Review, Value Engineering (VE) Review, and Project Management Review – are optional, unless required by the CIP Director. It is critical that reviews do not impact approved project schedules (both the phase level schedules and the overall project schedules). The various reviews required at each specific milestone of the planning and design phases should therefore be planned and scheduled well in advance, coordinated, and conducted simultaneously whenever possible. In some cases it may even be advantageous and efficient to combine reviews. Durations of reviews are to be strictly enforced so as not to impact project schedules. Except for a few exceptions, individual reviews will be limited to three (3) weeks. To assist with the timely completion of all required review activities, each review must be clearly defined in the Project Management Plan (PMP) and included as a separate and distinct activity in the project schedule. The following is a brief description of each review. (1) Technical Review The Technical Review is performed by EMB, Operations, Construction Management Bureau (CMB), Bureau of Environmental Management, Health and Safety, Security, and, as applicable, Information Technology Services (ITS), consultants, DPW, and other City Departments, with the purpose of reviewing the technical adequacy of project deliverables at the planning or design phase. The scope of this review is determined by the PE, under the direction of the EMB Manager. (2) Technical Advisory Panel (TAP) Review Review performed if needed to solicit current, high-level technical input and guidance from recognized experts in specialized fields. This review allows the Project Team to PM 6.01 Quality Assurance Program, Rev. 4, Page 3 of 8 benefit from the TAP members’ experience on comparable external projects and provides a forum for consideration of innovative ideas and new design concepts and methodologies. TAPs are typically required for tunnels, dams, water treatment plants, and other complex projects, as determined by the Bureau Managers. The PE, under the direction of the EMB Manager, coordinates and oversees this review. (3) Cost Estimate Review Review performed to support the development of an accurate Engineer’s Estimate. The review to be performed at the 35% design milestone consists of checking the cost estimate prepared by the Project Team. This first review provides the data necessary to determine early whether adequate funding is available to complete the project. The review to be performed at the 95% design milestone consists of preparing a totally independent cost estimate to ensure the accuracy of the final Engineer’s Estimate. To do so, this cost estimate requires validation of the preliminary construction schedule to ensure long-lead-time purchased items and system shutdowns do reflect a reasonable time frame and are indeed accounted for in the construction schedule critical path. The PM, with the assistance of the Cost Engineer and under the direction of the project controls lead or the PMB Manager, coordinates and oversees this review. (4) Independent Technical Review Review performed by third-party multi-disciplinary experts to provide an additional guarantee of the technical soundness of the design documents. The review focuses on the engineering design presented in the drawings and specifications. The emphasis of the review varies depending on the level of completion of the design documents. It should be noted that the 95% review includes a “biddability” assessment to minimize (or eliminate) errors, omissions, and ambiguities in the design documents. The PM, under the direction of the PMB Manager, coordinates and oversees this review. (5) Constructability Review Review performed to verify and enhance the “buildability” of a project. The review evaluates the design for completeness, field efficiency and ease of construction. One main objective of the review is to eliminate impractical and inefficient designs that do not meet construction requirements as well as address construction-specific deficiencies in contract documents. The PM, with the assistance of the Review Manager and under the direction of the CMB Manager, coordinates and oversees this review. (6) Steering Committee Review Review performed when specific milestones are achieved to provide SFPUC Senior Management with the reassurance that the project as a whole is being undertaken within the parameters and guidelines established. The Steering Committee essentially provides the validation required to proceed to the next phase of a project. The Steering Committee may also be convened on an as-needed basis if a critical policy decision is required from the SFPUC Deputy General Manager (DGM) or SFPUC General Manager (GM) on a specific issue that could not be resolved through the normal chain of PM 6.01 Quality Assurance Program, Rev. 4, Page 4 of 8 command within the Infrastructure Division. The PM, under the direction of the PMB Manager, coordinates and oversees this review. (7) Value Engineering (VE) Review Review performed if needed to analyze and evaluate possibilities of significant reductions in the cost of a project. At its “highest” form VE identifies innovative ways in which project costs may be minimized by the use of new technologies, changed operational criteria, unconventional construction methods, etc. The review uses a systematic application of analytical, creative, and evaluation techniques with the objective of looking for cost savings without compromising functions, reliability, performance, or quality. The PM, under the direction of the PMB Manager, coordinates and oversees this review. (8) Project Management Review Review performed if needed to address specific issues that have not been adequately dealt with in the other required reviews. It is the discretion of the PM to initiate this additional review if he/she feels a specific issue of concern needs to be assessed further. For example, the PM may create an independent construction schedule to validate the schedule generated by the project, or to complement the findings in the 95% Cost Estimate Review which may have used but not validated the construction schedule; request a shutdown review, an Operations Plan, and/or a ITS-SCADA/ITSDCS review at the 65% and 95% design stages; or coordinate required regulatory agency review. If beneficial, the PM may also choose to include optional reviews from outside agencies (e.g., courtesy reviews by local jurisdictions or agencies) under this review category. The PM, under the direction of the PMB Manager, coordinates and oversees this review. 4.2 QA Plan PMs shall provide approved QA Plans to the CEQS within 7 calendar days of approval. 4.3 Project Bid Approval All PMs are required to complete Attachment 2 before a capital improvement project is advertised for bidding. It addresses the various planning and design QC reviews listed in section 4.1 of this procedure and requires that a higher-level review be conducted by management to ensure completeness in the design documents as they become construction contract documents and require approval by the CIP Director. PM shall provide a copy of the fully signed Project Review & Construction Contract/Bid Checklist to the CEQS. 4.4 Construction Phase Requirements in the Resident Engineer’s Project QA Plan The RE shall create a project-specific QA Plan at the beginning of the Construction Phase to address how the RE will verify Contractor compliance with the requirements of PM 6.01 Quality Assurance Program, Rev. 4, Page 5 of 8 the Specifications. Topics include, but are not limited to: Project Quality organization and authority Field quality control procedures (refer to paragraphs below) Quality personnel experience qualifications and/or training Independent materials testing firm(s) qualifications Quality orientation training of site personnel Contractor and subcontractor interface and coordination Control of special processes Type and frequency of materials testing verification Control of measuring and test equipment Control of deficiencies and non-conformances Quality records/test data control 4.4.2 Before NTP, the RE shall thoroughly review the Specifications and related codes and standards to identify unique inspection requirements, including but not limited to: Dimensional tolerances Material receiving Weld testing/certification Finish requirements Special equipment/systems Unique concrete mixes Work sequencing High voltage electrical Rotating equipment Specialty testing/inspection services Equipment testing and performance In-factory inspection/testing 4.4.3 The RE shall also review existing Construction Management procedures and criteria and shall prepare project-specific criteria where indicated. As many of the accepted codes and standards incorporate varying definitions of compliance or offer several options for acceptability, the PE shall identify and establish the acceptance level for the specific circumstance. Some considerations include, but are not limited to: Concrete surface tolerances Maximum weld inclusion or voids Tighter or looser dimension tolerances Special storage requirements Drywall finishing, straightness, and/or joint quality Defining “square and plumb” for conduit and piping runs Defining “in a workmanlike manner” to incorporate acceptable/unacceptable standards PM 6.01 Quality Assurance Program, Rev. 4, Page 6 of 8 4.5 Rough/finish grade tolerances QA The Infrastructure Division QA Section performs the following tasks to support the Quality Management Program: 4.5.1 Update Infrastructure Division Procedures – Facilitate revision to procedures with Infrastructure Division Bureaus and other PUC Divisions and programs to reflect organizational structure and policies, and to minimize inconsistencies and duplications. 4.5.2 Support CIP Quality Management Program – Assist Bureaus to establish internal QA/QC process, as requested by the AGM, and track Project Reviews listed in Attachment 1.0 or Attachment 1.1. 4.5.3 Quality Assurance Audits – Conduct project audits as determined by and on behalf of the AGM. Planning Phase: Between Final Alternative Analysis Report (AAR) and Draft Conceptual Engineering Report (CER) Environmental Phase: Six (6) months before first Administrative Draft of Environmental Impact Report or Negative Declaration Design Phase: Before 50% Design (midpoint of 35% and 65% design milestone dates) Construction Phase: 20% elapsed time from start of construction (subject to requirements by CIP Director) Note: Additional random audits may be performed at the discretion of the CEQS or AGM, Infrastructure Division. 4.6 Training – With input from Infrastructure Division Bureau Managers and Operations Divisions, identify training needs regarding procedures tailored for specific Bureaus, and assist in the training effort. 5. REFERENCES PM 2.01 Project Development Process PM 2.02 Project Management Plan PM 6.02 Quality Assurance Audits PM 6.01 Quality Assurance Program, Rev. 4, Page 7 of 8 6. ATTACHMENTS (1.0) Project Reviews for Planning and Design Phases (1.1) Water R&R and Wastewater R&R Project Reviews for Planning and Design Phases (2) Project Review and Construction Contract/Bid Checklist (eDOCS DM #840490) PM 6.01 Quality Assurance Program, Rev. 4, Page 8 of 8 ATTACHMENT 1.0 – PROJECT REVIEWS FOR PLANNING AND DESIGN PHASES Project Reviews for Planning and Design Phases Bureau Lead Project Review Reviewers Budget PE Technical Review Refer to Paragraph 4.1 (1) in procedure. Engineering Design Fees PE TAP Review Outside Dam and Tunnel Experts Engineering Design Fees Program Controls 2 or Consultant Project Management Engineering Design Fees Engineering Design Fees EMB CE RM RM PM PMB PM PM 1 Cost Estimate Review Independent Technical Review Constructability Review Steering Committee Review Value Engineering 1 Review Project Management 1 Review Consultant 2 CMB and 2 Consultant Selected Infrastructure Division Managers Consultant Varies 2 Schedule AAR, CER SubPhase or Design Phase AAR, CER SubPhase or Design Phase Project Mgt Sub-Phase Project Mgt Sub-Phase Project Mgt Sub-Phase N/A Project Mgt Sub-Phase Engineering Design Fees Project Mgt Sub-Phase Project Management Project Mgt Sub-Phase Planning Design AAR CER DCR 35% 65% 95% As-Needed 2 PE PM PMB RM TAP - As-Needed List of Acronyms: Alternative Analysis Report Cost Engineer Conceptual Engineering Report Construction Management Bureau Design Criteria Report Engineering Management Bureau Health and Safety As-Needed Review to be conducted on as-needed basis only (i.e., review will not be required for all projects). Via Consultants through various contracting means as determined by the Program Manager and/or Bureau Managers. AAR CE CER CMB DCR EMB H&S - Footnotes: 1 Project Engineer Project Manager Project Management Bureau Review Manager (in Program Controls) Technical Advisory Panel PM 6.01 Quality Assurance Program, Attachment 1.0, Rev. 4, Page 1 of 1 ATTACHMENT 1.1 – WATER R&R AND WASTEWATER R&R PROJECT REVIEWS FOR PLANNING AND DESIGN PHASES Water R&R and Wastewater R&R Project Reviews for Planning and Design Phases Bureau 3 EMB Lead Project Review Reviewers Budget PE Technical Review Refer to Paragraph 4.1 (1) in procedure. Engineering Design Fees CE PM PMB PM Cost Estimate Review Constructability Review Project Management 1 Review Program Controls 2 or Consultant 3 CMB and 2 Consultant Varies 3 Schedule Project Management Engineering Design Fees AAR, CER SubPhase or Design Phase Project Mgt Sub-Phase Project Mgt Sub-Phase Project Management Project Mgt Sub-Phase Planning AAR CER Design DCR 35% 2 3 AAR CE CER CMB DCR DPW EMB H&S - Alternative Analysis Report Cost Engineer Conceptual Engineering Report Construction Management Bureau Design Criteria Report Department of Public Works Engineering Management Bureau Health and Safety PE PM PMB RM R&RTAP WWE - Project Engineer Project Manager Project Management Bureau Review Manager (in Program Controls) Renewal and Replacement Technical Advisory Panel Wastewater Enterprise PM 6.01 Quality Assurance Program, Attachment 1.1, Rev. 4, Page 1 of 1 As-Needed Review to be conducted on as-needed basis only (i.e., review will not be required for all projects). Via Consultants through various contracting means as determined by the Program Manager and/or Bureau Managers. Responsible Bureau can include DPW and Wastewater Enterprise for projects led by those organizations. List of Acronyms: 95% Footnotes: 1 65% ATTACH. 2 – PROJECT REVIEW & CONSTRUCTION CONTRACT/BID CHECKLIST PROJECT REVIEW & CONSTRUCTION CONTRACT/BID CHECKLIST PROJECT INFORMATION Project Name: Project No.: Contract Name: Contract No.: Region: Date: Design Performed By: (check all that apply) SFPUC-EMB City Department Consultant(s) - List below Name of Prime Consultant(s): Name (and Firm/Organization) of Engineer of Record: REQUIRED PLANNING & DESIGN PHASE REVIEWS Technical Reviews All Completed Some Completed None Completed AAR: By: Date: 35%: By: Date: CER: By: Date: 65%: By: Date: DCR: By: Date: 95%: By: Date: Cost Estimate Reviews 35%: By: All Completed Date: Independent Technical Reviews All Completed 35%: By: Date: 65%: By: Date: Constructability Reviews All Completed 35%: By: Date: 65%: By: Date: Steering Committee Reviews All Completed AAR: By: Date: CER: By: Date: Some Completed 95%: By: Some Completed 95%: By: Some Completed 95%: By: Some Completed 95%: By: None Completed Date: None Completed Date: None Completed Date: None Completed Date: Important: If "All Completed" box is not checked for all required reviews, attach explanation to checklist. AS NEEDED REVIEWS Technical Advisory Panel (TAP) Reviews Completed Not Completed Completed Not Completed Completed Not Completed Briefly Describe Reviews: Value Engineering Reviews 35%: By: Date: Project Management Reviews Briefly Describe Reviews: PM 6.01 Quality Assurance Program, Attachment 2, Rev. 4, Page 1 of 2 ATTACH. 2 – PROJECT REVIEW & CONSTRUCTION CONTRACT/BID CHECKLIST May substitute specific Program titles, where they occur (e.g., “SSIP Shutdown Coordinator”) May substitute specific Program, where occurs (e.g., “SSIP” instead of “CIP”) PM 6.01 Quality Assurance Program, Attachment 2, Rev. 4, Page 2 of 2