CONTRACT NO: T-12-16 ELECTRICAL DATE: August 2012 . DIVISION 16 – ELECTRICAL Division 16 2011-03-15 Page 1 of 1 CONTRACT NO: T-12-16 TABLE OF CONTENTS DATE: August 2012 SECTION NO. 16010 16015 16016 16020 16031 16050 16060 16122 16130 16131 16136 16141 16146 16221 16263 16271 16289 16330 16335 16339 16345 16346 16414 16441 16505 16620 16670 Division 16 2011-03-15 Page 1 of 1 SECTION NAME ELECTRICAL GENERAL REQUIREMENTS ELECTRICAL SYSTEMS ANALYSIS STAGING AND TRANSITION DEMOLITION OF ELECTRICAL SYSTEMS INSPECTION AND TESTING BASIC MATERIALS & METHODS GROUNDING WIRES AND CABLES 0-1000V RACEWAYS SPLITTERS, JUNCTION, PULL BOXES AND CABINETS CABLE BUS FEEDER SYSTEM WIRING DEVICES ELECTRIC VEHICLE CHARGING STATION THREE PHASE INDUCTION MOTORS ADJUSTABLE SPEED DRIVES FOR 5Kv motors DRY TYPE TRANFORMERS UP TO 600V PRIMARY TRANSIENT VOLTAGE SURGE SUPPRESSION (TVSS) 27.6 kV SWITCHGEAR MODIFICATIONS TEMPORARY AND TRANSITION ELECTRICAL EQUIPMENT STATION BATTERY & CHARGER SYSTEM 4160V MEDIUM VOLTAGE SWITCHGEAR MEDIUM VOLTAGE SOLID STATE STARTERS DISCONNECT SWITCHES – FUSED AND UNFUSED PANELBOARD BREAKER TYPE LIGHTING EQUIPMENT EMERGENCY POWER GENERATORS LIGHTING PROTECTION SYSTEM CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 PART 1. 1.1 1.2 1.3 Section 16010 2006-08-30 Page 1 of 16 GENERAL General .1 These general instructions are intended to supplement and not to replace the requirements of Division 1 – General Requirements. .2 The requirements of this Section apply to, and form part of, all Sections of Division 16 – Electrical. .3 The Specifications are divided into Divisions of Work and any Division may consist of the Work of more than one Subcontractor. The responsibility as to which Subcontractor provides labour, materials, equipment, and services required to complete the Work rests solely with the Contractor. .4 These Specifications define the requirements of equipment to be provided as part of this Contract, including the supply of the following major items to make up the new electrical system and the system transition requirement: .1 Incoming 27.6kV hydro feeders are configured in basic primary selective system and are required to be reconfigured to two source primary system. .2 One (1) 5 kV Secondary Switchgear with 3,000 kW standby diesel generator set, ATS and the associated distribution system. This will be used for transition from the existing system to the new system. .3 Three (3) new Standby Diesel Generators each 2000 kW complete with generator panels and energy management system. .4 Two new 5kV VFDs for Pump Nos. 2 and 5. .5 Two new motors for existing Pump Nos. 1 and 6. .6 Four new soft starters for existing Pump Nos. 1, 3, 4 and 6. .1 The requirements of this Section apply to and form part of all sections of Division 16 – Electrical. .1 Electrical and Electronic Manufacturers Association of Canada (EEMAC) .2 National Electrical Manufacturers Association (NEMA) .3 Institute of the Electrical and Electronic Engineers (IEEE) .4 Insulated Cable Engineers Association (ICEA) Related Sections References CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 1.4 1.5 Section 16010 2006-08-30 Page 2 of 16 .5 Canadian Gas Association (CGA) .6 Underwriters Laboratories Canada (ULC) .7 American National Standards Institute (ANSI) .8 National Fire Protection Agency (NFPA) .9 Canadian Standards Association (CSA) .1 CSA C22.2 No. 0 General Requirements - Canadian Electrical Code - Part 2 .2 CAN3-C235 Preferred Voltage Levels for AC Systems, 0-50,000 V .10 The Contractor shall comply with the latest editions of CSA C22.1 Canadian Electrical Code - Part 1, Ontario Electrical Safety Code (OESC) and Bulletins, and local codes and requirements which govern the installation. Where these regulations conflict, comply with the most stringent requirements. .11 The Contractor shall comply with latest editions of the CSA Certification Standards and Bulletins. .1 Perform a complete installation in accordance with CSA C22.1-06 except where specified otherwise in the Contract Documents. .2 Construct overhead and underground systems in accordance with CSA C22.3 No.1-1993 except where specified otherwise in the Contract Documents. .3 Abbreviations for Electrical Terms: Conform to CSA Z85-Latest Edition. .4 Ontario Electrical Safety Code and all bulletins. .5 Building Code of Ontario, O.Reg 413/97, Latest Revision. .6 Perform all grounding in accordance with CSA C22.3 No. 2. .7 IEEE 519 for total harmonic distortion, Latest Revision. .1 The following are definitions used in Division 16 Electrical. Refer also to Division 1 – General Requirements. .1 Inspection Authority means agent of Ontario Electrical Safety Authority which has jurisdiction, over construction and safety standards associated with any part of electrical site work. .2 Supply Authority (Power Stream Inc.) means electrical power company or commission Codes and Standards Definitions CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 .3 .4 1.6 1.7 1.8 Section 16010 2006-08-30 Page 3 of 16 responsible for delivering electrical power to the Site. Electrical Code or Code means the Ontario Electrical Code in force at the Site. CEC means latest edition of the Canadian Electrical Code. Design Requirements .1 Operating voltages shall be within those defined in CAN3C235. .2 Motors, electric heating, control and distribution devices and equipment to operate satisfactorily at 60 Hz, within normal operating limits established by CAN3-C235. Equipment must be able to operate in extreme operating conditions established by CAN3-C235, without damage. .3 Verify before energization that equipment supplied under this contract or by the Region is compatible with related electrical power supply system. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16010 – Electrical General Requirements as indicated in Schedule ‘A’ of the Bid Form. .1 Shop Drawings .1 The Contractor shall submit shop drawings, catalogue cuts and descriptive literature as described in Section 01300 – Submittals. Include the following: 1. Layouts of equipment and dimensional drawings, including weights. 2. Layouts of switchgear, generator enclosure, master control panel and control station components. Schematic and wiring diagrams indicating 3. wire and terminal numbers, including 120 VDC and 24 VDC battery systems. 4. Time - current characteristics and setting range data of protective devices in switchgear, panelboard. 5. Interconnection wiring diagrams. Include equipment supplied under work of other Sections, by Regions or under separate contracts. Measurement and Payment Submittals CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 6. 1.9 Section 16010 2006-08-30 Page 4 of 16 Bills of Material. .2 Record Drawings .1 The Contractor shall include with record drawings, a list of motors indicating motor or equipment numbers, service description, nameplate voltage, power (kW) and current, size of overload and protection device rating for each motor. .2 The Contractor shall indicate on record drawings, exact dimensioned locations of buried services and embedded or concealed conduits in floors and masonry walls. .3 Where cable trays and lay-in ducts are not detailed, the Contractor shall submit scaled and dimensioned record layout drawings of runs. .3 Electrical Systems Diagrams .1 The Contractor shall submit a grounding system single line diagram. Clearly indicate points of connection to grounding electrodes. Demonstration and Training .1 Instruct the Region’s personnel in the operation, care and maintenance of equipment. Perform demonstration and training in accordance with Section 01820 – Demonstration and Training. .1 Operating voltages: in accordance with CAN3-C235-83. .2 All motors, electric heating, control, and distribution devices and equipment shall operate satisfactorily at 60 Hz within the normal operating limits established by the above noted standard. The equipment shall operate in the extreme operating conditions established in the above standard without any damage to the equipment. .1 Submit to the Electrical Safety Authority (ESA) and Supply Authority necessary number of drawings and specifications for examination and approval prior to commencement of work. .2 Pay associated fees for review, permits and inspection. .3 The Consultant will provide drawings and specifications required by Electrical Safety Authority at no cost. 1.10 Voltage Ratings 1.11 Permits, Fees and Inspection CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 Section 16010 2006-08-30 Page 5 of 16 .4 Notify the Consultant of all changes required by the Electrical Safety Authority (ESA) prior to making the changes. .5 Upon completion of the Work, provide Certificates of Acceptance from the Electrical Safety Authority (ESA) to the Consultant. .6 Arrange for inspection of all Work by applicable authorities having jurisdiction over the Work (ESA, Power Stream Inc., or TSSA). On completion of the Work, provide the final unconditional certificate of approval to the Region. .7 Comply with the requirements of the latest edition of the applicable CSA Standards, the requirements listed in subsection 1.3, and codes and standards listed in subsection 1.4 of this Section. These codes and regulations constitute an integral part of these specifications. In case of conflict, the codes take precedence over the Contract Drawings. Otherwise follow the standards established by the Contract Drawings and specifications. .8 Before starting any Work, submit the required number of copies of drawings and specifications to the ESA. Comply with any changes requested as part of the Contract, but notify the Consultant immediately of such changes for proper processing of these requirements. Prepare and furnish any additional drawing details for information as may be required. .1 The Contractor shall submit installation and energization certificates from manufacturers of transformers, switchgear, bus duct, variable frequency drive systems, motor control centres, power panel boards, luminaires, emergency power systems, control systems and life safety systems. .2 The Contractor shall submit electrical equipment or system warranty certificates. .3 The Contractor shall report motor full load amps, type and size of overload heaters installed, breaker trip settings, fuse ratings and sizes of fuses in control circuits. .4 The Contractor shall report circuit insulation resistance. The Contractor shall report on coordination of .5 protective devices, including recommended and final field setting data and certified field test data. CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 Section 16010 2006-08-30 Page 6 of 16 1.12 Materials and Equipment .1 Provide all materials and equipment in accordance with Section 01600 – Material and Equipment. .2 All equipment and material shall be CSA certified. Where there is no alternative to supplying equipment which is not CSA certified, the Contractor shall obtain special approval from the Electrical Safety Authority (ESA). .3 Factory assemble all control panels and component assemblies. .1 Coordinate the electrical requirements of motors, equipment and mechanical Work with concerned disciplines and ensure the electrical system is appropriate controls. .2 Complete all electrical and control wiring for all equipment specified in Division 11 – Equipment, Division 15 – Mechanical and Division 13 – SCADA and Instrumentation 1.13 Electric Motors, Equipment and Controls 1.14 Finishes .1 Shop finish metal enclosure surfaces by the application of a rust resistant primer on the inside and outside, and a minimum of two coats of finish enamel. .1 Paint outdoor electrical equipment “equipment green” finish in accordance with EEMAC Y1-2-1979. .2 Paint indoor switchgear and distribution enclosures light grey in accordance with EEMAC 2Y-1-1958. .2 Clean and touch up any surfaces of shop-painted equipment which have been scratched or marred during shipment or installation, to match the original paint. .3 Clean and prime exposed non-galvanized hangers, racks and fastenings in order to prevent rusting. .1 Identify electrical equipment with nameplates as follows: .2 Nameplates: .1 Lamicoid 3 mm thick plastic engraving sheet, white face, black core, mechanically attached with self tapping screws. .2 Do not use self adhesive nameplates. 1.15 Electrical Equipment and Panel CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 .3 Section 16010 2006-08-30 Page 7 of 16 Use rivets and/or nuts and bolts where access may conflict with a protruding screw point. .3 Nameplate lettering sizes unless otherwise indicated in the Contract Documents: 1. Switchgear main nameplate: 25 mm individual components: 8 mm control devices, indicators: 3 mm 2. Control Panels main nameplate: 25 mm individual devices: 3 mm 3. Miscellaneous System Panels main nameplate: 13 mm individual devices: 3 mm 4. Panelboards: 13 mm 5. Bus Ducts: 13 mm .4 Wording on all nameplates shall be approved by the Consultant prior to manufacture. .5 Allow for an average of twenty-five (25) letters per nameplate. .6 Identification shall be in English. .7 Nameplates for terminal cabinets and junction boxes shall indicate system and/or voltage characteristics. .8 Disconnects, starters and contactors: indicate equipment being controlled and voltage. .9 Terminal cabinets, junction, and pull boxes: indicate system and voltage. .10 Transformers: Indicate the capacity, and the primary and secondary voltages. .11 Issue nameplates lists, for review prior to manufacture. .12 Lighting panels: Plates shall be mounted on inside of door, typical identification shall be "Lighting Panel 'A' 120/208 V, 1 phase, 3 wire". .13 Disconnect switches and starters: Plates shall be mounted externally on switch box cover. Typical identification shall be "Pump No. 1, 575 V, 3 phase". .14 Plates shall be installed after all painting has been completed and shall be secured with self-tapping screws except on the inside of panel doors where gluing will be accepted. .15 Have the manufacturers' nameplates affixed to each item of equipment showing the size, name of equipment, serial number and all information usually provided, including the voltage, cycle, phase, horsepower, etc., and the name of the manufacturer and its address. Ensure that all CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 Section 16010 2006-08-30 Page 8 of 16 stamped, etched or engraved lettering on plates is perfectly legible. Do not paint over nameplates and where apparatus is to be concealed, attach the nameplate in a location on the equipment support or frame which is unobstructed and clearly visible. .16 Identify all equipment with the corresponding remote controls. .1 Labels shall be visible and legible after equipment is installed. .1 As specified in the Contract Documents and to meet requirements of the Electrical Safety Authority and the Consultant. .2 Decal signs, minimum sized 175 mm x 250 mm. .3 Protect exposed live equipment during construction in order to ensure the safety of personnel. .4 No exposed live parts are acceptable. In unavoidable circumstances during construction, notify the Consultant. .5 Shield and mark live parts "LIVE 600 VOLTS", or with the appropriate voltage in English. .1 Identify wiring with permanent indelible identifying markings, either numbered or coloured plastic tapes, on both ends of phase conductors of feeders and branch circuit wiring. .2 Maintain phase sequence and colour coding throughout. .3 Colour code: Refer to York Region Design Guidelines: Section 12A – Wiring and Cabling Tagging including as an appendix. .4 Control wiring to have same tag at both ends. .1 Lugs, terminals, screws used for termination of wiring to be suitable for either copper or aluminum conductors. 1.16 Manufacturers and CSA Labels 1.17 Warning Signs 1.18 Wiring Identification 1.19 Wiring Terminations CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 Section 16010 2006-08-30 Page 9 of 16 1.20 Single Line Electrical Diagrams .1 Provide single line electrical diagrams under plexiglass as follows: .1 Electrical distribution system: locate in main electrical room. .2 Electrical power generation and distribution systems: locate in power plant rooms. .2 Drawings: 600 mm x 600 mm minimum size. .1 Do not install outlets back-to-back in wall; allow minimum 150 mm horizontal clearance between boxes. .2 Change the location of outlets at no extra cost or credit, provided that the distance does not exceed 3,000 mm from the original location, and this information is provided to the Contractor before the installation of the outlet. .3 Locate light switches on latch side of doors. Locate disconnect devices in mechanical and elevator machine rooms on the latch side of door. .1 The mounting height of equipment is from the finished floor to the centreline of equipment unless specified or indicated otherwise in the Contract Documents. .2 If the mounting height of equipment is not specified or indicated in the Contract Documents, verify it with the Consultant before proceeding with installation. 1.21 Location of Outlets 1.22 Mounting Heights .3 Install electrical equipment at the following heights unless indicated otherwise in the Contract Documents. Local switches: 1200 mm. .1 .2 Wall receptacles: 1. General: 450 mm. 2. Above top of continuous baseboard heater: 200 mm. 3. Above top of counters or counter splash backs: 175 mm. 4. In mechanical rooms: 1400 mm. .4 Panelboards: as required by Ontario Electrical Safety Code or in accordance with the layouts on the Contract Drawings. .5 Telephone and interphone outlets: 300 mm. .6 Wall mounted telephone and interphone outlets: 1200 mm. .7 Disconnect switches: 1400 mm. CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 Section 16010 2006-08-30 Page 10 of 16 1.23 Load Balance .1 Measure the phase current to panelboards with normal loads (lighting) operating at the time of acceptance. Adjust branch circuit connections as required in order to obtain best balance of the current between the phases and record any changes. .2 Measure phase voltages at loads and adjust transformer taps to within 2 percent of the rated voltage of the equipment. .3 Submit, upon completion of the Work, a report listing phase and neutral currents on panelboards, and dry-core transformers and motor control centres, operating under normal load. State the hour and date on which each load was measured, and voltage at time of test. .1 Install conduit and sleeves prior to pouring of concrete. Sleeves Passing Through Concrete: Plastic, sized for free passage of conduit, and protruding a minimum of 50 mm. .2 If plastic sleeves are used in fire rated walls or floors, remove them before conduit installation. .3 Install cables, conduits and fittings to be embedded or plastered over, neatly and close to building structure so furring can be kept to minimum. 1.24 Conduit and Cable Installation 1.25 Ambient Environment .1 Unless otherwise indicated in the Contract Documents, supply equipment enclosures, boxes, electrical materials and products suitable for ambient environment of the following area: Equipment Area Gen. Classification Enclosure Type 1. Outdoor Areas Wet EEMAC 3R 1.26 Field Quality Control .1 Conduct and pay for the following tests: .1 Power generation and distribution system including phasing, voltage, grounding, and load balancing. .2 Circuits originating from branch distribution panels. .3 Lighting and its control. CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 .4 .5 .6 .7 Section 16010 2006-08-30 Page 11 of 16 Motors, heaters and associated control equipment including sequenced operation of systems where applicable. Systems: communications Instrumentation. Variable Frequency Drives .2 Furnish the manufacturer's certificate or letter confirming that the entire installation as it pertains to each system has been installed in accordance with the manufacturer's instructions. .3 Insulation resistance testing. .1 Megger circuits, feeders and equipment up to 350 V with a 500 V instrument. .2 Megger 350-600 V circuits, feeders and equipment with a 1,000 V instrument. .3 Check resistance to ground before energizing. .4 Carry out tests in the presence of the Consultant. .5 Provide instruments, meters, equipment, and personnel required to conduct tests during, and at the conclusion of, the Work. .6 Submit all test results for the Consultant's review and continue to test and submit test results until the Consultant is satisfied with results of testing. .1 The Contractor shall arrange for manufacturers' plant inspection by the Consultant, where indicated in the Contract Documents or required for verification of shop drawing submittal contents. .2 The Contractor shall inform the Consultant of manufacturing progress upon request. .3 The Contractor shall not construe action taken as a result of factory inspection as final acceptance. .1 Ensure that all circuit protective devices such as overcurrent trips, relays, and fuses are installed to required values and settings in accordance with the short circuit and coordination studies. .1 The Region and Region's representatives shall have the privilege of trial usage of the electrical system or parts 1.27 Source Quality Control 1.28 Co-ordination of Protective Devices 1.29 Trial Usage CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 Section 16010 2006-08-30 Page 12 of 16 thereof for the purpose of testing and verifying operational procedures. .2 Trial usage by the Region shall not relieve the Contractor of any responsibility because of trial usage. .3 Trial usage shall not be construed as acceptance by the Region. .1 The Contractor shall provide to the Consultant for review a Harmonics Study of the overall electrical system complete with measured Harmonic distortion levels for both current and voltage. The study should identify the Harmonic distortion levels present in all orders. The point for this measurement shall be point of common coupling unless noted otherwise in the Contract Documents. Carry out the Harmonic Study for plant operation under normal and also under standby power under specified load conditions. Testing for Harmonics shall be performed according to IEEE 519 by a company approved by the Region. .2 Any recommendations identified in the Harmonics Study that are required in order to satisfy IEEE 519 are to be implemented by the Contractor at no additional cost to the Region. .1 The Contractor shall provide to the Consultant for review a short circuit and co-ordination study of the overall electrical system of the project with the MCC shop drawings. The shop drawings for equipment in this division shall not be reviewed without the short circuit and co-ordination study. .2 The study data shall be presented in tables and on composite charts and shall include but not be limited to the following: Maximum available short circuit current of systems. .1 .2 Maximum available ground fault current of systems. .3 Feeder cables thermal short circuit damage curve. .4 Primary fuse to power the transformer. .5 Power transformer thermal short circuit damage curve, 3 phase, phase to ground. .6 Main secondary 600 volt system circuit breakers. .7 Largest 600 volt moulded case distribution breaker and characteristics. .8 Largest distribution transformer thermal short circuit damage curve. 1.30 Harmonic Testing/Analysis 1.31 Coordination Study CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 .9 .10 .11 .12 .13 .14 .15 .16 Section 16010 2006-08-30 Page 13 of 16 Maximum available fault current, 3 phase and phase to ground for the 600 volt system. Main 120/208 volt breaker and characteristics. Largest 120/208 volt distribution breaker and characteristics. Maximum available fault currents, 3 phase and phase-to-ground for the 120/208 volt system. Maximum available fault current RMS symmetrical at each panel. Establish the required settings for all ground fault relays. Diesel engine generator set operating procedures and breakers characteristics. Co-ordination Study to be performed by a company approved by the Region. The report shall be sealed by a professional engineer licensed to practice in the Province of Ontario. 1.32 Site Tests by Contractor .1 All equipment and electrical systems which are provided under this Division shall be performance tested for electrical and mechanical defects and all defects and adjustments identified in the performance tests shall be rectified and all other adjustments shall be made by the Contractor prior to requesting inspection by the Consultant. .2 Submit original copies of letters from the manufacturers of auxiliary systems indicating that their technical representatives have inspected and tested the respective systems and are satisfied with the methods of installation, wiring, interface with existing or new interface equipment and operation. .3 Insulation resistance tests shall be performed for all wiring and equipment installed under this Division. Insulation resistance tests shall be performed with a 500V megger instrument for equipment up to 350V and with a 1000V megger instrument for 350 - 600V circuits and recorded in log book for reference. Lighting and power circuit feeders shall be meggered and the insulation resistance between live parts and ground shall not be less than that specified in Table 24 of the Ontario Electrical Safety Code. During the performance of the test the neutral conductor shall be disconnected from the ground and reconnected afterwards. .4 Conduits or ducts which are required to be installed but left empty shall be tested for clear bore using a ball mandrel of approximately 85 percent of the conduit or duct inside CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 Section 16010 2006-08-30 Page 14 of 16 diameter. Any conduit or duct which rejects the ball mandrel shall be cleared at no additional cost to the Region. These tests shall be witnessed by the Consultant. Three days notice shall be given prior to testing. .5 Single phase loads shall be connected so that there is the least possible imbalance of the supply. Common neutral shall be used for maximum 3-1 phase circuits, each circuit on a different phase. .6 Furnish labour, materials, instruments and bear all costs for tests as requested by the Consultant. .7 Conduct and pay for tests of the following: .1 Field wiring to all transmitters and field devices .2 RPU I/O's, transmitters, Field Devices - Calibration .3 Variable Frequency Drives .8 Carry out tests in presence of the Consultant. Give 3 Working Days notice of proposed tests. .9 Provide instruments, meters, equipment and personnel required to conduct tests during and at conclusion of project. .10 Submit two (2) copies of test results for the Consultant's review in addition to copies included in Maintenance Data. .1 The Contractor shall test and check electrical and instrumentation systems for correct operation and compliance with statutory and regulatory authority requirements. .2 The Contractor shall perform tests in presence of Consultant. Log, tabulate, sign and include test results in Maintenance Data and Operating Instructions. 1.33 Tests by Contractor .3 The Contractor shall test the following systems: .1 4160 V switchgear, including cabling for correct phasing, voltage, grounding and load balancing. .2 Standby generators .3 Communications, control and instrumentation. .4 The Contractor shall conform to the testing requirements of Section 01810 – Equipment Testing and Facility Startup .4 The Contractor shall supply instruments, meters, consumable parts (such as fuses) and equipment. The Contractor shall arrange for qualified personnel to conduct tests. .5 The Contractor shall observe field painting of electrical equipment or raceways. CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 Section 16010 2006-08-30 Page 15 of 16 1.34 Fire Transits .1 All cable trays, conduits etc. transitioning through building walls to be sealed with a one (1) hr fire rated caulking or fire transit. .2 Fire transit to be ULC listed. .1 Comply with Section 01740 – Cleaning. .2 Before energizing any system, inspect and clean all the inside of switchgear, MCC, etc to ensure that they are free from dust and debris. .3 At time of final cleaning, clean lighting reflectors, lenses, and other lighting surfaces that may have been exposed to construction dust, dirt and other debris. .4 Clean all polished, painted and plated work brightly. .5 Remove all debris, surplus material and all tools. .1 The use of permanent electrical system for temporary construction service shall be only with written permission of the Consultant. .2 Maintain at the Site, at all times, qualified personnel and supporting staff, with proven experience in erecting, supervising, and testing of projects of a comparable nature and complexity. .3 Expedite the Work as follows: .1 Continuously check and expedite the delivery of equipment and materials. .2 If necessary, inspect at the source of manufacture. .3 Continuously check and expedite the flow of necessary information to and from all parties involved. .4 Inform the Consultant promptly where information is required. .4 The Work of Division 16 shall be coordinated with the Work of other Divisions in such a manner so as not to interfere with other Work. In areas where the ducts, pipes, wiring, and equipment for other Sections will be installed in proximity to pipes, wiring and equipment pertaining to this Division, cooperate and coordinate with Subcontractors and Other Contractors to ensure that all pipes, ducts, wiring, and equipment are installed in the locations that best meet the requirements of the Region in a way that 1.35 Cleaning 1.36 Execution CONTRACT NO. T-12-16 ELECTRICAL GENERAL REQUIREMENTS DATE: April 2012 Section 16010 2006-08-30 Page 16 of 16 ensures their proper operation in accordance with the Contract Drawings and Specifications. .5 Equipment, conduit, etc., installed but not coordinated with the work of Other Contractors and Subcontractors shall be relocated as directed by the Consultant without extra cost to the Region. .6 Install equipment, conduits, and cables in a workmanlike manner to present a neat appearance and to function properly to the satisfaction of the Consultant. Install any exposed conduit runs parallel and perpendicular to building planes. Install conduit so that they are concealed in chases, behind furring, or above ceiling, except in unfinished areas. Install exposed systems neatly and group them to present a neat appearance. .1 The Contractor shall comply with the requirements of Section 01640 – Manufacturers’ Services. .2 Do not combine testing and startup with training. Testing and startup time shall not be used for manufacturers’ warranty repairs. .1 The Contractor shall comply with the requirements of Section 01430 – Operation and Maintenance Data. 1.37 Manufacturer’s Services 1.38 Operation and Maintenance Data END OF SECTION CONTRACT NO. T-12-16 ELECTRICAL SYSTEMS ANALYSIS DATE: April 2012 PART 1. 1.1 1.2 1.3 1.4 Section 16015 2006-08-30 Page 1 of 8 GENERAL Related Sections .1 Division 1 – General Requirements .2 Division 16 - Electrical .1 Comply with the latest edition of the following statutes codes and standards and all amendments thereto. .1 Institute of Electrical and Electronics Engineers, Inc. (IEEE): 1. IEEE 242, Recommended practice for Protection and Coordination of Industrial and Commercial Power Systems. 2. IEEE 399, Recommended Practice for Industrial and Commercial Power System Analysis. .2 American National Standards Institute (ANSI): 1. ANSI C57.12.00, Standard General Requirements for Liquid- Immersed Distribution, Power, and Regulating Transformers. 2. ANSI Std.80 - Guide for Safety in AC Substation Grounding 3. ANSI Std.837 – IEEE Standard for Qualifying Permanent Connections Used in Substation Grounding .3 CSA Standard C22.41 Grounding and Bonding Equipment. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16015 – Electrical Systems Analysis as indicated in Schedule ‘A’ of the Bid Form. References Measurement and Payment Submittals .1 Shop Drawings: Provide five copies of the following studies in hard cover, three-ring binders: .1 Ground Grid Design, indicating touch and step voltage .2 Short circuit study and Arc Flash protection .3 Protective Device Coordination Study: submit prior to submission of transformer and switchgear and MCC drawings. Drawings will not be reviewed prior to coordination study. .4 Arc Flash study .5 Load flow and power factor correction study. .6 Harmonic Analysis Study for plant operation under normal and emergency power. CONTRACT NO. T-12-16 ELECTRICAL SYSTEMS ANALYSIS DATE: April 2012 1.5 1.6 1.7 Section 16015 2006-08-30 Page 2 of 8 Quality Assurance .1 Ground Grid Design, Short circuit and protective device coordination studies to be prepared by a professional electrical engineer registered in Ontario. .2 Short circuit, protective device coordination studies and arc flash study shall be prepared by one of the following or an approved equal .1 Rondar Engineering and Technical Services .2 G.T.Wood Company Limited .3 K.Teck Electro Services .4 Cutler Hammer Engineering Services .1 The complete ground grid design and short circuit study including arc flash levels according to the equipment selected by the Contractor must be submitted and reviewed before the Consultant will approve shop drawings for switchgear, 5kV switchboard, 600 V Motor Control Centre, motor starters, cables and equipment for incoming and outgoing service. .2 The short circuit and protective device coordination and arc flash studies shall be updated prior to Substantial Completion of the Work. Utilize characteristics of as-installed equipment and materials. .1 Equipment and component titles used in the studies shall be identical to the equipment and component titles shown on the Contract Drawings. .2 Perform studies using a personal computer with approved software for the application. .3 Perform studies using windows based software such as Power Analytics Software EDSA, SKM System Analysis Inc. electrical engineering software, or CYME Power Engineering Software. .4 Perform complete fault calculations for each proposed and ultimate source combination. .5 Perform complete fault calculations for all switching scenarios. .6 Device coordination time-current curves from primary switchgear to medium voltage switchgear and the generators. .7 Coordinate with the Power Stream Inc. (the “Supply Authority”) to obtain their design fault levels and protective settings. .8 Source combination may include present and future power company supply circuits, large motors, or generators. Sequencing and Scheduling General CONTRACT NO. T-12-16 ELECTRICAL SYSTEMS ANALYSIS DATE: April 2012 1.8 Section 16015 2006-08-30 Page 3 of 8 Short Circuit Study .1 General: .1 Use cable impedances based on actual conductor materials. .2 Use bus impedances based on copper bus bars. .3 Use cables and bus resistances calculated at 25 degrees Celsius. .4 Use 600-volt cable reactance’s based on use of typical dimensions of RW90, Teck conductors. .2 Provide: .1 Calculation methods and assumptions. .2 Selected base per unit quantities .3 One-line diagrams. .4 Source impedance data, including electric utility system and motor fault contribution characteristics. .5 Impedance diagrams .6 Zero sequence impedance diagrams .7 Typical calculation .8 Tabulations of calculated quantities .9 Results, conclusions, and recommendations. .3 Calculate short circuit interrupting and momentary (when applicable) duties for an assumed three-phase bolted fault at each: .1 Electric utility’s supply termination point. .2 Main switchgear, on normal power and standby power. .3 Medium and low voltage switchgear and switchboards. .4 Motor control centres. .5 All 600V branch circuit panelboards. .6 27.6 kV Switchgear .7 %kV Switchgear .8 Main incoming breakers (tie-breaker) included. .9 Generator breakers. .4 Provide bolted line-to-ground fault current study for areas as defined for three-phase bolted fault short circuit study. .5 Provide bolted line-to-line fault current study for areas as defined for three-phase bolted fault short circuit study. .6 Verify: .1 Equipment and protective devices are applied within their ratings. .2 Adequacy of switchgear and motor control centre bus bars to withstand short circuit stresses. .3 Adequacy of bus bars to withstand short circuit stresses. .4 Adequacy of transformer windings to withstand short circuit stresses. .5 Cable and busway sizes for ability to withstand short circuit ratings besides normal load currents. CONTRACT NO. T-12-16 ELECTRICAL SYSTEMS ANALYSIS DATE: April 2012 1.9 Section 16015 2006-08-30 Page 4 of 8 Protective Device Coordination Study .1 Proposed protective device coordination time-current curves for distribution system, graphically displayed on conventional log-log curve sheets. .2 Each curve sheet to have title and one-line diagram that applies to specific portion of system associated with time-current curves on the curve sheet. .3 Terminate device characteristic curves at a point reflecting maximum symmetrical or asymmetrical fault current to which device is exposed. .4 Identify device associated with each curve by manufacturer type, function, and, if applicable, tap, time delay, and instantaneous settings recommended. .5 Plot Characteristics on Curve Sheets: .6 Electric utility's (Power Stream Inc.) relays. .1 Electric utility's fuses including manufacturer's minimum melt, total clearing, tolerance, and damage bands. .2 Medium voltage equipment relays. .3 Medium and low voltage fuses including manufacturer's minimum melt, total clearing, tolerance, and damage bands. .4 Low voltage equipment circuit breaker trip devices, including manufacturers tolerance bands. .5 Pertinent transformer full-load currents at 100 percent and 600 percent. .6 Transformer magnetizing inrush currents. .7 Transformer damage curves. .8 ANSI transformer withstand parameters. .9 Significant symmetrical and asymmetrical fault currents. .10 Ground fault protective device settings. .11 Other system load protective devices for largest branch circuit and feeder circuit breaker in each motor control center. .7 Primary Protective Device Settings for Delta-Wye Connected Transformer: .8 .1 Secondary Line-to-Ground Fault Protection: Primary protective device operating band within the transformer's characteristics curve, including a point equal to 58 percent of ANSI C57.12.00 withstand point. .2 Secondary Line-To-Line Faults: 16 percent current margin between primary protective device and associated secondary device characteristic curves. Separate medium voltage relay characteristic curves from curves for other devices by a 0.4 second time margin at a minimum. .1 For selection of CT ratio, feeder load amps will be given to the successful bidder at a later date. CONTRACT NO. T-12-16 ELECTRICAL SYSTEMS ANALYSIS DATE: April 2012 Section 16015 2006-08-30 Page 5 of 8 .9 Arc Flash Study .1 Arc Flash study shall be performed in accordance with NFPA 70E and IEEE Standard 1584. Provide lamacoid labels (to include arc flash boundary, .2 incident energy and hazard/Risk category for Protective clothing) for 5 kV switch board and for all motor control centers .3 Suggest methods for reducing arc flash energy (i.e. reducing trip times for 5 kV breakers at expense of coordination and replacement of incoming breakers at MCC with fuses) .1 Ensure all step and touch potentials are considered acceptable and conform to the requirements of the Ontario Electrical Safety Code. .2 Measure soil conductivity prior to performing ground grid design. Use soil conductivity results in preparation of the ground grid design. .1 General Data: .1 Short circuit reactances of rotating machines. .2 Cable and conduit material data .3 Bus data .4 Transformer data .5 Circuit resistance and reactance values. .2 Short Circuit Data: .1 Fault impedances .2 X to R ratios .3 Asymmetry factors .4 Motor contributions .5 Short circuit kVA .3 Symmetrical and asymmetrical fault currents .4 Recommended Protective Device Settings. .1 Solid State Relays: 1. Adjustable pickup 2. Adjustable time current characteristics 3. Curve slope and type 4. Current tap 5. Time dial 6. Instantaneous pickup 7. Overvoltage and under-voltage alarms 8. Reverse current settings 9. Metering and communications settings .2 Circuit Breakers: 1.10 Ground Grid Design 1.11 Tabulations CONTRACT NO. T-12-16 ELECTRICAL SYSTEMS ANALYSIS DATE: April 2012 1. 2. 3. Section 16015 2006-08-30 Page 6 of 8 Adjustable pickup Adjustable time-current characteristics Adjustable instantaneous pickup 1.12 Study Analyses . .1 Written Summary: .1 Scope of studies performed .2 Explanation of bus and branch numbering system .3 Prevailing conditions .4 Selected equipment deficiencies .5 Results of short circuit and coordination studies .6 Comments and suggestions .2 Suggest changes and additions to the equipment rating and/or characteristics. .3 Notify the Consultant in writing of any existing circuit protective devices which are improperly rated for the new fault conditions. 1.13 Load Flow and Power Factor Corrections Study .1 Load flow and power factor correction study .1 At the end of the construction document and demonstrate the distribution of power and voltage levels throughout the system for 25 percent, 50 percent and 100 percent load conditions for operation under normal and standby power conditions. .2 Study results to include: .1 Real kW .2 Reactive kvar .3 Power flow through transformers and cables .4 Power factor at each bus and system losses .5 Identify overloaded transformers and cables .6 Provide recommendations for proper transformers and cables .3 Study Procedure .1 Document normal and contingent operating conditions .2 Utilize state of the art software which utilizes an interactive technique to calculate, real and reactive power flow and bus voltage levels throughout the system. .3 Create data base from nameplates and by monitoring the existing feeders with a digital power monitor. Monitor each feeder for minimum of two hours, during typical operating period utilize current and voltage, kW kvar and kVA and power factor as an input to the load flow programme. .4 Results: The load flow study to include: .1 Bus voltages, line currents, power factor, transformer loading. .2 Recommended transformers tap settings CONTRACT NO. T-12-16 ELECTRICAL SYSTEMS ANALYSIS DATE: April 2012 .3 .4 Section 16015 2006-08-30 Page 7 of 8 Complete set of capacitor recommendations Recommend equipment upgrades or circuit configurations to optimize the power flow from the source to the loads. 1.14 Harmonic Analysis Study .1 Carry out the harmonic analysis of the electrical distribution system for the circuit conditions listed below: .1 Existing system configuration .2 System with new VFDs or other non linear harmonic creation loads in operation at no load, 50% and 100% load conditions. .3 Provide the following data from each study: 1. System harmonic voltages in rms and % THD. 2. System harmonic current in rms and % THD. 3. An IEEE 519 analysis at the point of common coupling with incoming utility. 4. Capacitor bank evaluation on the basis voltage, current and kVA. 5. Calculate harmonic generation of each VFD, take field measurements of VFD current harmonic generation during the process operation. 6. If the calculated magnitudes of harmonic voltages and/or currents are excessive, the corrective solution will be suggested to reduce the harmonic quantities to within the acceptable limits. 7. Recommend a filter and provide complete specifications for the same. .4 Results: At the conclusion of the harmonic analysis submit the following: 1. Description, purpose, basis and scope of the harmonic study and a single line diagram of the system 2. Tables listing the individual harmonic voltages and currents and total harmonic distortions for all major buses within the electrical distribution system, waveforms for all of the calculated harmonic voltages will be displayed. 3. Plot of frequency versus impedance for all capacitor locations (harmonic resonance scan) Complete recommendations for harmonic filters, 4. shunt capacitors and series reactors which are required for harmonic suppression 5. Complete text report of each measurement location sorted by current and voltage, and listing the harmonic component and total harmonic distortion. 6. Waveform of each measurement sample. 7. Detailed harmonic spectrums of harmonic generating loads. CONTRACT NO. T-12-16 ELECTRICAL SYSTEMS ANALYSIS DATE: April 2012 PART 2. PRODUCTS (NOT USED) PART 3. EXECUTION 3.1 3.2 3.3 Section 16015 2006-08-30 Page 8 of 8 Direct Burial of Cables .1 Adjust relay and protective device settings according to values established by the approved coordination study. .2 Provide detailed data sheets for all programmable meters, relays and monitors within the scope of this study, including all multifunction relays, feeder protection relays, motor protection relays and power monitors. .1 Detailed data sheets to include all 1. Protective device settings 2. Ranges 3. Output relay functions 4. Parameters for input devices 5. Addressing 6. Communication settings .2 Data sheets to be in an electronic format, suitable for downloading to devices, and in a hardcopy format to review. .3 Make mirror modifications to equipment as required to accomplish conformance with the short circuit and protective device coordination studies. .1 Adjust relay and protective device settings according to values established by coordination study. .2 Make minor modifications to equipment as required to accomplish conformance with the short circuit and protective device coordination studies. .3 Notify the Consultant in writing of any required major equipment modifications. .1 Test relay setting by secondary current and voltage injection. .2 Test ground continuity and resistance prior to energizing electrical systems. .3 Test grounding system efficiency for compliance with the requirements of the Ontario Electrical Safety Code and the Supply Authority. Verify ohmic resistance and touch and step voltage values are not exceeded. General Field Quality Control END OF SECTION CONTRACT NO T-12-16 Section 16016 STAGING AND TRANSITION Page 1 of 6 DATE: April 2012 PART 1. 1.1 1.2 1.3 1.4 GENERAL Related Sections .1 Section 01501 – Construction Sequencing .2 Division 1 – General Requirements .3 Division 2 – Sitework .4 Division 11 – Equipment .5 Division 13 – SCADA and Instrumentation .6 Division 15 – Mechanical .7 Division 16 – Electrical .1 Provide all the design, planning, materials, equipment, implantation, operational needs for staging as conceptually explained in the Contract Documents. Staging shall deliver uninterrupted power supply to ensure continued operation of the plant at normal levels of operation during the performance of this contract. .2 Draw out detailed plans, provide staging services and transition infrastructure for every stage of the project. .3 Professional handling of all staging and transition activities to ensure technically viable and operationally safe electrical system with reasonable redundancy for any unforeseen problems during the performance of the contracted Works. Electrical system includes power supply to instruments, valves, control panels, communication equipment, and other auxiliary devices. .4 Upon completion of the staging Work, restore the Site to normal operating conditions. .5 Coordination with the Consultant, plant operations, regulatory agencies, and other stakeholders for complete understanding of the plans and obtain their cooperation which is key element of successful staging exercise. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16016 – Staging and Transition as indicated in Schedule ‘A’ of the Bid Form. .1 All Work provided in the staging or transition to staging shall meet the requirements of the OESC (Ontario Electrical Safety Code), ESA (Electrical Safety Authority) and other regulatory statutes as mentioned in Section 16010 – Electrical General Requirements. Scope Measurement and Payment Regulatory Requirements CONTRACT NO T-12-16 Section 16016 STAGING AND TRANSITION Page 2 of 6 DATE: April 2012 1.5 Planning for Staging and Transition .1 Included in the Contract Documents is a broad based staging plan for phasing various activities, and providing temporary facilities and services during the Contract. .2 Plan for staging and transition to staging is primarily the responsibility of the Contractor. Subject to the approval of the Consultant, the Contractor may choose different staging schemes and prepare its plans partially or fully different from the plans included in the Contract. Such plans will be accepted only if they meet the objectives of the staging and have credible case for continued facility operation and completion of Work under the Contract. .3 Clear plans for staging shall be prepared by the Contractor and submitted for approval by the Consultant and the Region’s facility operations a minimum of 14 Days prior to start of the Work. If the Region or Consultant should find that the plans are not acceptable, the Contractor shall revise and resubmit in shortest time. No consideration shall be given in the overall schedule due to revision or changes to the plan. .4 Safety and security of the plant and the personal are of prime importance. A hazard analysis of each staging plan shall be prepared according to specific situation and it will be submitted for evaluation along with the safety measures planned during transition. .5 Temporary diesel generators shall be provided where power is required for operation of the facility and the power interruption is foreseeable. This provision shall include complete operational stand-by power including cable, switchboard, connections, all operational requirements and transfer of power means. The specific generator size, as specified on the Contract Drawings, is the minimum requirement. Actual size of generator may be greater based upon the specific plans prepared by the Contractor. The generator shall meet the limits outlined in the Ontario Ministry of the Environment Noise Pollution Control (NPC) documents for sound attenuation and emission levels. Whenever temporary generators are deployed they should be adequately maintained and monitored to ensure uninterrupted power. .6 Any spills shall be addressed promptly and according to applicable laws and standards. .7 A protection coordination check should be done for any breakers and fuses used for protection of the equipment installed for the staging activity. The Intent of the coordination check is to ensure that any fault on the staging network shall only trip the breaker or blow the fuse protecting the specific parts of staging. It should not trip the upstream breakers and affect the larger parts of the facility. CONTRACT NO T-12-16 Section 16016 STAGING AND TRANSITION Page 3 of 6 DATE: April 2012 1.6 .8 Submission of staging plans shall address all of the elements, scenarios, and contingent events which could likely effect the Work being planned. Provide test reports for the equipment involved in accordance with Section 16031- Inspection and Testing. .9 Submittal drawings for the temporary power shall be approved by the Consultant before the start of Work. .10 The Contractor shall be responsible for detailing the work mechanism of the staging plan, how it will be executed, all requirements of transition installations, provision of temporary generator, hook-up of temporary electrical distribution, temporary lighting and other consumables. .11 The Contractor shall provide a timeline of how the staging plan will be executed and how it will allow for the continuous operation of the facility. .12 Details of all temporary or permanent equipment, facilities and services required shall be available in accordance with the area classification and operational needs. .13 Confirm Protection coordination check for upstream breaker. .14 Confirm Power supply arrangement to instruments, valves, control panels, communication gear and other devices likely to be affected by the plan. .15 Provide a Safety and Hazard analysis, considering all possible situations. The Contractor shall include recommended solutions including methods of how the risks will be mitigated. Warning signs, barriers, adequate tools and supervision shall be listed in the plan. .16 Interface points with the existing system and the standby system, provide required isolation devices, emergency cut-off switches, grounding, and location specific safety provisions. .17 The Contractor shall provide a fall back situation plan in case the staging or transition activity has a catastrophic failure. This plan will provide for an immediate power restoration alternate in such catastrophic emergency. .1 Arrange and pay for the services of a qualified licenced electrician who has at least ten years experience in handling this type of work. The electrician shall prepare and finalize the staging activities and tasks and hold overall responsibility to implement these plans in a safe and reliable manner. The licenced electrician shall provide all required services during the staging Work and perform all coordination with the plant operations and the Consultant to ensure the plant remains operational. Design and Inspection CONTRACT NO T-12-16 Section 16016 STAGING AND TRANSITION Page 4 of 6 DATE: April 2012 1.7 1.8 .2 Before the start of each phase of the staging, the Contractor shall prepare a staging diagram for the information of plant operations and other stakeholders which shall be displayed at a prominent location. The diagram shall include; .1 The single line diagram changes to temporary and permanent facilities as applicable to the specific phase. .2 Any power interruptions planned, duration, schedule. .3 In case of an emergency response requirement, contact person(s) name and cell number during office hours /after hours. Caution or warning statements as required. .4 .3 The Contractor shall arrange, pay and obtain regular ESA inspections, or from other agencies having jurisdiction as determined by the conditions of the Site. The Contractor shall obtain assistance from the manufacturer as necessary during the course of equipment installation. .4 On completion of the staging activity the system shall be restored to its normal position and restore any damage to other site conditions or plant due to staging works. .1 On completion of the staging Work, the licenced electrician responsible for the staging work shall submit a completion report indicating the completed Work, any discrepancies, confirming the restoration of Site to normal conditions, removal of temporary installation, clearing of the areas and functioning state of plant devices, including details of attachment if affected. .2 This completion report shall be reviewed by the Consultant and the Supervisor of plant operations for any difficulties and the Contractor will be notified accordingly. The Contractor shall address these difficulties within 5 Working Days of the date of the notification. .3 If any part of the staging system needs to be kept available after the completion it shall be provided to plant operation along with the detailed sketches and technical information required. .4 A final inspection shall be held at the end of each staging activity to ensure that the Work has been completed as required by the Contract, the system has been restored to its normal condition, and is free of any unsafe or inoperable conditions, in accordance with operational needs and regulatory compliance. .1 It is the entire responsibility of the Contractor to design the staging network, including the required equipment and its installation and size it to meet the electrical load required for the plant operations under maximum operating conditions. The control wiring and Completion Responsibility CONTRACT NO T-12-16 Section 16016 STAGING AND TRANSITION Page 5 of 6 DATE: April 2012 needs for monitoring of this system on the Regions SCADA shall also be provided by the Contractor. .2 Staging shall not interfere or harm any other installed electrical equipment, including floor mounted distribution and control panels, switchboards, transformers, generators, luminaires, etc., which is part of the building electrical service systems. Any such harm shall be rectified by the Contractor at its sole cost. .3 Timeline of the staging activity shall be adhered to by the Contractor. The Contractor is responsible for keeping the Consultant and the Region informed about any unforeseen developments likely to affect this timeline. .1 All materials to be provided for staging shall be reliable for use and tested according to Section 16031 – Inspection and Testing before bringing to site. Test results shall be included with the submittal. .2 Any previously used material planned for installation in staging shall be tested for performance before it is brought to Site. Performance test records shall be verified at site and documents included in the submittal for reference. .3 In case any materials used in staging fails during the Work, adequate arrangement shall be in place for its prompt replacement by the Contractor at no additional cost to the Region. .4 All materials removed during the staging process and not required for further installation shall be handed over to the Region or disposed of according to the instructions from the Region. .1 Carry out all staging Work with due diligence and care as keeping the plant operational is a key requirement. .2 All Work shall be carried out on de-energized equipment. A temporary ground shall be required wherever the system ground is not available, ground protection shall be ensured for safety. .3 Staging installations shall have all safety measures in place before start of the Work, including warning signs, access barriers, area lighting, fire safety equipment etc. .4 Understand and comply with the plant safety requirements, follow the HOLD TAG and LOCK OUT procedures, and keep close PART 2. PRODUCTS 2.1 General PART 3. EXECUTION 3.1 General CONTRACT NO T-12-16 Section 16016 STAGING AND TRANSITION DATE: April 2012 Page 6 of 6 coordination with the plant operations for any additional case specific requirements. .5 Only a qualified licensed electrician with at least ten years experience in the specific trade should head the electrical crew involved in staging. All workers shall be provided with proper PPE (personal protective equipment), tools to handle the job without risk of damage to life and property. .6 All excavation near power lines, cables, and electrical cable ducts shall be carried out carefully using hand tools only. .7 Staging Work shall not hamper or disturb the other activities of the Region’s plant operators or the service agencies engaged by the Region for providing maintenance services on the plant. Coordinate the work with other trades as required. .8 The designated qualified professional responsible for staging shall keep the plant operations and all stake holders informed of the developments and ensure that the team responsible for the Work has adequate resources to meet any foreseeable contingencies created during the staging Work. END OF SECTION CONTRACT NO T-12-16 Section 16020 DEMOLITION OF ELECTRICAL SYSTEMS Page 1 of 5 DATE: April 2012 PART 1. GENERAL 1.1 1.2 General Conditions .1 Refer to Section 02030 – Demolition. .2 Comply with Division 1 - General Requirements and Section 16010 - General Electrical Requirements. .3 Refer to all other Divisions of the Specifications and these documents to determine their effect upon the work of this Section. .4 Treat the demolishing equipment containing designated substances (for example, PCB s, asbestos, etc.) in accordance with the Designated Substances Plan and all applicable regulations and codes. .5 When required by the Region, the Contractor shall remove and return equipment to a York Region storage facility located within 100km of the Site. Scope of Demolition of Electrical Systems Work .1 Furnish all labour, materials, equipment, transportation, services, facilities and supervision necessary to demolish all equipment, systems and materials specified herein and on the Contract Drawings. .2 Furnish all labour, materials, equipment, transportation, services, facilities and supervision necessary to dispose of all equipment, systems and materials listed for removal from the Site herein and on the Contract Drawings .3 Furnish all labour, equipment and supervision necessary to surrender (hand over) to the Region all equipment, systems and materials specified herein and on the drawings .4 Prepare drawings, stamped and signed by a registered professional engineer licensed to practice in the province of Ontario, indicating temporary bracing and/or supporting structures required during the demolition of doors and/or walls as described herein. .5 In general, the demolition of the electrical systems comprises, but is not limited to: .1 Removal of the existing 4160 V switchgear and starters .2 Removal of the specific parts of 600/208/120 V system. .3 Removal of the existing generators, buried diesel fuel tanks, fuel supply system, and all related equipment. .4 Removal of the existing station battery and charger .5 Removal of the HVAC control .6 Removal of the existing 4160 V power cables wherever indicated on the Contract Drawings. CONTRACT NO T-12-16 Section 16020 DEMOLITION OF ELECTRICAL SYSTEMS Page 2 of 5 DATE: April 2012 .7 1.3 1.4 1.5 Removal of sections of the existing cable trays and associated hardware Measurement and Payment .1 The Work outlined in this Section shall be included in the lump sum price for Section 16020 – Demolition of Electrical Systems as indicated in Schedule ‘A’ of the Bid Form. .1 Provide stamped and signed drawings for all structural demolition and temporary supporting works. .2 Provide a written procedure for all lifting operations involving the existing facility crane. Include weights and dimensions of items to be lifted and details of slings or other lifting tackle required. .1 Demolition and removal of the existing electrical equipment will not begin prior to the installation and commissioning and satisfactory operation of all temporary switchgear in accordance with Section 16330 – 27.6 kV Switchgear Modifications. .2 Demolition and/or removal of equipment must follow the approved sequencing schedules. The Contractor shall prepare the sequencing schedule and get approval from the Consultant and the Region’s Superintendent for Operations and Maintenance. .3 Perform the demolition of electrical systems such that availability and continuity of supply, monitoring and control of the common systems and auxiliaries are kept and secured. .1 Supply and install the necessary temporary bracing, supporting structures, guards, warning signs, etc. necessary to complete the Contract safely and in accordance with all regulations and/or codes referred to in Section 01060 – Regulatory Requirements and Section 16010 – Electrical General Requirements. .1 Organize the Work and provided sufficient labour and equipment to ensure safety of all personnel at all times. .2 All workers shall be competent in, and trained to perform, the tasks that they perform. Where applicable, workers shall be licensed or otherwise qualified for the tasks that they perform; Submittals Procedures and Stages PART 2. PRODUCTS 2.1 General PART 3. EXECUTION 3.1 General CONTRACT NO T-12-16 Section 16020 DEMOLITION OF ELECTRICAL SYSTEMS Page 3 of 5 DATE: April 2012 specifically electrical works shall always be performed under supervision of a licensed electrician or the High Voltage work under supervision of a qualified HV technician. .3 Prior to starting demolition, the Contractor and the Region shall inspect all facilities described to ascertain the limits of the Works. .4 Do not commence any demolition Work until the designated substance survey (DSS) is performed on the equipment to be removed and the Consultant has provided one (1) copy of the DSS report. .5 The DSS will be completed following the de-energization of the switchgear. There will be a period following de-energization where no Work on the electrical equipment, existing or new, will be permitted. During this period, Work may continue on ancillary equipment and/or the building structure. .6 Perform all demolition Work in accordance with the requirements of the DSS plan. .7 All the demolition Work shall be performed in a systematic manner and shall not damage other services and equipment nor affect the use and function of any process equipment and any services (electrical power, lighting, communication, heating, water supply) for the remaining facilities. .8 Co-ordination of Work .1 Co-ordinate demolition Work with the Consultant,and the Region’s staff to ensure no disruption of station operation. .2 Refer to Section 16010 – Electrical General Requirements for co-ordination with all other personnel, Subcontractors and Other Contractors. .9 Demolition and disposal .1 During the demolition Work, refrain from unnecessary damage to electrical equipment and hand over to the Region, unless noted otherwise on the Contract Drawings, all removed electrical equipment in good order and place the removed equipment into the areas as directed by the Consultant. .2 Remove and return the following reusable equipment to a York Region storage facility within 100km of the Site: 1. All Multilin relays, including the Multilin SR750 Feeder Management Relays and the Multilin SR469 Motor Management Relays. These relays will be re-used in the temporary equipment and the new switchgear and Medium Voltage MCC’s. 2. Any relays that are reused from the existing switchgear, or provided by the Region for the temporary switchgear must be installed in the permanent switchgear or “handed back” to the Region in good working order. CONTRACT NO T-12-16 Section 16020 DEMOLITION OF ELECTRICAL SYSTEMS Page 4 of 5 DATE: April 2012 .3 .4 .5 .6 .7 3.2 3.3 Remove the following equipment and surrender to the Region in good working order: 1. All medium voltage circuit breakers, and the breaker racking motors. 2. All new equipment installed under the PCS upgrades, including the switches, indicating lights, relays, and Multilin cases. 3. All 86 breaker lock-out relays. 4. Other materials as determined by the Region. Remove and return in good working order, all equipment belonging to PowerStream Inc. which is identified for removal to a location designated by PowerStream Inc located within 100km of the Site. Remove the equipment or material from Site and dispose in accordance with all applicable regulations and codes referred to in Section 01060 – General Requirements and Section 16010 – Electrical General Requirements. The Contractor shall pay all associated fees for disposal. The Contractor shall take all reasonable steps to ensure that equipment removed from site is in condition which allows for its reuse or recycle. Demolition Procedure for Station Battery .1 Remove the existing station battery only after all loads have been transferred to the new station battery, charger and temporary VDC panel. .2 Include details of battery removal in work plan. .3 Remove cells from battery prior to removing cabinet. .4 Arrange for a certified contractor to recycle the existing lead-acid cells. Demolition Procedure for the 4160 V Switchgear .1 Relocate the existing control cables and trough running up to the switchgear prior to demolition of switchgear. This wiring is the RTD signals from the motors and pumps to the switchgear, and is to be installed in the basement directly below the new switchgear. .2 Ensure that the equipment has been fully de-energized and locked-out prior to demolition. .3 Ensure that all control signals have been temporarily bypassed prior to demolishing switchgear. These signals can include communication, potential voltage (PT) and interlock signals. .4 Remove switchgear cell-by-cell. .5 Remove breakers prior to removing cells. CONTRACT NO T-12-16 Section 16020 DEMOLITION OF ELECTRICAL SYSTEMS DATE: April 2012 3.4 3.5 Page 5 of 5 Demolition Procedure for the 4160 V Cabling .1 The timing of cable removals shall be in accordance with the sequence schedules approved by the Consultant. All the cables shall be removed in one continuous run unless allowed otherwise by the Consultant. .2 Disconnect incoming 4160 V cables and remove as shown in the Contract Drawings. Ensure that replacement cables have been run before removing existing cables. Remove existing cables from site and dispose of according to the consultant instructions. .3 Remove the 4160 V cables between the starters and pump connection box. Remove existing cables from site and deliver at the location provided by the Region. .4 Follow all proper environmental procedures when cutting and removing paper insulated lead covered (PILC) type cable. The contractor is to remove PILC cable(s) in one continuous run if possible. Demolition Procedure for Unused Cable Trays .1 3.6 Remove existing 4160 V cable tray and bus duct and all associated hardware (hangers, etc.). Demolition Procedure for HVAC Controls .1 Remove all HVAC controls from the west wall of the mechanical room. .2 Remove cables from the existing MCC to the HVAC controls .3 Remove cables from each HVAC control to the associated HVAC loads. END OF SECTION CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 1 of 18 DATE: March 2012 PART 1. 1.1 1.2 1.3 1.4 1.5 GENERAL Related Sections .1 Section 11 – Equipment .2 Section 13 – SCADA and Instrumentation .3 Section 16 – Electrical .1 The tests and inspections shall comply with the requirements of the International Electrical Testing Association (NETA). .2 Technical basis for the Work under this Section will be provided by the standards referred to in Section 16010 – Electrical General Requirements. .1 Utilize the services of an independent group or agency specializing in the testing of medium and high voltage electrical equipment. The field services division of the switchgear or transformer supplier is not acceptable. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16031 – Inspection and Testing as indicated in Schedule ‘A’ of the Bid Form. .1 The Work covered by this Section of Specifications, includes the furnishing of all labour, test equipment, and performance tests for installations shown on the Contract Drawings and as herein specified during and at the conclusion of the Contract. .2 The Contractor shall test the following for proper operation and adjustments: .1 Cable and bus-bars. .2 Liquid filled transformers tests. .3 General or dry type transformers. .4 Switchgear tests. .5 Current transformers and potential transformer tests. .6 Substation grounding. .7 Low voltage distribution switchgear. .8 Low voltage power circuit breaker and protective relays. .9 Automated transfer switches. .10 Low voltage molded case breakers. .11 Motor control centres. .12 Bus Ducts. Standards Acceptable Testing Agency Measurement and Payment Scope CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 2 of 18 DATE: April 2012 .13 .14 .15 Low Voltage feeders. Switchboard and panel board circuits. All motors, heaters and associated control equipment including the sequential operation of systems where applicable and verification of correct over current and overload devices. PART 2. PRODUCTS 2.1 Test Equipment .1 General .1 Ensure that a suitable power supply is available for test equipment, be it 120 VAC or battery-powered devices. Record make, model, and calibration date of test instrument(s). .2 All test equipment shall have valid calibration stickers displayed on the equipment and must be calibrated within the last 12 months by a company who regularly engages in this service and is otherwise acceptable to the Consultant. .2 Transformer Doble® Test .1 Doble® test equipment shall be Type MH to 10kV at 60 cycles. .2 Test equipment voltage shall be variable from 2.0kV to 10kV depending on ratios of transformers. .3 Transformer Turn Ratio Test .1 Three-phase powered unit with solid state controls. .2 Unit shall be capable of tests on multiple transformer winding configurations. .3 Single-phase units may be used on specially wound transformers. .4 Turn ratio to 3 decimal place accuracy and display. .4 Relay Test Equipment .1 Relay test equipment shall be designed for relay testing and secondary current injection. .2 Current output shall be capable of 60 A for testing of instantaneous features. Indicators shall detect open signals, pick-up signals and .3 other required signals. .4 Timers shall be accurate to 1 millisecond. .5 MultiAmp or equivalent relay test units. Specifically designed relay testers for specific relays shall be used if available. .6 For equipment required on three phase systems, use a three-phase voltage and current output test unit. .7 For equipment required on three-phase differential test, use a six-channel current output test unit(s) or equivalent. .5 DC High Pot Units CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 3 of 18 DATE: April 2012 .1 .2 .3 Test instruments shall have a minimum output of 60 kV DC, 2000 uA capacity. Shall be 120 VAC powered. Test shall be conducted with full safety measures in force, including “barrier” of conductor ends, proper bonding, “flagperson”, as necessary. .6 AC High Voltage Units .1 Shall have a minimum output of 27 kV AC, 2000 mA capacity. .2 Use an AC high voltage unit for insulation tests and other tests as indicated in the Contract Documents, at voltage levels indicated in the Contract Documents or as required by the manufacturer’s recommendations. .3 Approved equipment shall be Doble® insulation test unit. .7 Insulation Resistance Meter (Megger) .1 DC megger shall have an insulation scale to 100,000 megohms (1000 V scale). Output voltages on DC megger units shall be 500 V, 1000 .2 V, 2500 V and 5000 V. .3 DC megger units shall be suitable for 10-minute megger tests and polarization index tests. .8 Low Resistance Test Units (Ductor) .1 Low resistance test units shall have 10 A output. .2 Digital display and accuracy to 1 microhm. .9 Ground Resistivity Tester .1 Ground resistivity tester shall measure earth impedance in variable distances from the source to 250 metres. Unit shall be capable of plotting ground resistivity from 0.1 .2 ohms and higher. .10 Load Survey .1 Test equipment shall be a Fluke Corporation Inc. (Fluke) 3 phase Power/Power Quality monitor or an approved equivalent, with capability to test Harmonic measurements, amplitude and phase angle for each harmonic, Watts, VA, VAR, true power factor, and displacement power factor, power quality standard measurements with high speed sampling of impulses at 2 MHz to measure impulses to 6400 volts peak, 500 nanoseconds duration and displays peak voltage. .11 Thermo graphic Scan equipment .1 Test equipment shall be Flir Systems Inc. Agema Thermo Vision 570 portable Infrared camera system or approved equal; and must be capable of taking a colour infrared image of all irregularities. .12 Ultrasonic Scan Equipment CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 4 of 18 DATE: April 2012 .1 2.2 Test equipment shall be at minimum equal to UE Systems Inc. – Portable Ultrasonic system or approved equal. A digital camera must be used for photo recording ability. Reports .1 Reports of all tests shall be in written form. .2 Include copy of the test results in the maintenance manuals. .3 General .1 All test results shall be inputted into an electronic test sheet program. .2 All test sheets shall include the equipment nameplate data, customer identification, time and date of tests, environmental conditions during tests, and environmental conditions during tests and test results. .4 Test Results and Reporting – Data For Inclusion .1 The following data shall be included in the test report: 1. Equipment data with selected position, if applicable, for example., transformer taps. 2. Protective device(s) make, model number, rating, “as found” settings. These shall include CT, PT relays, overloads, fuses, breakers. 3. Any adjustments, modifications and repairs made on the equipment on Site during the Work with an explanation as to why such Work was needed to be performed and the method of execution of the Work). 4. A summary of conclusions of the inspection and testing. 1. The acceptable criteria and limiting values of measured figures by the equipment manufacturer. These shall include the insulation resistance, (megohm) contact resistance (microhm), leakage current (microampere). 5. Recommendations for long-term and short-term remedial work. .5 Report Format .1 The final report shall be submitted in electronic and paper format in three (3) bound copies neatly in 3-ring binders with separate sections for each item as listed therein. .2 Photographs shall be mounted on background sheet complete with labels. Curves and graphs shall be neatly plotted on appropriate graph paper. Result tables shall be made electronically and logically arranged. .3 The applicable NETA test forms shall be used for reporting information. It is not intended to imply that these are the only forms required. The Contractor shall submit all CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 5 of 18 DATE: April 2012 information necessary to fully describe the inspection, testing and maintenance of all items. PART 3. TEST PROCEDURES 3.1 3.2 General .1 Coordinate all tests and shut downs with the Region. .2 Pre-service Inspection and Testing and Post-service Inspection and Testing of equipment shall be as described in PART 2 of this Specification and shall include the following: .1 Insulation resistance tests .2 DC high voltage tests .3 Liquid filled transformers tests .4 Switchgear tests .5 Substation grounding .6 Low voltage distribution switchgear. .7 Low voltage power circuit breaker and protective relays .8 Motor control centres .9 Low voltage molded case breakers greater than or equal to 100 A. .10 General or dry type transformers .11 Bus Ducts .12 Low Voltage feeders .13 Cable and bus-bars test .14 Protective relays .15 Power monitoring equipment .16 Coordination study related to calibration and testing .17 Current transformers and potential transformer tests .18 Thermo graphic scan, Ultrasonic scan .19 Load study Inspection and Testing Schedule .1 Inspection and Testing - General .1 The inspection and tests set out in the Inspection and Testing schedules and test reports are supplementary to the inspection and tests specified in individual sections of Division 16 - Electrical equipment. .2 Where test schedules are not specified, conduct tests and submit results in a tabulated format for all of the functional units associated with the equipment during the testing and commissioning phases. Conduct all production and routine tests as recommended .3 in the ANSI and CSA standards, preferably in the manufacturer's factory if possible. Unless otherwise stated in the Contract Documents or .4 otherwise agreed to by the Region and the Contractor the tests described herein are tests to be repeated on Site at a CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 6 of 18 DATE: April 2012 minimum. These tests are to be conducted in the sequence as described in this Section. .2 Equipment Test Schedule .1 Perform test as outlined in other Sections as well as the tests included in this Specification Section for the following equipment: 1. Test all new equipment supplied and installed under this Contract 2. Test the interface between existing equipment and installed equipment. 3. Test existing equipment being modified, relocated or moved within this contract. .3 Preparatory Work .1 Prior to beginning Work on Site submit for the Consultant's review, minimum of five (5) copies of data sheets for testing and reporting as follows: 1. List with descriptive literature of all test equipment to be used. 2. Calibration certificates for the proposed test equipment. 3. Test report forms shall be used for each equipment type. 4. Proposed Work schedule. .2 Do not commence inspection and testing Work before the above submissions are reviewed and approved by the Consultant. .3 The Contractor shall provide all necessary supplementary lighting to permit careful inspection and testing. The supplementary lighting provided shall be to the Consultant's approval. During any Hydro shutdown the requirement for supplementary lighting shall be increased to maintain an acceptable level of illumination. .4 Ensure Site conditions are satisfactory for execution of Work. .4 During Inspection & Testing .1 Carry out the Work with trained personnel, experienced in the particular type of testing and procedures required for each inspection and testing. .2 Ensure that any defects discovered are noted and corrected before continuing the Work. .3 As work progresses, maintain accurate records and submit to the Consultant for review when requested. .4 Mark any deviations found, initially on one set of the Contract Documents including the Drawings at the Site. Submit for Consultant's review. Revise Drawings and mark-up Contract Documents if requested by the Consultant to ensure accuracy. CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 7 of 18 DATE: April 2012 .5 .6 3.3 Revisions, further test results and clarifications of comments to be incorporated into the test reports. The Contractor shall record and report in detail any deficiencies rectified and repairs made during the course of the Work as part of the test report. .5 Test Instruments - General .1 Ensure suitable power supply is available for test equipment. Record make, model, and calibration date of test instrument. .1 Insulation Resistance Tests .1 Use a megger with 100,000 megohm at 1000 V resolution for megger tests. .2 Record ambient temperature and adjust the measured megohm reading to 20ºC ambient. .3 Use 5kV megger for 13.2kV equipment, 2.5kV megger for 2.4kV equipment and 1000 V megger range for power equipment of 600 V and below. .4 For a 10-minute megger test, record megohm values in megohms at 30 seconds, 60 seconds, 5 minutes and 10 minutes. Plot megohms against time for each connection. Calculate and record the ratio of measured megohms as follows: 1. 60-second megohm/30-second megohm = dielectric absorption. 2. 10-minute megohm/1-minute megohm = polarization index. 3. Report the 1-minute megohm as the insulation resistance value. 4. Submit tabulated measured megohm figures for 10minute insulation tests, submit in graphical format. .2 DC High Voltage (HV) Test .1 Conduct a 10-minute insulation resistance test immediately before high voltage tests and submit test reports. Conduct HV test only if the insulation resistance test result is satisfactory. .2 Test instrument shall have minimum output of 60kV DC, 2000 uA capacity. .3 Conduct test in accordance with IEEE Standard 400-2001. .4 Compile test report and submit it to the Consultant. .3 Liquid-Filled Transformers .1 General 1. Conduct inspections and tests and compile test reports. 2. Compile a separate test report for each power transformer. Proposed Tests CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 8 of 18 DATE: April 2012 3. .2 .3 .4 Conduct tests on existing transformers to verify that no damage or significant change has occurred since the last inspection and testing. 4. Conduct external inspections in accordance with layout shop drawings. 5. Check nameplates and vector diagrams against test results. 6. Inspect silica gel breathers, oil gauge, temperature gauge and similar devices where fitted. For devices with settings, record the settings in use. Record actual reading of all gauges and ambient temperatures. 7. Check to ensure that transformer is properly anchored to floor or pad. Inspect for oil leaks, correct oil level, and signs of 8. rusting. 9. Perform high voltage AC insulation test on high voltage windings to ground, low voltage windings to and low voltage windings using Doble® insulation tester. 10. Inspect bushings, and measure insulation resistance with use of high voltage AC insulation test. 11. Perform transformer turn ratio test on all tap positions. 12. Confirm proper grounding of transformer tank. Factory Tests shall include at a minimum 1. 10-minute insulation resistance test; 2. HV test at maintenance test voltage; 3. Winding resistance measurement; 4. Voltage ratio three phase, for each tap (transformer turn ratio); and 5. Relay and protective devices operation Site Tests shall include as a minimum 1. 10-minute insulation resistance test; 2. HV test at maintenance test voltage; 3. Winding resistance measurement; 4. Voltage ratio three phase, for each tap (transformer turn ratio); 5. Relay and protective devices operation 6. Exercise the manual tap changer to check its functions and ease of access. 7. Operate and simulate the alarm and trip conditions of each protective device. Switchgear .1 General 1. Conduct inspections and tests and compile test report. CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 9 of 18 DATE: April 2012 2. .2 .3 Compile separate test report for each circuit breaker, fuse switch, load break switch, isolation switch, soft starters and transition unit of 15kV in the Contract. 3. The following tests shall be included as the minimum tests for test performed on Site: 1. Inspection of all protective devices and auxiliaries (including lightning arresters) 2. 10-minute insulation resistance 3. Operational tests of protection and monitoring devices. 4. Relays calibration and metering devices calibration. 5. Circuit breaker trip and closing coil pick up and trip off voltages. 6. HV resistance tests 4. Conduct inspection after the equipment is isolated and grounded and the switchgear room is cleaned up and after the HV test. Measure the contact resistance of all main contacts 5. of equipment in the switchgear. 6. Verify the operation, interlocks, and tripping (for circuit breakers, starters, and fuse/unfused switches). Inspection of Switchgear 1. Check that nameplate and equipment identification corresponds with shop drawings, where applicable. 2. Check the provision and correctness of phase markers for power connections and cabling. 3. Check switchgear interior and exterior for cleanliness, and enclosure distortion. 4. Inspect the physical conditions and damage of terminations, shutters and mechanism and report any damage. 5. Check the structural supports and connections, grounding security and connection. 6. Check fuse type and ratings, correct CT ratio. 7. Check access of CT for replacement and routine inspections/testing. Operational Checks 1. Operate the closing and tripping mechanism and the shutters to ensure correct and smooth movement. Operate each protective and monitoring device for 2. correct operation and indication. 3. Sample check the torque of busbar bolts and cabling termination for correct tightness. 4. Check contact alignment and bouncing, contact pressure and contact resistance. CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 10 of 18 DATE: April 2012 5. 6. 7. 8. 9. 10. 11. 12. 13. Check mechanical and electrical interlocks. Check the draw out feature of breaker and PT drawer. Check the auxiliary switches operation and contacts. Verify that all interlocks are functioning as designed; including key interlocks, hard wired interlocks between cells, emergency stop pushbuttons and 86 lockout relay interlocks. 1. Insulation Resistance Test Conduct DC hipot test on each switchgear (circuit breaker, transition unit, fuse switch and load break switch). Perform Doble® test on each switchgear (circuit breaker, transition unit, fuse switch and load break switch). Conduct HV tests as specified in the Contract Documents. Duct tests on relays (relay testing), voltage/control transformers, current transformers, indicating meters, switchgear cell inspection and lightning arresters. For relays, check operation and indication. Lightning Arrester Testing. 1. Conduct tests after the lightning arresters have been isolated from system. 2. Check the arresters for cracks, corrosion and tracking marks. 3. Conduct megger and Doble® tests on 39kV lightning arresters in accordance with the manufacturer’s recommendations for one minute and record the results. Check grounding on arrestors and check the pressure and state of operation indicator. .5 Substation Grounding .1 Verify that ground connections meet the requirements of the Ontario Electrical Safety Code , and all that all equipment and metal surfaces are bonded to ground. .6 Low Voltage Distribution Switchgear (DS) Inspection .1 Inspect and clean the DS air circuit breakers. .2 Clean frames/mechanisms/auxiliary devices and apply lubricant in accordance with the manufacturer’s recommendations. .3 Inspection and testing shall include megger, ductor, protective relay testing and calibration, and visual inspection. Note any deficiencies. .4 Verify protective relay settings with coordination study. .5 Function test protective relays to ensure reliable operation. CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 11 of 18 DATE: April 2012 .6 Torque check a minimum of 10 percent of all connections. Torque check all connections if any connection is found to be defective. .7 Low Voltage Power Circuit Breaker and Protective Relay .1 Perform contact resistance testing on all breakers at or above the 400 A frame level, including limiters. .2 Perform secondary injection testing of zero sequence current transformers and ensure that pick-up value is in accordance with its respective ground fault relay. Function test each breaker via its zero sequence CT to ensure reliable operation. .3 Inspection and testing shall include a visual inspection of breaker and auxiliary device(s). Note any deficiencies. Verify protective relay settings with the coordination study. .4 .5 Check draw out devices, electrical and mechanical functions, interlock sequences. Test contact resistance. .6 Perform current injection tests to confirm the proper operation of trip devices. Record: .7 1. Long time pick-up current. 2. Long time trip times at 200 % and 300% of pick-up. 3. Short time pick-up current. 4. Short time trip time at 150% of pick-up. 5. Instantaneous pick-up. 6. Ground pick-up. 7. Insulation resistance test from pole to pole and from pole to ground for one (1) minute at KVDC. 8. Over-current and Ground Fault Tripping Relays: 9. Test by secondary current injection, tripping of device or alarms to be confirmed. 10. Test draw-out function, etc. 11. All relays to be adjusted and tested to show conformance with the recommended settings in the coordination study. .8 600 V MCC’s .1 Insulation Resistance .2 Continuity Check. .3 Proper Phase sequence, ABC. .9 Low Voltage Molded Case Circuit Breakers – above 300 A .1 Check mechanical operation and interlocks. .2 Test (via current injection) trip time at 300% of rating. .3 Test and record instantaneous trip value. .4 Test and record contact resistance. .5 Set protective devices to the requirements of the approved coordination study. .6 Insulation resistance test from pole to pole and from pole to ground for one (1) minute at KVDC. .7 Overcurrent and Ground Fault Tripping Relays: CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 12 of 18 DATE: April 2012 1. Test by secondary current injection, tripping of device or alarms to be confirmed. .10 General or Dry Type Transformers .1 General 1. Conduct inspections and tests and compile test reports. 2. Compile a separate test report for each power transformer. .2 Inspections 1. Conduct external inspections in accordance with the layout shop drawings. Check nameplates and vector diagrams against test results. 2. Inspect temperature gauge and fans. For devices with settings, record the settings in use. Record actual readings of all gauges and ambient temperature. 3. Check to ensure that the transformer is properly anchored to the floor or pad. Perform high voltage AC insulation tests on high 4. voltage windings to low voltage windings. 5. Perform core to ground test. 6. Perform transformer turn ratio test on all tap positions. 7. Confirm proper grounding of transformer frame and core assembly. Factory Tests shall include at a minimum .3 1. 10-minute insulation resistance test; 2. HV test at maintenance test voltage; 3. Winding resistance measurement; 4. Voltage ratio three phase, for each tap (transformer turn ratio); and 5. Relay and protective devices operation .4 Site Tests shall include as a minimum 1. 10-minute insulation resistance test; 2. HV test at maintenance test voltage; 3. Winding resistance measurement; 4. Voltage ratio three phase, for each tap (transformer turn ratio); 5. Relay and protective devices operation 6. Operate and simulate the alarm and trip conditions of each protective device. .11 Bus Ducts .1 Inspect and check for proper torque on a minimum of 10 percent of all joints. If any are found defective, all joints to be retorqued and marked by Contractor and then rechecked. CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 13 of 18 DATE: April 2012 .2 Duct to be meggered at 1,000 V DC and any reading of less than 50 Megohms shall be reviewed with manufacturer and the Consultant. .12 Low Voltage Feeder Cables .1 In and out of main board to be meggered at 1,000 V DC and terminals checked for torque. Any reading that is less than 50 Megohms shall be investigated. .2 Insulation Resistance. .3 Continuity Check. .4 Proper Phasing, ABC. .13 Cables/Busbar .1 General 1. Conduct inspection and testing. Compile all test results in accordance with the Equipment Test Schedule to be submitted by the Contractor and approved by the Consultant. 2. Record type and size of cables on test sheets and check against the single – line drawing. 3. Conduct tests on each set of cables and busbars of 400 A and above. 4. Confirm that all hardware is in accordance with the torque requirements of the manufacturer, and mark off all hardware after verification. .2 Cabling Inspection 1. For cables which are likely to have a sheath current, check to ensure that metal supports are not used. The use of fiber plates is acceptable. 2. Check for the proper physical protection of cables through concrete openings or metal plating. 3. Check that all power cables, including Teck cables etc., are properly spaced (by one cable diameter unless specifically indicated otherwise in the Contract Documents) and secured by proper clips. 4. Check insulators and bushings for cracks and other physical defects. 5. Visually inspect cables where possible throughout their run and check conditions of the following: 1. Use of proper lugs. 2. Cables are properly shaped without sharp bends. 6. Open cables are properly supported on racks, trays or ladders in buildings. No concentrated stress points exist. 7. Insulation jacket damage. 8. Cables at duct mouth for wear or cracking. 9. For rubber insulated cables inspect stress cones or terminations, and check the following: 1. Terminals for tightness and overheating. CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 14 of 18 DATE: April 2012 2. Stress cones and terminations for cracks, dirt, or tracking. .14 Current Transformer and Potential Transformer .1 General 1. Conduct inspections and tests and compile all test reports. 2. Compile a separate test report for each set of current transformers (CTs) and potential transformers (PTs). Test reports shall be included within the results of the devices that the CTs and PTs feed. 3. Perform CT saturation tests, polarity tests, ratio, winding resistance and insulation resistance tests. 4. Verify correct taps and ratios on CTs and PTs. 5. Ensure that CT circuits are not open circuited, and ensure any temporary shorting devices are removed. 6. Ensure correct fusing on PTs .2 Inspection of CTs and PTs 1. Check that nameplate and equipment identification corresponds with shop drawings. Check the provision and correctness of phase 2. markers for power connections and cabling. 3. Inspect the physical conditions of and any damage to housing and terminations. 4. Check the structural supports and connections, grounding security and connection. 5. Terminal and wire numbering information shall be included in the as-built drawings. .15 Protective Relay .1 General 1. Conduct inspection and tests, and compile all test results on relay test sheets approved by the Consultant. 2. Conduct tests on all protective relays, auxiliary voltage and current relays, overloads, specialty protection relays including generator, transformer and switchgear relays, trip supervisory relays and trip relays. 3. Calibrate all relays if tests indicate that the actual set points are outside the tolerance indicated in the coordination study, or recommended by the manufacturer. Record settings as found, and as revised .2 Relay Testing 1. Use special test equipment and methods as available from the relay manufacturer. Take all precautions recommended by the manufacturer. CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 15 of 18 DATE: April 2012 2. .3 Include a copy of the relay manufacturer’s test and commissioning schedule as part of the test report. 3. Submit calculations to substantiate current/voltage figures used in tests where these are not obvious. Protective Relay Testing, Power Monitor Testing 1. For motor protection relays and similar relays, use 3-phase current for unbalanced protection testing, unless recommended otherwise by the manufacturer. 2. Use 6-channel current relay (3-phase line, 3-phase load) test units, or equivalent for differential protection relays. .16 Power Monitoring .1 General 1. Conduct inspections and tests, and compile test results on setup and test sheets approved by the Consultant. 2. Conduct tests on all power monitors and power monitoring features on protective relays. Verify current transformer and potential transformer 3. windings. 4. Verify and correct, if necessary, current transformer and potential transformer orientation and polarities. Verify correct power flow direction. .2 Power Monitor Testing – General 1. Use special test equipment and methods as available from monitor manufacturer. Take all precautions recommended by the manufacturer. 2. Include a copy of power monitor manufacturer’s test and commissioning schedule as part of the test report. 3. Submit calculations to substantiate current/voltage figures used in tests where these are not obvious. 4. Verify current transformer and potential transformer windings. .3 Protective Relay Testing, Power Monitor Testing 1. Use 3-phase current and voltage relay test units for verification of power monitoring devices, including verification of power flow quadrant. .4 Approved Suppliers: 1. Schneider Canada Inc. 1. Eaton Yale Company Inc. Cutler Hammer. .17 Coordination Study Related Calibration and Testing .1 Test and calibrate, using relay test equipment, all settings as indicated by the coordination study, and approved by the Consultant. Show “as found” and “as left” settings and test results. CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 16 of 18 DATE: April 2012 .2 .3 .4 .18 Test and calibrate new breakers that have been installed after the coordination study. Incorporate test results as part of the study. Relays (including, but not limited to: feeder protection, differential protection, synchronization, generator protection and transformer protection), motor starters relays and power meters to be calibrated and tested prior to final energization. Listing relays (including, but not limited to; feeder protection, differential protection, synchronization, generator protection and transformer protection), motors starters relays and power meters to be calibrated and tested during switchovers or scheduled power outages. (Thermo graphic Scan) / (Ultrasonic Scan) Survey .1 Visual and Mechanical Inspection 1. Remove all necessary covers prior to scanning. 2. Inspect for physical, electrical, and mechanical condition. 3. Conduct survey on (120/208V), (347/600V), electrical distribution equipment indicated on the Drawings or defined below: 1. All dry type transformers. 2. All 600 V and 208 V 3-phase panelboards. 3. All starters. 4. All UPS’s. .2 Test Parameters 1. Scanning/detection system shall have the ability to detect 1ºC difference between subject area and reference at 30ºC. 2. Equipment shall detect emitted radiation and convert detected radiation to visual signal. 3. Infrared surveys shall be performed during periods of the maximum loading possible but at a minimum of twenty percent (20%) of rated load of the electrical equipment being inspected. .3 Test Results 1. Interpretation of temperature gradients requires an experienced technician with a minimum of 5 years of experience within the last 5 years in this type of work. Some general guidelines are: 1. Temperature gradients of 3ºC to 7ºC indicate a possible deficiency and warrant investigation. 2. Temperature gradients of 7ºC to 15ºC indicate a deficiency; repair as quickly as possible. CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING Page 17 of 18 DATE: April 2012 3. 4. .4 .19 Temperature gradients of 16ºC and above indicate a major deficiency; repair immediately. Provide infrared and digital photo recording (thermo-grams) of each irregularity. Submit an electronic photograph of the general area around the hot spot. Label and identify the data/photo clearly. Report Sheets 1. Report shall be provided in accordance with subsection 2.2 above, and shall include the following: List of equipment that was scanned by 1. name. 2. Deficient items shall be identified on a separate page to consist of the following: Equipment identification and location. 1. 2. Photograph of item 3. Thermograph of item 4. Temperature measurement in degrees Celsius (ºC) of the following: 1. Defective component. 2. Reference component 3. Over temperature of component. 4. Difference to ambient temperature. 5. Electrical load on device during inspection: 1. Phase unbalance, if present. 2. Probable cause of deficient item. 3. Recommendation for corrective action. Load Survey .1 Measure and record Phase-to-Phase Voltage, Phase to Neutral Voltage, Phase Current, Neutral Current and Ground Current of the following: All 208 Volt Panelboards. 1. 2. All primaries and secondaries of all dry type transformers; record tap settings. 3. All inputs and outputs of all UPS units. .2 Measure and record Magnitudes of Harmonic Phase and Neutral Currents at all of the equipment mentioned in subsection 3.1. Identify the current magnitudes for the 3rd, 5th, 7th, 9th, 11th, 13th, 15th, 17th, 19th and 21st harmonic (based on 60 Hz). CONTRACT NO. T-12-16 Section 16031 INSPECTION AND TESTING DATE: April 2012 Page 18 of 18 .3 .4 .5 Utilize test instruments with a maximum error of ±2% and submit two signed, dated and bound copies of typed result sheets to the Consultant. Measure power quality standard measurements: sags, swells, and wave shape fault events, rms volts, rms amps, and frequency summaries. Measure transients to 1000 volts peak, 130 microseconds duration. Measure at the main switchboard, power Consumption: Watts, VA, VAR, PF (true and displacement), Demand, KWh. END OF SECTION CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 PART 1. 1.1 1.2 1.3 Section 16050 2006-08-30 Page 1 of 16 GENERAL Summary .1 Comply with the requirements of Division 1 - General Requirements and Section 16010 - Electrical General Requirements. .1 Section 16010 – Electrical General Requirements .2 Section 16016 – Staging and Transition .3 Section 16335 – Temporary and Transition Electrical Equipment .1 Canadian Standards Association (CSA). .1 CSA C22.2 No. 0 General Requirements – Canadian Electrical Code – Part 2. .2 Comply with the latest editions of CSA C22.1 Canadian Electrical Code – Part 1, Provincial Electrical Authority Safety Codes and Bulletins, and local codes and requirements which govern the installation. Where these regulations conflict, comply with the most stringent condition. .3 Comply with latest editions of the CSA Certification Standards and Bulletins. .4 CAN3-C235 Preferred Voltage Levels for AC Systems, 050,000 V. .2 Electrical Equipment Manufacturers' Association of Canada (EEMAC). .3 National Electrical Manufacturers Association (NEMA). .4 Institute of the Electrical and Electronic Engineers (IEEE). .5 Insulated Cable Engineers Association (ICEA). .6 Canadian Gas Association (CGA). .7 Underwriters Laboratories Inc. (UL) and Underwriters Laboratories Canada (ULC). .8 American National Standards Institute (ANSI). .9 National Fire Protection Agency (NFPA). .10 Electrical Safety Authority (ESA). .11 Instrument Society of America (ISA): RP12.6, Wiring Practices for Hazardous (Classified) Locations Instrumentation – Part I: Intrinsic Safety. Related Sections References CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 1.4 1.5 1.6 1.7 Section 16050 2006-08-30 Page 2 of 16 Definitions .1 The following are definitions used in Division 16 - Electrical. Refer also to Division 1 – General Requirements. .2 Inspection Authority means the Electrical Safety Authority or the Ministry of Labour. .3 Supply Authority is Power Stream Corporation, which is the electrical power company responsible for delivering electrical power to the Site. .4 Electrical Code or Code means Ontario Electrical Safety Code. .5 CEC means latest edition of the Canadian Electrical Code. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16050 – Basic Materials & Methods as indicated in Schedule ‘A’ of the Bid Form. .1 Shop Drawings: .1 Device boxes for use in hazardous areas. .2 Junction and pull boxes used at or below grade. .3 Large junction and pull boxes. .4 Terminal junction boxes. .5 Panelboards and circuit breaker data. .6 Wiring devices. .7 Control devices. .8 Control relays. .9 Timers .10 Fuses. .11 Magnetic contactors. .12 Transformers. .2 Information Submittals: Test Report: Sound test certification for dry type power transformers (0 to 600-volt, primary). .1 UL Compliance: Materials manufactured within scope of Underwriters Laboratories shall conform to UL Standards and have an applied UL listing mark. .2 Hazardous Areas: Materials and devices shall be specifically approved for hazardous areas of the class, division, and group shown and of a construction that will ensure safe performance when properly used and maintained. Measurement and Payment Submittals Quality Assurance CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 1.8 1.9 Section 16050 2006-08-30 Page 3 of 16 Extra Materials .1 Furnish, tag, and box for shipment and storage the spare parts and special tools required for maintenance in accordance with the manufacturer’s requirements. .1 Six of each type and each current rating installed .1 Equipment Enclosures: Compatible with the room or area environment where the equipment is located and unless otherwise indicated in the Contract Documents, shall be in accordance with classification specified in Section 16010 – Electrical General Requirements .2 Finishes: Unless otherwise indicated in the Contract Documents, factory finish all equipment inside and outside with ANSI/ASA #61 grey paint. Fuses, 0 to 600 Volts: PART 2. PRODUCTS 2.1 2.2 General Individual Magnetic Motor Starters and Contactors .1 Approved Suppliers/Manufacturers: .1 Cutler-Hammer by Eaton Corporation .2 Schneider Canada Inc. (Square D) .3 Siemens Canada Ltd. .2 Magnetic motor starters: Combination type, full voltage,reduced voltage or multi-speed type, reversing or non-reversing, EEMAC Size 1 minimum, rated for system fault capacity as indicated in the Contract Documents or required to complete the scope of the Work. Intermediate EEMAC sizes are not acceptable. .3 Overload relays: Adjustable, ambient temperature compensated, manually resettable from enclosure door, one element for each ungrounded phase. .4 Overload relay heaters: Field installed, selected to match installed motor nameplate data. .5 Contactor: Electrically drawn in and held. .6 Reversing starters: Contactors mechanically and electrically interlocked. .7 Circuit disconnecting means: Circuit breaker as indicated in the Contract Documents. .8 Motor starter circuit breaker: Moulded case, with adjustable magnetic only trips. Must coordinate with thermal overload device. CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 2.3 Section 16050 2006-08-30 Page 4 of 16 .9 Mechanical interlock: Prevent opening of the door when disconnecting device is in the ON position. .10 Control transformer: Fused 120 V secondary winding, unfused leg grounded. .11 Auxiliary contacts: In addition to contacts indicated in the Contract Documents, a minimum of one normally open and one normally closed spare contact with separate poles. .12 Operator devices: Heavy duty, industrial, oil tight, functions as indicated in the Contract Documents (pushbuttons, selector switches and indicating lights), rated 120 V AC, wired to terminal blocks. .13 Indicating lights: Integral transformer type, 12 V secondary, pushto-test with long life incandescent or clustered LED lamps replaceable from the front without disconnecting power. .14 Heater and lighting contactors: Similar to magnetic motor starters, but without thermal overload devices. .15 Heater and lighting circuit breakers: Moulded case, with integral thermal magnetic trips, interrupting rating 18,000 A RMS symmetrical minimum at 600 V. .16 Internal power wiring: Stranded copper, minimum #12 AWG, rated 600 V, sized to accommodate the largest load that the starter is capable of switching. .17 Control wiring: Stranded copper, minimum #14 AWG, 600 V rated. Utilize extra flexible conductors for wiring to panel doors. .18 Wire identification: Oil-resistant, Type Z markers by Wieland Electric Inc. at conductor ends. Adhesive cloth or Mylar types will not be accepted. .19 Terminal blocks: Compression type, modular, 25 A, 600 V minimum, identified with numbers identical to wire numbers. Supply a minimum of six spare terminal blocks. .20 Maximum number of wires under each terminal screw: Two. .21 Wiring and schematic diagram: Permanently mounted inside enclosure. .1 General purpose relays: Heavy duty, industrial, EEMAC rated, electrically held, 120 V AC coil, minimum 10 A, 120 V AC convertible contacts, Type P by Rockwell Automation Canada Ltd (Allen-Bradley Canada Ltd), Type X by Schneider Electric Ltd Square D Canada, or Type AR by Cutler-Hammer Canada. by Eaton Yale Company .2 Magnetic latching relays: Heavy duty, industrial, EEMAC rated, magnetically held, electrically released, 120 V AC coil, minimum 10 A, 120 V AC convertible contacts Control Relays CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 .1 2.4 Section 16050 2006-08-30 Page 5 of 16 Type NM by Rockwell Automation Canada Ltd (AllenBradley), Type XL by Schneider Canada Inc. (Square D), Type ARML by Eaton Yale Company (Cutler-Hammer). .3 Timing relays: ON delay, OFF delay or Interval type as indicated in the Contract Documents, 120 V AC coil, minimum 10A, 120 V AC convertible contacts, knob adjustable timing, timing range as indicated in the Contract Documents, .1 Type PT, or NT by Rockwell Automation Canada Ltd (Allen-Bradley), Type X by Schneider Canada Inc. (Square D), Type ARPT by Eaton Yale Company (Cutler-Hammer). .4 Double voltage relays: Convertible contacts, number and type as indicated, metal barrier between coil and contact terminations, where required by the Inspection Authorities. .5 Thermistor relays: Type 3UN2100 or 3UN2131-1A by Siemens Canada Limited (Siemens Electric Ltd.) compatible with the respective motor winding temperature sensors (thermistors). .1 Acceptable manufacturers: .1 Eaton Yale Company (Cutler Hammer). .2 Siemens Canada Limited. .3 Schneider Canada Inc. (Square D). .2 Supply 600 V and 208/120 V panelboards from the same manufacturer. .3 Circuit breaker type panelboards: Deadfront design, equipped with double or single row, bolt-on, thermal magnetic, non-interchangeable, moulded case branch circuit breakers of the sizes and types indicated in the Contract Documents .4 Ratings: Unless otherwise indicated in the Contract Documents, circuit breaker panelboards and components with the following minimum (symmetrical) short circuit ratings: .1 600 V Power Panelboards 18,000A .2 600/347 V Lighting Panelboards 14,000A .3 208/120 V Panelboards 10,000A .5 Fusible type panelboards: Dead-front, safety switch type, double row of fusible switches. Minimum assembly rating, 100,000 A symmetrical. .6 Fusible switches: Quick-make, quick-break, heavy duty, industrial type with provision for padlocking in the OFF position and fuse holders suitable for High Rupture Capacity (“HRC”) fuses type HRC1-J. .7 Busbars: Tin-plated copper equipped with solderless lugs for incoming cables where main circuit disconnecting device is not indicated in the Contract Documents. Panel Boards CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 2.5 2.6 2.7 Section 16050 2006-08-30 Page 6 of 16 .8 Doors: With spring latches and cylinder locks keyed alike, two keys per panelboard. .9 Circuit directory: Framed Plexiglas enclosed legend, located on inside of door. .10 600 V power panelboard enclosure size: To accommodate the equivalent of 42 single pole circuit devices minimum. .11 Lock-on/lock-out devices: Minimum 10 percent of 15 A to 30A circuits provided. Turn over unused devices to Region. .12 Isolated ground bus: In designated panels as indicated in the Contract Documents. .13 Ground fault protection circuit breakers: Class A type, 120 V, automatic shunt trip, with facilities for testing and resetting as indicated in the Contract Documents. .1 Approved Suppliers: .1 Bussman Canada Inc. .2 Cooper Industries plc .3 Eaton Corporation .4 Ferraz Shawmut Canada Inc. .5 General Electric Company .6 S&C Electric Company .2 Type: As in the Contract Documents, HRC (high rupturing capacity) with fault interrupting capability of 200,000A symmetrical. .3 Rating: HRC1-J fast acting 600A maximum rating and HRC1-L, fast acting for circuits exceeding 600A. .1 Non-hazardous area: 120 V AC, low current, high decibel, vibrating, heavy duty, weatherproof, field adjustable output range, 78-103 dB at 3040 mm, Adaptahorn 876-N5 by Edwards Signaling & Security Systems, Vibratone Model 350 by Federal Signal Corp .2 Hazardous area: 120 V AC, low current, high decibel, vibrating, 100 dB at 3040 mm. Adaptahorn 878-120 by Edwards Signaling & Security Systems, Model 31X by Federal Signal Corp. .1 UL 810, NEMA CP 1, IEEE 18, and NFPA 70, Article 460. .2 Enclosed, indoor, dustproof, three-phase capacitor units containing internally mounted, indicating type, high interruptingcapacity, current-limiting fuses with blown fuse indicator and discharge resistors. Fuses Horn Industrial Capacitors CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 2.8 2.9 Section 16050 2006-08-30 Page 7 of 16 .3 Kilovar (KVAR) Ratings: .1 Kilovar ratings of capacitors connected to individual motor circuits were selected based on expected motor power factor. .2 Check motor nameplate and manufacturer’s power factor and no-load current data for actual motor installed. .3 Reduce capacitor kVAR if required, so the size does not exceed the motor manufacturer’s recommended maximum size, .4 Approved Manufacturers: .1 Eaton Corporation .2 General Electric Co. .3 Square D Co. .1 Supply distribution transformers of one manufacturer throughout the Contract where indicated in the Contract Documents. .2 Approved Suppliers/Manufacturers: .1 Schneider Electric .2 Cutler-Hammer by Eaton Corporation .3 Delta Transformers, Inc. .3 Design: General purpose, dry type, air cooled, 60 Hz, low sound level with vibration isolators, rating and voltages as indicated in the Contract Documents. .4 Insulation: Class 185ï‚°C minimum with a maximum 80ï‚°C temperature rise in 40ï‚°C ambient, Windings: Copper, delta connected primary, wye connected secondary with neutral grounding provision. .5 Mounting accessories: Mounting brackets for wall or ceiling suspension as required. .6 Enclosures: Ventilated, sprinkler proof in office areas and electrical rooms; and non-ventilated in plant areas. .7 Maximum Sound Level: NEMA ST 20: .1 40 decibels for 0 to 9 kVA. .2 45 decibels for 10 to 50 kVA. .3 50 decibels for 51 to 150 kVA. .4 55 decibels for 151 to 300 kVA. .5 60 decibels for 301 to 500 kVA. Distribution Transformers Convenience and Power Receptacles .1 Convenience receptacles: Heavy duty, specification grade, 5262 series, duplex, polarized, three wire grounding, 15A rating or as otherwise indicated in the Contract Documents, 125 V AC, white, with terminals suitable for side or back wiring and break-off fin for two-circuit use. CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 .1 Section 16050 2006-08-30 Page 8 of 16 Approved Manufacturers: 1. Hubbell Canada Inc.; 2. Arrow-Hart, Cooper Wiring Devices; 3. Bryant Wiring Devices, Hubbell Incorporated; 4. Slater Industries Inc.; 5. Smith & Stone Inc.; 6. Leviton Canada Ltd.; 7. Pass & Seymour Canada Inc. .2 Single outlet receptacles: Heavy duty, specification grade, 5261 series, specification grade, three wire grounding, polarized, 15A rating or as otherwise indicated in the Contract Documents, 125 V AC, white bakelite, with terminals suitable for side or back wiring. Supply twist lock type where indicated in the Contract Documents. .1 Approved Manufacturers: 1. Hubbell Canada Inc.; 2. Arrow-Hart, Cooper Wiring Devices; 3. Bryant Wiring Devices, Hubbell Incorporated; 4. Smith & Stone Inc. 5. Pass & Seymour Canada Inc. 6. Leviton Canada Ltd. .3 Corrosion resistant receptacles: For below grade and outdoor applications. .1 Approved Manufacturers: 1. Bryant Wiring Devices, Hubbell Incorporated 2. Smith & Stone Inc. 3. Arrow-Hart, Cooper Wiring Devices 4. Hubbell Canada Inc. 5. Pass & Seymour Canada Inc. .4 Power receptacles: Heavy duty, specification grade, single outlet duplex, three wire grounding, 15 ampere rating or as indicated in the Contract Documents, 250 V AC, ivory Bakelite, with terminals suitable for either side or back wiring. .1 Approved Manufacturers: 1. Hubbell Canada Inc. 2. Arrow-Hart, Cooper Wiring Devices 3. Bryant Wiring Devices, Hubbell Incorporated 4. Leviton Canada Ltd. .5 Polyphase power receptacles: Heavy duty, specification grade, three pole, four wire grounding, ampere rating as indicated, 250 V AC, single outlet, black bakelite, with pressure type terminals. Hubbell Canada Inc., Arrow-Hart, Cooper Wiring Devices. .1 Approved Manufacturers: 1. Hubbell Canada Inc. 2. Arrow-Hart, Cooper Wiring Devices 3. Bryant Wiring Devices, Hubbell Incorporated 4. Leviton Canada Ltd. CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 Section 16050 2006-08-30 Page 9 of 16 .6 Welder receptacles: Heavy duty, weatherproof, single outlet, four wire, four pole, 60 A, 600 V AC, black bakelite, pressure type terminals, cast iron back box, angle adapter and spring loaded cover .1 Approved Manufacturers: 1. AREA Series manufactured by Cooper CrouseHinds, 2. WR Series manufactured by Killark Electric Manufacturing Company, 3. Star-line Series manufactured by Pyle National of Canada Inc., or 4. ADJA Series manufactured by Appleton Electric Limited. .7 Ground fault interrupter receptacle: Class A type, rated 15A, 120 V, circuit interrupter, duplex type, ivory bakelite, integral solid state ground sensing, facility for testing. .1 Approved Manufacturers: 1. Arrow-Hart, Cooper Wiring Devices 2. Leviton Canada Ltd. 3. Bryant Wiring Devices, Hubbell Incorporated 4. Pass & Seymour Canada Inc. .1 Switch: Specification grade, flush mount, back and side wired, ivory high strength toggle, rated 20 A, 120 V AC. .1 Approved Manufacturers: 20 AC Series manufactured by Pass & Seymour 1. Canada Inc., 2. GE595 Series manufactured by Smith & Stone Inc. 3. 490 Series manufactured by Bryant Wiring Devices 4. 199 Series manufactured by Arrow-Hart, Cooper Wiring Devices 5. 122 Series manufactured by Hubbell Canada Inc. 6. 122 Series manufactured by Leviton Canada Ltd. 2.10 Limit Switches 2.11 Switch and Receptacle Cover Plates .1 Flush mounted switches and receptacles in dry locations: Type 302 stainless steel, 0.8 mm thick, with a brushed finish. .2 Surface mounted, dry location switch cover plates: Cast ferrous alloy type, guarded, gasketted. .1 Approved Manufacturers: 1. DS32G manufactured by Cooper Industries Ltd. Cooper Crouse-Hinds, 2. FSTG manufactured by Killark Electric Manufacturing Co., or 3. FSK-ITSG manufactured by Appleton Electric Ltd. CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 Section 16050 2006-08-30 Page 10 of 16 .3 Wet, damp and corrosive area switch cover plates: Cast ferrous alloy, epoxy coated, gasketted, toggle type, .1 Approved Manufacturers: 1. DS185 manufactured by Cooper industries Ltd. Crouse-Hinds, 2. FS-1-WSCA manufactured by O-Z/Gedney Inc., or 3. FZ type manufactured by Killark Electric Manufacturing Co. .4 PVC conduit system switch cover plates: Gasketted, PVC, toggle type, .1 Approved Manufacturers: 1. VSC 15/10 manufactured by IPEX Inc., or 2. E98TSC manufactured by Thomas & Betts Ltd., Carlon. .5 Receptacle outlet cover plates: Weatherproof, gasketted, cast ferrous or aluminum, with self closing, spring loaded covers, .1 Approved Manufacturers: 1. WLR Series manufactured by Crouse-Hinds, 2. FCL Series manufactured by Killark Electric Manufacturing Co., or 3. FSK-WR Series manufactured by Appleton Electric Ltd. 4. PVC conduit system receptacle cover plates: Gasketted, PVC, with self closing, spring loaded covers, or W Series BY IPEX Inc., E98GDR by Thomas & Betts Ltd Carlon. .6 Multi-gang outlets: except in office and finished areas, multiple single gang covers only. Multi-gang covers are not acceptable. 2.12 Low Voltage, Secondary Surge Protective Equipment .1 NEMA LA 1, ANSI C62.11. .2 Surge Capacitor: .1 Impregnated with non-PCB, biodegradable dielectric fluid. .2 Integral discharge resistor which will drain residual voltage to 50-volts crest in less than 1 minute after disconnection from circuit. .3 Arrestor: High strength metal oxide valve elements enclosed in high strength, corrosion-resistant, molded resin housing. .4 Equip capacitor and arrestor with mounting nipple, flat washer, and nut suitable for knockout or bracket mounting. 2.13 Support And Framing Channels .1 Carbon Steel Framing Channel: .1 Material: Rolled, mild strip steel, 12-gauge, ASTM A1011/A1011M, Grade 33. .2 Finish: Hot-dip galvanized after fabrication. CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 Section 16050 2006-08-30 Page 11 of 16 .2 Paint Coated Framing Channel: Carbon steel framing channel with electro-deposited rust inhibiting acrylic or epoxy paint. .3 PVC Coated Framing Channel: Carbon steel framing channel with 40-mil polyvinyl chloride coating. .4 Stainless Steel Framing Channel: Rolled, ASTM A167, Type 316 stainless steel, 12-gauge. .5 Extruded Aluminum Framing Channel: .1 Material: Extruded from Type 6063-T6 aluminum alloy. .2 Fittings fabricated from Alloy 5052-H32. .6 Nonmetallic Framing Channel: .1 Material: Fire retardent, fiber reinforced vinyl ester resin. .2 Channel fitting of same material as channel. .3 Nuts and bolts of long glass fiber reinforced polyurethane. .7 Approved Manufacturers: .1 B-Line Systems, Inc. .2 Unistrut Corp. .3 Allied Electrical Group Inc. - Aickenstrut. .1 Material: Laminated plastic. .2 Attachment Screws: Stainless steel. .3 Color: White, engraved to a black core. .4 Engraving: .1 Pushbuttons/Selector Switches: Name of drive controlled on one, two, or three lines, as required. .2 Panelboards: Panelboard designation, service voltage, and phases. .1 Pushbuttons/Selector Switches: 3-mm. .2 Panelboards: 6-mm. .1 General: Provide matting having a breakdown of 20 kV minimum. .2 Manufacturer: U.S. Mat and Rubber Company or approved equivalent. 2.14 Nameplates 2.15 Letter Height: 2.16 Switchboard Matting CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 Section 16050 2006-08-30 Page 12 of 16 2.17 Uninterruptible Power Supplies (UPS) .1 Approved Suppliers/manufacturers: APC (American Power Conversion) by Schneider Electric or approved equivalent. .2 Type: On-line, no-break, batteries continuously in circuit, with static bypass, suitable for powering the loads as indicated in the Contract Documents. .3 Rating: Minimum 5kVA rating or as indicated in the Contract Documents, 120 V AC, single phase, 60 Hz input, 120 V AC, single phase, 60 Hz output. .4 Voltage regulation: ±5% maximum for line or load changes from 0 to 100% under any battery condition. .5 Surge protection: Comply with category B, ANSI/IEEE C62.41 and ANSI/IEEE C62.45. .6 Frequency: Input synchronized with supply, output 60 Hz ±0.5%. .7 Total harmonic distortion: 5% maximum. .8 Battery: Sealed, maintenance free, with a minimum 10-year life, rated to supply full load output at the rated voltage for a minimum of 10 minutes minimum. .9 Metering: Indicate the following: .1 AC Input Current .2 AC Output Current .3 AC Output Voltage .4 Output Frequency .5 DC Voltage .10 Fault indication: One normally open and one normally closed, voltage free, common fault contact, 2 A, 120 VAC, for remote indication. Indicate individual faults locally. .11 Input and output connections: Hard wired. Output from receptacles is not acceptable. .1 Occupancy sensors: Dual or quad element, passive infrared detectors, 3 wire, 120 V AC, rated to switch 1200 W electronic ballasted fluorescent or incandescent loads, 30 second to 20 minutes field adjustable ON-time, field adjustable ambient light sensing, built-in OFF-AUTO-ON override switch. Manufactured by Sensor Switch Inc., distributed manufactured by ESL Canada Inc. .1 Non-hazardous areas: 120 V AC, heavy duty, weatherproof, red lens. .1 Approved Manufacturers: 2.18 Occupancy Sensors 2.19 Flashing Lights CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 1. 2. 3. 4. Section 16050 2006-08-30 Page 13 of 16 AdaptaBeacon 97C Series manufactured by Edwards Signaling & Security Systems, VDAS manufactured by Cooper Crouse-Hinds, Industrial Strobe manufactured by Applied Strobe Technology Co. Ltd., 371DST manufactured by Federal Signal Corp. .2 Explosion proof areas: 120 V AC, approved for use in specific area, red lens. .1 Approved Manufacturers: AdaptaBeacon, 50REX-5 manufactured by 1. Edwards Signaling & Security Systems, 2. EV Series manufactured by Cooper Crouse-Hinds, 3. Factory Sealed Strobe manufactured by Applied Strobe Technology Co. Ltd., 4. Model 27XST Series B manufactured by Federal Signal Corp. .1 Non-hazardous area: 120 V AC, low current, high decibel, vibrating, heavy duty, weatherproof, field adjustable output range, 78-103 dB at 3040 mm, .1 Approved Manufacturers: 1. Adaptahorn 876-N5 manufactured by Edwards Signaling & Security Systems, Vibratone Model 350 manufactured by Federal 2. Signal Corp., 3. WH Series manufactured by Cooper Crouse-Hinds. .2 Hazardous area: 120 V AC, low current, high decibel, vibrating, 100 dB at 3040 mm. .1 Approved Manufacturers: 1. Adaptahorn 878-120 manufactured by Edwards Signaling & Security Systems, 2. Model 31X manufactured by Federal Signal Corp., 3. ETH High Power Horn manufactured by Cooper Crouse-Hinds. .1 Design: Dual ionization chambers, 85 dB at 300 mm piezo electric alarm, visual power on and alarm indicator, .1 Approved Manufacturers: 1. Type 330 LR manufactured by Mirtone Industries Ltd., or 2. Type 330 LR manufactured by Chubb Edwards Company. .2 Supply: 120 V, single phase, 60 Hz. .3 Auxiliary contacts: Form C, rated 120 V AC, 2A minimum. 2.20 Horn 2.21 Smoke Alarms CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 Section 16050 2006-08-30 Page 14 of 16 2.22 Motor Protection Relay .1 Approved Suppliers: .1 General Electric Company (GE) - Multilin or approved equivalent. .1 Approved Suppliers: .1 Rockwell Automation Canada Ltd (Allen-Bradley). .2 Omron Canada Inc. .3 Potter & Brumfield Inc. .4 Schneider Canada Inc (Square D). .1 Approved Suppliers: .1 Honeywell International Inc. (Micro-Switch). .2 Rockwell Automation Canada Ltd (Allen-Bradley). 2.23 Solid State Timing Relay 2.24 Valve Limit Switch 2.25 Main Power Failure Relay (Single Phase) .1 Approved Suppliers: .1 Potter & Brumfield Inc. .2 Tyco Electronics Corporation (Agastat). .3 Omron Canada Inc. 2.26 Main Power Failure Relay (Three Phase) .1 Approved Suppliers: .1 Carlo Gavazzi (Canada) Inc or approved equivalent. .1 Provide disconnect switches of the type and rating indicated in the Contract Documents. .2 Flush-mount fractional horsepower disconnect switches in concealed conduit areas. .3 Provide fusible disconnect switches complete with fuses. .4 Provide mounting pedestal for units located adjacent to equipment in open areas. PART 3. EXECUTION 3.1 3.2 Disconnect Switch Installation Manual Motor Starter Installation .1 Provide manual starters as indicated in the Contract Documents. .2 Flush-mount manual starters in concealed conduit areas. CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 3.3 3.4 3.5 3.6 3.7 Section 16050 2006-08-30 Page 15 of 16 Individual Magnetic Motor Starter and Contactor Installation .1 Provide starters and contactors as indicated in the Contract Documents. .2 Connect auxiliary control devices. .1 Provide panel-boards of type and size indicated in the Contract Documents. .2 Terminate and connect field wiring. .3 Provide fusible panelboards complete with fuses. .4 For ground fault protected circuits, wire in accordance with the manufacturer's recommendations. .1 Install fuses in mounting assembly before energizing circuit. .2 Verify that the fuses physically match mounting devices. Where fuses and holders do not match, replace the holder. .3 Provide sizes and types of fuses in accordance with the requirements of the ESA. Panel board Installation Fuses Distribution Transformer Installation .1 Provide distribution transformers, mounted in the upright position, as indicated in the Contract Documents. Verify that wall or ceiling is adequate to support transformer. Provide additional bracing as required. .2 Install transformer to permit full accessibility to wiring and tap connections. For floor mounted units, allow 150 mm of clearance from walls or other equipment to permit adequate ventilation through and around the housing. .3 Adjust vibration isolators for optimum noise suppression. Convenience and Power Receptacle and Light Switch Installation .1 Provide receptacles and light switches as indicated in the Contract Documents; the location of outlets shown on the electrical Drawings is approximate. Measure Work requiring accurate dimensions on Site or from architectural and structural Drawings. .2 Do not install outlets back-to-back in walls. Offset boxes by a minimum of 150 mm. .3 Wire ground fault circuit interrupters in accordance with the manufacturer's recommendations. .4 After interior finish is erected, make any necessary adjustments without additional charge. CONTRACT NO. T-12-16 BASIC MATERIALS & METHODS DATE: April 2012 3.8 3.9 Section 16050 2006-08-30 Page 16 of 16 Switch and Receptacle Cover Plate Installation .1 Install cover plates after painting of room surfaces. .1 Provide UPS as indicated in the Contract Documents. .2 Carry out tests and start-up procedures as recommended by the manufacturer. .3 Train the Region’s staff in all aspects of operation and maintenance of the UPS system. .1 Provide occupancy sensors as indicated in the Contract Documents. .2 Adjust and calibrate occupancy sensors in accordance with the manufacturer's recommendations. .1 Provide flashing lights and horns as indicated in the Contract Documents. .2 Adjust in accordance with the manufacturer's recommendations. .1 Install smoke detectors as indicated in the Contract Documents. .2 Interconnect smoke detectors as recommended by the manufacturer. Uninterruptible Power Supply 3.10 Occupancy Sensors 3.11 Flashing Lights and Horns 3.12 Smoke Detectors END OF SECTION CONTRACT NO T-12-16 Section 16060 GROUNDING Page 1 of 5 DATE: April 2012 PART 1. GENERAL 1.1 1.2 1.3 References .1 Canadian Standards Association (CSA) .1 CSA C22.2 No. 0.4 Bonding and Grounding of Electrical Equipment (Protective Grounding). .2 CSA C22.2 No. 41 Grounding and Bonding Equipment. .2 Ontario Electrical Safety Code (OESC) requirements. .3 Institute of the Electrical and Electronic Engineers (IEEE) .1 IEEE No. 80 IEEE Guide for Safety in AC Substation Grounding. .2 IEEE No. 837 IEEE Standard for Qualifying Permanent Connections Used in Substation Grounding. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16060 – Grounding as indicated in Schedule ‘A’ of the Bid Form. .1 Action Submittals: .1 Shop Drawings: Product data for the following: 1. Exothermic weld connectors. .2 Submit three certified copies of field test results. .1 Material: Copper .2 Diameter: Minimum 19 mm. .3 Length: 3000 mm. .1 As specified by the OESC for the current carrying conductor capacity. .2 Ground conductors in corrosive environments: Insulated or having tinned copper where in contact with aluminum or corrosive material, soil or atmosphere. .3 Grounding bus in electrical rooms where indicated in the Contract Documents: Copper, minimum 50 mm cross-section or as indicated in the Contract Documents. Measurement and Payment Submittals PART 2. PRODUCTS 2.1 2.2 Ground Rod Ground Conductors CONTRACT NO T-12-16 Section 16060 GROUNDING Page 2 of 5 DATE: April 2012 2.3 2.4 Connectors .1 Exothermic Weld Type: .1 Outdoor Weld: Suitable for exposure to elements or direct burial. .2 Indoor Weld: Utilize low-smoke, low-emission process. .3 Approved Manufacturers: 1. Erico Products, Inc.; Cadweld and Cadweld Exolon. 2. Continental Industries Inc. - Thermoweld. .2 Compression Type: .1 Compress deforming type; wrought copper extrusion material. .2 Single indentation for conductors 6 AWG and smaller. .3 Double indentation with extended barrel for conductors 4 AWG and larger. .4 Barrels pre-filled with oxide-inhibiting and anti-seizing compound and sealed. .5 Approved Manufacturers: 1. Burndy Corp. 2. Thomas and Betts Co. 3. Ilso Corp. .3 Mechanical Type: Split-bolt, saddle, or cone screw type; copper alloy material. .1 Approved Manufacturers: 1. Burndy Corp. 2. Thomas and Betts Co. .1 Ground rod box complete with cast iron riser ring and traffic cover marked GROUND ROD. .2 Approved Manufacturers and Products: .1 Slaten Industries Inc. .2 Christy Co.; No. G5. .3 Lightning and Grounding Systems, Inc.; I R Series. .1 Interconnect conduits terminating in motor control centres with bare copper conductor. Connect to MCC ground bus. .2 Ground electrical service neutral at service entrance equipment to supplementary grounding electrodes. .3 Ground each separately derived system neutral to the nearest effectively grounded building structural steel member or separate grounding electrode. Grounding Wells PART 3. EXECUTION 3.1 General CONTRACT NO T-12-16 Section 16060 GROUNDING Page 3 of 5 DATE: April 2012 3.2 3.3 .4 Bond together system neutrals, service equipment enclosures, exposed noncurrent-carrying metal parts of electrical equipment, metal raceways, ground conductor in raceways and cables, receptacle ground connections, and metal piping systems. .5 Shielded Instrumentation Cables: Ground shields at each splice or termination in accordance with the recommendations of the splice or termination manufacturer. .6 Shielded Control Cables: Ground shield to ground bus at power supply for analog .1 signal. .2 Expose shield a minimum of 1 inch at the termination to field instrument and apply heat shrink tube. .3 Do not ground instrumentation cable shield at more than one point. .1 Ground Conductors: Install in conduit containing power conductors and control circuits above 50 volts. .2 Nonmetallic Raceways and Flexible Tubing: Install equipment grounding conductor connected at both ends to noncurrent carrying grounding bus. .3 Connect ground conductors to raceway grounding bushings. .4 Extend and connect ground conductors to ground bus in all equipment containing a ground bus. .5 Connect enclosure of equipment containing ground bus to that bus. .6 Bolt connections to equipment ground bus. .7 Bond grounding conductors to metallic enclosures at each end, and to intermediate metallic enclosures. .8 Junction Boxes: Furnish materials and connect to equipment grounding system with grounding clips mounted directly on box, or with 9.5 mm machine screws. .1 Extend equipment ground bus via grounding conductor installed in motor feeder raceway; connect to motor frame. .2 Nonmetallic Raceways and Flexible Tubing: Install an equipment grounding conductor connected at both ends to noncurrent carrying grounding bus. .3 Motors Less Than 10 kW: Furnish compression, spade-type terminal connected to conduit box mounting screw. .4 Motors 10 kW and Greater: Tap motor frame or equipment housing; furnish compression, one-hole, lug type terminal Wire Connections Motor Grounding CONTRACT NO T-12-16 Section 16060 GROUNDING Page 4 of 5 DATE: April 2012 connected with minimum 5/16 inch brass threaded stud with bolt and washer. 3.4 3.5 3.6 .5 Follow the manufacturer’s recommendations. .6 Circuits 20 Amps or Greater: Tap motor frame or equipment housing; install solderless terminal with minimum 8 mm diameter bolts. .1 Install full length with conductor connection at upper end. .2 Install with connection point below finished grade, unless otherwise shown on the Contract Drawings. .3 Space multiple ground rods by one rod length. .1 Install inside buildings, asphalt, and paved areas. .2 Install riser ring and cover flush with surface. .3 Place 150 mm crushed rock in bottom of each well. .1 General: .1 Abovegrade Connections: Install exothermic weld, mechanical, or compression-type connectors; or brazing. .2 Belowgrade Connections: Install exothermic weld or compression type connectors. .3 Remove paint, dirt, or other surface coverings at connection points to allow good metal to-metal contact. .4 Notify the Consultant prior to backfilling ground connections. .2 Exothermic Weld Type: Wire brush or file contact point to bare metal surface. .1 .2 Use welding cartridges and molds in accordance with the manufacturer’s recommendations. .3 Avoid using badly worn molds. .4 Mold to be completely filled with metal when making welds. .5 After completed welds have cooled, brush slag from weld area and thoroughly clean joint. .3 Compression Type: .1 Install in accordance with the connector manufacturer’s recommendations. .2 Install connectors of the proper size for the grounding conductors and ground rods specified in the Contract Documents. Install using the connector manufacturer’s compression .3 tool having proper sized dies. Ground Rods Grounding Wells Connections CONTRACT NO T-12-16 Section 16060 GROUNDING DATE: April 2012 Page 5 of 5 .4 3.7 Mechanical Type: .1 Apply a homogeneous blend of colloidal copper and rust and corrosion inhibitor before making connection. .2 Install in accordance with the connector manufacturer’s recommendations. .3 Do not conceal mechanical connections. Metal Structure Grounding .1 .2 .3 3.8 Manhole and Handhole Grounding .1 .2 .3 .4 3.9 Ground metal sheathing and exposed metal vertical structural elements to the grounding system. Bond electrical equipment supported by metal platforms to the platforms. Provide electrical contact between metal frames and railings supporting pushbutton stations, receptacles, and instrument cabinets, and raceways carrying circuits to these devices. Install one ground rod inside each manhole. Ground Rod Floor Protrusion: 100 to 150 mm above floor. Make connections of grounding conductors fully visible and accessible. Connect all noncurrent carrying metal parts, and any metallic raceway grounding bushings to the ground rod with No. 6 AWG copper conductor. Transformer Grounding .1 .2 .3 Bond neutrals of transformers within buildings to the system ground network, and to any additional indicated grounding electrodes. Bond neutrals of substation transformers to the substation grounding grid and system grounding network. Bond neutral of pad mounted transformers to network of four locally driven ground rods. 3.10 Surge Protection Equipment Grounding .1 Connect surge arrestor ground terminals to the equipment ground bus. .1 As specified in Section 16031 – Inspection and Testing. 3.11 Field Quality Control END OF SECTION CONTRACT NO T-12-16 Section 16122 WIRES AND CABLES Page 1 of 11 DATE: April 2012 PART 1. 1.1 1.2 1.3 1.4 GENERAL Intent of Section .1 This Section describes the main types of wires and cables to be installed in this Contract, as well as any special installation procedures and precautions. .1 Canadian Standards Association (CSA) .1 CSA C22.2 No. 131 Type TECK 90 Cables. .2 CSA C22.2 No. 38 Thermoset Insulated Wires and Cables. .3 CSA C22.2 No. 174 Cables and Cable Glands for use in Hazardous Locations. .4 CSA C68.3 Power Cables with Thermoset Insulation. .5 CSA C21.1 600 V Control Cable. .6 CSA C21.2 300 V Control Cable. .2 Insulated Cable Engineers Association, Inc. .1 ICEA S-66-524. .3 All power cables must be CSA approved for application. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16122 – Wires and Cables as indicated in Schedule ‘A’ of the Bid Form. .1 Number and sizes of wires (and associated raceways) indicated in the Contract Drawings are based on free air ratings and are not necessarily the exact number and sizes required for specific installation conditions. Wire or cable sizes smaller than indicated in the Contract Documents are not acceptable. .2 Unless otherwise indicated in the Contract Documents, every cable run from a source to a load is to include an appropriately sized separate ground wire, and the ground wire properly bonded and grounded. The following designations are used within the Contract Documents and the Contract Drawings: .1 All cables designed as “3c” infers 3 conductor cable plus ground conductor, within conduit this may be equivalent to “4#”. .2 All cables designed in a 3 phase, 3 wire system designated as “4#”, infers 3 branch conductors and one ground conductor of equal size as branch conductors. .3 All cables designed in a 3 phase, 4 wire system designated as “5#”, infers 3 branch conductors, one References Measurement and Payment Design Requirements CONTRACT NO T-12-16 Section 16122 WIRES AND CABLES Page 2 of 11 DATE: April 2012 neutral conductor and one ground conductor, all conductors sized as the branch conductors. 1.5 1.6 .3 Unless otherwise indicated in the Contract Documents, combine motor or electric heater branch power wiring (below 1000V) and associated local operator control or field control device wiring into a common conduit between motor or heater and its starter or motor control centre, provided all of the following conditions are met: .1 Motor circuit does not exceed 600 V. .2 Conductors and termination fittings for power and control circuits are rated 600 V minimum. .3 Control circuits are designed to operate at 120 V AC or higher. Install wiring for control circuits operating below 100 degrees Celsius AC or with DC in a separate conduit system. .4 Power conductors do not exceed #2AWG in size. .5 Control circuit wiring solely associated with respective motor or heater. Install wiring for control circuits of other equipment and systems, or wiring common to two or more pieces of equipment in separate conduits. .4 Supply spare conductors in control, communication and instrumentation cable circuits as follows: .1 Two to eight utilized conductors in one conduit or cable: two spare conductors. .2 Nine or more utilized conductors: 20 percent or three spare conductors, whichever is greater. .5 No loose wiring or wire ends are accepted. Use manufacturer recommended connectors when installing cables. Use TECK cable connectors terminated in grounded steel plate for all TECK cable terminations. Grounding and attachment to unistrut not acceptable. .1 Cap or seal cable ends to prevent water penetration into cable. Reseal after cutting length of cable. .2 Cables stored with ends unsealed will be immediately removed from the Site at the Contractor’s own expense. At no extra cost to the Region, the Contractor shall also replace cables to the satisfaction of the Consultant. .1 4.16 kV, 60 Hz, grounded wye, 3 phase, 3 wire. Storage Supply Characteristics CONTRACT NO T-12-16 Section 16122 WIRES AND CABLES Page 3 of 11 DATE: April 2012 PART 2. PRODUCTS 2.1 Manufactured Products .1 Comply with the standards listed in Subsection 1.2- References of this Section. .2 Medium Voltage Insulated Cables (5000 Volt): .1 Acceptable manufacturers: 1. Phillips Cables Limited 2. Pirelli Cables Inc, Anixter 3. Aetna Insulated Wire .2 Rating: Cables shall be rated at 5 kV, application is 4.16 kV, refer to subsection 1.6 “Supply Characteristics” above. Conductors: Stranded, annealed copper, class B .3 stranding, size as indicated in the Contract Documents. .4 Insulation: extruded cross-linked polyethylene (XLPE) or ethylene propylene rubber (EPR) compound. Suitable for installation in wet areas and suitable for handling at minus 40 degrees Celsius ambient, 90 degrees Celsius maximum conductor temperature. .5 Insulation level: 100 percent over each conductor. .6 Insulation shield: Semi-conducting thermosetting XLPE material applied over the insulation. .7 Metallic shield: Lapped copper tape or served copper wire. .8 Grounding conductor: Uninsulated, Class B stranded, soft bare copper conductor in multiconductor cable, concentric copper wires over insulation shield in single conductor cable. .9 Armour: where indicated in the Contract Documents, TECK construction, interlocking galvanized steel or aluminum armour over jacketed cable assembly (only aluminum on single conductor cables). .10 Non-Armoured cable: where indicated in the Contract Documents, Type RW90 (or equivalent CSA approved designation). Inner and outer jacket: PVC, moisture and oil resistant, .11 flame retardant composition, FT4, extruded, suitable for minus 40 degrees Celsius applications and of low acid gas evolution. Outer jacket colour, orange. .12 Multi-conductor cables: Suitable fillers and binders. .3 Low Voltage Unarmoured Wire and Cable (1000 V and Below) .1 Acceptable manufacturers: 1. Phillips Cables Limited 2. Alcatel Canada Wire Inc. 3. Pirelli Cables Inc. 4. United Wire of Canada. .2 Construction: Stranded, annealed copper conductors, 600 V minimum rating for conductors #10 AWG and CONTRACT NO T-12-16 Section 16122 WIRES AND CABLES Page 4 of 11 DATE: April 2012 .3 .4 .5 .6 .7 .8 .9 .4 smaller and 1000 V rating for conductors larger than #10 AWG, RW90 cross-linked polyethylene (XLPE) insulation, suitable for handling at minus 40 degrees Celsius ambient, 90 degrees Celsius maximum conductor temperature, limited flame spread FT4, jacketed. Direct buried installations or installation in direct buried PVC conduit: Cross-linked polyethylene (XLPE), RWU90 insulation, 1000 V minimum rating, jacketed. Standard: CSA C22.2 No. 38. Minimum conductor sizes: Unless otherwise indicated in the Contract Drawings, #12 AWG for power and current transformer circuits; #14 AWG for control circuits and fire alarm circuits; #16 AWG for PA circuits; telephone wiring to comply with telephone utility standards. Multi-conductor cables: PVC flame retardant black jacket overall, suitable for handling at minus 40 degrees Celsius, flame test rated FT4. Lighting wiring: GTF wire, 600 volt, 125 degrees Celsius, flexible copper conductor for connections between luminaire and outlet boxes. Colour coding: For insulated conductors, conform to the following: 1. 1-conductor power - Black (Phase Conductors) - White (Neutral) 2. 1-conductor control - Red 3. 2-conductor power - Black, White 4. 3-conductor power - Red, Black, White (Neutral) - Red, Black, Blue 4-conductor power - Red, Black, Blue, White 5. 6. Multi conductor cables - Manufacturer’s standard Insulated ground conductors forming part of a multiconductor cable assembly: Inspection Authority colour coding. Low Voltage Armoured Wire and Cable (1000 V and Below) .1 Acceptable manufacturers: 1. Phillips Cables Limited 2. Anixter International 3. Alcatel Canada Wire Inc. 4. Pirelli Cables Inc. 5. United Wire and Cable. .2 Construction: Stranded, annealed copper conductors, 1000 V rating, RW90 cross-linked polyethylene (XLPE) insulation, suitable for handling at minus 40 degrees Celsius ambient, 90 degrees Celsius maximum conductor temperature, flame test rated FT4. .3 Power cabling: TECK construction. .4 Control cabling: TECK construction. CONTRACT NO T-12-16 Section 16122 WIRES AND CABLES Page 5 of 11 DATE: April 2012 .5 .6 .7 .8 .9 .10 .11 .5 Lighting and receptacle branch wiring in office areas: BX construction. Minimum conductor size: Unless otherwise indicated in the Contract Documents, #12 AWG for power and current transformer circuits and #14 AWG for control and fire alarm circuits. Grounding conductor: Stranded, soft, bare copper conductor in multiconductor cables, concentric copper wires over insulation in single conductor cable. Multi-conductor cables: With inner jacket of suitable PVC (minus 40ï€ degrees Celsius). Interlocking armour: Flexible, galvanized steel or aluminum for multi-conductor cables and aluminum for single conductors, spirally wound over inner jacket. Outer jacket: PVC (minus 40 degrees Celsius), flame-retardant, FT4 flame test rated, low acid gas evolution, black outer jacket extruded over the armour. Colour coding: For insulated conductors, conform to the following: 1. 1-conductor power - Black (Phase Conductors) 2. 1-conductor control - Red 3. 2-conductor cable - Black, White 4. 3-conductor cable - Red, Black, White (Neutral) - Red, Black, Blue 5. 4-conductor cable - Red, Black, Blue, White 6. Multi conductor cables - Manufacturer’s standard Instrumentation Wiring .1 Conductors: #16 AWG, 7 strand minimum, tinned copper, unless otherwise indicated in the Contract Documents, 300 V minimum insulation. .2 Construction: Twisted pair, triplet and quad grouping with nominal 50 mm staggered lay and 100 percent aluminumMylar tape shield with minimum 25 percent overlap. .3 Drain wire: Over each group, bare, #20 AWG minimum, tinned copper, in direct continuous contact with shield. .4 Jacket: PVC (minus 40ï€ degrees Celsius) low acid gas, FT4 rated low flame spread. .5 Identification: Each grouping (pair, triplet, quad) by consecutive number coding, permanently marked at 25 mm intervals. .6 Armour: For exposed or direct buried cables, aluminum or steel interlocking armour with overall PVC jacket. General purpose instrumentation cable: 16 AWG, Type .7 #9316 by Belden Wire and Cable. .8 RS485 cables: 2 pair, 16 AWG stranded copper, separately twisted pairs, overall 100 percent aluminumpolyester shield, tinned copper stranded drain wire by Belden Wire and Cable. CONTRACT NO T-12-16 Section 16122 WIRES AND CABLES Page 6 of 11 DATE: April 2012 .9 .10 .11 .6 Termination fittings: Type, configuration and gender required to connect cable directly to equipment without additional adapters or fittings. Data highway communication cable: Stranded, tinned copper conductor with aluminum armour and overall PVC jacket, 18 AWG, Type #9463 by Belden Wire and Cable. For analog signal wiring, use uniformly twisted shielded pairs not smaller than CSA 0.823 mm2 (18 AWG) with a minimum of six twists per 300mm (one foot). Separate analog signal wiring at least 150mm (six inches) from power wiring. Provide continuous foil or metalized plastic shields with 100 percent coverage. Include a drain wire in continuous contact with the shield. Multiple cables must have an overall shield and individual shields for each signal cable. Control Wiring .1 Size and install all wire and cable in accordance with CSA, Ontario Electrical Safety Code, IEEE and all other applicable electrical safety codes. .2 Terminate all internal panel wiring to external devices at the terminal strips. Connect all field wiring to one side of the terminal strip. Connect all panel wiring to be connected to the opposite side. Arrange terminals for external connects in consecutive order for conductors within a given cable. .3 Use flexible, stranded, copper TEW wiring. Run wires in continuous lengths from terminal to terminal. Do not splice wires. .4 For analog signal wiring, use uniformly twisted shielded pairs not smaller than CSA 0.823 mm2 (18 AWG) with a minimum of six twists per 300mm (one foot). Separate analog signal wiring at least 150mm (six inches) from power wiring. Provide continuous foil or metalized plastic shields with 100 percent coverage. Include a drain wire in continuous contact with the shield. Multiple cables must have an overall shield and individual shields for each signal cable. .5 Use CSA 2.5 mm2 (14 AWG) or larger for control signal wiring. CSA 2.5mm² ( 14 AWG) requires approval from the Electrical Safety Authority (ESA) and/or Power Stream Inc. .6 Segregate signal wiring from control power wiring: group functionally, and arrange neatly to facilitate tracing of circuits. Arrange wiring, respective terminals and 25 percent spare in separate mounting rails according to the following categories: 120V AC, 24V DC signal, 24V DC control, communication wiring. .7 Use plastic wiring wraps to bundle wires, outside of wiring ducts. Securely fasten the bundles to the steel structure at CONTRACT NO T-12-16 Section 16122 WIRES AND CABLES Page 7 of 11 DATE: April 2012 .8 .9 .10 .11 .7 intervals not exceeding 300mm (12 inches). Each bundle contains 30 conductors maximum. Use Panduit, or equal wiring ducts and size to provide a minimum of 20 percent spare space not less than 5 per terminal block. Do not intermix signals within the same bundle or duct. Use twisted unshielded wire for other DC signals and segregate from wire conducting AC signals. Colour code wiring as follows: 1. Line and load circuits AC or DC power: Black 2. AC control circuits: Red 3. DC control circuits: Blue 4. Interlock control circuits on the panel: Yellow energized from external source 5. DC signal grounding conductors: Green/White Strip 6. Equipment grounding conductors: Green 7. Current carrying grounded conductor: White (neutral) 8. Intrinsically safe: Blue Use PVC crimped sleeve type wire tag identifications with legible machine printed markings and numbers. Adhesive or taped-on tags are not acceptable. Wiring Accessories .1 Wire markers: Plastic slip-on, black letters on white background. Shur-Code by Thomas & Betts Ltd., Z-Type by Wieland Electric Inc. .2 Cable markers: For cables or conductors greater than 13 mm diameter, strap-on type, semi rigid PVC carrier strip. Type K by Wieland Electric Inc. .3 Terminal blocks: 600 V, 25 A minimum rating, modular, 35 mm DIN rail mounted, provision for circuit number labelling, individually removable, sized to accommodate conductor size and circuit current. Sak Series by Weidmuller Ltd., UK Series by Phoenix Terminal Blocks Ltd., WK Series by Wieland Electric Inc., Entrelec. .4 Field wiring terminations: Where screw-type terminal blocks are provided, supply insulated fork tongue terminals. Sta-Kon by Thomas & Betts Ltd., Scotchlok by 3M Canada Inc. .5 Splice connectors for equipment pig-tail, lighting and receptacle circuits: For wire sizes #12 and #10 AWG inclusive, twist-on compression spring type. Wing-Nut by Ideal Industries Inc.., Marrette Type II by Marr Electric Ltd. .6 Moisture and waterproofing: In wet locations, with Liquid Tape by Ideal. .7 Equipment pig-tail power circuit connections: For wire sizes #8 AWG minimum, split-bolt type, sized to suit number and size of conductors. Servit Type KS by Burndy Inc. CONTRACT NO T-12-16 Section 16122 WIRES AND CABLES Page 8 of 11 DATE: April 2012 .8 .9 .10 .11 .12 .13 .14 High voltage (above 1000 V) cable terminations: Engineered termination kits, rated for conductor number, size and voltage class of cable, heat shrinkable type, stress relieving, with heat activated sealant. Supply outdoor skirts for outdoor terminations. Type HVT by Raychem Canada Ltd. 5kV motor terminations: heat shrinkable connection kits, including compression lug connectors, sealant, cover caps and tubes. Type MCK-5 by Raychem Canada Ltd. Low voltage (1000V and lower) motor terminations: heat shrinkable connection kit, including sleeves, caps and sealant. Type MCK by Raychem Canada Ltd. Cable ties: Nylon, one-piece, self-locking type, by Thomas & Betts Ltd., Burndy Inc., Wieland Electric Inc TECK cable connectors in hazardous locations: Approved for application. TECK cable connectors in wet or outdoor areas: Watertight type. Cable pulling lubricant: Compatible with cable covering and not to cause damage or corrosion to conduits or ducts. Yellow 77 by Ideal. Industries Inc PART 3. EXECUTION 3.1 3.2 Coordination .1 Report discrepancies promptly to the Consultant. .1 Provide wires of number and size (including corresponding raceways) required, with spare conductors as indicated. Provide adequate wiring for actual equipment installed. .2 Provide wire and cable according to the Contract Drawings and electrical system requirements. .3 Pull cable into ducts, conduits and cable trays in accordance with cable manufacturer's recommendations. Use patented cable grips suitable for cable type, or pulling eyes fastened directly onto cable conductors. .4 Limiting pulling tension and minimum bending radii to those recommended by manufacturer. .5 Prevent damage to cable jackets by utilizing adequate lubricant when pulling cables through ducts and conduits. .6 Support cables in manholes and utility tunnels on cable trays or cable racks. .7 Arrange cables in parallel rows on cable trays. Maintain cable spacing by fastening cables, with “P” clips, every 2000 mm minimum on straight horizontal runs and to each rung at bends, Installation CONTRACT NO T-12-16 Section 16122 WIRES AND CABLES Page 9 of 11 DATE: April 2012 including two rungs of adjoining straight sections. Fasten cables on vertical tray runs every 1000 mm maximum. 3.3 3.4 .8 Connect cables to electrical boxes and equipment enclosures located in wet or sprinkled areas with watertight cable connectors. .9 Provide cable grips for vertical and catenary cable suspension installations to reduce cable tension at connectors and at cable bends. .10 Install through wiring in junction and pull boxes having no connection within the box. Leave 150 mm minimum of slack inside box. .11 Facilitate making of joints and connections by leaving sufficient slack in each conductor at panelboards, outlet boxes and other devices. .12 Do not connect more than three lighting circuits for three phase panels and two lighting circuits for single phase panels to a common neutral. .13 Use #10 AWG minimum for home runs to lighting panels exceeding 25 m. .14 Install instrumentation signal and thermocouple extension wires in separate raceways from power and control wiring. .15 Provide mechanical protection for cables within 1500 mm of the floor in buildings and within 2000 mm above grade outdoors. .16 Identify each cable by attaching a cable marker at each end, in all intermediate manholes, junction boxes and pull boxes. .17 Provide cable grips on vertical and horizontal catenary cable suspensions. .1 Install direct buried cables in 75 mm layers sifted sand, free of rock, stone and other sharp objects, above and below. .2 Where indicated in the Contract Documents, protect direct buried cables with 50 mm thick concrete protection tiles. Extend protection 50 mm minimum on either side of cabling. .3 Install direct buried cable at depth of 600 mm minimum. Where rock is encountered and minimum depth cannot be attained, install cables in concrete encased ducts. .4 Install in suitably sized concrete encased duct where cables pass under roadway or area subject to vehicular traffic or heavy loads. .1 Insulate equipment pig-tail power circuit connections with wire sizes #8 AWG and larger, with heat shrink sleeving termination kits. Underground Installation Wiring Terminations CONTRACT NO T-12-16 Section 16122 WIRES AND CABLES Page 10 of 11 DATE: April 2012 1.1 3.5 .2 Terminate armoured cables with accepted connectors suitable for application, size and type of cable. .3 Except where pulling tensions exceed allowable cable limits or where tap connections are required, only install splices in power, control and instrumentation cable runs with written permission of Contract Administrator. Where unavoidable, install splices in junction boxes only. .4 Make power (1000 V and below), control and instrumentation wiring taps, splices and terminations in junction boxes with labelled terminal blocks, securely fastened to avoid loosening under vibration or normal strain. Terminate lighting circuits and 120 V convenience receptacle circuits with twist on or split-bolt type connectors and insulating tape. .5 Terminate control, signal and instrumentation circuit conductors, including spares, on terminal blocks. Label terminal blocks with unique alphanumeric designation or as indicated. .6 Identify each conductor, including spares, by wire markers at each termination. Indicate circuit designation or unique wire number. Identify spare conductors as 'SP1', 'SP2', etc. High Voltage Terminations (Above 1000 V) .1 Prepare high voltage cable ends. Assemble and install stress relieving cable terminations where necessary and in accordance with termination and cable manufacturers' recommendations. Utilize only personnel trained, experienced and qualified in this type of installation. .2 For motor terminations, provide compression lugs with bolt type connections on the motor leads and incoming conductors. Install cable stress relief termination kits and motor terminations kits in accordance with manufacturer’s recommendations. Prevent conductors and splices from coming into contact with enclosure walls. .1 Refer to Section 16031 – Inspection and Testing for additional inspections and tests required under this Contract. Follow all applicable NETA standards and procedures. .2 High Voltage Cable (Above 1000 Volts) .1 Install cable without making final connections so equipment (motors, switchgear, transformers, capacitors, and similar items) will not be subjected to test voltages. .2 Test complete with cable termination fittings. .3 A competent independent testing agency specializing in this work to test cable and terminations, including High Inspection and Testing CONTRACT NO T-12-16 Section 16122 WIRES AND CABLES DATE: April 2012 Page 11 of 11 .4 .5 1.2 Potential tests, in accordance with the ICEA #S-66-524 and CSA standards. Connect cable upon successful conclusion of tests. Submit two copies of certified test results to the Consultant. Replace defective or substandard cable runs. .3 Cable and Wire - 1000 Volt and Below .1 Conduct insulation resistance measurements using a "Megger" (500 V instrument for circuit up to 350 V systems, 1000 V instrument for 351-600 V systems). .2 Record test results in a log book and submit to the Consultant for reference. Replace or repair circuits which do not meet Inspection Authority requirements. With equipment disconnected, measure insulation resistance of the following circuits: 1. Power, lighting, heater and motor feeders: Phaseto-phase, phase-to-ground. 2. Control circuits: To ground only. .3 Do not perform "Megger" tests on equipment containing solid-state components. .4 Disconnect power factor correction capacitors from system prior to testing. .4 Instrumentation and Thermocouple Extension Wiring .1 Check the continuity of each conductor using ohmmeter or DC buzzer. Megger or 120 volt filament lamp testing is not acceptable. .2 Test thermocouple wiring for continuity and polarity in accordance with manufacturer's recommendations. .1 Identify wiring including fibre optic cabling, with wire markers. .2 Colour code power, feeder and branch conductors at both ends with coloured plastic tapes. Tapes are not required where conductors are identified by jacket colour. Maintain phase and colour sequence throughout. .3 Identify each conductor, including spares, with a unique alphanumeric designation to facilitate troubleshooting and maintenance. .4 Identify PLC wiring at terminal blocks and connection points with PLC terminal (I/O) address numbers. Wiring Identification END OF SECTION CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 1 of 22 DATE: April 2012 PART 1. 1.1 1.2 1.3 GENERAL References .1 Comply with the latest edition of the following statutes, codes and standards and all amendments thereto: .1 Canadian Standards Association: 1. CSA C22.2 No. 45 Rigid Metal Conduit. 2. CSA C22.2 No. 56 Flexible Metal Conduit and Liquid-Tight Flexible Metal Conduit. 3. CSA C22.2 No. 211.2 Rigid PVC (Unplasticized) Conduit. 4. CAN/CSA C22.2 No. 126 Cable Tray Systems. .2 National Electrical Manufacturers Association (NEMA): 1. RN 1, Polyvinyl-Chloride (PVC) Externally Coated Galvanized Rigid Steel Conduit and Intermediate Metal Conduit. 2. TC 2, Electrical Polyvinyl Chloride Plastic Tubing (PVC) and Conduit. 3. TC 3, PVC Fittings for Use with Rigid PVC Conduit and Tubing. 4. VE 1, Metallic Cable Tray Systems. 5. VE 2, Cable Tray Installation Guidelines. .3 Electronic Industry Association (EIA) and Telecommunications Industry Association (TIA): 569-A, Commercial Building Standard for Telecommunications Pathways and Spaces. .1 The Work outlined in this Section shall include the lump sum price for Section 16130 – Raceways as indicated in Schedule ‘A’ of the Bid Form. .1 Action Submittals: .1 Shop Drawings: 1. Manufacturer’s Literature: .1 Rigid galvanized steel conduit. .2 Rigid aluminum conduit. .3 PVC Schedule 40 conduit. .4 PVC Schedule 80 conduit. .5 PVC-coated rigid galvanized steel conduit. .6 Flexible, nonmetallic, liquid-tight conduit. .7 Conduit fittings. 2. Cable Tray Systems: .1 Submit shop drawings sealed and signed by a professional engineer licensed in the Measurement and Payment Submittals CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 2 of 22 DATE: April 2012 3. 4. 5. 1.4 Province of Ontario and retained by the Contractor certifying that cable trays supports and anchorage are designed in accordance with the requirements of postdisaster facility in accordance with the Ontario Building Code Division B, Part 4, Article 4.1.8.17 for post-disaster structures. .2 After installation a professional engineer licensed in the Province of Ontario and retained by the Contractor shall complete a Site review and then submit a letter, sealed and signed, stating that the cable trays supports and anchorage are designed and installed in accordance with the requirements of post-disaster facility in accordance with the Ontario Building Code Division B, Part 4, Article 4.1.8.17 for postdisaster structures. .3 Dimensional drawings and descriptive information. .4 CSA Load Class Designation. .5 Support span length and kilograms-permetre actual and future cable loading at locations, with safety factor used. .6 Layout drawings and list of accessories being provided. Conduit Layout: .1 Plan and section type, showing arrangement and location of conduit and duct bank required for: .2 Low and medium voltage feeder and branch circuits. .3 Instrumentation and control systems. .4 Communications systems. .5 Empty conduit for future use. .6 Scale not greater than 1:200. Equipment and machinery proposed for bending metal conduit. Method for bending PVC conduit less than 30 degrees. .2 Information Submittals: Submit copy of manufacturers’ certification of training for PVC-coated rigid steel conduit installer. .1 PVC-Coated, Rigid Steel Conduit Installer: Must be certified by the conduit manufacturer as having received a minimum of 2 hours of training on correct installation procedures. Qualifications CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 3 of 22 DATE: April 2012 PART 2. PRODUCTS 2.1 Cable Duct System .1 Scope .1 This Specification applies to the design and supply of the cable bus feeder system designed for power distribution and used to transmit large amounts of power, in indoor and outdoor locations, both above and below ground levels. The system design is used to provide a lower installed cost alternative to conventional power distribution systems by facilitating installation and replacement of circuit conductors, and by readily accommodating any future increased load current requirements. .2 General Information .1 This Specification defines the technical requirements related to the design and supply of the cable bus feeder system, which shall consist of a ventilated enclosure system, incorporating unarmoured cable, specifically engineered to transmit large amounts of power as well as concrete encasement for underground installations. The cable bus feeder system shall include all power cable, a bare copper ground wire, and all necessary components required to connect, from terminal to terminal, two electrical equipment units, and shall be comprised of the following components: 1. Cables and cable bus enclosure including cable supports and cable clamping; 2. Bare copper ground wire clamped to an inside wall of the enclosure; 3. Connections, including terminal lugs and adaptor plates suitable for the specific electrical equipment being connected at the supply end; 4. Transition box and flange connections, as required; 5. Top hat and flange connections, as required; 6. Fire penetration seals, as required; and 7. Any other accessories required to complete the installation, 8. Any support structure for the cable bus feeder system; and 9. Connections for the load end, including terminal lugs and adaptor plates suitable for the specific electrical equipment to be connected. .3 Code and Standards .1 The components and complete assembly of the Maxiamp Cable Bus Feeder System and its installation shall meet the requirements of the following Standards, as applicable: .2 Ontario Electrical Safety Code (OESC) CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 4 of 22 DATE: April 2012 .3 .4 .5 .6 .7 .4 Canadian Standards Association – CSA C22.2 #38 – Thermoset Insulated Wires and Cables Canadian Standards Association – CSA C68.3 – Shielded and Concentric Neutral Power Cables Rated 5 – 46 kV IEEE Standard #404 – Standard for Extruded and Laminated Dielectric Shielded Cable Joints Rated 2500 to 500,000 Volts. IEEE Standard #48 – Test Procedure for HV AC Cable Terminations 2.5-765 kV Canadian Standards Association – C22.2 #126.1 – Metal Cable Tray Systems. Products Ventilated Cable Bus Enclosure .1 .2 Enclosure material 1. The cable bus feeder enclosure shall be constructed of high strength, high conductivity, 6063-T6 corrosion resistant aluminium alloy meeting the requirements of CSA C22.2 #126.1, unless otherwise specified in the Contract Documents. .3 Enclosure Ventilation 1. The enclosure shall be completely enclosed on both sides, and provided with ventilated top and bottom covers designed to prohibit possible penetration of any size sharp object applied perpendicular to the enclosure surfaces. 2. Ventilation openings shall be louvered, with each opening being no greater than 5 mm wide by 50 mm long. 3. The number of ventilation openings provided shall allow sufficient air circulation to ensure free air rating of the enclosed cables. .4 Enclosure Top Cover Shapes 1. For outdoor horizontal straight sections, enclosures shall have removable ventilated top covers with sloped peaked tops, For indoor horizontal straight sections, enclosures 2. shall have removable ventilated flat top covers. 3. All other sections shall have removable ventilated flanged flat top covers. .5 Cable Bus Supports Within Enclosure 1. Cables shall be supported within the enclosure and on each level by metal supports which shall be at least 45 mm (1.77”) in width. 2. The metal supports shall be repeated throughout the cable bus enclosure at regular intervals not exceeding 305 mm (12”). CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 5 of 22 DATE: April 2012 3. .6 .5 Metal supports on each successive vertical cable level shall be longitudinally offset by ½ of the support spacing, relative to the supports in the level immediately below. Cable Bus Clamping Within Enclosure 1. Cable clamps shall be clamped to the metal supports at intervals not exceeding 915 mm (36”) 2. Cables shall be secured to a cable support by use of a one-piece non-ferrous metal clamp, of width equal to the underlying cable support. 3. Each clamp shall be formed to provide a sufficient number of cable ports to secure the designated number of feeder cables. 4. Each cable port shall be formed specifically to accommodate the diameter contour of the designated feeder cable. 5. Curvatures for cable ports shall be positioned to provide uniform lateral cable spacing while ensuring full free air current rating. 6. Positioning of cable clamping ports on successive levels of cable supports shall ensure achievement of both the highest degree of electrical field balance, and the lowest degree of system losses. Power Cables .1 Each individual power cable shall be of a single, continuous length between terminals, and shall meet the requirements of the appropriate Standard listed in subsection 2.3, consistent with the system design voltage. .2 Conductors 1. Conductors shall be annealed uncoated Class B stranded copper, sized to meet the current load requirements. Insulation .3 1. Insulation shall be Thermosetting Ethylene Propylene Rubber Class III (EPR) unless otherwise stated in the Contract Documents. Shielding .4 1. Strand and insulation shields shall be required on all cables rated 1000 volts or greater. 2. Nonmetallic semiconducting shields shall be thermosetting material, compatible with the insulation material. 3. Metallic shielding, when specified in the Contract Documents, shall consist of overlapped copper tape which is annealed and uncoated. .5 Jackets CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 6 of 22 DATE: April 2012 1. All cables rated 600 volts and greater shall include an insulation outer jacket in accordance with the applicable standards in subsection 2.3. .6 Grounding .1 The enclosure system shall be certified as a continuous ground conductor, with provision for a ground clamp at each end of each enclosure section. .2 A grounding conductor shall be connected at a single point to the inside wall of the enclosure system’s top level within each longitudinal section of enclosure. .3 A system grounding conductor of bare uncoated copper and no smaller than #4/0 AWG in size shall be supplied, and shall be connected to each enclosure section, and shall be connected to the grounding terminals at the supply and load ends of the system. .4 The enclosure connector shall be cable tray ground clamp of zinc plated copper alloy, suitable for securing two parallel conductors of minimum size #4/0 AWG to the enclosure wall, and shall be corrosion resistant. .7 Penetration Fire Seals .1 Where a fire separation is pierced by the enclosure system, all openings around the enclosure and around each individual cable within the enclosure shall be properly closed or sealed with an elastomeric three-hour rated sealing system, in compliance with the National Building Code of Canada. .8 Terminal Boxes – Transformer/Distribution Centre .1 Terminal boxes shall be provided at one or both systems ends, subject to the space available for cable terminations. .2 The terminal boxes shall be dimensioned to accommodate training and terminating of the number and size of the cables entering the box, while ensuring sufficient clearances to grounded metal. .3 The terminal boxes shall be of steel of minimum thickness of 11 gauge, primed and painted inside and outside. The outside paint colour shall match that of the transformer of distribution centre. .4 Terminal boxes shall include access panels on two sides, and shall contain ventilation openings on two sides; all ventilation openings shall be screened to protect against entry of rodents and animals. .5 Support arms shall be provided for the terminal boxes when deemed necessary to carry the weight. .6 Cable feeder bus entry into an outdoor terminal box shall be made watertight by thorough and effective sealing. .7 Outdoor terminal boxes shall contain a screened drain hole at the bottom of the unit. CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 7 of 22 DATE: April 2012 2.2 .9 Terminal Transition Plates and Lugs .1 Terminal plates when furnished, shall contain a sufficient mass of copper to transfer the current load without overheating. .2 Terminal transition plates when furnished, shall contain a sufficient number of holes of diameter and spacing to accommodate the holes of both the apparatus terminal, and the conductor termination lugs. .3 All conductor termination lugs shall be of the long barrel crimp type, the pads of which shall contain a minimum of two holes of diameter and spacing to match those of the transition plates. .10 Installation Procedure .1 All installations of a Maxiamp Cable Bus Feeder System shall be in complete accordance with the manufacturer’s written installation procedure. .1 Rigid Galvanized Steel Conduit (RGS): .1 Meet requirements of CSA C22.2 No. 45. .2 Material: Hot-dip galvanized, inside and outside, with chromated protective layer. .2 Rigid Aluminum Conduit: .1 Meet requirements of CSA C22.2 No. 45. .2 Material: Type 6063, copper-free aluminum alloy. .3 PVC Schedule 40 Conduit: .1 Meet requirements of CSA C22.2 No. 211.2 and NEMA TC 2. .2 Suitable for areas NOT exposed to physical damage, underground direct burial, concealed or direct sunlight exposure, and 90 degrees Celsius (C) insulated conductors. .4 PVC-Coated Rigid Galvanized Steel Conduit: .1 Meet requirements of NEMA RN 1. .2 Material: 1. Meet requirements of CSA C22.2 No. 45. 2. Exterior finish: PVC coating, 40 mils nominal thickness, bond to metal shall have tensile strength greater than PVC. 3. Interior finish: Urethane coating, 2 mils nominal thickness. .3 Threads: Hot-dipped galvanized and factory coated with urethane. Bendable without damage to either interior or exterior .4 coating. .5 Acceptable Manufacturer: “Plasti-Bond Red” by Robroy Industries. Conduit and Tubing CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 8 of 22 DATE: April 2012 2.3 .5 Flexible, Nonmetallic, Liquid-Tight Conduit: .1 Material: PVC core with fused flexible PVC jacket. .2 Suitable for: 1. Dry Conditions: 80 degrees Celsius insulated conductors. 2. Wet Conditions: 60 degrees Celsius insulated conductors. .3 Approved Manufacturers and Products: 1. Carlon Products by Gross Automation; Carflex or X-Flex. 2. Thomas & Betts Corporation, Xtraflex LTC 3. EFC International. .6 Fire Alarm - Electrical Metallic Tubing (EMT): .1 Meet requirements of CSA C22.2 No. 83. .2 Material: Hot galvanized, with RED factory coating. .3 Approved Manufacturers and Products: Columbia-MBF, Atkore International, Inc. - Fire Alarm Red EMT or approved equivalent. .1 Rigid Galvanized Steel: .1 General: 1. Meet requirements of CSA C22.2 No. 45. 2. Type: Threaded, galvanized. Set screw and threadless compression fittings are not permitted. Bushing: .2 1. Material: Malleable iron with integral insulated throat, rated for 150 degrees Celsius. 2. Approved Manufacturers and Products: .1 Appleton, Emerson Electric Co. - Series BU-I. .2 O-Z/Gedney; Emerson Electric Co; Type HB. .3 Grounding Bushing: 1. Material: Malleable iron with integral insulated throat rated for 150 degrees Celsius, with solderless lugs. 2. Approved Manufacturers and Products: .1 Appleton, Emerson Electric Co. Series GIB. .2 O-Z/Gedney, Emerson Electric Co; Type HBLG. .4 Conduit Hub: 1. Material: Malleable iron with insulated throat with bonding screw. 2. CSA or ULc listed for use in wet locations. 3. Approved Manufacturers and Products: Fittings CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 9 of 22 DATE: April 2012 .1 .5 .6 .7 .8 .9 .10 .11 Appleton, Emerson Electric Co. - Series HUB-B. .2 O-Z/Gedney, Emerson Electric Co - Series CH. Conduit Bodies: 1. Sized as required by CEC. 2. Approved Manufacturers and Products (For Normal Conditions): .1 Appleton, Emerson Electric Co - Form 35 threaded unilets. Cooper Crouse-Hinds; Form 7 or 8 .2 threaded condulets. .3 Killark, Hubbell Incorporated - Series O electrolets. .4 Thomas & Betts Corporation - Form 7 or 8. 3. Approved Manufacturers (For Hazardous Locations): .1 Appleton, Emerson Electric Co.. .2 Cooper Crouse-Hinds. .3 Killark, Hubbell Incorporated . Couplings: As supplied by conduit manufacturer. Unions: 1. Concrete tight, hot-dip galvanized, malleable iron. 2. Approved Manufacturers and Products: .1 Appleton, Emerson Electric Co. Series SCC Bolt-On Coupling or Series EC Three-Piece Union. .2 O.Z./Gedney, Emerson Electric Co. Type SSP split coupling or Type 4 Series, three-piece coupling. Approved Conduit Sealing Fitting Manufacturers and Products (For hazardous locations): 1. Appleton, Emerson Electric Co. - Type EYF, EYM, or ESU. 2. Cooper Crouse-Hinds; Type EYS or EZS. 3. Killark;, Hubbell Incorporated Type EY or EYS. Approved Drain Seal Manufacturers and Products: 1. Appleton, Emerson Electric Co. - Type SF. 2. Cooper Crouse-Hinds - Type EYD or EZD. Approved Drain/Breather Fitting Manufacturers and Products: 1. Appleton, Emerson Electric Co.; Type ECDB. 2. Crouse-Hinds; ECD. Approved Expansion Fitting Manufacturers and Products: 1. Deflection/Expansion Movement: .1 Appleton, Emerson Electric Co.; Type DF. .2 Cooper Crouse-Hinds; Type XD. 2. Expansion Movement Only: .1 Appleton, Emerson Electric Co.; Type XJ. CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 10 of 22 DATE: April 2012 .12 .2 .2 Cooper Crouse-Hinds; Type XJ. Cable Sealing Fittings: 1. To form watertight nonslip cord or cable connection to conduit. 2. For Conductors With OD of 13 mm or Less: Neoprene bushing at connector entry. 3. Approved Manufacturers and Products: .1 Appleton, Emerson Electric Co.; CG-S. .2 Cooper Crouse-Hinds; CGBS. Rigid Aluminum Conduit: .1 General: 1. Meet the requirements of CSA C22.2 No. 45. 2. Type: Threaded, copper-free. Set screw fittings are not permitted. .2 Insulated Bushing: 1. Material: Cast aluminum, with integral insulated throat, rated for 150 degrees Celsius. 2. Approved Manufacturer and Product: O-Z/Gedney, Emerson Electric Co.; Type AB. .3 Grounding Bushing: 1. Material: Cast aluminum with integral insulated throat, rated for 150 degrees, with solderless lugs. 2. Approved Manufacturer and Product: O-Z/Gedney, Emerson Electric Co.; Type ABLG. .4 Conduit Hub: 1. Material: Cast aluminum, with insulated throat. 2. UL listed for use in wet locations. 3. Approved Manufacturers and Products: .1 O-Z/Gedney, Emerson Electric Co.; Type CHA. .2 Thomas & Betts Corporation; Series 370AL. .5 Conduit Bodies: 1. Approved Manufacturers and Products (For Normal Conditions): .1 Appleton, Emerson Electric Co.; Form 85 threaded unilets. .2 Cooper Crouse-Hinds (Crouse-Hinds); Mark 9 or Form 7-SA threaded condulets. Killark; Series O electrolets. .3 2. Approved Manufacturers (For Hazardous Locations): .1 Appleton Electric Company. .2 Cooper Crouse-Hinds (Crouse-Hinds). .3 Hubbell Incorporated - Killark. .6 Couplings: As supplied by the conduit manufacturer. .7 Approved Conduit Sealing Fitting Manufacturers and Products: CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 11 of 22 DATE: April 2012 1. .8 .9 .10 .11 Appleton, Emerson Electric Co. - Type EYF-AL or EYM-AL. 2. Cooper Crouse-Hinds (Crouse-Hinds); Type EYS-SA or EZS-SA. 3. Killark, Hubbell Incorporated- Type EY or EYS. Approved Drain Seal Manufacturers and Products: 1. Appleton - Type EYDM-A. 2. Cooper Crouse-Hinds (Crouse-Hinds); Type EYD-SA or EZD-SA. Approved Drain/Breather Fitting Manufacturers and Products: 1. Appleton, Emerson Electric Co. - Type ECDB. 2. Cooper Crouse-Hinds (Crouse-Hinds); ECD. Approved Expansion Fitting Manufacturers and Products: 1. Deflection/Expansion Movement: Thomas & Betts Corporation - Steel City; Type DF-A. 2. Expansion Movement Only: Thomas & Betts Corporation - Steel City; Type AF-A. Cable Sealing Fittings: To form watertight nonslip cord or cable connection to conduit. Bushing: Neoprene at connector entry. 1. 2. Approved Manufacturer: Appleton; CG-S. .3 PVC Conduit and Tubing: .1 Meet the requirements of NEMA TC-3. .2 Type: PVC, slip-on. .4 PVC-Coated Rigid Galvanized Steel Conduit: .1 Meet the requirements of NEMA RN 1. .2 Fittings: Rigid galvanized steel type, PVC coated by the conduit manufacturer. .3 Conduit Bodies: Cast metal hot-dipped galvanized or urethane finish. Cover shall be of same material as conduit body. PVC coated by the conduit manufacturer. .4 Finish: 40-mil PVC exterior, 2-mil urethane interior. .5 Overlapping pressure sealing sleeves. .6 Conduit Hangers, Attachments, and Accessories: PVC-coated. .7 Manufacturers: 1. Plastibond Red by Robroy Industries Ltd. or approved equivalent .8 Expansion Fitting Manufacturer: Robroy Industries Ltd. .5 Flexible, Nonmetallic, Liquid-Tight Conduit: .1 Type: High strength plastic body, complete with lock nut, O-ring, threaded ferrule, sealing ring, and compression nut. .2 Body/compression nut (gland) design to assure high mechanical pullout strength and watertight seal. .3 Manufacturers and Products: 1. Carlon Products by Gross Automation; Type LT. 2. O-Z/Gedney, Emerson Electric Co.-; Type 4Q-P. CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 12 of 22 DATE: April 2012 3. 2.4 Thomas & Betts Corporation - Series 6300. .6 Watertight Entrance Seal Device: .1 New Construction: 1. Material: Oversized sleeve, malleable iron body with sealing ring, pressure ring, grommet seal, and pressure clamp. 2. Manufacturer and Product: O-Z/Gedney, Emerson Electric Co. - Type FSK or WSK, as required. Cored-Hole Application: .2 1. Material: Assembled dual pressure disks, neoprene sealing ring, and membrane clamp. 2. Manufacturer and Product: O-Z/Gedney; Emerson Electric Co. - Series CSM. .1 Meet requirements of CSA C22.2 No. 126.1 .2 Type: Ladder, of welded construction. Ladder rung spacing: 300 mm. .3 Material: Copper-free aluminum alloy 6063-T6 finish. .4 Dimensions: As indicated on the Contract Drawings. Fittings are to have a minimum bending radius of 600 mm. .5 Cover: Louvered, minimum 20-gauge steel. .6 Barrier Strip: Vertical, solid type, with horizontal fittings and strip clamps. .7 Fittings of same cross-sectional tray area, and hardware of same material as cable tray. .8 Tray Grounding: Conform to Ontario Electrical Safety Code and CSA C22.2 No. 126.1 .9 Provide next higher CSA C22.2 No. 126.1 class designation than required for support of designed span length. .10 Design Loads: Use working load adequate for actual cable installed plus 20 percent additional weight allowance for future cables, with safety factor of 2 in accordance with NEMA VE 1, Table 3-1. .11 Expansion Joints: NEMA VE 1 for 14 degrees Celsius maximum temperature variation. .12 Furnish Cable Tray with no sharp edges, burrs, or weld projections. .13 The Contractor shall design and provide cable trays supports and anchorage to meet the requirements of the manufacturer’s recommendations and the Ontario Building Code Division B, part 4, Article 4.1.8.17 for post-disaster structures. .14 Approved Manufacturers: .1 Pilgrim Technical Products Ltd. Cable Trays CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 13 of 22 DATE: April 2012 .2 .3 .4 .5 2.5 2.6 B-Line Systems, Inc. Canstrut Inc. Thomas and Betts Corporation - Electrotray. Pursley Inc. Multi cable transits (MCT) -Firestop .1 Provide Multi Cable Transits to seal cables at locations as shown on the Contract Drawings. .2 Provide type RGB-4 x 4 as used for buildings c/w all stay plates, modular blocks and MCT lubricant as supplied by Speedline Technologies - Electrovert. .1 Identification Devices: .1 Raceway Tags: 1. Material: Permanent, nylon or polyethylene. 2. Shape: Round. 3. Raceway Designation: Pressure stamped, embossed, or engraved. 4. Tags relying on adhesives or taped-on markers not permitted. .2 Wraparound Duct Band: .1 Material: Heat-shrinkable, cross-linked polyolefin, precoated with hot-melt adhesive. .2 50 mm width (minimum). .3 Manufacturer and Product: Tyco Electronics Corporation Raychem; Type TWDB. .1 Conduit and Tubing sizes shown on the Contract Drawings are based on the use of copper conductors. .2 Diameter: Minimum 21 mm. .3 Crushed or deformed raceways not permitted. .4 Maintain raceway entirely free of obstructions and moisture. .5 Immediately after installation, plug or cap raceway ends with watertight and dust-tight seals until time for pulling in conductors. .6 Aluminum Conduit: Do not install in direct contact with concrete. Install in PVC sleeve or cored hole through concrete walls and slabs. .7 Sealing Fittings: Provide drain seal in vertical raceways where condensate may collect above sealing fitting. Accessories PART 3. EXECUTION 3.1 General CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 14 of 22 DATE: April 2012 3.2 .8 Avoid moisture traps where possible. When unavoidable in exposed conduit runs, provide junction box and drain fitting at conduit low point. .9 Group raceways installed in same area. .10 Proximity to Heated Piping: Install raceways minimum 300 mm from parallel runs. .11 Follow structural surface contours when installing exposed raceways. Avoid obstruction of passageways. .12 Run exposed raceways parallel or perpendicular to walls, structural members, or intersections of vertical planes. .13 Block Walls: Do not install raceways in same horizontal course with reinforcing steel. .14 Install watertight fittings in outdoor, underground, or wet locations. .15 Paint threads and cut ends, before assembly of fittings, galvanized conduit or PVC coated galvanized conduit, installed in exposed or damp locations with zinc-rich paint or liquid galvanizing compound. .16 Remove burrs, ream and clean metal conduit, and clean before installation of conductors, wires, or cables. .17 Do not install raceways in concrete equipment pads, foundations, or beams. .18 Horizontal raceways installed under floor slabs shall lie completely under slab, with no part embedded within slab. .19 Install conduits for fiber optic cables, telephone cables, and Category 5 data cables in strict conformance with the requirements of EIA/TIA 596-A. .20 Unless otherwise indicated in the Contract Documents, install conduits surface-mounted on walls and ceilings. Conceal or embed conduits only where indicated in the Contract Documents. .21 Install concealed, embedded, and buried raceways so that they emerge at right angles to surface and have no curved portion exposed. Installation in Cast-In-Place Structural Concrete (Embedment) .1 Minimum cover 50 mm, including all fittings. .2 Conduit placement shall not require changes in reinforcing steel location or configuration. .3 Provide nonmetallic support during placement of concrete to ensure raceways remain in position. .4 Conduit larger than 27 mm shall not be embedded in concrete slabs, walls, foundations, columns or beams, unless approved by the Consultant. .5 Slabs and Walls: CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 15 of 22 DATE: April 2012 .1 .2 .3 .4 .5 .6 .7 3.3 Trade size of conduit not to exceed one-fourth of the slab or wall thickness at the thinnest point. Install within middle two-fourths of slab or wall. Separate conduit less than 53 mm trade size by a minimum of ten times the conduit trade size, center-to-center, unless otherwise shown on the Contract Drawings. Separate conduit 53 mm and greater trade size by a minimum of eight times the conduit trade size, center-to-center, unless otherwise shown on the Contract Drawings. Cross conduit at an angle greater than 45 degrees, with minimum separation of 25 mm. Separate conduit by a minimum six times the outside dimension of expansion/deflection fittings at expansion joints. Conduit shall not be installed below the maximum water surface elevation in walls of water holding structures. .6 Columns and Beams: .1 Trade size of conduit not to exceed one-fourth of beam thickness. .2 Conduit cross-sectional area not to exceed 4 percent of beam or column cross section. .1 Install conduits in order to conserve headroom in exposed locations and to minimize interference in spaces through which they pass. .2 Conceal conduits in office, washrooms and stairwells. .3 Surface mount conduits unless noted otherwise in the Contract Documents. .4 Use electrical metallic tubing (EMT) for wiring of life safe system and concealed wiring. .5 Use rigid PVC conduit in corrosive areas. .6 Use liquid tight flexible metal conduit for connection to motors or vibrating equipment. .7 Use explosion proof flexible connection for connection to explosion proof motors. .8 Install conduit sealing fittings in hazardous areas. Fill with compound. .9 Minimum conduit size for lighting and power circuits: 19 mm. .10 Bend conduit cold. Replace conduit if kinked or flattened more than 1/10th of its original diameter. .11 Mechanically bend steel conduit over 19 mm in diameter. Conduit Application CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 16 of 22 DATE: April 2012 3.4 .12 Field threads on rigid conduit must be of sufficient length to draw conduits up tight. .13 Install fish cord in empty conduits. Polypropylene 6 mm in all empty conduits .14 Run 2-27 mm spare conduits up to ceiling space and two 25 mm spare conduits down to ceiling space from each flush panel. Terminate these conduits in 152 mm x 152 mmx 102 mm junction boxes in ceiling space or in case of an exposed concrete slab, terminate each conduit in surface type box. .15 Remove and replace blocked conduit sections. Do not use liquids to clean out conduits. .16 Dry conduits out before installing wire. .17 Diameter: Minimum 21 mm. .18 Exterior, Exposed: 1. Rigid PVC where allowed by the Ontario Building Code 2. Rigid Galvanized Steel. .19 Interior, Exposed: 1. Rigid aluminum .20 Interior, Concealed (Not Embedded in Concrete): 1. Rigid PVC. .21 Aboveground, Embedded in Concrete Walls, Ceilings, or Floors: 1. Rigid PVC. .22 Under Slabs-On-Grade: 1. Rigid PVC. .23 Corrosive Areas: 1. Rigid PVC. .1 For motors, wall or ceiling mounted fans and unit heaters, dry type transformers, electrically operated valves, instrumentation, and other equipment where flexible connection is required to minimize vibration: .1 Conduit Size 103 mm or Less: Flexible, liquid-tight conduit. .2 Conduit Size Greater Than 103 mm: Nonflexible. .3 Wet or Corrosive Areas: Flexible, nonmetallic, liquid-tight. .4 Dry Areas: Flexible, metallic liquid-tight. .5 Length: 450 mm minimum, 1500 mm maximum, sufficient to allow for movement or adjustment of equipment. .2 Outdoor Areas, Process Areas Exposed to Moisture, and Areas Required shall be Oiltight and Dust-Tight: Flexible non-metallic, liquid-tight conduit. .3 Under Equipment Mounting Pads: Rigid galvanized steel, PVCcoated rigid steel, PVC Schedule 80 conduit. Connections CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 17 of 22 DATE: April 2012 3.5 .4 Exterior Light Pole Foundations: Rigid galvanized steel conduit. .1 Make at right angles, unless otherwise shown on the Contract Drawings. .2 Notching or penetration of structural members, including footings and beams is not permitted. .3 Fire-Rated Walls, Floors, or Ceilings: Firestop openings around penetrations to maintain fire-resistance rating as specified in Section 07840 - Firestopping. .4 Apply single layer of wraparound duct band to all metallic conduit protruding through concrete floor slabs to a point 50 mm above and 50 mm below concrete surface. .5 Concrete Walls, Floors, or Ceilings (Aboveground): Provide nonshrink grout dry-pack, or use watertight seal device. .6 Entering Structures: .1 General: Seal raceway at the first box or outlet with oakum or expandable plastic compound to prevent the entrance of gases or liquids from one area to another. .2 Concrete Roof or Membrane Waterproofed Wall or Floor: 1. Provide a watertight seal. 2. Without Concrete Encasement: Install watertight entrance seal device on each side. With Concrete Encasement: Install watertight 3. entrance seal device on the accessible side. 4. Securely anchor malleable iron body of watertight entrance seal device into construction with one or more integral flanges. 5. Secure membrane waterproofing to watertight entrance seal device in a permanent, watertight manner. Heating, Ventilating, and Air Conditioning Equipment: .3 1. Penetrate equipment in area established by manufacturer. 2. Terminate conduit with flexible nonmetallic conduit at junction box or condulet attached to exterior surface of equipment prior to penetrating equipment. 3. Seal penetration with Type 5 sealant, as specified in Section 07900 - Sealants. .4 Corrosive-Sensitive Areas: Seal all conduit passing through chlorine room 1. walls. 2. Seal conduit entering equipment panel boards and field panels containing electronic equipment. 3. Seal penetration with Type 5 sealant, as specified in Section 07900 - Sealants. Penetrations CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 18 of 22 DATE: April 2012 .5 .6 .7 .8 3.6 Existing or Precast Wall (Underground): Core drill wall and install a watertight entrance seal device. Nonwaterproofed Wall or Floor (Underground, without Concrete Encasement): 1. Provide Schedule 40 galvanized pipe sleeve, or watertight entrance seal device. 2. Fill space between raceway and sleeve with expandable plastic compound or oakum and lead joint, on each side. Manholes and Handholes: Metallic Raceways: Provide insulated grounding 1. bushings. 2. Nonmetallic Raceways: Provide bell ends flush with wall. 3. Install such that raceways enter as near as possible to one end of wall, unless otherwise shown on the Contract Drawings. Hazardous Areas Raceway penetrations shall meet the seal requirements of OESC Section 18. Support .1 Provide support from structural members only, at intervals not exceeding Canadian Electrical Code requirements, and in any case not exceeding 3.0 m. Do not support from piping, pipe supports, or other raceways. .2 Multiple Adjacent Raceways: Provide ceiling trapeze. For trapeze-supported conduit, allow 25 percent extra space for future conduit. .3 Application/Type of Conduit Strap: .1 Aluminum Conduit: Aluminum or stainless steel. .2 Rigid Steel or EMT Conduit: Zinc coated steel, pregalvanized steel or malleable iron. PVC Coated Rigid Steel Conduit: PVC coated metal. .3 .4 Nonmetallic Conduit: Nonmetallic or PVC coated metal. .4 Provide and attach wall brackets, strap hangers, or ceiling trapeze as follows: .1 Wood: Wood screws. .2 Hollow Masonry Units: Toggle bolts. .3 Concrete or Brick: Expansion shields, or threaded studs driven in by powder charge, with lock washers and nuts. .4 Steelwork: Machine screws. .5 Location/Type of Hardware: 1. Dry, Noncorrosive Areas: Galvanized. 2. Wet, Noncorrosive Areas: Stainless steel. 3. Corrosive Areas: Stainless steel. .5 Nails or wooden plugs inserted in concrete or masonry for attaching raceway are not permitted. Do not weld raceways or CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 19 of 22 DATE: April 2012 pipe straps to steel structures. Do not use wire in lieu of straps or hangers. 3.7 3.8 3.9 .6 Support aluminum conduit on concrete surfaces with stainless steel or nonmetallic spacers, or aluminum or nonmetallic framing channel. .1 Install concealed raceways with a minimum of bends in the shortest practical distance. .2 Make bends and offsets of longest practical radius. Bends in conduits and ducts being installed for fiber optic cables shall be not less than 20 times the cable diameter, 375 mm, minimum. .3 Install with symmetrical bends or cast metal fittings. .4 Avoid field-made bends and offsets, but where necessary, make filed made bends and offsets with acceptable hickey or bending machine. Do not heat metal raceways to facilitate bending. .5 Make bends in parallel or banked runs from same center or centerline with same radius so that bends are parallel. .6 Factory elbows may be installed in parallel or banked raceways if there is change in plane of run, and raceways are same size. .7 PVC Conduit: .1 Bends 30-Degree and Larger: Provide factory-made elbows. .2 Use the manufacturer’s recommended method for forming smaller bends. .8 Flexible Conduit: Do not make bends that exceed allowable conductor bending radius of cable to be installed or that significantly restricts conduit flexibility. .1 Provide on all raceways at all structural expansion joints, and in long tangential runs. .2 Provide expansion/deflection joints for 14 degrees Celsius maximum temperature variation. .3 Install in accordance with the manufacturer’s instructions. .1 Solvent Welding: .1 Provide manufacturer recommended solvent; apply to all joints. .2 Install such that joint is watertight. .2 Adapters: .1 PVC to Metallic Fittings: PVC terminal type. .2 PVC to Rigid Metal Conduit: PVC female adapter. Bends Expansion/Deflection Fittings PVC Conduit CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 20 of 22 DATE: April 2012 .3 Belled-End Conduit: Bevel the unbelled end of the joint prior to joining. 3.10 PVC-Coated Rigid Steel Conduit .1 Install in accordance with the manufacturer’s instructions. .2 All tools and equipment used in the cutting, bending, threading and installation of PVC-coated rigid steel conduit shall be designed to limit damage to the PVC coating. .3 Provide PVC boot to cover all exposed threading. .1 Install in accordance with Application Information Section of NEMA VE 2. .2 Provide accessories as necessary for a complete system. .3 Install such that joints are not made at support brackets. .4 The Contractor shall design and provide ceiling trapeze for all horizontal cable trays. .5 Install support within 600 mm on each side of expansion joints and within 600 mm of fitting extremity. .6 Provide expansion joints in accordance with NEMA VE 1 for 14 degrees Celsius maximum temperature variation. .7 Install horizontal tray level, plumb, straight, and true to line or grade within a tolerance of 3 mm in 3 metres and within a cumulative maximum of 12 mm. .8 Install vertical tray plumb within a tolerance of 3 mm in 3 metres. .9 Install without exposed raw edges. .10 Maintain 300 mm vertical separation between multi-tiered trays having a common support, and at all crossover locations. .11 Provide bonding jumper at each expansion joint and adjustable connection. .12 Ground Conductor: Provide properly sized clamps for each section, elbow, tee, cross, and reducer. .1 Install cables individually. .2 Lay cables into cable tray. Use rollers when necessary to pull cables. .3 Secure cables in cable trough at 6 m centers, with nylon ties. .4 Identify cables every 15 m with size 2 nameplates . .5 Maintain spacing between the cables to provide the required cable ampacity. 3.11 Cable Trays 3.12 Cables in Cabletrays CONTRACT NO T-12-16 Section 16130 RACEWAYS Page 21 of 22 DATE: April 2012 3.13 Multi cable transits (MCT) .1 Ensure that larger diameter cables are installed in lower levels and the smaller diameter on top. .2 Ensure all modular blocks be coated with multi cable transits (MCT) lubricant prior to cable being installed. .3 All spaces not enclosed with cables and modular blocks be sealed with filler blocks to ensure a completely sealed system. .1 Cast Metal Enclosure: Provide manufacturer’s premolded insulating sleeve inside metallic conduit terminating in threaded hubs. .2 Nonmetallic, Cabinets, and Enclosures: Terminate conduit in threaded conduit hubs, maintaining enclosure integrity. .3 Sheet Metal Boxes, Cabinets, and Enclosures: .1 Rigid Galvanized or Aluminum Conduit: 1. Provide one lock nut each on inside and outside of enclosure. 2. Install grounding bushing. 3. Provide bonding jumper from grounding bushing to equipment ground bus or ground pad; if neither ground bus nor pad exists, connect jumper to lag bolt attached to metal enclosure. 4. Install insulated bushing on ends of conduit where grounding is not required. 5. Provide insulated throat when conduit terminates in sheet metal boxes having threaded hubs. 6. Utilize sealing locknuts or threaded hubs on outside of NEMA 3R and NEMA 12 enclosures. 7. Terminate conduits at threaded conduit hubs at NEMA 4 and 4X boxes and enclosures. .2 Flexible, Nonmetallic Conduit: Provide nonmetallic, liquidtight strain relief connectors. .3 PVC-Coated Rigid Galvanized Steel Conduit: Provide PVC-coated, liquid-tight, metallic connector. .4 PVC Schedule 40 Conduit: Provide PVC terminal adapter with lock nut. .4 Motor Control Center, Switchboard, Switchgear, and FreeStanding Enclosures: .1 Terminate metal conduit entering bottom with grounding bushing; provide a grounding jumper extending to equipment ground bus or grounding pad. .2 Terminate PVC conduit entering bottom with bell end fittings. 3.14 Termination at Enclosures CONTRACT NO T-12-16 Section 16130 RACEWAYS DATE: April 2012 Page 22 of 22 3.15 Empty Raceways .1 Provide permanent, removable cap over each end. .2 Provide PVC plug with pull tab for underground raceways with end bells. .3 Provide nylon pull cord. .4 Identify, as specified in subsection 3.16, Identification Devices, with waterproof tags attached to pull cord at each end, and at intermediate pull point. .1 Raceway Tags: .1 Identify origin and destination. .2 Install at each terminus, near midpoint, and at minimum intervals of every 15 metres of exposed raceway, whether in ceiling space or surface mounted. .3 Provide nylon strap for attachment. .1 Protect Products from the effects of moisture, corrosion, and physical damage during construction. .2 Provide and maintain manufactured watertight and dust-tight seals over all conduit openings during construction. .3 Touch up painted conduit threads after assembly to cover nicks or scars. .4 Touch up coating damage to PVC-coated conduit with patching compound approved by the manufacturer; compound shall be kept refrigerated according to the manufacturers’ instructions until the time of use. 3.16 Identification Devices 3.17 Protection of Installed Work END OF SECTION CONTRACT NO. T-12-16 SPLITTERS, JUNCTION, PULL BOXES AND CABINETS DATE: April 2012 PART 1. 1.1 1.2 1.3 Section 16131 2011-03-15 Page 1 of 2 GENERAL Related Sections .1 Section 16050 – Basic Materials and Methods .2 Section 16122 – Wires and Cables .3 Section 16335 – Temporary and Transition Electrical Equipment Shop Drawings and Product Data .1 Submit shop drawings and Product data for cabinets in accordance with Section 01300 – Submittals. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16131 – Splitters, Junction, Pull Boxes and Cabinets as indicated in Schedule ‘A’ of the Bid Form. .1 Provide sheet metal enclosure, welded corners and formed hinged cover suitable for locking in closed position. .2 Provide main and branch lugs and connection bars are to match with the required size and number of incoming and outgoing conductors as indicated in the Contract Documents. .3 Provide a minimum of three spare terminals on each set of lugs in splitters less than 400 A. .1 Junction and pull boxes shall be of welded steel construction with screw-on flat covers for surface mounting. .2 Covers with a minimum of 25 mm of extension all around, for flush-mounted pull and junction boxes. .1 Provide Type E Cabinets: sheet steel cabinet with hinged door and return flange overlapping sides, handle, lock and catch, for surface mounting. .2 Provide Type T Cabinets: sheet steel cabinet, with hinged door, latch, lock, 2 keys, containing Unistrut backing flush mounted. .1 Approved Suppliers: Measurement and Payment PART 2. PRODUCTS 2.1 2.2 2.3 2.4 Splitters Junction and Pull Boxes Cabinets Control Panel Enclosure CONTRACT NO. T-12-16 SPLITTERS, JUNCTION, PULL BOXES AND CABINETS Section 16131 2011-03-15 Page 2 of 2 DATE: April 2012 .1 .2 .3 .4 Hammond Manufacturing Company Limited. Ralston Metal Products Limited. Rittal Systems Ltd. Pentair, Inc. (Hoffman). PART 3. EXECUTION 3.1 3.2 3.3 Splitter Installation .1 Install splitters and mount plumb, true and square to the building lines. .2 Extend splitters for the full length of equipment arrangement except where indicated otherwise in the Contract Documents. Junction, Pull Boxes and Cabinets Installation .1 Install pull boxes in inconspicuous but accessible locations. .2 Mount cabinets with top not higher than 2 m above finished floor. .3 Install terminal block as indicated in Type T cabinets in subsection 2.3 above. .1 Provide equipment identification in accordance with Section 16010 - Electrical General Requirements. .2 Install size 2 identification labels indicating the system name, voltage and phase. Identification END OF SECTION CONTRACT NO T-12-16 Section 16136 CABLE BUS FEEDER SYSTEM Page 1 of 4 DATE: April 2012 PART 1. GENERAL 1.1 1.2 1.3 1.4 Intent of Section .1 A complete CSA certified ventilated metal enclosed system shall be provided by the Contractor, including all necessary fittings, enclosure, connectors, entrance fittings, insulated conductors, electrical connectors, terminating kits and other accessories as required. .2 The bus system shall be suitable for indoor and/or outdoor use with conductor spacing and ventilation maintained throughout the system. .3 All elements of the bus enclosure shall be designed to eliminate any sharp edges or projections that may injure personnel or conductor insulations. .4 Rigid bus duct is NOT an acceptable alternative. .1 Submit shop drawings in accordance with Section 01300 Submittals. .2 Drawings to include electrical detail of conductors (quantity and ampacity) and enclosure dimensions. .1 Cable duct enclosure to be factory or field assembled to suit application. .2 Cables shall be field loaded. .3 Each finished section of cable bus enclosure to have nameplate, containing the manufacturers name, type, current rating of each phase and neutral cable (where applicable), BIL rating, and maximum spacing between supports. .4 Provide approval labels as applicable. .5 Two complete sets of installation instructions to be shipped with cable bus system. .1 Cable duct system rated at 5000 volts, 3-phase, 3-wire, plus one size #8AWG neutral for protection devices, plus 3/0 ground. .2 Amperes: as indicated on the Contract Drawings. Shop Drawings Plant Assembly Rating CONTRACT NO T-12-16 Section 16136 CABLE BUS FEEDER SYSTEM Page 2 of 4 DATE: April 2012 1.5 1.6 Measurement and Payment .1 The Work outlined in this Section shall be included in the lump sum price of Section 16136 – Cable Bus Feeder System as indicated in Schedule ‘A’ of the Bid Form. .1 United Wire & Cable Inc., Maxiamp cable bus system .2 MP Husky, Cable Bus System .3 Approved Equal .1 Cable duct enclosure to be made of fabricated aluminum and field loaded with insulated cables, supported and segregated by insulated cable support assemblies fastened to the enclosure at suitable intervals. Bug and rodent inside protection shall be provided. .2 Each straight length of duct enclosure to be factory assembled with necessary fittings. .3 The two side walls (main structural members) to be extruded aluminum at 0.08 inch to 0.125 inch (2mm to 3mm) thick, dependant on duct height. .4 The top and bottom enclosure sections shall be minimum 14 gauge aluminum with punched holes (not louvered style) to provide mechanical strength. The bottom section shall be factory installed by welding and the top cover shall be removable bolt on type. Cable Bus covers shall have a minimum of 25 percent opening of its total cover surface for efficient passage of air. .5 Cable supports are to be glass reinforced polyester, moulded with two sets of three or six cable grooves, with one set on each of the two opposite sides. .6 Conductor support blocks shall be composite non metallic material, self extinguishing, and with a minimum of 22 MPA compressive strength. The blocks shall be designed in segments to maintain a minimum of one conductor diameter in both the horizontal and vertical planes as required for free air rating. Cable supports are to be provided at maximum 24 inch (610mm) intervals. .7 The bus enclosure shall have a continuous current rating of a minimum of 1000 amps (50 degrees Celsius rise) and the resistance across the enclosure section shall not exceed 50 microhms. Acceptable Manufacturers PART 2. PRODUCTS 2.1 Enclosure CONTRACT NO T-12-16 Section 16136 CABLE BUS FEEDER SYSTEM Page 3 of 4 DATE: April 2012 2.2 2.3 2.4 2.5 2.6 .8 The bus enclosure shall be grounded at sufficient intervals for purpose of preventing a potential above ground on the bus enclosure in the event of fault. Cable bus enclosure shall be ULC certified as a grounding conductor. .9 Termination, entrance and tap boxes are manufactured in material coinciding with the cable bus enclosure. Termination, entrance and tap boxes to be certified to CSA 3R standards .1 Flange to be constructed of 3/16 inch (5 mm) aluminum sheet and sized to suit cable duct enclosure and complete with all necessary weather proofing materials (seal plate, heat shrink tubing, etc.). .1 Cable duct enclosure to have internal, 1 1/2 hour rated fire barrier, when passing through fire rated walls or ceilings. .1 Reference: CAN CSA C22.2 No. 18-M1987. CSA approved cables shall be used. .2 Power cables of size, type, insulation and quantity per phase, in accordance with the manufacturers’ data. .3 The conductors shall be phased and supported to maintain low impedance and ensure the mechanical strength necessary to prevent cable movement or damage under short circuit currents of 65,000 amps symmetrical. .4 Conductors shall be continuous length and pulled in after the bus enclosure is in place. Electrical connectors shall be used only at the termination of the conductor runs. All electrical termination materials shall be provided by the cable bus manufacturer. .5 Conductor temperature rise calculations and current balance calculations shall be provided. .1 Compression type cable connector bolted together and insulated. .2 Compression type cable splice, insulated. .1 INDOOR : High density polyethylene tube, 0.125 inch (3mm) thick, approx. 30 inch (760mm) length, to be used over joints and held in position by cable support assembly on each side of joint. .2 OUTDOOR : Tyco Electronics Corporation “Raychem” heat shrink insulation kits or equivalent, in accordance with the manufacturers’ data. Flanges Firestop Cable Cable Joints and Splices Cable Joints Insulation CONTRACT NO T-12-16 Section 16136 CABLE BUS FEEDER SYSTEM DATE: April 2012 2.7 Page 4 of 4 Bonding .1 Each Section of cable bus enclosure is bonded by the bolted joint between sections. Bolts are to be secured by external toothed plated lockwashers that bite into side walls. .2 Each expansion joint to be jumpered by 18 inch (455mm) length of cable on each side of enclosure. Size cable in accordance with OESC table 16. Terminate cable with compression type lugs and fixed on each side of enclosure using 3/8-16 inch bolts and external toothed lock washers. .1 Confirm all dimensions on site. .2 Factory authorized representative is to supervise installation and provide written certification of approval. PART 3. EXECUTION 3.1 Installation END OF SECTION CONTRACT NO. T-12-16 WIRING DEVICES DATE: April 2012 PART 1. 1.1 1.2 1.3 Section 16141 2011-03-15 Page 1 of 3 GENERAL Related Sections .1 Section 16010 – Electrical General Requirements .2 Section 16335 – Temporary and Transition Electrical Equipment .3 Section 16505 – Lighting Equipment .1 The Work outlined in this Section shall be included in the lump sum price for Section 16141 – Wiring Devices as indicated in Schedule ‘A’ of the Bid Form. .1 Submit shop drawings and Product data in accordance with Section 01300 – Submittals. .1 15 A and 20 A, 120 V, single pole, double pole, three-way, fourway specification grade switches. .2 Manually-operated general purpose AC switches with the following features: .1 Terminal holes approved for No. 10 AWG wire. .2 Silver alloy contacts. .3 Urea or melamine molding for parts which are subject to carbon tracking. .4 Suitable for back and side wiring. .5 Ivory toggle – office areas. .6 Brown toggle – non office areas .3 Use switches of one manufacturer throughout the Contract. .1 Receptacles with the amperage and voltage as indicated in Section 16050 – Basic Materials & Methods. .2 Use receptacles of one manufacturer throughout the Contract. .1 Approved Suppliers: .1 Rockwell Automation Canada Ltd (Allen-Bradley). Measurement and Payment Shop Drawings and Product Data PART 2. PRODUCTS 2.1 2.2 2.3 Switches Receptacles Selector Switch CONTRACT NO. T-12-16 WIRING DEVICES DATE: April 2012 .2 2.4 2.5 Section 16141 2011-03-15 Page 2 of 3 Schneider Canada Inc. (Square D). Special Wiring Devices .1 Ground fault receptacles are to be supplied and installed as shown on the Contract Drawings. .2 Supply and install 240/208V receptacles where shown on the Contract Drawings. .1 Provide cover plates for wiring devices. .2 Use cover plates from one manufacturer throughout the Contract. .3 Sheet steel utility box cover for wiring devices installed in surfacemounted utility boxes. .4 Stainless steel, 1 mm thick cover plates, with a thickness of 2.5 mm for wiring devices mounted in flush-mounted outlet boxes. .5 PVC cover plates for wiring devices mounted in surface-mounted FS (Fitting Shallow) or FD (Fitting Deep) type conduit boxes. .6 Receptacles and switches in unfinished areas shall be complete with coverplates to match related boxes. .7 Coverplates shall be provided for all blanked off outlets. .8 One piece gang plates shall be used at locations where more than one device is to be mounted adjacent to each other. .9 Weatherproof, double lift, spring-loaded cast aluminum cover plates, complete with gaskets for duplex receptacles as indicated in the Contract Documents. .10 Weatherproof cover plates complete with gaskets for single receptacles or switches. Cover plates shall be Scepter Corporation. type VSC 15/10 or WDR 15/10. .1 Switches: .1 Install single throw switches with the handle in the "UP" position when the switch is closed. .2 Install switches in gang type outlet boxes when more than one switch is required in one location. .2 Mount toggle switches at the height specified in Section 16010 Electrical General Requirements or as otherwise indicated in the Contract Documents. .3 Receptacles: .1 Install receptacles in gang type outlet boxes when more than one receptacle is required in one location. Cover Plates PART 3. EXECUTION 3.1 Installation CONTRACT NO. T-12-16 WIRING DEVICES DATE: April 2012 .2 .3 3.2 Section 16141 2011-03-15 Page 3 of 3 Mount receptacles at the height specified in Section 16010 - Electrical General Requirements or as otherwise indicated in the Contract Documents. Where a split receptacle has one portion switched, mount vertically and switch upper portion. Cover plates: .1 Protect the stainless steel cover plate finish with paper or plastic film until painting and all other Work is finished. .2 Install suitable common cover plates where wiring devices are grouped. .3 Do not use cover plates meant for flush outlet boxes on surface-mounted boxes. END OF SECTION CONTRACT NO. T-12-16 ELECTRIC VEHICLE CHARGING STATION DATE: March 2012 Section 16146 2012-03-08 Page 1 of 2 PART 1. GENERAL 1.1 1.2 1.3 1.4 1.5 Section Includes .1 Furnish and install one electric vehicle charging station, complete with all materials and accessories required for operation. .1 Section 16010 – Electrical General Requirements .1 SAE J1772 – Electric Vehicle and Plug in Hybrid Electric Vehicle Conductive Charge Coupler 1 The Work outlined in this Section shall be included in the lump sum price for Section 16146 – Electric Vehicle Charging Station as indicated in Schedule ‘A’ of the Bid Form. .1 Submit Product data describing: .1 Electrical power requirements .2 Cable, connector and electrical output .3 User control, identification and fee collection system .4 Control and status display available at station .5 Materials and finishes of station housing and mounting accessories .6 Management and operating instructions .7 Manufacturer’s standard warranty .2 Submit shop drawings showing: .1 Station dimensions .2 Mounting components and details .3 Locations and types of electrical connections .1 Single charging unit .1 Output: 208-240 VAC at 30 A .2 Output charging connector: SAE J1772 .3 Charging cable length: 5.48m .4 Designed and rated for outdoor use .2 Wall mounted charging station .3 Owner management functions .1 Radio frequency identification (RFID) or other card access Related Sections References Measurement and Payment Submittals PART 2. PRODUCTS 2.1 Charging Station CONTRACT NO. T-12-16 MODULAR WIRING SYSTEM DATE: January 2012 .2 .3 .4 2.2 Section 16145 2012-03-08 Page 2 of 2 Capability to meter and charge users Owner to have ability to designate users All accessories required for the Region’s management and control Products .1 ChargePoint CT2003 series as manufactured by Coulumb Technologies, Inc. .2 EV230WSRR as manufactured by Schneider Electric USA, Inc. .3 Or approved equal. .1 Inspect location where station is to be installed. .2 Verify that location is ready to accept proper installation. .3 Notify Consultant if conditions are present that would prevent proper installation. Do not proceed with installation until conditions are corrected. .1 Install system and components in accordance with manufacturer's instructions. .2 Coordinate with the Region regarding system setup and schedule for activation. .3 Demonstrate system operation to the Region’s representatives. PART 3. EXECUTION 3.1 3.2 Inspection Installation Verify that system is working properly. END OF SECTION CONTRACT NO. T-12-16 THREE PHASE INDUCTION MOTORS DATE: April 2012 PART 1. 1.1 1.2 1.3 Section 16221 2006-08-30 Page 1 of 9 GENERAL Summary .1 Comply with Division 1 - General Requirements and Section 16010 – Electrical General Requirements. .2 Products installed, but not supplied under the Work of this Section: Motors and power factor correction capacitors supplied together with drive equipment as package. Refer to drive equipment specifications. .3 Power factor correction capacitors: When required, supplied as package with motor. .1 Section 11441 – Dry Pit Centrifugal Pumps .2 Section 15830 - Fans .3 Section 15855 – Air Handling Units .4 Section 15856 – Custom Air Handling Units .1 Comply with the latest edition of the following statutes codes and standards and all amendments thereto. .1 Design motors in accordance with applicable sections of American National Standards Institute (ANSI), Institute of Electrical and Electronics Engineers (IEEE), National electrical Manufacturers Association (NEMA) and Canadian Standards Association (CSA). .2 Electrical Equipment Manufacturers Association of Canada (EEMAC) 1. EEMAC Standard MG1, Motors and Generators. 2. EEMAC Standard M1-6, Motors and Generators. 3. EEMAC Standard MG2, Safety Standard for Construction and Guide for Selection, Installation and Use of Electric Motors and Generators. .3 Canadian Standards Association (CSA). 1. CSA C22.2 No. 100-04, Motors and Generators. 2. CSA C22.2 No. 145-M1986, Motors and Generators For Use in Hazardous Locations. CSA C390-98, Energy Efficiency Test Methods for 3. Three-Phase Induction Motors. .4 Institute of Electrical and Electronics Engineers (IEEE) 1. IEEE 112, Standard Test Procedure for Polyphase Induction Motors and Generators. Related Sections References CONTRACT NO. T-12-16 THREE PHASE INDUCTION MOTORS DATE: April 2012 1.4 1.5 1.6 Section 16221 2006-08-30 Page 2 of 9 Quality Assurance .1 Conduct tests by methods detailed in IEEE 112 for three phase motors. .2 Unless noted otherwise in the Contract Documents, prior to shipment from motor manufacturer's factory to the Site, subject motors to routine tests as defined by NEMA/ANSI and IEEE. .3 Perform tests at motor full speed. .4 Statically and dynamically balance motors over 0-125 percent speed range in accordance with ISO G2.5 .5 Refer to related driven equipment specification for additional testing requirements in motor manufacturer's factory or driven equipment manufacturer's factory. Co-ordinate and include costs associated with additional testing. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16221 – Three Phase Induction Motors as indicated in Schedule ‘A’ of the Bid Form. .1 Submit the following shop drawings, information and data: .1 Motor and nameplate and performance data. .2 Efficiency and power factor at 1/2, 3/4 and full load. .3 Approximate outline dimensions of each motor, showing sizes and location of terminal boxes and horizontal and vertical clearances necessary for maintenance purposes. .4 Speed-torque curve, speed-current curve, rotor WK2 starting time, and locked rotor time. Maximum safe locked rotor time. .5 .6 Total weight and heaviest shipping weight of motor. .7 Permissible number of fully loaded and unloaded starts over a defined time period (e.g. starts per hour). .8 Design information regarding shaft and sheave sizes for coordination with driven equipment. .9 Diagrams of auxiliary systems, such as resistance temperature detectors, current transformers for differential protection. Auxiliary cooling water and leakage detection system. Space heaters to prevent moisture from condensing on the windings. .10 Manuals 1. Submit bound and indexed copies of operating and maintenance manuals including, but not limited to, the following: 2. Storage instructions 3. Complete parts list Measurement and Payment Submittals CONTRACT NO. T-12-16 THREE PHASE INDUCTION MOTORS DATE: April 2012 4. 5. 6. 7. 8. 1.7 Section 16221 2006-08-30 Page 3 of 9 Manufacturer’s recommended spare parts list Installation instructions Operating instructions Maintenance instructions Routine factory test results Design Requirements .1 Supply severe duty fixed speed, three lead, single-voltage, squirrel-cage induction motors designed for full voltage .2 Design motors and individual components thereof to perform at full nameplate rating in 40 degrees Celsius temperature and ambient conditions specified in the Contract Documents. Motor output power to meet operating conditions without infringing upon motor service factor rating. .3 Supply motors with 1.15 service factor .4 Comply with applicable standards of ANSI, IEEE, NEMA and CSA .5 If the required horsepower falls between two listed horsepower ratings, design the motor for the higher horsepower rating. .6 Minimum efficiency at full load to be 93 percent. .7 Utilize a design B squirrel cage induction motor, provided that this design meets starting and operating requirements of equipment. Minimum starting and breakdown torque as indicated in EEMAC MG1. If larger load torque or WK² requirements are encountered, other motor design type selection is acceptable subject to prior acceptance by the Consultant. .8 Motors to operate continuously at rated load without exceeding maximum temperature rise of 80 degrees Celsius above ambient temperature of 40 degrees Celsius. .9 Size pump and fan motors for duty point conditions without including service factor. .10 Power supply variations: A combination of 10 percent voltage variation, 2 percent phase voltage imbalance and continuous operation at rated load in specified ambient is not to raise winding hot-spot temperature beyond insulation class rating. .11 Do not exceed the maximum locked rotor current values as listed in EEMAC Standard MG1 for the specified EEMAC design and rating. .12 Maximum overall sound pressure level: 80 dBA measure on "A" weighing network using an octave band frequency analyzer conforming to ANSI Standard S1.12. Measure mean sound pressure level in accordance with IEEE 85. CONTRACT NO. T-12-16 THREE PHASE INDUCTION MOTORS DATE: April 2012 Section 16221 2006-08-30 Page 4 of 9 PART 2. PRODUCTS 2.1 2.2 2.3 Approved Suppliers .1 Electric Motor (>40 kW): .1 U.S. Electrical Motors, div. Emerson. .2 WEG Electric Motors Corp. .3 General Electric Company. .2 Electric Motor (<40 kW): .1 U.S. Electrical Motors, div. Emerson. .2 WEG Electric Motors Corp. .3 General Electric Company. .4 TECO-Westinghouse Motors (Canada) Inc. .5 Brook Crompton (Canada) Inc. .6 Emerson Industrial Automation (Leroy-Somer). .3 Power Factor Correction Capacitor: .1 TECO-Westinghouse Motors (Canada) Inc. .2 ABB Inc. .1 Frames: EEMAC standard regarding frame/horsepower relationships for single speed applications. .2 Frame Construction: The frame shall be constructed of cast or modular iron cast steel or welded steel plate. The end plates shall be detachable in order to facilitate the removal of the rotor and aid in the replacement of stator coils. Aluminum housing or endbells not acceptable. .3 Corrosion prevention: Internal parts of motor exposed to external cooling air, such as air deflectors and fans, shall be of corrosion resistant material or shall be equipped with corrosion resistant plating. Mounting hardware shall be of corrosion resistant material. .4 Mounting: Unless otherwise indicated in the Contract Documents, foot mounted suitable for horizontal installation. .5 Bases: The motor mounts on the common pump base, as supplied by the manufacturer. .1 Windings and terminal leads: Copper conductors, with ends brought into terminal box. .2 Insulating material: Epoxy based, vacuum pressure impregnation (VPI) insulating system, all winding connections including leads, shall be placed prior to VPI. The insulation system shall meet the criteria for NEMA Class F insulation. Winding temperature rise shall be maximum at 80 degrees Celsius as measured by Enclosures Stator CONTRACT NO. T-12-16 THREE PHASE INDUCTION MOTORS DATE: April 2012 Section 16221 2006-08-30 Page 5 of 9 resistance at a 1.0 service factor. Minimum rating phase to phase 5 kV and neutral to ground 5 kV. 2.4 .3 End turn support system: Coil ends shall be braced in order to prevent fatigue and cracking of insulation during starting and extended operation. The bracing should be suitable to withstand an external three phase short circuit at full load and 100 percent voltage. .4 High humidity environment: use an anti-fungus treatment. .5 Winding temperature detection: Where indicated in the Contract Documents, two temperature sensors per phase in the stator windings and one each motor bearing with leads brought out to a separate terminal box. Platinum three wire RTD’s shall be provided with resistance of 100 ohms at 0 degrees Celsius. One RTD of each winding will be monitored. .6 Space Heaters: Space heaters shall be low watt density silicon rubber wrap around or strip type. .7 Treat insulation to render stator winding and leads moisture proof, it must pass a sealed winding conformance test in accordance with NEMA MG 1-20.49. .1 Sleeve: Sleeves shall be spherically seated, hydrodynamic babbit lined, self angling type, with the following features: .1 The bearings shall be easily removable without disturbing any part of the pump other than the bearing caps. .2 Sleeve bearing loading shall not exceed 1200 kPa when calculated on a projected shaft area. .3 The L/d ratio for the sleeve bearing shall not be less than 1.0; were “L” is the bearing length and “d” is the sleeve diameter at the bearing. .4 Provide bearings with a maximum surface finish roughness of 0.3 to 0.5 micron, rms. .5 Provide material with a maximum hardness at least 100 Brinnell points less than the shaft. The shaft surface finish inside the bearing shall have a .6 maximum surface roughness of 0.15 to 0.3 micron, rms. The shaft shall have a minimum surface hardness of 350 bhn (Brinell hardness number). .7 Design the bearings for operation in reverse rotation at 135 percent of the maximum rated speed. .8 The bearings shall be pressure oil lubricated by a standalone system. The oil shall be fed under pressure to the bearings and flow by gravity back to the pressure lubricating system. .9 A redundant, two piece, brass oil ring shall be able to pick up oil from the bottom of the bearing housing to allow Bearings and Lubrication CONTRACT NO. T-12-16 THREE PHASE INDUCTION MOTORS DATE: April 2012 .10 .11 .12 2.5 2.6 2.7 Section 16221 2006-08-30 Page 6 of 9 equipment coast-down lubrication in the event of a power failure. The bearings shall only rely on the oil for cooling. Oil seals shall be floating labyrinth type. The motor manufacturer shall furnish and install bearing oil piping, flow switches, gauges, flow control valves, and isolation valves, as necessary to connect the individual bearings to the Oil Lubrication System. .2 Non drive end bearing shall be electrically insulated. .1 Rotation: For motors designed for single direction operation only, clearly indicate direction of rotation by means of arrow on nondriving end. Painted arrows are not acceptable. .2 Shaft extensions: With keys. .3 Keyway: EEMAC standards for EEMAC frame motors. .4 The rotor core shall be assembled with laminations of high grade fully processed and pre-coated silicon steel securely clamped between heavy end rings. The rotor bars and end rings shall be copper or copper alloy. Rectangular bars shall be placed in the slots without insulation or shims. End rings are to be induction brazed with silver brazing alloy. .1 Totally enclosed water cooled motors: Integral fan, part of rotor, non-sparking, abrasion resistant, low noise level material. Air flow from non-driving end toward driving end. .1 Terminal boxes: Waterproof, cast iron or heavy wall steel, split design, threaded conduit holes, field rotatable in 90 degree steps for bottom, side or top conduit entry. .2 Terminal box location: On right hand side when viewed from the non-driving end, unless otherwise indicated in the Contract Documents. .3 Motor lead terminations: Solderless type for incoming cable connections and clamp terminal for ground connections. Clearly and permanently mark motor leads. .4 Frame to terminal box cable passage: Seal to prevent the entrance of moisture or foreign matter. .5 Gaskets: Between cover and box mating surfaces. .6 Window type: Provide current transformers for differential protection with 50/5 Amperes-ANSI accuracy C10, - one for each winding. Provide separate terminal box for the same Rotor Assembly Ventilation System Terminal Boxes CONTRACT NO. T-12-16 THREE PHASE INDUCTION MOTORS DATE: April 2012 2.8 2.9 Section 16221 2006-08-30 Page 7 of 9 .7 Provide surge capacitors and lightning arrestors, mounted and connected as close as possible to the motor leads. Their primary function is to attenuate the incoming very high, rates of current change that can cause damage to machine winding. Lightning arrestors to serve as a limitation on the magnitude of the surges. These units will be accessible only after opening of main terminal box. .8 Design all high voltage motor terminal boxes large enough for installation of stress cones, current transformers and surge arrestors. .9 Where ancillary devices are specified in the Contract Documents provide a separate box for termination of sensor leads. Leads to be clearly identified, provide nameplate data and connection diagram. .1 Finish: Non-machined metal surfaces, one coat, primer and one coat suitable corrosion and oil resistant paint. Colour, manufacturer standard, unless otherwise indicated in the Contract Documents. .2 Highly corrosive areas: Chemical duty, epoxy finish. .3 Shipping protection: Including machined surfaces, protect with suitable means to prevent corrosion or moisture accumulation and damage during shipment and installation. .1 Lifting provisions: Motors weighing 23 kg minimum, one or more lifting eyebolts, rings, or lugs capable of supporting weight of motor. If lugs are concealed by enclosure, attach nameplates to both sides of motor warning against improper lifting. .1 Nameplates: Stainless steel or non-corrodible alloy, embossed lettering, fixed to non-removable part of frame, in easily readable location, nameplates gives. .1 Manufacturer’s type and frame designation .2 Horsepower/kilowatts output .3 Time rating .4 Temperature rise .5 RPM at rated load .6 Frequency .7 Number of phases .8 Voltage .9 Rated load amperes .10 Code letter and inrush current .11 Service factor Painting Lifting Provisions 2.10 Nameplates CONTRACT NO. T-12-16 THREE PHASE INDUCTION MOTORS DATE: April 2012 .12 .13 .14 .15 Section 16221 2006-08-30 Page 8 of 9 Enclosure Manufacturer’s name, mark & logo Manufacturer’s plant location Serial number and date of manufacture .2 Dual voltage and multi-speed motors: Nameplate information showing wiring diagram and connection for each voltage and/or speed. .1 Capacitors to be switched with motors unless otherwise indicated in the Contract Documents. Power factor to be corrected to a range, minimum of 0.93 lagging. .2 Rating selection: By motor manufacturer, to prevent overvoltage and damaging transient torques. .3 Liquid filled capacitors: With internal or external drip pans to contain liquid in the event of a rupture. .4 Enclosure: Splash proof, steel construction with removable cover, suitable for floor mounting adjacent to motors. .5 Liquid impregnated polypropylene film for high voltage application. .6 Internal discharge resistors: To discharge unit to 50 V maximum within one minute after disconnection from supply. .7 Ancillaries: Solderless line connectors, EEMAC 12 conduit box fuses, line terminals, fuse clips. .1 Protect motor against physical damage and moisture until it is ready for energization. .2 Dry out motor in accordance with the manufacturer's recommendations if dampness is present. .3 Install motor on driven machinery, baseplate, structure, slide rails or concrete base (once fully cured), rigid plumb square, using only lifting facilities provided. .4 Make electrical connections as indicated in the Contract Documents. Install liquid-tight PVC jacketed flexible conduit section between rigid conduit feed and motor where applicable. .5 Where applicable, make flexible conduit or armoured cable long enough to permit movement of motor over entire length of slide rails. .6 Check direction of rotation with motor uncoupled from driven equipment. Correct rotation where required. .7 Co-ordinate with the personnel or Subcontractor installing the driven equipment in the alignment and coupling of motor to driven 2.11 Capacitors PART 3. EXECUTION 3.1 Installation CONTRACT NO. T-12-16 THREE PHASE INDUCTION MOTORS DATE: April 2012 Section 16221 2006-08-30 Page 9 of 9 machinery. Comply with the manufacturers' instructions and use correct parts such as couplings, belts, sheaves, as provided by motor manufacturer. 3.2 .8 Where applicable, install power factor correction capacitors supplied with motor and make final connections. .1 Before connecting feeder cable, measure winding insulation resistance between each phase and ground. Repeat tests after connecting feeder cable at the supply. Where applicable, disconnect power factor capacitors, surge arresters and solid state equipment during tests. .2 Verify the operation and settings of the motor protection system before energization. .3 Check motor lubrication, alignment and direction of rotation. .4 For motors rated 200 kW minimum, employ the services of an independent testing agency that is otherwise acceptable to the Consultant to test variation in motor full load and peak current by means of an oscillograph as indicated by EEMAC MG1. Tests END OF SECTION CONTRACT NO T-12-16 ADJUSTABLE SPEED DRIVES FOR 5 KV MOTORS DATE: April 2012 PART 1. 1.1 1.2 1.3 Section 16263 2006-08-30 Page 1 of 13 GENERAL Description .1 This specification describes a complete Adjustable Speed AC Drive (ASD) used to control the speed of NEMA design B induction motors used in areas where low harmonic content is desired or mandated. .2 The Contractor shall ensure that the ASD manufacturer will supply the ASD and all necessary controls as herein specified. .3 The Contractor shall ensure that the ASD will be manufactured by a company with a minimum of fifteen (15) years experience in the production of this type of equipment. .4 The Contractor shall ensure that the ASD manufacturer will be able to provide start-up service, 24 hour/day emergency call service, repair Work, maintenance and troubleshooting training of customer personnel. .1 The ASD manufacturing facility shall be ISO 9001 and ISO 14001 certified. .2 All printed circuit boards shall be completely tested before being assembled into the complete ASD. The ASD shall be subjected to a functional test and load test. .3 All printed circuit boards shall be conformal coated for environmental protection. .4 The ASD manufacturer shall have an analysis laboratory to evaluate the failure of any component including but not limited to an entire phase module. .1 The specified ASD shall be designed and materials shall be furnished in accordance with the latest revisions of applicable sections of the following codes and standards. .1 International / European Standards for Design and Construction: .2 IEC / EN 60071-1: Insulation coordination - Part 1: Definitions, principles and rules .3 IEC / EN 60146: Semiconductor Converters .4 IEC / EN 60664-1: Insulation coordination for equipment within low-voltage systems - Part 1: Principles, requirements and tests .5 IEC / EN 61800-4: Adjustable speed electrical power drive systems – Part 4: General requirements – Rating specifications for AC power Quality Assurance Codes And Standards CONTRACT NO T-12-16 ADJUSTABLE SPEED DRIVES FOR 5 KV MOTORS DATE: April 2012 .6 .7 Section 16263 2006-08-30 Page 2 of 13 drive systems above 1 000 VAC and not exceeding 35 kV IEC / EN 61800-5-1: Safety requirements electrical thermal and energy IEC 62103: Electronic equipment for use in power installations (EN 50178) .2 International / European Standards for Transformers .1 IEC 60146-1-3: Semiconductor Converters – General requirements and line commutated converters – Part 1-3: Transformers and reactors IEC 61378-1: Converter transformers – Part 1: .2 Transformers for industrial applications .3 Electromagnetic Compatibility (EMC) Standards .1 Special international committee on radio interference (CISPR) 22 Cl A: Information technology equipment - Radio disturbance characteristics; Limits and methods of measurement .2 IEC / EN 61000-2-4: Electromagnetic compatibility (EMC) – Part 2-4: Environment – Compatibility levels in industrial plants for low-frequency conducted disturbances .3 IEC / EN 61800-3: Adjustable speed electrical power drive systems - Part 3: EMC requirements and specific test methods .4 Environmental Standards .1 IEC / EN 60721-3-1: Classification of environmental conditions – Part 3: Classification of groups of environmental parameters and their severities – Section 1: Storage .2 IEC / EN 60721-3-2: Classification of environmental conditions – Part 3: Classification of groups of environmental parameters and their severities – Section 2: Transport .3 IEC / EN 60721-3-3: Classification of environmental conditions – Part 3: Classification of groups of environmental parameters and their severities – Section 3: Stationary use at weather protected locations .5 American Standards .1 IEEE 519: Guide for Harmonic Control and Reactive Compensation of Static Power Converters .2 IEEE 958: Guide for Application of AC Adjustable Speed Drives on 2400-13800 V auxiliary systems in electric power generating stations .3 IEEE 1566: Standard for Performance of Adjustable Speed AC Drives Rated 375 kW and Larger CONTRACT NO T-12-16 ADJUSTABLE SPEED DRIVES FOR 5 KV MOTORS DATE: April 2012 .4 .5 .6 .7 1.4 1.5 1.6 Section 16263 2006-08-30 Page 3 of 13 IEEE C57.12.00: General Requirements for LiquidImmersed Distribution Power and Regulating Transformers IEEE C57.12.01: General Requirements for DryType Distribution and Power Transformers IEEE C57.18.10: Practices and Requirements for Semiconductor Power Rectifier Transformers Industrial Controls and Systems (ICS) 7.1 NEMA Safety standard for construction and guide to selection, installation and operation of Adjustable Frequency Drive Systems Qualifications .1 Acceptable manufacturers: .1 ABB Asea Brown Boveri Ltd., ACS 2000 Ultra Low Harmonic (ULH) drive. .2 Allen Bradley, Rockwell Automation, Inc. .3 ASD’s that are manufactured by a third party and/or “brand labeled” shall not be acceptable. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16263 – Adjustable Speed Drives for 5 kV Motors as indicated in Schedule ‘A’ of the Bid Form. .1 The Submittals shall include the following information: .1 Outline Dimensions and Weight. .2 Customer connection and power wiring diagrams as applicable to the specific installation requirement. .3 Complete technical product description including a complete list of options provided. .4 Cooling air requirements and cooling fan compatibility .5 Documented test results confirming Ultra low Harmonic and unity power factor without Power Factor correction capacitors. .1 The ASD shall be ‘state of the art’ Voltage Source, 5 level topology utilizing High Voltage insulated gate bipolar transistor (IGBT) technology. .2 The ASD shall be an Ultra Low Harmonic Adjustable Speed AC Drive that is designed to comply with standard IEEE 519-1992 when installed into a system that already is in compliance with this Measurement and Payment Submittals PART 2. DESIGN 2.1 Description CONTRACT NO T-12-16 ADJUSTABLE SPEED DRIVES FOR 5 KV MOTORS DATE: April 2012 Section 16263 2006-08-30 Page 4 of 13 standard without the use of a multi-pulse transformer or active filter components. 2.2 .3 Reliability: .1 The Mean Time Between Failure (MTBF) of the ASD shall be greater than 40,000 hours, demonstrated. All components of the ASD shall be considered for MTBF calculations. .2 The calculated Availability of the ASD shall be greater than 99.95 percent. The Availability shall be calculated based on the expected downtime due to corrective and preventive maintenance. .3 The manufacturer shall list any control or power components that require recommended maintenance or replacement before 40,000 hours of operation. Information must be available in manufacturer's maintenance manual and available for submittal. .4 ASD’s, using electrolytic capacitors in the power circuit, will not be accepted. Foil capacitors with estimated life of 100,000 hours or greater shall be used. .5 All power semiconductors and passive power components in both the rectifier and inverter part shall be medium voltage rated components rated 3300 V minimum. Low voltage components are not acceptable in the power circuit. .6 In the event of either an input or output power semiconductor failure, the component or assembly containing that component shall have a mean time to repair no greater than 30 minutes. .4 ASD Output Power Quality .1 Motor cable voltage reflections shall not result in any performance restrictions on motor side for cable distances up to 300 m. . .2 The ASD shall not induce greater than 2 percent torque pulsations in the motor air gap in the frequency range up to 100 Hz. .5 Efficiency .1 Overall Efficiency of the ASD system shall include the ASD Isolation Transformer (if required), ASD and all ASD auxiliaries (such as the cooling system), Power Factor Correction and Harmonic Filters. .2 The overall drive system efficiency shall be not less than 96 percent at full load, full speed. .1 The Ultra Low Harmonic construction of the ASD shall not contribute any significant harmonics to the system. The ASD shall Harmonics CONTRACT NO T-12-16 ADJUSTABLE SPEED DRIVES FOR 5 KV MOTORS DATE: April 2012 Section 16263 2006-08-30 Page 5 of 13 comply with the limits at or below those listed in “Harmonic Control in Electrical Power Systems, IEEE Std. 519-1992”. . 2.3 .2 All harmonic management devices must be internal to the ASD enclosure and supplied as a complete solution. .3 The ASD shall have an active line supply unit which controls the waveform of the input current and reduces the low order harmonic current drawn from the power line. Line currents and voltages shall be nearly sinusoidal. .4 IGBT’s shall be used in the rectifier and inverter circuits. The power structure of the inverter section shall be suitable for use in the rectifier section in order to minimize the number of unique spare parts required. .5 The ASD’s design shall not compensate for existing harmonic content in the distribution system. .6 The total power factor at the ASD input shall be > 0.95, for the load range of 20 percent to 100 percent. The Contractor shall ensure that the ASD manufacturer will provide a Power Factor Correction Filter if the ASD does not meet this requirement. .7 The ASD including Power Factor Correction and/or Harmonic Filter shall never have a leading power factor and take into account any interaction with other system components. ASD’s with large capacitance to ground on the input of the drive shall provide special provisions to maintain power factor above 0.96 throughout the entire speed range. .1 The ASD shall be rated to operate from 3-phase power at +10/-10 percent of rated voltage. The under voltage trip level shall be a minimum 25 percent under the nominal voltage. .2 The ASD shall be rated to operate at the following environmental operating conditions: ambient temperature 5 degrees Celsius to 40 degrees Celsius continuous. ASD’s that can only operate at 40 degrees Celsius intermittently (during a 24 hour period) are not acceptable and must be oversized. Altitude 0 to 2000 metres above sea level without derating, less than 95 percent humidity, non-condensing. .3 The ASD shall be rated to operate from input power from 48 Hz to 63 Hz. .4 Output voltage and current ratings shall match the adjustable frequency operating requirements of standard IEC and NEMA design A or NEMA design B motors. .5 The normal duty overload current capacity shall be 110 percent of rated current for one (1) minute out of ten (10) minutes. .6 The heavy duty overload current capacity shall be 150 percent of rated current for one (1) minute out of ten (10) minutes. Ratings CONTRACT NO T-12-16 ADJUSTABLE SPEED DRIVES FOR 5 KV MOTORS DATE: April 2012 2.4 Section 16263 2006-08-30 Page 6 of 13 .7 The area classification for the ASD shall be non-hazardous. .8 The ASD shall be protected from vibration with maximum sinusoidal displacement of 0.3 mm (2…9 Hz) and maximum acceleration of 1 m/s2 (2…200 Hz). .1 All models shall provide a complete, ready-to-install solution. Medium voltage input power cabling entering and exiting the ASD enclosure shall be a 3 in – 3 out configuration. External cabling to an isolation transformer is unacceptable unless specifically requested. .2 Construction shall be robust such that all power semiconductors are shipped completely assembled and installed in the drive cabinet. Separate shipping of power semiconductor phase modules is not acceptable .3 High voltage IGBT power technology shall be used. This technology shall be used for all power and voltage ranges offered by the manufacturer. The use of low voltage insulated gate bipolar transistors (IGBT) or medium voltage symmetrical gate commutated thyristors (SGCT) is unacceptable. .4 The ASD shall offer microprocessor based control logic that is isolated from power circuitry. .5 The ASD shall use the same main control board for all ratings. .6 Control connections shall remain consistent for all power ratings. .7 The ASD shall employ a pulse width modulation (PWM) controlled AC to DC rectifier (commonly referred to as an active supply unit or active front end). The ASD shall not require a multi-pulse transformer in order to meet IEEE 519 standards. If an input harmonic filter is required to meet IEEE 519 it shall be factory mounted and wired within the ASD enclosure. .8 The ASD shall be offered in NEMA Type 1/IP21 enclosures. .9 ASD shall be of free-standing construction and shall include the following standard features: .1 The phase modules in the cabinet shall be of a modular construction for quick removal and replacement. Phase modules shall be of modular construction with bus .2 stab connections to ensure fast and easy handling. .10 The ASD enclosure doors with access to power semiconductor parts shall include a mechanical interlocking system with a safety grounding switch. The enclosure doors can be opened only if the safety ground switch connects all DC buses to ground, to ensure all stored ASD and motor energy is discharged. Grounding of any power circuit via a resistor is not acceptable. Construction CONTRACT NO T-12-16 ADJUSTABLE SPEED DRIVES FOR 5 KV MOTORS DATE: April 2012 2.5 Section 16263 2006-08-30 Page 7 of 13 .11 ASD enclosure panels with access to medium voltage parts other than power semiconductors shall require a tool for entry. All panels shall have appropriate warnings. .12 All painted surfaces shall have an ANSI 61 grey exterior finish unless otherwise specified on Buyer’s Datasheet. Interior surfaces shall be bright (unpainted) galvanized steel. .13 The enclosure must be designed to avoid harmonic and inductive heating and eliminate radio frequency interference .14 Cooling fans of air cooled ASDs shall have the option for a redundant fan with automatic switch-over, if specified in Buyer’s Datasheet. Periodical cycling between active and stand-by fans shall be initiated automatically. Loss of redundancy shall issue an alarm. .15 ASD noise level shall be less than 85 dB(A) at 1 metre distance for air cooled ASDs. .1 Each ASD shall be equipped with a front mounted operator control panel consisting of a back lighted alphanumeric display and a keypad with the functions: .1 Run/Stop command .2 Local/Remote command .3 Speed Increase/Decrease command .4 Menu navigation and parameter selection .2 All parameter names, fault messages, warnings and other information shall be displayed. .3 During normal operation, the speed reference, and run/stop forward/reverse and local/remote status shall be displayed. A minimum of 2 additional user selectable values shall be available for display including the following values as a minimum: .1 Motor speed, current and power .2 Output frequency, voltage and torque .3 DC bus voltage .4 Cooling air pressure drop .5 Values of analog input and output signals .6 Status of discrete inputs and outputs. .4 Password protection shall be available for prevention of unauthorized parameter access. .5 The keypad shall be used for local control, for setting all parameters, and for stepping through the displays and menus. .6 An intelligent start-up assistant shall be provided as standard. The Start-up routine will guide the user through all necessary adjustments to optimize operation. Operator Interface CONTRACT NO T-12-16 ADJUSTABLE SPEED DRIVES FOR 5 KV MOTORS DATE: April 2012 2.6 Section 16263 2006-08-30 Page 8 of 13 Protective Features .1 The Contractor will provide a dedicated circuit breaker or vacuum contactor (hereto called Input Isolation Device); rated to protect the ASD at specified short-circuit levels. The Input Isolation Device shall be controlled by the ASD. .2 The ASD shall have short circuit detection capability at the gate unit level to allow for short circuit current to be switched off at the semiconductor level within 25 micro seconds. .3 A minimum of 40 time tagged fault messages shall be stored in the ASD’s fault history. .4 An Emergency Off pushbutton shall be provided on the ASD door. The Emergency Off pushbutton will trip the upstream main circuit breaker (MCB) and the motor will coast to stop. .5 A discrete (binary) input for ‘Process-stop’ shall be provided. The reaction upon activation of this input shall be either a ramp or coast to stop’, selectable by the user. .6 An automatic restart function shall attempt to restart the ASD after various internal fault conditions. An adjustable time-out setting shall be provided. The user shall have the option of employing this feature or disabling it. .7 The following motor protection functions shall be available at the ASD. .1 Motor winding or motor lead phase-to-phase short. .2 Motor ground fault protection. .3 Motor phase loss protection. .4 Stall protection shall be programmable to provide a warning or fault the ASD after the motor has operated above a programmed torque level for a programmed time limit. .5 Motor overload (overcurrent) protection shall be programmable to provide a warning or stop the ASD, applying a minimum of three time dependent thresholds. The ASD shall provide electronic motor overload protection. .8 The following ASD protective functions shall be available. .1 Overtemperature and pressure drop monitoring .2 Loss of cooling (fan) failure .3 ASD internal fault detection .4 Protection against input phase loss. .5 Surge arrestors for phase to phase and phase to ground line voltage transient protection. .6 The ASD shall provide input phase loss and line under voltage protection. .7 A power loss ride through feature shall allow the ASD to remain fully operational after losing power as long as CONTRACT NO T-12-16 ADJUSTABLE SPEED DRIVES FOR 5 KV MOTORS DATE: April 2012 .8 2.7 Section 16263 2006-08-30 Page 9 of 13 kinetic energy can be recovered from the rotating mass of the motor and load. For each programmed warning and fault protection function, the ASD shall display a message in complete English words or Standard English abbreviations. The five (5) most recent fault messages and times shall be stored in the ASD’s fault history. Control Inputs And Outputs .1 The Contractor shall provide 380 to 600 V auxiliary power. The ASD shall transform auxiliary power for the control section. Control power shall be defined on customer one line diagram by the Contractor in the product submittal. .2 Discrete Inputs .1 A minimum of ten (10) discrete inputs shall be provided. Inputs shall be independently programmable with function selections (run/stop, hand-off-auto, etc.). .2 Discrete (binary) inputs shall be designed for 24 VDC. Discrete input functions shall include ‘Run/Stop’, ‘Increase/Decrease’, ‘Disable Local’ (to prevent unauthorized operation from the local panel) and ‘Remote Reset’. .3 Additional (binary) inputs for transformer monitoring (oil pressure / temperature / level – alarm and trip) shall be available. .3 Discrete Outputs Minimum of four (4) freely programmable digital outputs .1 shall be provided. Selections shall include: Operating conditions such as ASD ready, ASD 1. running, reversed and at set speed General warning and fault conditions 2. 3. Relay contacts shall be rated to switch 6 Amps at 24 VDC or 115/230 VAC. .4 Analog Inputs .1 Minimum of two (2) analog inputs shall be provided: 1. Resolution of analog inputs must be at least 10 bit total resolution .5 Analog inputs shall be programmable for either voltage or current, (0-10V, or 0-20mA). Analog input signals processing functions shall include scaling adjustments and adjustable filtering. Analog signal functions shall include speed and torque reference signals. .6 Two (2) analog inputs shall be programmable to form a reference by addition, subtraction, multiplication, minimum selection or maximum selection. .7 Analog Outputs CONTRACT NO T-12-16 ADJUSTABLE SPEED DRIVES FOR 5 KV MOTORS DATE: April 2012 .1 .2 2.8 Section 16263 2006-08-30 Page 10 of 13 A minimum of two (2) analog outputs configurable for either voltage or current shall be provided. Outputs shall be independently programmable to provide signals proportional to output function selections including output speed, frequency, voltage, current and power. .8 RTD Inputs .1 If transformer winding temperature and/or motor winding and bearing temperature supervision are required, the drive shall provide an option for a minimum of 5 inputs. A Motor Protection Relay shall not be required for adequate protection. .9 Interface to Upstream Disconnect .1 Two (2) outputs and three (3) inputs shall be provided for interfacing to an upstream disconnect device. .1 If specified in Buyer’s Datasheet, serial field bus communication interface modules shall be provided. .2 The ASD shall be capable of communicating with other ASD’s or controllers via a serial communications link. A variety of communications interface modules for the typical overriding control systems shall be available. .1 Interface modules shall be available for a wide selection of protocols including but not limited to: 1. Modbus 2. Ethernet IP 3. DeviceNet 4. Profibus .2 I/O shall be accessible through the serial communications adapter. Serial communication capabilities shall include, but not be limited to: 1. Run-Stop control 2. Speed Adjustment 3. Accel/Decel time adjustments 4. The ASD shall have the capability of allowing the overriding controller to monitor feedback such as process variable feedback, output speed/frequency, current (in amps), % torque, power (kW), kilowatt hours, operating hours, relay outputs, and diagnostic warning and fault information. 5. A connection shall also be provided for personal computer interface. Software shall be available for ASD setup, diagnostic analysis, monitoring and control. Serial Communications CONTRACT NO T-12-16 ADJUSTABLE SPEED DRIVES FOR 5 KV MOTORS DATE: April 2012 2.9 Section 16263 2006-08-30 Page 11 of 13 Control Functions And Adjustments .1 Output frequency shall be adjustable between 0 Hz and 75 Hz. Operation above motor nameplate shall require programming changes to prevent inadvertent high-speed operation. .2 Stop mode selections shall include coast to stop and ramp to stop. .3 The ASD shall be capable of controlling deceleration of a load without generating an overvoltage fault caused by excessive regenerated energy. Overvoltage control on deceleration shall extend the ramp time beyond the programmed value to keep the amount of regenerated energy below the point that causes overvoltage trip. .4 The ASD shall run with a sensorless control algorithm with static speed error of less than 0.2 percent and open loop torque step rise time of less than 10 milliseconds. .5 The ASD shall be capable of starting into a rotating load (flying start) regardless of motor direction. It should then accelerate or decelerate to the active reference without tripping on fault or causing component damage. .6 The ASD shall provide an automatic current limit feature to control motor currents during startup and provide a “soft start” torque profile for the motor-load combination. Current and torque limit adjustments shall be provided to limit the maximum ASD output current and the maximum torque produced by the motor. .7 The ASD shall accept a start/stop command and speed reference from a local ASD panel, or from a remote panel. .8 Speed control functions shall include: .1 Adjustable min/max speed limits. .2 Three sets of critical speed lockout adjustments. .3 A built-in PID controller to control a process variable such as pressure, flow or fluid level. .9 Five (5) programmable critical frequency lockout ranges shall be provided to prevent the ASD from operating the load continuously at an unstable speed. .1 The ASD shall have optional data logging capability that will monitor and store all information with respect to system events and system alerts, as well as information about the ASD. .1 Data logging shall be independent from ASD control. .2 All events/alerts related to ASD operating data should be stored by the data logging system for later analysis. .3 Data logging system should on an event ASD basis monitor ASD operation and performance. .4 Data logging system should allow optionally to trend long term operating performance of the ASD 2.10 Datalogging CONTRACT NO T-12-16 ADJUSTABLE SPEED DRIVES FOR 5 KV MOTORS DATE: April 2012 .5 Section 16263 2006-08-30 Page 12 of 13 Data logging system should monitor and register all changes to the ASD configuration and monitor consequent performance .2 The data logging system should contain supporting information with respect to trouble shooting, tuning, and ASD set-up parameters .1 Optionally system should provide Preventive Maintenance information and monitor the Preventive Maintenance schedule over time. .3 The data logging system has to be equipped to enable remote access. .1 The data logging system should be equipped with remote access functionality enabling remote troubleshooting and performance analysis by Supplier experts (data transfer, remote collaboration, automated notifications etc.). .1 Enclosed ASD shall be provided with input emergency off function: .1 Emergency off command by the operator shall separate the ASD from the AC line by opening an upstream line circuit breaker. .1 Testing: .1 The ASD equipment shall undergo standard routine testing in accordance to applicable standards. Each ASD shall be factory load tested. This test shall .2 include a full current test and a light load test with an induction motor on a dynamometer test stand. .3 If requested in Buyer’s Datasheet, a factory acceptance test or factory inspection visit for Buyer’s representative shall be scheduled upon award of contract. .2 Spare Parts .1 The Contractor shall ensure that the ASD manufacturer shall provide a complete list of spare parts for the ASD. .2 The ASD manufacturer shall provide local support for renewal parts. .3 As a minimum, the ASD manufacturer shall include these spare parts as part of the Work of this Section: 1. 100 percent spares of each type of medium voltage fuse. 2. 100 percent spares of each type of low voltage fuse. 3. Spare filter material 4. Surge arresters. 2.11 Emergency Off Function PART 3. EXECUTION CONTRACT NO T-12-16 ADJUSTABLE SPEED DRIVES FOR 5 KV MOTORS DATE: April 2012 Section 16263 2006-08-30 Page 13 of 13 .3 Preparation for Shipment .1 Equipment shall be individually crated and tagged with proper identification of the assembly to which it belongs. Materials, including detailed wiring diagrams and .2 instructions for reassembling shipping sections and making bus connections at shipping splits shall be provided by the Contractor. .3 Terminal strips shall be provided for all interconnecting wiring at shipping splits. Each wire terminal shall be identified with permanent wire markers. .4 Installation .1 The Contractor shall ensure that the ASD manufacturer will provide adequate drawings and instruction material to facilitate installation of the ASD by qualified electrical and mechanical personnel employed by others. .5 Start-Up .1 The Contractor shall be able to provide commissioning services and basic hands-on maintenance and operation training on Site by an registered professional engineer licensed to practice in Ontario certified by the ASD Manufacturer. .2 Microsoft Windows based software shall be provided for ASD commissioning, parameters setup, fault log viewing, diagnostic analysis, monitoring and control. The software shall provide real time graphical displays of ASD performance. .6 Product Support .1 Factory trained application engineering and service personnel that are thoroughly familiar with the ASD Products offered shall be locally available at the installation location. .2 A 24/365 technical support line shall be available on a tollfree-line. .7 Warranty .1 All equipment furnished under this section shall be warranted by the installing Contractor and the equipment manufacturer(s) for a minimum period of 24 months from the date of Total Performance of the Work. .2 There shall be 24/365 support available on a toll-free-line. END OF SECTION CONTRACT NO. T-12-16 DRY TYPE TRANSFORMERS UP TO 600 V PRIMARY DATE: April 2012 PART 1. 1.1 1.2 1.3 Section 16271 2011-03-15 Page 1 of 2 GENERAL Related Sections .1 Section 16010 – Electrical General Requirements .2 Section 16335 – Temporary Electrical Equipment .1 Submit Product data in accordance with Section 01300 – Submittals. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16271 – Dry Type Transformers Up To 600 V Primary as indicated in Schedule ‘A’ of the Bid Form. .1 Design: .1 Type: ANN. .2 Size, voltage, phase, as shown on the Drawings. .3 Voltage taps: standard. .4 Insulation: Class 185 degrees Celsius temperature rise – 80 degrees Celsius over an ambient of 40 degrees Celsius. .5 Hipot: standard .6 Average sound level: 60 db .7 Enclosure – CSA # 2 .8 Mounting: Wall or Floor .9 Finish: in accordance with Section 16010 – Electrical General Requirements. .10 Rating - kVA .11 Winding – Copper – delta connected primary wye connected secondary with neutral grounding provision. .1 Provide equipment identification in accordance with Section 16010 - Electrical General Requirements. .2 Label size: 7. .1 Mount dry type transformers up to 75 kVA as indicated on the Contract Drawings. Product Data Measurement and Payment PART 2. PRODUCTS 2.1 2.2 Transformers Equipment Identification PART 3. EXECUTION 3.1 Installation CONTRACT NO. T-12-16 DRY TYPE TRANSFORMERS UP TO 600 V PRIMARY DATE: April 2012 Section 16271 2011-03-15 Page 2 of 2 .2 Mount dry type transformers above 75 kVA on the floor. .3 Ensure that there is adequate clearance around transformer for ventilation. .4 Install transformers in level upright position. .5 Remove shipping supports only after transformer is installed and just before putting the transformer into service. .6 Loosen isolation pad bolts until no compression is visible. .7 Make primary and secondary connections in accordance with the Contract Drawings. .8 Energize transformers after installation is complete. END OF SECTION CONTRACT NO. T-12-16 TRANSIENT VOLTAGE SURGE SUPPRESSION (TVSS) DATE: April 2012 PART 1. 1.1 1.2 1.3 1.4 1.5 Section 16289 2006-08-30 Page 1 of 6 GENERAL Scope .1 The Contractor shall furnish and install the Transient Voltage Surge Suppression (TVSS) equipment having the electrical characteristics, ratings and modifications as specified herein and as shown on the Contract Drawings. To maximize performance and reliability, the AC surge protection shall be integrated into electrical distribution equipment such as switchgear, switchboards, panelboards, busway and/or motor control centers. .1 Section 16620 – Emergency Power Generators .1 TVSS units and all components shall be designed, manufactured and tested in accordance with CSA standard C22.2 No.41.07 – Grounding and Bonding Equipment. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16289 – Transient Voltage Surge Suppression (TVSS) as indicated in Schedule ‘A’ of the Bid Form. .1 The following shall be submitted to the Consultant: .1 Provide verification that the TVSS device complies with the required CSA standards. .2 Provide actual let through voltage test data in the form of oscillograph results for the ANSI/IEEE C62.41 Category C3 & C1 (combination wave) and B3 (ringwave) tested in accordance with ANSI/IEEE C62.45. .3 Provide spectrum analysis of each unit based on MIL-STD220A test procedures between 50 kHz and 200 kHz verifying that the device’s noise attenuation equals or exceeds 50 dB at 100 kHz. .4 For retrofit mounting applications, provide electrical/mechanical drawings showing unit dimensions, weights, installation instruction details, and wiring configuration. .5 Provide test reports in compliance with NEMA LS1 from a recognized independent testing laboratory acceptable to the Consultant verifying that the suppressor components can survive published surge current rating on both a per Related Sections References Measurement and Payment Submittals CONTRACT NO. T-12-16 TRANSIENT VOLTAGE SURGE SUPPRESSION (TVSS) DATE: April 2012 Section 16289 2006-08-30 Page 2 of 6 mode and per phase basis using the IEEE C62.41. Test data on an individual module is not acceptable. 1.6 1.7 1.8 Submittals for Construction .1 The following information shall be submitted for record purposes: .1 Final drawings showing exact connection/configuration of the incorporated or retrofitted TVSS system. Drawings shall reflect all of the devices that were submitted to the Consultant for approval. .1 The Contractor shall ensure that the manufacturer will have a 24 hour response capability that can provide field engineering personnel on Site within 24-hours of a request from the Region. The field service organization must have fully accredited, power system engineers located nearby and on 24 hr notice time to arrive at the Site and who are capable of performing complete analysis, and coordination studies. Qualifications Delivery, Storage and Handling .1 1.9 Equipment shall be handled and stored in accordance with manufacturer’s instructions. One (1) copy of manufacturer’s instructions shall be included with the equipment at time of shipment. Operation and Maintenance Manuals .1 Equipment operation and maintenance manuals shall be provided with each assembly shipped, and shall include instruction leaflets and instruction bulletins for the complete assembly and each major component. .1 TVSS units installed within low voltage distribution equipment shall be provided by the manufacturer of the low voltage distribution equipment in which they are installed. PART 2. PRODUCTS 2.1 2.2 Manufacturers Voltage Surge Suppression - General .1 Electrical Requirements .1 Unit Operating Voltage – Refer to the Drawings for operating voltage and unit configuration. .2 Maximum Continuous Operating Voltage (MCOV) – The MCOV shall be greater than 115 percent of the nominal system operating voltage. CONTRACT NO. T-12-16 TRANSIENT VOLTAGE SURGE SUPPRESSION (TVSS) DATE: April 2012 .3 .4 2.3 Section 16289 2006-08-30 Page 3 of 6 The suppression system shall incorporate a hybrid designed Metal-Oxide Varistors (MOV) surge suppressor for the service entrance and other distribution level. The system shall not utilize silicon avalanche diodes, selenium cell, air gaps or other components that may crowbar the system voltage leading to system upset or create any environmental hazards. Protection Modes – For a wye configured system, the device must have directly connected suppression elements between line-neutral (L-N), line-ground (L-G), and neutralground (N-G). For a delta-configured system, the device must have suppression elements between line to line (L-L) and line to ground (L-G). TVSS Design .1 Balanced Suppression Platform – The surge current shall be equally distributed to all MOV components to ensure equal stressing and maximum performance. The surge suppression platform must provide equal impedance paths to each matched MOV. .2 Electrical Noise Filter – Each unit shall include a high – performance EMI/RFI noise rejection filter. Products not able to demonstrate noise attenuation of 50 dB at 100 kHz shall be rejected. .3 Extended Range Filter – The Surge Protective Device shall have a High Frequency Extended Range Tracking Filter in each Line to Neutral mode with compliance to UL 1283 and NEMA LS1. The filter shall have published high frequency attenuation rating in the attenuation frequencies. .4 Internal Connections – No plug-in component modules or printed circuit boards shall be used as surge current conductors. All internal components shall be hardwired with connections utilizing low impedance conductors and compression fittings. .5 Standard Monitoring Diagnostics – Each TVSS shall provide integral monitoring options: .1 Each unit shall provide a green/red solid state indicator light on each phase. The absence of a green light and the presence of a red light, shall indicate which phase(s) have been damaged. .2 Remote Status Monitor – The TVSS device must include form C dry contacts (one NO and one NC) for remote annunciation of unit status. The remote alarm shall change state if any of the three phases detect a fault condition. .3 Audible Alarm – The TVSS shall provide an audible alarm with a reset pushbutton that will be activated under any fault condition. CONTRACT NO. T-12-16 TRANSIENT VOLTAGE SURGE SUPPRESSION (TVSS) DATE: April 2012 .4 .5 .6 2.4 Section 16289 2006-08-30 Page 4 of 6 Event Counter – The TVSS shall be equipped with a system designed to indicate to the user how many surges, sags, swells and outages have occurred at the location. The event counter triggers each time under each respective category after significant event occurs. Push to Test – The TVSS shall be equipped with push-totest feature, designed to provide users with real time testing of the suppressor’s monitoring and diagnostic system. By depressing the test button, the diagnostic system initiates a self test procedure. If the system is fully operational, the self test will activate all indicator lights. Voltage Monitoring – The TVSS shall display true Root Mean Square (RMS) on the L-N voltage protection mode on Wye configuration and three L-L voltage on delta configuration. .6 Overcurrent Protection Fusing: In order to isolate the TVSS under any fault condition, the manufacturer shall provide: .1 Individual Fusing: MOV’s shall be individually fused via Copper Fuse Trace. The Copper Fuse shall allow protection during high surge (kA) events. .2 Thermal Protection: MOV’s shall be equipped with Thermal Fuse Spring (TFS) technology which allows disconnection of the suppression component at the overheated stage common during temporary over voltage condition. For small fault currents between 100 mA to 30 Amp, or if the occurrence is over a longer period of time, the TFS will disconnect first. .3 All overcurrent protection components shall be tested in compliance with UL 1449 – Limited Current Test and AIC rating test. .7 Minimum Repetitive Surge Current Capability shall be in accordance with the requirements of ANSI/IEEE C62.41 and ANSI/IEEE C62.45 .1 The suppression filter system shall be repetitive surge tested in every mode and it shall satisfy the requirements of ANSI/IEEE C62.41 and ANSI/IEEE C62.45 .1 The TVSS applications covered under this Section include distribution and branch panel locations, bus plugs, motor control centers (MCC), switchgear, and switchboard assemblies. The TVSS located in the branch panel shall be tested to demonstrate that it is suitable for ANSI/IEEE C62.41 Category C1 environments. .2 Lighting and Distribution Panelboard Requirements .1 The TVSS application covered under this section includes lighting and distribution Panelboards. The TVSS units shall System Application CONTRACT NO. T-12-16 TRANSIENT VOLTAGE SURGE SUPPRESSION (TVSS) DATE: April 2012 .2 .3 .4 .5 .6 .7 .8 2.5 Section 16289 2006-08-30 Page 5 of 6 be tested to demonstrate suitability for ANSI/IEEE C62.41 Category C1 environments. The TVSS shall not limit the use of through-feed lugs, subfeed lugs and sub-feed breaker options. The TVSS shall be installed as indicated in the Contract Documents. The panel board shall be capable of re-energizing upon removal of the TVSS. The TVSS components shall be connected to the panel board bus bar in a way which is recommended by the manufacturer. The TVSS shall be included and mounted within the panel board by the manufacturer of the panel board. The TVSS shall be of the same manufacturer as the panel board. The complete panel board including the TVSS shall be CSA and ULC listed. .3 Retrofit Installation (externally mounted suppressor).The maximum conductor lead length between breaker and suppressor shall not exceed 360 mm (14 inches). Comply with the manufacturer’s recommended installation and wiring practices. .4 Locate suppressor on load side of main disconnect device, as close as possible to the phase conductors and ground/neutral bar. .5 Provide a 30-amp disconnect. The disconnect shall be directly integrated to the suppressor and assembly bus using bolted bus bar connections. .6 The TVSS shall be integral to switchgear, switchboard, MCC and Bus Plug as factory standardized design. .7 All monitoring diagnostics features shall be visible from the front of the equipment. .1 All equipment enclosures shall conform to the appropriate NEMA designation as set out below. Provide enclosures suitable for locations as indicated on the Drawings and as described below: .1 NEMA 1 enclosures constructed for indoor use to provide a degree of protection to personnel against access to and contact with hazardous parts and to provide a degree of protection of the equipment inside the enclosure against ingress of solid foreign objects (falling dirt). .2 NEMA 3R rainproof enclosures intended for outdoor use primarily to provide protection against rain, sleet and damage from external ice formation. .3 NEMA 12 dust-tight enclosures intended for indoor use primarily to provide protection against circulating dust, falling dirt and dripping non-corrosive liquids. (Panelboards Only). Enclosures CONTRACT NO. T-12-16 TRANSIENT VOLTAGE SURGE SUPPRESSION (TVSS) DATE: April 2012 .4 Section 16289 2006-08-30 Page 6 of 6 NEMA 4 watertight stainless steel intended for indoor or outdoor use primarily to provide protection against windblown dust and rain, splashing rain, hose-directed water, and damage from external ice formation. (Side Mounted Units Only) PART 3. EXECUTION 3.1 3.2 3.3 Factory Testing .1 Standard factory tests shall be performed on the equipment under this Section. All tests shall be performed in accordance with the latest version of the applicable NEMA and CSA standards. .1 The Contractor shall install all equipment in accordance with the manufacturer’s recommendations and the Contract Drawings. .1 The manufacturer shall provide a warranty of a minimum of 24 months commencing on the date of the Total Performance of the Work against any TVSS part failure when installed in compliance with manufacturer’s written instructions and Ontario Electrical Safety Code. Installation Warranty END OF SECTION CONTRACT NO. T-12-16 Section 16330 27.6 kV SWITCHGEAR MODIFICATIONS Page 1 of 6 DATE: April 2012 PART 1. 1.1 1.2 1.3 1.4 GENERAL Intent of Section .1 This Section outlines the requirement to supply and install a new cable bus feeder from connecting incoming hydro to the main switchgear of existing transformers T1 and T2 as indicated in the Contract Drawings, to allow rearrangement of incoming hydro feeders such that both the feeders are independently connected to the transformers and existing throat is removed. .1 This Section describes technical requirements to provide safe, orderly, and secure installation. The Contractor is responsible for submitting their own detailed arrangement for installation of the system as part of the Contract. .2 The substation will continue normal operations and supply power to allow for uninterrupted operation of the Leslie Sewage Pumping Station during upgrade Work. .3 The Contractor shall make changes shall be made to the existing arrangement, the throat connection to existing load break switch shall be removed and new metering unit installed in coordination with the power utility, PowerStream Inc. .1 Section 16010 – Electrical General Requirements .2 Section 16016 – Staging and Transition .3 Section 16020 – Demolition of Electrical Systems .4 Section 16031 - Inspection and Testing .1 The Contractor shall arrange for installation of a temporary arrangement to keep the plant running during the construction work for the changes. The Region does not have any intention to keep the temporary equipment, or temporary cabling. Remove the temporary system installation after the new arrangement is in place and successfully in operation for 14 Days. .2 Supply and install temporary load break disconnect switch, fuses, poles, grounding system, cabling, splices, and all ancillaries required to provide a reliable, metered power supply to the existing facility during construction period. Submit details of the proposed arrangement for temporary power system installation to the Region and PowerStream Inc. for approval. Refer to Contract Drawings, specifically E08 and E09 for minimum requirements of the temporary service. Purpose and Function Related Sections Scope CONTRACT NO. T-12-16 Section 16330 27.6 KV SWITCHGEAR MODIFICATIONS Page 2 of 6 DATE: April 2012 1.5 1.6 .3 Furnish all labour, materials, supervision, equipment, and services specified, indicated, or requested to reconfigure the incoming feeders as required and indicated on the Contract Drawings. .4 Provide a copy of the factory test for the review and approval of the Consultant. .5 Submit a copy of the Electrical Safety Authority (ESA)Site inspection and approval prior to energization. .6 The Contractor shall perform a short circuit and protection coordination study on the proposed temporary installation, and submit for approval by PowerStream Inc. and the Consultant. .7 Restore all affected areas after removal of temporary system. .1 The Work outlined in this Section shall be included in the lump sum price for Item P.5 - 27.6 kV Switchgear Modifications as indicated in Schedule ‘A’ of the Bid Form. .1 The Contractor shall submit copies of the same set of shop drawings directly to PowerStream Inc and to the Consultant for their respective review. Provide copies of PowerStream Inc.’s comments to the Consultant immediately after they have been received. The following drawings shall be submitted by the Contractor for review and approval by PowerStream Inc. and the Consultant before installation of the temporary arrangements on site: .1 Temporary Substation Single Line Diagram .2 Overall single line diagram showing the 27.6 kV circuits including the incoming PowerStream Inc. feeders and the 4.16 kV busses. The drawing will show the rating of the equipment and connection to protective and metering devices where applicable. .3 Overall Physical Layout of the assembly including: 1. Existing transformers and 27.6 kV junction boxes, 27.6 kV cable routing from the utility feeders in maintenance hole to the fused disconnect switch, to the Power Stream metering pack, to the transformer, details of incoming and outgoing feeder terminations and connections. .4 Installation Details 1. Interconnection of the incoming cables from manhole to the fused disconnect switch. 2. Interconnection of the Power Stream metering pack. 3. Interconnection to the transformer 27.6 kV terminals. Measurement and Payment Shop Drawings Submittal CONTRACT NO. T-12-16 Section 16330 27.6 KV SWITCHGEAR MODIFICATIONS Page 3 of 6 DATE: April 2012 4. 5. 6. 1.7 1.8 Equipment Maintenance .1 The Contractor will ensure that the equipment operates as intended by the Contract and without interruption for the duration of the construction period. .2 During the period where the facility is operating on the temporary system in the event of loss of one PowerStream Inc. feeder or other equipment failure (e.g.. transformer, cable), the Contractor is responsible for transferring the electrical supply to the alternate PowerStream Inc. feeder or connecting and energizing alternate equipment. .3 The Contractor will perform all troubleshooting, maintenance and/or repair activities and will bear any and all costs associated with maintenance and repair of the temporary equipment. Repairs required to return the Plant to service shall continue to minimize outage duration. .4 Where the cause of the failure may be attributed to the acts beyond the Contractor’s control or responsibility, the Contractor will return the Plant to service and submit copies of all records indicating time and material costs to the Consultant. .1 The Region must have advance notice, and be present for all opening and closing of circuit breakers, switches, etc. .2 Notwithstanding the above, the Contractor may de-energize equipment where continued energization may endanger personnel or property. The Contractor shall inform the Consultant and the Region immediately after any equipment has been deenergized under such conditions. .1 Install and commission the new PowerStream Inc. metering pack at new location as shown on the Contract Drawings. Equipment Operation PART 2. 2.1 Installation of temporary devices during different stages of construction. Provide correspondence from PowerStream Inc. advising actual Short Circuit MVA values and protective device settings. Compare calculated short circuit levels to equipment ratings in tabular form. Provide recommended settings for all proposed and existing protective devices in tabular and graphical format. Short Circuit and Protection Coordination Study confirming arc flash levels and relay settings. PRODUCTS Power Stream Metering Pack CONTRACT NO. T-12-16 Section 16330 27.6 KV SWITCHGEAR MODIFICATIONS Page 4 of 6 DATE: April 2012 2.2 2.3 2.4 2.5 2.6 .2 Coordinate with PowerStream Inc. as required to maintain metered service to their satisfaction. .1 Supply install and terminate temporary 27.6 kV Copper crosslinked polyethylene (XLPE) cables for supply of 27.6 kV power cable from manhole to the hydro pole for power availability during removal of the throat arrangement. The Contractor shall secure cables and supply strain relief connectors. .2 Supply and install temporary bare magneto hydro dynamic (MHD) conductors for 27.6 kV service. All Contractor supplied cables connected to the transformer shall meet the requirements of OESC Rule 26-258. .1 Utilize hot shrink or cold shrink terminations approved by the Electrical Safety Authority (ESA). .1 The Contractor shall ensure the continuity and integrity of the existing grounding system at all times. .2 Provide temporary grounding system (minimum 4-19 mm x 3000 mm ground rods each buried 300 mm underground, connected via 4/0 bare copper conductor), in accordance with OESC Rule 36-302 1(a) and ESA Bulletin 36-10-11. .3 Provide a ground mat for the operation of the disconnect switch on the temporary hydro pole. .4 Interconnect the temporary grounding to all temporary installations and the existing grounding system via 2-#4/0 copper grounding conductors. HV Cabling Termination Points Grounding System Neutral Ground Resistor (NGR) .1 Supply and install a temporary 80Ω (3000 A, 10 sec) NGR if called for by the protection study for the transition equipment. .2 Connect NGR to new ground. .1 Verify if the protection settings are good for the transition switchgear, if not modify the settings. .2 Modify existing protection to prevent damage to overhead lines, transformer, secondary cabling, etc. .3 Coordinate with PowerStream Inc. and obtain all necessary authorizations from PowerStream Inc. Protection Coordination CONTRACT NO. T-12-16 Section 16330 27.6 KV SWITCHGEAR MODIFICATIONS Page 5 of 6 DATE: April 2012 2.7 3.2 3.3 Commission and demonstrate to the satisfaction of PowerStream Inc. the Consultant and the Region. .1 Supply and install continuous 2.4 m high plywood hoarding c/w hinged man door around manholes and manholes/work areas in the transformer yard. .1 Review different options for completion of construction Work and layout of the temporary equipment at the Site as required. Provide details of the proposed location and layout based on the construction Site set-up, final point of connection to utility feeders, etc. .2 Set and secure the temporary cable trays on the agreed upon location. .3 Make field connections in accordance with manufacturer’s recommendations and obtain approval from the ESA. .4 Check factory made connections for mechanical security and electrical continuity. .5 The Contractor acknowledges that it has verified and included all costs associated with a construction sequence that allows installation of the proposed temporary equipment at a time acceptable to the Consultant. The Contractor shall not be entitled to claim any increase in Contract Time or in Contract Price as a result of the time proposed by the Consultant for the installation of the proposed temporary equipment. .1 Make field connections in accordance with manufacturer’s recommendations. .2 Make the grounding connections. .3 Check all existing connections for mechanical security and electrical continuity. .1 Record existing phase rotation and sequence of each incoming and outgoing feeder before the start of construction. Check phase rotation and phase sequence of each incoming and outgoing feeder before re-energization. Plywood Hoarding PART 3. 3.1 .4 EXECUTION General Installation Inspection and Testing CONTRACT NO. T-12-16 Section 16330 27.6 KV SWITCHGEAR MODIFICATIONS DATE: April 2012 3.4 Page 6 of 6 .2 All testing shall be performed in accordance with the NETA Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems 2009 and in accordance with these specifications. .3 Testing shall confirm conformance of the equipment to the requirements of Section 16031 - Inspection and Testing and shall confirm the proper functioning of the equipment. .4 The equipment shall be functionally tested as far as practicable in the Contractor’s plant and, again, in the field to test the operation of all circuits and devices and to optimize performance. .5 Conduct a coordination test to confirm fuse sizes and protection settings. . .6 Furnish a Test Report certifying successful completion of the above tests, and any other test. .7 Conduct a night time thermographic survey (to negate solar gain) of the current carrying parts after the switchgear has been placed in service. Provide three copies of all areas surveyed including photographs and temperature. Correct any hot spots. Reissue report after hot spots have been corrected. .1 The Contractor is responsible for the full functionality of the temporary installation, including ensuring that critical spare parts are available. .2 The temporary installation must be fully commissioned and demonstrated to be reliable, to the full satisfaction of the Region and the Consultant, prior to transferring loads. .3 The Contractor shall have all the special tools required for commissioning and servicing of the equipment (these will remain the property of the Contractor and shall be removed from the Site when the temporary equipment is removed from the Site). Maintenance and Operation END OF SECTION CONTRACT NO T-12-16 TEMPORARY & TRANSITION ELECTRICAL EQUIPMENT DATE: April 2012 Section 16335 Page 1 of 8 PART 1. GENERAL 1.1 1.2 1.3 Intent of Section .1 This Section outlines the requirement to supply and install temporary switchgear in order to allow replacement of the existing switchgear and some parts of the substation with new in the same location. .1 This Section is not intended to describe all details that may be required to affect the safe, orderly, and secure supply and installation of a temporary facility. The Contractor is responsible for submitting their own detailed arrangement for installation of the temporary system as part of the Contract .2 The transition switchgear and transition cabling will be used to supply power to allow for uninterrupted pumping station operation during replacement of the existing switchgear with new switchgear. The temporary switchgear will be placed on the temporary foundation, which is constructed for this purpose and removed later when the temporary switchgear is removed. .3 The temporary equipment and cabling shall be CSA certified, conform to all requirements of Electrical Safety Authority (ESA) and electrical fault protections are set in coordination with the existing system. .1 The Contractor shall arrange for the 4.16 kV Transition switchgear, transformer, diesel generator, transfer switch, cabling, control panel, monitoring system on the Region’s SCADA system. Provide as required or as shown in the Contract Drawings temporary 600V MCC, 600V-120/208V transformer and 120/208V panel board, cabling, disconnects, lighting etc. The Region does not have any intention to keep the transition or temporary equipment on completion of the Contract. .2 Supply and install temporary switchgear, MCC, transformer, lighting panel, cabling, splices, junction boxes, and all ancillaries required to provide a reliable power supply to the existing facility during the construction period. Submit details of the proposed arrangement for temporary power system installation to the Region and for approval. Refer to the single line Drawing for minimum requirements of the temporary equipment. .3 Furnish all labour, materials, supervision, equipment and services specified, indicated or requested to install the temporary equipment as required and indicated on the Contract Drawings. Purpose and Function Scope CONTRACT NO T-12-16 TEMPORARY & TRANSITION ELECTRICAL EQUIPMENT DATE: April 2012 1.4 1.5 Section 16335 Page 2 of 8 .4 Provide a copy of the factory test for the review and approval of the Consultant .5 Submit a copy of the ESA Site inspection and approval prior to energization. .6 The Contractor shall perform a short circuit and protection coordination study on the proposed temporary switchgear installation, and submit it to and for the approval of PowerStream Inc. and the Consultant .7 Temporary equipment shall be removed from the Site by the Contractor after completion of Site Acceptance Testing of permanent equipment. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16335 – Temporary and Transition Electrical Equipment as indicated in Schedule ‘A’ of the Bid Form. .1 The Contractor shall submit shop drawings directly to and ESA for their review and comment in parallel with submission to the Consultant. Provide copies of ESA comments to the Consultant. The following drawings shall be submitted by the Contractor for review by and approval obtained from PowerStream Inc. and the Consultant before shipment of the temporary equipment to the Site: .1 Switchgear and standby generator single line diagram. .2 Equipment elevation, layout and overall dimension. .3 Overall single line diagram showing the HV circuits including the incoming feeders and the LV busses. The drawing will show the rating of the equipment and connection to protective and metering devices where applicable. .4 Overall Physical Layout of the switchgear assembly including: 1. Plan diagram in fully assembled condition including existing transformers and HV junction boxes, HV cable routing from the utility feeders to switchgear and from the switchgear to the transformer, details of incoming and outgoing feeders terminations and connections. .5 Lighting panel schedules. .6 Transformer wiring diagram and overall dimension. .7 Installation Details 1. Interconnection of the incoming cables from entry point of the cables to switchgear. Interconnection of the cable outgoing cable from 2. switchgear to transformer HV. Measurement and Payment Submittals CONTRACT NO T-12-16 TEMPORARY & TRANSITION ELECTRICAL EQUIPMENT DATE: April 2012 3. 4. 5. 6. 1.6 1.7 1.8 Section 16335 Page 3 of 8 Interconnection of cable from transformer LV to indoor switchgear. Installation of temporary devices during different stages of construction. Provide information advising actual Short Circuit MVA values and protective device settings. Compare calculated short circuit levels to equipment ratings in tabular form. Provide arc flash labels and recommended settings for all proposed and existing protective devices in tabular and graphical format. Short Circuit, Protection Coordination Study and Arc Flash Study. Equipment Maintenance .1 The Contractor shall ensure that the equipment operates as intended by the Contract and without interruption for the entire construction period. .2 During the period where the pumping station is operating on the temporary switchgear, in the event of loss of one feeder or other equipment failure (e.g. transformer, cable), the Contractor is responsible for transferring the electrical supply to the alternate feeder or connecting and energizing alternate equipment. This transfer must be performed within six (6) hours from the time that the Contractor is informed of the loss of power by the Region. .3 The Contractor will perform all troubleshooting, maintenance and/or repair activities and will be responsible for any and all costs associated with maintenance and repair of the temporary equipment. Repairs required to return the pumping station to service shall continue around the clock to minimize outage duration. .1 The Region must be notified a minimum of 24 hours in advance of, and be present for all opening and closing of circuit breakers, switches, etc. .2 Notwithstanding the above, the Contractor may de-energize equipment where continued energization may endanger personnel or property. The Contractor shall inform the Consultant and the Region immediately after any equipment has been de-energized under such condition. Equipment Operation Operation and Maintenance Data .1 Operation and Maintenance data is for use by the Contractor. However, provide a duplicate copy to the Region, which will be CONTRACT NO T-12-16 TEMPORARY & TRANSITION ELECTRICAL EQUIPMENT DATE: April 2012 Section 16335 Page 4 of 8 handed back to Contractor after the equipment is removed from Site. Copy of operating and maintenance manuals to include: .1 Complete parts list .2 Detailed trouble shooting procedures and fault correction schedules .3 Data for each type and style of equipment PART 2. PRODUCTS 2.1 2.2 Switchgear-General Requirements .1 All switchgear shall be CSA approved .2 The switchgear and other appurtenances shall be provided in a walk in type weather proof, ventilated outdoor enclosure. .3 The switchgear shall meet PowerStream Inc. and ESA requirements. .4 The complete temporary switchgear installation including access, cable installation, clearances, etc. shall be approved by PowerStream Inc.. All costs resulting from this requirement are to be paid by the Contractor. .5 The switchgear shall be suitable for outdoor operation, 3 phase, 4 wire, 60 Hz, 5 kV for connection to 4.16 kV system. .6 Loadbreak switches shall be 5 kV design voltage operating at 4.16kV. Impulse levels shall be 150 kV minimum and a minimum short circuit level of 350 MVA. Switches shall be 3 pole group operated in a metal enclosed structure and designed for close coupling to existing transformers. .7 If applicable a sign stating “CAUTION, SWITCH BLADES LIVE” shall be installed on all doors and screens where knife blades or moving contacts may be live when the device is in the open position. Ratings – Temporary Switchgear .1 The switchgear shall be supplied with the following minimum ratings: CONTRACT NO T-12-16 TEMPORARY & TRANSITION ELECTRICAL EQUIPMENT DATE: April 2012 Rated maximum voltage, kV Type Interrupting device Nominal operating voltage, kV Number of phases Number of wires Rated frequency, Hz Rated continuous current main bus, A Rated short circuit level, MVA Rated short circuit current at rated RMS voltage, kA Short time withstand current (busbars, load break switches, HV fuse and all primary equipment, kA (3 sec) Normal voltage variation, % System grounding Basic Insulation Level, kV Power Frequency Level, kV Load interrupting (for load break switches), A 2.3 2.4 2.5 2.6 Section 16335 Page 5 of 8 8 kV Metal-enclosed 5 kV fuse 4.16 3 4 60 1200 800 29 Symmetrical 29 -15%, +10% Grounded 150 60 600 HV Cabling .1 Refer to the construction Drawings for HV cable size. Power Stream Inc. is to be advised and scheduled to participate in the changeover. .2 This Contractor shall supply cables or cable busses to connect the existing transformer and shall meet the requirements of OESC Rule 26-258. .1 MCC shall be CSA approved .2 The MCC shall meet ESA requirements. .3 The MCC shall be rated at 600 V, 300 A, 3-phase, 4-wire, 60 Hz. It can be used type from another job site. .1 Transformer shall be CSA approved and meet ESA requirements. .2 The transformer shall be dry type, 600-120/208, 45 KVA. It can be used type from another site. .1 Lighting panel shall be CSA approved and meet ESA requirements. .2 The lighting panel shall be rated at 120/208V, 200A, 3 phase, 4 wire, 42 circuiting 60 Hz. It can be used type from another site. MCC Transformer Lighting Panel CONTRACT NO T-12-16 TEMPORARY & TRANSITION ELECTRICAL EQUIPMENT DATE: April 2012 2.7 2.8 2.9 Section 16335 Page 6 of 8 LV Cabling .1 Refer to the construction drawings for LV cable size. The 4.16 kV cables shall remain in service until the new electrical switchgear and new generators are tested by conducting an onload test for 4 hours, commissioned and certified by the Consultant as being operationally reliable. .1 Utilize cold shrink terminations approved by the ESA, PowerStream Inc. and Hydro One Networks Inc. .1 Provide a ground bus with cable lugs at switchgear for connection of the switchgear and HV cable shielding to the temporary grounding system. .2 Bond temporary service to existing grounding system and upgrade as necessary to have ESA approvals (minimum 4-19 mm x 3000 mm ground rods each buried 300 mm underground, connected via 4/0 bare copper conductor), in accordance with OESC Rule 36302 1(a) and ESA Bulletin 36-10-11. .1 Review different options for layout of the temporary switchgear, transformer and lighting panel at the Site and provide details of the proposed location and layout based on the construction Site set-up, final point of connection to utility feeders, etc. .2 Set and secure the temporary switchgear, transformer and lighting panel at the locations shown in the Contract Drawings. .3 Make field connections in accordance with manufacturer’s recommendations and as approved by PowerStream Inc. and the ESA. .4 Check factory made connections for mechanical security and electrical continuity. .5 Apply device settings and verify all equipment ratings as approved in the Short Circuit and Protective Coordination study. .6 Refer to Section 16016 – Staging and Transition. .7 The Contractor acknowledges that has verified and included all costs associated with a construction sequence that allows installation of the proposed switchgear at a time acceptable to the Consultant. The Contractor shall not be entitled to claim any increase in Contract Time or in Contract Price as a result of the Termination Points Grounding System PART 3. EXECUTION 3.1 General CONTRACT NO T-12-16 TEMPORARY & TRANSITION ELECTRICAL EQUIPMENT DATE: April 2012 Section 16335 Page 7 of 8 time proposed by the Consultant for the installation of the proposed temporary switchgear. 3.2 3.3 Installation .1 Obtain the services of an inspection agency approved by the Consultant to assist the Contractor in installation and start-up of the equipment specified under this Section. The Contractor shall ensure that the Inspection Agency will provide technical direction and assistance to the Contractor in general assembly of the equipment, connections and adjustments, and testing of the assembly and components contained therein. .2 Set and secure switchgear assembly in place on channel base, rigid, plumb, and square. .3 Make field connections in accordance with manufacturer’s recommendations. .4 Make the grounding connections to an acceptable grounding grid. .5 Check all existing connections for mechanical security and electrical continuity. .1 Refer to Section 16031 – Inspection and Testing for additional inspections and tests required under this Contract. .2 Record existing phase rotation and sequence of each incoming and outgoing feeder before the start of construction. Check phase rotation and phase sequence of each incoming and outgoing feeder before re-energization. .3 All equipment shall be subject to inspection and testing by, and at the expense, of the Contractor. All testing, including shop tests and field tests, shall be performed in accordance with the NETA Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems 2009 and in accordance with these specifications. .4 Testing shall verify conformance of the equipment to the Contract Documents and shall confirm the proper functioning of the equipment. .5 The equipment shall be functionally tested as far as practicable in the Contractor’s plant and, again, in the field to test the operation of all circuits and devices and in order to optimise performance. .6 Check fuse sizes. .7 Place switchgear in service and check ammeter, and voltmeter readings to ensure proper functioning of the system. .8 Furnish a test report certifying completion of the above tests, and any other test. Inspection and Testing CONTRACT NO T-12-16 TEMPORARY & TRANSITION ELECTRICAL EQUIPMENT DATE: April 2012 3.4 Section 16335 Page 8 of 8 .9 Conduct a thermographic survey of the current carrying parts after the switchgear has been placed in service. Provide three copies of all areas surveyed including photographs and temperature. Correct any hot spots. Reissue report after hot spots have been corrected. .1 The Contractor is responsible for the full functionality of the temporary equipment, including ensuring that critical spare parts are available. .2 The temporary equipment must be fully commissioned and demonstrated to be reliable, to the full satisfaction of the Region and the Consultant, prior to transferring loads. .3 The Contractor is to have all the special tools required for commissioning and servicing of the equipment (these will remain the property of the Contractor and shall be removed from the Site when the temporary equipment is removed from the Site). Maintenance and Operation END OF SECTION CONTRACT NO T-12-16 Section 16339 STATION BATTERY AND CHARGER SYSTEM Page 1 of 7 DATE: April 2012 PART 1. GENERAL 1.1 1.2 1.3 General .1 Refer to the Contract Documents in order to determine their effect upon the Work of this Section. .2 Refer to Section 16010 - General Electrical Requirements. .3 Coordinate with switchgear manufacturers to ensure adequate and complete DC supply for the automatic control of breakers in accordance with the Contract Drawings and Documents. .1 The equipment to be designed and manufactured shall comply with the latest edition of the following statutes, codes and standards, and all amendments thereto: .1 CSA Canadian Standards Association 1. CSA C22.2 No. 223-M91 CAN/CSA UPD 2: Power Supplies with Extra-Low Voltage Class 2 Outputs IEEE Institute of Electrical and Electronics Engineers .2 1. IEEE Standard 323TM-2003 .3 NEMA National Electrical Manufacturers Association 1. NEMA Standard PES & PET .4 OESC Ontario Electrical Safety Code 23rd Edition, 2002 .2 The 125 V DC Charger System shall be in accordance with standard C22.2 No. 107. .3 The 125 V DC battery bank shall be sized in accordance with IEEE 1115-2000. .4 The 125 V DC battery bank shall be installed and tested in accordance with IEEE 1106-1995. .5 The battery bank shall comply with the International Electrical Commission International Standard IEC 623. .6 All dimensions and design data shall be in SI (metric) units. .1 Supply and install a station battery c/w charger for the operation of the 27.6 kV substation and the 4.16 kV switchgear. .2 Provide one 125 V DC station battery able to operate as described in “System Operating Narrative” complete with the following: .1 One charger. .2 One battery bank. .3 Incoming and outgoing circuit breakers. .4 125 V DC Distribution Panel. .5 Factory testing. .6 Manufacturers agent installation commissioning. Codes and Standards Scope CONTRACT NO T-12-16 Section 16339 BATTERY AND CHARGER SYSTEM Page 2 of 7 DATE: April 2012 1.4 1.5 .3 All equipment furnished shall be standard catalogue Products of the manufacturer and rated for switchgear equipment. .4 All active electronic devices shall be solid state and rated for maximum reliability. .1 The 125V DC charger system shall operate as follows: 1. Continuous 125V DC will supply an external DC distribution panel board. 2. Charger system will be supplied from a separate 600 VAC, three phase, 4 wire, 60 Hz supply. 3. Charger will normally supply DC power to the batteries, and both charger and batteries will normally supply the load. 4. Design the system so that the charger or battery bank can be taken out of service for maintenance or repair while the remainder of the system continues to provide DC output. 5. The 125 V DC Charger system will be on-line continuously. The loads will be fed from the batteries and chargers continuously. In the event that the input voltage goes into a reduced voltage operation, called “brown out”, the 125 V DC Charger output will be supplied or compensated by the batteries. The output of the 125 V DC Charger system will be maintained regardless of the input voltage quality and level. 6. Any failure in any of the systems will sound an audible alarm, as well as open a normally closed dry contact. The DC battery charger must be able to supply the 7. complete full load requirements of the DC system. This includes multiple switchgear breaker operations. .2 Load Profile: .1 The switchgear base load is 1200 VA consisting of protective relays and control circuits. .2 The battery also supplies: 1. The trip and close coils of eight (8) 27.6 kV circuit breakers and nine (9) 4.16 kV circuit breakers. 2. The spring charge circuit, trip circuits of eight (8) 27.6 kV circuit breakers and nine (9) 4.16 kV circuit breakers. .1 DC Charger System footprint shall not exceed dimensions shown on the Contract Drawings. System Operating Narrative Dimensional Constraints CONTRACT NO T-12-16 Section 16339 BATTERY AND CHARGER SYSTEM Page 3 of 7 DATE: April 2012 1.6 1.7 Measurement and Payment .1 The Work outlined in this Section shall be included in the lump sum price for Section 16339 – Battery and Charger System as indicated in Schedule ‘A’ of the Bid Form. .1 Comply with all submittals requirements as specified under Section 01300 – Submittals. .2 Submit the following shop drawings, information and data: .1 Detail specific electrical performance characteristics for the charger and batteries. .2 Detail layout, enclosure, cooling requirements and similar items. .3 Dimensional outline and equipment arrangement drawings including clearance requirements, foundation details and weights. .4 Electrical schematics, wiring and interconnection drawings. .5 Provide battery sizing calculations (capacity calculations) including all assumptions. .6 General instructions including: start-up and test procedures, troubleshooting guide, safety notes and maintenance procedures. Submittals PART 2. PRODUCTS 2.1 2.2 Battery System Nominal Requirements .1 Battery system shall be capable of the following duty cycle (upon loss of V AC input voltage): .1 Base load for the first 40 minutes. .2 Twelve (12) breaker close and open operations (in sequence) plus base load during the next ten (10) minutes. Coordinate with circuit breaker suppliers for ampere requirements for individual breaker spring charge operation and for breaker open/close signal. .3 Base load for the next six hours and forty minutes (400 minutes). .4 Thirteen breaker close and open operations (in sequence) plus base load during the next ten (10) minutes. .5 Base load for the remaining time twenty (20) minutes. .2 Nominal battery voltage, full charge 125 VDC. .3 Capable of being recharged in a period of 8 hours to a minimum of 95 percent full charge after supplying rated load for period specified, with no harmful effects on battery, including leaking or foaming of electrolyte. .1 Nickel-Cadmium, Flooded Cell. Battery Type CONTRACT NO T-12-16 Section 16339 BATTERY AND CHARGER SYSTEM Page 4 of 7 DATE: April 2012 2.3 Battery Charger .1 A 125 volt nominal SCR type battery charger to be provided to operate from a 600 VAC, three phase, 4 wire, 60 Hz supply. Charger to have sufficient capacity to recharge the fully discharged batteries in 8 hours to 95 percent charged while simultaneously feeding the continuous loads. .2 Charger to have the following characteristics: .1 Regulation: ±1 percent voltage from 0 to 100 percent load .2 ±10 percent input voltage variation .3 ±5 percent frequency variation .4 Ripple Voltage: 2 percent (RMS) .5 AC input Breaker, 600 VAC, 3 phase, 4 wire, size to suit .6 Analogue type DC voltmeter, 2 percent accuracy, 75 mm .7 Analogue type AC Ammeter, 2 percent accuracy, 75 mm .8 AC and DC surge suppression .9 Reverse battery protection (blocking diodes) .10 Automatic current limiting adjustable from 80 percent to 120 percent of normal voltage rating .11 Convection cooled .12 Short circuit proof .13 LEDs to indicate: 1. AC “ON” 2. FLOAT “ON” 3. EQUALIZE “ON” .14 Charger to normally operate in the float mode and to have a push-button on the control panel to initiate a timed equalize charge. The charger to automatically return to the float mode at the end of the timed out period. .15 Both the float and equalize voltages to be adjustable. .16 The float voltage to be adjustable from 110 to 140 volts DC. .17 The equalize voltage to be adjustable from 120 to 154 volts DC. .18 Complete input/output isolation to be provided between the AC input and DC output. .19 Charger to be equipped with the following local alarms: 1. Low DC voltage alarm 2. High DC voltage alarm 3. AC failure alarm 4. Charger failure alarm 5. Positive or negative DC ground detection alarm .20 Each of the alarms mentioned in subsection 2.3.2.19 to have a RED LED on the charger control panel. .21 Each of the alarms mentioned in subsection 2.3.2.19 to have two dry contacts indicating status of each alarm. .22 The charger shall have a single dry contact, normally open, which will close in the event that any of any of the alarm conditions listed above. CONTRACT NO T-12-16 Section 16339 BATTERY AND CHARGER SYSTEM Page 5 of 7 DATE: April 2012 .23 .24 2.4 The charger system to be equipped with following: 1. DC output breaker panel: as shown on Drawings. 2. Audible alarm when any mode light indicates trouble. Silence pushbutton not to extinguish trouble light. 3. A common LED test/reset switch and two common Form “C” alarms contacts to also be provided and tied to SCADA for “AC Failure” and “Battery Charger Failure” alarm monitoring (in accordance with the existing PCS Drawings). The noise generated by the charger, under all operational conditions shall be less than 65 DBA measured 1 m from any surface of the cabinet. System Enclosures .1 Provide a free standing and self-supporting formed metal enclosure to be supplied to house the charger and the battery bank. The enclosure dimensions not to exceed those indicated on the Contract Drawings. .2 Enclosure to be NEMA 12, fully metal enclosed type with dead front construction. Ventilation for battery charger and battery bank cabinet to be through slotted plates on the front or sides of the cabinet. The cabinet shall have adequate strength to withstand stresses imposed by shipping, handling, installation and operation. .3 Enclosure shall be constructed of steel frames and panels. Aluminium shall not be acceptable. The Contractor shall provide an engineered stamped/drawing for the frame supporting the battery bank (by an engineer licensed to practice in the Province of Ontario). .4 One (or two) door(s) shall be provided for the cabinet. Hinges shall be of the concealed type. Suitable cam type closures shall be provided to hold the door(s) securely closed. Door(s) shall be lockable. .5 The equipment shall be designed for front access only. .6 The batteries shall be mounted on step type shelves for visual inspection of all electrolyte levels. .7 Incoming and outgoing connections shall be through knockouts on the top or sides of the cabinets. .8 The cabinets shall be pressure cleaned with a phosphate solution and finished with one coat of ANSI 61 light grey epoxy enamel applied by an electrostatic process. .9 The cabinets shall have provision for handling by a forklift, pallet truck or sling. CONTRACT NO T-12-16 Section 16339 BATTERY AND CHARGER SYSTEM Page 6 of 7 DATE: April 2012 2.5 2.6 2.7 2.8 2.9 Quality Assurance .1 The Contractor shall ensure that the manufacturer will have a quality assurance program, implemented to maintain Product quality. At a minimum, the Contractor shall ensure that an inspection program which complies with the CSA Z299.4 level to be offered by the manufacturer. .1 Complete DC system must carry a parts and labour warranty for the Warranty Period. .2 Battery bank to be warranted for 10 years (3 years full and 7 year pro-rata). The 10-year warranty to commence from the date of Total Performance of the Work. .1 DC system must be adequately prepared for shipment to protect it against damage during normal road transportation, handling and indoor storage. .2 The Contractor shall ensure that the manufacturer will indicate any special requirements for storage of the equipment for a prolonged period of time at the site, should it be necessary. .1 A suitable metal nameplate to be secured to the charger via screws. At a minimum it is to include: .1 Manufacturer’s name .2 Model number .3 Input voltage .4 Number of phases .5 Input frequency .6 Input current .7 Output current .8 Output voltage .2 A suitable metal nameplate to be secured to the battery bank via screws. At a minimum it is to include: .1 Manufacturer’s name .2 Model number .3 Number of Cells .4 Cell Voltage .5 Battery Capacity (Ah) .6 Battery Voltage .1 Provide four control fuses. Warranty Packaging and Storage Labelling Spare Parts and Special Tools CONTRACT NO T-12-16 Section 16339 BATTERY AND CHARGER SYSTEM DATE: April 2012 Page 7 of 7 2.10 Operation and Maintenance Manuals .1 Comply with Specification Section 01430 – Operation and Maintenance Data. .1 Saft S.A. .2 Approved equal. .1 Install charger and batteries in accordance with the manufacturers recommendations. .2 Provide a dry contact “General Alarm” signal to SCADA for alarm of a failure of either Charger .1 The following requirements are in addition to the requirements listed in Division 1 – General Requirements. .1 The Contractor shall ensure that the manufacturer will perform routine factory tests and inspections on each unit. The Consultant shall witness these tests. .2 .3 The Contractor shall ensure that the manufacturer will provide the Consultant with a minimum of 14 Days notice for tests. .4 All technical assistance and test equipment required to perform these tests to be furnished by the manufacturer. All test instruments must be calibrated and traceable to recognized standards. .5 The Contractor shall ensure that the manufacturer’s quality assurance department will have detailed test procedures available for the Consultant to review. .6 The test and inspection to cover the following: 1. A quantitative check of all features and items specified in the purchase order. 2. Visual inspection of workmanship and finish. 3. Measurement of dimensions. 4. Dielectric strength test. 5. Operational and sequence test. 6. A functional test to verify electrical performance .7 Three (3) sets of test certificates shall be submitted to the Consultant for review and approval before shipment to the Site. 2.11 Approved Manufacturers PART 3. EXECUTION 3.1 3.2 Installation Test and Inspection END OF SECTION CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 1 of 19 DATE: April 2012 PART 1. 1.1 1.2 1.3 1.4 GENERAL General Conditions .1 Refer to all other Divisions of the Specifications, Drawings and the Contract Documents to determine their effect upon the Work of this Section. .2 Refer to Section 16010 – General Electrical Requirements for general electrical requirements related to this Work. .1 Furnish all labour, materials, supervision, equipment and services required to install the equipment specified herein. .2 Commission the equipment specified herein and demonstrate, to the satisfaction of the Region and the Consultant, that the equipment functions as intended in the design and that all connections to control and ancillary equipment are functioning as intended in the design. .1 Section 16016 – Staging and Transition .1 Materials and workmanship shall comply with all applicable codes and standards of the Province of Ontario. .2 Comply with the latest edition of the following statutes, codes and standards, and all amendments thereto. .1 Canadian Standards Association (CSA) 1. CSA C22.2 No. 31 2. CSA C22.2 – 14, “Industrial Control Equipment” 3. CSA C22.1, Canadian Electrical Code, Part I .2 American National Standards Institute (ANSI) 1. ANSI C37.20 2. ANSI C37.09 3. ANSI C 57.13 Instrument Transformers .3 Ontario Electrical Safety Code, 2002 and supplements .4 National Electrical Manufacturers Association (NEMA) 1. NEMA SG-4 2. NEMA SG-5 .5 Electrical Equipment Manufacturers Association of Canada (EEMAC) 1. EEMAC G8.2 2. EEMAC Standard ICS2-322 Scope Related Sections Codes and Standards CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 2 of 19 DATE: April 2012 1.5 1.6 1.7 1.8 1.9 Coordination and Constraints .1 The Contractor must coordinate the medium voltage switchgear and medium voltage MCCs to minimize the overall footprint of the switchgear. The following items are key constraints and coordination issues: .1 Overall switchgear and related hardware/ accessories footprint is not to exceed dimensions shown on the Contract Drawings, however the individual component sizes may vary. .2 Contractor shall provide a metal clad vacuum type or gas insulated vacuum circuit breaker provided it meets the space restriction and fits in the electrical room and otherwise complies with the Specifications. .3 Bus PT’s are included as an integral component of the main switchgear. Bus PT’s shall be fused. .1 Manufacturer of the Equipment: The manufacturer of the equipment must have a satisfactory track record for the proposed equipment as specified in this Contract. The track record must be for equipment of similar size and voltage (2400 V to 4160 V), installed and operated within Canada for a minimum of five years over the last 5 years.. .1 In the event of any contradictions between this Specification and the local electrical codes, the most stringent requirement shall apply. .1 Deviations from this Specification may occur due to special design conditions. Such deviations may be permissible if they are equal to or better than the specified requirements, and are approved by the Consultant. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16345 – 4160 V Medium Voltage Switchgear as indicated in Schedule ‘A’ of the Bid Form. .1 Submit shop drawings of medium voltage switchgear panels and components in accordance with Sections 16010 – Electrical General Requirements and Section 01300 - Submittals, showing the following: Track Record of Performance Conflicting Requirements Deviations from Specifications Measurement and Payment 1.10 Submittals CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 3 of 19 DATE: April 2012 .1 .2 .3 .4 .5 .6 .7 .8 .9 .10 .11 .12 Outline dimensions and assembly details, foundation requirements, weights Dimensions of all openings and doors Door hinge locations, maximum opening angles Floor anchoring method, dimensioned foundation template and proposed core-hole locations Dimensioned position and size of busbars Dimensioned cable entrance and exit locations Dimensioned cable termination and support details Dimensioned lifting details Terminal block arrangements Materials of construction and construction details Bills of material Control schematic and wiring diagrams .2 Review Co-ordination Study as described in Section 16010 – Electrical General Requirements. Submit protective device characteristics data. .3 Submit final record drawings to the Consultant at completion of project. Include changes made during field installation and startup. Enclose one copy of final record wiring diagram in plastic envelope and place in each compartment door pocket. .4 Submit bound and indexed copies of operating and maintenance manuals. Include the following: .1 Complete parts list .2 Spare parts list .3 Installation, operation and maintenance instructions .4 Detailed trouble-shooting procedures and fault correction schedules .5 Final record drawings .6 Certified test results .5 Submit test results. Refer to Section 16031 – Inspection and Testing for details of additional inspections and tests. .6 Refer to data sheets provided in subsection 3.4 for equipment supply .1 Provide manufacturer’s type test certificates, and in accordance with the latest CSA, ANSI, IEEE, NEMA and EEMAC standards. .2 Conduct equipment inspection and factory acceptance testing at manufacturer’s plant. .3 Advise the Consultant in writing, a minimum of ten Working Days prior to carrying out tests. .4 The Consultant reserves the right to observe all factory testing. .5 Perform the following shop tests with the complete assembled switchgear where practical: .1 Standard production tests 1.11 Quality Assurance CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 4 of 19 DATE: April 2012 .2 .3 .4 .5 .6 .7 .8 .9 Demonstration of interchangeability for circuit breakers of equal rating Mechanical and electrical operation of circuit breakers, interlocks, draw-out mechanisms, auxiliary devices, manual devices Functional tests on all components and circuits to confirm conformance to all requirements outlined in this Contract. Polarity and ratio tests on current and potential transformers Power and control circuit wiring continuity Vacuum bottle integrity test High voltage AC withstand test Any additional tests customarily performed by the manufacturer .6 Test the switchgear as one complete assembly. Testing of individual shipping sections only will not be accepted. .7 Prior to shipment, submit to the Consultant four (4) copies of certified final test results. .1 Completely assemble the switchgear line-up (main-tie-main) in the factory prior to factory acceptance testing. .2 Perform only the minimum disassembly required to safely and practically transport the equipment to Site and install equipment in final location. .1 Maintain switchgear assembly in upright position and keep doors locked. .2 Protect door-mounted devices from damage and dust. Block moving parts to prevent damage from vibration. .3 Store switchgear in warm, dry area prior to installation. .1 4160 V, 60 Hz, 3 wire, delta-solidly grounded wye system. .1 Design a failsafe breaker control and interlock system which includes the following requirements: .1 Design shall include a load management scheme, in accordance with the Contract Drawings, which allows for the switchgear to work in auto mode and, upon the failure of any component, allows for the switchgear to operate in manual mode. 1.12 Shop Assembly 1.13 Storage and Handling PART 2. 2.1 2.2 PRODUCTS Supply Characteristics 4160 V Switchgear CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 5 of 19 DATE: April 2012 .2 .3 2.3 Direct hardwired safety interlocks to override manual control commands including lockout 86 relay (refer to Drawing E-02). Automatic tripping of breaker due to downstream cable or equipment fault conditions. Manufactured Units .1 Enclosure .1 As described in subsection 1.5 - Coordination and Constraints, equipment footprint shall not exceed dimensions shown on the Contract Drawings. .2 Switchgear assembly: .1 Arc resistant metal-clad circuit breaker cubicles and auxiliary equipment as shown on the Drawings. .2 Gas insulated vacuum breaker if the metal clad breaker cannot adhere to the footprint shown. .3 Assembly: made up of rigid, formed sheet steel, self supporting, dead front enclosures, EEMAC type as indicated in the Contract Documents, bolted together. Aluminium framed enclosures are not acceptable. .4 Floor channels: continuous, extending over the full length of the assembly complete with all necessary fixing hardware. .5 Front access: 135 degree swing hinged doors with handle opener and gaskets; .6 Rear access: bolted panels with gaskets. .7 Each vertical section shall contain not more than one high voltage switching unit (single tier arrangement). The high voltage switching unit shall be located in the lower half of each vertical section. The upper half shall contain low voltage metering and control equipment and wiring. .8 Circuit breaker compartment: with a horizontal draw-out circuit breaker, type as indicated in the Contract Documents; circuit breaker racking and/or levering mechanism, mechanical interlocks, stationary primary and secondary disconnecting contacts and automatic safety shutters. Provision shall be made for padlocking of the shutter mechanism when the breaker element is removed. Breaker rack in/out indication to be provided. .9 Bus and feeder shutter actuators: operate independently and lockable in the closed position (i.e. while the circuit breaker is in the ‘test’ or ‘withdrawn’ position), but still in the cell. .10 The shutters must be provided with a latch to latch them open. They must be self reset-able when the circuit breaker is racked into the service position .11 Busbar shutters shall be painted signal red and shall be clearly and indelibly labelled "Busbars" in large white CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 6 of 19 DATE: April 2012 .12 .13 .14 .15 .16 .17 .18 .19 .20 .21 letters. Circuit shutters shall be painted lemon colour and shall be labelled "Danger live cables" in large red letters. Circuit breaker guide rails: to ensure positive alignment when racking the circuit breaker into position. Access to the bus work, current transformers and power conductor terminations: from the rear or bottom. Breaker lifting device/truck and all accessories to be provided for the withdrawal and removal of all breaker elements from their respective cells at each site. Gland plates: removable in each section for entry of power and control cables. Furnish non-magnetic gland plates for entry of single conductor power cables. Provide viewing windows at rear of switchgear for thermographic surveys. Potential transformer enclosure: each set in a separate compartment (i.e., two sets of bus PTs per switchgear). Secondary circuits to open before the primary 1. disconnecting contacts part (to prevent arcing); 2. Provision to prevent personnel from coming in contact with the potential transformer primary fuses until after the primary disconnecting devices are separated by a safe distance and automatically grounded. 3. Shutter mechanism to close off access to stubs. 4. PT door to be lockable. Circuit breaker positions: three definite and distinct positions within the enclosure, as follows: 1. The "Operating" (connected, service) position - with the truck fully engaged inside the compartment and primary and secondary contacts connected; 2. The "Test" position - with the truck partially drawn out, primary contacts disconnected, secondary contacts connected but no live contacts exposed (shutters closed); and 3. The "Withdrawn" position - with the truck fully withdrawn, primary and secondary contacts disconnected and compartment fully and safely accessible. Clearly indicate each breaker position. Mechanical interlocks to prevent moving the breaker to or from the connected position with the circuit breaker closed. Dry contact status in control cell indicating whether breaker is in Operating Position or in Test Position or Racked out of cell. Hoisting: removable lifting hooks and/or angles, on each shipping section. Phase bus: high conductivity, hard drawn copper, fully insulated. CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 7 of 19 DATE: April 2012 .22 .23 .24 .25 .26 .27 .28 .2 Bus mounting insulators: track resistant co-ordinated dielectric properties and mechanical strength to withstand full thermal and mechanical stresses developed by maximum available short circuit currents. Bus joints, ends and connections: electrolytically silver plated, fasten with a minimum of two bolts. Insulate with preformed insulating boots, secured with non-conducting screws. Make witness marks on all nut and bolt assemblies. Bus work maximum temperature rise: not to exceed 65 degrees Celsius over an ambient temperature of 40 degrees Celsius. Insulation Class: 105 degrees Celsius Ground bus: 6 mm x 50 mm minimum, extend through the entire length of switchgear, securely fastened to the metal work in each compartment. Furnish compression type, solderless lugs for connecting the ground bus plant grounding conductors at each end. Circuit breaker draw-out mechanism: with a sliding ground contact to connect to the ground bus. Connect all noncurrent-carrying metal parts to the ground bus. Ground balls and insulated boots as provided by A B Chance Company shall be installed at all cable entry points to facilitate easy grounding of equipment for maintenance purposes. Two sets of 3 phase to ground, 3/0 grounding cables to be supplied for each site, for use with supplied ground balls. Metal Clad Circuit Breakers .1 Design: three pole arc resistant vacuum circuit breakers, draw-out type, electrically operated, mechanically and electrically trip-free, motor operated, stored energy closing and rated as indicated in the Contract Documents. .2 The actions of isolation from the power supply and withdrawal of the circuit breaker shall be separate and independent actions. Means shall be provided in the equipment to lock and padlock the circuit breaker in the ‘operating’ or ‘test’ position .3 Isolation (drawing the circuit breaker between operating, test and withdrawn position) shall be achieved by mechanical devices through the closed circuit breaker compartment door. Isolation shall be achieved without the need for tools or special attachments/devices which are not integral to the switchgear other than a specific device which represents an extension of the isolating mechanism (i.e. a racking or winding handle). .4 Operating voltage of circuit breaker operating mechanism shall be of the 125 VDC motor wound spring type. It shall be possible to charge the operating springs with the circuit breaker in either open or closed positions. In normal CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 8 of 19 DATE: April 2012 .5 .6 .7 .8 .9 .10 .11 .12 .13 .14 .15 .16 operation, recharging of the operating springs shall commence immediately and automatically upon completion of the closing operation. Closure while a spring charging operation is in progress shall be prevented, and release of the springs shall not be possible until they are fully charged The operating mechanism shall have a hand-charging amenity and it shall be possible to discharge the operating springs at the Site from a charged condition without difficulty. Manual spring release shall also be provided. The charging spring motor shall be interlocked so that it cannot operate when manual charging is selected. . Interchangeability: circuit breakers of the same type and current rating to be interchangeable, electrically and mechanically, but it shall be impossible to interchange circuit breakers of different current ratings. Neither the circuit breakers nor any other part of the switchgear or supporting structures shall be permanently strained when making or breaking the rated short circuit currents. Each circuit breaker shall be capable of making and breaking short circuit faults in accordance with the ANSI Standards referred to in subsection 1.4 and the requirements of these Specifications. All current carrying equipment shall be capable of withstanding the rated currents for a period of 2 seconds. Test Certificates must be supplied for the breakers. The testing must be conducted on breakers that are identical to the breakers that will be supplied under this Contract. Mechanical tripping features on all the circuit breakers via an emergency button shall be provided. Manual means of operation to be provided for all circuit breakers for maintenance purposes. Operating mechanisms shall be designed so that the circuit breaker is free to open electrically and mechanically. An approved mechanically operated indicator shall be provided to show whether the circuit breaker is open or closed. Stored energy mechanism: means of manually charging from the front of the circuit breaker; mechanical indication to show the status of the stored energy mechanism, automatically discharge before the breaker is withdrawn from the cell. Secondary disconnecting contacts or plug and socket: self aligning for connection of control circuits in the circuit breaker to control units in the circuit breaker cubicle. Additional truck operated and mechanism operated auxiliary contacts: wired to terminal blocks, rated at a minimum 10A at the rated control voltage of 125 V DC. CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 9 of 19 DATE: April 2012 .17 .18 .19 .20 .21 .22 .23 .3 2.4 Operation counter: non-resettable mounted on the face of the breaker. Primary draw-out power disconnecting devices: removable element to consist of a flexibly-mounted, self-aligning assembly of bridging segments, formed so each segment will make high pressure contact with the fixed terminal at one end and with the circuit breaker terminal at the other end. Heavily silver-plate all contact surfaces. Contact wear indicators: easily accessible with the circuit breaker in the withdrawn position. Auxiliary contacts: a minimum of three spare 'A' contacts and three spare 'B' contacts (or six spare convertible “A” or “B” contacts) on each circuit breaker in addition to the contacts required for switchgear operation, controls and those shown on the Contract Drawings. Interlocks must be provided to prevent incorrect operation of switchgear. The operator must be forced into the only safe and logical sequence of operations to actuate switching devices. Interlocking shall be achieved by mechanical means. The following interlock provisions are mandatory for circuit breakers: .1 The withdrawal or engagement of a circuit breaker shall be impossible unless it is in the ‘open’ position. .2 The operation of a circuit breaker shall be impossible unless it is in the ‘operating’ or ‘test’ position. .3 It shall be impossible to close the circuit breaker between service and test position. .4 Switching operations shall be performed with the circuit breaker compartment door closed, .5 The door of the compartment shall be prevented from being opened unless the unit is isolated, .6 Withdrawable units shall be prevented from being withdrawn or from being replaced without being isolated, One Breaker Test station at the Site shall be included, including an ‘umbilical’ cord to allow testing of breaker outside switchgear. Gas Insulated Vacuum Circuit Breaker Electrical Interlocking and Load Management Scheme .1 Provide electrical interlocking between the main and tie breakers in the switchboard to prevent paralleling the incoming feeders in accordance with the control schematic drawings and as follows: .1 Only two of three breakers, in the fully racked in position, can be closed at any one time; and CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 10 of 19 DATE: April 2012 .2 .3 .4 2.5 Automatically trip the tie breaker, should all three breakers, in the fully racked in position, become all closed at the same time. Allow all three breakers to close when one or more of the breakers is in the disconnected or test position. Electrical interlocks shall function so as to prevent the closing operation but not the opening of a circuit breaker. Breaker and Switchboard Controls .1 The control and monitoring shall conform to Section 13010 – Process Control: General Requirements. .2 Each breaker control is to be internally wired to allow the control modes and interlocks and controls to operate as follows: .1 Circuit breakers shall utilize vacuum breaking technology, and shall be arranged for either vertical or horizontal isolation complying with the requirements of ANSI C37. .2 It shall not be possible to render the electrical tripping feature inoperative by any mechanical locking device. .3 It shall be possible to verify full functional operation, indication and closing, tripping and interlock circuit when circuit breaker is in the test (isolated) position. .4 Provide separately fused circuits for the closing and tripping circuits. Provide continuous monitoring of the integrity of the trip coil .5 by mounting the “breaker closed” red pilot lamp in series with the trip coil. Also provide trip coil monitoring by the multifunction relay associated with the breaker. .6 Provide continuous monitoring of the integrity of the tripping power supply circuit for each breaker. .7 A rugged copper bar type grounding device shall be provided on the breaker element to positively ground the breaker frame to the switchgear ground bus in a test and connected position. .3 Current Transformers .1 Provide multi-tap current transformers as shown on the Drawings with a 5A secondary current rating. .2 Provide a zero sequence current transformer with current ratio as recommended in the Coordination Study, refer to Section 16015 - Electrical System Analysis. .3 Rated nominal voltage, class, frequency and basic impulse level shall be not less than the main bus. Mechanical and thermal withstand ratings shall be not less .4 than the circuit breakers. .5 Burden: capable of driving the combined burden of relays, meters, transducers and loads up to a minimum of fifteen (15) times nominal rating without saturating. .6 Accuracy class shall be suitable for protection relaying and Region metering. CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 11 of 19 DATE: April 2012 .7 .8 .9 .10 Provide saturation curves for all current transformers. Clearly and permanently mark the polarity of secondary terminals. Wire the secondary terminals to automatic shorting type terminal blocks mounted in the cubicle. Provide auxiliary current transformers as required. .4 Potential Transformers .1 Primary and secondary voltage ratings of 4160/120 V unless otherwise indicated on the Contract Drawings. Insulation class shall be equal to the main bus. .2 .3 Provide properly rated fuses for primary winding protection. .4 Provide properly rated fuses for ungrounded secondary circuit protection. Burden: capable of supplying 1.5 times the combined .5 burden of all known connected relays, meters, transducers and loads. .6 Accuracy class: suitable for the specific application. .7 Wire secondary leads to link type terminal blocks mounted in the cubicle. .8 Potential transformers used for protective and metering devices shall not supply any other loads. .9 Clearly and permanently mark the high voltage and low voltage terminals. .5 Protective Relays, Instruments and Meters .1 All protective relays for medium voltage circuit breakers shall be General Electric Company, Multilin SR750 relays. Relay power supply from plant 125V DC source as shown on the Contract Drawings. .2 Fully test relays during commissioning. .3 Provide door-mounted flexitest blocks for all metering, instrumentation and relaying circuits. Acceptable manufacturers: .4 1. General Electric Company, Multilin .5 Mount protective relays, instruments and meters on the front door. .6 Test blocks: door mounted for all metering, instrumentation and relaying circuits. Auxiliary and time delay relays: dust-proof, plug-in type, .7 mounted in the cubicle. .8 Auxiliary tripping relays: lock-out type, front door mounted reset handles. .9 Auxiliary relays: with no less than four normally open and four normally closed contacts. .10 Lock-out relays: with a minimum of 16 contacts. .11 Time delay relays: easily adjustable, with a minimum of two normally open and two normally closed contacts. .12 Mount door mounted devices between 900 mm and1700 mm above floor where possible. Where not possible, request written approval from the Consultant. CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 12 of 19 DATE: April 2012 .6 Control and Selector Switches .1 Circuit breaker local control switches shall have the following characteristics: 1. Three position (Close-Neutral-Trip); 2. Pistol grip handle, spring loaded to return to the neutral position; 3. Mechanical position indicator showing position of last manual operation; 4. Heavy duty type 5. Rated 600 V, 20 A, double-series-connected, silverplated contacts enclosed in an easily removable dust tight cover 6. With a minimum of one (1) spare NO/NC contacts on each position for remote monitoring. .2 Mounting height: 900 mm to 1700 mm from floor. .7 Indicating Lights .1 Indicating lights: long life, 125 V DC, Push-to-test clustered LED type lamps with series resistors. .2 Coloured lens caps: heat resistant, interchangeable and easily removable from the front. Red for circuit breaker closed; Green for circuit breaker open. .3 Lamps replacement: easily replaceable from the front, without disconnecting the power supply. .4 Mounting height: 900 mm to 1700 mm from floor. .8 Control Power .1 Breaker trip, closing and auxiliary circuits: supplied from a single external 125 V DC supply. .2 Control power disconnecting means: two pole, non-fusible disconnect switch in each circuit breaker compartment for isolating the tripping, closing and auxiliary circuit supplies. .3 Provide a 125V DC supply to each Multilin relay, as shown on the Contract Drawings. .4 Control power circuit protection: High Rupturing Capacity (HRC) fuses rated appropriately. .5 Fuse holders suitable for cartridge type HRC fuses rated 250 V, 30 A. .6 Trip circuit disconnecting means: disconnect switch for each breaker must be suitably rated as indicated in the Contract Drawings and calibrated for trip settings in accordance with the short circuit and coordination study. Trip circuit protection: with a suitably sized HRC fuse. Trip circuit: separate from the closing and auxiliary circuits. .7 Trip circuit monitoring relay: for each breaker, with two normally closed and two normally open contacts which may be used for remote annunciation of loss of breaker tripping power supply. .9 Control and Instrumentation Wiring CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 13 of 19 DATE: April 2012 .1 .2 .3 .4 .5 .6 .7 .8 .9 .10 Control and instrumentation wiring: no smaller than #14 AWG, 600 V, multi-stranded, extra flexible, copper, heat and flame retardant insulation, single conductor type. Current transformer wiring: a minimum of #10 AWG. Wiring termination: in terminal blocks GE MULTILIN 515. Wire identification: At both ends with Oil-resistant, Type Z markers by Wieland Electric Inc. at conductor ends. Adhesive cloth or Mylar tapes not acceptable. Terminal blocks: rail mounted, modular, 600 V rated, minimum 25 A, with grounded metal barriers separating voltage levels, tubular clamp type, clearly identify. Current transformer terminal blocks: automatically short circuiting link type. Separation of terminals and wiring: by class of signal AC, DC, voltage level. Spare terminal blocks: 30 percent in each cubicle. Brace, support and bundle all wiring to present a neat appearance. Cell interconnecting wiring: terminate on terminal blocks; clearly mark and tag wires to indicate where to terminate. Shipping split interconnecting wiring: pre-cut to length and terminate with compression type lugs. Cable supports: for control cables and wiring, including external cables and wiring. .10 External Connections .1 Cable termination: cable and terminating assembly supports; compression type, minimum of two bolt holes compression lugs sized to match the cable size as indicated on the Contract Drawings. Terminating pads: with standard NEMA hole patterns. .2 Stress relief cones: sufficient space for fitting and making off. .3 Insulating materials: sufficient to insulate the exposed cable ends and bus after completing the connections, insulation level equal to the insulation level of the main bus. .11 Surge Arresters .1 Surge arresters: To be installed on the line side of each of the new main breakers. Surge arrester to be sized for a 4160 V solidly grounded system. .12 Nameplates and Markings .1 Refer to Specification 16010 – Electrical General Requirements for all physical requirements for all labels, nameplates and warning signs. .2 Nameplates: to identify each compartment equipment and components on both the front and rear of the switchgear assembly. CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 14 of 19 DATE: April 2012 .3 .4 2.6 Phase bus identification: in the termination compartment with the letters A, B, C and/or colour coding Red, Black, Blue. Clearly and permanently mark automatic shutters as follows: 1. For incoming circuit breaker cubicles: Incoming, Bus. 2. For feeder circuit breaker cubicles: Bus, Load. 3. For tie breaker cubicle: Bus 0100, Bus 0200. 4. Letters: a minimum of 25 mm high. .13 Mimic Bus .1 Through-out the entire length of the switchgear, both front and back, provide a lamacoid representation of the switchgear major components including the 4160 V bus, main and tie breakers, termination and feeder points, CT’s, PT’s, and relays, and any other major components. .2 Mimic bus to be red, fastened with SS screws. .14 Finish .1 Painted surfaces: to be ground smooth, thoroughly cleaned, etched in a phosphate solution and coated with a rust inhibiting primer. Interior and exterior finish as indicated on the Contract Documents. .2 Circuit breaker painted surfaces: same colour as the switchgear external finish. .3 Touch up paint: one litre of original paint of each colour. .15 Accessories .1 Accessories: as indicated in the Contract Drawings or as required for complete functional system in accordance with the scope of the Contract. .1 The Contractor is responsible for the supply of all parts needed during commissioning. .2 Provide an itemized list of all recommended spare parts, and unit prices, required for routine and minor overhauls for two (2) years of normal operation. Each piece of equipment shall have part number or designation. .3 Use identical equipment and components where practical to permit inter-changeability of parts, minimize spare parts inventory, and to simplify maintenance. .4 Where two or more items of equipment perform similar functions, use the same make and, where practical, the same model number and size. .5 Supply two sets of all special tools required for commissioning and servicing of the equipment. Spare Parts and Tools CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 15 of 19 DATE: April 2012 PART 3. 3.1 3.2 EXECUTION General .1 Install embedded floor channels as required to align them on the floor. .2 Set and secure cubicles in place, rigid, plumb and square on floor channels. .3 Make ground connections. .4 Interconnect cubicles with bus connectors supplied by manufacturer, and with cable bus, as indicated in the Contract Documents. .5 Connect inter-cubicle wiring. .6 Make power supply connections to incoming terminals after performing functional tests requiring closing of incoming breaker. .7 Check factory made connections for mechanical security and electrical continuity. .8 Ensure correct phasing prior to attempting parallel operation. .9 Install and connect external control, metering and instrumentation cables. .10 Ensure controls are fully functional as described by the supplier of the switchgear system, including protective devices, synchronisation controls, automatic and manual operation. .11 Thoroughly clean interior and exterior. .12 Connect load side terminals to feeders as indicated in the Contract Documents. .1 Prior to energization of switchgear, perform the following checks: .1 Measure insulation resistance on bus, phase-to-phase and phase-to-ground, with breakers in normal operating position with main contacts open. Disconnect lightning arresters and withdraw potential transformers when carrying out these tests. .2 Measure control circuit insulation resistance to ground. Do not carry out insulation resistance test on circuits incorporating solid state devices. .3 Allow for required support from manufacturer during site testing. .4 Employ services of manufacturer or qualified independent testing agency to inspect, program and calibrate protection relays and sensors, refer to Section 16031 – Inspection and Testing for additional inspections and tests. Verify settings in accordance with manufacturer's instructions and setting data provided by Coordination Study. 1. Ensure correct protection devices installed in accordance with the co-ordination study, including Testing CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 16 of 19 DATE: April 2012 .5 .6 .7 .8 .9 .10 .11 3.3 current transformer ratings, fuse ratings, and protective device settings. 2. Ensure all “settable” protective and control devices are fully programmed, and properly set in accordance with the coordination study. For any parameters not included as part of the coordination study, ensure units are programmed in accordance with the manufacture’rs recommendations and load requirements (for example: this may include protection relays monitoring parameters). All such settings are to be submitted to the Consultant prior to equipment energization for review and approval. It is the responsibility of the Contractor to ensure all settings and programmed values are properly and completely set in all devices. Proper coordination with equipment supplier will ensure that no parameters are missed. Inspect current transformers, potential transformers and relays for correct polarity. Ensure shorting jumpers installed on unused CT circuits. Carry out functional tests and checks simulating operating and fault conditions. Check mechanical and electrical interlocks and safety devices. Check ground connection are made. Energize incoming circuit breaker(s). Ensure fully operational system. Refer to Section 16031 – Inspection and Testing for all additional tests and requirements. Training .1 As described in Section 01820 – Demonstration and Training. CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 17 of 19 DATE: April 2012 3.4 Switchgear Data Sheets .1 Enclosure Data: EQUIPMENT NUMBER: n/a DESCRIPTION SERVICE DESCRIPTION: REQ'D DESCRIPTION REQ'D CONTROL VOLTAGE AMBIENT CONDITIONS Location Closing Circuit 125 VDC Tripping Circuit 125 VDC Trip Healthy Indication Yes Indoor Ambient Design Temperature 40ºC ELECTRICAL DESIGN CONDITIONS Nominal Voltage Class Number of Phases 3 Exterior Paint Colour Frequency Maximum Design Fault Level (Symmetrical) Main Bus Rating 250 MVA SURGE ARRESTERS Yes 40kA At incoming of each main breaker. 2000 A System Grounding Type [Solid/Low Resistance/High Resistance] Indoor/Outdoor Grey (ANSI61) 60 Hz Nominal MVA Class (at 5 kV) Enclosure: 4160 V FINISH EEMAC Type Solid 1A POWER CONDUCTOR TERMINATIONS Indoor Type: Incomers Feeders Entry Cable bus duct Bus Top CONTROL CONDUCTOR TERMINATIONS Type Entry REMARKS: Refer to Drawings for more specific requirements. Bottom CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR Page 18 of 19 DATE: April 2012 .2 4160 V Main Breakers EQUIPMENT NUMBER: ELS-SWG-XXXX DESCRIPTION SERVICE DESCRIPTION: REQ'D DESCRIPTION REQ'D CIRCUIT BREAKER Type: Vacuum/Vacuum SF6 Vacuum ACCESSORIES Rating 2000 A levering/racking device Yes Voltage Class 4160 V hoisting device/mobile lifting device Yes MVA Class (At 4160V) Maximum Available Fault Level (Symmetrical) 250 MVA extension rails 40kA removable ramp Yes Yes Electrically Operated Yes ground and test device Yes Draw Out Yes test jumpers for testing breakers outside switchgear Yes Control Voltage 125 V dc test cabinet test plug to match current test block Yes Yes Manual Close (Yes, Blocked – tool accessible) Yes test plug to match potential test block Yes Manual Open Yes test plugs suitable for integral relay test blocks Yes FEEDER MANAGEMENT RELAY (FMR), GE MULTILIN SR750 FMR provided by [Owner, Contractor] FMR Panel mounting case required special tools and hardware required for installation, maintenance, operation, inspection and testing Yes anti-condensation heaters Yes Contractor motor anti-condensation heater controls Yes REMARKS: Refer to Drawings for more specific requirements. Yes CONTRACT NO. T-12-16 Section 16345 4160 V MEDIUM VOLTAGE SWITCHGEAR DATE: April 2012 Page 19 of 19 .3 4160V Tie Breakers: EQUIPMENT NUMBER: ELS-SWG-XXXX DESCRIPTION SERVICE DESCRIPTION: REQ'D DESCRIPTION REQ'D CIRCUIT BREAKER Type: Vacuum/Vacuum SF6 Vacuum ACCESSORIES Rating 2000 A levering/racking device Yes Voltage Class 4160 V hoisting device/mobile lifting device Yes MVA Class (At 4160V) Maximum Available Fault Level (Symmetrical) 250 MVA extension rails 40kA removable ramp Yes Yes Electrically Operated Yes ground and test device Yes Draw Out Yes test jumpers for testing breakers outside switchgear Yes Control Voltage 125 V dc test cabinet test plug to match current test block Yes Yes Manual Close (Yes, Blocked – tool accessible) Yes test plug to match potential test block Yes Manual Open Yes test plugs suitable for integral relay test blocks Yes special tools and hardware required for installation, maintenance, operation, inspection and testing Yes FEEDER PROTECTION RELAY (FMR), GE MULTILIN SR750 Not applicable anti-condensation heaters Yes FMR provided by [Owner, Contractor] Not applicable motor anti-condensation heater controls Yes FMR Panel mounting case required No REMARKS: Refer to Drawings for more specific requirements. END OF SECTION CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 1 of 18 DATE: April 2012 PART 1. GENERAL 1.1 1.2 1.3 Scope of Work .1 Furnish and install solid state starter(s) as shown on the Contract Drawings and as specified herein, including all required appurtenances. The solid state starter(s) shall be microprocessor controlled, suitable for use with three phase standard induction motors rated 7,200 VAC or less. The starter(s) shall provide Closed Loop Current Control, Sensorless Linear True Torque Control, and KW Ramp Control for smooth and stepless motor acceleration and deceleration. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16346 – Medium Voltage Solid State Starters as indicated in Schedule ‘A’ of the Bid Form. .1 The solid state starter(s) shall be the domestic product of a manufacturer incorporated, located, and manufacturing the products in Canada. They shall have produced medium voltage solid state starters of the same type and size for a minimum of 10 years consecutively. Brand labeled or third party integrator supplied starters are not acceptable. .2 Starter manufacturer shall provide a reference list of not less than 20 installations within the last 10 years with contact names and phone numbers for verification, as well as a general installation list of over 200 installed units in operation successfully for more than 5 years. Additionally, an application and industry specific user list shall be provided. Successful experience in the specific voltage class and horsepower range, specified in this Contract and applications in water and wastewater facilities must be demonstrated. .3 A Reduced Voltage Start Analysis must be provided to simulate and illustrate the coordination between the power distribution system, solid state starter(s), and the motor. The analysis shall indicate the optimum motor current start profile, acceleration times, and the equivalent locked rotor heating time of the motor under specific reduced voltage start profiles. The analysis shall be provided in PDF format. The following graphs must be produced: .1 Motor Current and Torque verses Speed .2 Load Torque (as a percentage of rated motor torque) verses Speed .3 Developed Torque, Load Torque and Accelerating Torque verses Speed Measurement and Payment Quality Assurance CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 2 of 18 DATE: April 2012 .4 1.4 Motor Current and Speed verses Time .4 The analysis stipulated above, must be included in the submittal process and final as built documentation. This data will be used at time of commissioning so accuracy is critical. The submittal shall be subject to review and approval by the Consultant.. .5 For safety, reliability, and continuity of warranty, any modifications, alterations, etc., required to conform to the requirements of this Specification shall be performed by the starter manufacturer only. Distributor or other third party modifications to a manufacturer’s standard product are specifically prohibited. .6 Solid state starter manufacturer shall supply proof of conformance for Electro-Magnetic Compatibility upon request. Field labeling is not acceptable. .7 The solid state starter shall be domestically designed, manufactured and tested to conform, where applicable, to the following industry standards and specifications: .1 Canadian Standards Association (CSA) .2 Electrical Equipment Manufacturers Association of Canada (EEMAC) .3 Institute of Electrical and Electronics Engineers (IEEE) .4 National Electrical Manufacturers Association (NEMA) .1 NEMA ICS2 .5 Underwriters Laboratories Canada (ULC) .1 ULC 347 .6 American National Standards Institute (ANSI) .8 Environmental Requirements: .1 Temperature: 0 degrees Celsius to 40 degrees Celsius. .2 Relative Humidity: Up to 95 percent, non-condensing. .3 Designed, tested and certified to meet Uniform Building Code on non-building structures, for Zone 1, 2, 3, and 4 requirements. Specifically, UBC Zone 4 (Earth Quake) Seismic Design Response Spectra Analysis. Altitude of up to 1,000 m. For altitude greater than 1,000 m, refer to manufacturers de-rating formula. .1 Submittals shall be furnished in accordance with Section 01300 Submittals. .2 Provide the following: .1 Elementary wiring and interconnection diagrams in accordance with NEMA Industrial Control and Systems (ICS) standards. .2 Size, type, and rating of all system components including the interrupting, withstand, and continuous current rating of: Bus Bars .1 Submittals CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 3 of 18 DATE: April 2012 .3 .4 .5 .6 .7 .8 1.5 .2 Starter Units .3 Incoming Line Units Enclosure frontal elevation and dimension drawings. Internal component layout diagrams. Available conduit entry and exit locations. Manufacturer’s Product data sheets. UL 347 certification file number. CE declaration of conformance (for Electromagnetic Compatibility (EMC)). Delivery, Storage and Handling .1 Handling and shipment of the equipment shall be in such a manner to prevent internal component damage, breakage, and/or denting and scoring of the enclosure finish. .2 Equipment shall be stored indoors in a clean, dry environment. Ambient storage temperature shall be –40 degrees Celsius to 70 degrees Celsius and humidity 20 percent to 95 percent noncondensating. Energize space heaters if furnished. .1 Benshaw Canada Controls Inc. or an approved equal, provided that the solid state motor starters being supplied are the end product; designed, engineered, manufactured and packaged by the original solid state starter manufacturer. Brand labeled solid state motor starters, packaged and supplied by a manufacturer that is not the original solid state motor starter manufacturer, is not acceptable. .2 All “named” Manufacturers are obligated to meet the detailed requirements of this Specification. The Consultant will be the sole determiner of the acceptability of a proposed exception. In no case will adjustments to the Contract Price be allowed later for conformance to the Specifications. .1 At a minimum, the starter(s) shall conform to the following requirements: .1 Size: 750 kW .2 Minimum Overload 500 percent of Starter FLA for 30 seconds .3 Rating: 115 percent continuous .4 PIV Ratings, 4,800 VAC: 12 KV .5 Rated Short Circuit: 350 MVA at 5KV .6 Insulation Test: 25 KVDC .7 Basic Impulse Load Level: 45 KV BIL Standard, 60KV BIL Optional PART 2. PRODUCTS 2.1 2.2 Manufacturers Equipment Design Criteria CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 4 of 18 DATE: April 2012 .8 .9 .10 .11 Transient Voltage Protection: Under Voltage Protection: .12 Control Input: .13 Fault level as a Fused (E2) controller: Starts Per Hour: Min Time Between Restarts: Audible Noise: .14 .15 .16 .17 2.3 Overall Efficiency w/o Bypass: Overall Efficiency with Bypass: SCR Firing Technique Basic Motor Control Algorithm Average 99.78 percent 99.9 percent Fiber Optic Continuous Hard Gate Drive dv/dt circuits / phase 80 percent Pickup 60 percent Dropout 120 VAC or dry contact, 2/3 wire NEMA/EEMAC 50KA SYM Maximum of 5 Not less than 12 minutes Not to exceed 60dbA @ 1 metre at any time True torque control and current ramp control Enclosure Construction .1 Construct to comply with the requirements of NEMA Part ICS 2324 as Class E2 controller. .2 Basic structure shall be welded type construction utilizing minimum 11 GA sheet metal. .1 Doors shall be minimum 12 GA sheet metal, pan type with flanges formed to provide sturdy, rigid structure. .2 Provide electrical and/or mechanical door interlocks to prevent doors from being opened with power applied. .3 Doors shall be hinged to allow 90 degree swing. .4 Total structure height shall not exceed 2.3 m (92.5 inches). .3 The solid state starter(s) enclosure shall be indoor, sealed, nonventilated NEMA 12, or NEMA 3R. .1 The starter(s) and any required accessories or auxiliary items shall fit within the space shown on the Drawings. Any costs associated with furnishing equipment which exceeds the available space shall be borne by the Contractor. Typical allowable enclosure dimensions are 36 Width x 30 Diameter x 92.5 Height (inches) for 2,200 kW, 5 KV and below; each starter. .2 Provide removable lifting provisions. .3 The starter cabinet shall contain the following: .1 Main load break and fault make isolating switch. .2 Vacuum inline and bypass contactors. .3 Auxiliary metering and control devices as shown on the Contract Drawings. CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 5 of 18 DATE: April 2012 .4 .4 Low voltage control panel. .1 Metal parts to be given thorough rust resistant treatment. Primer shall be Sherwin-Williams Canada Inc. recoatable epoxy primer B-67. Finish shall be Sherwin-Williams Canada Inc high solid polyurethane polane T plus. Colour shall be ANSI 61. Finish: .2 .3 .4 2.4 2.5 Wiring .1 Complete with internal power and control wires including terminations for external connections. Phase sequencing shall have proper identification. Control wire shall be #14AWG minimum with termination markings. .2 The Contractor shall allow for a minimum of 350 mm of space for the installation of Stress Cones during wiring of the starter. Medium Voltage Combination Starter .1 Main Isolation Switch: .1 Externally operable, ganged 3 pole load break, fault make unit. .2 The switch shall interrupt no-load current of control transformer supplied in controller. .3 In off position, the switch shall ground medium voltage power components, to discharge hazardous stored energy, to provide safer operation and maintenance. .2 Operational Features: .1 One N.O. and one N.C. auxiliary contact as standard. .2 Disconnect Switch will remain connected to external operating handle at all times, fully interlocked with inline contactor. .3 Must be capable of being padlocked in open position with up to three locks. .4 Mechanically and/or electrical interlocked to prevent opening of medium voltage door when isolating switch is in the closed position and prevent closing of the isolating switch when medium voltage door of starter is open. .5 Removes power to coil of inline and bypass contactor before removing line power during manual operation of the disconnect switch. .3 Required Ratings: Rating Description Rated interrupting current, 400 A Load RMS Break Rated interrupting current, 400 Amp Current 600 A Load Break 600 Amp 1200 A Load Break 1200 Amp CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 6 of 18 DATE: April 2012 RMS Continuous current, RMS Impulse withstand BIL Momentary current, RMS (asymmetrical ) Short-time current RMS Fault closing current with Current Limiting Fuses 400 Amp 600 Amp 45KV Standard, 60KV Optional. 22.5 KA 40 KA (asymmetrical) (asymmetrical) 14 KA, (2 sec.) 25 KA, (2 sec.) 22.5 KA 40 KA (symmetrical) (symmetrical) 1200 Amp 61 KA (asymmetrical) 38 KA, (2 sec.) 61 KA (symmetrical) .4 Power Fuses & Holders: .1 Current limiting type rated 50 KAIC symmetrical. .2 Fuse size shall be manufacturer’s standard. .3 Fuses shall be vertically mounted in the enclosure for ease of inspection and removal without special tools. .4 Provide blown fuse indication. .5 Power fuse holders shall be clip-in style, part of starter assembly. .6 Fuse clips shall be designed to accept current limiting fuses for NEMA Class E2 application .5 SCR Stacks: .1 Arranged horizontally for proper heat management. .2 Heat sinks sized for specified Starts Per Hour without requiring auxiliary cabinet cooling fans. .6 SCR Gating: .1 Provide Fiber Optic Continuous Hard Gate Drive Signals and Fiber Optic Cable to SCR stacks for safe isolation of control and power circuits and precision control of SCRs. .7 An inline (main) contactor and a bypass contactor shall be provided. .1 Vacuum break type: Fixed mounted style .2 Current rating: Manufacturer standard for horsepower rating .3 Voltage rating: 7,200 VAC minimum .4 The main and/or bypass contactor shall be sequenced by the starter manufacturer for proper operation of the solid state starter. .5 The bypass contactor shall bypass the SCRs after starting and while the starter is in the run (full voltage) mode. A standard option must be available for Dual Redundant.6 Emergency Bypass Starting. .8 Line Reactors (Optional): .1 Line reactor(s) shall be supplied with the starter(s) if the power source is 20 MVA or greater, or the motor leads exceed 300 m in length. Line reactor(s) shall be provided loose in a separate enclosure for field mounting by Contractor, or mounted and wired by the starter manufacturer within the starter enclosure. CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 7 of 18 DATE: April 2012 .2 2.6 Adequate length of 5 KV rated cable, power cable lugs and associated mounting hardware shall be supplied by the starter manufacturer for use in connecting the line reactor. Submittal Drawings shall show the wiring of the line reactor as reference for the installer. .9 Power Factor Correction .1 The starter must be furnished to provide connections to power factor capacitors once motor is up to speed. If external power factor capacitors are used, starter must include a 400 AMP vacuum contactor and one per phase, 6 inch coils of rated power wire. If power factor capacitors are internal, starter must provide a 400 amp vacuum contactor, one 6 inch coil of rated power wire per phase and power factor correction capacitors. Internal power factor correction capacitors must correct power factor to .95 or greater. .2 Power factor correction capacitors must be fuse protected. Optional protection may be over current protection, or over / under current, ground fault current and over voltage. .10 Ground Bus: .1 A continuous copper ground bus shall be provided along the entire length of the controller line up. The ground bus shall be ¼” x 1” or ¼” x 2” (6.4 x 51mm) bare or plated copper. .11 Ground Ball: .1 Each controller shall be equipped with a Grounding Ball on the ground bus, as well as two per phase. Grounding balls on the phases must be positioned on the load terminals as well as the primary side of the short circuit fuse. Grounding balls must be capable of a short circuit withstand rating of 30 KA for 30 cycles and 43 KA for 15 Cycles. .1 Control Power Transformer .1 Provide an internal 120 VAC step down transformer, mounted separately in the medium voltage power section, 1,000 VA minimum with 500 VA for miscellaneous use. .2 Supply two fuses on primary and one fuse on secondary side with one leg grounded. Disconnect primary of control transformer from power .3 supply with isolating switch (if supplied) in open position. .4 The Control Power Transformer shall also be sized to power the motor space heater, if applicable. The motor space heater is rated 500 Watts, 120 V. An auxiliary contact shall activate and deactivate the motor space heater. Control Hardware CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 8 of 18 DATE: April 2012 2.7 .2 Control Wiring: Control wire shall be #14AWG, 600 V, stranded, minimum with termination markings and continuously labeled over its entire length for ease of identification. .3 Terminal Strips: Rated for 600 V, suitable for contactor termination of up to #10AWG wire. .4 Provide push buttons, pilot lights, and control relays, heavy duty, rated to 600 V. .5 Low Voltage Compartment: .1 Locate low voltage section behind separate door and physically isolated from medium voltage section. Door to permit access to control logic without exposure to .2 medium voltages. .3 Customer interlocking and control as well as metering, relays, and pilot devices shall be located in this section. Optically isolate main control PC card located in low .4 voltage section from medium voltage Gate Driver cards on power poles. .5 Controller shall include 120 VAC test capability to power and adjust microprocessor control when isolating switch is in open position, with the following features: .1 Test circuit shall consist of receptacle and plug mounted in low voltage compartment and accessible only when low voltage door is open. .2 In test position, plug may be inserted into the provided receptacle and connected to external 120V source of power. The above features shall isolate control transformer .3 and prevent energizing control transformer secondary from test voltage source. Solid State Starter Logic Control .1 Starter(s) shall be fully microprocessor controlled and operated. At a minimum, the logic control shall include the following: .1 Default motor starting control algorithm must be one of the following: .1 Closed Loop Current Control providing a linear, squared or “S” curve increase in current from the initial current setting to the maximum setting .2 TruTorque Control for precise regulation of motor and load applied torque Power Control Acceleration controlling the power .3 (kW) drawn from the power source .4 Open Loop Voltage Ramp providing a linear increase in voltage from the initial voltage setting to the maximum setting .5 Tachometer Feedback Ramp providing a linear ramp of motor speed CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 9 of 18 DATE: April 2012 .6 .2 .3 .4 .5 Dual Acceleration Ramp profiles for selecting any two of the above starting algorithms .7 Cyclo Speed Control to run the motor at 1 percent to 40 percent rated speed .8 Auto Start Control allowing the starter to automatically start if the start signal is high when the control card is powered up and/or high after a fault reset Default motor deceleration control algorithm must be one of the following: .1 Coast deceleration allowing the motor and load to coast to a stop Closed Loop Current Control providing a linear, .2 squared or “S” curve decrease in current .3 Voltage deceleration control using an open loop voltage ramp, ramping the voltage down to decelerate the motor .4 TruTorque Control for precise regulation of motor and load applied torque Standard Duty or Heavy Duty DC Injection .5 Breaking for fast deceleration of motor speed .6 Tachometer Feedback Ramp providing a linear ramp of motor speed Embedded Modbus RS485 for communications purposes as published by the Telecommunication Industry Association (TIA) Optional communications ports Profibus DP, Ethernet/Modbus TCP, Devicenet, LonWork Provide additional motor control functions: .1 Motor winding heater control supplying a low current to heat motor windings .2 Energy Saver function which reduces energy consumption of motor while running .2 Provide a door mounted Display & User Interface Module with the following functions: Backlit LCD- 2 Lines, 16 Characters .1 .2 Tactile Feedback Buttons .3 Pass Code Protection .4 Built in Start/Stop Pushbuttons .5 Status Indication via LCD Display and LED’s .6 Scrolling Menu/Parameters .7 Discrete Enter Command Button .8 Meter Mode Display .3 Power Outage Ride Through: .1 The starter shall be furnished with the ability to ride through short-term power losses of up to 3 seconds duration without shutdown and/or dropout of internal control logic. An uninterruptible power supply is required. CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 10 of 18 DATE: April 2012 2.8 .4 Built In Self Test (Standard BIST): .1 The starter must contain a built in self test (BIST) feature that has the capability to perform a test sequence to ensure it is operating properly while isolating test personnel from high voltages. .2 BIST must provide proper interlocking to ensure that the test can be done only when not in service. .3 BIST must operate the vacuum contactors one time each to verify proper operation. It must alarm through the integral LCD display if the sequence fails. .4 BIST must verify SCR gate firing of all SCRs within the starter(s) and offer the ability to measure the gate voltage with a DC voltmeter or oscilloscope. .5 BIST must provide control power to all auxiliary devices to allow for verification of proper operation of each of these devices. .5 Programmable Analog Outputs: The analog output function shall be configured to one of the available output function selections and output scaling shown below. The analog output is updated every 25 msec. .1 Off .2 0-200 percent Current .3 0-800 percent Current .4 0-150 percent Voltage .5 0-150 percent Overload .6 0-10 kW .7 0-100 kW .8 0-1 MW .9 0-10 MW .10 0-100 percent AI .11 0-100 percent Firing .12 Calibration .1 Provide the following Starter Diagnostic Functions: .1 Alpha/Numeric Fault Display .2 Revolving 99 Most Recent Events .3 Start/Stop Recorder .4 Date & Time Stamped Events .5 Motor Thermal % Capacity Display .6 Closed Loop Motor Stall Detection .7 Open Loop Motor Stall Detection .8 Open Gate Detection .9 Starter Status Indication .10 Pre-Start: Pending Fault Indication .11 Pre-Start: Phase Rotation Indication .12 Control Board Built in Self Tests .13 Starter/System Level Built in Self Tests Starter Protection & Monitoring CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 11 of 18 DATE: April 2012 .14 .15 .16 .17 .18 .19 .2 Self Check Parameter Set-Up LED Indication SCR Status Full Screen Meter Mode 9 Event Fault Log Zero Sequence or Residual Ground Fault Detection 10 year Lithium Provide the following Metering Functions: .1 Accuracy The solid state starter shall be capable of measuring the following parameters within the accuracies of the measurements as noted below: .1 CT Inputs: True RMS, Sampling @ 1.562kHz .2 Line Voltage Inputs: True RMS .3 Current: 0-40,000 Amps 3 percent .4 Voltage: 0-15000 Volts 3 percent .5 Watts: 0-9,999 MW 5 percent .6 Volts-Amps: 0-9,999 MVA 5 percent .7 Vars: 0-9,999 Mvar 5 percent .8 Watt-Hours: 0-10,000 MWh 5 percent .9 PF: -0.01 to +0.01 (Lag & Lead) 5 percent .10 0.1 Hz Line Frequency: 23-72 Hz .11 Residual Ground Fault: 5-100% FLA 5 percent .12 Run Time: 3 seconds per 24 hour period .13 Analog Input: Accuracy 3 percent of full scale .14 Analog Output: Accuracy 2 percent of full scale .15 Zero Sequence CT 3 percent .2 Metering Functions: The solid state starter shall be capable of displaying the following metering functions: .1 Status .2 Average Current .3 Line 1 Current (Energy) .4 Line 2 Current .5 Line 3 Current Current Imbalance Level .6 .7 Residual Ground Fault Current .8 Average Voltage .9 L1-L2 Volts .10 L2-L3 Volts .11 L3-L1 Volts .12 Overload .13 Power Factor .14 Watts (Power) (Optional) .15 Zero Sequence GF .16 Volt Amps .17 VARS .18 kW Hours (Energy) .19 MW Hours .20 Phase Order CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 12 of 18 DATE: April 2012 .21 .22 .23 .24 .25 .26 .27 .28 .29 .30 .31 .32 .3 Line Frequency Analog Input Analog Output Run Days Run Hours Starts TruTorque % Power % Maximum Phase Current RTD 1-16 (Optional) Peak Accel Current Last Start Time Provide the following programmable Relay Outputs: .1 General Fault Relay .1 No fault: .2 UTS Time Limit Expired .3 Motor Thermal Overload Trip .4 Jog Time Limit Expired .5 Phase Rotation Error, not ABC .6 Phase Rotation Error, not CBA .7 Low Line Frequency .8 High Line Frequency .9 Input power not three phase . .10 Stack Protection Fault (stack thermal overload) .11 Bypass Contactor Fault .12 Control Power Low .13 Current Sensor Offset Error .14 External Fault on DI 1 Input .15 External Fault on DI 2 Input External Fault on DI 3 Input .16 External Fault on DI 4 Input .17 External Fault on DI 5 Input .18 External Fault on DI 6 Input .19 Modbus Timeout Fault .20 CPU Error – SW Watchdog CPU Error - Program EPROM Checksum Fault .21 .22 CPU Error – Parameter EEPROM Checksum Fault .23 Low Line L1-L2 .24 Low Line L2-L3 .25 Low Line L3-L1 .26 High Line L1-L2 .27 High Line L2-L3 .28 High Line L3-L1 .29 Phase Loss .30 No Line .31 I.O.C . .32 Overcurrent .33 Undercurrent CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 13 of 18 DATE: April 2012 .2 .3 2.9 .34 Current Imbalance .35 Ground Fault .36 No Current at Run .37 Shorted / Open SCR .38 Current at Stop .39 CPU Error–SW fault .40 Analog Input #1 Level Fault Trip(local) Optional Programmable Relay Outputs .1 OFF .2 Fault (fail safe) .3 Fault (Non Fail Safe .4 Running .5 Up to Speed .6 Alarm .7 Ready .8 Locked Out .9 Overcurrent .10 Undercurrent .11 Overload Alarm .12 Cool Fan Control .13 Shunt Trip (Fail safe) .14 Shunt Trip (Non fail safe) .15 Ground Fault .16 Energy Saver .17 Heating .18 Slow Speed (Cyclo-converter) .19 Slow Speed Forward (Cyclo-converter) .20 Slow Speed Reverse (Cyclo-converter) .21 DC Injection Braking .22 PORT (Power Outage Ride Through) .23 Tach Loss Output relay contacts shall be: .1 Quantity (Qty) 2, form C 5 Amps resistive (125V), 3 Amps resistive (250V) .2 Qty 3, form A 5 Amps resistive (125V), 5 Amps resistive (250V). Qty 2, form C 10 Amps resistive (125V) .3 Motor Protection & Monitoring .1 Provide motor monitoring and protection features as described below. Listed motor protection functions shall be supplied with all requisite PT’s and CT’s . .2 RTD Monitoring, for 100 Ohm Platinum RTDs .1 8 channels, programmable, expandable to 16 channels .2 Meter display in oC or oF, +/- 1 percent of the following: .1 Individual RTD temperatures .2 Sample and hold .3 Individual Alarm and Trip set points CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 14 of 18 DATE: April 2012 .4 Remote monitoring capability with RS-485 Standard (as published by the Telecommunication Industry Association) communication to Starter Overload Biasing .3 The following ANSI protective device functions shall be provided: .1 ANSI 14 – Speed Switch and Tachometer Trip .2 ANSI 19 – Reduced Voltage Start .3 ANSI 27 / 59 – Adjustable over/under voltage protection (Off or 1 to 40 percent, time 0.1 to 90.0 sec. in 0.1 sec. intervals, independent over and under voltage levels) .4 ANSI 37 – Undercurrent detection (Off or 5 to 100 percent and time 0.1 to 90.0 sec. in 0.1 sec. intervals) ANSI 38 – Bearing RTD .5 Other RTD Open RTD Alarm .6 ANSI 46 – Current imbalance detection (Off or 5 to 40 percent) .7 ANSI 47 – Phase rotation (selectable ABC, CBA, Insensitive, or Single Phase) .8 ANSI 48 – Adjustable up-to-speed / stall timer (1 to 900 sec. in 1 sec. intervals) .9 ANSI 49 – Stator RTD .10 ANSI 50 – Instantaneous electronic overcurrent trip .11 ANSI 51 – Electronic motor overload (Off, class 1 to 40, separate starting and running curves available) .4 Miscellaneous Functions: .1 Time between starts .2 Broken RTD alarm .3 Short/low RTD alarm .4 Undervoltage alarm .5 RS-485 Modbus communications .6 99 time/date stamped event records .7 9 Fault Event Date/Time/Status recorder .5 Provide the following programmable Motor Control Functions: .1 Motor Starting/Running .1 Realtime true torque control .2 Ramp to Limit .3 Full Voltage Start .4 Initial Current (50-600 percent) .5 Start Ramp Time (0-120 Seconds) .6 Maximum Current (200-800 percent) .7 Slow Speed Cylco control .8 Dual Kick Start (0.1-10 Seconds) .9 Dual Ramps .10 Programmable 1-6400 Amps .11 Motor Service Factor (1.0 to 1.99) .12 Power Outage Ride Through .2 Motor Stopping: CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 15 of 18 DATE: April 2012 .1 .2 .3 .4 .3 .4 .6 Real time true torque control Fail Soft on Motor Overload Auxiliary Motor Feeder Control Optional fully programmable “S” curve or linear pump deceleration .5 DC Injection Braking Interlocking/Logic: .1 Restart Block-Backspin Timer .2 Overload Lockout .3 Intelligent Overload .4 Overload Reset Time .5 General Fault Digital Relay Output .6 Assignable Digital Relay Outputs (2) .7 Frequency Tracking (23 – 72 Hz) .8 Up to Speed Indication/Contact .9 Digital Inputs (8) .10 Analog Input .11 Tachometer Input .12 User Selectable # of Auto Restarts .13 User Selectable Fault Priority .14 Fully Programmable 6 output Relays .15 Programmable “Ready” Contact Maintenance Mode .1 Emergency Restart after Fault Lockout .2 Selectable CT Ratios .3 Current Limited Jog .4 Built In Self Test: Provide built-in self testing (BIST) capability to perform the following functions to verify satisfactory starter operation: .1 Sustained generation of SCR gate firing signals for 3 minutes to allow measurements to be made for the presence, amplitude and duration of the gating signals. .2 Engage the bypass and inline contactors one time, utilizing auxiliary contact feedback to the micro processor to verify correct operation of the contactors. .5 Real Text Event Recorder Provide the following programmable Motor Protection Functions: .1 Motor/Machine Faults .1 Electronic Overload .2 Overload Reset .3 Overload Warning .4 Acceleration Timer .5 Mechanical Jam/Electronic Shearpin (Selectable Trip or Warning) .6 Motor Thermal Capacity Protection CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 16 of 18 DATE: April 2012 .7 .8 .9 .10 .2 .7 Undercurrent Alarm (Selectable Trip or Warning) Time Between Restarts Trip Reset Protection Machine Ground Fault Protection (Selectable Trip or Warning) Electrical System Faults .1 Undercurrent Protection .2 Current Imbalance (10-40 percent) .3 Undervolt Protection (10-30 percent) .4 Overvolt Protection (10-30 percent) .5 Phase Reversal Protection .6 Underfrequency Protection .7 Overfrequency Protection .8 Overload Alarm .9 Generator Set Frequency Tracking .10 Restart After Non-critical Fault .11 Ground Fault Protection Brush Type Synchronous Motor Only-ANSI devices. Provide the following: .1 #81- Frequency Trip/Alarm .2 #13- Synchronous Speed .3 #31- Separate Excitation .4 #40- Machine Field Relay .5 #56- Field Application Relay .6 #78- Phase Angle Out of Step .8 Ground Fault Current Detection The Solid State Starter must comply with the UL 1053 Standard for Safety for Ground-Fault Sensing and Relaying Equipment. Provide a Class 1 ground-fault current sensing device for protection of equipment for use in locations that will operate to cause a disconnecting device to open all ungrounded conductors at predetermined values of ground-fault current in accordance with the National Electrical Code, ANSI/NFPA 70. Rated for service entrance operation on 1000 amp and greater. 2.10 Pump Protection & Monitoring .1 Basic motor control algorithm shall be sensorless torque control. Provide the following operation via a real-time control method that dynamically determines motor efficiency in order to provide true torque control of the motor to control pressure overshoot, and deceleration to eliminate water hammer. Starters utilizing open loop voltage or closed loop current control algorithm are not acceptable. The torque control shall provide the following: .1 Pressure surge and transient reduction .2 Water hammer elimination .3 “Soft” check valve opening and closing CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS Page 17 of 18 DATE: April 2012 .2 Provide the following pump monitoring and protection, including all related sensing devices as described below. Listed pump protection functions shall be via the starters integral control package . .1 Pump jam protection .2 Self compensating for load and voltage .3 Low flow and run dry protection .4 Backspin detection .5 Shaft windup elimination on long shaft machines .1 Factory Testing Specification: .1 The solid state starter manufacturer shall functionally test the starter at rated voltage on an AC three phase induction motor (LOW VOLTAGE TESTING OF MEDIUM VOLTAGE EQUIPMENT WILL NOT BE ACCEPTED). .2 As a minimum, the manufacturer must test and certify starting, stopping and logic interlock functionality. .3 In addition, the manufacturer shall provide a load test of the starter at rated current (including the service factor rating). .4 The starter manufacturer must be UL load test certified. .5 The starter manufacturer shall issue a test report certifying that the starter has met the design requirements of the specification. .2 Starters furnished herein shall undergo the following additional factory testing: .1 All incoming material shall be inspected and/or tested for conformance to quality assurance specifications. Power semiconductors shall be fully tested for proper .2 electrical characteristics, including dv/dt and di/dt. .3 All subassemblies shall be inspected and/or tested for conformance to quality assurance specifications. .4 Each completed unit shall be functionally tested prior to shipment to ensure conformance to the Specifications. .1 Computer Based Training (CBT) must be provided with the starter at time of shipment. The course, supplied in DVD/CD format, will be interactive training covering medium voltage solid state starter design basics, equipment overview, programming and operation, commissioning, maintenance, and service. .2 Provide 2 Days of training prior to startup and another 2 consecutive Days for startup and operational training. PART 3. EXECUTION 3.1 3.2 Testing Startup & Training CONTRACT NO T-12-16 Section 16346 MEDIUM VOLTAGE SOLID STATE STARTERS DATE: April 2012 3.3 3.4 3.5 Page 18 of 18 .3 Services shall include startup of equipment and field/classroom training for Owner’s personnel. .4 Startup and training shall be provided by original solid state motor manufacturer personnel only. The use of agents, manufacturer’s representatives, third party brand labelers, packagers, associated integrators or manufacturer’s distributors for startup and training shall not be permitted. .1 Factory support must be provided by the original equipment manufacturer 365 Days a year, 24 hours a Day. .2 Factory support and service must be provided by original solid state motor control manufacturer’s trained technicians. The use of agents, manufacturer’s representatives, third party brand labelers, packagers, associated integrators or manufacturer’s distributors for service shall not be permitted. At the Region’s request, verification of the technicians qualifications must be provided. .1 Starters furnished herein shall include a three (3) year manufacturer’s warranty. The warranty shall be provided in writing and shall cover (from date of Total Performance of the Work) all solid state power sections and PowerController solid state cards with two (2) year manufacturer’s warranty (from date put in service) on other equipment of each system. .2 Additionally, solid state starter manufacturer shall guarantee in writing, availability of parts, service, and technical support for said product for a minimum of 7 years. .3 There shall be no transfer of warranty by manufacturer/ vendor/supplier. The supplier of the Product shall be the warranty holder and original equipment manufacturer. Third party warranty transfer is not acceptable including any third party brand labelers, packagers, associated integrators or manufacturer’s distributors. .1 A complete spare parts list shall be provided at time of submittal of shop drawings. .2 Spare parts shall include, but not be limited to: .1 One each of each type of Printed Circuit Board .2 One of each type and size of control fuse .3 Three of each type and size of power fuse .4 One complete spare Power Cell of each type and size used. Factory Service Warranty Spare Parts END OF SECTION CONTRACT NO. T-12-16 DISCONNECT SWITCHES – FUSED AND UNFUSED DATE: April 2012 PART 1. 1.1 1.2 1.3 Section 16414 2006-08-30 Page 1 of 2 GENERAL Related Sections .1 Section 16010 – Electrical General Requirements .2 Section 16141 – Wiring Devices .3 Section 16335 – Temporary and Transition Electrical Equipment .1 Submit Product data in accordance with Section 01300 – Submittals. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16414 – Disconnect Switches – Fused and Unfused as indicated in Schedule ‘A’ of the Bid Form. .1 Supply and install safety switches, fused or non fused, as required complete with fuses as shown on the Drawings or required by the OESC. Safety switches shall be quick make and quick break construction with safety interlock and HP ratings as indicated on the Contract Documents. .2 Provide for padlocking in off switch position by three locks. .3 Mechanically interlocked door to prevent opening when the handle is in the ON position. .4 Fuses: size as indicated on the Contract Drawings. .5 Fuseholders: relocatable and suitable without adaptors, for type and size of fuse indicated on the Contract Drawings. .6 Quick-make, quick-break action. .7 ON-OFF switch position indication on switch enclosure cover. .8 Switches are to be housed in an EEMAC 12 enclosure when located indoors and EEMAC 4 enclosure when located outdoors. .9 Approved Suppliers: .1 Schneider Canada Inc. (Federal Pioneer). .2 TECO-Westinghouse Motors (Canada) Inc. .3 Schneider Canada Inc. (Square D). .4 Eaton Yale Company (Cutler Hammer). Product Data Measurement and Payment PART 2. PRODUCTS 2.1 Disconnect Switches CONTRACT NO. T-12-16 DISCONNECT SWITCHES – FUSED AND UNFUSED DATE: April 2012 2.2 Section 16414 2006-08-30 Page 2 of 2 Equipment Identification .1 Provide equipment identification in accordance with Section 16010 - Electrical General Requirements. .2 Indicate the name of the load controlled on a size 4 nameplate. .1 Install disconnect switches complete with fuses if applicable. PART 3. EXECUTION 3.1 Installation END OF SECTION CONTRACT NO. T-12-16 PANELBOARDS BREAKER TYPE DATE: April 2012 PART 1. 1.1 1.2 1.3 Section 16441 2006-08-30 Page 1 of 2 GENERAL Related Sections .1 Section 16050: Basic Materials and Methods .1 Submit shop drawings in accordance with Section 01300 – Submittals. .2 Drawings to include electrical detail of panel, branch breaker type, quantity, ampacity and enclosure dimension. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16441 – Panelboards Breaker Type as indicated in Schedule ‘A’ of the Bid Form. .1 Panelboards: Product of one manufacturer. .1 Install circuit breakers in panelboards before shipment. .2 In addition to CSA requirements, the manufacturer's nameplate must show fault current that panel including breakers has been built to withstand. .2 200 – 600 V panelboards: bus and breakers rated for 22,000 A symmetrical interrupting capacity or as indicated in the Contract Drawings. .3 Sequence phase bussing with odd numbered breakers on the left and even numbered breakers on the right, with each breaker identified by permanent number identification as to circuit number and phase. .4 Panelboards: mains, number of circuits, and number and size of branch circuit breakers shall be as indicated on the Drawings. .5 Provide two keys for each panelboard and key panelboards alike. .6 Copper bus with neutral of same ampere rating as mains. .7 Mains: suitable for bolt-on breakers. .8 Trim with concealed front bolts and hinges. .9 Trim and door finish: baked grey enamel. Submittals Measurement and Payment PART 2. PRODUCTS 2.1 Panelboards CONTRACT NO. T-12-16 PANELBOARDS BREAKER TYPE DATE: April 2012 2.2 2.3 2.4 Section 16441 2006-08-30 Page 2 of 2 Custom Built Panelboard Assemblies .1 125 mm relay section on both sides of panels as indicated on the Drawings for installation of low voltage remote control switching components. .2 Double stack panels as indicated in the Contract Drawings. .3 Contactors in mains as indicated in the Contract Drawings. .4 Feed through lugs as indicated in the Contract Drawings. .5 Isolated ground bus. .1 Breakers: .1 Breakers with thermal and magnetic tripping in panelboards except as indicated otherwise in the Contract Drawings. .2 Main breaker: separately mounted on top or bottom of panel to suit cable entry. When mounted vertically, down position should open breaker. .1 Provide equipment identification in accordance with Section 16010 - Electrical General Requirements. .2 Nameplate for each panelboard size 4 engraved as indicated in the Contract Drawings. .3 Nameplate for each circuit in distribution panelboards size 2 engraved as indicated in the Contract Drawings. .4 Complete circuit directory with typewritten legend showing location and load of each circuit. .1 Locate panelboards as indicated on the Contract Drawings and mount securely, plumb, true and square, to adjoining surfaces. .2 Install surface mounted panelboards on plywood backboards. Where practical, group panelboards on common backboard. .3 Mount panelboards to height specified in Section 16010 Electrical General Requirements or as indicated in the Contract Documents. .4 Connect loads to circuits. .5 Connect neutral conductors to common neutral bus with respective neutral identified. Breakers Equipment Identification PART 3. EXECUTION 3.1 Installation END OF SECTION CONTRACT NO. T-12-16 LIGHTING EQUIPMENT DATE: May 2012 PART 1. 1.1 1.2 1.3 1.4 Section 16505 2006-08-30 Page 1 of 3 GENERAL Related Sections .1 Section 16010 – Electrical General Requirements .1 Comply with the latest edition of the following statutes, codes and standards, and all amendments thereto. .1 American National Standards Institute (ANSI) 1. ANSI C82.1, Specifications for Fluorescent Lamp Ballasts. 2. ANSI C82.4 , Ballasts for High-Intensity-Discharge and Low-Pressure Sodium Lamps. .2 American National Standards Institute/Institute of Electrical and Electronics Engineers (ANSI/IEEE) ANSI/IEEE C62.41- 1991, Recommended 1. Practices for Surge Voltages in Low-Voltage AC Power Circuits. .3 ASTM International (ASTM) 1. ASTM F1137, Specification for Phosphate/Oil and Phosphate/Organic Corrosion Protective Coatings for Fasteners. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16505 – Lighting Equipment as indicated in Schedule ‘A’ of the Bid Form. .1 Submit shop drawings in accordance with Section 01300 – Submittals. .2 Submit complete photometric data prepared by an independent testing laboratory for luminaires where specified in the Contract Documents. The data shall be submitted to the Consultant for approval. .1 Supply and install lighting fixtures of the type and number as shown on the lighting fixtures schedule in the Contract Drawings. .1 All LED fixtures shall be 120 VAC and supplied complete with drivers. These outdoor fixtures shall be surface mounted or References Measurement and Payment Submittals PART 2. PRODUCTS 2.1 2.2 General Lamps CONTRACT NO. T-12-16 LIGHTING EQUIPMENT DATE: May 2012 Section 16505 2006-08-30 Page 2 of 3 supplied complete with an adjustable aiming bracket and service mounting box where required. Drivers shall be suitable for starting at -35ºC. 2.3 .2 All 32 Watt rapid start fluorescent lamps shall be colour temperature 3500 K rated 20,000 hours, 2,900 lumens initial, unless otherwise noted in the Contract Documents. .1 All standard fluorescent fixtures shall be equipped with high power factor, rapid start ballasts for operation on 120 V. Ballasts shall be complete with non-automatic reset thermal protection. The ballasts shall meet the specifications and requirements of the Electrical Testing Laboratories and Certified Ballast Manufacturers' Association. .3 All 54 watt high output fluorescent lamps shall be colour temperature 3500 K rated 20,000 hours, 5000 lumens initial, unless otherwise noted in the Contract Documents. .1 All standard fluorescent fixtures shall be equipped with high power factor, rapid start ballasts for operation on 120 V. Ballasts shall be complete with non-automatic reset thermal protection. The ballasts shall meet the specification and requirements of Electrical Testing Laboratories and Certified Ballast Manufacturers' Association. .4 Approved manufacturers/suppliers: .1 Royal Philips Electronics NV .2 General Electric Company .3 Osram Sylvania LTD. .1 Fluorescent ballast: CBM and CSA certified, energy efficient type, High Frequency electronic design. .1 Rating: voltage as indicated in the Contract Documents, for use with 2/3 -32 W, rapid start lamps or 4-54 W high output lamps. RFI/EMI suppression circuit in accordance with: FCC .2 (CFR47) Part 18, sub-part C, Class A and Part 15, subpart B, Class B. .3 Totally encased and designed for 40 degree Celsius ambient temperature. .4 Power factor: minimum 95% with 95% of rated lamp lumens. .5 Crest factor: 1.7 maximum current, 2.0 maximum voltage. .6 Capacitor: thermally protected. .7 Thermal protection: non-resettable on coil. .8 Harmonics: 1 % maximum THD, including 49th for electronic discrete and hybrid ballasts. .9 Operating frequency of electronic ballast: 25 khz minimum. Ballasts CONTRACT NO. T-12-16 LIGHTING EQUIPMENT DATE: May 2012 .10 .11 .12 2.4 Ballast Factor: greater than 0.85. Sound rated: Class A+. Mounting: integral with luminaire. Emergency Lighting .1 2.5 Section 16505 2006-08-30 Page 3 of 3 Approved Suppliers: .1 Lumacell Inc. a Division of Thomas & Betts Ltd. .2 EmergiLite, Thomas & Betts Ltd. Lighting Control Devices .1 .2 .3 .4 .5 .6 Wall Sensor Switch, 1-circuit, line voltage, passive IR: Watt Stopper #DW-100 Wall Sensor Switch, 2-circuit, line voltage, passive IR: Watt Stopper #DW-200 Ceiling Sensor, line voltage, 360-degree coverage, dual technology: LeGrand Group, WattStopper #DT-355 Ceiling Sensor, low voltage, 360 degree coverage, dual technology, rated for hazardous locations, Class 1, Div. 1 areas: Protech Protection Technologies Inc., Protech Piramid SDI-77XL2-EX Power pack, 1-circult, dual voltage 120/277 VAC: Watt Stopper #BZ-100 Power pack, 2-circuit: Watt Stopper #LC-100 PART 3. EXECUTION 3.1 3.2 3.3 3.4 Installation .1 Locate and install luminaires as indicated in the Contract Documents. .1 Connect luminaires to lighting circuits: .1 Through flexible or rigid conduit for all luminaire designs . .1 For suspended ceiling installations support luminaires from ceiling grid in accordance with local inspection requirements. .1 Align luminaires which are mounted in continuous rows to form straight uninterrupted line. .2 Align luminaires which are mounted individually parallel or perpendicular to building grid lines. Wiring Luminaire Supports Luminaire Alignment END OF SECTION CONTRACT NO. T-12-16 Section 16620 EMERGENCY POWER GENERATORS Page 1 of 14 DATE: April 2012 PART 1. 1.1 1.2 1.3 1.4 1.5 GENERAL Summary .1 Comply with Division 1 – General Requirements and Section 16010 – Basic Electrical Requirements. .1 Section 11900 – Diesel Storage Tank and Monitoring System .2 Section 11905 – Fuel Oil Pumping System .1 Comply with the latest edition of the following statutes, codes and standards, and all amendments thereto. .1 British Standards Institution 1. BS5514 (ISO 8528) Reciprocating Internal Combustion Engine Driven Alternating Current Generator Set. .2 Canadian Standards Association (CSA) 1. CSA B139, with Ontario amendments: Ontario Installation Code for Oil Burning Equipment. 2. CSA C22.2 No. 100 Motors and Generators. 3. CSA-C282 Emergency Electrical Power Supply for Buildings. .3 DIN 6271 Reciprocating Internal Combustion Engine Driven Alternating Current Generator Set Performance Standard Reference Conditions, Declaration of Power, Fuel Consumption and Lube Oil Consumption. .4 Electrical Equipment Manufacturers Association of Canada (EEMAC) 1. EEMAC Standard MG1 Motors and Generators. 2. EEMAC Standard M1-6 Motors and Generators. 3. EEMAC Standard MG2 Safety Standard for Motors and Generators. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16620 – Emergency Power Generators as indicated in Schedule ‘A’ of the Bid Form. .1 Emergency power generation system includes three diesel engine driven generators. .2 The Contractor will have the final responsibility for the supply, supervision of installation, and integration of this equipment with the 4160 V switchgear. Since the 4160 V switchgear controls are Related Sections References Measurement and Payment Design Requirements CONTRACT NO. T-12-16 Section 16620 EMERGENCY POWER GENERATORS Page 2 of 14 DATE: April 2012 integrally tied into the generator controls, the generator manufacturer will coordinate with the switchgear supplier to ensure fully operational switchgear and generator controls. .3 The Contractor shall supply a system suitable to supply, without interruption, the maximum essential load indicated in the Contract Documents for an unlimited duration under the ambient conditions indicated in the Contract Documents. Intermittent ratings of limited durations are not acceptable. .4 The Contractor shall supply a system capable of starting and running the essential loads under any load condition. .5 The Contractor shall supply a system capable of connecting to load when the output is at a minimum of 90 percent of the normal voltage and frequency. Within 3 seconds after connection to load, 100 percent output nominal voltage and frequency shall be available at the generator terminals. .6 The Contractor shall supply a direct injection, cold starting type engine suitable for starting in an ambient temperature of -2 degrees Celsius without the use of battery powered heaters. .7 The Contractor shall rate engine output for standby power and generator set application as defined by BS5514 (ISO 8528) or DIN 6271. Derate net engine output power by taking into account engine driven accessories, 30 degree Celsius ambient air temperature and the project Site elevation above sea level. .8 Derated net engine output power at engine flywheel must not be less than the generator output power divided by the generator efficiency. (Engine Shaft Power = Rated Electrical Output Power) Generator Efficiency .9 Engine shall be capable of operating continuously with loads down to 30 percent of the rated capacity and with periodic intervals of no-load. .10 The Contractor shall supply a system with the generator rated to operate at 1800 RPM. .11 The Contractor shall supply a radiator cooling system adequate for engine operating under full load and overload conditions in an ambient temperature of 30 ï€ degrees Celsius. .12 The Contractor shall size the radiator so that the engine jacket water does not exceed 90 degrees Celsius under operating conditions. .13 Engine jacket water fouling (cleanliness) factor shall be a minimum of 75 percent. CONTRACT NO. T-12-16 Section 16620 EMERGENCY POWER GENERATORS Page 3 of 14 DATE: April 2012 .14 The generators shall include a speed governor to regulate the steady state speed within 2 percent, no-load to full-load and fullload to no-load. .15 The generators shall include speed regulation on the starting of motors and for peak no-load to full-load and full-load to no-load transients shall be within 8 percent. .16 Speed stability of the generators at the constant load shall be within 1 percent and free from hunting and oscillations. .17 Speed recovery of the generators, from the instant of load change to steady state, to occur within 3 seconds. .18 The Contractor shall size the silencer so that back pressure on the engine operating at 110 percent load will not exceed the engine manufacturer's recommended value. .19 The Contractor shall supply a 24 V battery with sufficient capacity to crank the engine, with 10 degree Celsius ambient temperature, for 60 seconds continuously without the battery nominal voltage reducing below 75 percent minimum. .20 The Contractor shall supply a synchronous generator conforming to EEMAC Standard MG1, capable of operating at 110 percent of the nominal rating for one hour in any 12 hour period without any reduction in the life span. .21 Generator and voltage regulator shall be capable of supplying 300 percent of full load current for a minimum of 10 seconds under fault and motor starting conditions. .22 Automatic voltage regulator to control steady state output within 2 percent, no-load to full load, between unity and 80 percent power factor lagging. .23 Provide for a fast transient response of the automatic voltage regulator to ensure that transient generator output voltage dips do not exceed 25 percent when carrying a load of 700 kW and another 1000 HP motor is started using a soft starter. .24 Voltage recovery time for load change to steady state shall be a maximum of 2 seconds. .25 Voltage regulation from no load to full load shall be within 1 percent. .26 Generator and automatic voltage regulator shall be suitable for supplying loads with significant harmonic content such as variable frequency drives, solid state starters and similar items. .27 The Contractor shall limit total vibration transmission to a maximum of 2 percent. .28 Noise from the generator enclosure shall not exceed a maximum of 75 dB at 7 m from the enclosure with the generator operating under full rated load. CONTRACT NO. T-12-16 Section 16620 EMERGENCY POWER GENERATORS Page 4 of 14 DATE: April 2012 1.6 1.7 Submittals .1 The Contractor shall submit the following shop drawings, information and data: .1 Dimensioned and scaled mechanical drawings of equipment, components and auxiliaries. .2 Schematic and wiring diagrams detailing system interlocks, internal wiring and field wiring connections. Indicate the size of wiring and identify the wire and terminal blocks. Indicate the colour coding used in wiring. .3 Manufacturer's data sheets and performance curves providing details of the engine and generator characteristics. .4 Dimensioned drawings of the control panel outline and the layout of internal and external components. .5 Bills of Material. .6 Details of vibration isolation. .7 Fuel oil piping connection details. .8 Engine exhaust and silencer details. .9 Details of space requirements around the generator for maintenance purposes. .10 Noise and emissions data. .11 P & ID in both a hardcopy and softcopy (Autocad). The Consultant will re-assign permanent tag numbers to all devices in the P & ID. The Contractor shall use the new number for all subsequent drawing submissions and documentation. .12 The Contractor shall submit four copies of the installation and start-up procedure manual to the Consultant prior to delivery of the emergency power generator system. .13 The Contractor shall submit operating and maintenance manuals including, but not limited to the following: 1. Complete parts list 2. Spare parts list 3. List of approved spare parts suppliers 4. Operating instructions 5. Maintenance instructions 6. Detailed troubleshooting procedures and fault correction schedules 7. Data sheets and performance curves 8. Certified shop test results 9. Final record drawings .1 The Contractor shall test equipment, components and auxiliaries to ensure their correct operation and function prior to shipment. The Contractor shall test actual safety devices and circuits and record actuating levels. Jumper tests are not acceptable. Quality Assurance CONTRACT NO. T-12-16 Section 16620 EMERGENCY POWER GENERATORS Page 5 of 14 DATE: April 2012 PART 2. 2.1 2.2 2.3 .2 The Contractor shall operate the engine and generator set for a minimum of three hours under full load, a minimum of one hour under varying load and one hour at 110 percent of full load. .3 The Contractor shall advise the Consultant a minimum of five Working Days prior to carrying out tests so that the Consultant may witness tests, if required. .4 Submit two sets of certified test results to the Consultant prior to shipment. .1 Standby power rating of 2000 kW (2500 kVA) @ 0.8 Power factor lagging, to meet EPA Tier 2 emission limits. .2 Output supply 4160 V, 3-phase, 60 Hz. .3 Grounding for generator set shall be connected to a high resistance plant grounding system with a 10 A neutral grounding resistor. Generator supplier to ensure that the generator set provided is compatible with this grounding configuration. .4 All process area loads will be started in sequence with a time delay from the SCADA. .1 Toromont/Caterpillar .2 Cummins Ontario Inc. .3 Harper Detroit Diesel Ltd. .1 Engine .1 Design: Four stroke cycle, pressurized induction, turbo charged, radiator cooled, suitable for operating on commercial grade #2 diesel fuel oil. .2 Block heater: 120 V, 60 Hz, rated to ensure that the engine will start without labouring in an ambient temperature of minus 2 degrees Celsius. .2 Cooling System .1 Radiator cooling system: Radiator set mounted complete with inlet cooling and outlet ducting flanges. .2 Fan: pusher type, engine driven with V-belts. .3 Flexible canvas boot: flanged on both sides, minimum length of 100 mm, mounted on the front of the radiator. .4 Water circulating pump: Engine driven. .5 Make-up and expansion tanks: With filling cap and vent over-flow pipe. For filling caps located higher than GENERAL Generator Set Requirements Manufacturers Manufactured Units CONTRACT NO. T-12-16 Section 16620 EMERGENCY POWER GENERATORS Page 6 of 14 DATE: April 2012 .6 .7 .8 .9 .10 .11 1500 mm above the floor, furnish a level indicator which is visible and legible from the floor level. Tank low level condition: Operate the engine shut-down switch to open the engine start circuit. Temperature regulating valve: With a bypass feature, located in the cylinder head water outlet. Piping: Furnish all necessary water pipes, flexible hoses and similar items. Drain cocks: Located to completely the drain system. Safety protection: Provide equipment guards on all moving parts. Coolant: Suitable for minus 40 degrees Celsius. Furnish first filling. .3 Speed Governor .1 Type: Electronic. .2 Manual speed adjustment: Micrometer screw type, shutdown lever and overspeed stop. .4 Fuel Oil System .1 Injection equipment: Fuel pumps and injectors. .2 Fuel rack or shutdown solenoid: Energized to run, maximum fuel at the start. Fuel solenoid valves are not acceptable. .3 Fuel filters: Replaceable element type. .4 Fuel piping: Secured to the engine for fuel supply, injection and bleed return with bronze check valves and cocks. .5 Fuel oil line connectors: Flexible, bronze corrugated type for suction and return lines, located on a horizontal plane, secured at one end of the engine base, Type BA by United Flexible. .6 Day tank unit: Sub base type with threaded pipe connections, suction pump, high level and low level alarm switches, fuel gauge tank mounting brackets, ULC approved. .7 Fuel supply accessories: Nippled manual gate shut-off valve and primary fuel filter with sedimenter. .8 Provision for connection to supply and return fuel piping from an external fuel tank. .5 Sub-Base Fuel Tank .1 The generator shall come complete with a sub-base, double walled, fuel tank (day tank). The tank shall have 3 hours fuel storage capability. .2 .3 The tank shall have a leak detector alarm. .4 The tank shall have float switches for level indication for alarm and monitoring to the plant PLC/SCADA, and for fuel filling requirements, as well as additional high and low level floats which shall be wired to the control panel as spare fuel level outputs. CONTRACT NO. T-12-16 Section 16620 EMERGENCY POWER GENERATORS Page 7 of 14 DATE: April 2012 .5 The day tank will be filled from an external underground storage tank supplied by the Contractor. .6 Engine Lubrication System .1 Engine lubrication system: Full pressure type. .2 Oil pump: Engine driven gear type with strainer and adjustable pressure relief valve. .3 Sump drain pipe: With gate valve and plug, extend 75 mm beyond the bedplate. .4 First oil filling: Shipped in containers for Site filling. .5 Engine must start within 10 seconds of receiving a start command. Provide a suitable lubrication system to meet this requirement. .7 Engine Air Intake and Exhaust Systems .1 Air intake filters: Dry replaceable element type located close to the inlet manifold. .2 Exhaust pyrometer: One in each manifold, with remote bulb, 75 mm dial, range 0 to 110 percent minimum, Millivolt type by Thermo Electric (Canada) Limited. .3 Turbo charger: Exhaust gas driven type. .4 Operator protection: Insulating exhaust blanket on manifold, piping, turbo charger, and similar items. .5 Exhaust connector: Flexible bellows with ANSI flange for installation between the exhaust manifold and the silencer. .6 Exhaust silencer: Residential grade with ANSI flanges, condensate drain cock and plug. .8 Engine Starting System .1 Cranking motor: Electrical, 24 V DC with positive engaging gear and solenoid. .2 Starting batteries: Storage, lead acid, heavy duty type, hard rubber case, HYCAP C8D by Exide Electronics Canada Inc. .3 Battery support rack: With support legs, acid resistant paint finish. .4 Battery charger: 120 V, 60 Hz input, 10 A, 24 V DC output, automatic boost and float charging, solid state voltage control and recycle timer, input and output circuit breakers, manual-automatic selector switch, separately adjustable boost and float rates, current limit protection, battery low level alarm relay, DC voltmeter and ammeter with 5 percent accuracy. Vulcan Electric Inc., DS12/ Series. .5 Battery charger location: Within the generator enclosure. .9 Engine Gauges .1 Furnish gauges equipped with, or indicating, the following: 1. Lube oil pressure. 2. Lube oil temperature. 3. Tachometer. 4. Exhaust pyrometer. CONTRACT NO. T-12-16 Section 16620 EMERGENCY POWER GENERATORS Page 8 of 14 DATE: April 2012 .2 .3 5. Jacket water temperature. Tachometer: 1 percent accuracy, scale 0-120 percent minimum of rated speed. Gauges may be included as part of the generator set controller. .10 Safety Switches .1 Sensors: Adjustable type with settings sealed by locknuts or Sealtite fittings, directly accessible for ease of maintenance and replacement. .2 Centrifugal speed switch: Direct mechanical drive, two element unit with independently adjustable normally closed contacts for cranking cutout and normally open contacts for overspeed, snap action. .3 Solid state speed switch: Direct mechanical drive from generator. .4 Cranking cutout back-up protection: Where solid state speed switch is furnished, provide an oil pressure sensor. .5 Furnish the following safety switches: 1. Lube oil low pressure. 2. Overspeed switch. 3. Cranking cut-out. 4. Jacket water high temperature. .11 Engine Wiring and Terminal Box .1 Safety switch and control device wiring: Heat and oil resistant, run in a harness secured to the engine and terminated in the engine terminal box. Number wires corresponding to the schematic and wiring diagrams with Type Z wire markers by Wieland Electric Inc. .2 Terminal box: EEMAC 12 dust tight enclosure with numbered terminal blocks corresponding to the schematic and wiring diagrams. Furnish a separate junction box for 120 V powered circuits. .12 Generator .1 Design: 4160 V, 3 phase, 60 Hz, wye connected, 1800 RPM, horizontal, protected enclosure. .2 Insulation: Class F with 105 degree Celsius temperature rise above 40 degree Celsius ambient temperature. .3 Field supply: Brushless exciter with removable shaft mounted diodes. .4 Terminals: For each phase, wye point and ground, readily accessible in a diagonally split, gasketted terminal box. .5 Bearings: One or two as required, anti-friction type, minimum B10 life of 50,000 hours. .6 Radio Frequency Interference (RFI) Suppression: Commercial standard. .7 Current transformers: Primary rating as required, secondary rating 5A, for each phase and neutral, for differential protection. CONTRACT NO. T-12-16 Section 16620 EMERGENCY POWER GENERATORS Page 9 of 14 DATE: April 2012 .13 Voltage Regulator .1 Design: Automatic, static type with fail safe feature so that no overvoltage will occur if the regulator fails, three phase sensing, protection against fault during underspeed running, located in the generator control panel, capable of voltage build-up without batteries. .2 Control potentiometers: Clockwise rotation to increase related function. Voltage adjustment potentiometer or tapped choke: To 5 .3 percent above and below nominal voltage. .14 Drive Coupling .1 Coupling: Torsionally rigid flexible steel disc type for connecting single bearing generator to engine with SAE housing. Flexible grid spring type, for connecting the two bearing generator to the engine. .15 Assembly .1 Base: Common for generator and engine, rigid heavy duty steel, machined pads, capable of maintaining alignment during transportation, installation and operation. If necessary, accommodate a crankcase oil drain pipe. .2 Vibration isolators: To support the base and assembly, visible steel spring type, levelling bolts, externally adjustable mechanical side snubbers, sound dampening pads. Type #LK by Korfund Dynamics .3 Personnel protection: Safety guards around the exposed rotating equipment. .16 Generator Control Panel .1 Enclosure: Compartmented, rigid, free standing, dead front, EEMAC 1, suitable for floor mounting in the generator enclosure. Access to equipment, components, wiring and .2 terminations: Front only. .3 Cable entry: Bottom. Furnish cable and wire supports. .4 Doors: Removable, gasketted, pad-lockable with concealed hinges, 120 degrees minimum opening arc and internal document pocket. .5 Ground bus: Tin-plated copper, minimum 6 mm x 50 mm cross section, extending the complete length of the control panel. .6 Engine Control Section: 1. Control selector switch: Three position, rotary, positive action type with wiping contacts, screw terminals, door mounted, marked AUTO-OFFMANUAL (TEST), shall be located in the generator breaker cell in the switchgear enclosure. 2. Automatic start circuit: Initiated by the closing of a dry contact in the Automatic Transfer Switch. CONTRACT NO. T-12-16 Section 16620 EMERGENCY POWER GENERATORS Page 10 of 14 DATE: April 2012 3. .7 .8 Cranking control circuit: Operate with a centrifugal speed switch or a solid state speed switch on the engine. 4. Over-crank timer: Pneumatic or solid state, adjustable 3 to 30 seconds minimum, single function with lock-out or failure to start. Thermal time relays are not acceptable. 5. Cranking solenoid and fuel rack solenoid control relays: Heavy duty industrial type, minimum contact rating of 30 A. Engine shut down control circuit: Operated by 6. safety switches, whether the selector switch is in the auto or manual position. 7. Building services relay: Heavy duty industrial type, dc operating coil, four form-C dry contacts rated 120 V AC, 10A minimum to operate the engine room building services equipment when the engine operates. Annunciator Section 1. Annunciator: Door mounted, clearly labelled, dc powered, individual visual type with long life LED cluster type lamps removable from the front without the use of special tools, manual alarm reset. 2. Load: 0.3A maximum on engine failure. 3. Relays: Plug in type, contacts rated 120 V, 10A minimum. Furnish a common alarm relay with a minimum of two form-C, dry contacts for external connection. 4. Solid state annunciator relays are not acceptable. 5. Annunciation conditions: .1 Overcrank, nominally set at 20 seconds .2 Overspeed, nominally set at 110 percent of rated speed .3 Low oil pressure, nominal time delay of 10 seconds .4 High engine temperature .5 High lube oil temperature .6 Generator circuit breaker open .7 Low engine temperature .8 Low battery level .9 Low fuel supply .10 Two spare points Generator Control Section 1. Meters: Digital, flush mounted type in the generator breaker cell. 2. Include the following functions: Amps, Volts, Frequency, KW and Elapsed Time (Hours). 3. Current transformers: 5A secondary, 1 percent accuracy class. CONTRACT NO. T-12-16 Section 16620 EMERGENCY POWER GENERATORS Page 11 of 14 DATE: April 2012 4. .9 .10 .11 .12 .13 .14 .17 Voltage transformers: 4160V/120 V ratio, 1 percent accuracy class. 5. Furnish ground fault indication. Wiring and Terminal Blocks: 1. Shop wiring: Copper, stranded conductor, RW90 insulation, #14 AWG minimum for control and #12 AWG minimum for power and current transformer wiring. Wiring to the door mounted equipment shall be the extra flexible type. Wire completely and connect external connection wires to the terminal blocks. 2. Colour coding: Insulation colour to conform to the requirements of the Ontario Electrical Safety Code. Where the Ontario Electrical Safety Code does not provide specific requirements, furnish the following: .1 Ground : green .2 Neutral : white .3 Phases : black .4 DC control: blue .5 AC control: red .6 Externally energized controls and interlocks: yellow 3. Wire identification: Oil resistant, type Z markers by Wieland Electric Inc. at each end of the conductor corresponding to the schematic and wiring diagrams. 4. Wiring arrangement: Adequately supported, neat, protected from mechanical damage by shields and grommets. Wiring between the frame and the door shall be vertical torsion type over the hinge side. 5. Terminal blocks: Tubular screw type with barriers and labels. Furnish 20 percent spare. Control fuses: Adequately rated, mounted in barrier type mounts with ground connection lugs. Component identification labels: Engraved lamacoid, black with 5 mm minimum white letters, for internal and external components, secured with stainless steel screws. Stick-on labels are not acceptable. Warning sign: Engraved lamacoid, red with 12 mm minimum white letters, indicating the sources of supply, points of isolation and that the engine may start automatically at any time. Secure with stainless steel screws. Panel auxiliary interior luminaire: Manually switched, 120 V AC with dc auxiliary. All contacts and I/O signals are specified to be wired to terminals which are suitable for connection to field wiring. Interface with external system CONTRACT NO. T-12-16 Section 16620 EMERGENCY POWER GENERATORS Page 12 of 14 DATE: April 2012 .1 .2 .3 .4 2.4 Generator panels shall communicate with the generator master control panel (GMCP) provided as part of the switchgear control system. The Contractor shall ensure that all signals required to be sent to the plant SCADA system are available to the GMCP. This can be achieved either by hardwired signals or through communication link between the panels. The Contractor shall provide a list of hardwired and softwired signals during the shop drawing submission process. The following signals shall be made available to the GMCP at a minimum: 1. Generator running 2. Generator fault 3. Battery low 4. Crank failed 5. Diesel tank level 6. Low Fuel level 7. High Fuel level 8. Fuel tank leak 9. Power factor 10. Power output 11. Generator voltage .18 Accessories .1 Engine oil drip tray: Minimum 1.5 mm galvanized steel with 50 mm lip, located between the base and vibration isolators, extended to protect the floor and readily removable without disturbing any component. .2 Panel mounted operation and maintenance summary instruction sheet: Steel backplate mounted with glass front or clear varnish protection, suitable for mounting on the side of the control panel. .3 Spare parts and tools storage cabinet: Steel, wall mounted with a padlockable hinged door and sized to house tools, spare parts and one set of manuals. .4 Tools: Set of standard and special tools to carry out routine maintenance. .1 The following equipment shall be installed in the Generator room: .1 Generator set, .2 Built in day sub base fuel tank, .3 Muffler, .4 Control panel, .5 Louvers and bird screens, .6 Associated wiring, lifting and anchoring provisions. .2 The entire package shall be manufactured and pre-engineered such that the only exterior connections required are fuel, power, Equipment CONTRACT NO. T-12-16 Section 16620 EMERGENCY POWER GENERATORS Page 13 of 14 DATE: April 2012 and security monitoring. Additionally the exterior connections must be suitable for connection to the exhaust stack which shall be provided by the Contractor. 2.5 2.6 .3 Hoisting Provisions .1 The unit shall include provisions for hoisting such as lifting eyes at each end of the base which shall be capable of lifting the enclosure with all equipment installed. .4 Safety Equipment .1 The Contractor shall provide a portable, ULC approved, multi-purpose dry chemical fire extinguisher (ABS type) located by the primary exit door. .2 The Contractor shall provide warning signs “Caution, Generator may start at any time” which shall be included on the generator enclosure and inside each door. .3 The Contractor shall provide two emergency battery units complete with 2 heads per unit. .4 The Contractor shall provide two emergency stop push buttons, within the generator enclosure, one on either side of the generator. .5 Exhaust Piping Installation Requirements .1 Provide all required engine-generator set exhaust from the generator set stub stack on the top of the pre-engineered generator to the generator exhaust stack. .2 Confirm the minimum piping size indicated by the generator manufacturer to ensure that there is no excessive back pressure. Prior to piping installation, confirm the size of the pipe required and provide to suit. .3 Provide a perforated type 304 stainless steel semi-circular guard around all exposed exhaust piping outside the building where the piping could be touched by personnel standing on the grade. .4 Provide engineered pipe supports to support the exhaust piping from the generator set stub stack on the top of the pre-engineered generator enclosure to the generator exhaust stack. .1 Provide: .1 Two sets of drive belts. .2 Two lube oil filter elements. .3 Three fuel oil filter elements. .4 Two sets of electrical expendable items such as fuses, lamps and similar items. .1 Shop Assembly Spare Parts Fabrication CONTRACT NO. T-12-16 Section 16620 EMERGENCY POWER GENERATORS Page 14 of 14 DATE: April 2012 .1 .2 PART 3. 3.1 3.2 3.3 3.4 Alignment: Align the engine and generator horizontally and vertically within 0.05 mm using steel shims where required. Secure the units to the base with machine bolts. Dowels: For two bearing generator units, dowel the feet of the engine and generator. .2 Finish .1 Engine and generator assembly: Prime prepared surfaces and finish with two coats of heat and oil resistant machinery paint. Do not paint rubber and PVC hoses, wiring harnesses or machined surfaces. .2 Generator control panel: Prime with rust inhibiting paint and finish with oil resistant paint. .3 Colour: Manufacturer’s standard. .1 Provide the services of the manufacturer's technical representative to carry out the manufacturer's recommended field tests and to start up unit. .2 Submit a field test and start-up report to the Consultant upon completion of field tests. .1 The Contractor shall comply with the requirements of Section 01640 – Manufacturers’ Services. .2 Do not combine testing and startup with training. Testing and startup time shall not be used for manufacturer’s warranty repairs. .1 The Contractor shall provide training in accordance with Section 01820 – Demonstration and Training. EXECUTION Field Quality Control Manufacturer’s Services Training Operation and Maintenance Data .1 The Contractor shall comply with the requirements of Section 01430 – Operation and Maintenance Data. END OF SECTION CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 PART 1. 1.1 1.2 Section 16741 Page 1 of 34 GENERAL Introduction .1 The Regions’ facility is a sewage pumping station. The plant operates 24hrs/Day, 7 Days/week. The network follows a hub and spoke topology. The structured cabling system shall service the entire Leslie Street Sewage Pumping Station. .2 This communications system must satisfy the requirements of the Ethernet/IP based integrated Supervisory Control and Data Acquisition (SCADA) network used for the pump station processes and where communication systems are specified elsewhere within the Contract Documents. .1 The following definitions shall apply throughout this Section: .1 “Structured Cabling System (SCS)” refers to the site’s telecommunications cabling infrastructure which consists of the following subsystems: network room, fiber-optic trunk cabling, fiber-optic backbone cabling, horizontal cabling system and Work Area Outlets. .2 “Fiber-Optic Trunk Cabling” refers to the trunk cabling providing interconnection between network core switch. The trunk consists of the trunk cables, mechanical terminations and patch cords or jumpers used for crossconnection. .3 “Fiber-Optic Backbone Cabling” refers to the backbone cabling providing interconnection between the Network Access Closets (NAC) and the network core switch. It consists of the backbone cables, mechanical terminations and patch cords or jumpers used for backbone-tobackbone cross-connection. .4 “Horizontal Cabling System” refers to the horizontal cabling (copper Ethernet cables) extending from the Work Area Outlet (WAO) to the Network Access Closet (NAC) and Remote I/O (RIO) panels. The system consists of horizontal cabling, Work Area Outlets, cable terminations and cross-connections. .5 “Station Cable” refers to the connection between the Work Area Outlet and the end field device (i.e. PLC, OIT, etc.). It consists of cords, adapters, and other transmission electronics. .6 “Work Area Outlet” provides the cross-connect between the horizontal cabling system and the station cable. .7 “Pathways” provide network connectivity between two or more points. .8 “Spaces” are the rooms and areas where media is terminated and/or communications equipment is installed. Definitions CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .9 .10 .11 .12 .13 1.3 1.4 Section 16741 Page 2 of 34 “Network Core Switch Closet”: A 48 cm (19 inch) rack enclosure constructed to support the termination of cables (fiber-optic, CAT6 UTP and power) and the installation of Cisco Systems, Inc. Catalyst 4506 Ethernet Switch(es) referred to as core switch(es). “Network Access Closet (NAC)”: A 48 cm (19 inch) rack enclosure constructed to support the termination of cables (fiber-optic, CAT6 UTP, power) and the installation of Cisco Systems, Inc. Catalyst 2960 Ethernet Switch(es). Network Access Closets are installed in the process areas and provide connectivity of the end field devices (i.e. Programmable Automation Controller (PAC) enclosure ,PLC, HMI, VFD’s, etc.) to the Network Core Switch. “Network Core Switch Fiber Patch Panel Closet”: A 48 cm (19 inch) rack enclosure constructed to support the termination of the fiber-optic backbone cables. The enclosure is installed in the SCADA Server Room. Fiber optic patch cables are used to interconnect the Cisco Systems, Inc. Catalyst 4506 core switch in the Network Core Switch Closet with the fiber-optic patch enclosures in the Network Core Switch Fiber Patch Closet. “UTP” : Un-shielded Twisted Pair “SCADA Server Closet”: A 48 cm (19 inch) enclosure constructed to support the installation of computer servers and associated hardware. The enclosure is located within the SCADA Server Room. Order of Precedence .1 If the requirements of this Section and other Sections in the Specifications are in conflict, the requirements of this Section shall take precedence. The Contractor shall meet or exceed the requirements for the cabling system described in this Section. .2 Where manufacturer and model numbers are provided within the Contract Drawings for network related equipment and the same equipment is specified within these Specifications, the manufacturer and model number specified within the Contract Drawings shall take precedence. .1 The complete cabling system shall be supported by a system warranty. .2 The communications system requires a structured cabling system and associated enclosures and components. .3 After installation, submit all documentation to support the warranty in accordance with the manufacturer’s warranty requirements, and to apply for said warranty on behalf of the Region within the requirements stipulated by the manufacturer’s warranty. The Warranty CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 Section 16741 Page 3 of 34 warranty will cover the components and labour associated with the repair/replacement of any failed link, within the warranty period. 1.5 .4 Where the Contractor selects the Product, ensure that the Products/components of the cable system are eligible for the 20 year certification provided by the cabling system Subcontractor (as described in subsection 1.4.7 below) and include the warranties as described herein. Ensure that all terms and conditions of the cabling system manufacturer are satisfied and complete. .5 The Contractor shall ensure that UTP and fiber optic cabling and components meet or exceed the specifications (including installation) of ANSI/TIA/EIA-568-B.1, 568-B.3 and 569B. .6 Performance Warranty: Provide a certified fiber optic system and copper CAT6 system warranted, by the cabling system Subcontractor and Product manufacturer, that the workmanship and materials perform in accordance with the Specifications for a period of twenty (20) years. In the event of performance degradation, the Subcontractor who is the installer shall provide necessary troubleshooting and repairs. Troubleshooting shall commence within 48 hours of notification by telephone to the Contractor; and performance required to resolve issues resulting in disruption of normal operation shall be completely restored within 120 hours of initial Contractor notification. .1 The communications system requires a structured cabling system and associated enclosures and components. .2 Furnish all labour, supervision, tooling, miscellaneous mounting hardware, enclosures and consumables for each cabling system installed. .3 Furnish and install complete with all accessories a Structured Cabling System (SCS) with enclosures and subsystem components to include cable, termination hardware, supporting hardware, and any required miscellaneous items. The SCS shall serve as a vehicle for transport of data signals throughout the network from designated demarcation points to Work Area Outlets located at various desk, workstation, control panel and other locations as indicated on the Contract Drawings and described herein. .4 Furnish and install cable and conduit for structured cabling links required under the Contract. .5 Fiber-optic backbone cable shall terminate to Network Core Switch Fiber Patch Closets located in the SCADA server room. .6 Provide all equipment and links as part of the Contract including, but not limited to, Network Access Closets, Patch Panels, Power Distribution, and Fiber-Optic Backbone Cables to areas within this Scope of Work CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 Section 16741 Page 4 of 34 Contract. Work Area Outlets, where installed outside the Instrument Control Panels, shall be furnished, wired and installed by the Contractor. 1.6 .7 The system shall utilize a network of single-mode and multi-mode fiber-optic cabling, unshielded copper Ethernet Category 6 cable (CAT6) and shielded CAT6 patch cables. Cables and terminations shall be provided and located as shown on the Contract Drawings. .8 Fiber optic cables shall terminate on fiber patch panels and/or modular patch panels located in demarcation and termination points indicated on the Specification data sheets. .9 All cables and terminations shall be identified at all locations. .10 All cables shall terminate in an alphanumeric sequence at termination locations. .11 All copper cable terminations shall comply with, and be tested to, ANSI/TIA/EIA 568-A standards for Category 6 installations. .12 Station cables shall terminate on one or two gang wall plates equipped as shown on the Contract Drawings and Specification data sheets. .13 Provide complete testing of the network cabling system, including documentation of the all tests performed with published test results. .14 Provide enclosures and mounting brackets that will contain rackmountable components listed in this Specification, the Contract Drawings, and Specifications data sheets. .15 Work with the suppliers of the Products stipulated under Division 13 – SCADA and Instrumentation; Division 11 – Equipment; Division 15 – Mechanical; and, Division 16 – Electrical to coordinate installation and terminations of the cables to patch boxes and Work Area Outlets. .16 Work with the Division 16 – Electrical, Subcontractor(s) to coordinate electrical power, conduit and trench requirements. Electrical, conduit and trench requirements for the structured cabling system described in this Specification are part of the scope of the structured cabling system. Co-ordinate with the requirements of Division 16 – Electrical, for power, conduit and trench installation details. Related Work Specified in Other Sections .1 All Work shall be completed in conjunction with the requirements of Division 1 – General Requirements, Division 11 – Equipment, Division 13 – SCADA and Instrumentation and Division 16 – Electrical. CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 1.7 1.8 1.9 Section 16741 Page 5 of 34 Applicable Documents .1 The cabling system described in this Specification is derived in part from the recommendations made in industry standard documents. .2 Conform to the requirements of the most recent release of the following: .1 Ontario Electrical Safety Code .2 TIA/EIA-568-B: Telecommunications Cabling Standard. Standards referenced within the TIA/EIA-568-B, where applicable, constitute standard provisions of this Specification. Furthermore, compliance with the Ontario Electrical Safety Code will supersede all other Specifications. .3 TIA/EIA-526-14-A: Optical Power Loss Measurement, Multimode .4 TIA/EIA-526-7: Optical Power Loss Measurement, Singlemode .5 TIA/EIA-606: Administration Standard for the Telecommunications .6 TIA/EIA-607: Commercial Building Grounding and Bonding Requirements for Telecommunications .3 If a conflict exists between the requirements of any of the above documents and the requirements of the Contract, then the more stringent requirement shall apply. .1 The Work outlined in this Section shall be included in the lump sum price for Section 16741 – Structured Cabling Systems and Enclosures as indicated in Schedule ‘A’ of the Bid Form. .1 It is critical for on-going management of the data systems that the Region have up-to-date and accurate records of all Work performed by the Contractor. .2 Work area outlets and patch boxes together with jack numbers shall be marked on the Drawings with the location of each work area outlet. .3 Upon completion of the Contract, the Contractor shall provide “asbuilt” records of actual jack and patch box locations, cable run pathways, identification labels, and test results. .4 The documentation shall be submitted in a printed paper format, an electronic ‘pdf’ format, and an electronic editable version. .5 Portfolio .1 Within thirty (30) Days of the notification of award of the Contract, and prior to submittal of the network shop Measurement and Payment Submittals CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .2 .6 Section 16741 Page 6 of 34 drawings, submit a portfolio of the proposed Network Installer (NI) for review by the Consultant. This portfolio is to contain documentation demonstrating that the proposed NI has an up to date certification status with Building Industry Consulting Service International (BICSI) and the manufacturers. Include the following in the portfolio: 1. Letter(s) and/or certificate(s) attesting that the installer’s personnel are current members of the BICSI Telecommunications Association; and 2. Letter(s) and/or certificate(s) on the letterhead of each manufacturer attesting that the installer’s personnel are certified by the manufacturer to install their Products. Obtaining successful review of the portfolio is a prerequisite to submitting Shop Drawings. Shop Drawings: .1 Submit shop drawings in accordance with Section 01300 – Submittals. .2 Determine the exact detailed routing paths for cabling within this Specification. Submit these detailed routing drawings to the Consultant for review and approval. .3 Submit shop drawings to the Consultant for review and approval containing quantities and Product data sheets before ordering. .4 Confirm the list of rack components from the Consultant on Site, and submit the Network Room Closet Enclosure rack layout, and plant area Wall-mounted Closet Enclosure layouts, to the Consultant for review and approval before ordering. .5 Submit Typical Work Area Outlet Wiring Drawing to the Consultant for review and approval. The Contractor shall submit, to the Consultant, factory test .6 information prior to installation. .7 Submit Structured Cabling Interconnection/Block Diagram: show interconnection from core switch, through patch panels and industrial switches, to IP end devices, such as computers, controllers, operator interface terminals, etc. Identify network locations such as enclosures with building, room, enclosure name. Identify quantity of cables in each link and quantity and type of IP end devices. Provide a cable schedule showing cable identification, fiber strand counts for each cable, and identification of used fiber pairs, and cable lengths. .8 Submit Cable Schedule/Wiring and Labeling Tables: identify and label network links. Identify terminal receptacles, cable ID tags, enclosure tags, patch panels, adapter plates, patch cord tags, actual cable lengths and maximum distance limitations for each link. CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .9 .10 .11 .12 .13 .14 .15 .16 .17 Section 16741 Page 7 of 34 Submit an overview of the structured cabling system and include description of labeling scheme applied for wire labeling. Submit power connection diagram: show interconnection from power sources, through uninterruptible power supplies and power distribution panels, to computers/servers, peripherals and network equipment (routers, switches and media converters). Submit Grounding Diagram: show grounding philosophy and implementation for access closet enclosures and network equipment. Submit Drawings indicating conduit/cable pathway/routing and terminations including patch boxes and work area outlets complete with labels. Submit Drawings indicating all port assignments for CAT6 and fiber. Refer to the Contract Drawings - Typical Port Assignment Drawings for the format. Submit network wiring table spreadsheets in Excel format listing all structured cabling components and cabling source and destination connections for each fiber optic cable transmit and receive pair for trunk, backbone and horizontal cabling and each CAT6 horizontal cable, and also include each fiber optic patch cord, each CAT6 patch cord, each work area outlet, each patch panel port and each network equipment switch port. These plant communications wiring tables shall be provided to the Consultant for pre-approval. Submit enclosures and mounting brackets that will contain all rack-mountable components listed in this Specification, the Drawings, and the Specification data sheets. Submit Site Layout Network Diagram showing: 1. Access holes with identification. 2. Above grade cable routings, with pole and cable identification. 3. Below grade conduit routings between access holes and buildings with conduit counts and identification. 4. Cable routing through innerducts and to patch panels, fiber centres, or network nodes, with cable and node identification. Test Documentation: 1. Submit documentation as defined in this subsection. 2. Submit test results showing Cable identification, fiber strand counts for each cable, identification of used fiber pairs, cable length and attenuation, and planned number for splices, based on TIA/EIA 568, Annex H. CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 Section 16741 Page 8 of 34 3. .18 .7 Submit “Manufacturer’s Certificate of Proper Installation”, conforming to the requirements of Section 01640 – Manufacturers’ Services. 4. Operation and Maintenance Data: As specified in Section 01430 – Operation and Maintenance Data, including the following: .1 Updated versions of Hardware Shop Drawings Submittals. .2 Component Manufacturers’ O&M Manuals: Instructions for installation, operation, maintenance, and troubleshooting. .3 List of spare parts provided. .4 List of recommended additional spare parts. Installation Certification Documentation: 1. Copy of the Ethernet cable installer’s factory certified installation certificate. Certificate shall have the name of the person who completed the training course and that person shall supervise all cable installation and termination for compliance with manufacturer recommendations. 2. Structured Cabling System Material and Installation Manufacturer’s Warranty. As-Built: .1 Provide shop drawings to the Region at the conclusion of the Contract. The marked up drawing set will accurately depict the as-built status of the system including termination locations, cable routing, and administration labeling for the cable system. .2 Submit a narrative that describes any areas of difficulty encountered during the installation that could potentially cause problems to the communications system. .3 Submit power consumption: Summary of equipment power consumption, current and voltage for connected network equipment (routers, switches, media converters) and computers, servers, peripherals and printers. Include network location (building, floor, room, enclosure/desk). .4 Submit Component Data including: 1. Manufacturer and model number. 2. General data description. 3. Engineering specifications and data sheet. 4. Scaled drawings and mounting arrangements. 5. Power and grounding requirements. 6. Electrical and network interfaces (copper and optical). .5 Submit Cable Test Results in conformance with subsection 4.7 – Cable Acceptance Testing – General. .6 Submit a FAT checklist. .7 Submit FAT documentation. CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 Section 16741 Page 9 of 34 1.10 General Requirements .1 No variations will be allowed to the planned closet termination positions of horizontal and backbone cables, and grounding conductors, unless approved in writing by the Region. .2 Fiber optic cable runs defined in this Contract are to have all fiber optic strands fully terminated and parked in bulkhead connectors. .1 The Work of this Section is to be performed by a member of the BICSI Telecommunications Association. .2 The Work of this Section is to be performed by personnel certified by the manufacturer of the Products being installed. Certification is to include all aspects of design, installation and testing of the Products described herein. .3 Obtain a letter or certificate, on the letterhead of each manufacturer, attesting that the installer’s personnel are certified to install the Products. Submit each letter prior to submitting shop drawings. .4 The Contractor shall utilize the authorized manufacturer components and distribution channels in completing this Work. .5 The Contractor shall have a minimum of five (5) years of experience in installing structured cabling systems of similar type and size. .6 The Contractor shall be experienced in all aspects of this Work and shall be required to demonstrate direct experience on systems of similar type and size. .7 The Contractor shall own and maintain tools and equipment necessary for successful installation and testing of optical, Category 6 and fiber optic premise distribution systems. .8 The Contractor shall have personnel who are adequately trained in the usage of such tools and equipment.. .9 Any Subcontractor, who will assist the Contractor in performance of this Work, shall have the same training and certification as the Contractor. 1.11 Qualifications 1.12 Project Management Requirements .1 The Contractor’s Network Supplier/Subcontractor shall provide a project manager who shall act as a single point of contact for all activities regarding network cabling for this Contract. The project manager shall have the authority to make on-Site decisions regarding the scope of the Work and ad hoc, minor changes that may be required. CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .2 Section 16741 Page 10 of 34 The Region, in turn, shall appoint a Regional Representative who will have the corresponding role on behalf of the Region. 1.13 Planning Meetings and Schedule .1 An initial planning meeting will be held with the Contractor to: .1 Clarify all requirements (systems, services, distribution methods, etc.); .2 Identify responsibilities; and .3 Schedule the events that will transpire during the implementation of the Contract. .2 The Contractor shall attend subsequent follow-up meetings as needed and as requested by the Region for coordination and planning efforts. PART 2. NETWORK COMPONENT IDENTIFICATION 2.1 2.2 General .1 The requirements of this Section will take precedence over the requirements of other Sections, with respect to network component identification. .2 The labeling of PCS network components, structured cabling and cable routing shall comply with the TIA/EIA-606 standard. .3 The codification of network components, cables and cable routing shall follow the identification standards detailed in this Specification Section. .4 Utilize the cable labeling and management software product manufactured by: LabelMark, Brady Corporation. (www.bradylabelmark.com). .1 Network Closet Identification .1 Network Closet identification is required for Network Access Closets, Server Closets, Network Core Switch Closets and Network Core Switch Fiber Patch Panel Closets. .2 Provide a nameplate for each closet on the top-left corner of the door. .3 Use engraved Gravoply laminate nameplates having white letters on black background. Minimum nameplate height shall be 50 mm. Minimum character height shall be 12 mm. .4 Mount nameplates with adhesive backing. .5 Centre lettering on each line. .6 Include device identification (tag) number as well as a descriptive name identifying the type of closet (Access, Core, Server, Fiber Patch). For example: the tag name: Closet Identification CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .7 .8 .9 .10 .11 .2 Section 16741 Page 11 of 34 DC-STR-COM-0500 followed by the description: ACCESS CLOSET. All network closet tags utilize a four-digit device number (XXYY). The first two numbers (XX) identify the closet and the last two numbers (YY) identify sub-devices. For closets the last two numbers (YY) are always zero (00). For example DC-STR-COM-0500 for SECONDARY TREATMENT CLOSET 0500. All Server Closet tags utilize a four-digit device number (XXYY). The first two numbers (XX) identify the closet and the last two numbers (YY) identify sub-devices. For closets the last two numbers (YY) are always zero (00). For example DC-AD-SRV-0100 for ADMINISTRATION BUILDING SERVER CLOSET 0100. Network Core Switch and Server Closets in the Network room are numbered from (01YY) to (10YY). Work Area Outlets, installed outside of Instrument Control Panels, and associated with a Network Closet, shall utilize the first two digits (XX) as the closet. The last two numbers (YY) are used in consecutive order (starting at zero) to uniquely identify the Work Area Outlet. For example the first Work Area Outlet associated with Secondary Treatment Access Closet 0500 (DC-STR-COM-0500) would be tagged as DC-STR-COM-0501-WA01. Work Area Outlets, installed inside Instrument Control Panels, associated with a Network Closet utilize the same digits as the Instrument Control Panel. For example the first Work Area Outlet associated with Secondary Treatment Instrument Control Panel 0500 (DC-STR-ICP0500) would be tagged as DC-STR-ICP-0500-WA01. UTP and Fiber Patch Panels .1 Labels for patch panels shall be laser printed, selflaminating, adhesive, polyester or polyolefin. Hand-written labels will not be accepted. .2 Lettering shall be black on a white background. Characters shall be a minimum of 6 mm high. .3 Labels shall be applied to patch panels in such a manner as to be readily visible and not obscured by structured cabling or patch cords. .4 The tagging convention for Network Closet patch panels will employ a four (4) character alphanumeric tag. The first two characters will indicate the type of patch panel. The second two characters will be a unique index within each closet starting from the top of the closet. The characters “CP” will denote Copper Ethernet Patch Panels. The characters “FP” will denote Fiber Patch Panels. For example the second patch panel from the top in Network Access Closet 0500 would be labelled CP02. CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 Section 16741 Page 12 of 34 .3 UTP Patch Panel Termination Point .1 Each 24-port or 48-port patch panel will be logically separated into groups of four terminations. Each logical group will be associated with a 4-port Work Area Outlet, 8port Work Area Outlet or another 24-port patch panel logical group. .2 Labels for each 4-port or 8-port logical group shall be laser printed, self-laminating, adhesive, polyester or polyolefin. Hand-written labels will not be accepted. .3 Lettering shall be black on a white background. Characters shall be a minimum of 4 mm high. .4 A label shall be applied to the top of each 4-port or 8-port logical group indicating the destination of the logical group. For example: a 4-port, logical group whose destination is Instrument Control Panel DC-STR-ICP-0500, Work Area Outlet 1 would be tagged as DC-STR-ICP-0500-WA01. .5 Provide a three-character label immediately beneath each port indicating its network membership. SPR indicates that the port is allocated as spare. MNT indicates that the port is allocated to maintenance. AMS indicates that the port is allocated for the asset management system. PMR indicates that the port is allocated for the power monitoring system. .6 Provide colour-coded, snap-in icons for each port (RJ). The following colours will indicate network membership: PLC/HMI (red), MNT (blue), AMS (green), PMR (yellow), RIO (orange) and SPARE (white). .4 Fiber Optic Patch Panel Termination Point .1 Terminate all strands of each fiber optic cable in either 36/72 Fiber Enclosures (Network Access Closet) or 72/144 Fiber Enclosures (Network Core Switch Fiber Patch Panel Closet). .2 The ordering and colour of individual fibers will be the same for each fiber cable and shall be compliant with TIA/EIA-568-B. .3 Labels shall be laser printed, self-laminating, adhesive, polyester or polyolefin. Hand-written labels will not be accepted. .4 Lettering shall be black on a white background. Characters shall be a minimum of 4 mm high. A label shall be applied to the top of the ST simplex fiber .5 adapter panel modules associated with a single fiber cable indicating the destination of the cable. For example the adapter modules that terminate the fiber cable whose destination is Secondary Treatment Access Closet 0500 would be labeled as DC-STR-COM-0500. .6 A three-character label shall be applied, that indicates the network membership (PLC/HMI, MNT, AMS, PMR, RIO, or CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 Section 16741 Page 13 of 34 SPR), either directly on the adapter module or on the cable position map. SPR indicates that the port is allocated as spare. MNT indicates that the port is allocated to maintenance. AMS indicates that the port is allocated for the asset management system. PMR indicates that the port is allocated for the power monitoring system. 2.3 .5 Work Area Outlet .1 Labels for each 4-port or 8-port work area outlet shall be laser printed, self-laminating, adhesive, polyester or polyolefin. Hand-written labels will not be accepted. .2 Lettering shall be black on a white background. Characters shall be a minimum of 4 mm high. A label shall be applied to the top of each 4-port or 8-port .3 Work Area Outlet indicating the source of the horizontal cables. For example: a 4-port, Work Area Outlet in Instrument Control Panel DC-STR-ICP-0500 connected to the first copper Ethernet patch panel in Secondary Treatment Access Closet 0500 would be labeled as DCSTR-COM-0500-CP01. .4 A three-character label shall be applied immediately beneath or above each port (RJ) indicating its network membership (PLC/HMI, MNT, AMS, PMR, RIO, or SPR). SPR indicates that the port is allocated as spare. MNT indicates that the port is allocated to maintenance. AMS indicates that the port is allocated for the asset management system. PMR indicates that the port is allocated for the power monitoring system. .5 Provide colour-coded, snap-in icons for each port (RJ). The following colours will indicate network membership: PLC/HMI (red), MNT (blue), AMS (green), PMR (yellow), RIO (orange), and SPARE (white). .1 Use durable non-fading sleeve type wire markers to identify network cables. .2 Labels for cabling shall be laser printed, self-laminating, adhesive, polyester (indoor/outdoor). Hand-written labels will not be accepted. .3 Lettering shall be black on a white background. Characters shall be a minimum of 4 mm in height. .4 Fiber Optic Backbone Cables .1 As a minimum, fiber optic backbone cables are to be labeled at both ends of the cable. In addition, the fiber backbone cables are to be labeled at .2 each transition. A transition is defined as: a change in ducting (e.g. cable tray to conduit), a change in direction of Network Cable Identification CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .3 .4 .5 Section 16741 Page 14 of 34 more than 45 degrees, or an entrance and exit of ducting through a wall or floor. If a single fiber cable is run in conduit then the transition labels shall be applied to the conduit. If multiple fiber cables are run in the same conduit then the transition labels shall be applied to the individual fiber cables. The tagging convention for identification of fiber optic backbone cables shall indicate the source and destination of the cable separated by a colon. For example a fiber optic backbone cable whose source is Network Core Switch Fiber Patch Panel Closet (DC—AD-COM-0200), Fiber Patch Panel #1 and terminates in Secondary Treatment Network Access Closet 0500 (DC-STR-COM0500) would have the following tag: DC-AD-COM-0200-FP01 : DC-STR-COM-0500-FP01 .5 Horizontal Cables .1 As a minimum, horizontal CAT6 cable is to be labeled at both ends of the cable. .2 The tagging convention for identification of Horizontal cables shall indicate the source and destination of the cable separated by a colon. Example 1: a horizontal cable whose source is Secondary Treatment Access Closet 0500 (DC-STR-COM-0500), UTP Patch Panel #1 (CP01), Position #10 and whose destination is Position #2, Work Area Outlet #1, in Instrument Control Panel DC-STR-ICP0500 would have the following tag: DC-STR-COM-0500-CP01-10: DC-STR-ICP-0500-WA0102 .3 Example 2: a horizontal cable whose source is Network Core Switch Fiber Patch Panel Closet 0200 (DC-AD-COM0200), UTP Patch Panel #2, Position #8 and whose destination is Position #5, UTP Patch Panel #1, in SCADA Server Closet 0100 (DC-AD-SRV-0100) would have the following tag: DC-AD-COM-0200-CP02-08: DC-AD-SRV-0100-CP01-05 .6 Patch Cords .1 As a minimum, Contractor installed CAT6 and fiber optic patch cords shall be labeled at both ends of the cable. .2 Provide colour-coded cable jackets and plug-boots to indicate network membership: PLC/HMI (red), MNT (blue), AMS (green) and PMR (yellow), and RIO (orange). CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .3 Section 16741 Page 15 of 34 The tagging convention for identification of patch cords shall indicate the source and destination of the cable separated by a colon. The source is the switch port and the destination is the patch panel, termination point. Example 1: a horizontal cable whose source is Secondary Treatment Access Closet 0500 (DC-STR-COM-0500) switch port #1 and whose destination is Secondary Treatment Access Closet 0500 (DC-STR-COM-0500), UTP Patch Panel #1 (CP01), Position #10. DC-STR-COM-0500-SW01-01: DC-STR-COM-0500CP01-10 SW shall be used to indicate a copper Ethernet switch port. UP shall be used to indicate the uplink port on the switch. .7 Cable Routing .1 All ducting (cable tray or conduit) carrying fiber optic backbone cable shall be tagged as “PCS LAN BACKBONE”. .2 All ducting carrying Horizontal cables shall be tagged as “PCS LAN HORIZONTAL”. .1 Provide fiber optic cable, connectors and appurtenances that make up the backbone cable segments. .2 The fiber optic backbone cable segments shall meet the requirements of the TIA/EIA-568-B specification for 62.5 micron multi-mode fiber and single-mode fiber. .3 Fiber optic backbone cable shall meet or exceed the following minimum requirements: .1 24 Fibers per Cable. .2 Quantity 12 – 62.5 micron multimode fiber strands. .3 Quantity 12 – 8 to 9 micron single-mode fiber strands. .4 Indoor/Outdoor Rating. .5 Core-locked, Tight-buffered. .6 62.5/125 micron Core/Cladding for multi-mode fiber. .7 385 MHz-km Bandwidth at 850 nm wavelength for multimode fiber. .8 500 MHz-km Bandwidth at 1300 nm wavelength for multimode fiber. .9 Riser-Rated (FT4) inner and outer PVC jackets (Optical Cable Corporation DX series). .4 The fiber optic cable shall be Optical Cable Corporation DX-Series Distribution cable, model DX24-085D-12WLX-12SLX/900-OFNRWB or an approved equal. PART 3. PRODUCTS 3.1 Fiber Optic Backbone Cable CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 3.2 3.3 Section 16741 Page 16 of 34 Fiber Optic Horizontal Cable .1 Fiber optic cable is to be provided for horizontal network cable runs which exceed 90 metres or for transitions from indoor to outdoor locations. .2 The fiber optic horizontal cable segments shall meet the requirements of the TIA/EIA-568-B specification for 62.5 micron multi-mode fiber. .3 Fiber optic horizontal cable shall meet or exceed the following minimum requirements: .1 Quantity 6 – 62.5 micron multimode fiber strands. .2 Indoor/Outdoor Rating. .3 Core-locked, tight-buffered. .4 62.5/125 micron core/cladding for multi-mode fiber. .5 385 MHz-km Bandwidth at 850 nm wavelength for multimode fiber. .6 500 MHz-km Bandwidth at 1300 nm wavelength for multimode fiber. .7 Riser-Rated (FT4) inner and outer PVC jackets (Optical Cable Corporation DX series). .4 The fiber optic cable shall be Optical Cable Corporation DX-Series Distribution cable, model DX06-055D-6WLX-OFNR-WB or an approved equal. .1 All connectors for the termination of the fiber optic backbone or horizontal cable shall be duplex SC connectors. .2 For multimode fiber optic terminations inside Network Access Closet Fiber Patch Panels the connectors shall be preloaded adapters configured with 3 SC duplex multimode adapters fitted with a bronze split sleeve. SC connectors shall be Panduit Corp. Catalogue No. FAP3WEIDSC. .3 For single-mode fiber optic terminations inside Network Access Closet Fiber Patch Panels the connectors shall be preloaded adapters configured with 3 SC duplex single-mode adapters fitted with a zirconia ceramic split sleeve. SC connectors shall be Panduit Corp. Catalogue No. FAP3WBUDSCZ or approved equal. .4 For multimode fiber optic terminations inside Network Core Switch Fiber Patch Panel Closets the connectors shall be preloaded adapters configured with 6 SC duplex multimode adapters fitted with a bronze split sleeve. SC connectors shall be Panduit Corp. Catalogue No. FAP6WEIDSC or approved equal. .5 For single-mode fiber optic terminations inside Network Core Switch Fiber Patch Panel Closets the connectors shall be preloaded adapters configured with 6 SC duplex single-mode adapters filled with a zirconia ceramic split sleeve. SC connectors Fiber Optic Connectors CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 Section 16741 Page 17 of 34 shall be Panduit Corp. Catalogue No. FAP6WBUDSCZ or approved equal. 3.4 Corrugated Split-Loom HDPE Conduit .1 3.5 3.6 Corrugated split-loom HDPE conduit shall meet or exceed the following minimum requirements: .1 Orange coloured 47.8 mm (1.881 in) Minimum ID (inner diameter) .2 .3 55.1 mm (2.169 in) Average OD (outer diameter) .4 Material to be polyethylene .5 The HDPE conduit shall be Panduit Corp. Corrugated Loom Tubing CLT188F-6C3 or an approved equal Corrugated Solid HDPE Conduit .1 Corrugated solid HDPE conduit shall meet or exceed the following minimum requirements: .1 Orange coloured .2 Average OD (outer diameter) shall not be less than 25.4 mm (1 in) .3 Conduit average OD to be sized appropriately for the number of fiber-optic cables while maintaining a 50 percent spare fill ratio. .4 Material to be polyethylene .5 Riser rated .6 The HDPE conduit shall be Eastern Wire and Conduit Protect-N-Duct Riser PDRUXXXX or an approved equal. .1 Provide twisted-pair cable, connectors and appurtenances that make up the horizontal cable segments. .2 Horizontal cable segments shall meet the requirements of the TIA/EIA-568-B specification for Category 6 (CAT6), Unshielded Twisted Pair (UTP) cable. .3 Horizontal cable segments shall meet or exceed the following minimum requirements: .1 The cable shall be tested up to 200 MHz with a guaranteed performance that meets or exceeds the ANSI/TIA/EIA568B/ISO/IEC 11801 horizontal cable requirements for PSNEXT, attenuation, structural return loss, and attenuationto-crosstalk ratio (ACR). .2 The cable shall be constructed from 0.54 mm (24AWG), bare copper wire insulated. Two insulated conductors twisted together to form a pair and four pairs laid up to form the basic unit. UTP Horizontal Cable CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .3 .4 .5 .6 .7 3.7 3.8 Section 16741 Page 18 of 34 The cable shall be jacketed in flame-retardant PVC. Cable run in conduit shall meet or exceed FT4 rating. Cable not run in conduit shall meet or exceed FT6 rating. Horizontal cable (except for remote I/O) run in conduit shall be Belden Inc. Catalogue No.. 24566945 or approved equivalent. Horizontal cable (except for remote I/O) not run in conduit shall be FT6 rated Belden Inc. Catalogue No. 24567945 or approved equivalent. For Remote I/O, horizontal cable run in conduit shall be orange in colour, Belden Inc. Catalogue No. 25066515 or approved equivalent. For Remote I/O, horizontal cable not run in conduit shall be orange in colour and FT6 rated Belden Inc. Catalogue No. 25067545 or approved equivalent. STP Horizontal Cable .1 Provide twisted-pair cable connectors and appurtenances that make up the horizontal cable segments. .2 Horizontal cable segments shall meet the requirements of the TIA/EIA-568-B specification for Category 6 (CAT6), Shielded Twisted Pair (STP) cable. .3 Horizontal Cable Segments shall meet or exceed the following minimum requirements: .1 The cable shall be tested up to 200 MHz with a guaranteed performance that meets or exceeds the ANSI/TIA/EIA568B/ISO/IEC 11801 horizontal cable requirements for PSNEXT, attenuation, structural return loss, and attenuationto-crosstalk ratio (ACR). .2 The cable shall be constructed from 0.54 mm (24AWG), bare copper wire insulated. Two insulated conductors shall be twisted together to form a pair and four pairs laid up to form the basic unit. .3 The cable shall be shielded with an overall aluminum tape with stranded tinned copper drain wire. The cable shall be jacketed in flame-retardant PVC. Cable .4 run in conduit shall meet or exceed the FT4 rating. Cable not run in conduit shall meet or exceed the FT6 rating. .5 The cable shall be orange in colour for remote I/O and blue for other applications. .1 All Category 6 (CAT6) UTP horizontal connectors shall be unshielded modular jacks.. .2 CAT6 connectors shall meet or exceed the following minimum requirements: UTP Horizontal Connectors. CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .1 .2 .3 .4 .5 .6 3.9 Section 16741 Page 19 of 34 Eight position modular jacks shall meet or exceed the TIA/EIA Category 6 standard. The jack termination to 4 pair 24 AWG unshielded twisted pair cable shall not require the use of a punch down tool. The jack shall limit conductor untwist to less than 23 mm (½ inch). The jack shall be IEC 60603-7 compliant. The jack shall accommodate icons for network identification. The jack shall support gigabit Ethernet. STP Horizontal Connectors. .1 All category 6 (CAT6) STP horizontal connectors shall be shielded modular jacks wired for a T586A wire-map. Each shielded jack is to be individually bonded to a ground. .2 CAT6 STP connectors shall meet or exceed the following minimum requirements: .1 Eight position modular jacks shall meet or exceed the TIA/EIA Category 6 standard. .2 The jack termination to 4 pair 24 AWG Shielded twisted pair cable shall not require the use of a punch down tool. .3 The jack shall limit conductor untwist to less than 12 mm (½ inch). .4 The jack shall be IEC 60603-7 compliant. .5 The jack shall accommodate icons for network identification. .6 The shielded jack must include a cable strain relief cap, TIA/EIA 607 compliant grounding, bonding metallic housing and ground termination. .7 The jack shall support gigabit Ethernet. 3.10 General Enclosure Requirements .1 Unless otherwise specified in the Contract Documents, indoor enclosures containing network components are to be NEMA 4. .2 Screws, bolts, fasteners, etc., are to be corrosion resistant stainless steel. .3 Doors are to have continuous hinges with removable pin and oil resistance cellular neoprene gasket secured by gasket retainers. .4 Cable bundles are to be neatly laced, routed in ducting or cable managers approved by the Region and secured to 48 cm (19 inch) rack or mounting back-panel. .5 Enclosure doors shall open through 180 degrees without restriction. .6 Enclosure layout and equipment spacing shall be constructed to allow for device removal, calibration and maintenance without disassembly of adjacent devices. CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 Section 16741 Page 20 of 34 .7 Enclosures shall have sufficient structural reinforcements to ensure a limited plane surface vibration and to provide rigidity during shipment, installation and operation without distortion or damage to the enclosure, mounting panel or mounted instruments. .8 Enclosure seams shall be continuously welded and ground smooth to be undetectable after painting. .9 Devices shall be installed on the enclosure back-panel or 48 cm (19 inch) rack. .10 There shall be no devices installed on the side plates of the enclosure. .1 All enclosure wiring shall run through a cable manager. .2 Cable managers shall not be filled to more than 50 percent of their volume upon initial installation. .3 Wires and cables, including spares, shall be identified at each end and at any connection. Use durable non-fading sleeve type wire markers to identify network cables as follows: .1 Labels for cabling shall be laser printed, self-laminating, adhesive, polyester (indoor/outdoor). .2 Hand-written labels will not be accepted. .3 Lettering shall be black on a white background. Characters shall be a minimum of 4 mm high. .4 Wire markers are required on each conductor in panel board gutters, and at load connections. The identification shall include branch circuit or feeder number for power and lighting circuits, and control wire numbers for control wiring. .5 All field wires and cables terminated within enclosures shall be identified at each termination with a marking that corresponds with the Drawings and supporting documentation. .1 Provide Network Access Closets in the locations identified in the SCADA Network Drawings. Construct Access Closets to support the termination of cables (fiber optic, CAT6 UTP, power) and the installation of Cisco Systems, Inc. Catalyst 2960 Ethernet Switches. .2 Provide Network Access Closets in accordance with the Typical Network Access Closet as shown on the Contact Drawings. .3 Network Access Closet enclosures shall meet or exceed the following minimum requirements 3.11 Enclosure Wiring 3.12 Network Access Closets CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .1 .2 .3 .4 .5 Section 16741 Page 21 of 34 Outside dimensions of 750 mm (30 inch) Height x 600 mm (24 inch) Width x 600 mm (24 inch) Depth 14 gauge steel, smooth continuously welded seams. Oil resistant gasket. ¼ turn latch capable of being padlocked. NEMA 4 rating. .4 Network Access Closets shall be Hoffman Enclosure Inc. NEMA 4 DataCom Series PTDHS362424G4 or approved equal. .5 Network Access Closets located in corrosive environments shall be constructed from stainless steel. .6 Provide a 19 unit (U), 48 cm (19 inch) rack for the mounting of 48 cm (19 inch) rack mountable components. The front of the 48 cm (19 inch) rack is to be recessed 50 mm (2 inch) from the front of the enclosure. .7 Bond 48 cm (19 inch) rack to ground. .8 Provide a rack mount, fiber optic enclosure for termination of the fiber optic cable within the Network Access Closet. .9 The fiber optic enclosure shall meet or exceed the following minimum requirements: .1 The fiber optic enclosure shall include a slide-out/tilt-down drawer for front access of the terminations. .2 The fiber optic enclosure shall include integrated bendradius managers for patch cords and backbone cable. .3 The fiber optic enclosure shall support 36 or 72 SC connectors. .10 The fiber optic enclosure shall be Panduit Corp. Catalogue No. FRME3 or approved equal. .11 The Contractor is to ensure that installation of the fiber optic enclosure allows the sliding drawer to be fully extended and lowered without interference from, or to, other components. .12 Fiber optic connectors shall be duplex SC style connectors. Fiber optic termination panels shall be Panduit Corp. Catalogue No. FAP6WEID or approved equal for multimode fiber. Fiber optic termination panels shall be Panduit Corp. Catalogue No. FAP3WBUDZ or approved equal for single-mode fiber. .13 Provide two (2) 48-port modular patch panels, connectors and appurtenances for termination of the unshielded twisted pair (UTP) within each Network Access Closet. .1 The connection between the 2960 Ethernet Switch and UTP horizontal cable is an inter-connect rather than a cross-connect. .2 All 48-port modular patch panels shall be Panduit Corp. Catalogue No. DP48688TGY or approved equal. .3 Rack mounted ground bars shall be Panduit Corp. Catalogue No. TRGB19 or approved equal. CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 Section 16741 Page 22 of 34 .14 The Catalyst 2960 switches shall have the following environmental and power requirements: .1 Operating Temperature: 0 to 45 degrees Celsius (C). .2 Power consumption with a single module is 30 W. .3 All of the Network Access Closets are located indoors, therefore ambient temperatures below 0 degrees Celsius are not a concern. Provide ventilating fans and associated controls where .4 noted on the Contract Drawings. Control the ventilating fans using thermostatic controls. .15 Provide two (2) duplex SC-to-LC fiber optic patch cords for each 2960 Ethernet Switch. Fiber optic patch cables shall be terminated at one end with a duplex SC style plug and at the other with an LC style plugs. .16 Fiber optic patch cords are to be factory assembled and tested by the manufacturer. Provide written certification from the manufacturer indicating the factory test results. The Contractor is responsible for determining the length of patch cords. .17 Supply forty-eight (48) Category 6 (CAT6), unshielded twisted pair (UTP), patch cords for each 2960 Ethernet switch installed by the Contractor. Install only those patch cords required to interconnect the 2960 Ethernet switch and Patch Panels. .18 CAT6 UTP Patch cords shall be orange in colour for remote I/O and blue for other applications. .19 Access Closets to be manufactured by one (1) of the following suppliers: .1 Black & McDonald Limited (First Named) Network Solutions Group 31 Pullman Court Scarborough, ON, M1X 1E4 Tel: (416) 366-2541 .2 Fiber Core Communications Inc. (Named Alternative) 4096 Meadowbrook Drive, Unit 119 London, ON, N6L 1G4 Tel: (519) 652-7222 .3 Quantech Electrical Contractors Ltd. (Named Alternative) 17 Guardsman Road Thornhill, ON, L3T 6L2 Tel: (905) 731-2343 .4 Selog Norteck Inc. (Named Alternative) 3190 Ridgeway Drive Mississauga, ON, L5L 5S8 Tel: (905) 608-9737 .1 Switches will be provided by the Contractor. 3.13 Catalyst Ethernet Switches CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 Section 16741 Page 23 of 34 .2 Install the switches on racks in Network Access Closets complete with UTP patch cables. .1 Provide media converters as indicated within the SCADA Drawings. .2 For fiber optic horizontal cable segments, media converters shall be installed in the Network Access Closet and, if required, in the Instrument Control Panel. Media converters shall be N-Tron Corp. Catalogue No. 102MC-ST or approved equivalent. .3 The N-Tron Corp. 102MC media converter has the following environmental and power requirements: .1 Operating Temperature: -40 to 80 degrees Celsius (C). .2 Input voltage: 10-30 VDC. .3 Input current: 140mA@24V .4 Physical dimensions: 73.1 mm (Height) x 38.1 mm (Width) x 122 mm (Depth) .5 Mounting: DIN rail .1 Work Area Outlets .1 Provide one or two 4-port, single-gang, metal Work Area Outlets, connectors and appurtenances for termination of the horizontal CAT6 UTP cables. If eight (8) CAT6 UTP cables are consolidated at the Work Area Outlet then one 8-port double gang metal work area outlet is required. .2 Each Work Area Outlet will be associated with a 4-port logical group in the Access Closet patch panel. For PLC Nodes the typical assignment for Work Area Outlets will be 1-PLC, 2-PLC, 3-AMS, 4-MNT (maintenance). .3 CAT6 unshielded modular jacks shall be Panduit Corp. Catalogue No. CJ688TGRD (red) for PLC/HMI, CJ688TGIW (white) for spare, CJ688TGGR (green) for AMS, CJ688TGYL (yellow) for PMR (power monitoring), CJ688TGOR (orange) for remote I/O, and CJ688TGBU (blue) for maintenance, or approved equal. .4 4-port outlet faceplates shall be stainless steel. Faceplates shall be Panduit Corp. Catalogue No. CFP4SY or approved equivalent. .5 8-port outlet faceplates shall be stainless steel. Faceplates shall be Panduit Corp. Catalogue No. CFP8SY or approved equivalent. .2 STP Patch Cords .1 Supply colour-coded cable jackets and plug-boots to indicate network membership: PLC/HMI (red), MNT (blue), AMS (green) and PMR (yellow), and RIO (orange). 3.14 Media Converters 3.15 Work Area Outlets CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .2 .3 Section 16741 Page 24 of 34 Supply four (4) 10 metre, CAT6 STP patch cords for each 4-port work area outlet. Supply eight (8) 10 metre, CAT6 STP patch cords for each 8-port work area outlet. Certify in writing that the patch cords supplied under this Contract meet or exceed the requirements for CAT6 STP patch cords as described in the TIA/EIA-568-B standard. PART 4. EXECUTION 4.1 4.2 General .1 Provide a complete and operational system, including all components and appurtenances necessary to ensure that the equipment is functional and meets the intent of this Specification. .2 It is the Contractor's responsibility to size power supply cables to meet the requirements of the Ontario Electrical Safety Code based on field verified length of cable run and power supply load. .3 Wall-mounted panels are to be separated from the wall by stainless steel spacers or galvanized steel struts. .1 Install network enclosures in the locations identified in the Contract Drawings. Field verify and obtain written approval from the Consultant of final locations of the enclosures prior to commencing this Work. Any costs required to relocate enclosures in unapproved locations will be the responsibility of the Contractor. .2 The Consultant reserves the right to have the Contractor relocate Network Access Closets within 3 m of the locations identified in the Contract Drawings, at no additional cost to the Region. .3 The Network Access Closet is to be mounted on stainless steel separators or galvanized struts to ensure a minimum 20 mm separation from the wall. The Network Access Closet shall be leveled against the wall using the separators. .4 All enclosure doors shall open through 180 degrees without restriction. .5 Mid-section of the enclosure shall open through 90 degrees without restriction from wall-mount section. .6 The Network Access Closets are to be installed between a maximum height of 762 mm (30 inch) from the ground and a minimum height of 610 mm (24 inch) from the ground. .7 Terminate all strands in the fiber optic enclosure. Park all strands on bulkhead connectors. Fiber colour and Transmit/Receive Tx/Rx orientation is to be identical in Network Access Closets. Terminate strands in a uniform standard colour sequence. Fibers are to be labeled. Dark fibers are to be covered to prevent Network Access Closets CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 Section 16741 Page 25 of 34 damage. Blank spaces in the breakout enclosure are to have blank covers installed. 4.3 4.4 4.5 Work Area Outlets .1 Locate Work Area Outlets such that the length of the horizontal cable runs from the Network Access Closet interconnecting to the Work Area Outlet shall be less than 90 metres. For Work Area Outlets where this proves impossible the Consultant may authorize, in writing, an exception if the link still meets the performance requirements of this Specification. .2 Install Work Area Outlets in the locations identified in the Contract Drawings. Field verify and obtain written approval from the Consultant of final locations prior to commencing this Work. All costs required to relocate Work Area Outlets in unapproved locations will be the responsibility of the Contractor. .3 The Consultant reserves the right to have the Contractor relocate Work Area Outlets within 3 m of the locations identified in the Contract Drawings at no additional cost to the Region. .1 Provide four (4) or eight (8) CAT6 UTP horizontal cables to each Work Area Outlet from a Network Access Closet in a single 35 mm (1 ¼ inch) conduit in non-corrosive environments. .2 Provide four (4) or eight (8) CAT6 STP horizontal cables to each Work Area Outlet from a Network Access Closet in single 35 mm (1 ¼ inch) conduit in corrosive environments. Corrosive environments will be noted on the Electrical Drawings. .3 Conduit carrying horizontal cables shall enter the Work Area Outlet through the top or bottom. .4 Conduit shall be galvanized rigid steel unless the environment is corrosive. Conduit running through corrosive environments shall be Rigid PVC. Cable and Conduit Fiber Optic Cable Installation – Backbone cable .1 Installation of the fiber optic backbone cable shall comply with Section 56 (Optical Fiber Cables) of the Ontario Electrical Safety Code and the EIA/TIA-568-B Telecommunications Building Standard. .2 Each fiber backbone segment shall be a continuous run (no splices) from the Network Core Switch Fiber Patch Closet to the target Network Access Closet. .3 Outdoor Fiber-Optic Backbone Conduit Installations: .1 Fiber-optic backbone cable is to be installed in corrugated split-loom HDPE conduit in outdoor electrical duct bank vaults. CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .2 .3 .4 .5 .6 .7 Section 16741 Page 26 of 34 HDPE conduit is to be installed in locations where the fiber-optic backbone cable is exposed and not protected by rigid conduit. Multiple fiber-optic backbone cables can be consolidated and protected by a single HDPE conduit. HDPE conduit is to be sized appropriately for the number of fiber-optic cables and to maintain a 50 percent spare fill ratio. HDPE conduit is to be supported by conduit hangers and supported at every one (1) metre if a cable tray does not exist. Conduit hangers are to be suspended from vault ceiling by threaded rods. Conduit hanger data sheets to be submitted to the Consultant for review prior to installation. HDPE conduit shall be inserted 0.6 m (24 inches) into electrical duct transition points. The Contractor is to submit digital photographs of the first fiber-optic backbone cable installation for the Consultant’s review and approval. As a minimum, the photographs must show labeling of the fiber-optic cable, conduit installation, conduit support and conduit labeling. The Contractor must receive written approval from the Consultant prior to continuing with the remaining Work. .4 Indoor Cable tray, Raceway and Office Environment Fiber-Optic Backbone Conduit Installations: .1 Fiber-optic backbone cable is to be installed in corrugated HDPE conduit (non split-loom) in indoor cable trays, raceways and office environments. .2 The HDPE conduit is to contain a single fiber-optic cable only. .3 HDPE conduit is to have a minimum ID (inner diameter) of 25.4 mm (1 inch). The Contractor is to submit digital photographs of the first .4 fiber-optic backbone cable installation for the Consultant’s review and approval. As a minimum, the photographs must show labeling of the fiber-optic cable, conduit installation, conduit support and conduit labeling. The Contractor must receive written approval from the Consultant prior to continuing with the remaining Work. .5 Indoor Wall, Ceiling and Industrial Environment Fiber-Optic Backbone Conduit Installations: .1 For other fiber-optic backbone cable installations, cable shall be installed in 25.4 mm (1 inch) galvanized rigid-steel conduit unless the environment is corrosive. .2 Conduit running through corrosive environments shall be rigid PVC. .3 The Contractor is to submit digital photographs of the first fiber-optic backbone cable installation for the Consultant’s CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 Section 16741 Page 27 of 34 review and approval. As a minimum, the photographs must show labeling of the fiber-optic cable, conduit installation, conduit support and conduit labeling. The Contractor must receive written approval from the Consultant prior to continuing with the remaining Work. .6 Rigid PVC, Rigid Steel or Corrugated HDPE installations: .1 Install conduit into the walls, ceilings or floors as required on the Contract Drawings. The actual route of the conduits is to be selected to avoid beams, columns and other obstructions, provided permission has been granted by the Consultant. .2 Conduit shall not interfere with the work of Other Contractors and shall be mounted over other piping where possible in parallel rows, parallel or perpendicular to walls and ceilings. Bends and offsets shall be uniform and symmetrical. The use of conduit bends shall be kept to a minimum. .3 Conduit and cables shall be installed to avoid proximity of water and heating pipes. In no case shall they run within 75 mm of such pipe, except where crossings are unavoidable, in which case they shall be kept at least 25 mm from the covering of pipe crossing. .4 For wall, ceiling or floor installations, HDPE conduit is to be anchored at every one (1) metre. .7 As a minimum, a one (1) metre loop for every 100 metres of cable length, shall be left at the end of each fiber optic backbone cable and housed in the Network Access Closet. .8 The bend radius for fiber optic backbone cable shall not be less than the manufacturer’s recommended minimum bend radius. .9 The tensile load for fiber optic backbone cable shall not exceed the manufacturer’s recommended maximum tensile load. .10 To prevent micro-bends the Contractor shall not use nylon cableties. Instead the Contractor shall use hook and loop straps to secure or collate fiber optic backbone cable. .11 Individual fiber backbone segment lengths are shown in the Site Plan and Fiber Optic Details on the Drawings. Segment lengths are estimates calculated from the Site Plan and Fiber Optic Details on the Drawings. The Layouts provided with this Contract are Reasonably-To-Scale (RTS). The Contractor is to field verify cable lengths. The recommended fiber route to the Network Access Closets is provided in the Site Plan and Fiber Optic Details on the Drawings. .12 Provide full circle and half circle coil formers at each end to coil excess fiber strands and excess fiber patch cords. .13 Labeling CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .1 .2 .3 .4 4.6 4.7 Section 16741 Page 28 of 34 Use durable non-fading sleeve type wire markers to identify network cables. Apply the tagging convention described in this Specification for Fiber Optic cables. At a minimum, label both ends of the fiber optic backbone cable. In addition, label the fiber optic cable at every 20 metres from the Network Core Switch Fiber Patch Panel Closet and at major transitions. Major transitions are defined as: the entrance and exit of a wall or floor, a change in method of ducting, or a change in direction of more than 45 degrees. Horizontal Cable Installation .1 Run horizontal cables connecting Network Access Closets to Work Area Outlets in 35 mm (1 ¼ inch) galvanized, rigid steel conduit. .2 Run either four (4) or eight (8) Horizontal cables in a conduit as noted on the Contract Drawings. .3 The bend radius for horizontal cable shall not be less than the manufacturer’s recommended minimum bend radius. .4 Horizontal cables within the network core may be run in cable tray or through conduit but must be segregated from power distribution cable. .5 Labeling .1 Use durable non-fading sleeve type wire markers to identify network cables. .2 Apply the tagging convention described in this Specification for horizontal cables. .3 At a minimum, label both ends of the horizontal cable. Cable Acceptance Testing – General .1 This Section specifies the inspection, test, and acceptance requirements for the structured cabling of the Process Control System (PCS) Local Area network. .2 Provide test equipment required to conduct acceptance tests. .3 Submit acceptance documentation as defined in this Section. .4 All of the installed cabling must be tested and successfully pass test criteria. .5 Standards referenced in this Section include: .1 TIA/EIA-568-B: Telecommunications Cabling Standard. Standards referenced within the TIA/EIA-568-B, where applicable, constitute standard provisions of this Specification. CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .2 .3 Section 16741 Page 29 of 34 TIA/EIA-526-14-A: Optical Power Loss Measurement, Multimode TIA/EIA-526-7: Optical Power Loss Measurement, Singlemode .6 Visually inspect cables, cable reels, and shipping cartons to detect possible cable damage incurred during shipping and transport. Visibly damaged goods are to be returned to the supplier and replaced at no additional cost to the Region. .7 The Region reserves the right to conduct, using the Contractor’s equipment and labour, a random re-test of up to five (5) percent of the cable plant to confirm documented results. Any failed cabling shall be re-tested and restored to a passing condition, at no additional cost to the Region. In the event more than two (2) percent of the cable plant fails during re-test, the entire cable plant shall be re-tested and restored to a passing condition at no additional cost to the Region. .8 Acceptance shall be subject to completion of Work, successful post-installation testing which yields a 100 percent PASS rating, and receipt of full documentation as specified in the Contract Documents. .9 Fiber-Optic Backbone Testing .1 Backbone fiber optic cable shall meet or exceed the permanent link performance requirements specified in TIA/EIA-568-B.3 for 62.5/125, multi-mode fiber and singlemode fiber. .2 Include final connectors when testing each strand. .3 Test fibers, as the Work progresses, as follows: 1. When 10 percent of the fibers have been terminated, notify the Consultant and schedule a representative of the supplier of the connectors to be present to witness fiber optic test. Submit test results from 10 percent phase, address any deficiencies and proceed with additional terminations to 50 percent. 2. Repeat the process outlined above when 50 percent of the fibers have been terminated. 3. Complete testing at 100 percent .4 Test link attenuation in accordance with TIA/EIA-526-14A for multimode fiber. Make reference measurements in accordance with method B or an equivalent method approved by the Consultant. Measure optical loss on each multimode fiber at 850 nm and 1300 nm. Measure loss on each fiber from each direction (bi-directionally). .5 Test link attenuation in accordance with TIA/EIA-526-7 for single-mode fiber. Make reference measurements in accordance with Method A.1 or an equivalent method approved by the Consultant. Measure optical loss on each CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .6 .7 .8 .10 Section 16741 Page 30 of 34 single-mode fiber at 1310 nm and 1550 nm. Measure loss on each fiber from each direction (bi-directionally). Measure link length optically or calculate using cable sheath length markings. Single-mode backbone fiber optic cabling shall meet the following loss and length criteria: 1. Attenuation @ 1310 nm shall be less than or equal to: fiber length (km) x 1.0 dB/km + number connector pairs x 0.75 dB + number of splices x 0.3 dB. 2. Attenuation @ 1550 nm shall be less than or equal to: fiber length (km) x 1.00 dB/km + number connector pairs x 0.75 dB + number of splices x 0.3 dB. 3. Length shall be less than or equal to 3000 metres. Multimode backbone fiber optic cabling shall meet the following loss and length criteria: 1. Attenuation @ 850 nm shall be less than or equal to: fiber length (km) x 3.0 dB/km + number connector pairs x 0.75 dB + number of splices x 0.3 dB. 2. Attenuation @ 1550 nm shall be less than or equal to: fiber length (km) x 1.00 dB/km + number connector pairs x 0.75 dB + number of splices x 0.3 dB. 3. Length shall be less than or equal to 2000 metres Fiber Optic Test Equipment .1 All test equipment of a given type shall be from the same manufacturer, and shall have compatible electronic results output. Acceptable test equipment manufacturers are Fluke Corporation, Hewlett-Packard Development Company, L.P. (Hewlett Packard), or MicroTest Inc. (Microtest). .2 Fiber optic test equipment shall meet the following minimum criteria: Test equipment shall be capable of measuring 1. relative or absolute optical power in accordance with TIA/EIA-526-14A, "Optical Power Loss Measurement of Installed Multimode Fiber Cable Plant." 2. Test equipment shall be capable of measuring relative or absolute optical power in accordance with TIA/EIA-526-7, “Optical Power Loss Measurement of Installed Single-mode Fiber Cable Plant.” 3. Test equipment shall not include the loss or length of the test jumpers in the cable plant measurements. CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 4. 5. 6. 7. 8. Section 16741 Page 31 of 34 Multimode test equipment shall incorporate both 850 nm and 1300 nm sources. The coupled output power into multimode fiber shall be >= -20 dBm at each wavelength. Detectors shall have a dynamic range of at least +3 dB to -55 dB. Single-mode test equipment shall incorporate both 1310 nm and 1550 nm sources. The coupled output power into multimode fiber shall be >= -20 dBm at each wavelength. Detectors shall have a dynamic range of at least +3 dB to -55 dB. Sources and meters shall automatically synchronize wavelengths to prevent calibrationrelated errors. Test equipment shall employ a serial port to facilitate uploading of saved information from tester to PC. The time-of-flight methodology shall be employed when optically measuring fiber length. .11 Optical Time Domain Refractometer (OTDR): .1 Provide OTDR tests for each strand/cable. .2 Test documentation; Hard copy of OTDR plots for each fiber strand. .12 Cable Test Results Manual .1 Submit test reports in both a hardcopy and electronic format. Hand-written test reports are not acceptable. Submit electronic files on a CD format disk in a PDF format. If test results cannot be converted to a PDF format then provide any necessary proprietary software to view the results at no cost to the Region. .2 Fiber optic backbone cable test results shall be incorporated in the PCS Network – Cable Test Results manual. Submit five (5) copies of the Cable Test Results manual for each plant. The manual consists of hardcopy test result reports placed into lockable ‘D’ ring binders with a cover and spline that clearly indicates the title of the manual. Provide a CD with the electronic copies of test reports in a pocket in the Cable Test Results manual. .3 Both the Contractor and the Consultant must sign a hardcopy of the reports. .4 Include a hard copy of the OTDR plots for each fiber strand. .13 Fiber Optic Documentation. At a minimum, test reports shall include the following information for each fiber optic cabling element (fiber) tested: .1 Actual measured attenuation, maximum allowable attenuation (loss) and the attenuation margin at the specified wavelengths. An individual test that fails the link criteria shall be marked as FAIL. CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .2 .3 .4 .5 .6 .7 .8 .9 .10 Section 16741 Page 32 of 34 Reference method. Number of mated connectors. Actual length and maximum allowable length. Any individual test that fails the link length criteria shall be marked as FAIL. Group refractive index (GRI) for the type of fiber tested, if length was optically measured. Tester manufacturer, model, serial number and software version. Circuit ID number (Cable Tag Id) and facility (Plant). Link criteria used. Overall pass/fail indication. Date and time of test. .14 CAT6 UTP Horizontal twisted pair cable shall meet or exceed the permanent link performance requirements specified in TIA/EIA568-B.2 for Category 6, Unshielded Twisted Pair (UTP). .15 Shielded horizontal twisted pair cable shall meet or exceed the permanent link performance requirements specified in TIA/EIA568-B.2 for Category 6, shielded Twisted Pair (STP). .16 Category 6 Test Equipment. Category 6 test equipment shall meet the following minimum criteria: .1 All test equipment of a given type shall be from the same manufacturer, and have compatible electronic results output. Acceptable test equipment manufacturers are Fluke Corporation, Hewlett-Packard Development Company, L.P. (Hewlett Packard), or MicroTest Inc. (Microtest). .2 Test adapters must be approved by the manufacturer of the test equipment. Adapters from other sources are not acceptable. Baseline accuracy of the test equipment must meet the .3 requirements of TIA Level III, as indicated by independent laboratory testing. .4 Test equipment must be capable of certifying Category 6 UTP to TIA/EIA-568-B.2-1 standards. Test equipment must have a dynamic range of at least 200 .5 dB to minimize measurement uncertainty. .6 Test equipment must be capable of storing full frequency sweep data for tests. .7 Test equipment must include S-Band time domain diagnostics for NEXT and return loss for accurate and efficient troubleshooting. .8 Test equipment must be capable of running individual NEXT, return loss, etc., measurements in addition to autotests. .9 Test equipment must make swept frequency measurements in compliance with TIA/EIA-568-B standards. CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 .10 .17 4.8 Section 16741 Page 33 of 34 The measurement reference plane of the test equipment shall start immediately at the output of the test equipment interface connector. There shall not be a time domain dead zone of any distance that excludes any part of the link from the measurement. Category 6 (UTP/STP) Documentation: At a minimum, test reports shall include the following information for each UTP/STP CAT 6 cabling element tested: .1 Wiremap results that confirm the cabling has no shorts, opens, mis-wires, or split, reversed, or crossed pairs, and that end-to-end connectivity is achieved. .2 Attenuation data that indicate the worst case result, the frequency at which it occurs, the limit at that point, and the margin. These tests shall be performed in a swept frequency manner from 1 MHz to highest relevant frequency, using a swept frequency interval that is consistent with TIA and ISO requirements. Information shall be provided for pairs or pair combinations and in both directions. .3 Length (in metres), propagation delay, and delay skew relative to the relevant limit. .4 Any individual test that fails the relevant performance specification shall be marked as a FAIL. .5 Cable manufacturer and cable model number/type. .6 Tester, manufacturer, model, serial number, hardware version, and software version. .7 Circuit ID number (Cable Tag Id) .8 Test criteria used. .9 Overall pass/fail indication. .10 Date and Time of test. Factory Acceptance Test – Network Access Closet .1 The system components that will be Factory Acceptance Tested are the Network Access Closets. The FAT will evaluate workmanship and verify construction and components against the Layout Drawings and associated Component Schedules submitted to and reviewed by the Consultant. .2 Provide Record and Shop Drawings to the Consultant for review at least fifteen (15) Working Days prior to the test. .3 Prepare a checklist or test sheet using MICROSOFT Excel. Submit to the Consultant for review, fifteen (15) Working Days prior to the commencement of the test. The Contractor shall conduct the test when directed by the Consultant. At a minimum, the FAT checklist or test sheet must include Products / materials used in the construction of the Network Access Closet. CONTRACT NO T-12-16 STRUCTURED CABLING SYSTEMS AND NETWORK ENCLOSURES DATE: February 2012 4.9 Section 16741 Page 34 of 34 Site Acceptance Test (SAT) .1 Site Acceptance Tests will evaluate the workmanship and verify installation against the Installation and Layout Drawings. .2 Provide Record and Shop Drawings to the Consultant for review fifteen (15) Working Days prior to the test .3 Prepare a checklist or test sheet using MICROSOFT Excel. Submit to the Consultant for review, fifteen (15) Working Days prior to the commencement of the test. The Contractor shall conduct the test when directed by the Consultant. At a minimum, the Consultant and the Region shall witness the test. .4 At a minimum, the SAT checklist or test sheet must include verification of the following: .1 All Products / materials used in the construction of the Network Access Closet .2 UPS power distribution and grounding .3 Utility power distribution and grounding .4 Fiber-optic cabling installation and termination .5 CAT6 (UTP/STP) cabling installation and termination .6 Work Area Outlet installation and termination .5 Network Access Closet SAT .1 The Contractor will provide one complete Network Access Closet, associated Work Area Outlet and Horizontal Cable for the Network Access Closet SAT. Following acceptance, the Contractor will be directed to proceed with the installation of the remaining Network Access Closets, Work Area Outlets and Horizontal Cabling. The Contractor is to note that the fiber optic backbone cable installation will be included in the Network Core Switch Closet SAT. .2 At a minimum, the complete Network Access Closet for the SAT will include the installation of the network switch, , UTP patch panels, fiber patch panel, power supplies, horizontal cable terminations, cable management and patch cords. .1 The Contractor shall provide a minimum of 40 hours of on Site support beginning immediately after the successful Site acceptance test for a period of 24 months following the date of Total Performance of the Work. The Site support shall include, but not be limited to, the following: .1 Respond within 24 hours to a request for on Site support. .2 The minimum Site time per call will be four (4) hours. .3 Travel time shall not be included in the cumulative Site support allowance. 4.10 Field Support END OF SECTION