CONSTRUCTION SURFACE WATER MANAGEMENT PLAN

advertisement
NEWCASTLE COAL
INFRASTRUCTURE GROUP
COAL EXPORT TERMINAL
CONSTRUCTION
SURFACE WATER
MANAGEMENT PLAN
NEWCASTLE COAL INFRASTRUCTURE GROUP
COAL EXPORT TERMINAL
PROJECT APPROVAL (06_0009)
CONSTRUCTION SURFACE WATER MANAGEMENT PLAN
Revision
Distribution
DoP Approval
CSWMP-R01-C
DoP
3 October 2007
CSWMP-R02-A
DoP
-
AUGUST 2010
Project No. NCIG-07-02/1
Document No. CSWMP-R02-A.DOC
Construction Surface Water Management Plan
TABLE OF CONTENTS
Section
Page
1
INTRODUCTION
1
2
POTENTIAL SURFACE WATER QUALITY IMPACTS
5
3
SURFACE WATER AND STORMWATER MANAGEMENT
7
3.1
3.2
4
THE INTERNAL DRAINAGE NETWORK
3.1.1
Coal Storage Area
3.1.2
Rail Infrastructure Area
3.1.3
Wharf Facilities and Shiploader Area
EROSION AND SEDIMENT CONTROL PLAN
3.2.1
Sources of Soil Erosion
3.2.2
Erosion and Sediment Control Strategies
3.2.3
Specifications for Surface Water Management and Sediment Control Structures
3.2.4
Progressive Development of Erosion and Sediment Control Plans
3.2.5
Erosion and Sediment Control Monitoring
7
7
10
10
13
13
13
14
14
14
SURFACE WATER AND STORMWATER MONITORING PROGRAM
15
4.1
4.2
4.3
4.4
15
15
17
MONITORING PROGRAM
SURFACE WATER QUALITY CRITERIA
DATA REVIEW AND VALIDATION
INVESTIGATION PROCEDURES IN THE EVENT OF EXCEEDANCE OF SURFACE WATER
QUALITY CRITERIA
17
5
REPORTING
18
6
REFERENCES
18
LIST OF TABLES
Table 1
Table 2
Table 3
Table 4
Table 5
Table 6
Condition 7.3(b), Schedule 2 of Project Approval (06_0009)
Potential Surface Water Quality Impacts
Sediment Control Structures – General Capacity Requirements
Surface Water Monitoring Program
EPL 6437 Surface Water Monitoring Program
Surface Water Quality Criteria
LIST OF FIGURES
Figure 1
Figure 2
Figure 3
Figure 4
Figure 5
Figure 6
Figure 7
Project Location
Project General Arrangement
Estimation of Fill Materials in the Project Disturbance Area
Site Drainage Layout - Stage 2AA Commencement
Provisional Site Drainage Layout - 66 Mtpa Capacity
Conceptual Typical Cross Section of the Rail Infrastructure Corridor
Drains (Culverts) along the Rail Infrastructure Corridor
LIST OF ATTACHMENTS
Attachment 1
Detailed Site Drainage Drawings - Stage 2AA Drainage Layout and Provisional Final
Drainage Layout
i
Construction Surface Water Management Plan
1
INTRODUCTION
The Newcastle Coal Infrastructure Group (NCIG) Coal Export Terminal (CET) (the Project) is located on
Kooragang Island in Newcastle, New South Wales (NSW) (Figure 1). The overall Project includes the
construction and operation of a CET up to 66 million tonnes per annum (Mtpa), including associated rail and coal
handling infrastructure and wharf/shiploading facilities on the south arm of the Hunter River.
NCIG is the proponent of the Project and is a consortium of the following six companies:
•
Hunter Valley Energy Coal Limited;
•
Centennial Coal Company Limited;
•
Donaldson Coal Pty Limited;
•
Peabody Energy Australia Coal Pty Limited;
•
Felix Resources Limited; and
•
Whitehaven Coal Limited.
NCIG was granted Project Approval (06_0009) on 13 April 2007. This Construction Surface Water Management
Plan (CSWMP) has been prepared in accordance with Condition 7.3(b), Schedule 2 of the Project
Approval (06_0009). Table 1 indicates where each component of Condition 7.3(b), Schedule 2 of Project
Approval (06_0009) is addressed within this CSWMP.
Table 1
Condition 7.3(b), Schedule 2 of Project Approval (06_0009)
Project Approval (06_0009) Condition
Section Addressed in
this Document
7. ENVIRONMENTAL MANAGEMENT
7.3 As part of the Construction Environmental Management Plan for the project required under
condition 7.2 of this approval, the Proponent shall prepare and implement the following:
b) a Construction Surface Water Management Plan to detail how surface water and stormwater
will be managed on the Site during construction. The Plan shall include use of appropriately-sized
stormwater controls, in accordance with Managing Urban Stormwater: Soils and Construction
(Landcom, 2004). The Plan shall include specific measures to avoid sediment-laden stormwater
from entering Deep Pond, wetland areas or the Hunter River, and a monitoring program for
stormwater leaving the Site;
This CSWMP
In accordance with Condition 7.3, Schedule 2 of Project Approval (06_0009), this CSWMP will be included as
part of the Construction Environmental Management Plan for the Project.
Other Project Approval conditions of relevance to this CSWMP in Schedule 2 of Project Approval (06_0009) are
provided below:
2.42 Unless otherwise agreed by the Director-General, the Proponent shall design, construct, maintain and
operate surface water and stormwater management infrastructure on the Site to accommodate a 1 in 100
ARI rainfall event, and shall not permit the discharge of any water from the Site to the Hunter River unless
expressly provided under the provision of an Environment Protection Licence.
2.43 The Proponent shall take all reasonable measures to prevent soil erosion and the discharge of
sediments and pollutants from the Site during construction of the project.
2.44 The Proponent shall install stormwater drains, stormwater ponds, settlement ponds and/or storage
ponds and other erosion, sediment and pollution controls as may be appropriate to manage stormwater on
the Site. The Proponent shall maintain all erosion, sediment and pollution control infrastructure at or above
design capacity for the duration of construction of the project and until such time as all ground disturbed by
the works has been stabilised and rehabilitated so that it no longer acts as a source of sediment.
1
ver
Ri
te
Hun
r
ific
Pac
386 000 E
384 000 E
382 000 E
380 000 E
378 000 E
MAITLAND
6 370 000 N
LEGEND
Approximate Extent of Project Key Components
6 370 000 N
High Capacity Optional Inlet Rail Spur and Rail
Sidings
Local Government Area Boundary
Nature Reserve
Mangrove Area
PORT STEPHENS
y
hwa
Hig
0
1
2
Kilometres
6 368 000 N
6 368 000 N
Tomago
Industrial
Estate
d
Roa
ago
Tom
TOMAGO
HEXHAM
6 366 000 N
6 366 000 N
KOORAGANG WETLAND
REHABILITATION PROJECT
ASH ISLAND
Fullerton Cove
KOORAGANG NATURE RESERVE
Hunter
River
6 364 000 N
HEXHAM
SWAMP
NATURE
RESERVE
KOORAGANG
NATURE
RESERVE
(North
Arm)
6 364 000 N
NCIG Coal Export Terminal
FERN BAY
KOORAGANG ISLAND
SHORTLAND
WETLANDS
H
un
ter
Riv
er
6 362 000 N
SANDGATE
SHORTLAND
Hexham
Swamp
PORT WARATAH COAL SERVICES
KOORAGANG COAL TERMINAL
(At Full Development)
( So
uth
Arm
)
Steel River
6 362 000 N
Corm
oran
STOCKTON SANDSPIT
t
Roa
d
MAYFIELD
WEST
OneSteel
MAYFIELD
NORTH
WARABROOK
Pa
cifi
c
University of
Newcastle
BIRMINGHAM
GARDENS
CALLAGHAN
6 360 000 N
Industrial
Hig
hw
ay
Drive
Intertrade Industrial Park
MA
Cha
nne
l
6 360 000 N
IN
PORT WARATAH
COAL SERVICES
CARRINGTON COAL TERMINAL
ton
RN
RA
AY
ILW
NEWCASTLE
6 358 000 N
HE
NORTH LAMBTON
RT
JESMOND
MAYFIELD
EAST
Stockton
Bight
Sto
ck
MAYFIELD
NO
WARATAH
WARATAH WEST
Port
Hunter
TIGHES HILL
GEORGETOWN
6 358 000 N
MARYVILLE
nte
LAMBTON
STOCKTON
CARRINGTON
ISLINGTON
Hu
HAMILTON
NORTH
r
LAKE
MACQUARIE
er
Riv
HAMILTON
NEW LAMBTON
HEIGHTS
BROADMEADOW
HAMILTON
EAST
6 356 000 N
NEW LAMBTON
NEWCASTLE
CBD
NEWCASTLE
WEST
NEWCASTLE EAST
6 356 000 N
COOKS HILL
RANKIN PARK
BLACKBUTT
RESERVE
384 000 E
382 000 E
380 000 E
378 000 E
THE JUNCTION
FIGURE
BAR BEACH 1
Project Location
386 000 E
CONSTRUCTION SURFACE WATER MANAGEMENT PLAN
ADAMSTOWN
NCIG-07-02 Task 1 CSWMP 2010_004A
Source: NCIG (2006); Connell
THE HILL Hatch (2006); RLMC (2006); UBD (2002)
HAMILTON SOUTH
Construction Surface Water Management Plan
2.45 All stockpiled construction materials shall be stabilised and covered where practicable to prevent
erosion or dispersal of the materials. The Proponent shall manage any fill/ preload material brought to the
Site in manner that prevents erosion and dispersal of those materials.
The above conditions are addressed where relevant in this CSWMP.
Construction of Stage 1 of the Project commenced in January 2008, with operations of the Stage 1 Project
components commencing in the third quarter of 2010. These works allow the CET to operate up to the initial
Project capacity of 30 Mtpa. The Stage 1 Project components included the construction of:
•
rail infrastructure including one train unloading station;
•
the southern portion of the coal storage area including two combined stacker/reclaimers; and
•
wharf facilities including one shiploader and two shipping berths.
The Stage 2AA construction activities are scheduled to commence in the third quarter of 2010. The construction
period is expected to take approximately 29 months and, when complete, will increase the capacity of the CET to
53 Mtpa. The Stage 2AA Project components will include the construction of (Figure 2):
•
a second train unloading station and associated rail infrastructure;
•
a portion of the coal storage area including a third combined stacker/reclaimer; and
•
a second shiploader.
The High Capacity Optional Inlet Rail Spur is not required for Stage 2AA of the Project.
The environmental management described in this document is specifically designed to ensure the construction
activity outlined for Stage 2AA is undertaken in a manner compliant with the requirements of the Project Approval
(06_0009).
NSW Maritime was granted Development Consent (DA 134-3-2003-i) (the Port Consent) by the Minister on
9 August 2005. The Extension of Shipping Channels, Port of Newcastle includes dredging, excavation, treatment
and disposal of sediments from the south arm of the Hunter River.
The dredging required for the development of the Project up to the initial 30 Mtpa capacity (Stage 1) involved the
removal and handling of material including sand, silt clay and rock from the south arm of the Hunter River. There
will be no dredging or marine works conducted during Stage 2AA of the Project and as such the Port Consent
(DA 134-3-2003-i) does not apply to the Stage 2AA development phase. Therefore, this CSWMP has been
prepared to only provide for the management of surface water and stormwater on the Project site.
This CSWMP has been prepared to assist NCIG in the implementation of appropriate environmental
management measures during the Stage 2AA construction period of the Project. Where there is any conflict
between the provisions of this CSWMP and any Contractors’ obligations under their respective Contracts,
including the various statutory requirements (i.e. licences, permits, Project Approval conditions and relevant
laws), the Contract and statutory requirements are to take precedence. In the case of any real or perceived
ambiguity between elements of this CSWMP and the above statutory requirements the Contractor shall first gain
clarification from NCIG prior to implementing that element of this CSWMP over which the ambiguity is identified.
The remainder of this CSWMP is structured as follows:
Section 2:
Summarises the potential surface water quality impacts for each area of the Project site.
Section 3:
Provides the surface water and stormwater management measures and the Erosion and
Sediment Control Plan.
Section 4:
Provides details of the surface water and stormwater monitoring program.
Section 5:
Describes the reporting requirements for this CSWMP.
Section 6:
Lists the references cited in this CSWMP.
3
Hun
Construction of
Second Train
Unloading Station
Stacker/Reclaimer
Conveyor
Overpass
KOO
Secondary
Settling
Combined
Pond
Stacker/
Reclaimer
PORT WARATAH COAL SERVICES
KOORAGANG COAL TERMINAL
(At Full Development)
Overflow
Pond
6 362 000 N
nter
Riv
er
(So
uth
Arm
Road
Cormorant
)
Coal Storage Area
U-turn Loop
Dredging Activities Not
Included in Stage 2AA
Tourle Street
Bridge
Steel River
Corm
oran
Third Berth
Not Included
in Stage 2AA
t
Blue Circle
Southern Cement
Conveyors Over
Cormorant Road
K9
OneSteel
Wharf Facilities
and Shiploaders
Curle
w
Rave
n S
treet
Egre
t
Tourle Stree
t
MAYFIELD
WEST
Construction
of Second
Shiploader
Origin
Energy
Road
K10
Stree
t
Hu
6 362 000 N
Water Tanks and
Pump Stations
Administration, Workshops
and Carpark
Energy Australia
Substation
Rail Loops
Stree
t
t
RAG
ANG
Rail Spurs and
Rail Sidings
Road
Primary
Settling Ponds
Cormorant
Road Level
Crossing
KOORAGANG NATURE RESERVE
Fourth Combined
Stacker/Reclaimer
Not Included in
Stage 2AA
Existing Cormorant
Road Roundabout
MAYFIELD
NORTH
Teal
Sandpip
er
Close
K8
K7
Stree
t
/
/
/
/
/
/
/
/
/
/
Train
Unloading
Stations
(Nor
tConstruction
h A
rm) of
Third Combined
Stree
ISLAND
Delta EMD Australia
Pacific Natio
nal Access
Road
AND
ISL
Rail
Overpass
Delta Access Road
MA
PWCS Fines
Disposal Area
ter
River
Teal
INL
INE
High Capacity Optional Inlet
Rail Spur and Rail Sidings
Not Included in Stage 2AA
KOORAGANG
384 000 E
382 000 E
380 000 E
KOORAGANG WETLAND
REHABILITATION PROJECT
ASH ISLAND
STAGE 2AA ACTIVITIES
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
K6
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
Road
\
\
/
X-ING
/
/
/
/
/
K4
\
\
\
\
\
Drive
\
\
\
\
\
\
\
\
\
\
\
\
\
\
\
Pa
cifi
c
\
\
\
Heron
\
Industrial
6 360 000 N
\
\
\
Intertrade Industrial Park
Source: NCIG (2006, 2010); Connell Hatch (2006);
LPI NSW (2001a, 2001b, 2001c, 2002)
/
\
\
\
\
\
\
\
/
\
Hig
hw
ay
CONSTRUCTION SURFACE WATER MANAGEMENT PLAN
\
\
\
MAYFIELD
384 000 E
/
/
/
FIGURE 2
Project General Arrangement
/
\
382 000 E
380 000 E
/
/
/
/
/
/
NCIG-07-02 Task 1 CSWMP 2010_009C
/
/
800
/
/
400
Metres
/
L.P.
K5
\
0
/
/
LEGEND
Site Access Point
WARABROOK
Rail Infrastructure Corridor
Conveyors
Transfer Points
6 360 000
K9 N Shipping Berth
Coal Stockpiles
Nature Reserve
Mangrove Area
Kooragang Island Waste Emplacement Facility
Construction Surface Water Management Plan
2
POTENTIAL SURFACE WATER QUALITY IMPACTS
Surface water runoff from disturbance areas during the construction of the Project could potentially contain
sediments, soluble salts, fuels, oils, grease and other contaminants. An estimation of fill materials (i.e. possible
contaminants) in the Project disturbance area is shown on Figure 3. The potential surface water quality impacts
that relate to these contaminants from each area of the Project site are summarised in Table 2.
Table 2
Potential Surface Water Quality Impacts
Project Site
Rail Infrastructure
Corridor
Potential Impact Scenario
Uncontrolled drainage of sediment laden runoff to downstream
waterbodies within the Kooragang Island Waste Emplacement
Facility (KIWEF) during construction of rail embankments.
Potential Contaminant
Sediments, soluble salts, heavy
metals, organic contaminants,
fuels, oils and grease.
Uncontrolled drainage of runoff from access roads and construction
areas to downstream waterbodies within the KIWEF.
Uncontrolled drainage of runoff from exposed soils within the
existing KIWEF to downstream waterbodies.
Potential erosion and sedimentation resulting from runoff from the
rail corridor and associated drainage system.
Coal Storage
Area
Uncontrolled drainage to downstream waterbodies during
construction of the coal storage area.
Sediments, soluble salts, fuels,
oils and grease.
Uncontrolled drainage of runoff from access roads and construction
areas to downstream waterbodies.
Spillage/overflow of site water to downstream waterbodies.
Wharf Facilities
and Shiploader
Area
Uncontrolled drainage of sediment laden runoff to the south arm of
the Hunter River during construction of the wharf structure,
excavation on or near the banks of the South Arm of the Hunter
River and during piling operations.
Uncontrolled drainage of runoff to the south arm of the Hunter River
from access roads and wharf construction areas including
excavation on or near the banks of the South Arm of the of the
Hunter River.
Source:
After NCIG and Connell-Hatch (2006)
5
Sediments, soluble salts, fuels,
oils and grease.
384 000 E
382 000 E
380 000 E
KOORAGANG NATURE RESERVE
INE
KOO
RAG
ANG
KOORAGANG
Delta Access Road
ISL
AND
MA
INL
Deep Pond
Pacific Natio
nal Access
Road
KOORAGANG WETLAND
REHABILITATION PROJECT
ASH ISLAND
ISLAND
Train
Unloading
Stations
PORT WARATAH COAL SERVICES
KOORAGANG COAL TERMINAL
(At Full Development)
6 362 000 N
6 362 000 N
Rail Infrastructure
Corridor
Road
Cormorant
Energy Australia
Substation
Tourle Street
Bridge
Road
Coal
Storage Area
t
Rave
n
Egre
Curle
w
Stree
Stree
t
t
K9
OneSteel
Teal
Sandpip
er
Close
Teal
K8
MAYFIELD
NORTH
K7
Stree
t
/
/
/
/
/
/
/
/
/
/
MAYFIELD
WEST
Stree
t
Wharf Facilities
and Shiploaders
/
/
/
/
/
/
/
/
/
/
/
/
/
/
WARABROOK
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
K6
/
/
/
K9
Tourle Stree
t
K10
LEGEND
Approximate Extent of Project Key Components
High Capacity Optional Inlet Rail Spur and Rail
Sidings
Nature Reserve
Mangrove Area
Kooragang Island Waste Emplacement Facility
Shipping Berth
Cormorant
Stree
t
Steel River
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
L.P.
/
/
/
/
/
/
/
/
/
/
/
\
\
\
\
\
\
\
6 360 000 N
\
\
\
\
\
\
\
/
\
Hig
hw
ay
CONSTRUCTION SURFACE WATER MANAGEMENT PLAN
\
\
\
MAYFIELD
384 000 E
/
/
/
FIGURE 3
Estimation of Fill Materials
in the Project Disturbance Area
/
\
382 000 E
380 000 E
\
\
\
\
\
\
\
\
\
\
\
\
)
Source: NCIG (2005); Connell Hatch (2005, 2006); Connell Wagner (2006);
Patterson Britton (2003); Dames & Moore (1999);
RCA Australia (2004, 2006); LPI NSW (2001a, 2001b, 2001c, 2002)
/
/
/
/
NCIG-07-02 Task 1 CSWMP 2010_003B
\
\
Arm
\
uth
/
Metres
800
/
/
Road
/
Intertrade Industrial Park
Heron
\
fic
\
\
Drive
\
(So
\
Pa
ci
Riv
er
\
Industrial
K4
nter
\
X-ING
Hu
/
400
/
/
/
/
0
/
/
K5
\
Blast Furnace Slag
Coal Washery Fine Rejects
Brecketts Material & Slag
Refuse
Coal Washery Coarse Rejects
6 360 000 N
BOS Dust
Dredge Material
Unknown Fill Status (Water & Marshes)
Miscellaneous Fill (Majority Dredge Material)
Unknown Fill
Construction Surface Water Management Plan
3
SURFACE WATER AND STORMWATER MANAGEMENT
This section provides details on the objectives, concepts and design criteria which are used in the design of the
infrastructure.
The construction surface water management strategy for the Project is based on:
•
the separation of surface water runoff generated from within the active Project construction areas from that
generated from surrounding areas; and
•
the implementation of adequate water management controls to minimise the potential for impacts to off-site
water resources such as adjacent wetland areas, adjacent ponds and the Hunter River (Figure 3).
3.1
THE INTERNAL DRAINAGE NETWORK
Temporary erosion and sediment controls (e.g. silt fences and construction settling ponds) will be installed prior
to the commencement of construction activities on the Project site.
A network of water management structures will be used to manage runoff on and around the construction site.
All long-term site water management structures have been lined with low permeability materials (e.g. compacted
clay or geo-membrane) to minimise the potential for leakage. Water management structures have been
designed and constructed with sufficient capacity for a 1 in 100 year average recurrence interval (ARI) rainfall
event. Project water management structures will also be designed to operate in accordance with Environment
Protection Licence (EPL) 12693 obtained from the Department of Environment and Climate Change (DECC)
(now the Department of Environment, Climate Change and Water).
In accordance with Condition 2.41, Schedule 2 of Project Approval (06_0009), Project water management
structures will be designed to operate to comply with Section 120 of the Protection of the Environment
Operations Act, 1997.
Where relevant, details of the site drainage layout for the Stage 2AA construction period are shown on Figure 4.
The provisional site drainage layout for the final operating capacity of 66 Mtpa is shown on Figure 5. Detailed
plans of the Stage 2AA and provisional final site drainage layout are provided as Attachment 1.
3.1.1
Coal Storage Area
The site drainage network has been established to capture site runoff, including runoff transferred from the rail
infrastructure corridor and the wharf facilities area (Figure 4).
The Project coal storage area is relatively flat with a slight fall to the north-west (Figure 4). Three coal stockpiles
pads and two berms were constructed in the southern section of the coal storage area during Stage 1 of the
Project. A sub-grade drainage system has been incorporated into the coal stockpile pads to capture water
infiltrating through the coal stockpiles. The sub-grade drainage system comprises of a series of underground
drains to control drainage from the coal storage area (see Attachment 1 for details of the sub-grade drainage
system).
Stormwater runoff collected on the Project infrastructure areas is diverted through sediment control structures
and/or construction settlement ponds. Construction settling ponds have been installed where necessary at the
end of the open drains to act as sediment and pollutant traps (Figure 4).
7
5
4
3 4
6
K9
2
Stree
Teal
3
0
t
4
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
4
4
/
/
/
6
/
/
/
/
/
/
/
/
/
/
L.P.
/
/
/
/
/
/
/
\
\
\
\
\
\
\
\
\
\
\
\
\
6
\
\
\
\
\
\
\
0
\
3
\
6
9
6 360 000 N
\
\
\
6
4
2
6
0
9
6
3
3
Intertrade Industrial Park
Source: NCIG (2006); Connell Hatch (2006);
LPI NSW (2001a, 2001b, 2001c, 2002)
\
\
\
\
\
\
\
/
\
6
6
CONSTRUCTION SURFACE WATER MANAGEMENT PLAN
\
\
\
\
FIGURE 4
Site Drainage Layout
Stage 2AA Commencement
/
/
3
/
3
3
4
15
12
9
0
MAYFIELD
/
0
382 000 E
3
Heron
Drive
/
15800
/
/
/
\
\
\
3
12
9
Road
/
/
/
/
2
\
3
9
4
3
9
Industrial
9
6
6
6
96
6
6
/
6
4
3
6
/
/
4
/
/
/
3
4
/
/
/
/
/
/
/
3
/
/
/
4
/
Metres
4
/
/
/
0
400
6
/
/
/
3
Shipping Berth
Coal Stockpiles
48
3P
39Surveys) (m AHD)
Contours
(North
aci
33
2 fic Contours (Connell
27 Hatch) (m AHD)
12
Nature Reserve21
18
9 Mangrove Area 15
H
Kooragang IslandighWaste
Emplacement Facility1
w
y
(KIWEF) (PotentiallyaContaminated
Catchment) 2
0
Stree
\
15
380 000 E
Teal
/
12
4
4
Sandpip
er
Close 4
3
Settling Basin
12
15
8
Construction Settling Pond 121
24
18
21
/
NCIG-07-02 Task 1 CSWMP 2010_001F
15
t
t
6
9
K9
Stree
/
24
w
4
3
9
K8
0
3
6
27
2
Wharf Facilities
and Shiploader
MAYFIELD
NORTH
4
Curle
Stree
t
6
9
33
3
Rave
n S
treet
3
MAYFIELD
WEST
LEGEND
36
Water Flow Direction
WARABROOK
Drainage Diversion/Construction Open Drain
39
Water Transfer (Via Pump and Pipeline)
Surface Water Monitoring Site
SW1
6 360 000 N EPL No 6437 Surface Water Monitoring Site
EPL No 6437 Background Surface Water
Monitoring Site
Approximate Extent of Project Key Components
Rail Infrastructure Corridor
Conveyors
Transfer Points
Pump to
Overflow Pond
5
5
3
8
Tourle Stree
t
Road
2
2
4
Cormoran2t
t
6
9
30
27
24
21
18
3
oran
21
30
2
6
Corm
2
2
3
3
/
0
6 362 000 N
Road
3
2
2
2
3
30
4
2
5
9
0
2
4
ad
2
9
24
4
2
3
2
3
2
2
32
KS10/2 4Ro
2
2
3
12
9
3
0
0
3
Tourle Street
Bridge
33
18
96
2
2
30
30
27
24
21
18
15
12
9
6
6
12 5
1 8
1 21 4
2
Pond L
Cormorant SW2
6 3
4
0
2
KS10/1
3
KS1/1 3
2
10
3
KS10/3
9
Combined
Stacker/
3
Reclaimer
Overflow
Pond
Water Tanks and
Pump Stations
SW1
Administration, Workshops
3
3
3
and Carpark
2
3
3 3
Rail Loops
3
3
9
4
3
2
3
)
3
Culvert
1
4 Egret
Arm
9
Pond6 Q
3
2
2
0
10
2
X-ING
KS1/2
uth
2
2
2
384 000 E
(So
Secondary
Settling Pond
6
Riv
er
9
Pond I
6
12
9
8
4
2
Primary
Settling Ponds
3
3
8
3
6
2
2
6 9
6
2
6
10
KS8/1
3
K Pond
East
1
2
3
r
Pond H
8
3
2
9
6
nte
4
6
6
2
2
AND
ISL
KOO
RAG
ANG
3
2Pond A
3 KS1/3
0
3
3
2
Rail Spurs and 2
Rail
Sidings 36
6
Rail
Overpass
K Pond
West
Train
Unloading
Stations
2
2
2
Hu
3 2
3
6
3
2
6 362 000 N
3
Culvert3
KOORAGANG
6
8
ISLAND
6
1
1
2
2
KOORAGANG NATURE RESERVE
1
2
12
9
Delta Access Road
2
90
1
Culvert
6
2
SW3
2
6
3
6
6
6
(Nor
th A
rm)
KS12/5
2
3
3
3
1
2
6
3
KS7/1
Pacific Natio
nal Access
Road
Deep Pond
KS12/4
3
6
3
3
2
KS2/1
9 6
2
ter
River
384 000 E
382 000 E
2
MA 2
INL
INE
400 m
3
4
3
KS4/12
KS12/1
KS12/2
6
2
3
1
KS12/3
2
3
KOORAGANG WETLAND
REHABILITATION PROJECT
ASH ISLAND 1
2
Hun
/
380 000 E
K12/6
ter
River
Deep Pond
384 000 E
382 000 E
380 000 E
KOORAGANG WETLAND
REHABILITATION PROJECT
ASH ISLAND
Hun
(Nor
th A
rm)
Train
Unloading
Stations
Primary
Settling Ponds
ANG
Rail Spurs and
Rail Sidings
KOO
Secondary
Settling
Combined
Pond
Stacker/
Reclaimer
PORT WARATAH COAL SERVICES
KOORAGANG COAL TERMINAL
(At Full Development)
Overflow
Pond
6 362 000 N
Hu
nter
Riv
er
(So
uth
Road
Cormorant
Arm
Coal Storage Area
)
Corm
Tourle Street
Bridge
oran
t
Stree
t
MAYFIELD
NORTH
Existing Cormorant
Road Roundabout
Teal
Sandpip
er
Close
K8
Teal
Wharf Facilities
and Shiploaders
Stree
t
Settling Basin
K7
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
K6
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
L.P.
/
/
/
/
/
/
/
/
/
/
/
/
Road
/
K5
\
\
/
X-ING
/
/
/
/
/
K4
\
\
\
\
\
\
\
\
\
\
\
Drive
\
\
\
\
\
\
\
Pa
ci
\
\
\
\
\
Heron
\
Industrial
fic
\
\
\
6 360 000 N
Intertrade Industrial Park
Source: NCIG (2006); Connell Hatch (2006);
LPI NSW (2001a, 2001b, 2001c, 2002)
/
/
\
\
\
\
\
\
\
/
\
Hig
hw
ay
CONSTRUCTION SURFACE WATER MANAGEMENT PLAN
\
\
\
MAYFIELD
384 000 E
/
/
/
FIGURE 5
Provisional Site Drainage
Layout - 66 Mtpa Capacity
/
\
382 000 E
380 000 E
OneSteel
/
/
/
/
NCIG-07-02 Task 1 CSWMP 2010_005D
t
/
800
Stree
K9
/
400
Metres
w
t
/
0
Curle
Stree
\
LEGEND
Stormwater Flow Direction
Drainage Diversion/Collection Drain
Water Transfer (Via Pump and Pipeline)
Drain (Culvert)
Site Access Point
WARABROOK
Rail Infrastructure Corridor
Conveyors
Transfer Points
6 360 000 N
K9
Shipping Berth
Coal Stockpiles
Nature Reserve
Mangrove Area
Kooragang Island Waste Emplacement Facility
Egre
Tourle Stree
t
MAYFIELD
WEST
Rave
n
t
Road
K10
Cormorant
Stree
t
Steel River
6 362 000 N
Water Tanks and
Pump Stations
Administration, Workshops
and Carpark
Energy Australia
Substation
Rail Loops
Road
ISLAND
Pacific Natio
nal Access
Road
AND
ISL
Rail
Overpass
Delta Access Road
MA
INL
INE
High Capacity Optional
Inlet Rail Spur and
Rail Sidings
KOORAGANG
RAG
KOORAGANG NATURE RESERVE
Construction Surface Water Management Plan
Two construction open drains running east-west will divert run-off from the northern portion of the coal storage
area around the coal stockpiles and berms during the Stage 2AA construction period (Figure 4). One drains to a
construction settling pond to the west of the coal storage area and then to the primary settling ponds. A second
construction settling pond located in the east of the coal storage area collects runoff from the second
construction open drain. Runoff from this pond is pumped to the overflow pond. The primary and secondary
settling ponds and overflow pond have been constructed to the north of the coal storage area. The primary and
secondary settling ponds and the overflow pond capture sediments not trapped in the construction settling
ponds.
Consistent with the design goal of no discharge to the Hunter River during operations, the construction settling
ponds, primary and secondary settling ponds and the overflow pond are designed and constructed with sufficient
capacity to contain a 1 in 100 year average recurrence interval (ARI) rainfall event. All Project water
management structures will be operated in accordance with the requirements of the Project Approval and
EPL 12693.
An existing stormwater drainage channel runs from the overflow pond to the Hunter River. This channel was
used to return seawater to the south arm of the Hunter River from reclaimed dredged material during Stage 1 of
the Project. As dredging activities are not to occur during Stage 2AA of the Project, no water will be discharged
to the Hunter River unless expressly provided for under the provision of an EPL.
3.1.2
Rail Infrastructure Area
Surface water features in the vicinity of the rail infrastructure corridor comprise waterbodies created by the
existing Kooragang Island mainline rail embankment, emplacement cells associated with the KIWEF and a
number of depressions in the KIWEF landform that intermittently fill with water in response to rainfall runoff.
There is also a drainage channel adjacent to the Kooragang Island mainline which drains to the south arm of the
Hunter River. Deep Pond is a large waterbody in this area and is connected to a series of ponds to its south-east
via drainage lines (Figure 4) (NCIG and Connell-Hatch, 2006). Figure 4 shows the various catchments within the
rail infrastructure corridor.
Stormwater runoff from areas adjacent to the Project rail infrastructure corridor is diverted via table drains along
parallel the Project rail infrastructure corridor and in to the existing drainage system across the KIWEF. The rail
embankment includes culverts where it traverses low points in the existing topography to allow drainage across
its alignment and prevent ponding in adjacent areas. Details of the drains and culverts along the rail
infrastructure corridor are shown on Figure 6 and Figure 7. These drains and culverts were constructed as a part
of the Stage 1 works.
Runoff from the train unloading stations will be collected in sumps before being transferred via pump and pipeline
networks to the coal storage area drainage system (Figure 4 and Attachment 1). These works were constructed
as a part of the Stage 1 project and are currently operational.
The High Capacity Inlet Rail Spur (Figure 2) will not be constructed as a part of the Stage 2AA construction
activities. This will result in any potential impact on Deep Pond being minimal.
3.1.3
Wharf Facilities and Shiploader Area
The wharf facilities and shiploader area is relatively flat with a slight fall to the south-east (Figure 4). The wharf
facilities have been designed to ensure that all stormwater from this area drains away from the Hunter River.
Stormwater runoff from the wharf facilities and shiploader area passes through sediment control structures
before being collected in a settling basin. Water collected in the settling basin will be transferred via pump and
pipeline to the coal storage area drainage system (Figure 4).
Silt curtains will be installed adjacent to disturbance areas that may create excessive disturbance during
construction works in the wharf facilities and shiploader area.
10
NCIG-HDC
Lease Boundary
Future KIWEF
Capping (By Others)
Service Road
Service Road
NCIG-HDC
Lease Boundary
Drain*
Rail Basecourse
Wearing Course
Drain* Wearing Course
Drain*
2
Existing Surface
1
Future KIWEF
Capping (By Others)
Drain*
3
1
Clean Engineered Fill
Existing Surface
CONCEPTUAL TYPICAL SECTION
RAIL SPUR AND RAIL SIDINGS
#
NCIG-HDC
Lease Boundary
NCIG-HDC
Lease Boundary
Future KIWEF
Capping (By Others)
Service Road
Drain*
Capping Layer incorporating:
+ Sealing Layer (0.5m thick) - including
a geo-synthetic and/or geo-membrane
as required to achieve effective
permeability and/or integrity.
+ Seal-bearing Surface (i.e. prepared
sub-grade).
Rail Basecourse
Wearing Course
2
Existing Surface
Drain*
Drain*
1
Drain*
3
Future KIWEF
Capping (By Others)
1
Existing Surface
CONCEPTUAL TYPICAL SECTION
RAIL LOOP
0
5
Kilometres
Source: NCIG (2006); Connell Hatch (2006); RCA Australia (2006)
Notes:
* Lining/armouring of drain alignments as required.
#
An Infiltration Drainage Layer and Revegetation Layer would be placed
across the Capping Layer as part of Project closure and rehabilitation works.
NCIG-07-02 Task 1 CSWMP 2010_008C
CONSTRUCTION SURFACE WATER MANAGEMENT PLAN
FIGURE 6
Conceptual Typical Cross Section
of the Rail Infrastructure Corridor
Download