our projects summary

advertisement
Current Projects Data
Since it was established in 2006, RAM Electrical & Civil has delivered more than 700 projects
throughout the SADC region.
Projects between R10 Million - R20 Million
Site
Code
Project
Description
Project
Start
Date
Project
Cost
Time
Involved
Electrical Installations
Apr-15
R 19.5 mil
12
months
Nebawest 46 PTY
Ballenden & Robb Andre
Sieberhagen
T: 045-838-1815
Robert Skinner
Construction Francois Baard
012-8030811
Ariano Consulting
Engineers
Willie Bouwer
T: 083 272 0552
Project
Title
Client
Engineer
2004
M Fletcher
New Cluster Offices
0354
LEMO Shopping
Mall - Heidedal,
Bloemfontein
Electrical Installations
Sep-14
R 19.5 mil
19
months
0371
Tsitsikamma
Windfarm- Civil work
and installation of
33kV connector
cables
Civil works and installation of
33kV and LV cables between
wind turbines/substation , LV
connector cables between
turbines and transformers,
road crossings, fibre optic
etc.
Apr-15
R 17.4 mil
9 months
Actom - RAM
Subcontracting for
CBI-African Cables
CBI-African Cables
Waldo van Wyk
T: 078 459 7560
0000
Kariba Powerstation,
Zimbabwe
Installation of 400kV Cables
Sept-15
R 12 mil
18
months
Helcraw Electrical Zimbabwe
Gary Laing
T: +26 377 215 2440
Projects between R5million - R10million
Site
Code
0280
Project
Title
Project
Description
Project
Start
Date
Project
Cost
Time
Involved
Ingula Water Pump
Scheme - Hydro
Electrical Power
Installation of cable brackets
and installation of cables
from the underground
transformers to the 400kV
yard. Total installation is
4x circuits, 1500m running
length, 400kV XLPE cables
Aug-14
R9 mil
12
Months
Client
Engineer
Eskom - RAM
subcontracting for CBI African Cables
CBI- African Cables
Waldo van Wyk
T: 078 459 7560
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
www.rame.co.za
Current Projects Data
Site
Code
Project
Title
(Continued)
Project
Description
Project
Start
Date
Project
Cost
Time
Involved
Client
Engineer
2021
Sebenza Project
Installation of 132kV cables
and cable brackets
Nov-15
R 7.8 mil
6 months
Eskom RAM subcontracting for
CBI - African Cables
Piet Marx
T: 083 304 5633
2010
Kiepersol Substation
construction of 132kV
Substation
Jun-15
R 7.45 mil
8 months
Spring Valley
Development
Bigen Africa
Johan Pieters
T: 082 410 9599
0353
Bisho Disaster
Management Centre
Electrical Installation
& Civil Works
Sep-14
R 6.1 mil
12
Months
Alexander Construction Trust
Peter Brooks
T: 082 920 4542
2022
Botshabelo
Streetlighting
Botshabelo Interchange
street lighting project
Oct-15
R 5.5 mil
5 months
SANRAL
Triocon Construction
Pieter Meyer
T: 021 552 4949
0374
Sol Plaatje University
Building 2
Electrical Installation
Mar-15
R 5.44 mil
Trencon Construction Neil
van der Westhuizen T:
082 739 2358
2008
NASREC Memorial
Park
Off grid Solar Installation with
water and irrigation systems
May-15
R 9.1 mil
11
months
Calgro M3 Holding
Nicolene Louw
T: 011 300 7540
Rudolph Evert
T: 082 825 9751
2006
Barky East Stadium
Installation of high mast
lights at Stadium
Senque Municipality N
Nkopane
T: 051 -603 1300
DFR Consulting
Engineers
Louw Brand
T: 074 889 8308
2024
Moffat Substation,
Kuruman
Upgrade of existing municipal
main intake substation
2009
Kuruman
Werkswinkel
Installation of
2 x Reclosers
Sept-15
2023
Twin City Mall
– Heidedal Bloemfontein
Supply and Install
Electrical Installation
Oct-15
Jun-15
Oct-15
R 3.24 mil
5 months
4 months
Dihlase Consulting
Engineers
Hendrik Jonck
T: 053 861 3722
R .68 mil
2 months
Dihlase Consulting
Engineers
Hendrik Jonck
T: 053 861 3722
R2.53 mil
12
months
Cupro Consulting
Fanie Smit
T: 082 923 3072
R 2.6 mil
Projects between R1million - R5million
Site
Code
Project
Title
Project
Description
Project
Start
Date
Project
Cost
Time
Involved
0374
Sol Plaatjie
University Building
C002 Project
Electrical First Fix
Feb-15
R 1.97 mil
2012
Qebe Clinic
Construction of a new
replacement clinic –
Electrical Installation
Jul-15
R1.84 mil
‘0274
Xina
Xina Solar Field –
Solar plant electrical
installation
Building Electrical
Installations, earthing and
electrical solar field
Oct-15
R 1.5 mil
Client
Engineer
Trencon Construction
Neil v.d. Westhuizen
T: 082 739 2358
6 months
Simunye Developers
T: 043 745 1399
Ballenden & Robb
Andrè Sieberhagen
Consulting Engineers
10
months
Teyma South Africa
Frederico Zanotta Rizzo
T: 021 937 0228
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 2
www.rame.co.za
Current Projects Data
Site
Code
Project
Title
(Continued)
Project
Description
Project
Start
Date
Project
Cost
Time
Involved
Client
Engineer
TP Construction
047 532 4427
Mr. Vuyani Skenjana
Ballenden & Robb
Andrè Sieberhagen
Consulting Engineers
Ballenden & Robb
Andre Sieberhagen
T: 071 851 4898
Lawrence&Victor
Construction & Civils
Leonard Bowles
T: 046 622 3205
T: 081 434 4408
6 months
MIS Pipelines
Guiliano
T: 082 334 3738
6 months
Chris Hani District
Municipality
T: 045 808 4600/67
2016
Nkwenkwana Clinic
Electrical Installation
Jul-15
R1.75 mil
6 months
0343
Ikhala Centre
Queenstown
Electrical Connection &
Building electrical
Jul-14
R 1.4 mil
1 year
0324
Komani Hospital
Queenstown
Eastern Cape
Laundry - Electrical
Installation
Apr-14
R1.3 mil
12
Months
‘0373
Babelegi Reservoir
Hammanskraal
Supply and install all motor
control distribution boards
Jun-15
R 1.3 mil
2018
Queenstown WWTW:
New Rathwick Bulk
Services (Phase 3B)
Supply & Installation of
standby diesel Generator at
Queenstown
July-15
R1 mil
Projects under R1million
Site
Code
Project
Title
Project
Description
Project
Start
Date
Project
Cost
Time
Involved
Client
Engineer
0342
Tredenham Valley
Phase 2
Electrical Connection
Jun-14
R 0.4 mil
1 year
Aurecon Consulting
Engineers
Koos Kritzinger
T: 082 770 0225
0330
Mdantsane Prison
Generator Installation
Apr-14
R 0.3 mil
6 months
Dept of Public Works
G Appels
T: 041 - 4082150
0345
Mangaung Small
Power
Electrical installation at
Northern Waste Water
Treatment works
Jul-14
R 0.27 mil
3 months
Stefanutti Stocks
0313
Kimberley Homevale
Waste Water
Treatment Works
Electrical installation
Apr-14
R 0.23 mil
3 months
0263
Bloemfontein
Race Course Bulk
Streetlight
1 month
Space Securitisation
(PTY) Ltd
Aurecon Consulting
Engineers
Koos Kritzinger
T: 082 770 0225
Bulk Streetlight installation
Aug-14
R 0.15 mil
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 3
www.rame.co.za
Completed Projects Data
Projects between R10million - R2million
Project
Description
Project
Start
Date
Project
Cost
Completion
Time
Client
Engineer
Sedibeng Iron Ore
Construction of 7.3km 132kV Power
Line and 132kV/11kV substation
Dec -14
R20.5mil
8 months
Sedibeng Iron
Ore
Eskom 132 kV Cable
Installations
Jhb = 132kV,
1000MMSQ AL XLPE
single core cables
Gauteng
Trenching and assistance with 132kV
cables installations.
1) Croydon substation to Germiston
north substation - 7 km (running
meters)
2) Croydon substation to
Bedfordview substation - 10 km
(running meters)
3) Croydon substation to Isando East
substation - 5km (running meters)
4) Lombardy substation to Edenvale
Industries - 9km (running meters)
Nov-09
1) R12.2 mil
2) R7.7 mil
3) R5.5 mil
4) R11 mil
Kroonstad Prison
Free State
Building Electrical
Security lighting
Generators
Substations
Intercom systems
Biometrical management systems
Electrical maintenance
0194
Site
Code
0385
0125
Project
Title
Engineer
Somdeb Banerjee
T: 011 459 1750
19 Months
Eskom
Frank van Heerden
Eskom Bloemfontein
T:051 435 6000 or
CBI African Cables
Willem v.d Vyver
T: 082 770 0225
M and C Consulting
Engineers
Barry Flood
T: 057 357 2763
T: 082 455 9945
CBI - African cables
Willem v.d. Vyver
T: 083 629 7088
Jan-04
R20.5 mil
36 Months
Department of
Public Works
44kV Cable JHB
1) Supply and installation of 840m of
500mm2 XLPE cable and accessories
from Isando East to Kempton Park
Substation.
2)Supply and installation of 800m of
1000mm2 XLPE cable from Horwood
Substation to Rietcons Substation.
3)The supply and installation of
2.1km 500mm2 XLPE cable form
Friskies to New Rietcons Substation,
140m extension of Croydon fo
Friskies cable and 140m cable from
Rietcons to Eskom Substation.
4)Supply and installation of 4km
of 1000mm2 XLPE cable and
accessories from Horwood Substation
to Lombardy Substation.
1) R 2.9 mil 2)
R 1.7 mil 3) R
.4 mil still under
installation
4) R 20 mil still
under installation
12 Months
Eskom - RAM
Subcontracting
for CBI - African
cables
0122
New Intermodal
Complex
11kV Reticulation and LV Reticulaton
of new taxi rank and shopping
complex
Mar-09
R16.1 mil
36 Months
Kwetse V 3
Kwetse V 3
Coenie van der
Merwe
T: 082 5600 429
0085
Cecilia Makiwane
Hospital
East London
MV reticulation - install 11kV
switchgear, Cables
Transformer
Standby generators
Building electrical
Mar-08
R16 mil
24 Months
Coega
Development
Co-operation
Rnzuza Engineers
Mr. D Flangaan
T: 082 771 6901
0008
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
www.rame.co.za
Completed Projects Data
Site
Code
Project
Title
(Continued)
Project
Description
0269
0270
0271
Free State State
Buildings
Bloemfontein
Kroonstad
Bethlehem
Free State
Electrical repairs to state owned
buildings
0197
Sandton 88kV Cable
Johannesburg
Gauteng
7km 88kv 1000mm2 single core
cable installation from Craighall
Substation to Benmore Substation
Project
Start
Date
Project
Cost
Completion
Time
Client
Mar-13
R14.6 mil
12 Months
Depart. of
Public Works
18 Months
Eskom - RAM
Subcontracting
for
CBI - African
cables
CBI - African cables
Willem v.d. Vyver
T: 083 629 7088
Aurecon Consulting
Engineers -B
Devenish T: 051408 9610
Dec-11
R14 mil
Engineer
Department of
Public Works
Mr Pule Thole
T: 051 408 7340
0272
Heuningsvlei
Solar Installation
Feb-13
R13.6 mil
12 Months
Joe Morolong
Municipality
0181
UMK Mine
Electrical reticulation, lighting and
small works
Sep-11
R11.60 mil
30 Months
UMK Mines
Goba Consulting
Engineers
Mark Louw
T: 011 236 3300
0105
New complex for
South African Police
Services
Cradock
Eastern Cape
Construction of new police station
including electrical and mechanical
installation and high tension
reticulation
Dec-08
R12.60 mil
29 Months
Department of
Public Works
Frans van Zyl
T:083 680
2456
Carifo
Aiden Sweetman
T: 041 368 1717
0072
Upgrade for FIFA
2010 World Cup
soccer
Free State Stadium
Bloemfontein
Free State
Electrical installation and reticulation
of low voltage and high voltage
installations
Upgrading Free State Stadium for
2010 World cup soccer
Sep-08
R11.14 mil
12 Months
Ruwacon
Koos Kritzinger
Tell: 051 447 1636
T: 082 770 0225
Client
Engineer
Projects between R5million – R10million
Site
Code
Project
Title
Project
Description
0297
Kouga Windfarm
- Civil work and
installation of 33kV
connector cables
Oysterbay
Easter Cape
Civil works and installation of 33kV
and LV cables between wind turbines/
substation , LV connector cables
between turbines and transformers,
road crossings, fibre optic etc.
0134
Kimberley GWK
Stadium - for FIFA
2010 world cup
Kimberley
Northern Cape
0232
Postmasburg New
Connection
Upgrade of the lights to serve as a
training facility for a base camp
New Mall electrical connection
Project
Start
Date
Sep-14
Mar-10
Mar-12
Project
Cost
R10 mil
R9.78 mil
R9.1 mil
Completion
Time
8 Months
Actom - RAM
CBI- African Cables
Willem v.c Vyver
T: 083 629 7088
Matshele
Monnakgotla
T: 082 800 8698
2 Months
Depart. of
Roads and
Public Works
Heyns van
Rooyen Consulting
Engineers
Heyns van Rooyen
T: 083 259 2271
2 months
Purple
Fountain
Properties
Dihlase Consulting
Engineers
Hendrik Jonck
T: 053 861 3722
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 5
www.rame.co.za
Completed Projects Data
(Continued)
Project
Start
Date
Site
Code
Project
Title
Project
Description
0082
Atteridgeville Prison
Pretoria
Gauteng
Repair and maintenance to electrical
and mechanical installation and
maintenance
RAMP Project
Mar-08
0180
Solar Geyser
installation
Port Elizabeth
Eastern Cape
Solar Geyser installation in RDP
houses
Installation of 15 000 geysers
0292
Letsatsi PV Farm
Solar PV Plant
Grootvlei Prison Bloemfontein
Free State
11kV cable installation
2 x 1000kVA miniature substations complete installation
11kV protection design, install and
commission
Low voltage cabling in laundry,
kitchen, prison etc.
1.2MVA Genset - install generator,
switch over board and commision
Building electrical
Installation to court
Completion
Time
Client
R8.58 mil
36 Months
Depart of
Public Works
Mnjiya Consulting
Engineers
Raymond
T: 011 3182849
Jan-11
R8.5 mil
36 Months
Eskom
HDC Industries
Alkara 79 cc
Nico Gouws
T: 053 831 1260
Jul-13
R 8.2 mil
8 Months
Raubex
Raubex
Dirk Lourens
T: 051 -406 2000
R7.5 mil
8 Months
Department of
Correctional
Services
Ingali Engineers
Mr. Lotter
T: 051 430 5435
T: 082 959 149
Nov-06
Eskom Homestead
Refurbishment of all 132kV and
66kV equipment and extension of
feeder bay
Feb-15
R6.5 mil
8 months
Eskom
Eskom
P Zitha
T: 053 830 5415
Jan Pan
Theunissen
Free State
11kV overhead line feeder
strengthening (construction of new
and existing O/H lines for Eskom)
Mar-13
R6.8mil
12 Months
Eskom
Paseletso Faba
T: 082 812 7378
T: 051 404 6442
0090
Free State Stadium
and Athletics for
2010 soccer
world cup
Bloemfontein
Free State
Install 246 New Flood lights and
control gear install 10 x D/B Boards
for lights
Install new LV cable network to lights
aiming commissioning
Free State athletics - Remove old
fittings from Free State Stadium and
installed at athletics stadium.
Refurbished re-lamp, install new
control gear
Upgraded to 200 Lux and 11kV
cables
11kV mini subs
New LV cables
Erect old masts
Jun-08
R6.8 mil
24 Months
Mangaung
Local
Municipality
Dihlase
Sarel Esterhuizen
T: 083 262 1699
0327
Eskom Canal
Substation
Apr-14
R 6.6 mil
12 Months
Eskom
Eskom K Zitha
T: 053-830 5415
0286
Postmasburg
Tsantsabane Community High Mast
Lighting
Jun-13
R 6.4 mil
Eskom
Dihlase Consulting
Engineers
Hendrik Jonck
T: 053-342 4648
0231
Chris Hani Gensets
Supply and installation of standby
generator
Mar-12
R6.0 mil
Infrastructure
Development
Gauteng
Province
Infrastructure
Development
Oliver Chimuru
T: 011 355 5000
0033
0393
0276
Project
Cost
Engineer
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 6
www.rame.co.za
Completed Projects Data
Site
Code
Project
Title
(Continued)
Project
Description
0099
132kVA cable
installation Subcontract for
CBI-African Cables
Bloemfontein
Free State
Civil works to prepare cable trenches
in bottom of storm canal.
Assist CBI-African cables with the
installation of the cables
Restore earthworks to normal concrete and steel works to repair
canal floor
0174
Eskom 11kV
cable installations
Vosloorus
Gauteng
Civil works: Trenching and installation
of 300Sq mm cables - three projects
1) Nguni sub to Womens Hostel Sub
2) Nguni sub toMoagi Sub
3) Nguni Sub to Didetso Sub
Project
Start
Date
Sep-08
May-11
Project
Cost
R6.6 mil
R6.5 mil
Completion
Time
Client
Engineer
12 Months
CBI - African
Cables
CBI - African Cables
Coen Boshoff
T: 083 637
9924
or
CBI African Cables
Willem v.d Vyver
T: 082 770 0225
4 Months
Eskom - RAM
Subcontracting
for CBI - African
cables
CBI - African cables
Mr Coen Boshoff
T: 082 5600 429
6 Months
Eskom - RAM
Subcontracting
for
CBI - African
cables
Ekurhuleni Metro
Municipality
or
CBI African Cables
Willem v.d Vyver
T: 082 770 0225
Planet Waves
179
Koos Kritzinger
Consulting
Engineers
Koos Kritzinger
T: 082 770 0225
Depart of Public
Works
Ms Thembisile
Madonsela
T: 011 713 6155
Nampak 33kV Cable
9.6km 33kV 500mm2 single core
cable installation in Wadeville for
Nampak
Hillside 1,2,3
Bloemfontein
Free State
11kV Primary substation, 315kVA
and 500 kVA miniature substation
installation
11kV cable reticulation
Low voltage reticulation to
connection boxes
Street light installation
Test and commission
Installation and hand-over to Centlec
0224
SAPS Jhb Generators
Supply and installation of emergency
generator sets at Langlaagte,
Mondeor, Buccleuch, Elsburg, Benoni
Radio Tech college & K53 and
Daveyton
Jan-12
R5.7 mil
Department of
Public Works
0070
Industrial Park East
End
Bloemfontein
Free State
New 11kV and Low voltage design,
supply and installation of electrical
network as well as ware house
electrical installation
Aug-07
R5.5 mil
24 Months
JM Onderstal
Property
Developers
0196
0045
Nov-11
Apr-07
R6 mil
R5.9 mil
48 Months
Mr JM Onderstal
T: 082 770 5505
Projects between R1million – R5million
Site
Code
0119
Project
Title
Zwelitsha
Court Bisho
Eastern Cape
Project
Description
Repair and Maintenance of
electrical installation
Project
Start
Date
Project
Cost
Completion
Time
Client
Jun-09
R4.9 mil
1 Year
Department
of Public Works
Engineer
Mr A Myathaza
T: 082 565 0868
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 7
www.rame.co.za
Completed Projects Data
(Continued)
Project
Description
Project
Start
Date
Project
Cost
Completion
Time
Client
Engineer
May-13
R4.9mil
7 months
Eskom
Holdings
Mr Albertus Teseling
T: 051 404 2553
R4.73 mil
36 Months
Department of
Public Works
Element Consulting
Engineers
Mr. D. Henning
T: 043 726 0074
R4.58 mil
36 Months
Department of
Justice
KV3 Engineers
Louw Cornelesen
T: 083 627 1907
R4.5 mil
4 Months
Setsoto Local
Municipality
Epitome Consulting
Engineers
Mr Vusi
T: 083 5560 676
Apr-06
R4.43 mil
36 Months
Department of
Public works
Ukhukhula
Consulting
Mr Grobelaar
T: 012 644 0291
Mar-13
R4.4 mil
12 Months
Eskom
Paseletso Faba
T: 082 812 7378
T: 051 404 6442
36 Months
Department of
Public works
Virtual Buro
Mr. Malan
T: 012 452 0450
T: 082 875 5763
R4.06 mil
36 Months
Department of
Public Works
Virtual Buro
Mr. Malan
T: 012 452 0450
T: 082 875 5763
R4.01 mil
24 Months
Department of
Public works
BVI Consulting
Mr W Bouwer
T: 051 447 2137
Site
Code
Project
Title
0285
Beatrix Mine Welkom
132/6.6kV Substation Refurbishment
0050
Bisho Airport
East London
Eastern Cape
11kV substation maintenance service switchgear, replace battery
charger, replace protection relay’s
and commission
Low voltage cable reticulation replace
papi cables
Cable Fault location
Replace High mast lights and cables
Install streetlights
Building - New electrical
Installations in fire station
Living Quarters, Tower,
Terminal building etc.
Mar-07
0003
Cape Town High
Court
Cape
Building electrical
Mechanical installations
Electrical maintenance
Mechanical maintenance
Jan-06
0249
0251
0252
0253
Setsoto Municipality
Ficksburg
Senekal
Marquard
Installation of High Mast lights in
Setsoto
Aug-12
0015
Lesotho / Kwazulu
- Natal Borderline
basis
RAMP Project
Kwazulu - Natal
Building electrical
Security lighting
Air conditioning
Kitchen Equipment
Generators
UPS Systems
Electrical maintenance
0277
Kgotsong
Bothaville
Free State
11kV overhead line feeder
strengthening (construction of new
and existing O/H lines for Eskom)
0010
Rammatlabama
Port of entry
RAMP Project
Mafikeng
North - West
Province
Building electrical
Security lighting
Air Conditioning
Generators
UPS Systems
Electrical maintenance
Civil maintenance
0020
Swaziland /
Mpumulanga
Borderline basis
RAMP Project
Mpumulanga
Building electrical
Security lighting
Air Conditioning
Kitchen Equipment
Generators
UPS Systems
Electrical maintenance
Mar-06
0068
Phillip Sanders
Bloemfontein
Free State
Electrical installations and audio
visual
Oct-07
Feb-05
R4.17 mil
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 8
www.rame.co.za
Completed Projects Data
Site
Code
Project
Title
(Continued)
Project
Description
Project
Start
Date
Project
Cost
Completion
Time
Client
Virtual Buro
Mr. Malan
T: 012 452 0450
T: 082 875 5763
Engineer
0044
Lebombo
-Komatipoort
Port of entry
Mpumulanga
Building electrical
Security lighting
Air Conditioning
Generators
UPS Sytems
Electrical Maintenance
Civil Maintenance
Apr-07
R3.9 mil
36 Months
Department of
Public works
0081
Murray Hill
South African Police
Services
Pretoria
Gauteng
New Electrical installation of special
forces training facility
Mar-08
R3.72 mil
14 Months
Department of
Public works
Ruwacon
Kobus Markram
T: 083 265 2695
0339
Jan Kempdorp &
West End Hospital
Generator installations
Jun-14
R 3.6 mil
6 months
Mekan Consulting
Engineers S Bakubaku
T: 083 208 2649
0265
Vista Park
Bloemfontein
Free State
Construction of Electrical services
- Phase 4
Jan-13
R3.5 mil
6 Months
Benchmark
Development &
Construction
Aurecon Consulting
Engineers
0014
Lesotho / Free State
Borderline basis
RAMP Project
Building electrical
Security lighting
Air conditioning
Kitchen Equipment
Generators
UPS Systems
Electrical maintenance
36 Months
Department of
Public works
Ukhukhula
Consulting
Mr Grobelaar
T: 012 644 0291
0135
UPS Installation on
floodlights for Free
State Stadium for
2010 World Cup
Bloemfontein
Free State
Installation of 1x 60kVA
1x 100kVA
2x 160kVA
1x 275kVA UPS For back up for
floodlights
Apr-10
R3.50 mil
1 Month
Mangaung
Local
Municipality
Dihlase
Coenie Jansen van
Rensburg
T: 051 447 1636
0096
Parmalat
Gabarone
Botswana
Install 11kV Cable
Install 1000 kVA Transformer
Install cables to main D/B
Do all the reticulation for the whole
new factory
Jul-08
R3.5 mil
3 Months
Parmalat SA
Pincor Consulting
Ian Pienaar
T: 083 09 0391
0103
University of the
Free State
Bloemfontein
Free State
Substation
Switchgear
New substation building
Mar-09
R3.4 mil
14 Months
University
of the
Free State
CKE Engineers
Ben Joubert
Tell: 051 444 4728
T: 082 565 0868
0079
Maluti - Border
bases
RAMP Project
Lesotho
Kwazulu - Natal
Repair, upgrading and maintenance
of buildings, civil infrastructure,
electrical installations and mechanical
equipment for 3 border-line bases
Feb-08
R3.41 mil
36 Months
Department of
Public works
Ikhulhula Engineers
Mr J Kruger
T: 082 335 0535
Mr T De Beer
T:079 892 7594
0107
Brandwag Hotel
Golden Gate
Free State
Upgrade of hotel in Highlands
National Parks: Electrical installation
Jan-09
R3.40 mil
12 Months
Sanparks
Vela Vke Engineers
Jan Voster
T: 012 461 3800
Apr-11
R3.5 mil
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 9
www.rame.co.za
Completed Projects Data
(Continued)
Project
Description
Project
Start
Date
Site
Code
Project
Title
0029
Soweto Magistrates
court
RAMP Projects
Gauteng
Electrical installation
Air conditioning
Fire fighting
Nov-06
0171
Lesotho Botshabelo
Hospital
Design and construct of Botshabelo
complex - Lesotho blood transfusion
service centre
0175
Brandwag Social
Housing Dev.
Electrical Connection
0164
Senekal
Correctional
Services
Free State
Repair and upgrade of electrical
and mechanical installations and
maintenance
RAMP Projects
0291
Mandela View Phase
2.2
Medium & low voltage Electrical
Reticulation
Jul-13
0242
ECDC Premiers
Office Bisho
Upgrade alterations and additions:
Electrical installation
May-12
0052
Bethlehem Social
Developments
Free State
New Office Block for social
development
Electrical installations
Installation of 11kV mini subs
Supply and install standby generators
Apr-07
0089
Pinelands SAPS
Baracks
Cape Town
Western Cape
Complete Electrical renovations
Install new standby generator
Apr-08
0188
Ladygrey - Kwezi
Naledi High Mast
Soccer stadium lighting upgrade
0298
East London Airport
Genset
Supply and installation of 2x500KVA
Generators
0151
Benmore Gardens
Shopping Centre CBI Cable Protection
Gauteng
Relocation of ESKOM cables at
shopping centre - 400m trenching,
relocating of 44kV cable, a 6,6kV
cable and 4 x 11kV cables
0341
Kimberley Talama
Square
Electrical Connection
Completion
Time
Client
R3.3 mil
36 Months
Depart of
Public Works
Kamble Davis
Constulting
Mr Webster
T: 083 378 2907
Apr-11
R3.2 mil
12 Months
Sanyati Civil
Engineering
Construction
Trio Con Consulting
Johan Grant
T: 082 374 5591
Jan-14
R 3.2 mil
3 year
24 Months
Department
of Public Works
Mustapha &
Cachalia
Barry Flood
T: 057 357 2763
R 3.24 mil
3 months
Akey
Developments
Aurecon Consulting
Engineers
Chris Johnson
T: 051-4478911
R3.0 mil
6 months
Siya Zama
GVK Building &
Renovation
GVK
Colin Bread
T: 041 365 1557
R3.0 mil
24 Months
Department of
Public Works
S & W Consulting
Mr Wessels
T: 058 622 2263
T: 082 446 4116
R3.0 mil
18 Months
Depart of
Public Works
SSI
Mr Leon Hans
T: 073 345 1695
5 Months
Senque
Municipality
T: 051
6030019
DFR Engineers
Louan Schlebusch
T: 041 582 1453
3 months
CA du Toit Cons
Engineers
Dawid Bester
T: 041 585 7559
3 Months
Eskom - RAM
subcontracting
for CBI African
cables
CBI African Cables
Coen Boshoff
T: 016 430 6291
or
CBI African Cables
Willem v.d Vyver
T: 082 770 0225
Sol Plaatje Mun
Dihlase Consulting
Engineers
Hendrik Jonck
T: 053 861 3722
Jan-11
Nov-11
Sep-14
Oct-10
Jun-14
Project
Cost
R3.2 mil
R2.95 mil
R 2.93 mil
R2.91 mil
R 2.89 mil
3 months
Engineer
Calgro M3
Deon Steyn
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 10
www.rame.co.za
Completed Projects Data
Site
Code
Project
Title
(Continued)
Project
Description
0001
Bisho High Court
Bisho
Eastern Cape
Building electrical
Security lighting
Air Conditioning
Generators
Electrical maintenance
Civil maintenance
0042
Red Cross Hospital Rondebosch
Cape Town
Western Cape
Replacement of 11kV switchgear and
commissioning
11,440kV/400V transformers replace and commissing
Replace LV boards complete
schedule shutdowns
0004
Cape Town SAPS
Garages Maitland
Cape Town
Western Cape
Building electrical
Mechanical installations
Electrical maintenance
Mechanical maintenance
Intercom system
Electrical fencing
0179
Maria Moroka Nature
Reserve
Overhead line
Project
Start
Date
Project
Cost
Completion
Time
Client
Apr-05
R2.8 mil
36 Months
Department of
Justice
KV3 Engineers
Mr. Viljoen
T: 043 721 0055
Feb-07
R2.8 mil
8 Months
Department of
Public works
BFBA Consulting
Mr. West
T: 021 421 0860
14 Months
Department of
Public works
De Villiers and
Moore
Mr. Dippenaar
T: 021 976 3087
T: 083 375 8992
12 Months
Dept. of
Public Works
and Rural
Development
Drake and Skull
Wyers Ludick
T: 082 769 8243
Heyns van
Rooyen Consulting
Engineers
Heyns van Rooyen
T: 083 259 2271
De Vos Pecksten
Johann De Bruin
T: 082 372 2685
Oct-05
Jul-11
R2.7 mil
R2.64 mil
Engineer
0149
Kathu Sesheng
Nothern Cape
Electrification of 98 stands in
Sesheng
Aug-10
R2.63 mil
6 Months
Gamagara
Local
Municipality
0144
Shoprite Ficksburg
Free State
11kV Reticulation
LV Reticulation
Building electrical
Jun-10
R2.63 mil
5 Months
Water Comfort
Wholesale
0286
Harmony North
44/6.6 kV
Welkom
Free State
44/6.6kV Substation Refurbishment
May-13
R2.6 mil
7 months
Eskom
Holdings
0282
Grasslands Phase
2 Dev.
New Development
Jun-13
R2.4 mil
12 months
Central
Development
Prop Group
FCE Consulting
Engineers - Stefan
Esterhuysen
T: 051 451 2612
0009
Mosselbay Prison
Eastern Cape
Building electrical
Security lighting
Airconditioning
Generators
Hotwater generation
Intercom system
Kitchen Equipment
Electrical maintenance
Civil maintenance
Jan-05
R2.46 mil
36 Months
Department of
Public works
Naylor, Naylor and
van Schalkwyk
Mr. Walters
T: 083 629 8154
136
Brandfort
Tollgate
Free State
Electrical installation and 200kVA
standby generator construction
of Toll Plaza R30
Jun-10
R2.3 mil
8 Months
South African
National Road
Agency
Aurecon
Steve Kruger
T: 012 427 2330
Mr Albertus Teseling
T: 051 404 2 553
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 11
www.rame.co.za
Completed Projects Data
Site
Code
Project
Title
(Continued)
Project
Description
Project
Start
Date
Project
Cost
Completion
Time
Client
Mar-06
R2.39 mil
36 Months
Department of
Public works
Virtual Buro
Mr. Malan
T: 012 452 0450
T: 082 875 5763
Engineer
0017
Leeuwkop Prison
RAMP Project
Gauteng
Building electrical
Security lighting
Air Conditioning
Generators
UPS Systems
Electrical maintenance
0018
Northern Cape
Labour centres and
service products
Kimberley, Upington,
Kuruman
Northern Cape
Building electrical
Security lighting
Air Conditioning
Electrical maintenance
Mechanical installations
Spray booths, compressors etc.
Mar-06
R2.3 mil
36 Months
Department of
Labour
KV3 Engineers
Mr. Hubert
T: 053 831 4199
0019
Centlec Electrical
connections to
900 stands Bloemfontein Free
State
Electrical connections to 900 stands
High voltage overhead reticulation
Transformer installations
LV Reticulation
Mar-06
R2.3 mil
4 Months
Centlec
Centlec
Mr. van der Walt
T: 051 409 2232
0011
Waterval Prison
RAMP Project
Kwazulu - Natal
Building electrical
Security lighting
Electrical maintenance
Mar-04
R2.2 mil
36 Months
Department of
Public works
KV3 Engineers
Mr. Strydom
0088
Ysterplaat Air Force
Base
Cape Town
Western Cape
Reticulation
Generators
Building electrical
Apr-08
R2.1 mil
6 Months
Department of
Public works
Tsepa Engineers
Mr. Febion
T: 079 833 5727
0146
St Rita’s
Hospital
Limpopo
Staff housing and laundry electrical installation and
reticulation
Jul-10
R1.9 mil
18 Months
Department
of Public Works
KV3
Nico Britz
T: 082 450 8917
0028
Sasko Bakery
Bloemfontein
Free State
Design primary substation
Design bakery electrical
Distribution and boards
New office development reticulation
1.8 MVA 11kV/400V transformer
installations
Air Conditioning
Access control
Aug-06
R1.9 mil
12 Months
Pioneer Foods
Civil Engineers
Phillip De Waal
T: 012 346 2568
0060
LCRC
Gauteng
Revamp of SAPS Laboratories
May-07
R1.8 mil
36 Months
Department of
Public works
Virtual Buro
Mr. Malan
T: 012 452 0450
T: 082 875 5763
0139
Transnet City
Deep
Gauteng
HT and LT Reticulation to new
warehouse electrical installation to
complete warehouse
Jul-10
R1.7 mil
11 Months
Ruwacon
Kobus Markram
T: 083 265 2695
0274
Kaxu Mirror
Assembly
Pofadder
Northern Cape
Mar-13
R1.7 mil
12 Months
Ruwacon
0234
Ratanang Sport
Stadion
Improvements including flood light
installation
Feb-12
R1.7 mil
Mofomo
Construction cc
Raymond Seboko
T: 057 355 2306
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 12
www.rame.co.za
Completed Projects Data
Site
Code
Project
Title
(Continued)
Project
Description
Project
Start
Date
Project
Cost
Completion
Time
Client
R 1.63 mil
Apr-11
R1.6 mil
6 Months
University
of the
Free State
CKE Engineers
Ben Joubert
T: 082 565 0868
Civil Sense
Consulting
Johan Hubert
T: 082 829 4357
Engineer
0168
Boitumelo Hospital
Electrical installation
170
University of the
Free State
Proefdier Substation
Bloemfontein
Free State
11kV Internal network upgrade
0173
Kathu SIOC Office
Development
Northern Cape
Office development electrical
installation
Apr-11
R1.6 mil
16 Months
Department
of Public Works
0169
Bloemside
Kamohelo
Primary School
Free State
Lt Reticulation and building electrical
Mar-11
R1.6 mil
15 Months
Department
of Public Works
Nedgroup SA
D. Bubb
T: 082 824 1288
0159
Kathu CAT
Barloworld
Norhten Cape
LV Reticulation and building
electrical
Oct-10
R1.6 mil
8 Months
Department
of Public Works
Civil Sense
Consulting
Johan Hubert
T: 082 829 4357
0141
Leandra
Tollgate
Mpumulanga
Electrical installation to new
Tollgate buildings
Jun-10
R1.5 mil
18 Months
Ruwacon
Kobus Markram
T: 083 265 2695
8 Months
SA Police
Service
Divisional
Commissioner
Supply Chain
Management
Snr Supt. P van der
Westhuizen
T: 012 845 8991
0133
Giyani South African
Police Services
Limpopo
Electrical and air conditioning and
generator installation
New CSC Block
0059
Saldanha SAPS
Cape Town
Western Cape
Electrical installation of New South
African Police Station
Jul-07
R1.4 mil
24 Months
Department of
Public works
0299
Warrenton O/H lights
Installation of high mast lights at
bridge
Jan-14
R 1.13 mil
3 months
0113
Postmasburg
Transnet A - Prep
Depot
Northern Cape
Building on new train depot
Lighting, D/B, Cabling, Wiring and
domesting power
0021
Beaufort - West
Prison
Northern Cape
Building electrical
Security lighting
Air Conditioning
Generators
Hot water generation
Intercom system
Electrical maintenance
0111
Botshabelo stadium
lights
Free State
Upgrade, repair and renovate the
flood lights to 750 Lux for the
training venue for FIFA 2010 World
cup soccer
Mar-10
Apr-09
Jul-06
Apr-09
R1.43 mil
R1.3 mil
R1.3 mil
R1.28 mil
4 Months
Transnet
West Coast
Consulstin
Mr P Marais
T: 022 713 2637
CKE Engineers
Ben Joubert
Tell: 051 444 4728
T: 082 565 0868
36 Months
Depart of
Public Works
De Villiers and
Moore
Mr. Dippenaar
T: 021 976 3087
T: 083 375 8992
12 Months
Mangaung
Local
Municipality
Dihlase
Frans Buter
T: 051 447 1636
T: 083 279 8200
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 13
www.rame.co.za
Completed Projects Data
Site
Code
Project
Title
(Continued)
Project
Description
Project
Start
Date
Project
Cost
Completion
Time
Client
Koos Kritzinger
Consulting
Engineers
Koos Kritzinger
T: 082 770 0225
Engineer
0091
Tredenham valley
Residential
Development
Bloemfontein
Free State
LV reticulation
House connection boxes
Streetlight installation work
Apr-09
R1.22 mil
9 Months
Koos Kritzinger
Consulting
Engineers
0130
N8 Airport inter
section bridge
Bloemfontein
Free State
Street light and LV reticulation
Jan-10
R1.21mil
5 Months
SSI
Christoffer Koa
T: 051 400 7200
0012
Johannesburg
Magistrates court
RAMP Project
Gauteng
Building electrical
Security lighting
Air Conditioning
Generators
UPS Systems
Electrical maintenance
Civil maintenance
Feb-06
R1.2 mil
36 Months
Department of
Public works
Manong and ass.
Mr. Malamela
T: 011 311 2040
0013
Sutherland
Magistrates court
RAMP Projects
Western Cape
Building electrical
Security lighting
Air Conditioning
Electrical maintenance
Apr-06
R1.2 mil
36 Months
Department of
Justice
Virtual Buro
Mr. Malan
T: 012 452 0450
T: 082 875 5763
0104
Transnet A - Prep
Depot
New Castle
Kwazulu - Natal
Building of a new transnet depot
Lighting
D/B
Cabling
Wiring and domestic power
Nov-09
R1.2 mil
8 Months
Transnet
Sivest EDM
Bruce Garrett
T: 084 888 6919
0076
Skilpadshek
Port of entry
Zeerust
North - West
Repairs to building electrical and
external lighting and generators
Nov-07
R1.2 mil
5 Months
Department of
Public works
Virtual Buro
Mr. Malan
T: 012 452 0450
T: 082 875 5763
0386
3 SAI BN
Installation of Temporary Electricity
Supply for Temporary Mess
Feb-15
R 1.14 mil
14 Days
Dihlase Consulting
Engineers
Hendrik Jonck
T: 053 861 3722
0262
Steynville High Mast
Steynville
Northern Cape
25 Metre Mid-Hinge High Mast
lighting at Mandela Square Steynville
Nov-13
R1.1 mil
12 Months
Thembelihle
Municipality
Dihlase Consulting
Engineers
Hendrik Jonck
T: 053 861 3722
0191
Gariepdam Fish
Hatchery A
Electrical installation
Oct-11
R1.08 mil
2 Months
Dikopo
Aurecon
Brain Devenish
Tell: 051 447 8911
0199
Lesotho - Blood
Transfusion Lab
5 months
Sanyati
Engineering
Central
Sanyati Engineering
Central
Hendrikjan Mosca
T: 051 411 5820
0200
Lesotho - Staff
Accommodation
5 months
Sanyati
Engineering
Central
Sanyati Engineering
Central
Hendrikjan Mosca
T: 051 411 5820
Electrical installation and Generators
Electrical installation and Generators
Jan-12
Jan-12
R1.07 mil
R1.07 mil
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 14
www.rame.co.za
Completed Projects Data
Site
Code
Project
Title
(Continued)
Project
Start
Date
Project
Description
Project
Cost
Completion
Time
Client
Engineer
5 months
Sanyati
Engineering
Central
Sanyati Engineering
Central
Hendrikjan Mosca
T: 051 411 5820
Sebokwa
Engineering
Lawrence Bekker
T: 012 343 0602
T: 082 653 4299
0201
Lesotho - Student
Dormitories
Electrical installation and Generators
0041
Oliver Thambo
House
Pretoria
Gauteng
HT Reticulation
LV Cabling
Upgrade of DB Boards
Air Conditioning
Feb-07
R1.06 mil
24 Months
Department of
Public works
0084
Atlantis South African
Police Services
Western Cape
Renovation and rewiring of SAPS
station
Building Electrical
Mar-08
R1.02mil
14 Months
Department of
Public Works
4EM
Fatiegh Soeker
T: 082 821 3563
0230
University of Fort
Hare
Servicing of Medium Voltage
switchgear and replacement of some
low voltage distribution boards
Feb-12
R1.0 mil
University of
Fort Hare
Richard Nzuza &
Associates
Richard Nzuza
T: 043 742 0041
0087
Riebeeck Wes
South African Police
Services
Western Cape
Renovation and rewiring of SAPS
station
Building electrical
Apr-08
R1.0 mil
14 Months
Depart of
Public Works
BFBA Consultants
Mr I Alloe
T: 083 442 7371
Completion
Time
Client
Engineer
Worley Parsons
Resources & Energy
Peet van den
Heever
T: 053 831 4199
T: 082 925 0442
Jan-12
R1.07 mil
Projects under R1million
Site
Code
Project
Title
Project
Description
Project
Start
Date
Project
Cost
0182
Petrusville Sport
Complex
Upgrading of Sports complex
Aug-11
R0.99 mil
5 Months
Renosterberg
Municipality
T:053 663
0041
0112
Middelburg Military
Base
Gauteng
Electrical upgrade
Apr-09
R0.96 mil
12 Months
Ruwacon
Kobus Markram
T: 083 265 2695
0074
Mananga building
houses
Nelspruit
Mpumulanga
Repairs Building electrical and
external lighting
Aircon installation and generators
Nov-07
R0.9 mil
5 Months
Department of
Public Works
Virtual Buro
Mr Malan
T: 012 452 0450
T: 082 875 5763
0066
Jackson House
Bloemfontein
Free State
Electrical installation of residential
house
Jul-07
R0.9 mil
24 Months
Groenewaldt
& Preller
Argitekte
De Villiers & Moore
Mr J Dippenaar
T: 021 976 3087
0152
Babelegi
Water works
Limpopo
Installation of a new motor starter
panel for pump station
Oct-10
R0.9 mil
14 Months
Ruwacon
Kobus Markram
T: 083 265 2695
0142
MTN Bloemfontein
(HVRC)
Free State
Electrical installation
1x 165kVA UPS Installation
May-10
R0.8 mil
3 Months
MTN
Bloemfontein
Phakamile
Engineering
Jama Dlamini
T: 011 726 1647
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 15
www.rame.co.za
Completed Projects Data
Site
Code
Project
Title
(Continued)
Project
Description
Project
Start
Date
Project
Cost
Completion
Time
Client
Engineer
Heyns van
Rooyen Consulting
Engineers
Heyns van Rooyen
T: 053 8311609
0237
Kathu erf 4106
Electrical supply to erf 4106
Mar-12
R0.8 mil
SOIC
Community
0382
Harvard Southdrift
T-off
Installation of 2 x 132kV in-line
Isolator
Jun-15
R0.75
3 months
Eskom
8 Months
Department of
Transport and
Public
Department of
Transport and
Public
F Wuim
T: 021 483 5867
Dihlase
Frans Buter
T: 051 447 1636
T: 083 265 2695
Eskom
J. Litlhakanyane
0163
Red Cross Hospital
Rondebosch
Cape Town
Western Cape
Service and replacement of HT
switchgear
0109
Siesa Ramabudo
Stadium
Bloemfontein
Free State
Upgrading of the existing 500kVA
supply to 1000kVA
Aug-09
R0.7 mil
3 Months
Mangaung
Local
Municipality
0165
Ficksburg Clicks
Free State
11kV reticulation
LV reticulation
Building electrical
Jan-11
R0.7 mil
2 Months
Water Comfort
Wholesale
De Vos Pecksten
Johann De Bruin
T: 082 372 2685
0153
University of the
Free State New
Miniature substation
Bloemfontein
Free State
Installation of a new miniature
substation for UFS swimming pool
Sep-10
R0.7 mil
10 Weeks
University of
the Free State
KV3 Engineers
FCE van der Merwe
T: 051 410 8700
0098
Health Treasure
East London
Eastern Cape
Installation of additional plug points
Sep-08
R0.7 mil
2 Months
Dimension Data
Mr Willem Botha
0061
Graaf Reinette
South African Police
Services College
Eastern Cape
Electrical Renovations
Jul-07
R0.7 mil
8 Months
Department of
Public works
RNA Engineers
Steve Lavis
T: 082 905 2010
0048
Ruwacon Service
Products
Bloemfontein
Free State
Upgrade of electrical installations
May-07
R0.7 mil
24 Months
Department of
Public Works
Dirk van Heerden
Engineers
Dirk van Heerden
T: 051 448 0185
T: 082 446 2981
0035
Parys Street Lights
Free State
Installation of street lights
Feb-07
R0.7 mil
2 Weeks
Meyker
Construction
0040
Admiralty house
Simonstown
Western Cape
Building electrical
Air Conditioning
Maintenance
Feb-07
R0.6 mil
36 Months
Department of
Public Works
BVI Engineers
Mr Reighert
T: 021 567 7000
0046
Kwaggafontein Industrial Park
Bloemfontein
Free State
Design of 11kV and low voltage
reticulation of industrial erven
May-07
R0.6 mil
24 Months
Qwaha Trust
Piet Beukes
T: 082 881 2911
0063
Grahamstown
Old School
Eastern Cape
Electrical and mechanical upgrading
of historic building
Jul-07
R0.6 mil
24 Months
Department of
Public Works
RJ Waters & Ass.
Mr RJ Waters
T: 041 463 1694
Jan-11
R0.8 mil
Meyker Construction
Mr De Bruin
T: 083 262 1230
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 16
www.rame.co.za
Completed Projects Data
Site
Code
(Continued)
Project
Description
Project
Start
Date
Project
Cost
Completion
Time
Client
Temporary electrical connection for
TMFS
2x Temporary connections for LOC
Standby during FIFA 2010 World Cup
soccer
Installation of 4x Mini subs and HV
reticulation
May-10
R0.6 mil
2 Months
LOC
Dihlase
Koos Kritzinger
T: 082 7700 225
Project
Title
Engineer
0137
Free State Stadium
Overlay for FIFA
World Cup 2010
Bloemfontein
Free State
0128
Ruwacon Student
House
Bloemfontein
Free State
Electrical installation
Oct-09
R0.5 mil
1 Month
Ruwacon
Ruwacon
Peter Ruthven
T: 051 403 0400
T: 082 205 5843
0047
Melanie Street 12 Pentagon Park
Bloemfontein
Free State
Electrical installation - Duet house
Jun-07
R0.5 mil
4 Months
Piet Beukes
Piet Beukes
T: 082 881 2911
0071
Burgersdorp
Hospital
Eastern Cape
Electrical installation in guard house
Sep-07
R0.5 mil
3 Months
Department of
Public Works
Allan Dale and Rob
Mr J van der Merwe
0077
Robben Island
Sebokwe House
Cape Town
Western Cape
Electrical repairs and renovations
Oct-07
R0.45 mil
24 Months
Meirelles
Lawson Burger
Argitekte
De Villiers & Moore
Mr J Dippenaar
T: 021 976 3087
0093
Settlers Hospital
Graaff Reinette
Eastern Cape
Supply and install 11kV SF6 type
circuit breakers
Terminate 11kV cables
Aug-08
R0.42 mil
1 Month
SSI Consutling
Engineers
SSI Consulting
Engineers
MR Otto Moffat
T: 051 400 7200
0143
UFS Soccer
Reticulation
Free State
Installation of cable and kiosk
Lighting protection
Jul-10
R0.4 mil
3 Months
University
of the
Free State
CKE Engineers
Ben Joubert
T: 082 565 0868
0138
Branding material
for FIFA World Cup
Bloemfontein
Free State
Removal, storage and re-installation
of existing branding at FIFA
designated venues in the Mangaung
Host City for the 2010 FIFA World Cup
Apr-10
R0.4 mil
3 Months
Mangaung
Local
Municipality
Mangaung Local
Municipality
George Mohlakoane
T: 051 405 8675
1 week
Gamagara
Development
Forum
NJ Multi Spillage
Control and
Contractors CC
NJ Mathe
T: 076 777 0604
Heyns van
Rooyen Consulting
Engineers
Heyns van Rooyen
T: 053 8311609
0190
Deben Bakery
Electrical installation
Oct-11
R0.4 mil
0244
Kathu erf 5906
Electrical supply to erf 5906
May-12
R0.4 mil
6 months
Khumani
Housing
Development
0117
St Patricks Hospital
Bizana
Kwazulu - Natal
Electrical installation
May-09
R0.36 mil
4 Months
Ruwacon
Ruwacon
Daniel Plekker
T: 082 902 0979
0094
Estoire mini sub
Bloemfontein
Free State
Installation on new minisubs
Jan-09
R0.35 mil
2 Months
Sanyati
Sanyati
Louw De Bruin
T: 083 262 1230
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 17
www.rame.co.za
Completed Projects Data
(Continued)
Project
Description
Project
Start
Date
Project
Cost
Completion
Time
Client
Installation of traffic lights
Oct-12
R0.3 mil
2 Months
Stefcor
Construction cc
Stefan Kruger
T: 083 457 6749
R0.3 mil
4 months
Department of
Public Works
Richard Nzuza &
Associates
Andisiwe
Mngcandubana
T: 043 7420041
Apr-11
R0.3 mil
8 Months
University
of the
Free State
CKE Engineers
Ben Joubert
T: 082 565 0868
Replacement of Medical B 1600
kVA transformer from South block
substation
Feb-12
R0.3 mil
University of
the Free State
CKE Engineers
Ben Joubert
T:051 444 4728
0078
Robben Island
Admin Block
Cape Town
Western Cape
Electrical repairs and renovations
Oct-07
R0.3 mil
24 Months
Meirelles
Lawson Burger
Argitekte
De Villiers & Moore
Mr J Dippenaar
T: 021 976 3087
0097
Huis Gavin Davids
Bloemfontein
Free State
New Residential
Sep-08
R0.29 mil
8 Months
Gavin Davids
Gavin Davids
T: 051 403 0400
T: 082 885 3987
0092
Ruthven Huis
Bloemfontein
Free State
New Residential
Aug-08
R0.27 mil
6 Months
Ruwacon
Ruwacon
Peter Ruthven
T: 051 403 0400
T: 082 205 5843
0095
ANC Woman’s
League
Bloemfontein
Free State
Install temporary power for ANC
conference
Jun-08
R0.25 mil
3 Days
N/A
0205
Breda School
Electrical Installation
Dec-12
R0.2 mil
3 months
Department of
Education
Aurecon
Brayn Devenish
T: 051 447 8911
0025
OFS Fire Office
complex Bloemfontein
Free State
New office building
Oct-07
R0.2 mil
3 Months
Centa OFS Fire
Dirk van Heerden
Engineers
Dirk van Heerden
T: 051 448 0185
T: 082 446 2981
0206
Friesland School
Electrical Installation
Dec-12
R0.2 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0209
Huntersvlei School
Electrical Installation
Dec-12
R0.2 mil
6 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0212
Lincoinshire School
Electrical Installation
Dec-12
R0.2 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
Site
Code
Project
Title
0259
Verkeerslig Checkers
Hyper
Bloemfontein
Free State
0240
Zwelitsha Document
Centre
Electrical Installation
Apr-12
0172
Sport Fields
Lighting Phase 2 - Rugby
reticulation
Free State
Supply and install LV cable
reticulation
0226
UFS Transformer
Replacement
Engineer
N/A
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 18
www.rame.co.za
Completed Projects Data
(Continued)
Project
Start
Date
Project
Cost
Completion
Time
Client
Electrical Installation
Dec-12
R0.2 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
Metsi - A - Hare
School
Electrical Installation
Dec-12
R0.2 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0216
Motheu School
Electrical Installation
Dec-12
R0.2 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0217
Niekerskuil School
Electrical Installation
Dec-12
R0.2 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0219
Saaiplaas School
Electrical Installation
Dec-12
R0.2 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0221
Seka School
Electrical Installation
Dec-12
R0.2 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0222
Sommerso School
Electrical Installation
Dec-12
R0.2 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0223
Witkoppies School
Electrical Installation
Dec-12
R0.2 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0027
House Ruthven Bloemfontein
Free State
New house
Sep-07
R0.2 mil
8 Months
Mimos 6 Trust
Ruwacon
Peter Ruthven
T: 051 403 0400
T: 082 205 5843
0121
Robben Island Single
Quarter
Cape
Upgrade, repair and renovate of all
electrical equipment
Domestic and industrial
Nov-09
R0.2 mil
2 Months
Department of
Public Works
Ned Group
Danie Fourie
T: 021 913 1813
0065
Idutywa Magistrate
Court
Eastern Cape
Electrical and mechanical renovations
Jul-07
R0.2 mil
24 Months
Department of
Public Works
KV3
Mr W Snyman
T: 042 721 0055
0145
CNS Call Centre
Bloemfontein
Free State
Installation of 171 dedicated plug
points
Jun-10
R0.2 mil
2 Weeks
CNS Call Centre
IJW Matthys
T: 083 633 8196
0140
Country Bird Power
Factor Correction
Bloemfontein
Free State
Installation of 4x power factor
correction units, design, supply,
installation and commissioning
May-10
R0.1 mil
1 Month
Supreme
Poultry
Lucas Gerber
T: 051 448 6803
0073
Leon Botha
Bloemfontein
Free State
Electrical installation of warehouse
Sep-07
R0.1 mil
3 Months
Leon Botha
0069
Huis Fichardt
Bloemfontein
Free State
Electrical installation of residential
house
Aug-07
R0.1 mil
6 Months
C Mac
Construction
Site
Code
Project
Title
0214
McGrarthspark
School
0215
Project
Description
Engineer
Mr C van Heerden
T: 083 400 0378
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 19
www.rame.co.za
Completed Projects Data
Site
Code
Project
Title
(Continued)
Project
Description
Project
Start
Date
Project
Cost
Completion
Time
Client
Engineer
0204
Banklaagte School
Electrical Installation
Dec-12
R0.1 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0207
Hamsverwacht
School
Electrical Installation
Dec-12
R0.1 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0210
Kgostsofalo School
Electrical Installation
Dec-12
R0.1 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0211
Lebonong School
Electrical Installation
Dec-12
R0.1 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0213
Makawansbank
School
Electrical Installation
Dec-12
R0.1 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0218
Nokanapedi School
Electrical Installation
Dec-12
R0.1 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0062
Cambridge Police
Station
Eastern Cape
Electrical upgrading of offices and
prison cells
Jul-07
R0.1 mil
24 Months
Department of
Public Works
Mr FJ van Zyl
T: 041 408 2041
0064
Grahams Town
South African Police
Services Leicester
street
Eastern Cape
Electrical upgrading of fourteen flats
Jul-07
R0.1 mil
5 Months
Department of
Public Works
Mr Kobus Nel
T: 041 408 2123
0220
Sardinia School
Electrical Installation
Dec-12
R0.1 mil
3 months
Department of
Education
Aurecon
Bryan Devenish
T: 051 447 8911
0243
132kV
Interconnector
Croydon and cable
88kV consol glass
installation
1) Installation of 132kV, 1800mm
sq AL, 270m,cable connection
between 132kV busbars and GIS
2) Installation of 132kV, 1000mm
sq AL, 600m to Concol Glass,
Olifantsfontein
May-12
R0.2 mil R.54
mil
CBI- African
Cables
Willem v.d Vyver
T: 083 629
7088
Frank van Heerden
Eskom Bfn
T:051 435
6000
or
CBI African Cables
Willem v.d Vyver
T: 082 770 0225
0225
UFS 11kV
Maintenance Plan
Maintenance of 11kV substations
Feb-12
R0.1 mil
University of
the Free State
CKE Engineers
Ben Joubert
T: 051 444 4728
0198
Eskom Maintenance
MV/LV Maintenance for Eskom’s
north West Region - Cable
maintenance, substation
maintenance, etc.
Nov-11
Various
amounts
36 Months
Eskom - RAM
Subcontracting
for
CBI - African
cables
CBI - African cables
Willem v.d. Vyver
T: 083 629 7088
0178
Barkley East
Eastern Cape
Repair 40m floodlight
Jun-11
R0.1 mil
1 Month
Senqu
Municipality
T: 051 603
0019
Senqu Municipality
Rean van Heerden
T: 082 789 0775
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 20
www.rame.co.za
Completed Projects Data
Site
Code
Project
Title
(Continued)
Project
Description
Project
Start
Date
Project
Cost
Completion
Time
Client
Engineer
0051
HDL - Dan Pienaar
Drive 7
Bloemfontein
Free State
Electrical installation - standby
generator and standby power
May-07
R0.1 mil
2 Weeks
HDL Jewellers
Harry Loubscher
T: 082 774 4985
0039
Library Mansions
Bloemfontein
Free State
Refurbishment of block of flats
Feb-07
R0.1 mil
4 Months
Bower and
Kemp
Investments
Mr Kemp
T: 082 561 7982
0049
Jan Kempdorp
development
Free State
Network Design
Low voltage reticulation
Certificate of compliance test
Jan-07
R0.1 mil
1 Week
Definite Pitch
Developers
Piet Beukes
T: 082 881 2911
0038
Leshoto PF
Maseru
Lesotho
Power correction factor installation
Connect to electrical system and
commission
Jan-07
R0.1 mil
5 Months
Lesotho Elec.
Corporation
Electrica assembles
Mr Arnold
T: 083 658 2981
0032
Maseru Port of
Entry
Lesotho
Emergency repair work
Dec-06
R0.3 mil
4 Days
Ruwacon
Ruwacon
Peter Ruthven
T: 051 403 0400
T: 082 205 5843
0036
House West
Bloemfontein
Free State
New home for Dr West
Building electrical
Nov-06
R0.4 mil
4 Months
Dr West
Dr West
T: 051 444 5820
0024
Parys Reticulation
Free State
Electrical distribution on street
lighting
Traffic signal lighting
Nov-06
R0.1 mil
2 Months
Meyker
Construction
0034
Bloemfontein
Student house
Free State
Rewire of student accommodation
Nov-06
R0.1 mil
3 Days
Mr Human
Mr Human
T: 082 922 4838
0026
Fynbos town house
Swellendam
Western Cape
Reticulation High and Low Voltage
Electrical metering
Mini Subs
Electrical installation - town houses
Oct-06
R0.7 mil
6 Months
Ruwacon
Johan Bester
Engineers
Johan Bester
Cel: 082 414 1867
0031
Henk Jacobs Bloemfontein
Free State
New Electrical installation
Oct-06
R0.5 mil
N/A
Mr Jacobs
N/A
0037
Ruwacon Offices
Bloemfontein
Free State
New offices
Building electrical
Air Conditioning
Sep-06
R0.4 mil
24 Months
Ruwacon
Ruwacon
Peter Ruthven
T: 051 403 0400
T: 082 205 5843
0030
Mcome Prison
Mpumulanga
Earthing of roof structures
Sep-06
R0.1 mil
N/A
DCS
0020
George Labour
Offices
Eastern Cape
Building electrical
Security lighting
Air Conditioning
Electrical maintenance
Jun-06
R0.5 mil
36 Months
Department of
Labour
KV3 Engineers
0016
Noupoort
Magistrates court
Northern Cape
Building electrical
Security lighting
Air Conditioning
Electrical maintenance
36 Months
Department of
Justice
Virtual Buro
Mr Malan
T: 012 452 0450
T: 082 875 5763
Mar-06
R0.6 mil
Meyker Construction
Mr De Bruin
T: 083 262 1230
Kwezi V3 Engineers
Mr F Strydom
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 21
www.rame.co.za
Completed Projects Data
Site
Code
Project
Title
(Continued)
Project
Description
Project
Start
Date
Project
Cost
Completion
Time
Client
Virtual Buro
Mr Malan
T: 012 452 0450
T: 082 875 5763
Engineer
Diepkloof Prison
RAMP Project
Gauteng
Security lighting
11kV substation (transformer and
switchgear) Maintenance transformer
oil testing and purification of oil test
protection at 11kV supply point.
11kV cable fault location
Repair and pressure teste
Sep-05
R0.8 mil
36 Months
Department of
Public Works
0007
Ficksburg Port of
Entry
Free State
Building Electrical
Security lighting
Air Conditioning
Generators
Electrical maintenance
Civil maintenance
Jun-05
R0.3 mil
12 Months
Department of
Public Works
Bigen Africa
Mr. Nel
T: 082 449 8287
0006
Elliot Magistrates
Court
Eastern Cape
Building Electrical
Security lighting
Air Conditioning
Electrical maintenance
Civil maintenance
Mar-05
R0.5 mil
36 Months
Department of
Justice
KV3 Engineers
Mr. Viljoen
T: 043 721 0055
0118
Free State Stadium
Overlay for FIFA
2010 World cup
soccer
Bloemfontein
Free State
Install 11kV cable network for LOC
2010-03-26
Install different LV cable and points
for LOC 2010
R0.8 mil
1 Month
Mangaung
Local
Municipality
Dihlase
Sarel Esterhuizen
T: 051 447 1636
T: 083 262 1699
Parmalat SA
Craig Sanders
T: 083 386 6072
Nico Jackson
T: 083 400 3679
0005
1 & 2) Parmalat
Transformer
0248
3) Parmalat Maputo
Maputo
Mosambique
1) Transformer Maintenance Parmalat Midrand
2) Transformer 630kVA replacement
in Maputo Mozambique
3) MV LV Upgrade
1&2)
Sept 2012
3)
April 2013
1&2) R0.2 mil
3) R2.6 mil
4 Months
0263
Raceway Park
Development
Bloemfontein
Free State
Construction of electrical services for
development ext 227
Mar-13
R6.3 mil
5 Months
0364
Raceway Park Ext 226 : Phase 2
Construction of the Electrical
Services
Jan-15
R 6.1 mil
12 Weeks
Space
Securitisation
Aurecon Consulting
Engineers
Koos Kritzinger
2004
Port Elizabeth
international Airport
Replace and upgrade of low voltage
panels in Main Substation and
Terminal Building substation
Apr-15
R 5.89 mil
7 months
ACSA Port Elizabeth
Karina Stroebel
T: 041-5077348
0365
King Shaka Airport
Generators: Standby
Oct ‘15
R5.58 mil
5 Months
ACSA
0340
Tuscan Place
Townhouse
Bloemfontein
Installation of Time of use Meters
Jun-14
R 0.04 mil
2 days
K Dolphin
0281
Bethulie Waste Water
Treatment Works
Electrical installations
R .8 mil
RWC
Aurecon Constulting Engineers
Koos Kritzinger
ACSA
V Moodley
T: 032 436 6000
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 22
www.rame.co.za
Completed Projects Data
Site
Code
Project
Title
(Continued)
Project
Description
Project
Start
Date
Project
Cost
Completion
Time
Client
Engineer
Engineer
Senque Mun
SKC Engineers
Maletswai Peter Brooks
T: 051 634 1847
0344
Sterkspruit Sport
Stadion
Installation of highmast lights at
Sportfield
Jul-14
R 2.5 mil
4 Months
0363
Volvo New Workshop
Bloemfontein
Supply and Install Electrical
Installation
Sep-14
R 2.49 mil
6 months
Boys & Willie Otto Construction cc
T: 051 433 2949
0328
Fort Glamorgan
Prison
Generator installations
Apr-14
R 1.62 mil
6 months
Dept of Public Works G Appels
T: 041 4082150
0380
Acacia Park :
Kimberley
Complete Construction of Electrical
Services for Phase 1 : 5 Residential
Erven for Trans 50 Group : Acacia
Park
0342
Tredenham Valley
Phase 2
Electrical Connection
Jun-14
R 0.4 mil
1 year
0330
Mdantsane Prison
Generator Installation
Apr-14
R .3 mil
6 months
Dept of Public Works
G Appels
T: 041 4082150
0345
Mangaung Small
Power
Electrical installation at Northern
Waste Water Treatment works
Jul-14
R 0.27 mil
3 months
Stefanutti Stocks
0313
Kimberley Homevale
Waste Water
Treatment Works
Electrical installation
Apr-14
R .23 mil
3 months
0263
Bloemfontein
Race Course Bulk
Streetlight
Bulk Streetlight installation
Aug-14
R 0.15 mil
1 month
Space
Securitisation
(PTY) Ltd
Aurecon Consulting
Engineers
Koos Kritzinger
T: 082 770 0225
0370
Tokkie Park: CUT
Upgrading of the Existing Sport Field
Lighting Installation
Nov-14
R 5.2 mil
5 Months
Central
University
of FS
Central University
of FS
Mr. W. Britz
T: 051 507 3664
Jan-15
R1.06 mil
6 months
Acacia Park
Retirement
Village
Dihlase Consulting
Engineers
Hendrik Jonck
T: 053 861 3722
Aurecon Consulting Engineers
Koos Kritzinger
T: 082 770 0225
electrical@rame.co.za
1 Rissie Street | Quaggafontein | Bloemfontein
PO Box 29741 | Danhof 9310
Bloemfontein: [ T ] +27 (0) 51 523 3720 [ F ] +27 (0) 51 523 3804
Johannesburg: [ T ] +27 (0) 10 003 0341
Port Elizabeth: [ T ] +27 (0) 41 384 3704
Page 23
www.rame.co.za