INDEX 1. HISTORY OF THE PROJECT a. About C-DAC b. Objectives c. Building Demand Analysis d. Land Acquisition e. Salient Features of Location of Land f. Building Planning g. Configuration of Campus h. Floor Space Usage Statement i. Initial Sanctioned Outlay j. Initial Fund Arrangement and Approval k. Initial Tendering and Award of work l. Back ground Analysis for Revision of Estimate 2. PREPARATION FOR REVISED ESTIMATE a. Appointment of Agency b. Site Inspection and Status Evaluations c. Identification of Balance Works d. Illustrations 3. REVISED DETAILED ESTIMATE a. Civil b. Electrical c. Fire d. HVAC e. Lift f. Other Services g. Recurring expenditures 4. REASONABILITY STATEMENT 5. SITE PHOTOGRAPHS 1 PREAMBLE The Center for Development of Advance Computing, Pune is setting up a campus under the name & style of Innovation Park. The campus is located at S.No.34B/1, CTS 788(P), Pashan, Pune. The objectives of setting up of this campus are to have its own premises befitting an organization of a stature of C-DAC. SFC, DeitY had sanctioned the project in the year 2008, funds were released for construction. In the open tender process, the agency for consolidated works was selected and work commenced. During the tender process and changes in configurations, it was revealed that, the initial estimate had been excessively under stated. The scope for the project execution was suitably changed to complete the structure of the building. The entire scenario has been presented before the 12th meeting of coordination committee and the committee has advised to revise the proposal and submit to the DeitY for sanctions. Revised proposals were prepared by C-DAC and submitted to Department of Information Technology in March 2011. In the month of Sept. 2011, since the additional fund requirements were in excess of 20% of earlier approved project cost, DeitY asked C-DAC to re-submit the revised proposal with a third party government agency vetting,. The 13th coordination committee meeting held on 15-11-2011 was advised to engage services of government agency to work out the realistic cost estimate to complete the building to suit the occupation. M/s. Hindustan Steel Works Construction Limited (HSCL) a Government of India undertaking has been appointed for preparation of Estimate for the balance work to occupy the building excluding the HPC facility related works on 12.09.2012. HSCL is established in 1964 as a construction organization under the Ministry of Steel. A pioneering Company in Infrastructure Projects and an ISO 9001-2008 company, having turnover of more than Rs.1200 Crores. HSCL studied the project, and the Detailed Project Report and re- estimate is being submitted here with for the necessary approval of the competent authority. 1 2 ABOUT - C-DAC (Center for Development of Advance Computing) Centre for Development of Advanced Computing (C-DAC) is the premier R&D organization of the Department of Electronics and Information Technology, Ministry of Communications & Information Technology (MCIT) for carrying out R&D in IT, Electronics and associated areas. Different areas of C-DAC, had originated at different times, many of which came out as a result of identification of opportunities. The setting up of C-DAC in 1988 itself was to build Supercomputers in context of denial of import of Supercomputers by USA. Since then, C-DAC has been undertaking building of multiple generations of Supercomputer starting from PARAM with 1 GF in 1988. Mankind has grown from Stone Age to space age! In this continuous exploration of opportunities for growth and safety, Super Computers have played a significant role in the last 50 Years. It would have been impossible to solve the most challenging and complex scientific and Engineering problems without supercomputing. Super computers also have strategic importance to play in National Security, Defense, Research and Development in many areas such as Molecular life science, Energy and environment, weapons, engineering industries such as Automobile, Aerospace, Nanotechnology and new material designs. Keeping in view the growth requirements in technology government of India set up “Center for Development of Advance Computing (C-DAC)” in 1988. State of the art supercomputing facility of the nation consists of following facilities: R&D Laboratories High performance Computing Grid Computing Lab Language Technology Lab Hardware Technology and Development Centre Applied Artificial Intelligence (AAI) Multi Media Group E-Governance Networking and Internet Security Scientific and Engineering Computing Geo informatics Solutions Development Medical informatics etc 3 OBJECTIVES From the year 1988 C-DAC had started functioning at Pune from hired building as it’s Head Office. Various activities of C-DAC Pune are being carried out from different hired buildings. 1. Pune University Campus, Pune C-DAC Head office National PARAM Super Computing Facility Technical Groups Applied Artificial Intelligence Geometric Solutions Development Group Advance Computer Training School Technical Group. 2. NSG IT Park, Aund, Pune 3. Agriculture College Campus, Pune HPC Business Group 4. MHADA Building, Gokhale Nagar, Pune Stores The objectives of setting of this campus are as follows: To have own premises befitting an organization of a stature of C-DAC. To be able to operate out of a common facility. To optimize the synergy of close working of various units. To save on rent & to honor the vacation notices served by owners of current rented premises. To set up & operate a Facility comprising HPC facility. BUILDING DEMAND ANALYSIS Various activities of C-DAC, Pune are being carried out from different hired buildings resulting in various operational issues such as: Restricted growth due to inadequate floor space Problems of proper technical interaction Duplication of activities and equipments Annual rent and lease of renewal problems etc A permanent own building is the only alternative solution 4 LAND ACQUISITION The Governing council and the steering committee of C-DAC in its annual meeting held on 23.10.1998 passed resolution that, C-DAC should acquire its own land and construct its own building , subsequently:In the year 2000 a land admeasuring 1.5 acres was acquired from the Government of Maharashtra. SALIENT FEATURES OF LOCATION OF LAND The land which was selected and allotted is in the vicinity of several national academic and research institutions such as: National Chemical Laboratory (NCL) Indian Institute of Topological Meteorology (IITM) National Informatics Center (NIC) National Science Education and Research Center (NSERC) Pune University Indian Institute of science and Engineering Research. This shall facilitate to have easy interactions with like minded scientists and Engineers to the right R&D out puts which may broadly benefit R&D in India. BUILDING PLANNING The requirement of proper building and infrastructure for C-DAC, Pune had been proposed in the C-DAC’s Eleventh Plan (11th) proposal to Department of Information Technology. Subsequently parliamentary standing committee on information technology recommended the proposal in June-2007. Governing Council meeting in 2007 approved the proposal of infrastructure development. Administrative approval from department of information technology had been accorded on 18.02.2008. M/s. Kirloskar Consultants Limited has been appointed as an Architect / Consultants for building, Infrastructure Planning and Project Management. 5 CONFIGURATION OF CAMPUS The campus plot size is 6,012.17 Sq Mtr. The net built up area of building, comprises usable office area of 15,845.45 SqM and parking / utility area of 11,003.30 SqM. The entry to the building is on upper ground floor. The access from upper ground to basement & lower ground is by way of ramps & podium. Building infrastructure planned to have following facilities:Air conditioning Chiller Plants (Double height) Substation (Double height) Diesel Generators (Double height) Fire Tanks, Fire Pumps Rain Harvesting system Water tanks and Drain Pump Station Parking Area 1. BASEMENT 2. STILT FLOOR Parking Area, Drivers Changing Room & Toilets Reception Electrical /BMS Room Drivers Changing Room Optical cables & Server Rooms Bank Store Room AHU Room Advanced Computer Training School (ACTS) Parking Area NOC Server Room Heat Exchanger Room for NOC Panel Room UPS Room for Building Lighting etc Building battery Room SANG AHU Room Administration Room Record Room Electrical Room FM-200 Protection Room Panel Room for PARAM HPC, UPS Room HPC, Battery Room HPC, Heat Exchanger Room HPC, Cabinet Room 3. GROUND FLOOR 4. FIRST FLOOR 6 5. SECOND FLOOR 6. THIRD FLOOR 7. FOURTH FLOOR 8. FIFTH FLOOR 9. SIXTH FLOOR Viewers Lobby Toilet Block Passages Etc Server Room Xerox and Pantry Record Room AHU Room Electrical Panel Room VIP Toilet s Toilet Block Laboratory Block Corporate office Server Room Xerox and Pantry Record Room AHU Room Electrical Panel Room Laboratory Block Office Area (2246 Sq. Feet) Toilet Block Server Room Xerox and Pantry Record Room AHU Room Electrical Panel Room Laboratory Block Office Area (2122 Sq. Feet) Toilet Block, Passages etc Server Room Xerox and Pantry Record Room AHU Room Electrical Panel Room Office Area (2477 Sq. Feet) Toilet Block, Passages etc Kitchen Pantry Room Cafeteria 7 FLOOR SPACE USAGE STATEMENT Basement Stilt Floor Ground Floor First Floor Second Floor Third Floor Fourth Floor Fifth Floor Sixth Floor Total Functional Area Total Parking Area Total Area Air conditioning Chiller Plants, Diesel Generators & Substation, Parking Area 4 Wheeler Parking Area Reception, Security, Bank, Training School, 4 Wheeler Parking High Performance Computing Facility. Corporate Office. Technical Workstations, AAI & GIST HBCC, HDC-1, HPCG,MIG,NMRC, Geo-M Library, HPC-2, eGov., BDG, Technical work stations Canteen for 400 persons 1680000 Sq. Feet Approx. 95600 Sq. Feet Approx. 263000 Sq. Feet Approx. INITIAL SANCTIONED OUTLAY 1. Building Civil Work 26.11 Crores 2. 3. 4. 5. 6. Interior Works HVAC Lifts External Services Recurring expenses TOTAL 14.59 Crores 7.00 Crores 1.25 Crores 0.55 Crores 0.3 Crores 49.80 Crores 8 INITIAL FUND ARRANGEMENTS AND APPROVAL The standing finance committee had sanctioned the project on 18.02.2008 for execution of the project with following financial arrangements 1. C-DAC Contribution to Project 19.92 Crores 2. Department of Information Technology Grant 29.88 Crores Total 49.80 Crores INITIAL TENDERING AND AWARD OF WORK An open integrated tender was processed after technical and financial approval for the execution of the work. In the tender, the interior works were eliminated since the planned outlay of 49.8 Crores was insufficient for the execution. Considering the urgency and to avoid delay in the execution process it was decided to call the tender excluding the interior works. Accordingly tender was processed and opened on 04th August 2008. Status of Financial Positions after Opening the Tender and Revision of price SL Item Initial Estimate Tendered Cost Rev. Amount Order value de-scoped Qty 1. Civil Work 26.11 Crores 363796400.63 336642637.29 294360848.90 2. Interior Works 14.59 Crores Excluded Scope Excluded Scope Excluded Scope 3. HVAC 7.00 Crores 82381182.00 68607033.40 64661919.28 4. Lifts 1.25 Crores 17079576.00 15804756.45 15804756.45 5. Fire Protection Part of civil work 34961081.00 32351585.91 30168969.82 6. Electrical Works Part of civil work 119077358.00 110189424.00 86855770.56 TOTAL 489500000.00 617295597.63 563595437.05 491852265.01 Note: As the total sanctioned amount for the project execution was 49.80 Crores. The scope of work was revised in consideration of the progress philosophy of the project and allowed to start the project work. 9 M/s. Nagarjuna Construction Company Limited, the lowest bidder was awarded the contract to execute the revised /reduced scope, item quantity of work and commenced work on 12th May 2009. Duration of the project execution awarded was 24 months. BACKGROUND ANALYSIS FOR REVISION OF ESTIMATE ORIGINAL CONFIGURATION OF PROJECT The project cost put to work was based on the fact that the campus envisaged a HPC system set up of 40 Tera flops requiring about 1 MVA of power. All components of works such as civil works, electrical system, HVAC System were planned on this assumption. Accordingly the project was conceptualized and a tender notice was issued on 10.07.2008 for the integrated works of civil construction, electrical power system, HVAC system & fire protection system after following the prescribed procedures. The bids were received on 10.09.2008. The prequalification evaluation of 8 bidders was undertaken. During this process 3 bidders were technically disqualified & balance 5 bidders were qualified. After the evaluation of technical bids, the price bids were opened on 23.10.2008 with the price of Rs. 617295598.00 M/s. Nagarjuna Construction Company was the lowest bidder. The package wise price break up of tendered offer was as below:ITEM PRICE BREAK UP Civil Construction 36,37,96,401.00 Electrical Power System 11,90,77,358.00 HVAC System 8,23,81,182.00 Fire Protection System 3,49,61,081.00 Elevator System 1,70,79,576.00 Total 61,72,95,598.00 In the meantime, in order to ensure that, the project cost remains within the approved budget, it was decided to rearrange the schedule of work to be executed to limit the approved budget of Rs.49.8 Crores. The price bid was evaluated and after considering the various effects of Exemption available to CDAC on account of Octroi. 10 Exemption available to CDAC on account of Service Tax Reduction in the express feeder runs from 2 to 1 due to availability of standby power DETAILS OF REDUCED SCOPE ITEM WISE Package Original Tendered Amount Ordered Amount after reduction of scope Civil construction 36,37,96,401 29,43,60,849 Electrical power system 11,90,77,358 8,68,55,771 HVAC system 8,23,81,182 6,46,61,919 Fire protection system 3,49,61,081 3,01,68,970 Elevator system 1,70,79,576 1,58,04,756 61,72,95,598 49,18,52,265 Total CHANGE IN THE SYSTEM CONFIGURATION (Over all Requirement with HPC) In the mean time 40 TF HPC systems has been commissioned in the university C-DAC campus, which was planned initially at Innovation Park. Accordingly, a higher capacity HPC facility has also been planned for the innovation park which resulted in following major additional works. The required basic infrastructure has been included in the execution of civil work. However due to constraints of funds, the other items could not be planned. ELECTRICAL: The addition of 22,000 Kgs for 4 x 800 KVA UPS batteries for HPC Facility. The addition of 5,000 Kgs for 2x 400 KVA UPS battery for building The increase in power demand from 3000 KVA to 5,000 KVA Increase in DG set capacity from 3000 KW to 6400 KW Increase in Transformer capacity from 2x1500 KVA to 2x2000 KVA + 1x2750 KVA Incidental change in size of express feeder from 85 Sqmm to 300 Sqmm Incidental changes in 22 KV switchgear Incidental changes on account of increased load in all LV distribution switchgear Incidental changes on account of increased load in power & control cabling Additional work of voice & data network & raceway 11 HVAC: Increase in chiller capacity from 950TR to 1780 TR Increase in associated works, pumping, piping etc. Addition of High density precision air conditioning system for HPC. Addition of High density precision air conditioning system for data center Duct less ventilation system in basement & lower ground in parking areas Pressurization of stair cases Supply air fans / ducting / exhaust air fans / acoustic treatment for open execution 4x1600 kW DG sets CIVIL:Due to the changes in requirements the civil structure has been redesigned to accommodate the facility, details are as follows: The additional weight of 22,000 Kgs for 4x 800 KVA UPS batteries for HPC Facility. The additional weight of 5,000 Kgs for 2x 600 KVA UPS battery for building Increase in thickness from 280 mm to 350 mm of first floor slab due to additional weight of UPS batteries. Increase in thickness of terrace floor slab 280 mm to 350 mm due to additional utility load Strengthening of column & foundations also was necessitated due to additional weight of UPS batteries and HPC racks. FIRE PROTECTION SYSTEM: Re-inclusion of FM 200 system for gas flooding protection of data center & floor server rooms. ADDITION AND ALTERATIONS DUE TO CHANGES OF BASIC PARAMETERS During execution of the project, following short comings, addition and alterations were necessitated to comply to proceed with the project. 1. SOIL STRATA: The soil survey was conducted through a third party agency. However the soil strata was found softer than the estimated, which has resulted in additional excavation and filling the same with plum concrete to bring the preplanned level of foundation. 12 2. HIGH PERFORMANCE COMPUTING FACILITY: The building was initially planned for 40F for next generation high performance computing facility. While changing the construction to suit the next generation HPC facility following major changes were done. Higher thickness slabs were designed and constructed to hold battery Banks and HPC Hardware Staging height was increased as per requirements 3. PAYMENT OF OCTROI:The centre had Octroi exemption allotted by Pune Municipal Corporation. However till the time the project come up, PMC withdrew the exemption which has resulted in additional financial burden on project (Approx: 1.3 Crores) 4. PAYMENT OF STATUTORY FEES:Statutory payments for construction clearance to Municipal Corporation, MSEDCL (Electricity Board), Service Tax etc were not considered in the initial estimate. This has resulted in financial burden on the project. 5. PAYMENT OF DESIGN AND SUPERVISION CHARGES:The charges for consultancy and supervision of work were not included in the initial estimate which has resulted again financial burden on the project sanctioned amount. 6. COST ESCALATION: Already three years has been passed, since the commencement of project, as per the agreement terms the cost escalation was also paid to the contractor. FUNDS SANCTION & ALLOCATION The financial sanction was accorded for an amount of Rs. 49,80,00,000 to accommodate the final reduced / rescheduled scope value accepted by M/s. NCC Ltd. for execution of work. The implication of certain provisions, as mentioned below, applicable to the contract were above the contract value. Price adjustment as per the tender provisions Additional work if any to suit the site conditions In the meantime C-DAC had incurred various prior expenses. Such as payments to Pune Municipal Corporation for construction permissions, Octroi, Service Tax, Consultancy and 13 Supervision Charges etc. This has now become known that, such expenses would also be adjusted against the sanctioned project cost. The final order value was now also required to be covered from the sanctioned funds. This has drastically reduced the funds available for execution of the work. The details of expenses made / to be made in addition to the planned are as under:ACCOUNTING HEADS AMOUNTS Consultancy Fees Rs.1.09 Crores Fees for PMC Development Charges Rs. 1.72 Crores Fees for Geotechnical Investigations Rs. 0.28 Crores Octroi Rs.1.3 Crores MSEDCL demand charges for load sanction Rs.1.15 Crores PMC ground rent for laying express feeder Rs.1.935 Crores Cost Escalation as per agreement to NCCL. Rs.1.89 Crores Service Tax Rs. 1.27 Crores. TOTAL APPROX. RS. 10.635 Crores PROPOSAL FOR COMPLETION OF WORK In order to examine the issues, CDAC has taken the expert help of Mr. S. Ramanujan, Advisor Infrastructure C-DAC. He visited the work site and also held meetings with building committee, consultants on 6th/7th October 2009 & 9th/10th March 2010. Having examined the necessity of the extra works executed, Mr. Ramanujan has opined as below: As per the PRSG meeting held on 16th January 2010 at Delhi, which was attended by him, it was informed that in the absence of additional funds the project may be undertaken with the available fund. Therefore it was decided that, the building work should so attempted as to Complete the civil works of the buildings Complete all services to such an extent that it becomes meaningfully available for occupation if possible. 14 PROPOSED SPLIT OF SCOPE OF WORK Under this arrangement it was proposed to split the total works in to three phases. The curtailed work out of total requirement to be executed under the contract currently in operation. The balance work of total requirement to be clubbed for execution with separate arrangement. Under this arrangement, the execution phases worked out as follows:CURRENT CONTRACT - PHASE – I CIVIL: Building superstructure for 6 floors Part structural glazing and external painting. ELEVATORS: 1 bank of 3 lifts as it is already delivered. FIRE: Firefighting hydrant and sprinkler system for all floors as the materials are delivered at site. HVAC SYSTEM: 2x370 TR WC chillers with pumps, 2 cooling towers, total piping with valves C.W pipe insulation etc. AHUs for 1st, 2nd and 3rd floors with panels etc. ELECTRICAL POWER SYSTEM: MSEDCL 22 KV power tapping in single run express feeder, Metering & cabling till the basement HT panel etc. 1x2000 KVA transformer with inter connection arrangements. PHASE – II: CIVIL: Basements grade slab, Vitrified flooring, Internal Painting, part Structural Glazing Tiles, Partitions, False Ceiling, Sewage Arrangements etc. ELEVATORS : 1 bank of 2 lifts ( Duplex Control System) HVAC SYSTEM: AHUs for 4th and 5th floors with panels, piping, wirings etc. 15 ELECTRICAL: Furniture, False flooring for server room, Storage system, Partitions. Etc. FIRE DETECTION, FIGHTING AND SUPPRESSION SYSTEM: 1x1600 KW DG set with associated cooling tower/piping/pumping, all light fittings, point wiring for light fitting, computers, raceways, data network, voice network etc.1x 600 KVA UPS for building services, 1x400 KVA UPS for servers etc. FURNITURE: 1 x 370 TR WC Chiller with Pumps, 1 x 500 TR Cooling Tower, Supply/Return Air Diffusers, Supply Air Grills, Ducting with Acoustic/Thermal Insulation etc. Fans and Ventilation System for fresh air arrangements. Air conditioning arrangements to Training school. Air conditioning arrangement to server room. Basement ventilation system and ventilation for DG set. Fire detection system, fire suppression system. Integration of fire fighting system detection and suppression systems with operating services. In addition, the systems for utility and services provided in the first phase, Testing commissioning and providing warranty for a period of one year for the performance. PHASE–III All works related to HPC Facility except major civil work and major changes in power demand related infrastructure. In view of above facts a revision of cost and financial approval has become essential to complete the job for the useful occupation of the building. The matter was presented before 12th and 13th co-ordination committee meeting and it was decided to engage a third party to work out a realistic cost estimate to make the building suitable for occupation and start centre functioning excluding the HPC Facility. Mean time the work has been stopped virtually at site and M/s NCC has asked to submit the bill for the works executed. M/s. Hindustan Steelworks Construction Limited a Government of India Undertaking company was approached by C-DAC. As they were willing to take up the job for reestimation, the job was entrusted to them including preparation of Detailed Project Report. 16 17 APPOINTMENT OF AGENCY The matter of revision of estimate was presented before 12th and 13th co-ordination committee meeting and it was decided to engage a third party to work out a realistic cost estimate to make the building suitable for occupation and start centre functioning excluding the HPC Facility. M/s. Hindustan Steelworks Construction Limited (HSCL) a Government of India Undertaking company was approached by C-DAC. As they were willing to take up the job for re-estimation, the job was entrusted to them including preparation of Detailed Project Report. HSCL is established in 1964 as a construction organization under the Ministry of Steel. A pioneer for Infrastructure Projects and an ISO 9001-2008 company having turnover of more than Rs.1200 Crores. SITE INSPECTION & STATUS EVALUATION Hindustan Steel works Construction Limited’s engineers and representatives visited the site and evaluated the status and observed the situation as follows: FACILITIES IN CAMPUS AND IT’S STATUS The innovation park has following equipped facilities: As per the current PMC rules which require captive parking, the parking places on the basement, lower ground & upper ground floor permit the parking of 117 four wheelers & 686 two wheelers. A water tank having capacity of 150000 Ltrs provided in the basement, caters to the general service water tank, fire water tank & make up water tank for the chillers etc. the provision of necessary pumps and pipe connections are pending. The elevators (machine room less type) in the first bank of 3 elevators with triplex control have been installed in the central section for quick movement of staff. The elevators will operate from the basement up to the terrace floor. 1 No. stair case of 2M width & 1 No. fire escape stair case of 1.5 M width also have been provided. The ramps of width of 4 Mtr have been provided to have access from upper ground level to lower ground & basement. A fire fighting system has been provided. The system modification is essential to integrate it with fire alarm system, false ceiling etc. The system testing commissioning etc. are still pending. A centralized air conditioning system with 2 x 370 TR water cooled chillers and its associated primary & secondary pumps placed in the basement. The cooling towers & condenser pumps have been located on the terrace floor. 18 The chilled water piping and provision of AHUs up to 3rd floor has been installed partially. ELECTRICAL & ALTERNATE POWER SYSTEM: The electrical substation arrangement is located in the basement with a dry type transformer HT and LT panels. Grid supply arrangement up to 5 MVA (on full development of load has been arranged.) Currently 1x2000 KVA transformer is installed for building services. The grid power supply tapping arrangement from 22 kV NCL Substation of MSEDCL Yard has been completed except the interconnecting cabling and metering arrangement. The wiring and light fittings of basement , lower ground floor , and upper ground floor on parking area are partially completed. RAIN WATER HARVESTING The rain water harvesting system comprise of water collected from the roof brought back to the reservoir in basement. DETAILS OF ITEM WISE WORK EXECUTED ARE AS FOLLOWS:1. Civil Structure of the building. 2. External glazing and painting. 3. Compound wall. 4. Under ground and over head water tanks. 5. All toilets. 6. Fire Fighting sprinkler and hydrant System Installation. 7. 3 out of 5 Lifts installation. 8. 1 x 2000 KVA Transformers Installation. 9. HT & LT Panels in substation side. 10. LT Distribution panels up to third floor. 11. 2 out of 3 x 370 TR Chillers Installation. 12. AHU up to 3rd Floor Installation along with Partial Ducting and Insulation. 13. Power taping arrangement at MSEB Yard. 14. Rain water harvesting arrangements. 15. Electrical earthing arrangements (Chemical Earthing Only). 16. Bus Trunking from LT Panel to distribution panel. 17. Laying of Panel to panel inter connecting cables partially. 18. Chilled water and condenser water piping partially. 19. Cooling tower Installation (2 out of 3) 20. Supply of fire Extinguishers 19 IDENTIFICATION OF BALANCE WORKS CIVIL WORKS – ALL FLOORS Internal and External Flooring works Internal painting works False ceiling Doors Fabrication and erection of steel structure for canteen on 6th floor Plumbing and drainage works False Flooring Sewage disposal arrangements INTERIOR WORKS OF ALL FLOORS Furniture Partitioning and Doors ELECTRICAL WORKS Cabling works from MSEB Yard to Metering and Switch Gear arrangement in meter Building (4.3 Km) room Internal electrification of all floors except parking Cabling of meter room to substation and stair case areas Compound lighting and Building Network cabling illumination Telephone Cabling Lights and Fitting arrangements Arrangement of 600 KVA UPS and integration for building services and 1 x 2000 KVA Diesel Generator Supply and ITC 400 KVA UPS for server. Integration, Testing and Commissioning of all Earthing extensions systems FIRE FIGHTING SYSTEM Rearrangements of Sprinklers as per cabins and False ceiling heights. Provision of Flexible hoses and Nozzles for fire fighting Approvals and Certifications from Fire Inspectors Testing and commissioning of wet riser and sprinkler system complete. Complete addressable type fire alarm system supply, Installation Testing and Commissioning Provision of sign boards and sign writings. HVAC SYSTEM Chilled Water Plant – High Side Provision of 1 x370 TR Chiller (SITC) Provision of 1 x 888 USGPM @ 25m head primary CW Pump Provision of 1x 500 TR Cooling Tower Provision of 1x 1500 USGPM @ 45 m head Cond.W Pump Provision of 1 x 888 USGPM @ 45m head Secondary CW Pump Integration of all above equipments with existing System 20 Low Side AIR HANDLING UNITS Hydronic Cassette Units Ducting and integration for Ground First, Second and Third Floors Completion of incomplete chilled pipe insulation Piping for Chilled water and Drainage System Modifications of Ducting to suit the site requirement Fresh air Arrangement to all floors 1. 4500 CFM 2. 13000 CFM 3. 6500 CFM 4. 9500 CFM 5. 8500 CFM 6. 10600 CFM 7. 16000 CFM 8. 7300 CFM 9. 6300 CFM 1 TR 1.5 TR 2 TR 3 TR 4 TR 1 No 4 Nos 1 Nos 2 Nos 1 No 1 No 1 No 1 No 1 No 6 Nos 7 Nos 5 Nos 4 Nos 3 Nos All Jobs of 4,5 and 6th Floors Integration, Testing and commissioning of entire low side job Complete VCDs, Diffusers, Grills etc for all floors Complete parking and basement ventilation system Complete system testing commissioning documentation and warranty LIFTS Provision of Machineroomless 15 passenger Lifts with duplex 2 Nos control Complete make: OTIS or equivalent. OTHER SERVICES BMS System Access Control System CCTV Audio Visual System Public Address System CERTIFICATIONS AND DOCUMENTATIONS Permissions, Certifications of all installations from respective certifying authorities 1. and handing over with all necessary documentations Sign writing, Tagging, Sign boards, instruction boards etc complete for all floors as 2. per usage of area and equipment’s utilization etc. A Revised detailed estimate for the balance work noted above has been prepared and forwarded here with for the approval of the competent authority. The detail follows:- 21 22 SITE INSPECTION The site has been inspected by a panel of expert Engineers to have the situational analysis, conducted meetings with the concerned authorities to have information about the details of situation. The team conducted the detailed study and measurements to arrive the balance work schedule. SCHEDULING THE WORKS The items were recalculated and re-scheduled to arrive a suitable schedule to complete the incomplete portion of work, re-calculated the requirements and scheduled the work which are necessary to occupy the building with adequate services excluding the requirements of HPC facility . BASIS OF RATES The rates are derived from the Delhi schedule of rates where ever possible (DSR-2007 and area index prepared by CPWD vide notification no. WZ-II/WS-19 (3) 2012/3393/97 dated 23.05.2012) and market rate quotations were called for the specialized services. COST ANALYSIS Cost analysis has been included considering the design, supervision charges, liasoning works and contingencies and arrived on final rates. ITEM WISE SCHEDULING AND COSTNG An item wise scheduling and costing has been done to have a transparent expenditure and being forwarded for the necessary approvals. 23 BROAD CONSIDERATIONS OF ESTIMATE (AT A GLANCE) 1. CIVIL WORK ESTIMATES The balance works consists of floorings, doors, internal paintings and finishing, structural shed on sixth floor for canteen, sewage line from building to PMC drain line etc. has been considered. False ceiling with gypsum and mineral boards as per design ( Armstrong make false ceiling considered) False flooring for server rooms. 2. ELECTRICAL 22KV cable laying to bring supply to the building along with associated works up to the transformer. Testing and commissioning of all floor panels. Provision of 1x 600 KVA UPS for building services and 1x 400 KVA UPS for servers with battery backup of 10 minute. Complete wiring for electrical, telephone and data communication. Provision of light fittings, fans, switches and plugs as per requirements. Compound and building illumination. 1x 2000KVA Diesel generator for emergency stand by supply arrangements along with associated works including extension of fume exhaust piping. Provision of underground diesel tanks having capacity of 20000 Ltrs. Provision of pumping system from basement water tank to over head water tanks including stand by arrangements. Provision of compound storm water pumping and associated works. Extension of earthing to complete areas and systems. Provision of lightning arrestors and earthing. Cabling and terminations for extending power to respective area DBs and equipments. Obtaining necessary certifications from respective authorities. The complete system already installed and new system testing, commissioning, handing over and warranty for a period of one year also considered along with necessary record documentation, training to the maintenance staff for day to day operation and up keeping 24 3. INTERIOR WORKS: The complete interior work are balance therefore the complete works of: Furniture such as tables, work station , chairs , special tables such as meeting room and bank etc, ( all Godrej furniture are considered) Partitions such as full rigid, half glazed, glass, glass doors etc. are considered. 4. FIRE FIGHTING AND DETECTION SYSTEM: The fire fighting system is installed however the same has to be re arrange in the sprinkler side according to the lay outs and false ceiling height where ever necessary. Items which are left over also have been considered. Fire alarm system has been scheduled for all the floors according to the utilization of area. An addressable type fire alarm system with all arrangements for detection , information and controlling the associated systems interlocking to operate / stop in case of fire has been considered The repeater panels are being considered for all the floors and security cabin for easy, efficient and off time monitoring. Fire suppression systems with FM-200 gas system with all associated arrangements are considered for UPS Room and Server Rooms (High hazard areas). The complete system already installed and new system testing, commissioning, handing over and warranty for a period of one year also considered along with necessary record documentation, training to the maintenance staff for day to day operation and up keeping. 5. HVAC SYSTEM Additional chiller of 370 TR and associated pump sets and cooling tower is considered for round the clock operation of building services 2 working +1 stand by arrangement. AHUs for the balance 4th, 5th and 6th floor along with associated works are considered. Cassette type indoor units are considered for ACTS. High density precision Hydronic package type AC units are considered for server rooms. 25 JET Fans are considered for the parking area ventilation. Supply air/ force ventilation system considered for DG sets. ( breathing and skin cooling) Fresh air intake arrangement with force ventilation considered as there is no clear access for fresh air intake. The complete system already installed and new system testing, commissioning, handing over and warranty for a period of one year also considered along with necessary record documentation, training to the maintenance staff for day to day operation and up keeping. 6. ELEVATOR : 2 x 13-15 Passenger machine room less Otis lifts from upper ground floor to sixth floor having speed of 1.5 m/seconds has been considered with duplex microprocessor based control system along with all associated works. 7. OTHER SERVICES: BMS, Access Control, CCTV, Public Address System and Audio Visual Systems for Conference Rooms etc have been planned. 26 SUMMARY OF ESTIMATES FOR THE BALANCE WORKS Table - 1 SL ITEM ESTIMATED COST 1 Balance Civil Works 78063388.00 2 Interior Works 3 Fire Fighting, Fire Detection And Fire Suppression Works 33616971.00 4 HVAC Works 73202363.00 5 Electrical Works 6 Lift Work 12651977.00 7 BMS, Audio Visual, CCTV, Access Control Etc. Services 19103662.00 8 Recurring Expenses During Project Period 45000000.00 9 Design and Supervision Charges 54836523.00 196076160.00 196580178.00 TOTAL COST OF WORK RUPEES 27 709131222.00 Table - 2 Details of items which was not considered in earlier scope, However necessary to complete for occupation. SL 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. ITEM AMOUNT (Rs. Crores) Additional plum concrete Compound wall on east side Sewage Treatment Electrical metering room Security Cabin UG Diesel Tank Rain Water Harvesting UPS for Services BMS & Services Recurring Electric Bill during Project Total 28 0.26 0.11 1.93 0.09 0.03 0.12 0.18 2.03 1.91 4.50 11.16 Table - 3 Details of extra item executed due to soil condition and HPC Loading SL ITEM Amount Spend DETAILS 1. Additional Excavation 0.70 Crores For Foundation 2. Concreting 1.07 Crores Foundation level to footings 3. Steel re-enforcement 3.90 Crores Due to change in design loads 4. Other miscellaneous items 0.17 Crores TOTAL RS. 5.84 Crores 29 DETAILS OF ITEMS EXECUTED TILL DATE SL Item Amount 1. Civil Works 30.83 2 Electrical 3.77 3 Fire Protection 1.82 4 HVAC 4.68 5 Lift 0.87 TOTAL 41.97 30 Details of statutory charges which were not considered in the initial estimate and payments made / pending SL ITEM AMOUNT REMARKS 1. Architectural & Consultancy Charges 1.90 Crores including supervision Already Paid 2. Pune Municipal Corporation for 1.72 Crores Development charges IT Premium etc Already Paid 3. Octroi Charges 1.30 Crores Party Paid to Contractor 4. MSEDCL 1.53 Crores Already Paid 5. Escalation charges 1.89 Crores Partly paid 6. Service Tax 1.27 Crores Anticipated Total 9.61 Crores 31 DETAILS OF EARLIER SANCTIONS, EXECUTED AND BALANCE WORK FOR THE USEFUL POSSESSION OF THE BUILDING SL 1 2 3 4 a b c d 5 6 7 8 9 10 Item Earlier Sanction 308283614.00 18287575.00 46872756.00 Estimated Cost for New Sanction 78063388.00 33616971.00 73202363.00 0.00 0.00 0.00 0.00 37691131.00 8714240.00 0.00 0.00 0.00 35606766.00 45054510.00 20350020.00 95568882.00 196580178.00 12651977.00 196076160.00 19103662.00 45000000.00 0.00 0.00 0.00 0.00 234271309.00 21366217.00 196076160.00 19103662.00 45000000.00 0.00 54836523.00 54836523.00 78200000.00 0.00 78200000.00 498049316.00 709131222.00 1207180538.00 Executed Amount 294360848.90 Civil works 30168969.82 Fire Protection Work HVAC Work 64661919.28 Electrical Work HT Works 0.00 DG Set 0.00 UPS 0.00 Electrical Installation 0.00 Electrical Total 86855770.56 Elevator Work 15804756.45 0.00 Interior Work 0.00 BMS & Other Services 0.00 Recurring Expenses Design & Supervision 0.00 Charges Statutory Fees (Octroi, MSEDCL, Consultancy, 0.00 PMC etc) TOTAL 491852265.01 32 Total Cost 386347002.00 51904546.00 120075119.00 Fund Flow & Time Frame for Execution of Balance work The balance work has been planned to complete with in a period of two years from the date of release of Fund. Following Table illustrates the details:- 1. Date of Release of Fund 01.11.2012 2. 3. SL 4. Amount (Crores) Finalization of PMC Date of Completion 31.01.2013 01.02.2013 Preparation of tender 28.02.2013 01.03.2012 Finalization of Tender 30.04.2012 01.05.2013 30 Civil Flooring Power Tapings Electrical Panels etc. 31.10.2013 Chiller DG Set UPS Electrical Wirings & Services Fire Alarm etc 31.03.2014 All other activities except commissioning of the systems 30.06.2014 Finishing, Commissioning and Training 30.10.2014 5. 01.11.2013 25 6. 01.04.2014 10 7. 01.07.2014 5.91 TOTAL 70.91 Planned Activity 24 Months 33 34 CIVIL BOQ C-DAC PUNE (BASED ON DSR/NON DSR RATES] SL DESCRIPTION OF ITEM UNIT QTY RATE AMOUNT Sq.Mtr 13800 1713.00 23639400.00 Sq.Mtr 200 1713.00 342600.00 Sq.Mtr 126 4,200.00 529200.00 Sq.Mtr 300 529 158700.00 Sq.Mtr 3650 573 2091450.00 CIVIL WORK 1 2 3 4 5 ALL FLOORS FOR FLOORING Providing and laying vitrified floor tiles in different sizes (thickness as specified by the manufacturer) with water absorptions less than 0.08% and confirming to IS: 15622 of approved make in all colors and shades, laid on 20 mm thick cement mortar 1:4 (1 cement: 4 coarse sand) including grouting the joints with white cement and matching pigments etc. complete. Size of Tile 60 x 60 cm ALL FLOORS FOR FLOORING Providing & fixing skirting of vitrified tile with cement including finishing balance plaster above skirting & curing etc. complete LIFT SIDE Providing & Fixing 18 TO 20MM THK Granite in flooring with bedding as per Drg./Design with finishing/polishing etc. complete ( Basic Rate of Granite18to 20 mm thick considered is Rs. 175/- per sq.ft.) FOR AHU ROOMS Providing and laying cement concrete 70 mm thick at all levels and lifts with 1:2:4 cement concrete laid to proper level and slope in alternate bays including compaction filling joints, marking lines to give appearance of tiles of 30 cm x 30 cm x or other size laid diagonally / square etc. finishing smooth (with extra cement) in any colour as directed and curing complete. FRONT SIDE LAWN Providing & laying Interlocking Paving Block in basement & for road(as per sample approved)of grade M 40 & 80mm thick on bedding of grit/sand to line & level including filling the joints with crushed sand & compacting the surface with compactor including re-fixing chamber covers of storm drainage etc. all complete. (Front Side Lawn] PARKING AREA 35 SL 6 7 8 9 10 11 12 DESCRIPTION OF ITEM Providing and laying polished chequered tiles at all levels of 20 to 25 mm thick and 30 cm x 30 cm size approved colour and pattern with white and coloured chips up to the maximum size of 6 mm / 12 mm for flooring and in required positions set in a bed of 1:4 cement mortar / including neat cement float, filling the joints with neat coloured cement slurry, curing, polishing and rubbing etc. complete. [For parking areas] [GROUND FLOOR RECEPTION AREA] Providing and laying Italian Marble flooring in required width in plain/ diamond or other designed pattern on a bed of 1:6 cement mortar including cement float, colour pigments, filling joints with neat cement slurry, curing, mirror polishing and cleaning etc. complete. (Basic Rate - Rs 300/-Sq.ft) Providing & fixing skirting of Italian Marble with cement, curing, polishing including finishing balance plaster above skirting etc. complete (BUILDING FRONT EXTERNAL SIDE] Providing and laying granite for cladding at all levels and lifts in required position with ready made adhesive mortar of approved quality on plaster of 1:2 cement mortar including joint filling with white/ coloured cement, pigments, slurry cleaning curing necessary screwing etc. complete as directed by Engineer-in-charge. (Basic Rate - Rs 175/-Sq.ft) Granite stone of any approved shade Providing and Laying granite for treads and risers of steps and staircase at all levels and lifts with rounded nosing for the treads on a bed of 1:4 cement mortar including cement float, filling joints with neat cement slurry, colour pigments, curing, polishing as per requirements and cleaning etc. complete. (Basic Rate - Rs 175/-Sq.ft) Granite stone of any approved shade Providing & fixing 20mm thick granite skirting with chamfer/edge polishing including finishing plaster above skirting with curing etc. Complete Providing & fixing Ceramic tile dado for canteen with necessary cement beading with cleaning & filling of joints with grout matching colour etc. complete ( Basic Rate of Tile is Rs.30/- per sq.ft.) 36 UNIT QTY RATE AMOUNT Sq.Mtr 3900 1287 5019300.00 Sq.Mtr 305 4379 1335595.00 Sq.Mtr 10 4379 43790.00 Sq.Mtr 105 4308 452340.00 Sq.Mtr 45 4308 193860.00 Sq.Mtr 20 4308 86160.00 Sq.Mtr 140 1047 146580.00 SL DESCRIPTION OF ITEM B DOORS Providing and fixing single / double leaf paneled door at all levels and lifts shutter 35 mm thick as per drawing consisting of CCTW top rail size 100 x 35 mm and bottom rail and lock rail 200 x 35 mm insert panels of 12 mm thick commercial ply faced with Laminate of 1mm thick on both the sides including CCTW door frame of 125 x 65 mm with chamfering, rounding, riveting and hold fast of size 300 mm x 40 mm x 5 mm and brass oxidized fixtures fastening, mortise lock, C.P. handles on both sides, stoppers etc. complete. (Considered the cost of hardware fittings Rs. 500/Sqm.) For Rooms Providing and fixing solid core flush door in all levels in single leaf of 32 mm thick decorative type of exterior grade as per detailed drawings approved face veneers 3 mm thick on both face without glazing and venetians in the position shown on the drawings or as directed, with all necessary beads, moldings and clippings, holdfast, chromium Plated fixtures and fastenings, with brass mortise lock, chromium plated handles on both sides, and finishing with French polish etc. complete (For Granite Door Framed Doors) Providing & fixing anodized (15 micron) Aluminium sliding shutters 3 track as per drg./design with 5mm thick plain glass of approved make with all fittings etc. complete. PAINTING Providing & applying Luster paint to walls/ceilings at all levels &lifts of approved quality/colour/shade with necessary preparation of surfaces, cleaning etc. complete Providing and applying two coats of waterproof cement paint of approved manufacture and of approved colour to the plastered surface at all levels and lifts with primer and colour wash in two coats, scaffolding if necessary, cleaning the preparing the surface, watering for two days complete.( For Basement Area.) Providing and applying three coats of texture paint including one coat of primer of approved manufacturer and approved colour and shade to plastered surface including scaffolding if necessary and preparing the surface etc. 13 14 15 C 16 17 18 37 UNIT QTY RATE AMOUNT Sq.Mtr 25 8,800.00 220000.00 Sq.Mtr 10 4,900.00 49000.00 Sq.Mtr 222 5,200.00 1154400.00 Sq.Mtr 23100 250 5775000.00 Sq.Mtr 1600 51 81600.00 Sq.Mtr 250 250 62500.00 SL DESCRIPTION OF ITEM UNIT QTY RATE AMOUNT Sq.Mtr 400 450 180000.00 Sq.Mtr 2300 11 25300.00 Kg 22000 77 1694000.00 Sq.Mtr 600 950 570000.00 Sq.Mtr 20 4,000.00 80000.00 Sq.Mtr 650 574 373100.00 R.Mtr 2355 562 1323510.00 Cu.Mtr 200 474 94800.00 No 30 15,000.00 450000.00 No 3 20,000.00 60000.00 complete.(for compound wall) 19 21 D 22 23 24 E 25 F 26 27 28 a) b) Providing & applying Texture Plaster as per specification of manufacturer on existing plaster surfaces with all tools /scaffolding etc. complete. (Compound Wall External Face) Providing & applying white wash ( total 3 coats) to walls/ceilings with scaffolding including surface preparation etc. complete STEEL WORK Fabrication & Erection of Roof Structure for canteen at Top Roof as per Drg/Design with all required fastener/bolts/washers etc. complete with one coat of lead base primer & 2 coats of approved epoxy paint Providing & Fixing pre-coated formed GI. Roofing Sheet 0.6 mm thick with all necessary hooks and fittings etc. complete. Providing & Fixing M.S. fabricated Safety Doors as per design/drg. with one coat primer & 2 cats of epoxy paint ( the weight considered per sq.mtr is 35- 40 kgs) ROAD WORKS Providing and fixing paver blocks by making sub base for receiving paving blocks, item includes:- a) preparing base with rolling & necessary murum with watering. b)providing 2 layers of 100mmthk metal well compacted with roller) top 3rd layer of 50-75 mm size metal with murum binding well compacted with roller to the level required etc. complete PLUMBING & DRAINAGE WORKS Providing and laying concrete pipes of ISNP2 class of 300 mm dia at all levels in proper line, level and slope including necessary collars, excavation in murum/S.Rock, laying, fixing with collars in cement mortar 1:1 and refilling the trench etc. complete. Extra for excavation in H.Rock for above pipeline Providing and constructing Brick Masonry inspection chambers of following dimensions including 1:4:8 cement concrete foundation, 1:2:4 cement concrete channels, half round G.S.W. pipes, brick masonry, plastering from inside and with frame fixed in cement concrete etc. complete with RCC cover of heavy duty 900 x 450 mm for depth up to 1mtr. Conical type 600 mm dia at top for depth beyond 1 to 2 meter 38 SL 29 30 G 31 32 33 34 H 1 DESCRIPTION OF ITEM UNIT Canteen kitchen equipments Stainless steel, complete with necessary cook wares, tables, shelves, utensils and all allied arrangements etc. complete as per the designs. Providing & fixing W.H. Basin at terrace for canteen with all bracket/ fastener/pillar tap(Jaquar, c.p. continental type) & bottle trap, stop cock including connection up to existing nearest drain 510 x 1040mm bowl depth 250 mm. Misc. Works Stainless Steel Railing of Grade 304 as per Drg. to Ramp/ steps Mirror (Belgium or equivalent 5mm thick) for Toilet blocks a) for Gents & ladies of size of counter(2400 x 1000 mm) fixed on 6mm thick waterproof ply with mirror screws including clipping of powder coated Al. Strips. b) for handicapped toilet & V.I.P. toilets of size 600 x 750 mm c) for Lower Gr. Fl. Toilet of size 450 x 600 mm Providing and fixing PTMT towel rail complete with brackets fixed to wooden cleats with CP brass screws with concealed fitting arrangement of approved quality. 600mm long towel rail with total length of 645mm, width 78mm and effective height of 88mm, weighing not less than 190 gms. Providing and applying wall putty/ plaster of Paris, Putty preferably of BIRLA with desired thickness over plastered surface to prepare the surface even and smooth etc. complete. (This item considered for all indoor wall painting) FALSE CEILING SCHEDULE Providing and fixing 12.5 mm thick Gypsum board false ceiling, Indian Gypsum board with 24 gauge G.I strips supported from roof, fixing main channels on the wall as per approved layouts and design. Necessary cut outs to be made for lights, AC diffusers & grills etc. The job shall include three coats of plastic emulsion paint of ISI make after preparing the surface. 39 QTY RATE AMOUNT Lot 1 2,200,000.00 2200000.00 No 5 10216 51080.00 Sq.Mtr 40 3,000.00 120000.00 No 14 4,000.00 56000.00 No 11 2,000.00 22000.00 No 4 1,500.00 6000.00 No 26 547 14222.00 Sq.Mtr 23100 150 3465000.00 Sq.Mtr 3,700 972 3596400.00 SL DESCRIPTION OF ITEM UNIT QTY 2 Supply & fixing of acoustical mineral fiber board (Dune-ML-RH-99) false ceiling of Armstrong/AMF or equivalent make system with 15 mm Silhouette (BR) grid quick hook suspension system having main tee 3000mm long x 42 mm web height x 15mm wide silhouette (BR) sections. The main runner is to be fixed with 4mm thick pre-stretched GI wire with soffit clear & GI Rawl plug inserted on the main roof to be fixed at 1200 mm c/c. The last hanger at the end of each main runner should not be grater than 450 mm from the adjacent wall. The main runner will be at the distance of 1200 mm c/c. The 1200 mm x 42 mm x 15 mm silhouette (BR) wide cross tee sections, having an integrally formed hook nose with precise butt cut joint end is to be fit in between the main tee at a distance of 600 mm to make a module of 1200mm x 600mm. Another cross tee having an integrally formed hook nose with precise butt cut joint end of size 600 mm x 42mm x 15mm is to be fitted at 1200 mm sections parallel to main tee at 600mm centre to make a square grid of 600 mm x 600 mm. All base frame material should be made of good quality galvanized steel. It should have a capping of material coated with baked polyester paint. The shadow molding perimeter angle white coloured secured at 450 mm c/c is to run all along the peripheral, Prime Dune, RH-99 per painted tiles, microlook, 15 mm thick suitable for 600mm x 600mm grid to be placed on grid. Tiles should have NRC of 0.50, STC of 34 dB, having light reflection of 85% or more & thermal conductivity K-0.052-0.057W/sq.m/ degrees centigrade. The fire rating of tile should be class 0 for fire propagation & class I for spread of flames as per BS 476 & having humidity resistance of 99% RH. The board should have a density of 240-260 kg/Cubic meter. The rate should include for cutout for AC grills & light fixtures, additional members if required is to be provided into the grid system. The work has to be done as per the direction of Engineer-incharge. Sq.Mtr 7,500 40 RATE 1,108.00 AMOUNT 8310000.00 SL DESCRIPTION OF ITEM I FALSE FLOORING Providing and installing raised false floor consisting of pedestals, stringers and floor panels etc. all complete as per drawing and directions of Engineer - in -Charge. . The rates are including cost of all material, labour etc. for the finished work: The work shall be as per the following broad specifications Providing and fixing galvanized and chromate passivation (as per IS: 4736- 1968 ) mild steel pedestal with 394 mm (Approx.) long 25 mm diameter bar 150 mm long machine threaded on one end along with double hexagonal nuts 25 mm internal dia. with necessary washers for level adjustments. The MS bright bar shall be fixed on 100 x 100 x 6 mm M.S base plate by welding it around as per drawing. The top heads of the pedestals shall be of pressure die cast aluminium alloy attachment cast to shape, thickness and size as per standards. The mild steel components of pedestals shall be securely fixed to base floor with rawl plugs and C.P. Brass screws and Araldite etc. Complete as per drawing and specifications and direction of Engineer-in-Charge. Approx. quantity. 1148 nos. Providing and fixing galvanised with chromate passivation (as per IS: 4736 – 1968) Cold rolled/ pressed steel channel stringers of size 40 x 40 x 3 mm placed over top head attachment of pedestals in both directions true to level and alignment complete as per drawing, specifications and direction of the Engineer-in- Charge. approx. qty. 3575 Kg. 1 a) b) 41 UNIT QTY Sq.Mtr 350 RATE 6,099.00 AMOUNT 2134650.00 SL DESCRIPTION OF ITEM UNIT c) Providing and fixing floor panels of size 600 x 600 mm and other similar sizes where ever required with minor adjustments as per requirements and comprising 35 mm thick phenol formaldehyde resin bonded three layered flat pressed teak wood particle boards (Novateak super or equivalent) with 2 mm thick decorative laminate super suede finish formica of fire retardant and flooring grade (FRFG), antistatic quality or equivalent fixed to the board surface with adhesive of approved quality. The bottom and edges of the floor panels shall be covered with 0.71mm aluminium sheet fixed to the board by using adhesive of approved quality. No portion of particle board shall remain exposed. The floor panels shall have holes and openings for sizes indicated in the drawing or as per the direction of Engineer-in-charge for the services and cabling. The edges of panels shall have a hard PVC beading of approved shade and size. The beading shall be push fitted with a suitable size groove engraved in the edges of the tile and fixed firmly with adhesive. Aluminium sheets shall over- lap the beading edge. The finished panels shall be perfect to size, shape, alignment, free from any undulations /warping and shall be numbered for identification and complete as per the direction of Engineer-in-Charge. Providing and fixing aluminium cleats of 38 mm x 38 mm x 3 mm, 50 mm long with two Nos 19x 6 mm pan head self tapping sheet metal steel screws in the middle of all the four sides of the floor tiles complete as per specifications and direction of Engineer-incharge. Approx. Qty. 4000 Nos Note : 1. The detailed specifications, procedure for and mode of measurement shall be finished floor area per sq.mtr. Only. 2. The pedestal including it's bar, base plate, nuts, washers and channels etc. in items (a) and (b) above shall be galvanised with chromate passivation as per IS:4736-1968 with minimum 15 micron thickness). 42 QTY RATE AMOUNT SL DESCRIPTION OF ITEM UNIT Total DSR & NON DSR Rate Add @ 8% WCT Add @ 1% Labour Cess Total Service Tax @ 12.36% on 40% Total Add @ 3% Contingencies TOTAL COST OF CIVIL WORK QTY RATE AMOUNT 66207537.00 5296603.00 715041.00 72219181.00 3570516.00 75789697.00 2273691.00 78063388.00 43 44 C-DAC ELECTRICAL – BOQ MSEDCL 22 KV TRANSMISSION LINE SL DESCRIPTION QTY UNIT RATE AMOUNT A MSEDCL 22 KV Transmission Line 1 Supply & Installation Testing Commissioning of 1No VCB complete with protective & aux. relays, Semaphores, Indications, Control & selector switches etc. for C-DAC, Meter Room 1 No. 340000 340000.00 Combined ACDB/ Station battery automatic 2 mode battery charger/ DCDB with SMF sealed lead acid 110 V 150 AH battery 1 No. 218000 218000.00 1 No. 342000 342000.00 4500 Mtrs 2350 10575000.00 4500 Mtrs 4000 18000000.00 100 Mtrs 800 80000.00 400 Mtrs 700 280000.00 800 Mtrs 200 160000.00 4000 Mtrs 40 160000.00 20 Mtrs 2200 44000.00 2 3 4 a) 5 Outdoor Metering cubicle complete as per MSEDCL main & check TV meters Supply laying and termination of 22kV, 3C x 300 mm 2 XLPE armored cable Suitable to outdoor cable including termination kits (4 nos). Including civil work such as, digging trenches having W x D of 0.6 x 1 mtr with sand cushioning, brick covering, cable markers at a distance of 10 mts. etc. complete with removal of paving blocks/ PCC/ RCC/Road, including refilling finishing of route and excavated area. the agency has to clear all the debris from the route to clear the site the whole work has to be executed in such manner that, the complete cabling shall be as per the requisite standards of local and other regulatory standards . Providing & laying including excavation, sand bedding, protection pipe / tiles, sleeves at road crossing, receiving PMC approval for cable laying along roads, laying as per PMC rules, breaking & reinstating the road surface to original condition Provision of obtaining route clearance from PMC with ground rent and other regulatory charges for laying cables through road and designated route etc. complete. Providing and fixing of 75mm x 10mm GI earth strip for Extending loop earthing. 6 Providing and fixing of 50 mm x 6 mm GI earth strip for equipment and loop connection 7 Providing and fixing of 25 mm x 5 mm GI earth strip for equipment and loop connection Providing and fixing of 8 SWG GI wire for loop earthing. Providing, laying and termination of 22 KV (E) 3C x 150 mm2 XLPE armored cable with 2 Nos Indoor cable termination kit for inter connection of HT PANEL and Transformer. 8 9 45 Sub Total of MSEDCL 22 KV Transmission Line 30199000.00 2415920.00 Add @ 8% WCT Add @ 1% Labour Cess 326149.00 Total 32941069.00 Service Tax @ 12.36% on 40% 1628606.00 34569675.00 Total 1037090.00 Add @ 3% Contingencies TOTAL MSEDCL 22 KV Transmission Line 35606765.00 DIESEL GENERATOR 1 x 2000 KVA FOR BLDG. SERVICES SL DESCRIPTION QTY UNIT RATE 1 2000 KVA, 433V, acoustically canopied, water cooled with remote radiator/cooling tower, AVP mounted electric start DG set complete with engine & generator safety features, 1500 RPM, complete with control panel having AMF, battery& battery charger, fuel / lube / fuel tanks with fuel lines, etc. complete 1 No. 29705271 29705271.00 2 2000 KVA DG set Remote radiator cooling pump set 1 working + 1 Standby Complete 2 No. 240000 480000.00 3 125 nb MS class B Piping complete with fittings & supports, monitoring pressure and temperature digital indicators etc. complete. 80 Mtrs 8800 704000.00 4 125 NB Sluice Gae Valve with companion flanges etc. complete. 125 NB non return sluice valve with companion flanches etc. Sandwich type 500 V bus duct complete with Horz. & Vert. bends, adopter boxes, structural supports, end bimetallic flexible connectors 6 Nos 28000 168000.00 2 No. 44000 88000.00 3200 A for DG set to AMF panel and AMF panel to Main LV board 50 Mtrs 82600 4130000.00 7 Providing and fixing Bus trucking termination box on alternator with suitable size of bus bar arrangement. 1 Job 45000 45000.00 8 Supply and fixing flexible bus bar joining at the end of bus trucking 4 Sets 62000 248000.00 9 a) Supply and fixing following size of MS pipe 5mm thick for extending exhaust piping from DG set to out side the building including providing thermal insulation with 75mm thick glass wool/ mineral wool and providing aluminium cladding etc, complete as required. 350mm dia 25 Mtrs 12600 315000.00 b) 500mm dia 40 Mtrs 18000 720000.00 5 6 46 AMOUNT 10 Supply and laying 50 mm dia MS 'C' class pipe with necessary bend, flanges reducers etc. for fuel piping from fuel tank to engine 120 Mtrs 1180 141600.00 11 Supply and fixing structural support for exhaust pipe, water piping bus duct etc. with suitable size of MS channel, angle, flats and square bar etc. complete with cutting, welding, drilling and painting with one coat of red oxide and two coat of enameled paint of approved shade. FUEL STORAGE UG TANK 3200 Kg 110 352000.00 Supply and fixing 20000 Ltrs. capacity under ground storage MS Diesel tank consists of tank, man hole and lid with cover, inlet and out let connections, level gauge, air vent etc. complete with unloading arrangement including hose, gate valve, Y strainer and NRV etc. as reqd, along with necessary civil works and sand cushioning. Supply and fixing self priming, flame proof, gear pump for diesel transport from under ground tank to Day tank . The pump shall have a capacity of 80 lpm @ 15 Mtr Head along with DOL starter, diesel level digital indicator cum controller for both the tanks for automatic fill up and level control. Sub Total of Diesel Generator 1 Job 1050000 1050000.00 1 Job 65000 65000.00 C 1 2 38211871.00 3056950.00 Add @ 8% WCT 412688.00 Add @ 1% Labour Cess 41681509.00 Total 2060734.00 Service Tax @ 12.36% on 40% 43742243.00 Total 1312267.00 Add @ 3% Contingencies TOTAL Diesel Generator Set 45054510.00 UPS (UNINTERRUPTIBLE POWER SUPPLY) SL DESCRIPTION QTY UNIT RATE 1 Supply, installation testing and commissioning of STAND ALONE 600 KVA UPS & their Batteries for back up period of minimum 10 minutes , Battery MCCBs, flexible leads, terminations, battery rack, connections between UPS & Batteries etc, including all other items required for installation, Testing and commissioning of UPS. 1 No 10965868 47 AMOUNT 10965868.00 2 Supply, installation testing and commissioning of Stand Alone 400 KVA UPS & their Batteries for back up period of minimum 10 minutes, Battery MCCBs, flexible leads, terminations, battery rack, connections between UPS & Batteries etc, including all other items required for installation, Testing and commissioning of UPS. Sub Total of UPS 1 No 6293500 6293500.00 17259368.00 1380749.00 186401.00 18826518.00 930783.00 19757301.00 592719.00 20350020.00 Add @ 8% WCT Add @ 1% Labour Cess Total Service Tax @ 12.36% on 40% Total Add @ 3% Contingenciec TOTAL UPS ELECTRICAL INSTALLATIONS SL DESCRIPTION QTY UNIT RATE AMOUNT Supply and fixing 4th floor & 5th floor light and power distribution panel consisting of 1 x 200 A TPN MCCB, 50 KA as incomer along with metering and 12 nos 63 A 4 pole MCB as out going feeders along with ON indicating lamps etc complete with internal wiring and suitable size PVC insulated, copper conductor flexible cable with suitable size crimpled lugs, sleeves, ferules insulators and terminals etc. complete as required. Supply and fixing First floor Data Centre UPS Distribution Panel, consisting of 1 x 630 A 4 pole MCCB as incomer and 6 x 200 A four pole MCCB and 20 Nos 63 A 4 pole MCBs as out going feeders complete with internal wiring with suitable size of PVC insulated, Copper conductor flexible wire with suitable size of crimpled lugs, sleeves, ferules insulators and terminals etc. complete as reqd. DISTRIBUTION BOARDS Supply, Installation, Testing & Commissioning of following type Distribution board surface / flush mounted with Double Door MCB DBs. The DB shall have appropriate no. of top & bottom knock outs for outgoing circuits & shall be complete with necessary bus bars, interconnection terminals & earth studs. All terminations in DB shall be complete with ferruling, dressing & all circuits shall be properly labeled with PVC strip (sticker type) having identification as per the final approval of Consultant. 2 No 328000 656000.00 1 Nos 416000 416000.00 PANELS 1 2 3 48 SL QTY UNIT a) 3 Way TPN DB Horizontal type DESCRIPTION 42 Nos RATE 9800 AMOUNT 411600.00 b) 4 Way Vertical MCB DB 6 Nos 10200 61200.00 c) 6 Way Vertical MCB DB 6 Nos 12800 76800.00 d) 8 Way Vertical MCB DB 18 Nos 14000 252000.00 e) 12 Way Vertical MCB DB 25 Nos 18000 450000.00 f) 4 Way SPN DB 6 Nos 8500 51000.00 F 1 MCBs Supply and fixing following type MCBs in existing MCB DBs including its incoming and out going connection with suitable size of PVC insulated, copper conductor flexible wire etc. as reqd. a) 63A 4 Pole MCB 60 Nos 4500 270000.00 b) 40A 4 Pole MCB 20 Nos 4000 80000.00 c) 32A 4 Pole MCB 70 Nos 2800 196000.00 d) 6-32A SP MCB 2500 Nos 180 450000.00 e) 32 A 4 Pole MCB with Suitable Sheet Steel Enclosure 20 Nos 4500 90000.00 G 1 a) CABLES AND ACCESSORIES Supply and laying of following LT cables rated for 600/1100 volt AC PVC insulated PVC sheathed Cu./Al. conductor armored cable as per IS standard 1554 part I with necessary M.S. clamps and spaces on existing wall, tray, Hume pipe etc. complete as reqd. including necessary terminations with required legs and glands. 3.5c x 300sq.mm. al. armored cable 1355 Mtrs 1800 2439000.00 b) 3.5c x 185sq.mm. al. armored cable 170 Mtrs 1200 204000.00 c) 3.5c x 120sq.mm. al. armored cable 224 Mtrs 980 219520.00 d) 3.5c x 70sq.mm. al. armored cable 30 Mtrs 700 21000.00 e) 3.5c x 50sq.mm. al. armored cable 60 Mtrs 580 34800.00 f) 3.5c x 25sq.mm. al. armored cable 1800 Mtrs 400 720000.00 g) 4c x 16sq.mm. al. armored cable 350 Mtrs 290 101500.00 h) 4c x 10sq.mm. cu. armored cable 800 Mtrs 850 680000.00 i) 4c x 6sq.mm. Cu. armored cable 3600 Mtrs 580 2088000.00 j) 4c x 2.5sq.mm. Cu. armored cable 21300 Mtrs 300 6390000.00 k) 2c x 1.5sq.mm. Co. armored cable 2000 Mtrs 190 380000.00 2 Supply and fixing of GI perforated cable trays, fabricated out of 16 Swg GSS, with supports, fittings etc. complete for the following sizes. a) 150 mm width x 50mm 1200 Mtrs 850 1020000.00 b) 250mm width x50mm 400 Mtrs 980 392000.00 c) 450 mm width X 50 mm 200 Mtrs 1400 280000.00 H POINT WIRING 49 SL DESCRIPTION QTY UNIT 1 Providing point wiring for Primary light points using 2 x 1.5 Sq.mm copper Flexible conductor PVC insulated wires conduits of 25/20mm dia. & 2mm. wall thickness, surface mounted on ceiling, concealed in wall and or through partitions with necessary boxes, Ceiling rose, 6A modular type switch, mounting plate and concealed Metal Box and proper clamping complete as per the final approval of Architect / Consultant. (Average length considered 10 Meters) the wiring points shall be with extension of earthing to all the points. Providing point wiring for Secondary light points using 2 x 1.5 sq.mm copper Flexible conductor PVC insulated wires in GI conduits of 20mm dia. & 2mm. wall thickness, surface mounted on ceiling, concealed in wall and or through partitions with necessary boxes, Ceiling rose and proper clamping complete as per the final approval of Architect / Consultant.( Average length considered 5 Meters) all the point wirings shall be along with necessary earthing arrangements. Providing point wiring for Primary 5A switch socket using 2 x 1.5 Sq.mm copper Flexible conductor PVC insulated wires in GI conduits of 25/20mm dia. & 2mm. wall thickness, surface mounted on ceiling, concealed in wall and or through partitions with necessary boxes, Ceiling rose, 6A modular type switch, and socket mounting plate and concealed Metal Box and proper clamping complete as per the final approval of Architect / Consultant. ( Average length considered 10 Meters) Providing Secondary point wiring for 5A switch socket using 1.5 sq.mm copper conductor PVC insulated wires with 6A modular type switch and socket, mounting plate and concealed Metal Box and proper clamping complete as per the final approval of Architect / Consultant. ( Average length considered 10 Meters) Providing point wiring for Primary 16A switch socket using 2R X 2.5 sq.mm copper conductor PVC insulated wires in GI conduits of 25/20mm dia. & 2mm. wall thickness, surface mounted on ceiling, concealed in wall and or through partitions with necessary boxes, Ceiling rose, 16A modular type switch, and socket mounting plate and concealed Metal Box and proper clamping complete as per the final approval of Architect / Consultant. ( Average length considered 10 Meters) along with earthing LIGHTING FUXTURE 1200 Nos 950 1140000.00 2000 Nos 600 1200000.00 1900 Nos 950 1805000.00 4600 Nos 300 1380000.00 260 Nos 1250 325000.00 2 3 4 5 I 50 RATE AMOUNT SL DESCRIPTION 1 Supplying, Installation, Testing & Commissioning of the following concealed /surface mounted or suspended light fixtures with lamps, Electronic ballast & all necessary mounting & supporting accessories as per the final approval of Architect / Consultant. 2 x 18 W CFL Recess Mounted CFL down lighter with frosted glass. a) QTY UNIT RATE AMOUNT 350 Nos 1980 693000.00 b) 4 x 14 W CFL recess decorative type fitting equivalent to GE Make TC 4 x 14 MO MLC HF 1800 Nos 7600 13680000.00 c) 2 x 13 W CFL recess down lighter equivalent to GE make CFL 2 x 13 DN FG R 740 Nos 1950 1443000.00 d) 1 x 50 W CFL light fixture equivalent to GE make MR C DNR 1 R 25 Nos 5150 128750.00 e) 1 x 28 W fluorescent tube light fitting recess type 25 Nos 3500 87500.00 f) 2 x 28 W Fluorescent recessed type fittings complete. 700 Nos 4400 3080000.00 g) 2 x 18 W spot light fittings with lamps 40 Nos 2200 88000.00 h) 18 W post top fitting all as per std. specifications 60 Nos 9400 564000.00 i) 18 W CFL decorative fittings as per the selection of Architect 250 W Halogen flood light fittings with gear box. 100 Nos 2200 220000.00 8 Nos 7000 56000.00 15 Nos 22000 330000.00 j) 1 COMPOUND LIGHTING Street Light Pole: Supply, assembling, installation, and erection of single arm 6 meter Octagonal galvanized tapered pole (above ground level) similar to M/s. Bajaj or equivalent, fabricated out of 3mm thick sheet complete with built in junction box, base plate size 225 x 225 x 16 mm, one arm of galvanized pipe of 48.3 mm OD, 3.25 mm thick and 1.5 m in length on one side of pole shaft as per detailed specifications. Junction box should be provided 500 mm above base plate with 4 Nos brass terminals on epoxy insulator, 1 no 6A SP MCB & 1 no. Neutral link mounted on 3mm thick Bakelite sheet, gland plate etc. Base plate should have 4 nos holes suitable for mounting on RCC foundation 200 mm above FGL, as per specification. The cost of pole shall include the cost of RCC foundation M 20 grade, foundation bolts, anchor plates, nuts, washers, PVC grade pipe 63 mm dia bend to shape & including excavation in all types of soil/foot path cutting, temporary reinstatement, back filling, dewatering, consolidation, disposal of excess earth within the radius of 500 mtrs and making good to the original finish etc. as required to complete the work in all respect as per instructions of the E-I-C. 51 SL DESCRIPTION 2 Light Fitting & Fixtures: Supply, Installation, testing & commissioning of following Luminaire including internal wiring with 3 x 2.5 Sq.mm PVC insulated copper conductor cable from terminal box at bottom of the pole to the fixture, earthing of fixture etc as per instructions of the EIC. Street light fitting with 150 W SONT lamp similar to Philips cat. No. CRP 330/SON-T-150W or equivalent. a) b) Earthing of street light pole with 2 nos of 8 SWG G.I earth wires each 8 m long coiled in 1 m dia coil at a depth of 1400 mm below ground level complete with soldering and connections with sockets etc all as per specifications and as per instruction of E.I.C 3 Supply, Installation, Testing & Commissioning of compound light Control Box fabricated from 2 mm thick MS CRCA sheet suitable for wall mounting type complete with seven tank processing and painting, earthing locking arrangement fixed on 40x40x5mm angle iron frame, incoming and outgoing cable/ wire way box etc with internal control wiring with FRLS PVC insulated copper conductor wires consisting of following & as per the instructions of E.I.C. GA drawing to be got approved before fabrication. a) 63 Amp.TP & N MCB -1 No. b) 63 A T P contractor (AC-3) 1 No c) Modular Astronomical Digital time switch similar to M/s Legrand make cat no. 004764 - Astrorex D21 or equivalent approved make (with software based self adjustment of all days in the year based on longitude of location.) with 6/10 A SP MCB and supporting arrangement - 1 set. d) ON/OFF push buttons with indicating lamps - 1 set. e) R, Y, B indicating lamp for main supply with HRC protection fuse - 1 set. f) Auto Manual Switch - 1 No. g) 2A HRC fuse for control circuit - 1 No. 52 QTY UNIT 15 Nos 12500 187500.00 15 Nos 2000 30000.00 48000 48000.00 1 Nos RATE AMOUNT SL a) DESCRIPTION QTY UNIT L.T.Cable: Supply, installation, testing & commissioning of 2 core 4 sq,mm.1.1 KV grade copper stranded circular/ sector shape core conductor with PVC/XLPE insulation, PVC extruded (inner) sheathed type ST-2 , G.I flat strip/wire armored, PVC outer sheathed with antirodent & anti termite treatment FR grade PVC sheath type ST-2 cable conforming to IS : 1554 Part I / IS 7098 Part-I with latest amendments, fixed on wall/column /slab /false ceiling or in existing Hume pipe/GI pipe/ trench / shaft/pit/ on 5mm thick M.S. flat /GI spacer/angle/ support fixed with coach screws /grouted in wall/anchor fasteners 2mm. thick G.I. fabricated saddle, all fixing accessories, etc complete including painting of M.S spacers/ angles and saddles or in ground at a - depth of 900 mm below ground level/in all types of soil/concrete road cutting /foot path cutting except hard rock excavation including excavation, sand bedding, laying of baked bricks on side & top, temporary reinstatement, back filling, dewatering, consolidation, disposal of excess earth within the radius of 500 mtrs and making good to the original finish etc providing brass cable number tag as per enclosed detailed specifications, drawings & as per instructions of the E-I-C & of the following sizes. LIGHTNING ARRESTERS Providing & fixing of conventional spike rod type copper air terminal / lightening arrestor (1.5 Kg 15mm solid copper rod of 1m length with 5 fingers) at shown location including making suitable fixing arrangement etc. complete as per site requirement. 200 Mtrs RATE 400 AMOUNT 80000.00 6 Nos 4000 24000.00 2 Nos 8000 16000.00 1 AVIATION LAMP Aviation obstruction light LED type with 1 meter mounting Bracket and necessary wiring, termination including necessary earthing etc. complete for auto operation. TELEPHONE AND DATA CABLING Telephone instruments 1400 Nos 1450 2030000.00 2 Telephone jacks with back box 1400 Nos 300 420000.00 3 2P 0.5 sqmm cu telephone cable in raceways 11300 Mtrs 28 316400.00 4 4P 0.5 sqmm cu telephone cable in raceways 7000 Mtrs 40 280000.00 5 10P 0.5 sqmm cu telephone cable in raceways 8500 Mtrs 64 544000.00 6 10x5 krone connector module in box for 20 IC lines 1 No 3500 3500.00 7 10x5 krone connector module in box for EPABX 1 No 2800 2800.00 8 10x 30 krone module in krone box (300 users) 6 No 16000 96000.00 9 100 pair jelly filled 0.5sqmm Cu telephone armored cable 350 Mtrs 850 297500.00 a) J 53 SL QTY UNIT 10 EPBAX 20IC1000OG with console & PC for MIS 1 No 480000 480000.00 11 Cabinet for switches 20 No 8000 160000.00 12 350 Mtrs 480 168000.00 13 12 C multimode outdoor armored OM3 OFC back bone 4P Cat VI 0.5sqmm Cu UTP data cable 100200 Mtrs 66 6613200.00 14 4 C multimode indoor OM3 OFC fly cable 19000 Mtrs 512 9728000.00 15 6 C multimode indoor OM3 OFC fly cable 7100 Mtrs 540 3834000.00 16 12 C multimode indoor OM3 OFC fly cable 7500 Mtrs 560 4200000.00 17 Live Interface Unit at the end of fly cable (for OFC backbone) 3 M long SCLC OFC patch cord 1 Nos 14500 14500.00 1 Sets 520 520.00 Media convertor at patch panel for OFC to UTP signal 16swg GI C shape channel with removable cover data 150 x 38mm 1 Sets 18000 18000.00 3900 Mtrs 700 2730000.00 18 19 20 K DESCRIPTION 1 PUMP SETS Supply, installation, testing and commissioning of Building water supply pumps having capacity of 330 LPM @ 60 mtr head along with inter connecting valves, piping up to 22 mtrs, all electrical and control accessories for auto mode operation for filling the tanks with necessary sensors and controls etc. complete. Supply, installation, testing and commissioning of De- Watering pumps having capacity of 200 LPM @ 25 mtr head along with inter connecting valves, piping up to 22 mtrs, all electrical and control accessories for auto mode operation for filling the tanks with necessary sensors and controls etc. complete. FIRST AID AND SAFETY MATS Rubber mat 2 1 2 L RATE AMOUNT 0.00 2 Nos 115000 230000.00 2 Nos 68000 136000.00 40 Nos 1800 72000.00 First Aid Box 8 Nos 4500 36000.00 12 Nos 650 7800.00 3 Shock treatment chart M TESTING COMMISSIONING AND WARRANTY OF SYSTEM 1 Installation testing commissioning of entire installation including the system already installed and system included in this boq. Etc. complete. 1 JOB 1200000 1200000.00 2 Providing all necessary documentations, training to the maintenance staff and warranty for entire system for a period of one year from the date of handing over to the user. Sub Total of Electrical Installation Add @ 8% WCT 1 JOB 2400000 2400000.00 Add @ 1% Labour Cess 81054390.00 6484351.00 875387.00 54 SL DESCRIPTION QTY UNIT RATE AMOUNT 88414128.00 Total Service Tax @ 12.36% on 40% 4371194.00 92785322.00 Total Add @ 3% Contingencies 2783560.00 TOTAL Electrical Installation 95568882.00 SUMMARY TOTAL MSEDCL 22 KV Transmission Line 35606766.00 TOTAL Diesel Generator Set 45054510.00 TOTAL UPS 20350020.00 TOTAL Electrical Installation 95568882.00 TOTAL 196580178.00 55 56 INTERIOR WORK – BOQ SL DESCRIPTION OF ITEM UNIT QTY RATE AMOUNT Nos 4 3,01,105.00 12,04,420.00 Nos 17 1,29,636.00 22,03,812.00 Nos 46 60,928.00 28,02,688.00 Nos 32 60,928.00 19,49,696.00 Nos 20 58,821.00 11,76,420.00 Nos 2 58,821.00 1,17,642.00 Nos 2 58,821.00 1,17,642.00 Nos 3 29,441.00 88,323.00 Nos 22 16,007.00 3,52,154.00 Nos 2 21,345.00 42,690.00 PART - I – FURNITURE 1 Providing and fixing Director General's Tables. Providing Godrej Jefferson Presdite Suite suite including J Main Desk 2400x1104, J eru 1400x580, J back unit 1860x580 and J tower unit 1700x400 mm. 2 Providing and fixing P.C.'s Tables Providing Godrej Numbero Uno table in size of 2200x1190, with side unit 1380x480 with pedstal and back unit in size of 2406x400 mm. 3 Providing and fixing T.C.'s Tables Providing Godrej Finness table 6030 in size of 1800x900 with F Eru 3619 with 3 dr steel pedstal with Finness HDU in size of 1280x520 MM. 4 Providing and fixing G.C.'s Tables . Providing Godrej Finness table 6030 in size of 1800x900 with F Eru 3619 with 3 dr steel pedstal with Finness HDU in size of 1280x520 MM. 5 Providing and fixing Secretary's Tables. Providing Godrej Finness table 5026 in size of 1500x750 with F Eru 3619 with 3 dr steel pedstal with Finness HDU in size of 1280x520 MM. 6 Providing and fixing Discussion Tables in Director General's Cabin. Providing Godrej Finness table 5026 in size of 1500x750 with F Eru 3619 with 3 dr steel pedstal with Finness HDU in size of 1280x520 7 Providing and fixing Record Room Table. Providing Godrej Finness table 5026 in size of 1500x750 with F Eru 3619 with 3 dr steel pedstal with Finness HDU in size of 1280x520 MM. 8 Providing and fixing Demonstration Room Tables. Providing Godrej Finness table 5026 in size of 1500x750 MM. 9 Providing and fixing Student's Table in Library. Providing Godrej Versatila Table V2 in size of 1500x894. MM. 10 Providing and fixing Staff Tables in Library Providing Godrej Finness table in size of 1200x600 with 3 dr steel pedestal 57 SL 11 DESCRIPTION OF ITEM Nos 2 16,007.00 32,014.00 Nos 1 60,928.00 60,928.00 Nos 6 58,821.00 3,52,926.00 Nos 1 58,821.00 58,821.00 Nos 1 94,865.00 94,865.00 Nos 1 63,243.00 63,243.00 Nos 123 3,765.00 4,63,095.00 Nos 30 6,451.00 1,93,530.00 Nos 1060 42,068.00 4,45,92,080.00 Nos 100 11,845.00 11,84,500.00 Nos 5 2,70,700.00 13,53,500.00 Nos 1 2,16,560.00 2,16,560.00 Providing and fixing Storekeepers Table . Providing Godrej Finness table 5026 in size of 1500x750 with F Eru 3619 with 3 dr steel pedstal with Finness HDU in size of 1280x520 15 AMOUNT Providing and fixing Bank Staff Tables. Providing Godrej Finness table 5026 in size of 1500x750 with F Eru 3619 with 3 dr steel pedstal with Finness HDU in size of 1280x520 14 RATE Providing and fixing Manager's Table Providing Godrej Finness table 6030 in size of 1800x900 with F Eru 3619 with 3 dr steel pedstal with Finness HDU in size of 1280x520MM 13 QTY Providing and fixing Tables in Discussion Room Providing Godrej Versatila table V 2 in size of 1500x894MM. 12 UNIT Providing and fixing Reception Tables. TYPE-A Providing Godrej First Immression reception table 3 arc TYPE-B Providing Godrej First Immression reception table 2 arc 16 Providing and fixing Corner Tables. Providing Godrej Side table CPR 530 2 E 17 Providing and fixing Center Tables providing Godrej Center table CPR 530 8 E 18 Providing and fixing Workstations with chairs. Providing Godrej Stallion workstation in height of 1200mm and in size of 1500x1500x600 with 3 dr steel pedstal with kbpt cpu trolley with chair Pch 5102R 19 Providing and fixing Cafeteria Tables. Providing Godrej Time out cafeteria table 4 seater pu coated in size of 1022x1022 20 Providing and fixing Conference Table for 30 persons. Providing Godrej Talk Modular conference room table 30 seater laminate finish. 21 Providing and fixing Conference Table for 24 persons . Providing Godrej Talk Modular conference room table 24 seater laminate finish. 22 Providing and fixing Meeting room Table for 12 persons. 58 SL 23 DESCRIPTION OF ITEM UNIT QTY RATE AMOUNT Providing Godrej Talk Modular conference room table 12 seater laminate finish. Nos 13 1,08,280.00 14,07,640.00 Nos 4 72,187.00 2,88,748.00 Nos 158 18,714.00 29,56,812.00 Nos 71 26,483.00 18,80,293.00 Nos 4 25,730.00 1,02,920.00 Nos 32 20,584.00 6,58,688.00 Nos 46 9,337.00 4,29,502.00 Nos 138 5,455.00 7,52,790.00 Nos 32 9,336.00 2,98,752.00 Nos 98 5,455.00 5,34,590.00 Nos 15 9,336.00 1,40,040.00 Nos 67 5,455.00 3,65,485.00 Nos 20 9,336.00 1,86,720.00 Nos 53 5,455.00 2,89,115.00 Nos 1 9,336.00 9,336.00 Nos 3 5,455.00 16,365.00 Nos 147 4,420.00 6,49,740.00 Nos 5 9,336.00 46,680.00 Providing and fixing Meeting room Table for 8 persons . Providing Godrej Talk Modular conference room table 8 seater laminate finish. 24 Providing and fixing Single Seater Sofa. Providing Godrej Petal sofa single seater 25 Providing and fixing Double Seater Sofa. Providing Godrej Petal sofa double seater 26 Providing and fixing Director's Chairs. Providing Godrej Monarch Chair 27 Providing and fixing Director's cabin visitor Chairs. Providing Godrej Monarch Visitor Chair 28 Providing and fixing T.C.'s Chairs. Providing Godrej Gallop Mesh – Mid Back - 9X02A 29 Providing and fixing T.C.'s Cabin Visitors Chairs Providing Godrej Spider Visitor chair Pch 5612 T 30 Providing and fixing G.C.'s Chairs. Providing Godrej Gallop Mesh – Mid Back - 9X02A 31 Providing and fixing G.C.'s Cabin Visitors Chairs. Providing Godrej Spider Visitor chair Pch 5612 T 32 Providing and fixing P.C.'s Chairs. Providing Godrej Gallop Mesh – Mid Back - 9X02A 33 Providing and fixing P.C.'s Cabin Visitors Chairs Providing Godrej Spider Visitor chair Pch 5612 T 34 Providing and fixing Secretary's Chairs. Providing Godrej Gallop Mesh – Mid Back - 9X02A 35 Providing and fixing Secretary's Visitors Chairs. Providing Godrej Spider Visitor chair Pch 5612 T 36 Providing and fixing T.C.'S Chair for Future Cabin . Providing Godrej Gallop Mesh – Mid Back - 9X02A 37 Providing and fixing Visitor's Chairs for Future Cabin. Providing Godrej Spider Visitor chair Pch 5612 T 38 Providing and Fixing Student's Chairs. Providing Godrej 1112 D with Quarter Desklet 39 Providing and fixing Teacher's Chairs. Providing Godrej Gallop Mesh – Mid Back - 9X02A 59 SL DESCRIPTION OF ITEM 40 Providing and fixing Laborartory Chairs. Providing Godrej Gallop Mesh – Mid Back - 9X02A 41 9,336.00 13,72,392.00 Nos 30 9,336.00 2,80,080.00 Nos 13 9,336.00 1,21,368.00 Nos 4 9,336.00 37,344.00 Nos 1 20,308.00 20,308.00 Nos 3 11,179.00 33,537.00 Nos 7 7,497.00 52,479.00 Nos 4 11,179.00 44,716.00 Nos 3 7,496.00 22,488.00 Nos 3 7,496.00 22,488.00 Nos 400 2,931.00 11,72,400.00 Nos 199 9,336.00 18,57,864.00 Nos 188 9,336.00 17,55,168.00 Nos 1 9,336.00 9,336.00 Sq.Mtr 1197 16,542.00 1,98,00,774.00 Providing and fixing Meeting room Chairs. Providing Godrej Gallop Mesh – Mid Back - 9X02A 55 147 Providing and fixing Conference Hall Chairs . Providing Godrej Gallop Mesh – Mid Back - 9X02A 54 Nos Providing and fixing Cafeteria Chairs. Providing Godrej MPC 4 cafeteria chair 53 46,680.00 Providing and fixing Reception Staff Chairs . Providing Godrej Bravo Mid back chair 52 9,336.00 Providing and fixing Storekeeper's Chairs . Providing Godrej Bravo Mid back chair 51 5 Providing and fixing Bank Staff's Visitor's Chairs. Providing Godrej Crest Visitor chair 50 Nos Providing and fixing Bank Staff's Chairs. Providing Godrej Bravo Mid back chair 49 37,344.00 Providing and fixing Manager's Visitor Chairs. Providing Godrej Crest Visitor chair 48 9,336.00 Providing and fixing Manager's Chair. Providing Godrej Ace High back chair 47 4 Providing and fixing Chairs in Discussion Room. Providing Godrej Gallop Mesh – Mid Back - 9X02A 46 Nos Providing and fixing Staff Chairs in Library. Providing Godrej Gallop Mesh – Mid Back - 9X02A 45 AMOUNT Providing and fixing Student's Chairs in Library. Providing Godrej Gallop Mesh – Mid Back - 9X02A 44 RATE Providing and fixing Demonstration Room Chairs. Providing Godrej Gallop Mesh – Mid Back - 9X02A 43 QTY Providing and fixing Record Room Chairs. Providing Godrej Gallop Mesh – Mid Back - 9X02A 42 UNIT Providing and fixing Chair for Gate pass Checker. Providing Godrej Gallop Mesh – Mid Back - 9X02A 56 Providing and fixing Storage units as per drawings and specifications, etc. complete. a) Gain Storage unit – 2100H x 500W x 500D and Gain Overhead storage unit 650H x 500W x 500D with Metal Doors 60 SL DESCRIPTION OF ITEM UNIT QTY RATE AMOUNT b) VSDU- 12 (1192.5H x 1200W x 450D) Sq.Mtr 422 19,342.00 81,62,324.00 c) VSDU -2 (735H x 900W x 450D) Sq.Mtr 450 13,546.00 60,95,700.00 d) Gain Storage unit – 2100H x 500W x 500D and Gain Overhead storage unit 650H x 500W x 500D with Metal Doors Sq.Mtr 21 16,542.00 3,47,382.00 e) Gain Storage unit – 2100H x 500W x 500D and Gain Overhead storage unit 650H x 500W x 500D with Metal Doors Sq.Mtr 29 16,542.00 4,79,718.00 f) Gain Storage unit – 2100H x 500W x 500D and Gain with Metal Doors Sq.Mtr 180 11,635.00 20,94,300.00 57 Column cladding ( for all the floors ) with teak wood frame, finished in laminate Fluorescent Sq.Mtr 2508 4,680.00 1,17,37,440.00 ROLLER BLINDS 1 Providing and fixing roller blinds to windows as per drawings and specifications, etc. complete. Sq.Mtr 1057 1,755.00 18,55,035.00 2 Providing and fixing roller blinds to openings as per drawings and specifications, etc. complete. Sq.Mtr 657 1,755.00 11,53,035.00 Sq.Mtr 3100 5539 1,71,70,900.00 Sq. Mtr 1500 7833 1,17,49,500.00 PARTITION Solid Partition: P&F full ht. laminated partition as per design out of t.w. frame 2" x 1 1/2" @ 1'6"x1'6" grid covered with 6mm comm. Plywood with glass wool insulation finished in laminate on both the sides. Laminate to be from merino designer range ML finish texture P&F full ht. partly laminated partly glazed partition as per design drawing out of t.w. frame 2" x 1 1/2" @ 1'6"x1'6" grid covered with 4mm+6mm comm. Plywood with glasswool insulation, finished in laminate on both the sides for part area and clear glass 12mm thk. as per design fixed onto the partition with 12 mm thk tw beading with PU paint matching in color and finish to the laminate and fixed on top with tw+ply supports concealed above false ceiling. Laminate to be of Merino range. The elevation of glass panels at upper level to be frameless, with only glass panel being visible. Laminated portion of partition to have 2 nos horizontal groove 6 mm x 6 mm in plywood with 6 mm x 6mm aluminium U section fixed in groove, along height of partitions. 61 SL DESCRIPTION OF ITEM Glass Partitions: P&F full ht. partition of 12mm thick clear toughened glass fixed on top with tw+ply supports concealed above false ceiling. The elevation of glass panels at upper level and lower level to be frameless, with only glass panel being visible. Glass panel to be fixed on floor wherever applicable, with channel and rubber gasket below tile level. Glass Doors Complete with toughened 12mm glass having height of 2.1 meter Glass Doors Complete with toughened 12mm glass having height of 2.4 meter SUB TOTAL (PART- I -FURNITURE) UNIT QTY RATE AMOUNT Sq. Mtr 50 15247 7,62,350.00 Sq. Mtr 512 15547 79,60,064.00 Sq. Mtr 22 13949 3,06,878.00 16,62,97,157.00 Add @ 8% WCT 13303773.00 Add @ 1% Labour Cess 1796009.00 181396939.00 Total Service Tax @ 12.36% on 40% 8968265.00 190365204.00 Total Add @ 3% Contingencies 5710956.00 TOTAL FURNITURE 196076160.00 62 63 SCHEDULE OF FIRE DETECTION, FIRE FIGHTING AND FIRE SUPPRESSION WORK AT CDAC, PUNE SL DESCRIPTION OF ITEM UNIT QTY RATE AMOUNT SECTION - 1 ADDRESSABLE FIRE DETECTION AND ALARM SYSTEM 1 2 3 4 5 6 7 8 9 Supply, Installation, testing and commissioning of Analogue Addressable Fire Alarm Control panel with battery backup for 8 hours normal operation and 15 minutes alarm operation. Panel to have number of loops based on quantity of detectors mentioned in the respective item below. The control panel, battery charger etc. shall be UL listed. The panel shall be calculate below quantity of devices with adequate loop arrangements and with 25% capacity additional for future use. & The panel shall be consisting with 40 x 4 line character LCD display and 485 for networking. Cost shall be included for required control module & control relay modules (Location ground floor BMS Room ) Supply, installation, testing and commissioning of Repeater panel FOR Each floor and security cabin. No 1 7650000.00 7650000.00 No 10 50000.00 500000.00 Supply, installation, testing and commissioning of Analogue Addressable Photo-Electrical detector with programmable for timed automatic sensitivity selection with base, junction box and other accessories as required and detectors shall be UL listed.(OSD) Supply, installation, testing and commissioning of Analogue Addressable Photo Thermal Multi Criteria Detector (PTMCD) with programmable for timed automatic sensitivity selection with base, junction box and other accessories as required and detectors shall be UL listed. Supply, installation, testing and commissioning of Response indicator for all detectors located above false ceiling Supply, installation, testing and commissioning of Analogue Addressable Fault isolator module capable of monitoring shorted loop circuit and automatically restore communication when shorted conditions are corrected. Supply, installation, testing and commissioning of Horn cum Strobe rated at 82 DBA @ 3m for Audible annunciation and 75cd flashing at 1 Hz for visual indication. Supply, installation, testing and commissioning of Addressable Single action Manual pull station having an integrally mounted addressable moudle that monitors and reports contact status. Supply, installation, testing and commissioning of Addressable monitor Module Nos 1355 4300.00 5826500.00 Nos 225 4800.00 1080000.00 Nos 425 225.00 95625.00 Nos 90 3750.00 337500.00 Nos 50 6500.00 325000.00 Nos 50 3800.00 190000.00 Nos 10 4000.00 40000.00 64 SL DESCRIPTION OF ITEM UNIT QTY 10 Supply, installation, testing and commissioning of Addressable Control Relay Module Supply, laying & fixing of 2 x 1.5 sq. mm, PVC insulated copper Cable confirming to IS standards and specifications.(Below ceiling or in shafts/walls etc) Supply, laying & fixing of 2 x 1.5 sq. mm, PVC insulated copper wires confirming to IS standards and specifications. (Underground including excavation, back filing, proper manner sand & brick work as per standard electrical manner.) FOR SECURITY CABIN. Supply, laying & fixing of perforated G.I. sheet cable tray with necessary angle iron suspension supports, anchor, fastners etc. complete. Maximum height of suspension shall not exceed 500mm size of the tray is 200mm x 50mm x 14SWG. Nos 40 5000.00 200000.00 Rmt 12000 200.00 2400000.00 Rmt 200 325.00 65000.00 Rmt 500 550.00 275000.00 11 12 13 a) 14 RATE AMOUNT No 50 11000.00 550000.00 a) Supply, installation, testing & commissioning of photo electric integrated low flow duct detectors complete with mounting relays and housing. AUTOMATIC SPRINKLER SYSTEM (REPAIRING & RE-WORK) Supplying, installing, testing and commissioning of G.I. pipes confirming to IS 1239 Pt -I heavy grade with painting, suitable type of supports, (shall be hanger type for all size pipes which run below the slab & for wet risers ‘C’ Channel to be used) with anchor fasteners, bolts nuts, clamps, "U" bolts shall be of malleable specials. Reducers, Tees, Elbows, flanges. Including cutting, welding, fixing in/ on walls, ceiling by using suitable supports etc. as per drawings. The quoted rate shall also include for chasing chipping walls, making bore holes in walls / floor and making them good with filler material and finished in cement mortar etc. complete. 65mm nominal dia Rmt 30 1650.00 49500.00 b) 50mm nominal dia Rmt 48 1350.00 64800.00 c) 40mm nominal dia Rmt 36 1100.00 39600.00 d) 32mm nominal dia Rmt 48 900.00 43200.00 e) 25mm nominal dia Rmt 72 700.00 50400.00 a) Supplying, installing, testing and commissioning of G.I. pipes confirming to IS 1239 Pt -I heavy grade with painting, suitable type of supports, Reducers, Tees Elbows, flanges, including cutting, welding, as per drawings. The rate quoted should be included with anticorrosive treatment with 4mm polymer corrosion resistant tape as per IS 10221, overlap shall be 15mm minimum, cement mortar etc. complete. 150mm nominal dia Rmt 6 3500.00 21000.00 b) 80mm nominal dia Rmt 6 2550.00 15300.00 1 2 65 SL DESCRIPTION OF ITEM UNIT QTY a) Providing and fixing 15mm dia CP gunmetal / brass sprinkler head with temperature of operation 68 deg. C at working pressure of 175 psi, quartzoid bulb and set to operate at specified temperature. Pendant type Nos 10 450.00 4500.00 b) Upright type Nos 2 465.00 930.00 c) Pendant type 91 deg. C FOR PANTRY. Nos 6 550.00 3300.00 a) Supplying, installing, testing and commissioning C.I Butterfly valves as per BS: 5155 (PN10) slim seal standard lever operated type with required flanges, nuts, bolts etc. complete. 150mm nominal dia Nos 1 8500.00 8500.00 b) 100mm nominal dia Nos 1 7500.00 7500.00 c) 80mm nominal dia Nos 1 5750.00 5750.00 d) 65mm nominal dia Nos 1 5250.00 5250.00 a) Supplying, installing, testing and commissioning of Gun metal chrome finished Ball valves as per (PN10) with fitting of screwed end type. 50mm nominal dia Nos 6 6000.00 36000.00 b) 25mm nominal dia Nos 1 3500.00 3500.00 a) Providing and fixing electrically operated flow indicating switches with threaded connection for minimum flow of 900 Ipm for indicating water flow in sprinkler branch line on each floor with necessary junction box installed in accessible plate 100mm nominal dia Nos 1 7500.00 7500.00 b) 80mm nominal dia Nos 1 6000.00 6000.00 c) 65mm nominal dia Nos 1 4750.00 4750.00 7 Supplying and fixing approved make 25mm dia automatic air release valve with unions etc. complete. Nos 4 3500.00 14000.00 8 UL Listed Sprinkler Flexible drop pipes made of Corrugated SS Tubing to with stand 16 Bar pressure with all support accessories with false ceiling framing work 1000 mm long Nos 500 1550.00 775000.00 Nos 18 3250.00 58500.00 3 4 5 6 a) RATE AMOUNT FIRE HYDRANT SYSTEM 1 a) 1 Supplying, erecting and commissioning of landing Hydrants comprising of the following in the fire duct. 1no. Stainless steel short branch pipe with nozzle. FIRE SUPPRESSION SYSTEM (FM 200] FOR UPS AND SERVER ROOMS Fire Fighting System for Server & UPS, Electrical rooms 66 SL 2 3 4 5 6 7 8 9 10 DESCRIPTION OF ITEM UNIT QTY RATE Designing, supply, installation, testing & commissioning of CCOE certified 80 L capacity. Seamless cylinders with valve assembly & protection cap, pressure gauge, Safety burst disc and with low pressure supervisory switch for FM-200 gas installed on cylinder valve with Cylinder Pressure Operated Head with Hose & accessories, install on the Cylinder Valve cylinder support arrangements etc. complete.. Make: Kidde or equivalent Supply of OEM Factory Filled FM 200 Gas. Nos 12 170000.00 2040000.00 Kg 720 4750.00 3420000.00 supply, installation, testing & commissioning of 24 VDC- 2.0 amps, Resettable Electrical cum Mechanical actuator for FM 200 Cylinder with Cylinder Support Assembly, floor mounted, Flexible rubber discharge hose, with braided reinforcement Make: Kidde or equivalent Designing, supply, laying & fixing/ installation of the FM 200 piping will be, as per flow calculations, Sch 40, ASTM - A-106 Gr. B with seamless 3000 psi Socket weld fittings, Discharge nozzles, rigid angle supports,2 coats of zinc primer & 3 coats of P.O red paint. The equipments should be ISI Marked and Indian Seamless. Supply, Installation, Testing & Commissioning of Two zone gas release panel with all requisite mounting accessories and it should be able integrate with other related and BMS System. The Panel should be Complete with Red Colour Housing, Power supply, required Battery charger & 30 min battery backup Supply, Installation, Testing & Commissioning of Manual Abort Stations with DPDT Relay, The Abort will be monitored simultaneously by Fire Alarm System Supply, installation, testing & commissioning of Manual Release Stations with DPDT Relay, The Release switch will be monitored simultaneously by Fire Alarm System. Supply, installation, testing & commissioning of Sign Board with Marking "Gas Discharge. Do Not Enter". Should Operate on 24 V DC, Driven Through Gas Release Panel / CM (for use outside room) Supply, installation, testing & commissioning of Sign Board with Marking "Gas discharge Evacuate immediately". (for use inside room) Supply, installation, testing & commissioning of Cylinder Discharge Pressure Switch, Shall be installed on the FM 200 piping. Nos 4 27500.00 110000.00 Job 4 80000.00 320000.00 No 4 23000.00 92000.00 No 4 1500.00 6000.00 No 4 1500.00 6000.00 No 4 3500.00 14000.00 No 4 4000.00 16000.00 No 4 7000.00 28000.00 67 AMOUNT SL DESCRIPTION OF ITEM UNIT QTY RATE AMOUNT TESTING COMMISSIONING OF HYDRANT AND SPRINKLER SYSTEM 1 2 Testing commissioning of existing hydrant and sprinkler system with necessary addition and alterations for the smooth functioning of the system complete including additional coat of paints where ever required as per engineer-in-charge's directions with necessary sign boards, floor plan indicators, warning boards, entry exit indicators, etc. complete. Providing warranty for the entire firefighting, fire detection and fire suppression system for a period of one year from the date of handing over the system with proper documentations. SUB TOTAL RS. Job 1 100000.00 100000.00 Job 1 1600000.00 1600000.00 28511405.00 Add @ 8% WCT 2280912.00 Add @ 1% Labour Cess 307923.00 31100240.00 Total Service Tax @ 12.36% on 40% 1537596.00 32637836.00 Total Add @ 3% Contingencies 979135.00 33616971.00 TOTAL 68 69 SCHEDULE OF HVAC, C-DAC, PUNE SL ITEM QTY UNIT RATES AMOUNT PART A : INCOMPLETE WORK 1 Chilled Water piping Insulation with 50 mm thick expanded polysterene covered with 28 Swg aluminium sheet from Main Header to AHU 15 Lot 7540.00 113100.00 2 Chilled Water piping Insulation near Chiller connections 3 Lot 6300.00 18900.00 3 Drain Water piping for water Pumps & AHU 1 Lot 15400.00 15400.00 4 Temp Guage , Pressure Guage for All AHU 12 Lot 11200.00 134400.00 5 Temp Guage , Pressure Guage & Flow switch for chiller 3 Lot 23400.00 70200.00 6 AHU valve Station / controller 1 Nos 16200.00 16200.00 7 Insulation on Chilled water piping headers. 45 Mtr 756.00 34020.00 8 Branch duct & Insulation 70 Sq Mtr 3430.00 240100.00 9 Supply + Reurn Air VCD 5 Sq Mtr 5600.00 28000.00 10 Collar Damper & Diffuser 1 Lot 39900.00 39900.00 11 Fire Damper actuators 8 Nos 16100.00 128800.00 12 Ducting arrangement for Fresh Air 65 Sq Mtr 1750.00 113750.00 952770.00 TOTAL OF PART A PART B : NEW WORK TO DO ( NOT EXECUTED ) EQUIPMENTS 1 Supply, installation, testing & commissioning of water cooled screw chillers, with spring loaded anti vibration mounts, Flexible bellows, First Charge of Refrigerant Gas & Oil etc., for the following chillers with the following operating conditions & tender specifications 1 Nos 12276094.00 12276094.00 1 Nos 400336.00 400336.00 Capacity Required - 370 TR Actual Capacity Pune Condition Chilled Water Out - 7 Deg. C. Chilled Water In - 12 Deg. C. Condenser Water In - 30 Deg. C. Condenser Water out - 34 Deg. C. 2 SITC of Condenser water pump end suction pump back pull out (3 W + 1S), each capable of delivering 1500 USGPM of water at 25 m head complete with base frame, spring mount & flexible Bellows etc. 37kw 70 SL 3 4 ITEM SITC of secondary chilled water pump sets , end suction pump back pull out type( 3 W + 1S), each capable of delivering 888 USGPM of water at 45 m head complete with base frame & spring mount, VFD Control & flexible Bellows etc. 45KW SITC of primary chilled water pump sets, horizontal end suction back pull out type ( 3 W + 1S), each capable of delivering 888 USGPM of water at 20 m head complete with base frame, spring mount & flexible Bellows etc. 18.5KW QTY UNIT RATES AMOUNT 1 Nos 826764.00 826764.00 1 Nos 231231.00 231231.00 5 SITC of Jet fan for parking area Ventilation. a) Air Volume CMH 5400/2700 Motor 1.2 KW 17 Nos 328000.00 5576000.00 b) Fresh Air AHU of 15000 CFM for DG SET AREA ventilation. 2 Nos 450000.00 900000.00 6 Air Handling Unit Side a) Double skin (25mm thick) vertical/ horizontal AHU complete with Butterfly Valves, Ball Valves,/2 way modulating Valve, Actuator & Sensor complete with bypass line, controller Strainer, Pressure & thermometers gauges valves duly insulated with 75/ 50 MM thick TF quality EPS & covered with 26 G Aluminium cladding. As per drawings . 4500 CFM 1 Nos 321750.00 321750.00 b) 13000 CFM 1 Nos 676000.00 676000.00 c) 6500 CFM 1 Nos 422500.00 422500.00 d) 9500 CFM 1 Nos 555750.00 555750.00 e) 9253 CFM 1 Nos 541125.00 541125.00 f) 7300 CFM 1 Nos 455520.00 455520.00 g) 13000 CFM 3 Nos 676000.00 2028000.00 h) 8500 CFM 1 Nos 497250.00 497250.00 i) 10600 CFM 1 Nos 606320.00 606320.00 j) 16000 CFM 1 Nos 790400.00 790400.00 k) 6300 CFM 1 Nos 409500.00 409500.00 7 SITC of Hydronic Cassette Air Conditioner unit with necessary piping, pipe insulation and controls. a) Capacity 1 TR 6 Nos 48000.00 288000.00 b) Capacity 1.5 TR 7 Nos 52000.00 364000.00 c) Capacity 2 TR 5 Nos 58000.00 290000.00 d) Capacity 3 TR 4 Nos 88000.00 352000.00 71 SL e) ITEM Capacity 4 TR QTY UNIT RATES AMOUNT 3 Nos 108000.00 324000.00 PIPING WORKS Chilled Water Piping 8 Supply, installation, testing & commissioning of M. S. Class 'C' Chilled Water Piping with insulation of 50 mm thick TF Quality EPS for pipes up to 100 - mm & insulation of 75 mm thick TF Quality EPS for pipes above 100 - mm with 26 Gauge Aluminium cladding. a) 19 mm Dia copper pipe with Nitrile Rubber Insulation. 500 Mtr 600.00 300000.00 b) 20 mm Dia 85 Mtr 634.00 53890.00 c) 25 MM Dia 150 Mtr 739.00 110850.00 d) 32 MM Dia 130 Mtr 921.00 119730.00 e) 40 MM Dia 90 Mtr 1038.00 93420.00 f) 50 MM Dia 185 Mtr 1334.00 246790.00 g) 65 MM Di 130 Mtr 1621.00 210730.00 h) 80 MM Dia 155 Mtr 2028.00 314340.00 i) 100 MM Dia 40 Mtr 2657.00 106280.00 9 Supply, installation, testing & commissioning of following valves with insulation of 50 MM/75mm thick TF Quality EPS covered with 26 Gauge Aluminium Cladding. Equipment side. a) 50 MM DIA 14 Nos 4550.00 63700.00 b) 65 MM DIA 18 Nos 4940.00 88920.00 c) Supply, installation, testing & commissioning of valves Station / controller for Air Handling Units 16 Nos 16900.00 270400.00 10 Supply, installation, testing & commissioning of following ball valves with insulation of 50 MM thick TF Quality EPS covered with 26 Gauge Aluminium Cladding. Equipment side. a) 25 MM dia. 20 Nos 4141.00 82820.00 b) 20 MM dia. 5 Nos 3088.00 15440.00 c) Supply, installation, testing & commissioning of valves Station actuator for Hydronic cassette Units 25 Nos 5400.00 135000.00 Condenser Water piping 72 SL ITEM QTY UNIT RATES AMOUNT 11 SITC of Condenser Water piping for 1 additional Water pump 1 Lot 132000.00 132000.00 12 SITC of Valves & accessories required for installation of water pump 01 Nos. and including Butterfly valve, TG , PG , Flow switch 1 Lot 198000.00 198000.00 13 Supply, installation, testing, commissioning of PVC Sintex Make expansion tank of 500 Lit. capacity with float valve, isolating ball valve, drain pipe with valve, over flow arrangement etc., 1 Nos 51935.00 51935.00 14 Supply, installation, testing & commissioning of following auto air vent valves with insulation of 50 MM thick TF Quality EPS covered with 26 Gauge Aluminium Cladding. Equipment side a) Automatic Air Vents 20 NOS 3120.00 62400.00 AIR DISTRIBUTION 15 SITC of factory made GI Ducting with TDF Flanges as per SMCNA Standard a) 18 Guage 280 Sq Mtr 2040.00 571200.00 b) 20 Guage 620 Sq Mtr 1680.00 1041600.00 c) 22 Guage 950 Sq Mtr 1380.00 1311000.00 d) 24 Guage 1180 Sq Mtr 1128.00 1331040.00 16 G.I Volume control duct damper 38 Sq Mtr 6063.00 230394.00 17 Aluminium Powder coated Supply air removable core diffuser with damper. 42 Sq Mtr 12850.00 539700.00 18 Aluminium Powder coated Return air removable core diffuser without damper. 43 Sq Mtr 10650.00 457950.00 19 Aluminium Powder coated Linear Continuous Grill 6 Sq Mtr 7250.00 43500.00 20 Aluminium Powder coated Box Type Damper Opposed blade construction. 40 Sq Mtr 7500.00 300000.00 21 Aluminium Powder coated Supply Air grill with damper with all side flanged for Supply Air. 4 Sq Mtr 13125.00 52500.00 22 Motorised Fire Dampers with Linkage & dead weights / spring etc to activated from central fire alarm system 20 Sq Mtr 28854.00 577080.00 23 Fresh Air Cowl with Aluminium grille, Bird Screen, Damper 3 Sq Mtr 5278.00 15834.00 73 SL ITEM QTY UNIT 24 Hard PVC drain piping for AHU's with Plumbing Grade PVC pipe, with PE insulation & finished with PVC tape a) 50mm 90 RMT 315.00 28350.00 b) 32 mm 20 RMT 245.00 4900.00 c) 25mm 20 RMT 175.00 3500.00 25 Acoustic insulation of duct with 12 MM thick CR300 rigid board (Fiber Glass) covered with RP Tissue & 30 G perforated Aluminium cladding. 440 Sq Mtr 914.00 402160.00 26 Thermal insulation of duct with 25mm thick CR150 Fiber. Glass covered with factory laminated Aluminium foil, stuck to the duct with Bitumen & finished with 2 "wide PVC Tape and bounded to the duct using Nylon binding strap at every 1 mtr. 100 Sq Mtr 504.00 50400.00 3200 Sq Mtr 1047.00 3350400.00 3100 Sq Mtr 463.00 1435300.00 27 28 Thermal Insulation of duct with 10 mm thick closed cell polyethylene with self-adhesive properties on one side & Aluminium foil on other side( Material to be self-extinguishing type CFC free) & all the joints sealed & finished with selfadhesive Pro-tape Under deck Roof insulation with 50 mm thick TF quality EPS (thermocole fixed with 5 GI screws & GI washers in grid of 1 m x 1m to the underside of the slab. All four corners & center screw will be tied with G.I binding wires RATES AMOUNT Electrical Works for Air conditioning. 29 SITC of Thermostat to be installed in condenser water header ckt. to control cooling tower fan operation (especially in winter) 3 No 4810.00 14430.00 30 Pump logic controller complete with variable speed pumping system comprising of accessories as per specifications for secondary pumps. 1 Lot 3728809.00 3728809.00 32 Electrical Panels for AHU complete with starter for AHU fan motor The panel shall also have on /off indication for AHU Blower and VFD along with temperature sensors to regulate AHU fan motor & 2/3 way valve with power/control cabling & earthing in AHU Room. 14 Nos 168044.00 2352616.00 32 SITC of cable Trays 150 Mtr 696.00 104400.00 33 SITC of Electrical cables 280 Mtr 342.00 95760.00 74 SL ITEM QTY UNIT RATES AMOUNT 34 SITC OF Hydronic Precision package units for NOC Server room each unit having capacity of 22 TR, WITH 12100 CFM etc complete with pipings, cablings and all controls as per requirements. Make: Emmersion, Stulz or equivalent. 7 Nos 1400000.00 9800000.00 35 Complete system testing, commissioning and providing warranty for a period of one year from the date of handing over of system. 1 Job 1500000.00 1500000.00 61132008.00 TOTAL OF PART B PART A 952770.00 PART B 61132008.00 SUB TOTAL 62084778.00 Add @ 8% WCT 4966782.00 Add @ 1% Labour Cess 670516.00 Total 67722076.00 Service Tax @ 12.36% on 40% 3348179.00 Total 71070255.00 2132108.00 Add @ 3% Contingencies Grant Total of HVAC Works 73202363.00 75 76 SCHEDULE OF ELEVATOR, C-DAC, PUNE SL DESCRIPTION OF ITEM UNIT QTY RATE AMOUNT Elivator – OTIS / Equivalent Make 1 Design, manufacture, shop testing, Supply, load trial and performance test for lifts below as per the specification a) 15 person, 1088 KG, in a bank of 2 with triplex control, 1.5 M/Sec speed, gearless machine room less, GROUND FLOOR to 6th floor, passenger lift as Per Approved Specification 2 Nos 4353991.00 8707982.00 b) Installation, Commissioning & Testing of the lifts above 2 Nos 1011240.00 2022480.00 10730462.00 TOTAL Add @ 8% WCT 858437.00 Add @ 1% Labour Cess 115889.00 Total 11704788.00 Service Tax @ 12.36% on 40% 578685.00 Total 12283473.00 Add @ 3% Contingencies 368504.00 GRANT TOTAL OF ELEVATOR WORKS 77 12651977.00 78 ESTIMATE OF OTHER SERVICE SUCH AS BMS, PA SYSTEM, CCTV, AV SYSTEM, ACCESSCONTROL SL 1 ITEM UNIT QTY RATE BUILDING MANAGEMENT SYSTEM (BMS) Complete System Floating Contacts for Connecting Subsystems with DI (Digital Input), DA (Digital Output), AI (Analog Input), AO (Analog Output) Job 1 2800000.00 UP to 80 DI for Electrical Distribution Panels UP to 30 DI for Lighting Control DIs, DAs , AIs . AOs for Central Air Conditioning System 30 DI Fire Alarm & Fire Fighting 10 DI, 5 DA Public Address 20 DI for CCTV System Monitoring 5 DI, 2 DA Elevators 60 DI Access Control, Parking Access, Intrusion Detection 2 DI PABX 2 DI UPS 4 DI for Water Consumption BMS Total 1 2 3 4 5 PA SYSTEM S/I/T/C of speaker wiring with 2c x 40/36SWG shielded and cable cleated to Mtr ceiling, walls etc complete the cost is inclusive of conduit S/I//T/C of 6W line matching transformer; speakers shall be mounted within the AC grills nos so that they are concealed. In some cases they may be ceiling mounted. (BOSCH) S/I/T/C of volume control switches for cabin nos areas (legrand/anchor) Communication Rack with 450 watt amplifier Set & 5 in 1 System with Microphone (AHUJA) With Music system (LG) nos 2 2800000.00 2800000.00 1800 80.00 144,000.00 200 850.00 170,000.00 65 600.00 39,000.00 1 40,000.00 40,000.00 1 38,000.00 38,000.00 431,000.00 PA SYSTEM TOTAL 1 AMOUNT CCTV SYSTEM WORK Supply, Installation, Testing Commissioning CCTV System comprising of following: I/R CCD color, Dome camera with detachable Nos wide angle lense & resolutions of 480 TVL VGA Flat screen TFT 17" high resolution No. Monitor with power supply complete with key 79 50 8,000.00 400,000.00 10 16,000.00 160,000.00 SL ITEM UNIT QTY RATE AMOUNT No. 7 6,000.00 42,000.00 No. 1 150,000.00 150,000.00 Mtrs 2500 180.00 450,000.00 Mtrs. 1200 150.00 180,000.00 board & mouse. 3 4 5 6 Power Supply with Input 230VAC +/- 10%, Output 12V +/- 2Volt, load regulation & line regulation less than 0.1%, Electronic protection against overload & short circuit, cutout ripple less than 1 millivolt RMS with Redundancy mode facility. 10 Amps output Networkable Digital Video Recorder Embedded Linux/Windows, MPEG 4+ compression LAN/TCP/IP, Networked Pentaplex operation Schedule/Motion/Alarm Sensor Recording/continuous Server to Server Configuration up to 8 Alarm input & 4 Relay output Alarm Notification Via e-mail Smart search, Post & pre Alarm recording Water marking, PTZ control, Password protection. Minimum 1000GB HDD, expandable built in DVD Writer up to 16 channel RG 59 cable PVC conduit for camera 2 Core power cable PVC insulated & sheathed Cable in above Conduit CCTV TOTAL 1,382,000.00 AUDIO VISUAL SYSTEMS FOR CONFERENCE ROOM. A Display system 1 Nos 17 68000 1156000.00 Nos 17 180000 3060000.00 Nos 6 68000 408000.00 Nos 17 18000 306000.00 B 40``: 5 SERIES DLP Data projector 2200 ANSI lumens; Texas Instruments designed DLP chip. 1024 x 768 XGA resolution.1300:1 contrast ratio, 4000 HRS LAMP LIFE Motorised imported screen (84" diagonal) with black border and tubular motor driving device with less noise and smooth functioning. Actual viewing area shall be 51" H X 69" W. Fixed mount projector kit for a projector support unit (PSU). Switching Devices / Interface 1 Motorised Nos 17 12000 204000.00 2 Splitter Nos 17 8500 144500.00 C Video Conference equipment ( HIGH DEFINITION ) 2 3 4 80 SL 1 2 3 D 1 2 4 1 2 3 4 5 6 7 8 9 ITEM UNIT HDX 7000-720: HDX 7000 HD codec, EagleEye HD camera, HDX mic array, P+C, PPCIP, 2nd monitor, Eng rmt. Cables: 2 component video Nos (DVI-RCA), audio (RCA-RCA), LAN, U/E/A pwr. Cntry code 20. PAL (Maintenance Contract Required) HDX MPPlus Multipoint Software Option License. Allows for 4 site MP video calls. No Available for HDX systems (4000, 7000, 8000 and 9000 Series). Quad BRI Module for HDX 9000 Series. Includes four 20ft/6m ISDN cables (with green Nos connectors). Cables and installation. Cables & connectors (as required). These shall include cables required for RGBHV, Svideo, video, audio, microphones, speakers & patch Mtrs cords for VGA and audio. The cables shall be of imported quality, designed by US companies like Extron, Belden or MS Project Management & Installation for the Job above equipments. Commissioning and training - Handing over the complete documents for the project, Job including user manuals, as built drawing and schematics. TOTAL -AUDIO VISUAL SYSTEM QTY RATE 3 340000 1020000.00 1 150000 150000.00 3 32000 96000.00 1 80000 80000.00 3 40000 120000.00 1 20000 20000.00 ACCESS CONTROL SYSTEM Proximity Readers Nos 40 Door Control Panels with Card/ Biometric No 40 Readers DC Power supply for Access controller No 40 S&I of single Door magnetic lockNo 40 S&I of magnetic door contact No 40 S&I of exit push button No 40 Proximity Card No 1200 S&I of system software time and attendance No 1 S&I of point wiring for access control system comprising of 8 core twin twisted signal wire 0.75sq mm cu pvc of 8 core twin twisted signal wire 0.75sq mm cu pvc insulated and overall Mtrs 1320 screened pulled through 20/25 pvc conduit fixed on wall/ above ceiling/ door frame to the door as required 81 AMOUNT 6764500.00 8000 320000.00 70000 2800000.00 4000 8000 6500 250 250 250000 160000.00 320000.00 260000.00 10000.00 300000.00 250000.00 140 184800.00 SL 10 11 ITEM UNIT 4 core 14/36 shielded unarmored cable with Mtrs 20/25 mm PVC conduit 2 core 14/36 shielded unarmored cable with Mtrs 20/25 mm PVC conduit Total BMS PA System CCTV System Audio Visual Systems Access Control System Total QTY RATE AMOUNT 500 240 120000.00 500 200 100000.00 4824800.00 2800000.00 431000.00 1382000.00 6764500.00 4824800.00 16202300.00 1296184.00 174985.00 17673469.00 873776.00 18547245.00 556417.00 19103662.00 Add @ 8% WCT Add @ 1% Labour Cess Total Service Tax @ 12.36% on 40% Total Add @ 3% Contingencies Grant Total of Works 82 83 Schedule of Recurring Expenses during project execution The MSEDCL have already sanctioned the power and pressing highly to take the power connection with immediate effect. The total sanctioned power is 300 KW/Hour however made provisions for 5 MVA The expected monthly bill without significant use during the project execution time has been taken as recurring expenses. SL 1 Item Expected cost Per month For ten months 4500000.00 45000000.00 MSEDL Charges The amount is included in the project cost. 84 85 BRIEF HISTORY:The Centre for Development of Advance Computing, Pune is setting up a campus under the name & style of Innovation Park. The campus is located at S.No.34B/1, CTS 788(P), Pashan, Pune. The objectives of setting up of this campus are to have its own premises befitting an organization of a stature of CDAC. Due to various reasons the building work has been stopped for the need of additional fund, The C-DAC, Pune has appointed HSCL for preparing a realistic cost estimate for the balance work. After appointment of HSCL as agency, number of meetings and deliberation has been conducted with the C-DAC Officials and their consultants. According to the meetings and requirements, addition and deletion of Items are effected and minor changes in the specification also have been carried out. The schedule of works was re-worked according to the requirements. The present estimate has been prepared based on Delhi Schedule of Rates (CPWD) Pune, Index for items where ever applicable and market rates of the financial year 2012-2013. REASONABILITY STATEMENT:The work estimated as per the items re-scheduled with the details are as follows. 1. Civil Works: - The earlier Estimate was prepared according to the market rate of 2007. The market rate in these years has gone up. The increase in the index amount is around 51% as per the DSR, Pune CPWD Index which is due market inflation. 2. Furniture: - The Item was excluded from the earlier scope of work due to constraints of fund. Now the Estimate has been prepared based on the quotation called from M/s. Godrej & Boyce manufacturing Co. Ltd. 3. Electrical Works: - The work was estimated during 2007. The detailed schedule was re-worked after number of meetings, for wiring, Distribution panel, fixtures etc. All the services such as Audio Visual system, EPABX system, UPS, Access control, CCTV etc has been considered in addition to the earlier estimate. The Generator of 2000 KVA has been considered with remote radiator to make the system more energy efficient. The addition of items and the market rate inflation has caused to increase in the cost of estimate. The present market rate quotations were called according to the same the rates has been calculated. 4. HVAC: - The work was initially estimated in the year of 2007 based on the market rates. Market rates have been increased considerably due to the changes in foreign exchange value for the components and materials such as copper and aluminium. The approximate rate variation is around 44%. The Present market rate quotations were called to consider the rates. 86 5. Fire Detection and Fighting Work:- The system were not comprehensively scheduled out in the earlier estimate for fire alarm system, the complete system has been re-calculated and rescheduled according to the requirements. The fire suppression system for the high hazard server rooms, with FM-200 gas has also been considered in addition to the earlier estimate. The repeater panels for all floors and security cabin etc was not considered in the earlier estimate, the same has been considered in order to have proper and prompt control in case of the fire eventuality. The sprinkler system installed will have to integrate with the false ceiling and other services which are routed through above the false ceiling. The present rigid piping system may require modification with flexible down pipes. The addition of systems and market inflation has caused increase in the cost. 6. Elevators:- The earlier estimated lift item has been changed due to continuous product developments and a present available system market rate quotation were called and accordingly item has been estimated. 7. Testing Commissioning and Warranty:- The situation of partial supply and installation of various systems and unknown situation for the future execution agencies, it has been taken in to the consideration that, the agency who will be executing the balance work should also be responsible for the entire system installation, Testing, Commissioning, Performance warranty, Training and Warranty services during the Defect Liability Period etc. Accordingly the item is included in the respective schedules and cost for the same also has been considered. Conclusion: - After necessary re-working, the complete works, as per the requirements and most modern trend of technology adaptation. Though the cost has been increased, but the complete system shall be integrated to suit all present and near future requirements. All the estimations of rates has been done, based on DSR Pune CPWD index and present market rates, the rate considered in the schedules are found to be reasonable and as per the standard engineering practice. The complete item wise detailed estimates and Detailed Project Report for the balance work of C-DAC, PUNE is being forwarded here with, for the consideration and approval of the competent authority. For Hindustan Steel Works Construction Limited. A.K. VERMA (General Manager Western Region) 87 88 ARCHITECTS IMPRESSION 89 90 91 92 93 94 95 96 97 98