21, rue d'Artois, F-75008 Paris http://www.cigre.org A3-302 Session 2004 © CIGRÉ CONSEQUENCES ON THE VOLTAGE STRESSES IMPOSED ON STEP-UP TRANSFORMERS DUE TO THE USE OF GENERATOR CIRCUIT-BREAKERS DIETER BRAUN ABB SWITZERLAND LTD. (Switzerland) 1. GEORG S. KOEPPL KOEPPL POWER EXPERTS (Switzerland) INTRODUCTION Today the use of generator circuit-breakers mounted between the generator and the low-voltage terminals of the step-up transformer is widespread because this offers many advantages when compared to the unit connection such as simplified operational procedures and better protection against the effects of faults [1]. One of the major reasons for introducing generator switchgear into a power station is the improved protection it provides both for the generator and the step-up transformer against damage due to fault currents, whether they arise from short-circuit, short-time unbalanced load or out-of-phase conditions. Specifically, the rapid and selective clearance of all kind of faults rendered possible by the use of a generator circuit-breaker helps to avoid expensive secondary damage and the consequently long down times for repair. The insertion of a switching device in the connection between the generator and the step-up transformer however exerts an influence on the type and magnitude of overvoltages that will occur. It therefore raises the question of the possibility of overvoltages being generated by the generator circuitbreaker itself during switching operations and by its sole presence while being in the open state. A large number of papers has been published which deal with the voltage stresses imposed on the high-voltage terminals of step-up transformers. These voltage stresses comprise e.g. lightning surges, very fast transients caused by the operation of disconnectors, energising transients and overvoltages due to the switching of transformer magnetising currents. There are also publications, which deal with overvoltages appearing at the terminals of the generator and other equipment connected to the generator busbar. This paper specifically examines the voltage stresses occurring on the low-voltage side of the step-up transformer in power stations equipped with generator circuit-breakers. It differentiates between - Temporary overvoltages Switching overvoltages Transient overvoltages transferred through the step-up transformer In most power stations the step-up transformers are protected by surge arresters fitted at or close to their high-voltage terminals. These surge arresters may not provide in all cases a sufficient overvoltage protection for the equipment on the low-voltage side and additional measures must be taken to protect the generator busbar and the equipment connected to it, such as the generator, the step-up transformer ___________________________________________________________________________ Dieter.Braun@ch.abb.com (low-voltage winding), the unit transformer(s), the excitation transformer, the voltage transformers, the current transformers and the generator circuit-breaker. In the present paper recommendations for an adequate overvoltage protection of this equipment are given. 2. SURVEY OF THE CONSEQUENCES OF THE USE OF GENERATOR CIRCUITBREAKERS IN POWER STATIONS The consequences of the use of generator circuit-breakers on the voltage stresses in power stations are explained based on the circumstances prevailing in thermal power stations. For other types of power stations similar considerations apply. A simplified single line diagram of a thermal power station is shown in Figure 1. High-Voltage Circuit-Breaker High-Voltage Circuit-Breaker Step-up Transformer Step-up Transformer ∆ Generator Circuit-Breaker ∆ Unit Transformer Generator ∆ ∆ Shut-down Transformer Unit Transformer Generator Unit Auxiliaries a) Station Transformer Unit Auxiliaries b) Rapid Changeover Equipment Figure 1: Single Line Diagram of a Thermal Power Station a) Layout with Generator Circuit-Breaker b) Layout without Generator Circuit-Breaker (Unit Connection) In a power station equipped with a generator circuit-breaker (Figure 1a)) the generator is switched on and off by means of this circuit-breaker. The unit auxiliaries are supplied at all times from the unit transformer, i.e. also during the starting-up and shutting-down of the unit. The station transformer can therefore either be completely omitted or rated as an emergency shut-down transformer. The circuitbreaker on the high-voltage side of the step-up transformer is normally operated only in case of longer standstill periods of the unit. In a power station without a generator circuit-breaker (Figure 1b)) the generator is switched on and off by means of the circuit-breaker on the high-voltage side of the step-up transformer. It is a characteristic of this layout that the unit auxiliaries cannot be supplied from the unit transformer unless the generator is synchronised to the high-voltage system. During the starting-up and shutting-down periods the unit auxiliaries must therefore be transferred to an alternative source. Usually this is a station transformer that is connected directly to the high-voltage system. A comprehensive survey of the consequences of the use of a layout with a generator circuit-breaker in comparison to a layout without a generator circuit-breaker (unit connection) is given in Tables 1, 2 and 3. Thereby all relevant technical aspects are considered. Specifically, an indication of the voltage stresses arsing from the various switching operations (transient recovery voltages, switching overvoltages) and fault conditions (temporary, switching and transient overvoltages) is given. Table 1 covers normal and exceptional operating conditions, Table 2 covers fault conditions and Table 3 covers conditions involving transient overvoltages. From Table 2 particularly the advantages of the use of a generator circuit-breaker with respect to the protection of power plant equipment from the effects of fault currents become evident. Some specific aspects of the use of generator circuit-breakers are dealt with in more detail in Sections 3 (temporary overvoltages), 4 (switching overvoltages) and 5 (transient overvoltages). Table 1: Consequences of the Use of a Generator Circuit-Breaker – Normal and Exceptional Operating Conditions Duty Connection with Generator Circuit-Breaker Generator Circuit-Breaker High-Voltage Circuit-Breaker Unit Connection High-Voltage Circuit-Breaker Normal operating conditions 1.1 Energising unloaded stepup transformer on HV-side Not applicable 1.2 Synchronising unit with HV-system Relatively low voltage stresses (compared to the BIL) imposed on circuitbreaker before closing 1.3 Taking unit out of service Circuit-breaker interrupts small current (few percent of the rated current of the generator), TRV ≤ 1.0 pu 3) Not applicable 1.4 De-energising unloaded step-up transformer on HVside Exceptional operating conditions 2.1 De-energising unloaded step-up transformer 2.2 Load rejection Circuit-breaker interrupts magnetising current, very small switching overvoltage (≤ 2.0 pu) 3) Temporary overvoltage (≤ 1.4 pu) Circuit-breaker interrupts load current, TRV ≤ 1.9 pu 3) Flow of inrush current 1) Possibly high-frequency oscillations at HV-terminals of step-up transformer (if circuitbreaker is located in some distance from power station) Possibly initiation of ferroresonance on LV-side of step-up transformer 2) Not applicable Not applicable Circuit-breaker interrupts magnetising current, small switching overvoltage (≤ 2.5 pu) Not applicable Relatively high voltage stresses (compared to the BIL) imposed on circuit-breaker before closing (especially critical for outdoor circuit-breakers in presence of high pollution) Circuit-breaker interrupts small current (few percent of the rated current of the generator), TRV ≤ 1.0 pu Not applicable See 1.4 Not applicable Not applicable Temporary overvoltage (≤ 1.4 pu) Circuit-breaker interrupts load current, TRV ≤ 1.7 pu Notes: 1 ) The magnitude of the inrush current can be reduced by the use of synchronised closing [2] 2 ) Refer to Section 3.1 regarding the prevention of ferroresonance on the LV-side of the step-up transformer 3 ) Applies to SF6 generator circuit-breakers only, air-blast and vacuum generator circuit-breakers may produce higher overvoltages and need special consideration Table 2: Consequences of the Use of a Generator Circuit-Breaker – Fault Conditions Duty Connection with Generator Circuit-Breaker Generator Circuit-Breaker High-Voltage Circuit-Breaker Unit Connection High-Voltage Circuit-Breaker Circuit-breaker interrupts system-source short-circuit current, TRV ≤ 2.7 pu De-excitation of generator necessary to remove generator-source short-circuit current Circuit-breaker interrupts generator-source short-circuit current (short-circuit current may exhibit delayed current zeros), TRV ≤ 2.7 pu No action Circuit-breaker interrupts system-source short-circuit current, TRV ≤ 2.4 pu De-excitation of generator necessary to remove generatorsource short-circuit current Circuit-breaker interrupts system-source short-circuit current, TRV ≤ 2.4 pu Circuit-breaker interrupts system-source short-circuit current, TRV ≤ 2.4 pu De-excitation of generator necessary to remove generatorsource short-circuit current Fault conditions 3.1 Short-circuit between generator and generator circuit-breaker 3.2 Short-circuit between generator circuit-breaker and high-voltage circuitbreaker Duty Connection with Generator Circuit-Breaker Generator Circuit-Breaker High-Voltage Circuit-Breaker Unit Connection High-Voltage Circuit-Breaker Circuit-breaker interrupts generator-source short-circuit current (short-circuit current may exhibit delayed current zeros), TRV ≤ 2.4 pu No back-up available Opening of line-side highvoltage circuit-breakers necessary to remove systemsource short-circuit current (loss of HV-busbar) Voltage in healthy phases on LV-side of step-up transformer rises to 1.8 pu Circuit-breaker interrupts load current, TRV ≤ 1.2 pu De-excitation of generator necessary to remove fault Not applicable Fault conditions (continued) 3.3 Short-circuit between highvoltage circuit-breaker and line-side high-voltage circuit-breakers Back-up for high-voltage circuit-breaker Circuit-breaker interrupts generator-source short-circuit current (short-circuit current may exhibit delayed current zeros), TRV ≤ 2.4 pu Opening of line-side highvoltage circuit-breakers necessary to remove systemsource short-circuit current (loss of HV-busbar) 3.4 Single-phase-to-earth fault between generator and generator circuit-breaker, generator circuit-breaker closed (or no generator circuit-breaker present) Voltage in healthy phases rises to 1.8 pu Circuit-breaker interrupts load current, TRV ≤ 2.4 pu 1) De-excitation of generator necessary to remove fault No action 3.5 Single-phase-to-earth fault between generator and generator circuit-breaker, generator circuit-breaker open 3.6 Single-phase-to-earth fault between generator circuitbreaker and LV-winding of step-up transformer, generator circuit-breaker closed (or no generator circuit-breaker present) 3.7 Single-phase-to-earth fault between generator circuitbreaker and LV-winding of step-up transformer, generator circuit-breaker open 3.8 Synchronising under out-ofphase conditions (up to an out-of-phase angle of 180°) Voltage in healthy phases rises to 1.8 pu De-excitation of generator necessary to remove fault No action Voltage in healthy phases rises to 1.8 pu Circuit-breaker interrupts magnetising current *), very small switching overvoltage (≤ 2.0 pu) 1) Circuit-breaker interrupts load current *), TRV ≤ 1.2 pu Voltage in healthy phases rises to 1.8 pu, possibly intermittent earth fault conditions Possibly initiation of ferroresonance 2) Circuit-breaker interrupts outof-phase current (fault current may exhibit delayed current zeros 3)), TRV ≤ 4.8 pu *) *) assuming that the HV-circuitbreaker interrupts the current before the generator circuitbreaker Circuit-breaker interrupts small load current, TRV ≤ 1.2 pu Not applicable *) across contacts of circuitbreaker only 3.9 Stuck-pole condition (during load current switching) Possibly high temporary overvoltages (≤ 3.0 pu) 4) De-excitation of generator necessary to remove fault condition Circuit-breaker interrupts load current, TRV ≤ 1.2 pu 3.10 Circuit-breaker failure condition De-excitation of generator necessary to remove fault condition Circuit-breaker interrupts load current or short-circuit current, TRV ≤ 2.4 pu Voltage in healthy phases on LV-side of step-up transformer rises to 1.8 pu Circuit-breaker interrupts load current, TRV ≤ 1.2 pu De-excitation of generator necessary to remove fault Not applicable Possibly extremely high saturation of step-up transformer, may lead to transformer failure Circuit-breaker interrupts out-of phase current (critical case for high-voltage circuit-breaker due to delayed current zeros 3)), TRV ≤ 4.8 pu *) Possibly small temporary overvoltages (≤ 1.3 pu) Opening of line-side highvoltage circuit-breakers and deexcitation of generator necessary to remove fault condition (loss of HV-busbar) Opening of line-side highvoltage circuit-breakers and deexcitation of generator necessary to remove fault condition (loss of HV-busbar) Notes: 1 ) Applies to SF6 generator circuit-breakers only, air-blast and vacuum generator circuit-breakers may produce higher overvoltages and need special consideration 2 ) Refer to Section 3.1 regarding the prevention of ferroresonance on the LV-side of the step-up transformer 3 ) Refer to [3] 4 ) Refer to Section 3.2 regarding the recognition of a stuck-pole condition 3. TEMPORARY OVERVOLTAGES There are a number of events, which may cause temporary overvoltages of considerable duration at power frequency or at low-order harmonics or sub-harmonics thereof on the low-voltage side of the Table 3: Consequences of the Use of a Generator Circuit-Breaker – Conditions Involving Transient Overvoltages LV-Side of Step-up Transformer Generator Circuit-Breaker Generator Circuit-Breaker Closed (Or No Generator Open Circuit-Breaker Present) HV-Side of Step-up Transformer Lightning overvoltages 4.1 Transient overvoltages due to shielding failures Not applicable Not applicable 4.2 Transient overvoltages due to back-flashes Not applicable Not applicable Not applicable Not applicable Transient overvoltages up to BIL, requires adequate surge protection on HV-side Transient overvoltages up to BIL, requires adequate surge protection on HV-side Very fast transients 5.1 Very fast transients due to high-voltage disconnector operation (only in case of GIS disconnectors) 1) Transient overvoltages ≤ 2.5 pu with extremely high rate of voltage rise, endanger winding insulation of step-up transformer Transferred surges 6.1 Lightning overvoltages Small transient overvoltages Transient overvoltages below Not applicable transferred through step-up (far below BIL) BIL, may require surge transformer protection on LV-side 6.2 Very fast transients due to Negligible transient Transient overvoltages below Not applicable high-voltage disconnector overvoltages (far below BIL) BIL, may require surge operation transferred protection on LV-side through step-up transformer Notes: 1 ) Can possibly be avoided by relocating the switching operations to the low-voltage side of the step-up transformer step-up transformer. Such events comprise load rejections, single-phase-to-earth faults, non-linear oscillations (ferroresonance) and circuit-breaker malfunctioning (stuck-pole condition). In the following the cases of ferroresonance and of a stuck-pole condition are closer looked at. 3.1 Ferroresonance (Relaxation Oscillations) The phenomenon of ferroresonance is caused by the periodic discharging and recharging of the phaseto-earth capacitances through saturable inductances, resulting in a cyclic displacement of the neutral point of the system [4]. Ferroresonance can only occur in a three-phase system with an isolated neutral in which the following conditions prevail: - Inductive voltage transformers connected between phase and earth in all three phases Value of the phase-to-earth capacitances within a certain range Kick-on event to trigger the relaxation oscillations, for example a switching operation (e.g. the energisation of a transformer) or the self-extinction of a single-phase-to-earth fault The overvoltages arising from the most frequent case i.e. that of the second sub-harmonic are relatively small and not dangerous. However the saturation currents in the voltage transformers can cause these to overheat and possibly destroy them. Based on the conditions listed above, relaxation oscillations can only occur on the low-voltage side of the step-up transformer when the generator circuit-breaker is open, because the part of the system comprising the low-voltage winding of the stepup transformer and the high-voltage winding of the unit transformer normally becomes a system with an isolated neutral under these circumstances. No relaxation oscillations can occur on the generator side of the open generator circuit-breaker or when the generator circuit-breaker is closed. Figure 2 shows the simulation of a case of ferroresonance, which is triggered by the energisation of the step-up transformer from the high-voltage side. A second sub-harmonic voltage develops across the open delta winding of the voltage transformer (Figure 2a)). With the fitting of a damping inductance device or a suitably dimensioned damping resistor across the open delta winding of the voltage transformer the relaxation oscillations are quickly damped out, as shown in Figure 2b) [5]. a) Figure 2: 3.2 b) Voltage Across Open Delta Winding of Transformer Side Voltage Transformer During Ferroresonance Condition a) Without Damping Device b) With Damping Inductance Device Fitted Across Open Delta Winding Overvoltages Due to Stuck-Pole Conditions Although being an extremely rare incident, the possibility of a malfunctioning of a circuit-breaker, in that one phase fails to close or open, does exist. The use of a common operating mechanism for all three phases reduces but cannot totally eliminate the possibility of such a failure. Figure 3 shows the results of a simulation of a load rejection at 100% load combined with stuck-pole condition in one phase of the generator circuit-breaker. After approximately 0.5 seconds a phase opposition condition is reached and the phase-to-earth voltages at the low-voltage terminals of the step-up transformer approach 3.0 pu in two phases. At the same time the voltage across the open a) Figure 3: b) Simulation of a Load Rejection at 100 % Load with a Stuck Pole in Phase R a) Phase-to-Earth Voltage (Phase T) at Generator Terminals b) Phase-to-Earth Voltage (Phase T) at Low-Voltage Terminals of Step-up Transformer contacts of the circuit-breaker rises to approximately 3.8 pu. In practice these values will not be attained due to the action of the voltage regulator. Further, if a stuck-pole condition occurs when the loading of the generator is low then the time to reach the maximum voltage is much longer. An even more critical condition can arise if a single-phase-to-earth fault develops in one of the phases where the generator circuit-breaker has opened. Surge arresters connected to the generator busbar will operate under such circumstances and could become thermally overloaded. Such a fault involves the risk of equipment being damaged and is to be avoided. A simple measure to recognise a stuck-pole condition that can easily be implemented into the generator protection system is described in [5]. 4. SWITCHING OVERVOLTAGES Switching overvoltages can arise during the switching of an unloaded step-up transformer, the switching of load currents, the switching of fault currents and also during the initiation of singlephase-to earth faults. In the following the cases of the switching transformer magnetising currents and of the switching of load currents are dealt with. 4.1 Overvoltages Following the Interruption of Transformer Magnetising Currents Under normal operating conditions the unloaded step-up transformer is de-energised via the highvoltage circuit-breaker and it is only under exceptional circumstances that a generator circuit-breaker is required to interrupt a transformer magnetizing current. Experience shows that SF6 circuit-breakers when performing this duty generate negligible overvoltages [6]. Site tests carried out with a SF6 generator circuit-breaker confirm this statement. During 15 interruptions of the magnetising current of a 240 MVA step-up transformer the overvoltage factor did not exceed 1.0 pu (Figure 4). Figure 4: 4.2 Oscillogram of the Interruption of the Magnetising Current of a 242/13.8 kV 240 MVA Step-up Transformer with a SF6 Generator Circuit-Breaker in a Hydro Power Station Overvoltages Following the Interruption of Load Currents Independent of the actual power factor, the transient recovery voltage resulting from the interruption of a load current in a power station is identical to that arising in a highly inductive circuit [7]. It is well known that vacuum circuit-breakers can initiate multiple reignitions in such circuits. Depending on the system parameters and the characteristics of the switch, a vacuum circuit-breaker may therefore give rise to multiple reignitions when interrupting the load current of a generator [8]. Although the probability of the initiation of this phenomenon is low it cannot be ignored due to high phase-to-earth voltages associated with it. The use of a vacuum circuit-breaker as a generator circuit-breaker therefore requires an additional and carefully designed overvoltage protection scheme to protect both the generator and the step-up transformer. SF6 generator circuit-breakers on the other hand do not give rise to this phenomenon. 5. TRANSIENT OVERVOLTAGES TRANSFERRED THROUGH THE STEP-UP TRANSFORMER Transient overvoltages hitting the high-voltage terminals of a step-up transformer are transferred both capacitively and inductively to the low-voltage side [5]. The initial portion of voltage surges with very steep wave fronts and high amplitudes is thereby transferred via capacitive coupling. During the time when the generator circuit-breaker is open the large phase-to-earth capacitance of the generator stator winding is removed from the capacitor divider formed by the capacitance between the high-voltage and low-voltage windings of the step-up transformer and the phase-to-earth capacitances on the lowvoltage side. The highest transferred surges will therefore appear under these circumstances. 6. RECOMMENDATIONS FOR OVERVOLTAGE PROTECTION From Tables 1 and 2 follows that the voltage stresses which are generated by SF6 generator circuitbreakers during switching operations (transient recovery voltages, switching overvoltages) remain far below the insulation level of the equipment connected to the generator busbar and therefore are of no concern. Air-blast and vacuum generator circuit-breakers may produce higher overvoltages and need special considerations. A switching device in the connection between the generator and the step-up transformer while being in the open state exerts a negative influence on the amplitude and steepness of transient overvoltages which are transferred from the high-voltage system through the step-up transformer to the low-voltage side. To mitigate this effect the connection of surge capacitors with a capacitance of at least 100 nF to the low-voltage side of the step-up transformer is recommended. The decision whether surge arresters should also be fitted can in principle be made as the case arises. Because surge arresters are low cost elements they are normally included in the overvoltage protection scheme without any further investigations. It is however important that both the surge capacitors and the surge arresters are connected to the generator busbar between the low-voltage terminals of the step-up transformer and the generator circuit-breaker so that they remain effective when the circuit-breaker is open. In power stations with generator circuit-breakers the occurrence of ferroresonance has to be prevented by selecting properly rated voltage transformers and fitting a damping inductance device or a suitably dimensioned damping resistor across the open delta winding of the voltage transformers on the transformer side of the generator circuit-breaker. Finally, it is also recommendable to use an arrangement of protective equipment that recognises a stuck-pole condition. 7. CONCLUSIONS The use of generator circuit-breakers offers many advantages when compared to the unit connection such as simplified operational procedures and better protection against the effects of faults. But the insertion of a switching device in the connection between the generator and the step-up transformer obviously also exerts an influence on the type and magnitude of overvoltages that will occur. By introducing the described measures the advantages of the use of a generator circuit-breaker can be fully exploited. 8. BIBLIOGRAPHY [l] Braun, D.; Guerig, A: Life Management for Generator Circuit-Breakers. CIGRE 1994 Session, Report 13-204. [2] Braun, D.; Koeppl, G.; Azuaje, C.J.; Borges, F.: Inrush Currents of a Large Step-up Transformer and Means for their Reduction. International Conference on Power System Transients, Rio de Janeiro, 2001. [3] Canay, I.M.; Braun, D.; Koeppl, G.S.: Delayed Current Zeros Due to Out-of-Phase Synchronizing. IEEE Transactions on Energy Conversion, 13(1998)2, pp. 124-132. [4] Bergmann, C.: Grundlegende Untersuchungen über Kippschwingungen in Drehstromnetzen. ETZ-A 88(1967)12, pp. 292-298. [5] Sanders, M.; Koeppl, G.; Kreuzer, J.: Insulation Co-ordination Aspects for Power Stations with Generator Circuit-Breakers. IEEE Transactions on Power Delivery, 10(1995)3, pp. 1385-1393. [6] CIGRE WG of Study Committee 13: Interruption of Small Inductive Currents, Chapter 5: Switching of Unloaded Transformers, Part 1: Basic Theory and Single Phase Transformer lnterruption without Reignitions. Electra (1990)133, pp. 87-107. [7] Vadaszi, J.: Load Current Interruption with Generator Circuit-Breakers and Generator Load Switches. Brown Boveri Review 68(1981)8/9, pp. 316-325. [8] Glinkowski, M.T.; Gutierrez, M.R.; Braun, D.: Voltage Escalation and Reignition Behavior of Vacuum Generator Circuit-Breakers During Load Shedding. IEEE Transactions on Power Delivery, 12(1997)1, pp. 219-226.