NRS 033:1996 - Eskom Board

advertisement

UDC 621.315.668.1

ICS 29.240

ISBN 0-626-10996-5

NRS 033:1996

First Edition

Rationalized User Specification

ELECTRICITY DISTRIBUTION -

Guidelines for the application design, planning and construction of medium voltage overhead power lines up to and including 22 kV, using wooden pole structures and bare conductors

For applications in the Electricity Supply Industry

NRS 033:1996 1

CONTENTS

Page

Foreword................................................................................................................................2

Introduction ............................................................................................................................4

2

3

Key words .............................................................................................................................4

1 Scope...........................................................................................................................

5

4

Normative references...................................................................................................5

Definitions ....................................................................................................................6

Application design guides.............................................................................................7

4.1

Preferred structures, conductors and components.................................................7

4.2

Wind loading and loading levels ...........................................................................8

4.3

Minimum factors of safety ....................................................................................8

4.4

Use of vibration dampers .....................................................................................9

4.5

Minimum clearances ............................................................................................9

4.6

Basic insulation level, earthing and surge protection ............................................9

4.7

Recommended crossing practice ..........................................................................10

4.8

Support structure function .....................................................................................10

5

6

Planning guidelines .....................................................................................................14

5.1

The power distribution system planning phase .....................................................14

5.2

The pre-construction planning phase ....................................................................14

Construction guidelines ...............................................................................................17

6.1

Delivery and handling ..........................................................................................17

6.2

Assembly or dressing ...........................................................................................17

6.3

Excavation ...........................................................................................................18

6.4

Erection, backfilling and stay installation ...............................................................18

6.5

Conductor erection ...............................................................................................21

6.6

Transformer and switchgear erection ...................................................................23

6.7

Route reinstatement and clearing .........................................................................23

6.8

Labelling of structures ..........................................................................................23

6.9

Inspection ............................................................................................................23

Figures

1 Pole pike .....................................................................................................................20

A.1

Formed armoured road crossing twin tie for vertically mounted pin or post insulator ....25

A.2

Formed arcing horn for horizontally mounted long rod insulator ...................................25

A.3

Formed arcing horn for horizontally mounted disc insulator .........................................25

A.4

Crossing with strain structures on both sides ...............................................................26

A.5

Crossing with an intermediate structure on one side and a strain structure on the other side ..............................................................................................................27

A.6

Crossing with intermediate structure on both sides ......................................................27

2 NRS 033:1996

CONTENTS

(continued)

Page

A

B

C

D

C.1

Intermediate wood pole structure, vertical no deviation ...............................................42

C.2

Intermediate wood pole structure, vertical, small angle deviation ................................43

C.3

Road crossing intermediate wood pole structure, vertical, no deviation .......................44

C.4

Suspension wooden pole structure, vertical, medium angle deviation ..........................45

C.5

Strain wooden pole structure, vertical 30° to 90° deviation ..........................................46

C.6

Strain wooden pole structure, delta, up to 30° deviation ...............................................48

C.7

H-pole strain wooden pole structure, horizontal, 60° to 90° deviation ...........................48

C.8

Long span H-pole suspension wooden pole structure, delta, no deviation ....................49

C.9

Long span H-pole strain wooden pole structure, delta, no deviation .............................50

C.10

Long span triple-pole strain wooden pole structure, delta, no deviation ........................51

C.11

Terminal wooden pole structure, vertical .....................................................................52

C.12

Terminal wooden pole structure, delta .........................................................................53

C.13

Tee-off wooden pole structure, vertical intermediate to vertical tee-off, no deviation ...54

C.14

Tee-off wooden pole structure, vertical intermediate to delta tee-off, no deviation .......55

C.15

Recloser or sectionalizer strain wooden pole structure, horizontal, no deviation ..........56

C.16

In-line isolating strain wooden pole structure, delta, no deviation .................................57

C.17

Pole mounted CSP transformer, mass <760 kg, terminal wooden pole structure, delta 58

C.18

Pole mounted transformer, mass <760 kg, intermediate wooden pole structure, vertical, no deviation ...................................................................................................59

C.19

Platform mounted transformer, 760 kg <mass <2000 kg, terminal wooden pole structure, horizontal .....................................................................................................60

C.20

Platform mounted transformer, 760 kg <mass <2 000 kg, terminal wood pole structure, vertical ........................................................................................................................

61

C.21

Delta to vertical phase configuration intermediate wooden pole structures ..................62

C.22

Pole foundation detail ..................................................................................................63

C.23

Stay anchor assembly installation detail ......................................................................64

C.24

Rock anchor assembly installation detail .....................................................................65

C.25

Stay assembly detail ....................................................................................................66

C.26

Overhead (flying) stay arrangement detail ...................................................................67

C.27

Conductor tie installation detail on pin or post insulator ...............................................68

D.1

Schematic lay-out Wye electrification extension ..........................................................71

D.2

Wye village electrification extension spanning plan .....................................................72

D.3

Wye village electrification extension construction programme .....................................75

Annexes

Design of crossings of proclaimed roads, railway lines, tramways and important communication lines with a power lines .......................................................24

Procedure for positioning of structures on a surveyed route plan .................................29

Description and illustrations of overhead power line support standards and related features ............................................................................................................40

Project example ..........................................................................................................69

ISBN 0-626-10996-5

NRS 033:1996 3

Foreword

These guidelines have been prepared on behalf of the Electricity Suppliers Liaison Committee (ESLC) and approved by it for use by supply authorities and other interested parties.

These guidelines have been prepared by a Working Group comprising the following members:

A J Poulton (Chairman)

J W J Dixon

R Dhrochand

A D du Plessis

J C Fivaz

G R Marshall

M D McIntosh

P A Johnson

D M Michie

C N Ravera

R G Stephen

L J Verster

Technology Consultancy Services (Pty) Ltd.

Technology Consultancy Services (Pty) Ltd.

Durban Electricity

Department of Manpower

Bloemfontein Electricity Department

Merz & McLellan (South Africa)

Johannesburg Electricity Department

NRS Project (Project Leader)

Port Elizabeth Electricity Department

Eskom (Transmission Engineering)

Eskom (Transmission Engineering)

Pretoria Electricity Department

The Working Group was appointed by the ESLC which, at the time of approval, comprised the following members:

F H D Conradie

B F Berwyn-Taylor

A J Claasen

P Crowdy

R W Curtis

J A Ehrich

A H L Fortmann

R B Gwilt

D F Hunt

I P Kruger

J G Malan

J Maroga

A Lock

A J van der Merwe

H R Whitehead

National PTM&C Manager, Eskom

City Electrical Engineer, Cape Town, AMEU

Manager, Electrical Engineering Standards, SABS

Distribution Planning Manager, Eskom

JCI, for Chamber of Mines of South Africa

City Electrical Engineer, Pretoria, AMEU

City Electrical Engineer, Boksburg, AMEU

City Electrical Engineer, Port Elizabeth, AMEU

Corporate Technology Standardization Manager, Eskom

Director, Department of Electrical Engineering, SABS

City Electrical Engineer, Kempton Park, AMEU

Distribution Technology Manager, Eskom

Director, Electrical Engineering, Johannesburg Electricity

City Electrical Engineer, Bloemfontein, AMEU

Executive Director, Durban Electricity, AMEU

Annexes A, B and C form an integral part of this guide.

Annexes D and E are for information only.

Recommendations for corrections, additions or deletions should be addressed to the NRS Project

Manager, c/o SABS, Private Bag X191, Pretoria, 001.

Introduction

4 NRS 033:1996

The planning and construction of medium voltage overhead lines are regularly undertaken by electricity suppliers. The ESLC commissioned the compilation of these guidelines in order to facilitate the electricity distribution process, and to promote the standardization of structures and materials used.

Although these guidelines are based on wooden pole structures, concrete poles may be used. However, when concrete poles are used, it is important that insulators of higher lightning impulse withstand voltage also be used, the object being to ensure that an overall basic insulation level (BIL) of 300 kV per structure is maintained.

These guidelines include an example project, complete with tabulated information, standardized structure designs and explanatory comments.

The techniques proposed, and the designs given, are in accordance with the Occupational Health and

Safety Act, 1993 (Act 85 of 1993).

Key words

Guidelines; Overhead power lines ; Electricity distribution.

NRS 033:1996

GUIDELINE

5

Electricity distribution — Guidelines for the application design, planning and construction of medium voltage overhead power lines up to and including 22 kV, using wooden pole structures and bare conductors

For applications in the Electricity Supply Industry

1 Scope

These guidelines are intended for use by an experienced person as defined in the Occupational Health and Safety Act, 1993 (Act 85 of 1993), of Regulation 11 of the General Safety Regulations, for the application design and construction of medium voltage overhead power lines up to and including 22 kV, using wooden pole structures.

Should higher voltage, alternative or more comprehensive designs be required, these should be carried out in accordance with NRS 041.

These guidelines are not intended as a text book for the design of overhead power lines but do provide an example of overhead line design that complies with professionally accepted practices and the OHS

Act 1993, as amended.

2 Normative references

The following standards contain provisions which, through reference in the text, constitute provisions of these guidelines. At the time of publication, the editions indicated were valid. All standards are subject to revision and parties to purchase agreements base on these guidelines are encouraged to investigate the possibility of applying the most recent edition of the standards listed below. Information on currently valid national and international standards can be obtained from the South African Bureau of Standards.

BS 3242:1970, Specification for aluminium alloy stranded conductors for overhead power transmission.

IEC 433:1980, Characteristics of string insulator units of the long rod type.

IEC 1089:1991, Round wire concentric lay overhead electrical stranded conductors.

NRS 039:1995, Guideline for the application of gapless metal oxide surge arresters in distribution systems .

SABS 182-3:1975, Aluminium Conductors, steel reinforced.

SABS 753, Pine poles, cross arms and spacers for power distribution, telephone systems and street lighting.

SABS 754:1994, Eucalyptus poles, cross arms and spacers for power distribution and telephone systems.

SABS IEC 305:1978, Characteristics of string insulator units of the cap and pin type.

SABS IEC 383-1:1993, Insulators for overhead lines with a nominal voltage above 1000 V — Part 1:

Ceramic or glass insulator units for a.c. systems — Definitions, test methods and acceptance criteria.

SABS IEC 720:1981, Characteristics of line post insulators.

6

3 Definitions

For the purposes of these guidelines, the following definitions apply:

NRS 033:1996

3.1 basic insulation level (BIL):

The test voltage, under specified conditions, that the insulation of a device is designed to withstand.

3.2

completely self-protected (CSP) transformer: A transformer that is designed to be self-protected against overloads, short-circuits and overheating.

3.3

dressing of poles: The attachment of hardware and accessories to poles.

3.4

experienced person: A full-time employee, designated (in writing) by the employer, charged with the duty of supervising the construction of overhead lines, and who has had at least two years' experience in the type of construction to be supervised.

NOTE — An experienced person should be: a) familiar with the OHS Act, 1993, and its implications; b) trained in the construction of overhead lines; and c) aware of the dangers associated with the construction of overhead lines.

3.5

formed tie: A custom-designed wire strand, set of wire strands or plastic strand that has been factory formed to suit a particular insulator neck size, or conductor or stay wire type (or both).

3.6

ground span: That horizontal distance between supporting structures, that on level ground with the conductor at maximum sag, enables the statutory clearance of the conductor above the ground to be achieved.

NOTE — The ground span is dependent on the structure height, the type of conductor, the temperature, and the tension limits within which the conductor is designed to operate.

3.7

lightning impulse withstand voltage: The lightning impulse voltage that an insulator, under prescribed conditions of test, will withstand when the insulator is dry.

3.8

mass span: Those portions of the span lengths on either side of the structure that impose a vertical load on the structure.

NOTE — The maximum mass span that can be supported by the structure is dependent on the strength of the structure and the strength of the supporting hardware, including insulators. The mass span is calculated using the mass per unit length of the conductor supported by the structure.

3.9

overturn span: The maximum span length capability of the structure foundation under maximum wind load conditions, with the statutory foundation factor of safety (currently 2).

3.10

pole pike: A device that is used to assist the manual erection of poles. The top end usually consists of an aluminium tube of diameter approximately 75 mm, with the lower end being flat with a pair of handles.

NOTE — For wooden pole erection, a single pike or a pair of pikes secures the pole during erection and backfill operations.

3.11

skid board: Panels that have a smooth, clean upper surface that is placed between the butt of the pole and the face of the excavation, to facilitate the erection of the pole.

NRS 033:1996 7

3.12

structure: A dressed and erected single pole or multipole assembly, including cross-arms and hardware.

3.13

templating: The activity of placing or positioning the structure on the ground profile, drawing or map.

3.14

wind span: The sum of those portions of span lengths on either side of the structure that, when subjected to wind, impose a horizontal load on the structure.

NOTE — The maximum wind span is dependent upon the ability of the structure and its foundation to resist the overturning moment caused by the action of the wind.

4 Application design guidelines

4.1 Preferred structures, conductors and components

4.1.1 General

The structures, conductor and components referred to in these guidelines are among those most commonly used. In the interests of standardization, users of these guidelines are encouraged to select the required components from these preferred items, whenever practicable.

Where it is vital to use conductor sizes other than those listed in tables B.3, B.4, B.5, B.6, B.7 and B.8 of annex B, the conductor manufacturers should be consulted for the relevant sag/tension data.

Except where allowed for in the scope of this guide, the structures included in annex C should be used for all lines up to and including 22 kV. The insulation levels should correspond to the highest system phaseto-phase and phase-to-earth voltages.

Where it is foreseen that a higher voltage level will be used in the future, it is good practice:

— to insulate the strain structures to at least the proposed higher voltage level, and

— to allow adequate ground clearance for the proposed higher voltage level.

In particular, it is recommended that 11 kV insulation be used for 6,6 kV lines.

Single-phase two-wire lines should use the three-phase structures, minus the bottom insulator on staggered vertical configuration structures, and minus the centre insulator on horizontal and delta configuration structures.

4.1.2 Recommended insulator characteristics

Insulators should comply with the relevant of the following standards: a) SABS IEC 305 for disc insulators; b) SABS IEC 383-1 for ceramic or glass insulators; c) SABS IEC 433 for long rod insulators; and d) SABS IEC 720 for line post insulators.

The essential mechanical and electrical characteristics of insulators are given in tables 1, 2 and 3.

NOTE — Where adverse environmental conditions exist, the use of composite insulators that comply with IEC 1109 should be considered.

8

Table 1 — Mechanical characteristics of insulators

NRS 033:1996

1 2 3

Insulator type and application

4

Pin or post, intermediate

Pin or post road crossing, small deviation

Long rod or disc, intermediate

Minimum mechanical failing load, kN (see 4.1.2)

Long rod or disc, strain

4

(cantilever)

10

(cantilever)

1

or to suit conductor tension.

40

(tensile)

40

1

(tensile)

Table 2 — Electrical characteristics of insulators

1

Nominal r.m.s. system voltage

11

22

2

Rated peak lightning impulse withstand voltage

95

150 min.

3

Rated wet power frequency r.m.s.

withstand voltage

28

50

The standard atmospheric pollution level in South Africa should be taken as medium, and the minimum specific creepage distance between phase and earth should be 20 mm per kilovolt of the highest system phase-to-phase voltage, U m

. Where other conditions prevail, the creepage distance should be as specified in table 3.

Table 3  Creepage distances between phase and earth

1

Pollution level

Light

Medium

Heavy

Very heavy

2

Minimum specific creepage distance between phase and earth mm per kV of U m

16

20

25

31

4.2 Wind loading and loading levels

Structures, conductors and components described in these guidelines have been designed to withstand the loads imposed when they are subjected simultaneously to a wind pressure of 700 Pa and an ambient temperature of − 5 °C.

These figures should be used unless a Professional Engineer has access to local data that indicate designs not covered by this guideline.

4.3 Minimum factors of safety

The minimum factors do safety that should be used are:

— Wooden poles not continuously loaded : 2,7 based on ultimate fibre stress (bending loads)

NRS 033:1996 9

— Wooden poles and cross-arms continuously loaded : 4,5 based on ultimate fibre stress (bending loads) and modules of elasticity (axial loads)

— Conductors, insulators and conductor fittings

— Stay assemblies :

: 2,5 based on type-tested breaking strength

2,5 based on type-tested breaking strength

4.4 Use of vibration dampers

As a general rule, in the case of spans of less than 150 m, vibration dampers will not normally be necessary, provided that at 15 °C, the conductor tension does not exceed 15 % of the ultimate tensile strength (UTS).

However, in the case of spans that cross mountainous country, long valleys or long rivers the use of vibration dampers should be considered.

4.5 Minimum clearances

The minimum clearances, as required by the OHS Act, 1993, for the range of voltages covered by these guidelines are shown in table 4.

Table 4 — Minimum clearances for bare conductors in accordance with regulation 15 of the Electrical Machinery Regulations

1 2 3 4 5 6

Maximum r.m.s.

phase-to-phase voltage for which insulation is designed

Minimum safety clearance

Above ground outside townships

Above ground in townships

Above roads in townships, proclaimed roads outside townships, railways and tramways kV

1,1 or less

7,2

12

24

36

48

72

100

145

245

300

362

420

800 m

1,00

1,45

1,85

2,35

2,90

3,20

5,50

0,15

0,20

0,32

0,43

0,54

0,77 m

4,9

5,0

5,1

5,2

5,3

5,4

5,7

5,9

6,3

6,7

7,2

7,8

8,1

10,4 m

5,5

5,5

5,5

5,5

5,5

5,5

5,7

5,9

6,3

6,7

7,2

7,8

8,1

10,4 m

6,1

6,2

6,3

6,4

6,5

6,6

6,9

7,1

7,5

7,9

8,4

9,0

9,3

11,6

NOTE — The minimum safety clearance is equal to the minimum safe approach clearance.

1,6

2,0

2,4

2,9

3,5

3,8

6,1

0,6

0,7

0,8

0,9

1,0

1,1

1,4

To communication lines, other power lines or between power lines and cradles m

7

To buildings, poles and structures not forming part of power lines m

3,4

3,8

4,2

4,7

5,3

5,6

8,5

3,0

3,0

3,0

3,0

3,0

3,0

3,2

4.6 Basic insulation level, earthing and surge protection

4.6.1

The designs in these guidelines are based on a 300 kV lightning impulse withstand voltage of a wooden pole structure, except for a structure fitted with equipment protected by surge arresters

(see 4.6.4). The insulation level of 300 kV was chosen to obtain the optimum balance between reliability,

10 NRS 033:1996 system performance and damage to wooden poles in areas of medium to high lightning activity

(> 4 flashes/km

2

/year).

4.6.2

Where earth wires are required on a structure, these are shown in the relevant figures in annex C.

4.6.3

Where an earth wire is used on a pole to maintain a BIL of 300 kV at a structure, it is important that it be terminated 500 mm below: a) the hardware that is attached to the mounting point of the lowest insulator in the case of unbonded structures, b) the lowest bonded hardware in the case of bonded structures, c) stay attachment points, and d) equipment not protected by surge arresters, such as line links.

The top of the earth wire should be secured to the pole with a band of metal or similar durable material around the pole, so that a measure of electrical stress relief is provided.

4.6.4

Surge arresters should be provided to protect equipment and structures that have a BIL of less than 300 kV and they should be selected and installed in accordance with NRS 039. In areas subject to marine or high industrial pollution, the insulator mounting hardware and other metal work should be bonded to prevent pole-top fires.

4.6.5

All stays should have stay insulators. The stay insulators should be fitted approximately 1 500 mm from the stay attachment point on the pole.

4.6.6

In order to maintain a BIL of 300 kV on all stayed structures, especially those where stays are attached to steel cross-arms or insulator anchor points, fibreglass rod stay insulators have been used in the designs throughout these guidelines. These insulators should have an ultraviolet resistant fibreglass rod that has a BIL of approximately 300 kV and an ultimate breaking strength (UBS) that exceeds that of the stay wires used, i.e. the UBS of the insulators should be 70 kN for a 7/3,35, 1 100 MPa stay wire and

100 kN for a 7/4,0, 1 100 MPa stay wire.

NOTE — Higher values of UBS have been specified for the stay insulators than for the stay wires, so that the stay wires act as a mechanical weak link if an abnormal strain is applied.

4.6.7

On structures where the 300 kV BIL cannot be maintained, a single conventional porcelain stay insulator should be used in each stay assembly. An example of such a structure is one located in a coastal area, where the metal hardware is bonded, and where surge arresters are installed or earthed equipment is located. Conventional porcelain stay insulators can also be used where it is particularly important that the mechanical integrity of a stay assembly be retaomed.

NOTE — See NRS 022 for the mechanical and electrical requirements of stay assembly components.

4.7 Recommended crossing practice

The design of power line crossings of proclaimed roads, railway lines, tramways and important communication lines is covered in annex A.

4.8 Support structure function

The recommended structure designs are given in annex C. Wooden poles and cross-arms should conform to the requirements of SABS 753 or SABS 754 (as relevant). The type of configuration

(horizontal, delta or vertical) and the type of structure (intermediate, suspension or strain) for the structures that have pole-mounted equipment is only typical. The line design engineer or experienced person should choose the required configuration and the type of structure depending on the local circumstances, for example the availability of pole sizes and the positioning of pole-mounted equipment.

NRS 033:1996 11

The functions of the typical structures are as given in 4.8.1 to 4.8.7.2.

4.8.1 Intermediate wooden pole structure, vertical, no deviation

(see figure C.1)

This intermediate structure should be used where the line extends in a straight line, and where the conductors are continuous. The capabilities of these structures are obtainable from tables B.1 and B.2 in annex B.

4.8.2 Intermediate wooden pole structure, vertical, small angle deviation

(see figure C.2)

This intermediate structure should be used where the line deviates by a small angle. This angle is dependent on the type of conductor used, since different types of conductor will impose different loads on the structure.

4.8.3 Road crossing intermediate wooden pole structure, vertical, no deviation

(see figure

C.3)

This intermediate structure should be used where the line crosses a road without the line’s changing direction.

4.8.4 Suspension wooden pole structure, vertical, medium angle deviation

(see figure C.4)

This structure should be used for line deviations where the structure shown in figure C.2 cannot accommodate the extent of the angle. The reason for the minimum deviation is that the insulators need to be kept away from the pole. If the deviation angle is too small, the conductors could be too close to the pole to satisfy the insulation requirements. The maximum angles are determined by the loads applied to the structure by the conductors.

4.8.5 Strain wooden pole structure, vertical, 30° to 90° deviation

(see figure C.5)

This structure should be used where the angle of deviation is too great for any of the preceding structures. The conductors from each span are separately terminated and strained-off, and interconnecting jumpers are fitted as shown in the diagram.

4.7.6 Strain wooden pole structure, delta, up to 30° deviation

(see figure C.6)

This structure should be used for all strain positions where the line deviation does not exceed 30

°

. These structures should also be used on all rail crossings.

4.8.7 H-pole strain wooden pole structure, horizontal, 60° to 90° deviation

(see figure C.7)

This structure should be used where a line using hare or oak conductor (see table B.1 and table B.2), is required to be angled in the range 60° to 90°.

4.8.8 Long span H-pole suspension wooden pole structure, delta, no deviation

(see figure

C.8)

This structure should be used on spans from 180 m up to 470 m, for conductors in a delta formation, without any deviation.

4.8.9 Long span H-pole strain wooden pole structure, delta, no deviation

(see figure C.9)

12 NRS 033:1996

This structure should be used on spans from 180 m up to 470 m. It is designed to prevent the conductors from touching, causing interruptions in the supply.

4.8.10 Long span triple-pole strain wooden pole structure, delta, no deviation

(see figure

C.10)

This structure illustrates the use of a triple-pole strain structure, which may be used to support long spans of conductor in a delta formation, with no deviation, up to a span of 700 m.

4.8.11 Terminal wooden pole structure, vertical

(see figure C.11)

The structure illustrates the termination of conductors in a vertical configuration.

4.8.12 Terminal wooden pole structure, delta

(see figure C.12)

This structure illustrates the termination of conductors in a delta configuration.

4.8.13 Tee-off wooden pole structure, vertical intermediate to vertical tee-off, no deviation

(see figure C.13)

This structure should be used where it is necessary to provide a vertical tee-off from an existing intermediate vertical structure, where an isolating point is not required for maintenance or for operational purposes.

4.8.14 Tee-off wooden pole structure, vertical intermediate to delta tee-off, no deviation

(see figure C.14)

This structure should be used where it is necessary to provide a delta tee-off from an existing intermediate vertical structure where an isolating point is not required for maintenance or for operational purposes.

4.8.15 Recloser or sectionalizer strain wooden pole structure, horizontal, deviation

(see figure C.15)

This structure should be used to support a recloser or sectionalizer. The structure has bypass facilities, so that the supply can be maintained whilst the recloser or sectionalizer is out of service.

4.8.16 In-line isolating strain wooden pole structure, delta, no deviation

(see figure C.16)

This structure should be used when it is necessary to break the line for maintenance or for operational purposes. A "switch" or link is then placed in the line to provide an isolating point.

4.8.17 Pole-mounted CSP transformer, mass < 760 kg, terminal wooden pole structure, delta

(see figure C.17)

This structure should be used for the support and connection of the CSP type of transformer that contains internal fuses. If this structure is used to support non-CSP transformers, the transformers should be individually protected. The maximum transformer mass that may be used on this structure is 760 kg.

NRS 033:1996 13

4.8.18 Pole-mounted transformer, mass < 760 kg, intermediate wooden pole structure, vertical, no deviation

(see figure C.18)

This structure is the same as illustrated in figure C.17, but for use in the in-line position. The maximum transformer mass that may be used on this structure is 760 kg.

4.8.19 Platform-mounted transformer, 760 kg < mass < 2 000 kg, terminal wooden pole structure, horizontal

(see figure C.19)

This structure should be used to support a transformer of mass exceeding 760 kg but not exceeding

2 000 kg. The structure can either be a terminal structure or an in-line strain structure.

4.8.20 Platform-mounted transformer, 760 kg < mass < 2 000 kg, intermediate wooden pole structure, vertical

(see figure C.20)

This structure should be used to support a transformer and associated equipment of mass exceeding

760 kg but not exceeding 2 000 kg, where the line is in the vertical configuration.

4.8.21 Delta to vertical phase configuration intermediate wooden pole structures

(see figure C.21)

These structures illustrate the correct phase configuration arrangement of phase conductors where a change is required from a delta configuration to a vertical configuration.

4.8.22 Pole foundation detail

(see figure C.22)

The overturning moment of the structures has been designed in accordance with these diagrams. The steel base plate or precast concrete slab, where indicated, is necessary to prevent the pole from punching into the soil, and should be used on all stayed and transformer structures.

4.8.23 Stay anchor assembly installation detail

(see figure C.23)

The stay loadings are designed in strict accordance with this installation diagram. It is imperative that this drawing be adhered to.

4.8.24 Rock anchor assembly installation detail

(see figure C.24)

This illustrates the application of a double-eyed stay rod and a rock anchor for anchoring a stay wire assembly.

4.8.25 Stay assembly detail

(see figure C.25)

This stay assembly should be used with the appropriate stay wire of the stay loading tables B.9 and B.10.

Stay insulators should be used on all stays.

4.8.26 Overhead (flying) stay arrangement detail

(see figure C.26)

This illustrates the arrangement of an overhead stay which is used where clearance above a road is required.

4.8.27 Conductor tie installation for pin and post insulators

(see figure C.27)

This illustrates conductor tie installation details for pin and post insulators.

14 NRS 033:1996

5 Planning guidelines

5.1 The power distribution system planning phase

To select the correct system operating voltage and conductor size it is necessary to make an estimate of the load to be served, its type, and the growth in the load likely to be encountered over a period of 10 to

15 years, and to establish the expected distribution distances. A combination of conductor sizes and system operating voltages can be analysed to calculate voltage drops and power losses from which a suitable design can be formulated to comply with the voltage drop requirements and to yield the lower capitalized costs. In this way, the following can be defined: a) the nominal system operating voltage; b) the type of conductor; c) the type of construction; d) the type of system electrical protection;

NOTE — The determination of the capacity of the fuses and surge arresters, and also the auto-recloser protection settings, are beyond the scope of this guideline and are deemed to have been determined.

e) requirements of any affected authorities with regard to, for example, road and rail crossings, civil aviation and telephone cable routes, etc.; f) whether these guidelines are appropriate for the type of line under consideration; and g) whether construction will be executed "in house", or by contractors.

NOTE — The "in-house" mode of construction is adopted in the example in annex D.

5.2 The pre-construction planning phase

5.2.1 Survey

5.2.1.1

The services of a power line surveyor should be used for all lines, except for short lines along simple routes. The surveyor should be provided with the proposed line route marked out on a survey map, showing start, finish, and approximate length of the line. Terrain features, crossings, environmental factors and isolation points should also be indicated.

NOTES

1 In these guidelines, a surveyor means a surveyor experienced in the survey of power lines.

2 The services of a surveyor are assumed in the power line project example described in annex D.

3 The surveyor should also be advised of the type of structures intended to be used (see 4.8 and annex C).

5.2.1.2 Route planning

The survey usually has two purposes: a) to produce a plan showing prominent features in relation to the proposed route, and b) to place planned features on the ground so that they are in the correct position.

NRS 033:1996 15

The line route between the start and end points should be planned, taking into account physical features, existing and planned infrastructure (such as roads, railway lines and townships), natural areas and landowner requirements. No part of the pole structure or stay assembly may be erected within the road reserve without the permission of the relevant provincial or local authority. In areas sensitive to environmental degradation, it is advisable that the services of an environmental consultant be used.

5.2.1.3 Route acquisition

If the power line crosses properties not owned by the electricity supplier, it is necessary to negotiate an agreement of occupation or wayleave for the power line. It is advisable to use a legal document that specifies the rights of the electricity supplier, and the restrictions placed upon the land-owner by the presence of the power line. The document should specify, for example, the building restriction, access along the power line route, compensation for the rights (if any), limits of the electricity supplier and damage compensation due to construction activities. The document should also include any special conditions negotiated with the land-owner. The services of an attorney or registrar of deeds should be secured. It is important to that signature of the contract be finalized before any work is carried out on a property.

5.2.1.4 Approval from holders of other rights

If the power line crosses other services such as telecommunication lines, roads, railway lines, water pipes or any servitudes and mining rights, it is necessary to obtain approval for such a crossing from the holders of these rights. The approval will specify under what conditions the particular service may be crossed, what supervision will be required during construction activities, and how payment, if any, will be effected.

Whenever practicable, joint planning with the providers of other services and other relevant authorities is recommended.

5.2.1.5 Route survey

In any route survey, two processes are required. First of all, the bend points are placed in the positions as planned in 5.2.1. The surveyor ensures that no encroachments, other than those approved under

5.2.1.3 or agreed to by the land owner, occur. Secondly, measurements are then taken along the line between bend points, and the chainage position of topographical features (roads, railway lines, structures, cultivation, streams, high ground, etc.) is recorded. The angles at the bends are also measured. If the ground is undulating, or if there are steep slopes, it is necessary to take vertical measurements so that a ground profile can be produced. As a general rule, it is advisable to produce a ground profile or crosssection for slopes that exceed 5°. The ground profile or cross-section will be required to ensure that specified conductor-to-ground clearances are achieved at the optimal structure spacings. This process is called templating, and requires the specialized knowledge of a competent person.

It is now possible to determine the support structure positions, taking into account the topographical features, distances specified from other services and structures, land-owner requirements and span lengths. The type of structures (angle and support) can also be determined. This process can be done by the surveyor in the field, provided that he has been supplied with all the relevant information.

The surveyor is now in a position to produce a spanning plan, showing all the topographical features, structure positions and structure types, including those for transformers and isolators (see annex B). This plan is then checked and approved by the experienced person who has been appointed as the construction supervisor (see 5.2.4), for use during the construction process.

16 NRS 033:1996

The next step is to peg all the support structure positions on the ground. At the same time, any stay positions are also pegged.

5.2.2 Span length and structure positioning

A procedure to select appropriate span lengths and to determine suitable positions for the location of the structures is given in annex B. The ground profile is provided by the power line surveyor.

After the type of structures and their positions have been selected a structure schedule can be compiled

(see the examples in tables D.1 and D.2 of annex D).

5.2.3 Bill of materials

The bill of materials is compiled from the structure schedules.

The materials required for the construction project can be obtained by any one of the following: a) ordering individual items from recognized suppliers of such items; b) including the supply of materials in the project construction responsibilities; or c) appointing an agent familiar with the market;

At the time of ordering, a decision regarding the delivery destination should have been made, i.e. to a peg, to a store or to a site near the project.

5.2.4 Appointment and duties of the construction supervisor

5.2.4.1

The person responsible for the construction of the project should appoint, in writing, an experienced person as a construction supervisor in terms of regulation 11 of the General Safety

Regulations of the OHS Act., 1993.

5.2.4.2

The construction supervisor's duties will include the following: a) allocation of suitably trained labour to carry out the work; b) ensuring that all safety aspects are addressed; c) inspection of the route to ascertain:

1) the type of terrain, and access to structure positions,

2) any special foundation requirements,

3) the type of ground to be excavated and equipment required, and

4) environmental aspects that could affect construction; d) assigning of equipment and transport (such as cranes for off-loading, 4-wheel drive vehicles), dependent on construction techniques and field conditions; e) optimum use of resources to achieve a quality product; and f) scheduling of all activities, including preparation of a programming sequence, typically using a bar chart or an activity schedule as shown in the project example in figure D.3 of annex D.

5.2.4.3 Scheduling of activities

NRS 033:1996 17

When the activities for the construction phase are being scheduled, at least the following activities need to be considered: a) pegging of all pole and stay positions; b) notification to land-owners of the intended date of construction; c) programmed delivery of materials; d) assembly (see 6.2); e) excavation (see 6.3); f) structure erection (see 6.4); g) conductor erection/regulating (see 6.5); h) transformer and switchgear erection (see 6.6); i) route reinstatement (see 6.7); j) clearing up; and k) commissioning of apparatus.

6 Construction guidelines

6.1 Delivery and handling

6.1.1

The way of laying poles upon delivery is dependent on the methods of excavation, dressing and erection.

6.1.2

Care should be exercised in the loading and off-loading of poles. Poles should not be thrown off the vehicle because this can cause hidden damage to a pole which could lead to its early failure. Cranes or off-loading ramps should be used.

6.1.3

Poles of the correct length and diameter should be delivered to each peg.

6.1.4

If holes are to be excavated manually and the poles erected manually, the pole should be laid out in line with the longitudinal axis of the excavation, with the butt ready to enter the lead into the hole (see figure C.22 of annex C.

6.1.5

If holes are to be excavated mechanically and poles erected by crane, the pole should be laid out sufficiently clear of the peg to allow for machine access, but no further from the peg than necessary.

6.1.6

Insulators, stay assemblies and other components required to dress the structures should be loaded onto a separate vehicle or trailer, for delivery at the same time as the poles, provided that there is no risk of theft.

6.2 Assembly and dressing

NOTE — The equipment required for this activity is relatively simple, consisting of a trestle to support the pole top above ground at a sufficient height to enable drilling and dressing, an auger for drilling poles, pliers, spanners, a hacksaw and a hammer.

6.2.1

Dressing of poles should preceed their erection. Any holes drilled into poles on site should be properly treated by impregnating the holes with the same type of preservative that was used for the pole

(for example, creosote).

The preservative should be applied under pressure.

18 NRS 033:1996

6.2.2

When a pole is being dressed, care should be taken to ensure that the dressed structure presents a good appearance. Aspects such as the earth wire downlead’s being stapled frequently and in a straight vertical line, holes being drilled perpendicularly to the pole axis where required and insulator alignment and separation should be carried out with care.

6.2.3

The stay assembly should be assembled in accordance with figure C.25 of annex C. Stay wire lengths are determined on site. Allowance for sloping ground is made on site, but wastage should be avoided. Where stay wires cannot be made off immediately, the stay wires should be tied to the pole at a position above normal reach ,to prevent injury to persons and livestock.

6.2.4

Road-crossing intermediate structures should be dressed with 10 kN post insulators. All other intermediate structures should be dressed with 4 kN post insulators. Strain structures should be dressed with 40 kN strain insulators.

NOTE — The provision of anti-climbing guards is not normally considered necessary for the structures described in these guidelines. However, where there is the possibility of a structure being climbed unaided, the provision of anti-climbing devices is a statutory requirement. Refer to Regulation 16 of the Electrical Machinery Regulations of the OHS Act, 1993 (Act 85 of 1993).

6.3 Excavation

6.3.1

Excavation should preferably be carried out after the dressed structures are in position and ready for erection, since excavations present a hazard to persons and livestock.

6.3.2

The holes for the poles and stays should be excavated in accordance with figures C.22 and C.23

of annex C.

6.3.3

Cognizance should be taken of Regulation 13 of the General Safety Regulations of the OHS Act,

1993, in respect of the depth of excavation in which a man may work without shoring. The step method of excavation shown in figure C.22 of annex C complies with the OHS Act, 1993.

6.3.4

If for some reason the excavation is to be left open and exposed for a period of time, it should be adequately barricaded to prevent injury to persons and livestock.

6.3.5

It is essential that the excavated soil be separated into top soil and other soil, in order to allow for the reinstatement of the excavation with the top soil in place at ground level.

6.4 Erection, backfilling, and stay installation

CAUTION — Unless excavations are barricaded, this activity should take place immediately after the excavation activity.

6.4.1 Mechanical erection

Erection by crane requires the observance of all safety aspects relating to equipment ratings, equipment stability, and the positioning of workmen.

6.4.2 Manual erection

The equipment needed for the manual erection of poles includes pole pikes (see figure 1), or ladders with reinforced top rungs, or similarly adapted equipment with a special attachment to engage and support the pole during the raising operation.

CAUTION — Under no circumstances should a normal ladder be subjected to the loads imposed by the lifting of poles.

The supervisor should ensure that no support will be released until the load has been taken by another pike or reinforced ladder.

NRS 033:1996 19

Stayed poles should be so erected that, upon completion of the backfill operation, the pole leans away from the stay position by at least a half a pole diameter at the top. This will ensure correct alignment when the stay is made-off correctly.

6.4.4 Backfilling of excavations for poles and stays

An extremely important part of structure erection is the backfilling, and it is essential that this be carried out properly. The backfill material should be introduced into the excavation in small quantities and thoroughly tamped or rammed to ensure maximum compaction and maximum bearing pressure.

A layer of backfill of depth not exceeding 200 mm at a time should be rammed as solidly as possible before the next layer is added. To achieve this objective, typically there should be twice as many workmen ramming as shovelling.

Where the backfill material is such that it will not consolidate (i.e. is non-cohesive), it is necessary to add cement in the ratio of 1 unit of cement to 8 units of soil (a unit could be a shovel full).

The soil and cement should be thoroughly mixed before they are returned to the excavation as backfill. It is preferable that the soil/cement mix be slightly moistened by the addition of a little water to the mixture.

Do not add too much water because the mix will be weakened and will not consolidate when rammed.

The moistened mix should be returned to the excavation in small quantities and thoroughly rammed.

6.4.5 Stay installation

The stay should be installed in accordance with figure C.23 of annex C, and carefully backfilled.

When the stay is installed, the stay wire should be made off in accordance with figure C.25 of annex C.

20

75

All dimensions in millimetres

NRS 033:1996

300 300

Handle

Tension stay

6.5 Conductor erection

Figure 1 — Pole pike

There are three basic activities involved in conductor erection. These are:

NRS 033:1996 a) delivery of conductors; b) running out and stringing of conductors; and

21 c) tensioning and regulating of conductors.

6.5.1 Delivery of conductors

As considerable activity occurs around a drum site, care should be taken in the selection of the site position, to prevents unnecessary damage to valuable land. The area to which conductors are delivered is most important in the case of longer lines.

In the case of short lines, delivery may be combined with the running out of the conductor.

6.5.2 Running out of conductors

CAUTION — Care should be exercised to prevent conductor damage during the running out operation.

6.5.2.1

Continuous stringing of conductors is preferable, but where crossings are necessary, stringing will not be continuous. Road crossings can be included in the normal stringing, since scaffolding can be in place and the local Traffic Authority can be represented at the time of crossing. Rail crossings will probably be carried out as a separate activity, in order to satisfy Spoornet requirements. Valley crossings will involve manually run-out conductors, and will also be separate activities. The structures in both rail and valley crossings will support terminal loading if correctly installed.

6.5.2.2

Where road vehicles cannot travel along the full extent of the line route, the conductor will have to be pulled through by other means, such as a tractor or manpower.

6.5.2.3

To prevent unnecessary land damage, all conductors should be run out together.

6.5.2.4

In the case of road crossings, all goalpost scaffolding should be correctly installed beforehand.

6.5.2.5

All fences should be guarded or protected in order to prevent conductor or fence damage.

6.5.2.6

Specialized equipment is available for conductor stringing, but it is not needed on short lines.

6.5.2.7

It is preferable to use commercially available insulator mounted rollers.

6.5.2.8

Structures that have line deviations and continuous conductors should be equipped with stringing blocks of the correct rating.

6.5.2.9

Ensure that: a) all necessary stays, including temporary stays, are correctly installed, b) all conductor rollers or blocks are on site and are running free, c) the necessary pull-lifts, come-along clamps (at least six of each) and slings are on site and have been examined for safe working condition, and d) vehicle access has been arranged.

6.5.2.10

The preferred method of conductor run-out is achieved by mounting the drum on a vehicle.

This prevents damage to the conductor, caused by dragging it along the ground.

22 NRS 033:1996

6.5.2.11

The end of the conductor is fastened or made-off on the strain or terminal structure at the start of the line.

6.5.2.12

A braking system should be used to prevent the drums from over-running. This system can involve a strong wooden plank applied manually to the rim of the drum, to control the drum’s running speed.

6.5.2.13

The conductor should be pulled off from the top of the drum. The arrows on the drum indicate the rolling direction. When the drum is mounted on a truck or trailer, the vehicle travels until approximately 20 m beyond the first structure. After the conductor has been made-off on this structure, the vehicle then reverses, to allow conductor slack to be pulled back towards the pole. The conductors are placed on conductor rollers and attached to the pole top or to the insulators.

6.5.2.14

When the drum cannot be mounted on a vehicle and if no suitable drum jacks or cradles are available, it is acceptable to dig drum pits for mounting the drums. A drum pit is an excavation of sufficient size to allow a drum to rotate on a spindle that is at ground level. In this method, holes are excavated to suit the size of the drum. Solid planks are placed on the sides of the excavation to support a spindle through the drum. Additional pieces of timber are nailed onto the planks on each side of the spindle, to prevent the spindle from sliding along the planks. The same method of drum braking as with vehicle mounted drums is used.

6.5.2.15

Extreme care should be taken to protect the conductor from rocky ground and other objects that could scrape, or otherwise damage, the conductor surface. This protection can be achieved by the use of timber slats that are lain on the ground over which the conductor is to be pulled.

6.5.2.16

When the tensioning position is reached, the conductor can be placed in stringing blocks of correct rating, ready for sagging or tensioning.

6.5.2.17

When the conductor reaches the point where it is to be tensioned or made-off, it should be pulled well clear of the ground and temporarily made-off into a come-along. If any crossings are involved in the section, it is essential that a back-up come-along also be installed as a precaution against the conductor’s slipping and dropping onto the service or road being crossed.

6.5.3 Regulating/tensioning

Before attempting any regulating or tensioning, first ensure that the tension structures are correctly stayed against the tension. Where necessary, temporary stays will already have been installed. The conductor temperature should then be taken by means of a thermometer inserted into the end of a length of conductor from which the centre strand has been removed to allow the insertion of the thermometer.

The conductor supplier will provide sag or tension tables to suit the particular line, provided that they are in possession of the structure schedule. If this is not the case, advice should be sought from a qualified person. The conductor should be regulated to the relevant tables, using a dynamometer.

When the conductor is correctly regulated, the termination fittings (thimble clevis and formed tie deadends) can be made-off.

6.5.4 Tying of conductor

6.5.4.1

When the conductors have been regulated, it is necessary to attach them firmly to the insulators by means of formed conductor ties (see figure C.3 and figure C.13 of annex C). The conductor should be

NRS 033:1996 23 marked at the centre of the stringing block, and transferred and correctly positioned to the attachment point.

6.5.4.2

Care should be taken to install ties in accordance with the manufacturer’s instructions.

6.5.4.3

The crossing span over a road or over other services should be protected by the use of road crossing twin ties for vertically mounted pin or post insulators, and arcing horns for horizontally mounted strain insulators.

6.5.4.4

All temporary stays should be removed during the tying of conductors.

6.6 Transformer and switchgear erection

To avoid possible damage to equipment from falling objects, in particular damage to bushings, erection of transformers and switchgear should only commence after all overhead work has been completed. The transformers and switchgear should be erected strictly in accordance with drawings and other relevant standards.

6.7 Route reinstatement and clearing

Route reinstatement and clearing are important activities, and should be treated as such. The route should be environmentally intact when these activities are completed. All vehicle tracks and damaged fences, culverts and pipes should be repaired, and no refuse or waste left on site. If any trees have been felled or lopped, the timber should be stacked neatly, or removed in accordance with the land-owner's instructions.

6.8 Labelling of structures

Each individual structure should be uniquely identified. All labels should be permanent and indelible, and of a size that can be read at ground level. Danger labels are not mandatory, but these should be fitted on structures where equipment is mounted below the MV conductors.

6.9 Inspection

Prior to being commissioned, the line should be thoroughly inspected, to ensure that: a) all structures have been correctly erected; b) all clearances are correct; c) all insulators have been correctly installed; d) conductors are undamaged; e) stays have been correctly installed; f) pole and anti-climbing guards, if needed, are in place; and g) pole and equipment earths are correct.

24

Annex A

(normative)

NRS 033:1996

Design of power line crossings of proclaimed roads, railway lines, tramways and important communication lines

A.1 Scope

This annex covers overhead power line crossings of proclaimed roads, railway lines, tramways and important communication lines, and should be read in conjunction with the regulations mentioned below.

A.2 Regulations and figures

A.2.1 Regulations

The following regulations are applicable:

Regulations 14, 15, 16, 17, 18, 20 and 22 of the Electrical Machinery Regulations of the Occupational

Health and Safety Act, 1993 (Act 85 of 1993).

A.2.2 Figures

The following figures show the most common crossing configurations: a) Figure A.1 — Formed armoured road crossing twin tie for vertically mounted pin or post insulator b) Figure A.2 — Formed arcing horn for horizontally mounted long rod insulator c) Figure A.3 — Formed arcing horn for horizontally mounted disc insulator d) Figure A.4 — Crossing with strain structures on both sides e) Figure A.5 — Crossing with an intermediate structure on one side and a strain structure on the other side f) Figure A.6 — Crossing with intermediate structures on both sides

A.3 Purpose

Should configurations other than those indicated in A.2.2 be used, it should be borne in mind that the main purpose of applying the above-mentioned precautions at crossings, is to ensure that flashovers to overhead line conductors and hardware adjacent to the crossing will not jeopardize the integrity of the crossing span. The crossing span conductors should not be lower than 4,5 m above ground in the case of a broken phase conductor in a span other than the crossing span as stipulated in the Occupational Health and Safety Act, 1993.

These precautionary requirements, and the regulations detailed in A.2.1, should be taken into account in the design of every crossing.

NRS 033:1996 25

Annex A

(continued)

Fully armoured conductor

Ties

10 kN insulator

Figure A.1 — Formed armoured road crossing twin tie for vertically mounted pin or post insulator

Thimble clevis

Formed dead-end

Formed arcing horn

Figure A.2 — Formed arcing horn for horizontally mounted long rod insulator

Thimble clevis

Formed dead-end

Formed arcing horn

Figure A.3 — Formed arcing horn for horizontally mounted disc insulator

26

Annex A

(continued)

NRS 033:1996

A.4 Arcing horns

A.4.1

Formed arcing horns, as shown in figures A.2 and A.3, are to be fitted to strain insulators in a crossing span where the conductor is terminated with a formed dead-end on a thimble clevis fitting. The reason for fitting arcing horns at such terminations is that, should a flashover occur, it is very likely that there will be arcing to the thimble groove, causing damage to one or more strands of the formed tie.

Damage of this nature could result in the immediate burn down of the crossing span conductor, or could give rise to a potentially dangerous situation because of the weakened formed tie (see A.5.4, alternative

2).

A.4.2 Alternatively, bolted or compression type deadends can be used without the fitting as arcing horns, because a flashover with these fittings will result in arcing to the body of the clamp, with little or no damage to the conductor (see A.5.4, alternative 1).

A.5 Structures

A.5.1

Where there are strain structures on either side of the crossing, intermediate structures without any special precautions can be erected beyond the crossing (see A.5.4).

A.5.2

Where there is one strain structure at the crossing, special precautions should be taken on the first three intermediate structures on the opposite side of the crossing (see A.5.5).

A.5.3

Where there are no strain structures at the crossing, special precautions should be taken on the first three intermediate structures on both sides of the crossing (see A.5.6).

Figure A.4 — Crossing with strain structures on both sides

C C

Telecommunication lines

B B

Road

C C

Figure A.4 — Crossing with strain structures on both

Stays, if required

NRS 033:1996 27

Annex A

(continued)

C A

Telecommunication lines

A A B

Road

C C

Figure A.5 — Crossing with an intermediate structure on one side and a strain structure on the other side

C A

Telecommunication lines

A A A

Road

A A C

Figure A.6 — Crossing with intermediate structures on both sides

28

Annex A

(continued)

NRS 033:1996

A.5.4

Requirements for strain structures marked B in figures A.4 and A.5

Alternative 1:

With bolted type conductor strain clamps or compression dead-end fittings: a) single conductor per phase; b) single strain insulator string or long rod per phase; and c) no arcing horns.

or

Alternative 2:

With formed conductor dead-ends on thimble clevis fitting: a) single conductor per phase; b) single strain insulator string or long rod per phase; and c) fit arcing horns to live end of insulators.

A.5.5

Requirements for intermediate structures marked C in figures A.4, A.5 and A.6

Alternative 1:

With rigid post or pin insulators: a) use 4 kN (minimum) insulators; and b) use standard formed twin tie.

or

Alternative 2:

With suspension insulators, fit either armour rods or arcing horns to live end of insulator.

A.5.6

Requirements for intermediate structures marked A in figures A.5 and A.6

Alternative 1:

With rigid post or pin insulators: a) use 10 kN (minimum) insulators; and b) use special formed road crossing twin tie as per figure A.1.

or

Alternative 2:

With suspension insulators, fit either armour rods or arcing horns to live end of insulators.

NRS 033:1996 29

Annex B

(normative)

Procedure for positioning of structures on a surveyed route plan

B.1

A "spanning plan" is produced from the route plan (see 5.2.1.2). Initially, the only points indicated are the "tee offs", "terminals" and "angles" and the approximate transformer and switchgear positions.

B.2

The designer should use the following procedure to plot the structure positions on the plan in the case of a small project, such as in the project example itt is advisable, to walk the route and to take note of all obstructions.

a) Select the type of structures to be used, taking account of the loading limits given in the pole span data tables (tables B.1 and B.2), and the stay loading data tables (tables B.9 and B.10).

b) Select the primary fixed points, such as a tee off point, angle position, road, rail or other crossing, transformer position, terminal position and valley crossing.

c) Divide the distances between the fixed points by the span capability of the structure selected, using the following tables which give the appropriate data:

— Table B.1

specifies wooden pole span data for preferred ACSR conductor sizes.

— Table B.2 specifies wooden pole span data for preferred AAAC conductor sizes.

— Table B.3 specifies conductor sag and tension for FOX conductor.

— Table B.4 specifies conductor sag and tension for MINK conductor.

— Table B.5 specifies conductor sag and tension for HARE conductor.

— Table B.6 specifies conductor sag and tension for FIR conductor.

— Table B.7 specifies conductor sag and tension for PINE conductor.

— Table B.8 specifies conductor sag and tension for OAK conductor.

— Table B.9 provides data for pole loading with stays at 45°.

— Table B.10 provides data for pole loading with stays at 30°.

d) So adjust the positions selected in clause B.3 that comparable span lengths result, and take cognizance of ground level variances and conductor-to-ground clearances (see 5.2.1.5).

e) Peg according to the selection, and adjust the positions to obtain the best foundation and access options.

f) Each time a reselection or change is necessary, redivide the remaining lengths and pinpoint structure positions again.

30

Annex B

(continued)

NRS 033:1996

Table B.1 : Wooden pole span data for preferred sizes of hard-drawn aluminium steel-reinforced

(ACSR) conductors

1

Wooden pole length

2

Pole top diam.

3

Planting depth

4

Lowest conductor attachment

5

Available for sag

6

Conductor code name

7

Wind span

8

Overturn span

9

Ground level clearance span at

50 ºC m

10

10

10

10

10

9

9

9

10

11

11

11

11

11

11

11

11

11 mm

140

140

140

140

140

140

140

140

140

140

140

140

160

160

160

160

160

160 m

1,5

1,5

1,5

1,5

1,5

1,5

1,6

1,6

1,6

1,8

1,8

1,8

1,8

1,8

1,8

2,0

2,0

2,0 m

6,15

6,15

6,15

7,15

7,15

7,15

7,05

7,05

7,05

7,85

7,85

7,85

7,85

7,85

7,85

7,65

7,65

7,65 m

0,65

0,65

0,65

1,65

1,65

1,65

1,55

1,55

1,55

2,35

2,35

2,35

2,35

2,35

2,35

2,15

2,15

2,15

FOX

MINK

HARE

FOX

MINK

HARE

FOX

MINK

HARE

FOX

MINK

HARE

FOX

MINK

HARE

FOX

MINK

HARE m

132

100

78

120

92

71

121

92

72

113

86

67

161

123

95

164

125

97 m

61

47

95

73

56

94

71

55

79

114

87

67

125

95

74

165

125

97 m

50

50

50

110

110

110

100

100

100

150

150

150

150

150

150

135

135

135

NOTES

1 The selected span length is determined by the limiting factors and is the least of the spans given in columns 7, 8 and 9.

2 The conductor code names FOX, MINK and HARE are the code names for the preferred sizes of hard-drawn aluminium steel-reinforced overhead conductors specified in SABS 182-3:1975.

The data in the table has been calculated based on the following assumptions.

— span capabilities on single wooden poles of minimum fibre strength of 55 MPa.

— configuration: staggered vertical with phase spacing of 600 mm.

— centre of gravity of wind load on three conductors is 750 mm from pole top.

— overturn span calculated from soil bearing pressure of 345 kPa.

— ground clearance span based on a minimum clearance of 5,5 m at 50 °C.

— wind pressure taken as 700 Pa.

NRS 033:1996 31

Annex B

(continued)

Table B.2 — Wooden pole span data for preferred sizes of all aluminium alloy (AAAC) conductors sizes

1

Wooden pole length

2

Pole top diam

3

Planting depth

4

Lowest conductor attachment

5

Avail able for sag

6

Conductor code name

7

Wind span

8

Overturn span

9

Ground level clearance span at

50 ºC m

11

11

11

11

11

11

11

NOTES

10

10

10

11

11

9

9

9

10

10

10 mm

140

140

140

140

140

140

140

140

140

140

140

140

160

160

160

160

160

160 m

1,5

1,5

1,5

1,6

1,6

1,6

1,6

1,6

1,6

1,8

1,8

1,8

1,8

1,8

1,8

2,0

2,0

2,0 m

6,15

615

6,15

7,15

7,15

7,15

7,05

7,05

7,05

7,85

7,85

7,85

7,85

7,85

7,85

7,65

7,65

7,65 m

0,65

0,65

0,65

1,65

1,65

1,65

1,55

1,55

1,55

2,35

2,35

2,35

2,35

2,35

2,35

2,15

2,15

2,15

FIR

PINE

OAK

FIR

PINE

OAK

FIR

PINE

OAK

FIR

PINE

OAK

FIR

PINE

OAK

FIR

PINE

OAK m

125

102

79

114

93

72

115

94

73

107

88

68

152

125

97

155

127

98 m

89

72

56

75

61

48

90

74

57

108

88

68

118

96

75

156

127

99 m

1) The selected span length is determined by the limiting factors and is the least of the spans given in columns 7, 8 and 9.

2) The conductor code names Fir, Pine and Oak are the code names for the preferred sizes of all aluminium alloy conductors specified in BS 3242. The equivalent descriptors for these conductors, using the convention used in IEC 1089, are

FIR 47,84 — A3 — 7/2,95

PINE

OAK

71,65 — A3 — 7/3,61

118,90 — A3 — 7/4,65

100

100

100

140

140

50

50

50

110

110

110

140

140

140

140

130

130

130

The data in the table has been calculated based on the following assumptions.

— span capabilities on single wooden poles of minimum fibre strength of 55 MPa.

— configuration: Staggered vertical with phase spacing of 600 mm.

— centre of gravity of wind load on three conductors is 750 mm from pole top.

— overturn span calculated from soil bearing pressure of 345 kPa.

— ground clearance span based on a minimum clearance of 5,5 m at 50 °C

— wind pressure taken as 700 Pa.

32

Annex B

(continued)

NRS 033:1996

NRS 033:1996 33

Annex B

(continued)

34

Annex B

(continued)

NRS 033:1996

NRS 033:1996 35

Annex B

(continued)

36

Annex B

(continued)

NRS 033:1996

NRS 033:1996 37

Annex B

(continued)

38 NRS 033:1996

Annex B

(continued)

Table B.9 — Pole loadings with stays at 45°

CONDUCTOR TENSION = 40 % OF UTS (see note)

1 2 3 4 5 6 7 8 9 10 11

Pole type

Length m

.

Top dia.

mm

Planting depth m

Ultimate buckling load kN

Maximum deviation angles for conductor of type: degrees

FOX MINK HARE FIR PINE OAK

13,2 33,3 21,8 36,0 13,43 20,2

Pole loading with stays at 45° kN

Gum

11

11

11

12

12

12

10

10

9

9

140

160

140

160

140

160

180

140

160

180

1,5

1,5

1,6

1,6

1,8

1,8

1,8

2,0

2,0

2,0

88

140

74

117

64

101

152

57

89

133

76

157

62

111

53

90

180

47

77

137

Pine

11

12

12

12

10

10

11

11

9

9

140

160

140

160

140

160

180

140

160

180

1,5

1,5

1,6

1,6

1,8

1,8

1,8

2,0

2,0

2,0

52

82

44

69

38

60

90

33

52

78

42

70

36

58

31

49

78

27

43

66

NOTE — Conductor tension has been taken as 40 % of ultimate tensile strength.

45

16

26

39

25

41

21

34

18

29

32

51

80

28

44

69

44

73

37

60

26

42

22

35

19

30

46

17

26

40

15

24

13

20

11

18

27

10

15

23

74

149

61

108

52

88

180

46

75

133

42

69

35

57

30

48

76

27

42

65

47

80

40

65

34

55

88

30

48

75

27

44

23

37

20

32

48

18

28

42

21

33

50

18

29

43

28

46

24

38

29

11

17

25

16

26

14

22

12

19

Stay data in respect of poles in this cable

20 mm grade 300 W stay rod

24 mm grade 300 W stay rod

7/3,35 1100 MPa stay wire

7/4,00 1100 MPa stay wire

19/2,65 1100 MPa stay wire

Ult. load kN

94,2

135

67,9

96,8

115

Max. load kN

38

54

27

39

46

Anchor combination

Stay rod Stay wire FOX

One

Two

One

20 mm

20 mm

20 mm

7/3,35 1100 MPa

7/3,35 1100 MPa

7/4,00 1100 MPa

74

148

114

Two

One

20 mm

24 mm

7/4,00 1100 MPa

19/2,65 1100 MPa

All

All

Two 24 mm 19/2,65 1100 MPa All

NOTE — “All” signifies angles of deviation up to 180°.

Terminal stays

Stay rod

One

Two

One

Two

One

Two

20 mm

20 mm

20 mm

20 mm

24 mm

24 mm

Stay wire

7/3,35 1100 MPa

7/3,35 1100 MPa

7/4,00 1100 MPa

7/4,00 1100 MPa

19/2,65 1100 MPa

19/2,65 1100 MPa

FOX

Yes

Yes

Yes

Yes

Yes

Yes

Deviation angle capability factor of safety = 2,5

MINK

43

86

61

122

77

154

HARE

25

50

36

72

44

88

FIR

73

146

112

224

All

All

PINE

46

92

66

132

84

168

MINK

No

Yes

Yes

Yes

Yes

Yes

Annex B

HARE

No

Yes

No

Yes

No

Yes

FIR

Yes

Yes

Yes

Yes

Yes

Yes

PINE

No

Yes

Yes

Yes

Yes

Yes

OAK

No

Yes

No

Yes

No

Yes

OAK

28

56

39

78

48

96

NRS 033:1996

1

Pole type

Gum

Pine

2

Length m

10

10

11

9

9

11

11

12

12

12

11

11

11

12

12

12

10

10

9

9

.

3

Top dia.

1,5

1,5

1,6

1,6

1,8

1,8

1,8

2,0

2,0

2,0

1,5

1,5

1,6

1,6

1,8

1,8

1,8

2,0

2,0

2,0 mm

140

160

140

160

140

160

180

140

160

180

140

160

140

160

140

160

180

140

160

180

52

82

44

69

38

60

90

33

52

78

88

140

74

117

64

101

152

57

89

133

39

4

Planting depth m

(concluded)

Table B.10 — Stay load at 30°

5

Ultimate buckling load kN

6 7 8 9 10 11

Maximum deviation angles for conductor of type: degrees

FOX

13,2

MINK

21,8

HARE

36,0

FIR

13,43

PINE

20,2

OAK

33,3

Pole loading with stays at 45° kN

42

69

35

57

30

48

76

27

42

65

24

39

20

32

18

28

42

16

24

37

25

40

21

33

18

29

44

16

25

38

15

23

12

19

11

17

25

9

15

22

15

24

13

20

11

17

26

10

15

23

9

14

7

12

6

10

15

6

9

13

41

68

34

56

30

47

75

26

41

64

24

38

20

32

17

27

42

15

24

36

Stay data in respect of poles in this table

20 mm grade 300 W stay rod

24 mm grade 300 W stay rod

7/3,35 1100 MPa stay wire

7/4,00 1100 MPa stay wire

19/2,65 1100 MPa stay wire

Ult. load kN

94,2

135

67,9

96,8

115

Max. load kN

38

54

27

39

46

Anchor combination

Stay rod

One

Two

One

Two

One

Two

20 mm

20 mm

20 mm

20 mm

24 mm

24 mm

Stay wire

7/3,35 1100 MPa

7/3,35 1100 MPa

7/4,00 1100 MPa

7/4,00 1100 MPa

19/2,65 1100 MPa

19/2,65 1100 MPa

FOX

51

102

73

146

93

All

NOTE — “All” signifies angles of deviation up to 180°.

Terminal stays

Stay rod

One

Two

One

Two

One

Two

20 mm

20 mm

20 mm

20 mm

24 mm

24 mm

Stay wire

7/3,35 1100 MPa

7/3,35 1100 MPa

7/4,00 1100 MPa

7/4,00 1100 MPa

19/2,65 1100 MPa

19/2,65 1100 MPa

FOX

No

Yes

Yes

Yes

Yes

Yes

MINK

No

Yes

No

Yes

No

Yes

Deviation angle capability factor of safety = 2

MINK

30

60

42

84

52

104

HARE

18

36

25

50

31

62

FIR

50

100

71

142

91

All

PINE

32

84

45

90

56

112

HARE

No

No

No

No

No

Yes

FIR

No

Yes

Yes

Yes

Yes

Yes

PINE

No

Yes

No

Yes

No

Yes

OAK

No

No

No

Yes

No

Yes

OAK

19

38

27

54

33

66

16

25

13

21

11

18

27

10

16

24

20

31

47

17

27

41

27

43

23

36

9

15

8

13

7

11

17

6

10

14

12

19

28

10

16

25

16

26

14

22

ANNEX C

40

(normative)

NRS 033:1996

Description and illustrations of overhead power line support standards and related features

Figure C.1 - Intermediate wooden pole structure, vertical, NO deviation.

Figure C.2 - Intermediate wooden pole structure, vertical, small angle deviation.

Figure C.3 - Road crossing intermediate wooden pole structure, vertical, no deviation.

Figure C.4 - Suspension wooden pole structure, vertical, medium angle deviation.

Figure C.5 - Strain wooden pole structure, vertical, 30° to 90° deviation.

Figure C.6 - Wooden pole structure, delta, up to 30° deviation.

Figure C.7 - H-pole strain wooden pole structure, horizontal, 60° to 90° deviation.

Figure C.8 - Long span H-pole suspension wooden pole structure, delta, no deviation.

Figure C.9 - Long span H-pole strain wooden pole structure, delta, no deviation.

Figure C.10 - Long span triple-pole strain wooden pole structure, delta, no deviation.

Figure C.11 - Terminal wooden pole structure, vertical.

Figure C.12 - Terminal structure, delta.

Figure C.13 - Tee-off wooden pole structure, vertical intermediate to vertical tee-off, no deviation.

Figure C.14 - Tee-off wooden pole structure, vertical intermediate to delta tee-off, no deviation.

Figure C.15 - Recloser or sectionalizer strain wooden pole structure, horizontal, no deviation.

Figure C.16 - In-line isolating strain wooden pole structure, delta, no deviation.

Figure C.17 - Pole-mounted CSP transformer, mass < 760 kg, terminal wooden pole structure, delta.

Figure C.18 - Pole-mounted transformer, mass < 760 kg, intermediate wooden pole structure, vertical, no deviation.

Figure C.19 - Platform-mounted transformer, 760 kg < mass < 2 000 kg, terminal wooden pole structure, horizontal.

Figure C.20 - Platform-mounted transformer, 760 kg < mass < 2 000 kg, terminal wooden pole structure, vertical.

Figure C.21 - Delta to vertical phase configuration intermediate wooden pole structures.

Figure C.22 - Pole foundation detail.

ANNEX C

NRS 033:1996 41

(continued)

Figure C.23 - Stay anchor assembly installation detail.

Figure C.24 - Rock anchor assembly installation detail.

Figure C.25 - Stay assembly detail.

Figure C.26 - Overhead (flying) stay arrangement detail.

Figure C.27 - Conductor tie installation for pin and post insulators.

ANNEX C

(continued)

42 NRS 033:1996

NRS 033:1996 43

ANNEX C

(continued)

44

ANNEX C

(continued)

NRS 033:1996

NRS 033:1996 45

ANNEX C

(continued)

46

ANNEX C

(continued)

NRS 033:1996

NRS 033:1996 47

ANNEX C

(continued)

48

ANNEX C

(continued)

NRS 033:1996

NRS 033:1996 49

ANNEX C

(continued)

50

ANNEX C

(continued)

NRS 033:1996

NRS 033:1996 51

ANNEX C

(continued)

52

ANNEX C

(continued)

NRS 033:1996

NRS 033:1996 53

ANNEX C

(continued)

54

ANNEX C

(continued)

NRS 033:1996

NRS 033:1996 55

ANNEX C

(continued)

56

ANNEX C

(continued)

NRS 033:1996

NRS 033:1996 57

ANNEX C

(continued)

58

ANNEX C

(continued)

NRS 033:1996

NRS 033:1996 59

ANNEX C

(continued)

60

ANNEX C

(continued)

NRS 033:1996

NRS 033:1996 61

ANNEX C

(continued)

62

ANNEX C

(continued)

NRS 033:1996

NRS 033:1996 63

ANNEX C

(continued)

64

ANNEX C

(continued)

NRS 033:1996

NRS 033:1996 65

ANNEX C

(continued)

66

ANNEX C

(continued)

NRS 033:1996

NRS 033:1996 67

ANNEX C

(continued)

68

ANNEX C

(concluded)

NRS 033:1996

NRS 033:1996 69

ANNEX D

(informative)

Project example

D.1 General

The construction of a medium voltage overhead line in terms of the guidelines is illustrated, using the following example:

A supplier of electricity has to provide a power supply to a pump station and sewerage works, and exploits the opportunity to supply electricity to a farm enroute. A road crossing, rail crossing and valley crossing are encountered.

It is presupposed that the electricity supplier determines the desired power supply parameters for the project as outlined in 5.1, and has finalized the issues raised in 5.1 and 5.2.

D.2 The power distribution system planning phase

(see 5.1)

D.2.1

The supply voltage is determined: 22 kV

D.2.2

The type of conductor is selected: FOX

D.2.3

The type of construction is chosen: Wooden poles

D.2.4

The system electrical protection comprises: a) an auto-recloser/switchgear or circuit-breaker with isolating and bypass links at the tee-off from the main line; b) solid isolating links at subsequent tee-offs; and c) fuses and surge arresters at transformers;

D.2.5

A schematic layout of the overhead line is prepared and is as shown in figure D.1.

D.3 Spanning plan

D.3.1

Figure D.2 shows the result of the application of the procedure (described in annex B of this guideline) to the power line project.

D.3.2

The railway crossed in the example is an electrified line and as such, the time allowed to effect the crossing is restricted since the electrical supply to the railway line has to be disconnected. An outage will have to be arranged. Two strain pole structures are selected for either side of the railway line, to enable the construction of the line to proceed unhampered, whilst the crossing can be completed at a convenient time.

D.3.3

The power line should be at least 1,8 m above the Telkom line.

D.3.4

In this example, the fixed points are: a) tee-off from existing line; b) auto-recloser; c) first angle; d) road crossing (N.B. In this case, the road will be crossed with intermediate structures);

70 NRS 033:1996

ANNEX D

(continued) e) rail crossing (N.B. Strain structures are selected to facilitate construction arrangements with

Spoornet); f) tee off to village pump; g) valley; h) angle near sewerage works; i) terminal at sewerage works; j) links on village pump tee; k) chicken farm transformer; l) angle approaching village pump; and m) village pump transformer.

D.4 Distances

The distances shown between structures on the spanning plan in figure D.2 are selected by application of the procedures outlined in B.2 (c) to (f).

As an example, consider the portion of the route between fixed point 1 (auto-recloser) and 4 (first angle).

The distance is 305 m. Taking the span capabilities of the appropriate structures, into account it is determined that three span lengths of approximately 100 m each, are required.

Furthermore taking local site conditions into account, span lengths of 110 m, 95 m and 100 m are chosen.

D.5 Survey

The next step in the process depends on whether or not a surveyor is to peg the structure positions.

In this example, the services of a surveyor are used and the structure pegs will be placed by him in the best position possible whilst keeping within the limitations of the selected structures.

Examples of a case where the surveyor would adjust a structure position could be: a) where ground water exists, or b) where there are rock outcrops or where rocks are known to be present.

Once the spanning plan is complete, it is advisable to prepare a structure schedule, as shown for this example in tables D.1 and D.2, to facilitate preparation of a bill of materials and to assist the construction supervisor.

NRS 033:1996 71

ANNEX D

(continued)

72 NRS 033:1996

ANNEX D

(continued)

Figure C.14

50 m

1

Exe to Wye 22 kV line

Figure C.15

Figure C.1

110 m

2

95 m

Auto-recloser

Figure C.1

3

100 m

Figure C.2

4

110 m

1 Pr Telkom

5

Figure C.3

Figure C.3

7

65 m

Exe to Wye gravel road

6

80 m

Figure C.6

40 m

Railway single line

8

Figure C.6

50 m

Figure C.14

115 m

9

50 m

T1

Figur e

C.16

12

0 m

T2

Links

T3

10

0 m

Fi gu re

C.

11

5 m

Fi gu re

C.

T4

Fi gu re

C.

18

Figure C.1

10

100 m

11

Chicken farm

100 kVA Transformer

10

8 m

T5

Fi gu re

C.

11

5 m

Fi gu re

C.

T6 12

Wye village pumps

150 kVA Transformer

0 m

T7

11

5 m

Fi gu re

C.

T8

12

0 m

Fi gu re

C.

T9

Figure C.9

T1

0

Fi gu

C.

0 m

Fi gu re

C.

19

420 m

Route length = 1 083 m

Valley

Sewerage works

100 kVA Transformer

Figure C.17

14

Figure C.9

12

13

115 m

Figure C.5

65º

Route length = 1 580 m

Figure D.2 — Wye village electrification extension

NRS 033:1996 73

ANNEX D

(continued)

Table D.1 — Structure schedule

Wye village electrification extension sewerage works tee-off from existing Exe/Wye 22 kV line

Voltage:

Conductor:

Route length:

Conductor length:

1

Structure type number on figure D.2

E/W 63

1

2

3

4

5

8

9

6

7

10

11

12

13

14

2

Type

22 kV

FOX 6/1/2,79 mm ACSR

1 844 m

4 736 m = (route length times 3) + 2,5 %

3

Drawing number

4

Span length

5

Section length

Existing

Strain

Intermediate

Intermediate

Light angle

Intermediate

Figure C.14

Figure C.15

Figure C.1

Figure C.1

Figure C.2

Figure C.3

0

50

110

95

100

110

50

6

Remarks instructions

Tee/arrangement only/FOX to MINK auto recloser with bypass

8° deviation left

Road crossing

Span 5-6

Intermediate

Strain

Figure C.3

Figure C.12

65

80 560 Rail crossing

Span 7-8

Strain

Inter. tee

Figure C.12

Figure C.14

40

50

40

Tee to village pump/spur

Intermediate

Strain

Figure C.1

Figure C.9

115

100 265 Long span.

Vlei crossing

Strain

Angle Strain

Terminal transformer

TOTAL ROUTE LENGTH

Figure C.9

Figure C.5

Figure C.17

420

115

90

420

115

90

1 540

65° deviation right

100 kVA CSP transformer (mass as elsewhere 760 kg)

Structure summary: 11 m x 160 mm top diameter. 55 MPa. Wooden poles. 16 required.

NOTE — Auto-recloser to be graded to suit protection on EXE/WYE feeder.

74

ANNEX D

(continued)

NRS 033:1996

T5

Table D.2 — Structure schedule

Wye village pump 22 kV tee-off from sewerage works feeder

Voltage:

Conductor:

Route length:

Conductor length:

1

Structure type number on figure

D.2

E/W VPT 9

T1

T2

T3

T4

2

Type

Existing

Strain

22 kV

FOX 6/1/2,79 mm ACSR

1 843 m

3 330 m = (route length times 3) + 2,5 %

3

Drawing number

4

Span length

5

Section length

Intermediate

Intermediate

Transformer

Intermediate

Figure C.14

Figure

Figure

C.16

Figure C.1

Figure C.1

C.18

Figure C.1

0

50

120

115

100

108

50

6

Remarks instructions

Tee/arrangement only/FOX to FOX section links

Chicken farm

100 kVA transformer

T6

T7

T8

T9

T10

Angle susp

Intermediate

Intermediate

Intermediate

Terminal transformer

Figure

Figure

Figure

Figure

C.4

C.1

C.1

C.1

Figure C.17

115

120

115

120

120 1 033

TOTAL ROUTE LENGTH 1 083

Structure summary: 11 m x 160 mm top diameter. 55 MPa. Wooden poles. 10 required.

NRS 033:1996 75

ANNEX D

(concluded)

76

ANNEX E

(informative)

Bibliography

NRS 033:1996

IEC 1109:1992,

Composite insulators for a.c. overhead lines with a nominal voltage greater than 1000 V — Definitions, test methods and acceptance criteria.

NRS 022:1993,

Electricity distribution — Stays and associated components

(under revision).

NRS 027:1994

, Distribution transformer — completely self-protecting type for rated voltages up to and including 33 kV.

NRS 041:1995,

Electricity transmission and distribution — Code of practice for overhead lines for conditions prevailing in South Africa.

sabs pta

Download