PELE MOUNTAIN RESOURCES INC. TECHNICAL REPORT ON THE ECO RIDGE MINE PROJECT, ELLIOT LAKE, ONTARIO, CANADA NI 43-101 Report Qualified Persons: Jason J. Cox, P.Eng. Tudorel Ciuculescu, M.Sc., P.Geo. Kathleen Altman, P.E. Leo Hwozdyk, P.Eng. June 20, 2012 ROSCOE POSTLE ASSOCIATES INC. Report Control Form Document Title Technical Report on the Eco Ridge Mine Project, Elliot Lake Area, Ontario, Canada Client Name & Address Pele Mountain Resources Inc. 2200 Yonge Street Suite 905 Toronto, Ontario M4S 2C6 Document Reference Project #1826 Issue Date Lead Author Final Version Status & Issue No. June 20, 2012 Jason Cox Tudorel Ciuculescu Kathleen A. Altman Leo Hwozdyk (Signed) (Signed) (Signed) (Signed) Peer Reviewer Deborah McCombe (Signed) Project Manager Approval Jason Cox (Signed) Project Director Approval Richard Lambert (Signed) Name Report Distribution No. of Copies Client RPA Filing 1 (project box) Roscoe Postle Associates Inc. 55 University Avenue, Suite 501 Toronto, Ontario M5J 2H7 Canada Tel: +1 416 947 0907 Fax: +1 416 947 0395 mining@rpacan.com 0 www.rpacan.com TABLE OF CONTENTS PAGE 1 SUMMARY .................................................................................................................. 1-1 Executive Summary ................................................................................................. 1-1 Technical Summary ............................................................................................... 1-17 2 INTRODUCTION......................................................................................................... 2-1 3 RELIANCE ON OTHER EXPERTS ............................................................................ 3-1 4 PROPERTY DESCRIPTION AND LOCATION ........................................................... 4-1 Licences of Occupation ............................................................................................ 4-5 Royalties and Other Encumbrances......................................................................... 4-5 Permits ..................................................................................................................... 4-5 Environmental Liabilities .......................................................................................... 4-6 5 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY .......................................................................................................... 5-1 6 HISTORY .................................................................................................................... 6-1 7 GEOLOGICAL SETTING AND MINERALIZATION .................................................... 7-1 Regional Geology ..................................................................................................... 7-1 Local Geology .......................................................................................................... 7-5 Property Geology ................................................................................................... 7-12 Mineralization ......................................................................................................... 7-15 Historical Mineralogical Studies ............................................................................. 7-17 Mineralogical Studies on the Eco Ridge Mine Property ......................................... 7-20 Detailed Description of Mineralized Zones ............................................................. 7-23 Discussion of Mineralized Zones............................................................................ 7-27 8 DEPOSIT TYPES........................................................................................................ 8-1 9 EXPLORATION........................................................................................................... 9-1 10 DRILLING................................................................................................................ 10-1 Pele Mountain Drill Programs................................................................................. 10-1 11 SAMPLE PREPARATION, ANALYSES AND SECURITY ...................................... 11-1 Historic Holes ......................................................................................................... 11-4 Pele Mountain Drilling Programs ............................................................................ 11-5 12 DATA VERIFICATION ............................................................................................ 12-1 Drill Hole Collar Surveys ........................................................................................ 12-1 Drill Hole Deviation ................................................................................................. 12-1 Database ................................................................................................................ 12-1 Data Entry .............................................................................................................. 12-2 Database Validation ............................................................................................... 12-3 Pele Mountain QA/QC Monitoring .......................................................................... 12-3 Pele Mountain QA/QC Program 2011 .................................................................... 12-4 Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page i www.rpacan.com Independent Sampling by RPA .............................................................................. 12-7 13 MINERAL PROCESSING AND METALLURGICAL TESTING ............................... 13-1 14 MINERAL RESOURCE ESTIMATE ........................................................................ 14-1 Summary ................................................................................................................ 14-1 Mineral Resource Database ................................................................................... 14-2 Geological Interpretation and 3D Solids ................................................................. 14-3 Basic Statistics and Capping of High Assays ......................................................... 14-6 Block Model and Grade Estimation ...................................................................... 14-20 Classification ........................................................................................................ 14-24 Sensitivity Analysis ............................................................................................... 14-27 Comparison with Previous Mineral Resource Estimate ....................................... 14-31 Exploration Potential of Additional Resources on the Property ............................ 14-31 15 MINERAL RESERVE ESTIMATE ........................................................................... 15-1 16 MINING METHODS ................................................................................................ 16-1 Selected Mining Method ......................................................................................... 16-1 Mine Development ................................................................................................. 16-1 Dilution ................................................................................................................... 16-7 Mining Production Rate .......................................................................................... 16-8 Mining Sequence ................................................................................................. 16-10 Support Services .................................................................................................. 16-13 Equipment ............................................................................................................ 16-15 Manpower ............................................................................................................ 16-17 Material Handling Trade-Off Study ....................................................................... 16-22 17 RECOVERY METHODS ......................................................................................... 17-1 18 PROJECT INFRASTRUCTURE ............................................................................. 18-1 19 MARKET STUDIES AND CONTRACTS ................................................................. 19-1 Uranium .................................................................................................................. 19-1 Rare Earths ............................................................................................................ 19-1 Contracts ................................................................................................................ 19-7 20 ENVIRONMENTAL STUDIES, PERMITTING, AND SOCIAL OR COMMUNITY IMPACT........................................................................................................................ 20-1 Introduction ............................................................................................................ 20-1 Permits, Licences and Other Legislative Requirements......................................... 20-2 Environmental Assessment .................................................................................... 20-6 Aquatic Baseline Study ........................................................................................ 20-12 Decommissioning and Closure Planning.............................................................. 20-15 Environmental Risk Assessments ........................................................................ 20-16 Environmental Management Strategies ............................................................... 20-16 Occupational Health and Safety ........................................................................... 20-18 Community Relations ........................................................................................... 20-22 21 CAPITAL AND OPERATING COSTS ..................................................................... 21-1 Capital Costs .......................................................................................................... 21-1 Operating Costs ..................................................................................................... 21-4 Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page ii www.rpacan.com 22 ECONOMIC ANALYSIS .......................................................................................... 22-1 23 ADJACENT PROPERTIES ..................................................................................... 23-1 24 OTHER RELEVANT DATA AND INFORMATION .................................................. 24-1 25 INTERPRETATION AND CONCLUSIONS ............................................................. 25-1 26 RECOMMENDATIONS ........................................................................................... 26-1 27 REFERENCES........................................................................................................ 27-1 28 DATE AND SIGNATURE PAGE ............................................................................. 28-1 29 CERTIFICATE OF QUALIFIED PERSON .............................................................. 29-1 LIST OF TABLES PAGE Table 1-1 Pre-Tax Cash Flow Summary ...................................................................... 1-4 Table 1-2 Sensitivity Analysis ...................................................................................... 1-8 Table 1-3 Summary of Mineral Resources – April 16, 2012 ...................................... 1-10 Table 1-4 Proposed Work Program and Estimated Cost ........................................... 1-15 Table 1-5 Overall Capital Cost Estimate .................................................................... 1-25 Table 1-6 Operating Cost Estimate ............................................................................ 1-25 Table 4-1 Schedule of Claims ...................................................................................... 4-1 Table 4-2 Precambrian Agreement Terms ................................................................... 4-3 Table 4-3 May 2007 Agreement Terms ....................................................................... 4-4 Table 5-1 Average Minimum and Maximum Temperatures in the Elliot Lake District .. 5-2 Table 6-1 Historic Drill Hole Summary ......................................................................... 6-5 Table 7-1 Table of Formations in the Region ............................................................... 7-1 Table 7-2 Stratigraphy of the Huronian Supergroup .................................................... 7-2 Table 7-3 Elliot Lake Group, Elliot Lake Area .............................................................. 7-5 Table 7-4 Stratigraphy of Lower Matinenda ................................................................. 7-9 Table 7-5 Stratigraphy of Lower Matinenda (Ryan Member) ..................................... 7-17 Table 7-6 Uranium-Bearing and Associated Heavy Minerals .................................... 7-17 Table 7-7 Uranium Mineralogy of the Main Conglomerate Bed ................................. 7-21 Table 7-8 Uranium Mineralogy of the Basal Conglomerate Bed ................................ 7-22 Table 7-9 Relative Percentage of Individual Rare Earth Elements ............................ 7-29 Table 7-10 Correlation Between Uranium and Rare Earths ....................................... 7-30 Table 12-1 RPA Independent Sampling..................................................................... 12-8 Table 13-1 Preliminary Screening Size Distribution ................................................... 13-2 Table 13-2 Preliminary Screening Size Distribution ................................................... 13-2 Table 13-3 Overall Size Distribution........................................................................... 13-3 Table 13-4 Magnetic Separation Results ................................................................... 13-4 Table 13-5 Flotation Results ...................................................................................... 13-5 Table 13-6 Leaching Results ..................................................................................... 13-6 Table 13-7 Bulk Sample #4 Analyses ........................................................................ 13-6 Table 13-8 Fine Size Fraction Analyses .................................................................... 13-7 Table 13-9 Estimated REO Recoveries ..................................................................... 13-9 Table 14-1 Summary of Mineral Resources – April 16, 2012 .................................... 14-1 Table 14-2 MCB and Hwz Intercepts True Thickness - Descriptive Statistics ........... 14-4 Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page iii www.rpacan.com Table 14-3 Rare Earth and Other Elements - MCB Resource Assays Descriptive Statistics ....................................................................................................................... 14-7 Table 14-4 Rare Earth and Other Elements - HWZ Resource Assays Descriptive Statistics ....................................................................................................................... 14-8 Table 14-5 Rare Earth and Other Elements - MCB Resource Composites Descriptive Statistics ..................................................................................................................... 14-10 Table 14-6 Rare Earth and Other Elements - HWZ Resource Composites Descriptive Statistics ..................................................................................................................... 14-11 Table 14-7 Block Model Setup ................................................................................. 14-20 Table 14-8 Search Strategy Parameters.................................................................. 14-20 Table 14-9 Summary of Mineral Resources – April 16, 2012 .................................. 14-25 Table 14-10 Mineral Resource Estimate - April 16, 2012 - Rare Earth Oxides and Related Oxides........................................................................................................... 14-26 Table 14-11 Indicated Resource – Tonnage And TREO% Grade at Various NSR Cutoff Values ................................................................................................................... 14-28 Table 14-12 Inferred Resource – Tonnage and Treo% Grade at Various NSR Cut-off Values ........................................................................................................................ 14-28 Table 14-13 Mineral Resource Comparison – 2007 to 2012 ................................... 14-31 Table 14-14 Historic Drill Holes Not Included in the 2012 Resource Estimate ........ 14-32 Table 14-15 Historic Drill Holes Demonstrating the Down-Dip Potential of the Main Conglomerate Bed ..................................................................................................... 14-33 Table 14-16 Historic Drilling Results from the Pecors Lake Block ........................... 14-34 Table 16-1 Equipment Optimum Production Capacities ............................................ 16-9 Table 16-2 Effective Production Rates..................................................................... 16-10 Table 16-3 Air Volume Requirements ...................................................................... 16-13 Table 16-4 Mine Equipment Summary ..................................................................... 16-16 Table 16-5 Manpower Requirements ....................................................................... 16-18 Table 17-1 Conceptual Design Criteria ...................................................................... 17-5 Table 17-2 Conceptual Mass Balance ....................................................................... 17-6 Table 19-1 Distribution of Rare Earths by Source – China ........................................ 19-3 Table 19-2 Rare Earth Supply – 2008 & 2010 ........................................................... 19-4 Table 19-3 REO Forecast Prices vs. Current Spot Prices ......................................... 19-6 Table 21-1 Overall Capital Cost Estimate .................................................................. 21-1 Table 21-2 Mine Capital Cost Estimate ...................................................................... 21-2 Table 21-3 Initial process Capital Cost Estimate ....................................................... 21-3 Table 21-4 Total Operating Cost Estimate ................................................................. 21-4 Table 21-5 Mine Operating Cost Estimate ................................................................. 21-5 Table 21-6 Process Operating Cost Estimate ............................................................ 21-6 Table 22-1 Pre-Tax Cash Flow Summary .................................................................. 22-3 Table 22-2 Sensitivity Analysis .................................................................................. 22-6 Table 25-1 Summary of Mineral Resources – April 16, 2012 .................................... 25-2 Table 26-1 Proposed Work Program and Estimated Cost ......................................... 26-2 LIST OF FIGURES PAGE Figure 1-1 Sensitivity Analysis ..................................................................................... 1-7 Figure 1-2 Project Schedule....................................................................................... 1-16 Figure 4-1 Location Map .............................................................................................. 4-7 Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page iv www.rpacan.com Figure 4-2 Land Tenure Map ....................................................................................... 4-8 Figure 7-1 Regional Geology ....................................................................................... 7-4 Figure 7-2 Property Geology ...................................................................................... 7-10 Figure 7-3 Location of the Mineralized Channels....................................................... 7-11 Figure 7-4 Property Geology ...................................................................................... 7-14 Figure 7-5 Typical Cross Section Through the Adit Block .......................................... 7-25 Figure 7-6 Variation in Uranium Concentration in the Main Conglomerate Bed ........ 7-26 Figure 10-1 Location of the Historic Drill Holes .......................................................... 10-3 Figure 10-2 Location of Pele Mountain Drill Holes ..................................................... 10-4 Figure 12-1 Blank Samples ........................................................................................ 12-5 Figure 12-2 Certified Reference Materials Samples .................................................. 12-6 Figure 12-3 Field Sample Duplicates ......................................................................... 12-7 Figure 14-1 MCB Intercepts True Width Histogram (n=238)...................................... 14-5 Figure 14-2 HWZ Intercepts True Width Histogram (n=130) ..................................... 14-6 Figure 14-3 U3O8, Dy, and Nd Assay Histograms - MCB and HWZ........................... 14-9 Figure 14-4 U3O8, Dy, and Nd Composite Histograms - MCB and HWZ ................. 14-12 Figure 14-5 MCB intercepts Variography for U3O8, Nd, and Dy ............................... 14-15 Figure 14-6 HWZ intercepts Variography for U3O8, Nd, and Dy............................... 14-16 Figure 14-7 U3O8 Composites Grade Contours in MCB .......................................... 14-17 Figure 14-8 Nd Composites Grade Contours in MCB .............................................. 14-18 Figure 14-9 Dy Composites Grade Contours in MCB .............................................. 14-19 Figure 14-10 Resource Blocks in MCB .................................................................... 14-22 Figure 14-11 Resource Blocks in HWZ .................................................................... 14-23 Figure 14-12 Grade –Tonnage Curves of Indicated Resource ................................ 14-29 Figure 14-13 Grade –Tonnage Curves of Inferred Resource .................................. 14-30 Figure 14-14 Historic Drill Holes with Mineralized Intersections Outside the Mineral Resource .................................................................................................................... 14-36 Figure 14-15 Location of the Exploration Targets .................................................... 14-37 Figure 16-1 Site Layout .............................................................................................. 16-2 Figure 16-2 Mine PLan............................................................................................... 16-5 Figure 16-3 Panel Plan .............................................................................................. 16-6 Figure 16-4 Mining Sequence Section ..................................................................... 16-11 Figure 16-5 Stope Development Section ................................................................. 16-12 Figure 16-6 Stope Drilling Section ........................................................................... 16-19 Figure 16-7 Tramming Section................................................................................. 16-20 Figure 16-8 Hauling Section..................................................................................... 16-21 Figure 17-1 Process Flow Sheet ................................................................................ 17-7 Figure 19-1 Chinese Rare Earth Export Quotas by Year (Thousands of Tons) ......... 19-4 Figure 22-1 Sensitivity Analysis ................................................................................. 22-5 Figure 24-1 Project Schedule..................................................................................... 24-2 Figure 26-1 Project Schedule..................................................................................... 26-3 Figure 26-2 Preliminary Proposed Drill Hole Location for Indicated and Inferred Tonnage Targets 2012 Program .................................................................................. 26-4 Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page v www.rpacan.com 1 SUMMARY EXECUTIVE SUMMARY INTRODUCTION Roscoe Postle Associates Inc. (RPA) was retained by Pele Mountain Resources Inc. (Pele Mountain), to carry out a Preliminary Economic Assessment (PEA) on the Eco Ridge Mine Project (the Project), located in Elliot Lake, Ontario. The purpose of this report is to update the Project economics with results of work completed since the previous PEA in August 2011 (the “2011 PEA”). This updated PEA features an updated resource estimate and a base case scenario for production that focuses on mining the relatively higher-grade main conglomerate bed, and uses a conventional milling approach for processing which achieves materially higher recoveries for rare earths and uranium. Pele Mountain is a Canadian resource exploration and development company focused on the sustainable development of its 100%-owned Eco Ridge Mine Rare Earths and Uranium Project (Eco Ridge or the Project). Pele Mountain is a reporting issuer in Ontario, British Columbia, and Alberta, and its common shares are listed on the TSX Venture Exchange and also trade on the OTCQX. Pele Mountain has also entered into an agreement to purchase the Simon Rare Earth Claims in Mountain Pass, California. Currently, the major asset associated with the Project is a stratabound zone of rare earth oxide (REO) and uranium oxide (U3O8) mineralization. Rare earth elements (REE) are divided into two groups: 1. The Light Rare Earth Elements (LREE) or cerics, comprising of La, Ce, Pr, and Nd. 2. The Heavy Rare Earth Elements (HREE) or yttrics, comprising of Y, Eu, Gd, Tb, Dy, Ho, Er, Tm, Yb, Lu, and Sm. Scandium, while not a rare earth, has been included with the HREE for purposes of this report. LREO and HREO refer to oxides of light and heavy rare earth elements respectively. In this document, TREO (Total Rare Earth Oxides) refers to LREOs and HREOs collectively. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 1-1 www.rpacan.com PEA-level work on the Project is based on the development of an underground mining operation ramping up to 9,000 tonnes per day (tpd), with the recovery of REO and U3O8. The 2011 PEA was based on processing via underground bioleaching and surface heap leaching, while this update is based on conventional milling and acid baking. Materially higher recoveries of REO and U3O8, based on recent testwork, proved to outweigh associated capital and operating cost increases, providing for more robust economic results. ECONOMIC ANALYSIS A Pre-Tax Cash Flow Projection has been generated from the Life of Mine (LOM) production schedule and capital and operating cost estimates, and is summarized in Table 1-1. A summary of the key criteria is provided below. PRODUCTION Production quantities total 34.6 Mt, at grades of 0.040% U3O8 and 1,455 ppm TREO, over a mine life of 11 years. o The Main Conglomerate Bed (MCB) zone totals 31.0 Mt grading 0.043% U3O8 and 1,544 ppm TREO o The Hangingwall Zone (HWZ) totals 3.6 Mt grading 0.017% U3O8 and 1,017 ppm TREO Underground mining using room and pillar mining methods, with all development in ore. Two years of pre-production development with mill commissioning and limited production commencing in the second year. Production rate ramping up to a nominal 9,000 tpd in Year 1. Processing by crushing and grinding, magnetic separation, froth flotation, acid baking and water leaching, solid/liquid separation, high density sludge (HDS) removal, and recovery of the valuable elements by solvent extraction and precipitation. The proposed processing method produces yellow cake and a mixed rare earths carbonate concentrate. Uranium recovery of 90% (assumption, based on historical operations in the area). Rare earths recoveries by individual oxide, based on preliminary bench scale testwork. LREOs average 89% recovery, while HREOs average 75% recovery. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 1-2 www.rpacan.com Mine life production of 27.5 million pounds of U3O8 and 44.1 million kg of TREO. Production of a strategically significant combination of rare earths forecast to remain in supply deficit, with 85% of Project revenue from heavy REO, neodymium oxide (Nd2O3) and U3O8. REVENUE Exchange rate US$1.00 = C$1.00. Uranium price of US$70 per pound U3O8. Rare earth prices by individual oxide, with a basket price of US$78 per kg. o Net of costs for separating the rare earth concentrate into individual oxides – C$30 per kg for HREOs and C$10 per kg for LREOs. LREOs consist of CeO2, La2O3, Nd2O3 and Pr6O11 while HREOs consist of Sm2O3, Eu2O3, Gd2O3, Sc2O3, Y2O3, Yb2O3, Dy2O3, Er2O3, Ho2O3, Lu2O3, Tb4O7 and Tm2O3. NSR royalty of 0.75%. Average net revenue (NSR unit value) of $154 per tonne. Uranium provides 36% of revenue, and rare earths provide 64%. HREO make up slightly over 50% of the rare earths revenue. Revenue is recognized at the time of production. Initial capital of C$563 million (first two years), includes contingency of $108 million. Mine life capital totals C$670 million. Unit operating costs of $71.33 per tonne. COSTS Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 1-3 TABLE 1-1 PRE-TAX CASH FLOW SUMMARY Pele Mountain Resources Inc. – Eco Ridge Mine Project Year -2 Units Inputs Year -1 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Total MINING Ore Mined 34,550 000s tonnes Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Uranium Grade CeO2 Grade La2O3 Grade Nd2O3 Grade Pr6O11 Grade Sm2O3 Grade Eu2O3 Grade Gd2O3 Grade Sc2O3 Grade Y2O3 Grade Yb2O3 Grade Dy2O3 Grade Er2O3 Grade Ho2O3 Grade Lu2O3 Grade Tb4O7 Grade Tm2O3 Grade Th Grade LREO Grade HREO Grade Total REO Grade 0.040% %U3O8 ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm Oxide Factors 1.23 1.17 1.17 1.21 1.16 1.16 1.15 1.53 1.27 1.14 1.15 1.14 1.15 1.14 1.18 1.14 1.14 657.05 346.12 210.56 65.49 36.34 2.05 24.30 7.12 71.39 5.04 15.54 6.48 2.62 0.69 3.36 0.88 338.14 1,279.23 175.80 1,455.03 229 318 3,287 3,284 3,284 3,283 3,278 3,279 3,253 3,280 3,282 3,279 1,214 - 0.048% 0.058% 0.058% 0.052% 0.044% 0.045% 0.045% 0.036% 0.036% 0.037% 0.032% 0.020% 0.018% 0.000% 758.70 395.72 248.58 77.66 42.32 2.41 27.83 5.91 85.32 5.88 18.43 7.59 3.08 0.76 3.90 1.00 398.19 1,481 204 1,685 881.29 464.47 283.77 88.46 48.89 2.62 32.73 6.36 96.21 6.93 21.31 8.95 3.59 0.91 4.52 1.18 428.55 1,718 234 1,952 900.46 472.81 289.64 90.71 50.08 2.70 33.88 6.49 98.87 7.09 21.92 9.22 3.69 0.93 4.69 1.21 451.49 1,754 241 1,994 784.53 415.51 256.07 79.60 43.91 2.36 29.05 6.25 87.46 6.20 19.14 7.98 3.18 0.82 4.01 1.05 389.40 1,536 211 1,747 677.01 355.06 222.51 69.06 38.24 2.25 25.45 6.28 77.30 5.35 16.73 6.88 2.77 0.70 3.57 0.91 360.63 1,324 186 1,510 759.61 401.86 240.41 75.12 41.67 2.16 27.86 7.78 77.93 5.58 17.36 7.20 2.90 0.77 3.79 0.98 345.06 1,477 196 1,673 718.66 381.27 229.30 71.28 39.49 2.12 26.02 6.50 74.84 5.45 16.37 6.88 2.77 0.74 3.55 0.93 348.42 1,401 186 1,586 680.21 358.22 218.13 68.24 37.60 2.07 24.49 6.00 70.74 5.09 15.47 6.43 2.57 0.69 3.38 0.86 322.34 1,325 175 1,500 658.74 351.36 209.09 65.50 35.93 2.07 24.07 6.85 71.15 4.92 15.20 6.36 2.59 0.71 3.29 0.90 339.23 1,285 174 1,459 464.09 241.90 152.27 46.79 27.35 1.83 19.49 9.85 61.01 4.33 13.32 5.56 2.26 0.61 2.86 0.76 330.19 905 149 1,054 512.57 267.86 163.22 49.56 28.11 1.77 19.35 6.79 57.29 3.96 12.37 5.16 2.17 0.58 2.70 0.73 292.97 993 141 1,134 462.46 241.41 141.33 43.90 24.10 1.40 15.87 9.29 45.15 3.06 9.38 3.97 1.64 0.47 2.13 0.57 232.66 889 117 1,006 448.10 234.52 139.47 43.90 23.34 1.20 14.52 5.07 40.85 2.67 8.41 3.44 1.36 0.38 1.90 0.45 218.42 866 104 970 - PROCESSING Ore to Processing 34,550 %U3O8 ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm 0.040% 657.05 346.12 210.56 65.49 36.34 2.05 24.30 7.12 71.39 5.04 15.54 6.48 2.62 0.69 3.36 0.88 338.14 1,304 179 1,483 Recovery U3O8 Recovery CeO2 Recovery La2O3 Recovery Nd2O3 Recovery Pr6O11 Recovery Sm2O3 Recovery Eu2O3 Recovery Gd2O3 Recovery Sc2O3 Recovery Y2O3 Recovery Yb2O3 Recovery Dy2O3 Recovery Er2O3 Recovery Ho2O3 Recovery Lu2O3 Recovery Tb4O7 Recovery Tm2O3 Recovery Th % % % % % % % % % % % % % % % % % % Recovered U3O8 Recovered CeO2 Recovered La2O3 Recovered Nd2O3 Recovered Pr6O11 Recovered Sm2O3 Recovered Eu2O3 Recovered Gd2O3 Recovered Sc2O3 Recovered Y2O3 Recovered Yb2O3 Recovered Dy2O3 Recovered Er2O3 Recovered Ho2O3 Recovered Lu2O3 Recovered Tb4O7 Recovered Tm2O3 Recovered Th Recovered LREO Recovered HREO Total REOs 000 lbs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 lbs 3,287 3,284 3,284 3,283 3,278 3,279 3,253 3,280 3,282 3,279 1,214 - 0.054% 829.93 435.66 269.03 83.94 46.14 2.53 30.68 6.17 91.65 6.49 20.10 8.38 3.38 0.85 4.26 1.11 415.83 3,199 439 3,637 546 0.058% 900.46 472.81 289.64 90.71 50.08 2.70 33.88 6.49 98.87 7.09 21.92 9.22 3.69 0.93 4.69 1.21 451.49 1,754 241 1,994 0.052% 784.53 415.51 256.07 79.60 43.91 2.36 29.05 6.25 87.46 6.20 19.14 7.98 3.18 0.82 4.01 1.05 389.40 1,536 211 1,747 0.044% 677.01 355.06 222.51 69.06 38.24 2.25 25.45 6.28 77.30 5.35 16.73 6.88 2.77 0.70 3.57 0.91 360.63 1,324 186 1,510 0.045% 759.61 401.86 240.41 75.12 41.67 2.16 27.86 7.78 77.93 5.58 17.36 7.20 2.90 0.77 3.79 0.98 345.06 1,477 196 1,673 0.045% 718.66 381.27 229.30 71.28 39.49 2.12 26.02 6.50 74.84 5.45 16.37 6.88 2.77 0.74 3.55 0.93 348.42 1,401 186 1,586 0.036% 680.21 358.22 218.13 68.24 37.60 2.07 24.49 6.00 70.74 5.09 15.47 6.43 2.57 0.69 3.38 0.86 322.34 1,325 175 1,500 0.036% 658.74 351.36 209.09 65.50 35.93 2.07 24.07 6.85 71.15 4.92 15.20 6.36 2.59 0.71 3.29 0.90 339.23 1,285 174 1,459 0.037% 464.09 241.90 152.27 46.79 27.35 1.83 19.49 9.85 61.01 4.33 13.32 5.56 2.26 0.61 2.86 0.76 330.19 905 149 1,054 0.032% 512.57 267.86 163.22 49.56 28.11 1.77 19.35 6.79 57.29 3.96 12.37 5.16 2.17 0.58 2.70 0.73 292.97 993 141 1,134 0.020% 462.46 241.41 141.33 43.90 24.10 1.40 15.87 9.29 45.15 3.06 9.38 3.97 1.64 0.47 2.13 0.57 232.66 889 117 1,006 0.018% 448.10 234.52 139.47 43.90 23.34 1.20 14.52 5.07 40.85 2.67 8.41 3.44 1.36 0.38 1.90 0.45 218.42 866 104 970 0.000% - 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% Recovery 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 44,942 23,227 14,210 4,425 2,355 123 1,496 331 4,127 272 882 364 142 39 200 49 20,605 86,804 10,381 97,185 27,491 20,386 10,535 6,446 2,007 1,068 56 678 150 1,872 123 400 165 64 18 91 22 9,346 39,374 4,709 44,083 97,185 583 407 210 130 41 21 1 14 2 38 3 8 3 1 0 2 0 182 788 94 882 3,776 2,658 1,369 843 264 140 7 90 13 247 17 54 22 9 2 12 3 1,187 5,135 615 5,750 3,413 2,314 1,202 745 232 123 6 77 13 218 14 47 19 7 2 10 3 1,023 4,493 539 5,033 2,855 1,997 1,027 647 201 107 6 68 13 193 12 41 17 6 2 9 2 948 3,873 475 4,348 2,960 2,240 1,162 699 219 116 6 74 16 194 13 42 17 7 2 10 2 906 4,320 499 4,819 2,926 2,115 1,101 666 207 110 5 69 13 186 13 40 17 6 2 9 2 914 4,089 473 4,562 2,374 2,003 1,035 634 198 105 5 65 12 176 12 38 16 6 2 9 2 846 3,870 447 4,317 2,350 1,925 1,007 603 189 99 5 63 14 176 11 37 15 6 2 8 2 883 3,723 439 4,162 2,422 1,367 699 443 136 76 5 52 20 152 10 33 13 5 1 7 2 867 2,645 376 3,021 2,111 1,511 774 475 144 79 5 51 14 143 9 30 13 5 1 7 2 769 2,904 358 3,262 1,298 1,362 697 411 128 67 4 42 19 112 7 23 10 4 1 5 1 610 2,597 295 2,893 423 489 251 150 47 24 1 14 4 38 2 8 3 1 0 2 0 212 937 98 1,034 www.rpacan.com Rev. 0 Page 1-4 000s tonnes Uranium Grade CeO2 Grade La2O3 Grade Nd2O3 Grade Pr6O11 Grade Sm2O3 Grade Eu2O3 Grade Gd2O3 Grade Sc2O3 Grade Y2O3 Grade Yb2O3 Grade Dy2O3 Grade Er2O3 Grade Ho2O3 Grade Lu2O3 Grade Tb4O7 Grade Tm2O3 Grade Th Grade LREO Grade HREO Grade Total REO Grade Head Grade Year -2 Inputs Units Year -1 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Total REVENUE Gross Revenue Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 U3O8 CeO2 La2O3 Nd2O3 Pr6O11 Sm2O3 Eu2O3 Gd2O3 Sc2O3 Y2O3 Yb2O3 Dy2O3 Er2O3 Ho2O3 Lu2O3 Tb4O7 Tm2O3 Sub-Total LREOs Sub-Total HREOs Sub-Total REOs Total Gross Revenue US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s Exchange Rate 1 US$=C$ REO Basket Price Gross Revenue C$ '000s $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 70 18 20 175 140 80 2,900 150 3,000 150 90 1,450 195 1,200 2,200 3,000 $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 1,924,376 366,941 210,708 1,127,993 280,988 85,468 162,090 101,756 450,732 280,814 11,094 579,933 32,232 21,280 199,912 67,163 1,986,631 1,992,474 3,979,104 5,903,481 $ $ 90 5,903,481 $40,804 $7,331 $4,195 $22,795 $5,696 $1,717 $3,168 $2,032 $6,183 $5,702 $226 $11,867 $659 $0 $412 $4,011 $1,338 $40,017 $37,314 $77,332 $118,135 1.00 1.00 $ $264,346 $47,837 $27,381 $147,601 $37,023 $11,205 $20,336 $13,494 $39,129 $36,995 $1,485 $77,812 $4,359 $0 $2,713 $26,563 $8,775 $259,842 $242,867 $502,710 $767,055 1.00 $238,883 $41,649 $24,045 $130,398 $32,465 $9,819 $17,761 $11,564 $37,632 $32,705 $1,297 $67,894 $3,771 $0 $2,401 $22,688 $7,656 $228,557 $215,188 $443,745 $682,628 1.00 $199,859 $35,940 $20,546 $113,305 $28,166 $8,550 $16,910 $10,130 $37,786 $28,903 $1,121 $59,341 $3,250 $0 $2,037 $20,192 $6,616 $197,956 $194,836 $392,793 $592,652 1.00 $207,172 $40,312 $23,248 $122,384 $30,629 $9,313 $16,224 $11,085 $46,831 $29,128 $1,168 $61,555 $3,403 $0 $2,242 $21,453 $7,105 $216,573 $209,508 $426,081 $633,253 1.00 $204,808 $38,074 $22,019 $116,529 $29,011 $8,812 $15,900 $10,338 $39,028 $27,927 $1,137 $57,958 $3,245 $0 $2,165 $20,061 $6,726 $205,633 $193,297 $398,930 $603,737 1.00 $166,176 $36,052 $20,697 $110,900 $27,785 $8,394 $15,539 $9,732 $36,075 $26,408 $1,062 $54,786 $3,032 $0 $2,007 $19,069 $6,255 $195,434 $182,360 $377,795 $543,971 1.00 $164,503 $34,642 $20,142 $105,473 $26,464 $7,959 $15,390 $9,492 $40,831 $26,352 $1,019 $53,410 $2,976 $0 $2,061 $18,458 $6,492 $186,720 $184,439 $371,159 $535,663 1.00 $169,567 $24,608 $13,982 $77,447 $19,060 $6,108 $13,747 $7,749 $59,251 $22,787 $906 $47,190 $2,623 $0 $1,767 $16,160 $5,530 $135,096 $183,816 $318,912 $488,478 1.00 $147,739 $27,192 $15,490 $83,056 $20,198 $6,282 $13,282 $7,696 $40,852 $21,406 $828 $43,866 $2,439 $0 $1,692 $15,264 $5,312 $145,935 $158,917 $304,853 $452,592 1.00 $90,895 $24,511 $13,948 $71,853 $17,874 $5,379 $10,506 $6,307 $55,851 $16,856 $638 $33,230 $1,873 $0 $1,374 $12,029 $4,136 $128,185 $148,179 $276,364 $367,259 1.00 $29,625 $8,793 $5,017 $26,253 $6,618 $1,929 $3,328 $2,136 $11,284 $5,647 $207 $11,025 $600 $0 $410 $3,964 $1,223 $46,680 $41,751 $88,432 $118,057 1.00 88 $ $118,135 87 $ $767,055 88 $ $682,628 90 $ $592,652 88 $ $633,253 87 $ $603,737 88 $ $543,971 89 $ $535,663 106 $ $488,478 93 $ $452,592 96 $ $367,259 86 $118,057 $7,880 $2,825 $10,705 12 $ 13.8% $51,346 $18,453 $69,799 12 $ 13.9% $44,931 $16,182 $61,113 12 $ 13.8% $38,726 $14,254 $52,980 12 $ 13.5% $43,201 $14,981 $58,181 12 $ 13.7% $40,893 $14,178 $55,071 12 $ 13.8% $38,699 $13,404 $52,103 12 $ 13.8% $37,234 $13,171 $50,405 12 $ 13.6% $26,449 $11,292 $37,741 12 $ 11.8% $29,040 $10,736 $39,776 12 $ 13.0% $25,974 $8,860 $34,833 12 $ 12.6% $9,366 $2,928 $12,294 12 13.9% Offsite Concentrate Costs LREOs HREOs Total C$ '000s C$ '000s C$ '000s C$/kg % of Gross $ $ 10.00 30.00 $ $ $ $ 393,737 141,264 535,002 12 13.4% $ Net Revenue Uranium Rare Earths Total Net Revenue C$ '000s C$ '000s C$ '000s $ $ $ 1,924,376 3,444,103 5,368,479 $40,804 $66,627 $107,431 $264,346 $432,911 $697,256 $238,883 $382,632 $621,515 $199,859 $339,813 $539,672 $207,172 $367,900 $575,072 $204,808 $343,858 $548,666 $166,176 $325,691 $491,867 $164,503 $320,755 $485,258 $169,567 $281,171 $450,737 $147,739 $265,077 $412,816 $90,895 $241,531 $332,425 $29,625 $76,137 $105,762 NSR Royalty NSR Royalty Total Royalty Paid C$ '000s C$ '000s C$ '000s 0.75% $ 0.00% $ $ 40,264 40,264 $806 $0 $806 $5,229 $0 $5,229 $4,661 $0 $4,661 $4,048 $0 $4,048 $4,313 $0 $4,313 $4,115 $0 $4,115 $3,689 $0 $3,689 $3,639 $0 $3,639 $3,381 $0 $3,381 $3,096 $0 $3,096 $2,493 $0 $2,493 $793 $0 $793 Net Smelter Return $106,625 $195 $692,027 $211 $616,854 $188 $535,625 $163 $570,759 $174 $544,551 $166 $488,178 $149 $481,618 $148 $447,357 $136 $409,720 $125 $329,932 $101 $104,969 $86 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 C$ '000s C$/t $ OPERATING COSTS Mining Processing G&A Total Opex Per Tonne Milled C$/t mined C$/t milled C$/t milled C$/t milled $ $ $ $ 42.64 26.31 3.44 72.40 Mining Processing G&A Total Operating Cost C$ '000s C$ '000s C$ '000s C$ '000s $ $ $ $ 1,473,308 909,013 119,013 2,501,334 $28,519 $0 $0 $28,519 $32,959 $14,378 $0 $47,336 $136,462 $86,472 $11,503 $234,438 $136,365 $86,410 $11,495 $234,270 $136,359 $86,407 $11,495 $234,260 $136,320 $86,382 $11,491 $234,193 $136,085 $86,233 $11,472 $233,790 $136,144 $86,270 $11,476 $233,891 $135,080 $85,597 $11,387 $232,064 $136,200 $86,306 $11,481 $233,987 $136,266 $86,348 $11,487 $234,101 $136,143 $86,270 $11,476 $233,889 $50,405 $31,940 $4,249 $86,594 Operating Margin C$ '000s $ 2,826,882 -$28,519 $59,288 $457,589 $382,583 $301,365 $336,566 $310,761 $254,288 $249,554 $213,370 $175,619 $96,043 $18,375 $0 $0 $86,420 $7,300 $165,366 $33,926 $20,215 $3,000 $47,620 $35,000 $30,909 $7,300 $82,683 $16,963 $10,107 $3,000 $10,000 $17,000 $30,276 $9,404 $5,963 $6,977 $2,891 41.52 26.31 3.50 C$ '000s C$ '000s C$ '000s C$ '000s C$ '000s C$ '000s C$ '000s C$ '000s $86,802 $7,300 $165,366 $33,926 $20,215 $3,000 $47,620 C$ '000s C$ '000s C$ '000s $12,000 $67,561 $35,000 $12,000 $67,561 $35,000 $6,000 $33,781 $17,500 $6,000 $33,781 $17,500 C$ '000s C$ '000s C$ '000s 30% 25% $89,210 $18,396 $562,843 $46,150 $9,227 $290,620 $43,060 $9,169 $272,224 C$ '000s C$ '000s C$ '000s $24,000 $22,000 $667,013 $3,000 $3,000 $3,000 $3,000 $290,620 $272,224 $19,404 $8,963 $26,389 $5,891 $3,000 $3,000 $2,000 $5,000 $3,000 $2,000 $11,523 $3,000 $3,000 $6,000 $3,000 $2,000 $5,000 $2,000 $2,000 $8,000 $8,000 $2,000 $2,000 $1,000 $1,000 PRE-TAX CASHFLOW Pre-Tax Cash Flow Cumulative C$ '000s C$ '000s $2,159,868 -$319,139 -$319,139 -$212,935 -$532,074 $438,185 -$93,889 $373,620 $279,731 $274,976 $554,706 $330,675 $885,381 $307,761 $1,193,142 $249,288 $1,442,430 $238,031 $1,680,462 $207,370 $1,887,831 $170,619 $2,058,450 $94,043 $2,152,493 $10,375 $2,162,868 -$2,000 $2,160,868 -$1,000 $2,159,868 PROJECT ECONOMICS Pre-Tax IRR Pre-Tax NPV Pre-Tax NPV Pre-Tax NPV C$ '000s C$ '000s C$ '000s Sustaining Capital Site Decomissioning and Monitoring Total Capital Cost 5% 7.5% 10% 50% $1,475,351 $1,226,684 $1,022,820 $82,683 $16,963 $10,107 $14,685 $8,000 $16,412 $6,523 $10,000 www.rpacan.com Rev. 0 Page 1-5 CAPITAL COSTS Directs Mining Process Site Development Acid Baking Plant Uranium Extraction Plant Y & REE Plant Water Treatment Plant Tailings Site infrastructure Indirects Mine Indirects Process Indirects Construction Indirects Contingency Process Contingency Mining & Other Contingency Total Initial Capital $ $ $ 5,328,215 $154 www.rpacan.com CASH FLOW RESULTS The cash flow analysis in this report has been carried out on a pre-tax basis. Considering the Project on a stand-alone basis, the undiscounted pre-tax cash flow totals C$2.1 billion over the mine life and simple payback occurs 1.5 years after the start of commercial production. The internal rate of return (IRR) is 50% and the net present value (NPV) is as follows: C$1.5 billion at a 5% discount rate C$1.2 billion at a 7.5% discount rate C$1.0 billion at a 10% discount rate The economic analysis contained in this report is based, in part, on Inferred Resources, and is preliminary in nature. Inferred Resources are considered too geologically speculative to have mining and economic considerations applied to them and to be categorized as Mineral Reserves. There is no certainty that economic forecasts on which this Preliminary Economic Assessment is based will be realized. SENSITIVITY ANALYSIS Sensitivity analyses were performed for uranium price, REO prices, operating cost, capital cost, uranium recovery, and rare earth recoveries. The sensitivity analyses on IRR and NPV at a discount rate of 10% indicate that the Project economics are most heavily influenced by the recovery and market price of REEs. The Project economics are also heavily influenced by the operating cost. These sensitivities focus on rare earth oxides, which provide approximately 64% of the base case revenue whereas uranium provides approximately 36% of the base case revenue. The recent price history for rare earths covers a wide range, including order-ofmagnitude increases within 2011. The rare earths price sensitivity is based on results at a conservative long-term forecast ($30/kg basket price), the base case ($90/kg basket price), and current prices ($103/kg basket price). Note that these basket prices relate to gross revenue, before charges for separation are applied. Figure 1-1 and Table 1-2 summarize the results of the sensitivity analyses. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 1-6 www.rpacan.com FIGURE 1-1 SENSITIVITY ANALYSIS $2,000,000 NPV @ 10% ('000s) $1,600,000 REE Recovery $1,200,000 U3O8 Recovery REE Price $800,000 U3O8 Price Operating Costs $400,000 Capital Costs $0 ‐40% ‐30% ‐20% ‐10% 0% 10% 20% 30% 40% Factor of Change Note: U3O8 recovery has the same slope as U3O8 price. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 1-7 www.rpacan.com TABLE 1-2 SENSITIVITY ANALYSIS Pele Mountain Resources Inc. – Eco Ridge Mine Project Factor 0.72 0.86 1 1.14 1.29 U3O8 Market Price U3O8 Price (US$/lb) NPV (C$ millions) 50 728 60 875 70 1,022 80 1,171 90 1,319 IRR (%) 35% 45% 50% 57% 60% Factor 0.33 0.66 1 1.14 REO Basket Price REO Price (US$/kg) NPV (C$ millions) 30 (381) 60 324 90 1,022 103 1,316 IRR (%) NA 26% 50% 59% Operating Cost Per Tonne Milled Opex (C$/t) NPV (C$ millions) IRR (%) Factor 0.8 0.9 1 1.1 1.2 Factor 0.8 0.9 1 1.1 1.2 Factor 0.85 0.925 1 1.075 1.15 58 65 71 80 87 1,278 1,151 1,022 895 767 Capital Cost Capex (C$ millions) NPV (C$ millions) 534 600 667 734 800 1,132 1,077 1,022 968 914 Recovery - REE Average Recovery NPV (C$ millions) 68% 751 74% 887 79% 1,022 85% 1,159 90% 1,295 58% 54% 50% 46% 42% IRR (%) 63% 56% 50% 46% 41% IRR (%) 42% 46% 50% 54% 58% EXTENDED MINE LIFE SENSITIVITY The MCB is known to persist to the north of the current resource model, as indicated by historical drilling. RPA examined the effect of extending the mine life to include an additional 50 Mt of production from the MCB, resulting in a mine life of 25 years. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 1-8 www.rpacan.com The undiscounted pre-tax cash flow for the extended mine life sensitivity totals C$6.5 billion with an IRR of 51%. The net present value (NPV) is as follows: C$3.2 billion at a 5% discount rate C$2.3 billion at a 7.5% discount rate C$1.7 billion at a 10% discount rate Given the long mine life, RPA also looked at a higher production rate for this extended mine life sensitivity, increasing production from 9,000 tpd to 12,000 tpd while using the same mining method. A summary of the key inputs and criteria in developing the 12,000 tpd option is illustrated below. LOM of 20 years Higher capital costs for larger operation: o Initial capital cost of C$661 million o Total capital cost of C$838 million Lower operating costs of C$69 per tonne of ore mined, The undiscounted pre-tax cash flow in this case totals C$6.6 billion. The IRR is 53% and the NPV is as follows: C$3.6 billion at a 5% discount rate C$2.7 billion at a 7.5% discount rate C$2.1 billion at a 10% discount rate CONCLUSIONS In RPA’s opinion, the PEA indicates that positive economic results can be obtained for the Eco Ridge Mine Project, in a scenario that includes room and pillar mining, and uranium and rare earth recovery by conventional milling. The Base Case LOM plan for the Project indicates that 34.6 Mt, at average grades of 0.040% U3O8 and 1,455 g/t TREO, will be mined over 11 years at a nominal production rate of 9,000 tpd. Uranium production is projected to total 27.5 million pounds, and REO production is projected to total 44.1 million kilograms. The Project has good potential for increasing the base case mine life. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 1-9 www.rpacan.com Specific conclusions by area of the PEA are as follows. GEOLOGY AND RESOURCES Rare earth and uranium mineralization on the Eco Ridge property is hosted primarily by the Main Conglomerate Bed (MCB) and the Hangingwall Zone (HWZ) located within the Ryan Member of the Mississagi Quartzite. On average, the MCB is 2.7 m thick and dips consistently at an average of -21o north. The HWZ, located immediately above the MCB, is defined by economic limits. The current Mineral Resource estimate is listed in Table 1-3. TABLE 1-3 SUMMARY OF MINERAL RESOURCES – APRIL 16, 2012 Pele Mountain Resources Inc. – Eco Ridge Mine Project Tonnes U3O8 U3O8 LREO HREO TREO TREO (000) (%) (000 lbs) (ppm) (ppm) (ppm) (000 lbs) MCB 20,514 0.045 20,447 1,426 193 1,618 73,184 HWZ 28,223 0.012 7,214 733 88 821 51,111 Total 48,737 0.026 27,661 1,025 132 1,157 124,295 MCB 16,906 0.043 15,940 1,279 183 1,463 54,515 HWZ 20,956 0.013 5,822 713 95 808 37,329 Total 37,863 0.026 21,762 966 134 1,100 91,843 Zone & Classification Indicated Inferred Notes: 1. 2. 3. 4. 5. 6. CIM definitions were followed for Mineral Resources. Mineral Resources were estimated at a cut-off value of $100 per tonne for the MCB, and $50 per tonne for the HWZ. Values were calculated based on prices and recoveries of uranium and rare earths, net of off-site rare earth separation costs. Mineral Resources were estimated using an average uranium price of US$70 per lb U3O8, a rare earth “basket price” of $78 per kg (net of separation charges), and a C$:US$ exchange rate of 1.00:1.00. A minimum mining thickness of 1.8 m was used for the MCB. Light Rare Earth Oxides include La2O3, CeO2, Pr6O11, and Nd2O3. Heavy Rare Earth Oxides include Sm2O3, Eu2O3, Gd2O3, Tb4O7, Dy2O3, Ho2O3, Er2O3, Tm2O3, Yb2O3, Y2O3, and Lu2O3. Sc2O3 is also included in HREO, as it occurs in low concentrations and carries high unit values like an HREO. Historic drilling has intersected the MCB to the west, to the east, and down-dip from the current Mineral Resource. A target for further exploration was estimated for these areas, Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 1-10 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com consisting of a further 40 Mt to 60 Mt, grading from 0.030% to 0.050% U3O8, accompanied by 0.12% to 0.18% TREO for the MCB. The potential quantities and grades of the exploration targets are conceptual in nature and there has been insufficient drilling to define a Mineral Resource. It is uncertain if further exploration will result in the definition of a mineral resource in these areas. MINING The MCB is correlated with the “Pardee Reef” in the Nordic Channel. This reef was mined at the adjacent Nordic and Stanleigh mines operated by Rio Algom between 1957 and 1996. A number of mining methods have been assessed by RPA and others for extraction of the MCB mineralization. The selected mining method was room and pillar, with both development and production contained within the mineralized zone. The development and production tonnage will be loaded into trucks and transported to surface for processing. Although the MCB average mining thickness is 2.7 m, in RPA’s opinion, the deposit will support a high production rate. The lateral extents are such that multiple accesses from surface are feasible, providing many independent workplaces. The use of conveyors instead of haul trucks for material handling, while not included in the base case, may provide economic advantages, and is worth consideration in future studies. Particular attention should be paid to impacts on grade distribution in production schedules for each option, as there may be less flexibility with conveyors, offsetting the cost advantage that they provide. In RPA’s opinion, conveyors may also provide operational advantages that are difficult to quantify economically at this stage of the Project, including better mine ventilation, reduced traffic on the ramps, and easier material handling as the mine extends at depth. Geotechnical and hydrogeological assumptions are supported by historic operations in Elliot Lake, however, require confirmation by data collection and analysis at the Project. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 1-11 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com PROCESSING AND METALLURGY Historically, mining and processing operations have been carried out in the Elliot Lake area, but not on the Eco Ridge Mine property. The major portion of the ore mined was processed through a conventional uranium processing plant, with some production from underground leaching on run-of-mine ore. Yttrium oxide and rare earth oxides were also recovered at the Denison Mine in the past, as by-products of the uranium production. RPA has observed that the metallurgical program supporting the current Project flowsheet has been dynamic, involving changes in pursuit of potential improvements on relatively short notice. The unit operations within the process flowsheet have been tested at various times, using different metallurgical samples, which is not unusual at the PEA stage of project development. The testwork to date has focused on optimizing rare earths recoveries, and although the overall uranium recovery assumption has not been verified by testwork, it is typical of that achieved in historical operations. The assumed recovery is supported by excellent results achieved for uranium in the acid bake unit operation. RPA made a number of assumptions in assembling the various testwork results into a coherent overall recovery for each element. The data used for the PEA is preliminary in nature and, therefore, indicative of the results that may be expected after a more rigorous and thorough program of metallurgical testing is conducted. The actual results achieved in the long term may vary significantly if a plant is ultimately constructed and operated, particularly since the current design is based on many assumptions. That being said, the processes that have been tested are not optimized and, based on that observation, it is reasonable to expect that the results may also be better. ENVIRONMENT Preliminary baseline aquatic and terrestrial environmental studies have been performed and no environmental problems have been identified to date. In order to identify all potential environmental risks pertaining to the Project, Human Health and Ecological Risk Assessments will need to be conducted during the Environmental Assessment (EA) process. The assessments will be completed in full matrices, with the highest ranking environmental risks being identified along with corresponding abatement strategies listed in table format. Because of the extensive documented experience in the Elliot Lake Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 1-12 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com mining camp with uranium mine operations and decommissioning, it is expected that all significant risks can be effectively managed. MARKETS Uranium A uranium price of US$70/lb U3O8 has been used in this PEA, based on independent metal price forecasts from banks and financial institutions. RPA notes that the price used in the PEA, while slightly above the long term price for U3O8, is within the range of medium- to long-term forecasts. Rare Earths The market for rare earth products is currently relatively small but growing rapidly for certain rare earths. Public information on price forecasts and sales terms are difficult to obtain and vary within a wide range. Current prices are tracked by sources such as Asian Metal and Metal-PagesTM, based on transactions. Recent history shows international rare earth market prices growing at an unprecedented rate since China cut export quotas by approximately 40% in 2011. China’s overwhelming control on the rare earth supply chain, from upstream mining to downstream processing and end-user products, is likely to remain intact on all but a few materials through 2016. Rare earth prices are expected to remain volatile in the short term. A small number of REE producers outside of China are likely to be in operation by the time the Eco Ridge Mine Project is developed. This is expected to saturate the market for LREO such as lanthanum and cerium, however, demand for high-value HREO (such as dysprosium) is expected to grow, and supply is expected to remain in deficit. Price forecasting in this environment is difficult, and certain to contain wide margins of error. RPA selected rare earth prices within a range of available forecasts. Prices for certain elements are higher than current prices, and for others, lower, however the average basket price is approximately 13% lower than Q2 2012 prices. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 1-13 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com RPA considers these rare earths prices to be appropriate for a PEA-level study, however, we note that the recent market volatility introduces considerably more uncertainty than a comparable base or precious metals project. RECOMMENDATIONS RPA recommends that Pele Mountain continue collecting data to support the feasibility and licensing process, and move on to more advanced engineering studies. Specific recommendations are as follows: Continue infill drilling programs to advance the Inferred Resources to Indicated classification. The budget presented below includes resource drilling. Carry out geotechnical and hydrogeological studies to confirm the parameters for mining without adversely impacting ground stability. Undertake a systematic metallurgical testing program. Care should be taken to collect samples that are representative of the material that will be processed over the LOM. An outline of the testing program should be developed prior to the time the samples are collected and sufficient amounts of materials should be shipped to the testing facility to complete the testing that is required for the next phase of the project development. RPA also recommends that SNC Lavalin continue to liaison and coordinate with the testing laboratory to oversee the testing parameters and to review the results as they become available. This will help to ensure that the data meets the requirements of producing design information that is needed to support the Feasibility Study. The metallurgical program should be planned, budgeted, and scheduled to integrate with other aspects of the project. Future testing programs must also include tests to evaluate the processes to precipitate uranium oxide and rare earth carbonate concentrates to determine the processing parameters required for the plant design. Continue to evaluate rare earth separation opportunities for upgrading the rare earth concentrate to separated rare earth oxides. Continue baseline studies in preparation for an EA, and the licensing process. Continue public consultation. Once the project activities have been sufficiently defined and funding for the Feasibility Study and licensing process is secured, an application should be submitted to the Canadian Nuclear Safety Commission (CNSC) to construct Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 1-14 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com the Eco Ridge Mine and the EA process should continue by submitting a revised Project Description to the Major Projects Management Office. Continue the EA process based on EA Guidelines (to be provided by the CNSC / Canadian Environmental Assessment Act (CEAA)) and the licensing process in consultation with CNSC. Monitor developments in REO and uranium markets, including forecast market prices based on supply and demand fundamentals for each of the rare earths and uranium. Based on Pele Mountain’s intention to advance the Project to the feasibility stage, RPA has recommended the proposed program. The objectives of the proposed program are to assess the opportunities, while advancing the studies supporting the feasibility and licensing process. A budget is presented in Table 1-4. TABLE 1-4 PROPOSED WORK PROGRAM AND ESTIMATED COST Pele Mountain Resources Inc. – Eco Ridge Mine Project Item Infill Drill Program Cost (C$ millions) 5.6 Geotechnical Studies 0.7 Metallurgical Testwork 0.7 Feasibility Study 8.0 Environmental Baseline Monitoring 1.5 Permitting Activities 4.5 Government Agency Project Review 1.5 Contingency 2.5 Total 25.0 A schedule for the Project, covering the path forward through a Feasibility Study, permitting, and construction, is presented in Figure 1-2. The critical path runs through the permitting process, although this is influenced by the availability of sufficient engineering work being completed as needed for key permitting documents. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 1-15 Technical Report NI 43-101 – June 20, 2012 Activity ID Activity Name Original Start Duration Environmental EIA (SENES) Finish 2012 2013 J F M A M J Jul A S O N D J F M A M J J A S O N D 1463 03-Jan-12 10-Nov-17 1463 03-Jan-12 10-Nov-17 1463 03-Jan-12 10-Nov-17 1463 03-Jan-12* 10-Nov-17 S50810 Consultation S50760 Submit Project Description to CNSC S50770 Baseline Characterization Program/Reporting 427 03-Jul-12 24-Mar-14 F3310 Environment Impact Statement 427 27-Sep-12 19-Jun-14 S50800 Other Authorisations 488 28-Mar-13 19-Mar-15 S50780 Regulatory Review and EA Decision Statement 190 19-Jun-14 30-Mar-15 S50790 Issue Site Preparation / Construction Licences 122 06-Jan-15 02-Jul-15 220 01-Aug-12 24-Jun-13 220 01-Aug-12 24-Jun-13 220 01-Aug-12 24-Jun-13 Preliminary Mine Site Study Geotechnical MINE SITE - RPA 60 03-Jul-12* 60 01-Aug-12* Hydrogeological Study S50730 Underground Geotechnical Studies 120 01-Aug-12 29-Jan-13 F3290 Resource Drilling 160 01-Aug-12 27-Mar-13 S50720 Resource Update 60 28-Mar-13 24-Jun-13 248 02-Jan-13 13-Dec-13 240 02-Jan-13 13-Dec-13 240 02-Jan-13 13-Dec-13 Key Milestones GENERAL F1160 Commence Feasibility Study F1150 Feasibility Study Complete Engineering MINE SITE S50750 Feasibility Mine Design & Cost Estimation 26-Oct-12 0 13-Dec-13* 26-Sep-13 120 02-Jan-13 25-Jun-13 120 02-Jan-13 25-Jun-13 180 10-Jan-13 18-Sep-13 Process Engineering 165 10-Jan-13 05-Sep-13 49E0030 Engineering Design & MTO's 140 07-Mar-13 18-Sep-13 49E0020 Plant Layouts 110 04-Apr-13 04-Sep-13 180 10-Jan-13 26-Sep-13 180 10-Jan-13 26-Sep-13 157 18-Mar-13 28-Oct-13 157 18-Mar-13 28-Oct-13 157 18-Mar-13 28-Oct-13 60 19-Sep-13 13-Dec-13 60 19-Sep-13 13-Dec-13 60 19-Sep-13 13-Dec-13 1-16 TAILINGS FACILITY F2970 Tailings Facility Design & MTO's Procurement F1840 Equipment/Installation Contract Pricing Estimate Compilation F2780 Estimate Compilation & Review F1190 Handover to Client 0 Project Execution Key Milestones GENERAL KM10 Contract Award for Execution KM20 Project Completion 05-Dec-16 718 21-Jan-14 05-Dec-16 718 21-Jan-14 05-Dec-16 06-May-15 310 04-Feb-14 06-May-15 310 04-Feb-14 06-May-15 TF0010 Tailings Facility Design 150 04-Mar-14 06-Oct-14 530 15-Apr-14 08-Jun-16 530 15-Apr-14 08-Jun-16 Procurement 240 15-Apr-14 08-Apr-15 F3220 Manufacture & Deliver to Site 490 13-Jun-14 08-Jun-16 359 02-Jul-15 05-Dec-16 359 02-Jul-15 05-Dec-16 F3320 Construction Permits Available F3240 Site Establishment F3330 Construction Monitoring for Tailings Facility F3250 Site Work F3340 Continue Construction Monitoring for Tailings Facil ity 80 18-Apr-16 09-Aug-16 F3260 Commissioning 60 12-Sep-16 05-Dec-16 Actual Work Critical Remaining Work Milestone June 2012 Project Schedule 0 02-Jul-15 100 02-Jul-15 24-Nov-15 80 23-Jul-15 17-Nov-15 299 30-Jul-15 10-Oct-16 Source: SNC Lavalin, 2012. www.rpacan.com F3230 Remaining Work Elliot Lake, Ontario, Canada 05-Dec-16* 310 04-Feb-14 Engineering Design for Process Plant Construction Eco Ridge Mine Project 0 21-Jan-14 49010 Procurement Pele Mountain Resources Inc. 13-Dec-13 718 21-Jan-14 0 Engineering Figure 1-2 0 02-Jan-13* 192 02-Jan-13 49E0010 PROCESS PLANT A S O N 26-Sep-12 S50740 Feasibility Study 2014 2015 2016 2017 J F M A M J J A S O N D J F M A M J Jul A S O N D J F M A M J J A S O N D J F M A M J J www.rpacan.com TECHNICAL SUMMARY PROPERTY LOCATION, ACCESS AND INFRASTRUCTURE The Eco Ridge Mine property is located in northern Ontario, approximately 11 km east of the City of Elliot Lake and 400 km northwest of Toronto. The Project is located in Gunterman, Deagle, Gaiashk, Joubin, and Proctor townships, District of Algoma. It is centred at approximately Universal Transverse Mercator (UTM) coordinates 384000E and 5138000N (NAD 83, Zone 17). Highway 108 crosses the western portion of the Eco Ridge property. The turn-off for the access road to the property from Highway 108 is located three kilometres south of Elliot Lake. The road is a public road. The west boundary of the property is located four kilometres from the turn-off. The road extends across the property and in this area is suitable for access by all-wheel drive vehicles only, during some of the year. LAND TENURE The Eco Ridge Mine property consists of 38 mining claims totalling 392 claim units and two mining leases covering approximately 7,822 ha in the Sault Ste. Marie Mining Division. Pele Mountain’s interest in the above mining claims was acquired by staking and by entering into purchase agreements and mining leases. As of the effective date of this report, all of the subject lands are in good standing and are currently 100% held under the name of First Canadian Uranium Inc., a wholly-owned subsidiary of Pele Mountain. On October 16, 2006, Pele Mountain announced that it had entered into an agreement with CanAlaska Uranium Ltd. (CanAlaska) to purchase five unpatented claims totalling 60 claim units in Joubin Township. Pele Mountain agreed to pay $13,000 in cash and issue 60,000 common shares at an attributable value of $12,000. Pele Mountain’s interest in the claims is subject to a 1.75% Net Smelter Return (NSR) royalty. Pele Mountain has the right to buy-back up to 1% of the royalty for $1 million. Pele Mountain completed and filed $25,000 of assessment work to keep the claims in good standing as part of the acquisition agreement. On December 18, 2006, Pele Mountain announced that it had entered into an agreement with Precambrian Ventures Ltd. (Precambrian) whereby it could acquire a 100% interest Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 1-17 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com in eight claims totalling 101 claim units. Pursuant to the terms of the agreement, Pele Mountain agreed to make cash payments totalling $305,000 and issue 425,000 common shares at an attributable value of $0.88 per share over three years. Precambrian retains a 1.75% NSR royalty. Pele Mountain has the right to buy-back 1% for $1 million. On May 2, 2007, Pele Mountain announced that it had entered into an agreement to acquire five additional claims totalling 77 claim units in Joubin and Proctor townships. Pursuant to the terms of the agreement, Pele Mountain agreed to pay $122,000 in cash and issue 150,000 shares at an attributable value of $0.90 per share or an aggregate value of $135,000. Pele Mountain’s interest in these claims is subject to a 3% NSR royalty with provision to buy-back 1.5% for $1.5 million. In 2009, Pele Mountain signed a 21-year lease agreement (the “Lease”) with the City of Elliot Lake (the “City”) in respect of surface rights to key mining claims. The Lease includes the City’s surface rights to a total of 48 surface patents, comprising of approximately 796 ha, and includes an option for the Company to purchase the surface rights under certain circumstances. The annual lease payment is $2,388. In 2011, two mining leases (the “Mining Leases”) were granted to Pele Mountain from the Province of Ontario for the Eco Ridge Mine Project. The Mining Leases provide the Company with the exclusive right to mine the Eco Ridge deposit, and include surface rights that allow for siting of Project infrastructure and processing facilities. The Mining Leases are for a period of 21 years (commencing March 1, 2011) and are renewable. The Mining Leases cover an area of 1,550 ha, and the annual lease payments total $4,652. HISTORY Uranium was discovered in the Elliot Lake District in 1948 and the subsequent prospecting resulted in the discovery of several zones of radioactive conglomerate. Production started in 1958 and by the end of 1996, when the last mine in the district was shut down due to the low demand and oversupply of uranium, a total of 138,500 tonnes of uranium metal had been produced at an average grade of about 0.09% U3O8 from the 12 mines at Elliot Lake. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 1-18 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com The mining at Elliot Lake was all by underground methods, primarily room and pillar, with shaft access. The major portion of the ore mined was processed through a conventional uranium processing plant, with some production from underground leaching. Yttrium oxide and rare earth oxides were also recovered at the Denison mine in the past, as byproducts of the uranium production. A number of companies have been involved in exploration on the Eco Ridge Mine property. The major portion of the exploration was conducted in the period from 1953 to 1955 immediately following the discovery of uranium in the Elliot Lake District. The uranium mineralization was discovered by surface prospecting and mapping, followed by diamond drilling. This exploration outlined the Pardee Channel, which hosts the deposit, and the subsequent drilling traced the mineralization down dip to a depth of about 500 m over a strike length of about 5,000 m. Further exploration during the 1960s and early 1970s consisted of deeper drilling and demonstrated that the mineralization continued down dip and extended to a depth of about 1,200 m. With the closure of the mines at Elliot Lake in the 1990s, the Eco Ridge Mine claims, then held by Rio Algom Limited, were allowed to lapse. The near surface part of the property was staked by CanAlaska in October 2004 and January 2005. CanAlaska carried out a compilation of historic data on the property but did not conduct any exploration surveys or drilling. In October 2006, Pele Mountain drilled one hole on the property for assessment purposes. In January 2007, RPA prepared a Mineral Resource estimate based on the historical drilling results. An Inferred Mineral Resource was estimated at approximately 30 Mt grading 0.050% U3O8 containing 33 million pounds of U3O8. Pele Mountain drilled another 56 holes under supervision by RPA in 2007. A Preliminary Assessment report was prepared in October 2007 and presented an updated Mineral Resource, including an Indicated Mineral Resource of 5.7 Mt at 0.051% U3O8 containing 6.4 million pounds of U3O8 and an Inferred Mineral Resource of 37.3 Mt at 0.044% U3O8 containing 36.1 million pounds of U3O8. RPA’s 2007 Preliminary Assessment projected a 20 year mine life, including decommissioning, at a production rate of 3,214 tonnes per day (tpd), with 1,260 tpd from Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 1-19 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com panel drifting trucked to surface and processed in a conventional acid leach plant and 1,954 tpd from longhole mining with underground bioleaching. RPA completed an NI 43-101 Technical Report containing an updated Mineral Resource estimate in April 2011. Indicated Mineral Resources totaled 14.3 Mt, at grades of 0.048% U3O8 and 1,640 ppm TREO. Inferred Mineral Resources totaled 33.1 Mt, at grades of 0.043% U3O8 and 1,320 ppm TREO. In August 2011, RPA completed a Preliminary Economic Assessment based on processing by in-situ and surface heap leaching. GEOLOGY AND MINERALIZATION The Elliot Lake area lies within the Precambrian Canadian Shield of Northern Ontario, Canada, at the boundary between the Southern and Superior Geological Provinces. Three major regional lithological components and two regional structural components locally influenced the initial deposition and subsequent deformation of the Elliot Lake mineral deposits: The Archean-age basement made up of metavolcanic and metasedimentary rocks, granite and minor mafic intrusive rocks of the Superior province; Proterozoic-age Huronian metasedimentary intercalated mafic volcanic rocks; Post-Huronian intrusive rocks including Nipissing diabase sills and post Nipissing diabase dykes and sills, small felsic intrusive bodies and lamprophyre dykes; Regional folding and thrust faulting during the Penokean Orogeny; Faulting during the late Proterozoic. rocks containing minor The Elliot Lake uranium deposits are located within the Huronian sediments, in the thicker sections of the Matinenda Formation that are located over depressions in the underlying Archean basement. These thicker sections are termed channels and the channels generally strike west-northwest. The Matinenda Formation consists of wellsorted arkosic quartzite with coarse-grained beds containing scattered quartz pebbles. The uraniferous quartz-pebble conglomerates are enclosed within the quartzite beds. The quartz-pebble conglomerate beds (historically called reefs) containing the uranium mineralization is located within the lower Matinenda Formation about 40 m to 50 m Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 1-20 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com above the basement. The lower Matinenda, designated as the Ryan Member, is characterized by the presence of pebbles, an increase in the amount of pyrite, and a distinctive green colour as a result of sericite alteration. The higher grade rare earths and uranium mineralization is contained within three conglomerate beds in the Ryan Member: the BCB, the MCB, which is equivalent to the Pardee Reef, and the Floater Reefs. Although little uranium is found outside of the conglomerate beds, rare earths mineralization has been found throughout the Ryan Member, including within the HWZ. The Elliot Lake deposits are interpreted to be modified paleoplacer (detrital) deposits and the source rocks are believed to be pegmatitic granite located to the north. The primary uranium-bearing minerals are uraninite and brannerite. Other uranium minerals that have been reported are pitchblende, coffinite, and thucolite. All minerals deposited with the uranium have a specific gravity of 5.0 or greater and they are also resistant to weathering (hardness of 5.0 or greater), which results in their deposition as heavy minerals within the matrix of the quartz pebble conglomerate beds. The major carrier of the REE is monazite, which contains over 90% of the REE in the MCB. The remainder of the REE (about 10%) is contained within the uranium minerals uraninite, pitchblende, coffinite, and brannerite. EXPLORATION STATUS Pele Mountain drilled its first hole on the Property in February 2005 and has been systematically exploring and evaluating the Eco Ridge Mine Property since October 2006. Pele Mountain carried out exploration programs in 2007, 2008, 2009, and 2011, oriented mainly towards infill drilling. Pele Mountain’s exploration programs have consisted primarily of resource drilling, mineralogical evaluation, and metallurgical testing. In 2010, Pele Mountain re-assayed pulps from the 2007-2009 drilling programs to obtain REE, yttrium and scandium data. In 2011, Pele conducted an extensive core resampling program to include the hanging wall zone (HWZ) above the main conglomerate bed. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 1-21 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com MINERAL RESOURCES The current Mineral Resource estimate is listed above, in Table 1-3, including Indicated Mineral Resources of 48.7 Mt at 0.026% U3O8 and 1,157 ppm TREO and Inferred Mineral Resources of 37.9 Mt at 0.026% U3O8 and 1,100 ppm TREO. Cut-offs were applied on the basis of unit values - $100 per tonne for the MCB and $50 per tonne for the HWZ. A minimum mining thickness of 1.8 m was used. Historic drilling has intersected the MCB down-dip from the current Mineral Resources. A target for further exploration was estimated for these areas, consisting of a further 40 Mt to 60 Mt, grading from 0.030% to 0.050% U3O8, accompanied by 0.12% to 0.18% TREO for the MCB. The potential quantities and grades of the exploration targets are conceptual in nature and there has been insufficient drilling to define a Mineral Resource. It is uncertain if further exploration will result in the definition of a mineral resource in these areas. MINING METHOD The geometry of the MCB within the resource wireframe can be described as a narrow reef, with a shallow dip approximately 20° to the north and a plunge of approximately 10° to the north-west. The mineralized zone is oriented in an easterly direction with a strike and dip length of approximately 5,700 m and 2,000 m, respectively. The selected mining method was room and pillar. Both development and production will be contained within the mineralized zone. The development and production tonnage will be loaded into trucks and transported to surface for milling. Mine access will be accomplished using decline ramps from surface. MINERAL PROCESSING The conceptual process design and preliminary capital and operating costs were developed by SNC-Lavalin Inc., as reported in Pele Mountain Resource Eco Ridge Project Capital and Operating Cost Estimates (2012). Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 1-22 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Rare earths and uranium will be recovered by crushing and grinding, froth flotation, and magnetic separation, acid baking and water leaching, solid/liquid separation, high density sludge (HDS) removal, and recovery of the valuable elements by solvent extraction and precipitation. MARKET STUDIES URANIUM A uranium price of US$70/lb U3O8 has been used in this PEA, based on independent metal price forecasts from banks and financial institutions. RARE EARTHS The market for rare earth products is small and public information on price forecasts and sales terms are difficult to obtain. Current prices are tracked by sources such as Asian Metal and Metal-PagesTM, based on transactions. Recent history shows international rare earth market prices growing at an unprecedented rate since China cut export quotas by approximately 40% in 2011. China’s overwhelming control on the rare earth supply chain, from upstream mining to downstream processing and end-user products, is likely to remain intact on all but a few materials through 2016. Rare earth prices are expected to remain volatile in the short term. A small number of REE producers outside of China are likely to be in operation by the time the Eco Ridge Mine Project is developed. This is expected to saturate the market for certain light rare earths such as lanthanum and cerium, however, demand for highvalue heavy rare earths (such as dysprosium) is expected to grow, and supply is expected to remain in deficit. Price forecasting in this environment is difficult, and certain to contain wide margins of error. RPA selected rare earth prices within a range of available forecasts. Prices for certain elements are higher than current prices, and for others, lower, however the average basket price used in the PEA is approximately 13% lower than Q2 2012 prices. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 1-23 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com RPA considers these rare earths prices to be appropriate for a PEA-level study, however, we note that the recent market volatility introduces considerably more uncertainty than a comparable base or precious metals project. ENVIRONMENTAL CONSIDERATIONS Pele Mountain Resources has conducted preliminary baseline environmental studies in support of development of the Eco Ridge Mine Project. Consultation with potentially affected communities, including First Nations, has also been given a high priority by Pele. The environmental studies that have been conducted in support of the project include: Terrestrial Ecosystems Preliminary Site Characterization Report – 2008 Aquatic Ecosystems Preliminary Site Characterization Report – 2008 Additional Aquatic Studies of Rioux Lake Preliminary Groundwater Scoping Evaluation – 2008 Stage 1 Archaeological Assessment Conceptual Design of a Tailings Disposal Facility (TDF) – 2008, updated in 2012 Project Description submitted to the Major Projects Management Office and the Canadian Nuclear Safety Commission in 2008 (for information purposes only, not as a formal regulatory submission) Preliminary Geo-Chemical Characterization of Tailings – on-going Work Planning for Detailed Environmental Characterization Studies – ongoing Pele Mountain will be required to complete an Environmental Assessment prior to receiving the necessary licenses to operate. CAPITAL AND OPERATING COST ESTIMATES The total Project capital costs are presented in Table 1-5. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 1-24 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 1-5 OVERALL CAPITAL COST ESTIMATE Pele Mountain Resources Inc. – Eco Ridge Mine Project Mine Initial (C$ 000) 61,185 Sustaining (C$ 000) 25,235 TOTAL (C$ 000) 86,802 Processing 229,806 - 229,806 Tailings 24,685 22,935 47,620 Infrastructure 25,000 10,000 35,000 114,561 - 114,561 Sustaining - 24,000 24,000 Closure - 22,000 22,000 Contingency 107,606 - 107,606 Total 562,843 104,170 667,013 Component Indirects Note: This table does not include costs of $75.9 million for ore mining during the construction period. Those costs are included in the cash flow as operating costs. The total operating costs are summarized in Table 1-6. TABLE 1-6 OPERATING COST ESTIMATE Pele Mountain Resources Inc. – Eco Ridge Mine Project Area C$/t Mining 41.52 Processing 26.31 G&A 3.50 Total 71.33 Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 1-25 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 2 INTRODUCTION Roscoe Postle Associates Inc. (RPA) was retained by Pele Mountain Resources Inc. (Pele Mountain), to carry out a Preliminary Economic Assessment (PEA) on the Eco Ridge Mine Project (the Project), Elliot Lake, Ontario. The purpose of this report is to update the Project economics with results of work completed since the previous PEA in August 2011 (the “2011 PEA”). This updated PEA features an updated resource estimate and a base case scenario for production that focuses on mining the relatively higher-grade main conglomerate bed, and uses a conventional milling approach for processing which achieves materially higher recoveries for rare earths and uranium. Pele Mountain is a Canadian resource exploration and development company focused on the sustainable development of its 100%-owned Eco Ridge Mine Rare Earths and Uranium Project (Eco Ridge or the Project). Pele Mountain is a reporting issuer in Ontario, British Columbia and Alberta, and its common shares are listed on the TSX Venture Exchange and also trade on the OTCQX. Pele Mountain has also entered into an agreement to purchase the Simon Rare Earth Claims in Mountain Pass, California. Currently, the major asset associated with the Project is a stratabound zone of rare earth oxide (REO) and uranium oxide (U3O8) mineralization. Rare earth elements (REE) are divided into two groups: 1. The Light Rare Earth Elements (LREE) or cerics, comprising of La, Ce, Pr, and Nd. 2. The Heavy Rare Earth Elements (HREE) or yttrics, comprising of Y, Eu, Gd, Tb, Dy, Ho, Er, Tm, Yb, Lu, and Sm. Scandium, while not a rare earth, has been included with the HREE for purposes of this report. LREO and HREO refer to oxides of light and heavy rare earth elements respectively. In this document, TREO (Total Rare Earth Oxides) refers to LREOs and HREOs collectively. PEA-level work on the Project is based on the development of an underground mining operation ramping up to 9,000 tonnes per day (tpd), with the recovery of REO and U3O8. The 2011 PEA was based on processing via underground bioleaching and surface heap leaching, while this update is based on conventional milling and acid baking. Materially Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 2-1 www.rpacan.com higher recoveries of REO and U3O8, based on recent testwork, proved to outweigh associated capital and operating cost increases, providing for more robust economic results. SOURCES OF INFORMATION A site visit was carried out on November 22, 2010, by R. Barry Cook, M.Sc., P.Eng., Associate Consulting Geologist, RPA, and Tudorel Ciuculescu, M.Sc., P.Geo., Senior Geologist, RPA. Messrs. Cook and Ciuculescu were accompanied by Patrick Enright and Leo Robert, contractors working for Pele Mountain. Discussions were held regarding the geology of the Eco Ridge Mine property, and a number of sections of core from holes through the mineralized zone were reviewed. For verification sampling, Messrs. Cook and Ciuculescu personally collected five half-core sample intervals from four holes. The conceptual process design and preliminary capital and operating cost estimates for processing were developed by SNC-Lavalin Inc., as reported in Pele Mountain Resource Eco Ridge Project Capital and Operating Cost Estimates (2012). Conceptual tailings design and cost estimation was carried out by Golder Associates. Environmental portions of this report were carried out by SENES Consultants Ltd., who were involved in the 2007 Preliminary Assessment (PA), and retained by Pele Mountain to assist with the ongoing environmental assessment process. The documentation reviewed, and other sources of information, are listed at the end of this report in Section 27, References. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 2-2 www.rpacan.com LIST OF ABBREVIATIONS Units of measurement used in this report conform to the Imperial system. All currency in this report is Canadian dollars (C$) unless otherwise noted. °C °F g A a bbl Btu C$ cal cfm cm cm2 d dia. dmt dwt ft ft/s ft2 ft3 g G Gal g/L g/t gpm gr/ft3 gr/m3 hr ha hp in in2 J k kcal kg km km/h micron degree Celsius degree Fahrenheit microgram ampere annum barrels British thermal units Canadian dollars calorie cubic feet per minute centimetre square centimetre day diameter dry metric tonne dead-weight ton foot foot per second square foot cubic foot gram giga (billion) Imperial gallon gram per litre gram per tonne Imperial gallons per minute grain per cubic foot grain per cubic metre hour hectare horsepower inch square inch joule kilo (thousand) kilocalorie kilogram kilometre kilometre per hour km2 kPa kVA kW kWh L L/s lb m M m2 m3 m3/h min MASL mm mph MVA MW MWh opt, oz/st oz ppm psia psig RL s st stpa stpd t tpa tpd US$ USg USgpm V W wmt yd3 yr square kilometre kilopascal kilovolt-amperes kilowatt kilowatt-hour litre litres per second pound metre mega (million) square metre cubic metre cubic metres per hour minute metres above sea level millimetre miles per hour megavolt-amperes megawatt megawatt-hour ounce per short ton Troy ounce (31.1035g) part per million pound per square inch absolute pound per square inch gauge relative elevation second short ton short ton per year short ton per day metric tonne metric tonne per year metric tonne per day United States dollar United States gallon US gallon per minute volt watt wet metric tonne cubic yard year Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 2-3 www.rpacan.com 3 RELIANCE ON OTHER EXPERTS This report has been prepared by RPA for Pele Mountain. The information, conclusions, opinions, and estimates contained herein are based on: Information available to RPA at the time of preparation of this report, Assumptions, conditions, and qualifications as set forth in this report, and Data, reports, and other information supplied by Pele Mountain and other third party sources. For the purpose of this report, RPA has relied on ownership information provided by Pele Mountain. RPA has not researched property title or mineral rights for the Eco Ridge Mine Project and expresses no legal opinion as to the ownership status of the property. RPA did review the status of most of the claims on the web site of the Ontario Ministry of Northern Development, Mines and Forestry (www.mndmf.gov.on.ca/ mines/claimaps_e.asp) and, for those claims verified the information is as noted in Table 4-1. Except for the purposes legislated under provincial securities laws, any use of this report by a third party is at that party’s sole risk. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 3-1 www.rpacan.com 4 PROPERTY DESCRIPTION AND LOCATION The Eco Ridge Mine property is located in northern Ontario, approximately 11 km east of the City of Elliot Lake and 400 km northwest of Toronto (Figure 4-1). The Project is located in Gunterman, Deagle, Gaiashk, Joubin, and Proctor townships, District of Algoma, within 1:50,000 scale NTS map sheet 41J07 (Elliot Lake) and map sheet 41J/08 (Whiskey Lake). The Project consists of one irregularly shaped block located within a rectangular area extending for 13 km in an east-west direction and 6.5 km in a northsouth direction. It is centred at approximately Universal Transverse Mercator (UTM) coordinates 384000E and 5138000N (NAD 83, Zone 17). LAND TENURE The Eco Ridge Mine property consists of 38 mining claims totalling 392 claim units and two mining leases covering approximately 7,822 ha in the Sault Ste. Marie Mining Division (Figure 4-2). Table 4-1 lists all the subject claims and their relevant tenure information. As of the effective date of this report, all of the subject lands were in good standing and were currently 100% held under the name of First Canadian Uranium Inc., a wholly-owned subsidiary of Pele Mountain. Pele Mountain staked two non-contiguous claim blocks in Joubin and Gunterman Townships, Elliot Lake District, in February 2005. The eastern claim block became the first part of “Pele Mountain’s Elliot Lake Property” which was subsequently expanded by the claim acquisitions described below, which has come to be known as the Eco Ridge Mine rare earths and uranium project. TABLE 4-1 SCHEDULE OF CLAIMS Pele Mountain Resources Inc. – Eco Ridge Mine Project Township Deagle Gaiashk Gunterman Gunterman Gunterman Claim 4221196 4221195 3018858 4254190 4257106 Recording Date 08/05/2007 08/05/2007 07/03/2008 08/06/2010 08/06/2010 Due Date 08/05/2013 08/05/2013 06/04/2012 08/06/2012 08/06/2012 Work Req’d $4,800 $6,400 $800 $800 $2,800 Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Units 12 16 2 2 7 Hectares 192 256 32 32 112 Rev. 0 Page 4-1 www.rpacan.com Township Gunterman Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Joubin Proctor Proctor Proctor Proctor Proctor Proctor Total Claim 4257107 1211241 1249895 1249896 1249897 1249898 1249899 3009472 4201552 4201554 4201555 4201556 4201560 4201561 4201568 4201634 4201635 4201637 4205078 4214880 4220221 4220222 4220223 4220224 4220225 4220226 4259108 4210398 4215306 4215307 4221192 4221193 4221194 Recording Date 08/06/2010 23/05/2000 23/02/2001 23/02/2001 23/02/2001 23/02/2001 23/02/2001 04/06/2004 24/02/2005 24/02/2005 24/02/2005 24/02/2005 24/02/2005 24/02/2005 24/02/2005 24/02/2005 24/02/2005 24/02/2005 25/01/2007 16/01/2007 15/02/2007 15/02/2007 20/12/2006 16/01/2007 16/01/2007 15/02/2007 28/01/2011 18/03/2009 29/12/2006 29/12/2006 08/05/2007 08/05/2007 08/05/2007 Due Date 08/06/2012 23/05/2013 23/02/2013 23/02/2013 23/02/2013 23/02/2013 23/02/2013 04/06/2013 24/02/2013 24/02/2013 24/02/2013 24/02/2013 24/02/2013 24/02/2013 24/02/2013 24/02/2013 24/02/2013 24/02/2013 25/01/2013 16/01/2013 15/02/2013 15/02/2013 20/12/2013 16/01/2013 16/01/2013 15/02/2013 28/01/2014 18/03/2012 29/12/2013 29/12/2013 08/05/2013 08/05/2013 08/05/2013 Work Req’d $4,400 $3,600 $6,400 $5,600 $5,600 $3,200 $6,000 $4,800 $4,800 $3,600 $3,200 $3,600 $3,600 $2,000 $4,800 $3,200 $6,400 $2,400 $5,200 $1,600 $4,800 $2,000 $4,800 $4,800 $4,800 $1,200 $1,200 $1,600 $6,400 $6,400 $6,400 $6,400 $6,400 38 Units Hectares 11 9 16 14 14 8 15 12 12 9 8 9 9 5 12 8 16 6 13 4 12 5 12 12 12 3 3 4 16 16 16 16 16 176 144 256 224 224 128 240 192 192 144 128 144 144 80 192 128 256 96 208 64 192 80 192 192 192 48 48 64 256 256 256 256 256 392 6,272 Note: claims due in 2012 are in the process of being renewed. On October 16, 2006, Pele Mountain announced that it had entered into an agreement with CanAlaska Uranium Ltd. (CanAlaska) to purchase five unpatented claims (1192671, 3009465, 3009474, 3009475, and 3009485) totalling 60 claim units in Joubin Township. Claim 3009475 was re-staked as claim 4218565. Pele Mountain agreed to pay $13,000 in cash and issue 60,000 common shares at an attributable value of $12,000. Pele Mountain’s interest in the claims is subject to a 1.75% Net Smelter Return (NSR) royalty. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 4-2 www.rpacan.com Pele Mountain has the right to buy-back up to 1% of the royalty for $1 million. Pele Mountain completed and filed $25,000 of assessment work to keep the claims in good standing as part of the acquisition agreement. The subject claims include the original Calder-Bousquet claim block and the major portion of the Pardee claim block. It is RPA’s understanding that the payments and share issuances related to the CanAlaska agreement have been satisfied. On December 18, 2006, Pele Mountain announced that it had entered into an agreement with Precambrian Ventures Ltd. (Precambrian) whereby it could acquire a 100% interest in eight claims (1211241, 1249895, 1249896, 1249897, 1249898, 1249899, 3009471, and 3009472) totalling 101 claim units. Pursuant to the terms of the agreement, Pele Mountain agreed to make cash payments totalling $305,000 and issue 425,000 common shares at an attributable value of $0.88 per share over three years as shown in Table 42. TABLE 4-2 PRECAMBRIAN AGREEMENT TERMS Pele Mountain Resources Inc. - Eco Ridge Mine Project Date Cash ($C) Shares Upon Closing Dec. 19, 2007 Dec. 19, 2008 Dec. 19, 2009 30,000 50,000 75,000 150,000 50,000 75,000 100,000 200,000 Precambrian retains a 1.75% NSR royalty. Pele Mountain has the right to buy-back 1% for $1 million. Claim 3009471 was re-staked as 4218566. The subject claims comprise the eastern portion of the Pardee Channel covering the original Pecors Block. It is RPA’s understanding that the payments and share issuances related to the Precambrian agreement have been satisfied. In January and February 2007, Pele Mountain staked another six claims (4214876, 4214877, 4214880, 4214882, 4214883, and 4214884) totalling 48 claim units and covering the potential down-dip extension of the favourable conglomerate bed to the north of the previously acquired claim blocks. Five of these six claims were Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 4-3 www.rpacan.com subsequently re-staked as claims 4220225, 4220224, 4220222, 4220226, and 4220221; claim 4214880 was not re-staked. On May 2, 2007, Pele Mountain announced that it had entered into an agreement to acquire five additional claims (4215304, 4215305, 4215306, 4215307, and 4215007) totalling 77 claim units in Joubin and Proctor townships. Pursuant to the terms of the agreement, Pele Mountain agreed to pay $122,000 in cash and issue 150,000 shares at an attributable value of $0.90 per share or an aggregate value of $135,000 as shown in Table 4-3. TABLE 4-3 MAY 2007 AGREEMENT TERMS Pele Mountain Resources Inc. - Eco Ridge Mine Project Date Cash (C$) Shares On Closing 01-May-08 01-May-09 01-May-10 24,000 28,000 30,000 40,000 30,000 40,000 40,000 40,000 Pele Mountain’s interest in these claims is subject to a 3% NSR royalty with provision to buy-back 1.5% for $1.5 million. Claim 4215007 was re-staked as claim 4205078. It is RPA’s understanding that the payments and share issuances related to the May 2007 agreement have been satisfied. Additional staking was carried out in May 2007 and June 2010. Three claim units that tie on to the western boundary of the Eco Ridge Mine property were purchased in May 2011 for $3,000 in cash, with the vendor retaining a 1% NSR royalty. In 2009, Pele Mountain signed a 21-year lease agreement (the “Lease”) with the City of Elliot Lake (the “City”) in respect of surface rights to key mining claims. The Lease includes the City’s surface rights to a total of 48 surface patents, comprising of approximately 796 ha, and includes an option for the Company to purchase the surface rights under certain circumstances. The annual lease payment is $2,388. In 2011, two mining leases (the “Mining Leases”) were granted to Pele Mountain from the Province of Ontario for the Eco Ridge Mine Project. The Mining Leases provide Pele Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 4-4 www.rpacan.com Mountain with the exclusive right to mine the Eco Ridge deposit, and include surface rights that allow for siting of Project infrastructure and processing facilities. The Mining Leases are for a period of 21 years (commencing March 1, 2011) and are renewable. The Mining Leases cover an area of 1,550 ha, and the annual lease payments total $4,652. Figure 4-2 shows the location of the access roads and trails relative to the property boundaries. The west boundary of the claim block has been surveyed and a claim inspection was conducted for Pele Mountain by an independent consultant in April-June 2007. The area covered by the provincial Mining Lease has been surveyed. LICENCES OF OCCUPATION There are Licences of Occupation within the claim block, which are held by Rio Algom Limited (Rio Algom). The locations of these Licences of Occupation are shown in Figure 4-2. These Licences of Occupation comprise less than 2% of the overall area of the claim block and are not considered necessary to conduct future mining and processing operations on the property. ROYALTIES AND OTHER ENCUMBRANCES With the exception of the royalties related to the agreements documented above, RPA is not aware of any other royalties, back-in rights, or other obligations related to the agreements or underlying agreements. PERMITS The project is currently at the resource definition and Preliminary Economic Assessment stage and, based on discussions with the Canadian Nuclear Safety Commission (CNSC) and the Ontario Ministry of Northern Development and Mines (MNDM), no permits are required from either the provincial or federal governments to conduct preliminary exploration and evaluation on a mineral project. There is a requirement to notify the Ontario Ministry of Labour that exploration drilling or surveys are being conducted on the property. Preliminary exploration may include geological mapping, ground geophysical Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 4-5 www.rpacan.com and geochemical surveys, airborne geophysical or geochemical surveys, limited stripping and trenching, limited bulk sampling, and various forms of drilling from surface. Permits will be required when the project proceeds to the advanced exploration stage. Advanced exploration means the excavation of an exploratory shaft, adit or decline, the extraction of material in excess of the prescribed quantity (1,000 t) where the extraction involves the disturbance or movement of prescribed material located above or below the surface of the ground, the installation of a mill for test purposes or any other prescribed work (includes the excavation of backfilled raises, shafts or adits). ENVIRONMENTAL LIABILITIES There are no known environmental liabilities associated with the Eco Ridge Mine property. There has been no previous production at the property. Exploration was conducted on the property from 1953 through to 1974, with the majority of the holes drilled in 1953 and 1954. During this period, 109 diamond drill holes were drilled on the property. None of these holes were grouted and the casings for some of the holes are still in place. Many of the casings have been destroyed as a result of logging operations conducted in the area. An exploration adit was excavated in 1954 to recover samples for metallurgical investigations. The adit was backfilled in 1994 by Rio Algom as part of the decommissioning programs carried out when the mines were closed in the Elliot Lake area. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 4-6 www.rpacan.com Québec Hudson Bay Manitoba PROJECT LOCATION James Bay Source: Geomatics Office, Ministry of Transportation Ontario, 2006. Red Lake Pickle Lake N O NTAR I O Kenora Sioux Lookout Thunder Bay Timmins Lake Superior Rouyn-Noranda Chapleau Kirkland Lake Sault Ste. Marie Sudbury Val d’Or Elliot Lake eM ichi g an North Bay Toronto Lak U. S. A. Lake Ottawa Huron ECO RIDGE MINE PROJECT Windsor Lake Erie 0 100 200 300 400 500 Lake Ontario Figure 4-1 Pele Mountain Resources Inc. Eco Ridge Mine Project Kilometres Elliot Lake, Ontario, Canada Location Map June 2012 4-7 375,000 E 380,000 E 385,000 E 390,000 E 395,000 E 5,145,000 N 5,145,000 N N 5,140,000 N 5,140,000 N Pele Mountain Property Boundary 5,135,000 N 5,135,000 N 4-8 Pele Mountain 2011 Lease Boundary Figure 4-2 5,130,000 N 0 1 2 3 4 Kilometres Mining Land Tenure Source: Ministry of Northern Development and Mines of Ontario, Provincial Mining Recorder’s Office, Plan G-3254, 9 February 2011. Land Tenure Map (Sault Ste. Marie Mining Division) 5,130,000 N June 2012 Eco Ridge Mine Project Joubin Township, Ontario, Canada www.rpacan.com Pele Mountain Resources Inc. www.rpacan.com 5 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY ACCESSIBILITY AND PROPERTY INFRASTRUCTURE The Eco Ridge Mine property is located 11 km east of the City of Elliot Lake, Ontario, which is situated 26 km north of Highway 17 (TransCanada Highway) on Highway 108. Highway 108 crosses the western portion of the property. The turn-off for the access road to the property from Highway 108 is located three kilometres south of Elliot Lake. The access road is a public road. The west boundary of the property is located four kilometres from the turn-off. The road extends across the property and during some of the year this area accessible by all-wheel drive vehicles only. The access road to the property is shown in Figure 4-2. The major assets and facilities located on the property are the rare earths and uranium oxides Mineral Resources, and a 236 kV power line extending across the property. The location of the exploration adit is also shown in Figure 4-2. The adit has been backfilled. Elliot Lake is located 160 km west of Sudbury and 180 km east of Sault Ste. Marie and these communities are connected by highway. The Sault Ste. Marie, Ontario – Sault Ste Marie, Michigan border crossing is located 200 miles west of Elliot Lake. There is a railway line 26 km south at the intersection of Highways 108 and 17 (TransCanada Highway). There are two deep water ports near the same highway intersection on the North Channel of Lake Huron. One port is currently used by Lafarge at the town of Blind River and the other, located at Sprague, is now used by a yacht club. Elliot Lake airport has a runway 30 m wide and 1,372 m long. The airport is maintained year round and is certified by Transport Canada for airline service. Air Bravo Corporation operates an air ambulance service and provides charter service. CLIMATE The climate in the Elliot Lake region is suitable for conducting exploration, development, and operation of a mine throughout the year. The average winter temperature (December to February) is -9ºC and the average summer temperature (June to August) is +16ºC. The minimum and maximum temperatures for each month are shown in Table Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 5-1 www.rpacan.com 5-1. The average annual winter snowfall is 236 mm and the average annual rainfall is 636 mm for a total annual precipitation of 872 mm (a factor of 0.1 is used to convert snowfall to precipitation). Historically, the maximum rainfall for Elliot Lake has been estimated to be 420 mm of rain within 12 hours. TABLE 5-1 AVERAGE MINIMUM AND MAXIMUM TEMPERATURES IN THE ELLIOT LAKE DISTRICT Pele Mountain Resources Inc. – Eco Ridge Mine Project Min (°C) Max (°C) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Year -17.7 -17.6 -11.1 -2.6 4.0 9.5 12.2 11.4 7.7 2.9 -3.9 -12.3 -0.8 -6.4 -5.2 0.8 8.2 15.9 21.5 23.6 22.3 17.7 11.9 3.0 -3.7 9.8 The wind direction is predominantly from the north from December through to April and from the southwest and south the remainder of the year. LOCAL RESOURCES Based on the 2006 census, the City of Elliot Lake has a population of 11,549 people. The median age of the population is 49.4 years, with about 85% of the population over 15 years of age. Based on October to December 2005 statistics, the labour force is 3,855, or about 38%, of the total population over 15 years of age. This low participation rate reflects the large number of retirees in the city. The unemployment rate at the same period was 13%. There are two fully serviced industrial park areas within the community and existing buildings are available for lease or purchase. Elliot Lake has a full complement of educational, professional, medical, and social services. A new multidisciplinary community medical centre in downtown Elliot Lake opened in 2007. Tenants of the state-of-the-art facility include 12 family doctors, other health care professionals such as nurse practitioners and dieticians, and a drug store. LOCAL INFRASTRUCTURE Natural gas has been available in Elliot Lake since the mid-1980s and is provided by Union Gas Limited, a major natural gas company in Canada. Natural gas was used at Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 5-2 www.rpacan.com the Rio Algom and Denison mines for facility and mine air heating and for product drying. Natural gas was provided to the Stanleigh Mine, which is located directly northwest of Pele Mountain’s property, and to the adjacent Nordic Mine property for the operation of the yellow cake drying and packing plant. The main east to west high voltage three-phase transmission lines between Ontario Power Generation’s station in Mississagi and Sudbury cross the eastern edge of the property. These lines are rated at 230 kV. There is a load centre at Elliot Lake with a generation capacity of 23 MW. The capacity can be increased. The Elliot Lake hydro system has the capacity to supply electricity to 25,000 people plus six operating mines. The entire hydro infrastructure is still in place, although it is not all in current use. Sulphuric acid is available from Sudbury where it is manufactured as a by-product from the nickel mining operations sulphur dioxide emission reduction program. The acid is produced by Vale and Xstrata, but marketed through chemical supply companies. Lime is available from the Lafarge Cement Plant in Sprague. Cameco Corporation operates a uranium conversion facility at Blind River, located 50 km from the property on Highway 17. PHYSIOGRAPHY The Eco Ridge Mine property is underlain by moderately rugged topography, with elevations ranging from 320 m to 430 m. Steep cliffs form the south slopes, while the north slopes are gentler and tend to follow the dip of the stratigraphy. The ridges trend east-northeast along the strike of the rocks. The contact between the Huronian sediments and the underlying Archean rocks forms a south-facing hill. To the south of this hill, where any future infrastructure would be sited, the topography is relatively flat. Lakes and streams tend to develop along the strike of the strata and along the northnorthwest trending faults that crosscut the strata. DRAINAGE BASINS The Eco Ridge Mine property is located within the Serpent River drainage basin. The Serpent River Watershed is comprised of more than 70 lakes and nine sub-watersheds, which cover an area of 1,376 km2, and drain into Lake Huron. The Eco Ridge Mine property is located within two of the major sub-basins: the Elliot Lake sub-basin on the Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 5-3 www.rpacan.com western portion of the property and the Pecors Lake sub-basin on the eastern portion of the property. Drainage on the western part of the Pele Mountain claims is west into Pardee and Stinson Lakes and south into Kings Lake, while the eastern portion of the claims drains into Pecors Lake. FLORA AND FAUNA The valleys are covered with hemlock and cedar trees and the ridges are wooded with maple, oak, birch, and poplar trees. Many different species of birds and mammals can be seen in the forests and surrounding areas of the Pele Mountain claims. These include finches to bald eagles and beaver to moose. At this time no rare, threatened, or endangered species or habitat are known to be present in the project area. A 1993 survey found 22 different species of fish in the lakes of the Serpent River Watershed. Benthic invertebrates include snails, insect larvae, and clams. Pele Mountain conducted site characterization and environmental baseline surveys on the property in 2007 and 2008. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 5-4 www.rpacan.com 6 HISTORY EXPLORATION A number of companies have conducted exploration on Pele Mountain’s Eco Ridge Mine property. The major portion of the exploration on the property was conducted in the period from 1953 to 1955 immediately following the discovery of uranium in the Elliot Lake District. The uranium mineralization on the property was discovered by surface prospecting and mapping, followed by diamond drilling. This exploration outlined the Pardee Channel, which hosts the deposit, and the subsequent drilling traced the mineralization down dip to a depth of approximately 500 m over a strike length of approximately 5,000 m. Further exploration during the 1960s and early 1970s consisted of deeper drilling and demonstrated that the mineralization continued down dip and extended to a depth of approximately 1,200 m. The previous exploration on the property is summarized below. Aquarius Porcupine Gold Mines Limited (Aquarius) staked the Pardee property in 1953. The Pardee property forms the central portion of the claim blocks of the current Pele Mountain property. McIntyre Porcupine Gold Mines Limited (McIntyre) optioned the claims from Aquarius later in 1953 and carried out line cutting and geological mapping. In 1954, McIntyre drilled 28 AQ diamond drill holes totalling 2,498 m (S-1 to S-28). The drill holes were drilled over a strike length of about 3,000 m. Pardee Amalgamated Mines Limited (Pardee) was formed in 1954 to consolidate the Aquarius property with other properties in the area. Pardee carried out extensive mapping, trenching, diamond drilling, and drove an inclined adit along the conglomerate bed for a distance of approximately 31 m to obtain a bulk sample for metallurgical tests. Pardee drilled an additional 30 AXT diamond drill holes totalling 6,567 m (Series PA-1 to PA-29) and CPA-24 was a joint hole with New Jersey Zinc Exploration Company Canada Ltd. (New Jersey Zinc) on the boundary with the Calder-Bousquet property, located immediately to the west of the Pardee claims. The drilling results from the Sseries and PA-series holes outlined a large zone of uranium mineralization within the Main Conglomerate Bed. The drill hole logs and the analytical results from the core samples for the S-series and PA-series holes are on file at the MNDM offices in Sault Ste. Marie. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 6-1 www.rpacan.com The eastern portion of the Eco Ridge Mine property was staked in 1953 by Preston East Dome Mines, a company controlled by the Algom group of companies. Prospecting and geological mapping were conducted on these claims in 1953 by Algom. Algom drilled a total of 1,486 m in 15 holes (PW-101 to PW-115) in the eastern portion of the Eco Ridge Mine property immediately to the west of Pecors Lake in 1953 and 1954. The drilling intersected the Main Conglomerate Bed (MCB) and mineralization was reported. Although some cross sections showing the plots of the drill holes were found in the MNDM office, the drill hole logs with the sample intervals and analytical results are not available. New Jersey Zinc conducted exploration drilling on the Calder-Bousquet property located directly west of the Pardee claim block. In 1954 and 1955, New Jersey Zinc conducted 7,201 m of AXT diamond drilling in 23 holes (CB-1 to CB-23). The holes were tested with a scintillometer and samples taken. The historic analytical results for these holes and many of the drill logs were located at the MNDMF offices. The CB-series drill holes also intersected the MCB. The northwest portion of the Pele Mountain property was originally staked by St. Mary’s Uranium Mines Limited (St. Mary’s). Two diamond drill holes were drilled, one a joint hole with New Jersey Zinc on the boundary with the adjoining Calder-Bousquet property. The St. Mary’s claims came open for staking and were re-staked by Rio Algom in 1964. Rio Algom staked the claims in 1965 covering the original Calder-Bousquet claim block. Rio Algom also acquired the Pardee property. Rio Algom drilled two assessment holes, CB-30 and CB-31, on the former Calder-Bousquet claim block. The holes were wedged to provide a second intersection through the MCB. Sprague (1965) conducted a resource estimate for Rio Algom based on the surface diamond drilling. The “ore reserve estimate” was based on surface diamond drilling programs [undertaken] in 1954 and 1955 by McIntyre, Pardee, St. Mary’s, and New Jersey Zinc on the Calder-Bousquet Property, and two assessment holes drilled by Rio Algom in late 1965 and early 1966. The estimate indicated 31,265,000 tons of mineralization averaging 0.059% U3O8 in the MCB, which was referred to as the “Pardee Reef”. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 6-2 www.rpacan.com Sprague’s “ore reserve estimate” was based on a total of 99 holes using a minimum thickness of 1.5 m (5.0 ft.). This estimate is a historic estimate and does not conform to the current CIM definitions required under NI 43-101. Rio Algom drilled three additional holes, CB 32, 33, and 34, on the former St. Mary’s property in 1967. Rio Algom drilled another two holes on the property (CB-35 and CB36) in 1969 and 1974, respectively. In 1977, Rio Algom re-estimated the “ore reserves” initially compiled and estimated by Sprague and reported these estimates as “ore estimates”. The revised estimates included Calder-Bousquet Block, the Pardee Block and the additional drilling conducted by Rio Algom from 1967 to 1974. The estimates also include the Pecors Block and the estimate for this block is based on the drilling conducted by Rio Algom in 1954 (PW-1 to PW-116). This historic estimate is discussed in the previous Technical Report (Cochrane and Roscoe, 2007). The northern part of the Pele Mountain Property was formerly held by Stancan Uranium Corporation (Stancan), Consolidated Callinan Flin-Flon Mines Ltd. (Consolidated Callinan), and Magoma Mines Ltd. (Magoma). Stancan drilled two deep holes (Z-5-1 and Z-5-2) which intersected a uranium-bearing conglomerate bed. Based on the descriptions in the drill hole logs and the position of the conglomerate bed in the stratigraphic sequence, the bed is correlated with the MCB intersected in the up-dip drilling. However, no assays are available in the public files for the intersections. Consolidated Callinan and Magoma reportedly drilled one deep hole each, but no data for these holes are available. The claims were allowed to lapse and were re-staked by Kerr-McGee Corporation (Kerr-McGee) in the late 1960s. Kerr-McGee drilled three deep drill holes in 1967, with one hole drilled on the Eco Ridge Mine property. The drill hole logs are available for these holes. The summary of the historic drilling programs is presented in Table 6-1. Since the filing of the 2007 Technical Report (Cochrane and Roscoe, 2007) on the property, the copies of drill hole logs CB-16 to CB-23 were located. All the historic drilling was core drilling using AXT rods with a core diameter of 32.5 mm (1.28 in.). The drill collar locations of the historic drilling are shown in Section 10. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 6-3 www.rpacan.com With the closure of the mines at Elliot Lake in the 1990s, the claims held by Rio Algom were allowed to lapse. The near-surface part of the deposit was staked by CanAlaska in October 2004 and January 2005. CanAlaska carried out a compilation of historic data on the property but did not conduct any exploration surveys or drilling. The property was acquired by Pele Mountain as described in Section 4. In October 2006, Pele Mountain drilled one hole on the property (PM-1) for assessment purposes. An Inferred Mineral Resource estimate based on results of historic drilling was reported in January 2007 (Cochrane and Roscoe, 2007) at 30 Mt grading 0.050% U3O8 containing approximately 33 million pounds of U3O8. This Mineral Resource estimate is superseded by the current estimate. Pele Mountain drilled another 56 holes under the supervision of Scott Wilson RPA in early 2007. A Preliminary Assessment report presented an updated Mineral Resource in October 2007 (Cochrane et al., 2007) consisting of 5.7 Mt grading 0.051% U3O8 containing approximately 6.4 million pounds of U3O8 in the Indicated category, and 37.3 Mt grading 0.044% U3O8 containing approximately 36.1 million pounds of U3O8 in the Inferred category. This Mineral Resource estimate is superseded by the current estimate. Pele Mountain conducted exploration and infill drilling programs from October 2007 to August 2009, resulting in 114 new drill holes targeting the MCB. In November 2010 Pele Mountain sent 1,283 pulps to SGS from MCB intercepts collected previously for a pulp re-assay program, targeting rare earth elements, Yttrium and Scandium. A PEA was released in August 2011 (Cox et al., 2011), including an updated Mineral Resource consisting of 14.3 Mt grading 0.048% U3O8 and 0.164% TREO containing approximately 15.2 million pounds of U3O8 and 51.9 million pounds of TREO in the Indicated category, and 33.1 Mt grading 0.043% U3O8 and 0.132% TREO containing approximately 31.4 million pounds of U3O8 and 96.4 million pounds of TREO in the Inferred category. This Mineral Resource estimate is superseded by the current estimate. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 6-4 www.rpacan.com TABLE 6-1 HISTORIC DRILL HOLE SUMMARY Pele Mountain Resources Inc. – Eco Ridge Mine Project Year Operator 1954 1955 1953-54 1954-55 1955 1955 1967 1965-69 1974 McIntyre Porcupine Mines Pardee Amalgamated Algom Uranium Mines Ltd. New Jersey Zinc St. Mary’s Stancan Uranium Corp Kerr-McGee Corporation Riocanex and Rio Algom Mines Rio Algom Number of Holes 28 30 15 23 1 2 2 5 1 Metreage Hole Numbers 2,498 6,567 1,486 7,201 642 1,744 3,058 5,269 489 S-1 to S-28 PA-1 to PA-29CPA -24 PW-101 to PW-115 CB-1 to CB-23 E-2 Z-5-1 to Z-5-2 143-2 to 143-3 CB-30 to CB-35 (all wedged) CB-36 Note: CB-30 to CB-35 were wedged from the parent holes to provide duplicate intersections HISTORICAL MINING Historically, mining and processing operations were carried out in the Elliot Lake area, but not on the Eco Ridge Mine property. The mining at Elliot Lake was all by underground methods, primarily room and pillar, with shaft access. The major portion of the ore mined was processed through conventional uranium processing plants, with some production from underground leaching. The Elliot Lake mineralization also contains rare earth oxides. Yttrium oxide and heavy rare earth oxides were recovered at the Denison mine in the past, as by-products of the uranium production. 2007 PRELIMINARY ASSESSMENT The 2007 PA proposed a mining method consisting of a combination of panel drifting and longhole slashing, followed by uranium recovery via leach processing. This scenario involved significantly reduced mining and processing costs relative to the room and pillar and conventional processing methods previously used at Elliot Lake. Approximately 40% of the mine production was proposed to be transferred to the surface for processing in a conventional acid-leach plant, while the remaining 60% was proposed to be broken down and left in place underground for extraction of the uranium by bioleaching. The mining and processing parameters were used to extend the evaluation to the Inferred Resources adjacent to the Indicated Resources to achieve a 20 year mine life, including decommissioning. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 6-5 www.rpacan.com 2011 PRELIMINARY ASSESSMENT In preparation for the 2011 PEA, Pele Mountain assayed for rare earth elements, and commissioned testwork on rare earths processing. RPA estimated Mineral Resources for rare earths and uranium. The 2011 PEA indicated that positive economic results could be obtained for the Eco Ridge Mine Project, in a scenario that includes room and pillar mining, and uranium and rare earth recovery by leaching both on surface (heap leach) and underground (in-situ bio-leach). Leaching recoveries ranged from 70% for uranium, to 38% (average) for heavy rare earths, and 11% (average) for light rare earths. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 6-6 www.rpacan.com 7 GEOLOGICAL SETTING AND MINERALIZATION REGIONAL GEOLOGY The Elliot Lake area lies within the Precambrian Canadian Shield of Northern Ontario, Canada, at the boundary between the Southern and Superior Geological Provinces. Three major regional lithological components and two regional structural components locally influence the initial deposition and subsequent deformation of the Elliot Lake mineral deposits: The Archean-age basement made up of metavolcanic and metasedimentary rocks, granite and minor mafic intrusive rocks of the Superior province; Proterozoic-age Huronian metasedimentary intercalated mafic volcanic rocks; Post-Huronian intrusive rocks including Nipissing diabase sills and post Nipissing diabase dykes and sills, small felsic intrusive bodies and lamprophyre dykes; Regional folding and thrust faulting during the Penokean Orogeny; Faulting during the late Proterozoic. rocks containing minor The major geological provinces and the crosscutting structures within the region are shown in Figure 7-1 and a table listing the formations is shown in Table 7-1. TABLE 7-1 TABLE OF FORMATIONS IN THE REGION Pele Mountain Resources Inc. – Eco Ridge Mine Project Period Province or Complex Dominant Lithology Age – Ma Paleozoic Ordovician Limestone 448 - 443 Mid-Proterozoic Grenville Variable, highly metamorphosed 1,200 - 1,000 Mid- Proterozoic Keweenawan Mafic Volcanics 1,225 Early Proterozoic Nipissing Diabase Gabbro and Diabase Intrusions 2,115 Early Proterozoic Huronian Supergroup Clastic Sediments 2,450 - 2,115 Archean Superior Granite and Metavolcanics >2,500 Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 7-1 www.rpacan.com The Huronian metasedimentary and basal volcanic rocks lie unconformably above the Archean basement. They are part of the Huronian Supergroup, portions of which extend across the region from Sault Ste. Marie in the west to the Cobalt Area near the Quebec border in the east. The Huronian sedimentary rocks are interpreted to have been deposited during a period of marine transgression from south to north, commencing with quartzite, conglomerates, and argillite with local intercalated mafic volcanics followed by more mature clastic sediments and marine evaporates. The source of the sediments is the Archean rocks of the Superior province to the north. The unconformity with the basement rocks is sharp in some places and at others is represented by several metres of regolith. The Huronian Supergroup has been divided into four groups, each containing several formations (Table 7-2). TABLE 7-2 STRATIGRAPHY OF THE HURONIAN SUPERGROUP Sault Ste Marie – Sudbury – Cobalt Region Pele Mountain Resources Inc. – Eco Ridge Mine Project Formation COBALT GROUP BAR RIVER FORMATION GORDON RIVER FORMATION LORRAIN FORMATION GOWGANDA FORMATION Orthoquartzite, siltstone Siltstone Arkose, orthoquartzite Polymictic conglomerate, quartzite, siltstone, argillite QUIRKE LAKE GROUP SERPENT FORMATION ESPANOLA FORMATION BRUCE FORMATION Orthoquartzite Greywacke, limestone Limestone, siltstone HOUGH LAKE GROUP MISSISSAGI FORMATION PECORS FORMATION RAMSAY LAKE FORMATION Orthoquartzite Greywacke, argillite, quartzite Polymictic conglomerate ELLIOT LAKE GROUP McKIM FORMATION MATINENDA FORMATION LIVINGSTONE CREEK FORMATION Description Greywacke, argillite, quartzite Stinson Member: Polymictic conglomerate Ryan Member, Manfred Members: Arkosic quartzite Mafic Volcanics with intercalated feldspathic quartzite and conglomerates Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 7-2 www.rpacan.com POST HURONIAN IGNEOUS INTRUSIONS The primary intrusive event affecting the region and the Elliot Lake District was the intrusion of the Nipissing diabase sills and dykes. These intrusions are dated at 2,120 Ma (Van Schums, 1976). The sills and dykes have been folded during the Penokean Orogeny and have been metamorphosed to greenschist facies. The Nipissing diabase is primarily found as intrusions in the Huronian sediments, but the intrusions are also found in the underlying Archean rocks. STRUCTURAL GEOLOGY The major structural event that has deformed the Huronian sedimentary rocks is the Penokean orogeny which affected the region between about 1,850 Ma and 1,750 Ma (Van Schmus, 1976). The deformation caused by the Penokean Orogeny resulted in folding and thrust faulting of the Huronian sedimentary rocks. The Murray and Onaping fault systems are composed predominantly of strike-slip faults that were formed some time after the Grenville orogeny (post 1,000 Ma). These faults generally strike northnortheast and east. REGIONAL URANIUM OCCURENCES Uranium and thorium occur within the Huronian Supergroup at a number of localities in the region. Most of the occurrences are in conglomerates, but some are in coarsegrained quartzite referred to locally as “grit”, and in quartzite and argillite. The only uranium deposits known to contain sufficient grade and tonnage to be economically viable occur in the lower part of the Matinenda Formation within about 40 m of the basement. The majority of the exploitable uranium deposits are found in the Elliot Lake area. The Pronto Mine is located in the Blind River area and the Agnew Lake Mine is located about 60 km west of Sudbury. The Huronian sedimentary basin is one of a number of early to mid-Proterozoic basins in Canada that host, or has the potential to host, uranium deposits. Others include the Athabasca Basin in Saskatchewan, the Thelon Basin in Nunavut, the Otish Region in Quebec, and the Sibley Basin in Ontario (Jefferson et al, 2005). Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 7-3 85° 84° 83° 82° 47° N ADA CANS.A. U. SUPERIOR PROVINCE Lake Superior 129 PROJECT LOCATION Sault Ste Marie Quirke HURONIAN SUPERGROUP Murray 17 7-4 Fault Synclin e Elliot Lake Chiblow Anticline 108 Murray Fault 17 MICHIGAN BASIN Blind River Massey Lake Huron 85° 84° 46° 82° 83° 0 10 20 30 40 50 Kilometres Figure 7-1 Legend: Fold Axes Fault Proterozoic Metasedimentary Rocks Town Proterozoic Plutonic and Volcanic Rocks Road Archean Granitoid Rocks Archean Greenstone Terranes June 2012 Source: CanAlaska Ventures Limited, Adapted from O.G.S. Map 2670, Johns et al, 2003. Pele Mountain Resources Inc. Eco Ridge Mine Project Elliot Lake, Ontario, Canada Regional Geology www.rpacan.com Paleozoic Sedimentary Rocks Paleozoic Sedimentary Rocks www.rpacan.com LOCAL GEOLOGY GENERAL GEOLOGY In the Elliot Lake area, the Huronian sedimentary rocks are folded and form shallow westward plunging, gently folded syncline and anticline structures, referred to as the Quirke syncline and the Chiblow anticline (Figure 7-2). The Elliot Lake uranium deposits are located within the sediments that form the Quirke syncline. The Quirke syncline is flanked on the north and east by Archean granites and on the south by Archean mafic metavolcanic and metasedimentary rocks. On the north, the limbs of the Quirke syncline generally dip from 20o to 40o south and, on the south, the limbs dip from 15o to 30o north. The depth to the centre of the syncline from the present surface is estimated to be approximately 1,500 m. The axis of the syncline plunges gently west at approximately 15o. The Huronian sedimentary rocks are intruded by Nipissing diabase dykes and sills and by younger lamprophyre dykes. The stratigraphy of the Elliot Lake Group, which contains the Matinenda Formation and hosts the uranium deposits, is shown in Table 7-3. TABLE 7-3 ELLIOT LAKE GROUP, ELLIOT LAKE AREA Pele Mountain Resources Inc. – Eco Ridge Mine Project Formation Member Elliot Lake Group McKim Formation Matinenda Formation Livingston Creek Formation Description Banded greywacke and argillite, locally termed “Nordic Formation”. Cross bedding indicates beds were deposited from the NW. Stinson Massive grey quartzite with minor pebble beds and coarse-grained grit. Ryan Coarse-grained quartzite or arkose, pebble bands, and quartz-pebble conglomerates bands, sericitic alteration with distinctive green colour. Contains the conglomerate beds hosting the rare earths and uranium mineralization. Basal Conglomerate or Breccia Quartz pebbles and fragments of basement rocks, pyrite and pyrrhotite in matrix, contains rare earths and uranium mineralization. Amygdaloidal basalt, metamorphosed to greenschist facies, intercalated sediments. Archean Basement Rocks – Metavolcanics, Metasediments, Iron Formation and Granite Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 7-5 www.rpacan.com POST HURONIAN INTRUSIONS The Nipissing diabase intrusions occur as sill-like bodies paralleling the strike of the sedimentary formations, but with steeper dips and as crosscutting dykes. The sills vary in thickness from about 10 m to over 100 m and displace the conglomerate beds hosting the uranium mineralization. The dykes are generally 10 m to 20 m thick and strike predominantly east-west, parallel to the sills, and northwest. These dykes can be mapped and delineated, and are included as a distinct unit in the geological and block model of the mineralization. In a report by Sprague (1965), significant chlorite alteration of the conglomerate bed is described in the zones adjacent to the Nipissing diabase intrusions. In some cases the mineralization could not be mined because the chlorite alteration resulted in the processing problems in the filters caused by the presence of chlorite. These altered zones were generally left in place despite having above average uranium grades, however, they are amenable to underground leaching based on metallurgical testing (CANMET, 1988). The Huronian sedimentary rocks and the uranium deposits are also intruded by narrow lamprophyre dykes. The lamprophyre dykes generally vary in width from less than a metre up to about four metres. The lamprophyre dykes have chilled margins, but there is no evidence of contact metamorphism in the adjacent rocks. Two major trends are exhibited in the strike of the lamprophyre dykes: east-west and north-northwest. Occasionally, these dykes are calcite-rich and they deteriorate rapidly when exposed during underground mining. FAULTING The major fault mapped within the immediate Elliot Lake District is the Flack Lake fault which is located immediately north of the Quirke syncline. The Canyon Lake fault, which was mapped by Robertson (1961), crosses the Eco Ridge Mine property. The Canyon Lake fault is shown displacing both the Huronian sediments and a diabase dyke to the north in Gunterman Township between McCabe Lake and Canyon Lake and recent drilling demonstrates that it extends across the Eco Ridge Mine property. The general geology of the Elliot Lake District is shown in Figure 7-2. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 7-6 www.rpacan.com GEOLOGICAL SETTING AT THE URANIUM AND REE MINERALIZATION The uranium-bearing conglomerate beds are found within thicker sections of the Matinenda Formation that are located over depressions in the underlying basement. These thicker sections are termed channels and the channels generally strike westnorthwest. The Matinenda Formation consists of well-sorted arkosic quartzite with coarse-grained beds containing scattered quartz pebbles. The quartz-pebble conglomerates are enclosed within the quartzite beds. The quartz-pebble conglomerate beds (historically called reefs) containing the uranium and REE mineralization are located within the lower Matinenda Formation about 40 m to 50 m above the basement. The lower Matinenda, designated as the Ryan Member, is characterized by the presence of pebbles, an increase in the amount of pyrite, and a distinctive green colour as a result of sericite alteration. Although the coarser grained quartzite beds commonly contain low-grade mineralization, the higher grade mineralization is hosted within the beds of quartz-pebble conglomerate with disseminated pyrite in the matrix. The number and thickness of the conglomerate beds are not uniform between the channels. In general, the thickest sections and the most number of conglomerate beds occur within the channels which host the higher grade deposits. The channels are separated by topographic highs in the underlying basement, where the sediments of the Elliot Lake Group are thinner or, in some cases, absent. The reefs are located within the channels. The number and thickness of the conglomerate reefs are not uniform between the channels. In general, the greatest numbers of reefs and the highest grade deposits occur in the thickest sections of the Ryan Member. The sedimentary rocks are interpreted to have been formed by the erosion of Archean granite to the north and deposited as sands and conglomerates. The uranium was transported as heavy mineral grains along with quartz pebbles, pyrite, and other heavy minerals such as zircon, rutile, leucoxene and monazite in fast-flowing streams within topographic lows in the Archean bedrock. The quartz pebbles and the heavy minerals were deposited locally where the velocity of the streams decreased. The sediments may also have been re-worked, upgrading the mineralization locally. The two major channels in the Elliot Lake District are the Nordic Channel and the Quirke Channel. Within each of these channels, the conglomerate beds or reefs occur at Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 7-7 www.rpacan.com different stratigraphic intervals. Three other channels have been identified in the syncline, the Pardee, Pecors and Whisky Lake channels (Robertson, 1986). No mining has taken place within these last three channels to date. The locations of the channels based on historic data and interpretations are shown in Figure 7-3. STRATIGRAPHY OF THE MINERALIZED CONGLOMERATE BEDS The stratigraphy of the Lower Matinenda Formation varies between the channels. The stratigraphy of the mineralized reefs within the Pardee Channel on the Eco Ridge Mine property can be correlated with the stratigraphy of the reefs in the Nordic Channel. The Nordic Channel is located on the south limb of the Quirke syncline. The Nordic Channel has an average strike length of about 2,130 m (7,000 ft.) and extends approximately 6,100 m (20,000 ft.) down dip along the limb of the anticline. The channel plunges northwest at an average angle of 17o. The Nordic Channel hosts the former Nordic, Lacnor, Milliken, and Stanleigh mines. Hart and Sprague (1968) describe three conglomerate beds within the Nordic Channel that host the higher grade uranium mineralization: the lower, the middle, and the upper conglomerate reefs. These reefs are located in the bottom 46 m (150 ft.) of the Ryan Member. The stratigraphy of the Ryan Member of the Lower Matinenda at the Stanleigh Mine is shown in Table 7-4 (Golder Associates, 1983). The lower reef or Lacnor Reef is located directly above the basement. The lower reef is generally thin and discontinuous, however, some mining was carried out on this reef in the Stanleigh Mine. At the Lacnor and Milliken mines, the lower conglomerate was mined at an average height of 2.44 m (8 ft.). The parting quartzite divides the lower reef from the middle reef. The parting quartzite contains intercalated quartzite with weak pebble conglomerate bands. The Middle Conglomerate Bed, or Nordic Reef, was the primary unit mined at all the four of the mines located in the Nordic Channel. The cobble size was generally smaller than the cobbles in the lower reef. The average height was 3.0 m (10 ft.). A limited amount of mining took place in the Upper Conglomerate Bed, or the Pardee Reef, and the average mining height was 1.5 m (5 ft.) at the Nordic Mine, but it reached thicknesses of 3.0 m (10 ft.) at the Stanleigh Mine. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 7-8 www.rpacan.com The Floater Reef occurs above the Upper Reef. The Floater Reef is thin and very discontinuous. No mining was carried out on the Floater Reef. Golder Associates (1983) indicated that the surface of the original basement is irregular and the presence of “basement highs” can result in the Lower or Main Reef being absent because they were not deposited. TABLE 7-4 STRATIGRAPHY OF LOWER MATINENDA Stanleigh Mine Pele Mountain Resources Inc. – Eco Ridge Mine Project Zone Thickness (ft) Quartzite - Relative Content of U3O8 (lb/st) - Floater Reef 7 - Quartzite 0 – 20 - Upper Reef 7 1.4 Correlated with the MCB Divider Quartzite Comments Discontinuous Quartzite 20 0.2 Main Reef 10 1.6 Parting Quartzite 8 0.5 Lower Reef 8 1.4 Quartzite Variable - Generally thin Basement - - Metavolcanics Parting Quartzite The Upper Reef in the Nordic Channel is correlated with the MCB in the Pardee Channel on the Eco Ridge Mine property. Figure 7-3 shows a plan of the mineralized reefs and a longitudinal section along the south limb of the Quirke syncline looking north. The section illustrates the correlation of the mineralized conglomerate beds through the Nordic, Pardee, Pecors, and Whisky channels. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 7-9 www.rpacan.com Pele Mountain Property Cutler Granite Cobalt Group Bruce Group Algoman Granite Archean Greenstone Mines Quirke Stanleigh Denison Panel Spanish AM. Stanrock Milliken Lacnor Nordic Buckles Can-Met Pronto Elliot Lake Group Sources: Ore Reserve Estimation and Grade Control, CIM Special Volume 9, 1968, and Robertson , 1986. Figure 7-2 0 4 2 8 6 Pele Mountain Resources Inc. Miles 0 2 4 6 8 10 Eco Ridge Mine Project Kilometres Elliot Lake, Ontario, Canada Geology of the Elliot Lake District June 2012 7-10 www.rpacan.com N 0 0 QUIRKE 2 1 2 3 Miles 4 4 6 5 8 Kilometres Twp. 150 Twp. 144 Twp. 138 Twp. 149 Twp. 143 Twp. 137 Stanleigh Mine WHISKEY PECORS A PARDEE NORDIC Pardee Reef A B Main Conglomerate Bed B Base of Middle Mississagi Conglomerate C 0 PARDEE NORDIC PECORS WHISKEY 0 200 400 600 800 1000 ft Schematic Cross Section A - B - C Legend: Lower Mississagi Formation Figure 7-3 Conglomerate Huronian-Archean Contact at surface Pele Mountain Resources Inc. Granite Greenstone Eco Ridge Mine Project Iron Formation, Outcrop; Magnetic Anomaly Elliot Lake, Ontario, Canada Fault Location of Mineralized Channels Deposit Mineralized Channel June 2012 Source: J. Robertson, 1986. 7-11 www.rpacan.com PROPERTY GEOLOGY The Eco Ridge Mine property is situated to the east of the Nordic Channel on the south limb of the Quirke syncline (Figure 7-2). All the formations within the Quirke Lake Group, the Hough Lake Group, and the Elliot Lake Group are present within the property boundaries, including the Livingston Creek Volcanic Formation. GENERAL GEOLOGY The Archean basement rocks underlying the syncline are primarily metasedimentary, and chloritized metavolcanic. Robertson (1961) mapped the pre-Huronian basement as igneous gabbroic and diabasic rocks, as well as metamorphosed sediments consisting of quartzites, greywackes tuffs and agglomerates, and minor basic lavas. These sediments strike northwest and dip steeply to the northeast. The Archean basement is overlain by east-west trending, north dipping Elliot Lake Group sediments and volcanics with the Livingston Creek Formation forming the basal unit. The Livingston Creek Volcanics are intercalated with minor beds of conglomerate. The Huronian volcanics are directly overlain by a thin ‘green grit’ (possible regolith) from 10 cm to 20 cm thick, which commonly is logged as a fault zone or gouge in the drill core. The mineralization on the property is hosted by conglomerate beds that occur within the Ryan Member. The Ryan Member unit has been designated “Green Quartzite” in the descriptions in the historic drill hole logs and the unit overlying the green quartzite has been logged a “Grey and/or Pink Quartzite” which correlates with the Stinson Member. The Ryan Member is approximately 100 m thick, well sorted quartzite and quartzarenite with intercalated quartz-pebble conglomerates with a matrix of quartz grains. The quartzite has been altered to sericite which imparts the light green colour. Pyrite in the matrix occurs as small grains and can be 3% to 4% and up to 15% in the coarser quartzpebble conglomerate units. INTRUSIONS The Huronian sediments on the property have been intruded by dykes and sills of Nipissing diabase. A prominent Nipissing diabase dyke, averaging 30 m in thickness and striking east-west extends across the entire property, crosscutting the mineralization. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-12 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Narrow dykes of lamprophyre are logged throughout the drilling. These dykes are generally less than a metre in thickness, but they can reach thicknesses of about six metres. These dykes are the youngest geological units on the property. STRUCTURE Based on structural contours of the unconformity, Sprague (1965) interpreted the preHuronian topography as being relatively flat except for two local highs. He suggested that the first high, outlined by drill hole S-10 immediately east of the adit, is probably the extension of a zone of basic rocks in the Archean footwall mapped by Robertson (1961) as gabbros, amphibolites and diabase. Sprague suggested that these massive intrusions would be more resistant to erosion than the enclosing softer rocks and thus would tend to form areas of positive relief. The second area of positive relief was interpreted from holes PW-113, PW-112 and PW-106 on the east end of the property near Pecors Lake. A major structural feature on the Pele Mountain property is the Pecors Lake structure. This fault is shown on Ontario Geological Survey Map 2419 (Robertson, 1961). It is located along the west shore of Pecors Lake and strikes north 60 degrees west across the property (refer to Figure 7-3). Sprague indicated that the direction of movement is observed by the offset on the diabase and suggested a vertical displacement of about 150 m, north side up as indicated in the deep drill holes drilled by Stancan. Based on structural analyses carried out by Scott Wilson RPA and using information from drill holes located north of the Pecors Lake structure, the conglomerate bed containing the uranium mineralization continues to the north of the fault and appears to have been uplifted relative to the location of the conglomerate bed on the south side of the structure. The apparent extension of the Canyon Lake fault to the south is marked by a prominent depression that strikes south 40 degrees east through the Eco Ridge Mine property to the west end of Stinson Lake. This topographic depression continues to the south across the Huronian-basement contact into the Archean basement rocks. A plan showing the general geology of the property is shown in Figure 7-4. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-13 Technical Report NI 43-101 – June 20, 2012 386,000 E 385,500 E 385,000 E 384,500 E 384,000 E 383,500 E 383,000 E 382,500 E 382,000 E 381,500 E 381,000 E 380,500 E 380,000 E on ny Ca La ke N ult Fa Pe co rs Tees Lake La ke 5,139,500 N Fa ult Vanhorn Lake 5,139,000 N Resource Boundary Pecors Lake Pardee Lake 5,138,500 N 7-14 Stinson Lake 5,138,000 N ADIT 5,137,500 N 5,137,000 N Figure 7-4 McKim Property Boundary Matinenda Resource Diabase Drill Hole Fault June 2012 0 250 500 Metres 750 1000 Eco Ridge Mine Project Elliot Lake, Ontario, Canada Property Geology www.rpacan.com Pele Mountain Resources Inc. Legend: Basement Volcanics 5,136,500 N www.rpacan.com MINERALIZATION GENERAL DESCRIPTION The quartzite beds in the Ryan Member in the Pardee Channel have a background grade of about 0.01% U3O8, rising to 0.02% within coarser grained “gritty” beds. The higher grade uranium mineralization is contained within three conglomerate beds, the Basal Conglomerate Bed (BCB), the MCB, which is equivalent to the Pardee Reef, and the Floater Reefs. Limited rare earth assay data are available outside of the MCB intercepts drilled and assayed by Pele Mountain from 2006 to 2011. The available data show that rare earths mineralization continues above and below the Main Conglomerate Bed. The current Pele Mountain sampling protocol targets the conglomerate and pebble beds occurrences, as well as concentrations of heavy mineral bands within the Ryan Member to determine the extent of the mineralization The BCB is located directly above the Archean basement rocks. This unit consists of poorly sorted, angular, and rounded pebbles that are granitic, volcanic and quartzitic and are commonly 2 in. (5 cm) in diameter. It may contain up to 5% pyrite in the matrix. This bed is discontinuous and, in drill holes where it is intersected, is generally thin, averaging about one-half metre in thickness. However, historically, the sampling of the BCB has not been consistent and thicker sections have been intersected at Eco Ridge. The matrix is a grey or grey-green quartzite with up to 10% medium to coarse grained pyrite, and locally some pyrrhotite. The BCB is discontinuous, but, where intersected in the historic drilling, the average thickness is about 0.5 m, although widths up to four metres have been intersected in recent drilling and an intersection of 11 m was returned in drill hole CB-1. Sprague (1965) indicated that the basal reef was interpreted as being too narrow and too local to be of primary interest in Rio Algom’s program, however, he did note that two holes, PA-26 and S-18, cut basal reef averaging 0.07% U3O8 / 1.7 m and 0.126% U3O8 / 1.4 m, respectively. Sprague suggested that detailed drilling of this reef may prove up small tonnages of interest. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-15 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com The MCB is located approximately 10 m to 15 m above the BCB. It is intercalated within the quartzite beds. The MCB and the first few metres immediately above it host the Mineral Resource on the Eco Ridge Mine property. The conglomerate contains quartz, quartzite, and dark cherty pebbles in a fine grained, pyrite-rich matrix. The pebbles make up to 60% of the rock and are most abundant in the lower metre. The pebbles are well rounded and 0.64 cm to 3.8 cm thick. This bed fines upwards with narrow intercalated beds of quartzite. Pyrite occurs in the matrix generally as small grains comprising 4% to 15% of the rock. Sprague reported that the bed varies from 1.3 m to 4.4 m in thickness. The highest grade uranium mineralization within the bed is located in the conglomerate band on the footwall contact with the underlying quartzite. The footwall contact is well-defined and provides a marker for geological assessment. The hanging wall contact is not as distinct due to the increased occurrences of intercalated bands of quartzite within the conglomerate. The MCB contains the higher grade rare earths and uranium mineralization and outcrops on the property and extends over a strike length of 6,000 m. The uranium and REE mineralization has been intersected in holes at a depth of 1,000 m and over a dip length of approximately 3,800 m. A series of thin conglomerate beds are present within the quartzite overlying the hanging wall contact of the MCB. These thin conglomerate beds represent the Floater Reefs. The Floater Reefs generally extend from 6 m to 15 m above the MCB. The Floater Reefs average from 0.1 m to 2.0 m in thickness and the uranium content is generally less than 0.04%. These beds are not well developed on the Eco Ridge Mine property and it is not possible to correlate individual beds between the drill holes. In many cases, quartzite beds logged as “grit” or “pebble conglomerate” contain low-grade mineralization and these pebble conglomerates are probably equivalent to the Floater Reefs. The quartzite with Floater Reefs above the MCB is referred to in this report as the Hanging Wall Zone (HWZ). The stratigraphic units in the Matinenda Formation on the Eco Ridge Mine property are summarized in Table 7-5. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-16 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 7-5 STRATIGRAPHY OF LOWER MATINENDA (RYAN MEMBER) Pele Mountain Resources Inc. – Eco Ridge Mine Project Relative Content of %U3O8 Comments 0.2 – 0.4 0.02-0.04 Discontinuous Quartzite Variable (2 to 10) 0.01 Main Conglomerate Bed 2-3 0.02-0.1 Very Continuous Divider Quartzite 10-15 0.01 Variable in thickness Basal Conglomerate Bed Variable (0 to 11) 0.02 – 0.5 Not Continuous Unit Thickness (m) Quartzite 30 – 40 Floater Reef Livingston Creek Formation (volcanic) – Archean (Greenstone) HISTORICAL MINERALOGICAL STUDIES The primary uranium-bearing minerals reported in the Elliot Lake Camp are uraninite and brannerite. Other uranium minerals that have been reported are pitchblende, coffinite and thucolite. Uranium-bearing, REE-bearing, and associated heavy minerals that have been identified previously at the Elliot Lake Camp are listed in Table 7-6. All minerals deposited with the uranium have a specific gravity of 5.0 or greater and they are also resistant to weathering (hardness of 5.0 or greater), which results in their deposition as heavy minerals within the matrix of the quartz pebble conglomerate beds. TABLE 7-6 URANIUM-BEARING AND ASSOCIATED HEAVY MINERALS Pele Mountain Resources Inc. – Eco Ridge Mine Project Uranium Minerals Formula Uraninite UO2 Specific Gravity 7.5 – 9.7 Brannerite (U,Ca,Ce)(Ti,Fe)2O6 5.4 4–5 Pitchblende UO2 7.5 – 10 5-6 Coffinite U(SiO4)1-x(OH)4x 5.1 5-6 Substitution and Trace Elements Th, Pb, Ra, Ce, Y, other REE Forms series with Thorutite, (33% U) Variety of uraninite, Rare, no substitution Rare, Secondary Thucolite Carbonaceous 3.9 – 4.2 2.5 Also known as “gummite”, rare Monazite (Ce,La,Nd,Y,Th)PO4 4.6 – 5.4 5.0 – 5.5 Minor U Pyrite FeS2 5.0 6.0 – 6.5 Ni, Co Rutile TiO2 4.2 6.0 – 6.5 Fe, Ta Zircon ZrSiO4 4.65 7.5 Hardness 5.5 Heavy Minerals Reported from the Elliot Lake Camp Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-17 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com URANIUM MINERALS URANINITE The uranium mineralization in the Elliot Lake deposits is reported to occur as detrital microscopic uraninite grains within the matrix of the quartz-pebble conglomerates (Theis, 1979). In the main reef at the Denison Mine, Theis reported that the grains commonly show increased concentration near the base of the beds. He also reported that the uraninite grains are more commonly found in samples that contained medium to large quartz pebbles. Theis also reported that the texture of the grains varies from smooth to highly pitted and ragged, suggesting secondary leaching of some grains. Theis reported the following analyses for uraninite: 65% UO2; 6.5% ThO2; 18% PbO and 2.5% Y2O3, with less than 1% Ce2O3. Uraninite also represents a source of rare earths, particularly of heavy rare earths. BRANNERITE Composite grains which contain mixtures of uranium and titanium-bearing phases are referred to as brannerite. The brannerite occurs as skeletal-like grains within rutile and as microscopic blebs in bands and veinlets. Saager and Stupp (1983) determined that U-Ti phases are second only to uraninite as the most important uranium minerals in the Elliot Lake mineralization. Microprobe work confirmed the existence of a continuous mineral series recognized optically, which ranges from uranium-free leucoxene/rutile to uranium enriched brannerite. They suggested that redistribution and subsequent adsorption of uranium on Ti phases during diagenesis and/or metamorphism of the conglomerates resulted in microcrystalline leucoxene/rutile admixtures containing uranium in varying amounts. Theis (1979) found that brannerite was associated with other titaniferous phases throughout the matrix of the conglomerate, which were associated with beds that had medium to smaller size pebbles. Based on 23 microprobe analyses, Theis reported that the brannerite averaged from 31% to 37% UO2. ACCESSORY URANIUM MINERALS Secondary uranium minerals, coffinite, thucolite and pitchblende, have been reported historically. These are thought to be the result of “diagenetic modification” of the original uraninite. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-18 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com ASSOCIATED MINERALS MONAZITE Monazite, a phosphate mineral, is the main mineral containing the REE and the more common form of monazite is enriched in cerium relative to the other REE. The monazite content generally decreases with increasing pebble size and is associated with zircon. This relationship is the opposite of the uraninite which is concentrated in the conglomerate beds with the largest pebble size. The monazite present at the Eco Ridge Mine project is particularly enriched in light rare earth elements. PYRITE In general, the higher uranium grades reported from the mines that previously produced in the Elliot Lake area were hosted by the thickest quartz-pebble conglomerate lenses with high pyrite contents. The pyrite occurs ubiquitously with uranium. The pyrite content was used as a visual ore estimate during mining as the uranium content generally increased proportionally with pyrite. The pyrite is also considered to be detrital, having been deposited in a reducing environment in the early Proterozoic. ACCESSORY HEAVY MINERALS Other accessory minerals Roscoe and Steacy (1958) are hematite, magnetite, monazite, zircon, uranothorite, coffinite, sphene, anatase, rutile, chromite, spinel, epidote, sericite, chlorite, amphibole, apatite, cassiterite, fluorite, barite, pyrrhotite, chalcopyrite, galena, sphalerite, molybdenite, marcasite, and gold. GEOCHEMISTRY General geochemical relationships that have been observed at Elliot Lake are: Uranium and thorium have no significant correlation, suggesting that they are concentrated in separate minerals. The lead content closely parallels the uranium content. There is a general correlation between the pyrite content and uranium. REE mineralization appears to continue beyond the limits of uranium mineralization Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-19 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com MINERALOGICAL STUDIES ON THE ECO RIDGE MINE PROPERTY In 2007, Scott Wilson RPA selected a total of 10 samples from the drill core and sample rejects. One sample was taken from the Floater Reef, six samples from the MCB, and three samples from the BCB. The samples are considered to be representative of the deposit. The samples were sent to the Inco Innovation Centre (IIC) at Memorial University in Newfoundland (MUN) for mineralogical examination using a mineral liberation analyzer (MLA), which is an automated mineralogy system that utilizes a scanning electron microscope (SEM). The results were provided to Pele Mountain in a detailed report (Sylvester, 2007) and the results are briefly summarized here. Overall, the mineralogy of conglomerate in the three beds is dominated by detrital quartz (60% to 70%), orthoclase (10% to 20%) and pyrite (5% to 15%). Secondary muscovite is present in amounts ranging from 3% to 9%. The uranium-bearing minerals and the heavy minerals make up less than 1% of the rock. In 2011 Pele Mountain selected 15 additional samples for mineralogical analysis. The selection included ten samples from MCB, three from BCB and two from pyrite enriched bands. Polished thin sections and polished slabs were prepared from each sample, and the study included examination in normal plain and polarized light, cathodoluminescence, scanning electron microscopy with utilization of energy dispersive x-ray detection, backscattered electron imaging, and x-ray element mapping. This study identified the main uranium minerals to be uranothorite, thorite, brannerite, coffinite, as well as an unidentified uranium silicate containing Ti, REE, Y, S, and Bi. The coffinite, thorite, and the unidentified uranium silicate carry Y and heavy rare earth elements, while the monazite is the most common light rare earth elements-bearing mineral at Eco Ridge (Mariano, 2011). URANIUM MINERALS MAIN CONGLOMERATE BED The uranium mineralization in the deposit is contained within a much greater number of mineral phases than previously reported at Elliot Lake. The mineral phases are similar in all the conglomerate beds, however, the relative amounts of each mineral phase varies between the beds. The uranium minerals, their modal abundance and uranium content, Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-20 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com and the relative contribution of the mineral to the overall uranium content of the six samples from the MCB are summarized in Table 7-7. The only detrital uranium mineral identified is Th-uraninite. All other uranium minerals and mineral phases (pitchblende, brannerite, uranium in rutile, a complex aluminumsilicate-uranium-pyrite mix and a uranium pyrite mix) are minerals that have been formed by secondary processes subsequent to the primary deposition of the uranium as uraninite. The main uranium-bearing minerals in the MCB are pitchblende (Th-poor uraninite) and brannerite. The pitchblende has been deposited from the aqueous alteration of uraninite by oxidizing fluids and has been precipitated by reduction of the fluid upon encountering pyrite. This process has increased the uranium content. The brannerite was formed by the reaction of the uranium in fluids with rutile. The brannerite is associated with muscovite, biotite and rutile. Th-uraninite, the only detrital mineral present, forms 10% of the contained uranium mineralization. Silica-rich minerals and mineral phases (coffinite and a complex aluminum-silica-pyrite-uranium phase) contain about 25% of the uranium. TABLE 7-7 URANIUM MINERALOGY OF THE MAIN CONGLOMERATE BED Pele Mountain Resources Inc. – Eco Ridge Mine Project Mineral Phase Th-uraninite Modal Mineralogy Weight % of Sample 0.057 9 % Contribution to Total Uranium 10 Relative % Brannerite 0.177 27 24 Pitchblende 0.079 12 32 UO2 Rutile 0.074 11 4 UO2-Py-AlSi mix 0.166 26 13 UO2-Py 0.032 5 3 Coffinite 0.067 10 14 BASAL CONGLOMERATE BED The samples selected from the BCB contain higher grade uranium than the samples in the MCB, and the mineralization occurs in altered zones with extensive pyrite and solution cavities, suggesting that these zones represent permeable bands where extensive fluid flow has taken place. The mineralization within the BCB contains the same minerals and mineral phases as the MCB; however, there are a larger proportion Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-21 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com of secondary minerals. The modal analyses, the relative abundances of the uranium minerals and mineral phases and the per cent of the total uranium contained within the mineral or the mineral phase is shown in Table 7-8. Based on the three samples examined, coffinite (U(SiO4)1-x(OH)4x), a uranium silicate, comprises approximately 40% to 45% of the uranium, followed by pitchblende with 19% and composite grains of aluminum-silicate-pyrite-uranium with 15%. Detrital Th-uraninite comprises only about 4% of the mineralization. The presence of coffinite and the aluminum-silicate-pyrite-uranium phase suggests that the fluids depositing the secondary uranium mineralization contained more silica than the fluids forming the secondary uranium mineralization in the MCB. TABLE 7-8 URANIUM MINERALOGY OF THE BASAL CONGLOMERATE BED Pele Mountain Resources Inc. – Eco Ridge Mine Project Mineral Phase Th-uraninite Modal Mineralogy Weight % of Sample 0.019 9 % Contribution to Total Uranium 4 Relative % Brannerite 0.028 5 11 Pitchblende 0.026 5 19 UO2 Rutile 0.039 7 3 UO2-Py-AlSi mix 0.166 39 15 UO2-Py 0.031 6 5 Coffinite 0.189 35 43 GOLD Gold is present in the MCB in amounts ranging from 10 ppb to 40 ppb (0.01 g/t to 0.04 g/t Au). The gold content of the BCB is higher, ranging from 100 ppb up to 900 ppb (0.1 g/t to 0.9 g/t Au). No discrete grains of gold or gold alloy were identified by the MLA. The gold is therefore likely to be dissolved in one or more of the detrital or alteration minerals. The higher content of gold in the BCB suggests that the gold may be associated with the secondary mineralization process and it may be contained within the pyrite. In situ analyses of the minerals would be required to determine the host mineral for the gold and assess its potential for recovery. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-22 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com RARE EARTHS The major carrier of the REE is monazite, which contains over 90% of the REE in the MCB. The remainder of the REE (about 10%) is contained within the uranium minerals uraninite, pitchblende, coffinite and brannerite. DETAILED DESCRIPTION OF MINERALIZED ZONES The geology interpreted from the drilling conducted by Pele Mountain has been consistent with the interpretation based on the historic drilling. Figure 7-5 shows a typical cross section through the deposit. The section illustrates the relative positions of the Floater Reef, the HWZ, the MCB, the BCB and the Nipissing diabase dyke that crosscuts the deposit from east to west. The MCB is a consistent marker and has been intersected in almost all holes drilled on the property. The MCB has an average dip of -21 degrees north and the thickness averages 2.7 m with little variation. The HWZ is the lower grade mineralization continuing above the MCB. The BCB generally parallels the strike and dip of the MCB and is located from 10 m to 15 m below the MCB at the contact with the underlying Livingston Creek Volcanic Formation. The BCB is variable in thickness and is discontinuous in the Adit Block as shown in Figure 7-5. It is thicker and more continuous in the Canyon Lake Block. The Adit block refers to the area of detailed drilling in 2007, in the central part of the deposit. The Canyon Lake block is located on the western side of the Adit block. MINERALIZATION IN THE MCB The thickness of the MCB, the U3O8, and REE grades and their distribution consistent throughout the MCB. The Pele Mountain drilling results are similar to the results from the historic drilling. The uranium analytical results from the twin holes indicate that the historic analyses may be low compared to the current analyses (CB-series holes). The uranium is concentrated primarily within pitchblende and brannerite. The REE mineralization is contained primarily in monazite and the uranium bearing minerals. The gold content of the MCB varies between 10 ppb and 60 ppb. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-23 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com The uranium mineralization is consistently concentrated at the base of the MCB and the uranium content decreases toward the top of the bed. A vertical profile in the grade is shown in Figure 7-6. The data are based on the analyses for drill holes PM-04 to PM-19 drilled in the Adit Block. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-24 Technical Report NI 43-101 – June 20, 2012 5,138,400 N 5,138,200 N 5,138,000 N 5,137,800 N 5,137,600 N 500 Elev 500 Elev S-14 PM-38, 39 400 Elev PM-161 PA-11 PM-19 0.072 / 2.70 PA-3 400 Elev PA-16 0.038 / 2.74 PM-01 PA-28 Dyk e 0.068 / 3.69 Surface 300 Elev bas e 300 Elev Dia 0.038 / 2.94 0.053 / 2.96 0.056 / 2.99 7-25 200 Elev Bas eme 0.051 / 2.97 nt C onta 200 Elev 0.057 / 2.38 ct 0.084 / 2.63 0.042 / 2.57 100 Elev 100 Elev 0 Elev Figure 7-5 0 Elev Pele Mountain Resources Inc. “Floater” Conglomerate Beds Basal Conglomerate Bed Eco Ridge Mine Project Main Conglomerate Bed Assay Result: U3 O 8 % / metres Hanging Wall Zone Basement Contact Drill Hole Trace June 2012 0 50 100 Metres 150 200 Elliot Lake, Ontario, Canada Typical Cross-Section through the Adit Block www.rpacan.com Legend: www.rpacan.com FIGURE 7-6 VARIATION IN URANIUM CONCENTRATION IN THE MAIN CONGLOMERATE BED Vertical variation in U in MCB 3 Height from base of MCB (m) 2.7 2.4 2.1 1.8 1.5 1.2 0.9 0.6 0.3 0 0.000 0.020 0.040 0.060 0.080 0.100 0.120 %U3O8 Adit block basedon17holes MINERALIZATION IN THE HWZ The thickness of the HWZ is variable, while the U3O8 and REE grades are less variable. The HWZ represents the lower grade mineralization in the floater reefs and quartz grit immediately above the MCB conglomerate. The uranium is concentrated primarily within pitchblende and brannerite. The REE mineralization is contained primarily in monazite. MINERALIZATION IN THE BCB The BCB is located at, or close to, the unconformity between the Huronian sediments and the underlying volcanic rocks. The BCB is narrow and discontinuous within the Adit Block, but thicker and more continuous in the Canyon Lake Fault block. The variation in the grade of the mineralization in the BCB does not exhibit a consistent pattern across the BCB. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-26 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com The uranium mineralization is higher grade relative to the mineralization in the MCB. The secondary mineralization in the BCB, when present, is associated with porous alteration zones containing massive pyrite, extensive solution cavities, and chlorite and carbonate alteration within coarse conglomerate. Mineralogical studies indicate that the U3O8 in the BCB is contained in secondary minerals: coffinite, uraninite-pyrite-alumosilicate composite grains, and pitchblende. Detrital uranium minerals compose less than 5% of the uranium minerals. The mineralogy of the uranium minerals and the concentration of the mineralization within permeable alteration zones suggest the uranium has been deposited by secondary concentration from silica-rich fluids. The gold content of the zones containing the secondary mineralization is enriched compared to the MCB. DISCUSSION OF MINERALIZED ZONES The MCB is a continuous unit, except in areas of the greatest topographic highs, where the basement depth is higher than the position of the MCB. In these areas, the MCB pinches out against the basement volcanic formation. This appears to occur only in one location. Otherwise, the variations in the depth to the basement do not appear to affect either the grade or the thickness of the MCB. The HWZ is a continuous unit, trailing the MCB and including the floater reefs immediately above the MCB. The thickness and frequency of the floater reefs influence the thickness and continuity of the HWZ. The relationship between the depth of basement and the presence of the sections of conglomerate is more pronounced within the BCB. The BCB is thickest and most continuous in the deepest portions of the basin. The BCB represents a distinct style of mineralization compared to the MCB. The BCB appears to have been deposited initially as a sedimentary deposit of coarse-grained quartzite or conglomerate at or immediately above the contact with the underlying volcanics. Although the intersections in the BCB are generally narrow, the uranium grade is typically higher than the grades in the MCB and the higher grade mineralization over thicker sections have been intersected. The higher grade mineralization is associated Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-27 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com with permeable zones within the BCB where fluid flow has reacted with pyrite to deposit secondary uranium minerals and mineral phases high in SiO2, such as coffinite. The presence of pyrite or other sulphide minerals appears to be a very important factor in the deposition and concentration of the secondary uranium. Although secondary enrichment has occurred in the MCB, the process appears to be more efficient in the BCB and may have resulted in the formation of thicker lenses of higher grade uranium. The secondary enrichment in the MCB has upgraded the uranium only locally and the secondary mineralization within the MCB is concentrated at the base of the bed where the highest grades occur. In general, the base of the MCB is in sharp contact with very low grade quartzite. GEOCHEMICAL RELATIONSHIPS AND METALLURGICAL IMPLICATIONS RARE EARTH OXIDES Recent and historic drilling by Pele Mountain has confirmed that REE mineralization is widespread outside of the MCB. The relative percentages of the individual REE within the MCB and the BCB are shown in Table 7-9. The distribution of the REE within each of the beds is different. The REE content of the BCB is significantly less than the REE content of the MCB and the relative distributions of the REE are also different, as shown in Table 7-10. The REE content of the MCB is dominated by the light REE (La, Ce, Pr, Nd, and Sm) which constitute 88% of the REE content. The remainder of the REE is the heavy REE which make up 12% of the REE content in the MCB. The relative distribution of the REE in the MCB is consistent with the distribution of the REE within the mineral monazite ((Ce,La,Nd,Y,Th)PO4). Although monazite is the major carrier of LREE in the BCB, a greater percentage of HREE are also contained within the uranium minerals and, in particular, coffinite. The relative amount of monazite in the BCB is less than the amount in the MCB, which accounts for the lower REE content in the BCB relative to the MCB. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-28 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 7-9 RELATIVE PERCENTAGE OF INDIVIDUAL RARE EARTH ELEMENTS Pele Mountain Resources Inc. – Eco Ridge Mine Project REE Yttrium (Y) Cerium (Ce) Dysprosium (Dy) Erbium (Er) Europium (Eu) Gadolinium (Gd) Holmium (Ho) Lanthanum (La) Lutetium (Lu) Neodymium (Nd) Praseodymium (Pr) Samarium (Sm) Terbium (Tb) Thulium (Tm) Ytterbium (Yb) MCB 4.5 45.2 1.2 0.5 0.1 2 0.2 24.1 0 14.4 4.6 2.5 0.3 0 0.4 BCB 16.5 31.8 3.9 1.9 0.6 4.2 0.7 16 0.2 14 3.9 4 0.7 0.2 1.4 The recovery of REE contained within the monazite increases greatly by acid baking. Over 90% of the REE in the MCB are contained within monazite and the remainder is contained within uranium minerals. The recovery of the REE to leaching is discussed in Section 13. The correlation coefficient between uranium and rare earth and other elements (ppm) for the resource assays ranges from 0.03 to 0.72 (Table 7-10). The LREE have generally a lower correlation coefficient with uranium than HREE. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-29 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 7-10 CORRELATION BETWEEN URANIUM AND RARE EARTHS Pele Mountain Resources Inc. – Eco Ridge Mine Project Element La Ce Pr Nd Sm Eu Gd Tb Dy Ho Er Tm Yb Lu Y Sc Th Correlation factor 0.28 0.31 0.32 0.34 0.45 0.52 0.54 0.64 0.70 0.70 0.72 0.72 0.72 0.66 0.63 0.02 0.46 The correlation factors between the HREE ranges from 0.71 to 0.99, and between LREE from 0.93 to 0.99. The relatively poor correlation coefficients between uranium and REE assay results concur with the mineralogical observations made by Sylvester, 2007. Much of the HREE come from same minerals as uranium, while for the LREE only a small fraction comes from uranium bearing minerals. The low correlation coefficient suggests that the distribution of the REE should be investigated apart from uranium. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 7-30 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 8 DEPOSIT TYPES Uranium occurs in a number of different igneous, metamorphic and sedimentary environments. The primary deposit types that are currently being exploited for uranium are sandstone-hosted deposits, unconformity-related deposits, and metamorphic vein deposits. Uranium is also produced as a by-product from hematite breccia deposits at Olympic Dam in Australia and from quartz-pebble gold deposits in the Witwatersrand Basin in South Africa. Geological studies on the uranium-gold deposits in the Witwatersrand Basin in South Africa and the uranium deposits in the Blind River-Elliot Lake region of Canada have resulted in the definition of the uranium-gold bearing quartz-pebble conglomerate class of mineral deposit (Robertson 1986). Uranium is produced from the Witwatersrand deposits as a by-product and the conglomerate bands are commonly referred to as “reefs”. This terminology was used at Elliot Lake to designate the uranium-bearing conglomerate beds. The Quartz-Pebble Conglomerate Deposit types also occur at other localities, such as the Jacobina District in Brazil, and at certain locations in Australia, however, these deposits have mostly not yet been exploited. The Elliot Lake deposits are interpreted to be modified paleoplacer (detrital) deposits and the source rocks are believed to be pegmatitic granite (Robertson, 1986) located to the north. The uranium and rare earth-bearing heavy minerals were released from the granites as a result of weathering and transported to the site of deposition in channel systems in Early Proterozoic sedimentary basins. Heavy mineral grains along with quartz pebbles and pyrite were deposited from fast-flowing streams in topographic lows in the Archean bedrock. With the current oxygen content of the atmosphere, the uranium minerals would oxidize and dissolve in the ground water and be transported in solution. It is suggested that the erosion and sedimentation took place in the early Proterozoic in a reducing environment as a result of the low oxygen content of the atmosphere prior to 2,200 Ma. The quartz pebbles and the uranium and associated heavy minerals were deposited in areas where the velocity of the streams was reduced, forming conglomerate beds in deltaic piles. Peripheral to the conglomerate beds, poorly sorted feldspathic sand and silt were deposited. Subsequent diagenesis resulted in the formation of the conglomerate Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 8-1 www.rpacan.com beds intercalated within coarse sandstone with scattered pebbles and siltstone. At the Denison Mine, the highest grade uranium mineralization occurred to the lee of basement highs where the flow was more abruptly reduced (A. MacEachern, personal communication, in Cochrane et al, 2007). There has been post-depositional alteration of the uranium as evidenced by the formation of brannerite, secondary pyrite and the formation of secondary quartz and sericite (Robinson and Spooner, 1984). Robinson and Spooner suggest that this postdepositional modification was caused by low Eh near-neutral ground water. The mineralogical examination of the Pardee deposit supports this suggestion and demonstrates that the uranium is now primarily contained within secondary uranium minerals as a result of the interaction of the detrital uraninite with groundwater. Within the MCB, the deposition of the secondary minerals appears to have been limited causing local upgrading of the uranium content in some areas and leaching in others. For the heavy REE there is a predominant contribution from secondary mineral phases, while the light REE are predominantly found in detrital minerals. EXPLORATION MODEL In the MCB, it appears that the formation of the secondary uranium mineralization has not transported the uranium any significant distance from the initial point of deposition during sedimentation. Therefore, a detrital depositional model is still considered to be applicable to exploration for the uranium mineralization contained in the MCB. The exploration model at Elliot Lake consists of drilling the lower Matinenda Formation to test and outline the MCB and the HWZ. The quartz-pebble conglomerate beds have formed within the thicker sections of the Lower Matinenda Formation in topographic lows in the underlying basement rocks, forming the uranium-bearing channels. The channels are identified and outlined based on general isopach maps of the host sedimentary formation. The initial exploration is focused on identifying these channels. Within the channels, the highest grade sections within the quartz-pebble conglomerate are concentrated locally where the physical conditions such as topographic highs in the basement rocks may have reduced the velocity of the streams. The uranium minerals, the quartz pebbles and other heavy minerals are generally concentrated along the flanks Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 8-2 www.rpacan.com of the topographic highs. Although secondary enrichment has occurred in the MCB, the uranium has not been transported any distance and secondary enrichment does not appear to be the primary process controlling the uranium grade. SECONDARY ENRICHMENT MODEL Although the secondary enrichment of the uranium appears to be local within the MCB, there is also evidence that the uranium has been leached and transported greater distances in the BCB at the base of the sediments. Therefore, any exploration program at Elliot Lake should also consider the potential for secondary enrichment deposits resulting from the interaction of ground water with either deep hydrothermal fluids that may have mobilized along faults or the presence of iron-rich rocks. Along with uranium, heavy rare earth elements are likely to have been subjected to secondary enrichment. Jefferson et al. (2005) have indicated that several Paleoproterozoic and Mesoproterozoic basins in Canada, including the Huronian Basin which hosts the Elliot Lake deposits, are considered to have potential for unconformity-related uranium deposits. Unconformity deposits are extremely high grade and result from the deposition of uranium from secondary fluids that come in contact with a reducing environment. In unconformity deposits, the uranium is deposited primarily as pitchblende in faults or fractures at the unconformity between the sediments and the underlying basement, or within faults or fractures in the overlying sediments or the underlying basement rocks. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 8-3 www.rpacan.com 9 EXPLORATION Pele Mountain has been systematically exploring and evaluating the Eco Ridge Mine Property since October 2006. Pele Mountain carried out exploration programs in 2007, 2008, 2009, and 2011 oriented mostly towards infill drilling. Some of the programs also included step-out drilling. Pele Mountain’s exploration programs have consisted primarily of diamond drilling, mineralogical analysis and metallurgical testing. The results from the drill programs are described in Section 10 of this report. In 2010, Pele Mountain reassayed pulps from the 2007-2009 drilling programs to obtain REE, yttrium and scandium data. In 2011 Pele Mountain conducted a sampling and assaying program on core from previous drill programs, aimed at intercepts above the MCB, to help delineate the HWZ. TOPOGRAPHIC SURVEY Pele Mountain contracted Dudley Thompson Mapping Corporation Inc. (Dudley) of Surrey, British Columbia, to carry out an aerial survey over the Eco Ridge Mine property. The survey was completed in April 2007 over an area of approximately 4,955 ha. Ten surveyed control points were established on the ground. Black and white aerial photographs at a scale of 1:20,000 were provided. The aerial film was scanned at a resolution of 12 microns using a Wehrli RM-6 scanner and the scanned images were aerotriangulated and adjusted to the control data. Dudley compiled a digital elevation model suitable for the support of five metre contours. GEOLOGICAL MAPPING The geology of the deposit was compiled using government township maps (Robertson, 1961, 1962) and the interpretation of the information provided by the historical and current drilling. In 2007, RPA conducted reconnaissance mapping to determine the surface location of a Nipissing diabase dyke that crosscuts the mineralization. RADIOMETRIC LOGGING In order to validate the analyses from the historic drilling, several of the historic holes were logged using a spectral gamma-ray probe. The spectral gamma-ray probe Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 9-1 www.rpacan.com measures the natural gamma ray emitted by potassium-40, uranium and thorium series isotopes from the rocks in counts per second (cps). Pele Mountain contracted DGI Geoscience Inc. (DGI) to carry out the radiometric logging. DGI provides a number of well logging services including radiometric logging. Their head office is in Toronto and their operations centre is located in Sudbury. A Mount Sopris temperature-compensated, digital spectral gamma probe sampling 1,024 channels in the energy range of 100 keV to 3 MeV was used to obtain gamma emission spectra in time based mode over 15 minute intervals. The probe was calibrated at the United States Department of Energy’s calibration facility in Grand Junction, Colorado, to determine the constant of proportionality (K factor) that relates the instrument’s response in cps to the grade of the material being measured. The K factor must be determined empirically from measurements made in a controlled situation. The facility contains test pits with material of known grade and thickness. The uranium grade determined from the radiometric logging is reported as an equivalent assay (eU3O8) to distinguish it from the determination by chemical analysis. SUMMARY OF RESULTS OF RADIOMETRIC SURVEYS Although the results from the radiometric surveys match the core analyses for many of the new drill holes, the results do not match the core analyses for a number of historic drill holes. In the later cases, the eU3O8 is higher and the results are attributed to secondary leaching of the uranium from the MCB causing disequilibrium. The magnitude of the disequilibrium (and the leaching) varies throughout the deposit. As a result, the radiometric surveys are not recommended as an alternative to determine the uranium content of any of the new drill holes that are drilled. The %eU3O8 determined in the historic holes from the radiometric surveys do not match the historic core analyses. In all cases, the eU3O8 is much higher. The difference may be attributed to disequilibrium, however, it may also be due to the presence of secondary uranium deposited on the drill hole wall. In either case, the radiometric probe cannot currently be used to validate the analyses in the historic holes. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 9-2 www.rpacan.com EXPLORATION POTENTIAL Historic drilling (described below) has intersected the MCB down-dip from the current Mineral Resource and to the east in the resource wireframes. A target for further exploration was estimated for the areas where the historical drilling has demonstrated the presence of mineralized MCB outside of Mineral Resources. A polygonal method was used based on the thickness of the intersections of the MCB, uranium grades, typical TREO grades, and a specific gravity of 2.7. It was estimated that these areas could contain a further 40 Mt to 60 Mt in an exploration target grading from 0.030% to 0.050% U3O8, accompanied by 0.12% to 0.18% TREO for the MCB. The potential quantities and grades of the exploration targets are conceptual in nature and there has been insufficient drilling to define a Mineral Resource. It is uncertain if further exploration will result in the definition of a mineral resource in these areas. More detail on the data supporting the exploration targets is available at the end of Section 14, below. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Technical Report NI 43-101 – June 20, 2012 Rev. 0 Page 9-3 www.rpacan.com 10 DRILLING PELE MOUNTAIN DRILL PROGRAMS Historic drilling is described in Section 6. Figure 10-1 shows the location of the historic drill holes on the property. Pele Mountain has been exploring and evaluating the Eco Ridge Mine property since October 2006. Diamond drill programs were carried out in 2006, 2007, 2008, and 2009. A total of 232 holes were drilled by Pele Mountain on the property. Out of these, 214 investigated the MCB or other targets and 18 are geotechnical holes. The early Pele Mountain drilling was aimed at confirming the historical data, and then it focused on delineating the mineralized conglomerate. One drill hole was drilled in 2006 to confirm the historic drilling. Two drilling programs, from January to March 2007 and from April to August 2007, were executed to provide data for the 2007 PA (Cochrane et al, 2007). Exploration and infill drill programs were carried out from October 2007 to June 2008, from June 2008 to February 2009, and from June 2009 to August 2009, directed towards obtaining a tighter drill spacing for better grade delineation and upgrading of Inferred Resources into the Indicated category, as well as to provide mineralized core material for metallurgical tests. MCB intercepts from 22 drill holes have been used for metallurgical tests (Cox et al, 2011). In 2011 Pele Mountain conducted an infill and step-out drill program aimed at upgrading Inferred Resources into Indicated category and to explore the down-dip continuation of the MCB to the north. DRILLING PROCEDURES The drilling was conducted by independent drill contractors, using a dieselpowered core drill. The drill rods were thin-wall BQ, NQ, and HQ. The drill used initially was capable of drilling up to 350 m. Drills used in later drill programs were capable of drilling past 700 m. Each run consisted of three metres. It took two rods to complete one run. Typically, it took an hour for four runs. The drill crew marked any lost core or faulted area on metreage marker as indicated by loss of water or water pressure in the hole. Core recovery was excellent, with less than 1% of the core lost. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 10-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Upon completion of drilling, all material and waste were removed from the site. The sludge was removed and buried and the hole was capped with a removable metal cap. DRILL HOLE DEVIATION SURVEY Pele Mountain drill holes were surveyed by two different instruments. Holes PM-001 to PM-022 were surveyed with an Icefield MI-03 instrument, with stations at every five metres. Holes PM-023 to PM-213 were surveyed with a Ranger Multifunctional Tool. This tool measures inclination, azimuth, gravity roll, magnetic dip, magnetic interference, and temperature. Communication with the tool is with infrared link with RSC (ranger survey controller). The tool employs a Triaxial Accelerometer (accuracy +\- 0.2 degrees), a Triaxial Fluxgate Magnetometer (accuracy +\- 0.5 degrees) and a temperature sensor packaged in a solid state brass alloy tube. The tool is employed in open hole environments with stations taken at 10 m intervals. RESULTS FROM THE PELE MOUNTAIN DRILLING The results from the 2006-2011 drilling were used to prepare the MCB and HWZ block model based on U3O8 and REE grade optimization. The locations of the recent holes are shown in Figure 10-2. The average thickness of the intercepts in the 2006-2011 drilling was 2.7 m for MCB and 6.5 m for the HWZ. The highest U3O8 and REE grades in the MCB consistently occured at the base of the bed, and the grade decreased toward the top of the MCB. In the HWZ the higher grades were related to the presence and frequency of floater reefs. The U3O8 grades of the intercepts were within the range indicated by historic drilling on the property. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 10-2 Technical Report NI 43-101 – June 20, 2012 -36 CB Z-5-1 5140000 N N Resource Outline CB-22A CB-17 4 CB-3 E-2 5139000 N CB-21 CB-15 CB-23 C-PA-24 CB-20 CB-13 Property Boundary CB-18 CB-12 CB-30 Canyon Lake Area PA-21 PA-29 PA-23 PA-20 PA-19 3 PA-17 PA-9 PA-7 PA-10 10-3 PA-16 CB-11 PA-13 PA-5 PA-6 CB-8 PA-11 PA-2 S-28 S-26 PA-3 PA-1 S-10 S-23 CB-7 CB-9 S-24 PA-4 S-22 CB-10A CB-2 PA-26 PA-8 CB-14 PA-14 5138000 N PA-15 PA-24 CB-3 2 CB-3 PA-12 PA-27 PA-28 PA-25 CB-31 CB-16 PA-18 PA-22 S-21 S-20 S-19 S-18 S-17 S-16 S-15 S-14 S-12 S-9 S-6 S-7 S-5 S-4 S-2 S-3 S-25 S-27 S-1 S-11 S-13 CB-6 CB-4 Cross Section Adit Area CB-1 CB-5 385000 E 384000 E 383000 E 382000 E 5137000 N 381000 E 380000 E CB-3 Figure 10-1 Property Boundary Resource Historic Drill Hole Powerline Road/trail June 2012 0 200 400 600 800 1000 Metres Eco Ridge Mine Project Elliot Lake, Ontario, Canada Location of Historic Drill Holes www.rpacan.com Pele Mountain Resources Inc. Legend: -36 CB Z-5-1 5140000 N N Resource Outline CB-22A PM19 8 CB-17 4 CB-3 CB-21 CB-15 CB-23 PM203 C-PA-24 PM190 CB-20 PM152 PA-3 PA-1 S-12 PM0402 PM04 PM069 S-10 S-9 PA-7 PM127 PM141 PM0 79 S-28 PM131 61 PM0 S-3 PM12 9 S-4 PM125 PM137 S-5 66 M0 PM173 PPM176 7 118 PM172 PM171 PM119 PPMM11 PM166 PM165 PM065 PA-9 PPM1 M1 35 36 S-26 PM130 3 PM06 064 PM PM138 S-6 S-11 PM059 0 PM06 S-24 PM124 S-7 PA-15 PA-24 7 PM139 PM043 PM 6 045 PM04 12 5 PM111 MPM114 P1 11 PM S-13P PMM1056 PM109 110 PM S-14 06 PA-12 PM128 S-2 S-1PM062 1 08 PM PM180 2 18 PM178 PM S-15 5 PM05 4 PM05 PM126 PM13 PM 4 M078 00 P 3 8 04 7 04 PM PM 049 PM PM01 PPM M0000 678 58 S-23 57 7 PA-18 S-25 S-27 PM132 8 PM184 18 6 PM185 PMM18 P PM019 0389 PM PM03 PM PM174 PM175 PM0 8 PM15 1 PM14 2 3 3 PM183 PM179 PM189 PM177 116 PM023 PM025 107 S-17 S-166 PM05 PM14037 0365 PM PPM03 PM068 PM144 PM14 44 S-19 S-18 0 PM02 PA-26 149 PA-4 PM0 S-20 PM CB-6 PM024 PM028 CB-2 PM053 PM PM S-21 PM213 PM212 PM14 PM14 PM13 PM080 PM021 PA-8 2 PM05 1 04 PM PM033 PM034 CB-7 PM161 15 3 PM012 001 PM PM PM210 PA-27 PM162 PM070 PM153 PA-2 1 S-22 2 PM03 PM207 CB-9 170 PA-11 PM0 PM155 3 20 PM PM031 PM169 2 PM199 PM168 PM PM201 0 PM20 PM205 PA-5 PA-6 PM150 PA-29 PM146 7 7 PA-10 PA-16 PM022 PA-13 0 PM07 7 74 PM072 PM157 PM001 05 CB-11 PA-17 PA-14 PM209 PM07 PM 1 CB-8 PM211 PM 16 7 5 PM089 PM159 6 PM08 8 PM05 PM164 PM156 PA-28 PA-25 PM082 PA-19 PM084 PM08 3 PM08 PM16 1 PM194 PM204 PM19 PM 085 PA-21 PM16 10-4 CB-14 PM192 CB-10A CB-3 3 2 CB-3 5138000 N 206 PM 208 PM158 PA-22 18 CB-31 PM PPM010 PM00 01 4 P M M0001 PM 0191764 Property Boundary PM196 PM197 1 M07 P PA-23 PMPA-20 154 PM073 11 3 PM PM195 PM090 076 PM PM CB-30 Lake PMCanyon PM099 0 10 1 PM10 Area PM002 PM050 CB-18 CB-12 CB-16 PM14 5 8 18 CB-13 PM PM10 PM E-2 5139000 N PM088 PM193a PM193b CB-4 PM0 026 PM 27 CB-1 Cross Section Adit Area PM103 PM091 PM095 PM PM030 02 CB-5 PM094 PM092 385000 E PM098 383000 E 382000 E 381000 E 380000 E 5137000 N PM097 PM104 384000 E 9 PM093 CB-3 PM102 Legend: PM096 Pele Mountain Resources Inc. Resource Historic Drill Holes Pele Mountain Past Drill Holes Pele Mountain Recent Drill Holes Powerline Road/trail June 2012 0 200 400 600 800 1000 Metres Eco Ridge Mine Project Elliot Lake, Ontario, Canada Location of Pele Mountain Drill Holes PM-001 to PM-213 www.rpacan.com Property Boundary Figure 10-2 www.rpacan.com 11 SAMPLE PREPARATION, ANALYSES AND SECURITY Throughout the Pele Mountain drilling programs the core collected has been sampled using standard core drilling methods. The core has been analyzed at independent commercial laboratories with routine quality assurance and quality control (QA/QC) procedures. It is the opinion of RPA that the sampling method implemented by Pele Mountain at the Eco Ridge Mine Project meets industry standards. CORE HANDLING PROCEDURES Pele Mountain used the following core logging procedures: Core was placed by the driller in well identified, one metre and a half long, labelled wooden core boxes, from left to right, with the start and finish of each drill run labelled with a metreage marker. Core boxes were closed by the driller at the drill site and regularly transported to the core logging facility, and laid out in order of increasing hole depth. The core logging facility is a secure warehouse in an industrial area in the City of Elliot Lake. Signage is posted restricting no unauthorized personnel. Employees working in the building are informed of this restriction. The building is locked and bolted at all times when not occupied. Core box labels and metreage were checked for accuracy, and aluminum labels recording hole number and box number were affixed to the boxes. The core was stored at the core storage facility in Elliot Lake. Core which was split and samples collected were stored inside the locked core storage facility. All other core was stored outside. CORE LOGGING PROCEDURES Specially designed forms including general data such as location, date drilled, diameter, azimuth, dip, etc., were used for logging. Geological data were manually recorded on the drill logs. The drill log includes: lithology, alteration, mineralization, and structure. The handwritten log when completed was transferred to electronic format for analysis. The sample numbers were recorded on the drill logs. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 11-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com SAMPLING PROCEDURES At the Pele Mountain core facility, sampling intervals have been set according to geological and/or mineralogical constraints. From 2006 to 2009 sampling was continuous from the at least one metre above the hanging wall of the MCB to its base. At least one barren sample has been taken from the quartzite underlying the base of the MCB. If there were significant floater reefs above the MCB, sampling was extended into the hanging wall to include these reefs. In 2010, core from holes drilled previously was sampled to approximately 20 m above the base of the MCB. For the 2011 drill program, 20 m or more of core was sampled above the base of the MCB to allow the definition of the HWZ. The sampling interval was variable and dependent upon lithological or mineralogical parameters. From 2006 to 2009, in the floater reefs, sample intervals varied from 0.5 m to 1.5 m. In the MCB, sample intervals varied between 0.1 m and 0.5 m. From 2010, inside the MCB the samples were less than 0.5m long, and above the MCB, into the HWZ and above it, sample length was typically 1 m. The sampling of the BCB was continuous from at least one sample above the contact to at least one sample below the contact. Sample intervals were marked on the core and core boxes with a red lumber crayon, and sample tickets prepared in triplicate. One tag was stapled to the interior of the core tray at the beginning of the sample interval, one tag accompanied the sample, and the remaining tag was used for drill log entry. The core was sampled by halving with a diamond saw. Once sawn, both halves of the core were returned to the core tray. After each sample, the saw blade was cleaned with water. Some of the sampling in the MCB required that one of the sawn halves be halved again to create quarters. Quarter core was submitted for analysis while the remaining quarter core was retained for the geological record and the half core was put aside for future metallurgical testing. Before removing the sample from the core tray and placing it in a plastic sample bag, each sample interval was checked to confirm the sample tag matched the interval being sampled. QA/QC PROCEDURES For control purposes, one blank sample of barren material was included with each batch of 15 to 20 samples, approximately one blank sample per hole. From 2007 to early 2011, the blank samples are diabase dyke intercepts from a gold project at Manitowadge, Ontario, located several kilometres from Eco Ridge Mine Project. In late 2011 the blank material was changed to syenite grab samples, collected at a Pele Mountain gold property in Wawa area. Certified reference material samples DL-1a, UTS-4, UTS-3, SY-3, and SY-4 from CANMET, and OREAS102A from Ore Research & Exploration Pty. Ltd. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 11-2 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com were inserted every 15 to 20 samples for independent assessment of the laboratory performance. Duplicate samples were submitted at a rate of one in 15 to 20 samples to assess the reliability of the grade determination at various grades. Pulp replicates were sent to a different lab for check analyses. Blanks, as well as duplicate pulp replicates were submitted at a rate of 1 in 20. SAMPLE SHIPMENT AND SECURITY OCTOBER 2006 – AUGUST 2007 Bagged and securely closed samples were placed in larger, triple bagged “rice bags”, approximately 15 samples per bag. The name of the client (Pele Mountain) and the sample numbers of the samples contained within the “rice bags” were recorded on the exterior of the second bag. The third bag had the name and address of the recipient recorded on it. Analytical request forms were submitted with each bag and placed in the first bag. Each bag was securely fastened with a numbered security tag and then the bag was photographed so that both the security number and bag number were recorded. The bags were strapped and placed on wooden pallets and transported by a commercial carrier to the laboratories for sample preparation. When the samples were received, the laboratory recorded the sample numbers and assigned a group number. Sample receipt verification was then e-mailed for confirmation. OCTOBER 2007 – AUGUST 2009 Broken sample pieces were placed in properly tagged heavy duty plastic bags. Samples were packed into five litre heavy plastic pails with locking lids. Description of the content, analysis packages, and addresses were also placed in the pail, then the lids were sealed with security tags. The numbered seals were recorded and the information relayed to the laboratory. The name of the client (Pele Mountain), drill hole name, and the sample numbers were recorded on the exterior of the pail, as well as the address of the laboratory. The pails were transported by a commercial carrier to the laboratories for sample preparation. When the samples were received by the laboratory, a work order number was assigned and sample receipt verification was transmitted to Pele Mountain. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 11-3 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com MAY – JULY 2011 Bagged and securely closed samples were placed in larger “rice bags”. The name of the client (Pele Mountain) and the sample numbers of the samples contained within the “rice bags” were recorded on the bag. Analytical request forms were submitted with each bag. Each bag was securely fastened with a numbered security tag, and security number and bag number were recorded. The bags were strapped and placed on wooden pallets and transported by a commercial carrier to the laboratories for sample preparation. When the samples were received, the laboratory recorded the sample numbers and assigned a group number. Sample receipt verification was then e-mailed to Pele Mountain for confirmation. SPECIFIC GRAVITY MEASUREMENTS The specific gravity measurements implemented for the 2007 RPA Preliminary Assessment (Cochrane et al., 2007) were applied to the following drill programs (October 2007, 2008, and 2009) for continual assessment of the deposit for estimation purposes. The average specific gravity is 2.71 g/c3, confirming the value determined for the 2006-early 2007 drill program (Cochrane et al., 2007). Thirty-six samples were submitted to Activation Laboratories Ltd. (Actlabs), Ancaster, Ontario, for specific gravity measurements. The average specific gravity for the quartz pebble conglomerate is 2.76 g/c3, while the quartzite has a specific gravity of 2.65 g/c3. The specific gravity value of 2.71 g/c3 determined in this study concurs with the 2.70 g/c3 used by Rio Algom for its "ore estimates". In this resource estimate, a specific gravity of 2.70 g/c3 is used for tonnage determination. HISTORIC HOLES No information is available concerning the sampling and assaying methods used in the historic drilling for the CB-series and PA-series drill holes. The samples have been analyzed at a number of different laboratories, which most likely include mine site laboratories. The laboratories are generally not identified and there is no comprehensive description available on the assay procedures used. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 11-4 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Robinson (1954) provided a list of check assay results for samples taken from the Sseries holes drilled by McIntyre in the 1954 exploration program. The primary laboratory used was identified as Bell-White, check assays were carried out at the Ontario Department of Mines Laboratory, and some samples were sent to a laboratory identified as “Technical Services Laboratory”. PELE MOUNTAIN DRILLING PROGRAMS Pele Mountain drilling at Eco Ridge property spanned several programs. Samples were sent to several laboratories and up to six different assay methods were used, tailored to accommodate the exploration and mineralization delineating drilling programs. The samples have been sent mainly to SGS and Activation Laboratories. It is the opinion of RPA that the analytical procedures used for assaying the samples collected at the Eco Ridge Mine Project meet industry standards. JANUARY TO MARCH 2007 DRILL PROGRAM For the January to March 2007 drilling program, the samples were sent to SGS Toronto, an accredited laboratory with the Standards Council of Canada, for sample preparation and analyses. The samples were crushed, split, and pulverized and were analyzed using two methods: IMS95R (metaborate fusion with ICP-MS finish) for U, Th, and RRE and ICM40B (multi-acid digestion with ICP-ES and ICP-MS finish) for a suite of 50 elements, including U and S. Some samples were also analyzed for gold with FAI313 method (lead collection fire assay with ICP-OES finish). APRIL TO AUGUST 2007 DRILL PROGRAM For the April to August 2007 program, core samples were sent to Saskatchewan Research Centre (SRC) in Saskatoon for sample preparation and analyses. SRC analyzed the samples for uranium with a multi-element ICP package using an aqua regia digest, with a second analysis using a digestion in a mixture of HF/HNO3/HClO4. Because of variations in the analyses from SRC compared to the historic analyses and the analyses from SGS Toronto, all of the pulps for drill holes were re-analyzed at SGS Toronto using the IMS95R method to ensure consistency in the data used for Mineral Resource estimation. Core samples from the remaining holes in the program were sent to SGS Toronto for sample preparation and analyses. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 11-5 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com The 2007 PA (Cochrane et al., 2007) contains a detailed discussion of the analytical methods employed for samples collected from January to August 2007. OCTOBER 2007 TO AUGUST 2009 DRILLING PROGRAMS The samples collected by Pele Mountain from October 2007 to August 2009 were sent to Actlabs for sample preparation and analyses. Actlabs is an accredited laboratory with the Standards Council of Canada, and is also accredited to ISO/IEC 17025. This accreditation is the standard for analytical testing laboratories. The entire rock or core sample was crushed to a nominal minus 10 mesh (1.7 mm), mechanically split (riffle) to obtain a representative sample and then pulverized to at least 85% minus 200 mesh (75 μm). All of the steel mills at Actlabs had mild steel and did not induce Cr or Ni contamination. As a routine practice, sand was used as a cleaner between each sample. Quality of crushing and pulverization was routinely checked as part of the quality assurance program. Randomization of samples in larger orders (>100) provided an excellent means to monitor data for systematic errors. The data was restored after analysis according to sample number. For soil samples, a 100 g to 150 g aliquot was pulverized in a mild steel ring mill to normally finer than 95% minus 150 mesh. As a routine practice, sand was used as a cleaner between each samples. Uranium was analyzed using three different methods. Package 4B2-standard was used for uranium, thorium, and the rare earth elements. Package U-DNC provides delayed neutron counting for uranium and was assayed if high. Package 1D was used for the soil samples for uranium and rare earth elements. The Actlabs Code 4B and trace element ICP/MS package Code 4B2 was a whole rock package fusion technique that employs lithium metaborate/tetraborate fusion. The resulting molten bead was rapidly digested in a weak nitric acid solution. The fusion ensured that the entire sample was dissolved. This procedure allowed for the major oxides including SiO2, REE and other high field strength elements to be put into solution. The Actlabs U – DNC package was a Delayed Neutron Count for uranium. The Actabs Code 1D technique employed an irradiation with flux wires. An approximately 30 g aliquot was encapsulated and weighed in a polyethylene vial and then irradiated with flux wires at a thermal neutron flux of 7 x 1011 n.cm-2s-1. After a seven day decay to allow Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 11-6 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Na-24 to decay the samples were counted on a high purity Ge detector with a resolution of better than 1.7 KeV for the 1332 KeV C0-60. Using the flux wires the decay corrected activities were compared to a calibration developed from multiple certified international reference materials. Actlabs routinely monitored and documented the reliability of submitted samples to ensure that any sub-samples taken (e.g. from a crushed rock split) were reliable and representative of the original sample submitted. Actlabs maintained a schedule for the maintenance and calibration of equipment used in the laboratory. Records of calibration and performance parameters were maintained for both testing and measuring equipment. SGS Laboratories in Toronto was used for sample check analyses. SGS is an accredited laboratory with the Standards Council of Canada. SGS Minerals Services is also accredited to ISO/IEC 17025. Pele Mountain consulting geologists used the SGS analysis package IMS95R recommended in the PA of October 2007 (Cochrane et al, 2007). PULP RE-ASSAY PROGRAM NOVEMBER 2010 In November 2010, Pele Mountain submitted 1,283 pulps from MCB intercepts collected in the 2008 and 2009 drill programs for re-analysis. The pulps were sent to SGS Toronto to be assayed for REE, yttrium and scandium. The analytical methods chosen were IMS95A (trace elements by lithium metaborate fusion with ICP-MS finish) for REE and Yttrium. The digestion with lithium metaborate is not suitable for producing accurate results for Scandium, hence the ICP40B analysis package was used (four acid digestion with ICP-AES finish) for reporting the latter. MAY - JULY 2011 DRILLING PROGRAM AND EXTENDED SAMPLING PROGRAM NOVEMBER 2011 The samples collected by Pele Mountain from the 2011 drill program and samples collected from core obtained in previous drill programs were sent to Actlabs for sample preparation and analyses. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 11-7 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Uranium and REE were analyzed using the analysis package 4B/4B2, involving metaborate/tetraborate fusion and ICP/MS. Samples with uranium results above detection limit were analyzed via DNC or XRF. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 11-8 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 12 DATA VERIFICATION DRILL HOLE COLLAR SURVEYS Drill hole collar locations and elevations were determined by Paul H. Torrance Surveying using precision GPS measurement. The equipment used to survey was a Leica dual frequency GPS RTK (Real Time Kinematic) system, and the surveys were based on static sessions from Ministry Of Transportation Ontario control monuments. The coordinate values provided were UTM, NAD83 CSRS (Canadian Spatial Reference System) horizontal datum and CGVD28 vertical datum, rounded to one decimal place. DRILL HOLE DEVIATION The historic holes have been tested with acid, providing control points for dip variation along the hole or at the end of the hole. For those with no data regarding the dip, i.e., 18 holes from the CB series, a correction was applied considering variations similar to the neighbouring holes. Pele Mountain drill holes were surveyed by two different instruments. Deviation survey data was provided in digital files. Prior to transfer to the database, the data was scrutinized for errors. Details about the instruments are provided in Section 10. DATABASE Drill log data were formatted accordingly for import into a Gemcom GEMS project database for geological modelling and resource estimation. The drill log data for the Eco Ridge Mine Project contained information acquired from several stages of exploration, during a period of more than 50 years. The database contained drill hole and sample data from several historic drill programs and the recent Pele Mountain drill programs. The historic drill programs were conducted by Pardee in 1955 (series PA, holes 1-29), New Jersey Zinc in 1954-1955 (series CB, holes 1 to 24), Rio Algom in 1967-1979 (series CB, holes 30 to 35, diameter AX and AXT), and McIntyre (series S). There were in total 325 holes in the Gemcom database, containing 29 holes from CB series, 29 holes from the PA series, 27 holes from the S series, and 214 holes from the recent PM Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 12-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com series. There were 143 sample entries for the CB series, 243 samples for the PA series, 58 for the S series, and 7,629 for the PM series. The database contained drill hole collar location, deviation surveys, lithology, sample numbers, sample intervals, and analytical data. For the historic holes the analyses primarily included %U3O8 and there were some samples with ThO2 analysis. For the PMseries holes, the analyses included %U3O8, Th, REE, Y, Sc, S, Au, and P. DATA ENTRY Data were extracted from copies of the original historic drill logs, which contained the core description, sample numbers, sample intervals, and the uranium analyses. The lithology was encoded according to a scheme containing 27 lithological types. Analytical data in the historic drill holes was expressed in mixed units, either as percentage U3O8 or pounds/ton U3O8. ThO2 analysis was available for a few samples only. All the pounds/tons values were converted to percentage U3O8 by dividing the pounds/tons results by 20 before the data were entered into the database. For the drill programs and pulp replicate re-assay program conducted by Pele Mountain in 2006-2011 the core description, sample numbers, sample intervals, drill hole coordinates, and survey data were entered into the database from the drill logs. Core samples were analyzed at SGS in Toronto, SRC in Saskatoon, and at Actlabs in Ancaster. The analyses were sent to RPA and Pele Mountain in printed and digital format. Analytical values were provided in ppm for U, Th, and REE, Y, and Sc, while S in percentages and Au in ppb. Uranium was converted to oxide percentage prior to importing in the database, while Th, REE, Y, and Sc results were preserved in element ppm values. Dhlogger and Microsoft Excel were used for data entry and data were exported as comma separated files and then imported into Gemcom GEMS. Assay data for historic holes were typed by the database operator and imported, while the PM-series assay results were imported from files provided by the laboratory. The drill hole collar locations in UTM coordinates were entered directly into the Gemcom database. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 12-2 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Drill hole deviation survey data were typed for historic drill holes and imported directly when properly formatted digital data was provided, as was the case for most of the Pele Mountain drilling. DATABASE VALIDATION All data imported into the Gemcom GEMS project database were initially in the form of comma separated values file format. Checks on the collar location, lithology, and assay data were performed. Sample and lithology location entries were validated by comparison with drill logs. Drill hole deviations were inspected visually. Collar locations were checked against paper maps and digital topographic surface. Assays were compared with drill logs for historic data and with assay certificates files originated from the laboratory. Assays were also compared by plotting the assay value against lithology. Gemcom GEMS database verification routines were used for database validation The 3D geological model developed in Gemcom shows a good agreement between the historic holes and the Pele Mountain drill programs. PELE MOUNTAIN QA/QC MONITORING Under direct supervision from RPA, Pele Mountain implemented a QA/QC protocol in 2007 that has been continued throughout the Pele Mountain drilling. The QA/QC protocol consisted of regular submission of blanks, certified reference materials (standards), and core duplicates at a rate of one in 15 to 20 samples, as well as pulp replicates to alternate lab. The QA/QC procedures, results, interpretation and conclusions for the 2006-2009 drill programs and the 2010 pulp re-assay program are presented in the 2007 Preliminary Assessment Report (Cochrane et al., 2007) and in the 2011 Preliminary Assessment Report (Cox et al., 2011). Excellent correlation coefficients were found for sample duplicates and interlaboratory checks, demonstrating that samples are representative of the mineralization. No evidence of contamination was revealed by the blanks. The certified reference materials indicated that there was no bias and the level of Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 12-3 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com contamination was not considered significant. Pulp replicates sent to SRC and Actlabs returned assay values with correlation coefficients of 0.99, indicating excellent interlaboratory agreement, as well as good reproducibility with different analytical methods. PELE MOUNTAIN QA/QC PROGRAM 2011 The rock samples from the drill core were analyzed by Actlabs. Actlabs is accredited by the Standards Council of Canada. The samples were analyzed for U, REE, Y Sc, and Th by the 4B2 lithium metaborate/tetraborate fusion - ICP/MS analysis package. Pele Mountain geologists regularly submitted blanks, certified reference material samples, and sample duplicates to monitor the assay results. The control samples were submitted one in every 15 to 20 samples. Pele Mountain personnel inserted 136 samples of blank material in the sample stream. Out of these, 91 samples were diabase dyke core taken from a gold project at Manitowadge, Ontario, while 45 were syenite grab samples from a Pele Mountain gold project in Wawa, Ontario. The diabase material assayed consistently at the Earth uranium background level, as well as consistent REE values. The syenite returned roughly twice the uranium level of the diabase, while the REE values were less homogenous (Figure 12-1). There was no indication of sample contamination. The certified reference material (CRM) samples inserted by Pele Mountain in the sample stream were DL-1a (waste-rock from the Denison Mine) (112 samples), UTS-4 (from Eldor Mine at Rabbit Lake, Saskatchewan) (15 samples), and UTS-3 (from Eldorado Nuclear Ltd., at Beaverlodge, Saskatchewan) (20 samples), totalling 147 samples (Figure 12-2). These CRM are certified for uranium and thorium and have been used continuously throughout the Pele Mountain drilling programs. The CRM were obtained from CANMET. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 12-4 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com FIGURE 12-1 BLANK SAMPLES Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 12-5 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com FIGURE 12-2 CERTIFIED REFERENCE MATERIALS SAMPLES Approximately 175 field sample duplicates were assayed. The correlation coefficient was 0.89 for U3O8 after removing one outlier. The correlation coefficient for Nd was 0.84, and for Dy it was 0.83. This represents a good correlation for field sample duplicates. No bias was identified (Figure 12-3). Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 12-6 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com FIGURE 12-3 FIELD SAMPLE DUPLICATES INDEPENDENT SAMPLING BY RPA During the November 2010 site visit, RPA personnel collected five samples from four diamond drill holes and sent them to SGS for independent assays using the IMS95A analytical package. The samples consisted of the second half of the sampled core retained. The presence of mineralization was confirmed and the assay results were similar to the original samples. A comparison of the assays is listed in Table 12-1. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 12-7 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 12-1 RPA INDEPENDENT SAMPLING Pele Mountain Resources Inc. – Eco Ridge Mine Project Original sample Pulp replicate Hole From To Sample ID U3O8 (%) Pulp ID U3O8 (%) PM075 239.05 239.50 01208 0.248 70973 above DL1 PM078 107.35 107.64 01367 0.023 70972 0.022 PM084 236.29 236.60 01561 0.013 70971 0.016 PM087 199.86 200.02 01646 0.064 70975 0.074 PM087 214.90 215.26 01655 0.056 70974 0.059 Note 1 - the grade of the sample was higher than the upper detection limit imposed by the IMS95A analytical package It is the opinion of RPA that the sample preparation, security, and analytical procedures implemented by Pele Mountain for the Eco Ridge Mine Project meet industry standards. The analysis of CRM, blanks, duplicate pulp samples, and duplicate core samples show acceptable results. RPA considers the database is acceptable to use for resource estimation. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 12-8 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 13 MINERAL PROCESSING AND METALLURGICAL TESTING Results of earlier metallurgical testwork are summarized in the 2007, April 2011, and August 2011 NI 43-101 Technical Reports (Scott Wilson RPA 2007, RPA 2011a, RPA 2011b). In efforts to advance the project, Pele Mountain embarked on a metallurgical testing program to investigate processing methods that will improve the recovery of the REOs that are contained in the Eco Ridge resources. The most recent phase of metallurgical testing was performed by the Saskatchewan Research Council (SRC) in Saskatoon, Saskatchewan. The conceptual process utilizes comminution, magnetic separation, flotation, acid baking, and leaching to extract uranium and REOs. The results were reported in a report and via e-mail and personal communication with SRC (SRC, 2012). SAMPLES Four bulk samples, weighing between 12 kg and 32 kg, were sent to SRC by Pele Mountain contractors. The samples were used to perform physical separation tests, including size reduction, high intensity magnetic separation, flotation, acid baking, and leaching. SAMPLE PREPARATION The samples were prepared using a combination of crushing, screening, and dry milling to reduce the particle sizes to 100% passing 300 µm. Due to the limited sample sizes, the various tests were performed on different samples. It is assumed that the results are comparative and follow up testwork is advancing at SRC that will include tracking individual samples throughout the full testing cycle in preparation for pilot plant testing. For the majority of the tests, the product was screened at 45 µm. The screen oversize, i.e., minus 300 µm plus 45 µm, was separated by gravity and magnetic separation and the screen undersize, i.e., minus 45 μm, was processed by flotation. Since the preliminary flotation recovery of REEs and uranium on the fine particles achieved significantly lower recovery than achieved by dry magnetic separation, a screen size of Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 13-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 20 µm was used to increase the amount of material reporting to the magnetic separation and reduce the amount reporting to flotation. A single Frantz barrier magnetic separation was performed on the plus 20 µm minus 45 μm size fraction. During this separation no obvious electrostatic interference was observed which appears to support an assumption that plus 20 µm is a viable particle size fraction for dry magnetic separation. This size distribution formed the basis of the mass balance and economic analysis that was used to complete the PEA. Ongoing magnetic separation testwork at SRC is transitioning to a focus on wet magnetic separation as a better approach to reducing the size of the particles that can be effectively treated. Testwork is also advancing at SRC on new collectors to optimize recovery for the relatively small amounts that are expected to report to flotation. Bulk sample #3 was screened at 45 µm. The product weights and size distributions are shown in Table 13-1. TABLE 13-1 PRELIMINARY SCREENING SIZE DISTRIBUTION Pele Mountain Resources Inc. – Eco Ridge Mine Project Size (µm) minus 300 plus 45 minus 45 Weight (g) 2,422 787 Weight (%) 75.5% 24.5% The minus 45 µm material was then wet screened at 20 µm. The product weights and size distributions from the wet screening are shown in Table 13-2. TABLE 13-2 PRELIMINARY SCREENING SIZE DISTRIBUTION Pele Mountain Resources Inc. – Eco Ridge Mine Project Size (µm) Weight (g) Weight (%) minus 45 plus 20 minus 20 53.8 84.8 39% 61% From these two size distribution analyses, the overall size distribution was calculated, as shown in Table 13-3. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 13-2 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 13-3 OVERALL SIZE DISTRIBUTION Pele Mountain Resources Inc. – Eco Ridge Mine Project Size (µm) Weight (g) minus 300 plus 45 minus 45 plus 20 minus 20 75.5% 9.5% 15.0% ANALYSES Although x-ray diffraction (XRD) was used at times to quickly evaluate various parameters, lithium metaborate fusions, and inductively coupled plasma (ICP) analyses were used to determine the metallurgical balances. MAGNETIC SEPARATION The magnetic separation tests were performed on bulk sample number #3. The coarse fraction, i.e. minus 300 µm plus 45 µm, was separated into four fractions using three different magnetic field intensities, as shown in Table 13-4. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 13-3 Technical Report NI 43-101 – June 20, 2012 REO Feed Sc2O3 Y2O3 La2O3 CeO2 Pr6O11 Nd2O3 Sm2O3 Eu2O3 Gd2O3 Tb4O7 Dy2O3 Ho2O3 Er2O3 Tm2O3 Yb2O3 Lu2O3 U3O8 8 79 424 796 80 277 39 2 25 3 15 3 5 1 5 1 432 Assays (ppm) Mag1 Mag 2 6,500 G 10,000 G 666.7 3670.8 7014.0 712.8 2507.7 343.2 17.7 207.5 26.1 125.1 24.4 42.2 7.1 38.1 5.3 3372.6 292.1 1899.9 3439.4 348.0 1021.8 161.2 9.0 98.8 12.7 60.3 10.9 19.2 3.2 16.9 2.3 2051.9 Mag 3 18,000 G Tails Mag 1 6,500 G 70.4 362.4 621.6 50.9 175.0 30.3 2.2 24.3 3.3 16.5 3.2 6.0 1.0 5.8 0.8 625.0 7.7 23.5 36.9 3.6 12.2 2.2 0.2 2.0 0.3 1.6 0.3 0.7 0.1 0.7 0.1 42.6 78.8% 80.9% 82.4% 83.4% 84.8% 82.0% 76.4% 78.8% 77.3% 76.4% 76.3% 74.8% 74.9% 73.7% 74.4% 73.0% Recovery (%) Mag 2 Mag 3 10,000 G 18,000 G 7.4% 8.9% 8.6% 8.7% 7.4% 8.2% 8.3% 8.0% 8.0% 7.9% 7.3% 7.3% 7.1% 6.9% 6.8% 9.5% 5.8% 5.6% 5.1% 4.2% 4.2% 5.1% 6.5% 6.5% 6.8% 7.1% 7.0% 7.4% 7.5% 7.8% 7.6% 9.5% Total 92.0% 95.5% 96.2% 96.3% 96.4% 95.3% 91.2% 93.3% 92.1% 91.3% 90.6% 89.5% 89.5% 88.4% 88.8% 91.9% www.rpacan.com Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 13-4 Technical Report NI 43-101 – June 20, 2012 TABLE 13-4 MAGNETIC SEPARATION RESULTS Pele Mountain Resources Inc. – Eco Ridge Mine Project www.rpacan.com A preliminary rougher flotation test was performed using the fine, i.e. minus 45 µm, size fraction. Flotation was performed at 25°C to 30°C using modified hydroximic acid collector at a dosage of 2.5 kg/t. Sodium silicate was used as a depressant at a dosage of 1.5 kg/t. The pH was between eight and nine and the flotation time was six minutes. The results are shown in Table 13-5. The collectors used in this test were not targeting U3O8 recovery. Follow up testwork is advancing at SRC to optimize flotation recovery results. TABLE 13-5 FLOTATION RESULTS Pele Mountain Resources Inc. – Eco Ridge Mine Project REO Sc2O3 Y2O3 La2O3 CeO2 Pr6O11 Nd2O3 Sm2O3 Eu2O3 Gd2O3 Tb4O7 Dy2O3 Ho2O3 Er2O3 Tm2O3 Yb2O3 Lu2O3 U3O8 Feed (ppm) n/a 99 519 963 95 292 49 3 33 5 22 4 8 1 7 1 640 Con. (ppm) n/a 218.4 1747.4 3242.9 320.2 940.1 147.3 8.3 84.1 10.5 47.3 8.9 16.2 2.6 13.3 1.9 838.4 Tails (ppm) n/a 61.2 137.2 253.0 25.3 90.7 18.4 1.5 16.9 2.7 14.1 2.8 5.4 0.9 5.1 0.7 577.8 Recovery (%) n/a 52.6% 79.8% 80.0% 79.8% 76.3% 71.3% 63.0% 60.7% 54.8% 51.0% 49.7% 48.6% 46.7% 45.0% 46.2% 31.1% ACID BAKING AND LEACHING Leaching tests were performed using three different batches of samples. First, five samples were used to determine the optimum conditions for acid baking and leaching. The effect of baking temperature, baking time, acid to ore ratio, and leaching time were evaluated using samples that had been pre-concentrated and samples that had not been pre-concentrated. The optimum conditions based on the preliminary tests were determined to be acid baking at 310°C using the sulphuric acid to sample ratio of 0.3 t acid to one tonne of ore, an acid baking time of three hours and a leaching time of three hours. A new sample was used as the feed material to conduct batch leaching tests that Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 13-5 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com were used as the basis for this PEA. The leaching results for the selected, optimum leaching conditions are shown in Table 13-6. TABLE 13-6 LEACHING RESULTS Pele Mountain Resources Inc. – Eco Ridge Mine Project REO Sc2O3 Y2O3 La2O3 CeO2 Pr6O11 Nd2O3 Sm2O3 Eu2O3 Gd2O3 Tb4O7 Dy2O3 Ho2O3 Er2O3 Tm2O3 Yb2O3 Lu2O3 U3O8 Feed (ppm) 10 298 1540 2952 241 959 121 8 101 16 54 8 27 0 20 0 946 PLS (ppm) 0.5 18.2 98.9 190.6 15.4 61.8 7.7 0.5 6.4 1.0 3.3 0.5 1.7 0.0 1.2 0.0 61.5 Residue (ppm) 3.1 24.5 45.7 71.2 8.8 25.4 5.2 0.4 4.6 0.8 4.3 1.0 1.9 0.3 2.0 0.3 15.2 Recovery (%) 70.4% 92.5% 97.3% 97.8% 96.7% 97.6% 96.0% 94.8% 95.8% 95.6% 92.6% 89.0% 93.6% 0.0% 90.8% 0.0% 98.5% HEAD ASSAYS REE assays for the plus 45 μm and minus 45 μm size distributions were conducted for bulk sample #4, as shown in Table 13-7. TABLE 13-7 BULK SAMPLE #4 ANALYSES Pele Mountain Resources Inc. – Eco Ridge Mine Project Size (μm) +45 -300 -45 +45-300 -45 Sc Y La Ce Pr Nd Sm Eu Gd 3 9 47.6 90.4 319 847 677 1430 66.8 147 203 451 32.3 69.8 1.83 4.1 22.8 49.1 Tb Dy Ho Er Tm Yb Lu U Th 2.62 5.62 12.7 26.6 2.43 4.87 4.44 8.82 0.76 1.44 4.32 7.79 0.63 1.05 267 777 281 832 The results show that the finer size fraction has higher concentrations of the REEs, which is common. When the decision was made to change the classification size to 20 Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 13-6 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com μm, assays were also conducted on the plus 20 μm minus 45 μm size fraction and the minus 20 μm size fraction. The finer size fraction was analyzed in duplicate. The results are shown in Table 13-8. TABLE 13-8 FINE SIZE FRACTION ANALYSES Pele Mountain Resources Inc. – Eco Ridge Mine Project Size (μm) -45 +20 -20 -20R +45 +20 -20 -20R Sc Y La Ce Pr Nd Sm Eu Gd 6 11 12 57.2 42.5 41.8 337 197 191 614 341 335 49.7 28.2 27.5 206 115 113 37.2 21.6 20.8 2.73 2.12 1.91 28.4 19.7 17.2 Tb Dy Ho Er Tm Yb Lu U Th 3.37 2.41 2.38 17.8 13.6 12.5 3.23 2.57 2.38 6.47 4.77 4.65 1.00 0.81 0.74 5.69 4.40 4.22 0.76 0.59 0.55 988 771 768 326 221 213 These results show that the analyses for the coarser and finer size fractions are similar and, in fact, the concentrations of the REEs in the coarser size fraction are oftentimes slightly higher than the concentrations of the REEs in the finer size fraction. Based on this observation, it was assumed that the REEs are evenly distributed in the minus 45 μm plus 20 μm and the minus 20 μm particle size fractions. RECOVERY The analyses of the size fractions showed that the total amount of REEs reporting to the fine size fraction was not proportional to the weights reporting to the coarse and fine sizes alone. It was, however, possible to estimate the relative quantity of each REE reporting to the coarse fraction, i.e., plus 20 μm, and the fine fraction, i.e., minus 20 μm, using the weights reported in Tables 13-1, 13-2, and 13-3 and the analyses of the various size fractions. For the purposes of these estimations, it was assumed that the assays for the minus 20 μm fraction were the same as those for the minus 45 μm fractions. In some cases, e.g., Sc, Tm, and Lu, complete test data was not available. In these cases, the average recoveries for the other light rare earth and heavy rare earth oxides were utilized to estimate the overall recovery. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 13-7 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Using these assumptions and the recovery data reported for the various unit operations, the overall recovery for each of the REOs was estimated as shown in Table 13-9. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 13-8 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 13-9 ESTIMATED REO RECOVERIES Pele Mountain Resources Inc. – Eco Ridge Mine Project REO Sc2O3 Y2O3 La2O3 CeO2 Pr6O11 Nd2O3 Sm2O3 Eu2O3 Gd2O3 Tb4O7 Dy2O3 Ho2O3 Er2O3 Tm2O3 Yb2O3 Lu2O3 U3O8 REE to Magnetic Separation 65.4% 74.9% 68.1% 72.8% 72.0% 71.8% 72.4% 71.7% 72.5% 72.5% 73.0% 73.9% 74.0% 74.9% 75.9% 77.3% 66.1% Magnetic Separation Flotation Leaching Overall 94.7% 92.0% 95.5% 96.2% 96.3% 96.4% 95.3% 91.2% 93.3% 92.1% 91.3% 90.6% 89.5% 89.5% 88.4% 88.8% 91.9% 71.8% 52.6% 79.8% 80.0% 79.8% 76.3% 71.3% 63.0% 60.7% 54.8% 51.0% 49.7% 48.6% 46.7% 45.0% 46.2% 31.1% 70.4% 92.5% 97.3% 97.8% 96.7% 97.6% 96.0% 94.8% 95.8% 95.6% 92.6% 89.0% 93.6% 93.7% 90.8% 93.7% 98.5% 61.1% 75.9% 88.1% 89.8% 88.7% 88.6% 85.1% 78.9% 80.8% 78.3% 74.5% 71.1% 73.8% 73.8% 70.8% 74.1% 70.2% SAMPLES A bulk sample collection program ran from November 2011 to December 2011, consisting of drilling multiple holes on two sites located in the southeast of the resource area. The sites were selected due to the proximity to surface of the MCB, while being of sufficient depth to avoid the usual excessive groundwater leaching of the MCB near surface. M.G. Forage Inc completed drilling of 98 NTW boreholes, for a total of 2139.5 m of drilling, resulting in 2635 kg of MCB material. Approximately 200 kg of this material is currently being used in processing optimization testwork at SRC and the balance is being securely stored in Elliot Lake in preparation for commencement of a pilot plant test program. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 13-9 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 14 MINERAL RESOURCE ESTIMATE SUMMARY The current Mineral Resource estimated by RPA for the Eco Ridge Mine Project is summarized in Table 14-1. The Mineral Resources are reported at a cut-off value of $100 per tonne for the MCB and $50 per tonne for the HWZ. Indicated Mineral Resources total 48.7 Mt at 0.026% U3O8 and 0.116% TREO. Inferred Mineral Resources total 37.9 Mt at 0.026% U3O8 and 0.110% TREO. The effective date of the Eco Ridge Mineral Resource estimate is April 16, 2012. TABLE 14-1 SUMMARY OF MINERAL RESOURCES – APRIL 16, 2012 Pele Mountain Resources Inc. – Eco Ridge Mine Project Tonnes U3O8 U3O8 LREO HREO TREO TREO (000) (%) (000 lbs) (ppm) (ppm) (ppm) (000 lbs) MCB 20,514 0.045 20,447 1,426 193 1,618 73,184 HWZ 28,223 0.012 7,214 733 88 821 51,111 Total 48,737 0.026 27,661 1,025 132 1,157 124,295 MCB 16,906 0.043 15,940 1,279 183 1,463 54,515 HWZ 20,956 0.013 5,822 713 95 808 37,329 Total 37,863 0.026 21,762 966 134 1,100 91,843 Zone & Classification Indicated Inferred Notes: 1. 2. 3. 4. 7. 5. CIM definitions were followed for Mineral Resources. Mineral Resources were estimated at a cut-off value of $100 per tonne for the MCB, and $50 per tonne for the HWZ. Values were calculated based on prices and recoveries of uranium and rare earths, net of off-site rare earth separation costs. Mineral Resources were estimated using an average uranium price of US$70 per lb U3O8, a rare earth “basket price” of $78 per kg (net of separation charges), and a C$:US$ exchange rate of 1.00:1.00. A minimum mining thickness of 1.8 m was used for the MCB. Light Rare Earth Oxides include La2O3, CeO2, Pr6O11, and Nd2O3. Heavy Rare Earth Oxides include Sm2O3, Eu2O3, Gd2O3, Tb4O7, Dy2O3, Ho2O3, Er2O3, Tm2O3, Yb2O3, Y2O3, and Lu2O3. Sc2O3 is also included in HREO, as it occurs in low concentrations and carries high unit values like an HREO. RPA has carried out the Mineral Resource estimate for the mineralization within the MCB and the HWZ, situated immediately above the MCB. A minimum true thickness of 1.8 m was used for MCB, while for HWZ the thickness was determined based solely on Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com economic considerations. Mineral Resources have not been estimated for any zones outside of the MCB and the HWZ. Since the previous NI 43-101 resource estimate, Pele Mountain has completed a 7,000 m drill program as well as a core re-sampling campaign to increase the sampling range to include the HWZ above the MCB. As a result of these initiatives, the Indicated and Inferred Resources have increased significantly. The shape of the Resource Wireframe has been changed due to the inclusion of new drilling and the exclusion of historic uranium-focused drill holes where complete assay analysis for REO in the MCB and sampling of the HWZ is not available. However, the MCB was reported as present in every one of the historic drill logs in those areas and at similar thicknesses. The Mineral Resources at Eco Ridge have excellent potential for upgrade and expansion, with lower-than-normal exploration risk in the historically drilled areas. The mineralized reefs of the Elliot Lake mining camp are well known for their consistency and size and, to-date, infill drilling has been successful in upgrading Inferred resources to the Indicated category in the MCB. There is also excellent potential to add substantial new mineral resources in areas beyond the Resource Wireframe where the deposit remains open down-dip beyond the historically drilled areas. MINERAL RESOURCE DATABASE The April 16, 2012 Mineral Resource estimate for the Eco Ridge deposit was based on 238 diamond drill holes totalling 44,066 m. The resource drilling consisted of 68 historic holes drilled from 1954 to 1974 totalling 11,471 m, and 170 Pele Mountain holes drilled from 2006 to 2011 totalling 32,595 m. Rare earth data has been collected only for the Pele Mountain drill holes. There were 163 mineralized intercepts assayed for REE. Twenty-five of these drill holes were not assayed for Tm and Lu, and five other drill holes were not assayed for Sc. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-2 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com The resource estimate was based on 3,572 assays for uranium and 3,338 assays for REE and other elements. The REE assays did not have Tm and Lu reported for 194 samples, and Sc results were not reported for 18 samples. In 2011, along with an infill and exploration drilling program, Pele Mountain sampled and assayed core from above the MCB that was collected in previous years. The assaying was carried out for U, Th, light rare earth elements LREE (La, Ce, Pr, and Nd) and heavy rare earth elements HREE (Sm, Eu, Gd, Tb, Dy, Ho, Er, Tm, Yb, and Lu) as well as Y and Sc. GEOLOGICAL INTERPRETATION AND 3D SOLIDS Historic drill logs, cross sections, government geology maps, and sample analyses were used in combination with data collected in the 2006 to 2011 Pele Mountain drill programs. West facing north-south cross sections were drawn which displayed topography and the locations of historic and current diamond drill holes with the stratigraphic intercepts identified in the holes. The geological interpretations from the diamond drill holes used the base of the MCB and the top of the underlying volcanic formation as marker beds. These two features were linked between the diamond drill holes for each cross section and longitudinal section. The base of the MCB and the top of the volcanic formation are the most distinct and recognizable features in the stratigraphy. The base of MCB, marked by distinct conglomerate beds or presence of pebbles accompanied by pyrite and accumulation of heavy minerals, relates directly to the location of the uranium/REE mineralization. The contact between the MCB and the HWZ is transitional and it is identified by a decrease in grades across the board. The top of the HWZ is also transitional, marked by diminishing grades. NSR values of $100/t for the MCB and $50/t for the HWZ were used as a guide for the top of the units. Based on assay data, the percent of uranium and REE mineralization through the HWZ and MCB typically increased down hole. The mineralization stops abruptly at the contact with the underlying quartzite. The underlying quartzite have grades of 0.01% U3O8 or less. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-3 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com A large 25 m wide Nipissing diabase dyke crosses the property. The dyke strikes eastwest and dips at approximately 65° to 70° S. Several dyke segments have been modeled based on the available drilling information. Geological interpretations were used to generate 3D wireframe models of the MCB, the unconformity and the diabase dyke. The cross sections indicated that the MCB has an average dip of 21° towards the north, with values ranging from 17° to 25°. Data from deeper holes suggested a down-dip steepening of the dip angle. The longitudinal sections showed that the MCB has a 2° to 3° plunge towards the west. Both the cross sections and the longitudinal sections reflected a consistent thickness of quartzite between the base of the MCB and the Volcanic/Sediment contact. The interpretation and extrapolation of the cross section data to the topographic surface on the plan map showed that the MCB has a strike of N80°E. The resource wireframes were based on the MCB and the HWZ 3D wireframe solids. Table 14-2 shows the descriptive statistics of the MCB and the HWZ intercepts true width, and the intercepts true width histogram is shown in Figure 14-1 for the MCB and in Figure 14-2 for the HWZ. TABLE 14-2 MCB AND HWZ INTERCEPTS TRUE THICKNESS DESCRIPTIVE STATISTICS Pele Mountain Resources Inc. – Eco Ridge Mine Project Mean Median Minimum Maximum Count MCB true thickness (m) HWZ true thickness (m) 2.76 2.74 1.74 4.36 238 6.48 5.71 0.11 19.61 130 Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-4 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 60 120% 50 100% 40 80% 30 60% 20 40% 10 20% 0 0% 1 1.2 1.4 1.6 1.8 2 2.2 2.4 2.6 2.8 3 3.2 3.4 3.6 3.8 4 4.2 4.4 4.6 4.8 5 More Frequency FIGURE 14-1 MCB INTERCEPTS TRUE WIDTH HISTOGRAM (N=238) True thickness (m) Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-5 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com FIGURE 14-2 HWZ INTERCEPTS TRUE WIDTH HISTOGRAM (N=130) 120% 25 100% 20 Frequency 80% 15 60% 10 40% 5 20% 0% More 25 23 21 19 17 15 13 11 9 7 5 3 1 0 True thickness (m) The resource wireframes were trimmed at the property boundary, license of occupation contours, clipped with the dyke solids, and the resulting solid was then trimmed to vertical 16 m below the topographic surface to account for a crown pillar. BASIC STATISTICS AND CAPPING OF HIGH ASSAYS The resource estimate was based on a total of 238 drill holes which intersected the MCB and the HWZ. These comprise 170 drill holes drilled by Pele Mountain from 2006 to 2011, and 68 historic drill holes drilled from 1954 to 1974. Descriptive statistics of the MCB resource assays are shown in Table 14-3. The HWZ resource assays are shown in Table 14-4. RPA did not consider it necessary to cap the assays based on relatively low coefficients of variation across the board. Uranium has the highest coefficient of variation among all the elements, with a value of less than 1.1, in both MCB and HWZ. Percentile analysis for U3O8, Nd, and Dy, the three largest Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-6 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com contributors to the revenue and providing in excess of 60% of the net value, indicated that capping of high grades was not required. As more data becomes available, the necessity for high grade capping should be investigated. Figures 14-3 show the resource assays histograms for U3O8, Dy (from the heavy REE group) and Nd (from the light REE group), respectively. TABLE 14-3 RARE EARTH AND OTHER ELEMENTS - MCB RESOURCE ASSAYS DESCRIPTIVE STATISTICS Pele Mountain Resources Inc. – Eco Ridge Mine Project Element Mean Median U3O8 (%) 0.046 Th (ppm) 326.51 La (ppm) 330.09 Ce (ppm) 599.37 Pr (ppm) 61.18 Nd (ppm) 202.94 Sm (ppm) 34.80 Eu (ppm) 1.93 Gd (ppm) 23.18 0.033 289 296 534 53.9 178 30.6 1.7 20.6 Minimum 0 1.8 1.7 5.2 1 4.2 0.9 0.09 0.78 Maximum 1.021 1,420 2,270 3,820 401 1,340 261 18.7 196 St. Dev. 0.05 226.86 222.90 418.22 43.96 145.70 25.03 1.34 16.48 C of V 1.08 0.70 0.68 0.70 0.72 0.72 0.72 0.69 0.71 Count 2,161 1,937 1,937 1,937 1,937 1,937 1,937 1,937 1,937 Tb (ppm) 3.14 Dy (ppm) 14.91 Ho (ppm) 2.53 Er (ppm) 6.23 Tm (ppm) 0.85 Yb (ppm) 4.85 Lu (ppm) 0.66 Y (ppm) 61.67 Sc (ppm) 3.70 Median 2.7 12.6 2.19 5.3 0.74 4.2 0.58 53 3.1 Minimum 0.1 0.7 0.1 0.38 0.05 0.4 0.06 3 0.25 Maximum 30.9 161 28.2 71.8 9.23 52 6.22 627 43 St. Dev. 2.31 11.22 1.88 4.67 0.62 3.54 0.46 44.76 2.53 C of V 0.74 0.75 0.74 0.75 0.74 0.73 0.70 0.73 0.68 Count 1,937 1,937 1,937 1,937 1,758 1,937 1,758 1,937 1,935 Element Mean Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-7 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 14-4 RARE EARTH AND OTHER ELEMENTS - HWZ RESOURCE ASSAYS DESCRIPTIVE STATISTICS Pele Mountain Resources Inc. – Eco Ridge Mine Project Element Mean Median U3O8 (%) 0.013 Th (ppm) 171.29 La (ppm) 183.73 Ce (ppm) 329.47 Pr (ppm) 33.18 Nd (ppm) 110.68 Sm (ppm) 18.48 Eu (ppm) 1.01 Gd (ppm) 11.64 0.009 134 146 258 25.9 86 14.2 0.81 8.95 Minimum 0 4.3 4.6 9.9 1.26 5.5 1.3 0.09 0.8 Maximum 0.179 1,620.00 1,710.00 3,000.00 306.00 1,070.00 189.00 9.44 103.00 0.01 153.37 150.85 282.58 28.98 98.51 16.89 0.81 10.06 St. Dev. C of V 1.06 0.90 0.82 0.86 0.87 0.89 0.91 0.80 0.86 Count 1,411 1,401 1,401 1,401 1,401 1,401 1,401 1,401 1,401 Tb (ppm) 1.45 Dy (ppm) 6.59 Ho (ppm) 1.10 Er (ppm) 2.81 Tm (ppm) 0.37 Yb (ppm) 2.24 Lu (ppm) 0.33 Y (ppm) 29.70 Sc (ppm) 3.15 Median 1.1 5.2 0.9 2.2 0.3 1.8 0.27 24 3 Minimum 0.1 0.5 0.05 0.3 0.03 0.2 0.02 3 1 Maximum 12.60 56.40 8.80 21.80 2.77 16.10 2.20 224.00 41.00 1.25 5.58 0.91 2.24 0.29 1.66 0.23 23.60 2.23 Element Mean St. Dev. C of V 0.87 0.85 0.83 0.80 0.78 0.74 0.70 0.80 0.71 Count 1,401 1,401 1,401 1,401 1,350 1,401 1,350 1,401 1,401 Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-8 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com FIGURE 14-3 U3O8, DY, AND ND ASSAY HISTOGRAMS - MCB AND HWZ Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-9 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com COMPOSITING RPA composited the assays in the two mineralized domains, MCB and HWZ. Inside the MCB, full intercept composites were used. For the HWZ, the assays were composited in one metre fixed length composites, starting from collar, and preserving the orphans. The assays were weighted by sample length. The composites were used for the mineral resource estimate. Descriptive statistics of the composites in the MCB and in the HWZ are shown in Table 14-5 and Table 14-6, respectively. Histograms of the U3O8, Nd, and Dy composited grades for the MCB and the HWZ are shown in Figure 14-4. TABLE 14-5 RARE EARTH AND OTHER ELEMENTS - MCB RESOURCE COMPOSITES DESCRIPTIVE STATISTICS Pele Mountain Resources Inc. – Eco Ridge Mine Project U3O8 (%) 0.046 Th (ppm) 333.48 La (ppm) 334.17 Ce (ppm) 607.42 Pr (ppm) 61.46 Nd (ppm) 203.65 Sm (ppm) 34.99 0.043 325.06 335.26 620.98 63.08 206.54 Minimum 0 156.26 8.36 22.18 3.68 16.6 Maximum Element Mean Median Eu (ppm) 1.95 Gd (ppm) 23.88 35.2 1.93 23.31 6.3 1.05 7.35 50.94 0.118 685.06 583.37 1,041.90 115.44 350.29 62.44 3.31 St. Dev. 0.02 87.30 98.27 179.10 18.80 59.46 9.87 0.44 7.00 C of V 0.40 0.26 0.29 0.30 0.31 0.29 0.28 0.23 0.29 Count 238 163 163 163 163 163 163 163 163 Tb (ppm) 3.22 Dy (ppm) 15.16 Ho (ppm) 2.59 Er (ppm) 6.38 Tm (ppm) 0.87 Yb (ppm) 4.95 Lu (ppm) 0.68 Y (ppm) 62.68 Sc (ppm) 4.01 Median 3.19 14.91 2.52 6.26 0.84 4.84 0.65 62.36 3.59 Minimum 1.16 5.84 1.27 2.52 0.42 1.87 0.32 23.43 2.07 Maximum 6.78 29.67 5.03 13.36 1.55 9.49 1.20 112.43 18.59 St. Dev. 0.93 4.21 0.67 1.79 0.21 1.34 0.16 16.95 2.21 C of V 0.29 0.28 0.26 0.28 0.24 0.27 0.24 0.27 0.55 Count 163 163 163 163 143 163 143 163 163 Element Mean Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-10 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 14-6 RARE EARTH AND OTHER ELEMENTS - HWZ RESOURCE COMPOSITES DESCRIPTIVE STATISTICS Pele Mountain Resources Inc. – Eco Ridge Mine Project Element Mean Median U3O8 (%) 0.011 Th (ppm) 151.07 La (ppm) 163.55 Ce (ppm) 292.05 Pr (ppm) 29.45 Nd (ppm) 97.32 Sm (ppm) 16.12 Eu (ppm) 0.90 Gd (ppm) 10.44 0.01 140.655 150.72 269.525 27.17 90 15.015 0.85 9.65 Minimum 0 4.3 5.39 11.75 1.5 6.51 1.7 0.12 1.1 Maximum 0.047 524.31 518.44 949.00 94.10 323.00 54.40 3.07 35.60 St. Dev. 0.01 76.43 76.96 144.20 14.75 49.00 8.27 0.40 5.22 C of V 0.55 0.51 0.47 0.49 0.50 0.50 0.51 0.45 0.50 Count 991 986 986 986 986 986 986 986 986 Tb (ppm) 1.30 Dy (ppm) 5.84 Ho (ppm) 0.98 Er (ppm) 2.51 Tm (ppm) 0.33 Yb (ppm) 2.02 Lu (ppm) 0.29 Y (ppm) 26.61 Sc (ppm) 3.15 1.2 5.5 0.91 2.4 0.31 1.9 0.28 25 3 0.1 0.7 0.1 0.3 0.01 0.3 0.01 4 0.32 4.61 20.29 3.27 7.90 1.03 6.03 0.86 84.99 41.00 0.65 2.73 0.45 1.11 0.15 0.83 0.12 11.82 2.57 0.50 0.47 0.46 0.44 0.45 0.41 0.41 0.44 0.82 986 986 986 986 968 986 968 986 986 Element Mean Median Minimum Maximum St. Dev. C of V Count Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-11 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com FIGURE 14-4 U3O8, DY, AND ND COMPOSITE HISTOGRAMS - MCB AND HWZ Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-12 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com CUT-OFF GRADE RPA used a net smelter return (NSR) cut-off value for the Mineral Resources. The assumptions used for calculating the NSR value include the following: Uranium price of $70 per lb U3O8 Rare earth basket price of $78 per kg REO o Net of separation costs of $10 per kg for LREO and $30 per kg for HREO Exchange rate of C$1.00 = US$1.00 Metallurgical recoveries of 85% for uranium and rare earths (50% for scandium) NSR royalty of 0.75% A net value (in $ per tonne) was calculated for each block in the model, using the grades as inputs and the assumptions above. This value was compared to operating cost assumptions to determine which blocks to include in the Mineral Resource and which blocks to exclude. An operating cost of $100 per tonne was assumed for the MCB, for room and pillar mining, and full process and G&A costs. The MCB wireframe was drawn at the limit of $100 per tonne NSR values, so by definition, entirely above cut-off. An operating cost of $50 per tonne was used for the HWZ, on the assumption that bulk mining methods could be applied, and/or the HWZ could be mined as an incremental addition to the MCB, and need not bear the full operating cost. Both the assumptions above and the operating costs differ slightly from those used in the cash flow presented in this report, due to additional information becoming available between the time of resource estimation and the time of PEA completion. VARIOGRAPHY AND TREND ANALYSIS Variograms were prepared for the MCB and HWZ using the U3O8%, Nd, and Dy full intercepts. The omnidirectional variograms shown in Figures 14-5 and 14-6 are essentially 2D variograms in the plane of the mineralization. The variograms indicated ranges between 375 m and 450 m for both the MCB and the HWZ for the three commodities investigated. The nugget effect values were relatively high for the MCB, Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-13 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com generally above 50% of the sill value in the MCB, and for the HWZ the nugget effect values tended to be lower. Directional variograms are generally sensitive to minor variations of the orientation and lag, which may be indicative of insufficient sampling or the need to define smaller domains within the resource wireframe. The U3O8%, Nd, and Dy grade contours (Figures 14-7, 14-8, and 14-9) indicated that the eastern and central part of the MCB wireframe might represent two separate domains. The area in the central part of the MCB displayed a NNW-SSE (approximately 155°) oriented trend, while the eastern part displayed a WNW-ESE (approximately 120°) oriented trend. The necessity for subdomaining should be investigated when more drilling at closer spacing becomes available. Within the HWZ, with a higher variation of the true thickness and based on a smaller number of intercepts, no clear trends of grade continuity were identified. The two directions of continuity identified in the MCB represent relatively small deviations from the documented regional paleocurrent NW direction (135°) (Fralick and Miall, 1989). Further analysis performed on the two MCB domains with approximate trends of 155° and 120° did not yield good variograms, mainly because of the reduction in available composites. Consequently, the inverse distance squared algorithm was used for interpolation of uranium and REE grades. The search ellipses were oriented towards 135° for grade interpolation in both the MCB and the HWZ. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-14 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com FIGURE 14-5 MCB INTERCEPTS VARIOGRAPHY FOR U3O8, ND, AND DY Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-15 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com FIGURE 14-6 HWZ INTERCEPTS VARIOGRAPHY FOR U3O8, ND, AND DY Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-16 Technical Report NI 43-101 – June 20, 2012 382,000 E 383,000 E 384,000 E 385,000 E 5,140,000 N 5,140,000 N 381,000 E Resource Outline 0 . 0 3 5,139,000 N 0. 04 5,139,000 N 0. 05 0. 05 0. 04 0. 05 3 0. 0 0. 0 4 0. 03 04 2 0. 0 5 0 0. 0. 0 5 0. 05 5 .0 .0 4 0 0 0. 0. 0 4 05 05 0 .0 5 0 0 3 0 0. 0 0 2 0 . 0. 03 0. 0 4 0. 05 0. 04 5 02 0 0. 4 5 0 0 0 . 0 . 0. 0. 0. 03 5 0. 0 04 0 4 02 04 5 0. 0 . 0 2 0. 0. 0 0 . 04 .0 5 0. 0 3 4 0. 0 0 0. 0 5 0 0. 03 00. 3 . 0. 04 0 0. 04 02 0. 05 0. 0. . 0 0. 04 4 0 3 0. . 05 0 3 4 0. 02 0. 4 0. 0 3 0. 0 03 0. 0.0 3 5,138,000 N 04 05 04 0. 0 4 0 5 0. 0. 04 0. 0. 0. 04 0. 0. 05 . 04 04 . 4 0. 0 . 0 4 0 . .0 4 0. 05 0. 0 5 .0 4 05 0. 05 0. 0 0. 0 . 0 0. 04 03 . 0 5 0 0. 03 0. 0 0. 0 0. 04 05 0. 5 0. 03 0. 0 5 5,138,000 N 04 4 0. 0 .0 4 04 5 3 0. 0 05 0 0. 04 04 0. 04 0. 04 0. 0 . 05 14-17 03 0. 0 . 03 0 0 4 0. 0. 03 0 . 0 5 0. 03 0. 0. 03 0. 0. 0. 4 0. 0 0 2 0 5 04 0. 0. 0 5 0. 0 2 0. 03 0 . 0 3 0 5,137,000 N 3 . 0 < 0.02 0.02 - 0.03 0.03 - 0.04 0.04 - 0.05 > 0.05 June 2012 0 200 400 600 Metres 800 1000 Pele Mountain Resources Inc. Eco Ridge Mine Project Elliot Lake, Ontario, Canada Main Conglomerate Bed U3 O 8% Composites Grade Contours www.rpacan.com U3 O 8 % Within Resource Boundary 5,137,000 N Figure 14-7 Legend: 382,000 E 383,000 E 384,000 E 385,000 E 5,140,000 N 5,140,000 N 381,000 E Resource Outline 15 0 100 5,139,000 N 100 5,139,000 N 0 15 5 0 2 00 15 0 10 0 0 15 250 0 10 2 0 0 25 1 15 0 5 0 0 2 25 0 00 2 00 20 0 0 15 200 0 15 25 0 2 00 200 3 50 0 0 0 1 100 25 10 2 00 50 10 15 0 0 2 20 0 0 2 0 2 2 200 5 2 50 0 30 0 20 50 0 0 0 2 200 2 0 5 0 5 0 25 1 15 0 0 150 10 150 0 200 0 250 20 10 200 0 25 0 5 0 Figure 14-8 Legend: Pele Mountain Resources Inc. Eco Ridge Mine Project 50 - 100 100 - 150 150 - 200 200 - 250 >250 June 2012 Elliot Lake, Ontario, Canada 0 200 400 600 Metres 800 1000 Main Conglomerate Bed Neodymium (Nd) (ppm) Composites Grade Contours www.rpacan.com Nd (ppm) Within Resource Boundary 0 - 50 5,137,000 N 5,137,000 N 150 1 5 0 20 0 0 150 20 1 0 5 20 0 25 100 150 0 0 15 0 100 250 0 300 50 0 200 200 25 5,138,000 N 0 1 3 0 0 200 15 0 200 0 15 2 00 10 0 150 200 0 00 20 25 20 0 0 20 5,138,000 N 20 250 200 0 14-18 200 382,000 E 383,000 E 384,000 E 385,000 E 5,140,000 N 5,140,000 N 381,000 E 15 5,139,000 N 5,139,000 N Resource Outline 15 1 0 20 1 0 1 5 10 10 15 1 15 20 5 15 20 5 1 15 15 14-19 15 15 20 15 10 1 15 15 1 5 5 15 20 2 0 15 5 15 20 25 2 15 5 20 1 15 2 0 15 15 10 5 20 5 1 5 5 25 10 1 5 1 1 5 15 10 10 15 10 10 15 10 1 0 5 10 Figure 14-9 Dy (ppm) Within Resource Boundary <5 10 15 20 > 25 June 2012 0 200 400 600 Metres 800 1000 Pele Mountain Resources Inc. Eco Ridge Mine Project Elliot Lake, Ontario, Canada Main Conglomerate Bed Dysprosium (Dy) (ppm) Composites Grade Contours www.rpacan.com Legend: 5,137,000 N 5,137,000 N 10 0 10 15 5,138,000 N 15 5 5,138,000 N 1 5 20 10 1 www.rpacan.com BLOCK MODEL AND GRADE ESTIMATION A block model extending beyond the limits of the modeled MCB wireframe was set up in Gemcom GEMS. The block sizes were 25 m east-west by 25 m north-south by 3 m vertical. The MCB and HWZ resource wireframes were used to flag the resource blocks and also to establish the percent of each block inside the wireframe. Table 14-7 lists the block model characteristics. TABLE 14-7 BLOCK MODEL SETUP Pele Mountain Resources Inc. – Eco Ridge Mine Project Element Origin Block size Block count X (m) 378412.5 25 324 Y (m) 5137012.5 25 152 Z (m) 500 3 300 The interpolation method used for the resource estimate was Inverse Distance squared, performed in three passes, with an ellipsoidal search having its long axis oriented towards 135°. The search ellipse characteristics and sample selection strategy are presented in Table 14-8. TABLE 14-8 SEARCH STRATEGY PARAMETERS Pele Mountain Resources Inc. – Eco Ridge Mine Project Zone MCB HWZ Ellipse Z X Z Pass 1 Anisotropy X Y Z (m) (m) (m) 150 100 50 Rotation about Sample selection Min Max Max per sample sample drill hole 2 12 1 5° -20° 120° Pass 2 300 200 100 5° -20° 120° 2 12 1 Pass 3 600 400 200 5° -20° 120° 1 12 1 Pass 1 150 100 10 5° -20° 120° 2 12 3 Pass 2 300 200 20 5° -20° 120° 2 12 3 Pass 3 600 400 80 5° -20° 120° 1 12 3 For each resource block, the interpolated REE values were transformed into their respective oxide grade and summed to suit the need for reporting light rare earth oxides, Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-20 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com heavy rare oxides including yttrium oxide and scandium oxide, as well as total rare earth oxides. The tonnage estimate was based on a density of 2.7 g/cm3. This is the same factor used by Rio Algom for its “ore estimates”, as outlined in the description of Rio Algom’s estimation methods in Hart and Sprague (1968), and used by Sprague (1965), as well as in previous RPA estimates. BLOCK MODEL VALIDATION The interpolated block grades were visually compared with the grades of the composites, both in plan and on vertical section. The U3O8% grade was also interpolated using the Nearest Neighbour method, rendering similar grades. In the opinion of RPA, the block model is a reasonable representation of the tonnage and grade of the MCB and of the HWZ uranium and rare earth mineralization of the Eco Ridge Mine Project. A plan view of the resource block model is shown in Figure 14-9. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-21 Technical Report NI 43-101 – June 20, 2012 382,000 E 383,000 E 384,000 E 385,000 E 5,140,000 N 5,140,000 N 381,000 E 5,139,000 N 5,139,000 N Resource Outline June 2012 Pele Mountain Resources Inc. 0 200 400 600 Metres 800 1000 Eco Ridge Mine Project Elliot Lake, Ontario, Canada Resource Blocks in Main Conglomerate Bed www.rpacan.com NSR 2012 0 - 30 30 - 50 50 - 70 70 - 100 100 - 150 150 - 200 >200 5,137,000 N 5,137,000 N 5,138,000 N 5,138,000 N 14-22 Figure 14-10 Legend: 382,000 E 383,000 E 384,000 E 385,000 E 5,140,000 N 5,140,000 N 381,000 E 5,139,000 N 5,139,000 N Resource Outline June 2012 Pele Mountain Resources Inc. 0 200 400 600 Metres 800 1000 Eco Ridge Mine Project Elliot Lake, Ontario, Canada Resource Blocks in Hanging Wall Zone www.rpacan.com NSR 2012 0 - 30 30 - 50 50 - 70 70 - 100 100 - 150 150 - 200 >200 5,137,000 N 5,137,000 N 5,138,000 N 5,138,000 N 14-23 Figure 14-11 Legend: www.rpacan.com CLASSIFICATION The uranium and REE mineralization at Eco Ridge is hosted in the MCB and the HWZ. For both the MCB and the HWZ, the continuity between holes is excellent. The true thickness displays less variation for the MCB than for the HWZ, as shown by the histograms of the intercepts in Figures 14-1 and 14-2. The omnidirectional variograms for uranium, neodymium, and dysprosium in both MCB and HWZ displayed ranges between 375 m and 450 m. Therefore, the Mineral Resources were classified as Indicated using a maximum drill hole spacing of 200 m. For the Indicated Resources, the MCB average drill hole spacing was 115 m, while for the HWZ the average spacing was 140 m. The remaining Mineral Resources are classified as Inferred. For the Inferred Resources drill hole spacing averages 320 m for MCB and 510 for HWZ. This takes into account the continuous structure of the mineralization and concurs with past practice in the Elliot Lake district. The current mineral resource estimate is listed in Indicated and Inferred categories in Table 14-9. The grade of individual rare earth oxides and related oxides, as well as LREO, HREO, and TREO, are presented in Table 14-10. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-24 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 14-9 SUMMARY OF MINERAL RESOURCES – APRIL 16, 2012 Pele Mountain Resources Inc. – Eco Ridge Mine Project Tonnes U3O8 U3O8 LREO HREO TREO TREO (000) (%) (000 lbs) (ppm) (ppm) (ppm) (000 lbs) MCB 20,514 0.045 20,447 1,426 193 1,618 73,184 HWZ 28,223 0.012 7,214 733 88 821 51,111 Total 48,737 0.026 27,661 1,025 132 1,157 124,295 MCB 16,906 0.043 15,940 1,279 183 1,463 54,515 HWZ 20,956 0.013 5,822 713 95 808 37,329 Total 37,863 0.026 21,762 966 134 1,100 91,843 Zone & Classification Indicated Inferred Notes: 1. 2. 3. 4. 8. 5. CIM definitions were followed for Mineral Resources. Mineral Resources were estimated at a cut-off value of $100 per tonne for the MCB, and $50 per tonne for the HWZ. Values were calculated based on prices and recoveries of uranium and rare earths, net of off-site rare earth separation costs. Mineral Resources were estimated using an average uranium price of US$70 per lb U3O8, a rare earth “basket price” of $78 per kg (net of separation charges), and a C$:US$ exchange rate of 1.00:1.00. A minimum mining thickness of 1.8 m was used for the MCB. Light Rare Earth Oxides include La2O3, CeO2, Pr6O11, and Nd2O3. Heavy Rare Earth Oxides include Sm2O3, Eu2O3, Gd2O3, Tb4O7, Dy2O3, Ho2O3, Er2O3, Tm2O3, Yb2O3, Y2O3, and Lu2O3. Sc2O3 is also included in HREO, as it occurs in low concentrations and carries high unit values like an HREO. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-25 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 14-10 MINERAL RESOURCE ESTIMATE - APRIL 16, 2012 - RARE EARTH OXIDES AND RELATED OXIDES Pele Mountain Resources Inc. – Eco Ridge Mine Project Notes: 1. 2. 3. 4. 9. 5. Indicated Category MCB HWZ Inferred Category MCB HWZ Tonnage (000) 20,514 28,223 16,906 20,957 U3O8% 0.0452 0.0116 0.0428 0.0126 ThO2% 0.0366 0.0178 0.0354 0.0185 La2O3% 0.0386 0.0200 0.0346 0.0194 CeO2% 0.0731 0.0376 0.0657 0.0365 Pr6O11% 0.0073 0.0037 0.0066 0.0037 Nd2O3% 0.0235 0.0120 0.0212 0.0117 Sm2O3% 0.0040 0.0020 0.0037 0.0020 Eu2O3% 0.0002 0.0001 0.0002 0.0001 Gd2O3% 0.0027 0.0012 0.0025 0.0013 Tb4O7% 0.0004 0.0002 0.0004 0.0002 Dy2O3% 0.0017 0.0007 0.0016 0.0008 Ho2O3% 0.0003 0.0001 0.0003 0.0001 Er2O3% 0.0007 0.0003 0.0007 0.0003 Tm2O3% 0.0001 0.0000 0.0001 0.0000 Yb2O3% 0.0006 0.0002 0.0005 0.0003 Lu2O3% 0.0001 0.0000 0.0001 0.0000 Y2O3% 0.0079 0.0035 0.0074 0.0038 Sc2O3% 0.0006 0.0005 0.0009 0.0006 LREO% HREO% TREO% 0.1426 0.0193 0.1618 0.0733 0.0088 0.0821 0.1280 0.0183 0.1463 0.0713 0.0095 0.0808 CIM definitions were followed for Mineral Resources. Mineral Resources were estimated at a cut-off value of $100 per tonne for the MCB, and $50 per tonne for the HWZ. Values were calculated based on prices and recoveries of uranium and rare earths, net of off-site rare earth separation costs. Mineral Resources are estimated using an average uranium price of US$70 per lb U3O8, a rare earth “basket price” of $78 per kg (net of separation charges), and a C$:US$ exchange rate of 1.00:1.00. A minimum mining thickness of 1.8 m was used for the MCB. Light Rare Earth Oxides include La2O3, CeO2, Pr6O11, and Nd2O3. Heavy Rare Earth Oxides include Sm2O3, Eu2O3, Gd2O3, Tb4O7, Dy2O3, Ho2O3, Er2O3, Tm2O3, Yb2O3, Y2O3, and Lu2O3. Sc2O3 is also included in HREO, as it occurs in low concentrations and carries high unit values like an HREO. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-26 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com SENSITIVITY ANALYSIS The Mineral Resources in the MCB were moderately sensitive to the cut-off value in the $80 to $110 NSR range, and became sensitive for higher NSR values in both Indicated and Inferred Resources. In the HWZ, for both Inferred and Indicated categories, the Mineral Resources were sensitive to NSR cut-off values. The tonnage and TREO grades for various NSR cut-off values are presented in Table 14-11 and Figure 14-12 for Indicated Resources, and in Table 14-12 and Figure 14-13 for Inferred Resources. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-27 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 14-11 INDICATED RESOURCE – TONNAGE AND TREO% GRADE AT VARIOUS NSR CUT-OFF VALUES Pele Mountain Resources Inc. – Eco Ridge Mine Project MCB Indicated Cut-off NSR value Tonnage ($/t) (000) 0 21,104 10 21,104 20 21,104 30 21,104 40 21,104 50 21,104 60 21,104 70 21,104 80 21,092 90 20,939 100 20,514 110 19,768 120 18,500 130 16,379 140 13,657 150 10,262 TREO (%) 0.160 0.160 0.160 0.160 0.160 0.160 0.160 0.160 0.160 0.161 0.162 0.164 0.167 0.172 0.177 0.184 HWZ Indicated Cut-off NSR value Tonnage ($/t) (000) 0 37,992 10 37,992 20 37,958 30 37,680 40 35,908 50 28,223 60 15,300 70 4,585 80 1,236 90 297 100 75 110 8 120 130 140 150 - TREO (%) 0.075 0.075 0.076 0.076 0.077 0.082 0.090 0.102 0.112 0.121 0.130 0.141 0.000 0.000 0.000 0.000 TABLE 14-12 INFERRED RESOURCE – TONNAGE AND TREO% GRADE AT VARIOUS NSR CUT-OFF VALUES Pele Mountain Resources Inc. – Eco Ridge Mine Project MCB Inferred Cut-off NSR value Tonnage ($/t) (000) 0 17,679 10 17,679 20 17,679 30 17,679 40 17,679 50 17,679 60 17,679 70 17,679 80 17,679 90 17,616 100 16,906 110 16,156 120 13,291 130 11,468 140 9,651 150 7,356 TREO (%) 0.144 0.144 0.144 0.144 0.144 0.144 0.144 0.144 0.144 0.144 0.146 0.148 0.160 0.167 0.172 0.178 HWZ Inferred Cut-off NSR value Tonnage ($/t) (000) 0 27,082 10 27,082 20 27,082 30 27,007 40 26,082 50 20,957 60 12,278 70 6,164 80 2,565 90 1,320 100 212 110 26 120 2 130 140 150 - TREO (%) 0.075 0.075 0.075 0.075 0.076 0.081 0.092 0.103 0.118 0.124 0.141 0.151 0.173 0.000 0.000 0.000 Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-28 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com FIGURE 14-12 GRADE –TONNAGE CURVES OF INDICATED RESOURCE Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-29 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com FIGURE 14-13 GRADE –TONNAGE CURVES OF INFERRED RESOURCE Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-30 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com COMPARISON WITH PREVIOUS MINERAL RESOURCE ESTIMATE The Mineral Resource estimates for the Eco Ridge Mine Project reported in the 2007 Scott Wilson RPA Preliminary Assessment and in the 2011 RPA Technical Report are compared with the current 2012 estimate in Table 14-13. TABLE 14-13 MINERAL RESOURCE COMPARISON – 2007 TO 2012 Pele Mountain Resources Inc. – Eco Ridge Mine Project Resource Kt % U3O8 % TREO 2007 Indicated 2007 Inferred 5,681 37,262 0.051 0.044 - 2011 Indicated 2011 Inferred 14,312 33,121 0.048 0.043 0.164 0.132 2012 Indicated 2012 Inferred 48,737 37,863 0.026 0.026 0.116 0.110 The increase in Mineral Resource from 2007 to 2011 was based on new drilling north (down-dip) of the previous resource estimate. The REOs were also included in the 2011 Mineral Resource. The main evolution reflected in the 2012 Mineral Resource is the addition of the HWZ, along with the inclusion of new exploration drill holes north of 2011 resource. The 2012 Mineral Resource represents an increase of approximately three times in the Indicated Resource category and a slight increase in the Inferred category. The addition of lower grade HWZ material in the current estimate led to an overall decrease for U3O8 and TREO grades for both the Indicated and Inferred categories compared to the 2011 estimate, however, the MCB grades in the 2012 estimate (Table 14-9) are similar to those in the MCB only 2011 estimate. EXPLORATION POTENTIAL OF ADDITIONAL RESOURCES ON THE PROPERTY MAIN CONGLOMERATE BED AND HANGING WALL ZONE There is additional exploration potential to expand the MCB and HWZ down dip towards north and northwest. Historical drilling has indicated that the conglomerate bed and the uranium mineralization continue, but no REE assay data is available to support the Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-31 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com expansion of the resource wireframes. Uranium-only assays available for the historical drill holes were focused on the first few metres above the base of the conglomerate, which differs from the current sampling strategy that spans approximately 20 m above the conglomerate base. The location of the historical drill holes outside current resource wireframes is shown in Figure 14-14. Ten historic (uranium-only) drill holes that were used in the 2007 and 2011 resource estimates, focused on the MCB, were not included in the current estimate. Table 14-14 shows the list of drill holes and the U3O8% grade of the intercepts. These are located north and northwest of the western edge of the current resource wireframes (Figure 1414). TABLE 14-14 HISTORIC DRILL HOLES NOT INCLUDED IN THE 2012 RESOURCE ESTIMATE Pele Mountain Resources Inc. – Eco Ridge Mine Project Hole C-PA-24 CB-13 CB-15 CB-17 CB-20 CB-21 CB-22A CB-23 CB-30 CB-34 From To Length (m) (m) (m) 498.6528 393.3444 515.4168 593.4456 549.2496 423.5196 576.9864 592.5312 356.70744 588.05064 502.0056 397.79448 519.3792 596.9508 552.6024 427.3296 580.0344 595.7316 359.78592 590.8548 3.36 4.45 3.96 3.5 3.35 3.81 3.04 3.2 3.08 2.8 %U3O8 0.0263 0.032 0.051 0.0253 0.06 0.0564 0.04 0.04 0.0518 0.044 Another four historic drill holes located farther to the north and northwest demonstrate the presence of conglomerate beds and uranium mineralization. The drill hole 143-3 is located approximately 14.8 m above the basement contact, which is consistent with the location of the MCB up-dip within the portion of the deposit containing the estimated Mineral Resource. Additional thin mineralized conglomerate beds are located above the MCB, which correlates with the upper conglomerate beds. The MCB in drill hole CB-35 is located approximately 15.6 m above the basement contact. Again, the location is consistent with the position of this bed throughout the deposit. Drill hole Z-5-1 reported a coarse-grained quartzite and conglomerate intersection from 726.3 m to 729.9 m (3.6 m). Although no samples were taken and no radioactivity was specifically mentioned, Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-32 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com there was a reference to “slightly radioactive in spots” in the interval from 712.9 m to 770.5 m. Drill hole Z-5-2 reported a “quartzite-pebble conglomerate” from 888.4 m to 894.8 m (6.4 m) with pyrite, pyrrhotite and radioactivity. The section was sampled from 889.0 m to 892.7 m. The drill holes are listed in Table 14-15 and the locations of the holes are shown in Figure 14-14. TABLE 14-15 HISTORIC DRILL HOLES DEMONSTRATING THE DOWN-DIP POTENTIAL OF THE MAIN CONGLOMERATE BED Pele Mountain Resources Inc. – Eco Ridge Mine Project CB-35 From (m) 903.32 To (m) 908.50 Length (m) 5.18 143-3 860.71 865.58 4.87 Z-5-2 888.4 894.8 6.40 Z-5-1 726.3 729.9 3.60 Hole %U3O8 Comments 0.044 Log 0.027 Log Sampled from 899.0 to 892.7 Analyses Not Available Conglomerate – Not Sampled In addition, the drilling on the eastern portion of the original Pecors Claim Block intersected mineralization in the MCB. The drill hole logs and sample intervals are not available, but several sections showing the drill holes were found, indicating the location of the MCB, the thickness and the uranium assays. The MCB is located about 10 m to 15 m above the underlying metavolcanics demonstrating the correlation of the bed with the MCB from the other drilling programs. These drill holes are listed in Table 14-16 and the thickness of the MCB that was sampled and analyzed is shown. The average thickness of the portion of the MCB that was analyzed is 1.54 m and the average grade based on the historical analyses is 0.041% U3O8. The locations of these holes are also shown on Figure 14-14. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-33 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 14-16 HISTORIC DRILLING RESULTS FROM THE PECORS LAKE BLOCK Pele Mountain Resources Inc. – Eco Ridge Mine Project Hole PW-115 PW-114 PW-113 PW-112 PW-111 PW-110 PW-109 PW-108 PW-107 PW-106 PW-105 PW-104 PW-103 PW-102 PW-101 Average From (m) 78,48 81.23 75.28 32.92 80.46 76.66 61.26 73.15 88.09 89.76 77.11 111.25 112.62 105.61 92.05 71.32 59.13 To (m) 80.00 82.75 77.42 34.68 82.90 78.64 62.94 74.17 89.76 91.44 78.18 112.62 114.00 107.90 93.27 73.00 60.35 Thickness (m) 1.52 1.52 2.14 1.72 2.44 1.98 1.68 1.22 1.68 1.68 1.07 1.37 1.37 2.29 1.22 1.68 1.22 1.54 %U3O8 0.050 0.057 0.030 0.059 0.034 0.041 NA 0.024 0.014 0.063 0.033 0.018 0.046 0.047 0.053 0.043 0.038 0.041 Comments 0.3 m not sampled NA – Analysis Not Available EXPLORATION POTENTIAL As noted above, historic drilling has intersected the MCB down dip from the current Mineral Resource and to the east in the resource wireframes. The widths of the intersections of the MCB in these holes and the % U3O8 are shown in Tables 14-14, 1415, and 14-16. A target for further exploration was estimated for the areas where the historical drilling had demonstrated the presence of mineralized MCB (Figure 14-15). A polygonal method was used based on the thickness of the intersections of the MCB, uranium grades in Tables 14-15 and 14-16, typical TREO grades, and a specific gravity of 2.7. It was estimated that these areas could contain a further 40 Mt to 60 Mt in an exploration target grading from 0.030% U3O8 to 0.050% U3O8, accompanied by 0.12% TREO to 0.18% TREO for the MCB. There is insufficient drill hole information for the HWZ outside the current resource wireframes; however, the length of some of the historical Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-34 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com intercepts with demonstrated uranium mineralization suggests that lower grade mineralization might continue above the MCB, hence the HWZ might be present. The potential quantities and grades of the exploration targets are conceptual in nature and there has been insufficient drilling to define a Mineral Resource. It is uncertain if further exploration will result in the definition of a Mineral Resource in these areas. EXPLORATION OF THE BASAL CONGLOMERATE BED Based on the results to date, the higher-grade mineralization in the BCB is contained near permeable zones in the MCB, and is associated with the presence of pyrite and pyrrhotite. For further exploration in the BCB, key exploration parameters for this style of mineralization appear to be: The presence of thicker sections of the MCB. The presence of permeable zones within the MCB that allowed fluids carrying uranium, possibly leached from the overlying sediments, to flow. The presence of pyrite or other sulphide minerals to react with the fluids and deposit the uranium. (Mineralogical assessments indicate that the sulphide minerals in the BCB consist of a much higher percentage of pyrrhotite than found in the MCB: 16% of the sulphide minerals in the BCB compared to 0.5% of the sulphide minerals in the MCB.) Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 14-35 Technical Report NI 43-101 – June 20, 2012 386,000 E 385,000 E 384,000 E 383,000 E 382,000 E 381,000 E 380,000 E 379,000 E Z-5-2 N 5,141,000 N CB-35 143-3 5,140,000 N Z-5-1 Resource Outline CB-34 14-36 5,139,000 N CB-23 CB-17 CB-22A CB-21 CB-15 C-PA-24 CB-20 CB-13 CB-30 PW-104 PW-102 PW-115 PW-105 PW-103 PW-101 PW-107 PW-113 PW-114 PW-112 PW-115 PW-109 PW-107 PW-111 PW-110 PW-108 PW-115 PW-105 PW-103 PW-104 PW-102 PW-101 PW-106 PW-113 PW-112 PW-111 PW-114 PW-115 PW-107 PW-110 PW-108 5,138,000 N 0 250 500 750 1000 Metres Figure 14-14 5,137,000 N Pele Mountain Resources Inc. Property Boundary Eco Ridge Mine Project Resource Outline 5,136,000 N Historic Drill Hole with Mineralization Outside Resource Area Powerline Road/trail June 2012 Elliot Lake, Ontario, Canada Historic Drill Holes with Mineralized Intersections Outside the Mineral Resource www.rpacan.com Legend: Property Boundary Figure 14-15 N Pele Mountain Resources Inc. Eco Ridge Mine Project Elliot Lake, Ontario, Canada Property Boundary Location of the Exploration Targets Furth er Ex plora tion P 14-37 Exploration Target Mineral Resource otent ial Exploration Target ADIT Licence of Occupation Access Roads June 2012 0 0.5 1.0 1.5 Kilometres 2.0 Mining Land Tenure Source: Ministry of Northern Development and Mines of Ontario, Provincial Mining Recorder’s Office, Plan G-3254, September 2007. www.rpacan.com Lease Boundary www.rpacan.com 15 MINERAL RESERVE ESTIMATE Mineral Reserves have not yet been estimated for the Eco Ridge Mine Project. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 15-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 16 MINING METHODS A number of mining methods have been proposed for the Project by RPA and others. SELECTED MINING METHOD The geometry of the mineralized zone can be described as a narrow reef, with a shallow dip approximately 20° to the north and a plunge of approximately 10° to the north-west. The mineralized zone is oriented in an easterly direction with a strike and dip length of approximately 5,700 m and 2,000 m, respectively. The selected mining method was room and pillar. Both development and production will be contained within the mineralized zone. The development and production tonnage will be loaded into trucks and transported to surface for processing. MINE DEVELOPMENT The deposit outcrops at the surface along a five-kilometre strike length, at depths suitable for mine access via decline from surface as opposed to vertical shafts. Two sets of dual ramps were proposed. The first set will service the eastern portion of the deposit and the second set will service the western portion. Both ramps will serve as fresh air intakes as well as service/haulage ways. All the mine access headings will be driven at 18% on the footwall contact of the reef. Panel access will be driven off the mine access headings spaced every 300 m. The top heading will provide access to the mining cell entry. The bottom heading will serve as a ventilation exhaust way for blasted muck in the stopes below. See Figure 16-1 for a site layout. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 16-1 Technical Report NI 43-101 – June 20, 2012 380,000 E 381,000 E 382,000 E 383,000 E 384,000 E 385,000 E 386,000 E 387,000 E N Mine Portal Mill Stockpile Parking Lot Proposed Plant Location/Expansion for Temporary Tailings Cell Separation Plant Tailings Storage Facility Settling Pond HW 8 Figure 16-1 5,134,000 N Elliot Lake, Ontario, Canada 0 380,000 E 381,000 E 500 1000 Metres 382,000 E 1500 2000 383,000 E Site Layout 384,000 E 5,134,000 N Eco Ridge Project www.rpacan.com Pele Mountain Resources Inc. 5,135,000 N 10 5,135,000 N Y Pele Mountain Property as of May 2012 Pele Mountain Lease as of 2011 June 2012 Explosive Storage 5,136,000 N 5,136,000 N Mine Portal Admin/Dry Warehouse Shops 5,137,000 N 16-2 5,137,000 N 5,138,000 N 5,138,000 N 5,139,000 N 5,139,000 N 2012 Mineral Resource Outline 5,140,000 N 5,140,000 N 379,000 E www.rpacan.com ROOM AND PILLAR LAYOUT Each panel will be subdivided into mining blocks. Each block will measure 300 m on strike by 300 m on dip. Access to the mining block will contain an entry and exit each connected by a ramp driven at 18% (Figure 16-2). Ore extraction will be carried out by a series of strike drifts separated by rib pillars located every 20 m (Figure 16-3). GEOTECHNICAL The preliminary assessment of the rock mass based on geotechnical logging of the core (Kim, 2007) indicates that the rock mass rating is between 75 and 80, which is good to excellent, depending on groundwater conditions. Based on point load tests, the intact strength is approximately 210 MPa, similar to the other mines at Elliot Lake. Based on these measurements, the rock mass conditions at the Pele Mountain Project are comparable to the conditions encountered at the mines operated previously in the Elliot Lake area. PILLAR STABILITY Pillar design was based on the Elliot Lake Camp’s empirical relationship between pillar strength and pillar stress (Salamon and Munro (1967) and Hedley (1983)). The relationship takes into account pillar widths, pillar height, mining depth, dip of the orebody, field stresses, and extraction ratio as shown below: 26000 1.1 Where: W = pillar width, ft. H = pillar height, ft. D = depth below surface, ft. α = dip of orebody, degrees R = extraction ratio 1 . . 3000 Horizontal stress is taken as 3,000 psi Uniaxial strength of a one foot cube as 26,000 psi Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 16-3 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Using the above formula and field data, the safety factor for a failed pillar was around 1.0, those that partially failed lie between 1.0 and 1.3, and those that were stable exceeded 1.5. EXAMPLE: At a depth 1,312 ft, a pillar width of 13.1 ft, a seam height of 7 ft dipping at 20 degrees and extraction of 80 % the factor of safety is calculated to equal 2.7. Therefore, it could be concluded that the pillar will be stable given the above conditions. 13.1 . 7 . 20° 3000 1 0.80 26000 1.1 1312 20° 21866 1274 350 0.20 2.7 Where: W = 13.1, ft H = 7, ft D = 1312, ft α = 20, degrees R = 80%. Although further geotechnical testing and analysis is required, this empirical formula indicates that the current room and pillar configuration will be stable. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 16-4 Technical Report NI 43-101 – June 20, 2012 X - SECTION 5,140,000 N 1 3 2 4 8 7 6 5 11 10 9 15 14 13 12 18 17 16 N Division between East and West Resource Outline 67 5,139,000 N 66 48 33 32 16-5 5,138,000 N 3 101 7 6 5 102 104 103 9 106 105 10 107 28 27 26 11 108 12 109 13 110 29 30 14 111 15 112 386,000 E 100 4 8 89 88 East Main Ramp Stone Access Ramp 43 Panel Access Ramp 42 41 44 385,000 E 2 20 19 18 17 21 25 24 23 22 40 39 38 37 36 35 34 52 51 50 49 160 91 56 55 54 53 87 86 West Main Ramp 5,137,000 N Pele Mountain Property Boundary 0 250 500 Figure 16-2 750 1000 Pele Mountain Resources Inc. 5,136,000 N 384,000 E 383,000 E 382,000 E 381,000 E 380,000 E June 2012 Eco Ridge Project Elliot Lake, Ontario, Canada Mine Plan www.rpacan.com Metres Fresh Air Intake Panel Access Ramp 300m 292m 8m 20m East Main Ramp 4m 284m Stope Access Ramp 16-6 Drifting Pillar Figure 16-3 Ventilation Exhaust Drift Eco Ridge Project Elliot Lake, Ontario, Canada Panel Plan June 2012 www.rpacan.com Pele Mountain Resources Inc. www.rpacan.com DILUTION Mining dilution occurs in two forms - planned and unplanned dilution. Planned dilution consists of sub-economic grade material deliberately included within stope design limits for practical mining reasons. Planned dilution is accounted for when estimating the grade of the designed mining block or stope. A major portion of the planned dilution is derived from the footwall step that must be excavated to maintain a flat floor. Unplanned dilution occurs from sub-economic grade material that originates from beyond the designed stope limits due to wall failure, poor blasting practice, inaccurate drilling and other such sources. No additional tonnage was added for unplanned dilution on the basis that any losses due to reduced mining extraction would be replaced by diluted material assuming the same factors for dilution and recovery. The resource grade of the main access drifting and panel drifting has been reduced by approximately 2% to account for dilution. This dilution rate is lower than the dilution rate experienced previously in the Elliot Lake Camp. This is possibly due to improvements made to equipment technology from the time the Elliot Lake Camp commenced operations. None the less, particular care will still be required for blasting the base of the drift to ensure the higher grade mineralization is recovered without breaking significant amounts of the underlying quartzite. A comprehensive grade control program is required to minimize the dilution and additional pre-shear holes have been added to assist in reducing any dilution from overbreak. Achieving the production grade is identified as a project risk and a comprehensive dilution control program is recommended. DILUTION CONTROL PROGRAM Dilution control during mining will be of high importance to the economics of the Project. Dilution control methods were well established in the Elliot Lake Camp at the time of mine closure. The use of trucks for transport to surface provides the option to transport low-grade material or waste, such as dykes, to either a low grade stockpile or a waste stockpile. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 16-7 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com The following dilution control program is recommended. Pre-development drilling from surface on a 50 m by 50 m grid or closer as required to estimate the block grades for planning of the stope layouts and identifying the presence of dykes or faults. Planning a minimum mining height of 2.1 m (7 ft) where appropriate. Geological control of all headings, with face and wall mapping using scintillometers and REO scanning equipment to direct material to processing or to the low-grade stockpile. Sampling the jumbo drill holes or development of a slim tool for radiometric and REO analyses of the holes. Strict quality control of the drilling practices to ensure the higher grade material at the base of the MCB is recovered without adding significant dilution. Strict quality control of the drilling with pre-shear holes at the hanging wall contact to prevent overbreak. Consider the potential to drill and blast thinner lifts to decrease the portion of lower grade hanging wall material. MINING PRODUCTION RATE Production rates were developed based on first principles. Cycle times were estimated for each part of the mining cycle. With respect to drilling, the cycle time was based on the number of holes to be drilled, drilling penetration rate, allowance for setup/ teardown and travelling time to the next face. Cycle times were estimated in a similar manner for explosive charging, mucking, and installing of ground support. Table 16-1 summarizes the optimum production capacities for each piece of production equipment for the various heading sizes. For example, when these capacities were used to determine the mobile equipment requirements using 9,000 tpd as the production target, the number of drilling units needed ranges between 3.5 and 6.3, the average being 6, which includes an 85% equipment mechanical availability allowance. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 16-8 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 16-1 EQUIPMENT OPTIMUM PRODUCTION CAPACITIES Pele Mountain Resources Inc. – Eco Ridge Mine Project Description Heading Size (t/day) Explosive Charging (t/day) Mucking (5m3) (t/day) Drilling Bolting (t/day) Main Ramps 5.0mWx3.2mH 1,860 1,512 2,124 1,710 Panel Drifts 4.8mWx3.2mH 1,796 1,455 2,096 1,685 Stope Ramp 4.8mWx3.2mH 1,796 1,455 2,096 1,685 1st Pass Pilot 3.4mWx3.0mH 1,419 1,101 1,841 1,521 st 4.6mWx3.0mH 2,309 1,617 2,022 1,655 nd 6.5mWx3.0mH 2,776 2,054 2,223 1,801 rd 5.5mWx3.0mH 2,573 1,850 2,133 1,736 1 Pass Slash 2 Pass Slash 3 Pass Slash The production rates found in Table 16-2 allow for inefficiencies during mining operations, due to the difficulties in managing delays at the workplace. Typically, these occur due to issues such as: lack of coordination of equipment; jumbo, scoops and bolters not having a follow-up assignment so they have idling time; mine services such as ventilation and sumps not functioning properly which interrupt production; miscommunication between miners that results in rework; not having all the necessary materials and equipment at the start of the job; equipment not functioning properly and procedures not being followed. Table 16-2 identifies the effective advance and corresponding production rates for two mining scenarios, double heading and multiple headings (more than eight faces). These rates include 30% and 25% additional time for the delays identified above in the double heading and multiple heading rates, respectively. Using the effective production rate in Table 16-2 a total of eight mining blocks need to be active at any one time to maintain a nominal mining rate of 9,000 tpd. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 16-9 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 16-2 EFFECTIVE PRODUCTION RATES Pele Mountain Resources Inc. – Eco Ridge Mine Project 5.0mWx3.2mH DoubleHeading (m/day) 14.7 Multi – Heading (m/day) 27.7 DoubleHeading (tpd) 642 Multi – Heading (tpd) 1,210 4.8mWx3.2mH 14.9 28.0 618 1,164 Description Heading Size Main Ramp Panel Headings Stope Ramp 4.8mWx3.2mH 14.9 28 618 1,164 1st Pass Pilot 3.4mWx3.0mH 17.2 31.8 477 880 st 4.6mWx3.0mH 19.1 35.2 700 1,293 nd 6.5mWx3.0mH 14.6 27.6 765 1,441 rd 5.5mWx3.0mH 16.6 31.4 736 1,389 1 Pass Slash 2 Pass Slash 3 Pass Slash MINING SEQUENCE Typically, the mining steps would be as follows: The deposit is divided into two portions, east and west, with each portion having a similar mine layout. The following sequence describes in detail how the eastern portion will be developed and mined which will be similar for the western portion. Approximately mid way along the eastern face, twin main ramps will be driven at a decline of 18% to provide access to the deposit. Eight equally spaced twin drive panel access drifts will be developed on either side of the main ramp. Block access ramps will be developed off the panel access drift. These ramps will be collared as the block entrances were exposed. Their development will proceed once the panel drifts have advanced 20 m (Figures 16-3 and 16-4). Once the block access ramp has broken through to the panel above, mining of the block will progress from the top down. Each mining block will have 24 stopes, 12 on either side of the block’s access ramp. Each stope measures 20 m in width and approximately 150 m in length. Each stope will be mined in four passes. The first pass would be a pilot driven along the top cut of the undeveloped stope followed by a second and third pass (Figure 16-5). All the muck will be hauled to the surface stockpiles. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 16-10 Technical Report NI 43-101 – June 20, 2012 Mucked Out Room Exhaust Airway Pillar 8 yd Scoop 16-11 Third Pass Mining Slashing Second Pass Mining First Pass Mining Figure 16-4 Eco Ridge Project Elliot Lake, Ontario, Canada Mining Sequence Section June 2012 www.rpacan.com Pele Mountain Resources Inc. 1st Pass 2nd Pass 3rd Pass 1067mmØ VENT DUCT 16-12 3.22m 3.44m 6.67m 6.67m 20.00m 6.67m 4.00m 4.76m 22° Figure 16-5 Eco Ridge Project Elliot Lake, Ontario, Canada Stope Development Section June 2012 www.rpacan.com Pele Mountain Resources Inc. www.rpacan.com SUPPORT SERVICES VENTILATION The final ventilation air volume capacity has been estimated 736 m3/sec (1,559,000 cfm), detailed in Table 16-3. Mine air volume requirements were based on the current Ontario Occupational Health and Safety Act and Regulations for Mines and Mining Plants, which prescribes 0.06 m3/s for each kilowatt of power. Total volume of air flow is provided in the following table. The primary Load-Haul-Dump units and haulage trucks rated at 95% utilization and the remaining service vehicles range between 21% and 79%. TABLE 16-3 AIR VOLUME REQUIREMENTS Pele Mountain Resources Inc. – Eco Ridge Mine Project Equipment Units kW /unit Total kW Utilization Jumbos – 2-boom EH Explosive Charger Scoops (5m3) Haul Truck (30 t) Bolting Jumbo Remix Truck Grader Service Truck Fuel & Lube Truck Shifter Vehicles Personnel Carrier Ventilation Subtotal Leakages 20% Miscellaneous Ventilation Required Conversion (CFMx1000) 6 4 7 16 7 2 1 5 1 10 2 61 120 111 243 393 110 110 110 110 110 30 61 720 444 1,701 6,288 770 220 220 550 110 300 122 11,355 32% 32% 95% 95% 32% 53% 79% 42% 53% 42% 21% Air Volume Required (m3/sec) 14 8 97 357 15 7 5 14 3 8 2 530 106 100 736 1,559 VENTILATION DISTRIBUTION SYSTEM Main ventilation fans located at the portal areas will provide fresh air to the mine by means of the main ramps. Auxiliary ventilation fans will redirect the fresh air from the main ramp to the panel drifts and mining blocks. Exhaust air will be collected from the mining blocks in the lower drift of the two panel drift system and directed to the limits of the panel where it will exhaust to surface through a series of low angle raises developed in the ore. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 16-13 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com DEWATERING Very little water is expected to occur from ground water inflows and the principal sources of water underground will be from service water required for drilling, wetting muck during and after blasting operations, and drilling ground support holes. The estimated dewatering pumping requirements will be 1.6 million litres per day or 19 litres per second. The pumping system is designed to handle 31 litres per second assuming pumps will run 18 hours per day at an efficiency of 80%. Development headings will be pumped as necessary using 11.2 kW submersible pumps. The headings will be driven on line and therefore may undulate slightly to follow the ore and some low spots may collect pools of water. An allowance has been made for a small number of 1.1 kW submersible pumps to pump this water back to the nearest sump. Main sumps would be located at the bottom of the mine and would be equipped with 104 kW submersible pumps, two operating and one on standby, pumping water directly to surface through a 150 mm standard pipe discharge line. ELECTRICAL The maximum installed power underground at full production is expected to be 8.5 MW at steady state. The underground power distribution network has been based on a new 44 kV overhead electrical line to be built by a local contractor over a distance of 10 km. The grid connection for the power line is located in the city of Elliot Lake. Stationary transformer stations will service the main ventilation fans while portable transformer stations will service the drill jumbos, dewatering pumps, auxiliary fans and area lighting as required. The portable substations will be widely available throughout the mine to provide the necessary flexibility to power equipment as the mine advances. SERVICE SHOPS Equipment servicing will be completed on surface in a building located between the two mine access ramps. Lubricants and service utility vehicles will enable the mechanical Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 16-14 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com crews to quickly access equipment breakdowns and allow efficient routine service of drill rigs and LHDs at their place of work. EQUIPMENT The selection of equipment at the Eco Ridge Mine Project has been based on the philosophy of using best available relevant technology for a fully mechanized mining operation. The high capital cost of mechanized equipment and higher levels of skills required from operating personnel calls for maximizing equipment utilization. The estimated equipment fleet size is based on detailed cycle time using information from equipment suppliers, other operations and in-house operating experience where available. Two 10.5-hour shifts have been assumed per day, with an effective utilization of 9.5 hours per shift for equipment. Allowance has been made for travelling to and from the workplace at the change of shift. An average of 85% mechanical availability and 83% utilization were assumed when estimating the total mucking and haulage fleet size. The total number of active units required for drilling, charging and bolting was estimated based on equipment performance with allowances made for set-up/tear down and equipment travel to the next heading. These numbers were then increased to account for mechanical availability of 85%. Table 16-4 summarizes the necessary mine equipment at Eco Ridge Mine. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 16-15 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 16-4 MINE EQUIPMENT SUMMARY Pele Mountain Resources Inc. – Eco Ridge Mine Project Description Jumbos – 2Bm Explosive Charging Rig Scoops – 5m3 Haul Trucks – 30 tonne Bolting Jumbo Remix Truck Grader Service Truck Fuel and Lube Truck Personnel Carrier Shifter Vehicles Units 6 4 8 18 7 2 1 5 1 2 10 DEVELOPMENT EQUIPMENT Two boom low profile electric hydraulic drill jumbos were selected to carry out the development advance. The drill rig will be equipped with the latest generation drifter technology. A typical profile is illustrated in Figure 16-6. Six machines are recommended, three for the east half of the deposit and the remaining three for the west half of the deposit. Four explosive charging rigs will be used to load the holes in the face. Ground support will be installed by a low profile bolting rig. The unit is a one man operated electro-hydraulic low profile bolting machine capable of bolting in an excavation with headroom as low as 1.7 m. The unit is also capable of installing several rows of bolts without moving the machine. The operator is protected by a FOPS telescopic canopy. The unit is equipped with an automatic function that allows the operator to concentrate on safe, fast and accurate drilling and bolt installation. Muck loading in development headings will utilize diesel- powered LHDs. The 5 m3 scoop will load 30 tonne trucks for haulage to the surface leach pads. Typical 5 m3 scoop and 30 tonne truck profile illustrated in Figures 16-7 and 16-8, respectively. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 16-16 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com PRODUCTION EQUIPMENT In the room and pillar areas, two boom low profile electric/hydraulic jumbos were selected to carry out the production advance. Explosive loading units used in the development headings would be shared with the production headings. Muck loading and haulage trucks used in the development headings would be shared with production areas. It was estimated that a total of seven LHD are required at full production. The number of trucks would depend on the depth of operation. In the section on mining capital costs (Section 21 of this report), the number of units by year is forecasted. In year five, it is estimated that 16 units will be required. SERVICE A fleet of ten 4x4 vehicles modified for underground use is required to transport people and materials. A personnel carrier is also required to carry workers from the shop/warehouse/office/dry complex to the underground workings. Various service vehicles will be purchased to transport large bulky material from the surface warehouse to the underground storage facilities. A grader will maintain the underground road ways. A fuel and lubricant dispensing type vehicle will be used to service the less mobile units like the drill jumbo, explosive loading rig and the bolting jumbo. Units such as the scoop, truck and remixer will be serviced on surface. MANPOWER Manpower requirements for the underground mine have been estimated based on first principles. For the various size openings the total mining cycle time was estimated. From the individual components of the cycle i.e. drilling, explosive loading etc., the capacity of each unit could be identified. Knowing the daily production target, the units required to meet the target could be determined. Manning the equipment would identify the number of equipment operators required which makes up the majority of the mine hourly workers. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 16-17 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com The number of shifters, technical staff and underground administrative staff to provide maintenance, technical and administrative support to the miners has been based on field experience. The underground operation would consist of two shifts, at 10.5 hours per shift, seven days per week. The 10.5 hour shift would allow time for blasting gases to dissipate. Operations manpower will peak at approximately 251 people on payroll distributed as shown in Table 16-5. This study was based on Pele Mountain performing their own development and production mining. TABLE 16-5 MANPOWER REQUIREMENTS Pele Mountain Resources Inc. – Eco Ridge Mine Project Description On site On Payroll Technical Support 18 18 Mining 109 213 Construction 10 20 Total 127 251 Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 16-18 Technical Report NI 43-101 – June 20, 2012 2.97 2.27 1.96 16-19 Low-Profile Twin-Boom Jumbo Figure 16-6 Eco Ridge Project Elliot Lake, Ontario, Canada Stope Drilling Section June 2012 www.rpacan.com Pele Mountain Resources Inc. Figure 16-7 Pele Mountain Resources Inc. Eco Ridge Project Elliot Lake, Ontario, Canada Tramming Section 2.53m 2.97m 16-20 1.96m June 2012 www.rpacan.com Low Profile 5 cu.m LHD 30 Tonne Haul Truck 16-21 Haulage and Fresh Air Drift Exhaust Drift Figure 16-8 Eco Ridge Project Elliot Lake, Ontario, Canada Hauling Section June 2012 www.rpacan.com Pele Mountain Resources Inc. www.rpacan.com MATERIAL HANDLING TRADE-OFF STUDY A trade-off study was carried out to look at using conveyors instead of trucks for material handling to surface. Most of the mine development layouts will be the same as in the base case trucking option. The main difference will be the use of three ramps instead of two; a central triple-heading ramp and two sets of dual ramps. The central triple-heading ramp will consist of a main conveyor, which will transport muck to surface, and equipment access ramps on either side. The dual ramps will be located 1,380 m on either side of the central ramp. The three ramps will be driven at 18% on the footwall contact of the MCB reef. The blasted muck from working stopes will be transported by LHD to secondary conveyors located in the panel access drifts. Panel conveyors will transfer the muck to the main conveyor via a transfer chute and a grizzly feeder. The main conveyor will transfer the material to surface for processing. Both the feeder conveyor drifts and the main conveyor drifts will be used as ventilation exhaust way while the haulage drifts will be used for fresh air intake. Production will start with blocks adjacent to the main conveyor ramp and move away sequentially along strike. This results in a schedule with much more uniform grades year to year, in comparison to the base case trucking option, which targets higher grades in early years. Key changes to inputs for the conveyor option are listed below: Adjusted production schedule. Initial capital cost of $553 million (compared to $563 million for the base case). Total capital cost of $675 million (compared to $670 million for the base case). Mining operating cost of $35.23 per tonne of ore mined (compared to $42.64 per tonne for the base case). The conveyor scenarios provide an operating cost advantage of 15%. This advantage is offset by the change in the production schedule (less opportunity to mine higher grades first). The resulting discounted cash flow analysis has a slightly lower IRR, and slightly higher NPV. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 16-22 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com The use of conveyors for material handling may provide economic advantages, and is worth consideration in future studies. Particular attention should be paid to impacts on grade distribution in production schedules for each option. In RPA’s opinion, conveyors may also provide operational advantages that are difficult to quantify economically at this stage of the Project, including better mine ventilation, reduced traffic on the ramps, and easier material handling as the mine extends at depth. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 16-23 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 17 RECOVERY METHODS The results of the metallurgical tests and brief economic trade-off studies have led to the selection of a process including crushing and grinding, froth flotation, and magnetic separation, acid baking and water leaching, solid/liquid separation, high density sludge (HDS) removal, and recovery of the valuable elements by solvent extraction and precipitation as shown in Figure 17-1. CRUSHING AND GRINDING Run-of-mine (ROM) throughput for the process plant is assumed to be 3.2 million tpa, or 9,143 tpd. The ROM material is transported to the surface and dumped on the primary stockpile. Mill feed is reclaimed by front end loader and delivered to the crusher feed bin. A grizzly prevents oversize materials from entering the crushing circuit. The undersize from the grizzly is screened to remove fines before being fed to the crusher. The crushed product is combined with the screen undersize and dumped on an intermediate stockpile for homogenisation. Crushed material is reclaimed from the intermediate stockpile and fed to the grinding circuit, where it is ground to 100% passing 300 µm. Discharge from the grinding circuit is diluted with process water and pumped to classifying cyclones, where it is classified into minus 25 µm in the cyclone overflow and plus 25 µm in the cyclone underflow. The overflow is pumped to flotation, while the underflow is directed to the two-stage magnetic separation circuit. Concentrate from magnetic separation is reground to 100% passing 74 µm before mixing with concentrate from flotation, and the combined concentrate is filtered to remove excess moisture. The filter cake is directed to the acid baking process. Tailings from flotation and magnetic separation are pumped to the tailings thickener. The thickened underflow supplies a paste backfill plant, and the remainder of the tailings are pumped to the tailings storage facility. ACID BAKING Dewatered concentrate containing uranium and rare earth minerals is mixed with concentrated sulphuric acid at an acid:concentrate ratio of 0.3:1, and cured for a period of one hour. After curing, the acidified concentrate mixture is transferred to a rotary kiln Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 17-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com and baked at 310°C for approximately three hours. Baked solids from the kiln are discharged into a water leach circuit and leached for a period of three hours. Various sulphates formed during acid baking, including uranium and rare earth sulphates, are dissolved during leaching. After leaching, the slurry is pumped to a solid/liquid (S/L) separation circuit. A counter-current decantation (CCD) circuit is used for washing and S/L separation. Residues from the CCD circuit will be sent to the tailings storage facility. Overflow from the CCD circuit, the pregnant leach solution (PLS), continues to downstream processing for purification and recovery of valuable metals. Since testwork is still in its early stages, and currently focused on further defining the concentration and extraction process, no testwork has been carried out on the treatment of the PLS. The unit operations that occur after acid baking and water leaching are preliminary and were selected based on previous experience with similar operations. RPA understands that the processes must be selected and defined in detail through future testwork. NEUTRALIZATION AND IRON REMOVAL Overflow from the CCD circuit, the PLS, is neutralized in a four-stage iron precipitation (PPTN) circuit using milk of lime to achieve a final pH of 3.8, to remove heavy metals and, predominantly, iron. The high density sludge (HDS) thickener receiving the slurry from the iron precipitation circuit, the iron/gypsum cake generated in the uranium extraction plant, and the iron sludge generated in the REE extraction plant, will produce an overflow that will become the feed to the uranium extraction circuits in the uranium extraction plant. The ferric iron (Fe3+) content in the solution reporting to the uranium extraction circuit must be maintained between 6 g/L Fe3+ to 10 g/L Fe3+. The sludge in the underflow from the HDS thickener will be mixed into the paste backfill and sent underground for final disposal. URANIUM EXTRACTION AND YELLOWCAKE PRECIPITATION The final solution discharged from the HDS removal unit will be pumped to a combination of clarifier and sand filter arrangement to ensure solution clarity prior to uranium solvent extraction. Uranium is recovered by solvent extraction, followed by precipitation and drying. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 17-2 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com The clarified PLS from the clarifier and sand filter feeds the uranium extraction circuit which consists of three high-rate mixer-settlers. In the uranium extraction circuit, the uranium is extracted by counter-current contact with an organic solution containing 2.5% v/v Alamine 336, 2.5% v/v Isodecanol in a kerosene diluent. The aqueous solution (PLS) to organic solution volume (A:O) ratio is estimated to be 20 volumes of aqueous to one volume of organic for the extraction process. The aqueous to organic ratio was assumed in order to produce an aqueous solution of approximately 100 g/L of U3O8 in the uranium stripping circuit. Testwork is required to determine the number of uranium extraction stages and the actual aqueous to organic ratio that is required. The organic solution carrying the uranium enters a four-stage stripping circuit. The stripping medium is assumed to be an aqueous solution of 400 g/L sulphuric acid (H2SO4). The organic solution is stripped of its uranium content by counter-current contact with the aqueous solution at an estimated acid to organic ratio of one to 20. The number of stripping stages and acid to organic ratio must be confirmed through further testwork. The aqueous phase from the extraction circuit, from which most of the uranium has been removed, will feed the REO plant. The strip solution, rich in uranium, at approximately 100 g/L U3O8, is directed to a fourstage iron and gypsum precipitation circuit where the iron and gypsum are precipitated out of the solution at pH 3.5 using milk of lime. The resulting precipitate, i.e., sludge, is directed to a drum filter to produce an iron and gypsum filter cake and a filtrate that contains the uranium. The iron and gypsum cake from the drum filter is directed to the high density sludge (HDS) thickener in the neutralization and iron removal circuit. The filtrate is directed to a three-stage yellowcake precipitation circuit where it is treated with a 70 wt % solution of hydrogen peroxide (H2O2), to produce yellowcake slurry. The yellowcake slurry is dewatered in a thickener and a centrifuge, producing what is known in the uranium industry as “yellowcake” due to its bright yellow colour. This yellowcake is further dried in a porcupine dryer producing the final product, which is packed and shipped. The final uranium content in the yellowcake is expected to be approximately 70 wt % U. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 17-3 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com REE EXTRACTION AND CARBONATE PRODUCTION The aqueous stream from uranium extraction will feed the REO plant. It will be a relatively pure solution from which all ferric iron and some of the thorium has been removed, while still containing almost all of the leached yttrium and REEs. The feed solution to the REE plant will be fed to a high-rate mixer-settler where it is mixed with an organic stream containing 10% diethyl hexyl phosphoric acid (DEHPA) and 2% tributyl phosphate (TBP) in a kerosene diluent (Exxsol D80) with an acid to organic ratio of approximately ten to one. The valuable REEs transfer to the organic phase in a single extraction step along with unwanted constituents, primarily iron and thorium. The loaded organic is first contacted with a mixed acid at 1.5 normal nitric and 1.5 normal sulphuric to strip the yttrium and rare earths. The organic is stripped in five mixer-settlers arranged in counter-current configuration with an acid to organic ratio of 1.25 to one. The strip solution is purified and the valuable materials are recovered. The organic is then washed with fresh water in five mixer-settlers arranged in countercurrent flow to remove all traces of nitric acid, with an acid to water ratio of one to 20. The organic is then contacted with a salt-sulphuric solution at 5 g/L sodium chloride and 8.5 normal sulphuric acid in an agitated tank. This removes iron, uranium, and thorium from the organic, with the thorium precipitating out as thorium sulphate. The thorium salts are thickened and pumped to waste. The salt-sulphuric solution overflowing the thickener is re-used as strip solution after reagents are added to achieve the appropriate reagent concentrations in the strip solution. The organic is then washed with fresh water in a single mixer-settler. A bleed stream of the organic is pumped to a small stripping mixer-settler where it is treated with an ammonium bifluoride solution to recover scandium. The combined stripped organic stream is then pumped back to the extraction mixer-settler for re-use. The yttrium strip solution is partially neutralized with milk of lime to pH 3.2 to remove any contained iron and thorium, in a five-stage neutralization circuit. The slurry is filtered using a drum filter and the pure solution is neutralized to pH 8.0 with magnesia slurry in a three-stage precipitation circuit. The iron and thorium cake produced from the drum Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 17-4 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com filter is recycled back to the HDS thickener in the neutralization and iron removal circuit. The precipitated yttrium and REEs are thickened and the slurry is filtered. The filter cake is reacted with 29% w/w sodium carbonate solution to convert the precipitate to a carbonate form. This slurry is then filtered and the cake is dried in a porcupine dryer. The dried mixed rare earth carbonate product is packed in drums in preparation for separation into individual oxides. DESIGN CRITERIA Design criteria listed in Table 17-1 have been followed for the conceptual mass balance calculation for the acid baking plant. TABLE 17-1 CONCEPTUAL DESIGN CRITERIA Pele Mountain Resources Inc. – Eco Ridge Mine Project Description ROM Throughput Operating days per year % Uranium in feed % TREO in feed H2SO4: solids ratio Acid baking temperature Acid baking retention time H2O:solids ratio in water leaching Water ratio for CCD circuits Rate 3,200,000 9,143 350 0.045 0.13 300 310 3 50 2.5:1.0 Units tpa, or tpd d/a % % kg/t ºC hr % CONCEPTUAL MASS BALANCE The primary purpose of a conceptual mass balance calculation is to estimate the liquid and solid volumes to be processed in each unit operation and to provide a preliminary design basis for equipment sizes and cost estimation. Reagent consumptions and cost estimations are also supported by the conceptual mass balance. The conceptual mass balance is provided in Table 17-2. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 17-5 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 17-2 CONCEPTUAL MASS BALANCE Pele Mountain Resources Inc. – Eco Ridge Project Description Feed ROM throughput Uranium in feed TREO in feed U3O8 in feed TREO in feed Ground Ore Separation Portion of ground ore to flotation Portion of ground ore to magnetic separation Consumption rate of collector in flotation Collector used in flotation Overall portion of concentrator feed to acid baking Concentrates to acid baking Concentrate Acid Baking (H2SO4 : Solids) ratio Total H2SO4 Water Leaching Solids in outgoing stream Product Overall uranium recovery (assumed) Uranium production Overall TREO recovery from concentration, acid baking, and water leaching TREO production Unit Route 2 tpa wt % wt % tpa tpa 3,200,000 0.045 0.13 1440 4180 % % kg/t tpa % tpa 15 85 2.0 1,600 19.3 617,600 kg/t tpa 300 185,280 wt % 50 % tpa 90 1,296 % 88.2 tpa 3,686 Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 17-6 Technical Report NI 43-101 – June 20, 2012 Concentrated Sulfuric Acid Off-gas ACID BAKING Collector WATER LEACHING FLOTATION Flocculant O/F Tailings ROM CRUSHING GRINDING S/L SEPARATION CLASSIFICATION REGRINDING Solids Lime Slurry U/F 17-7 MAGNETIC SEPARATION Fe PPTN & HDS REMOVAL Fe Sludge Tailings Organic Solvent Organic Stream URANIUM SX Aqueous Stream URANIUM PRODUCTION Yellow Cake U 3O8 REO PRODUCTION REO Carbonate Figure 17-1 Eco Ridge Mine Project Elliot Lake, Ontario, Canada Process Flow Sheet June 2012 www.rpacan.com Pele Mountain Resources Inc. www.rpacan.com 18 PROJECT INFRASTRUCTURE EXISTING MINING INFRASTRUCTURE Pardee Amalgamation Mine Limited (Pardee) was formed in 1954 to consolidate the Aquarius property with other properties in the area. In 1955, Pardee carried out extensive mapping, trenching, diamond drilling, and the excavation of a decline adit, bulk sampling, and metallurgical tests. The adit was driven along the dip of the MCB for a distance of 30.5 m (azimuth 120° west and 27° dip) and channel samples were taken approximately every 1.5 m. Highway 108 passes through the southwest corner of the property, and a power transmission line crosses through the centre of the property. OTHER INFRASTRUCTURE The remaining infrastructure, including access road, plant roads, parking, administrative offices, shops, warehouse, power line, electrical substation, power distribution, waste water treatment facilities, water supply and distribution, explosives magazine, and natural gas supply must be constructed for the Eco Ridge Mine Project. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 18-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 19 MARKET STUDIES AND CONTRACTS URANIUM A uranium price of $70/lb U3O8 has been used in this PEA, based on independent metal price forecasts from banks and financial institutions. RPA notes that the price used in the PEA, while above the current price, is within the range of medium- to long-term forecasts. RARE EARTHS Pele Mountain and RPA collected historical price information, supply/demand analysis, and long term forecasts for REO. The sources of price information include the websites of Metal-PagesTM and Asian Metal, and analyst reports by Asian Metal, TD (Toronto Dominion) Newcrest Inc., and CIBC (Canadian Imperial Bank of Commerce). RARE EARTH SUPPLY Rare earths are found in more than 200 minerals, of which about a third contain significant concentrations. Only a handful, however, have potential commercial interest. The most important source minerals are carbonates (bastnaesite) and phosphates (monazite and xenotime). Apatite is also an important source of rare earths, while heavy rare earths are more commonly found in minerals in granitic and alkaline rocks and in ionic clays. The main geological environments for rare earths are: Carbonatites – bastnasite (Mountain Pass, California; Kola Peninsula; Russia, Sichuan, China) Monazite and xenotime-bearing placers (west coast of Australia; east coast of India) Iron-bastnaesite rare earth element deposits (Bayan Obo, Inner Mongolia; Olympic Dam, Australia) Ion absorption clays (Longnan, Jiangxi, China) loparite and eudialyte in alkaline intrusives (Kola Peninsula, Russia; Dubbo, Australia) Pegmatites, hydrothermal quartz and fluorite veins (Northern Territories, Australia; Karonge, Burundi; Naboomspruit, South Africa) Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 19-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Other generic types which may contain rare earths are: Phosphates (Phosphoria Formation, western USA), Uranium deposits in sandstone and black shales (Wheeler River, Alberta; Williston Basin, Saskatchewan), Mylonites in limestones (Nam-Nam-Xe, Vietnam), Scheelite skarns (Ingichke, Uzbekistan), Nickel deposits (Sudbury Basin, Ontario). By far the most important current sources of rare earths are the Bayan Obo iron rare earth deposits near Baotou, Inner Mongolia, the bastnaesite deposits in Sichuan, China and the ionic clay deposits in southern China. China is the dominant source of all rare earth oxides, accounting for approximately 97% of world production in 2009. Light rare earths are primarily produced in northern China (Inner Mongolia) and south-western China (Sichuan). The heavy rare earths are primarily produced in southern China (Guangdong), from ionic clays. There are distinct differences in the elemental composition of various rare earth sources, as illustrated in Table 19-1. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 19-2 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 19-1 DISTRIBUTION OF RARE EARTHS BY SOURCE – CHINA Pele Mountain Resource Inc. – Eco Ridge Mine Project Baotou, Inner Mongolia Bastnaesite Concentrate Sichuan Guangdong Longnan, Jiangxi Mountain Pass, Ca Mt. Weld, W. Australia1 Bastnaesite Concentrate High-Eu clay High-Y clay Bastnaesite Monazite 50% 50% 92% 95% La 23 29.2 30.4 2.1 33.2 25.5 Ce 50.1 50.3 1.9 0.2 49.1 46.74 Pr 5 4.6 6.6 0.8 4.34 5.32 Nd 18 13 24.4 4.5 12 18.5 Sm 1.6 1.5 5.2 5 0.789 2.27 Eu 0.2 0.2 0.7 0.1 0.118 0.44 Gd 0.8 0.5 4.8 7.2 0.166 1 Tb 0.3 0 0.6 1 0.0159 0.07 Dy 0 0.2 3.6 7.2 0.0312 0.12 Er 0 0 1.8 4 0.0035 0.1 Y 0.2 0.5 20 62 0.0913 trace Ho-Tm-Yb-Lu 0.8 0 0 5.9 0.0067 trace Total TREO 100 100 100 100 99.9 100 Source Ore Type TREO in Concentrate2 Element 1 Central Zone pit assays for La, Ce, Pr, Nd, Sm, Dy, Eu, and Tb 2 TREO contents of China clays represent the relative amounts in concentrate produced from the clay deposits Source: Neo-Materials International, Harben, Lynas Corp. As a consequence of the mix of the individual elements within a raw material source, the distribution of supply of the individual elements does not match the distribution of demand for the elements. The mixed composition of rare earth minerals necessitates the production of all of the elements within a given ore source. Such production does not necessarily equal the demand for the individual oxides, leaving some in excess supply and others in deficit. Overall production of rare earths on an oxide basis is therefore typically greater than the sum of demand for the individual elements in any given year. Total supply of rare earth oxides for 2010 was estimated at between 123,600 tonnes and 124,000 tonnes, as illustrated in Table 19-2. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 19-3 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 19-2 RARE EARTH SUPPLY – 2008 & 2010 Pele Mountain Resource Inc. – Eco Ridge Mine Project Source China Supply 2008 (tonnes REO) 117,000 Supply 2010 (tonnes REO) 120,000 ~5,000 N/A 2,500 - 3,000 1,800 - 2,000 100 25 - 50 2,000 1,800 – 2,000 121,600 - 127,100 123,600 – 124,000 Others Recycling Russia India Mountain Pass Total Source: Roskill Information Services, 2010 & 2011 As described by Asian Metal, the international rare earths market has grown at an unprecedented rate since China cut export quotas by approximately 40% in 2011 as seen in Figure 19-1. China’s overwhelming control on the rare earth supply chain, from upstream mining to downstream processing and end-user products, is likely to remain intact on all but a few materials through 2016. Further price increases are expected with continued decreases in export availability from major Chinese suppliers and a surge in domestic China demand. FIGURE 19-1 CHINESE RARE EARTH EXPORT QUOTAS BY YEAR (THOUSANDS OF TONS) 70 65.6 61.8 Tonnes (000) 60 59.6 47 50 50.1 40 30.3 30 28 20 10 0 2005 Source: Asian Metal 2006 2007 2008 2009 2010 2011 (estimated) Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 19-4 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com A crackdown on illegal mining operations, which accounted for an estimated 20% to 25% of production over the past five years, has substantially cut down on the availability of material on the spot market. A major consolidation of the market, which began in 2009, has also limited the number of active rare earth miners, separation plants, and exporters in China. New production from US-based Molycorp and Australia-based Lynas should add between 30,000 tons (27,000 tonnes) and 40,000 tons (36,000 tonnes) of high purity material to the market by the end of 2012, which is widely expected to saturate the light rare earths market when it becomes available. The ore bodies from Molycorp’s Mountain Pass and Lynas’ Mount Weld mine sites are predominantly composed of light rare earths - lanthanum, cerium, praseodymium, and neodymium. The heavy rare earths and yttrium are found at the mines only in trace amounts and will be neither recovered nor produced in quantities that would have a material impact on global supply. It should be noted that the heavy rare earths – Dy, Er, Eu, Gd, Ho, Lu, Sc, Sm, Tb, Tm, Y, Yb – are not only much more rare than the light rare earths, but the separation and processing of heavy rare earth-rich concentrate into high purity oxides and metals outside of China will require substantial new capital investment. At present, substantially all heavy rare earth processing facilities are in China, and previous scoping studies done by prospective rare earth mining ventures indicate that a new separation plant would cost roughly US$250 million to US$350 million and take three to four years to complete. As a result, availability of heavy rare earths will be contingent on Chinese production levels until 2015 at the earliest - the soonest a non-Chinese processing facility could be completed. On a macro level, over the next five years, the Chinese government is expected to further regulate the rare earth mining industry. China has already begun enacting a series of new policies designed to improve environmental guidelines, limit illegal production, establish provincial and national stockpile reserves, and continue a consolidation of the overall industry. RARE EARTH PRICING The market for rare earth products is relatively small, and information on pricing and sales terms, especially for 2016, is difficult to obtain. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 19-5 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Sustained growth in demand and price is expected for nearly all rare earths through 2016 with the exception of lanthanum, cerium, and praseodymium. REO price forecasts for 2016 were obtained from a number of sources, which covered a wide range of values. The prices used in the PEA cash flow are described in Table 19-3, below. The prices were applied as a constant throughout the Life of Mine (LOM) schedule. TABLE 19-3 REO FORECAST PRICES VS. CURRENT SPOT PRICES Pele Mountain Resources Inc. – Eco Ridge Mine Project Rare Earth Oxide Ce2O3 FOB China Forecast (US$/kg) 18 FOB China Q2 2012 Spot* (US$/kg) 25 La2O3 20 24 Nd2O3 175 175 Pr2O3 140 140 Sm2O3 80 90 Eu2O3 2,900 2,300 Gd2O3 150 100 Sc2O3 3,000 7,200 Y2O3 150 132 Yb2O3 90 90 Dy2O3 1,450 1,100 Er2O3 195 195 Ho2O3 - - Lu2O3 1,200 - Tb4O7 2,200 2,000 Tm2O3 3,000 - * Source: Metal-Pages.com The average rare earth oxide price used in this PEA is US$90/kg, while current (Q2 2012) prices average US$103/kg. MARKETING CONCLUSIONS RPA considers these REE prices to be appropriate for a PEA-level study, however, we note that the recent market volatility introduces considerably more uncertainty than a comparable base or precious metals project. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 19-6 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com CONTRACTS No contracts relevant to the PEA have been established by Pele Mountain. Pele Mountain has not hedged, nor committed any of its production pursuant to an off-take agreement. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 19-7 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 20 ENVIRONMENTAL STUDIES, PERMITTING, AND SOCIAL OR COMMUNITY IMPACT INTRODUCTION Pele Mountain has conducted preliminary baseline environmental studies in support of development of the Eco Ridge Mine Project. Consultation with potentially affected communities, including First Nations, has also been given a high priority by Pele Mountain. Specifically, the studies that have been conducted in support of the Project include: Terrestrial Ecosystems Preliminary Site Characterization Report – 2008 Aquatic Ecosystems Preliminary Site Characterization Report – 2008 Additional Aquatic Studies of Rioux Lake Preliminary Groundwater Scoping Evaluation – 2008 Stage 1 Archaeological Assessment Conceptual Design of a Tailings Disposal Facility (TDF) – 2008, updated in 2012 Project Description submitted to the Major Projects Management Office and the Canadian Nuclear Safety Commission in 2008 (for information purposes only, not as a formal regulatory submission) Preliminary Geo-Chemical Characterization of Tailings – on-going Work Planning for Detailed Environmental Characterization Studies – ongoing While significant progress has been made in terms of preparing for the environmental assessment and permitting of the Project, significant work remains before the Project is approved and licensed. The work that has been conducted to date, and the work that will be required in the future, is outlined in more detail below. It should be noted that the history of the uranium and REE mining and processing operations at Elliot Lake shows that these operations can be conducted without causing damage to the environment. The primary environmental issues were resolved during the Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com later operational period of the former Elliot Lake uranium mines, including the management and treatment of wastewater entering the environment, management of tailings and waste rock, and the health, safety and environmental systems required to operate underground mines. These issues were identified and addressed and mitigation methods were developed. The mitigation methods have led to the development of a quality assurance process to ensure that all potential environmental issues are identified and addressed through an extensive licensing process from development through to decommissioning. For the former mines, the control methods are well understood and extensive environmental monitoring programs have been put in place to ensure the control methods are effective. The successful implementation of these programs has demonstrated that uranium and rare earths mining and milling can be conducted without causing significant adverse environmental impacts. This should be of assistance with respect to obtaining approval for the Eco Ridge Mine Project. Recent experience in Elliot Lake has demonstrated that potential impacts associated with mining can be effectively managed, however, “Legacy issues” and the potential for cumulative effects associated with the former mines will have to be addressed. PERMITS, LICENCES AND OTHER LEGISLATIVE REQUIREMENTS The regulation of nuclear substances is a federal responsibility and a licensing process has been established to protect health, safety, security, and the environment. The licensing process for new uranium mines and mills in Canada is outlined in an information document (Licensing Process for New Uranium Mines and Mills in Canada, INFO-0759) issued by the Canadian Nuclear Safety Commission (CNSC) in March 2007. CNSC is the primary regulator for new uranium mines and mills in Canada. The commission has the responsibility to make licensing decisions based on laws and regulations. Their authority is derived from specific federal legislation – the Nuclear Safety and Control Act (NSCA) and regulations made under the NSCA, as well as the Canadian Environmental Assessment Act (CEAA). The site preparation, construction, operation, decommissioning, and abandonment of a uranium mine and mill require separate licences from CNSC. In making a licensing decision, the Commission considers the application, recommendations from CNSC staff, and any written or oral presentations from intervenors made during public hearings. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-2 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com It is important to note that the federal government recently tabled new legislation that is intended to integrate and streamline regulatory processes. The operational details of the legislation have yet to be defined and, as a consequence, it is premature to determine the extent to which the regulatory process for the Eco Ridge Project will be affected although the stated objectives of the new legislation are expected to be beneficial. On this basis, the information presented in the PEA is consistent with the regulatory regime at the time of writing. However, Pele Mountain will continue to monitor the federal government’s regulatory reform initiative and the approach for the Eco Ridge Project will be adjusted accordingly. The licensing process under the NSCA is initiated by an application to CNSC. CNSC licensing of a new uranium mine facility is sequential. The licences are: Licence to Prepare the Site Licence to Construct a Facility Licence to Operate a Uranium Mine, Mill and Waste Management Facility Licence to Decommission a Site Licence to Abandon a Site The initial licence application is generally oriented to the site preparation and development stages of the project. Discussions with CNSC staff on the level of information that will be required in the initial application are required before the application is prepared. Information required in support of the application to prepare the site and construct a new mine and processing facility typically includes: A description of the proposed design for the mine, tailings management, processing facility, and waste management systems. Environmental baseline data on the site and surrounding area. A description of the site geology, ground support, and groundwater regime (local and regional). The quantities and grade of the production and waste rock and plans for storage and disposal. A description of the mining and processing methods. Results of the process hazard analysis and the proposed quality assurance program for the design of the mine, tailings management, and processing facility. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-3 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com A proposed decommissioning plan. Measures to mitigate the effects on the environment and the health and safety of personnel that may arise during construction, operation, or decommissioning of the facility. Information on the potential release of nuclear substances and hazardous materials, and proposed measures to control them. Programs and schedules for recruiting and training operations and maintenance staff. A description of all proposed laboratory facilities and programs. The proposed commissioning plan and schedule. The application for the licence to prepare the site requires the completion of these studies. Upon receiving the licence application, CNSC conducts a financial review and establishes the review plan for the licensing procedures. It is important that the project proposal not undergo substantive changes with regard to the proposed production rates and methods, and capacities of the facilities. Changes to the production plan subsequent to the application could delay the permitting process. OTHER LICENSING REQUIREMENTS The Project will have to be evaluated for additional federal requirements including, but not limited to: Fisheries Act Canada Water Act Canadian Environmental Protection Act Provincial permits and legislative requirements are summarized as follows: PERMIT TO TAKE WATER Before construction and operation of the proposed freshwater intake facility from Rioux Lake, Pele Mountain will be required to obtain a permit to take surface water (PTTW). A permit to take groundwater will also be required for mine dewatering. CERTIFICATE OF APPROVAL: INDUSTRIAL SEWAGE During operations, active recycling of all contaminated liquids will be the dominant water management strategy employed at Eco Ridge Mine. However, when process water must be released, it will be treated and discharged to a marshy area south of the Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-4 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com processing facility, which eventually drains to Rioux Lake, two kilometres further south. The industrial sewage treatment system needed to handle the process water will require a certificate of approval for industrial sewage. It should be noted that significant quantities of sludge will be generated through the uranium and REO processes that must be managed. CERTIFICATE OF APPROVAL: AIR A Certificate of Approval – Air is required for the ongoing operation of any equipment that may discharge a contaminant, potentially including noise and vibration, to the atmosphere. Potential contaminant sources include the mine openings, roads, tailings facilities, and the processing plant. MINISTRY OF NORTHERN DEVELOPMENT, MINES AND FORESTRY CLOSURE PLAN In Ontario, a company cannot commence mining operations until it files a certified closure plan with the Ministry of Northern Development, Mines and Forestry (MNDMF). The closure plan must include information such as current project site conditions, a project description, rehabilitation measures, monitoring programs and procedures, and expected ultimate site conditions. In addition, an estimate of the cost to rehabilitate the site must be provided, along with financial assurance. MINISTRY OF NATURAL RESOURCES WORK PERMIT (LAKES & RIVERS IMPROVEMENT ACT) Before construction and operation of the proposed freshwater intake facility, and potentially other facilities, Pele Mountain will be required to obtain a Work Permit from the Ontario Ministry of Natural Resources (MNR). WASTE GENERATOR REGISTRATION Waste of a type or amount considered "registerable" or "hazardous" as defined under the Environmental Protection Act, Reg. 347 requires the waste generator to be registered. A preliminary Project schedule is presented later in this report, in Figure 24-1. The schedule includes the CNSC EA and licensing process due to the critical role that this process will play in determining the overall timeline of the Eco Ridge Mine. Pele Mountain currently plans to re-initiate consultations with CNSC during the summer of 2012 and the schedule will be revisited based on any feedback provided at that time. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-5 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Overall, the schedule is considered to be optimistic. Although technically feasible, recent experience suggests that one or more factors could result in substantive delays to the schedule as presented. ENVIRONMENTAL ASSESSMENT Prior to any licence being granted, CNSC must meet obligations under the Canadian Environmental Assessment Act (CEAA). Under CEAA, an application for a licence to prepare a site and construct a new uranium mine or mill requires an environmental assessment (EA) of the potential environmental impact of the proposed project. The EA is a planning document and the purpose of the EA is to identify whether a project is likely to cause significant adverse environmental effects, taking into account the appropriate mitigation methods. Only when this determination has been made can the federal authority issue a licence. The proposal may trigger other EAs by other federal or provincial departments. These EAs would likely be coordinated and harmonized to avoid duplication for the proponent. New projects that are not being constructed within the boundaries of an existing mine or mill normally require that a Comprehensive Study be conducted by CNSC, however, it is also possible that a Panel Review will be required instead of a Comprehensive Study. The CNSC guidelines suggest a project “could be referred to a mediator or to a review panel if public concerns warrant it”. The first step in the EA process involves the issuance of EA Guidelines by CNSC. The EA Guidelines identify the scope of the project and the factors to be included in the EA, including the identification and assessment of possible mitigation measures for possible adverse environmental effects. CNSC also prepares a Comprehensive Study Track Report (CSTR) which describes and discusses any public concerns, potential adverse environmental effects, and the ability of the comprehensive study to address any issues. These two documents, the EA Guidelines and the CSTR, are issued by CNSC staff for public review and comment and submitted to the Commission Tribunal for consideration at a one day hearing. CNSC then submits the CSTR and its recommendations to the Minister of the Environment. If it is decided that the EA will continue as a comprehensive study, CNSC delegates the completion of the technical studies and preparation of the Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-6 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com EA to the proponent. The proponent must then provide all information necessary to satisfy the approved EA Guidelines. The proponent’s Study Report is reviewed and analyzed by technical specialists at CNSC and other federal authorities. The CSTR is then submitted to the Minister of the Environment, with public consultation on it being conducted on behalf of the Minister by the Canadian Environmental Assessment Agency (CEAA). The Panel managing the EA process may rely heavily on issues and concerns raised by the public. The Minister of Environment issues a statement on whether the proposed project is likely to cause significant adverse environmental effects, taking into account the mitigation measures and programs. If the decision is that there would not be significant adverse environmental effects, CNSC may proceed with the licensing process. Successful completion of the EA process includes several aspects, as follows: Presentation of detailed plans for all aspects of the proposed mine development; Consideration of concerns with a new mine development from stakeholders in the Elliot Lake area, First Nations peoples, and interest groups; Demonstrations of very low ecological and human health risks, including the assurance that the mine will implement rigorous environmental management standards; and On closure, assurance that the facilities will require minimal continuous care and maintenance. The sequential steps in the EA process are as follows: Completion of Project Optimization Assessments Collection of Baseline Environmental Data and Information Preparation of a Project Description Preparation and Submission of Applications to CEAA and CNSC Establishment of the EA Scope and Appointment of a Panel EA Scope Public Hearings Issuance of EA Guidelines EA Preparation by the Proponent EA Submission, Regulatory Review and Proponent Response EA Panel and Public Review Panel Recommendation to Minister Ministerial Decision In preparation for an application to CNSC for a licence to develop the Eco Ridge Mine, studies were initiated in 2007, continuing into 2008 and beyond to identify and collect Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-7 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com site-specific environmental data on the proposed project site. These studies were designed to meet the initial needs for a pre-project baseline study which will be a requirement of the EA needed to support the application. INFORMATION REQUIRED FOR THE PREPARATION OF AN ENVIRONMENTAL ASSESSMENT BASELINE STUDIES Formal requirements for baseline studies will be specified in the EA Guidelines that will be issued by CNSC. However, based on past experience and current trends, reasonable assumptions on the anticipated requirements for the baseline studies can be made. Four major components may be considered: 1. 2. 3. 4. Assessment of Biophysical Environment; Socio-Economic Survey; Decommissioning and Closure; and Preliminary Risk Assessment The baseline environmental studies conducted in 2007 and 2008 provided a preliminary characterization of current conditions over an area that may be influenced by the proposed mine and waste management facilities that are planned to be established on the property. Building off the findings of the initial baseline studies, Pele Mountain is in the process of developing a comprehensive environmental site characterization program that will be initiated during the summer of 2012. Additional baseline monitoring needs may also arise from the eventual EA guidelines. Contact should be made with CNSC staff early in the next evaluation stage to solicit guidance on the preparatory work for the licensing application. Significant regional baseline information has been accumulated (much is publicly available) and will be utilized during the preparation of an EA. For example, there are significant reports from various investigations sponsored by the former Elliot Lake mine operators as well as detailed field studies under the National Uranium Tailings Program. The Ontario Ministry of the Environment also has a data bank of area monitoring information. Access to proprietary information and data (e.g., Rio Algom (BHP Billiton) and Denison) would be subject to negotiation. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-8 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com GEOGRAPHIC MAPPING Geographic mapping has been completed from existing 1:50,000 topographic maps supplemented with detailed, excellent quality topographic mapping from aerial photography conducted in 2007. Authorization was obtained by Pele Mountain for Expert Access on-line to all the MNR mapping databases. Project maps have been prepared showing all the existing salient natural and man-made features and these are filed in hard copy and electronically. As a guide for upcoming baseline characterization work, maps have been prepared showing the Site, Local, and Regional Study Areas. These study areas reflect the different potential zones of influence that the Project may have on the environment, including the potential for cumulative effects. It is recommended that Pele Mountain request that the CNSC apply the same study areas in the EA Guidelines for the Project. An initial estimate suggests that the boundaries of the potentially affected area encompass the Serpent River Watershed from the closed Quirke and Panel mine sites in the north, Dunlop and Elliot lakes in the west, and Pecors Lake in the east (the city of Elliot Lake boundary), down to Lake Huron in the south – including the Serpent River First Nation. CLIMATE AND METEOROLOGY Existing climate information will be summarized and a gap analysis completed. Recent climate and meteorology data are extensive, with the data collected by the weather service of Environment Canada Elliot Lake airport station and by previous mine operators. An ongoing gap analysis will indicate the requirements for additional data acquisition to complete an outline of the local climate and detailed analyses for the proposed development. It is not expected that a dedicated weather station on the Eco Ridge Mine property will be required for the EA. Key elements of climate and meteorology include: Wind speed and direction Atmospheric stability Mixing layer heights Precipitation and evaporation Temperature and solar radiation A preliminary analysis of the effects of global climate change in the near term (life of the Project) and long term (100 years) will be required to determine what additional studies Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-9 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com may be required to complete an outline of the effects of climate change on the proposed Project. This is a requirement of current EAs. GEOLOGY Surface geology can be summarized from existing data and from surface surveys. Surface geology surveys will outline rock outcrops and types, solids and glacial-remnant produced features such as eskers and moraines. Bedrock geology is well documented in existing reports as well as detailed on-site investigations conducted by Pele Mountain. The mineralogy of the property has also been investigated extensively as part of site characterization studies. HYDROLOGY The hydrology of the Serpent River Watershed is well understood and documented. The property has been surveyed to describe watersheds within the property. Further investigations will be required to determine the mean and max/min stream flow rates and the flows following a Probable Maximum Precipitation (PMP) event will have to be calculated. Historically, the PMP for Elliot Lake has been estimated to be 42 cm of rain in 12 hours. This estimate may be revised when considering the predicted effects of climate change during the proposed operational period for the Project. Recently, Pele Mountain has carried out extensive site surveys of the property and produced detailed hydrologic mapping showing all streams, lakes and ponds within the property boundary. Descriptions of the area, each lake and stream are documented together with a significant database of site photographs. Bathymetric lake surveys were also completed in 2007 for the following lakes: SSM 223 (Pear Lake), Pardee, Stinson, Kings and small ponds 8 and 9. A detailed aquatic survey was completed for Rioux Lake in 2008. The aquatic survey was conducted by the Fresh Water Ecology Unit, a branch of the Ministry of Natural Resources (MNR) affiliated with Laurentian University. Significant historical information has been obtained for the following lakes in the vicinity of the Project: Tees, McCarthy, McCabe, Elephant, Flying Goose, Hough, and May. Throughout 2008, regular inspections were made of streams, including sampling and Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-10 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com flow measurements. No fixed stream flow monitoring has been installed to date - data is from occasional site visits. As the Eco Ridge property is sited primarily on the top of an escarpment, there are no major rivers or streams discharging from the property. In fact, all streams on the property have been found to be intermittent. Water bodies and streams in the Project area were identified during initial site characterization studies. Principal properties and potential chemicals of concern have also been identified. For all the sampling locations, key data has been documented including locations with photos. Sampling and analytical protocols have been developed and used. Surface water samples for key locations were obtained routinely through the summer of 2008, with 79 samples sent to accredited laboratories for analysis including full metal scans and some radiological analysis. A similar but more comprehensive program is scheduled for the summer of 2012. HYDROGEOLOGY The extensive studies carried out for the earlier Elliot Lake mines clearly indicated that the bedrock in the region was relatively impervious and that groundwater movement was primarily controlled by and confined to the overburden or structural features. SRK Consulting (SRK) completed a Preliminary Groundwater Scoping Study from June 2008 to November 2008. The study concluded that the permeability of the Huronian Metasediments (quartzite and quartz pebble conglomerate) was very low – typical of previous experiences in the Elliot Lake area. The study also concluded that the dewatered mine was likely to provide a regional hydraulic capture while in operation. This would contain potential contamination. Once pumping ceased and the mine began to flood, the groundwater regime would return to pre-mining conditions. SRK recommended that pre-mine groundwater monitoring of horizontal and vertical gradients, as well as water chemistry, was needed to increase the confidence of contaminant modelling. Further structural and hydrogeology testing, analysis, and modelling would be required as the Project advances. These additional studies would be integrated into a comprehensive baseline characterization program for the site. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-11 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com AQUATIC BASELINE STUDY BASELINE AQUATIC ECOSYSTEM Eco Ridge Mine site specific environmental studies were initiated in 2007 through Blythe and Associates who carried out aquatic characterization studies. The assessment encompassed identification of the Project watershed and adjacent areas, definition of potentially affected water bodies, as well as water bodies that did and would represent unaffected, background conditions. Existing data for these lakes, streams, ponds, and wetlands was verified and supplemented with additional bathymetry and water column characteristics. Aquatic and shoreline vegetation was recorded. Water, sediment, benthos, and fish were identified through specific sampling and monitoring. The study concluded that the Project would be sited within a well understood Northern Ontario ecosystem with no unusual or remarkable features and that further research was required to assess in more detail, for environments which would be disturbed (proposed locations of mine sites, mine infrastructure, and access roads), what mitigation measures would be appropriate and the scope of the rehabilitation measures required upon closure. Further information on the surveys is provided in the following sections. AQUATIC VEGETATION A baseline survey of aquatic macrophytes (plants in the water) was conducted and reported in the Aquatic Ecosystems Characterization Report submitted by Blythe and Associates in July 2008. The results of this survey indicated that the aquatic vegetation was unremarkable and reflective of typical undeveloped forested lands in much of northern Ontario. FISH The Aquatic Ecosystems Characterization Report indicates that none of the aquatic ecosystems within the Pele Mountain property sustain populations of rare fish as designated by the federal Species at Risk Act, the provincial Endangered Species Act 2007, or the natural heritages protection component of the Ontario Planning Act. Information on fish in lakes and streams outside the Pele Mountain property (e.g., Pecors, King, and McCabe lakes) will be derived from historical information. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-12 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com BENTHIC INVERTEBRATES Benthic invertebrate sampling was conducted in all lakes surveyed in the Aquatic Ecosystems Characterization Report (July 2008) by Anishinawbek/Ontario Fisheries Resource Centre and the samples were analyzed by the Cooperative Freshwater Ecology Unit at Laurentian University in Sudbury, Ontario. The results of the benthic invertebrate survey indicate that the benthic invertebrate populations found within the various inlet and outlet stream courses of the Pele Mountain property are comparable to those values found in other locations in this part of Northern Ontario. A comprehensive aquatic baseline characterization program is currently being developed for the Eco Ridge property. The additional aquatic studies are anticipated to include further water quality sampling, benthic and fish inventory surveys, habitat mapping and sediment sampling. The aquatic baseline study is also expected to include measurements of flow rates from the streams to assist with the characterization of local hydrology and preparation of an overall water balance for the site. BASELINE TERRESTRIAL ECOSYSTEM A preliminary site-specific study of the terrestrial environment was also conducted in 2007 by Blythe and Associates. The scope of the study included soils and topography, surface drainage, climate, land use, vegetation, wetlands, birds, and animals. The study has been supplemented with additional site inspections conducted in 2008. This information, comprising field notes, sketches, and photographs, has been documented and filed. Regional data on vegetation has been obtained and filed. Two wildlife species at risk are known to occur near the Pele Mountain property, the Blanding’s turtle and the peregrine falcon. No peregrine falcons have been observed on the property. One Blanding’s turtle has been observed near Highway 108, approximately five kilometres to the southwest of the main area of development for the Eco Ridge Mine. The preliminary terrestrial study concluded that the Project would be sited within a well understood Northern Ontario ecosystem with no unusual or remarkable features. It was also concluded, however, that additional characterization studies would need to be performed once a preliminary design concept for the mine had been developed (e.g., proposed locations of mining operations, tailings management areas, mine infrastructure Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-13 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com and access roads). The conceptual design of the Project is now sufficiently advanced that these additional terrestrial investigations can be initiated. A comprehensive terrestrial baseline characterization program is currently being developed and is scheduled for implementation during the second half of 2012. BASELINE SOILS STUDY Baseline soils sampling will need to be conducted in order to establish background levels of metals and radionuclides within soils that have the potential to be affected by the mining operation. This requirement will be addressed during 2012 site characterization studies. BASELINE AIR MONITORING A baseline air quality monitoring program will be implemented to confirm predevelopment concentrations of relevant parameters. At a minimum, air sampling will evaluate the following: Total suspended particulate (TSP); Particulate less than 10 µm in diameter (PM10, or inhalable particulate); and Particulate less than 2.5 µm in diameter (PM2.5, or respirable particulate). Additional monitoring may also be conducted to determine baseline concentrations of potential contaminants (e.g., metals in particulate matter). The air quality monitoring program will be conducted during multiple seasonally representative periods. Based on preliminary planning, monitoring stations will be established at the following locations: Elliot Lake Municipal Airport; Pele Mountain Elliot Lake Uranium Project site; and The City of Elliot Lake. BASELINE NOISE MONITORING Minimal baseline noise monitoring is needed. Other than noise generated by the use of the all-terrain vehicle (ATV) and snowmobile trails and hiking trails, noise levels on the Project property are expected to represent general background conditions. This will be confirmed through the implementation of a cursory noise monitoring program. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-14 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com RADIOLOGICAL MONITORING Baseline radiological monitoring of the site is required. Based on preliminary planning, it is expected that this program will include: A scanning gamma radiation survey to determine the variability in gamma radiation levels on the site; A radon-in-air / thermoluminescent dosimeter (TLD) sampling program; and Soil sampling for radionuclides and other elements. DECOMMISSIONING AND CLOSURE PLANNING After removing all underground equipment, Pele Mountain will permanently close the decline ramps and all other mine openings in accordance with regulatory requirements. If there is an outflow from any of the mine openings it may require treatment to meet appropriate water quality standards until it can be demonstrated that adverse impacts to the environment are not occurring. Following closure of the mine and removal of surface infrastructure (the processing plant, roads, etc.) evidence of the mine will be limited primarily to the TDF. Preliminary planning anticipates that the decommissioning of the facility will involve the following: Installation of a soil cover over tailings to minimize infiltration and prevent tailings erosion; Decommissioning of containment dams to drain the tailings pond; Removal of the emergency tailings pond and disposal underground; and Revegetation of soil covers. The closure plan for the TDF will minimize the need for long-term care and maintenance, including requirements for effluent treatment. However, drainage from the facility may require treatment during a transition period following closure. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-15 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com ENVIRONMENTAL RISK ASSESSMENTS In order to identify all potential environmental risks pertaining to the Project, Human Health and Ecological Risk Assessments will need to be conducted during the EA process. Taking into consideration the extensive documented experience in the Elliot Lake mining camp with uranium mine operations and decommissioning, it is expected that all significant risks can be effectively managed. PERMITTING AND ENVIRONMENTAL ASSESSMENT COSTS As indicated above, once the Project has been registered, and it is decided that the EA will continue as a comprehensive study, the CNSC will delegate the completion of the technical studies and preparation of the EA to the proponent. The proponent must then provide all of the information necessary to satisfy the approved EA Guidelines. The proponent’s Study Report will be reviewed and analyzed by technical specialists at the CNSC and other federal authorities. The costs associated with the preparation of the EA, for hearings, and for permitting are not known in detail at this time, however, these costs could be in the range of $7 million to $12 million. ENVIRONMENTAL MANAGEMENT STRATEGIES TAILINGS MANAGEMENT A preliminary tailings management design concept for the Eco Ridge Mine was prepared by Golder Associates in 2012. The design is based on assumed LOM production of 34 Mt and a total estimated tailings volume of 24 million cubic metres. Of this total, roughly half of the tailings will be returned to the mine as cemented paste backfill and the remainder will be disposed in a TDF on surface. The following summarizes environmental considerations that were incorporated into the preliminary TDF design: No impact on the Stinson Lake watershed which is located north of the TDF and discharges into Buckles Creek – receptor of effluent from Nordic Mine. Minimize water discharge into the environment. Reduce the collecting watershed by diverting clean water runoff away from the site infrastructure. Collect mine and process plant drainage. Contain tailings solids and pore-water during operations and following closure. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-16 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Minimize groundwater impact. Minimize air borne release of tailings. Treat tailings pond effluent for radium and acidity, if required, to meet appropriate water quality standards during operation and in the transition period to closure. Control radiological releases (radon gas, gamma radiation, radium) in accordance with the As Low As Reasonably Achievable (ALARA) principle. Reduce the potential for effluent treatment for the long-term. TDF to perform in perpetuity. Additional testing is required to determine the environmental and geotechnical properties of tailings from the Eco Ridge Mine. In particular, studies are required to verify the acidproducing potential of the tailings and any implications on TDF designs and water management. As part of a broader program of laboratory studies, Pele Mountain is currently developing a work plan to characterize the environmental properties of tailings. It is currently expected that this work will be performed on tailings produced from pilot scale mineral processing tests that are planned for 2012. WATER MANAGEMENT Specific requirements for the management of water have yet to be developed. Water management plans are currently based on the following principles: Maximize use of mine water and recycle of process water. Minimize contamination of fresh water, including storm water. Treat, monitor, and discharge water to the highest level of water quality. Water treatment will use proven technology to neutralize acidity and remove suspended solids, heavy metals, uranium and radium-226 to below established discharge standards. Treated water will be held in monitoring ponds before discharge. Sludge disposal during operations is assumed to be disposal underground as backfill in mined-out areas of the mine. An extensive water, sediment, and biology monitoring program will be established. This monitoring program will ideally include local peer review. WASTE MATERIALS Waste materials will be recycled and managed according to best practices. It is planned that radioactively contaminated materials will be disposed of in a secure landfill on site, Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-17 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com or in long-term storage underground. Such disposal would be in conformance with requirements stipulated by CNSC and other regulators. AIR EMISSIONS Principal sources of air emissions include mine ventilation (e.g., radon) and activities related to the movement/management of ore and tailings on surface (e.g., particulate matter). There is also a potential that the processing facility will produce emissions to air (e.g., from the “acid baking” of ore). The potential effects of these emission sources will be monitored at the facility boundaries and in the surrounding area. SOILS Soils near mine facilities may be subject to fallout from airborne emissions. Monitoring programs will be required to identify any changes from baseline conditions. OCCUPATIONAL HEALTH AND SAFETY Health and safety requirements in Ontario mines are regulated under the Occupational Health and Safety Act (OHSA). The philosophy behind the law is known as the “internal responsibility system”. Although this term is not mentioned in any legislation, the Ministry of Labour’s guide to the act makes it clear that the government expects employers and workers to cooperate to control occupational health and safety hazards. Pele Mountain developed an Occupational, Safety, Health and Environmental Policy dated May 2007. Together with RPA, Pele Mountain developed the “Best Management Practices and Exploration Guidelines for the Pele Mountain Resources Elliot Lake Project”, which is specific to the Eco Ridge Project and uranium exploration. Environment and health and safety inspections have been carried out on the Project by Pele Mountain and SENES Consultants Limited. Several gamma and radon surveys have been conducted at Pele Mountain’s core logging and storage facility in Elliot Lake and at an active drill site by Denison Environmental Services. Denison reported that the radiation levels were very low and there were no health or safety concerns. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-18 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com LEGISLATION Operations at the Project will have to comply with: a. The Occupational Health and Safety Act and Regulations for Mines and Mining Plants. R.S.O. 1990 b. The Nuclear Safety and Control Act, Uranium Mines and Mills Regulations (SOR/2000-206) HEALTH AND SAFETY RELATED TO URANIUM MINING AND PROCESSING RADON GAS The primary health concern with uranium mining is exposure to radiation/radioactivity. Historic studies have concluded that radon gas exposure in high concentrations causes lung cancer. These studies have been updated (CNSC, 2004) and the implementation of stringent health and safety standards have resulted in significantly lowering the radon level in today’s uranium mines. Today’s uranium miners are exposed to very low levels of radon and there is a very low risk of lung cancer from occupational exposure to radon. The study has found that uranium workers and Canadian citizens in general face a comparable risk of getting lung cancer from exposure to radon gas. Radon levels are now lower in mines due to the increased awareness of the link between high levels of radon and lung cancer. The use of modern ventilation systems and other measures diminish these risks. Modern health and safety regulations keep the doses in mines so low that exposure no longer poses a significant concern. CNSC (2003) has issued a regulatory guide to ventilation requirements for uranium mines and mills (G-221, June 2003) based on the Uranium Mines and Mills Regulations. The proponent for a licence to construct a uranium mine and processing facility is required to submit information on: The proposed ventilation and dust control methods, The proposed equipment for controlling the air quality, and The proposed level of effectiveness of and the inspection schedule for the ventilation and dust control system. CNSC will review any proposed ventilation systems or activities against regulatory requirements. The proposal will also need to outline a quality assurance program, the results from process hazard analyses, and a proposed code of practice. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-19 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com As part of any ongoing feasibility studies, Pele Mountain will need to develop a radiation protection policy and procedures. The procedures and systems will need to address dust control, radiation control, and hygiene standards for workers handling uranium oxide concentrate. HEALTH AND SAFETY PROGRAMS To meet or exceed legislation, Pele Mountain will use OHSAS 18001 as the basis for its Health and Safety Management Systems. Included in these management systems will be: 1. Development of an Occupational Health and Safety Policy for the Elliot Lake operation. The policy shall: a. Be appropriate to the nature and scale of the organization’s Health and Safety risks; b. Include a commitment to continual improvement; c. Include a commitment to comply with current applicable Health and Safety legislation; d. Be documented, implemented and maintained; e. Be communicated to all employees with the intent that employees, associates and contractors are made aware of their Health and Safety obligations; f. Be available to interested parties; g. Be reviewed periodically to ensure that the policy remains relevant and appropriate to the organization. 2. Assignment of Health and Safety responsibilities. Each individual must be fully aware of their responsibilities and held accountable. Health and Safety activities will be established, communicated and performance measured. 3. Orientation and Training. Ensures staff has the necessary knowledge and skills to perform their duties safely and efficiently. 4. Risk evaluation. Using risk analysis matrices focuses management attention on high risk activities. 5. Hazard Assessment. A formal methodology for identification, evaluation, and control of hazards. 6. Planned inspections. Systematic examinations of workplaces, materials, and practices. 7. Safe Work Practices and Best Practice. Includes occupation inventory, task analysis and procedures, safety manuals, housekeeping, personal protective equipment, etc. 8. Emergency Preparedness. Contain and control emergencies including fire, property loss, medical evacuation, spills, site and personnel security, and environmental damages. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-20 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 9. Incident Reporting. Systems and procedures for the reporting of incidents, accidents, property loss, and development of records. 10. Investigations. Formalized investigations of any undesired Responsibilities, accountabilities, and record keeping defined. event. 11. HSE Communications Primarily internal communication of Health and Safety issues and concerns. Safety meetings, huddles, tool box meetings. 12. Occupational Health. Travel safety, medical and security issues, and corporate health initiatives. 13. Contractor Health and Safety. Contractor qualifications, Health and Safety responsibilities, and legislative requirements. 14. Engineering and Control Systems. Purchase, modification, and installation of designs, equipment, and systems. Management of change procedures. 15. Records. Requirements, systems, and access to Health and Safety records and information. 16. Health and Safety Management System Evaluation. Periodic evaluations and audits of management performance and Health and Safety systems. 17. Corrective Action and Continuous Improvement. Guidelines for non-compliance with Health and Safety standards. Correction of deficiencies. Action plans for Health and Safety improvement. WORKER PROTECTION To comply with the Uranium Mines and Mills Regulations, Pele Mountain will develop the following information in relation to worker protection: The effects on the health and safety of persons that may result from the activity to be licensed, and the measures that will be taken to prevent or mitigate those effects. The proposed program for selecting, using, and maintaining personal protective equipment. The proposed worker health and safety policies and programs. The proposed positions for and qualifications and responsibilities of radiation protection workers. The proposed training program for workers. The proposed measures to control the spread of any radioactive contamination. The proposed ventilation and dust control methods and equipment for controlling air quality. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-21 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com The proposed level of effectiveness of and inspection schedule for the ventilation and dust control systems. In addition, Codes of Practice will be required that include action levels for specific radiation exposures that identify the action to be taken and reporting procedure. The Radiation Protection Regulations of the Nuclear Safety and Control Act regulates the following: Obligation of Licensees and Workers Radiation Dose Limits Dosimetry Labelling and Signs Records to be kept Radiation Protection programs are required to keep exposure to radon progeny as low as is reasonably achievable. Dose limits for exposure to radon progeny are regulated under the Radiation Protection Regulations. Management standards, worker training, adequate ventilation, close monitoring, and extensive audits will ensure compliance with the Act. COMMUNITY RELATIONS The EA process will require extensive public consultations. For example, it is expected that Aboriginal groups (the Serpent River First Nation in particular), non-governmental organizations, and local citizens from the City of Elliot Lake will have questions concerning the Project. These questions may include: The impact of the Project on tourism and outdoor recreational activities in the area. There are ATV and snowmobile trails on the Project property and local residents use the area for casual recreational purposes. The impact of the Project on water quality, particularly within the Serpent River and other downstream water bodies where fishing occurs. Management of solid and liquid wastes. Management of the Tailings Disposal Facility will be an important concern, for both the operational and post-closure periods. Long term site remediation and closure. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-22 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Noise and traffic affecting other land uses (e.g., the local golf course which is adjacent to the Project property). Dispersion of airborne contaminants. Concerns about nuclear power in general. The loss of habitat or access due to construction of site infrastructure. Extensive, proactive, and meaningful consultation will assist in addressing public concerns. However, it should be understood that certain “public interest” groups are committed to oppose uranium mining and nuclear power under any circumstances and there is a possibility that such groups can mobilize substantial public support. CITY OF ELLIOT LAKE ELLIOT LAKE ECONOMIC DEVELOPMENT STRATEGY The City of Elliot Lake was originally developed for the sole purpose of supporting uranium mining and processing and remained a single-resource community until the early 1990s when the mines closed. The City of Elliot Lake is proud of that mining heritage. During the period when the uranium mines were operating, Elliot Lake’s population reached 25,000. Since the closure of the mines, the City has developed alternative economic plans. Most notably, the highly successful “Retirement Living Program” was initiated to attract retirees to rent or buy vacant housing units. By attracting more than 4,000 new residents, the program has enabled the city to enjoy a market position as a favourable retirement destination. The influx of retirees has stabilized the population and allowed the city to develop its tourism and recreational infrastructure. It has also resulted in new residents that are less familiar and perhaps less sympathetic with the mining heritage of Elliot Lake. Cottage lot development has been another local initiative that has enjoyed a measure of economic success. After several years of negotiations with the Ministry of Natural Resources, Elliot Lake was able to get approvals for a potential 400 lots on ten lakes north of the city. In 2004, 62 waterfront lots became available on Dunlop Lake and Quirke Lake. Many of the buyers are retirees who have built permanent homes on the waterfront lots. None of the developed cottage lots are located on the Eco Ridge Mine property. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-23 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com These two initiatives coupled with the development of business opportunities are described as the three “pillars” of the local economy. The mission statement of the City of Elliot Lake is “to continue the growth and cultural diversity of Elliot Lake as a modern, well-connected community with business opportunities, active retirement, and all-season tourism, in a pristine natural environment.” Pele Mountain has communicated with the incumbent Mayor, members of the City Council, business leaders, and citizens on numerous occasions to keep them informed of Pele Mountain’s ongoing exploration program in the area and future plans. The discussions to date have been open and productive. NORTH SHORE COMMUNITIES The Township of the North Shore along Highway 17 (Sprague, Algoma Mills, and Serpent River Village) has a population of 549 residents, based on the 2006 census. These communities benefited economically from the mining industry and there is considerable interest in renewed drilling and exploration activity in the area. There was a considerable negative impact on the communities when the mines shut down. The economy of the communities along the North Shore is largely dependent on the tourism industry. Lake Lauzon and the North Channel are popular swimming, fishing, and boating areas. ABORIGINAL INTERESTS The Serpent River First Nation is located in the southern portion of the Serpent River drainage basin near the outlet of the river into Lake Huron. The Anishnawbek First Nations were among the original inhabitants of the region. In 1850, the Anishnawbek First Nations signed the Robinson-Huron Treaty with the Crown, creating Indian reserves, including the Serpent River First Nation Reserve (the Reserve) of 10,913 ha, within the Serpent River Watershed. The claims held by Pele Mountain are in the area covered by the treaty and the treaty gives First Nations persons “full and free privilege to hunt over the territory – and to fish in the waters thereof” (traditional land Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-24 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com use). Under the treaty, all mining rights were retained by the Crown. Pele Mountain acquired its exclusive interest in the mining rights from the Crown pursuant to the provisions of the Ontario Mining Act. The Serpent River First Nation has been directly affected by several aspects of the historic uranium mining activities at Elliot Lake. Examples of the issues that have affected the Serpent River First Nation include: 1. The construction of a sulphuric acid plant on the Reserve in 1955, which was closed in 1962 without adequate decommissioning of the site. It was not until 1989 that the site was declared a hazard and was decommissioned. 2. Concerns about the health of the Serpent River Watershed were raised following the recognition that the watershed was being damaged by the uranium mining operations. The Serpent River First Nation became involved in the hearings with the provincial Environmental Assessment Board to prevent the mining companies from causing further damage to the Serpent River Watershed. They claimed that they had been forced to bear the environmental costs of the development of the uranium mining industry, and in their opinion, the mining companies should reimburse their costs. The hearings lasted three years and the Board noted in the final report issued in 1979 that lack of communication between the mining companies and the Reserve was a problem, stating: “A considerable portion of the band’s concerns result from a general lack of communication… the mining companies did not make any serious attempt to find out what the band’s concerns were with respect to the expansion and to address these in their submissions to the Board.” 3. The Serpent River First Nation actively participated in the scoping sessions held on the Reserve in December 1993 by the Federal Environmental Assessment and Review Office (FEARO) Panel on the decommissioning of the tailings. The band raised concerns that there was no proposal to restore the lands for their use or any discussion on the social impact of the loss of historical hunting and camp areas to the tailings managements facilities (TMAs). The mining legacy has been a continuous issue for the people of the Serpent River First Nation. Concerns related to the loss of access to their traditional lands because of the TMAs and the health of the Serpent River Watershed which suffered damage during the early days of mining activity before the damage was recognized and preventive methods were developed and implemented. Effective communications will be important in order to address a wide range of concerns relevant to all potentially affected Aboriginal peoples. The Crown will also have a role to play in the communication and consultation process. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-25 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com ARCHAEOLOGICAL ASSESSMENT Archaeological investigations, specific to the Project property, are required. Detailed archaeological investigations have been conducted in the Serpent River basin in the past. Significant sites have been identified, but details remain confidential in order to protect the integrity of the locations. Archaeological Services Inc. (ASI) was contracted by Pele Mountain to conduct a Stage 1 archaeological assessment of the Proposed Eco Ridge Mine. The assessment was completed in August 2008. During the course of the assessment one archaeological site, the Kings Lake site, was identified. The Stage 1 archaeological assessment identified site potential within the undisturbed areas of this study area and recommends that a Stage 2 assessment be conducted in areas of archaeological potential prior to any land disturbance. COMMUNITY CONSULTATIONS Consideration of licence applications for new uranium mines and mills by CNSC follows a public hearing process. Typically, public hearings take place over two days within a ninety-day period following public notice. In addition to the formal public hearings, CNSC encourages licence applicants to undertake pre-application consultation activities regarding their potential plans for new uranium mines and mills. A preliminary project communication plan has been developed by Pele Mountain to ensure accurate and timely dissemination of project information. The communication plan has led to friendly, open, and productive dialogue between Pele Mountain and both the Serpent River First Nation and the City of Elliot Lake. Notwithstanding this early and positive progress, a more robust public consultation and engagement program will be required as the Project advances through the EA and regulatory approvals process. Pele Mountain has initiated the preparation of a strategy for such a program. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 20-26 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 21 CAPITAL AND OPERATING COSTS CAPITAL COSTS The total Project capital costs are presented in Table 21-1. TABLE 21-1 OVERALL CAPITAL COST ESTIMATE Pele Mountain Resources Inc. – Eco Ridge Mine Project Component Mine Processing Initial (C$ 000) 61,185 Sustaining (C$ 000) 25,235 TOTAL (C$ 000) 86,420 229,806 - 229,806 25,000 10,000 35,000 Indirects 114,561 - 114,561 Tailings 24,685 22,935 47,620 Mine & Process Sustaining Capital - 24,000 24,000 Site Decommissioning & Monitoring - 22,000 22,000 Contingency – Process 89,210 - 89,210 Contingency – Mining & Other 18,396 - 18,396 562,843 104,170 667,013 Infrastructure Total Note: This table does not include costs of $75.9 million for ore mining during the construction period. Those costs are included in the cash flow as operating costs. MINE CAPITAL COSTS Mine capital costs for equipment and infrastructure purchases are derived from a combination of supplier quotes and cost reference guides for similar projects. Ramp development (in ore) is estimated on an operating cost basis. Costs are presented in 2011 Canadian dollars and do not include taxes and/or duties. Table 21-2 summarizes total capital expenditure on mining for the LOM. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 21-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 21-2 MINE CAPITAL COST ESTIMATE Pele Mountain Resources Inc. – Eco Ridge Mine Project Component Initial Capital (C$ 000) Sustaining Capital (C$ 000) Total Capital (C$ 000) Ore Mining Yr -1, -2 operating cost 75,856 - 75,856 Mine Capital Mine Portal 1,000 - 1,000 32,028 12,471 44,500 Pastefill Distribution 2,397 2,801 5,197 Mine Infrastructure 25,760 9,963 35,723 Mine Capital 61,185 25,235 86,420 Mobile Equipment PROCESS CAPITAL COST The capital costs for the proposed Eco Ridge plant were estimated by SNC-Lavalin and include estimates for site development, the acid baking plant, the uranium extraction plant, the Yttrium & REE extraction plant and a water treatment plant. The overall cost of the acid baking plant, the uranium plant and the Y & REE plant, not including indirect costs, is C$165 million, C$34 million, and C$20 million, respectively. Other process costs include C$7.3 million for site development, C$3 million for a water treatment plant. The capital cost estimate is an order of magnitude estimate to a level of accuracy of approximately plus or minus 35%. Details of the initial process capital cost estimate are provided in Table 21-3. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 21-2 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 21-3 INITIAL PROCESS CAPITAL COST ESTIMATE Pele Mountain Resources Inc. – Eco Ridge Mine Project Component Capital Cost (C$ 000) Direct Costs: Site Development 7,300 Acid Baking Plant 165,366 Uranium Extraction Plant 33,926 Y & REE Plant 20,215 Water Treatment Plant Sub-total Direct Costs 3,000 229,806 Indirect Costs: Construction Indirects 10,797 EPCM 45,961 Freight 5,453 Spare Parts 5,350 Contingency 89,210 Sub-total Indirect Costs Total Initial Capital Costs 156,772 386,600 The process capital cost estimate that was completed by SNC-Lavalin excludes: Ancillary buildings and services, including any mine related facilities, camp and general admission All off-site costs including services to the site All yard utilities All utility sources such as water supply, water treatment, electrical substation, sewage disposal Any secondary effluent treatment facilities that may be required Any abnormal soil conditions which result in special foundations or piling Construction camp or catering Tailings disposal or pipelines Rock excavation All taxes and duties First fills and initial product inventory All Owner’s costs Project interest and financing costs during construction Project insurance Working capital Cost of this and future study work Disposal/clean-up of existing (if any) hazardous materials Mitigation for contaminated materials Operations mobile equipment Commissioning and commissioning assistance Training of operations personnel Land costs Permits and cost of permitting Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 21-3 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Environmental studies, investigations and permits License and Royalty fees Environmental/ecological/cultural considerations incorporated in the design Cost changes due to currency fluctuation Escalation beyond 3rd quarter 2010 Force majeure issues Warehouse inventories other than spares identified Future scope changes Sustaining and closure costs other than those RPA notes that some of these exclusions from SNC-Lavalin’s estimate have been accounted for, as described elsewhere in this report. OPERATING COSTS The total operating costs are summarized in Table 21-4. TABLE 21-4 TOTAL OPERATING COST ESTIMATE Pele Mountain Resources Inc. – Eco Ridge Mine Project Component C$/t Mining 41.52 Processing 26.31 G&A 3.50 Total 71.33 MINE OPERATING COSTS Mine operating costs for the Project have been estimated from first principles and were based on equipment productivity, operating hours, and operating cost per hour. Operating costs per hour are based on RPA’s in house data base. Productivities were based on equipment performance. Labour costs were based on manning the equipment and Northern Ontario negotiable contract wages. Salaries have been estimated based on a 2010 PricewaterhouseCoopers annual salary survey. The third quartile salary figure was used to ensure that the employees will be encouraged to join and remain once employed. An additional 30% was added to cover payroll burdens. The hourly rates were based on Sudbury camp collective bargaining agreements for the periods 2008-2011. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 21-4 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Material costs were based on supplies and budgetary quotes. Mine operating costs average shown in Table 21-5. TABLE 21-5 MINE OPERATING COST ESTIMATE Pele Mountain Resources Inc. – Eco Ridge Mine Project Component Labour Equipment Repairs Material Supplies Mining Cost Subtotal Indirect Mining Costs Haulage to surface Surface stockpile rehandle Power consumption - Main Fans & pumps Mine Heating (propane) Production sampling costs Delineation drilling costs Health & safety Indirect Cost Sub Total Total mining Opex Pastefill Costs Labour Material & Equipment Pastefill Sub Total Total Total Cost (C$ millions) 252.2 346.2 492.2 1,090.6 6.82 9.36 13.30 29.48 92.5 46.2 92.5 57.3 18.5 14.0 0.7 321.7 1,412.3 2.50 1.25 2.50 1.55 0.50 0.38 0.02 8.70 38.18 15.9 107.7 123.6 0.43 2.91 3.34 1,536.0 41.52 C$/t PROCESS OPERATING COSTS Process operating costs for the Project were estimated by SNC-Lavalin. The labour costs are estimated from the current labour market rates in northern Ontario and an additional 45% is added to cover the costs of fringe benefits. Power costs are $0.07 per kilowatt hour. Reagent consumption is estimated using the preliminary mass balance and stoichiometry; the reagent unit costs were obtained from various sources, including published information, historical data, and in-house information. The annual consumption of sulphuric acid has been calculated based on an acid:concentrate ratio of 0.3:1 and the price estimated to be $90/t delivered by truck. Maintenance costs are estimated using factors relating to the capital cost estimate and associated maintenance Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 21-5 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com labour costs. The operating cost estimate is split into costs to operate the acid baking plant, the uranium plant, and the Y & REE plant as shown in Table 21-6. TABLE 21-6 PROCESS OPERATING COST ESTIMATE Pele Mountain Resources Inc. – Eco Ridge Mine Project Area Labour Staff Acid Baking with Flotation Staff USX Staff Y&REE Labour Acid Baking Labour USX Labour Y&REE $/year $6,816,000 $587,500 $587,500 $587,500 $1,684,500 $1,684,500 $1,684,500 Supplies Reagents Acid Baking Plant Reagents USX Plant Reagents Y&REE Plant Tailings $58,651,300 $34,624,000 $9,271,020 $13,576,200 $1,180,000 Power Acid Baking Plant USX Plant Y&REE Plant Reagents USX Reagents Y&REE $12,286,100 $10,510,000 $1,052,700 $453,000 $114,400 $156,000 Maintenance Acid Baking Plant Uranium Extraction Plant Yttrium & REE Plant Reagents Acid Baking Reagents USX Reagents Y&REE General Acid Baking General USX General Y&REE Piping/Electrical/Instrumentation Acid Baking Piping/Electrical/Instrumentation USX Piping/Electrical/Instrumentation Y&REE Labour Acid Baking Labour USX Labour Y&REE $/t $2.13 $0.18 $0.18 $0.18 $0.53 $0.53 $0.53 $18.33 $10.82 $2.90 $4.24 $0.37 $3.84 $3.28 $0.33 $0.14 $0.04 $0.05 $6,434,800 $2,623,947 $450,135 $290,817 $131,467 $45,008 $6,340 $22,229 $24,449 $20,354 $557,629 $121,629 $65,318 $691,800 $691,800 $691,800 TOTAL OPEX $84,189,000 $2.01 $0.82 $0.14 $0.09 $0.04 $0.01 $0.00 $0.01 $0.01 $0.01 $0.17 $0.04 $0.02 $0.22 $0.22 $0.22 $26.31 Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 21-6 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com G&A OPERATING COSTS RPA has allocated $11.5 million per year to cover general and administrative costs (G&A). The average annual unit cost is C$3.50/tonne of ore. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 21-7 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 22 ECONOMIC ANALYSIS CASH FLOW ANALYSIS A pre-tax cash flow projection has been generated from the LOM production schedule and capital and operating cost estimates, and is summarized in Table 22-1. A summary of the key criteria is provided below. PRODUCTION Production quantities total 34.6 Mt, at grades of 0.040% U3O8 and 1,455 ppm TREO, over a mine life of 11 years. o The Main Conglomerate Bed (MCB) zone totals 31.0 Mt grading 0.043% U3O8 and 1,544 ppm TREO o The Hangingwall Zone (HWZ) totals 3.6 Mt grading 0.017% U3O8 and 1,017 ppm TREO Underground mining using room and pillar mining methods, with all development in ore. Two years of pre-production development with mill commissioning and limited production commencing in the second year. Production rate ramping up to a nominal 9,000 tpd in Year 1. Processing by crushing and grinding, magnetic separation, froth flotation, acid baking and water leaching, solid/liquid separation, high density sludge (HDS) removal, and recovery of the valuable elements by solvent extraction and precipitation. The proposed processing method produces yellow cake and a mixed rare earths carbonate concentrate. Uranium recovery of 90% (assumption, based on historical operations in the area). Rare earths recoveries by individual oxide, based on preliminary bench scale testwork. LREOs average 89% recovery, while HREOs average 75% recovery. Mine life production of 27.5 million pounds of U3O8 and 44.1 million kg of TREO. Production of a strategically significant combination of rare earths forecast to remain in supply deficit, with 85% of Project revenue from heavy REO, neodymium oxide (Nd2O3) and U3O8. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 22-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com REVENUE Exchange rate US$1.00 = C$1.00. Uranium price of US$70 per pound U3O8. Rare earth prices by individual oxide, with a basket price of US$78 per kg. o Net of costs for separating the rare earth concentrate into individual oxides – C$30 per kg for HREOs and C$10 per kg for LREOs. LREOs consist of CeO2, La2O3, Nd2O3 and Pr6O11 while HREOs consist of Sm2O3, Eu2O3, Gd2O3, Sc2O3, Y2O3, Yb2O3, Dy2O3, Er2O3, Ho2O3, Lu2O3, Tb4O7 and Tm2O3. NSR royalty of 0.75%. Average net revenue (NSR unit value) of $154 per tonne. Uranium provides 36% of revenue, and rare earths provide 64%. HREO make up slightly over 50% of the rare earths revenue. Revenue is recognized at the time of production. Initial capital of C$563 million (first two years), includes contingency of $108 million. Mine life capital totals C$670 million. Unit operating costs of $71.33 per tonne. COSTS Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 22-2 Technical Report NI 43-101 – June 20, 2012 TABLE 22-1 PRE-TAX CASH FLOW SUMMARY Pele Mountain Resources Inc. – Eco Ridge Mine Project Year -2 Units Inputs Year -1 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Total MINING 34,550 000s tonnes Uranium Grade CeO2 Grade La2O3 Grade Nd2O3 Grade Pr6O11 Grade Sm2O3 Grade Eu2O3 Grade Gd2O3 Grade Sc2O3 Grade Y2O3 Grade Yb2O3 Grade Dy2O3 Grade Er2O3 Grade Ho2O3 Grade Lu2O3 Grade Tb4O7 Grade Tm2O3 Grade Th Grade LREO Grade HREO Grade Total REO Grade 0.040% %U3O8 ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm Oxide Factors 1.23 1.17 1.17 1.21 1.16 1.16 1.15 1.53 1.27 1.14 1.15 1.14 1.15 1.14 1.18 1.14 1.14 657.05 346.12 210.56 65.49 36.34 2.05 24.30 7.12 71.39 5.04 15.54 6.48 2.62 0.69 3.36 0.88 338.14 1,279.23 175.80 1,455.03 229 318 3,287 3,284 3,284 3,283 3,278 3,279 3,253 3,280 3,282 3,279 1,214 - 0.048% 0.058% 0.058% 0.052% 0.044% 0.045% 0.045% 0.036% 0.036% 0.037% 0.032% 0.020% 0.018% 0.000% 758.70 395.72 248.58 77.66 42.32 2.41 27.83 5.91 85.32 5.88 18.43 7.59 3.08 0.76 3.90 1.00 398.19 1,481 204 1,685 881.29 464.47 283.77 88.46 48.89 2.62 32.73 6.36 96.21 6.93 21.31 8.95 3.59 0.91 4.52 1.18 428.55 1,718 234 1,952 900.46 472.81 289.64 90.71 50.08 2.70 33.88 6.49 98.87 7.09 21.92 9.22 3.69 0.93 4.69 1.21 451.49 1,754 241 1,994 784.53 415.51 256.07 79.60 43.91 2.36 29.05 6.25 87.46 6.20 19.14 7.98 3.18 0.82 4.01 1.05 389.40 1,536 211 1,747 677.01 355.06 222.51 69.06 38.24 2.25 25.45 6.28 77.30 5.35 16.73 6.88 2.77 0.70 3.57 0.91 360.63 1,324 186 1,510 759.61 401.86 240.41 75.12 41.67 2.16 27.86 7.78 77.93 5.58 17.36 7.20 2.90 0.77 3.79 0.98 345.06 1,477 196 1,673 718.66 381.27 229.30 71.28 39.49 2.12 26.02 6.50 74.84 5.45 16.37 6.88 2.77 0.74 3.55 0.93 348.42 1,401 186 1,586 680.21 358.22 218.13 68.24 37.60 2.07 24.49 6.00 70.74 5.09 15.47 6.43 2.57 0.69 3.38 0.86 322.34 1,325 175 1,500 658.74 351.36 209.09 65.50 35.93 2.07 24.07 6.85 71.15 4.92 15.20 6.36 2.59 0.71 3.29 0.90 339.23 1,285 174 1,459 464.09 241.90 152.27 46.79 27.35 1.83 19.49 9.85 61.01 4.33 13.32 5.56 2.26 0.61 2.86 0.76 330.19 905 149 1,054 512.57 267.86 163.22 49.56 28.11 1.77 19.35 6.79 57.29 3.96 12.37 5.16 2.17 0.58 2.70 0.73 292.97 993 141 1,134 462.46 241.41 141.33 43.90 24.10 1.40 15.87 9.29 45.15 3.06 9.38 3.97 1.64 0.47 2.13 0.57 232.66 889 117 1,006 448.10 234.52 139.47 43.90 23.34 1.20 14.52 5.07 40.85 2.67 8.41 3.44 1.36 0.38 1.90 0.45 218.42 866 104 970 - 546 3,287 3,284 3,284 3,283 3,278 3,279 3,253 3,280 3,282 3,279 1,214 - 0.054% 829.93 435.66 269.03 83.94 46.14 2.53 30.68 6.17 91.65 6.49 20.10 8.38 3.38 0.85 4.26 1.11 415.83 3,199 439 3,637 0.058% 900.46 472.81 289.64 90.71 50.08 2.70 33.88 6.49 98.87 7.09 21.92 9.22 3.69 0.93 4.69 1.21 451.49 1,754 241 1,994 0.052% 784.53 415.51 256.07 79.60 43.91 2.36 29.05 6.25 87.46 6.20 19.14 7.98 3.18 0.82 4.01 1.05 389.40 1,536 211 1,747 0.044% 677.01 355.06 222.51 69.06 38.24 2.25 25.45 6.28 77.30 5.35 16.73 6.88 2.77 0.70 3.57 0.91 360.63 1,324 186 1,510 0.045% 759.61 401.86 240.41 75.12 41.67 2.16 27.86 7.78 77.93 5.58 17.36 7.20 2.90 0.77 3.79 0.98 345.06 1,477 196 1,673 0.045% 718.66 381.27 229.30 71.28 39.49 2.12 26.02 6.50 74.84 5.45 16.37 6.88 2.77 0.74 3.55 0.93 348.42 1,401 186 1,586 0.036% 680.21 358.22 218.13 68.24 37.60 2.07 24.49 6.00 70.74 5.09 15.47 6.43 2.57 0.69 3.38 0.86 322.34 1,325 175 1,500 0.036% 658.74 351.36 209.09 65.50 35.93 2.07 24.07 6.85 71.15 4.92 15.20 6.36 2.59 0.71 3.29 0.90 339.23 1,285 174 1,459 0.037% 464.09 241.90 152.27 46.79 27.35 1.83 19.49 9.85 61.01 4.33 13.32 5.56 2.26 0.61 2.86 0.76 330.19 905 149 1,054 0.032% 512.57 267.86 163.22 49.56 28.11 1.77 19.35 6.79 57.29 3.96 12.37 5.16 2.17 0.58 2.70 0.73 292.97 993 141 1,134 0.020% 462.46 241.41 141.33 43.90 24.10 1.40 15.87 9.29 45.15 3.06 9.38 3.97 1.64 0.47 2.13 0.57 232.66 889 117 1,006 0.018% 448.10 234.52 139.47 43.90 23.34 1.20 14.52 5.07 40.85 2.67 8.41 3.44 1.36 0.38 1.90 0.45 218.42 866 104 970 0.000% - 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% PROCESSING Ore to Processing 000s tonnes 34,550 Uranium Grade CeO2 Grade La2O3 Grade Nd2O3 Grade Pr6O11 Grade Sm2O3 Grade Eu2O3 Grade Gd2O3 Grade Sc2O3 Grade Y2O3 Grade Yb2O3 Grade Dy2O3 Grade Er2O3 Grade Ho2O3 Grade Lu2O3 Grade Tb4O7 Grade Tm2O3 Grade Th Grade LREO Grade HREO Grade Total REO Grade %U3O8 ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm ppm 0.040% 657.05 346.12 210.56 65.49 36.34 2.05 24.30 7.12 71.39 5.04 15.54 6.48 2.62 0.69 3.36 0.88 338.14 1,304 179 1,483 Recovery U3O8 Recovery CeO2 Recovery La2O3 Recovery Nd2O3 Recovery Pr6O11 Recovery Sm2O3 Recovery Eu2O3 Recovery Gd2O3 Recovery Sc2O3 Recovery Y2O3 Recovery Yb2O3 Recovery Dy2O3 Recovery Er2O3 Recovery Ho2O3 Recovery Lu2O3 Recovery Tb4O7 Recovery Tm2O3 Recovery Th % % % % % % % % % % % % % % % % % % Recovered U3O8 Recovered CeO2 Recovered La2O3 Recovered Nd2O3 Recovered Pr6O11 Recovered Sm2O3 Recovered Eu2O3 Recovered Gd2O3 Recovered Sc2O3 Recovered Y2O3 Recovered Yb2O3 Recovered Dy2O3 Recovered Er2O3 Recovered Ho2O3 Recovered Lu2O3 Recovered Tb4O7 Recovered Tm2O3 Recovered Th Recovered LREO Recovered HREO Total REOs 000 lbs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 kgs 000 lbs Head Grade Recovery 90% 90% 88% 89% 89% 85% 79% 81% 61% 76% 71% 75% 74% 71% 74% 78% 74% 80% 44,942 23,227 14,210 4,425 2,355 123 1,496 331 4,127 272 882 364 142 39 200 49 20,605 86,804 10,381 97,185 27,491 20,386 10,535 6,446 2,007 1,068 56 678 150 1,872 123 400 165 64 18 91 22 9,346 39,374 4,709 44,083 97,185 583 407 210 130 41 21 1 14 2 38 3 8 3 1 0 2 0 182 788 94 882 3,776 2,658 1,369 843 264 140 7 90 13 247 17 54 22 9 2 12 3 1,187 5,135 615 5,750 3,413 2,314 1,202 745 232 123 6 77 13 218 14 47 19 7 2 10 3 1,023 4,493 539 5,033 2,855 1,997 1,027 647 201 107 6 68 13 193 12 41 17 6 2 9 2 948 3,873 475 4,348 2,960 2,240 1,162 699 219 116 6 74 16 194 13 42 17 7 2 10 2 906 4,320 499 4,819 2,926 2,115 1,101 666 207 110 5 69 13 186 13 40 17 6 2 9 2 914 4,089 473 4,562 2,374 2,003 1,035 634 198 105 5 65 12 176 12 38 16 6 2 9 2 846 3,870 447 4,317 2,350 1,925 1,007 603 189 99 5 63 14 176 11 37 15 6 2 8 2 883 3,723 439 4,162 2,422 1,367 699 443 136 76 5 52 20 152 10 33 13 5 1 7 2 867 2,645 376 3,021 2,111 1,511 774 475 144 79 5 51 14 143 9 30 13 5 1 7 2 769 2,904 358 3,262 1,298 1,362 697 411 128 67 4 42 19 112 7 23 10 4 1 5 1 610 2,597 295 2,893 423 489 251 150 47 24 1 14 4 38 2 8 3 1 0 2 0 212 937 98 1,034 www.rpacan.com Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 22-3 Technical Report NI 43-101 – June 20, 2012 Ore Mined Year -2 Inputs Units Year -1 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Total REVENUE Gross Revenue US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s US$ '000s Exchange Rate 1 US$=C$ REO Basket Price Gross Revenue C$ '000s $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 70 18 20 175 140 80 2,900 150 3,000 150 90 1,450 195 1,200 2,200 3,000 $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 1,924,376 366,941 210,708 1,127,993 280,988 85,468 162,090 101,756 450,732 280,814 11,094 579,933 32,232 21,280 199,912 67,163 1,986,631 1,992,474 3,979,104 5,903,481 $ $ 90 5,903,481 $40,804 $7,331 $4,195 $22,795 $5,696 $1,717 $3,168 $2,032 $6,183 $5,702 $226 $11,867 $659 $0 $412 $4,011 $1,338 $40,017 $37,314 $77,332 $118,135 1.00 1.00 $ $264,346 $47,837 $27,381 $147,601 $37,023 $11,205 $20,336 $13,494 $39,129 $36,995 $1,485 $77,812 $4,359 $0 $2,713 $26,563 $8,775 $259,842 $242,867 $502,710 $767,055 1.00 $238,883 $41,649 $24,045 $130,398 $32,465 $9,819 $17,761 $11,564 $37,632 $32,705 $1,297 $67,894 $3,771 $0 $2,401 $22,688 $7,656 $228,557 $215,188 $443,745 $682,628 1.00 $199,859 $35,940 $20,546 $113,305 $28,166 $8,550 $16,910 $10,130 $37,786 $28,903 $1,121 $59,341 $3,250 $0 $2,037 $20,192 $6,616 $197,956 $194,836 $392,793 $592,652 1.00 $207,172 $40,312 $23,248 $122,384 $30,629 $9,313 $16,224 $11,085 $46,831 $29,128 $1,168 $61,555 $3,403 $0 $2,242 $21,453 $7,105 $216,573 $209,508 $426,081 $633,253 1.00 $204,808 $38,074 $22,019 $116,529 $29,011 $8,812 $15,900 $10,338 $39,028 $27,927 $1,137 $57,958 $3,245 $0 $2,165 $20,061 $6,726 $205,633 $193,297 $398,930 $603,737 1.00 $166,176 $36,052 $20,697 $110,900 $27,785 $8,394 $15,539 $9,732 $36,075 $26,408 $1,062 $54,786 $3,032 $0 $2,007 $19,069 $6,255 $195,434 $182,360 $377,795 $543,971 1.00 $164,503 $34,642 $20,142 $105,473 $26,464 $7,959 $15,390 $9,492 $40,831 $26,352 $1,019 $53,410 $2,976 $0 $2,061 $18,458 $6,492 $186,720 $184,439 $371,159 $535,663 1.00 $169,567 $24,608 $13,982 $77,447 $19,060 $6,108 $13,747 $7,749 $59,251 $22,787 $906 $47,190 $2,623 $0 $1,767 $16,160 $5,530 $135,096 $183,816 $318,912 $488,478 1.00 $147,739 $27,192 $15,490 $83,056 $20,198 $6,282 $13,282 $7,696 $40,852 $21,406 $828 $43,866 $2,439 $0 $1,692 $15,264 $5,312 $145,935 $158,917 $304,853 $452,592 1.00 $90,895 $24,511 $13,948 $71,853 $17,874 $5,379 $10,506 $6,307 $55,851 $16,856 $638 $33,230 $1,873 $0 $1,374 $12,029 $4,136 $128,185 $148,179 $276,364 $367,259 1.00 $29,625 $8,793 $5,017 $26,253 $6,618 $1,929 $3,328 $2,136 $11,284 $5,647 $207 $11,025 $600 $0 $410 $3,964 $1,223 $46,680 $41,751 $88,432 $118,057 1.00 88 $ $118,135 87 $ $767,055 88 $ $682,628 90 $ $592,652 88 $ $633,253 87 $ $603,737 88 $ $543,971 89 $ $535,663 106 $ $488,478 93 $ $452,592 96 $ $367,259 86 $118,057 $7,880 $2,825 $10,705 12 $ 13.8% $51,346 $18,453 $69,799 12 $ 13.9% $44,931 $16,182 $61,113 12 $ 13.8% $38,726 $14,254 $52,980 12 $ 13.5% $43,201 $14,981 $58,181 12 $ 13.7% $40,893 $14,178 $55,071 12 $ 13.8% $38,699 $13,404 $52,103 12 $ 13.8% $37,234 $13,171 $50,405 12 $ 13.6% $26,449 $11,292 $37,741 12 $ 11.8% $29,040 $10,736 $39,776 12 $ 13.0% $25,974 $8,860 $34,833 12 $ 12.6% $9,366 $2,928 $12,294 12 13.9% Offsite Concentrate Costs LREOs HREOs Total C$ '000s C$ '000s C$ '000s C$/kg % of Gross $ $ 10.00 30.00 $ $ $ $ 393,737 141,264 535,002 12 13.4% $ Net Revenue Uranium Rare Earths Total Net Revenue C$ '000s C$ '000s C$ '000s $ $ $ 1,924,376 3,444,103 5,368,479 $40,804 $66,627 $107,431 $264,346 $432,911 $697,256 $238,883 $382,632 $621,515 $199,859 $339,813 $539,672 $207,172 $367,900 $575,072 $204,808 $343,858 $548,666 $166,176 $325,691 $491,867 $164,503 $320,755 $485,258 $169,567 $281,171 $450,737 $147,739 $265,077 $412,816 $90,895 $241,531 $332,425 $29,625 $76,137 $105,762 NSR Royalty NSR Royalty Total Royalty Paid C$ '000s C$ '000s C$ '000s 0.75% $ 0.00% $ $ 40,264 40,264 $806 $0 $806 $5,229 $0 $5,229 $4,661 $0 $4,661 $4,048 $0 $4,048 $4,313 $0 $4,313 $4,115 $0 $4,115 $3,689 $0 $3,689 $3,639 $0 $3,639 $3,381 $0 $3,381 $3,096 $0 $3,096 $2,493 $0 $2,493 $793 $0 $793 Net Smelter Return $106,625 $195 $692,027 $211 $616,854 $188 $535,625 $163 $570,759 $174 $544,551 $166 $488,178 $149 $481,618 $148 $447,357 $136 $409,720 $125 $329,932 $101 $104,969 $86 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 $41.52 $26.31 $3.50 $71.33 C$ '000s C$/t $ OPERATING COSTS Mining Processing G&A Total Opex Per Tonne Milled C$/t mined C$/t milled C$/t milled C$/t milled $ $ $ $ 42.64 26.31 3.44 72.40 Mining Processing G&A Total Operating Cost C$ '000s C$ '000s C$ '000s C$ '000s $ $ $ $ 1,473,308 909,013 119,013 2,501,334 $28,519 $0 $0 $28,519 $32,959 $14,378 $0 $47,336 $136,462 $86,472 $11,503 $234,438 $136,365 $86,410 $11,495 $234,270 $136,359 $86,407 $11,495 $234,260 $136,320 $86,382 $11,491 $234,193 $136,085 $86,233 $11,472 $233,790 $136,144 $86,270 $11,476 $233,891 $135,080 $85,597 $11,387 $232,064 $136,200 $86,306 $11,481 $233,987 $136,266 $86,348 $11,487 $234,101 $136,143 $86,270 $11,476 $233,889 $50,405 $31,940 $4,249 $86,594 Operating Margin C$ '000s $ 2,826,882 -$28,519 $59,288 $457,589 $382,583 $301,365 $336,566 $310,761 $254,288 $249,554 $213,370 $175,619 $96,043 $18,375 $0 $0 $86,420 $7,300 $165,366 $33,926 $20,215 $3,000 $47,620 $35,000 $30,909 $7,300 $82,683 $16,963 $10,107 $3,000 $10,000 $17,000 $30,276 $9,404 $5,963 $6,977 $2,891 CAPITAL COSTS Directs Mining Process Site Development Acid Baking Plant Uranium Extraction Plant Y & REE Plant Water Treatment Plant Tailings Site infrastructure Indirects Mine Indirects Process Indirects Construction Indirects Contingency Process Contingency Mining & Other Contingency Total Initial Capital $ $ $ 41.52 26.31 3.50 5,328,215 $154 C$ '000s C$ '000s C$ '000s C$ '000s C$ '000s C$ '000s C$ '000s C$ '000s $86,802 $7,300 $165,366 $33,926 $20,215 $3,000 $47,620 C$ '000s C$ '000s C$ '000s $12,000 $67,561 $35,000 $12,000 $67,561 $35,000 $6,000 $33,781 $17,500 $6,000 $33,781 $17,500 C$ '000s C$ '000s C$ '000s 30% 25% $89,210 $18,396 $562,843 $46,150 $9,227 $290,620 $43,060 $9,169 $272,224 C$ '000s C$ '000s C$ '000s $24,000 $22,000 $667,013 $3,000 $3,000 $3,000 $3,000 $290,620 $272,224 $19,404 $8,963 $26,389 $5,891 $3,000 $3,000 $2,000 $5,000 $3,000 $2,000 $11,523 $3,000 $3,000 $6,000 $3,000 $2,000 $5,000 $2,000 $2,000 $8,000 $8,000 $2,000 $2,000 $1,000 $1,000 PRE-TAX CASHFLOW Pre-Tax Cash Flow Cumulative C$ '000s C$ '000s $2,159,868 -$319,139 -$319,139 -$212,935 -$532,074 $438,185 -$93,889 $373,620 $279,731 $274,976 $554,706 $330,675 $885,381 $307,761 $1,193,142 $249,288 $1,442,430 $238,031 $1,680,462 $207,370 $1,887,831 $170,619 $2,058,450 $94,043 $2,152,493 $10,375 $2,162,868 -$2,000 $2,160,868 -$1,000 $2,159,868 PROJECT ECONOMICS Pre-Tax IRR Pre-Tax NPV Pre-Tax NPV Pre-Tax NPV C$ '000s C$ '000s C$ '000s Sustaining Capital Site Decomissioning and Monitoring Total Capital Cost 5% 7.5% 10% 50% $1,475,351 $1,226,684 $1,022,820 $82,683 $16,963 $10,107 $14,685 $8,000 $16,412 $6,523 $10,000 www.rpacan.com Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 22-4 Technical Report NI 43-101 – June 20, 2012 U3O8 CeO2 La2O3 Nd2O3 Pr6O11 Sm2O3 Eu2O3 Gd2O3 Sc2O3 Y2O3 Yb2O3 Dy2O3 Er2O3 Ho2O3 Lu2O3 Tb4O7 Tm2O3 Sub-Total LREOs Sub-Total HREOs Sub-Total REOs Total Gross Revenue www.rpacan.com CASH FLOW RESULTS The cash flow analysis in this report has been carried out on a pre-tax basis. Considering the full project on a stand-alone basis, the undiscounted pre-tax cash flow totals C$2.2 billion over the 11 year mine life and simple payback occurs 1.5 years after the start of commercial production. The internal rate of return (IRR) is 50% and the net present value (NPV) is as follows: C$1.5 billion at a 5% discount rate C$1.2 billion at a 7.5% discount rate C$1.0 billion at a 10% discount rate The economic analysis contained in this report is based, in part, on Inferred Resources, and is preliminary in nature. Inferred Resources are considered too geologically speculative to have mining and economic considerations applied to them and to be categorized as Mineral Reserves. There is no certainty that economic forecasts on which this Preliminary Economic Assessment is based will be realized. SENSITIVITY ANALYSIS Sensitivity analyses were performed for uranium price, REO prices, operating cost, capital cost, uranium recovery, and rare earth recoveries. The sensitivity analyses on IRR and NPV at a discount rate of 10% indicate that the Project economics are most heavily influenced by the recovery and market price of REEs. The Project economics are also heavily influenced by the operating cost. These sensitivities focus on rare earth oxides, which provide approximately 64% of the base case revenue whereas uranium provides approximately 36% of the base case revenue. The recent price history for rare earths covers a wide range, including order-ofmagnitude increases within 2011. The rare earths price sensitivity is based on results at a conservative long-term forecast ($30/kg basket price), the base case ($90/kg basket price), and current prices ($103/kg basket price). Note that these prices relate to gross revenue, before separation charges are applied. Figure 22-1 and Table 22-2 summarize the results of the sensitivity analyses. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 22-5 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com FIGURE 22-1 SENSITIVITY ANALYSIS $2,000,000 NPV @ 10% ('000s) $1,600,000 REE Recovery $1,200,000 U3O8 Recovery REE Price $800,000 U3O8 Price Operating Costs $400,000 Capital Costs $0 ‐40% ‐30% ‐20% ‐10% 0% 10% 20% 30% 40% Factor of Change Note: U3O8 recovery has the same slope as U3O8 price. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 22-6 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 22-2 SENSITIVITY ANALYSIS Pele Mountain Resources Inc. – Eco Ridge Mine Project Factor 0.72 0.86 1 1.14 1.29 U3O8 Market Price U3O8 Price (US$/lb) NPV (C$ millions) 50 728 60 875 70 1,022 80 1,171 90 1,319 IRR (%) 35% 45% 50% 57% 60% Factor 0.33 0.66 1 1.14 REO Basket Price REO Price (US$/kg) NPV (C$ millions) 30 (381) 60 324 90 1,022 103 1,316 IRR (%) NA 26% 50% 59% Operating Cost Per Tonne Milled Opex (C$/t) NPV (C$ millions) IRR (%) Factor 0.8 0.9 1 1.1 1.2 Factor 0.8 0.9 1 1.1 1.2 Factor 0.85 0.925 1 1.075 1.15 58 65 71 80 87 1,278 1,151 1,022 895 767 Capital Cost Capex (C$ millions) NPV (C$ millions) 534 600 667 734 800 1,132 1,077 1,022 968 914 Recovery - REE Average Recovery NPV (C$ millions) 68% 751 74% 887 79% 1,022 85% 1,159 90% 1,295 58% 54% 50% 46% 42% IRR (%) 63% 56% 50% 46% 41% IRR (%) 42% 46% 50% 54% 58% EXTENDED MINE LIFE SENSITIVITY The MCB is known to persist to the north of the current resource model, as indicated by historical drilling. RPA examined the effect of extending the mine life to include an additional 50 Mt of production from the MCB, resulting in a mine life of 25 years. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 22-7 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com The undiscounted pre-tax cash flow for the extended mine life sensitivity totals C$6.5 billion with an IRR of 51%. The net present value (NPV) is as follows: C$3.2 billion at a 5% discount rate C$2.3 billion at a 7.5% discount rate C$1.7 billion at a 10% discount rate Given the long mine life, RPA also looked at a higher production rate for this extended mine life sensitivity, increasing production from 9,000 tpd to 12,000 tpd while using the same mining method. A summary of the key inputs and criteria in developing the 12,000 tpd option is illustrated below. LOM of 20 years Higher capital costs for larger operation: o Initial capital cost of C$661 million o Total capital cost of C$838 million Lower operating costs of C$69 per tonne of ore mined, The undiscounted pre-tax cash flow in this case totals C$6.6 billion. The IRR is 53% and the NPV is as follows: C$3.6 billion at a 5% discount rate C$2.7 billion at a 7.5% discount rate C$2.1 billion at a 10% discount rate Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 22-8 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 23 ADJACENT PROPERTIES EXPLORATION Abeta Mining Corporation Limited (Abeta) held a block of 25 claims (Abeta Block) on the west boundary of the Eco Ridge Mine property. During the period from October 1953 to June 1954, 15 holes were drilled by the Mining Corporation of Canada on the Abeta Block. In 1977, Long Lac Mineral Exploration drilled 14 holes on the Abeta Block and, in 1977, David S. Robertson & Associates Ltd. (Robertson) completed a report on the economic potential of the property previously owned by Abeta. Robertson noted that there were several beds of uraniferous conglomerates within the Lower Matinenda Formation. The principal bed was located from 15.2 m (50 ft) to 30.4 m (100 ft) above the basement rocks and Robertson identified this bed as the “Pardee Reef”. It also noted that uraniferous conglomerate beds were developed from 3.3 m (10 ft) to 15.2 m (50 ft) above the hangingwall contact of the Pardee Reef and termed these units “Floater Reefs”. Robertson also noted the occurrence of a polymictic conglomerate at the contact between the sediments and the underlying basement rocks. The uranium mineralization on the Abeta Block is interpreted as an extension of the mineralization on the Pele Mountain property to the west (the Pardee deposit). The Pardee Reef described by Robertson is directly correlated with the MCB described on the Pele Mountain property. The Floater Reefs are correlated with the upper reefs and the conglomerate located at the basement contact on the Abeta property is correlated with the BCB described on the Eco Ridge Mine property. This information was used to extend the Mineral Resource to the western boundary of the Eco Ridge Mine property. MINING OPERATIONS Historically, mining and processing operations were carried out in the Elliot Lake area, but not on the Eco Ridge Mine property. The mining at Elliot Lake was all by underground methods, primarily room and pillar, with shaft access. The major portion of the ore mined was processed through a conventional uranium processing plant, with some production from underground leaching. The Elliot Lake mineralization also Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 23-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com contains rare earth oxides. Yttrium oxide and rare earth oxides were recovered at the Denison mine in the past, as by-products of the uranium production. Rio Algom operated a total of nine uranium mines between 1955 and 1996 while Denison Mines operated three. The two closest mines to the Eco Ridge Mine Project are Nordic (Denison Mines) and Lacnor (Rio Algom) mines. Nordic Mine started its operations in 1956 and ended in 1970, producing approximately 13 Mt of ore from the Pardee Reef. Lacnor operated from 1956 to 1960 producing approximately 3.4 Mt of ore. Stanleigh Mine (Rio Algom), another major uranium mine further to the west of Nordic and Lacnor mines, operated from 1956 to 1960 and re-opened in 1982 until its final closure in 1996, producing over 14.0 Mt of ore from the Pardee Reef. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 23-2 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 24 OTHER RELEVANT DATA AND INFORMATION Past PEA-level work on the Project includes studies on alternative production scenarios that may be relevant to future work: Various mining methods Processing options Waste management alternatives PROJECT SCHEDULE A schedule for the Project, covering the path forward through a Feasibility Study, permitting, and construction, is presented in Figure 24-1. The critical path runs through the permitting process, although this is influenced by the availability of sufficient engineering work being completed as needed for key permitting documents. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 24-1 Technical Report NI 43-101 – June 20, 2012 Activity ID Activity Name Original Start Duration Environmental EIA (SENES) Finish 2012 2013 J F M A M J Jul A S O N D J F M A M J J A S O N D 1463 03-Jan-12 10-Nov-17 1463 03-Jan-12 10-Nov-17 1463 03-Jan-12 10-Nov-17 1463 03-Jan-12* 10-Nov-17 S50810 Consultation S50760 Submit Project Description to CNSC S50770 Baseline Characterization Program/Reporting 427 03-Jul-12 24-Mar-14 F3310 Environment Impact Statement 427 27-Sep-12 19-Jun-14 S50800 Other Authorisations 488 28-Mar-13 19-Mar-15 S50780 Regulatory Review and EA Decision Statement 190 19-Jun-14 30-Mar-15 S50790 Issue Site Preparation / Construction Licences 122 06-Jan-15 02-Jul-15 220 01-Aug-12 24-Jun-13 220 01-Aug-12 24-Jun-13 220 01-Aug-12 24-Jun-13 Preliminary Mine Site Study Geotechnical MINE SITE - RPA 60 03-Jul-12* 60 01-Aug-12* Hydrogeological Study S50730 Underground Geotechnical Studies 120 01-Aug-12 29-Jan-13 F3290 Resource Drilling 160 01-Aug-12 27-Mar-13 S50720 Resource Update 60 28-Mar-13 24-Jun-13 248 02-Jan-13 13-Dec-13 240 02-Jan-13 13-Dec-13 240 02-Jan-13 13-Dec-13 Key Milestones GENERAL F1160 Commence Feasibility Study F1150 Feasibility Study Complete Engineering MINE SITE S50750 Feasibility Mine Design & Cost Estimation 26-Oct-12 0 13-Dec-13* 26-Sep-13 120 02-Jan-13 25-Jun-13 120 02-Jan-13 25-Jun-13 180 10-Jan-13 18-Sep-13 Process Engineering 165 10-Jan-13 05-Sep-13 49E0030 Engineering Design & MTO's 140 07-Mar-13 18-Sep-13 49E0020 Plant Layouts 110 04-Apr-13 04-Sep-13 180 10-Jan-13 26-Sep-13 180 10-Jan-13 26-Sep-13 157 18-Mar-13 28-Oct-13 157 18-Mar-13 28-Oct-13 157 18-Mar-13 28-Oct-13 60 19-Sep-13 13-Dec-13 60 19-Sep-13 13-Dec-13 60 19-Sep-13 13-Dec-13 24-2 TAILINGS FACILITY F2970 Tailings Facility Design & MTO's Procurement F1840 Equipment/Installation Contract Pricing Estimate Compilation F2780 Estimate Compilation & Review F1190 Handover to Client 0 Project Execution Key Milestones GENERAL KM10 Contract Award for Execution KM20 Project Completion 05-Dec-16 718 21-Jan-14 05-Dec-16 718 21-Jan-14 05-Dec-16 06-May-15 310 04-Feb-14 06-May-15 310 04-Feb-14 06-May-15 TF0010 Tailings Facility Design 150 04-Mar-14 06-Oct-14 530 15-Apr-14 08-Jun-16 530 15-Apr-14 08-Jun-16 Procurement 240 15-Apr-14 08-Apr-15 F3220 Manufacture & Deliver to Site 490 13-Jun-14 08-Jun-16 359 02-Jul-15 05-Dec-16 359 02-Jul-15 05-Dec-16 F3320 Construction Permits Available F3240 Site Establishment F3330 Construction Monitoring for Tailings Facility F3250 Site Work F3340 Continue Construction Monitoring for Tailings Facil ity 80 18-Apr-16 09-Aug-16 F3260 Commissioning 60 12-Sep-16 05-Dec-16 Actual Work Critical Remaining Work Milestone June 2012 Project Schedule 0 02-Jul-15 100 02-Jul-15 24-Nov-15 80 23-Jul-15 17-Nov-15 299 30-Jul-15 10-Oct-16 Source: SNC Lavalin, 2012. www.rpacan.com F3230 Remaining Work Elliot Lake, Ontario, Canada 05-Dec-16* 310 04-Feb-14 Engineering Design for Process Plant Construction Eco Ridge Mine Project 0 21-Jan-14 49010 Procurement Pele Mountain Resources Inc. 13-Dec-13 718 21-Jan-14 0 Engineering Figure 24-1 0 02-Jan-13* 192 02-Jan-13 49E0010 PROCESS PLANT A S O N 26-Sep-12 S50740 Feasibility Study 2014 2015 2016 2017 J F M A M J J A S O N D J F M A M J Jul A S O N D J F M A M J J A S O N D J F M A M J J www.rpacan.com 25 INTERPRETATION AND CONCLUSIONS In RPA’s opinion, the PEA indicates that positive economic results can be obtained for the Eco Ridge Mine Project, in a scenario that includes room and pillar mining, and uranium and rare earth recovery by conventional milling. The Base Case LOM plan for the Project indicates that 34.6 Mt, at average grades of 0.040% U3O8 and 1,455 g/t TREO, will be mined over 11 years at a nominal production rate of 9,000 tpd. Uranium production is projected to total 27.5 million pounds, and REO production is projected to total 44.1 million kilograms. The Project has good potential for increasing the base case mine life. Specific conclusions by area of the PEA are as follows. GEOLOGY AND RESOURCES Rare earth and uranium mineralization on the Eco Ridge property is hosted primarily by the Main Conglomerate Bed (MCB) and the Hangingwall Zone (HWZ) located within the Ryan Member of the Mississagi Quartzite. On average, the MCB is 2.7 m thick and dips consistently at an average of -21o north. The HWZ, located immediately above the MCB, is defined by economic limits. The current Mineral Resource estimate is listed in Table 25-1. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 25-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TABLE 25-1 SUMMARY OF MINERAL RESOURCES – APRIL 16, 2012 Pele Mountain Resources Inc. – Eco Ridge Mine Project Tonnes U3O8 U3O8 LREO HREO TREO TREO (000) (%) (000 lbs) (ppm) (ppm) (ppm) (000 lbs) MCB 20,514 0.045 20,447 1,426 193 1,618 73,184 HWZ 28,223 0.012 7,214 733 88 821 51,111 Total 48,737 0.026 27,661 1,025 132 1,157 124,295 MCB 16,906 0.043 15,940 1,279 183 1,463 54,515 HWZ 20,956 0.013 5,822 713 95 808 37,329 Total 37,863 0.026 21,762 966 134 1,100 91,843 Zone & Classification Indicated Inferred Notes: 1. 2. 3. 4. 5. 6. CIM definitions were followed for Mineral Resources. Mineral Resources were estimated at a cut-off value of $100 per tonne for the MCB, and $50 per tonne for the HWZ. Values were calculated based on prices and recoveries of uranium and rare earths, net of off-site rare earth separation costs. Mineral Resources were estimated using an average uranium price of US$70 per lb U3O8, a rare earth “basket price” of $78 per kg (net of separation charges), and a C$:US$ exchange rate of 1.00:1.00. A minimum mining thickness of 1.8 m was used for the MCB. Light Rare Earth Oxides include La2O3, CeO2, Pr6O11, and Nd2O3. Heavy Rare Earth Oxides include Sm2O3, Eu2O3, Gd2O3, Tb4O7, Dy2O3, Ho2O3, Er2O3, Tm2O3, Yb2O3, Y2O3, and Lu2O3. Sc2O3 is also included in HREO, as it occurs in low concentrations and carries high unit values like an HREO. Historic drilling has intersected the MCB to the west, to the east, and down-dip from the current Mineral Resource. A target for further exploration was estimated for these areas, consisting of a further 40 Mt to 60 Mt, grading from 0.030% to 0.050% U3O8, accompanied by 0.12% to 0.18% TREO for the MCB. The potential quantities and grades of the exploration targets are conceptual in nature and there has been insufficient drilling to define a Mineral Resource. It is uncertain if further exploration will result in the definition of a mineral resource in these areas. MINING The MCB is correlated with the “Pardee Reef” in the Nordic Channel. This reef was mined at the adjacent Nordic and Stanleigh mines operated by Rio Algom between 1957 and 1996. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 25-2 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com A number of mining methods have been assessed by RPA and others for extraction of the MCB mineralization. The selected mining method was room and pillar, with both development and production contained within the mineralized zone. The development and production tonnage will be loaded into trucks and transported to surface for processing. Although the MCB average mining thickness is 2.7 m, in RPA’s opinion, the deposit will support a high production rate. The lateral extents are such that multiple accesses from surface are feasible, providing many independent workplaces. The use of conveyors instead of haul trucks for material handling, while not included in the base case, may provide economic advantages, and is worth consideration in future studies. Particular attention should be paid to impacts on grade distribution in production schedules for each option, as there may be less flexibility with conveyors, offsetting the cost advantage that they provide. In RPA’s opinion, conveyors may also provide operational advantages that are difficult to quantify economically at this stage of the Project, including better mine ventilation, reduced traffic on the ramps, and easier material handling as the mine extends at depth. Geotechnical and hydrogeological assumptions are supported by historic operations in Elliot Lake, however, require confirmation by data collection and analysis at the Project. PROCESSING AND METALLURGY Historically, mining and processing operations have been carried out in the Elliot Lake area, but not on the Eco Ridge Mine property. The major portion of the ore mined was processed through a conventional uranium processing plant, with some production from underground leaching on run-of-mine ore. Yttrium oxide and rare earth oxides were also recovered at the Denison Mine in the past, as by-products of the uranium production. RPA has observed that the metallurgical program supporting the current Project flowsheet has been dynamic, involving changes in pursuit of potential improvements on relatively short notice. The unit operations within the process flowsheet have been tested at various times, using different metallurgical samples, which is not unusual at the PEA stage of project development. The testwork to date has focused on optimizing rare Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 25-3 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com earths recoveries, and although the overall uranium recovery assumption has not been verified by testwork, it is typical of that achieved in historical operations. The assumed recovery is supported by excellent results achieved for uranium in the acid bake unit operation. RPA made a number of assumptions in assembling the various testwork results into a coherent overall recovery for each element. The data used for the PEA is preliminary in nature and, therefore, indicative of the results that may be expected after a more rigorous and thorough program of metallurgical testing is conducted. The actual results achieved in the long term may vary significantly if a plant is ultimately constructed and operated, particularly since the current design is based on many assumptions. That being said, the processes that have been tested are not optimized and, based on that observation, it is reasonable to expect that the results may also be better. ENVIRONMENT Preliminary baseline aquatic and terrestrial environmental studies have been performed and no environmental problems have been identified to date. In order to identify all potential environmental risks pertaining to the Project, Human Health and Ecological Risk Assessments will need to be conducted during the Environmental Assessment (EA) process. The assessments will be completed in full matrices, with the highest ranking environmental risks being identified along with corresponding abatement strategies listed in table format. Because of the extensive documented experience in the Elliot Lake mining camp with uranium mine operations and decommissioning, it is expected that all significant risks can be effectively managed. MARKETS Uranium A uranium price of US$70/lb U3O8 has been used in this PEA, based on independent metal price forecasts from banks and financial institutions. RPA notes that the price used in the PEA, while slightly above the long term price for U3O8, is within the range of medium- to long-term forecasts. Rare Earths The market for rare earth products is currently relatively small but growing rapidly for certain rare earths. Public information on price forecasts and sales terms are difficult to Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 25-4 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com obtain and vary within a wide range. Current prices are tracked by sources such as Asian Metal and Metal-PagesTM, based on transactions. Recent history shows international rare earth market prices growing at an unprecedented rate since China cut export quotas by approximately 40% in 2011. China’s overwhelming control on the rare earth supply chain, from upstream mining to downstream processing and end-user products, is likely to remain intact on all but a few materials through 2016. Rare earth prices are expected to remain volatile in the short term. A small number of REE producers outside of China are likely to be in operation by the time the Eco Ridge Mine Project is developed. This is expected to saturate the market for LREO such as lanthanum and cerium, however, demand for high-value HREO (such as dysprosium) is expected to grow, and supply is expected to remain in deficit. Price forecasting in this environment is difficult, and certain to contain wide margins of error. RPA selected rare earth prices within a range of available forecasts. Prices for certain elements are higher than current prices, and for others, lower, however the average basket price is approximately 13% lower than Q2 2012 prices. RPA considers these rare earths prices to be appropriate for a PEA-level study, however, we note that the recent market volatility introduces considerably more uncertainty than a comparable base or precious metals project. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 25-5 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 26 RECOMMENDATIONS RPA recommends that Pele Mountain continue collecting data to support the feasibility and licensing process, and move on to more advanced engineering studies. Specific recommendations are as follows: Continue infill drilling programs to advance the Inferred Resources to Indicated classification. The budget presented below includes resource drilling. Carry out geotechnical and hydrogeological studies to confirm the parameters for mining without adversely impacting ground stability. Undertake a systematic metallurgical testing program. Care should be taken to collect samples that are representative of the material that will be processed over the LOM. An outline of the testing program should be developed prior to the time the samples are collected and sufficient amounts of materials should be shipped to the testing facility to complete the testing that is required for the next phase of the project development. RPA also recommends that SNC Lavalin continue to liaison and coordinate with the testing laboratory to oversee the testing parameters and to review the results as they become available. This will help to ensure that the data meets the requirements of producing design information that is needed to support the Feasibility Study. The metallurgical program should be planned, budgeted, and scheduled to integrate with other aspects of the project. Future testing programs must also include tests to evaluate the processes to precipitate uranium oxide and rare earth carbonate concentrates to determine the processing parameters required for the plant design. Continue to evaluate rare earth separation opportunities for upgrading the rare earth concentrate to separated rare earth oxides. Continue baseline studies in preparation for an EA, and the licensing process. Continue public consultation. Once the project activities have been sufficiently defined and funding for the Feasibility Study and licensing process is secured, an application should be submitted to the Canadian Nuclear Safety Commission (CNSC) to construct the Eco Ridge Mine and the EA process should continue by submitting a revised Project Description to the Major Projects Management Office. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 26-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Continue the EA process based on EA Guidelines (to be provided by the CNSC / Canadian Environmental Assessment Act (CEAA)) and the licensing process in consultation with CNSC. Monitor developments in REO and uranium markets, including forecast market prices based on supply and demand fundamentals for each of the rare earths and uranium. Based on Pele Mountain’s intention to advance the Project to the feasibility stage, RPA has recommended the proposed program. The objectives of the proposed program are to assess the opportunities, while advancing the studies supporting the feasibility and licensing process. A budget is presented in Table 26-1. TABLE 26-1 PROPOSED WORK PROGRAM AND ESTIMATED COST Pele Mountain Resources Inc. – Eco Ridge Mine Project Item Infill Drill Program Cost (C$ millions) 5.6 Geotechnical Studies 0.7 Metallurgical Testwork 0.7 Feasibility Study 8.0 Environmental Baseline Monitoring 1.5 Permitting Activities 4.5 Government Agency Project Review 1.5 Contingency 2.5 Total 25.0 A schedule for the Project, covering the path forward through a Feasibility Study, permitting, and construction, is presented in Figure 26-1. The critical path runs through the permitting process, although this is influenced by the availability of sufficient engineering work being completed as needed for key permitting documents. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 26-2 Technical Report NI 43-101 – June 20, 2012 Activity ID Activity Name Original Start Duration Environmental EIA (SENES) Finish 2012 2013 J F M A M J Jul A S O N D J F M A M J J A S O N D 1463 03-Jan-12 10-Nov-17 1463 03-Jan-12 10-Nov-17 1463 03-Jan-12 10-Nov-17 1463 03-Jan-12* 10-Nov-17 S50810 Consultation S50760 Submit Project Description to CNSC S50770 Baseline Characterization Program/Reporting 427 03-Jul-12 24-Mar-14 F3310 Environment Impact Statement 427 27-Sep-12 19-Jun-14 S50800 Other Authorisations 488 28-Mar-13 19-Mar-15 S50780 Regulatory Review and EA Decision Statement 190 19-Jun-14 30-Mar-15 S50790 Issue Site Preparation / Construction Licences 122 06-Jan-15 02-Jul-15 220 01-Aug-12 24-Jun-13 220 01-Aug-12 24-Jun-13 220 01-Aug-12 24-Jun-13 Preliminary Mine Site Study Geotechnical MINE SITE - RPA 60 03-Jul-12* 60 01-Aug-12* Hydrogeological Study S50730 Underground Geotechnical Studies 120 01-Aug-12 29-Jan-13 F3290 Resource Drilling 160 01-Aug-12 27-Mar-13 S50720 Resource Update 60 28-Mar-13 24-Jun-13 248 02-Jan-13 13-Dec-13 240 02-Jan-13 13-Dec-13 240 02-Jan-13 13-Dec-13 Key Milestones GENERAL F1160 Commence Feasibility Study F1150 Feasibility Study Complete Engineering MINE SITE S50750 Feasibility Mine Design & Cost Estimation 26-Oct-12 0 13-Dec-13* 26-Sep-13 120 02-Jan-13 25-Jun-13 120 02-Jan-13 25-Jun-13 180 10-Jan-13 18-Sep-13 Process Engineering 165 10-Jan-13 05-Sep-13 49E0030 Engineering Design & MTO's 140 07-Mar-13 18-Sep-13 49E0020 Plant Layouts 110 04-Apr-13 04-Sep-13 180 10-Jan-13 26-Sep-13 180 10-Jan-13 26-Sep-13 157 18-Mar-13 28-Oct-13 157 18-Mar-13 28-Oct-13 157 18-Mar-13 28-Oct-13 60 19-Sep-13 13-Dec-13 60 19-Sep-13 13-Dec-13 60 19-Sep-13 13-Dec-13 26-3 TAILINGS FACILITY F2970 Tailings Facility Design & MTO's Procurement F1840 Equipment/Installation Contract Pricing Estimate Compilation F2780 Estimate Compilation & Review F1190 Handover to Client 0 Project Execution Key Milestones GENERAL KM10 Contract Award for Execution KM20 Project Completion 05-Dec-16 718 21-Jan-14 05-Dec-16 718 21-Jan-14 05-Dec-16 06-May-15 310 04-Feb-14 06-May-15 310 04-Feb-14 06-May-15 TF0010 Tailings Facility Design 150 04-Mar-14 06-Oct-14 530 15-Apr-14 08-Jun-16 530 15-Apr-14 08-Jun-16 Procurement 240 15-Apr-14 08-Apr-15 F3220 Manufacture & Deliver to Site 490 13-Jun-14 08-Jun-16 359 02-Jul-15 05-Dec-16 359 02-Jul-15 05-Dec-16 F3320 Construction Permits Available F3240 Site Establishment F3330 Construction Monitoring for Tailings Facility F3250 Site Work F3340 Continue Construction Monitoring for Tailings Facil ity 80 18-Apr-16 09-Aug-16 F3260 Commissioning 60 12-Sep-16 05-Dec-16 Actual Work Critical Remaining Work Milestone June 2012 Project Schedule 0 02-Jul-15 100 02-Jul-15 24-Nov-15 80 23-Jul-15 17-Nov-15 299 30-Jul-15 10-Oct-16 Source: SNC Lavalin, 2012. www.rpacan.com F3230 Remaining Work Elliot Lake, Ontario, Canada 05-Dec-16* 310 04-Feb-14 Engineering Design for Process Plant Construction Eco Ridge Mine Project 0 21-Jan-14 49010 Procurement Pele Mountain Resources Inc. 13-Dec-13 718 21-Jan-14 0 Engineering Figure 26-1 0 02-Jan-13* 192 02-Jan-13 49E0010 PROCESS PLANT A S O N 26-Sep-12 S50740 Feasibility Study 2014 2015 2016 2017 J F M A M J J A S O N D J F M A M J Jul A S O N D J F M A M J J A S O N D J F M A M J J 380,000 E 381,000 E 382,000 E 383,000 E 384,000 E 385,000 E 5,138,000 N 2012 INDICATED MCB Property Boundary 5,137,000 N 2012 INFERRED MCB 5,137,000 N 26-4 5,138,000 N 5,139,000 N 5,139,000 N N 5,140,000 N 5,140,000 N 379,000 E Figure 26-2 380,000 E 381,000 E INDICATED ~160m drill hole spacing (horizontal projection) - each zone is 7-7.5 mil t MCB - for ~50 mil t IND target = drill 4 zones (”add” ~30 mil t) - for ~40 mil t IND target = drill 3 zones (”add” ~20 mil t) Zone 1 - 28 drill holes Zone 3 - 27 drill holes Zone 2 - 26 drill holes Zone 4 - 31 drill holes INFERRED ~500m drill hole spacing to add ~17 mil t MCB Zone 2 throught 4 - 11 drill holes 382,000 E 0 0.5 1.0 383,000 E 1.5 2.0 Kilometres June 2012 384,000 E 385,000 E Pele Mountain Resources Inc. Eco Ridge Mine Project Elliot Lake, Ontario, Canada Preliminary Proposed Drill Hole Location for Indicated and Inferred Tonnage Targets 2012 Program www.rpacan.com 379,000 E www.rpacan.com 27 REFERENCES Blythe and Associates, 2008: Terrestrial Ecosystems Preliminary Site Characterization Report, prepared for Pele Mountain Resources Inc. Environmental Assessment Panel, “Decommissioning of Uranium Mine Tailings Management Areas in The Elliot Lake Area, June 1996”, Canadian Environmental Assessment Agency, http://www.ceaa.gc.ca/Content/D/B/D/DBD6667F-9B4F-4FB6A55F-3BBD1D8C5AF3/elliot_e.pdf (Accessed June 20, 2012). Canadian Nuclear Safety Commission, 2005: Canadian National Report for the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management, Second Report, Government of Canada. Canadian Nuclear Safety Commission, 2004: 50 years of health monitoring of uranium workers exposed to radon gas – Update of the Eldorado Study. Canadian Nuclear Safety Commission, 2003: A guide to ventilation requirements for uranium mines and mills, Regulatory Guide G-221. CANMET, 1988: Underground Biological In-Place Leaching of Uranium Ore – Phase II Final Report to Denison Mines Ltd. Reference No. CA910-5-0786A. Denison Mines Limited, 1988: Annual Report. Energy Information Administration, May, 2007: Uranium Marketing Annual Report, Official Energy Statistics from the U.S. Government. Fralick, P. W., and Miall, A. D., 1989: Sedimentology of the Lower Huronian Supergroup (Early Proterozoic), Elliot Lake area, Ontario, Canada; Sedimentary Geology, v. 63, p.127-153. Golder Associates, 1983: Stanleigh Mine – Rock Mechanics Study and Revised Mine Layouts. Golder Associates, 2012: Conceptual Design and Preliminary Cost Estimate for the Proposed Tailings Storage Facility Hart, R.C., and Sprague, D., 1968: Methods of Calculating Ore Reserves in the Elliot Lake Camp in Ore Reserve Estimation and Grade Control. Special Volume 9, The Canadian Institute of Mining and Metallurgy. Hedley, D.G.F., Gangal, M. and Morgan, G., 1983: Effect of Pillar Orientation on Stability, Elliot Lake Laboratory, CANMET. International Atomic Energy Agency, Canadian Uranium Production PowerPoint Presentation, http://www.iaea.org/OurWork/ST/NE/NEFW/documents/RawMaterials/ TM%20JOR/31%20talk3-U%20production.pdf (Accessed June 20, 2012). Jefferson, C., Gandhi, S., Ramaekers, P., Delaney, G., Thomas, D., Cutts, G., and Olsen, R., 2005: Geology and Uranium Exploration Technology of the Proterozoic Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 27-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Athabasca Basin, Saskatchewan and Alberta. Geological Survey of Canada, Bulletin 588. Kim, Bo-Hyun, September 2007: Rockmass Classification: Pele Mountain Resources Elliot Lake Project. Prepared by MIRARCO/Geomechanics Research Centre, Laurentian University. Kirkwood, D., McCreath, D., and Peters, T., 1996: Decommissioning of uranium mine tailings management areas in the Elliot Lake area. Report of the Environmental Assessment Panel. Marchbank, A., 1986: Underground biological in-place leaching of uranium ores, Denison Mines Limited Mariano, A. N., 2011, Report on 15 rock samples for Pele Mountain Resources Inc., internal report. MiningWatch Canada, Elliot Lake Uranium Mines, http://www.miningwatch.ca/elliot-lakeuranium-mines (accessed June 20, 2012). Rio Algom Ltd., Denison Mines Inc. and Minnow Environmental Inc., June, 2005: Presentation to Elliot Lake City Council. Activities Associated with the Care and Maintenance of the Tailings Facilities. Robertson, J. 1986: Huronian geology and the Blind River (Elliot Lake) uranium deposits. In Uranium Deposits of Canada, Special Volume 33, Canadian Institute of Mining and Metallurgy. Robertson, James A., 1962: Geology of Townships 137 and 138. Ontario Department of Mines, Geological Report No. 10. Robertson, James A., 1961: Geology of Townships143 and 144; Ontario Department of Mines Geological Report No. 4 (with maps No. 2001-Township 143 and No. 2002Township 144). Robinson, A., Spooner, T., 1984: Post-depositional modification of uraninite-bearing quartz-pebble conglomerates from the Quirke ore zone, Elliot Lake, Ontario. Economic Geology, April 1984, v. 79; no 2; pp. 279-321. Robinson, H.S., 1954: Aquarius Porcupine Option, Twp 143 Sudbury Mining Division – Summary Report of Surface Exploration and Diamond Drilling. Roscoe Postle Associates Inc., 2011: Technical Report on the Eco Ridge Mine Project Uranium and Rare Earths Mineral Resources, Elliot Lake Area, Ontario, Canada NI 43-101 Report, prepared for Pele Mountain Resources, filed on SEDAR/available at www.sedar.com (March 10, 2011). Roscoe Postle Associates Inc., 2011b: Technical Report on the Eco Ridge Mine Project Uranium and Rare Earths Mineral Resources, Elliot Lake Area, Ontario, Canada NI 43-101 Report, prepared for Pele Mountain Resources, filed on SEDAR/available at www.sedar.com (September 7, 2011). Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 27-2 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com Roscoe, S.M. and Steacy, H.R., 1958: On the Geology and Radioactive Deposits of Blind River Region; Proc. 2nd United Nations Conference on Peaceful Uses of Atomic Energy, Paper 222. Saager, R. and Stupp, H.D., 1983: U−Ti phases from Precambrian quartz-pebble conglomerates of the Elliot Lake area, Canada, and the Pongola basin, South Africa, Journal of Mineralogy and Petrology, Vol. 32, Numbers 2-3, pp. 82-103 Saskatchewan Research Council, 2012: Draft Final Report, Metallurgical Recovery for Rare Earth Elements, prepared for Pele Mountain Resources, SRC Publication No. 13197-2C12, February 2012. Scott Wilson RPA, 2007: Preliminary Assessment of the Elliot Lake Project, Ontario, Canada, prepared for Pele Mountain Resources, filed on SEDAR/available at www.sedar.com (October 3, 2007). SENES Consultants Limited, 1997: Comprehensive Study Report, Decommissioning of the Stanleigh Facilities. SGS Lakefield Research, 2011: unpublished metallurgical data. SNC-Lavalin, 2011: Pele Mountain Resources Inc. Eco Ridge Project Capital and Operating Cost Estimate. SNC-Lavalin, 2012: Process Description and Cost Estimation_Concentrate Acid Baking with Floatation_Mar202012. Sprague, D., 1965: Geology and Ore Reserves, Block ‘L’, 41 J – 7 & 8, 1964. Hand written report contained in the MNDMF offices at Sault Ste. Marie. SRK Consulting, 2008, Preliminary Groundwater Scoping Evaluation, prepared for Pele Mountain Resources Inc. Sylvester, P.J., 2007: Mineralogy of Uranium Beds, Elliot Lake Uranium Deposit. Report prepared for Pele Mountain Resources Inc. Inco Innovation Centre, Memorial University, St. John’s Newfoundland and Labrador. Theis, N.J., 1979: Uranium-bearing and associated minerals in their geochemical and sedimentological context, Elliot Lake Ontario. Geological Survey of Canada, Bulletin 304. Van Schmus, W.R., 1976: Early and Middle Proterozoic history of the Great Lakes area, North America. Philosophical Transactions; Royal Society, London, Vol. A280, pp. 605-628. World Nuclear Association, September, 2007: The Global Nuclear Fuel Market – Supply and Demand 2007-2030. Zhang, J., 2012: personal communication via e-mail and telephone. www.asianmetal.com Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 27-3 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com www.metalpages.com www.roskill.com (Roskill Information Services). Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 27-4 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 28 DATE AND SIGNATURE PAGE This report titled “Technical Report on the Eco Ridge Mine Project, Elliot Lake Area, Ontario, Canada” and dated June 20, 2012, was prepared and signed by the following authors: (Signed & Sealed) “Jason J. Cox” Dated at Toronto, ON June 20, 2012 Jason J. Cox, P.Eng. Senior Mining Engineer (Signed & Sealed) “Kathleen Ann Altman” Dated at Lakewood, CO June 20, 2012 Kathleen Ann Altman, Ph.D., P.E. Principal Metallurgist (Signed & Sealed) “Tudorel Ciuculescu” Dated at Toronto, ON June 20, 2012 Tudorel Ciuculescu, M.Sc., P.Geo. Senior Geologist (Signed & Sealed) “Leo Hwozdyk” Dated at Toronto, ON June 20, 2012 Leo Hwozdyk, P.Eng. Consulting Mining Engineer Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 28-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 29 CERTIFICATE OF QUALIFIED PERSON KATHLEEN ANN ALTMAN I Kathleen Ann Altman, P.E., as an author of this report entitled “Technical Report on the Eco Ridge Mine Project, Elliot Lake Area, Ontario, Canada” prepared for Pele Mountain Resources Inc. and dated June 20, 2012, do hereby certify that: 1. I am Principal Metallurgist with Roscoe Postle (USA) Ltd. of Suite 505, 143 Union Boulevard, Lakewood, Co., USA 80228. 2. I am a graduate of the Colorado School of Mines in 1980 with a B.S in Metallurgical Engineering. I am a graduate of the University of Nevada, Reno Mackay School of Mines with an M.S. in Metallurgical Engineering in 1994 and a Ph.D. in Metallurgical Engineering in 1999. 3. I am registered as a Professional Engineer in the State of Colorado (Reg.# 37556) and a Qualified Professional Member of the Mining and Metallurgical Society of America (Member # 01321QP). I have worked as a metallurgical engineer for a total of 30 years since my graduation. My relevant experience for the purpose of the Technical Report is: I have worked for operating companies, including the Climax Molybdenum Company, Barrick Goldstrike, and FMC Gold in a series of positions of increasing responsibility. I have worked as a consulting engineer on mining projects for approximately 15 years in roles such a process engineer, process manager, project engineer, area manager, study manager, and project manager. Projects have included scoping, prefeasibility and feasibility studies, basic engineering, detailed engineering and start-up and commissioning of new projects. I was the Newmont Professor for Extractive Mineral Process Engineering in the Mining Engineering Department of the Mackay School of Earth Sciences and Engineering at the University of Nevada, Reno from 2005 to 2009. 4. I have read the definition of "qualified person" set out in National Instrument 43-101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a "qualified person" for the purposes of NI 43-101. 5. I did not visit the Eco Ridge Mine Project site. 6. I am responsible for the preparation of Section 13 and portions of Sections 17, 25, 26, 27, 28 and 29 of the Technical Report. 7. I am independent of the Issuer applying the test set out in Section 1.5 of NI 43-101. 8. I have previously prepared an NI 43-101 Technical Report for Pele Mountain Resources, titled “Technical Report on the Eco Ridge Mine Project Uranium and Rare Earths, Elliot Lake Area, Ontario Canada”, dated August 19, 2011. 9. I have read NI 43-101, and the Technical Report has been prepared in compliance with NI 43-101 and Form 43-101F1. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 29-1 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com 10. To the best of my knowledge, information, and belief, the Technical Report contains all scientific and technical information that is required to be disclosed to make the technical report not misleading. Dated this 20th day of June, 2012 (Signed & Sealed) “Kathleen Ann Altman” Kathleen Ann Altman, P.E. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 29-2 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com JASON J. COX I, Jason J. Cox, P.Eng., as an author of this report entitled “Technical Report on the Eco Ridge Mine Project, Elliot Lake Area, Ontario, Canada” prepared for Pele Mountain Resources Inc., and dated June 20, 2012, do hereby certify that: 1. I am a Senior Mining Engineer with Roscoe Postle Associates Inc. of Suite 501, 55 University Ave Toronto, ON, M5J 2H7. 2. I am a graduate of the Queen’s University, Kingston, Ontario, Canada, in 1996 with a Bachelor of Science degree in Mining Engineering. 3. I am registered as a Professional Engineer in the Province of Ontario (Reg.# 90487158). I have worked as a Mining Engineer for a total of 15 years since my graduation. My relevant experience for the purpose of the Technical Report is: Review and report as a consultant on mining operations and projects around the world for due diligence and regulatory requirements Engineering study work on projects around the world Planning Engineer to Senior Mine Engineer at three North American mines Contract Co-ordinator for underground construction at an American mine 4. I have read the definition of "qualified person" set out in National Instrument 43101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a "qualified person" for the purposes of NI 43-101. 5. I did not visit the Eco Ridge Mine Project. 6. I am responsible for overall preparation Sections 2, 3, 19, 20, 22, 24, 25 and 26 and am partially responsible for Section 1 and 21 of the Technical Report. 7. I am independent of the Issuer applying the test set out in Section 1.5 of NI 43101. 8 I have previously prepared an NI 43-101 Technical Report for Pele Mountain Resources, titled “Technical Report on the Eco Ridge Mine Project Uranium and Rare Earths, Elliot Lake Area, Ontario Canada”, dated August 19, 2011. 9 I have read NI 43-101, and the Technical Report has been prepared in compliance with NI 43-101 and Form 43-101F1. 10 To the best of my knowledge, information, and belief, the Technical Report contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading. Dated this 20th day of June, 2012 (Signed & Sealed) “Jason J. Cox” Jason J. Cox, P.Eng. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 29-3 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com TUDOREL CIUCULESCU I, Tudorel Ciuculescu, M.Sc., P.Geo., as an author of this report entitled “Technical Report on the Eco Ridge Mine Project, Elliot Lake Area, Ontario, Canada” prepared for Pele Mountain Resources Inc., and dated June 20, 2012, do hereby certify that: 1. I am Senior Geologist with Roscoe Postle Associates Inc. of Suite 501, 55 University Ave Toronto, ON, M5J 2H7. 2. I am a graduate of University of Bucharest with a B.Sc. degree in Geology in 2000 and University of Toronto with an M.Sc. degree in Geology in 2003. 3. I am registered as a Professional Geologist in the Province of Ontario (Reg.# 1882). I have worked as a geologist for a total of 6 years since my graduation. My relevant experience for the purpose of the Technical Report is: Preparation of Mineral Resource estimates. Over 5 years of exploration experience in Canada and Chile. 4. I have read the definition of "qualified person" set out in National Instrument 43101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI43-101) and past relevant work experience, I fulfill the requirements to be a "qualified person" for the purposes of NI 43-101. 5. I visited the Eco Ridge Mine project in November 2010. 6. I am responsible for overall preparation of Sections 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, and 23, and am partially responsible for Section 1 of the Technical Report. 7. I am independent of the Issuer applying the test set out in Section 1.5 of NI 43101. 8. I have previously prepared an NI 43-101 Technical Report for Pele Mountain Resources, titled “Technical Report on the Eco Ridge Mine Project Uranium and Rare Earths, Elliot Lake Area, Ontario Canada”, dated August 19, 2011. 9. I have read NI 43-101, and the Technical Report has been prepared in compliance with NI 43-101 and Form 43-101F1. 10. To the best of my knowledge, information, and belief, the Technical Report contains all scientific and technical information that is required to be disclosed to make the technical report not misleading. Dated this 20th day of June, 2012 (Signed & Sealed) “Tudorel Ciuculescu” Tudorel Ciuculescu, M.Sc., P.Geo. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 29-4 Technical Report NI 43-101 – June 20, 2012 www.rpacan.com LEO R. HWOZDYK I, Leo R. Hwozdyk, P.Eng., as an author of this report entitled “Technical Report on the Eco Ridge Mine Project, Elliot Lake Area, Ontario, Canada” prepared for Pele Mountain Resources Inc., and dated June 20, 2012, do hereby certify that: 1. I am Associate Mining Engineer with Roscoe Postle Associates Inc. of Suite 501, 55 University Ave Toronto, ON, M5J 2H7. 2. I am a graduate of Queen’s University, Kingston, Ontario, in 1976 with a B.Sc. in Mining. 3. I am registered as a Professional Engineer in the Province of Ontario (Reg.# 21150016). I have worked as a mining engineer for a total of 31 years since my graduation. My relevant experience for the purpose of the Technical Report is: Review and report as a consultant on numerous mining operations and projects around the world for due diligence and regulatory requirements. Mines Engineer at Denison Mines, Elliot Lake Property, Ontario. Mine Projects Superintendent at Curragh Resources, Faro, Yukon. Mining Consultant for various base metal mines in Ontario. 4. I have read the definition of "qualified person" set out in National Instrument 43101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a "qualified person" for the purposes of NI 43-101. 5. I did not visit the Eco Ridge Mine Project. 6. I am responsible for preparation of Section 16 and 18 and am partially responsible for Section 21 of the Technical Report. 7. I am independent of the Issuer applying the test set out in Section 1.5 of NI 43101. 8. I have previously prepared an NI 43-101 Technical Report for Pele Mountain Resources, titled “Technical Report on the Eco Ridge Mine Project Uranium and Rare Earths, Elliot Lake Area, Ontario Canada”, dated August 19, 2011. 9. I have read NI 43-101, and the Technical Report has been prepared in compliance with NI 43-101 and Form 43-101F1. 10. To the best of my knowledge, information, and belief, the Technical Report contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading. Dated this 20th day of June, 2012 (Signed & Sealed) “Leo R. Hwozdyk” Leo R. Hwozdyk, P.Eng. Pele Mountain Resources Inc. – Eco Ridge Mine Project, Project #1826 Rev. 0 Page 29-5 Technical Report NI 43-101 – June 20, 2012