solar power Rakesh Bohra Project Engineer, Solar PV Projects, Malpani Group Best Practices before and during Project Execution – Grid connected solar PV Project A solar PV project engineering is well diversified into different segments viz. civil, electrical, mechanical, electronics, data acquisition, weather monitoring etc. The paper tries to incorporate all the desired details, minute yet very important to be taken care of while constructing a solar PV project. I ndia is on verge to solar revolution in coming time. With growing demand of clean energy, the solar energy sector is also growing fast. Project Developer companies are investing a huge finance to fetch the finalized good quality SPV plant. EPC (Engineering Procurement and construction) companies are also not leaving any stone unturned to maintain their credibility and is now getting global maintaining all international practices in SPV Projects. There are lot many things that are essentially to be kept in mind before finalizing the execution and during execution. In solar power plant to get the desired result it is must to know that the design and the execution you are going through is well versed and well done. Preliminary basic things to be kept in concern • SPV Plants are put under following 3 modes in India: JNNSM, State Policies & REC mechanism. • Which policy (international, national, state or other) you want to set up your project in keeping in mind the well availability of Recourses and pay back tariff scheme. • The geography and the terrain you are looking ahead for your future project must be receiving best irradiation preferably > 6.5 kwh/m2/day . Yet depending on the states with favorable tariffs irradiation may be considerably acceptable. We must consider past 10 years weather data before working upon the designs. • We need to keep in mind few very important things viz. approach road to 4 the project plot, distance of nearest power pumping station and the most important is land strata. • It is a known fact that single axis and dual axis tracking technologies provide more than 15% additional generated power. However technical experts choose to operate without both single axis and dual axis tracking systems, simply to avoid any moving part in the plant. They want to avoid the risk of a breakdown ever. It is also a bit costlier however if you have enough space, it is better to install more PV modules to cover the desired power generation. • At times some land brokers buy agricultural land and sell and want to sell it off as agricultural land itself to avoid short term capital gain tax. It is advisable for the potential developers to buy the converted land by sharing the short term capital gains tax with land broker Civil and Structural Engineering 1. Site Topography and Contour Survey • The most important here in this segment is to review the strata of the land and thus design the structure foundations as per it. Say if you are planning a project in rocky terrain, make sure that the excavation for foundation of building or array structure will be easily done up to the designed depth. • If the terrain is undulated or with dune soil strata, it is recommended to properly water bound it and compact the land before starting work. To avoid undulations the soil cutting can be done yet it is a cost effective step. If the arrays are not properly designed on undulated land plant will not generate power effectively. 2. Soil Testing • The foremost step is to examine the soil strength by testing procedures under IS 2720 and then design the mix concrete ratio as per the result. • The concrete shall be designed for moderate to severe exposure condition as suggested in Table no. 3 of IS: 456 -2000. • Generally , soils that are a bit alkaline (pH = 7.5 – 7.9), are slightly corrosive to uncoated steel, and are very slightly corrosive to concrete materials as well, they may adversely effect the life of foundations and Module Mounting structures. 3. MMS Marking and Foundation Work • The first step is to mark true North on the plane and with respect of it only start marking the foundations and structures. • Main step and the first one is to mark the foot/stub with surveying total station, it is highly important to mark and excavate/auger it with accuracy because as if this first step will be wrong the whole structure will be misaligned at the end and there are chances for PV modules may not fit into the structure. • It is always recommended to constantly verify each stub/foot for accurate alignment, horizontal and vertical both. We can use threading technique or Laser technique to avoid inclination of stubs from actual axis. If by mistake some of the stub slightly misaligned, during the energetica india · JUL14 solar power Fig. 1: Misalignment in Stub from The Very Initial stage of Project. concrete casting process itself you can use hammer (ensure to stroke lightly from bottom of stub only) to straighten it back to its position. • Make a habit during project to constantly check and measure the distance (Horizontal and vertical) between stubs is as per drawing or not. Use calibrated spirit level and measuring tape for accuracy. • Some important tests to ensure strength of concrete mixture are strongly recommended viz. cube test , hammer test , slump test etc. strict test procedures as per IS 516-1959 must be followed. With This pull out test of stubs/structure foot is also recommended to ensure the strength of casted stub. • Proper water curing with specific frequency needs to be ensured. 4. Inverter/MCR • Ensure the mix design ratio of foundations of control rooms. • If the Land strata there is comprised with loose/dune soil structure, first go for compaction following rubble filling then put the foundations. • The foundation height of the transformers and inverter rooms must be design in such a way that there may not occur any problem in cable laying and termination. • There must be a wall isolating the inverters to nearby duty transformers. Fig 2: Zinc coating Thickness of MMS testing by Alcometer. • Sliding Ramp must be there to easily take heavy equipments in and out of the room. • The Iron rods to be used in Reinforcement concrete must be specifically TMT and ISI marked, construction grade Fe 500 (PRIMEAR) and must be certified as per IS 1786-2000 Mechanical/ Array Structure: • Make sure that the structure are designed to bear the wind load, dead load, seismic load etc. as per weather history and the design must be assured by software like Staad Pro etc. • It is recommended to ensure if the structure is properly galvanized or not. Use instruments like alcometer to check at site. • Never allow any sort of drilling in array structure specifically if the MMS (module mounting structure) segment is hot dip galvanized, as drilling may allow the inward area to get rusted in future. In case of segment that are cold rolled pre-galvanized you can allow drilling and paint the drilled area with zinc rich paint as the cold rolled sheet has inherent quality where-in the Zinc seeps in and automatically covers the cut portion as the section is very thin .In reference to BS 4652, The thickness of zinc coating is in accordance with the values laid down in BS 729 APPENDIX D The repaired area should in general not be more than 0.5 % of surface area of component. Date Coating Observed (Microns) Spec. Status 21.01.13 132 65 micron (Min) OK 23.01.13 95 65 micron (Min) OK 31.01.13 105 65 micron (Min) OK 06.02.13 156 65 micron (Min) OK • Make sure that the fasteners installed in the structure are as per design i.e. it is strictly to be observed that washers are installed or not, where ever required in case of chances of thermal expansion/contraction spring washers should also be used. Also it is recommended to use stainless steel fasteners instead of GI fasteners. • The fasteners must be tightened with the help of torque wrench only; ensure proper torque, it is strongly recommended to put a mark on the tightened fastener to guide the torque limit and loosening of fasteners in future. • The tightened structure prior to module mounting must be checked with inclinometer to ensure that it is perfectly giving exact PV Module tilt angle and alignment. • It is highly important to confirm that the diagonal alignment of PV array structure is perfect. • Make sure that the free flow of string cables must not be hindered by Bolts in between the purlin , bolts should Concrete Cube Testing Parameters Cube Design Mix Area Cube Made on Date Cube tested on Date Actual Load(N) Strength(N/mm2) Average Status 7 Days 7 Days 7 Days 7 Days 1 410 18,22 2 395 17,56 17,56 Ok 3 380 16,89 1 385 17,11 2 380 16,89 17,11 Ok 3 390 17,33 Cube No. 7 Days M25 Stub Piles Control Room (Footing) M25 10.02.13 10.02.13 17.02.13 17.02.13 Table1: Depicting Concrete Cube Test Under Different Design Ratios energetica india · JUL14 5 solar power be outward in such case, if design does not allow separate cable trays for strings to be laid on. • For any of the Movable electromechanical parts say in Breakers, Transformers, and Isolators etc. Ensure proper greasing /lubricating movable part Electrical Engineering This is the most important segment in a solar PV projects, and requires high attention to work within this segment very since during drawing preparation itself. The performance of the plant is highly dependent on this part. All designs must meet the international standards like IEC 62548 etc. To understand better we are further dividing this category into two parts: DC Electrical and AC Electrical Engineering. 1. DC Electrical Engineering • PV Modules are the Soul of a solar PV plant and are source of DC power, High level of care with specific skilled resources are required while handling and mounting them on the structures. • Ensure the orientation of modules while mounting otherwise at the end it will be difficult to make string connections. • Ensure at initial stage itself if any physical defects (as defined in clause 10.1 of IEC 61215 For crystalline modules and IEC 61646 for Thin film PV Modules) must not be there in PV modules . • It is better to have least inter-connections in DC system. No any joint at string level is recommended. • Make sure that while mounting the modules , the terminals of modules must be kept open. • Ferruling in strings and other cables must be done in R-C-T-P (Row/column/Table/Polarity)Way with practical checking (Continuity checking/Fuse in-out method etc.) and not to rely only on what mentioned in the drawings ;as there are chances of manipulating the string connections by workers during execution. Also Labeling on Module Mounting structures in field must be essentially done. • DC Cable sizing is recommended to be variable for JBs at different distances from inverters to minimize the losses. 6 Fig 3: DC Cable Laying in Trenches and Module Mounting Structrures. • While interconnecting the strings, it is highly recommended to take care of the positive /negative terminal connections as it may cause fuse failure problems afterwards keeping the strings out of generation. • Ensure that exact wattage (indicated on Module spec. sheet) of modules are mounted or not. • For safe side you can also record and compare the initial parameters viz. Vmp ,Imp, Voc , Isc , ff , temp. (Module & Ambient) and Radiation Readings before connecting them on load with the parameters recorded in flash test reports. • Make sure that DC cables are TUV certified and UV protected and designed as per IEC 60364- 712. • All cables must be laid strictly as per drawings and any change during project must be recorded and revised drawings must be made to refer in future whenever required. • Make sure that the DC string cables are properly dressed in well placed trays, they must not be hanging, UV protected cable ties must be used for dressing them properly. • Heat Shrinkable sleeves must be applied to cables at Junction Box end up to lugs. • It is always better to have different color DC cables say Red for Positive and Black for Negative. • The string cables must be laid within PVC Conduits in the trenches. Bricks and granular sand with safety tape should be laid in proper way through the whole trench is a basic practice. • The string combiner boxes must be of IP 65 ratings ,and must be kept at a height of atleast 500 mm above FGL to keep it safe in case of floods and water accumulation. All spare openings must be sealed with Puff seal to avoid rodents to enter into it. • Make sure that only bimetallic lugs must be used at SMB (+/-) termination if the cables and bus-bar bar of dissimillar metals say if cables are of alluminium and bus-bar is of copper, to avoid electrolysis phenomenon. • Module tilt angle recommended in design must be checked with inclinometer. 2. AC Electrical Engineering : • The most important point to remember here is to take extensive care while working with H-Poles at both the ends (Plant side and Substation side). All material used in the system viz Fuses, CT/PT/ Disc insulators, lightening arrestors ,earthling mechanism etc. must be of high quality and of specific ratings as any minor fault in this system may lead huge power generation loss. • It is recommended to ensure the availability of distance protection relay at either side of the project. • Conductors/ earthling wire /Transmission tower angles & Braces must be properly tightened with torque energetica india · JUL14 solar power PV Module Tilt Angle Tilt angle (Measured) Spec. Result 19.8° 20°±1 OK 20.6° 20°±1 OK 20.9° 20°±1 OK 18.1° 20°±1 NOT OK 22.2° 20°±2 NOT OK Fig 4: Module tilt angle measurement (sampling must be done continuously during project execution) ,Structure Must not be in Rectangular form and not in Trapezoidal form. • • • • • • • wrenches. Phase markings must be provided on towers and H-Poles. Isolator and Earth switch must be there inclusive of Gang operating switch on H-Pole switchyard. All CTs (current transformer) & PTs (Potential Transformer) must be tested thoroughly and must be compliance with state utility. All types of relays must be tested prior to commission the plant. The fuses to be used on H-Pole and Grid (11/33/66 KV) must be a pure AlNiCo fuse with specified ratings AS PER DESIGNS. All recording meters must be kept safe in box in the switch yard. Ensure Phase sequence matching at each terminal from substation side to plant side before commissioning itself Ensure if the arrived electrical equipments are as per rated designs or not with reference to SLD. energetica india · JUL14 • It is recommended to have a design mechanism equipped with RMU (Ring Main Unit, SF6 recommended) for big plants to avoid generation loss during failure in cables, transformers or during maintenances as well. RMU is best recommended to provide redundancy during faults and is used to provide uninterrupted power distribution. • It is must to take extensive care while planning the schedule of cable lying in trenches (say which cable will lay first in the same trench), as unplanned laying may impose unnecessary material losses and even create defects in delicate communication cables. • Ensure the availability of testing instruments like IR tester, Micro ohm Meter, Clamp On Meter, Leakage Clamp On Meter, 3 Ph Variac , Phase sequence meter, & DC HV kit. • The most important task is to ensure following tests on transformer to be done strictly as per IEC 60050 Chapter 421 & IS 2026 etc. Viz. Insulation resistance (IR) measurement BETWEEN HV TO LV, LV TO EARTH & HV TO EARTH (IEC 60137) ; VOLTAGE RATIO TEST; Excitation/Magnetizing current test; Magnetic Balance Test; Vector group Relationship; winding resistance etc. • IS 1225-1983 rules and guidelines should be strictly followed during power cables and communication cables lying. LV/HV Cables must be buried at depth of 1.5 b below the ground, with proper brick work. • IS 1225-1983 ;clause 4.2.1.3 Route indicators - Power cable route Indicators should be provided at an interval not exceeding 200 M and also at turning points of the power cable route wherever practicable.’ • Meggering of cables must be essentially done before laying and connecting. • Cables in trenches at road crossings must be laid within Hume pipes (NP-2 grade) only. • Always leave at least 1-1.5 Meter cable loop on both LV/HV Cables in case to be used during any fault in future. • Newly laid HV & LV cables after straight through joint / end termination shall be tested as per IS 1255. • If all HV/ LV and communication cables are to be laid in same trench then the minimum separation distance between HT & LT cables should be 75-100 mm strictly separated by brick wall to avoid total harmonic distortions in signal transmission. Communication cable must be separated by a distance of at least 400 mm and it should also be separated by brick wall. • All LV cables shall be fire resistant and in accordance with IEC 60331. • The depth of the cable trench must be at least 1000-1200 mm. • Try to avoid unnecessary joints in HT Cables as they may get failed during rainy season. Jointing must be done by skilled engineers only. • Lying of cables and dragging them from cable drum must be done giving support (sand/plastic sheet etc.) to the cables at ground to avoid cutting/ scratching of the cables. • If you are using single core cable ,ensure color coding for separate phases • Cable terminations should be done by skilled engineers only, lugs should be properly crimped. In cables with shielding required, the shielding must be done neatly. • Insulation Resistance, High-Pot and contact resistance test must be performed on the Bus Bar of HT breaker. • HV test; IR test; Contact Resistance; BREAKER TIMINGS ETC. tests must be conducted on Breakers Electronics Engineering: • The inverters make should be finalized before confirming its temperature coefficient and sustainability to the weather conditions of the site. Also it needs to be ensured that the vendor‘s post installation service is satisfactory or not. • Inverters to be used must have AC/DC isolation slot. • It is must to check a few main specifications viz. reference voltage, conversion efficiency, IP protection islanding mode (compliance to IEEE 1547 & UL 1741 Safety standards) mechanism etc. • Make sure to install GFDI Kit in inverters (Else As recommended by module manufacturer) so as to avoid PID Loses in future if any. 7 solar power Fig 5: Cable terminations at inverter end. • Make sure to design the inverter rooms outdoor/indoor as per IP protection standards specified for inverters and other equipments. • The AC supply of inverter is meant to be kept un-interrupted during running, hence suitable auxiliary supply system needs to be ensured. You can use UPS systems but the best recommended is to use Inverter output itself to provide auxiliary supply to the inverter (closed loop system, tapping from LT of transformer for auxiliary supply) . • There should be a gland plate at bottom of the inverter to support the cables at bus-bar. For convenience it is recommended to use single core cables. • The communication cables must be CAT 6 OFC. Modes of the cables need to be ensured for different purposes to be used, viz. for CCTV it should be single mode and for SCADA it must be multimode. • The data sending/receiving speed / bandwidth should be proper enough to handle required data transmission on remote access as well. • The jointing /splicing of the OFC cables should be done very precisely and by skilled engineers only, try to avoid the number of joints in OFC cables as much as possible. • Try to avoid the bending of OFC cables as much as possible; it should be done within permissible radii specified by manufacturer only. • Signal cables shall be routed separate from HV, MV and LV cables. Minimum distance should be 600mm to HV and MV cables and 300mm to LV cables. Instrument cables and communication cables can generally be routed together. Signal cables crossing at a right angle with LV cables is acceptable without further segregation. 8 Solar PV projects are always thought to be simplest power projects to construct; people often perform project activities as taken for granted and does not give much attention to the execution work • The saving memory of data should be enough to save at least one year data (CCTV data can be rewrite on every 15 days interval). • SCADA must be designed for string level monitoring; if string is 2x1 type, then separate monitoring should be provided by SCADA System for single string. • The SCADA application enables dynamic configuration, stand-alone and client-server configurations, redundancy for data protection, and historical and real-time trends analysis, as well as advanced alarm management. • The support of such protocols as IEC 61850 and DNP3 are considered an asset if you have to communicate with various electric substation devices. • Weather monitoring station must be well equipped with sensors and gauges like pyranometer (both on horizontal tilt and POA tilt), anemometer, temperature sensor (ambient & module ) , rain gauge ,hygrometer, air mass sensor etc. Earthing /Grounding of AC/DC & Communication System Photovoltaic (PV) power systems are capable of producing hazardous voltages and Currents for decades. To ensure the safety of the public for these extended periods of time, PV systems must be properly designed and installed with respect to earthling/grounding using the highest standards of workmanship. • The overall grid/mesh in DC FIELD must possess earthling value less than 1 ohm as per IEEE-80 equations. • Yet earthling values are dependent on soil resistivity ,soil strata varies at different geographies , even though the design does not recommends the termination of DC Field earthing mesh ;it is highly recommended to terminate the earthing mesh at different places in dedicated earthing pits (earth rods) • Earthing design must follow the practices strictly mentioned in IS 3043. • In case you are using RS-485 cables for communication (say different JBs are in communication loop), ground the shielding at one end only keeping the other end ungrounded so that the noise if any will not travel in a continuous path. • Make sure to provide separate earthing mechanism of String Combiner Boxes, if possible try to provide separate earthing for Power and Communication elements. • It is highly recommended to ground the shielding strip of HT Cable at secondary end and not primary ; where the HT Breaker is connected , so that in case any graund fault occur it may not flow via transformer itself . • Neutral of transformer (where ever star connection is made, mostly secondary) must be grounded to avoid unbalancing of phase voltages and energetica india · JUL14 solar power • • • • • • • • • • • • thus causing major faults.Also the body of transformer must be grounded.Neutral and ground on the transformet can be tied together. Body of HT Breakers along with neutral must also be grounded. Avoid connecting neutrals of different transformers to common ground, it may violate. Ensure dedicated earthling pits to be drawn for inverters and transformers, carbon black paint should be applied where Earth strips are welded /jointed in mesh. All module frames and mounting racks must be properly grounded. The grounding wire must be -- Properly fastened to the module frame to assure good electrical contact. Use the recommended -- type, or an equivalent, connector for this wire. If the support structure is made of metal, the surface of the structure must be electroplated and -- have excellent conductivity. The grounding conductor must then make a connection to earth using a suitable earth ground electrode. We recommend the lay-in lug when grounding. The rack must also be grounded unless it is mechanically connected by nuts and bolts to the grounded PV modules. Proper grounding is achieved by connecting the module frame(s) and structural members continuously using a suitable grounding conductor It is recommended to use maintenance free earthing system inclusive of minimum 15 mm dia. 3000 mm long cu rod. Earthing of SCADA system should be done separately. Separate dedicated earthing Pits are recommended to each inverter in the system. All transmission line lattice towers must be equipped with counter poise earthing system. If simple pole tower structure is there, earthing rod can be buried nearby and connected with the tower leg. Separate dedicated earthling pits must be provided for Main H-Pole in switch yard. The earthling grid must energetica india · JUL14 Fig: 6 Earthing values in permissible limits at various terminals in PV System. be made up of 50X6 MM aluminum strips. • The fencing of switchyard and other transformer yards must also be earthed connected to nearby earthling pit. • All Lightening arrestors must be of ESE (Early Streamer Emission) type and must be provided with dedicated earthing mechanism. Miscellaneous • Before deputing the engineers and supervisors to start work, a firm training should be delivered them regarding what things to be kept in mind regarding each and every respective job. • Every deputed engineer/ in-charge must be having handy drawings during execution. • Any changes deviation from drawing in execution must be done within permissible tolerance limit. • Since solar projects are fast pace projects, proper lighting arrangements should be done for working during night as well. • If the project plot is having good contour with less frequent rainfall, it is recommended to plan well designed Rain Water Harvesting system, harvested water post treated with RO Plant can be used to clean PV Modules. • It is must to construct proper drainage system otherwise Water may accumulate in the plant premises during heavy rain and may cause hazards. Conclusion Solar PV projects are always thought to be simplest power projects to construct; people often perform project activities as taken for granted and does not give much attention to the execution work. This paper very strongly concludes that SPV project execution should not be taken in very lightly. Be specific and précised while finalizing each activity. The points drawn & recommendations made here are not limited to, activity engineers are ought to be much focused and knowledge oriented about their respective field 7 9