OF POWER FAIL.URES ‘- ort of the Commission A Report to the President by the Federal Power Commission July 1967 PREVENTION OF POWER FAILURES An Analysis and Recommendations Pertaining to the Northeast Failure and the Reliability of U.S. Power Systems I I Volume I-Report of the Commission A Report to the President by the cu ,s ,A Federal Power Commission , II July 1967 For sale by the Superintendent of Documents, U.8. Government Printing Office Washington, D.C. 20402 - Pnce II.60 FEDERAL POWER COMMISSION WASHINGTON July 19, 1967 Dear Mr. President: t 1 I .t I / I I We are pleased to transmit our final report on the Northeast power failure of November 9-10, 1965, and our recommendations for enhancing power system reliability in the Northeast and elsewhere in the Nation. This report is in response to your memorandum of November 9, 1965, and the strong interest evidenced by Congress and the public at large in seeking the causes of the failure and the steps necessary to prevent recurrences. It supplements our December 6, 1965 analysis of the power failure and our interim reports of April and November, 1966. At the time of the cascading failure, questions were raised as to whether a fundamental error had been made in permitting utility systems to be so dependent on other systems that the failure of one could jeopardize great areas of the country and conceivably the entire Nation. The various segments of the industry, responsible observers including scientists, technicians, and academicians and interested governmental agencies are in agreement that the concept of coordinated efforts is not only a very successful means of achieving lower cost power, but actually enhances the reliability of participating systems. The key lesson of the Northeast failure and the subsequent cascading outages, we believe, is that these interconnections and the coordination of diverse systems must be strong in order to be effective. I Since November 9, 1965, many of the more easily achieved improvements in emergency equipment, communications and controls have been initiated I I The President The White House Washington, D. C. 20500 The President -2. or completed in the Northeast and throughout the Nation. These steps will be helpful in avoiding a collapse in power supply. Should failures occur, however, those systems which have improved their equipment will be able to restore power more quickly. Attention has also been focused upon providing emergency power for essential services during outages of commercial power. But as constructive and as encouraging as these improvements are, we believe the prevention of crippling power failures requires much more, The Nation's electric power industry consisting of over 3500 utilities of diverse size and ownership-investor-owned companies, municipal and statesponsored systems, rural electric cooperatives, and federal systems-- generally has a superb record of supplying low-cost power on a reliable basis. We are, however, so dependent on continuouselectric power in our urbanized and industrialized society that additional efforts must be made to reduce even further the likelihood of potentially hazardous area-wide power failures. Our studies, in which experts from every segment of the industry assisted, convince us that the prevention of major cascading failures of the type which hit the Northeast in 1965 and very recently in eastern Pennsylvania, New Jersey and the Delmarva peninsula, requires expanded coordination among all utilities on a region-wide basis and a substantial strengthening of transmission systems. We believe implementation of the recommendations in this report--and, as noted above, many are either totally or partially in force today--will substantially assist the industry to achieve these objectives. As you are aware, the Commission earlier this month submitted to the Congress a proposed "Electric Power Reliability Act of 1967." That bill would authorize the FPC to play a role in accomplishing a number of the recommendations contained in this report and, in large measure, the bill rests upon the same studies and analyses which underlie this final report on the Northeast power failure of November 1965. Th In de of . ::I be su me: eat We co1 t ma1 the Mer CO1 ma Fir2 sic thz hi5 to L t The President -30 The Senate Commerce Committee and the House Interstate and Foreign Commerce Committee have demonstrated deep interest in the general problem of reliability of electric service and, accordingly, we are sending copies of our report to the members of those Committees. Additionally, because the report contains some information and suggestions applicable to state and local governments, copies are being sent to the governor of each state. We are grateful for your personal and continuing concern for power reliability, evidenced in so many ways including, of course, references in the State of the Union message and in your Special Message to Congress on Consumer Problems. We are confident that our recommendations will result in more dependable electric service to the Nation's power consumers --a goal that you have articulated, that the Congress has supported, that this Commission and state regulatory bodies must support, that the industry has traditionally given the highest priority and that the public has a right to expect. Respectfully, bee C. White, Chairman Commissioner Charles R. Ross, Commissioner CONTENTS PREFACE....................................................... CHAPTER l-PREVENTION OF POWER FAILURES-HIGHLIGHTS OF THE REPORT................................ CHAPTER P-THE NORTHEAST FAILURE-REMEDIAL ACTIONS AND REQUIREMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . Circumstances of the Failure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Impact on the Public . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Status of Improvements in the Northeast. . . . . . . . . . . . . . . . . . . . . . . . . . . . Equipment Additions and Modifications. . . . . . . . . . . . . . . . . . . . . . . . . Spinning Reserve Practices. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Provisions for Load Shedding. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Service to New York City. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Power for New York Subway . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ServicetoBoston . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Studies of Northeast Network . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Projections of Development by Northeast Utilities. . . . . . . . . . . . . . . . Need for Further Study. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . The Northeast Power Coordinating Council. ............... 1 . . . . . . . . CHAPTER 3-POWER INTERRUPTIONS AND INTERRUPTIONS AVOIDED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Power Interruptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . PJM Power Failure, June 5, 1967 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Reporting Power Failures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Summary of Power Interruptions 1954-1966 . . . . . . . . . . . . . . . . . . . . . . Interruptions Avoided . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . CHAPTER 4-COMPOSITION, INTERCONNECTION, AND COORDINATION OF ELECTRIC SYSTEMS. . . . . . . . . . Composition of the Industry . . . . . . . . . . . . . . . . . . . . Interconnection of Utilities. . . . . . . . . . . . . . . . . . . . . Coordinated Planning and Operation . . . . . . . . . . . . Benefits of Coordination. . . . . . . . . . . . . . . . . . . . . . . The PJM Interconnection . . . . . . . . . . . . . . . . . . . . . . Other Forms of Coordination . . . . . . . . . . . . . . . . . . . Areas for Improving Coordinating Organizations. . Continuing Problems. . . . . . . . . . . . . . . . . . . . . . . . . . Conclusion. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . .. . .. .. .. .. .. , . . . . . . . .. . . . . . . . . . .. .. vii ... VI11 C H A P T E R 5 - K E Y - E L E M E N T S F O R R E L I A B I L I T Y I N THE PLANNING AND OPERATION OF INTERCONNECTED POWER SYSTEMS . . . . . . . . . . . . . . . . . . . . . . We Key Elements in Reliability. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Load Projections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Lead Time for Planning and Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . System Generating Reserve. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Importance of Transmission in Reliability. . . . . . . . . . . . . . . . . . . . . . . . . . . Regional and Interregional Coordination . . . . . . .1 . . . . . . . . . . . . . . . . . . . . Network Stability Analyses. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Direct Current Interconnections. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Problems of Separated Systems. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . LoadShedding . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Relay and Control Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Dependable Communications. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Computer Application in Control. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Restoration of System Services. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Criteria and Standards for Reliability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OperationGuides . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . CentralStudyGroup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41 42 43 43 44 45 45 46 48 50 51 52 53 54 55 55 56 56 41 CHAPTER &-THE ROLE OF TRANSMISSION IN RELIABILITY. . 57 Transmission Objectives. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Bases for Appraisal of Transmission Needs. . . . . . . . . . . . . . . . . . . . . . . . . . . Possible Pattern of Needed Transmission. . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cost of EHV .Transmission . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Economic and Social Justification. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Alternative Considerations for Achieving Reliability. . . . . . . . . . . . . . . . . . Regional and Inter-regional Planning and Cost Sharing. . . . . . . . . . . . . . . . 57 58 58 62 63 64 64 CHAPTER ‘I-OTHER RELIABILITY CONSIDERATIONS. . . . . . . . . . 67 Defense Implications of Power Failures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . Defense Impacts of the Power Interruption . . . . . . . . . . . . . . . . . . . . . . . Power Systems and Sabotage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Vulnerability of Power Systems to Nuclear Attack . . . . . . . . . . . . . . . . . Attributes of Power Systems in Surviving Severe Damage. . . . . . . . . . Fallout Shelters and Power Requirements. . . . . . . . . . . . . . . . . . . . . . . . Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Emergency Power for Essential Public Services. . . . . . . . . . . . . . . . . . . . . . . Equipment Reliability. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Research and Development Needs. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Capacity Requirements in Relation to Manufacturing Capability. . . . . . . Preservation of Aesthetic Values. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Technical Talent for the Industry. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Observations on Power Systems of Other Countries. . . . . . . . . . . . . . . . . . . International Interconnections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Interconnected Operations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Examples of Particular Systems and Practices. . . . . . . . . . . . . . . . . . . . . PowerFailures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . International Technical Exchanges . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Comparability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67 67 67 68 68 69 69 69 71 72 72 74 75 76 76 76 78 79 80 80 Fl Fl k’ Appc *pw v6lux 2-PC CHAPTER 8-THE COMMISSION’S RESPONSIBILITIES AND ACTIVITIES TO IMPROVE COORDINATION AND RELIABILITY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . The Commission’s Responsibilities. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . FPC Activities in Coordination. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Further Commission Assistance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . CHAPTER 9-CONCLUSIONS AND RECOMMENDATIONS . . . . . . . . Formation of Coordinating Organizations. . . . . . . . . . . . . . . . . . . . . . . . . . . Interconnected System Planning. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Interconnected System Operating Practices. . . . . . . . . . . . . . . . . . . . . . . . . . Interconnected System Maintenance Practices. . . . . . . . . . . . . . . . . . . . . . . Criteria and Standards. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Defense and Emergency Preparedness. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Manufacturing and Testing Responsibilities. . . . . . . . . . . . . . . . . . . . . . . . . . Increased Need for Technical Proficiency. . . . . . . . . . . . . . . . . . . . . . . . . . . . Power System Practices in Other Countries. . . . . . . . . . . . . . . . . . . . . . . . . . ACKNOWLEDGMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Surveys of the Reliability Characteristics of U.S. Power Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Appendix A-General Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Criteria for General Surveys. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . GeneralSurveys . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Appendix B-Mod@ations to Northeast Power Systems Since November 9, 1965. . Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Relaying . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Emergency Power at Generating Stations . . . . . . . . . . . . . . . . . . . . . . . . . . . . Communications, Instrumentation, and Data Transmission. . . . . . . . . . . . Spinning Reserves. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . LoadReduction........: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Appendix C-Major Coordinating Organ&ations. . . . . . . . . . . . . . . . . . . . . . . . . . . . Mechanisms for Coordination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Members of Major Formal Power Pools. . . . . . . . . . . . . . . . . . . . . . . . . . . . . Members of Major Power Planning Groups . . . . . . . . . . . . . . . . . . . . . . . . . . Appendix D-Impact of Power Failures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . General Impacts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . AgencyActions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Legislative Proposals . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Appendix E-Summary of Larger Power Interruptions 19561967. . . . . . . . . . . . . . Volume II-Report of the Advisory Committee on Reliability of Electric Bulk Power Supply, Separate Volume. Volume III-Studies of the Task Groups on the Northeast Power Interruption, Separate Volume. i. TABLES l-Major Power Failures Which Have Occurred Subsequent to the Northeast Failure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-Power Service Interruptions Reported ‘in Accordance with FPC Order No. 331 through June 12, 196?. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-Regional Distribution of Electric Utilities-1965, By Function. . . . . . . . . . 2 4---Regional Distribution of Electric Utilities-1965, By Size of. Energy Requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . .‘. . . . . . . . . . . . . . . . . . . . 5-Statistics on Electric Po.wer Systems in Other Countries . . . . . . . . . . . . . . . . A-l-Stability Studies. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-2-Comparison by Regions of Number of Systems Using Automatic Emergency Load Reduction Programs. . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-S-Comparison by Regions of Automatic Emergency Load Reduction Programs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-+--Emergency Load Reduction Program, by Regions. . . . . . . . . . . . . . . . . . A-5-Load & Generation Emergency Dropping Practices, by Regions. . . . . . A-6-Spinning Reserve Practices, by Regions. . . . . . . . . . . . . . . . . . . . . . . . . . . A-7-Means of Obtaining Emergency Startup Power, by Regions . . . . . . . . . . A-8-Practices & Plans for Use of Digital Computers, by Regions. . . . . . . . . . B-l-Emergency Power Supplies. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-2-Communication, Instrumentation, and Data Transmission. . . . . . . . . . . B-S-Spinning Reserves-Northeast Power Systems. . . . . . . . . . . . . . . . . . . . . . B-+--Load Reduction Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . D-l-Selected Essential Services Requiring Emergency Electric Power. . . . . . D-P-Port of New York Authority Emergency Electric Power Equipment. . . . D-J-State Codes and Regulations for Emergency Power. . . . . . . . . . . . . . . . . E- 1-RbumC of Power Interruptions 1954-l 966. . . . . . . . . . . . . . . . . . . . . . . . 23*-a 32 76 102 122 122 123 129 132 148 147 156 160 162 163 173 179 186 194 FIGURES I l-Power Failure in the Northeast . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-Service Area Separations Northeastern Power Failure, November 9, 1965 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3*-15,000 kw Gas Turbine Generating Unit for Peaking and Station Startup-Long Island Lighting Company’s Port Jefferson Station. . . . 4*-Emergency Standby Power-608 Kw Diesel Set at Consolidated Edison Company’s Hudson Avenue Generating Station. . . . . . . . . . . . . . 5-Major Transmission Lines and Generating Stations. . . . . . . . . . . . . . . . . . . GMember Systems of Northeast Power Coordinating Council. . . . . . . . . . . . 7-PJM Area Power Failure-June 5, 1967 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-PJM Transmission Network. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-Service Areas of Electric Utility Industry. . . . . . . . . . . . . . . . . . . . . . . . . . . . lo-National Power Survey Regions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 l-Growth of Interconnected Systems Operating in Parallel. . . . . . . . . . . . . . 12-Major PowerPools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13-Principal Power Planning Groups in U.S., March 1967. . . . . . . . . . . . . . . 14-Electric Energy Requirements 1960-l 980. . . . . . . . . . . . . . : . . . . . . . . . . . . 15-Response of Interconnected Network Power Flow to Outage of TVA Paradise Steam Plant. . . . . . . . . . . . . . . . :. . . . . . . . . . . . . . . . . . . . . . . . . . 16*-Model of North Terminal of Pacific Northwest-Southwest Direct Current Intertie . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17-Generation and Frequency Variations November 9, 1965. . . . . . . . . . . . . 18-Automatic Load Shedding. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19*--ProtectiveRelay . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . PO-Energy Control Center fo Consolidated Edison Co. in New York City. . . . Pl-Possible Pattern of Transmission by 1975. . . . . . . . . . . . . . . . . . . . . . . . . . . PP-Projected Investment in EHV transmission . . . . . . . . . . . . . . . . . . . . . . . . . . * Photograph. 7 8 9 13 17 18 24 25 33 34 35 36 38 42 47 48 49 51 52 53 60 63 SC 24-Ste 25-PO1 26Tn 27-Em D-1-c E-l-PC * Ph Page Page 23*-500 kv Transmission Tower on BPA Portion of Pacific NorthwestSouthwest Intertie . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B&-Steam Turbine Generators. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25-Power Transformers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I . . 26-Transmission Lines in Western Europe. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27-European Power Pools. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . D-l-Questionnaire Used by Business & Defense Services Administration. . . E-l-Power Interruptions, 19541966. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32 76 i. 102 122 E 122 123 : 129 f; 132 , 140 e 147 156 i 160 ; 162 163 173 179 i 186 L 194 * Photograph. 1,: 7 8 I 9 13 17 18 24 25 33 34 35 ; 36 38 \ 42 4 7 t, 1 48 49 / 51 52 53 60 63 65 73 73 77 78 176 197 PREFACE This report summarizes more than a year of intensive investigation following the Northeast power failure of November 9, 1965. Many utilities, agencies of Federal, State, and local governments, and committees of Congress have joined in reviewing the Northeast failure and its significance in relation to the reliability of the Nation’s electric power supply. The area in which the failure occurred has been studied intensively and utilities in every part of the Nation have been reviewing practices in power system planning and operation in the light of the lessons revealed by the Northeast failure. The report summarizes the actions taken by utilities in the Northeast and elsewhere in the Nation and the need for further improvements. It reviews the history of major power failures, analyzes the elements which compose a reliable generation and transmission system and their functions, discusses the necessity for reliability and its value, projects an accelerated scale of development for EHV transmission lines, and discusses important elements in coordinated power system planning, including effective regional organizations, lead time for planning and construction, sound load projections, environmental effects of system facilities and the recruitment of technical talent to meet the unparalleled challenges of modern power system technology. The report discusses practices in other countries having well-developed power systems, and considers the relation between cascading failures and the survivability of United States power systems under enemy attack. The supply of bulk electric power is considered to include the generation of electric power and its transmission at high voltage to major substations near load centers. Reliability in the distribution of power from substations to customers is not included. As used in this report, the term “reliability” means the ability of a utility system or group of systems to maintain the supply of power. Reliability is gauged by the infrequency of interruption, the size of the area affected, and the quickness with which the bulk power supply is restored if interrupted. For many reasons it is not possible to provide an infallible source of power, but the probability of interruption and the area affected can be greatly minimized by following sound practices in planning and operating power systems. The Commission’s report to the President, December 6, 1965, on the Northeast Power Failure l contains a detailed account of the cause and the sequential events which resulted in the widespread separation and collapse of power systems on November 9, 1965, and presents recommendations for preventing recurrence of major failures. Although not republished as a part of this report, it is a principal reference. The report herewith is in three volumes. Volume I is the report of the Commission. Staff work for the report was carried out under the direction of F. Stewart Brown, the Commission’s Chief Engineer and Chief Df the Bureau of Power. Volume II is the report of the Commission’s Advisory Committee on the Reliability of Electric Bulk Power Supply. This Committee was established by the Commission by Order dated February 9, 1965, “to review and investigate the problems in assuring the reliable supply of bulk power” and to “recommend general criteria and guidelines for system planning and operation and maintenance of facilites to assure the reliability d bulk power supply * * +.” Volume III summarizes the Task Group studies performed under the general guidance of the Federal Power Commission and its Advisory Panel for the Northeast Power Interruption. The studies include an examination of the strength of the Northeast transmission network under assumed severe disturbances, an appraisal of needed network additions, and a detailed analysis of the collapse in power supply in the eastern New York and New England “island’ area which occurred progressively over a period as long as 12 minutes. The Commission is greatly indebted to many persons and organizations for their cooperative assistance in the studies and assembly of information on which the report is based. Acknowledgment of those who have 1 “Northeast Power Failure November 9 and 10, 1965-A report to the President by the Federal Power Commission, December 6, 1965”-Superintendent of Documents, U.S. Government Printing Ofice, Washington, D.C.-Price $1.00. been of principal help to the Commission and its staff are included in the separate volumes of the reporf as follows: . Members of the Commission’s Executive Advisory Committee and of the six Regional Advise Committees, in “Acknowledgments” following Chapter 9 of this Volume. . Members of the Commission’s Advisory Committee on Reliability of Electric Bulk Power supp in Volume II. . Members of the Commission’s Advisory Panel on the Northeast Power Interruption, and members Task Groups associated with the Panel, in Volume III. . Those who participated with the Commission in the immediate weeks following the Northeast pow failure are acknowledged in the Commission’s report to the President, December 6, 1965, on tht The masz Northeast Power Failure. which cast States and people, tout Of power s 85-year his1 of the natio: sider wheth areas. If so: them? If &II quickly? Su ing review utility oper; made by II sponded to tion and car As our PI of the faiIu transmissior transmissior too weak to network wa and under t! to function ties separate of the coun several eIec areas, loads SO that the could not these areas control5 to ing to full 1~ in the Nortl tion in time open to the peased. i Because I quate starts of service w l FPC Reg and Interim xiv ; of the report ional Advisory I Lower Supply,; nd members ofi CHAPTER 1 I ortheast power #, 1965. on the THE PREVENTION OF POWER FAILURES-HIGHLIGHTS OF THE REPORT ’ The massive power failure of November 9, 1965, which cascaded across the northeastern United States and Ontario, Canada, affecting 30 million i people, touched off the most intensive examination of power system planning and operation in the / 85-year history of the electric power industry. All / of the nation’s utilities have been challenged to con! sider whether similar failures could occur in their 1 areas. If so, what steps should be taken to prevent them? If they should occur, could power be restored quickly? Such questions have demanded a searching review of the fundamentals of interconnected 1 utility operation. Rigorous self-analyses have been made by many utilities and the industry has responded to the Commission’s review with coopera’ tion and candor. I As our previous reports 1 indicated, the cascading : of the failure of November 9 occurred because the transmission network in the Northeast and the transmission connections to the south and west were too weak to withstand the massive power surge. The i network was not planned to withstand such a surge, , and under the impact, it became unstable and ceased \ to function as an integrated whole. Transmission ties separated, isolating the Northeast from the rest I of the country and subdividing the Northeast into several electrical “islands”. In most of the island areas, loads were greater than generation-so much so that the automatic response of the generators I could not restore equilibrium. Utility systems in t these areas were not equipped with automatic ontrols to drop loads temporarily before rebuild‘ng to full load. The numerous utility control rooms En the Northeast were unable to exchange informaItion in time to take such emergency actions as were jopen to them. As a consequence, power generation jceased. Because many of the utility systems lacked adeuate‘startup resources and procedures, restoration f service was delayed for several hours and in parts 1 FPC Report to the President on December 6, 1965, nd Interim Reports in April 1966 and November 1966. of New York City for periods up to 13 hours. While much public loss and inconvenience were caused by the outage, general tragedy was averted by the ability of radiostations having emergency power to inform the public, by the good sense of hundreds of thousands of people and by fortunate weather conditions. The initial reaction to the Northeast failure was one of general disbelief that such an incident could happen. The outstanding record of service of electric utilities in the United States certainly had given little suggestion that a widespread failure of this magnitude could occur. The sequence of difficulties which ensued, exposing the types of deficiencies enumerated herein, appeared contrary to the performance of utilities in meeting hundreds of emergencies that have arisen year after year on power systems everywhere in the United States. In perspective, it should be recognized that the electric utility industry is confronted with the most difficult challenge of any of the public utility services in assuring the continuity of supply. There are no ways to hold power demands in waiting, no electric storage pools and no ways of providing partial service to overcome unexpected peak demands or suddenly to fill gaps in equipment failures. These must be met by more difficult means and peak demands must be served instantaneously and in full. Electric power generating machines throughout the nation must work together in split-second synchronism. The industry responds to emergencies with alacrity and dedication. The industry has good reason for pride in its overall record of service, in its growth achievements, and in its discharge of a vital public service responsibility that must be virtually unfailing. The problems before us do not stem from any lack of desire of any individual utility to do its best. They are generated in part by the dynamic growth of the industry and the difficulties of keeping pace in all respects with these demands. They con1 tern primarily the requirements for greater COordination among electric utility systems. Although some improvements undertaken by the utilities since the 1965 failure have not been completed because demands for equipment, such as emergency power units, temporarily exceeded manufacturers’ capabilities, the industry has gone far to protect its own equipment from damage, to be prepared for speedier restoration of service, to improve communications to and from the various utility control rooms, and to make plans for temporary dropping of less essential loads (load shedding) to avoid a complete power failure in case of similar crises. Also, utilities in the Northeast and in many other locations throughout the nation have proceeded independently or in cooperation with the Commission as requested in numerous studies and surveys relating to reliability. The critical remaining needs which many utilities are striving to meet are to develop mechanisms for effective coordinated planning, design, construction and operation of generation and transmission facilities. The challenges here are as much institutional as technical: there are hundreds of large and small utilities, privately, publicly, cooperatively and federally owned. The technology of reliability, however, ignores ownership and calls for a high degree of coordination in planning and functional cooperation by the diverse managements in carrying out their bulk power supply responsibilities. Bulk power systems consist of generating and transmission facilities. The individual pieces of equipment are fallible and components will be forced out of service from time to time. Major equipment outages, however, should not result in service interruptions if the many generating plants of a large group of systems are joined by strong transmission lines which enable each generating unit to instantly make a contribution. These small individual contributions can, in the aggregate, offset the outage. Adequate generating reserves must be at hand to take the place of failed equipment until it is repaired, but without strong interlocking transmission systems, even large and costly amounts of reserve may not prevent interruptions. Transmission lines designed with adequate reserve capacity, which is what we mean by strong ties, can sustain the impact of sudden changes in generation or load, such as the power surge of November 9, without becoming unstable and opening. Well-planned systems with adequate automatic controls and interconnected over a wide area, result in a high quality 2 of electric service with little fluctuation in system frequency or voltages-a characteristic important to many industrial processes. Beginning with various local transmission links among utilities prior to World War II, interconnection has continued to progress, largely through the voluntary efforts of utilities, to the present pattern in which the transmission systems of all principal utilities have become interwoven into a continuous transmission network which nearly blankets the United States and includes part of Canada. However, many of the links are weak, and additional ties are needed. The underlying theme of the report of the Commission’s Advisory Committee on the Reliability of Electric Bulk Power Supply (Volume II of this report) is that the transmission capacity of the interconnected network must be adequate. The report states : Transmission must be recognized as the principal medium for achieving reliability, both within a system and through coordination among systems. It is the cohesive force which ties together power systems. Cascading power failures are usually the result of insufficient capability within the transmission links of a system or group of systems to withstand the sudden demands placed upon them by reason of disturbances arising within or outside the system. Our studies bear out the views of the Committee. The Northeast power failure clearly revealed that systems and interties between systems must have ample reserve transmission capacity to supply power demands much in excess of normal load requirements. Seventeen of the 20 major failures which have occurred since November 9, 1965, have also been cascading failures, each the result of interconnections which were too weak to cope with the particular system disturbance. Progress toward stronger transmission systems must be accelerated if all utilities in the United States are to be able both to provide and receive strong emergency support. If EHV transmission lines are built by 1975 to the level of development suggested in this report, a rough estimate of the added investment is $8 billion, which is about 12.5 percent of the anticipated expenditures for all power facilities over the same period. This amount is about $3 billion more than utilities apparently contemplate spending, assuming reasonable extrapolation of recently announced planned rates for EHV construction. The annual cost of a $3 billion increment of investment, which might be considered to represent the prin be1 ing in c erat ject vey E can mu by tier tict ( sign bili the hsu chi nir em we OII i n ml fo1 thl Tl mc the t0 enI Uti rel wi A b ar er ax U! er tl IT ir fa re, pl; ac TC principal cost of obtaining greater reliability, would be less than 2 percent of the total cost of supplying electric power in 1975. The added investment in coordination and transmission might also accelerate the achievement of the economic gains projected in the Commission’s National Power Survey published in December 1964. Effective coordination of bulk power facilities cannot be achieved by mere interconnection. It must encompass mutual review of load projections by utilities in each region, coordination in construction proposals, and agreement upon operating practices and safeguards. Coordination and interconnection can produce significant benefits in addition to increased reliability. When adequate networks are fully developed, the economy of bulk power supply will be enhanced through regional and interregional exchanges of capacity and energy, sharing of spinning and standby reserves, and the transfer of emergency power supplies for meeting unusual weather conditions and other contingencies. Economy and reliability are closely associated objectives in the supply of electric bulk power, but reliability must have priority if any conflict occurs. The early establishment of strong organizations for regional planning and operation is essential to the orderly growth of the electric utility industry. The Advisory Committee on Reliability recommends: the establishment of effective organizations and procedures to implement the necessary coordination among planning, engineering and operating personnel of the participating utilities, with assigned responsibility to review, adjudge, report upon, and effectuate utility plans and practices within the area affecting bulk power system reliability. A regional coordinating organization was created by electric utilities in the Northeast early in 1966 and in the East Central area in 1967. Although still engaged with some of the problems of organizing and programming, these councils are directing useful efforts in the analysis of bulk power generation and transmission to improve reliability through coordination. Fears are frequently expressed that coordinating mechanisms would encroach upon prerogatives of individual management. Such concerns, we believe, fail to take into account that full management responsibility can be achieved only by joining in planning which extends beyond the boundaries of a corporate or other entity, an area or even a region. To the extent there is such encroachment, we be%7-781 O - 6 7 - 2 lieve it must be balanced against the legitimate system, area, regional and national interest in reliable service. No management can avoid its share of the responsibility for building adequate interconnected transmission systems. Coordinated planning and operation must not only be extended more broadly among the 437 investor-owned utilities which furnish nearly 80 percent of total electric needs, but must bridge as well the differences among the four segments composing the industry’s.total structure. Reliability and economy should be available to all users of bulk electric power, regardless of the nature of the system serving them. At the same time these users must contribute their proper share of the cost. Useful mechanisms have evolved for coordinating the planning and operation of systems in some areas. Others have not matured to levels of optimum effectiveness. Some are too limited in purpose to serve adequately as instruments of coordination. We are mindful, however, of the progress achieved and the opportunity for expanding the scope and usefulness of these existing mechanisms. We do not suggest setting them aside, but rather building upon them as steps toward greater accom. plishments. In accordance with section 202 (a) of the Federal Power Act, the Commission has endeavored to promote and encourage the interconnection of systems for the enhancement of both economy and reliability of electric power supply. We beheve the industry has been stimulated by the efforts of the Commission “to promote and encourage voluntary interconnection.” Accelerated progress, however, will be needed to satisfy the demands in both quantity and quality of service over the next decade. Substantial economic gains can be achieved through coordinated planning and operation spanning a large area or region.2 Close coordination within regions is the most practical approach and the foundation for achieving bulk power supply reliability for the nation. However, interregional coordination is a further necessary step. The Advisory Committee on Reliability recognizes this need and suggests : The establishment of a council on power system coordination made up of top-level representatives from each of *In the Commission’s National Power Survey, the 48 contiguous states are grouped into 16 areas and 8 regions. In the current updating of the National Power Survey, six regions have been delineated. 3 the nation’s area OF regional coordination groups. The purposes of such a body would be primarily to exchange and disseminate information on regional coordination practices to all of the regional organizations, to communicate to the public and regulatory and governmental authorities information on coordination, and to review, discuss and resolve matters affecting interregional coordination. . We concur in the Committee’s view. Also we believe there would be much merit in coordination of investigative efforts by the industry to meet some of the challenging opportunities for improving power system facilities and operations. Electric power use by 1985 is expected to be more than three times that of today. Supplying these demands economically calls for increasingly larger generating unit and plant capacities and correspondingly stronger transmission systems. All, of course, must be in keeping with the density of the load and other factors which may be of significance in a particular area. Fortunately, the technology is now available or can reasonably be anticipated, which will permit such increases with continuing gains in both economy and reliability. . We are concerned that delays from many causes are adding years, not months, to planning and construction schedules for major generation and transmission facilities. The nation may be confronted with a serious impairment in the sufficiency and dependability of its electric supply if prompt recognition is not given to these potential delays. Unexpected demands, particularly those influenced by prolonged summer heat storms, have already encroached on normal margins of reserve generating capacity in some areas. A few areas are faced with a possible curtailment of service in 1967, such as happened in the St. Louis area last summer, if extreme weather occurs, particularly if one or more large generating units experience a,forced outage during the peak period. Sufficient generation is at hand in neighboring systems to overcome the deficiency, but transmission strength is insufficient in many cases to move all available surplus within safe line loading limits. Such limitations in generating capacity and the inability to utilize all available generating resources in neighboring areas to benefit marginal situations because transmission is inadequate, are of serious concern. Our emphasis on accelerating the construction of high capacity, high voltage lines does not indicate lack of concern for the appearance and location of power system structures. We believe that much further greater attention must be given to the aesthetics of public service facilities, and that the public should be brought into the planning process as early as possible. The present severe economic and technical limitations on placing extra-high-voltage transmission lines underground demand an intensification of research in this area. In addition, major efforts are needed to improve overhead transmission line appearance, to select inconspicuous routings, and to make the best use of existing rights-of-way. We recognize that the location of generating stations affects the pattern of transmission. To the extent that large generating plants are placed closer to load centers, the average distance for moving bulk power supplies can be reduced. However, the requirements for cooling water, the difficulties of acquiring suitable close-in sites, the increased seriousness of air pollution in densely populated areas, and the favorable economics of some mine-mouth locations will tend to limit the number of plants that can be placed at load centers. Thus the supply of bulk power to many centers will still require major transmission. More fundamentally, these considerations do not lessen the need for an effective overlay of high voltage lines to improve the reliability of bulk power supply. Achieving adequate reliability throughout the nation will engage not months, but years of concerted planning and construction. We believe the 12 recommendations which follow go to the heart of the problem. They are drawn from the recommendations, 34 in all, which are set forth in detail in chapter 9. The supplemental recommendations concern numerous improvements in the planning, operating, and maintenance of interconnected systems, defense emergency preparedness, responsibility in the manufacturing and testing of equipment, and the challenge to technical talent. In summary we conclude and recommend, principally, that : 1. To the extent they do not now exist, strong regional organizations be established throughout the nation, for coordinating the planning, construction, operation and maintenance of individual bulk power supply systems; and that representation of systems be by groups, where feasible, to facilitate progressive improvements in coordination. 2. A council on power coordination be established, made up of representatives from each of the nation’s regional coordinating organizations to exchange and disseminate informa- B / i r 3. 4. 5. 6. 7. c recof rinI0% ugh$ lantePlY F ms be litate 31: !stabeach gani‘ma- tion on regional coordinating practices to all of the regional organizations, and to review, discuss and assist in resolving matters affecting interregional coordination. A central study group or committee be established to coordinate industry efforts in investigating some of the more challenging problems of interconnected system development. Early action be taken to strengthen transmission systems serving the Northeast. Transmission facilities be critically reviewed throughout the nation, and planning and construction of needed additions be accelerated on schedules which will provide ample transmission capacity to meet a broad range of potential needs for both reliability and economy as they occur. In estimating future loads, full attention be given to economic trends, potential weather extremes, and growth in special uses of electricity in each load area. Utilities solicit the full participation of interested parties at an early date in the resolution of problems relating to the location and environmental effects of new facilities. 8. Utilities intensify the pursuit of all opportunities to expand the effective use of computers in power system planning and operation. 9. Coordinated programs of automatic load shedding be established and maintained in areas not so equipped, to prevent the total loss of power in an area that has been separated from the main network and is deficient in generation. Load shedding should be regarded as an insurance program and should not be used as a substitute for adequate system design. 10. Utilities complete a thorough reassessment of their needs for emergency power for system operation. 11. All levels of government appropriately establish requirements for emergency power sources for services essential to the safety and welfare of the public, and ensure the availability of such facilities. 12. Utilities cooperate with appropriate public officials and customers in planning and maintaining customer standby facilities to assure service to critical loads in the event of emergency. CHAPTER 2 THE NORTHEAST FAILURE-REMEDIAL ACTlONS AND REQUIREMENTS Circumstances of the Failure The Northeast power failure began at approximately 5 : 16 p.m. on November 9,1965, and by 5 : 30 p.m. most of the northeastern United States and much of the Province of Ontario, Canada was in darkness. Power was interrupted for periods ranging from a few minutes in some locations to as much as 13 hours in some parts of New York City. The failure encompassed 80,000 square miles (figure 1) , and directly affected an estimated 30 million people in the United States and Canada. It was by far the largest power interruption ever experienced in the United States. It dramatized the dependence of the nation on electric power, and emphasized the responsibility of the electric utility industry for providing virtually unfailing service. Under its statutory responsibilities and in response to the urgent request of the President, the Commission began its investigation immediately. The Commission’s initial report, published December 6, 1965, pinpointed the initiating cause of the POWER FAILURE IN THE NORTHEAST November 9-10, 1965 Generalized Areas of Outage and .iome restorntrons over lapped the boundaries shown. I5 mmutes to 3 hours 8. hours to 13 hours FIGURB 1 interruption as the operation of a backup relay on one of the five main transmission lines taking power to Toronto from Ontario Hydro’s Sir Adam Beck No. 2 Hydroelectric Plant on the Niagara River. This relay, which was set too low for the load which the line was carrying, disconnected the line. This caused the flow of power to be shifted to the remaining four lines, each of which then tripped out successively due to overloading. With the opening of these lines, about 1500 megawatts of the power being generated at Ontario’s Beck Plant and the Niagara Plant of the Power Authority of the State of New York, which had been serving the Canadian loads in the Toronto area, reversed its flow and attempted to get to the Canadian loads through the only remaining U.S.-Canadian tie at Massena. This overloaded the Massena intertie and it opened, thus completely isolating the Canadian system. As a result, a total flow of something over 1700 megawatts to Canadian loads was blocked, and the power surged into the United States. These flows exceeded the capability of the transmission system in New York and the interconnections to the south, and triggered the breakup of the systems in Northeastern United States. The power failure .had three stages. The first encompassed the initial shock to United States systems from the sudden thrust of the 1700 megawatts of power from Canada. A widespread separation of systems through New York and New England followed in a matter of seconds. If this had been the end of the disturbance, the power failure would have touched only one-third of the customers who were eventually affected, and none in southeastern New York and New England. The second stage marked the attempted survival of the electric utilities in eastern New York and New England which had been separated from the rest of the interconnected systems of the United States. Isolated from other systems, these “islands” (see\ figure 2) generally were left with insufficient generation to meet their loads. Power generation 7 AREAS OF SEPARATION AT 5:17 PM 1. 2. 3. 4. 5. Ontario Hydro System St Lawrence Oswego Western New York Eastern New York - New England Maine and Part of New Hampshir .3ERvlcE AREA SEPARATIONS NORTHEASTERN POWER FAILURE NOVEMBER 9,1965 FIGURE 2 in virtually all of this area except Maine and eastern New Hampshire (area 5, figure 2) ceased within a matter of three to twelve minutes. During this period, system operators attempted to interpret the information provided by their control center instruments, some of which were operating erratically, and to determine, with relatively little information, and in some cases with inadequate communications, the extent of the interruption and the appropriate course of action each should take to keep his particular system functioning. The third stage of the failure-the restoration of power-was prolonged in some areas of the region, particularly in New York City and Boston, because power was not readily available to restart the steam-electric generating units. Moreover, substantial delays were encountered in energizing the high-voltage underground transmission networks. The power failure revealed deficiencies in equip ment, system planning, operation and maintenance, and preparedness for emergencies. There were problems with control equipment; there was a more-or-less lack of auxiliary or emergency generating equipment; many transmission interties proved to be inadequate; there were few welldeveloped plans for quickly balancing load and generation (load shedding and, in special cases, disconnection of generation) ; and provision for quick restoration of service in the event of system failure was often inadequate. The utilities in the affected area have corrected or have made plans to correct 8 1 many of these deficiencies. Some of the measures that have been taken to meet the obvious needs are summarized later in this chapter. A more detailed summary of actions by individual utilities is contained in appendices A and B. Many additional studies are underway or planned to find solutions to the more complex problems related to the re- 1 liability aspects of systems design and operation. These are generally carried on as a part of normal iI procedures, but the Northeast interruption has led to a new recognition of their importance and urgency. The deficiencies revealed by the Northeast incident are the basis for most of the recommendations contained in chapter 9 of this report. Many of these recommendations, however, have general applicability to the development of power systems in other parts of the United States and are not limited to the Northeast. ! Impact on the Public The Northeast power failure affected the most densely populated area of the nation. It caused inconveniences to about 30 million people and estimates of economic losses run as high as $100 million. It left more than 800 hospitals without commercial power, and in some cases, particularly in New York City, no standby sources of power were availabie. In some sections water and sewerage services were interrupted. Fortunately, there were few fires during the interruption. Many persons were confined 16 for long periods in darkened elevators stuck bef tween floors, and in subway trains stranded between stations. Economic losses and impact on the public welfare were greatly lessened because the failure occurred on a mild moonlit evening. Public and ; individual anxieties were moderated because tele’ phone service and many radio stations continued to operate, using standby power supplies. Police functions were not seriously hampered because of continued telephone service and the availability to most law enforcement agencies of self-contained power units. 4 In order ta assess the full impact of the November 9th power failure on significant aspects of human and institutional activities throughout the affected area and the country at large, the Commission requested information from 30 Federal, state and I local bodies, on ( 1) their investigations and findings relating to a list of essential services, (2) actions taken, or in process, to prevent or alleviate the impact on these services of possible future power FICWRE 3 . 7 interruptior tional servic be supporte The replies, indicate a g uncovered 1 been taken i A subs1 and c througl The de cedure! and otl kept 01 Initiati that al a const Initiati ernmer et en. 1 c rk ” P tId L ic k Id 3 :0 :lIt !r I !r : !- d I:e r FIGURE 3.This 15,000 kw gas turbine generating unit was installed in December, 1966 for peaking and station startup at Long Island Lighting Company’s Port Jefferson Station. interruptions, and (3) their suggestions for additional services considered sufficiently important to be supported by emergency electric power facilities. The replies, which are summarized in appendix D units in stairwells, elevator cars, transformers and switchgear rooms, control centers, and other specific areas; indicate a generally high level of response to needs ment of Housing and Urban Development, for emergency transportation facility improvements, including emergency power supplies for the movement of trains; the development of emergency radio, station lighting and alarm signal equipment; and the additions of other essential facilities; uncovered by the power failure. Actions that have been taken include, for example : A substantial upgrading of emergency lighting and communication facilities at airports throughout the country; The development of emergency plans and procedures to insure that teletypewriters, PBX and other telecommunications media could be kept open and available to the public; Initiation of a nationwide program to assure that all civil defense warning telephones have a constant power supply; Initiation of a program to equip Federal government buildings with emergency lighting The grant of Federal funds, by the Depart- Upgrading of standby power capability for communications and control during all critical phases of space flight missions; Promulgation by the City of New York of rules to assure continuing adequate and safe functioning of hospital services and facilities during power emergencies; 9 Action by the Port of New York Authority to upgrade communication, lighting, and emergency evacuation procedures for facilities under its jurisdiction. date represent only the beginning of what needs to be done to insure optimum reliability in the rapidly expanding power systems being designed to meet future needs. These improvements are substantial, but deficiencies still remain in many vital areas. For example, a state-by-state survey by the Engine Generator Set Manufacturers Association of mandatory provisions for standby power for essential services indicates that 22 states have no legislative provisions requiring emergency power. Also a nationwide study of auxiliary power available in the nation’s hospitals as of 1965 showed that of 6,915 hospitals surveyed, only 2,973 or 43 percent had adequate emergency power. The United States Congress has been concerned about the Northeast power failure, its causes and effects, and the remedial actions needed to minimize the likelihood of future occurrences of this kind. Particularly, the House of Representatives’Committee on Interstate and Foreign Commerce s and the Senate Committee on Commerce,4 investigated the circumstances surrounding the failure, its national implications, and subsequent actions undertaken by the electric power industry. The studies and reports of these Committees reveal a widespread interest and concern throughout the nation about the reliability of electric power systems. They contain much information on actions taken or planned by utilities, State Commissions and others to improve system reliability and alleviate the effects of power service interruptions. As random examples, the State of Montana has asked the utilities within the State to so plan and schedule maintenance that only a minor portion of the state-wide transmission system will be out of service at any time. Evidence of similar concern is reflected in the State of Michigan’s recommendations that its utilities improve their practices in periodic testing of system control devices, and that isolated systems review the advantages of interconnection in increasing reliability. Information assembled in the Committee reports, however, suggests that accomplishments to Status of Improvements in the Northeast a See transcript of hearings before the Special Subcommittee to Investigate Power Failures, Committee on Interstate and Foreign Commerce, United States House of Representatives, 89th Congress, and Addendum thereto. Serial Nos. 89-40 and 89-54. ‘See Interim Report of the Committee on Commerce, United States Senate on the Northeast Power Failure, Responses to Inquiries [Committee Print, March 15, 19661 89th Congress, 2d Session. 10 During the year following the Northeast power interruption, the major affected utilities invested $20 million in new equipment and improvements to protect existing facilities and to lessen the likelihood of a recurrence of a cascading power systems failure. An additional $30 million or more has been committed for further improvements that are being made as rapidly as procurement and installation schedules will permit. The following sections describe the typical major improvements completed or underway. Equipment Additions and Modifications Every utility in the power failure area has reviewed the adequacy of its protective and control equipment, and hundreds of modifications or additions have been made. Within a few days after the power failure, the Hydro-Electric Power Commission of Ontario modified the protective backup relay at the Sir Adam Beck Hydro Station which had initiated the power failure, and additional relays were installed to give the main transmission lines improved protection and to permit their carrying increased loads. As a further protective measure the utilities in the United States that are interconnected with the Ontario system placed controls on the two interconnecting transmission lines at Niagara which, under any conceivable future mishap, would open these lines before power flows 1 reached levels likely to disrupt the operation of the interconnected network in New York and adjoining areas. Thus, the probability of another power failure from the same precipitating cause is very remote. Many of the dual-scale frequency meters which confused system operators when extremely subnormal frequencies occurred have been replaced with I two separate instrument-ne with a magnified scale to show small deviations during normal operations and the second to indicate the wide frequency deviations that occur during severe system disturbances. A serious deficiency uncovered by the Northeast failure was the frequent lack of emergency power to provide lights and communication at control centers; to protect generation facilities during the run- down pe: mum de1 of gener: some are: Utilitic of the cc auxiliary service a tions foll start-up Northea! Marylan gregate c primaril) be availa help met cause of ment, fo arisen sir the equil of 1967,, Where systems i: up powe plified s\ had acce first to re APPLY improve1 stations 100,000 nearly 9r terns inv ’ Altoge capacity a service frc c Install’ March 31 ‘Nine 1 facilities ( power can service. F Corpora& its Rutlar can be c CONVEE cedures tc power to 1 Mountain from the ( establishec elevation Storage P cranking I b‘on !de!ted lays ines on at the ing Ill-i? !. ich [orith ied !M/reem mt qer enItll1 down periods; and to restart generators with minimum delay. This resulted in damage to a number of generators 5 and prolonged the interruption in some areas, notably New York City. Utilities in the Northeast and in many other parts of the country have installed or have on order the auxiliary power units needed to maintain station service and to restart steam-electric generating stations following a shutdown when other sources of start-up power are not available. Plants in the ,Northeast and in the Pennsylvania-New JerseyMaryland area are adding G 62 units with an aggregate generating capacity of 1,025,OOO kilowatts, primarily to assure that adequate starting power will be available. Many of the units can also be used to help meet peak loads during normal operation. Because of the time required for delivery of this equipment, for which an especially large demand has arisen since the power failure, only a small part of the equipment ordered is now installed. By the end of 1967, all of the units should be ready for service. Where hydroelectric power is readily available, systems are relying upon, this source for quick startup power, and some are arranging circuits for simplified switching in time of need.7 Systems which had access to hydroelectric power were among the first to restore service on November 9. Appendix B, table B-l, summarizes the major improvements that have been made at generating stations in the Northeast that have capacities of 100,000 kilowatts or more. These stations represent nearly 90 percent of the total capability of the systems involved. ’Altogether, five units in the island area having a rated capacity of 1,945,OOO kw were damaged and were out of service from three weeks to two months. ‘Installed or ordered between November 9, 1965 and March 31, 1967. ‘Nine utilities in the Northeast have made changes in facilities or operating instructions to assure that hydro power can be quickly routed to thermal plants for station service. For example, Central Vermont Public Service Corporation has rearranged the station service wiring at its Rutland Gas Turbine Station so that station service can be obtained from a nearby hydro station. The CONVEX Pool has established emergency switching procedures to expedite the routing of emergency auxiliary power to the West Springfield Steam Station from Cobble Mountain Hydro Station and to Mt. Tom Steam Station from the Cabot Hydra Station. General Public Utilities has established an operating procedure to retain a minimum elevation in the upper reservoir of Yards Creek Pumped Storage Plant so that this station can serve as a source of cranking power for thermal plants. ,“” ,- Spinning Reserve Practices 8 The function of spinning reserve in the operation of a power system is to provide additional generation quickly whenever it is needed. Such reserves enable an interconnected system which has encountered difficulty, such as the sudden loss of a generating unit, and which is temporarily being supported by small increments of power from many units of the network, to rebuild its own supply rapidly and restore tieline flows to normal. It is not always practical to carry enough quickly responding spinning reserve to permit complete restoration of needed generation in an area that becomes an “island” (separated from the interconnected system) after a severe disturbance. Such was the case when the Southeast New York-New England area became an electrical island on November 9. A contributing problem in the island area was the concentration of spinning reserves in the Southeast New York area, resulting in a substantial increase in system losses when the island was formed. The combined response of the spinning reserve in this area on November 9 immediately following the separation is depicted in figure 17, chapter 5, and is discussed in detail in the excellent studies of the Task Force which appear in Volume III. The responses of individual units varied widely. Some with considerable steam reserve in the boilers responded quickly, but the energy stored in the boilers became exhausted in less than 30 seconds and was not replenished at normal rates because the declining system frequency and voltage seriously impaired the capacity of the units’ auxiliaries which service the boilers. Other units served by boilers which operate with more limited heat storage capacities were slower to respond because increased steam output is dependent upon increasing the fuel supply rate and a related series of actions which necessarily produce a lag in the fuel inputsteam output sequence. As this discussion has indicated, to expect spinning reserves to meet such extreme situations is to anticipate performance beyond their usually assigned function. The experience demonstrates that performance cannot be measured merely by numerical addition of excess machine capacities above current outputs; the speed and amount of sustained response over an interval of time must also be a See also the discussion on System Reserve in chapter 5. 11 considered. The overall dependable rate of response of a group of steam turbine generators is improved by distributing the spinning reserve over a large number of the units. In this respect, the practice which prevailed on November 9 in the Northeast nee-ded some improvement. Provisions for load Shedding o The best protection against a power interruption is sound planning and a well designed and operated bulk power supply system. It remains conceivable, however, that at some time an unexpected event can isolate a utility or group of utilities from the network. If the island area thus created is deficient in generation, loads must quickly be reduced to avoid total collapse of the power supply system. Manual load shedding is likely to be accomplished too slowly during a severe emergency, so automatic controls are needed to assure that load shedding will effectively serve its intended purpose. On November 9, the southeast New York and New England utilities became an electrical island five seconds after the disturbance began, but the island system did not collapse until 12 minutes after its separation. During that period, system voltage and frequency fell far below normal and the capability of the generators which remained in operation declined rapidly. A separation of the network caused by a severe disturbance usually creates an “electrical island” encompassing a number of utilities. Unless load shedding is effected automatically, the load reduction of each utility would be subject to the promptness of its operators in decision-making and actions, with a resulting pattern of overall load reduction that could vary widely from the planned objective. Even rigorous drilling and training of operators in manual operation would not be completely effective because of the need for quick determination and action involving speeds beyond human capabilities. Moreover, uncoordinated manual load shedding by one utility might not be properly timed with respect to similar actions by adjoining utilities using either manual or automatic controls. To be effective, automatic load shedding equipment must be designed to provide adequate relief under all foreseeable circumstances. “The purpose and problems of load shedding are discussed in greater detail in chapter 5. At the time of the interruption, no utility in the CANUSE lo area employed automatic load shedding. This is in marked contrast to some other parts of the United States where it is employed extensively. Automatic load shedding procedures, however, have recently been adopted by all major utilities in the Northeast, as a result of the efforts of the Northeast Power Coordinating Council.*1 The agreed upon procedures should be implemented as quickly as the necessary equipment can be designed and installed: Service to New York City The interruption of November 9 placed New York City, the center of the largest metropolitan area in the world, in total darkness. At the time of the interruption, Consolidated Edison Company was serving a load of 4,770,OOO kilowatts. The installed capacity of the Company’s generating equipment was about 7,580,OOO kilowatts. The Consolidated I Edison system collapsed not because of a direct generation deficiency within its own area, but because of the effects of deficiencies in the interconnected system, the rapidly changing conditions during the disturbance, inadequate information to the system operator, and lack of automatic controls to restore balance. Since the failure, the Company has improved its systems of instrumentation and control. It has installed separate wide band and narrow band frequency meters at its control center in order to avoid the hazard of misreading the scale. It has provided alternative power sources which can furnish continuously available and reliable power during system disturbances for all of its communication systems, including power supplied for the transmission of system performance data by telemetering and other communication equipment. The density of power service in the City of New York, and the extensive use of underground cable feeders added to the task of restoring power. The magnitude of loads required separation of the cable system into sections to prevent potentially harmful overloading of some circuits. Furthermore, reenergizing large sections of underground cable must XI Canada-United States Eastern Interconnection, an informal coordinating organization that includes representatives from utilities in Michigan, the Hydra-Electric Power Commission of Ontario, and utilities in the Northeast. “The Council is described in the last section of this chapter. FIG be ant are sys da1 1 da va: arc inf kej ag UI? sal ca i the edarts P Iten- , I P ew jitan b of i w= alled but b teri;ons k oid Ided ‘sh ‘ Fng b ble $ful renust , an ctric the this FIGURE 4.-Emergency standby power for safe rundown is provided by this 600 kw diesel engine generator set at Consolidated Edison Gompany’s Hudson Avenue generating station. be done with caution to prevent excessive voltage and damage to equipment. Compensating devices are being installed on the underground cable system to minimize the likelihood of equipment damage.” Emergency power standby units have been ordered by the company and are being installed at various generating stations. Small emergency units are being installed to maintain dil pressure on bearings of generating units during rundown and to keep the hot units in slow rotation should power again be totally interrupted for any reason. Larger units up to 20,000 kilowatts capacity will supply power to steam station auxiliaries to enable restart of major generating plants in the event that other sources of startup power are lost. These large standI2 The Company has installed 680 megavars of compensation in the form of shunt reactors on its underground cable transmission system. Another 860 megavars have been authorized, most of which will be added by 1969. by units also can contribute to the system reserve capacity or be operated to help meet short time peaks. The Company has placed in effect a system of load shedding through automatic voltage reduction which will be applied in two steps by the action of underfrequency relays. These steps are expected to reduce loads about 5 and 3 percent, respectively, in areas serving about 75 percent of the system load. In addition, the Company has agreed to the automatic and manual load shedding procedures adopted by the Northeast Power Coordinating Council.13 System controls are arranged at present so that practically all loads can be interrupted by la The schedule provides for automatically reducing loads 10 percent when system frequency is in the 59.5-59.0 c.p.s. range and an additional 15 percent when system frequency deteriorates to the 59.0-58.5 c.p.s. range. If the emergency situation continues, an additional 25 percent of load will be shed manually. 13 the pushing of supervisory control buttons in the Company’s system control center. The readiness of the Company to cope with an under-frequency situation will be substantially improved when the automatic provisions cited above are fully installed. The operating program ‘now in effect relies entirely on the judgment of the system operator to shed loads manually if automatic voltage reduction is insufficient. This places an excessive responsibility on individuals to take timely and correct action under emergency stress, and unnecessarily subjects the city’s power supply to significant risk. Although skilled operators have been able to bring systems through critical subnormal frequency situations without interrupting loads, the margin between success and failure can be very narrow. The automatic load shedding procedures that have been agreed to by the Northeast Power Coordinating CounciI should be implemented as rapidly as possible. Power for New York Subway Since November 1965, officials of Consolidated Edison Company and the New York City Transit Authority have been conducting studies to determine the best means of strengthening service reliability to the subway system. The failure left parts of the system without power for nearly ten hours. The BMT (the old Brooklyn-Manhattan Transit) and IRT (Interboro Rapid Transit) use 25-cycle power and the IND (Independent) system is supplied from the 60-cycle network. Consolidated Edison has ordered ten gas turbine generators ranging in size from 11,000 to 20,000 kilowatts for emergency and peak-power requirements. While these gas turbine units are intended primarily for starting power in the event of another widespread failure, they will also be, able to furnish sufficient power to permit the BMT and IRT trains to reach the next station. The situation on the IND system% different. This system is supplied from the 60-cycle network which also supplies the general utility loads, and it is not possible to afford it selective treatment in either protection from interruption or restoration of service if the system loses all power. However, Consolidated Edison is looking’ into the possibility of providing a minimum number of single-duty 60-cycle feeders to selected rectifier stations (perhaps every fourth station along the subway line) to make it possible to move stalled trains at least into the next station. 14 Service to Boston The power failure in Boston on November 9, was generally similar to that in the. New York area. The Boston Edison Company load just prior to the interruption was 1,375,OOO kilowatts, including 174,000 kilowatts being exported. Sufficient capacity was available to meet these loads plus spinning reserve requirements. Nevertheiess, the system had completely collapsed by 5 : 21 p.m.about five minutes after the initial disturbance. Charts from recording instruments indicate that system conditions were changing so rapidly during the five minutes, that it was impossible for the system operators reasonably to interpret all the events that occurred. The disturbance in the Boston area was aggravated by the tripping of 16 generators on the New England-Eastern New York systems by loss-of-field relays.14 Some of these units did not have high speed automatic voltage regulators and others were being operated with the regulators out of service. The units might have remained in operation if fast response voltage regulating equipment had been operative.15 Restoration of service in Boston was delayed by the lack of emergency power sources for unit start-up. After more than an hour, start-up power for one station was obtained through a 13.8 kilovolt connection to the U.S. Naval Shipyard in the Charlestown section of Boston. Other units were started in sequence until the system was virtually restored to normal about 71/z hours after the beginning of the trouble. Boston Edison’s basic problems were those common to most of the “island” area-too much load for the available generation, lack of an effective program of rapid load reduction in an emergency, and no readily available sources of emergency power for restoration of generating units after the system had collapsed. Recognizing these problems, Boston Edison has installed a jet-engine generator for emergency starting power and four small diesel engine generators for safe rundown. Underfrequency relays have I’Loss-of-field relays are used to detect trouble in the excitation systems of generators. If serious trouble occurs, the relay acts to disconnect the generator to minimize damage to the machine and prevent development of an unstable condition on the power system. 15Discussion of the importance of fast response voltage regulation is included in the report of the Eastern New York-New England System Studies Group in Volume III. ,@ been instalk auxiliary 102 ing any se\ then providl ual load ret matic load Power Co01 being plann that system should agai island. , The Bost systems wer plied from i chusetts Ba: tinued to op Studies oi Immedial 9, the Con studies of t1 determine it losses in eii were condul Commission east Power under the C The nets examined u probable, o severity to t 13 selected c ber of pote conceivably They have : point of spel selection wa ment which past. Most of “double con currence of multaneous Examples ar I8 The powe land States an of close coordi tion, the Pen terconnection of the North1 system must t interconnectio. :r 9, was rea. The ) the inlcluding ient cards plus es, the p.m.rice. ate that ? during the syse events :on area ators on terns by d autoe being ce. The fast red been ayed by or unit ) power kilovolt in the ts were irtually the beie comzh load ffective rgency, :rgency jter the iOn has ,y startaerators s have : in the occurs, minimize it of an voltage rn New me III. been installed to isolate a steam unit with sufficient auxiliary load to permit its continued operation during any severe system disturbance. This unit can then provide power for restarting other units. Manual load reduction procedures are in use and automatic load shedding incorporating the Northeast Power Coordinating Council’s recommendations is being planned. Until installed, some danger remains that system power could be totally lost if Boston should again become part of a distressed power island. , The Boston subway and elevated transportation systems were not interrupted since they were supplied from independent power plants of the Massachusetts Bay Transportation Authority which continued to operate during the disturbance. Studies of the Northeast Network Immediately following the failure of November 9, the Commission initiated a series of intensive studies of the Northeast transmission network l6 to determine its ability to respond to severe faults and losses in either load or generation. These studies were conducted under the general guidance of the Commission and its Advisory Panel on the Northeast Power Interruption by task groups ‘organized under the Commission’s direction. The network as it existed in January 1966 was examined under 13 assumed possible, although improbable, occurrences similar in magnitude and severity to that experienced on November 9. These 13 selected cases were representative of a large number of potential improbable situations that could conceivably occur in various places on the system. They have no special significance from the standpoint of specific location or type of occurrence. The selection was guided by types of failures in equipment which have occurred on power systems in the past. Most of the cases tested are characterized as “double contingencies,” since they combine the occurrence of a severe incident with the prior or simultaneous occurrence of another serious incident. Examples are loss of a large generating unit follow“The power failure involved primarily the New England States and New York. However, from the standpoint of close coordination of overall system planning and operation, the Pennsylvania-New Jersey-Maryland (PJM) interconnection is a vital link in the strength and reliability of the Northeast area systems. Consequently, the PJM system must be considered in planning future expansion, interconnection, and control for the Northeast systems. ing loss of a major transmission line, the simultaneous interruption of two transmission lines on the same corridor or the failure of a breaker to clear a severe fault on a main circuit promptly. The test results indicated both stable and unstable conditions.lT Further stability studies were made of the Northeast network as strengthened by three new transmission interconnections scheduled to be in operation by 1968.l’ One of these, a 230 kilovolt extension of a western New York-Pennsylvania tie into northern Ohio, was placed in operation a month after the power failure. A second interconnection, in effect strengthening an existing transmission link between Public Service Elect.& & Gas System in New Jersey and Consolidated Edison in New York City, will be fully completed by the end of 1967. It consists of a new 345-kilovolt transmission line between the Consolidated Edison Company’s Arthur Kill Generating Station on Staten Island and its Farragut Switching Station in Brooklyn, now in service, and conversion of the present 138 kilovolt tie to Public Service to 230 kilovolts. These changes will increase capacity for the flow of power into New York City under emergency conditions from 300 megawatts, the present limit, to 500 megawatts. The third addition is a 500 kilqvolt intertie from Pennsylvania and New Jersey to southeast New York. This line will have a carrying capacity of about 1,000 megawatts and is intended primarily to strengthen the interconnection. The purchase or sale of firm capacity over this intertie is not contemplated during the early years of its operation. Consequently, practically the entire capacity of the intertie should be available for emergency or reserve interchange. The studies show that these added interties will substantially improve network stability. However, the 500-kilovolt intertie from Pennsylvania and New Jersey to southeast New York has been delayed by right-of-way problems in New Jersey and now is not scheduled for operation until the summer of 1969. This seriously prolongs the present deficiency in interconnection capacity between the Northeast and the P JM load areas. Various groups of utilities in the Northeast have sponsored several independent studies by private consulting firms, among these a study of the Northeast interconnection Is by Stone and Webster Engi“The report of the task group which performed these studies is included in Volume III of this report. “A summary of the report of the Stone and Webster Corporation is included in Volume III of this report. 15 neering Corporation. Thk consultant examined the effects of severe disturbances, involving loss of lines or generating units, on system stability. For many of the cases, it was concluded that system separation was a possibility. Even so, there is some question about whether the criteria for assumed disturbances were sufficiently severe. The study was made primarily to develop general guidelines for increasing reliability rather than to produce plans and designs for system changes. The consultant’s report sets forth recommendations relating to criteria for stability examinations, spinning reserve, automatic voltage regulation, restoration of tielines, establishment of system security centers for continually monitoring system conditions and performing security analyses, and suggested requirements for automatic load shedding. Prqjectionr of Development by Northeast Utilities I Figure 5 depicts the principal elements of the transmission network in the Northeast and interconnections with adjoining areas, and delineates lines added since the power failure of November 9 and those scheduled for addition up to 1973. The projections are in response to the Commission’s request for a six-year forecast of load, generation, and transmission requirements. In the period from November 1965 to 1973, 1400 miles of 345-kilovolt circuits and nearly 300 miles of 500-kilovolt circuits have been or are scheduled to be placed in service in the Northeast. The peak load projected for the Northeast I9 systems for the winter of 1973 is 31,200 megawatts, an increase of 35 percent over the area peak load projected for the winter of 1967. Planned generating capability in the area is 40,300 megawatts, an increase of 44 percent above the capability in 1967. The gross margins of capabilities above projected peak loads for the period of 1969 to 1973 is a minimum of 29 percent and averages about 30 percent, substantially more than the 21 percent available in 1967. The portion of the gross margin of future generation that will exceed the requirement for reserves is dependent upon such things as required downtime for maintenance, flow conditions at hydro installations, lead time for construction of new units, and inaccuracies in load forecasts. The fact that indicated gross margins are high does not necessarily “Not including the Hydro-Electric Commission of Ontario. 16 mean that they are excessive. Nevertheless, in the Northeast where planned system improvements will enhance the opportunities for improving coordination of construction and maintenance programs, the figures in the preceding paragraph suggest that a careful review of gross margin requirements might lead to some substantial savings in construction investments without sacrificing reliability. EXlSTlh Need for Further Study Continuing study of the Northeast network and its ties to neighboring systems is essential to assure continuous stable operation in the face of rapidly increasing loads. The Northeast Power Coordinating Council has initiated a region-wide stability study of the configuration of generation and transmission contemplated for 1973. These studies have not progressed sufficiently to judge the adequacy of the network for the projected 1973 loads, but additional strengthening may be needed to reduce the possibility of network separation. The Commission’s Advisory Panel for the Northeast Bower Interruption, in reviewing the task group studies and projected programs of the Northeast utilities has stated : . . . The Panel believes that the proposed increased distribution of generation and its location closer to the load centers, particularly in thermal and pumped storage plants, should strengthen the network in the future by reducing some of the need to transport power over substantial distances in the area. This, thereby will relieve transmission capacity for backup purposes during outage contingencies. The Panel suggests that further consideration be given to additional interconnections, particularly to the South and West from upper New York State. This judgment was arrived at by noting the future proposed 345-kv and 500-kv developments in this and adjacent areas. While the Panel is in no position to determine whether such lines are essential, it, nevertheless, believes that any additional reinforcing ties of this type would contribute greatly to the overall reliability of the area, particularly because of the area’s somewhat radial relationship to the systems to the South and West.*’ Provisions for strengthening interconnections, not only in the Northeast but throughout the nation, are discussed in chapter 6. The discussion presents a general pattern which, on the basis of rough appraisals, will be needed by 1975 to prevent the recurrence. of cascading power failures. Suggestions 2o Comments by the Advisory Panel on the Northeast Power Interruption on the Task Group Studies are included in Volume III of this report. beyond ordinal general f The N i ’ , : One elusion improt formin fective planni nating MAJOR TRANSMISSION LINES AND GENERATING STATIONS EXISTING AND PROPOSED IN THE NEW YORK AND NEW ENGLAND POWER SYSTEMS AS OF JANUARY 1967 FICWRE 5 beyond those outlined by the Northeast Power Coordinating Council for 1973 are included in this general pattern. The Northeast Power Coordinating Council One of the immediate and most significant conclusions from the power failure was the need for improved coordination among the many utilities forming the Northeast interconnection. To be effective, such coordination must encompass both the planning and operating functions, and the coordinating mechanism must provide a satisfactory means for reaching timely agreement. Improvement in coordinating organizations throughout the nation to achieve better reliability of bulk power supplies is one of the principal recommendations of this report. A step forward toward closer coordination among utilities in the Northeast was achieved by the formation of the Northeast Power Coordinating Council in January 1966. Its members include 21 21 major utilities in the Northeast and the Hydra-Electric Power Commission of Ontario (figure 6). The work of the Council is carried out under the direction of an Executive Committee of nine members and a Chairman who is also the Chairman of the Council. There are two principal standing committees-the System Design Coordination Committee and the Operating Procedure Coordinating Committee. The work of these committees is supn Including Connecticut Light & Power Company, Hartford Electric Light Company, and Western Massachusetts Electric Company recently consolidated into Northeast Utilities. 17 I MEMBER SYSTEMS OF NORTHEAST POWER COORDINATING COUNCIL L 1 i DO ha sy ! ha th ro of m PENNSYLVANIA 1 BOSTON EDISON COMPANY 2. CENTRAL HUDSON GAS 6 ELECTRlC CORP. 3. CENTRM MAINE POWER COMPANY 4. CENTRAL VERMONT P”BL,C SERVlCE CDRP 5. CONNECTICUT LIGHT AND POWER COMPANY, THE 6: CONSOLIDATED EDISON COMPANY OF’ NEW YORK, INC. I EASTERN UTILITIES ASSOCIATES 8. G~A;$UNTAiN POWER CORPO9. HARTFORD ELECTRIC LlGHT COMPANY, TNE IO. HOCYOKEWATER POWEROOMPANY ANDHOLYDKEPOWERhELECTRlC COMPANY 1,. HYDRD-ELECTRIC POWER CO~,SSIC,, OF ONTARIO, THE 12. LONG ISLAND LIGHTING COMPANY 13 NEW ENGLAND ELECTRlC SYSTEM 14. NEW ENGLAND GAS AND ELECTRlC ASSOCIATION IS. NEW YORK, STATE ELECTRlC & GAS CORP. lb. NIAGARA MOHAWK POWER CORPDRATION Il. ORANGE AND ROCKLAND UT, LITIES, INC. 18. POWER AUTHORITY OF THE STATE OF NEW YORK 19. PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE 20. ROCHESTER GAS AND ELECTRlC CORP. 21. UNITED ILLUMINATING COMPANY, THE 22. WESTERN MASSACHUSETTS ELECTRlC COMPANY FIGURE 6 plemented by task forces on system studies, system protection, load and capacity, load shedding and spinning reserve, and computers. Many of the Council’s activities since organization have been related to seeking solutions to problems revealed by the Northeast power failure, many of these in direct response to the request of the Federal Power Commission. Major efforts of the Council’s committees have included stability studies of the Northeast network (partly in valuable assistance to the Task Group Studies, summarized in 18 Volume III), projections of load, generation, and transmission requirements by 1973, and coordinated study of load shedding. Recently, members of the Northeast Power Coordinating Council adopted an automatic load shedding program. Th e program provides that each system will be equipped with underfrequency relays which will drop 10 percent of system load should frequency decline to 59 cycles and 15 percent more at 58.5 cycles. Each svstem will urovide for dropping, manually, an additional 25 percent of its load whenever emergency conditions warrant. Prior to this agreement, the Niagara Mohawk Power Corporation was the only member of the NPCC which had undertaken installation of a comprehensive system of automatic load shedding, although a few had installed some automatic equipment. Stability studies of the transmission network projected for 1973, tested under the severe criteria reviewed earlier in this chapter, are in process and are scheduled for completion later this year. It appears that the Northeast utilities and also those in surrounding areas will need to expand their analyses of the integrated regional and interregional transmission requirements. The Commission has urged bE STATE NYDF .KTRlC UMPANY, IS ELECTRIC ation, and 1 coordinated i t Power Cotic load shed:s that each luency relays load should lercent more de for dropnt of its load the Council to intensify its efforts and to expand its analysis of future requirements. The Council also has reached agreement on the establishment of two central control centers for coordinating the operation in 1970, one for systems in the State of New York and the other for systems in the New England area. Council officials report increasing awareness of the value of coordination among its members. We believe these values would be further enhanced in the region if all ownership classes of bulk power supply entities in the Northeast region were represented in the Council membership, and actively participated in Council undertakings. CHAPTER 3 POWER INTERRUPTIONS AND INTERRUPTIONS AVOIDED Power Interruptions Since the November 1965 Northeast power failure, the Commission has investigated and reported upon most of the significant interruptions in the nation’s bulk power supply. Twenty interruptions are briefly described in this chapter which have occurred at widely scattered points in southeast and southwest Texas, Alaska, the Pacific Northwest and Rocky Mountain areas, southern California, Nebraska, Missouri, Ohio, Virginia, and the PennSylvania-New Jersey-Delaware-Maryland area. All but three of these twenty interruptions were cascading failures. The largest of these occurred on June 5, 1967, and interrupted power service to eastern Pennsylvania, New Jersey, and the Delaware-Maryland peninsula. The failure affected 13 million people and lasted for periods up to ten hours. TABLE This failure is described separately later in this chapter. The principal circumstances of each failure are summarized in table 1. These occurrences illustrate the variety of circumstances which can cause power interruptions. They also reveal that a single precipitating cause may affect many generating or transmission facilities, that a failure of one element can contribute to the failure of others, and that protective devices must operate reliably to be effective. For example, in Beaumont, Texas, a defective element in a supervisory control system, which permits operators to perform switching operations from a central station, opened a high voltage transmission line and a few minutes later disconnected a principal generating station. l.-Major power failures which have occurred subsequent to the Northeast failure. El Paso, Texas, December 2,1965 Los Angeles Power Failure, January 24, 1966 A loss in load of 267,000 kilowatts for periods up to two hours and ten minutes affecting 470,000 persons in the United States and 100,000 in Juarez, Mexico, was caused by the accumulation of condensates in the gas supply line to the El Paso Electric Company’s principal generating station. The movement of condensates into the generating plant operated protective controls which shut ofs the burners. This major loss in generation, amounting to 51 percent of the system’s output at the time, caused the 115-kilovolt tieline to the north to become overloaded and trip out. The emergency capability of this line is about 40 megawatts. Power was interrupted for periods of 11 to 31 minutes, affecting an estimated 200,000 customers in the northwest section of the city. The interruption was triggered by the programed opening of two 138-kilovolt lines to permit construction on an adjacent new 230-kilovolt circuit. Two 138-kilovolt lines in another section of the network became overloaded following this switching operation and relayed open, followed in turn by the opening of some intermediate 230-kilovolt circuits. Underfrequency relays dropped approximately 20 percent of the city’s load, permitting the system to stabilize. Vicinity of Beaumont, Texas, December 6, 1965 An interruption in bulk power supply occurred on the interconnected systems in the Anchorage area, extending from Seward to Palmer, affecting a population of 125,000 for periods up to nearly two hours. The interrupted load amounted to 54,400 kilowatts. The failure was initiated by a prankster throwing a length of wire across a 34-kilovolt line. A protective relay on this line malfunctioned and the fault was cleared by breakers on the main 115-kilovolt line which tripped out. With the loss of power supply from Eklutna over this line, the generation in the Anchorage area was insufficient to meet requirements and the entire Anchorage area load was lost. Malfunction of supervisory control equipment caused the opening of a 138-kilovolt transmission line, and subsequently tripped all units of a principal generating station on the western section of Gulf States Utilities Company’s system. As system frequency declined, attempts were made to isolate a portion of the Gulf States’system and transfer the load temporarily to Houston Lighting and Power. The remote control switching did not operate as planned, and the section lost 79 megawatts for 26 minutes. Protective devices on industrial loads of the western section dropped approximately 140 megawatts of load for periods up to three hours. Anchorage, Alaska and Vicinity, May 13, 1966 TABLE l.-Major power failures which have occurred subsequent to the Northeast failure-Continued Western States Power Interruption, April 26, 1966 An inaccurate telemetering signal caused an overgeneration of power in the Pacific Northwest which overloaded and tripped off several long distance interconnecting ties. As a consequence, the western interconnection was separated into five major and two minor areas. To prevent collapse of power in some of the distressed separated systems, some 505 megawatts of load, mostly industrial, was dropped for periods up to 56 minutes. The last tie restoring the interconnection was closed five hours after the interruption. Western States Interruption, June 7, 1966 A high speed ground switch associated with a 230/345kilovolt transformer bank malfunctioned and caused a widespread tripping of tie lines in the western interconnection, separating it into eight isolated areas. A total of 848 megawatts of load was interrupted for periods up to 40 minutes. The interconnection was restored in less than two hours, except for the 230 and 345kilovolt lines initially interrupted. These were closed on the next day. Nebraska Interruption, ]uZy II,1966 Two power failures occurred on the same day in the Nebraska-Dakota areas, the first from incorrect wiring of a relay, and the second from failure of a power transformer. The two interruptions caused widespread separation of systems in this area, and in each instance 800 megawatts of load was interrupted. Power was restored in about three and one-half hours following the first interruption, and in two and one-half hours after the second. About 600,000 persons were affected by the loss in service. Western States Interruption, July 12,1966 A severe lightning storm caused the opening of breakers at a principal station near Spokane, Washington, which tripped seven 230-kilovolt transmission lines in the area. The resulting interruption separated the interconnection into eight major isolated areas. The load interruption exceeded 975 megawatts for periods up to 32 minutes. The interconnection was restored approximately 20 minutes after separation, Forced Curtailment of Electricity in the St. Louis Area, July 11 and 12,1966 The forced curtailment of power use in the St. Louis area began at 1: 47 p.m. on July 11 and amounted to a reduction of about 300,000 kilowatts from the 3,500,000kilowatt load which would have developed without the curtailment. The problem was precipitated by a period of abnormally hot weather accompanied by high peak loads coupled with the unavailability of the new 478,000-kilowatt generating unit at the Portage des Sioux station, originally scheduled for initial service on May 1, 1966. All interruptible loads, totalling about 55,000 kilowatts, were cut off at 8: 15 a.m. on July 11. Telephone contacts with industrial customers netted some voluntary curtailments and spot radio announcements gained some additional voluntary reductions in residential, commercial, and industrial loads. Beginning at 1: 47 p.m., some low-priority loads were cut off on a rotational basis, and this continued I j/! Ilj 22 the VEP bus to 01 In additi to the n into the load was mission ! until 3 : 50 the next morning. Such curtailments were resumed from 11: 30 a.m. to 7 : 30 p.m. on July 12. Although power was available from utilities to the north and east, interconnecting transmission lines were able to move in only about 176,000 kilowatts of emergency assistance. Western States Interruption, July 18,1966 A telemetering error affecting the interchange power flows resulted in overgeneration on the power system. The overgeneration tripped a number of the weaker ties and _separated the interconnection into five isolated areas. Loads totalling 3 12 megawatts were interrupted for periods up to 30 minutes. The last tie line was reclosed in one hour and 15 minutes. Arkansa. A set line was circuit s service 1 remainir system h 56,700 hour an some 5,’ 295,000 Southern California Edison Company, July 19, 1966 The 1,465,000-kilowatt output of the Company’s Alamitos steam electric generating station was suddenly interrupted by the failure of two 230-kilovolt air-blast circuit breakers in the plant’s switchyard. This loss amounted to about 25 percent of total system generation at the time and resulted in overloading and opening all ties with other utilities. The Company’s underfrequency relays acted instantly to drop major blocks of load. Including lesser loads which were shed manually, the reduction totalled about 1,300,OOO kilowatts:Ties to other systems were restored in a few minutes and service to all customers was restored within 27 minutes following the interruption. The generation deficiency following interruption on the Southern California Edison Company’s “island” operation was larger in magnitude than the deficiency experienced in the Northeast power failure in the eastern New York-New England islaud area, and much larger in proportion to the total load in the island areas. In California, a prolonged total system collapse was averted because the emergency situation was instantly countered by automatic load shedding. Western States Interruption, July 21,1966 A’ defective relay opened a 230-kilovolt transmission line between Walla Walla and Wanapun, Washington. The subsequent adjustment of flows resulted in other lines being tripped on overload, and the western interconnection was separated into seven areas. Approximately 590 megawatts of load was shed for periods up to 43 minutes. The final closure of all ties was not completed until more than ten hours following interruption. Western States Interruption, August 1,1966 Bonneville Power Administration’s McNary-Roundup line was inadvertently tripped when its relays were being reset. Overloads on other lines caused the western interconnection to separate into four isolated areas. Approximately 445 megawatts of load was lost for periods up to 45 minutes. The interconnection was restored to normal in five minutes. Virginia Electric B Power Company System, November 3, 1966 i: I Austin, 1966 Simd breaker! o f eleci 50,000 1 was red determi system i Gulf St A PO t May 11 Cornpar Doucetl About tion w: which i of a 5 general megaw later, E 138-kilt and set eight n Gulf SI at the comple second: Attem shift st unsucf resuitt In J The interruption was caused by the explosion of a 115- m kilovolt circuit breaker at the government-owned Kerr E’ son Cc statior Dam project. The fault caused five 115-kilovolt circuits in 1 TABLE l.-Major power failures which have occurred subsequent to the Northeast failure-Continued the VEPCO system which connected to the government bus to open under back-up protection at remote locations. In addition, a 115-kilovolt breaker at a subs&on 80 milts to the north opened due to overload and severed supply into the area from the north. About 155,000 kilowatts of load was interrupted, affecting 150,000 customers. Transmission service was restored to the area in 45 minutes. Arkansas-Missouri Power Company, December 2, 1966 A section of the Company’s 115-kilovolt transmission line was knocked out of service by a felled tree. Another circuit supplying Arkansas-Missouri had been taken out of service previously for re-insulating work. The Company’s remaining ties and plants were overloaded interrupting system load amounting to 91 megawatts and approximately 56,700 electric customers. Service was restored in one hour and seven minutes throughout the area which covered some 5,800 square miles with a population estimated at 295,000 persons. Austin, Texas, Munici#al Electric System, December 14, 1966 Simultaneous trip-out of three 69-kilovolt circuit breakers at the System’s Holly Street Plant caused a loss of electric power of 120 megawatts to approximately 50,000 customers, in the city of Austin. Complete service was restored in 40 minutes. The exact cause has not been determined but a malfunction in the supervisory control system is suspected. Gulf States Utilities Company, May II, 1967 Under-frequency relays l&&l not yet been installed on the company’s system. Cleveland Electric Illuminating Com.pany, May 17, 1967 At 11: 59 p.m., EDT, an interruption affected approximately 66,000 customers and 80,000 kilowatts of load in the Greater Cleveland west side area of Cleveland, Ohio. No equipment trouble was found and all service was restored within 28 minutes. The interruption occurred during a labor strike, and the four 132 kilovolt transformer breakers found open at the Clinton Substation were believed to have been tripped manually in the switchyard. The substation had been the scene of heavy picketing, and barbed wire barriers at the top of the main switchyard gate and fence were found cut. Cincinnati Gas and Electric Company, May 26, 1967 At 9:29 p.m., EDT, the Cincinnati Gas and Electric Company and subsidiary systems sustained an interruption to about 40,000 customers and 48,000 kilowatts of load in the Cincinnati, Ohio and Covington, Kentucky areas for periods ranging from about thirty minutes to more than six hours. The trouble started from what appears to have been willful damage to a 13 kilovolt cable on a highway bridge across the Ohio River between the West End Generating Statian and Covington. This was followed by a pothead failure on a voltage regulator in the outdoor substation at the West End Plant, and fire affecting the oil circuit breaker control cables. At 6:30 a.m. on May 27, the control cable fire still persisted and it became necessary to deenergize all incoming circuits to the substation. This resulted in dropping the Cincinnati downtown network for 5 hours and 20 minutes affecting about 6,500 customers in a one and one-half square mile area. A power interruptiun of 696 megawatts occurred on May 11 affecting all of the load of Gulf States Utilities Company in Texas except for a very small area east of Doucette. Service to 163,000 customers was interrupted. About half of the severed load was industrial. Interruption was caused by the failure of a lightning arrester which in turn damaged a bushing on the high voltage side of a 500 megavolt-ampere transformer at the Sabine generating station and resulted in tripping out a 440 megawatt generating unit at the station. Five minutes later, a wave trap burned out interrupting one of two 138-kilovolt lines moving power from Louisiana to Texas and sequentially causing the second line to open. Within eight minutes, electric service to the entire Texas area of Gulf States failed except for the area noted above which, at the time, was connected only to Louisiana. Service was completely restored in about seven hours. There was no secondary damage to the company’s electrical equipment. At 10: 15 a.m., EDT, an interruption affected approximately 13,000,OOO people and 10,000,000 kilowatts of load in Pennsylvania, New Jersey, Maryland, and Delaware. The interruption was caused by a short circuit on a heavily overloaded 230 kilovolt transmission line carrying power from the lower Susquehanna River to Philadelphia. This was followed by automatic tripping of 430,000 kilowatts of generation at the new Muddy Run pumpedstorage project and the subsequent tripping of other lines and loss of generation. Power was restored after periods ranging from about one to ten hours. Attempts to operate remotely controlled switches to shift some of the load to an adjoining system were unsuccessful and a partial system interruption resulted. In July, 1966, when the Southern California Edison Company lost the entire output of a generating station ( 1,465,OOO kilowatts) ) amounting to about 25 percent of total system generation, ties to adjoining systems became over-loaded and opened. Collapse of the Company’s system was prevented by automatic load-shedding through the action of under-frequency relays which performed exactly as intended. Although installed in 1960, this was the first occasion in which these relays were brought Pennsylvania - New jersey - Maryland Interconnection, June 5,1967 23 \ into action. This interruption is a noteworthy example of the value of load shedding as an emergency measure. One of the principal cascading power failures of recent record occurred January 28, 1965, prior to the Northeast failure, and affected most of the utilities in Iowa and parts -of five other mid-western States. In many respects, this failure was similar to the one in November 1965, in the Northeast. It affected a larger area but considerably fewer peopleapproximately two million compared to 30 million in the Northeast. Service was restored within two and one-half hours. This interruption was initiated by a loose connection in a protective relay circuit at the federally-owned Fort Randall power plant in South Dakota. The relay disconnected six generators at this station resulting in a loss of 240 megawatts. It also opened all lines into the substation at the plant. Loss of these lines caused widespread instability of the network, isolation of various areas, and a general collapse of power operation in the sixstate area. A similar cascading interruption occurred in this same area in June, 1962-also from the m&operation of a relay at Fort Randall. Five electric power disturbances occurred on June 7, July 12, 18 and 2 1 and August 1, 1966, on the Western Interconnection. The Western Interconnection includes investor-owned and publicly owned interconnected electric systems in the 11 western states. The five disturbances resulted in losses of power loads ranging from 312 megawatts to 975 megawatts, for varying periods up to 45 minutes. Each was of a cascading nature and resulted in separating the Interconnection into a number of isolated areas. These disturbances were unnoticed by most of the people in the area, since most of the loads interrupted were those of industrial customers. A number of power failures have occurred on systems which are adjacent to the utilities which serve most of Texas. The Texas utilities are interconnected among themselves, but not with the bordering systems. This absence of interconnections has contributed to a number of power failures: near Sweetwater, Texas, on August 10, 1964 ; at El Paso, Texas, on December 2, 1965 ; at Beaumont, Texas, on December 6, 1965, and again at Beaumont on May 11,1967. PJM Power Failure, June 5, 1967 A 10 million kilowatt cascading power failure occurred on a major part of the area served by the 24 POWER FAdRE IN THE PJM INTERCONNECTION June 5, 1967 Generalized Area of Outage FI~URB 7 Pennsylvania-New Jersey-Maryland interconnected utilities (PJM Interconnection), beginning at 10: 16 a.m. on June 5,1967. Spreading across 15,000 square miles in eastern Pennsylvania, New Jersey and the Maryland-Delaware peninsula (see figure 7), the interruption .affected about 13 million people and lasted for periods varying from one to ten hours. Service was 70 percent restored by 3 : 00 p.m., 90 percent by 5: 00 p.m., and to all areas by 7: 55 p.m. The failure was similar in many respects to the 1 Northeast failure of November 1965. It began ; with the interruption of an overloaded 230 1 kv line which was transmitting power to Philadel- 1 phia from hydroelectric generating plants on the E lower Susquehanna River. The interruption, by prearrangement of system controls, simultaneously disconnected the full power output of the new Muddy Run pumped storage project on the Susquehanna River. The four units of the plant at the time were generating 430 megawatts. The exact sequence of further line openings and 1 loss of generating plants in the area has not yet been clearly defined. It appears, however, that the initial 1 incidents precipitated very abnormal system conditions causing numerous additional line segments and some generating units to trip out of service over a period of about two minutes. By 10: 18 a.m., the automatic inflow of power into the distressed area from neighboring systems, backed by systems throughout the nation, reached 1500 megawatts. At I that time, some of the in-feeding lines became overloaded and opened, creating an electric island. Power gc after the minutes the time area had The 1 to restor Ph ia in its hydr generati power tc prompt delays 1 were ha ing uni island 1 develop a seconc Basic adequal In’ Mlabu b WVLLANI ELECTRIC lLLUHlNAllNG I ; iAl Power generation in the island began to fail rapidly after the loss of tieline support, and within five minutes all generation in the island ceased. At the time of total failure, frequency in the separated area had declined to 52 cycles per second. The Philadelphia Electric Company was able to restore power in the downtown area of Philadelphia in a little less than one hour. It reconnected its hydroelectric resources and rebuilt its steam generation without particular difficulty and restored power to load blocks in its service area in relatively prompt sequence. Most other PJM systems experienced some difficulty in restoration. There were delays for rebuilding boiler pressures, and some were hampered by temporary damage to generating units. Restoration of power in a part of the . island was further delayed when local instability developed as loads were being reconnected, causing a second loss in generation. Basically, the failure occurred betause of inadequate transmission, not only within the PJM Interconnection, but in the ties of the Interconnection to surrounding systems. The tie between PJM and southeastern New York which opened on Nov. 9, 1965, again opened on this occasion because of inadequate capacity. The failure occurred on the eve of energizing part of a new 500 kilovolt transmission system extending east and west across Pennsylvania and on the eve of the initial operation of a 900 megawatt generating unit, the first of two identical units being constructed at the Keystone Station in western Pennsylvania. By greatly accelerated effort, a segment of the 500 kilovolt system was made ready and energized on June 11, and the initial unit of the Keystone plant was placed in service under very light loading on June 18. The line which failed was a 50 mile segment of the 230 kilovolt network extending from the Nottingham substation near the Susquehanna River to Plymouth Meeting near Philadelphia. Through an inadvertency, the line became more heavily loaded than planned. Under an interim program to secure MAJOR TRANSMISSION LINES OF THE PJM INTERCONNECTION Including Significant lines (230 KV and Above) in Service at 10~00 AM June 5, 1967 and lines Scheduled for Service by December 31, 1967 from’ one to ten NIAGARA MOHAWK lCLEVE ELECT IllUMlNAl overloaded 230 wer to Philadel- i IALLEGHENY WWER SYSTEMI \ ’ -. . . I (( IALLEGHENY LEGEND lines became overelectric island. 0 GENERATING STATIONS A SUBSlAllON & SWITCHING STATIONS - 500 KV LINf - 230 KV LINE -- fUTURE LlNf SCHEDULED FOR SERVICE BY DEC 31 1967 MANY GENERATING SIAMNS ARE NOT SHOWN IVIRGINIA ELECTRIC a- FIGURE 8 25 the advantage of power from the new Muddy Run project prior to placing the 500 kilovolt system in service, the 230 kilovolt line was scheduled to carry power only from the Muddy Run project. That part of the power from the Conowingo Project which had been carried on the Nottingham line when only two units of Muddy Run were operating, was to be transferred to another 230 kilovolt line assigned to carry all of Conowingo’s generation. By error, however, the Nottingham line continued to carry a part of the Conowingo load in combination with the full output of the four units at Muddy Run. The opening of the line occurred when the long spans of the line sagged physically as the temperature of the overloaded conductors increased. At about midway point of the line, one of the three conductors of the circuit came in close proximity to a 4,000-volt distribution line which crossed underneath, resulting in a flashover and fault which caused both the highvoltage and distribution lines to open. With the exception of two utilities, none of the PJM systems was equipped, on June 5, to shed loads automatically. At the beginning of the disturbance on the morning of June 5, the central dispatch office of the PJM Interconnection started calls to order a 5 percent voltage reduction on all PJM systems, a procedure which is occasionally employed and results in about a 2 percent reduction in load. However, only Baltimore Gas & Electric, Potomac Electric, and General Public Utilities received the calls before the system conditions deteriorated to a point where it was apparent &at some form of separation was imminent. A review of the failure reveals that the attempted relief had little effect, good or bad, because the failure occurred before any significant reduction could be effected. Although all PJM system operators have instructions to shed loads manually when system frequencies decline, no companies took action to do so except for a minor drop of 125 megawatts by one utility. Had automatic loadshedding been available, relays would have temporarily interrupted less than 10 percent of the load in the island area to bring generating capability and load demands into quick balance, permitting very early reconnection of the island area to the main network. PJM’s spinning and ready reserves then could have restored service to the interrupted loads in a matter of 15 to 20 minutes from the start of the incident. It appears that some of the difficulties and deficiencies which attended the Northeast failure of November 1965 were also present in the PJM experience. 26 Reporting Power Failures In order to secure timely and useful information on significant power failures, the Commission [ amended its regulations in December 1966 (Order 1 No. 33 1) to require all electric utilities throughout the nation to report any interruption in bulk power supply which involves transmission facilities of 69 t kilovolts or above and causes load interruptions of 1 25,000 kilowatts or more for a period in excess of i 15 minutes. If the interruption exceeds 200,000 kilowatts, the utility must report to the FPC by tele- t phone as soon as praticable. Through June 12, 1967, fifty-two power interruptions were reported in accordance with Order No. 331. Seventeen of the failures were caused I by natural phenomena and 25 were the result of equipment failures. Two were triggered by the t actions of birds, one by malicious destruction of in- : sulators, four by human errors, one by malicious tripping of circuit breakers, and two by small planes flying into transmission lines. These interruptions are summarized in table 2 on pages 28 and 29, and are briefly described in appendix E. The of th Over help flashc avoic open mom of a I Sh0l-l Furtl light fore! equil 01 whit sever togel be re iines. In a he: accu flash Summary of Power Interruptions from 1954 to wher 1966 i thee 01 In order that a longer term review could be made t torn: of the nature and magnitude of interruptions which have occurred on power systems in the United f r o m whit States, information was assembled fro;n various Atla! sources on interruptions which have occurred since effec 1954. A summary of these and their locations are ing t presented in appendix E. Although detailed ina ba formation is meager, the survey presents the gen- 1 tions eral nature and frequency of interruptions which Indi: have affected the supply of electric power for this rate la-year period. The list includes only those interthef ruptions which were sufficiently important to gain in II some measure of public notice. has It appears that a number of these interruptions t work involved transmission network instability and sepaUtilil ration, the precursor of potential cascading failures. t Poe Others were local in nature, affecting load areas area, served radially from the network. Fifty-three perSt cent of the failures were due to storms, 32 percent majc to equipment failures, 6 percent to operator errors, I t pow1 and 9 percent to other causes. ston In the category of weather-caused interruptions, Ir lightning is a frequent offender. A lightning stroke volt; can cause a very high voltage flashover from con- c been ductor to conductor or from conductor to ground. tion: t ‘ormation mm&ion 6 (Order .roughout ilk power ties of 69 options of excess of ,000 kilo: by telejer interth Order e caused result of 1 by the ion of inmalicious all planes :rruptions 3 29, and 1954 to be made Ins which : United 1 various -red since rtions are :ailed inthe genns which r for this ?se intert to gain rruptions tnd sepa; failures. bad areas wee per! percent or errors, ,ruptions, ng stroke rom con) ground. The 60 cycle power then follows the ionized path of the lightning arc in a continuing short-circuit. Overhead ground wires above the power circuits help greatly in fending off lightning strokes. If a flashover occurs, permanent interruptions are avoided in most instances by the automatic fast opening and reclosing of circuit breakers. The momentary opening of a breaker for about a third of a second permits the arc to be extinguished. The short interval of line opening is scarcely perceptible. Further protection is provided at substations by lightning arresters which divert lightning surges before they reach vital and vulnerable terminal equipment. Outages sometimes occur from the effect of wind which can cause conductors to oscillate and in severe storms occasionally to swing close enough together to cause &hovers. These vibrations can be reduced by installing vibration dampers on the iines. In some circumstances, problems may arise from a heavy buildup of ice on conductors, or from heavy accumulation of snow on equipment. Frequently, flashovers occur from conductors whipping together when ice begins to melt and falls to suddenly unload the conductors. Other atmospheric causes of interruptions are tornadoes, which occur most frequently in a belt from Texas to the Great Lakes, and hurricanes, which wreak their destruction primarily along the Atlantic and Gulf coasts. Probably the most severe effect of a tornado on power facilities occurred during the night of April 11, 1965. The storm, in effect a barrage of tornadoes, caused extensive mterruptions of local service from Iowa through Illinois, Indiana, Ohio and into Michigan. Some 37 separate tornadoes were identified as having affected the facilities of the American Electric Power system in Indiana and Ohio. However, the system, which has developed a strong internal transmission network and has strong connections with neighboring utilities, was able to reroute power over undamaged portions to maintain service in almost all of its area. Storms are less likely to affect power service in major metropolitan centers, because most of the power facilities are underground and protected from storm damage. In a few areas subject to frequent storms, high voltage transmission facilities above ground have been especially designed to withstand storm conditions. Utilities in Florida, for example, have success- fully employed a “hurricane proof” design for highvoltage transmission lines. Many storms, however, cause damage and local interruptions, even though special protection is provided for high voltage transmission facilities. Although it is not possible to prevent direct ,damage to equipment and transmission lines from severe weather phenomena, transmission systems can be planned, as exemplified by the continuity of bulk power service on the American Electric Power System despite extensive tornado damage, to prevenr localized damage from causing a widespread power failure. Interruptions Avoided A power interruption is immediately obvious to the general public, but the instances in which interconnections assist in preventing interruptions go unnoticed. Few people are aware of the frequency with which sudden outages occur in major generating and transmission equipment. In most cases the automatic and instantaneous rerouting of power over the network to points of need prevents an interruption in service. A number of instances have occurred in recent years in which the amount of power suddenly lost has approached the magnitude of the initial surge which started the Northeast failure of November 9. Some instances of disturbances which probably would have caused interruptions to service except for the support afforded by the system’s own network or through its interconnections with other utilities are described below. The information was assembled by the Commission’s Regional Advisory Committees. A study of the Pennsylvania-New Jersey-Maryland Power Pool (PJM) discloses that on 129 occasions since 1955, a unit, and in one case, two units, tripped off with a loss in generation to the system of 200 megawatts or more. In the most extreme case, the unit lost represented about 67 percent of the owning system’s load at the time. PJM’s intra-pool and inter-pool connections replaced the loss of generation, and in no instance was customer load interrupted or curtailed. The Southeast Region reported a total of 57 incidents between January 1, 1964 and June 30,1966, involving equipment outages totalling 12,397,OOO kilowatts, or an average of 218,000 kilowatts per outage. Seven outages of about 500,000 kilowatts were reported. In only one of these incidents was curtailment of load required. 27 TABLE Z-Power service intmupfions reported in amwdamc with -iUtility Date 1967 Location -- 1-15 1-16 l-24 l-25 l-26 l-26 l-28 2- 2 2- 8 2- 9 2- 9 2-15 2-17 2-20 2-24 2-25 2-25 2-27 2-28 3-6 3-10 3-10 3-12 3-14 3-16 3-19 * 3-19 3-26 3-27 3-27 3-27 3-28 3-28 4-12 4-13 4-16 4-19 4-20 5 - l 5 - l 5-8 5-11 5-12 5-12 5-17 5-19 5-25 5-26 6-2 6-5 6-9 6-12 Marias River Electric Coop . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . MoreauGrandElectricCoop . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . UnionElectricCompany . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ProvoMunicipal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Grand River Dam Authority . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Illinois Power Company . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ElPasoElectricCompany . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Fulton, Ky., Municipal. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Tennessee Valley Authority . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ChugachElectricAssociation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Moreau Grand Electric Coop. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OhioEdisonCompany . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Public Service Co. of Indiana. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Burbank Municipal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Carolina Power d Light Co. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Tennessee Valley Authority . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Ariiona Public Service Co . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . GeorgiaPower Company . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Texas Power d Light Company . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Duquesne Lighting Company. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pacific Power &’ Light Co . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Tennessee Valley Authority . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Moreau Grand Electric Coop. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Western Interconnection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Sacramento Municipal Utility Dist. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Grand River Dam Authority . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Sherrard Power System. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Marquette Bd of Lt B Pwr . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pacific Power 63 Light Co . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Tennessee Valley Authority. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Georgia Power Company . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Utah Power.@ Light Company. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Puget Sound Pwr. d Lt. CO . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Bangor HydroElectricCo . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Jefferson Davis Elect. Coop. Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Muscatine Iowa Municipal. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Bailey County Elect. Coop. Assn. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Western Interconnection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Community Public Service Co. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Carolina Power & Light Co. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . South Carolina Electric &’ Gas Co . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Gulf States Utilities Co. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Virginia Electric 133 Power Co . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Greenville Texas Municipal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cleveland Electric Illum. Co . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . South Texas Electric Coop. Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Bonneville Power Administration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cincinnati Gas 6? Electric Co. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SnohomishCounty PUD . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . PJMInterconnection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Utah Power & Light Co. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pennsylvania Power d Light Co. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Shelby, Montana. . . . . . . . . . . . . . . . . Timber Lake, S.D . . . . . . . . . . St. Louis County. . . . . . . . . . Provo, Utah. . . . . . . . . . . . . . . Oklahoma. . . . . . . . . . . . . . . . . Champaign-Urbana . . . . . . . . ElPaso,Tcxas . . . . . . . . . . . . Fulton, Kentucky . . . . . . . . . . Bowling Green, Ky . . . . . . . . . Anchorage, Alaska. . . . . . . . Timber Lake, S.D . . . . . . . . . . Massillon, Ohio. . . . . . . . . . . . Batesville, Ind . . . . . . . . . . . . . . Burbank, Calii. . . . . . . . . . . . Asheville, N.C . . . . . . . . . . . . Johnson City, Tenn . . . . . . . . . S. W. Arizona . . . . . . . . . . . . . Fulton-Cobb Cntys. . . . . . Grayson B Adj Cntys. . . . . . . Pittsburgh, Pa.. . . . . . .. Crescent City, Cal. . . . Bowling Green, Ky . .. Timber Lake, S.D. . . . . . Washington-Colo . . . .. Sacramento, Calif.. .. ... Oklahoma. . . . . . . ... .. ... Orion, Illinois. . . . . Marquette, Mich. . . . . . Enterprise, Ore . . . . . . . . . . . . . . . . . .. Mayfield, Ky . . . . . . . . . . . . . . . Marietta, Ga. . . . . . . . . . . . . . . . . . . Southeast Utah . . . . . . . . . . . . . . . . . East Seattle, Wash. . . . . . . . . . . . . . . Veaaie B Vincent, Maine. . . . . Cameron Parrish, La. . . . . . . . Muscatine, Iowa. . . . . . . . . . . . .. Muleshoe, Texas. . . . . . . . . . . . . Washington tY Idaho. . . . . . . . Princeton, Texas. . . . . . . . . . . . Rocky Mount, N.C. . . . . . . . . . . . Charleston, S.C . . . . . . . . . . . . . . . Beaumont, Texas. . . . . . . Richmond, Va. . . . . . . . . Greenville, Texas. . . . . . . Cleveland, Ohio. . . . . . . . Corpus Christi, Texas. Spokane, Wash. . . . . . . . . Cincinnati. Ohio. Everett, Wash. . Pa., N.J., Md., Del. Salt Lake City, Utah. Frackville, P a . . . - * Not Reported 28 . . E 115 kv USBF High windsTornado.. . . Line short-l Lighting arre Icing-high 1 Bii nest on I Lightning. . . Current tran Arcing horn : Line pin cam Construction Transformer Lost 55 mw I Broken insul; Transformer Plane hit 69 1 Ground wire Disconnect s\ Flood-lost I Wet, heavy s: Current tram Icing on 69 k Overload due High wind-. X-arm Failec Insulator co* Broken insul; Insulators shz Bird shorted i 115 kv condu Water leak tr Cable or pod Flash over on Salt spray COI Tree feIl on t Insulator fail Line tripped Wind and lig Not determiu Tree fell on 1 Insulator fail Lightning an Generator exl OCB’s openeq Unexplained Crop dusting 13 kv cable E Brushfire... Operating en Not reported Lightning an w rcfiorted in accordance with FPC Order .No. 331 through June 12, 1967 .Cause MW Los 1 Customers Duration HI% - .......... .......... .......... .......... .......... .......... .......... .......... .......... .......... .......... I:. . . . . . . . . i--*-*-......... .......... .......... .......... .......... .......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... - 115 kv USBR line fault . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . High winds-galloping conductors. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Tornado . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. Line short-falling snow . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Lighting arrestor failure. : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Icing--highwinds . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Bii nest on substation bus. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Lightning.................................: .................... . Current transformer failure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Arcing horn failure on switch. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Linepincameout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Construction material blew into substation. . . . . . . . . . . . . . . . . . . . . . . . . . . Transformer tap changer failure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Lost55mwunitduetoLosAngelesfault.. . . . . . . . . . . . . . . . . . . . . . . . . . Broken insulator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Transformer tripped, over temperature. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Planehit69kvline . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Ground wire fell on 115 kv line . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Disconnect switch insulator broke . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Flood-lost Elrama Generating Sta. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Wet, heavy snow on 120 kv line. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Current transformer failure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Icingon69kvline . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Overload due to switching. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . High wind-jumper burned off . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . X-arm Failed-Pole caught fire. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Insulator contamination. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Broken insulator..............................................~ . . Insulators shattered by gun shots. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Bird shorted insulator. . . . . . . . . . . . . . . . . . . . . . . . . . . . , . . . . . . . . . . . . . . . . 115 kv conductor burned at clamp. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Water leak tripped 138 kv circuit. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cable or pothead failure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Flash over on 46 kv-loose connection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Salt spray contaminated insulators-69 kv. . . . . . . . . . . . . . . . . . . . . . . . . . . Tree fell on 69 kv line-lost 56 mw plant. . . . . . . . . . . . . . . . . . . . . . . . . . . . Insulator faileddross arm burned. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Line tripped while BPA was installing relay. . . . . . . . . . . . . . . . . . . . . . . . . . Wind and lightning tripped 138 kv line. . . . . . . . . . . . . . . . . . . . . . . . . . . . . Notdetermined . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Tree fell on 115 kv line-lost substation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . Insulator failures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Lightning arrestor failure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Generator exciter failure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OCB’s opened manually. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Unexplained differential relay operation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . Crop dusting plane damaged line. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 kv cable failure and fire in generating station. . . . . . . . . . . . . . . . . . . . . . Brushfire . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Opvatingerror . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Notreported . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Lightning arrestor failure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . E Min. - 7.0 4.0 75. 0 15. 0 30.0 30.0 25.0 1.0 64.0 37. 5 2.0 50. 0 28.0 10. 0 27.0 37. 6 25.0 56.0 30. 0 120.0 28.0 50.0 2.0 282 50. 0 30.0 10. 3 10. 5 5. 0 52.0 23. 8 35. 0 45. 0 35.2 6 27 9 10.11 9 25 38 700 38 23 80 14.6 31 48 60 ), 300 105 163 2,900 2, 708 75, ooo 12, ooo 2 17,000 N.R. * 1, 648 N.R.’* 18, 100 2,500 20, ooo 6, 182 3, ooo 16,000 Johnson Cy 4,500 20, ooo 18, 000 8 6, ooo 2 2, 200 50, ooo 37,748 2 5, ooo 8,500 2,500 25, 000 N.R.’t 8,400 22, ooo 42,000 2, ooo 8, ooo NR* I: NR3 c 3, 140 1 15,080 163,008 12,508 9, 108 66, ooo 17,135 SCW.d thousand 4QfJOQ 15,000 13,000,080 NR* 78,000 - 03 31 1 16 1 25 30 20 30 15 35 20 04 15 20 35 33 22 52 36 29 43 30 36 16 18 13 24 23 25 53 50 32 59 50 20 27 27 23 30 00 a 8 a a 1 a 1 0 0 0 1 0 0 0 0 4 3 0 1 0 0 9 1 0 6 0 0 0 0 0 3 2 1 NR * 1 0 0 6 0 3 0 0 1 __ J - I l.?-- ’ 02 59 16 22 24 20 28 50 16 00 29 30 15 24 I - 29 The West Central Region indicated a total of 170 incidents between January 1, 1964 and June 20, 1966. Over 90 of these outages exceeded 100,000 kilowatts and several exceeded 500,000 _ . *kilowatts. For example, Commonwealth Edison ---%mpany had four incidents during this period when one of its 580,009 kilowatt units tripped out of service while carrying full load. Records of one occasion indicate that over 95 percent of the loss was supplied by Commonwealth’s neighbors through interconnections. No transmission lines opened and no customer load was dropped. The East Central Region reported 13 1 equipment outages during the 2ya year period from January 1, 1964 through July 1, 1966, without any loss of customer load. The South Central Region reported a total of 236 incidents between January 1961 and August 1966, involving generating unit interruptions with- ’ out any loss of customer load. t The credit to interconnections in the instances reviewed is not necessarily limited to preventing a loss in load equal to the loss in capacity of generating equipment which failed. Without the support F of an adequate network, some of the outages might well have led to large system-wide or area-wide failures. Ct 1I Compositic In the di\ tion, the UI unique amor 3,500 system , Nor&east Rq Investor-ow Public (non Cooperative F&d.... Total.. East Central Investor-ow Public (non Cooperativl Federal.. Total. Southeast Re Investor-ov e. t Public (no1 Cooperativ Federal. Total. South Centri Investor-01 Public (no: COOpuati\ Federal.. Total. 1 Include I 1 y loss of a total of nd August tions with- i )e instances mventing a 1 of generatihe support pages might I area-wide CHAPTER 4 COMPOSITION, INTERCONNECTION AND COORDINATION OF ELECTRIC SYSTEMS Composition of the Industry In the diversity and complexity of its organization, the United States electric utility industry is unique among the power systems of the world. Over 3,500 systems, varying greatly in size, type of ownership and range of power supply functions, participate in the generation, transmission, and distribution of electric energy in the United States. T ABLE The industry is made up of four segments according to types of ownership-investor-owned utilities, state and local public agencies, cooperatives, and Federal agencies. Data on the size, number of systems, functions, and energy requirements of each segment are tabulated by regions for the contiguous United States in tables 3 and 4. Figure 9 illustrates the geographic distribution of 3.-Regional distribution of electriG utilities-Z965-By function Number of Systems Number of Systems Ownership Engage in Generating and Transmission Engage in Distribution Only 111 182 31 9 63 54 3 9 48 128 28 0 Total . . . . . . . . . East Central Region: Investor-owned. . . Public (non-Federal). Cooperatives . . . . F e d e r a l . . 333 129 204 54 256 108 0 33 95 5 0 21 161 103 0 Total. . . . . . . . . . Southeast Region: ’ Investor-owned. . . . Public (non-Federal). . Cooperatives. . . . . . Federal. . . 418 133 285 40 324 194 4 27 33 9 3 13 291 185 1 Total. . . . . South Central Region: Investor-owned. . . . . Public (non-Federal). Cooperatives. . . . . . . . Federal. . . . . . . . . . . . . 562 72 490 53 381 201 6 34 154 13 6 19 227 188 0 Total. . . . . 641 207 Total Northeast Region : Investor-owned. . Public (non-Federal). Cooperatives. . . . F e d e r a l . Total West Central Region: Investor-owned. . . Public (non-Federal). . Cooperatives. . . . . Federal. . . . . Sngage in Generating and Transmission Sngage in Distribution Only . . . . 85 706 272 4 56 300 20 4 496 252 0 Total. . . . . . . West Region: Investor-owned. . . . Public (non-Federal). . Cooperatives. . . . . . . Federal............... 1,067 380 687 94 252 165 18 49 89 22 17 45 163 143 1 Total . . . . . . . . . . . . Summary for the Contiguous United States: Investor-owned 1. . . Public (non-Federal). Cooperatives. . . . . . . . . Federal. . . . . . . . . . . T o t a l s . 1 Includes 20 industrial concerns that supply energy to customers. . . 29 352 262 725 72 39 175 1,376 899 2 1,098 2,452 T ABLE 4 .-Regional distribution $‘clcctrk utilities-1965-by size of entrgy requirements Annual Energy Requirements, Billions of Kwh I ownership -z-Over 10 0.1-l .o 1.0-10 Jnder 0.1 -Northeast Region: Inv*ltor-owned . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Public (non-federal) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cooperatives. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Federal Government. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111 4 0 0 0 22 1 0 0 18 14 1 0 67 167 30 9 Total Number of Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . East Central Region: Investorswned . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Public (non-federal) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cooperatives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . FederalGovernment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 23 33 273 7 0 0 0 19 1 0 0 8 14 3 0 20 241 105 0 Total Number of Systems. . . . . . . . . . . . . . . . . . . . . . . . . . . . Southeast Region: Investor-owned . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Public (non-federal). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cooperatives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Federal Government. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 20 25 366 418 6 0 0 1 8 7 0 2 3 74 37 1 23 243 157 0 40 324 194 4 7 17 115 423 2 0 0 0 19 4 0 1 9 16 12 1 23 361 189 4 Total Number of Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . Weat Central Region: Investor-owned . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Public (non-federal). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Coopffatives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Federal Government. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 24 38 15 2 1 1 22 13 17 2 46 691 254 1 272 4 Total Number of Systems. . . . . . . . . . . . . . . . . . . . . . . . . . . . West Region: Investor-owned . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Public(non-federal) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cooperativei . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Federal Government . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 19 54 992 1,067 14 9 0 2 18 44 18 5 60 198 147 10 94 Total Number of Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . Summary for the Contiguous United States: Investor-ownedl..................................... Yublic (non-federal). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cooperatives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Ftderal............................................. 4 25 85 415 23 1 0 2 97 24 1 6 78 175 88 9 239 1,901 882 24 Total number of systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 128 350 Total Number of Systems. . . . . . . . . . . . . . . . . . . . . . . . . . . . South Central Region: Investor-owned . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Public (non-federal) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cooperatives. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Fe&&Government . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 Includes 20 industrial concerns that supply energy 32 to customers. Of and t quire large] Total - - - 182 outp1 31 stanti cilitie tram1 with kilow 9 333 t = Ec watts. .S t 252 165 t 1 8 f 529 Rl. ! i 67 167 111 182 30 9 31 9 -I 273 c 333 20 241 54 256 105 0 108 0 366 418 23 243 157 0 40 324 194 4 Ii i systems in each of the four segments. The boundaries of the six regions listed in tables 3 and 4 are shown in figure 10. Of the 1,100 systems that engage in generation and transmission, only 154 have annual energy requirements in excess of one billion kwh, but these larger systems produce more than 90 percent of the output of the electric power industry and own substantially all principal bulk power transmission facilities. More than half of the 1,100 generating and transmission systems are small municipal systems with energy requirements of less than 100 million kilowatt-hours per year.22 At the present time, many 22 Equivalent to a system peak of 20,000 to 25,000 kilowatts. of these small systems and a few of the larger systems, such as the Columbus and Cleveland municipal systems in Ohio, are electrically isolated. More than two-thirds of the electric utility systems in the nation, mainly small municipal and cooperative systems, engage only in the distribution of electricity. Many of the 899 distribution cooperatives are members of generating and transmission cooperatives (G&T’s) and thereby participate indirectly in the generation and transmission functions. A substantial number of the 1,376 public (non-federal) systems that are engaged only in distribution are supplied partially or entirely with power produced at Federal projects or by public power entities such as the Power Authority of the SERVICE AREAS OF ELECTRIC UTILITY INDUSTRY In the 48 Contiguous States INVESTOR-OWNED UTILITIES NON-FEDERAL PUBLICLY OWNED SYSTEM (Municipal,State,Countv.and Power Districts) 562 23 361 189 4 53 381 201 6 641 1i 46 691 254 1 85 706 272 4 .SINGLE UTILITY SYSTEM SINGLE MUNICIPAL SYSTEM-LIMITS OF SERVICE AREAS OF STATE POWER AUTHORITIES AND UTILITY DISTRICTS ORGANIZED UNDER STATE STATUTE DEFINED BY SHADING l 1,067 ’ I 60 198 147 10 94 252 165 18 RURAL ELECTRlC COOPERATIVE SYSTEMS FEDERAL MARKETING AREAS 415 i 239 1,901 885 24 -j - From 1964 National Power Survey FICXJRE 9 33 State of New York. Much of this power, except in the TVA area and to a large extent in the Pacific Northwest, is wheeled over the facilities of the investor-owned companies. Most of the remaining distribution systems purchase their entire requirements from investor-owned companies. Interconnection of Utilities The framework of interconnections has changed materially since 1939 when the electric power industry of the United States was divided into numerous relatively small groups of interconnected systems. The progression of interconnections from 1939 to today’s pattern of nearly complete interconnection throughout the country is depicted on figure 11. The most recent joining of areas occurred in February, 1967, with the closure of four transmission lines in the west to tie together electrically the eastern and western grids. Although the great majority of the nation’s power systems are now interconnected in a single network, the network is not strong enough at many points to assure adequate support in the event of emergency. Some inter%onnections are, in a sense, round about and others can do little more than maintain the \JL- areas which they join in synchronous operation under normal conditions; many tie lines have insufficient reserve capacity for superimposed emergency loads. Until very recently, for example, the systems in the northwest were not interconnected with those in the southwest except indirectly through Idaho, Wyoming and Utah, an interconnection of very limited strength. Similarly, tie-line capacities are very limited between the southwest systems and the south central areas; between northern New Mexico and El Paso, Texas; from the northwest to the north central states; and from the Upper Missouri River Basin to systems in Nebraska. The four ties mentioned above as interconnecting the eastern and western grids are of limited capacity. Most utilities serving areas entirely in Texas still have no operating interconnections with neighboring areas across state lines. Systems in Michigan za are interconnected with the main net28 The principal Michigan systems (Detroit Edison Company and Consumers Power Company) have entered into an agreement with systems in Ohio and Indiana for the construction of two 345-kv interconnections betwee,n the two groups, expected to be completed on or before January 1, 1970. NATIONAL POWER SURVEY REGIONS -, FEDERAL POWER COMMISSION POWER SUPPLY AREA REGIONS SELECTED FOR UPDATING THE NATIONAL POWER SURVEY FKXJRE 10 GROWTH OF INTERCONNECTED SYSTEMS OPERATING IN PARALLEL mous operation e lines have inz-imposed emer‘or example, the t interconnected xcept indirectly ah, an intercon,imilarly, tie-line reen t h e southI areas; between so, Texas; from states; and from o systems in Nemove as intercongrids are of lim; areas entirely in ,connections with ines. Systems in .th the main net- 1962 /etroit Edison Com- 1967 j have entered into nd Indiana for the dons between the i on or before Jan- BOUNDARIES OF INTERCONNECTED SYSTEM SERVICE AREAS (Generalized) UNSHADED AREAS INDICATE LOCAL SERVICE ONLY FICWRE 11 work of the U.S. only through the network in Ontario, Canada. Deficiencies in network strength in the northeast have already been discussed. Elsewhere in the east, networks need strengthening in western Pennsylvania and in parts of the PJM area, and between systems in Florida and areas to the north. Coordinated Planning and Operation Various arrangements for coordinated planning and operation have been worked out among some of the interconnected systems. The most comprehensive form of coordination is the formal power 26’7-781 O-674 pool under which two or more systems coordinate their resources in varying degrees for the supply of their combined loads under a contractual arrangement. The 18 major formal power pools now in existence are depicted on figure 12. Membership in these pools and in the principal planning groups outlined in figure 13 are listed in appendix C. Bulk power supply reliability and optimum economy are not automatically assured by the establishment of a formal power pool. Members must participate jointly in planning and operation of pool facilities and provide transmission ties that have ample reserve margins to operate within safe 35 MAJOR POWER POOLS metn lmas ghen COO1 ber I whit coor T: inch inter min agre lant to ir Cool mer pati StZil P the fun sew (Ii) Denotes Holdtng Company Peal Q Denotes a pod formed sim 1960. Note Pow PC& shown are hmtted to those ast&M under formal arrangements. FIGURE 12 and stable limits under emergency conditions as well as during normal loading. Maximum benefits are achieved when power pool members plan new generation and transmission facilities and operate these facilities as though the entire power pool were a single electric system. Benefits of Coordination Many benefits are available to member systems of fully coordinated power pools. For example, less total installed capacity is needed because of peak load diversity, diversity of forced outages, balancing of load forecasting errors, coordinated planning of capacity additions, and diversity in schedules for unit maintenance. Operating costs are reduced by centrally dispatching power from the most economical sources of the pool. Greater reliability can be expected through the pooling of generation and transmission resources, and through the pooling of talent to study network stability, develop sound transmission and control systems, determine operating limits, and program spinning and standby reserves. The PJM Interconnection The Pennsylvania-New Jersey-Maryland Interconnection (PJM) is an example of a formal 36 Tb cltl era sub pez power pool which has gone far toward establishing a mechanism for useful coordination. This pool consists of six full members including one holding company with four operating subsidiaries. In addi01 tion, PJM has three associated systems which par. . . ticipate in many of the coordinating functions. The O t l members of PJM coordinate the planning of new I hti generation and transmission facilities. They operate of the existing facilities with free flowing ties as though an PJM were a single electric system. The service area ab of the PJM utilities and the major transmission lines sin of this interconnection are shown in figure 8, co page 25. VI Each member in PJM is responsible for providing ar capacity to meet its own loads plus its proportionate en share of total required system reserves. New generash tion is scheduled taking into consideration the retic sults of joint planning with the objective that total pool capacity will be adequate to meet total load and reserve requirements. All generation is dispatched under central control. Capacity and energy transactions are accounted for after the fact with savings shared equally among the parties to each bl transaction. ai At present, coordination between PJM and neigha: boring groups is accomplished through agreements between the members of PJM and one or more 1 establishI. This pool me holding zs. In addiwhich parctions. The ing of new hey operate :s as though service area nission lines I figure 8, r providing Dportionate lew generaion the ree that total al load and dispatched ergy transt with saves to each and neighagreements le or more ! members of the New York Power Pool, the Carolinas-Virginia Power Pool (CARVA), the Allegheny Power System, and the Central Area Power Coordination Group (CAPCO) . Each PJM member receives some portion of the financial benefits which result from transactions under each of these coordination agreements. The PJM agreement permits pool members to include the loads and resources of associated systems interconnected with them for the purpose of determining pool transactions. This provision of the agreement permits associated systems such as Atlantic City Electric and Delmarva Power & Light to improve system reliability and economy through coordinated planning and operation with pool members. These two associated systems are participating in the 1,800 megawatt Keystone Generating Station. Although the P JM pool has increased its role over the years in coordinating the planning and operating functions of its members, it currently suffers from several of the difficulties that are affecting the reliability of bulk power supply in a number of areas. These problems, briefly reviewed in chapter 6, include delays in the scheduled start-up of new generation and energizing new transmission, which has substantially reduced reserve margins for meeting peak loads this summer ( 1967). Other Forms of Coordination In addition to the formal power pools, many other, less comprehensive, coordinating mechanisms have been developed. Among these are a variety of agreements under which systems exchange power and energy to achieve improved economy and reliability of power supply. Such contracts range from simple emergency assistance agreements to highly complex arrangements for the exchange of various types of electric services. Another coordinating arrangement of growing’importance is the joint enterprise in which several entities join in the ownership of a single generating plant or both generation and transmission facilities. Various organizations have been formed to engage in inter-system planning on an area or regional basis. The work of these groups is generally carried out by committees composed of representatives of the several members Some of these groups have been successful in developing comprehensive plans and constructing bulk power facilities on a large area or regional basis. Several new organizations intended to encourage some degree of coordination have been established or announced recently. One of these, the Northeast Power Coordinating Council, has been discussed in chapter 2. In February, 1967, it was announced that a Reliability Coordination Agreement had been executed by 23 investor-owned utilities in the East Central area.24 The stated purpose is “to augment reliability of the parties’bulk power supply through coordination of the parties’ planning and operation of their generation and transmission facilities.” The agreement, besides providing for a representative board which will establish principles and procedures for system operation involving reliability also expresses intentions to study the possibility of additional arrangements that will also contribute to operating economies. The agreement also establishes a Coordination Review Committee which is charged with the responsibility for reviewing with each party to the agreement its plans for generation and transmission facilities and other matters relevant to reliability and to guard against adversely affecting the reliability of other ECA members’ bulk-power supply. It also establishes a full-time manager to coordinate decisions made by the various operating and planning committees. Another procedure for coordinating two or more interconnected systems is corporate merger or the formation of a holding company. After merger or holding company affiliation, management normally will begin to operate the facilities as a single system and to plan for new facilities on a single-system basis. With few exceptions, mergers in recent years have been in the form of acquisitions of small utilities or parts of utilities by larger systems. The formation of new holding companies has become very infrequent. Areas for Improving Coordinating Organizations The inventory of existing coordinating groups recently completed by the Federal Power Commission’s Regional Advisory Committees indicates that some power pools are too small, by themselves, to ** An area including all or parts of the States of Indiana, Ohio, Kentucky, Virginia, Maryland, Tennessee, West Virgina, Michigan and Pennsylvania and one which approximately corresponds with the area served by the Commission’s East Central Regional Advisory Committee. The principal exceptions are the systems in Michigan which are expected to become parties to the Agreement when the interties across the Indian-Michigan and Ohio-Michigan borders are completed. 37 take full advantage of large-scale, efficient generating units, and EHV transmission. However, many of these are attempting to gain the advantages of more extensive coordination through membership in regional planning organizations which provide opportunities for both formal power pools and individual systems to participate in joint planning over broad geographic areas. The creation of a large number of planning organizations in recent years has resulted in overlapping in some areas as illustrated in figure 13 ; 25 in others there is no regional planning organization at all. For example, although subsidiary utilities of the Southern Company, which operate in Georgia, Alabama, Florida and Mississippi, are well coordinated among themselves, and there is some degree of coordination among utilities in adjacent Florida, they do not participate in a common regional coordis The eastern boundary of MAIN (No. 3) has been changed very recently to eliminate overlapping with ECARCA (No. 11) . nating organization.26 Such an orgamzatlon COUICI help make better use of the available opportunities for economy, including a seasonal load diversity in the order of 1,000 megawatts between Florida and areas to the north. Continuing Problems Some of the most challenging problems of successful operation of planning and pooling organizations pertain to ways of reaching accord among the various members and the resolution of disagreements as, for example, where one or more members decline to participate in the construction of facilities which serve the entire area. The formation of planning and pooling organizations has often necessitated assurance to the several members that individual rights and prerogatives will not be overridden 1 IJy ! I1 I aa Announcement has been made recently of the formation of an organization comprising the eight electric systems of the CARVA and Southern System power pools to enhance bulk power supply reliability in the region. PRINCIPAL POWER PLANNING GROUPS IN THE UNITED STATES : : : : : : : : : : 2 Cmtrol Are.3 Pwe, Caxdin.a,ion Grwp - 3 M,d.Americo l”ferpOOl Ne,*ork - - - 4 M,d.Cootment Area Power Pionnerr - 5 Southwest Pow, Pool FICXIRE 13 I t f IrlaJ”“L) agreement i sions which made for 1 organization riod of tim The cone in that it c questioned debate that time it ma thwarting t element ant to reliabilit planning a solution in utilities is n rather to I reasons ant but these a teed in act Small sy! portunity t tion with fc rectly, but area and rt pools and small syste plete elect installatior erating cal if coordina generally : and inferi The chz permit int in emerge large. Sm: r coordir wganization could able opportunities J load diversity in wen Florida and i iroblems of sucpooling organizaaccord among the ‘on of disagreeEh br more members WYion of facilities Wmation of planlas often necessibers that individlot be overridden ently 01 the formaight electric systems m power pools to n the region. iD STATES by majority vote. As a consequence, unanimous agreement is often required at least in those discussions which affect all members. Usually, provision is made for withdrawal by any member from the organization following notice after a specified period of time. The concept of unanimity is not without benefit in that it can be expected to bring to bear, in a questioned decision, a thoroughness of analysis and debate that might not otherwise result. At the same time it may be expensively time-consuming and thwarting to vital progress. Tie can be a critical element and delays can be as severe a transgression to reliability as lack of thoroughness in power system planning and operation. It would seem that the solution in the bverall interest of the public and the utilities is not to sweep aside the minority view, but rather to recognize the right to object for valid reasons and to call for further study and analysis; but these accomplished, planning should then pmteed in accord with the preponderant view. Small systems usually have not been given the opportunity to coordinate their planning and operation with formal power pools, either directly or indirectly, but recently they have begun to participate in area and regional coordination as satellites of power pools and planning organizations. Hundreds of small systems, however, are still operating in complete electrical isolation. This has resulted in the installation by many small systems of reserve generating capacity that would not have been needed if coordination were practiced. Isolated operation is generally accompanied by higher production costs and inferior reliability. The characteristics of electrical networks which permit interconnected systems to assist each other in emergencies apply to small systems as well as large. Small systems participating in power pools or coordination agreements must expect to carry their share of responsibilities associated with interconnected planning and operation. Their generating capacity and operating reserves must be maintained and must be operated under standards and controls which are commensurate in quality with those of the larger systems. To the extent it may be physically impossible for a small system to fulfill all such obligations in kind, equalization should take the form of exchanging power or dollars among the systems. Among the problems of interconnected system coordination are the equitable sharing of costs and the division of ownership of interconnecting facilities. Such problems appear to be especially acute where the systems differ greatly in size and in type of ownership. No formulae have been accepted as universally applicable to these situations. However, policies and practices are evolving through discussions and negotiations among utility systems and in formal and informal proceedings with regulatory agencies in which a wide range of pertinent factors are being considered such as relative benefits, methods of participating, reliability of service, conservation of natural resources, alternative opportunities and broad equities. Conclusion Interconnection and coordination of systems has been progressing steadily in recent years. Some of the more widespread forms of coordination at the present time, particularly among relatively large systems, include interchange arrangements, formal power pools, joint enterprises and joint planning. In addition, it appears that the industry is properly placing growing emphasis on coordinated planning on a regional scale, partly under the impetus of the Northeast power failure. These developments are commendable, but greater progress is essential if the industry is to keep pace with the multiplying demands for reliable, low-cost power. * 39 CHAPTER 5 KEY ELEMENTS FOR RELIABILITY IN THE PLANNING AND OPERATION OF INTERCONNECTED POWER SYSTEMS Imaginative planning and thorough analysis are 0th key ingredients in engineering of bulk power Istems. The inherent challenges have attracted a igh order of technical talents, Opportunities and aponsibilities presented by the increasing interxrnection and coordination of electric utility sys:ms should stimulate continued attention by creave engineers. Electric system planning proceeds continuously nce effective planning must consider tentative lans for distant needs while at the same time comleting arrangements for the immediate future.2’ loreover, effective planning is intimately tied to rstems operation. The progress of technology intenfies the systems approach, intrinsic to this industry. The electric utility industry deals in a unique nergy process. It produces, from the heat of bumig fuel and nuclear reactions or from falling water, different form of energy which travels at the speed F light and must be consumed by the customer bads as it is produced. Generation must continuusly be equal to load in the operation of power rstems. The load balance fluctuates continually as lstomers alter usage, and system balances change ,henever a generator or a part of the transmission rstem suddenly becomes impaired or is tripped out. ‘he changed requirements can be met very briefly y stored energy from the electromagnetic fields of re generators themselves and the mechanical in-tias of the rotating turbines or rotors. Within a ratter of seconds or less, however, load variations eed to be matched by variations in the input of rime energy. The ability of a group of generators ) operate continuously and reliably to meet loads epends on the capacity of such generators to rexmd rapidly to meet changing needs and on the istribution of generators and loads throughout the stem. The ability of the entire system to maintain RThe Advisory Committee on Reliability has underken an extended treatment of the planning process. See olume II, Appendix F. stable operation depends on these factors and the transmission capacity tying together the various parts of the network. The stronger the transmission ties, the better assurance there is that under severe disturbances generators over a wide area will remain available to share the load. Electric system planning identifies and evaluates alternative bulk power arrangements in terms of load requirements, reliability, capability, resources, finances, and social factors, such as air pollution requirements. Effective system planning considers the potential place of each alternative in subsequent programs. The system planner seeks programs which can achieve the lowest construction and operating costs possible within the planning constraints of the utility or group of utilities for which he plans. In our judgment these constraints should include severe criteria for reliability of design and operation applicable to a broad planning region as well as to the subareas within the regional interconnection. Reliable service on any system depends on the careful planning and operation of that system; today’s system planner, however, must be concerned not only with his own system’s needs but also with the needs of surrounding systems serving communities hundreds of miles away. Planning and operating a system successfully, therefore, are exciting processes which require the cooperation of many individuals. Key Elements in Reliability The likelihood of power failures, whether of major or minor proportions, depends upon the quality of planning, operation, and maintenance of interconnected power systems. A weak link in the chain of producing and delivering bulk electric power which may cause only a liited interruption in one instance, can in others, be the precipitating factor in a widespread failure. 41 Power interruptions may be caused by inadequate transmission systems, faulty settings or action of relays, failures in power system equipment, poor workmanship or maintenance, insufficient provisions for load relief, insufficient training of operators, neglect of emergency procedures, communication failures, defective or inadequate instrumentation, lack of standby emergency power, willful damage, severe storms and floods, and many similar factors. The precipitating causes are numerous, but systems can be designed and operated to withstand such incidents without an ensuing power failure. Key challenges confronting reliability of bulk power supply can be grouped under the following elements : (a) Carefully prepared projections of load requirements sufficiently far in advance to permit orderly planning, construction and testing of new facilities to serve the projected loads. (b) A transmission network designed to withstand possible disturbances of major proportions. (c) A frequently reviewed and updated system of operating controls and protective devices. (d) Rigorous adherence to well planned and continually updated operating practices, including provision of spinning reserves, emergency load shedding, and where appropriate, generator dropping. (e) Continuous power, isolated from the effects of a system disturbance, for communications, data collection, and switching operations. (f) Standby power for the safe rundown of generating units if system power is lost. (g) Standby power for rapid restarting of generating facilities. (h) Use of equipment specially designed to withstand adverse environmental conditions in areas where they occur frequently. This chapter examines in detail these aspects of power system planning and operation and recommends various means of enhancing the reliability of interconnected networks. a 1980 in order that a general pattern of long-range trends could be identified and analyzed. In the up dating of the National Power Survey now in progress, the Commission, with the assistance of the in- I dustry, is extending these projections to the year 1990. Such projections of load and resources permit a useful generalization of the nature, magnitude and location of facilities likely to be needed in the fairly distant future, and hence provide perspective on how early expansion may be consistent with future i needs. Long range planning brings into earlier i recognition the magnitude of problems which will arise in siting, water supplies, rights-of-way, air and water pollution and other environmental effects, and provides a better grasp of topics needing early study and research. Projections of ener,7 require- I ments to 1980, developed in the Commission’s National Power Survey, are illustrated in figure 14. I Intermediate-range projections, about 10 years ahead, can guide the more detailed planning of generation and transmission which in a few yean F will be moving into the final design stages. Pro- I grams to meet loads 10 years in the future may re- ! fleet new concepts in size and types of generating units, higher transmission voltages and other technological advances which could require more than normal time for examination and coordinated planning. The need for this range of planning is underscored by the fact that coordination among a large number of utilities has become a principal requirement in achieving reliability, and that such coordi- ELECTRIC ENERGY REQUIREMENTS* 1960-1980 load Projections A system planner is concerned with assuring that the needs of every customer will be met. Therefore, the planning of any system starts with a projection of future power requirements. Long range load projections, generally on a service area basis, have been used by most utilities for many years. The National Power Survey, published by the Commission in 19&, included load projections of this type to 42 nation ( plannin! Cons1 facilitie! of need’ conside: activitic expansi and hc: forms 0 The made a several the nai mands Peaks contim day. T utilitie Year* I preced 7.2 pe trends which demo1 develc the r: equip, Ma areas ment ObViO expec i n dc the sz [ &efc i apro lead mall undo l 1970 1960 Includas Industrial InPlant Generation tLlIi1 from 1964 Nahnal Power SurW EfoURE 1980 Plan ing Arm 14 and pattern of long-range analyzed. In the upSurvey now in prog: assistance of the inejections to the year and resources permit jlture, magnitude and e needed in the fairly Dvide perspective on :onsistent with future brings into earlier problems which will rights-of-way, air and nvironmental effects, ! topics needing early 1s of energy requirene Commission’s Na:rated in figure 14. .ons, about 10 years detailed planning of which in a few years I design stages. Pron the future may re1 types of generating ages and other techd require more than nd coordinated plan>f planning is under.ation among a large I a principal requirend that such coordi- PUIREMENTS” nation can add several years to the normal system planning process. Construction programs for major generating facilities must be firmed up, or nearly so, on forecasts of needs six years in advance. Specific trends to be considered are near-term commercial and industrial activities of the area, seasonal trends in population, expansion in use of electricity for air conditioning and heating, and the activities of promoting other forms of energy. The marked influence of weather on loads was made abundantly clear in the summer of 1966 when several utilities in the central and southern parts of the nation had difficulty in meeting peak load demands during a prolonged period of hot weather. Peaks were much higher than normal and loads continued at high levels for many hours of the day. The peak load of one of the major midwestern utilities was 12.4 percent higher than the previous year. Peak loads of this utility had increased for the preceding five years at an average annual rate of 7.2 percent. Other utilities in the area had similar trends. This experience emphasizes the problems which can arise from unexpected load trends and demonstrates how rapidly a serious situation can develop from causes such as extreme weather and the rapid rate of installation of climate control equipment. Many instances of power shortages in various areas of the Nation point to a need for improvement in load forecasting techniques. Although it is obvious that completely accurate results cannot be expected, some systems have expended much effort in developing better methods of forecasting. At the same time, many reports indicate that too often the forecasting procedure consists of little more than a projection of past load growth. lead Time for Planning and Construction 1980 The elapsed time between the decision to buy and install an item of equipment and the date when it is available for service is commonly referred to as lead time. Current reevaluation of lead time is extending the period beyond that normally allowed in past years. More time is needed under today’s requirements for broader coordinated planning. Longer times are elapsing between ordering and commercial operation of new facilities. Among the causes of frequent delays in manufacturing and construction, are shortages in skilled labor and Iabor-management disputes, and more exten- sive testing of new equipment of expanded size and voltage. Additional time also is needed to obtain approval from local bodies or federal authorities of the location of generating plants and transmission lines, and to acquire sites and right-of-way. A few years ago, utilities generally found four years to be adequate for the design and construction of most generating capacity. Lead time for fossil fuel units now ranges from four and a half to five and a half years, and about a year longer for nuclear additions. Lead time for transmission additions has ranged from one and a half to two and a half years depending upon line length, right-of-way problems and terrain, and type of construction. More recently, it has increased to two to three years and to as high as four and one half years for some EHV additions. Considering these trends, firm plans for new facilities should be formulated as far as six years in advance of the date of required initial operation. This, however, should not preclude shorter lead time for final planning and construction of component elements of system expansion if shorter periods for these elements will not endanger meeting firm schedules for commercial operation. Indiscriminate use of expanded lead time could result in adding unnecessarily to the expense of system development or in precluding use of the latest technological improvements. System Generating Reserve In order to provide a continuity of supply, all power systems must have available more generating capacity than their aggregate loads. The desirable amount of this spare capacity, known as “reserve,” varies from system to system. It is affected by a number of factors, including system size, the sizes and types of generating units, system load characteristics, and system maintenance practices. Reserves are needed to offset errors in load forecasting, to replace machines taken out of service for regular maintenance or emergency repairs, and to provide minute by minute ready reserve capacity. Satisfactory operating performance requires the continuous availability of reserve generating capacity for quick response when unusual demands are placed upon the system. This is generally called “ready reserve” and is defined as capacity that can be produced or supplied in 10 minutes or less.28 g Appendix I, Volume II. 43 Ready reserve for most systems is the sum of two components : (a) spinning reserve, which is generating capacity connected to the bus and ready to take load automatically by prime mover control action; and (b) non-spinning reserve, which is capacity that can be fully realized within 10 minutes. It may include quick-starting capacity at rest, such as hydroelectric or gas turbine and diesel engine driven units ; temporary emergency capacity that may be obtained from some units by temporarily increasing steam pressures above normal operating limits, and at some sacrifice in’thermal efficiency, by.reducing the amount of steam normally diverted from the turbine for boiler feedwater heating; loads which may be dropped under interruptible power contracts; or pumping loads which can be interrupted quickly at pumped-storage hydroelectric projects. Typically, a utility or a group of utilities may maintain a minimum ready reserve of 6 percent of the area’s predicted load and a spinning reserve not less than 3 percent of the load. Coordination among systems with different seasonal load characteristics can permit substantial reductions in aggregate reserve margins required and at the same time afford increased system reliability. Experience during the Northeast power failure indicated some need to distribute spinning reserve margins in smaller increments among a larger number of generating units in order to assure faster response. The Regional Advisory Committees’ surveys of the practices followed by most utilities throughout the U.S., indicate that there is general recognition of the need to maintain adequately distributed spinning reserves. Providing the desirable amount of reserve is a problem which requires continual attention because loads rise sharply at peak periods, and can change rapidly with shifts in the weather and from unusual local circumstances. Most forms of spinning reserve, however, are incapable of replacing a major loss in generation suddenly imposed by the formation of an electrical island, such as occurred in the Northeast failure. This inability is discussed in chapter 2. Importance of Transmission in Reliability The importance of adequate transmission is clearly expressed in the report of the Commission’s Advisory Committee on the Reliability of Electric Bulk Power Supply. Transmission must be recognized as the principal medium for achieving reliability, both within a system and through coordination among systems. It is the cohesive 44 force which ties together power systems. Cascading power failures are usually the result of insufficient capability within the transmission links of a system or group of sys. terns to withstand the sudden demands placed upon them by reason of disturbances arising within or outside the system. In the interconnected networks, transmission has the multiple functions of energy transportation and system integration. The latter involves the need, not only to dis. patch generation economically, but also to handle emergency flows resulting from facility outages and system disturbances which will create sudden power swings. Thir requires maintaining at all times margins of transmission capability above scheduled transmission line flows so as to tolerate such power swings. (Emphasis added.) Because of the self-interlocking character of alter= nating current, any change in load or generation at any particular point on an interconnected network instantly affects the flow of power over connecting transmission lines. The effect diminishes with increased distance from the point of change as an increasing number of lines and generating units share in the reaction to it. Such immediately responsive changes in flow over the transmission system are the only sources of emergency power available instantaneously to a distressed area. Weak interconnections which join adjacent re- 1 gions are of little value in improving reliability and, in fact, can be harmful. The appearance of strength by the mere presence of connecting links can be seriously misleading. New and existing interconnections should be examined critically to determine whether the system has adequate capacity to remain in operation under a wide variety of assumed serious emergencies. The ability of a strongly interconnected network to withstand a severe disturbance was clearly demonstrated on TVA’s system on January 19, 1964, when 1,250 megawatts, the full output of TVA’s Paradise Generating Station was abruptly lost. The loss occurred when sheet metal from a nearby building was carried by violent winds into the station’s switchyard, creating a short circuit on the 161-kilovolt bus. Upon loss of the Paradise Station, the frequency on TVA’s system dropped from 60.005 to 59.95 cycles per second. Concurrently, power flows on TVA’s ties with other systems changed from a net outflow of 82 megawatts to a net inflow to TVA of 1,107 megawatts. All spinning generators on the TVA system responded quickly to the sudden deficiency in generation and within 4f/l minutes overcame the loss. The net outflow returned to 18 megawatts and frequency returned to 60.00 cycles. During the 4% minute recovery period, TVA increased its generation by 1,240 megawatts. Of this amount, 300 mc units and 940 IT Because TVA’S strength to car-r from other syst and the accom load and gener The change i nections with ot after the loss of ure 15. This fig reserve respond to normal. A similar inc the Virginia E TWO 500 kilovc Storm Plant ii megawatts of gc tie lines to neig maining netwc redistributed M customer servic A more det: transmission in ity is included strengthened t is illustrated a: gest the appro, to provide adec Regional ar Limiting the and operation of immediate problems of o but, as mentio the risk that regions will be connections at opening ties a disturbance. 1; entire regional inability to ret regions. Inter] exchange of prominent exz and winter sl nessee Valley 1 tric Companie Western Miss; area. ascading power ient capability r group of systed upon them or outside the a-smission has ion and system rot only to dis1 handle emeres and system :r swings. Thic ?f transmission 1 flows so as to d.) tcter of alter;eneration at :ted network ‘r connecting hes with innge as an ing units share ly responsive stem are the lable instanadjacent reliability and, e of strength inks can be interconnec3 determine ty to remain tmed serious ted network :learly demy 19, 1964, t of TVA’s tly lost. The earby buildhe station’s he 161-kiloion, the fren 60.005 to mower flows ged from a ow to TVA rtors on the sudden de!nutes overto 18 megacycles. d, TVA intts. Of this amount, 300 megawatts were supplied from steam units and 940 megawatts from hydroelectric plants. Because TVA’s interconnections were of adequate strength to carry the instantaneous inflow of power from other systems, isolation of the TVA system and the accompanying hazard of further loss of load and generation were avoided. The change in power flows on TVA’s interconnections with other utilities, immediately before and after the loss of the Paradise plant, is shown in figure 15. This figure illustrates how TVA’s spinning reserve responded and restored system generation to normal. A similar incident occurred in January, 1967 on the Virginia Electric & Power Company’s s;stem. Two 500 kilovolt circuit breakers failed at its Mt. Storm Plant in West Virginia, tripping off 950 megawatts of generation. Although two 500-kilovolt tie lines to neighboring s stems were opened, the remaining network ties held and power flows were redistributed without causing any interruptions to customer service. A more detailed discussion of how dependable transmission interconnections contribute to reliability is included in chapter 6. A general pattern of strengthened transmission throughout the Nation is illustrated and described in the chapter to suggest the approximate scope of the additions needed to provide adequate reliability by 1975. Regional and Interregional Coordination Limiting the size of areas of coordinated planning and operation has some merit from the viewpoint of immediate economic gains and the practical problems of organizing and conducting business, but, as mentioned above, such limitation increases the risk that interconnections between areas or regions will be inadequate. Weaknesses in the interconnections at the boundaries may contribute to opening ties and isolating systems during a major disturbance. In consequence, the reliability of the entire regional supply may be seriously impaired by inability to receive support from systems in adjacent regions. Interregional connections also permit the exchange of diversity loads between regions. A prominent example is the interchange of summer and winter surplus capacities between the Tennessee Valley Authority and the South Central Electric Companies, a group of utilities operating in the Western Mississippi-Oklahoma-Arkansas-Louisiana area. Progress in coordination has been accelerated within the last few years, and it is likely that the size of coordination areas will undergo continual expansion as loads increase, as larger scale generation and transmission become practical, as utility mergers and other consolidations continue, and as new techniques and control systems are perfected for accomplishing satisfactory coordinated operation in larger areas. Considering the current status of industry development, the physical and electrical geography of the interconnected network, the practical problems of organization, and the necessity for inter-area coordination, it appears that the most practical and effective overall program would be founded upon close coordination of utility systems on i. regional basis. The formation of planning groups directed towards these objectives have been described in chapter 4. Network Stability Analyses Analyzing the stability of large networks under possible abnormal conditions is an essential part of transmission system planning. The Northeast failure has spurred the industry to reexamine network stability utilizing more severe impacts and including larger areas of the network in the analyses. The report of the Commission’s Advisory Committee on Reliability of Electric Bulk Power SupPlY 2s recommends the following abnormal conditions as criteria for examining the stability of networks : The outage of any power plant, including the largest of any of the interconnected systems . . ., The outage of the most critical transmission line . . ., The outage of all transmission circuits on any one common right-of-way . . ., The outage of an entire transmission substation of any one of the interconnected systems . . ., and The sudden dropping of a large load or a large load center. Digital computers and sophisticated computer programs now make practicable the study of large interconnections, and permit extensive analyses that were impossible only a few years ago.3o As discussed in Chapter 2, studies of this nature were made for the Commission by task groups under the supervision of the Commission’s Advisory Panel for the Northeast Power Interruption.31 Similar studies Is Included as Volume II of this report. Jo Appendix G of the Report on the Reliability of Electric Bulk Power Supply. *I See Volume III. 45 constituted a significant part of the Northeast Tnterconnection Study by a private consultant for the Northeast Power Coordinating Council.3’ The Report of the Reliability Committee includes a detailed discussion of various aspects of network design and operation for system stability and emphasizes the need for capabilities such as high-speed tripping of circuit breakers to remove as rapidly as possible the damaging dynamic effects of short circuits, strong network connections to enable emergency power flows without serious overloads, and high-speed reclosing of breakers to restore system connections quickly in appropriate situations. The needs for automatic voltage and frequency regulating equipment in relltion to stable system operation are also discussed in Volumes II and III. Appendix A of this report includes a section devoted to the reports of the six Regional Advisory Committees on their surveys of recent studies of network stability under severe disturbances. Many of the interconnected groups have made comprehensive transient stability analyses using criteria similar to those recommended by the Reliability Committee. Other groups have not fully agreed upon criteria as severe as the recommendations suggest. Still others have not participated in analyses of severe disturbances on a region-wide basis or determined the expected performance of their own systems during disturbances originating elsewhere in the network with which they are interconnected. Making broad scale computer studies to investigate network stability and to identify improvements required to assure reliable network performance should be an important responsibility of regional coordinating groups. Direct Current Interconnections Direct current transmission has certain characterstics which, for particular applications, may offer advantages over the usual alternating current transmission. Some of these characteristics are of interest in considering possible ways of improving the stability of interconnected networks. Recent advances in dc terminal conversion equipment and reductions in cost have enhanced interest in and the opportunities for using direct current in EHV transmission. In the movement of bulk power for distances up to about 600 miles, ac is more * Northeast Interconnection Study, Stone & Webster Engineering Corporation, November, 1966. Summary recommendations are included in Volume III. economical; for longer distances dc transmission ? can have a cost advantage. The dc interties under construction on the west coast will move power 800 miles between the Pacific Northwest and the Pacific Southwest. Direct current transmission has been used in other countries for the transmission of power by underwater cables. Because of the problems involved in transmission of power by underwater or underground high-voltage alternating current cables,33 the cost of ac and dc transmission in such situations equalizes in the range of 35 to 65 miles. Direct current provides a means for transmitting a constant flow of power without regard to many 1 0 hi 225 I current network such as deviations in frequency, phase angle or sudden surges of power between the areas interconnected. In other words, the dc transmission line does not transmit “synchronous power,” and because of this difference some planners have considered that direct current interlinks between major areas could. help to resolve some of the stability problems which have resulted in severe power interruptions. As previously stated, ac interconnections have the characteristic of automatically moving power into -! areas which suddenly become deficient in power i supply. A dc line, on the other hand, does not have I the characteristic of automatic response and cannot resourcefully increase interarea support. Thus, while dc links could protect against the entrance I of undesirable surges from one area to another, they : are likewise incapable of transferring a desirable t surge in power. It is not inconceivable that control 1 equipment could be superimposed upon normal dc flow control equipment to detect a disturbance and Ii change the flow of power instantIy to help mainI : the complications, cost, and maintenance of such I equipment are imponderable factors at present. Thus some of the uniquely desirable characteristics of ac systems should not be overlooked when comc paring the two approaches. as None of the presently known insulating materials suitable for buried or submerged cables are perfect insulators. Because of this, small currents are produced in the insulation when ac voltages are impressed. These currents pro. duce losses which heat the cable and limit its load carrying ability. This problem does not occur with dc systems, and the absence of the cable charging current and insulation wear make the dc cable cheaper and practical for distances beyond the capability of ac cable. L ELEC conditions which normally affect flows in alternating tain the stability of the interconnected network, but RE! Tc MIDDI 124 MW TV RESPONSE OF INTERCONNECTED, NETWORK POWER FLOW TO SUDDEN OUTAGE OF TVA PARADISE STEAM PLANT transmission terties under e power 800 nd the Pacific b January 19, 1964 been used in of power by ilems involved lter or underrent cables,33 uch situations ,m 1 KENTUCKY UTILITIES r transmitting Rard to many in alternating in frequency, I between the the dc transmous power,” Aanners have inks between ne of the stasevere power Sons have the g power into :nt in power goes not have nse and canIpport. Thus, the entrance another, they ; a desirable : that control )n normal dc turbance and I help mainnetwork, but ante of such 1 at present. haracteristics j when com- materials suitfeet insulators. I in the insula: currents pro. s load carrying !c systems, and and insulation 11 for distances PLANT / I CAROLINA POWER AND LIGHT COMPANY 18 MW FROM TVA (a) LEGEND a - Power flow immediately before loss of Paradise b - Power flow immediotely after loss of Paradise TVA SYSTEM FREQUENCY SWING DURING DISTURBANCE 60.1 r1 TVA SYSTEM GENERATION RECOVERY 1 8500 4 4% MINUTES H z ti 60.0 5 -LOSS OF PARADISE 59.8 I ’ I I 10 PM I I I - _ I I or' 9 PM OTHER TVA SYSTEM GCNERATION " 9:39 " 9:40 " 9:41 , 1 " 9:42 9:43PM FIWRE 15 47 supply. A deficie tards the frequer on the generatin for an increase il ning reserve of t If the network a disturbance ar formance. Such when the large e areas became is connected netwc most immediate for four minute The decline in 13.000 showing general arrangement of equipment at north terminal of Pacific Northwest-Southwest direct current intertie. Buildings house converter valves to change power from ac to dc and vice versa. FIGURE 16.-Model These considerations, however, do not diminish the potential value of dc lines for the movement of large blocks of power over long distances or for transferring a block of power betwen power areas not otherwise interconnected and which could not be connected by ac lines of comparable cost without the risk of major instabilities. Problems of Separated Systems Regardless of the care with which individual and interconnected systems are planned and operated, some extreme event may occur which will cause a separation of interconnections. It is likely that should an area become isolated, it will be faced with a sudden imbalance between generation and load and may be forced to operate below normal frequency. Under these circumstances, generation and load balance must be restored promptly if the system is to continue in operation. Ordinarily, a surplus of generation is less difficult to a’djust, although the system frequency will increase momentarily until the turbo-generator controls react to reduce the output of the machines. Excess generation does carry the hazard of a generating unit being tripped by action of overspeed relays, or of an unstable condition developing through the machine’s pulling out of step. Instantaneous generator dropping may be helpful and even essential under special circumstances such as the sudden loss of transmission lines which are heavily loaded by the generating source. The objective is to prevent a surge from overloading other I interconnected lines, causing them to become unstable and trip out. I An area which becomes isolated with a substantial deficiency in generation has a serious problem in sustaining operation and regaining normal power 12.000 z ZE 9.000 8 000 5 z s z 3 2 s + 7.000 6.000 n z ti ! VJ E 3.000 ; !f y u ’ z 5 2.000 g 5.000 4.000 1.000 0 apply. A deficiency in generation automatically relrds the frequency of the power system, and controls n the generating machines will automatically call )r an increase in output, bringing into use the spining reserve of the area. If the network is too weak to remain intact during disturbance and a system or group of systems be3mes isolated, the reserves may not be able to funcon effectively in accordance with expected permnance. Such was the case of November 9, 1965, ,hen the large eastern New York and New England reas became isolated from the rest of the interonnected network within seconds after the disturbnce at Niagara. Due to the deficiency in generation, le frequency of the disconnected area dropped allost immediately to 59 cycles per second, progresvely declined to and remained at about 54 cycles )r four minutes and finally dropped to 49 cycles. ‘he decline in both frequency and generation is raphically portrayed in figure 1’7. Satisfactory operation of steam-electric generating nits, which made up a large proportion of the spinning reserve in the CANUSE area, is dependent upon many auxiliary devices such as boiler feed water pumps, forced and induced draft fans, and pulverizing mills for coal-fired units. A reduction in system frequency reduces the capability of these auxiliaries and can seriously reduce the capability of the boiler-generator unit. Unless these auxiliary systems are specially designed to produce rated outputs at reduced frequency, and few auxiliary systems are, steam generating units not only may be unable to increase their output if system frequency has declined to about 58 cycles per second, but may even have difficulty in maintaining the output which was being produced immediately prior to the disturbance. Furthermore, operation at such a low frequency for even a few minutes can seriously damage the turbine blading of large modern units. The performance of generating units in the eastern New York-New England area has been critically analyzed by the special task group appointed by the Commission. Their investigations are summarized in Volume III. GENERATION AND FREQUENCY VARIATIONS Eastern New York and New England 515 to 528 PM November 9, 1965 15.000 \ AREA REQUIREMENT AT 60 CYCLES PER SECOND 14.000 13.000 wthwest direcf L. 12.000 , 11,000 although the entarily unti :duce the outm does carry lg tripped by rstable condi‘s pulling out 60 10.000 I 9.000 8 000 7.000 6.000 5.000 lay be helpful nstances such es which are e. The objecoading other become unh a substanious problem lormal power I TIME OF INITIAL II - D I SDISTURBANCE TURBANCE 4.000 3.000 2.000 1.000 0 5:15 5:16 5:17 5:18 5:19 5:20 5:21 5122 TIME 5123 5123 5124 5124 5125 5125 5126 5126 5127 5127 5~28 FIOURE 1 7 49 load Shedding When a system or group of systems has become isolated and is operating at a marked subnormal frequency, action should be taken promptly to reduce the load temporarily, so that operation may be restored to normal frequency. Taking such measures will permit machines with spinning reserve to increase their outputs more rapidly because power to their auxiliaries will be less impaired. This also will permit early reconnection with surrounding systems and restoration of loads temporarily dropped. The frequency at which load reduction begins varies among systems and among sections of the country. Different levels may be selected to suit the ability of the generating plants of a system or group of systems to operate safely and to respond quickly under subnormal frequency conditions. The density and character of the service area may also influence the program for load reduction. Many systems will begin load reduction when frequency has fallen somewhere within the range of 59.5 to 59.0 cycles per second. The Stone and Webster Engineering Corporation’s report of the Northeast interconnection recommends that load reduction begin within the range of 59.7 to 59.3 cycles per second. Successive increments of load shedding should be scheduled to obtain adequate relief if a serious deficiency in generation occurs. It is suggested that an adequate program of load shedding should provide for as much as 50 percent reduction in the load. It is important that load be shed rapidly enough to prevent a frequency reduction below about 58.0-58.5 cycles. Otherwise, system recovery, unless it has large hydroelectric resources, is likely to be unduly prolonged, inviting further decline and possible collapse of system power. Load reduction can also be obtained by reducing system voltage but reduction by this means is usually limited to a few percent of total system load. Small amounts of load reduction may result from undervoltage tripping of motor loads in industrial plants if abnormally low voltages accompany a system disturbance. It is a common practice to protect large electric motors with under-voltage relays. There are some situations in which planned load shedding by undervoltage relays is useful or necessary in addition to underfrequency control. The transmission network in the Pacific Northwest, for example, has experienced severe under-voltage con50, ditions upon loss of a main circuit requiring tem- L porary load relief locally in the affected area. But the severity of a disturbance is more likely to be I evidenced by system frequency deviation than by voltage variations. Load shedding may not be effective, and in fact can be hazardous, if not coordinated by systems which are closely interconnected and likely to continue operating together during an area separation. :?; A change in frequency follows area isolation almost ‘i instantly. Unless arrangements are provided for rapid automatic control, there is little likelihood of I satisfactory load reductions by systems that may be operating together in the isolated area. As a consequence, an operator who is first to employ load shedding procedures might find his system carrying ! the brunt of the load relief. Conceivably this could compound the problem of stability by overloading ties and causing secondary separation in the isolated i area. These factors favor placing load reduction under coordinated automatic control. Each system, area and region should carefully I study its load shedding program to avoid the possibility of overloading inadequate internal ties if the deficiency in supply is concentrated in a very small ! part of the separated area. Such contingencies may require special consideration in the application of automatic underfrequency relays until adequate 1 transmission can be built. Some utilities serve industrial loads which can be ’ interrupted without significant injury or inconvenience. Often the contracts under which they are served have special terms permitting such interruptions and include provision for slightly lower rates. Efforts should be made to avoid shedding loads identified as highly essential or critical. Some changes in circuits may be needed to accomplish I this. The present application of load shedding on sys-. terns throughout the United States is illustrated in I figure 18. Although load shedding is shown to be utilized in large areas of the Nation, it should not be assumed that present practices are coordinated ’ fully adequate to meet the needs in all parts of th areas during severe system disturbances. Public acceptance of load shedding as a second ary safeguard against devastating failures can be expected once its assuring role is understood. Although much can be done to design cascade-fret H systems, there still can be no ultimate guarantee of infallibility of bulk power supply, even if utiliti a provided virtually complete duplication of powe buit requiring temb affected area. But is more likely to be :y deviation than by ,ffective, and in fact rdinated by systems d and likely to con; an area separation. uea isolation almost s are provided for is little likelihood of systems that may be d area. As a conseht to employ load his system carrying nceivably this could ility by overloading ,ation in the isolated :ing load reduction control. 3n should carefully 1 to avoid the possi: internal ties if the ated in a very small 1 contingencies may the application of lys until adequate loads which can be : injury or inconlder which they are :ting such interrupilightly lower rates. id shedding loads or critical. Some ded to accomplish Id shedding on sys.tes is illustrated in ng is shown to be on, it should not be tre coordinated or in all parts of these %bances. :ddjng as a secondng failures can be is understood. Aldesign cascade-free imate guarantee of ly, even if utilities plication of power UNDER 20% SCHEDULED FUA lNSTRLlATlUN IN 1967-68 I ~~~)lil’~i’iO OVER 20% ml Note: Wide variations occur within shaded blocks in the setting of under frequency relays. FIGURE 18 system equipment at the enormous cost which this would entail. The causes which can trigger severe disturbances are practically unlimited. Many of them are derivatives of severe storms, seemingly unaccountable equipment failures, or even the fallibility of well-trained system operators and maintenance men. The customer of a well planned and operated system should understand that any interruption of his load through load shedding would be infrequent and of short duration. The customer should recognize that it is much better to accept a brief load interruption than to undergo a prolonged disruption in service associated with total system collapse. Careful planning of load shedding programs and explaining their purpose to customers and to the public are important utility responsibilities. Utilities should work closely with state commissions and other appropriate governmental authorities in setting up their programs of load shedding, and in establishing suitable procedures for informing the 2867-781 O-67--5 public or parties who may be affected. These measures, properly accomplished, should be helpful in protecting utilities from individuals who press claims for damage because of actions for the public good. Relay and Control Systems Modern power systems are controlled by a wide variety of instruments and devices, many of which function automatically. The art of instrumentation and control undergoes continual improvement. Relays are used to protect power equipment and maintain service. They initiate corrective actions under abnormal conditions. Most of these devices are preset for certain limiting power characteristics and function automatically when these hmits are reached. Relays can be accurate and dependable in performance but they require regular maintenance and inspection. An important need is to update the million kilowatts, approximately the power requiretional changes k ment of Washington, D.C. and its surrounding absolute necessit suburbs, probably would utilize several thousand up communicatic relays on its bulk power supply system. In addition ppwer supplies c to those which detect transmission system power characteristics, others perform functions such as Computer AF detecting the formation of gas in high voltage transAnalog and d formers and sounding an alarm, or removing a geneconomic dispat erator from service if excessive temperatures deconnected netw velop in bearings or windings. and continuous1 Increased dependability and broader control crements of genl functions have been the objective of manufacturers taking into act and utility engineers in the design of control syscosts, and gene tems. Many of the relays are actually small comsend signals to puters which are capable of analyzing a number automatic incre: of power system characteristics and taking approinstallations are priate actions instantly. they work with Following the Northeast power failure, many situation which power systems across the Nation made special rethe computer. S examinations of their relay settings and the status of dispatch do no1 existing equipment. As an example, the Central era1 seconds or Hudson Gas and Electric Company reported that 1 tions, can be dl all transmission line relay settings were reviewed computer. and all protective devices field tested at least once Without que between November 9, 1965 and February 1, 1966. c L utilizing digital Dependable Communications FIGURE lg.-Static relay terminal ready for installation. Solid state devices are replacing many electromechanical components in modern relay design. Typically, the relays in this terminal might control several hundred miles of EHV line for phase and ground-fault protection. setting of relays or install updated relay controls as the system is modified or expanded to serve increasing requirements. Despite general reliability of relays, improper installation, faulty settings, inadequate maintenance or other forms of deficient operation continue to cause a substantial number of system interruptions. Six of the 173 significant interruptions in bulk power supply since 1954 resulted from undesired relay and control circuit performances. The causes include equipment failure, inadequate adjustments, and deficient maintenance. Closer coordination between planning, operating and maintenance staffs of utilities will help to eliminate errors in relay settings and better assure timely resetting or replacement of relays as system conditions change. Large numbers of relays are required for the average system. A utility serving a peak load of three 52 The Report on Reliability of Bulk Power Supply 34 points out the complete dependence of system control and dispatching upon both data and voice transmission, and emphasizes the necessity of maintaining vital communication links during system disturbances and operating emergencies. To accomplish this, continuously available standby or auxiliary power supplies must be provided at all communication, relay, and terminal points. The report recommends the use of alternative routes and back-up facilities for all critical needs. Furthermore, it suggests the various types of communication facilities that are suitable for particular services and the kinds of standby power arrangements that can supply essential needs during interruptions of the normal sources. Failure of communications greatly complicated matters on many of the Northeastern utility systems during and after the November 9 power failure. Subsequent actions by some systems have improved emergency communication resources, and addi*‘Included as Volume II of this report. The detailed discussion of communications is included in Appendix I of that report. 1 F IGURE 20.-C< proximately the power require‘, D.C. and its surrounding b uld utilize several thousand &r supply system. In addition Et transmission system power 1 perform functions such as P of gas in high voltage transi an alarm, or removing a genif excessive temperatures deindings. ility and broader control e $ objective of manufacturers [in the design of control sys:lays are actually small combable of analyzing a number Iacteristics and taking approY. rtheast power failure, many the Nation made special rerelay settings and the status of 4s an example, the Central ctric Company reported that relay settings were reviewed ices field tested at least once 1965 and February 1, 1966. tional changes have been planned by others. The absolute necessity of providing the necessary backup communication channels and reliable emergency ppwer supplies cannot be overemphasized. Computer Application in Con.trol Analog and digital computers are utilized for the economic dispatch of power on a number of interconnected networks. ’ These devices automatically and continuously determine the most economic increments of generation from the numerous sources, taking into account transmission line losses, fuel costs, and generator incremental efficiencies, and send signals to the selected generator to cause an automatic increase or decrease in unit output. Such installations are termed “on line” computers since they work with data describing the current system situation which is continually supplied directly to the computer. Since the actions needed for economic dispatch do not require split-second response, several seconds or even longer periods for some functions, can be devoted to the analyses made by the computer. Without question, new functions and controls utilizing digital analysis will be continuously intro- duced into the operation of power systems. Continual improvement is being made in display and print-out arrangements to aid system operators during abnormal conditions. In addition to display of information, computers can provide valuable assistance in making a wide variety of “security” checks on the capability of transmission networks to handle normal and emergency loads. “Security”, as used here relates to the assurance that various parts of a system will not be expected to function beyond their safe load-carrying limits. Security checks are particularly useful in scheduling operations when equipment is forced out of service or needs to be removed from service for inspection and repair or for the connection of new facilities. The computer can be programmed to provide reliable answers quickly for both plarined and emergency situations. Extensive computer installations are planned or are being studied by several interconnected groups. For example, the PJM interconnection will have a system in service by the fall of 1967 which will continuously maintain economic dispatch of the generators in service, monitor network loading, and check system security. Cunications liability of Bulk Power Supreplete dependence of system kg upon both data and voice hasizes the necessity of main!ation links during system dispg emergencies. To accomtsly available standby or kes must be provided at all pnd terminal points. bends the use of alternative F ilities for all critical needs. s the various types of comF t are suitable for particular 1 of standby power arrangeiessential needs during interburces. @ions greatly complicated j Northeastern utility systems !November 9 power failure. pome systems have improved btion resources, and addi,I1 of this report. The detailed ions is included in Appendix I FIWRE 20.-Consolidated Edison Company’s new energy control center in New York City was placed in service in March 1962. Perhaps the most imaginative analyses of possible applications of computers in system control are those being sponsored by the State of New York and by the Bonneville Power Administration. The practicability of extensive control systems capable of intelligence reporting and responding to rapidly changing conditions during system disturbances will be investigated. The use of computers for power system control has increased rapidly within the last few years. About 20 percent of the nation’s electric utilities now use them for various control functions. Virtually all utilities utilize computers for engineering design and system planning studies. The computer installations vary from relatively small machines which collect data and monitor operational variables in generating plants and control centers to very extensive and elaborate systems which analyze interconnected network situations and transmit control signals to cause automatic adjustments needed to preserve programmed operatinghitsorconditions. The operation of power systems may continue to becmne mox~ automatic with further advances in computesz, sensing devices and communications systema As higher degrees of automation are accomplished, the operator’s function will change toward monitoring computer control actions. This pqRSion towad automation, however, will be gradual and many intermediate developments must come firsr. &Xajjr advances must come in mariy areas such assezGqgde&es, rapid and mliile transmission of da#a to centd wntr01 points, almost instantaneoars onrnpaskr “.“agsis of the da@ coordination aB ceniza.l and satilite computers, and immediate &. - - of -czmarol %igd% to actuating devices. ~~as@emhasnotbeenprvposedinpractical form which could anaiyze and prevent tie splitsecond instability which characterized tie initial phase of the Northeast Power failure. Even, if saz&a& e&&o&c equipment were %~va.ilabh, prepamtim a& ,up&ting of the raqvired computer programs would be a tremendous undertaking. Furthermore, the very large number of sensing, oommu&ca&on and analytical devices involved would be subgct to 4justment, maintenance and toed t&&dive operation. To provide for wnA ava&abiiy3 two computers would need to be provided. These are some of the problems that mnst be taken ‘Il;llto account in evaluating the net ypir3s af p~uzgmkdy ezxpadd oornputer control. Restoration of System Sewices I Because of the ever present possibility that power interruptions may occur, it is important that emergency sources of power be provided for the auxiliary equipment that must continue to function for safe shutdown of generating equipment without damage, and for its subsequent rapid return to service. I From an operating viewpoint, it is desirable to I return steam units to service as quickly as possible after a shutdown, because the longer they are down, 1 the longer it takes to get them started again. Time ! required to pick up load is closely related to loss of heat in the boilers, and cooling of the turbine and generator. This was dramatically illustrated during the November 1965 power failure. The first units in the Consolidated Edison system were back in service in approximately two hours where auxiliary power was available. Where plants were without auxiliary power for five or six hours, it took almost that much additional time to get them ready to carry load I again. Electric generators used in the utility industry are driven by various prime movers, including hydraulic turbines, steam turbines, gas turbines, and internal combustion engines. Each has different startup I requirements. Hydroelectric projects, including pumped storage plants, can be started more quickly than steam units with their complex arrangements of auxiliary equip- I ment. Where available, hydro units may offer a convenient source of emergency startup power for I steam turbogenerators. Many systems, however, have no hydro units. Internal combustion units, such as the diesel engine and gas turbine, usually can be started quickly, and are self-contained. Gas turbines are being supplied in increasingly larger sizes, with some multiple unit plants as large as 14O,OOO kilowatts. The time required to bring a large gas turbine from cold start I to full load is about four or five minutes. Therefore, these units serve well to supply a source of startup or other standby power. Many items of auxiliary equipment are necessary for startup, continued operation, and safe shutdown of steam-electric generating units. Principal auxil- I iaries include boiler feed pumps, circulating water pumps, condensate pumps, draft fans, fuel handling I equipment, pumps for bearing lubrication and hydrogen sealing, and turning gears for off-line slow rotation of turbo-generators. Rotation is needed to t distribute the residual heat evenly around the tur bine to pre which migh tion during pumps mus bearings an generators. These au munication SOme auxili ures and SC Individu needs that which are . for emerge monwealth emergency pumps req ground piI Lack of a relative11 Northeast great atte: Regional i systems art service po’ types of pi November of the COI east Powe sary to prc at every distributes larly if sys plants wii hydro rest tion of g generator auxiliary Mainter The m o f camp available liability. the Corn nravated if relate for exan f r o m hrc chapter, failed. 7 ...on mites lossibility that power nportant that emerded for the auxiliary to function for safe ment without damlid return to service. nt, it is desirable to s quickly as possible mger they are down, started again. Time osely related to loss rg of the turbine and Iy illustrated during .re. The first units in were back in service Lere auxiliary power re without auxiliary >k almost that much eady to carry load e utility industry are including hydraulic rbines, and internal s different startup ling pumped storage kly than steam units s of auxiliary equip; units may offer a y startup power for systems, however, ch as the diesel en1 be started quickly, lines are being supwith some multiple kilowatts. The time bine from cold start minutes. Therefore, source of startup or )ment are necessary , and safe shutdown Its. Principal auxils, circulating water fans, fuel handling g lubrication and lsus for off -line slow ltation is needed to dy around the tur- bine to prevent differences in thermal expansion which might warp the shaft and cause severe vibration during later operation. For safe shutdown, all pumps must continue to function to lubricate the bearings and maintain the seals for hydrogen cooled generators. These auxiliaries, as well as station lighting, communication, and control systems must be supplied by some auxiliary source of supply during power failures and subsequent restarting of unZs. Individual systems have specific emergency power needs that may be peculiar to these systems but which are just as important as others in providing for emergency situations. For example, the Commonwealth Edison Company has provided small emergency generators to supply the cooling oil pumps required for circulation of oil in the underground pipe-type cable system in Chicago. Lack of adequate emergency power was noted as a relatively common deficiency at the time of the Northeast failure. It is an area that has received great attention subsequently. The reports of the Regional Advisory Committees indicate that most systems are providing sources of emergency station service power sufficient to alleviate the more serious types of problems encountered during and after the November 9 failure. As indicated in the critique of the Commission’s Advisory Panel on the Northeast Power Interruption, it is not considered necessary to provide “emergency crank-up power sources at every major generating plant. Appropriately distributed installations may be sufficient, particularly if systems have ready access to other generating plants with such crank-up power equipment or to hydro resources, or if they have provided for separation of generating units from the system so that generators can be kept operative on their own auxiliary loads.” Maintenance The maintenance of equipment and replacement of components when improved designs become available are particularly important factors in reliability. In a large number of failures reported to the Commission, the initial trouble has been aggravated by the subsequent failure or malfunction of related protective equipment. Simultaneously, for example, with the loss of power at Mt. Storm from breaker failures as described earlier in this chapter, a dc-powered emergency oil pump also failed. This resulted in damage to bearings and seals on one of the 570 megawatt generating units during the emergency shutdowns, and required returning thespindles to the manufacturer for repair. Adequate maintenance is a prime factor in reliability for all power system equipment from the largest generator to the smallest control device, and maintenance programs should be directed toward preventive rather than corrective actions. This entails firm schedules for overhaul and testing, and extends into coordinated planning and operation so that maintenance outages will not reduce area reserves to the point of endangering reliable system performance. The power interruptions reported in chapter 3 include a number of failures which resulted from incomplete coordination between staff elements. It is obvious that not only those involved directly in maintenance activities, but system operating and design groups as well, should participate in developing maintenance arrangements and programs. Much emphasis needs to be placed on a rigorous upgrading of maintenance practices. Criteria and Standards for Reliability Investigations since the November 9 power failure point to the need for criteria and standards as basic guidelines for improving the reliability of electric bulk power supply. Although it is recognized that particular circumstances might sometimes require consideration beyond a given set of minimum standards, such criteria and standards would help to eliminate weaknesses which exist in some areas of planning, operating and maintaining interconnected system facilities. Planning criteria, for example, could well begin with load projections and include consideration of the effects of weather extremes, surveys of appliance saturation, analysis of load diversity and delineation of areas for coincident peak determinations. General criteria for stability investigations have been recommended by the Advisory Committee on the Reliability of Electric Bulk Power Supply. Tliere may be reasons, in special circumstances for increasing or possibly decreasing the severity of the recommended contingencies. Other elements in guidelines for stability investigations could include the appropriate size of the area for analysis, the type of analytical programg to be employed, criteria for interregional stability studies, bases’ for describing system electrical characteristics, and procedures for establishing and updating regional inventories of electrical characteristics of facilities for use in stability studies. 55 Coordinated system planning and design should consider the matter of centralized area control with a view towards providing a limited number of central control offices to replace a large number of independent control points that currently exist in some coordination groups. Design criteria should insure adequate protection and provide for emergency operation of essential equipment, power to operate communication networks in the event of system disturbances, and minimum equipment and facilities needed in control centers to automatically and manually control interconnected systems. Criteria and standards should cover emergency power for generating plants and should consider the underfrequency performance of station auxiliaries. Because of the dynamic growth in electric loads and the continual evolution in new equipment and methods, criteria and standards must remain flexible. Furthermore, conditions vary widely throughout the nation, and what is desirable in one place may be essential in another, and perhaps even unneeded in still another. Operation Guides For several years the North American Power Systems Interconnection Committee (NAPSIC) , a voluntary organization of representatives of the operating sector of electric utilities, has issued operation guides to promote uniform and acceptable practices in interconnected system operation. Some of the guides pertain to such matters as time correction, and accounting for inadvertent interchange power flows, but others bear directly upon the reliability of system performance. Following the Northeast power failure, NAPSIC undertook a complete revision of its guides and after extensive deliberation approved an updated and expanded version for interim use. Those participating in NAPSIC are among the best qualified representatives of the operating sector of the industry and deserve much credit for their initiative in creating the organization and in promptly reviewing and improving the guides when the need became apparent. Of necessity the guides are a composite of industry thinking and sometimes a compromise of varying views. However, the committee is serving a useful and necessary function in 56 the discussion and resolution of problems in coordinating operating practices of interconnected systems. Need for a Central Study Group It would be useful for the industry to increase its coordination in the field of investigation and analysis to accelerate solutions to challenging problems and attainment of goals in electric system planning and operation. Many professional societies and associations have an interest in activities of the electric utility industry. Some have programs of continuing data collection and analysis on many subjects. These activities are praise-worthy and, produce beneficial results, but are characteristically limited in progress and breadth due to overworked volunteer assistance or sponsorship by a single industry segment. It is believed the industry would benefit from having a central organization supported by all segments of the industry to undertake studies of special subjects from which much could be gained by concentrating a common exploratory effort. Topics for coordinated analysis can be drawn from many problem areas in which better solutions would be useful to the entire industry. The study of advanced cooling methods; irnproved methods of load projection; nationwide study of load diversity; analysis of inter-regional exchanges to meet seasonal peaks; assembly and analysis of data on the performance of generating units under normal and abnormal conditions; studies of line reclosing problems; recommendations of advanced methods of security checks of system operation; evaluations of programs for operator training, studies of relative usefulness of various displays for system operators for prompt appraisal of system conditions, automatic equipment to analyze system disturbances and indicate correct emergency procedures-these are a few of the challenges to the industry today which are worthy of industry’s best talent. Investigative activities are generally oriented toward potential economic gains of individual manufacturers or the objectives of special groups. A Central Study Group could, in part, address itself to explorations left unapproached because of uncertain economic returns. -, .2$ ‘: ,d Inter size fl North sultin! hundr systen greate safety is car intere indus spreal tude, inter] Wi unus catas pro& adeq oper; elect inter qua1 and coor Tral T adec 1 CHAPTER 6 THE ROLE OF TRANSMISSION IN RELIABILITY Interruptions in bulk power supply have varied in size from the unprecedented interruption in the Northeast to localized incidents such as those resulting from severe storms or the failure of any of the hundreds of items of equipment in a bulk supply system. Widespread cascading failures cause the greatest economic damage and hazard to the public safety, but any interruption in bulk power supply is cause for concern. To safeguard the national interest and the public welfare, the electric power industry must accept the task of preventing widespread power failures and of reducing the magnitude, frequency, and duration of any bulk power interruptions to the lowest practical levels. With the exception of interruptions caused by unusually severe weather, earthquakes, or other catastrophic phenomena for which only partial protection can be provided, the industry has adequate technical competence, equipment, and operating knowledge to provide a reliable supply of electric power. The major defense against power interruptions, whether large or small, lies in high quality planning of interconnected power systems and in strict adherence to carefully developed and coordinated operating and maintaining programs. Transmission Objectives There are three principal objectives in providing adequate transmission capacity : 1. To support immediately any load area suddenly faced with a serious and unexpected deficiency in its normal generation supply. The network must have capacity to handle, well within stable limits, the automatic inflow of supporting power, from the hundreds of generators in the surrounding interconnected network. 2. To transfer, without serious restriction, capacity and energy within regions and between regions to meet power shortages. Emergencies can arise from innumerable causes, such as delays in commercial operation of new generation, problems with new equipment, the failure of major generating units or other elements of the system, and unexpected peak demands caused by weather extremes. 3. To exchange power and energy on a regional and interregional scale, and to achieve important reductions in generating capacity investments and in the cost of energy production. The value of having a network adequate to meet contingencies included under objective 2. above is illustrated by situations in two separate areas of the nation which are expected to have only marginal sufficiency to meet the 1967 summer loads. In the Pennsylvania-New Jersey-Maryland (PJM) pooling area, the completion of two large generators has been delayed from the scheduled date for commercial operation earlier in 1967. As a result, generating reserves are expected to fall to the very low margin of 3!4 percent. Commitments for firm power from neighboring utilities and load relief through voltage reduction, curtailment of load in the system’s commercial and office buildings, and curtailment of station light and power at all of the generating stations will increase the margin to about 8ys percent of estimated remaining load. Additional power may be available from other utilities as far removed as Michigan, Ontario, Canada, and New England in the north, Ohio on the west, and the Carolinas to the south. Some transmission lines will be heavily loaded during periods when power is imported and, in fact, additional power could be supplied if line capacities were larger. Interconnections between PJM and surrounding utilities will be substantially strengthened by EHV ties soon to be placed in service. At present, the capability of interconnecting lines to surrounding utilities is about 1300 megawatts, less than 7 percent of the area’s current peak load. Utilities in the area which includes Minnesota, Wisconsin, Iowa, Illinois, and part of Missouri, have experienced faster growth in summer loads for 57 the last two years than anticipated, and will have a deficiency in normal system reserves in the summer of 1967. Some power will be imported from surrounding utilities in Indiana and Kentucky. Additional power could be made available from these utilities and from the Missouri Basin System if intermediate networks were stronger. It appears that the margin of generating capability in this area, normally scheduled to be not less than 12 to 14 percent of the projected summer peak load, will probably be less than 10 percent this summer. Bases for Appraisal of Transmission Needs In order to gauge the general magnitude of desirable network strengthening, the staff of the Commission has made an appraisal of EHV lines that may be needed by 1975. The stafI appraisal utilized loads projected for 1980 under the concept that transmission network capability should lead, rather than risk lagging behind, the power generation requirements. In considering network contingencies, it was assumed that the Northeast disturbance was far from being the upper limit of impacts that could occur in the future as loads double and triple. Generating capacity at a single site in the next decade is likely to reach 3000 mw and the loads carried on some individual transmission rights-of-way may reach similar levels. Accordingly, instantaneous emergency support in large amounts should be available to areas of concentrated power use. The staff appraisal was guided in part by an examination of required transmission service to a number of principal load centers throughout the country to meet loads projected for 1980. The adequacy of transmission was judged on the ability d the lines to carry normal and emergency loading without exceeding 50 percent of the aggregate canying capacity of the lines, with one principal line out of the service. The assumed emergency loads var&~I from a minimum of 1250 megawatts to a maximum of 3OOO megawatts, representing, in general, abolnt 2,O TV 25 percent of the total peak load of the load center. Limiting line loading to 50 percent of a line’s capability was intended to allow for three principal conditions: ( 1) lines in a oonaplex network will not necessarily share loads in ptvpodon t o t h e i r n o m i n a l capabiUes; (2) dynamic loading from a disturbance can be much laager than steady-state loading; and (3) a large maxgin should be available for seasonal or other diversity flows, economy transfers, and emergencies which may continue for several weeks or months. In some areas, the appraisal was guided by prospective interregional power exchanges including emergency power movements. Possible Pattern of Needed Transmission A possible pattern of line additions, considered to be representative of a suitably strengthened EHV transmission system to meet projected loads for 1975, is shown in figure 21. About half of the added lines have already been programmed or are under consideration by various utilities or pools for completion in the late 60’s or early 70’s. A major portion of these are in the east central, north central, and far west regions of the United States. Other lines have been added where interconnections are nonexistent or are of inadequate capacity. The depicted pattern is the product of appraisal and judgment rather than detailed analysis, and individual lines are not to be viewed as specific recommendations. Rather, the pattern is intended to present a general outline that would encourage systerns to initiate the detailed studies required for broad coordination with emphasis on reliability, and to develop a dependable network that could serve areas now isolated from, or weakly connected with, the present main network of interconnected systems. Additions in EHV lines beyond those scheduled for service in 1967 include 16,000 miles of 345-kilovolt, 21,4OO miles of 500-kilovolt, 5,750 miles of 765-kilovolt and 1,665 miles of +750-kilovolt dk transmission circuits. In the general pattern depicted for 1975, the utilities in the northeast and southeast are more strongly integrated with the central body of utility systems in the east. The 765-kilovolt line which is shown on Figure 21 to overlay the 345-kilovolt network now under development in New England, is suggested to enable major flows to take place between the heart of New England and the central eastern section. It may be considered by some that 765 kilovolts is an unnecessarily high voltage to meet prospective requirements in this area. However, overlaying in single step increases such as 345-kilovolt with 500kilovolt can be uneconomic. The short time before another step is needed can result in unnecessarily short life of expensive equipment or added cost for large inventories of spare equipment to suit a multiplicity of voltages. Southeastern utilities are shown to be interconnetted with a 5OO-kilovolt loop which joins with the loop of corre! begun to span board from nor Strong nort cated, beginnir of Michigan, 1 Pennsylvania, 2 to utilities sen Electric Power voltage networ which span a s Virginia. At PI of 345-kilovob overlay networ 197 1. America tions with 21 s are at 500 kilt 138 kilovolts. ! transferring 4, kystem, more Relatively few interconnecti exporting or ir of peak load I The Hydrotario has ties v Michigan, and The present @ system is abou 1973 is projecl 58 percent wil tions and 42 p time, the larg the Lakeview with a capaci plants will in’ plant in westc Pickering Nut the new cap: Hydro’s majol ancing area lc Following i terns with tho in 1970, On from Windsor part of a new The increase the western en flows normal1 the 230-kilovo loop of corresponding voltage that has already begun to span a major section of the eastern seaboard from north to south. Strong north-south interconnections are indicated, beginning in the heavy industrial load areas of Michigan, Illinois, Indiana, Ohio and western Pennsylvania, and extending through the TVA area to utilities serving the Gulf states. The Americin Electric Power system has an extensive extra high voltage network interconnecting its six subsidiaries which span a six-state area from Michigan to West Virginia. At present, the system includes 1800 miles of 345-kilovolt transmission lines. A 765-kilovolt overlay network is scheduled for initial operation in 1971. American Electric Power has 53 interconnections with 21 separate utility systems. Two of these are at 500 kilovolts, ten at 345 kilovolts and 41 at 138 kilovolts. These interconnections are capable of transferring 4,500,OOO kilowatts into or out of the ‘system, more than half of its present peak load. Relatively few utilities in the United States have interconnections or internal networks capable of exporting or importing as much as 15 to 20 percent of peak load requirements. The Hydro-Electric Power Commission of Ontario has ties with United States utilities at Detroit, Michigan, and at Buffalo and Massena, New York. The present generating capability of the Ontario system is about 8,860 megawatts. Its capability in 1973 is projected to be 15,400 megawatts, of which 58 percent will be in thermo-electric generating stations and 42 percent. in hydroelectric plants. At that time, the largest thermal generating plant will be the Lakeview steam-electric station near Toronto, with a capacity of 2,400 megawatts. Other large plants will include the 2,000-megawatt Lambton plant in western Ontario and the 2,000-megawatt Pickering Nuclear Plant near Toronto. In general, the new capacity will be located near Ontario Hydro’s major load centers and should aid in balancing area load and generation. Following interconnection of the Michigan systems with those to the south in Indiana and Ohio in 1970, Ontario Hydro’s transmission network from Windsor (near Detroit) to Niagara will be part of a new transmission loop around Lake Erie. The increase in generation on Ontario’s system at the western end will reduce the magnitude of power flows normally transmitted from east to west on the 230-kilovolt network north of the lake. This will leave more reserve capacity in these lines for handling major disturbances, should they occur at the major generating centers in Canada or the United States at either end of Lake Erie. Ontario’s program includes some additional 230-kilovolt construction s in this section of its system. Ontario and United States utilities in Michigan, Indiana and Ohio are reviewing stability studies to determine whether interconnections now planned have adequate strength to meet the stability tests suggested in the report of the Reliability Committee. Design loading of some of these lines should reflect the likelihood of seasonal power flows between the United States and Canada. Basically, closure of the loop around Lake Erie will substantially improve the stability of the network in this area and increase the reliability of service to the interconnected load centers in Canada and the United States. Interconnections among utilities in the far midwest from the Dakotas and Minnesota in the north, to Texas in the south, present the problem of economically tying together smaller load centers spaced farther apart. Here, north-south transmission lines are generally shown to be 345 kilovolts. Heavier lines will be needed eventually in the east-west direction to transfer surplus and emergency power, and to provide some insurance for unforeseen emergencies. The east-west ties are not considered to be a first priority need but, as stated earlier, are suggested to encourage the systems involved to study the appropriate configuration for reliable ties between the western and central sections of the continent. An important early step is to complete the strengthening of the transmission network in the large western region and the network in the west central region, particularly in the western section of the region. The eastern and western sections of the United States were successfully joined together for the first time in February 1967, with the closure of three 230-kilovolt and one 161-kilovolt ties. These lines are very light for this duty. They cannot dependably move more than a few hundred megawatts in either direction and therefore, cannot significantly improve the reliability of the networks of the nation. These ties will separate, as they did on two occasions in the first two months of closure, when disturbances occur. These separations have not caused cascading or loss of customer service. However, the situation needs improvement to relieve 59 c - - - - w - - - L_/ 1’ \\ /’ ’ -d&---\\ \ \ ---I\ \ \ ‘ \ ./ General Note: None of the lines indicated on this exhibit is to be considered as a specific recommendation of the Commission. Further, no recommendation is intended as to number of lines, levelof voltage, or type of power (ac or dc) for the principal east-west ties between areas marked with .>. 1 ” . an asterisk. FIGURE 21 60 i--------. ! --i----I 1 i 1-‘ i, 1 i \ \ I t- - - - - - /” \ \ /’ \’ --/ -\- - - \ \ \ - - 3r- i POSSIBLE PATTERN ‘~ \ ____ \ \ \ __--- 345 KV ___-- 500 KV 700+ KV 11-111 POSSIBLE PATTERN OF TRANSMISSION FOR INCREASED RELIABILITY BY 1975 61 the utilities in the region from operating under uncertain circumstances. The construction of strong east-west transmission lines should be of interest to many utilities in the United States. The merits of their construction should be carefully studied by regional coordinating organizations. The planning and construction of the four major north-south EHV lines connecting systems in the Pacific Northwest with those in the Pacific Southwest are progressing, generally on schedule. Part of the first 500-kilovolt line to California from John Day Substation on the Columbia River, has been operating at 230 kilovolts since April 1966. The operating voltage is expected to be raised to 500 kilovolts by December 1967. The parallel 500-kilovolt line is scheduled for service in May 1968. The first dc line from the Northwest to .Los Angeles is scheduled for service in April 1969. A dc line from the Northwest to the Hoover Dam is planned for operation in 1972. The successful operation of these lines will require a substantial strengthening of the north-south lines which interconnect in the mountain states to the east. These lines form the eastern section of a large transmission loop, of which the new northsouth interties form the western part. Strengthening the eastern portion is essential to prevent frequent separations among utilities in Wyoming, Idaho, Utah, Colorado and New Mexico. This is of concern to all of the utilities in the western part of the United States.. Plans to establish a regional coordinating organization for the solution of such problems were announced earlier this year. Developing a network of the general configuration illustrated in figure 21 by 1975 should enable utilities to plan with assurance and confidence for the exchange of power on a regional and interregional scale. Until transmission systems in the United States are planned and built well in advance of fully demonstrated requirements, the nation will continue to be faced with the possibility of further power failures, forced load curtailments, and the foregoing of economic power exchanges. Cost of EHV Transmission Because of differences in design, conductor materials and sizes, and related elements of transmission line construction, it is difficult to present a simple comparison of line costs and capabilities. Nevertheless, the following table shows a general 62 comparison for several EHV levels now in use an planned for early construction in the United States. .i Line Voltage-Kv 230 345 500 750 Range of Ave39000COBt Per’Mile 45-60 60-80 S-100 125-160 Approximate Line Capa- I 10 100 Miles 275 700 1,750 4,4Jm 135 350 850 2,150 The cost of lines depicted in figure 21, excluding I those in service at the end of 1966, and including an allowance for new internal lines, substations, communications, new control centers and other facilities which would accompany these network additions, is estimated to be about $8 billion. This I pattern of transmission, or one of similar strength, will be needed whether added by 1975 for increased reliability, or deferred a few years until it becomes a necessity under less severe reliability criteria. The I true cost of upgrading reliability to prevent major failures is the cost of advancing normal transmis- E sion line construction and appurtenant facilities over an immediate future period of about eight years (1968 to 1975). A diagram comparing this accelerated construction with projected normal EHV construction, based on recent trends, is shown in figure 22. The accumulated incremental expenditures by 1975 for accelerated EHV construction at today’s costs is roughly $3 billion. This includes the added EHV lines and associated facilities and, in addition, an allowance of a half-billion dollars for incremental strengthening of lower voltage facilities to permit full realization of the capabilities of the advanced EHV system. It is difficult to depict a long-range projection of transmission programs which can be correctly classified as an industry projection. The only one currently available was published in Electrical World I in 1966, said to have been a nearly complete canvass of the industry. In fairness to industry’s view of its future transmission requirements, it may very well be that more transmission lines will be added as final studies are made of the needs at any point in time. Whether the difference between the indusi try projection and the needs suggested in this chapter is more or less than the $3 billion indicated 1 *Ba is of no grea it does not either to the nual cost of $350 milliol cost of elect States in 19: Economic The bene are not reac the health pairment 0: nity and h particularly considerati Under a fits of fully tan centers other area substantial curred in I nual cost may be se1 PROJECTED INVESTMENT IN EHV TRANSMISSION 1 now in use and re United States. imate Line Capalility-Mw 1966 - 1975 10- 300 Miles - ----__ 135 350 850 2, 150 .re 21, excluding i, and including nes, substations, rters and other r these network $8 billion. This similar strength, 175 for increased until it becomes lity criteria. The 1 prevent major ormal transmistenant facilities of about eight comparing this ejected normal trends, is shown :xpenditures by ction at today’s ludes the added s and, in addiI dollars for involtage facilities iabilities of the ge projection of correctly classi: only one curElectrical World r complete canindustry’s view nts, it may very s will be added ds at any point ween the indusgested in this rillion indicated 1966 1967 1968 1969 1970 1971 1972 1973 1974 1975 *Based on a survey by Electrical World, published 10-3-66 FIGURE 22 is of no great significance. Whatever the difference, it does not appear that it would be burdensome either to the utilities or to the rate payers. The annual cost of a $3 billion incremental investment is $350 million, less than 2 percent of the estimated cost of electric power to be produced in the United States in 1975. Economic and Social Justification The benefits of providing this degree of reliability are not readily quantifiable. The potential injury to the health and welfare of persons, the possible impairment of the national defense, and the community and human concern of multitudes of people, particularly in densely populated areas, are vital considerations. Under any standard of measurement, the benefits of fully adequate reliability in major metropolitan centers will far exceed the incremental costs. In other areas of the nation where density of load is substantially less and major expense may be incurred in minimizing power failures, the added annual cost of such facilities per unit of power sold may be several times more than the average for the country. In such areas, the choice may lie between acceptance of somewhat higher cost to acquire improved reliability, or acceptance, for an interim period, of more frequent load shedding to prevent total failures in power service. As previously indicated, strengthening the network in the general manner depicted in figure 21 would also open the way for many beneficial exchanges of power and energy among the systems of the area or region, or between regions. It would permit the establishment of regional capacity and energy exchange programs, so that an unexpected deficiency in any part of the region can be supplied by the transfer of power from systems located elsewhere in the region, or even beyond the region. Had a network approaching this strength been in existence in the summer of 1966, the utilities in the central part of the nation which were engaged in the struggle to maintain electric service during the prolonged heat wave could have been supported by systems to the north and east which had extra capacity. Similarly, adequate transmission networks can support utilities or groups of utilities which may have experienced a serious reduction in reserve generating capacity because of delays in placing new 63 generating units on the line or because of an abnormally large number of equipment failures. Such situations are becoming more prevalent as manufacturing and construction delays, and problems in obtaining generating plant sites and transmission rights-of-way, have seriously delayed the scheduled on-line dates of new facilities. The loads in the area including Kansas, Oklahoma, New Mexico, Texas, Arkansas, Louisiana and parts of Mississippi and Missouri, are an example of the extreme difference between summer and winter peaks which make interarea and interregional exchanges imperative for economy as well as reliability. In 1966, the summer peak of the region was 28,139 megawatts, 16.6 percent higher than in 1965. The winter peak for 1966 was only 18,720 megawatts, although up more than 10 percent from the previous year. From these figures, it is evident that the summer peak was about 50 percent greater than the winter peak which followed. A portion of this seasonal capacity is being exchanged between the South Central Electric Companies and TVA, but a very major part remains surplus. If adequate transmission is provided, this capacity could be utilized to assist in emergency situations, maintenance requirements, further seasonal exchanges, and as an economic supply of energy for future growth in cold weather loads. Expansion of the network for reliability in accordance with the general pattern depicted in figure 21 approaches the network strengthening visualized in the National Power Survey by 1980. It can be expected that the net result of stepping up additions to transmission systems for reliability would be an earlier achievement of some of the economic gains projected in the Survey. Alternative Considerations for Achieving Reliability It may be helpful in understanding the value of interconnections, to hypothesize on other ways that utility coordination might have developed. Assume, for example, that electric systems in the United States had evolved up to this time in the form of 15-20 operating groups isolated from each other. Such groups would have individual loads in 1975, say, of 10-30 million kilowatts each. As a second alternative these groups could be assumed to be interconnected with transmission lines of limited capacity, sufficient to take advantage of some seasonal 64 diversity, but not strong enough to remain in service ’ the sudden in threaten over-k under severe network disturbances. With the first alternative, an isolated area with of the loop. Th an assumed load of 15 million kilowatts, could not I transmission r which may be reasonably use units larger than about 700 megai populated, ma watts. The size of generating plants and the loads the area. Sucl supplied through one primary substation or carried underscore the on any one corridor of transmission should not exteed about 1000 megawatts. Even so, the sudden I mechanisms tl loss of 1000 megawatts of generation would result , planning is no in an immediate drop in system frequency to about 59.5 cycles per second. I Under the second alternative with limited capac2 ity interconnections to other systems, the situation could be less satisfactory. Assume, for example, that the area had been receiving an inflow of 500 megawatts from neighboring networks at the time of the loss of 1000 megawatts internally. It is likely that . the external ties would become overloaded and trip Iout. The frequency of the separated area would be I 111( expected to drop to about 59 cycles per second. Although a decline in frequency may reduce loads I , slightly, a serious disturbance in a network can cause i substantial rerouting of flows accompanied by in1 creases in system losses and reactive requirements ; offsetting the load decreases resulting from lower 1 frequency. a Under the alternative conditions described, load shedding would need to be incorporated into the planning of systems as an essential working tool to prevent collapse of power in the area. It would not be reserved solely as insurance against failure as I herein for application to strongly inter- -connected systems. Aside from lesser reliability, these alternative schemes would be economically handicapped. Larger generating reserves would be needed to meet F major equipment failures, unforeseen loads, the ef- 1 : fects of sharp weather extremes, and the ravages of severe storms. Diversity power exchanges with other , areas would be barred or restricted. In addition, the limitations imposed on the size of generation t and transmission equipment would involve increased investment and operating costs. I I Regional and Interregional Planning- and ’ Cost Sharing Some of the interconnections depicted in figure 21 are of interest and value to utilities outside of 1 the service area in which they are constructed. Some add strength to large “loop” networks in which I I F IGURE 23.-A nough to remain in servic iturbances. ive, an isolated area wit1 b lion kilowatts, could no er than about 700 mega tting plants and the load mary substation or Carrie1 k;rnisiz; ;zE ;.;te; If generation ‘would resul system frequency to abou the sudden interruption of part of the loop can threaten overload and instability in the remainder of the loop. Thus, the cost of required high capacity transmission necessary for reliability iii an area, which may be geographically extensive but thinly populated, may merit the support of utilities outside the area. Such technical and economic problems underscore the need for strong regional planning mechanisms to assure that adequate coordinated planning is not seriously delayed. Regulatory agencies as well as utilities may need to re-examine usual practices of cost-sharing and cost allocation as interconnecting facilities. are constructed which assure reliability for utilities over a wide area. Forecasts of needs and values many years ahead may be required. Exchanges of information and analyses may be required among regulatory bodies on values assignable to increased reliability for portions of an interconnected network. native with limited capac her systems, the situation Assume, for example, tha lg an inflow of 500 mega networks at the time o 1 internally. It is likely thal come overloaded and tril separated area would be : 59 cycles per second. Al, luency may reduce load5 Ice in a network can cause ‘lows accompanied by in reactive requirements resulting from lower nnditions described, load be incorporated into the ‘essential working tool to in the area. It would not )rance against failure as ication to strongly interability, these alternative nor&ally handicapped. would be needed to meet nforeseen loads, the efIitmes, and the ravages of wer exchanges with other * restricted. In addition, n the size of generation tent would involve in:rating costs. lional Planning and ctions depicted in figure ue to utilities outside of h they are constructed. “loop” networks in which FIGURE 23.-A typical transmission tower on the Bonneville Power Administration’s segment of one of the 500 kv a~ interties between the Pacific Northwest and the Southwest. 65 CHAPTER 7 OTHER RELIABILITY CONSIDERATIONS Defense Implications of Power Failures The Northeast power failure understandably has created concern that power systems might be more vulnerable to enemy attack than previously had been thought. The following paragraphs present pertinent information about the Northeast failure as a basis for appraising the probable impact of a nuclear attack or acts of sabotage on the nation’s interconnected electric power system. Defense Impacts of the Power Interruption The duration of the Northeast power interruption varied from a few minutes in some sections to as long as 13 hours in parts of New York City. The impact on the productive capability of the areas affected, however, was not as severe as might be assumed. Since the interruption started at the close of the normal workday, interference with production was largely confined to those industries working on multiple shifts. Weather was not severe and there was little damage to production materials or equipment as a result of climatological conditions. If the outage had occurred during normal work-day hours, in a period of severe winter, weather, the losses in materials, equipment, and production would undoubtedly have ,been much greater. Power Systems and Sabotage The Northeast power failure focused increased attention on the vulnerability of power systems to disturbance and damage from acts of sabotage. For many years the utilities have recognized their vulnerability to pranksters, vandals, carelessness on the part of operators, and to unique incidents of seemingly insignificant origin, such as a bird’s nest falling on an exposed circuit or the entry of a tree frog into a relay. Normally these incidents cause little or no permanent damage and, if service interruption is involved, power can usually be restored quickly. Automatic protective equipment is usually successful in confining such interruptions to a limited area. Despite past successes, however, it cannot safely be assumed that electric utilities are adequately prepared to meet the challenge of any concerted efforts at planned interference. Triggering incidents affecting major supply lines, substations, or switchyards of large generating plants, could cause protective equipment to function, or perhaps malfunction, and result in serious system separations creating imbalances between supplies and loads in isolated areas. In order to insure against system collapse, existing networks must be strengthened and a well-planned program of load reduction must be established. Implemention of this dual program will significantly strengthen the electric power industry’s ability to offset any effects of sabotage. Strong and flexible transmission networks are clearly essential to the nation’s security in a society so dependent on the availability of adequate electric energy. As a check against sabotage-as well as vandalism-many utilities have established security programs. At present, few of these programs are vigorously administered. Most utilities screen and check new employees during a probationary period prior to granting them permanent status. Historically, utilities have taken special protective measures during wartime periods. During World War II utilities made more stringent security checks, and in addition to the normal precautions of fencing and floodlighting, they closely guarded critical power system facilities and maintained vigilant plant entrance restrictions. As power systems become larger and more complex, maintaining adequate security is increasingly difficult. Special precautionary measures should be well planned in advance, to be instituted in the event the nation’s security is again directly threatened. The Provost Marshal General of the United States Army conducts an annual survey of several hundred facilities in the United States which supply electric energy to important defense production areas. The survey includes reviews of measures for 67 control of entry to critical areas, prevention of sabotage, fire protection, civil defense, minimizing the effects of damage, restoration preparedness, and continuous staffing by qualified personnel. The capabilities of the utilities are rated as “adequate” or “inadequate” under both normal and emergency conditions, the latter including both enemy attack and civil catastrophe. In the survey for fiscal year 1965, 92 percent of the utilities were rated as being adequately prepared for normal conditions and 77 percent were considered adequately prepared for emergency situations. With respect to measures for controlled entry into critical areas, including prevention of sabotage, 85 percent were found adequate under normal conditions and 56 percent under emergencies. The survey results underscore the need for improving preparatory measures to strengthen electric utility security controls in order to meet any untoward contingencies which may arise. In addition, it would appear advisable to broaden the scope of security guidance and coverage to include all electric utilities by making available to them the established security criteria developed by the Provost Marshal General. Vulnerability of Power Systems to Nuclear Attack Utilizing patterns of nuclear attack furnished by defense planning agencies, studies have been made of the effect a nuclear attack might have on power systems. These patterns generally have assumed a large number of surface explosions of major nuclear weapons at principal population and industrial centers. Based on guidelines of the destructive effects of these weapons at various distances from the explosion centers, these studies have provided estimates of the effect of postulated attacks on electric utility operations and electric utility loads in the affected areas. The studies, which include a nationwide study by the Defense Electric Power Administration and a regional study made by the Triangle Research Institute for the FPC in connection with the National Power Survey, led to the general conclusion that the electric power industry’s usable capacity following attack will exceed the needs of the surviving loads. This conclusion is based in part on the overall ability of electric power systems to overcome the loss of individual electric facilities, and in part on the long periods following any widespread attack during which industrial and commercial activity would be reduced. 68 Attributes of Power Systems in Surviving Severe Damage Severe damage to main generating equipment would be serious and could require several months to a year or more for repair. Damage to transmission and distribution facilities usually is not as serious, although principal substations, if severely damaged, could require time consuming repairs. Generally, however, substation equipment can be repaired or by-passed much more readily than can complex generating facilities. The strength of electric power systems and their ability to cope adequately with acts of sabotage or widespread attack which temporarily cause system outages, rests with the ability of each utility in an interconnected system to restore any essential lines to service and meet any generating deficiencies by obtaining power from alternative sources. The random destruction from nuclear attack could cripple an electric system in a manner that would, in some respects at least, be similar to that which results from severe storms. The American Electric Power System, for example, was hard hit in April 1965, by a tornado that caused loss of service on seven 345 kilovolts lines and twenty-one 138 kilovolt circuits. The damage, however, did not bring about a cascading failure within the AEP or neighboring systems. Automatic protective devices disconnected the damaged circuits and left alternative ones in service. Largely because of the strength of the AEP network and its many interconnections with other systems, service was maintained in the undamaged areas. For strongly interconnected systems with adequate arrangements for emergency load shedding, a nuclear attack will not necessarily touch off cascading power failures. To avoid cascading outages, however, systems must be prepared to survive ran dom network separations. Some consideration has been given to the advisability of planning the temporary separation ol systems in a predetermined optimum pattern im. mediately following a warning of impending nuclear attack. The objective of such separations would bf to prevent the possibility of cascading power fail ures triggered by loss of large blocks of capacity a a result of major damage to transmission lines, sub, stations or generating plants. The theory that pre, separation of the network might be beneficial under broad scale attack is founded on the probabilit! that damage would be directly inflicted on only i limited number of the separated network sections Lnd although p’ damaged sectiol tions would be u Defense expel ably anticipate II prior to an att; would need to periodic practic terns quickly an carry out. Many which is general transmitted OVE many cases, sep require a major ning reserves, a For separated power from sol dary, it is like1 would be no mc attack separatio with random UI must be overcc resulting from e Fallout She1 In the event ( people will be cc some of the she plies, no gener power service h lit shelters sure Department of iary power wet type of shelter, and opportuni manually powe range of risks i tend a massive plies to shelter in occurence tl visions for mir overall conseqi discomfort ratl @ The warnins the country not i much longer. Tl arrival of the rad winds, would ra most areas of the Systems in Surviving ‘Damage ain generating equipment uld require several months Lir. Damage to transmissiori I usually is not as serious, tions, if severely damaged, ‘uming repairs. Generally, ment can be repaired or L dily than can complex strength of electric power ’ to cope adequately with zread attack which tempoES, rests with the ability of jnnected system to restore vice and meet any generining power from alternaion from nuclear attack system in a manner that at least, be similar to that re storms. The American ‘or example, was hard hit nado that caused loss of volts lines and twenty-one damage, however, did not failure within the AEP or :omatic protective devices d circuits and left alterna:ly because of the strength its many interconnections ce was maintained in the hcted systems with adeFmergency load shedding, Inecessarily touch off casL avoid cascading outages, 1 prepared to survive rants been given to the ad! temporary separation of d optimum pattern imt-‘ng of impending nuclear mch separations would be of cascading power failarge blocks of capacity as to transmission lines, submts. The theory that premight be beneficial under 1 nded on the probability brectly inflicted on only a arated network sections, P and although power might be lost in the directly damaged sections, generation in undamaged sections would be unaffected. Defense experts advise that we cannot reasonably anticipate more than 10 or 15 minutes warning prior to an attack.35 System separation therefore would need to be preprogrammed and subject to periodic practice. The wholesale separation of systems quickly and effectively is difficult to plan and carry out. Many load areas are supplied with power which is generated several hundred miles away and transmitted over an interconnected network. In many cases, separation into “local systems” would require a major pickup in generation by local spinning reserves, and preprogrammed load shedding. For separated sections which normally received power from sources outside the separation boundary, it is likely that the consequences of attack would be no more severe than those caused by preattack separation. In short, the problems associated with random unplanned system separation can and must be overcome if we are to minimize outages resulting from enemy attack. Fallout Shelters and Power Requirements In the event of a nuclear attack, large numbers of people will be concentrated in fallout shelters. While some of the sheIters may have auxiliary power supplies, no general program for providing auxiliary power service has been instituted for the many public shelters surveyed by the Office of Civil Defense, Department of the Army. Requjrements for auxiliary power would vary widely, depending upon the type of shelter, available space, potential occupancy, and opportunity for natural ventilation or use of manually powered devices. However, in the whole range of risks and damaging events that would attend a massive attack, the loss in electric power supplies to shelter areas would likely be more random in occurence than wholesale. With reasonable provisions for minimum standby power facilities, the overall consequences would be inconvenience and discomfort rather than disaster. “The warning time to detonations, if any, for areas of the country not included in the initial attack, obviously, is much longer. The time between the detonations and the arrival of the radioactive fallout, due to its spread by upper winds, would range from 30 minutes to many hours in most areas of the country. Summary Electric power systems are subject to damage from sabotage and from direct enemy attack. The severity of the impact could be as great as that on November 9, but the consequences need not be a massive cascading if power systems are strongly interconnected, and are provided with controls which will assure immediate balancing of load and generation should the network separate. The availability of strong transmission facilities with a large reserve capacity above normal maximum loading will be highly beneficial in preventing major power failures and in re-routing power from undamaged generating plants to undamaged and surviving loads. Such availability would also facilitate the reconstruction or repair of damaged facilities. Emergency Power for Essential Public Services The Northeast incident demonstrated the necessity for emergency sources of electric power to maintain vital services during major failures of normal power supply. It also pointed up that planning, maintaining and operating emergency facilities are di.%cuIt problems for most individual users. A large number of emergency sources did not function or functioned inadequately because of poor maintenance, lack of fuel, or absence of qualified operators. Outstanding among facilities which had inadequate auxiliary provisions was the Kennedy International Airport. This installation had been considered invulnerable to power interruption because it is supplied by seven principal distribution feeder lines. All of them, however, received power from a single utility system, so the entire central service supply failed during the November 9 emergency. A large number of these observed deficiencies are being rectified. A summary of the responsibilities and activities of various organizations which have a ihare in planning and maintaining emergency facilities or in establishing regulations governing their provision is presented in appendix D. Federal, state, county and municipal governments are all concerned. Proposals have been placed before the Congress which would offer support for the installation of emergency power facilities in some critical areas. The dependence upon electric power is critical in health services. However, since emergency routines are characteristically a part of hospital services, the 69 power failure was only a temporary inconvenience to patients and staff at those facilities where emergency generators were available and operative. In New York City only about half the hospitals had adequate auxiliary power, and the ratio was even worse in some other areas. In many instances, local government agencies and public utilities made available mobile generating units to provide emergency service. Fortunately no deaths were attributed to the power failure, but the results might have been different if the emergency had involved a large influx of injured persons. At best, the necessity of providing auxiliary power in all hospitals and developing improved procedures for emergency switching and maintenance were too readily apparent. As a result of this experience, much new equipment has been installed, and emergency facility codes for hospitals and nursing homes have been reviewed and strengthened. Urban transportation dependent upon utility systems for its power supply was seriously affected by the power outage. In New York City, the power failure resulted in a complete cessation of subway operations. As a consequence, auxiliary gas turbine generators have been installed by the Consolidated Edison Company for essential lighting and controls, and to bring subway trains to the nearest station platform, one at a time, for the discharge of passengers. The cost of an independent generation and transmission system to provide total emergency subway service is considered to be prohibitive. The power outage impact on street vehicular traffic in large metropolitan areas was evidenced by congestion and traffic snarls that resulted from the failure of traffic light systems. In a national emergency involving a need for mass movement of people out of target or contaminated areas, such traffic tie-ups might constitute life-or-death hazards to the persons involved. Recircuitry of a major traffic light system to permit the use of standby power service, however, is very expensive. As an emergency expedient, New York City’s Department of Traffic has expanded and reoriented its mobile unit communication system so that it can now maintain a reasonable control of sensitive emergency traffic situations. For the general public in the affected areas, communications interruptions were not intolerable. Many radio broadcast stations had auxiliary power sources and were able to maintain service. Batterypowered radios were able to receive broadcasts, and some television service was maintained for battery70 powered receivers and for standard sets where emergency power was available. This communication service was undoubtedly a major factor in avoiding public excitement. All major metropolitan broadcasters have now installed emergency power equipment to insure continuity of service during emergencies. Telephone services were maintained throughout the affected area although dial tone and throughconnection delays were experienced in the heavy trafhc following the power interruption. Prior planning for emergency operations resulted in continued local, intercity, long distance and even overseas 1 service, and did much to help prevent panic. Commercial telephone systems are equipped with standby battery and auxiliary power generators which automatically take over if commercial power falters or fails. In addition, a reserve supply of portable generators is kept on ,hand as further backup, ready for dispatch to key locations. During the night of the power failure, 15 Bell System emergency centers were activated, and loans of generators were made to such essential users as hospitals, convalescent homes, railroad and airline terminals, and fire and police departments. The telephone companies in the Northeast helped to coordinate emergency activity in the public interest by maintaining liaison with government agencies, power companies and the general public. All Federal systems under GSA control have, since November 1965, been provided with auxiliary power support to maintain continuous telephone service. Telegraphic services failed during the blackout because of lack of power sources in central offices and at terminal receivers. These weaknesses have been remedied in the major telegraphic switching areas and power packs are available for terminal customers as a tariff item. Generally, auxiliary power was available for such essential public services as fire and police protection, although some central-station operations had to be curtailed. A problem developed in many public buildings where power was not available for services such as elevators and water and sewage pumping. Some municipal water supply and sewage disposal functions were weakened, or in some cases failed entirely, but no serious problems developed as a result of the difficulties encountered. The potential for serious sanitation and health problems was readily apparent, however. Since the power failure, the building developers have accelerated the practice of equipping high-rise building with auxiliary power for ings and p entities ha power in t failures. I departmel ditional p: of auxilia York City Centers a The Cor proposed lature th. Water Su public ut A num tities, nc emergent installatic Electric planning ties of inc the urger type of si of the cu can be of arrangen ply with 1 and rem and open could va contract1 nance. Equipm The r-c lated to 1 Equipme sonable specified utilizing and pro\ nance. Some : ment, pi new 50C little mo formers i breakers tion of tl capacito: !ard sets where emerrhis communication or factor in avoiding metropolitan broadrgency power equipervice during emerintained throughout 1 tone and throughenced in the heavy rruption. Prior planesulted in continued and even overseas Irevent panic. Comquipped with stand:r generators which Commercial power r reserve supply of and as further backtcations. During the Bell System emernd loans of genera11 users as hospitals, td airline terminals, nts. The telephone :lped to coordinate c interest by mainnt agencies, power lit. All Federal sys:, since November iary power support : service. uring the blackout es in central offices K weaknesses have legraphic switching ilable for terminal available for such d police protection, jerations had to be d in many public vailable for services I sewage pumping. hd sewage disposal some cases failed ns developed as a :red. The potential rlth problems was the power failure, :elerated the praclmg with auxiliary s Power for safety lighting, moving elevators to landings and pumping water and sewage. Local political entities have become aware of the need for auxiliary power in the event of widespread commercial power failures. Fire, police, sanitation, and public works departments have assured service continuity by additional procurement and by improved maintenance of auxiliary power generating equipment. In New York City all five Borough Emergency Operating Centers are equipped with auxiliary power units. The Corporation Counsel’s Office has submitted proposed legislation to the New York State Legislature that would give the City’s Department of Water Supply,,Gas & Electricity direct control over public utility services in the City of New York. A number of states, and other government entities, now ,have legislation requiring auxiliary emergency power in specified buildings and installations. Electric utilities generally do not participate in planning and maintaining emergency power facilities of individual users. While the determination of the urgency of the need and the magnitude and type of supply required is largely the responsibility of the customer, it appears that the serving utilities can be of important assistance in suggesting suitable arrangements for coordinating the emergency supply with the utility supply and suggesting procedures and reminders for periodic maintenance, testing and operation of the facilities. The responsibility could vary from one of general advice to formal contractual service for installation and maintenance. Equipment Reliability The reliability of a power system is closely related to the satisfactory operation of its equipment. Equipment reliability is obtained by specifying reasonable performance margins, testing to verify specified performance, providing proper operation, utilizing appropriate control and protective systems, and providing adequate regular and special maintenance. Some failures have occurred in major new equipment, particularly in items designed to operate on new 500-kilovolt transmission systems. Within a little more than two years, six 500-kilovolt transformers and a larger number of 500-kilovolt circuit breakers have failed, causing delays in initial operation of these systems. Other devices such as coupling capacitors and lightning arrestors also have failed, !2%7-781 O - 6 7 - 6 but with less disturbance to schedules. Improved performance, however, can be expected. It appears now that design changes and other modifications resulting from failure experiences have rectified the difficulties. The impact of some of these failures in new equipment can be serious. Usually there are no spares for such new equipment and repairs may involve lengthy delays for return of the equipment to the factory. The number of failures suggests that present concepts and procedures for proof testing are not always sufficiently profound to demonstrate fully the reliability of the equipment under actual system operating conditions and demands. An increasingly significant problem in testing EHV equipment, particularly for short circuit capacity, is the extremely high current requirements. For some tests, only the large utilities have the necessary current-carrying capacity, and there may be undue risks in using these systems for short circuit test purposes. It appears that the industry would do well to increase its testing facilities to avoid unnecessary delays in the utilization of new devices. While there are some 20 laboratories for testing high-voltage equipment in Europe and Japan,36 two manufacturing companies have the only laboratory facilities in the United States which can be considered reasonably adequate for testing large circuit breakers and other system components for maximum duty. Many other American manufacturers use foreign laboratories. Generally, United States utilities have not had laboratories for major testing, and many of them have been cautiously unwilling to use their system facilities for extensive testing operations. Preliminary plans have been developed for a test facility near Grand Coulee Dam in the heart of the major hydroelectric network of the Pacific Northwest. The benefits from such a facility warrant careful consideration by the Federal government, the utilities, and the manufacturers of major equipment. It would reduce testing time which is an important item in the total schedule of new major facilities and would permit subjecting the equipment to some as Of the foreign laboratories, 11 are operated by electric equipment manufacturers and thus are not generally available for use by American manufacturers. The four foreign laboratories principally used by American manufacturers are N. V. Tot Kearing van Electrotechnische Materialim (KEMA) at Arnhem, Holland; Centro Electrotechnico Spe.rimental Italian0 (CESI) at Milan, Italy; Centre de Recherches et d’Essais de Fontenay (Fontenay) at Paris; and Allmanna Sveska Elektriska Aktieholaget (ASEA) in Sweden. 71 system operating conditions not fully reproduced in U.S. laboratories. Reliability also can be enhanced by wide dissemination among utility groups of information about equipment failures and troubles which would provide a forewarning of possible needs for preventive action. Information of this type is issued to users of similar equipment by many of the equipment manufacturers, but much of the reporting may tend to be limited more to major items of equipment than is desirable. Research and Development Needs Because the advances in electric technology usually attract little public attention, the public generally does not realize the amount of effort which the industry devotes to research and development. Traditionally, most of this has been performed by the equipment suppliers, with the cooperation and often at the suggestion or urging of the utilities. More recently the utilities have directly supported R & D activities, not only on an individual basis, but also jointly, particularly through the Electric Research Council and the Edison Electric Institute. However, with the mpid expansion of the industry, even more extensive research and development effort will be required to advance technology, especially in areas where extrapolation of present designs and practices is likely to be inadequate to meet future needs. Following are a few of the many areas which need further exploration. Significant work is already being done or is planned in most of them. Further substantial advances in high voltage technology will be needed .to accompany the continued progression to higher load densities. Plans are underway to investigate transmission voltages as high as 1,500 kilovolts. There is evidence at such voltages, that phenomena not yet well understood may present new problems, and that significant changes in insulation materials and systems may be needed before equipment at the higher EHV levels will be available for satisfactory operation. Another area of possible improvement is in switchgear where high capacity solid state devices offer some promise of decreased interrupting time, less complicated arc extinction, higher reliability, and lower maintenance requirements. If highly sophisticated applications of computer controls to systems of automation for electric network supervision and operation are to be achieved, many improvements must be made. These involve improved sensing devices, better communication 72 links, means of high-speed analysis and automated decision techniques. Nuclear power generation has made rapid advances recently but still further advancement in the field of breeder type reactors is eagerly awaited and predicted to be the answer to a continuing search for lower cost sources of electric power. Present estimates indicate suitable breeder types are likely to be commercially available sometime between 1980 and 1985. Extensive research and development is being expended in their development. There is a need for extra high voltage underground cables and methods of significantly decreasing the costs of underground installation. The Electric Research Council has recognized these needs and has proposed research and development programs which it is hoped will produce useable solutions to at least the technical problems. Appreciable decreases in costs seem to be necessary before the use of underground circuits can be expected to expand appreciably. Improvement in reliability of performance is a worthy goal in all aspects of power system equipment and operation. Every increment in improved reliability makes possible a reduction in reserve capacity of installed facilities. Reductions of this type can significantly aid in justifying expenditures for work which promises improvements in any of these areas. Capacity Requirements in Relation to Manufacturing Capability An important element in scheduling the planning and construction of new bulk power supply facilities is the time required for manufacturers to produce and test heavy equipment ‘such as large boilers, steam turbines, generators, nuclear reactors, transformers and related accessories. The rapid increase in the use of larger size units in the last six to eight years has permitted the manufacturers to keep pace with the increasing capacity requirements without having to expand production space greatly. The larger units weigh less per kilowatt of output and take up less manufacturing space. This situation has changed in the last few years with the sharp increase in the ordering of nuclear generating plants. Turbines and generators powered by low pressure steam from nuclear plants are much larger per unit of output and occupy more space in the factory than a conventional unit. This means that as present types of nuclear capacity become a larg total kilowatt : ing plants will 1 In 1965, elc ordered 24.4 generators, of 1 nuclear-powen to 18.5 million million kilowz United States orders in corn1 turbine general illustrated in f sharp increase difference betv of manufactur large power t The latter indi of orders. Trar influenced by t These large I two years, on what in adva This is partly M4 STEAM TI 10 100 1 1962 m The overall to 4 conventiona bd analysis and automated neration has made rapid adstill further advancement in ype reactors is eagerly awaited I the answer to a continuing 6t sources of electric power. tcate suitable breeder types are cially available sometime be5. Extensive research and detpended in their development. br extra high voltage under:thods of significantly decreasground installation. The Elecil has recognized these needs search and development pro)ed will produce useable solu$&al problems. Appreciable in to be necessary before the ~circuits can be expected to iability of performance is a ects of power system equipiivery increment in improved le a reduction in reserve caP Ilities. Reductions of this type in justifying expenditures for improvements in any of these become a larger part of total new capacity, the total kilowatt production capacity of manufacturingplants will be reduced.37 In 1965, electric. systems in the United States ordered 24.4 million kilowatts of steam turbine generators, of which 4.9 million or 20 percent were nuclear-powered. In 1966, nuclear orders jumped to 18.5 million kilowatts, 41.5 percent of the 44.5 million kilowatts of large capacity ordered by United States utilities. Tlne large accumulation of orders in comparison with orders shipped of steam turbine generator capacity in the years 1962-1966 is illustrated in figure 24, which clearly depicts the sharp increase in orders in 1966 and the wide difference between new orders and the present rate of manufacturing production. The situation for large power transformers is shown in figure 25. The latter indicates only a moderate accumulation of orders. Transformer production is, of course, not influenced by the type of generating plant. These large orders for nuclear capacity in the last two years, on the whole, have been placed somewhat in advance of normal ordering schedules. This is partly because more time is required from MANUFACTURE OF STEAM TURBINE GENERATORS 10,000 Kw and larger IOO- bments in Relation to pability I lent in scheduling the plann of new bulk power supply kquired for manufacturers to ivy equipment such as large , generators, nuclear reactors, L ted accessories. The rapid [ larger size units in the last ipermitted the manufacturers ’ increasing capacity requireg to expand production b ger units weigh less per kilo,take up less manufacturing banged in the last few years se in the ordering of nuclear bines and generators powered m I from nuclear plants are iof output and occupy more n a conventional unit. This types of nuclear capacity I 80 - / O N O R D E R , ENDY) 60 - MANUFACTURE OF POWER TRANSFORMERS 240 r 501 Kva and larger / ON ORDER, END OF YEAR 160 - 1963 1964 1965 1966 YEAR FIGURE / / 40 t 1962 1963 1964 YEAR 1965 1966 FIWRB 25 the planning decision to generator startup for nuclear plants. However, the speed up in ordering is prompted to some extent by the concern of utilities to obtain a reasonable place on manufacturers’ booming lists of advance orders. As of the first quarter of 1967, the tivo principal manufacturers of large steam turbine generators were quoting deliveries in the first and second quarters of 1972. Allowing a year for installation and testing, this indicates a lead time of at least six years from order to commercial operation. The following illustrates year-to-year increases in peak loads for the electric utility industry in the contiguous United States. 1961-62 . . . . . . . . . . 1962-63 . . . . . . . . . . 1963-64 . . . . . . . . . . 1964-65 . . . . . . . . . . 1965-66. . . . . . . . . . 24 m The overall space relationship is about 3 nuclear type to 4 conventional type turbo-generators of a given output. / ,' , S H I P P E D DURING YEAR SummerMillions of kw (Gidawatts) 2 / cumulative Total. . . . . . . . . 8.0 - 10.4 15.5 11.3 17.6 62.8 DecembrxMillions of kw (Gigawatts) 10.5 5.8% 10. 1 7.0% 9. 8% 9.8 5yC 9.3 6. 13.5 9.5% ........ 7.6% 6.7Y0 6. 1% 5.5% 7.5% 53. 2 73 The average annual increase in summer loads for the last three years in the above table is nearly 15 gigawatts, which closely approximates the indicated total manufacturing output in 1966.38 Based on information published by Edison Electric Institute in its 41st Semi-Annual Electric Power Survey, April 1967, the past and projected shipments of turbo-electric generators by United States manufacturers are as follows : Megawatts Outside U.S. 1966 . . . . . . . . . . . . . . . 1967 . . . . . . . . . . . . . . . 1968. . . . . . . . . . . . . . . 1969 . . . . . . . . . . . . . . . 1970 . . . . . . . . . . . . . . . 12, loo 19,400 22,700 25,400 24,000 Total -15,500 21,400 24,600 26,400 24.000 3,400 2, ooo 1,900 l,Oc@ ..*......, It is possible that the projected shipment for 1970 may not be inclusive of all orders that will pass through the manufacturing process in that year. The principal manufacturers have recently announced plans for expanding production facilities of steam turbine-generators. The current and projected production capability of these U.S. manufacturers is as follows: 1967 I i 22,060mw.. . . . . . . . 1970 1971 27,000mw... . . . 28,500mw. These projections take into account the mix of normal and conventional type turbo-generators on order. Based on the foregoing, it appears that planned expansion of manufacturing plants should provide a reasonable margin in plant production capacity for the next five or six years. Manufacturers need the help of good load forecasting as much as the utilities. Moreover, since they serve the requirements of the entire nation, longrange comprehensive plans, which are indicative of the range of Sizes and total capacities of various types of generating equipment, are of much interest and o Added annual steam electric generation can be compared approximately to total annual load increases. New steam elect,ric generation is running about 85 percent of total new generation in the United States. New steam electric capacity additions, however, must include about 15 percent for reserve capacity. value to them. The suggestions for coordinated regional planning in this report should result in improved projections and be helpful to manufacturers in the timely planning of adequate production capacity. Preservation of Aesthetic Values Recent events have made aesthetics a primary concern of management in planning and operating electric utility systems. As the population has increased and land use has become more concentrated, the public has become increasingly concerned with aesthetics in all phases of development. It has become an important and early consideration in power system planning. The electric utility industry has responded to this new challenge and is devoting greater attention toward improving the appearance of existing facilities and to the design and location of new facilities. Recent trends include the development of new types of construction materials; blending construction into the surroundings; increasing the capacity of existing transmission facilities to avoid the necessity of acquiring new rights-of-way; utilization of existing rights-of-way for recreational and non-power uses; and continuing research to discover more economical and practical ways to place transmission and distribution lines underground. There are major problems, both technical and economic, in putting high voltage transmission lines underground. Underground Power TransmissionA report to the Federal Power Commission by the Commission’s Advisory Committee on Underground Transmission, April 1966-discusses the outlook for new ideas which are considered worthy of research and investigation, and analyzes the relative cost of underground versus overhead transmission for a variety of conditions. The Electric Research Council, formed in 1965 with representation from all segments of the utility industry, recently adopted a program of research and investigation in underground transmission which is directed toward the development of high-voltage underground equip ment up to 500 kilovolts and the improvement of installation techniques. It is contemplated that these efforts will be supported with both non-Federal and Federal funds. The Secretary of the Interior has requested an appropriation of $2 million as the initial part of a program to support the Federal interest in underground transmission research. Present high-voltage underground construction is generally from 10 to 20 times more costly than over- head transmission of improvements in unc petted, they may not wide cost differential lengths of high-volt tional problems arise In the developmen power system facilith the public be kept it and their economic equally important fc that the public dem; high standards of ae: reliability. If the indl and provides an ear its plans, it will ha reducing delays whit reliability of bulk po Technical Talent The increasing dij taming adequate pn of electric utility 01 facturers, and regl serious problems. ? to the cause fall into as: 1. The industry c sophistication I for a high or planning ant systems. 2. The industry the space am programs. 3. Many uoiven doned program Universities cl try do not sup] gineering as t ence and other 4. Universities st the professor needed and cooperative 1 fellowships. A recent survey sion of 129 colleg technical curricula institutions now 0 engineering. But m suggestions for coordinated this report should result in and be helpful to manufacrnning of adequate production tsthetic Values made aesthetics a primary t in planning and operating F Ls increased and land use has rated, the public has become d with aesthetics in all phases as become an important and I power system planning. industry has responded to this devoting greater attention topearance of existing facilities Kd location of new facilities. the development of new types ‘als * blending construction asing the capacity of es to avoid the necessity * utilization of existnal and non-power research to discover more ecoll ways to place transmission 1 underground. problems, both technical and Ggh voltage transmission lines ground Power Transmissionral Power Commission by the y Committee on Underground 966-discusses the outlook for nsidemd worthy of research analyzes the relative cost of 1 ‘overhead transmission for a The Electric Research Counwith representation from all k industry, recently adopted a j and investigation in underwhich is directed toward the Cvoltage underground equip tolts and the improvement of . It is contemplated that these with both non-Federal and kretary of the Interior has relion of $2 million as the initial )~pport the Federal interest in sion research. underground construction is L times more costly than over- head transmission of equivalent capacity. Although improvements in underground construction are expected, they may not substantially alter the present wide cost differential. For other than relatively short lengths of high-voltage cable installations, additional problems arise in operation and maintenance. In the development of more aesthetically pleasing power system facilities, it is of great importance that the public be kept informed of new developments, and their economic and practical feasibility. It is equally important for the industry to be mindful that the public demands considerations of the same high standards of aesthetics it has come to expect of reliability. If the industry keeps the public informed, and provides an early opportunity for comment on its plans, it will have taken a major step toward reducing delays which could seriously endanger the reliability of bulk power supply. Technical Talent for the Industry The increasing difficulties of acquiring and maintaining adequate professional and technical staffing of electric utility organizations, equipment manufacturers, and regulatory agencies are creating serious problems. The various views advanced as to the cause fall into several general categories, such as: 1. The industry does not adequately portray the sophistication of its needs and the opportunity for a high order of technical innovation in planning and operating electrical power systems. 2. The industry is outbid in securing talent by the space and other government sponsored programs. 3. Many universities have curtailed or abandoned programs in power system engineering. Universities claim that government and industry do not support research in power system engineering as they do in electronics, space science and other scientific pursuits. 4. Universities state that a closer relationship of the professor and student to the industry is needed and could be encouraged through cooperative programs of employment and fellowships. A recent survey by the Federal Power Commission of 129 colleges and universities which have technical curricula revealed that only 29 of these institutions now offer programs in power system engineering. But more revealing still is the acknowl- edgment by many of these schools that their power system programs have limited attraction to students. Some courses are available for which no classes have been formed in several years. Out of the 29 schools, perhaps only 15 can be said to have reasonably active programs in power system engineering. An educator from a large midwestern university reported that only 25 students are majoring in power, out of a total enrollment of 500 .junior and senior students in electrical engineering. He believes the trend in part has resulted from the availability of federal funds for research in other lines of electrical engineering and the lack of similar programs in the electric power field. The students, for example, see great activity in areas related to electronics and information processing, and conclude that the power-related areas are unimportant. He believes that support from both private and federal sources must be made available to foster basic research and development at the universities in power systems including their control. He further observes that utilities salaries are not as high at the start as in other fields, nor has there been any indication that this is made up by faster advancement later. Similar observations were received from several other universities. There appears to be a relatively rigid attitude on the part of some employers that specific education or experience in power system analysis is essential if the applicant is to be considered. Undoubtedly, the average employee who has become expert in power system planning and operation has gained a large measure of his knowledge and ability through study and application subsequent to his academic years. For the aggressive individual, this can be selfinduced; for others it can be acquired through formalized training programs of the employing organization. In any event, in-house programs for training persons with sound technical foundations can be of substantial aid in meeting the problems of personnel shortage. Although many utilities contract with qualified consultants or consulting engineering organizations for parts of their engineering analysis and design, it is the general practice to perform a large share of the engineering work within the operating organizations. The expanding demands for comprehensive system and inter-system studies may exceed the capabilities of utility staffs in several specialized areas and there may be greater need to call upon consulting firms for these services. Such use should 75 help to expand the resources of technical talent available to the industry, and enhance the overall attractiveness of electric systems as a field of technical endeavor. The attraction of adequate numbers of qualified people to the electric utility industry is an important factor in planning for increased reliability. In this brief review, it is not intended to ignore the enlightened action of some utilities and organizations in supporting chairs and fellowships at universities, in conducting cooperative exchange programs with universities and colleges and in offering summer programs for professors and students. But industry wide, these efforts are modest. direction of a voluntary organization, UCPTE,S* composed of representatives of the eight countries. In addition to UCPTE, which was founded in 1951, a number of other coordinating organizations have come into being in various parts of Europe, as shown in figure 27. Operations are guided essentially by working groups of experts who deal with technical problems, examine economic effects and prepare recommendations, which, however, are not obligatory. Subordinate groups examine questions involving service, the operation of thermal power stations, and the operation of hydroelectric projects.‘0 Observations on Power Systems of Other Countries UCPTE has recommended to all participants of the interconnection that sufficient spinning reserve be maintained to limit frequency variation to onehalf cycle per second, which is equivalent to a spinning reserve of four to five percent. Also, if a frequency decrease cannot be avoided, provisions are recommended for suitable load shedding. Most of the interconnected systems maintain protective controls at the borders between countries to open the circuits in the event that a disturbance occurs on the interconnected network which could affect the stability of the system within the protected country. Under a typical arrangement, the country import- A general review has been made of power systems in a number of other countries with emphasis on any particular practices in planning and operation which might have useful application in the United States. Table 5 compares the magnitude of electric power installations in the United States with nine other countries having the highest installed capacity. International Interconnections The largest interconnection of power systems outside of the United States (figure 26) is located in western Europe and includes eight countri&Belgium, West Germany, France, Italy, Luxembourg, Netherlands, Austria and Switzerland. Power is exchanged between these countries under specific contracts between two or more parties, but the operation of the network as a whole is under the general TABLE Interconnected Operations 19 Union for the Coordination of the Production and the Transmission of Electricity. ” The information on European interconnections has been summarized largely from the paper on “Economic Problems in the Operation of Integrated Power Transmission Systems in Europe,” presented by Franz Hintermayer at the World Power Conference Sectional Meeting in Tokyo, 16-20 October, 1966. 5.-Cafiaci& andjmduction of electric systems, U.S. and othr countries-?965~rcliminary da& I Installed Hydro united states . . . . . . . . . . . . . . . . . . . . . . U.S.S.R . . . . . . . . . . . . . . . . . . . . . . . . . . United Kingdom. . . . . . . . . . . . . . . . . . Japan . . . . . . . . . . . . . . . . . . . . . . . . . . . . GermBny (west). .................. Canada. . . . . . . . . . . . . . . . . . . . . . . . . . . France ..: . . . . . . . . . . . . . . . . . . . . . . . . Italy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Germany (East). . . . . . . . . . . . . . . . . . . swcde.n ........................... 44,490 22,250 1, 760 16,284 4, 064 21,792 12,631 14,272 349 9,297 Capacity-Mw Thermal 210,030 92,550 46,650 24,815 35,878 7, 602 15,447 10,824 10,311 2,411 I Total Production-Million Hydro _254,520 114,800 48,410 41,099 39,943 29,394 28,078 25,096 10,660 11,708 196,984 80,617 4,612 75,464 15,145 116,712 46,429 42,831 562 45,966 6 Thermal Total _1, 157, 583 480,383 184,266 181,942 160,554 143,161 101,442 80,287 49,958 %fjOO 960,599 399,766 179,648 106,478 145,409 26,449 55,013 37,456 49,396 2,532 7 Kwh - - PRIN GREAT E ~ta.ry organization, UCPTE,*e ntatives of the eight countries. ‘E, which was founded in 195 1, xndinating organizations have various parts of Europe, as uided essentially by working I deal with technical problems, ects and prepare recommenter, are not obligatory. Subdne questions involving service, amal power stations, and the :ctric projects.‘O ,ected Operations PRINCIPAL TRANSMISSION LINES IN WESTERN EUROPE 1966 GREAT BRITAIN mended to all participants of @it sufficient spinning reserve bt frequency variation to one, which is equivalent to a spinif” five percent. Also, if a freLot be avoided, provisions are itable load shedding. Most of items maintain protective conbtween countries to open the bat a disturbance occurs on the irk which could affect the statithin the protected country. ngement, the country importlination of the Production and the ity. r European interconnections has i from the paper on “Economic on of Integrated Power Transmis’ presented by Franz Hintermayer lonference Sectional Meeting in 1966. c preliminary data Production-Million Kwh yo 984 617 I,612 ,464 , 145 ,712 ,429 ;831 :562 ;966 Thermal 960,599 399,766 179,648 106,478 145,409 26,449 55,013 37,456 49,396 2,532 Total 1, 157,583 480,383 184,260 181,942 160,554 143, 161 101,442 80,287 49,958 48,500 LEGEND - 380K” TRANSMISSION LINES .....***** 220K” T R A N S M I S S I O N L I N E S - DC TRANSMISSION LINES N U M B E R O F CIRCUITS FIGURE 26 ing power receives a first warning by an alarm signal if the flow of power on the interconnection reaches, say, 95 percent of normal maximum value. A second alarm might be received at 105 percent, and at 135 percent the line would be opened. With this procedure, the importing country may have several minutes to reduce the amount of power imported by increasing the output of its generators or by curtailing loads. Inter-ties are usually protected by underfrequency relays which may operate either with delayed action to give a few minutes warning or may open the inter-tie as soon as a specific level of subnormal frequency is reached. Under these provisions, the interconnected network serves well for economic exchanges and has been of assistance in preventing loss of power on a system of an interconnected member nation. It is not designed, however, to provide major assistance to member countries experiencing a severe diiturbance. EUROPEAN POWER POOLS 27.-European Power Pools UCPTE-Union for the Coordination of the Production and the Transmission of Electricity UFIPTE-France-Iberian Union for the Coordination and the Transmission of Electricity SUDELSouth-European Union for the Coordination and the Transmission of Electricity NORDEGScandinavian Power Pool COMECON-Communist Eastern European Power Pool FIGURE 78 Many aspects of interconnected system planning and operation are summarized in a UCPTE article “Mesures Propres a Eviter des Perturbations Importantes sur les Reseaux d’Intercormexion,” extracted from Bulletin Trimestrial IV 1966. Many of the practices described are similar to those commonly used in the United States. Examples of Particular Systems and Practices The power systems of the major countries of Europe and of Japan are fairly well interconnected and controlled. The practices followed, although varying from one nation to another. are generally similar to those utilized by interconnected systems in the United States. Transmission at 225-kilovolts, 275-kilovolts and 400-kilovolts prevails in most 01 the larger countries. Power installations in France, totalling more than 25,000 megawatts, are about equally divided be tween thermal and hydroelectric stations. Electricite’ de France, a national organization which produces about two-thirds of the country’s power supply, has a central dispatching office in Paris and eight regional centers. The system maintains spinning reserve capacity equal to three to five percent of the system load or enough to cover the loss of the largest line. Each area of the system carries an appropriate part of this reserve to maintain area security. As much as 70 percent of load can be shed in successive blocks from 48.5 to 47.5 cycles per second (cps) . The normal frequency of European systems is 50 cps as opposed to the United States standard of 60 cps. This load shedding program has been in use since 1938, and since 1945, has been a statutory requirement. The supply of bulk power in England and Wales is under the direction of the Central Electricity Generating Board, a national organization. CEGB operates eight regional load dispatching offices under the general direction of the central load dispatching office in London. Systems in Scotland are under separate control but are interconnected with the CEGB system. The peak demand for England and Wales in 1965 was 35,000 megawatts, with aa installed capability of 36,600 megawatts. Most of the power is generated in central and northern England and Wales by coal burning steam-electric stations, and is transmitted to load centers in central and southern England through a network of five double circuit 275.kilovolt lines. Planning of the transmission system is based on the assumption that system integrity must be main- tamed with the transmission lint Generation is margin above t winter. This is some load in ac average of one 1 needed, five ste duction in systf per second ; sect with a load red) each stage ; thir tor output, limil capable of augl 700 megawatts : which are interr fifth, manual ( shedding in tht plans are bein frequency relay Installed cal megawatts, of The Swedish ! tional grid syst tion. The nets kilovolt circuit! hydroelectric ! Sweden to loac operating trite the north-soutl circuit. Transi network are m puter program: On the basi number of ye Board has eval interruptions a power, plus 4C eration, the 1~ duction cost. 1 the Swedish S1 to the Northe: of approximat to rough estim east failure. As mention1 Swedish Boar north-south tr viding for the planned in thf certain gener tripped, upon lterconnected system planning I arized in a UCPTE article viter des Perturbations Imc beaux d’Interconnexion,” exTrimestrial IV 1966. Many of ed are similar to those com,ted States. ular Systems and Practices of the major countries of are fairly well interconnected practices fohowed, although tion to another. are generally :ed by interconnected systems Transmission at 225-kilovolts, l-kilovolts prevails in most of IS in France, totalling more than about equally divided be%roelectric stations. Electricite’ organization which produces country’s power supply, has 1office in Paris and eight retern maintains spinning re6 three to five percent of the I to cover the loss of the largest system carries an appropriate :o maintain area security. As Bf load can be shed in succeso 47.5 cycles per second (cps) . :y of European systems is 50 United States standard of 60 ing program has been in use e 1945, has been a statutory power in England and Wales m of the Central Electricity Inational organization. CEGB al load dispatching offices tion of the central load dis1 don. Systems in Scotland are bl but are interconnected with he peak demand for England ‘as 35,000 megawatts, with an f 36,600 megawatts. Most of ted in central and northern coal burning steam-electric Ritted to load centers in cenlgland through a network of 5.kilovolt lines. msmission system is based on ystem integrity must be main- tained with the loss of a complete double circuit transmission line. Generation is planned for a 17 percent capacity margin above the projected loads for an average winter. This is said to require the interruption of some load in addition to voltage reduction on the average of one winter in twenty-five. If load relief is needed, five steps have been provided: first, a reduction in system frequency from 50 to 49 cycles per second; second, voltage reduction in two stages with a load reduction of about 3 to 31/z percent for each stage; third, an emergency forcing of generator output, limited to about one hour’s duration and capable of augmenting the supply by some 600 to 700 megawatts; fourth, disconnecting certain loads which are interruptible under tariff agreements; and fifth, manual or automatic load shedding. Load shedding in the past has been done manually, but plans are being formulated for utilizing underfrequency relays. Installed capacity in Sweden is nearly 12,000 megawatts, of which about 9,300 is hydroelectric. The Swedish State Power Board controls the national grid system and about 45 percent of production. The network consists principally of five 400kilovolt circuits extending 400 to 600 miles between hydroelectric generating plants in the north of Sweden to load centers in the south. Planning and operating criteria require integrity of operation of the north-south transmission system after loss of one circuit. Transient and steady-state analyses of the network are made, using sophisticated digital computer programs. On the basis of a, comprehensive study made a number of years ago, the Swedish State Power Board has evaluated the cost to the nation of service interruptions at 20 cents per kilowatt of interrupted power, plus 40 cents per kilowatt-hour of lost generation, the latter being about 50 times the production cost. As a matter of interest, engineers of the Swedish State Power Board applied their values to the Northeast interruption and obtained a figure of approximately $80 million, which is comparable to rough estimates of the tangible cost of the Northeast failure. As mentioned earlier, a principal concern of the Swedish Board is maintaining the integrity of the north-south transmission system. In addition to providing for the loss of one line, other actions are planned in the event of an emergency. For example, certain generators in the north are automatically tripped, upon loss of lines, to prevent overloading and instability tripping of other lines. Load shedding is practiced in southern load areas if needed, but a general program of underfrequency load shedding has not been adopted. If loss of power should occur, restoration procedures are based on rapidly mobilizing the northern hydro resources. Power Failures No formal record of power failures in other countries is available, but general information has been obtained from various sources, much of it through technical exchange visits of government and industry representatives, who have provided information on failures which have occurred. The causes are similar to those which have initiated failures in the United States. The system planners and operators in these countries are also concerned with the need for incorporating any improvements in planning and operation which will raise the standards of reliability in bulk power supply and, above all, prevent major cascading failures. The Northeast failure has alerted electric utility officials in all countries with well-developed systems to the magnitude of failure that can occur. The Commission’s December 6, 1965, report on the Northeast power failure has been translated into a number of languages and widely reviewed in foreign countries. A few of the major failures which have occurred in recent years in other countries are summarized in the paragraphs following. They illustrate difficulties similar to those experienced in the United States : The loss of 3,000 megawatts, about 75 percent of total system load, of the Kansai Electric Power Company in Japan on June 22, 1965, as a result of a landslide which damaged a transmission line. Full restoration of service was completed within three hours. On March 27,1959, the entire Belgian system was interrupted while carrying a load of 2,200 megawatts. The interruption was precipitated by failure of a 36,000~volt cable, followed by breakup of the 150-kilovolt network, frequency decay, and loss of generators because of overload or loss of auxiliaries. 0.n January 24, 1966, a 220-kilovolt breaker exploded near Lyons, France, resulting in the loss of about 2,000 megawatts of generation for up to an hour. A failure caused by transmission line &lays set at limits that were too low occurred in 1961 in northeast England, and affected part of London. One relay operated as its load setting was reached, 79 and other lines opened quickly in sequence, causing a loss of power which lasted from five to six hours. Northern Italy experienced a power interruption on October 13, 1964, when an electrical storm tripped two lines in central Italy, causing lines which were importing 1000 megawatts of power from Switzerland to trip on overload. The northern industrial area became isolated from the main systems of Italy and southern Europe. Frequency dropped to 48.2 cycles per second for six minutes, then momentarily to 47 cycles when a thermal plant tripped out on loss of auxiliary power. This was followed by the loss of about 4000 megawatts of power in the entire area. Service was restored in about 19 minutes. On January 8, 1966, a defective line connector caused a 130-kilovolt line to open in the vicinity of Naples, Italy, causing four other lines bringing power to the Naples area to trip, interrupting service to the area. Other lines which had sufficient capacity to carry the extra load temporarily tripped out because a relay had been set too low. Power was restored over a period of 20 minutes to nearly five hours. The entire system of Switzerland was lost for about an hour on January 17,1963. This was caused by an overload and tripping of ties with other countries. It occurred when attempts were being made by Switzerland to make up a deficiency of 200 megawatts suddenly lost in an interconnected country. On June 12, 1960, the system of West Germany separated into two parts as the result of the cascade tripping of north to south ties. The northern part, along with Denmark, continued to operate but the southern portion was lost. All service was restored in two hours. International Technical Exchanges Knowledge of new developments and new prcr cedures is continually exchanged between power system experts of the United States and those of other countries. Papers summarizing results of research and studies are presented at meetings of various international organizations such as the World Power Conference and CIGRE.‘l Equipment manufacturers in many countries have extended their sales and service programs to all parts of the world, a Conference Intemationale des Grands Electriques a Haute Tension. 80 and thus have intimate knowledge of planning and operating practices of systems in many nations Visi.ts are frequently made between countries to ob serve and discuss trends and practices. Many d these international reviews are supported by gov emments as well as by power supply entities. Comparability In general, power systems in the United State and in other countries utilize similar equipment and follow similar practices in planning and operation Although systems of Western Europe are extensive11 interconnected internationally, only limited reliana is placed on these ties for emergency support. Be cause of the absence of political boundaries, inter connection and coordination in the United State have advanced further than elsewhere. In spite 0:t the diverse structure of the U.S. power systems;, coordination in this country probably will continue ! c to progress at a faster rate than in other parts of the . world. A number of practices of interest have been ob served in reviewing systems in other countries. Some systems, notably Electricite’ de France, have pro vided elaborate display of power flows and system I conditions on a current basis, giving operators I knowledge of conditions that exist at any time. Most systems utilize or are installing computer systems for analyzing data, for security checks, and, in a few I cases, for the economic selection and dispatch of power. Italy has strengthened its north-south network and has a substantial reserve capacity in its transmission system for potential impacts. It has installed a number of frequency relays which are. actuated by a time-rate of frequency decay, in addition to fixed low frequency tripping. Several of the European systems require full capability of steam~ plant auxiliaries at frequencies as low as 46 to 48 cycles per second (50 cycles per second is normal) 1 and one system is installing gas turbine generators to- furnish power for steam-plant auxiliaries at normal frequency if system frequency declines. Atten- I tion is being directed to arrangements which will permit quick isolation of generating units in time of severe system trouble to prevent loss of units if system power collapses. In summary, it can be said that the best prz~tice~ in a number of other countries are generally equivalent to the best practices in the United States. NO new developments were found in the planning and \ ff operation of p a panacea for or in the Unit The intensii tion internally suming nation exist in well-cc The interconn tte knowledge of planning and of systems in many nations. de between countries to obP ends and practices. Many of eviews are supported by govy power supply entities. mparability systems in the United States s utilize similar equipment and xs in planning and operation. Western Europe are extensively lationally, only limited reliance w for emergency support. Beof political boundaries, interdination in the United States ,er than elsewhere. In spite of t of the U.S. power systems, ~untry probably will continue : rate than in other parts of the operation of power systems abroad which represent a panacea for power failure problems either there or in the United States. The intensity of interconnection and coordination internally in a number of the larger power consuming nations is comparable to conditions which exist in well-coordinated areas in the United States. The interconnection and coordination among sys- tems and regions throughout the United States has developed further, on the average, than among nations in Europe. The scale of power use and service territory in the United States is larger, and opportunities generally are more abundant and attainable for conserving reserves, for making economy and diversity exchanges, and for mutual support to meet emergencies. ‘ces of interest have been o Iiterns in other countries. Some ttricite’de France, have prolay of power flows and system ,rrent basis, giving operators ons that exist at any time. Most installing computer systems for k curity checks, and, in a few mic selection and dispatch of mgthened its north-south netstantial reserve capacity in its or potential impacts. It has frequency relays which are 1k of frequency decay, in addiency tripping. Several of the uire full capability of steamP uencies as low as 46 to 48 cycles per second is normal) b” talling gas turbine generators team-plant auxiliaries at nor1 m frequency declines. Attenb to arrangements which will m of generating units in time ible to prevent loss of units if Es. 1 be said that the best practices countries are generally equivaitices in the United States. NO ere found in the planning and 81 CHAPTER 8 THE COMMISSION’S RESPONSIBILITIES AND ACTIVITIES TO IMPROVE COORDINATION AND RELIABILITY The Commission’s Responsibilities The Northeast power failure called public atten.ion to the fact that the Federal Power Commission lees not have specific authority for the reliability of service of the interstate electric power industry, or ‘or approving the construction of facilities or the operating practices of the systems affected by the sower failure. The Commission has no licensing authority over generating or transmission facilities, )ther than hydroelectric projects which come under ts jurisdiction including directly related transmisiion lines. The Commission has no authority to reluire adherence to reliability standards. The responsibilities of the Federal Power Comnission are established by the Federal Power Act, 1. statute which had its origin in 1920 as the Federal Water Power Act. The original act, now Part I of :he statute, defines the Commission’s responsibilities ior licensing projects for the development cf hydm:lectric power and other uses. The Act was substantially expanded in 1935, by the addition of Parts II and III, to include the regulation of “public utilities” engaged in the transmission of electric energy in interstate commerce, including the regulation of rates, and sale of electric energy at wholesale in interstate commerce, accounting practices, issuance of securities, collection and publication of data, and other administrative and corporate review functions. Part II includes a number of responsibilities pertaining to the interconnection and coordination of electric utilities, but for the most part, actions depend upon voluntary cooperation by the industry, or require formal complaint before action can be taken by the Commission. The Act, which has not been significantly amended since 1935, does not use the specific term “reliability,” but in 202 (a) cites “an abundant supply of electric energy throughout the United States” as an objective, and grants authority to the Commission, as noted herein, to take certain actions in emergencies. Section 202(a) of the Act sets forth major responsibilities in coordination. It directs the Commission to promote and encourage the interconnection and coordination of power systems for the purpose of assuring an abundant supply of electric energy with the greatest possible economy and with regard to the proper utilization and conservation of natural resources. The Commission is directed to divide the country into regional districts for the voluntary interconnection and coordination of facilities for the generation, transmission, and sale of electric energy, and to make such modification thereof as in its judgment will promote the public interest. Each such district shall embrace an area which, in the judgment of the Commission, can economically be served by such interconnected and coordinated electric facilities. The National Power Survey, which the Commission published in December 1964, suggesting general guidelines for the coordinated growth of the industry in the future, was conducted principally under the provisions of Section 202 (a). Section 202 (b) authorizes the Commission, upon complaint, to require a jurisdictional public utility, after opportunity for hearing, physically to interconnect its transmission facilities with the facilities of other entities engaged in the transmission or sale of electric energy or to sell energy to or exchange energy with such persons. The Commission may require interconnection, exchange or sale only if no undue burden will be placed upon the public utility, and the Commission may not compel the enlargement of generating facilities or any action which would impair the ability of a utility to render adequate service to its customers. When the Commission directs an interconnection, it may prescribe the terms and conditions to govern the inter-utility services. The limited authority to order interconnections permits the Commission in some cases to enhance reliability by providing utility systems with a 83 more reliable power supply, subject to the payment of fair and reasonable compensation. Isolated SYSterns dependent wholly upon their own generation have filed complaints under this provision in order to secure backup from neighboring systems. The section has been invoked also to secure an alternative interconnection as a means to enhance reliability and efficiency. The Commission may not act under Section 202 (b) in the absence of a complaint. In practice, the section has not been used by major bulk power systems which have failed to secure voluntary interconnections with other major systems. The Commission has recommended to Congress in the past that it be empowered to require interconnection (subject to all the safeguards of the existing law) on its own motion as well as upon complaints. Section 202(c) provides that during any war, or whenever the Commission determines that an emergency exists by reason of a sudden increase in the demand for electric energy, or a shortage of electric energy or of generation or transmission facilities, or for other causes, the Commission may act upon complaint or upon its own motion, with or without notice or hearing, to require temporary connections and service to meet the emergency and serve the public interest. Any emergency service is, of course, to be paid for on a just and reasonable basis. Last year the Commission exercised this authority to require emergency interconnection between two neighboring utility systems where the smaller‘ system had been electrically isolated and as a result had suffered a series of interruptions. Section 203 of the Act provides for Commission review of utility property transfers and mergers (except those subject to the Public Utility Holding Company Act), affording the Commission some opportunity to consider reliabilitpof service and other coordination problems and to require the parties to a transaction to achieve the most satisfactory arrangement. Sections 205 and 206 ‘Grovide for Commission review and regulation of wholesale rates and charges for services rendered by jurisdictional public utilities. These provisions authorize Commission review of their power pool arrangements, and consequently provide a further opportunity to assist the parties in strengthening the coordination of bulk power suPPlY* Section 207 authorizes the Commission, upon complaint of a State commission and after oppor84 tunity for hearing, to determine the proper, adequate or sufficient service, to be furnished by a utility so long as it does not compel the enlargement of generating facilities or compel the sale or exchange of energy, when to do so would impair the utility’s ability to render adequate service to its customers. Since no state commission has ever filed such a complaint, the full scope of this section is I uncertain. FPC Activities in Coordination In December 1964, the Commission published the National Power Survey Report, a comprehensive analysis of electric systems in the United States. The Survey projected the growth of electric requirements to 1980, and suggested general patterns for i industry growth and coordination. It also evaluated the many benefits attributable to interconnection I and coordination. I The Survey was prepared with the collaboration of many outstanding utility representatives from all parts of the country and from all segments of the electric power industry, including representatives of state commissions. It has helped to further the economic and coordinated development of elec- t tric power systems. The close association of many industry leaders from all segments has promoted a better understanding of some of the problems which I have retarded collaboration. With the help of an Executive Advisory Committee and six Regional Advisory Committees, the Commission is now revising the Survey so that it ’ may continue to serve as a current reference in electric utility planning. The goal is to publish an up dated report early in 1969. With the continuing cooperation of the Advisory Committees and the industry, the Commission believes the course of studies in updating the Survey will prove to be of substantial value. In addition to the end product of a new Survey, much benefit will undoubtedly accrue, as it has in the past, from the cooperative association among the members of the Advisory Committees and others in the industry assisting I them, and with the Commission and members of its staff. It should be recognized, however, that the six existing Regional Advisory Committees have been established as sources of analysis and information rather than for planning and operation. This report urges that additional regional planning organizations be established throughout the industry for these purposes. Such groups would be distinct tram and she gional , templa Part1 Comm: arbiter mental This k formal and iI was in vey al years, came i Furthc The impm opcrx to irnl leadin sire a advar dures, vincir aligrlc time, prop< porta try 1, In sion’s . inter1 and time1 pro0 tions failu W tDjb indu ities. COUl. regic or ii Con gion plar tinu pro; to t D determine the proper, adeervice, to be furnished by a us not compel the enlargement bs or compel the sale or exlen to do so would impair the ier adequate service to its custe commission has ever filed e full scope of this section is and should by no means supersede the present Regional Advisory Committees. The Commission contemplates continuation of the Power Survey effort. Partly as a result of the work of its Survey, the Commission has been able to serve as an effective arbiter on numerous intersystem and inter-segmental issues for the benefit of the public interest. This has been achieved by both formal and informal means. Industry interest in the formation and improvement of coordinating organizations was intensified during the preparation of the Survey and following its publication. During these years, a large number of pools and planning groups came into existence in many parts of the country. Coordination 1, the Commission published gurvey Report, a comprehen: systems in the United States. the growth of electric requireuggested general patterns for oordination. It also evaluated tributable to interconnection Further Commission Assistance The industry as a whole recognizes the need to improve coordinated planning, construction, and operation, and is taking steps on its own initiative to implement more effective action. Although many leading industry participants have expressed the desire and shown the capability for leadership in ad\ ancing coordinating mechanisms gnd procedill-es, the course of achievement is not easy. Convincing a large number of utility participants aligned in diverse forms of ownership takes much time, persuasion, and understanding on the part of proponents. We believe that the magnitude and importance of the problems which confront the industry will require greater Commission assistance. In chapter 9 we have summarized the Commission’s recommendations for improving practices in interconnected system planning, design, operation and maintenance. Of primary importance is the timely and useful formulation of organizations and procedures which will help to achieve the suggestions which have come from our review of power failure experiences. We are recommending in chapter 9 that the country be divided into appropriate regions in which the industry can conduct intensive coordinating activities. We are suggesting that regional coordinating councils be established in which all utilities in the region have the opportunity to participate, directly or indirectly. We foresee the usefulness of having Commission representation at the meetings of regional councils. The process of coordinating the planning of utilities in the region should be continuous to keep plans updated. Plans should be projected sufficiently in advance to be of value, alike, to the coordinating utilities, to manufacturers and :pared with the collaboration utility representatives from try and from all segments of dustry, including representaions. It has helped to further rdinated development of eleche close association of many all segments has promoted a $ some of the problems which ration. Executive Advisory CommitI Advisory Committees, the :vising the Survey so that it as a current reference in elecThe goal is to publish an up1969. With the continuing dvisory Committees and the rsion believes the course of .e Survey will prove to be of addition to the end product Ich benefit will undoubtedly e past, from the cooperative e members of the Advisory :rs in the industry assisting lmmission and members of its gnized, however, that the six isory Committees have been of analysis and information kg and operation. This report Iregional planning organizabroughout the industry for roups would be distinct from to the public and public officials concerned with how environmental values can best be preserved or enhanced. To serve these objectives, we are suggesting that comprehensive plans should be projected not less than six years in advance of their intended completion, and tentative general programs ten years in advance. Plans should be open to modification from year to year or at intervening times as conditions arise which would make it prudent to do SO. The Commission, concurring in the recommendations of its Advisory Committee on the Reliability of Electric Bulk Power Supply, advocates the establishment of an interregional Council on power coordination composed of representatives from each of the nation’s regional coordinating organizations. The Council would exchange and disseminate information on regional coordination practices to all of the regional organizations, would communicate to the public, and keep state, regulatory and government authorities informed on coordination programs, and would review, discuss, and assist in resolving matters affecting interregional coordination. The Council could also assist regional organizations in supplying data for interregional studies. Within a relatively few years, utilities should be able to assist each other through exchanges of capacity and energy on a broad interregional scale. As recommended in chapter 9, general criteria and standards of national and regional applicability should be established for the planning, operation and maintenance of power systems to avoid omissions which could lead to questioned reliability. Regulating the construction of new EHV transmission facilities including the authority to assist utilities in securing rights-of-way when required for approved facilities would assure that wasteful duplication of facilities is avoided; that such facilities are planned with adequate capacity to meet the foreseeable regional transmission needs of all utilities; that they conform with network plans tested for stability; and that the facilities are planned and constructed to protect aesthetic values.42 Planning which overcomes competitive differences among various utilities and segments of the industry will encourage the most effective development of our “The Commission has supported and recommended legislation providing for Federal certification, by the FPC, of new EHV transmission lines and hearings were held by the Committee on Commerce, U.S. Senate, on S. 1472, S. 2139, S. 2140,89th Congress. 85 t bulk power systems with minimum intrusion upon competing social values. The major problem raised in past hearings was the fear the certification proceedings might themselves unduly delay construction of EHV facilities. The Commission, in turn, has recognized that certification of EHV lines, standing alone, might not prove effective in realizing the major objectives unless the proposed review, mainly informal in nature, could begin relatively early in the continuous planning process. I I I / Achieving x-c power involves prise-the plal maintenance 0 to develop im methods; and public and wit responsibilities mental values. The industr growth in the farsightedness for a continui utilities can r public with a electric energ thoughtful car power system The tentati. in the Comm on the North stantiated by in the expanc this report. 1 have also incl nizations, pral tion, includin plies to meet future. In thj tees, establish dating the P great assistan In broad 1 has supplied and adequat supply failur utilities havl many years u1 Northeast Report to the December 6, n of EHV lines, standective in realizing the Iposed review, mainly ;in relatively early in is. CHAPTER 9 CONCLUSIONS AND RECOMMENDATlONS Achieving reliability in the supply of electric power involves every aspect of electric utility ewerp&-the planning, construction, operation and maintenance of electric power facilities; research to develop improved materials, equipment, and methods; and the relationship of utilities with the public and with parties having special interests or responsibilities in protecting resource and environmental values. The industry can never be static. The dynamic growth in the demand for electric power compels farsightedne’ss in planning of new facilities. It calls for a continual reappraising of ways in which all utilities can more closely cooperate to serve the public with an abundant and reliable supply of electric energy at the lowest cost consistent with thoughtful consideration to minimize the impacts of power system facilities on environments. The tentative conclusions and recommendations in the Commission’s initial report to the President on the Northeast power failure *3 have been substantiated by our further studies and are included in the expanded findings and recommendations of this report. The Commission’s subsequent studies have also included a general survey of utility organizations, practices and problems throughout the nation, including the probable gdequacy of power supplies to meet unforeseen peak demands in the near future. In this, the six Regional Advisory Committees, established by the Commission to assist in updating the National Power Survey, have been of great assistance. In broad perspective, the electric power industry has supplied the nation with a highly dependable and adequate supply of bulk power. Major power supply failures have been relatively infrequent and utilities have met increasing power demands for many years with few defaults. There are many de‘* Northeast Power Failure, November 9 and 10, 1965 ; a Report to the President by the Federal Power Commission, December 6, 1965. ficiencies, however, that need attention, and their correction is becoming more important with each passing year. The Commission’s conclusions and recommendations apply not only to the area directly affected by the November 1965 power failure, but also to systems throughout the nation. The circumstances that triggered and attended the Northeast power failure are not unique in power system operation. The power surge which ensued was unusual in magnitude, but not unprecedented. The quick opening of transmission lines from overloading and instability has occurred many times in the operation of power systems. The isolation of areas with deficient generation, causing a drop in system frequency, is not a new experience, and the total loss of system power and slow rebuilding of boiler steam pressures to restore generation has happened before. The Northeast incident revealed numerous system conditions which were marginal, but still sufficient to meet ordinary disturbances. When sharply triggered, they pyramided into an unprecedented failure. Upgrading the reliability of bulk power supply throughout the nation will involve expenditures of several billion dollars. These investments, while large, are small in comparison with total electric utility investments. Improving metering and display arrangements for the benefit of system operators, upgrading communication systems, installing underfrequency relays for load shedding, providing emergency power supplies to permit rapid restarting of generating units and other related improvements will cost many millions of dollars on a national scale, but in total perspective, such expenditures are nominal. By far, the largest cost will be incurred in strengthening transmission systems with thousands of miles of EHV lines. Yet even here, although the additional investment over the next eight years might amount to as much as $3 billion, the added annual cost, relatively, is not large. In 1975, it would be less than two percent of the estimated cost of supplying power to meet the projected loads. 87 The added transmission which we believe is essential for improving reliability should have large reserve capacity to serve unforeseen requirements and opportunities. The nation’s interconnected power systems now span a tremendous field of present and potential diversities-diversity in power demands including errors in forecasting, in fuel costs and the opportunities for economic energy exchanges, in water resources, in types of generation and their proper association to meet regional loads, in weather extremes and the threats of unprecedented localized loads, in air pollution and shifts in generation for relief under critical circumstances, and in the diversity of scheduled maintenance, forced outages of equipment and a wide variety of emergency power and transmission demands. The nature and magnitude of the benefits of increased transmission capability will be varied and extensive. Through meaningful coordination of utility systems throughout the nation, improvements made for power system reliability can be associated with large economic benefits as well. If the recommendations in this report are adopted and conscientiously followed by the electric utility industry, it is believed that the probability of recurrence of major cascading bulk power failures can be greatly reduced. The Commission’s specific conclusions and recommendations follow : Formation of Coordinating Organizations As outlined in chapter 4, a variety of planning and pooling organizations are contributing substantially to improving the economy and reliability of power supply in their areas, but some are too limited in membership or in scope of activities to be effective fully. Others have overlapping responsibilities and in many sections no effective organizations have been formed. In general, there is a need for improved alignment and strengthening of coordinating organizations. 1. To the extent they do not now exist, strong regional organizations need to be established throughout the nation, for coordinating the planning, construction, operation and maintenance of individual bulk power supply systems. a. In view of the rapid growth of the industry and the urgent need for accelerated coordination, the service areas of the .@ contiguous states should be grouped into regions, each to be served by a coordinat- 88 ing organization which would include representation from all utilities in the region. These organizations should be provided with ample funds by member utilities and have procedures for effective coordinating actions. In the years ahead, utility management cannot fully discharge its responsibilities without intensive participation in coordinating activities. All participating utilities should respect the legitimate interests of adjoining utilities. b. Representation of systems in regional organizations should be grouped to facilitate progressive improvement in coordination. Coordination of planning and operation of bulk power supplies on a regional basis cannot be performed efficiently by a large number of people such as might be assembled if every utility in a region were individually represented. Qualified representatives of groups of systems will produce effective results. Technical committees with limited, rotating membership have proven workable and effective. 2. A Council on Power Coordination should be established, made up of representatives from each of the nation’s regional coordinating organizations to exchange and disseminate information on regional coordinating practices to all of the regional organizations, and to review, discuss, and assist in resolving matters affecting inter-regional coordination. Interconnections and power exchanges ,between regions today are fairly abundant. Many requirements and opportunities for enhancing the reliability and economy of bulk power supply will necessarily extend across regional boundaries. 3. A Central Study Group or Committee should be established to coordinate industry efforts in investigating some of the more challenging problems of interconnected system development. An early coordination of ideas, efforts and funds is needed for more effective investigations and research in planning and operation. Today, most utilities are burdened with system problems demanding immediate solutions, making it difficult for them individually to devote adequate attention to advancing the development of improved design and operatir be perfc universi before I ive rang search rently c minima Interconned Numerous fications shou facilities. Son listed below. 4. Early ( transm The York a ing sys for hi! missior betwee Pennsl netwol from delays recom North PJM and shoulc of vol provic and 1 system Thr Michi Ohio cling COT of Tl Onta syster tern ( the , Elect inati 5. Trar revit ning shou proc elude L the vided s and ating manspanon in mating interorgaXtate &on. ation basis large aemindientaxiuce ittees have Id be f rom ating inate prac; and mat72. :s bedant. s for 1y of stend ‘lould forts ngiv lelop- sand stigaation. h syssolulually ncing and operating practices. Much of the work could be performed under contract with qualified universities and research institutions, placing before the education committee an attractive range of technological examinations. Research investigations in electric power currently offered to educational institutions are minimal. Interconnected System Planning Numerous improvements, expansions and modifications should be made in interconnected system facilities. Some of the more important of these are listed below. 4. Early action should be taken to strengthen transmission systems serving the Northeast. The peninsular relationship of the New York and New England areas to the adjoining systems of other states and Canada, calls for highly coordinated planning of transmission. The 500~kilovolt interconnection between southeastern New York and the Pennsylvania-New Jersey-Maryland ( P JM) network, which has required rescheduling from 1968 to 1969 because of right-of-way delays, is urgently needed. The Commission recommends an early strengthening of the Northeast network and additional ties to the PJM systems and to other systems in Ohio and western Pennsylvania. Consideration should be given to the need and desirability of voltage levels higher than 345 kilovolts to provide strong ties between the New England and New York utilities and to adjoining systems. The initial interconnection in 1969 of the Michigan utilities with those in Indiana and Ohio will close a transmission loop encircling Lake Erie. This loop network which incorporates the western part of the system of The Hydro-Electric Power Commission of Ontario is being reviewed by participating systems to determine its adequacy under system conditions similar to those suggested by the Advisory Committee on Reliability of Electric Bulk Power Supply. A careful examination is merited. 5. Transmission facilities should be critically reviewed throughout the nation, and planning and construction of needed additions should be accelerated on schedules which will provide ample transmission capacity to meet a broad range of potential needs for both reliability and economy as they occur. Transmission networks and ties between areas and regions are now deficient in numerous locations. Many systems have not participated in, or completed, area or regionwide studies of their systems under severe impact. Accelerated studies of transmission systems regionally and inter-regionally are among the industry’s foremost responsibilities. a. Networks should remain stable under severe disturbances. Networks should be planned and tested for their ability to withstand the severe types of contingencies discussed in chapter 5. Stability analyses should include examination of both regional and inter-regional strength. b. The pace of construction should enable transmission capability to lead rather than lag behind emergency requirements. The transfer of power from an area with surplus generating capability to one experiencing a deficiency is frequently restricted because of inadequate transmission capacity. The incremental cost of an adequate network in comparison with one of marginal capability is a small part of the total cost of supplying power. c. Stronger transmission networks will encourage greater exchanges of capacity and energy. The availability of adequate transmission capacity will lead to an earlier examination of opportunities for the economic transfer of capacity and energy within and among regions. 6. In estimating future loads, full attention should be given to economic trends, potential weather extremes, and growth in special uses of electricity in each load area. Substantial errors can be made in relying too heavily on projections of load growth based primarily on past trends. More attention should be given to the probable growth of individual components of load such as air conditioning and home heating where extended records of past experience are of little signiiicance. 7. Lead times for planning and constructing major new facilities should be selected which will avoid delays in meeting completion 89 schedules and impairment of system reliability. Extensions of as much as one to two years in comparison with past practice may be needed for large components. The added complications of coordinated planning, the time required for certifications by regulatory bodies, the increasing difficulties of acquiring rights-of-way, delays frequently incurred in manufacturing and construction, sometimes caused by labor shortages or labor-management disputes, and the problems in testing new EHV and very large capacity equipment are adding, not months, but years, to lead time requirements. In many cases, it may be necessary to develop relatively firm expansion plans not less than six years in advance of need. 8. Utilities should solicit the participation of interested parties at an early date in the resolution of problems relating to the locat i o n a n d e n v i r o n m e n t a l ejects of new facilities. Utility planning involves many important considerations. In addition to technical factors, careful attention must be given to facility location, the preservation of aesthetic values, the satisfactory control of air pollution and the effects of generating station cooling systems on aquatic environments. 9. Special attention should be paid to transmission line routing, and to switching arrangements at generating centers and at principal interconnections in the transmission network to provide maximum reliability in emergencies. The economic growth of the industry will of necessity require the concentration of large amounts of power at generating centers and the movement of large blocks of power on transmission rights-of-way. Particular care should be taken to avoid excessive concentration of critical circuits, which would expose the system unnecessarily to large loss of capability. 10. The size of generating plants, the magnitude of area loads, and the capability of the transmission system should be kept in good balance. Generating capacity which is too large in relation to the capability of the interconnecting transmission lines and the general concentration of loads in the area can impair the reliability of supply. Transmission capacity usefully can lead but must not lag the growth in loads. 11. Suficient transmission should be provided to avoid excessive generating reserve margins. Limited transmission capacity tends to result in generating reserve margins larger than could otherwise be justified on either economic or reliability considerations. With increased transmission capability and closer coordination in planning, utilities having large reserves should be able to reduce them with confidence to more economic levels. The numerous delays which are being experienced in placing new units in commercial operation may appear to be an element justifying the projection of larger reserves. These delays, however, can be overcome by expanding the lead time for planning and construction to take account of manufacturing schedules and expected problems in siting or related matters. 12. A workable number of control centers should be established in each region. promi econol 14. Utiliti OPPor compl eratio ET puteri withir new ; speed eratin lectio data, are i autor interc econc to m tion netw meet datic sient plani netw mit 1 anal; distu plica speei achit At present, many systems are still controlled individually or in small groups, which impedes coordination and, in severe emergencies, may make it virtually impossible to take the best corrective actions. The 22 systems of the Northeast Coordinating Council are controlled by 12 dispatch offices, six in New England and six in New York. The Northeast power failure dramatically underscored the inability of operators in these many centers to have meaningful communications with each other. Plans are being made in the Northeast to establish two central control points, one in New England and one in New York. This simplification should greatly improve coordination of these systems for both normal and emergency operations. Various were revea utilities thl profit fror completed, ciencies in be correcte 15. Syst 13. Relay protection should be continually up- wit1 dated to fit changing system development and to incorporate improved relay control devices. pro; cleo posj I: Relays are key elements in achieving reliability of bulk power supply. They are relatively inexpensive in the whole scheme of system development. Therefore, adequacy, quality, and readjustment should not be com- Intercom ran; and out con promised for the sake of practically negligible economies. n capacity the growth 14. Utilities should intensify the pursuit of all opportunities to expand the eflective use of computers in power system planning and operation. rovided to e margins. tends to Tins larger on either ions. With and closer es having duce them nit levels. being exommercial n element r reserves. ercome by nning and anufacturns in siting Equipment for relatively complete computerized control of power systems is not within present capabilities. However, many new applications are being found for high speed digital computers in planning and operating utility systems. Among these are collections and print-out of system operating data, including warning of conditions which are approaching or exceeding safe limits; automatic control of generating units in an interconnected network to produce the most economic increment or decrement of power to meet changing loads; increased automation of generating plants; rapid analysis of networks to determine line load limits to meet assumed outages (see also recommendation 17) ; and a wide range of both transient and steady state stability studies for planning additions to the interconnected network. Further progress is needed to permit the reliable use of computers for on-line analysis and control of power systems during disturbances. Computer development and applications have advanced with phenomenal speed and such advancement may be achieved in a relatively few years. !ers should still conups, which rere emerpossible to . The 22 ting Counch offices, Jew York. amatically erators in neaningful Plans are ablish two v England lplification )n of these emergency Interconnected System Operating Practices I Various deficiencies in utility operating practices were revealed by the Northeast failure, and most utilities throughout the Nation have been quick to profit from it. Many remedial actions have been completed, and others are in progress. All deficiencies in the categories enumerated below should be corrected as soon as possible. 15. Systems control centers should be equipped oually uppment and ontrol de- with display and recording equipment which provide the operator at all times with as clear a picture of system conditions as is possible. ving reliar are relascheme of adequacy, ot be com- Desirable displays include narrow and wide range indications of system frequency, tieline and principal transmission line flows, lines out of service, positions of switches, overload conditions, generating units in service, unit and plant outputs, available spinning reserve and current rate of response, voltages and frequency 44 at key points, area control error 4j and appropriate alarms. .16. Communication systems should be supplied with continuously available power in order that information on system conditions can be transmitted correctly to control centers during system disturbances. System data transmitted by equipment supplied with erratic system power during a disturbance will furnish computers and operators with misleading information. Whenever power supply for communications equipment deviates beyond specified limits, the equipment should be automatically and instantaneously switched to an emergency power source. 17. Control centers should be provided with a means for rapid checks on stable and safe capacity limits of system elements. The necessity for isolating a line or substation or dropping a generating unit, either in an emergency or for planned maintenance, can result in major shifts in network power flows. Rapid security checks to determine that various elements will be operated within safe limits under such modified conditions are essential to prevent unsafe loading. Rapid security checks are now feasible through the use of digital computers. 18. Spinning reserves should be able to respond quickly to a level which can be sustained in meeting emergency power demands. The effectiveness of spinning reserve is measured by its rate and level of sustained response rather than the sum of surplus capacities in generating machines connected to the load. Rapid response normally requires that the reserve be distributed among a large number of units. 19. Coordinated programs of automatic load shedding should be established and maintained in areas not so equipped to prevent the total loss of power in an area that has been separated from the main network and is deficient in generation. Load shedding should “In the event of an area separation from the network. “Deviation of an area’s generation from power supply commitments. 91 be regarded as an insurance program, however, and should not be used as a substitute for adequate system design. Strongly interconnected systems should be able to meet emergencies without loss of load. Every utility, however, should have a wellorganized load shedding program as an emergency backup. Since it is not possible to be sure of the boundaries of separation that may occur from a severe disturbance, it is important that systems adopt coordinated programs of load shedding. To fail to do so is to risk imposing inequities among the customers of various systems, creating an imbalance in the flow of supporting power, and reducing the effectiveness of the programs. The effect of these programs should be carefully checked for a variety of unusual loading conditions during an assumed severe disturbance. Where appropriate to a particular area, procedures for automatic generation dropping upon the loss of a principal transmission artery should also be considered. The Commission recommends that all areas have a coordinated program of automatic load’ shedding as an emergency backup to strong interconnections among systems. Automatic load shedding will be much more effective in emergencies than a manual program. Arrangements should provide for shedding load in total amounts at least equal to the largest conceivable loss of power supply in appropriate increments as system frequency declines. A thoughtful selection of loads or load areas for the various increments of load relief is essential. Some revisions in circuits may be needed. Occasional rotation of areas may be helpful. Each utility should, in cooperation with state commissions or other appropriate authorities, establish procedures for informing the public of its load shedding program. 20. Plans should be made and to the extent feasible, tested for the quick isolation of generating units to maintain them in operation if collapse of system power is imminent. Some units can continue to operate under very light loading, supplying power only to their own auxiliaries. Others cannot continue in satisfactory operation when serving loads less than 20 to 30 percent of rated output. 92 Switching procedures must be carefully planned to isolate appropriate units quickly in an emergency. Units maintained in isolated operation will be able to pick up loads rapidly following correction of power failure problems. Smaller units may be isolated primarily to assure that restarting power for larger units in the plant or adjacent plants is available. 21. Emergency power should be auailable at all thermal generating stations to prevent damage to turbo-generators during rundown if system power is lost, and for lighting and control system operation. To prevent damage to units, pressures must be sustained on bearing lubrication and hydrogen sealing systems. Emergency power should be provided to operate the pumps of these systems, to operate turning gear, to keep the control system operable and to provide lighting in the control room and other critical areas. 22. Auxiliary power should be available to the principal thermal generating plants of a system to enable rapid restarting if system power is lost and units are forced to shut down. Power required to drive the auxiliary equipment of a thermal generating station averages 5 to 6 percent of the station’s output. Provision of emergency power for the operation of auxiliaries during plant startup can save hours of time in service restoration if power is lost over a wide area. 23. Thorough programs and schedules for operator training and retraining should be vigorously administered. Many operators become highly skilled in handling the day-to-day problems of system operation, including commonly occurring system disturbances, but more attention should be devoted to rehearsing procedures for meeting severe disturbances from a wide variety of potential contingencies. New technical skills are required in monitoring modern power systems. Special switching requirkments to meet temporary or unusual conditions must be thoroughly checked and rechecked. Close coordination among the planning, operating and maintenance staff, is indispensible. Interconned Practices 24. Program strongl: than re swit lays, cc PlY sys many eratior a rigor are inc 25. Manu, dissem ures i users c Thi dissen bulk 1 on sek 26. The i for te sched opera sor probl’ coord Criteria a 27. Crilz tion, syster gui4ic w: the plan of 01 and I dust] ning . syste sent neig Defense 28. Altk can fails atta ? Interconnected System Maintenance Practices 24. Programs of system maintenance should be strongly directed toward preventive rather than remedial maintenance. Switch gear, transformers, protective relays, communications, emergency power supply systems, supervisory control systems, and many other elements involved, in system operation should be tested and maintained on a rigorous schedule, whether remedial actions are indicated or not. 25. Manufacturers and utilities should promptly disseminate information on troubles or failures of equipment for the information of users of similar equipment. The Federal Power Commission will also disseminate the information reported to it on bulk power outages, and its special reports on selected power interruptions. 26. The isolation of any elements of the system for testing, repair, or replacement should be scheduled by, or receive the clearance of, the operating department. Some of the power failure reports indicate problems resulting from a lack of internal coordination of work plans. Criteria and Standards 27. Criteria and standards for planning, construction, operation, and maintenance of power systems should be formulated for general guidance. With the expansion of electric loads and the interconnection of power systems, the planning, operating and maintenance policies of one system increasingly affect the quality and cost of service of its neighbor. The industry needs minimum standards for planning, construction, and operation so that each system can be reasonably assured that its own service will not be adversely affected by its neighbors’ policies. Defense and Emergency Preparedness 28. Although severe damage to power systems can be inflicted by enemy attack, cascading failures should not follow as a consequence of attack on a strong bulk power system. The steps which we recommend be taken to improve ,the reliability of bulk power supply will also place the utility systems of the United States in a better position to resist widespread failure if subjected to enemy attack. The nation’s utilities are organized and generally have adopted programs of defense readiness by providing emergency supplies, fallout shelters, mobilization procedures, and property protection prescribed by the Defense Electric Power Administration of the Department of the Interior, and the Department of the Army. Utilities generally have security programs which are adequate for normal requirements, but many, with further guidance from defense authorities, should strengthen their preparedness for security control under enemy attack. 29. All levels of government appropriately should establish requirements for emergency power sources for services essential to the safety and welfare of the public, and ensure the availability of such facilities. Precautions should be taken not only against the possibility of a future area-wide power failure, but also the more likely occurrence of local outages such as caused by severe storms. Since the November 1965 power failure, Federal agencies and many state and local governmental bodies have taken steps to lessen the impact of future power interruptions. More than half of the states now require local auxiliary power for certain critical loads. This practice should be extended, under carefully considered criteria to assure essential emergency service while safeguarding against unwarranted duplication of expensive generating facilities. Accordingly, the Commission urges state, county and local government agencies to encourage and direct by legislation, regulation and other means, the planning and installation of needed auxiliary power facilities to provide essential services for the safety and welfare of the public. 30. Utilities should cooperate with appropriate public oficials and customers in planning and maintaining customer standby facilities to assure service to critical loads in the event of emergency. Even though the improvements recommended herein will do much toward preventing further widespread power failures, the 93 possibility of interruptions remains. Localized failures will continue to occur from storms, equipment breakdown and other causes. The complete dependence of many important public services upon electric power requires the appropriate provision of emergency power supplies. These services typically include hospitals, police and fire departments, sewer and water plants, transportation systems and terminals, communications facilities, and emergency lighting and elevator service in public or other multi-story buildings which normally contain many people. Many such facilities in the Northeast were not equipped with emergency power. Others had standby sets that did not operate because they had not been tested and maintained or because informed operators were not available to start them. The Commission urges that utilities and agencies responsible for essential services work together in the proper planning and maintenance of emergency power facilities. Manufacturing and Testing Responsibilities 31. Manufacturing capacity of electrical equipment suppliers should be expanded on a continuing basis to meet future needs. A deficiency in manufacturing capacity can delay production of needed equipment, with detrimental effects on the reliability of bulk power supply. The need for adequate electrical equipment is of such importance that risk of serious shortages must be avoided. The Commission recommends that utilities study the long-range outlook carefully, and that manufacturers take appropriate actions to ensure that sufficient manufacturing capability will be available to allow for timely delivery of equipment. Better dialogues on projected requirements between utilities and manufacturers is needed and -will be aided by improved planning and coordinating procedures suggested in this report. 32. Facilities are needed in the United States for more extensive testing of EHV equipment. Resources for testing major items of electrical equipment are limited primarily to the laboratories of two manufacturers which are not adequate in some respects for subjecting new equipment to tests which fully represent actual service conditions. 94 . The Commission urges the early consideration by the electric utility industry of its future needs for high-voltage testing facilities, the development of plans, the required support by utilities and manufacturers and the early construction of appropriate facilities so that the reliability of future bulk power supplies will not be impaired unnecessarily by lack of proper testing capabilities. Increased Need for Technical Proficiency 33. The industry should take advantage of every opportunity to present to young people tlze full challenge of modern power systems engineering. Shortages of technical talent represent one of the more serious problems facin~g the electric utility industry. The electric utilities have not kept up with competition in attracting technical talent, and the mounting shortage of strong technical staffs poses a threat to the future reliability of the nation’s power supply. Utilities should work more closely with educational institutions to develop and sponsor appropriate research activities, to utilize cooperative work programs for students and industry assignments for educators, and to exploit fully the opportunities for new and sophisticated research and development programs. Power System Practices in Other Countries 34. Power systems in other countries arc experiencing similar problems in the planning and operation of power systems. System clesign and operating practices in other countries arc generally similar to those in the U.S. The practice of exchanging technical information on improvements in power system equipment and operations among other power consuming n a t i o n s s h o u l d b e c o n t i n u e d a n d expandea. The circumstances of the Northeast power failure have alerted power system engineers in every country having a well-developed power supply program. There are no systems abroad which match the scale of interconnection, wide variation in load density and pluralistic composition that exist in the ic United ,C having M however deeply ( portancc power. Actions takf ity of power f: are progressin The Commis strengthened but also to as: be strongly st emergencies, 1 The Comr tention of th of coordinate provide the r that most ef The Corn of the Execl ges tions in t tion of the review of tl Committee Supply and herewith. The Rei cially helpj tailed infor in responst by the Cc pendix A We also R. Acker, ordinatin,g Chairmar Committc Jack K. c. P. Alr Cornmitt their dets We wi report of necessari lectively, :onsideraof its fufacilities, lired sup: and the rcilities so )wer supssarily by diciency : of every aople the stems cn- esent one the elecities have attracting shortage :at to the leer supsely with :nd sponto utilize lents and #, and to new and slopment wntries c cxperiaing and n d,esign Itries arr is. Thea umation pipment consum.ed a n d st power :ngineers eveloped ) systems .nterconlsity and i n the United States. We find among all countries having well-developed electric power systems: however, a common understanding and a deeply concerned appreciation of the importance of reliability in the supply of electric power. 1..h g. Q .x. -Yc Actions taken by utilities to reduce the probability of power failures in the Northeast or elsewhere, are progressing. These must be pursued vigorously. The Commission is concerned that networks be strengthened not only to minimize power failyres, but also to assure that every area of the nation can be strongly supported by adjoining utilities in any emergencies, whatever they may be. The Commission will continue to direct the attention of the industry to the timely development of coordinated procedures and programs which will provide the nation with a bulk power supply system that most effectively incorporates the elements of reliability and economy. The Commission believes that these objectives can best be sought by: 0 stronger coordination mechanisms, 0 comprehensive planning of power resources in each region and among regions, 0 the construction of transmission facilities that will meet the requirements of reliability and economy. Despite the long record of outstanding service that has characterized the supply of electric energy in the United States, the industry is faced squarely with the challenge that much remains to be done if the nation is to have the reliability it requires, deserves and demands. The industry must act, not only to prevent cascading failures, but to assure freedom from the hazards of marginally sufficient power supplies. In some aspects, the improvement process is time consuming and requires careful planning, but with the concerted effort of all, these goals can be achieved before 1975. ACKNOWLEDGMENTS The Commission is greatly indebted to members of the Executive Advisory Committee for their suggestions in the formulation of programs of investigation of the Northeast power failure, and for their review of the report of the Commission’s Advisory Committee on Reliability of Electric Bulk Power Supply and early drafts of the Commission’s report herewith. The Regional Advisory Committees were. especially helpful to the Commission in assembling detailed information on industry practices in reliability in response to the several lines of inquiry suggested by the Commission staff paper included in Appendix A of this report. We also take this opportunity to thank Mr. Ernest Ii. Acker, Chairman of the Northeast Power Coordinating Council and Mr. Philip Sporn, past Chairma; of the Commission’s Executive Advisory Committee, for their special assistance, and Messrs. Jack K. Busby, Chairman, and T. J. Nagel and C. P. Almon, Jr., Vice Chairmen of the Advisory Committee on Reliability of Bulk Power Supply, for their detailed review of this report. We wish to note, however, that Volume I is the report of the Commission and the staff and does not necessarily represent the views individually or collectively, of those we acknowledge here. Members of the Executive Advisory Committee are as follows : EXECUTIVE ADVISORY COMMITTEE Chairman: Lee F. Sillin, Central Hudson Gas & Electric Corporation Members : Thomas G. Ayers, Commonwealth Edison Company David S. Black, Bonneville Power Administration Donald S. Kennedy, Oklahoma Gas & Electric Company A. H. McD0wel1,“~ Virginia Electric & Power Company Ii. J. McMullin, Salt River Project Agricultural Improvement & Power District. Harry L. Oswald, Arkansas Electric Cooperative Corporation S. L. Sibley, Pacific Gas & Electric Company C. H. Whitmore, Iowa-Illinois Gas & Electric Company Harry G. Wiles,47 Kansas Corporation Commission 95 Members of the Regional Advisory Committees are as follows : NORTHEAST REGIONAL ADVISORY COMMITTEE Chairman: Howard J. Cadwell, Western Massachusetts Electric Company Members : Ernest R. Acker, Northeast Power Coordinating Council W. S. Chapin, Power Authority of the State of New York Walter N. Cook, Vermont Electric Cooperative, Inc. T. C. Duncan, Consolidated Edison Company of New York, Inc. William H. Dunham, Central Maine Power Company J. Emerson Harper, Department of the Interior William F. Hyland, New Jersey Board of Public Utility Commissioners F. H. King, Holyoke Municipal Gas & Electric Department M. H. Pratt, Niagara Mohawk Power Corporation Edwin H. Snyder, Public Service Electric & Gas Company Stephen R. Woodzell, Potomac Electric Power Company SOUTHEAST REGIONAL ADVISORY COMMITTEE Chairman: W. B. McGuire, Duke Power Company Members: E. B. Crutchfield, Virginia Electric & Power Company Thomas R. Eller, Jr.,48 North Carolina Utilities Conmiission R. H. Fite, Florida Power & Light Company Shearon Harris, Carolina Power & Light Company Charles W. Leavy, Southeastern Power Administration E. V. Lewis, Central Electric Cooperative, Inc. J. B. Thomason, South Carolina Public Service Authority Alvin W. Vogtle, Jr., The Southern Company James E. Watson, Tennessee Valley Authority A. M. Williams, Sr., South Carolina Electric & Gas Company 96 SOUTH CENTRAL REGIONAL ADVISORY COMMITTEE Chairman: Gordon W. Evans, Kansas Gas and Electric Company Members : C. W. Anthony, Oklahoma Gas & Electric Company W. M. Brewer, Middle South Utilities, Inc. B. B. Hulsey, Texas Electric Service Company Czar D. Langston, Jr., Oklahoma Association of Electric Cooperatives Charles M. Matthews, Greenwood Utilities Frank W. May,4? Missouri Public Service Commission G. E. Richard, Gulf States Utilities Company G. E. Schmitt, Lower Colorado River Authority J. R. Welsh, Southwestern Electric Power Company Douglas G. Wright, Southwestern Power Administration EAST CENTRAL REGIONAL ADVISORY COMMITTEE Chairman: D. Bruce Mansfield, Ohio Edison Company Members : J. H. Campbell, Consumers Power Company John P. Gallagher, Piqua Municipal Power Plant E . L . Lindseth,4’ The Cleveland Electric Illuminating Company Wells T. Lovett, Kentucky Public Service Commission Walter J. Matthews, Public Service Company of Indiana, Inc. F. J. McAlary, Allegheny Power System, Inc. T. J. Nagel, American Electric Power Service Corp. H. L. Spurlock, East Kentucky Rural Electric Cooperative WEST CENTRAL REGIONAL ADVISORY COMMITTEI Chairman: J. W. McAfee, Union Electric Cornpan: Members : G. R. Corey, Commonwealth Edison Cornpan. H. N. Ericksen, Nebraska Public Power Systen E. Ewald, Northern States Power Company J. L. Grahl, Basin Electric Power Cooperative A. Gruhl, Wisconsin Electric Power Compan] D. M. Heskett, Montana-Dakota Utilitie Company George A. Lewi Dick-A. Witt, mission A. Van Wyck, ! W EST REGION‘ Chairman : Frank Electric Compan) Members : Marshall L. B Company P. A. Bland Company J. F. Bonner, I J. J. Bugas, Cc Inc. Howard Elmo of Chelan C Kansas Gas and George A. Lewis, Bureau of Reclamation Dick A. Witt, Iowa State Commerce Commission A. Van Wyck, Illinois Power Company Gas & Electric W EST R E G I O N A L A D V I S O R Y C O M M I T T E E SORY COMMITTEE Ith Utilities, Inc. Service Company homa Association wood Utilities blic Service ComI tilities Company lo River AuthorElectric Power stern Power AdDRY C O M M I T T E E 1, Ohio Edison Power Compaq Iunicipal Power :veland Electric Public Service ervice Company k yer System, Inc. C Power Service Y Rural Electric FRY C O M M I T T E E ectric Company ,dison Company C Power System fer Company rer Cooperative ‘ower Company akota Utilities Chairman : Frank M. Warren, Portland General Electric Company Members : Marshall L. Blair, Washington Water Power Company P. A. Blanchard, Utah Power & Light Company J. F. Bonner, Pacific Gas & Electric Company J. J. Bugas, Colorado Ute Electric Association, Inc. Howard Elmore, Public Utility District No. 1 of Chelan County Bernard Goldhammer, Bonneville Power Administration Frederick B. Holoboff,47 California Public Utilities Commission Emil Lindseth, U.S. Bureau of Reclamation S . B. Nelson,47 Los Angeles Department of Water & Power Robert P. O’Brien, Southern California Edison Company L. R. Patterson, Public Service Company of Colorado D. W.. Reeves, Public Service Company of New Mexico 4G Deceased. ” Indicates members who no longer are active in the associations named and have terminated their participation with their committees. ” Resigned from committee. e APPENDIX A GENERAl. SURVEYS OF THE RELIABILITY CHARACTERISTICS OF U.S. POWER SYSTEMS Introduction The Federal Power Commission, on January 10, 1966, established six Regional Advisory Committees to assist it in updating the National Power Survey alld in compiling important data relating to current practices in the design and operation of electric utility systems throughout the nation. In June 1966, the FPC staff issued criteria for surveys of six areas of design and operation related to the reliability of bulk power supply. The staff paper outlining these criteria follows. Criteria for General Surveys by ,Regional Advisory Committees of Important Power System Design and Operating Practices Relating to Reliability of Bulk Power Supply Surveys of certain practices in system design and operation which have a bearing on the reliability of bulk power supply have been scheduled by the Commission for the early attention of the Regional Advisory Committees. This staff paper enumerates items suggested for the surveys, and general specifications for the scope of the inquiries. Because of the early need for this information, the Commission is asking that the surveys and evaluations by each of the Regional Committees be concluded by September 1, 1966. The several items suggested for investigation are as follows : 1. Surveys of the system design studies relating to stability under severe disturbances. 2. Practices in load and generation reduction under disturbed system operating conditions. 3. Practices in providing spinning reserves, and design and experience data on response of spinning reserve. 4. Provisions for rapid restoration of system service. 5. Practices and plans for use of digital computers as aids or controls in improving system power supply reliability and system stability. 6. A summary of incidents in which a major outage of equipment occurred but there was no service interruption because of support through interconnections. The Regional Committees should summarize each one of these investigations in a separate paper. The information included will also be made available to the Advisory Committee on the Reliability of Bulk Power Supply and to the Executive Advisory Committee. Survey of Sfability Sfudies It is the purpose of this survey to examine the extent to which interconnected systems have analyzed the transient stability of their networks under assumed very severe impacts. To this end, it is suggested that those studies be enumerated and described which are of the greatest magnitude from the standpoint of area of interconnection and severity of imposed disturbing conditions. It is presumed, for example, that in each region studies may have been made for three or four areas within the region or possibly for the entire region and that such events as a total generating plant or a major corridor of transmission or a principal substation .has been assumed to be interrupted. If studies of this magnitude have not been made, it would be .helpful to have a description of those studies which most nearly approach this scale of examination. It is not intended that the survey encompass a listing or description of the many steady state and transient analyses which simulate normal steady state operation or which test transient conditions of a more routine nature. Information can be supplied in whatever narrative, tabular or other form is convenient and understandable. However, it will be useful to have a designation of the group of utilities, the pool, or other coordinating organization or entity responsible for the 99 studies, a discussion of the types of incidents selected, whether the studies embrace current or include future loading system conditions and an appraisal of the effects of the assumed incidents on system performance. Practices for Emergency Load and Generation Reduction The scope of this survey includes practices in load reduction under disturbed system conditions, either through programs of manual or automatic load tripping or through manual or automatic voltage reduction; and any procedures for automatic disconnection of generators simultaneous with major loss of load. The survey reports could be made by coordinated systems or pools insofar as the coordinated group employs common practices. For each utility, system, or group surveyed in the region, the following information is desired : a. Description of any emergency load reduction program, including percentage of load shedding at various levels of frequency or other methods of defining amounts of and corresponding conditions for load reduction as appropriate. b. Practices and policies in maintaining or opening interconnections between utilities operating at abnormal frequencies following isolation of the group from the interconnected network. If policies are not defined, this should be so stated. c. Applications of automatic generator tjpping concurrent with major loss of load. d. Number of different occasions when load shedding was utilized during 1965 by the utility or group reporting. e. How completely does this survey cover the individual utilities in your region? (List individual entities covered by survey.) Practices in Spinning Reserve Spinning reserve is the capacity of generating equipment-connected to the load which is in excess of the load being carried. The intent of this survey is to obtain information on general practices among utilities, or coordinating groups where uniform practices are in effect, in planning spinning reserve. Each system or group of systems normally is composed of a variety of types of generating facilities, some of which are loaded partially and some fully. The response can be in narrative form using tabulations if helpful, indicating the entity for which the 100 analysis is presented, the general composition of generation, the variation in loading, the rate of response under emergency conditions in terms of actual experience, or if not available, in terms of estimated performance. Information is also desired on the change in system output that would occur with a 0.1 cycle per second change in frequency, based on normal load distribution, and plant operating practice; and the time required for the system or group of systems to pick up ten percent of its rated maximum capacity. If interruptible loads are included as a part of the “spinning reserve” allowance, what are the procedures and what is the time required for effecting interruption? What are the typical practices in distributing spinning reserve among units? What reliance is placed upon interconnections with other systems, upon spinning reserve held in the largest generating unit of the system or other criteria? Is quick-starting capacity which is not actually on the line relied upon as a part of spinning reserve? Restoration of System Service It is recognized that practices for rapid restoration of service in the event of a total loss of system power or when such loss of system power is imminent vary widely among systems depending upon individual circumstances. Some utilities rely upon their interconnections with other systems for the supply of emergency restarting power. Others rely upon hydroelectric plants within their own systems from which power can be transmitted to stations in need of startup assistance. Still others have made provisions at their steam stations for quick-starting sources of power, such as diesel or gas turbines, which can be used for operating station auxiliaries. It would be helpful in responding to this survey to receive narrative reports from principal systems or groups of systems or pools which have established a consistent practice, which present specific information on the provisions made and an evaluation of the effectiveness of these provisions for the area should a widespread power failure occur in the area. Practices and Plans for Use of Digital Computers Most digital computer applications today are thought to be in the areas of load flow analysis, transient stability studies, and economic dispatch. However, at least some thought has been given to the possibilities of using digital computers on a realtime basis for consolidation or coordination of current information on system conditions so that oper- ators may takr for system secu elements of the reliability of p would seek out along the lines developed plan they may not E year or so. Interrtiptions 1 This is inter of important si past three to f have played a interruption. A currence in eat be of significal must be approl nections utilize example, to inI loss of a genera tern carrying a though some 01 the interconnec system would h without intercc Descriptions in sufficient infon indicate the i interconnectior The results visory Commit for investigatic sections. Infon interruptions a port appears in General Sur a. Survey of S The problen tern has been r rent generators 1 composition of ~g, the rate of reons in terms of ble, in terms of esbn is also desired that would occur 1ge in frequency, > and plant operuired for the systen percent of its ruptible loads are lg reserve” allow1 what is the time n? What are the spinning reserve laced upon interlpon spinning re~g unit of the sysstarting capacity relied upon as a Service for rapid restorajtal loss of system rower is imminent nding upon indies rely upon their ns for the supply Others rely upon )wn systems from o stations in need iave made provi:k-starting sources rbines, which can iaries. It would be ey to receive narems or groups of lished a consistent lformation on the n of the effectivcea should a widerea. igital Computers ators may take quicker or more effective action, for system security checking, or even for actuating elements of the system in such a way as to increase reliability of power supply. The survey proposed would seek out and describe any such applications along the lines of the second group, and any well developed plans for such applications, even though they may not be expected to be in operation for a year or so. Interru’ptions Avoided Through Interconnected Support This is intended to be a comprehensive survey of important situations which have occurred in the past three to five years in which interconnections have played a major role in preventing a service interruption. A short description of each such occurrence in each region would be appropriate. To be of significance, the magnitude of the incident must be appropriate to the strength of the interconnections utilized. It would not be impressive, for example, to include an incident that involved the loss of a generating unit of 100 megawatts on a system carrying a total load of 3,000 megawatts, even though some of the support would have come from the interconnections. Outage incidents in which the system would have been adequate to absorb the loss without interconnections should not be included. Descriptions in great detail are not intended but sufficient information should be included to clearly indicate the importance of the part played by interconnections. The results of the surveys by the Regional Advisory Committees of the first five items suggested for investigation are summarized in the following sections. Information pertaining to the survey of interruptions avoided through interconnection support appears in chapter 3 of this report. General Surveys a. Survey of Stability Studies The problem of stable operation of a power system has been recognized ever since alternating current generators have been operated in parallel, and has been under continuous study by power system engineers since the beginning of the industry. A technical discussion of power system stability is contained in Appendix B of Volume II, Advisory Committee Report on Reliability of Bulk Power SUPPlY* Longhand calculations to determine the effects of most changes in a complex electric system are SO tedious and time consuming as to be virtually impossible. Network analyzers were generally used for many years, but the advent of the large-scale, highspeed digital computer within about the last ten years has provided a better means of making studies of large electric systems. Since the Northeast power failure, most stability studies have considered somewhat more severe conditions, and have examined more extensive areas, than in the past. Also, power networks in virtually all areas of the country have been examined for expected performance during severe disturbances. Most of the stability studies reported in the surveys indicated that the systems were stable for the loss of a large generating plant or a major transmission line. However, if the study were carried further to include the loss of a second line, generally the result was further cascading of lines and the isolation of areas. In some instances, there are needs for more comprehensive studies, encompassing larger geographical areas and time periods farther into the future, than those which have been used in the past. Furthermore, the length of the interval for detailed analysis following initiation of a disturbance is being increased by the study groups in some areas, and others may profit by analyzing system performance for longer periods than the first swing cycle used in most studies in the past. The following tabulation lists the major stability studies reported in each of the Federal Power Commission’s six regional study areas. Included in this tabulation are the systems involved in each study, the purpose of the study, the conditions examined, and the conclusions reached. .ations today are Iad flow analysis, :onomic dispatch. has been given to nputers on a realordination of curtions so that oper101 TABLE A-l .-Stabili~ Studies NORTHEAST Sponsor of Study Northeast Interconnected System Studies Group. 1966 Peak Load IMW !9, ooo argest Jnit in ervice 1966 iecond argest I Jnit in Liervice 1966 -- l,ooo 400 Eastern New York-New England Systems Study Group. NPCC Task Force on System Studies. argest Jnit in ;ervice 1970 ,argest Jnit in lervice 1970 Principal Transmission Voltage in Service 1966 I Principal Transmission Voltage in Service 1970 295 Utilities C I 345-230 500-345-230 1,169 345-230 500-345-230 1,069 345-230 500-345-230 640 230-138 500-230 I Allegheny Power System and General Public Utility Systern. REGION CANUSE Syst , CANUSE Syst CANUSE Syst 4 Allegheny Pov General Public I 500-345-230 I 400 Pennsylvania-New JerseyMaryland Power Pool. 363 , 363 865 865 230 500-230 AEP-APS-VEPCO-PJM. . . . 58C 57c 865 865 345-230-138 765-500-345 ESURPA-PJM-APS. . 13,600 345-230 Utilities in N.’ Penna-NJ-Md Allegheny Pou I Penna-NJ-M1 American Elt Allegheny PO Virginia Elec Penna-NJ-M 267-7 1 .-Stability Studies <THEAST REGION II TransVoltage ice 1970 - Utilities Covered by Study Purpose of Study Conditions Studied and Conclusions Simulate sequence of events during the early period of the Northeast blackout. Simulate sequence of events to final shutdown of the “island.” To study cases of instability developed in Northeast Interconnected System Studies Group with generation and transmission additions to 1968. Study made by General Electric Company with APS and GPU to determine whether or not the systems would be stable for the loss of a large generator under realistic operating conditions. To determine the problems that result from the loss of Consolidated Edison’s Ravenswood #3-1000 Mw generating unit. Discussed further in report. See Volume III. - -345-230 CANUSE Systems. . . . . . . . . . . . . . . . -345-230 CANUSE Systems.. . . . . . . . . . . . . . . -345-230 CANUSE Systems. . . . . . . . . . . . . . . . 500-230 Allegheny Power System. . . . . . General Public Utility System. . . -345-230 Utilities in N.Y. State.. . . Penna-NJ-Md Pool. Allegheny Power System. . . 500-230 Penna-NJ-Md Power Pool. . . . . 500-345 American Electric Power System Allegheny Power System. Virginia Electric & Power Co. Penna-NJ-Md Pool. 267-7810-67--s To study the transient stability of the PJM 500-Kv system which includes Keystone (1800 Mw) and Muddy Run (800 Mw) plants. To investigate the region for possible stability problems for loss of any transmission on same right-of-way, major substation, or generating station. Discussed further in report. See Volume III. Discussed further in report. See Volume III. The study made in 1963 found no operating difliculties. Studies made in 1965 and 1966 indicated the necessity of operating the unit at less than full load until additional transmission already under construction was installed. This study covered three-phase, two-phase, and single-phase faults at critical locations on the Keystone 500-Kv system for 1968. It includes an evaluation of the swing problems that occur on the underlying 230-Kv network as a result of swings of the Keystone generators. The system was found to be stable for threephase faults with normal clearing and for single-phase faults with delayed clearings. This study of the 1968-72 period includes both transient stability and post-transient load flow runs during the build-up of generation at Keystone (1809 mw), Homer City (1309 mw), and Conemaugh (1609 mw) in PJM, atPort Martin (1000 mw) in APS, and Mt. Storm (1140 mw) in VEPCO. 103 . TABLE A-l .--Sfabik SOUTHEAS’ Largesi Unit ir Service 1966 400 Seconc Larges Unit ir Service 1966 40( Large Unit Servi 1971 7: Secant d Largerrt Unit i n Servics e 1970 531 3 Studies-Continued Principal Transmission Voltage in Service 1966 Principal Transmission Voltage in Service 1970 23t 236 REGION Utilities Cove Florida Power Car Florida Power & City of Jacksonvil City of Orlando. Tampa Electric C c Southern Services, Inc. . . . . . 27f 27C 544 544 230 230 Alabama Powa Georgia Power Gulf Power Co Mississippi POW Southern Elect TABLE A-I.-Stabi& SOUTHEAST lal Trans1 Voltage rice 1966 23G 230 Principal Transmission Voltage in Service 1970 230 230 Studies--Continued REGION Utilities Covered by Study Purpose of Study Florida Power Corp.. . . . . . . . . . . . Florida Power & Light Co. City of Jacksonville. City of Orlando. Tampa Electric Company. To assure that the transient stability problems associated with the loss of large generating units will not adversely alTect service. Alabama Power Co.. . . . . . . . . . . . . Georgia Power Co. Gulf Power Company. Mississippi Power Co. Southern Electric Generating Co. Transient stability studies are made routinely for planned generating unit additions. Conditions Studied and Conclusions I. Studies for the winter of 1964-65 and 1965-66 considered single contingencies of an outage of the largest generating unit. It was concluded that the peninsula of Florida would not have transient stability problems due to the sudden loss of the largest unit in major load areas. 2. Studies for the winter of 1967-68 are being conducted to determine the worst outage incident that can be feasibly planned for. Examples of incidents to be studied are: (1) Lo3: of largest generating unit within the peninsula of Florida. (2) Simultaneous loss of the two largest generating units within the peninsula of Florida. (3) Loss of the largest generating plant in the peninsula of Florida. It has not been agreed that items (2) or (3) above should be considered as conditions which have to be met. The results of this study will provide a guide in evaluating the seriousness of such events. The utilities in Florida are acutely aware of the need for continuing studies of transiert stability problems, and have implemented procedures for jointly reviewing future transient stability. 1. After the size and location of a new generating unit has been determined, its proposed transmission is tested by transient stability studies to examine the adequacy of the transmission system, and for the selection of circuit breakers and protective relaying arrangements. It is assumed that a three-phase fault will occur on the most critical line at the generating station being tested. Stability is assured for normal relay operation and also in the event that backup relays must substitute for the primary relaying, which increases the fault clearing time. Problems usually occur when a new plant is being added, these problems becoming less severe as additional generation and transmission are added in the future. 105 T ABLE A-l .-Stabit SOUTHEA! Sponsor of Study Southern Largest Unit in Service 1966 Second Largest Unit in Service 1966 41,400 650 650 Largest Unit in Service 1970 Second Largest Unit in Service 1970 Principal Transmission Voltage in Service 1966 Principal Trans. mission Volta e in Service 19 5 0 LEGION Utilities Co? Services-Continued Tennessee Valley Authority and South Central Electric Companies. 106 1966 Peak Load in MW :ludics--Continued 1, 150 161-115 500-16 Arkansas Pow{ Central Louisi Inc. Empire Distric Gulf States U1 Kansas Gas & Louisiana Pov Mississippi PO TABLE A-l .-Stabil SOUTHEAS Principal Transmission Volta e in Service 19 7 0 500-161 Studies-Continued REGION Utilities Covered by Study Arkansas Power & Light Co.. . Central Louisiana Electric Company, Inc. Empire District Elec. Co. Gulf States Utilities Co. Kansas Gas & Electric Co. Louisiana Power & Light Co. Miippi Power & Light Co. Purpose of Study Planning the EHV transmission system for the SCEC-TVA tenyear interchange agreement to exchange 1500 mw of seasonal power. Conditions Studied and Conclusions !. When making transient stability studies, Southern Services records the transient currents and voltages as viewed by protective relays on unfaulted lines. This facilitates determining whether the apparent impedances resulting from those currents and voltages would cause opening of circuit .breakers on lines other than the faulted line and thus initiate a cascading interruption. In some instances, studies showed that usual relay applications and settings would be susceptible to the currents and voltages occurring on unfaulted lines immediately after clearing of the faulted line. Such studies resulted in relay application and settings to minimize undesired openings. 3. Where a large portion of the interconnected system must be set up, load flow studies with phase angle readings provide a good approximate indication of stability. 4. The severity of criteria established for stability of a plant will depend partly upon whether the system can withstand the loss of that entire plant without causing opening of other ties and thus the “cascade” opening of interconnections. While the loss of an entire plant is extremely rare, a circuit breaker may fail to open when tripped by protective relays, either due to mechanical or electrical defects, or inability to interrupt the short circuit. Local backup protection is usually provided to guard against this condition by opening another breaker, but the plant will then be exposed to the short circuit for two or three times the usual clearing interval. If the fault involves all three phases and is on a critical line at the plant, then special expedients may be required to assure stability. Problems of this type are being studied in connection with planned 1969 generating unit additions. In 1962 a number of load flow studies were made followed in 1963 by cases run to investigate transient stability conditions on the then anticipated 1968 system. Additional load flow studies and transient stability cases were run in 1964 through 1966 to update the 1968 system and to investigate the 1968 conditions. 107 TABLE A-l .-Stabildy SOUTHEAST Sponsor of Study 1966 Peak Load in MW Larges Unit il Service 1966 Seconc Lzugea Unit ir SeNiCf 1966 Largesl Unit ir Service 1970 Largesl Unit ir Service 1970 Principal Transmission Voltage in Service 1966 Principal Transmission Voltage in Service 1970 ., REGION Utilities Cc Tennessee Valley Authority and South Central Electric Companies-Continued Tennessee Valley Authority and American Electric Pow System. Studies-Continue{ New Orleans Pu Oklahoma Gas Public Service C Southwest Elect] Tennessee Valle: Southern Comp: Illinois Missouri Missouri-Kansas Southwestern PC 21,100 6 X 65C 1, 150 1,150 345-161-138 765-500-345 . Tennessee Valle American Elect1 500 Virginia Electril ,_ -.,, : . Virginia Electric & Powa Company. 3,300 570 570 694 570 230-l 15 1 , CAFWA Pool (CarolinasVirginia). 10,500 570 570 694 650 230-l 15 500-230 VEPCO-AEP-APS-PJM . 10,400 580 570 865 865 345-230-138 765-500-345 108 Virginia Electr Duke Power Cc Carolina Powel South Carolina Company. Virginia Elect1 Allegheny Pow American Elec Pennsylvania-b Pool. LE A-l .-Stability SOUTHEAST ‘rincipal Transa&ion Voltage In Service 1970 Studies-Continued REGION Utilities Covered by Study Purpose of Study New Orleans Public Service Co. Oklahoma Gas & Electric Co. Public Service Co. of Oklahoma. Southwest Electric Power Co. Tennessee Valley Authority. Southern Company System. Illinois Missouri Pool. Missouri-Kansas Pool. Southwestern Power Administration. 765-500-345 . Tennessee Valley Authority.. . . . . . . . American Electric Power System. To determine present performance and the desirability of additiona EHV extensions. 500 Virginia Electric .& Power Co. . Planning their 500 kv system. . . . Virginia Electric & Power Co. . . Duke Power Company. Carolina Power & Light Co. South Carolina Electric & Gas Company. Virginia Electric & Power Co . . Allegheny Power System. American Electric Power System. Pennsylvania-New Jersey-Maryland Pool. Planning a combined transmission system which will permit integration of production facilities. 500-230 765-500-345 Preparatory to the development of 3451500 kv transmission facilities Conditions Studied and Conclusions These studies were required because of the addition of very large generators connected directly to the 500 Kv system and to determine the timing and location of interconnections to the system. A great majority of the cases studied assumed three-phase faults with unsuccessful reclcsing. A few were made with phase-to-phase or phase-to-ground faults. . These are joint studies in which a greater part of the Eastern United States is represented. They are load flow studies for the 1969-70 conditions but include various emergency conditions such as loss of major lines, large generating units or both. Also cases have been run with the sudden loss of a plant or large generating unit, with the lost generation being picked up by the various systems proportional to their inert&. . Stability was investigated for two phaseto-ground faults at several locations on the 500 kv loop with normal high speed relaying time and combinations of successful and unsuccessful high speed reclosing. These studies showed that there was a possibility of instability if high speed reclosing was used and a permanent fault existed. This condition is being corrected by omitting high speed reclosing until a 500 kv tie with Appalachian Power Co. is completed. Either the 500 kv tie to Appalachian Power scheduled for late 1966 or the 500 kv tie with Allegheny Power scheduled for 1967 would eliminate this problem. Load flow studies have been made with the outage of the two largest generating units on the system. Stability studies will be made for the years 1968, 1969, 1970 and 1972. Load flow studies involving major outages on the EHV system for the years 1968, 1970 and 1972, have been made. Outages such as loss of all lines on a common right of way, loss of complete switching station or loss of all units in a plant were considered. Stability cases for three phase faults with normal high speed relaying and single phase-to-ground faults with stuck breakers will be studied for cases that appear critical in load flow studies. 109 TABLE A-l .-Stability 1966 Peak Load ilnMW Sponsor of Study Cincinnati-Columbus-Dayton Group. - EAST - 1zugest 1Unit in <service 1966 -- second ,argest Jnit in krvice 1966 I argest IJnit in E iervice 1970 - - iecond .argest Jnit in iervice 1970 Principal Transmission Voltage in Service 1966 Principal Transmission Voltage in Service 1970 cEF$-I’RAL REG: Utilities Co 9, 700 580 475 800 800 345-138 765-345-138 American Electri Cincinnati Gas ( Columbus & So1 co. Dayton Power 8 4 l4,ooo 580 475 865 865 345-138 765-500-345 American Elcctr Detroit Edison C Consumers Powc Northern Indian Toledo Edison f Cleveland Elect] Ohio Edison Co Penna-New Jers Niagara Mohavl Hydro Electric Ontario. Power Author? PJM-APS-VEPCO-AEP Systems. 30,400 580 570 865 865 345-23w138 765-500-345 American Elect Allegheny Powe Penn-New Jersc Virginia Electri AEP-CARVA-APS Systems. . . 19,800 580 570 800 800 345-230-138-115 CAPCO (Central Area Power Coordination Group). 15,900 580 475 800 800 345-138 Michigan-Illinois-Indiana-Ohio Group. 765-500-345-230 American El& Allegheny POW{ Carolina Power South Carolina Duke Power Cc Virginia Electr 765-345-138 3 MAIN (Mid-America Interpoc 11 Network). 24,300 580 580 I 715 715 345-l 38 765-345-138 Appalachian P The Cleveland co. Duquesne Ligl Indiana & Mi Monongahela Ohio Edison C Ohio Power C Pennsylvania 1 The Potomac The Toledo E West Penn Po American Ela Commonwcah Illinois-Missor Central I1 Illinois Pa Union Elc Indiana Powe Indianapc Public Se TABLE A-l .-Stability EAST 3e 5 Principal Transmission Voltage in Service 1970 CENTRAL REGION Utilities Covered by Study Purpose of Study 765-345-138 American Electric Power Systems.. . Cincinnati Gas & Elcc. Co. Columbus & Southern Ohio Electric co. Dayton Power & Light Co. Made necessary by the projection of generation and 345-Kv transmission. 765-500-345 American Electric Power Systems.. . Detroit Edison Co. Consumers Power Co. Northern Indiana Public Service Co. Toledo Edison Co. Cleveland Electric Illuminating Co. Ohio Ediion Co. Pcnna-New Jersey-Maryland Pool. Niagara Mohawk Power Corp. Hydro Electric Power Comm. of Ontario. Power Authority State of New York. Made necessary by the projected Michigan 345-Kv interconnections, embracing the entire Northeast-East Central loop (Ontario; N.Y., PJM, Michigan and Ohio-Indiana systems.) American Electric Power Systems. . . Allegheny Power System. Penn-New Jersey-Maryland Pool. Virginia Electric & Power Co. Made necessary by development of large blocks of generation in the Eastern Ohio-West Virginia Panhandle-Western Pennsylvania areas. Preparatory to the development of their 345/500-Kv transmission facilities. 765-500-345 765-500-345-230 765-34%138 765-345-138 American Electric Power Systems.. . Allegheny Power System. Carolina Power & Light Co. South Carolina Electric & Gas Co. Duke Power Company. Virginia Electric & Power Co. Appalachian Power Co.. . . . The Cleveland Electric Illuminating co. Duquesne Light Co. Indiana & Michigan Electric Co. Monongahela Power Co. Ohio Edison Co. Ohio Power co. Pennsylvania Power Co. The Potomac Edison Co. The Toledo Edison Co. West Penn Power Co. To determine the effects of the most severe incidents on the participants’ systems. American Elec. Power System.. . . . . Commonwealth Edison System. Illids-Missouri Pool: Central Illinois Public Service. Illinois Power Co. Union Electric Co. Indiana Power Pool: Indianapolis Power & Light Co. Public Service Co. of Indiana. To determine the effects of the most severe incidents on the participants’ system, embracing an area including Missouri, Iowa, Minnesota, Wisconsin, Illinois and eastward to include all of AEP. Conditions Studied and Conclusions Extensive load flow and stability studies are an essential part of planning and operating procedures. Comprehensive studies are carried out whenever new internal or interconnection facilities are installed or whenever deemed necessary by changes and additions in facilities on external systems or by major changes in system operating conditions and practices. Most studies included outages of complete major power plants and associated transmission, outages of multiple transmission lines on same right-of-way or transmission corridor, and outage of major transmission substations or switching stations. The studies indicated that about half of the systems would have no system-wide disruption and no load interruption. As a result of all the studies, over half of the systems reported they would have local load interruption. The loss of load, however, is not the result of instability, but is simply due to the removal of the source line or substation. As a result of all of the studies, one utility reported at least two severe conditions studied resulted in a major part of the system being disrupted with a loss of a major part of the load but with minor effects on the interconnection. Also, two systems reported transient instability which resulted in separation of the system from the interconnection. It was reported that new interconnections being constructed and planned will limit the disturbances to the loss of certain local loads. 111 - 1966 Peak Load iin MW Sponsor of Study 1Largest 1Unit in ‘service 1966 kcond ,argest Jnit in ,argest Jnit in Service 1970 Second Largest Unit in SeNice 1970 Principal Transmission Voltage in Service 1966 T ABLE A-l.--Stobili Stud&-C0ntinufk EAS CENTRAL REG Principal Transmission Volt in Service 19 “$0 Utilities Cc -- - - WiscOnSin Plant Madison Ga Wiionsin E Wisconsin-h wiinsin P Wisconsin P AEP-TVA-Kentucky Systems. 22, ooo 650 650 1, 150 345-161-138 765-500-341 American Elect3 Tcnnessce Valle Kentucky Utilit Owcnsboro (Ky OVEC..................... 16,000 580 475 800 345-138 765-345-X% American Elect The Cincinnati Columbus and ElectTic co. Dayton Power Kentucky Utili kmiwille Gas i West Penn Pov Ohio Edison C Southern India The Toledo EC - South Cential Electric Companies and Tennessee Valley Authority. 27,800 - - - - 650 - 650 SOUTH CENTRA - 1, 150 1, 150 161-l 15 500-16’ REGION - Arkansas Pow1 Central Louisi Empire Distric Gulf States UI Kansas Gas & Louisiana Pov Mississippi PO New Orleans Oklahoma G: Public Service Southwestern Kansas City I Southwestern Tenneseeva LB A-l .--Stabif~ EAST ‘rincipal Transnission Voltage n Service 1970 Wits-Continued CENTRAL REGION Utilities Covered by Study Purpose of Study Conditions Studied and Conclusions Wiinsin Planning Group: Madison Gas & Electric Co. Wiionsin Elec. Power Co. wisconsin-Michigan Power co. Wiiin Power & Light Co. Wisconsin Public Service Corp. 765-500-345 American Electric Power System. . . . . Texmcssee Valley Authority. Kentucky Utilities Co. Gwensboro (KY.) Municipal Utilities. To determine present performance and the desirability of additional EHV extensions. 765-345-138 American Electric Power System. . . . . The Cincirmati Gas & Electric Co. Columbus and Southern Ohio F4lectric co. Dayton Power & Light Co. Kentucky Utilities Co. Louisville Gas and Electric Co. west Penn Power Co. Ohio Edison Co. Southern Indiana Gas & Electric Co. The Toledo Edison Co. For the initial design to serve the AEC load and the subsequent AEC load curtailment. _. REGION 500-161 Arkansas Power& Light Co. . . . . Central Louiiana Electric Co., Inc. Empire District Electric Co. Gulf States Utilities Co. Kansas Gas & Electric Co. Louiiana Power & Light Co. Mississippi Power & Light Co. New Orleans Public Service Co. Oklahoma Gas & Electric Co. Public Service Co. of Oklahoma Southwestern Electric Power Co. Kansas City Power Co. Southwestern Power Administration Temiessee Valley Authority. To finalize the EHV transmission system for the SCEC-TVA tenyear interchange agreement to exchange 1500 Mw of seasonal power. EHV line loadings were analyzed from normal and emergency load flow studies. System operation was reproduced for three-phase faults with SCEC breaker operation to open at six cycles, reclose at 30 cycles and reopen at 36 cycles for sustained fault conditions. For several TVA system faults, 4.5 cycle clearing was used. Special studies were performed to observe the effects of critical HV line trip-out following an EHV fault and the interruption of a large generator prior to an EHV disturbance. Studies made in 1961 and 1962 were for design purposes. Updated studies were made in 1965 and 1966 to determine safe operating procedures for the current year and to observe any critical areas that may exist in future years. 113 TABLE A-l .-Stabil$ SOUTH CENTRAL Sponsor of Study 1966 Peak ,oad IMW zriz ervice 1966 econd arg=t lnit in ervice 1966 arg-t [nit in ervice 1970 iFEz ervice 1970 MOKAN Pool. . . . . . . . . . . . Principal Trammission Voltage in Service 1970 138 Texas Utilities Company system. South Texas Intcrconncctcd systems. principal Transmission Voltage in Service 1966 5, 700 275 27: 565 565 &d&s--Continued REGION Utilities Covl Dallas Power & Li Texas Power & Li Texas Electric Ser 138 345-131 Houston Lighti] Central Power City Public Ser San Antonio, City of Austin 1 Lower Colorad 161-138 345-161-131 Kansas Gas & Kansas Power Kansas City PC Missouri Publi Empire Distric Union Electric Southwestern : Associated Ele TABLE A-l .--stab& SOUTH CENTRAI Principal Transmission Voltage in Service 1970 Stud&s-Continued REGION Utilities Covered by Study Purpose of Study 345-13l Dallas Power& Light Co.. . . . . . . Texas Power & Light Co. Texas Electric Service Co. The companies making up the Texas Utilities Company system have been conducting and participating in stability studies for several years. When major system changes are contemplated, such as a new generating unit or plant or a major transmission addition, stability studies are made to determine how the addition will affect the system. 345-138 Houston Lighting & Power Co. . . . Central Power & Light Co. City Public Service Board San Antonio, Texas. City of Austin Electric Dept. Lower Colorado River Authority. The most severe impact possible will be imposed on each of the individual systems and an analysis made of the recovery or nonrecovery from these impacts on the entire interconnected systems. 345-161-138 Kansas Gas & Electric Co.. . . . Kansas Power & Light Co. Kansas City Power & Light Co. Missouri Public Service Co. Empire District Electric Co. Union Electric Co. Southwestern Power Adm. Associated Electric Coop. To study the effects of a 345-Kv transmission line between Wichita, Topeka and Kansas City scheduled for service in 1967. The line will be used initially to transfer 200 Mw from Wichita to Kansas City. Conditions Studied and Conclusions n 1963 this system jointly with Houston Lighting & Power Company cr-npleted a stability study to determine the stabilizing effect of a 345-Kv interconnection from Houston to Dallas-Ft. Worth area. Studies confirmed that the 345-Kv line would provide a highly reliable channel for transfer of emergency power between the areas. The most recent stability study was for the 1966 peak load conditions and the light load season of winter 1966-67. Included among the conditions studied were single phase-to-ground faults, double line-toground faults, three-phase faults, simultaneous faults on double circuit lines, single and double bus faults, loss of entire generating plants, and breaker failure in conjunction with line and bus faults. Scheduled maintenance and construction schedules were considered in setting up conditions. Some of these studies indicated loss of local load, low voltages in local areas, separation of areas, but the remainder of the system was stable. 4 normal steady state load flow and an emergency steady state load flow have been completed. The transient stability studies were to be completed in August. In these studies the most severe impact possible will be imposed on each of the individual systems. I’ransient stability studies were run in 1964 and 1965 to de&mine the stability of the systems involved during loss of sections of the 345-Kv line and/or major generating units. A series of stability studies are being run to determine the effect of prolonged fault condition? in the event a breaker should fail to operate properly. It is felt that these conditions represent the most severe disturbances which might be encountered in the operation of the 345-Kv line. Some members of thii group are also members of the South Central Electric Companies and participated in the SCECTVA studies mentioned above. All transient stability studies which have been run indicate the systems are stable. 115 TABLE A-l .-Stabili Studies-Continue? SOUTH CENTRP 1966 Peak Load in MW Sponsor of Study Largest Unit in Service 1966 Second Largest Unit in Service 1966 358 275 - Missouri Public Service Co. Largest Unit in Service 1970 Second Largest Unit in Service 1970 Principal Transmission Voltage in Service 1966 161 REGION Principal Transmission Voltage in Service 1970 Utilities Cc 345-16! Missouri Public Union Electric ( Kansas City PO\ W E S T CENTRA MAIN. . . . , . . . . . . . . . . . . . . . . !24,300 580 345-138 REGION 765-345-l 3t I 116 American Elecl Commonwealtl Illinois-Missoul Central Ill. Illinois Pot Union Elec Indiana Powa Indianapol Public Ser Wisconsin Pliu Madison C WiiOMh Wisconsin, Wisconsin Wisconsin A-l .-Stability ‘II CENTRAL cipal Translion Voltage iervice 1970 Studies-Continued I REGION Utilities Covered by Study Conditions Studied and Conclusions Purpose of Study -Missouri Public Service Co. . . . . . . . Union Electric Co. Kansas City Power St Light Co. T CENTRAL REGION 765-345-l 38 American Electric Power System. . . . Commonwealth Edison System. Illinois-Missouri Pool: Central Ill. Public Service. Illinois Power Co. Union Electric Co. Indiana Power Pool : Indianapolis Power & Light Co. Public Service Co. of Ind. Wiionsin Planning Group: Madison Gas & Electric Co. Wisconsin Electric Power Co. Wisconsin-Michigan Power Co. Wisconsin Power & Light Co. Wisconsin Public Service Corp. Have under construction a 400 Mw generating unit and a 345-Kv interconnection. 1verall performance of the MAIN grid on a routine and continuing basis. The initial study is based on 1968 conditions before Missouri Public Service Company will have its 345-Kv interconnection. The study will be continued into 1969 when the interconnection is completed. The study will include the loss of each major unit of the three companies and numerous transmission line switching operations. The most severe contingency to be studied is that all transmission lines on a common right-of-way will be lost. This is considered a possibility because of tornado activity. A study was completed for 1966 conditions. Studies are in progress for 1968, 1970, and 1973 conditions. The 1966 study included investigations of system integrity for very severe disturbances at various locations throughout the MAIN system that were considered to be the most critical from the point of view of concentrated generation andjor transmission capacity. In three cases investigated, it was found that overall integrity of the MAIN system is maintained and there would be no cascade tripping of transmission lines. In one case, it was assumed that all four bus sections at the Meramec station would somehow be subject to the electrical equivalent of simultaneous and permanent three-phase faults. This would result in the loss of all transmission circuits and 872 Mw of generation. The studies of transient performance for thii case indicated cascade tripping of kansmission lines to ultimate isolation of the Southern portion of the Illinois-Missouri Pool, leaving the area with a capacity deficiency that would actuate its emergency load reduction program. The EHV line under construction will provide increased capacity to the IllinoisMissouri Pool. Under future system conditions this diiturbance at Meramec should not cause cascade tripping of lines and service outage would be limited to loads supplied from Meramec. TABLE A-l .-Stabilii - Sponsor of Study USBR-MBSG . . . . . . . . . . . . WEST CENTRAI - 1966 Peak Load IMW argest lnit in ervice 1966 1, 100 200 iecond .argest Jnit in &vice 1966 argest Jnit in iervice 1970 econd ,argesl Jnit in ervice 1970 Principal Transmission Voltage in Service 1966 Principal Transmission Voltage in Service 1970 230-161-115 230-161-11: Studies-Contin REGION Utilities U.S. Bureau Missouri Basi Minnesot Nebraska North D; Coloradc Iowa Eastern Wisconsin Utilities. . . . 2,600 310 275 230-l 38 . MAPP . . . . . . . . . . . . . . . . . . . , 9, ooa 358 275 : 345-230-131 ; 345-231 230 . ;.I 118 !, m Wiconsi Wiconsi Wionsi Manitob Black Hi Intcrstat Iowa El{ Iowa-Ill Iowa Pa Iowa Pu Iowa Sa Lake Su Minncsc Montan Norther Northwl otter T Union 1 cooper: Dairyla Eastern COOP. Minnkc Northa Rural ( 17 Mur TABLE A-l .-Stability WEST CENTRAL Insage P66 Principal Transmission Voltage in Service 1970 Sn&.r-Continued REGION Utilities Covered by Study -115 230-161-115 U.S. Bureau of Reclamation. . . . . . . . . Missouri Basin System Group : 15 Municipals. Minnesota 3 Cooperatives. 3 State InstituNebraska tions. 3 Municipals. 1 Cooperative. 9 Municipals. North Dakota 9 Cooperatives. 1 Cooperative. Colorado 34 Municipals. Iowa 3 Cooperatives. 9 Cooperatives. Montana South Dakota 20 Municipals. 3 Cooperatives. r138 345-230-l 38 30 345-230 P t i - Purpose of Study Conditions Studied and Conclusions ........................ The large geographical area encompassed by the Federal power system and the location of several large hydroelectric plants within the system have made the problem of system stability under various loading conditions of particular concern to the Bureau of Reclamation. Since January 1964, this group has conducted or participated in five different system stability studies. These include investigation of the effects of new interties and the addition of new generating plants. Wisconsin Electric Power Co. . . Wisconsin Power & Light Co. Wisconsin Public Service Co. Planning expansion of 345-Kv transmission in area. Large-scale stability studies now in progress. Manitoba Hydro-Electric Board. . Black Hills Power & Light Co. Interstate Power Co. Iowa Elec. Light & Power Co. Iowa-Illinois Gas & Electric Co. Iowa Power & Light Co. Iowa Public Service Co. Iowa Southern Utilities Co. Lake Superior District Power Co. Minnesota Power & Light Co. Montana-Dakota Utilities Co. Northern States Power Co. Northwestern Public Service CO. Otter Tail Power Co. Union Electric Co. Cooperative Power Assn. Dairyland Power Cooperative. Eastern Iowa Light & Power Planning individual segments of MAPP’s 345-Kv grid. These studies are unusual in terms of the area covered but are based on more normal disturbances as compared to the MAIN studies. COOP* Miiota Power Cooperative. Northern Minn. Power Assn. Rural Cooperative Power &an. 17 Municipal Systems. - 119 287.381 o-67---9 TABLE A-l .-Stability WEST Sponsor of Study 1966 Peak Load in MW Second Largest Second Largest Unit in Largest Unit in Service Unit in 1966 Service 1970 1966 5% - - - - - - - a2 Service Principal Transmission Voltage in Service 1966 Principal Transmission Voltage in Sexvice 1970 Shcdics-Centi REGION Utilitie Pacific Intertie System Technical Studies Task Force. 33,000 495 475 700 700 230 kv 500-230 750 kv dc Northwest PC Arizona Pub salt River PI California Pc Los Angeles PoWa. USBR, Regi Western United States Transmission Study Task Force sponsored by WEST. 45,000 475 475 750 750 230 kv 500-230 750 kv dc Utilities in tl -Stability WEST Trans‘oltaqe e 1970 - Studies-Continued REGION Utilities Covered by Study Conditions Studied and Conclusions - cm-230 50 kv dc Northwest Power Pool. . . . . . . . . . . . . Arizona Public Service Co. Salt River Project. California Power Pool. Los Angeles Dept. of Water and Power. USBR, Region 2 and 3. 00-230 50 kv dc Utilities in the eleven Western States. I- Purpose of Study For the design of the 500-Kv AC and 750-Kv DC Pacific intertie. Comprehensive stability studies are currently being made of the systems associated with the 500-Kv AC and 750-Kv DC Pacific interties. The studies are being enlarged to include the entire 2,&Omile Western loop. Load flow studies are being made of the transmission network that embraces the eleven Western states. When the load flow studies are completed, stability studies of the same system wilI be made. The above stability studies will depart ‘from the classical transient type which uses a first-swing cycle criterion only, to one that will investigate multiple swings and include the effects of changing machine impedances, governor and exciter responses over a period of 15 to 20 seconds or longer if necessary. The necessity for having this type of study available was demonstrated when several long duration power and frequency oscillations (system instability) occurred after the Pacific Northwest and Pacific Southwest systems were intercomrected at Glen Canyon, Arizona in 1!364. Experience gained in the interconnected operation of the Western utilities has shown that unstable conditions with longterm characteristics can develop. Many studies have been made of these conditions and installation of damping devices operating on the governor control systems has proven that stability can be achieved by special generator response. Additional studies are being made of the resulting system operating conditions and it is anticipated that system stability can be considerably improved by using similar devices to change generator voltage in relation to frequency changes created by the unstable conditions. 121 b. Practices for Emergency Load and Generator Reduction clined to some predetermined level. More than 11 percent of the systems (20) rely upon the judgment of their system dispatcher to make the correct switching decisions during emergencies.. Thirty systems do not have any kind of load reduction program. Of the systems that initiate load shedding on the basis of a predetermined deviation from normal frequency, 81 do so at or above 59.3 cycles per second, 31 systems begin their load reduction program between 59.2 and 58.0 cycles per second, and 6 systems initiate action below 58.0 cycles per second. A total of 44 utilities already have or plan equipment for automatically shedding load at or above 59.3 cycles per second. The following tabulations give the responses by Regions to the survey questionnaires sent out by the Regional Committees. Recommendations concerning load shedding and generator dropping as practices for dealing with problems of separated systems are discussed in chapter 5 of this report. Other information concerning load shedding procedures in the area of the United States affected by the November 9, 1965 power failure is included in chapter 2. A majority of the electric systems that comprise the bulk power supply of the United States have instituted or are in the process of instituting some type of load reduction program to cope with severe system disturbances. Nearly 70 percent of the systems responding to inquiries by the Regional Advisory Committee ( 118 out of 175) indicate that they will shed load when system frequency has de- I TABLE A-P.-Ccmparison by region of number of systems using automatic emergency load reduction programs Total No. of systems reporting Region Number of users at each frequency step 59.2-59.7 58.6-59.1 cps cps Northeast. . . . . . . . . . . Southeast. . . . . . . . . . . . . . . . . . . . . . South Central . . . . . . . . . . . . . . . . . . . West. . . . . . . . . . . . . . . . . . . . . . . . . . West Central. . . . . . . . . . . . . . . . . . . East Central. . . . . . . . . . . . . . . . . . . . 33 16 30 34 34 28 0 6 24 1 12 Total. . . . . . . . . . . . . . . 175 44 ll 58.0-58.5 cps BeloW 58.0 cps Total No. Total of users’ of users load in percent of region load -- 0 8 27 8 13 1 1 7 6 7 6 0 0 2 1 18 4 0 57 27 25 1 12 28 29 15 -- 10 83 56 94 71 1 11 86 .............. TABLE A-3.-Corn/&son by region of automatic emergency load reduction programs - - Percent automatic load ieduction Region -1 &cumulative 59.2-59.7 cps 58.6-59.1 cps 58.0-58.5 cps Below 58.0~ P I - - -- 0 Northeast. . . . . . . . . . . . . . . . . . . . . . Southeast . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SouthCentral . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . west . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . West Central. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . East Central . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 0 2. 7 14.8 2.8 7. 6 0. 1 5. 3 6. 8 0 3. 7 0. 5 - total - -I 2. 1 3.6 5.9 3. 5 4. 3 0 0 2. 1 0 30. 1 0.2 0 2. 1 13. 7 27.5 36.4 15.8 0.6 G New York po Central H Consolida Long Isla New Yorl Niagara B Rochester Power Au Orange & Connecticut ’ United 11 Connectic Hartford Western 1 Holyoke ’ New Englanc Boston EC Cent. Ma Cent. Vei Eastern I Green MN New Eng New Eng PSofNa Penn.-New J Public SC Philadelp Atlantic 1 Delmarv; Penna. F Luzcrne Baltimore Potomac General Jersey Metro1 NmJ Pennsy CARVA gm Carolina Duke PO S. Caroli Virginia see footno ined level. More than 11 20) rely upon the judg,atcher to make the coruring emergencies.. Thirty 1 kind of load reduction hat initiate load shedding nined deviation from nort or above 59.3 cycles per their load reduction proj.0 cycles per second, and claw 58.0 cycles per secies already have or plan ally shedding load at or nd. Ins give the responses by itionnaires sent out by the iauction programs TABLE A-4.-Emcrgmcy load reduction flogram NORTHEAST REGION 59.2-59.7 CP Group or system 1 4uto 1 matic NewYorkpowerpool............... 10 83 56 t I 29 15 1 I 94 71 1 I 86 . . . . . . . . . . . . . . I E Below 58.0 cps 0 2. 1 0 30. 1 I . 0 I 2. 1 13. 7 27. 5 36.4 15.8 0.6 Ud 58.6-59.1 Cps 4uto natic CentralHudsonG&E.. . . . . . . . . . Consolidated Edison I. . . . . . . . . . . . Lung Island Lighting. . . . . . . . . . . . NewYorkStateE&G.. . . . . . . . . . Niagara Mohawk. . . . . . . . . . . . . . . . Rochester Gas & Elez. . . . . . . . . . . . Power Auth. State of N.Y . . . . . . . . . Orange & Reckland Utilities. . . . . . vaky . Elec. Exchange. . . ~MCCtiCUt Light & Power. . . . . . . Hartford Electric Light . . . . . . . . . . . Western Massachusetts Electric. . . . Holyoke Water Power . . . . . . . . . . . . New England group. . . . . . . . . . . . . . . . . Boston Edison Co . . . . . . . . . . . . . . . . Cent. Maine Power. . . . . . . . . . . . . . Cent. Vermont P.S. . . . . . . . . . . . . . Eastern Utilities Asscc . . . . . . . . . . . . Green Mountain Power. . . . . . . . . . New England Electric . . . . . . . . . . . . New England Gas & Elec. . . . . . . . PS of New Hampshire . . . . . . . . . . . . Penn-New Jemey-Maryland system. . . Public Serv. Elect. & Gas Co. . . . . Philadelphia Electric Co . . . . . . . . . . Atlantic City Electric. . . . . . . . . . . . Delmarva Power & Light. . . . . . . . Penna. Power & Light. . . . . . . . . . . Luaerne Electric. . . . . . . . . . . . . . . . . Baltimore Gas & Elec . . . . . . . . . . . . Potomac Electric Power. . . . . . . . . . General Public Utilities . . . . . . . . . . Jersey Cent. Power & Light. . . . . Metropolitan Edison Co . . . . . . . . New Jersey Power & Light. . . . . Pennsylvania Electric Co. . . . . . . . . 58.0-58.5 cpa Autc+ Man- matic Ud -- .... 10.0 .... 15.0 0 0 0 0 . .... 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 . .... 0 0 0 0 0 0 0 0 . .... 0 0 0 0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10. 0 10.0 10. 0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 .... 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 .... 0 0 0 0 0 0 0 0 .... .... 0 .... 0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 0 . . United Illuminating Co. . . . . . . . . . 1 12 28 dan- - -- &MCCtiCUt Total No. Total of users’ of users load in percent of region load Percent load reduction - 0 0 0 0 0 0 0 0 0 0 0 0 Accumulative Below 58.0 -- Man- Auto 1matic Ud total eps Marl- hto- -- Take individual. . action . . . do . . . . . . . . . . . ..do . . . . . . . . . . . . . do . . . . . . . . . . . ..do . . . . . . . . . . . ..do . . . . . . . . . . . . . do. . . . . . . . . . . . . . do. . . . . . . . . . . . . do . . . . . . . . . . . . . do . . . . . . . . . . . ..do . . . . . . . . . . . . . do . . . . . . . . . . . . . do . . . . . . . . . . . ..do . . . . . . . . . . . ..do . . . . . . . . . . . . . do . . . . . . . . . . . . . do . . . . . . . . . . . ..do . . . . . . . . . . . . . do . . . . . . . . . . . . . do . . . . . . . . . . . . . do . . . . . . . . . . . . . do . . . . . . . . . . . ..do . . . . . . . . . . . . . do. . . . . . . . ...... 4. 2 0 4. 2 0 4. 2 0 4. 2 0 4. 2 0 4. 2 0 4. 2 4. 2 0 0 4. 2 . . . . . 4. 2 ...... 4. 2 0 4. 2 ...... 4. 2 0 4. 2 - . .... . .... . . . . .... .... .... .... . . . .... .... . . . .... .... .... . . . . . .... . . . . . .... .... .... .... .... 0 0 0 0 0 0 0 0 .... .... 0 . . . 0 . . . . . . * . . . . . . . . . . . . . . . 5.8 25.0 . . . . . 0 Q 0 0 21.0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 . . ..I 0 0 0 0 (9 0 0 PI 25.0 25.0 25.0 25.0 25.0 25.0 25.0 25.0 25.0 25.0 25.0 25.0 25.0 25. 0 25.0 25. 0 25.0 25.0 25.0 25.0 25.0 25.0 25.0 29.5 29. 5 29. 5 29. 5 29. 5 29. 5 29. 5 29. 5 29. 5 29. 5 29. 5 29. 5 29. 5 29. 5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . &I: i. 25. 3 25. 3 25. 3 25. 3 25. 3 25. 3 25. 3 25. 3 25. 3 25. 3 25. 3 25. 3 25. 3 ‘(9;. ;; (9 - SOUTHEAST REGION Lc CARVA group: 0 21.0/........ 1 0 . . . . . . 27.0 CarolinaPower &Light . . . . . . . . . . 1 . . . . . . / 6.0 . 1 . . . . . 1 Duke Power. . . . . . . . . . . . . . . . . . Has no program. S.CarolinaElec. &Gas . . . . . . . . . . . Manual shedding as required beginning at 59.0 cps. . . . . . . 28.5 VirginiaElectric.& Power . . . . . . . . . 1 0 . 2 I . . . . . . 1 1 0 . 1 I . . . . . . 1 8.21........ 1 0 See footnotes at end of table. Manual natic Ud - TABLE A-4.-Emergency load rductidn program-Continued - SOUTHEAST REGION-Continued Percent load reduction - ,, 7 . 59.2-59 Group or system ) 58.6$X1 1 58.r.5 - . . . . . I A u t o - M a n - A u t o - Mu:- A u t o - Manmatic u a l matic matic u a l --~--5.0 5.0 5.0 5.0 5.0 9.0 .. . .. .. . . .... . . .... . . .... ...... ...... ...... 5 . 0 . . .... 0 ........ 0 5 . 0 . . .... 0 ........ 0 5 . 0 . . .... 0 ........ 0 5.0 . . . . . . 0 ........ 0 5.0 . . . . . . 0 ........ 0 Manual as required below 59.2 cps. Manual reduction as 0 ...... 0 0 ...... 0 . . . . . . 30.9 0 0 . . . . . . 16.6 . Be1ocwps58.0 A~cm~~u$tiv -I 1 I - - Southern Services. . . . . . . . . . . . . Alabama Power. . . . . . . . . . Georgia Power. . . . . . . . Gulf Power. . . . . . . . . . . Mississippi Power. . . . . . . . . . Tennessee Valley Authority. . . . . Florida group : Florida Power Corp.. . . . . Florida Power & Light Co. . . Tampa Electric Co. . . . Orlando Utilities. . . . . . . . City of Jacksonville. . . . . . . . . Others: Savannah Electric Power. . S. Carolina Public Service. . 1 required. ...... 9.0 ...... 12.2 ...... 20.6 ...... 33.4 blto- ...... ...... ...... ...... ...... Manual .......... .......... .......... .......... .......... As req’d. ...... 20.0 ...... ...... .......... 20.0 .......... .......... Manual reduction as required up to 50 percent before 58.0 cps. I.. . . . :I 2 0 . 0 I.. . . . . . .I 0 I...... 0 .......... ........ ........ ........ ........ 24.0 7.8 0 (4) - EAST CENTRAL REGION American Electric Power: Appalachian Power. . . . . . . . . . . . . Indiana & Michigan. . . . . . . . . . . . . Kentucky Power. . . . . . . . . . . . . . . . Kingsport Power. . . . . . . . . . . . . . . Ohio Power. . . . . . . . . . . . . . . . . . . . Wheeling Electric.. . . . . . . . . . . . . . Allegheny power system : Monongahela Power. . . . . . . . . . . . . Potomac Ediion. . . . . . . . . . . . . . . . . West Penn Power. . . . . . . . . . . . . . . . Ohio-Pennsylvania: Cincinnati Gas & Elec. . . . . . . . . . . Cleveland Elec. Illum s . . . . . . . . . . . Columbus & Southern Ohio Elec . Duquesne Light Co. . . . . . . . . . . . . . Ohio Edison Co. . . . . . . . . . . . . . . . . Toledo Edison Co. . . . . . . . . . . . . . . Indiana group: Indianapolis Power & Light. . Pub. Serv. Co. of Indiana. . . . . Southern Indiana Gas & Elcc. Northern Indiana Pub. S,erv. . See footnotes at end of table. \r rhe vast number and wide distribution of interconnections on the AEP system, its distribution of reasonably sized generating plants relative to its size of system and its continued adherence to a program of transmission development makes the general application of load shedding thus far impracticable and unnecessary on the AEP system. Interruptible lqads play an important role in maintaining the integrity of AEP’s generation. These loads presently amount to 5.40/, of the system total. . 1Drop 24 Mw ( 1 .O percent) interruptible load by manual means at 59.9 cps. Manual reduction of selected customer load at 59.5, 59.0, 58.5, and 58.0 cps. Power :I stations to take independent action to save the station at 57.5 cps. 1 I t x 1 :;:x j 8 1 Go I x 0 0 Manual load reduction as required. 0 0 20.0 0 110.0 1 0 1 10.0 1 0 0 0 Manual reduction as required. j percent load relief via 5 percent voltage reduction and 1 percent load reduction by shutting down interruptible customers if disturbance is not severe. For more severe conditions, up to 50 percent manual load reduction in 19 steps. : zi ... . . 50.0 20.0 / ;;g / H / :;i: / ij / Shed load as required below 58.5 cps. 24.0 1;o 1 8 / 8 / ; I g; ~ ....................................................................... Kentucky g East Kc Kentuc Ownest Louisvi OVEC Michigan g Consun Detroit Detroit Lansinl South Cen Middle .t LO Mi NC Kansar Centri Empir Gulf S Oklah Pub. ,c South? Southwest west ’ Kansa Kansa Kansz St. Jo City c Weste Misso Spring Dentc Brow] south Te Hous Centx City ( City ( Lowe See foo 124 TALL& A-l.-Emergency load reduction program--Continued EAST CENTRAL KEGION-Continued I w 58.0 w ManUd Accumulative total Automatic Group or system .......... .......... .......... .......... .......... . . . . . . . . . . . . . . . . . . . . . . . . 4s req’d. . . . . . . 20. 0 ..... . ...... 59.2-59.7 cps 58.6-59.1 cps 58.0-58.5 cps Auto- Man- Auto- Manmatic u a l matic u a l - Manual -. . . . . Percent load reduction Below 58.0 cps Automatic Kentucky group: 13.5 0 5.6 East Kentucky REA.. . . . . . . . . . . . . . 0 13.5 0 Kentucky Utilities Co. . . . . . . . . 0 5.6 13.5 0 Ownesboro Municipal. . . . . . . . . 0 5.6 LouisvilleGas&Elec.. . . . . . . . . . . . Manual load reduction as required. OVEC . . . . . . . . . . . . . . . . . . . . . . . . . . I Michigan group : Consumers Power Co. . . . . . . . . . . . . DetroitEdisonCo.. . . . . . . . . . . . . . . Manual load reduction as required. Detroit Public Lighting. . . . . . . . . . . . Lansing Water & Light. . . . . . . . . . . . I 4utomatic Accumulative total 4utonatic Manual 2.8 2.8 2.8 SOUTH CENTRAL REGION ons on the AEP system, its ive to its size of system and u1 development makes the able and unnecessary on the ole in maintaining the inBunt to 5.4’?$ of the system means at 59.9 cps. Manual 8.5, and 58.0 cps. Power at 57.5 cps. ‘0 0 0 0 50.0 20.0 0 0 20.0 F \ 1 percent load reduction x is not severe. For more ion in 19 steps. Aired below 58.5 cps. 24. 0 30.0 20.0 ...................... South Central group s. . . . . . . . . . . . . . . . Middle South Utilities . . . . . . . . . . . . . Arkansas Power & Lights . . . . . Louisiana Power & Light s. . . . Mississippi Power & Light s. . . . New Orleans Public Service s . . . Kansas Gas & Electric s . . . . . . . . . . . Central Louisiana s. . . . . . . . . . . . . . . Empire District s. . . . . . . . . . . . . . . . . Gulf States Utilities s . . . . . . . . . . . . . . Oklahoma Gas & Electric s . . . . . . . . Pub. Serv. Co. of Oklahoma. . . . . . . Southwest Electric Power C0.s. . . . . Southwest group : West Texas Utilities s. . . . . . . . . . . . . Kansas Power & Light 6. . . . . . . . . . . Kansas City Power & Light 6. . . . . . . Kansas City Municipal 7 . . . . . . . . . . . St. Joseph Light & Power 7. . . . . . . . . City of Independence 6. . . . . . . . . . . . Western Farmers Coop.6 . . . . . . . . . . . Missouri Public Service Co.6. . . . . . . Springfield, Missouri. . . . . . . . . . . . . . Denton, Texas. . . . . . . . . . . . . . . . . . . Brownsville Municipal. . . . . . . . . . . . . South Texas system. . . . . . . . . . . . . . . . . . Houston Light & Power Co. . . . . . . Central Power & Light Co. . . . . . . . City of San Antonio. . . . . . . . . . . . . . City of Austin. . . . . . . . . . . . . . . . . . Lower Colorado River. . . . . . . . . . . See footnotes at end of table. 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10. 0 . . . . 20.0 ..... . . . . . . 20.0 20.0 20.0 20.0 20.0 . 20.0 20.0 . . . 20.0 20.0 . . 20.0 20.0 . 20. 0 .... . . . . . . . . . .... . . . . . . . . . . . . . . 6.0 4.0 . . . . 20. 0 10.0 . . . . 20.0 10.0 .... . . . 20.0 10.0 . . . . . 20.0 10.0 . 10.0 . . 20.0 . . 20. 0 10.0 . . 20.0 . . 10.0 10.0% automatic at unspecified frequency (future). Manual shedding of up to 100 percent load in 8 steps. Manual reduction as reouired when frequency drops to 59.5 c ...... 25.6 5.0 ...... 5.0 25.0 ...... 5.0 25.0 5.0 ...... 25.0 5.0 ...... 25.0 5.0 ...... 25.0 ......... ......... ......... ......... ......... ......... 125 TABLE A-4.-Emergency load reduction flogram--Continued SOUTH CENTRAL REGION-Continued Percent load reduction 59.2-59.7 Group or system 58.6-59.1 58.0-58.5 Below 58.0 Accumulative total GX Auto- Manual matic Texas Utilities system: Dallas Power & Light Co. . . . . . . Texas Power & Light Co. . . . . . . Texas Electric Service. . . . . . . . . . Manual operations according to a definite plan augmented by under frequency relays and interruptible industrial load. The Ft. Worth-Dallas area load can be reduced by use of supervisory control. Load would be reduced in whatever amounts necessary to maintain system frequency at or above 58 cps. In one large area of the system which is subject to isolation, under frequency relays are set to disconnect 30 percent of the area load at 59 cps. The largest single manually interruptible load is 60,000 Kw. WEST CENTRAL REGION Wisconsin group: Wisconsin Public Serv. . . . Wisconsin Power & Light. . Wisconsin Electric Power. . Wisconsin-Michigan Power. Madison Gas & Electric. . . Upper Pennisula Power. . . . Edison Sault Electric.. . . . . Commonwealth Edison Co.. Illinois-Missouri pool. . . . . Union Electric Co. . . Cent. Illinois Pub. Serv. . . Illinois Power Co. . . Central Illinois Light.. . . . . Iowa pool.. . . . . . . Iowa-Electric L & P. . Iowa-Illinois G & E . . . Iowa Public Service.. . . . . . Iowa Southern Util.. . . . . Iowa Power & Light. . Corn Belt Power Coop. . Nebraska Public Power Sys.. . Omaha Public Power District. . . Missouri Basin Systems Group.. . .. . . Upper Mississippi Valley power pool: Cooperative Power Assoc. . . . . Dairyland Power Coop. . . Interstate Power Co.. . . . Lake Superior District.. . Minnesota Power & Light . . . Minnkota Power Coop. . . . Montana Dakota Utilities.. . . Northern Minn. Power Assoc. Northern States Power Co. . . Northwestern Public Service. Otter Tail Power Co. . . . . . Rural Cooperative Power. . . . United Power Assoc.. . . . . . See footnotes at end of table. 126 0 19.0 0 19.0 r) 0 0 0 0 0 0 20.0 0 5.0 0 5.0 0 10.0 0 0 0 5.0 0 10.0 0 30.0 15.0 0 0 0 0 0 0 0 0 0 0 0 0 0 10.8 0 0 0 5.4 0 5.4 0 21.6 0 0 1 1 . 2 3 4 . 0 27.6 0 ’ 0 0 0 16.4 34.0 Manual load reduction as required. 45.0 15.0 . . . . . . 0 7. 0 30. 0 7.0 . . . . ‘.. 20. 0 6.0 42.0 0 . 2 4 2 . 0 24.0 10. 7 . . . . . . . . 0 . 6 . . . . . 12.5 . . . . . . 42.0 0 . 2 4 2 . 0 24.0 0 . 6 . . . . . . 12.5 . . . . . . 10. 7 . . . . . . . . 42.0 0. 2 4 2 . 0 24.0 0 . 6 . . . . . . 12.5 . . . . . . 10. 7 . . . . . . . . 0 . 2 4 2 . 0 24.0 42.0 0 . 6 . . . . . . 12.5 . . . 10.7 . . . . . . . . Manual reduction as required up to 8 percent of system. 10.0 . . . . . . 20.0 . . . . . . 0 .._....... ........ 0 ..... 10.0 . . . . . . 2 0 . 0 . . . . . . 0 0 .......... ........ ..... 10.0 . . . . . . 20.0 . . . . . . ........ 0 ..... 0 . ......... 10.0 . . . . . . 20.0 . . . . . . 0 .._....... ........ 0 ..... 10.0 . . . . . . 20.0 . . . . . . 0 . ......... ........ 0 ..... ........ 0 ..... 10.0 . . . . . . 2 0 . 0 . . . . . . 0 . ......... 10.0 . . . . . . 20.0 . . . . . . 0 . ......... ....... 0 ..... ....... 10.0 . . . . . . 20.0 . . 0 .......... 0 ..... 10.0 . . . . 2 0 . 0 . . . . . . 0 ........ 0 ..... . ......... Wider operating range of hydrogeneration eliminates the need for a load reduction program. IO percent initial automatic reduction supplemented by manual as required before decay to 58.0 cps. 0 ...... 6.6 . . . 13.4 . . . . . . . . . . . . . . 25.0 20.0 25.0 10 percent initial automatic reduction supplemented by manual as required before d-[tos-[vs. 1 1 1 1 ( ( 1 c Northwest pow So. IdahoIdaho USBR Utah-E. Ic UtahI Central & ‘ Monta Bonnel E. Wash.-? Washir Bonnet west E Central W: Washir Bonnet Pacific Puget ! Chelan Grant 1 Puget Sour British Seattle, Bonnet Puget ! Tacom Southern C Pacific Portland-M Portlan Bonna Pacific Eugene Rocky Mounta AreaI.... Mental Bonna Arcas II, I Mental USBR Area III, I Utah & Bonnev Prefere Califor Area IV.. Pacific Tri St; USBR See footnotes TABLE A-4.-Emergency load rcduckon program-Continued WEST REGION Percent load reduction - - Itive 59.2-59.7 cps Group or system ml al Auto- Man.. matic Ud -xn be IlOUIltS I of the le load 19.0 20.0 30.0 0 21.6 V34.0 45.0 42.0 42.0 42.0 42.0 ..... ..... . . . . . . . . . . . ,.... ..... ,.... action CfOrC 25 .O -- I 1 1 1 1 Northwest power pool. . . . . . . . . . . . So. Idaho-E. Oregon . . . . . . . . . . . . . Idaho Power Co. . . . . . . . . . . . . USBR . . . . . . . . . . . . . . . . . . . . . . Utah-E.Idaho . . . . . . . . . . . . . . . . . . UtahPower&LightCo . . . . . . Central & W. Montana . . . . . . . . . . . Montana Power Co. . . . . . . . . . Bonneville Power Adm. . . . . . . . E. Wash.-N. Idaho-W. Kootenay. Washington Water Power Co. . Bonneville Power Adm . . . . . . . . West Kootenay Pr. & Lt. Ltd. Central Wash.-Oregon . . . . . . . . . . . Washington Water Power Co. . Bonneville Power Adm . . . . . . . . Pacific Power & Light . . . . . . . . . Puget Sound Power & Lt. Co. . Chelan County P.U D . . . . . . . . Grant County P.U.D. . . . . . . . . Puget Sound-SW British Columbia. British Columbia Hydro . . . . . . . Seattle, Dept. of Lighting. . . . . Bonneville Power Adm . . . . . . . . Puget Sound Power & Lt. Co. . Tacoma, Dept. of Pub. Util. SouthernOregon . . . . . . . . . . . . . . . . . Pacific Power& Light Co . . . . . . Portland-Willamette-Oregon Coast. Portland General Electric. . . . . . Bonneville Power Adm. . . . . . . . . Pacific Power & Light Co. . . . . . Eugene Water & Elec. Bd. . . . . Rocky Mountain power pool. Area1 . . . . . . . . . . . . . . . . . . . . . Montana Power Co. . . . . Bonneville Power Adm. . . Areas I I , I I - A , I I - B . Montana Power Co. . USBR Reg. 6. . . . . , Area III, III-A.. . . . , . Utah & Idaho . . . Bonneville Power Adm. Preference Customers. . . . . . California Pacific Util. Co.. Area IV.. . . . . . . . . . . . . . . . . . Pacific Power & Light Co. Tri StateG&TAssoc..... USBR Reg. 4. . . . . . . . . See footnotes at end of table. _0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 58.6-59.1 cps -. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . J -- ,Auto1matic 3. 8 22. 6 24. 4 0 14. 7 14. 7 8. 7 13. 3 0 3. 2 0 0 11.4 1. 1 0 0 4. 6 0 0 0 2. 3 0 0 11. 8 0 0 0 0 0. 9 0. 3 0 3. 5 0 9. 4 7. 0 15.0 0 12.0 13.0 0 25. 0 35. 0 0 0 0 8. 0 12.0 0 0 -- Mall- 58.0-58.5 cps Automatic Ud -. . . . . . . . . . . . . . . . . . . . ..... ..... . . . . ..... ..... . . . . . . . . . . . . ..... ..... ..... . . . . . . . . . . . . . . . . . ..... ..... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..... ..... . . . . . . ..... . . . . . . MarlUd -1. 5 2. 3 2.4 0 12. 3 12. 3 1. 3 2. 0 0 1.8 0 0 6. 3 0 0 0 0 0 0 0 1. 0 0 0 4. 9 0 0 0 0 0. 5 0 0 2. 1 0 16. 7 41.0 15.0 68.0 47. 0 48.0 0 6. 5 9. 2 0 0 0 16.0 24. 0 0 0 -- Below 58.0 cps - I Accumulative total .- Auto . 1Man- Auto. / matic matic Ud -- --_ ....... 30. 3 ...... 10. 1 ...... 10. 9 ...... 0 ...... 22. 4 ...... 22. 4 ...... 2 7 . 0 ...... 2. 8 ...... 72. 9 ...... 42. 8 ...... 49. 2 ...... 73. 6 ...... . . . . . . ...... 22. 5 ...... . 1 00. ...... 28. 9 ...... 4.6 ...... . 1 00. ...... 0 ...... 0 ...... 39. 5 ...... 27. 9 ...... 64. 0 ...... 7. 2 ...... 72. 3 ...... 22. 8 ...... 63. 2 ...... 63. 2 ...... 17. 3 ...... 6. 3 ...... 35. 0 8. 5 ...... ...... 55.0 ...... 4. 3 ...... 8.0 0 ...... ...... 16. 0 ...... 0 ...... 0 ...... 0 ...... 13. 5 ...... 19. 1 ...... 0 ...... 0 ...... 0 ...... 15.0 ...... 2 1 . 0 ...... 0 ...... 0 16.4 35. 1 2. 5 35.0 . . . . 37. 7 34. 6 0 . . . 49. 4 . . . 49. 4 . . . . 37. 0 . . . . 18. 1 . . 72. 9 11.4 47. 8 15.0 49. 2 12. 9 73. 6 4. 5 17. 7 18. 6 23.6 . .1 00. 16. 2 28. 9 30. 7 9. 2 . . . . 1 00. 0 0 0 0 6. 5 42. 8 . . . . 27. 9 . . . 64.0 30. 2 23. 9 72. 3 3.6 . . 22.8 ‘4.6 63. 2 4. 6 63. 2 43. 7 18. 7 48. 3 6. 6 44.7 35. 0 14. 1 31.4 . , . . 55.0 . . . . . 30.4 . . . . . 56. 0 . . . . . 30. 0 . . . . . 84. 0 . . . . . 59.0 . . . . 61.0 . . . . 0 . . . . 45.0 . . . . . 63. 3 . . . 0 0 ..... . . . 0 . . . . . 39.0 . . . . . 57. 0 . . . . 0 0 ..... 16.4 2. 5 ......... 34. 6 ......... ......... ......... ......... ......... 11.4 15. 0 12. 9 4. 5 18.6 ......... 16. 2 30. 7 ......... 0 0 6. 5 ......... ......... 30. 2 3. 6 ......... 4. 6 4. 6 43. 7 48. 3 44.7 31.4 ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... ......... 127 TABLE A-4.-Emergency load reduction program-Continued WEST REGION-Continued Percent load reduction - Group or system 59.2-59.7 cps b-----l- Rocky Mountain power pool-Con. Areav. . . . . . . . . . . . . . . . . . . . . . . . . . 0 ...... 0 ..... Pacific Power & Light Co . . . . . . . TriStateG&TAssoc.. . . . . . . . 0 ..... 0 ..... Cheyenne Lt., Heat & Pr. Co. . Consumers PPD . . . . . . . . . . . . . . . 0 ..... AreaVI . . . . . . . . . . . . . . . . . . . . . . . . . 0 ..... USBR Reg. 4 . . . . . . . . . . . . . . . . . 0 ..... 0 ..... Western Colorado Pcwer Co. . . Colorado-Ute Elec. Assoc. . . . . . 0 ..... 0 AreaVII . . . . . . . . . . . . . . . . . . . . . . . . ..... Public Service Co. of Colorado. 0 ..... So. Colorado Power Div . . . . . . . . Colorado Springs Pub. Util. . . . . 0 ..... 0 USBRReg.7.. . . . . . . . . . . . . . . . ..... TriStateG&TAssoc.. . . . . . . 0 .: . . . REA,G&T’s,Munic.. . . . . . . . 0 ..... California-Nevada group: Sacramento Muni. Util. Dist . . . . . . . . . . . . . . . . . . Sierra Pacific Power Co. . . . . . . . . . . Equipment Pacific Gas & Electric Co. . . . . . . . . . . . . . . . . . . . . Southern California Edison Co. . . . . . . . . . . . . . . . LosAngelesDept.ofWater&Power. . . . . . . . . . . . SanDiegoGas&ElectricCo.. . . . . . . . . . . . . . . . . Arizona-Nevada group : Arizona Public Service Co. . . . . . . . . . . . . . . . . . . . Arizona Power Authority. . . . . . . . . . . . . . . . . . . . . ArizonaElectricCoop . . . . . . . . . . . . . . . . . . . . . . . . USBRReg.3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Nevada Power Co. . . . . . . . . . . . . . . . . . . . . . . . . . . Salt River Project. . . . . . . . . . . . . . . . . . . . . . . . . . . Tucson Gas & ElectricCo . . . . . . . . . . . . . . . . . . . . New Mexico-Texas group: USBRReg.5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Plains Electric G & T Coop. . . . . . . 10.0 . . . . . Community Public Service . . . . . . . . . . . . . . . . . . . . Public Service Co. of New Mexico. . . . . . . . . . . . . El Paso Electric Co. . . . . . . . . . . . . . . . . . . . . . . . . . 58.6-59.1 cps -- Auto- Man.* matic u a l .- 58.0-58.5 W Below 58.0 cps Accumulative total -_ /Auto- Man1matic u a l A u t o - M a n - A u t o - M a nI- Automatic matic u a l Ud matic -.-~~-- - - Manual 1.0 . . . . . . . . 0 ..... 5.0 . . . . . . 6.0 0 . . . . . . 0 13.0 . . . . . . . . . 13.0 0 . . . . 0 0 ...... . . . . 0 f..... 0 0 0 0 0 ...... 8.0 :::::::: 0 ::::: a. 0 0 ...... . . . . . . 0 0 0 0 0 ...... 0 . . . . . 0 0 0 0 ...... 0 ....... 0 0 0 0 ...... 0 0 0 0 20.0 : : : : : : : : 10.0 . . . . . 0 ...... 30.0 ...... 0 30.0 . . . . . . . . 23.0 . . . . . 53.0 Equipment on order (Frequency not specif ied ) . . . . . . 0 1. . . . . . 0 0 . . 0 . . . . . . 0 ....... . . . 0 0 0 0 ....... 0 . . 0 0 I. . . . . . I 0 . . . . . . 0 ....... 0 0 . . ......... ......... ......... ......... ......... 0 0 0 0 ......... ......... -- - New York POT Central H Consolida Long Islai New York ......... ......... ......... ......... , . . I I . I...... I . . . . . . I . . . . . . L order (frequency not specified) I I I . ..... . . . YeJ ......... ..... . . . ..... * . . . . . .... . . . 29.0 36.0 40.0 27.0 ......... ......... ......... ......... . . . . . . . . . . . . . . . . . . ........................... .................... ............... ..... ............... ..... . . . .................... ............... ..... .................... t Has an automatic load relief program wherein voltage is automatically reduced by underfrequency relays, 5% at 59cps to provide a 2.3% load reduction and 3Cr, at 58.5 cps to provide an additional 1.570 load relief. *Have equipment orders in process to bring automatic load shedding to approximately 30 percent. 3 300/, of load will be under automatic control by end of 1968. 4 Additional reduction can be accomplished by super- 128 -7 ......... . ......... YeS . . . . . . . . . 67. 0 . . . . . . . . . 30.0 . . . . . . . . . 61.0 . . . . . . . . . YeS . . . . . . . . . . . . . . . ........ ii’ ,’ . . . . . . . . . YeS ........ YeS . . . . . . . . . ........ Yt3 . . . 0 . . . . - Green M New Eng New En8 Public SC Pennsylvania 38.0 . . . . . . Niagara 1 Orange & Rochester Power Au Connecticut 7 United 11 Connectic Hartford Western 1 Holyoke ’ New Englanc Boston EI Central n Central \ Eastern I . - - visory control. Transfer tripping of 148 Mw (24 percent is planned for loss of City’s largest unit (250 Mw). 5 Program not yet in effect but scheduled for 1967 corn pletion. s 20 percent more is planned in steps at 59.3, 59.0 ant 58.7 cps. 7 Program not yet in effect but scheduled for 1968 pletion. corn CARVA Grc Carolina Duke PC s. Carol Virginia Florida Grow Florida Florida Tampa Orlandc City of. Southern St Tennessee 7 Savannah E S. Carolina See footnc TABLE A-5.--Load aad gmrabon emergency dropping pm&es NORTHEAST REGION Open Interconnections on Low Frequency Group or System - - Manual ........ ........ ........ ........ ........ 0 0 0 0 ........ ........ ....... /....... ....... ....... ....... ....... ....... ....... ....... ....... ....... ....... ....... ....... ....... ....... ....... ....... ....... ....... ....... lercent) 17 com9.0 and i8 com- -_ l- ulative :al Drop Generation on Loss of Load New York Power Pool. . . . . . . . . . . . . . . . . Central Hudson Gas & Electric. . . . Consolidated Edison . . . . . . . . . . . . . . . . . Long Island Lighting. . . . . . . . . . . . . . . . New York State Elec. & Gas . . . . . . . . . . Niagara Mohawk. . . . . . . . . . . . . . . . . . . Orange & Rockland. . . . . . . . . . . . . . . . . Rochester Gas & Electric. . . . . . . . . . . . . Power Authority, State of New York. .. Connecticut Valley Electric Exchange . . . . . United Illum. Co. . . . . . . . . . . . . . . . . . . Connecticut Light & Power. . . . . . . . . . . Hartford Electric Light. . . . . . . . . . . . . . Western Massachusetts Elect . . . . . . . . . . Holyoke Water Power. . . . . . . . . . . . . . . New England Group . . . . . . . . . . . . . . . . . . . . Boston Edison Co. . . . . . . . . . . . . . . . . . . Central Maine Power. . . . . . . . . . . . . . . . Central Vermont Public Service . . . . . . . Eastern Utilities Assoc. . . . . . . . . . . . . . . Green Mountain Power . . . . . . . . . . . . . . New England Electric. . . . . . . . . . . . . . . New England Gas & Electric. . . . . . . . . Public Service of New Hampshire. . . . . Pennsylvania-New Jersey-Maryland. . . . . . . Not planned but as a last resort. . . . . . do . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . ..do . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . do. . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . ..do . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . ..do . . . . . . . . . . . . . . . . Openat59.0cps.. . . . . . ...................... No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . (1). . . . . . . . . . . . . . . . . . . . . 0. 0. Once in 15 yrs. 2. 1. 1 manual. 0. 0. ii0............. ......................... 1. 1. 1. 1. 0. No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . ....................... No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . Automatically on 10% ovelspeed. No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . (2). . . . . . . . . . . . . . . . . . . . . CARVA Group: Carolina Power & Light . . . . . . . . . . . . . Duke Power . . . . . . . . . . . . . . . . . . . . . . . . S. Carolina Electric & Gas . . . . . . . . . . . Virginia Electric & Power. . . . . . . . . . . Florida Group : Florida Power Corp. . . . . . . . . . . . . . . . . Florida Power & Light. . . . . . . . . . . . . . Tampa Electric Co . . . . . . . . . . . . . . . . . . Orlando Utilities . . . . . . . . . . . . . . . . . . . . City of Jacksonville. . . . . . . . . . . . . . . . . Southern Services. . . . . . . . . . . . . . . . . . . . . . Tennessee Valley Authority . . . . . . . . . . . . . . Savannah Electric & Power. . . . . . . . . . . . . S. Carolina Public Services . . . . . . . . . . . . . . See footnotes at end of table. . . 0. 0. 0. 0. 1. 1. 0. 0. 0. - - - No. of Occasions Load Shedding Used in 1965 SOUTHEAST REGION No policy . . . . . . . . . . . . . . . . . . do. . . . . . . . . . . . . . . . . . . . . do. . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . No policy . . . . . . . . . . No. . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . Open at 58.3 cps. . . Yes. . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . 0. 0. 0. 0. No. . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . Separate Indian River Plant #l with 60 Mw. Load at 58.0 cps. . . . No . . . . . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . ........................... ........................... 0. 0. 0. 0. ... ... ... ... 0. 0. 0. 0. 0. TABLE A-5.--Load and generation emergemy dra#ing practices--Continued SOUTHEAST REGION-Continued Group or System CAPCO Group: American Electric Power . . . . . . . . . . . . . . Allegheny Power System. . . . . . . . . . . . . . Cincinnati Gas & Electric. . . . . . . . . . . . Cleveland Electric Illum. . . . . . . . . . . . . . Coldmbus & So. Ohio Elec. . . . . . . . . . . Duquesne Light Co. . . . . . . . . . OhioEdiinCo . . . . . . . . . . . . . . . Toledo Edison Co. . . . . . . . Indiana Group : Indianapolis Power & Light.. . . . Public Service Co. of India. . . Southern Indiana Gas & Elec . Northern Indiana Public Serv. . . Kentucky Group : East Kentucky REA.. . . . . . . . . Kentucky Utilities Co. . . . . . Owensboro Municipal. . . . . . . Louisville Gas & Electric. . . . . . Michigan Group : ConsumersPowerCo . . . . . . . . . . Detroit Edison Co. . . . . . . . Detroit Public Lighting. . . . . Lansing Water & Light. . . . . . . . ... . . ... . . . . . . Open Interconnections on Low Frequency Drop Generation on Loss of Load No. of Occasions Load Sheddirig Used in 1965 No. . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . Openat 58.2 cps . . . . . . . . Open 58.0 cps. . . . . . . . . . . Now being engineered for automatic operation. Openat58.5cps.. . . . . . . Openat59.0cps.. . . . . . . . . . do . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . 0. 0. 0. 0. 0. No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . 1. 0. 0. Openat58.0cps.. . . . . . . Openat57.5cps.. . . . . . . Openat58.0cps.. . . . . . . ....................... No . . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . 0. 0. 0. 0. Openat57.5cps.. . . . . . . No . . . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . . Openat58.0cps . . . . . . . Openat58.5cps . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . Openat59.5cps.. . . . . . . Openat58.8cps.. . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . Eastern Wisco Upper Peninsi Edison Sault I Commonweal1 Illinois-Missot Central Illinoi Iowa Pool. . Nebraska Pub Omaha Public Missouri Basir Upper Mississ I 0. ! 0. 0. 0. 0. 0. 0. 1. SOUTH CENTRAL REGION Kansas City Power & Light. . Kansas Power & Light. . . . Missouri Public Service. . . Middle South System . . . . Gulf States Utilities.. . . . . Central Lousiaina Electric. . . Kansas Gas & Electric.. . . . . . Public Service of Oklahoma. . . Western Farmers Electric Coop City of Independence. . . . . . . . . . . . . Southwestern Electric Power. . . . . . . Oklahonia Gas & Electric . . . . . . . . . Texas Utilities System. . . . . . . . . . . . Empire District. . . . . . . . . . . . . . . . . . St. Joseph Light & Power . . . . . . . . . South Texas System. . . . . . . . . . . . . . Springfield, Missouri . . . . . . . . . . . . . . Plains Electric Gas & Transmission. Denton, Texas. . . . . . . . . . . . . . . . . . . Kansas City Municipal . . . . . . . . . . . . Brownsville Municipal. . . . . . . . . . . . . . . . . . . . . Studying 58.5 cps . . . . . . . . No. . . . . . . . . . . . . . . . . . . Open at 58.5 cps . . . . . . . . No. . . . . . . . . . . . . . . . . . . Stay until untenable. . . . . No . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . Openat58.5cps.. . . . . . . No. . . . . . . . . . . . . . . . . . . No policy. . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . Open at 58.5cps . . . . . . . . No. . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . Maybe at 58.5 cps . . . . . . . No. . . . . . . . . . . . . . . . . . . Open if necessary. . . . . . . . No. . . . . . . . . . . . . . . . . . . Open at 59.4 cps. . . . . . . . No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . Last resort. . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . Open below 57 cps . . . . . . . No. . . . . . . . . . . . . . . . . . . Openat58cps.. . . . . . . . . No. . . . . . . . . . . . . . . . . . . YeS . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . Last resort. . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . Openat59.0cps.. . . . . . . No. . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . 0. 0. 0. I. 1. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. 0. See footnotes at end of table. 130 Northwest POT utah POH Idaho Pov Grant COI Puget Sou Portland ( Tacoma, I Eugene, V Montana Washingtc Bonneville Seattle, D’ Pacific Po Chelan C California-Ne Pacific Gz Southern Los Angel Sacramen Sierra Pat San Diegc USBR Re Arizona-Neva Arizona I Tucson G Arizona E Arizona F USBR Rc Nevada P Salt Rive] Rocky Moun USBR Rc USBR Rc USBR Rc Colorado So. Color Colorado. Public Se see footnote TABLE A-5.--Load and generation emcrgmy dro@g +&es-Continued WEST CENTRAL REGION I Occasions hedding Used .n 1965 Group or System Eastern Wisconsin Utilities. . . . . . . . . . . . . . Upper Peninsula Power. . . . . . . . . . . . . . . . . Edison Sault Electric. . . . . . . . . . . . . . . . . . . Commonwealth Edison. . . . . . . . . . . . . . . . . Illinois-Missouri Pool. . . . . . . . . . . . . . . . . . . Central Illinois Light. . . . . . . . . . . . . . . . . . . Iowa Pool . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Nebraska Public Power. . . . . . . . . . . . . . . . . Omaha Public Power. . . . . . . . . . . . . . . . . . . Missouri Basin Systems . . . . . . . . . . . . . . . . . . Upper Mississippi Valley Pool . . . . . . . . . . . . Open Interconnections on Low Frequency Drop Generation on Loss of Load No. of Occasions Load Shedding Used in 1965 Openat58.5cps . . . . . . . . Has no closed ties.. . . . Open when capacity is exceeded. No................... O p e n a t 58.5cps.. . . . . . do. . . . . . . . . . . . . . Take individual action below 58.5 cps. No policy.. . . . . . . . . . . . . . . .do.. . . . . . . . . . . . . . No................... Open at 58.0 cps. . . . . . . No. . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . 0. 8. 0. No. . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No. . . . . . . . . . . . . . . . . . . . 1. 1. 0. 3. ....................... ii;::::::::::::::::::: No . . . . . . . . . . . . . . . . . . . . 3. WEST REGION Northwest Power Pool: Utah Power & Light Co. . . . . . . . . . . . . Idaho Power Co . . . . . . . . . . . . . . . . . . . . . Grant County PUD. . . . . . . . . . . . . . . . . . Puget Sound Power & Lt. Co. . . . . . . . . Portland General Electric, . . . . . . . . . . . . Tacoma, Dept. of Pub. Util. . . . . . . . . . Eugene, Water & Elec. Bd. . . . . . . . . . . . Montana Power Co. . . . . . . . . . . . . . . . . . Washington Water Power Co. . . . . . . . . . Bonneville Power Adm. . . . . . . . . . . . . . . Seattle, Dept. of Lighting . . . . . . . . . . . . . Pacific Power & Light Co. . . . . . . . . . . . . Chelan County P.U.D. . . . . . . . . . . . . . . California-Nevada Group: Pacific Gas & Electric Co. . . . . . . . . . . . . Southern California Edison Co . . . . . . . . . Los Angeles Dept. of Water & Power. . . Sacramento Muni. Util. Dist. . . . . . . . . . Sierra Pacific Power Co. . . . . . . . . . . . . . San Diego Gas & Elec. Co. . . . . . . . . . . . USBRReg.2 . . . . . . . . . . . . . . . . . . . . . . . Arizona-Nevada Group: Arizona Public Service Co. . . . . . . . . . . . Tucson Gas 8c Elec. Co. . . . . . . . . . . . . . . Arizona Electric Power Coop. . . . . . . . . . Ariiona Power Authority. . . . . . . . . . . . . USBRReg.3.. . . . . . . . . . . . . . . . . . . . . . Nevada Power Co . . . . . . . . . . . . . . . . . . . . Salt River Project . . . . . . . . . . . . . . . . . . . . Rocky Mountain Power Pool : USBRReg.4.. . . . . . . . . . . . . . . . . . . . . . USBRReg.6 . . . . . . . . . . . . . . . . . . . . . . . USBR Reg. 7. . . . . . . . . . . . . . . . . . . . . . . Colorado Springs Dept. of Public Util . . . So. Colorado Power Div . . . . . . . . . . . . . . Colorado-Ute Elec. Assoc. . . . . . . . . . . . . Public Service Co. of Colorado. . . . . . . . . See footnotes at end of table. No. . . . . . . . . . . . . . . . . . ..... ;4~:::::::::::::: . . . . . No . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . 7 times last 5 years. ...................... ...................... No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . YeS . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . ~~.:.:::::::::::::::: No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . ....................... Openat59cps.. . . . . . . . . ....................... ....................... No . . . . . . . . . . . . . . . . . . . . Openat59cps.. . . . . . . . . No. . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . ..................... ..................... ..................... No. . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . 2 times last 5 years. 1 time last 5 years. Open at 57 cps . . . . . . . . . . ....................... ....................... ....................... Openat57cps . . . . . . . . . . YCS . . . . . . . . . . . . . . . . . . . . Open at 57 cps . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . ...................... ...................... No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . 2 times last 5 years. No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . . YeS . . . . . . . . . . . . . . . . . . . . ....................... ....................... ....................... YeS . . . . . . . . . . . . . . . . . . . ...................... No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . 0. 0. 0. 0. 0. 2 times last 5 years. 0. 1 time last 5 years. 1 time last 5 years. 0. 0. 3 times last 5 years. Do. 3. I. 3. 3. I time last 5 years. 131 TABLE A-5.-Load and gemration emergency drotiing @&c~Continued c. Practices in WEST REGION-Continued Information lation to the in chapter 2 o ations of the sI in Volume II on Reliability The followi the surveys cc Regional Aclv uniformity in difficult to prl mation receive reserves are a - No. of Occasions Load Shedding Used in 1965 Open Interconnections on Low Frequency Group or System -New Mexico-Texas Group: Public Service Co. of New Mexico. . . . . USBR Reg. 5. . . . . . . . . . . . . . . . . . . . . . Community Pub. Serv. Co.. . , . . . . , . . PlainsElecG.&T.Coop... . . . . . . . . . . El Paso Electric Co. . . . . . . . . . . . . . . . . No..... No..... No..... No..... No..... ....... ....... ....... ....... ....... ..... ...*. .,..* ..... ..... No . . . . . . . . . . . . . . . . . . . ...................... No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . No . . . . . . . . . . . . . . . . . . . 2 times last 5 years. 2 times last 5 years. Do. Sylvania Electric Co’s Front Street #5 (52 Mw) Potomac Elect. Power Co’s Potomac River #3 (102 Mw) and Benning #9 (20 Mw). s Manual generator drooping procedures are used at the USBR Fort Peck, Fort Garrison, and Fort Randall power plants as required. 4 On overload of a specific transmission line. s At one plant to avoid instability. 1 Automatic generator tripping schedules at St. Lawrence covers 1 to 6 units depending on loaded generation levels. Automatic generator tripping at Niagara under study. * The following units are equipped for automatic separation including auxiliaries for the purpose of providing a source of rapid restoration in event of a major shutdown: Baltimore G & E Co’s Westport #4 (74 Mw), Gould Street #3 (107 Mw), Riverside Nos. 4 & 5 (8 Mw each), Wagner Nos. 1 & 2 (140 Mw each), Crane #2 (195 Mw.), Penn- T ABLE A-C-Spinning Predominant Types of Generation Group or System - - .- Emergency Ratf of Response Mw/Min. -- Frequency Bias Mw/.l Cps NORTHEAST reserue practices REGION Time Req’d to pick up 10% Max. Cap. in Min. Minimum Sl -- A- Upstate New York Group. . . . . . . . . . . Steam. . . . . . . . . 230 . . . . . . . . . . . 96 . . . . . . . . . . . . . 5-8.................... New York State Electric and Gas . Steam. . . . . . . . . 10 . . . . . . . . . . . . 12 . . . . . . . . . . . . 6...................... summer-Lar Winter-Large 45 Mw in 4-5 Niagara Mohawk. . . . . . . , . . . . . . . Steam. . . . . . . . . 10 . . . . . . . . . . . . 48 . . . . . . . . . . . . 5 ,,....,..,,........... 45 hfw in 4-5 Rochester Gas and Electric. . . . . . . Steam.. . . . . . . . 10 . . . . . . . . . . . . .............. . , . . . . . 90 Mw in 4-5 Power Authority State of New York.. . Southeastern N.Y. State Pool. . . , . . . . Consolidated Edison.. . . . . . . . . Long Island Lighting. . . . . . . . . . . . Hydro . . . . . . . . Steam , . . . . . . . Steam . . . . . . . . Steam . . . . . . . . 200 . . . . . . . . . . . 272 . . . . . . . . . . . 183 . . . . . . . . . . . 65 . . . . . . . . . . . . Incl. in Niagara Mohawk. 36 . . . . . . . . . . . . 107.4. . . . . . . . . 98 . . . . . . . . . . . . Incl. in ConEd 1.25. . . . . . . . . . . . . . . . . . . 5...................... 5...................... 2....................... 4OOMwinlLargest Unit 1 Obligation = 7 Obligation= 1 Central Hudson.. . . . . . . . . Steam . . . . . . . . 14 . . . . . . . . . . . . 6............. 5...................... Obligation = 4 10 . . . . . . . . . . . . 3.4. . . . . . . . . . . 5...................... Obligation = I 225 . . . . . . . . . . . 116 . . . . . . . . . . . 49& of peak ir 45 . . . . . . . . . . . . 23 . . . . . . . . . . . . 1st 6% in 5 minutes, next 4% in 20 min. to 1 hour. 1st 6% in 5 minutes, next 40/o requires add’l. machine commitment. 5...................... 1st 6% in 5 minutes, next 470 may require starting add’l. units. Orange and Rockland. . . . . . . Steam . . . . . . . New England System. . . . . . . . . . . Steam. . . . . . . . Boston Edison Co. . . . . . . . . . . . . . Steam. . . . . . . . Central Maine.. . . . . :. . . . . . . CONVEX Group. . . . . . Steam. . . . . . . . Steam. . . . . . . . See footnotes at end of table. 132 . . . . . 14 . . . . . . . . . . . . 62 . . . . . . . . . . . . . . .............. 42........: . . . 4y0 of peak ir 4y, of peak il 4o/o of peak ir c. Practices in Spinning Reserve Information concerning spinning reserves in relation to the Northeast power faiiure is included in chapter 2 of this report. More general considerations of the subject may be found in chapter 5 and in Volume II, Report of the Advisory Committee on Reliability of Electric Bulk Power Supply. The following table summarizes the responses to the surveys conducted for the Commission by the Regional Advisory Committees. Lack of complete uniformity in some replies to the survey has made it difficult to prepare a simple summary of the information received. Furthermore, the levels of spinning reserves are affected by factors such as the sizes of units, the combinations of unit types, the system size, and the capacity of interconnections with neighboring systems. The survey results indicate that approximately 30 percent of the systems or operating groups maintained spinning reserves equal to or greater than the largest generating unit, 24 percent carried less than the equivalent of the largest unit, and 46 percent scheduled reserves as a percentage of peak load. Of the latter group, spinning reserves varied from 3 percent to 10 percent of system peak. Since the Northeast failure, more attention has been given to allocating reserves among a larger number of units to obtain faster system response and wider geographical distribution of reserve capacity. reservepractices REGION T Minimum Spinning Reserve and Time Required I Non-Spinning Reserve and Time Required Summ~Largest Unit + 50 Mw (260 Mw) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Winter-Largest Unit+90 Mw (300 Mw) (1) 45Mwin4-5Min . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..*................. 45Mwin4-5Mln . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9OMwin4-5Min . . . . . . . . . . . . . . . . . . ..I Spinning Reserve Unit Allocation PrXtkXS No uniform group policy. Maintain 7 or 8 Mw on each unit consistent with area power flow and security. System security determines day to day unit commitments and reserve distribution schedules. Economy loading. 4QOMwinl-2Min . . . . . . . . . . . . . . . . . . . Largest Unit Loading+200 Mw. . . . . . . Obligation = 73.3y0 available in 5 minutes Obligation= 18.8% available in 1 minute.. ........................ . . . . . . . . ........................ . . . . . . . . No uniform pool policy. ........................ . . . . . . Spread throughout based on response. Economy loading with high limit ........................ . . . . Obligation=4.6% available in 5 minutes. . ........................ control. . . . . . . . . Maintain at least 15 Mw on the largest unit (280 Mw). Economy loading. Obligation=3.30/, available in 2-4 minute 4Q/oofpeakin5min.s . . . . . . . . . . . . . . . . . 2y0 of peak in 5 minutca s. 4%ofpeakin5min.s.. . . . . . . . . . . . . . . . 270 of peak in 5 40/0ofpeakin5min.s.. . . . . . . . . . . . . . . . 4%ofpeakin5min.s.. . . . . . . . . . . . . . . . 2% of peak in 5 minutes 2. 2% of peak in 5 minutes 2. No uniform group policy. minutes *. Unita loaded for maximum economy. .... .... Economic dispatch. Economic dispatch consistent with area security. 133 TABLE A-6.-S’inning - NORTHEAST - Group or System Time Req’d to pick up 10% Max. Cap. in Min. Emergency Rate Frequency Bia L.9 Mw/.l Cps of Response MwJMin. Predominant Types of Generation -- Minimum Spin; -- New England System-Continued New England Electric. . . . . . . . . . Steam . . . . . . . . 40............. 51........... New England Gas and Elect&. . Steam . . . . . . . . 18.. . . . . . . . . . . . Incl. inN.E. Electric. Public Service of New Hampshire Central Vermont Public Service.. Steam . . . . . . . . Purchase power . . 1-5 . . . . . . . . . . . . . . . . . . . . 8. . . . . . . . . . . . . . . . . . . . . . Green Mountain Power. . . . . . . . . . . . Purchase. . . . . . 24............. . . . . . d o . . . . . . . 9 . . . . . . . . . . . . . . 1ncl.inN.E. Electric. 6.............. . . . . d o . . . . . . . . . 2-3 . . . . . . . . . . . . . . . . . . . . Eastern Utilities.. . . . . . . . . . . Penna-N.J.-Maryland System. . . . . . . Steam. . . . . . . . . Steam. . . . . . . . . 7.. . . . . . . . . . . . . . .do.. . . . . . . 47.............. 190.......... . . . . 10 . . . . . . . . . . . . . . . . . . . . . 15-30 . . . . . . . . . . . . . . . . . . 1st 6% in 5 minutes, next 4% unknown. 5-20................... . SOUTHEAST - Florida Group. . . . . . . . . . . . . . . . . . . . Steam. . . . . . . . . 100-150 . . . . . . . . 98 ............ 2-4............ CARVAPool..................... Steam. . . . . . . . . Approx. 200. . . . .............. upto15min... Carolina Power and Light . . . . . . . Duke Power Co . . . . . . . . . . . . . . . . Steam. . . . . . . . . Steam. . . . . . . . . 50-75 . . . . . . . . . . 50 . . . . . . . . . . . . . 34 . . . . . . . . . . . . 58 . . . . . . . . . . . . 10 . . . . . . . . . . . . . 6. . . . . . . . . . . . . . South Carolina Electric and Gas. Virginia Electric and Power. . . . . Steam. . . . . . . . . Steam. . . . . . . . . ................ 50 . . . . . . . . . . . . . 15 . . . . . . . . . . . . 59 . . . . . . . . . . . . 1-15 . . . . . . . . . . . 8.5 . . . . . . . . . . . . . Southern Services. . . . . . . . . . . . . . . . . Steam . . . . . . . . 108 . . . . . . . . . . . . 132 . . . . . . . . . . . 8. . . . . . . . . . . . . . Tennessee Valley Authority . . . . . . . . . Steam. . . . . . . . . Approx. 250. . . . 162 . . . . . . . . . . . ....... EAST CENTRAL - -7 - 1st 8’% in 3-5 minutea, next 10% in l-8 hours. 1st 5% in 3 minutcs, next 10% in 4 hours. 17..................... American Electric Power. . . . . . . . Steam. . . . . . . . . 50-100 . . . . . . . . . 140 . . . . . . . . . . . . Allegheny Power. . . . . . . . . . . . . . . . . . Steam. . . . . . . . . 58 . . . . . . . . . . . . . 38 . . . . . . . . . . . . . Cincinnati Gas and Electric.. . . . Steam . . . . . . . . 24 . . . . . . . . . . . . . 36 . . . . . . . . . . . . . Cleveland Electric Illum. . . . . . . Steam. . . . . . . . . 33 . . . . . . . . . . . . . 44 . . . . . . . . . . . . 1st 3% in 2 minutes, next 10% in 2 hours. Columbus and South Ohio Electric. . . Steam . . . . . . . . 20-35 . . . . . . . . . . 20 . . . . . . . . . . . . . 4...................... Consumers Power-Detroit Edison. . . Steam. . . . . . . . 300 . . . . . . . . . . . ill........... 20..................... Detroit Public Lighting. . . . . . . . . See footnotes at end of table. Steam. . . . . . . . . 13-27 . . . . . . . . . .............. 134 reserve practices-Con REGION-Contin . . .I 4yo of peak in 5 I 4% of peak in 5 I 4oj, of peak in 5 I 4% of peak in 5 tion. 43$& of req’d. r purchase. 4oj, of peak in 5 1 Largest liability, REGION Largest unit ava quency change “/3 of largest unit Refer to Pool. . , Refer to Pool. Refer to Pool s. . Refer to Pool s. Largest unit pra 236 minutes. 2%yo of load+! Mw but never REGION 100 Mw (f< of la minutes. 115 Mwin2mi 60 Mw (5yo of: 33 Mw (K of I; Mw via inte one minute. 40-70 Mw (% to 2 min. 4 5 0 M w t”/3 c minutes. 135, . . . . . . . . . . . . . 267-7810 L-Spinning RTHEAST r pick up p. in Min. rmruc practices-Continued REGION-Continued - Non-Spinning Reserve and Time Required Spinning Reserve Unit Allocation Practices 4%ofpeakin5min.s. . . . . . . . . . . . . . . . . 2% of peak in 5 minutes s. . . . . . . . . . 4%ofpeakin5min.s ..,.............. 2% of peak in 5 minutes *. . . . . . . . . . 4%ofpeakin5min.s. . . . . . . . . . . . . . . . . 4% of peak in 5 minutes via interconnec- 2yn of peak in 5 minutes s.. . . . . . . 2% of peak in 5 minutes via interconnections. ................................. Units loaded for maximum economy consistent with area security. High pressure units are max. base loaded-Reserve maintained on low pressure units. Maintain 20% on the largest unit. Not applicable. Minimum Spinning Reserve and Time Required -- lutes, mm. .......... .......... .......... .......... .......... .......... tion. 43% of req’d. reserve available through purchase. 40/,ofpeakin5min.s . . . . . . . . . . . . . . . . . . Largest liability, presently 500 Mw . . . . 2% of peak in 5 minutess. . . . . . . . . . 287 Mw available in 30 minutes. . . .....Do......................... Units loaded for maximum economy. Economy loading consistent with system security. - UTHEAST .......... .......... .......... .......... .......... .......... ...... .... .......... REGION - Largest unit available before 0.5 cps frequency change. IyZ of largest unit available in 10 X of largest unit. . . . . . . . . . . . . .,. . ;H of largest unit available in 10 50/, on 100 Mw units and larger. 7Hg/, on 75 Mw units. 10% on 50 Mw units and smaller. No uniform pool policy. RefertoPools . . . . . . . . . . . . . . . . . . . . . . . . . RefertoPools . . . . . . . . . . . . . . . . . . . . . . . . . Refer to Pool . . . . . . . . . . . . . . . . . . . . . Refer to Pool. . . . . . . . . . . . . . . . . . . . . Economic dispatch. Economic loading consistent with area security. Widespread distribution. Widespread distribution. Largest unit presently 270 Mw available in 2% minutes. 2% ye of load+j/l of largest liability+300. Mw but never less than largest 1iability.s ............................... minutes. minutes. 1Refer to Pool.. . . : . . . . . . . . . . . . . . Refer to Pool. . . . . . . . . . . . . . . . . . . . . . . . Refer to Pool. . . . . . . . . . . . Refer to Pool.. . . . . . . . . . . . . . . . . . . Widespread distribution consistent with economy loading. Spread over a large number of hydro units whenever possible; otherwise operate steam units at reduced loading. CENTRAL ninutes, l-8 hours. nutes, 4 hours. nutes, 2 hours. .......... .......... i .......... LEGION - 100 Mw (>/6 of largest unit) available in l-2 minutes. 115Mwin2minutes . . . . . . . . . . . . . . . . . . 60Mw(5’%ofpeak)in2~min ......... 560 Mw (96 of largest unit) available in 10 minutes. 19 Mw interruptible in one minute.. . Distribution proportional to unit’s ability to respond. Economic dispatch and unit response ability. 125 Mw in 15 minutes.. . . . . . . . . Economic dispatch with fixed Mw assignment. Fixed Mw assignment. 67 Mw (s of largest unit + 50-200 Mw via interconnections available in 1 min. 73 Mw in 10 minutes.. . . . . . . . . . . . . . Economic dispatch. 33 Mw (g of largest unit + 50 Mw-200 / Mw via interconnections) available in one minute. 4@70 Mw (K to 34 of largest unit) avail. in 2 min. 450 Mw (# of two largest units) in 10 minutes. 220 Mw (s of two largest units) in 10 min. 20-40 Mw in 134 minutes.. . . . . . . . . . . 31 Mw interruptible in 2 minutes. . . . 267-7810-M-10 Economic dispatch consistent with area security and widespread distribution. Fixed Mw assignment. 135 TABLE A-G.-Spinn Predominant Types of Generation Group or System _- .- 1 1 I / EAST CENTR Emergency Rate of Response MwjMin. - Time Req’d to pick up 10% -Max. Cap. in Mii Frequency Bias Mw/.l Cps -- Steam . . . . . . . . . lo-13 . . . . . . . . . . 20 . . . . . . . . . . . . East Kentucky REA . . . . . . . . . . . . . . . . Steam. . . . . . . . . . .............. . . .............. Indianapolis Power and Light . . . . . . . . Steam. . . . . . . . . . 20 . . . . . . . . . . . . 20 . . . . . . . . . . . . Kentucky Utilities . . . . . . . . . . . . . . . . . . Lansing Water and Light . . . . . . . . . . . . Steam. . . . . . . . . . Steam. . . . . . . . . . 12 . . . . . . . . . . . . .............. 26. . . . . . . . . . . . .............. Louisville Gas and Electric. . . . . . . . . . Steam. . . . . . . . . 38 . . . . . . . . . . . . Northern Indiana Public Service. . . . . Steam. . . . . . . . . 90 . . . . . . . . . . . . Ohio Edison Co . . . . . . . . . . . . . . . . . . . . Steam. . . . . . . . . . OVEC . . . . . . . . . . . . . . . . . . . . . . . . . . . 1st 4% in 14 minutes, next 10% in 15-24 H Included in Kentuc 30 . . . . . . . . . . . . .............. 1st 5% in s minute . . . . 360 . . . . . . . . . . . 48 . . . . . . . . . . . . 1st 7% in 5 minutes, next 10% in 2-3 hour Steam. . . . . . . . . . .............. 20 . . . . . . . . . . . . Public Service Co. of Indiana. . . . . . . . Steam. . . . . . . . . 150 . . . . . . . . . . . 38 . . . . . . . . . . . . Southern Indiana Gas and Electric. , . . Toledo Edison Co. . . . . . . . . . . . . . . . . . Steam. . . . . . . . . . . 25:::::::::::: Steam. . . . . . . . . . .............. . . 1st 5% in 36 minute, next 10% in 6 hours. 14 . . . . . . . . . . . . Included in Kentuc Owensboro Municipal. . . . . . . . . . . . . . - - - Southwest Group. . . . . . . . . . . . . . . . . . . West Texas Utilities . . . . . . . . . . . . . Kansas Power and Light. . . . . . . . . Kansas City Power and Light. . . . . Kansas Municipal. . . . . . . . . . . . . . . St. Joseph Light and Power. . . . . . City of Independence . . . . . . . . . . . . Western Farmers Coop. . . . . . . . . . Missouri Public Service Co. . . . . . . Springfield, Mo. . . . . . . . . . . . . . . . . Denton, Texas. . . . . . . . . . . . . . . . . . Brownsville Municipal. . . . . . . . . . . South Central Group. . . . . . . . . . . . . . . Ivijddle South Utilities . . . . . . . . . . . Kansas Gas and Electric. . . . . . . . . Central Louisiana. . . . . . . . . . . . . . . Empire District. . . . . . . . . . . . . . . . . Gulf States Utilities. . . . . . . . . . . . . Oklahoma Gas and Electric. . . . . . Public Service Co. of Oklahoma. Southwestern Electric Power Co. See footnotes nt end of table. 136 SOUTH CENTR. Upto30min.. . . . . . . . ............................. ............................. ............... ............... . ............... . .. . ............... .. .. ............... ............... ............... . . ............... . ............... 12 . . . . . . . . . . . . 19 . . . . . . . . . . . . 47 . . . . . . . . . . . . 5.6. . . . . . . . . . . 2............. 0.25. . . . . . . . . . 2............. .............. .......... ss . . . . . . . . . . . . .............. 25 . . . . . . . . . . . . . . . . . . . 3.................... 13 . . . . . . . . . . . . . . . . . . . 5. . . . . . . . . . . . . . . . . . . . 5.................: . . Inst. . . . . . . . . . . . . . . . . . 4.................... 30 . . . . . . . . . . . . . . . . . . . 25 . . . . . . . . . . . . . . . . . . . Inst. . . . . . . . . . . . . . . . . . ..................... Steam.......................... 195 . . . . . . . . . . . Upto 1 5 m i n . . . . . . . . . /66 . . . . . . . . . . . . 0.5. . . . . . . . . . . . . . . . . . 10 . . . . . . . . . . . . . . . . . . . 10 . . . . . . . . . . . . . . . . . . . 12 . . . . . . . . . . . . . . . . . . . 8. . . . . . . . . . . . . . . . . . . . 2.5. . . . . . . . . . . . . . . . . . 8.................... 15 . . . . . . . . . . . . . . . . . . . .............. .............. .............. .............. . . .................... +OMw(XtimcsI 3-4 minutes. ‘tilities Companl Minimum of 50 available in 23 50 Mw (s time minutes. Cover largest loa minute. 75 Mw (25% o peak) in two t 45 Mw plus ap connections tc able in 34 min 120 Mw (H of 1 minute. 136 Mw availal 75Mw(5%of: . . . . . . . . . . 25 Mw (5 Mw tingencies available in c Utilities Cornpa REGION - Approx. 100. . . Steam.......................... Minimum Spin - - - REGION-Contil - -- Duquesne Light Co. . . . . . . . . . . . . . . . . . reserve practices-Cc 20. . . . . . . . . . . . 5............. 4............. 42 . . . . . . . . . . . . 24 . . . . . . . . . . . . 18 . . . . . . . . . . . . 16 . . . . . . . . . . . . 3% of peak at frequency fa . . . .do . . . . . . . . . . .do . . . . . . . . . . .do . . . . . . . . . . .do . . . . . . . . . . .do.. . . . . . . . . .do . . . . . . . . . . .do.. . . . . . . . . do . . . . . . . . . . do . . . . . . . . . .do . . . . . . Considers Cer connection 1 ning reserve 3% of peak i frequency E . . . do . . . . . . . . . do . . . . . . . . . do . . . . . . . . . do . . . . . . . . .do.. . . . . . . .do . . . . . . . . . do . . . . . . . . . do . . . . . roerue practicts-Continued REGION-Continued - Minimum Spinning Reserve and Time Required - -- 40 Mw (s times 6% of peak less 30 Mw) in 3-4 minutes. Utilities Company Minimum of 50.Mw over peak load hour available in 2% minutes. ( Non-Spinning Reserve and Time Required ‘1 60 MW (g times 4: of largest unit) in 5 Spinning Reserve Unit Allocation Practices -- 20 Mw (45 times 6% of peak less 3( ) Mw) in 10 minutes. Economic dispatch. 20 Mw interruptible in 5 minutes. . Economic dispatch with high limit control to insure a widespread regulating margin. Fixed Mw assignment. 49Mwin5minutes.. . . . . . . . . . . . . . minutes. Cover largest load on any single unit in one I Mw in 30minute.s.. . . . . . . . . . . . . . minute. 75 Mw (25% of largest unit plus 25% of 60Mwin7minutes.. . . . . . . . . . . . . . peak) in two minutes. 45 Mw plus approx. 138 Mw from inter- N o n e . . . . . . . . . . . . . . . . . . . . . . . . . . . connections to cover largest unit-available in 3/z minute. 120 Mw (2/5 of largest unit) available in yS 60 Mw interruptible (s of largest minute. unit) available in 5 minutes. 136 Mw available immediately.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75 Mw (5yc of peak) available in yZ minute Economic dispatch with high limit control whenever possible. Economic dispatch with distribution proportional to unit capacity. Distribution proportional to unit’s ability to respond. 90% in proportion to capability and 10% via economic dispatch. Distribution proportional to power participation ratio. Economic dispatch. None........................... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ................................. 25 Mw (5 Mw regulation + 13 Mw contingencies +7 Mw bias obligation) available.in one minute. Utilities Company kAL 1 REGION -i , ,.. .. L I” 1.. ST ‘I II .... ,.. ... ... ... 53 Mw available in 15 minutes. Maintained on 3 units consistent with economic dispatch and unit’s response rate. - - - - 3% of peak available automatically when 3% of peak available in 10 minutes. . frequency falls to 59.5 cps. . . . ..do................................ .do. . . . . . ..do................................ .do. . . . ..do................................ .do. .. . . . ..do................................ .do. . .. .. . . . ..do................................ .. .do. . . . .. . . . . ..do................................ .. . .. .do. . . . ..do................................ .do. . . - . . . ..do................................ .do. . . .. .. .. .do................................ . .do. . . .. . i::::.do . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .do. Considers Central Power and Light’s inter. . .do. connection worth 10 megawatts of spinning reserve. . do........................ 3yo of peak available automatically when frequency falls to 59.5 cps. . . .do.. . . . .. .. . . ..do................................ . .do. . . . .. . ...’d o . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..do................................ .do . . . . . .. . . .do . . . . . ‘ ... d o . . , . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .do . . . . . .... d o . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .do . . . . . ...’d o . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .do.. . . . .. ...’d o . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .do................................ . .do . . . . . Distribution based on ability to respond before 59.5 cps. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. Do. 137 TABLE A-6.---@innir SOUTH CENTRA Time Req’d to pick up 10% Max. Cap. in Min. Frequency Bias Mw/.l Cps SouthTexasSystem . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . lOO............ . . . . . . . . . . . . . . . . . . . . . . . ve practices--Con! ;ION--Continu Minimum Spinni RI lrgest u n i t . Texas Utilities System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ugest unit + 10 I W E S T CENTRA ,GION - Steam.. Steam.. . 50 . . . . . . . . . . . . 100 . . . . . . . . . . . 131............ 69 . . . . . . . . . . . . . 15 . . . . . . . . . . . . . . . . . . . 5..................... WOMW.. . . ,argest u n i t ‘. Steam... . Hydro. . Steam... Steam... Steam... . Steam... Steam.. Hydro . . . Steam... .............. ...... iii::::: ...... 20. . . . . . . . . . . . .............. .............. ........ ii,::: . . . . . . . . 85 . . . . . . . . . . . . .............. . ....... iii::::: ....... 9.7. . . . . . . . . . . . 44 . . . . . . . . . . . . . ............ is . . . . . . . . . . . . . 30 . . . . . . . . . . . . . 69 . . . . . . . . . . . . . 5.................. 5.................. 5.................... 3.................... ,&4OMw’.... 0%. . . . /z of largest unit Commonwealth Edison.. Eastern Wisconsin UtiIities Upper Peninsula Power. . Edison Sault Electric. . . . . Ill.-MO. Pool. . . . . . Central Ill. Light. Iowa Pool.. . . . . Omaha Public Power. . Nebraska Public Power. . . . Missouri Basin System. . . Upper Mississippi Valley. . . . . . . . .... . . . . . . .,.... ..................... 0.85. . . . . . . . . . . . . . . . . 30 . . . . . . . . . . . . . . . . . . . O~o+20 Mw.. ,argest u n i t . ;y& . . . . . . i% or largest un Largest unit. - WE! EGION - Northwest Power Pool. . . . . . . . . . . . . . Utah Power & Lt. Co . . . . . . . . . . . Idaho Power Co. . . . . . . . . . . . . . . . Grant County P.U.D. . . . . . . . . . . . Puget Sound Power & Lt. Co. . . . Portland General Electric Co. . . . . Tacoma, Dept. of Pub. Util. . . . . . Eugene, Water & Elec. Bd. . . . . . . Montana Power Co . . . . . . . . . . . . . Wash. Water Power Co. . . . . . . . . Bonneville Power Adm . . . . . . . . . . Seattle, Dept of Lighting. . . . . . . Pacific Power and Light Co. . . . . Chelan County P.U.D. . . . . . . . . . Army . . . . . . . . . . . . . . . . . . . . . . . . California-Nevada: PacificGasandElectricCo . . . . . . Southern California Edison Co. . . Hydro . . . . . 138 ............... ............... ............... ............... ............... ............... ............... ............... ............... ............... ............... .............. .............. .............. ............... ............. ............. ............. ............. ............. -I ............. ........ ..... ............. ............... . ..................... ..................... ..................... ..................... ..................... ............... . . . . . . . . . . . . . . . ............... . . . . . . . . . . . . . . . 100 . . . . . . . . . . . . 90 . . . . . . . . . . . . . ............... ...... ..................... ............... ................ ............... ............... ............... ............... ............... 14 . . . . . . . . . . . . ............... ...... ..................... ..................... ..................... ............... ............... ............... ............... ............... ............... ............... ............... .............. 30 . . . . . . . . . . . . 15 . . . . . . . . . . . . 6............. .............. .............. 5 ........... 1;: . . . . . . . . . . . . . . . . Los Angeles Dept. of Water and Power. . . . . . . . . . . Sacramento Muni. Util. Dist. . . . . . . . . . . . . . . . . . . . Sierra Pacific Power Co. . . . . . . . . . . . . . . . . . . . . . . . . SanDiegoGas & Elec. C o . . . . . . . . . . . . . . . . . . . . . . Rocky Mountain Power Pool. USBR Region 6. . . . . . . . . . . . USBR Region 4. . . . . . . . . . . . USBR Region 7. . . . . . . . . . Colorado Springs Dept. of Pub. Southern Colorado Power Div. Colorado-Ute Elec. Assoc. . . . . Public Service Co. of Colorado. See footnotes at end of table. . . . . . . . . . . . Hydro.... ............ . Hydro . . . . Util. . . . . . . . . ............ ............ ............ . . .. . . .. ............. ..................... ..................... ..................... ..................... ..................... ......... ............ ..................... ........ ............. No uniform pool l’i;B.. _...... 200-300 Mw Normally 30%. . l%... . 1%‘ . 1y . . ,..... . . Relies on intero 5y&. . . . Largest unit. 15yo 6, 1%‘ . . . . . . 2%7., . . . . . . Relies on intcrc 1 5 % . . . Largest unit pb 5% of daily pe unit. Largest unit. Included with Largest unit. Largest units n No uniform pc Largest unit 01 107,. . . . 10Yo.. . . Relies on inter 10% 7. . Relies on intet Largest contin ftrz~e practices-Continued .EGION-Continued Spinning Reserve Unit Allocation Practices Non-Spinning Reserve and Time Required Minimum Spinning Reserve and Time Required - Largest unit. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Distribution based on ability to respond befoke 59.5 cps. Each unit is limited to 10% or 25 Mw, whichever is smaller. Largest unit + 100 Mw . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . lEGION 20&300 Mw . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Largest unit 4. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 364OMw’ ........................... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50% . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . j$oflargeatunit6.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . lOQ/o+20Mw . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Large&unit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6% . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..... ................................................................... 5% orlargestunit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Largestunit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Minimum of 3% on each unit. Economic dispatch or widespread distribution. . Do. Do. Do. Do. Do. Do. Do. Do. Do. LEGION - No uniform pool policy. . . . . . . . . . . . . .................................. .................................. .................................. .................................. ................................... .................................. .................................. .................................. .................................. .................................. .................................. .................................. .................................. .................................. No uniform pool policy. . . . . . . . . . . . . . . . l%‘ ................................ 200-300 Mw . . . . . . . . . . . . . . . . . . . . . . . . . Normally 30%. . . . . . . . . . . . . . . . . . . . . . . 1% . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1707 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1% . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Relies on interconnections. . . . . . . . . . . . . . 5% . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Largestunit . . . . . . . . . . . . . . . . . . . . . . . . . . 15%6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . l%‘ ................................ 2%7 ................................ Relies on interconnections. . . . . . . . . . . . . . 15% . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Largest unit plus largest line plus 90 Mw 5oJ, of daily peak but not leas than larges unit. Largest unit. . . . . . . . . . . . . . . . . . . . . . . . . . Included with PG &E. . . . . . . . . . . . . . . . . . Largest unit. . . . . . . . . . . . . . . . . . . . . . . . . . Largest units minus 5y0 of daily peak. . . No uniform pool policy. . . . . . . . . . . . . . . . ‘kargest unit or 5%. . . . . . . . . . . . . . . . . . . . 10% . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10% . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Relies on interconnections. . . . . . . . . . . . . . loo/,1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Relies on interconnections. . . . . . . . . . . . . . . Largest contingency plus load swings. . . . . No unifcmn pool policy. Widespread distribution. .................................. .................................. t .................................. .................................. .................................. .................................. . . . . . .................................. .................................. .................................. .................................. .................................. .................................. .................................. .................................. 139 TABLE A-6.S’innin~ - 7 Emergency Rate Frequency Bias Mw/.l Cps of Response Mw/Min. Predominant Types of Generation Group or System WES’l Time Req’d to pick up 10% Max. Cap. in Min. rem practices-CO EGION-Contin Minimum Spin -. ............................... ............................... ............................... ............................... ............................... ............................... NewMexico-Texaz . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Public Service Co. of New Mexico . . . . . . . . . . . . . . . USBR Reg.5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Community Public Service Co. . . . . . . . . . . . . . . . . . PlainsElec.G&TCoop.. . . . . . . . . . . . . . . . . . . . . . El PasoElectric Co . . . . . . . . . . . . . . . . . . . . . . . . . . . . Arizona-Nevada : Arizona Public Service . . . . . . . . . . . . . . . . . . . . . . . . . . Arizona Electric Power. . . . . . . . . . . . . . . . . . . . . . . . . Tucson Gas & Elec. Co. . . . . . . . . . . . . . . . . . . . . . . . USBRR eg. 3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Nevada Power Co. . . . . . . . . . . . . . . . . . . . . . . . . . . . . Salt River Project . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .......... .......... . . . . . .......... . . . . . .......... ....................... ....................... 45 ............ ....................... See Arizona Put7 dit c Service. . . . . . . . . . . . . . . . .....................do . . . . . . . . . . . . . . . . . . . . . . . . ... . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . . . . . ... . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33............. . . . . . . . . . . . . . . . ................ ................ Largest unit. . . See Arizona Pub d o . . . ..do......... do. . . . Largest unit. 1 Rely on PASNY contract for approximately 125-165 Mw spinning capacity. * 40% of an amount equal to total of spinning plus non- spinning reserve must be available within one minute. s Quick start capacity incIuded in spinning reserve. * Includes a small amount of quick starting capacity. 5 Depends on ir lr additional 3/2 1 eludes 36 Mw i d. Restoration of System Services Further information concerning the needs for power to insure safe shutdown and prompt restarting of generating units appears in chapter 5 and in Volume II. I In recent years, little thought had been given in many instances to the idea that a generating plant on a large interconnected system would find itself without station power to shut down safely and Rstart quickly. The power failure proved otherwise. Since that time, provisions have been planned or ccomplished 1 mergency pow xe were depel The replies 1 2storation of s @em power i ent of those r ions with othc tartup power. Iart on hydro This section is concerned with the sources of power available for restarting generating units and restoring power systems to operation following a widespread outage involving the loss of system power or other usual sources of station service supply. Seine of the problems encountered in the Northeastern part of the United States on November 9, 1965, are discussed in chapter 2 of the report. TABLE A-7.-Practices for rapid restoration of service in the event of total loss of system power or when such loss of ytem power is imminnd TABLE A - 7 . - Means of Obtaining Emergency Startup Power System or Pool - Interconned tt i o n s withL other systen ls - *;*zi”” I Gasoline or Diesel Engines 1 System or Pot 1 - - -. .Northcast Region ‘b+ut region4 Boston Edison Co. . Central Hudson Gas & ElectriC. . . . . . Central Maine Power Co. . . . . . . . Central Vermont Pub. Serv. . . . . . . . Connecticut Light 82 Power. . . . . . . Consolidated Edison 0fN.Y.. . . . . . . . . Green Mountain Powercorp...... 140 ............ ............. X X X X X ............ X X ,X ............ ............... X ............ X ............... ............. X X ............... ............. X X ............... ............. Under study. ............ . . ............... he Hartford Ele LightCo...... ong Island Ligh c o . . ‘ew England Ele tric System. . lew England Ga & Elec. A s s n I.Y. State Electr & Gas. . . . fiagara Mohawk Power Corp. . . rcscrvc practices-Continued REGION-Continued Non-Spinning Reserve and Time Required Minimum Spinning Reserve and Time Required Spinning Reserve Unit Allocation Practices _ .- . .... .... .... .... .... . . . .... .... . . ... kb... 10% . . . . . . 10% . . . . . . 10% . . . . . . 10% . . . . . . 10% . . . . . . 10% . . . . . . ...................................................... ...................................................... ........................................ .............. ...................................................... ...................................................... ...................................................... Largestunit . . . . . . . . . . . . . . . . . . . . . . . . . . . See Arizona Public Service. . . . . . . . . . . . . . ... ..do . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..do . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..do . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Largest unit. . . . . . . . . . . . . . . . . . . . . . . . . . . 3 I-- . . . . . . . . . ... ... . . .. . . . . . . ... ... . . ... ... ... ... .. . . . . interruptible by phone call. 0 Includes interruptible loads. 7 Includes quick starting capacity. 6 Depends on interconnections and reciprocal exchange for additional >h of largest unit. Ill.-MO. spinning reserve includes 36 Mw interruptible by pushbutton and 50 Mw c dy. )wer g of 1 in gas or diesel engine generators, 20 percent have gas turbines, 18 percent isolate units, and 11 percent store steam for quick starting. In addition ,to these arrangements, 5 percent have additional emergency startup plans under study, and 7 percent have gas turbines on order. The following table shows the responses to questionnaires distributed by the Regional Advisory Committees to obtain information on restarting practice. accomplished to insure a dependable source of emergency power for many stations which heretofore were dependent upon network connections. The replies to the survey of practices for rapid n in I restoration of service in the event of total loss of llant system power indicate that approximately 30 pertself cent of those reporting expect to use interconnecI l-etions with other systems as sources of emergency vise. startup power. About 45 percent depend at least in 1 or part on hydro facilities. Twenty-six percent have I zinenl 1 TABLE A-7.-Practices for rapid restoration of service in the event of total loss of system power or when such loss of system power is imminenl-Continued I I System or Pool I .... ,... .... .... .... .... . . . . . . . .... Means of Obtaining Emergency Startup Power -i-- Interconnecttions with other systems Gasoline or Diesel Engines Gas Turbines owk2dro I Separating Steam Storing Steam Unit from System in Boilers for with Auxiliaries Quick Starting Nar~hcast region-Con. IThe Hartford Elcc. Light Co. . . . . . . Long Island Lighting co............... New England ElecI tric System. . . . . . . . . . . New England Gas &Elcc.Assn . . . . . . ._.. N.Y. State Electric &Gas . . . . . . . . . . . . . . . . Niiara Mohawk I Power Corp. . . . . . . . .............. . . . . ........................... . .....,.. . . . . . X . . . x . . .’ :: .............. ............. .............. .I Taking steps to insure cranking power to all stations. . . ............. X x ............................. x ............................. .I x 141 TABLE A-7.-Practices TABLE for rapid restoralion of service in the cven~ of total loss of system power or whm such loss of systm power is A-7.- imminent-Continued Means of Obtaining Emergency Startup Power System or Pool - System or Po Gasoline or Hesel Engine! lnterconnecttions with other systems Gas Turbines -- SC zparating Steam U[nit from System Yvith Auxiliaries - - Ltoring Steam n Boilers for luick Starting East Central Regio Northeast Region-Con Orange & Rockland utilities, Inc.. . . Western Massachusetts Electric. . . Penna-New JerseyMaryland. Power Authority of the State of New York. Public Service Co. of New Hampshire. Rochester Gas & Electric Co. The United Illuminating Co. ,........... ,........... X X X X X X X ,........... X ............ X ............ X X ............ 1 j . . . . . . . . . . . . .............. . ‘X X X . . . . . . . . . . . . .............. . . . .............. . . . . 4 . . . . . . . . . . . . .............. . . .._........... . . X Southeast Region Summary. 9 systems. _.__....... . I31 steam plants have units which can reject load and hold auxiliaries. 7 separate automatically and 74 are separated manually. 13 hydro and 30 steam plants can be started without system. power from West Central R Commonwealth Edison Co. Eastern Wiscon: Utilities. Upper Peninsul Systems. Iowa Pool East Central Region American Electric Power System. Allegheny Power System. cindnnati Gas & Elec. Columbus & Southern Ohio Electric Company. Consumers Power Cc DetmitEdisonCo... Detroit Public Light ing Comm. Duquesne Light Co. East Kentucky Rura Electric Coop. Indianapolis Power ( Light Co. 142 X ........... X ........... Industrial plants. ........... X ........... ........... . . ........... X .............. ........... ........... . . ........... X .............. ........... X X X X ........... .......... X Industrial plants. ........... ........... .......... ........... ........... . . X . . . X . X Nebraska Syste U.S. Bureau of Reclamation. Missouri Basin tern Group. Upper Mississi] Power Pool. . . . . . . . . . . . .............. . . . . Continued Kentucky Utilitic co. Lansing Board 01 Water and Lig Louisville Gas & Electric. Northern Indian Public Service Ohio Edison Company. Pennsylvania PO co. Owensboro Municipal Uti Public Service Company of Indiana. Southern Indiar Gas & Electric The Toledo Edi co. . . X South Central ., X .............. X .............. . . . .............. X Central Kansa Power Co. Public Service Oklahoma. Kansas Gas 8z tric Co. is TABLE A-7.-Practices fw rapid r&oration of service in the event of total loss of system power or when such loss of system flower is imminent-Continued Means of Obtaining Emergency Startup Power -- System or Pool team s for uting - I - - - - l East Central Region’ Continued Kentucky Utilities co. Lansing Board of Water and Light. Louisville Gas & Electric. Northern Indiana ‘Public Service Co. Ohio Edison Company. Pennsylvania Power co. Owensboro Municipal Util. Public Service Company of Indiana. Southern Indiana Gas & Electric Co. The Toledo Edison co. - - -7 I nterconnecttions with C nher systems - - ow&lt-2dro . ............ X . ............ X .. ............ X .. ............ X Gasoline or Diesel Engine: . . . .. . . . separating Stean Unit from System with Auxiliaries ‘ Gas Turbinesi i - - -- ........... . . ............. ........... . . ............. ............. Available in 1968. X .. ....... ........... . . ............. X ....... . . ..*.... ........... . . ............. .. ............ ....... . ............ ....... .. ............ ....... X ....... t* . . . . . . . . ............. . .. .. . ............ . itoring Steam n Boilers for luick Starting - . . . . . X X ............. X ............. . X X ............. .. X Available in 1968. ........... . . . . . . . . . . . .. . X . . . . . . . . . . . .. . X . . . West Central Region Commonwealth Edison Co. Eastern Wisconsin Utilities. Upper Peninsula Systems. owa Pool . . . . Nebraska System. . . U.S. Bureau of Reclamation. Missouri Basin System Group. Upper Mississippi Power Pool. X . ............ X . . . . . . ............ ....... X X X ............ ....... X X Will be operational by mid-1967. ............. . . ........... X ............ . . USBR has only hydro and there is no problem restarting generatic ,n. ............ X X X X X South Central Region Central Kansas Power co. Public Service Co. 01 Oklahoma. Kansas Gas & Electric Co. ............ . ...... X ....... ............ . ............ . ...... X ....... ............ ... ............ . . ...... ....... ............ ... To be installed. 143 TABLE A-7.-Pm&es for rapid restoration of service in the event of total loss of system gown or when such loss of system fiower is imminent--Continued Means of Obtaining Emergency Startup Power System or Pool interconnecttions with Ither systems “w;~~;~o Gasoline or Diesel Engines Gas Turbines - Separating Stean1 s#toring Steam Unit from Systen1 i n Boilers for with Auxiliaries cBuick Starting - - X ............... X c . . . . . . . . . X spare capacity of system and proper maintenance assure rapid restoration of service. ,............ ............. X X ........................... St. Joseph Light & Power Co. ............. ........................... Gulf States Utilities. South Texas Interconnected System. City Power & Light, Independence, Missouri. Western Farmers Electric Coop. City Utilities of Springfield, Miiouri. Southwestern Power Adm. Southwestern Elec. Power Co. Board of Public Utilities, Kansas City. The Kansas Gas & Electric Co. Texas Electric Service Co. Texas Power & Light Co. Dallas Power & Light Co. Central Louisiana Electric Co. Oklahoma Gas & Electric Co. Kansas City Power & Light Co. X ............. 144 System or : West Rcg1 South Central RsgionContinued West Texas Utilities co. Middle South System Empire District Electric Co. City of Denton, Texas. Missouri Utilities Co TABLE A-7.- x x .............. .............. ............. . ............. Available in 1967. ,............ .............. ............. .............. .............. ........................... Being installed. Being studied. ............ . ........................... ............. ............. ........................... Being ordered, X ............ X Use old unit a Edmond St. Station. .............. X ............. All hydro system and there is no problem starting hydro. X Planned for future. ........................... [mplementing plans. _._.......... Understudy.. . . . . . . . Each system has the capability of orderly and safe shutdown of units and providing for fast startup. ,............. . . . . . X Being planned, ............... Adequate facilities available. . ............... ’ . .............. X x Bonneville PO\ Adm.: U.S. corps 1 Engineers. U.S. Bureau Reclamati Public Utility trict #l Che City of Eugen Public Utility #l Grant Cl Idaho Power Montana Pov Pacific Power Light Co. Portland Gen Elec. Co. Puget Sound & Light Cc Seattle Dept. Lighting. ‘~‘acoma Pub Utilities. Utah Power’ co. Washington Power Co. Dept. of Wa Power, L.1 Pacific Gas 8 tric Co. U.S. Bureau lamation 1 San Diego C Electric C Sierra PaciE co. Sacrament0 util. Diit. Southern C Edison Cc Arizona Pu ice Co. Arizona PO Authority Tuscan Ga! Electric ( U.S. Bur. I mation R Means of Obtaining Emergency Startup Power System or Pool Interconncc tt i o n s wit11 other systenIs <separating Stear Gasoline or Diesel Engines Gas Turbines iUnit from Syster Ow&aYro I -- I with Auxiliario .- West Region bnneville Power Adm. : U.S. corps of EngineaS. U.S. Bureau of Reclamation. Public Utility District#l chelanco. =ity of Eugene, Ore. Public Utility District #l Grant Co. [dahoPowerCo..... tiontana Power Co. Pacific Power & Light Co. Portland General Elec. Co. Puget Sound Power & Light Co. Seattle Dept. of Lighting. l’acoma Public Utilities. Utah Power & Light co. Nashington Water Power Co. Dept. of Water & Power, L.A. Pacific Gas & Electric Co. U.S. Bureau of Reclamation Region 2. Ian Diego Gas & Electric co. Sierra Pacific Power co. Sacramento Munic. Util. Dist. southern California Edison Co. 4rizona Public Service Co. 4rizona Power Authority. Tuscan Gas & Electric Co. U.S. Bur. Reclamation Reg. 3. ........... . . I x ......... . . ........... . . . . . . . . . x. . . . . . . . . . ........... I All hydro system, one plant with separate hydro station unit. x ......... ........... ii::::::::: All hydro system and plants self-starting. X:::::::::::I.x:::::::::::/:::::::::::::l::::::::::::::: x ...................................................... x ...................................................... ........................................................ x ...................................................... . . All plants have separate units or other type power for startup. I I I All plants self-starting. ........... . . After present work is completed, all plants will be self-sufBcient. x ......... . . x. . . . . . . i. . . . . . . . I::::::::::::::‘ :::::::::::::: ........... All but two plan ts are self-starting. Planning to make these two self-starting. x ........................ .I .............. /. .............. . . . . . . . . . . . . . . ............. Have house turbine generators. ........... . ........... , All hydro, no external source of power required. .......... x . . . . . .. . . . . . . . . . . ........... x . . . . . . . . . . . . . . . . . . . . . . . . x........... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .x. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ........... . Have a 70 Mw unit with 7.3 Mw house turbine. . . . . . . . . . . . . . .K . . . . . . . . . X ......... . . . IX. . . . . . . . . USBR-hydro X........ TABLE A-7.-Practices for rapid restoration.of service in the event of total loss of system power or when such loss of system power is imminent-Continued T System or Pool Means of Obtaining Emergency Startup Power - Interconnect. tions w i t h other systems Gasoline ad Diesel Engin es 1 -- -- Separating Stearn Storing Steam Unit from Syster n in Boilers for with Auxiliarie! s 1Quick Starting - - Gas Turbines - -- Area pool - Norfkasf regio; Niagara Mc Corp. West Region-Con. Nevada Power Co.. . Salt River Project. City of Colorado Springs. Colorado Ute Electric Assn. Public Serv. Co. of Colorado. Southern Colorado Power Co. U.S. Bureau of Reclamation, Reg. 4. U.S. Bureau of Reclamation, Reg. 6. U.S. Bureau of Reclamation, Reg. 7. El Paso Electric Co. Public Service Co. of New Mexico. Community Public Service Co. Plains Elec. Gen. & Trans. Coop. U.S. Bur. of Reclamation, Reg. 5. . X X X X X ........... X .......... X X .. . .. . Planned. . . X ........... ............ . . . . . . . . . . . . . . New York ! &GasCc . . . . ............ Central Hu Electric ( ............... CONVEX Emergency procedure manual-New Mexico Power Pool. . - I e. Practices and Plans for Use of Digital Computers The electric utility industry has used computers for many years in planning the operation and expansion of generating and transmission facilities. Until recently, these have been analog devices, but the digital computer and its associated technology has developed in about the last ten years to the point that it has replaced the analog computer in many instances, and its use is increasing rapidly throughout the industry. Practically all utilities can now use digital computers to some extent in making system expansion and operation studies, and many have special purpose machines for economic dispatch determination and control. Still others utilize computers to monitor operation and in some instances control the start-up and shut-down of turbogenerators. 146 ............ . . . . . . . . . . . . . . . X All hydro, no external source required. :. ..... . ............ ............... X . . . . . . . . . ., . . . ............ ............... . . . . . . . . . . . . . ............ ............... I I - This section of the report, however is concerned primarily with the use of digital computers on a real-time basis for implementing various phases of power system operation and control. The survey results show that ten major utility systems had real-time computers in use primarily for economic dispatch computations and to direct analog load-frequency control equipment. There were 24 control computers on order, being installed, or definitely planned. Three of these were primarily to perform economic dispatch and load-frequency control, five were to be used for system security monitoring, and sixteen were to perform all of these functions. The following tabulation summarizes the responses to the Regional Advisory Committees’ inquiries concerning plans and practices for these types of application. New Engla System. Consolidat pany of I - TABLE A-8.-Practices and plans Area pool or system Computer type -- for use of digital computers Present uses Northeast region: Niagara Mohawk Power t Corp. I 1!n service.. . . . . On line digital. Yew York State Electric & Gas Corp. Dnorder...... On line digital. Central Hudson Gas & Electric Corporation. Under consideration. Data logging. CONVEX . . . . . . . . . . Planned. . On line digital. New England Electric System. Consolidated Edison Con pany of New York. Planned. . . . . . On line digital. On line digital. In . service. / . Economic dispatch. .............. Economic dispatch and sys tern security. I Future uses Economic dispatch will absorb a very small part of the capability of the computer. Plans are being developed to use the computer to provide guidance and instructions for system operation under both normal and emergency conditions. N.Y. State Electric & Gas Corporation has ordered a digital computer and both computers will be so designed and operated that they will provide maximum mutual benefits. Engineering applications and for expansion of the operations center. The computer will be designed and operated so it will provide maximum mutual benefits with Niagara Mohawk’s computer. Provide printout of the occurrence of breaker operations and alarm conditions on the bulk power supply system. The system will provide more detailed load and voltage data and reduce transmission interruption time by providing faster intelligence and a rapid summary of equipment out of service. Will back up load frequency control. Will display power flows at more tie points and more generating stations than presently available to dispatcher. System data will be available on call from the computer which will permit the dispatcher to locate trouble areas and to take remedial action. The computer will be programed to make security checks of spinning reserves and the status of lines and capacity in specific areas. Decisions on the number and how such checks will be made is under consideration. Same as above. At present, the computer periodically compares tie feeder and line loading with the ratings and signals operator if loads approach or exceed the ratings. It will be possible to determine the effects of tie fee&r and generator outages on the security of the system. The system security check is being programmed to make an analysis of the situation followed by a printout of methods to correct any impending or existing abnormal conditions. The computer checks spinning reserves on demand and is being programmed to predetermine the safe and economical allocation of spinning reserves. _.: ‘1. I TABLE Areapoolorsystem A-8.-Practices and plans for use of digital computers-Continued - - Ex cted date 0r operation Computer type - - Future uses Present uses -- -- Northeast region- .Mortheast region-Con. Ccnsolidated Edison Company of New YorkContinued Long Island Lighting Company. On order. . t Online..... Initially. . . . . . 1. Automatic load frequency control. 2. Economic dispatch. 3. Logging. Programs for the allocation of MVAR’s on Edison’s system are under study. Security checks, spinning reserve allocation and MVAR scheduling can be extended to cover not only Edison’s system but also the pool operation. The following functions are under study: 1. Automatic control to determine need for capacity and automatically send start signals to quick-starting peaking units. 2. Automatic transmission security review for frequency, voltage or load abnormalities with an initial alarm and with the ultimate goal of automatic “make safe” signal via supervisory. 3. Review frequency decay, tie line conditions and initially to alarm for these conditions. The ultimate goal is to send enabling signal to supervisory controlled frequency relays to shed required load. 4. To improve rate of response of generating units. Telemeter data on steam pressure, drum level, etc. may be monitored. This will enable the computer to initiate rapid load changes in times of emergency without endangering the Units. Pennsylvania-New Jersey-Maryland Interconnection 148 Area pool or 1967......... . . On line digital . . . . . . . . . 5. All of these systems under study are ultimately closed loop systems and a great deal of attention must be given to assure that the systems are fail safe. Specific application areas in the initial operation are: 1. Master Schedule-determine the mix of steam, hydro, pumped storage, gas turbine, and diesel units to provide the optimum schedule. Outage Scheduling2. Transmission through remote console, each system has access to computer to simulate any contemplated transmission changes for maintenance. If the outage is scheduled, the system configuration would be changed within the computer for the appropriate period and subsequent evaluations would be made reflecting the effects of all scheduled outages. Pennsylvania-N Maryland In tion-Contin TABLE A-&-Practices Area pool or system .Northeast region--Con. Pennsylvania-New Jersey Maryland Interconnec tion-Continued Rx cted date 0% operation and plansjor USC of digital computers-Continued - Computer type Present uses Future uses -3. Megawatt Monitor-the power flow on selected lines within and between PJM systems and between PJM and neighboring pools will be monitored to determine if any area has reached a limiting value of interchange due to equipment rating or stability. When a limiting condition is found to exist, information to this effect will be printed at the appropriate dispatch center as well as at PJM dispatch center. 4. Control Area Regulation-PJM functions as a single control area and the control signals sent to the individual system’s Automatic Dispatch System equipment will be developed by the computer. 5. Dispatch Lambda-the computer will develop more comprehensive incremental transmission loss. Scaled values of Lambda will be sent to each system’s ADS approximately every five minutes and will result in the system’s generation being dispatched more economically. 6. Pool-to-Pool Scheduling-PJM is interconnected with four neighboring pools and the computer will develop the PJM cost and replacement values used in establishing an hourly interchange schedule with each pool. 7. System Security-this program is initiated when one or more of the PJM frequencies decay to 59.75 cycles per second. Messages will be printed in the PJM office and on the system’s remote console describing the abnormal condition and possible corrective measures. 8. Data Logging and Reports-the teleprocessing capability of the computer and data transmission system makes it suited to take on the additional task of data collection from remotes, data checking, data storing, and data distribution and logging at selected terminals. The data handled relates to Present Condition (unit and transmission line status) Scheduling Conditions (estimated loads and start-stop schedules), Summary Reports (periodic summaries of operating experience and production cost). 9. Accounting-determine the division of savings and preparation of monthly billing statements of energy and capacityinterchanged. 149 f. lnterrupm Support TABLE A-a.---Practices and plans for use of digital computers-Continued Area pool or system -. - - Expected date of operation -- Computer We - Future uses Present uses -_ Data logging and monitoring. East Central region: summary. Several in use. On line digital. West Central region: .............. None in use fo r coordination of information or system control. Summary. Southeast region: summary. South Central region: summary. One in service. On line digital, Three being planned. On line digital. Some in service. On line digital. Some being planned. West region: summary. . . . . . . . . . . . . 150 Four in service. On line digital. Iwo on order, others are being considered by 12 utilities. On line digital. Following tion, it was in an atten Consequeni connection: mental thal A wide s attention 0 turbance, 1: -- Load frequency control and economic dispatch. Load frequency control and economic dispatch. Load frequency control. Economic dispatch. While none of the systems in this region is now using a digital computer for system security checking or directly controlling stability or reliability, much attention is being given these matters. Plans are not far enough along to disclose more than generalities. It will be a year or more before any actions are taken. Systems are actively evaluating the need for such facilities, both from the point of view of expanding computer facilities in existing control centers and planning for future operational coordination on an interpool basis. None, however, are expected to be operational within a year or so. Two of these planned installations will have security monitoring functions. tions assist receive no 1 In order perspective stapces of c I Area regulation. Selective load shedding. Generation and transmission control for economic dispatch and area regulation. 1 Load Frequency control. Economic dispatch. Data collection. One utility has ordered seven digital computers to be installed at modern substations for annunciation and time sequence monitoring. The data from these units will be made available to the system drspatcher by way of a new central dispatch computer. One utility has hired a consultant to study the operating systems and to evaluate the current status of automatic control and data management systems with rcspect to their adequacy. Computers are being studied for system security and supervisory control. 26%: f. Interruptions Avoided lhrough Interconnection Support Following the November 9,1965 power interruption, it was recognized that some systems collapsed in an attempt to restore service to their neighbors. Consequently, there were suggestions that interconnections between systems might be more detrimental than helpful. A wide spread power interruption comes to the attention of everyone within the area of the disturbance, but the instances in which interconnections assist in preventing an interruption usually receive no publicity. In order to put interconnections into their proper perspective, it seemed advisable to document instapces of disturbances which probably would have caused interruptions on the affected system except for the assistance rendered through interconnections. Accordingly, the Commission’s Regional Advisory Committees assembled some information of this nature. Brief summaries of the reports from the six Regions appear in Chapter 3 of this report. It is always difficult to assess the extent of the disturbance which would have occurred if existing interconnections had not been present, but several of the cases reported point conclusively to the value of strong interconnections for improving power supply reliability. Additional information on the value of interconnections may be found in Chapter II of Volume II, Advisory Committee Report on Reliability of Bulk Power Supply. APPENDIX B MODIFICATIONS IN NORTHEAST POWER SYSTEMS SINCE NOVEMBER 9, .1%5 I Introduction During the calendar year following the Northeast interruption, ‘the affected major utilities invested $20 million in new facilities and improvements to protect existing facilities and to prevent a recurrence of a cascading power systems failure. An additional $30 million has been committed for further improvements that are being made as rapidly as procurement and installation schedules will permit. This Appendix lists some of the major improvements that have been made on the Northeast systems. Tabular summaries with a minimum of textual material are provided for those areas of improvement that are discussed in Appendix A. For other types of improvement, representative samples are used to indicate what has been done. In both cases, the information shown is considered typical but does not necessarily provide complete coverage of all system improvements that have been made. It rather demonstrates the general direction that system improvement work has taken as a result of the knowledge that was gained from the blackout experience. power Relaying Power system protection is a highly specialized field. Its purpose is to automatically monitor system behavior or performance and to either give warning or initiate action when predetermined limits of voltage, current or frequency are reached or exceeded. Protective actions involve isolation of damaged or malfunctioning parts of the system; adjustments in generation or load to meet emergency conditions; and the mechanical and electrical protection of equipment during the shut-down process if loss of service cannot be avoided. Various types of relays provide much of the automatic monitoring and action-initiating service that is so essential to system protection. Following the determination of the cause of the November 9 failure, utility systems throughout the area initiated reexamination of their relay applications and settings to assure their adequacy for present and immediate future conditions. The first step, taken by the Hydra-Electric Power Commission of Ontario, was to block out the backup relays (on the five lines out of the Sir Adam Beck No. 2 Station) that had operated to initiate the November 9 disturbance. The next step was to install additional relays which give the lines two zones of protection and increase their load-carrying capability. Blinder relays have been ordered and will soon be installed to replace the interim installation described above. These blinder relays are designed to limit their action to a narrow’beam that parallels and encompasses only the lines out of the Beck plant, with down-system protection relegated to other protective installations. Ontario has been coordinating its studies with those of the Niagara Mohawk Power Corporation and the Power Authority of the State of New York in the investigation of relay systems which would protect against massive power surges into either the United States or Canada. As a result of these studies, an interim installation of overcurrent power directional relays was made, within about 10 days after the November 9 power interruption, at Niagara Mohawk’s Packard Station and at PASNY’s Niagara switchyard on the 230 kilovolt tie-lines to Ontario Hydro. The relay control scheme requires manual adjustment for varying power flows toward Ontario. If a rapid reversal in power flows toward New York should occur and exceed predetermined limits, the relays will initiate the opening of the Niagara tie-line power circuit breakers to prevent a widespread disturbance. Ontario has also installed interim relays on the 230-kilovolt lines, set to operate if there is a significant rate of change of power flow into Canada. Since the direction of flow is normally into Canada, the rate of change appears to 153 be a better guide to protection than the amount of power flow. Ontario is installing automatic relays which will provide the same protection as the interim installation but the relay settings will be automatic. To complete the protection, a tmnsfer trip circuit has Ibeen installed which will act to simultaneously trip selected generating units in the Saunders Hydroelectric Plant on the St. Lawrence River if the ties at Niagara trip out. Typical of other actions with respect to protective equipment are those taken by Central Hudson Gas and Electric Company. The protective levels and margins previously determined desirable for relay settings were re-examined on all the Company’s transmission lines. All the protective devices on the system were field tested at least once between November 9, 1965 and February 1, 1966. The field testing included actual test tripping of all circuit breakers actuated by these relays. Modifications were made to the relaying and control wiring of the Danskammer Steam Station units so as to keep the generator auxiliary load connected to each unit if the unit is automatically tripped from the system. This makes possible continued operation of the turbine generators over an extended period, in readiness to pick up load as required. Conducted tests proved the feasibility of this type of operation. Every. utility in the Northeast has reviewed the adequacy of its protective equipment, and hundreds of modifications or additions have been made to provide optimum protection under all foreseeable conditions, including those studied in detail as a part of the stability analyses described in Volume III of this Report. Emergency Power at Generating Stations Appendix A explained why emergency power is critical at generating stations and other system key locations to provide lights, communications, telecommunication and telemetering, to drive recording charts and to provide other essential functions in case of loss of system service. Because of its extreme importance and the difficulties encountered as a result of lack of emergency service during the power interruption, all utilities in the Northeast gave immediate and special attention to this need and instituted a program of modifications and improvements as necessary. These endeavors involve many types of improvements, depending upon operating conditions within each utility or pool. Table El summarizes major improvements that have been made at generating stations in the Northeast that have capacities of 100,000 kilowatts or mom. These 154 stations represent nearly 90 percent of the total capability of the systems involved. There is no particular significance to the arbitrarily selected 100,000 kilowatt limit for unit size covered by the table except that it provides information to demonstrate that a reasonable portion of the system capability is protected during rundown and can be restarted with a minimum of delay. Communications, Instrumentation, and Data Transmission Uninterrupted communications within a utility system and with interconnected neighboring utilities are critical to service reliability. Communications include both voice and signal transmission, involving ordinary short-wave radio, microwave systems, metallic circuit transmission such as company-owned private lines and Bell system telephone circuits, and carrier-current systems using power transmission lines or insulated shield wires on conventional transmission lines. All require electric power for signal propagation and transmission; thus it is extremely important that adequate auxiliary or back-up power is available at dispatching offices and service centers to insure that both voice communication and recording equipment will operate continuously through emergency periods. Communications and instrumentation go handin-hand. The system dispatcher must rely on data transmitted from instrumentation at remote locations for much of his knowledge of minute-to-minute operating conditions on his system. As automation and computerization progress, reliance on transmitted data from remotely instrumented locations becomes extremely critical. Power system instrumentation is designed also to provide a continuing record of all system conditions, including rapidly changing transients, to permit analysis and reconstruction of what transpires during emergency periods such as those of November 9,1965. Shortcomings or deficiencies noted at the time of the area-wide disturbance included loss of ringing power and signal lights on land line voice circuits, loss of power to drive teletype printers, loss of signal fidelity (accuracy) in telemetered data, insufficient power or lack of back-up for radio and microwave systems, and insufficiency of telephone circuits between dispatchers and plant operators or between dispatch centers on different systems.’ Perhaps one of the more critical deficiencies occurring during the time systems were breaking up on November 9 was lack of a true and complete record of SYE and indicati dual-range t in all cases a the instrume scale. Also, : drive slowed dication of tl In some ins curred both per second was difficul Oscillograpl for “after th out of photc sent the corn Many im munication with major tive channe operating tl significant ( table B-2. Spinning When th night of No state New ‘I reserve coul material ass the Eastern spinning re been expec normal con separated f: not occur, 1 gation of r conducted I System Stu September Report. ) Prior to area was ld generation. ing supplie in the systr 1474 megai percent of in the iirsl creased by ating an ef additional record of system frequency fluctuations. Recording and indicating frequency meters were generally of , dual-range type and operating personnel were not in all cases able to immediately determine whether the instrument was on the compressed or expanded scale. Also, as system frequency decayed, the chart drive slowed down and thus gave an erroneous indication of the duration of low frequency operation. In some instances, wide frequency deviations occurred both above and below the normal 60 cycles per second in such a short period of time that it was difficult to determine which occurred first. Oscillograph records were in some cases deficient for “after the fact” analysis because instruments ran out of photo-sensitive paper and thus failed to present the complete picture. Many improvements have been made in communication systems since the power interruption, with major emphasis placed on providing alternative channels and independent power sources for operating the communication facilities. The more significant of these changes am summarized in table B-2. Spinning Reserve When the initial disturbance occurred on the night of November 9, 1965, the break-up in the up state New York area came so quickly that spinning reserve could not respond rapidly enough to be of material assistance in preserving system stability. In the Eastern New York-New England area, however, spinning reserve in service would normally have been expected to enable the area’s recovery to a normal condition of frequency and voltage after it reparated from the western systems. Since this did not occur, the Commission urged intensive investigation of reserve levels and response. This study, :onducted by the Eastern New York-New England System Studies Group, is covered in their report of September 15, 1966. (See Volume III of this Report.) Prior to the disturbance the load in the “island” irea was 14,678 megawatts with 13,204 megawatts pmeration. The balance (1474 megawatts) was being supplied from external sources. When the split in the system occurred, resulting in the loss of this 1474 megawatts of capacity, 1046 megawatts, or 71.0 percent of the loss was picked up from reserve units In the first 30 seconds. However, losses were in:reased by approximately 175 megawatts, thus cresting an effective deficiency of 1649 megawatts. An additional 40 megawatts was picked up in the next 30 seconds, resulting in a total pick-up in one minute of 1086 megawatts, or 73.7 percent of the loss of capacity and 7.4 percent of the area load. The maximum non-coincidental pick-up in the period 5: 16 pm to 5: 19 pm was 1260 megawatts, or 87.0 percent of the capacity originally lost. However, in holding the interconnected systems together, it is the coincident pick-up that is especially important, and the total coincident pick-up was 1086 megawatts, only 66.7 percent of the 1626 megawatts of spinning reserve thought to be available. This experience illustrates the significance of rapid response of reserve capacities, and provides a basis for evaluating the information presented in table B-3. The criteria and practices with regard to maintenance of spinning reserve vary among the several groupings of Northeast electric utility systems. Merging of power pools such as the recent fonnation of a single pool among the seven principal utilities of New York and the establishment of the NPCC are likely to bring about some modification of the practices in effect at the present time. Generally, however, the operating utilities consider present practices, outlined in appendix A, to be reasonable and adequate, and no significant changes in reserve policies are planned. Table B-3 summarizes 1966 spinning reserve data for the systems directly affected by the November 9 disturbance. load Reduction At the time of the Northeast interruption, no CANUSE system employed automatic load shedding. This is in marked contrast to the situation in some other parts of the United States where it is employed to a considerable degree. (See appendix A) The Spinning Reserve Task Force of the Eastern New York-New England Systems Studies Group concluded that “the spinning reserve policies now in effect provide for adequate spinning reserve. An extreme disturbance, however, may result in separations of the system. Under these conditions, the reserve may not be sufficient in all areas or cannot be picked up fast enough to restore frequency. Therefore, provisions for load shedding should be initiated by automatic and/or manual means quickly enough to prevent further deterioration of frequency and voltage. If this cannot be accomplished, further separation of systems or areas should be considered.” In February 1966, the Eastern New York-New England (ENY-NE) System Studies Group appointed a Station Operation Task Force to investi155 T ABLE B-l .-Emergency Pawn Su@lies-Generating System and Station Generating Stations 100,008 kw and over Type Boston Edison Co.: Edgar . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . L street. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Mystic . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Steam. . . . . . . . . . . ..do . . . . . . . . . . . . do . . . . . . . . NewBoston . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Central Hudson Gas and .Electric Corp.-Danskammer . Rundown Auxiliaries Added since 11/9,65 Size-kw Stations with ( Rel Capacity kw Diesel. . . . . . . . . .............. Diesel. . . . . . . . . 150 ............ 150 ........... ........... .... ....... . . . . do . . . . . . . . . . . . do . . . . . . . . 150 .......... . . . . do . . . . . . . . .............. ............ ........... 457,860 225,750 618,750 Central Maine Power Co.: Mason . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . W.F.Wyman . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . do . . . . . . . . 146,500 213,636 Diesel. . , . . , . . , 108 Consolidated Edison Co.: ArthurKill . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Astcmia . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . EastRiver . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59thstrcct . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . HellGate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IndianPoint . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . HudsonAvenue . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . do. . . . . . . . . . . . do . . . . . . . . . . . . do . . . . . . . . . . . . do . . . . . . . . . . . . do . . . . . . . . Nuclear. . . . . . . Steam ......... 376,200 1,530,600 833,652 149,500 646,250 275,000 845,000 . . ..do . . . . . . . . . . ..do. . . . . . . . . . . . do . . . . . . . . . . . . do . . . . . . . . . . . . do . . . . . . . . . . . . do . . . . . . . . . . . . do . . . . . . . . ............ ............ 1, 200 ............ 600 ............ ............ KentA+enue . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Ravenswood . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74thStreet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ShermanCr . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Waterside . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .... do . . . . . . . . . . . . do . . . . . . . . . . . . do. . . . . . . . . . . . do . . . . . . . . . . . . do . . . . . . . . 107,500 1,827, 700 269,000 216,500 712,250 . . ..do . . . . . . . . . . . . do . . . . . . . . . . . . do . . . . . . . . . . . . do . . . . . . . . .............. ............ . ........... . ........... . ........... . ........... Eastern Utilities Associates-Somerset. . . . . . . . . . . . . . . . . . ..do . . . . . . . . 325,ooO .............. . ........... Holyoke Water Power Co.-Mt. Tom. . . . . . . . . . . . . . . . . . . . do . . . . . . . . 136,060 . . . . . . . . . . . . . . ............ Long Island Lighting Co.: E.F.Barrett . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . FarRockaway . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Glenwood . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . PortJelIerson . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . do . . . . . . . . . . ..do . . . . . . . . . . . . do . . . . . . . . 375,000 147,236 397,272 467, ooo .............. .............. .............. .............. . ........... ............ ............ ............ Diesel. . . . . . . . . .............. - - 4al ............ . . . ..*........ . . . . . . . . . . . . Units at ea varying fi 600 kw e; units hav since 1 l/Z 24 diesel 10,200 kv All units p: auxiliaric 1965. New England Electric System: Comerford . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . S.C.Moore.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Hydro . . . . . . . . Brayton Point. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SalemHarhor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Steam. . . . . . . . . . . ..do. . . . . . . . 482, 040 319,938 .............. .............. ............ ............ .......... .......... Manchester . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . slnlthstret . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . do . . . . . . . . . . ..do . . . . . . . . 147,000 206,625 .............. .............. ............ ............ _..._..... Diesel. . . . . . . . . 100 New England Gas and Electric Association-Cannon St. . 156 . . ..do . . . . . . . . . . ..do . . . . . . . . St&ions with ca@ci~ of 100 megawatts or mOr6 1Restart Service Added or Improved Since 1 l/9,65 - Remarks - Type - -. spacity kw ........................ . .................. .......................I Gas Turbine. . . . . . . .......................! isolated Unit. . . . . . . ........... 18,594 50, ooo . . . . . . . . . . . . . . . . . . . . . . . . . .................. ........... . . . . . . . . . . . . . . . . . . . . . . . . 1Diesel. . . . . . . . . . . . . 5,500 . 1Hydro . . . . . . . . . . . . . . . . . do . . . . . . . . . . . . Units at each station varying from 150 to 600 kw each. Fourteen units have been added since 1 l/9/65. Total of 24 diesel units provide 10,200 kw. ........... ........... Gas Turbine. . . . . . . Isolated Unit . . . . . . . ,Gas Turbine (2)r. . . 16,000 7,500 34,204 ,GasTurbine . . . . . . (Stored Steam to start Gas Turbine (2)r. Turbine (2)r. .. IGasTurbine...... . IGas Turbine ($1. .. ‘ Stored Steam. . . . . IGasTurbiner...... . IGas . Isolated Unit.. . . .,. . IHydra . ............ Remarks 16,575 7, 500 unit 35,696 29, 600 16,000 37,188 .......... 16,575 Fuel oil pump converted to DC operation. Relaying installed to isolate #3 unit to provide start-up for station and system. Also can be direct-connected to Sturgeon Pool and Never-sink Hydro plants. Generator aux. load direct-connected to each unit to permit no-load operation. Restart power available, with emergency switching, from system hydro stations. Restart units can be switched to any unit. All rundown equipment starts automatically. Some house generators wired to carry some auxiliaries. Start-up power at some stations provided by nearby steam-heating plants. Unit isolation under study. Ravenswood plant has steamdriven oil pumps, as well as battery-cranked diesel auxiliaries. All stations can be restarted without system service. Switching arrangements to isolate units at 59th St., 74th St., and Waterside. . . . . . . . . . . . . One small unit in plant can be isolated and connected to low-voltage bus to provide cranking power for other units. . . . . . . . . . . . . Restart power provided by direct line to Cabot hydro station. Turbine. . . . . . . . . . . do . . . . . . . . . . . . . . . . do . . . . . . . . . . . . . . . . do . . . . . . . . . . . . (ks All units provided with auxiharies on Nov. 9, 1965. 18, 600 15,000 16, 000 15,009 ........... . . ........................ 1Diesel (4). . . . . . . . . ........................ . . . . d o . . . . . . . . . . . 11,000 10,000 Diesel . . . . . . . . . . . . . .da . . . . . . . . . . . 2,750 2,750 Stored steam. . . . . . .......... ....................... . ....................... . . All units equipped with dc backup oil pumps. Gas turbine unit at Southampton station can be used for cranking power at steam stations. Far Rockaway unit to be isolated to insure service to New York Transit Authority Minor changes in sta. service assume adequate oil pressure and provide faster availability of sta. prime movers in case of emergency. Diesel equipment located at Gloucester, connected by underground cable. Roth Manchester and South St. Stas. can be fed from either emergency generator. Restart after short outage can be provided from stored steam. System service required for cold restart. T ABLE B-1.-E mergctuy Power Supplies-Generating Stations with Capacity - Generating Stations 100,000 kw and over System and Station Rundown AuxiEariea Added since 11/9,65 - - Typt Size-kw Tvpe . . . ..do . . . . . . . . . kw - - -- New York State Electric and Gas Corp. : Goudey....................................... ICapacity Re 145,750 .............. . . ........... Emergency all statio: . . . .do . . . . . . . . . . ..do . . . . . . . . 160,000 270,000 .............. . . ........... .............. . . ........... . . . . .do . . . . . . . . . . . . do. . . . . . . . . . ..do . . . . . . . . . . ..do . . . . . . . . 376,000 Klo, 000 628,000 828,000 Diesel. . . . . . . . . . . . .do . . . . . . . . . . ..do . . . . . . . . . . ..do . . . . . . . . 700 700 700 700 . . . . . . do . . . . . . . . 209,636 propane. . . . . . . 100 .......... ...... . . ...... . . ...... . . ...... . . ....... . . . . ..do . . . . . . . . . . . . do . . . . . . . . . . ..do . . . . . . . . . . ..do . . . . . . . . . . ..do . . . . . . . . 479,000 176,000 326,400 421,996 216,750 .............. .............. .............. .............. .............. ........... ........... ........... ........... ........... .......... .......... . . ........ .......... : ......... . . . . . . do. . . . . . . . 294,520 Stored Steam Hydro. Hydro . . . . . . . . 240, m 1,953,900 912,000 Hydro . . . . . . . . . . . . do. . . . . . . . . . . .d a . . . . . . . Steam. . . . . . . . . . . . .d o. . . . . . . . 113,636 190,000 .............. .............. . . . .d a . . . . . . . . . . .d o. . . . . . . . 206,200 252,600 .............. .............. . . . .do. . . . . . . . 261,042 .............. . . ..d a . . . . . . . . . ..d a . . . . . . . 146,250 155,500 .............. .............. Nuclear. . . . . . . 185,000 .............. Greenidge . . . . . . . . . . . . . . . . . ............ Mill&n. . . . . . . . . . . . . . . . . . . ............ . . . . Niagara Mohawk Power Corp. : oswego. . . . . . . . . . . . . . . . . . . . Albany . . . . . . . . . . . . . . . . . . . . Dunkirk. . . . . . . . . . . . . . . . . . . C. R. Hun&y. . . . . . . . . . . . . . ............ ............ . . . ............ . . . . ............ . , . . Northeast Utilities W. Springfield . . . . . . . . . . . . . . . . . . . . . . . . Devon . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Montville . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . NorwalkHarbor . . . . . . . . . . . . . . . . . . . . . . . . Middletown. . . . . . . . . . . . . . . . . . . . . . . . . . . . So.Meadow...‘ ......................... Orange and Rockland Utilities, Inc.-Lovett . . Power Authority-State of New York: Lewiston. . . . . . . . . . . . . . . . . . . . . . . . . . Moses Niagara . . . . . . . . . . . . . . . . . . . . Moses Power Dam . . . . . . . . . . . . . . . . . Public Sexvice Co. of New Hampshire: Merrimack........................ schiller........................... Rochester Gas and Electric Corp.: RochesterNo.3... . . . . . . . . . . . . . . . . Rochester No. 7. . . . . . . . . . . . . . . . . . . Yankee Atomic Electric Co.-Rowe.. . . . . . . . . . . . . . 1 . . . .... . ... ... .... ,. . . . . f . . . Unite-d Illuminating Co. : Bridgeport Harbor. . . . . . . . . . . . . . English . . . . . . . . . . . . . . . . . . . . . . . . . . . Steel Point. . . . . . . . . . . . . . . . . . . . . . . . . ,. ... .... .... . ,. . ,. . . - 1 On order. 1.58 . . . . do. . . . . . . . . . . . da . . . . . . . . . . . . . . . . ........... ........... .......... .......... .......... .......... 1 7 5 ........... ........... ........... .......... .......... .......... ........... ........... ........ ........ . . ........... ........... .......... .......... . . ........... . . . . . . . . . . . . ........... ........... . . ........... . . - .......... .......... with Cajacity of 700 megawatts or mwcContinued - R.estart Service Added or Improved Since 11,/g, 65 Type Zapacity kw H[ydro . . . . . . . . . . . . Stored steam .......... ....................... . . . . . . . . . . . . . . . . . . . ....................... Dhx.L . . . . . . . . . . . . .......... ....................... HJydro . . . . . . . . . . . . ....................... . ..do . . . . . . . . . . . . ....................... . . . ..d 0.. . . . . . . . . . . . . . . ..d 0.. . . . . . . . . . . .......... .......... .......... .......... Cranking power for steam station provided by hydro plants, with facilities for rapid sectionalizing to provide direct line between hydro and steam plants. New 115/35 transformer added at Albany Sta. to provide this service. Stored steam used for restart after short outage. Standby air pressure tanks provided at hydro plants to open gates should normal station service be lost. ........................ LJnit Isolation . . . . . 100,009 Start-up power also provided by direct line to Cobble Mountain hydro station ........................ Gla9 Turbine. . . . . . . ........................ c1iesel. . . . . . . . . . . . . ........................ G)as Turbine. . . . . . . ........................ . . . ..d 0.. . . . . . . . . . . : ....................... . . . ..d 0.. . . . . . . . . . . 15,370 5, 500 16,320 18,000 10, Otnl ........................ I-I lydro. . . . . . . . . . . . . .......... Start-up power available from Mongaup River hydro plants. 50 kw start-up emergency unit installed at Mongaup. .......................E Iydro . . . . . . . . . . . . ........................ . . . . .da . . . . . . . . . . . ........................ . . . . .do. . . . . . . . . . . . .......... .......... .......... Generating units at each plant wired to provide station service completely independent of any transmission system connections or normal source of station service power. ........................ . . ... do. . . . . . . . . . . . ........................ . . . . . do. . . . . . . . . . . . .......... .......... Stations can be started by direct service from hydro stations. ........................ . . . ..d a . . . . . . . . . . . ........................ . . . . .da . . . . . . . . . . . .......... .......... Beebee steam station units can be started from nearby hydro plant, to start restoration of service in case of system failure. 120,000 Start-up power provided to Steel Point plant by 138 kv direct cable. No cranking auxiliary. Tie to Bridgeport being considered. Direct connection to emergency power supply at Bridgeport Harbor. -Emergency generators at all stations. ........................ cJnit isolation; jet Stored steam arrangements available for prompt restart. Service from hydro interconnections or Milliken station required for cold restart. Two units, wired to both stations. 5, 500 turbine. ........................ . . . . . . . . . . . . . . . . . . . ........................ . . . . . . . . . . . . . . . . . . . .......... .......... ....................... . . . . . . . . . . . . . . . . . . . . .......... 10,000 installed in 1962. 159 T ABLE B-2.-Communications, Instrumentation and Data TransmissionSign$icaficant System Improvements Since Nov. 1#.5 System Operator’s communications and aids Recording equipment Boston Edison Company. . The communications system operated satisfactorily during the November 9 emergency. The system has been analyzed and it was concluded that no significant changes are necessary. The leased circuit system is backed up by radio communication equipment. Expanded-scale frequency meters added to monitor 115 KV transmission. Two additional radio frequencies assigned, one to be used solely for emergency, the other for mobile equipment. Automatic voice alarm system provided between each of the four operator’s offices, with alarm also provided in other southeast New York operator’s offices. Emergency communications power provided at all key stations. Direct leased telephone lines added between control center and Danskammer Station. Computer system under consideration. Signal system provided to warn all station operators when emergency exists, and also to alert system operators of neighboring utilities. Two separate leasedwire channels available to all generating stations. Signalling is independent of system AC supply. At energy control center, 100 KW diesel provides emergency lights, instrument drive and other emergency service. Audible warnings and printouts of tie line overloads are provided by computer. Alarm system warns when inter-ties within Southeastern New York companies become overloaded. Clearchannel radio contact available to all company stations at all times. Emergency power provided at operations center by 150 KW d&cl generator. Largescale indicating meter added to provide more easily read frequency information. Single-range meters installed. Meter drive3 at Millbury dispatch center provided by 125 KW gasoline gcnerator and 50 KW diesel generator. Basic communications system completely operative without system service. Ringing service now provided independently from system service. Leased line and carrier channels provided adequate communications during emergency. Independent power supply for ringing and signal lights has been arranged for. Unlisted telephone numbers provided at key stations. Radio system changed to dual frequency. All operating centers (23) and dispatching centers (13) equipped with emergency power sources. Direct telephone communication to neighboring systems has been provided. “Line Load Control” insures availability of needed service during emergencies. Single range frequency meters provided at dispatch centers. Emergency battery and AC emergency power provided at dispatch center. Additional radio equipment provided. All visual and audible signals connected to auxiliary power supply. Unlisted telephone numbers provided. Stations provided with quick connections to mobile generators. Computer provides line data and other control information. Instructions and training on restoration of service without normal communica- Recording equipment is provided with back-up power to provide continuous record during emergency. Central Hudson Gas and Electric Corp. Consolidated Edison Company of New York Inc. Lung Island Lighting ComPanY- New England Electric Systems. New York State Gas and Electric Assn. Niagara Mohawk Power Corporation. tions have been given to all operators. Additional recording meter installed. All recording equipment at key stations provided with emergency power independent of system service. Battery & emergency AC power supplies insure continuity of records without system service. Two additional frequency meters installed at control center to provide additional records. Oscillograpbs have been modified to provide longer postincident records. Dual-range recording frequency meters provided, with emergency power supplies at dispatch center and other major stations to insure continuity of records. TABLE B-2.S! Northeast U Orange and Utilities, I Power Auth State of N Rochester C fJm=Y Recording devices provided with auxiliary power supply to insure continuity of record under emergency conditions. Emergency generating equipment at key station assures power supply for recorders and telemetering under all conditions. Dual speed meters provided at all division control centers. Auxiliary power supplies installed at district operators centers and other key locations to insure power for data transmission. gate wha thermal I on Novel vestigate System 01 dition of : the Nove an analyl Force co ernors re position too mud consideri opinion ( abnorma TABLE B-2.-Communica~ion.r, Indnmwhtion and Data Tran.rmissimr4i’n$cant Syskm Improuemcnt~ Since JVm. 9, 1965-Continued System Operator’s communications and aids Northeast Utilities. . . . . . Reserve alarm system provided at CONVEX control center at Southington. Warnings provided for transmission line flows in excess of normal limits. Telephone system revamped to provide direct-line communications with all outlying manned stations either individually or as a group. A “management” center with separate unlisted lines provided to separate management and operations communications during emergency periods. New emergency power supply installed at dispatch center and at other major stations. New dual-range, multi-speed meter provided at dispatch center. Audio and visual enunciator signals indicate change in range at 59.7 cycles. Private leased telephone lines installed between dispatch and other major operating stations. Direct communications provided to neighboring utilities. Emergency alarm indicates tie line loads approaching limits at major interconnections. Single-range meters provided at each station. Communicat+ improvements will provide assured service to Syracuse control center to eliminate problems of the type that developed on’ November 9 in connection with initiating needed switching operations. A battery powered communications power source has been installed at PASNY New York City Oflice. Emergency radio power provided at all stations. Emergency lighting installed in Andrew control center, and new 60 kw power unit installed for additional emergency power. Unlisted telephone numbers assigned to key personnel and key stations, direct line telephone circuits between stations not dependent on telephone company switchboards. Battery system provided for emergency telemetering. Dual-route microwave channels leased from telephone company for some relay-control activities. Orange and Rockland Utilities, Inc. Power Authority of the State of New York. Rochester Gas and Electric Company. gate what had occurred in the various operating thermal plants at the time of the system disturbance on November 9, 1965. The assignment was to investigate specifically the reaction of the ENY-NE System operating thermal plants to the unusual condition of frequency and voltage which existed during the November 9 system disturbance. On the basis of an analysis of the information obtained, the Task Force concluded that in general the turbine governors responded properly by going to the wide open position with the drop in frequency, but there was too much load for the available generating facilities considering their possible rate of response. It is&e opinion of the Station Operation Task Force that abnormal system conditions resulting in a rapid fre- Recordii equipment Wide-range frequency meter provided with speedup arrangement for emergencies. Butane “tertiary” unit keeps recording charts moving for few seconds between loss of system service and full-speed operation of automatic auxiliaries. New emergency power supplies pro- vided at all major stations to provide continuous service to recording devices under any foreseeable system conditions. New metering equipment provides improved records. Rearrangements in station service facilities will insure continuity of records during emergency periods. Delay devices being installed on oscillographs to provide one or two cycles of pre-fault information. Fly-wheel-inertia provided with station power system to give continuous records during changes of station power source. Recording frequency meters installed on split busses to provide record in case of loss of service on part of system. Meters are dual range. Totalizing meters added to provide tie-line data. Additional oscillographs have been installed, and time-stamp facilities installed. quency decay call for an immediate, well-planned fully coordinated and automatic or manual load shedding procedure to quickly arrest the frequency reduction. This should be accomplished prior to a low frequency of 58.5 cycles which, according to the major turbine manufacturers, is the critical frequency for continuous full load operation of turbines. Recently, the Northeast Power Coordinating Council adopted an automatic load shedding program. The specifications for this program are summarized in chapter 2, of this report. The load reduction policies which are currently in effect, and will continue until the automatic system is installed, are indicated in table I34. 161 TABLE B3.--Spinning Rmr~cs, Northeast Power +tms - Group or System 1966 S tern r hi” 7 S stem apa6. I12bztJ6 Capac- Capacity of ity of LEys’ Lp!Ke;’ M”w MW Coord. Group for Reserve Requirement 4 Re uired Avar9ability Basis for Reserve Requirement _BostonFdiinCo..... Central Hudson Gas & Elec. co. Central Maine Power co. Central Vt. Public krv. Corp. Consolidated Edison co. Eastern utilities Associates. Green Mountain Power Corp. Holyoke Water Power co. Long Island Lighting co. New England Electric systems. New England Gas & Elec. Assoc. N.Y. State Elec. & Gas Corp. Niagara Mohawk Power Corp. Northeast Utilities. . . . Orange & Rockland Utilities, Inc. Power Authority-State of N.Y. Public Serv. Co. of N.H. Rochester Gas & Electric Corp. United Illuminating co. Yankee Atomic Electric co. c rota1 (‘1 1 -E System In one minute - Boston Edison -s Percent MW 82 53 40 ... 32 0 45 14 34 40 13 14 6 40 2 9 923 . . .. 0 180 23 40 7 6 -- 1,442 393 1,742 340 359 147 469 293 ECCNE NYPP 559 703 114 214 ECCNE 15.......... Max. Pool u n i t + 2OfI. 6% Pool . . . . 199 98 13 31 ECCNE 6% Pool.. . . . 6, 154 7,477 1,028 1,828 NYPP 382 408 125 325 ECCNE Max. Pool U n i t + 2Of1. 6% Pool. . . . . 147 83 17 30 ECCN’E 6% Pool.. . . . 5 40 2 6 136 136 ECCNE 6% Pool. . . . . 4 40 2 2 187 . .. 0 187 106 40 40 40 72 - (‘1 1,555 1, 606 188 467 NYPP 1,980 1,895 241 482 ECCNE Largest Pool Unit + 2Ot). 6% Pool.. . . . 330 251 33 131 ECCNE 6% Pool.. . . . 19 40 8 18 1,150 847 135 270 NYPP 45 25 11 10 3,987 3,067 218 828 NYPP 165 . . .. 0 45 2,934 293 3, 106 368 240 180 479 295 ECCNE NYPP 131 37 40 ... 50 0 50 10 636 3, 200 150 1,954 .......... Pool Peak + 300. Pool Peak + 300. 6% ECCNE. Largest Pool Unit + 200 ‘. 20% of total. 400 50 200 200 476 471 114 190 ECCNE 6% Pool.. . . . 28 40 11 24 592 502 82 253 NYPP 90 . . .. 0 10 261 ECCNE Pool Peak + 300. 6% Pool. . . . . 35 40 14 14 . . .. .... 605 (9 180 176 (9 .... ...... 0) - ............ . . ..... Central Huds Central Mair Central Verr Consolidated Eastern Utll Green Mom Power. Holyoke Wa Power. Long Island Lighting. - 1 In each case, total reserve requirement is to be provided in five minutes. s CONVEX totals shown under Northeast Utilities. s Included above. 4 Coordinating Groups are listed in Appendix C. New Englar tric Syster New Englar and Elect N.Y. State. and Gas. 1 LD--L 162 E TABLE B-4.--Load System fethod I Reduction Procedures; Utilities Affected by the .Northcast Power Zntcnuption Procedure T Percent reduction 60-59 -- cycles 59-58.5 cycles Other hvised operaor9 in- Remarks StIllC- tions -- BostonEdison...... LD Manual.. . 10 15 ................ Central Hudson. . . . . 1 ;D Manual. . . 10 15 Yes Central Maine. . . . 1 >D 10 15 Central Vermont. . . . Consolidated Edison . 1 >D ’i7R 1 ;D Manual and Automatic. Manual.. . Automatic and Manual. 1perator’s instruct provides for load reduction up to 108 Mw, or ovu 3070 of system peak, in case of emergency. ............... 10 5 5 15 3 12 ............... ................ {es [es Eastern Utilities. . . . Green Mountain Power. Holyoke Water Power. Long Island Lighting. 1 ;D 1 ;D Manual. . . Manual. . . 10 10 15 15 ............... ............... [es (es LD Manual. . . 10 15 LD VR Manual. . . Manual. . ...... ...... 15 3 New England Electric Systems. New England Gas and Electric. N.Y. State Electric and Gas. LD Manual.. . LD LD VR tea Under-frequency relays installed to activate automatic voltage reduction mechanism. System involves 101 relays at 15 stations. Reduction is at rate of 1 yo per 1 o/o reduction in voltage. YCS YCS YCl 15 Instructions to op erators provide for combined voltage reductio & load dropping, after freq. drops to 58.5 or lower, up to 600 mw (35%). ............... Manual. . . 15 . . . . . . . ...*..... YC.9 Manual.. . Manual. . . 15 ............... YCS 1 LD-Load dropping; VR-Voltage reduction. Load shedding controlled from buttons in diipatch office, with one button for first lo?&, a second button for next 15%, a thiid button to initiate tie-line opening if frequency is below 58.5 cycles and falling. Two additional buttons provide relief above 25% if necessary. Protection provided to insure against accidental load shedding. New supervisory control equipment provided to permit load dropping from dispatch center. If frequency continues to drop below 58.5 cycles, the interconnection with Con Ed will be opened and additional system load will be dropped until frequency has been stabilixed. YCS Automatic load dropping under study. 163 TABLE H.--Load Reduction Procedures; Utilities Affected by the Northeast Power Znterrupion-Continued - ISystem Method Procedure Percent reduction 60-59 cycles 59-58.5 cycles Other Revised operators instructions Niagara Mohawk. LD Automatic and Manual. 10 15 ................ YeS Northeast Utilities.. LD Manual.... 10 15 ................ YtS Orange and Rockland. LD Manual and Automatic. 10 15 Load dropping proceeds to 100 mw total, which is at least 30% of load. YeS PASNY. . . . . . . . . . LD Manual.... 10 15 ................ YeS Public Service of New Hampshire. Rochester Gas and Electric. United Illuminating LD Manual.... 10 15 ................ YC3 LD Manual.... 10 15 ................ YCS LD Manual.... 10 15 ................ Yt!S 1 LD-Load dropping; VR-Voltage reduction. Remarks Automatic equipment drops up to 850 megawatts of industrial load at various frequencies down to 58.5 cycles. Automatic load dropping under study. Operator’s instructions indicate switches to be opened for each level of load relief. At 59.5 cycles Mongaup hydra unit isolated from system. Most PASNY power sold to other utilities, so load shedding, per se, not significant factor in PASNY operations. Procedures for load shedding under study. Mechani Electric of and opera coordinati “formal p ma1 powe more elecl coordinatt economy ; bined loac rangemen capacity a procedure requireme opinion as can be inc so defined groups of In addi a number tern plan1 vary wide tiveness. 5 for the cc statistical and plana cilities. 0 ing about planned 5 present ti formed w system rel Chapte the print and short groups nc ing areas and the 1 bers of ea shown in variety APPENDIX C MAJOR COORDINATING ORGANIZATIONS Mechanisms for Coordination Members of Major Formal Power Pools Electric power systems have developed a wide variety of mechanisms for coordination of planning and operation. The most fully developed form of coordination at the present time is the so-called “formal power pool”. In the present context, formal power pool should be taken to mean ,two or more electric systems which are interconnected and coordinated for the purpose of achieving greater economy and reliability in the supply of their combined loads in accordance with a contractual arrangement which provides for the exchange of capacity and energy among them and establishes a procedure for the sharing of their generating reserve requirements. There may be some difference of opinion as to whether one or a few individual groups can be included within the concept of power pools so defined, but it is clear that there are at least 18 groups of systems that can reasonably be included. In addition to *the formal power pools, there are a number of organizations that engage in inter-system planning on an area or regional basis. They vary widely in size and functions as well as effectiveness. Some appear to be little more than centers for the collection, organization and distribution of statistical information concerning load projections and plans for new generation and transmission facilities. Others have been highly effective in bringing about the construction of bulk power facilities planned and engineered on a regional basis. At the present time, only two regional groups have been formed whose principal function is improvement in system reliability. Chapter 4 of the main report discusses some of the principal characteristics, objectives, functions and shortcomings of the power pools and planning groups now in existence. It also includes maps showing areas covered by 18 major formal power pools and the 11 major power planning groups. The members of each of these pools and planning groups are shown in the following lists. Connecticut Valley Electric Exchange (CONVEX) Connecticut Light & Power Company Hartford Electric Light Company United Illuminating Company Western Massachusetts Electric Co. New York State Power Pool Central Hudson Gas & Elecrtic Corporation Orange and Rockland Utilities, Inc. Consolidated Edison Company of N. Y. Long Island Lighting Company Niagara Mohawk Power Corp. New York State Electric and Gas Corp. Rochester Gas and Electric Corp. Pennsylvania-New Jersey-Maryland Interconnection (P]M) Public Service Electric and Gas Company Philadelphia Electric Company Pennsylvania Power and Light Company Baltimore Gas & Electric Company Potomac Electric Power Company General Public Utilities Corporation Metropolitan Edison Company Pennsylvania Electric Company Jersey Central Power and Light Company New Jersey Power and Light Company Associate Members Delmarva Power & Light Company Atlantic City Electric Company Luzerne Electric Division, United Gas Improvement Company Carolinas-Virginias Power Pool (CARVA) Virginia Electric & Power Company Carolina Power & Light Company Duke Power Company South Carolina Electric & Gas Company American Electric Power System Appalachian Power Company Indiana & Michigan Electric Company Kentucky Power Company American Electric Power System-Continued Ohio Power Comapny (Kingsport Power Co. and Wheeling Electric Co., which are part of AEP, have no generation.) Allegheny Power System Monongahela Power Company Potomac Edison Company West Penn Power Company Southern Company System Alabama Power Company Georgia Power Company Gulf Power Company Mississippi Power Company (Southern Electric Generating Co., which is part of the Southern Company System, was formed by Alabama Power Co. and Georgia Power Co. to construct a generating plant owned jointly by the two companies. ) Middle South Utilities Power Pool Arkansas Power & Light Company Louisiana Power & Light Company Mississippi Power & Light Company (New Orleans Public Service, Inc., is a subsidiary of this holding company but is not a pool member; it has an interchange agreement with Louisiana Power & Light Company.) Illinois-Missouri Pool Central Illinois Public Service Company Illinois Power Company Union Electric Company (Electric Energy, Inc. is owned by these three companies. Missouri Edison Co. and Missouri Power & Light Co. are wholly owned subsidiaries of Union Electric Company.) Missouri-Kansas Pool Empire District Electric Company Kansas City Power & Light Company Kansas Gas & Electric Company Kansas Power and Light Company Missouri Public Service Company Upper Mississippi Valley Power Pool Cooperatives Cooperative Power Association Dairyland Power Cooperative Minnkota Power Cooperative Northern Minnesota Power Association Rural Cooperative Power Association United Power Association Investor-owned Companies Interstate Power Company 166 Lake Superior District Power Company q Minnesota Power & Light Company Montana-Dakota Utilities Co. Northern States Power Company (Minn.) Northern States Power Company (Wise.) Northwestern Public Service Company Otter Tail Power Company Iowa Power Pool Iowa Electric Light and Power Company Iowa-Illinois Gas and Electric Company Iowa Power and Light Company Iowa Public Service Company Iowa Southern Utilities Company Corn Belt Power Cooperative California Power Pool Southern California Edison Company Pacific Gas and Electric Company San Diego Gas & Electric Company Indiana Power Pool Indianapolis Power & Light Company Public Service Co. of Indiana Wisconsin Power Pool Wisconsin Public Service Company Wisconsin Power and Light Company Michigan Pool Consumers Power Company Detroit Edison Company Northwest Intercompany Pool Puget Sound Power & Light Company Pacific Power & Light Company Portland General Electric Company Washington Water Power Company Northwest Coordination Group Bonneville Power Administration City of Eugene, Oregon City of Seattle, Washington City of Tacoma, Washington Colockum Transmission Company Montana Power Company Pacific Power & Light Company Portland General Electric Company P.U. Dist. No. 1 of Chelan County, Washington P.U. Dist. No. 1 of Cowlitz County, Washington P.U. Dist. No. 1 of Douglas County, Washington P.U. Dist. No. 1 of Pend Oreille County, Washington P.U. Dist. No. 2 of Grant County, Washington Puget Sound Power & Light Company United States Corps of Engineers Washington Water Power Company Aembers Groups Associated 11 Idaho P Montan Pacific 1 Utah PC Washin! C e n t r a l A1 ( CAPCO: Appalac Clevelai Duques Indiana Mononl Ohio E Ohio PI Pennsyl Potoma Toledo West P East Centra ment Appala Cincini Cleveli ColUml Pam Daytor Duque Indian Indian Indian Kentut Kentu’ Louisv Mono] North1 Ohio 1 Ohio 1 Ohio ’ Penns Poton Public South’ Toled West Electric Cc Bang< Bosto: Centr 267-7 Aembers of Major Power Planning Groups Associated Mountain Power Systems Idaho Power Company Montana Power Company Pacific Power & Light Company Utah Power & Light Company Washington Water Power Company Central Area P o w e r Coordination Group (CAPCO) Appalachian Power Company Cleveland Electric Illuminating Company Duquesne Light Company Indiana & Michigan Electric Company Monongahela Power Company Ohio Edison Company Ohio Power Company Pennsylvania Power Company Potomac Edison Company Toledo Edison Company West Penn Power Company East Central Area Reliability Coordination Agreement Appalachian Power Company Cincinnati Gas & Electric Company Cleveland Electric Illuminating Company Columbus and Southern Ohio Electric ComPanY Dayton Power and Light Company Duquesne Light Company Indiana & Michigan Electric Company Indiana-Kentucky Electric Corporation Indianapolis Power & Light Company Kentucky Power Company Kentucky Utilities Company Louisville Gas and Electric Company Monongahela Power Company Northern Indiana Public Service Company Ohio Edison Company Ohio Power Company Ohio Valley Electric Corporation Pennsylvania Power Company Potomac Edison Company Public Service Company of Indiana, Inc. Southern Indiana Gas and Electric Company Toledo Edison Company West Penn Power Company Electric Coordination Council of New England Bangor Hydro-Electric Company Boston Edison Company Central Maine Power Company 267-7810-67-12 Central Vermont Public Service Corporation Connecticut Light and Power Company Eastern Utilities Associates Fitchburg Gas and Electric Light Company Green Mountain Power Corporation Greenville Electric Lighting Company Hartford Electric Light Company Holyoke Water Power Company Maine Public Service Company New England Electric System New England Gas and Electric Association Newport Electric Corporation Public Service Company of New Hampshire Rangeley Power Company United Illuminating Company Western Massachusetts Electric Company Mid-America Interpool Network (MAIN) American Electric Power System Appalachian Power Company Indiana and Michigan Electric Company Ohio Power Company Kentucky Power Company Kingsport Power Company Wheeling Electric Company Commonwealth Edison System Illinois-Missouri Pool Central Illinois Public Service Company Illinois Power Company Union Electric Company Indiana Power Pool Indianapolis Power and Light Company Public Service Company of Indiana Wisconsin Planning Group Madison Gas and Electric Company Wisconsin Electric Power Company Wisconsin Michigan Power Company Wisconsin Power and Light Company Wisconsin Public Service Corporation Mid-Continent Area Power Planners (MAPP) Canadian Crown Corporation Manitoba Hydro-Electric Board Investor-Owned Electric Utility Companies Black Hills Power and Light Company Interstate Power Company Iowa Electric Light and Power Company Iowa-Illinois Gas and Electric Company Iowa Power and Light Company Iowa Public Service Company Iowa Southern Utilities Company Lake Superior District Power company Minnesota Power & Light Company Montana-Dakota Utilities Company Mid-Continent Area Power Planners--Con. Investor-Owned Electric Utility Companies- Continued Northern States Power Company Northwestern Public Service Company Otter Tail Power Company Union Electric Company Municipal Electric Utilities Ames, Iowa Austin, Minnesota Cedar Falls, Iowa Delano, Minnesota Glencoe, Minnesota Hutchinson, Minnesota Lake Crystal, Minnesota Madelia, Minnesota Marshall, Minnesota Mazeppa, Minnesota Melrose, Minnesota Moor-head, Minnesota New Ulm, Minnesota Owatonna, Minnesota Redwood Falls, Minnesota Sleepy Eye, Minnesota Watertown, South Dakota Public Power District Omaha Public Power District Rural Electric Cooperatives Cooperative Power Association Dairyland Power Cooperative Eastern Iowa Light and Power Cooperative Minnkota Power Cooperative Northern Minnesota Power Association Rural Cooperative Power Association Missouri Basin Systems Group Bureau of Reclamation Loup River Public Power District, Nebraska Platte Valley Public Power and Irrigation District, Nebraska State of Nebraska, Department of Public Institutions University of Nebraska Municipal Electric Systems Aberdeen Municipal Utilities, South Dakota Adrian, Minnesota Akron Municipal Light & Water Works, Iowa Alta Municipal Power Plant, Iowa Anita Municipal Utilities, Iowa Arlington Municipal Light & Power, South Dakota Atlantic Municipal Utilities, Iowa 168 Badger Utility, South Dakota Beatrice Board of Public Works, Nebraska Beresford Utility, South Dakota Big Stone City Utility, South Dakota Breda, Iowa Brewster Municipal Light & Power, Minnesota Burke Utility, South Dakota Callaway, Nebraska Cavalier City Light & Water Plants, North Dakota Coon Rapids Municipal Utilities, Iowa Den&on Municipal Utilities, Iowa Elk Point Light & Water, South Dakota Estelline Utilities, South Dakota Fairfax Municipal Power Plant, Minnesota Faith Utility, South Dakota Fort Pierre Utility, South Dakota Gowrie Municipal Utilities, Iowa Graettinger, Iowa Grafton Utilities, North Dakota Grove City Utility, Minnesota Harlan Municipal Utilities, Iowa Hawarden Municipal Utilities, Iowa Henning Electric, Minnesota Hillsboro Utilities, North Dakota Hope City Light and Power, North Dakota Jackson Municipal Light Plant, Minnesota James Valley Electric Power Cooperative, North Dakota Kimballton Municipal Light & Power, Iowa Lake Park Municipal Utilities, Iowa Lakefield Public Utilities, Minnesota Lakeview, Iowa Lakota Utilities, North Dakota Lang-ford Municipal Electric, South Dakota Laurens Municipal Light & Power Plant, Iowa Lenox Municipal Light and Power, Iowa Litchfield Public Utilities Commission, Minnesota Maddox Utility, North Dakota Madison Electric Utility, South Dakota Manilla Municipal Service Department, Iowa Manning Municipal Light Plant, Iowa Mapleton Municipal Electric Plant, Iowa Melrose Utility, Minnesota Milford Municipal Light Plant, Iowa Miller Utility, South Dakota Mountain Lake, Minnesota Nebraska City, Nebraska Onawa Municipal Utilities, Iowa Orange City Municipal Utilities, Iowa Parker Municipal Light Plant, South Dakota Paullina L Pierre Mu Primghar 1 Remsen h4 Rock Rap St. James 1 sanborn h Sharon Vi1 Shelby Mt Sibley Util Sioux Cen Spencer h, Stanton, I Stephen E Tyler MUI Tyndall L Valley Cit ’ Vermillior Dakota Volga Pou Wadena nesota Wall Lake Water-tow south I Wessingtc Power, Westbroo nesota Woodbinc Rural Elect! Baker E Dakota Basin Ele Dakota Big Flat Big Herr Monta Central 1 Gentral Dakot: Cherry-l Dakou Corn Be Dakota Dakot; East Riv Dakot Grand Dakot Paullina Utility, Iowa Pierre Municipal, South Dakota Primghar Municipal, Iowa Remsen Municipal Utilities, Iowa Rock Rapids Municipal .Utilities, Iowa St. James Electric Utility, Minnesota Sanborn Municipal Light Plant, Iowa Sharon Village Light and Power, North Dakota Shelby Municipal Utility, Iowa Sibley Utility, Iowa Sioux Center Municipal Utility, Iowa Spencer Municipal Utilities, Iowa Stanton, Iowa Stephen Electric Department, Minnesota Tyler Municipal Utilities, Minnesota Tyndall Utility, Minnesota Valley City Municipal Utilities, North Dakota ‘Vermillion City Light and Power, South Dakota Volga Power and Light, South Dakota Wadena Light & Water Department, Minnesota Wall Lake, Iowa Watertown Municipal Utilities Department, South Dakota Wessington S p r i n g s M u n i c i p a l L i g h t & Power, South Dakota Westbrook Municipal Light & Power, Minnesota Woodbine Municipal Light & Power, Iowa Rural Electric Cooperatives Baker Electric Cooperative, Inc., North Dakota Basin Electric Power Cooperative, Inc., North Dakota Big Flat Electric Cooperative, Inc., Montana Big Horn Country Electric Cooperative, Inc., Montana Central Montana Electric G&T, Montana 43entral Power Electric Cooperative, North Dakota Cherry-Todd Electric Cooperative, South Dakota Corn Belt Power Cooperative, Iowa Dakota Electric Cooperative, Inc., North Dakota East River Electric Power Cooperative, South Dakota Grand Electric Cooperative2 Inc., South Dakota Hill County Electric Cooperative, Inc., Montana KEM Electric Cooperative, Inc., North Dakota L&O Power Cooperative, Iowa Lyon-Lincoln Electric Cooperative, Minnesota Marias River Electric Cooperative, Inc., Montana McCone Electric Cooperative, Inc., Montana Minnesota Valley Light and Power Association, Minnesota Moreau-Grand Electric Cooperative, South Dakota Mor-Gran-Sou Electric Cooperative, Inc., North Dakota Nebraska Electric G&T Cooperative, Inc., Nebraska Nodak Rural Electric Cooperative, Inc., North Dakota Northwest Iowa Power Cooperative, Iowa Park Electric Cooperative, Inc., Montana Renville-Sibley Cooperative Power Association, Minnesota Rosebud Electric Cooperative, Inc., South Dakota Rushmore Electric Cooperative, Inc., South Dakota Sheyenne Valley Electric Cooperative, North Dakota T&State G&T Association, Colorado Upper Missouri G&T, Montana Verendrye Electric Cooperative, Inc., North Dakota Yellowstone Valley Electric Cooperative, Inc., Montana Southwest Power Pool Arkansas-Missouri Power Company Arkansas Power & Light Company Central Louisiana Electric Company, Inc. Empire District Electric Company Gulf States Utilities Company Kansas Gas and Electric Company Louisiana Power & Light Company Mississippi Power & Light Company Missouri Public Service Company Missouri Utilities Company New Orleans Public Service, Inc. Oklahoma Gas and Electric Company Public Service Company of Oklahoma Southwestern Electric Power Company Western Power and Gas Company, Inc. 169 Western Energy Supply B Transmission ASSOciates ( W E S T ) Arizona ElectricPower Cooperative Arizona Public Service Company City of Burbank, Public Service Department City of Colorado Springs, Department of Public Utilities Colorado-Ute Electric Association El Paso Electric Company City of Glendale Imperial Irrigation District City of Los Angeles, Department of Water and Power Nevada Power Company Pacific Power & Light Company (Wyoming Division) Pasadena Municipal Light & Power Department Plains Electric G&T Cooperative ?ublic Service Company of Colorado Public Service Company of New Mexico Salt River Project San Diego Gas & Electric Company Sierra Pacific Power Company Southern California Edison Company Tucson Gas & Electric Company Utah Power & Light Company Northeast Power Coordinating Council Boston Edison Company Central Hudson Gas & Electric Corporation Central Maine Power Company Central Vermont Public Service Corporation Connecticut Light and Power Company Hartford Electric Light Company Western Massachusetts Electric Company Consolidated Edison Company of New York, Inc. Blackstone Valley Electric Company Brockton Edison Company Fall River Electric Light Company Montaup Electric Company Green Mountain Power Corporation Holyoke Water Power Company Hydro-Electric Power Commission of Ontario Long Island Lighting Company Cambridge Electric Light Company New Bedford Gas and Edison Light Company Cape and Vineyard Electric Company Plymouth County Electric Company New England Power Company Massachusetts Electric Company This Apl tad impact activities ar marizes the state, munil the event a ments to m Because of wide diitril agencies of sion considc informatior, of the infor mission’s in of agencies General Transpol large metro early eveni New York electric POT sands of pe tions, in tu electric mc have offere because tra However, used effect town busir more than portation v station pui stalled car commercia for three continued electric ger Railroac in the Neon 170 _“, . :. APPENDIX D IMPACT OF POWER FAILURES This Appendix enumerates some of the important impacts of the Northeast power failure on the activities and welfare of the area affected and summarizes the investigations and activities of Federal, state, municipal and other authorities in reviewing the event and in examining preparedness requirements to minimize effects of major power failures. Because of the importance of this subject and the wide distribution of responsibilities among many agencies of all levels of government, the Commission considered that it would be helpful to compile information on actions taken and planned. A digest of the information received in response to the Commission’s inquiry on this subject to a large number of agencies is included in this Appendix. General Impacts Transportation Transportation facilities and equipment in the large metropolitan areas were meeting their normal, early evening peaks at the time of the outage. In New York City, the sudden interruption of the electric power supply stranded hundreds of thousands of people in elevators, on trains between stations, in tunnels under rivers and on bridges. Nonelectric motor bus service, which normally could have offered some relief was rendered less effective because trafhc control systems became inoperative. However, in New York City the bus system was used effectively to evacuate people from the downtown business districts, where on an average day more than a million people are employed. Transportation was further hampered because most filling station pumps could not be operated. Occasional stalled cars added to traffic congestion. Although commercial power service in Boston was interrupted for three to eight hours, Boston’s subway system continued in operation with power from its own electric generating facilities. Railroad passenger service was extremely limited in the New York City metropolitan area until 5:00 a.m., November 10 and was erratic throughout the Northeast because of the wide dependence upon commercial power sources for the operation of signaling and switching devices. Air transportation for the most Fart fared somewhat better than the railroads or subways. Aided by clear weather and some auxiliary and improvised emergency power facilities to energize essential traffic control systems, most airports were able to continue functioning on a restricted basis. LaGuardia, for example, handled 246 flights during the emergency period. However, many flights were cancelled, delayed or diverted to airports outside the affected area. New York’s LaGuardia and John F. Kennedy Airports were without adequate power for about 12 hours. Fortunately, power service to the Newark Airport was not interrupted and flight accommodations at this field were extended to receive about 70 diverted flights. Interstate and intrastate motor bus and line haul freight carriers were not affected in their operations except for delays caused by increased traffic congestion in some areas. Marine terminals, canal and ocean shipping operations were also minimally affected since ships generate their own power and navigational aids and canal locks generally have auxiliary or self-contained power units. Public Service The massive power interruption had a significant effect on such essential functions as water and sewage service, particularly for high-rise buildings. Many persons were confined in elevators for varying periods of time. Hospital procedures, medical equipment, and drugs and blood supplies depend heavily upon electric energy for their use and maintenance. Fortunately, no grave effects in human care institutions were reported as directly attributable to power failure. This was due mainly to the alertness and capability of hospital staffs and the cooperation of local 171 government services and some public utilities. At the time of the power outage only five of New York City’s 21 city-operated hospitals had their own generators, but local government services and public utilities made available mobile generating units to a number of hospitals that lacked auxiliary power. In Massachusetts, of 142 hospitals responding to an inquiry by the Massachusetts Hospital Association on auxiliary power availability during the power outage, six hospitals reported no loss of power, 11 sustained power losses of less than onehour duration, 23 experienced power losses for periods of one to two hours ; the remaining 102 hospitals were without power for periods ranging from two to over eight hours. Only four of the respondents had no emergency generators. One hundred and thirty hospitals reported having automatic switching devices, but about 10 percent reported some switchover problems. Only four were unable to start their generators. The Boston Regional Office of the Department of Health, Education, and Welfare reported that while some of the hospitals in Massachusetts are improving their emergency power capabilities, there appear to be no legislative or building code changes pending for the same purpose. The threat to public safety from crime was appreciably minimized by the availability of self-contained power units in most law enforcement facilities. Fortunately, the number of fires during the blackout was low. Communications Keeping a large electric power-deprived population continuously informed about the power failure was psychologically important. Initially, radio broadcasts assured all listeners that the cause was primarily of mechanical origin and not due to sabotage or enemy action. The broadcasting industry was also helpful in preparing and delivering special announcements on traffic and travel conditions, suggestions on the prevention of food spoilage and statements concerning services affected by the blackout. Within minutes after the power failure, 61 standard broadcast stations, 18 FM stations, and 12 TV stations resumed operation with emergency generators, and within a two hour period, 12 1 standard broadcast stations, 47 FM stations and 19 TV stations located in the affected area had been restored to service. The value of battery-powered radio receiving sets was amply demonstrated. 172 The affected area involved 16 million telephones and 1,380 communications equipment centers. The various telephone companies, supported by their own emergency power, continued to operate when commercial power failed. Although loads were abnormally heavy, priority calls and mdst of the regular calls were completed without service difficulty. There were delays in some instances, due to circuit overloading. Little difficulty was experienced in maintaining government communication services. The major problems encountered concerned equipment which depended upon local power sources for operation, such as teletypewriters and PBX switchboards. Telegraphic service was delayed up to 14 hours. Although some auxiliary power equipment was available outside the New York City area, service was not assured to customers due to the lack of commercial power at most telegraph branch offices and to customers using private wire service. The overall impact on critical national security communications was negligible, due mainly to the availability of emergency standby power and the alternative routing capability of the defense services. Similarly, the overall effect of communication losses on the critical functions of Federal government agencies in the affected area was minor due to the availability of priority service and the fact that the event occurred during a period which normally has a very low communications traffic demand. Agency Actions In order to assess the impact of the November 9th power failure on significant aspects of human and institutional activities throughout the affected area and the country at large, the Commission sent letters to approximately 30 Federal, state, and local agencies requesting the following information : ( 1) a summary of their investigations and findings relating to a given list of essential services, (2) a list of specific actions taken, or in process, directed towards preventing or alleviating the impact on these services in the future should a power failure occur, and (3) their suggestions for additional services considered sufficiently important to be supported by emergency electric power facilities. The reported activities of several of the agencies having important responsibilities for essential services are summarized in the sections which follow. Table D-l shows the emergency services that have been suggested or required at selected essential service facilities. Item Operating Rot X-Ray..... Emergency Re Area. . . . . . . Recovery ROOI Intensive Care Elevator Se& Corridor & Ex Stairwell Lighl Alarm & Call ! Heating/Cooli tilation.. . . . Refrigeration : Minimal Food Pumps, Fuel, Lubrication Air Compressc Exterior Lighl Tower...... Lights, Runwi Phones, Switc boards, Rat typewriterv 1 Include! s Includes s Includes Fee As a resu of dependir port of tllf was modifi engine get-r The agent; nation as 0 with adeqc full operat least one m failure. Th apart were tion to pra of an area1 of the airy engine gen lations are all of the November TABLE Item Operating Rooms X-Ray. . . . . . . . . . . Emergency Receiving Area.............. ReeoveryRooms..... Intensive Care Areas. , Elevator Service.. . . . Corridor & Exit Light! Stairwell Lights. . . . Alarm & Call System 1 Heating/Cooling/Ventilation.. . . . . . . . . . . Refrigeration s. . . . . . Minimal Food Service pumps, Fuel, Vacuum Lubrication &Motor A i r Compressor.. . Exterior Lighting.. . . Tower. . . . . . . . . Lights, Runway, Road Phones, Switchboards, Radio, Tele. typewriters . . . . . . . Haspitals D-l.-Sclectcd Essential Services Requiring Emergmcy Ehctric Power Schools Hotels Apartments Office Bldgs. Mwable Bridges ...... ...... ...... ...... ...... ...... ...... ...... ....... ...... ...... 1Fog X X X X X X”” X X X”” X X X ...... ...... ...... ...... ...... X X X X X X X ...... ...... X ...... ...... ...... ...... ...... X X X . . . . . ...... ...... ...... ...... ...... ...... ..... . . . . . . . . . . ...... ...... ...... ...... ...... X X”” ...... ...... X X X X X xa Airports Railroad h Rapid Transit Stations and Tunnels Industrial Produc:ion and R&D ties Civil Defenst Operat hi3 Centen Law En‘orce- 1 Includes fire protection. s Includes heat removal from hydrogen and other cooling medii. s Includes blood bank refrigeration. Federal Aviation Administration As a result of the power failure, the agency policy of depending upon two prime power sources for support of the National Air Space System’s facilities was modified to provide the addition of standby engine generators for all critical operational needs. The agency has identified 50 key airports across the nation as continuous power airports, to be equipped with adequate auxiliary power generators to permit full operational capability of agency facilities on at least one runway in the event of a commercial power failure. These 50 airports, no more than 200 miles apart were selected on the basis of activity and location to provide for recovery of aircraft in the event of an areawide power outage. As of April 1967, two of the airports had been equipped with the necessary engine generators. Many of the remaining 48 installations are now approaching completion and almost all of the installations will be fully completed by November 1967. A number .of engine generators have been loaned to airport sponsors to provide backup power for runway lighting. Federal funds are also available to airport sponsors under the Federal Aid to Airports Program, to help finance the cost of permanent emergency power facilities for runway and taxiway lighting. Battery-powered radio transceivers are being procured for use as emergency equipment at major air traffic control towers other than at the 50 continuous power airports, and are scheduled for complete installation by mid-March 1968. Additionally, the FY-1968 operations program is scheduled to provide the emergency power equipment at Air Route Traffic Control Centers with out-of-tolerance frequency sensing devices to avoid shutdown of these essential facilities due to variations in the frequency of commercial power. Department of the Interior All agencies of the Department concerned with electric power generation, transmission or marketing were asked to review their power systems for deficiencies following the Northeast outage. Responses indicated that where such deficiencies were found, corrective actions have been taken or are in progress. These actions include improvements in communications and telemetering, station service power supply, and circuit design. Interior’s Office of Oil and Gas, concerned with electric power requirements for oil and gas gathering, processing, production and transportation, requested the National Petroleum Council to undertake a study of the adverse effects of massive power failures on the oil and gas industry. The Council reported that: ( 1) There is a very high dependency upon purchased electric power in the crude oil and products pipeline transportation and refining phases of the industry. It also reported that in the event of a massive power outage, damage to equipment would be light, and would generally center at those refineries unable to shut down in an orderly fashion due to insufficient auxiliary steam equipment. (2) The November 9 outage had no major impact on the refinery industry. Only three refineries in the Northeast area were directly affected; one was forced to shut down, the other two continued operations by switching to auxiliary steam equipment. The Council found that, although refineries constructed in the last 10 years are essentially all-electric and would shut down in the event of a power failure, they generally have sufficient auxiliary steam to permit a normal shutdown without damage. The Council recommended that companies planning to construct new facilities or expand existing facilities consult with experts in the electric power industry on such matters as auxiliary generating and pumping facilities. (3) Little, if any, damage would be incurred by pipeline pumping or compressor equipment in a massive power outage. Practically all gas compressors and pumps are driven by engines utilizing natural gas as a fuel. Standby generators would be utilized, as is customary in emergencies to control pipeline flows at reduced rates. Federal Communications Commission The FCC’s critical direction finding and monitoring operations concerned with the practical aspects of locating unauthorized stations, or sources of interference to broadcast and radio reception, measuring signal quality, and providing other similar aids, are maintained through an interconnected l&station communications network equipped with 174 auxiliary generators. Washington headquarters of FCC is the exception; no emergency auxiliary power generators are available at the Commission’s .headquarters offices. In the event of a commercial power failure in Washington, D.C., network control operations would be shifted automatically to an alternative control center. Through the efforts of the national and state Industry Advisory Committees, the broadcasting industry, common carrier services and the safety and special radio services have developed emergency plans and procedures directed toward keeping telecommunications media open and available to the public. Following the Northeast power failure, system improvements have been made in all sections of the telecommunications industry, particularly where the absence of auxiliary power facilities resulted in communications failures. All major companies 1 have reviewed their systems’ weaknesses, as indicated by service failures during the outage, and to the extent feasible have corrected or are in the process of correcting themessentially increasing the availability and reliability of emergency power generating equipment and providing additional circuit capability. A problem not completely resolved concerns the regular installation of power packs or other self-contained power supply units on the customer’s premises, to activate terminal equipment such as teletypewriters, facsimile transmission facilities, switchboards and telephone signal lights. The various reports furnished to FCC indicate that the communications industry has put forth strong efforts to meet emergency service needs. Department of Defense The Northeast power failure had a relatively minor impact on the Defense Communications System. Critical defense functions were not impaired. An evaluation of all critical military voice and record circuits has been undertaken to ferret out weaknesses and to establish increased reliability. Where emergency power installations were available and failed to perform as planned, corrective measures have been taken to preclude a recurrence of the difficulty. Where emergency power was absent, it has since been installed or is planned for installation. Nationwide action has been initiated on the defense warning system voice network to 1 Including The Western Union Telegraph CO., Western Union International, RCA Communications, Inc., and ITT World Communications, Inc. assure that central pow ply. A joir Military Dc ing Groupmanship, i worldwide 1 deficiencies. availability tions, incll routings, al variable vc power syste Gt A progra isting gove emergency cars, trand centers, sti gram is sch of calendar made for e service ant Federal bu deemed ne have been power sup1 power soux trict offices speed telep continued bility. Batt teletype tr hours are subscriber5 impact SUI operations Northeast these opec Departme The De: ban Mass expenditur elude pov radio corn and alarm provide fu ties under lit Facilit programs. assure that all warning telephones have a reliable central power source or a local battery power supply. A joint Defense Communications AgencyMilitary Departments Power Improvement Working Group-formed under permanent DCA chairmanship, is engaged in the resolution of any worldwide Defense Communications Systems power deficiencies. Re-examination of all factors affecting availability and reliability of critical communications, including emergency power, alternative routings, and the maintenance of operations with variable voltage and frequency due to unstable power system conditions will be undertaken. General Services Administration A program has been initiated to provide all existing government-owned buildings with needed 1 emergency power sources for lighting in elevator cars, transformers and switchgear rooms, control centers, stairwells and other critical areas. This program is scheduled to be completed prior to the end of calendar year 1967. Provisions also are being made for emergency power generation for elevator service and other essential requirements in those I Federal buildings where ,this emergency service is deemed necessary. All GSA-operated switchboards have been equipped with an emergency battery power supply. Similarly, the addition of emergency power sources at message dispatch centers and district offices of the Advanced Record System (high speed teletypewriter and data transmission) insures continued operation of telegraphic switching capability. Battery power packs capable of operating a teletype transmitter or receiver for at least eight hours are made available at additional cost to subscribers who need such service. A power outage impact survey of GSA supply and material depot operations concluded that power outages of the Northeast proPortions would not seriously impair ’ these operations. I Department of Housing and Urban Development The Department can make grants under the Urban Mass Transportation Act of 1964 for capital expenditures for emergency facilities which may include power supply for the movement of trains, radio communications equipment, station lighting and alarm signals. The Department is also able to provide funds for standby electric generating facilities under its Public Works Planning Advance, Public Facility Loans, and Water and Sewer Grant programs. Office of Emergency Planning Under its national security responsibility for coordinating overall emergency preparedness, OEP, assisted by the Business and Defense Services Administration of the Department of Commerce, prepared and distributed the questionnaire shown in figure D-l to a sample group comprising approximately 3000 establishments. Information was requested relative to the effects of the power outage Standard Industrial Classifications: paper and allied products; chemicals and allied products; stone, clay and glass products; primary metals industry; fabricated metal products; machinery, except electrical; electrical machinery; transportation equipment, instruments and related products. Approximately 43 percent of the addressees responded to the questionnaires. No significant differences were noted among the responses within a given industrial classification or across industry groups. The responses indicated that: 1. Production time was lost by those companies using night shift. 2. Relatively minor damage to equipment was incurred by firms operating at the time. Similarly, some work in process was damaged. .3. On the whole, losses were nominal, although severe cold weather and longer duration of the outage would have aggravated the losses. 4. Nearly all reporting companies indicated lack of sufficient auxiliary generating equipment to operate independently of commercial power. Very few companies reported plans to install auxiliary generating equipment. 5. About one half of the companies in each classification have emergency shutdown procedures which helped alleviate damage. 6. Available communications were generally adequate. Telephones were operable and battery-powered radios were in prevalent use. Teletypes generally were inoperable. 7. Some respondents suggested prompt notification by electric utility via radio, or utility-tocustomer private line regarding magnitude of outage and probable duration, in order to expedite critical management decisions. 8. Restoration of electric power service, where possible, should be on a priority basis. Ii B”DOBT .e”REA” NO. 97-660, APPROVAL, EXPIRES /“NE SO.1966 . l.Do Return no later than APRIL 22, 1966 Name of Company Reporting REPORTON EFFECTSOF POWERFAILURE NOVEMBER 9 AND 10, 1965 b. If y 3-s ?eturn to: U.S. Department of Commerce Washington, D.C. 2GPO kttention: Business and Defense Services Administration Industrial Mobilization (6140) FILE COPY . 1.D.a 2. wet INSTRUCTIONS hailing - Prepare and teturn one copy of this report to the Business and Defense Services Administration, Industrial Mobilization (6140), U. S. Department of Commerce, Washington, D.C. 20230, no later than April 22, 1966. 2uesti ons concerning the form should be addressed to the lonstruction, Production and Power Resources Division, Office of Emergency Planning, Washington, D.C. 20504, relephone: Area Code 202 - DU 2-2311. File Copy - In addition to the original report form to be returned to us, there is enclosed a file copy for your records. You ate not legally required to fill out ot retain this file copy- While it would be a convenience to the Government for a file copy to b e made and retained for reference purposes, no assurances can be provided that file copies ate exempt from compulsory examination or production pursuant to legal process. 3. If L 4. Ifw 5. Do l 1. 1. Wh Te ‘lant Address Ra TC or 4. 1. Did your commercial electric power fail? [? Yes CIiNo o. If “Yes,” how long did the failure last? What was the damage to equipment ot work in process? 2. we E. Plea. to en Was plant operation affected in any other way? Explain b. If “No,” in your judgment what damage would have been caused by such failure to equipment, facilities, ot work in process? Explain: Ceftific 2. How soon would power have to be restored in order to avoid damage mentioned above? 3. Would the effects be different between day or night, and under severe weather conditions? Explain: FIGURE 176 D-l.-Questionnaire used by Business and Defense Services Administration. a. Front side tion co Nameo B- 1. Do you have auxiliary generating equipment? o. If “Yes,” was it put into serviceduring blackout? If a. above is Yes, what portion of total load can this auxiliary equipment carry? 0 Yes ON* 0 Yes ON* Hew long can you operate on auxiliary power? b. If you do oat have auxiliary equipment. are you planning to install such? .lf so, what portion of your total load would this carry? 0 Yes 0 Yes ON* 2. Were they used in the blackout? 0 Yes ON* 3. If so, did their use mitigate damage? r-J Ye.9 ON* 0 Yes ON* C- 1. Do you have emergency shut-down procedures? ON* How long could you operate on it? 4. How much rime is required for their execution? 5. DIJ these procedures rely on the use of electric power? D. 1. Whet communications remained operative during the power failure? Telephone 0 Yes IIN* Radio 0 Yes ON* Teletype 0 Yes ON* Orher (~eecrw.e) 2. Were the communications available to you adequate during the emergency? OYCS ON” E. Please discuss any observations or recommendations you may have concerning the November 9 outage which might be pertinent to emergency preparedness. lame of persoo who should be contacted if questions arise regarding this report Tel,ephone No. and Atea Code htificmtion - The undersigned company and the official executing this cenificarion in its behalf hereby certify that the informatioa contained in this report is correct and complete to the best of their knowledge and belief. Signature of authorized official q*me of compnny 4ddress of company FIOURE D-l.-Questionnaire Title Dare used by Business and Defense Services Administration. b. Reverse side 177 Data based on questions similar to the BDSA Survey, forwarded to the OEP by the Office of Minerals and Solid Fuels, Department of the Interior, indicated that the power outage effects on coke plants, coke docks, mines and mineral processors in the Northeast were negligible. OEP requires a rapid and reliable procedure for gathering information on emergency situations. Such a system for reporting electric power failures was developed by the Commission in conjunction with OEP which will provide information on the cause and extent of the trouble, restoration problems and schedules, and possible government actions. In addition, OEP has taken steps which will improve its ability to respond to this type of significant incident through additions to its communications systems and expansion of its automatic staff reporting system. navigational aids at the Kennedy and LaGuardia airports; (3) to provide additional portable lights at various Port Authority facilities; (4) to institute corrective action and inspection procedures to insure prompt operation of all existing emergency generators; and (5) to update all existing evacuation and emergency procedures for Port Authority facilities. The Authority also prepared a report on long-range plans for providing emergency generators or trickle charge batteries for moving stalled elevators, power for essential lighting at all Port Authority facilities, minimum heating in certain critical areas, radio transmitters where needed to improve system communications, and electrically driven compressors for use in certain tunnel pumping operations. Emergency electrical generating facilities existing or presently scheduled l for instaJlation by the Port of New York Authority are shown in table D-2. Department of Agriculture City of New York Survey questionnaires were also distributed by the Department of Agriculture to approximately 200 food processors and handlers. Approximately 50 percent responded, indicating that some nominal losses were sustained, due mainly to the interruption of production, cost of idle and standby labor, and clean-up. Equipment damage was minor. Favorable weather conditions and off-shift time of day were contributory factors to keeping the losses small. Among the many emergency power supply needs highlighted by the power failure in the City of New York was the relatively high ratio of hospitals found to be without reliable auxiliary power-more than half. As a result of the November 1965 experience, additional rules and regulations pertaining to emergency lighting and power requirements for all hospitals and nursing homes were promulgated in 1966 by the City as follows: National Aeronautics and Space Administration Hospitals This agency’s field centers are carrying out a program of updating standby power capability for communications and control to insure uninterrupted service during all critical phases of major space flight missions. In addition, improved operation and maintenance procedures are being implemented to insure operational readiness of all NASA emergency power facilities. Port of New York Authority This agency, responsible for the operations of certain commuter train service, bridges, tunnels, airports and terminals in the Metropolitan area of New York City, reported that actions had been instituted : ( 1) to expand the Port Authority network of radio communications; (2) -to cooperate with FAA in the installation of emergency power for 178 The following rules and regulations pertain to emergency lighting and power requirements for all existing and new hospitals in New York City. Purpose : The regulations set forth herein recognize the dependence of hospitals on electrical power essential to the safety of the patients and staff, for lighting, operation of plant and apparatus, and the continuation of the treatment in which timing is critical. These are minimal requirements to achieve, generally, these ends. Each institution must evaluate its own plant on the basis of its own program. Nothing in these regulations is to be construed as precluding expansion of emergency electrical SYSterns to other areas or functions. 1 Schedules received April 7,1967. John F. Ken Proposel Swih Polic Obst HZ Existing Swit Rem Ren: Rtlr ReIX ASE oub ARE Poli Bull La Guardia Propose Fiel Cer F: Cer F Cer F Gel F PO1 Ha M2 Ob I Unit -- -John F. Kennedy International Airport: proposed: Switchhouse No. 1. . . . . . . Area served . 3 0 0 K W . . . . . . . . . . . . . . 1Runway, Taxiway, Obstructions at Various Locations Hangars, Poles, etc. Centerline & Edge Ltg. 150 KW . . . . . . . . . . . . . 1 Entire Garage, l/3 Apron Field Ltg. 3 5 0 K W . . . . . . . . . . . . . 1 Emerg. Ltg., Fire Alarm Supv. office, Obstruction Lts. ZOKW . . . . . . . . . . . . . . . !Sewage Ejector, Controls & Emerg. Ltg. ,Obstruction Ltg . . . . . . . . Approx. 15 KW in smaller units. W: Switchhouse No. 1. . . . . . . . . . . . 125 KW (F.A.A.) . . . . . . 1Runway, Taxlway Ltg. . Police Emergency Garage.. . . . . . . International Arrivals Building. . . IAB-Sewage Ejector Bulldlng. . . . Remote Site No. 1.. . . . . . . Remote Site No. 2. . . . . . . . . Remote Site No. 3. . . . . . . . . . . . . 75 KW (F.A.A.). . . . . . . IControl Tower Navigational Aids. 25 KVA (F.A.A.). . . . . 1 Ground & Air. . . . . 25 KVA (F.A.A.). . . . . 1 Radio Control. . . . . . . . Transmit & Receive. . . 25 KVA (F.A.A.) . . . . . Remote Site Vortac (Radio Beam), 37.5 KVA (F.A.A.). . . . 1Navigational Aid. . . . . ASR-4 Site (Approach Radar). 62.5 KVA (F.A.A.). . . . 1Navigational Aid. . . . . . . Outer Marker Site (Navigation Ald 8 KVA (F.A.A.). . . . . . . Navigational Aid. . . . . . ARSR-2 (Long Range Radar). . . 125 KVA (F.A.A.). . . .,. Navigational Aid. . . Police Emergency Garage. . . . . . 35 KW (Mobile). . . . . Entire Garage.. . . . . . 25 KW . . . . . . . . . . . . . . . Emerg. Ltg. & Power.. . 288KW . . . . . . . . . . . . . . Runway, Centerline, Edge & Taxiway Ltg. Switchhouse No. 1. . . . . . . . . . . Building No. 141.. . . . . . . . . . . . . . La Guardia Airport : Proposed : Field Lighting Vault. . . . . . . . . . . Central Terminal Building, Finger # 1 Central Tuminal Building, Finger #2 Central Terminal Building, Finger #3 Central Terminal Building, Finger 14 Police Emergency Garage. . . . . Hangar No. 7B. . . . . . . . . . . I Scheduled colxlmkioning March 1868. March 1868. March 1868. March 1868. March 1868. ,‘/j To be returned to FAA &rcpiacalby300 KW unit. To be replaced by a 588 KW FAA Gen. Fed from 500 KW Gen. Fed from 500 KW Gen. To remain FAA owned 82 operated. To remain FAA owned & opcratcd. To remain FAA owned & opaatal. To remain FAA owned & operated. To remain FAA owned & operated. To be replaced by a 158 KW unit. Mobile Unit. March 1988. 75KW. . . . . . . . . . . . . . . Emerg. Ltg., Fingers, Wing & Central Bldg. s of Apron Field Ltg., Sewage Ejectors, Air Comp. & Emerg. Ltg. in Heating Plant. 150 KW . . . . . . . . . . . . 150 KW . . . . . . . . . . . . . 200KW.. . . . . . . . . . . . 6OKW . . . . . . . . . . . . . 25KW . . . . . . . . . . . . . Marine Terminal.. . . . . . . . . 25KW.. ........... Obstructions at Various Location Dike Pump Houses, Hangars, Etc Approx. 30 KW. . . . . . 4 rIMarch 1868. Entire Garage. . .. March 1868. March 1868. Emerg. Ltg., Fuel Pumps, Sewage Ejector. Emcrg. Ltg., Obstructior L March 1968. Lts., Sewage Ejector. Obstruction Lights. . . . .. March 1868. il TABLE D-2.-Port of N~ZII York Authority Emergcncy Electrical Power Equipment-Continued Area served La Guardia Airportaontinued Existing : Control Tower. . . . . . . . . . . . . . . 125 KVA (F.A.A.). . . Field Vault. . . . . . . . . . . . . . . . 75 KVA (F.A.A.). . . Control Tower Navigational Aids. Taxiway & Runway Ltg. Police Emergency Garage. . . . . . 32 KVA . . . . . . . Entire Garage.. . . . . Central Terminal Building. . . . . . ASR-4 Site (Approach Radar). . . . 28 KVA (Mobile). . . . 75 KVA (F.A.A.). . . Outside Lighting. . . . . Navigational Aids. . . . . ATR Site (Radar). . . . . . . . . . . . 25 KVA (F.A.A.). . . . Navigational Aids. . . . . Wave Guide Local&r Site.. . . . . . 37.5 KVA (F.A.A.). . . Navigational Aids. . . . . Newark Airport : Proposed : Switchhouse. . . . . . . . . . . . . . . . . 5OOKW............. Police Emergency Garage. . . . . . . . 5OKW.. . . . . . Terminal Building. . . . . . . . . . . . 75 KW . . . . . . . Terminal Existing : Building. . . . . Various Locations. . . . . . . . . . . Field Lighting Vault. . . . . . . . . Port Authority Building: Proposed : Basement. . . . . . . . . . . . . . . . . . . . . . 8th Avenue Basement. . . . . . . . . . . Existing: Switchboard J. . . . . . . . . . . . . . . . Center Basement. . . . . . . . . . . . . . Switchboard I . . . . . . . . . . . . . . . . . Bus Terminal: Proposed : Mobile Unit. . . . . . . . . . . . Edge, Center Line, Emerg. Htg. & Ltg. & FAA Loads to 250 KW (Required by FAA) Entire Garage, Obstruction Lts. 1Emerg. Ltg., All Facility Radio-Partial Apr. 1 KW. Ltg. 1Obstruction Ltg. . . . . . . . SKW...... 2-25KW... 2-5OKW... I-15KW... . . 1 . 2-5KW.. 5KW.... 5KW.... New York Truck Terminal: Existing . . . . . . Hoboken Piers : Existing. . . . . . . . . . . . . . . . 5KW.... 5KW.... Port Newark: Existing.. . . . . . . . . . . . . . 2-5 KW.. January 1968. January 1968. NCW Lincoln Tunl Proposed George Wasl Proposed Adm Mair Palis; ing Bayonne BrL Existing: Outerbridge Existing: January 1968. January 1968. December 1967. December 1967. Port Authol proparsd 33rx 23~ 14t1 9th ChI Exe Gra December 1967. . . . 1Elevator 8th Ave., Emerg. Ltg. . 1Htg., Emerg. Ltg.. . . . . IElec. Htg.-Steam PlantEmerg. Ltg. 1Emerg. Ltg. . . . . . . . . . . . 1Boiler Room Power Base Gravity Tank. 1Mobile Units-Emerg. Power & Light. December 1967. ... ... Holland Tun Proposed N-V. Gocthals Brif Existing: ,Stairway Ltg.. . . . . . . . . . 1Lighting. . . . . . . . . . . . . ,Stairway Ltg.. . . . . . 70 KW . To remain FAA installed & operated. To remain FAA installed & operated. To remain FAA installed & operated. ... ... . . 50 KW 100 KW. FAA maintained to remain. FAA Generator to be replaced ‘by 200 KW unit. To be replaced by 60 KW unit. IMobile Units. . . . . . . . . . 1Mobile Units.. . . . . . . . . Mobile Units.. . . . . . 1Runway Lighting. . . . . . . 50KW.. . . . . . . . . . . . . . 1Emerg. Ltg., Elevator. . . 10 KW . . . . . . . . . . . . . . . . 1Replace Existing 5 KW Unit. Existing: Basement . . . . . . . . . . . . . . . . Bus Station: Proposed: Near Switchboard. . . . . . . 180 . Runways, Taxiway, Scheduled Commissioning Being replaced. Pav HOI Hu Jm Wa Emagmcy Existin! Pot Get Go TABLE D-2.-Port of Nczu York Authority Emergency Electrical Power Equipment-Continued - Unit Area served Holland Tunnel: Proposed : New Jersey Administration Building 30KW.. . . . . . . . . . . . . New York Field Office. . . . . . . . . . . 15KW. . . . . . . . . . . . . . Emerg. Ltg., Htg., Tolls Indication. Emerg. Ltg., Htg., Tolls Indication. Lincoln TUMC~: Proposed : Administration Building. . . . 55KW. . . . . . . . . . . . . . Emerg. Ltg., Htg., Tolls Indication. December 1967. George Washingtog.Bridge: Proposed: Administration Building. . . . . . . . . . 55KW. . . . . . . . . . . . . . December 1967. Main Plaza Building . . . . . . . . . . . . . 30KW.. . . . . . . . . . . . . Palisade-s Interstate Parkway Build. ing. Bayonne Bridge: Existing: Field Office. . . . . . . . . . . . . . . . 30KW. . . . . . . . . . . . . . Emerg. Ltg., Htg., Tolls Indication. Emerg. Ltg., Htg., Tolls Indication. Emerg. Ltg., Htg., Tolls Indication. -- 150KW . . . . . . . . . . . . . Emerg. Ltg., Htg., Tolls Indication. Goethals Bridge: Existing: Electric Shop. . . . . . . . . . . . . . 150KW. . . . . . . . . . . . . Emerg. Ltg., Htg., Tolls Indication, Base Radio. Outerbridge: Existing : Garage. . . . . . . . . . . . . . . . . . . . 60KW. . . . . . . . . . . . . Htg., Emerg. Ltg., Tolls Indication PORTA Scheduled Commissioning Dtrcember 1967. December 1967. Decemba 1967. December 1967. E UNITS 1.5 KW, 1.8 KW, 3.5 KW, 5 KW - Port Authority Trans-Hudson: Proposed: 33rd Street. . . . . . . . . . . . . . . . . . . . . 23rd Street. . . . . . . . . . . . . . . . . . . . . 14th street. . . . . . . . . . . . . . . . . . . . . 9th Street. . . . . . . . . . . . . . . . . . . . . . Christopher Street. . . . . . . . . . . . . . . Exchange Place. . . . . . . . . . . . . . . . . 18 Battery Units. . . 12 Battery Units. . . 8 Battery Units.. 4BatteryUnits.... 4BatteryUnits.... 12 Batte-ry Units.. . Grove Street. . . . . . . . . . . . . . . . . . . . . Pavonia Street. . . . . . . . . . . . . . . . . . . Hoboken Terminal. . . . . . . . . . . . . . . Hudson Terminal . . . . . . . . . . . . . . . . . Journal Square. . . . . . . . . . . . . . . . . . . Washington Street Sub. . . . . . . . . . . . 6 Battery Units . . . . . . . . 6 Battery Units . . . . . . . . 17 Battery Units . . . . . . . 34 Battery Units . . . . . . . 27 Battery Units . . . . . . . 500 KW . . . . . . . . . . . . . . Emergency radio system: Existing : Port Authority Building. . . . . . . . . . . ‘, 1.5 KVA.. . George Washington Bridge . . . . . . . . . 300 Watts. . . . Goethals Bridge. . . . . . . . . . . . . . . . . . 300 Watts. . . . . . . . . Lighting . . . . . . . . December 1967. Lighting. . . . . . . . Do. Do. Lighting. . . . . . . . Do. Lighting. . . . . . . . Do. Lighting. . . . . . . . Lighting . . . . . . . . . Partial October ‘67, completed December ‘67. Station Lighting. . . . . . . . . Do. Station Lighting. . . . . . . . . Do. Do. Station Lighting. . . . . . . . . Do. Station Lighting. . . . . . . . . Do. Station Lighting . . . . . . . . . . November 1967. Tunnel Ltg. & Compressors Station Station Station Station Station Station Power Supply for “D” & “ES, & Cbn “A” Control Station Power Supply for Chan. “A” Station Power Supply for than. “A’ Station from Facility Gen. - 181 General Requirements : Emergency lighting and power shall be provided from an auxiliary source generated on the hospital premises. The auxiliary source shall have a capacity sufficient to supply and maintain the total connected emergency lighting and power load, with not more than six (6) percent reduction from rated system voltage for a continuous period. Each receptacle shall be computed at no less than two hundred (200) watts. Fuel capacity shall be provided for a period of at least twenty-four (24) hours with the generator operating at maximum capacity. Means shall be provided for automatically transferring the emergency lighting and power supply from the main source to the auxiliary source within fifteen (15) seconds in the event of a failure of the main source. The emergency power system shall be tested once a week. When the primary source of current for the building is supplied by a generating plant on the premises, an emergency supply shall be obtained from a source other than the primary source. Emergency lighting shall be provided for the following spaces, with the load being automatic- ally transferred : a. All lighting outlets in operating rooms, delivery rooms, exit signs, and stairways. b. Lighting outlets in labor rooms, nurseries, recovery rooms, emergency rooms, intensive care units, anesthetizing areas, essential clinical laboratories and radiological facilities, blood bank, and nurses’ stations; .to provide. average illuminating intensity of not less than fifteen ( 15) foot candles. c. One-half ( f/2 ) the lighting units in main pharmacy, telephone switchboard rooms, main switchboard rooms, transformer rooms, boiler rooms, machine rooms containing emergency equipment, and generator set location. d. Safety lighting for corridors, laundry (for new hospital construction only), kitchen, and utility rooms; provided that the average illumination intensity of the safety lighting is not less than five (5) foot candles. Emergency power shall be provided for the following, and the load shall be automatically trans- ferred : a. One ( 1) elevator which services inpatients on each occupied floor. The wiring shall be arranged to permit connecting all the elevators to an emergency source, with controls arranged to operate one ( 1) elevator at a time. 182 b. Two (2) identified receptacles in each operating, recovery, delivery, and emergency room, intensive care unit, all nurseries, anesthetizing area, and essential critical laboratories. c. Identified receptacles spaced throughout all corridors in all nursing units so that a onehundred (100) foot extension cord can provide emergency power to every bed. Extension cords shall be provided in readily available locations. d. Nurses’ call system; physiological monitoring systems; paging system; telephone switching, signaling, and monitoring equipment; and other essential communications equipment. e. All power plant and electrical equipment necessary for the continuous operation of: 1. One ( 1) diagnostic radiographic x-ray unit and related processing and viewing facilities. 2. Fire pump. 3. Alarm system for: fire, sprinkler, fire and smoke detection, generator unit malfunction, medical gases, and other alarm systems mandatory by local ordinance. 4. Central suction and medical air compressors. Emergency power shall be provided for the following, and the load may be either automatically or manually transferred : a. Fuel burning equipment including heaters, pumps, fans, and controls. Where electricity is the only source of power normally used for space heating, the emergency service shall provide for heating of operating, labor, recovery, intensive care, nurseries, and patient rooms. Emergency heating of patient rooms will not be required if the hospital is supplied by at least two utility service feeders, each supplied by separate generating sources. b. All pumps; sumps, boiler feed, domestic water, sewerage and ejector systems. c. Air compressors for general building use. d. Refrigeration for blood and bone banks, pharmaceuticals, frozen foods, and other critical refrigeration. e. Ventilating systems for one ( 1) operating room, one ( 1) delivery room, one ( 1) emergency room, and all nurseries. f. Data transmission’equipment used for diagnostic or other purposes related to the care or treatment of patients. Enforcem The efl ulations sl a. New Imn tracl 196t b. Exis Buil shal N&sing I The fo Emergent and New General 1 Emergt room, exi and nurs be suppli or a battc ity suffic emergent (4) hour shall be hours. Tl available tamed ir regulatio sion of z Unit Eql Unit f in lieu 0; Individu nation sl tery cha (d) a : lamps 511 ply to tl able rati not less total lan of at lea of the a strutted service. in place shall hz cordanc permitt by flexi at Enforcement: The effective date for compliance with these regulations shall be as follows : a. New Building: Immediately, except that projects under contract on July 1, 1966 shall have until July 1, 1968 to comply. b. Existing Building: Buildings constructed prior to July 1, 1966 shall have until July 1, 1968 to comply. N&sing Homes The following Rules and Regulations pertain to Emergency Lighting Requiremeilts for all Existing and New Nursing Homes in New York City. General Requirements : Emergency lighting shall be provided for boiler room, exits (including exit signs), patient corridors and nurses’ stations. Such emergency lighting shall be supplied by an automatic emergency generator or a battery on the premises, and shall have a capacity sufficient to supply and maintain the total emergency lighting load for a period of at least four (4) hours. Fuel storage capacity for the generator shall be adequate for a period of at least four (4) hours. This emergency lighting shall be immediately available when required and continuously maintained in proper working order. Nothing in these regulations is to be construed as precluding expansion of emergency lighting systems to other areas. Unit Equipments : Unit equipments of approved type may be used in lieu of the methods specified in paragraph 112.1. Individual unit equipments for emergency illumination shall consist of (a) storage battery, (b) battery charging means, (c) one or more lamps, and (d) a relaying device arranged to energize the lamps automatically upon failure of the normal supply to the building. The batteries shall be of suitable rating and capacity to supply and maintain at not less than 91 per cent of rated lamp voltage the total lamp load associated with the unit for a period of at least four (4) hours. Storage batteries whether of the acid or alkali type shall be designed and constructed to meet the requirements of emergency service. Unit equipments shall be permanently fixed in place (i.e. not portable) properly grounded and shall have all wiring to each unit installed in accordance with one of the approved wiring methods permitted in Article 5. They shall not be connected by flexible cords. Emergency illumination fixtures 267-7810-67-13 which obtain power from ;t unit eauinment and I I are not part of the unit equipment shall be wired to the unit equipment by an approved wiring method permitted in Article 5. Approval of Drawings: Plans and specifications incorporating the extent of the emergency lighting system to be provided, details of the equipment to be used and its associated wiring method shall be submitted in triplicate for approval to the Commissioner of the Department of Water Supply, Gas and Electricity, Municipal Building, Manhattan. Enforcement: The effective date for compliance with these regulations shall be as follows: a. Proprietary Nursing Homes: New and existing buildings-Effective immediately. b. Voluntary Nursing Homes : New. buildings-Effective immediately. Existing buildings constructed prior to July 1, 1966 shall have until July 1, 1968 to comply. Federally Supported Hospitals A nationwide study of auxiliary power availability in the Nation’s hospitals as of 1965, based on Public Health Service staff surveys and findings by the American Hospital Association, showed that of 6,915 hospitals, 2,973 or 43 percent had adequate emergency power. About 35 percent or some 2,420 required auxiliary power upgrading, 22 percent or some 1,522 needed complete auxiliary power systems. All of the agencies queried recognized the need for auxiliary power equipment, updated emergency operating procedures and improved emergency lighting and power systems to maintain essential services. At the time the FPC query was issued, many agencies had already initiated actions to implement some of the most critical improvements. The Federal Hospital Council approved a draft of new regulations to be promulgated by the Publit Health Service as a basis for granting aid to hospitals, pursuant to the Hill-Burton Act, Public Law 725, 79th Congress, as amended. These regulations were approved by the Secretary, Department of Health, Education, and Welfare on June 9,1967, and read as follows : t Public Health Service Regulations Pertaining to Emergency Electric Service for General Hospitals. J. Emergency Electric Service 1. General : To provide electricity during an interruption of the normal electric supply that could affect the medical care, treatment, or safety of the occupants, an emergency source of electricity shall be provided and connected to certain circuits for lighting and power. 2. Sources: The source of this emergency electric service shall be as follows : a. An emergency generating set, when the normal service is supplied by one or more central station transmission lines. b. An emergency generating set or a central station transmission line, when the normal electric supply is generated on the premises. 3. Emergency generating set. An emergency generating set, including the prime mover and generator, shall be located on the premises and shall be reserved exclusively for supplying the emergency electrical system. Exception: A system of prime movers which are ordinarily used to operate other equipment and alternately used to operate the emergency generator(s) will be permitted provided that the number and arrangement of the prime movers is such that when one of them is out of service (due to breakdown or for routine maintenance), the remaining prime mover(s) can operate the required emergency generator(s) and provided that the connection time requirements described in sec. 8-2455 are met. The emergency generator set shall be of sufficient kilowatt capacity to supply all lighting and power load demands of the emergency system. The power factor rating of the generator shall be not less than 80 percent. 4. Emergency electrical connections. Emergency electric service shall be provided to circuits for lighting and for operation of equipment as follows : a. Lighting : ( 1) Exitways and all necessary ways of approach thereto including exit signs and exit direction signs, exterior of exits, exit doorways, stairways, and corridors. (2) Surgical, obstetrical, and emergency room operating lights. (3) Nursery, laboratory, recovery room, intensive care areas, nursing station, medication preparation area, and labor rooms. (4) Generator set location, switch-gear location, and boiler room. 184 b. Equipment: Essential to life, safety and for protection of important equipment or vital materials : ( 1) Nurses’ calling system. (2) Alarm system including fire alarm actuated at manual stations, water flow alarm devices of sprinkler system if electrically operated, fire detecting and smoke detecting systems, paging or speaker systems if intended for issuing instructions during emergency conditions, and alarms required for nonflammable medical gas systems, if installed. (3) Fire pump, if installed. (4) Receptacles for incubators for infants. (5) Pump for central suction system. (6) Sewerage or sump lift pump, if installed. (7) Receptacles for blood bank refrigerator. (8) Receptacles in operating, recovery, intensive care, and delivery rooms except those for X-ray. At least one duplex receptacle in each nursery. (9) Duplex receptacles in patient corridors. One elevator, where elevators are used to transport patients to operating and delivery rooms or from these rooms to nursing areas on another floor. Equipment such as burners and pumps necessary for operation of one or more boilers and their necessary auxiliaries and controls, required for heating and sterilization. Ventilation of operating and delivery rooms. Equipment necessary for maintaining telephone service. (14) One electric sterilizer, if installed. c. Heating: Where electricity is the only source of power normally used for space heating, the emergency service shall provide for heating of operating, delivery, labor, recovery, intensive care, nurseries, and patient rooms. Emergency heating of patient rooms will not be required under either of the following conditions : ( 1) the design temperature is higher than + 20”F., based on the Median of Extremes as shown in the current edition of the ASHRAE Handbook of Fundamentals; or (2) the hospital is supplied by at least two utility service feeders, each supplied by separate generating sources, or a network distribution system fed by two or more generators, with the hospital feeders so route any pita1 mart 5. Deti be so co normal e brought tc within l( automatic ing; all z ment net pump for operating covery r( nurseries. to .be con be connec automatif quently manual 1 to the c marked f lights, PI ing or fo of transfc terruptio be used generatoi site, the hour ope ground tl storage f; Federal The v with the a nation; Congress projects, visory co The S 15, 1966 govemm try to a of the N mittee tc of Repr Foreign ’ Senate printed IV routed, connected, and protected that a fault any place between the generators and the hospital will not likely cause an interruption of more than one of the hospital service feeders. ’ 5. Details: The emergency electrical system shall be so controlled that after interruption of the normal electric power supply, the generator is brought to full voltage and frequency and connected within 10 seconds through one or more primary automatic transfer switches to all emergency lighting; all alarms; blood banks; nurses’call; equipment necessary for maintaining telephone service; pump for central suction system; and receptacles in operating and delivery rooms, patient corridors, recovery rooms, intensive care nursing areas, and nurseries. All other lighting and equipment required to be connected to the emergency system shall either be connected through the above described primary automatic transfer switching or shall be subsequently connected through other automatic or manual transfer switching. Receptacles connected to the emergency system shall be distinctively marked for identification. Storage-battery-powered lights, provided to augment the emergency lighting or for continuity of lighting during the interim of transfer switching immediately following an interruption of the normal service supply, shall not be used as a substitute for the requirement of a generator. Where fuel is normally stored on the site, the storage capacity shall be sufficient for 24hour operation. Where fuel is normally piped underground to the site from a utility distribution system, storage facilities on the site will not be required. Federal legislative Proposals The vital concern of the Federal Government with the reliability of bulk electric power supply on a national scale is expressed in legislative proposals, Congressional hearings, studies, reports, research projects, and the activities of special technical advisory committees. The Senate Committee on Commerce, on March 15, 1966, issued an interim report 1 on responses by government (Federal, State and local) and industry to a series of pertinent questions on the impact of the November 9th outage. The Special Subcommittee to Investigate Power Failures of the House of Representative’s Committee on Interstate and Foreign Commerce held hearings on the November * Senate Report No. 1079, 89th Congress, 2d Session, March 22, 1966. printed power interruption on December 15,1965 and February 24 and 25,1966. Measures directed towards mitigating the possible adverse affects of power failures on hospitals were introduced under S. 2803, H.R. 12841 and H.R. 16050 during the 89th Congress, 2d Session, and H.R. 6260 of the 90th Congress. These bills would amend the Public Health Service Act to provide grants and loans for the construction and improvement of standby electrical systems for public or private non-profit hospitals. S. 3004 introduced during the 89th Congress and S. 536,9Oth Congress, would require specified buildings such as hotels, motels, train and bus stations, and airports, restaurants and similar public gathering places to be equipped with emergency lighting systems. State legislative Proposals The Northeast power failure alerted every section of the country to the possibility of a similar occurrence affecting their power systems and the populations they serve. Consequently, many states and independently, electric utility companies, have initiated studies to determine the probabilities for such failures within their systems and the necessary corrective measures.l The National Association of Railroad and Utility Commissioners has communicated with all state utility regulatory agencies requesting that comprehensive investigations be made of power systems within their jurisdictions and that appropriate actions be taken by the state commissions. An example of a state’s concern is a California study 2 of six large California utilities. The study indicated that 2305 customers had installed standby generating equipment to provide for their minimum needs in the event of a power failure. These customers were classified as follows: Hospitals and Medical Centers---------------Communications --- ____- - ______ --- ____ -----Police, Fire, and Other Governmental Functions-Military -_---__- ________ --__--- ____________ Transportation (including navigation facilities) --Other (including commercial and industrial)---- 596 476 690 124 77 342 2,305 ‘See Part 2, Northeast Power Failure, Addendum to Hearings, Special Subcommittee to Investigate Power Failures, Committee on Interstate and Foreign Commerce, House of Representatives. *California Systems Reliability Task Force Report to Public Utilities Commission Staff, December 28, 1965. The California experience is fairly representative of the national attitude towards the need for this critical equipment. A state-by-state survey by the Engine Generator Set Manufacturers Association, Chicago, Illinois, of mandatory provisions for standby power for essential services indicates that nationwide, much remains to be done. As shown in table D-3, of the 51 states (including the District of Columbia), 22 have no legislative provisions for any emergency power, while the remaining 29 have some legislation or policy relating to emergency power for some -- Legislation Requiring Emergency Power. / I -i <-l ,f 1 P--4- - Y e N NI 0 0 8 - - Y Y e e s 9 - - -- A ’Y e 8 -- A 1 - - Power Source Rapsired. . . . . . . . . . . . . T - Applicable Governing Agency.. . . . . . .# I $ .”tj .j - - 4 6 “0 u - Types of Buildings and/or Installation Sites Covered. For Lights Only (L)-Light and Power (P). essential services. The kinds of emergency power to be provided vary and include battery-powered lights, generator sets, and alternate feeder lines. In several states, no particular power source is specified. A wide range of buildings or installations is covered by the meager legislation in these 29 stateshospitals, nursing homes, schools, theaters and public gathering places, airports, public buildings, hotel and office buildings. Six states include only one of these types of installations or buildings; the remainder includes from two to five such types. Eleven of the 29 states require auxiliary electricity for lights r - 7 -- 1 L - - - -- - Y e S - A B A C B D F G - - - Q S - - - T P L 5 5 3- - m 3 A ra - N N 0 0 - - - - ff s Y e S - F 2 R - - P L 2 TABLE D--J.-State - 4 B c: D E J - - 7 - - - 9 - - Codes and Regulations T I 4 2 - 3 i - - Y e Y e N N 0 0 Yl S - S - - - A A B - - R - - - 0 N Y 0 e s - - B - - - - Q A K - - RQ Q - - - - - - - P - - - 7 - - - - - - *= Although Nevada has no legislative requirement for 2=Department of Licenses and Inspections. emergency power in public buildings, Nevada reports that 3= Advisory Board. it is the policy of the State Planning Board to install emer4=Department of Public Safety. gency power and lighting facilities in all state financed 5=Fire Marshal. public buildings and to encourage this for non-state owned 6=Department of Public Buildings. public buildings. 7=State Board of Health. #=Based on survey by Engine Generator Set Manufac8=Department of Labor and Industries. turers Association. 9=Not Specified. Information as of April 1, 1967. 186 Y Y e c s S - - A J R S - - P P 7 h - 5 7 R S S - L L - 5 6 5 only, wh other pot lation enj 29 states, in the Sta share this eight stat falls with and Insp and Indu Since t ties and I for Emngcn - !i 2 fj Y e Y e S S - - A B D F A B - T R - L P - 4 I5 - A= Hos B= Nur C= Sch D=Th( E=Offi F=Hot G= Air] only, while 19 states require electric energy for other power uses as well as lights. Codes and regulation enforcement authority also vary. In 15 of the 29 states, responsibility for compliance resides within the States’ Boards of Health. Fire marshalls either share this responsibility or are solely responsible in eight states. In the remaining seven states this duty falls within the purview of Departments of Licenses and Inspections, Buildings, Public Safety or Labor and Industries. Since the November 9, 1965, power outage, utilities and other entities involved with essential servfor Emergency Power # - -- - - i fP -4 * ‘i 2 !?z - E G3 2d E i! 3 2 - 2 - 3 2 - 0 Y e Y e Y e - - - A B D F A B K D G A B C D A B C D F - - - - B .s 1 f -_- p E- Y e Y e Y e 8 - 8 - T L 4 - _- 8 - R S N 8 8 R R S S - - - L P P L - - - 5 9 7 3 - 8 - A= Hospitals. B=Nursing Homes. C= Schools. D=Theaters and Public Gathering Places. E= Office Buildings F=Hotels and Apar 1ment Buildings. G= Airports. 4 & 2 -iz N - g 2 9 5 - f z - 0 Y e - 8 - 8 - Y e Y e Y e Y e Y e 8 8 - 8 - 8 - 8 8 - _-- -- Y e ii 2 2 :i 4 P 3 g - - - - Q N N Y 0 0 e 0 e e - L 8 - - - - .-- N - - - - - - 7 7 - - - - - - - 7 - 8 5 -- - - - -- --_- 7 7 8 - - - ----- - - - - - - - P P - - 7 8 - - 5 - 8 Q T L P Y A B T - Y 8 A C D E F R P .B ti 3 3 - - 0 R - 1 .5 N A B A B - Q Q Q - - ices in the Northeast-and their nationwide counterparts-have greatly improved their readiness and capability for preventing power failures and for dealing rapidly with major failures should they occur. Their actions focus on correcting system deficiencies such as those which caused or contributed to the November 9 interruption. Present plans provide for the improvement and strengthening of interconnections with neighboring systems, the installation of auxiliary power units to assure the availability of critical power, improvement and greater reliability of communications, and updating operating instructions and procedures. H= Fire and Police Stations. J= All Public Buildings, State and Commercial. K= State Buildings only. Q=Battery Powered Lights. R= Emergency Generator Sets. S=Alternate Source of Electricity from another Feeder. T= None specified. 187 APPENDIX E SUMMARY OF LARGER POWER INTERRUPTIONS 1954-1967 In the period 1954-1966, there were.148 power interruptions which were sufficiently important to gain publicity. Some of these involved transmission network instability and separation; others were local in nature, affecting load areas served radially from the network. A summary of these interruptions is presented in table E-l, and their locations are shown on figure E-l. FPC Order No. 331, issued December 20, 1966, requires all entities engaged in the generation and transmission of electric power to report significant interruptions of bulk power supply to the Commission. Through June 12, 1967, fifty-two power interruptions were reported in accordance with Order No. 331. These are briefly described below. Marias River Electric Cooperative, Inc., January 15; 1967 Failure of a suspension insulator during a blizzard resulted in interruption to Shelby, Rudyard, Cut Bank, and Tiber Dam substations in Montana. Service to some 6,900 customers amounting to about 19,000 kilowatts was interrupted for times ranging from one hour and 43 minutes to nine hours and 13 minutes. Moreau Grand Electric Cooperative, January 16, 1967 This outage affected about 3,000 customers and 4,000 kilowatts of load in an area of some 5,000 square miles around Timber Lake and Eagle Butte, North Dakota. The outage occurred on a 69 kv line of the U.S. Bureau of Reclamation during a period of high winds. Union Electric Company, January 24, 1967 A tornado damaged distribution and subtransmission facilities in northwest St. Louis County, Missouri, affecting service to about 75,000 customers. Restoration was begun in 35 minutes and service was restored to all customers who were in a condition to accept service in about 17 hours. Provo, Utah, January 25, 1967 Service was interrupted for 20 minutes to the entire 13,200 customers of the City of Provo. It is believed that the outage resulted from a short circuit when accumulated snow fell from the conductors. Grand River Dam Authority, January 26, 1967 Failure of a lightning arrestor interrupted 30,000 kilowatts of load of two industrial customers for about 30 minutes near Choteau, Oklahoma. Illinois Power Company, January 26, 1967 About 17,000 customers with a load of 30,000 kilowatts in the Champaign-Urbana area of Illinois were without power for periods ranging from about two to six hours. No damaged facilities were found, and the outage is presumed to have been caused by high winds and icing conditions. El Paso Electric Company, January 28, 1967 A bird carrying a metallic necklace caused a short circuit on the bus of the Sunset substation which interrupted electric service to commercial loads and office buildings. About 25,000 kilowatts was interrupted for 55 minutes. Fulton, Kentucky, Municipal, February 2, 1967 Lightning destroyed two cross arms on a 69 kv line of the Tennessee Valley Authority, serving the City of Fulton. 1,640 customers with a load of 960 kilowatts were interrupted for 20 minutes. Tennessee Valley Authority, February 8, 1967 The failure of a current transformer resulted in the interruption of about 64,000 kilowatts of load in Warren and Simpson Counties, Kentucky, including the cities of Bowling Green and Franklin. All loads were restored in 30 minutes except South Bowling Green where restoration was further complicated by a frozen valve on the circuit breaker air suppiy. This service was restored in 64 minutes. 189 Chugach Electric Association, Inc., February 9, 1967 37,500 kilowatts of load and 18,100 customers in the Anchorage, Alaska, area were interruped for 15 minutes when an air-break switch failed during tests following repair work. Moreau Grand Electric Cooperative, February 9, 1967 Loss of a pin on a 69 kv line interrupted power to some 2,500 customers with a load of about 2,000 kilowatts in the Timber Lake, Eagle Butte, Dupree, Isabel, and McLaughlin areas of South Dakota for 20 minutes. Ohio Edison Company, February IS, 1967 High winds blew construction material into the Cloverdale substation, so severely damaging one of the double busses that it had to be cut away. Service to 20,000 customers in Massillon, Ohio, amounting to 50,000 kilowatts, was interrupted for 55 minutes. Public Service Company of Indiana, February 17, 1967 Failure of a transformer tap-changer at Batesville, Indiana, caused a short circuit in the primary winding. An apparent operating error in subsequent switching actuated a differential relay, leading to additional checking of the circuits before service was restored. About 28,000 kilowatts of load and 6,180 customers were interrupted for 33 minutes. Burbank, California, Municipal, February 20, 1967 A fault on the City of Los Angeles system resulted in loss of the City of Burbank’s 55 mw generating unit. Service to 3,000 customers amounting to 10,000 kilowatts was interrupted for 22 minutes. Carolina Power d Light Company, February 24, 1967 A broken insulator resulted in tripping of a 1151 12 kv transformer at West Asheville, North Carolina substation. About 16,000 customers and 27,000 kilowatts of load were interrupted for one hour and 52 minutes. Tennessee Valley Authority, February 25, 1967 A high temperature detector removed a transformer from service at Johnson City, Tennessee. No damage was apparent and when restored to service the transformer continued to function normally. Loads of 36,700 kilowatts were interrupted for 36 minutes. 190 Arizona Public Service Company, February 25,1967 An area in and around the towns of Gila Bend, Ajo, Pheba, Hyder, Aztec, and Horn in southwestern Arizona were without power for about 29 minutes after a light plane flew through a 69 kv line. Total load for the 4,500 customers affected was about 25,000 kilowatts. Georgia Power Company, February 27, 1967 Service was interrupted to parts of Fulton and Cobb County, Georgia, including parts of Atlanta, Smyrna, and Marietta, when an overhead ground wire fell into a 115 kv line. 56,000 kilowatts of load were interrupted-20,000 customers for 31 minutes and the Lockheed-Georgia plant for 43 minutes. Texas Power t3 Light Company, February 28,1967 An insulator failure at Paine switching station interrupted the 69 kv bus, including a 138/69 kv transformer. Subsequent trouble with the transformer breaker prolonged the interruption. 30,000 kilowatts of load to 18,000 customers in a 900 square mile area around the towns of Bonham, McKinney, Gainesville, Sherman, and several small communities were interrupted for 33 minutes. Duquesne Light Company, March 6,1967 Flood-borne debris clogged the cooling water intakes to the Elrama 325 mw generating station, causing it to be shut down. Ties with other systems were inadequate and eight industrial customers curtailed 120 mw of load for a maximum of four hours and 36 minutes. The area affected was in Allegheny and Beaver counties in and near Pittsburgh, Pennsylvania. Pacific Power & Light Company, March 10, 1967 28,000 kilowatts and 6,000 customers in and around Crescent City, California, were interrupted from 61 minutes to three hours and 16 minutes. NO facilities were found to be damaged, and the interruption is believed to have resulted from heavy snow accumulation on a 120 kv line in the vicinity of Oregon Mountain, California. Tennessee Valley Authority, March 10, 1967 The failure of a current transformer at the Bowling Green, Kentucky, substation resulted in a 50,000 kilowatt interruption for 18 minutes to the City of Bowling Green and the Warren County Rural Electric Cooperative Cooperation. Moreau ( 12,1967 Icing cc terruption of 2,000 k Eagle Bu South Dal restored i! Western 1967 More t! area, inch Aluminun Bureau o interrupte ville Pow to Belling lators. Pr Sedro WC loaded an 1 line op Columbia surge whc the Canal which car Oregon 1 der, in U Sacramer 1967 During off in th Pacific G lines sup1 MUD. S 50,000 b minutes. Grand R Servic em near for nine failed on Sherrard Insula of servic area aro kilowattr Moreau Grand Electric Cooperative, Inc., March 12,1967 Marquette Board of Light and Power, March 26, 1967 Icing conditions on 69 kv lines resulted in an interruption of service to 2,200 customers with a load of 2,000 kilowatts in the area around Timber Lake, Eagle Butte, Dupree, Isabel, and McLaughlin, South Dakota. Lines were sectionalized and service restored in one hour and 13 minutes. The entire 10,500 kilowatt load and 8,500 customers of Marquette, Michigan, system was lost for 50 minutes when a broken insulator caused tripping of a new generating station. Western United States and Canada, March 14, 1967 More than 50,000 customers over a widespread area, including the 256,000 kilowatt load of Intalco Aluminum at Bellingham, Washington, and the Bureau of Standards at Denver, Colorado, were interrupted for as much as 24 minutes after Bonneville Power Administration opened its Snohomish to Bellingham 230-kv line to replace damaged insulators. Puget Sound Power & Light Company’s Sedro Wolley-Beverly Park No. 2 line became overloaded and was opened manually. The parallel No. 1 line opened by relay. Two 230-kv lines to British Columbia either overloaded or were tripped by a surge when Puget’s lines were reclosed. The loss of the Canadian lines created a 480,000 kilowatt surge which caused tripping of tie lines at the CaliforniaOregon boundary, at the Arizona-California border, in Utah, and across Colorado. Sacramento Municipal Utility District, March 16, 1967 During high winds, a jumper connection burned off in the Brighton, California, substation of the Pacific Gas & Electric Company, tripping the two lines supplying the Hedge substation of Sacramento MUD. Service was lost to 37,748 customers and 50,000 kilowatts in Sacramento County for 23 minutes. Grand River Dam Authority, March 19,1967 Service was interrupted to two industrial customers near Choteau Generating Plant in Oklahoma for nine hours and 25 minutes when a cross arm failed on a 115 kv line and set the pole on fire. Sherrard Power System, March 19,1967 Insulator contamination caused an interruption of service.to 5,000 customers in a 500 square mile area around Orion, Illinois. The load was 10,300 kilowatts. Pacific Power @ Light Company, March 26, 1967 A 69 kv line fault interrupted service for six hours and 32 minutes to 2,500 customers with a load of 5,000 kilowatts in the Enterprise and Elgin, Oregon, areas. Insulators on sections of the line owned by both Pacific Power & Light Company and California Pacific Utilities had beendamaged by gun fire. Tennessee Valley Authority, March 27, 1967 A bird caused an arc across an insulator at the Mayfidd substation, apparently severing a line conductor. Service was interrupted to 25,000 customers in Mayfield, Kentucky, and surrounding areas for 59 minutes. Total load lost was 52,000 kilowatts. Georgia Power Company, March 27,1967 Both Atkinson-Marietta 115 kv lines were open at Marietta for work on the lines. This upset relay coordination. When a 115 kv jumper connection burned off at a clamp in the Marietta substation, 23,800 kilowatts in the area were interrupted for 14 minutes, 2,376 kilowatts were interrupted for two hours and 2,380 kilowatts were out for 50 minutes. Puget Sound Power t3 Light Company, March 28, 1967 One of two 115 kv underground circuits to Mercer Island (East Seattle) was taken out of service in connection with the relocation of a 230 kv line. The load on the remaining circuit was interrupted when the underground cable or a pothead failed. About 22,000 customers with a load of 45,000 kilowatts were without power for 27 minutes. Utah Power B Light Company, March 28, 1967 A cooling water leak spraying on a transformer and a circuit breaker caused the breaker to trip. The trouble was not correctly identified and the equipment was returned to service in 11 minutes, only to trip out again. The second outage was for 9 minutes. The 35,000 kilowatt loss affected some 8,400 customers in Grand, Carbon, San Juan, and . . 3 . . TT. -1Emery counties in eastern and soutneastern uran. Bangor Hydro-Electric Company, April 12, 1967 South Carolina Electric and Gas Company, A loose connection caused a flashover on two 46 kv insulators on the main bus at the Graham generating station which resulted in loss of power to about 42,000 customers with a load of about 35,000 kilowatts in Bangor, Brewer, Veazie, Orono, Stillwater, Orrington, Hampden, East Corinth, LaGrange, and Milo, Maine. Service was completely restored in 27 minutes. 8,1967 Service to some 15,000 customers amounting to 38,000 kilowatts in Charleston, South Carolina, was interrupted for 23 minutes when a tree fell on a 115 kv line. Jefferson Davis Electric Coop, Inc., April 13, 1967 Insulation contamination caused an interruption of service to some 2,000 customers amounting to about 6,000 kw in Cameron Parish, Louisiana, for 3 hours and 23 minutes. Muscatine, Iowa Municipal Electric Plant, April IS,1967 The system’s entire load of approximately 27,000 kilowatts and 8,000 customers was interrupted for approximately two and one-half hours after high winds felled a large tree across a 69 kv line near the system’s 56,000 kilowatt generating plant. Bailey County Electric Coop. Association, April 19, 1967 Failure of an insulator on a 69 kv line resulted in the loss of 9,000 kilowatts of load in Bailey County, Texas, for one hour. Western United States and Canada, April 20, 1967 Failure of BPA’s Snohomish-Bellingham 230 kv line during the installation of a transfer trip relay caused numerous transmission lines to trip in Washington, Idaho, and Montana. About 800,000 kilowatts of load in the Bellingham, Washington, area and about 210,000 kilowatts of load in southern Idaho were interrupted for a few minutes. The east-west transmission ties in Montana and Nebraska did not trip during the initial disturbance but tripped eleven minutes later as a result of heavy flows to the west. Community Public Service Company, May I, 1967 High winds and lightning caused a 138 kv line to trip and result in loss of service for one hour to 3,140 customers in Collin and Fannin County, Texas. Carolina Power & Light Company, May 1, 1967 25,000 kilowatts of load in the city of Rocky Mount, North Carolina, was interrupted for about an hour when the 110 kv bus at the Rocky Mount substation tripped. Cause of the interruption is unknown. 192 May Gulf States Utilities Company, May 11, 1967 An interruption of 696,000 kilowatts affecting 163,000 customers occurred in an area of southeast Texas. Loss of service ranged from 45 minutes to about seven hours. The interruption was caused by failure of a 138 kv lightning arrestor and a high side bushing on a 500 mva transformer at Sabine generating station. Clearing of this fault caused loss of a 440,000 kilowatt unit. About five minutes later, failure of a wave trap caused tripping of two 138 kv lines and resulted in complete collapse of the Company’s Texas load. Virginia Electric tY Power Company, May 12,1967 The failure of a lightning arrestor on a 115 kv line resulted in an interruption of service to 12,500 customers with a load of 38,000 kilowatts in Richmond, Virginia, for 24 minutes. City of Greenville, Texas, May 12, 1967 Failure of a static exciter on the municipal system’s steam-electric station caused loss of 17,000 kilowatts of load for about two and one-half hours. Cleveland Electric Illuminating Company, May 17, 1967 Service to 66,000 customers with a load of 80,000 kilowatts was interrupted for 27 minutes when four 132 kv transformer bank circuit breakers were manually tripped at the Clinton Substation. Company reported that barbed wire barriers across the top of the main gate to the substation had been cut. South Texas Electric Cooperative, Inc., May 19, 1967 Operation of a 69 kv bus differential relay at the Sam Rayburn generating station separated the dation from its load. Service was interrupted to 17,135 customers and 14,600 kilowatts for 24 minutes. Bonneville Power Administration, May 25, 1967 Damage to BPA’s Bell-Metaline Falls 115 kv line in the Spokane, Washington area at 7: 39 P.M., PDT, resulted in the interruption for as much as one hour and sixteen minutes of approximately 31,000 kw to several thousand customers of the Pend Oreille PUD and Washington Water Power Company sys- terns. The ing plane cident. Cincinnati Failure ure of a p station of in control to some L kilowatts i tucky, for to over sin tinued to de-energiz and to in downtowr Snohomis Approx watts of lc a brush fi kv line SI County nc Pennsylva tion, June At abo tripped a Company erations j terns. The line damage was caused by a crop dusting plane which was damaged slightly in the accident. Cincinnati Gas & Electric Company, May 26, 1967 Failure of a 13 kv cable and the subsequent failure of a pothead on a voltage regulator in the substation of the West End generating station and fire in control cables in the station interrupted service to some 40,000 customers with a load of 48,000 kilowatts in Cincinnati, Ohio, and Covington, Kentucky, for periods of time ranging from 30 minutes to over six hours. The fire in the control cables continued to the next day when it was necessary to de-energize all incoming circuits to the substation and to interrupt service to 6,500 customers in the downtown area of Cincinnati. Snohomish County PUD, June 2,1967 Approximately 15,000 customers and 32,000 kilowatts of load were interrupted for 29 minutes when a brush fire burned a pole and crossarm on a 115 kv line serving the northern part of Snohomish County near Everett, Washington. Pennsyluania-New Jersey-Maryland Interconnection, June 5,1967 At about 10: 16 A.M., EDT, excessive loading tripped a 220 kv line on the Philadelphia Electric Company’s system which in turn caused other operations from instability or overloads until power service was lost in a 15,000 square mile area covering parts of Pennsylvania, New Jersey, Maryland, and Delaware. Estimates indicated that approximately 13,000,000 people and 1 O,OOO,OOO kilowatts of load were affected. Although about a dozen generating units suffered varying amounts of damage during the disturbance, service was gradually restored to all areas within about ten hours. A detailed resume of this interruption is included in Chapter 3 of the main report. Utah Power and Light Company, June 9, 1967 At 6 : 48 P.M., MST, trouble outside of the Utah Power and Light Company system resulted in the tripping of a 46 kv line to Gadsby Steam Electric Plant and a 130 kv line serving the Salt Lake City distribution system. Approximately 105,000 kilowatts of load was interrupted for one minute and 50,000 kilowatts for 15 minutes. Pennsylvania Power and Light Company, June 12, 1967 Approximately 78,000 customers and 163,000 kilowatts of load in Lycoming and Schuylkill Counties in Pennsylvania were interrupted at 2 : 01 P.M., EDT, when a 220 kv lightning arrester failed on a 220/66 kv transformer bank at Frackville Substation. The failure occurred during clear weather and the cause was unknown. Service was restored to 113 mw within 15 minutes and to the remaining 50 mw within 24 minutes. 193 T ABLE E-l .-Rlmml of power intmu@ons 1954-1966 Approximate Location Date Probable Cause Oicge .1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 4: 4 4; 4f 41 5f 51 5: 5: 9 5: 5t 5’ 194 L-30-54 3-30-54 9-54 &lo-54 &15-54 >30-54 2-19-54 3-55 3-55 j-25-55 6-55 7- 7-55 8-55 8-55 lo-55 6-56 9-28-56 Q-18-56 Z-14-56 I- 3-57 l-23-57 l-27-57 l-57 3-57 4- 9-57 5-20-57 5-23-57 6-l 7-57 6-27-57 8- 2-57 o-31-57 3-20-58 6- 4-58 6-18-58 6-17-58 ?- 2-58 ?- 2-58 9-58 12-58 l- 2-59 l- 7-59 1-15-59 l-29-59 8-17-5:3 12-28-5! 3 l- ?-6f 1 3- l-6( 1 3- 2-6( 1 4-28-6t I 5- 54 1 5-23-6t 1 6-29-6t 1 9- !3-6( 3 9-l l-6(3 3- 3-6 1 6-13-6 1 6-21-6 1 C Ileveland, Ohio . . . . . . . . . . . . . . . . . . . . . . . . . . . . . E astern Massachusetts. . . . . . . . . . . . . . . . . . . . . . . Nlortheast Coast. . . . . . . . . . . . . . . . . . . . . . . . . . . . CChicago, Ill. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . E ast coast. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . CCleveland, Ohio. . . . . . . . . . . . . . . . . . . . . . . . . . . . C hicago,Ill................................ Peoria,Ill.................................. 11 ndiana, Ohio, Pennsylvania. . . . . . . . . . . . . . . . . . s ummit, N.J. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . C llney,Tex . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . N lew York, N.Y. . . . . . . . . . . . . . . . . . . . . . . . . . . . . E,ast coast. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . K lew England Coast. . . . . . . . . . . . . . . . . . . . . . . . . lx lortheast U.S. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . s tephensville, Wii. . . . . . . . . . . . . . . . . . . . . . . . . . . T ‘oledo,Ohio . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B lew York, N.Y. . . . . . . . . . . . . . . . . . . . . . . . . . . . . C:onnccticut, N. J . . . . . . . . . . . . . . . . . . . . . . . . . . . . P‘lattsburg, N.Y. . . . . . . . . . . . . . . . . . . . . . . . . . . . . P ‘eru, Ind. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Little Rock, Ark. . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 ‘enncssee, Kentucky, West Virginia. . . . . . . . . . Ii Kansas, Colorado, Texas, Oklahoma, New Mexico I Dallas, Tex. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I!Kansas-Missouri . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Elast Aurora, N.Y. . . . . . . . . . . . . . . . . . . . . . . . . . . PTew York, N.Y . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I ouisiana-Texas . . . . . . . . . . . . . . . . . . . . . . . . . . . . bYashington, D.C. . . . . . . . . . . . . . . . . . . . . . . . . . . nvlinneapolis, Minn. . . . . . . . . . . . . . . . . . . . . . . . . . Pgortheast Coast . . . . . . . . . . . . . . . . . . . . . . . . . . . . . sit. Paul, Minn . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ISldorado, Kans. . . . . . . . . . . . . . . . . . . . . . . . . . . . . I,ouisiana-Mississippi. . . . . . . . . . . . . . . . . . . . . . . . I<earney,N.J . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (Charleston, S.C . . . . . . . . . . . . . . . . . . . . . . . . . . . . . rrTorth Carolina. . . . . . . . . . . . . . . . . . . . . . . . . . . . . tUbuquerque, N. Mex. . . . . . . . . . . . . . . . . . . . . . ESeattle, Wash . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 jan Antonio, Tex. . . . . . . . . . . . . . . . . . . . . . . . . . . Ikrgen, N.J. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . :k. Louis, MO . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . rNew York, N.Y. . . . . . . . . . . . . . . . . . . . . . . . . . . . Western New York . . . . . . . . . . . . . . . . . . . . . . . . . Orange,N.J . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Tennessee, Alabama, Georgia. . . . . . . . . . . . . . . . Texas, Louisiana. . . . . . . . . . . . . . . . . . . . . . . . . . . Oklahoma City, Okla . . . . . . . . . . . . . . . . . . . . . . . Oklahoma. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Hilo, Hawaii. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cleveland, Ohio. . . . . . . . . . . . . . . . . . . . . . . . . . . East Coast. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Long Island, N.Y . . . . . . . . . . . . . . . . . . . . . . . . . . Norwalk,Conn . . . . . . . . . . . . . . . . . . . . . . . . . . . . San Francisco, Calif. . . . . . . . . . . . . . . . . . . . . . . . Southern Idaho. . . . . . . . . . . . . . . . . . . . . . . . . . . . Major Short Circuit. Hurricane Carol. Hurricane Edna. Flood. Hurricane Hazel. snow Storm. Turbine Explosion Transformer Failure. Storm. Lightning. Weather Balloon Drifted Onto Line. Dverload of Distribution Feeders. Hurricane Connie. Hurricane Diane. Floods. Wind Storm. He Line Breaker Misoperation. Transformer Tap Changer Failure. ice Storm. Distribution Feeder and Transformer Failure. Flood. Ice Storm. Floods. Blizzard. Tornado. Tornado. Wind Storm. Curtailment. Hurricane Audrey. Underground Cable Failure. Lightning Arrestor Failure. Blizzard. Tornado. Tornado. Operating Error. Distribution Transformer Failure. Gas Line Fire. Hurricane Helene. Snow Storm. Substation Fire. Substation Breaker Failure. Power Plant Failure. Ice Storm. Underground Cable Failures. Sleet. Fire. Ice Storm. Ice Storm. Tornado. Tornadoes. Tidal Wave. Underground Cable Failure. Hurricane Donna. Hurricane Donna. Substation Equipment Explosion. Circuit Breaker Explosion. Fire. 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 8C 81 82 81 84 8: 8t 8: 81 8: 90 91 92 93 94 95 96 97 98 99 108 101 102 103 104 105 106 107 108 109 110 111 TABLE hrtage No. Date E-l.-Rlsuml of power interruptions 1954-I966-Continued Approximate Location Probable Cause - .- 58 59 60 6-29-61 7- 3-61 7-13-61 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 8-4-61 8-29-6 1 9-l 1-61 9-21-61 1 1-13-61 3-l 3-62 3-62 6-25-62 8- 5-62 8-l 3-62 8-20-62 8-20-62 O-l 2-62 O-12-62 .o-12-62 .2-30-62 3-17-63 7-23-63 6-13-63 6-19-63 6-28-63 12- - 6 3 2-24-64 3- 4-64 3-10-64 4-3-64 4- 3-64 4- - 6 4 5-23-64 8-10-64 91 92 93 94 95 96 97 98 99 lot 101 102 103 104 105 8-27-64 8-27-64 9-9-64 lo- ‘i-64 11-19-64 1 l-30-64 12- 4-64 12- 5-64 12-22-64 l- 7-65 l-23-65 l-28-65 2-17-6: 4- 7-6: 4-l 1-6: 1Ot 105 1Of 101 ll( 111 4-16-6: 4-27X 4-29-6: 5-18-6! 6-16-6: 6-27-6: iouthernIdaho . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Power Plant Failure. Transmission Line Failure. kouthern Idaho . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Bushing Failures in Adjacent Distribl ution Feeder Jew York, N.Y. . . . . . . . . . . . . . . . . . . . . . . . . . . . . Breakers. Transmission Line Flashover. Cleveland, Ohio. . . . . . . . . . . . . . . . . . . . . . . . . . . . Rain and Lightning. Nassau, N.Y . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . &.lveston, Tex . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Hurricane Carla. ,ong Island, N.Y. . . . . . . . . . . . . . . . . . . . . . . . . . . Hurricane Esther. ZlPaso,Tex . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Snow Storm. Xendale, Calif. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Operating Error. Atlantic City, N.J. . . . . . . . . . . . . . . . . . . . . . . . . . . Storm. Operating Error. owa-Nebraska. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Underground Cable Failure. jtaten Island, N.Y. . . . . . . . . . . . . . . . . . . . . . . . . . ‘asadena, Calif. . . . . . . . . . . . . . . . . . . . . . . . . . . . . Failure of Four Oil Filled Cutouts. 3rooklyn, N.Y. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Underground Cable FailureXeveland, Ohio. . . . . . . . . . . . . . . . . . . . . . . . . . . . Tornado. ?ortland,Oreg . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . storm. Nashington-Oregon . . . . . . . . . . . . . . . . . . . . . . . . . S t o r m . 3ellingham, Wash. . . . . . . . . . . . . . . . . . . . . . . . . . . S t o r m . Storm and Wind. Vassau,N.Y . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Circuit Breaker Control Circuit Failure. I’ampa, Fla . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Failure of Plant Circulating Water Pump. Blackwell, Okla. . . . . . . . . . . . . . . . . . . . . . . . . . . . Failure of Transmission Line Splice. Cansas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . YVestchester, N.Y. . . . . . . . . . . . . . . . . . . . . . . . . . . Hot Weather. Staten Island, N.Y. . . . . . . . . . . . . . . . . . . . . . . . . Hot Weather. Dam Failure. Los Angeles, Calii. . . . . . . . . . . . . . . . . . . . . . . . . . rexas-Oklahoma. . . . . . . . . . . . . . . . . . . . . . . . . . . Exciter Flashed Over. jouthwest Tennessee . . . . . . . . . . . . . . . . . . . . . . . Tornado. Rain and Sleet. Kingston, N.Y. . . . . . . . . . . . . . . . . . . . . . . . . . . . . Earthquake. Alaska . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Tidal Wave. California-Oregon. . . . . . . . . . . . . . . . . . . . . . . . . . Frog in Relay. Jacksonville, Fla. . . . . . . . . . . . . . . . . . . . . . . . . . . Transmission Line Fault. Long Island, N.Y. . . . . . . . . . . . . . . . . . . . . . . . . . Gas Regulator Closed on Fuel Supply Line to Sweetwater, Tex. . . . . . . . . . . . . . . . . . . . . . . . . . . Large Power Plant. Emergency Shutdown of a 13 mw unit. Lordsburg, N. Mex . . . . . . . . . . . . . . . . . . . . . . . . . Miami,Fla. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Hurricane Cleo. North Florida. . . . . . . . . . . . . . . . . . . . . . . . . . . . . H u r r i c a n e D o r a . Louisiana. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Hurricane Hilda. Submarine Cable Failure. Northwest Washington. . . . . . . . . . . . . . . . . . . . . Teaneck,N.J . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Circuit Breaker Failed to Operate. Eastern N.Y.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Ice Storm. Michigan City, Ind . . . . . . . . . . . . . . . . . . . . . . . . . Line Short. Northern California. . . . . . . . . . . . . . . . . . . . . . . . F l o o d s . Western Pennsylvania . . . . . . . . . . . . . . . . . . . . . . . Boiler Tube Failure. Chicago, Ill. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I c e S t o r m s . Iowa-Nebraska . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Operating Error. Lawrenceburg, Ind. . . . . . . . . . . . . . . . . . . . . . . . . . Operating Error. Minneapolis, Minn. . . . . . . . . . . . . . . . . . . . . . . . . . Tornadoes. Iowa, Illinois, Indiana, Wisconsin, Michigan 1, Tornadoes. Ohio. Bird Nest Fell on Power Line. Chester, Pa . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Operating Error. Arizona . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Earthquake. Tacoma,Wash . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Mud Slide on Powerhouse. Lower Baker, Wash . . . . . . . . . . . . . . . . . . . . . . . . . Floods. Denver, Colo. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . -.-. . DesMeines,Iowa . . . . . . . . . . . . . . . . . . . . . . . . . . TABLE 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 196 E-l .-Rhmc’ of power interruptions 19%1966-Continued Date Approximate Location 8-29-65 9-9-65 s9-65 ll- 9-65 1 l-22-65 12- 2-65 12- 6-65 l-24-66 l-28-66 3- 3-66 4-26-66 5-13e 5-16-66 6- 7-66 6-8-66 7- 3-66 7- 7-66 7-l l-66 7-l l-66 7-19-66 7-12-66 7-13-66 7-14-66 7-26-66 7-27-66 7-26 & 27-66 8-29-66 ll- 3-66 ll- 5-66 1 l-10-66 1 l-14-66 1 l-22-66 1 l-24-66 12- 2-66 12-14-66 12-19-66 12-23-66 Des Moines, Iowa. . . . . . . . . . . . . . . Louisiana. . . . . . . . . . . . . . . . . . . . . . . Florida. . . . . . . . . . . . . . . . . . . . . . . . Northeast U.S . . . . . . . . . . . . . . . . . . Elgin, Ill . . . . . . . . . . . . . . . . . . . . . . . . Texas-New Mexico. . . . . . . . . . . . . . Beaumont, Tex. . . . . . . . . . . . . . . . Los Angeles, Calif. . . . . . . . . . . . . . . . Dallas, Tex . . . . . . . . . . . . . . . . . . . . . . Jackson, Miss. . . . . . . . . . . . . ... western u.s . . . . . . . . . . . . . . . . . . . . . Anchorage, Alaska. . . . . . . . . . . . . Columbus, Ga. . . . . . . . . . . . . . . . . . Western U.S . . . . . . . . . . :. . . . . . . . Clearwater, Fla. . . . . . . . . . . . . . . . Fairfax, Va. . . . . . . . . . . . . . . . . Nashville, Tenn. . . . . . . . . . . . . . . ... Nebraska . . . . . . . . . . . . . . . . ................... St. Louis, M O . . . . . . . . . . . . ................... Los Angeles, Calif. . . . . . . . ................... Washington-Idaho. . . . . . . . ................... Tulsa, Okla. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Houston, Tex. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ElPaso,Tex . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Oregon,Calii . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Travis Ail Base, Calii. . . . . . . . . . . . . . . . . . . . . . . . . .. . .. Farmington, N. Mex. . . . Southern Virginia. . . . . . . . . .. Atlanta, Ga. . . . . . . . . . . . .. . Oakland, Calif. . . . . . . . . .. .. LasVegas,Nev.. . . . . . . . . . . . .. .. .. . Chicago, Ill. . . . . . . . . . . . .. .. Seattle, Wash. . . . . . . . . . .. Southeastern Missouri. . . . . Austin, Tex. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Sandy Spring, Ga. . . . . . . . . . . . . . . . . . . . . . . . . . . . Jonesboro, Ark. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Probable Cause Lightning. Hurricane Betsy. Hurricane Betsy. Undesired Relay Operation. Wind. Loss of Fuel Supply. Misoperation of Supervisory (Control). Operating Error. Ice and Wind. Tornado. Erroneous Telemeter Signal. Pranksters. Tornado. False Relaying of 345 KV Circuit. Hurricane Alma. Transformer Failure. Winds. Faulty Relay Setting. Curtailment. Breaker Operations-Cause Unknown. Lightning. Car Hit Pole. Transformer Failure. Lightning and Wind. Line Failure and Breaker Operations. Line Flashover During Maintenance. Breaker Bushing Failure. Rain Storm. Breaker Failure. Vandalism During Strike. Breaker Bushing Failure. Generator Oil Pressure Failure. Transformer Relay Operation-Cause Unknown. Fault on Secondary System. Tree Felled on Line. Lines Tripped Out-Cause Unknown. Sabotage of Control Circuits. Galloping Conductors. POWER INTERRUPTIONS 1954 - 1966 FI~IJRE E - l .“.S. GOVERNMENT PRlNTlNG OFFICE: 1967 O-267-781