SCOPE: THIS STANDARD SHOWS APPROVED SOURCES AND INSTALLATION DETAILS FOR 6'x8', 8'x10', AND 10'x12' TRANSFORMER PAD WITH CABLE BOX REQUIRED FOR 12kV, 3PH., PADMOUNT TRANSFORMER INSTALLATION. BOLTED, GALVANIZED STEEL DIAMOND TREAD SAFETY FLOOR PLATE COVER WITH TAMPERPROOF LIFT HOLES OVER 30" x 48" CLEAR ACCESS OPENING 6' 1'-6" 8' 1 5/8" x 1 5/8" UNISTRUT INSERT, GALV. 2 REQ'D PER PAD 6" 4' 6" 2'-6" FRONT 4"-5" 4' 7' 16"-20" THIN WALL KNOCKOUTS EACH CORNER 24" 3'-6" F 12" 6" DEEP X 12" WIDE BASE 6" 1" THREADED INSERT LOCATED EACH WALL FILENAME: CU1600-20 REV 12 FIGURE 1 6'x8' PAD CABLE BOX SIZE FIGURE 4'x7' 1 8'x10' 5'x8'-6" 2 10'x12' 5'x8'-6" 3 TRANSFORMER SIZE (KVA) PAD SIZE 75 - 150 (SEE NOTE J) 6'x8'-6" 300 - 2500 2500 - 3750 6'x8' CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT ELECTRICAL DIVISION T&D CONSTRUCTION STANDARDS T&D MGR APPROVALS FIELD MGR OPER. MGR REVISION KEYS: MFG'R. RISER SECTION CATALOG NO. JENSEN K68-SB42-16 UTILITY VLT. ANAHEIM 686SB VPMT4X7-6X8CONT JENSEN K810-SB60-16 PB586-R12-FF UTILITY VLT. JENSEN ANAHEIM 810SB 0130250 K1012-SB60-16 PB986-R12-FF UTILITY VLT. ANAHEIM 1012SB ADDED / REVISED TEXT COMPATIBLE UNIT NO. 0130250 VPMT5X8-8X10 VPMT5X8-10X12 NEW SHEET ADDED / REVISED MATERIAL TRANSFORMER PAD WITH CABLE BOX FOR 12KV 3 PHASE PADMOUNT TRANSFORMERS 12 01-11 1 OF 5 REVISION NO. ISSUE DATE : SHEET CONSTRUCTION STANDARD: CU1600-20 3/4" DEEP NOTCH (UNDERSIDE OF PAD) FOR LOCATING ON CABLE BOX. 10' 8' 24" 8" 8" 6" 30" 60" 1 5/8" X 1 5/8" UNISTRUT GALV., 2 REQ'D. PAD FRONT 5'x8'6"x12" HIGH RISER SECTION TO INCREASE BOX DEPTH FOR MULTIPLE CONDUIT RUNS. GALV. STEEL DIAMOND TREAD SAFETY FLOOR PLATE COVER WITH TAMPERPROOF BOLTS AND LIFT HOLES OVER 30" X 48" CLEAR ACCESS OPENING MARKED "ELECTRIC" 6" 5' 1/2" DIA. PLASTIC INSERTS 6 PER EA. SIDE WALL 2 PER EA. END WALL 8'-6" 30" 24" 4" DIA. TERMINATORS OR 5" KNOCKOUTS 16 PLACES EACH WALL 32 1/2" 4" 5'-1" 10" 6" 8" 12"Ø SUMP 8" 8" 7" FILENAME: CU1600-20 REV 12 C L l" PULL IRONS 8 PLACES FIGURE 2 CAPPED 1" PVC 4" DIA. TERMINATORS LOCATION (TYPICAL) CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT ELECTRICAL DIVISION T&D CONSTRUCTION STANDARDS T&D MGR APPROVALS FIELD MGR OPER. MGR 6" CAPPED 1" SCH. 40 PVC CONDUIT 2 PER EA. END WALL REVISION KEYS: 8'x10' PAD ADDED / REVISED TEXT NEW SHEET ADDED / REVISED MATERIAL TRANSFORMER PAD WITH CABLE BOX FOR 12KV 3 PHASE PADMOUNT TRANSFORMERS 12 01-11 2 OF 5 REVISION NO. ISSUE DATE : SHEET CONSTRUCTION STANDARD: CU1600-20 3/4" DEEP NOTCH (UNDERSIDE OF PAD) FOR LOCATING ON CABLE BOX. 12' 10' 24" 8" 30" 6" 6" 60" 1 5/8" X 1 5/8" UNISTRUT PAD FRONT 8" GALV. STEEL DIAMOND TREAD SAFETY FLOOR PLATE COVER WITH TAMPERPROOF BOLTS AND LIFT HOLES OVER 30" X 48" CLEAR ACCESS OPENING MARKED "ELECTRIC" 5'x8'6"x12" HIGH RISER SECTION TO INCREASE BOX DEPTH FOR MULTIPLE CONDUIT RUNS. 6" 5' 1/2" DIA. PLASTIC INSERTS 6 PER EA. SIDE WALL 2 PER EA. END WALL 8'-6" 30" 24" 4" DIA. TERMINATORS OR 5" KNOCKOUTS 16 PLACES EACH WALL 32 1/2" 4" 5'-1" 10" 6" 8" 12"Ø SUMP FILENAME: CU1600-20 REV 12 8" 8" 7" C L l" PULL IRONS 8 PLACES FIGURE 3 CAPPED 1" PVC 4" DIA. TERMINATORS LOCATION (TYPICAL) CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT ELECTRICAL DIVISION T&D CONSTRUCTION STANDARDS T&D MGR APPROVALS FIELD MGR OPER. MGR 6" CAPPED 1" SCH. 40 PVC CONDUIT 2 PER EA. END WALL REVISION KEYS: 10'x12' PAD ADDED / REVISED TEXT NEW SHEET ADDED / REVISED MATERIAL TRANSFORMER PAD WITH CABLE BOX FOR 12KV 3 PHASE PADMOUNT TRANSFORMERS 12 01-11 3 OF 5 REVISION NO. ISSUE DATE : SHEET CONSTRUCTION STANDARD: CU1600-20 TYPICAL CLEARANCE & GROUNDING REQUIREMENTS 1O' REQUIRED MINIMUM CLEARANCE (PUBLIC UTILITY EASEMENT) SEE NOTE G MIN. SEE NOTE G PAD FRONT 6' MIN. SPACING GROUND RODS CABLE OPENING FILENAME: CU1600-20 REV 12 MATERIAL LIST FOR INSTALLATION OF TRANSFORMER PAD WITH CABLE BOX ITEM QTY 1 2 2 2 3 40' ANAHEIM PART NO. COMPATIBLE UNITS ROD, GROUND, 5/8" x 8' COPPERCLAD 547005 GRNDROD CLAMP, GROUND ROD 568075 GRNDCLMP-ROD WIRE, #4 B.C., SOLID, SOFT DRAWN 446150 W4CUBARE-SD DESCRIPTION GROUND WIRE, MINIMUM OF #4 SOLID, SOFT DRAWN, BARE COPPER WIRE IN ONE CONTINUOUS LENGTH, CONNECTED BETWEEN GROUND RODS AND BOTH ENDS EXTENDING MINIMUM OF 72" ABOVE TRANSFORMER PAD AT CABLE OPENING. COIL WIRE IN VAULT BELOW. FURNISHED AND INSTALLED BY CONTRACTOR/ DEVELOPER 2 72" FINISH GRADE 3 KNOCKOUTS OR CONDUIT TERMINATORS SEE NOTE E 6" SEE NOTE C 1 CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT ELECTRICAL DIVISION T&D CONSTRUCTION STANDARDS T&D MGR APPROVALS FIELD MGR OPER. MGR REVISION KEYS: 2 - 5/8" DIA. x 8' LONG COPPER CLAD GROUND RODS, SPACED 6' MINIMUM APART, EACH WITH BRONZE GROUND CLAMP PER CU 16OO-25C. TOP OF DRIVEN RODS SHALL BE MAXIMUM OF 6" ABOVE GRAVEL BASE. FURNISHED AND INSTALLED BY CONTRACTOR/DEVELOPER. ADDED / REVISED TEXT NEW SHEET ADDED / REVISED MATERIAL TRANSFORMER PAD WITH CABLE BOX FOR 12KV 3 PHASE PADMOUNT TRANSFORMERS 12 01-11 4 OF 5 REVISION NO. ISSUE DATE : SHEET CONSTRUCTION STANDARD: CU1600-20 SAFETY COVER FOR PMC & PMT SLAB TOP COVER OPENINGS WHEN NOT IN SERVICE 1'-0 " EXISTING SAFETY FLOOR PLATE " 2'-6 1/4 " 1'-6 TYP, 2 PL. 3/8-16 x 8" HEX HEAD BOLT (2 REQ'D) 2" x 1 1/2" x 1'10" STEEL CHANNEL (2 REQ'D) 9/16" DIA. 2'-0" X 5'-6" X 3/16" DIAMOND TREAD SAFETY FLOOR PLATE 3/8-16 HEX NUT (2 REQ'D) TYPICAL INSTALLATION VIEW SEEN FROM BELOW NOT TO SCALE NOTES: A. CONCRETE COMPRESSIVE STRENGTH SHALL BE 4500 PSI IN 28 DAYS. B. THE STRUCTURE SHALL MEET THE APPLICABLE REQUIREMENTS OF THE LATEST REVISED EDITIONS OF THE FOLLOWING STANDARDS: ACI-318-89 BUILDING CODE, ASTM C-857 MINIMUM STRUCTURAL DESIGN LOADING FOR UNDERGROUND PRECAST CONCRETE UTILITY STRUCTURES, AND AASHTO STANDARD SPECIFICATION FOR HIGHWAY BRIDGES. C. D. E. F. FILENAME: CU1600-20 REV 12 G. H. J. K. ALL OPENINGS IN VAULT FOR CONDUITS AND GROUND WIRE SHALL BE GROUTED TO PREVENT WATER INTRUSION. CONTRACTOR/DEVELOPER INSTALLED FACILITIES SHALL BE INSPECTED BY UTILITY ELECTRICAL INSPECTOR TO ENSURE COMPLIANCE TO THIS STANDARD AND WORK ORDER DRAWING. REQUIRED MINIMUM CLEARANCE (PUBLIC UTILITY EASEMENT) OF 36" FOR 6' x 8' PAD OR 6O" FOR 8' x 10' AND 10' x 12' PADS ALONG THREE SIDES AND MINIMUM OF 10' REQUIRED ALONG FRONT OF EACH PAD. PROTECTIVE POSTS PER CU 1600-9, AND AS SHOWN ON ELECTRICAL ENGINEERING WORK ORDER DRAWING SHALL BE FURNISHED AND INSTALLED BY DEVELOPER/ CONTRACTOR. UTILITY MAY UPGRADE TO 300kVA ON EXISTING 6' x 8' TRANSFORMER PAD. THIS WILL REQUIRE SEALING THE BOTTOM OPENING OF THE PRIMARY COMPARTMENT WHERE IT OVERHANGS THE PAD SIDE FOR SAFETY AND COMPLIANCE WITH G.O. 128. REPLACEMENT PADS FOR MAINTENANCE: 6' x 8' PAD USE CITY P/N 486075 8' x 10' PAD USE CITY P/N 486080 REPLACEMENT ACCESS COVER, USE CITY P/N 486280. M. FOR LARGER TRANSFORMER 3750 KVA, SPECIAL ORDER 10' x 12' PAD. PUBLIC UTILITIES DEPARTMENT ELECTRICAL DIVISION T&D CONSTRUCTION STANDARDS APPROVALS FIELD MGR CONTRACTOR/DEVELOPER SHALL LOCATE AND INSTALL TRANSFORMER PAD AND VAULT IN ACCORDANCE WITH ELECTRICAL ENGINEERING WORK ORDER DRAWINGS. TRANSFORMER PAD MUST BE LEVEL. L. CITY OF ANAHEIM T&D MGR EXCAVATION PER CU 1600-4B, MINIMUM SIZE PER MANUFACTURER'S SUGGESTED EXCAVATION SIZE. OPER. MGR REVISION KEYS: ADDED / REVISED TEXT NEW SHEET ADDED / REVISED MATERIAL TRANSFORMER PAD WITH CABLE BOX FOR 12KV 3 PHASE PADMOUNT TRANSFORMERS 12 01-11 5 OF 5 REVISION NO. ISSUE DATE : SHEET CONSTRUCTION STANDARD: CU1600-20