Alan Price Director, Railway Planning and Performance Telephone 020 7282 3825 alan.price@orr.gsi.gov.uk Paul Plummer Network Rail Kings Place 90 York Way London N1 9AG 12 September 2014 Dear Paul, Enhancements Costs Adjustment Mechanism (ECAM) W001a Great Western Electrification Programme (GWeP), Route Sections 1 - 9 I am writing to you following ORR’s review of the above enhancement project as part of the ECAM process which we set out in our Final Determination. ORR has considered the project submission, received on 21/07/14, and the further information you have supplied during the period May – August 2014. We have concluded that the efficient level of funding is an AFC of £1649.1m spanning CP4 and CP5 with a CP5 component of £1343.7m. This compares to your originally submitted AFC of £1528.6m (all costs in 4Q12 prices). This represents the level of efficient expenditure for this project that we will assume as we build up the portfolio baseline for CP5 enhancements. We aim to conclude this baseline as soon as possible so that Network Rail has the certainty to deliver its obligations within a defined funding envelope. Projects included in the portfolio to be treated in this way are listed in Annex E of our final determinations. Particular points we would like to make about this submission are as follows: In the submission, the opportunities register was not as well developed as the risk register. We consider that the efficiencies in this letter are a reasonable assumption of the possible opportunities yet to be identified by the project team. To realise these savings Network Rail needs to implement stronger governance Page 1 of 17 10791241 around cost control and value management. The principal cost savings we have assumed are as follows: further cost reductions in achieving OLE clearance at structures, where there are still many pre-GRIP3 options assumed and costed. We are also concerned that clearance work may be progressing that is not absolutely necessary and hence we request that you review upcoming works as a matter of urgency. We do not however have sufficient information to make a judgement on any further saving from the Schedule 4 reduction that could arise from cancelling possession-hungry structures work. reducing the OLE specification on parts of the route with line speeds of less than 125pmh, rather than installing Series 1 OLE as currently priced. Decisions on this are urgently required to maintain the schedule and to realise these savings whilst avoiding the installation of over-specified OLE system bettering the productivity rates that have been used in the cost estimate for high output installation of masts and piled foundations, the current production rates are significantly behind what was envisaged for the HOPS. minimising the need for temporary bridge provision, as this is the largest single risk in the project Since the date of the ECAM submission, further opportunities for reducing costs have arisen, but we have not taken them into account because we consider they may impact the project outputs. These changes to outputs can be dealt with under the usual change control arrangements, whereby if agreed with stakeholders, the output will be amended in the delivery plan, and the funding adjusted accordingly. These include: the Wentloog to Cardiff independent feeders which if deleted might have a performance impact on the mainline. There is an option to wholly or partfund this through the Welsh Valley Lines electrification project. This saving has not been included in this ECAM determination for GWEp, as a full impact assessment on the outputs in terms of performance and schedule has not been undertaken. We feel this is not a true efficiency, but a movement of cost form one project to another. the wiring of only two of the four tracks west of Newport is an opportunity to reduce the output and costs accordingly, but needs to be properly assessed and instructed by DfT as a change to outputs in the delivery plan The installation of main feeder fixed earthing devices (FEDs) has been included in this cost assessment, but the business case for intermediate FEDs did not support the additional £50m expenditure required, and so has been excluded following full consultation with our safety colleagues The funding of the bulk power supply point at Bramley (or the alternative solution at Didcot) was not included in this ECAM submission and we have not included any costs for this. However it may be required in future to achieve great western mainline performance requirements and so we expect it to be part of a separate Page 2 of 17 10791241 ECAM submission in due course, noting that there are already risks that it may not be delivered on time. This ECAM determination is based around the Fundamental Outputs statement for the project, issued by you on 24th July 2014, and attached to this letter to provide clarity on the outputs funded at a more detailed level than the Delivery Plan As you know, we have not yet agreed the size of any portfolio adjustment to take account of the benefits of aggregating project risks into a portfolio. We used a figure of -3.05% in the PR13 Final Determinations, but need to have further meetings with you on this issue. In reaching our conclusions we have looked for evidence that the estimated costs represent efficient expenditure, and have also used our broader criteria that we set out in paragraph 9.66 in the Final Determination. We have summarised our findings in the following pages to this letter, and have also included your draft Delivery Plan entry and your Fundamental Outputs statement to be clear on the scope and outputs that we have assessed this submission against. Yours sincerely Alan Price Director, Railway Planning and Performance Page 3 of 17 10791241 Cost Adjustment Summary (all costs in 4Q12) £m, 12/13 prices SBP Final Dets ECAM (Coversheet v11) ORR adjusted CP4 * 15/16 16/17 17/18 CP5 * * CP6 AFC 305.00 236.21 939.80 342.14 305.39 207.63 826.08 300.75 10.49 9.23 nil nil 1528.64 1343.69 nil nil 1833.64 1649.08 * 13/14 14/15 * * * costs for this scheme were not specified in the SBP or FDs in comparable terms of route sections to be electrified, scope or outputs Category Omissions & adjustments Reason Omitted scope post ECAM and associated ORR unit rate adjustments Correction of cost base errors in ECAM coversheet - (CP4 sunk costs and Schedule 4) Reallocation of incorrectly allocated costs Cost base Unchanged. Already in 12/13 prices. Direct costs P&D: Removal of costs for intermediate FEDs OLE: Reduced specification OLE system for lower speed routes General: Rate adjustments where high unit rates not justified, brought back to benchmarks Indirect costs Risk Efficiency Amendments to project management costs to match PR13 benchmark; removal of misallocated items Reduction in risk allowance for temporary bridges and slab track in tunnels. Increased likelihood of additional costs at Bridge Street Newport Removal of risk for items now included in scope (Shrivenham, Goring and Tilehurst). Removal/amendments to FED risks following removal of intermediate FEDS from scope Overall – adoption of NR ECAM Opportunity schedule at P20 amended as follows: Signalling - inclusion of opportunity to reduce net risks from 32% to 20% Civils - Amendments to specific civil opportunity probability and values; inclusion of an additional opportunity allowance to reflect on-going drive to reduce clearance works to the minimum necessary P&D - Removal of intermediate FED opportunities as now removed from scope (to avoid double counting) OLE – Inclusion of additional Opportunity to achieve improved production rates and reduce net risk to go to 17% Total of all changes (subject to rounding) Page 4 of 17 Change to CP5 (£m) 7.5 0.0 -76.8 -11.5 -21.5 -82.4 -184.9 10791241 Assurance record for W001a Great Western Electrification Cost (4Q12) Commentary on whether costs are fully justified and efficient We have concluded that the efficient cost for the CP5 works is £1343.7m, coupled with the sunk CP4 costs of £305.4m this gives an AFC of £ 1649.1m. This figure includes the additional Schedule 4 costs for the higher CP5 rates. Output, Scope and Milestones Outputs, scope and milestones are clearly defined in Delivery Plan and are consistent with the HLOS The project completion milestones have been added into the Delivery Plan as NR’s regulatory outputs. This has yet to go through formal change control with stakeholders and funders, but represents the outputs that have been priced in this ECAM. The requirements have been stated at a more detailed level in the attached Fundamental Outputs Statement. Business case and Value for Money If costs significantly higher than assumed in the Final Determination do government still support the project? DfT have been working closely with NR in reviewing the higher emerging costs for this project since April 2014. The original business case (held by DfT) is being updated. Any changes to outputs following this ECAM determination will be dealt with under the existing regulatory change control process. Operator buy‐in Evidence of operator buy‐in to the selected option Regular meetings are held with TOCs who are involved in the programme governance arrangements. Additional fGW staff are directly employed in the project assisting with Entry into Service activities and future operations planning. Authorisations Defined strategy on compliance with Interoperability TSI’s and other relevant statutory provisions Interoperability compliance strategy has been submitted. The project has declared it will comply with Energy TSI and PRM TSI Page 5 of 17 10791241 Network Rail 7 Great Western Electrification Maidenhead to: Oxford, Newbury, Bristol and Cardiff Fundamental Outputs This document addresses the specific ORR question re outputs delivered by GWEp and should be read in conjunction with the requirements Document Hierarchy diagram and GWRM Requirements Structure. See Appendices A and B Summary of fundamental outputs that are being delivered by GWEp The fundamental outputs being delivered support, and are compliant with, the final draft DfT Outcomes Requirements 12/06/2014 and its approved appendix D – Infrastructure Output Specification 07/05/2014. This document is approved for reference in this GWEp submission in correspondence from Stuart Baker 15 July 2014. In that final draft, the date of electrifying the Dr Day’s to Filton Abbey Wood section is however incorrectly stated as being by May 2017. This will be commented back to the DfT but for clarity here - this section will be electrified for service by December 2017 following completion of the four-tracking works in August 2017. This will be in time for the electric-only Class 801 Hitachi SET cascade in 2018. Lines to be electrified Line to be wired diagram is as per the Client remit: WN-Elect-100.5, 21 April 2010 An additional output is to electrify all four tracks of Dr Days to Filton Abbey Wood Capacity Improvements (W007) (otherwise excluded from the ECAM settlement for W007) as agreed with DfT in 2009 see DfT outcomes’ Requirements 12/06/2014 [section 2.1.h] Line speeds achieved System line speed diagram – Sponsor instruction update, agreed at RSPG, shared with DfT. Version 2.4i, 22 July 2014. Appendix C Electrical and Structural Clearances achieved Where interventions are undertaken “normal” clearances are achieved; as listed in the PRS. Clearances are defined in GE/RT8025 The project has followed the NR internal process (TIF33) to determine clearances at structures, with the aim of significantly improving the frequency of flashover outages. Peer-reviewed exceptions have been agreed where reduced clearances are better WLC. GWEp provides electrical clearances only, it does not provide for the IEP train clearances. Network Rail Trains types/ modelling input assumptions The electrification is being designed for the SET types 800 and 801 (5/9/10-car 2-pan operation) and the cascaded EMU stock (up to 12-car {3x4-car} and 3-pan operation). DfT outcome requirements letter July 2014: 2.2. Network Rail is funded in CP5 to deliver performance at a level of 92.5% PPM by the end of CP5 2.3. From December 2017 onwards a key requirement of the Department is for the route to be capable of achieving the following journey times, based on IEP trains: Route Paddington – Bristol Temple Meads Calling Via and calling at Bristol Parkway only Time (min) 82 Paddington – Bristol Temple Meads Reading, Didcot, Swindon, Chippenham, Bath Spa 93 Paddington - Swansea Reading, Newport, Cardiff (104 min), Bridgend, Port Talbot, Neath Reading, Oxford (49 min) and six more stations Reading, Didcot, Swindon, Kemble, Stroud, Stonehouse 158 Paddington – Worcester Shrub Hill Paddington - Gloucester 126 100 Delivery Plan statement on outputs: The electrification of the GWML facilitates the introduction of electric train operation delivering significant journey time improvements on key intercity routes and high seating capacity trains on suburban services contributing to the delivery of the HLOS capacity metric for London Paddington by 2019. 2tph to Bristol sees DMU replaced by EMU. 4tph IEP replaces HST into Bristol. 9tph IEP replaces HST into Paddington. Line speed diagram (3pan-2pan divide) Appx C Client remit – train service specification issues DfT Oct 2009 Line capacity (traction capacity) No infrastructure alterations are being undertaken by the project to enhance network capacity. The capacity of the traction supply has been designed to accommodate all realistic anticipated growth. The Traction Power Supply Strategy has used the following service pattern to model the power requirements and to help create the Major Feeder Diagram. The Traction Power Supply Strategy has informed the Major Feeder Diagram, which has sufficient capacity to feed all reasonably anticipated growth scenarios. Network Rail Power Supply Outage Scenario – timetable achieved The Traction Power Supply Strategy is designed on the principle of single outage redundancy i.e. if any one bulk supply point is totally lost, the remaining system will be able to continue to function without any loss of train service. Each bulk supply is dual redundant and therefore any single equipment failure results in no loss of service. Note that the Bulk Supply Point and associated feeder will not be available until 2018 and this arrangement is somewhat compromised until that date. The AT feeder system has the inherent advantage of being non-directional and the MFD has been designed so that so far as is practicable dewirement on any 2-track section will not isolate any area of railway. Independent feeds are taken to Reading Depot from the Reading SATS. There is no contingent service TT for total loss of power, as no EMU service would run. Some (dual-mode) Class 800 SET could run on diesel power to complete their journey. Reliance on other projects (delivery dependence) Crossrail – deliver Slough and Langley loops Reading (RSAR) – Reading Area - delivery of OLE (foundations/main steel) and Reading depot - all Oxford corridor – revised siding layout for stabling EMUs, revised layout generally Western Mainline Signalling Renewals (WMSR) programme Immunisation of the signalling and telecoms systems (accelerated renewal, signalling equipment changes, electrical clearance on signalling structures and signal sighting issues) Delivery of the SCADA Fibre and RSC cables Delivery of defined parts of the earthing and bonding of equipment Bristol Area Signalling Renewals and Enhancements – Stoke Gifford depot connections Stoke Gifford depot (Agility Trains) – transition into the depot, power calcs Dr Days to Filton Abbey Wood capacity Enhancement (Filton Bank 4-tracking) – delivery of foundations, main steel, route clearance Severn Tunnel junction AfA – provision of compliant footbridge at Severn Tunnel junction (subject to change control approval) National Grid – provide bulk supply points National Utilities – move their services (not part of the ECAM financial scope but required to deliver the Regulated Output dates) Network Rail National SCADA renewals project – Provision of the SCADA control system and equipment to monitor and control the electrified railway. Integration Protection and Control utilises the dedicated fibre optic cable with full diversity between distribution sites, connected to Fixed Telecoms Network (FTN) nodes for communication with the Electrical Operations Control Centre (EOCC) Reliance on other projects (Interfaces) Crossrail – transition at Maidenhead Hinksey flood mitigation – track raising Oxford corridor – Provision of revised layout to be wired TSI compliance The PRS mandates the TSI compliance required see section 2.4 “The route between London and Cardiff is classified as TENS, High Speed and is further classified as: Category II – specifically upgraded high-speed lines equipped for speeds of the order of 200 km/h. Category III – specifically upgraded high-speed lines or lines specially built for high speed, which have special features as a result of topographical or environmental, relief or town planning constraints, on which speed must be adapted individually. “Power supply and OLE shall be compliant with the High Speed Energy TSI (or equivalent Energy TSI as may be officially published within the lifecycle of the project) taking into account the particular features of the British network as permitted by Specific Case; clause 7.4.6. of the HS ENE TSI. 118049 PRS – 1009 The project has published its Authorisation Plan for Interoperability and has appointed NoBo and DeBo as required by the Interoperability regulations. The costs of TSI compliance form part of this ECAM submission. National Rules compliance The PRS mandates the company standards and national rules that apply vis: The following are mandatory requirements: European and National Legislation (e.g. Electricity at Work Regulations 1989) Railway Group Standards Network Rail company standards Network Rail asset and environmental policies The requirements of the Project Requirements Specification The requirements of applicable temporary non compliances pending standard change for Group and Company Standards BS EN 50126:1999, Railway Applications. The specification and demonstration of reliability, availability, maintainability and safety (RAMS), covering validation and verification. British and European standards where referenced within Technical Specifications for Interoperability or in Railway Group Standards. 118049 PRS - 2649 Active Provisions for future growth Active provision is being made in the Power and Distribution system to accommodate the anticipated power requirements of the following scope: Welsh Valley Lines (bulk supply at St. Brides) Cardiff to Swansea electrification Electric Spine (AT transformer at Oxford and AT to Oxford from Didcot) Provision of “space and base” for AT supply Basingstoke to Newbury for electrification beyond Newbury Sponsor Instruction – Issue 1.8 GRIP4-8 12th July 2012 sections 9.1.4 and 9.1.5 Network Rail 9.1.4 One of the clear objectives of the establishment of the Network Electrification Programme was to make the case for, and begin the implementation of, a rolling programme of electrification. Consequently, all actions of the project must be consistent with a[national] programme of electrification, including future schemes. This would include all works for both physical clearance and electrical immunisation. In addition, it is proposed that, as part of electrification reconstruction works on routes proposed for gauge clearance in the Freight RUS and the Strategic Freight Network, opportunities should be taken from more efficient delivery through the integration of relevant works. 9.1.5 In addition to GWML electrification, there are also a number of other electrification projects underway across the network. The programme team is to liaise with the other electrification programme teams to develop nationally-required products (e.g. plant strategy) and for the sharing of best practice and application of new technology / engineering initiatives. DfT Outcome requirements section 3.4c i.e. Bristol-Birmingham (i.e. design of connections at Westerleigh). Oxford – Coventry (AT transformer at Oxford) Oxford - Bedford (AT transformer at Oxford) Immunisation of additional interlockings where the residual interlocking would otherwise not be a viable project as per John Larkinson 28/09/2011 in the accelerated renewals agreement. “ Passive provisions for future growth Passive provision is being made in the Power and Distribution system for the following: Conversion to AT Operation for Reading to Newbury Independent supply for Thingley to Bathampton Additional distribution site for Westerleigh to Birmingham Additional distribution site for Swindon to Kemble line Additional distribution site for Berks and Hants line beyond Newbury Maintenance Provision –Initial/Strategic Spares Provision Training Provision A training establishment will be built at Cocklebury to train the additional 113 staff required for maintain the OLE. OLE maintenance facilities The project will construct maintenance facilities at London, Reading, Didcot, Bristol, Wales Operational Control Controlled from Western ROC Didcot as per NR central strategy but can be controlled from any ECO in the country should the technical need arise. Other significant issues:PRM provision The equal opportunities legislation [Equality Act 2010] appears to place a requirement on NR to provide access so far as is reasonable at rural foot bridges (i.e. lifts and/or ramps). In a response to the Equality and Human Rights Commission July 2014 we will Network Rail state that “NR … is committed as an organisation to improving our facilities for disabled people and will make adjustments provided there is a reasonable case for doing so”. EU Legislative requirement at stations is covered by PRM TSI 200 Network Rail Appendix A Great West Western Ele Elecctrifica trificattion – Do Document Hier Hierarchy Rou Route Se Sect ctions ions 1 – 9 ECAM ECAM HLOS DfT Outcome DfT Outcome Requirements DfT Business Case DfT Business Case Infrastructure Output Specification Infrastructure Output Specification (Appendix D (Appendix D ‐‐ 07/05/2014) Department for Transport Network Rail CP5 Delivery Plan CP5 Delivery Plan W001a Great Western Great Western RUS Stakeholder Stakeholder’s ’s Consultation Change Control Change Control Western Route Output Spec. Western Route Output Spec. NR Client Remit NR Client Remit Electrification RUS (06/03/2014) Lines to be Wired Diagram Lines to be Wired Diagram (Appendix) Great Western Route Modernisation Great Western Route Modernisation Programme Requirements Programme Requirements NR Sponsor Instruction NR Sponsor Instruction Traction Power Power Traction Supply Strategy Strategy Supply PRS System Linespeeds System Linespeeds Major Feeding Major Feeding Diagram Route Schematics Route Schematics Route Route Clearance Clearance In Inclu clud des es:: •Trrack Lo •T Low wer •Civ ivils ils •Can •C anop opiies •Veeg, Sc •V Scrrap & RRAPs Network Rail Overhead Line Overhead Line Equipment Incl In clud udes es:: •HOPSS •HOP •Co •C onvent ntiional •Maaterials Dis •M Disttrib ribu utio tion n •Cockle ockleb bury Sidings Signalling & Signalling & Telecoms Includes Includ es:: •Sign •Sig nallllin ingg Im Immun muniisation •Telleco •Te ecom ms Im Immu munis nisaation •SCA •SC ADA Power & Power & Distribution In Incl clud udes es:: •Poweer & Di •Pow Distribu stributio tion n •Nattional •Na nal Gr Grid id PMO PMO & & Others Others Inccludes In udes:: •PMO •PM •Deesign Fee •D Feess •RU •RUS Develop Developm ment •NO •NOB BO/DEBO •Posse ssessi ssio ons •Scchedul •S ulee 4 •Cons •C onseent ntss & En Envvironment Appendix B GWRM Requirements Structure Network Rail Network Rail 16 Network Rail