071-16 Addendum 5

advertisement
Procurement Department Bid Office
Customer Center 1st Floor, Room 002
21 W. Church Street
Jacksonville, Florida 32202
June 23, 2016
ADDENDUM NUMBER: Five (5)
TITLE: Construction Services for 2304 McMillan Wastewater Class III/IV Pumping Station Rehabilitation
JEA IFB NUMBER: 071-16
BID DUE DATE: July 7, 2016
TIME OF RECEIPT: 12:00 PM
TIME OF OPENING: 2:00 PM
THIS ADDENDUM IS FOR THE PURPOSE OF MAKING THE FOLLOWING CHANGES OR
CLARIFICATIONS:
1.
CHANGE: Appendix B Bid Workbook has been modified. The attached Appendix B Bid Workbook shall replace the
current one.
2.
SPECIFICATION CHANGES:
Section 01370: Schedule of Values & Schedule of Assets
1. Paragraph 1.03, add items H and I as follows:
“H. Any items on the bid form denoted as allowances shall be accompanied with actual receipts showing the actual
costs. The OWNER will only reimburse the CONTRACTOR for actual cost incurred and shall not include any
additional markups. All remaining unsued allowance amounts will be returned to the OWNER at the end of
construction.
I. Any items on the bid form denoted as unit price items shall be field verified by the ENGINEER and/or JEA
Representative for each payment application. All remaining unsued portions of each unit price item will be
returned to the OWNER at the end of construction.”
Section 02065: Temporary Bypass Pumping System
1. Paragraph 1.03D., add item 4 as follows: “4. United Rentals”.
Section 03446: Specialty Coatings and Linings
1. Paragraph 1.01A, delete the sentence: “For the purposes of bidding, the CONTRACTOR shall anticipate the concrete
deterioration is an average of 3-inches thick and shall plan on rebuilding the surface with shotcrete as specified prior to
applying the protective specialty coating or lining.”
2. Paragraph 1.01, add item E as follows: “E. The payment for structural repair via concrete/mortar buildback and
specialty coating will be based on volumetric unit prices and actual quantities. The actual quantities for payment will
be quantified by the ENGINEER and JEA inspector during a field inspection. The cost for hydroblasting the structures
shall be included as part of the “Repair Deteriorated Concrete” line item on the bid form. Refer to the bid form for
estimated quantities.”
Section 09900: Painting
1. Paragraph 3.05 C., add item 2. b as follows: “b. All existing interior piping that remains in the pump station. ”
Section 16231: Diesel Engine Driven Generator
1. Paragraph 1.02B.1. b, delete “or Engineer approved equal” and replace with “Cummins”.
2. Paragraph 2.05A, add item 2 to read: “2. The CONTRACTOR shall notify JEA thirty days prior to the tank being
installed so it may be registered with the state. Provide five days notice so tank can be filled by JEA.”
Section 16440: Switchboards
1. Paragraph 2.01A., 3., delete “Or Engineer approved equal” and add “Siemens Industry, Inc.”.
Section 16443: Motor Control Centers
1. Paragraph 2.01A., 3., delete “Or Engineer approved equal” and add “Siemens Industry, Inc.”.
Section 16495: Variable Frequency Drives (Sewage Pumps)
1. Paragraph 2.02, add Paragraph D that states “D. In addition to the JEA approved manufacturers per JEA’s 2016 Water
and Wastewater Standards Manual, Siemens Industry, Inc. is an approved VFD manufacturer.”
3.
DRAWING CHANGES:
C-1: General Notes
1. Modify the callout for the existing bar screens that reads “REMOVE & DISPOSE OF DECOMMISSIONED
MECHANICAL BAR SCREENS; TO BE PERFORMED BY OTHERS” to read: “REMOVE & DISPOSE OF
DECOMMISSIONED MECHANICAL BAR SCREENS”.
S-1: General Notes
1. Add the following sentence to the beginning of Note E under the Concrete Restoration section as follows: “WHERE
UNSOUND CONCRETE EXTENDS BEYOND THE REINFORCING STEEL, THE CONTRACTOR SHALL
CONTINUE TO REMOVE ALL FURTHER CONCRETE WITHIN THE REPAIR AREA UNTIL SOUND
MATERIAL IS ENCOUNTERED. ALL EXISTING REINFORCING STEEL SHALL BE CLEANED BACK TO
NEAR WHITE METAL TO REMOVE ANY SCALE OR CORROSION PRIOR TO BEING ASSESSED FOR
DETERIORATION. REINFORCEMENT STEEL SHALL BE REPLACED IN ACCORDANCE WITH THE
CONTRACT DRAWINGS.”
2. Add the following sentence to the end of Note E under the Concrete Restoration section as follows: “THE ENGINEER
SHALL DETERMINE OR VERIFY AT THIS INSPECTION THE AMOUNT OF REBAR REQUIRED TO BE
REPLACED AS WELL AS THE MORTAR REQUIRED FOR BUILDBACK.”
3. Delete the following sentence from Note F under the Concrete Restoration section as follows: “FOR THE PURPOSES
OF BIDDING, THE CONTRACTOR SHALL USE AN AVERAGE DEPTH OF REPAIR REBUILD OF 3 INCHES
IN ALL AREAS.”
4. Add Note 2 under the Concrete Restoration section as follows: “2. THE PAYMENT FOR STRUCTURAL REPAIR
VIA CONCRETE/MORTAR BUILDBACK AND SPECIALTY COATING WILL BE BASED ON VOLUMETRIC
UNIT PRICES AND ACTUAL QUANTITIES. THE QUANTITIES FOR PAYMENT WILL BE QUANTIFIED BY
THE ENGINEER AND JEA INSPECTOR DURING A FIELD INSPECTION. THE COST FOR
HYDROBLASTING THE STRUCTURES SHALL BE INCLUDED AS PART OF THE “REPAIR
DETERIORATED CONCRETE” LINE ITEM ON THE BID FORM. REFER TO THE BID FORM FOR
ESTIMATED QUANTITIES.”
S-4: Foundation Plan
1. Delete the sentence “THE FLOOR OF THE WET WELL AT ELEVATION -11.70’ SHALL NOT BE INCLUDED.”
from Note 2.
2. Add the following to the end of Note 3: “ALL INTERIOR SURFACES OF THE GATE WELL SHALL BE COATED
WITH THE PROTECTIVE LINER MATERIAL.”
S-7: Sections
1. Modify the cross hatching on Section 1 to include the top of the influent gate well and the bottom of the wet well.
D-4: Lower Level Plan - Demolition
1. Modify the callout on pump no. 1 that reads “REMOVE ALL VALVES AND PUMPS FROM THE SUCTION GATE
VALVE TO THE DISCHARGE GATE VALVE; REFER TO MECHANICAL DRAWINGS FOR THE PROPOSED
PIPING, VALVES AND EQUIPMENT” to read “REMOVE ALL VALVES AND PUMPS FROM THE SUCTION
GATE VALVE INCLUDING THE SPOOL PIECE AFTER THE BASE BEND; REFER TO MECHANICAL
DRAWINGS FOR THE PROPOSED PIPING, VALVES, AND EQUIPMENT.”
2. Add a callout pointing to Pump No. 2 that reads: “REMOVE ALL VALVES AND PUMPS FROM THE SUCTION
GATE VALVE INCLUDING THE SPOOL PIECE AFTER THE BASE BEND; REFER TO MECHANICAL
DRAWINGS FOR THE PROPOSED PIPING, VALVES, AND EQUIPMENT.”
3. Add a callout pointing to Pump No. 3 that reads: “REMOVE ALL VALVES AND PUMPS FROM THE SUCTION
GATE VALVE INCLUDING THE SPOOL PIECE AFTER THE BASE BEND (THE EXISTING 30” x 24”
REDUCING BASE BEND MAY BE REUSED); REFER TO MECHANICAL DRAWINGS FOR THE PROPOSED
PIPING, VALVES, AND EQUIPMENT.”
4. Add a callout pointing to Pump No. 4 that reads: “REMOVE ALL VALVES AND PUMPS FROM THE SUCTION
GATE VALVE INCLUDING THE SPOOL PIECE AFTER THE BASE BEND (THE EXISTING 30” x 24”
REDUCING BASE BEND MAY BE REUSED); REFER TO MECHANICAL DRAWINGS FOR THE PROPOSED
PIPING, VALVES, AND EQUIPMENT.”
M-1: Dry Well Upper Level Plan El. 25.6’
1. Add Note 2 as follows: “ALL EXISTING FLOOR DRAIN OPENINGS IN THE SCREENING ROOM SHALL
EITHER BE PATCHED AND GROUT FILLED (IF NOT NEEDED AFTER REHABILITATION OF THE ROOM)
OR NEW CAST IRON GRATE COVERS INSTALLED. THE FLOOR DRAIN REPAIR METHOD WILL BE
EVALUATED AND REVIEWED BY JEA IN THE FIELD DURING CONSTRUCTION.”
M-3: Dry Well Lower Level Plan El. -11.6’
1. See “clouded” drawing changes in the reissued sheet M-3 (attached to this Addendum No. 5)
M-5: Dry Well Section Views
1. See “clouded” drawing changes in the reissued sheet M-5 (attached to this Addendum No. 5).
X-1: Miscellaneous Mechanical Details
1. Detail A: Modify callout for hose rqack to read “HOSE RACK ALL 316 STAINLESS STEEL”.
2. Detail A: copy notes 1-3 from Detail I to Detail A to read:
“1. ALL ANCHORS SHALL BE 316 SST.
2. 1.5” 316 STAINLESS STEEL BALL VALVE HOSE BIBB W/ LEVER HANDLE PER
SPECIFICATIONS.
3.
4.
5.
6.
7.
8.
3. ANTI-SIPHON VACUUM BREAKER WATTS 88 OR ENGINEER APPROVED EQUAL.”
Detail C: Replace “TRANSDUCER” with “TRANSMITTER” in the title of the detail.
Detail C: Modify callout that reads “JEA STANDARD FORCE MAIN PRESSURE TRANSDUCER” to read “JEA
STANDARD FORCE MAIN PRESSURE TRANSDUCER”
Detail C: Add a Note to read “NOTE: ALL PIPING CONNECTING VALVES AND FITTINGS SHALL BE TYPE
316SS SCH 40”
Detail I: Modify callout to the stainless steel piping insulation that reads “INSULATE PIPING WHEN USED
OUTSIDE, SEE SHEET G3.0 FOR INSULATION REQUIREMENTS” to read: “INSULATE PIPING WHEN USED
OUTSIDE, SEE SPECIFICATIONS FOR INSULATION REQUIREMENTS”.
Detail I: modify callout to the stainless steel piping that reads “¾” SCH 40 304 SST RISER FROM SUPPLY
FITTING” to read: “¾” SCH 40 316 SST RISER FROM SUPPLY FITTING”.
Detail I: Add callout to the bottom of the stainless steel piping that reads “PROVIDE TRANSITION AND REDUCER
TO CONNECT ¾” 316 SST TO 2” PVC BELOW GRADE”.
4.
INQUIRY: Sludge removal out of wet well.
 RESPONSE: JEA will pump down the wet well as far as possible, possibly to the top of the pump suction bells
(approximately 4’-4”), before shut down for rehabilitation of the interior of the wet well. The check valves then
shall be opened to allow all wastewater within the piping network to drain back into the wet well. This volume
must then be completely removed from the wet well and disposed of at an approved facility. The contents shall be
removed and disposed by Contractor’s selected means and methods. Removal and disposal of material from this
point is the responsibility of the contractor. Contractors that have done this work previously at JEA sites are listed
(suggested names not a requirement): USI environmental Dave Patchell (904) 874 - 5520 or MER (Morgan
Environmental) David Billingley (904) 509-3213 cell or 800-359-3740 office. Contractor is responsible for
removing the sludge and taking it to a landfill regulated for this type of material. Payment for content removal will
be made on a unit volume basis. Refer to bid form for estimated volume of contents to be removed. Note: JEA
will need one day notice for this work to take place.
5.
INQUIRY: Section 16231
1.02 B.1 – Subject to compliance requirements, provide a generator by one of the following manufacturers:
a. Caterpillar
b. or Engineer Approved equal
We would request Cummins be approved to bid on this project. We have reviewed the specifications and can meet the
requirements. Cummins has also been an approved bidder on other JEA projects.
 RESPONSE: Cummins is an approved manufacturer and shall meet ALL requirements of Section 16231 as
specified.
2.02 C - Does this project require the listed Siemens components listed in this section?
 RESPONSE: The components listed are required to meet JEA Standard installation.
2.04 B – Does this project required the Current Transformers and Voltage Transformers indicated? These are typically
only used on projects with switchgear? If needed? Where should they be located in the package?
 RESPONSE: The generator supplier shall provide only the current transformers and voltage transformers that
may be required for the internal controller monitoring of the engine generator set. Any additional current
transformers and voltage transformers are in the scope of supply for the MCC.
2.05 – The drawings show a stand- alone fuel tank. Should this be provided by the generator supplier and comply with the
requirements in this section?
 RESPONSE: It’s the Contractor’s responsibility to provide a complete package including generator and fuel
storage tank. The tank shall meet the requirements of the specification.
6.
INQUIRY: What is the engineer’s budget for this project?
 RESPONSE: See Addendum No. 1 and the bid solicitation.
7.
INQUIRY: Which roofing contractor did the existing roofing on this building?
 RESPONSE: Barber & Associates installed this roof approximately six (6) years ago. Either Barber & Associates
or J Register Co. may provide any roofing repair necessary so long as the existing warranty remains intact as
described in Addendum No. 3. The roof is 6 years old on its 20 year NDL warranty.
8.
INQUIRY: It appears all of the existing walls, floors, ceilings, pipe and equipment are peeling the paint. Can you give us a
detailed scope for the painting requirements? What parts of the existing structure, piping, etc. will be re-painted?
 RESPONSE: See Addendum No. 3 and additional clarification of existing piping as part of Addenum No. 5.
9.
INQUIRY: Who will pay for the lead and asbestos removal?
 RESPONSE: The lead paint and asbestos removal will be performed by JEA under a separate contract. This
work shall be removed from this contract.
10. INQUIRY: Will the owner pay for the cost of the right of way permit? If not, we need to know what that cost is.
 RESPONSE: JEA will pay the Right of Way permitting fee directly to COJ.
11. INQUIRY: During the pre-bid meeting it was discussed that JEA will pay for the by-pass pump fuel. Will they also pay
for the dewatering pump fuel?

RESPONSE: JEA will supply fuel for the temporary fuel tanks supplying the bypass pumping system (Phases I
and II only). The temporary fuel tanks shall be supplied by the bypass pumping contractor or general contractor.
Fuel for the dewatering pumps shall be the responsibility of the Contractor.
12. INQUIRY: Who is responsible for filling the new [permanent] diesel fuel tank?
 RESPONSE: JEA will fill the tank. It is the contractors responsibility to notify JEA thirty days prior to the tank
being installed so it may be registered with the state. Contractor to provide five days notice for tank to be filled.
13. INQUIRY: Page 115 shows the water pipe as schedule 40 304ss, page 115 shows water pipe as schedule 10. Are only the
risers to the hose valves schedule 40?
 RESPONSE: The stainless steel piping for the seal water and wash down systems shall be 316 Schedule 10. The
stainless steel piping exterior to the building (for the yard hose bibbs) and all piping for potable water shall be 316
Schedule 40. Refer to Specifcation Section 15140, Paragraph 2.01B.
14. INQUIRY: Will JEA pump down the wet well as far as possible, possibly to the invert of the suction bells, before shut
down for rehabilitation of the interior of the wet well?
 RESPONSE: JEA will pump down the wet well as written in the above inquiry. Refer to Inquiry Note. 4. JEA
requires one day notice to pump down the well as stated in inquiry 4.
15. INQUIRY: Can JEA establish a bid quantity and a unit price on the bid form for removal of the residuals in the wet well?
This way all bidding contractors will be bidding on the same amount of material since it is not possible to quantify at this
time.
 RESPONSE: The material in the wet well depends on the level to which the existing pumps can pump down the
wet well. Assuming the pumps can pump down to a level of approximately 7.5’ from the bottom of the well (the
current operational LWL), the remaining volume to be disposed of is estimated to be approximately 150 cubic
yards. At a level of 5’ depth, the estimated volume is 70 cubic yards.
16. INQUIRY: Can JEA add a unit price on the bid form for deteriorated rebar repair?
 RESPONSE: JEA has added an allowance to the bid form to pay for up to $10,000 in costs for rebar replacement.
The quantities of rebar and associated costs for such rebar replacement will be evaluated by the ENGINEER and
JEA inspector. Refer to this Addendum for further instruction on rebar repair.
17. INQUIRY: Will this project require a security guard 24/7?
 RESPONSE: See solicitation item 2.13.8 (page 57 of 87) and Addendum No. 3 concerning JEA security when
the fence surrounding the JEA facility is temporarily removed during the doghouse work. Contractor is
responsible for protection of JEA surplus material as written in solicitation section 2.13.27(page 64 of 87) and
storage of equipment solicitation section 2.13.30 (page 64 of 87).
18. INQUIRY: Will the existing bar screen that are lying in the parking lot be removed by JEA prior to the job starting?
 RESPONSE: See Addendum No. 3. This is for contractor to remove for surplus and shown on Appendix D.
19. INQUIRY: Confirm that the 8” and 6” valves in the gate well are working correctly.
 RESPONSE: The 8” and 6” valves in the gate well are not functioning properly. These valves will be removed by
the Contractor as part of the project per the drawings.
20. INQUIRY: Is an extension an option on the subject project? Please advise.
 RESPONSE: See Addendum No. 4.
21. INQUIRY: Siemens would like to be added as an approved for supplier for the following sections so we may provide a
complete electrical package. We have recently been approved for Blacksford and NW Regional WTP projects for similar
equipment following JEA approval.
Switchboard spec section 16440 2.01A
Motor Control Center spec section 16443 2.01A
Variable Frequency Drives 16495 2.01A

RESPONSE: Siemens has been added as an approved supplier for the above referenced sections.
22. INQUIRY: Per section 11500, submersible mixers. Will the 2 submersible mixers run continuously 24-7 or are they on
timers to run sometimes, if so do you know how long they will run in a 24 hr period?
 RESPONSE: The mixers are expected to run continuously, 24/7.
23. INQUIRY: In reviewing the specification for the odor control equipment (Section 11700) we noticed the following –
2.07 DUCTWORK
A. All air ducting from the blower inlet to odor control vessel exhaust and to the carbon polishing unit shall be
supplied by the odor control system manufacturer. Materials of contruction shall be FRP and rated for 150 psig
pressure
However, Specification Section 15892- FRP Ductwork and Accessories, states the followingB. Construction
1. All FRP ductwork shall be of filament wound or hand lay-up construction.
2. Maximum allowable deflection for any size ductwork shall be ½ inch between supports for any size of duct
under worst case operating conditions.
3. FRP ductwork shall be designed using a safety factor of 10 for pressure and 5 for vacuum. FRP ductwork shall
be designed for a maximum vacuum pressure of 20” w.c. and a maximum positive pressure of 10” w.c.

RESPONSE: The two specifications shall be applied to their respective systems. All duct installed within the
building shall meet the requirements of Section 15892. After the stainless steel penetration through the exterior
wall (shown on Detail H, Sheet H-7), all duct shall meet the requirements of Section 11700.
24. INQUIRY: Does the top of the stop logs stacked should be just above the HHWL (+3.30) or as high as the channel (+7.28)
 RESPONSE: The stop logs and frames shall extend the entire height of the channel as shown on M-4.
25. INQUIRY: What's the max. height allowed for each log?
 RESPONSE: The height for each log shall be no greater than 1’-6”.
26. INQUIRY: What's the max. water level on front and back of the sluice gates?
 RESPONSE: Assume the max differential water level for the sluice gates is 18’-0”. See specifcation Section
11300 Paragraph 2.01A.
Acknowledge receipt of this addendum on the Bid Form
Download