FY2017 Construction Capital Improvement and Replacement Program Presentation – April 18, 2016 Sponsored By: Metropolitan St. Louis Sewer District AGC-Missouri SITE Improvement Association St. Louis Minority Business Council Agenda MSD Staff Introduction FY2017 Capital Construction Program MSD Budget and Board Introduction Schedule Diversity Manager’s Update Executive Director’s Update Networking Event 2 MSD Staff Introduction Purchasing Betsy Schubert – Manager Amanda Cooper – Specifications Associate Lisa Treat – Specifications Associate Engineering Marie Collins – CM Assistant Director Matt Bacon – Program Manager (Collection System) Allen Muehlher – Program Manager (CIPP, Facilities, Tunnels) Mike Buechter – Program Manager (Small Contractor Program) Angela Noble – Construction Administrative Supervisor 3 MSD Staff Introduction Human Resources - Diversity Vicki Edwards – Director Shonnah Paredes – Diversity Manager Marnita Spight – MWBE Compliance Specialist Katlynn Woodruff – Diversity Administrative Support 4 Agenda MSD Staff Introduction FY2017 Capital Construction Program MSD Budget and Board Introduction Schedule Diversity Manager’s Update Executive Director’s Update Networking Event 5 MSD Website – Today’s Presentation 6 FY2017 Work Type Overview Work Type No of Total Value of Projects Work Scope TOTAL 89 $509,060,000 Private Inflow Removal (PIR) 7 $2,585,000 Disconnect downspouts, yard drains, etc., on 482 properties Sewer Construction (w/o PIR)* 29 $31,033,000 Construct 37,800 feet of 8-inch to 108-inch pipe Sewer Construction (with PIR)* 18 $50,212,000 Construct 50,000 feet of 8-inch to 36-inch pipe and disconnect private inflow on 2,134 properties Force Mains* 3 $19,650,000 Construct 17,000 of 30-inch to 356-inch force main and 1,700 feet of 2-inch to 8-inch pipe. Small Pump Station 4 $3,465,000 Replace 5 small pump stations 7 * Select projects will be funded over two fiscal years FY2017 Work Type Overview Work Type No of Total Value of Projects Work Scope Natural Channel – Restoration 4 $2,190,000 Bank stabilization of about 2,725 feet of channel using various natural channel restoration methods CIPP 17 $75,825,000 Rehabilitation about 790,000 feet (150 miles) of pipe Facility 3 $6,950,000 Work primarily consists of mechanical and/or electrical improvements at existing facilities Tunnel* 2 $314,900,000 20,000 feet of 19-foot tunnel and 17,000 feet of 7-foot tunnel Miscellaneous 2 $2,250,000 Earth berm and water feed installation at Missouri River WWTP and concrete repair at Lemay WWTP * Projects will be funded over multiple years. 8 Cost Distribution by Work Type Value of Work Number of Projects PIR Sewers Sewers w/o With PIR PIR Force Main Small Pump Station Total < $150,000 3 7 1 - - 11 $150,000 < $500,000 2 12 1 - 1 16 $500,000 < $1,000,000 2 4 3 1 2 12 $1 M < $5 M - 4 9 1 1 15 $5 M < $10 M - 2 4 - - 6 => $10 M - - - 1 - 1 TOTAL 7 29 18 3 4 61 9 Cost Distribution By Work Type Value of Work No. of Projects Natural Channel CIPP Facility Tunnel Misc. Total < $150,000 - - - - - - $150,000 < $500,000 3 - - - - 3 $500,000 < $1,000,000 - - 2 - - 2 $1 M < $5 M 1 13 - - 2 16 $5 M < $10 M - 3 1 - - 4 => $10 M - 1 - 2 - 3 TOTAL 4 17 3 2 2 28 10 Other Capital Construction Dollars $7,000,000 for Sanitary/Combined Sewer Infrastructure Repairs in addition to the current balance of about $3.3 Million $5,440,000 for Storm Sewer Infrastructure Repair in addition to the current balance of $ 1.7 Million $5,000,000 for Green Infrastructure BMP’s in the Combined Sewer Area 11 Major Facility Projects FISCAL YEAR PROJECT NAME CONSTRUCTIO N COST $40,000,000 FY2019 University City Sanitary Storage Facility (Hafner Ct.) FY2019 FY2021 Gravois Trunk Sanitary Storage Facility (Pardee Ln and Pardee Rd) Lemay Pump Station No. 3 FY2021 Lower Meramec Expansion FY2021 Caulks Creek "A" Pump Station (P-750) Replacement $11,006,000 FY2025 Lemay CSO Outfall 063 High Rate Clarification Facility $96,000,000 FY2025 LMRDP Tunnel Dewatering Pump Station FY2029 Watkins Creek Pump Station (P101) Improvements $66,781,000 FY2029 Mackenzie Creek Sanitary Storage Facility $10,753,000 FY2030 Gravois Creek Sanitary Storage Facility $40,040,000 FY2032 Coldwater Creek WWTF Storage $24,543,000 $48,000,000 $41,000,000 $114,000,000 $102,000,000 TOTAL $594,123,000 12 Major Tunnel Projects FISCAL YEAR PROJECT NAME CONSTRUCTION COST* FY2019 Ferguson Sanitary Sewer (Olive to Page) (Diamond Park) $10,000,000 FY2020 LMRDP CSO Storage Tunnel $835,000,000 FY2020 Lower Meramec River System Improvement Baumgartner to Fenton WWTF Tunnel FY2024 RDP Tributaries CSO Tunnel $202,000,000 FY2028 Upper RDP CSO Storage Tunnel $320,000,000 $464,000,000 TOTAL $1,831,000,000 * Includes the cost of near surface consolidation sewers 13 FY2018 and FY2019 Capital Construction PROJECT TYPE FY18 No. Projects FY19 Dollar Value No. Projects Dollar Value CIPP 5 $ 14,970,000 13 $ 66,581,000 FACILITY 7 $ 21,261,000 3 $ 3,685,000 INFRASTRUCTURE REPAIR Multiple $ 7,000,000 Multiple $ 9,500,000 GREEN INFRASTRUCTURE Multiple $ 5,000,000 Multiple $ 5,000,000 MISCELLANEOUS 1 $ 480,000 2 $ 18,500,000 NATURAL CHANNEL 1 $ 780,000 5 $ 1,790,000 PIR 16 $ 9,152,000 11 $ 6,497,000 SEWER 29 $ 69,700,000 44 $ 55,663,000 SMALL PUMP STATION 5 $ 3,360,000 2 $ 1,000,000 64 $131,703,000 80 $168,216,000 1 TOTAL 1 Includes sewer projects with PIR 14 FY2020 and FY2021 Capital Construction PROJECT TYPE FY20 No. Projects FY21 Dollar Value No. Projects Dollar Value CIPP 20 $ 50,474,000 7 $ 35,740,000 FACILITY 3 $ 12,400,000 2 $ 8,000,000 INFRASTRUCTURE REPAIR Multiple $ 10,000,000 Multiple $ 8,000,000 GREEN INFRASTRUCTURE Multiple $ 5,000,000 Multiple $ 5,000,000 MISCELLANEOUS 2 $ 6,200,000 3 $ 4,500,000 NATURAL CHANNEL 5 $ 995,000 5 $ 1,120,000 PIR 4 $ 1,221,000 1 $ SEWER 55 $ 43,716,000 32 $ 22,695,000 SMALL PUMP STATION 4 $ 4,602,000 93 $134,608,000 1 TOTAL 1 500,000 $ 5,500,000 51 $ 91,055,000 Includes sewer projects with PIR 15 Agenda MSD Staff Introduction FY2017 Capital Construction Program MSD Budget and Board Introduction Schedule Diversity Manager’s Update Executive Director’s Update Networking Event 16 MSD Website - CIRP BUDGET 17 MSD Website – Board Introduction Schedule 18 FY 2017 Board Introduction Schedule Overview Total Project Budget 1st Quarter* 2nd Quarter 3rd Quarter 4rd Quarter Total No. of Projects 23 24 23 19 89 Project Value $243,298,000 $151,200,000 $57,913,000 $56,649,000 $509,060,000 FY2017 Appropriation $61,298,000 $61,375,000 $48,023,000 $44,349,000 $215,145,000 *Includes 3 (three) projects with bid openings in May and Board Introduction in June 2016 19 FY2017 Board Introduction Schedule Overview Work Type PIR Sewers (w/o PIR) Sewer (with PIR) Force Mains Small Pump Station First Quarter Second Quarter Third Quarter Fourth Quarter No. Projects Value No. Projects Value No. Projects Value No. Projects Value 4* 1 2 - $1,147,000 $65,000 $1,373,000 - 7 8 6 8 $3,629,000 $5,395,000 $6,084,000 $8,135,000 5* 6 4 3 $21,140,000 $13,420,000 $8,838,000 $6,814,000 - - 1 2 - - $650,000 $19,000,000 2 - 1 1 $1,265,000 - $500,000 $1,700,000 * Includes 1 (one) project with bid opening in May and Board Introduction in June 2016 20 FY2017 Board Introduction Schedule Overview First Quarter Second Quarter Third Quarter Fourth Quarter Work Type No. Projects Value No. Projects Value No. Projects Value No. Projects Value Natural Channel – Restoration 1 1 2 - $152,000 $400,000 $16,638,000 - 3* 4 5 5 $7,965,000 $17,820,000 $29,690,000 $20,350,000 - 2 - 1 - $6,200,000 - $750,000 1 1 - - $208,000,000 $106,900,000 - - - 1 1 - - $1,000,000 $1,250,000 - CIPP Facility Tunnel Miscellaneous * Includes 1 (one) project with bid opening in May and Board Introduction in June 2016 21 Agenda MSD Staff Introduction CM Implemented Organizational Change FY2017 Construction Program MSD Budget and Board Introduction Schedule Diversity Manager’s Update Executive Director’s Update Networking Event 22 FY2017 Diversity Program Updates 60 Day Workforce Plan Templates Diversity website updates gives easier access to policy guidelines, forms and Diversity staff contact information Monthly Workforce Utilization Reporting going online (June, 2016) Conducting more contractor trainings (quarterly and via webinar) Contractors project final evaluations Annual pre-qualification evaluation process MSD will post contractor’s M/WBE Utilization and Payments online as of July 1, 2016 Contractor OJT Tunneling Training Program Opportunities 23 M/WBE Utilization & Workforce Updates Workforce Plan (Projects > $500,000) – Workforce Plan Template (Available June 1, 2016) • Trainings on use of the template and Prism will be held weekly on Tuesday’s at 2:30 p.m. throughout the month of May (Registration is required) – Plan due within 15 days of “Boots On The Ground” • Workforce Plan with a forecast of the anticipated workforce utilization for the first 60 days of the project is due to Diversity • Workforce Plan includes Prime and Subcontractors on site during first 60 days • Contractors cannot mobilize to project site without an approved Workforce Plan on file • If the contractor make changes after the initial 60 day plan is in place, the contractor must notify MSD of the change • Workforce Plan must be on file before involvement reporting is set 24 up for the project reporting MWBE Utilization & Workforce Updates Workforce Plan (Projects > $500,000) Cont. – Good Faith Effort Acceptance • Good Faith Effort is required if Contractor is not meeting goals with the workforce currently performing on the job • Contractor can submit a Project Workforce Plan which identifies when contractor plans to meet workforce participation goals by the end of the project • Failure to meet workforce goals requires contractor to provide documentation of request and responses from all 3: – Affiliate Unions – First Source Hiring - SLATE – BUD Training – SLATE 25 MWBE Utilization & Workforce Updates Website Updates Easier access to policy guidelines, forms, reports and Diversity staff contact information I want Disparity Study information I want Supplier Diversity & M/WBE Certification information I want to learn more about the Community Benefits Agreement I want Diversity Programs and Resources I want Diversity Policies and Forms I want to view Diversity Compliance Reports I want to Report my Project Vendor and Workforce Utilization I want Diversity Contact Information 26 MWBE Utilization & Workforce Updates Website Updates Dashboard data for CIRP at a glance CIRP Workforce Participation for FY2016 Q2 27% 70% Minority Woman 3% Non-Minority/Woman 27 MWBE Utilization & Workforce Updates Contractor M/WBE Utilization Reports & Contractor Payments available online July 1, 2016 – – – – Prime Contractor Payments Capital Expenditure Report Workforce Utilization Report Final Project Participation Reports (Vendor/Workforce) Contractors with workforce projects will receive notifications of where they stand at 25%, 50% and 75% of completion OJT Tunneling Training Program Opportunities Diversity Opportunity Fairs for Tunnel Projects 28 MWBE Utilization & Workforce Updates Annual and Final Project Evaluations – Reminder: Workforce goal attainment is a component of each project’s final evaluation – Reminder: Vendor utilization and workforce utilization is a component of contractor’s annual pre-qualification evaluation process 29 Agenda MSD Staff Introduction FY2017 Capital Construction Program MSD Budget and Board Introduction Schedule Diversity Manager’s Update Executive Director’s Update Networking Event 30 Executive Director’s Update Board of Trustees and Senior Staff Update Results of December Flooding on the Meramec Results of Proposition Y and S Remaining Stormwater Services 31 Agenda MSD Staff Introduction CM Implemented Organizational Change FY2017 Capital Construction Program MSD Budget and Board Introduction Schedule Diversity Manager’s Update Executive Director’s Update Networking Event 32 Follow MSD on: Twitter: @YourMSD Facebook: YourMSD 33