Constructive Notes ® April 2014 INSURANCE CONSTRUCTION & ENGINEERING RESOURCES CORPORATE COMMERCIAL PROPERTY LITIGATION & DISPUTE RESOLUTION AVIATION Liquidated Damages: A sole remedy for delay? By Patrick Mead, Partner In the first of the March 2014 editions of Constructive Notes, the writer observed that oftentimes exclusion of liability clauses and liability caps are mechanisms which operate in tandem with provisions in relation to Liquidated Damages (which are not considered to be exclusory, operating in theory for the benefit of both parties to the contract) to create a finely balanced risk regime. Services Ltd v Maschinenfabrik Ernst Hese GmbH [2008] EWHC 6 (TCC)] is relevant in this regard. This decision by the Honourable Justice Ramsey of the High Court of Justice (Queens Bench Division, Technology and Construction Court) went to the Court of Appeal, but it is only the part of the judgment dealing with vicarious liability that was reversed on appeal. It was further noted that other than in respect of a provision for Liquidated Damages (which was likely to be capped as a percentage of the Contract Sum), the contractor may insist upon a complete exclusion of damages for loss of profit, loss or use or business interruption, or alternatively seek to cap any such exposure to the limit of any applicable insurances. In this case, Biffa sought to argue that a valid and enforceable liquidated damages clause was an exclusive remedy for breach only of the obligation to complete on time. It was argued that it was not applicable to breach of other obligations, which whilst causing delay, were not obligations dealing with the need to complete on time. It was argued that such breaches allow an entitlement to unliquidated damages. A question can then arise as to whether the remedy of Liquidated Damages is the Principal’s sole remedy for delay, however caused, or whether there is scope to argue for an entitlement to further damages (leaving to one side the efficacy of the consequential loss exclusion) on the basis that defective design (where this is the responsibility of the contractor) or workmanship which caused or contributed to the delay constitute a separate and discrete breach of contract. Biffa submitted that the wording of the contract [‘…shall not relieve the Contractor from its obligation to complete the works or from any other of its obligations and liabilities under the contract and shall be without prejudice to any other right or remedy of the Employer’] opened up a claim by Biffa against WEH for damages for delay where that delay was not simply a breach which it referred to as ‘simple’ delay. The English case of Biffa Waste Services Ltd v Maschinenfabrik Ernst Hese GmbH.50 [Biffa Waste This was however rejected by the Judge who accepted the defendant’s submission that the distinction between a Constructive Notes - April 2014 © Carter Newell 2014 ‘simple delay’ and breaches of other terms of the contract leading to delay was not one which was properly made. The Judge considered that if liquidated damages were the only monies payable for failure to complete, that must exclude other remedies for payment of damages. At paragraph 114, the Judge said: ‘I do not consider that it is possible to draw a distinction between a ‘simple’ failure to complete and a failure to complete caused by breach of another obligation. If there is a failure to complete then liquidated damages are ‘the only monies’ due for such default. If there is a breach of another obligation and that breach causes a failure to complete then liquidated damages are still the only monies due for that default, that is a breach of contract causing a failure to complete on time’. And then, [at 115]: ‘Secondly, I do not accept that a liquidated damages clause which only applied to a case where there was simply a failure to complete on time without a breach of any other provision would make commercial sense. The purpose of the liquidated damages clause is, as Lord Upjohn said in the Suisse Atlantique case, for the benefit of both parties: ‘the party establishing breach by the other need prove no damage in fact; the other must pay that, no less and no more.’…. A party wishing to avoid liquidated damages and argue for no loss or a smaller sum would attempt to find some other breach of an implied or express term to hang the delay on. A party seeking to uphold the clause would be trying to disprove that another breach was the cause of the delay’. And then, [at 117]: ‘I consider that my view is consistent with the decision of His Honour Judge Gilliland QC in Piggott Foundations Ltd v. Shepherd Construction Ltd [1993] 67 BLR 48 at 68 where he held that there was a liquidated damages provision and that this provision ‘prevents the defendant from seeking to avoid the overall limitation of damages to £40,000 by claiming as a head of general damages for the breach of any other provisions or obligation under the contract such damages which have resulted from the failure of the plaintiff to complete the piling work within the period of 10 weeks.’ The same consistency is implicit in the decision of His Honour Judge Fox-Andrews QC in Surrey Health Borough Council v. Lovell Construction Ltd (1988) 42 BLR 25 where at 37 he found that the liquidated damages were an exhaustive remedy for delay where a building had been damaged by a fire’. It has been written that the ‘irresistible conclusion’ is that a valid enforceable liquidated delay damages clause presents an exclusive or exhaustive remedy for delay, regardless of what breach of what obligation has caused (partly or wholly) the delay.1 This ‘complete remedy’ analysis [so described] is summarised in Keating on Construction Contracts (8th Edition at paragraph 9-006) which was referred by The Judge [at 118]: www.carternewell.com ‘It is suggested that the solution is primarily a question of the construction of the contract in question. If, as in most (if not all) cases, the clause is clearly expressed to be or, as a matter of proper construction appears to be, a complete remedy for delayed completion then it matters not why the contractor failed to complete by the due date. . . The fact that the delay is due to a breach of contract by the contractor as opposed to merely going slow, cannot affect the nature or quality of the loss which the liquidated damages is intended to compensate. In reality, in such situations, there are two breaches: the carrying out of the defective work. . . and the failure to complete by the due date. Neither the employer nor the contractor can avoid liquidated damages by simply relying on the first breach.’2 The writer believes that this decision and these comments have to be understood in the context of an attempt to recover damages outside of the Liquidated Damages regime on the basis of a breach unrelated to time, but still referable to the period of delay. It seems clear that damages for breach of warranties or failure to achieve performance guarantees may still be otherwise recoverable, subject to whatever remedies might be specifically provided for in the Contract. Further, under a D & C Contract where co-extensive tortious duties may arise, a clear intent that Liquidated Damages are to operate as a sole remedy to the exclusion of general law damages may be necessary to confine recovery in the manner suggested in the Biffa case. It also seems unlikely in this Country that a Liquidated Damages clause of itself would be effective to limit damages in circumstances where the proscribed conduct is found to be in breach of Schedule 2 of s 18 of the Australian Corporations Act 2001 (Cth) or associated provisions of the Competition and Consumer Act 2010 (Cth). Interestingly, in the Biffa case, the Judge went on to consider whether the recovery of Liquidated Damages precluded the recovery of costs incurred in reasonable mitigation of the delay. The Judge noted [at 121] that the cost of taking reasonable mitigating steps is generally recoverable as part of the damages for the breach (citing The World Beauty [1970] 144 at 156 per Winn L J). The Judge went on to say: ‘As stated above, Liquidated Damages are an exhaustive remedy for delay. That exhaustive remedy therefore includes any damages which could be recovered damages for failure to complete.’ A further aspect – Insurance Policy Exclusions Insurance policies sometimes contain an exclusion of loss said to be referable to the imposition of Liquidated Damages. If however, the cause of the delay that gives rise to the Principal’s entitlement to levy Liquidated Damages is otherwise indemnifiable, this might be seen to operate harshly on an Insured. If in fact such a provision is penal in nature, it is likely to be struck down on the basis that it does not reflect a genuine pre-estimate of damage. If on the other hand, it is upheld and found to be enforceable as a remedy, then it arguably has the potential to operate not just for the benefit of both parties to the contract, but also for the benefit of insured and insurer, operating as a cap on recoverable loss (often as a percentage of the contract sum) and further in certain circumstances as a sole remedy in the event of delay occasioned by the insured’s breach. 1 Dr Hamish Lal in his article ‘Liquidated Damages’ (2009) 25 Const. L.J. 567 – 690 [586]. 2 Keating on Construction Contracts, 2006, [9-006]. Author Patrick Mead Partner P: 3000 8353 E: rstevens@carternewell.com Excluding consequential loss – Do you really know what you are not getting? By Mark Kenney, Special Counsel In an article in the first of the March 2014 editions of Constructive Notes, consideration was given to the operation of exclusory or limiting provisions directed to economic, indirect or consequential loss. We have all seen simple clauses in contracts to the effect of ‘neither party is liable to the other for any consequential or indirect loss’. The presumption of most is that this will exclude damages that are too distant or unknown, but what if anything, does it really exclude? As a basic premise, when one party breaches a contract, the other party is entitled to damages that flow from that breach. Over time this principle has narrowed to what is commonly referred to as the ‘two limb approach’.1 The two limbs outline what types of damages can be claimed, all others being considered too remote. The first limb is those damages that arise naturally from a breach of contract (obvious and direct). The second limb is those damages that are non-direct but that would be within the reasonable contemplation of the parties at the time of contracting. Understandably, this second limb, which is where consequential type losses would potentially sit, has been the subject of considerable dispute over the last 150 years. In Australia, the High Court decision in Darlington v Delco2 confirms that at the time of contracting, parties can include clauses excluding certain damages, however these clauses must be construed according to their natural and ordinary meaning. However it is not a simple just excluding ‘consequential loss’. Unfortunately, there is still no consensus in Australia as to what the natural meaning of consequential loss actually is. There are conflicting decisions in three jurisdictions: Victoria, South Australia and Western Australia, none of which are strictly binding on Queensland or New South Wales. In Victoria,3 the test is what an ordinary reasonable business person would consider consequential loss i.e. everything beyond the normal measure of damages such as lost profit. In South Australia,4 a very broad approach has been taken using a literal interpretation of the word ‘consequential’ so that consequential loss means any loss that was consequent or following, immediate or eventual, flowing from a breach of contract. This could exclude even direct or first limb losses. In Western Australia,5 the position is different again. Here, the Court rejected the Victorian position (beyond the normal measure) and also excluded strict reliance on the second limb test. Instead, it reinforced the original view in Darlington v Delco that consequential loss exclusion clauses should be construed on a case by case basis according to their natural and ordinary meaning as determined in the context of the relevant contract when read as a whole. In summary, there is still an obligation to give clauses their natural meaning but there is no consensus on what this meaning is for consequential loss. The solution is comparatively simple though. Whenever you want to deal with consequential losses, then define that term in the contract so that the meaning is clear. There are some simple steps to consider every time this process is undertaken. 1. Decide what specific types of indirect or consequential loss you want to exclude and then list them in the definition e.g. loss of profit, loss of future contracts, losses from business interruption, loss of business opportunity and so on. If included, then the meaning will be clear. If you do not include a specific loss then the meaning will be open to dispute later. For example simply broadly stating that ‘Consequential Loss means any and all indirect or consequential losses’ is of next to no real assistance. 2. Consider if there are any specific exclusions from the general classes of consequential loss that you list. The most common is delay liquidated damages. When liquidated damages are calculated, they will take into account a variety of factors, some of which could fall within your definition of consequential loss, such as business interruption. To avoid ambiguity, simply Constructive Notes - April 2014 © Carter Newell 2014 make it clear that the exclusion of consequential loss does not apply to liquidated damages. Liquidated damages will then be a separate head of loss that is a genuine pre-estimate of losses associated with delay that does not fall within the consequential loss exclusion. 3. Consider insurance implications. There is no sense in requiring the other party to have a policy that names you and has coverage of $20 million if you then exclude their liability for a large part of what the policy covers. Rather than having an argument with an insurer over whether it is only required to indemnify parties for their contractual liability, which excludes consequential loss, consider whether it is necessary or appropriate to carve out insurance coverage from the consequential loss exclusion. In that way the other party will reduce its direct personal liability but you will both still have the protection of the insurance policy. As most consequential loss clauses are mutual, excluding liability of both parties, you should also always check with your own insurance broker before doing so to ensure that this does not diminish coverage under your own policies. common to carve out from the consequential loss exclusion, the indemnities relating to personal injury and death, so that these remain in force, irrespective of whether elements of the indemnity would usually be considered as consequential losses. In short, think about what obligations you want to limit and what rights you want to protect and then draft a specific consequential loss definition and an exclusion clause that meets those requirements. When doing so also consider how this works in the context of the whole contract. If you do not do this, then you run the risk of dispute and then leaving it to the Court to make a decision on how the definition of consequential loss and the relevant clause is meant to be interpreted. As we can see above, there is currently no certainty as to how courts in Queensland or New South Wales will do so. Hadley v Baxendale (1854) 9 Exch 341. Darlington Futures Ltd v Delco Australia Pty Ltd (1986) 161 CLR 500. 3 Environmental Systems Pty Ltd v Peerless Holdings Pty Ltd [2008] VSCA 26. 4 Alstom Ltd v Yokogawa Australia Pty Ltd & Anor (No 7) [2012] SASC 49. 5 Regional Power v Pacific Hydro [No 2] [2013] WASC 356. 1 2 Author 4. Consider how the consequential loss exclusion impacts or interacts with other clauses of the contract, in particular indemnities or warranties. Be aware that a specific exclusion of consequential loss may reduce a more general right of indemnity or ability to enforce a warranty. For example, it is Mark Kenney Special Counsel P: 3000 8474 E: mkenney@carternewell.com STOP PRESS – the first significant changes to the Security of Payment legislation are announced today Following the extensive review of the Building and Construction Industry Payments Act (BCIPA) last year, the Queensland State government has today announced three key changes to BCIPA all effective from 1 September 2014. ▪ There will now be a single adjudication registry within the Queensland Building and Construction Commission (QBCC), who will maintain a registry of active adjudicators. This will mean the end of referring applications to individual Authorised Nominating Authorities, however the precise details of the new process are not yet available. The QBCC are also currently obtaining feedback from industry about how the skills and performance of Adjudicators can be improved and it is expected that this will flow into the process for appointment of adjudicators to be adopted by the QBCC. ▪ Timeframes under BCIPA have been amended to reflect the size and complexity of claims. There will now be longer periods to provide payment schedules and to respond to adjudication applications on claims over $750,000 or that involve latent conditions or time related costs. Further the period where time does not run under BCIPA over Christmas has been extended to reflect the longer industry shutdown periods. ▪ Adjudication responses will not be limited to the material raised in a payment schedule – an adjudication response can now include all relevant material and the claimant will be given a right of reply. How will this change things now ? Not at all, the current process will remain unchanged until 1 September 2014. Carter Newell is well resourced to handle BCIPA matters at all levels specialising in large scale and complex claims and brings particular expertise to this area with Partners, Patrick Mead and David Rodighiero and Special Counsel, John Grant and Luke Preston all Registered Adjudicators under BCIPA (QLD). Please note that Carter Newell collects, uses and discloses your personal information in accordance with the Australian Privacy Principles and in accordance with Carter Newell’s Privacy Policy, which is available at www.carternewell.com/legal/privacy-policy. To tell us what you think of this newsletter, or to have your contact details updated or removed from the mailing list, please contact the Editor at newsletters@carternewell.com. If you would like to receive newsletters electronically, please go to www.carternewell.com and enter your details in CN|Newsletter signup. The material contained in this newsletter is in the nature of general comment only, and neither purports nor is intended to be advice on any particular matter. No reader should act on the basis of any matter contained in this publication without considering, and if necessary, taking appropriate professional advice upon their own particular circumstances. © Carter Newell Lawyers 2014 Brisbane Sydney All correspondence to: Level 13, 215 Adelaide Street Level 6, 60 Pitt Street, GPO Box 2232, Brisbane QLD 4001 Brisbane QLD Australia 4000 Sydney NSW Australia 2000 www.carternewell.com Phone +61 7 3000 8300 Phone +61 2 9241 6808 ABN 70 144 715 010