Pre-Feasibility Study for Rural Electrification Program by Renewable Energy In The Mountainous Region of Northern Samar in the Philippines STUDY REPORT March 2007 Engineering and Consulting Firms Association, Japan West Japan Engineering Consultants, Inc This work was subsidized by Japan Keirin Association through its Promotion funds from From Manilla CATARMAN CATUBIG RIVER NORTHERN SAMAR SAMAR ISLAND LEYTE ISLAND Location Map Contents Executive Summary ························································································································ S-1 Chapter 1 Introduction·················································································································· 1 1.1 Background and Objectives ···························································································· 1 1.2 Scope of Works··············································································································· 2 1.3 Study Area ······················································································································ 2 1.4 Study Schedule ··············································································································· 2 1.5 Study Team Member······································································································· 3 Chapter 2 2.1 Socio-Economic Development in Communities Hosting Renewable energy ················ 4 Economic Development and Energy in the Philippines··················································· 4 2.2 Renewable Energy Development in the Philippines ························································ 5 2.3 Major Issues ··················································································································· 14 2.4 Government Policies and Programs ················································································ 14 2.5 Impact to Host Communities ·························································································· 8 Chapter 3 Rural Electrification ····································································································· 19 3.1 Current Condition of Rural Electrification ······································································ 19 3.2 Promotion Policy of Rural Electrification ······································································· 22 3.3 Issues of Rural Electrification ························································································· 23 3.4 Effects of Rural Electrification ······················································································· 25 Chapter 4 Outline of the Surveyed Area ······················································································· 29 4.1 Outline of Northern Samar Province··············································································· 29 4.2 Electrical Power Situation in Northern Samar Province ·················································· 30 Chapter 5 Pre-Feasibility Study of Rural Electrification by Renewable Energy···························· 34 5.1 Current Situation of Rural Electrification in Coverage Area ··········································· 34 5.2 Assumption of Electric Demand associated with Rural Electrification···························· 41 5.3 Assumption of Electrification associated with Expansion of Distribution Line··············· 46 5.4 Assumption of Electrification Cost by Renewable Energy·············································· 51 5.5 Selection of Candidate Barangays for Electrification by Renewable Energy··················· 60 Chapter 6 6.1 Rural Electrification Plan by Renewable Energy·························································· 61 Potential of Micro Hydro Power Plant ············································································ 61 6.2 Hydro Power Generation Plant at Barangays ·································································· 61 6.3 Micro Hydro Power Plant ······························································································· 62 6.4 Biogas Power Plant········································································································· 66 Chapter 7 Profile of the Project ···································································································· 69 Appendix 1 Schedule for Field Investigation Appendix 2 Interviewed Persons List Appendix 3 Photos Figure List Fig-5.1 Status of Barangay Electrification in Region VIII ···················································· 35 Fig-5.2 Status of Barangay Electrification in Northern Samar ············································· 36 Fig-5.3 Diagram of Transmission Line in Philippines (Northern Samar Area) ···················· 37 Fig-5.4 Breakdown of Consumer Numbers in NORSAMELCO (as of 2004) ····················· 39 Fig-5.5 Demand Forecast of NORSAMELCO ······································································ 40 Fig-5.6 Assumption of Electric Demand by Rural electrification (daily load curve)··········· 45 Fig-5.7 Expansion Plan of Distribution Line ········································································· 48 Fig-5.8 Outline of 3kW Stirling Engine (ST-5) ····································································· 57 Fig-6.1 Micro Hydro Power Turbine Types ············································································· 63 Fig-6.2 Turbine Selection Diagram·························································································· 64 Fig-6.3 Biogas Generating System··························································································· 68 Table List Table-1.1 Study Team Members·································································································· 3 Table-2.1 Hydropower Measurable Targets ······································································ 9 Table-2.2 Indicative Hydropower Capacity Addition ······················································ 10 Table-3.1 1999 – 2006 Implementation Plans of O-Ilaw Program and ER Program ··············· 20 Table-3.2 Electrification Level by Region (As of 31, October 2006) ······································ 21 Table-3.3 Barangay Electrification Level by Franchise Holder (As of October 2006) ··········· 21 Table-3.4 Rural Electrification by Method (1999 – 2002) ························································ 25 Table-4.1 Electricity Demand ······························································································· 31 Table-4.2 Annual Power Purchase ······················································································ 32 Table-4.3 Supply – Demand Profile ····················································································· 32 Table-4.4 Level of Electrification ························································································· 33 Table-5.1 Status of Barangay Electrification in Region VIII ···················································· 35 Table-5.2 Status of Barangay Electrification in Northern Samar ············································· 36 Table-5.3 Outline of NORSAMELCO (As of 2006 Oct.)························································· 38 Table-5.4 Energy Distribution of NORSAMELCO(2004) ······················································· 39 Table-5.5 Electric Tariff of NORSAMELCO(2004) ································································· 39 Table-5.6 Income Statement of NORSAMELCO(2004) ·························································· 40 Table-5.7 NORSAMELCO Development Plan ········································································· 41 Table-5.8(1) Current Situation of Electrification of Barangays in Catubig ·································· 43 Table-5.8(2) Current Situation of Electrification of Barangays in Las Navas ······························ 44 Table-5.9 Assumption of Electric Demand by Rural electrification········································· 45 Table-5.10 Electrification Plan of Barangay ··············································································· 46 Table-5.11 Number of Household and Distance of Distribution Line ········································ 48 Table-5.12 Electrification Cost by Expansion of Distribution Line ··········································· 50 Table-5.13 Electrification Cost by Each Method of Power Generation ····································· 53 Table-5.14 CDM Project by Usage of Biogas in Philippines (Registered CDM Project)·········· 54 Table-5.15 Current Situation of Firming of Livestock and Poultry in Catubig ·························· 55 Table-5.16 Specification of Stirling Engine ················································································ 58 Table-5.17 Assumed Amount of Rice Chaff for Generating ······················································· 58 Table-6.1 Potential of Micro Hydro Power at Catubig Service Area············································ 61 Table-6.2 Basic Specification of Hybrid Power Generating at Each Barangay ···························· 65 Table-6.3 Basic Specification of Biogas Power Generation························································· 67 Table-6.4 Comparison of Biogas Generating in Philippines and Japan········································ 68 Abbreviations ã»DOEïŒDepartment of Energy ã»NPCïŒNational Power Corporation ã»NPC-SPUGïŒNational Power Corporation Small Power Utilities Group ã»NIAïŒNational Irrigation Administration ã»PNOCïŒPhilippine National Oil Corporation ã»PNOC-EDCïŒPhilippine National Oil Corporation-Energy Development Corporation ã»TRANSCOïŒTransmission Company ã»NEAïŒNational Electrification Administration ã»PSALMïŒPower Sector Assets and Liabilities Management Corporation ã»ERCïŒEnergy Regulatory Commission ã»EPIRAïŒElectric Power Industry Reform Act ã»PEPïŒPhilippine Energy Plan ã»WESMïŒWholesale Electricity Spot Market ã»IPPïŒIndependent Power Producer ã»NEDAïŒNational Economic and Development Authority ã»NORSAMELCOïŒNorthern Samar Electric Cooperative, Inc. ã»SIDCïŒSorosoro Ibaba Development Cooperative ã»LGUïŒLocal Government Unit ã»NGOïŒNon Government Organization ã»DILGïŒDepartment of Interior and Local Government ã»ERïŒEnergy Regulation ã»RWMHEEïŒReforestation and Watershed Management, Health and Environment Enhancement ã»RECïŒRural Electrification Cooperative ã»BAPAïŒBarangay Alternative Power Association ã»LUWASïŒLocal Unit Water and Sanitation Systems ã»RAICïŒRegional Agri-Industrial Center ã»PDIPïŒProvincial Development Investment Program ã»PDMPïŒProvincial Development Management Plan ã»PDCïŒProvincial Development Council ã»RPSïŒRenewables Portfolio Standard ã»JICAïŒJapan International Cooperation Agency ã»JBICïŒJapan Bank For International Cooperation Executive Summary To sustain the government’s efforts in providing a better quality of life to the Filipino people, the eradication of poverty remains a top national concern and a big challenge to the present administration in the Philippines. The Philippine government set plans that would attain its target of completing the energization of all barangays by year 2008. The Northern Samar province in the Eastern Visayas region, which is the study area for this feasibility study on rural electrification, is one of the underdeveloped areas in the Philippines. Its per capita income level is less than 50% of the average per capita income level in the Philippines. Since the electrification rate of households in the northern mountainous area is only less than 20%, it has targeted to increase the electrification rate in order to boost the growth of agricultural activity and the development of the tourism industry. JBIC has decided to fund the Exclusive Agricultural Development Project in the Catubig watershed area in the municipalities of Catubig and Las Navas in Northern Samar. This project aims to increase agricultural productivity, particularly of rice and other crops, increase the income of residents and improve health and sanitary conditions. This will be addressed by the development of an agricultural infrastructure centered on an irrigation system. This project will commence in 2007 and will be completed in 2008. It is envisioned that there will be an improvement in the quality of life of the people belonging to the poor sector upon the development of the base infrastructure. Moreover, the acceleration of rural electrification is also expected. This study covers the feasibility of rural electrification by renewable energy, such as micro hydro power supplied from the potential of the Catubig River and irrigation facilities and biomass power energy supplied from agricultural products. The increase in agricultural products is an expected outcome of the Exclusive Agricultural Development Project in the Catubig watershed area. As a result of this study total construction cost of rural electrification by hybrid system between micro hydro power for the base load and biogas power for the peak load is estimated as most competitive other than the cost of other alternatives such like expansion of distribution line to the beneficiary, soro micro hydro power, soro biogas power and rice chaff power. - S-1 - Chapter 1 Introduction 1.1 Background and Objectives To sustain the government’s efforts in providing a better quality of life to the Filipino people, the eradication of poverty remains a top national concern and a big challenge to the present administration in the Philippines. The Philippine government set plans that would attain its target of completing the energization of all barangays by year 2008. Two-thirds of the poverty group, which comprises about 40% of the population in the Philippines, are engaged in the farming and fishing industries. Realization of rural electrification is expected to bridge the gap between the rich and the poor, help eradicate poverty in rural areas, provide a better quality of life and produce new sources of income. The Northern Samar province in the Eastern Visayas region, which is the study area for this feasibility study on rural electrification, is one of the underdeveloped areas in the Philippines. Its per capita income level is less than 50% of the average per capita income level in the Philippines. Since the electrification rate of households in the northern mountainous area is only less than 20%, it has targeted to increase the electrification rate in order to boost the growth of agricultural activity and the development of the tourism industry. The main industry in this province is agriculture, with major crops including rice, corn, coconut, banana and cassava. Although agriculture is the province’s main income source, self-sufficiency in rice has not been attained. Therefore, rice has been imported from the adjoining Leyte province. Poor health and sanitary conditions, including that of the rural sewerage systems, have brought some diseases to the residents, thereby contributing to the slow progress in the province. Furthermore, since the roads in this area are unpaved, agricultural products can not be easily transported during the rainy season. These factors contribute to the low income level in the province. JBIC has decided to fund the Exclusive Agricultural Development Project in the Catubig watershed area in the municipalities of Catubig and Las Navas in Northern Samar. This project aims to increase agricultural productivity, particularly of rice and other crops, increase the income of residents and improve health and sanitary conditions. -1- This will be addressed by the development of an agricultural infrastructure centered on an irrigation system. This project will commence in 2007 and will be completed in 2008. It is envisioned that there will be an improvement in the quality of life of the people belonging to the poor sector upon the development of the base infrastructure. Moreover, the acceleration of rural electrification is also expected. This study covers the feasibility of rural electrification by renewable energy, such as micro hydro power supplied from the potential of the Catubig River and irrigation facilities and biomass power energy supplied from agricultural products. The increase in agricultural products is an expected outcome of the Exclusive Agricultural Development Project in the Catubig watershed area. 1.2 Scope of Work This study covers the feasibility of a scheme for implementation of this project, site survey and collection of data on the following: 1.3 z Site Survey at Power Plant site z Present condition and action assignment of rural electrification z Feasibility study of rural electrification by renewable energy Study Area This study was conducted in the municipalities of Catubig and Las Navas, which are located in the Northern Samar province, the mountainous region of north Samar Island. To gather more information on case examples for renewable energy generation, the study team visited a biogas power plant site, which is currently undergoing construction in the Batangas province, and an existing micro hydro power plant in the Laguna province. 1.4 Study Schedule Two site surveys were conducted for this study. The first survey was conducted to have a meeting, gather information and collect data from the concerned government units and branch offices during the period October 10, 2006 to October 14, 2006. -2- The second survey was conducted to have a meeting with concerned government officials and visit the proposed site and some unenergized barangays in Northern Samar, the existing micro hydro power plant in Laguna and the biogas power plant site in Batangas. This second survey was carried out from December 3, 2006 until December 12, 2006. The detailed schedule of the site surveys is shown in the attached documents. 1.5 Study Team Member Members of this study are listed below. Table-1.1 No Study Team Member Name Specialty 1 Takatoshi Nagao Project Manager, Project Implementation Plan 2 Masahiko Kaneko Study of Renewable Energy 3 Yusuke Inoue Electric Power Facility Plan 4 Kei Katayama Rural Electrification Plan 5 Hiroki Aso Regional Development Plan -3- Chapter 2 Socio-economic Development in Communities Hosting Renewable Energy 2.1 Economic Development and Energy in the Philippines The link between energy and the economy has never been more evident than now when energy-related events tend to impact on a country’s economic performance. An increase in prices of oil, for example, is bound to immediately affect the prices of basic commodities and utilities such as water and electricity. The trickling effect goes on a wider scale as oil is a primary input to run our transport facilities. Electricity is also a basic requirement to sustain our industrial, commercial, and to a certain extent, agricultural activities. There is no doubt, therefore, that energy is a fundamental tool in any country’s development and a priori in the improvement of the people’s quality of life. Being aware of this fact, the government ensures that energy development is preceded by a rationalized and integrated energy-environment and economic planning approach. The Philippine Energy Plan (PEP), which has a revolving time frame of ten years, is guided and remains consistent with national development plans such as the Medium-Term Philippine Development Plan (MTPDP) and Medium-Term Philippine Investment Plan (MTPIP). It is also cognizant of the country’s commitment to international agreements such as the UN Convention on Climate Change, the Kyoto Protocol and more recently, the Johannesburg Plan of Action for Sustainable Development. The PEP, with the most recent edition being the 2006 PEP Update, is annually modified by the Department of Energy (DOE) and its attached agencies to integrate vital developments in the global and domestic economy. Thus, any PEP update carefully considers macro-economic planning set by the relevant government agencies in the Philippines such as the National Economic and Development Authority (NEDA) for the Gross Domestic Product, Gross National Product and Gross Value Added rates; National Statistics Office for the population growth and the Central Bank of the Philippines for the foreign exchange rates. On the other hand, crude oil prices are taken from international benchmarks. Such is the link between energy and the economy that the Arroyo administration has included energy independence as one of the components in its Five-Point Reform Package together with macro-economic stability, good governance, job creation and social development. With Philippine prospects for growth pegged at 5.5 percent in the next three years, all sectors in government including energy are called upon to contribute their respective shares in ensuring -4- the country’s sustainable growth. The DOE, the country’s energy policy making body, commits to this over-arching goal as affirmed in its mission statement, to wit: “improving the quality of life of the Filipino by formulating and implementing policies and programs to ensure sustainable, stable, secure, sufficient, accessible and reasonably-priced energy.” These are fleshed out in the two major goals as outlined in the Philippine Energy Plan 2005-2014 and affirmed in the 2006 PEP Update, to wit: attaining energy independence or a sustained self-sufficiency level of 60 percent by year 2010 and beyond; and, promoting the effective implementation of power sector reforms to bring about fair and reasonable energy prices in a competitive environment. In realizing the 60 percent self-sufficiency goal, the energy sector has laid out plans that will accelerate the exploration, development and utilization of indigenous energy resources, intensify renewable energy development; increase the use of alternative fuels; and, enhance energy efficiency and conservation measures. In the context of the study, the discussion will focus on the strategy of intensifying renewable energy development. Anchored on the government’s Renewable Energy Policy Framework (REPF) 2003-2013, the goal is to double the capacity share of renewable energy sources within the REPF time frame through the following specific objectives: a) Be the number one geothermal producer in the world b) Double hydro capacity by 2013 c) Be the number one wind energy producer in Southeast Asia d) Become the solar manufacturing hub in Southeast Asia e) Expand contribution of biomass, solar, and ocean energy by 131 MW 2.2 Renewable Energy Development in the Philippines Hydropower Hydro energy, as defined in the REPF, is generated from the movement of masses of water. Hydroelectric power plants convert energy contained in flowing water, such as rivers and streams, into electricity. They are classified according to various capacities as follows: a) -5- micro-hydro – 1 to 100 kW; b) mini-hydro – 101 kW to 10 MW; and c) large hydro- more than 10 MW. Hydropower generation started in the country in the early 1900s in the northern mountains of Luzon. This was followed by the construction of the Botocan hydroelectric plant in Laguna in the 1930s but which was commissioned only during the 1940s as a result of the war that crippled operations in the country. During the same decade and the 1950s, more hydroelectric plants were commissioned by the state-owned National Power Corporation (NPC). Below is a listing of the early hydro power projects built by the NPC, the Manila Electric Company (MERALCO), the country’s largest electric utility provider, and some private institutions, such as the Villa Escudero Plantation and Resort (Tiaong, Quezon ) and Camp John Hay Development Corporation (Baguio City): a) Early Micro-hydros 1) VILLA ESCUDERO HP Operator/Owner : Villa Escudero Plantations & Resort Capacity : 75 kW Year of Operation : 1937 Operator/Owner : PHILPODECO Capacity : 80 kW Year of Operation : 1939 2.) CALIBATO HP -6- b) Early Mini-hydros 1) Operator/Owner : John Hay Development Corp. Capacity : 560 kW Year of Operation : 1913 Operator/Owner : PHILPODECO Capacity : 650 kW Year of Operation : 1928 2) 3) c) CAMP JOHN HAY MHP BALOGBOG MHP PALACPAQUIN MHP Operator/Owner : PHILPODECO Capacity : 400 kW Year of Operation : 1937 Operator/Owner : MERALCO /NPC (1979) Capacity : 16.96 MW Year of Operation : 1930 Operator/Owner : NPC Capacity : 32.0 MW Initial Year of Operation : 1941 Complete Operation : 1950 Large Hydros 1) 2) BOTOCAN HP CALIRAYA HP -7- Current Situation In accordance with the REPF goals, the Philippines seeks to double its existing hydropower capacity from 2,518 MW in 2002 to 5,468 MW in 2013 through indicative capacity addition of 2,950 MW. Performance Assessment In the country’s quest for alternative clean sources of energy and correspondingly reduced dependence on imported fuels, hydropower generation presents a vital option. In 2004, hydropower resources contributed 15.9 percent to the country’s total power generation with the commissioning of the 345-MW San Roque Hydropower plant in Pangasinan and 350-MW Kalayaan 3 and 4 in Laguna. of fuel oil (MMBFOE). Fuel oil displacement of the sector reached 14.8 million barrels Currently, the country has 134 hydropower plants in operation, broken down into 21 large hydropower plants, 52 mini-hydropower plants and 61 micro-hydropower plants. -8- Measurable Sectoral Targets By 2014, the hydropower sector targets a cumulative installed capacity of 3,991 MW from hydropower resources, as outlined in the Philippine Energy Plan update 2006 (Table-2.1). This corresponds to about 780 MW of additional capacity from the current capacity of 3,219.1 MW, and is much smaller that the target capacity addition as defined in the REPF. Generation of electricity will reach 14,741 GWh by 2014, thereby displacing 25.4 MMBFOE. Table-2.1 Installed capacity (MW ) Luzon Visayas Mindanao Gross Generation (GWh) Luzon Visayas Mindanao Total Imported Fuel Oil Displacement (in MMBFOE) Hydropower Measurable Targets 2005 3,219.1 2006 3,219.1 2010 3,219.1 2014 3,991.1 2,209.8 11.61 997.65 8,374 2,209.8 11.61 997.65 8,563 2,209.8 11.61 997.65 12,996 2,509.8 61.61 1,427.65 14,741 4,422 35 3,917 14.44 4,611 35 3,917 14.76 8,896 35 4,065 22.41 8,819 188 5,734 25.42 Indicative Projects Potential sites for mini and micro-hydro projects are evenly distributed in all the country’s administrative regions. These were identified by the DOE, NPC and the National Electrification Administration (NEA). In 1995, the DOE conducted a water resource inventory study to validate NEA’s and NPC’s identified potential sites for promotion to private investors. Meanwhile, a study conducted by the United States Renewable Energy Laboratory (US-NREL) likewise revealed that micro-hydro potential sites are well distributed all over the country. The study gained the support of the local government units (LGUs), non-government organizations (NGOs), electric cooperatives (ECs) and the state-university based Affiliated Non-Conventional Energy Centers (ANECs) by also conducting local identification projects. -9- Table-2.2 Indicative Hydropower Capacity Addition Potential Region Project Location Capacity (MW) CAR Pasil HEP Kalinga 22.0 Talubin MHP Mt. Province 5.6 Can-eo MHP Mt. Province 5.9 Agbulu HEP* Apayao 360.0 Nalatang HEP* Benguet 75.0 Binongan HEP* Abra 175.0 I Upper Agno MHP* Pangasinan 5.0 II Adalam HEP Quirino 46.0 Diduyon HEP* Quirino 345.0 Abuan HEP* Isabela 60.0 Ilaguen HEP* Isabela 88.0 III Dinalugan MHP Aurora 0.5 Debutunan MHP Aurora 0.5 IV-A Kanan HEP* Infanta, Quezon 113.0 IV-B Batang-Batang MHP Palawan 3.5 Langogan MHP* Palawan 6.8 Babuyan Island MHP* Palawan 5.6 Catuiran HEP* Mindoro Oriental 18.0 Aglubang HEP* Mindoro Oriental 13.6 Cabinbin MHP* Palawan 0.8 V Kapipian MHP Catanduanes 3.0 Colasi MHP* Camarines 0.96 Dugui MHP* Catanduanes 3.5 Cawayan II MHP* Sorsogon 2.5 Hitoma MHP* Catanduanes 3.0 VI Igbolo MHP* Iloilo 4.0 Timbaban HEP* Aklan 23.5 Villasiga HEP* Antique 16.5 VII Pacuan HEP Negros Oriental 33.0 Siaton MHP* Negros Oriental 5.4 Okoy HEP* Negros Oriental 12.0 Sicopong HEP* Negros Oriental 17.8 VIII Bugtong MHP* Samar 1.0 Amandaraga MHP* Eastern Samar 4.0 IX Lower Dapitan MHP Zamboanga Norte 3.8 Salug Daku 1 MHP* Zamboanga Sur 2.5 Salug Daku 2 MHP Zamboanga Sur 2.5 Middle Dapitan MHP Zamboanga Norte 4.4 Salug Daku 3 MHP Zamboanga Sur 6.0 Salug Daku 4 MHP Zamboanga Sur 6.0 Upper Dapitan MHP Zamboanga Norte 3.6 Ingin MHP* Zamboanga Norte 3.0 * With feasibility study - 10 - Year Available 2011 2012 2012 2012 2014 2014 2008 2010 2011 2013 2014 2007 2010 2008 2006 2010 2010 2011 2011 2013 2006 2008 2009 2012 2012 2010 2011 2012 2007 2011 2012 2012 2009 2012 2006 2008 2008 2008 2010 2010 2011 2012 Region X Project Location Tuasan MHP Larangan MHP Culaman MHP Odiongan 3 MHP* Cabulig MHP* Tagoloan HEP* Impasugong HEP Odiongan 2 MHP* Liangan HEP Bulanog Batang HEP* Agus III HEP* XI Sibulan A Sibulan B Taytayan MHP Tandik MHP* Siguil B Talaingod MHP Suwawan HEP Tamogan HEP Camanlangan MHP Balutakay MHP XII Magpet MHP* Libungan MHP Pulangi V HEP* XIII Taguibo MHP Lake Mainit HEP Pugo HEP* ARMM Kanapnapan Fall MHP * With feasibility study Camiguin Misamis Occidental Bukidnon Misamis Oriental Misamis Oriental Bukidnon Bukidnon Misamis Oriental Lanao Norte Bukidnon Lanao Norte/Sur Davao del Sur Davao del Sur Compostela Valley Compostela Valley Sarangani Davao del Norte Davao City Davao City Compostela Valley Davao del Sur Cotabato North Cotabato North Cotabato Agusan Norte Agusan Norte Agusan Norte Lanao Sur Potential Capacity (MW) 0.5 8.5 10.0 10.0 3.5 68.0 68.0 5.0 11.9 132.0 225.0 16.5 24.0 0.6 5.0 15.0 10.0 40.0 60.0 1.0 0.2 10.0 10.0 300.0 7.0 22.0 18.0 10.0 Year Available 2008 2008 2008 2008 2009 2010 2010 2012 2012 2012 2014 2008 2008 2009 2010 2010 2010 2011 2011 2012 2012 2007 2010 2012 2008 2009 2010 2008 The 2006 Plan Update identifies 70 hydropower projects with a total potential capacity of 2,603.5 MW (Table-2.2). This is composed of 34 large hydropower projects, 27 mini-hydropower projects and nine micro-hydropower projects. projects have existing feasibility studies. - 11 - About 37 of these indicative Wind Power Wind energy refers to the energy that can be derived from the wind, which can then be converted into useful electrical or mechanical energy. In the Philippines, there are six regions identified with wind electric potential. These include the following: 1. Batanes and Babuyan Island 2. Northwest tip of Luzon (Ilocos Norte) 3. Higher interior terrain of Luzon, Mindoro, Samar, Leyte, Panay, Negros, Cebu, Palawan, Eastern Mindanao and adjacent islands 4. Well-exposed east-facing coastal locations from Northern Luzon southward to Samar 5. The wind corridors between Luzon and Mindoro (including Lubang Island) 6. Between Mindoro and Panay (including the Semirara and Cuyo Island The first large-scale wind power plant in the Philippines and in Southeast Asia is located in Bangui, Ilocos Norte. This 25-MW plant is developed by Northwind Power Development Corporation. During the first wind contracting round in 2004, 16 potential wind power sites were offered to private investors. The estimated total capacity of these sites is 345 MW. Six pre-commercial contracts (PCCs) were since then issued by the Department of Energy (DOE) to various developers. Nineteen additional wind power sites with an estimated total capacity of 3,270 MW were identified during the second batch. Six private investors signified their interest in developing some of these sites. Solar Power Solar energy is defined as energy derived form solar radiation which can be converted into useful thermal or electrical energy. Considering that the Philippines is situated near the equator, there is a nationwide potential for harnessing solar energy. Presently, there is a 960-kW CEPALCO solar power plant which is located in Cagayan de Oro in Mindanao and connected to the grid. - 12 - There are eight solar energy programs, seven of which are funded by foreign donors. As part of the Solar Electrification Project, a 28-kWp centralized photovoltaic (PV) plant was also installed in Pangan-an Island, Cebu to supply electricity to about 200 households. The Solar Power Technology Support (SPOTS) Project was designed to install solar energy systems in about 80 Agrarian Reform Communities (ARCs). There are 5,600 solar energy systems completed in 154 barangays under this program. The Environmental Improvement for Economic Sustainability (EIES) Project also promotes the use of photovoltaic systems for rural-based electrification through the installation of 15,000 Solar Hybrid Systems (SHSs) in the target regions, which include Regions I to VII, the Minadanao area and the Cordillera Administrative Region (CAR). implemented by PNOC, in coordination with the DOE. This project is being As of the first quarter of 2006, 9,191 SHS have already been installed. Biomass The Philippines has significant biomass resources which can be harnessed to develop energy systems. The DOE has identified a biomass (bagasse) potential of 250 million barrels of fuel oil equivalent (MMBFOE) in the country. In terms of capacity, the country has a total installed capacity of 235.7 MW from the different regions, with Western Visayas having the biggest potential of 127.8 MW. While the documentation of biomass energy systems is still an ongoing activity, the DOE has listed down several ongoing biomass projects including the 30-MW Talisay Bioenergy Project and the 50-MW Bioenergy Project. There are likewise ongoing studies for the 25-MW Bais City Project, the 25-MW Capiz Bioenergy Project, the 5-MW La Suerte Rice Hull Project and the 5-MW Inter City Rice Hull project. The DOE foresees the expansion of RE contribution (biomass, solar, micro hydro and ocean) by 250 MW by year 2013. - 13 - 2.3 Major Issues The capital-intensive nature, long gestation period (average of seven years) and related issues of social acceptability of large hydropower projects remain to be the sector’s biggest challenges. On the other hand, micro-hydro development for off-grid electrification is hindered by high upfront costs and the need for government support and intervention. Socio-environmental concerns There is considerable resistance for the development of large hydropower projects due to the potential for upstream flooding, destruction of agricultural areas and animal habitats and disruption of communities in the affected areas. These factors have affected the attractiveness of large hydropower projects. Shift in type of development Given the many issues plaguing large hydropower projects, the logical step is to focus on smaller, more manageable run-of-river projects. However, such shift will have to consider some challenges, such as a decrease in new potential capacity given the smaller scale of the projects, intermittent supply of power and an anticipated decrease in power generation during the summer months. Commercialization of hydropower technology There is a need to develop and commercialize suitable micro-hydro technology in the Philippines, even as hydropower technology for large and small projects is proven and mature. The Philippines remains to be dependent on imported electro-mechanical equipment for micro-hydro projects. The costs of these equipment vary based on kilowatt capacity. For instance, a 5-kW equipment with controls and metering devices costs US$11,000 while a 100-kW equipment costs US$64,500. 2.4 Government Policies and Programs The aggressive development of the country’s renewable energy (RE) resource potential comes as the second most critical strategy in attaining the Philippine government advocacy for energy independence. In recent years, the steady increase in the contribution of geothermal - 14 - and hydropower resources to the power generation mix has lessened the country’s dependence on imported fuels. In the government’s rural electrification efforts, renewable energy sources such as solar, micro-hydro, wind and biomass resources are seeing wide-scale use. Thus, it has become the government’s policy to facilitate the energy sector’s transition to a sustainable system with renewable energy as an increasingly prominent, viable and competitive option. Along this context, the government is strongly working for the passage of House Bill 1068 entitled “An Act to Promote the Development, Utilization and Commercialization of Renewable Energy Sources” to further boost renewable energy in the country. The proposed bill, now on bicameral discussions, aims to promote the development of RE to further reduce the country’s reliance on generation systems powered by imported fuels while minimizing exposure of the economy to price fluctuations in the international markets. The bill will also ensure the increase in RE use through the provision of fiscal and non-fiscal incentives to RE developers, including mandatory generation, priority dispatch for intermittent generation and establishment of a trust fund. Likewise, the zero rating provided for RE-generated electricity under the recently-implemented Reformed Value Added Tax Law (R-VAT) or Republic Act 9337 will enhance the competitiveness of RE-sourced electricity. Specifically, for hydropower projects, the enactment of Republic Act No. 7156, otherwise known as the Mini-Hydroelectric Power Incentives Act, in September 12, 1991 institutionalized attractive incentives for mini-hydro development, and consolidated under the then Office of Energy Affairs the responsibility and authority for hydropower development in the country. The law was meant to address the financial issues plaguing the industry then in the wake of the peso depreciation experienced by the country in the late 1980s. Summarized below are the important provisions of RA 7156 which are enforced to date: a) Special privilege tax rates – Tax payable by developers/grantees to develop potential sites for hydroelectric power and to generate, transmit and sell electric power shall be 2.0 percent of their gross receipts. b) Income tax holiday for seven years from the start of commercial operation. c) Tax and duty free importation of machinery, equipment and materials – Exemption from payment of tariff duties and value-added tax (VAT) on the importation of machinery and equipment within seven years from date of award of contract. - 15 - d) Tax credit on domestic capital equipment – For developers who buy machinery, equipment, materials and parts from local manufacturers, tax credit is granted in an amount equivalent to 100 percent from the value of VAT and customs duties that would have been paid to import said machinery, equipment, etc. e) Special realty tax rates on equipment and machinery – Realty and other taxes on civil works, equipment, machinery and other improvements of a registered mini-hydroelectric power developer shall not exceed 2.5 percent of their original cost. f) VAT exemption – Exemption from payment of 10 percent VAT on gross receipts derived from the sale of electric power whether wheeled via NPC or electricity utility lines. In relation to the issues presented earlier, the following are some action plans that the DOE has indicated to pursue: a) Information, Education and Communication to enhance public acceptability Prior to the implementation of the hydropower projects, the DOE shall involve all stakeholders in the decision-making process which could also include consultations with cultural communities (since hydro projects are mostly in the hinterlands). consideration. This would ensure that rights of the affected peoples are taken into At the same time, project risks are easier to ascertain through the joint conduct of social preparation activities. b) Promotion of alternative hydro development The run-of-river schemes of construction will allow for a balance of river ecosystems while providing communities dependent on the river for their livelihood to co-exist with hydropower projects. In addition, the government would place greater emphasis on projects with social and environmental issues by treating these problems as an integral element, along with economic and financial considerations in the decision-making process. - 16 - c) Commercialization of hydropower technology With additional incentives as stipulated in the proposed RE Bill, the commercialization of locally made hydropower equipment can be attained. The following measures are proposed to hasten commercialization: 1) Establishment of a Market Service Center The Center will assist RE producers to obtain legal papers and permits required for RE projects. Likewise, under the UNDP-assisted CBRED project, there are provisions for various financing assistance options available to developers of renewable energy projects. The Center is also envisioned to be the repository of database for all hydropower projects. 2) Pursuit of technical cooperation with other countries For small-scale hydropower development, the basic strategy for commercialization is to encourage electro-mechanical manufacturers to set up facilities in the Philippines and reduce the cost of importation of turbine equipment. There are several local turbine fabricators in the country that can be trained to enhance their capability to manufacture turbine equipment. The DOE will likewise continue to seek technical and bilateral cooperation with other countries that offer the latest expertise and technology transfer to replicate some successful demonstration projects. - 17 - 2.5 Impact to Host Communities The DOE continues to fulfill its social commitment to communities hosting energy projects through Energy Regulations (ER) 1-94 of Republic Act (RA) 7638 or the Department of Energy Act of 1992. Other enabling legislations include the following: Republic Act 7160 or the Local Government Code and Republic Act 9136 or the Electric Power Industry Reform Act (EPIRA) of 2001. Energy projects include energy-generating facilities or energy resource development activities. Section 289 and 294 of the RA 7160 provides that the LGU shall receive 1.0 percent of the gross sales of the preceding calendar year or 40 percent of the total collection of royalties, taxes and other fees earned from the development and utilization of energy resources, whichever is higher. Eighty percent of this allocation shall be applied solely for the reduction of electricity costs where such resources are located while the remaining 20 percent will be used for local development and livelihood projects. On the other hand, ER 1-94 requires generation companies and/or energy resource developers to set aside Php 0.01/kWh of their total electricity sales as financial benefits to the host communities. classifications: Funds can be accessed by proposing projects under any of the following electrification fund (EF); development and livelihood fund (DLF); and, reforestation, watershed management, health and/or environment enhancement (RWMHEEF). The allocation of the fund is as follows: 50 percent of one centavo for EF and 25 percent each for DLF and RWMEEF, respectively. The non-monetary advantages, on the other hand, include the prioritization of load dispatch, training and skills development, preference in employment, preference in procurement of local supplies and sound environmental management. The grant of financial benefits was subsequently strengthened in Section 66 of the EPIRA and Part A, Rule 29 of the EPIRA’s Implementing Rules and Regulations. The guidelines expanded the coverage with the inclusion of energy generating facilities having capacities of 10 MW and below. - 18 - Chapter 3 Rural Electrification 3.1 Current Condition of Rural Electrification Rural electrification in the Philippines has been adopted as a key policy of the national government as it can improve the living standards of the people and reduce poverty by the creation of new income sources in rural areas. In 1960, the Philippine government declared its stance in tackling rural electrification as a national policy, and established the Electrification Agency (EA). In 1969, the National Electrification Act was enacted and the EA was reorganized to form the National Electrification Administration (NEA), with the task to seriously undertake rural electrification. As power distribution in the Philippines had been carried out by private companies, the business was concentrated in highly populated urban areas where economic efficiency is greater. was growing larger. Therefore, the difference between urban and rural areas To solve this situation, NEA initiated the promotion of rural electrification through the Rural Electrification Cooperatives (RECs1) to be established in the local areas pursuant to the Act2. Spurred by a substantial amount of subsidies from the national government and the support agencies, rural electrification dramatically advanced in the 1970s, and the number of RECs reached the current 119 in 1980. However, there were some RECs with weak financial foundation and many had poor collection of electricity charges. Thus, electrification has been carried out with many financial issues. By 1997, electrification was completed for all municipalities, but the barangay level electrification remained only at roughly 72%. In order to keep promoting rural electrification, the Philippine government launched the O-Ilaw program in 2000 and the Expanded Rural Electrification (ER) program in April 2003. These programs were initiated to meet the objectives to complete electrification of all barangays by 2008 (initial target was 2004, which was changed to 2006 and re-changed to the current target), and to reach 90% household connection rate by 2017. It is said that there are 41,995 barangays in the Philippines, and roughly 8,300 (19.8%) were un-electrified as of the end of 2000. The national government is trying to accelerate electrification by increasing the annual target for electrification to 1,500 barangays (Table-3.1). 1 2 REC changed its name to Electric Cooperative (EC) in 1993. JICA Report of SW mission on "Rural Electrification in the Philippines (June 2004)" page 27 - 19 - Table-3.1 1999 – 2006 Implementation Plans of O-Ilaw Program and ER Program YEAR ANNUAL TARGET CUMULATIVE NO. OF BARANGAYS BARANGAY ELECT. LEVEL 1999(actual) 2000(actual) 2001(actual) 2002 2003 2004 2005 2006 TOTAL 755 1,366 1,253 1,636 1,664 1,700 1,095 1,000 7,095 32,281 33,647 34,900 36,536 38,200 39,900 40,995 41,995 - 76.90% 80.10% 83.10% 87.00% 91.00% 95.00% 97.60% 100.00% - (Source: DOE, http://www.doe.gov.ph/Rep/O-ilaw/oilaw.htm) In the Philippines, a subject barangay is deemed electrified either (1) electricity is supplied to 10 or more households in that barangay, or (2) feeder lines have been installed in the un-electrified barangay (electricity supply is possible, but to be electrified or not is up to the customer). But recently DOE reformed its definition (1) electricity is supplied to 30 or 40 households in that barangay by sustainable energy such as solar power, battery charge station (BCS), diesel power and others or (2) feeder lines have been installed in the un-electrified barangay. Definition described in (2) is the same as the last one but the number of beneficiaries of electrification was increased. However, even if 100% electrification is achieved on the barangay level, many households are yet to be electrified. In fact, an average 30 to 40 households in a barangay are connected, meaning that the barangay is electrified even if only a part of the barangay is actually served with electricity3. As of October 2006, of the total 41,945 barangays4, electrification has been completed in 39,590 barangays, giving an electrification rate of 94.4% (Table-3.2). Electrification rates are largely different among regions: Luzon region 97.1%, Visayas region 96.0%, and Mindanao region 87.0%. Comparison of the electrification rate by power distributor, which is responsible for electrification implementation, shows 93.8% for ECs, the largest in number, followed by 98.5% for MERALCO, and 97.7% for private business/municipality/others (Table-3.3). 3 4 Japan Electric Power Information Center, Inc "Overseas Electric Utility Industries 2003 – Philippines" pp. 543 The October 2006 data says the total number of barangays is 41,945. - 20 - Table-3.2 Area Electrified Barangays 39,590 19,888 10,982 8,720 Barangays Philippines Luzon Visayas Mindanao (Source: DOE) Table-3.3 Electrification Level by Region (As of 31, October 2006) 41,945 20,476 11,443 10,026 Unelectrified Barangays 2,355 588 461 1,306 Ratio (%) 94.4 97.1 96.0 87.0 Barangay Electrification Level by Franchise Holder (As of October 2006) Franchise Holder 119 Electric Cooperatives MERALCO 24 Private Investor Owned/ LGUs/ Others Total (Source: DOE ) 36,080 4,314 1,625 86% 10% 4% Electrified Completed 33,752 4,251 1,587 41,945 100% 39,590 Number of Barangay - 21 - Electrification Level (%) 93.8 98.5 97.7 94.4 Challenge 2,251 66 38 2,355 3.2 Promotion Policy of Rural Electrification Rural electrification has been carried out by concerned organizations led by the DOE, in accordance with the O-Ilaw Program and the ER Program. First, the Secretary of the DOE formulates an electrification objective for the year, which is allocated to the concerned organizations by the Program Team (PT) comprised of the DOE and other parties. 5 RECs and private power companies conduct actual implementation . Then, the The PT was formed through DOE Special Order No. 2000-01-03 in January 2000 (revised by S.O. No. 2001-04-010 in 2001). Its responsibilities include the overall planning, promotion, monitoring and evaluation of rural electrification. PNOC and NPC. The PT is composed of officials from the DOE, NEA, The Program Management Office (PMO) based in the DOE serves as the implementing arm of the PT. The O-Ilaw Program allows for a menu of options for participation from which donors or prospective partners can choose. The O-Ilaw Program components include the following6: (1) Regular electrification program of government agencies a) Department of Energy and its related agencies (i) Locally-funded projects on electrification using new and renewable energy sources (ii) Grant-in-Aid Programs (iii) Electrification projects under ER 1-94 Fund7 b) National Electrification Administration/Rural Electric Cooperatives c) National Power Corporation d) Philippine National Oil Company through its Environmental Improvement for Economic Sustainability (EIES) Project e) PNOC-Energy Development Corporation f) Department of Agrarian Reform through its Solar Power Technology Support (SPOTS) Project for Agrarian Reform Communities (2) Electrification projects of Private Investors-Owned Utilities such as Meralco, Davao Light and Power Company, etc. (3) Electrification projects of LGU-owned utilities 5 Japan Electric Power Information Center, Inc "Overseas Electric Utility Industries 2003 – Philippines" p. 544 The Philippine Department of Energy Website http://www.doe.gov.ph/Rep/O-ilaw/oilaw.htm 7 Financial Benefits to Host Communities under ER 1-94. One-centavo per kilowatt-hour (P0.01/kWh) of the Electricity Sales which shall apply to Generation Facilities and/or energy resource development projects (50% for Electrification Fund, 25% for Development and Livelihood Fund and 25% for Environment Enhancement Fund). 6 - 22 - (4) The Independent Power Producers (IPP) Program (5) The Adopt-a-Barangay Program (6) Electrification through the Renewable Energy Service Company (RESCO) concept As seen from these programs, the O-Ilaw Program and the ER Program offer participation in rural electrification projects to organizations other than government agencies and electric power suppliers. The funds come from different sources such as the national general budget, ER 1-94 fund, LGU budget, and subsidies from NGO or overseas. IPPs are also invited to participate with some expectation placed on their financial capability. Some examples of rural electrification implemented using the ER 1-94 fund are the PNOC-EDC's electrifying roughly 10 barangays near Ormoc on Leyte Island in 2000, the US Southern Energy's barangay electrification project near the coal-fired thermal power plant in Quezon, and 8 the Malaysia's East Asia project in Cebu . Rural electrification is basically carried out by an entity which holds the power distribution rights in the relevant area (Franchise Distribution Unit, e.g., EC). However, in the area where such FDU has declared no electrification plan in the foreseeable future in view of economic efficiency, electrification is implemented by the Missionary electrification project. Missionary electrification is undertaken by entities other than ECs, and they also expect private companies to participate. qualified third party (QTP). as a last resort. The entity implementing electrification in that area is called the If there are no QTPs, the NPC-SPUG will implement the project As Missionary electrification projects are for areas with little or no profitability, continuous subsidies are needed and the fund from a universal charge is appropriated. Universal charge is imposed on every electricity end-user as a part of the electricity charge, and its rate is decided by the Energy Regulatory Commission (ERC). 3.3 Issues of Rural Electrification For power distribution, the country is divided into a total of 138 service districts; 119 ECs, 16 private power distributors, and 3 municipal electric power suppliers. Of the ECs, only 15 (12.6%) have achieved 100% barangay electrification, and 75 (63.0%) have not reached 90%. None of the ECs have achieved 100% household connection rate9. 8 9 Japan Electric Power Information Center, Inc "Overseas Electric Utility Industries 2003 – Philippines" p. 544 JICA "Survey of Donor Trend for Overseas Electrification (Philippines) September 2003" page 123 - 23 - Electrification has two methods, one is to extend transmission/distribution grids and the other is to utilize dispersion type power sources. At the end of 2000, roughly 4,000 (approx. 45%) of about 8,300 barangays were located quite a distance from the existing grids 10 . Investment efficiency in these areas is significantly low. The grid extension is difficult due to dispersed locations of villages and electrification cost is high because of the low income level. Such areas have no choice but to depend on the off-grid dispersion-type power sources. Mini-hydropower is utilized in areas where hydropower potential exists. Other areas utilize mini grids that use new or renewable energy sources such as solar light, wind power and biomass. Individual electrification by solar home system (SHS) is also promoted. Table-3.4 shows the electrification methods used from 1999 to 2002. Of the 5,082 barangays, 4,159 or 81.8% were electrified by grid extension, and the remaining 923 or 18.2% ere through mini grid. Roughly 70% of the mini-grid electrification was through new or renewable energy sources11. Whether electrified by grid extension or by mini grid, the barangays to be electrified in the future have a small power demand, making the electricity supply cost high. As the income of the people living in such barangays is small, an electrification project is quite unattractive to the power distributors. A big issue for the future is how electrification should be promoted in such areas from the perspective of livelihood improvement of the residents. The DOE has other data useful for planning future electrification. Roughly 1,700 barangays, approx. 18% of roughly 8,300 un-electrified barangays, are located in the provinces where power plants have already been constructed. for the demand outside the province. These power plants mainly supply energy It is desirable for them to contribute to promoting the electrification of un-electrified barangays in one way or another. ER1-94 fund was established to this end. As aforementioned, pursuant to this system, power producers are obliged to set aside one centavo (0.01 peso) per kWh of energy generation to the DOE fund. 50% of this fund is disbursed to energize the un-electrified barangays surrounding the power plants. It is also possible for a power producer to construct a power-distribution grid, and in such a case, the ER 1-94 fund will be refunded later on12. At any rate, it has a significant value in planning the 10 11 12 The Philippine Department of Energy Website http://www.doe.gov.ph/Rep/O-ilaw/oilaw.htm JICA Report of SW mission on "Rural Electrification in the Philippines (June 2004)" page 32 The Philippine Department of Energy Website http://www.doe.gov.ph/Rep/O-ilaw/oilaw.htm - 24 - future direction of rural electrification to physically or institutionally utilize the existing power plants for electrification of areas surrounding the power plants. Table-3.4 Rural Electrification by Method (1999 – 2002) Year 1999 2000 2001 2002 Total Extension of Grid 713 1,078 1,010 1,358 4,159ïŒ81.8%ïŒ Isolated Small Gird 42 288 245 348 923ïŒ18.2%ïŒ Solar (PV) 42 56 212 310 620ïŒ12.2%ïŒ Micro Hydro 15 3 6 24 (0.5%) Hybrid 2 2 4 (0.1%) Generator Set 215 28 32 275 (5.4%) Total 755 1,366 1,706 5,082 (100.0%) ïŒ,255 (Source: JICA Report of SW mission on “Rural Electrification in the Philippines” (June, 2004) p. 32) 3.4 Effects of Rural Electrification During the survey of last year, we visited the area in Pasil, Kalinga Province, which was electrified through micro hydro by JICA. We interviewed one customer and the details are as given below: (1) Place visited: Residence of Mr. Constantio Rosito (2) Location: Dangtalan (former Balangao), Pasil (3) Summary: i) State of electrification: The electrification of this area was carried out in December 2004, through micro hydropower to provide 15 kW, by JICA and DOE. of the 180 households in this area are connected. a.m. the next morning. Almost all Power is supplied from 5 p.m. to 8 The operation is undertaken by the Barangay Alternative Power Association (BAPA). ii) Electric appliances owned: adjacent town. Mr. Rosito is in the police service of Balbalan, the His house has fluorescent lamps (8 W x 5: 40 W), a refrigerator (93 W), a rice cooker, a TV, a VCR, etc. demand is less than 200 W. As they are not used simultaneously, the total Fluorescent lamps of 8 W are recommended so that electricity can be used by as many households as possible. pesos. One lamp costs 170 At another household whose head is a carpenter, a power saw (800 W) and a - 25 - power planer (500 W) were purchased after electrification. The electricity charge is computed using a calculation formula according to the demand. per month. They pay 180 pesos Though there is no meter installed now, BAPA is looking into installing meters, which have already been provided free of charge by the DOE. As no meters are installed, some residents complain that they may be overcharged. The BAPA has two charge collectors. iii) Lifestyle changes after electrification: after electrification. People's lifestyle has significantly changed The biggest change is the use of kerosene. They were using kerosene lamps and 4 liters of kerosene in 15 days costing 140 pesos. turned out to be cheaper. Changes occurred in children's life. Electricity The time used for studying lessened during the first 6 months after electrification because they were watching TV and videos. Recently, however, they got bored of those activities and started to study longer than before. There are 6 children in the family, 2 in junior high school, 3 in elementary school, and one toddler. happening in other households. VCR. The same thing seems to be Roughly 30% of the households own a TV and a Satellite broadcasting system can be installed for 750 pesos. The problem of micro hydropower is the voltage fluctuation. At one time, the heater of the dummy load at the power plant broke down causing a rise in voltage and shutting the lights off. The effects of rural electrification on residents are systematically summarized in the 2004 Ex-Post Evaluation Reports regarding the Philippine NEA Rural Electrification Project13 implemented by the Japan Bank for International Cooperation from 1994 to 2001. The Report states that the rural electrification in the Philippines brought about the following effects14. [Impact of Project] For this evaluation, a survey was conducted to study the positive and negative impacts of this project on local residents. 47% of the residents interviewed answered "very satisfied," and 46% answered "satisfied," showing as much as 93% of the residents are satisfied with the project. Asked what impact of electrification they recognized, they 13 L/A was concluded in August 1994. Yen loan amount 11.4 billion yen (loan disbursed amount 9.7 billion yen). Implementing agency: National Electrification Administration (NEA) 14 JBIC Ex-Post Evaluation Report 2004 "NEA Rural Electrification Project" http://www.jbic.go.jp/english/oec/post/2004/pdf/2-26_full.pdf - 26 - responded that the project provided not only pastimes and convenience through lighting and other electric appliances but various positive changes such as few fires, improved working and educational environment and improved communications among family members and neighbors. The negative impacts of this project were the debts incurred by household appliance purchases and electricity payment (13%) and the diminished traditional sense of values (3%). a) Increase in employment opportunities and income In the barangays electrified under the project, some residents started new businesses or increased their income utilizing electricity. Other examples include being able to operate the sundry store till late at night, making ice lollipops in the freezer for sale, and opening of a bakery. b) Improvement in educational environment The project electrified the educational institutions in the barangays, such as nurseries and elementary schools, as well as the general households. In the 16 barangays interviewed, a total of 13 nurseries and elementary schools and 4 high schools were electrified. In the general households, fluorescent and incandescent lamps that are much brighter than the formerly used kerosene lamps allow for the children to study at night. c) Improved convenience and increased pastimes After electrification, most households purchased fluorescent lamps, light bulbs and other lighting fixtures (93% of the surveyed). Other electric appliances purchased that can serve to enhance convenience and ease the burden of household chores are refrigerators (26%), irons (16%), washing machines (8%), electric rice cookers (5%), and electric pumps for domestic water (4%). They also bought entertainment items, such as TVs (54%), VCRs (24%), radios/radio cassette players (30%), karaoke machines (13%), and video games (2%). The residents' lifestyle changed from working in the field during the day and coming home to sleep after the sunset to talking under the light, or visiting neighbors to watch TV or video, or singing karaoke together. Many households replied that their communication within the family or with the neighbors had improved. d) Securing less expensive, safe light source Prior to electrification, most of the households were using kerosene lamps as a light - 27 - source. After electrification, fluorescent lamps of 20 to 40 W or incandescent lamps of 40 to 60 W are used. A 60-W incandescent lamp is 7 to 70 times brighter than a kerosene lamp, while the former is roughly a half to one-ninth of the latter in cost. The kerosene lamps often caused a fire when toppled. Other problems with kerosene lamps are bad smell from smoke, health damage including coughs and eye irritation, and soot. Many residents think that, now that they use fluorescent or incandescent lamps, they are worry free from fire and damage by kerosene lamp smoke. - 28 - Chapter 4 Outline of the Surveyed Area 4.1 Outline of Northern Samar Province Northern Samar is part of the Eastern Visayas Region, which hosts five (5) other provinces, namely: Leyte, Southern Leyte, Biliran, Eastern Samar and Western Samar. Northern Samar province occupies a total land area of 3,498 square kilometers. Northern Samar is located on the eastern part of the Philippine Islands. It is bounded by San Bernardino Strait on the north, Samar Sea on the west, Pacific Ocean on the east, and the provinces of Samar and Eastern Samar on the south. It ranks thirty-fifth (35th) in size among the 74 provinces of the Philippines and accounts for practically 1.2 percent of the total land area of the country. About 52 percent of the total land area is covered by forest and 42 percent is classified as alienable and disposable. Northern Samar is the gateway to the Visayas and Mindanao from Luzon. It can be reached by 14 hours bus travel through the Maharlika Highway passing Bicol Region and traversing the San Bernardino Strait via ferryboat in the primary ports of San Isidro and Allen. Presently, it is already accessible to Manila via Asian Spirit Airlines servicing four flights a week. It can also be reached by boat from Manila and Cebu via Calbayog City, Catbalogan - 29 - and Tacloban City. Some inter-island shipping companies have scheduled travel to the ports of San Jose and Laoang. Northern Samar covers 25 municipalities, 569 barangays and 94,410 households. Catarman is its capital town. The province registered a total population of 500,639 in 2000 (2000 Census of Population and Housing), posting an annual growth rate of 2.11 percent. Its population density is recorded at 143 persons per square kilometer. Majority speak the Waray-waray dialect. In terms of income, the province is classified as second class. Among the municipalities, majority or 62.5% are fifth class municipalities. Only two are considered second and third class municipalities (Catarman and Laoang). The major industries in Northern Samar are agriculture and fishery. Coconut, abaca, palay and root crops are the major agricultural crops of the province while bangus, crabs and prawns are among its major fish/seafood products. Other industries include furniture and handicraft making, hat and mat weaving, brick making, oil manufacturing and soap making. Northern Samar falls under the intermediate type climate, which has no distinct dry and wet seasons. 4.2 The rainiest months are October to January, while the driest is the month of May. Electric Power Situation in Northern Samar Eastern Visayas is dependent mainly on geothermal resource, Leyte Province host of the largest producer of geothermal energy in the country. being the The region hosts two (2) geothermal power plants: the Leyte Tongonan 1, 2 and 3 geothermal power plants – the Leyte Geothermal Power Plant (LGPP 1) with total installed capacity of 112.50 MW and dependable capacity of 99 MW, and the Tongonan 2 & 3 (Leyte A) with a total installed capacity of 610.80 MW and dependable capacity of 578.40 MW. The LGPP total power generation in 2005 stood at 1,929.62 GWh while Leyte A generation reached 604.04 GWh for the same year. Excess power generation from these plants are exported to Cebu and Luzon through the Leyte-Cebu grid and the Leyte-Luzon grid, respectively. Northern Samar is being serviced by an electric cooperative - the Northern Samar Electric Cooperative (NORSAMELCO) - in supplying the power requirements of the province. In 2005, the EC sold a total of 36,271 MWh of electricty to its customers. - 30 - The residential sector is the major user of electricity of the province with a 92.5 percent share in the total electricity demand for the same year. The electricity utilization level of the sector is expected to post an annual average growth rate of 9 percent for the 10-year period (2006-2015). On the other hand, the commercial sector only registered a 5.36 percent share in 2005 with an annual growth rate of 2 percent within the 10-year period, while the rest is shared by the industrial sector and other users of electricity, such as public buildings and street lights. Table-4.1 Electricity Demand Electricity Demand No. of Custom ers 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 Residential 33510 37670 41948 46001 50378 54995 59714 64131 68395 73001 Commercial 1985 2067 2128 2192 2279 2335 2391 2421 2450 2481 1 1 1 1 1 1 1 1 1 1 Others 818 869 888 905 930 956 962 969 982 996 Total 36,313 40,608 44,966 49,099 53,588 58,287 63,068 67,521 71,829 76,479 Industrial NORSAMELCO has no existing bilateral supply contract with the National Power Corporation (NPC) for the delivery of its power requiement. of power for the province. As such, there is no firm supply The EC depends on its annual non-contracted purchase of power from NPC, which is not sustainable since it would be determined by the availability of supply from NPC not contracted with other utilities. Given this condititon, the annual supply power deficit would be the annual power purchase of the province. average of 18% from 2001 to 2005. System losses acounted at an Projected system loss for the next 10 years is seen at a decreasing rate from 14% in 2006 to 5% in 2015. Meanwhile, peak demand stood at an average of 7.4 from 2001 to 2005, which is expected to demonstrate an increasing trend within the 10-year period – from 8% in 2006 to 17% in 2015. 7:00 p.m. consumers. The system peak occurs at around The over-all system load factor is low at 58% due to the dominance of residnetial To meet the required 13.2% reserve margin , the the electric cooperative needs additional capacity of 1 MW from 2006 to 2009 and 2 MW from 2010 to 2015. - 31 - Table-4.2 Annual Power Purchase Annual Pow e r Purchas e Purchas e Ye ar (MWh) 2001 25,871 2002 30,790 2003 34,235 2004 39,224 2005 40,550 2006 42,734 2007 45,967 2008 49,776 2009 54,235 2010 59,106 2011 65,391 2012 72,459 2013 78,001 2014 83,267 2015 89,302 Table-4.3 Supply – Demand Profile 30.00 Supply - Demand Profile (MW) 20.00 10.00 0.00 2008 2009 2 0 10 2 0 11 2 0 12 2 0 13 2 0 14 2 0 15 A dd'l C a p t o m e e t a t le a s t 13 .2 % R M 2002 2003 0 .9 2 1.0 6 2004 2005 2006 2007 1.0 6 1.0 6 1.11 1.19 1.2 9 1.4 1 1.5 4 1.7 0 1.8 5 1.9 9 2 .0 9 2 .2 4 Indic a t iv e S upply ( M W) 7 .0 0 8 .0 0 8 .0 0 8 .0 0 8 .4 1 9 .0 5 9 .8 0 F irm S upply ( M W) 0 .0 0 0 .0 0 0 .0 0 0 .0 0 0 .0 0 0 .0 0 0 .0 0 0 .0 0 P E A K LO A D ( M W) 7 .0 0 8 .0 0 8 .0 0 8 .0 0 8 .4 1 9 .0 5 9 .8 0 10 .6 7 11.6 3 - 32 - 10 .6 7 11.6 3 0 .0 0 12 .8 7 14 .0 2 15 .0 9 15 .8 4 16 .9 9 0 .0 0 0 .0 0 0 .0 0 0 .0 0 0 .0 0 12 .8 7 14 .0 2 15 .0 9 15 .8 4 16 .9 9 The barangay electrification level in 2005 stood at 67%, which can be translated to 380 barangays electrified. The electrification level represents one of the lowest in the country and is mainly due to the remote nature of the remaining unenergized barangays in the province. The absence of roads also makes it more difficult to extend the distribution lines to the barangays. The municipality of Las Navas, for example, can be easier reached by cruising the Catubig River, a main source of transportation for the village folks from the said town. The EC has waived twenty-three (23) barangays from its coverage for possible Third Party Agreements From its 546 coverage barangays (96% of the total number of barangays), the EC could meet its target of 100% barangay electrification level by 2008. However, about 40% of the total household population would remain unelectrified until 2015. Table-4.4 Level of Electrification Level of Electrification 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 83% 92% 96% 96% 96% 96% 96% 96% 96% 96% No . o f B arangays Energized (On-Grid) 446 493 516 516 516 516 516 516 516 516 No . o f B arangays Energized (Off-Grid) 26 30 30 30 30 30 30 30 30 30 Barangay Level (%) Total 472 523 546 546 546 546 546 546 546 546 36% 37% 39% 41% 44% 46% 49% 52% 55% 58% No . o f Ho useho ld Energized (On-Grid) 31,717 34,096 36,653 39,402 42,475 45,788 49,360 53,308 57,573 62,179 No . o f Ho useho ld Energized (Off-Grid) n.a. n.a. n.a. n.a. n.a. n.a. n.a. n.a. n.a. n.a. Total 31,717 34,096 36,653 39,402 42,475 45,788 49,360 53,308 57,573 62,179 Household Level (%) References: 1. 2. 3. 4. 5. Philippine Energy Plan 2005-2014 Philippine Energy Plan 2006 Update Renewable Energy Policy Framework National Electrification Chronicle, 2003 - 2005 Official Website of Northern Samar (www.northernsamar.gov.ph) - 33 - Chapter 5 Pre-Feasibility Study of Rural Electrification by Renewable Energy 5.1 Current Situation of Rural Electrification in Coverage Area 5.1.1 Current Situation of Rural Electrification in Northern Samar An area for this investigation is located along the Catubig watershed area in Northern Samar, in the municipalities of Catubig and Las Navas. Northern Samar is a province in the Eastern Visayas region (Region VIII). As of July 2006, the level of energization for barangays in Region VIII stood at 90.8%, with several electric cooperatives in Leyte, whose electric power is supplied by geothermal power plant, attaining a 100% energization level. However, the energization level in NORSAMELCO, which covers Northern Samar, is only 73.1%, the lowest among electric cooperatives in Region VIII (Table-5.1, Fig-5.1). The energization level in Catubig is 60.9% but in Las Navas, the level is a very low 11.3%. Thus, the acceleration of energization has become a very serious problem (Table-5.2 , Fig-5.2). - 34 - Table-5.1 Status of Barangay Electrification in Region VIII Electric Number of Barangays Cooperatives Covered Energized % Region VIII 4390 3984 90.8 DORELCO 499 494 99.0 LEYECO II 196 196 100.0 LEYECO III 285 285 100.0 LEYECO IV 245 242 98.8 LEYECO V 416 416 100.0 SOLECO 500 483 96.6 BILECO 132 132 100.0 SAMELCO I 427 366 85.7 SAMELCO II 524 482 92.0 ESAMELCO 597 472 79.1 NORSAMELC 569 416 73.1 (as of 2006,July,31) (Source: NEA) Fig-5.1 Status of Barangay Electrification in Region VIII Status of Barangay Electrification in Region VIII (as of 2006,July) 90 80 70 io n VI II DO RE LC O LE YE CO LE II YE CO III LE YE CO IV LE YE CO V SO LE CO BI LE CO SA M EL SA CO I M EL CO ES I AM I EL NO CO RS AM EL CO 60 Re g Barabgay Base Electrification Ratio (%) 100 - 35 - Table-5.2 Status of Barangay Electrification in Northern Samar (as of 2004.12.31) Municipality Energized Allen Biri Bobon Capul Catarman Catubig Gamay Laoang Lapinig Las Navas Lavezares Lope de Vega Mapanas Mondragon Palapag Pambujan Rosario San Antonio San Isidro San Jose San Roque San Vicente Silvino Lobos Victoria Total Potential Number of Barangays Households Covered Energized % 20 19 95.0 3,217 8 2 25.0 1,317 18 13 72.2 2,613 12 5 41.7 1,780 55 37 67.3 9,228 46 28 60.9 4,050 26 12 46.2 3,119 56 33 58.9 7,968 15 5 33.3 1,396 53 6 11.3 4,286 26 20 76.9 3,635 22 5 22.7 1,621 13 7 53.8 1,326 25 14 56.0 3,987 32 23 71.9 4,019 26 12 46.2 3,349 11 7 63.6 1,196 10 10 100.0 1,423 14 13 92.9 3,591 16 16 100.0 2,099 16 10 62.5 2,493 7 3 42.9 1,178 26 3 11.5 1,601 16 13 81.3 1,873 569 316 55.5 72,365 Cooperative Members House Connections Total % Total % 2,140 66.52 2,529 78.6 376 28.55 397 30.1 1,710 65.44 1,598 61.2 504 28.31 446 25.1 7,465 80.90 8,145 88.3 1538 37.98 1596 39.4 992 31.81 1104 35.4 3,707 46.52 3,905 49.0 441 31.59 476 34.1 451 10.52 479 11.2 1,565 43.05 1,624 44.7 309 19.06 374 23.1 472 35.60 471 35.5 1,985 49.79 1,927 48.3 2,181 54.27 2,259 56.2 1,396 41.68 1,470 43.9 596 49.83 629 52.6 723 50.81 665 46.7 2,155 60.01 2,291 63.8 1,356 64.60 1,385 66.0 1257 50.42 1288 51.7 195 16.55 196 16.6 12 0.75 12 0.7 956 51.04 945 50.5 34,482 47.65 36,211 50.0 Source : Northern Samar Electric Cooperative (NORSAMELCO), Inc., Bobon, Northern Samar Fig-5.2 Status of Barangay Electrification in Northern Samar Status of Barabgay Electrification in Northern Samar (as of 2004) 90 80 70 60 50 40 30 20 10 - 36 - Total Victoria San Vicente Silvino Lobos San Jose San Roque San Isidro Rosario San Antonio Palapag Pambujan Mapanas Mondragon Lope de Vega Lavezares Lapinig Las Navas Gamay Laoang Catubig Catarman Capul Biri Bobon 0 Allen Barangay Base Electrification Ratio (%) 100 5.1.2 Power Supply Facilities NORSAMELCO supplies electricity to its customers through the Wright substation (138kV/69kV), a transmission line system with 69kV and three substations (Dalakit, Lawaan and Allen) from the Tongonan geothermal power plant unit 1 (Steam Development: PNOC-EDC, Generating: NPC, Output 112.5MW). NORSAMELCO covers the Northern Samar area after receiving the electricity at the substation and distributes electricity to its customers. Electric supply to Catubig and Las Navas is transmitted from the Lawaan substation (69kV/13.2kV, 3.75MW) through a 30 km long distribution line (Fig-5.3). Fig-5.3 Diagram of Transmission Line in Philippines (Northern Samar Area) Electricity is also supplied by photovoltaic (PV) solar systems, small diesel power generating sets and battery charging systems (BCS) in Catubig and Las Navas. BCS put up using Solar panel systems are supplied by PNOC-EDC and NPC. The cost for charging a battery through the grid is 50-70 pesos while charging a battery through the PV solar system is about 20 pesos. The diesel power system is supplied by private enterprises with a cost of 100 pesos per 10m per month and four operating hours (18:00-21:00, 5:00-6:00). Even though the electricity rate is still expensive compared to the residents’ average income of 4,000-6,000 pesos per month, electricity demand is high as it increases the level of convenience in the life of the residents. Even though the normal cost of the solar system panel is 75Wp per set, the expensive 150Wp panel has nevertheless started to become popular. - 37 - 5.1.3 Summary of NORSAMELCO NORSAMELCO, the electric cooperative which provides electricity to the Northern Samar area, was established in 1977. NORSAMELCO distributes power to a total of 23 municipalities and 316 barangays out of 24 Municipalities and 569 Barangays in an area covering 3,498km2. The only remaining municipality without electricity will be energized by 2007. As of 2004, a total of 36,211 households out of the 72,000 households had a contract to receive the electricity (Table-5.3). The breakdown of the consumer volume of NORSAMELCO is 67% for residential, 18% for commercial, 9% for public building, 1% for industrial and 4% for street light (Fig-5.4). Table-5.3 Outline of NORSAMELCO (As of 2006 Oct.) Item Unit Number Peak Load kW 8,133 Load Factor % 64.8 System Power factor % 94.1 No. of Towns Covered 24 No. of Towns Energised 24 No. of Barangays Covered 569 No. of Barangays Energised 318 No. of Potential Consumers 72,365 No. of Actual Consumers 38,400 Energy Net Purchased (Monthly) kWh 3,717,908 % 21 Average Energy Rate (Buying) Peso/kWh 4.66 Average Energy Rate (Selling) Peso/kWh 6.23 Peso 18,331 System Loss Revenue (Monthly) (Source: NORSAMELCO) The energy distribution of NORSAMELCO in 2004 was 31,249MWh which included 72.4% for residential (Table-5.4). The latest information shows that 3,717,900kWh per month is distributed (as of October 2006) corresponding to 44,615MWh per year. As of 2006, the maximum electricity demand was 8,133kW (Table-5.3). With more electrification projects on line, NORSAMELCO foresees a problem of a larger system loss. At present, the average system loss stands at 12%. In addition to technical losses, the other sources of losses may come from defective electric meters, etc. - 38 - As of 2004, the electricity selling rate of NORSAMELCO was 6.13 pesos/kWh for Residential, 5.41 pesos/kWh for Commercial and 5.60 pesos/kWh for Total (Table-5.5). As of October 2006, the rate increased to 6.23 pesos/kWh. NORSAMELCO pays 4.66 pesos/kWh for electricity it purchases from the NPC (Table-5.3). Fig-5.4 Breakdown of Consumer Numbers in NORSAMELCO (as of 2004) Industrial, 1% Street Light, 4% Public Building, 9% Commercial, 18% Resident, 67% (Source: NORSAMELO) Table-5.4 Energy Distribution of NORSAMELCO(2004) MWh 22,632 5,141 183 3,293 31,249 Type Residential Commercial Industrial Others Total 72.4% 16.5% 0.6% 10.5% 100.0% (Source:2005 Regional Social & Economic Trends) Table-5.5 Electric Tariff of NORSAMELCO(2004) Type Peso/kWh Residential Commercial Industrial Public Building Street Light Total 6.13 5.41 5.45 5.46 5.57 5.60 (Source:2005 Regional Social & Economic Trends) According to the income statement of the electric cooperative, NORSAMELCO recorded deficits in two years. It had a deficit of 1,550,085 Pesos in 2004 but the deficit has been covered in recent years (Table-5.6). Fig-5.5 and Table-5.7 show the prospects for electric - 39 - demand and development plan, respectively, in NORSAMELCO. According to Fig-5.5 and Table-5.7, the number of consumers and the maximum peak load will increase by 13% and 7% per year, respectively. NORSAMELCO has formulated plans to attain its target of completing the energization of all barangays by year 2008. Table-5.6 Income Statement of NORSAMELCO(2004) Operating Revenue Operating Expense Net Operating Income Interest Charge Depreciation Charge Net Operating Income after Interest & Dep. Other Income Net Income (Loss) (Source: NORSAMWELCO 2004 Annual Report) Fig-5.5 Demand Forecast of NORSAMELCO 100,000 16.0 90,000 14.0 80,000 12.0 70,000 60,000 10.0 50,000 8.0 40,000 6.0 30,000 4.0 20,000 2.0 10,000 0 0.0 2005 2006 2007 2008 2009 2010 2011 2012 No. of Consumers - 40 - Peak Load (MW) Peak Load (MW) No. of Consumers (Peso) 2003 151,005,569 144,958,715 6,046,854 5,650,702 5,871,375 -5,475,223 2,998,464 -2,476,759 2004 188,004,480 180,266,376 7,738,104 3,326,224 8,291,743 -3,879,863 2,329,778 -1,550,085 Table-5.7 NORSAMELCO Development Plan Item 2005 No. of Costumers 39,044 Peak Load (MW) 9 Level of Electrification Barangay Level 73% No. Barangay Electrified (On-Grid) 352 No. Barangay Electrified (Off-Grid) 63 Total 415 Projected Infrastructure Requirement Distribution/ Sub-transmission Facilities 102 Expansion (ckt-kms) 102 Rehabilitation / Upgrade (ckt-kms) Substation Capacity (MVA) Reactive Power Compensation Plan (MVAr) 48 Capital Investment Requirements (Million Peso (Source: Phillipnes Energy Plan 2004-2013 ) 2006 44,014 9 2007 49,617 10 2008 55,942 11 2009 63,075 12 2010 71,124 13 2011 80,329 13 2012 90,447 14 82% 382 84 466 91% 412 105 517 100% 443 126 569 100% 443 126 569 100% 443 126 569 100% 443 126 569 100% 443 126 569 125 125 64 64 94 94 87 26 31 9 8 8 9 NORSAMELCO has adopted the QTP (Qualified Third Party) concept to implement the extension of distribution lines to some of its franchise areas. The DOE has considered the weakness of the financing base of NORSAMELCO. PNOC-EDC provides the electricity to surrounding areas in Leyte as it operates geothermal power plants in the area. Therefore, there is no claim from the beneficiaries of economical inefficiencies. However, intention of development of distribution lines depends on the QTP’s policy so that it is not so smooth to implement. The DOE expects that development of distribution lines will be implemented not only by PNOC-EDC but also by NPC-SPUG, NEA using public funds, and Mirant and KEPCO using private funds. 5.1.4 Current Situation of Electrification in the municipalities of Catubig and Las Navas A total of 28 barangays out of the 47 barangays in Catubig have been energized, while a total of 26 barangays out of the 53 barangays in Las Navas have been energized. Both municipalities consider electrification plans which will be implemented by QTPs (Table-5.8(1), Table-5.8(2)). However, these plans may not be actually implemented because no measures are taken such as assistance or penalty. 5.2 Assumption of Electric Demand associated with Rural Electrification As mentioned in the Help for Catubig Agricultural Advancement Project (HCAAP), the said project as financed through a yen-loan has been implemented. This project will bring development of irrigation and drainage facilities in an area of 4,500ha and a highway with a - 41 - distance of 65 kilometers. As a result of this project, extensive improvements are expected so that agricultural productivity will significantly increase from 1 ton/ha to 5 tons/ha. This study provides for the feasibility of the effective utilization of renewable energy resources in rural electrification. Renewable resources will be provided by micro hydro power potential from the irrigation canal as developed by HCAAP, and by biomass energy, contingent to increased agricultural production. Once barangays are energized, residents will purchase electric products such as lights, TV and refrigerator to make living conditions more convenient, and improve livelihood opportunities. Residents will also be encouraged to buy electric equipment such as power planer and electric saw which will generate savings on labor power and produce high-value added products. Once barangays are energized, household electrical goods such as household lights, TV, and refrigerators will become common along with street lights and pumps for water well, Ice manufacturing stores and rice mills will likewise be installed in the barangays (Table-5.9). Thus, a peak load of 9.6 kW is estimated for all barangays with a condition that 50 households are energized in one barangays. According to the daily power demand in the barangays (Fig-5.6), the load factor is estimated as 48.8%. - 42 - Table-5.8(1) Current Situation of Electrification of Barangays in Catubig 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 Catubig Barangay Population Household Electrification Plan Barangay 1Pobl 1,119 240 Barangay 2Pobl 441 83 Barangay 3Pobl 607 122 Barangay 4Pobl 416 78 Barangay 5Pobl 370 71 Barangay 6Pobl 313 58 Barangay 7Pobl 299 64 Barangay 8Pobl 827 154 Anongo 795 155 2007 Bonifacio 332 61 2007 Boring 182 35 Energized Cagbugna 432 76 Energized Cagmanaba 728 113 Energized Cagugubngan 451 84 Calingnan 976 182 Energized Canuctan 280 48 Energized CM Recto 477 88 D Mercader 465 97 Energized Guibuangan 368 73 Energized Hinagonoyan 676 105 Energized Hiparayan 694 125 Energized Hitapian 1,004 180 Energized Inobururan 141 25 Irawahan 704 128 Energized Lenoy ahan 334 65 Energized Libon 273 47 Energized Mag-ongon 342 53 Energized Magtuad 876 178 Energized Manering 221 43 Energized Nabuluo 337 63 Energized Nagoocan 643 120 Energized Nahulid 198 39 Energized Opong 590 114 Osang 244 51 2008 Osmena 290 66 P Rebadulla 339 56 Roxas 896 147 2007 Sagudsoron 435 80 San Antonio 309 55 2007 San Fransico 1,074 193 San Jose 2,348 435 San Vicente 1,671 327 2007 Santa Fe 787 138 2007 Sulitan 801 151 Tangbo 342 77 2006 Tongodnon 174 35 2006 Viena Maria 224 37 Total 26,845 5,015 (Source: Census 2000, DOE materials) - 43 - Fund Source PNOC-EDC PNOC-EDC NPC-SPUG PNOC-EDC PNOC-EDC PNOC-EDC PNOC-EDC NEA Mirant Table-5.8(2) Current Situation of Electrification of Barangays in Las Navas 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 Las Navas Barangay Population Household Electrification Plan Balugo 385 80 Energized Bugtosan 436 83 Energized Bukid 900 189 Energized Geguinta 408 82 Energized Geraodo 337 66 Energized Guyo 387 73 Energized H Jolejole 409 82 Energized H Jolejole District 1,477 322 L Empon 332 69 Energized Lourdes 793 151 Energized Lumala-og 399 89 Energized Mabini 491 92 Energized Mac Arthur 326 56 Energized Palanas 164 35 Energized Quirino District 1,748 331 Energized Rebong 557 101 Roxas 571 99 Energized San Andres 380 82 Energized San Jorge 756 149 Energized San Miguel 1,116 207 Energized Caputoan 209 41 Energized Cuenco 290 54 Energized San Fransisco 654 111 Energized San Isidro 1,666 335 Energized San Jose 259 44 Energized Santo Tomas 155 31 Energized 316 60 Energized Tagan-aïœan Victory 565 102 Energized Bugay 621 103 2006 Bulao 935 196 2008 Catoto ogan 219 44 2006 Dapdap 1,673 296 Energized 2006 Del Pilar 858 168 2006 Dolores 143 24 2006 Epaw 179 36 2006 Hangi 521 98 2008 Imelda 296 54 2006 Lakandula 224 46 2006 Magsaysay 459 96 2008 Matelarag 261 48 2007 Osmena 206 40 2008 Paco 305 63 2006 Perez 360 64 2008 Poponton 526 104 2008 Quezon 163 35 2008 Quirino 841 159 2008 Rizal 517 90 2008 Rufino 200 35 2008 Sag-od 188 33 2008 San Antonio 228 45 2008 San Fermando 921 184 2006 Tagab iran 1,157 224 2008 Taylor 859 140 2006 Total 29,346 5,641 (Source: Census 2000, DOE materials) - 44 - Fund Source Mirant PNOC-EDC KEPCO NEA NEA KEPCO KEPCO PNOC-EDC KEPCO KEPCO PNOC-EDC PNOC-EDC NPC-SPUG KEPCO NPC-SPUG NPC-SPUG PNOC-EDC NPC-SPUG PNOC-EDC NPC-SPUG NPC-SPUG NPC-SPUG NEA PNOC-EDC KEPCO Table-5.9 Assumption of Electric Demand by Rural electrification ïŒEnergy Denmand in BarangayïŒ <Demand> coverage (kW) (hour) Number of Households 50 Households 160 W Household Light (40Wx4) 70 W Household TV Households Refrigerator (50L 100 W (Refrigerator Availability) 0.3 ) ( Street Light (40WX25) 40 W Pump for Water Well 250 W Ice Manufacturer 1,250 W Rice Miller 3,000 W Total ïŒPeak Demand ïŒBase Demand Fig-5.6 0.8 0.5 0.3 6.4 1.75 0.45 25 1unit 1unit 1unit 1 0.25 1.25 3 9.6 5.0 4 4 24 (kWh/ day) Remarks 25.6 Peak 7.0 Peak 10.8 Peak & Base 12 12.0 Peak & Base 20 5.0 Non-Peak 20 25.0 Non-Peak 9 27.0 Non-Peak 112.4 kW 44.6 ïŒ kW 67.8 ïŒ Assumption of Electric Demand by Rural electrification (daily load curve) Daily Power Demand in Barangay (50 Households) 12 10 Demand (kW) 8 6 4 2 0 1 2 3 4 5 6 HH Ref 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 hour St Light HH Light - 45 - HH TV Pump Ice Rice 5.3 Assumption of Electrification associated with Expansion of Distribution Line Before initiating the study of electrification by renewable energy, a cost estimation study to develop extension of distribution line for rural electrification is needed. Unenegized barangays in Catubig and Las Navas are distributed in the south and east areas. To study rural electrification by extension of distribution line in the vicinity of the Catubig Service area, that study team needed to obtain the potential data. The population and number of households of the barangays are shown in Table-5.10. The table includes energized barangays as shown in Table-5.8(1) and Table-5.8(2). Barangays served by solar panel systems and small diesel generators are considered by the government as energized. Table-5.10 No. 47 53 14 48 27 25 35 49 24 50 Electrification Plan of Barangay Barangay Population Households Rizal Taylor Palanas Rufino Tagan-aïœan San Jose Epaw Sag-od San Isidro San Antonio 517 859 164 200 316 259 179 188 1,666 228 90 140 35 35 60 44 36 33 335 45 Total 4,576 853 - 46 - The specific plan for expansion of distribution line is assumed as shown in Fig-5.7. As a result of these expansion plans, the distance of expansion of distribution line and households is assumed as shown in Table-5.11. The electrification cost by expansion of distribution line is assumed to consist of the items as follows. 1. Capital cost for expansion of distribution line 2. Capital cost for installation of electric transformer and incoming line 3. Capital cost for extension of transformer at Lawaan substation 4. Operation and Maintenance cost for power distribution equipment 5. Cost for distribution loss from Lawaan substation to household 6. Power cost Where, As for No.1, the cost for expansion of distribution line is estimated to be USD 8,000 per km. The annual expense rate of 0.114 is estimated based on an expected lifetime of 25 years and a discount rate of 12%. As for No.2, the unit rate for a transformer of USD 1,600 is applied based on NORSAMELCO’s standard specifications for transformers with 13.2kV, 240V and 15kVA. As for No.3, the unit rate for a transformer of USD 12/kVA is applied. Even though no expansion is needed at the Lawaan substation in this plan, this cost is estimated for future expansion of electrification. As for No.4, the O & M cost is assumed to be 1.5% of the construction cost As for No.5, the distribution loss depends on the distance of the distribution line and the electric power, so that it is estimated by the multiplication method using the electric unit rate of NORSAMELCO. As for No.6, the consumer price is applied which contains the generating and transmission costs as well as the administration costs of NORSAMELCO. - 47 - Fig-5.7 Expansion Plan of Distribution Line Las Navas Mabini Goyo Taylor Rizal Hangi San Antonio Del Pilar Tagab iran Palanas Rufino Dapdap San Isidro Epaw Tagan-aïœan San Jose Sag-od Table-5.11 Section 1 2 3 4 5 6 7 8 9 10 Number of Household and Distance of Distribution Line From Mabini Rizal Hangi Palanas Tagabiran Dapdap Epaw San Jose Dapdap Dapdap Total To Household Population (house) (people) Rizal Taylor Palanas Rufino Tagan-ayan Epaw San Jose Sag-od San Isidro San Antonio - 48 - 90 140 35 35 60 44 36 33 335 45 853 517 859 164 200 316 259 179 188 1,666 228 4,576 Distance (km) 2.8 2.2 3.0 2.4 3.6 2.4 2.4 3.6 3.4 3.6 29.3 The Long-run Marginal Cost (LRMC) is estimated by the cost at block distance of expansion of distribution line divided by the annual usage of electric power of consumer. Table-5.12 shows the electrification cost of each area by expansion of distribution line. As a result, the electrification cost is estimated to range from 19.8 centavos/kWh to 32.2 centavos/kWh. If the distance of the distribution line is long and the barangay is small, the electrification cost is estimated to be more than 25centavos/kWh. - 49 - Table-5.12 Eenergize Plan up to each Barangay Rizal Taylor Palanas Electrification Cost by Expansion of Distribution Line Rufino Tagan-ayan Epaw San Jose Sag-od San Isidro San Antonio All Area-A Calculation Methodology 90 517 140 859 35 164 35 200 60 316 44 259 36 179 33 188 335 1,666 45 228 853 4,576 (a) (b) Census 2000 data Census 2000 data (kW) (MWh) 17.3 73.8 26.9 114.9 6.7 28.7 6.7 28.7 11.5 49.2 8.4 36.1 6.9 29.5 6.3 27.1 64.3 274.9 8.6 36.9 163.8 699.9 (c) (d) (a)xStandard Barangay Power Demand/100 (a)xStandard Barangay Energy Demand/100x365 (km) (km) (%) (MWh) (MWh) 2.8 29.8 0.13% 73.9 0.1 2.2 31.9 0.22% 115.1 0.3 3.0 29.4 0.05% 28.7 0.0 2.4 31.8 0.05% 28.7 0.0 3.6 31.8 0.09% 49.3 0.0 2.4 36.0 0.08% 36.1 0.0 2.4 38.4 0.07% 29.6 0.0 3.6 42.0 0.07% 27.1 0.0 3.4 37.0 0.61% 276.6 1.7 3.6 37.2 0.08% 37.0 0.0 29.3 34.5 0.31% 702.1 2.2 (e) (f) (g) (h) (i) From Feeder Line Allocation Tabel Distance from Laoang S/S depend on distance & power demand (d)/(1-(g)) (h)-(d) Cost of Dist. Trans. Extension ('000$) Cost of Distribution Lines Extensio('000$) Pole Transformer ('000$) Connecting Line ('000$) Total Construction Cost ('000$) 0.3 22.1 2.3 6.1 30.8 0.4 17.3 3.6 9.5 30.8 0.1 24.0 0.9 2.4 27.4 0.1 19.2 0.9 2.4 22.6 0.2 28.8 1.5 4.1 34.6 0.1 19.2 1.1 3.0 23.4 0.1 19.2 0.9 2.4 22.7 0.1 28.8 0.8 2.2 32.0 1.0 26.9 8.6 22.8 59.2 0.1 28.8 1.2 3.1 33.1 2.5 234.2 21.8 58.0 316.5 (j) (k) ïŒïœïŒ (m) (n) @12$/kVA @8,000$/km @1,600$(15kVA) @85$/Household (j)+(k)+(l)+(m) Annual Cost of Construction. O&M Cost Cost of Loss Energy Total Cost (Annual) ('000$) ('000$) ('000$) ('000$) 3.50 0.46 0.01 3.98 3.50 0.46 0.03 4.00 3.12 0.41 0.00 3.53 2.57 0.34 0.00 2.91 3.94 0.52 0.01 4.46 2.67 0.35 0.00 3.02 2.58 0.34 0.00 2.92 3.64 0.48 0.00 4.12 6.74 0.89 0.21 7.84 3.77 0.50 0.00 4.27 36.0 4.7 0.3 41.1 (o) (p) (q) (r) (n)x annuity 0.114 (25 yrs, 12%) (n)x1.5% (i)x(t) (o)+(p)+(q) Cost of Grid Expansion Cost of Energy Energy Cost by Grid Extension ïŒï¿ /kWh) ïŒï¿ /kWh) ïŒï¿ /kWh) 5.4 17.0 22.4 3.5 17.0 20.5 12.3 17.0 29.3 10.1 17.0 27.1 9.1 17.0 26.1 8.4 17.0 25.4 9.9 17.0 26.9 15.2 17.0 32.2 2.9 17.0 19.8 11.6 17.0 28.6 5.9 17.0 22.9 (s) (t) (u) (r)/((d) Norsamelco Tariff (6.23P/kWh) x Tariff Increase (2.0% annu (s)+(t) Beneficiary Households Beneficiary Population (houses) (people) Power Demand Annual Energy Demand Distance of Feeder Expansion Distance from Laoang S/S Loss rate in Dist. Line Annual Energy to be Transmitted Annual Energy Loss in Dist. Line - 50 - 5.4 Assumption of Electrification Cost by Renewable Energy 5.4.1 Assumption of Electrification Cost by Micro Hydro Power Plant As mentioned in Chapter 2, the electric demand for rural electrification is estimated to have a peak load of 10 kW and a base load of 5kW. If all electric demand is covered only by the micro hydro power plant, an output of 10 kW is needed. If the facility is not used efficiently during peak load, the utilized capacity is estimated to be 46.8%. A potential discharge 0.2m3/s and a head of 7m is essential to cover the output of 10kW generation. On the other hand, if only the base load is to be covered by the micro-hydro power plant, the installation of a plant with an output of 5kW is needed. In this case, the utilized capacity is estimated as 66.5%. A potential discharge 0.1m3/s and a head of 7m is essential to cover the output of 10kW generation. The electrification cost by micro hydro power plant is assumed to consist of the items as follows. 1. Capital cost of installation of Turbine and Generator 2. Capital cost of installation of distribution line (low-voltage distribution system of 240V) 3. Operation and Maintenance cost for Turbine and Generator 4. Cost of operator Where, As for No.1, the cost for Turbine is estimated at USD 8,000 per kW. The annual expense rate of 0.1078 is estimated based on an expected lifetime of 45 years and a discount rate of 12%. As for No.2, the same unit rate is applied with the expansion of distribution line As for No.3, the total annual O&M cost for the Turbine, Generator and distribution facility is assumed to be 1.5% of the construction cost. As for No.4,the remuneration of one operator is assumed to be 4,000peso/month. The Long-run Marginal Cost (LRMC) is estimated by all construction cost of micro hydro power plant divided by the annual usage of electric power of consumer. The - 51 - electrification cost of 27.7centavos/kWh is estimated if the total electric demand of 10kW is covered by the micro hydro power plant. Meanwhile, the electrification cost of 22.1centavos/kWh is estimated if the base load of 5kW is covered by the micro hydro power plant. The details of the hydro power potential from the irrigation canal constructed under HCAAP is described in chapter 6. Accordingly, a potential of 10kW can not be anticipated so that the installation of a 5kW micro hydro power plant is assumed as suitable. Table-5.13 shows the results of the study. - 52 - Table-5.13 Micro Hydro Generation Type Biogas <ALL> (a) Power Plant Output Plant Factor Annual Generation (kW) (%) (MWh) 10.0 46.8% 41.0 Energy Source Current of Irrigation Channel Discharge (m3/s) Head (m) 0.2 7 Initial Construction Turbine & Generator Cost Estimation Distribution Line Connecting Line Total ('000$) ('000$) ('000$) ('000$) Annual Generation Capital Cost Cost Estimation O&M Cost Operator (1 person) Total Generation Cost Comments Electrification Cost by Each Method of Power Generation Generation Cost <Base> (b) <ALL> (c) 5.0 Output 66.5% Plant Factor 29.1 Annual Generation (kW) (%) (MWh) Animal Waste 0.1 Swine 7 Daily Biogas Offtake Heat Value Gas Engine Efficiency 80.0 Rice Hull Combustion (heads) (Nm3) (kcal/m3) (%) 10.0 46.8% 41.0 <Peak> (d) 5.0 Output 27.2% Plant Factor 11.9 Annual Generation 1,800 100 5,000 20% 500 28 5,000 20% Micro Hydro & Biogas <ALL> (e) Rice Hull Harvest Area Annual Available Rice Hull Heat Value Engine Efficiency (kW) (%) (MWh) (ha) (ton/y) (kcal/kg) (%) 10.0 46.8% 41.0 <Hybrid> (b)+(d) 10.0 46.8% 41.0 130 182 3,250 8% ('000$) ('000$) ('000$) ('000$) ('000$) ('000$) 30.0 4.0 8.0 1.2 3.4 46.6 10.0 2.0 5.0 1.2 3.4 21.6 Stirling Eng. & Gen. (3.3 kW x 3units) Rice Hull Storage Distribution Line Connecting Line Total ('000$) 105 1.2 3.4 84.6 40.0 CIGER Gas Holder Gas engine & Generator 1.2 Distribution Line 3.4 Connecting Line 44.6 Total ('000$) ('000$) ('000$) ('000$) 5.0 1.2 3.4 114.6 ('000$) ('000$) ('000$) 9.12 1.27 0.96 4.81 Capital Cost 0.67 O&M Cost 0.96 Operator (2 person) ('000$) ('000$) ('000$) 5.57 0.93 1.92 ('000$) 11.35 6.44 ('000$) 8.42 2.58 Capital Cost 0.43 O&M Cost 1.92 Operator (3 person) Supplemental Fuel 4.93 Total ('000$) ('000$) ('000$) ('000$) ('000$) 13.70 2.29 2.88 0.46 19.33 10.41 (ï¿ /kWh) 27.7 22.1 Generation Cost (ï¿ /kWh) 20.5 41.5 Generation Cost (ï¿ /kWh) 47.1 25.4 - - Total Difficulty of acquiring necessary swine Difficulty of acquiring necessary discharge - 53 - As stirling engine is in the demonstration stage, the generation cost estimation is high. However if the engine cost becomes lower, the generation cost also becomes lower. 50.0 2.0 5.0 1.2 3.4 61.6 7.39 1.10 1.92 5.4.2 Assumption of Electrification Cost by Biogas Energy The system which performs a methane fermentation process using livestock manure from swine, cows, or poultry has been used commercially in the Philippines. These technologies have been used as the technology for livestock manure processing from an environmental impact point of view but marsh gas has also been used effectively from an energy usage point of view. According to DOE officials, large and small processing system of livestock manure has been done in more than 650 places in Philippines. An example of a large case application is at the Maya farm, where electricity is generated by marsh gas from 60,000 hogs in a farm with an area of 40Ha, and is used for light and refrigerator in the enclosure. The usage of simplified digester tanks of concrete is encouraged in case of small scale farming. There have been 9 manufacturers for digester tank of livestock manure processing in the Philippines. In recent years, cases of methane fermentation system with swine manure planned as CDM project have been increasing in the Philippines (Table-5.14). In this case, marsh gas has been processed by CIGAR (Covered In-ground Anaerobic Digester) which was developed by the Bioscience Company. Thus, the system which performs a methane fermentation processing of livestock manure has been used commercially. Swine farming has been a livelihood activity in Catubig (Table-5.15). If the income level of the farm household is increased in association with HCAAP, it is assumed that farm households engaged in swine farming as an auxiliary business will also increase. Thus, biogas generation by livestock manure as renewable energy is studied. Table-5.14 Registered CDM Project by Usage of Biogas in Philippines (Registered CDM Project) Title Host Parties Other Parties Methodology * Reductions ** Ref 30-Oct-06 Gaya Lim Farm Inc. Methane Recovery Philippines United Kingdom of Great Britain and Northern Ireland AMS-III.D. ver. 9 3130 611 28-Oct-06 Uni-Rich Agro-Industrial Corporation Methane Recovery and Electricity Generation Philippines United Kingdom of Great Britain and Northern Ireland AMS-III.D. ver. 9 2929 609 23-Oct-06 Joliza Farms Inc. Methane Recovery Philippines United Kingdom of Great Britain and Northern Ireland AMS-III.D. ver. 9 3656 607 21-Oct-06 Gold Farm Livestocks Corporation Methane Recovery and Electricity Generation Philippines United Kingdom of Great Britain and Northern Ireland AMS-III.D. ver. 9 2929 612 ïŒSource: UNFCCC CDM Project activities http://cdm.unfccc.int/Projects/registered.htmlïŒ - 54 - Table-5.15 Current Situation of Firming of Livestock and Poultry in Catubig (as of 2000) Livestock / Production Number Poultry (heads) (metric tons) Livestock Swine 5,200 6.50 Cattle 150 0.75 Goat 1,000 5.75 Carabao 3,197 15.90 Horse Sheep 20 0.02 Poultry Chicken 11,760 5.80 Duck 500 0.25 Turky 100 0.10 (Source: Materials of Catubig Municiparity) In the case of generating by marsh gas, and similarly as with micro hydro power, biogas generating equipment with an output of 10 kW is needed. In this case, the utilized capacity is estimated as 46.8%. 1,800 hogs, a digester tank with a capacity of 3,600m3 and a biogas volume of 100m3/day is needed for an electric demand of 10 kW. On the other hand, if only the base load is to be covered by the biogas power plant, an installation of only 5kW is needed. The utilized capacity is estimated as 11.9% but if the gas holder uses 500 hogs only, a corresponding smaller biogas digester tank and a biogas volume of 28m3/day is need. The electrification cost by biogas power plant is assumed to consist of the items as follows. 1. Capital cost of biogas transaction equipment (including installation cost) 2. Capital costs of gas engine and generator (including installation cost) 3. Capital cost of installation of distribution line (low-voltage distribution system of 240V) 4. O&M cost of biogas transaction equipment, gas engine, generator and distribution equipment. 5. Cost of operator Where, As for No.1, the construction cost for CIGAR is estimated as 7.4$/m3 and an annual expense rate of 0.1195 is estimated based on an expected lifetime of 20 years and a - 55 - discount rate of 12%. As for No.2, the cost of gas engine and generator is estimated with annual expense rate of 0.1195. As for No.3, the same unit rate is applied with the expansion of the distribution line. As for No.4, the total annual O&M cost of CIGAR, gas engine, generator and distribution equipment is assumed to be 1.5% of the construction cost. As for No.5, the remuneration of two operators is assumed to be 4,000peso per person per month. The Long-run Marginal Cost (LRMC) is estimated by all construction costs`of the biogas power plant divided by the annual usage of electric power of consumers. The electrification cost of 20.5centavos/kWh is estimated if the total electric demand of 10kW is covered by the biogas power plant. Meanwhile, an electrification cost of 41.5centavos/kWh is estimated if the base load of 5kW is covered by the biogas power plant (Table-5.13). As a result of this study, the electrification cost by biogas with a capacity of 10kW is assumed as the same cost as by expansion of distribution line. However, it might be difficult to gather 1,800 hogs for swine farming. 5.4.3 Assumption of Electrification Cost by Rice Chaff Power Plant It is expected that agricultural productivity will increase substantially from rice cropping, from a daily capacity of 1ton/ha to 5ton/ha under HCAAP. As a result of this, rice chaff might be used for generating energy. Even though rice chaff is used for household cooking in the Philippines, there is no experience of large scale usage of rice chaff. According to the DOE, rice chaff power plant is planned in Bulacan province with a capacity of 35MW and in Nueva Ecija province with capacity of 25-30MW. If the study of rice chaff power plant is conducted and existing boiler technology and steam electric generation are used, the scale of generating equipment becomes large. In fact, the capacity of the case example mentioned above is 25-30MW, and operating rice chaff power plant in Thailand is 10-20MW. To install the generating equipment with large capacity, large amounts of rice chaff is needed. However, there is no committed plan of rice chaff collecting system under HCAAP. Thus, in the current situation, rice chaff power is not suitable for rural electrification. - 56 - On the other hand, Stirling engine has been coming up with small size biomass energy using higher efficiency technology. Stiring engine is an external-combustion engine, unlike an internal-combustion engine, and generates power from various external fuel sources such as rubbish timber, biomass, etc.. Even if the technology of internal-combustion engine was invented many years ago, it has not, come into practical use, in the shadow of development of internal combustion power. However, nowadays, the technology of external-combustion engine has come up from the point of view of the efficient use of untouched natural resources and environmental aspects. These days, small type systems with 5 horsepower and capacity output of 3kW (Fig-5.8) have been tested for validation. Since a small size system is suitable for the electrification of small barangays, the feasibility of electrification by using the Stirling engine is studied15. If rice chaff power is generated using a Stirling engine, it becomes advantageous to raise economical efficiency by raising the facility utilization factor. Thus a total of 10kW output may be generated by 3 sets of 3.3kW engines. In this case, the utilization factor is estimated as 46.8%. The specifications of the Stirling engine is shown in Table-5.16. An amount of 180 tons per year of rice chaff is needed to generate 10kW. This amount is equivalent to the amount of rice chaff produced from the farm with an area of 130ha and which is prepared under HCAAP (Table-5.17). Fig-5.8 Outline of 3kW Stirling Engine (ST-5) Biomass Fuel Hopper Controller Fan Combustion Chamber Heater Head ïŒSource: 15 Compressor Generator Boucher of STIRLING ENGINE Co. Ltd.ïŒ Materials and information about stirling engine has been kindly provide by STIRLING ENGINE Co. Ltd. Kanagawa Science Park East Tower 213 3-2-1 Sakado, Takatsu-ku, Kawasaki-city, Japan, 213-0012 http://www.stirling–engine.com - 57 - Table-5.16 Specification of Stirling Engine Specifications of the ST-5 Stirling Engine Engine Type Engine Output Fuels Used External Combustion, Stirling Cycle, Crank Drive 5 Horse power (Shaft), at 650 rpm Wood, Saw dust, Husks, Corn cods, Weeds, Other Agro-byproducts, Natural Gas Fuel Consumption 38 kW of Heat (approximately 10 kg/h of wood) Lubrication Dry bearing; No oil used Working Fluid Air Working Pressure 5 bar, self pressurizing Heater Head temperature 650 â Dimension 49" x 16" x 16" Weight 440 lbs (200kg) (Source: Stirling Engine Co. Ltd) Table-5.17 Assumed Amount of Rice Chaff for Generating Item Rice Productivity Paddy Field Area Rice Production Available RiceHusk Ratio Rice Husk Weight Available Rice Husk Heat Value of RiceHusk Energy Generation Energy Generation ïŒ*) Rainy season 5.0 t/ha, - 58 - Estimation 5.0 t/ha 130 ha 1,140 ton/year (*) 0.8 0.2 kg/kg Rice 180 ton/year 3,250 kcal/kg 41,270 kWh/year 113 kWh/day dry season 3.75 t/ha. The electrification cost by rice chaff power with Stirling engine is assumed to consist of the items as follows. 1. Capital cost of Stirling engine and installation cost 2. Capital cost of construction of storage house for rice chaff 3. Capital cost of installation of distribution line (low-voltage distribution system of 240V) 4. O&M cost of Stirling engine, generator and distribution equipment 5. Cost of operator Where, As for No.1, currently, since stirling engine is under verification test, the commercial price has not been set. Therefore, the cost of $35,000 is used as a provisional value. An annual expense rate of 0.1195 is estimated based on an expected lifetime of 20 years and discount rate of 12%. As for No.2, the cost is estimated to be $5,000 and an annual expense rate of 0.1195 is used similarly as in No.1. As for No.3, the same unit rate is applied with the expansion of distribution line. As for No.4, the total annual O&M cost of Stirling engine, generator and distribution equipment is assumed to be 2.0% of the construction cost. As for No.5, the remuneration of three operators is assumed to be 4,000peso per person per month. The Long-run Marginal Cost (LRMC) is estimated by all construction costs of biogas power plant divided by the annual usage of electric power of consumers. The electrification cost of 47.1centavos/kWh is estimated if the total electric demand of 10kW is covered by the biogas power plant (Table-5.13). This price is estimated to be higher than the cost of expansion of distribution line since the capital cost of Stirling engine is provisional. Meanwhile, the electrification cost of 20centavos/kWh is estimated if the cost of Stirling engine becomes common and consequently attains a lower price such as $10,000. The commercial viability and popularization of Stirling engine is expected since the cost is just the same as the expansion cost of distribution line. - 59 - 5.4.4 Assumption of Electrification Cost by Hybrid Generating System between Micro Hydro Power and Biogas Power As described in Sub clause 4.1 and 4.2, it is not expected that only micro hydro power potential is hard to cover the number of 50 households of standard Barangay. On the other hand, number of the firming swines are also not enough to produce the electricity by Biogas method to cover all households. In consideration of both features, micro hydro is available to operate 24 hours and Biogas is available to stock in Gas holder, hybrid system between a micro hydro power plant for base load and biogas power for peak load is proposed in this study. As a result of this study total construction cost of rural electrification by hybrid generating system between micro hydro power with 5kW and biogas power with 5 kW is estimated to be $61,600. As the method mentioned above indicates that the annual operating and maintenance cost is estimated to be about $10,400. The Long-run Marginal Cost (LRMC) is estimated by all construction costs of the hybrid generating system divided by annual usage of electric power of consumers. The electrification cost of 25.4centavos/kWh is estimated. 5.5 Selection of Candidate Barangays for Electrification by Renewable Energy As mentioned in Chapter 3, the electrification cost for the expansion of distribution line is estimated from 20centavos/kWh to 32centavos/kWh and there are some barangays with costs of more than 25centavos/kWh. On the other hand, the electrification cost by hybrid generating system between micro hydro power and biogas power is estimated as 25centavos/kWh. As a result of this study, seven barangays in Las Navas may possibly adopt the hybrid system as follows. No. 1 2 3 4 5 6 7 Barangay Palanas Rufino Tangan-ayan Epaw San Jose San-od San Antonio Population 164 200 316 259 179 188 228 - 60 - Household 35 35 60 44 36 33 45 Chapter 6 Rural Electrification Plan by Renewable Energy 6.1 Potential of Micro Hydro Power Plant The HCAAP plan consists of constructing three irrigation facilities which include the Catubig service area (3,565.5ha), the Bulao service area (742.2ha) and the Hagbay service area (665.3ha), respectively. The data discharge and head of the water channel, and of the irrigation channel at the Catubig service area were subsequently obtained in this study. Table-6.1 show the potentials for micro hydro power generation at the Catubig service area. As a result of this study, the possibility of micro hydro power generation was found in four barangays, namely, Palanas, Tagan-ayam, Epaw and San Jose. Table-6.1 Potential of Micro Hydro Power at Catubig Service Area Site No. Discharge (m3/s) 1 0.11 2 0.19 3 0.19 4 0.17 5 0.24 6 0.22 7 0.10 8 0.14 6.2 Head (m) 2.6 2.8 1.5 4.5 4.2 2.0 3.0 3.4 Output (kW) 1.7 3.2 1.8 4.3 6.0 2.6 1.8 2.8 Nearest Barangay San Isidro Epaw San Jose Tagan-Ayan Tagan-Ayan Tagan-Ayan Palanas Rizal Hybrid Power Generation Plan at Barangays The respective electric power demand in each of the four barangays, namely, Palanas, Tagan-ayan, Epaw and San Jose is shown under the Demand side column of Table-6.2. The possible supply sources, on the other hand, and in case that power is provided for by Micro hydro power and Biogas power, is shown under the Supply side column of Table-6.2. In Palanas, a barangay peak demand of 6.7kW and an electric energy demand of 78.7kWh per day are anticipated. These requirements can be met by hybrid power generation, which consists of constructing a 1.8kW micro hydro power facility along the No.7 water channel for base load, and a supplemental 4.9kW biogas power facility, for covering the shortfall. In this instance, a total of about 540 farmed swine (about 15 swine per stand alone) and the installation of a CIGER digester chamber with a volume of 1,100m3 shall be needed. - 61 - In barangay Tagan-ayan, the expected peak demand of 11.5kW and an electric energy demand of 134.9kWh per day are anticipated. The expected demand can likewise be met through hybrid power generation, which consists of constructing a 6.0kW micro hydro power plant along the No.5 water channel for base load, and an additional biogas power facility with a capacity of 5.5kW, to cover for the shortfall. About 600 farmed swine (about 10 swine per stand alone) and the installation of a CIGER digester chamber of 1,200m3 shall be needed. In barangay Epaw, the daily peak demand is expected to reach 8.4kW with a corresponding electric energy demand of 98.9kWh. Hybrid power generation, consisting of a 3.2kW micro hydro power facility along the No.2 water channel for base load, and a 5.2kW biogas power structure for covering the shortfall, are necessary. These will require getting manure from about 440 farmed swine (about 10 swine per stand alone) and installing a CIGER digester chamber with a volume of 900m3. In barangay San Jose, a peak demand of 6.9kW and electric energy demand of 80.9kWh per day is anticipated. Once again, a hybrid power generation consisting of a 1.8kW micro hydro power facility along the No.3 water channel for base load, and a biogas power structure with a capacity of 5.1kW for covering the shortfall, are needed. Considering the requirements, manure from about 580 farmed swine (about 16 swine per stand alone) and the installation of a CIGER digester chamber with a volume of 1,200m3 are needed. 6.3 Micro Hydro Power Plant 6.3.1 Turbine for micro hydro power With the micro hydro power turbine, which is applied to micro hydro power stations of less than 100kW, more emphasis is placed on low cost and ease of inspection and maintenance rather than on turbine efficiency. The Pelton turbine, Francis turbine and S-type tubular turbine, which are also widely used for small and micro hydro power, and only the types particular to micro hydro power are described below. The cross-flow turbine is used for relatively small flow with a head of 5 to 100m. The runner is a cylindrical cage type with 20 to 30 arc shaped blades. One guide vane is divided into two parts which are arranged axially. It maintains high efficiency in a wide load range as the guide vanes are switched according to the load. - 62 - The rim-generator unit has the generator rotor installed on the circumference of the runner blade and the generator and turbine are integrated into one piece. The turgo impulse turbine is applied to the intermediate specific speed between the Pelton turbine and Francis turbine. This is an old model dating from 1920’s but is now being reconsidered for small hydro power applications. Fig-6.1 shows various types of micro hydro power turbine. Fig-6.1 Micro Hydro Power Turbine Types - 63 - 6.3.2 Selection of type of turbine The turbine type is selected on the basis of the effective head and turbine discharge, while considering such factors as river flow, operation of the reservoir and regulating pondage. When two or more turbine types are possible, they are determined by comprehensively studying their cost efficiency, maintainability, etc. Various turbines have limitation on their respective head and applicable specific speed. The application range is determined by their adaptability to the head variation, characteristic, strength against cavitation, etc. Turbine Selection Diagram is shown in Fig-6.2. Effective Head ïŒïœïŒ 1000 1000 Pelton Turbine Horizontal Francis Turbine Turgo Impulse Turbine Vertical Francis Turbine 100 100 Kaplan Turbine 10 10 Reversible pump Turbine Cross-Flow Turbine S-type Tubular Turbine Submerged pump Turbine Propeller Turbine Propeller Turbine(Siphon) 1 0.01 1 0.1 1 10 100 Maximum Discharge ïŒïœ 3 /sïŒ Fig-6.2 Turbine Selection Diagram For the type of turbine, Propeller turbine was found to be appropriate in view of the flow (0.1-0.24m3/s) and effective head (1.5-4.5m) relationship based on the turbine selection diagram given in Fig-6.2. Thus Propeller turbine was selected for its high efficiency and proven performance. - 64 - Table-6.2 Basic Specification of Hybrid Power Generating at Each Barangay Demand Side Barangay Palanas Tagan-ayan Epaw San Jose Supply Side Hydro Energy Daily Base Biogas Micro Hydro Site production by Energy Generation Potential No. Micro Hydro Demand Household s Peak Demand Base Demand Daily Energy Demand (house) (a) (kW) (b) (kW) (c) (kWh) (d) (kWh) (e) (kW) (f) 35 60 44 36 6.7 11.5 8.4 6.9 3.5 6.0 4.4 3.6 78.7 134.9 98.9 80.9 55.9 95.8 70.2 57.5 1.8 6.0 3.2 1.8 7 5 2 3 Energy Necessary Capacity of Production No. of Swine Digester by Biogas (kWh) (g) (kW) (h)=(b)-(f) (kWh) (i)=(d)-(g) (Head) (j) (m3) (k) 43.2 95.8 70.2 43.2 4.9 5.5 5.2 5.1 35.5 39.1 28.7 37.7 540 600 440 580 1,100 1,200 900 1,200 Note 1. Peak demand (b) is calculated by 9.6kW x (Households No./ 50) 2. Base demand (c) is calculated by 5.0kW x (Households No./ 50) 3. Daily energy demand (d) is calculated by 112.4 kWh x (Households No./ 50) 4. Daily base energy demand (e) is calculated by 79.8 kWh x (Households No./ 50) 5. Energy production by Micro hydro (g) is smaller number of either micro hydro potential (f) x 24h or daily base energy demand (e). 6. Biogas generation (h) is the balance of peak demand (b) and Micro hydro potential (f). 7. Energy production by biogas (i) is the balance of daily energy demand (d) and energy production by micro hydro (g). 8. Necessary No. of swine (j) is calculated by energy production by biogas (i) divided by 6.54 kWh/day/100 swine head. 9. Capacity of digester (k) is calculated by energy production by biogas (i) multipled by 31.0 m3/kWh/day. - 65 - 6.4 Biogas Power Plant As already mentioned, the CIGER (Covered In-ground Anaerobic Digester) method, which is more common in the Philippines and which was developed by the Philippine Bioscience Company, is considered for the biogas power plant plan. In order to protect the penetration of digestive juice to the ground and the emission of produced gas to the air, the chamber is covered with a 1mm-thick, high density polyethylene (HDPE) liner. The waste material of the farm animal is stocked in the digester chamber for at least 30 days. Then, the organic matter is broken down by bacteria, so that biogas, including methane, is produced. This gives a BOD of more than 90% and a COD of more than 80% which account for the density of methane becoming more than 65%. On the other hand, bacillus withers away in a temperature condition of more than 35 degrees. ïŒSource: UNFCCC CDM Project Activity, Gaya Lim Farm Inc. Methane Recovery project PDD p.5ïŒ The biogas generating system with a CIGER chamber is being constructed by the Sorosoro Ibaba Development Cooperative (SIDC) in Batangas province. The SIDC was established in 1969 as a cooperative and as of the end of 2005, the cooperative had full category members totaling 3,834 and supporting members numbering 4,976. The activities of SIDC include stock growing, distribution, rice milling and sales of goods. SIDC also consistently maintains a swine population of approximately 30,000 throughout the year. Two years ago, SIDC started the study of fermentative treatment with swine’s manure, from an environmental perspective and considering digestive gas and usage of organic manure. At present, a big gas power generation system is being constructed with funding support from the British government. This system covers the following processes: manure is produced from 8,000 swine; the manure is digested in the CIGER chamber (30m x 90m x depth of 6m), where - 66 - biogas with an average daily volume of 400-500m3 is produced; the gas is collected in the tank to generate 75kw of electricity; and the electricity is distributed to the office building of SIDC and some households in the vicinity. The generating system will be completed by 2007. The swine manure is gathered automatically using a drain system. The total construction cost of 6 million pesos is broken down as: 4 million pesos for the digester chamber, and 2 million pesos for construction. The generator is procured from the United States of America with a price of 1.3 million per set. The generated electricity is distributed to some households (50-100 households, 200-300 residents) in the barangay. At the moment, electricity is being distributed by MERALCO. However, a reduction in electricity tariff is expected with the potential use of biogas power. Aside from swine, manure from poultry and cows may additionally be considered. For instance, chicken manure produces biogas more efficiently than manure from swine. However, due to the local dry conditions, manure from poultry has been utilized better as fertilizer on commercial basis, than for energy use. Therefore, manure of swine is still the most efficient fuel source for biogas energy in the Philippines. Considering the specifications of SIDC’s system, manure from 500 swine and a biogas digester chamber with a volume of 1,010m3 shall be needed to generate an output of 5kW. These are expected to result in the production of 28m3 of biogas per day and the generation of about 32.7kWh of electric energy. Table-6.4 shows that comparison of biogas generation in Philippines and Japan. Table-6.3 Basic Specification of Biogas Power Generation Item Swine number Biogas Production Heat Value of Biogas Daily Energy of Biogas Output Power Generation Hour per day Energy Prod. by Swine No. Capacity of Digester Digester cap. by Energy prod Estimation 500 head 28 m3/day 5,000 kcal/m3 32.7 kWh/day 5 kW 6.5 hours 6.5 kWh/day/100head 1,010 m3 31.0 m3/kWh/day - 67 - Table-6.4 Comparison of Biogas Generating in Philippines and Japan Item Bio Materials Animal Waste Digester Type Capacity Daily Biogas Offtake Heat value Gas Holder Capacity Engine Capacity SIDC Cooperative (Philippines) Yagi Bio-Ecology Center (Japan) Swine 8,000 (heads) Cow, Swine etc. 86 (t/day) CIGER 16,200 m3 30m×90m×6m(D) 450 m3 around 5,000 kcal/m3 (Methane content 65%) ïŒïŒ¡ 2,100 m3 14mφ×17.7m(H) 2,120 m3 4,780 kcal/m3 500 m3 unknown 220 kW 75kW×2 80kW×1 28.1% 3,500 kWh 75 kW Heat Efficiency Daily Electricity Generation unknown Project Cost Digester Gas Engine Total 6.0 million Peso 1.3 million Peso 7.3 million Peso 1,048 million Yen Source Hearing at SIDC (Note: CIGER;Covered in ground anaerobic reactorïŒ Fig-6.3 350 m3 Broacher of the Center Biogas Generating System Pigpen Gas Holder CIGER Electricity Gas Engine & Generator - 68 - Chapter 7 Profile of the Project Profile for Rural Electrification Program by Renewable Energy in The Mountainous Region of Northern Samar 1. Sector 2. Project site Energy Catubig and Las Navas Province, Mountainous Region in Northern Samar, Philippines, 3. Agency in charge of implementation Philippine National Oil Corporation ;PNOC 4. Background and Purpose The Northern Samar province in the Eastern Visayas region, which is the study area for this feasibility study on rural electrification, is one of the underdeveloped areas in the Philippines. Its per capita income level is less than 50% of the average per capita income level in the Philippines. Since the electrification rate of households in the northern mountainous area is only less than 20%, it has targeted to increase the electrification rate in order to boost the growth of agricultural activity and the development of the tourism industry. This study covers the feasibility of rural electrification by renewable energy, such as micro hydro power supplied from the potential of the Catubig River and irrigation facilities and biomass power energy supplied from agricultural products. The increase in agricultural products is an expected outcome of the Exclusive Agricultural Development Project in the Catubig watershed area. 5. Outline of Project (1) Name ; Rural Electrification Program by Renewable Energy (2) Maximum Output Generated by Hybrid Power System Palanas barangay: P=6.7kW (Micro Hydro: 1.8kW, Biogas: 4.9kW) Tagan-ayan barangay: P=11.5kW (Micro Hydro: 6.0kW, Biogas: 5.5kW) Epaw barangay: P=8.4kW (Micro Hydro: 3.2kW, Biogas: 5.2kW) San Jose barangay: P=6.9kW (Micro Hydro: 1.8kW, Biogas: 5.1kW) 6. Project implementation term F/S to completion of construction ; approx two yearsïŒConstruction period : a half yearïŒ 7. Expected benefit and beneficiary Beneficiary ; Local residents Benefits ; Efficient use of Livestock Manure, Employment effect brought by construction, Development of local industry after electrification, Reduce poverty by productivity improvement 8. Expected influence to environment 9. Expected cost Almost no influence About 0.5million dollars - 69 - - 70 - Appendix 1 Schedule for Field Investigation - 71 - - 72 - Schedule for Field Investigation (1st Field Investigation) Days Night 1 2 3 Date Week 1 2006.10.10 Tue From (Via) Fukuoka By To Air Manila Departure Meeting with West Jec Resident Coordinator Manila Meeting with DOE Energy Utilization Management Bereau Director Meeting with PNOC-EDC Engineering Design and Construction Department Manila Meeting with NIA Design and Specfications Department Office-in-Charge Data collection at Bureau of Agricultural Statistics Data collection at National Statistic Office Manila Meeting with DOE Energy Utilization Management Bureau (JICA Experts) Meeting with PNOC-EDC Assistant to the President Meeting with PNOC-EDC Engineering Design and Construction Department 2 2006.10.11 Wed 3 2006.10.12 Thu 4 4 2006.10.13 Fri 5 5 2006.10.14 Sat Manila Air Fukuoka - 73 - Activities Arrival Schedule for Field Investigation (2nd Field Investigation) Days Night 1 2 3 4 5 6 7 Date Week 1 2006.12.03 Sun From (Via) Fukuoka By To Air Manila Departure Meeting with West Jec Resident Coordinator Manila Meeting with DOE Energy Utilization Management Bureau Director Meeting with NIA Design and Specfications Department Office-in-Charge Meeting with NPC-SPUG Vice President 2 2006.12.04 Mon 3 2006.12.05 Tue Manila Air 4 2006.12.06 Wed Catarman Meeting with NIA Catubig Agricultural Project Office Meeting with Las Navas LGU Office Survey for Catubig irrigation dam site Survey for Pinipisakan Fall Survey for Energized Barangay (Dapdap) Survey for Unenergized Barangay (Epaw) Catarman Meeting with NIA Catubig Field Office Meeting with Catubig LGU Office Survey for Lawaan Substation (NORSAMELCO) Meeting with NIA Catubig Consultant Office Meeting with NORSAMELCO Meeting with Eastern Philippines University Catarman Air Manila Manila Car Batangas 5 2006.12.07 Thu 6 2006.12.08 7 2006.12.09 Fri Activities Batangas Car Manila Manila Car Laguna Laguna Car Manila Sat Meeting with DOE Electric Power Industry Management Bureau Director Meeting with DOE Rural Electrification Adm. & Mgt. Division Meeting with PNOC-EDCEngineering Design, Procurement & Construction Department Meeting with NIA Administrator Meeting with Sorosoro Ibaba Development Cooperative Survey for Biomass Powerstation site (Under construction) Data collection at National Statistic Office Survey for Balugbog Hydropower Plant Meeting with Philippine Power and Development Corporation Survey for Villa Escudero Hydropower Plant 8 8 2006.12.10 Sun Manila Making for field investigation report Collection data arrangement 9 9 2006.12.11 Mon Manila Meeting with EDCOP (Philippine consultant) Meeting with JBIC Manila Meeting with DOE Energy Utilization Management Bureau (JICA Experts) 10 2006.12.12 Tue Manila Air Fukuoka - 74 - Arrival - 75 - Appendix 2 Interviewed Persons List - 76 - Interviewed Persons List (No.1) Name Post Position Dr.Guillermo R. Balce Department of Energy Undersecretary Mr. Mario C. Marasigan Ditto Mr. Ronnie N. Sargento Ditto Ms.Mylene Capongcol Ditto Ms.Marissa Mariano Ditto Mr.Sherwin Adeva Ditto Mr.Elmer Casao Ditto Mr.Rodel Padrique Ditto Mr. Lorenzo S. Marcelo National Power Corporation Vice President(Small Power Utilities Group) Mr. Noel D. Salonga PNOC Energy Development Corporation Assistant to the President Energy Utilization Management Bureau Director, Officer-in-Charge Renewable Energy Management Division Officer in charge Electric Power Industry Management Bureau Director Electric Power Industry Management Bureau Senior Science Research Specialist Electric Power Industry Management Bureau Senior Science Research Specialist Electric Power Industry Management Bureau Science Research Specialist Electric Power Industry Management Bureau World bank consaultant on rural power project Engineering Design Procurement and Construction Department Manager Construction Department Superintendent Corporate Plannung Manager Mr. Martin Jude Lacambra Ditto Mr. Ronnie Andador Ditto Mr. Erudito S. Recio Ditto Mr.Danilo H. Cruz Ditto Process Design Supervisor Mr.Arturo C. Lomibao National Irrigation Administration Administrator Mr. Rodolfo D. Gales Ditto Ms. Proserpina Mariano Ditto Mr.Reinerio E. Irinco Ditto Project Manager(HCAAP-IDC) Mr.Prisco Buco Ditto Project Engineer(HCAAP-IDC) Mr.Abner Morales Ditto Project Engineer(HCAAP-IDC, Catubig) Mr.Romualdo Saises Las Navas LGU Municipal Engineer Dr.Felipe Gavino Las Navas LGU Municipal Engineer Mr.Antonio Adella Catubig LGU Planning Officer Mr.Lidany Cornillez University of Eastern Philippines Engineer Design and Specifications Department Office-in-Charge Design and Specifications Department Senior Engineer - 77 - Interviewed Persons List (No.2) Name Post Position Mr.Henry Banjawan Northern Samar Electric Cooperative, Inc. Engineer Mr.Roy Sosa Ditto Engineer Mr.Rico B. Geron Sorosoro Ibaba Development Cooperative General Manager Ms.Marife Dimaano Ditto Executive Assistant Mr.Ramon Achacoso Mr.jaime Iporac Mr.Hiroshi Togo Philippine Power and Development Corporation Villa Escudero Hydro Power Station Japan Bank for International Cooperation General Manager Engineer Chief Representative in Manila Mr. Jun Tamakawa Department of Energy Energy Utilization Management Bureau JICA expert (Tokyo Electric Power Company) Mr.Jose U. Jovellanos Engineering and Development Corporation of the Philippines Chairman Mr.Restituto A. Arbolente Ditto Vice President(Power & Industrial) Mr.Wilfredo A. Osabel Ditto Vice President(Agri-Infrastructure) Mr.Teofilo Malicse Ditto NIA HCAAP Engineer Mr.Ben Ibuna, Jr Ditto NIA HCAAP Engineer - 78 - - 79 - Appendix 3 Photos - 80 - Boatslip of Catubig Boatslip of Catubig River Condition of Catubig River (Downstream) River Condition of Catubig River (Downstream) River Condition of Catubig River (Upstream) River Condition of Catubig River (Upstream) - 81 - Intake Dam Site (JBIC Catubig Agricultural Advancement Project) Upstream of Intake Dam Intake Site Unenergized Barangay (Right side of Intake Dam) Unenergized Barangay (Right side of Intake Dam) - 82 - Pinipisakan Falls (Downstream of Intake Dam site) Pinipisakan Falls (Downstream of Intake Dam site) Downstream of Pinipisakan Falls Boatslip of Pinipisakan falls Rest Area of Pinipisakan Falls - 83 - Las Navas LGU Office Las Navas Town Energized Barangay (Dapdap) Energized Barangay (Dapdap) Energized Barangay (Dapdap) Rice mill (Dapdap) - 84 - Unenergized Barangay (Epaw) Unenergized Barangay (Epaw) Diesel generator 3kW (Epaw) Diesel generator 3kW (Epaw) University of Eastern Philippines (Catubig) Old Church (Catubig) - 85 - NORSAMELCO Substation (Catubig) NORSAMELCO Substation (Catubig) Biogas Powerstation of Under construction (SIDC) Pig Farm (SIDC) Covered In-ground Anaerobic Digeter of Under construction (SIDC) - 86 - ãã£ãªãã³åœãµããŒã«å³¶åéšå±±éå°åã«ããã åçå¯èœãšãã«ã®ãŒã«ããå°æ¹é»åä¿é²èšç»å¯èœæ§èª¿æ» åæèŠçŽ - 87 - - 88 - ïŒ. èæ¯ãšç®ç ãã£ãªãã³åœã«ãããŠã¯ãå°æ¹é»åã¯è²§å°æ²æ» ã«ã€ãªãã人éç掻ã®è³ªçåäžã«å¯äžã ããããæ¿åºã®æéèŠæ¿çã®äžã€ãšã㊠2008 幎ã®ãã©ã³ã¬ã€ïŒæèœïŒé»åç 100ïŒ ãç®æš ã«å°æ¹é»åãæšé²ããŠãããšããã§ããã ãã£ãªãã³ã§ã¯ã人å£ã®çŽïŒå²ãå ãã貧å°å±€ã®çŽïŒåã®ïŒãå°æ¹éšã®èŸ²æ°ã»æŒæ°ã§ã ããšèšãããŠããããããã£ãŠãå°æ¹é»åã®å®çŸã¯èŸ²æéšã§ã®è²§å°è»œæžãéœåžéšãšå°æ¹èŸ² æéšã®æ Œå·®æ¯æ£ãªã©èŸ²æå°åã«ãããäœæ°ã®ç掻氎æºåäžãæ°ããåå ¥æºã®åµé ãçã¿åº ããã®ãšæåŸ ãããŠããã ä»åãå°æ¹é»å調æ»ã®å¯Ÿè±¡ãšãããã£ãªãã³äžéšããµã€ã¹å°æ¹ãµããŒã«å³¶ã®åãµããŒã« å·ã¯ããã£ãªãã³ã®äžã§ããçµæžã»ç€ŸäŒéçºã®æãé ããå°åã®äžã€ã§ããïŒãã£ãªãã³ å šïŒïŒå·ã®ãã¡çŽïŒïŒãæ°ãã貧å°å·ã®äžã€ïŒ ãäœæ°äžäººåœããã®æåŸæ°Žæºãå šåœå¹³åã®ïŒ å²æªæºãšãªã£ãŠããããŸããåéšå±±éå°åã¯ãäžåž¯æ°ããèŠãé»åç㯠20%以äžã§ãã£ãªã ã³ã®äžã§ãæãéçºãé ããŠããå°åã§ãããããåçå¯èœãšãã«ã®ãŒãå©çšããå°æ¹é» åãå³ãã蟲æ¥çç£ã®æ¡å€§ã芳å ç£æ¥ã®çºå±ãç®æããŠããã åå·ã®ç£æ¥ã¯èŸ²æ¥ãäž»äœã§ãããç±³ããšããããããã³ã³ããããããããã£ããµã㪠ã©ãäž»ãªåç©«ç©ã§ããããããã蟲æ¥ãäž»ãªåå ¥æºã§ããã«ãããããããç±³ã®å·å èªçµŠ ãéæãããŠããããè¿é£ã®ã¬ã€ãå·çããã®ç§»å ¥ã«é Œã£ãŠããç¶æ³ã§ããããŸããææ°Ž ç¶æ³ãæªãããäœæ°ãäœè¡åžè«ç ã«ããããªã©ãå£æªãªä¿å¥è¡çç¶æ ãéçºã®åŠšããšãªã£ ãŠãããããã«ãåœå°åã®éè·¯ã¯æªèè£ ã®ããéšå£ã«æ°Žæ²¡ãããªã©ã»ãšãã©éè¡ãåºæ¥ãã 蟲ç£ç©ãåžå Žã«éæ¬ããããšããŸãŸãªãããåå ¥ç¢ºä¿ã®éãŸã§éããããŠããç¶æ³ã§ããã ãã®ãããªç¶æ³ã®ããšãåœéååéè¡ã¯åãµããŒã«å·ã«ãã¥ããã°å·æµåã®ã«ãã¥ãã ã°çºãã©ã¹ããã¹çºã«ãããŠãããã£ãªãã³ã«ãã¥ããã°èŸ²æ¥ç·åéçºäºæ¥ããåå欟äºæ¥ ãšããŠæ¯æŽããããšãšãªã£ããæ¬äºæ¥ã¯ãããããæœèšãäžå¿ãšãã蟲æåºç€æŽåãè¡ã ããšã«ãããåå°åã«ãããç±³ãäžå¿ãšãã蟲æ¥çç£æ§ã®åäžãšèŸ²ç£ç©ã®å¢ç£ãå³ããã² ããŠã¯å°å蟲æ°ã®æåŸåäžãä¿å¥ã»è¡çç¶æ ã®æ¹åã«å¯äžããããšãç®çãšãããã®ã§ã ããæ¬äºæ¥ã¯ä»å¹ŽåºŠçæãã 2008 幎ã«å®æããèŠèŸŒã¿ã§ããããäºæ¥ã®é²æã«ãããã£ãŠ åºç€ã€ã³ãã©ã®æŽåãé²ã¿ãããã«ã¯è²§å°å±€ã®ç掻ã®è³ªçåäžãèŠèŸŒãŸããããããã㫠䌎ãé»åã®ä¿é²ãæãŸããŠãããšããã§ããã æ¬èª¿æ»ã§ã¯ããã£ãªãã³åœãµããŒã«å³¶åéšãæµããã«ãã¥ããã°å·ïŒCatubig RiverïŒæµ åã®æªé»åæèœå°åã«ãããŠãåçå¯èœãšãã«ã®ãŒãç¹ã«åæ²³å·ãããããæœèšãæã€æ°Ž åçºé»ããã³ã·ã£ã«åã³åœå°åã§å®æœããã蟲æ¥ç·åéçºäºæ¥ã«ãã蟲ç£ç©ã®å¢ç£ã«äŒŽã£ ãŠçºçãããšãã«ã®ãŒã§ãããã€ãªãã¹ãå©çšããå°æ¹é»åãããžã§ã¯ãã®ä¿é²å¯èœæ§æ€ èšãè¡ããã®ã§ããã - 89 - ïŒ. åçå¯èœãšãã«ã®ãŒéçºãšå°åç€ŸäŒ 2.1 ãã£ãªãã³ã®çµæžçºå±ãšãšãã«ã®ãŒ ãã£ãªãã³ã«ãããŠã¯ãä»åŸ 3 幎é㧠5.5ïŒ ã®çµæžæé·ãèŠèŸŒãŸããŠããããšãã«ã®ãŒã¯ åœã®çµæžçºå±ã«äžå¯æ¬ ãªèŠçŽ ãšããŠä»åŸã®æ¹çãæ€èšãããŠããã 2006 幎ã®ãã£ãªãã³ãšãã«ã®ãŒãã©ã³ã§ã¯ãèŒžå ¥åç³çæäŸååãšãã«ã®ãŒæ§é ããã® è±åŽãä¿é²ããããã2010 幎ãŸã§ã«ãšãã«ã®ãŒèªçµŠçã 60ïŒ ãšããããšãç®æšãšããŠããã ãŸããç°å¢è² è·ã®å°ãªãåœç£ãšãã«ã®ãŒã®éçºãšå©çšãç©æ¥µçã«æšé²ããŠãããç¹ã«åæ²¹ äŸ¡æ Œãé«éš°ããŠããçŸåšã®ç¶æ³ãèæ ®ã®ããåçå¯èœãšãã«ã®ãŒã«ããé»æºéçºãäžèšã« 瀺ãåœã®éèŠãªãšãã«ã®ãŒæ¿çãšããŠäœçœ®ã¥ããŠããã ã»äžçã§äžçªã®å°ç±ãšãã«ã®ãŒéçºåœã«ãªãããšã ã»2013 幎ãŸã§ã«æ°Žåãšãã«ã®ãŒéçºéã 2 åã«ããããšã ã»æ±åã¢ãžã¢ã§äžçªã®é¢šåãšãã«ã®ãŒéçºåœã«ãªãããšã ã»æ±åã¢ãžã¢ã«ããããœãŒã©ãŒèšå補äœã®æ ç¹ãšãªãããšã ã»ãã€ãªãã¹ã倪éœå ãæµ·æŽãšãã«ã®ãŒã®æ¡å€§ãå³ãããšã 2.2 ãã£ãªãã³ã®åçå¯èœãšãã«ã®ãŒéçº ãã£ãªãã³åœå ã®åçå¯èœãšãã«ã®ãŒã®éçºã¯ãçŸåšç©æ¥µçã«é²ããããŠããå°æ¹é»å ããã°ã©ã ã®äžã§ãªãã°ãªããé»æºãæŽã«ã¯ç°å¢ä¿è·é¢ããç°å¢è² è·ã®å°ãªãé»æºãšã㊠éèŠãªäœçœ®ä»ããšãªã£ãŠãããç¹ã«ä»åŸã¯æ°Žåãå°ç±ããã€ãªãã¹ã倪éœå ã颚åãªã©ã äžå¿ã«ç©æ¥µçã«å°å ¥ãããèšç»ãšãªã£ãŠããã (1) æ°Žå ãã£ãªãã³ã®æ°Žåçºé»æœèšã¯åœå®¶ã®é»å系統㫠3,219MW ã®é»åãäŸçµŠããŠãããæ°Žåçº é»ã¯ãä¿¡é Œã§ããé»åäŸçµŠæºã§ãããåœã®é»åéèŠã«å¯Ÿãããªãã®è²¢ç®ãããŠããŠããã ãã£ãªãã³ãšãã«ã®ãŒãã©ã³ã§ã¯ãäžè¡šã«ç€ºãããã« 2014 幎ãŸã§ã« 780MW ã®æ°ããªéçº ãè¡ãé»åäŸçµŠéã 3,991MW ã«ããç®æšãæ²ããŠããã è¡š−1 æ°Žåçºé»éçºç®æš 2005 (MW ) 2006 2010 2014 3,219.1 3,219.1 3,219.1 3,991.1 2,209.8 2,209.8 2,209.8 2,509.8 11.61 11.61 11.61 61.61 997.65 997.65 997.65 1,427.65 8,374 8,563 12,996 14,741 4,422 4,611 8,896 8,819 35 35 35 188 Mindanao 3,917 3,917 4,065 5,734 ç·èŒžå ¥ç³æ²¹ç䟡æç®é 14.44 14.76 22.41 25.42 èšå容é Luzon Visayas Mindanao (GWh) çºé»é Luzon Visayas (in MMBFOE) - 90 - (2) ãã€ãªãã¹ ãã€ãªãã¹ãšãã«ã®ãŒã®éçºãæåŸ ãããŠããããšãã«ã®ãŒçã¯åœå šäœã§ç³æ²¹æç®ã«ã ㊠250 çŸäžãã¬ã«ã®ããã³ã·ã£ã«ããããšæšå®ããŠããã æ¢åãã€ãªãã¹çºé»èšå容é㯠235.7MW ã§ãã®ãã¡è¥¿ããµã€ã¹å°æ¹ã 127.8MW ãå ã㊠ãããçŸåšããã°ãã¹å³¶ã® 2 ç®æ㧠30MW ãš 50MW ã®ãã€ãªãšãã«ã®ãŒçºé»æã建èšäžã§ã ãã4 ç®æã®ãããžã§ã¯ããé²è¡äžã§ããã (3) 倪éœå ãã£ãªãã³ã¯èµ€éã«è¿ãããšããå šåœçã«å€ªéœãšãã«ã®ãŒã®æœåšéã¯å€§ããã ãã£ãªãã³æ¿åºã¯ã倪éœãšãã«ã®ãŒæè¡ãµããŒããããžã§ã¯ããšããŠãçŽ 80 ã®èŸ²æ¥çµå çµç¹ã«ãœãŒã©ãŒã·ã¹ãã ãèšçœ®ããããšãšããŠãããçŸåš 154 ã®ãã©ã³ã¬ã€ã§ 5,600 ç®æ ã®å€ªéœå çºé»èšåãèšçœ®ãããŠããããŸããç°å¢æ¹åãããžã§ã¯ããšããŠãšãã«ã®ãŒçãš PNOC ãå ±åããŠã«ãœã³å³¶åéšã³ã«ãã£ãªã¢å°åãšãã³ãããªå³¶ã«ãããŠãœãŒã©ãŒãã€ã㪠ããã·ã¹ãã ã®å°å ¥ãé²ããŠãããšããã§ããã (4) 颚å ãã£ãªãã³ã§ã®é¢šåéçºææå°åã¯ä»¥äžã«ç€ºããšããã§ããã ã»åéšã«ãœã³ã®ãã¿ãã¹ãããã€ã³è«žå³¶ ã»ã«ãœã³å³¶åæ±ç«¯ ã»ã«ãœã³ããã³ããããµããŒã«ãã¬ã€ããããã€ããã°ãã¹ãã»ãããã©ã¯ã³ã®å éžå±±å²³éš ã»åéšã«ãœã³ããåéšãµããŒã«ã®æ±æµ·å²ž ã»ã«ãœã³å³¶ãšãã³ãã島ã®é ã»ãã³ãã島ãšããã€å³¶ã®é ãã£ãªãã³ã§æåã®å€§èŠæš¡é¢šåçºé»æïŒ25MWïŒã¯ãåéšã«ãœã³å³¶ã€ãã³ã¹ãã«ãã§éçº ãããããã®åŸ 2004 幎ã«ã¯ 16 ç®æã§åèš 345MW ã®é¢šåçºé»éçºãèšç»ãããããŸããæ è¿ã§ã¯ 19 ç®æã§åèš 3,270MW ã®éçºãèšç»ãããŠããã 2.3 æ¿åºã®æ¿çãšããã°ã©ã ãã£ãªãã³åœã«ãããåçå¯èœãšãã«ã®ãŒã®ç©æ¥µçãªéçºã¯ããã£ãªãã³æ¿åºããšãã« ã®ãŒèªçµŠã®ããã«éæããªããã°ãªããªãéèŠãªæŠç¥ã§ãããè¿å¹Žãé»æºæ§æã«ãããå° ç±ãšæ°Žåçºé»ã®ç¢ºå®ãªå¢å ã¯ãèŒžå ¥çæãžã®äŸåãæžå°ãããŠãããæ¿åºã®å°æ¹é»åæœç ã«ãããŠãããœãŒã©ãŒããã€ã¯ãæ°Žåã颚åããã€ãªãã¹çºé»ã¯åçå¯èœãšãã«ã®ãŒè³æº ãšããŠå©çšãæ¡å€§ãããŠããããã®ããã«åªããç¹åŸŽãæã€åçå¯èœãšãã«ã®ãŒãæç¶å¯ èœãªã·ã¹ãã ã«ç§»è¡ããããšãåºæ¥ãããä¿é²ããããšã¯éèŠãªæ¿åºã®æ¿çãšãªã£ãŠããã æ¿åºã¯ãã®ãããªèæ¯ã®ããšããåçå¯èœãšãã«ã®ãŒè³æºéçºãå©çšãåæ¥åä¿é²æ³æ¡ã ã®äžé¢è°äŒééã匷åã«é²ããŠãããåœéåžå Žã§ã®äŸ¡æ Œå€åãçµæžã«åœ±é¿ãäžããªããã¡ ã«ãšãã«ã®ãŒã·ã¹ãã ã«ãããèŒžå ¥çæãžã®äŸåãæžããããã«ãåçå¯èœãšãã«ã®ãŒé çºãæšé²ããç®çã§ãã®æ³æ¡ã®ææ¡ãè¡ãçŸåšäžäžé¢ã§åè°ããŠãããšããã§ããããã® æ³æ¡ã®æç«ã«ããã¯åçå¯èœãšãã«ã®ãŒã®äœ¿çšãå¢å ããããšã¯ç¢ºå®ã§ãããåæ§ã«æè¿ å®æœãããæ¹æ£ä»å 䟡å€çšæ³ãããã¯å ±ååœæ³ No9337 ã®ããšåçå¯èœãšãã«ã®ãŒã®éèª²çš æªçœ®ã¯åçå¯èœãšãã«ã®ãŒã«ããé»åã®ç«¶äºåãé«ããããšã«ãªãã - 91 - 2.4 å°å瀟äŒãžã®åœ±é¿ ãã£ãªãã³æ¿åºã¯ãçºé»æã®å»ºèšãé æ»ããŠããäºæ ã«å¯ŸåŠããããã1990 幎代ã«ïŒã€ ã®å»ºèšä¿é²çãçå®ããã ïŒå°æ¹èªæ²»æ³ã«ããå¶åºŠïŒ 第ïŒã®æ¿ç㯠1991 幎æç«ããå°æ¹èªæ²»æ³ã«ããå¶åºŠã§ãããããã«ãããšãçºé»äºæ¥è ã¯äºæ¥ã«ãã売äžãïŒïŒ ããŸãã¯åœå¯çšããã€ã€ãªãã£ããŸãã¯æéã® 40%ãå°å èªæ²»äœã« ããããå¿ èŠããããå°å èªæ²»äœã¯æ¬¡ã® 2 ã€ã®æ¹æ³ã§çºé»äºæ¥è ããåŸããã売ãäžãã 䜿çšããããšãã§ããããã®åå ¥ã¯ã80%ãäœæ°ã®é»æ°ä»£ã®å©æéãé é»ç·ã®ãªãããªãªã© ãéããå°å ã®é»æ°ä»£ãäžããã®ã«äœ¿çšããããšãã§ããããŸããæ®ã 20ïŒ ã¯éçºãšç掻 åäžãããžã§ã¯ãã«äœ¿çšããããšãã§ããã1992 幎ãã 2004 幎ã®éã«æ°Žåéçºããã®åœå¯ çšã«ãã城åãããç·å£²ãäžã㯠1,019,715,354.53 ããœã§ããã ãã ããæèè ã«ãããšããã®æ¿çã¯æ åœè ã®å®æœèœåãšè©äŸ¡èœåã®æ¬ ä¹ã«ãã£ãŠã㟠ãæ©èœããŠããªããšè©äŸ¡ãããŠãããå°å èªæ²»äœã®è¡æ¿å¢çã®ãããæ£ç¢ºãªå°å³ã®æ¬ åŠã åºéã管çããåœå®¶äºç®åœå±ã®åºéã®å·è¡ã®é ããããã€ãã®èªæ²»äœè·å¡ã®åœå¯çšäœç³»ã« 察ããèªèäžè¶³ãªã©ããããã®åå ãšãªã£ãŠããã ïŒER 1-94 ã«ããå©çéå ïŒ 2 çªç®ã®æ¿çã¯ããšãã«ã®ãŒç什ïŒEnergy Regulation(ER)ïŒ1-94 ãšããŠçºé»æå°å èªæ²» äœã«å¯Ÿããå©çéå å¶åºŠã§ããããã®ç什ã«ãããšçºé»äºæ¥è ã¯ã販売é»åé 1kWh åœã ã 0.01Peso ãç©ã¿ç«ãŠãªããã°ãªããªãããã®è³éã¯æ¬¡ã®å²åã§æ¬¡ã®åºéã«å åœãããã â é»ååºé(Electrification Fund)<50%> ãã®é»ååºéã¯ãçºé»æã®ããäœæ°ç§»è»¢ãè¡ãããå°åãçºé»æç«å°éèœïŒã ã©ã³ã¬ã€ïŒBarangyïŒãç«å°åžïŒMunicipality or CityïŒãç«å°çïŒProvinceïŒã ç«å°å·ïŒRegionïŒã®é ã«ãåå°åã®é»åäºæ¥ã«åœãŠãããã â¡éçºã»çèšåºé(Development and Livelihood Fund)<25%> ãã®éçºã»çèšåºéã¯ãå°å å°åã®çŠç¥ã®åäžããã°ã©ã ã«äœ¿çšãããããã® åºéã¯ãäœæ°ç§»è»¢å°åïŒ5%ãçºé»æç«å°éèœïŒãã©ã³ã¬ã€ïŒïŒ20%ãç«å°åžïŒ 35%ãç«å°çïŒ30%ãç«å°å· 10%ã§é åãããã â¢æ€æã»æµå管çã»ä¿å¥ã»ç°å¢åäžåºé(Reforestation, Watershed management, Health and Environment Enhancement Fund)ïŒ<25%> ãã®åºéã¯æåéããå°å èªæ²»äœã«ãããæ€æã»æµå管çã»ä¿å¥ã»ç°å¢ã®åäž ã®ããã«äœ¿çšããããé åæ¹æ³ã¯éçºã»çèšåºéãšåãã§ããã ER 1-94 åºéã®è³éé㯠2005 幎 3 æã«ã¯ 3,360,000,000 ããœã«è³ã£ãŠããããã¡ 1,500,000,000 ã¯ç©ç«ã®çŸ©åéã§ãããããæ®ã 1,800,000,000 ããœãå°å èªæ²»äœã§å©çšå¯ èœãšãªã£ãŠãã 1,877 件ã®ãããžã§ã¯ãã ER 1-94 è³éã§æ¿èªããå®æãããã - 92 - ïŒ. å°æ¹é»åã®ç¶æ³ 3.1 å°æ¹é»åã®çŸç¶ ãã£ãªãã³ã«ãããå°æ¹é»åã¯ã蟲æåã³é éå°åã«ãããäœæ°ã®ç掻氎æºã®åäžãæ° èŠåå ¥æºã®åµåºã«ãã貧å°åæžã«ã€ãªãããšããŠãæ¿åºã®éèŠæ¿çãšããŠåãäžããã㊠ããããã£ãªãã³æ¿åºã¯ 1960 幎ã«åœçãšããŠå°æ¹é»åã«åãçµãããšã宣èšããé»ååºã èšç«ãããããã« 1969 幎ãå°æ¹é»åæ³ãå¶å®ãåœå®¶é»ååºïŒNEAïŒã«æ¹çµããå°æ¹é»åã« æ¬è °ãå ¥ããããšãšãªã£ãããã£ãªãã³ã®é é»äºæ¥ã¯æ°éäŒç€Ÿã«ãã£ãŠãªãããŠããããã çµæžæ§ã®é«ã人å£éäžå°åºã®éœåžéšã«éäžããéœåžéšãšå°æ¹éšãšã®æ Œå·®ãåºãã£ãŠããã ãã®ãããNEA ã§ã¯æ³ã«åºã¥ãå°æ¹ã«èšç«ãããå°æ¹é»åçµåãéããŠå°æ¹é»åãæšé²ã ãŠããããšãšãªã£ãã 1970 幎代ã«ã¯æ¿åºãšæŽå©æ©é¢ããã®å€é¡ã®æŽå©ã«ããå°æ¹é»åã¯æ¥éã«é²å±ãã1980 幎ã«ã¯é»åçµåæ°ã¯çŸåšã® 119 çµåã«è³ã£ããããããäžæ¹ã§è²¡æ¿åºç€ã®è匱ãªé»åçµå ãèšç«ããããŸããé»æ°æéã®åŸŽåçãæªãçµåãå€æ°ããã財åé¢ã§ã¯å€ãã®èª²é¡ãæ± ããªããã®é»åã®æ¡å€§ãè¡ãããŠããŠããã 1997 幎ã«ã¯åœå ã®ãã¹ãŠã®çºïŒMunicipalityïŒã¬ãã«ã§ã®é»åãéæããããããã©ã³ ã¬ã€ïŒæèœïŒBarangayïŒã¬ãã«ã§ã®é»åçã¯çŽ 72%ã«ãšã©ãŸã£ãŠããããã®ããããã£ãª ãã³æ¿åºã¯åŒãç¶ãå°æ¹é»åãæšé²ããããã2000 幎㫠O-ILAW ãšç§°ããå°æ¹é»åæšé²ã ãã°ã©ã ãéå§ãã2003 幎 4 æããã¯æ°ãã« ERïŒExpanded Rural ElectrificationïŒèšç» ãã¹ã¿ãŒãããããããã¯ã2008 幎ã«ãŸã§ã«ãã¹ãŠã®ãã©ã³ã¬ã€ã®é»åéæããç®æšã«æ² ãããšãšãã«(åœå㯠2004 幎ç®æšã ã£ããã®ãã2006 幎ã«å»¶é·ãããçŸåšã¯ 2008 幎ç®æš ãšãããŠãã)ãæ°ãã«ã2017 幎ã«äžåž¯ããŒã¹ã§ã®é»åç 90%éæããšããç®æšãèšå®ã ããã®ã§ããããã£ãªãã³ã«ã¯ 41,995 ãã©ã³ã¬ã€ãååšãããšãããŠããã2000 幎æ«çŸ åšã§ã¯ãã®ãã¡ 19.8%ã«çžåœããçŽ 8,300 ãã©ã³ã¬ã€ãæªé»åã§ãã£ãããã®ãããã㣠ãªãã³æ¿åºã¯æ¯å¹Žã®é»åãã©ã³ã¬ã€æ°ãçŽ 1,500 ã«å éããããšããŠããã ãã£ãªãã³ã§ã¯ãåŸæ¥ãâ ãã©ã³ã¬ã€ã®äžã® 10 æžä»¥äžã«é»æ°ãäŸçµŠãããŠãããâ¡ç¡é» åã®ãã©ã³ã¬ã€ã«é é»ç·ãééããŠããïŒé»åäŸçµŠã¯å¯èœã§ãããé»åãããåŠãã¯éèŠ å®¶ã®å€æã«ãããšã®èãã«åºã¥ãïŒ ãã®ããããã®æ¡ä»¶ãæºãããããšãã®ãã©ã³ã¬ã€ã¯é» åããããšå€æãããŠãããããããæè¿ïŒ€ïŒ¯ïŒ¥ã§ã¯ãã®å®çŸ©ãèŠçŽããâ ç¬ç«ç³»çµ±ã®å Ž åãæç¶å¯èœãªãšãã«ã®ãŒã«ãã 30∼40 件ãé»åãããŠããããšãïŒæç¶å¯èœãšãã«ã®ãŒ ãšã¯ããœãŒã©ãŒãããããªãŒãã£ãŒãžã¹ããŒã·ã§ã³ïŒïŒ¢ïŒ³ïŒ£ïŒããã£ãŒãŒã«ã«ããå°èŠæš¡çº é»æ©ã»ããããªã©ã§ããïŒãâ¡ã°ãªããããã®é»åã®å Žåã¯ãã©ã³ã¬ã€ã«é é»ç·ãééã㢠ã¯ã»ã¹å¯èœã§ããããšããšãããããªãã¡ãâ¡ã¯åŸæ¥éãã§ãããã®ã®ãâ ã¯é»ååçè æ°ãåŒãäžãããããããªãããäŸç¶ããã©ã³ã¬ã€åäœã§ã®é»åç㧠100%ãéæãããšã ãŠãå®äœã¯äŸç¶å€ãã®å®¶å±ã®é»åããªãããŠããªãç¶æ ãç¶ãããšã«ã¯å€ãããªããå®éã ïŒã€ã®ãã©ã³ã¬ã€ã§é»åãããäžåž¯æ°ã¯å¹³å 30∼40 æžçšåºŠãšããããã©ã³ã¬ã€ã®äžéšäžåž¯ ã®é»åãšããã±ãŒã¹ãã»ãšãã©ã®ããã§ããã 2006 幎 10 æçŸåšããã©ã³ã¬ã€ç·æ° 41,945 ã®ãã¡ãé»åããããã©ã³ã¬ã€ã¯ 39,590 㧠- 93 - é»åçã¯å šåœå¹³å㧠94.4ïŒ ãšãªã£ãŠãããé»åçã¯å°æ¹ã«ãã倧ããªå·®ããããã«ãœã³å° åã§ã¯ 97.1%ãããµã€ã¹å°åã§ã¯ 96.0%ããã³ãããªå°åã§ã¯ 87.0%ãšãªã£ãŠããããã ãé»åå®æœã®è²¬ä»»è ã§ããé é»äºæ¥è å¥ã«ã¿ããšãæãå€ãé»åçµå(ECs)ã§ã¯ 93.8%ã MERALCO ã§ã¯ 98.5%ããã®ä»æ°éäºæ¥è /å°æ¹èªæ²»äœ/ãã®ä»ã§ 97.7%ãšãªã£ãŠããã 3.2 å°æ¹é»åã®æšé²æ¹ç å°æ¹é»å㯠O-ILAW ããã°ã©ã åã³ ER èšç»ã«åºã¥ããDOE ãäžå¿ãšãªã£ãŠåé¢ä¿æ©é¢ãå® æœããŠãããå°æ¹é»åã®é²ãæ¹ã¯ãŸã倧統é ãš DOE é·å®ã幎éã®é»åç®æšãç«ãŠãããã® é»åç®æšã DOE çã«ããããã°ã©ã ããŒã (PT)ãé¢ä¿æ©é¢ã«å²ãæ¯ããããã«åºã¥ããŠå° æ¹é»åçµåãæ°å¶é»åäŒç€Ÿçã®å®æœæ©é¢ãå®æœã«è¡ã£ãŠããã O-ILAW ããã°ã©ã åã³ ER èšç»ã§ã¯å°æ¹é»åãå¹ççã«é²ããããã«ãæ¿åºæ©é¢ãé»æ° äºæ¥è 以å€ã®çµç¹ã«ãå°æ¹é»åäºæ¥ã«åå ããæ©äŒãäžããŠããããŸããã®è³éãåœã®äž è¬äºç®ãER1-94 åºéãå°æ¹èªæ²»äœäºç®ãNGO ãå€åœæŽå©ã«ããæ¯æŽããªã©å€æ§ãªè³éæº ã«ãã£ãŠãããããã«ãIPP ã«ãåå ã®æ©äŒãäžãããšå ±ã«ãã®è³éåã«ãæåŸ ããŠããã ER1-94 åºéãçšããŠå®æœããå°æ¹é»åã®äŸãšããŠã¯ã2000 幎㫠PNOC-EDC ãã¬ã€ã島 ã® Ormoc åšèŸºã§çŽ 10 ã®ãã©ã³ã¬ã€ã®é»åãå®æœããã®ãã¯ãããç±³åœã® Southern Energy ãã±ãœã³ã«ããç³çç«åçºé»æåšèŸºã®ãã©ã³ã¬ã€é»åãå®æœããäŸãã»ãã§ãã¬ãŒã·ã¢ East Asia ãè¡ã£ãäŸãªã©ãå ±åãããŠãã ãªããå°æ¹é»åã¯åœè©²å°åã«é é»äºæ¥æš©å©ãæããè ïŒFranchise Distribution Unitãå · äœçã«ã¯ EC ãªã©ïŒãåºæ¬çã«å®æœãããã®ã§ããããé é»äºæ¥æš©å©è ãæ¡ç®æ§ããåœè©²å° åã«åœé¢é»åèšç»ã¯ãªãããšè¡šæããå°äœã«å¯ŸããŠã¯ Missionary é»åå¶åºŠã«ããé»åãé² ããããšãšããŠãããMissionary é»åã¯ãEC 以å€ã®è ã«ãã£ãŠãããããšã«ãªããäŸã ã°æ°éäŒæ¥ã«ãæåŸ ããŠããããã®ãããªå Žåããã®å°æ¹é»åã®å®æœè 㯠QTPïŒQualified Third Party æè³æ Œç¬¬ïŒè ïŒãšåŒã°ãããè¿å¹Žã¯ãã¿ã³ã¬ã¹å·ã€ãªãã³ç«åçºé»æã®äž»èŠäŒ æ¥ã§ããéåœé»åïŒKEPCOïŒã QTP ãšããŠè²¢ç®ãããŠãããšã®ããšã§ãããQTP ãçŸã ãªããã°æåŸã®æ段ãšã㊠NPC-SPUG ãå®æœãããMissionary é»åã¯æ¡ç®ã®ãšããªãå° åã察象ãšããŠããããšããç¶ç¶ããè£å©éãå¿ èŠã§ããããŠãããŒãµã«ãã£ãŒãžã«ãã è³éãå ãŠãããããŠãããŒãµã«ãã£ãŒãžãšã¯é»æ°æéã®äžéšãšããŠå šéèŠå®¶ã«è»¢åãã 城åãããè³éã§ããããã®é¡ã¯ãšãã«ã®ãŒèŠå¶å§å¡äŒïŒERCïŒã決å®ããŠããã 3.3 å°æ¹é»åã®èª²é¡ ãã£ãªãã³ã®é é»äºæ¥ã¯ 119 ã®é»åçµåã16 ã®æ°éé é»äºæ¥è ã3 ã€ã®åžå¶é»æ°äºæ¥è ã®åèš 138 ã®é é»äºæ¥è ã®ãµãŒãã¹å°åºã«åå²ãããŠãããé»åçµåã®ãã¡ãã©ã³ã¬ã€é» å 100%ãéããŠããçµå㯠15 çµåïŒ12.6%ïŒã«ãããã75 çµåïŒ63.0%ïŒã¯ãã©ã³ã¬ã€ é»åçã 90%ã«éããŠããªãããŸãããããã®çµåãäžåž¯é»åç㯠100%ã«éããŠããªãã é»åäºæ¥ã¯éé é»ç³»çµ±ã®å»¶äŒžãšåæ£åé»æºã掻çšããæ¹æ³ã«åããããã2000 幎æ«æç¹ ã§æªé»åã§ããçŽ 8,300 ãã©ã³ã¬ã€ã®ãã¡ãçŽ 45%ã«çžåœããçŽ 4,000 ãã©ã³ã¬ã€ã¯æ¢å 系統ããããªãé¢ããå°åã«ååšããŠããããããã®å°åã§ã¯éèœãåæ£ããŠååšããŠã ã系統ã®å»¶äŒžã¯å°é£ã§ãããããæåŸæ°Žæºãäœãããšããé»åã«ãããã³ã¹ãã¯é«ããæ - 94 - è³å¹çã¯æ¥µããŠäœãç¶æ ã«ããããã®ãããªå°åã«ãããŠã¯ãªãã°ãªããã®åæ£åé»æºã® 掻çšã«é ŒããããåŸãªãç¶æ ã§ãããåæ£åé»æºãšããŠã¯ãå èµæ°Žåãããå°ç¹ã§ã¯å°æ°Ž åã掻çšãããã®ä»ã®å°ç¹ã§ã¯å€ªéœå ãäžå¿ã«é¢šåããã€ãªãã¹ãªã©ã®æ°ã»åçå¯èœãšã ã«ã®ãŒçºé»ã«ããããã°ãªããã掻çšãããŸããSHSïŒSolar Home SystemïŒã«ããæžå¥ é»åã®åãçµã¿ã匷åããããšãšããŠããããªãã1999 幎ãã 2002 幎ã®éã«é»åããã 5,082 ãã©ã³ã¬ã€ã®ãã¡ 81.8%ã«çžåœãã 4,159 ãã©ã³ã¬ã€ã¯ç³»çµ±ã®å»¶äŒžã«ããé»åããã æ®ãã® 18.2%ã923 ãã©ã³ã¬ã€ã¯ããã°ãªããã«ããé»åã§ãã£ããããã°ãªããã«ããé» åã®ãã¡çŽïŒå²ãæ°ã»åçå¯èœãšãã«ã®ãŒã«ããé»åã§ãã£ãã 系統延䌞ã«ããé»åã«ãããããã°ãªããã«ããé»åã«ãããä»åŸã®é»å察象ãšãªãã ã©ã³ã¬ã€ã¯é»åéèŠã®èŠæš¡ãå°ãããé»åã®äŸçµŠã³ã¹ãã¯é«ããã®ãšãªã£ãŠããããŸãã ãã®ãããªãã©ã³ã¬ã€ã®äœæ°ã®æåŸã¯å°ããããšããé é»äºæ¥è ã«ãšã£ãŠé»åäºæ¥ã®é å ã¯æ¥µããŠå°ãããã®ãšãªã£ãŠãããããããªãããäœæ°ã®ç掻氎æºã®åäžã®èŠ³ç¹ãããã® ãããªå°åã«ãããŠã©ã®ããã«é»åãé²ããŠããããä»åŸã®å€§ããªèª²é¡ãšãªã£ãŠããã 3.4 å°æ¹é»åã®å¹æ åœéååéè¡ãå®æœãããã£ãªãã³ãNEA å°æ¹é»åäºæ¥ãã«é¢ãããåå欟æ¡ä»¶äºåŸè© äŸ¡å ±åæžïŒ2004 幎ïŒãã«ãããšããã£ãªãã³ã«ãããå°æ¹é»åã¯æ¬¡ã®ãããªå¹æããããã ããšãããŠããã a)å°±æ¥æ©äŒããã³åå ¥ã®å¢å æ¬äºæ¥ã«ãã£ãŠé»åãå®äºãããã©ã³ã¬ã€ã§ã¯ãé»æ°ã掻çšããŠæ°ããä»äºãå§ã ãããåå ¥ãå¢ããããããŠããäºäŸãã¿ãããããŸããçµå¶ããŠããé貚åºãå€é ããŸã§éãããšãã§ããããã«ãªã£ããå·å庫ã䜿çšããŠã¢ã€ã¹ãã£ã³ãã£ãŒãäœã 販売ããŠããããã³å±ãéæ¥ãããªã©ã®äºäŸãã¿ãããã b)æè²ç°å¢ã®æ¹å æ¬äºæ¥ã§ã¯äžè¬ã®äžåž¯ã§ã¯ãªãããã©ã³ã¬ã€ã®ä¿è²åãå°åŠæ ¡ãªã©ã®æè²æœèšãå æã«é»åãããŠãããã€ã³ã¿ãã¥ãŒèª¿æ»ãå®æœãã16ã®ãã©ã³ã¬ã€ã§ã¯ãåèš13ã«æ ã®ä¿è²åã»å°åŠæ ¡ã4ã«æã®é«æ ¡ãé»åãããŠããããŸãå家åºã«ãããŠãåŸæ¥ã®ã± ãã·ã³ã©ã³ãããã¯ããã«æããèå ç¯ã»çœç±é»çã䜿çšã§ããããã«ãªã£ãããã å€éã§ãå匷ãè¡ããããã«ãªã£ãã c)å©äŸ¿æ§ã®åäžãšåš¯æ¥œã®å¢å é»ååŸãã»ãšãã©ã®äžåž¯ãèå ç¯ãé»ççã®ç §æãè³Œå ¥ããŠããããã®ã»ãã«ãã äœæ°ã¯å·èµåº«ãã¢ã€ãã³ãæŽæ¿¯æ©ãé»åãžã£ãŒãç掻çšæ°Žãã¿äžãçšé»æ°ãã³ãçã å©äŸ¿æ§ãé«ãã家äºåŽåã軜æžããããšãã§ãã家é»è£œåãè³Œå ¥ããŠããããŸããã ã¬ãããããªãã©ãžãªãã©ãžã«ã»ãã«ã©ãªã±ãªã©äœæã楜ããããã®é»æ°è£œåãè³Œå ¥ ããŠãããé»åããããŸã§ã®æŒéçã§åããæããªã£ããå¯ããšããç掻ãããé»å åŸã«ã¯ã嚯楜ã家æãè¿æãšã®ã³ãã¥ãã±ãŒã·ã§ã³ãåäžãããšåçããäžåž¯ãæ°å€ ãã¿ãããã - 95 - d)å®äŸ¡ã§å®å šãªå æºã®ç¢ºä¿ é»åããã以åãåäžåž¯ã¯ç §æãšããŠãã»ãšãã©ã®å®¶åºãã±ãã·ã³ã©ã³ãã䜿çšã ãŠãããé»ååŸã¯ãèå ç¯ãçœç±é»ççã䜿çšãããŠããã60Wçœç±é»çã¯ãæãã ã®é¢ã§ã±ãã·ã³ã©ã³ãã®7∼70åãã®æãããããã®ã«å¯Ÿãã1æéãããã®è²»çšã¯çŽ 2åã®1∼9åã®1åãå®äŸ¡ã§ããããŸããã±ãã·ã³ã©ã³ãã¯ç«çœã®åå ãæç ã«ããæª èãå³ã»ç®ã®ããã¿çã®å¥åº·è¢«å®³ã宀å ãžã®ç €ã®ä»çãªã©ã®åé¡ãçããŠãããå€ã ã®äœæ°ã¯é»åã«ããã±ãã·ã³ã©ã³ãã®æç ã«ãã被害ãç«çœã®å¿é ããªããªã£ããš èããŠããã ïŒ. 察象å°åã®ç¶æ³ 4.1 åãµããŒã«å·ã®ç¶æ³ åãµããŒã«å·ã¯ãã¬ã€ãå·ãåã¬ã€ãå·ãããªã©ã³å·ãæ±ãµããŒã«ã西ãµããŒã«ãšäžŠã¶ æ±ããµã€ã¹å°åã®äžéšã§ãããåãµããŒã«å·ã¯ãã£ãªãã³è«žå³¶ã®æ±éšã«äœçœ®ããåã¯ãµã³ ãã«ããã£ã海峡ã西ã¯ãµããŒã«æµ·ãæ±ã¯å€ªå¹³æŽãåéšã¯è¥¿ãµããŒã«å·ãæ±ãµããŒã«å·ã« æ¥ããŠããã å³−1 åãµããŒã«å·æŠç¥å³ åãµããŒã«å·ã¯ãã«ãœã³ããããµã€ã¹åã³ãã³ãããªãžã®ã²ãŒããŠã§ã€ã§ããã¹ãšã㧠ãªãŒã䜿ãããã©ãã 14 æéããããæè¿ã§ã¯ããã©ãšå·éœã§ããã«ã¿ã«ãã³ã®éã§èªç©º æ©ãé± 4 䟿å©çšå¯èœãšãªãã¢ã¯ã»ã¹ãè¯ããªã£ãã åãµããŒã«å·ã¯é¢ç© 3,498km2ã25 ã® MunicipalitiyïŒçºïŒã569 ã® BarangayïŒæïŒããæ§ æãããããã人å£ã¯ 500,639 人ïŒå¹Žç 2.11ïŒ ã§å¢å ïŒãäžåž¯æ°ã¯ 94,410 äžåž¯ã§ããïŒ2000 幎調æ»ïŒã åãµããŒã«å·ã¯ããã£ãªãã³ã®äžã§ããçµæžã»ç€ŸäŒéçºã®æãé ããå°åã®äžã€ã§ãã ïŒãã£ãªãã³å šïŒïŒå·ã®ãã¡çŽïŒïŒãæ°ãã貧å°å·ã®äžã€ïŒãäœæ°äžäººåœããã®æåŸæ°Žæºã å šåœå¹³åã®ïŒå²æªæºãšãªã£ãŠããããŸããåéšå±±éå°åã¯ãäžåž¯æ°ããèŠãé»åç㯠20% 以äžã§ãã£ãªãã³ã®äžã§ãæãéçºãé ããŠããå°åã§ãããããåçå¯èœãšãã«ã®ãŒã - 96 - å©çšããå°æ¹é»åãå³ãã蟲æ¥çç£ã®æ¡å€§ã芳å ç£æ¥ã®çºå±ãç®æããŠããã åå·ã®ç£æ¥ã¯èŸ²æ¥ãäž»äœã§ãããç±³ããšããããããã³ã³ããããããããã£ããµã㪠ã©ãäž»ãªåç©«ç©ã§ããããããã蟲æ¥ãäž»ãªåå ¥æºã§ããã«ãããããããç±³ã®å·å èªçµŠ ãéæãããŠããããè¿é£ã®ã¬ã€ãå·çããã®ç§»å ¥ã«é Œã£ãŠããç¶æ³ã§ããããŸããææ°Ž ç¶æ³ãæªãããäœæ°ãäœè¡åžè«ç ã«ããããªã©ãå£æªãªä¿å¥è¡çç¶æ ãéçºã®åŠšããšãªã£ ãŠãããããã«ãåœå°åã®éè·¯ã¯æªèè£ ã®ããéšå£ã«æ°Žæ²¡ãããªã©ã»ãšãã©éè¡ãåºæ¥ãã 蟲ç£ç©ãåžå Žã«éæ¬ããããšããŸãŸãªãããåå ¥ç¢ºä¿ã®éãŸã§éããããŠããç¶æ³ã§ããã åãµããŒã«å·ã¯å æ¥ãåå£ã»æ°Žè³ªãšãã«èŸ²æ¥ã«é©ããŠããããšãããäžéšã«ãœã³å¹³éã ãã³ãããªå³¶ãšäžŠã³èŸ²ç£ç©å¢ç£ã®æœåšåãæãé«ãå°åãšããŠæåŸ ãããŠããçµç·¯ãããã 1970 幎代ã«ã¯ãäžéãªã©ã®æ¯æŽã®ããšãéè·¯ãäžæ°ŽéæŽåã蟲æ¥éçºãªã©ã®éçºèšç»ãäœ æããããããããªãããå ±ç£ã²ãªã©ã®æŽ»çºãªæŽ»åãªã©ã®æ²»å®åé¡ã«ããå®éã«ã¯éçºã« çæããããçŸåšãéè·¯ãããããæœèšã®æªæŽåãåå ã§äœç©åéã䌞ã³æ©ã¿ã蟲æ°ã貧 å°ããè±åŽã§ããªãç¶æ³ã«ãããçŸåšã§ã¯ãã®æ²»å®äžã®åé¡ã解æ¶ãããŠãããããæœèš ãªã©ã®åºç€ã€ã³ãã©ãæŽåããããšã«ããã蟲æ°ã®åå ¥å¢å ãå³ãããšãæ±ããããŠããã ããã«èŸ²æ¥ã€ã³ãã©ã«å ããé»åèšåãäžæ°ŽéæŽåãé茞ã€ã³ãã©æŽåãäœè¡åžè«ç 察ç ãªã©ã®ä¿å¥è¡çæœèšæŽåãè¡ãããšã«ããã蟲æ°ã®å± äœç°å¢ã»ç掻åäžãå³ãããšãç·æ¥ ã®èª²é¡ãšãªã£ãŠããã 4.2 åãµããŒã«å·ã®é»åäºæ åãµããŒã«å·ãå«ãæ±ããµã€ã¹å°åã®é»åäŸçµŠã¯ãã¬ã€ãå·ã®ãã³ãŽãã³ No1,2,3 å°ç± çºé»æãããšãªã£ãŠãããç·çºé»å®¹é㯠700MW ãè¶ ããŠãããããã§çºé»ãããé»åã¯ã ã«ãœã³−ã¬ã€ãé£ç³»ç·ãã¬ã€ã−ãµããŒã«é£ç³»ç·ãã¬ã€ã−ãããŒã«−ã»ã−ãã°ãã¹− ããã€é£ç³»ç·ã«ããåå°ãžäŸçµŠãããŠããã åãµããŒã«å·ã®é»åäŸçµŠã¯ãåãµããŒã«é é»çµåïŒNORSAMELCOïŒã«ããè¡ãããŠããã 2005 幎æ«çŸåšã§ãåãµããŒã«å·ã® 569 ã® Barangay ã®ãã¡ 73ïŒ ã«çžåœãã 415 ã® Barangay ã§é»åãè¡ãããŠãããäžåž¯æ°ã«å¯ŸããŠã®çŽ 50%ã®é»åçã§ãããé é»çµåã®è©³çŽ°ã¯ïŒç« 㫠瀺ãã ïŒ. åçå¯èœãšãã«ã®ãŒã«ããå°æ¹é»åã®å¯èœæ§æ€èš 5.1 察象å°åã«ãããå°æ¹é»åã®ç¶æ³ 5.1.1 åãµããŒã«å·ã®å°æ¹é»åã®ç¶æ³ ä»å調æ»ã®å¯Ÿè±¡å°åã¯åãµããŒã«å· Catubig å·æµåã§ãããè¡æ¿åºåã§ãããšåãµã㌠ã«å· Catubig çºããã³ Las Navas çºã§ããã åãµããŒã«å·ã¯æ±ããµã€ã¹ã® Region VIII ã«å±ããã2006 幎 7 æçŸåšã«ããã Region VIII ã®ãã©ã³ã¬ã€é»åçã¯å šäœã§ 90.8%ã§ãããç¹ã«å°ç±çºé»æãæããã¬ã€ã島ã®åé» åçµåã¯ã»ãŒ 100%ã®é»åçã«ãªã£ãŠãããããããªãããåãµããŒã«å·ã管èœå°åãšãã é é»çµå NORSAMELCO ã«ãããŠã¯é»åç㯠73.1%ã«ããããRegion VIII ã®æäœãšãªã£ãŠã ãïŒ è¡š−2 ïŒã - 97 - ãŸãã2004 幎æ«æç¹ã§ã®åãµããŒã«å·å ã®åèªæ²»äœå¥é»åç¶æ³ãèŠããš Catubig çºã¯å ãµããŒã«å·å¹³åãè¥å¹²è¶ ãã 60.9%ã§ãããã®ã®ãLas Navas çºã¯åå·å ã®æäœã®é»åç ïŒ11.3%ïŒãšãªã£ãŠãããé»åä¿é²ãå«ç·ã®èª²é¡ãšãªã£ãŠããããšãåããïŒ è¡š−3 ïŒã è¡š−2 Region⠧㮠Barangay é»åç Electric Number of Barangays Cooperatives Covered Energized % Region VIII 4390 3984 90.8 DORELCO 499 494 99.0 LEYECO II 196 196 100.0 LEYECO III 285 285 100.0 LEYECO IV 245 242 98.8 LEYECO V 416 416 100.0 SOLECO 500 483 96.6 BILECO 132 132 100.0 SAMELCO I 427 366 85.7 SAMELCO II 524 482 92.0 ESAMELCO 597 472 79.1 NORSAMELC 569 416 73.1 (as of 2006,July,31) (Source: NEA) è¡š−3 åãµããŒã«å·ã® Brangay é»åç (as of 2004.12.31) Municipality Energized Allen Biri Bobon Capul Catarman Catubig Gamay Laoang Lapinig Las Navas Lavezares Lope de Vega Mapanas Mondragon Palapag Pambujan Rosario San Antonio San Isidro San Jose San Roque San Vicente Silvino Lobos Victoria Total Potential Number of Barangays Households Covered Energized % 20 19 95.0 3,217 8 2 25.0 1,317 18 13 72.2 2,613 12 5 41.7 1,780 55 37 67.3 9,228 46 28 60.9 4,050 26 12 46.2 3,119 56 33 58.9 7,968 15 5 33.3 1,396 53 6 11.3 4,286 26 20 76.9 3,635 22 5 22.7 1,621 13 7 53.8 1,326 25 14 56.0 3,987 32 23 71.9 4,019 26 12 46.2 3,349 11 7 63.6 1,196 10 10 100.0 1,423 14 13 92.9 3,591 16 16 100.0 2,099 16 10 62.5 2,493 7 3 42.9 1,178 26 3 11.5 1,601 16 13 81.3 1,873 569 316 55.5 72,365 Cooperative Members House Connections Total % Total % 2,140 66.52 2,529 78.6 376 28.55 397 30.1 1,710 65.44 1,598 61.2 504 28.31 446 25.1 7,465 80.90 8,145 88.3 1538 37.98 1596 39.4 992 31.81 1104 35.4 3,707 46.52 3,905 49.0 441 31.59 476 34.1 451 10.52 479 11.2 1,565 43.05 1,624 44.7 309 19.06 374 23.1 472 35.60 471 35.5 1,985 49.79 1,927 48.3 2,181 54.27 2,259 56.2 1,396 41.68 1,470 43.9 596 49.83 629 52.6 723 50.81 665 46.7 2,155 60.01 2,291 63.8 1,356 64.60 1,385 66.0 1257 50.42 1288 51.7 195 16.55 196 16.6 12 0.75 12 0.7 956 51.04 945 50.5 34,482 47.65 36,211 50.0 Source : Northern Samar Electric Cooperative (NORSAMELCO), Inc., Bobon, Northern Samar - 98 - 5.1.2 é»åäŸçµŠèšå NORSAMELCO ã¯äž»ã«ã¬ã€ã島㮠Tongonan å°ç±çºé»æïŒå·æ©ïŒèžæ°éçº PNOC-EDC,çºé» NPCã åºå 112.5MWïŒããã®é»åããµããŒã«å· Wright å€é»æã«ãŠ 138kV ãã 69kV ã«éäžããã 69kV éé»ç·ãçµç±ã㊠DalakitãLawaanãAllen ã®ïŒå€é»æã«ãŠåé»ã管å ã«äŸçµŠããŠããã NORSAMELCO ã®æ管ã¯å€é»æåé»ç«¯ä»¥éã§ãããCatubig çºã Las Navas çºãžã®é»åäŸçµŠã¯ Lawaan å€é»æïŒ69kV/13.2kV 容é 3.75MW)ããè¡ãããããããçŽ 30km ã®é é»ç·ãä»ã㊠Las Navas ãŸã§äŸçµŠããŠããã ãŸããCatubig çºã Las Navas çºã«ãããŠã¯ããœãŒã©ãŒã·ã¹ãã ãå°èŠæš¡ãªãã£ãŒãŒã«çº é»æ©ã»ããã«ããé»åããããã¯ãœãŒã©ãŒã·ã¹ãã ã系統ããã®é»åãèªåè»çšããã㪠ãŒïŒ12vïŒã«å é»ãåæžã§å©çšãããšããããããªãŒã»ãã£ãŒãžã»ã·ã¹ãã ïŒBCSïŒã«ãã æžå¥é»åãè¡ãããŠããããœãŒã©ãŒã·ã¹ãã ã«ãã BCS 㯠PNOC-EDC ã NPC ã«ããæ äŸãããŠãããšã®ããšã§ãããBCS ã®å é»äŸ¡æ Œã¯ç³»çµ±ããã®é»åã®å ŽåïŒååœãã 50-70 ããœããœãŒã©ãŒã·ã¹ãã ã®å Žå 20 ããœçšåºŠã§ããããŸãããã£ãŒãŒã«çºé»æ©ã»ããã¯å°å Ž ã®æ°éäŒæ¥ãããžãã¹ãšããŠè¡ã£ãŠãããé»æ°æé㯠10W åœããæ 100 ããœãé転ã¯ïŒæ éïŒ18:00-21:00ã5:00-6:00ïŒã§ããããªããåœå°ã®å®¶åºã®å¹³åæå㯠4,000-6,000 ããœçš 床ã§ãããé»æ°æéã¯åå ¥ã«æ¯èŒãããšããªãé«ããã®ãšãªã£ãŠãããããããå©äŸ¿æ§å äžã®ãããé»æ°å©çšãåžæãããã®ãå€ããšã®ããšã§ããããœãŒã©ãŒã·ã¹ãã ã¯ããã«ïŒ æ 75WpïŒ1.2ïœ×1.7mïŒãæšæºã§ããããïŒæ 150Wp ã®ããã«ãæ®åãå§ãŸã£ãŠãããš ã®ããšã§ããã 5.1.3 NORSAMELCO ã®æŠèŠ NORSAMELCO é é»çµåã¯ãåãµããŒã«å·ãäŸçµŠåºåãšããé»åçµåã§ããã1977 幎 ã«èšç«ããããäŸçµŠåºåé¢ç©ã¯ 3,498kmãäŸçµŠå¯Ÿè±¡ã® Municipality æ°ã¯ 24ãBarangay æ° ã¯ 569 ã§ãããããã¡ã23 Municiparityã316 Barangay ã«äŸçµŠããŠãããæªé»åã® 1 Municiparity ã 2007 幎äžã«ã¯é»åãããäºå®ã§ãããäŸçµŠåºåå ã®äžåž¯æ°ã¯çŽ 72,000 äž åž¯ã§ãããã 2004 幎çŸåšã36,211 äžåž¯ãåé»å¥çŽãè¡ã£ãŠãããéèŠå®¶æ§æã¯å®¶åºçšã 67ïŒ ã åæ¥çšã 18%ãå®å ¬åºçšã 9%ãç£æ¥çš 1%ãè¡ç¯ 4%ãšãªã£ãŠããã NORSAMELCO ã®è²©å£²é»åé㯠2004 幎㧠31,249MWh ã§ããã72.4%ã家åºçšã§ããã ææ°ã®ããŒã¿ã§ã¯ïŒã«æ 3,717,900kW ïœïŒ 2006 幎 10 æïŒãšãããŠããã®ã§ã幎é 44,615MWh ã«çžåœããã æ倧éèŠé»å㯠2006 幎㧠8,133ïœW ã§ãããé»åã®é²å±ã«äŒŽãã NORSAMELCO ã§ã¯ã·ã¹ãã ãã¹ã倧ãããªãåé¡ãåºãŠãããå¹³åã·ã¹ãã ãã¹ã¯ 21ïŒ ã«ãéããŠãããæè¡çãªãã¹ã«å ããé»åèšã®æ éãªã©éæè¡çãã¹ã倧ãããšã®ããš ã§ããã NORSAMELCO ã® 2004 幎ã®é»æ°æéã¯ã家åºçšãæãé«ã 6.13 ããœ/kWhãåæ¥çšã æãå®ã 5.41 ããœ/kWhãå šäœã§ 5.60 ããœ/kWh ã§ããããŸããææ°ã®é»åæéã§ã¯ 2006 幎 10 æçŸåšã§ 6.23 ããœ/kWh ã«äžãã£ãŠããããªããNORSAMELCO ã NPC ããè³Œå ¥ ããŠããè²·é»å䟡㯠4.66 ããœ/kWh ã§ããã - 99 - NORSAMELCO ã®åæ¯ç¶æ³ã¯ãå¶æ¥å©çâ²1,550,085Peso ã®èµ€åïŒ2004 幎ïŒã§ãïŒå¹Ž é£ç¶èµ€åãèšé²ããŠããããªããèµ€åå¹ ã¯çž®å°ããŠããŠããããŸããéèŠå®¶ä»¶æ°ã¯å¹ŽççŽ 13%ãæ倧é»åã¯å¹ŽççŽ 7ïŒ ã§å¢å ãããã®ãšèŠãããŠããã2008 幎ã«ã¯å šãã©ã³ã¬ã€ã® é»åçéæãç®æšã«ããŠããã 5.1.4 ã«ããŒããã°çºåã³ã©ã¹ããã¹çºã®é»åã®æŠèŠ Catubig çºã«ã¯ 47 ã® Barangay ãååšããããã®ãã¡ 28 Barangay ãé»åãããŠããã ãŸããLa Navas çºã«ã¯ 53 ã® Barangay ãååšãããã¡ 26 Barangay ãé»åãããŠããã ãŸããäž¡çºãšãæªé»åã® Barangay ã«å¯ŸããQTP ã«ããé»åèšç»ãæããŠããããããã QTP ã«ããé»åã«å¯Ÿããæ¯æŽçãããã¯çœ°åã®ãããªæªçœ®ã¯ãªãããããã®é»åèšç»ãäº å®éãå®æœããããã¯äºæãèš±ããªãã 5.2 å°æ¹é»åã«äŒŽãé»åéèŠã®æ³å® Catubing çºããã³ Las Navas çºã«ãããŠã¯ãCatubig 蟲æ¥ç·åéçºäºæ¥ïŒHelp for Catubig Agricultural Advancement Project;HCAAPïŒããããåœã®åå欟ã掻çšããŠå®æœãããŠããã ããã«ããçŽ 4,500Ha ã«ã®ãŒãçæŒïœ¥ææ°Žæœèšã®æŽåãè¡ãããå¹¹ç·éè·¯ãçŽ 65km ã«ãã ãæŽåãããäºå®ã§ããããã®çµæãåœå°ã®èŸ²æ¥çç£æ§ã¯åŸæ¥ã®çš²äœåäœçç£é 1 ãã³/ha æªæºãã 5 ãã³/ha ãžãšå€§å¹ ã«æ¹åããããšãæåŸ ãããŠããã æ¬èª¿æ»ã¯åãããžã§ã¯ãã«ããæŽåãããçæŒæ°Žè·¯ã«ãããå°èŠæš¡æ°Žåããã³ã·ã£ã«ã 蟲æ¥çç£æ§åäžã«äŒŽããã€ãªå»æ£ç©ã®çºçãªã©ã«æ³šç®ãããããã®åçå¯èœãšãã«ã®ãŒè³ æºãåœå°åã«å€æ°ååšããæªé»å Barangay ã®é»åã«æå¹å©çšã§ããªãããæ€èšãããã®ã§ ããã ãŸããBarangay ã®é»åã«äŒŽããã©ã®çšåºŠã®é»åéèŠãçºçããã§ããããã3 ç« ã§èŠã ãšãããã²ãšãã³é»åãè¡ããããšäœæ°ã¯ãç §æãTVãå·èµåº«ãªã©ã®å®¶é»è£œåãè³Œå ¥ãã ç掻ã®å©äŸ¿æ§ãé«ããããšããããŸããé»åãããªãé»åã®ããããªã©ã®åšå ·ãæŽåãã åŽååã®è»œæžãä»å 䟡å€ã®é«ã補åãçç£ããããšããããã®ãããããçšåºŠã®ãŸãšãŸã£ ãé»åéèŠãçºçããããšã芳枬ãããŠããã ããã§ã¯ãäžåž¯æ° 50 æžã® Barangay ãã¢ãã«ãšããé»åãè¡ãããå Žåã家åºçšç §ææ© åšãTVãå·èµåº«ãªã©ã®å®¶é»è£œåãããçšåºŠã®å®¶åºã«æ®åãããã®ãšèãããŸããBarangay å ã«ãããŠãè¡ç¯èšçœ®ãç°¡ææ°Žéçšãã³ãæŽåãªã©ãè¡ãããããã«ã¯ã粟米æ¥è ã氷補 é æ¥è ã®çºçãªã©ãèµ·ãããã®ãšæ³å®ããïŒè¡š−4ïŒãããã«ãããæèœå šäœãšããŠçŽ 9.6kW ã®ããŒã¯éèŠãçºçãããã®ãšèããããããŸãããããã®éèŠã«ããæš¡åŒçæ¥è² è·æ²ç· ã¯å³−2 ã®ããã«æ³å®ãããããã®éèŠã®è² è·ç㯠48.8%ã§ããã - 100 - è¡š−4 æèœé»åã«ããéèŠæ³å® ïŒEnergy Denmand in BarangayïŒ <Demand> coverage (kW) (hour) Number of Households 50 Households 160 W Household Light (40Wx4) 70 W Household TV Households Refrigerator (50L 100 W (Refrigerator Availability) ( 0.3 ) Street Light (40WX25) 40 W Pump for Water Well 250 W Ice Manufacturer 1,250 W Rice Miller 3,000 W Total ïŒPeak Demand ïŒBase Demand 0.8 0.5 0.3 6.4 1.75 0.45 25 1unit 1unit 1unit 1 0.25 1.25 3 9.6 5.0 (kWh/ day) 4 4 24 Remarks 25.6 Peak 7.0 Peak 10.8 Peak & Base 12 12.0 Peak & Base 20 5.0 Non-Peak 20 25.0 Non-Peak 9 27.0 Non-Peak 112.4 kW 44.6 ïŒ kW 67.8 ïŒ å³−2 æèœé»åã«ããé»åéèŠæ³å®ïŒæ¥è² è·æ²ç·ïŒ Daily Power Demand in Barangay (50 Households) 12 10 Demand (kW) 8 6 4 2 0 1 2 3 4 5 6 HH Ref 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 hour St Light HH Light HH TV Pump Ice Rice 5.3 é é»ç·å»¶é·ã«ããé»åèšç»ãšã³ã¹ãæ³å® åçå¯èœãšãã«ã®ãŒã«ããé»åãæ€èšããã«åœãããé é»ç·ã®å»¶é·ã«ããé»åã«ã¯ã©ã® çšåºŠã®ã³ã¹ããããã£ãŠããããæ€èšããå¿ èŠããããæ€èšã®çµæãé é»ç·å»¶é·æ¹åŒã®é» åã³ã¹ã㯠19.8ï¿ /kWh ãã 32.2ï¿ /kWh ãŸã§å¹ ãããããšãåãã£ããç¹ã«ãæèœèŠæš¡ã® å°ããå Žåãé é»ç·å»¶é·è·é¢ã®é·ãå Žå㯠25ï¿ /kWh ãäžåãå ŽåãåºçŸããããããã®é é»ç·å»¶é·æ¹åŒã«ããé»åã³ã¹ãã®é«ã Barangay ã«ã€ããŠã¯åçå¯èœãšãã«ã®ãŒå©çšã®ç¬ç« 系統ã«ããé»åæ¹åŒã競äºåãæããå Žåããããã®ãšèããããã - 101 - 5.4 åçå¯èœãšãã«ã®ãŒã«ããé»åèšç»ãšã³ã¹ãæ³å® 5.4.1 ãã€ã¯ãæ°Žåã«ããé»åèšç»ãšã³ã¹ãæ³å® 5.2 ã§è¿°ã¹ãããã«æèœé»åã«ããé»åéèŠã¯ããŒã¯æã§çŽ 10kWãããŒã¹æã§çŽ 5kW 㧠ãããããããã€ã¯ãæ°Žåã«ããçºé»ãè¡ãå Žåããã¹ãŠããŸããªãããšãåæã«çºé»æ ã建èšãããšãåºå 10kW ã®çºé»èšåãå¿ èŠãšãªãããã®å ŽåãéããŒã¯æã«ã¯èšåãæå¹ å©çšãããªãããšãããèšåå©çšç㯠46.8%ãšãªãã10ïœW ã®çºé»ã«å¿ èŠãªãšãã«ã®ãŒæºãš ããŠã¯ãæµé 0.2 m3/sãèœå·® 7ïœçšåºŠã®ããã³ã·ã£ã«ãå¿ èŠã§ãããä»æ¹ãé»åéèŠã®ãã¡ ããŒã¹åã®ã¿ãæ°Žåçºé»ã«ããè² æ ãããšèããå Žåã¯ã5kW ã®çºé»èšåã®èšçœ®ãé©åã§ã ãããã®å Žåãèšåå©çšç㯠66.5%ã«ãªãã5ïœW ã®çºé»ã«å¿ èŠãªãšãã«ã®ãŒæºãšããŠã¯ã æµé 0.1 m3/sãèœå·® 7ïœçšåºŠã®ããã³ã·ã£ã«ãå¿ èŠãšãªãã æ°Žåçºé»èšåã«ããé»åã³ã¹ãã¯æ¬¡ã®èŠçŽ ãããªããããªãã¡ã â æ°Žè»ã»çºé»æ©ã®èšçœ®ã«èŠããè³æ¬è²»ïŒå»ºèšè²»èŸŒã¿ïŒ â¡é é»ç·ïŒ240V ã«ããäœå§é é»ãåæãšããïŒèšçœ®ã«èŠããè³æ¬è²» â¢æ°Žè»ã»çºé»æ©ãé é»ç·çã®ç¶æ管çè²»ïŒO&M è²»ïŒ â£é転å¡è²»çš ãã®ãã¡ã â ã«é¢ããŠã¯ãæ°Žè»å䟡ã 8,000ïŒ/kW ãšæ³å®ããããã«èçšå¹Ž 45 幎ãå²åŒç 12% ãçšããŠç®åºãã幎çµè²»ç 0.1078 ãçšããŠå¹Žçµè²»æç®ããã â¡ã«é¢ããŠã¯ãé é»ç·å»¶é·æ¹åŒã®å Žåãšåæ§ã®å䟡ãçšãç®åºããã â¢ã«é¢ããŠã¯ãæ°Žè»ã»çºé»æ©ãé é»èšåã®ç¶æ管çè²»ã¯å¹Žéã«å»ºèšè²»ã® 1.5%çžåœ é¡ãå¿ èŠã§ãããã®ãšããã â£ã«é¢ããŠã¯ãé転å¡ïŒåã絊äžæé¡ 4,000 ããœãšæ³å®ããã ãããã®çµè²»ãåçããæ¶è²»è ã®å¹Žéé»å䜿çšéã§é€ãããšã§ããã€ã¯ãæ°Žåå©çšæ¹åŒ ã«ããé»åã®é·æéçè²»çšïŒLRMCïŒãæ±ããããã10ïœW ã®èšåãèšçœ®ããŠãã¹ãŠã®éèŠã æ°Žåã®ã¿ã§ãŸããªãæ¹åŒã®å Žåã®é»åã³ã¹ã㯠27.7ï¿ /kWh ãšè©Šç®ãããããŸãã5kW ã®ã ãŒã¹å¯Ÿå¿ã®çºé»èšåãèšçœ®ããããŒã¹è² è·ã®ã¿ããŸããªãå Žå㯠22.1ï¿ /kWh ãšè©Šç®ãããã ãªããHCAAP èšç»ã«ããæŽåãããçæŒæ°Žè·¯ã«ãããæ°Žåããã³ã·ã£ã«ã¯æŠã 5kW çšåºŠãš å€æããããã®ããã10ïœW ã®ãšãã«ã®ãŒæºç¢ºä¿ã®èŠ³ç¹ããã¯å°é£ã䌎ããã®ãšèããããã 5.4.2 ãã€ãªã¬ã¹å©çšã«ããé»åèšç»ãšã³ã¹ãæ³å® ãã£ãªãã³ã§ã¯è±ãçãé¶ãªã©ã®å®¶çç³ãã¡ã¿ã³çºé µããŠåŠçããã·ã¹ãã ãæ¢ã«åæ¥ å©çšæ®µéã«ããããããã®æè¡ã¯ç°å¢é¢ãã家çç³åŠçæè¡ãšããŠå©çšãããŠããããçº çããã¡ã¿ã³ã¬ã¹ããšãã«ã®ãŒé¢ããæå¹å©çšããããšãè¡ãããŠãããDOE ã«ãããšã倧 å°æ§ã ãªå®¶çç³ã®åŠçã·ã¹ãã ããã£ãªãã³å šäœã§ 650 ã«æ以äžã«ãããå°å ¥ãããŠãã ãšã®ããšã§ããã倧èŠæš¡å©çšã®ä»£è¡šäŸãšããŠã¯ãèŸ²å° 40Haãè± 6 äžé ã飌è²ããæ°éäŒæ¥ ã§ãã Maya èŸ²å Žã§ãçºé µã¡ã¿ã³ãå©çšããçºé»ãè¡ããå Žå ã®ç §æãå·èµåº«ãªã©ã«å©çšã ãŠããäºäŸãããããŸãã蟲家ã«ããå°èŠæš¡é£Œè²ã®å Žåã«ã¯ã³ã³ã¯ãªãŒã補ã®ç°¡ææ¶å槜 ãæšå¥šãããŠããããã®ãããªå®¶çç³åŠçæ¶å槜ã®ã¡ãŒã«ãŒã¯ãã£ãªãã³åœå ã« 9 瀟ã»ã© ååšããŠããããã§ããã - 102 - è¿å¹Žããã£ãªãã³åœå ã§ã¯è±ç³ã®ã¡ã¿ã³çºé µåŠçäºæ¥ã CDM äºæ¥ãšããŠèšç»ããäºäŸã å¢å ããŠããããã®ããã«è±ç³åŠçã«ãããã€ãªã¬ã¹çºé»ã¯æè¡çã«å®çšæ®µéã«å ¥ã£ãŠã ããCatubig çºã«ãããŠãè±ã®é£Œè²ã¯äžè¬ã«è¡ãããŠãããä»åŸãHCAAP èšç»ã®é²å±ã«äŒŽ ã蟲家ã®æåŸæ°Žæºã®åäžãå³ãããå Žåãå蟲家ãå¯æ¥ãšããŠè±ã®é£Œè²æ°ãå¢å ãããã ãšã¯å€§ãã«èããããã·ããªãªã§ããããã®ãããããã§ã¯åçå¯èœãšãã«ã®ãŒãšããŠè± ç³å©çšã«ãããã€ãªã¬ã¹çºé»ãæ€èšããã ãã®ãã€ãªã¬ã¹å©çšã«ããçºé»ãè¡ãå Žåããã€ã¯ãæ°Žåã®å Žåãšåæ§ã«ããã¹ãŠã㟠ããªãããšãåæã«çºé»æã建èšãããšãåºå 10kW ã®ãã€ãªã¬ã¹çºé»èšåãå¿ èŠãšãªãã ãã®å Žåãèšåå©çšç㯠46.8%ãšãªãã 10ïœW ã®çºé»ã«å¿ èŠãªãšãã«ã®ãŒæºãšããŠã¯ãè± 1,800 3 é ã容é 3,600m çšåºŠã®ãã€ãªã¬ã¹çºçæ¶å槜ããã€ãªã¬ã¹çºçé 100 m3/æ¥ã®èšåãšè±é£Œ è²æ°ãå¿ èŠã§ããã ä»æ¹ãé»åéèŠã®ãã¡ããŒã¯åã®ã¿ããã€ãªã¬ã¹çºé»ã«ããè² æ ãããšèããå Žåã¯ã 5kW ã®ãã€ãªã¬ã¹çºé»èšåã®èšçœ®ãé©åã§ããããã®å Žåãèšåå©çšç㯠11.9%ãšå°ãªãã ã®ã§ããããã¬ã¹ãã«ããŒã®å©çšã«ããè±é£Œè²æ°ã¯ 500 é ã容é 1,000 m3 çšåºŠã®ãã€ãªã¬ ã¹çºçæ¶å槜ããã€ãªã¬ã¹çºçé 28 m3/æ¥çšåºŠã®èšåã§ããããšãšãªãã ãã€ãªã¬ã¹çºé»èšåã«ããé»åã³ã¹ãã¯æ¬¡ã®èŠçŽ ãããªããããªãã¡ã â ãã€ãªã¬ã¹çºçèšåã®èšçœ®ã«èŠããè³æ¬è²»ïŒå»ºèšè²»èŸŒã¿ïŒ â¡ã¬ã¹ãšã³ãžã³ã»çºé»æ©èšçœ®ã«èŠããè³æ¬è²»ïŒå»ºèšè²»èŸŒã¿ïŒ â¢é é»ç·ïŒ240V ã«ããäœå§é é»ãåæãšããïŒèšçœ®ã«èŠããè³æ¬è²» â£ãã€ãªã¬ã¹çºçèšåãã¬ã¹ãšã³ãžã³ã»çºé»æ©ãé é»ç·çã®ç¶æ管çè²»ïŒO&M è²»ïŒ â€é転å¡è²»çš ãã®ãã¡ã â ã«é¢ããŠã¯ãCIGER è£ çœ®å»ºèšè²»å䟡ã 7.4ïŒ/m3 ãšæ³å®ããããã«èçšå¹Ž 20 幎ãå²åŒ ç 12%ãçšããŠç®åºãã幎çµè²»ç 0.1195 ãçšããŠå¹Žçµè²»æç®ããã â¡ã«é¢ããŠã¯ãã¬ã¹ãšã³ãžã³ã»çºé»æ©èšçœ®è²»ã«å¯Ÿããâ ãšåæ§ã«å¹Žçµè²»ç 0.1195 ãçš ã幎çµè²»æç®ããã â¢ã«é¢ããŠã¯ãé é»ç·å»¶é·æ¹åŒã®å Žåãšåæ§ã®å䟡ãçšãç®åºããã â£ã«é¢ããŠã¯ãCIGER è£ çœ®ãã¬ã¹ãšã³ãžã³ã»çºé»æ©ãé é»èšåã®ç¶æ管çè²»ã¯å¹Žéã«å»º èšè²»ã® 2.0%çžåœé¡ãå¿ èŠã§ãããã®ãšããã â€ã«é¢ããŠã¯ãéè»¢å¡ 2 åã絊äžæé¡ 4,000 ããœãšæ³å®ããã ãããã®çµè²»ãåçããæ¶è²»è ã®å¹Žéé»å䜿çšéã§é€ãããšã§ããã€ãªã¬ã¹çºé»æ¹åŒã« ããé»åã®é·æéçè²»çšïŒLRMCïŒãæ±ããããã10ïœW ã®èšåãèšçœ®ããŠãã¹ãŠã®éèŠãã ã€ãªã¬ã¹çºé»ã®ã¿ã§ãŸããªãæ¹åŒã®å Žåã®é»åã³ã¹ã㯠20.5ï¿ /kWh ãšè©Šç®ãããããŸãã 5kW ã®ããŒã¯å¯Ÿå¿ã®çºé»èšåãèšçœ®ããããŒã¯è² è·ã®ã¿ããŸããªãå Žå㯠41.5ï¿ /kWh ãšè©Š ç®ãããããã®çµæã10kW ã®ãã€ãªã¬ã¹çºé»ã«ããé»åéèŠããã¹ãŠè³ãæ¹åŒã§é»åãã å Žåãé»åã³ã¹ãã¯é é»ç·å»¶é·æ¹åŒãšåã¬ãã«ã§ãããšèãããããããããå¿ èŠãšãªã è±ç³ãéãããã 1,800 é ãšãã飌è²æ°ã®ç¢ºä¿ã«èª²é¡ãæ®ããã®ãšèããããã - 103 - 5.4.3 籟殻çºé»ã«ããé»åèšç»ãšã³ã¹ãæ³å® HCAAP èšç»ã«ããåœå°ã®èŸ²æ¥çç£æ§ã¯åŸæ¥ã®çš²äœåäœçç£é 1 ãã³/ha æªæºãã 5 ãã³/ha ãžãšå€§å¹ ã«æ¹åããããšãæåŸ ãããŠããããã®çµæ倧éã«çãã籟殻ãé»åã«å©çšãã ããšãæ€èšã«å€ããããã£ãªãã³ã§ã¯ç±Ÿæ®»ã¯å®¶åºèª¿ççšãªã©ã«å°èŠæš¡ã«å©çšããããšã¯ã ã£ãŠãã倧èŠæš¡ã«å©çšããäºäŸã¯ãŸã ãªããDOE ã«ãããšçŸåšãBulacan å·ã§ 35MW ã®ç±Ÿæ®» çºé»ãããŸããNueva Ecija å·ã§ 25-30MW ã®ç±Ÿæ®»çºé»ãèšç»ãããŠãã段éã§ããã 籟殻çºé»ãæ€èšããå ŽåãåŸæ¥ã®æè¡ã§ãããã€ã©ãŒåã³èžæ°çºé»ãå©çšããå Žåãèš å容éãã©ãããŠã倧èŠæš¡ã«ãªã£ãŠããŸããäºå®ãäžèšã®èšç»äžã®äºäŸã 25-35MW ã¯ã©ã¹ ã§ããããŸããã¿ã€ã§çšŒåäžã®ç±Ÿæ®»çºé»ã 10MW∼20MW ã¯ã©ã¹ã§ããããã®ãããªå€§èŠæš¡ã® çºé»èšåãèšçœ®ããå Žåã倧éã®ç±Ÿæ®»ãå¹ççã«åéããã·ã¹ãã ãå¿ èŠãšãªãããHCAAP èšç»ã«ãããŠã¯ãã®ãããªç±Ÿæ®»åéã·ã¹ãã ïŒäŸãã°å€§èŠæš¡ãã¹ãããŒãã¹ãæœèšã®å»ºèšïŒ ãèšç»ãããŠããªãçŸç¶ã§ã¯æèœé»åã®é»æºãšããã«ã¯é©åœãšã¯èšããªãã çŸåšãå°èŠæš¡ãªãã€ãªãã¹çæãæå¹å©çšããæè¡ãšããŠã¹ã¿ãŒãªã³ã°ãšã³ãžã³ãæ³šç® ããå§ããŠãããã¹ã¿ãŒãªã³ã°ãšã³ãžã³ãšã¯ã¬ãœãªã³ãšã³ãžã³ããã£ãŒãŒã«ãšã³ãžã³ãªã© ã®ããã«ã·ãªã³ããŒå ã§çæãçãããŠãã¹ãã³ãé§åããããããå çæ©é¢ãšã¯ç°ãªãã ã·ãªã³ããŒå ã®æ°äœã«å€éšããç±ãå ãèšåŒµãããããšã«ãããã¹ãã³ãé§åããããã ãå€çæ©é¢ã§ãããçŸåšã軞åºå 5 銬åãçºé»åºå 3kW çšåºŠã®å°èŠæš¡ãªã·ã¹ãã ãå®èšŒæ®µ éã«ãããä»å調æ»ã®å¯Ÿè±¡ãšãªãå°èŠæš¡ Barangay ã®é»åã«ã¯é©åãªèŠæš¡ã§ããããããã ã§ã¯ç±Ÿæ®»ããã®ã¹ã¿ãŒãªã³ã°ãšã³ãžã³ãå©çšããŠé»åã«å©çšããå¯èœæ§ãæ€èšããã ãã®ã¹ã¿ãŒãªã³ã°ãšã³ãžã³ç±Ÿæ®»çºé»ãè¡ãå Žåãã§ããã ãèšåå©çšçãé«ããããšã çµæžæ§ãé«ããããã§æå©ã«ãªããããçºé»åºå 3.3ïœW ã®èšåã 3 åºå°å ¥ãåèš 10kW ã® èšåãšãããã®ãšããããã®å Žåãèšåå©çšç㯠46.8%ãšãªããã¹ã¿ãŒãªã³ã°ãšã³ãžã³ã®ä» æ§ãã«ç€ºãããŸãã10ïœW ã®çºé»ã«å¿ èŠãªç±Ÿæ®»éãšããŠã¯å¹Žé 180 ãã³ãšæšèšããããã㯠HCAAP èšç»ã«ããæŽåãããèŸ²å° 130ha ããçãã籟殻éã«çžåœããã ã¹ã¿ãŒãªã³ã°ãšã³ãžã³ç±Ÿæ®»çºé»ã«ããé»åã³ã¹ãã¯æ¬¡ã®èŠçŽ ãããªããããªãã¡ã â ã¹ã¿ãŒãªã³ã°ãšã³ãžã³ã»çºé»æ©èšçœ®ã«èŠããè³æ¬è²»ïŒå»ºèšè²»èŸŒã¿ïŒ â¡ç±Ÿæ®»è²¯èµåº«å»ºèšã«èŠããè³æ¬è²» â¢é é»ç·ïŒ240V ã«ããäœå§é é»ãåæãšããïŒèšçœ®ã«èŠããè³æ¬è²» â£ã¹ã¿ãŒãªã³ã°ãšã³ãžã³ã»çºé»æ©ãé é»ç·çã®ç¶æ管çè²»ïŒO&M è²»ïŒ â€é転å¡è²»çš ãã®ãã¡ã â ã«é¢ããŠã¯ãçŸåšãã¹ã¿ãŒãªã³ã°ãšã³ãžã³ã¯å®èšŒè©Šéšäžã§ããåæ¥äŸ¡æ Œãèšå®ãã ãŠããªãããã®ããæ«å®å€ãšããŠïŒåº 35,000ïŒãšæ³å®ãããããã«èçšå¹Ž 20 幎ãå² åŒç 12%ãçšããŠç®åºãã幎çµè²»ç 0.1195 ãçšããŠå¹Žçµè²»æç®ããã â¡ã«é¢ããŠã¯ã5,000ïŒãšæ³å®ããâ ãšåæ§ã«å¹Žçµè²»ç 0.1195 ãçšã幎çµè²»æç®ããã â¢ã«é¢ããŠã¯ãé é»ç·å»¶é·æ¹åŒã®å Žåãšåæ§ã®å䟡ãçšãç®åºããã â£ã«é¢ããŠã¯ãã¹ã¿ãŒãªã³ã°ãšã³ãžã³ã»çºé»æ©ãé é»èšåã®ç¶æ管çè²»ã¯å¹Žéã«å»ºèš - 104 - 費㮠2.0%çžåœé¡ãå¿ èŠã§ãããã®ãšããã â€ã«é¢ããŠã¯ãéè»¢å¡ 3 åã絊äžæé¡ 4,000 ããœãšæ³å®ããã ãããã®çµè²»ãåçããæ¶è²»è ã®å¹Žéé»å䜿çšéã§é€ãããšã§ãã¹ã¿ãŒãªã³ã°ãšã³ãžã³ 籟殻çºé»æ¹åŒã«ããé»åã®é·æéçè²»çšïŒLRMCïŒãæ±ãããããããã«ãããš 10ïœW ã®èš åãèšçœ®ããå Žåã®é»åã³ã¹ã㯠47.1ï¿ /kWh ãšè©Šç®ãããããã®äŸ¡æ Œã¯ä»ã®æ¹åŒã«ããé» åã³ã¹ãããé«ããã®ãšãªã£ãŠããããã¹ã¿ãŒãªã³ã°ãšã³ãžã³ã®äŸ¡æ Œãæ«å®çã«èšå®ãã ããã§ãããä»®ã«ã¹ã¿ãŒãªã³ã°ãšã³ãžã³ãæ®åããäŸ¡æ ŒãïŒåº 10,000ïŒçšåºŠãŸã§äœäžãã ãšããã°ããã«ããé»åã³ã¹ã㯠20ï¿ /kWh çšåºŠãŸã§å€§å¹ ã«äœäžãããããã¯é é»ç·å»¶é·ã« ããé»åã³ã¹ããšéè²ãªãã¬ãã«ã§ãããã¹ã¿ãŒãªã³ã°ãšã³ãžã³ã®å®çšåãæ®åã倧ãã« æåŸ ããããã®ã§ããã 5.4.4 ãã€ã¯ãæ°Žåãšãã€ãªã¬ã¹ã®ãã€ããªããçºé»ã«ããé»åèšç»ãšã³ã¹ãæ³å® 5.4.1 åã³ 5.4.2 ããã50 äžåž¯ã®æšæº Barangay ããã€ã¯ãæ°Žåã®ã¿ã§é»åããã ãã®æ°Ž åããã³ã·ã£ã«ã¯ãã®å°ã§ã¯ããŸãæåŸ ã§ããªãããŸããè±ç³ãã€ãªã¬ã¹ã®ã¿ãå©çšã㊠é»åããã ãã®è±é£Œè²æ°ãæåŸ ã§ããªãç¶æ ã§ãããä»æ¹ãæè¡çç¹æ§ãšããŠãã€ã¯ãæ°Ž å㯠24 æéã®çºé»ãå¯èœã§ãããè±ç³ãã€ãªã¬ã¹ã¯ã¬ã¹ãã«ããŒãå©çšããããšã§ã¬ã¹ã ããå¿ èŠãªãšãã«çºé»ãå¯èœã§ããããã®ãããäž¡è ãçµã¿åããããã€ã¯ãæ°Žåãã㌠ã¹é»æºãšããŠãè±ç³ãã€ãªã¬ã¹çºé»ãããŒã¯é»æºãšããŠçµã¿åããããã€ããªããã·ã¹ã ã ãæ€èšããã 5kW ã®ãã€ã¯ãæ°Žåãš 5kW ã®è±ç³ãã€ãªã¬ã¹çºé»ãçµã¿åãããŠæèœé»åãè¡ã£ãå Žåã 建èšã«èŠããç·ã³ã¹ãã¯çŽ 61,600ïŒãšæ³å®ãããããŸãæ¢ã«åç¯ã§ç€ºããæ¹æ³ã«ãã幎é ã®å¿ èŠçµè²»ãè©Šç®ãããšçŽ 10,400ïŒãšè©Šç®ããããããã幎éã®å©çšå¯èœé»åé 41.0ïŒïŒ· ïœã§é€ãããšã§ãã®ãã€ããªããæ¹åŒã®é»åã³ã¹ãïŒé·æéçè²»çšïŒã¯ 25.4ï¿ /kWh ãšè©Šç® ãããã 5.4.5 åçå¯èœãšãã«ã®ãŒã«ããé»å察象 Barangay ã®æœåº 5.3 ã§æ€èšããããã«é é»ç·å»¶é·æ¹åŒã«ããé»åã³ã¹ãã¯æŠã 20ï¿ /kWh∼32ï¿ /kWh ã§ã ã£ãããäžã«ã¯ 25ï¿ /kWh ãè¶ãã Barangay ãååšãããä»æ¹ããã€ã¯ãæ°Žåãšè±ç³ã〠ãªã¬ã¹çºé»ãçµã¿åãããåçå¯èœãšãã«ã®ãŒçºé»ã«ããé»åã®å Žåãé»åã³ã¹ãã¯æŠã 25ï¿ /kWh çšåºŠã§ããããšãå€æããããã®ããšãã以äžã® 7 Barangay ããã®ã·ã¹ãã ã®å° å ¥å¯èœæ§ã®ããå°åãšãããã è¡š−5 é»å察象 Barangay Barangay äººå£ äžåž¯æ° Palanas 164 35 Rufino 200 35 Tangan-ayan 316 60 Epaw 259 44 San Jose 179 36 San-od 188 33 San Antonio 228 45 - 105 - ïŒ. åçå¯èœãšãã«ã®ãŒã«ããå°æ¹é»åèšç» 6.1 ãã€ã¯ãæ°Žåããã³ã·ã£ã« HCAAP èšç»ã¯ãCatubig Sercvice Area(3,565.5ha)ãBulao Service Area (742.2ha)ã Hagbay Service Area(665.3ha) ã®ïŒå°åã®çæŒèšç»ãããªã£ãŠããããã®ãã¡ãä»åã Catubig Sercvice Area ã«é¢ããçæŒçšæ°Žè·¯ã®æ°Žéåã³æ°Žè·¯èœå·®ã®ããŒã¿ãå ¥æã§ãããã ãããå€æããããã€ã¯ãæ°Žåã®ããã³ã·ã£ã«ã¯ãè¡š−6 ã®éãã§ããã ãã®çµæãåç« ã§æ€èšããåçå¯èœãšãã«ã®ãŒå©çšã®å¯èœæ§ããã Barangay ã®ãã¡ã PalanasãTagan-ayanãEpawãSan Jose ã®ïŒBarangay ã«ãããŠããã€ã¯ãæ°Žåãå©çšã§ ããå¯èœæ§ãããã è¡š−6 ãã€ã¯ãæ°Žåããã³ã·ã£ã« Site No. Discharge (m3/s) 1 0.11 2 0.19 3 0.19 4 0.17 5 0.24 6 0.22 7 0.10 8 0.14 Head (m) 2.6 2.8 1.5 4.5 4.2 2.0 3.0 3.4 Output (kW) 1.7 3.2 1.8 4.3 6.0 2.6 1.8 2.8 Nearest Barangay San Isidro Epaw San Jose Tagan-Ayan Tagan-Ayan Tagan-Ayan Palanas Rizal 6.2 å Barangay ã«ããããã€ããªããçºé»èšç» PalanasãTagan-ayanãEpawãSan Jose ã®ïŒBarangay ã«ã€ããŠãåç« ã®äœæžæ° 50 äž åž¯ã®æšæº Barangay ã§æ€èšããé»åéèŠãåæ§ã«çºçãããšããå Žåã®é»åéèŠãè¡š-2 ã® Demand Side æ¬ã«ç€ºãããŸãããã®éèŠã«å¯Ÿãããã€ã¯ãæ°Žåçºé»åã³ãã€ãªã¬ã¹çºé»ã« ããé»åãäŸçµŠããå Žåã®ä»æ§ãåè¡šã® Suply Side æ¬ã«ç€ºãã ããã«ãããšãPalanas Barangay ã§ã¯ãããŒã¯éèŠ 6.7ïœWãé»åééèŠïŒæ¥éïŒ78.7kWh ãæ³å®ãããããã«å¯Ÿããæ°Žè·¯ïŒçªãµã€ãã«ãã㊠1.8ïœW ã®ãã€ã¯ãæ°ŽåãæåŸ ã§ããã ãããã«ããããŒã¹éèŠãè³ããšå ±ã«ã4.9ïœW ã®äžè¶³åããã€ãªã¬ã¹çºé»ã«ããè³ãã〠ããªããçºé»èšç»ãèããããããã®å Žåãå¿ èŠãªè±é£Œè²æ°ã¯çŽ 540 é ïŒäžæžåœããçŽ 15 é ïŒã§ãããæ¶å槜ã¯å®¹é 1,100ïœ3 ã® CIGER æ¶å槜ãèšçœ®ããããšãå¿ èŠã§ããã åæ§ã« Tagan-ayan Barangay ã§ã¯ãããŒã¯éèŠ 11.5ïœWãé»åééèŠïŒæ¥éïŒ134.9kWh ãæ³å®ãããããã«å¯Ÿããæ°Žè·¯ïŒçªãµã€ãã«ãã㊠6.0ïœW ã®ãã€ã¯ãæ°ŽåãæåŸ ã§ããã ãããã«ããããŒã¹éèŠãè³ããšå ±ã«ã5.5ïœW ã®äžè¶³åããã€ãªã¬ã¹çºé»ã«ããè³ãã〠ããªããçºé»èšç»ãèããããããã®å Žåãå¿ èŠãªè±é£Œè²æ°ã¯çŽ 600 é ïŒäžæžåœããçŽ 10 é ïŒã§ãããæ¶å槜ã¯å®¹é 1,200ïœ3 ã® CIGER æ¶å槜ãèšçœ®ããããšãå¿ èŠã§ããã åæ§ã« Epaw Barangay ã§ã¯ãããŒã¯éèŠ 8.4ïœWãé»åééèŠïŒæ¥éïŒ98.9kWh ãæ³å® ãããããã«å¯Ÿããæ°Žè·¯ïŒçªãµã€ãã«ãã㊠3.2ïœW ã®ãã€ã¯ãæ°ŽåãæåŸ ã§ãããããã - 106 - ã«ããããŒã¹éèŠãè³ããšå ±ã«ã5.2ïœW ã®äžè¶³åããã€ãªã¬ã¹çºé»ã«ããè³ããã€ããªã ãçºé»èšç»ãèããããããã®å Žåãå¿ èŠãªè±é£Œè²æ°ã¯çŽ 440 é ïŒäžæžåœããçŽ 10 é ïŒã§ ãããæ¶å槜ã¯å®¹é 900ïœ3 ã® CIGER æ¶å槜ãèšçœ®ããããšãå¿ èŠã§ããã åæ§ã« San Jose Barangay ã§ã¯ãããŒã¯éèŠ 6.9ïœWãé»åééèŠïŒæ¥éïŒ80.9kWh ã æ³å®ãããããã«å¯Ÿããæ°Žè·¯ïŒçªãµã€ãã«ãã㊠1.8ïœW ã®ãã€ã¯ãæ°ŽåãæåŸ ã§ãããã ããã«ããããŒã¹éèŠãè³ããšå ±ã«ã5.1ïœW ã®äžè¶³åããã€ãªã¬ã¹çºé»ã«ããè³ããã€ã ãªããçºé»èšç»ãèããããããã®å Žåãå¿ èŠãªè±é£Œè²æ°ã¯çŽ 580 é ïŒäžæžåœããçŽ 16 é ïŒ ã§ãããæ¶å槜ã¯å®¹é 1,200ïœ3 ã® CIGER æ¶å槜ãèšçœ®ããããšãå¿ èŠã§ãããè¡š−7 ã« å Barangay ã«ããããã€ããªããçºé»ã®åºæ¬ä»æ§ã瀺ãã - 107 - Demand Side Barangay Palanas Tagan-ayan Epaw San Jose Supply Side Hydro Energy Daily Base Biogas Micro Hydro Site production by Energy Generation Potential No. Micro Hydro Demand Household s Peak Demand Base Demand Daily Energy Demand (house) (a) (kW) (b) (kW) (c) (kWh) (d) (kWh) (e) (kW) (f) 35 60 44 36 6.7 11.5 8.4 6.9 3.5 6.0 4.4 3.6 78.7 134.9 98.9 80.9 55.9 95.8 70.2 57.5 1.8 6.0 3.2 1.8 7 5 2 3 Energy Necessary Capacity of Production No. of Swine Digester by Biogas (kWh) (g) (kW) (h)=(b)-(f) (kWh) (i)=(d)-(g) (Head) (j) (m3) (k) 43.2 95.8 70.2 43.2 4.9 5.5 5.2 5.1 35.5 39.1 28.7 37.7 540 600 440 580 1,100 1,200 900 1,200 Note 1. Peak demand (b) is calculated by 9.6kW x (Households No./ 50) 2. Base demand (c) is calculated by 5.0kW x (Households No./ 50) 3. Daily energy demand (d) is calculated by 112.4 kWh x (Households No./ 50) 4. Daily base energy demand (e) is calculated by 79.8 kWh x (Households No./ 50) 5. Energy production by Micro hydro (g) is smaller number of either micro hydro potential (f) x 24h or daily base energy demand (e). 6. Biogas generation (h) is the balance of peak demand (b) and Micro hydro potential (f). 7. Energy production by biogas (i) is the balance of daily energy demand (d) and energy production by micro hydro (g). 8. Necessary No. of swine (j) is calculated by energy production by biogas (i) divided by 6.54 kWh/day/100 swine head. 9. Capacity of digester (k) is calculated by energy production by biogas (i) multipled by 31.0 m3/kWh/day. - 108 - åãµããŒã«å·å±±å²³å°åã«ãããåçå¯èœãšãã«ã®ãŒã«ããå°æ¹é»åèšç»å¯èœæ§èª¿æ» 1. ã»ã¯ã¿ãŒ é»å 2. ãããžã§ã¯ãå°ç¹ ãã£ãªãã³åœãåãµããŒã«å·ãã«ãã¥ãã° åã³ã©ã¹ããã¹å°æ¹ 3. å®æœæ©é¢ ãã£ãªãã³åœå¶ç³æ²¹å ¬ç€ŸïŒPNOC 4. èæ¯åã³ç®ç æ¬å°æ¹é»åãããžã§ã¯ãå¯èœæ§èª¿æ»ã®å¯Ÿè±¡å°åã¯æ±ããµã€ã¹å°åã®åãµããŒã«å·ã«äœçœ® ãããã£ãªãã³ã«ãããŠãæªéçºå°åã§ãããåœè©²å°åã®äžäººåœããã®åå ¥ã¯ãã£ãªãã³ å šäœå¹³åå€ã® 50ïŒ çšåºŠã§ãããåãµããŒã«å·ã®å±±å²³å°åã«ããã家å±é»åç㯠20ïŒ ä»¥äžã§ ããããšãããåå·ã§ã¯èŸ²æ¥çç£æ§ã®åäžåã³èŠ³å ç£æ¥ã®çºå±ãä¿é²ãããããé»åçã® åäžãç®æšã«æ²ããŠããã æ¬èª¿æ»ã¯ãã«ãã¥ãã°å·ãæœ æŒæœèšããã®æ°Žãå©çšãããã€ã¯ãæ°Žååã³èŸ²ç£ç©ããçº çãããã€ãªãã¹ãšãã«ã®ãŒçã®åçå¯èœãšãã«ã®ãŒã«ããå°æ¹é»åã®å¯èœæ§ãæ€èšã ããã«ãã¥ãã°æµåã«ãããŠã¯ãçŸåšå®æœãããŠããå æ¬ç蟲æ¥éçºèšç»ïŒECDPïŒã«ãã 蟲ç£ç©ã®çç£æ§åäžãæåŸ ãããŠããã 5. ãããžã§ã¯ãæŠèŠ (1) ãããžã§ã¯ãåïŒåçå¯èœïœŽïŸïŸïœ·ïŸïœ°ã«ããå°æ¹é»åèšç» (2) ãã€ããªããçºé»ã«ããæ倧åºå ïŸïŸïŸïŸïœ¶ïŸïœ² ïŸïŸïŸïŸ : P=6.7kW ïŒïŸïœ²ïœžïŸæ°Žå: 1.8kWã ïŸïŸïœ²ïœµïœ¶ïŸïœœ: 4.9kWïŒ ïŸïŸïŸïŸïœ¶ïŸïœ² ïŸïœ¶ïŸïŸïœ±ïŸïŸ: P=11.5kW ïŒïŸïœ²ïœžïŸæ°Žå: 6.0kWã ïŸïŸïœ²ïœµïœ¶ïŸïœœ: 5.5kWïŒ ïŸïŸïŸïŸïœ¶ïŸïœ² ïŸïŸïœ³: P=8.4kW ïŒïŸïœ²ïœžïŸæ°Žå: 3.2kWã ïŸïŸïœ²ïœµïœ¶ïŸïœœ: 5.2kWïŒ ïŸïŸïŸïŸïœ¶ïŸïœ² ïŸïŸïœŸ: P=6.9kWïŒïŸïœ²ïœžïŸæ°Žå: 1.8kWã ïŸïŸïœ²ïœµïœ¶ïŸïœœ: 5.1kWïŒ 6. ãããžã§ã¯ãå®æœæé å¯èœæ§èª¿æ»ããå·¥äºå®äºãŸã§çŽ 2 幎éïŒå»ºèšæéïŒ0.5 幎éïŒ 7. æåŸ ããã䟿çåã³åçè åçè ïŒ å°åäœæ° 䟿ç ïŒ å®¶çç³ã®æå¹å©çšã建èšå·¥äºã«ããéçšåµåºã é»åã«ããå°åç£æ¥ã®çºå±ãçç£æ§æ¹åã«ãã貧å°åæž 8. ç°å¢ãžã®åœ±é¿ 圱é¿ãªã 9. ãããžã§ã¯ãè²»çš çŽ 0.5 çŸäžç±³ãã« - 109 -