Regulatory incentives for smart grids demonstration and deployment in Italy, within the European framework Luca Lo Schiavo Infrastructure Division, Regulation Department, deputy director IRED 2014 Kyōto, 20 November 2014 The EU context (1/3): the 2020 European targets for RES > Share of renewables in final energy consumption in 2005 > Target in 2020 Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 2 The EU context (2/3): liberalisation and unbundling rules • Generation liberalisation: since 1999, including DG; dispatching priority for Renewable Energy Sourced (RES) generation units • Retail liberalisation: since 2007, with Universal Supply Regime for small customers that do not choose their own supplier • Unbundling of Transmission System Operator (TSO) in Italy, full ownership unbundling for Terna from 2006 (certified according 3rd energy package rules) • Unbundling of Distribution System Operator (DSO): DSOs with more than 100.000 customers can not operate as retail suppliers and must treat every supplier on a non-discriminatory basis (in Italy, Enel 32 million customers; ACEA-Rome and A2A Milan-Brescia more than 1 million customer each; other 8 DSOs with more than 100.000 customers; as a whole, DSOs > 100.000 customers distribute energy to 97% customers) • Network Codes advanced development but different voltage levels (in Italy: EHV-HV Transmission; MV-LV distribution; only exception: city of Rome) Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 3 The EU context (3/3): European Regulators cooperation • Position Paper on Smart Grids (2009) Issued for public consultation (50! contributions were received) • Conclusions paper (2010) 10 final Recommendations for National Regulators • Status Review of regulatory (2011) regulatory approaches to smart electricity grids • Second Status Review (2014) Ref: C13-EQS-57-04 Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 4 European Regulators recommendations (2010) Ensure stable regulatory framework and long-term return on investments Decouple profits and volume for grid operators Incentivise innovative solutions (demonstration pilots) Introduce output regulation: value for money of users Improve consumer awareness for energy use and market opportunities Kyōto, 20 November 2014 Distinguish grid-related versus market-related activities Perform societal cost-benefit assessment Adopt open protocols and standards for interoperability Disseminate the results and lessons learned from the demonstration projects Learn from best regulatory practices Luca Lo Schiavo, AEEGSI (Italy) 5 1. Italian power system: the impact of renewables Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 6 RES evolution due to State incentives 23,3 Puglia 19,5 +86% GW 15.9 Wind 12.7 PV Sicilia 2.4 1.9 1.0 Campania 1.2 0.5 1.7 Lombardia 1.7 1.7 Sardegna 9.3 1.4 3.9 2.8 1.6 1.9 1.6 2005 1.9 0.1 2.7 3.5 2006 2007 2008 3.5 Veneto 1.1 0.4 Calabria 4.9 5.8 2009 2010 2.9 1.0 0.5 1.5 8.6 Emilia Rom. 0.2 1.5 6,0 3.8 6.8 7.4 2011 2012 Target PAN 2020 Altre regioni 1.4 1.7 1.4 1.0 0.3 1.3 0.8 6.1 7.0 Italian Power System (2013): distributed RES 26 GW 53 GW (peak), ~20 GW (min.load, night), ~30 GW (min.load, daylight) Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 7 RES energy production (2013): 108 TWh (out of 288 TWh tot) Produzione lorda da fonti rinnovabili in Italia dal 1996 a oggi Impianti termoelettrici da biomasse e rifiuti Impianti fotovoltaici GWh Impianti eolici Impianti geotermoelettrici 95.000 Impianti idroelettrici 2013: 90.000 85.000 80.000 37 TWh wind & PV 75.000 70.000 65.000 60.000 55.000 (more than half produced by DG units connected to distribution grids) 50.000 45.000 40.000 35.000 30.000 25.000 20.000 15.000 10.000 5.000 0 1996 1997 1998 1999 Kyōto, 20 November 2014 2000 2001 2002 2003 2004 2005 2006 2007 2008 Luca Lo Schiavo, AEEGSI (Italy) 2009 2010 2011 2012 8 Impact on hourly residual load (working days) March 2010 – working days, Southern regions Hour (h) Load covered by wind and PV Kyōto, 20 November 2014 March 2013 – working days, Southern regions Apparent reduction in the morning Luca Lo Schiavo, AEEGSI (Italy) Hour (h) Steep ramps in the evening 9 Impact on wholesale prices (yearly average per hour) Rapporto trabetween il PUN medioHourly orario e il PUN medio complessivo Ratio price and PUN 1,5 1,4 1,3 1,2 PUN: electricity average price (nation-wide) 1,1 1,0 2011: 72,23 €/MWh 0,9 0,8 0,7 0,6 Anno 2010 0,5 Anno 2011 0,4 Anno 2012 0,3 Anno 2013 Impact on tariffs of the RES incentives: ~45 €/MWh 0,2 0,1 0,0 1 2 3 4 5 6 Kyōto, 20 November 2014 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Luca Lo Schiavo, AEEGSI (Italy) 2012: 75,47 €/MWh 2013: 62,99 €/MWh 2014: ≈50 €/MWh ? 10 Impact on hourly residual load (Sundays and public holidays) March 2010 – Sundays & holidays Southern regions March 2013 – Sundays & holidays Southern regions Hour (h) Hour (h) Load covered by wind and PV Kyōto, 20 November 2014 Reverse power flow (from MV to HV) Luca Lo Schiavo, AEEGSI (Italy) 11 Impact on wholesale prices: Sundays/Holydays SUNDAY 16 March 2014 average price in Italy During Sundays and Holydays the load is low, but PV generation can be very high (in proportion to the demand) if the sun is shining Source: GME (Market Operator) Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 12 Impact on power flows: DSOs’ view 900 In Italy, there are around 4.000 HV/MV transformers Numero sezioni AT/MT con inversione di flusso > 5% 800 700 600 500 Nord Centro Sud e Isole 400 TOTALE 300 200 Typical voltages: HV 132-150 kV MV 15-20 kV LV 230-380 V 100 0 2010 2011 2012 2013 REVERSE POWER FLOW TIME: % of time (hours) during which energy flows from Medium Voltage (distribution) to High Voltage (Transmission) Extremely relevant indicator of distribution criticalities Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 13 Distribution networks: possible impact on voltage profiles For the time being we do not have congestions on MV lines: RES have been connected only after due network reinforcement («fit and forget» approach) Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 14 Potential impact on system security (voltage dips on T-grid) Residual Voltage 1 p.u. 80% Vn post PV 80% Vn ante PV 0 Distance Due to reduction of rotating machines connected to Transmission grid, there is less Shortcircuit-Power available and therefore voltage dips generated at T-level have larger impact (in this simulation the spatial distribution of DG has been assumed homogeneous) Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 15 Potential impact on system security (frequency response) Scenario 2020, RSE simulation The current primary regulation band is 1.5%. Due to reduction of rotating machines, the system inertia is decreasing and the risk of cascade effects for EU-wide frequency perturbation is higher A first EU-wide incident already happened on 4th Nov. 2006: split of European synchronous area due to a RES-related problem in Northern Germany (sudden wind decrease, not meshed network for works) Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 16 2. The Italian Regulator response: connection requirements for DG Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 17 Main regulatory actions for system security (Grid Code) Connection requirement: • Voltage fault ride-through capabilities for DG units (PV and wind) • extends some existing HV rules also to the PV plants connected at the MV and LV levels • Avoid disconnection for low frequency perturbation • retrofitting of existing DG units: MV units, over 50 kW 92% achieved; LV units, over 6 kW scheduled until the end of April 2015 Distributed generation shedding: • First phase (2012-2014): only DG directly connected to Primary Station MV busbars can be disconnected in < 30 min (but: no observability) • Second phase (2015>): all DG units at MV level can be disconnected remotely through a simple but secure SMS-based device at TSO request (both new & existing DG units) • Third phase: improve observability (to be defined in next months) Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 18 Voltage fault ride-through capabilities for DG units (PV) PV plants: CEI 0-16 revised version, Terna Grid Code approved by AEEGSI 1,3 1,25 1,2 1,15 1,1 Disconnecting the plant is allowed OVRT Curve 1,0 0,9 0,85 0,8 Plants must be connected LVRT Curve Caratteristica LVRT 0,7 0,6 Zona di distacco ammesso 0,5 0,4 Disconnecting the plant is allowed 0,3 0,2 Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 2300 2200 2100 2000 1900 1800 1700 1600 1500 1400 1300 1200 1100 1000 900 800 700 600 500 400 300 200 100 0 -100 0,1 Time (ms) 19 Reduced risk in case of deep voltage dip in the grid Without new FRT requirements Kyōto, 20 November 2014 With new FRT requirements Luca Lo Schiavo, AEEGSI (Italy) 20 Frequency variation tolerance requirements for DG units Before approval of Annex A.70 to Network Code After approval of Annex A.70 to Network Code Extremely risky condition before the new requirements: if automatic load shedding was called, the effect would have be less, or even the opposite, than desired Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 21 3. The Italian Regulator initiative: smart grid demonstration projects Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 22 European Regulators recommendations (2010) Ensure stable regulatory framework and long-term return on investments Decouple profits and volume for grid operators Incentivise innovative solutions (demonstration pilots) Introduce output regulation: value for money of users Improve consumer awareness for energy use and market opportunities Kyōto, 20 November 2014 Distinguish grid-related versus market-related activities Perform societal cost-benefit assessment Adopt open protocols and standards for interoperability Disseminate the results and lessons learned from the demonstration projects Learn from best regulatory practices Luca Lo Schiavo, AEEGSI (Italy) 23 The Italian Regulator’s approach to innovation pilots • Demonstration pilot: real operations in real grid (no lab) • Regulatory attention to both effectiveness (performance) and efficiency (cost): pilots are paid by all customers…. • Transparency of the rules: procedures, evaluation methods and criteria, etc., known ex-ante • Knowledge development with the involvement and the support of the best expertise (RSE and University like Politecnico MI) • Continuous monitoring in the medium and long term: cost benefit analysis for the whole life-time of the new components • Replicability and dissemination of the best-practices • Output disclosure: because demonstration pilots are paid by all customers > results must be public (no patents) Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 24 AEEG DECISION 12/11 Focus of pilot demonstration projects active grid AEEG DECISION 5/10 AEEG DECISION 66/13 DISTR. NETWORK AUTOMATION VOLTAGE REGULATION DISTRIBUTED GENERATION wind integr. LARGE SCALE INTERMITT.GEN. V-2-G SERVICES AEEG DECISION 96/11 Kyōto, 20 November 2014 E-mobility ELECTRIC VEHICLES DR & EE ELECTRONIC METERS smart metering SMART DISPLAYS STORAGE SYSTEMS storage RECHARGING INFRASTRUCTURE MICRO GENERATION AEEG DECISIONS 292/06 393/13 631/13 MULTIUTILITY INFRASTRUCT. SMART APPLIANCES DEMAND RESPONSE DEMAND AGGREGATION AEEG CONSULTATION 232/14 Luca Lo Schiavo, AEEGSI (Italy) SMART POWER SYSTEMS 25 Requirements for smart grid demonstration pilots • Focus on MV networks: 75% of DG rated power • Active grids only: at least reverse power-flow for 1% of time from MV to HV • Real time control system at MV level: the selected MV network has to be controlled (voltage limits / anti-islanding) • Open grid: non-proprietary communication protocols only, in order to minimize interface costs for network users • Selection process with both quantitative benefit/cost ratio and qualitative score • Awarded with extra-WACC (+2%) for 12 years (“input-based”) • Dissemination: report to the Regulatory Authority every six months for selected projects, published on Regulator’s website Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 26 P-smart concept: hosting capacity in safe conditions Vcontrol HV REVERSE POWER-FLOW TIME: 1% of year PDG Smart network – latency 200 ms: + storage (regulatory issues) Psmart MV MV LV MV Smart network – latency 200 ms remote intertrip (no islanding)* Smart network – latency 10-20 s remote voltage regulation LV Min. Load Passive network: NO flow from MV to HV PDG= 0 Psmart is the increase in DG-production (PDG) that can be connected to the grid in safe conditions (voltage, currents, frequency) thanks to smart investments on the grid Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) * Very critical in Italy due to fast reclosure (400ms) for network automation 27 «in safe conditions for voltage, currents and frequency» • Power modulation: modulating active power Related to Current (thermal) limits > latency: minutes Costly solution due to loss of revenue for generators (not implemented) Including instantaneous curtailment for emergency • Voltage regulation: modulating reactive power Related to Slow Voltage Variations > latency: some tens of seconds Very low-cost solution for voltage network constraints • Intertrip: combined dialogue between DSO and DG in order to avoid inslanding in case of network fault and secure the system Related to both Frequency perturbation and fast Voltage Dips > latency hundreds of millisec • Keep alive: in case ICT layer is not available, DG rolls back in old setting in order to avoid risks (check every 1 second) Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 28 KPI approach for smart grid pilot projects evaluation Synthetic indicator IP used to assess ex-ante the expected performance of the demonstration projects Further benefits qualitative scoring Quantitative cost and main benefit indicator IP m Psmart Aj j i C EI post EI pre Psmart 8760 Kyōto, 20 November 2014 IP: priority index Aj: project benefits [point score] C: project costs [€] P-smart: increase in DG-produced electricity / hour [MW] EI-post: DG-produced electricity that can be injected in the network after the project in safe conditions [GWh] EI-pre: DG-produced electricity that can be injected in the network before the project without reverse flow [GWh] Aj: score for size, innovation, feasibility, replicability Luca Lo Schiavo, AEEGSI (Italy) 29 Selected smart grid pilot projects: Enel distrib. – Isernia Main functions tested in the Enel D. pilot (first four ones are similar to other pilots) Anti – Islanding Detection of possible islanding condition on MV Network and disconnection of relevant generators Fast MV fault Isolation Detection on isolation of MV fault sections without the tripping of the breaker at the line departure Voltage Control Participation of MV Distributed Generation to Voltage regulation on MV feeders TSO-DSO integration Measurement collection, DG production forecasting and data transmission towards TSO systems - observability Electromobility PV roof for workforce EV fleet integrated with storage system Customer awareness Large demonstration (>4000 customers) of “SmartInfo” device, a plug-in satellite of smart meter Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 30 Unbundling issues • In the pilot projects, some activities are performed by the distribution system operator (DSO) even though in a strict unbundling perspective a separate operator should be required • Examples: Electromobility: independent EV recharge provider is foreseen by the recent “AFID” (Alternative Fuels Infrastructure Directive); EV recharging should be a competitive activity Visual displays: electricity retail supplier or other retailers (e.g. telecom services) should be involved - see next section on customer awareness • Further, involvement of DG producers in pilots has been reached only on a voluntary basis (so far, requirements are only for sake of system security) - see next section on new role of DSOs Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 31 4. Regulatory incentives for Smart grids: input-based vs output-based Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 32 European Regulators recommendations (2010) Ensure stable regulatory framework and long-term return on investments Decouple profits and volume for grid operators Incentivise innovative solutions (demonstration pilots) Introduce output regulation: value for money of users Improve consumer awareness for energy use and market opportunities Kyōto, 20 November 2014 Distinguish grid-related versus market-related activities Perform societal cost-benefit assessment Adopt open protocols and standards for interoperability Disseminate the results and lessons learned from the demonstration projects Learn from best regulatory practices Luca Lo Schiavo, AEEGSI (Italy) 33 Evaluating costs and benefits on a project basis… “Many technical and economic features of the Smart Grid, Distributed Generation and Demand Response provide diffuse benefits to the customers that are hard to put a value on. [US] regulators must engage in lenghty proceedings to set methods of measuring the value and then utilities must administer them under the critical eye of regulators…” P. Fox-Penner, Smart Power, 2010 Output-based Regulation is the key progress towards «smart regulation»: efficiency and effectiveness Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 34 Output-based vs Input-based incentives: a synthesis OUTPUT-BASED INPUT-BASED • e.g. Quality of Supply • e.g. Innovation (so far) • Reliable and fair metrics: • Metrics not yet fully available key outcome indicators that must be cleansed from out-of-control effects; authoritative and enforceable guidance for data recording and auditing • Baseline (natural improvement trend): output based incentive should be related only to additional improvements on top of natural improvement trend (historically observable) • Output valuation • Demonstration projects “real networks, real voltages, real currents, real bills”; selectivity indexes for identifying critical network areas • Incentive as extra-WACC +2% for 12 years on top of ordinary WACC value of outcome should be assessed taking into consideration both customers view and societal welfare (CEER 2011 report compares VoLL values; Italy in the range 15 to 40 €/kWh-ENS) Kyōto, 20 November 2014 however, regulator needs simple cost/benefit ratios, KPI and filter tools, in order to avoid “lenghty proceedings” (differently from US) • Learning process evaluation and selection process, monitoring performance and dissemination of results; evolution in output-based regulation Luca Lo Schiavo, AEEGSI (Italy) 35 First thoughts for output-based for smart grids incentives Indicator Type of network Usability for project assessment Usability for output-based regulation Reverse Power-Flow Time Distribution Identifying critical situations due to high RESpenetration Selective filter (together with DG capacity) P-smart Distribution Measure of main smart grid benefit Possibly an output indicator (for incentive) Energy not withdrawn from renewables due to congestion Distribution or Transmission Only on a simulation basis (ex-post indicator) Possibly a disbenefit indicator (for penalty) Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 36 5. Customer awareness of its consumption behaviour Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 37 European Regulators recommendations (2010) Ensure stable regulatory framework and long-term return on investments Decouple profits and volume for grid operators Incentivise innovative solutions (demonstration pilots) Introduce output regulation: value for money of users Improve consumer awareness for energy use and market opportunities Kyōto, 20 November 2014 Distinguish grid-related versus market-related activities Perform societal cost-benefit assessment Adopt open protocols and standards for interoperability Disseminate the results and lessons learned from the demonstration projects Learn from best regulatory practices Luca Lo Schiavo, AEEGSI (Italy) 38 Selected smart grid pilot projects: Enel distrib. – Isernia Enel Info+ Kit Smart Info is based on Enel remote metering system (installed 2001-06), on the whole national territory: • plugged into one of the house electricity sockets; • univocally associated to customer’s own meter; • makes consumption data available (and local generation as well, if any). Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 39 Extremely interesting results from field sperimentation Average load profile pre- and post-usage of the kit Experimenters average gross reduction: 0.7 -7% 0.6 Post SI 0.2 Pre SI 0.1 Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 23:00 22:00 21:00 20:00 19:00 18:00 17:00 16:00 15:00 14:00 13:00 12:00 11:00 10:00 9:00 8:00 7:00 6:00 5:00 4:00 0 0:00 -4% 0.3 3:00 Experimenters net reduction: 0.4 2:00 -3% 0.5 1:00 Control group average reduction: 40 Public consultation on tools for customer awareness • Consultation paper 232/14: submitted many feedbacks • Unbundling issues: the experimental kit includes the display but this is not a device to be developed by the distributor • Proprietary issues: for the time being, 3rd party devices are not allowed by the smart meter technology currently implemented • Market issues: how to involve suppliers without distort market (there is also a different technology: optical coupling with meter) • Tariff issues: European Directive 27/2012 on Energy efficiency (currently national transposition pending): information on historical consumption “in an appropriate way and free of charge” • Innovation issues: towards the 2nd generation of smart meters (“C-band” on the Power Line Carrier for 3rd parties messages) Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 41 6. The new role of DSOs: recent European developments Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 42 Evolution of the role of DSOs • Traditional role: Grid development, operation and maintenance Connections Metering (in most EU Member States) • Role related to retail liberalization (“single-bill” model) Non discriminatory relationship with suppliers Switching process No longer commercial activities towards final customers • New role related to “resource transformation” (DG, DER) Change in network management (reverse flow, congestions) Local dispatching / ancillary services Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 43 ACER/CEER “Bridge to 2025” consultation process • To meet new demand and generation patterns, DSOs will be required to implement more active and intelligent network management, monitoring and control of their networks Active grid management • To allow for well functioning customer-centric retail markets, Data management commercial data management will increase in weight as well as in relevance and the role of DSOs has to be clarified • The TSO-DSO interface must be designed to ensure efficient information exchange for security of supply, coordinated congestion management and integrated planning System security • DSOs shall remain neutral facilitator for competitive Neutral market facilitator Kyōto, 20 November 2014 market. It has to be investigated which services could be better provided within competitive markets and which additional safeguards (or boundaries) are required to ensure that competitive market can develop. Luca Lo Schiavo, AEEGSI (Italy) 44 ACER/CEER “Bridge to 2025” main conclusions The regulatory framework must adapt to this new role of DSOs in order to: • Enable DSOs to take on the role of a neutral market facilitator; • Accompany the development of new flexibility markets to the benefit of consumers, including load control and energy usage monitoring; • • Review distribution network tariff structure in order to ensure cost recovery and focused incentives for smarter networks; Clearly define DSOs’ and TSOs’ respective roles, establishing coordination requirements. Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 45 Dispatching of local resources: a role for DSOs? In Italy: Public consultation 354/2013: • • Distinguish between system resources for global services and local resources for local services In principle 3 models are envisaged (hybrid solutions possible): 1. Centralised extended dispatching: lowering the threshold (currently 10 MVA in most cases, except Spain), TSO remains fully in charge for ancillary services, DSO role limited to local services 2. Federated central+local dispatching: lowering the threshold, DSOs play active role on their network for procurement of resources for global services, TSO accepts bids/offers from conventional plants or DSOs 3. Scheduled program at TSO/DSO interface: DSO is engaged to respect a scheduled program (nodal or zonal), but system resources are not provided to TSO Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 46 Please visit: www.autorita.energia.it www.energy-regulators.eu www.acer.europa.eu Suggested reading on the Italian case CHANGING THE REGULATION FOR REGULATING THE CHANGE Innovation-driven regulatory developments in Italy ICER Distinguished regulatory scholar Award 2012 http://www.iern.net/portal/page/portal/IERN_HOME/ICER_HOME/ABOUT_ICER/Distinguished_Scholar_Award_2012 Thank you for your attention lloschiavo@autorita.energia.it Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 47 Back-up: - lessons from pilot projects - models for local dispatching Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 48 Lesson learned from pilot projects (1/3) • The evolution can not be achieved through a single integrated solution that covers the electrical system from T&D networks to end-users • Smart grids should be considered as a set of technological solutions to customize, develop and implement according to the DSO’s needs. • The innovative applications are enabled by TLC based on a broadband “always on” technology that connects MV producers, passive customers, and the primary and secondary substations: it is the “extended substation” • Issues: prototyping and small-scale costs, interoperability, cost of telecom services Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 49 Lesson learned from pilot projects (2/3) • Interoperability: conformance to IEC 61850 is not sufficient • The communication profiles developed by each manufacturer vary: different profiles from different vendors are said to comply with the standard (!) but not 100% interoperable. • Network users (DG) can install the equipment they prefer, so the devices connected to the MV network are from many vendors. • To allow the DSO to exchange information, a data model is needed, in order to guarantee the interoperability between multivendor devices and allows the DSO to communicate with all third party devices in the extended substation • While we wait for a possible improvement in IEC technical standards (?), each DSO needs to develop his own data model today… role for national standardisation bodies Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 50 Lesson learned from pilot projects (3/3) • The power grid and the ICT layer are complementary for SGs • ICT performance: always-on and low-latency are essential • In urban contexts, the public internet infrastructure is available: pilots in these areas show that it’s fully compatible with the applications related to inter-trip, V/Q regulation, limitation/modulation of active power, even without specific agreements signed with TLC providers! • In rural areas, can new developments of the electricity network be the driver for the ICT deployment? Doubts • In order to reduce ICT costs: avoid too complex and customised protocol solutions and avoid dedicated networks • Extra-low latency might be an hurdle to large-scale efficient deployment of smart grids: is it really always needed? Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 51 Model 1. Centralised Extended Dispatching • Conventional plants connected to EHV/HV networks • RES connected to EHV/HV networks • Final customers connected to EHV/HV networks TSO • Trader (DG with rated power ≤ 1 MW) • DG connected to MV or LV networks (rated power > 1 MW) • Trader (for MV and LV final customers) DSO Local resources (fixed price) • DG connected to MV and LV networks • MV and LV final customers • DSO verifies that the power flow in the planning phase and in real time due to the participation of the DG to the Ancillary Service Market (ASM) are compliant with the capacity of the distribution network… …but constraints never occur with (costly) fit & forget approach. • DSO requires to DG units (like PV plants) some local services (e.g., voltage regulation), not in conflict with the system services Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 52 Model 2. Federated Central+Local Dispatching TSO System resources (ASM) • Conventional plants connected to EHV/HV networks • RES connected to EHV/HV networks • Final customers connected to EHV/HV networks System resources (ASM_D) DSO • Trader (DG with rated power ≤ 1 MW) • DG connected to MV or LV networks (rated power > 1 MW) Local resources • Trader (for MV and LV final customers) (ASM_D or fixed price) • TSO: accepts bids/offers from conventional plants or DSOs in order to operate the power system: solve residual congestions and create secondary and tertiary reserve at minimum costs) central dispatch. • DSO: enters into purchase and sale contracts for the tradable resources by DG (like PV plants) (ASM_D, Ancillary Service Market for Distribution network) and provides system resources to the TSO; procures the resources necessary to operate the distribution networks, while respecting all constraints (ASM_D or regulated price) Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 53 Model 3. Scheduled program at TSO/DSO interface TSO Scheduled program at TSO/DSO interface • Conventional plants connected to EHV/HV networks • RES connected to EHV/HV networks • Final customers connected to EHV/HV networks Resources to guarantee the scheduled program (ASM_D or fixed price) DSO Local resources (ASM_D or fixed price) • Trader (DG with rated power ≤ 1 MW) • DG connected to MV or LV networks (rated power > 1 MW) • Trader (for MV and LV final customers) • TSO: procures the resources necessary to operate the power system, respecting all system constraints central dispatch. • DSO: is obliged to maintain a scheduled cumulative program wrt each single HV/MV interface (nodal model) or wrt one zone that includes more HV/MV interfaces (zonal model). System resources for the TSO are not provided; procures the resources necessary to operate the distribution networks, while respecting all constraints (ASM_D or fixed price) Kyōto, 20 November 2014 Luca Lo Schiavo, AEEGSI (Italy) 54