Electrical Energy Engineering Department 1 7/4/2016 Distribution Planning This section describes the general distribution planning steps that may be taken in order to estimate the magnitude of the medium and low voltage distribution system loads to be supplied. The overall efficiency of the distribution system is as important in load energy consumption. Therefore load factor, maximum demand, diversity, losses and growth characteristics are particularly discussed. DEFINITIONS: 1- Demand or average demand: The demand of system is the load at the receiving terminals averaged over a specified interval of time’. Dr audih 2 The load may be expressed as active power (kW) or reactive power (kVAr). The period over which the demand is averaged is known as the demand interval ,the next figure load curve illustrates average hourly loads (kW) over a 24-hour period. Dr audih 3 The load curve was based on the following data Dr audih 4 2- Maximum demand (MD): MD: Is the greatest of all demands which have occurred during the specified period of time, the maximum demand may be expressed in kW, kVAr, etc. Dr audih 5 3- Demand factor ()ﻣﻌﺎﻣل اﻟطﻠب DF : Is the ratio of the maximum demand of a system to the total connected load of the system 4- Utilization factor (UF) The utilization factor is the ratio of the maximum demand of a system to the rated capacity of the system, UF indicates the degree to which the system is being loaded during peak load periods with respect to its capacity Note: Both the maximum demand and the total connected load should be expressed in the same units thus making the demand factor dimensionless. Dr audih 6 5 -Load factor (LDF) ()ﻣﻌﺎﻣل اﻟﺣﻣل LDF: is the ratio of the average load over a designated period of time to the peak load occurring in that period The load factor indicates the degree to which the peak load is sustained during the period. For the figure sample 24-hour period before Dr audih 7 6- Diversity factor (DF)()ﺗﻧوع اﻻﺣﻣﺎل DF: is the ratio of the sum of the individual maximum demands of the various subdivisions of a system to the maximum demand of the whole system. Loads do not normally all peak at the same time. The sum of the individual peak loads will therefore inevitably be greater than the peak load of the composite system Dr audih 8 From Figure Dr audih 9 7- Coincident factor (CF) ()ﺗﻣﺎﺛل اﻻﺣﻣﺎل The reciprocal of the diversity factor is known as the coincident factor The coincident factor is dependent upon the type of loads connected to the system. Typically: In general, and in the absence of other data: n-is the number of loads connected to the system Dr audih 10 8- Load diversity( )ﺗﻧوع اﻻﺣﻣﺎل Load diversity is the difference between the sum of the peaks of two or more individual loads and the peak of the combined load. Referring to Figure 9- Loss factor (LSF)()ﻣﻌﺎﻣل اﻟﻔﺎﻗد LSF: is the ratio of the average power loss to the peak load loss, during a specified period of time. Since power losses are proportional to the square of the load current: Dr audih 11 From the simple average hourly load variation and square of the hourly demand patterns shown in Figures befor Dr audih 12 Although loss factor cannot generally be expressed in terms of load factor, the limiting values of the relationship may be established and this is illustrated in Figures. Dr audih 13 In more general terms if: x peak load of duration, t yminimum load of duration (Tt) Dr audih 14 Dr audih 15 Thus if the load remains at its peak value all the time that it is on, and zero for the remainder of the time period, then the loss factor (LSF) is equal to the load factor (LDF). Further, if the following assumptions are considered: Dr audih 16 then rewriting equation above and applying these assumptions and comparing with equation above: The loss factor cannot be determined directly from the load factor because the loss factor is determined from the losses as a function of time, which in turn are proportional to the time function of the square of the load. However, a relationship has been calculated which gives a reasonable value of the 30-minute, monthly, kW loss factor in terms of the corresponding load as shown graphically in Figure. Dr audih 17 In general: Dr audih 18 10- Load duration()ﻓﺗرة اﻻﺣﻣﺎل LD: is the relationship of demands and the duration of the demands over a specified time period. Referring to Figure the hourly demands have been sorted from grater to lower order and tabulated in Table as shown below to give: Dr audih 19 11 -Loss equivalent hours Loss equivalent hours are the number of hours of peak loads which will produce the same total losses as is produced by the actual loads over a specified period of time. Both the actual and peak demand values must be chosen from the associated load duration: Dr audih 20 With reference to the load duration and loss table Dr audih 21 Load duration and loss table (for the peak day described in Figure Dr audih 22 The loss equivalent hours are also referred to as the ‘Equivalent peak loss time’ (EPLT). An alternative method of calculating this is: Dr audih 23 12- Peak responsibility factor (PRF) The peak responsibility factor represents the contribution a component makes to the system demand losses at the time of system peak demand. Dr audih 24 Dr audih 25 It should be noted that no-load losses are continuous and occur both during system peak demand and at other times. Generation therefore had to be designed to support these no-load losses. Load losses vary with the load such that peak losses on a particular component of the overall distribution system occur at peak load on that component which may not be at the same as the overall system peak demand. Only a fraction of the individual component losses therefore contribute to the system peak demand. Dr audih 26 Aerial Bundled Conductor (ABC) A distribution systems the Aerial Bundled Conductor(ABC) is used ,why?. -To improving consumer supply reliability. -The cost of ABC quite naturally. -The limiting factor is volt drop, this being determined by the line reactance. The capital costs per unit length for ABC are approximately twice that for bare-wire. Dr audih 27 Currents in various distribution station bus-bar voltages calculation sections and Example: 3-phase ring main ABCD fed at A at 11 kV supplies balanced loads of 50 A at 0.8 p.f. lagging at B, 120 A at unity p.f. at C and 70 A at 0·866 lagging at D, the load currents being referred to the supply voltage at A. The impedances of the various sections are : Section AB = (1 + j 0·6) Ω; Section BC = (1·2 + j 0·9) Ω Section CD = (0·8 + j 0·5) Ω; Section DA = (3 + j 2) Ω Calculate the currents in various sections and station bus-bar voltages at B, C and D. Dr audih 28 Solution. shows one phase of the ring main. The problem will be solved by Kirchhoff’s laws. Let current in section AB be (x+ j y). Dr audih 29 Dr audih 30 Applying Kirchhoff’s voltage law to mesh ABCDA, we have, Drop in AB+ Drop in BC + Drop in CD+ Drop in DA= 0 or [(x −0·6y) + j(0·6x+ y)] + [(1·2x −0·9y −75) + j(0·9x+ 1·2y)]+ [(0·8x −0·5y −143) +j(0·5x+ 0·8y −56)] + [(3x −2y −791·8) + j(2x+ 3y −246·2)] = 0 or (6x −4y −1009·8) + j(4x+ 6y −302·2) = 0 As the real (or active) and imaginary (or reactive) parts have to be separately zero, ∴ 6x −4y −1009·8 = 0 and 4x+ 6y −302·2 = 0 Solving for x and y, we have, x = 139·7 A ; y= −42·8 A Dr audih 31 Current in section AB =(139·7 − j42·8) A Current in section BC =(x −40) + j(y+ 30) = (139·7 −40) + j(−42·8 + 30) =(99·7 − j12·8) A Current in section CD =(x −160) + j(y+ 30) = (139·7 −160) + j(−42·8 + 30) =(−20·3 − j12·8) A Current in section DA =(x −220·6) + j(y+ 65) = (139·7 −220·6) + j(−42·8 + 65) =(−80·9 + j 22·2) A Dr audih 32 **Note : In stead of the current in example ,the power may be given and we need to calculate the impedance of the conductor in order to designate the cross-section needed. Dr audih 33 REVIEW QUESTIONS 1. Discuss why: (a)All ac transmission and distribution systems are 3 phase systems. (b) The transmission systems are mostly overhead systems. (c) All overhead lines use ACSR conductors. (d) Overhead line conductors are invariably stranded. 2. Give reasons: (a) The transmission lines are 3 phase 3 wire circuits while distribution lines are 3 phase 4 wire circuits. (b) It is necessary to use high voltages for transmission systems. (c) At 400 kV and above the transmission lines have bundled conductors. (d) The tendency of corona formation is lesser in aluminum conductor lines than in copper conductor lines. (e) The voltage drop is a very important consideration in distribution lines but not so important in transmission lines. 3.Draw a single line diagram showing the essential parts in a modern power system network. 4.Bring out the relative advantages and disadvantages of overhead and underground systems. 5. Write a short note on 'overhead line conductors' bringing out the reasons for using ACSR conductors. 6.What is a bundled conductor? Why is it used? Give a few configurations of such conductors commonly employed. Dr audih 34