GENERATOR INTERCONNECTION REQUEST BHBE-G7 Interconnection System Impact Study PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING August 21, 2008 Executive Summary Black Hills Power conducted an Interconnection System Impact Study (SIS) under the guidance of the Common Use System (CUS) Joint Open Access Transmission Tariff Large Generator Interconnection Procedures (LGIP) for the interconnection customer to construct and interconnect a 200 MW wind farm in northeast Wyoming. The proposed project consists of one hundred thirty-four (134) 1.5 MW GE wind turbine generators and will connect to the CUS 230 kV transmission system at the Pumpkin Buttes substation in Campbell County, Wyoming. The initial interconnection date for the project is September 2010. The SIS was performed based upon the information set forth in the signed LGIP Interconnection System Impact Study agreement dated April 30, 2008. The purpose of the study was to: (i) Analyze the steady-state and short circuit conditions for the project (ii) Evaluate transient stability performance (iii) Determine any upgrades to the transmission system that would be required to mitigate any adverse impacts that the proposed project could otherwise pose on the reliability and operating characteristics of the transmission system. The primary area of concern for this study is northeast Wyoming. The proposed project is to be interconnected at the existing Pumpkin Buttes 230 kV substation. The project was evaluated as both an Energy Resource and as a Network Resource. Steady-State Analysis Steady-state voltage and thermal analysis examined system performance without the proposed project in order to establish a baseline for comparison. System performance was re-evaluated with the project in place and compared with the baseline performance to demonstrate the impact of the project on local transmission reliability. The analysis determined that no steady-state criteria were violated as a result of the interconnection. Stability Analysis Stability analysis evaluated the impact of the proposed project on transmission system performance for the light winter load level, as high energy exports and lower load levels present a worst-case model. Several wind dispatch scenarios were utilized during the stability analysis. The stability analysis identified the project’s impacts on the transmission system following several different disturbances and verified the project’s Low Voltage Ride-Through (LVRT) capability was in accordance with current FERC LVRT requirements. Stability analysis results showed that no transient stability criteria were violated as a result of the proposed interconnection. TOT 4A/4B Analysis The results of the TOT 4A/4B analysis performed in the Feasibility Study (FS) verified that there were no negative impacts to TOT4A and TOT4B as a result of interconnecting the proposed wind plant. A 300 MW reduction of the original project size as studied in the FS was not expected to increase negative impacts to the TOT 4A/4B paths; therefore the TOT analysis was not repeated for this study. Short Circuit Analysis Short circuit analysis was performed during the FS to assess the impact of the proposed project on the fault current levels and breaker duty in the area. The surrounding breakers were evaluated to determine if the additions to the transmission system created any breaker over-duty conditions. No adverse short circuit impacts were identified as a result of interconnecting the original 500 MW proposed project. The short circuit analysis was not repeated for the SIS. ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 2 Conclusion The interconnection System Impact Study identified no necessary upgrades to the local transmission system to accommodate the full 200 MW injection from the proposed wind project. Network facilities required to interconnect the project are a new 230 kV bay in the Pumpkin Buttes substation with an estimated cost of $2,000,000. Additional reactive equipment will be required to mitigate the charging effects of the wind park collector system, particularly under light load conditions with no wind generation output. Interconnection Service in and of itself does not convey any right to deliver electricity to any specific customer or Point of Delivery. Curtailment of the proposed interconnection project may be necessary under certain emergency operating conditions. ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 3 Table of Contents Background ............................................................................................................................... 6 1.1 Study Objective................................................................................................................... 6 1.2 Project Description ............................................................................................................. 6 1.3 Modeled Layout.................................................................................................................. 7 2 Study Area ................................................................................................................................. 8 2.1 Transmission System .......................................................................................................... 8 3 Base Case Development............................................................................................................ 8 3.1 Base Case Origin and Year................................................................................................. 8 3.2 Area Load ........................................................................................................................... 8 3.3 Planned Projects.................................................................................................................. 8 3.4 Analytical Tools.................................................................................................................. 9 4 Steady State Analysis Methodology ........................................................................................ 9 4.1 Steady State Analysis Methodology ................................................................................... 9 4.1.1 Voltage Limits ............................................................................................................ 9 4.1.2 Thermal Limits ......................................................................................................... 10 4.1.3 Solution Parameters .................................................................................................. 10 4.2 Case Naming Convention ................................................................................................. 10 4.3 Steady State Contingency List.......................................................................................... 11 4.4 Steady State Base Case Dispatch and Interface Conditions ............................................. 12 5 Steady State Analysis Results ................................................................................................ 12 5.1 Light Winter Pre-Wind Results ........................................................................................ 12 5.2 Light Winter Energy Resource Results ............................................................................ 12 5.3 Light Winter Network Resource Results .......................................................................... 12 5.4 Heavy Summer Pre-Wind Results .................................................................................... 12 5.5 Heavy Summer Energy Resource Results ........................................................................ 12 5.6 Heavy Summer Network Resource Results...................................................................... 12 6 Stability Analysis Methodology ............................................................................................. 12 6.1 Stability Analysis Methodology ....................................................................................... 13 6.1.1 Stability Performance Criteria .................................................................................. 13 6.1.2 Low Voltage Ride Through Criteria......................................................................... 13 6.2 Stability Base Case Dispatch and Interface Conditions.................................................... 13 6.3 Stability Fault Descriptions .............................................................................................. 13 7 Stability Analysis Results ....................................................................................................... 14 8 TOT 4A/4B Analysis............................................................................................................... 14 9 Short Circuit Analysis ............................................................................................................ 14 10 Conclusions.............................................................................................................................. 15 1 ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 4 Appendices APPENDIX A: Preliminary One Line Diagrams of Proposed Wind Farm...................................... 16 List of Tables Table 1: Proposed Project Generator Modeling Data......................................................................... 6 Table 2: Proposed Project Conductor Data......................................................................................... 6 Table 3: Proposed Project Equivalent Modeling Data........................................................................ 7 Table 4: Steady State Voltage Criteria ............................................................................................... 9 Table 5: Steady State Solution Parameters ....................................................................................... 10 Table 6: Prior Outage List ............................................................................................................... 11 Table 7: Contingency List................................................................................................................. 11 Table 8: Stability Analysis Scenarios ............................................................................................... 13 Table 9: Stability Analysis Prior Outages......................................................................................... 13 Table 10: Stability Analysis Fault Descriptions ............................................................................... 14 Table 11: Pumpkin Buttes 230 kV Interconnection Costs................................................................ 15 List of Figures Figure 1: Modeled Layout of Proposed Project.................................................................................. 7 Figure 2: Case Naming Convention.................................................................................................. 10 ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 5 1 Background 1.1 Study Objective The primary objective of the study was to determine whether the proposed interconnection had any adverse impacts on the reliability, stability or operating characteristics of the Bulk Electric System (BES). Comprehensive steadystate and “worst-case” stability performance was evaluated. 1.2 Project Description The proposed project consists of one hundred thirty-four (134) 1.5 MW GE wind turbine generators, producing up to 200 MW total. The project was studied as both a network resource and an energy resource, interconnected directly to the Pumpkin Buttes 230 kV substation. The Project as modeled consists of the following electrical components and construction activities: • Add a bay and necessary switchgear to the Pumpkin Buttes 230 kV substation. • Install two 230/34.5 kV transformers that will connect the 34.5 kV collector system feeders directly to a 230 kV bus, which will be located at the project’s substation. • Construct 134 wind turbine generators (WTGs) operating at 575 V nominal, each equipped with its own dedicated 575 V: 34.5 kV generator step-up transformer (GSU). • Construct two collector buses operating at 34.5 kV nominal; each bus consisting of approximately 67 GE 1.5 MW wind turbines. The collector buses will tie into one 34.5 kV main collector bus in the project’s 230 kV: 34.5 kV substation. 1.2.1 Technical Specifications Tables 1-3 list the technical specifications as provided by the interconnection customer. Table 1: Proposed Project Generator Modeling Data Proposed Project Generator Modeling Data Referenced From Low Side of GSU Power Factor Range Type Individual Unit MVA Rating MW Lagging Leading Doubly-Fed Induction Generator (DFIG) 1.67 1.5 0.90 0.95 Table 2: Proposed Project Conductor Data Proposed Project Transmission Line Data Description Type Base MVA R (u-Ohm/ft) X (u-Ohm/ft) B (uS/mi) 34.5 kV Collector System 500 MCM 100 0.00 0.0001 0.0001 ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 6 Table 3: Proposed Project Equivalent Modeling Data STEP-UP EQUIVALENT GEN PARAMETERS FEEDER PARAMETERS Feeder# Length (mi) R X B # of Turbines MVA P Qmax Qmin #1 - rated 75/100/125 MVA 1 1.0 0.024 0.027 0.004 17 28.4 25.5 8.3 -12.4 (x=0.1200 on 100 MVA Base) 2 2.0 0.048 0.053 0.009 16 26.7 24.0 7.8 -11.7 3 2.5 0.060 0.067 0.011 17 28.4 25.5 8.3 -12.4 4 2.0 0.048 0.053 -12.4 230/34.5 kV Xfmr 0.009 Transformer Total 17 28.4 25.5 8.3 67 111.9 100.5 32.7 -48.9 #2 - rated 75/100/125 MVA 6 4.5 0.090 0.100 0.017 17 28.4 25.5 8.3 -12.4 (x=0.1200 on 100 MVA Base) 7 3.8 0.132 0.146 0.024 17 28.4 25.5 8.3 -12.4 8 5.5 0.163 0.181 0.030 17 28.4 25.5 8.3 -12.4 9 6.8 0.192 0.213 -11.7 0.035 Transformer Total 16 26.7 24.0 7.8 67 111.9 100.5 32.7 -48.9 Project Total 134 223.8 101.0 65.4 -97.8 1.3 Modeled Layout The project was modeled using lumped equivalent machines as shown in Figure 1. The POI in Figure 1 is the Hartzog 230 kV substation. The Hartzog 230 kV bus as shown in Figure 1 is synonymous with the Pumpkin Buttes 230 kV bus. A detailed one-line diagram is included in Appendix A. Figure 1: Modeled Layout of Proposed Project ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 7 2 Study Area 2.1 Transmission System The study area consists of the northeast Wyoming bulk transmission system centered on Campbell County, Wyoming. The study area is bounded by TOT4B to the northwest, TOT4A to the southwest, Laramie River Station and Stegall to the southeast, and Rapid City to the east. 3 Base Case Development 3.1 Base Case Origin and Year The base cases originated from the Western Electricity Coordinating Council (WECC) Library as part of the 2007 Study Program. The base case for the 2011 heavy summer load scenario was the 11HS1B1P study case. The 2011 light load scenario started with the 2011LSP1SA1P study case. These base cases were selected primarily due to their recent approval dates with the assumption that the level of accuracy regarding system representation would be higher than that of an older base case. The seasonal cases used in the SIS were modified versions of the cases used for the FS. 3.2 Area Load 3.2.1 2011 Heavy Summer The 2011 heavy summer load case was created by updating BHP, CLF&P, and Basin Electric loads to their 2011 peak forecast values. Minor load additions were also included for better representation of the northeast Wyoming area. 3.2.2 2011 Light Winter The 2010 light winter load case was created by scaling BHP and CLF&P loads to 55% of 2011 peak summer forecast values, and Basin Electric loads to 75% of 2011 peak winter forecast values. Coal Bed Methane (CBM) loads were scaled to 100% of peak winter forecast values. As in the summer case, minor load additions were included. 3.3 Planned Projects Several planned projects exist that were deemed relevant to the study and were added to the WECC base cases. These additions are listed below. 3.3.1 Hughes Transmission Project The Hughes Transmission Project was included in all study cases. The project consists of two phases, the first of which is a new 230 kV transmission line extending from the existing Hughes 230 kV substation to the new Dry Fork 230 kV substation and on to the existing Carr Draw 230 kV substation. The second phase consists of a new 230 kV transmission line from the new Dry Fork 230 kV substation extending north and west to the new Tongue River 230 kV switching station and on to the existing PacifiCorp Sheridan 230 kV substation. 3.3.2 Wyodak-Dave Johnston Area 230 kV Line The project consists of two new 230 kV transmission lines. The first line terminates at the new Donkey Creek substation and the Pumpkin Buttes substation. The second line terminates at the Pumpkin Buttes substation and a yet to be determined point in the Dave Johnston area. For purposes of this study the second line was modeled as terminating at the Dave Johnston 230 kV substation. 3.3.3 Teckla Dynamic Voltage Support Two 16 MVAR dynamic reactive devices were modeled at Teckla 230 kV substation, one device on each tertiary winding of the existing 230/69 kV transformers. The existing 15 MVAR capacitors were modeled at their respective 69 kV bus. ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 8 3.3.4 Rapid City Dynamic Voltage Support A +100/-50 MVAR Static VAR Compensator was modeled on the Lange 230 kV bus. 3.3.5 Casper-Dave Johnston Transmission Project The DJ-Spence 230 kV line was looped into the Casper 230 kV substation. The resulting parallel DJ-Casper 230 kV lines were re-conductored to maintain TOT 4A/4B nomogram capabilities. 3.3.6 Dave Johnston Wind Two identical 99 MW wind generating projects were modeled at the Dave Johnston 230 kV bus per PaciCorp’s request. 3.3.7 300 MW Path ‘C’ Upgrade Various upgrades were made to the 138 kV lines between Populus and Terminal substations to increase the transfer capability from Wyoming/Idaho to Utah by up to 300 MW. 3.3.8 Threemile Knoll 345 kV Project The Bridger-Goshen 345 kV line was looped into a new Threemile Knoll 345/138 kV substation. Project includes various 115 kV line additions. Should any one of the projects listed above not be complete prior to the proposed project in-service date, the Interconnection project may be curtailed due to transmission prior outages or other emergency conditions. These curtailments and/or operating restrictions, if needed, will be developed and identified through operational studies as required. 3.4 Analytical Tools Power flow and dynamic analyses were performed using PSS/E load flow and dynamic simulation software, version 30.3.1. 4 Steady State Analysis Methodology 4.1 Steady State Analysis Methodology The proposed project was evaluated at 2011 peak summer and light winter load levels to determine if it caused any significant adverse impact to the reliability and operating characteristics of the WECC bulk transmission system and, more specifically the CUS transmission system. Steady state voltage and thermal analyses examined system performance without the proposed project in order to establish a baseline for comparison. Performance was reevaluated with the proposed project in-service and compared to the baseline performance to determine the impact of the project on area transmission reliability. The criteria described below are consistent with the WECC Minimum Operating Reliability Criteria and Colorado Coordinated Planning Group’s Voltage Coordination Guide. 4.1.1 Voltage Limits Table 4 identifies the voltage criteria used in or around the primary study area for the steady state voltage assessment. Pre-existing voltage violations outside the localized study area were ignored during the evaluation of the proposed project’s impacts. Table 4: Steady State Voltage Criteria Applicable Control Area Voltage Class PACE, WAPA-RMR 69 kV and above Acceptable Voltage Range Pre-Contingency Post-Contingency (normal conditions) (emergency conditions) 0.95 to 1.05 p.u. 0.90 to 1.10 p.u. ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 9 4.1.2 Thermal Limits WECC member utilities follow a planning philosophy whereby normal thermal ratings shall not be violated under system intact conditions, and the applicable emergency rating shall not be exceeded under contingency conditions. It should be noted that the emergency rating for all monitored PacifiCorp 230 kV transmission lines and transformers is 123% of the continuous thermal rating. This emergency rating is applied to all postcontingency scenarios. 4.1.3 Solution Parameters The steady state analysis was performed with pre-contingency solution parameters that allowed adjustment of load tap-changing (LTC) transformers, static VAR devices including switched shunt capacitors and reactors, and DC taps. Post-contingency solution parameters only allowed adjustment of DC taps. Area interchange control was disabled and generator VAR limits were applied immediately for all solutions. The solution method implemented for all cases was a fixed-slope decoupled Newton solution. To maintain consistency with the 1990 TOT4A/4B study methodology, fixed capacitors in the TOT4A area were manually switched in and out of service as necessary to help meet the performance criteria. Table 5: Steady State Solution Parameters Case Area Interchange Transformer LTCs Phase Shifters Static VAR Devices DC Taps Pre-Contingency Disabled Stepping Disabled Stepping (discrete) Enabled Post-Contingency Disabled Disabled Disabled Disabled Enabled 4.2 Case Naming Convention Study case designations were formatted as shown in Figure 2: Resource Type_ RCDC Tie Schedule_ Network Gen Offset by Wind_ Prior Outage Wind Resource Type: A B Energy Resource (Dispatched to Currant Creek) Network Resource RCDC Tie Schedule: 1 2 200 MW EÆW Blocked (0 MW) Generation Offset: A B No Offset 200 MW Network Resource Reduction Prior Outage: See Table 6 Figure 2: Case Naming Convention ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 10 Table 6: Prior Outage List Steady State Pre-Wind Prior Outage List 1 SYSTEM INTACT 18 P. BUTTES -DJ 35 WYODAK UNIT 2 GOOSE CRK-SHERIDAN 19 TECKLA-ANTELOPE MR 36 WYGEN3 UNIT 3 BUFFALO-SHERIDAN 20 RENO-TECKLA 37 DRYFORK UNIT 4 BUFFALO-KAYCEE 21 DONKEY CRK-RENO 38 LRS UNIT 5 CASPER-CLAIMJPR 22 DONKEY CRK- P. BUTTES 39 DJ UNIT 6 CASPER-DJ 23 WYODAK-DONKEY CRK 40 CASPER XFMR 7 SHERIDAN-T. RIVER 24 WYODAK-OSAGE 41 DJ XFMR 8 T. RIVER-ARVADA 25 WYODAK-HUGHES 42 WYODAK XFMR 2 9 ARVADA-DRYFORK 26 HUGHES-LOOKOUT 43 WESTHILL XFMR 10 DRYFORK-CARR DRAW RB 27 YELLOW CREEK-OSAGE 44 OSAGE XFMR 11 DRYFORK-HUGHES RB 28 LOOKOUT-YELLOW CREEK 45 LANGE XFMR 2 12 BUFFALO-CARR DRAW 29 OSAGE-WESTHILL 46 LOOKOUT XFMR 2 13 WYODAK-CARR DRAW 30 LANGE-LOOKOUT 47 YELLOWCREEK XFMR 14 CARR DRAW-BARBER CREEK 31 LANGE-SOUTH RAPID 48 SOUTH RAPID XFMR 15 BARBER CREEK- P. BUTTES 32 SOUTH RAPID-WESTHILL 49 16 P. BUTTES –PBWIND 33 RCDCW-SOUTH RAPID 50 17 P. BUTTES -TECKLA *RB indicates Dryfork runback WESTHILL-STEGALL 34 51 *MR indicates Barber Creek and Hartzog DG Must Run (Heavy Summer loads only) 4.3 Steady State Contingency List A list of forced outages simulated for the various steady state scenarios is shown in Table 7. Table 7: Contingency List Pre-Wind Forced Outage List 1 ATLANTIC-WYOPO-1 26 RIVERTON-WYOPO-1 51 TONGRIVR-DRYFORK-1 2 BADWATER-SPENCE-1 27 SHERIDAN-TONGRIVR-1 52 CARR DRA- P. BUTTES 3 BADWATER-THERMOPL-1 28 WYODAK-OSAGE-1 53 TECKLA-DJ 4 BUFFALO-CARR DRA-1 29 WYODAK-HUGHES-1 54 WYODAK UNIT 5 BUFFALO-KAYCEE-1 30 WYODAK-DONKYCRK-1 55 WYGEN3 UNIT 6 BUFFALO-SHERIDAN-1 31 YELOWTLP-YELLOWBR-1 56 DRYFORK UNIT 7 CARR DRA-WYODAK-1 32 LOVELL-THERM 115 57 LRS UNIT 8 CARR DRA-DRYFORK-1 33 BGEORGE-LOVELL-1 58 DJ3 UNIT 9 CASPERPP-DAVEJOHN-1 34 BGEORGE-THERM-1 59 CASPER XFMR 10 CASPERPP-CLAIMJPR-1 35 WESTHILL-OSAGE-1 60 DJ XFMR 11 CASPERPP-RIVERTON-1 36 WESTHILL-STEGALL-1 61 WYODAK XFMR 1 12 CASPERPP-CASPERLM-1 37 WESTHILL-RCSOUTH1-1 62 WESTHILL XFMR 13 CASPER-SPENCE-1 38 LOVELL-YELLOWBR-1 63 OSAGE XFMR 14 DAVEJOHN-DIFICULT-1 39 OSAGE-YELOWCRK-1 64 LANGE XFMR 1 15 DAVEJOHN-LAR.RIVR-1 40 LANGE-LOOKOUT1-1 65 LOOKOUT XFMR 1 16 DAVEJOHN-STEGALL-1 41 LANGE-RCSOUTH1-1 66 YELLOWCREEK XFMR 17 DAVEJOHN-P. BUTTES-1 42 RENO-TEKLA-1 67 SNOWY RANGE XFMR 1 18 FRANNIE-GARLAND-1 43 RENO-DONKYCRK-1 68 RCSOUTH XFMR 1 19 FRANNIE-YELOWTLP-1 44 LOOKOUT1-YELOWCRK-1 69 HUGHES XFMR 20 GOOSE CK-SHERIDAN-1 45 LOOKOUT1-HUGHES-1 70 21 GOOSE CK-YELOWTLP-1 46 TEKLA- P. BUTTES -1 71 22 GRASS CK-OREBASIN-1 47 WYODAK-HUGHES-69 72 23 GRASS CK-THERMOPL-1 48 HUGHES-DRYFORK-1 73 24 MUSTANG-SPENCE-1 49 RCSOUTH1-RCDC W-1 74 25 RIVERTON-THERMOPL-1 50 DONKYCRK- P. BUTTES -1 75 ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 11 4.4 Steady State Base Case Dispatch and Interface Conditions The steady state analysis looked at the addition of the project as an Energy Resource (ER) and a Network Resource (NR). The ER scenario was dispatched against Currant Creek generation in Utah, with no changes made to generation on the CUS. The NR scenarios dispatched the proposed project against network generation. First, the RCDC Tie was blocked in scenarios where it was on-line, and on-line gas generation was taken off-line. The remainder of the proposed project’s generation was dispatched against network base load generation on a pro-rata basis. Refer to Appendix B for a summary of generation dispatch and transmission line flows for the various systemintact scenarios described in 4.2. 5 Steady State Analysis Results All violations that could be mitigated through the application of existing BHP operating procedures were omitted. Also, high voltage violations due to improperly configured capacitors were not included in the results. 5.1 Light Winter Pre-Wind Results There were no criteria violations during the light winter pre-wind steady state analysis. 5.2 Light Winter Energy Resource Results The Alcova-CasperLM 115 kV line became overloaded for several prior and forced outage combinations in the light winter Energy Resource scenarios. However, the Alcova-CasperLM 115 kV line rating is currently planned to be upgraded by WAPA prior to the Interconnection Customers in-service date. 5.3 Light Winter Network Resource Results There were no criteria violations for the light winter network resource steady state analysis due to the interconnection of the proposed project. 5.4 Heavy Summer Pre-Wind Results The steady state analysis for the 2011 heavy summer pre-wind case revealed no voltage criteria violations. Thermal criteria violations on the Lovell-Nahne Jensen 115 kV line were experienced following the prior outage of a Wyodak, Dryfork, LRS, or Dave Johnston generator and the forced outage of the PACE-WAPA 230 kV tie line at Yellowtail. This overload occurred only for cases with the RCDC Tie off-line. 5.5 Heavy Summer Energy Resource Results There were no voltage criteria violations as a result of the addition of the proposed project. 5.6 Heavy Summer Network Resource Results The heavy summer network resource analysis revealed results similar to those described in 5.4. There was a 0.5% increase in the overload for the LRS generator prior outage case, but this difference was considered negligible. A sensitivity analysis was performed on the light winter study case with the proposed wind plant off-line in order to observe the charging effect of the proposed interconnection’s collector system. The collector system as modeled supplied approximately 15 MVARs at the POI. The model as depicted in Appendix A contained a slightly different collector system layout than the model used for this study. This alternate representation was found to supply approximately 20 MVARs at the POI. The risk of an over-voltage condition may arise when the local transmission system is lightly loaded and the wind turbines are not generating. 6 Stability Analysis Methodology ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 12 6.1 Stability Analysis Methodology The primary objective of the stability analysis is to analyze the impact of the project on transient stability performance of the bulk electric system for various system disturbances. Stability simulations were conducted with and without the proposed interconnection project for the 2011 light winter load level scenario to confirm performance with respect to applicable criteria. 6.1.1 Stability Performance Criteria The disturbance performance criteria for this study requires that the transient low voltage swing shall not be lower than 0.70 p.u. at any load or non-load bus and the system shall exhibit positive damping following any contingency. Table W-1 of the NERC/WECC Planning Standards states that for a NERC Category B contingency, the frequency at a load bus must not dip below 59.6 HZ for more than 6 cycles, but this requirement was applied to all contingencies to simplify the presentation of the results. 6.1.2 Low Voltage Ride Through Criteria The current WECC Low Voltage Ride Through (LVRT) Standard requires generators to remain inservice for 3-phase faults with normal clearing (4-9 cycles) and single line-to-ground faults with delayed clearing that result in a GSU high side voltage of 0.15 per unit or greater. The FERC LVRT Standard, however, requires generation to remain on-line for GSU high side voltages of 0 per unit for similar faults. The more stringent FERC standard was applied as the LVRT requirement for this study. 6.2 Stability Base Case Dispatch and Interface Conditions The stability base case dispatch and interface conditions were a subset of the steady state base case conditions listed in Section 4.2. Dynamic simulations were run for the following light winter load scenarios: Table 8: Stability Analysis Scenarios Scenario Name A1AX A2AX B2AX B2BX Scenario Description Energy Resource, RCDC @ 200MW EÆW, No Network Generation Offset Energy Resource, RCDC Blocked, No Network Generation Offset Network Resource, RCDC Blocked, No Network Generation Offset Network Resource, RCDC Blocked, 200 MW Network Generation Offset The ‘X’ in the ‘Scenario Name’ column in Table 8 refers to the prior outage simulated for each scenario. A list of the prior outages simulated for each scenario in the Stability Analysis is shown in Table 9. Table 9: Stability Analysis Prior Outages # 1 2 3 4 5 6 7 8 9 10 Prior Outage System Intact Goose Creek-Sheridan 230 Arvada-Dryfork 230 Dryfork-Carr Draw 230 RB Dryfork-Hughes 230 RB Buffalo-Carr Draw 230 Wyodak-Carr Draw 230 Carr Draw-Barber Creek 230 Barber Creek-Pumpkin Buttes 230 Pumpkin Buttes-Teckla 230 # 11 12 13 14 15 16 17 18 19 20 Prior Outage Pumpkin Buttes-Dave Johnston 230 Teckla-Antelope Donkey Creek-Reno 230 Donkey Creek-Pumpkin Buttes 230 Wyodak-Donkey Creek 230 Wyodak-Osage 230 Wyodak-Hughes 230 Westhill-Stegall 230 Wyodak Unit Dryfork Unit * RB indicates Dryfork runback 6.3 Stability Fault Descriptions In addition to a disturbance-free steady state simulation, each dispatch scenario for the 2011 light winter load case was simulated with various faults applied. Table 10 lists the faults and the load cases in which they were applied. ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 13 Table 10: Stability Analysis Fault Descriptions Fault Description 3 PH Bus Fault Cleared Element Wyodak 230 Wyodak-Carr Draw 230 line Wyodak 230 Wyodak-Donkey Crk 230 line Wyodak 230 Wyodak-Hughes 230 line Wyodak 230 Wyodak-Osage 230 line Dryfork 230 Dryfork-Hughes 230 line Dryfork 230 Dryfork-Carr Draw 230 line Dryfork 230 Dryfork-Tongue River 230 line Donkey Crk 230 Donkey Creek-Reno 230 line P. Buttes 230 kV P. Buttes-Carr Draw 230 line Donkey Crk 230 P. Buttes-Donkey Crk 230 line P. Buttes 230 P. Buttes-Donkey Crk 230 line P. Buttes 230 P. Buttes-Teckla 230 line P. Buttes 230 P. Buttes-DJ 230 line Westhill 230 Westhill-Stegall 230 line Teckla 230 Teckla-DJ 230 line 7 Fault Type Fault Duration 3Φ 3Φ 3Φ 3Φ 3Φ 3Φ 3Φ 3Φ 3Φ 3Φ 3Φ 3Φ 3Φ 3Φ 3Φ 4.25 cycles 4.25 cycles 4.25 cycles 4.25 cycles 4.25 cycles 4.25 cycles 4.25 cycles 4.25 cycles 4.25 cycles 3.50 cycles 3.50 cycles 4.25 cycles 4.25 cycles 4.25 cycles 4.25 cycles Stability Analysis Results There were no stability performance criteria violations observed on the transmission system as a result of the interconnection of the proposed project. All post-contingent voltage dips remained well above the established limit and rotor angle oscillations were positively damped. Additionally, there were no frequency excursions below the 59.6 HZ limit for a period of 6 cycles or more at any of the monitored buses. The faults simulated at the Pumpkin Buttes 230 kV bus confirmed the stated LVRT capability of the GE 1.5 MW machines and exhibited performance that met FERC LVRT requirements. 8 TOT 4A/4B Analysis The TOT 4A/4B analysis performed as a part of the Feasibility Study for the 500 MW project exhibited no adverse impacts on the paths. The size of the project has since been reduced to 200 MW and the impacts are assumed to be reduced as well. Therefore the TOT 4A/4B analysis was not performed as part of the SIS. Refer to the ‘Pumpkin Buttes 500 MW Wind Project Interconnection Feasibility Study’ report for more information. 9 Short Circuit Analysis The short circuit analysis performed as a part of the Feasibility Study for the 500 MW project exhibited no adverse impacts on the local transmission system. The size of the project has since been reduced to 200 MW and the impacts are assumed to be reduced as well. Therefore the short circuit analysis was not performed as part of the SIS. Refer to the ‘Pumpkin Buttes 500 MW Wind Project Interconnection Feasibility Study’ report for more information. ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 14 10 Conclusions This report describes the power flow and stability studies performed to determine the impacts of interconnecting a new 200 MW wind plant at the Pumpkin Buttes 230 kV substation in northeast Wyoming. The interconnection project as studied is comprised of one hundred thirty-four (134) GE 1.5 MW wind turbine generators. There were no negative impacts to the transmission system as a result of the proposed interconnection. Facilities required for interconnection to the Pumpkin Buttes 230 kV substation are listed in Table 11. Table 11: Pumpkin Buttes 230 kV Interconnection Costs Network Upgrades Required for Interconnection Pumpkin Buttes Line Terminal Expand the Pumpkin Buttes substation to accommodate the new interconnection of the Project ESTIMATED TOTAL COST ESTIMATED TIME FRAME $2,000,000 $2,000,000 15 Months The thermal capacity on the Alcova-CasperLM 115 kV line would need to be increased to at least 109 MVA. The upgrade would require a CT tap ratio increase at the Casper terminal, which is currently planned as part of WAPA’s TOT 3 Expansion project. No additional upgrades to the existing transmission system were identified for the proposed interconnection. The possibility of increased system voltages may exist due to collector system charging when the transmission system is lightly loaded and the proposed wind interconnection is not generating. It is the responsibility of the customer to compensate for any effects of charging that the wind park collector system may have on the transmission system. Namely, the installation of reactive equipment will be required to mitigate the potential impacts of the collector system charging. The equipment shall be under the control of the Transmission System Operator. All cost estimates include labor and materials for network infrastructure only, and do not reflect any additional ancillary services that may be necessary. All costs associated with radial transmission and/or equipment from the point of interconnection (POI) to the generation facility would be the sole responsibility of the customer. Preliminary cost estimates are subject to change pending a review of detailed design information in the Facility Study, providing the customer elects to proceed with the project. Interconnection Service in and of itself does not convey any right to deliver electricity to any specific customer or Point of Delivery. Curtailment of the proposed interconnection project may be necessary under certain emergency operating conditions. ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 15 APPENDIX A PRELIMINARY ONE-LINE DIAGRAMS OF PROPOSED WIND FARM ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 16 ONE-LINE REPRESENTATION OF PROPOSED PROJECT ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 17 PSS/E EQUIVALENT ONE-LINE REPRESENTATION ____________________________________________________________________________________________________________ BHBE-G7 Black Hills Power Interconnection System Impact Study Report August 21, 2008 18