RFQ for products to be deployed on Commercial Advanced Lighting Control Demonstration Projects – Responses to Questions Updated 11/25/2014 Question: Will exterior lighting controls be accepted and/or demonstrated? Response: All of the ten demonstration projects as part of this RFQ will be interior demonstrations. Exterior demonstrations will be considered in the future, but manufacturers should not submit products/proposals for exterior demonstrations at this time. Question: Can a manufacturer propose multiple solutions or products? Response: Yes, manufacturers may propose multiple solutions or products. However, each proposed solution requires a separate proposal. Question: Question 13 of the Manufacturer Questionnaire states “What is the topology of the system (Node-to-node, gateway-to-node)? A processor or controller are not gateways. Is the question whether it is hierarchical or whether it has a flat topology? Can NEEP elaborate on the intent of the question? Response: “gateway-to-node” is incorrect terminology. Question 13 should read: “What is the network topology of the system (Bus, Ring, Star, Mesh, Partial Mesh, Hybrid, etc.)? A revised Manufacturer Questionnaire has been posted to the NEEP website. Question: Question 16 of the Manufacturer Questionnaire states “What is your product’s method of data encryption?” What part of the communication schema are you talking about? Response: Manufacturers should respond with any and all forms of encryption their product uses for any or all parts of the communication schema. Question: Question 19 asks about estimated initial costs for “equipment, installation, and commissioning” in new construction and retrofit projects, in terms of $/ft2. Does this equipment cover all products like fixtures, gateways, and Ethernet wiring? Can NEEP confirm the following definitions? Northeast Energy Efficiency Partnerships 91 Hartwell Avenue Lexington, MA 02421 P: 781.860.9177 www.neep.org PAGE 2 OF 5 Equipment rate = (all costs of physical material someone must purchase) / (square feet of area) Installation rate = (all labor costs to install equipment above) / (square feet of area) Commissioning rate = (price for an expert user to commission the advanced lighting control system to a turnkey state) / (square feet of area) Response: NEEP is only looking for the costs associated with the advanced lighting controls including gateways and Ethernet wiring but excluding the cost of the fixture or light source. For manufacturers that sell their controls only as embedded systems within their light fixtures, they should estimate the cost of the lighting controls alone with the fixture cost removed when developing their equipment and installation costs. The definitions provided for Equipment and Installation rate in the above question are correct. The Commissioning rate should be the cost associated with your most typical and/or recommended method for commissioning your specific system, whether it is typically done by an installing contractor, by a 3rd party commissioning agent, by the manufacturer, or other alternatives. Your response to Question 19 should align with your response to Question 22. NEEP provides the following clarifying definition for Commissioning rate: Commissioning rate = (average or range of price for installing contractor or 3rd Party or Manufacturer or other recommended party to commission system to fully commissioned, turnkey state) / (square feet of area) Question: Question 23 of Manufacturer Questionnaire – can NEEP define “Lighting-as-a-Service (LaaS)? Response: Lighting-as-a-Service refers to a type of business model that is generally new to the lighting industry where the manufacturer (or associated party) provides services beyond the sale of lighting equipment to an end-user. These services may include operation, maintenance, leasing, and/or performance of the lighting system or even services to support end-user business processes based on data that the lighting system collects. The manufacturer is then paid contractually based on these services or the performance of these services, rather than the traditional model of being paid based on equipment sales. NEEP is particularly interested in this business model in the context of Advanced Lighting Controls because it can potentially reduce or eliminate initial cost barriers, provide more qualified support to install/operate/maintain Advanced Lighting Control systems, as well as drive more sustainable manufacturing processes by creating an incentive for manufacturers to re-use and re-cycle products since they may maintain ownership through the full lifecycle of the product. Northeast Energy Efficiency Partnerships 91 Hartwell Avenue Lexington, MA 02421 P: 781.860.9177 www.neep.org PAGE 3 OF 5 Question: RFQ Page 7 of 10 – Installation and Commissioning Paragraphs. The outcome and price of a project depend on the level of expertise of the installer. What steps will NEEP take to ensure that all manufacturers responding are using the same level of installer? Response: NEEP cannot ensure that all demonstration projects will use the same level of installer. However, NEEP will ensure that the responses the manufacturer provides to Questions 24, 33, 34 of the Manufacturer Questionnaire are incorporated into each demonstration project for which that manufacturer’s product will be installed. This may include, for example, pre-bid training and/or pre-wire training of the contractor. Further, NEEP will incorporate requirements that the contractor demonstrate knowledge and experience in installing Advanced Lighting Controls into the process NEEP uses to procure installation contractors. Question: Re: Part C, Item 4 – High Costs. High Costs are defined in the RFQ to include material, installation (labor) and commissioning. As we have learned over the years, the installation cost can range significantly based on location, Union Labor vs. Non-Union Labor, and installation time of day … off-hours vs. normal hours. What assumptions for installation shall be used in the RFQ response? What City, Union or Non-Union, Off-Hours or Normal Hours? Response: Question 19 of the Manufacturer Questionnaire calls for “either a range or average cost”. Manufacturers can respond with a single range or average cost to include all potential conditions (location, union vs. non-union, off-hours vs. normal hours), or they may provide separate average or range of costs for union vs non-union or off-hours vs. normal hours, as long as assumptions for each are provided. Question: How do you want “High Costs” represented in our response? The response will not have a particular project example to quite the “High Costs”, so we can represent it in different ways: a. On a per fixture basis b. On a per square foot basis c. On a per 1000 fixtures basis Response: Question 19 of the Manufacturer Questionnaire provides information as to how the cost information to be provided. Question: Northeast Energy Efficiency Partnerships 91 Hartwell Avenue Lexington, MA 02421 P: 781.860.9177 www.neep.org PAGE 4 OF 5 What are the maximum page limits of the proposal? Response: There are no page limits for the proposal. However proposals that are not written concisely may receive lower scores in the area of “Proposal quality”. Question: Will multiple submissions be required to support multiple projects? Response: No. Multiple submissions are only required if the manufacturer is proposing multiple solutions or product types to be demonstrated. Question: Should products in development, not currently commercialized, be submitted for these projects? Response: Products must be fully commercialized and available by January 15, 2015. Products that are not commercialized by this time will be removed from consideration. It should also be noted that manufacturers that submit a proposal for a product that is not yet commercialized without track record of successful installations may receive lower scores in the area of “demonstrated… experience of company to support demonstration projects…” Question: As there are retrofits involved, will 3rd party integration be required (example: shade control, Building Management System Integration)? Response: 3rd Party integration is not specifically required, however, manufacturers should provide information on any capabilities of their system for 3rd Party integration in their response. When it comes time to implement the demonstration projects, NEEP is utilizing a process that first selects technologies, and then sites. Through this process, NEEP will ensure that the requirements of selected sites match the capabilities of the selected product. Question: In the RFQ you mention how manufacturers are addressing security. We would like to know if there are specific security/government certifications required for these projects. For instance for US projects, the system needs to get approved by GSA. Response: Northeast Energy Efficiency Partnerships 91 Hartwell Avenue Lexington, MA 02421 P: 781.860.9177 www.neep.org PAGE 5 OF 5 There are no specific security/government certifications required, however, manufacturers should provide information on any security/government certifications their product has. Further as NEEP implements the process to select the demonstration sites, NEEP will ensure the requirements of those sites match the capabilities of the selected product. Northeast Energy Efficiency Partnerships 91 Hartwell Avenue Lexington, MA 02421 P: 781.860.9177 www.neep.org